﻿Fiscal Year 1992
Annual Report 
Fiscal Year 1992 
of the Secretary of the Army 
on Civil Works Activities 
(1 October 1991 - 30 September 1992) 
Volume II 
-L I 
I

ITEM 
APPROPRIATIONS ($ MILLIONS) 
Navigation 
Flood Control Total 
Flood Control 
Mississippi River & Tributaries
1 
Multipurpose including power 
Beach Erosion Control 
Total New Work
s 
Other Work' 
TOTAL 
NAVIGATION (Calendar Year)' 
Ton(Miles of Commerce (Millions) 
Foreign, Coastal Ports 
Foreign, Grat Lakes Ports 
Domestic, Coastal (Intraterritory not compiled) 
Domestic, Great Lakes 
Domestic, Inland 
Domestic, Local 
TOTAL 
Tons of Commerce (Millions) 
Foreign, Coastal Ports 
Foreign, Grat Lakes Ports 
Domestic, Coastal and Intraterritory 
Domestic, Great Lakes 
Domestic, Inland 
Domestic, Local 
TOTAL 
FLOOD DAMAGES PREVENTED ($ Billion) 
FLOOD DAMAGES SUFFERED ($ Billion) 
POWER 
Installed (Cumulative in millions of kw) 
Generated (Billions of kwh) 
RESERVOIR Storate (Millions of acre feet) 
All Purpose 
Flood Control (Maximum) 
Water Supply 
Irrigatirn 
PUBLIC ATTENDANCE AT RESERVOIRS 
tecreation Days of Use (Millions) 
Visitor Days (Millions)' 
FUNDING 
General Investigation 
Construction General 
Operations & Maintenance, General 
Regulatory Program 
Flood Control Mississippi River & Tribs. 
General Expenses 
Flood Control & Coastal Emergencies 
Revolving Fund 
Permanent Appropriation 
TOTAL 
1992 STATISTICAL HIGHLIGHTS 
1992 1991 1990 1989 1988 1987 1986 1985 1984 1983 
461 437 439 519 512 443 299 304.0 257.0 577.0 
914 901 879 856 840 787 673 676 647 832 
(229) (221) (220) (222) (205) (206) (227) (225) (203) (291) 
70 62 60 73 73 69 93 112 171 221 
56 66 43 27 27 23 17 12 25 5 
1,501 1,466 1,421 1,475 1,452 1,221 1,082 1,104 1,127 1,685 
2,167 1,848 1,776 1,770 1,826 1,813 1,658 1,797 1,567 1,734 
3,668 3,314 3,197 3,245 3,278 3,135 2,730 2,901 2,668 3,419 
72,916.5* 68,563.4 56,208.2 50,985.0 47,274.2 44,769.3 46,508.8 45,286.7 
25,153.5 27,118.9 24,448.4 22,003.3 24,235.2 27,171.9 32,249.4 24,309.4 
479,099.3 483,888.6 561,594.9 586,818.7 580,888.7 610,976.5 593,923.1 649,749.4 
59,329.0 58,307.6 58,159.4 50,076.4 43,198.2 48,184.0 49,784.4 43,088.2 
293,330.3 272,157.4 269,035.7 257,336.4 248,116.9 232,707.5 242,855.4 225,628.2 
1,087.0 1,196.3 1,183.9 1,197.2 1,102.0 1,157.1 1,099.7 
930,915.6 911,232.2 970,685.0 968,403.7 944,910.5 964,911.2 966,478.2 989,161.6 
991.1 983.1 923.7 845.1 791.4 723.0 744.5 702.7 
50.5 54.8 52.5 45.9 45.7 51.3 58.8 48.4 
303.1 307.2 330.3 328.2 312.0 313.2 311.1 312.8 
110.2 109.1 109.7 96.5 87.4 92.0 98.0 83.5 
622.6 606.0 588.1 569.8 560.5 534.7 542.5 487.1 
86.4 80.2 83.7 82.0 77.4 74.2 81.1 73.2 
2,163.9 2,140.4 2,088.0 1,874.4 1,788.4 1,836.0 1,707.7 
8.1 17.5 17.6 8.3 2.1 5.2 27.3 10.8 16.8 23.5 
0.8 1.7 1.6 1.1 0.2 1.4 6.0 0.5 3.5 3.7 
20.7 20.7 20.0 20.7 20.7 20.7 20.3 20.1' 19.7' 20.1' 
68.2 83.9 81.6 78.5 69.6 74.0 80.7 88.3 91.2 88.2 
273.6 273.6 272.1 270.6 
123.3 123.3 ,123.0 123.0 
9.5 9.5 9.2 9.2 
506 502 482 480 
203 192 190 191 191 181 
194,427 146,433 129,251 142,405 138,767 136,287 128,272 
1,284,142 1,143,073 1,083,811 1,184,735 1,200,175 1,152,150 919,345 
1,538,329 1,450,656 1,398,219 1,370,714 1,421,733 1,389,846 1,319,973 
86,000 71,099 68,455 63,752 55,262 
356,437 344,602 330,296 332,550 317,704 310,797 314,760 
141,500 126,598 141,997 120,000 115,000 115,000 107,000 
55,000 20,000 20,000 20,000 20,000 10,000 48,976 
0 0 9,860 0 0 12,000 7,000 
12,298 11,801 14,700 9,000 9,000 0 8,000 
3,668,133 3,314,262 3,196,589 3,245,261 3,278,091 3,135,080 2,830,050 
' Included in Flood Control Total 
s Advance engineering and design and construction. (Including major rehabilitation projects.) Savings and slippages applied to projects. 
* Operation and maintenance, surveys, administrative and misc. programs and activities. 
' For further information on waterborne commerce, see Waterborne Commerce of the United States, published annually. It may be obtained by writing Commander, U. S. Army 
Engineer District, New Orleans, ATTN: CELMN-ED-S, Box 60267, New Orleans, Louisiana 70160-0267 
' Includes New Melones and Spettishman, built by the Corps and operated by others 
' All Federal agencies changed to "Visitor Days" at the direction of OMIB

DEPARTMENT OF THE ARMY 
OFFICE OF THE ASSISTANT SECRETARY 
WASHINGTON, DC 20310-0108 
REPLY TO 
ATTENTION OF 
Honorable Albert Gore 
President of the Senate 
Washington, D. C. 20510-0010 
Dear Mr. President: 
I am submitting Volume II of the Annual Report on 
Civil Works Activities for Fiscal Year 1992 in accordance 
with Section 8 of the Rivers and Harbors Act of 1988 and 
Section 925(b) of the Water Resources Development Act of 
1986.
This volume of field reports contains narrative 
summaries and statistics on water resources development 
projects of the Army Corps of Engineers where there has 
been activity between October 1, 1991 and September 30, 
1992. 
Sincerely, 
G. Edward Dickey 
Acting Assistant Secretary of the Army 
(Civil Works) 
HECSA TECHIrC M~. I

DEPARTMENT OF THE ARMY 
OFFICE OF THE ASSISTANT SECRETARY 
WASHINGTON, DC 20310-0108 
REPLY TO 
ATTENTION OF 
Honorable Thomas S. Foley 
Speaker of the House 
of Representatives 
Washington, D. C. 20515-6501 
Dear Mr. Speaker: 
I am submitting Volume II of the Annual Report on 
Civil Works Activities for Fiscal Year 1992 in accordance 
with Section 8 of the Rivers and Harbors Act of 1988 and 
Section 925(b) of the Water Resources Development Act of 
1986.
This volume of field reports contains narrative 
summaries and statistics on water resources development 
projects of the Army Corps of Engineers where there has 
been activity between October 1, 1991 and September 30, 
1992. 
Sincerely, 
G. Edward Dickey 
Acting Assistant Secretary of the Army 
(Civil Works)

CONTENTS 
New England Division .................................................................. 1-1 
North Atlantic Division: 
New York, NY, District ....................................... 2-1 
Philadelphia, PA, District .............................................................. 3-1 
Baltimore, MD, District ................................................................ 4-1 
Norfolk, VA, District .................................................................. 5-1 
South Atlantic Division: 
Wilmington, NC, District .......................................................... 6-1 
Charleston, SC, District .............................................................. 7-1 
Savannah, GA, District ............................................................. 8-1 
Jacksonville, FL, District ....................................... . 9-1 
Mobile, AL, District ................................................................... 10-1 
Lower Mississippi Valley Division: 
New Orleans, LA, District ................ ........................................ 11-1 
Vicksburg, MS, District ............................................................... 12-1 
Memphis, TN, District ................... ........................................... 13-1 
St. Louis, MO, District ................................................................ 14-1 
Ohio River Division: 
Nashville, TN, District ................................................................ 15-1 
Louisville, KY, District ................................................................ 16-1 
Huntington, WV, District ........................................ 17-1 
Pittsburgh, PA, District .................................. .................... 18-1 
O hio R iver ....................................................................... ....... 19-1 
North Central Division 
Buffalo, NY, District ................................................................ 20-1 
Detroit, MI, District .................................................................. 21-1 
Chicago, IL, District ............................................................... 22-1 
Rock Island, IL, District ...................................... 23-1 
St. Paul, MN, District ................................................................ 24-1 
Mississippi River between Missouri River and Minneapolis, MN................. 25-1 
Missouri River Division: 
Omaha, NE, District .................................................................... 26-1 
Kansas City, MO, District ............................................................ 27-1 
Southwestern Division: 
Little Rock, AR, District .............................................................. 28-1 
Tulsa, OK, District ................................... ................................. 29-1 
Fort Worth, TX, District ......................................... 30-1 
Galveston, TX, District ........................................................... 31-1 
Albuquerque, NM, District .......................................................... 32-1

South Pacific Division: 
Los Angeles, CA District............................................................... 33-1 
San Francisco, CA, District .......................................................... 34-1 
Sacramento, CA District .............................................................. 35-1 
California Debris Commission ..................................................... 35-1A 
Pacific Ocean Division ................................................................. 36-1 
North Pacific Division: 
Portland, OR, D istrict ................................................................ 37-1 
Seattle, W A , D istrict ................................................................... 38-1 
Walla Walla, WA, District ........................................................... 39-1 
A laska, AK , D istrict ................................................................... 40-1 
Board of Engineers for Rivers and Haibors............................................... 41-1 
Mississippi River Commission ............................................................ 42-1 
Construction Engineering Research Laboratory ......................................... 43-1 
Cold Regions Research & Engineering Laboratory ..................................... 44-1 
Waterways Experiment Station ............................................................ 45-1 
Engineer Topographic Laboratories ....................................................... 46-1 
Water Resources Support Center .......................................................... 47-1 
Permanent International Association of Navigation Congresses ................... 48-1 
International Boundary Waters Board .................................................... 49-1 
Investigation of Pmrojects Under Federal Power Act .......................................... 50-1 
Regulatory Sunken Vessel Removal & National Emergency Preparedness .............. 51-1 
Natural Disaster Preparedness, Response & Recovery Activities........................... 52-1 
Appendices: 
Flood Control Reservoirs Operable .................................................. A-1 
Flood Control Projects Under Construction......................................... B-1 
Beach Erosion Control Projects Under Construction ............................ .. B-1 
Navigation Locks and Dams Operable .............................................. C-1 
Navigation Projects Under Construction ........................................... D-1 
Multiple-Purpose Projects Including Power in Operation ........................ E-1 
Multiple-Purpose Projects Including Power Under Construction ............... F-1 
Flood Damages Sustained and Prevented ........................................... G-1 
In d ex ........................ ...... ........... ............................................... I-1

NEW ENGLAND DIVISION* 
The New England Division, an operating division with 
both district and division functions, comprises all of New 
England except western Vermont and small portions of 
Massachusetts and Connecticut along their western 
boundaries, and includes small portions of southeastern 
New York, all embraced in the drainage basins tributary 
to Long Island Sound and the Atlantic Ocean east of the 
New York-Connecticut State line. It also includes Fishers 
Island, NY. 
IMPROVEMENTS 
Page Page 
Navigation 
1. Aquatic Plant Control .................................. 1-3 
2. Boston Harbor, MA ...................................... 1-3 
3. Cape Cod Canal, MA .................................... 1-3 
4. Chatham (Stage) Harbor, MA ..................... 1-4 
5. Connecticut River below Hartford, CT ........ 1-4 
6. Cuttyhunk Harbor, MA ............................... 1-5 
7. Green Harbor, MA.........................................1-5 
8. Guilford Harbor, CT.....................................1-5 
9. Hyannis Harbor, MA.....................................1-6 
10. Jonesport Harbor, ME ................................. 1-6 
11. Kennebec River, ME .................................... 1-6 
12. Newburyport Harbor, MA.............................1-7 
13. Portsmouth Harbor and 
Piscataqua River, ME and NH....................1-7 
14. Saco River, M E ............................................. 1-8 
15. Sesuit Harbor, MA.......................................1-8 
16. Wood Island Harbor and the Pool at 
Biddeford, M E ............................................. 1-8 
17. Reconnaissance and Condition Surveys ...... 1-9 
18. Other Authorized Navigation Projects.........1-9 
19. Navigation Activities Pursuant to 
Section 107, Public Law 86-645 
(Preauthorization) ........................................ 1-9 
Alterations of Bridges 
20. Authorized Bridge Alteration ...................... 1-9 
Beach Erosion Control 
21. Revere Beach, MA ........................................ 1-9 
22. Roosevelt Campobello International 
Park, Lubec, M E ........................................... 1-9 
23. Southeast Lighthouse, Block 
Island, RI .................................................... 1-10 
24. Woodmont Beach, Milford, CT .................. 1-10 
25. Inspection of Completed Beach Erosion 
Control Projects .......................................... 1-10 
26. Other Authorized Beach Erosion 
Control Projects .......................................... 1-10 
27. Beach Erosion Control Activities 
Pursuant to Section 103, Public Law 
87-874 (Preauthorization) .......................... 1-10 
Flood Control 
28. Blackstone River Basin, MA and RI..........1-11 
28A. West Hill Dam, MA....................................1-11 
29. Charles River (Natural Valley 
Storage Areas), MA .................................... 1-11 
30. Connecticut River Basin, VT, 
NH, M A and CT..........................................1-11 
30A. Ball Mountain Lake, VT ............................ 1-12 
30B. Barre Falls Dam, MA.................................1-12 
30C. Birch Hill Dam, MA...................................1-13 
30D. Colebrook River Lake, CT..........................1-13 
30E. Conant Brook Dam, MA.............................1-13 
30F. Connecticut River, Middletown, CT ........... 1-13 
30G. Connecticut River Basin Fish 
Passage Facilities for Townshend and 
Ball Mountain Lakes, West River, VT ....... 1-14 
30H. Farmington River, Simsbury, CT..............1-14 
30I. Knightville Dam, MA ................................. 1-14 
30J. Littleville Lake, MA ................................... 1-14 
30K. North Hartland Lake, VT ........................... 1-15 
30L. North Springfield Lake, VT ........................ 1-15 
30M. Otter Brook Lake, NH ............................... 1-15 
30N. Riverdale, West Springfield, MA................1-15 
300. Surry Mountain Lake, NH.......................... 1-16 
30P. Townshend Lake, VT ................................. 1-16 
30Q. Tully Lake, M A ............................................ 1-16 
30R. Union Village Dam, VT .............................. 1-16 
30S. West Springfield, MA..................................1-16 
31. Housatonic River Basin, CT and MA ......... 1-17 
31A. Black Rock Lake, CT .................................. 1-17 
31B. Hancock Brook Lake, CT ........................... 1-17 
31C. Hop Brook Lake, CT.................................... 1-17 
31D. Northfield Brook Lake, CT ........................ 1-18 
31E. Thomaston Dam, CT .................................. 1-18 
1-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Page 
Flood Control (Continued) 
32. Merrimack River Basin, NH and MA ........ 1-18 
32A. Blackwater Dam, NH .................................. 1-19 
32B. Edward MacDowell Lake, NH ................... 1-19 
32C. Franklin Falls Dam, NH.............................1-19 
32D. Hopkinton-Everett Lakes, NH .................. 1-19 
33. New Bedford, Fairhaven, 
and Acushnet, MA ....................................... 1-19 
34. New London, CT ......................................... 1-20 
35. Roughans Point, Revere, MA...................... 1-20 
36. Stamford, CT .............................................. 1-20 
37. Thames River Basin, CT, RI, and MA ....... 1-20 
37A. Buffumville Lake, MA................................. 1-21 
37B. East Brimfield Lake, MA............................1-21 
37C. Hodges Village Dam, MA...........................1-21 
37D. Mansfield Hollow Lake, CT ....................... 1-21 
37E. West Thompson Lake, CT...........................1-21 
37F. Westville Lake, MA.....................................1-22 
38. Town Brook, Quincy and Braintree, MA ... 1-22 
39. Town River Bay, Quincy, MA .................... 1-22 
40. West River, New Haven, CT ...................... 1-22 
41. Inspection of Completed Flood 
Control Projects ......................................... 1-23 
42. Flood Control Reservoir Operations...........1-23 
43. Hurricane Barrier Operations..................1-24 
44. Other Authorized Flood Control Projects .. 1-24 
45. Flood Control Work Under 
Special Authorization ............................... 1-24 
Deauthorized Projects 
46. Deauthorized Projects ................................ 1-24 
Page 
General Investigations 
47. Surveys ....................................................... 1-24 
48. Collection and Study of Basic Data............ 1-25 
49. Planning, Engineering and Design ........... 1-25 
50. Preconstruction Engineering and 
D esign ......................................................... 1-25 
Tables 
Table 1-A Cost & Financial Statement ........... 1-26 
Table 1-B Authorizing Legislation .................. 1-35 
Table 1-C Other Authorized 
Navigation Projects ......................... 1-41 
Table 1-D Other Authorized Beach 
Erosion Control Projects ................. 1-45 
Table 1-E Other Authorized 
Flood Control Projects ..................... 1-46 
Table 1-F Other Authorized Multiple- 
Purpose Projects including Power ... 1-48 
Table 1-G Deauthorized Projects ..................... 1-49 
Table 1-H Navigation Activities 
Pursuant to Sec. 107 ....................... 1-51 
Table 1-I Beach Erosion Activities 
Pursuant to Sec. 103 ....................... 1-51 
Table 14-J Flood Control Activities 
Pursuant to Sec. 205 ....................... 1-52 
Table 1-K Blackstone River Basin....................1-52 
Table 1-L Connecticut River Basin..................1-53 
Table 1-M Housatonic River Basin .................... 1-55 
Table 1-N Merrimack River Basin .................. 1-56 
Table 1-0 Thames River Basin ........................ 1-57 
Table 1-P Boston Harbor, MA........................... 1-57 
Table 1-Q Reconnaissance and 
Condition Surveys ............................ 1-58 
Table 1-R Projects Under Special 
Authorization...................................1-59 
1-2

NEW ENGLAND DIVISION 
Navigation 
1L AQUATIC PLANT CONTROL 
Location. The program is conducted in all navigable 
waters, tributary streams, connecting channels and 
associated waters under the New England Divisionjurisdiction. 
Existing project. The purpose of the program is to 
provide technical assistance in the eradication or control 
of aquatic plants that are causing or have the potential 
to cause major economic problems in the above waterways. 
The plant control is done in the interest of 
navigation, flood control, drainage, agriculture, fish and 
wildlife conservation, public health and research. The 
program is administered by the Chief of Engineers, 
under the direction of the Secretary of the Army, and in 
cooperation with other Federal and State agencies. (See 
Table 1-B at end of chapter for Acts authorizing existing 
program.) 
Local cooperation. Local interests must contribute 
at least 50 percent of the cost of planning beyond the 
reconnaissance stage and at least 50 percent of the cost 
of controlling the aquatic plants, and in addition must 
hold the United States free from damages that may occur 
from control operations. 
Operations during fiscal year. On request, technical 
information was provided to local interests on 
specific aquatic weed problems. These problems included 
nuisance growth of aquatic vegetation in the Charles 
River and several lakes. 
2. BOSTON HARBOR, MA 
Location. Harbor includes all expanse of tidewater 
lying within a line from Point Allerton to Point Shirley 
and extending from that line westward to mainland. 
This comprises an area of about 47 square miles, exclusive 
of the islands. (See National Ocean Survey Charts 
13270 and 13272.) 
Previous project. For details see Annual Report for 
1915, 1917, 1938. 
Existing project Completed work at Boston Harbor, 
adopted in 1825 and supplemented by enactments 
through 1958, provides for the improvement of the harbor 
proper and its approaches - Fort Point Channel, 
Reserved Channel, Chelsea River and Weir River. For a 
more detailed description see page 3 ofAnnual Report for 
1974. These improvements were completed in May 1966 
with the construction of Chelsea River 35-foot channel 
and maneuvering basin. New work involves deepening 
the Mystic River and Reserved Channels from 35 to 40 
feet and the Chelsea River Channel from 35 to 38 feet; 
along with widening and deepening to 40 feet the Inner 
Confluence Area which provides access to the Mystic and 
Chelsea River Channels; and widening at the entrance to 
the Reserved Channel. The proposed project would 
increase the navigational efficiency and safety of harbor 
operations and reduce tidal delays for larger vessels. 
(See Table 1-B at end of chapter for Acts authorizing 
existing projects.) 
Local cooperation. Fully complied with for completed 
work. Formal assurances for new work have not 
been requested yet. Consistent with the cost sharing and 
financing concepts reflected in the Water Resources 
Development Act of 1986, the non-Federal sponsor must 
pay 25 percent of the costs allocated to deep draft navigation 
during construction, currently estimated at 
$7,790,000; reimburse an additional ten percent of the 
costs allocated to deep draftnavigation within a period of 
30 years following completion of construction (partially 
offset by a credit allowed for the value of lands, easements, 
rights-of-way, relocations and dredged material 
disposal areas), currently estimated at $2,165,000; relocate 
utilities necessary for construction of the project, 
currently estimated at $950,000; and deepen berthing 
areas at the terminals of project beneficiaries, currently 
estimated at $2,400,000. 
Terminal facilities. There are 156 wharves and 
piers in harbor, not including Mystic, Weymouth-Fore, 
and Town Rivers, which are reported elsewhere. Of the 
terminals, 28 are publicly owned, 13 are open to public 
use, 73 have mechanical-handling facilities, and 70 have 
railroad connections. Facilities are considered adequate 
for existing commerce. For a full description of channel 
facilities in Chelsea River, refer to House Document 350, 
87th Congress, 2nd session. (See Port Series No. 3, Part 
2, Port of Boston, MA dated 1967.) 
Operations during fiscal year. New work: Continued 
preconstruction engineering and design activities 
including ship simulation studies and preparation of the 
Design Memorandum. Maintenance: Hired labor costs 
of $42,417 were incurred for preparation of an Environmental 
Impact Statement for maintenance dredging in 
association with a proposed improvement project. 
3. CAPE COD CANAL, MA 
Location. This waterway is a sea level canal; extending 
from the head of Buzzards Bay, MA, easterly to a 
point on Cape Cod Bay about 15 miles southeast of 
Plymouth Harbor, MA. (See National Ocean Survey 
Chart 13246.) 
Existing project. For description of existing project 
see Annual Report for 1975. (See Table 1-B at end of 
chapter for Acts authorizing existing project.) Navigational 
improvements were completed in April 1963, with 
completion of East Boat Basin extension. Initial recreational 
development consists of public use facilities at 
various locations, which were completed in February 
1965. Improvements to public use facilities at the East 
Boat Basin were completed in May 1974. Construction of 
public use facilities at Bourne Scenic Park were completed 
in May 1976. Canal is crossed by two high-level 
highway bridges and a vertical-lift railroad bridge. Initial 
major rehabilitation of Bourne Highway Bridge was 
completed in December 1965. More recent major rehabilitation 
of the two highway bridges crossing the canal 
1-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
is completed. Rehabilitation of the Bourne Highway 
Bridge was completed in 1981. The Sagamore Highway 
Bridge was completed in 1982. Minor rehabilitation of 
stone breakwater was completed in October 1963. 
Local cooperation. Fully complied with. Local interests 
must also bear 50 percent of future recreational 
development in accordance with 1965 Federal Water 
Project Recreation Act. 
Terminal facilities. There are seven terminals on 
the canal, of which three are privately owned. Four are 
used for receipt and freezing of fish and two are used for 
receipt and storage of oil. Seventh terminal is State pier, 
owned by Commonwealth of Massachusetts, and on 
north bank of canal at Bourne Neck. Terminals are 
adequate for purposes for which they are used. 
Operations during fiscal year. Maintenance: A 
contract awarded last FY to replace the walkway at 
Sandwich bulkhead was completed in December 1991. 
Final contract amount was $29,481. A contract awarded 
last FY to install storage tanks was completed in April 
1992. Final contract amount was $60,939. A contract 
awarded last FY for road and parking lot repairs in the 
Bourne Recreation Area was completed in February 
1992. Total contract amount was $42,095. A contract for 
emergency shoreline protection at Wings Neck, Bourne, 
was awarded in July 1992. Ending the FY the contract 
was 71 percent complete with earnings of $145,000. A 
continuing contract to paint the Bourne highway bridge 
was awarded in September 1992. Work had not started 
at close of FY. Other FY 1992 maintenance costs were: 
operation and maintenance of Buzzards Bay railroad 
bridge $219,498; review of architect engineer proposal 
for rehabilitation of the Buzzards Bay railroad bridge 
$55,427. Other FY 1992 costs for work accomplished by 
hired labor and contract were: vessel traffic control 
activities $2,118,735; maintenance ofbuildings, grounds 
and utilities $761,275; operation and maintenance of 
project recreational facilities $654,073; project administration 
facilities $490,712; project utilities $163,283; 
maintenance of roads and bridges $93,829; periodic inspections 
$113,418; engineering and design $130,194; 
contract supervision and administration $19,033 and 
$25,836 for real estate activities. 
4. CHATHAM (STAGE) HARBOR, MA 
Location. At northeastern corner of Nantucket Sound 
about 16 miles east of Hyannis Harbor, MA, and 66 miles 
south of Providence Harbor, RI, at northern extremity of 
Cape Cod. (See National Ocean Survey Chart 13237.) 
Previous project. For details see Annual Report for 
1942. 
Existing project. An entrance channel ten feet deep 
and 150 feet wide from Chatham Roads into upper 
harbor. (See Table 1-B at end of chapter for Acts authorizing 
existing project.) Construction of existing project 
was initiated in September and completed in October 
1957. By 1961, a break in barrier beach connecting 
Morris and Monomoy Islands caused Federal Channel to 
fill in completely. Local interests dredged an emergency 
channel to obtain eight-foot depth in June 1962 and 
performed additional dredging in 1963. Minimal maintenance 
dredging by the Federal Government in April and 
May 1964 provided access to inner harbor for 1964 
boating season. Anew ten-foot channel through Harding 
Beach to Morris Island was completed in July 1965. 
Local cooperation. Fully complied with. 
Terminal facilities. The town operates a wharf on 
the north side of the inner harbor which is leased out to 
commercial users. Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: Adjustment 
of $12,426 for rental cost of Government-owned 
hopper dredge CURRITUCK was made for dredging 
completed last FY; final costs were $64,574. Hired labor 
costs of $654 were incurred for supervision and inspection 
associated with a contract completed last FY for 
removing timber pile jetty remains. 
5. CONNECTICUT RIVER BELOW 
HARTFORD, CT 
Location. Has its source in Connecticut Lake in 
northern New Hampshire, flows southerly 380 miles and 
empties into Long Island Sound at Saybrook, CT, 14 
miles west of New London. Hartford, now head of 
commercial navigation, is 52 statute miles, by channel, 
from mouth. (See National Ocean Survey Charts 12373 
and 12377.) 
Previous project. For details see Annual Reports for 
1915 and 1938. 
Eightmile River, CT, elimination as separate project: 
Provides for a channel 8 feet deep and 75 feet wide from 
deep water in Connecticut River to Hamburg and for 
turning basin of same depth, 150 feet wide, approximately 
300 feet long at Hamburg. Project was adopted by 
River and Harbor Act of 1910. Costs and expenditures 
were $9,000 all for new work. In accordance with River 
and Harbor Act of 1950, project for Connecticut River 
below Hartford was modified to include project for 
Eightmile River. Aforementioned Act also provided for 
an anchorage basin 6 feet deep and about 6.5 acres in 
area in upper cove in Hamburg. A channel 15 feet deep 
and 150 feet wide for a distance of 52 miles upstream to 
Hartford; two riprap jetties at the mouth of the river; and 
dikes, training walls, revetments and other regulatory 
works along the river between Hartford and Gildersleeve 
Island. The project provides for small-boat improvements 
at Wethersfield Cove; Eightmile River; Essex; and 
North Cove, Old Saybrook. For a more detailed description 
of project see page 7 of Annual Report for 1974. (See 
Table 1-B at end of chapter for Acts authorizing existing 
project.) Existing project was completed in September 
1965 with the construction of channel and anchorage in 
North Cove, Old Saybrook, CT. For further details, see 
Annual Report for 1974. 
Local cooperation. Fully complied with. 
1-4

NEW ENGLAND DIVISION 
Terminal facilities. Along both Connecticut and 
Eightmile Rivers there are two or three wharves at each 
river town, one or more in each town being open to public 
use. At Hartford and Middletown there is about one-half 
of wharf frontage along west bank of river. Facilities are 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: A 
maintenance dredging contract awarded last FY was 
completed in October 1991. Earnings this FY were 
$61,963 with 13,770 cubic yards of material removed. 
Final contract amount was $337,963 with a total of 
75,103 cubic yards of material removed from Saybrook 
Outer Bar, Calves Island Bar and Essex Shoal. Hired 
labor costs for supervision and inspection were $21,300 
and $10,100 for performing and plotting after-dredge 
surveys. A contract awarded last FY for a disposal site 
study at Cornfield Shoals was completed; earnings this 
FY were $20,000. Total contract amount was $40,000. 
Costs incurred in conjunction with evaluating potential 
impacts on Shortnose Sturgeon and their habitat were 
$39,350 for in-house sampling and testing and $8,166 for 
contract sampling and testing. A continuing contract 
awarded last FY for maintenance dredging of the channel 
and anchorages in North Cove commenced in late 
October 1991 and ceased in mid April 1992 due to an 
environmental restriction. Approximately 80,993 cubic 
yards of material were removed and disposed of at the 
Cornfield Shoals disposal site in Long Island Sound. 
Ending the FYthe contract was 51 percent complete with 
earnings of$321,872. Dredging is to continue in October 
1992. Earnings this FY on a disposal inspection contract 
were $15,000. Hired labor costs included $42,200 for 
supervision and inspection, $1,300 for contract administration, 
and $32,200 for performing and plotting preand 
after-dredge surveys. 
6. CUTTYHUNK HARBOR, MA 
Location. At eastern end of Cuttyhunk Island, at 
western entrance to Buzzards Bay, about 14 miles south 
of New Bedford Harbor, MA. (See National Ocean 
Survey Chart 13229.) 
Existing project. A channel generally 75 feet wide 
and 10 feet deep from outer harbor to westerly terminal 
in Cuttyhunk Pond, about 3,500 feet; an anchorage in 
inner harbor 10 feet deep, 900 feet long, and 800 feet 
wide; and maintenance of existing jetties and stone 
dikes. Existing project was completed in 1939. (See 
Table 1-B at end of chapter for Acts authorizing existing 
project.) 
Local cooperation. Fully complied with. Disposal 
areas for maintenance will be furnished when required. 
Terminal facilities. Two town wharves of timber 
and pile construction, having total berthing space of 400 
feet, are open to public use. Limited mechanical-handling 
facilities are available. Facilities are adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Maintenance dredging in the entrance channel by the 
Government-owned hopper dredge CURRITUCK was 
performed in June 1992 at a rental cost of $75,000. 
Approximately 9,585 cubic yards of sand were removed 
and placed in a nearshore disposal site off Church's 
Beach. Hired labor costs of $27,000 were incurred for 
performing pre-and after-dredge surveys and progress 
surveys. 
7. GREEN HARBOR, MA 
Location. On west side of Massachusetts Bay within 
the town of Marshfield, MA, about 30 miles southeast of 
Boston, MA, and nine miles north of Plymouth Harbor, 
MA. (See National Ocean Survey Chart 13253.) 
Existing project. Provides for channel six feet deep 
(eight feet at entrance), 100 feet wide extending about 
4,000 feet from deep water to head of navigation with 
small turning basin at upstream limit; five-acre anchorage 
near Town Pier, six feet deep; sealing, rebuilding in 
part, and a 200-foot extension of existing west jetty at 
elevation +12, with dike to beach berm at elevation +14 
feet, and raising eastjetty to elevation +14. (See Table 1- 
B at end of chapter for Act authorizing existing project.) 
Construction was completed in October 1969. 
Local cooperation. Fully complied with. 
Terminal facilities. Major terminal facility is Town 
Pier in village of Brant Rock. Facility is a bulkheaded, 
earth-filled landing and parking area about 290 feet 
wide, extending 210 feet into harbor. A marina service is 
south of Town Pier; and a facility for recreational craft 
has been developed on south side of harbor near head of 
navigation. 
Operations during fiscal year. Maintenance: 
Maintenance dredging in the entrance channel by the 
Government-owned hopper dredge CURRITUCK was 
performed in May 1992 at a rental cost of $101,430. 
Approximately 35,600 cubic yards of sand were removed 
and disposed of nearshore off Green Harbor Beach. 
Hired labor costs of $26,842 were incurred for performing 
and plotting pre- and after-dredge surveys and 
progress surveys. A final adjustment of $15,000 was 
madefor dredging completed last FYby the CURRITUCK. 
Final rental cost for last FY dredging was $225,145. 
8. GUILFORD HARBOR, CT 
Location. On north side of Long Island Sound about 
13 miles east of New Haven Harbor, CT. (See National 
Ocean Survey Chart 12354.) 
Existing project. An entrance channel 6 feet deep, 
100 feet wide through the harbor from Long Island 
Sound to an anchorage basin in East River, length 0.8 
mile, a channel 6 feet deep, 60 feet wide up Sluice Creek 
880 feet to Whitfield Street; an anchorage basin 6 feet 
deep, 200 feet wide in East River, length 1,500 feet. 
Mean and spring tidal ranges are 5.4 and 6.4 feet, 
respectively. (See Table 1-B at end of chapter for Act 
authorizing existing project.) Project was completed in 
April 1957. 
1-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Local cooperation. Fully complied with. 
Terminal facilities. State wharf about 370 feet long 
provides adequatefacilities for existing commerce. Town 
wharf on north bank of East River at foot of Whitfield 
Street is no longer usable. 
Operations during fiscal year. Maintenance: A 
continuing contract for maintenance dredging was 
awarded in September 1992. Work had not started at 
close of FY. The total contract amount was $522,550 of 
which $40,000 was obligated this FY. Dredging is expected 
to start early in November 1992. Hired labor costs 
included $8,700 for preparation of plans and specifications, 
$700 for contract administration, and $12,060 for 
performing pre-dredge surveys. 
9. HYANNIS HARBOR, MA 
Location. On south shore of Cape Cod about 16 miles 
west of Chatham, MA and 20 miles northeast ofVineyard 
Haven, MA. (See National Ocean Survey Chart 13237.) 
Existing project. A stone breakwater 1,170 feet long, 
lying about 0.7 mile offshore, dredging to 15.5 feet deep 
in protected area behind breakwater; a channel 12 feet 
deep with widths of 150 and 100 feet in outer and inner 
harbors respectively, an anchorage area 12 feet deep and 
about 5 acres in area adjacent to inner harbor channel 
north of Harbor Bluff; and a riprap jetty 1,000 feet long 
extending south from Dunbar Point. Mean spring tidal 
ranges in outer harbor 3.1 and 3.7 feet, respectively. 
Breakwater was completed in 1882 and dredging behind 
breakwater in 1906. Rehabilitation was necessary to 
restore breakwater to its designed purpose of providing 
aharbor of refuge. Restoration was completed in November 
1961. Construction of 12-foot channel and anchorage 
was initiated in May and completed in November 1959. 
Commonwealth of Massachusetts constructed the jetty 
extending south from Dunbar Point in 1962. (See Table 
1-B at end ofchapter for Acts authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are two town wharves in 
the inner harbor. One has a bulkhead frontage of about 
800 feet. Other private landings are available. Facilities 
are adequate for existing commerce. 
Operations during fiscal year. Maintenance: Adjustment 
of $47,800 was made on dredging completed 
last FY by the Government-owned hopper dredge 
CURRITUCK. Final rental cost was $156,189. Hired 
labor costs of $1,539 were incurred for plotting afterdredge 
surveys associated with last year's maintenance 
dredging. 
10. JONESPORT HARBOR, ME 
Location. Jonesport Harbor is situated on the north 
side of Moosabec Reach in Washington County, ME, 
about 190 miles northeast of Portland, ME, and about 40 
miles southwest of the Canadian border at Eastport, ME. 
Existing project. A combined rubble mound and 
cellular steel sheet pile breakwater, 1,200 feet in length; 
a 15-acre anchorage composed ofnine acres, six feet deep, 
and six acres, eight feet deep; and an entrance channel 
100 feet wide and eight feet deep. (See Table 1-B at end 
of chapter for Act authorizing existing project.) 
Local cooperation. For full description see Annual 
Report for 1987. Fully complied with for contribution 
during construction. Local interests must pay an additional 
ten percent of project costs ($832,119) within a 
period of 30 years following completion. 
Terminal facilities. There are 13 privately owned 
wharves in the harbor, 12 of which are used by local 
fishermen and one which is used for receiving about 
three million gallons of petroleum annually. 
Operations during fiscal year. New work: Administrative 
close-out of project completed. 
11. KENNEBEC RIVER, ME 
Location. Drains a large number of lakes and minor 
streams, and flows from Moosehead Lake about 150 
miles southerly and discharges into Atlantic Ocean about 
25 miles east of Portland, ME. (See National Ocean 
Survey Chart 13298.) 
Previous projects. For details see Annual Reports 
for 1915 and 1938. 
Existing project. A channel 27 feet deep and not less 
than 500 feet wide, extending from mouth to bridge at 
Bath; thence to Gardiner a channel not less than 150 feet 
wide, 17 feet deep at Beef Rock Shoal, at foot of Swan 
Island, 18 feet deep through rock at Lovejoy Narrows, 
near head of Swan Island, decreasing to 16 feet deep at 
Gardiner; channel west of Swan Island, 100 feet wide, 12 
feet deep, except at upper shoal, where depth was to be 
15 feet; and channel 125 feet wide and 11 feet deep from 
Gardiner upstream to Augusta at head of navigation. 
Section of river included in project is about 44 miles long. 
Work includes dredging, rock excavation, and two riprap 
training walls. (See Table 1-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. None required. 
Terminal facilities. Wharves suitable for landing or 
loading are at Bath, Woolwich, Richmond, Randolph, 
Gardiner, Hallowell, and Augusta. Rail connections are 
available at some wharves. Depths alongside range from 
12 to 25 feet. Many facilities are equipped with mechanism 
for handling passengers and freight. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Maintenance dredging of the Doubling Point Reach was 
completed in October 1991 by the Government-owned 
hopper dredge McFARLAND. Rental charges for FY 
1992 were $416,080. Total cost, including mobilization 
last FY, was $526,080. Approximately 69,000 cubic 
yards of material were removed and disposed of in a deep 
spot in the river about two miles south of the dredging 
area and north of Bluff Head. Hired labor costs of 
$34,877 were incurred for performing and plotting preand 
after-dredge surveys and progress surveys. A cost of 
$600 was incurred for rental of a van. 
1-6

NEW ENGLAND DIVISION 
12. NEWBURYPORT HARBOR, MA 
Location. On south bank of Merrimack River, about 
2.5 miles above mouth, and about 48 miles by water 
north of Boston, MA. (See National Ocean Survey Chart 
13282.) 
Existing project. Two jetties, one projecting 4,118 
feet from the north shore, the other projecting 2,445 feet 
from the south shore, converging until 1,000 feet apart, 
then extending seaward 1,000 feet parallel to axis of 
channel; partially closing Plum Island Basin by a timber 
dike; channel 12 feet deep and 400 feet wide through bar, 
thence nine feet deep and 200 feet wide to and including 
a widened turning basin in front of wharves. (See Table 
1-B at end of chapter for Acts authorizing existingproject.) 
Existing project was completed in August 1958, with the 
improvement of 12-foot channel and outer harbor. North 
jetty was completed in 1914; south jetty was completed, 
except for a length of about 30 feet at its outer end, in 
1905. Required rehabilitation in these jetties completed 
in September 1970. Plum Island Basin was partially 
closed in 1883 by construction of a timber dike. North 
Rock was removed in 1901. 
Local cooperation. Fully complied with. 
Terminal facilities. Marinas, a yacht club, public 
landings, and a commercial fish pier extend along a 
frontage of the south bank of Merrimack River below 
highway bridge and one town pier and four marinas on 
the north side of river. Terminal facilities are adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Hired 
labor costs of $800 were incurred for supervision, inspection 
and contract administration in association with 
maintenance dredging performed at the end oflast FY. A 
payment of$171 was made on a FY 1990 dredging project 
by the Government-owned dredge CURRITUCK with 
final payment still pending at the end of this FY. 
13. PORTSMOUTH HARBOR AND 
PISCATAQUA RIVER, ME AND NH 
Location. Piscataqua River forms a portion of boundary 
between Maine and New Hampshire. Mouth of this 
river is called Portsmouth Harbor. It is 45 miles northeast 
of Boston Harbor, MA and 37 miles southwest of 
Portland Harbor, ME. (See National Ocean Survey Chart 
13278.) 
Previous project. For details see Annual Report for 
1892. 
Existing project. Removal of ledge rock areas in 
vicinity of Gangway Rock, southwest point of Badgers 
Island and Boiling Rock to 35 feet deep; widening 35-foot 
channel at bends by removal of ledge rock areas in 
vicinity of Henderson Point, Gangway Rock, Badgers 
Island, Maine-New Hampshire Interstate Bridge and 
Boiling Rock; and extending channel from above Boiling 
Rock to a point about 1,700 feet above Atlantic Terminal 
Sales dock in Newington generally 400 feet wide, and 35 
feet deep below mean low water with maneuvering 
basins above Boiling Rock and at head ofproject; channel 
6 feet deep, 100 feet wide from Little Harbor through 
Rye-New Castle drawbridge, then northerly between 
mainland and Leach's Island to deep water in vicinity of 
Shapleigh and Goat Islands, channel 75 feet wide six feet 
deep up Sagamore Creek to public landing on downstream 
side of Sagamore Avenue bridge and anchorage 
strip, six feet deep, 75 feet wide, totalling three acres, 
adjacent to channel in Sagamore Creek. Public Law 86- 
645, Sec. 107, 1960 River and Harbor Act, as amended in 
1965 and by Chief of Engineers, December 23, 1965 
authorized construction of the six-foot channels and 
anchorages. Modification authorized by 1986 Water Resources 
Development Act provides for: widening of the 
35-foot deep channel from 600 feet to 1,000 feet between 
two vertical lift bridges; widening northern limit of 35- 
foot deep channel adjacent to Badgers Island by 100 feet; 
and widening southern limit of existing 35-foot deep 
channel at Goat Island from 400 to 550 feet. Total 
estimated cost (September 1990) for new work is 
$17,890,000 exclusive of $5,384,043 for new work completed 
before 1971 and amounts expended on previous 
projects. (See Table 1-B at end of chapter for Acts authorizing 
existing project.) 
Local cooperation. Fully complied with for completed 
work. Assurances for 1986 modification were 
executed on February 4, 1988. Local interests must pay 
the initial 25 percent of project costs concurrent with 
project construction and reimburse the additional ten 
percent within the 30-year period following completion of 
construction. In addition, local interests must do the 
following, for which there is no estimate of cost: provide 
all lands, easements and rights-of-way necessary for 
construction and later maintenance of the project including 
suitable areas determined by the Chief of Engineers 
to be required in the general public interest for initial 
and later disposal of dredged material and including 
necessary retaining dikes, bulkheads, and embankments 
therefor, or the costs of such retaining works; provide 
and maintain adequate terminal and transfer facilities 
open to all on equal terms; provide and maintain adequate 
depths in berthing areas and local access channels 
serving the terminals; accomplish all alterations 
and relocations of transportation facilities (excluding 
railroads, combined highway and railroad and publicly 
owned highway bridges and approaches thereto), storm 
drains, sewer outfalls, utilities and other structures and 
improvements made necessary by the project; prohibit 
the erection of any structure, within a distance to be 
determined by the Chief of Engineers, from the bottom 
edge of the proposed channel and turning basin. 
Terminal facilities. Waterfront terminals are chiefly 
on south bank of Piscataqua River in Portsmouth and 
Newington. U.S. Navy Yard is on opposite bank at 
Kittery, ME. Eighteen piers, wharves, and landings 
represent available terminals for handling the port's 
waterborne commerce. Navy Yard is not used for commercial 
activities. On Maine side of river are a town 
landing and two docks. On New Hampshire side there 
are 13 terminals, six of which include a public landing, 
1-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
two docks, three facilities used for vessel mooring and 
landings, are at Portsmouth. In addition there are a 
number of private recreational boat docks. Terminal 
facilities are considered adequate for existing commerce. 
(See Port Series 1 for Ports of Searsport and Portland, 
ME, and Portsmouth, NH.) 
Operations during fiscal year. New work: A contract 
for widening the channel adjacent to Goat Island 
was awarded October 4, 1991. Work began in December 
1991 and was completed in April 1992. Payments through 
July 1992 were $2,431,364 with final payment pending 
at close of FY. Maintenance: A maintenance dredging 
contract was awarded in November 1991. Work began on 
December 11 and was completed on December 15, 1991. 
Final payment was still pending at the end of the FY with 
earnings to date of $91,948. Approximately 20,100 cubic 
yards of material were removed and disposed of at a 
riverine disposal site about 3,000 feet downstream from 
the dredging area. Hired labor costs included $6,500 for 
supervision and inspection; $500 for contract administration; 
and $15,500 for performing and plotting pre- and 
post-dredge surveys. 
14. SACO RIVER, ME 
Location. Rises in White Mountain region of New 
Hampshire at an elevation about 1,900 feet above sea 
level, flows about 105 miles in a general southeasterly 
direction, and discharges into Atlantic Ocean about 16 
miles southwest of Portland, ME. (See National Ocean 
Survey Chart 13287.) 
Existing project. For description of completed existing 
portion of project see Annual Report for 1978. For a 
description of completed improvement of project see 
Annual Report for 1983. (See Table 1-B at end of chapter 
for Acts authorizing existing project.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are five wharves of solid 
fill construction at Saco and Biddeford, none of which has 
railroad connection; and a small pier near mouth of river 
used for summer passenger business. 
Operations during fiscal year. Maintenance: 
Maintenance dredging by the Government-owned hopper 
dredge CURRITUCK was performed south of Half- 
Tide Island near the upstream limit of the project from 
July 20 to August 12, 1992 at a rental cost of $163,000. 
Approximately 15,785 cubic yards of material were removed 
and placed in deep areas of the river located about 
4,000 feet downstream from the dredging site. A contract 
for maintenance dredging at the mouth of the river was 
awarded in August 1992 in the amount of $649,589. 
Mobilization took place this FY at a cost of $130,000. 
Dredging is to commence in October 1992. Hired labor 
costs included $22,500 for the preparation of plans and 
specifications; $10,600 for supervision and administration; 
and $86,400 for performing and plotting pre- and 
after-dredge surveys. 
15. SESUIT HARBOR, MA 
Location. Sesuit Harbor is located on the north shore 
ofDennis in Barnstable County, about85 miles southeast 
of Boston, MA. The town of Dennis is bordered on the 
north by Cape Cod Bay, Brewster and Harwich on the 
east, Nantucket Sound on the south, and Yarmouth on 
the west. Land area within the town is 20.66 square 
miles and has a tidal shoreline of 29.8 miles. (See 
National Ocean Survey Chart 13250.) 
Existing project. Provides for a channel 6 feet deep 
below mean low water and 100 feet wide from deep water 
in Cape Cod Bay to a point opposite the Dennis Yacht 
Club thence reducing in width to 80 feet at the entrance 
to the inner harbor basin, for a total channel length of 
2,400 feet. (See Table 1-B at end of chapter for Act 
authorizing existing project.) Project was completed in 
August 1982. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: 
Maintenance dredging in the entrance channel by the 
Government-owned hopper dredge CURRITUCK was 
performed from May 23 to June 6, 1992 at a rental cost 
of $94,226. Approximately 37,360 cubic yards of sand 
were removed and placed in near-shore areas east of the 
entrance channel off Cold Storage Beach. Hired labor 
costs of $24,300 were incurred for performing pre- and 
after-dredge surveys and progress surveys. 
16. WOOD ISLAND HARBOR AND THE 
POOL AT BIDDEFQRD, ME 
Location. This harbor is situated at the southern end 
of Saco Bay, ME, immediately south of the mouth of the 
Saco River. It is 20 miles southwest of Portland, ME, and 
30 miles northeast of Portsmouth, NH. (See National 
Ocean Survey Chart 13286.) 
Existing project. Provides for a basin in the Pool 6 
feet deep, approximately 9.7 acres in extent, and three 
icebreakers south of Fishermen's Wharf. This work was 
completed in 1956. New work provides for a navigation 
channel from deep water in Wood Island Harbor to a 
point just inside the gut at Biddeford Pool. The channel 
is approximately 4,200 feet long, 100 feet wide and 10 
feet deep. (See Table 1-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation. Fully complied with for completed 
work. A Local Cooperation Agreement (LCA) was 
signed on February 5, 1992 between the Corps and the 
city of Biddeford, ME for new work. The local sponsor 
must provide all lands, easements, rights-of-way, and 
dredged material disposal areas; perform all alterations 
and relocations of facilities and utilities determined by 
the Government to be necesary for construction, operation 
and maintenance of the project; provide during the 
period of construction a cash contribution equal to ten 
percent of total project costs; and repay with interest, 
over a period not to exceed 30 years following completion 
of construction, an additional ten percent of total project 
1-8

NEW ENGLAND DIVISION 
costs, partially offset by a credit allowed for the value of 
lands, easements, rights-of-way, relocations and dredged 
material disposal areas. 
Terminal facilities. There are five wharves in the 
harbor. Three are of pile and timber, and the other two 
are solid-fill construction. One wharf is used for the 
receipt of seafood, two are used in connection with a 
yacht club, and the remaining two are private. There is 
no public-owned wharf but one of the wharves is open to 
the public free of charge. None of the wharves have 
railroad connections. 
Operations during fiscal year. New work: A 
continuing contract for improvement dredging at Wood 
Island Harbor was awarded March 5, 1992. Work is 
scheduled to begin next FY due to environmental restrictions. 
Maintenance: Project condition surveys were 
conducted at a cost of $5,400. 
17. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 1-Q at end of chapter.) 
18. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 1-C at end of chapter.) 
19. NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 
(PREAUTHORIZATION) 
(See Table 1-H at end of chapter.) 
Alterations of Bridges 
20. AUTHORIZED BRIDGE 
ALTERATION 
Location. Chelsea Street Highway Bridge, MA. Construction 
was completed in October 1961 with a Federal 
cost of $138,518. In addition non-Federal contributed 
funds amounted to $8,062. For details see page 63 of 
Annual Report for 1962. 
Beach Erosion Control 
21. REVERE BEACH, MA 
Location. In the city of Revere, Suffolk County, MA, 
approximately seven miles north of the main entrance 
channel to Boston Harbor, and six miles northeast of the 
city of Boston, MA. (See National Oceanic and Atmospheric 
Administration Chart No. 13275 and U.S. Geological 
Survey Maps, Boston Bay quadrangle.) 
Existing project. Placement of sandfill along 13,000 
feet of beach. The top of the sandfill will be placed at 18 
feet above mean low water, including a 50-foot wide 
berm, sloping one-foot vertical in 15 feet horizontal to 
meet the existing beach. The total width of the beach will 
extend approximately 300 feet, of which, about 185 feet 
is above the mean high waterline. (See Table 1-B at end 
of chapter for Acts authorizing existing project.) 
Local cooperation. Formal assurances were executed 
on May 31, 1990 between the Corps and the 
Metropolitan District Commission. Consistent with the 
cost sharing and financing concepts contained in the 
Water Resources DevelopmentAct of 1986 (P.L. 99-662), 
local interests are required to: contribute in cash 35 
percent of the cost of construction of the project, presently 
estimated at $3,605,000; contribute in cash 35 
percent of the periodic nourishment cost for an initial 
period of 50 years, now estimated at $22,000 annually, 
such contribution to be prior to each nourishment operation; 
assure the continued performance of the periodic 
nourishment and repair of the project after the first 50 
years and during the economic life as may be required to 
serve the intended purpose; assure that water pollution 
that would endanger the health of bathers would not be 
permitted; hold the United States free from damages due 
to construction ofthe project; provide all necessary lands, 
easements and rights-of-way for the initial construction 
and subsequent nourishment of the project; assure continued 
public ownership of the shore and its administration 
for public use during the economic life of the project. 
Operations during fiscal year. New work: A contract 
awarded in FY 1990 to place initial beach fill was 
completed in June 1992. Final contract amount was 
$4,374,664. 
22. ROOSEVELT CAMPOBELLO 
INTERNATIONAL PARK, LUBEC, 
ME 
Location. The Roosevelt Campobello International 
Park is located on the southeast end of Campobello 
Island. The island is politically part of New Brunswick, 
Canada, and is separated from Lubec, ME, by the Lubec 
Narrows and connected by FDR Memorial Bridge. It is 
approximately 120 miles east of Bangor, ME. 
Existing project. Stone slope revetment to provide 
shoreline protection for the lighthouse at Mulholland 
Point. The stone protection extends 375 feet around the 
point at a height of about 10 feet and ties into stable 
ground at either end of the project. The upper slope, 
above the stone protection, is graded and seeded. (See 
Table 1-B at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Provide without cost to the 
United States, all lands, easements, rights-of-way, and 
utility relocations necessary for project construction; 
hold and save the United States free from damages due 
to the construction, operation and maintenance of the 
project, except where such damages due to the fault or 
1-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
negligence of the United States or its contractors; maintain 
and operate the project after completion without 
cost to the United States in accordance with regulations 
prescribed by the Secretary of the Army; prevent future 
encroachment which might interfere with proper functioning 
of the project. 
Operations during fiscal year. New work: The 
Operation and Maintenance Manual was in the process 
of being completed. 
23. SOUTHEAST LIGHTHOUSE, 
BLOCK ISLAND, RI 
Location. Southeast Lighthouse is located atop a 
150-foot bluff on the southeast tip of Block Island in the 
town of New Shoreham, RI. The lighthouse was first 
illuminated in 1875 and has been a popular tourist 
attraction for over a century. It is the highest lighthouse 
in New England, visible from 35 miles at sea, and its 
237,000 candle power is the strongest on the Atlantic 
coast. 
Existing project. Provides for all work necessary to 
relocate Southeast Lighthouse and the attached dwelling 
some 245 feet away from the erodingbluff. (See Table 
1-B at end of chapter for Act authorizing existing project.) 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on April 5,1992 between the Corps, the 
Rhode Island Department of Environmental Management 
and the Southeast Lighthouse Foundation. Local 
interests must furnish all lands, easements and rightsof-
way; provide 50 percent of project costs for relocating 
Southeast Lighthouse; assume all costs in excess of the 
Federal statutory limitation of $970,000; and bear all 
costs for operation and maintenance of the lighthouse 
after project completion. 
Operations during fiscal year. New work: A 
competitive services contract for the relocation of 
Southeast Lighthouse was negotiated, however, award 
was delayed pending receipt of local funds. 
24. WOODMONT BEACH, MILFORD, CT 
Location. Woodmont Beach is located on the northern 
shore of Long Island Sound in the borough of 
Woodmont, city of Milford about five miles southwest of 
New Haven, CT and some 82 miles northeasterly of New 
York City. 
Existing project. Provides for Federal participation 
in the amount of one-third of the first cost of protection 
and improvement ofthose portions ofthe shore which are 
publicly owned by widening to a width of 100 feet by 
direct placement of sand, 500 feet of shore in the first 
pocket beach west of Merwin Point; widening to a width 
of 100-150 feet, 3,500 feet of shore from Chapel Street 
northerly to a point about 400 feet north of Anderson 
Avenue; and construction offive impermeable groins 300 
to 400 feet long. This work was completed by the State 
of Connecticut in 1959. (For details see Annual Report 
for 1961.) 
New work provides for the direct placement of sandfill 
along approximately 1,500 feet ofbeach between Clinton 
and Bonsilene Streets to form a berm 50 feet wide. 
Reconstruction of the Usher Road/Dunbar Street and 
Bonsilene Street groins. Mitigation to replace rocky 
habitat for Blue Mussels lost as a result of sand placement. 
(See Table 1-B at end of chapter for Acts authorizing 
project.) 
Local cooperation. Fully complied with for completed 
work. A Local Cooperation Agreement (LCA) was 
signed on May 18, 1992 between the Corps and the city 
of Milford, CT for the new work. The local sponsor must 
provide all necessary lands, easements and rights-ofway 
for the initial construction and subsequent nourishment 
of the project; contribute in cash 35 percent of 
the cost to construct the project; contribute in cash 35 
percent of the periodic beach nourishment cost and 100 
percent of the groin maintenance cost for the 50-year 
economic life of the project; assure continued public 
ownership of the beach and its administration for public 
use for 50 years; control water pollution to the extent 
necessary to safeguard the health of bathers; and if 
necessary provide a drainage system to divert freshwater 
runoff away from the beach. 
Operations during fiscal year. New work: A continuing 
contract for construction of shore protection and 
erosion control measures at Woodmont Beach was 
awarded August21, 1992. The contractor began work on 
the administrative phase of the contract but had not 
mobilized by FY end. 
25. INSPECTION OF COMPLETED 
BEACH EROSION CONTROL 
PROJECTS 
Inspections of beach erosion projects were not conducted 
in fiscal year 1992. 
26. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 1-D at end of chapter.) 
27. BEACH EROSION CONTROL 
ACTIVITIES PURSUANT TO 
SECTION 103, PUBLIC LAW 87-874 
(PREAUTHORIZATION) 
(See Table 1-I at end of chapter.) 
1-10

NEW ENGLAND DIVISION 
Flood Control 
28. BLACKSTONE RIVER BASIN, MA 
AND RI 
Works covered by this plan include a dam and reservoir 
on West River and local protection works at three 
cities on Blackstone River. Flood Control Act of 1944 
authorized plan for a reservoir on West River and local 
protection works at Worcester, MA, and Woonsocket and 
Pawtucket, RI, substantially in accordance with House 
Document 624, 78th Congress, 2nd session. Flood Control 
Act of 1960 authorized a localflood protection project 
at lower Woonsocket, RI, substantially in accordance 
with Senate Document 87, 85th Congress, 2nd Session. 
Local protection nonstructural project authorized in 1982 
for Belmont Park section of Warwick, RI, along the 
Pawtuxet River. Streambank protection projects on the 
Blackstone River in Millbury, MA, and on the Clear 
River in Burrillville, RI, were authorized in 1985. (See 
Table 1-K at end of chapter on Reservoir and Local 
Protection Projects, Blackstone River Basin, for projects 
comprising authorized plan.) 
28A. WEST HILL DAM, MA 
Location. Dam is on West River, MA, three miles 
above its confluence with Blackstone River and 2.5 miles 
northeast ofUxbridge, MA. (See Geological Survey maps 
Blackstone, MA and RI, Milford, MA, and Grafton, MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Work on contract for 
dam and appurtenant structures was initiated in June 
1959 and completed in June 1961. Construction of recreational 
facilities was completed in June 1967. 
Local cooperation. Section 3, Flood Control Act of 
1944 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to replace gate operators and install 
generator was completed in October 1991. Final contract 
amount was $100,114. 
29. CHARLES RIVER (NATURAL 
VALLEY STORAGE AREAS), MA 
Location. The Charles River extends inland from 
Boston Harbor southwesterly toward the 
Massachusetts-Rhode Island border and is some 80 miles 
long with a watershed covering 307 square miles. 
Existing project. The project provides for Federal 
acquisition and protection of 17 natural valley storage 
areas totalling 8,102 acres in what is known as the 
Middle and Upper watershed of the Charles River. The 
acquisition in fee or by easement of the major natural 
valley storage areas within the Charles River watershed 
is intended as a multiple-purpose project for flood control, 
recreation, and fish and wildlife management. (See 
Table 1-B at end of chapter for Act authorizing existing 
project.) Land acquisition is complete. 
A total of 3,210 acres have been acquired in fee at a 
cost of $2,152,853 and restrictive easements have been 
obtained for 4,892 acres at a cost of $591,193. 
Local cooperation. Local interests are required to 
prevent modifications or alteration of existing roadways, 
utilities, bridges, culverts, and any other improvements 
that might affect the drainage characteristics of the 
natural storage areas; adopt and enforce regulations to 
restrict development of flood plain lands; and operate 
and maintain the existing dams along the Charles River. 
Local assurances were provided by the Commonwealth 
of Massachusetts. 
Operations during fiscal year. Maintenance: Hired 
labor costs for ordinary maintenance activities, project 
surveillance and inspection, as well as land use administration, 
were $144,366. In addition $65,616 was expended 
on a fish and wildlife management contract. 
30. CONNECTICUT RIVER BASIN, VT, 
NH, MA AND CT 
Location. Works covered by this project are a series 
of dams and reservoirs on tributaries of Connecticut 
River in Vermont, New Hampshire and Massachusetts, 
within a radius of 230 miles from Hartford, CT, and local 
protection works at several cities in the basin. 
Existing project. Flood Control Act of 1936, as 
amended by Act of May 25, 1937, authorized construction 
often reservoirs on tributaries of Connecticut River 
in accordance with plans in House Document 412, 74th 
Congress, 2nd session, as the same may be revised upon 
further investigation of 1936 flood. Flood Control Act of 
1938 approved a general comprehensive plan for control 
of floods and other purposes in Connecticut River Valley, 
as set forth in House Document 455, 75th Congress, 2nd 
session, and authorized $11,524,000 for construction of 
local flood protection projects in the plan. Act of October 
15, 1940, modified Act of June 18, 1938, to provide 
additional protection at East Hartford, CT, as setforth in 
House Document 653, 76th Congress, 3rd session. Act of 
August 18, 1941, modified comprehensive plan approved 
in 1938 to include improvements recommended in House 
Document 653, 76th Congress, 3rd session, and House 
Document 724, 76th Congress, 3rd session, with such 
further modifications as may be found justifiable in 
discretion of Secretary of the Army and Chief of Engineers. 
Latter Act also authorized to be appropriated 
additional $6 million for local protection works and $10 
million for reservoirs. Act of October 26, 1942, further 
modified plan by including construction of Gully Brook 
conduit at Hartford, CT. Flood Control Act of 1944 
authorized expenditure of $30 million in addition to 
previous authorization for comprehensive plan approved 
in 1938 and modified plan by directing specific consideration 
of an alternative plan of Vermont State Water 
Conservation Board instead of Williamsville Reservoir 
1-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
in West River Basin, VT; directing consultation with 
affected States during course of investigations and 
transmission of proposal and plans to each affected State 
for written views and recommendations for reservoir 
projects heretofore authorized for construction at 
Cambridgeport, Ludlow, South Tunbridge, and Gaysville, 
and resubmission of projects or modifications for construction 
of Sugar Hill site. Flood Control Act of 1950 
modified project for flood control at Hartford, CT, authorized 
by Flood Control Act of 1938, as amended to include 
Folly Brook dike and conduit. Flood Control Act of 1954 
modified plan for flood control in Connecticut River 
Basin to provide for construction of a reservoir on Otter 
Brook at South Keene, NH, in lieu of any reservoir or 
reservoirs heretofore authorized. This Act further modified 
plan for West River Basin of Connecticut River in 
Vermont to consist of three reservoirs at Ball Mountain, 
The Island, and Townshend sites, in lieu of plan of eight 
reservoirs authorized in Flood Control Act of 1944. Flood 
Control Act of 1958 modified plan for flood control in 
Connecticut River Basin to include construction of 
Littleville Reservoir on Middle Branch ofWestfield River, 
MA, and Mad River Reservoir on Mad River, above 
Winsted, CT. Flood Control Act of 1960 included authorization 
in Connecticut River Basin of plan for flood 
protection on Chicopee River, MA, substantially in accordance 
with House Document 434, 86th Congress; plan 
for flood protection on Westfield River, MA, substantially 
in accordance with Senate Document 109, 86th 
Congress; plan for flood control and related purposes on 
Farmington River, CT, substantially in accordance with 
House Document 443, 86th Congress. Flood Control Act 
of 1968 included authorization in Connecticut River 
Basin ofplan for construction of Beaver Brook Reservoir, 
on Beaver Brook in Keene, NH, substantially in accordance 
with Senate Document 60, 90th Congress; and 
plan for protection on Park River, CT, substantially in 
accordance with Senate Document 43, 90th Congress. 
Flood Control Act of 1970 deauthorized the construction 
of a reservoir at Claremont, NH. The Water Resources 
Development Act of 1976 deauthorized the construction 
of Gaysville Lake, VT project. Flood control projects at 
Cambridgeport Lake, Brockway Lake, Victory Lake, 
South Tunbridge Lake, Ludlow Lake and The Island 
Lake, VT; Honey Hill Lake, West Canaan Lake, and the 
Alternative to Sugar Hill Reservoir, NH, were 
deauthorized in August 1977 in accordance with Section 
12 of the Water Resources Development Act of 1974. The 
authorization for Beaver Brook Lake, NH project expired 
in April 1978 due to lack of local cooperation. Local 
protection projects at Gardner, MA, West Springfield, 
MA, Hartford, VT, Wethersfield, CT, and Keene, NH 
authorized and constructed in accordance with Section 
205 of 1948 Flood Control Act. Emergency streambank 
erosion control projects at Brownsville, VT, Conway, 
MA, Milford, CT, Simsbury, CT authorized in accordance 
with Section 14 of the 1946 Flood Control Act were 
completed. (See Table 1-L at end of chapter for reservoirs 
and local protection works for Connecticut River Basin.) 
Water Resources Development Act of 1986 modified the 
comprehensive plan for the control of flood-waters in the 
Connecticut River Basin, Vermont, New Hampshire, 
Massachusetts, and Connecticut, authorized by Section 
5 of the Act of June 22, 1936 (49 Stat. 1572) by authorizing 
the design, construction, operation, and maintenance 
of facilities at Townshend Dam, West River, VT to 
enable upstream migrant adult Atlantic salmon to bypass 
that dam and Ball Mountain Dam, VT, and to 
provide at both Townshend and Ball Mountain Dams 
facilities as necessary for the downstream passage of 
juvenile Atlantic salmon. The estimated project cost is 
$1,500,000. 
30A. BALL MOUNTAIN LAKE, VT 
Location. Dam is on West River, 29 miles above its 
junction with Connecticut River at Brattleboro, VT. It is 
two miles north of village ofJamaica, VT. (See Geological 
Survey map for Londonderry, VT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1957 and 
completed in November 1961. Construction of initial 
recreation facilities was initiated in June 1975 and 
completed in June 1977. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. New work: A 
contract for construction of fish passage facilities at 
Townshend and Ball Mountain Lakes on the West River 
was awarded in May 1992. Work at Ball Mountain Lake 
involves automation of the center gate to regulate the 
spring pool elevation for downstream passage ofjuvenile 
salmon. Ending the FY the contract was 67 percent 
complete with earnings of $391,550. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to paint the service gates at two projects was awarded in 
June 1992. Work had not started at close of FY. 
30B. BARRE FALLS DAM, MA 
Location. Dam is on Ware River in town of Barre, 
MA, 31.9 miles above confluence of Ware and Swift 
Rivers. It is 13 miles, northwest of Worcester, MA. (See 
Geological Survey maps for Barre, MA and Wachusett 
Mountain, MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1956 and 
completed in May 1958. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to replace the electrical service at the 
Environmental Laboratory was completed in January 
1992. Final contract amount was $34,659. A contract for 
addition to the Water Quality Laboratory was awarded 
in April 1992. Ending the FY the contract was 95 percent 
1-12

NEW ENGLAND DIVISION 
complete with earnings of$40,774. A contract to upgrade 
the electrical system at various dam sites was awarded 
in July 1992. Work had not started at FY end. 
30C. BIRCH HILL DAM, MA 
Location. Dam is on Millers River, 27.3 miles above 
its junction with the Connecticut River. It is 1.3 miles 
east of South Royalston, MA and 7.5 miles northwest of 
city of Gardner, MA. (See Geological Survey maps for 
Royalston and Winchendon, MA-NH and Templeton, 
MA) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in June 1940 and 
completed in February 1942. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. Local interests have contributed $32,000 
as their required 50 percent cost sharing of recreational 
development in accordance with 1965 Federal Water 
Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY for road repairs was completed in 
October 1991. Final contract amount was $116,693. A 
contract to upgrade the electrical system at various dam 
sites was awarded in July 1992. Work had not started at 
FY end. A contract to repair the New Boston Road bridge 
was awarded in August 1992. Work had not started at 
FY end. 
30D. COLEBROOK RIVER LAKE, CT 
Location. Damsite is in town ofColebrook, Litchfield 
County, CT, on West Branch Farmington River about 3.9 
miles upstream from its confluence with Still River at 
Riverton, CT, and about 1.5 miles upstream from Goodwin 
(Hogback) Dam. (See Geological Survey map for Winsted, 
CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1965 and 
completed in June 1969. Construction of recreation 
facilities was initiated in August 1969 and completed in 
June 1970. 
Local cooperation. Water supply contract was signed 
by Hartford Connecticut Metropolitan Water District. 
Repayment is being made in accordance with provisions 
of 1958 Water Supply Act. 
Operations during fiscal year. Maintenance. Ordinary 
operation and maintenance activities. A contract 
awarded last FY to repair six bridges at various locations 
was completed in October 1991. Final contract amount 
was $306,666 of which $28,836 was for Colebrook River 
Lake. A contract awarded last FY for pavement repairs 
at two projects was completed in December 1991. Final 
contract amount was $61,156. 
30E. CONANT BROOK DAM, MA 
Location. Site is in south central part of Massachusetts 
in town of Monson. Damsite, across Conant Brook, 
is about two miles southeast of community of Monson, 
MA. (See Geological Survey map for Monson, MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, 
highway relocations, and appurtenances was initiated in 
June 1964 and completed in December 1966. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a cost of $84,492. 
30F. CONNECTICUT RIVER, 
MIDDLETOWN, CT 
Location. The city of Middletown is located in 
Middlesex County, in the lower Connecticut Valley, in 
south-central Connecticut. Middletown is approximately 
15 miles south of Hartford, CT and 20 miles north of New 
Haven, CT. 
Existing project. The project is located along the 
Connecticut River in the vicinity of River Road at the 
intersection with Eastern Drive, approximately 6,500 
feet downstream of the Arrigoni (Route 66) Bridge. The 
project consists of 500 linear feet of 6-inch concrete 
paving block protection underlain by a 1-foot layer of 
gravel bedding and riprap toe protection along River 
Road. (See Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on February 13, 1992 between 
the Corps and the Connecticut Department of Environmental 
Protection. The local sponsor shall provide all 
lands, easements, rights-of-way, and dredged material 
disposal areas; perform all relocations and alterations of 
buildings, utilities, highways, railroads, and bridges 
determined by the Government to be necessary for construction 
of the project; pay a cash contribution in the 
amount necessary to bring the non-Federal share of 
project costs to 25 percent (a minimun cash contribution 
of 5 percent is required); assume all costs in excess of the 
Federal statutory limitation of $500,000; and bear all 
operation, maintenance and repair costs of the project 
after completion. 
Operations during fiscal year. Plans and specifications 
were issued in Feburary 1992, however, receipt 
of bids had to be temporarily postponed when the city of 
Middletown identified utilities in the project area. Plans 
and specifications were revised and an amendment to 
the original solicitation was issued and favorable bids 
were opened on September 22, 1992. 
1-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
30G. CONNECTICUT RIVER BASIN 
FISH PASSAGE FACILITIES FOR 
TOWNSHEND AND BALL 
MOUNTAIN LAKES, WEST RIVER, 
VT 
Location. The West River watershed is located in 
southern Vermont. Townshend Lake dam is located on 
the West River about 19.5 miles above its confluence with 
the Connecticut River. Ball Mountain Lake dam is 
situated on the West River approximately 9.5 miles 
upstream of Townshend Lake and 29 miles upstream of 
the Connecticut River. 
Existing project. Construct a fish barrier and fish 
holding structure 300 feet downstream of Townshend 
Lake, modifications to the Townshend outlet structure, 
automation of the gate controls at Ball Mountain Lake, 
and procurement of a fish transport tank (truckmountable 
for depositing fish). 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on May 4, 1992, between the Corps and 
the State of Vermont. Local interests are required to 
provide, without cost to the Government, all lands, easements, 
rights-of-way, and relocations necessary for 
construction, operation and maintenance of the project; 
and hold and save the Government free from damages 
arising from the construction, operation and maintenance 
of the project, except damages due to the fault or 
negligence of the Government or its contractors. 
Operations during fiscal year. New work: A continuing 
contract for the construction of fish passage 
facilities at Townshend and Ball Mountain Dams was 
awarded on May 12, 1992. Work began during June and 
was 67 percent complete at the end of FY with earnings 
of $391,550. 
30H11. FARMINGTON RIVER, 
SIMSBURY, CT 
Location. The town of Simsbury is located in the 
central portion of Hartford County in north-central Connecticut, 
approximately 25 miles east of the New York- 
Connecticut state line and 14 miles northwest of the city 
of Hartford, CT. 
Existing project. The proposed project includes concrete 
grid block and stone slope protection along 900 feet 
of eroding Farmington River streambank. The project 
will protect the river bank and an adjacent three-foot 
diameter sewer trunk line. 
Local cooperation. Formal assurances have not 
been requested yet. Local interests must provide all 
lands, easements, rights-of-way, and dredged material 
disposal areas, currently estimated at $12,000; perform 
all relocations and alterations of buildings, utilities, 
highways, railroads and bridges, determined by the 
Government to be necessary for construction of the 
project; provide during the period of construction a cash 
contribution of five percent of total project costs, currently 
estimated to be $26,000; provide during the period 
of construction an additional cash contribution of 17.6 
percent, presently estimated at $91,000, so that the total 
contribution equals 25 percent of total project costs; 
assume the responsibility for all costs in excess of the 
Federal statutory cost limitation of $500,000; no less 
than once each year, inform affected interests of the 
limitations of the protection afforded by the project. 
Operations during fiscal year. New work: Preparation 
of plans and specifications was completed. 
30I. KNIGHTVILLE DAM, MA 
Location. Dam is on Westfield River, 27.5 miles 
above its confluence with Connecticut River. It is four 
miles north of town of Huntington, MA, and about 12 
miles west of city of Northampton, MA. (See Geological 
Survey map for Westhampton, MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in August 1939 
and completed in December 1941. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. Final 
payment on the contract for installation ofsafety fencing, 
completed last FY, was pending at close of FY. A contract 
to repair concrete spillway weir/retaining wall was 
awarded in May 1992. Ending the FY the contract was 
42 percent complete with earnings of $59,233. A contract 
to upgrade the electrical system at various dam sites was 
awarded in July 1992. Work had not started at FY end. 
30J. LITTLEVILLE LAKE, MA 
Location. Dam is on Middle Branch of Westfield 
River, one mile above its confluence with main stem of 
Westfield River and 25.2 miles above confluence of 
Westfield River with Connecticut River, in town of 
Chester, MA. (See Geological Survey map for Chester, 
MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenances was initiated under a multicomponent 
contract in June 1962 and completed in September 
1965. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, and Title III, Water Supply Act of 1958 
applies and fully complied with. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
1-14

NEW ENGLAND DIVISION 
to upgrade the electrical system at various dam sites was 
awarded in July 1992. Work had not started at FY end. 
30K. NORTH HARTLAND LAKE, VT 
Location. Dam is on Ottauquechee River, 1.5 miles 
above its junction with Connecticut River, and one mile 
northwest of North Hartland, VT. Reservoir extends 
upstream 5.5 miles. (See Geological Survey map for 
Hanover NH-VT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
was initiated in June 1958 and completed in June 1961. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
for miscellaneous concrete repairs, awarded last FY, was 
completed in July 1992. To date the contractor has 
received $95,240 with final payment pending at the close 
of the FY. 
30L. NORTH SPRINGFIELD LAKE, VT 
Location. Dam is in town of Springfield, VT, on Black 
River, 8.7 miles above its junction with Connecticut 
River, and three miles northwest of Springfield, VT. (See 
Geological Survey maps for Ludlow, VT, and Claremont, 
NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
was initiated in May 1958 and completed in November 
1960. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $662,997. 
30M. OTTER BROOK LAKE, NH 
Location. Dam is on Otter Brook, 2.4 miles upstream 
from its junction with The Branch, which flows 2.5 miles 
to Ashuelot River at Keene, NH. (See National Ocean 
Survey maps for Keene, NH-VT, and Monadnock, NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in September 1956 
and completed in August 1958. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $455,920. 
30N. RIVERDALE, WEST 
SPRINGFIELD, MA 
Location. The town of West Springfield is situated in 
southwestern Massachusetts on the west bank of the 
Connecticut River, about 90 miles west of Boston, MA 
and 135 miles northwest of New York City. Riverdale is 
in the northern portion of the town of West Springfield, 
MA. 
Existing project. The project involved the construction 
of approximately 12,700 feet of earth levee, two 
pumping stations and three stop-log structures. The 
project, with the approved plan of upstream reservoirs, 
is designed to protect against a flood greater than any of 
record. The project is a unit of the comprehensive plan 
of flood control and other purposes in the Connecticut 
River Basin and was authorized by the Flood Control Act 
approved August 18, 1941. Construction of this work 
was initiated in April 1949 and completed in December 
1950. (For details see Annual Report for 1950.) 
A plan of improvement authorized in 1987 calls for the 
expansion of the gravity outflow and pumping capacity of 
the existing Riverdale Pumping Station. This includes 
adding a 24-inch diesel powered pump into the existing 
station. The proposed project also includes jacking a 
separate 5-foot diameter, reinforced concrete culvert 
through the dike, running parallel to the existing culvert 
to increase the gravity outflow capacity. The new gravity 
conduit will be equipped with an ungated inlet and an 
outlet structure which includes a 60" x 6" self contained, 
electronically operated sluice gate. During emergencies, 
the gate could be operated manually from a new bridge 
and tower structure on the river side of the dike. An 
existing nine-foot diameter culvert, about 400 feet downstream 
on Bagg Brook will be replaced with a realigned 
eight-foot x 13-foot corrugated metal arch and a 50-foot 
long transition aligned to tie smoothly into the existing 
downstream channel. Project cost estimate for the modification 
is $890,000. (See Table 1-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Fully complied with for completed 
work. A Local Cooperation Agreement (LCA) was 
signed on July 16, 1992 between the Corps and the 
Massachusetts Department of Environmental Management 
for new work. The local sponsor shall be solely 
responsible for operating, maintaining, replacing, and 
rehabilitating the project; provide, during the period of 
construction, a cash contribution of five percent of total 
project costs, currently estimated to be $44,500; provide 
all lands, easements, rights-of-way, and dredged material 
disposal areas, and perform all relocations and 
alterations of buildings, utilities, highways, sewers, and 
related and special faciltiies determined by the Government 
to be necessary for construction of the project, 
currently estimated to be $50,000; provide during the 
period of construction an additional cash contribution of 
14.4 percent, presently estimated at $128,000, so that 
the total contribution equals 25 percent of total project 
costs; prescribe and enforce regulations to prevent obstruction 
of or encroachment on the project that would 
reduce the level of protection it affords, or that would 
1-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
hinder operation and maintenance; and the local sponsor 
will assume full responsibility for all project costs in 
excess of $5 million. 
Operations during fiscal year. New work: Project 
plans and specifications were updated. Continued coordination 
with the local sponsor to assist in the acquisition 
of required real estate. 
300. SURRY MOUNTAIN LAKE, NH 
Location. Dam is on Ashuelot River, 34.6 miles above 
its junction with Connecticut River and five miles north 
of Keene, NH. (See Geological Survey maps for Keene 
and Bellows Falls, NH-VT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in August 1939 
and completed in June 1942. Initial phase of additional 
recreational facilities completed in September 1969, secondary 
phase in 1980. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to replace underground fuel tanks was 
completed in January 1992. Final contract amount was 
$44,958. 
30P. TOWNSHEND LAKE, VT 
Location. Dam is on West River, 19.1 miles above its 
junction with Connecticut River at Brattleboro, VT, and 
about two miles west of Townshend, VT. Reservoir extends 
upstream about four miles. (See Geological Survey 
maps for Saxtons River, VT, and Londonderry, VT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in November 1958 
and completed in June 1961. Initial phase of additional 
recreational facilities completed in October 1969. Secondary 
phase completed in September 1971. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. New work: A 
contract for construction of fish passage facilities at Ball 
Mountain and Townshend Lakes on the West River was 
awarded in May 1992. Work at Townshend Lake involves 
the construction of a fish trap facility approximately 
300 feet downstream of the dam and construction 
of a plunge pool just downstream of the overflow weir. 
Ending the FY the contract was 67 percent complete with 
earnings of $391,550. Maintenance: Ordinary operation 
and maintenance activities. A contract to paint the 
service gates at two projects was awarded in June 1992. 
Work had not started at FY end. 
30Q. TULLY LAKE, MA 
Location. Dam is on East Branch of Tully River, 3.9 
miles above its junction with Millers River. It is one mile 
north of Fryville, MA, and 3.5 miles north of Athol, MA. 
(See Geological Survey map for Royalston, MA-NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in March 1947 and 
completed in September 1949. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. Local interests must also bear 50 percent of 
future recreational development, in accordance with 
1965 Federal Water Project Recreational Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to upgrade the electrical system at various dam sites was 
awarded in July 1992. Work had not started at FY end. 
30R. UNION VILLAGE DAM, VT 
Location. Dam is on Ompompanoosuc River, four 
miles above its junction with Connecticut River. It is onefourth 
mile north of Union Village, VT, and 11 miles 
north of White River Junction, VT. (See Geological Survey 
maps for Strafford, VT and Mount Cube, NH-VT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
was initiated in March 1947 and completed in June1950. 
Local Cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded in September 1989 to repair Route 132 bridge 
was terminated for non-performance in June 1991. After 
readvertising, a contract was awarded in September 
1991 and completed in July 1992. Final contract amount 
was $56,997. A contract to replace the stairs and railing 
was awarded in August 1991 and completed in February 
1992. Total contract amount was $43,357. A contract to 
upgrade the electrical system at various dam sites was 
awarded in July 1992. Work had not started at FY end. 
A contract to replace guard rails was awarded in July 
1992. Work had not started at FY end. 
30S. WEST SPRINGFIELD, MA 
Location. The West Springfield local protective works 
are located in the town of West Springfield, MA. The 
project is on the west bank of the Connecticut River, 76 
miles above its mouth. (See Geological Survey maps for 
Springfield South and West Springfield, MA-CT.) 
Existing project. This project consists of a system of 
earth levees and concretefloodwalls approximately 24,500 
feet in length. The system starts at high ground, in the 
vicinity of Harrison Place, and extends downstream 
1-16

NEW ENGLAND DIVISION 
along the Connecticut River and up the north bank of the 
Westfield River to high ground at the Boston & Albany 
Railroad. The work involved raising 13,700 feet of existing 
levee, constructing 2,300 feet offloodwall, improving 
2,400 feet of river bank, and treating 6,100 feet of 
existing levee foundation. Three pumping stations with 
appurtenant drainage facilities were also constructed for 
the disposal of interior drainage. The project, with the 
approved plan of upstream reservoirs, is designed to 
protect against a flood greater than any of record. 
The project is a unit of the comprehensive plan offlood 
control and other purposes in the Connecticut River 
Basin and was authorized by the Flood Control Act 
approved June 28, 1938. Construction of this work was 
initiated in March 1939 and completed in July 1942 with 
the exception offoundation treatment along the Westfield 
River south of Agawam Bridge, which was initiated in 
May 1947 and completed in November 1947, and relief 
well and drainage system, which was initiated in August 
1952 and completed in July 1953. 
A modification of the project was authorized in October 
1982 providing for the raising of the floodwall sections by 
one foot and the provision of a flood forecasting system. 
Work for floodwall modification began in April 1984 and 
was completed in August 1984. 
The National Weather Service and the town of West 
Springfield have entered into a Memorandum of Agreement 
for the installation and operation of an automated 
flood forecasting system. This system includes a centralized 
micro-computer, four precipitation gages, two river 
gages and a repeater site. Installation of the automated 
flood forecasting system was completed in February 
1991 and provides the town with timely and accurate 
forecasts ofpotential flooding along both the Connecticut 
and Westfield Rivers. (See Table 1-B at end of chapter for 
Acts authorizing existing project.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: A 
supplemental Operation and Maintenance Manual for 
the flood forecasting system was completed and final 
project costs were apportioned between Federal and non- 
Federal accounts. 
31. HOUSATONIC RIVER BASIN, CT 
AND MA 
Seven flood control reservoirs on tributaries of the 
Naugatuck River, principal tributary of the Housatonic 
River, and three local protection projects have been 
specifically authorized as part of an overall plan for flood 
control in the Housatonic River Basin. The Naugatuck 
and Housatonic Rivers converge 12 miles above mouth of 
Housatonic River. A project for emergency snagging and 
clearing of the Blackberry River, a tributary of the 
Housatonic River, was authorized under authority contained 
in Section 208 of the 1954 Flood Control Act. 
Emergency bank protection projects at: Alford, Green 
River, MA; Sheffield, MA; Salisbury, CT; and Squantz 
Pond, Fairfield, CT were authorized under authority 
provided by Section 14 of the 1948 Flood Control Act. 
Projects for local flood protection for: West Branch, 
Torrington, CT; East Branch, Torrington, CT; Pittsfield, 
MA; and Waterbury-Watertown, CT, were authorized 
under authority provided by Section 205 of the 1948 
Flood Control Act. (See Table 1-M on dams, reservoirs, 
and local protection projects for Housatonic River Basin.) 
31A. BLACK ROCK LAKE, CT 
Location. Damsite is on Branch Brook, about two 
miles upstream from its confluence with Naugatuck 
River, in towns of Thomaston and Watertown, CT. (See 
Geological Survey map for Thomaston, CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Road relocation completed 
in November 1967. Contract for construction of 
dam and appurtenances was initiated in July 1967 and 
completed in July 1971. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to repair six bridges at various projects 
was completed in October 1991. Final contract amount 
was $306,666 of which $24,500 was for Black Rock Lake. 
Another contract awarded last FY for pavement repairs 
at two projects was completed in December 1991. Final 
contract amount was $61,156. 
31B. HANCOCK BROOK LAKE, CT 
Location. Dam is on Hancock Brook, in town of Plymouth, 
CT, about 3.4 miles above its confluence with 
Naugatuck River. (See Geological Survey map for Waterbury, 
CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant structures was initiated in July 1963 
and completed in August 1966. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $136,332. 
31C. HOP BROOK LAKE, CT 
Location. Damsite is on Hop Brook, in city of Waterbury 
and towns ofMiddlebury and Naugatuck, CT, about 
1-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
1.4 miles upstream of confluence of Naugatuck River and 
Hop Brook. (See Geological Survey map for Waterbury, 
CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant structures was initiated in December 
1965 and completed in December 1968. Construction of 
a public use facility was completed in November 1973. 
Construction of an additional restroom was completed in 
1980. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to repair six bridges at various projects 
was completed in October 1991. Final contract amount 
was $306,666 of which $88,964 was for Hop Brook Lake. 
A contract awarded last FY for remedial repairs was 
completed in August 1992. To date the contractor has 
received $703,768 with final payment pending at the 
close of the FY. A contract awarded last FY to repair 
roads and parking aprons was completed in August 1992. 
Final contract amount was $187,970. Acontract awarded 
last FY for construction of restroom was 26 percent 
complete at FY end. Earnings to date were $18,710. 
31D. NORTHFIELD BROOK LAKE, CT 
Location. Dam is on Northfield Brook, about 1.3 
miles upstream from its confluence with Naugatuck 
River, in town ofThomaston, CT. (See Geological Survey 
map for Thomaston, CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenances was initiated in May 1963 and completed 
in October 1965. Construction of recreation facilities 
was initiated in November 1966 and completed in 
August 1967. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. However, local interests must establish 
encroachment lines downstream of dam to permit efficient 
reservoir operation. State legislation requires establishment 
of such lines. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to repair six bridges at various projects 
was completed in October 1991. Total contract amount 
was $306,666 of which $134,166 was for Northfield 
Brook Lake. A contract to build a picnic area restroom 
was awarded in October 1991. Ending the FY the 
contract was 72percent complete with earnings of $76,977. 
A contract to renovate the beach area restroom was 
awarded in May 1992. Ending the FY the contract was 
56 percent complete with earnings of $25,900. 
31E. THOMASTON DAM, CT 
Location. On Naugatuck River, about 30.4 miles 
above its junction with Housatonic River, and about 1.6 
miles north of Thomaston, CT. Reservoir extends upstream 
about 6.4 miles. (See Geological Survey map for 
Thomaston, CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1958 and 
completed in November 1960. 
Local cooperation. Section 3, Flood Control Act of 
1944 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to repair six bridges at various locations 
was completed in October 1991. Total contract amount 
was $306,666 of which $30,200 was for Thomaston Dam. 
32. MERRIMACK RIVER BASIN, 
NH AND MA 
Works covered by comprehensive plan are on 
Merrimack River and its tributaries in New Hampshire 
and Massachusetts. Flood Control Act of 1936 authorized 
construction of a system of flood control reservoirs 
in Merrimack River Basin for reduction of flood heights 
in Merrimack Valley. Flood Control Act of 1938 approved 
general comprehensive plan for flood control and other 
purposes as approved by Chief of Engineers pursuant to 
preliminary examinations and surveys authorized by 
Act of June 22, 1936, and modified project to provide in 
addition to construction of a system of flood control 
reservoirs, related flood control works which may be 
found justified by the Chief of Engineers. All operations 
pertaining to flood control in Merrimack River Basin are 
now carried on under and reported under projects for 
individual units of comprehensive plan referred to above. 
No further expenditures are contemplated under general 
project for flood control in Merrimack River Basin. 
For final cost and financial summary, see Annual Report 
for 1946. 
A comprehensive plan for development of water resources 
of the North Nashua River Basin, a principal 
tributary of the Merrimack River, was authorized by 
1966 Flood Control Act substantially in accordance with 
Senate Document 113, 89th Congress. Plan provides for 
construction of coordinated system of four reservoirs and 
three local protection projects for flood protection, water 
supply, recreation and allied purposes. Water Resources 
Development Act of 1986 deauthorized two of the reservoirs 
and one of the local protection projects. 
The 1966 Flood Control Act also authorized construction 
ofSaxonville local protection project substantially in 
accordance with Senate Document 61, 89th Congress. An 
emergency bank protection project at Amesbury, MA 
was authorized under authority provided by Section 14 
of the 1948 Flood Control Act. (See Table 1-N at end of 
1-18

NEW ENGLAND DIVISION 
chapter for reservoirs and related flood control works for 
Merrimack River Basin.) 
32A. BLACKWATER DAM, NH 
Location. Dam is on Blackwater River, 8.2 miles 
above confluence with Contoocook River, and 118.8 miles 
above mouth of Merrimack River. It is in the town of 
Webster, NH, just above village of Swetts Mills, NH, 18 
miles by highway northwest of Concord, NH. (See Geological 
Survey maps for Penacook and Mount Kearsarge, 
NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete except for construction 
of public facilities. Construction of dam and appurtenant 
works was initiated in May 1940 and completed in 
November 1941. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to clean and paint the service and emergency gates was 
awarded in February 1992. Ending the FY the contract 
was 97 percent complete with earnings of $89,207. 
32B. EDWARD MACDOWELL LAKE, NH 
Location. Dam is on Nubanusit Brook, a tributary of 
Contoocook River, one-half mile upstream from village of 
West Peterborough, NH, and 14 miles east of Keene, NH. 
(See Geological Survey map for Peterboro and Monadnock, 
NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in March 1948 and 
completed in March 1950. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $292,138. 
32C. FRANKLIN FALLS DAM, NH 
Location. Dam is on Pemigewasset River, main 
tributary of Merrimack River, and about 2.5 miles upstream 
of Franklin, NH. (See Geological Survey maps for 
Penacook and Holderness, NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in November 1939 
and completed in October 1943. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
for deleading and repainting the service bridge was 
awarded in April 1992. Work had not started at FY end. 
Another contract for conduit repairs awarded in May 
1992 was completed in September 1992. Earnings to 
date were $192,940 with final payment pending at close 
of the FY. A contract to rehab the Knox Brook bridge was 
awarded in July 1992. Work had not started at FY end. 
32D. HOPKINTON-EVERETT LAKES, 
NH 
Location. Hopkinton Dam is on Contoocook River, 
17.3 miles above its junction with Merrimack River and 
about one-half mile upstream from village of West 
Hopkinton, NH. Everett Dam is on Piscataquog River, 16 
miles above its junction with Merrimack River, and 
about 1.3 miles southeast of village of EastWeare, NH. 
Two interconnecting canals were provided to enable the 
two reservoir areas to function as one. (See Geological 
Survey map for Hillsboro, NH, and Concord, NH.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of two 
dams and appurtenant works was initiated in November 
1959 and completed in December 1962. Construction of 
recreation facilities was initiated in November 1974 and 
completed in September 1975. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. Local interests must also bear 50 percent of 
future recreational development in accordance with 1965 
Federal Water Project Recreation Act. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last fiscal year to repair Dike P-1 was 97 percent 
complete ending the FY with earnings of $310,332. A 
contractfor miscellaneous concrete repairs was awarded 
in June 92. Ending the FY the contract was 40 percent 
complete with earnings of $12,374. 
33. NEW BEDFORD, FAIRHAVEN, AND 
ACUSHNET, MA 
Location. Main harbor barrier is across New Bedford 
and Fairhaven Harbor in vicinity of Palmer Island. 
Supplemental dikes and walls are provided in Clark 
Cove area of New Bedford and Fairhaven. (See Geological 
survey maps for New Bedford North, New Bedford 
South, Marion, and Sconticut Neck, MA and National 
Ocean Survey Charts 13230, 13070 and 13218.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction ofbarrier 
and appurtenances was initiated in October 1962 and 
completed in January 1966. Construction ofthe pumping 
station was initiated in October 1962 and completed in 
June 1964. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: A 
1-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
contract awarded last FY to repave the access road to 
barrier office was completed in November 1991. Final 
contract amount was $57,455. A contract for miscellaneous 
concrete repairs was awarded in May 1992. Ending 
the FY the contract was 80 percent complete with 
earnings of $5,465. A contract for roof repairs was 
awarded in June 1992. Ending the FY the contract was 
99 percent complete. Operating costs included $144,000 
forprojectoperations; $33,599 for administration; $29,280 
for engineering and design; $11,647 for contract supervision 
and inspection. The cost of maintenance work 
accomplished by contract included $3,300 for replacement 
of garage door. 
34. NEW LONDON, CT 
Location. In the city of New London, CT, about 45 
miles southeast of Hartford, CT, and 50 miles southwest 
of Providence, RI. (See Geological Survey map for New 
London, CT.) 
Existing project. The hurricane protection project 
consists of approximately 715 feet of rock-faced earthfill 
dike and 800 feet of I-walls around the northerly shore of 
Shaw Cove and the regrading of approximately 21 acres 
of land along the west shore of the cove to elevation 12.5 
feet mean sea level. Top of dike and floodwalls are 14.5 
feet mean sea level. Appurtenant structures include a 
street gate, pressure conduit and a pumping station to 
discharge interior drainage. Project is complete. (See 
Table 1-B at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: Final 
adjustment of project costs between Federal and non- 
Federal accounts. 
35. ROUGHANS POINT, REVERE, MA 
Location. The city of Revere is a coastal community 
located in Suffolk County about five miles northeast of 
the city of Boston, MA. Roughans Point is a low-lying, 
ocean front neighborhood of Revere. The area has 55 
acres and about 300 structures, mostly residential homes, 
which lie below elevation ten feet NGVD. 
Existing project. Project consists of 3,125 feet of 
stone revetment to dissipate incoming waves, prevent 
overtopping and stabilize existing facilities along the 
shoreline. The revetment would extend from a point 
about 250 feet south of Eliot Circle southerly to a point 
200 feet south of the intersection of Winthrop Parkway 
and Leverett Avenue. The project also calls for "backwater" 
protection by constructing an earth berm one foot 
high and 200 feet long on the existing median strip 
between Bennington Street and State Road and a sluice 
gate on the 42-inch drain from the Roughans area to 
Sales Creek. Interior drainage improvements consist of 
a new intake structure at the existing pump station and 
a new gravity drain with a sluice gate. The total estimated 
project cost (October 1992) is $13,800,000. (See 
Table 1-B at end of chapter for Act authorizing existing 
project.) 
Local cooperation. Formal assurances have notbeen 
requested yet. Local interests must provide without cost 
to the United States all lands, easements, and rights-ofway 
necessary for construction of the structural elements 
of the project, including ponding areas, borrow areas, 
and disposal areas for excavated material presently 
estimated at $880,000; hold and save the United States 
free from damages due to construction, operation, and 
maintenance ofthe project, not including damages due to 
the fault or negligence of the United States or its contractors; 
bear all costs of operation, maintenance and 
replacements, presently estimated at $25,000 annually; 
pay an amountin cash, presently estimated at $3,950,000, 
to bring the total non-Federal share to 35 percent of 
project costs allocated to storm damage reduction; provide 
and maintain necessary access roads; and accomplish 
without cost to the United States all alterations and 
relocations of buildings, streets, storm drains, utilities, 
highway bridges, and other structures necessary for 
construction of the project. 
Operations during fiscal year. New work: Preparation 
of project plans and specifications was initiated 
during April 1992. The General Design Memorandum 
was appproved on September 20, 1992 and work on the 
Project Management Plan continued. 
36. STAMFORD, CT 
Location. In Fairfield County on north shore of Long 
Island Sound, about 30 miles east of New York City, and 
20 miles southwest of Bridgeport, CT. (See Geological 
Survey map for Stamford, CT.) 
Existing project. For description of completed improvement 
see Annual Report for 1974. (See Table 1-B at 
end of chapter for Act authorizing existing project.) 
Project was completed in 1969. Local interests still owe 
a substantial amount based on claims settlements, including 
interest payment under the Contract Disputes 
Act. 
Local cooperation. Fully complied with except for 
$662,000 outstanding which is local share of final claims 
settlement including interest payment. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to repair fenders and replace camels 
was completed in January 1992. Final contract amount 
was $165,690. Another contract awarded last FY to 
install sluice gates was completed in February 1992. 
Final contract amount was $49,523. A contract to replace 
the roof was awaded in July 1992. Work had not 
started at FY end. 
37. THAMES RIVER BASIN, CT, RI, 
AND MA 
Works covered by this plan are a series of dams and 
reservoirs on tributaries of Thames River in Massachusetts 
and Connecticut, within a radius of 45 miles from 
1-20

NEW ENGLAND DIVISION 
Norwich, CT, and a channel enlargement on Shetucket 
River where it discharges into Thames River at Norwich. 
Flood Control Act of August 18, 1941, approved plan for 
a system of reservoirs and channel improvements in 
Thames River Basin in accordance with House Document 
885, 76th Congress, 3rd session, and authorized $6 
million for initiation and partial accomplishment of 
project. Flood Control Act of December 22, 1944, authorized 
completion of approved plan. Flood Control Act of 
July 14, 1960, authorized project for West Thompson 
Reservoir, substantially as recommended in Senate 
Document 41, 86th Congress, 2nd session. Local flood 
protection project for West River, New Haven, CT was 
authorized under authority provided by Section 205 of 
the 1948 Flood Control Act. (See Table 1-0 at end of 
chapter on reservoirs and local protection districts, 
Thames River Basin, for projects comprising approved 
plan.) 
37A. BUFFUMVILLE LAKE, MA 
Location. Dam is on Little River, 1.3 miles above its 
junction with French River, and eight miles northeast of 
Southbridge, MA. Reservoir extends upstream about 1.7 
miles northerly and 1.9 miles southerly. (See Geological 
Survey maps for Webster, MA and CT, and Leicester, 
MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in September 1956 
and completed in June 1958. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to renovate the recreation area restroom was awarded in 
June 1992. Work had not started at close of FY. 
37B. EAST BRIMFIELD LAKE, MA 
Location. Dam is on Quinebaug River, 64.5 miles 
above its confluence with Shetucket River, and one mile 
southwest of village of Fiskdale, MA. (See Geological 
Survey maps for Whales, MA and CT, Southbridge, MA 
and CT, East Brookfield, MA, and Warren, MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in May 1958 and 
completed in June 1960. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to replace weir gates and repair/repaint 
service gates was completed in August 1992. Earnings to 
date were $75,505 with final payment pending at close of 
FY. 
37C. HODGES VILLAGE DAM, MA 
Location. Dam is on French River, 15 miles above its 
confluence with Quinebaug River, at Hodges Village in 
town of Oxford, MA, about five miles north of Webster, 
MA. (See Geological Survey maps for Webster, MA, and 
CT, Leicester, MA, Worcester South, MA, and Oxford, 
MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works, initiated in March 1958, was 
completed in December 1959. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
awarded last FY to paint the service gates was completed 
in July 1992. Earnings to date were $40,844 with final 
payment pending at close of FY. 
37D. MANSFIELD HOLLOW LAKE, CT 
Location. Dam is at Mansfield Hollow, CT, on 
Natchaug River, 5.3 miles above its confluence with 
Willimantic River. It is four miles northeast of city of 
Willimantic, CT. (See Geological Survey maps for Spring 
Hill and Willimantic, CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, 
initiated in 1949, was completed in May 1952. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities. A contract 
to paint the service gates was awarded in March 1992. 
Ending the FY the contract was 16 percent complete with 
earnings of $7,359. 
37E. WEST THOMPSON LAKE, CT 
Location. Dam is on Quinebaug River, in town of 
Thompson, CT. Site is in village of West Thompson, two 
miles upstream from city of Putnam, CT. (See Geological 
Survey map, for Putnam, CT.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam, 
road relocation, and appurtenances was initiated in 
August 1963 and completed in October 1965. Initial 
phase of recreation facilities was completed in May 1976. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $546,909. 
1-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
37F. WESTVILLE LAKE, MA 
Location. Dam is on Quinebaug River, 56.7 miles 
above its confluence with Shetucket River, in towns of 
Sturbridge and Southbridge, MA, and 1.3 miles west of 
center of Southbridge. (See Geological Survey maps for 
Southbridge, MA and RI, and East Brookfield, MA.) 
Existing project. For description of completed improvement 
and authorizing legislation see Annual Report 
for 1975. Project is complete. Construction of dam 
and appurtenant works was initiated in April 1960 and 
completed in August 1962. 
Local cooperation. Section 2, Flood Control Act of 
1938 applies. 
Operations during fiscal year. Maintenance: Ordinary 
operation and maintenance activities were conducted 
at a total cost of $359,577. 
38. TOWN BROOK, QUINCY AND 
BRAINTREE, MA 
Location. The project is located in the city of Quincy 
and the town of Braintree on the south side of Massachusetts 
Bay, along the eastern shore of Massachusetts, 
seven miles south of Boston in Norfolk County. The 
watershed is approximately 4.5 square miles. 
Existing project. Project provides for the construction 
of a 12-foot diameter, 4,060-foot long, concrete lined 
tunnel in bedrock approximately 140 to 180 feet below 
ground, intake and outlet structures, and improvements 
to the Town River downstream of the outlet shaft. The 
tunnel and its appurtenances will be supplemented by 
reconstruction of the Old Quincy Reservoir Dam, located 
at the headwaters of Town Brook. Reconstruction work 
includes a new spillway and outlet structure. The estimated 
total project cost (October 1992) is $40,600,000, 
and includes $6,100,000 in approved credit for compatible 
work that has been accomplished by the project 
sponsor. Total project costs do not include dam safety 
measures at Old Quincy Reservoir Dam, which are anon- 
Federal responsibility. (See Table 1-B at end of chapter 
for Act authorizing existing project.) 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on July 7, 1992 between the Corps and 
the Metropolitan District Commission (MDC). The MDC 
is required to provide all lands, easements, and rights-ofway, 
presently estimated at $830,000; reconstruct Old 
Quincy Dam to insure its structural integrity, presently 
estimated at $4,550,000; pay a cash contribution for the 
costs allocated to flood control, presently estimated at 
$3,220,000; so that the total contribution of local interests 
is equal to 25 percent of costs allocated to flood 
control; and bear all costs of operation, maintenance, and 
replacements, presently estimated at $38,000 annually. 
In addition, local interests must do the following: prescribe 
and enforce regulations to prevent encroachment 
on both the improvements and unimproved channels, 
and manage all project-related channels to preserve 
capacities for local drainage as well as for project functions. 
Operations during fiscal year. New work: A continuing 
contract for construction of Town River improvements 
was awarded on September 30, 1992. 
39. TOWN RIVER BAY, QUINCY, MA 
Location. The city of Quincy is located in Norfolk 
County in eastern Massachusetts, approximately five 
miles north of Braintree, MA and ten miles southeast of 
Boston, MA. Quincy is bordered by Milton, MA to the 
west, Weymouth, MA to the south, and the Atlantic 
Ocean to the east. 
Existing project. Construct a stone revetment approximately 
280 feet long and 15 feet high along an 
eroding section of Town River Bay shoreline. The project 
will protect a subsidized housing structure situated 
about ten feet from the top edge of the eroding shoreline. 
(See Table 1-B at end of chapter for Act authorizing 
existing project.) 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on December 31, 1990 between the 
Corps and Massachusetts Department of Environmental 
Management (DEM) for the project. Local interests 
are required to furnish all lands, easements, and rightsof-
way, including suitable borrow and dredged material 
disposal areas; accomplish all alterations and relocations 
determined by the Government to be necessary for 
construction; provide 25 percent of total project costs 
during construction; and bear all costs for maintenance 
of the project after completion. 
Operations during fiscal year. New work: A 
contract for construction of emergency shoreline protection 
measures along Town River Bay was awarded 
March 6, 1992. Work began in April 1992 and was 
completed in June 1992. Final contract amount was 
$28,850. 
40. WEST RIVER, NEW HAVEN, CT 
Location. New Haven, CT is located in southern New 
Haven County, about 35 miles south of Hartford, CT. The 
project area is located upstream of the intersection of 
Route 63 and West River in northwestern New Haven. 
Existing project. The West River will be widened for 
1,150 feet from its existing 25- to 30-foot width to a 50- to 
70-foot width; a 1,150-foot modular wall will be built 
along the right bank and a 600-foot cantilever sheet pile 
wall will be built along the left bank. For Wintergreen 
Brook the channel will have a 20- to 30-foot width, and a 
550-foot sheet pile wall and 450-foot dike on the right 
bank. A recreational walkway on top of the modular wall 
with lighting and fencing to connect two existing city 
parks is also included. (See Table 1-B at end ofchapter for 
Act authorizing existing project.) 
Local cooperation. A Local Cooperation Agreement 
(LCA) was signed on January 17, 1989 between the 
Corps and the Connecticut Department of Environmental 
Protection (DEP). Local interests are required to 
provide all lands, easements, rights-of-way and reloca- 
1-22

NEW ENGLAND DIVISION 
tions, presently estimated at $1,700,000; pay a cash 
contribution for the costs allocated to flood control, presently 
estimated at five percent or $291,000 so that the 
total contribution of local interests is equal to 25 percent 
of costs allocated to flood control; pay 50 percent of the 
costs allocated to recreation, presently estimated to be 
$140,000; assume full responsibility for all project costs 
in excess of the Federal statutory limitation of $5,000,000; 
and bear all costs of operation and maintenance of the 
project after completion, presently estimated at $7,000 
annually. In addition, local interests must do the following, 
for which there is no estimate of cost: participate in 
and comply with applicable Federal flood plain management 
and flood insurance programs; prescribe and enforce 
regulations to prevent encroachment on the project 
which would reduce level of protection afforded; notify, 
not less than once a year, affected interests of the limitations 
of the protection afforded by the project. 
Operations during fiscal year. New work: A contract 
awarded during FY 1990 for construction of the 
project was 94 percent complete ending the FY with total 
earnings of $3,310,000. 
41. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
In accordance with provisions of the Flood Control Act 
of 1936, as amended, local flood protection works constructed 
with Federal funds are transferred to local 
interests to operate and maintain. To insure compliance 
with regulations prescribed for their operation and 
maintenance, regularinspections ofthefollowingprojects 
were made during the fiscal year: 
CONNECTICUT: April 92 - Bridgeport, Colchester/ 
East Hampton, East Branch, East Hartford, HallMeadow, 
Hartford, Mad River, Milford, New London, North 
Canaan, Norwalk, Pawcatuck, Salisbury, Stamford, 
Sucker Brook, Waterbury, Wethersfield, Woodbury; May 
92 - Ansonia, Danbury, Derby, North Fairfield, 
Torrington, Winsted; September 92 - Ansonia, Derby, 
Hartford, New London, Stamford. 
MAINE: April 92 - Ogunquit; June 92 - Beals, Blaine, 
Castine, Cherryfield, Fort Kent, Gouldsboro, Harpswell, 
Hartland, Indian Island, Islesboro, Lubec, Machias, Perry, 
Whiting. 
MASSACHUSETTS: April 92 - Alford, Amesbury, 
Blackstone, Canton, Conway, Fitchburg, Haywood Creek/ 
Braintree, Holyoke, Huntington, Lancaster, Lee, 
Millbury, Pittsfield, Quincy, Saxonville, Scituate, 
Sheffield (covered bridge), Sheffield (state maintenance), 
Three Rivers, Ware, West Haven, Westfield, Weymouth/ 
Braintree, Worcester; May 92 - Charles River Dam, 
Chicopee, Gardner, Haverhill, Lowell, Northampton, 
Springfield, West Springfield; September 92- Fitchbus 4, 
Springfield, West Springfield. 
NEW HAMPSHIRE: April 92 - Charlestown, 
Farmington, Nashua, North Stratford,Wilton; May 92 - 
Lincoln, Shelbourne; September 92 - Keene, Nashua. 
RHODE ISLAND: April 92 - Burrillville. 
VERMONT: April 92 - Brownsville, Saxtons River, 
Weston. 
42. FLOOD CONTROL RESERVOIR 
OPERATIONS 
A coordinated system of reservoirs, many of which are 
multipurpose in nature and all containing significant 
amounts of storage for flood control purposes, has been 
established in five major flood producing basins in New 
England. During periods of flood flows, regulation of 
reservoirs is fully coordinated within each basin dependent 
upon its location in the watershed, its available 
storage capacity and origin of the flood. In addition to 
flood control releases, water supply, flow augmentation 
and hydropower releases were made from selected reservoirs. 
Winter pools are maintained at many projects to 
submerge the flood control gates and keep them from 
freezing. 
During FY92, there was only one significant inland 
flood event in New England which required notable 
regulation activities at our reservoirs. Over the weekend 
of 5-6 June, three to eight inches of rainfall occurred over 
southern New England with the highest concentrations 
in central Connecticut in the Wallingford-Waterbury 
area. Some reservoirs within the Naugatuck, Farmington 
and Westfield watersheds were throttled back during 
the storm resulting in storages of 2 to 25 percent being 
utilized. Flooding occurred predominantly in the 
Naugatuck watershed and resulting reservoir regulation 
activities provided about $2 million in benefits. 
CONNECTICUT RIVER BASIN 
Regulation for canoe activities occurred at Ball Mountain 
and Townshend - April 1992; Otter Brook - March 
1992; Birch Hill, Tully, Littleville and Knightville -April 
1992; Surry Mountain -May 1992. 
Non-flood releases from Colebrook Lake were made 
throughout FY92 for hydropower generation, as required 
by the Hartford MDC. 
Non-flood releases were made from Union Village and 
North Hartland in March 1992, in support of the Dynamic 
Ice Breakup Experiment sponsored by the State 
of New Hampshire and CRELL. Additional non-flood 
releases from North Hartland Lake were controlled by 
the Vermont Electric Generation and Transmission Cooperative 
for hydropower throughout FY92. 
MERRIMACK RIVER BASIN 
Blackwater was regulated for canoe races in May 
1992. 
THAMES RIVER BASIN 
Regulation activities in the basin included releases for 
canoe races at Mansfield Hollow in June 1992; Hodges 
Village in May 1992 and East Brimfield in April 1992. 
The permanent pool at West Thompson was raised on 
several occasions to accommodate the American Kennel 
Club (AKC) retriever trials. 
1-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
43. HURRICANE BARRIER 
OPERATIONS 
Five hurricane barriers are situated along the southern 
coast of New England, protecting coastal communities 
from tidal flooding associated with hurricanes and 
severe coastal storms. The Corps operates the navigational 
elements of the Stamford, CT and New Bedford- 
Fairhaven, MAbarriers. The Fox Point, RI, the Pawcatuck 
and New London, CT barriers are operated by the local 
communities. A brief resume of operations for the fiscal 
year follows: 
STAMFORD BARRIER. The barrier gates were operated 
on 13 occasions for coastal storms during FY92. 
Benefits associated with the operation totalled $2.15 
million. 
NEW BEDFORD BARRIER. During FY92, the New 
Bedford Barrier was operated on 11 different occasions 
resulting in a total of $300,000 in benefits. 
FOX POINT HURRICANE BARRIER. The Fox 
Point Hurricane Barrier was operated one time during 
FY92. No benefits were attributed to the operation. 
PAWCATUCK HURRICANE BARRIER. The 
Pawcatuck Hurricane Barrier was not operated during 
FY92 and did not experience damaging tidal flood conditions. 
NEW LONDON HURRICANE BARRIER. The New 
London Hurricane Barrier was not operated duringFY92 
and did not experience damaging tidal flood conditions. 
44. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 1-E at end of chapter.) 
45. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205. Public 
Law 858, 80th Congress, as amended (preauthorization). 
(See Table 1-J at end of chapter.) 
Snagging and clearing activities pursuant to Section 
208 of the 1954 Flood Control Act. 
Fiscal year costs were as follows: 
Quaboag River, Brookfield, MA $ 9,065 
Emergency Bank Protection activities pursuant to 
Section 14 of the 1946 Flood Control Act. 
Fiscal year costs were as follows: 
Baker River, Rumney, NH 
Belfast, ME 
Blynman Canal, Gloucester, MA 
Cold River, Alstead, NH 
Connecticut River, Cromwell, CT 
Connecticut River, Middletown, CT 
Conn. River, (Wellfield), Middletown, CT 
Farmington River, CT 
Fort Trumbull Beach, Milford, CT 
Holmes Bay, Whiting, ME 
Johnson Bay (Retention Wall), Lubec, ME 
Lighthouse Beach, Chatham, MA 
Machias Bay (Rte. 92) Machiasport, ME 
Merrimack River, Hooksett, NH 
Mosman Park, Searsport, ME 
Myers Brook, Glastonbury, CT 
Narraguagus River, Milbridge, ME 
Nashua River, Leominster, MA 
North Nashua River (Sewer Line), MA 
Ocean Grove Beach, Swansea, MA 
Packer Brook, Tilton, NH 
Point Shirley, Winthrop, MA 
Sheepscot River, Alna, ME 
Sylvia State Beach, Oak Bluffs, MA 
Town River Bay, Quincy, MA 
Westfield Rvr. (Frog Hole), Westfield, MA 
$ 2,922 
40 
11,000 
3,911 
2,408 
9,446 
7,000 
2,079 
369 
8,166 
10,660 
28,600 
6,035 
985 
9,000 
561 
3,973 
17,937 
34,097 
3,944 
1,910 
31,830 
7,651 
25,138 
19,502 
308 
Fish passage facilities (Section 872 of the 1986 Water 
Resources Development Act.) 
Fiscal year costs were as follows: 
Townshend & Ball Mountain Lakes, VT $602,542 
Emergency flood control activities--repair,f lood fighting, 
and rescue work (Public Law 99, 84th Cong., and 
antecedent legislation.) 
Federal costs for fiscal year were $594,555 for disaster 
preparedness. 
Deauthorized Projects 
46. DEAUTHORIZED PROJECTS 
(See Table 1-G at end of chapter.) 
General Investigations 
47. SURVEYS 
Costs for the fiscal year for surveys from regular funds 
were $1,242,304 ofwhich $171,411 was for four navigation 
studies; $472,834 for two flood damage prevention studies; 
$52,972 for two special studies; and $545,087 for 
coordination studies. 
1-24

NEW ENGLAND DIVISION 
48. COLLECTION AND STUDY OF 
BASIC DATA 
The Division Engineer is the U.S. member on Saint 
Croix River Board of Control. Annual inspections are 
made of conditions on the Saint Croix River and a 
continuing program of compilation of basic hydrologic 
information is carried out. Division Engineer's representatives 
during the past year kept closely in touch with 
development in the basin and cooperated with their 
Canadian counterparts assisting in development of basins' 
resources. Total costs for the fiscal year were 
$3,534. Total costs to 30 September 1992 are $253,277. 
Flood plain studies comprise compilation and dissemination, 
upon responsible local request, of information on 
floods and potential flood damages, including identification 
of areas subject to inundation by floods of various 
magnitudes and frequencies, and general criteria for 
guidance in use of flood plain area; and engineering 
advice to local interests for their use in planning to 
ameliorate flood hazard. Total costs for the fiscal year 
were $424,796. Total costs to 30 September 1992 are 
$7,086,378. 
The April 1987 flood was one of the largest of recent 
times in New England, resulting in spillway discharge at 
six Corps flood control reservoirs. A comprehensive 
hydrologic analysis of this flood event is needed to develop 
a base of information for use in future planning and 
design studies, as well as reservoir operation. Fiscal year 
1992 funds were used to initiate a generalized hydrologic 
investigation of the 1987 flood with consideration of 
overall rainfall patterns and frequency. Total costs for 
the FY were $17,880. Total costs to 30 September 1992 
are $17,880. 
The New England Division has initiated a program to 
consolidate the vast amount of sediment chemistry data 
it maintains using the Geographic Information System 
(GIS). This data management system will allow Project 
Managers, as well as other agencies, to quickly retrieve 
historical data for specific waterways andhelp determine 
the quality of material in that area. FY 1992 funds were 
used to initiate a joint effort with U.S. Geological Survey 
to collect existing sediment chemistry data for Boston 
Harbor and enter this information into GIS. Total costs 
for the FY were $11,985. Total costs to 30 September 
1992 are $11,985. 
49. PLANNING, ENGINEERING AND 
DESIGN 
Total costs for Planning, Engineering and Design 
were $1,417,907 for local protection studies for Saugus 
River and Tributaries, MA. 
50. PRECONSTRUCTION 
ENGINEERING AND DESIGN 
Preconstruction Engineering and Design costs were 
$635,889 for the navigation project at Boston, MA and 
$104,779 for the local protection project at Massachusetts 
Coastal, Roughans Point, Revere, MA. 
1-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
1. Aquatic Plant 
Control 
2. Boston Harbor, MA 
3. Cape Cod Canal, 
MA 
(Contributed 
Funds) 
4. Chatham (Stage) 
Harbor, MA 
(Contributed 
Funds) 
5. Connecticut River 
below Hartford, 
CT 
(Contributed 
Funds) 
6. Cuttyhunk Harbor, MA 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
12,000 
9,454 
10,000 
6,527 
- 10,000 
8,811 131,383 
88,,881111 113311,,338833 
- - 
5,338,954 4,812,428 
5,646,961 4,743,139 
70,392 833,430 
70,326 832,130 
54,622 59,443 
54,465 59,043 
3,420 
3,420 
7,298 
7,298 
1,000 
10,794 
571,000 
441,041 
14,029 
14,029 
1,000 
1,014 
293,496 
293,381 
599,000 24,526,974 41 
635,889 24,423,904 41 
43,836 10,201,709 42 
43,253 10,201,036 42 
- 21,798,322 1,2 
- 21,798,322 1,2 
4,785,446 5,078,637 116,925,083 
4,725,917 5,113,557 116,654,772 
- - 115,432 
- - 115,432 
- - 390,677 
- - 390,677 
- - 26,609,000 
- - 26,609,000 
- - 266,705 12 
- - 266,705 12 
168,240 
164,705 
839,332 
414,000 
16,080 
16,080 
17,441 3,730,501 s 
22,421 3,729,974 9 
- 43,500 
- 43,500 
- 1,541,185 7,8 
- 1,541,185 7,8 
361,156 16,545,369 4 
601,116 16,358,997 4 
60,000 
60,000 
130,410 
130,410 
27,168 
27,168 
136,680 1,214,647 43 
136,679 1,214,646 4a 
11,643 
11,643 
1-26

TABLE 1-A (Continued) 
NEW ENGLAND DIVISION 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
7. Green Harbor, 
MA 
(Contributed 
Funds) 
8. Guilford Harbor, CT 
(Contributed 
Funds) 
9. Hyannis Harbor, 
MA 
(Contributed 
Funds) 
10. Jonesport Harbor, 
ME 
(Contributed 
Funds--Required) 
11. Kennebec River, 
ME 
12. Newburyport Harbor, 
MA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
254,512 
254,512 
24,947 220,167 
25,356 218,910 
323,226 
323,422 
174,938 2,875,037 
127,210 2,826,058 
162,341 
162,341 
137,222 
137,222 
2,275 
2,275 
11,347 
550,000 
478,037 
25,216 
25,216 
15,049 
15,049 
293,172 
275,323 
-10,759 
-260,000 
2,792 
2,792 
33,000 
50,560 17,884 
78,995 1,385.429 
37,855 1,344,289 
- 25,500 
- 25,500 
- 24,700 
- 6,950 
484,137 
484,137 
911,617 s 
910,866 s 
103,363 
103,363 
-927 7,489,073 
- 7,489,073 
934 3,726 
934 3,726 
- 833,000 
- 832,119 
1,599,9406 
1,599,9406 
50,225 972,598 
50,225 972,379 
167,543 
167,606 
477,568 3,937,116 
477,509 3,936,901 
565,224 
565,224 
18,752 401,313 
18,752 374,789 
543,000 
567,405 
21,671 5,515,621 
23,081 5,514,546 
1,415,524 
1,415,524 
1-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
13. Portsmouth Harbor and 
Piscataqua River, 
ME and NH 
(Contributed 
Funds-Required) 
14. Saco River, ME 
(Contributed 
Funds-Required) 
15. Sesuit Harbor, MA 
(Contributed 
Funds) 
16. Wood Island Harbor and 
the Pool at Biddeford, ME 
(Contributed 
Funds) 
21. Revere Beach, MA 
(Contributed 
Funds) 
22. Roosevelt Campobello 
International Park, 
Lubec, ME 
23. Southeast Lighthouse, 
Block Island, RI 
24. Woodmont Beach, 
Milford, CT 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
4,400,000 5,676,000 
1,378,000 8,183,675 
40,157 
39,957 
1,000,000 
400,000 
32,863 
32,863 
3,500,000 
2,553,326 
368,000 2,327,927 18,456,228 10 
812,769 2,482,034 18,447,88810 
1,634 
1,634 
744,819 
141,345 2,173,248 
116,842 2,148,545 
- 4,599,707 
456,966 4,254,818 
1,064,983 
1,064,983 
81,007 
81,385 
-9,603 
1,158 
481,690 
481,344 
50,000 
105,664 
157,390 
31,829 
31,489 
14,976 
14,976 
530 
425 
3,450,000 
134,384 
2,293,000 
10,256 
40,000
- 
65,044 
65,490 
16,990 
16,990 
25,000 
550 
-10,904 
-10,064 
2,771,316 
1,260,000 
-5,000 
858 
190,000 
153,914 
46,386 
975,562 2,847,935 
456,051 2,328,317 
215,785 
159,379 
262,700 
37,049 
5,400 
5,400 
74,996 
74,996 
226,306 
226,306 
510,862 
454,456 
124,588 
124,588 
430,812 
180,711 
566,909 
566,909 
28,400 40,400 
- 12,000 
-400,000 3,858,712 13 
135,919 3,820,513 s13 
-144,000 2,291,965 
747,188 2,150,153 
634 
780,000 
48,784 
250,000 
20,277 
239,200 
228,335 
970,000 
202,698 
343,838 
120,501 
111,679 a 
111,679 4 
1-28

TABLE 1-A (Continued) 
NEW ENGLAND DIVISION 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
28A. West Hill Dam, 
MA 
29. Charles River 
(Natural Valley 
Storage Areas), MA 
30A. Ball Mountain 
Lake, VT 
30B. Barre Falls Dam, 
MA 
30C. Birch Hill Dam, MA 
(Contributed 
Funds) 
30D. Colebrook River 
Lake, CT 
30E. Conant Brook 
Dam, MA 
30F. Connecticut River, 
Middletown, CT 
30G. Connecticut River 
Basin Fish Passage 
Facilities for Townshend 
and Ball Mountain Lakes, 
West River, VT 
30H. Farmington River, 
Simsbury, CT 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
2,306,902 14 
2,306,902 14 
639,400 446,664 
690,987 381,399 
7,236 
495,700 
514,607 
43,066 
124,300 145,743 
127,825 125,039 
103,900 
114,090 
522,000 5,629,698 
533,639 5,584,606 
- 8,606,000 
- 8,606,000 
205,000 1,411,343 
209,982 1,399,376 
- 11,039,298 5s 
- 11,039,298 15 
418,700 432,684 
435,932 404,120 
451,400 463,933 
478,718 433,065 
476,400 601,502 
623,168 506,086 
130,800 287,383 
178,771 243,582 
105,900 
126,417 
45,000 
40,000 
4,540 
70,517 
45,810 
15,000 
56,274 
30,000 
23,646 
419,200 
420,098 
401,400 
388,071 
538,900 
484,120 
192,300 
208,495 
109,900 
123,252 
5,000 
5,884 
300,000 
157,602 
10,000 
42,648 
458,000 7,854,723 
468,128 7,830,161 
- 1,967,819 
- 1,967,819 
438,000 6,194,060 
431,956 6,127,565 
- 4,815,679 s16 
- 4,815,679 16 
566,000 6,795,429 
658,696 6,725,979 
- 32,000 17 
- 32,000 17 
- 14,263,971 
- 14,263,971 
321,000 3,549,027 
330,462 3,528,548 
- 2,950,530 
- 2,950,530 
76,000 1,654,197 
84,492 1,648,699 
10,000 
9,446 
640,000 
602,542 
2,079 
75,000 
71,604 
940,000 
760,144 
120,000 
112,939 
1-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
30I. Knightville Dam, 
MA 
30J. Littleville Lake, 
MA 
30K. North Hartland 
Lake, VT 
30L. North Springfield 
Lake, VT 
30M. Otter Brook 
Lake, NH 
30N. Riverdale, West 
Springfield, MA 
(Contributed 
Funds) 
300. Surry Mountain 
Lake, NH 
30P. Townshend Lake, 
VT 
30Q. Tully Lake, MA 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
507,500 371,742 
522,977 343,235 
621,500 
620,486 
- 3,415,640 18 
- 3,415,640 18 
580,000 7,783,446 
501,874 7,642,788 
7,013,412 
7,013,412 
561,200 312,836 
574,335 231,465 
- - 
433,900 442,728 
381,073 473,378 
1,196,369 
1,314,280 
466,983 
461,934 
260,000 
349,207 
346,300 
312,921 
445,500 
410,366 
271,000 5,232,927 
242,654 5,179,350 
- 7,312,22519 
- 7,312,22519 
470,000 6,028,543 
528,790 6,005,457 
- 6,831,52620 
- 6,831,52620 
589,000 10,189,449 
662,997 10,161,174 
4,360,44821 
4,360,44821 
456,600 394,583 
583,497 358,570 
15,000 
826 3,202 
330,000 363,648 
351,551 288,745 
421,900 
422,768 
1,047 
503,200 
475,904 
435,000 6,153,297 
455,920 6,135,592 
25,000 1,303,000 
13,279 1,280,670 
- 25,000 
- 25,000 
- 2,833,61022 
- 2,833,610" 
383,000 6,664,491 
475,776 6,653,286 
7,398,413 23 
7,398,413 23 
392,000 419,047 
402,749 385,736 
455,900 440,639 
452,772 383,216 
327,400 
346,364 
421,200 
483,014 
415,000 7,381,418 
400,839 7,321,621 
- 1,666,752 24 
- 1,666,752 24 
460,000 6,038,725 
456,312 6,013,012 
40,000 17 
40,000 17 
1-30

NEW ENGLAND DIVISION 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
30R. Union Village 
Dam, VT 
30S. West Springfield, 
MA 
(Contributed 
Funds) 
31A. Black Rock Lake, 
CT 
31B. Hancock Brook 
Lake, CT 
31C. Hop Brook Lake, 
CT 
31D. Northfield Brook 
Lake, CT 
31E. Thomaston Dam, 
CT 
32A. Blackwater Dam, 
NH 
32B. Edward MacDowell 
Lake, NH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
482,900 485,337 
474,338 292,022 
21,368 
12,390 
10,000 
10,218 
-86 
454,700 
520,111 
1,133 
2,200 
506,000 5,963,393 
545,910 5,845,447 
-5,272 1,798,452 5 
-2,039 1,798,452 s 
-857 
2,039 
14,343 
14,343 
8,182,300 
8,182,300 
272,300 234,572 
285,311 196,744 
271,300 
239,230 
280,000 3,613,581 
346,003 3,606,727 
4,178,911 
4,178,911 
87,900 145,385 
90,163 92,555 
129,900 
174,115 
132,000 1,751,934 
136,332 1,744,757 
6,151,562 26 
6,151,562 26 
920,300 
1,029,440 
834,840 
722,931 
1,768,800 1,067,000 9,971,325 
942,275 1,874,473 9,789,965 
2,850,512 27 
2,850,512 27 
158,500 282,597 
210,899 161,938 
349,400 362,175 
432,468 309,606 
323,300 238,909 
336,978 210,802 
341,400 329,177 
350,042 267,761 
410,300 
472,018 
445,400 
459,772 
220,200 
235,228 
320,900 
354,784 
448,000 3,307,708 
466,801 3,262,177 
- 14,282,112 
- 14,282,112 
513,000 6,969,342 
519,966 6,933,911 
- 1,319,746 28 
- 1,319,746 28 
365,000 4,469,094 
372,960 4,462,385 
- 2,014,253 29 
- 2,014,253 29 
277,000 5,320,569 
292,138 5,304,919 
1-31 
4,095,160 25 
4,095,160 25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
32C. Franklin Falls 
Dam, NH 
32D. Hopkinton-Everett 
Lakes, NH 
33. New Bedford, 
Fairhaven, and 
Acushnet, MA 
(Contributed 
Funds) 
34. New London, CT 
(Contributed 
Funds-Required) 
(Contributed 
Funds- Other) 
35. Roughans Point, 
Revere, MA 
36. Stamford, CT 
(Contributed 
Funds-Required) 
(Contributed 
Funds - Other) 
37A. Buffumville Lake, 
MA 
37B. East Brimfield 
Lake, MA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
561,500 439,123 
556,450 396,856 
611,000 
641,213 
- 7,950,487 3 
- 7,950,487 30 
945,000 8,685,382 
834,456 8,555,998 
- - - - 21,452,440 31 
- - - - 21,452,440 s31 
817,400 817,308 1,228,100 1,111,000 11,551,570 
962,420 685,643 1,091,214 1,243,716 11,406,245 
- - - - 11,510,088 
- - - - 11,510,088 
193,400 636,257 
173,421 562,783 
4,726 
422,200 
380,424 
85,000 
9,094 
245,000 -15,000 
116,622 290,741 
195,700 238,719 
209,717 186,438 
205,700 321,394 
214,535 298,391 
339,300 472,156 
355,006 346,595 
100,000 
113,329 
439,700 
340,563 
341,300 
347,133 
374,900 
400,740 
240,400 5,292,821 
299,281 5,208,205 
151,583 
-81,001 
-235,584 
81,001 
84,001 
230,000 
104,779 
6,513,763 32 
6,513,763 32 
8,504,919 44 
8,504,919 44 
2,173,999 33 
2,015,709 33 
303,251 
303,251 
975,779 
849,309 
9,911,300 
9,900,640 
446,000 4,016,191 
497,172 3,912,102 
- 3,367,970 34 
- 3,367,453 34 
- 210,000 
- 209,969 
- 2,998,603 ** 
- 2,998,603 * 
553,000 4,953,016 
521,885 4,902,796 
7,057,043 " 
7,057,043 36 
343,000 4,516,439 
435,671 4,508,161 
1-32

TABLE 1-A (Continued) 
NEW ENGLAND DIVISION 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sep. 30, 1992 
37C. Hodges Village 
Dam, MA 
37D. Mansfield Hollow 
Lake, CT 
37E. West Thompson 
Lake, CT 
37F. Westville Lake, 
MA 
38. Town Brook, Quincy 
and Braintree, MA 
(Contributed 
Funds) 
39. Town River Bay, 
Quincy, MA 
(Contributed 
Funds) 
40. West River, New 
Haven, CT 
(Contributed 
Funds-Required) 
(Contributed 
Funds-Not Required) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
4,461,268 37 
4,461,268 37 
510,200 1,642,659 
496,116 1,656,803 
390,100 
362,869 
361,000 6,809,947 
387,547 6,795,595 
6,447,164 38 
6,447,164 38 
309,500 309,102 
331,485 273,978 
375,500 
388,355 
523,000 5,211,599 
399,276 5,059,611 
7,001,220 39 
7,001,220 3 
404,100 407,399 
425,327 385,655 
257,100 352,663 
304,048 331,714 
550,000 
509,110 
400,000 
359,252 
31,000 
30,972 
25,000 
34,747 
419,800 
436,725 
327,000 
313,840 
175,000 
268,427 
2,102 
563,000 5,814,997 
546,909 5,780,964 
- 5,684,683 40 
- 5,684,683 40 
328,000 5,069,059 
359,577 5,062,618 
746,000 2,741,740 
198,271 2,174,020 
144,000 
26,500 
19,502 
144,000 
57,500 
52,576 
- 23,750 - 23,750 
- - 17,200 17,200 
190,000 1,300,000 1,900,000 3,985,000 
84,849 1,284,991 1,821,672 3,781,046 
822,000 
94,400 
9,764 
154,629 
100 
317,036 
47,371 
822,000 
471,665 
94,400 
57,235 
'Excludes $ 6,138,157 from Public Works Funds and 
$4,849,740 from Emergency Relief Funds. 
2 Includes $389,929 Code 711 funds and $511,089 
Code 713 funds. 
3 Excludes $129,757 expended for rehabilitation; 
breakwater repaired 1961. 
4 Includes $366,348 for previous projects. 
6 Includes $245,000 Public Works Funds. 
6 Includes $509,411 for previous projects. 
' Includes $287,374 for previous projects and excludes 
$9,000 for subproject "Eightmile River, CT." 
8 Excludes $60,000 expended for major 
rehabilitation. 
9 Includes $83,276 for maintenance of previous 
project.
o1I0n cludes $130,390 for previous projects. 
" Includes $12,000 for previous project. 
12 Includes $7,889 for previous project. 
13 Excludes $73,800 for previous project. 
14 Includes $18,310 Code 711 funds. 
1-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-A (Continued) COST AND FINANCIAL STATEMENT 
15 Includes $504,062 Code 711 funds. 
16 Includes $618,469 Code 711 funds and $32,000 
Code 713 funds. 
17 Recreational cost sharing. 
18 Includes $199,303 Code 711 funds. 
19 Includes $229,436 Code 711 funds. 
20 Includes $59,536 Code 711 funds. 
21 Includes $364,688 Code 711 funds. 
SIncludes $470,077 Code 711 funds. 
* Includes $245,168 Code 711 funds. 
24 Includes $3,695 Code 711 funds and $115,138 Code 
713 funds. 
SIncludes $88,931 Code 711 funds. 
26 Includes $143,538 Code 711 funds. 
27 Includes $20,000 Code 711 funds. 
28 Includes $2,881 Code 711 funds. 
9 Includes $6,432 Code 711 funds. 
3 Includes $4,671 Code 711 funds. 
31 Includes $179,727 Code 711 funds. 
32 Cash for construction only. Excludes $146,020 
expended to date for land condemnation. 
33 Excludes $27,961 expended to date for land 
condemnations. Cash for construction only; excludes 
$1,629,256 for lands. 
SCash for construction only. Excludes $199,410 
expended to date for land condemnations. 
Includes $71,943 Code 711 funds. 
Includes $207,700 Code 711 funds. 
7 Includes $6,255 Code 711 funds and $40,353 Code 713 
funds. 
Includes $68,717 Code 711 funds. 
Includes $315,420 Code 711 funds. 
4Includes $67,667 Code 711 funds. 
41 Includes $1,465,123 for previous projects. Excludes 
$935,303 Emergency Relief Funds and $1,030,806 Public 
Works Funds. 
42 Includes $17,879 for previous projects. Excludes 
$17,767 Contributed Funds. 
4Excludes $50,000 Contributed Funds expended for 
maintenance. 
Excludes $852,127 non project cost per 1976 WRDA. 
4Excludes $118,215 expended for work beyond scope of 
project. 
1-34

NEW ENGLAND DIVISION 
TABLE 1-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1825 
June 14, 1880 
Aug. 5, 1886 
Sep. 19,1890 
July 25, 1892 
July 13, 1892 
June 3, 1896 
Mar. 3, 1899 
June 13,1902 
July 25, 1912 
Aug. 8, 1917 
Aug. 30,1935 a 
Do. 
Aug. 26, 1937 
Oct. 17, 1940 
Sep. 7, 1940 
July 24,1946 
July 3, 1958 
Oct. 23, 1962 
Nov. 28, 1990 
AQUATIC PLANT CONTROL (See Section 1 of Text.) 
Control and progressive eradication of obnoxious Aquatic Plant 
growths from the waters and streams in the U.S. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BOSTON HARBOR, MA (See Section 2 of Text.) 
Preservation of islands and seawalls. 
Wier River (Nantucket Beach Channel) 9.5 ft. deep, 100 ft. wide 
to Steamboat Wharf at Nantasket. 
Fort Point Channel.4 
Wier River (Nantucket Beach Channel) 9.5 ft. deep, 150 ft. 
wide to Steamboat Wharf at Nantasket. 
Wier River (Nantucket Beach Channel) from mouth of 
Wier River to Steamboat Wharf at Nantasket Beach 
12 ft. deep, 150 ft. wide. 
Channel 15 feet deep from Long Island to Nixes Mate 
Shoal (Nixes Mate to Nubble Channel). 
Channel 27 feet from Nantasket Roads to President Roads. 
Dredge Chelsea River channel to 18 feet. 
For 30-foot channel from sea to President Roads 
through Broad Sound by less direct route than 35 
and 40-foot channels. 
For 35-foot channel from sea to Boston Naval Shipyard, 
Chelsea and Charles River Bridges. 
Elimination from project of removal of Finns Ledge at 
outer entrance. 
Dredge Chelsea River channel 25 ft. 
Depth of 40 feet (45 feet in rock) in Broad Sound Channel. 
Present project dimensions of channel from President 
Roads to Commonwealth pier No. 1, East Boston and 
anchorage area north side of President Roads. 
Present project dimensions of that part of approach 
channel to U.S. Navy drydock No.3 at South Boston 
between Main Ship Channel and U.S. harbor line. 
Chelsea River, channel 30 feet deep. 
Reserved channel 30 feet deep. 
Abandons seaplane channel authorized in 1940 River 
and Harbor Act (H.Doc.262,76th Cong., 1st sess.) 
Extension of President Roads anchorage. 
Reserved channel 35 feet deep, 430 feet wide, extending one 
mile from 40-foot main channel to L Street. 
Chelsea River Channel and Maneuvering Basin 35 feet deep. 
Deepen Mystic River and Reserved Channels to 40 feet; 
Chelsea River Channel to 38 feet; widen and deepen Inner 
Confluence Area to 40 feet. 
H. Doc. 37, 85th Cong., 1st sess. 
Public Law 87-874, 87th Cong. 
H. Doc. 251, 89th Cong. 
Annual Report, 1881, p. 518 
H. Ex.Doc. 206,48th Cong., 2nd sess. 
Annual Report, 1885, p. 543. 
Annual Report, 18 9 0,p. 503 
Annual Report, 1893, p. 769 
Annual Report, 1887, p.517 
Annual Report, 1893, p. 766 
H. Ex. Doc. No. 162,53rd Cong., 3rd 
sess.,Annual Report, 1895, p. 648 
H. Doc. 133, 55th Cong., 2nd sess. 
Annual Report, 1898, p. 886. 
H. Doc. 119, 56th Cong., 2nd sess. 
Annual Report, 1901, p. 1096 
Authorized by Chief of Engineers. 
Mar. 11,1913. 
H. Doc. 272, 62nd Cong., 2nd sess.2 
H. Doc. 931, 63rd Cong., 2nd sess.2 
H. Doc. 244, 72nd Cong., 1st sess. 2 
Rivers and Harbors Committee 
Doc. 29, 74th Cong., 1st sess. 2 
Rivers and Harbors Committee 
Doc. 24, 75th Cong., 1st sess. 2 
H. Doc. 225, 76th Cong., 1st sess.2 
Public Law 420,78th Cong. 
H. Doc. 244, 80th Cog., 1st sess. 2 
H. Doc. 349, 84th Cong., 2nd sess.2 
H. Doc. 350, 87th Cong., 2nd sess. 2 
Section 101, Public Law 101-640. 
1-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jan. 21, 1927 
(Section 2) 
Included in Public 
Works Administration 
program, 
Sep. 6, 1933 
June 26, 1934 
(Permanent 
Appropriations 
Repeal Act) 
Included in Public 
Works 
Administration 
Program Apr. 29, 
1935 
Included in 
Emergency Relief 
Program, May 28, 
1935. 
Aug. 30, 1935 
Mar. 2, 1945 
July 3, 1958 
Mar. 2, 1945 
June 10, 1872 
Mar. 3, 1881 
June 25, 1910 
Feb. 27, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
May 24, 1937 
Mar. 2, 1945 
July 14, 1960, 
as amended 
CAPE COD CANAL, MA (See Section 3 of Text.) 
Purchase canal from Boston, Cape Cod & New York 
Canal Co., in accordance with contract dated July 29, 1921, 
executed by that company. 
Construct three bridges and widen canal to 250 feet. 
Operation and care of works of improvement provided for the 
funds from War Department appropriations for rivers and 
harbors. 
Construct a mooring basin. 
Dredging and bank protection. 
Existing project for main canal adopted. 
15-foot channel and turning basin in Onset Bay. 
Extend East Boat Basin for an area of about 4.3 acres to a 
depth of eight feet. 
CHATHAM (STAGE) HARBOR, MA 
(See Section 4 of Text.) 
Entrance channel ten feet deep, 150 feet wide from Chatham 
Roads into upper harbor. 
CONNECTICUT RIVER BELOW HARTFORD, CT 
(See Section 5 of Text.) 
Jetties at mouth 
The Hartford dike 
Channel and turning basin in Eightmile River. 
Present project dimensions of channel over Saybrook Bar. 
Dikes, training walls, and revetments. 
Present project dimensions of channel and additional dikes, 
training walls, revetments, and accessory works. 
Park River declared nonnavigable. 
Channel and anchorages, North Cove, Old Saybrook. 
Channel and anchorage in Essex Cove. 
Channel and anchorage in Wethersfield Cove. 
H. Doc. 139, 67th Cong., 2nd sess. 
H. Doc. 795, 71st. Cong., 3rd sess. 
Do. 
Do. 
Do. 
Rivers and Harbor Committee 
Doc. 15, 74th Cong., 1st sess. 
H. Doc. 431, 77th Cong., 1st sess. 
H. Doc. 168, 85th Cong., 1st sess. 
H. Doc. 456, 77th Cong., 1st sess. 
Annual Report 1942. 
Present project dimensions approved 
by Chief of Engineers, 
December 22, 1887. 
Present project dimensions authorized 
by Chief of Engineers in 1889. 
H. Doc. 327, 60th Cong., 1st sess. 
H. Doc. 1294, 61st Cong., 3rd sess. 
H. Doc. 132, 65th Cong., 1st sess.' 
H. Doc. 49, 73rd Cong., 1st sess. 
Ltr. Sec. War, April 21, 1937. 
H. Doc. 368 76th Cong., 1st sess.' 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
October 18, 1961. 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
November 15, 1960. 
1-36

NEW ENGLAND DIVISION 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 26, 1937 
July 14, 1960, 
as amended 
Mar. 2, 1945 
Mar. 2, 1827 
July 11, 1871 
Aug. 5, 1886 
Mar. 2, 1945 
Oct. 27, 1965 
June 13, 1902 
Mar. 2, 1907 
Mar. 4, 1913 
Oct. 17, 1940 
June 14, 1880 
June 25, 1910 
Sep. 3, 1954 
Oct. 23, 1962 
July 14, 1960, 
as amended 
Nov. 16, 1986 
CUTTYHUNK HARBOR, MA (See Section 6 of Text.) 
Channel 10 feet deep, 75 feet wide. 
Anchorage 10 feet deep, 900 feet long, 800 feet wide. 
Maintenance of existing jetties and stone dikes. 
GREEN HARBOR, MA (See Section 7 of Text.) 
Channel six feet deep, 100 feet wide from deep water to head of 
navigation; anchorage near town pier; sealing, rebuilding in 
part and extension of existing west jetty. 
GUILFORD HARBOR, CT (See Section 8 of Text.) 
Entrance channel 100 feet wide, 6 feet deep; a channel 60 
feet wide, 6 feet deep; an anchorage basin 6 feet deep, 
200 feet wide. 
HYANNIS HARBOR, MA (See Section 9 of Text.) 
Breakwater. 
Present dimensions of breakwater. 
Dredging behind breakwater. 
Channel, anchorage and jetty. 
JONESPORT HARBOR, ME (See Section 10 of Text.) 
A steel sheet pile breakwater 1200 feet in length. 
A 15-acre anchorage composed of nine acres six feet deep and 
six acres eight feet deep. 
An entrance channel 100 feet wide and eight feet deep. 
KENNEBEC RIVER, ME (See Section 11 of Text.) 
Channel between Augusta and Gardiner, ME. 
Channel below Gardiner, ME. 
Channel west of Swan Island, ME. 
27-foot channel from mouth of Bath, ME. 
NEWBURYPORT HARBOR, MA (See section 12 of Text.) 
Construction of rubblestone jetties. 
Dredging the bar at entrance to harbor. 
PORTSMOUTH HARBOR & PISCATAQUA RIVER, 
ME and NH (See Section 13 of Text.) 
Removal of ledge rock; widening 35-foot channel; extending 
channel and maneuvering basins above Boiling Rock and at 
head of project. 
Modified existing project for widening and extending 
35-foot channel. 
Construct six-foot channels and anchorages. 
Widen 35-foot channel to 1,000 feet between two vertical lift 
bridges; widen northern limit of 35-foot channel by 100 feet 
and widen southern limit to 550 feet at Goat Island. 
H. Doc. 81, 75th Cong., 1st sess. 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
December 15, 1965. 
H. Doc. 149, 77th Cong., 1st sess. 
S. Doc. 32, 18th Cong., 2nd sess. 
H. Doc. 63, 41st Cong., 2nd sess. 
H. Ex. Doc. 96, 48th Cong. 2nd sess. 
H. Doc. 98, 77th Cong., 1st sess.' 
H. Doc. 481, 94th Cong., 2nd sess. 
Authorized by H. Res. September 23, 
1976 and S. Res. October 1, 1976 
pursuant to Section 201 of cited 
Act. 
H. Doc. 262, 56th Cong., 1st sess.1 
H. Doc. 321, 59th Cong., 2nd sess. ' 
H. Doc. 746, 62nd Cong., 2nd sess. ' 
S. Doc. 55, 77th Cong., 1st sess.' 
Annual Report 1910, p. 59. 
Annual Report 1892. H. Doc. 556, 
82nd Cong., 2nd sess. 
H. Doc. 482, 87th Cong., 2nd sess. 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
December 23, 1965. 
Section 202, P.L. 99-662. 
1-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1827 
June 23, 1866 
Sep. 19, 1890 
June 25,1910 
Mar. 3, 1925 
Aug. 30, 1935 
July 14, 1960, 
as amended 
July 14, 1960, 
as amended 
May 17,1950 
July 14, 1960, 
as amended 
Sep. 3, 1954 
Oct. 27, 1965 
July 7,1964 
Nov. 28, 1990 
Sep. 3, 1954 
Oct. 23, 1962 
SACO RIVER, ME (See Section 14 of Text.) 
Extension of piers, placing bouys, and removal of obstruction 
at entrance to harbor. 
Breakwater on north side of mouth of river. 
Jetty on north side or mouth of river. 
Channel improvements and jetty extension on south side of 
mouth of river. 
Present project channel dimensions and extensions of north 
breakwater about 1,600 feet. 
Extension of north breakwater to Sharps Ledge. 
Anchorage and maneuvering basin. 
SESUIT HARBOR, MA (See Section 15 of Text.) 
Channel 6 feet deep and 100 feet wide. 
WOOD ISLAND HARBOR and the POOL at 
BIDDEFORD, ME (See Section 16 of Text.) 
Dredged basin 6 feet deep and construction of three ice 
breakers. 
Channel 4,200 feet long, 100 feet wide and 10 feet deep. 
REVERE BEACH, MA (See Section 21 of Text.) 
Placement of sandfill for protection and improvement. 
Raising and widening of about 13,000 feet of beach by 
placement of sandfill. 
ROOSEVELT CAMPOBELLO INTERNATIONAL PARK 
LUBEC, ME (See Section 22 of Text.) 
Stone slope protection for the lighthouse at Mulholland Point. 
SOUTHEAST LIGHTHOUSE, BLOCK ISLAND, RI 
(See Section 23 of Text.) 
Relocate the lighthouse approximately 200 feet north of its 
present location. 
WOODMONT BEACH, MILFORD, CT 
(See Section 24 of Text.) 
Widening to 100-foot width by direct placement of sand, 
500 feet of shore west of Merwin Point; widening 
3,500 feet of shore from Chapel Street; and 
construction of 5 impermeable groins. 
Placement of suitable sandfill along approximately 1,500 feet 
of beach. Reconstruction of groins. Mitigation to replace 
rocky habitat for Blue Mussels. 
S. Ex. Doc. 44, 48th Cong., 1st sess. 
and Annual Report 1884, p. 482 
H. Doc. 752, 61st Cong., 2nd sess. 1 
H. Doc. 477, 68th Cong., 2nd sess. 
Rivers and Harbors Committee 
Doc. 11, 74th Cong., 1st sess. 1 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
November 14, 1967. 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
February 6, 1980. 
H, Doc. 49, 81st Cong., 1st sess. 
Section 107, P.L. 86-645. Authorized 
by Chief of Engineers, 
October 18, 1990. 
H. Doc. 146, 82nd Cong., 1st sess. 
H. Doc. 211, 91st Cong., 2nd sess. 
Authorized by H. Res. December 15, 
1970 and S. Res. December 17, 
1970 pursuant to Section 201 of 
1965 Flood Control Act. 
Roosevelt Campobello International 
Park Act, P.L. 88-363. 
Section 416, P.L. 101-640. 
H. Doc. 203, 83rd Cong., 1st sess. 
Section 103, P.L. 101-640. Authorized 
by Chief of Engineers, 
March 30, 1992. 
1-38

TABLE 1-B (Continued) 
NEW ENGLAND DIVISION 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
CHARLES RIVER (NATURAL VALLEY STORAGE 
Mar. 7. 1974 
July 24, 1946, 
as amended 
Nov. 16, 1986 
July 24, 1946, 
as amended 
Aug. 18, 1941 
June 30, 1948, 
as amended 
June 28, 1938 
June 30, 1948, 
as amended 
July 3, 1958 
Oct. 23, 1962 
Oct. 22, 1976 
AREAS), MA (See Section 29 of Text.) 
Federal acquisition and perpetual protection of 17 crucial 
natural valley storage areas totalling 8,422 acres in what 
is known as the Middle and Upper watershed of the 
Charles River. 
CONNECTICUT RIVER, MIDDLETOWN, CT 
(See Section 30F of Text.) 
Bank protection of 500 linear feet with 6-inch concrete 
paving block and riprap toe protection. 
CONNECTICUT RIVER BASIN FISH PASSAGE 
FACILITIES FOR TOWNSHEND AND BALL MOUNTAIN 
LAKES, WEST RIVER, VT (See Section 30G of Text.) 
Construct fish passage facilities along the West River 
in Vermont. 
FARMINGTON RIVER, SIMSBURY, CT 
(See Section 30H of Text.) 
Bank protection by clearing and grubbing existing slope and 
refilling eroded areas with compacted granular fill. 
RIVERDALE, WEST SPRINGFIELD, MA 
(See Section 30N of Text.) 
Approximately 12,700 feet of earth levee, two pumping 
stations and three stop-log storage structures. 
Construct improvements to existing pumping station 
and gravity outflow channel. 
WEST SPRINGFIELD, MA (See Section 30S of Text.) 
A system of earth levees and concrete floodwalls approx. 24,500 
feet long. Work involves raising 13,700 feet of existing 
levee; constructing 2,300 feet of floodwall; improving 2,400 
feet of river bank; treating 6,100 feet of existing levee 
foundation. Three pumping stations with appurtenant drainage 
facilities also constructed. 
Raise the floodwall section of the West Springfield project by 
one foot in combination with a flood forecasting system. 
NEW BEDFORD, FAIRHAVEN AND ACUSHNET, 
MA (See Section 33 of Text.) 
Hurricane barriers in New Bedford Harbor. 
NEW LONDON, CT (See Section 34 of Text.) 
Hurricane barrier protecting city of New London from tidal 
damage. 
Chief of Engineers report dated 
December 6, 1972. 
Section 14, P.L. 79-526. Authorized 
by Chief of Engineers, 
December 17, 1991 
Section 872, P.L. 99-662. 
Section 14, P.L. 79-526. Authorized 
by Chief of Engineers, 
September 27, 1988. 
H. Doc. 724, 76th Cong., 3rd sess. 
Section 205, P.L. 80-858. Authorized 
by Chief of Engineers, 
June 13, 1986. 
H. Doc. 455, 75th Cong., 2nd sess. 
Section 205, P.L. 80-858. Authorized 
by Chief of Engineers, 
October 5, 1982. 
S. Doc, 59, 85th Cong., 1st sess. 
H. Doc. 478, 87th Cong., 2nd sess. 
1-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
ROUGHANS POINT, REVERE, MA (See Section 35 of Text.) 
Nov. 16, 1986 Stabilize existing facilities along the shore with a 4,080-foot Section 401, P.L. 99-662. 
long armor stone revetment. Construct earth berm one-foot high 
and 200 feet long on existing median strip between Bennington 
Street and State Road. 
STAMFORD, CT (See Section 36 of Text.) 
July 14, 1960 Hurricane barrier protecting areas of Stamford from H. Doc. 210, 86th Cong., 1st sess. 
tidal damage. 
TOWN BROOK, QUINCY & BRAINTREE, MA 
(See Section 38 of Text.) 
Nov. 17, 1986 Construct 12-foot diameter, 4,060-foot long, concrete lined H. Doc. 39, 99th Cong., 1st sess. 
tunnel in bedrock approximately 190 feet below ground. 
TOWN RIVER BAY, QUINCY, MA 
(See Section 39 of Text.) Section 14, P.L. 79-526. Authorized 
July 24, 1946, Stone revetment approximately 280 feet long and 15 feet high. by Chief of Engineers, 
as amended August 16, 1990. 
WEST RIVER, NEW HAVEN, CT (See Section 40 of Text.) 
June 30, 1948, Widen river for 1,150 feet to 50-70 feet. Widen the Wintergreen Section 205, P.L. 80-858. Authorized 
as amended Brook channel to 20-30 feet. Construct recreational walkway by Secretary of the Army, 
connecting two existing city parks. September 26, 1988. 
Contains latest maps. 
2 Contains latest published maps. See also Annual Report, 1911, p. 1178 
(seawalls and Nixes Mate Channel) and Annual Report, 1903, p. 770 
(Fort Point Channel.) 
3Authorized in part by Public Works Administration, September 6, 1933. 
4A portion has been abandoned pursuant to P.L. 91-624, December 31, 1970. 
1-40

NEW ENGLAND DIVISION 
TABLE 1-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full 
Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Andrews River, MA"6,"5 
Apponaug Cove, RI' 
Bagaduce River, ME"4 ,5 
Bar Harbor, ME1' 
Bass Harbor, ME ', 
Bass Harbor Bar, ME' 
Beals Harbor, ME' 
Belfast Harbor, ME' 
Bellamy River, NH"s,4 
Beverly Harbor, MA' 
Black Rock Harbor, CT' 
Boothbay Harbor, ME' 
Branford Harbor, CT' 
Bridgeport Harbor, CT' 
Bristol Harbor, Bristol, RI 8 
Bucks Harbor, Machiasport, ME ,6 
Bucksport Harbor, ME' 
Bullocks Point Cove, RI' 
Bunker Harbor, ME"6 
Buttermilk Bay Channel, MA' 
Camden Harbor, ME' 
Canapitsit Channel, MA"4 
Cape Porpoise Harbor, ME' 
Carvers Harbor, Vinalhaven, ME' 
Cathance River, ME"' 
Clinton Harbor, CT' 
Coasters Island Harbor, RI" 4 
Cobscook Bay, ME"3"4 
Cocheco River, NH s,4 
Cohasset Harbor, MA' 
Corea Harbor, Gouldsboro, ME ,6 
Criehaven Harbor, ME' 
Cross Rip Shoals Nantucket Sound, MA' 
Damariscotta River, ME",4 
Deer Island Thoroughfare, ME",4 
Dorchester Bay and Neponset River, MA" 
Duck Island Harbor, CT' 
Duxbury Harbor, MA' 
East Boothbay Harbor, ME' 
Edgartown Harbor, MA' 
Essex River, MA' 
Exeter River, NH",4 
Fall River Harbor, MA'5 
Falmouth Harbor, MA' 
Fivemile River Harbor, CT 5 
Frenchboro Harbor, ME' 
Georges River, ME' 
Gloucester Harbor and Annisquam River, 
MA' 
Great Salt Pond, Block Island, RI 5 
Greenwich Bay, RI' 
Greenwich Harbor, CT' 
Hampton Harbor, NH"6 
Harbor of Refuge, Block Island, RI' 
Harraseeket River, ME",4 
1990 
1964 
1912 
1932 
1965 
1920 
1959 
1971 
1897 
1951 
1988 
1953 
1990 
1983 
1987 
1976 
1907 
1979 
1969 
1985 
1960 
1899 
1977 
1964 
1884 
1985 
1911 
1866 
1913 
1979 
1984 
1939 
1954 
1906 
1916 
1968 
1953 
1978 
1953 
1978 
1948 
1913 
1984 
1978 
1969 
1978 
1978 
1983 
1989 
1893 
1969 
1988 
1990 
1896 
$ 219,042 
156,874 2 
28,000 
406,591 
188,859 
4,076 
184,880 
61,561 32 
34,643 
246,048 
18,000 
9,537 
4,491,119 4 
316,288 
277,420 
18,421 
170,902 
95,372 
163,855 
102,400 
9,113 
175,037 
147,438 
21,000 
191,406 
5,500 
4,173 
119,089 
267,737 38 
795,253 
40,776 
24,200 
5,000 
40,000 
94,584 
482,166 
421,297 29 
6,500 
65,614 
21,759 
62,454 9 
6,164,757 40 
123,763 
35,490 
657,345 
25,788 
1,296,934 36 
189,037 
2,000 
198,758 
200,000 
576,856 
30,963 
$ 619,438 
42,189 
39 
2,187 
21,995 
12,175 
132,289 
260,952 
23,808 
1,633,728 
33,543 
1,925,607 
2,090,576 50 
16,838 
20,833 
268,369 
28,406 
220,563 46 
152,411 
12,279 
347,865 
24,465 
1,043,938 
13,161 
42,617 
313,953 
83,243 
10,117 
54,328 
905 
5,376 
362,224 
399,546 
881,239 
17,238 
62,980 
83,938 14 
3,032 
2,064,767 34 
331,187 
188,802 
24,616 
263,899 
1,570,626 
578,321 
6,527 
204,872 
2,170,817 
1,735,562 
5,309 
$ 187,500 
100,000 
147,887 
123,757 
69,323 
20,000 
111,289 
35,000 30 
10,000 
35,000 
25,000 
100,000 
193,761 
1-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full 
Report Contributed 
See Annual Operation and Funds Expend. 
Project Report for Construction Maintenance (Construction 
Hay (West Harbor), Fisher's 
Island, NY' 
Hendrick's Harbor, ME' 
Hingham Harbor, MA' 
Housatonic River, CT 5 
Ipswich River, MA' 
Island End River, Chelsea, MA '" 
Isle Au Haut Thoroughfare, ME' 
Isle of Shoals Harbor, ME and NH' 
Josias River, ME' 
Kennebunk River, ME' 
Kingston Harbor (North Plymouth), MA' 
Lagoon Pond, Martha's Vineyard, MA'" 
Lamprey River, NH"4 
Little Harbor, NH' ,4 ,2
6 
Little Harbor, Woods Hole, MA' 4 
Lubec Channel, ME' 
Lynn Harbor, MA' 
Machias River, ME' 
Malden River, MA' 20 
Matinicus Harbor, ME' 
Medomak River, ME' 
Menemsha Creek, MA' 
Merrimack River, MA' 
Mianus River, CT' 
Milford Harbor, CT 522 
Moosabec Bar, ME' 
Mystic River, CT' 
Mystic River, MA' 
Nantucket (Harbor of Refuge), MA' 
Narraguagus River, ME' 
New Bedford and Fairhaven 
Harbors, MA' 
New Harbor, ME' 
New Haven Breakwater, CT' 
New Haven Harbor, CT' 
New London Harbor, CT' 
Newport Harbor, RI' 
Niantic Bay and Harbor, CT 1,6 
' 
Northeast Harbor, ME' 
Norwalk Harbor, CT' 
Owl's Head Harbor, ME "3 
Patchogue River, CT 1,22 
Pawcatuck River, Little Narragansett 
Bay and Watch Hill Cove, RI & CT' 
Pawtuxet Cove, RI' 
Penobscot River, ME' 
Pepperell Cove, ME 5 
Pig Island Gut, ME' 6 
Pleasant River, ME' 
Plymouth Harbor, MA' 
Point Judith Pond and Harbor of 
Refuge, RI' 
Pollock Rip Shoals, Nantucket 
Sound, MA ' 
Portland Harbor, ME' 
1931 
1957 
1954 
1983 
1969 
1983 
1980 
1977 
1977 
1985 
1895 
1976 
1913 
1977 
1906 
1956 
1956 
1972 
1922 
1962 
1953 
1981 
1940 
1985 
1989 
1930 
1957 
1986 
1989 
1969 
1953 
1966 
1950 
1990 
1986 
1953 
1972 
1954 
1983 
1968 
1984 
1978 
1975 
1985 
1969 
1966 
1892 
1990 
1991 
1956 
1985 
$ 8,401 
28,204 
28,316 
859,691 
5,618 
311,850 
137,653 
80,691 
115,565 
350,334 
8,940 
99,098 
19,980 
133,227 
18,000 
380,322 
755,576 
32,000 
104,853 
14,000 21 
17,000 
56,926 
369,891 
132,435 
90,506 3' 
11,400 
197,582 
3,222,777 
502,661 58 
821,144 
1,857,618 
118,620 24 
1,242,246 
4,423,162 62 
638,774 17 
733,524 
66,464 
138,942 
531,129 39 
124,158 
351,181 
318,787 28 
295,356 
501,020 
171,351 
191,753 
3,500 
2,127,218 52,53 
2,714,510 19 
1,083,504 
9,588,710 27 
$ 38,462 
6,325 
166,800 
2,496,878 
32,947 
180,786 
651,644 
125,573 
1,243,802 
28,064 
33,563 
266,119 
13,144 
23,941 
216,321 
222,352 
45,097 
8,989 
92,359 
716,094 
322,685 
659,390 
1,349,790 56 
25,227 
143,385 
2,008,406 
742,106 
102,327 
708,967 
28,611 
40,273 
14,353,389 55 
1,851,070 
145,023 
111,789 
51,047 
3,822,092 42 
13,867 
693,299 
662,713 
173,547 
951,886 
46,882 
86,456 
217 
1,360,832 54 
6,163,374 33 
846,590 
7,940,340 
$ 
222,010 
192,336 48 
26,813 
88,917 
80,990 
62,000 
12,500 
46,500 
11,380 5' 
14,000 
20,385 
7,015 
65,139 
34,500 
4,383 
156,694 
20,000 
295,356 
541,611 
17,587 
1-42

NEW ENGLAND DIVISION 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full 
Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
Potowomut River, RI1 
Providence River and Harbor, RPI 
Provincetown Harbor, MA5 
Red Brook Harbor, Bourne, MAs ,8 
Richmond Harbor, ME",4 
Richmond's Island Harbor, ME",4 
Rockland Harbor, ME1 
Rockport Harbor, ME' 3 
Rockport and Old Harbors, 
Rockport, MA' 
Rockport Harbor and Pigeon Cove, 
Rockport, MA' 
Royal River, ME ,6 
Rye Harbor,NH' 
St. Croix River, ME' 
Sakonnet Harbor, RI' 
Sakonnet River, RpI" 0o 
Salem Harbor, MA' 
Sandy Bay (Harbor of Refuge), 
Cape Ann, MA'8 
Sasanoa River, ME" 4 
Scarboro River, ME' 
Scituate Harbor, MA' 
Searsport Harbor, ME' 
Seekonk River,RI' 
South Bristol Harbor, ME' 
Southport Harbor, CT' 
Southwest Harbor, ME' 
Stamford Harbor, CT' 
Stockton Harbor, ME" 3,4 
Stonington Harbor, CT' 
Stonington Harbor, ME'6 
Stony Creek, Branford, CT ,6 
Sullivan Falls Harbor, ME' 
Taunton River, MA' 
Tenants Harbor, ME' 
Thames River, CT' 
Union River, ME 3"' 
Vineyard Haven, MA' 
Wareham Harbor, MA' 
Warren River, RI' 
Warwick Cove, RI ,6 
Wellfleet Harbor, MA' 
Wells Harbor, ME' 
Westcott Cove, CT' 
Westport Harbor and 
Saugatuck River, CT5 
Weymouth Back River, MA' 
Weymouth-Fore & Town 
Rivs., MA" 
Wickford Harbor, RI"' 
Wilson Point Harbor, CT"4 
Winnipesaukee Lake, NH' 
Winter Harbor, ME",6 
Winthrop Harbor, MA' 
Woods Hole Channel, MA' 
1882 
1990 
1985 
1972 
1883 
1882 
1976 
1989 
1986 
1989 
1986 
1991 
1950 
1983 
1909 
1969 
1922 
1915 
1976 
1971 
1966 
1954 
1971 
1962 
1962 
1980 
1915 
1959 
1985 
1978 
1914 
1948 
1920 
1967 
1912 
1943 
1896 
1890 
1975 
1981 
1991 
1978 
1972 
1944 
1979 and 1983 
1973 
1895 
1952 
1976 
1895 
1940 
$ 5,000 
25,417,022 60 
3,548,954 41 
38,764 
20,000 
119,844 
1,948,462 
32,000 59 
22,000 
1,786,754 
336,704 
130,342 
179,550 
764,651 
38,427 
1,693,202 
1,925,553 
35,000 
392,635 
379,851 
572,568 16 
672,214 
89,593 
59,213 ' 
180,042 
892,824 37 
33,000 
377,328 
898,500 
112,487 
19,871 
442,895 
18,750 
1,471,919 
146,855 
27,186 
95,997 
5,000 
155,430 
157,634 25 
360,973 
55,960 
19,308 
48,740 
30,194,613 43 
233,410 
54,177 
7,500 
162,937 
8,992 
230,000 
1-43 
$ 50 
4,176,754 61 
1,053,966 
1,808 
473,776 
252,853 
197,147 
29,816 
770,108 12 
698,592 
36,392 
211,852 
13,578 
573,063 
16,060 
124 
1,239,293 
181,929 
54,070 
821,854 
40,730 
388,649 
66,540 
1,745,024 a 
23,216 
123,060 
16,491 
328,569 
32,917 
20,332 
1,624,978 
132,356 
16,795 
30,184 
85,451 
944,059 
1,875,501 
347,248 
180,824 
27,353 
1,527,377 4 
111,363 
29,870 
19,967 
38,515 
55,614 
760,000 
51,430 
49,562 " 
61,338 47 
19,892 
21,928 
10,000 
69,976 
67,792 
2,567 
18,285 
7,501 
169,636 
85,176 
133,985 65 
32,000 
212,0000 64 
21,000 
20,000 
630,133 
49,094 23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-C (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full 
Report Contributed 
See Annual Operation and Funds Expended 
Project Report for Construction Maintenance (Construction) 
York Harbor, ME' 1977 $ 239,654 $ 354,690 $ 32,161 
1 Completed. 
2 Excludes costs of $137,583 for local cooperation 
requirements, which includes $104,583 cash contribution. 
3 Abandonment recommended in H. Doc. 467, 69th 
Congress, 1st session. 
4 No commerce reported. 
5 Completed except for inactive portion. 
6 Authorized by the Chief of Engineers (Public Law 
86-645, Sec. 107.) 
' Excludes $37,714 Emergency Relief Funds. 
8 Inactive. 
9 Includes $53,254 for previous projects. 
o1C0o mmerce included under Tiverton Harbor, RI. 
11 Authorized work remaining on project is comprised of 
an incomplete and an inactive portion. 
12 Excludes $20,000 expended from Contributed Funds, 
Other for maintenance. 
13 Recommendation for abandonment of existing project 
made in H. Doc. 467, 69th Congress, 1st session. Portion of 
project authorized by the Chief of Engineers (Public Law 
86-645, Sec. 107) is complete. 
14Excludes $5,000 Contributed Funds expended. 
15 Improvement adequate for commerce. 
16 Costs to local interests for berth improvements are 
estimated to be $60,000. 
17 Includes $40,800 for previous project. 
18 Abandonment recommended in H. Doc. 411, 64th 
Congress, 1st session, and in River and Harbor Committee 
Doc. 3, 65th Congress, 1st session. 
19 Includes $12,000 for previous project. 
20 Under State maintenance. 
21 Excludes $114,327 expended for rehabilitation; 
breakwater repaired in 1962. 
2 Portion of project authorized by Chief of Engineers. 
23 Excludes $10,000 Contributed Funds, Other. 
24 All assurances of local cooperation have not been 
fulfilled. Public landing at Back Cove has not been 
constructed. Portion of project authorized by Chief of 
Engineers (Public Law 86-645, Sec. 107.) 
25 Includes $11,350 for previous project. 
26 H. Doc. 467, 69th Cong., 1st sess. recommended 
eliminating maintenance dredging. 
27 Includes $692,435 for previous projects. 
28 Includes $133,357 for previous project. 
29 Includes $37,000 for new work for previous project. 
30 Excludes local requirements of $65,000 consisting of 
$13,000 for public wharf and $52,000 for additional 
construction costs. 
31 Includes $42,340 for previous project. 
32 Includes $22,000 for previous project. 
3"Excludes $1,926,000 expended for rehabilitation. 
SIncludes $81,410 for previous project. 
*5Includes $15,614 for new work for previous projects. 
* Includes $21,000 for previous projects. 
37 Includes $135,143 for previous project. 
" Includes $10,000 for previous project. 
39 Includes $162,517 for previous project. 
4 Includes $330,204 for previous project. 
41 Includes $215,801 for previous project. 
42 Includes $66,120 for previous projects. 
4a Includes for previous projects $735,900 (Weymouth, 
Fore R.) and $25,000(Town R.). 
4 Includes for previous project $5,250 (Weymouth, Fore 
River) and $12,577 (Weymouth, Town River.) 
S Includes $59,420 for previous project. 
4 Includes $35,214 for previous project. 
4 Excludes $81,548 Contributed Funds, Other. 
48 Excludes $582,188 Contributed Funds, Other expended. 
49 Includes $378,450 for previous project. 
50 Includes $11,949 for maintenance of previous project. 
51 Excludes $18,000 Contributed Funds, Other. 
52 Includes $188,647 for previous project. 
53 Excludes $894,475 major rehabilitation for Long Beach 
Dike.
54 Includes $2,013 for previous projects. In addition $400 
was expended for maintenance from Contributed Funds. 
5 Includes $32,570 for previous projects. 
5 Includes $3,160 for previous project. 
57 Excludes $173,425 Contributed Funds, Other. 
5 Includes $45,835 for new work for previous project; 
excludes $211,649 expended for minor rehabilitation; jetty 
repaired in 1963. 
59 Excludes $15,000 expended for previous project. 
o Includes $3,761,412 for previous projects. 
e Includes $650,136 for previous projects. 
62Includes $331,626 for previous projects. Includes 
$290,877 National Industrial Recovery Funds and $59,207 
Public Works Funds. 
3 Excludes $37,200 Contributed Funds, Other. 
64 Excludes $5,000 Contributed Funds, Other. 
65 Excludes $10,000 Contributed Funds, Other. 
1-44

NEW ENGLAND DIVISION 
TABLE 1-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last 
Full Report Cost to Amount 
See Annual Sep. 30, 1992 Expended by 
Project Report For Construction Local Interest 
Burial Hill Beach, Westport, CT 1 1958 $ 5,810 $ 11,612 
Calf Pasture Beach Park, Norwalk, CT ' 1964 56,386 120,179 
Clark Point Beach, New Bedford, MA 1 1982 228,081 228,080 
Cliff Walk, Newport, RI 4 1984 405,491 955,237 
Compo Beach, Westport, CT 1 1962 84,544 169,089 
Cove Island, Stamford, CT ' 1961 47,131 94,262 
Cummings Park, Stamford, CT ' 1963 26,886 53,771 
Guilford Point Beach (Jacobs Beach), 
Guilford, CT ' 1961 15,620 31,241 
Gulf Beach, Milford, CT 1 1958 21,303 42,606 
Hammonasset Beach, Madison, CT 1 1956 163,183 326,366 
Hampton Beach, Hampton, NH 1 1966 260,868 385,641 
Jennings Beach, Fairfield, CT ' 1956 14,401 28,802 
Lighthouse Point Park (Area 9), CT 1 1961 3,930 7,859 
Lynn-Nahant Beach, MA 5 1986 50,000- 
Middle Beach, CT ' 1958 8,810 17,620 
Misquamicut Beach, Westerly, RI 2 1963 14,512 29,024 
North Scituate Beach, Scituate, MA 1 1969 106,552 106,552 
Oak Bluffs Town Beach, Martha's Vineyard, MA' 1976 273,334 198,583 
Oakland Beach, Warwick, RI ' 1982 559,200 181,175 
Plum Island, MA ' 1977 118,882 104,875 
Prospect Beach, West Haven, CT ' 1958 104,573 240,819 
Quincy Shore Beach, Quincy, MA 1 1962 621,464 1,242,880 
Sand Hill Cove Beach, RI ' 1959 40,143 82,000 
Sasco Hill Beach, Fairfield, CT 1 1961 23,759 47,518 
Sea Bluff Beach, West Haven CT 1 1991 292,545 157,533 
Seaside Park, CT 1 1958 150,000 329,921 
Sherwood Island State Park, Westport, CT' 1983 1,186,830 889,330 
Short Beach, CT 3 1956 - - 
Silver Beach to Cedar Beach, CT 1 1964 62,560 270,695 
Southport Beach, CT 1 1960 17,631 35,263 
Town Beach, Plymouth, MA4 1964 5,490 10,981 
Wallis Sands State Beach, Rye, NH 1 1966 65,131 435,942 
Wessagusset Beach, Weymouth, MA 1 1971 180,944 200,208 
Willard Beach, South Portland, ME 5 1983 171,000- 
Winthrop Beach, MA 1 1960 176,567 353,134 
1 Completed. 
2 Additional Federal participation will be required based on Public Law 87-874. 
3 Project completed at no cost to Federal Government by using fill from Federal navigation improvement at 
Housatonic River. (See page 88 of the 1956 Annual Report.) 
4 Completed except for inactive portion. 
6 Inactive. 
1-45

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Alford, Green River, MA 34 
Alley Bay, Beals, ME3,4.10 
Amesbury, Powwow River, MA 3,4 
Ansonia - Derby, CT 3 
Bagaduce River, ME 3,4,10 
Beaver Brook, Keene, NH 3,4 
Blackstone River, Millbury, MA s4.10 
Bound Brook, Scituate, MA 3.4 
Canton, MA 3*4 
Charles River Dam, MA 3 
Charlestown, NH 34 
Cherryfield, ME 3,4 
Chicopee, MA 3 
Chicopee Falls, MA3 
Clear River, Burrillville, RI 3.4 
Cocheco River, NH 3,4 
Connecticut River, North Stratford, NH 3,4 
Connecticut River, W. Stewartstown, NH 3.4 
Covered Bridge, Sheffield, MA 3,4,10 
Danbury, CT 3 
Derby, CT 3 
East Branch Dam, CT 3 
East Hartford, CT 3 
Fitchburg, MA (See No. Nashua River) 
Folly Brook, Wethersfield, CT 3,4 
Fort Kent, ME 3.4 
Fox Point Barrier, RI3 
Gardner, MA 3.4 
Gulf Street, Milford, CT 3.4,10 
Hall Meadow Brook Dam, CT 3 
Hartford, CT 3 
Hartford, White River, VT 3.4 
Haverhill, MA 3 
Hayward Creek, Braintree-Quincy, MA34 
Holmes Bay, Whiting, ME 34.o10 
Holyoke, MA 3 
Housatonic River, Pittsfield, MA .4 
Housatonic River, Salisbury, CT 3.4.1 0o 
Housatonic River, Sheffield, MA 3.4.10 
Huntington, MA 3,4,10 
Island Avenue, Quincy, MA 34 
Islesboro (The Narrows), ME 3,4,10 
Johnson Bay, Lubec, ME 3,4.o10 
Keene, NH 3.4 
Lancaster, Israel River, NH 3'
4 
Lee, Housatonic River, MA 3.4,10 
Little River, Belfast,ME3,4 
Lowell, MA 3 
Lower Woonsocket, RI3 
Machias River, Machias, ME3,4 
Mad River Lake, CT 3 
Marginal Way, Ogunquit, ME '4 
Merriconeag Sound, Harpswell, ME 3.4.1o 
Mill Brook, Brownsville, VT 3,4,.o 
Nashua, NH s 
Nonewaug River, Woodbury, CT3 ,4, o 
1977 
1979 
1978 
1977 
1985 
1989 
1986 
1974 
1964 
1981 
1976 
1963 
1954 
1978 
1987 
1963 
1982 
1976 
1988 
1978 
1977 
1973 
1951 
1979 
1979 
1976 
1970 
1991 
1970 
1960 
1973 
1940 
1979 
1980 
1953 
1985 
1982 
1981 
1960 
1983 
1985 
1985 
1955 
1982 
1976 
1990 
1945 
1977 
1987 
1973 
1987 
1980 
1988 
1950 
1985 
$ 41,419 
190,500 
132,113 
18,266,040 
129,500 
2,591,000 
249,999 
47,300 
156,568 5 
41,170,921 
113,330 
191,095 
1,433,600 
2,183,912 
168,000 
183,100 
180,000 
54,703 
250,000 
13,143,000 
7,582,642 
1,959,836 
2,135,447 13 
220,284 
1,997,820 
11,112,801 
495,161 
250,369 
2,572,357 
6,094,100 9 
332,236 
1,743,485 
2,325,470 
207,390 
3,418,000 25 
739,003 
102,800 
202,608 
3,900 
172,000 
165,500 
163,082 
44,146 
551,606 
37,852 
166,682 
490,600 11 
6,600,681 
152,000 
4,773,020 
243,000 
107,682 
110,000 
270,000 8 
222,500 
$ 
21 
4,576 
92,981 
5,554,088 15 
385 
411,292 22 
180,000 
2
19 
7,637 
3,616,290 14 
15,000 
21,000 
2,781,100 
120,000 
24,447 
43,000 
1,266,638 20 
327 
1-46

NEW ENGLAND DIVISION 
TABLE 1-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Northampton, MA 3 
North Canaan, Blackberry River, CT 3'4 
North Nashua River, Fitchburg, MA3 
North Nashua River, Lancaster, MA s,4,10 
Norwalk, CT3 ,4 
Norwich, CT 3 
Park River, Hartford, CT 3 
Pawcatuck, CT 3 
Pawtuxet River, Warwick, RI 3,4 
Penobscot River, Old Town, ME 34 
Perley Brook, Fort Kent, ME3'4 
Phillips Lake, MA' 
Pleasant Point, Perry, ME*3,4 
Port 5 Facility, Bridgeport, CT 3,4,10 
Prestile Stream, Blaine, ME s,4,10 
St. John River Basin, ME 24 
Salmon River, Colchester, CT 3,4 
Sand Cove, Gouldsboro, ME 3,4,10 
Saxonville, MA3 
Sebasticook River, Hartland, ME 34 
Shelburne, Androscoggin River, NH 3,4,10 
Smelt Brook, Weymouth-Braintree, MA 3,4 
South River, Conway, MA3,4,10 
Springdale, MA3 
Springfield, MA 3 
Squantz Pond, New Fairfield, CT 3,4 
Stony Brook, Wilton, NH 3,4 
Sucker Brook Dam, CT' 
Three Rivers, MA3 
Torrington, East Branch, CT 3*4 
Torrington, West Branch, CT 3*4 
Trumbull Lake, CT ' 
Village of Saxtons, VT 3,4,10 
Ware, MA 34 
Waterbury-Watertown, CT 3,4 
Weston, VT 3,4 
West Branch, Westfield River, Huntington, MA3,4 
West Warren, MA3,4 
Whitmanville Lake, MA ' 
Winsted, CT 3 
Woonsocket, RI 3 
Worcester Diversion, MA3 
'Inactive. 
2 Excludes $1,146,828 expended from Contributed Funds, 
Other.
sCompleted. 
4 Authorized by Chief of Engineers. 
' Reflects FY1967 settlement of outstanding claims in the 
amount of $13,295. 
6 Excludes $8,503 Contributed Funds, Other. 
' Includes $295,000 Public Works Administration funds. 
8 Excludes $147,366 Flood Control and Coastal Emergency 
funds expended. 
9 Excludes $835,000 Public Works Administration funds. 
o1E0m ergency Bank Protection. 
" Excludes $794,374 Public Works Administration funds. 12 Excludes $565,168 Contributed Funds, Other. 
13 Includes $380,000 Public Works Administration Funds. 
14 Cash for construction only. Excludes $245,000 expended 
for land condemnation. 
15 Excludes $1,674,567 Contributed Funds, Other. 
16 Excludes $259,408 Contributed Funds, Other. 
17 Excludes $280,000 Public Works Administration funds. 
18 Excludes $355,000 Public Works Administration funds. 
19 Excludes $406,653 Contributed Funds, Other. 
20 Excludes $488,920 Contributed Funds, Other. 
21 Excludes $727,460 Contributed Funds, Other. 
1-47 
1950 
1977 
1981 
1979 
1952 
1960 
1986 
1966 
1986 
1986 
1990 
1982 
1987 
1986 
1980 
1983 
1984 
1980 
1985 
1977 
1978 
1987 
1952 
1950 
1983 
1973 
1976 
1970 
1963 
1963 
1983 
1985 
1963 
1963 
1957 
1983 
1964 
1979 
1954 
1962 
1978 
$ 680,000 17 
73,865 
3,235,000 23 
81,671 
52,150 
1,209,000 
60,176,919 
644,311 
3,174,260 
178,045 
85,998 
300,000 
189,000 
227,500 
73,674 
55,595 
247,100 
127,500 
4,218,700 
1,857,475 
37,657 
1,803,738 
133,500 
700,000 
577,000 18 
116,296 
19,500 
2,227,792 
1,577,189 
389,237 
228,237 
1,498,800 
140,500 
400,000 
265,300 
13,079 
119,433 
389,176 
605,023 
245,500 
4,033,100 
5,086,896 
$ 
- 16 
214,106 
18,600 
6 
5,350 
58,800
- 12 
41,000 
224,476 
70,161

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Excludes $12,000 expended for land condemnations and 
$25,184 Contributed Funds, Other for relocations. 
23 Excludes $1,370,000 Public Works Administration funds 
expended on Fitchburg, MA. 
24 Irrigation demonstration project. 
SIncludes $610,000 Public Works Administration funds. 
TABLE 1-F OTHER AUTHORIZED MULTI-PURPOSE PROJECTS 
INCLUDING POWER 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Contributed 
Project Report for Construction Funds 
Passamaquoddy Tidal Power Project, ME ' 1935 $ 6,384,394 
SWork discontinued in 1937. Facilities transferred to War Assets Administration. 
1-48

NEW ENGLAND DIVISION 
TABLE 1-G DEAUTHORIZED PROJECTS 
Funds Expended 
For Last 
Full Report 
See Annual. Date Contributed 
Project Report for Deauthorized Federal Funds 
Alternative for Sugar Hill Reservoir 
Andover Lake, CT 
Bagaduce River, ME (uncompleted portion) 
Baker Brook, MA 
Bar Harbor, ME (uncompleted portion) 
Beards Brook Reservoir, NH 
Beaver Brook Lake, NH 
Bennington Reservoir, NH 
Big River Reservoir, RI 
Black Rock Harbor, CT (uncompleted portion) 
Boston Harbor, MA (1945 Act) 
Brant Rock Beach, Marshfield, MA 
Bridgeport Harbor, CT (uncompleted portion) 
Brockway Lake, VT 
Cambridgeport Lake, VT 
Chicopee, MA (uncompleted portion) 
Claremont Lake, NH 
Clyde, RI 
Connecticut River (above Hartford), CT 
Connecticut River below Hartford, 
CT (uncompleted portion) 
Cotuit Harbor, MA 
Dickey - Lincoln School Lakes, ME 
Dorchester Bay and Neponset River, MA 
(uncompleted portion) 
Eastport Harbor, ME 
Edgartown Harbor, MA (uncompleted portion) 
Fall River Harbor, MA (uncompleted portion) 
Fivemile River Harbor, CT (uncompleted portion) 
Gaysville Lake, VT 
Great Salt Pond, Block Island, RI 
(uncompleted portion) 
Greenwich Point Beach, CT 
Harbor of Refuge, Block Island, RI 
(uncompleted portion) 
Housatonic River, CT (uncompleted portion) 
Honey Hill Lake, NH 
Ipswich River, MA (uncompleted portion) 
Kennebec River, ME (uncompleted portion) 
Ludlow Lake, VT 
Lynn Harbor, MA (uncompleted portion) 
Manchester Harbor, MA 
Marblehead Harbor, MA 
Mattapoisett Harbor, MA 
Milford Harbor, CT (uncompleted portion) 
Monoosnoc Brook, MA 
Monoosnoc Lake, MA 
Mountain Brook Dam, NH 
Mystic, CT 
Mystic River, CT (uncompleted portion) 
Nantasket Beach, MA 
Nantucket, Harbor of Refuge, MA 
(uncompleted portion) 
Nantucket (Harbor of Refuge), MA 
(inactive portion) 
Napatree Beach, RI 
1972 
1932 
1949 
1973 
1949 
1987 
1986 
1984 
1961 
1980 
1946 
1954 
1968 
1948 
1932 
1979 
1962 
1984 
1968 
1984 
1978 
1984 
1969 
1970 
1983 
1959 
1983 
1979 
1949 
1969 
1986 
1956 
1949 
1968 
1950 
1981 
1967 
1967 
1949 
1968 
1986 
1971 
1965 
1989 
Aug 1977 $- 
Aug 1977 
Oct 1978 
Nov 1979 
Nov 1986 
Aug 1977 
Apr 1978 
Aug 1977 
Nov 1990 
Nov 1986 
Jan 1990 
Nov 1979 
Nov 1979 
Aug 1977 
Aug 1977 
Aug 1977 
Dec 1970 
Apr 1951 
Jan 1990 
Oct 1978 
Oct 1978 
Nov 1986 
Jan 
Nov 
Nov 
Nov 
Oct 
Oct 
94,000 
78,000 
378,300 
205,000 
242,700 
8,800 
132,146 
8,541 
26,285,298 
1990 
1983 
1986 
1986 
1978 
1976 
Nov 1986 
Oct 1978 
Nov 1986 
Nov 1979 
Aug 1977 
Nov 1986 
Nov 1986 
Aug 1977 
Nov 1986 
Nov 1979 
Oct 1978 
Oct 1978 
Nov 1986 
Nov 1986 
Nov 1986 
Aug 1977 
Aug 1972 
Nov 1986 
Jan 1990 
Nov 1986 
Jan 1990 
Nov 1979 
638,675 141,530 
206,600 
92,000 
23,986 
43,711 
57,000 
67,700 
1-49

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-G (Continued) DEAUTHORIZED PROJECTS 
Funds Expended 
For Last 
Full Report 
See Annual Date Contributed 
Project Report for Deauthorized Federal Funds 
Narragansett Pier, RI 1966 Nov 1970 $ 115,590 $ - 
New Bedford and Fairhaven Harbors, MA 
(uncompleted portion) 1953 Nov 1986 - - 
New Haven Harbor, CT (uncompleted portion) 1986 Nov 1986 - - 
Newburyport Harbor, MA (uncompleted portion) 1986 Nov 1986 - - 
Nookagee Lake, MA 1976 Nov 1986 563,677 - 
North Andover and Lawrence, MA 1949 Aug 1977 20,000 - 
North Hampton Beach, North Hampton, NH 1963 Nov 1981 - - 
Norwalk-Wilton, CT 1973 Nov 1979 - - 
Pawcatuck River, Little Narragansett Bay, RI 
and CT (uncompleted portion) 1978 Nov 1986 - - 
Pawcatuck River, RI & CT (uncompleted portion) 1979 Nov 1979 - - 
Pawtucket, RI 1949 Nov 1977 - - 
Pepperell Cove, ME (uncompleted portion) 1969 Nov 1981 - - 
Pleasant Bay, MA 1971 Nov 1986 - - 
Point Judith, RI 1968 Nov 1977 198,477 - 
Pontiac Diversion, RI 1948 Apr 1951 24,200 - 
Providence River and Harbor, RI 
(uncompleted portion) 1976 Nov 1986 - - 
Provincetown Beach (Herring Cove), MA 1961 Oct 1978 - - 
Provincetown Harbor, MA (uncompleted portion) 1979 Oct 1978 - - 
Rockland Harbor, ME (uncompleted portion) 1976 Nov 1986 - - 
Saco River, ME (uncompleted portion) 1979 Oct 1979 - - 
Sakonnet Harbor, RI (uncompleted portion) 1982 Jun 1982 176,000 - 
Salem Harbor, MA (uncompleted portion) 1969 Nov 1986 - - 
Sandy Bay, Cape Ann, MA (uncompleted portion) 1922 Oct 1978 - - 
Silver Beach to Cedar Beach, CT 1 1964 Nov 1986 - - 
South Coventry Lake, CT 1951 Aug 1977 96,000 - 
South Tunbridge Lake, VT - Aug 1977 - - 
Stamford Harbor, CT (2 projects 
uncompleted portions) 1979 Oct 1978 - - 
Stamford Harbor, CT (inactive portion) 1979 Jan 1990 - - 
Stonington Harbor, CT (uncompleted portion) 1959 Nov 1986 - - 
Stonington Harbor, ME 1961 Nov 1979 2,543 - 
Stratford, CT 1973 Mar 1977 934,500 - 
Sugar Hill Reservoir, NH 1946 Dec 1944 - - 
Taunton River, MA (inactive portion) 1948 Jan 1990 - - 
Thames River, CT (uncompleted portion) 1967 Nov 1986 - - 
The Island Lake, VT - Aug 1977 - - 
Thumperton Beach, Eastham, MA 1961 Nov 1979 - - 
Town Beach, Plymouth, MA (inactive portion) 1964 Jan 1990 - - 
Town Neck Beach, Sandwich, MA 1961 Nov 1986 - - 
Wareham Harbor, MA (inactive portion) 1896 Jan 1990- 
Wareham-Marion, MA 1965 Aug 1977 81,715 - 
Victory Lake, VT 1967 Aug 1977 168,400 - 
West Brookfield Reservoir, MA 1948 Jul 1960 67,000 - 
West Canaan Lake, NH 1948 Aug 1977 92,000 - 
Westerly, RI 1966 Nov 1986 - - 
Westfield, MA 1967 Sep 1969 507,200 - 
Westport, CT 1965 Feb 1970 29,634 - 
Westport Harbor and Saugatuck River, CT 
(uncompleted portion) 1972 Nov 1979 - - 
Westport River, MA 1942 Jan 1990 - - 
Williamsville Reservoir, VT 1949 Dec 1944 146,500 - 
Winthrop Beach, MA (uncompleted portion) 1960 Nov 1986 - - 
'Walnut Beach and impermeable groins. 
1-50

NEW ENGLAND DIVISION 
TABLE 1-H NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645 (PREAUTHORIZATION) 
Fiscal Year Contributed Funds 
Study Identification Costs Expended 
Aunt Lydia's Cove, Chatham, MA $ 574 $ 39,000 
Bass Harbor, Tremont, ME 12 
Danvers River, Danvers, MA 45,628 
East River, Wareham, MA 21,088 
Gloucester Harbor, Gloucester, MA 26,716 
Mill Creek, Yarmouth, MA 18,042 
Oak Bluffs Harbor, Oak Bluffs, MA 1,971 
Perkins Cove, Ogunquit, ME 27,007 
Provincetown Harbor, MA 446 
Saugus and Pine Rivers, MA 62,307 
Westport Harbor, Westport, MA 2,048 
Winthrop Harbor, Winthrop, MA 9,585 
TABLE 1-I BEACH EROSION ACTIVITIES PURSUANT TO SECTION 103, 
PUBLIC LAW 78-874 (PREAUTHORIZATION) 
Fiscal Year Contributed Funds 
Study Identification Costs Expended 
Drakes Island Beach, Wells, ME 
Lighthouse Beach, Chatham, MA 
Morris Cove, New Haven,CT 
North Nantasket Beach, Hull, MA 
Planting Island Causeway, Marion, MA 
Point Shirley, Winthrop, MA 
Poppenessett Spit, Mashpee, MA 
Prospect Beach, West Haven, CT 
Sandy Point, West Haven, CT 
Sylvia State Beach, Oak Bluffs, MA 
Town Beach,Madison, CT 
Town Beach, Narragansett, RI 
West Haven Beaches, CT 
$ 8,000 
9,152 
18,224 
15,765 
11,000 
3,000 
3,721 
50,988 
11,743 
2,733 
9,000 
8,000 
2,915 
1-51

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-J FLOOD CONTROL ACTIVITIES PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858 (PREAUTHORIZATION) 
Fiscal Year Contributed Funds 
Study Identification Costs Expended 
Cedar Beach, Milford, CT $ 1,724 
Deerfield River, Wilmington, VT 72 
Israel River, NH 5,568 
Kennebec River, Madison, ME 714 
Lake Shirley, Lunenburg,MA 15,000 
Mad River, Waterbury, CT 1,413 
Mad River, Wolcott, CT 3,660 
Nantasket Beach, Hull, MA 39,261 
Point Beach, Milford, CT 2,991 
Sebasticook River, Pittsfield, ME 1,325 
Silver Beach, Milford, CT 827 
Ten Mile River, Cheshire, CT 949 
TABLE 1-K BLACKSTONE RIVER BASIN, MA AND RI 
(See Section 28 of Text) 
RESERVOIR 
Miles Estimated Federal Cost 
Above 
Mouth of 
Black- Reservoir Lands 
stone Height Capacity and 
Name Nearest City River (feet) Type (acre-feet) Construction Damages' Total 
West Hill2 Worcester,MA 25.8 51 Earthfill 12,400 $1,366,902 $940,000 $2,306,902 
1 Includes highway, railroad, and utility relocations. 
2 See individual report for details. 
1-52

NEW ENGLAND DIVISION 
TABLE 1-K (Continued) LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of 
Black- Lands 
stone and 
Location River Type of Structure Construction Damages' Total 
Worcester, MA 48 Diversion tunnel and channel $4,923,500 $1,179,000 2 $6,102,500 
Woonsocket, RI 15 Channel improvement 3,733,100 1,069,000 ' 4,802,100 
Lower Woonsocket, Flood wall, conduits and 
RI 13 channel improvement 8,356,239 435,000 8,791,239 
Blackstone River, 
Millbury, MA 32 Slope protection 254,575 - 254,575 5 
Clear River, 
Burrillville, RI 23 Retaining wall 168,000 - 168,000 
Pawtuxet River, 
Warwick, RI - Land acquisition 4,125,000 - 4,125,000 4 
' Includes relocation. 4 $3,300,000 Federal; $825,000 non-Federal. 
2 $158,000 Federal; $1,021,000 non-Federal. 5 $249,999 Federal; $4,576 non-Federal. 
a $300,000 Federal; $769,000 non-Federal. 
TABLE 1-L CONNECTICUT RIVER BASIN, VT, NH, MA AND CT 
(See Section 30 of Text) 
DAMS AND RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of 
Connec- Reservoir Lands 
ticut Height Capacity Constr- and 
Name Nearest City River (feet) Type (acre-feet) uction Damages' Total 
Vermont: 
Union Village 2 
North Hartland 2 
North Springfield 2 
Ball Mountain 2 
Townshend 2 
New Hampshire: 
Surry Mountain 2 
Otter Brook 2 
Massachusetts: 
Birch Hill 2 
Tully 2 
Barre Falls 2 
Knightville 2 
Littleville 2 
Conant Brook 2 
Connecticut: 
Colebrook River 2 
Mad River 
Sucker Brook 
White River Jct. 
White River Jct. 
Springfield 
Brattleboro 
Brattleboro 
Keene 
Keene 
228.4 170 Earthfill 
211.7 185 Earthfill 
191.3 120 Earthfill 
178.2 265 Rockfillearth 
168.3 133 Earthfill 
174.4 86 
171.2 133 
Gardner 
Athol 
Worcester 
Northampton 
Northampton 
Springfield 
Winsted 
Winsted 
Winsted 
153.3 
148.7 
130.2 
102.8 
102.0 
122.0 
56 
62 
62 
160 
150 
85 
38,000 
71,400 
50,600 
54,600 
33,200 
$3,186,860 
6,349,225 
4,781,526 
10,689,298 
$ 908,300 
963,000 
2,050,000 
350,000 
$4,095,160 
7,312,225 
6,831,526 
11,039,298 
5,520,413 1,878,000 7,398,413 
Earthfill 32,500 2,448,610 385,000 2,833,610 
Earthfill 18,300 2,982,048 1,378,400 4,360,448 
Earthfill 
Earthfill 
Rockfillearth 
Earthfill 
Earthfill 
Rockfillearth 
116.0 223 Rockfillearth 
120.0 178 Earthfill 
118.5 68 Earthfill 
49,900 
22,000 
24,000 
49,000 
32,400 
3,740 
98,500 
1,740,679 
1,298,752 
1,928,819 
2,594,440 
5,863,412 
1,935,530 
3,075,000 
368,000 
39,000 
821,200 
1,150,000 
1,015,000 
4,815,679 
1,666,752 
1,967,819 
3,415,640 
7,013,412 
2,950,530 
8,341,971 5,922,000 14,263,971 
9,700 4,773,020 2,210,000 * 6,983,020 
1,480 2,227,792 180,0003 2,407,792 
' Includes highway, railroad, and utility relocations. 
2 For details, see individual report. 
3 Non-Federal cost. 
4 Non-Federal $670,000; Federal $1,540,000. 
1-53

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-L (Continued) LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of 
Connec- Lands 
ticut and 
Location River Type of Structure Construction Damages' Total 
Beaver Brook, Keene, NH 170.4 Channel improvement $ 2,591,000 $ - $ 2,591,000 
Charlestown, NH 181 Riverbank protection 113,330 - 113,330 
Chicopee, MA 80 Wall and levee 1,434,000 250,000 1,684,000 
Chicopee Falls, MA 83 Wall and levee 2,600,000 70,000 2,670,000 
East Hartford, CT 52 Wall and levee 2,135,447 271,000 2,406,447 
Folly Brook, Wethersfield, CT 50 Channel improvement 220,284 - 220,284 
Gardner, MA 163 Dam and levee 495,691 35,000 530,691 
Gulf Street, Milford, CT - Slope protection 290,277 - 290,277 
Hartford, CT 52 Wall and levee 6,930,000 s 1,150,000 8,080,000 
Hartford, White River, VT 216 Channel improvement 332,236 - 332,236 
Holyoke, MA 85 Wall and levee 3,418,000 150,000 3,568,000 
Huntington, MA 100 Riverbank protection 3,900 - 3,900 
Israel R., Lancaster, NH 314 Gabion overflow weir 551,606 - 551,606 
Keene, NH 167 Channel improvement 44,100 - 44,100 
Mill Brook, Brownsville, VT 200.3 Streambank stabilization 110,000 - 110,000 
Northampton, MA 94 Wall and levee 960,000 ' 150,000 1,110,000 
North Stratford, NH 345 Slope protection 180,000 - 180,000 
Park River, CT 51 Conduit 60,176,919 1,300,000 61,476,919 
Riverdale, MA 80 Wall and levee 1,263,724 50,000 1,313,720 
Salmon R., Colchester, CT 38 Slope protection 247,100 - 247,100 
South River, Conway, MA 107 Slope protection 133,500 - 133,500 
Springdale, MA 84 Wall and levee 700,000 57,000 757,000 
Springfield, MA 76 Wall and levee 932,000 272,000 1,204,000 
Three Rivers, MA 98 Wall and levee 1,577,189 700,000 2,277,189 
Ware, MA 110 Channel improvement 400,000 85,000 485,000 
Weston, VT 195 Channel improvement 13,000 2,000 15,000 
West Springfield, MA 76 Wall and levee 1,789,141 2 30,000 1,819,141 
West Warren, MA 111 Wall and levee 389,200 64,000 453,200 
Winsted, CT 115 Channel improvement 245,500 30,000 275,500 
'To be borne by local interests. Also includes local interests portion of relocation. 
For details see individual report. 
2 Includes $245,000 Public Works Administration funds. 
3 Includes $835,000 Public Works Administration funds. 
4 Includes $280,000 Public Works Administration funds. 
5 Includes $355,000 Public Works Administration funds. 
1-54

NEW ENGLAND DIVISION 
TABLE 1-M HOUSATONIC RIVER BASIN, CT AND MA 
(See Section 31 of Text) 
DAMS AND RESERVOIRS 1 
Miles Estimated Federal Cost 
Above 
Mouth of 
Nauga- Reservoir Lands 
tuck Height Capacity Constr- and 
Name Nearest City River (feet) Type (acre-feet) uction Damages 2 Total 
Hall Meadow 4 Torrington, CT 41.0 73 Rock and 8,620 $2,572,357 $1,290,0003 $3,862,357 
East Branch 5 Torrington, CT 43.7 92 Earthfill 4,350 1,959,836 1,290,0003 3,249,836 
Thomaston Torrington, CT 30.5 142 Rock and 42,000 6,382,112 7,900,000 14,282,112 
earthfilloMfouth 
Northfield Brook Torrington, CT 30.6 118 Earthfill 2,432 1,875,512 975,000 2,850,512 
Black Rock Waterbury, CT 29.0 154 Earthfill 8,700 5,223,700 2,958,600 8,182,300 
Hancock Brook Waterbury, CT 25.0 57 Earthfill 4,030 1,594,911 2,585,000 4,179,911 
Hop Brook Waterbury, CT 15.9 97 Earthfill 6,970 2,701,562 3,450,000 6,151,562 
' For details of projects, see individual reports. * For last full report, see Annual Report for 1970. 
2 Includes highway, railroad, and utility relocations. s For last full report, see Annual Report for 1973. 
cost of lands borne by local interests. aIncludes 
LOCAL PROTECTION PROJECTS 1 
Miles Estimated Cost 
Above 
Mouth of 
Housa- Lands 
tonic and 
Location River Type of Structure Construction Damages 2 Total 
Alford, Green River, MA 111.0 Earth dike and stone slope $41,419 $ - $ 41,419 
protection 
Ansonia-Derby, CT 13.0 Wall, levee, channel 18,266,040 1,178,000 19,444,040 
improvement and pumping 
station 
Danbury, CT 56.0 Walls, channel improvement 13,143,000 1,862,000 15,005,000 
and bridge replacememt 
Derby, CT 12.0 Walls, levees and pumping 7,582,642 647,000 8,229,642 
station 
North Canaan, 
Blackberry River, CT 83.0 Snagging and clearing project 73,865 - 73,865 
Pittsfield, MA 133.0 Stone arch culvert 739,003 85,000 824,003 
Salisbury, CT 76.0 Gabionade with slope 102,800 - 102,800 
protection 
Sheffield, MA 96.0 Stone slope protection 205,608 - 205,608 
Squantz Pond, New 43.0 Timber Bulkhead 116,296 - 116,296 
Fairfield, CT 
Torrington, East Branch, CT 51.0 Dike and channel improvement 389,200 - 389,200 
Torrington, West Branch, CT 52.0 Walls, dikes and channel 228,300 - 228,300 
Waterbury- Watertown, CT 32.0 Wall, dike and channel 263,300 - 263,300 
For details of projects, see individual reports. 
2 To be borne by local interests. Includes relocations. 
1-55

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-N MERRIMACK RIVER BASIN, NH, AND MA 
(See Section 32 of Text) 
DAMS AND RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of 
Merri- Reservoir Lands 
mack Height Capacity Constr- and 
Name Nearest City River (feet) Type (acre-feet) uction Damages 2 Total 
Franklin Falls 2 Franklin, NH 118.2 140 Earthfill 154,000 $ 6,190,487 $ 1,760,000 $ 7,950,487 
Blackwater 2 Concord, NH 118.8 75 Earthfill 46,000 766,746 553,000 1,319,746 
Hopkinton- 
Everett 2,4 Concord, NH 87.3 115 Earthfill 157,300 12,715,440 8,737,000 21,452,440 
Edward 
MacDowell 2 Keene, NH 161.3 67 Earthfill 12,800 1,708,253 306,000 2,014,253 
Phillips Fitchburg, MA 105.4 48 Earthfill 1,600 13,450,000 7,350,000 20,800,000 
Whitmanville Fitchburg, MA 110.6 76 Earthfill 9,350 11,590,000 6,210,000 17,800,000 
' Includes highway, railroad, and utility relocations. 
2 For details, see individual report. 
3Based on "large" Phillips plan which would eliminate Nookagee Lake. 
4 Substituted for Bennington and Beards Brook. Distance and height are for Everett Dam. Distance and height for Hopkinton 
Dam are 118 miles and 76 feet, respectively. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of 
Merri- Lands 
mack and 
Location River Type of Structure Construction Damages 1 Total 
Amesbury, Powwow and 3.0 Wall and revetment $ 132,113 $ - $ 132,113 
Merrimack Rivers, MA 2 
Haverhill, MA 2 21.0 Floodwall, conduit and 1,743,485 - 1,743,485 6 
pumping station 
Lowell, MA 2 39.0 Wall and levee 490,600 5 90,000 580,600 
Nashua, NH 2 55.0 Wall and levee 270,000 3,000 273,000 4 
North Nashua River, MA 2,3 100.5 Channel improvement 3,241,421 - 3,241,421 
Saxonville, MA 2 69.0 Wall, levee, channel 4,218,700 530,000 4,748,700 
'To be borne by local interests. 
2 Project completed. 
3 Excludes $1,370,000 Public Works Administration Funds expended on Fitchburg, MA. 
4 Excludes $15,000 expended from Contributed Funds. 
5 Excludes $794,374 Public Works Administration Funds. 
6 Excludes $120,000 expended from Contributed Funds. 
1-56

NEW ENGLAND DIVISION 
TABLE 1-0 THAMES RIVER BASIN, CT, RI AND MA 
(See Section 37 of Text) 
DAMS AND RESERVOIRS 
Miles Estimated Federal Cost 
Above 
Mouth of Reservoir Lands 
Thames Height Capacity Constr- and 
Name Nearest City River (feet) Type (acre-feet) uction Damages 1 Total 
Hodges Village 2 Webster, MA 74.5 55 Earthfill 13,000 $1,317,268 $3,144,000 $4,461,268 
Buffumville 2 Webster, MA 74.4 66 Earthfill 12,700 2,157,603 841,000 2,998,603 
East Brimfield 2 Southbridge, MA 82.8 55 Earthfill 30,000 1,337,043 5,720,000 7,057,043 
Westville 2 Southbridge, MA 75.2 80 Earthfill 11,000 2,284,683 3,400,000 5,684,683 
West Thompson 2 Putman, CT 59.3 70 Earthfill 25,600 5,036,220 1,965,000 7,001,220 
Mansfield Hollow 2 Willimantic, CT 40.0 70 Earthfill 52,000 4,107,164 2,340,000 6,447,164 
SIncludes highway, railroad, and utility relocations. 
2 For details, see individual report. 
LOCAL PROTECTION PROJECTS 
Miles Estimated Cost 
Above 
Mouth of Lands 
Thames and 
Location River Type of Structure Construction Damages 1 Total 
Norwich, CT 15.0 Channel improvements $1,209,000 $72,000 $1,281,000 
West River, New Haven, CT - Channel improvements 1,959,374 - 1,959,374 
1 Borne by local interests. 
TABLE 1-P BOSTON HARBOR, MA 
Total Federal Cost for Existing Project to September 1992 
Funds New Work Maintenance Total 
Regular $21,881,851 $8,766,496 $30,648,347 
Public Works 1,030,806 - 1,030,806 
Emergency Relief 935,303 - 935,303 
$23,847,960 $8,766,496 1 $32,614,456 
1 Excludes $17,767 Contributed Funds. 
1-57

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 1-Q RECONNAISSANCE AND CONDITION SURVEYS 
Date Survey Date Survey 
Project Conducted Project Conducted 
CONNECTICUT 
Bridgeport Harbor 
Clinton Harbor 
Connecticut River 
below Hartford 
Guilford Harbor 
Housatonic River 
Milford Harbor 
New Haven Harbor 
Norwalk Harbor 
Stamford Harbor 
Belfast Harbor 
Biddeford Pool 
Boothbay Harbor 
Camden Harbor 
Deer Island Thorofare 
Isle of Shoals Harbor 
Josias River 
Kennebec River 
Narraguagus River 
Rockland Harbor 
Searsport Harbor 
South Bristol Harbor 
Stonington Harbor 
Tenants Harbor 
Wells Harbor 
Winter Harbor 
York Harbor 
MASSACHUSETTS 
Jan 1992 
Oct/Nov 1991 
Sep 1992 
May/Jun 1992 
Apr/May 1992 
Nov/Dec 1991 
Nov 1991 
Jun/Jul 1992 
May/Jun 1992 
Sep 1992 
Jul 1992 
May 1992 
Feb 1992 
Oct 1991 
Sep 1992 
Feb 1992 
Jul/Aug 1992 
May-Jul 1992 
Jan/Feb 1992 
May 1992 
Feb/Mar/Jun/ 
Sep 1992 
Oct 1991 
Apr/May 1992 
Jul 1992 
May 1992 
Sep 1992 
Andrews River 
Annisquam River 
Chatham (Stage) Harbor 
Cohasset Harbor 
Cuttyhunk Harbor 
Duxbury Harbor 
Falmouth Harbor 
Green Harbor 
Hyannis Harbor 
Lagoon Pond 
Little Harbor 
Menemsha Creek 
Nantucket Harbor 
Newburyport Harbor 
Onset Bay 
Rockport Harbor 
Scituate Harbor 
Sesuit Harbor 
Vineyard Haven 
Wareham Harbor 
Weymouth Fore & 
Town River 
NEW HAMPSHIRE 
Hampton Harbor 
RHODE ISLAND 
Block Island 
Point Judith Pond 
Providence River & 
Harbor 
Sakonnet Harbor 
Seekonk Harbor 
Wickford Harbor 
Feb 1992 
Nov/Dec 1991 
Feb/Mar/Apr 1992 
Jan 1992 
Sep 1992 
Feb 1992 
Mar 1992 
Oct 1991 
Feb 1992 
Feb/Mar 1992 
Mar 1992 
Sep 1992 
Oct 1991 
Mar 1992 
May 1992 
Aug 1992 
Aug/Sep 1992 
May 1992 
Mar/Apr 1992 
Jan/Feb/Apr 1992 
Mar 1992 
Apr/May 1992 
Nov 1991 
Jul/Aug 1992 
Oct/Dec 1991 
Jan 1992 
Mar/Apr 1992 
Jun/Aug 1992 
Dec 1991 
Jan/Feb 1992 
Aug/Sep 1992 
May/Jun 1992 
Major activities under the Dredged Material Management Program under PCS for fiscal year 1992 were (1) monitoring 
surveys at the Jonesport, New London, Cornfield Shoals, Central Long Island Sound, Western Long Island Sound, Massachusetts 
Bay, and Portland disposal sites (2 ) maintenance, replacement, and repositioning of disposal site buoys. Additionally, 3 
monitoring study reports and a public information brochure were completed and distributed to the public and regional resource 
agencies. Total cost of contracts was $690.000. Labor costs of $260,000 for program management, sampling and testing, and 
environmental analysis were incurred. 
1-58 
MAINE

TABLE 1-R 
Study Identification 
MFS, Howard Complex, Cranston, RI 
NEW ENGLAND DIVISION 
PROJECTS UNDER SPECIAL AUTHORIZATION 
Fiscal Year 
Authority Costs 
Code 140 $ 44,124 
1-59 
I

NEW YORK, N.Y. DISTRICT* 
This district comprises western Vermont, small portions of 
western Massachusetts and Connecticut, eastern New York 
including Long Island, and northeastern New Jersey, embraced 
in the drainage basins tributary to Lake Champlain and St. 
Lawrence River system east thereof and to the Atlantic Ocean 
from New York-Connecticut State Line to, but not including 
Manasquan Inlet, N.J. In addition it exercises jurisdiction over 
Navigation 
matters pertaining to improvement of Great Lakes to Hudson 
River waterway. Under the direction of the Secretary of the Army, 
the District Engineer, as Supervisor of New York Harbor, 
also exercises jurisdiction under the laws enacted for the preservation 
of the tidal waters of New York Harbor, its adjacent or 
tributary waters, and the waters of Long Island Sound. 
Page 
1. Aquatic Plant Control...............................................2-3 
2. Bay Ridge-Red Hook Channels, N.Y.......................2-3 
3. East Chester Creek, N.Y .......................................... 2-3 
4. East Rockaway Inlet, N.Y ........................................ 2-4 
5. Fire Island to Jones Inlet, N.Y ................................. 2-4 
6. Flushing Bay and Creek, N.Y................................... -5 
7. Great South Bay, N.Y .............................................. 2-5 
8. Hempstead Harbor, N.Y............................................2-6 
9. Hudson River, N.Y...................................................2-6 
10. Hudson River Channel, N.Y. & N.J ...................... 2-7 
11. Jam aica Bay, N.Y ..................................................... 2-8 
12. Kill Van Kull-Newark Bay, N.J. & N.Y................2-8 
13. Long Island Intacoastal W/W, N.Y........................2-9 
14. Narrows of Lake Champlain, N.Y. 
15. New York and New Jersey Channels ....................... 2-9 
16. New York Harbor-Collection and 
Removal of Drift ..................................................... 2-10 
17. New York Harbor-Entrance Channels 
and Anchorage Areas..............................................2-11 
18. Shinnecock Inlet, N.Y.............................................. 2-11 
19. Shrewsbury River, N.J ........................................... 2-12 
20. Tarrytown Harbor, N.Y...........................................2-13 
21. Westchester Creek, N.Y ........................................... 2-13 
22. Supervisor of New York Harbor .............................. 2-13 
23. Reconnaissance and Condition Surveys ................. 2-14 
24. Other Authorized Navigation Projects.....................2-14 
25. Navigation work under special authorization..........2-14 
Beach Erosion Control 
26. Rockaway Inlet to Norton Point 
(Coney Island) N.Y ................................................ 2-14 
27. Sandy Hook to Barnegat Inlet, N.J ........................ 2-14 
28. Other Authorized Beach erosion 
control projects.......................................................2-15 
29. Beach erosion control work under 
special authorization ................................................ 2-15 
Flood Control 
30 North Ellenville, N.Y ............................................... 2-15 
31. Passaic River Basin, N.J. & N.Y ........................... 2-16 
32. Inspection of completed flood control projects.......2-17 
33 Other authorized flood control projects...................2-17 
34 Flood control work under 
special authorization................................................2-17 
35 Emergency steambank and shoreline 
protection under special authorization.....................2-17 
General Investigations 
36. 
37. 
38. 
Surveys ..................................................................... 2-17 
Collection and study of basic data ..................... 2-17 
Deauthorized projects ............................................. 2-17 
Tables 
Table 2-A Cost & Financial Statement............................2-18 
Table 2-B Authorizing legislation .................................. 2-22 
Table 2-C Hudson River, N.Y. Features of 
Lock and Dam Included in 
Existing Project..............................................2-27 
2-1 
IMPROVEMENTS 
Page

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Page 
Table 2-E Supervisor of New York Harbor 
Statement of Activities .................................. 2-27 
Table 2-F Reconnaissance & Condition Surveys ........... 2-28 
Table 2-G Other Authorized Navigation Projects...........2-29 
Table 2-H Other Authorized Beach 
Erosion Control Projects .............................. 2-31 
Table 2-I Other Authorized Flood 
Control Projects ............................................. 2-32 
Page 
Table 2-J Surveys ........................................................... 2-33 
Table 2-L Costs for Flood Plain Management 
Services .......................................................... 2-33 
Table 2-M Deauthorized Projects ..................................... 2-34 
Table 2-N Section 107 Study..........................................2-35 
Table 2-P Section 205 Projects ...................................... 2-35 
Table 2-Q Section 14 Reports 
and Plans and Specs ...................................... 2-36 
2-2

NEW YORK, N.Y. DISTRICT 
1. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in New York District. 
Existing Project. Provides for control and progressive eradication 
of water chestnut, Eurasian water milfoil, and other 
obnoxious aquatic plant growths from the navigable waters, 
tributary streams, connecting channels, and other allied waters 
of the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including continued 
research for development of the most effective and economic 
control measures. (See Table 2-B for Authorizing Legislation.) 
Local cooperation. Local interests were required to provide 
30 percent of the cost of the program except as modified by 1962 
River and Harbor Act and agree to hold the United States free 
from damages. The Water Resources Development Act of 1986 
changed the local responsibility from 30% to 50%. In FY 87 the 
States involved in the program were permitted to keep the cost 
sharing at 30% by order of the Secretary of the Army. Starting 
FY 88, however, local sponsors contributed 50% of the costs. 
Operations and results during period. FY 1992 has been the 
eleventh year of a control program started in FY 1982 for the 
removal of nuisance aquatic plants in Lake Champlain. Recent 
work continued the removal of water chestnut from portions of 
the south end of the lake. The State of Vermont was able to 
identify alternative sources to fund the FY 1991 program at no 
Federal cost. 
Condition as of September 30. Reconnaissance report covering 
the aquatic plant problems of the North Atlantic Division 
areas was completed in August 1967. The General Design 
Memorandum for this program was completed in March 1982 
by the State of Vermont. The total Federal cost of this control 
program to date is $1,809,605. In October 1991, waterways 
experiment station was directed to conduct a 3-year study for 
$90,000 which would identify and test potential biocontrol 
agents of water chestnuts. Early results are good, as a particular 
wevil has tested successfully as a biocontrol agent of water 
chestnut. 
2. BAY RIDGE AND RED HOOK CHANNELS, N.Y. 
Location. These channels lie along east shore of Upper Bay, 
New York Harbor and, with Buttermilk Channel, form an 
easterly channel along Brooklyn waterfront from the Narrows 
to East River. (See National Ocean Survey Charts 12327 and 
12334). 
Previous projects. For details see Annual Report for 1915 
and 1938, page 1768 and 195 respectively. 
Existing projects. A channel 1,200 feet wide 40 feet deep 
at mean low water from the Narrows to Bay Ridge Avenue, 
Brooklyn, thence 1,750 feet wide to junction of Bay Ridge and 
Red Hook Channels, thence 1200 feet wide through Red Hook 
Channel to junction with Buttermilk Channel and a channel 
of same depth extending into Gowanus Bay from junction of 
Bay Ridge Channel with Red Hook Channel, narrowing uniformly 
in width to about 500 feet at 28th Street Brooklyn. 
Section included in project is 4 miles long. Mean tidal range, 
4.7 feet; mean range of spring tides, 5.6 feet: irregular fluctuations 
due to wind and atmospheric pressure vary from 3.9 feet 
below mean low water up to 5.2 feet above mean high water. 
New work for completed project cost $4,277.197 exclusive of 
amounts expended on previous projects. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, revised 1988. 
Vol. 2 
Operations and results during period. Approximately 
178,000 of material was removed by Corps' Hopper Dredge 
"McFarland" during FY92 at the Gowanus Bay portion of the 
Bay Ridge and Red Hook Channel, NY. The total cost was 
$2,080,098 for maintenance work. 
Condition as of September 30. New work under existing 
project was commenced March 1901 and completed June 1940. 
3. EAST CHESTER CREEK N.Y. 
Location, This creek also known as Hutchinson River, is a 
small tidal stream emptying into East Chester Bay, an indentation 
in north shore of Long Island Sound immediately north of 
Throgs Neck, 12 miles southwest of Connecticut State line and 
21 miles by water northeast of the Battery, New York City. (See 
Coast and Geodetic Survey Chart 12366) 
Previous projects. For details see Annual Reports for 1915 
1929, 1938 and 1949, pages 1761, 167, 163, and 208. respectively. 
Existing project. A channel 10 feet deep at mean low water 
and generally 150 feet wide from Long Island Sound through 
East Chester Bay to a point 700 feet below Boston Post Road 
Bridge, and thence 70 feet wide extending to a point where the 
creek divides into a Y, thence approximately 1,000 feet into east 
branch of the Y and Approximately 500 feet into west branch, 
of the Y; a passing basin south of Boston Post Road Bridge; 
widening channel at Boston Post Road Bridge and construction 
of a check dam at head of navigation. Section included in 
project is 5 miles. Mean tidal range,7.3 feet in the estuary; mean 
range of spring tides, 8.6 feet irregular fluctuations due to wind 
and atmospheric pressure vary from 3.9 feet below mean low 
water up to 8.1 feet above mean high water.(See Table 2-B for 
Authorizing Legislation.) 
2-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Note: The 10-foot project has been deauthorized. The 8-foot 
project, with same widths as above, authorized in 1930, remains 
as the existing project. 
Local cooperation. River and Harbor Act of May 17, 1950, 
provides that local interests furnish lands, rights of-way, and 
suitable areas for disposal of dredged material during construction 
and future maintenance, and hold the United States 
free from damages. City of New York has complied with 
requirements. Assurances are yet to be received from other 
local interests concerned with improvement. 
Terminal facilities. Port Series No. 5, revised 1965, Vol. 2, 
Part 2, 
Operations and results during period. An engineering and 
design effort for East Chester Creek, NY was conducted during 
this period to determine the feasibility to perform dredging at 
the "Y" portion of the upper channel. The total cost of the E&D 
effort was $172,697, 
Conditions as of September 30. No work has been accomplished 
under the existing project. Work under the 1930 
project was completed in August 1941. 
4. EAST ROCKAWAY INLET, N.Y. 
Location. On south shore of Long Island between main 
body of island and western end of Long Beach It is 10 miles 
east of Rockaway Inlet and about 27 miles by water south and 
east from the Battery, New York City. (See National Ocean 
Survey Chart 12353.) 
Existing project. A channel. 12 feet deep at mean low water 
and 250 feet wide from 12 foot contour in Long Beach Channel 
protected by a jetty. Mean tidal range, 4.3 feet; mean range of 
spring tides, 5.2 feet; irregular fluctuations due to wind and 
atmosphere pressure vary from 3.9 feet below mean low water 
up to 5.6 feet above mean high water. New work for completed 
project cost $603,969, including. $100,000 contributed funds 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with. 
Terminal facilities. There are numerous terminals in 
Oceanside. Island Park, Long Beach, and East Rockaway, 
including oil terminals. Other terminals are repair and mooring 
docks with mechanical handling facilities. There are public 
wharves at East Rockaway and Woodmere. Waterfront on 
north side of Long Beach has been bulkheaded. Facilities are 
considered adequate for existing commerce. 
Operations and results during period. A contract for the 
maintenance dredging of the Inlet was awarded onl8 July 1991. 
Work commenced on 26 September 1991 and was completed on 
11 November 1991. Approximately 157,000 c.y. of material 
was removed. Operations and maintenance funds in the amount 
of $357,062 was expended on Supervision and Inspections, and 
contract work for this project during FY 1992. 
Condition as of September 30. Work under existing project 
began February 1933 and is 100 percent complete. East jetty, 
4.250 feet tong was completed in July 1934. Project channel 
was completed in May 1935. 
5. FIRE ISLAND TO JONES INLET, N.Y., 
Location. On south shore of Long Island, about 50 miles by 
water south and east of the Battery, New York City. Fire Island 
Inlet is the main entrance into Great South Bay from the Atlantic 
Ocean. (See National Ocean Survey Chart 12352.) 
Existing project. A jetty at Fire Island Inlet extending 
generally southwest and south for 5,000 feet from high ground 
on Democrat Point at the west end of Fire Island and a channel 
14 feet deep and 450 feet wide between the north-western edge 
of the Inlet's shoaling area and the tip of the Sore Thumb 
connecting the ocean to the deep water in the Inlet. Mean tidal 
ranges at the ocean and inlet ends of Democrat Point are 4.1 feet 
and 2.4 feet respectively. Irregular fluctuations due to wind and 
atmospheric pressure vary from 2.5 feet below mean low water 
up to 6.2 feet above mean high water on the ocean side. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Requires cost sharing and lands, easements 
and rights-of-way: 
Terminal facilities. Great South Bay has extensive public 
and private facilities for mooring and servicing recreational 
boats. Much of this traffic uses the inlet during the boating 
season, and some traffic (Coast Guard craft and party and head 
fishing boats) continues throughout the year. 
Operations and results during period. A contract for 
dredging in the Inlet and placement of 1,200,000 cubic yards of 
sand on Gilgo Beach, N.Y. was awarded on 21 August 1992. 
Work commenced in September 1992 and is scheduled to be 
completed in Feb 1993 as a combined dredging and beachnourishment 
project, The total of Operations and Maintenance 
funds expended on the project during FY 92 is $2,519,744, with 
New York State contributing an additional $530,829 for beach 
placement of sand. Additional $4,025,480 in Construction 
general funds together with New York State's matching $847,947 
are reserved for FY 93. 
Condition as of September 30. The jetty, completed in 
1941, surpassed its capacity as a sand entrapping agent in a little 
over a decade. Since then extensive sand bars and shoals 
continued to form west of the jetty and in the inlet throat. 
Hydraulic dredging in the inlet was undertaken in 1959 and 
again in 1964 under a combined beach erosion control and 
navigation authorization (1958 Act). Since then 3 more hydraulic 
dredging operations were conducted starting in 1973 and 
completed in 1977 under provisions of the 1962 Act (see Table 
2-4

NEW YORK, N.Y. DISTRICT 
2B). Maintenance dredging using small hopper dredges has 
also been done from time to time. Due to local concerns about 
inlet dredging and erosion at Oak Beach, maintenance had been 
deferred since 1979 which has allowed the complete shoaling of 
the authorized project channel. To facilitate navigation in this 
period the existing natural channel was dredged in FY 1985 and 
in FY 1987. In FY 1987 sand was deposited offshore of Gilgo 
Beach by hopper dredge using operations and maintenance 
funds. O&M funds were also used during FY 1987 and 1988 to 
make repairs to the inner portion of the jetty. 
In March 1988 the District recommended a plan to maintain 
a realigned channel in the vicinity of the natural channel to a 
depth of 14 feet (plus 2 feet of allowable overdepth) and a width 
of 450 feet. The plan also recommended placement of the 
dredged material along Gilgo Beach for shore protection purposes. 
The recommended plan was approved by the Assistant 
Secretary of the Army for Civil Works on 2 August 1988. 
During FY 1990 and 1991 the realigned channel was dredged 
to project depth, with placement of material along Gilgo Beach 
for shore protection purpose. 
6. FLUSHING BAY AND CREEK, NY 
Location. On north shore Long Island, opening into East 
River, 12 miles by water northeast of the battery, New York 
City. Bay is 1.8 miles long in a northwest-southeast direction 
and from 0.4 to 0.8 mile wide. Flushing Creek enters bay from 
southeast and is about 1.1 miles long. (Chart No. 12339) 
Previous projects. For details see Annual Reports for 1915, 
1932 and 1938; pages 1772, 169, and 168 respectively. 
Existing project. (a) A bay channel for a depth of 15 feet at 
mean low water, and 3000 feet wide from deep water in East 
River 1.8 miles to maneuvering area; (b) thence a creek channel 
with a depth of 15 feet at mean low water and 200 feet wide to 
Northern Boulevard Bridge, thence decreasing uniformly in 
width to 170 feet at a point 50 feet downstream from Van Wyck 
expressway Bridge, a distance of about 1.1 miles; (c) a branch 
channel with a depth of 15 feet at mean low water and width of 
200 feet from bay channel, maneuvering area 0.1 mile long; (d) 
an irregularly shaped maneuvering area about 2,000 by 750 feet 
with a depth of 15 feet at mean low water except approach to 
west side of municipal boat basin which will remain at 12 feet 
at mean low water; (e) an anchorage basin about 2,100 feet by 
1,800 feet, encompassing about 84 acres with a depth of 6 feet 
at mean low water, and (f) riprap revetment of 1,400 feet 
extension of earth dike. Mean Tidal range, 6.5 feet at mouth of 
Flushing Bay, 6.8 feet at Northern Boulevard Bridge; mean 
range of spring tides 8.1 feet; irregular fluctuations due to wind 
and atmospheric pressure vary from 4 feet low water to 7.6 feet 
above mean high water. New work for completed project cost 
$1,894,282, including $8,752 expended by local interest for 
requiredwork, $580,435 contributed, other, funds, and amounts 
expended on previous projects (See Table 2-B for Authorizing 
Legislation). 
Local cooperation. Complied with except that local interests 
must furnish lands, easements and rights-of way for maintenance 
and for aids to navigation upon request of Chief of 
Engineers; hold the United States free from damages; make 
necessary removals or relocations of pipelines, cables and other 
utilities and all necessary protective measures to bridges and all 
other maintain necessary mooring facilities and utilities for 
recreational boating open to all on equal terms. 
Terminal facilities. See Port Series No. 5, revised 1965, 
Vol. 2 Part 2, pages 244-248. 
Operations and results during period. Under contract for 
removal and satisfactory disposal of all material except ledge 
rock above the planes of 15, and 6 feet below mean low water, 
work began on 6 July 1992 and was completed on 20 September 
1992. Approximately 195, 425 c.y. was removed at a total 
project cost of $1,984,967 
Condition as of September 30. Work under existing project 
was commenced April 1963 and was completed October 1964. 
7. GREAT SOUTH BAY, N.Y. 
Location. This is a lagoon inside south shore of Long 
Island, N.Y. about 26 miles long and 2 to 6 miles wide. Principal 
entrance, through Fire Island Inlet, is about 50 miles by water 
south and east of the Battery New York City (See Coast and 
Geodetic Survey Chart No. (12352) 
Previous projects. For details see Annual Reports for 1915 
and 1918, pages 1773, and 182, respectively, 
Existing project. A channel 200 feet Wide and 10 feet deep 
at mean low water from Fire Island Inlet to central basin in 
Great South Bay, and a channel 8 feet deep and 100 feet wide 
from central basin in bay to head of navigation in Patchogue 
River. Length of section included in project is about 19,1 miles. 
Mean tidal range in bay, 0.7 foot; mean range of spring tides, 0.8 
foot irregular fluctuations due to wind and barometric pressure 
vary from 1.7 feet below mean water up to 4.6 feet above mean 
high water. New Work for completed project cost $226,900 
exclusive of amounts expended on previous projects. For latest 
published map, see 1916 Annual Report, page 2018. (See Table 
2-B for Authorizing Legislation.) 
Local cooperation. None required 
Terminal facilities. In Great South Bay there are boat repair 
and storage yards, several commercial fish terminals, and ferry 
service to Fire Island. Many terminals have travelifts and there 
are public docks. Facilities are considered adequate for existing 
commerce. In addition to the commercial facilities there are 
numerous privately-owned terminals. 
2-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Operations and results during period . A contract for removal 
and satisfactory disposal of all material lying above the 
plane of 10 'below MLW was awarded on May 18, 1992. 
Dredging commenced on 30 September 1992. Operations & 
Maintenance funds in the amount of $357,369 was expended on 
Great South Bay during FY92. 
Conditions at end of fiscal year. Work under existing project 
was commenced November 1902 and completed June 
1958.Channel in Patchogue River was completed in 1904. West 
jetty, 1700 feet long, completed under previous project in 1897 
and repaired in 1914, and east jetty formed of a sand spit, 1,000 
feet long, with a riprap extension 330 feet long, completed in 
1917, are in good condition. 
8. HEMPSTEAD HARBOR, N.Y. 
Location. On the north shore of Long Island, 25 miles by 
water northeast of the Battery, New York City, and 13 miles 
southwest of Stamford Harbor, Conn. (Chart No. 12366.,) 
Previous project. For details see page 165, Annual Report 
for 1953. 
Existing project. (a) a channel 13 feet deep at mean low 
water and 150 feet wide from deep water in the harbor to North 
Hempstead Turnpike Viaduct, a distance of 2.1 miles; (b) 
thence 6 feet deep at mean low water and 50-80 feet wide to head 
of navigation, a distance of 0.2 miles; and (c) a turning basin off 
west side of channel north of Viaduct 9 feet deep at mean low 
water, 190 in net width and 470 feet in maximum length. 
Dredging the 13-foot channel is subject to the condition that no 
work -shall be done by the United States within 50 feet of any 
established pierhead line, wharf or other structure. Section 
included in project is about 2.3 miles long. Mean tidal range, 7.1 
feet; mean range of spring tides, 8.4 feet; irregular fluctuations 
due to wind and barometric pressure vary from 3.6 feet below 
mean low water up to 8.3 feet above mean high water. 
The present work in Hempstead Harbor involves removal 
and disposal of derelict barges in the shallow waters along the 
western shore. Estimated cost is $2,465,000 federal funds and 
$1,232,000 non-Federal. 
Local cooperation. Local interests must pay 33% of the 
construction cost of the barge removal project and ensure that 
the area will remain free of derelict vessels after construction is 
completed and hold the U.S. free from damages. A local 
cooperation agreement was signed in Sept. 1991. 
Operations and results during fiscal year. Work on the 
barge removal project was initiated in April 1992, resumed in 
Sept. 1992, and is about 30% completed. 
Condition at end of fiscal year. Work under the navigation 
portion of the project was commenced March 1912 and the 6- 
foot channel completed October 1912, Deepening the project to 
13 feet, as described above, has not been done, and has since 
been deauthorized.
9. HUDSON RIVER, N.Y. 
Location. Originates in Adirondack Mountains, about 250 
miles in a direct line and 315 miles along its course from the 
Battery. New York, City, and flows generally southerly into 
New York Bay- Section under improvement extends from New 
York City about 156 miles to Waterford. (See National Ocean 
Survey Charts 12335,12341,12343.12347,12348, and 14786.) 
Previous projects. For details see Annual Reports for 1915 
and 1938, pages 164 and 226, respectively. 
Existing projects. A channel 600 feet wide from New York 
City to Kingston, and thence 400 feet wide to Albany. with 
widening at bends, a turning basin 700 feet wide and 1,200 feet 
long at Albany, and 2 anchorages, I near Hudson and I near 
Stuyvesant, each 400 feet wide and an average length of 2,400 
feet; all with depths of 32 feet in soft material and 34 feet in rock 
to 2.200 feet south of the Mall Bridge; thence 27 feet deep and 
400 feet wide to 900 feet south of Mall Bridge, thence 14 feet 
deep at lower low water and generally 400 feet wide to Federal 
lock at Troy; and thence of same depth and 200 feet wide to 
southern limit of State barge canal at Waterford; and removal of 
State dam at Troy and construction of a lock and dam about 2.5 
miles below Waterford. Channel is to be formed by dredging 
and rock excavation, and maintained by dredging and constructing 
new, and raising and repairing old, longitudinal dikes, 
built partly under previous projects and partly by the State N.Y. 
In the tidal section below the Federal dam at Troy, the 
assumed lowest low water plane downstream to Albany is 3 feet 
below mean sea level. Mean tidal range is about 5 feet below the 
dam and about 4.9 feet at Albany. The normal pool level above 
the dam from Troy to Waterford is 14.3 feet above mean sea 
level, with the mean range of pool level in seasons of moderate 
rains being 2.2 feet. (See Table 2-C for features of lock and dam 
included in existing project.) New work for completed project 
cost $39,050,019 exclusive of amounts of expended on previous 
projects. Widening to form harbors at Albany and Troy, 
N.Y., to 12 feet deep ata cost of $522,000 (1954) and completion 
of 27-foot channel at Albany at a cost of $642,000 (1957) was 
placed in deferred for restudy category, and has since been 
deauthorized. All three features of work are excluded from 
foregoing description of existing project and cost estimate. 
Construction of mooring facilities has been authorized. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Complied with except that local interests 
must furnish suitable soil disposal areas for future maintenance 
as required. 
Terminal facilities. See Port Series No. 6 
2-6

NEW YORK, N.Y. DISTRICT 
Operations and results during period. A continuing cotract 
in the amount of $934,000 was awarded on August 31, 1992 to 
North Atlantic Trailing Company Limited Partnership for removal 
of approximately 100,000 cubic yards of material for the 
Hudson River Federal Navigation Project Channel. Funds in 
the amount of $549,996 were expended to initiate work on 
the continuting contract during FY 1992.In addition, Operation 
and Maintenance funds in the amoutnt of $80,850 were 
expended on engineering, design, supervision and administration 
for the dredging contract during FY 1992. 
Government Plant and hired labor were employed through 
the fiscal year in the removal of stumps, snags and other 
obstructions which constituted a potential hazard to navigation 
at a coat including supervision and administration of $250,608 
for maintenance in FY 1992., 
A contract in the amount of $30,813 was initiated and 
completed by a LaBarge Bros. Co. Inc. for chipping and 
grinding of previously placed material at the Van Wies Snag 
Placement Site during FY 1992. 
Government plant end hired labor were employed throughout 
the fiscal year with operation and maintenance of the Troy 
Lock and Dam, including the associated building and grounds. 
Operation of the Lock was suspended for the 1992 navigation 
season on November 27,1992 and was resumed for the 1992 
navigation season on May 1, 1992. Total funds expended for 
the operation and maintenance of the Troy Lock and Dam 
and the associated building and grounds, including supervision 
and administration was $867,807 for FY 1992. 
A continuing contract in the amount of $1,868,485 was 
awarded during FY 1991 to perform concrete repairs at the Troy 
Lock and Dam to insure continued operability and safety of the 
facility. FY 1992 funds in the amount of $1,720,014 were 
expended to substantially complete the contact work. In 
addition, Operation and Maintenance funds in the amount of 
$157,534 were expended on supervision administration on the 
contract. 
Condition as of September 30. Work underexistingproject 
began in July 1910 and was substantially completed in November 
1965. New lock and dam at Troy, removal of dam at Troy 
and construction of 15,545 linear feet of dikes also are complete. 
In reconstruction of old dikes 39,676 linear feet were 
raised to adopted crest height. Channel from New York City to 
Albany is complete to a depth of 32 feet except for the 1,500 
linear foot section at the northern end of the 32-foot project 
which has never been dredged to project depth. Additionally, 
the 1.300 linear feet of 27-foot project remains undredged. 
Channel from Albany to Waterford is complete to a depth of 14 
feet except for a small part of the widening to form a harbor at 
Troy. 
10: HUDSON RIVER CHANNEL, N.Y. & N.J. 
Location. Hudson River empties into Upper Bay of New 
York Harbor at the Battery, New York City. Section included 
under this title extends from deep water in Upper New York 
Bay about 14.5 miles to just north of Harlem River (Spuyten 
Duyvil Creek). 
Previous projects. For details see Annual Report for 1915 
and 1938, pages 1765, and 213 respectively. 
Existing project. A channel 48 feet deep and 2,000 feet 
wide, suitably widened at bends from West 59th Street, Manhattan, 
to West 40th Street thence 45 feet deep of same width 
to deep water in Upper Bay; a channel 40 feet deep to full width 
of river extending from northline of 59th Street to south side of 
Little Basin, and thence a channel of same depth to deep water 
in Upper New York Bay off Ellis Island, substantially as shown 
on maps in H. Doc. 309, 72d Cong., 1st sees., subject to 
provision that no dredging be done under project within 50 feet 
of pierhead lines; a channel 750 feet wide and 30 feet deep 
along Weehawken-Edgewater waterfront; removal of a shoal 
on New York side between West 59th and West 61st Streets to 
a depth of40 feet; and removal of an obstruction north of mouth 
of Spuyten Duyvil Creek to depth surrounding river bottom. 
Channel included in project is about 11 miles long. Plane of 
reference is mean low water. Mean tidal range at the Battery, 
4.4 feet, and West 129th Street, 4.1 feet; mean range of spring 
tides, 5.3 and 4.9 feet respectively: irregular fluctuations due to 
wind and atmospheric pressure vary from 3.8 feet below mean 
low water at the Battery up to 6.2 feet above mean high water 
and at West 129th Street from 3.6 feet below mean low water 
up to 5.3 feet above mean high water. (See Table 2-B for 
Authorizing Legislation.) 
Local cooperation. None required. 
Terminal facilities. See Port Series No. 5, revised 1988. 
Operations and results during period. Approximately 
252,600 c.y. of material was removed by Corps' Hopper Dredge 
McFarland during FY92. at the Edgewater-Weehawken reach 
of Hudson River, Channel, NY. The total cost for the work was. 
$2799, 533. 
Condition as of September 30. Work under existing project 
as commenced April 1913 and completed September 1952. 
Widening and deepening Weehawken-Edgewater Channel to 
project dimensions was completed in August 1937.Widening 
40-foot channel for full width of river from Ellis Island to West 
59th Street, Manhattan, was completed in March 1939. Widening 
48-foot project to full project width of 2,000 feet from West 
40th Street to West 59th Street was completed in November 
1950. Deepening 45-foot channel for a width of 2,000 feet from 
Upper Bay to West 40th Street was completed to project dimensions 
in September 1952. 
2-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
11. JAMAICA BAY, N.Y. 
Location. Inside south shore of Long Island, the entrance 
being about 17 miles by water south and east of the Battery. New 
York City. (See National Ocean Survey Chart No. 12350). 
Previous projects. For details see page 1770 of Annual 
Report for 1915, and page 185 of Annual Report for 1938. 
Existing project. Provides for an interior channel extending 
from vicinity of Marine Parkway Bridge along west and north 
shores of the bay, 18 feet deep at mean low water and 300 feet 
wide to Mill Basin, with a swinging basin, 1,000 feet wide and 
1.000 feet long at the point- thence 12 feet deep and 200 feet 
wide to Fresh Creek Basin; and interior channel extending from 
the same locality alone south shore to Head of Bay, 15 feet deep 
and 200 feet wide, a channel in Mott Basin, 15 feet deep and 200 
feet wide extending from the channel along south shore. 3.000 
feet to junction of the two branches, thence 2,200 feet in north 
branch (Inwood Creek) and 3,200 feet in south branch: and an 
entrance channel connecting the two interior channels with deep 
water in Atlantic Ocean, of suitable hydraulic dimensions to 
maintain present tidal prism in the bay, but not less than 18 feet 
deep and 500 feet wide from opposite Barren Island to Rockaway 
Point, thence enlarging to not less than 200 feet deep and 1,000 
feet wide to the sea, protected by one riprap jetty. Length of 
section included in project is 19.7 miles. Mean tidal range, 4.9 
feet at Barren Island, and 5.1 feet at Head of Bay; mean range of 
spring tides, 5.9 and 6.1 feet, respectively: irregular fluctuations 
due to wind and atmospheric pressure vary from 4 feet below 
mean low water to 4.9 feet above mean high water 
Cost for new work for completed project is $4,466,421 (July 
1961). excluding amounts expended on previous projects. 
Local cooperation. River and Harbor Act of 1945 provides 
that in lieu of conditions heretofore prescribed local interest 
furnish suitable areas for disposal of dredged materials for new 
work and subsequent maintenance, and hold the United States 
free from damages, City of New York was notified of conditions 
of local cooperation in letter dated January 25, 1946. In 
letter dated February 7, 1946, the Mayor of New York advised 
that disposal areas are available and necessary document" 
holding the United States free from claim for damages" would 
be executed. 
Riverand Harbor Act of 1950provides local interests furnish 
lands. easements, rights-of-way, and suitable areas for disposal 
of dredged material during construction and subsequent maintenance. 
hold the United States free from damages and perform 
all necessary alterations to existing terminals and bulkheads, 
and dredge adequate approaches thereto. These conditions have 
been fulfilled. 
Terminal facilities. See Port Series No. 5 revised 1988. 
Operation and results during period. A contract for the 
removal and disposal of material lying above the plane of 20 
feet below mean low water in Jamaica Bay, NY was awarded on 
21 February 1992. Work commenced 21 March 1992 and was 
completed 15 April 1992. The dredged material (sand) was 
placed at the nearby Plumb Beach to replenish the eroding 
shoreline. Approximately 146,000 c.y. of material was removed 
at total project cost of $1,485,000 
Condition as of September 30. 'Work under existingproject 
was commenced in August 1912 and completed in June 1961. 
Westerly interior channel from Barren Island to Fresh Creek 
Basin and swinging basin at Mill Basin were completed in April 
1929. Southerly interior channel and channel in Mott Basin, 
including its two branches were completed in June 1961 No 
new work dredging of entrance channel, was done, since depths 
provided underprevious project were greater than thoserequired 
under existing project. East jetty was restored to project dimensions 
in August 1963. 
12. KILL VAN KULL - NEWARK BAY CHANNEL, 
N.J. & N.Y. 
Location. The project includes Kill Van KULL connecting 
upper New York Bay with Newark Bay, and channels in lower 
Newark Bay serving Port Newark and Elizabeth Marine Terminal. 
These terminals are located on the west shore of Newark 
Bay. (See National Ocean Survey Chart 12333.) 
Existing project. Deepening the existing Kill Van Kull 
channel and channels in lower Newark Bay, including turning 
and maneuvering areas, as well as deepening the Elizabeth and 
Port Newark channels. The deepening to be done from the 
existing 35 foot depth incrementally to 40 feet and then 44 feet. 
The Federal cost of construction is estimated at over 
$312,000,000 with an additional $194,000,000 to be contributed 
by local interests. 
Local cooperation. The Port Authority of New York and 
New Jersey, the local cooperating agency, has entered into a 
local cooperation agreement with the Government which 
was executed on 30 May 1986. A supplemental agreement 
was executed on 21 May 1987. 
Terminal facilities. See Port Series No. 5, Vol. 2. 
Operations and results during period, and condition 
as of Sept. 30. Stage 1, channel deepening to 40 feet in six 
contracts, is underway. Contract No.1, awarded in June 
1987, is completed. Contract No. 2 was awarded in July 1988 
and is completed. Contract No. 3 was awarded in Sept. 1988 
and is completed. Contract No. 4 is planned to remove rock 
and hard material in the Kill Van Kull and Newark Bay. This 
work is divided in two contracts, 4A. and 4B. Contract 4A 
was awarded in April 1991 and is scheduled for completion 
in April 1994. Contract No. 5 was awarded in May 1988 and 
is complete. 
2-8

NEW YORK, N.Y. DISTRICT 
13. LONG ISLAND INTRACOASTAL 
WATERWAY, N.Y. 
Location. Extends from East Rockaway Inlet, on the 
south side of Long island, to Great Peconic Bay at the eastern 
end of Long Island. Section included under this project 
extends from Great South Bay opposite Patchogue to the 
South end of Shinnecock Canal. (See National Ocean 
Survey Chart 12352.) 
Existing project. A channel 100 feet wide and 6 feet deep 
at mean low water from the federally improved channel in 
Great South Bay, opposite Patchogue to south end of 
Shinnecock Canal, Section included in project is 34 miles 
long. Mean tidal range varies from 1 foot in Shinnecock bay 
to 0.7 foot in Patchogue Bay; mean range of spring tides 
varies from 1.2 feet to 0.8 foot; irregular fluctuations due to 
wind and atmospheric pressure vary from 1.8 feet below 
mean low water to 12 feet above mean high water. (See Table 
2-B for Authorizing Legislation.) 
Local cooperation. Complied with except local interest 
must furnish suitable spoil-disposal areas for future maintenance 
as required. 
Terminal facilities. There are boat repair and storage 
yards within the area immediately adjacent to the federal 
improvement. There is ample room for expansion and 
development of terminals when future traffic warrants. 
Operations and results during period. A contract for 
removal and satisfactory disposal of material lying above the 
plane of 10 feet below mean low water was awarded on 
August 14, 1992. Dredging commenced on September 29, 
1992 and expected to be completed by November 1993. Operations 
and Maintenance funds in the amount of $669,820 was 
expended on Long Island Intracoastal Waterway during FY92. 
Condition as of September 30. Original work under the 
existing project was commenced October,1939 and completed 
September 1940 
14. NARROWS OF LAKE CHAMPLAIN, N.Y. &VT. 
Location. This waterway. 37 miles long, comprises southern 
end of Lake Champlain and extends from Whitehall to 
Crown Point. N.Y. at southern extremity of lake, northerly to 
Benson Landing, Vt. (See N.O.S. Chart 14784). 
Previous projects. For details, see Annual Reports for 
1931, and 1963, pages 256 and 177, respectively. 
Existing project. A channel extending from Whitehall, 
N.Y. at head of Lake Champlain to Benson Landing, 12 feet 
deep at low lake level and generally 150 feet wide, and 
installation of fender booms at Putts Rock, Putts Leap, Narrows 
near Dresden, Pulpit Point and, Cedar Mountain. Reference 
plane of low take level is 93 feet above mean sea level. Section 
included in project is about 13.5 miles. Usual annual variation 
of lake level is 5.8 feet and extreme variation varies from 0.6 
foot below up to 8.8 feet above low lake level. 
Widening channel throughout its entire length to project 
width of 200 feet is inactive and excluded from foregoing 
description of existing project and cost estimate. (See Table 2- 
B for Authorizing Legislation. 
Local cooperation. None required. 
Operations and results during period. Government plant 
end hired labor were employed intermittently during the fiscal 
year in removal of stumps and snags that posed a potential 
hazard to navigation at a cost of $16,809. Government plant and 
hired labor were employed in the replacement of deteriorated 
fender booms at a cost of $8,081. Operations and maintenance 
funds in the amount of $13,884 were expended in FY 1992 on 
surveys and funds in the amount of $1,227 were expended on 
supervision and administration. 
Condition as of September 30. Work under the existing 
project was commenced June 1919 and is about 77 percent 
complete. A channel 12 feet deep at low lake level and least 
width of 150 feet has been excavated throughout the length of 
the improvement, except at the Elbow, where the width is 110 
feet. Fender booms have. been placed at the elbow. (Putts Leap 
and Putts Rock.) 
15. NEW YORK AND NEW JERSEY CHANNELS 
Location. Extends from deep water northwest of Sandy 
Hook, through Lower New York Bay and Raritan Bay, to Perth 
Amboy, and thence through Arthur Kill, Lower Newark Bay, 
and Kill Van Kull to deep water in Upper New York Bay. This 
route is approximately along boundary line between States of 
New York and New Jersey. (See National Ocean Survey Charts 
12333, 12331, and 12327.) 
Previous projects. For details see 1963 Annual Report 
pares 184 and 185. 
Existing project. A channel through Lower New York Bay, 
Raritan Bay, Arthur Kill, Lower Newark Bay, and Kill Van Kull 
to Upper New York Bay and Raritan Bay and in Arthur Kill to 
a point 1,000 feet north of Smith Creek, widened to 800 feet in 
vicinity of Seguine Point and Wards Point, respectively, thence 
500 wide to a point 1,000 feet south of Piles Creek; thence 500 
to 600 feet wide and passing, north of Shooters Island and 
protected by a dike on its northern side to junction of channel 
into Newark Bay; thence 800 feet wide through Kill Van Kull 
to Constable Hook; thence 1,000 feet wide for a point opposite 
the east end of Constable Hook to a point near the intersection 
with the channel along New Jersey pierhead line: and thence 
1,400 feet wide through Kill Van Kull to Upper New York Bay; 
with an anchorage 38 feet deep to accommodate five vessels 
2-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
south of Perth Amboy, all with suitable easing at bends and 
junctions. Section included in project is .30.8 miles long. In 
addition, construction of a dike north of Shooters Island and two 
secondary channels 30 feet deep and 400 feet wide, one south 
of Shooters Island and the other in Raritan Bay connecting with 
Raritan River, were completed under previous projects and 
maintained under existing project. A triangular area at the 
eastern end of the 30 foot channel south of Shooters Island was 
deepened to 35 feet in order to provide additional widening in 
the vicinity of Bergen Point and is included in the Newark Bay 
project. All depths refer to plane of mean low water. Mean 
range of tides varies between 4.7 and 5. 1 feet; mean range of 
spring tides 5.7 to 6.3 feet; irregular fluctuations due to wind 
and atmospheric pressure vary from 3.9 feet below mean low 
water up to 6.9 feet above mean high water. Anchorage at 
Sandy Hook and cutoff at junction of Main Ship Channel are 
deferred for restudy and excluded from foregoing description 
and cost estimate. (See Table 2-B for Authorizing Legislation.) 
Location cooperation. Fully complied with except for the 
middle section of Arthur Kill where local interest must furnish 
spoil disposal areas for maintenance. 
Terminal facilities. See Port Series No.5, revised 1988, 
Vol. 2. 
Operations and results during period A study entitled 
"Assessment and Treatment of Disposal Options for New York/ 
New Jersey Harbor Sediments" was performed and a contract 
was awarded on 22 September 1992 for additional Architect 
Engineer services in connection with the Long-Term dredged 
material plan for the NewYork/New Jersey region. Engineering 
and Design for future maintenance dredging of Perth Amboy 
& the Mainship Channel was also performed. Operation & 
Maintenance funds in the amount of $987,366 was expended 
for this project during FY92. 
Condition as of September 30. Work under active portion 
of existing project began in October 1933. Work completed 
consists of providing authorized project depth and widths 
throughout entire channel from Lower New York Bay to Upper 
New York Bay and providing depths of 37 and 25 feet in Perth 
Amboy Anchorage. In addition to above mentioned work, 
construction of dike north of Shooters Island, two secondary 
channels 30 feet deep and 400 feet wide, one south of Shooters 
Island, the other in Raritan Bay connecting with Raritan River 
were completed under previous projects. Work remaining under 
existing project consists of dredging cutoff at junction of 
Main Ship Channel to dimensions authorized by River and 
Harbor Acts of August 30, 1935, and May 17, 1950, dredging 
anchorage in vicinity of Sandy Hook. 
16. NEW YORK HARBOR-COLLECTION AND 
REMOVAL OF DRIFT 
Location. Applies to Lower and Upper Bays, New York 
Harbor; East River, Harlem River, Hudson River Channel, 
N.Y., New York and New Jersey Channels, Newark Bay, N.J. 
and their tributaries. 
Existing project. Provides for collection, removal and disposal 
of drift, derelict vessels, deteriorated shore structures and 
debris along shores of New York Harbor and tributary waters, 
and for the repair of certain other piers, wharves and shore 
structures. Work authorized before Act of 1974 was restricted 
solely to removal of drift from waterway and was funded as 
maintenance activity. The current estimate of first cost is 
$260,000,000 (October 1992 P.L.) including $61,000,000 cash 
contribution from local interests plus to be contributed for 
repair and disposal of deteriorated shore structures in use. (See 
Table 2-B for Authorizing Legislation.) 
Local cooperation. Local cooperation conditions of the 
plans currently under review by the Chief of Engineers provide 
that local interests must furnish all lands, easements and rightsof-
way required for the improvement; hold the United States 
free from damages; enact and enforce local legislation to 
prevent creation of sources of drift, contribute in cash one third 
of the first cost of the Federal work, and make necessary repairs 
to deteriorated structures in use so as to eliminate them as a 
source of drift. These conditions are subject to approval by the 
Secretary of the Army and the President, as stipulated in Section 
113 of the authorizing law, Public Law 91-611. 
Operations and results (New work-cumulative to date) 
A total of five Liberty State Park contracts have been 
completed at a cost of $10,321,121. East River-Manhattan 
Waterfront contract was completed at a cost of $1,477,806. A 
contract for the removal of Piers 17 and 1 8 on the East River 
was completed at a cost of $219,604. The City of Elizabeth 
contract was completed at a cost of $791,656. The Stapleton, 
Staten Island contract was completed at a cost of $2,910,400. 
A contract for the City of Hoboken was completed at a cost of 
$2,123,404. Work along the Jersey City South waterfront was 
completed at a cost of $979.580. Contract Number One at 
Weehawken toEdgewater was completed at acostof $1,697,487. 
The Brooklyn Reach One contract was completed at a cost of 
$5,057,920. Work is continuing on the Weehawken to Edgwater 
contract No.2. and Jersey City North ContractNo.2. The Bayonne 
One contract has been completed at a cost of $735,800. Hoboken 
Pier B was completed at a-cost of $973,590, and Jersey City 
North I was completed atacostof $2,358,000. Engineering and 
design is in progress for Brooklyn Reach 2. 
Maintenance. U.S. Derbris Boats Drifmaster, Gelberman 
and Hayward and auxiliary plant were assigned the task of 
removing and disposing of floating debris that is a hazard to 
navigation. Removal and disposal of 548,970 cubic feet (4,253 
cords) of floating debris consisting mainly of driftwood, ranging 
2-10

NEW YORK, N.Y. DISTRICT 
in size from small blocks to large timbers, including pilings, 
pieces, of wreckage, derelict vessels and sections of deteriorated 
pier structure was accomplished at a cost of $4,289,000 in 
FY 1992. 
Condition as of September 30. For work authorized by 
Water Resources Development Act, removal of drift sources 
has been completed in New Jersey at Liberty State Park, the City 
of Elizabeth, Hoboken, and parts of Jersey City, Weekawken 
and Edgewater. In New York City, work has been completed 
along the Manhattan side of the East River inclusive Of Piers 
17 and 18, Stapleton, Staten Island. Removal work is currently 
underway at Weehawken-Edgewater Contract 2, and of Jersey 
City North Contract 2. 
17. NEW YORK HARBOR-ENTRANCE CHANNELS 
AND ANCHORAGE AREAS 
Location. In Upper and Lower Bays, New York Harbor is 
330. miles southwest by water of Boston Harbor. Mass, and 165 
miles northwest of entrance to Delaware Bay, N.J. The Upper 
Bay extends about 5.5 miles southerly from junction of Hudson 
and East Rivers opposite the Battery, New York City to the 
Narrows. Lower Bay extends about 9 miles from the Narrows 
to the sea. (See National Ocean Survey charts 12334, 12335, 
and 12349.) 
Existing project. Ambrose Channel 45 feet deep and 2,000 
feet wide. extending about 10.2 miles from sea to deep water 
in the Lower bay; Anchorage Channel, an extension of 
Ambrose Channel, with same depth and width, in the Upper bay 
opposite anchorage grounds about 5.7 miles long and southerly 
entrance channel. Sandy Hook Channel (East Section) 35 feet 
deep and generally 800 feet wide extending 3.4 miles from 35- 
foot ocean contour to Bayside Channel along an alignment 
generally west of the South Channel; and elimination from 
authorized project of that portion of Bayside-Gedney Channel 
east of junction with new southerly entrance channel; for 
Bayside Channel 35 feet deep and 800 feet wide, extending 
about 5.3 miles from Bayside Channel to deep water in Lower 
bay; a channel alone New Jersey pierhead line connecting Kill 
Van Kull with deep water in anchorage Channel, south of 
Liberty Island anchorage. 20 feet deep for 500 feet wide with 
widening at bends to 800 feet and about 3 miles long; an 
anchorage in vicinity of Liberty (Bedloes) Island (about 160 
acres in extent) 20 feet deep; and for removal of Craven Shoal 
to 30 feet deep; for a channel 16 feet deep, 200 feet wide, and 
about 2.3 miles long. extending from bell buoy 23 to Hoffman 
and Swinburne Island; for an anchorage area in Red Hooks Flats 
to depths of 45,40 and 35 feet and an anchorage area in 
Gravesand Bay to47 feet deep. Projectdepthsrefer to mean low 
water. Mean tidal range is 4.7 feet at Fort Hamilton; mean range 
of spring tides, 5.7 feet; irregular fluctuations due to wind and 
atmospheric pressure vary from 3.9 feet below mean low water 
up to 6.2 feet above mean high water 
Location cooperation. Fully complied with. 
Terminal facilities. See Port Series No. 5, Vol.2. 
Operations and results during period, The U.S. Army Corps 
of Engineers Dredge"McFarland" was employed in FY92 to 
restore projects dimensions in New York Harbor Red Hook 
Flats Anchorage, A total of 26,186 cubic yards of material was 
removed at a project cost of $329,162. 
Condition as of September 30. Work under existing 
projects began in 1885 and is 100 percent complete. Main Ship 
and Bayside-Gedney Channels were completed to 30 feet deep 
in February 1891. Deepening of Bayside-Gedney Channel to 
35 feet for a width of 800 feet was completed in June 1939. 
Ambrose Channel was completed to 40 feet deep for a width of 
2.000 feet in April 1914 and substantially completed to 45 feet 
for a width of 2,000 feet in 1951. Relocation of Anchorage 
Channel was completed to 40 feet deep in October 1932. Center 
800 feet was dredged to45 feet in June 1947 and westerly 600- 
foot strip in April 1948. Easterly 600-foot strip was substantially 
completed in June 1953. Channel between Staten Island 
and Hoffman and Swinburne Islands was competed in December 
1920 up to within 300 feet of southerly limits of the project. 
Dredged channel meets all needs of navigation and no further 
work of improvement is contemplated for the present. Channel 
along New Jersey pierhead line from Kill Van Kull to Anchorage 
Channel was completed in March 1939. Widening at bends 
nearly southerly and northerly ends authorized in 1948 was 
completed to depths of 45, and 35 feet in October 1976. 
Anchorage Channel was relocated to the westward in 1982. Red 
Hook Flats Ancjorage was accordingly increased in area. No 
dredging was required. Liberty (Bedloes) Island anchorage was 
completed to 20 feet in October 1944. Sandy Hook Channel 
(east section was completed to a depth of 35 feet in June 1963. 
Gravesend Bay was completed to a47- foot depth in November 
1977. 
18.. SHINNECOCK INLET, N.Y. 
Location. On the south shore of Long Island, about 95 miles 
east of the Battery. New York City. It is an opening through 
the sandy barrier beach, connecting Shinnecock Bay with the 
Atlantic Ocean. (See National Ocean Survey Chart 12352.) 
Existing project. Provides fora channel 10 feet deep (mlw) 
and 200 feet wide with a deposition basin, thence extending 
through the inlet to Shinnecock Bay for a distance of about 0.7 
mile thence a channel 6 feet deep and 100 feet wide to the Long 
Island Intracoastal Waterway, a distance of about 1 mile: 
rehabilitation of the existing jetties and revetments. Estimate 
of cost for work is S22,300.000 of which the Federal share is 
$16.900,000 and non-Federal share is $5.400.000. 
2-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Local cooperation. The navigation improvement will accrue 
both recreational and commercial benefits which result in 
a first cost allocation of 69 percent Federal and 31 percent non- 
Federal. The authorizing document also requires that local 
authorities: provide without cost to the United States, all lands 
easements, rights-of-way, and suitable disposal areas for the 
initial work and for subsequent maintenance, when and as 
required; hold and save theUnited States free from damages due 
to the construction and maintenance of the project; maintain and 
operate the works after completion in accordance with regulations 
prescribed by the Secretary of the Army; provide and 
maintain suitable terminal facilities when and as required for 
the accommodation of vessels that would navigate the inlet and 
adjacent bays, open to all on equal terms; maintain, for the 
duration of the economic life of the project, continued public 
ownership of the publicly owned shores and their administration 
for public use, and continued availability for public use of 
the privately owned shores upon which a portion of the Federal 
share of the costs is based. A Local Cooperation Agreement for 
the dredging element of the project was executed with the New 
York State Department of Environmental Conservation on 7 
June 90. A Local Cooperation Agreement for the jetty reconstruction 
phase of work was executed on Dec 10,1991. 
Terminal facilities. Shinnecock Bay, and adjacent ocean 
area, constitute an important marine fishery. The public fishing 
facility includes three docks, one of which, the Shinnecock 
Fishermens Cooperative, stores and market the catch for the 
fishermen. 
Operations and results during period. A contract was 
awarded on March 31, 1992 for Jetty Repair and maintenance 
dredging for Shinnecock Inlet. Jetty repair commenced on May 
21,1992, and maintenance dredging will be completed in FY93. 
Operations and Maintenance funds in the amount of $545,596 
was expended for O&M portion of the work during FY92. 
Condition as of September 30. The initial dredging element 
of the project has been completed. Work is proceeding on 
the jetty re-construction project and also maintenance dredging 
of the channel. 
19. SHREWSBURY RIVER, N.J. 
Location. Mainly a large tidal basin in eastern part of New 
Jersey, the outlet being at the southeast end of SandiHook. (See 
National Ocean Survey Chart 12324.) 
Previous projects. For details see Annual Reports of 1915, 
1918, and 1938. pages 1778, 373, and 267, respectively. 
Existing project. A channel 12 feet deep and 300 feet wide, 
following the westerly shore, from deep water in Sandy Hook 
Bay 2.2 miles to a point 500 feet south of former location of 
railroad bridge at Highlands; then 9 feet deep and generally 150 
feet wide, suitably widened at bends and turns, in south branch 
of river 6.8 miles to Branchport Avenue Bridge in city of Long 
Branch: and a channel in north branch (Navesink R.) 6 feet deep 
and 150 feet wide 6.1 miles from the junction to Red Bank. 
Plane of reference is mean low water. Mean range of tide at 
Highlands, 3.8 feet; at Seabright, 1.7 feet; at Branchport, 1.7 
feet; and at Red Bank, 3 feet. Mean range of spring tides is 4.7, 
2.1, 2.2, and 3.6 feet respectively, irregular fluctuations due to 
wind and atmospheric pressure vary from 1.9 feet below mean 
low water up to 6.5 feet above mean high water. (See Table 2- 
B for Authorization Legislation.) 
Local cooperation. River and Harbor Act of 1950 provides 
local interests furnish lands, rights-of-way, and spoil-disposal 
areas for construction and future maintenance; hold the United 
States free from damages; provide and maintain a suitable 
public wharf on each of the creeks to be improved, which shall 
be open to all on equal terms; remove Locust Avenue bridge 
over Claypit Creek; and make cash contributions of $25,000. 
$33,000 and $27,500 toward cost of improvement of Claypit. 
Oceanport, and Little Silver Creeks. respectively. Provided 
further that construction of any unit of proposed improvement 
may be undertaken independently of the other units when the 
required local cooperation has been provided. These conditions 
have not been fulfilled. Requirements under prior acts have 
been fully complied with. 
Terminal facilities. There are numerous terminals along the 
waterway. Some of which are open to the public. In addition, 
many private pleasure boat landings have been constructed by 
owners of riverfront property. None of the terminals has direct 
rail connections. Facilities considered adequate for existing 
commerce. 
Operations and results during period. A continuing 
contract in the amount of $2,884,932 for maintenance dredging 
was awarded in June 1990. Work commenced on July 1990 
and was substantially completed by September 1991. Additional 
$300,000 was obligated in FY92 for this project. 
Condition as of September 30. Work under the active portion 
ofexistingprojectbegan in October 1919. Work completed 
consisted of providing authorized project dimensions in 12-foot 
entrance channel. 9-foot channel in South Branch, and a 6-foot 
channel in North Branch of the river. Work remaining (dredging 
an inlet channel across the base of Sandy Hock protected by 
jetties and bulkheads, a bay channel extending to the existing 
Shrewsbury River Channel and a six-lane fixed highway, bridge 
to span the new inlet as authorized by the River and Harbor Act 
of 1965) was subsequently reclassified to inactive because of 
state and local opposition. Formal close out of this work 
remains. Under the RiverandHarbor Actof 1950 work remaining 
consists of dredging turning basin and anchorage in vicinity of 
Red Bank and channels in Claypit, Oceanport, and Little Silver 
Creeks. 
2-12

NEW YORK, N.Y. DISTRICT 
Note: Work under the Acts of 1950 and 1965 has since been 
deauthorized. 
20. TARRYTOWN HARBOR, N.Y. 
Location. Extends along east shore of Hudson River for 
about 1 mile below Kingsland Point, 29 miles above the Battery, 
New York City. 
Existing project. A channel along wharf front of the harbor 
12 feet deep at mean low water and 250 feet wide, and northerly 
and southerly connections with deep water in Hudson River of 
same depth and 150 feet wide; total length, about 1 mile. Mean 
tidal range, 3.1 feet; mean range of spring tides, 3.7 feet; 
extreme range due to wind and barometric pressure, 8.2 feet; 
irregular fluctuations are infrequent and do not materially affect 
navigation. New work for completed project cost $69,836. 
Local cooperation. None required. 
Terminal facilities. Terminals with a total available dockage 
of about 3,000 feet are along the waterfront. Railroad connections 
are adjacent to the waterfront. Terminals are considered 
adequate for present commerce. 
Operations and results during period. -Under a continuing 
contract for maintenance dredging to restore project depth of 
12 feet, work commenced on 22 September 1992 and was 
completed on 22 October 1992 to remove 109,069 cubic yards, 
place measurement of material. Operations & Maintenance 
funds in the amount of $220,195 was expended on this project 
during FY92. 
Condition at end of fiscal year. Existing project commenced 
in April and was completed in July 1937. Controlling depth 
mean low water (Oct-Nov. 1965) was 12 feet for 150 feet width 
in southerly connecting channel, then 12 feet for 250 feet width 
in the channel along the wharf, then 12 feet for a width varying 
from 250 to 150 feet in northerly channel. 
21.WESTCHESTER CREEK, N.Y. 
Location. A tidal stream flowing into East River from north 
at a point 14 miles by water northeast of the Battery, New York 
City. (See National Ocean Survey Chart 12336.) 
Previous projects. For details see Annual Reports for 1921 
and 1938, pages 238 and 164, respectively. 
Existing project. A 2.6 mile channel 12 feet deep at mean 
low water, 100 feet wide for 2,000 feet through the estuary; 
thence 80 feet wide for 3,000 feet; and thence 60 feet wide 8,800 
feet to head of navigation at East Tremont Avenue (Fort 
Schuyler Road), with widening at bends, and two turning 
basins, one near upper end of channel, the other near Eastern 
Boulevard (Unionport) Bridge. Mean tidal range, 7 feet; mean 
range of spring tides, 8.4 feet; irregular fluctuations due to wind 
and atmospheric pressure vary from 3.9 feet below mean low 
water up to 8.4 feet above mean high water. New work for 
completed active portion of the project cost $98,751 exclusive 
of amounts expended on previous projects. Dredging turning 
basin to a depth of 12 feet below mean low water, 250 by 1250 
feet in extend. 500 feet downstream from head of navigation, is 
inactive and excluded from foregoing description and cost estimate. 
(See Table 2-B for Authorizing Legislation.) 
Local cooperation. River and Harbor Act of 1954 provides 
that local interests agree to furnish lands, easements, and rightsof-
way for construction and maintenance and furnish suitable 
spoil-disposal areas for initial work and future maintenance as 
required; hold the United States free from damages; and provide 
and maintain a suitable bulkhead or other works approved by 
Chief of Engineers for retaining the east bank of the turning 
basin alongside Hutchinson River Parkway; and that local 
interests give assurances they will construct a public wharf 
when required. Requirements under prior acts have been fully 
complied with. 
Terminal facilities. See Port Series No. 5, revised 1988, 
Vol. 2. 
Operations and results during period. A contract for the 
removal of all material, except ledge rock, lying above the plane 
of 12 feet below mean low water with satisfactory disposal of 
dredged material at the EPA's approved Mud Dump site in the 
Atlantic Ocean was awarded on 28 June 1991. The dredging 
work commenced on 5 Sept. 1991 and was completed on 22 
November 1991. Approximately 110,000 c.y. of material was 
removed from the project channel. Operations and maintenance 
funds in the amount of $180,006 was expended on Westchester 
Creek during FY92. 
Condition as of September 30. Work under the entire existing 
project is about 82 percent complete. Work under active 
portion of existing project commenced March 1932 and was 
relocated by city of New York in 1941. Head of navigation is 
at East Tremont Avenue, Bronx, about 2.6 miles above the 
mouth. Work remaining under existing project, consists of 
dredging to 12 feet below mean low water a turning basin 250 
by 250 feet in extent to be 500 feet downstream from head of 
navigation. 
22. SUPERVISOR OF NEW YORK 
HARBOR(PREVENTION OF OBSTRUCTIONAND 
INJURIOUS DEPOSITS) 
The District Engineer, New York District, was designated 
Supervisor of New York Harbor under the provisions of the 
River and Harbor Act of June 29, 1888 (33 U.S.C.441-451), as 
amended July 12, 1952. Under this Act, the Supervisor of New 
York Harbor is charged with the mission of preventing the 
deposit of obstructive and injurious materials in New York 
2-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Harbor and its adjacent and tributary waters, including Long 
Island Sound. The River and Harbor Act of August 18,1894 (33 
U.S.C. 452) makes it unlawful for any person or persons to 
engage in fishing or dredging for shellfish in any of the channels 
leading to and from New York Harbor, or to interfere in any way 
with the safe navigation of deep draft traffic; the River and 
Harbor Act of March 3. 1899 (33 U.S.C. 403, 407, 409) 
prohibits obstructions to navigable waters such as unauthorized 
structures, unauthorized fill, deposit of refuse, and willful or 
negligent abandonment of vessels. Other laws relating to the 
supervision of New York Harbor and its tributary waters are the 
Clean Water Act, the Marine Protection, Research and Sanctuaries 
Act of 1972, the Coastal Zone Management Act of 1969, 
the Fish and Wildlife Act of 1956, the Federal Power Act of 
1920, the National Historic Preservation Act of 1966, the 
Endangered Species Act of 1973, the Deepwater Port Act of 
1972, the Wild and Scenic Rivers Act, and the Land and Water 
Conservation Fund Act. 
Direct supervision of the waters under the jurisdiction of the 
New York District is accomplished by means of a patrol vessel 
whose scope of duty includes surveillance of the water front for 
unauthorized construction or fill, surveillance to the 3-mile 
limit of tows enroute to dumping grounds in the Atlantic Ocean 
to ensure that material is not illegally deposited in the waters of 
New York Harbor, and investigation of wrecks and abandoned 
vessels. In addition to the patrol vessels, whose range of patrol 
is limited to New York Harbor, inspectors utilizing government 
vehicles equipped with two-way radios patrol shorefront facilities 
and property. The inspectors operate out of the New York 
District Office. Their duties include inspection of authorized 
construction, fill or excavation in waterways, including wetland 
areas, to ensure that work is performed in accordance with the 
Corps permit, as well as investigating unauthorized construction 
activities. The inspectors also patrol all waterways in their 
respective areas and inform the public of the Corps' role and 
jurisdiction as well as provide assistance in the preparation of 
permit application. (See Table 2-E at end of chapter.) 
23. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 2-F at end of chapter.) 
24. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 2-G at end of chapter.) 
25. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities pursuant to Section 107, Public Law 
645, 86th Congress as amended (Pre-authorization). 
(See Table 2-N at end of chapter.) 
BEACH EROSION CONTROL 
26. ROCKAWAY INLET TO NORTON POINT 
(CONEY ISLAND AREA), N.Y. 
Location. Atlantic coast of New York City, in Brooklyn 
(Kings County), approximately nine miles south of the Battery, 
N.Y. City. 
Existing project. Authorized by the Water Resources Development 
Act of 1986. The authorized plan provides for beach 
erosion control by restoring the Coney Island public beach up 
to 250 feet beyond its historic shoreline; the extension of the 
westerly terminal groin; construction of a terminal groin at the 
easterly end of the restored beach, and a fillet of beachfill from 
the terminal groin at W. 37th St. extending approximately 2300 
ft. into the community of Sea Gate. The authorized plan also 
provides, for restoration of the beach by periodic beach nourishment. 
The estimated project construction cost is $144,780,000 
(Oct 1992. P.L.). 
Local cooperation. The local sponsor is the N.Y. State Dept. 
of Environmental Conservation. The local agreement has not 
been finalized, but the customary provisions are that local 
interests will; provide without cost to the United States all 
lands, easements, and rights-of-way including borrow areas 
necessary for construction of the project, hold and save the 
United States free from claims for damages which may result 
from the construction works and subsequent maintenance of the 
project; provide a cash contribution toward the total first cost; 
assure that water pollution that would affect the health of 
bathers will not be permitted; assure continued conditions of 
public ownership and use of the shore upon which the amount 
of Federal participation is based, during the economic life of the 
project; maintain public use facilities open and available to all 
on equal terms and maintain all improvements after completion 
in accordance with regulations prescribed by the Secretary of 
the Army, including periodic nourishment during the economic 
life of the project as may be required to serve the intended 
purpose, subject to Federal participation in the cost of periodic 
nourishment for the economic project life. 
Operations and results during period, and condition as of 
September 30. The General Design Memo was approved in 
'92. The final Supplemental EIS was submitted in May '92. The 
Local Cooperation Agreement is in process. Initiation of construction 
is expected in June 1993. 
27. SANDY HOOK TO BARNEGAT INLET, N.J. 
Location. The northern portion of the Atlantic coast of New 
Jersey extending from Sandy Hook southerly to Barnegat Inlet 
- length about 48 miles. Erosion has seriously reduced the 
2-14

NEW YORK, N.Y. DISTRICT 
width of most beaches in the study area with consequent 
exposure of the shore to storm damage. Because of this erosion 
of the shore the area does not provide sufficient recreational 
beaches for the proper accommodation of the present and prospective 
tributary population. 
SECTION I - SEA BRIGHT TO 
OCEAN TOWNSHIP, N.J. 
Location. That portion of the Atlantic coast of New Jersey 
in Monmouth County extending from Sea Bright southerly to 
Ocean Township - length about 12 miles. Sea Bright is about 30 
miles by water south of the Battery, New York City. 
Authorized project. The WaterResources Development Act 
of 1988 (PL 100-670) authorized a plan substantially in accordance 
with the plan recommended in the General Design 
Memorandum for the project dated May, 1988. In general the 
plan provides for beach erosion control along approximately 12 
miles of coastline, extending from Sea Bright southward to 
Ocean Township, New Jersey, by artificial placement of sand to 
widen the beach berm to 100 feet at an elevation of 10 feet above 
mean low water with an additional 2 foot high berm cap to 
provide an extra increment of protection from overtopping. The 
project also provides for the notching of 15 groins, and periodic 
nourishment throughout the 50 year economic life of the project. 
Total estimated Federal cost for Section I is $620,900,000. 
Total estimated non-Federal cost for all requirements of local 
cooperation is $331,600,000. 
Local cooperation. Includes reconstruction of sea wall at 
Sea Bright and all lands easements, rights of way and drainage 
outfall extensions. 
Operations and results during period and condition as of 
September 30. The Local Cooperation Agreement has been 
signed by the State of New Jersey. It is anticipated that construction 
will begin in the Spring of 1993. The State of New 
Jersey has completed reconstructing the seawall. 
SECTION II- ASBURY PARK TO 
MANASQUAN, N.J. 
Location. That portion of the Atlantic coast of New Jersey in 
Monmouth County extending from Asbury Park southerly to 
Manasquan - length about 9 miles. 
Recommended project. Provides for Federal participation 
in the restoration and protection of the shore from Asbury Park 
to Manasquan by artificial placement of sand to widen the beach 
to a minimum width of 100 feet at an elevation of 10 feet above 
mean low water. The project provides for Federal participation 
in periodic nourishment costs for a period of 50 years from the 
year that the total quantity to fill placed has equalled that 
required to restore the beach to project dimensions. Total 
estimated cost is $236,500,000 (See Table 2-B for Authorizing 
Legislation.) 
Operations and results during period and condition as of 
September 30. The project is in active planning status. A draft 
General Design Memo was submitted for approval on Sept 30 
1992. 
28. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 2-H at end of chapter.) 
29. BEACH EROSION CONTROL 
WORK UNDER SPECIAL AUTHORIZATION 
Beach Erosion Control activities pursuant to Section 103 
Public Law 826, 84th congress as amended (None during FY 
1992) 
FLOOD CONTROL 
30. NORTH ELLENVILLE, N.Y. 
Location. In Ellenville, N.Y., on Beer Kill and Fantine Kill, 
at their confluence with Sandburg Creek. which discharges into 
Rondout Creek at Napanoch, N.Y., about 2 miles downstream 
from Ellenville. (See Geological Survey, Ellenville quadrangle). 
Existing project. Improvementincludes construction of levees 
and floodwalls along Beer Kill and Fantine Kill-I capping 
retaining walls along Beer Kill; removing concrete dam, channel 
improvements and stream diversion on Fantine Kill; providing 
interior drainage including diversion ditches drainage structures, 
popnding areas; alteration of 6 bridges: and relocating 
structures and utilities. The project was completed in 1975. 
Since that time severe storms in March 1980 and April 1987 
caused erosion of the riprap bank protection and significant 
damage to the project floodwalls and levees, Subsequent repairs 
to damaged areas were undertaken in 1981-82 and in 1987-88 
under PL-84-99 authority. A Design Deficiency Report has 
been prepared and submitted to Office of Chief of Engineers. 
The recommended plan for design deficiency correction involves 
repair, reinforcement, and replacement of undermined 
floodwalls, placement of riprap protection along the Beer Kill 
Channel bottom and toes of banks; repair and replacement of 
riprap along the side slopes and toes of the levees, and possible 
removal of a rock outcrop to reduce erosive velocities. The 
current Federal cost estimate is $4,650,000 (Oct. 92-P.L.) 
Local cooperation. Assurances of Local Cooperation were 
received from the New York State Department of Environmental 
Conservation in 1968 and 1970. An additional Local Cooperation 
Agreement was signed in November 1987 to cover 
the repairs accomplished through the PL-84-99 effort. In a letter 
dated 9 November 1990, the New York State Department of 
Environmental Conservation indicated their willingness to participate 
and act as local sponsor under the terms of Section 414 
2-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
of the 1990 WaterResources Development Act (the non Federal 
share of the cost to correct the deficiency will be the same as at 
the time the project was authorized and constructed). 
Operation and results during period, and condition as of 
Sept. 30. The Project Deficiency Report was approved and the 
work allowance was used in preparation of a Design Memorandum. 
Construction has not been initiated. 
31. PASSAIC RIVER BASIN, N.J. & N.Y. 
Location. The Passaic Basin, comprising 787 square miles in 
northeastern New Jersey and 148 square miles in southern New 
York State, is located in the greater New York City Metropolitan 
area. The Passaic River Basin is roughly elliptical in shape 26 
miles long and 56 miles wide - and contains portions or 
Bergen, Essex, Morris, Passaic, Hudson, Somerset, Sussex and 
Union Counties in New Jersey. The Basin also includes parts 
of Orange and Rockland Counties in New York. 
Previous projects. Three Federal flood control projects have 
been completed by the Corps of Engineers in the Passaic River 
Basin. A $67,400 desnagging, debris removal, and channel 
restoration project was completed in 1951 along Beaver Brook 
and the Pequannock Township Ditch, tributaries of the Pompton 
River in Pequannock Township, NJ. 
Along the Pompton River, a channel clearing project including 
shoal removal and channel restoration was implemented in 
the two-mile reach from the Delaware, Lackawanna and Western 
Railroad Bridge to the Erie Railroad (Greenwood Lake 
Branch) Bridge. This work, in Pequannock Township, Wayne 
Township and Lincoln Park Borough, NJ., was completed in 
1954 at a cost of $50,000. 
A $1.5 million basin-wide project to improve the Flood 
Warning and Preparedness System was completed in 1988. 
This project includes enhanced and increased number of rain 
and stream flow gauges in combination with a state-of-the-art 
communication and computer system designed to improve the 
occupancy and reliability of flood warning in the Passaic River 
Basin. The project was implemented by the Corps of Engineers 
in conjunction with the National Weather Service and U.S. 
Geological Survey, the State of New Jersey is the non-Federal 
sponsor of the project. 
Project history. U.S. Army Corps of Engineers involvement 
in Passaic River planning was first authorized in the 
Flood Control Acts of 1936. Since then, reports recommending 
plans of action were issued in 1939, 1948, 1962, 1972, and 
1973. None of these plans were implemented because they did 
not receive widespread public support, with opposition based 
on the concerns of municipalities and various other interests 
throughout the Basin. In 1976, Congress authorized a Phase I 
Advanced Engineering and Design Study in Section 101 (a) of 
the Water Resources Development Act of 1976. Congressional 
Guidance on the conduct of the study was provided in House 
Report 94-1702. This reformulation study was initiated in 
October 1977 and the overall study was completed in December1989. 
Local protection plans were completed for tributary 
flood damage areas along the Ramapo and Mahwah Rivers at 
Mahwah, N.J., and Suffern,N.Y., Molly Ann's Brook at Haledon, 
Prospect Park and Paterson, N.J., the Ramapo River at Oakland, 
N.J., and the Lower Saddle River in Bergen County, N.J. These 
projects were authorized in the Water Resources Development 
Act of 1986 A wide range of feasible basin-wide alternative 
plans were developed. These alternatives, which were presented 
for extensive public review, included tunnel diversions, channel 
modification, levees and floodwalls, and nonstructural 
measures. 
In April 1984, the Passaic Basin experienced flooding 
estimated to be the worst in 40 years. In June 1984, the State 
of New Jersey selected a dual inlet diversion tunnel plan as the 
preferred Basin-wide alternative for detailed plan formulation. 
. The Phase I General Design Memorandum and draft Environmental 
Impact Statement, (EIS), recommending the Pompton 
River/Passaic Dual Inlet Tunnel Diversion Plan, were completed 
during FY 1988. The Phase I report was approved by the 
Board of Engineers for Rivers and Harbors (BERH) on July 23, 
1988 and by the office of the Chief of Engineers on 3 February 
1989. The final EIS was filed with EPA in December 1988, with 
the comment period ending in January 1989. OMB approved 
the report 5 February 1990. OASA (CW) transmitted the report 
to the House of Representatives on 8 March 1990. 
Condition as of September 30. Section 101 (a) 18 of the 
Water Resources Development Act (WRDA) 1990 (PL 101- 
640), as modified by section 102(p) of WRDA'92 (PL 102-580) 
authorizes construction of the Passaic River Flood Protection 
Project for the Passaic River Basin which will address both 
environmental and engineering objectives of the Act. The 
Passaic River Flood Protection Project combines diversion 
tunnels, levees, flood walls, channel modification, and natural 
flood storage to provide flood protection to about 35 towns in 
the Passaic River Basin. The Federal government is to pay 
$1,017 million; the State of New Jersey's share of the project's 
cost - $353 million in today's dollars-will be paid in increments 
spread over the duration of construction. However, the 
actual cash contribution by the State of New Jersey may be 
reduced by crediting provisions of the WRDA '90 and WRDA 
"92. 
The U.S. Army Corps of Engineers is designing the $1.37 
billion flood control project for the State of New Jersey, the 
non-Federal sponsor. The Corps' goal is to restore or replace any 
wetlands and wildlife habitats that the project may disturb so 
that there is no net loss of wetlands. 
2-16

NEW YORK, N.Y. DISTRICT 
The authorizing legislation modifies the project recommended 
in the Phase 1 report by eliminating 13.5 miles of levees 
and floodwalls in South Bergen and Essex counties, and by 
extending the flood diversion tunnel .by over six miles to outlet 
in Newark Bay. The tunnel extension provides fluvial flood 
protection to the lower Passaic River without any structural 
works whatsoever. The legislation also authorizes the Corps to 
participate in the maintenance and operation of the water 
diversion tunnels, the most expensive part of the project. The 
authorization also provides for a $25 million streambank restoration 
in the City of Newark. 
The project calls for the acquisition of 5,350 acres of water 
storage areas, 5,200 of which are wetlands. In an agreement 
with the Corps, the State has promised to continue to protect an 
additional 6,300 acres that are part of the project. Thus there will 
be no secondary development in these areas. The act also 
establishes a wetlands bank and allows the State of New Jersey 
to credit more wetlands, parklands, watershed lands toward its 
share of the project cost. WRDA '92 expanded the streambank 
restoration features, authorized a flood warning and emergency 
operations center and amended the wetland bank credit provision. 
32. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspections of completed flood control works and beach 
erosion and hurricane protection projects were performed to 
determine the extent of compliance by local interests with 
operation and maintenance requirements. 
33. OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
(See Table 2-1 at end of chapter.) 
34. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Natural Disaster and Emergency Flood Control Activities. 
Pursuant to Public Law 84-99 and antecedent legislation 
provides for disaster preparedness, emergency operation, rehabilitation, 
advance measures, emergency water, and drought 
assistance. 
Under disaster preparedness, the New York District completed 
revisions of various emergency manuals and pamphlets, 
attended meetings and seminars dealing with emergency response 
and preparation, and purchased supplies and equipment 
to maintain its' flood fighting and response capability. 
Under emergency operations, the New York District provided 
technical assistance and sandbags to local and county governmental 
organizations which requested such aid during several 
minor storm/flood events. 
Pursuant to Public Law 93-228 the New York District providedassistance 
to the Federal Emergency Management Agency 
(FEMA) in connection with Hurricane Andrew disaster recovery 
operations in Florida. 
35. EMERGENCY STREAMBANK 
AND SHORELINE PROTECTION 
Activities pursuant to Section 14, Public Law 526, 79th Congress 
as amended (Preauthorization). (See Table 2-Q at end of 
chapter.) 
36. SURVEYS 
(See Table 2-J at end of chapter.) 
37. COLLECTION AND STUDY 
OF BASIC DATA 
Costs for the period of $92,281 for flood plain management 
services are set forth in Table 2-L at the end of chapter. 
38. DEAUTHORIZED PROJECTS 
Projects having all, or inactive or uncompleted portions 
deauthorized by Congressional Action pursuant to Water Resources 
Development Acts (See-Table 2-M at end of chapter.) 
2-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-A COST AND FINANCIAL STATEMENT 
see 
Section Total Cost to 
in Text Projects Funding FY 89 FY 90 FY 91 FY92 September 30, I1992 
1. Aquatic Plant 
Control 
2. Bay Ridge & Red 
Hook'Channels, N.Y. 
3. East Chester Creek, 
N.Y. 
4. East Rockaway Inlet, 
N.Y. 
5. Fire Island To 
Jones Inlet, N.Y. 
6. Flushing Bay and 
Creek, N.Y. 
7. Great South 
Bay, N.Y. 
8. Hempstead Harbor, 
N.Y. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Week 
Approp. 
Cost 
Maint 
Approp. 
Cost 
140,000 140,000 
121,294 129,117 
132,000 20,000 1,885,806 1 
24,310 114,007 1,809,065 2 
5,523.297 
5,523,297 27 
3,091,000 136,368 
3,090,000 138,204 
2,020,000 2,080,110 40,921,666 
2,019,901 2,080,098 40,921,313 
592,056 
592,056 
969,000 
972,107 
215,678 
64,942 
161,530 173,001 3,122,251 
161,529 172,697 2,970,469 
83,969 4 
533,334 
855,000 
855,866 
836,820 
834,653 
486,000 1,556,555 50,000 
6,567,178 1,558,999 51,410 
368,000 358,003 10,405,559 
370,296 357,062 10,404,614 
3,341,000 125,000 4,060,360 
3,299,572 336,017 4,229,944 2 
1,420,103 16,780,054 
1,414,825 16,841,504 
2,113,502 10.11 
2,102,905 
121,000 
125,210 
103,714 
103,679 
60,035 
60,034 
1,985,000 7,690,629 10 
1,984,967 7,688,769 
266,857 
266,857 
360,000 
306,703 
200,000 
290,582 
100,000 360,000 1,743,699 
100,000 357,369 1,741,068 
270,000 2,508,000 3,434,470 
287,054 337,348 1,298,149 
76,497 
76,497 
2-18

NEW YORK, N.Y. DISTRICT 
TABLE 2-A COST AND FINANCIAL STATEMENT 
see 
Section Total Cost to 
in Text Projects Funding FY 89 FY 90 FY 91 FY92 September 30, 1992 
9. Hudson River, N.Y. 
10. Hudson River 
Channel, N.Y. 
11. Jamaica Bay, N.Y. 
12. Kill Van Kull-Newark 
Bay, N.J. & N.Y. 
13. Long Island 
Intracoastal 
Waterway, N.Y. 
14. Narrows of Lake 
Champlain, N.Y. 
15. New York and New 
Jersey Channels 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Approp. 
Cost 
Maint. 
Approp. 
cost. 
- - - - 44,-249,800 6.'7 
- - - - 44,249,865 
2,110,000 2,384,226 2,545,000 3,926,911 46,553,452 8.9 
2,114,916 2,392,670 2,544,978 3,922,485 46,438,629 
- - - - 6,771,870 
- - - - 6,771,870 13 
295,000 
294,998 
45,000 
S44,939 
640,000 2,800,002 28,750,639 
640,060 2,799,533 28,750,167 
4,545,753 
4,545,753 
47,350 
47,212 
2,390.000 1,485,000 8,760,477 
2,390,138 1,485,000 8,737,032 
14,904,000 16,300,000 12,792,000 51,139,000 146,849,000 
42,443,863 22,826,306 12,109,869 56,699,017 146,460,398 
-- - - 235,964 
-- - - 235,964 
47,000 
71,296 
55,000 
55,253 
222 
222 
64,396 
64,854 
245,002 680,006 8,874,877 
244,996 669,820 8,877,402 
40,000 40,002 
39,999 40,002 
681,811 12 
681,811 
1,282,091 
1,282,061 
- - - - 73,052,435 15,16,17 
- - - - 73,052,435 
97,000 2,039,022 1,690,000 989,161 15,020,542 
1,212,679 1,948,728 2,078,515 987,366 49,367,835 18 
2-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-A COST AND FINANCIAL STATEMENT 
see 
Section Total Cost 
in Text Projects Funding FY 89 FY 90 FY 91 FY92 September 30, I1992 
16. New York Harbor- 
Collection and 
Removal of Drift 
17. New York Harbor- 
Entrance Channels & 
Anchorage Areas 
18. Shinnecock Inlet, 
N.Y. 
19. Shrewsbury River, 
N.J. 
20. Tarrytown 
Harbor, N.Y. 
21. Westchester Creek, 
N.Y. 
22. Supervisor of New 
York Harbor 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
cost 
New Work 
Approp. 
Cost 
Maint. 
Approp- 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Approp. 
Cost 
1,269,000 700,000 2,400,000 Z,2 Co ' 45,,660,000 
3,137,515 2,424,393 2,539,547 iZ45 32,77,215 19 
3,656,000 3,368,662 3,976,000 4,564,788 76,231,247 
3,856,047 3,375,831 3,980,579 4,542,752 76,475,837 
45,009,710 
45,009,710 20 
4,708,000 5,192,886 4,827,000 3,520,856 61,787,166 
4,699,288 5,223,871 4,838,456 3,499,950 64,594,805 
51,014 
5,226,000 
1,613,738 
3,537,000 9,017,000 
1,204,480 1,742,111 4,814,330 
550,000 
545,596 
550,000 
545,596 
1,145,457 21 
1,145,457 
83,000 
82,515 
2,148,304 1,410,000 299,921 5,814,263 
2,145,927 1,412,782 299,950 5,815,153 
35,000 
34,803 
220,197 
220,195 
69,836 
69,836 
686,396 
686,197 
175,933 24 
175,933 
83,032 
82,624 
725,000 
724,927 
1,075,000 180,006 5,209,349 " 
1,075,402 180,006 5,209,343 
595,055 605,000 822,457 32,097,959 
599,054 601,729 814,078 32,569,330 
2-20

NEW YORK, N.Y. DISTRICT 
TABLE 2-A (continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to .2, 
in Text Projects Funding FY 89 FY 90 FY 91 FY 92 September 30, 1992 
26. Rockaway Inlet to 
Norton Point (Coney 
Island), N.Y. 
27. Sandy Hook to 
Barnegat Inlet, NJ. 
30. North Ellenville. 
N.Y. 
31. Passaic River, N.J. 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
1. Of which $12,500 is for North Atlantic Division Accounts. 
2. Of which $12,127 is for North Atlantic Division Accounts. 
3. Includes $1,040,000 for new work and $1,040,000 expended 
for the portion under construction general. 
4. Excludes $100,000 for new work expended from contributed 
funds and includes $82,600 for new work expended 
from public work fund. 
5. Includes $39,465 expended for previous project. 
6. Includes $5,112,694 for new work for previous project. 
7. Includes $238,350 for new work expended from public 
works funds and $311,461 emergency relief funds. Excludes 
$81.373 expended from contributed funds. 
8. Excludes $454,273 expended between August 18, 1915 and 
June 30, 1935, for operation and care of lock and dam at 
Troy, N.Y., under permanent indefinite appropriation. 
Excludes $23,735 reimbursement for repairs to Troy Lock. 
9. Includes $346,797 for maintenance for previous project. 
10.Includes $628,502 for new work and $210,365 for maintenance 
for previous projects 
11. Excludes $419,879 for new work expended from contributed 
funds and $58,425 contributed funds from other, and 
$8,752 expended by the Worlds Fair Corp. for riprap protection 
of rubble dike. 
12. Includes $115,000 for new work for previous projects. 
13.Includes $69,629 for new work for previous projects and 
$668,820 expended from public works funds. 
15. Includes $12,809,975 for new work for previous projects. 
685,000 
587,796 
531,000 
587,483 
825,000 750,000 3,291,000 
724,140 474,996 2,843,706 
1,200,000 1,613,000 1,354,000 2,000,000 13,202,000 
946,329 1,305,100 1,246,343 1,042,781 11,496,873 
350,000 176,000 270,000 4,766,450 
431,670 197,900 4,530,220 
750,000 3,900,000 5,800,000 7,145,000 36,681,700 
1,104,308 3,975,359 4,605,177 7,497,720 35,680,390 
16. Includes $7,712 for new work expended from contributed 
funds and includes $22,861 incurred in FY 1963 to be 
transferred to construction of Staten Island Rapid 
Transit Bridge during FY 1971. 
17.Includes $807,000 for new work expended from public 
works funds and $2,023,308 for new work expended from 
emergency relief funds. 
18. Includes $1,160,380 for maintenance for previous project, 
and $1,621 for maintenance of Lemon Creek, Staten Island, 
N.Y. 
19.Includes $2,491,206 expended to date for construction of 
a land-based overfire air pit incinerator ($1,493,393 in maintenance 
funds and $997,813 in 0 & M funds.) 
20.Includes $116,530 applied to removing wrecks authorized 
by acts prior to adoption of existing projects 
21.Includes $220,894 for new work for previous projects. 
22.Includes $286,600 for maintenance for previous projects. 
23.Includes $69,036 for new work and $26,921 for 
maintenance for previous projects. Excludes $10,000 for 
new work expended from contributed funds. 
24.Includes $77,182 for new work for previous projects. 
25. Includes $66,000 for maintenance for previous projects. 
27. Includes $1,246,100 for new work for previous projects and 
$64,560 extended from public work funds. 
28.Excludes $90,190 for new work expended from 
contributed funds. Additional NY State funds were $200,000 
in 1990 and $581,000 in 1991. 
2-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-B AUTHORIZING LEGISLATION 
Act Work Authorized Document 
River and Harbor 
Act of 1959 
Section 104 and Harbor 
Act of 1958 
Section 302 River and 
Harbor act of 1965 
March 3,1989 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and Progressive eradication of obnoxious 
Aquatic Plant growths 
Provided that all research and Planning cost to be borne fully by 
the United States 
Modified project to include control of waterchestnut 
BAY RIDGE AND RED HOOK CHANNELS, N.Y. 
(See Section 2 of Text) 
Channel 40 feet deep and 1,200 feet wide 
H.Doc. 37, 85th Cong., 
Ist sess. 
H. Doc. 337,54th Cong., 
2nd sess. (Annual Report 
1899, P. 1177.) 
March 2, 1907 
July 30, 1930 
May 17,1950 
July 3, 1930 
August 26, 1937 
May 17,1950 
1958 River & Harbor Act 
1962 River & Harbor Act 
Oct 23,1962 
June 13,1902 
Dredging to obtain first a depth of 35 feet, subsequently increasing 
depth of 40 feet for full width. 
Widening of Bay Ridge Channel to 1,780 feet. Rivers & Harbors Committee 
Doc. 44, 71st Cong., 1st sess. 
EAST CHESTER CREEK, N.Y. 
(See Section 3 of Text) 
Channel 10 feet deep and 150 to 70 feet wide. (Deauthorized in 1992) H. Doc. 749, 80th Cong., 
The 8-foot channel, authorized in 1930, completed in 1941, 2nd sess. 
remains as the existing project. 
EAST ROCKAWAY INLET, N.Y. (See Section 4 of Text) 
Channel 12 feet deep and 250 feet wide, and a jetty. H. Doc 19, 71st Cong., 1st sess. 
FIRE ISLAND TO JONES INLET, N.Y. (See Section 5 of Text) 
construction of jetty. Rivers & Harbors Committee 
Doc. 33, 75th Cong., 1st sess. 
Channel 10 feet deep. H. Doc. 762, 80th Cong., 
2nd sess. 
Three dredging operations with sand serving as nourishment to the H. Doc. 411, 84th Cong., 
beaches westerly of the inlet 2nd sess.. 
Extension of existing jetty, a littoral reservoir, a navigation chan- H. Doc. 115, 89th Cong., 
nel and dikes, sand deposit on westerly beaches 1st sess. 
FLUSHING BAY AND CREEK, N.Y. (See Section 6 of text) 
15 foot bay, creek and branch channels: 15-foot 
maneuvering area; 6-foot anchorage basin; revetment of dike H. Doc. 551, 87th Cong., 
extension; & abandonment of portion of creek channel & repair of dike 2nd sess.. 
GREAT SOUTH BAY, N.Y. (See Section 7 of text) 
Channel 10 feet deep and 200 feet wide from Fire Island 
Inlet to central basin in Great South Bay. 
Channel 8 feet deep and 100 feet wide from central basin 
to head of navigation in Patchogue River. 
H. Doc. 103, 56th Cong., 
2nd sess.. 
2-22

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Act Work Authorized Document 
June 25, 1910 
August 13, 1968 
W.R. D. A. of 1986 
June 25, 19 1 0 
March 3, 1925 
July 3. 1930 
July 1, 1935 
August 30, 1935 
June 20, 1938 
September 3, 1954 
P.L. 89-72 
March 4, 1913 
March 4, 1915 
August 8, 1917 
March 3, 1925 
January 21, 1927 
July 3, 1930 
August 30, 1935 
HEMPSTEAD HARBOR, N.Y. (See Section 8 of Text) 
Channel 6 deep, 50-80 feet wide 
Channel 13 feet deep, 150 feet wide, and turning basin 9 feet 
deep. (Deauthorized in 1990) 
Removal of derelict barges 
HUDSON RIVER, N.Y. (See Section 9 of Text) 
Channel 12 feet deep from Hudson to Waterford, remove State 
lock and dam at Troy and construct a new lock and dam. 
Channel 27 feet deep from Hudson to Albany, NY 
Channel 27 feet below Hudson. 
Operation and care of lock and dam at Troy were included in project. 
Relocation of 12 foot channel between Troy and Waterford. 
Deepen channel between Albany and Waterford to 14 feet with 
no change in depths for harbors in front of Albany & Troy. 
Deepen channel between New York City and Albany to 32 feet 
and construct a turning basin and 2 anchorages. 
Mooring facilities 
Note: The 12 and 27 foot classification have been deauthorized. 
HUDSON RIVER CHANNEL, N.Y. (See Section 10 of Text) 
Channel 30 feet deep from Ellis Island to Neward St., 40 feet deep 
through shoal from Newark St. to Castle Point and channel 26 by 
550 feet along Weehawken-Edgewater waterfront. Remove shoal 
east side of river between West 19th and West 32nd Sts.; remove 
rock near Battery to 40 feet; remove obstruction near Spuyten Duyvil 
Creek. 
Additional dredging through shoal from Newark St. to Castle Point. 
Remove shoal between West 32nd and West 61st Sts. to 40 feet and 
widen 40 foot channel between the Battery and Canal St. to 2.000 feet. 
Channel 30 by 750 fee.along Weehawken-Edgewater waterfront. 
Modification of conditions of local cooperation affecting channel 
along Weehawken-Edgewater waterfront. 
Channel 40 feet deep between pierhead lines from 20th St., Manhattan, 
to a point 1,300 feet below Newark St. Hoboken, thence 2,800 feet 
wide to deep water off Ellis Island. Channel 30 feet deep between 
40 foot channel and channel along Jersey City waterfront. 
Widen 40 foot channel to full width of river from north line of 
59th St. to south side of Little Basin, thence a channel of same 
depth to deep water off Ellis Island.
2-23 
Rivers & Harbors Conm. 
Doc. 1, 61st Cong., 2nd sess. 
H. Doc. 719, 61st Cong., 
2nd sess. 
H. Doc. 350, 68st Cong., 
1st sess. 
H. Doc. 210, 70th Cong., 
1st sess. 
S. Doc. 155, 72nd Cong., 
2nd sess. 
H. Doc. 572, 75th Cong., 
3rd sess. 
H. Doc. 228, 83rd Cong., 
1st sess. 
H. Doc. 719, 62nd Cong., 
2nd sess. 
Annual Report 1914, 
pp. 234-235 
H. Doc. 1697, 64th Cong., 
2nd sess. 
H. Doc. 313, 68th Cong., 
1st sess. 
H. Doc. 450, 70th Cong., 
2nd sess. 
H. Doc. 309, 72th Cong., 
1st sess.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Act Work Authorized Document 
August 30, 1935 
August 26, 1937 
June 25, 1910 
March 2, 1945 
May 17, 1950 
FY 1985 Supplemental 
Appropriations Act. 
(PL99-98) 
August 26, 1937 
August 8, 1917 
September 6, 1933 
August 30, 1965 
May 28, 1935 
May 17. 1950 
October 27, 1965 
March 14, 1915 
July 3, 1930 
December 31, 1970 
Waiver all conditions of local cooperation affecting channel along 
Weehawken-Edgewater waterfront. 
Channel 45 and 48 feet deep and 2,000 feet wide. 
JAMAICA BAY, N.Y. (See Section 11 of Text) 
Construction of I jetty. Interior channel along west shore of bay, 
18 and 12 feet deep; interior channel along south shore, 15 feet 
deep; entrance channel 20 and 18 feet deep; and I riprap jetty all 
in lieu of work heretofore authorized. Modified conditions of local 
cooperation. 
Channel 15 feet deep in Mott Basin including its 2 branches 
KILL VAN KULL-NEWARK BAY, NJ. & N.Y. 
(See Section 12 of Text) 
Deepening existing 35 foot channels in increments to 40 feet and 
then 44 feet. 
LONG ISLAND INTRACOASTAL WATER, N.Y. 
(See. Section 13 of Text) 
Channel 6 feet deep and 100 feet wide. 
NARROWS OF LAKE CHAMPLAIN, N.Y. AND VERMONT 
(See Sectio 14 of Text) 
Chanpel 12 feet aeep and 150 feet wide. 
NEW YORK AND JERSEY CHANNELS 
(See Section 15 of Text) 
Anchorage off Perth Amboy to 35 feet 
E 
Channels 35 feet deep from lower bay to upper bay, except between 
vicinity of Smith Creek and vicinity of Piles Creek to 30 feet with 
anchorage 38 feet deep at Sandy Hook and Perth Amboy. 
Channel 35 feet deep from vicinity of Smith Creek to vicinity of 
Piles Creek. 
Widen entrance to Kill Van Kull to 1,400 feet narrowing to a 
minimum width of 1,000 feet. 
NEW YORK HARBOR COLLECTION AND REMOVAL 
OF DRIFT (See Section 16 of Text) 
Allotment from appropriations made for New York Harbor and 
its immediate tributaries may be used for collection and removal 
of drift in these waterways. 
Carrying on this work as a separate and distinct project. 
Increase scope of project to include removal and disposal of 
derelict vessels, some deteriorated shore structures and debris 
along shores; and the repair of other shore structures; all 
subject to approval by Secretary of the Army and the President. 
2-24 
Rivers & Harbors Committee 
Doc. 49,72 Cong., 2nd sess. 
Senate Committee print, 
75th Cong., 1st sess. 
H Doc. 1488, 60th Cong., 
2nd sess. 
H. Doc. 700, 76th Cong., 
3rd sess. 
H.Doc. 665, 80th Cong., 
H. Doc. 181, 75th Cong., 
I st sess. 
H. Doc. 1387, 62nd Cong., 
3rd sess. 
Rivers & Harbors Committee 
)oc. 17, 71 st Cong., 2nd sess. 
H. Doc. 133, 74th Cong., 
I st sess. 
H. Doc. 233, 8 1 st Cong., 
Ist sess. 
H. Doc. 108, 98th Cong., 
I st sess. 
P.L. 91-611, 91 st Cong., 
H.R. 1987

NEW YORK, N.Y. DISTRICT 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Act Work Authorized Document 
March 7, 1974 
July 5, 1884 
March 3, 1899 
June 25, 1910 
August 8. 1917 
August 8. 1917 
July 14, 1960 
Mar..2, 1919 
Aug. 30, 1975 
Aug. 30. 1935 
May 17, 1950 
Mar. 3,1905 
Sept. 22, 1922 
Removal and disposal of derelict vessels, some deteriorated shore 
structures and debris along shores and the repair of other shore 
structures. 
NEW YORK HARBOR, ENTRANCE AND 
ANCHORAGE AREAS (See Section 17 of Text) 
Main-Ship-Bayside-Gedney to 30 feet leerfor width of 1,000 feet 
(Dimensions fixed by Secretary of War, December 27, 1886 by 
authority of Act of August 5, 1886). 
Ambrose Channel (East Channel) to 40 feet. 
Maintenance of entrance channel under I head. 
Anchorage Channel, extension of Ambrose Channel into Upper Bay. 
Removal of Craven Shoal 
SHINNECOCK INLET, N.Y. (See Section 18 of Text) 
Channel 10 feet deep and 200 feet wide in Inlet, and 6 feet deep 
and I 00 feet wide in the Bay, and 2 jetties. 
SHREWSBURY RIVER, N.J. (See Section 19 of Text) 
Channel 6 feet in North Branch 
Channel 12 feet deep. 
Channel 9-feet deep 
Turning basin and anchorage 6 feet at Red Bank and Channels 6 
feet deep in Claypit, Ocean port, and Little Silver Creeks. 
(Deauthorized in 1990) 
TARRYTOWN HARBOR, N.Y. (See Section 20 of Text) 
Channel 12 feet deep, 100 feet wide in approach arms, 
and 150 feet wide along waterfront. 
Widening channel to 150 feet in approach arms 
and 250 feet along waterfront. 
WESTCHESTER CREEK, N.Y. (See Section 21 of Text) 
Channel 12 feet deep and two turning basins. 
P.L. 93-251, 93rd Cong. 
Annual Reports 1887 p. 62 
and 1888, p. 63 
H. Doc- 159, 55th Cong., 
2nd sess. 
H. Doc- 518, 63rd Cong., 
2nd sess. 
H. Doc. 557, 64th Cong., 
I st sess. 
H. Doc. 126, 86th Cong., 
I st sess. 
FY 83 Supplemental 
Appropriations Act 
H. Doc. 1296, 62nd Cong., 
3d sess. 
H. Doc. 157, 71st Cong., 
2d sess. 
Rivers and Harbors Committee. 
Doc.' 31, 74th Cong., 
H. Doc. 285, 81 st Cong., 
1st sess. 
H. Doc. 283, 56th Cong., 
1st sess. 
H.Doc. 262 72nd Cong., 
1 st sess 
Rivers and Harbors Committee 
Doc. 8, 67th Cong., 
2d sess. 
1986 Water Resources 
Development Act 
Section 501 
ROCKAWAY INLET TO NORTON POINT (CONEY ISLAND) N.Y. 
(See Section 26 of Text) 
Provide beach fill to public beach to furnish storm damage 
protection to the area. 
Extension of terminal groins at W. 37 St. and Brighton Beach 
Fillet of beach fill at Sea Gate. 
2-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-B (continued) AUTHORIZING LEGISLATION 
Act Work Authorized Document 
July 3. 1958 
1988 Water Resources 
Development Act 
1962 Flood Control Act 
1990 Water Resources 
Development Act 
1976 and 1990 Water 
Resources Development 
Acts 
SANDY HOOK TO BARNEGAT INLET, NJ. 
(See Section 27 of Text) 
Restoration of beach to minimum width of 100 feet at height of 
10 feet above mlw, and construction of 23 new groins and 
extension of 14 existing groins. 
NORTH ELLENVILLE, N.Y. (See Section 30 of Text) 
Levees and floodwalls, removing concrete dam, stream diversion, 
interior drainage structures. Subsequent damage repairs. 
PASSAIC RIVER BASIN, N.J. 
(See Section. 31 of Text) 
Advanced engineering and design study, involving reformulation 
of plans for flood control and water resource management. 
H. Doc. .332, 85th Cong., 
2nd sess. modified by Appr. 
Act for Energy & Water Dev. 
for FY 85 
S. Doc. 113, 87th Cong., 
2d sess. 
PL-84-99 
H. Rpt. 94-1702 
2-26

NEW YORK, N.Y. DISTRICT 
TABLE 2-C HUDSON RIVER, N.Y. 
FEATURES OF LOCK AND DAM INCLUDED IN EXISTING PROJECT 
LSection 9 of Text) 
Location: 
Below Waterford 
Above Battery, New York City 
Locks: 
Clear Width 
Greatest length available for full width 
Lift at lowest stages 
Depth on miter sills: 
Upper (at normal pool level) 
Lower (at lowest low water) 
Character of foundation: Rock 
Kind of dam: Fixed Crest 
Type of construction: Concrete 
Complete: 1917 
Cost $1,463,014 
TABLE 2-E 
2.2 miles 
152.6 miles 
44.4 feet 
492.5 feet 
17.3 feet 
16.3 
13.0 feet 
SUPERVISOR OF NEW YORK HARBOR 
(Section 22 of Text) Statement of Activities-FY 1992 
1. Number of Patrols 
a. Shore 
b. Vessel 
c. Air (helicopter) 
2. Number of Inspections 
a. Shore Facilities 
b. Vessels 
3. Disposition of Cases 
a. Voluntary Restoration 
b. After-the-fact Permit Applications Accepted 
c. Permit not required or already under permit 
d. Submitted for litigation to OCE or US Attorney 
e. Other misc. 
f. Cases pending as of October 1, 1992 
242 
218 
463 
229 
459 
21 
18 
89
2 
38 
20 
359 
2-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-F RECONNAISSANCE AND CONDITION SURVEYS FY 1992 
NAME OF PROJECT DATE SURVEY CONDUCTED 
NEW JERSEY 
Cheesequake Creek ......................................................................................................................................... Feb 91 
Keyport Harbor............................................................................................................................................. Jun 91 
Hackensack River..........................................................................................................................................Sep 92 
M atawan Creek.............................................................................................................................................. Jun 91 
N ew ark Bay..................................................................................................................................................... Jul92 
Passaic River..................................................................................................................................................Jun 92 
Raritan Riven.................................................................................................................................................. Jan 91 
Raritan River Cut-off...................................................................................................................................... Jan 91 
Sandy Hook Bay at A tlantic H ighlands............................................................................................Feb & M ar-91 
Sandy Hook Bay at Leonardo.......................................................................................................................M ar 91 
Shrewsbury River...........................................................................................................................................Jun 91 
NEW YORK 
Bay Ridge & Red Hook Channels................................................................................................................. Sep 92 
Brow ns Creek................................................................................................................................................. Sep 92 
Coney Island Channel....................................................................................................................................Jun 91 
Coney Island Creek........................................................................................................................................Feb 91 
Eastchester Creek.......................................................................................................................................... M ar 92 
East Rockaw ay Inlet ..................................................................................................................................... N ov 91 
East River...................................................................................................................................................... A ug 92 
Fire Island Inlet.............................................................................................................................................N ov 90 
Flushing Bay & Creek....................................................................................................................................Jun 91 
Great South Bay................................................................................................................................ M ar & Apr 91 
Greenport Harbor.......................................................................................................................................... M ar 91 
Hem pstead H arbor........................................................................................................................................ M ay 91 
H udson River Channel................................................................................................................................... Apr 92 
Jamaica Bay ...................................................................................................................................................... Jul 92 
Jones Inlet ....................................................................................................................................................... Apr 92 
Lake M ontauk H arbor .................................................................................................................................... N ov 91 
Long Island Intra: W 'W ay ....................................................................................................... Feb, M ar & Apr 91, 
Mamaroneck Harbor....................................................................................................................................... Aug 92 
M ilton,H arbor................................................................................................................................................ Oct 91 
N ew tow n Creek..............................................................................................................................................Oct 91 
New York Harbor 
a. Am brose Channel ................................................................................................................................. Jun 91 
b. Liberty Island Anchorage ................................................................................................................... Feb 91 
c. M ain Ship Channel .............................................................................................................................. Jun 91 
d. NJ Pierhead Channel ............................................................................................................ Feb & Oct 91 
e. Red Hook Flats A nchorage ................................................................................................................ Feb 92 
f. Sandy Hook Channel ....................................................................................................................... Jun 92 
New York & New Jersey Channels 
a. Arthur K ill ................................................................................................................................ Jan & Feb 91 
b. K ill V an K ull .................................................................................... ............................................. Jun 91 
c. Perth Am boy Anchorage .................................................................................................................. Jan 91 
Peconic R iver .......... ...... ... ............................................................. ............................................. Jun 91 
Port Chester H arbor .................................................................................... ............................................... N ov 91 
Sheepshead Bay...... ................................................................................................................... O ct 90 & Jun 91 
2-28

NEW YORK, N.Y. DISTRICT 
TABLE 2-F (Cont.) RECONNAISSANCE AND CONDITION SURVEYS FY 1992 
NAME OF PROJECT (Continued) DATE SURVEY CONDUCTED 
NEW YORK 
Shinnecock Inlet..............................................................................................................................................Jul 92 
Sw ash C hannel.............................................................................................................................................. Feb 92 
Tarrytow n H arbor...........................................................................................................................................Jun 91 
W estchester C reek........................................................................................................................................... Jun 91 
Total cost of Reconnaissance and Condition Surveys in Fiscal Year 1992 was $1,479,606. 
TABLE 2-G OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sept 30, 1992 
For Last 
Full Report 
See Annual Operation & 
Projects Report For Construction Maintenance 
Buttermilk Channel, NY 
Bronx River, NY 
Browns Creek, NY 
Burlington Harbor, VT 
Channel between North & South Hero Islands, VT. 
Cheesequake Creek, NJ 
Coney Island Channel, NY 
Coney Island Creek, NY 
East River, NY 
Echo Bay Harbor, NY 
Fire Island Inlet, NY 
Glen Cove Creek, NY 
Gordon's Landing, VT 
Gowanus Creek Channel, NY 
Great Chazy River, NY 
Great Kills Harbor, NY 
Great Lakes to Hudson River W/W, N.Y. 
Greenport Harbor 
Harlem River, NY 
Huntington Harbor, NY 
Jones Inlet, NY 
Keyport Harbor, NJ 
Lake Montauk Harbor, NY 
Larchmont Harbor, NY 
Little Neck Bay, NY 
Mamaroreck Harbor, NY 
Mattituck Harbor, NY 
Matawan Creek, NJ 
1990 
1991 
1987 
1966 
1909 
1953 
1973 
1952 
1991 
1953 
1973 
1986 
1982 
1972 
1980 
1962 
1976 
1953 
1969 
1953 
1990 
1990 
1991 
1970 
1969 
1990 
1990 
1984 
$45590,201 $5,041,920 
1,149,946 12 3,802,517 
33,5976 673,369 
706,414 9 303,555. 
31,000 1,288 
40,000 210,675 
111,371 423,148 
69,489 6,203 
32,723,662 13 5,935,215 
64,584 21,571 
594,355 2,908,786 
29,760 130,760 
34,1750 115 
346,831 394,004 
18,000 292,919 
137,301 88,029 
- 457 
74,681 21,720 
3,616,119 493,491 
91,08117 57,527 
1,822,530 14,455,619 
40,475 1,417,437 
791,680 14 1,288163 
76,065 267,768 
1,741,210 19 537 
513,764 1,351,086 
177,925 1,417,832 
21,000 315,613 
2-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-G (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sept 30, 1992 
For Last 
Full Report 
See Annual Operation & 
Projects Report For Construction Maintenance 
Milton Harbor, N.Y. 
Moriches Inlet, N.Y. 
Newark Bay, Hackensack & Passaic Rivers, N.J. 
Newtown Creek, N.Y. 
New Rochelle Harbor, N.Y. 
Northport Harbor, N.Y. 
Peconic River, N.Y. 
Peekskill Harbor, N.Y. 
Plattsburgh Harbor N.Y. 
Port Chester Harbor, N.Y. 
Port Henry Harbor, N.Y. 
Port Jefferson Harbor, N.Y. 
Raritan River, N.J. 
Raritan River to Arthur Kill Cut-Off Channel, N.J. 
Rondout Harbor 
Rouses Point, Lake Champlain, N.Y. 
Sag Harbor, N.Y. 
Sandy Hook Bay, N.J. 
Sandy Hook Bay @ Leonardo, N.J. 
St. Albans Harbor, Lake Champlain, N.Y. 
Saugerties Harbor, N.Y. 
Shark River, N.J. 
Sheepshead Bay. N.Y. 
Shoal Harbor & Compton Creek, N.J. 
Staten Island. Rapid Transit Railway Bridge, Arthur Kill, N.Y. 
Sumpawanus (Babylon Creek) Inlet, N.Y. 
Wallabout Channel, N.Y.. 
Wappinger Creek, N.Y. 
Washington Canal and South River, NJ 
Woodbridge Creek, N.J. 
1. Excludes $104,800 for new work expended from contributed 
funds 
2. Includes $1,836,400 for new work for previous projects. 
Excludes $285,600 expended from contributed Funds. 
3. Includes $496,250 for new work for previous projects and 
$122,051 from public works fund. 
4. Excludes S1,822,530 for new work expended from 
contributed funds. 
5. Excluded $34,580 from contributed funds. 
6. Includes $16,369 for maintenance for pervious projects. 
7. Includes $17,000 for new work for previous projects 
1984 
1990 
1989 
1986 
1971 
1956 
1953 
1951 
1986 
1990 
1931 
1977 
1991 
1991 
1989 
1895 
1964 
1985 
1991 
1917 
1988 
1987 
1948 
1990 
1973 
1895 
1953 
1950 
1953 
1953 
151,373 1 1,057,266 
7,725,843 101,840 
29,014,500 2 25,255,368 
1,168,354 11760,745 
73,214 * 212,411 
78,644 23 615487 
25,000 116,500 
19,400 66,037 
198,415 6 256,415 
433,470 1,742,097 
69,406 2 1,299 
221,128 359,294 
1,551,470 16, 114,463 
810,500 3,965,631 
142,437 3,185,437 
98,468 249 
121,805 26 11,710 
508,936 4,002,330 
56,479 679,916 
3,125 385 
81,905 2 429,180 
150,000 1,254,813 
33,828 64,078 
124,572 1,822,938 
7,730,476 
7,000 
18,174 36,312 
13,000 44,691 
206,116 30 212,827 
48,823 178,398 
8. Includes $43,175 for new work for previous projects. 
9. Includes cost of maintenance prior to July 1, 1886. Excludes 
$1,425,133 for rehabilitation. 
10. Includes $169,700 for maintenance for previous projects. 
11. Includes $115,000 for new work for previous projects. 
12. Includes $69,036 for new work and $26,921 for mainte 
nance forprevious projects. Excludes $10,000 for new 
work expended from contributed funds. 
13. Includes $6,187,690 for new work and $37,664 formain 
tenance for previous projects. 
14. Excludes $104,805 for new work expended from contrib 
uted funds. 
2-30

NEW YORK, N.Y. DISTRICT 
15. Includes $111,419 for maintenance for previous projects 
and $64,5\60 expended from public works funds. 
16. Includes $1,490,713 for maintenance for previou 
projects. 
17. Excludes $19,546 for new work expended from contrib 
uted funds and $31,454 to be contributed. 
18. Excludes $119,276 required contributed funds and 
$72,619 other contributed funds. 
19. Excluded $1,741,210 for new work expended from 
contributed funds 
TABLE 2-H 
23. Excludes $15,000 for new york expended from con 
tributed funds 
25. Excludes $1,000 for new work expended from contrib 
uted funds. 
26. Excludes $66,758 for rehabilitation. 
28. Includes $15,000 for maintenance for previous projects. 
30. Includes $84,934 for maintenance for previous projects. 
31. Includes cost for new work $171,427 and maintenance 
$10,646 for previous projects. 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS
Cost to Sept 30, 1992 
For Last 
Full Report 
See Annual Operation & 
Projects Report For Construction Maintenance 
Atlantic.Coast of N.J., Sandy Hook to Barnegat Inlet 1 1959 
East Rockaway Inlet to Rockaway Inlet and 
Jamaica Bay. N.Y. (Part 1) 1989 $25,238,400 
Fire Island Inlet to Jones Inlet, N.Y. 2 1981 18,044,667 217,899 
1. Reactivated as a modified project in 1985 (Sec 27) 
2. Listed since 1982 as a navigation and beach nourishment project (Sec 5). 
2-31 
TABLE 2-G (Continued) OTHER AUTHORIZED NAVIGATION PROJECTS

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 2-1 
Cost to Sept 30, 1992 
For Last 
Full Report 
See Annual Operation & 
Projects Report For Construction Maintenance 
Adams, Hossic River Basin, Mass.1 1964 6,282,307 2 - 
Ardsley, N.Y. 1990 5,522,846- 
Byram River at Pemberwick, Conn.' .3 1959 363,515- 
East Barre Dam, Winooski River, Vt.' 1963 2,898,334- 
Elizabeth, NJ. 1985 54,374,070- 
Fire Island to Montauk Point. N.Y. 1984 12,741,660 6 143,753 
Herkimer, N.Y. 1973 1,249,530 ' - 
Hoosic Falls, Hoosic River Basin. N.Y.' 1956 1,064,626- 
Lamoille River, Vt.: Hardwich Dams .6 1939 - - 
Liberty State Park Levee and Seawall, N.J. 1990 17,888,670- 
Missisquoi River at Richford, Vt.1-3 1965 238,169- 
North Adams, Hoosic River Basin, Mass. 1968 15,572,988 7 
Rahway. N.J.: 1971 973,142 8 
Rahwav. South Branch, NJ. 1979 15,863,723- 
Raritan Bay and Sandy Hook, N.J. 1981 11,061,256 262 
Rosendale, N.Y. 1975 3,684,966- 
Sandburg, Creek. Spring Glen, N.Y. 1976 109,702 
Sawmill R. Elmsford & Greenburgh. N.Y. 1987 59,142 
South Amsterdam, Mohawk River. N.Y.' 1967 1,564,976- 
South Ellenville. N.Y. 1984 289,702- 
South Orange, NJ. 1981 6,857,484- 
Staten Island. N.Y. 1983 644,998- 
Wappinger Creek at Pleasant Valley, N.Y. 1'-3 1959 142,075 
Waterbury Reservoir Winooski River Basin, Vt. 1976 1,438,845 8,200 
Winooski River. Vt. 1940 5,897,427- 
Wrightsville Dam, Winooski River Basin, Vt. 1970 1,549,929 
Yonkers, N.Y. 1984 113,729,270 10to 
TABLE 2-1 (continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
1. Completed. 
2. Excludes costs of $913,360 under other contributed funds. 
3. Authorized by Chief of Engineers pursuant to Sec. 205, 
Public Law 858, 80th Cong. as amended. 
4. Inactive. 
5. Includes $213.507 emergency relief funds. 
6. Includes 3,788,341 contributed funds. 
7. Excludes cost of $21,000 under other contributed funds. 
8. Excludes cost of $51,500 under other contributed funds. 
9. Uncompleted portion has been deauthorized on August 5, 
1977. 
10. Includes $622,8171 contributed funds. 
2-32

NEW YORK, N.Y. DISTRICT 
TABLE 2-J SURVEYS 
Study Class FY 92 Cost 
Navigation Studies 
Flood Control Studies 
Beach Erosion 
Special Studies 
TOTAL 
$533,510 
2,428,610 
455,890 
591,850 
4,009,860 
1. Includes Dam Inventory and safety criteria studies, National Estuary Studies, Ferc licensing activities, Coordination studies. 
Community Ass't Progr. FEMA, and Sec 933 and 934 studies. 
TABLE 2-L COSTS FOR FLOOD PLAIN MANAGEMENT SERVICES 
Study Class FY 92 Cost 
Flood Plain Technical Services $68,621 
Flood Plain Management Unit 23,660 
TOTAL 92,281 
2-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-M DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed Operation 
See Annual And Funds Funds and 
Projects Report For Authority Expended Construction Expended Maintenance 
1974 
1981 
1980 
1953 
1952 
1992 
1963 
1976 
Bennington. VT (1936 & 41 Acts) 
Bronx River, N.Y. 
Brown's Creek, N.Y. 
Cheesequake Creek, NJ. , 
Coney Island Creek, N.Y. '46 
East Chester Creek, N.Y. (1950 Act) 
East Rockaway (Debs) Inlet, N.Y., 
East Rockaway Inlet to Rockaway Inlet 
and Jamaica Bay, N.Y. (Part 11) 
Elizabeth, N.J. 
Glen Cove Harbor, N.Y. 
Hempstead Harbor, NY (68-Act) '14 
Hudson River, NYC to Albany (12 Ft, 27 Ft)18 
Huntington Harbor, N.Y. 
Irvington Harbor, N.Y. 
Lamoille River, Vt. 
Lemon Creek, NY 
Manhasset Bay, NY 
Matawan Creek, NJ (1881 Act) 
N. Shore of Long Island, Suffolk County, 
NY 
Newark Bay, Hackensack and Passaic 1982 
River, N.J. 16 
N.Y. & N.J. Channels 4.18 1982 
Orowoc Creek, NY. 1949 
Otter Creek, Vt. 1937 
Perth Amboy, NJ. 1966 
Port Chester Harbor, N.Y. 2.3 1967 
Port Jefferson Hbr. N.Y. (1890,1930 & 68 Acts) 1977 
Rahway River, N.J. 6.7 1948 
Raritan River, NJ.4 6 1981 
Rome Mohawk River, N.Y. 6,7. 1959 
Rutland, Otter Creek, VT 1963 
Sag Harbor, N.Y. (Channel) 1 1964 
Shooters Island, NJ. & N.Y. 9- 
Shrewsbury River, N.J. (1950 & 1965 Act) 1992 
Swanton Harbor, VT6 1888 
Ticonderoga River, N.Y. 16 1895 
Waterbury, VT (1941 Act) 7.8 1951 
Waterford. N.Y. 6.7 1939 
Waycake Creek, NJ 1949 
Westchester Creek, N.Y. 4 1981 
Aug. 1982 
Aug. 1977 
Aug. 1982 
Aug.1982 
Jul 1992 
Aug. 1977 
1988 
1948 Aug.1977 
1966 Aug. 1977 
1989 Jan 1990 
1982 Aug. 1987 
1953 Aug. 1977 
1947 Aug. 1977 
1939 Aug. 1977 
1937 1988 
1948 1988 
1984 1988 
1979 Jan 1990 
Aug. 1982 
Aug. 1982 
1988 
Jan 1990 
Jan 1990 
Aug. 1977 
Jan. 1990 
Aug. 1982 
Aug. 1982 
Aug. 1982 
1988 
Oct. 1992 
Jul 1992 
Jan 1990 
Aug. 1977 
Nov. 1983 
Nov. 1981 
Aug. 1982 
1988 
Aug. 1982 
1,149,946 
33,976 
40,000 
69,489 
3,503,969 13 
60,481 
165,882 
49,035 
49,837 
433,470 
1,551,470 
7,000 
167,760 
9,253 
175,933 
670,000 
1,159,946 
33,976 8 
40,000 
69,489 
100,000 
1,185,365 
60,481 
165,882 4-11 
39,468 
68,581 
49,837 
6,621 
21,000
-- 
433,470 " 
37,000 ' 
1,617,470 15 
7,000 
211,015 
70,500 4 
16,500 
9,253 
2,781 
175,933 
12 10,000 
829,421 
19,546 
1,947,853 
505,369 
30,675 
1,622
-- 
59,391 
2,455 
76,497 
51,566 
1,621 
4,636 
257,237 
4,951 
- 441,656 
307 
66,000 10,113,903 
235 
1.260 
2,921,311 
2-34

NEW YORK, N.Y. DISTRICT 
TABLE 2-M (Continued) DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed Operation 
See Annual And Funds Funds and 
Projects Report For Authority Expended Construction Expended Maintenance 
1. No Commerce reported. 10. Deepening 8 foot project to 10 feet. 
2. Completed. 11. Includes $93,882 for Rehabilitation. 
3. A portion of this project is classified "inactive." 12. Includes $10,000 expended from contributed funds. 
4. Uncomplete portion deauthorized. 13. Includes $100,000 expended from contributed funds. 
5. Excludes $19,546 for new work expended from contrib- 14. Depening project to 13 feet. 
uted and $31,454 to be contributed. 15. Includes $66,000 expended from contributed funds. 
6. Inactive. 
16. 1912 authorization. 
7. Entire project deauthorized. 
17. 1935 authorization. 
8. Excludes $71,423 for rehabilitation. 
18. 1910 construction dikes. 
9. Removal for navigation. 
TABLE 2-N SECTION 107 
(Sec. 26 of Text) 
Project FY 92 Cost 
CONTINUE FEASIBILITY STUDY 
Belford, N.J. $48,960 
TABLE 2-P SECTION 205 
Project FY 92 Cost 
COMPLETE RECONNAISSANCE REPORT 
Mill Brook,-Highland Park, NJ. 
CONTINUE INITIATIVE PLANS AND SPECIFICATIONS 
Elizabeth River, Hillside, N.J. 
CONTINUE COORDINATION FOR CONSTRUCTION 
Ramapo River, Monroe, N.J. 
Yonkers, Nepera Park, N.Y. 
$52,930 
252,110 
17,670 
2-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 2-Q SECTION 14 
(Sec 35 of Text 
Project FY 92 Cost 
CONTINUE PLANS AND SPECIFICATIONS 
Green Brook (Regional Center), NJ. 
2-36 
523

PHILADELPHIA, PA DISTRICT * 
This district comprises a portion of southeastern New 
York, eastern Pennsylvania, western and southern New 
Jersey, northern and southeastern Delaware, and a small 
Part of northeastern Maryland embraced in the drainage 
basins tributary to the Atlantic Ocean from Manasquan 
River, NJ inclusive, to south boundary of Delaware. It 
also includes Chesapeake and Delaware Canal and 
approach channel thereto in Chesapeake Bay and Elk 
River, MD. 
IMPROVEMENTS 
Navigation Page 21. Flood Control Work Under Special 
Authorization.........................................................3-12 
1. Barnegat Inlet, NJ .................................................... 3-2 
2. Cedar Creek, NJ.......................................................3-2 
3. Chesapeake and Delaware Canal 
St. Georges Bridge Replacement, DE ...................... 3-2 
4. Cold Spring Inlet, NJ...............................................3-3 
5. Delaware River between 
Philadelphia, PA and Trenton, NJ............................3-3 
6. Delaware River, PA, NJ, and DE 
Philadelphia to the Sea ............................................ 3-4 
7. Delaware River Vicinity of Camden, NJ..................3-5 
8. Indian River Inlet and Bay, DE...............................3-5 
9. Inland Waterway from Delaware 
River to Chesapeake Bay DE, MD...........................3-5 
10. Inland Waterway Rehoboth 
to Delaware Bay, DE...............................................3-6 
11. Mispillion River,DE ................................................ 3-7 
12. Murderkill River, DE ............................................... 3-7 
13. New Jersey Intracoastal Waterway .......................... 3-8 
14. Salem River, NJ.......................................................3-8 
15. Schuylkill River, PA................................................3-9 
16. Wilmington Harbor, DE ........................................ 3-10 
Beach Erosion Control Page 
17. Cape May Inlet 
to Lower Twp., NJ..................................................3-10 
Flood Control Local Protection Page 
18. Beltzville Lake, PA.................................................3-11 
19. Blue Marsh Lake, PA ............................................ 3-11 
20. Delaware Coast Protection, DE.............................3-12 
22. Emergency Bank Protection .................................. 3-12 
23. Francis E. Walter Dam, PA ................................... 3-12 
24. General Edgar Jadwin Dam and 
Reservoir, PA ......................................................... 3-13 
25. Great Egg Harbor Inlet 
and Peck Beach, NJ.................................................3-13 
26. Inspection of Completed Flood 
Control Projects......................................................3-14 
27. Inspection of Non-Federal Levees.........................3-14 
28. Prompton Lake, PA................................................3-14 
29. Reconnaissance and Conditions 
Surveys ................................................................... 3-14 
30. National Emergency Preparedness ........................ 3-14 
General Investigations 
31. 
32. 
33. 
Surveys .................................................................... 3-14 
Collection and Study of Basic Data.......................3-15 
Preconstruction, Engineering and Design ............. 3-15 
Tables 
TABLE 3-A Cost and Financial Statement ................ 3-16 
TABLE 3-B Authorizing Legislation ......................... 3-20 
TABLE 3-C Other Authorized 
Navigation Projects................................3-25 
TABLE 3-D Other Authorized Beach 
Erosion Control Projects........................3-27 
TABLE 3-E Other Authorized Flood 
Control Projects ..................................... 3-27 
TABLE 3-F Deauthorized Projects.............................3-28 
* All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at 
the end of this chapter. 
3-1 
Page 
Page

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
L BARNEGAT INLET, NJ 
Location: On the east coast of New Jersey about 50 
miles south of Sandy Hook, between Island Beach on the 
north and Long Beach on the south (See U.S.Coast and 
Geodetic Chart Nos. 825 and 1216). This inlet is main 
the entrance to Barnegat Bay, largest of the bays on New 
Jersey coast which are separated from the ocean by 
narrow barrier beaches. 
Previous Project: None 
Existing project: The existing project, adopted as 
HD 73-19 in 1935 and modified as HD) 74-85 in 1937 and 
HD 79-358 in 1946, provides for a channel eight feet 
deep through the inlet and ten feet deep through the 
outer bar, protected by two converging stone jetties and 
a channel of suitable hydraulic characteristics extending 
in a northwesterly direction from the gorge in the 
inlet to Oyster Creek channel and through the latter 
channel to deep water in the bay. The project was 
modified in 1946 to provide for the maintenance of a 
channel eight feet deep and 200 feet wide to connect 
Barnegat Light Harbor with the main inlet channel. The 
project length is about 4.5 miles. (For details see page 
203, Annual Report 1964.) 
The Supplemental Appropriation Act of 1985 contained 
language stating that the existing project has not 
worked as projected and, in fact, has created a hazard to 
navigation. As a result, the following administratively 
approved modifications are to be constructed as design 
deficiency correction measures: a new south jetty 4,270 
feet in length along an alignment generally parallel to 
the existing north jetty, extending from the existing 
groin located near the Barnegat Lighthouse to the tip of 
the existing south jetty; a navigation channel 300 feet 
wide to a depth of 10 feet below mean low water from the 
outer bar in the Atlantic Ocean to the north end of the 
existing sand dike in Barnegat Bay; remove the shoal 
located between the north jetty and the proposed navigation 
channel; jetty sport fishing facilities on the new 
jetty. All dredged material from initial construction 
would be placed on the shores of Barnegat Light between 
the existing and new south jetties, and would be stabilized 
by vegetation and sand fence. Dredged material 
from maintenance operations would be placed on the 
down draft beaches, the area between the existing and 
new south jetties, or in other locations as determined by 
a shoreline monitoring program. Estimated cost for new 
work (October 1990) Federal share is $31,200,000 and 
non-Federal is $14,230,000. (See Table 3-A at end of 
chapter for total cost for existing project to Sept. 
30,1992.) 
Local cooperation: Fully complied with. A local 
cooperation agreement for the approved modification 
was executed on 19 May 1986 and a modification to the 
local cooperation agreement was executed on 20 March 
1987. 
Terminal facilities: There are four docks or terminals 
in inner harbor at Barnegat Light which furnish 
adequate facilities for present commerce of locality. 
Operation during fiscal year: New Work, contract: 
Work included construction of South Jetty and sport 
fishing pier,maintenance dredging was accomplished by 
American Dredging Company from October 23, 1991 to 
July 19, 1992 removing a total of 183,057 cubic yards of 
material at a cost of $1,495,338 and inlet monitoring. 
New Work, hired labor: Work included dredging, engineering 
and design and supervision and 
administration for South Jetty and sport fishing pier. 
Maintenance, hired labor: Work included general 
maintenance, repair of North Jetty, surveys, engineering 
and design, and supervision and administration. 
Dredging by the U.S. Government Dredge Currituck 
was accomplished from November 14, 1991 to December 
12, 1992, from April 18, 1992 to May 9, 1992, from June 
29, 1992 to July 19,1992, and from August 12, 1992 to 
September 13, 1992 removing 148,880 cubic yards at a 
total of $ 752,468. 
2. CEDAR CREEK, NJ 
Location: In the northeastern corner of Sussex County 
DE, approximately five miles east of the Town of 
Milford. The area is accessible via State Route 36. 
Existing project: Cedar Creek, with headwaters in 
Sussex County, meanders northward through coastal 
salt marsh to its terminus at Mispillion River. The 
creek currently ranges in depth from 13 feet below mean 
low water at the Route 36 bridge to less than 5 feet at 
several locations. The channel width varies from approximately 
75 feet to 250 feet. Tidal range in the lower 
reaches of the creek is approximately 4 feet. Existing 
project was adopted by the Chief of Engineers, 10 
December 1979 under the small navigation program, 
section 107, River and Harbor Act of 1960. 
Local cooperation: Fully complied with. 
Terminal facilities: Five marinas are located along 
the lower stretch of the creek, with residential areas 
being situated near the Delaware Bay shore. The area is 
sparsely populated, and there are no major metropolitan 
areas nearby. 
Operations during fiscal year: Maintenance, hired 
labor: Work included surveys, BCR updates, and supervision 
and administration. 
3. CHESAPEAKE AND DELAWARE 
CANAL, ST. GEORGES BRIDGE 
REPLACEMENT, DE 
Location: The new St. Georges Bridge will carry the 
new Delaware State Route 1 over the Chesapeake and 
Delaware Canal in New Castle County, Delaware and 
will be located approximately 2,200 feet west of the 
existing St. Georges Bridge. 
3-2

PHILADELPHIA, PA DISTRICT* 
Previous project: None 
New project:This project was authorized by the 
Water Resources Development Act of 1990. It states 
that the project for navigation, Inland Waterway from 
the Delaware River to the Chesapeake Bay, Delaware 
and Maryland, authorized by the first section of the Act 
of August 30, 1935 (45 Stat. (030) and modified by the 
Act entailed an Act authorizing construction of a highway 
bridge across the Chesapeake and Delaware Canal 
at Saint Georges, Delaware" approved August 7, 1939 
(53 Stat. 1240-1241) is modified to direct the Secretary 
to replace the highway bridge on United States Route 
13 in the vicinity of St. Georges, Delaware, to meet 
current and projected traffic needs, at a Federal cost of 
$115,000,000. 
Local cooperation: The state will carry out the 
bridge replacement and the Secretary will reimburse the 
State for cost incurred. 
Terminal facilities: None 
Operations during fiscal year: Maintenance, contract: 
Work included reimbursement to state of 
Delaware for construction of St. Georges Bridge Replacement. 
4. COLD SPRING INLET, NJ 
Location: In Cape May County, southern New Jersey, 
about 3 miles east of Cape May City and about 16 
miles northeast of Delaware breakwater. Inlet connects 
Cape May Harbor and New Jersey Intracoastal Waterway 
with the Atlantic Ocean and is about 1 mile long. 
(See Coast and Geodetic Survey Charts 234, 827 and 
1219). 
Existing project: An entrance channel 25 feet deep 
and 400 feet wide, protected by two parallel jetties, and 
extending from the 25-foot depth curve in the Atlantic 
Ocean to a line 500 feet harborward of a line joining the 
inner ends of the jetties, thence 20 feet deep and 300 feet 
wide to deep water in Cape May Harbor. The total length 
of the section included in the project is about 2.25 miles. 
Extreme tidal range, due to ocean storms, is about 11 
feet. Project was completed in 1942.(For details see 
page 238, Annual Report for 1962. See table at end of 
chapter for Acts authorizing existing project. See Table 
3-A at end of chapter for total cost for existing project to 
Sept. 30,1992.) 
Local cooperation: Complied with Act of 1907, except 
work of deepening and enlarging inner harbor 
which is 80 percent complete. 
Terminal facilities: See page 238 Annual Report for 
1962. 
Operations during fiscal year: Maintenance, hired 
labor: Work included repair of jetty, surveys, supervision 
and administration, and engineering and design. 
Dredging by the U.S. Government Side Casting Dredge 
Schweizer was accomplished from April 20, 1992 to April 
30, 1992 and from September 14, 1992 to September 28, 
1992 removing a total of 111,692 cubic yards of material 
at a total cost of $169,600. 
5. DELAWARE RIVER BETWEEN 
PHILADELPHIA, PA AND 
TRENTON, NJ 
Location: Rises in southeastern New York, flows 
generally southerly 367 miles, forming boundary line 
between New York and New Jersey on the east and 
Pennsylvania and Delaware on the west, and empties 
into Delaware Bay.(See U.S.Coast and Geodetic Survey 
Charts 1218, 280, 294, 295, and 296.) 
Previous project: For details see page 1778 of annual 
report for 1915, page 311 of Annual Report for 1924, 
page 220 of Annual Report for 1934, and page 296, 
Annual Report for 1938. 
Existing project: A channel from Allegheny Avenue, 
Philadelphia, 23.5 miles to upstream end of Newbold 
Island 40 feet deep and 400 feet wide, with suitable 
widening of bends, including relocation of channel at 
Delair Railroad bridge, and reconstruction of bridge, 
thence 5.5 miles to upper end of Trenton Marine Terminal, 
35 feet deep and 300 feet wide, with a turning 
basin 800 feet wide and 1,700 feet long at the terminal; 
and maintenance of a channel 12 feet deep and 300 feet 
wide from upper end of 34-foot channel to Penn Central 
railroad Bridge at Trenton, dredged under a previous 
project. Project also provides for an auxiliary channel 20 
feet deep and 200 feet wide east of Burlington Island, 
extending easterly from main channel to upper end of 
U.S.Pipe and Foundry Co.'s property at East Burlington, 
with a turning basin 450 feet wide at upper end; for 
initial excavation, only, of a cross channel 8 feet deep 
and 200 feet wide through artificial island opposite 
Delanco, NJ, and for construction of such bank protection 
works as may be necessary. Section included in 
project is about 30.5 miles long, excluding auxiliary 
channel east of Burlington Island, which is 1.4 miles 
long, and cross channel opposite Delanco. Lower end is 
about 55 miles above river mouth at Liston Point and 
about 105 miles above Harbor of Refuge at mouth of 
Delaware Bay. Freshets, which occur usually during 
February and March, attain a height of 9 to 20 feet above 
mean low water in the vicinity of Trenton. Navigation is 
occasionally suspended during a portion of winter 
months due to ice. Existing project is 90 percent complete. 
A 40-foot channel under the 1954 modification 
from Allegheny Avenue to upper end of Newbold Island 
was completed April 1964. Work remaining is dredging 
from upper end of Newbold Island to Trenton Marine 
Terminal and widening turning basin at terminal which 
is in deferred category. (See Table 3-B at end of chapter 
for Acts authorizing existing project. See Table 3-A at 
end of chapter for total cost for existing project to Sept. 
30,1992.) 
Local cooperation: Modification authorized by 1954 
3-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
River and Harbor Act provides local interests must provide 
suitable terminal facilities, furnish lands and 
rights-of-way for construction and future maintenance, 
and hold the United States free from damages. Local 
interest complied with requirements, except city of 
Trenton has not provided suitable terminal facilities. 
Terminal facilities: There are 21 piers, wharves, 
and docks from Allegheny Avenue, Philadelphia, PA to 
Trenton, NJ facilities are considered adequate for existing 
commerce. (For details see Port Series No. 8 (revised 
1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, hired 
labor: Work included general surveys, BCR update, environmental 
monitoring, general maintenance, plans 
and specifications, engineering and design, and supervision 
and administration. 
6. DELAWARE RIVER, PA, NJ, AND 
DE, PHILADELPHIA TO THE SEA 
Location: See U.S.Coast and Geodetic Survey Charts 
1218, 394, 295, and 280. 
Previous project: For details see page 1779 of Annual 
Report for 1915, and page 299, Annual Report for 
1938 
Existing project: Provides for a channel from deep 
water in Delaware Bay to a point in the bay, near Ship 
John Light, 40 feet deep and 1,000 feet wide; thence to 
Philadelphia Naval Base, 40 feet deep and 800 feet wide, 
with 1,200-foot width at Bulkhead Bar and 1,000-foot 
width at other bends; thence to Allegheny Avenue, 
Philadelphia, PA, 40 feet deep and 500 feet wide through 
Horseshoe Bend and 40 feet deep and 400 feet wide 
through Philadelphia Harbor, along west side of channel; 
and for anchorages at Reedy Point, Deepwater 
Point, Marcus Hook, and Mantua Creek, each 40 feet 
deep and 2,300 feet wide with respective length of 8,000, 
5,200, 12,650, and 11,500 feet; anchorage at Gloucester 
30 feet deep and about 3,500 feet long. Project also 
provides for construction of dikes and training works for 
regulation and control of tidal flow; for maintenance of 
an area on north side of channel opposite Philadelphia 
Naval Base between Shipway 3 and Schuylkill River to 
40 feet deep and width of 150 feet on Mifflin Range and 
200 feet on West Horseshoe Range; and for maintenance 
of any areas dredged by local interests to 35 feet deep 
between channel and a line 100 feet channelward of 
pierhead line between Point House wharf and Philadelphia 
Naval Base, when in opinion of Chief of Engineers 
such areas are so located as to be of benefit to generate 
navigation. Section included in project is about 96.5 
miles long. All depths refer to plane of mean low water. 
Under influence of heavy and long-continued winds extreme 
tidal range is about 14 feet. Normal maximum 
velocity of tidal currents in the dredged channel varies 
between 2 and 3.5 miles per hour. Storm tides may 
increase maximum to as much as 4.5 miles per hour. 
Estimated cost for new work is $71,630,000 (July 1972) 
exclusive of amounts expended on previous projects. 
Channel to 37 deep and 500 feet wide through Horseshoe 
Bend and 37 feet deep and 60 feet wide through Philadelphia 
Harbor along east side of channel and Port 
Richmond anchorage to 37 feet deep, except for that 
portion of channel which forms a part of 40 feet deep and 
400 feet wide channel portion is to be restudied and 
excluded from foregoing cost estimate. Estimated cost 
(July 1960) of this portion of project is $2,951,000. Existing 
project, excluding work deferred for restudy, is about 
66 percent complete. The 40-foot channel from Naval 
Base to the sea was completed in 1942. Dredging Naval 
Base to Allegheny Avenue to 40 feet deep was completed 
in 1962. Enlarging anchorage at Marcus Hook was completed 
in 1967. Work remaining is to construct new 
anchorages at Reedy Point and Deepwater Point, and 
enlarge Mantua Creek anchorage, channel dredging 
from 35 to 37 feet deep over a width of 500 feet through 
Horseshoe Bend and about 600 feet through Philadelphia 
Harbor, and deepening Port Richmond Anchorage 
to 37 feet, all of which have been deferred for restudy. 
(See Table 3-B at end of chapter for Acts authorizing 
existing project. See Table 3-A at end of chapter for total 
costs for existing project to Sept. 30,1992.) 
Local cooperation: Requirements under 1938 River 
and Harbor Act for maintaining channel and anchorage 
in Philadelphia Harbor annually by cities of Philadelphia 
and Camden were removed (see 1962 Annual 
Report for details). 
Terminal facilities: There are 217 piers, wharves, 
and docks between Allegheny Avenue, Philadelphia and 
the sea, 135 on the waterfront of Philadelphia, Camden, 
and Gloucester, and 82 below Philadelphia. Facilities 
are considered adequate for existing commerce. (For 
further details see Port Series Nos. 7, revised 1967, and 
8, revised 1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, contract: 
Work included aerial surveys, lease of amphibious 
carrier, construction of dikes and sluices, lease of equipment, 
ditching and chemical testing. Maintenance 
dredging by was accomplished Norfolk Dredging Company 
from September 30 1991 to January 14, 1992 and 
from July 31,1992 to September 30,1992 removing a 
total of 2,716,665 cubic yards of material at a cost of 
$4,410,927. Dredging was accomplished by Great Lakes 
Dredge & Dock Company from June 3,1992 to August 
14, 1992 removing a total of 200,000 cubic yards of 
material a cost of $1,834,560. 
Maintenance, hired labor: Work included surveys, 
general maintenance, disposal area well and environmental 
testing and monitoring, preparation arch site, 
pipelines, conditions and operation study, construction 
of subdrainage, leasing of equipment, rock removal at 
Oldmans's Groundwater and BCR update. Work on 
spot shoals, drainage and maintenance dredging, construction 
of dikes and sluices, disposal ditching, and 
plans and specifications, engineering and design, and 
supervision and administration was also accomplished. 
3-4

PHILADELPHIA, PA DISTRICT 
There was also maintenance dredging by the Government 
dredge McFarland from June 23, 1992 to August 
13, 1992 removing 300,000 cubic yards material at a cost 
of $1,578,118. 
7. DELAWARE RIVER VICINITY OF 
CAMDEN, NJ 
Location: Camden, NJ, on east bank of Delaware 
River, is directly opposite the city of Philadelphia, PA. It 
is about 51 miles above mouth of the river and about 101 
miles above Harbor of Refuge at the mouth of Delaware 
Bay. (See U.S. Coast Guard and Geodetic Survey Charts 
Nos. 295 and 280.) 
Previous project: Adopted by River and Harbor Act 
of June 25, 1910. No work was done on this project, for 
further details, see page 321, Annual Report for 1932. 
Existing project: The existing project which is a 
modification to the Delaware River from Philadelphia to 
the Sea project was adopted as House Document No. 
63-1120 in 1919 and modified by House Document No. 
70-111 in 1930 and House Document No. 77-353 in 1945. 
Dredging to project depth of 37 feet in front of the 
Camden Marine Terminal was completed in March 
1988. It also provides for dredging in of Camden to 
Newton Creek, with the depth increased to 40 feet in 
front of the Beckett Street Marine Terminal. These 
depths extend from the ship channel in Delaware River 
to a line parallel with and 50 feet distant from the 
established pierhead line. The project length is about 
four miles. Projects depths are well maintained in 30 
foot depth section of channel. Work is scheduled to 
initiate dredging the project depth of 40 feet in front of 
the Beckett Street Marine Terminal in FY 1992. Estimate 
cost for New Work (October 1990) is Federal, 
$4,500,000 and non-Federal, $1,500,000. (See Table 3-B 
at end of chapter for Acts authorizing existing project. 
See Table 3-A at end of chapter for total costs for existing 
project to Sept. 30, 1992.) 
Local cooperation: Fully complied with. 
Terminal facilities: See page 228, Annual Report 
1962. 
Operations during fiscal year: New Work, contract: 
Work included dredging by T.L. James from June 
6, 1992 to September 30, 1992 removing 217,216 cubic 
yards of material at a total cost of $2,503,028. 
New Work, hired labor: Work included tide gage, supervision 
and administration, engineering and design. 
8. INDIAN RIVER INLET AND BAY, DE 
Location: Indian River rises in Sussex County, DE, 
and flows easterly 13 miles into Indian River Bay which 
is a shallow lagoon 6 miles long and 2 miles wide on the 
Delaware Coast about midway between Cape Henlopen 
and the Maryland State line. The inlet is an opening 
through the barrier beach separating Indian River Bay 
and the Atlantic Ocean (See U.S.Coast and Geodetic 
Survey Chart No.1219.) 
Previous project: Adopted by River and Harbor Act 
of August 2, 1882. For further details see page 744, 
Annual Report for 1888. 
Existing project: This provides for the fixation of the 
inlet by the construction of two parallel jetties of steelsheet 
pile and stone design extending to approximately 
the 14-foot depth curve in the ocean, and for dredging an 
entrance channel 15 feet deep and 200 feet wide, for a 
distance of 7,000 feet inshore from the jetties; thence a 
channel 9 feet deep, 100 feet wide in the bay, and 80 feet 
wide in the river, to and including a turning basin 9 feet 
deep, 175 feet wide, and 300 feet long at Old Landing; 
thence a channel 4 feet deep and 60 feet wide to the 
highway bridge at Millsboro. The project also provides 
that the interior channel dimensions may, at the discretion 
of the Chief of Engineers, be modified as found 
desirable to increase the hydraulic efficiency of the channel, 
without increasing the cost. The total length of the 
section included in the project is about 13.75 miles. All 
depths refer to the plane of mean low water. The extreme 
tidal range at the highway bridge is about 6 feet. 
Existing project was completed in 1951. For details see 
Annual Report for 1963.(See Table 3-B at end of chapter 
for Acts authorizing existing project. See Table 3-A at 
end of chapter for total costs for existing project to Sept. 
30,1992.) 
Local cooperation: Fully complied with except that 
local interest are required to furnish suitable areas for 
disposal of dredged material during maintenance as and 
when needed, and provide terminal facilities. 
Terminal facilities: There is a privately owned 
basin with berthing facilities for small boats located .75 
miles west of the highway bridgenear the inlet and .25 
miles north of the inlet channel, connected therewith by 
a channel 6 feet deep and 40 feet wide; a U.S. Coast 
Guard wharf on the north side of the inlet channel in the 
same locality; and two wharves at Oak Orchard in Indian 
River Bay. The facilities are considered adequate 
for existing commerce. 
Operations during fiscal year: Maintenance, contract: 
Work included hydo-dynamic model testing inlet 
scour and stabilization. 
Maintenance, hired labor: Work included inlet scour, 
stabilization study, tide gage, and engineering and 
design. 
9. INLAND WATERWAY FROM 
DELAWARE RIVER TO CHESAPEAKE 
BAY DE, AND MD 
Location: The Waterway begins at Reedy Point on 
Delaware River, about 41 miles below Philadelphia, PA, 
and passes through the sea level Chesapeake and 
Delaware Canal, a distance of 14 miles, to Back Creek, 
at Chesapeake City, MD. It then passes for 5 miles 
3-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
down Back Creek, thence 9 miles down Elk River to 
Chesapeake Bay and thence 18 miles down Chesapeake 
Bay to a point near Pooles Island. A branch channel 
connects Delaware River at Delaware City, DE, with 
main channel at a point about 1.5 miles west of Reedy 
Point.(See U.S.Coast and Geodetic Survey Charts 294, 
1226, 570, and 572.) 
Previous project: For details see Annual Report for 
1934, page 242, and Annual Report for 1938, page 312. 
Existing project: A channel 35 feet deep and 450 feet 
wide from Delaware River through Elk River and 
Chesapeake Bay to water of natural 35-foot depth in 
Chesapeake Bay including a cutoff at Penn Central 
Railroad crossing, and having a maximum radius of 
curvature of 7,000 feet at bends; a high-level, fixed 
railroad bridge with vertical clearance of 135 feet and 
horizontal clearance of 600 feet at the railroad crossing 
over the cutoff (economic study of railroad crossing requested 
by Office of Management and Budget resulted 
in construction of a single track vertical lift bridge in lieu 
of a high-level fixed railroad bridge); high-level fixed 
highway bridges over canal at Reedy Point, St. Georges, 
Summit, and Chesapeake City; a bascule drawbridge 
across Delaware City Branch Channel; extension of 
entrance jetties at Reedy Point; and anchorage in Elk 
River, 35 feet deep and 1,200 feet wide, with an average 
length of 3,700 feet; enlargement of anchorage and 
mooring basin in Back Creek to afford an area about 400 
feet wide, 1000 feet long, and 12 feet deep;dredging 
Delaware City Branch Channel to 8 feet deep and 50 feet 
wide, and deepening existing basin to same depth; revetment 
of banks of canal as required between Delaware 
and Elk Rivers, and on banks of Delaware City Branch 
Channel east of Fifth Street Bridge; and construction of 
bulkheads. Total of section included in project, excluding 
Delaware City Branch Channel, which is about 2 miles 
long, is about 46 miles. All depths refer to plane of low 
water in Delaware River. Extreme tidal range is from 
6.3 feet above mean high water to 3 feet below mean low 
water. Existing project is about 89 percent completed. 
Channel 27 feet deep and 250 to 400 feet wide. Delaware 
River to Pooles Island, completed in 1938. High-level 
fixed highway bridges were completed at St. Georges 
(4-lane) in 1942; at Chesapeake City (2-lane) in 1949; 
and at Summit (4-lane) in 1960. Relocation of Penn 
Central Railroad bridge was completed December 21, 
1965. Enlargement to 35 feet deep and 450 feet wide St. 
Georges and Summit bridges and Summit and Goose 
Island was completed on June 20, 1972 and February 18, 
1972, respectively. Removing the old Penn Central railroad 
bridge was completed on January 21, 1972. 
Channel work for Part II is about 87 percent complete. 
Work remaining consists of completing channel enlargement 
to 35 feet deep and 450 feet wide between Reedy 
Point Bridge and St. Georges Bridge; widening and 
deepening the channel between Delaware River and 
Reedy Point Bridge, the completion of recreation 
facilities, and miscellaneous completion items. Deepening 
of the Delaware City Branch Channel from 6 to 8 feet 
from a point 400 feet east of Fifth Street Bridge to its 
junction with the canal has been deferred for study. 
Original cost of canal including purchase was 
$10,709,755; estimated cost of new work for modifications 
of 1935 and 1954 is federal cost $139,000,000 and 
non-federal cost $17,189,000 (October 1990). Major 
Rehabilitation of St. Georges and Summit Bridges was 
completed in fiscal year 1991 at an approximate federal 
cost of $20,868,000. Portion of project comprising completion 
of Delaware City Branch Channel from a point 
400 feet east of Fifth Street Bridge to its junction with 
canal is to be restudied and excluded from foregoing 
estimate. Estimated cost of this portion is $145,000 
(July 1954). (See Table 3-A at end of chapter for total 
costs for existing project to Sept. 30,1992. See Table 3-B 
at end of chapter for Acts authorizing existing project.) 
Local cooperation: River and Harbor Act of 1954 
provided that local interests furnish lands and rights-ofway 
required for bridges. Assurances accepted and 
approved February 16, 1955. Requirements for Summit 
and Reedy Point Bridges have been met. 
Terminal facilities: Ample mooring facilities at 
eastern and western ends of canal and bulkheads at 
Delaware City and St. Georges were constructed by the 
United States. A small-boat harbor was provided and a 
wharf constructed at Chesapeake City. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, contract: 
Work included electrical maintenance, 
environmental monitoring, bridge inspection, night 
lighting, operation and minor maintenance on museum 
, maintenance of bridges. There was also maintenance 
dredging by Great Lakes Dredge & Dock Company from 
October 28, 1991 to November 8, 1991 removing a total 
of 498,314 cubic yards of material at a total cost of 
$1,389,000. 
Maintenance, hired labor: Work included general 
maintenance of rip-rap, bridges, roadways, monitoring 
of stabilization banks, night lighting, ditching, buildings, 
locks, and grounds. Also included in work was 
drainage of disposal areas, lease of equipment, bridge 
inspections, dispatch, surveys, flow and tide monitoring, 
flow and environmental monitoring, maintenance 
dredging, snagging and clearing, modification to 
hydrodynamic, plans and specifications, mosquito control, 
engineering and design, and supervision and 
administration. 
10. INLAND WATERWAY, REHOBOTH BAY 
TO DELAWARE BAY, DE 
Location: A tidal canal in southeasterly part of Sussex 
County, DE It extends 12 miles northward from 
Rehoboth Bay through high land west of town of 
Rehoboth to Gordon Lake; thence down Lewes River to 
its junction with Broadkill River near its mouth. An 
entrance to the waterway from Delaware Bay is about 4 
miles above Cape Henlopen. (See U.S. Coast and 
Geodetic Survey Charts 379, 1218, and 1219.) 
3-6

PHILADELPHIA, PA DISTRICT 
Previous project: A canal along a slightly different 
route formed a part of projected waterway from Chincoteague 
Bay, Va. to Delaware Bay, begun in 1886 and 
abandoned in 1905. 
Existing project: This provides for an entrance 
channel near Lewes 10 feet deep and 200 feet wide 
protected by two parallel jetties 500 feet apart; thence a 
channel 10 feet deep and 100 feet wide to South Street 
Bridge at Lewes, and a basin of the same depth 1,200 
feet long and up to 375 feet in width at the latter point; 
thence a channel 6 feet deep and 100 feet wide (40 feet 
wide through Deep Cut near Rehoboth Bay) to Rehoboth 
Bay; a channel 6 feet deep and 100 feet wide from the 
entrance to Broadkill River; two parallel rubble jetties 
725 feet long at the Rehoboth Bay entrance; and the 
construction of the one highway bridge and one railroad 
Bridge to Rehoboth. The total length of the section 
included in the project is about 12 miles. 
The extension of the jetties at the Delaware Bay 
entrance is considered to be inactive and is excluded 
from the foregoing cost. The cost of the portion was last 
revised in 1960 and was estimated to be $816,000. Existing 
project is about 70 percent complete. For details 
on completed work see page 241 of Annual Report for 
1963. Work remaining, extension of existing jetties at 
Delaware Bay entrance, is considered inactive. The 
Sheet Pile Jetty at the Delaware Bay entrance was 
removed during FY 1987. (See Table 3-A at end of 
chapter for total costs for existing project to Sept. 
30,1991. See Table 3-B at end of chapter for Acts 
authorizing existing project.) 
Local cooperation: Complied with except local interest 
must furnish suitable terminal facilities and 
necessary spoil-disposal areas. 
Terminal facilities: See page 228, Annual Report 
1962. 
Operations during fiscal year Maintenance hired 
labor: Work included survey on maintenance dredging 
and plans and specifications. 
Maintenance, contract: Work included removal of 
sheet pile jetty. 
11. MISPILLION RIVER, DE 
Location: Rises in Kent County and Sussex Counties, 
DE, flows northeasterly 15 miles along the boundary 
line between the two counties and emties into Delaware 
Bay about 16 miles above Cape Henlopen .(See Coast 
and Geodetic Survey Chart 1218). 
Previous project: For details see page 1786, Annual 
Report for 1915, page 448 of Annual Report for 1918, and 
page 327 of Annual Report for 1938. 
Existing project: Project is about 31 percent complete. 
Four cutoffs for 6-foot channel were completed in 
1923; 6-foot channel from Delaware Bay to Milford in 
1924; and jetties at the mouth in 1939. Work remaining 
is dredging channel to 9-foot depth, 80 feet wide in 
Delaware Bay to the mouth, thence 60 feet wide to 
Milford, with the provision of three cutoffs to eliminate 
bends, and a turning basin at Milford. Controlling 
depths at mean low water; in October 1964 from 
Delaware Bay to mouth 7.1 feet, and thence to fixed 
highway bridge at Report 1957, (See Table 3-A end of 
chapter for total costs for existing project to Sept. 30, 
1992.) 
Local cooperation: Assurances required by 1954 
River and Harbor Act have not been furnished. For 
details see page 243, Annual Report for 1957. Prior 
requirements fully complied with. 
Terminal facilities: For details see page 244, Annual 
Report for 1957. 
Operations during fiscal year: Maintenance, 
hired labor: Work included breach repair , environmental 
monitoring, disposal area sub-surface exploration 
and design. 
12. MURDERKILL RIVER, DE 
Location: Rises in Kent County, DE, flows northeasterly 
19 miles through county, and empties into 
Delaware Bay about 25 miles above Cape Henlopen. 
(See U.S. Coast and Geodetic Survey Chart no. 1218.) 
Existing project: Provides for a channel 7 feet deep 
at mean low water, 150 feet wide in Delaware Bay to 
mouth, and thence 80 feet wide to Frederica, 7.5 miles 
above mouth. Total length of section included in project 
is about 8.5 miles. Extreme tidal range is from about 1 
foot below mean low water to about 2 feet above mean 
high water. 
Estimated cost for new work revised in 1954 is 
$38,000. Portion comprising widening channel to project 
width throughout its length is to be restudied and excluded 
from foregoing cost estimate. Estimated cost of 
this portion last revised in 1954 was $86,000. Project 
was authorized by River and Harbor Act of July 13, 1892 
(H. Ex. Doc. 21,52d Cong., 1st Sess. See page 981 Annual 
Report for 1892). Latest published map is in House 
Document 1058,62d Congress 3d Session. 
Existing project about 30 percent complete, including 
revision to be restudied. Channel 7 feet deep and 60 feet 
wide was completed in 1911. Work remaining is widening 
the channel to project width. (See Table 3-A at end 
of chapter for total costs for existing project to Sept. 
30,1992.) 
Local cooperation: None required. 
Terminal facilities: There are a number of light 
timber wharves on both sides of river near mouth and 
two wharves at Frederica, all privately owned. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year: Maintenance, 
3-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
hired labor: Work included plans and specifications, 
engineering and design, and supervision and administration. 
13. NEW JERSEY INTRACOASTAL 
WATERWAY 
Location: A sea level inland water route approximately 
parallel with New Jersey coast, extends 
from Atlantic Ocean at Manasquan Inlet, about 26 miles 
south of Sandy Hook, NJ to Delaware Bay about 3 miles 
above Cape May point. Waterway extends through inlet 
and up Manasquan River about 2 miles; thence by Point 
Pleasant Canal through high ground for 2 miles to head 
of Barnegat Bay. It then passes through a series of bays, 
lagoons, and thoroughfares along New Jersey coast to 
Cape May Harbor; thence across Cape May County to 
Delaware Bay through a land cut by way of New 
England Creek basin.(See U.S.Coast and Geodetic Survey 
Charts, 234, 795, 825, 826, 827, 1216, 1217, 1218, 
and 1219.) 
Existing project: This provides for a channel 12 feet 
deep at mean low water and generally 100 feet wide, 
extending from the Atlantic Ocean at Manasquan Inlet, 
NJ to Delaware Bay above Cape May, NJ, by the further 
improvement of Manasquan River and Inlet, NJ, and the 
present New Jersey Intracoastal Waterway, and by the 
construction of a canal of similar dimensions from Cape 
May Harbor to Delaware Bay via the New England 
Creek basin, with adequate jetties at the Delaware Bay 
entrance. The total length of the project is about 117 
miles. Normal tide range in sections of the waterway 
remote from inlets is 0.5 foot. 
Estimated cost for new work is $71,549 (July 1969), 
exclusive of $1,824,940 Navy Department funds and 
$99,000 contributed by local interests. Portion of project 
extending from Manasquan River to Cape May Harbor 
is to be restudied and excluded from new work costs 
estimate. Estimated cost of this portion is $6,470,000 
(July 1954). Existing project was adopted by 1945 River 
and Harbor Act (H.Doc 133, 76th Cong., 1st Sess.) Latest 
published map is in project document. River and Harbor 
Act of 1946 (Public Law 525,79th Cong., 2nd Sess., as 
extended by Public Law 240,82d Cong.), authorized use 
for a period not to exceed 6 years, of funds from appropriations 
heretofore or hereafter made for 
maintenance and improvement of rivers and harbors, for 
maintenance of canal from Cape May Harbor to 
Delaware Bay constructed as an emergency wartime 
project with Navy Department funds, including cost of 
maintaining temporary railroad and seashore highway 
bridges over canal. 
Existing project is about 25 percent complete. A canal 
12 feet deep and 100 feet wide from Cape May Harbor to 
Delaware Bay was completed in 1942 as well as two 
parallel stone jetties at Delaware Bay entrances and a 
temporary highway and a railroad bridge in 1944, all 
with Navy Department funds. Work remaining consists 
of dredging a channel 12 feet deep and 100 feet wide 
from Atlantic Ocean at Manasquan Inlet to Cape May 
Harbor, has been deferred for restudy; however, the 
project between Ottens Harbor and Richardson Channel 
and from that point to Cape May are being maintained 
to 10 feet and 12 feet, respectively, since they were 
originally dredged to these depths by the State. Section 
860 of the Water Resources Development Act of 1986 
authorized, for preconstruction engineering and design, 
a 15 foot depth in the Vicinity of Cape May Harbor, titled 
as Cold Spring Inlet. (See Table 3-A at end of chapter for 
total costs for existing project to Sept. 30,1992.) 
Local cooperation: The project is subject to the 
conditions that the State of New Jersey cede to the 
United States all right, title, and interest that it has 
acquired to lands, easements, rights-of-way, and structures 
other than bridges for the Bayhead-Manasquan 
Canal; that the State of New Jersey furnish, free of cost 
to the United States, all lands, easements, rights-ofway, 
and disposal areas required for construction of the 
Cape May Canal and for improvement of the proposed 
waterway and for their subsequent maintenance; that 
local interests provide, maintain, and operate suitable 
bridges over the waterway; that the State of New Jersey 
donate to the United States the navigation aids in use 
on the present New Jersey Intracoastal Waterway; and 
that the State of New Jersey hold and save the United 
States and its agents free from any claims for damages 
resulting from the work of improvement. Compliance 
with these conditions was completed January 15, 1954, 
except that local interests are required to furnish disposal 
areas for the construction and the subsequent 
maintenance of the proposed improvements. 
Terminal facilities: See Annual Report for 1962. 
Operations during fiscal year: Maintenance, contract: 
Work included Pt. Pleasant bulkhead coating, 
environmental monitoring, bank stabilization, and 
repair bank erosion. There was maintenance dredging 
by Barnegat Bay Dredging Company from September 
30, 1991 to December 17, 1991 and from March 17, 1992 
to September 30, 1992 removing a total of 450,000 cubic 
yards of material at a total cost of $1,548,056. 
Maintenance, hired labor: Work included general 
maintenance, dike construction, surveys, repair of bank 
erosion, maintenance dredging, plans and specifications, 
engineering and design, and supervision and 
administration. 
14. SALEM RIVER, NJ 
Location: This river rises in Salem County, NJ, flows 
through the county westerly 13 miles, thence southerly 
7 miles to the City of Salem, and thence westerly 3 miles, 
emptying into Delaware River about 45 miles below 
Philadelphia, PA. It is joined at Salem by Little Salem 
River, or Fenwick Creek, from the east. (See U.S. Coast 
and Geodetic Survey Chart No. 294.) 
Previous project: The River and Harbor Act of July 
11, 1870, provided for a survey and the original project 
3-8

PIILADELPHIA, PA DISTRICT 
was adopted by River and Harbor Act of March 3, 1871, 
and modified in 1878, and a subsequent project adopted 
by River and Harbor Act of March 2, 1907. For further 
details see page 1784, Annual Report for 1915; page 349 
of Annual Report for 1924; and page 346 of Annual 
Report for 1938. 
Existing project: This provides for a channel 12 feet 
deep at mean low water, 150 feet wide in Delaware River 
across Salem Cove to the mouth, thence 100 feet wide to 
the fixed highway bridge in Little Salem River at Salem, 
2 1/4 miles above the mouth. It also provides for a cutoff 
to eliminate a large horseshoe bend between the mouth 
and Salem. The total length of the section included in 
the project is about 4 miles. The mean tidal range is 5.4 
feet. The extreme tidal range is from about 1 foot below 
mean low water to about 2 feet above mean high water. 
The estimate of cost for new work 51,825 exclusive of 
amounts expended on previous projects and $51,825 contributed 
by local interests. The portion of the project 
comprising the deepening of Little Salem River to 12 feet 
is to be restudied and is excluded from the foregoing 
estimate. The estimated cost of this portion revised in 
1953 is $28,000 excluding an equal amount to be contributed 
by local interests. 
The existing project is about 64 percent completed. 
The dredging of the channel from Penns Neck Bridge to 
project dimensions, including the cutoff, was completed 
in 1928. The channel from Penns Neck Bridge to the fixed 
highway bridge in Little Salem River was dredged to a 
depth of 9 feet under a previous project. The work 
remaining to be done is the deepening of the channel in 
Little Salem River from 9 feet to 12 feet. (See Table 3-A 
at end of chapter for total costs for existingproject to Sept. 
30, 1992.) 
The controlling depths at mean low water were as 
follows: In January 1961, Delaware River to Penns Neck 
Highway Bridge 12.0 feet; and thence in December 1956 
to the fixed highway bridge at Salem, 0.9 feet. 
The existing project was adopted by the River and 
Harbor Act of March 3, 1925 (H.Doc. 110, 68th Cong. 1st 
Sess.) The latest published map is in this document. 
Section 859 of the Water Resources Development Act 
of 1986 authorized a project depth of 20 feet. 
Local cooperation: The existing project required 
local interest contribute 50 percent of the estimated costs 
of new work and that a right-of-way for the proposed 
cutoff shall be conveyed to the United States free of cost. 
The contributions thus far made provided the right of way 
for the cutoff and 50 percent of the cost of the 12-foot 
channel up to a point 225 feet above the county (Penns 
Neck) highway bridge, amounting to $51,825. 
Terminal facilities: There are 9 wharves on the 
river all at Salem, NJ. Eight wharves are privately 
owned and one is owned by the City. The facilities are 
considered adequate for existing commerce. 
Operations during fiscal year*. Maintenance, contract: 
Work included einvornmental monitoring, 
dredging by Cottrell Dredging from August 4, 1992 to 
October 18, 1992 removing 90,173 cubic yards of 
material at a cost of $314,000. 
Maintenance, hired labor: Work included surveys, supervision 
and administration on maintenance dredging, 
engineering and design and plans and specifications. 
15. SCHUYLKILL RIVER, PA 
Location: Rises in Schuylkill County, PA, flows 
generally southeasterly 150 miles, and empties into 
Delaware River at Philadelphia, PA (See U.S. Coast and 
Geodetic Survey Charts 295 and 280.) 
Previous project: For details see page 325, Annual 
Report for 1932. 
Existing project: This provides for a channel 33 feet 
deep and 400 feet wide in Delaware River the mouth and 
within the river to 29th Street, .75 mile above the mouth; 
thence the same depth and 300 feet wide to Passyunk 
Avenue Bridge, 3.5 miles above the mouth; thence 26 feet 
deep and 300 feet wide to Gibson Point, 4.5 miles above 
the mouth; and thence 22 feet deep and 200 feet wide to 
University Avenue Bridge, 6 miles above the mouth, 
including widening at bends. The total length of the 
section included in the project is about 6.5 miles. All 
depths refer to the plane of mean low water. The extreme 
tidal range, due to freshets and prolonged heavy winds, 
is about 14 feet. 
The cost for new work for the completed existing 
project was $2,809,007. Existing project was completed 
in September 1962. For details see Annual Report for 
1962. (See Table 3-A at end of chapter for total costs for 
existing project to Sept. 30,1992. See Table 3-B at end of 
chapter for acts authorizing existing project.) 
Local cooperation: The River and Harbor Act of 
July 24, 1946, imposed the condition that the City of 
Philadelphia agree to remove 60,000 cubic yards, place 
measurement, of material annually from that portion of 
those portions of the project which the District Engineer 
may designate until such time as adequate municipal 
sewage-treatment works are constructed and placed in 
effective operation. Compliance with this condition has 
been met through the completion of sewage-treatment 
works by the City of Philadelphia. All other requirements 
have been fully complied with. 
Terminal facilities: There are 38 wharves, piers, 
and docks within limits of improvement. Facilities are 
considered adequate for existing commerce. (For further 
details see Port Series No. 7, Revised 1967, Corps of 
Engineers.) 
Operations during fiscal year: Maintenance, contract: 
There was maintenance dredging by Great Lakes 
Dredge & Dock Company from December 5,1991 to 
December 31, 1991 removing 413,593 cubic yards of 
material at a cost of $1,010,583. 
Maintenance, hired labor: Work included surveys, 
general maintenance, plans and specifications, en- 
3-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
gineering and design, and supervision and administration. 
16. WILMINGTON HARBOR, DE 
Location: Formed by Christina River, which rises in 
New Castle County, DE, flows northeasterly 16 miles, 
passing through the City of Wilmington, DE, and 
empties into Delaware River about 29 miles below 
Philadelphia, PA (See U.S. Coast and Geodetic Survey 
Chart 294.) 
Previous project: For details see page 1785 of Annual 
Report for 1915 and page 308 of Annual Report for 
1938. 
Existing project: This provides for a channel 38 feet 
deep and 400 feet wide from west edge of Delaware River 
ship channel to Lobdell Canal, a distance of about 1.2 
miles; thence 21 feet deep and 250 feet wide for the 
distance of .8 mile to the mouth of Brandywine River; 
thence the same depth and 200 feet wide for a distance 
of about 2.2 miles to a point approximately 4.2 miles 
from the Delaware River ship channel; thence decreasing 
to a depth of 10 feet in a distance of 750 feet to Penn 
Central Railroad bridge No.4; and thence 7 feet deep and 
100 feet wide for a distance of of about 5.6 miles to 
Newport, DE, approximately 9.9 miles above Delaware 
River ship channel, including a turning basin 38 feet 
deep opposite the Wilmington Marine terminal and extending 
upstream from the mouth to Lobdell Canal, 320 
feet wide, 2,900 feet long on the north side of the channel 
and decreasing to a length of 2,000 feet on the north side 
of the basin. It also provides for the removal of about 
1,200 feet of the outer end of a stone-filled, pile-and-timber 
crib jetty constructed 2,150 feet long on the north 
side of the entrance; for a steel sheet-pile jetty 2,300 feet 
long, with 120-foot inshore wing, on the south side of the 
entrance, and for a V-shaped stone-filled pile-and-timber 
jetty at the mouth of Brandywine River 430 feet 
along the north side of Brandywine and 260 feet long on 
the Christina. Depths refer to the plane of mean low 
water. The extreme tidal range, due to prolonged heavy 
winds, is about 13 feet. Existing project was completed 
in 1962. (For details see page 222, Annual Report 1962.) 
Authority from Section 107 of the River and Harbor Act 
of July 1960 provide for channel and turning basin 
deepening from 35 to 38 feet and the turning basin 
widened from 200 to 320 feet. (See Table 3-A at end of 
chapter for total costs for existing project to Sept. 
30,1992. See Table 3-B at end of Chapter for Acts 
authorizing existing project.) 
Local cooperation: Fully complied with. 
Terminal facilities: There are 18 piers, wharves, 
and docks within limits of the improvement. Facilities 
considered adequate for existing commerce. (For further 
details see Port Series No.8, revised 1966-Corps of Engineers.) 
Operations during fiscal year: Maintenance, contract: 
Work included construction of dikes and sluices, 
lease of equipment, wetland mitigation, monitoring of 
artificial reef, boundary monumentation, and installation 
and maintenance stream gaging. There was 
maintenance dredging by American Dredging Company 
from September 30,1991 to December 5,1991 removing 
a total of 255,319 cubic yards of material at a cost of 
$255,319. Dredging was also done by Norfolk Dredging 
Company from July 9, 1992 to July 25,1992 removing 
360,982 cubic yards of material at a cost of $507,932. 
Maintenance, hired labor: Work included general 
maintenance, environmental monitoring, wetland 
mitigation, BCR updates, monitoring of artificial reefs, 
construction of dikes and sluices, plans and specifications, 
survey, mapping, ditching and drainage of 
disposal area, engineering and design, and supervision 
and administration. 
Beach Erosion Control: 
17. CAPE MAY INLET TO LOWER TWP., NJ 
Location: The proposed project is located in Cape 
May County and extends along the beach front from the 
northern side of Cape May Inlet to the boundary of 
Lower Township, and Cape May City. 
Existing project: The plan, as presented in HD 94- 
641, was authorized for the Phase I Design 
Memorandum Stage of Advance Engineering and 
Design by Section 101a of the Water Resources Development 
Act of 1976, proposes the following features: 
breakwater on the updrift side of Cape May Inlet; beachfill 
from Cape May Inlet to Cape May Point; provision of 
a dune with sand fence and grass from Cape May Inlet 
to Wilmington Avenue; construction of two groins in 
Cape May City and seven groins in Lower Township; 
inclusion of all groins comprising the existing project; 
and periodic nourishment of the beaches and maintenance 
of the dune and dikes. 
The Phase I GDM, completed in August 1980 and 
approved by the Chief of Engineers in December 1981, 
determined that only beach erosion control measures in 
Cape May City are warranted. The plan proposed in that 
document consists of modifying the existing navigation 
project for Cape May Inlet to provide; a weir-breakwater 
at Cape May Inlet with construction being deferred 
pending demonstration of need; two new groins at Trenton 
and Baltimore Avenues in Cape May City; 
placement ofbeachfill between Cape May Inlet and the 
terminal groin at Third Avenue in Cape May City; maintenance 
of two new groins and existing groins in Cape 
May; periodic beach maintenance with material obtained 
from deposition basin on the northeast side of 
Cape May Inlet; and institution of a beach monitoring 
program in Lower Township area. Work for the initial 
beachfill was accomplished as follows; USGS feeder 
beach fiscal year 1989, Cape May City groin fiscal year 
1990, and Beachfill Cape May City fiscal year 1991. 
Project estimate costs (October 1990) is Federal, 
$112,000,000, which includes $61,034,000 of Coast 
3-10

PHILADELPHIA, PA DISTRICT 
Guard contributions non-Federal costs are 
$124,300,000. 
The existing authority is for Phase I studies as 
provided by Section 101(a) of the Water Resources 
Development Act of 1976 in accordance with the 
provision of House Document 94-641. Continuation of 
planning and engineering for this proposed project was 
initiated in October 1977. The Phase I GDM was completed 
in August 1980 and approved by the Chief of 
Engineers in December 1981. Phase II AE&D studies 
were completed in July 1983. The project was authorized 
for separable elements under Section 501(a) of the 
Water Resources Development Act of 1986, PL 99-662. 
(See Table 3-A at end of chapter for total cost for existing 
project to Sept. 30,1992.) 
Local cooperation: The State of New Jersey furnished 
a letter of intent on 6 May 1981 regarding their 
willingness to comply with the above items of local 
cooperation. In addition, a draft Section 221 local 
cooperation agreement has been coordinated with letter 
of intent on 31 May 1983 regarding compliance with the 
items of local cooperation. 
Operations during fiscal year: New work, contract: 
Work included inlet beachfill, periodic 
nourishment, and construction of groins at Cape May 
City. 
New Work, hired labor: Work included inlet monitoring, 
surveys, mapping, and supervision and 
administration. 
Flood Control 
18. BELTZVJLLE LAKE, PA 
Location: Damsite is on Pohopoco Creek about 4.5 
miles upstream from its confluence with Lehigh River 
and 4 miles east of Lehighton, PA (See Geological Survey 
Quadrangle Map for Lehighton, PA-1960.) 
Existing project: This is a multiple-purpose 
development project providing water supply, flood control, 
and recreation. Plan of improvement provides for 
an earth and rock fill dam 4,200 feet long rising 170 feet 
above creekbed; a spillway around the north end of dam; 
and gate control outlet works discharging through a 
conduit on rock along right abutment. The lake, a unit 
of comprehensive plan for flood control and other purposes 
of Delaware River Basin, has a reservoir capacity 
of 68,250 acre-feet at spillway crest level with 1,390 
acre-feet of inactive storage, 39,830 acre-feet for water 
supply and recreation, and 27,030 acre-feet for flood 
control. The cost of project was $22,931,400 including 
$6,100,000 required non-Federal reimbursement for 
costs allocated to water supply storage during life of 
project. The construction of the dam and appurtenances 
was completed in 1971. (See Table 3-A at end of chapter 
for total costs for existing project to Sept. 30,1992.) 
Local cooperation: Project was approved subject to 
certain requirements of cooperation by local interests as 
defined in approved House Document. Resolution of 
Delaware River Basin Commission providing assurances 
of repayment of water supply and pollution control 
costs was accepted June 7, 1965. A contract for repayment 
of water supply costs was signed October 16,1966. 
Operations during fiscal year: Maintenance, contract: 
Work included maintenance of stream gauge, 
water quality testing and monitoring, surveys, concrete 
testing, computer maintenance, installation of water 
supply joint use facility, maintenance of dam tower, and 
leak detection device, and weir study. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir, USGS snow surveys, 
water quality testing and monitoring, painting of service 
bridges, , engineering and design on dam slope, ditches 
and stilling basin, and supervision and administration. 
19. BLUE MARSH LAKE, PA 
Location: Dam site is on Tulpehocken Creek about 
1.5 miles upstream from its confluence with Plum Creek 
and about 6 miles northwest of Reading, PA (See 
Geological Survey Quadrangle Sheet, Bernville, PA) 
Existing project: This is a multiple-purpose 
development project providing water supply, flood control, 
and recreation. Construction started in 1974 and 
was completed in 1980. The dam is 1,775 feet long and 
rises 98 feet above creekbed, with spillway about. 1,500 
feet south of dam, and gate-controlled outlet works discharging 
through a conduit on rock along right 
abutment. The lake, a unit of comprehensive plan for 
flood control and other purposes of Delaware River 
Basin, has a capacity of 50,010 acre-feet at spillway crest 
level, with 3,000 acre-feet of inactive storage, 14,620 
acre-feet for water supply and recreation, and 32,390 
acre-feet for flood control.(For details see H.Doc 533 
87th Cong., 2nd Sess.) Cost of project $63,163,791. Existing 
project was authorized by 1962 Flood Control Act. 
(See Table 3-A at end of chapter for total costs for 
existing project to Sept. 30,1992.) (H. Doc. 533, 87th 
Cong., 2d Sess., contains latest published maps.) 
Local cooperation: Project was approved subject to 
certain requirements by local interests, as prescribed in 
House Document cited above. Delaware River Basin 
Commission on December 29, 1964, adopted a preliminary 
resolution providing for repayment of water supply 
costs. 
Operations during fiscal year:. Maintenance, contract: 
Work included recreation safety program, 
computer maintenance, electrical services, installation 
of tiolet partitions, leak detection device, bridge inspection, 
survey monitoring, water quality testing, surveys 
by USGS, work on stilling basin, arch survey, sewage 
treatment plant, snow survey and NOAA Weather Service 
Cooperation. Work also included lawn 
maintenance, janitorial services, trash removal, and 
cost incurred for Lower Heidelberg and Bern Township 
3-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
police department. 
Maintenance, hired labor: Work included operation 
and maintenance of recreation area, instrumentation 
and surveillance, leak detection device, reservoir, water 
quality testing and monitoring. There was joint use of 
water facilities, work on stilling basin, boat launch, day 
use area, drilling of well, installation of siding on storage 
barn, engineering and design, and supervision and administration. 
Also incurred were costs for seasonal 
employment at recreation area and boat launch repairs. 
20. DELAWARE COAST PROTECTION, DE 
Location: The project is located in Sussex County, 
Delaware, on the Atlantic Ocean and starts immediately 
south of Delaware Bay extending in a southerly direction 
a distance of 24.5 miles to Fenwick Island on the 
Delaware-Maryland border. 
Previous Project: The previous project, adopted as 
HD 85-216 in 1958 and modified by P.L. 87-874 in 1962, 
provided for Federal participation in the cost of restoration 
and subsequent periodic nourishment, and the 
initial periodic nourishment was completed in 1957 by 
local interests. The second increment of beach 
replenishment by local interest was completed in 1963. 
Existing project: Provides a plan of improvement 
which consists of the construction of a sand bypass 
system and periodic nourishment until 2027. (For 
details, see S. Doc. 90,90th Cong. 2d Sess.) Estimated 
cost of project (October 1989) is 22,400,000 of which 
10,300,000 are federal costs and $12,100,000 are required 
non-Federal costs. The construction of the feeder 
beach north of Indian River Inlet was completed in 1973 
and nourished in 1978, and 1984. Other work undertaken 
has been engineering and design associated for 
the remaining portion of the project. (See Table 3-A at 
end of chapter for total costs for existing project to Sept. 
30,1992.) Section 869 of the Water Resources Development 
Act of 1986 deauthorized the unshceduled portion 
of the project. 
Local cooperation: Assurances of local cooperation 
were provided by the State of Delaware, January 13, 
1981. 
Operations during fiscal year: New work, contract: 
Work included operation of sand bypassing plant 
and monitoring. 
New work, hired labor: Work included monitoring 
sand bypassing plant, and engineering and design. 
21. FLOOD AND CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, 
Public Law 838, 80th Congress, as amended 
(Preauthorization). 
Name of Project Cost to 30 Sept. 1992 
Feasibility Reports 
Newton Creek, Woodlynne N.J. 
Palmerton, PA. 
Shabakunk Creek, Ewing, NJ 
Construction 
Poquessing Creek Bucks County, PA 
$ 161,350 
$ 2,484 
$40,210 
$ 2,979 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
antecedent legislation). 
Fiscal year costs were $540,570 for disaster preparedness. 
22. EMERGENCY BANK PROTECTION 
Emergency Bank Protection Section 14, Public Law 
79-526. 
Feasibility Reports 
Manasquan River, Howell Township, NJ $ 27,174 
23. FRANCIS E. WALTER DAM, PA 
Location: Reservoir is in northeastern Pennsylvania 
on Lehigh River between White Haven and Stoddartsville. 
Dam is about 0.4 mile below mouth of Bear 
Creek, about 60 miles above confluence of Lehigh River 
and Delaware River at Easton, PA(See Geological Survey 
Quadrangle Sheet, Stoddartsville, PA) 
Existing project: Plan of improvement authorized 
by 1946 Flood Control Act (H. Doc. 587,79th Cong.,2d 
Sess.) provided for a single-purpose flood control reservoir. 
Modification of project, authorized by 1962 Flood 
Control Act (H. Doc.522,87th Cong., 2d Sess.), provides 
for a multiple-purpose development for water supply 
and recreation in addition to present single-purpose 
flood control project. Plan of improvement requires altering 
spillway, increasing height of dam, constructing 
a new intake tower, extending outlet tunnel by addition 
of a concrete conduit, and constructing new dikes and 
raising existing dikes. Modified dam will rise 264 feet 
above riverbed and be 3,500 feet long. Reservoir 
modification, a unit of comprehensive plan for flood 
control and other purposes of Delaware River Basin, will 
have a reservoir capacity of 181,000 acre-feet spillway 
crest level with 3,000 acre-feet of inactive storage, 
70,000 acre-feet for water supply and recreation and 
108,000 acre-feet for flood control. Estimated Federal 
cost of new work (October 1988) is $21,200 including 
$108,800 required non-Federal reimbursement for costs 
allocated to water supply storage during life of project 
after use of this storage is initiated. Project as 
authorized under the 1946 Flood Control Act was completed 
June 1961. Settlement for lands was completed 
October 1962. The advance engineering and design for 
the modified project is completed. (See Table 3-A at end 
of chapter for total costs for existing project to Sept. 
30,1992.) 
Local cooperation: None required under 1946 Flood 
Control Act. Under 1962 Flood Control Act, project was 
3-12

PHILADELPHIA, PA DISTRICT 
approved subject to certain requirements by local interests, 
as defined in House Document 522 cited above. The 
Delaware River Basin Commission expressed its support 
by a resolution dated 23 April 1980 and reiterated 
its sponsorship for the modified project in August 1985, 
October 1985, and July 1988. 
Operations during fiscal year: Maintenance, contract: 
Work included USGS Stream Gage repair, bridge 
inspection, rehabilitation operations building, repair 
stop logs, surveys, computer emergency maintenance, 
repair access road, NOAA Weather Service, and installation 
of water control device. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir, instrumentation and surveillance 
of reservoir, repair access road, periodic 
inspection, leak detection device, USGS Cooperative 
Stream Gaging, and stair installation. There was also, 
rehabilitation of operations building, reservoir regulation 
data collection, water quality testing and 
monitoring, engineering and design, and supervision 
and administration. 
24. GENERAL EDGAR JADWIN DAM AND 
RESERVOIR, PA 
Location: In Dyberry Creek valley in central part of 
Wayne County, PA, between borough of Honesdale and 
village of Tanners Falls. Dam is about 3 miles above 
confluence of Dyberry Creek and Lackawaxen River in 
Honesdale and 29 miles above confluence of Lackawaxen 
and Delaware Rivers. (See Geological Survey 
Quadrangle Sheet, Honesdale, PA) 
Existing project: A single-purpose flood control 
reservoir with a capacity of 24,500 acre-feet formed by 
an earth embankment, about 1,225 feet long at crest and 
rising 109 feet above creek bed. It also has a tunnel with 
intake structure and a chute-type spillway with a stilling 
basin in left abutment. Reservoir controls runoff 
from a drainage area of 65 square miles which is 91 
percent of watershed of Dyberry Creek and 39 percent of 
Lackawaxen River watershed above Honesdale, PA. 
Construction of project was authorized by 1948 Flood 
Control Act (H.Doc. 113, 80th Cong., 1st Sess.). Project 
completed in June 1960. (See Table 3-A at end of chapter 
for total costs for existing project to Sept. 30,1992.) 
Local cooperation: Assurances of Compliance with 
requirements of local cooperation were accepted July 30, 
1956. For details see page 251, Annual Report for 1962. 
Operations during fiscal year: Maintenance, contract: 
Work included surveys, management planning, 
USGS Stream Gaging, and NOAA Weather Service. 
Maintenance, hired labor: Work included operation 
and maintenance of the reservoir, instrumentation and 
surveillance, repair guard rail, survey monitoring, engineering 
and design, and supervision and 
administration. 
25. GREAT EGG HARBOR INLET & PECK 
BEACH, NJ 
Location: The project is located in Cape May and 
Atlantic Counties, New Jersey. Great Egg Harbor Inlet, 
an unimproved inlet, is about 1.1 miles wide at its 
narrowest point and provides a tidal connection between 
the Atlantic Ocean, Great Egg Harbor Bay, the New 
Jersey Intercoastal Waterway, and Great Egg Harbor 
River. Peck Beach is occupied in its entirety by the City 
of Ocean City and extends from Great Egg Harbor Inlet 
southward to Corson Inlet. The ocean frontage is about 
eight miles in length. 
Existing project: The recommended plan consists of 
providing initial beachfill, with subsequent periodic 
nourishment, with a minimum berm width of 100 feet at 
an elevation of 8 feet above mean low water. The beachfill 
will extend from Surf Road southwest to 34th Street 
with a 1000 foot taper south of 34th Street. This plan 
will require the initial placement of 4,118,000 cubic 
yards of material and subsequent periodic nourishment 
of approximately 1,072,000 cubic yards every three 
years. The material for the initial construction, and 
periodic nourishment will be taken from the ebb shoal 
area located approximately 5,000 feet offshore of the 
Great Egg Harbor Inlet. Additionally, the construction 
of the project will require the extension of 38 storm drain 
pipes. All work is programmed. Estimated cost for new 
work (October 1990) Federal share is $430,000,000 and 
non-Federal is $232,000,000. (See Table 3-A at end of 
chapter for total cost for existing project to Sept. 
30,1992.) 
Local Cooperation: Federal participation in the 
proposed project is recommended and contingent on the 
local sponsor signing the Local Cooperation Agreement 
which identifies the required items of cooperation. In a 
letter dated 28 September 1990, the State of New Jersey 
identified a funding source for their costs and indicated 
that they were prepared to proceed with the final 
negotiations to sign the Local Cooperation Agreement as 
required by Section 221 of the Flood Control Act of 1970 
(Public Law 91-611, 42 U.S.C. 196d-5b) and by the 
Water Resource Development ACT of 1986 (Public Law 
99-662).The Local Cooperation agreement was executed 
in September 1991. 
Operations during fiscal year: Maintenance, contract: 
Work included Phase I of construction. There was 
dredging by Bean Dredging Company/Weeks Marine 
Incorporated from October 30, 1991 to September 30, 
1992 removing 2,617,666 cubic yards of material at a 
total cost of $10,914,910. 
New work, hired labor: Work included surveys, 
preparation work, engineering and design, plans and 
specifications. 
3-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
26. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
To ascertain whether local interests were maintaining 
and operating completed projects as 
tions were made as follows: 
PROJECT INSPECTION 
Lehigh River at Allentown, PA 
Lehigh River at Bethlehem, PA 
Delaware River at East Branch, NY 
Rancocas Creek at Mount Holly, NJ 
Chester River at Chester, PA 
required, inspec- 
DATES 
April 8, 1992 
October 15, 1991 
-April 7, 1992 
April 20, 1992 
July 31, 1992 
August 28, 1992 
Beach Erosion & Hurricane Protection 
Cape May to Barnegat, NJ 9-11 October 1991 
Local interests are satisfactorily maintaining and 
operating projects in accordance with regulation. Costs 
during the period were $9,125. 
27. INSPECTION OF NON-FEDERAL 
LEVEES 
Inspection of non-federal levees were conducted at the 
following sites: 
Allentown, PA February 27, 1992 
Cheltenham, PA April 30, 1992 
Honesdale, PA April 27, 1992 
Norristown, PA April 30, 1992 
Weissport, PA April 28, 1992 
White Mills, PA April 27, 1992 
28. PROMPTON LAKE, PA. 
Location: In Lackawaxen River Valley in central 
part of Wayne County, PA, between borough of 
Prompton and village of Aldenville. Dam is within corporate 
limits of Prompton, 4 miles upstream from 
Honesdale, PA, and approximately 30 miles above confluence 
of Lackawaxen and Delaware River. (See 
Geological Survey Quadrangle Sheet, Honesdale, PA) 
Existing project: Plan of improvement authorized 
by 1948 Flood Control Act (H. Doc. 113, 80th Cong., 1st 
Sess.) provides for a single-purpose flood control reservoir. 
Modification of project authorized by 1962 Flood 
Control Act (H.Doc 522, 87th Cong., 2d Sess.) provides 
for a multiple-purpose development for water supply 
and recreation in addition to present single-purpose 
flood control project. Plan of improvement requires construction 
of control tower with gates and service bridge, 
placing an impervious blanket on valley walls and floor 
upstream from dam, widening spillway, and clearing 
land and relocating roads in reservoir. Dam, completed 
under 1948 Flood Control Act which will not be modified, 
is 1,230 feet long and rises 140 feet above riverbed. 
Existing spillway, cut into rock of right abutment, will 
be modified and present uncontrolled outlet works discharging 
into a concrete conduit along right bank, and 
will be provided with gates and a control tower. Reservoir 
modification, a unit of comprehensive plan for flood 
control and other purposes of Delaware River basin has 
a capacity of 52,000 acre-feet: 3,500 acre-feet for inactive 
storage, 28,200 acre-feet for water supply and recreation, 
and 20,300 acre-feet for flood control. Estimated 
Federal cost of new work (October 1990) is $47,610,000 
including $44,570,000 required non-Federal reimbursement 
for costs allocated to water supply storage during 
life of project after use of this storage is initiated. Project 
as authorized under the 1948 Flood Control Act was 
completed in November 1960. (For details, see page 358, 
Annual Report for 1963.) Work accomplished under the 
1962 Flood Control Act was preconstruction engineering 
and design. (See table 3-A at end of chapter for total cost 
for existing project to Sept. 30, 1992.) 
Local cooperation: Project modification was approved 
subject to certain requirements by local 
interests, as defined in House Document 522 cited 
above. Assurances of compliance under Flood Control 
Act of 1948 have been met. Delaware River Basin Commission 
on March 18, 1966, gave their view that the need 
for water supply was not urgent at that time. However 
recent studies conducted by DRBC have determined 
that there is now a need for water supply. In August 
1983, DRBC expressed their strong support for the 
project modification. 
Preconstruction engineering and design was initiated 
in 1966 and suspended in 1968 and resumed in 1986. 
Operations during fiscal year: Maintenance, contract: 
Work included USGS Cooperative Stream Gaging, 
repairing of access roads and other road improvements, 
water quality monitoring and testing, surveys, and installation 
of relief well. 
Maintenance, hired labor: Work included operation 
and maintenance of reservoir, instrumentation and surveillance, 
maintenance of relief well, water quality 
monitoring and testing, engineering and design, and supervision 
and administration. 
29. RECONNAISSANCE AND CONDITION 
SURVEYS 
Condition Surveys 
Salem River, NJ 
Mispillion River, DE 
Murderkilll River, DE 
Oystser Creek, NJ 
Date Survey Conducted 
January 6-8 1992 
March 20, 25 & 26 1992 
April 7, 1992 
June 6 & 10 1992 
30. NATIONAL EMERGENCY 
PREPAREDNESS 
The total fiscal year cost for this category amounted 
to $115,500. 
General Investigations 
31. SURVEYS 
Cost for the period were $1,208,430 for navigation 
studies: $217,599 for flood control studies, $622,215 for 
3-14

PHILADELPHIA, PA DISTRICT 
shoreline protection studies, $261,823 for special 33. PRECONSTRUCTION ENGINEERING 
studies: a total of $2,532,748 AND DESIGN 
32. COLLECTION AND STUDY OF BASIC Cost and expenditures during the period $625,968 for 
DATA navigation studies; $257,026 for flood control: a total of 
$882,994. 
Cost and expenditures during the period for flood 
plain information studies were $257,521. 
3-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 3-A COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY89 FY90 FY91 FY92 SEPT. 30,1992 
1. Barnegat Inlet. NJ New Work 
(Regular 
Funds) 
(Contributed 
Funds) 
2. Cedar Creek, NJ 
(Regular 
Funds) 
(Contributed 
Funds) 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
3. Chesapeake & DelawareMaint. 
Canal, St. George's Approp. 
Bridge Replacement Cost 
4. Cold Spring 
Inlet, NJ 
(Regular 
Funds) 
(Contributed 
Funds) 
5. Delaware River 
between Philadelphia, 
PA and 
Trenton, NJ 
(Regular 
Funds) 
(Contributed 
Funds) 
6. Delaware River, 
PA, NJ, AND DE 
Philadelphia 
to the Sea 
(Regular 
Funds) 
7. Delaware River 
Vincinity of Camden 
(Regular 
Funds) 
(Contributed 
Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
7,025,000 
8,449,126 
734,000 
727,851 
4,550,000 
3,523,181 
6,052,000 
7,018,368 
984,798 
979,610 
4,175,000 
4,721,899 
4,344,000 3,236,000 
2,938,806 6,718,919 
- 727,000 
- 721,945 
1,400,000 1,500,000 
516,571 2,985,298 
287,200 
285,095 
35,100 
35,100 
26,000 
25,643 
- 7,000,000 14,000,000 
- 6,999,999 13,979,822 
173,000 1,028,344 469,800 563,000 
178,547 1,024,244 474,236 561,463 
1,757,000 469,630 472,547 612,000 
1,766,834 470,428 472,198 611,586 
13,316,400 11,341,749 
13,275,220 11,251,631 
14,122,500 15,369,767 
14,254,971 15,371,772 
94,000 3,930,000 
988 3,364,363 
1,648 - 1,720,000 
- 1,145,122 
31,083,849 
31,083,379 
14,300,933 
14,280,291 
13,917,000 
13,892,847 
256,100 
256,100 
313,200 
310,738 
35,100 
35,100 
21,000,000 
20,979,821 
879,275 
879,275 
5,379,651 
5,378,107 
1,134,346 
1,134,346 
150,000 10 
150,000 10 
72,147,800 o 
72,147,800 
41,143,037 
4 
41,142,538 4 
15,000 
15,000 
57,879,872 5 
57,879,872 5 
404,894,568 19 
404,865,029 19 
508,324 
508,324 
5,816,906 1 
5,362,2181 
362,962 
362,799 
2,705,000 
1,940,078 
3-16

PHILADELPHIA, PA DISTRICT 
TABLE 3-A (Contined) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY89 FY90 FY91 FY92 SEPT. 30,1992 
8. Indian River 
Inlet and Bay, DE 
(Regular 
Funds) 
(Contributed 
Funds) 
Inland Waterway 
from Delaware River 
to Chesapeake Bay, 
DE, and MD 
(Regular 
Funds) 
10. Inland Waterway, 
Rehoboth Bay to 
Delaware Bay, DE 
and MD (Regular 
Funds) 
(Contributed 
Funds) 
11. Mispillion River 28 
(Regular 
Funds) 
12. Murderkill 
River, DE 
(Regular 
Funds) 
13. New Jersey 
Intracoastal 
Waterway 
(Regular 
Funds) 
(Contributed 
Funds) 
14. Salem River, NJ 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
23,000 103,245 475,875 79,000 
33,804 103,045 475,539 78,624 
6,566,500 
6,527,440 
576,000 
578,316 
11,003,107 
11,049,585 
3,343,031 
3,364,748 
9,671,000 
9,641,060 
3,933,000 
3,918,075 
8,913,000 
8,809,414 
(278,151) 
(265,000) 
511,210 18 
511,210 18 
3,939,043 
3,937,698 
1,323,775 
1,323,775 
210,000 
210,000 
132,535,5918 
132,532,598 
227,916,365 9 
227,738,465 9 
17,376,718 
17,364,106 
561,514 
561,514 
43,400 309,880 
44,600 303,428 
12,000 86,000 
12,860 87,828 
2,320,258 
2,316,394 
60,000 
60,000 
197,000 
196,938 
- 100,000 176,000 
- 97,543 151,782 
738,83926 
738,839 26 
2,147,807 27 
2,120,132 27 
37,630 
37,630 
335,100 21,781 328,756 40,000 
335,016 20,082 329,031 33,052 
1,648,000 3,060,445 2,438,000 3,196,000 
1,643,711 3,062,892 2,425,386 3,185,888 
- 274,169 390,000 
- 275,000 389,000 
2,033,114 
2,026,166 
71,549 1 
71,549 
38,206,316 12 
38,178,743 12 
1,196,581 
1,196,581 
99,000 
99,000 
107,634 2 
107,634 2 
2,767,173 6 
2,767,133 6 
3-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 3-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY89 FY90 FY91 FY92 SEPT.30,1991 
(Contributed 
Funds) 
15. Schuylkill 
River, PA 
(Regular 
Funds) 
16. Wilmington 
Harbor, DE 
(Regular 
Funds) 
(Contributed 
Funds) 
17. Cape May Inlet 
to Lower Twp., NJ 
(Regular 
Funds) 
(Contributed 
Funds) 
18. Beltzville 
Lake, PA 
(Regular 
Funds) 
19. Blue Marsh 
Lake, PA 
(Regular 
Funds) 
20. Delaware Coast 
Protection 
(Regular 
Funds) 
(Contributed 
Funds) 
23. Francis E. 
Walter Dam, PA 
(Regular 
Funds) 
24. General Edgar 
Jadwin Dam and 
Reservoir, PA 
(Regular 
Funds) 
New Work 
Approp. 
Cost 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
NewWork 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
51,825 
51,825 
141,000 1,351,520 424,536 965,000 
140,940 1,345,895 432,769 961,697 
5,585,800 4,824,340 2,204,920 2,611,000 
5,613,926 4,866,118 2,188,084 2,610,850 
4,759,000 
3,502,390 
200,000 
58,993 
2,213,000 
1,282,829 
1,335,300 
146,297 
2,648,000 
4,014,549 
839,258 
1,965,786 
136,785 
107,986 
406,500 562,914 597,000 686,000 
427,026 519,341 629,371 676,836 
11,874 
1,442,500 
1,429,509 
1,100,000 
920,187 
974 296 
1,315,772 1,872,000 
1,355,899 1,863,945 
- 230,000 
545,089 210,274 
- 30,000 
- 30,000 
900,000 
712,986 
549,000 
546,206 
135,427 
570,928 
585,470 
14,008 
(47,000) 
4,625 
693,000 
682,545 
1,053 
2,093,800 
2,050,013 
165,000 
96,789 
4,339 
909 
1,448,000 
1,450,336 
145,000 129,000 228,000 259,000 
151,308 114,381 227,559 235,652 
3,334,00713 
3,334,007 13 
30,007,045 
30,003,742 
1,954,725 14,7 
1,954,725 14,7 
74,944,725 
74,914,300 
60,00017 
60,000 17 
9,219,176 
9,355,911* 
2,174,758 
2,279,062 
22,931,831 
22,931,831 
8,846,089 
8,823,842 
63,180,300 
63,180,299 
15,700,594 
15,626,248 
4,498,953 20 
3,991,89820 
215,350 
215,350 
1,268,67121 
1,259,00221 
12,449,68215 
12,352,75315 
9,179,949 
9,167,573 
4,073,105 
4,073,105 
2,658,064 
2,601,308 
3-18

PHILADELPIIA, PA DISTRICT 
TABLE 3-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Projects Funding FY89 FY90 FY91 FY92 SEPT.30,1995 
25. Great Egg Harbor New Work 
Inlet & Peck Approp. - 159,000 750,000 8,317,000 9,226,00( 
Beach, NJ Cost - 140,600 451,994 6,352,622 6,945,21( 
(Regular 
Funds) 
(Contributed New Work 
Funds) Approp. - - 1,500,000 6,000,000 7,500,00( 
Cost - - - 4,978,243 4,978,24 
31. Prompton Lake New Work 
Approp. - - - - 4,609,48 
(Regular Cost - - - - 4,609,48& 
Funds) Maint. 
Approp. 506,700 537,779 703,000 730,000 6,504,64: 
Cost 497,921 541,355 712,166 714,452 6,488,98& 
*Total adjusted to correct discrepancies in prior years. 
1. Includes $1,950,906 for 30 and 37 foot projects. 
2. Includes $55,809 for new work funds expended on previous project. 
3. Includes $2,489,173 for new work for previous projects, 
$105,000 for preauthorization studies and minus $142,015 
adjustment (new work) toDelaware River, Philadelphia to Sea 
project from this project underl954 modification. 
4. Includes $552,720 for maintenance for previous projects, 
and $685,000Jobs Bill Funds. 
5. Excludes $12,976,054 for new work for previous projects 
and $142,015 adjustment from Delaware River, Philadelphia 
to Trenton, NJ under 1954 modification. 
6. Includes $1,285 for reconnaissance and condition 
surveys in FY 1957, $1,792 Operations and Maintenance 
cost incurred for preperation of environmental impact 
statement, and $48,000 expended for maintenance on 
previous projects. 
7. Excludes $412,400 spent for Continueing Authority 
project. 
8. Includes $10,709,755 for new work for previous projects. 
9. Includes $6,903,748 for maintenance for previous projects, 
and $9,500 Job Bill Funds. 
10. Includes $50,000 Navy Department Funds. 
11. Excludes $1,824,940 Navy Department Funds. 
12. Excludes $286,953 Navy Department Funds expended for 
maintenance. 
13. Includes $525,000 for previous projects. 
14. Includes $402,121 for new work for previous project, and 
$206,177 emergency relief funds. 
15. Includes $40,000 appropriated and $61,551 expended under 
Code 710 Recreation Facilities. 
16. Includes 63,000 appropriated and $61,551 expended under 
Code 710Recreation Facilities, excluded $23,600 
preauthorization studies under 1948 modification. 
17. Excludes $213,336 spent on Continuing Authority project. 
18. Excluded $10,000 for previous projects. 
19. Includes $1,025,409 for maintenance of previous projects, and 
$8,000 Jobs Bill funds. 
20. Includes $704,000 AE&D. 
21. Excludes $85,000 cash and $130,000 (services) furnished 
during preconstruction planning. 
22. Includes $39,000 for new work for previous projects. 
23. Includes $2,054 for maintenance for previous projects. 
24. Includes $555,600 for previous project. 
25. 10 & 12 foot anchorages are considered deauthorized. 
26. Includes $148,798 for new work on previous projects. 
27. Includes $61,172 for maintenance on previouse projects. 
28. 9 foot turning basin is considered inactive. 
3-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 3-B AUTHORIZING LEGISLATION 
Acts Work Authorized Dcurnents 
Aug 30, 1935 
Aug 26, 1937 
July 24, 1946 
July 2, 1985 
Dec 10, 1979 
Oct 27, 1990 
Mar 2, 1907 
Mar 2, 1945 
July 3, 1930 
Aug 30, 1935 
Aug 30, 19352 
Aug 26,1937 
July 24, 1946 
Sept 3, 1954 
June 25, 1910 
BARNEGAT INLET, NJ (See Section 1 of Text) 
An 8-foot depth through inlet to Oyster Creek 
Channel across inner bar, 10-foot depth through 
outer bar and for jetties. 
A channel of suitable hydraulic characteristics from 
gorge to Oyster Creek Channel, and thence to deep 
water in bay. 
Maintenance dredging of channel to connect main inlet 
channel with Barnegat City Harbor. 
Construction of a parallel, 4270 foot rubble mound 
south jetty and dredging a channel 10 feet deep, 300 
feet wide, and 11,300 feet long. 
CEDAR CREEK, NJ (See section 2 of Text) 
Creek ranges in depth from 13 feet at the Route 36 
bridges to less than 5 feet at several locations. 
Channel with varies from 75 feet to 250 feet. 
CHESAPEAKE AND DELAWARE CANAL 
ST. GEORGES BRIDGE REPLACEMENT, DE 
(See Section 3 of Text) 
The replacement of the U.S. Route 13 
bridge near St. Georges, DE, and the state may be 
reimbursed if it carries out the work 
COLD SPRING INLET, NJ (See Section 4 of Text) 
An inlet channel 25 feet deep and jetties. 
A 20-foot channel to deep water in harbor 
DELAWARE RIVER BETWEEN PHILADELPHIA, 
PA AND TRENTON, NJ (See Section 5 of Text) 
A channel 28 feet deep, 300 feet wide between 
Allegheny Ave., Philadelphia, PA and Delair Bridge 
Channel 25 feet deep from Delair Bridge to Trenton, 
NJ, and maintenance of 12-foot channel from upper 
end of 25-foot project to Penn Central R.R. Bridge 
at Ferry St., Trenton. 
Auxiliary channel, 20 feet deep east of Burlington 
Island. 
A cross channel 8 feet deep, opposite Delanco, NJ 
Anchorage at mouth of Biles Creek 
A channel 40 feet deep and 400 feet wide between 
Allegheny Ave., Philadelphia, PA, and upstream end 
of Newbold Island, thence 35 feet deep to Trenton 
Marine Terminal and turning basin to 800 feet wide. 
Relocate channel at railroad bridge at Delair and 
suitably reconstruct bridge. Construct necessary 
bank protection works; and eliminate authorized 
anchorage near mouth of Biles Creek, PA 
DELAWARE RIVER, PA, NJ, AND DE, PHILADELPHIA 
TO THE SEA (See Section 6 of Text) 
Channel 35 feet deep from Allegheny Ave., 
Philadelphia, PA to Delaware Bay. 
Rivers and Harbors 
Committee Doc. 19, 
73d Con.,2d sess. 
Rivers and Harbors 
Committee Doc. 85 
74th Con.,2d sess. 
H. Doc.358,79th Cong 
2d sess. 
H. Doc.236,99th Cong 
2d sess. 
River and Harbor Act 
of 1960 
WRDA 1990 
H. Doc.388,59th Cong 
2nd sess. 
H. Doc.262,77th Cong 
1st sess. 
Rivers and Harbors 
Committee Doc. 3, 
71st Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 11, 
73d Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 66, 
74th Cong., 1st sess 
Rivers and Harbors 
Committee Doc. 90, 
74th Cong.,2d sess. 
H. Doc. 679, 79th 
Cong., 2d sess. 
H. Doc. 358, 83d 
Cong., 2d sess. 
H. Doc. 733, 61st 
Cong, 2d sess. 
3-20

PHILADELPHIA, PA DISTRICT 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
Aug 30, 19353 
June 20, 19384 
Mar 2, 19455 
Mar 2, 19455 
Mar 2, 19455 
Sept. 3, 1954 
July 3, 1958 
March 2, 1919 
July 3, 1930 
March 2, 1945 
Oct 20, 1988 
Aug 26, 1937 
Mar 2, 1945 
Aug 30, 1935 
Aug 7, 1939 
Anchorages 35 feet deep at Port Richmond and Mantua 
Creek, a 30 foot anchorage at Gloucester, NJ and 
extend 1,000 foot channel in Philadelphia Harbor to 
Horseshoe Bend. 
An anchorage 35 feet deep at Marcus Hook, PA 
A channel 37 feet deep from Philadelphia - Camden 
Bridge to Navy Yard, thence 40 feet deep to deep 
water in Delaware Bay. 
A 37-foot depth channel from Allegheny Ave., 
Philadelphia, PA to Philadelphia-Camden Bridge 
A 37-foot depth in an enlargement of anchorage near 
Mantua Creek and Marcus Hook. 
Maintain enlarged channel opposite Philadelphia 
Navy Yard. 
A channel from Allegheny Ave., to Naval Base 40 feet 
deep, 400 feet wide along west side of channel 
through Philadelphia Harbor and 500 feet wide through 
Horseshoe Bend. 
Anchorages at Reedy Point, Deepwater Point, Marcus 
Hook, and Mantua Creek 40 feet deep and 2,300 feet 
wide with mean lengths of 8,000, 5,200,13,650 and 
11,500 feet respectively. 
DELAWARE RIVER VICINITY OF CAMDEN, NJ 
(See Section 7 of Text) 
A depth of 30 feet from Newton Creek 
to Kaighn Point, thence 18 feet to Cooper Point. 
Extending the 30-foot depth upstream to Berkely Street terminal 
A depth of 37 feet in front of the Camden Marine terminal 
A depth of 40 feet in front of the Camden Marine terminal 
INDIAN RIVER INLET AND BAY, DE (See Section 8 of Text) 
A 15-foot inlet channel, steel and stone jetties, 
6 foot channel from end of inlet channel to deep 
water in the bay and authority to modify interior 
inlet channel. 
A 9-foot channel from inlet to Old Landing, including 
basin, and 4-foot channel to highway bridge at 
Millsboro. 
INLAND WATERWAY FROM DELAWARE RIVER 
TO CHESAPEAKE BAY, DE & MD (See Section 9 of Text) 
A sea level channel 27 feet deep, 250 feet wide from 
Delaware River to Elk River and 400 feet wide down 
Elk River and Chesapeake Bay to deep water at or 
near Pooles Island; alter existing bridges over 
canal; enlarge Delaware City Branch Channel to 8 
feet deep and 50 feet wide, with a basin same depth 
and revetment of both banks east of Fifth Street; 
enlarge anchorage and mooring basin in Back Creek to 
400 feet wide, 1,000 feet long and 12 feet deep; 
extend jetties at Reedy Point; and construct bulkheads. 
Construct a 4-lane high-level fixed highway bridge 
at or near St. Georges. 
H. Doc. 304, 71st Cong. 
2d sess. 
Rivers and Harbors 
Committee Doc.5, 73d 
Cong., 1st sess. 
S. Doc. 159, 75th Cong. 
3d sess. 
H. Doc. 580,76th Cong. 
1st sess. 1 
H. Doc. 340, 77th Cong. 
1st sess. 1 
Specified in Act. 
H. Doc. 358, 83rd Cong. 
2d sess. 
H. Doc. 185, 85th Cong. 
1st sess. 
74th Cong., 1st sess. 1 
H. Doc. 1120, 63d 
Cong., 2d sess. 
H. Doc. 111, 70th Cong., 
1st sess. 
H. Doc. 353, 77th Cong., 
1st sess. 
WRDA 1988 
Rivers and Harbors 
Committee Doc. 41, 
75th Cong. 1st sess. 
H. Doc. 330,76th 
Cong., 1st sess. 
H. Doc. 201, 72d Cong., 
1st sess. and Rivers 
and Harbors 
Committee Docs. 18 
and 24, 736 Cong., 
2d sess. 
Public Law 310, 76th 
Cong., 1st sess. 
3-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts WorkAuthorized Documents 
Sept 3, 1954 
Aug 30, 1935 
July 25, 1912 
Aug 30, 1935 
Mar 2, 1945 
March 2, 1912 
August 26, 1937 
September 3, 1954 
July 13, 1982 
July 1, 1945 
Nov 17, 1986 
July 3, 1930 
Aug 30, 1935 
Nov 17, 1986 
Aug 8, 1917 
July 3, 1930 
A channel 35 feet deep and 450 feet wide from 
Delaware River through Elk River and Chesapeake Bay. 
For an 8-foot depth and width increased to 150 feet 
in Delaware Bay. 
INLAND WATERWAY, REHOBOTH BAY TO DELAWARE BAY, DE 
(See Section 10 of text) 
For a 6-foot depth canal to connect Rehoboth Bay and 
Delaware Bay. 
For a 6-foot depth entrance near Lewes, for jetties, 
for widening the canal from Broadkill River to 
Lewes and basin. 
For a 10-foot depth from Delaware Bay to Lewes and 
in basin, and for extending jetties. 
MISPILLION RIVER, DE (See Section 11 of Text) 
A 6-foot depth and extention of south. 
Extention of north jetty. 
A channel 9 feet deep, 80 feet wide from like depth in Delaware Bay to 
the landward end of the jetties and thence 60 feet wide to Milford, including 
3 cutoffs, with a turning basin at Milford. 
MURDERKILL RIVER, DE (See Section 12 of Text) 
A channel 7 feet deep at low water from Frederica 
to the 7 foot curve in Delaware Bay, 80 feet wide 
down to the mouth, and 150 feet wide at bottom and 
250 feet wide at top from the mouth to the 7 foot 
curve in the bay. Embankment of dredged material 
on each side to a height of at least 2 feet above 
high spring tides. 
NEW JERSEY INTRACOASTAL WATERWAY 
(See Section 13 of Text) 
A channel 12 feet deep at mean low water and 
generally 100 feet wide, extending from the Atlantic 
Ocean at Manasquan Inlet, NJ to Delaware Bay above 
Cape May, NJ. Construction of a canal of similar 
dimensions from Cape May Harbor to Delaware Bay via 
the New England Creek basin, with adequate jetties at 
the Delaware Bay entrance. 
To increase the depth of the 2,000, foot reach of the 
Waterway in Cape May County to 15 feet. 
SALEM RIVER, NJ (See Section 14 of Text) 
A channel of 10-foot depth from Delaware River Masters Sand Plant 
Extention of project to Clements Bridge. 
A channel of 20-foot depth 
SCHCUYLKILL RIVER, PA (See Section 15 of Text) 
Depths of 35 feet from mouth to Girard Point 
thence 30 feet, 26, and 22 feet to University 
Avenue Bridge, Philadelphia. 
A depth of 30 feet instead of 35 feet between the 
S. Doc. 123, 83d Cong. 
2d sess. 
H.Doc.275,73d Cong. 
2d sess. 1 . 
H. Doc. 823, 60th Cong., 
1st sess. and Rivers 
and Harbors 
Committee Doc. 51, 
61st Cong., 3d sess. 
Rivers and Harbors 
Committee Doc. 56, 
75th Cong., 2st sess. 
H. Doc. 344, 77th Cong., 
1st sess. 
H. Doc. 678, 62d Cong. 
2d sess. 1 
Rivers and Harbor 
Comm., Doc. 83 
S.Doc 229, 81st 
Cong., 2d sess. 1 1 
H.Ex.Doc. 21, 52d Cong., 
1st Sess.)(See page 981 
Annual Report of 1892.) 
H.Doc. 133,76th Cong., 
1st Sess.) 
Rivers and Harbors 
Committee Doc.525 
79th Cong., 2d sess. 
WRDA of 1986 
H. Doc. 217, 70th Cong. 
1st Sess. 
Rivers and Harbors Comm. 
Doc. 15 73d Cong., 
1st sess. 1 
WRDA of 198611 
H. Doc. 1270, 64th 
Cong., 1st sess. 
Rivers and Harbors 
3-22

PHILADELPHIA, PA DISTRICT 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts WorkAuthorized Documents 
July 24, 1946 
Committee Doc. 40, 
71st Cong., 2d sess 1 
H. Doc. 699, 79th Cong., 
2d sess 
mouth and the conditional restoration and 
maintenance of the channel below Passyunk Ave., 
by the United States. 
A depth of 33 feet from the channel in Delaware 
River to Passyunk Ave., restoration of the project 
channel dimensions between Passyunk Ave., and 
University Ave., and full maintenance of the entire 
project. 
WILMINGTON HARBOR, DE (See Section 16 of Text) 
Depths of 21,10 and 7 feet and jetties. 
Purchase or construct a dredge and auxiliaries 
including a wharf and depot, and maintenance of 
project. 
Entrance channel and basin with 25-foot depth and 
construction by local interests of new south jetty. 
A 30-foot depth between Delaware River and Lobdell 
Canal and modification or removal of a portion of 
north jetty. 
Completion of new south jetty by the United States 
subject to provision that city of Wilmington 
reimburse the United States for cost, without 
interest, of any part of structure that may 
subsequently be occupied and utilized for city 
activities. 
Permit temporary occupancy by city of Wilmington 
of any part of south jetty for city activities 
under revocable license, provided occupied portion 
ofjetty is properly maintained without expense to 
the United States. 
A 35-foot depth between Delaware River ship channel 
and Lobdell Canal including turning basin of same 
depth, opposite Wilmington Marine Terminal, 200 feet 
wide, 2,900 feet long on north side of channel, and 
2,000 feet long on north side of basin. 
CAPE MAY INLET TO LOWER TOWNSHIP, NJ 
(See Section 17 of Text) 
Consists of beach fill; dune fill; new groins; maintenance 
of existing groins; rehabilitation of an 
existing seawall; and a breakwater with weir and 
deposition basin at Cape May Inlet. 
Project may be constructed separately or in combination 
with any other feature of the project. 
BELTZVILLE LAKE, PA (See Section 18 of Text) 
Provides for multiple-purpose development for water 
supply flood control and recreation 
BLUE MARSH LAKE, PA (See Section 19 of Text) 
Provides for multiple purpose development for water 
supply, flood, control, and recreation. Site is 
located on Tulpehocken Creek about 1 1/2 miles upstream 
from its confluence with Plum Creek and about 
six miles northwest of Reading, PA. 
Rivers & Harbors 
Act of 1968 
WRDA of 1986 
H. Doc.522, 87th Cong., 
2d sess. 
H. Doc. 522, 87th Cong., 
2d sess. 
3-23 
H. Doc. 66, 54th Cong., 
1st sess. 
Annual Report, 1897 
p. 12501 
H. Doc. 359, 62d Cong., 
2nd sess. 
H. Doc. 114, 67th Cong., 
1st sess. and S. 
Committee Print, 68th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 20, 
71st Cong. 2d sess. 
Rivers and Harbors 
Committee Doc. 32 
73d Cong., 2d sess. 
H. Doc. 658, 76th Cong., 
3rd sess. 
H. Doc. 88, 86th Cong., 
2d sess. 
June 3,1896 
July 25,1912 
Sep 22,1922 
July 3,1930 
Aug 30, 19358 
Oct 17, 1940 
July 14, 1960 
Nov 17, 1986

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 3-B (continued) AUTHORIZING LEGISLATION 
Acts WorkAuthorized Documents 
DELAWARE COAST PROTECTION (See Section 20 of Text) 
Provides for Federal participation in the cost H. Doc.90, 90th Cong 
of restoration and subsequent periodic nourishment, 2nd sess. 
not to exceed 10 years, of the shore from Rehoboth 
Beach to Indian River Inlet. 
Nov 17, 1986 Project is modified to authorized the construction WRDA of 1986 
of sand bypass facilities and stone revetment erosion Sec. 869 
control measures at Indian River Inlet, DE. * 
FRANCIS E. WALTER DAM, PA (See Section 23 of Text) 
Provided for a single-purpose flood control reservoir H. Doc 587, 79th Cong., 
2d sess. 
Provides for a multiple-purpose development for H. Doc 522,87th Cong., 
water supply and recreation. 2d sess. 
GENERAL EDGAR JADWIN DAM AND RESERVOIR, PA 
(See Section 24 of Text) 
A single-purpose flood control reservoir with a H. Doc 113, 80th Cong., 
capacity of 24,500 acre-feet formed by an earth 1st sess. 
embankment. 
GREAT EGG HARBOR INLET & PECK BEACH, NJ 
(See Section 25 of Text) 
Nov 17, 1986 Project may be constructed separately or in River and Harbor Act of 
combination with any other feature of the project. 1965. WRDA of 1986. 
Consists of providing initial beachfill, with 
subsequent periodic nourishment, with a minimum 
berm width of 100 feet at an elevation of 8 feet 
above mean low water. 
PROMPTON LAKE, PA (See Section 28 of Text) 
Provides for a single-purpose flood control reservoir. H. Doc. 113, 80th Cong., 
1st sess. 
Provides for multiple-purpose development for water H. Doc 522, 87th Cong., 
supply and recreation in addition to present single- 2d sess. 
purpose flood control project. 
1. Contains latest published maps. 
2. Also Public Works AdministrationSeptember 6, 1933, and 
Emergency Relief Administration, May 28, 1935 
3. Also Public Works Administration 
4. Channel 37 feet deep and 600 feet wide from Naval Base 
to Philadelphia-Camden Bridge, deferred for restudy. 
5. Channel 37 feet deep and 600 feet wide fromPhiladelphia-Camden 
Bridge to Allegheny Ave. deferred for restudy. 
6. Extension ofjetties considered to be active. 
7. The 10 and 12 foot anchorages are considered inactive. 
8. Also May 28,1935, under Emergency Relief Administration. 
9. Deauthorized the remaining portion of the project. 
10. The 10 and 12 foot anchorages are considered inactive. 
11. Contains latest published maps. 
3-24

PHILADELPHIA, PA DISTRICT 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Active Projects Status Report For Construction Maintenance 
Absecon Creek, NJ 
Absecon Inlet, NJ 
Alloway Creek, NJ 
Appoquinimink River,DE 
Big Timber Creek, NJ 
Broadkill River, DE 
Cooper River, NJ2 1 
Delaware River, Pennsville, NJ 
Double Creek, NJ' 
Harbor of Refuge, 
Inland Waterway from Chincoteague 
Bay to Delaware Bay 
Little River, DE 
Manasquan River, NJ 2 5 
Mantua Creek, NJ 
Maurice River, NJ 
Delaware Bay to Millville 
Millville fixed bridge to upper 
end of project 
** Neshaminy State Park Harbor, PA 
Oldmans Creek, NJ 
** Pepper Creek, DE 
Raccoon Creek, NJ 
St. Jones River, DE 
Delaware Bay to Lebanon1 '1 1 
Jetties and entrance at mouth 
Schuylkill River above Fairmount 
Dam, PA1 
Smyrna River, DE 
Delaware River t Wharf at 
Smyrna Landing" 
Wharf at Smyrna Landing to 
fixed bridge. 
Toms River, NJ 
Channel 5 feet deep 
Channel 12 feet deep � 
Tuckerton Creek, NJ 
Waterway from Indian River Inlet 
to Rehoboth Bay, DE 
Woodbury Creek, NJ' 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
SEE TABLE 3-F 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
COMPLETED 
SEE TABLE 3-F 
COMPLETED 
SEE TABLE 3-F 
COMPLETED 
COMPLETED 
COMPLETED 
1989 
1990 
1989 
1934 
1989 
1976 
1989 
1912 
1912 
1981 
1980 
1991 
1966 
1948 
1968 
1941 
1989 
1981 
1961 
1955 
1949 
1950 
1986 
1991 
1940 
11,935 
534,20918 
21,398 
36,973 
58,665 
68,228 
33,102 
256,624 
7,800 
5,162,23020 
168,41213 
12,016 
8,008,2782224 
169,687 
143,98421 
128,20316 
31,188 
138,09422 
83,66515 
207,102 
4,291,810 
- 
198,844 
10,050 
60,242 
27,09312 
84,186' 
5,98517319 
55,117 
41,270 
71,925 * 
243,641 
396,528* 
5 
1,169,01421 
98,36014 
288,310 
3,615,70023 
339,340 
161,913 
54,601 
32,125 
38,988 * 
341,734 
66,093 
5 
197,327 
33,311 
638,860 
328,634 
56,474 
3-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 3-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Active Projects Status Report For Construction Maintenance 
Alloway Creek INACTIVE 1931 21,398 35,761 
Aquatic Plant Control INACTIVE 1975 87,594 - 
Dennis Creek, NJ 1 INACTIVE 1897 4,701 - 
Goshen Creek, NJ1 INACTIVE 1905 15,359 870 
Ice Harbor at Marcus Hook, PA1" 6 INACTIVE 1928 208,964 14,336 
Ice Harbor at New Castle, DE"1,6 INACTIVE 1898 224,704 - 
Leipsic River, DE 1INACTIVE 1931 36,956 32,345 
Little Egg Harbor, NJ "'4 INACTIVE - 15,048 - 
Maurice River, NJ-Channel 8 feet 
deep, Delaware Bay to mouth INACTIVE 1948 - 
For Last 
Full Report Cost to September 30,1992 
See Annual Operation and 
Deferred Projects Status Report For Construction Maintenance 
St. Jones River, DE 1961 - - 
Delaware Bay to Lebanon 1 '10 - 207,102 66,093 
Jetties and new entrance at 
mouth DEFERRED - -- 
1. Completed. 
2. Excludes $50,000 contributed funds expended for new work. 
3. Abandonment recommended in House Doc. 467, 69th Congress, 
1st Sess. 
4. Maintenance assumed by local interests. 
5. Harbor not now required by commerce. 
6. Last appropriation for project was in 1852. No information is at 
hand relative to work done. 
7. Includes $3,000 for new work for previous projects. 
8. Deferred 
9. Includes $54,590 new work and $28,935 maintenance funds 
expended on previous projects. 
10. Includes $55,085 new work and $22,723 maintenance funds 
expended on previous projects. 
11. Includes $2,950 new work funds expended on previous projects. 
12. Entire amount expended on previous projects repealed in 1905. 
13. Excludes $2,000 contributed funds and includes $25,330 for 
maintenance for previous project. 
14. Includes $39,000 for new work on previous projects. 
15. Includes $757 new work funds expended on previous projects. 
16. Excludes $327,957 contributed funds allotted expended for new 
work. 
17. Excludes $38,988 non-Federal funds. 
18.Includes $116,497 for new work on previous projects. 
19.Includes $2,489,173 for maintenance for previous projects. 
20. Includes $2,749,452 for new work for previous projects. 
21. Excludes $1,089 for reconnaissance and condition surveys fiscal 
year 1963. 
22. Includes $39,000 for new work for previous projects. 
23. Includes $2,054 for maintenance for previous projects. 
24. Incluses $555,600 for previous projects. 
25. 10 & 12 foot anchorages are considered deauthorized. 
* Operation and maintenance figure includes cost incurred for preparation of environmental impact statements. 
** Projects authorized by the Chief of Engineers. 
3-26

PHILADELPHIA, PA DISTRICT 
TABLE 3-D 
OTHER AUTHORIZED 
BEACH EROSION CONTROL PROJECTS 
For Last 
Full Report Cost to September 30,1992 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Brigantine Island INACTIVE* - - - 
Corson Inlet and Ludlam Beach, NJ INACTIVE* 1978 314,400 
Hereford Inlet INACTIVE* --- 
Long Beach Island INACTIVE - - 
Townsends Inlet and Seven Mile 
Beach, NJ INACTIVE* - - - 
1. Operation and maintenance required under Public Works expended for extension 
Acceleraion Program for by law to be assumed by local interests. 3. Excludes cost of $1,146,325 to local interests and $272,766 
Extension of five existing groins completed Federal participation expended under extension of five existing 
2. Excludes $58,585 Accelerated Public 11 May 1964. Works funds groins completed 11 May 1964. 
* NO CURRENT YEAR FUNDS. 
OTHER AUTHORIZED 
TABLE 3-E FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allentown, Lehigh River, PA COMPLETED 1961 1,615,581 
Bethlehem, Lehigh River, PA COMPLETED 1966 4,520,995 - 
Mt. Holly, NJ COMPLETED 1946 283,655 -1 
Pottstown, PA ACTIVE 1984 487,366 - 
Hay Creek, Birdsboro, PA INACTIVE 1984 335,299 
Tamaqua, PA ACTIVE 1990 628,4674 - 
1. Maintenance assumed by local interest as required by authorizing 
project. 
2. New project deferred. 
3. $1,316,464 expended for preconstruction planning only. 
4. Transfer from Baltimore District in Fiscal Year 1989. 
3-27

Millville fixedbridge to upper 
end of project 
Maiden Creek Reservoir, PA 
Ocean City, NJ 
Oldmans Creek, NJ3 
Rancocas River, NJ4 
Rehoboth Beach to Indian River 
Inlet, DE 
Smyrna River, DE5 
Wharf at Smyrna Landing to fixed 
bridge. 
Tocks Island, PA,NJ,and NY9 
HD 00-000 
Tocks Island (Relocation of U.S. 
HD 00-000 
Route 209 only) PA9 
Toms River, NJ6 
Channel 12 feet deep 
Trexler Lake, PA 
1963 
1969 
1941 
1942 
1965 
1949 
1979 
$65,106,2600 
1979 
$195,223 
1950 
1981 
17 Nov 86 
PL 99-662 46 Stat. 
918 
HD 184 
918 
2 Nov 79 
Section 12 PL 93-251 
2 Nov 79 
Section 12 PL 93-251 
HD 216 
918 
2 Nov 79 
HD 95-157 
0 000 00 
0 000 00 
2 Nov 79 
Section 12 PL 93-251 
17 Nov 86 
PL 99-66276 Stat. 
1180 
$395,831 
$ 63,313 
$ 57,590 
$326,116 
$396,169 
$ 43,361 
Flood Control Projects 
Lehigh River at Bethlehem, PA7 
1966 
2 Nov 79 
Section 12 
PL 93-251 $4,520,995 
3-28 
I 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 3-F DEAUTHORIZED PROJECTS 
For Last Full Date Federal Contributed 
Report See Annual And Funds Funds 
Navigation Projects Report For Authority Expended Expended 
Appoquinimink River, DE1 1931 3 Oct 78 
HD 95-351 $ 78,243 - 
Aquashicola Reservoir, PA 1963 17 Nov 86 
PL 99-662 46 Stat. 
918 - - 
Atlantic City, NJ 1972 HD 538 
918 $2,083,289 - 
Barnegat Light, NJ 1964 HD 208 
918 $ 70,908 - 
Cape May City, NJ 1961 3 Sep 54 
HD 206 
918 $ 22,9578 - 
Chester River, 17 Nov 86 
Delaware County, PA 1931 PL 99-662 52 Stat. 
323 $ 7,139 - 
Delaware River, Mouth of 5Aug 77 
Neversink 1917 HD94-192 - - 
Long Beach Island, NJ 1964 14 Jul 60 
HD 208 
918 $ 40,665 - 
Maurice River, NJ 1948 Section 12 PL 93-251

PHILADELPHIA, PA DISTRICT 
TABLE 3-F (continued) DEAUTHORIZED PROJECTS 
1. Includes $36,973 new work, and $41,270 for maintenance. 
2. There is no need now for this portion of the project. 
3. Includes $31,188 new work, and $32,125 for maintenance. 
4. Includes $44,500 new work, and $13,090 for maintenance. 
5. Includes $143,759 new work, $55,085 previous project, $174,602 
for maintenance, and $22,723 maintenance, previous project. 
6. Includes $10,050 new work, and $33,311 for maintenance. 
7. Maintenance assumed by local interest. 
8. Excludes $58,585 accelerated Public 11 May 1964. Work funds 
expended for extension. 
9. Includes $3,489,088 for AE&D. 
10. National Parks and Recreation Act of 1978 terminated Corps 
authority to proceed with project. Legislation would be required to 
proceed with the project. 
3-29

BALTIMORE, MD DISTRICT* 
This district comprises the watershed of Susquehanna 
River and its tributaries from headwaters in south 
central New York State through central Pennsylvania to 
its mouth in Chesapeake Bay; watershed of the Potomac 
River and its tributaries from headwaters in Maryland, 
eastern West Virginia, and Northern Virginia to its 
mouth in Chesapeake Bay; District of Columbia; and 
southwestern portion of Delaware. It includes that portion 
of Chesapeake Bay and its tributaries north of Smith 
Point, MD, on western shore of the bay, and includes that 
portion of Maryland between Chesapeake Bay and 
Atlantic Ocean. 
IMPROVEMENTS 
Navigation 
1. Baltimore Harbor and 
Channels, MD and VA ............... 
2. Baltimore Harbor, MD, 
Collection and Removal of Drift ....... 
3. Bonum Creek, VA ..................... 
4. Chester River, MD ................... 
5. Knapps Narrows, MD ................. 
6. Nanticoke River, MD .................. 
7. Ocean City Harbor and Inlet and 
Sinepuxent Bay, MD ................ 
8. Potomac and Anacostia 
Rivers, DC, Collection 
and Removal of Drift ............... 
9. Potomac River-Aquatic 
Plant Control, MD, VA, DC ......... 
10. Potomac River at 
Alexandria, VA ..................... 
11. Potomac River below 
W ashington, DC ................... 
12. Prevention of Obstructions 
and Injurious Deposits, 
Baltimore Harbor, MD ............... 
13. Twitch Cove and 
Big Thorofare, MD ................. 
14. Washington Harbor, DC ............... 
15. Wicomico River, MD .................. 
16. Reconnaissance and Condition Surveys... 
17. Navigation work under special 
authorization ....................... 
Beach Erosion Control 
18. Beach Erosion Control Work 
under special authorization ........... 
19. Atlantic Coast of Maryland ............ 
20. Colonial Beach, MD ................... 
Page 
4-3 
4-4 
4-4 
4-4 
4-5 
4-5 
4-5 
4-6 
Flood Control Page 
21. Anacostia River and 
Tributaries, Flood 
Protection and Navigation 
Improvements, DC & MD ............ 4-9 
22. Cumberland, MD, and Ridgeley, WV ..... 4-10 
23. Isle of Wight Bay, 
Ocean City, MD.................... 4-10 
24. Jennings Randolph Lake, MD and WV... 4-10 
25. Lackawanna River Basin, PA ........... 4-11 
25A. Aylesworth Creek Lake, PA ............ 4-11 
26. Lock Haven, PA ...................... 4-11 
27. Raystown Lake, Raystown Branch, 
Juniata River, PA................... 4-11 
28. Southern New York Flood 
4-6 
28A. 
4-6 28B. 
28C. 
4-7 28D. 
28E. 
28F. 
4-7 28G. 
28H. 
4-7 28I. 
4-7 28J. 
4-8 28K. 
4-8 28L. 
28M. 
4-8 
4-9 
4-9 
Control Projects ...... 
Addison, NY ............ 
Almond Lake, NY ........ 
Arkport Dam, NY ....... 
Avoca, NY............. 
Binghamton, NY ......... 
Canisteo, NY ........... 
Corning, NY ............ 
East Sidney Lake, NY.... 
Elmira, NY ............ 
Hornell, NY............ 
Lisle, NY ............... 
Oxford, NY ............. 
Whitney Point Lake, NY.. 
............ 4-12 
....... . 4-12 
............ 4-12 
....... . 4-12 
............ 4-12 
....... . 4-13 
. 4-13 ....... . 4-13 
... ...... . 4-14 
....... 4-14 
....... 4-14 
....... . 4-15 
............ 4-15 
............ 4-15 
28N. Whitney Point Village, NY............. 
29. Solomon Creek, Ashley 
Borough, Luzerne Co., PA ............ 
30. Solomons Island, Calvert 
County, M D ........................ 
31. Spring Brook Creek, 
Pittston Township, PA ............... 
S4-16 
S4-16 
4-16 
4-16 
4-1 
4-8

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Flood Control (cont'd) Page 
32. Stillwater Lake, Lackawanna 
River, PA .......................... 4-17 
33. Susquehanna River Flood Control 
Projects, NY and PA ................ 4-17 
33A. Cowanesque Lake, PA ................. 4-17 
33B. Tioga-Hammond Lakes, PA ............ 4-18 
34. West Branch of Susquehanna 
River, PA .......................... 4-18 
34A. Alvin R. Bush Dam, PA ............... 4-18 
34B. Curwensville Lake, PA................. 4-18 
34C. Foster Joseph Sayers Dam, PA ......... 4-19 
35. York, Indian Rock Dam, PA............ 4-19 
36. Inspection of Completed Flood 
Control Projects .................... 4-19 
37. Scheduling Flood Control Reservoir 
Operations ......................... 4-19 
38. Flood Control Work under special 
authorization ....................... 4-19 
Water Supply 
39. Washington Aqueduct ................. 4-20 
General Investigations 
40. Surveys ............ ....... ..... 
41. Collection and Study of Basic Data. 
42. Pre-construction Engineering and 
D esign ........................ 
Tables 
Table 4-A Cost and Financial Statement... 
Table 4-B Authorizing Legislation ........ 
Table 4-C Other Authorized 
Navigation Projects.......... 
Table 4-D Other Authorized Beach Erosion 
Control Projects............. 
Table 4-E Other Authorized Flood 
Control Projects............. 
Table 4-F Not Applicable 
Table 4-G Deauthorized Projects........ 
Table 4-H Reconnaissance and 
Condition Surveys ........... 
Table 4-I Inspection of 
Completed Projects .......... 
Page 
..... 4-20 
..... 4-20 
..... 4-20 
... 4-22 
... 4-27 
... 4-32 
... 4-34 
..... 4-35 
..... 4-36 
..... 4-37 
..... 4-38 
4-2

BALTIMORE, MD DISTRICT 
1. BALTIMORE HARBOR AND 
CHANNELS, MD AND VA 
Location. Baltimore Harbor is at the head of the 
navigable portion of Patapsco River about 12 miles 
from Chesapeake Bay. The Patapsco River rises near the 
town of Westminster in Carroll County, MD, and flows 
generally southeast for about 65 miles to enter Chesapeake 
Bay. (See National Ocean Survey Chart 12278.) 
Existing project. 
a. A uniform main channel depth of 50 feet between 
Cape Charles, VA, and Fort McHenry at Baltimore, MD, 
with dimensions as follows: (1) Cape Henry Channel: 50 
feet deep and 1,000 feet wide from the 50-foot depth curve 
in the Atlantic Ocean to that depth in Chesapeake Bay, 
a distance of 3.0 miles; (2) York Spit Channel: 50 feet deep 
and 1,000 feet wide connecting the 50-foot depth curves 
in Chesapeake Bay near York Spit, a distance of 18.4 
miles; (3) Rappahannock Shoal Channel: 50 feet deep and 
1,000 feet wide connecting the 50-foot depth curves in 
the Chesapeake Bay opposite the Rappahannock River, 
a distance of 10.3 miles; and (4) Baltimore Harbor 
Approach Channels: 50 feet deep and generally 800 feet 
wide, widened at the approach and bends, from the 
50-foot depth curve in Chesapeake Bay opposite the 
mouth of the Magothy River to Fort McHenry on the 
Patapsco River, a distance of 20.2 miles. 
b. Branch channels with dimensions as follows: (1) 
Connecting Channel to Chesapeake and Delaware Canal 
Approach Channel: 35 feet deep, 600 feet wide, and 15.6 
miles long from the Cutoff Angle in the main channel to 
the 35-foot depth curves in the natural channel on the 
east side of Chesapeake Bay which is part of the inland 
waterway from Delaware River to Chesapeake Bay. The 
channel includes the Brewerton Extension and Swan 
Point and Tolchester Channels; (2) Curtis Bay: 50 feet 
deep, 600 feet wide, and 2.3 miles long from the main 
channel to and including a turning basin at the head of 
Curtis Bay; (3) Curtis Creek: (a) a channel, 35 feet deep 
and generally 200 feet wide, from the 50-foot channel in 
Curtis Bay to 750 feet downstream of the Pennington 
Avenue Bridge; (b) a channel, 22 feet deep and generally 
200 feet wide, from the 35-foot channel to and along the 
marginal wharf of the Curtis Bay Ordnance Depot; (c) 
an irregular shaped 3-acre basin, with a depth of 18 feet, 
adjacent to the head of the 22-foot channel; (d) a basin, 
15 feet deep and 450 feet wide, from the end of the 22-foot 
channel to the end of the marginal wharf; and (e) a 
channel, 22 feet deep and 200 feet wide, from the 22-foot 
channel south of the Baltimore and Ohio Railroad Bridge 
to the vicinity of Arundel Cove, a distance of 2,800 feet, 
thence 100 feet wide in Arundel Cove for a distance of 
2,100 feet, with an anchorage basin, 700 feet square, adjacent 
to the channel and southwest of the wharf of the 
Coast Guard Depot at Curtis Bay; (4) Middle Branch; 
Ferry Bar East Section: a channel, 42 feet deep and 600 
feet wide, from the main channel at Fort McHenry to 
Ferry Bar, a distance of 1.5 miles; and (5) Northwest 
Branch: Federal maintenance of 39-foot or 35-foot deep 
channels after either depth has been provided by local 
interests: (a) East Channel: a channel, 49 feet deep, 600 
feet wide, and 1.0 mile long with a turning basin at the 
head of the channel from that depth existing at the time 
of construction; and (b) West Channel: a channel, 40 feet 
deep, 600 feet wide, and 1.3 miles long with a turning 
basin at the head of the channel from that depth existing 
at the time of construction. 
c. The following anchorages: (1) Riverview Anchorage 
No. 2: 30 feet deep, 2,400 feet long, and 1,200 feet wide; 
(2) Riverview Anchorage No. 1: 35 feet deep, 4,500 feet 
long, and 1,500 feet wide; and (3) Fort McHenry 
Anchorage: 35 feet deep, 3,500 feet long, and 400 feet 
wide. 
The mean range of tide is 2.8 feet at the Cape Henry 
Channel, 2.3 feet at the York Spit Channel, 1.4 feet at 
the Rappahannock Shoal Channel, 0.8 foot at the 
Craighill Entrance, 0.9 foot in the Cutoff Section, 1.1 feet 
at Fort McHenry, and 1.2 feet at Pooles Island in the 
upper Chesapeake Bay. Depths refer to mean low water. 
Estimated cost for new work is $361,581,000 which includes: 
$8,330,000 for completed work through the River 
and Harbor Act of 1945; $38,411,000 for work completed 
under the River and Harbor Act of 1958 of which 
$33,991,000 is Corps of Engineers, $60,000 is U.S. Coast 
Guard and $4,360,000 is non-Federal; and $314,840,000 
(October 1989 prices) for work authorized by the River 
and Harbor Act of 1970, of which $460,000 is U.S. Coast 
Guard and $314,380,000 is Corps of Engineers and non- 
Federal. 
Local cooperation. Requirements are described in full 
on page 4-3 of Fiscal Year 1982 Annual Report. 
Terminal facilities. The Port of Baltimore has 45 miles 
of waterfront of which 25 miles are industrially developed. 
There are 94 covered and open overseas piers for 
the loading and discharging of 173 ships, providing 84 
general cargo, 65 specialized cargo, and 24 public bulk 
cargo berths. The existing ground storage is equivalent 
to 53,700 railroad cars of cargo. There are 31 public 
general merchandise warehouses, with 4.9 million square 
feet of storage space and 4.7 million cubic feet of cold 
storage space. Eight ship-building, ship repair, and ship 
dismantling yards are available for handling up to 90 
vessels. The two grain elevators in the port have a 
capacity of about 8 million bushels. Latest description 
of terminal facilities is in "Port Series No. 10 (revised 
1991)" on Port of Baltimore, MD, (issued by Board of 
Engineers for Rivers and Harbors). 
Operations and results during fiscal year. New Work, 
Baltimore District: None. 
New Work, Norfolk District: None. 
Maintenance, Baltimore District: Condition surveys of 
the project channels were made. Maintenance dredging, 
by contract, of the Brewerton Channel Eastern Extension 
and Tolchester Channel commenced on October 14, 
1991 and was completed on April 15, 1992. Approximately 
3,048,844 cubic yards of material were dredged 
and deposited in the approved Hart-Miller Island containment 
facility and the Pooles Island open water placement 
areas in the Chesapeake Bay at a cost of 
$10,686,567. A contract in the amount of $3,169,000 was 
awarded on September 21, 1992 to dredge an estimated 
1,381,400 cubic yards of material from the Craighill 
4-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Entrance, Cutoff Angle, and Swan Point Channel and 
deposit the material in the approved Pooles Island open 
water placement areas in the Chesapeake Bay. 
Maintenance, Norfolk District: Condition surveys of 
the Cape Henry, York Spit, and Rappahannock Shoal 
Channels were made. Maintenance dredging, by contract, 
of the Cape Henry Channel commenced on March 31, 
1992 and was completed on June 10, 1992. Approximately 
711,360 cubic yards of material were dredged and 
deposited in the approved Dam Neck Dredged Material 
Placement Area in the Atlantic ocean at a cost of 
$1,659,560. 
2. BALTIMORE HARBOR, MD 
COLLECTION AND REMOVAL 
OF DRIFT 
Location. Project applies to Baltimore Harbor, MD, 
and its tributaries. 
Existing project. Provides for collection and removal 
of drift from Baltimore Harbor and its tributary waters, 
and authorizes the Secretary of the Army to allot such 
amounts as may be necessary for work from appropriations 
for maintenance and improvement of existing river 
and harbor works or other available appropriations, and 
that this work shall be carried as a separate and distinct 
project. It is wholly a work of maintenance. Purpose of 
work is to afford relief from variable conditions of 
obstruction. 
Local cooperation. None required. 
Terminal facilities. See Section 1 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations, by hired labor, consisted of collection 
and disposal of 9,200 cubic feet of driftwood, ranging 
from small blocks up to timbers of large dimensions. 
3. BONUM CREEK, VA 
Location. A tidal estuary of the Potomac River, enters 
its right bank 18 miles upstream from Chesapeake Bay. 
It is in Westmoreland County, VA, about 90 miles 
southeasterly of Washington, DC. (See Coast and 
Geodetic Survey Chart 12286.) 
Existing project. Provides for a channel 60 feet wide 
and 6 feet deep from that depth in the Potomac River 
to and including an anchorage basin at the same depth 
160 feet wide and 200 feet long in front of the proposed 
public landing to be provided by local interests. Project 
also provides for the entrance channel to be protected 
on both sides by jetties, the north jetty being about 700 
feet long and the south jetty being about 300 feet long. 
Cost of new work for completed project was $205,998 for 
construction, of which $202,000 was for the Federal cost, 
exclusive of aids to navigation and preauthorization and 
$3,998 was the non-Federal contribution. 
Local cooperation. Local interest must furnish lands, 
and rights-of-way for new work and future maintenance; 
hold the United States free from damages; build and 
maintain a suitable public landing with adequate approaches 
thereto; make alterations, relocations, and 
removals as required of utility facilities, and wrecks and 
stakes; establish a competent public body to regulate the 
harbor facilities; and make a lump sum cash contribution 
of 2 percent of the first cost of general navigation facilities. 
Assurances of local cooperation were accepted on 
January 11, 1967. 
Terminal facilities. Several small privately owned piers 
or wharves are available on Bonum Creek. Local interests 
constructed an oyster packing house and a public 
landing. 
Operations and results during fiscal year. Maintenance: 
Dredging of the project channel, by contract, 
began October 3, 1992. Dredged material will be placed 
in open water, covered with oyster shell in anticipating 
an oyster set. This beneficial use of dredged material to 
create an oyster bar may be used as a long-term effort. 
4. CHESTER RIVER, MD 
Location. Rises in Kent County, DE, flows 50 miles 
generally southwesterly and empties into the Chesapeake 
Bay. Kent Island Narrows is a passage connecting 
Chester River and Eastern Bay. Wells Cove is an indentation 
on the easterly side of Kent Island Narrows about 
0.4 miles south of the highway bridge crossing the 
Narrows. (See Coast and Geodetic Survey Charts 12266 
and 12270.) 
Previous project. For details see page 262 of the 1960 
Annual Report. 
Existing project. Provides for a channel 6 feet deep at 
mean low water and 60 feet wide from Crumpton to Jones 
Landing, section included in project is about 5.5 miles 
long with the lower end of the section being about 37 
miles above mouth of river; for a channel 7 feet deep at 
mean low water and 75 feet wide from Chester River to 
Eastern Bay through Kent Island Narrows; and a 
channel 7 feet deep at mean low water and 75 feet wide 
extending from 7-foot deep curve in Kent Island Narrows 
800 feet into Wells Cove with a basin of same depth and 
300 feet square at head of channel. Mean range of tide 
is 2.4 feet. Cost of new work for completed project was 
$32,454, exclusive of amounts expended on previous 
projects. Widening 7-foot deep channel from 75 to 100 
feet from Chester River to Eastern Bay through Kent 
Island Narrows was deauthorized and is excluded from 
the foregoing estimate. 
Local cooperation. Fully complied with except local 
interests are to furnish spoil disposal areas for future 
maintenance of Wells Cove section of the project. 
Terminal facilities. There are two bulkhead vharves 
on Chester River section. Facilities on the Kent Island 
Narrows section of the existing project consist of about 
10,000 linear feet of timber pile bulkheaded wharf. About 
1,350 linear feet of the wharf is owned and operated by 
4-4

BALTIMORE, MD DISTRICT 
the Queen Anne's County; the remainder is privately 
owned. The privately owned bulkheaded wharf is operated 
mostly by the 7 marinas located on the Narrows 
with the remainder being owned and operated by the 
seafood packing houses in the area. In addition to the 
slips of the marinas, there are marine railways, launching 
ramps, and travel-lifts. All of these facilities are in 
good condition and are located adjacent to the proposed 
improvements. In Wells Cove there is a small wharf, a 
small marine railway, and a public landing. All facilities 
are privately owned except the public landing on Wells 
Cove. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. The 
material will be placed behind segmented offshore breakwaters 
and planted with marsh grass. Dredging is expected 
to begin in the spring 1993. 
5. KNAPPS NARROWS, MD 
Location. A small channel separating Tilghman Island 
from mainland of eastern shore of Chesapeake Bay about 
40 miles south of Baltimore, MD. (See Coast and 
Geodetic Survey Chart 1225.) 
Existing project. A channel 9 feet deep at mean low 
water, 75 feet wide, widened at the bends from deep water 
in Chesapeake Bay to deep water in Harris Creek, MD. 
Mean range of tide is 1.4 feet. Cost of new work for completed 
project was $46,121. Existing project channel was 
authorized by the Public Works Administration, 
September 16, 1933, and later adopted by 1935 River and 
Harbor Act. 
Local cooperation. Complied with except local interests 
must furnish spoil disposal areas as needed for future 
maintenance. 
Terminal facilities. A bulkhead wharf exists on each 
side of the southerly abutment of the bridge across the 
Narrows. There are several small-boat landings within 
the Narrows and several marine railways for repairing 
boats of a few feet in draft. A bulkhead landing is available 
for public use at the turning basin. 
Operations and results during fiscal year. Maintenance: 
A maintenance dredging contract was awarded 
on September 20, 1991 to remove 72,000 cubic yards of 
material. Dredging was completed in February 1992. 
6. NANTICOKE RIVER, MD 
Location. The Nanticoke River flows in a southwesterly 
direction to Tangier Sound, Chesapeake Bay, 
and is about 50 miles long. The town of Nanticoke, Md., 
is on the east side of the river, about 3 miles from the 
mouth, just north of Roaring Point. (See Coast and Geodetic 
Survey Chart 567.) 
Existing project. Provides for a small-boat harbor 7 
feet deep, 120 feet wide, and 400 feet long in the marsh 
at Nanticoke, with an entrance channel of the same depth 
and 60 feet wide, protected by twin stone jetties in the 
river, the north jetty being about 870 feet long and the 
south jetty being about 770 feet long. The mean range 
of tide is about 2.6 feet. The cost of new work for the completed 
project was $73,243. 
Local cooperation. Fully complied with except that 
local interests are to furnish placement sites as required 
for subsequent maintenance and guarantee the United 
States and its contractors against claims for damages 
to oyster beds attributable to subsequent maintenance. 
Terminal facilities. There are three privately owned 
wharves open to the general public. 
Operations and results during fiscal year. Maintenance 
dredging, by contract, to restore channel and 
basin to authorized dimensions began in April 1992 and 
was completed in September 1992. A total of 49,867 cubic 
yards of material, place measure, was removed and 
deposited in an upland placement site. 
7. OCEAN CITY HARBOR AND 
INLET AND SINEPUXENT BAY, MD 
Location. Ocean City is on a barrier island between 
Sinepuxent Bay and Atlantic Ocean about 35 miles south 
of entrance to Delaware Bay. (See U.S. Coast and 
Geodetic Survey Chart 12211.) 
Existing project. This provides for an inlet channel 200 
feet wide and 10 feet deep through the inlet to the channel 
in the Isle of Wight Bay, protected on the south side by 
a stone jetty with a top elevation of 8.8 feet above mean 
low water and a top width of 18 feet, and on the north 
side by a stone jetty with a top elevation of 9 feet above 
mean low water and a top width of generally 20 feet, 
thence generally 100 feet wide and 6 feet deep to the 
project harbor; a channel 6 feet deep and 150 feet wide 
in Sinepuxent Bay from the inlet to Green Point, and 
thence 100 feet wide in Chincoteague Bay; and for a 
channel 6 feet deep and 125 feet wide from the inlet 
channel to a point opposite North Eighth Street in Ocean 
City, thence 75 feet wide into the Isle of Wight Bay. The 
modification authorized by the 1954 River and Harbor 
Act was deauthorized in December 1989. This work included 
16 and 14 foot depth channels with widths from 
300 to 100 feet from the Atlantic Ocean to the head of 
the harbor. Depths in the inlet channel and harbor refer 
to project datum. Depths in the bay channels refer to 
mean low water. 
The elevation of mean low water in the bays above 
mean low water in the ocean at Ocean City varies from 
about 0.8 foot in the vicinity of the inlet to 1.7 feet at 
their heads. The mean range of ocean tide is 3.4 feet. The 
extreme range is from 3 feet below mean low water to 
about 3.5 feet above mean high water, a total of 9.9 feet. 
In the bays the mean range of tide varies from approximately 
2.5 feet at the inlet to 0.3 foot at their heads. 
4-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Greater fluctuations are caused by prolonged high winds. 
Federal cost of new work for the completed project was 
$1,190,530, exclusive of $500,000 contributed by local 
interests and exclusive of $3,700,000 for rehabilitating 
the south jetty. 
Local cooperation. Fully complied with except local 
interests must furnish spoil disposal areas for future 
maintenance as needed. 
Terminal facilities. On bay side of Ocean City: two 
storage basins, for pleasure and small commercial craft, 
and numerous privately owned pile-and-timber piers and 
bulkhead wharves. At project harbor: a public landing 
about 1,000 feet long, several privately constructed 
bulkhead wharves open to the public for transaction of 
business with the owners, and a boat repair yard with 
a marine railway capable of handling boats up to about 
150 tons. All piers and wharves are accessible by highway. 
Port facilities have been expanded to include all 
available space in the Fish Harbor. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with the proposed maintenance dredging. 
8. POTOMAC AND ANACOSTIA 
RIVERS, DC COLLECTION AND 
REMOVAL OF DRIFT 
Location. Project applies to the Potomac and 
Anacostia Rivers, Washington, DC and their tributaries. 
Existing project. Collection and removal of drift from 
the waters of the Potomac and Anacostia Rivers and 
their tributaries in the Washington area from the head 
of tidewater to Mount Vernon, VA. Total length of 
project, considering both sides of the waterway, is about 
50 miles. 
Local cooperation. None required. 
Terminal facilities. See Section 19 of this text. 
Operations and results during fiscal year. Maintenance: 
Operations by hired labor consisted of collection 
and disposal of 262,430 cubic feet of driftwood, ranging 
from small blocks up to timbers of large dimensions. 
9. POTOMAC RIVER AQUATIC PLANT 
CONTROL, MD, VA, DC 
Location. The project is located in the Potomac River 
and its tributaries with the northern boundary at Chain 
Bridge in Washington, DC extending southward to the 
U.S. Route 301 Bridge (See U.S. Coast and Geodetic 
Chart 12289). 
Existing project. On July 2, 1986 the Chief of 
Engineers under the authority of Section 302 of the 1965 
River and Harbor Act, as amended, authorized the 
control of hydrilla and other nuisance plants using 
mechanical harvesting to clear a 60 foot wide, 6 foot deep 
connecting channel from open waters to eligible public 
use areas. 
Local cooperation. The Local Cooperation Agreement 
(LCA) was signed on June 6, 1986 between the Corps, 
MD, VA, DC and Metropolitan Washington Council 
of Governments. The LCA which must be reexecuted 
annually expired on September 30, 1991 included the 
following provisions: 1. Local sponsors share 50 percent 
of the program cost; 2. Local sponsors provide lands, 
easements, and rights-of-way; 3. Metropolitan Washington 
Council of Governments is responsible for coordinating 
local interests and issuing work orders for the 
program. 
Terminal facilities. There are 75 marina activities 
between DC and the U.S. Route 50 Bridge providing 
approximately 3,400 commercial and recreational boat 
slips and 50 boat ramps. 
Operations and results during fiscal year. New Work: 
Harvesting operations resulted in about 16 acres of 
nuisance aquatic plants at sites in Maryland and 
Virginia. Due to budget constraints, Maryland did not 
participate in the program this year and Virginia participated 
late into the season. There were no harvesting 
operations conducted in the District of Columbia or 
Maryland this fiscal year. 
10. POTOMAC RIVER AT 
ALEXANDRIA, VA. 
Location. Alexandria is 3 miles below Washington, 
D.C., on right bank of Potomac River, which flows 
southeasterly into Chesapeake Bay 105 miles downstream. 
(See Coast and Geodetic Survey Chart 12289.) 
Existing project. Provides for depth of 24 feet in front 
of Alexandria between the through channel and a line 
drawn 20 feet outside of established pierhead line. Project 
area is about 6,700 feet long and averages 300 feet wide. 
Plane of reference is mean low water. Tidal ranges are: 
Mean, 2.8 feet; irregular, 4.5 feet; and extreme, 10.6 feet. 
Cost of new work for completed project was $95,215. 
Existing project was adopted by 1910 River and Harbor 
Act (H. Doc. 1253, 60th Cong., 2d sess.). Map is in project 
document. 
Local cooperation. None required. 
Terminal facilities. Alexandria has 12 regular shipping 
wharves or landings; nine of these are privately owned 
(of which four are open to the public by special arrangement) 
and three owned by the United States. Terminal 
and transfer facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
4-6

BALTIMORE, MD DISTRICT 
11. POTOMAC RIVER BELOW 
WASHINGTON, DC 
Location. Potomac River is formed 21 miles below 
Cumberland, MD, and flows southeasterly about 285 
miles and enters Chesapeake Bay, about 80 miles from 
Atlantic Ocean. Washington, DC is 108 miles upstream 
of mouth, and head of tidewater is at mile 117. (See Coast 
and Geodetic Survey Charts Nos. 12233, 12286, 12287, 
12288, and 12289.) 
Existing project. Provides for a channel 24 feet deep 
and 200 feet wide between the mouth of the river and 
Giesboro Point at Washington, DC a distance of 108 
miles. Plane of reference is mean low water. Tidal ranges 
are: mean, 1.3 feet at mouth, 2.9 feet at Washington; 
irregular, 2 feet at mouth, 4.5 feet at Washington; 
extreme, about 6 feet at mouth, 10.7 feet at Washington. 
Federal cost of new work for the completed project was 
$153,836. 
Local cooperation. None required. 
Terminal facilities. In general, the improvement is a 
main river channel, and terminal facilities are only served 
where the channel runs close to either bank of river. In 
all, 11 wharves are thus served. These wharves are of 
open and solid fill construction and bulkhead type. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
12. PREVENTION OF OBSTRUCTIONS & 
INJURIOUS DEPOSITS, 
BALTIMORE, MD 
Location. Project applies to tidal waters of the harbor 
of Baltimore and its adjacent and tributary waters and 
to all tidal waters of Chesapeake Bay and in Maryland. 
Existing project. Patrol and inspection throughout the 
project location to detect violations of sections 13 and 
15 of the River and Harbor Act of March 3, 1899 and 
to investigate obstructions to navigation pursuant to 
Federal regulations (33 CFR 209.109). 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Operations, by Supervisor of Harbor of Baltimore 
included inspections of approximately 75 Federal 
navigation channels within the project location to insure 
channels are not obstructed to general navigation by 
debris, sunken vessels/wrecks and/or fishing appurtenance. 
There were two detailed investigations of 
obstructions or sunken vessels/wrecks. 
13. TWITCH COVE AND BIG 
THOROFARE, MD 
Location. A tidal waterway about 4 miles long traversing 
Smith Island, MD, southeasterly from Chesapeake 
Bay on the west to Tangier Sound on the east. (See U.S. 
Coast and Geodetic Survey Chart 1224.) 
Existing project. A channel 7 feet deep at mean low 
water and 60 feet wide from Twitch Cove on Tangier 
Sound through Big Thorofare, thence through canal at 
Ewell, MD, thence through Levering Creek and Big 
Thorofare to vicinity of Swan Point, thence of same depth 
and 100 feet wide through offshore bar to deep water in 
Chesapeake Bay, with twin stone jetties at entrance, 
north jetty is about 2,080 feet long, and south jetty about 
1,800 feet long; and anchorage basin 7 feet deep, 100 feet 
wide, and 700 feet long connecting with west side of existing 
project channel at Ewell; extension of existing 
project channel in Levering Creek, 6 feet deep, 60 feet 
wide, and 1,000 feet long; and a channel 4 feet deep and 
25 feet wide around point between Big Thorofare and 
Tylers River. Mean range of tide is 1.7 feet, and extreme 
tidal range is 3 feet. Federal cost of new work for completed 
project was $193,175. 
Local cooperation. Fully complied with, except that 
local interests are to furnish placement sites for future 
maintenance as needed. 
Terminal facilities. Numerous privately owned pileand-
timber wharves and bulkheads at Ewell are open to 
the public for business transactions with the owners. A 
county wharf is also at west end of town. Five crab 
houses are on Levering Creek, and one oyster house on 
project waterway west of Town of Ewell. 
Operations and results during fiscal year. Maintenance: 
Engineering and design was accomplished in 
connection with proposed maintenance dredging. Contract 
awarded on March 25, 1992, to remove 95,000 cubic 
yards of material from Twitch Cove and Big Thorofare 
West River. Dredging completed in September 1992. 
Dredged material was used for beach nourishment and 
for submerged aquatic vegetation habitat creation. 
14. WASHINGTON HARBOR, DC 
Location. Within District of Columbia at junction of 
Anacostia River with Potomac River which flows southeasterly 
108 miles to Chesapeake Bay. It is southerly 202 
miles by water from Baltimore, MD, and northerly 195 
miles from Norfolk, VA. (See U.S. Coast and Geodetic 
Survey Chart 12289.) 
Existing projects. A combination and extension of 
latest projects for Potomac River at Washington, DC, 
and Anacostia River, DC. The Washington Harbor 
project provides for a channel in the Potomac River from 
Giesboro Point to Key Bridge, a second channel from 
Giesboro Point to the end of Washington Channel, and 
a third channel from the mouth of the Anacostia River 
to the foot of 15th Street, SE, with turning basins opposite 
the Naval Weapons Plant (800 feet wide and 2,400 
feet long) and at the head of the Anacostia Channel (400 
feet square). Channel dimensions are 24 feet deep and 400 
feet wide except upstream from Anacostia Bridge where 
the width is reduced to 200 feet and from Giesboro Point 
to a point 3,000 feet downstream of Arlington Memorial 
4-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Bridge and above Easby Point where channel dimensions 
are 20 feet deep and 200 feet wide. Channel lengths including 
turning basins are: Virginia Channel, 5,000 feet; 
Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and operation and maintenance of the inlet 
gates and lock and the outlet gates of the Tidal Basin 
constructed under a previous project to flush Washington 
Channel. Plane of reference is low-water datum which is 
0.35 foot below mean low tide as observed from 1932 to 
1942. Tidal ranges are: mean, 2.9 feet; irregular, 4.5 feet; 
and extreme, 10.7 feet. Federal cost of new work for the 
completed project was $162,006. 
Local cooperation. None required. 
Terminal facilities. There are four wharves generally 
of bulkhead type on Virginia Channel that are privately 
owned and not open to the public except by special 
arrangement. On Washington Channel there are four 
piers under jurisdiction of District of Columbia, two of 
which are open to the public and one open to the public 
by special arrangement. In Anacostia River there are four 
privately owned piers and eight governmental piers and 
slips. None of the piers are open to the public except by 
special arrangement. Terminal facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
The tidal basin gates were inspected and maintained 
by hired labor. 
15. WICOMICO RIVER, MD 
Location. Wicomico River has its source in northern 
part of Wicomico County, MD, and flows generally southwardly 
emptying into Monie Bay, a tributary of Tangier 
Sound on the east side of Chesapeake Bay about 85 miles 
southeast of Baltimore. Webster Cove is site of improved 
small-boat harbor on southeast bank of Wicomico River 
about 3 miles above the mouth. (See U.S. Coast and 
Geodetic Survey Charts 567 and 1224.) 
Existing project. Channel 14 feet deep and 150 feet 
wide from Chesapeake Bay to Salisbury, section included 
in project is 37 miles long, including about 12 miles from 
mouth of river to Chesapeake Bay; 14 feet deep in 
channels and turning basins in north and south prongs 
with channel widths of 100 feet, and a channel 6 feet deep 
and 60 feet wide extending from 6-foot contour in 
Wicomico River to and including a basin in Webster Cove 
of same depth, 100 feet wide and 400 feet long; and 
extension of basin 200 feet long and 100 feet wide on each 
side. Plane of reference is mean low water. Mean range 
of tide is about 3 feet and extreme tidal range is 4.4 feet. 
Cost of new work for completed project was $421,609, 
exclusive of amounts expended on previous project. 
Local cooperation. Fully complied with, except that 
local interests are to furnish spoil disposal areas for 
future maintenance as needed and hold the United States 
free from such damages as may occur to public or leased 
oyster beds. 
Terminal facilities. Present waterfront at Salisbury 
consists of pile-and-timber bulkheads with earthfills. 
Some wharves have warehouses and factories with 
mechanical freight-handling facilities and rail sidings. All 
terminals are privately owned. A shipyard, with two 
marine railways with capacities of 1,200 and 500 tons, 
respectively, is on right bank of river below prongs. Areas 
for development of new terminals on north prong are 
limited. Areas for considerable expansion of terminal 
facilities are available on main river. There is a pileand-
timber wharf about 4 miles above mouth of river at 
Mount Vernon. A wharf of similar construction is at 
White Haven. There is a county wharf at head of basin 
in Webster Cove, a pile-and-timber pier at oyster house 
on southwest side of basin, a T-shaped pile-and-timber 
pier at cafe on southwest side of basin and several small 
timber piers on walkways that local interests constructed 
around the basin. Fueling facilities are available at the 
T-shaped pier. Sufficient areas are available for construction 
of additional facilities when required. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was accomplished 
in connection with proposed maintenance dredging. 
16. RECONNASSISANCE AND 
CONDITION SERVICES 
(See Table 4-H at end of chapter.) 
17. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Fiscal year costs were $3,339 for Monroe Bay, VA; 
$54,132 for Pocomoke Creek, MD; $395 for Shallow 
Creek, Spur Channel, MD; and $16,090 for Solomon 
Island Harbor, MD. 
Non-Federal contributed costs for the fiscal year were 
$30,497 for Solomon Island Harbor, MD. 
Beach Erosion Control 
18. BEACH EROSION 
CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Beach Erosion Control pursuant to Sec. 103 of Public 
Law 727, as amended (preauthorization). 
Fiscal year costs were $3,219 for Town of North Beach, 
MD. 
4-8

BALTIMORE, MD DISTRICT 
19. ATLANTIC COAST OF MARYLAND 
Location. The project is located on Fenwick Island at 
Ocean City, Maryland which is about 35 miles south of 
the entrance to Delaware Bay. (See U.S. Coast and 
Geodetic Survey Charts 1220.) 
Existing project. The authorized project provides for 
a steel sheetpile bulkhead along the oceanward edge of 
the boardwalk from about 4th Street to 27th Street and 
a sand dune from 27th Street to about 0.3 miles across 
the Delaware line. The bulkhead is fronted by a 165-foot 
wide beach and the dune is fronted by a 100-foot wide 
beach. The project also provides for periodic nourishment 
over the 50-year project life. The current estimated total 
project cost is $540,000,000 (including a future inflation 
allowance through the project completion) which 
includes $45,822,000 for initial construction and 
$494,178,000 for periodic nourishment. 
Local cooperation. The State of Maryland is the 
project sponsor and the Local Cooperation Agreement 
was executed March 30, 1990. The sponsor is required 
to: provide lands, easements, and rights-of-way; modify 
or relocate buildings, utilities, roads, bridges and other 
facilities; pay 35% of the first costs and 47% of periodic 
nourishment costs; and bear all costs of operation maintenance, 
replacement and major rehabilitation of storm 
damage reduction facilities. To date the sponsor has fully 
complied with these requirements. 
Operations and results during fiscal year. New Work: 
Following project dedication on October 30, 1991, Atlantic 
storms smashed the northeast coast on October 30 
and 31, November 9 and 10, 1991 and January 4 and 5, 
1992. The combination of these storms eroded about 80% 
of the completed sand dune. A construction contract to 
reconstruct the dune and beach was awarded April 9, 
1992 and was essentially completed by September 1, 
1992. 
20. COLONIAL BEACH, VA 
Location. Colonial Beach, Westmoreland County, VA, 
is located on the right bank of the Potomac River 40 miles 
upstream from its mouth at Chesapeake Bay and 69 
miles downstream from Washington, DC. (See U.S. Coast 
and Geodetic Survey Chart No. 12286.) 
Existing project. On May 29, 1980, the Chief of Engineering 
under authority of Section 103 of the River and 
Harbor Act, as amended, authorized construction of the 
following work: The project provides for extending the 
existing Central Beach area and beach at Castlewood 
Park; off shore breakwaters; and one terminal groin at 
Castlewood Park. The Central Beach extension begins 
downstream from Hawthorne Street and continues 
southward for 1,570 feet, a maximum width of 120 feet 
and provides 107,200 square feet of area, stabilized with 
vegetation about 200 feet of embankment behind the 
beachfill. There are four 200-foot breakwaters to stabilize 
this beach area. At Castlewood Park there are: a 
59,300 square feet beach area; three breakwaters and one 
100-foot terminal groin to reduce shoaling to the entrance 
channel to Monroe Creek. The breakwaters are two each 
at 200 feet in length and one at 300 feet. The beach will 
have periodic nourishment when needed. 
Local cooperation. The May 4, 1981 Local Cooperation 
Agreement between DOA and the Town of Colonial 
Beach, in brief, requires the local sponsor to: provide all 
lands, easements, and rights-of-way; hold and save U.S. 
from damages; assure public ownership; assure maintenance 
and repair of the breakwaters; provide 50 percent 
of the initial construction cost; provide 50 percent 
of the cost of periodic beach nourishment. 
Operations and results during fiscal year. Maintenance: 
Engineering and design work was performed in 
connection with proposed beach nourishment. 
Flood Control 
21. ANACOSTIA RIVER AND TRIBUTARIES, 
FLOOD PROTECTION 
AND NAVIGATION IMPROVEMENTS, 
D.C. and MD. 
Location. Project is on Anacostia River at confluence 
of northeast and northwest branches of Bladensburg, 
Md., about 9 miles above mouth at Washington, D.C. 
(See Coast and Geodetic Survey Chart 560.) 
Existing project. Channel improvements of Anacostia 
River from foot of 15th Street SE in District of Columbia, 
to junction of Northeast and Northwest Branches at 
Bladensburg, Md.; channel improvement in Northeast 
Branch from mouth upstream to near Longfellow Street 
in Riverdale, Md.; channel improvement in Northwest 
Branch from mouth upstream to near 38th Street in 
Brentwood, Md.; levees along both banks of the streams 
to protect Bladensburg, Edmonston, Riverdale, Cottage 
City, and Colmar Manor, Md.; interior drainage facilities 
in these communities, including four pumping stations 
and necessary intercepting sewers and alterations and 
reconstruction of highway and railroad bridges. Portion 
of channel improvement of Anacostia River from vicinity 
of 15th Street SE in District of Columbia to near 
Defense Highway Bridge on U.S. Route 50, provides for 
navigation channel 8 feet deep and 80 feet wide with a 
commercial boat basin, and a recreational boat basin having 
a capacity of 150 boats, both on east bank of river 
near Bladensburg, Md. Federal cost for new work for 
completed project was $6,042,325. Estimated cost to 
local interests for construction, lands, and damages is 
$6,275,000. 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. Maintenance: 
Engineering and design work accomplished in connection 
with proposed maintenance dredging. Beneficial use of 
dredged material to restore Kenilworth Marsh. Contract 
awarded on September 30, 1992 to remove 154,000 cubic 
yards of material from Benning Road Bridge in the District 
of Columbia to Bladensburg, Maryland. 
4-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
22. CUMBERLAND, MD, AND 
RIDGELEY, WV 
Location. On North Branch of Potomac River, 21 miles 
upstream from its junction with the South Branch of the 
Potomac River and 197 miles upstream from Washington, 
DC. (See Geological Survey Quadrangles, Frostburg 
and Flintstone, MD, WV, and PA.) 
Existing project. Channel improvements of North 
Branch of Potomac River from the Western Maryland 
Railway bridge in South Cumberland upstream to the 
mouth of Wills Creek, with levees and fill along the left 
bank and levees along the right bank from downstream 
corporate limits of Ridgeley, WV, to a point about 150 
feet above Johnson Street Bridge; channel improvements 
along Wills Creek from its mouth upstream to a point 
in the Narrows about 500 feet upstream from the highway 
bridge on U.S. Highway 40; levee and flood wall in 
West Cumberland, MD, on the left bank of the North 
Branch of the Potomac River from the mouth of Wills 
Creek upstream to Kelly Boulevard; levee and flood wall 
in Ridgeley, WV, on the right bank of the North Branch 
of the Potomac River from Carpenter Avenue upstream 
to Patapsco Street near the upstream corporate limits 
of Ridgeley, WV; interior drainage facilities in Cumberland 
and West Cumberland, MD, and Ridgeley, WV; 
removal of the Chesapeake and Ohio Canal dam and construction 
of a new industrial dam on the North Branch 
of the Potomac River immediately above mouth of Wills 
Creek; and alteration and reconstruction of highway and 
railroad bridges. Federal costs of new work for the completed 
project were $15,633,970, which includes $49,998 
emergency relief funds and is exclusive of $197,513 public 
works acceleration funds. Estimated cost to local interests 
is $2,900,000 of which $1,402,001 is contributed 
funds and $1,497,999 is for lands and damages. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
23. ISLE OF WIGHT BAY, 
OCEAN CITY, MD 
Location. The project is located on Chicago Avenue 
along the Isle of Wight Bay between 2nd and 4th Streets, 
in downtown Ocean City, Worcester County, Maryland. 
Ocean City is located on the Atlantic Ocean approximately 
20 miles south of the Maryland-Delaware line. 
(See NOAA Chart No. 12211.) 
Existing project. On October 6, 1988 the Chief of 
Engineers, under the authority provided by Section 14 
of the 1946 Flood Control Act, as amended, authorized 
the construction of shoreline protection. The work consists 
of the placement of 3,500 tons of stone against a 
deteriorated steel sheetpile bulkhead along Chicago 
Avenue. This stone is required to prevent the bayward 
movement of the bulkhead due to increased scour at the 
toe of bulkhead. The estimated project implementation 
cost is $520,000 of which the sponsor will be paying 
$127,600. 
Local cooperation. The July 14, 1988 Local Cooperation 
Agreement between DOA and Ocean City, in brief, 
requires the local sponsor to: Provide all lands, easements 
and rights-of-way; provide modifications and relocations 
of buildings, roads, bridges, and related utilities; operate 
and maintain completed works; hold and save U.S. from 
damages; pay 25 percent of the total project costs; provide 
cash contribution not less than 5 percent of total 
project costs; assume responsibility for all costs in excess 
of the $500,000 Federal limitation. 
Operations and results during fiscal year. New Work: 
The construction contract was completed on May 25, 
1990. Several contract claims were settled and paid during 
the fiscal year. 
24. JENNINGS RANDOLPH LAKE, 
MD & WV 
Location. Project is located on the North Branch 
Potomac River on the state line between Garrett County, 
MD, and Mineral County, WV. The damsite is located 
approximately 7.9 miles upstream from the confluence 
with Savage River at Bloomington, MD. It is also about 
5 air miles southwest of the tritowns of Luke and 
Westernport, MD, and Piedmont, WV. (See Geological 
Survey quadrangle sheets, "Kitzmiller" and "Westernport," 
MD.) 
Existing project. The improvement consists of a rolled 
earth and rock fill dam with an impervious core and an 
800-foot long dike on the left bank. Top of dam is 296 
feet above streambed with a total length of 2,130 feet. 
When filled to spillway crest, the reservoir will extend 
about 6.6 miles upstream and inundate 965 acres. Flood 
control storage of 36,200 acre-feet is provided. Storage 
available for low flow augmentation for water supply and 
water quality improvement is 92,000 acre-feet. The reservoir 
controls a drainage area of 263 square miles. Recreation 
facilities are provided for picnicking, camping and 
boating. Final project cost is $176,325,300. 
Local cooperation. See page 4-15 of the 1977 Annual 
Report for requirements. A water supply contract 
between the Federal Government and the Washington 
Suburban Sanitary Commission in concert with the 
Fairfax County Water Authority, VA, and the District 
of Columbia has been executed for repayment of all water 
supply costs. The first of 50 annual payments began in 
July 1981. Federally approved water quality standards 
put into effect by Maryland, Virginia, West Virginia, and 
the District of Columbia are considered satisfactory 
assurances of intent to control pollution. Satisfactory 
assurances have been received from Maryland, West 
Virginia, and Virginia that they will protect downstream 
channels from encroachment that would adversely affect 
operation of the project. 
4-10

BALTIMORE, MD DISTRICT 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
25. LACKAWANNA RIVER BASIN, PA 
Flood Control Act of 1962 authorized construction of 
Aylesworth Creek Lake, Fall Brook Lake, and local protection 
works on Lackawanna River at Scranton, PA, 
substantially as recommended by the Chief of Engineers 
(S. Doc. 141, 87th Cong., 2d Sess.). The Basin includes 
an area of 346 square miles in northeastern Pennsylvania. 
25A. AYLESWORTH CREEK LAKE, PA 
Location. Project is located in Lackawanna County on 
Aylesworth Creek about one mile above its confluence 
with the Lackawanna River, near the community of East 
Jermyn, PA. 
Existing project. Provides for an earthfill dam with a 
maximum height of 90 feet above streambed and a top 
length of 1,200 feet. The spillway located adjacent to the 
left abutment is an open cut channel 80 feet wide with 
a concrete sill. The outlet works consist of a 3-foot 
diameter uncontrolled conduit. Project controls a 
drainage area of 6.2 square miles and provides flood control 
storage of 1,700 acre-feet equivalent to 5.1 inches of 
runoff from the drainage areas. The lake will extend 
about 4,600 feet and inundate 87 acres when filled to spillway 
crest. Recreation facilities constructed by local 
interest include a bathing beach, bathhouse, and picnic 
area. Federal cost of new work was $2,268,200 of which 
$2,153,559 was for construction and $114,641 for lands 
and damages. In addition $52,200 Federal and $52,200 
non-Federal funds were expended for construction of 
bathhouse facilities under the recreation facilities for 
completed projects program. 
Local cooperation. None required. The Aylesworth 
Creek Reservoir Park Authority, representing the 
Boroughs of Archbald and Jermyn, operate and maintain 
limited day use facilities including a small beach. In 
September 1978 a cost-sharing agreement for construction 
of bathhouse facilities was signed. The cost for the 
facilities which were completed in July 1979 was $104,400 
of which $52,200 was Federal and $52,200 was non- 
Federal. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
26. LOCK HAVEN, PA 
Location. On the West Branch Susquehanna River in 
the City of Lock Haven, PA about 194 miles above the 
mouth of the Susquehanna River in Clinton County, 
Pennsylvania. (See Geological Survey Quadrangle sheets, 
Lock Haven and Mile Hall, PA.) 
Existing project. Provides for 36,600 feet of levee and 
1,000 feet of concrete floodwall along the West Branch 
and Bald Eagle Creek, five closure structures, five ponding 
areas, a sanitary pumping station, 35 gravity type 
drainage structures, necessary road and utility relocations, 
non-structural measures for Woodward and Allison 
Townships, and minor recreation facilities. The current 
estimated total project cost is $86,400,000 which includes 
a future inflation allowance through project completion. 
Local cooperation. The Lock Haven Area Flood Protection 
Authority, a municpal authority created by the 
City of Lock Haven and Woodward Township, is the 
sponsor for the project. The Local Cooperation Agreement 
was signed March 14, 1991. The local sponsor is 
required to: provide lands, easements, rights-of-way; 
modify or relocate buildings, utilities, roads, bridges, and 
other facilities, pay 5% of structural flood control costs 
during construction; pay 50% of separable recreation 
costs; and bear all operation maintenance and replacement 
costs for the project after construction. 
Operations and results during fiscal year. New Work: 
Construction continued on the Bald Eagle Creek levee 
contract. The second major construction contract (West 
Branch Susquehanna River levees below Jay Street) was 
awarded December 3, 1991. The overall project which is 
about 45% complete is scheduled for completion in July 
1994. 
27. RAYSTOWN LAKE, RAYSTOWN 
BRANCH, JUNIATA RIVER, PA 
Location. Dam site is on Raystown Branch, about 5.5 
miles upstream from its confluence with Juniata River. 
Project is about 10 miles south of Huntingdon, PA. (See 
Geological Survey Quadrangle sheets, Huntingdon, Mt. 
Union, Broad Top and Everett, PA.) 
Existing project. The rock and earthfill dam rises 225 
feet above streambed with a gated concrete spillway and 
auxiliary spillway in the right abutment. The reservoir 
has a storage capacity of 762,000 acre-feet, of which 
248,000 acre-feet are for flood control, 476,000 acre-feet 
for recreation and water quality control, and the balance 
for sediment reserve. At full flood control pool elevation, 
the reservoir would inundate 10,800 acres and extend 34 
miles upstream. Recreation facilities are provided for 
boating, fishing, camping, swimming, hunting, hiking, 
and picnicking. Federal cost for new work was $77,408,700 
of which $46,120,931 was for construction and $31,287,769 
was for lands and damages including relocations. Construction 
of a private hydroelectric plant at Raystown 
Lake was completed May 1988. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. A contract was awarded in July 1991, 
4-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
to construct Seven Points Water Treatment Plant. The 
contract work has been completed and the plant is now 
operational. 
28. SOUTHERN NEW YORK FLOOD 
CONTROL PROJECTS 
Authorized plan provides for construction of reservoirs 
and related flood control works for protection of towns 
in New York and Pennsylvania. The improvements are 
located in the upper watershed of the Susquehanna River 
to and including the Chemung River. 
28A. ADDISON, NY 
Location. At confluence of Tuscaroroa Creek and 
Canisteo River in the City of Addison, NY. (See Geological 
Survey map for Addison, NY.) 
Existing project. Provides for construction of about 
3,100 feet of earth levee and 700 feet of concrete flood 
wall on the right bank of the Canisteo River, extending 
from high ground on Steuben Street near the Baltimore 
& Ohio Railroad to the mouth of Tuscarora Creek; 
removal of existing dam, mill, and raceway from the 
channel; construction of about 2,200 feet of earth levee 
on the left bank of Tuscarora Creek, extending from 
Tuscarora Street to Canisteo River; construction of 4,600 
feet of earth levee on the right bank of Tuscarora Creek, 
extending from high ground at the southwest edge of the 
village to high ground at the southeast edge of the 
village; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28B. ALMOND LAKE, NY 
Location. Dam is located two miles upstream from 
Hornell, NY, on Canacadea Creek, a tributary of the 
Canisteo River. (See Geological Survey map for Hornell, 
NY.) 
Existing project. The dam is an earthfill structure, 
1,260 feet long rising 90 feet above the streambed, with 
a concrete spillway and a gated outlet conduit in the left 
abutment. The outlet works consist of three 5-foot by 
10-foot service gates and three emergency gates of the 
same size. The reservoir has a storage capacity of 14,640 
acre-feet at spillway crest. The project controls a draining 
area of 56 square miles, 36 percent of the watershed 
of the Canisteo River upstream from Hornell, NY. Recreation 
facilities include a boat-launching ramp and dock, 
bathing beach, picnic area, and tent and trailer camping 
area. 
Local cooperation. None required. Local interests have 
developed recreational facilities at the lake in conjunction 
with the Federal Government. These facilities are 
operated and maintained by the Steuben County Board 
of Supervisors. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
28C. ARKPORT DAM, NY 
Location. Dam is located five miles upstream from 
Hornell, NY, on the Canisteo River, a tributary of the 
Chemung River which flows into the Susquehanna River. 
(See Geological Survey map for Arkport, NY.) 
Existing project. The dam is an earthfill structure, 
1,200 feet long, exclusive of spillway, rises 113 feet above 
the streambed, with a concrete spillway and an ungated 
outlet in the right abutment. The outlet structure consists 
of an 8-foot diameter reinforced concrete lined 
conduit, 660 feet long. A cast iron nozzle is placed in the 
lower end of the conduit, reducing the outlet size to 4 feet 
4 inches. The reservoir has a storage capacity of 7,950 
acre-feet at spillway crest. The project controls a 
drainage area of 31 square miles, 20 percent of the 
watershed of the Canisteo River upstream from Hornell. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28D. AVOCA, NY 
Location. On the Cohocton River at the Village of 
Avoca, NY, about 30 miles upstream from the confluence 
of the Cohocton and Chemung Rivers. (See Geological 
Survey map for Avoca, NY.) 
Existing project. Provides for improvement and realignment 
of about 8,300 feet of Cohocton River channel, 
extending from above the Erie Railroad to below the 
junction of Main Street and U.S. Highway 15; construction 
of about 8,500 feet of earth levee on left bank of the 
Cohocton River, extending from high ground above 
Alexander Avenue to about 1,300 feet below the junction 
of Main Street and U.S. Highway 15; and 4,500 feet 
of earth levee on the right bank of Salmon Creek, extending 
from high ground above Alexander Avenue to the 
Erie Railroad; a new highway bridge for U.S. Highway 
15 over Cohocton River, raising of the Erie Railroad 
bridge 4 feet; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
4-12

BALTIMORE, MD DISTRICT 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28E. BINGHAMTON, NY 
Location. At the confluence of the Chenango and 
Susquehanna Rivers in the City of Binghamton, NY. (See 
Geological Survey map for Binghamton, NY.) 
Existing project. Provides for construction of earth 
levees, concrete flood walls, and appurtenant drainage 
structures, consisting of about 850 feet of channel 
excavation and about 1,375 feet of earth levee along 
Phelps Creek, Town of Port Dickinson; new concrete wall 
on the right bank of the Chenango River, extending 
downstream from high ground near the city limits to an 
existing flood wall below DeForest Street, a distance of 
about 520 feet; about 150 feet of concrete wall just below 
Cutler Dam; about 180 feet of concrete wall at the pumphouse 
near McDonald Avenue; raising existing earth 
levees on the right bank of Chenango River, extending 
from Cutler Dam downstream for about 1,220 feet; about 
2,915 feet of earth levee on the left bank of Chenango 
River north of the city limits in the Village of Port 
Dickinson, extending from Church Street to high ground 
just north of the city line; about 3,900 feet of earth levee 
on the left bank of Chenango River, extending from 
DeForest Street to Cutler Dam; new concrete flood walls 
and riverbank revetment for about 5,570 feet extending 
on the left bank of Chenango River from Cutler Dam to 
the junction with the Susquehanna River; about 540 
feet of new concrete flood wall and raising about 1,085 
feet of concrete flood wall on the right bank of the 
Susquehanna River, extending from the Delaware, Lackawanna 
& Western Railroad downstream to Tompkins 
Street Bridge; about 1,940 feet of earth levee; about 1,940 
feet of concrete flood wall and capping about 125 feet of 
concrete flood wall, on the right bank of the Susquehanna 
River from Stuyvesent Street to mouth of Chenango 
River; about 8,380 feet of earth levee, about 2,180 feet 
of new concrete flood wall and raising about 125 feet of 
existing flood wall on the left bank of the Susquehanna 
River extending from Pierce Creek to high ground at 
State Highway 17; a debris dam and flume between 
Corbett and Hotchkiss Streets and a concrete pressure 
conduit, 1,060 feet long to carry flow of Park Creek from 
Vestal Avenue to the Susquehanna River; about 665 feet 
of levee extending from the Erie Railroad to high ground 
along the right bank of Chamberlain Creek near the 
mouth; closure structures at Erie Railroad and at Court 
Street; a weir, a drop structure, and about 1,800 feet of 
earth levee, about 2,235 feet of channel excavation, about 
645 feet of channel paving and raising, about 470 feet 
of existing concrete flood wall, and about 200 feet of new 
concrete flood wall for improvement of Pierce Creek from 
its mouth to about 1,000 feet above Conklin Avenue; and 
appurtenant drainage structures. Improvement, supplemented 
by authorized flood control dams above the 
area, will provide protection for the City of Binghamton 
against a flood discharge about 20 percent greater than 
the maximum flood of record, which occurred in July 
1935 on the Chenango River and in March 1936 on the 
Susquehanna River. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28F. CANISTEO, NY 
Location. On Purdy and Bennetts Creeks in the Town 
of Canisteo, NY, situated along the south side of the 
Canisteo River, at the confluence of Bennetts Creek and 
the Canisteo River. (See Geological Survey map for 
Canisteo, NY.) 
Existing project. Provides for construction of about 
8,000 feet of earth levees on the right bank of the 
Canisteo River, extending from high ground 1,570 feet 
west of State Highway Route 21 above the Town to a 
point at the intersection of Ordway Lane and East Main 
Street; about 7,400 feet of earth levee on the left bank 
of Purdy and Bennetts Creeks, extending from the Main 
Street Bridge to high ground above Greenwood Street; 
1,000 feet of earth levee on the right bank of Bennetts 
Creek extending upstream from the Main Street Bridge; 
a concrete check dam with wing levees from Greenwood 
Street; a new highway bridge at Greenwood Street; 
alterations to existing timber check dams in Bennetts 
Creek; channel excavation in Bennetts and Purdy Creeks; 
and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28G. CORNING, NY 
Location. On the Chemung River in the City of Corning, 
NY, about 44 miles upstream from the confluence 
of Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Corning, NY.) 
Existing project. Flood protection for this community 
was originally authorized by the Flood Control Act of 
1936. Plan of improvement provides for construction of 
a pumping station, earth levees, and concrete flood walls, 
consisting of: about 4,300 feet of earth levee, enlargement 
of about 8,610 feet of existing earth levee and bout 3,100 
feet of concrete flood wall on the right bank of the 
Chemung River, extending from the Erie Railroad Bridge 
to high ground at Park Avenue below the City; about 200 
feet of conrete flood walls; about 2,500 feet of earth levees 
and enlargement of about 11,500 feet of existing earth 
levee on the left bank of the Chemung and Cohocton 
Rivers, extending from the Erie Railroad Bridge over 
4-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Cohocton River to the mouth of Post Creek; about 2,500 
feet of earth levee and enlargement of about 4,700 feet 
of existing earth levee on the right bank of Post Creek 
from its mouth to Watkins Street; realignment of about 
3,000 feet of channel, about 8,800 feet of earth levee, 
about 3,000 feet of channel excavation, a pressure conduit 
about 400 feet long, a drop structure and a weir for 
improvement of Cutler Creek, extending from its mouth 
to high ground at Deckertown Road and Hornby Road; 
and appurtenant drainage structures. Flood protection 
on Monkey Run was authorized by the Flood Control Act 
of 1950. Plan of improvement provides for construction 
of 2,010 feet of open flume, 2,320 feet of pressure conduit 
storm sewers, and appurtenant facilities between the 
existing improved channel above Sixth Street and the 
Chemung River at a point immediately east of Pine 
Street East. Modified improvement will provide protection 
for the City of Corning against a flood discharge in 
Chemung River approximately equal to the maximum 
flood of record, which occurred in May 1945, and on tributary 
streams against floods of greater magnitude than 
known to date. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28H. EAST SIDNEY LAKE, NY 
Location. Dam is located near East Sidney, NY, on the 
Ouleout Creek, about five miles above the confluence of 
the creek with the Susquehanna River. (See Geological 
Survey map for Franklin, NY.) 
Existing project. The dam is an earthfill and concrete 
structure, 2,010 feet long, including spillway, rises 130 
feet above the streambed and consists of a concrete 
gravity-type section with a compacted earth-dike section 
at the right abutment. The outlet works consist of five 
rectangular conduits each 3.5 feet by 5.85 feet and 105 
feet long. The reservoir has a storage capacity of 33,500 
acre-feet at spillway crest. The project controls a 
drainage area of 102 square miles which is 93 percent of 
the Ouleout Creek drainage area, and 5 percent of the 
watershed of the Susquehanna River upstream from 
Binghamton, NY, exclusive of the separately controlled 
Chenango River. Recreation facilities include a bathing 
beach, picnic and camping areas, and boat-launching and 
docking facilities. 
Local cooperation. None required. The Town of Sidney, 
NY, cooperated in the development of recreation facilities 
and operates and maintains all the facilities with the 
exception of the recreational pool, which is the responsibility 
of the Federal Government. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28I. ELMIRA, NY 
Location. On the Chemung River in the City of Elmira, 
NY, about 27 miles upstream from the confluence of the 
Chemung River and North Branch of Susquehanna 
River. (See Geological Survey map for Elmira, NY.) 
Existing project. Provides for about 17,700 feet of 
earth levees, and about 4,100 feet of concrete flood wall 
on the right bank of the Chemung River, extending from 
South Hoffman Street to a point below the city near the 
upper end of Big Island; about 12,100 feet of earth levee 
and about 6,300 feet of concrete wall on the left bank of 
the Chemung River extending from Durland Avenue to 
the Delaware, Lackawanna & Western Railroad at the 
mouth of Newton Creek; about 10,000 feet of earth levee 
on right bank of Newton Creek, extending from about 
the intersection of Delaware, Lackawanna & Western 
Railroad and East Church Street to high ground near intersection 
of Sullivan and Warren Streets; about 4,300 
feet of earth levee on the right bank of Divan Creek; 
about 2,000 feet of concrete conduit enclosing Hoffman 
Brook from West Second Street to the Chemung River; 
clearing islands and riverbanks of trees and brush for 
about 3.5 miles in the Chemung River; about 14,300 feet 
of earth levee on the left bank of Seely Creek, extending 
from the Erie Railroad to high ground approximately 
1,000 feet northwest of the intersection of South Broadway 
and Pennsylvania Avenue; a pumping plant for disposal 
of interior drainage; an interceptor sewer about 
6,000 feet long varying in size from 48 to 96 inches in 
diameter; and appurtenant structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28J. HORNELL, NY 
Location. On the Canisteo River in the City of Hornell, 
NY, about 42 miles upstream from the confluence of the 
Canisteo and Tioga Rivers. (See Geological Survey map 
for Canisteo, NY.) 
Existing project. Provides for channel realignment and 
earth levees, concrete flood walls, and check dams consisting 
of: realignment of about 4,600 feet of the 
Canisteo River channel, and about 5,800 feet of earth 
levee on its right bank, extending from Seneca Street 
upstream to the junction of the Pittsburgh, Shawmut & 
Northern Railroad and the Erie Railroad; about 4,500 feet 
of earth levee, extending on both sides of Seneca Street 
from the Canisteo River to Wrightman Avenue and the 
junction of Cleveland Avenue and Bethesda Drive; about 
7,200 feet of earth levee, about 2,500 feet of concrete flood 
wall, and raising about 1,500 feet of existing concrete 
flood wall, on the right bank of the Canisteo River, and 
about 12,000 feet of channel improvement, extending 
from Seneca Street to the Erie Railroad; about 2,500 feet 
of earth levee, about 2,100 feet of concrete flood wall on 
the left bank of the Canisteo River extending from a point 
4-14

BALTIMORE, MD DISTRICT 
opposite Walnut Street to the Erie Railroad; a ring-earth 
levee about 2,800 feet long around the sewage-disposal 
plant on the left bank of the Canisteo River; about 4,500 
feet of realignment and improvement of the Canisteo 
River Channel with about 4,500 feet of earth levee on its 
right bank extending from Cedar Street downstream to 
about 1,400 feet above East Avenue; about 2,400 feet of 
channel paving, 1,400 feet of earth levee, raising about 
1,900 feet of concrete flood wall, and construction of one 
check dam on Canacadea Creek; about 1,600 feet of 
channel paving and construction of three check dams on 
Chauncey Run with about 300 feet of new wall and about 
300 feet of capping; a weir, a check dam, 3,030 feet of 
channel paving, 4,800 feet of flood walls and levees, and 
related work on existing walls, on Crosby Creek; removal 
of 6 bridges, erection of 4 bridges, miscellaneous bridge 
structures, and 3 drop structures; and appurtenant 
drainage structures and small stream control works. 
Improvement, supplemented by Arkport and Almond 
Reservoirs above the area, provides protection for the 
City of Hornell against a flood discharge approximately 
double the maximum flood of record, which occurred in 
July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. A Phase I contract for removal of sediment 
from selected locations along the project was completed 
in October 1990. Phase II contract for repair and 
replacement of floodwalls, replacement of check dams 
and other miscellaneous repairs to slopes and channels 
was completed in October 1991. Phase III contract for 
repair at floodwalls was awarded in fiscal year 1992 and 
is expected to be completed by end of fiscal year 1993. 
28K. LISLE, NY 
Location. On the Tioughnioga River in the Village of 
Lisle, NY, about 12 miles upstream from the confluence 
of the Tioughnioga and Chenango Rivers. (See Geological 
Survey map for Lisle, NY.) 
Existing project. Provides for channel realignment and 
construction of earth levees and concrete flood walls, consisting 
of: relocation of about 3,000 feet of Dudley Creek 
Channel, extending from 1,200 feet west of the intersection 
of Cortland and Main Streets to the confluence with 
Tioughnioga River, realignment of some 5,700 feet of 
Tioughnioga River Channel east of the Village; about 
4,150 feet of earth levee and 970 feet of concrete wall on 
the right bank of Dudley Creek and Tioughnioga River; 
realignment of some 5,700 feet of Tioughnioga Street to 
the railroad crossing on River Street; raising about 1,860 
feet of the Delaware, Lackawanna & Western single track 
railroad over the levee; relocation of about 1,600 feet of 
Cortland Street; a new bridge over relocated Dudley 
Creek; and appurtenant drainage structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28L. OXFORD, NY 
Location. On the Chenango River in the Village of 
Oxford, NY, about 40 miles upstream from the confluence 
of the Chenango and Susquehanna Rivers. (See 
Geological Survey map for Oxford, NY.) 
Existing project. Provides for earth levees and clearing 
of Chenango River Channel, consisting of about 2,100 
feet of earth levees on the left bank of the Chenango 
River, extending from high ground near Cemetery Drive 
and running mostly along the railroad to high ground 
near Main Street; removal of dam and island below Main 
Street; raising the Delaware, Lackawanna & Western 
Railroad over the levee; and appurtenant closure and 
drainage structures. Improvement provides protection 
for the Village of Oxford on the left bank against a flood 
discharge substantially larger than the maximum flood 
of record, which occurred in July 1935. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
28M. WHITNEY POINT LAKE, NY 
Location. Dam is located near Whitney Point, NY, on 
the Otselic River about 0.7 mile upstream from its confluence 
with Tioughnioga River. (See Geological Survey 
map for Whitney Point and Willet, NY.) 
Existing project. The dam is an earthfill structure, 
4,900 feet long, exclusive of a spillway, rises 95 feet above 
the streambed, with a concrete spillway and gated outlet 
in the left abutment. The outlet works consist of three 
5-foot by 10-foot gates and one emergency gate of the 
same size. The reservoir has a storage capacity of 86,440 
acre-feet at spillway crest. The project controls a 
drainage area of 255 square miles, the entire watershed 
of Otselic River, or 16 percent of the Chenango River 
watershed upstream from Binghamton, NY. Recreation 
facilities, constructed in cooperation with local interests, 
provide for swimming, picnicking, camping, boating, fishing, 
and hunting. 
Local cooperation. None required. Local interests operate 
and maintain all of the recreation facilities. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. A contract was awarded in September 
1991 to replace some deteriorating sections of concrete 
at the project. This work will be completed in fiscal year 
1993. 
4-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
28N. WHITNEY POINT VILLAGE, NY 
Location. On the Tioughnioga River at the confluence 
of the Tioughnioga and Otselic Rivers, tributaries of the 
Susquehanna River. (See Geological Survey map for 
Whitney Point, NY.) 
Existing project. Provides for channel realignment and 
earth levees, consisting of realignment of about 1,800 feet 
of Tioughnioga River Channel, above the confluence with 
Otselic River; about 7,100 feet of earth levee along the 
right bank of the Tioughnioga River, extending from high 
ground on Main Street above the village to Collins Street 
just below the Village; and appurtenant drainage 
structures. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
29. SOLOMON CREEK, ASHLEY 
BOROUGH, LUZERNE COUNTY, PA 
Location. Solomon Creek is located in central Luzerne 
County in northeastern Pennsylvania, approximately .5 
mile south of Wilkes Barre. 
Existing project. On September 25, 1990, the Assistant 
Secretary of the Army for Civil Works authorized 
the Chief of Engineers, under authority of Section 14 of 
the Flood Control Act of 1946, as amended, to construct 
an emergency streambank protection project at Solomon 
Creek, Ashley Borough, Pennsylvania. The project consists 
of constructing 30 feet of gabion retaining wall 
along an eroding streambank. Without construction of 
the Federal project, Solomon Creek would continue to 
erode the streambank resulting in the eventual collapse 
of the roadway above. 
The gabion wall will tie into the existing concrete wall 
at the downstream end of the project and an existing 
stone masonry wall at the upstream end. The structure 
is approximately 11 feet high. A small section of the 
streambank upstream of the project area will also be protected 
with additional gabions. 
Local cooperation. The Local Cooperation Agreement 
between the Corps of Engineers and the Borough of 
Ashley was executed on October 4, 1990. The local 
sponsor is responsible for providing all lands, easements, 
and rights of way as well as 25 percent of the total construction 
costs. Following more than two years of coordination, 
the easements were obtained by the local 
sponsor and advertisement for construction of the 
project was initiated in late fiscal year 1992. 
Operations and results during fiscal year. New Work: 
A construction contract was awarded on September 29, 
1992. Following issuance of a Notice to Proceed, construction 
will be initiated in November 1992. Construction 
should be completed in January 1993. 
30. SOLOMONS ISLAND, 
CALVERT COUNTY, MD 
Location. Solomons Island is located in Calvert 
County, Maryland, approximately 40 miles southeast of 
Washington, DC and 55 miles south of Baltimore, 
Maryland. 
Existing project. On February 4, 1992, the Assistant 
Secretary of the Army for Civil Works authorized the 
Chief of Engineers, under authority of Section 14 of the 
Flood Control Act of 1946, as amended, to construct an 
emergency shoreline erosion control project at Solomons 
Island, Calvert County, Maryland. The project consists 
of 500 linear feet of stone revetment placed against a 
deteriorating steel sheetpile bulkhead. The project is 
designed to protect the roadway adjacent to the shoreline. 
Without construction of the Federal project, continued 
wave attack will result in structural failure of the 
steel sheetpile bulkhead and collapse of the roadway. 
The revetment consists of a bedding stone layer placed 
over a geotextile fabric. Armor stone weighing between 
200-800 lbs will be placed over the bedding layer at a 
varying slope. The revetment ties into the existing bank 
on the seaward side of the roadway at an average elevation 
of 7.5 feet above mean low water (MLW). 
Local cooperation. The Local Cooperation Agreement 
between the Corps of Engineers and the Maryland 
Department of Transportation, State Highway Administration, 
was executed on April 14, 1992. The local sponsor 
is responsible for providing all lands, easements, and 
rights of way, as well as 25 percent of the total construction 
costs. 
Operations and results during fiscal year. New Work: 
A construction contract was awarded on September 29, 
1992. Following issuance of a Notice to Proceed, construction 
will be initiated on October 9, 1992 and should 
be completed in December 1992. 
31. SPRING BROOK CREEK, 
PITTSTON TOWNSHIP, PA 
Location. The project is located in the Township of 
Pittston along the banks of Spring Brook Creek adjacent 
to PA state route 502. Pittston Township is located in 
northeastern Luzerne County, PA approximately 1 mile 
southeast of Scranton, PA. (See USGS quad sheets 
"Pittston, PA" and "Avoca, PA".) 
Existing project. On January 26, 1989, the Chief of 
Engineers, under the authority provided by Section 14 
of the 1946 Flood Control Act, as amended, authorized 
construction of streambank protection. The work consists 
of the excavation and backfilling of the existing 
streambank and placement of approximately 870 feet of 
stone riprap. Additional riprap is being placed as a 
betterment that was proposed by the sponsor. The 
estimated project implementation cost is $460,000, of 
which the sponsor has contributed $115,000 as well as 
provided $40,000 for the betterment. 
4-16

BALTIMORE, MD DISTRICT 
Local cooperation. The July 24, 1989 Local Cooperation 
Agreement between DOA and Pittston Township, 
in brief, requires the local sponsor to: Provide all lands, 
easements and rights-of-way; provide modifications and 
relocations of buildings, roads, bridges, and related 
utilities; operate and maintain completed works; hold and 
save U.S. from damages; pay 25 percent of the total 
project costs; provide cash contribution not less than 5 
percent of total project costs; assume responsibility for 
all costs in excess of the $500,000 Federal limitation. 
Operations and results during fiscal year. New Work: 
The construction contract was awarded on September 30, 
1989 and was physically completed in June 1990. A construction 
contract claim was settled during the fiscal year 
and the project is expected to be fiscally closed out early 
in fiscal year 1993. 
32. STILLWATER LAKE 
LACKAWANNA RIVER, PA 
Location. Dam is on the Lackawanna River, 39 miles 
from the mouth of the stream and about 4 miles upstream 
from Forest City, Susquehanna County, PA (See Geological 
Survey Quadrangle sheet, Honesdale, PA.) 
Existing project. Dam is earthfill type, rising 77 feet 
above the streambed, with a controlled outlet conduit and 
side channel spillway in the left abutment. Reservoir 
capacity is 12,000 acre-feet, of which 11,600 acre-feet is 
flood control storage and the remainder utilized to maintain 
the existing water supply reservoir for Forest City, 
PA, at this site. Reservoir area is 422 acres,and the pool 
extends about 2.1 miles upstream. Reservoir controls 52 
percent of the watershed above Carbondale, 26 percent 
above Olyphant, and 17 percent above Scranton. Federal 
cost of new work, completed in 1965, was $5,725,700 of 
which $4,500,500 was for construction and $1,225,200 
was for lands and damages. 
Local cooperation. None required. Section 2, Flood 
Control Act of June 28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of project 
continued. 
33. SUSQUEHANNA RIVER FLOOD 
CONTROL PROJECTS, NY AND PA 
Plan of improvement authorized by the 1958 Flood 
Control Act provides for construction of Cowanesque 
Lake, PA, Tioga-Hammond Lakes, PA, local protection 
works at Elkland, PA, and Nichols, NY, and channel 
improvements at Cortland, NY. This project plan supplemented 
the comprehensive flood control program for 
Southern New York and Northern Pennsylvania which 
included the Southern New York flood control project 
and Stillwater, Genegantslet, and South Plymouth 
Reservoirs. 
33A. COWANESQUE LAKE, PA 
Location. Dam is on the Cowanesque River about 2.2 
miles above its confluence with Tioga River at Lawrenceville, 
PA. (See Geological Survey map for Tioga, PA.) 
Existing project. The project constructed under the 
Flood Control Act of 1958 provides for an earthfill dam 
3,100 feet long and rising 151 feet above the streambed, 
an uncontrolled spillway in the right abutment, a gated 
conduit in the Valley floor, and flood control storage is 
82,000 acre-feet. Relocation of the Town of Nelson to a 
new townsite was authorized by Section 121 of the Water 
Resources Development Act of 1976. The Federal cost 
of this new work was $106,030,700 of which $61,743,600 
was for construction and $44,287,100 was for lands and 
damages and relocations (which includes $5,755,000 for 
relocation of the Town of Nelson). Within the discretionary 
authority of the Chief of Engineers the project 
was modified in March 1983 in accordance with the 
Water Supply Act of 1958, as amended, and the Flood 
Control Act of 1944, as amended. The modification provides 
for reallocating 25,600 acre-feet of present flood 
control storage for water supply storage by raising the 
permanent pool from elevation 1,045 to 1,080 mean sea 
level. Other features include modifying the existing intake 
tower and two access ramps, stabilizing the reservoir 
slope near the relocated Town of Nelson, replacing 
existing day-use recreation facilities, and expanding both 
day-and overnight-use recreation facilities to accommodate 
an expected increase in annual visitation due to the 
larger pool. Estimated cost (October 1991) of the modification 
is $55,198,000 of which $1,257,000 is Federal (for 
expanded recreation facilities) and $53,941,000 is non- 
Federal (which includes $39,414,000 for reimbursement 
of the cost of existing flood control storage reallocated 
to water supply storage, $13,270,000 cash contribution 
for the water supply modification, and $1,257,000 cash 
contribution for expanded recreation facilities). 
Local cooperation. The Water Resources Development 
Act of 1976, which authorized relocation of the Town of 
Nelson, provides that before the Secretary of the Army 
acquires any real estate property for the new townsite, 
appropriate non-Federal interests shall furnish binding 
contractual commitments that all lots in the new townsite 
will be either occupied when available, replacements 
for open space and vacant lots in the existing town, or 
will be purchased by non-Federal interests at the fair 
market value. The required contractual agreement for 
local cooperation was executed with Nelson Township on 
August 25, 1977. The March 1983 project modification 
(discussed above) requires non-Federal interests repay 
100 percent of the investment cost of project modifications 
allocated to water supply, to terrestrial wildlife 
habitat mitigation, and to in-kind replacement recreation, 
plus the allocated share of the project's original cost 
(escalated to current price levels). Additionally, they are 
required to pay annual costs of operation, maintenance, 
and major replacements allocated to water supply and 
to provide 50 percent of the cost of expanded recreation 
facilities, as well as, all operation, maintenance, and 
replacement costs for the expanded facilities. Water 
supply and recreation contracts were executed by the 
4-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Assistant Secretary of the Army (Civil Works) and the 
Susquehanna River Basin Commission on June 30, 1986. 
Operation and results during fiscal year. New Work: 
Work was completed on modifications to the intake tower 
which completes project construction. Fiscal close-out is 
expected through December 1992. Maintenance: Normal 
operation and maintenance of the project continued. 
33B. TIOGA-HAMMOND LAKES, PA 
Location. The dams are located in Tioga County, PA, 
upstream from the confluence of the Tioga River and 
Crooked Creek. Tioga Dam is located on the Tioga River 
and Hammond Dam on Crooked Creek, approximately 
opposite the Tioga damsite, about 3.3 miles above its 
mouth and less than one mile from the Village of 
Brooklyn. (See Geological Survey map for Tioga, PA.) 
Existing project. Tioga Dam is 2,600 feet long, rising 
140 feet above the streambed, with a controlled outlet 
conduit. Hammond Dam is 5,900 feet long, and has a 
maximum height of 121.5 feet above the streambed, with 
a concrete spillway. Both dams are of earth and rockfill 
construction. The Tioga-Hammond Lakes project controls 
a total drainage area of 402 square miles, with Tioga 
Dam controlling 280 square miles of the Tioga River 
Basin and Hammond Dam controlling 122 square miles 
of the Crooked Creek Basin. Recreation facilities are 
provided for swimming, camping, picnicking, boating, 
and fishing. Federal cost of completed work was 
$185,620,000 of which $125,029,000 is for completed construction 
and $60,591,000 is for lands and damages and 
relocations. Estimated Federal cost (October 1988) of Mill 
Creek recreation facilities (inactive) is $7,500,000. 
Local cooperation. None required on the completed 
portion of the project; however, construction of the Mill 
Creek Area recreation facilities was reclassified to inactive 
(May 16, 1990) since The Mill Creek Project, Incorporated 
was unable to gain private funding for 
construction of specialized facilities, as required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. An additional $50,000 was provided 
in Fiscal Year 1992 to reopen an access road to the Mill 
Creek area of Tioga Lake which had been closed due to 
unsafe conditions. This work has been completed, and the 
road is now open. 
34. WEST BRANCH OF 
SUSQUEHANNA RIVER, PA 
A system of three flood control reservoirs, in the headwaters 
of the West Branch Susquehanna River, PA, are 
known as Curwensville, Alvin R. Bush (formerly known 
as Kettle Creek) and Foster Joseph Sayers (formerly 
known as Blanchard) on the West Branch about 2.5 miles 
upstream from Curwensville, PA; on Kettle Creek 8.4 
miles above the mouth and 17 miles upstream from 
Renovo, PA; and on Bald Eagle Creek about one mile 
upstream from Blanchard, PA, respectively. 
In accordance with the terms of local cooperation, the 
Commonwealth of Pennsylvania furnished assurances 
that it will coordinate operation of George B. Stevenson 
Reservoir (formerly known as First Fork Reservoir) with 
operation of Curwensville, Alvin R. Bush, and Foster 
Joseph Sayers Reservoirs to secure optimum flood 
control benefits from system operation. George B. 
Stevenson Reservoir on the First Fork Sinnemahoning 
Creek in Cameron and Potter Counties, PA, was constructed 
by the Commonwealth of Pennsylvania at a first 
cost of $12,240,000 and an estimated $30,000 annually 
for operation and maintenance. 
34A. ALVIN R. BUSH DAM, PA 
Location. Alvin R. Bush Dam (formerly Kettle Creek 
Dam) is located on Kettle Creek about 8.4 miles above 
the mouth and 15 miles upstream from Renovo, PA. (See 
Geological Survey map for Keating, PA.) 
Existing project. Dam is an earthfill structure,about 
1,350 feet long, rises 165 feet above the streambed, with 
an uncontrolled spillway located in rock adjacent to the 
right abutment, and has a horseshoe-shaped outlet tunnel 
with 3 service gates. The reservoir has a storage capacity 
of 75,000 acre-feet at spillway crest. The project controls 
a drainage area of 226 square miles or about 92 percent 
of the Kettle Creek watershed. Recreation facilities are 
provided for camping, fishing, boating, picnicking, 
hiking, winter sports, hunting, and swimming by the 
State of Pennsylvania at Kettle Creek State Park. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
34B. CURWENSVILLE LAKE, PA 
Location. Dam is on the West Branch of the Susquehanna 
River approximately 2.5 miles upstream from Curwensville, 
Clearfield County, PA. (See Geological Survey 
map for Curwensville, PA.) 
Existing project. Dam is an earthfill structure, about 
1,850 feet long, rises 131 feet above the streambed, and 
has an open-cut concrete sill 1,750 feet from the left abutment. 
The outlet works, located in the left abutment, consist 
of a 15-foot diameter circular outlet conduit with 3 
slide control gates 5.5 feet wide and 12 feet high. The 
reservoir has a storage capacity of 124,200 acre-feet at 
spillway crest. The project controls a drainage area of 
365 square miles, or about 98 percent of the West Branch 
Susquehanna River at Curwensville and about 75 percent 
4-18

BALTIMORE, MD DISTRICT 
at Clearfield. Clearfield County provides recreation including 
boating, fishing, picnicking, and swimming. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
34C. FOSTER JOSEPH SAYERS DAM, PA 
Location. Dam is located on Bald Eagle Creek in Centre 
County, PA, about one mile upstream from Blanchard 
and about 14 miles above the confluence of Bald Eagle 
Creek with the West Branch Susquehanna River at Lock 
Haven, PA. (See Geological Survey map for Howard, PA.) 
Existing project. Dam is an earthfill structure, about 
6,835 feet long, rises 100 feet above the streambed, and 
has an open-cut concrete chute and uncontrolled concrete 
weir 600 feet wide located in rock in a saddle adjacent 
to the left abutment. The outlet works, located in the left 
abutment, consist of a 15-foot diameter circular outlet 
conduit with two hydraulically-operated wheel gates 7 
feet wide and 15 feet high. The reservoir has a storage 
capacity of 99,000 acre-feet at spillway crest. The project 
controls a drainage area of 339 square miles or 88 percent 
of the drainage area above Beech Creek and 43 percent 
of the Bald Eagle Creek drainage area. Recreation facilities 
are provided for boating, camping, fishing, picnicking, 
hunting, swimming, hiking, and winter sports by the 
State of Pennsylvania at Bald Eagle State Park. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. 
35. YORK, INDIAN ROCK DAM, PA 
Location. On Codorus Creek 10 miles above its confluence 
with the Susquehanna River. Codorus Creek has 
tributary branches in York County in the south and 
central parts of Pennsylvania. (See Geological Survey 
Quadrangle sheets, Pennsylvania-York and Hanover.) 
Existing project. Indian Rock Dam is an earth and 
rockfill dam about 1,000 feet long at the top, rising 83 
feet above the streambed, with a reservoir providing for 
control storage of 28,000 acre-feet. Dam is on the main 
branch of Codorus Creek about 3 miles above York. Outlet 
works are in the right abutment and the uncontrolled 
spillway is on the right bank. Reservoir will control entire 
drainage area of the main branch of Codorus Creek and 
41 percent of the drainage area above York. Improvements 
in Codorus Creek in the vicinity of and through the City 
of York provide for 22,969 feet of channel extending from 
300 feet above Richland Avenue to a point downstream 
from the Pennsylvania Railroad crossing known as Black 
Bridge. Improvements, which will increase channel capacity 
to 24,000 cubic feet per second, include widening and 
deepening the channel, bank protection, removal of York 
Roller Mill Dam, and a low water channel about 3,900 feet 
long in the vicinity of York Roller Mill Dam. Cost of new 
work for the completed project was $5,061,167, of which 
$4,566,446 (regular funds) and $11,588 (emergency relief 
funds) were for construction and $483,133 (regular funds) 
was for lands and damages. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938, applies. 
Operations and results during fiscal year. Maintenance: 
Normal operation and maintenance of the 
project continued. Phase II contract for rehabilitation of 
the Codorus Creek was awarded in September 1992. Contract 
work consisted of construction of stop log closure, 
riprap repair, and drainage structure repairs. This work 
is scheduled for completion in fiscal year 1993. 
36. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Projects in New York, Pennsylvania, Maryland, District 
of Columbia, and Virginia were inspected during the 
period by hired labor. See Table 4-I. 
37. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Operations and results during fiscal year. The operation 
of George B. Stevenson Dam, PA, was coordinated 
with the operation of Alvin R. Bush, Curwensville, and 
Foster Joseph Sayers Dams in the West Branch Susquehanna 
River Basin in order to secure optimum flood control 
benefits from the system operation. Costs during the 
period were $46,734. 
Supplemental instructions for the operation of Savage 
River Dam, MD, were provided, during periods of high 
water, to insure maximum protection for downstream 
localities. Costs during the period were $66,393. 
38. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
antecedent legislation). 
Cost for the period was $2,907,607 for the Disaster Preparedness 
Program. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (pre-authorization). 
4-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Fiscal year costs were $56,541 for Gwynns Falls, Baltimore, 
MD; and $48,488 for Paxton Creek, Harrisburg, 
PA. 
Non-Federal contributed costs for the fiscal year were 
$464 for Gwynns Falls, MD. 
Flood control activities pursuant to Section 14, Public 
Law 526, 79th Congress, as amended (pre-authorization). 
Fiscal year costs were $68,247 for Chesapeake Bay, 
Hoopersville, MD; $8,566 for McCreadys Point Rd, MD; 
and $15,122 for Middle Hooper Island, MD 
Water Supply 
39. WASHINGTON AQUEDUCT 
Location. The diversion dam and raw water supply 
intakes at Great Falls, the two collecting conduits, part 
of Dalecarlia receiving reservoir, the booster pumping 
station and the Little Falls raw water pumping station 
are located in Maryland. All other structures of the water 
supply system including parts of the raw water collecting 
system, two purification plants, pumping stations, 
storage reservoirs, and transmission mains are in the District 
of Columbia. Federal owned water mains are maintained 
in Virginia and Maryland. 
Existing project. Control of the water supply system 
is vested in Chief of Engineers (See Acts of March 3, 
1859, and March 2, 1867, November 22, 1973 and Sec. 
1800 of Revised Statutes). The project includes: administration; 
operation and maintenance of the collection, 
purification, pumping, and transmission facilities; protection 
of the water supply system; engineering; and construction 
of major water system additions and 
improvements. 
Authority to supply water to Arlington County, the 
City of Falls Church, and other jurisdictions in Virginia 
is contained in Public Law 119, 69th Congress, approved 
April 14, 1926; and Public Law 118, 80th Congress, 
June 26, 1947. 
Local cooperation. Requirements are described in full 
on page 4-19 of the Fiscal Year 1981 Annual Report. 
Operations and results during fiscal year. An uninterrupted 
and adequate supply of purified water was 
furnished to the District of Columbia; Arlington County, 
and Falls Church, VA; and to Federal establishments in 
the District of Columbia, Arlington County, VA and 
Montgomery and Prince Georges Counties in Maryland. 
Total consumption for Fiscal Year 1992 was 66,878 
million gallons; the maximum daily consumption was 237 
million gallons and average daily consumption was 183 
million gallons. The average amount furnished Arlington 
County and Falls Church, VA was 38.0 million gallons 
per day. The Corps of Engineers was reimbursed in the 
amount of $5,939,067 for water furnished to the Virginia 
communities by the Washington Aqueduct. 
The treated water delivered to the 1.1 million consumers 
served by the Washington Aqueduct met or surpassed 
all Water Quality standards promulgated by the 
U.S. Environmental Protection Agency under the Safe 
Drinking Water Act (P.I. 93-523). 
General Investigations 
40. SURVEYS 
Federal costs for the fiscal year were $1,830,129 of 
which $201,690 was for navigation studies, $1,019,476 
for flood damage prevention studies, -$1,917 for shoreline 
protection studies, $49,525 for special studies, 
$144,200 for review of completed projects, $120,000 for 
special investigations, $27,939 for interagency Water 
Resource development, $4,942 for North American waterfowl 
management plan, and $266,274 for coordination 
with other agencies and non-Federal interests. 
Non-Federal contributed costs for the fiscal year were 
$578,964 of which $435,177 was for flood damage prevention 
studies, $94,088 for review of completed projects, 
and $49,699 for coordination with other agencies and non- 
Federal interests. 
41. COLLECTION AND STUDY OF 
BASIC DATA 
Costs for flood plain management activities and 
general planning guidance during the period was 
$209,751. Providing assistance and guidance to local 
interests on methods and procedures for preventing and 
reducing flood damages was in progress at end of fiscal 
year. 
42. PRE-CONSTRUCTION ENGINEERING 
AND DESIGN 
Curwensville Lake, PA-Reallocation-The recommended 
project includes modification of project features 
to allow reallocating an estimated 5,360 acre-feet of 
storage from conservation to water supply. Contract 
negotiations for a water supply contract were underway 
during the fiscal year. Estimated planning and engineering 
costs is $523,000, which will be repaid by the sponsor 
during the first year of construction. Total costs during 
the fiscal year were $14,886. 
Lackawanna River at Olyphant, PA-The recommended 
project includes about 5,200 feet of levees and 
walls, one closure structure and other minor features to 
protect against a 100-year design flood. Surveying and 
mapping and preparation of a detailed project management 
plan were initiated during the fiscal year. Estimated 
planning and engineering cost is $800,000 pending the 
results of the detailed project management plan. Total 
costs during the fiscal year were $42,119. 
4-20

BALTIMORE, MD DISTRICT 
Lackawanna River at Scranton, PA-The recommended 
project includes about 7,400 feet of levees and 
walls, four closure structures and other minor features 
to protect against a 100-year design flood. Surveying and 
mapping and preparation of a detailed project management 
plan were initiated during the fiscal year. Estimated 
planning and engineering cost is $1,200,000 pending the 
results of the detailed project management plan. Total 
costs during the fiscal year were $72,459. 
Wyoming Valley, PA (Levee Raising)-The authorized 
project provides for raising the existing levees and floodwalls 
between 3 and 5 feet, modifying closure structures, 
relocating utilities, and providing some new floodwalls 
and levees to maintain the system's integrity. The plan 
also includes raising four other local protection projects, 
removing an abandoned railroad bridge, and providing 
non-structural measures to mitigate any significant induced 
damages and the potential of a catastrophic failure 
of an existing project. Preparation of a Phase II General 
Design Memorandum continued during the fiscal year. 
The estimated planning and engineering cost is 
$11,400,000 and costs during the fiscal year were 
$1,674,069. 
Washington, DC & Vicinity-The authorized project 
would provide for raising the grade of a portion of P 
Street, filling an area near the Lincoln Memorial (along 
23rd Street) regrading the area adjacent to 17th Street 
and constructing a removable closure structure across 
17th Street. These measures were authorized to restore 
the design level of protection of the existing project and 
to reduce the need for emergency closure in the event of 
a flood. Preparation of a General Design Memorandum 
was completed during the fiscal year and total costs were 
$71,803. Estimated preconstruction planning cost is 
$2,600,000. 
Moorefield, WV-The authorized project includes 
21,735 feet of earth levee, 1,290 feet of floodwall, replacement 
of the South Branch Valley Railroad bridge, and 
appurtenant project features, such as ramps, closures, 
riprap, and relocations. Preparation of a project design 
memorandum continued during the fiscal year. Estimated 
planning and engineering cost is $2,437,000. Total 
costs during the fiscal year were $754,754. 
Petersburg, WV-The authorized project includes 
19,370 feet of earth levee, 920 feet of floodwall, 35,430 
cubic yards of channel excavation near the Main Street 
bridge, bridge replacement/modification and appurtenant 
project features, such as ramps, closures, riprap, relocations, 
and ponding areas for local drainage. Preparation 
of a project design memorandum continued during the 
fiscal year. Estimated planning and engineering cost is 
$1,802,000. Total costs during the fiscal year were 
$838,317. 
4-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 4-A COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
1. Baltimore Harbor New Work 
& Channels, Approp. 
MD & VA Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
2. Baltimore Harbor Maint. 
MD Collection & Approp. 
Removal of Drift Cost 
3. Bonum Creek, VA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
4. Chester River, MD New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Knapps Narrows, New Work 
MD Approp. 
Cost 
Maint. 
Approp. 
Cost 
6. Nanticoke River, New Work 
MD Approp. 
Cost 
Maint. 
Approp. 
Cost 
7. Ocean City Harbor New Work 
and Inlet and Approp. 
Sinepuxent Bay, MD Cost 
Maint. 
Approp. 
Cost 
Major 
Rehab. 
Approp. 
Cost 
8. Potomac and Maint. 
Anacostia Rivers, Approp. 
DC, Collection & Cost 
Removal of Drift 
9. Potomac River- New Work 
Aquatic Plant Approp. 
Control, MD, Cost 
VA, DC Contributed 
Approp. 
Cost 
10. Potomac River at New Work 
Alexandria, VA Approp. 
Cost 
Maint. 
Approp. 
Cost 
14,100,000 18,096,000 
17,579,367 17,818,943 211,510 
- 142,230,712' 
(50,818) 142,042,0541 
3,748,4852 4,455,0634 13,330,3006 15,983,4628 119,428,6691� 
3,752,0643 4,316,7556 13,277,589' 15,993,6009 119,247,699 � 
13,178,920 12,714,500 
13,769,831 12,690,072 
224,000 
223,999 
337,789 
337,776 
(318,933) 
379,000 
377,288 
30,000 
29,997 
(3,000) 
(2,999) 
(67,500) 
(67,498) 
20,000 
19,623 
5,000 
4,282 
85,000 
85,353 
201,000 
195,687 
(94,300) 65,659,600 
270,795 64,781,728 
329,000 
330,551 
108,000 
98,003 
60,000 
48,284 
458,200 
464,230 
519,000 
517,723 
74,100 
74,100 
516,000 
516,324 
175,000 
257,475 
(20,278) 
27,202 
382,772 
379,284 
565,500 
565,420 
94,000 
(24,925) 
22,003 
169,900 
169,302 
548,100 
546,898 
46,000 
43,907 
596,000 
597,207 
130,000 
116,331 
98,000 
47,307 
5,061,999 
5,061,823 
202,000" 
202,000"11 
282,576 
272,576 
70,49512 
70,49512 
1,803,924 
1,792,184 
46,12113 
46,12113 
2,551,775 
2,551,774 
73,243 
73,243 
568,841 
567,564 
350,19314 
350,19314 
10,376,380 
10,370,201 
4,335,900 
4,335,900 
9,502,775 
9,502,519 
2,123,065 
1,957,787 
291,866 
291,865 
95,214 
95,214 
606,658 
555,892 
4-22

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
11. Potomac River 
below Washington, 
DC 
12. Prevention of 
Obstructions & 
Injurious Deposits, 
Baltimore Harbor, 
MD 
13. Twitch Cove & 
Big Thorofare, MD 
14. Washington 
Harbor, DC 
15. Wicomico River, 
MD 
19. Atlantic Coast 
20. Colonial Beach 
MD 
21. Anacostia River & 
Tributaries, Flood 
Protection & 
Navigation Improve 
ments, DC & MD 
22. Cumberland, MD 
and Ridgeley, 
WV 
23. Isle of Wight 
Bay, Ocean City, 
MD 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
-Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
153,836 
153,836 
55,900 
56,312 
372,000 
372,000 
20,000 
19,996 
742,000 
742,002 
69,320 
68,562 
543,005 
543,005 
13,887 
13,529 
56,252 
55,624 
8,085,000 
5,490,279 
6,417,600 
2,866,545 
47,400 
47,994 
375,000 
374,830 
32,500 
32,240 
49,000 
46,700 
79,000 
76,295 
8,991,000 
9,499,409 
2,215,100 
4,846,249 
16,260 
12,117 
56,000 
54,164 
72,000 
72,000 
313,800 
231,421 
127,612 
85,083 
68,184 
68,184 
7,500 
87,450 
2,500 
41,119 
75,000 
72,264 
500,000 
515,671 
3,910 
57,000 2,206,294 
54,432 2,203,547 
365,000 6,640,045 
365,170 6,460,045 
- 193,175 
- 193,175 
862,000 3,448,911 
812,541 3,399,192 
- 3,191,07715 
- 3,191,077 5 
68,600 5,025,783 ' 6.1'7 
71,262 5,025,78316.1'7 
- 471,60918 
- 471,60918 
153,000 8,351,989 
156,332 8,351,988 
3,400,000 
5,213,051 
3,127,797 
3,214,978 
1,409 
20,476,000 
20,202,739 
11,760,497 
10,927,772 
535,260 
531,556 
414,977 
414,977 
6,042,325 
6,042,325 
140,000 1,645,65519 
129,242 1,633,06119 
- 15,633,970 
- 15,633,970 
82,000 1,071,413 
84,735 1,071,412 
71,400 
71,207 
973,200 
972,988 
130,112 
130,112 
4-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
24. Jennings Randolph 
Lake, MD & WV 
25A. Aylesworth Lake 
Creek, PA 
26. Lock Haven, PA 
27. Raystown Lake, 
Raystown Branch, 
Juniata River, PA 
28A. Addison, NY 
28B. Almond Lake, 
NY 
28C. Arkport Dam, 
NY 
28D. Avoca, NY 
28E. Binghamton, NY 
28F. Canisteo, NY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- - - 2,310 
1,224,200 1,272,444 1,284,900 1,332,000 
1,247,520 1,264,520 1,229,745 1,384,577 
214,000 
213,962 
105,321 
99,214 
102,700 
107,217 
1,045,000 5,500,000 
925,615 4,532,728 
- 12,637,000 
169,000 
169,541 
16,212,000 
15,090,644 
1,996,495 
2,237,274 
176,325,300 
176,324,093 
13,103,122 
13,091,699 
2,320,400 
2,320,400 
1,784,523 
1,783,373 
22,757,000 
20,548,935 
14,633,495 
2,237,274 
- - - - 77,408,770 
- - - - 77,408,770 
2,568,100 2,358,655 2,761,000 3,056,000 32,986,815 
2,587,911 2,342,366 2,716,846 3,098,539 32,975,205 
13,800 
13,780 
322,000 
323,338 
142,000 
141,763 
9,100 
9,098 
30,000 
50,271 
30,700 
30,700 
42,400 
42,368 
9,700 
9,430 
301,106 
295,354 
138,638 
138,743 
8,300 
6,285 
26,200 
24,087 
45,800 
44,160 
24,000 
23,801 
313,400 
318,055 
147,000 
147,298 
4,000 
3,840 
17,000 
18,770 
18,000 
15,218 
11,100 
11,588 
351,000 
351,775 
171,000 
170,494 
13,200 
13,377 
38,200 
36,542 
45,900 
50,331 
827,050 
827,050 
252,755 
252,754 
5,760,211 
5,760,211 
4,942,681 
4,941,931 
1,910,00020 
1,910,00020 
2,531,712 
2,530,714 
436,37421 
436,37421 
455,761 
455,760 
3,460,00022 
3,460,00022 
569,981 
569,980 
1,183,11123 
1,183,11123 
843,135 
843,099 
4-24

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
28G. Corning, NY 
28H. East Sidney Lake, 
NY 
28I. Elmira, NY 
28J. Hornell, NY 
28K. Lisle, NY 
28L. Oxford, NY 
28M. Whitney Point 
Lake, NY 
28N. Whitney Point 
Village, NY 
29. Solomon Creek, 
Ashley Borough, 
Luzerne Co, PA 
30. Solomons Island, 
Calvert Co, MD 
Luzerne Co. PA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
26,700 
26,655 
1,130,600 
1,130,829 
12,100 
12,100 
50,200 
49,386 
690,852 
690,098 
15,500 
14,825 
48,530 
49,112 
341,700 
431,023 
8,600 
9,200 
267,400 1,469,293 2,007,150 
267,337 1,453,919 2,020,870 
3,200 
31,998 
11,000 
11,000 
731,700 
733,420 
20,100 
20,098 
19,200 
18,895 
11,200 
10,384 
43,000 
43,051 
10,000 
9,949 
582,717 1,068,000 
582,411 1,047,249 
18,600 
17,986 
10,020 
10,422 
53,000 
53,189 
374,000 
372,058 
19,000 
19,075 
578,900 
573,242 
34,200 
34,456 
13,000 
13,867 
3,939 
1,166,139 
18,000 
18,215 
71,000 
12,552 
17,300 
135,300 
14,779 
90,625 
4-25 
3,322,00024 
3,322,00024 
913,888 
913,800 
6,049,504 
6,049,504 
6,727,771 
6,813,998 
6,883,305 
6,883,305 
355,249 
355,249 
4,558,69825 
4,558,69825 
8,121,276 
8,113,897 
661,19926 
661,19926 
821,722 
821,722 
131,00027 
131,00027 
260,932 
260,932 
5,421,539 
5,421,539 
7,417,296 
7,558,009 
424,096 
424,096 
423,281 
423,282 
71,000 
12,552 
17,300 
135,300 
14,779 
90,625

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project 
31. Spring Brook 
Creek, Pittston 
Twp, PA 
32. Stillwater Lake, 
Lackawanna River, 
PA 
33A. Cowanesque Lake, 
PA 
33B. Tioga-Hammond 
Lakes, PA 
34A. Alvin R. Bush 
Dam, PA 
34B. Curwensville Lake, 
PA 
34C. Foster Joseph 
Sayers Dam, PA 
35. York, Indian Rock 
Dam, PA 
Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
New Work 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Contributed 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
287,000 
20,976 
315,000 
392,400 
393,128 
(524,248) 
1,110,400 
1,111,622 
5,341,000 
5,572,939 
3,779 
1,333,600 
1,337,198 
426,000 
427,276 
449,600 
450,171 
550,300 
551,937 
617,400 
617,951 
270,535 
150,653 
316,681 
314,459 
(837,120) 
1,168,627 
1,156,918 
1,121,308 
2,070,014 
63,588 
1,607,989 
1,596,890 
494,354 
494,304 
674,587 
669,293 
488,524 
488,594 
1,001,663 
997,228 
11,500 
(35,676) 
264,700 
266,368 
(1,114,000) 
80,532 
2,009,000 
1,273,953 
568,068 
1,574,600 
1,580,952 
552,300 
546,086 
479,200 
482,625 
519,900 
519,084 
1,153,700 
1,155,730 
61,500 
59,624 
19,570 
292,000 
283,740 
(170,000) 
240 
1,425,000 
1,427,617 
190,682 
148,389 
8,575 
1,786,400 
1,786,728 
436,000 
445,696 
461,000 
459,947 
563,000 
557,431 
525,300 
520,719 
1. Includes $8,764,003 for previous project. 
2. Includes $310,485 for sections of project in Norfolk 
District. 
3. Includes $314,269 for sections of project in Norfolk 
District. 
4. Includes $96,594 for sections of project in Norfolk 
District. 
5. Includes $94,883 for sections of project in Norfolk 
District. 
6. Includes $230,660 for 
District. 
7. Includes $221,674 for 
District. 
sections of project in Norfolk 
sections of project in Norfolk 
8. Includes $1,955,262 for sections of project in Norfolk 
District. 
9. Includes $1,961,340 for sections of project in Norfolk 
District. 
10. Includes $399,802 for previous projects. 
4-26 
420,000 
413,357 
315,000 
134,547 
5,725,700 
5,725,700 
3,789,590 
3,780,377 
107,576,700 
107,574,623 
11,567,581 
11,549,388 
13,504,759 
13,388,613 
19,244,800 
19,244,800 
17,988,243 
17,982,568 
7,103,001 
7,103,001 
8,279,076 
8,288,443 
20,396,060 
20,396,060 
10,314,576 
10,310,507 
30,887,06328 
30,887,06328 
9,713,108 
9,705,876 
5,061,16729 
5,061,16729 
10,646,28030 
10,643,77030

BALTIMORE, MD DISTRICT 
TABLE 4-A (Continued) COST AND FINANCIAL STATEMENT 
See Total 
Section to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
11. Excludes $3,998 contributed funds. 21. Includes $109,944 emergency relief funds. 
12. Includes $38,041 for previous project. 22. Excludes $163,096 contributed funds. 
13. Includes $46,121 public works funds. 23. Includes $207,520 rehabilitation funds. 
14. Includes $283,008 public works funds and $67,185 24. Excludes $34,729 contributed funds. 
emergency relief funds; excludes $500,000 contributed funds. 25. Includes $250,899 emergency relief funds and excludes 
15. Includes $3,029,001 for previous project. $15,000 contributed funds. 
16. Includes $1,831,609 for previous project. 26. Includes $71,557 emergency relief funds. 
17. Excludes $4,000 for emergency dredging under provi- 27. Includes $73,465 emergency relief funds. 
sions of Section 3, 1945 River and Harbor Act. 28. Excludes $263,900 contributed funds in accordance 
18. Includes $50,000 for previous project and excludes with the Tri-party Agreement for construction of a sanitary sys- 
$14,000 contributed funds. tem for public use. 
19. Includes $49,998 emergency relief funds. 29. Includes $11,588 emergency relief funds. 
20. Includes $62,577 emergency relief funds. 30. Includes $15,000 for deferred maintenance. 
TABLE 4-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
BALTIMORE HARBOR AND CHANNELS, MD and VA 
Aug. 8, Branch channel 35 feet deep to head of Curtis Bay, and one 35 feet deep and 
1917 400 feet wide Fort McHenry to Port Covington entrance channel, thence 
150 feet wide to Ferry Bar, and thence 27 feet deep and 150 feet wide to 
Hanover Street Bridge, widen approaches and bends, and enlarge anchorage 
basin near entrance. Inclusion of Patapsco River and tributaries into one 
project for Baltimore Harbor.' 
Jan. 21, Change in location of anchorage near upper end of Fort McHenry Channel. 
1927 
Jul. 3, 
1930 
Increased anchorage facilities. 
Jul. 3, For 37-foot depth in that portion of channel to Baltimore lying between 37-foot 
1930 depth curve near Baltimore Light to Sparrows Point entrance channel; widen 
angle between Fort McHenry and Ferry Bar section; and for width of 400 
feet in Curtis Bay section. 
Oct. 17, For 22-, 18-, and 15-foot channels in Curtis Creek from 22-foot depth below 
1940 Pennington Avenue Bridge to upper end of marginal wharf of U.S. Ordinance 
Depot. 
Mar. 2, Uniform main channel 39 feet deep from the ocean through York Spit section 
1945 and Craighill entrance to Fort McHenry, additional anchorage area, 2,400 
feet long, 1,200 feet wide, and 30 feet deep; a connecting channel 400 feet 
wide and 27 feet deep from Cutoff Brewerton Angle in main channel to Inland 
Waterway from Delaware River to Chesapeake Bay; a channel in Curtis Creek 
200 feet wide and 35 feet deep from head of existing 35-foot project channel 
in Curtis Bay to a point in the creek about 750 feet below Pennington 
Avenue Bridge. 
Mar. 2, A channel 22 feet deep and 200 feet wide from 22-foot depth curve south of 
1945 Baltimore & Ohio R.R. bridge about 2,800 feet to vicinity of Arundel Cove, 
thence 100 feet wide in Arundel Cove for about 2,100 feet; with an anchorage 
basin about 700 feet square adjacent to channel southwesterly of Coast 
Guard wharf. 
H. Doc. 799, 
64th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 11, 
70th Cong., 1st Sess. 
H. Doc. 86, 
85th Cong., 1st Sess. 
Adopted as a national 
defense project. (No 
printed report.) 
H. Doc. 741, 
79th Cong., 2nd Sess. 
In accordance with 
plans on file in the 
Office, Chief of 
Engineers 
4-27 
1.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 3, Main channel 42 feet deep and 1,000 feet wide in Cape Henry section at 
1958 entrance to Chesapeake Bay and in York Spit section; 42 feet deep and 800 
feet wide in Rappahannock Spit section and in approach channel to Baltimore 
Harbor from Craighill entrance to Fort McHenry, with widening at entrance 
and bends; channels 42 feet deep and 600 feet wide in Curtis Bay and Ferry 
Bar sections of harbor; a connecting channel 35 feet deep and 600 feet wide 
from main channel to approach channel to Chesapeake and Delaware Canal; 
and for three disjointed sections of channels of same depth and width in 
Chesapeake Bay leading to Chesapeake and Delaware Canal; and to provide 
Federal maintenance of 39-foot depth in Northwest Branch, in areas dredged 
to that depth by local interests. 
Dec. 31, Deepening of the Cape Henry Channel to 50 feet at the existing width of 
1970 1,000 feet, with widening at bends; deepening of the Spit Channel to 50 feet 
at the existing width of 1,000 feet, with widening at bends; enlargement of 
the Rappahannock Shoal Channel to a depth of 50 feet and a width of 1,000 
feet; deepening of the main ship channel from Chesapeake Bay to Fort 
McHenry to a depth of 50 feet at the existing width of 800 feet, with widening 
at bends and at the Craighill Entrance; deepening of the Curtis Bay Channel 
to a depth of 50 feet at the existing width of 600 feet, and deepening of the 
950-foot wide and 980-foot long turning basin at the head of channel to the 
same depth; deepening of the Northwest Branch-East Channel to a depth 
of 49 feet from the depth existing at the time of construction at a width of 
600 feet, and deepening of the 950-foot wide and 950-foot long turning basin 
at the head of the channel to the same depth; and deepening and extension 
of the Northwest Branch-West Channel to a depth of 40 feet from the depth 
existing at the time of construction, at a width of 600 feet, and with an 
irregularly shaped turning basin at the head of the channel 40 feet deep and 
about 2,000 feet long with a maximum width of 1,150 feet. 
BALTIMORE HARBOR, MD-COLLECTION AND REMOVAL OF 
DRIFT 
Jun. 30, Collection and removal of drift from Baltimore Harbor and its tributary 
1948 waters. 
May 12, 
1966 
Sec. 107 
Jul. 14, 
1960 
Mar. 3, 
1873 
Sep. 19, 
1980 
Jun. 30, 
1948 
BONUM CREEK, VA 
A channel 60 feet wide and 6 feet deep from that depth in the Potomac River 
to and including an anchorage basin of the same depth, 160 feet wide and 
200 feet long. Protection of the entrance channel on both sides by jetties. 
The north jetty is about 700 feet long and south jetty is about 300 feet long. 
CHESTER RIVER, MD 
A channel 7 feet deep at mean low water and 100 feet wide from Chester 
River to Eastern Bay through Kent Island Narrows. 
A channel 6 feet deep at mean low water and 60 feet wide from Crumpton 
to Jones Landing. 
A channel 7 feet deep at mean low water and 75 feet wide extending from 
the 7-foot depth in Kent Island Narrows 800 feet into Wells Cove with a 
basin of the same depth and 300 feet square at the head of the channel. 
KNAPPS NARROWS, MD 
Aug. 30, A channel 9 feet deep at mean low water, 75 feet wide, widened at the bends 
1935 from deep water in Chesapeake Bay in deep water in Harris Creek, MD 
with a turning basin west of the drawbridge, 7 feet deep at mean low water, 
about 320 feet long and 120 feet wide. Project channel was authorized by 
the Public Works Administration September 16, 1933 and later adopted by 
1935 River and Harbor Act. 
NANTICOKE RIVER, MD 
Aug. 26, A small boat harbor 7 feet deep, 120 feet wide, and 400 feet long in the 
1937 marsh at Nanticoke with an entrance channel of the same depth and 60 
feet wide protected on either side by stone jetties in the river. 
H. Doc. 86, 
85th Cong., 1st Sess. 
H. Doc. 181, 
94th Cong., 1st Sess. 
River and Harbor Act 
of 1948 
Detailed Project 
Report, 
August 1965 
E. Doc. 25, 
42d Cong., 3d Sess. 
H. Ex. Doc. 65, 
51st. Cong., 1st Sess. 
H. Doc. 380, 
80th Cong., 1st Sess.2 
H. Doc. 308, 
72nd Cong., 1st Sess. 
H. Doc. 242, 
75th Cong., 1st Sess.2 
4-28 
5. 
6.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
OCEAN CITY HARBOR & INLET & SINEPUXENT BAY, MD 
Aug. 30, Construction of an inlet between the Atlantic Ocean and Sinepuxent Bay, 
19353 10 feet deep and 200 feet wide, protected by jetties; a channel 8 feet deep 
and 100 feet wide from the inlet to Ocean City, 6 feet deep and 150 feet 
wide to Green Point, and 100 feet wide into Chincoteague Bay. 
Aug. 30, Modification providing a 10-foot by 100-foot channel from the inlet to the 
19354 west side of the bay with two turning basins; a channel 6 feet deep and 125 
feet wide from the inlet channel to opposite North 8th Street, Ocean City, 
and 75 feet wide into Isle of Wight Bay. 
Sep. 3, Modification providing for raising the north jetty to an elevation 9 feet 
19455 above mean low water, and a channel 300 feet wide and 16 feet deep from 
the ocean through the inlet to the Isle of Wight Bay Channel, thence 200 
feet to the project harbor, and a depth of 14 feet in the project harbor. Channel 
depths refer to project datum. 
POTOMAC & ANACOSTIA RIVERS, DC-COLLECTION & 
REMOVAL OF DRIFT 
Oct. 27, Collection and removal of drift from waters of the Potomac and Anacostia 
1965 Rivers and their tributaries in the Washington, DC area from the head of 
the tidewater to Mount Vernon, VA. 
POTOMAC RIVER AQUATIC PLANT CONTROL, MD, VA, DC 
Jul. 2, Control of Hydrilla and other nuisance plants using mechanical harvesting 
1986 to clear a 60 foot wide, 6 foot deep connecting channel from open waters to 
eligible public use areas. 
POTOMAC RIVER AT ALEXANDRIA, VA 
Jun. 25, A channel 6,700 feet long and averages 300 feet wide for depth of 24 feet in 
1910 front of Alexandria between the through channel and a line drawn 20 feet 
outside of established pierhead line. 
POTOMAC RIVER BELOW WASHINGTON, DC 
Mar. 3, A channel 24 feet deep and 200 feet wide between mouth at Chesapeake Bay 
1899 and Giesboro Point at Washington, DC, a distance of 108 miles. 
PREVENTION OF OBSTRUCTIONS & INJURIOUS DEPOSITS, 
BALTIMORE HARBOR, MD 
Aug. 28, Continuous patrol and inspection of Baltimore Harbor, Chesapeake Bay, 
1958 and its tributaries to prevent and detect violations, and issue permits as 
required for transporting and depositing waste materials in navigable 
waters. (The project is limited to the tidal waters of Chesapeake Bay and 
its tributaries that lie within the State of Maryland.) 
TWITCH COVE AND BIG THOROFARE, MD 
Jul. 25 A channel 4 feet deep and 25 feet wide from Tangier Sound into Big Thorofare 
1912 River, and one of same dimensions around point between said river and Tyler 
River. 
WASHINGTON HARBOR, DC 
Aug. 30, Provides for: (a) Virginia Channel, from Giesboro Point to area for 25,000 
1935 square feet; (b) Washington Channel, from Haines Point to head of Washington 
Channel, 24 feet deep and 400 feet wide; (c) Anacostia River from 
Giesboro Point to Anacostia Bridge, 24 feet deep and 400 feet wide, with 
turning basin 800 feet wide and about 2,400 feet long of same depth opposite 
Naval Weapons Plant; (d) Anacostia River from Anacostia Bridge 24 feet 
deep and 200 feet wide to turning basin 400 feet square of same depth at 
foot of 15th Street SE Channel lengths including turning basins are: Virginia 
Channel, 25,000 feet; Washington Channel, 10,000 feet; and Anacostia River, 
15,000 feet; and (e) operation and maintenance of inlet gates and lock and 
outlet gates of Tidal Basin constructed under a previous project to flush 
Washington Channel. 
Rivers and Harbors 
Committee Doc. 38, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 60, 
74th Cong., 1st Sess. 
H. Doc. 444, 
82nd Cong., 2nd Sess. 
H. Doc. 286, 
89th Cong., 1st Sess. 
State Design 
memorandum 
July 2, 1986 
H. Doc. 1253, 60th 
Cong., 2nd Sess. 
H. Doc. 33, 
52nd Cong., 1st Sess. 
River and Harbor Act, 
June 29, 1888 as 
amended by Public 
Law 85-802, dated 
August 28, 1958 
H. Doc. 285, 
62nd Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 22, 
74th Cong., 1st Sess.2 
4-29 
8. 
9. 
10. 
11. 
12. 
13. 
14.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 4-B (Continued) 
See Date 
Section Authorizing 
in Text Act 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
15. 
Sep. 19, 
1890 
Jun. 25, 
1910 
Mar. 2, 
1919 
Jul. 3, 
1930 
Aug. 26, 
1937 
WICOMICO RIVER, MD 
Channel 9 feet deep from Main Street Bridge to about 2 miles below. 
Extend 9-foot depth into north prong from Main Street Bridge to the 
Salisbury Dam and turning basin. 
Extend 9-foot depth into south prong to head of navigation at Cathell Street, 
including a turning basin, and extend project down to mouth of river in 
Monie Bay. 
A 12-foot channel below the Main Street Bridge. 
A 14-foot channel, 150 feet wide; depths of 14 feet in the north and south 
prongs and a basin 6 feet deep at Webster Cove and approach channel 
thereto of the same depth. 
Sep. 3, Enlarge existing basin at Webster Cove, by dredging an extension 6 feet 
1954 deep, 100 feet wide, and 200 feet long on each side of existing basin to 
form a T-shaped harbor. 
ATLANTIC COAST OF MARYLAND 
Nov. 17, Consists of a dune beginning at 27th Street extending north to the Delaware 
1986 line; a steel sheetpile bulkhead from 27th Street south to Fourth Street; and 
widened and raised beach from Third Street to just beyond the Delaware line. 
COLONIAL BEACH, VA 
Sept. 15, Extending and widening the existing Central Beach area, stabilizing the bank 
1980 behind the beachfill with vegetation, and constructing four segments of 
offshore breakwater; and extending and widening of the existing Castle Beach 
area, constructing three segments of offshore breakwater, removing debris 
in the beachfill area, and constructing a 100-foot long terminal groin at the 
southern end of Castlewood Park beachfill. 
ANACOSTIA RIVER & TRIBUTARIES, FLOOD PROTECTION & 
NAVIGATION IMPROVEMENTS, D.C. & MD. 
May 17, Channel improvements, levees, pumping stations with connecting storm 
1950 sewers, pressure conduit and relocation and reconstruction of 4 highway 
bridges and 1 railroad bridge. 
CUMBERLAND, MD AND RIDGELEY, WV 
Jun. 22, 
1936 
Jul. 24, 
1946 
Oct. 6, 
1988 
Sec. 14 
Oct. 23, 
1962 
Levees, retaining walls, movable dam, and channel clearing for Cumberland, 
West Cumberland and South Cumberland, MD and Ridgeley, WV. 
Levees, wall, channel improvement, remove Chesapeake and Ohio Canal 
Dam and construct new industrial dam. 
ISLE OF WIGHT BAY, OCEAN CITY, MD 
Consists of the placement of 3,500 linear feet of steel sheetpile bulkhead 
along Chicago Avenue. 
JENNINGS RANDOLPH LAKE, MD & WV 
Construction of Bloomington Lake project. 
LACKAWANNA RIVER BASIN, PA 
Oct. 23, Construction of Aylesworth Creek Lake, Fall Brook Lake, and local pro- 
1962 tection works on Lackawanna River at Scranton, Pennsylvania. 
H. Doc. 20, 
51st Cong., 1st Sess., 
and Annual Report 
1890, p. 947, 
H. Doc. 569, 
61st Cong., 2nd Sess. 
H. Doc. 1509, 
63rd Cong., 3rd Sess. 
Senate Committee 
Print, 75th Cong., 
3rd Sess.2 
H. Doc. 619, 
81st Cong., 2nd Sess. 2 
Report of the Chief of 
Engineers dated 
Sept. 29, 1981 
Detailed Project 
Report, May 1980 
H. Doc. 202, 81st 
Cong., 1st Sess. 
H. Doc. 101, 
73rd Cong., 1st Sess. 
Report on file in 
Office, Chief of 
Engineers. 
Initial Appraisal 
Report Jul. 1986 
H. Doc. 469, 
87th Cong., 2nd Sess. 
S. Doc. 141, 
87th Cong., 2nd Sess. 
4-30 
Documents 
19. 
20. 
21. 
22. 
23. 
24. 
25.

BALTIMORE, MD DISTRICT 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
LOCK HAVEN, PA 
Nov. 17, Consists of 36,600 feet of levee and 1,000 feet of concrete floodwall along 
1986 the West Branch and Bald Eagle Creek, five closure structures, seven ponding 
areas, a sanitary pumping station, 35 gravity type drainage structures, 
necessary road and utility relocations, non-structural measures for Woodward 
and Allison Townships, and minor recreation facilities. 
Oct.23, 
1962 
Jun. 22, 
1936 
modified 
by Acts 
of Jun. 
28, 1938; 
Aug. 18, 
1941; 
Dec. 22, 
1944; 
May 17, 
1950; and 
Jul. 3, 
1958 
RAYSTOWN LAKE, RAYSTOWN BRANCH, JUNIATA RIVER, PA 
Construction of dam and appurtenant facilities. 
SOUTHERN NEW YORK FLOOD CONTROL PROJECTS 
Construction of detention reservoirs and related flood control works for 
protection of Binghamton, Hornell, Corning and other towns in New York 
and Pennsylvania. 
SOLOMON CREEK, ASHLEY BOROUGH, LUZERNE CO, PA 
July 11, Consists of restoration which will include the placement of compacted back- 
1988 fill material and the construction of a gabion wall approximately 24 feet 
in length along the alignment of the collapsed stone masonry wall. 
SOLOMONS ISLAND, CALVERT COUNTY, MD 
July 11, Construction of a stone revetment along the 500-foot reach of shoreline in 
1988 order to stabilize the deteriorating steel bulkhead and prevent roadway 
subbase material from moving through the revetment. 
Jan. 26, 
1989 
Sec. 14 
Aug. 18, 
1941 
SPRING BROOK CREEK, PITTSTON TOWNSHIP, PA 
Consists of the excavation and backfilling of the existing streambank and 
placement of approximately 870 feet of stone riprap. 
STILLWATER LAKE, LACKAWANNA RIVER, PA 
Construction of a flood control reservoir. 
SUSQUEHANNA RIVER FLOOD CONTROL PROJECTS, NY AND PA 
Jul. 3, Construction of Cowanesque and Tioga-Hammond reservoirs, local flood 
1958 protection works at Elkland, PA, and Nichols, NY and channel improvement 
at Cortland, NY. 
Oct. 22, Modification in connection with the construction of Cowanesque Lake to 
1976 relocate the Town of Nelson, PA, to a new townsite. 
Mar. 1, Modification of Cowanesque Lake to include water supply as provided by 
1983 Section 4 of the Flood Control Act of 1944 (PL 78-534) and Section 301 of 
Water Supply Act of 1958 (PL 85-500). 
Sep. 3, 
1954 
WEST BRANCH OF SUSQUEHANNA RIVER, PA 
Construction of three flood control reservoirs. 
27. 
28. 
4-31 
26. 
H. Doc. 187, 
98th Cong., 
H. Doc. 565, 
87th Cong., 2nd Sess. 
H. Doc. 702, 
77th Cong., 2nd Sess. 
Feasibility Report, 
August 25, 1989 
Detailed Project 
Report, May 31, 1989 
Initial Appraisal 
Report Nov. 1985 
H. Doc. 702, 
77th Cong., 2nd Sess. 
H. Doc. 394, 
84th Cong., 2nd Sess. 
H. Doc. 29, 
84th Cong., 1st Sess. 
29. 
30. 
31. 
32. 
33. 
34.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 4-B (Continued) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
35. YORK, INDIAN ROCK DAM, PA 
Jun. 22, Construction of Indian Rock Dam and channel improvements on Codorus H. Doc. 702, 
1936 Creek. 77th Cong., 2nd Sess. 
1. Exclusive of portion considered inactive. Inactive por- September 16, 1933. The site chosen for the inlet under this 
tion is widening 35-foot depth channel from 150 to 400 feet from authorization was that opened just south of Ocean City by 
Port Covington to Ferry Bar, widening 27-foot depth channel natural forces during a severe storm in August 1933. This 
from 150 to 250 feet to Hanover Street Bridge, and providing eliminated the necessity for an 8-foot channel from the inlet to 
a channel 27 feet deep by 250 feet wide to Western Maryland Ocean City. 
Railway Bridge with an anchorage and turning basin at the 4. Included in Emergency Relief program 1935. 
upper end. 5. Raising of the north jetty to an elevation of 9 feet above 
2. Contains latest published maps. mean low water was accomplished with maintenance funds in 
3. Included in Public Works Administration program 1956. 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Annapolis Harbor, MD 
Accotink Creek, VA2 
Anacostia River and Flats3 
Aquia Creek, VA 
Back Creek, MD 
Black Walnut Harbor, MD 
Branson Cove, 
Lower Machodoc River, VA 
Breton Bay, MD5 
Broad Creek River, DE 
Broad Creek, MD 
Cambridge Harbor, MD 
Choptank River, MD8 
Claiborne Harbor, MD 2 
Corsica River, MD 
Crisfield Harbor, MD 
Cypress Creek, MD 
Duck Point Cove, MD 
Elk and Little Elk Rivers, MD'1 
Fishing Bay, MD 
Fishing Creek, MD 
Goose Creek, MD' 5 
Herring Bay and Rockhold Creek, MD 
Herring Creek, MD 
Honga River and Tar Bay, MD 
Island Creek, MD 
Island Creek, St. Georges Island, MD 
Completed 
Completed 
Deferred 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1991 
1878 
1953 
1928 
1946 
1982 
1950 
1950 
1964 
1962 
1991 
1979 
1987 
1948 
1990 
1947 
1982 
1932 
1990 
1991 
1973 
1989 
1989 
1990 
1948 
1988 
$ 34,250' 
5,000 
3,910,582 
52,4654 
23,061 
32,631 
15,755 
47,9245 
64,5106 
28,227 
195,9747 
96,796 
42,974 
39,0719 
349,154' 0 
3,057 
25,289 
90,12112 
33,87414 
111,242 
75,900 
50,591 
1,506,259 
66,11916 
6,230 
23,836 
$ 45,352 
11,770 
41,378 
431,478 
17,675 
12,621 
133,088 
104,215 
930,668 
94,095 
681,933 
106,565 
1,771,351 
14,729 
334,396 
53,80813 
1,580,960 
1,841,803 
8,312 
769,550 
148,329 
41,148,167 
54,828 
478,035 
4-32

BALTIMORE, MD DISTRICT 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C (Continued) 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
La Trappe, MD Completed 1980 8,06417 40,475 
Little Creek, Kent Island, MD Completed 1958 23,000 7,327 
Little Wicomico River Completed 1991 81,88518 1,747,479 
Lowes Wharf, MD Completed 1986 2,100 322,080 
Lower Machodoc Creek, VA Completed 1904 9,916 25,143 
Lower Thorofare, Deal Island, MD Completed 1988 1,787,15819 640,938 
Madison Bay, MD"15 Completed 1977 125,550 33,353 
Manokin River, MD 20 Completed 1919 34,78821 43,534 
Middle River and Dark Head Creek, MD Completed 1947 38,71522 50,934 
Monroe Bay and Creek, VA Completed 1989 12,460 387,685 
Muddy Hook and Tyler Coves, MD Completed 1990 64,001 666,075 
Nan Cove, MD4 Completed 1965 34,86123 22,498 
Nanticoke River at Bivalve, MD 12 Completed 1983 240,817 142,131 
Nanticoke River (Including Northwest Fork) 
DE and MD Completed 1990 143,13424 1,097,524 
Neabsco Creek, MD Completed 1978 14,600 14,800 
Neale Sound, MD Completed 1991 12,60025 903,450 
Neavitt Harbor, MD 15 Completed 1968 36,500 34,533 
Nomini Bay and Creek, VA 26 Completed 1946 78,446 42,063 
Northeast River, MD Completed 1984 28,48927 937,074 
Occoquan Creek, VA" Completed 1971 66,25328 203,198 
Parish Creek, MD Completed 1988 19,17029 525,886 
Patuxent River, MD" Completed 1905 14,0003� - 
Pocomoke River, MD31 Completed 1990 191,72632 2,045,392 
Potomac River and Tributaries at and 
below Washington, DC, Elimination 
of Waterchestnut Completed 1977 - 184,394 
Potomac River at Lower Cedar Point, MD Completed 1920 10,234 6,216 
Potomac River at Mt. Vernon, VA" Completed 1984 17,000 331,219 
Potomac River North Side 
of Washington Channel, DC2 Completed 1956 1,744,69233 27,46134 
Queenstown Harbor, MD Completed 1985 72,85835 321,803 
Rhodes Point to Tylerton, MD Completed 1988 304,000 1,003,857 
Rock Hall Harbor, MD Completed 1982 1,072,50036 71,059 
Shad Landing State Park, MD Completed 1966 33,53137 19,198 
Shallow Creek, MD 15 Completed 1989 278,100 - 
Slaughter Creek, MD Completed 1987 4,140 615,897 
St. Catherines Sound, MD Completed 1989 29,94738 648,618 
St. Georges Creek, MD Completed 1985 147,650 - 
St. Jeromes Creek, MD Completed 1991 44,35739 719,788 
St. Michaels Harbor, MD 15 Completed 1964 16,72340 14,403 
St. Patricks Creek, MD Completed 1987 15,752 141,506 
St. Peters Creek, MD15 Completed 1963 46,7404' 31,716 
Smith Creek, MD Completed 1936 5,252 16,448 
Susquehanna River 
above and below Havre De Grace, MD Completed 1985 293,57042 849,350 
Susquehanna River at Williamsport, PA5 Completed 1974 57,0314s 41,437 
Tilghman Island Harbor, MD Completed 1983 424,800" 395,785 
Town Creek, MD Completed 1950 43,220 41,959 
Tred Avon River, MD Completed 1988 523,310 845,243 
Tuckahoe River, MD Completed 1980 9,727 23,489 
Twitch Cove and 
Big Thorofare, MD Completed 1988 193,175 2,574,002 
Tyaskin Creek, MD Completed 1923 16,297"' 54,302 
Upper Machodoc Creek, VA Completed 1971 20,281 34,777 
4-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
OTHER AUTHORIZED NAVIGATION PROJECTS 
TABLE 4-C (Continued) 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Upper Thorofare, MD Completed 1987 62,446 814,657 
Warwick River, MD Completed 1984 22,04146 148,728 
1. Includes $8,476 for previous projects. 
2. Unconstructed portion of the project was deauthorized 
August 5, 1977. 
3. Project deferred for restudy. 
4. Includes $31,065 for previous project. 
5. Includes $37,500 for previous project. 
6. Includes $50,000 for previous project. 
7. Excludes $3,998 contributed funds and includes 
$61,321 for previous projects. 
8. Authorization for the unconstructed portion of the 
project was withdrawn by the Chief of Engineers January 22, 
1979. 
9. Includes $30,000 for previous project. 
10. Includes $87,740 for previous project. 
11. Unconstructed portion of the project was deauthorized 
November 2, 1979. 
12. Includes $79,626 for previous project and excludes 
$8,414 contributed funds. 
13. Includes $24,321 for previous project. 
14. Includes $2,839 for previous project. 
15. Authorized by Chief of Engineers. 
16. Excludes $2,200 contributed funds and includes 
$27,668 emergency relief funds. 
17. Excludes $1,100 contributed funds. 
18. Excludes $5,000 contributed funds. 
19. Includes $5,000 for previous porject. 
20. Abandonment recommended in 1926 (H. Doc. 467, 69th 
Cong., 1st sess.) 
21. Includes $2,000 expended outside project limits. 
22. Excludes $111,581 expended by Navy Department and 
$52,000 from contributed funds. 
23. Excludes $565 contributed funds. 
24. Includes $5,000 for previous project. 
25. Excludes $1,000 contributed funds. 
26. Unconstructed portion of the project was deauthorized 
November 6, 1977. 
27. Includes $20,640 for previous project. 
28. Includes $25,000 for previous project. 
29. Includes $19,170 Works Progress Administration 
funds. 
30. Includes $10,617 for previous project. 
31. Unconstructed portion of the project is inactive. 
32. Includes $20,500 for previous project. 
33. Excludes $389,000 contributed funds. 
34. Excludes $101,162 Public Health Service funds expended 
for waterchestnut removal. 
35. Includes $19,000 for previous project. 
36. Excludes $672,880 contributed funds. 
37. Excludes $24,125 contributed funds. 
38. Excludes $600 contributed funds. 
39. Includes $26,500 for previous project. 
40. Excludes $600 contributed funds. 
41. Excludes $6,984 contributed funds. 
42. Unconstructed portion of the project was deauthorized 
November 6, 1977. Includes $22,905 Works Progress funds and 
$97,390 for previous project. 
43. Excludes $40,000 contributed funds. 
44. Excludes $16,409 contributed funds. 
45. Includes $10,158 for previous project. 
46. Includes $6,000 for previous project. 
OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Oxford, MD' Completed 1978 $ 97,7502 
1. Authorized by Chief of Engineers. 
2. Excludes $80,648 contributed funds. 
4-34 
TABLE 4-D

BALTIMORE, MD DISTRICT 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
TABLE 4-E 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Status Report Construction Maintenance 
Anacostia River and Tributaries, 
Prince Georges Co., MD1 Completed 1977 1,000,0002 - 
Bainbridge, NY 2,3 Completed 1959 382,000 - 
Bath, NY' Completed 1970 638,332 - 
Bayard, WV3 Completed 1965 55,2185 - 
Black Walnut Point, MD Completed 1985 200,500 - 
Bridgewater, VA3 Completed 1953 136,500 - 
Bull Run, PA Completed 1984 2,742,000 - 
Conklin-Kirkwood, NY3 Completed 1955 71,000 - 
Cortland, NY6 Completed 1970 324,486 - 
Elkland, PA Completed 1971 1,297,850 - 
Endicott Johnson City and Vestal, NY Completed 1979 7,034,534' - 
Forest Heights, MD 3 Completed 1964 430,0008 - 
Fourmile Run, VA Completed 1987 52,480,000 - 
Hills Point Road, Dorchester Co., MD 2 Completed 1989 186,077 - 
Greene, NY 3 Completed 1951 37,000 - 
Kingston-Edwardsville, PA Completed 1979 4,731,3949 - 
Kitzmiller, MD 3 Completed 1965 501,50010 - 
Latta Brook Rd., NY Completed 1984 115,500 - 
Nichols, NY Completed 1974 1,487,800 - 
Norwich, NY 3 Completed 1950 94,500 - 
Painted Post, NY 4 Completed 1970 414,181 - 
Plymouth, PA Completed 1958 1,911,689"11 - 
Savage River Dam, MD Completed 1954 2,271,93912 33,999 
Scranton, PAl3 Completed 1971 2,006,800 - 
Sunbury, PA Completed 1953 6,063,000"14 - 
Swoyersville-Forty Fort, PA Completed 1968 2,728,113 - 
Tunkhannock Creek, Tunkhannock, PA Completed 1991 174,49115 - 
Tyrone, PA16 Deferred 1980 6,401,016 - 
Unadilla, NY Completed 1970 1,000,000" - 
Upper Marlboro, MD 3 Completed 1965 590,013 - 
Verona Lake, VA"8 Deferred 1978 992,000 - 
Washington, DC and Vicinity Completed 1953 331,92719 - 
Wilkes-Barre, Hanover Township, PA Completed 1958 3,853,45720 - 
Williamsport, PA Completed 1979 12,964,89321 - 
Wyoming Valley, PA Completed 1987 25,549,098 - 
1. Local interests will not accept operation and maintenance 
responsibility of the project until the severe erosion 
and sedimentation of the project caused by tropical storm Eloise 
is corrected and the project is restored to design condition. 
2. Excludes $357,022 contributed funds. 
3. Authorized by Chief of Engineers. 
4. Unit of Southern New York Flood Control Projects. 
5. Excludes $182,672 Public Works Acceleration funds 
and $4,290 contributed funds. 
6. Unit of Susquehanna River Flood Control Projects. 
7. Excludes $154,694 contributed funds. 
8. Excludes $87,720 contributed funds. 
9. Includes $1,162,548 emergency relief funds and 
excludes $225,877 emergency relief funds expended prior to 
adoption of project. 
10. Excludes $6,616 contributed funds. 
11. Includes $4,357 emergency relief funds. 
12. Includes $200,000 expended from contributed funds. 
13. Unit of Lackawanna River Basin Projects. 
14. Excludes $140,504 contributed funds. 
15. Excludes $53,383 contributed funds. 
16. The unconstructed portion of the project was reclassified 
to the deferred category January 8, 1981. 
17. Excludes $132,578 contributed funds. 
18. Authorized for the design memorandum stage of advanced 
engineering and design. 
19. Cost of previous project. Includes $106,500 emergency 
relief funds. 
20. Includes $872,715 emergency relief funds. Excludes 
$36,375 emergency relief funds expended for new work before 
adoption of project. 
21. Includes $1,887 emergency relief funds and excludes 
$110,835 contributed funds. 
4-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
DEAUTHORIZED PROJECTS 
TABLE 4-G 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Almond Village, NY 1"
2 
Baltimore Harbor & Channels, MD 
(Ferry Bar & Spring Garden Channel) 
Betterton Harbor, MD 
Breton Bay, MD 
(1902 River & Harbor Act) 
Broadwater Creek, MD 
Cadle Creek, MD2 
Cambridge Harbor, MD 
(1948 River & Harbor Act) 
Channel Connecting Plain 
Dealing Creek and Oak 
Creek, MD 
Chester River, MD 
(1873 River & Harbor Act) 
Coan River, VA 
1970 
1920 
1960 
1950 
1949 
1949 
1989 
1940 
1988 
1937 
1970 
1978 
1977 
1970 
1970 
1954 
1950 
1937 
Copes Corner Lakes, NY 2 
Cuckold Creek, MD4 
Cunninghill Cove, MD4 
Davenport Center Lake, NY 2 
Fall Brook Lake, PA 
Genegantslet Lake, NY 
Governors Run, MD 
Harpers Ferry, WV 
May 26, 1953 
1941 Flood 
Control Act 
Nov. 17, 1986 
1986 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Aug. 5, 1977 
1914 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
Jan. 22, 1979 
1960 River 
and Harbor Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
4-36 
$ 24,6223 
787,710 
3,482 
10,424 
212 
112 
25,419 
106,7003 
5,720 
11,200 
286,4003 
46,100 
214,5783

BALTIMORE, MD DISTRICT 
DEAUTHORIZED PROJECTS 
TABLE 4-G (Continued) 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Hellens Creek, MD 
Lake Ogleton, MD 
Mill Creek, MD 
Moorefield, WV 
1950 
1950 
1949 
1941 
1978 
1989 
1989 
1989 
1971 
1974 
1953 
1939 
1970 
Neabsco Creek, VA 
(1881 River & Harbor Act) 
Ocean City Harbor and Inlet 
and Sinepuxent Bay, MD 
(1954 River & Harbor Act) 
Pocomoke River, MD 
(1945 River & Harbor Act) 
Pocomoke River, MD & VA 
(1954 River & Harbor Act) 
Saint Georges Creek, MD 
Sixes Bridge Lake, MD & PA6 
South Plymouth Lake, NY 
Waterway from Little Choptank River to 
Choptank River, MD 
West Oneonta Lake, NY 2 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Nov. 6, 1977 
1974 Water 
Res. Dev. Act 
Oct. 3, 1978 
1974 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Dec. 31, 1989 
1986 Water 
Res. Dev. Act 
Sep. 23, 1986 
1974 Water 
Res. Dev. Act 
Dec. 29, 1981 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
Aug. 5, 1977 
1974 Water 
Res. Dev. Act 
May 6, 1981 
1974 Water 
Res. Dev. Act 
1. Local cooperation withdrawn, project authorization Engineers. 
expired May 26, 1953. 5. Unit of Lackawanna River Basin Projects. 
2. Unit of Southern New York Flood Control Projects. 6. Authorized for the design memorandum stage of ad- 
3. Cost for preliminary work only. vanced engineering and design. 
4. Project authorization was withdrawn by the Chief of 
RECONNAISSANCE AND CONDITION SURVEYS 
TABLE 4-H 
Date Survey 
Project Completed 
MARYLAND 
Crisfield Harbor June 1992 
4-37 
7,9286 
14,600 
100,0368 
305 
189,1008

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
RECONNAISSANCE AND CONDITION SURVEYS 
TABLE 4-H (Continued) 
Date Survey 
Project Completed 
Herring Bay and Rockhold Creek 
Honga River and Tar Bay 
Little Creek, Kent Island 
Lower Thorofare, Deal Island 
Madison Bay 
Nan Cove 
Nanticoke River 
Queenstown Harbor 
St. Georges Creek 
St. Jerome Creek 
St. Peters Creek 
Tyaskin Creek 
Warwick River 
VIRGINIA 
Little Wicomico River 
Monroe Bay 
Nomini Bay and Creek 
Pocomoke River 
Upper Machodoc Creek 
June 1992 
May 1992 
December 1991 
February 1992 
April 1992 
August 1992 
September 1992 
April 1992 
December 1992 
September 1992 
July 1992 
March 1992 
April 1992 
October 1991 
July 1992 
April 1992 
May 1992 
October 1991 
INSPECTION OF COMPLETED PROJECTS 
TABLE 4-I 
Project Date Inspected 
MARYLAND 
Anacostia River Basin 
Cumberland 
Forest Heights 
Kitzmiller 
Savage River Dam 
Upper Marlboro 
NEW YORK 
Bainbridge-Newton Creek 
Bath-Cohocton River 
Cincinnatus 
Conklin-Kirkwood 
Corning-Monkey Run 
Cortland 
Endicott-Johnson City & Vestal 
Greene 
Nichols 
Norwich 
Oneonta 
Owego 
Painted Post 
Port Dickinson 
Sherburne 
Unadilla 
PENNSYLVANIA 
Elkland 
Kingston-Edwardsville 
Milton 
Plymouth 
Scranton 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
September 1992 
October 1991 
October 1991 
4-38 
a

BALTIMORE, MD DISTRICT 
INSPECTION OF COMPLETED PROJECTS 
TABLE 4-I (Continued) 
Project Date Inspected 
Sunbury September 1992 
Swoyersville-Forty Fort October 1991 
Tyrone October 1991 
Wilkes-Barre-Hanover Twp. October 1991 
Williamsport September 1992 
VIRGINIA 
Bridgewater October 1991 
Fourmile Run October 1991 
District of Columbia & MD Projects October 1991 
Anacostia River October 1991 
Washington, DC & Vicinity October 1991 
WEST VIRGINIA 
Bayard October 1991 
Ridgeley October 1991 
4-39

NORFOLK, VA DISTRICT* 
NORFOLK, VA DISTRICT 
This district comprises the State of Virginia, except the 
Potomac, Roanoke, and Ohio River Basins; the entire area on the 
eastern shore of Virginia except for the project for Pocomoke River, 
Maryland and Virginia. On the west shore of Chesapeake Bay, all 
waterways south of Smith Point, VA, at the mouth of the Potomac 
River except the project for Little Wicomico River, VA. North 
Carolina, only the Chowan River Basin downstream to and including 
the mouth of the Meherrin River, and the Dismal Swamp Canal 
Route of the Atlantic Intracoastal Waterway to the Albemarle 
Sound. West Virginia, only the James River Basin. 
IMPROVEMENTS 
NAVIGATION PA 
1. Appomattox River, VA . . . . . . . . . . . . . . . . . 
2. Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL................. 
3. Baltimore Harbor and Channels 
(Norfolk District) . . . . . . . . . . . . . . . . . . . 
4. Bennett Creek, VA ...................... 
5. Channel to Newport News, VA .............. 
6. Chincoteague Inlet, VA . . . . . . . . . . . . . . . . . 
7. Cranes Creek, VA ... .................. 
8. Hampton Roads, VA 
(Collection and Removal of Drift) . . . . . . . . . . . 
9. James River, VA .. . . . . . . . . . . . . . . . .. 
10. Newport News Creek, VA . . . . . . . . . . . . . . . 
11. Norfolk Harbor, VA .................. 
12. Tangier Channels, VA . . . . . . ..... . . . . . . 
13. Tylers Beach Channel, VA . . . . . . . . . . . . . . . 
14 Rudee Inlet, VA.................. ... ...... 
15. Supervisor of the Harbor of 
Hampton Roads (Prevention of 
Obstructive and Injurious Deposits) . . . . . . . . . . 
16. Waterway on the Coast of VA ... . . . . . . ..... 
17. Navigation Work Under Special 
Authorization ...................... 
BEACH EROSION CONTROL 
18 Virginia Beach, VA................... 
19 Cape Charles, VA . . . . . . .. . . . . . . . . . .. 
20 Beach Erosion Control . . . . . . . . . . ..... 
Under Special Authorization 
GE FLOOD CONTROL PA 
5-2 21. James R. Olin Flood Control Project . . . . . . . . . . 
22. Gathright Dam and Lake Moomaw, VA . . . . . . . 
5-2 23. Richmond, VA ..................... 
24. Emergency Flood Control Activities . . . . . . . . . 
5-2 GENERAL INVESTIGATIONS 
5-3 25. Surveys ................ ........ 
5-3 26. Collection and Study of Basic Data . . . . . . . . . . 
5-3 TABLES 
5-3 TABLE 5-A Cost and Financial Statement ... . . . . . . 
A TABLE 5-B Authorizing Legislation . . . . . . . . . . . . 
5-4 
5-4 
5-4 
5-5 
5-5 
5-6 
5-6 
5-6 
5-6 
5-7 
5-7 
5-7 
5-7 
TABLE 5-C Data Relative to the Completed Locks . . . . 5-16 
TABLE 5-D Other Authorized Navigation Projects . . . . 5-17 
TABLE 5-E Other Authorized Beach Erosion 
Control Projects.................5-18 
TABLE 5-F Other Authorized Flood Control Projects . . . 5-18 
TABLE 5-G Reconnaissance and Condition Surveys . . . 5-19 
5-1 
\GE 
5-7 
5-8 
5-8 
5-8 
5-8 
5-8 
5-9 
5-13 
t!

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
Navigation 
1. APPOMATTOX RIVER, VA 
Location. This river rises in Appomattox County, VA, flows 
northeasterly 137 miles, and empties into the James River at 
Hopewell, VA. The portion under improvement extends from its 
mouth to Petersburg, VA, a distance of 11 miles, which is the length 
of the tidal and navigable reach. (See U.S. Coast Geodetic Survey 
Chart No. 531.) 
Previous Projects. For details see page 469 of Annual Report 
for 1938. 
Existing Project. This provides for a channel 80 feet wide 
and 10 feet deep from the mouth of the river to a point 400 feet 
above Lieutenant Run; thence 80 feet wide and of such depth, not 
exceeding 10 feet, as can be obtained without rock excavation to 
the head of navigation at Petersburg; including a basin at the mouth 
of Poes Run 200 feet long, 150 feet wide, and 20 feet deep: and a 
turning basin at the mouth of Lieutenant Run 500 feet long, 140 to 
160 feet wide, and 12 feet deep in the upper 300 feet, the removal 
of rock to a depth of 18 feet in the north half of the lower 200 feet, 
and removal of soft material to rock in the south half of the lower 
200 feet of this basin. All depths are referred to mean low water. 
The project also provides for a dam at Petersburg and the 
excavation for a width of from 200 to 300 feet of a diversion 
channel connecting the river above the dam with the river at a point 
2.5 miles below; for about 1.7 miles of levees on the low grounds 
between the navigable and the diversion channels; for a highway 
bridge and a railway bridge across the diversion channel; and for 
other work incidental to the diversion channel. 
Under ordinary conditions the mean tidal range is 2.9 feet and 
the extremes 2.4 and 3.3 feet. There are no records available of the 
heights of stage due to ordinary floods. These are estimated at 6 
to 8 feet above mean low water at Petersburg, where the extremes 
are from 15.6 feet to 17.1 feet. 
Local cooperation. Fully complied with. For details see page 
212 of Annual Report for 1969. 
Terminal Facilities. There are about 2,500 feet of wooden 
bulkhead and a shore landing in Petersburg Harbor. These 
facilities are in an abandoned, dilapidated condition and have not 
been used by commercial traffic on the river since 1950. There are 
two large recreational facilities now in operation on the Appomattox 
River. One is located about 2 miles downstream from 
Petersburg, VA and the other is at Hopewell, VA near the confluence 
of the Appomattox and the James. 
Operations and results during fiscal year. A maintenance 
dredging contract awarded at the end of the fiscal year 1991 
continued intermittently during fiscal year 1992. Between October 
17,1991 and June 19,1992 there were 381,418 cubic yards of 
material removed from the channel. At year end approximately 
260,000 cubic yards remained under contract to be removed, which 
is delayed due to the creosote-laden apperance of the material. 
2. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN 
NORFOLK, VA AND ST. 
JOHNS RIVER, FL 
(NORFOLK DISTRICT) 
Location.Two inland water routes approximately paralleling 
Atlantic coast south of Norfolk, VA between a point in 
Southern Branch of Elizabeth River, Va 2,500 feet upstream of 
Norfolk & Western Railway bridge and Virginia-North Carolina 
state line in North Landing River, a distance of 27.2 miles; and 64.6 
miles between mouth of Deep Creek, VA and mouth of Pasquotank 
River, NC. These routes are shown on National Ocean Service 
Chart 12206. 
Existing project. A channel 12 feet deep at mean low water 
and 90 to 250 feet wide following Southern Branch of Elizabeth 
River, 5.2 miles, Virginia Land Cut, 8.3 miles, and North Landing 
River, 13.7 miles; and construction of tidal guard lock at Great 
Bridge, VA. It also provides channels 10 feet deep at mean low 
water and 90 to 100 feet wide in Deep Creek, 3.1 miles, Turners 
Cut, 4.3 miles and Pasquotank River, 35.1 miles; maintaining 
Dismal Swamp Canal, 22.1 miles, to about 9 feet deep mean canal 
level over a width of 50 feet; protection of banks in Turners Cut 
with sheet piling, and cutting certain sharp points in Pasquotank 
River to shorten its course. (See Table 5-C at end of chapter on 
Data Relative to Completed Locks included in Project.) 
Project includes operating and care of completed locks, dams 
and bridges, under maintenance. Southern Branch of Elizabeth 
River and Deep Creek sections of the two routes are tidal, mean 
range being about 3 feet with extremes of minus 3.5 and plus 9.6 
feet. Remaining sections are nontidal with fluctuations of 1 to 2 
feet in level due to winds. Cost for new work for completed project 
was $3,396,276. Protection of canal property at Great Bridge 
portion is considered inactive and excluded from foregoing cost. 
Estimated cost of this portion (1954) is $265,000. For details of 
previous projects, see page 476 of Annual Report for FY 1938. 
Local Cooperation. None required. 
Terminal facilities. Existing facilities are considered adequate. 
See Annual Report for FY 1970. 
Operations during fiscal year. Maintenance: Work on the 
5-year operation and maintenance contract, awarded Feb 88 is 
progressing. A contract to replace the bulkheads at Great Bridge 
and South Mills, NC awarded 4 Aug 90 was completed during the 
fiscal year 1992. 
3. BALTIMORE HARBOR 
AND CHANNELS 
(NORFOLK DISTRICT) 
Existing project. Provides for deep water approach channels 
in Baltimore Harbor. Northern portion including Baltimore Harbor 
is under jurisdiction of Baltimore District. Portion under jurisdiction 
of Norfolk District is more fully described below. 
3A. CAPE HENRY CHANNEL, VA 
Location. At mouth of Chesapeake Bay opposite Cape Henry. 
(See National Ocean Service Chart No. 12222.) 
Existing project. A channel about 2.3 miles long, 1,000 feet 
wide, and 50 feet deep at mean low water through shoal at mouth 
of Chesapeake Bay opposite Cape Henry. Under ordinary conditions 
mean range of tide 2.5 feet and extreme 3 feet. Extremes of 
irregular fluctuation due to combined effect of wind and tides 
referred to mean low water, are minus 2 feet and plus 9.5 feet. 
5-2

NORFOLK, VA DISTRICT 
3B. RAPPAHANNOCK SHOAL 
CHANNEL, VA 
Location. In lower Chesapeake Bay opposite mouth of Rappahannock 
River and about 50 miles northerly from Atlantic Ocean 
at entrance of Chesapeake Bay. (See National Ocean Service Chart 
No. 12225.) 
Existing project. A channel about 9.9 miles long, 1,000 feet 
wide, and 50 feet deep at mean low water between contours of that 
depth in Chesapeake Bay, opposite Rappahannock River. Under 
ordinary conditions mean tidal range is 2.5 feet and extreme 3 feet. 
Extremes of irregular fluctuation due to combined effect of wind 
and tides, referred to mean low water, are minus 2 feet and plus 9.5 
feet. 
3C. YORK SPIT CHANNEL, VA 
Location. In lower Chesapeake Bay opposite mouth of York 
River and about 20 miles northerly from Atlantic Ocean at entrance 
of Chesapeake Bay. (See National Ocean Service Chart No. 
12221.) 
Existing project. A channel about 18.2 miles long, 1,000 feet 
wide, and 50 feet deep at mean low water between contours of that 
depth in Chesapeake Bay opposite York Spit. Under ordinary 
conditions mean tidal range is 2.5 feet and extreme 3 feet. Extremes 
of irregular fluctuation, due to combined effect of wind and tides, 
referred to mean low water, are minus 2 feet and plus 9.5 feet. For 
details of previous projects see Annual Report for 1932. 
Terminal facilities. These three channels form the access 
between lower and upper Chesapeake Bay. 
Operations during fiscal year. Operations performed included 
condition studies, engineering and design, and supervision 
and inspections. Maintenance dredging by contract between 
March 31, 1992 and June 10,1992 removed 860,850 cubic yards 
from Cape Henry Channel. 
4. BENNETT CREEK, VA 
Location. Bennett Creek is a tidal estuary of the Nansemond 
River wholly in the city of Suffolk, Va. It is about 3 miles in length, 
flows in a northeasterly direction, and empties into the Nansemond 
River at its juncture with the James River.(See U.S. Coast and 
Geodetic Survey Chart 12222.) 
Previous Project. None. 
Existing project. A channel 6 feet deep and 60 feet wide from 
the 6 foot contour in the Nansemond River to the 6 foot contour 
within the mouth of Bennett Creek, and extending upstream to the 
city boat ramp at Bennett Creek Park, a distance of approximately 
2.4 miles. Mean tidal range is 2.8 feet. 
Local cooperation. Fully complied with for construction. 
Local interests are to furnish spoil disposal areas as required for 
maintenance. 
Terminal facilities. A privately owned commercial dock and 
berthing facility on the southside of the creek at the U.S. Route 17 
crossing and a public boatramp and parking area at the city park. 
Operations during fiscal year. New Work dredging by 
contract between May 16 and May 31,1992 removed 110,737 cubic 
yards to complete construction of the project. 
5. CHANNEL TO 
NEWPORT NEWS, VA 
Location. West of north entrance to Norfolk Harbor Channel, 
connects deep water in James River with Hampton Roads. (See 
National Ocean Service Chart No. 400.) 
Previous project. For details see Annual Report for 1938. 
Existing project. Dredging a channel 55 feet deep at mean 
low water and 800 feet wide from Norfolk Harbor Channel in 
Hampton Roads to Newport News, a distance of about 4.5 miles, 
and two deep-draft anchorage berths opposite Newport News 45 
feet deep over a 1,200-foot swinging radius. Under ordinary conditions 
mean tidal range is 2.7 feet and extremes 2.1 and 3 feet. 
Extremes of irregular fluctuations due to combined wind and tides, 
referred to mean low water, are minus 2 feet and plus 9.5 feet. 
Local cooperation. Fully complied with for dredging the 
channel to an intermediate depth of 50 feet, which was completed 
December 2, 1988. The local sponsor (Virginia Port Authority) is 
required to furnish cost sharing in accordance with the provisions 
described in the Water Resources Development Act of 1986, as 
amended, for additional deepening. 
Terminal facilities. See Port Series No. 11, (Revised 1971, 
Part II) on Ports of Hampton Roads, prepared by Board of Engineers 
for Rivers and Harbors. 
Operations during fiscal year. New work coordination with 
the sponsor regarding the scheduling of additional deeping, and 
dredge material management alternatives. Maintenance dredging 
by contract between July 26, and August 9, 1992 removed 461,785 
cubic yards from the two 45 foot deep anchorages. 
6. CHINCOTEAGUE INLET, VA 
Location. Chincoteague Inlet at the southern end of Assateague 
Island provides access to the Atlantic Ocean from the 
inland waterway near the town of Chincoteague, VA. (See National 
Ocean Service Chart 12211.) 
Existing project. Provides for a channel 12 feet deep and 150 
feet wide across the ocean bar in the Atlantic Ocean and to the 
mouth of the inlet, a channel 9 feet deep and 100 feet wide from 
the inlet through the canal, and then along Chincoteague Channel 
to a point approximately 2,000 feet north of the state highway 
bridge to Chincoteague, a distance of about 6.6 miles. Mean range 
of tide is about 3 feet. All depths are referred to mean low water. 
Local cooperation. For details see Annual Report for 1974. 
Terminal facilities. Existing facilities at Chincoteague are 
considered adequate for current and prospective traffic. 
Operations during fiscal year. Maintenance dredging by 
contract between April 20 and May 29, 1992 removed 148,420 
cubic yards from the Entrance Channel, and from July 27 to August 
29, 1992 removed 58,754 cubic yards from the Inner Harbor and 
79,247 cubic yards from the Lewis Creek Reach. 
7. CRANES CREEK, VA 
Location. Cranes Creek in Northumberland County, Virginia 
is a small tidal estuary approximately 2 miles long and entering the 
right bank of the Great Wicomico River 2-1/2 miles upstream to 
the Chesapeake Bay. The creek is about 76 miles northerly from 
Norfolk, Virginia. (See Coast and Geodetic Chart No. 12235) 
5-3

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
Existing project. This provides for a channel 6 feet deep, 80 
feet wide, and, 1,500 feet long from deepwater in the Great 
Wicomico River to deepwater within Cranes Creek. The plane of 
reference is mean low water. The tidal ranges are mean 1.1 feet, 
irregular 2.0 feet, and extremes approximately 7.2 feet. 
Local cooperation. Fully complied with for construction. 
Local interests are to furnish spoil disposal areas as required for 
maintenance. 
Terminal Facilities. There are several small privately owned 
wharfs and landings on the creek which are considered adequate 
for present commerce. 
Operations during fiscal year. Maintenance dredging by 
contract between October 30, and November 11, 1991 removed 
9,802 cubic yards. 
8. HAMPTON ROADS, VIRGINIA 
COLLECTION AND 
REMOVAL OF DRIFT 
Location. Hampton Roads is a natural harbor 300 miles south 
of New York and 180 miles south of Washington, D.C. Its principal 
tributaries are James River, affording a natural deep harbor 
at Newport News, VA; Elizabeth River, with its Southern, Eastern, 
and Western Branches providing harbors for Norfolk and 
Portsmouth, VA; and Hampton Creek, serving the harbor at 
Hampton, VA. (See National Ocean Service Chart Nos. 12248, 
12245 and 12253.) 
Existing project. Collection and removal of drift in Hampton 
Roads and its tributary waters authorizes the Secretary of the Army 
to allot necessary amounts of work from appropriations for maintenance 
and improvement of existing river and harbor works or 
from other available appropriations and that this work shall be 
carried on as a separate and distinct project. It is wholly a work of 
maintenance. The purpose of work is to afford relief from variable 
conditions of obstruction. No advance estimate of the amount of 
work is required. 
Local cooperation. None required. 
Terminal facilities. See Norfolk Harbor, VA and Channel to 
Newport News, VA. 
Operations during fiscal year. Maintenance: Operation of 
the project resulted in collection and disposal of a variety of 
floating refuse. Operations were performed using government 
plant and hired labor. 
9. JAMES RIVER, VA 
Location. The river is formed by the junction of the Cowpasture 
and Jackson Rivers in Botetourt County, VA, flows easterly 
340 miles and empties into Hampton Roads at Newport News, VA. 
(See National Ocean Service Chart Nos. 12248 and 12251.) 
Existing project. A channel 35 feet deep and 300 feet wide 
form the mouth to Richmond Deepwater Terminal, and a channel 
18 feet deep and 200 feet wide from the Deepwater terminal to 
Richmond Lock; a mooring basin 35 feet deep, 180 to 220 feet wide 
and 2,100 feet long alongside the channel opposite waterfront at 
Hopewell; enlargement of the turning basin at Richmond Deepwater 
Terminal to 825 feet wide, 2,770 feet long and 35 feet deep; 
a turning basin in Richmond Harbor 200 feet wide, 600 feet long 
and 18 feet deep; and construction of spur and training dikes. Depth 
of channels are referred to mean low water. Total length of channel 
included in the project is 87 miles, which is the navigable section. 
Mean tidal ranges under ordinary conditions for different parts of 
the river are: mouth, 2.6 feet; Jamestown, 2 feet; City Point, 2.6 
feet; and Richmond, 3.2 feet. Spring tide ranges under ordinary 
conditions at the same localities are mouth, 3.1 feet; Jamestown, 
2.4 feet; City Point, 3 feet; Richmond, 3.2 feet. Ordinary fluctuations 
of stage at Richmond, due to floods are 6 to 12 feet above 
mean low water. Extreme fluctuations are 16 to 32 feet. Flood 
heights below Richmond diminish rapidly. The extreme according 
to available information is about 11 feet lower at Dutch gap, 14 
miles below and 17 to 18 feet lower, 20 miles below. For previous 
projects, see Annual Report for 1938. 
Local cooperation. Fully complied with for conditions imposed 
by River and Harbor Act of 1962. However, the local 
sponsor (Richmond Port Authority) is required to furnish cost 
sharing in accordance with the provisions described in the Water 
Resources Development Act of 1986, as amended. Deepening the 
project from 25 feet to 35 feet, and the widening, authorized by the 
River and Harbor Act of 1962 has not been started. 
Terminal facilities. River commerce at Richmond is handled 
by city-owned terminals, city wharf, Richmond dock, and 16 
privately-owned wharves within or in the immediate vicinity of 
Richmond Harbor. The city's Upper Terminal, located on the north 
bank within the manufacturing section of Richmond, provides for 
750 feet of concrete wharf and 80,000 square feet of warehouse 
and transit shed. The other terminal is located approximately 4 
miles downstream from the Upper Terminal which provides about 
1,250 feet of wharf and 2 concrete warehouses with about 190,000 
square feet of floor space. This deepwater terminal at the head of 
the 25-foot deep improved channel serves oceangoing vessels and 
larger ships engaged in coastwide trading. Below the deepwater 
terminals the improvement is served by 42 wharves. Richmond 
terminals and wharves together with wharves between Richmond 
and the river's mouth are adequate for river's commerce. 
Operations during fiscal year. Maintenance dredging by 
contract between July 1 and August 8, 1992 removed 1,225,114 
cubic yards. 
10. NEWPORT NEWS CREEK, VA 
Location. Newport News Creek, Va., is located on the southeastern 
end of the peninsula between the James and York Rivers 
and within the corporate limits of the city of Newport News. (See 
U.S. Coast and Geodetic Survey Charts Nos. 400 and 1222.) 
Existing project. This provides for a channel 12 feet deep at 
mean low water with widths varying from 200 to 60 feet from 
deepwater in Hampton Roads to and through the municipal boat 
harbor entrance, thence 12 feet deep at mean low water and 150 
feet wide to and including a turning basin and anchorage of the 
same depth 220 feet wide and 400 feet long in the upper end of the 
harbor. The mean tidal range is 2.6 feet and the extreme 3.1 feet. 
The extremes of irregular fluctuations due to combined wind and 
tides referred to mean low water, are minus 2 feet and plus 9.5 feet. 
The existing project was adopted by the River and Harbor Act of 
July 24, 1946 (H. Doc. 559, 79th Cong., 2d sess.). The latest 
published map is in the project document. Significant modifications 
to the entrance to the project, constructed to accomodate 
construction of Interstate Highway 664 crossing Hampton Roads, 
5-4

NORFOLK, VA DISTRICT 
has been incorporated on the unpublished map maintained at the 
District. 
Local cooperation. Fully complied with as to initial construction. 
Local interests are required to simultaneously dredge certain 
areas adjacent to the project during periods of future maintenance. 
Terminal facilities. There are 4,210 linear feet of steel-andwood 
bulkhead, and two marine railways, which can accomodate 
vessels up to 85 feet in length, on Newport News Creek. The city 
of Newport News maintains 400 feet of bulkhead open to the public 
without charge and operates a pleasure boat marina with 18 finger 
piers at which a nominal wharfage fee is charged. The remaining 
facilities are privately owned or are leased by the city to private 
firms. These facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance 
dredging, by contract, between April 13 and April 21, 1992 
removed 43,721 cubic yards. 
11. NORFOLK HARBOR, VA 
Location. Norfolk, VA is 187 miles south of Baltimore, MD 
and 30 miles from entrance to Chesapeake Bay at Cape Charles 
and Cape Henry. Harbor extends 18.3 miles from 40-foot contour 
in Hampton Roads to a point 2,500 feet above Norfolk and Western 
Railway bridge over a Southern Branch of Elizabeth River. (See 
National Ocean Service Chart Nos. 400 and 452.) 
Previous Projects. For details see Annual Report for 1938. 
Existing project. 
HAMPTON ROADS AND ELIZABETH RIVER: A channel 
55 feet deep and 1,500 feet wide from that depth in Hampton Roads 
to a point approximately 6.3 miles upstream from the Hampton 
Roads Bridge-Tunnel; thence 55 feet deep and 800 feet wide to 
Lamberts Point; thence 45 feet deep and 750 feet wide to the 
junction of Southern Branch and Eastern Branch. 
SOUTHERN BRANCH: A channel 45 feet deep and 450 feet 
wide from the junction with the Eastern Branch to the Norfolk and 
Portsmouth Belt Line Railway Bridge; thence 45 feet deep and 375 
feet wide to the Norfolk and Western Railway Bridge; thence 40 
feet deep and 250 feet to 500 feet wide to the U.S. Routes 460 and 
13 highway bridge; thence 35 feet deep and 250 to 300 feet wide 
to a point 0.8 mile above Interstate 64 high level bridge. Project 
includes an approach and turning basin 45 feet deep opposite the 
Norfolk Naval Shipyard; a turning basin at the mouth of St. Julians 
Creek 40 feet deep, 400 to 600 feet long, and 800 feet wide; a 
turning basin at the mouth of Milldam Creek 40 feet deep and 800 
feet square and a turning basin at the mouth of Mains Creek, the 
upstream end of the project, 35 feet deep and 800 feet square. 
EASTERN BRANCH: A channel 25 feet deep and 500 feet 
wide from the junction of the branches to Norfolk and Western 
Railway Bridge, from the Norfolk and Western Railway Bridge a 
channel 25 feet deep and 200 feet wide to the Campostella Bridge, 
channel 25 feet deep and 200 feet wide to the Norfolk and Western 
Railway Bridge (formerly Virginian), including a turning basin 25 
feet deep and approximately 5.5 acres in size located at the 
upstream end of the project. 
WESTERN BRANCH: A channel 24 feet deep and 300 feet 
wide to a point 0.78 mile from the 40-foot channel, thence 24 feet 
deep and 200 feet wide for a distance of 0.38 mile; thence 18 feet 
deep and 150 feet wide for 0.57 mile to a point 0.34 mile above the 
West Norfolk Bridge. 
SCOTTS CREEK: A channel 12 feet deep at mean low water 
and 100 feet wide from the 40-foot channel for a distance of 0.73 
mile.
ANCHORAGES: Three fixed mooring anchorage facilities 
with a depth of 55 feet, each capable of accommodating two large 
vessels simultaneously; two anchorages opposite Sewells Point, 45 
feet deep over a swing radius of 2,300 feet; anchorage area on the 
west side of the 55-foot channel opposite Lamberts Point aggregating 
173 acres consisting of open space 1,500 feet square and 38 
feet deep, one space 1,500 feet square and 35 feet deep, and one 
space 3,000 feet long, 1,000 feet wide and 20 feet deep; and a 
45-acre anchorage, 12 feet deep, near Pinners Point. 
DISPOSAL AREA: a disposal area of about 2,500 acres 
adjacent to and north of Craney Island, enclosed by stonefaced 
levee of sand; rehandling basin, approach and exit channels connecting 
rehandling basin and Norfolk Harbor 55-foot channel and 
hopper dredge unloading facility. 
Local cooperation. Fully complied with for dredging the 
channel to an intermediate depth of 50 feet, which was completed 
December 15, 1988. The local sponsor (Virginia Port Authority) 
is required to furnish cost sharing in accordance with the provisions 
described in the Water Resources Development Act of 1986, as 
amended for additional deepening. 
Terminal facilities. See Port Series No. 11 (revised 1971, Part 
II) on Ports of Hampton Roads, prepared by Board of Engineers 
for Rivers and Harbors. 
Operations during fiscal year. New Work: Coordination 
with the sponsor and other agencies regarding scheduling of additional 
deepening, and dredge material management alternatives. 
Maintenance: Dredging by contract in progress at the beginning 
of fiscal year 1992 was completed on December 29, 1991 removing 
1,201,500 cubic yards from the 45 and 50 foot channel reaches. 
The annual dredging contract for fiscal year 1992 was rescheduled 
to fiscal year 1993 due to contractor protest. Operation and Maintenance 
of the Craney Island Dredged Material Management Area 
continued. 
Terminal facilities. See Port Series No. 11, (revised 1971, 
Part II) on Ports of Hampton Roads, prepared by Board of Engineers 
for Rivers and Harbors. 
Operations during fiscal year. Maintenance: 367,461 cubic 
yards of material was dredged from the Norfolk Harbor 40' channel 
between 7 Aug and 19 Sept 91. Maintenance dredging of the 
Norfolk Harbor 45' and 50' channels removed 874,500 cubic yards 
of material between 1 Aug and 30 Sept 91 and is continuing into 
FY 92. 
12. TANGIER CHANNELS, VA 
Location. A tidal channel about 2 miles lng extending from 
Tangier Island, Virginia, northeasterly to deepwater in Tangier 
Sound, Chesapeake Bay. (See National Ocean Services Chart No. 
12228.) 
Existing project. A channel 8 feet deep at mean low water 
and 100 feet wide from 8 foot contour to Tangier Sound to day 
marker No. 4, and thence 8 feet deep and 60 feet wide to the town 
of Tangier, with an anchorage basin adjacent of town 400 feet 
5-5

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
square and 7 feet deep. A channel 7 feet deep and 60 feet wide 
about 4,000 feet from the anchorage basin northwesterly across 
Tangier Island to Chesapeake Bay. Mean range of tide is 1.7 feet 
and extreme tidal range 4.7 feet. 
Local cooperation. Complied with except that local interests 
must furnish spoil disposal area as needed for future maintenance. 
Terminal facilities. Accomack County constructed a public 
dock in 1961. There are four privately owned docks adjecent to 
existing project and two marine railways. 
Operations during fiscal year. Maintenance dredging by 
contract between September 10 and September 28, 1992 removed 
76,895 cubic yards. 
13. TYLERS BEACH HARBOR, VA 
Location. On south shore of James River in Isle of Wight 
County in a deep indentation known as Burwells Bay about 13 
miles above the mouth of the James River. (See Coast and Geodetic 
Survey Chrt No. 12248.) 
Existing project. Provides for harbor of refuge 6 feet deep, 
150 feet wide and 300 feet long, just south of Tylers Beach, and a 
channel 6 feet deep, 50 feet wide and about 2,350 feet long from 
that depth in Burwells Bay to the harbor of refuge. Plane of 
reference is mean low water. The project was modified in 1981 to 
provide for construction of two 370 foot placed stone revetment/
jetty structures along the banks of the inlet throat leading to 
the harbor. Mean range of tide is 2.4 feet. 
Local cooperation. Fully complied with except that local 
interests must furnish spoil disposal area as needed for future 
maintenance. 
Terminal facilities. A public landing has been constructed by 
a local interest under the requirements of local cooperation. Watermen 
basing operations at Tylers Beach have constructed mooring 
facilities in the harbor of refuge for their vessels. Existing facilities 
are considered adequate. 
Operations during fiscal year. Maintenance dredging by 
contract between September 29 and October 5,1992 removed 
18,209 cubic yards. 
14. RUDEE INLET, VA 
Location. Rudee Inlet is located on the Atlantic Ocean at 
Virginia Beach in an area where boating is a major activity. It 
provides a gateway to a variety of oceanic pursuits varying from 
pleasure cruising to commercial deep sea fishing. 
Existing project. An entrance channel 10-ft deep, 110 to 72-ft 
wide and 1605-ft long; an inner channel 7-ft deep, 72 to 53-ft wide 
and 2,495-ft long including a safety area 7-ft deep, and approximately 
1.9 acres in size and a turning basin 7-ft deep, 175-ft 
wide and 1,570-ft long; a sand trap 18-ft deep and approximately 
3.3 acres in size; and a weir and jetty system at the mouth of the 
inlet.
Local cooperation. Complied with for initial dredging as a 
Federal project in fiscal year 1991. Local interests are to financially 
participate in continued annual maintenance at an increasing rate 
as described in the Local Cooperation Agreement. 
Operations during fiscal year. Maintenance dredging between 
March 18 and May 5, 1992 removed 128,786 cubic yards. 
15. SUPERVISOR OF NORFOLK 
HARBOR (PREVENTION OF 
OBSTRUCTIVE AND INJURIOUS 
DEPOSITS) 
The District Engineer, Norfolk District, was designated Supervisor 
of the harbor of Hampton Roads under the provisions of the 
River and Harbor Act of June 29, 1888 (33 U.S.C. 441-451) as 
amended July 12, 1952. Under this Act, the Supervisor of the 
harbor of Hampton Roads is charged with the mission of preventing 
the deposit of obstructive and injurious materials in the tidal waters 
of the harbors of Norfolk, Portsmouth, Newport News, Hampton 
Roads, and their adjacent and tributary waters, so much of the 
Chesapeake Bay and its tributaries as lies within the State of 
Virginia, and so much of the Atlantic Ocean and its tributaries as 
lies within the jurisdiction of the United States within or to the east 
of the State of Virginia. The River and Harbor Act of March 3, 
1899 (33 U.S.C. 403,407,409) as amended prohibits obstructions 
to navigable waters such as unauthorized structures, unauthorized 
fill, deposit of refuse, and sinking of vessels. Other laws relating 
to the supervision of Norfolk Harbor and its tributary waters are 
the Clean Water Act, the Marine Protection, Research and 
Sanctuaries Act of 1972, the Coastal Zone Management Act of 
1969, the Fish and Wildlife Act of 1956, the Federal Power Act of 
1920, the National Historic Prevention Act of 1966, the Endangered 
Species Act of 1973, the Deepwater Port Act of 1972, the 
Wild and Scenic Rivers Act, and the Land and Water Conservation 
Fund Act. 
Direct supervision of the waters under the jurisdiction of the 
Norfolk District was accomplished by means of two patrol vessels 
performing inspections, removing debris and investigating navigational 
hazards and sunken or abandoned vessels. A derrickboat and 
crane barge performed removal of sunken vessels and navigational 
hazards and supported Federal dredging projects. In addition, 
surveillance of the harbor was performed regarding the Corps' 
regulatory program, using also two small outboard craft, motor 
vehicles from land and occasional chartered aerial reconnaissance. 
This regulatory surveillance involved compliance surveys of permitted 
activities and evaluation of navigational impacts of 
proposed piers and other structures. 
16. WATERWAY ON THE COAST 
OF VIRGINIA 
Location. Between barrier beach along Atlantic Ocean on the 
east and Virginia portion of mainland peninsula on the west. It 
extends for 83.7 miles from south end of Chincoteague Bay 
through a number of creeks, thoroughfares and bays to enter 
Chesapeake Bay in the vicinity of Fisherman Island, just south of 
Cape Charles on the southern tip of the peninsula. (See National 
Ocean Service Chart Nos. 12211, 12210, and 12221.) 
Existing projects. An inland waterway 6 feet deep at mean 
low water and 60 feet wide from Chesapeake Bay to Chincoteague 
Bay, VA. Mean range of tide is about 3 feet. Greater fluctuations 
in water level are caused by high winds and storms. A modification 
of the project approved during 1970 under Section 201 of the Flood 
Control Act of 1965 authorized relocation of portions of the waterway 
and widening of 100 feet. 
5-6

NORFOLK, VA DISTRICT 
Local cooperation. Complied with except that local interests 
are to furnish spoil disposal areas for future maintenance. 
Terminal facilities. Existing facilities are considered adequate. 
Operations during fiscal year. Maintenance dredging by 
contract between June 14 and July 10, 1992 removed 230,417 cubic 
yards. 
17. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
The District continued work on five studies: Hunting/Gilford 
Creeks, VA; Lynnhaven River, VA; Back River, Poquoson, VA; 
York and Pamunkey Rivers, VA; and Newport News Creek, VA. 
Total expenditures amounted to $140,830. 
BEACH EROSION CONTROL 
18. VIRGINIA BEACH, VA 
Location. On the Atlantic Seaboard, 22 miles north of Virginia-
North Carolina State line, 3.5 miles south of Cape Henry, and 
19 miles east of Norfolk, VA. (See National Ocean Service Chart 
12207.) 
Existing project. Federal participation in restoration and 
protection of shore of Virginia Beach between Rudee Inlet and 49th 
Street by artificial placement of sand to provide a minimum beach 
width of 100 feet at elevation 7 feet above mean low water, and 
maintenance of such beach by periodic replenishment of losses to 
ensure continuous protection; including construction of a groin 
system to be undertaken at such times as estimated annual charges 
therewith would be less than the annual cost of beach replenishment 
alone. The 1962 modification provided that the United States 
participate in periodic nourishment of the beach for 25 years. 
The 1974 modification which provides for structural and nonstructural 
improvements was authorized for construction by the 
Water Resources Development Act of 1986. Structural measures 
will be provided for the 6 mile reach of shoreline between Rudee 
Inlet and 89th Street. This will include maintaining the beach and 
construction of a seawall from Rudee Inlet to 58th Street, and 
raising and strengthening sand dunes from 58th Street to 89th 
Streets. 
Local cooperation. The city of Virginia Beach has complied 
with the 1962 requirements. Cost sharing in accordance with the 
provisions described in the Water Resources Development Act of 
1986, as amended, will be required for construction of the 1974 
modification. 
Operations during fiscal year. New Work: The project, as 
authorized by the River and Harbor Act of 1962, expired Feb 87. 
Federal participation has been extended from 25 years to 35 years, 
on March 10, 1988 by the Assistant Secretary of the Army for Civil 
Works. 
The 1974 modification project is in the preconstruction engineering 
and design phase. 
19. CAPE CHARLES SHORELINE, VA 
Location. The Mason Avenue Sewage Lift Station is on the 
north bank of the entrance to Cape Charles City Harbor, on the 
Chesapeake Bay side of the Delmarva Peninsula separating the bay 
from the Atlantic Ocean, about 11 miles north of the southern 
extremity of the peninsula and 45 miles south of the Maryland-Virginia 
State line. 
Previous projects. None. 
Existing project. A free-standing, engineered rubble-mound 
revetment structure with 4.5 foot crest width, 5.25 above mean low 
water, to control erosion along a 265 foot segment of shoreline. 
Local cooperation. Fully complied with for construction. 
Local interests will be responsible for operation and maintenance 
of the project. 
Operations during fiscal year. New Work: Construction 
was approved May 19, 1992. Bids were opened September 1 and 
the contract awarded September 25, 1992. 
20. BEACH EROSION 
CONTROL UNDER SPECIAL 
AUTHORIZATION 
The district completed work on one study: Cape Charles City 
Harbor, VA. 
FLOOD CONTROL 
21. JAMES R. OLIN 
FLOOD CONTROL PROJECT, VA 
(Formerly- Buena Vista, Va.) 
Location. The city of Buena Vista is on the left bank of the 
Maury River, 40 miles below the river's origin and about 11 miles 
upstream of its juncture with the main stem of the James River at 
the community of Glasgow. The Maury River Basin above Buena 
Vista contains a drainage area of some 649 square miles. 
Existing projects. The recommended plan of improvement 
provides for a combination earth levee and floodwall along the left 
bank of the river for nearly the full length of the city. The main 
features of the plan are (a) an 11,900-foot combination riprapped 
levee and floodwall, extending to high ground just upstream of 
Universal Match Company to high ground downstream from 
General Cable Corporation at a point near the Norfolk and Western 
Railway Bridge across the Maury River; (b) 4,000 feet of improved 
channel in the Maury River, provided by straightening and widening 
the existing channel to a bottom width of 200-300 feet, for the 
purpose of eliminating a backwater effect upstream, which would 
otherwise increase natural flood damage to the property located in 
that area; (c) diversion of internal runoff from surface sources and 
from Indian Gap Run and Pedlar Gap Run into an abandoned canal 
bed, appropriately improved for a distance of 7,400 feet 
downstream and thence discharged by gravity, into the Maury 
River; and (d) a 2,270 foot concrete ringwall at the Georgia 
Bonded Fibers manufacturing facility. 
Local cooperation. The local sponsor (City of Buena Vista) 
is required to furnish cost sharing in accordance with the provisions 
described in the Water Resources Development Act of 1986, as 
amended, for project construction, and maintain and operate all 
works after completion. 
Operations during the fiscal year. Preconstruction planning, 
design, and engineering was in progress. 
5-7

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
22. GATHRIGHT DAM AND 
LAKE MOOMAW, VA 
Location. Gathright Dam is on the Jackson River, a tributary 
of James River at mile 43.4 in Alleghany County. Gathright Dam 
site is in the reach of the Jackson River known as the Gorge, about 
19 miles upstream from Covington, VA At the elevation of the top 
of the conservation pool, the lake extends upstream about 9 miles. 
(See Falling Spring and Mountain Grove, Virginia-West Virginia 
quadrangles of geological survey.) 
Existing project. Gathright Dam consists of a 1,172-foot 
long, rolled-rock-fill dam with an impervious core, with the top at 
elevation 1,684.5; outlet works consisting of a concrete intake 
structure located in the right bank 500 feet upstream from the axis 
of the dam; a 1,075-foot long outlet tunnel through the right 
abutment and a stilling basin; and a 2,450-foot long fixed-crest 
emergency spillway excavated in a low saddle in the divide at 
Fortney Branch about 2.5 miles south of the dam. Discharges 
through the maximum conservation pool elevation 1,582 will be 
provided for water quality control. The reservoir area at elevation 
1,582 will be 2,530 acres. A total of 302,000 acre-feet of storage 
between elevation 1,582 and the spillway crest (elevation 1,663.5) 
will be reserved for flood control. At the spillway crest the reservoir 
will have an area of 4,540 acres. 
Local cooperation. None required. 
Operations during fiscal year. Care of service and recreational 
facilities, water control management, testing and monitoring, 
supervision and administration and engineering and design. 
23. RICHMOND, VA 
Location. The city of Richmond, the capital of Virginia, is 
located in the Piedmont Plateau and is bordered on the north by 
Henrico County and on the south by Chesterfield County. The 
James River flows directly through Richmond separating its business 
district into two areas, the Shockoe Creek area on the north 
bank and the industrial-commercial complex on the south bank. 
Previous project. None. 
Existing project. The project will provide a system of floodwalls 
and levees on both sides of the river in the downtown area 
which would protect against a flood higher than that which occurred 
in June 1972 which is the maximum flood of recent record. 
The project to be constructed is that generally described in House 
Document 98-178, 98th Congress, 2nd Session with modifications 
recommended by the Assistant Secretary of the Army on February 
21, 1984. The present construction cost of the project is now 
estimated at $122,300,000. 
Local Cooperation. A Local Cooperation Agreement was 
signed with the city of Richmond on June 16, 1986. For details see 
Annual Report for 1986. 
Operations during fiscal year. New Work: Construction 
was initiated December 1988 and is continuing. Completion is 
scheduled for Sep 1993. 
24. EMERGENCY FLOOD CONTROL 
ACTIVITIES 
During FY 92, $171,865 was spent on the National Emergency 
Preparedness Program, and $235,527 on the Disaster Preparedness 
Program. 
GENERAL INVESTIGATIONS 
25. SURVEYS 
Total cost of surveys during the fiscal year amounted to 
$492,259. The work performed consisted of a flood damage 
prevention study of the upper James River Basin, $18,970; review 
of the completed AIWW Bridge, $366,448; miscellaneous activities 
consisting of Special Investigations, Intragency Water 
Resouces Development and American Waterfoul Management 
Plan amounting to $33,880; Coordination Studies with other agencies 
and states, $36,601; and Preauthorization Studies, $36,360. 
26. COLLECTION AND STUDY OF 
BASIC DATA 
During the fiscal year, cost of collection and study of Basic 
Data was $150,078 consisting of $43,173 for Management Service 
Unit, $80,563 for Technical Services, and $26,342. for Va. Beach 
Hurricane Evacuation study. 
5-8

NORFOLK, VA DISTRICT 
TABLE 5A COST AND FINANCIAL STATEMENT 
See Total to 
Sect. Project Funding FY89 FY 90 FY91 FY92 30 Sept 92 
in Text. 
1. Appomattox River, VA New Work 
(Regular Funds) Approp 
Cost 
Maint 
Approp 
Cost 
- 
212,025 
211,957 
270,128 
266,423 
1,763,859 
1,755,304 
, 
1,673,600 
1,670,788 
870,341 
870,341 
4,808,805 
4,793,665 
2. Atlantic Intracoastal 
Waterway, between 
Norfolk, VA and 
St. John's River, FL 
(Norfolk District) 
(Regular Funds) 
3. Baltimore Harbor 
and Channels 
(Norfolk District) 
(Regular Funds) 
4. Bennetts Creek, VA 
(Regular Funds) 
(Contributed Funds) 
5. Channel to 
Newport News, VA 
(Regular Funds) 
(Contributed Funds) 
6. Chincoteague Inlet,VA 
(Regular Funds) 
(Contributed Funds) 
7. Cranes Creek, VA 
(Regular Funds) 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Major Rehab 
Approp 
Cost 
Recreation 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
- - - - 3,688,372' 
- - - - 3,688,372 
2,255,274 3,479,644 4,707,862 3,562,589 64,358,7602 
3,046,911 3,373,880 4,641,338 3,590,029 64,213,093 
-- - - 479,947 
- - - - 479,947 
-- - - 59,871 
- - - - 59,871 
319,453 
323,236 
1,730 
4,783 
96,594 
94,883 
261 
- 8,015,0733 
- 8,015,073 
230,660 1,955,262 12,934,465 
221,674 1,959,561 12,927,207 
75,000 
37,914 
285,000 453,229 
311,459 442,602 
104,700 
104,621 
334,020 1,010,871 
1,344,891- 
231 
331 
78,921 
70,485 
1,424,410 
1,780,206 
713,341 
723,695 
800,686 
793,577 
104,700 
104,621 
S- 4,097,1176 
- - 4,097,117 
53,000 1,270,326 7,165,886 
60,741 1,271,031 7,165,886 
- - 4,918,544 
- - 4,695,108 
- - 227,000 
- - 227,000 
450,997 1,412,747 10,272,427 
457,354 1,412,571 10,271,104 
3,850 
3,850 
6,274 
6,274 
9,738 
9,738
5-9 
9,205 
9,205 
182,010 
181,933 
39,634 639,871 
39,651 639,871

NORFOLK, VA DISTRICT 
TABLE 5A COST AND FINANCIAL STATEMENT 
See Total 
Sect. Project Funding FY89 FY 90 FY91 FY92 To 30 Sept 92 
in Text. 
8. Hampton Roads, VA 
(Collection and 
Removal of Drift) 
9. James River, VA 
(Regular Funds) 
(Contributed Funds) 
10. Newport News 
Creek, VA 
(Regular Funds) 
11. Norfolk Harbor, VA 
(Regular Funds) 
(Contributed Funds) 
12. Tangier Channels, VA 
(Regular Funds) 
13. Tyler Beach Harbor, 
VA 
(Regular Funds) 
14. Rudee Inlet, VA 
(Regular Funds) 
(Contributed Funds) 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
193,000 
193,000 
204,400 
189,096 
216,000 
231,304 
496,000 4,501,384 
485,169 4,490,553 
- - - - 7,639,9045 
- - - - 7,639,904 
900,219 1,762,027 1,061,066 1,517,949 35,503,648 
898,399 1,249,130 1,578,387 1,518,707 35,503,251 
- - - - 413,456 
- - - - 379,792 
- 50,000 
- 2,520 
29,636 
29,636 
8,305 
8,305 
1,015,121 1,815,129 
1,185,908 813,749 
38,641 
38,641 
53,836 
441,441 
- 183,080 
45,754 181,354 
196,248 423,175 
196,247 423,174 
100,000 6,795,6326 
290,672 6,543,316 
3,384,391 2,508,553 5,466,669 3,354,059 96,610,683 
3,633,105 2,500,064 5,444,477 3,360,293 96,581,208 
104,989 - - - 1,805,4516 
145,452 13,092 274 - 1,762,697 
- 116,550 
- 116,550 
8,606 
8,474 
10,000 
32,998 
1,799 
50,000 
6,592 
18,018 
16,645 
15,625 
4,298 
4,298 
37,000 
36,093 
515,556 
517,058 
40,637 3,460,419 
40,637 3,460,417 
- 311,201 
- 311,201 
184,615 
160,614 
584,949 
579,568 
- 70,000 
- 67,723 
- 138,100 
42,940 35,631 
167,916 766,958 
191,855 766,896 
- 872,949 
7,866 873,489 
723,243 793,243 
725,502 793,225 
210,000 398,100 
254,668 339,831 
5-10

NORFOLK, VA DISTRICT 
TABLE 5A COST AND FINANCIAL STATEMENT 
See Total 
Sect. Project Funding FY89 FY 90 FY91 FY92 To 30 Sept 92 
in Text. 
15. Supervision of the 
Harbor of Hampton 
Roads, VA 
(Prevention of 
Obstruction and 
Injurious Deposits) 
(Regular Funds) 
16. Waterway on the 
Coast of VA 
(Regular Funds) 
17. Navigation Work 
Under Special 
Authorization 
18. Virginia Beach, VA 
(Regular Funds) 
19. Cape Charles 
Shoreline, VA 
(Regular Funds) 
(Contributed Funds) 
20. Beach Erosion Control 
Under Special 
Authorization 
21. James R. Olin Flood 
Control Project, VA 
(Regular Funds) 
22. Gathright Dam and 
Lake Moomaw, VA 
(Regular Funds) 
23. Richmond, VA 
(Regular Funds) 
(Contributed Funds) 
24. Emergency Flood 
Control Activities 
26. Surveys 
27. Collection and 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Cost 
Cost 
Cost 
518,000 
536,031 
473,500 494,000 
472,765 495,662 
308,000 7,780,324 
306,574 7,778,631 
- 850,498 
- 850,498 
996,215 
999,506 
62,088 
513,000 
157,402 
20,000 
4,797 
4,797 
899,530 898,584 1,271,274 16,722,833 
877,747 921,795 1,218,254 16,666,041 
67,249 76,993 140,830 
- (14,000) 900,000 8,746,195 
358,138 66,445 716,366 8,528,113 
10,000 18,000 
22,632 18,072 
22,632 18,072 
38,900 94,400 
28,863 74,364 
10,000 10,000 
13,729 
- 604,644 1,565,000 1,831,000 4,000,644 
- 493,403 1,415,058 1,244,937 3,153,398 
- - - - 80,970,527 
- - - 80,970,527 
1,086,000 1,214,736 989,537 1,357,721 13,845,158 
1,159,993 1,221,310 981,540 1,362,875 13,833,550 
3,800,000 19,562,999 22,700,000 
3,339,978 13,717,076 28,159,456 
26,813,000 77,042,000 
27,533,293 76,663,089 
90,012 3,019,978 5,494,337 5,515,000 14,019,326 
- 2,908,710 4,176,021 6,105,961 13,190,692 
174,385 210,475 199,488 407,392 
550,842 1,000,046 712,350 492,259 
154,051 
5-11 
248,829 133,214 150,078

NORFOLK, VA DISTRICT 
TABLE 5A COST AND FINANCIAL STATEMENT 
See Total 
Sect. Project Funding FY89 FY 90 FY91 FY92 To 30 Sept 92 
In Text. 
1 Includes $292,096 for previous projects. 
2 Includes $52,804 for previous projects. 
3 Costs prior to 1942 are included in the project "Baltimore Harbor and Channels, MD" (Baltimore District). Costs 
listed are for York Spit Channel, VA and Rappahannock Channel, VA. 
4 Includes $445,291 military funds expended from new work dredging on existing project and $83,041 expended 
military funds for construction of a wharf. 
5 Includes $763,000 for previous projects. 
6 Excludes previous projects. See Annual Report for FY 1986. 
5 -12

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 3, 1871 
June 13, 1902 
March 3, 1909 
June 25, 1910 
Jan. 21, 1927 
Mar. 2, 1945 
APPOMATTOX RIVER, VA (See Section 1 of Text) 
Channel 12 feet deep at mean high water and 60 feet wide. 
Diversion channel and work incidental thereto. 
increasing channel to width of 80 feet and maintenance of 
diversion works. 
Channel 80 feet wide and 10 feet deep at mean low water 
between mouth and Petersburg. 
Existing project dimensions. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA AND ST. JOHNS RIVER, FL 
(NORFOLK DISTRICT) (See Section 2 of Text) 
Mar. 3, 1899 Existing project dimensions and original route, waterway 
from Norfolk, VA to sounds of North Carolina 
July 25, 1912 
July 25, 1912 
Mar. 3, 1925 
Original route to Norfolk-Beaufort Inlet section 
Purchase of Albemarle & Chesapeake Co. Canal 
Purchase of Lake Drummond Canal (Dismal Swamp Canal) 
July 3, 1930 Construct a tidal lock at Great Bridge at a cost not to exceed 
$500,000 
June 26, 1934 Operating and care of works of improvement provided for with 
funds from War Department appropriations for rivers and 
harbors 
Mar. 2, 1945 Construct dikes for protection of canal property against 
floodtides 
BALTIMORE HARBOR AND CHANNELS (NORFOLK 
DISTRICT) (See Section 3 of Text) 
CAPE HENRY CHANNEL, VA (See Section 3 of Text) 
July 3, 1958 Channel 42 feet deep; 1,000 feet wide 
Dec. 31, 1970 Channel depth increased to 50 feet 
RAPPAHANNOCK SHOAL CHANNEL, VA 
(See Section 3 of Text) 
July 3, 1958 Channel 42 feet deep and 800 feet wide 
Dec. 31, 1970 Channel width increased to 1,000 feet and depth increased 
to 50 feet 
Mar. 3, 1905 
Mar. 4, 1913 
July 3, 1930 
Mar. 2, 1945 
July 3, 1958 
Dec. 31, 1970 
YORK SPIT CHANNEL, VA (See Section 3 of Text) 
Channel 35 feet deep, 600 feet wide 
Channel width increased to 1,000 feet 
Channel depth increased to 37 feet 
Channel depth increased to 39 feet 
Channel depth increased to 42 feet 
Channel depth increased to 50 feet 
July 14, 1960 BENNETTS CREEK, VA (See Section 4 of Text) 
(Sec. 107) Existing Project Approved in 1992 
June 25, 1910 
Aug 8, 1917 
Jan 21, 1927 
Oct27th 1965 
Oct 17, 1986 
July 14, 1960 
(Sec. 107) 
CHANNEL TO NEWPORT NEWS, VA. (See Section 5 of Text) 
Channel 35 feet deep, 400 feet wide 
Channel 35 feet deep, 600 feet wide 
Channel 40 feet deep, 600 feet wide 
Channel 40- feet deep, 800 feet wide, two deep-draft anchorage 
Deepen existing 45 foot channel to 55 feet 
CHINCOTEAGUE INLET, VA (See Section 6 of Text) 
Existing Project 
CRANES CREEK, VA (See Section 7 of Text) 
Mar. 2, 1945 Entrance Channel 6 feet deep, 80 feet wide 
Annual Report 1874, pt. 11 p. 54 
H. Doc. 139, 56 Cong., 2d sess. 
and Annual Report 1901, p. 1467 
H. Doc. 952, 60th Cong., 1st sess. 
H. Doc. 215, 69th Cong., 1st sess. 
H. Doc. 223, 76th Cong., 1st sess.(1) 
H. Doc. 317, 54th Cong., 1st sess. 
AR 1896 
H. Doc. 131, 55th Cong., 3rd sess. 
AR 1899 
H. Doc. 391, 62nd Cong., 2nd sess. 
H. Doc. 589, 62nd Cong., 2nd sess. 
Rivers & Harbors Comm. Doc. 
67th Cong., 2nd sess. 
S. Doc. 23, 71st Cong., 1st sess.1 
Not available 
H. Doc. 117, 76th Cong., 1st sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report, Sept. 21, 1970 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report, Sept, 21, 1970 
H. Doc. 186, 57th Cong., 2nd sess. 
H. Doc. 190, 62nd Cong., 3rd sess. 
H. Doc. 29, 71st Cong., 1st sess. 
H. Doc. 741, 79th Cong., 2nd sess. 
H. Doc. 86, 85th Cong., 1st sess. 
Chief of Engineers Report Sept. 21, 1970 
Unpublished Report 
H. Doc. 550, 61st cong.,2nd sess. 
H. Doc. 486, 67th Cong., 4th sess. 
H. Doc. 143, 89th Cong., 2nd sess. 
Approved in 1972 
H. Doc. 687, 76th Cong., 3d sess. 
5-13

TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
HAMPTON ROADS AND HARBORS OF NORFOLK AND 
NEWPORT NEWS, VA COLLECTION AND REMOVAL 
OF DRIFT (See Section 8 of Text) 
May 17, 1950 Collection and removal of floating debris in Hampton Roads and specified in Act 
its tributary waters 
JAMES RIVER, VA (See Section 9 of Text) 
July 5, 1884 Channel 22 feet deep from mouth of Richmond and construct spur 
and training dikes 
June 13, 1902 Extension of improvement to Richmond lock gate 
Mar. 3, 1905 Form a turning basin by widening channel at Richmond 
July 3, 1930 Channel 25 feet deep mouth to Richmond Deepwater Terminal 
Aug. 26, 1937 Removal of Trigg cofferdam 
Mar. 2, 1945 Turning basin at Richmond Harbor 
May 17, 1950 Maintaining turning basin at Richmond Deepwater Terminal 
Oct. 23, 1962 Channel depth increased to 35 feet to Richmond Deepwater 
Terminal 
NEWPORT NEWS CREEK (See Section 10 of Text) 
July 24, 1946 Existing project 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Sept. 3, 1954 
Oct. 27, 1965 
Oct. 17, 1986 
NORFOLK HARBOR CHANNEL, VA 
(See Section 11 of Text) 
HAMPTON ROADS AND ELIZABETH RIVER 
Channel 30 feet deep to Navy Yard 
Depth of 35 feet to Navy Yard 
Depth of 40 feet and width of 750 feet to mouth of Southern 
Branch 
Widen 40-foot channel to 1,500 feet from 40-foot contour in 
Hampton Roads to a point just south of Norfolk 
International Terminal 
45 feet deep Ft. Wool to Lambert Point, 800 feet wide Norfolk 
International Terminal to Lambert Point 
Deepen existing 45 foot channel to 55 feet deep 
SOUTHERN BRANCH 
June 25, 1910 Channel with a depth of 22 and 25 feet 
Aug. 8, 1917 Depth of 40 feet and width of 450 feet from mouth to Belt Line 
RR Bridge 
Mar. 30, 1925 Channel 30 feet deep and 375 feet wide to Virginia RR bridge: 
thence 25 feet deep and generally 200 feet wide to Norfolk & 
Western RR bridge 
Aug. 30, 1935 Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to a point 2,500 feet above with a turning basin 500 
feet square 
June 30, 1948 Approach and turning area 40 feet deep and a maximum width 
of 830 feet opposite Norfolk Naval Shipyard: thence a channel 
35 feet deep and 375 and 250 feet wide to a point 1900 feet 
above Norfolk & Western RR bridge and a turning basin 35 
feet deep and 600 feet at upstream end 
Oct. 27, 1965 45 feet deep Belt Line bridge to Old Virginia bridge, 35-foot 
deep turning basin opposite St. Julians Creek 
Oct. 22, 1976 Extend existing 35-foot project to a channel 35 feet deep and 
250 feet wide upstream 1.5 miles to the Norfolk and 
Portsmouth Belt Line RR bridge and a turning basin at the 
mouth of Mains Creek 35 feet deep and 800 feet square 
Oct. 17, 1986 Deepen existing 40-foot portions to 45-feet deep 
Deepen portion of the 35-foot, from mile point 15 to Gilmerton Bridge, 
to 40 feet deep 
Mar. 2, 1907 
Mar. 3, 1925 
July 3, 1930 
EASTERN BRANCH 
Width of 500 feet and depth of 25 and 22 feet 
Removal of shoals at mouth 
Depth of 25 feet and width of 200 feet from Norfolk & Western 
RR bridge to Virginia RR bridge 
30-foot channel to a point opposite terminal of Imperial 
Tobacco Co. in Berkley 
5-14 
S. Ex. Doc. 714, 47th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 234, 56th Cong., 1st sess. 
H. Doc. 314, 71st Cong., 2nd sess. 
Rivers & Harbors Comm. Doc. 68 
74th Cong., 1st sess.2 
H. Doc. 738, 77th Cong., 2nd sess. 
H. Doc. 191, 81st Cong., 1st sess. 
H. Doc. 586, 87th Cong., 2nd sess. 
J. Doc. 559, 79th Cong., 2nd Sess. 
H. Doc. 381, 59th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2nd sess. 
H. Doc. 140, 65th Cong., 1st sess. 
S. Doc. 122, 83rd Cong., 2nd sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc 1013, 99th Cong., 2nd sess. 
H. Doc. 551, 61st Cong., 2nd sess. 
H. Doc. 140, 65th Cong., 1st sess. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 182, 73rd Cong., 2nd sess.2 
H. Doc. 545, 80th Cong., 2nd sess. 
H. Doc. 187, 89th Cong., 1st sess. 
H. Doc. 355, 94th Cong., 2nd sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 373, 59th Cong., 1st sess. 
Specified in act. 
H. Doc. 226, 68th Cong., 1st sess. 
H. Doc. 37, 71st Cong., 1st sess. 3

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
TABLE 5-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 Depth of 25 feet and width of 300 feet from Norfolk & Western 
RR bridge to Campostella bridge 
Mar. 4, 1913 
July 3, 1930 
WESTERN BRANCH 
Channel 24 feet deep and 300 & 400 feet wide to West 
Norfolk highway bridge 
For 18-foot channel to a point about 3,000 feet above West 
Norfolk highway bridge 
SCOTTS CREEK 
July 3, 1930 Channel 12 feet deep and 100 feet wide to a point 100 feet above 
the Atlantic Coast Line RR bridge 
June 25, 1910 
Aug. 8, 1917 
Sept, 3, 1954 
Oct. 27, 1965 
Oct. 17, 1986 
Mar. 2, 1919 
Jan. 3, 1934 
(P.W,A,Act) 
& Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
(Sec. 107) 
July 14, 1960 
(Sec. 107) 
July 14, 1960- 
(Sec. 107) 
ANCHORAGES 
30-foot anchorage at Lambert Point 
12-foot anchorage at Pinner Point 
An anchorage 38 feet deep and 1,500 feet square: anchorage 
35 feet deep and 1,500 feet square: and an anchorage 20 
feet deep, 1,000 feet wide and 3,000 feet long 
Two anchorages opposite Sewells Point 45 feet deep with 
1,200-foot swinging radius 
Construct a 55-foot anchorage and increase the radius 
to 1500 feet for an existing 45-foot anchorage 
TANGIER CHANNEL, VA (See Section 12 of Text) 
Channel from Tangier Sound and anchorage 
Modified project deminsions 
Channel across Tangier Island 
TYLERS BEACH, VA. (See Section 13 of Text) 
Existing Project 
Jetty Modification 
RUDEE INLET, VA (See Section 14 of Text) 
Jul 14, 1960 Project Authorized 
(Sec. 107) Existing Project Approved in 1986 
June 25, 1910 
Mar. 2, 1945 
Sept. 3, 1954 
Oct. 23, 1962 
Mar. 7, 1974 
Oct. 17, 1986 
Nov. 28, 1990 
Oct. 5, 1992 
Jul. 24, 1946 
(Sec. 14) 
Nov. 28, 1990 
Oct. 5, 1992 
WATERWAY ON THE COAST OF VIRGINIA 
(See Section 16 of Text) 
Existing project adopted 
Project modified 
VIRGINIA BEACH, VA (See Section 18 of Text) 
Project authorized 
Project modified 
Project modification authorized for Phase I Advanced 
Engineering and Design 
Project Modified 
Participation after Feb. 6, 1987 
Cost Sharing 
H. Doc. 224, 76th Cong., 1st sess. 
H. Doc. 556, 62nd Cong., 2nd sess. 
H. Doc. 265, 70th Cong., 1st sess. 
H. Doc. 189, 70th Cong., 1st sess. 
H. Doc. 551, 61st Cong., 2nd sess. 
H. Doc. 605, 63rd Cong., 2nd sess.1 
S. Doc. 122, 83rd Cong., 2nd sess.1 
H. Docs. 187 & 143, 89th Cong., 1st sess. 
H. Doc. 1013, 99th Cong., 2nd sess. 
H. Doc. 107, 63rdCong., 1st sess. 
River harbors Comm. 
Doc. 51, 72nd Cong., 2nd sess. 
H. Doc. 141, 77th Cong., 1st sess. 
Approved in 1964 
Approved in 1966 
Approved in 1981 
Unpublished Report 
H. Doc. 957, 60th Cong., 1st sess. 
H. Doc. 268, 76th Cong., 1st sess. 
H. Doc. 186, 83rd Cong., 1st sess. 
H. Doc. 382, 87th Cong., 2nd sess. 
H. Doc. 365, 92nd Cong., 2nd sess. 
H. Doc. 216, 99th Cong., 2nd sess. 
CAPE CHARLES SHORELINE, VA (See Section 19 of Text) 
Existing Project Approved in 1992 Unpublished Report 
JAMES R. OLIN FLOOD CONTROL PROJECT, VA (See Section 21 of Text) 
(Formerly BUENA VISTA, VA) 
Project authorized Chief of Engineers Report, July 27, 1990 
Name of Project Changed 
GATHRIGHT DAM AND LAKE MOOMAW, VA (See Section 22 of Text) 
July 24, 1946 Project authorized H. Doc. 325, 61st Cong., 2nd sess. 
RICHMOND, VA (See Section 23 of Text) 
Existing project H. Doc. 178, 98th Cong., 2nd sess. 
5-15 
Aug. 15, 1985

TABLE 5-C 
Report of the Secretary of the Army on Civil Works Activities For FY 1992 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA AND ST. JOHNS RIVER, FLORIDA: 
DATA RELATIVE TO THE COMPLETED LOCKS 
(See Section 2 of Text) 
Dimensions 
Greatest 
Length Depth on 
Width Available Miter Sills Year 
Miles of for Full Character Opened Construction 
From Location Chamber Width Lift Upper Lower of to Cost 
Norfolk, VA feet (feet) (feet) (feet) (feet) Foundation Navigation 
12.4 Albemarle and 75 600 2.7 1 1 Piles in sand 1932 $499,913 
Chesapeake Canal and shells 
(Great Bridge, VA) 
10.7 Dismal Swamp 52 300 12 12 12 Natural earth 1940 $348,879 
Canal (Deep Creek) with cutoff 
walls 
33.1 Dismal Swamp 52 300 12 12 13 Natural earth 1941 $373,226 
Canal with cutoff walls 
(South Mills, NC) 
116 feet at mean low water. 
5-16

TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30, 1992 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For 1992 Construction Maintenance Contributed Funds 
Aberdeen Creek, VA 1975 109,643 221,827 
Appomattox River, VA 1 1992 $870,341 4,794,436- 
Atlantic Ocean Channel, VA 1991 608,255 -- 
Bennett Creek, VA 1992 442,602 - 104,621 
Blackwater River, VA 
Active portion2 10 1975 342,118 181,317 19,300 
Broad Creek, VA2 1986 27,888 684,156 500 
Cape Charles, VA 1989 622,644 2,449,473 
Carters Creek, VA 
Active portion2 3 1951 28,398 3,277- 
Channel to Newport News, VA 1992 4,097,117 7,105,145 4,965,108 
Channel from Phoebus, VA 
to deepwater in Hampton Roads2 1944 11,500 64,919 1,200 
Channel connecting York River, VA 
Back Creek to Slaights Wharf2 1950 14,855 38,634 2,500 
Chesconessex Creek, VA2 1968 25,516 43,775- 
Chincoteague Bay, VA 1984 25,126 499,340- 
Chincoteague Harbor of Refuge, VA 1985 49,396 217,592 
Chowan River, NC2 1975 107,220 - 5,700 
Cockrells Creek, VA4 1949 - -- 
Cranes Creek, VA 1992 6,274 639,871- 
Davis Creek, VA 2 1971 97,612 213,105 4,000 
Deep Creek, Accomack Co., VA 1974 83,000 142,907- 
Deep Creek, Newport News, VA2 1991 288,278 3,271,714- 
Dymers Creek, VA2 1953 5,582 4,610- 
Finney Creek at Wachapreague, VA 1988 68,656 - 7,763 
Greenvale Creek, VA 1991 20,003 609,112- 
Hampton Creek, VA 1989 186,237 1,219,638 62,969 
Horn Harbor, VA2 1990 13,987 346,230- 
Hoskins Creek, VA2 1990 44,100 1,608,896 500 
Jackson Creek, VA2 1971 8,500 36,486- 
Jarvis Creek, VA4 1979 39,259 - 
Kings Creek, VA4 1957 5,593 -- 
Lafayette River, VA2 1982 242,047 364,452 188,962 
Little Machipongo River, VA 1990 211,990 533,700 1,211 
Little River (Creek), VA212 1966 168,623 520,995 16,955 
Locklies Creek, VA2 1928 11,581 64,517 
Lynnhaven Inlet, VA 1991 459,612 2,984,952- 
Mattaponi River, VA 1971 83,836 209,040 
Meherrin River, VA 1987 47,734 54,764 
Miliford Haven. VA 1950 24,568 33,001 
Mill Creek, VA 1937 5,445 21,536- 
Mulberry Creek, VA2 1950 2,393 2,458 
Nandua Creek, VA2 1950 6,988 91,265 
Nansemond River, VA6 1978 167,477 499,555 
Newport News Creek, VA2 1992 181,354 423,174- 
Nottoway River, VA2 1986 44,295 8,734 43,000 
Occohannock Creek, VA 
Active portion2 1951 13,859 92,044- 
Onancock River, VA25 1963 187,914 492,703- 
Oyster Channel, VA2 1991 119,117 756,517 
Pagan River, VA2 6 1950 51,425 311,612 
Pamunkey River. VA 
Active portion 1964 31,376 161,183 
Parker Creek, VA 1991 15,530 559,767 
Parrotts Creek, VA2 1957 37,045 54,575 
Portsmouth Harbor, VA Channel to 
Nansemond Ordnance Depot2 1947 165,566 66,162 
Queens Creek2 1991 26,949 397,274 
Quinby Creek, VA 1991 104,176 1,484,027 
Rappahannock River, VA 9 1 1 1983 414,633 1,962,057 
Rappahannock River at 
Bowlers Wharf, VA4 1950 - - 
Starlings Creek, VA 1991 66,242 1,095,549 
Tangier Channels, VA 1992 116,550 3,460,417 
Taskinas Creek, VA 1975 7,479 135 
Thimble Shoal Channel, VA13 1991 17,934,772 14,789,255 3,459,868 
Totuskey Creek, VA 1970 167,869 451,293 2,000 
Tylers Beach Harbor, VA2 1982 311,201 766,896- 
5-17

Report of the Secretary of the Army on Civil Works Activities For FY 1992 
TABLE 5-D OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Full Cost to Sept. 30, 1992 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
1992 
Urbanna Creek, VA 2 7 1963 55,724 113,300 
Whitings Creek, VA 1990 21,630 405,720 500 
Winter Harbor, VA2 1981 171,334 337,178 2,973 
Willoughby Channel, VA2 1953 8,500 67,319- 
Wishart Point Channel, VA2 1975 118,762 102,527 30,625 
York River, VA 
Active portion2 1986 180,904 302,068 
1lncludes $22,500 for previous projects. 8In addition, $168,091 was expended for rehabilitation. 
2Completed. 9lncludes $197,146 for previous new work projects. 
31n addition, $700 for maintenance was expended from contributed funds. 1 lncludes $15,000 for new work for previous projects. 
45Innaclcutidvees. 11ncludes $113,500 for previous maintenance projects $33,549 for new work and $24,754 for maintenance for pre- 12Federal funds expended by the U.S. Navy for new work 
vious projects. 131n addition, $143,000 for maintenance was expended from contributed 
61ncludes $20,671 for new work for previous projects. funds. 
In addition, $61,087 was expended for rehabilitation 
TABLE 5-E OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Full Cost to Sept. 30, 1992 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintence 
1992 Contributed Funds 
Anderson Park, Newport News, VA 1979 $471,474 632 $176,671 
Hampton Institute, VA 1976 $156,906 1,589 $175,845 
Rapidan River, Orange, VA 1984 45,000 - - 
Saxis Island, VA 1987 $273,600 - $ 3,145 
Tangier Island Shore Protection, VA 1990 $2,478,825 1,812 1,379,371 
TABLE 5-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to Sept. 30, 1992 Additional Expenditure 
Project Report, See For New Work 
Annual Report Expended From 
For Construction Maintenance Contributed Funds 
1992 
Newmarket Creek, VA 1970 1,000,000 13,295 $550,097 
Norfolk Floodwall, VA 1973 1,851,933 40,342 516,256 
Richmond Filtration Plant, VA 1985 478,2241 
Scottsville, VA 1989 3,431,746 7,725 32,954 
Virginia Beach Canal No. 2, VA 1990 4,692,063 48,785 216,596 
1 Preconstruction planning terminated. 
5-18

NORFOLK, VA DISTRICT 
TABLE 5G RECONNAISSANCE AND CONDITION SURVEYS 
PROJECT NAME MO 
Aberdeen Creek 
Atlantic Ocean Channel 
Atlantic Intracoastal Waterway: 
Deep Creek 
Dismal Swamp Canal 
Baltimore Harbor and Channels: 
Cape Henry 
Rappahannock Shoal Channel 
York Spit Channel 
Broad Creek, Middlesex Co. 
Cape Charles City Harbor 
Channel connecting York River 
with Back Creek to Slaights Wharf 
Chesconessex Creek 
Davis Creek 
Deep Creek, Accomack Co. 
Hoskins Creek 
James River: 
Jordon Point to Windmill Point 
Richmond Deepwater Terminal to Hopewell 
Richmond Deepwater Terminal 
Rocklanding Shoal Channel 
Tribell Shooal 
Lynnhaven Inlet 
Onancock River 
Nansemond River: 
Western Branch 
Norfolk Harbor: 
Southern Branch 
Western Branch 
Starlings Creek 
Tangier Channels 
Whitings Creek 
Whitings Creek 
Willoughby Channel 
NTHIYEAR TYPE OF SURVEY 
Oct 91 
Oct 91 
Condition 
Reconnaissance 
Condition 
Condition 
Jun 92 
Mar 92 
Aug 92 
Oct 91 
Sep 92 
May 92 
Aug 92 
Nov 91 
Jun 92 
Jul 92 
May 92 
Apr 92 
Jan 
Dec 
Jul 
Feb 
May 
Mar 
Sep 
Reconnaissance 
Condition 
Condition 
Reconnaissance 
Reconnaissance 
Condition 
Reconnaissance 
Reconnaissance 
Reconnaissance 
Reconnaissance 
Condition 
Condition 
Reconnaissance 
Condition 
Condition 
Condition 
Reconnaissance 
92 
91 
92 
92 
92 
92 
92 
May 92 
Nov 91 
Dec 91 
Sep 92 
Aug 92 
Nov 91 
Sep 92 
Jun 92 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
Condition 
5 -19

WILMINGTON, N. C., DISTRICT* 
This district comprises central and eastern North 
Carolina and a portion of south-central Virginia, embraced 
in drainage basins tributary to the Atlantic Ocean from 
the southern boundary of Virginia to the Shallotte River, 
inclusive, with exception of the Meherrin River Basin 
above Murfreesboro, N. C., the Chowan River Basin above 
the confluence of the Nottaway and Blackwater Rivers, 
and the Pasquotank River and its tributaries for navigation 
only. Also included are those portions of the Yadkin- 
Pee-Dee and Catawba River basins within the state of 
N. C. as well as a portion of the Atlantic Intracoastal 
Waterway from the northern boundary of North Carolina 
to Little River, S. C., and a portion of the waterway from 
Norfolk, Va., to the Sounds of North Carolina, south of the 
north shore of Albemarle Sound. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control 
(R & H Actof 1965).........................6-2 
2. Atlantic Intracoastal Waterway 
Between Norfolk, Va. and St. Johns 
River, Fla. (Wilmington District).............. 6-2 
3. Beaufort Harbor, N. C........................6-4 
4. Cape Fear River, N. C. Above Wilmington...... 6-4 
5. Channel from Back Sound to 
Lookout Bight, N. C.........................6-5 
6. Drum Inlet, N. C............................6-5 
7. Far Creek, N. C............................6-5 
8. Lockwoods Folly River, N. C................ 6-5 
9. Manteo (Shallowbag) Bay, N. C.. .......... 6-6 
10. Morehead City Harbor, N. C...................6-7 
11. Pamlico and Tar Rivers, N. C..................6-7 
12. Rollinson Channel, N. C......................6-8 
13. Shallotte River, N. C ............ ............ 6-8 
14. Silver Lake Harbor, N. C.....................6-8 
15. Stumpy Point Bay, N. C....................6-9 
16. Waterway Connecting Pamlico Sound 
and Beaufort Harbor, N. C...................6-9 
17. Wilmington Harbor, N. C....................6-9 
Flood Control 
18. Cape Fear River Basin, N. C................ 6-10 
18A. B. Everett Jordan Dam and Lake, N. C........ 6-11 
18B. Randleman Lake, N. C.................. 6-11 
19. Carolina Beach and Vicinity, N. C.......... 6-11 
20. Neuse River Basin, N. C.................. 6-12 
20A. Falls Lake, N. C...........................6-12 
21. Hamlet City Lake, N. C......................6-13 
22. Lower Creek, Lenoir, N. C...............6-13 
23. Neuse River, Oriental, N. C............... 6-14 
24. Roanoke River Upper Basin, 
Va.- Headwaters Area.....................6-14 
Page 
25. Yadkin River Basin, N. C. and S. C............6-14 
25A. W. Kerr Scott Dam and 
Reservoir, N.C................ ............ 6-15 
26. Inspection of Completed 
Flood Control Projects.....................6-15 
27. Flood Control Work Under 
Special Authorization....................... 6-15 
Multiple-Purpose Projects, 
Including Power 
28. Roanoke River Basin, Va. and N. C.. ..... 6-15 
28A. John H. Kerr Dam and Reservoir, 
Va. and N .C................. .............. 6-15 
28B. Philpott Lake, Va...........................6-16 
29. Scheduling Flood Control 
Reservoir Operations......................6-16 
General Investigations 
30. 
31. 
32. 
Surveys..................................6-17 
Collection and Study of Basic Data...........6-18 
Preconstruction Engineering and Design....... 6-18 
Tables Page 
Table 6-A Cost and Financial Statement.......... 6-19 
Table 6-B Authorizing Legislation.............. 6-23 
Table 6-C Other Authorized 
Navigation Projects.................6-26 
Table 6-D Other Authorized Beach Erosion 
Control Projects..................... 6-27 
Table 6-E Other Authorized Flood Control 
Projects ...... ...................... 6-28 
6-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Tables Page 
Table 6-F Not Applicable 
Table 6-G Deauthorized Projects................ 6-29 
Table 6-H Reconnaissance and 
Condition Surveys.................... 6-30 
Table 6-I Navigation Work Under 
Special Authorization................. 6-30 
Table 6-J Dams and Reservoirs................ 6-31 
Table 6-K Flood Control Work Under 
Special Authorization................ 6-32 
Navigation 
1. AQUATIC PLANT CONTROL (RIVER AND HARBOR 
ACT OF 1965) 
Location. Navigable waters, tributary streams, connecting 
channels, and other allied waters in Wilmington 
District. 
Existing project. The existing project provides for control 
and progressive eradication of water-hyacinth, 
alligatorweed, Eurasian watermilfoil, and other obnoxious 
aquatic plant growths from navigable waters, tributary 
streams, connecting channels, and other allied waters of 
the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of the most effective 
and economic control measures in cooperation with other 
Federal and State agencies in accordance with the report 
of the Chief of Engineers, House Document 251, 89th Congress, 
1st session. The project was authorized by Section 
302, 1965 River and Harbor Act (H.D. 25, 89th Cong., 1st 
sess.). The Act provides that research and planning costs 
shall be borne fully by the United States. 
Local cooperation. Local interests must agree to hold 
the United States free from damages that may occur from 
operations performed in connection with this project, and 
participate to the extent of 50 percent of the cost of the 
program. Recon studies are 100 percent Federal. Requirements 
are being met. 
Operations and results during fiscal year. New work: 
Operations for FY 92 included chemical control on about 66 
river miles of alligatorweed (about 15 treatment acres), 
biological control of hydrilla at 1 lake (25 acres of hydrilla), 
and monitoring of biological control of hydrilla at 8 sites 
stocked with triploid grass carp in previous years. 
All alligatorweed control in FY 92 was by the application 
of rodeo herbicide. All treatment sites are under 
maintenance control. Control sites include the Scuppernong 
Basin (5 acre/21 river miles), Little River Basin (1 
acre/9 river miles), Pasquotank River Basin (2.5 acres/14 
river miles), Alligator River Basin (4 acres/9 river miles), 
Lumber River Basin (4 acres/21 river miles) and Mackeys 
Creek (.5 acres/? river miles). No new alligatorweed treatment 
areas were added to the program in FY 92. 
One hydrilla biological control site, Brier Creek Reservoir 
(a 500 acre impoundment with 25 acres of hydrilla) was 
stocked with triploid grass carp in FY 92. About 5 acres of 
hydrilla in Lake Crabtree were treated with aquatic herbicide 
in FY 92. 
Monitoring of hydrilla control sites previously stocked 
with triploid grass carp to determine the effectiveness of 
the stocking and predict future control was continued in 
FY 92. 
Condition at end of fiscal year. All alligatorweed treatment 
sites under maintenance control in FY 92 are expected 
to remain under maintenance control. A biennial 
treatment schedule in some maintenance level 
alligatorweed control sites implemented in FY 92 will continue 
in FY 93. 
Monitoring of hydrilla control sites previously stocked 
with triploid grass carp indicates that overall our 
biological control efforts have been effective. Supplemental 
stocking has been required to achieve control in some 
sites. Restocking on at least a once every 5-year basis is expected 
to be required to maintain weed control in these 
sites. 
Investigations of aquatic weed problems, in response to 
requests by county governments and muncipalities, may 
result in the addition of new treatment sites and species in 
future years. 
All planning efforts in FY 92 were at the reconnaissance 
level and included ongoing work for the expansion of the 
program for inclusion of new treatment areas. 
Operations were accomplished for a Federal cost of 
$44,085. Planning was accomplished at a Federal cost of 
$3,145. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA., AND ST. JOHNS 
RIVER, FLA. (WILMINGTON DISTRICT) 
Location. The project is located on the east coast of the 
United States, between Norfolk, Va., and St. Johns River, 
Florida. The section within Wilmington District begins at 
the Virginia-North Carolina State line and extends 
generally southerly and southwestwardly to Little River, 
S. C., a total of 308 statute miles. (See Coast and Geodetic 
Survey Charts 830 to 842, inclusive.) 
Previous projects. For details see Annual Reports for 
1915, 1926, 1932, and 1938. 
Existing project. The authorized project provides for a 
waterway, 12 feet deep, with widths varying from 90 feet 
in land cuts to 300 feet in open waters; the construction, 
operation and maintenance of suitable bridges; saltwaterintrusion 
preventive measures in the vicinity of Fairfield, 
N. C.; a channel in Peltier Creek, 6 feet deep and 50 feet 
wide from the Intracoastal Waterway in Bogue Sound to 
and including a basin in Peltier Creek, 6 feet deep, 200 feet 
wide, and 600 feet long; a channel, 6 feet deep and 90 feet 
wide between the Intracoastal Waterway and the gorge in 
Bogue Inlet, then 8 feet deep and 150 feet wide across the 
ocean bar; a channel, 12 feet deep and 90 feet wide to a 
turning basin, 200 feet wide and 350 feet long, at 
Swansboro; a channel, 6 feet deep and 90 feet wide in New 
6-2

WILMINGTON, N. C., DISTRICT 
River Inlet, and a connecting channel of the same dimensions 
to the Intracoastal Waterway near the mouth of New 
River; a channel, 10 feet deep, and 90 feet wide in New 
River, between the Intracoastal Waterway and the 
Seaboard Coastline Railroad bridge at Jacksonville, N. C.; 
a channel through New Topsail Inlet, 8 feet deep and 150 
feet wide and a channel from New Topsail Inlet to the Intracoastal 
Waterway by way of Old Topsail Creek, 7 feet 
deep and 80 feet wide; a channel, 7 feet deep and 80 feet 
wide, in Banks Channel, from New Topsail Inlet, paralleling 
the barrier beach, to the Atlantic Intracoastal Waterway; 
a channel, 14 feet deep and 400 feet wide, across the 
ocean bar at Masonboro Inlet, with suitable jetties at the 
entrance, thence 12 feet deep and 90 feet wide to the channel 
of the Intracoastal Waterway at Wrightsville Beach by 
way of Banks and Motte Channels; a turning basin, 15 feet 
deep, 300 feet wide, and 700 feet long, on the east side of 
Banks Channel near Masonboro Inlet, with three 15-pile 
dolphins therein; a channel, 8 feet deep and 150 feet wide 
across the ocean bar at Carolina Beach Inlet to the Atlantic 
Intracoastal Waterway; a channel, 6 feet deep, 80 feet 
wide, and 8,000 feet long, to and including a turning basin 
of the same depth, 130 feet wide and 180 feet long, at 
Carolina Beach; a yacht basin, 230 feet wide, 450 feet long, 
and 12 feet deep, at the town of Southport, connected to 
the waterway by a suitable channel of the same depth; and 
maintenance of the general navigation features of the 
North Carolina State Ports Authority Small-Boat Harbor 
at Southport, consisting of an entrance channel, 150 feet 
wide and 400 feet long, an eastern harbor-access channel, 
70 feet wide and 430 feet long, a western harbor-access 
channel, 60 feet wide and 185 feet long, to a turning basin, 
180 feet wide and 550 feet long, all to a depth of 6 feet. A 
modification providing for the replacement of five Federally 
owned and operated highway bridges was authorized in 
December 1970. A modification providing for 100 percent 
Federal funding for Walter B. Jones (formerly Wilkerson 
Creek) and Joseph P. Knapp (formerly Coinjock) bridges 
was authorized in October 1976. A modification providing 
for 100 percent Federal funding at Core Creek, Hobucken, 
and Fairfield bridges was authorized in November 1986. 
Estimated Federal cost is $69,497,000 (1992). The tidal lock 
at Snow's Cut was deauthorized September 23, 1986, 
under authority of Sec. 12, PL 93-251. The 12-foot-deep 
channel in Peltier Creek was deauthorized by the Water 
Resources Development Act of 1986. The 12-foot deep 
channel modification to New River was deauthorized 
January 1, 1990, under Sec. 1002, PL 99-662. The jetties at 
Masonboro Inlet are complete except for the training wall. 
The training wall has an estimated Federal cost of 
$3,470,000 (1992). The wall was reclassified to the 
"inactive" category on August 14, 1992. A Section 111 project 
to mitigate damages caused by the north jetty was 
authorized in October 1980 and was completed in April 
1981. Length of channels and basins total 347.7 miles. 
Plane of reference is mean low water. 
In the waterway north of Neuse River, variations in 
water surface due to winds seldom exceed 2 feet above or 
below mean stage. Between Beaufort and the Cape Fear 
River, normal tidal range varies from 3.5 feet at the inlets 
to 1 foot at points between. Average range of tide is 4 feet 
on the ocean side of Bogue Inlet and 2.5 feet just inside the 
inlet. At New River, tidal range varies from 3.5 feet at the 
inlet to 1 foot at the head of the marshes and zero at Tar 
Landing, 31 miles above. From Cape Fear River, N. C., to 
Little River, S. C., mean tidal range varies between 4.7 
feet in Cape Fear River and 4 feet at the intermediate inlets, 
and 2 feet at points midway between the inlets. On October 
15, 1954 (Hurricane Hazel), the tide at Holden Beach 
reached an elevation of 17.6 feet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date except 
for the uncompleted modifications. The State of North 
Carolina has agreed to keep the bridges toll free and upon 
completion of each bridge, accept maintenance, replacement, 
and ownership responsibilities thereof. They have 
withdrawn their offer to contribute 25 percent of the first 
cost. The Water Resources Acts of 1976 and 1986 modified 
the terms of local cooperation to delete the non-Federal 
cost-sharing requirement for all five bridges. 
Operations and results during fiscal year. New work: 
Construction of Core Creek Bridge was continued at a 
cost of $5,087,639. Design of Hobucken Bridge was continued 
at a cost of $603,966. Design of Fairfield Bridge 
was continued at a cost of $219,129. Work in connection 
with the completion of Joseph P. Knapp Bridge resulted 
in a negative cost of $25,546. Work in connection with 
the General Design Memorandum for the Masonboro Inlet 
jetties cost $38. Maintenance: Through Channel 
-During intermitent periods the U. S. debris boat Snell 
conducted clearing and snagging operations and maintained 
dredging ranges and mooring facilities at a cost 
of $116,901. Between November 30, 1991, and February 
1, 1992, the contract dredge Jekyll Island removed 231, 
268 cubic yards from shoals in Inlet Crossings at a cost 
of $1,577,626. Between December 6, 1991, and January 
13, 1992, the contract dredge Marion removed 129,337 
cubic yards from shoals in the channel at a cost of 
$410,613. Between January 13 and May 1, 1992, the contract 
dredge Juanita B removed 327,289 cubic yards 
from shoals in the channel at a cost of $595,603. Between 
January 27 and April 10, 1992, the contract dredge 
Stuart removed 245,596 cubic yards from shoals in Inlet 
Crossings at a cost of $949,058. Removal of ordnance in 
connection with prior year pipeline dredging of the 
AIWW-Wilmington District thru Camp Lejeune, N. C., 
between Brown and Bear Inlets, cost $9,479. Design cost 
for future year maintenance dredging was $1,354. Mosquito 
control in disposal areas cost $36,000. Archeological 
investigations of sounds and inlets cost $74. 
Condition and operation studies cost $508,812. Interim 
inspection of three remaining bridges cost $1,949. Longterm 
environmental dredging and monitoring study cost 
$1,524. Master Plan supplement for Snow's Cut cost 
$10,921. Three highway bridges and utilties were 
operated and maintained at a cost of $620,209. Design 
cost changes for future year pipeline dredging cost 
$5,930. Environmental Review Guide for Operations 
(ERGO) investigations cost $2,500. Bogue Inlet - During 
intermittent periods the U. S. sidecasting dredge Merritt 
removed 119,042 cubic yards from shoals in Bogue 
Inlet at a cost of $480,892. Condition and operation 
6-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
studies cost $24,062. Carolina Beach Inlet - During intermittent 
periods the U. S. debis boat Snell conducted 
clearing and snagging operations and maintained dredging 
ranges and mooring facilties at a cost of $34,823. 
During intermittent periods the U. S. sidecasting dredge 
Merritt removed 57,956 cubic yards from shoals in 
Carolina Beach Inlet at a cost of $264,587. During intermittent 
periods the U. S. hopper dredge Curritusck 
removed 110,937 cubic yards from shoals in Carolina 
Beach Inlet at a cost of $290,252. During intermittent 
periods the U. S. sidecasting dredge Fry removed 74,081 
cubic yards from shoals in Carolina Beach Inlet at a cost 
of $267,994. Monitoring of Carolina Beach Inlet cost 
$14,025. Condition and operation studies cost $23,333. 
Masonboro Inlet - Work in connection with prior year 
pipeline dredging Masonboro Inlet and Banks Channel 
cost $31. Condition and operation studies cost $294. 
Preparation of the rehabilitation report for the north 
jetty at Masonboro Inlet was continued at a cost of 
$48,851. Monitoring at Masonboro Inlet cost $35,736. 
New River Inlet - During intermittent periods the U. S. 
sidecasting dredge Merritt removed 154,168 cubic yards 
from shoals in New River Inlet at a cost of $478,359. During 
intermittent periods the U. S. sidecasting dredge 
Fry removed 84,231 cubic yards from shoals in New 
River Inlet at a cost of $237,600. Condition and operation 
studies cost $35,192. New Topsail Inlet - During intermittent 
periods the U. S. debris boat Snell conducted 
clearing and snagging operations and maintained dredging 
ranges and mooring facilities in New Topsail Inlet at 
a cost of $2,489. During intermittent periods the U. S. 
sidecasting dredge Merritt removed 36,981 cubic yards 
from shoals in New Topsail Inlet at a cost of $151,900. 
During intermittent periods the U. S. hopper dredge 
Currituck removed 22,689 cubic yards from shoals in 
New Topsail Inlet at a cost of $79,226. During intermittent 
periods the U. S. sidecasting dredge Fry removed 
77,883 cubic yards from shoals in New Topsail Inlet at a 
cost of $491,050. Between April 11 thru 25,1992, the contract 
dredge Stuart removed 75,519 cubic yards from 
shoals in Banks Channel at a cost of $177,830. Archeological 
investigations cost $1,266. Conditions and 
operation studies cost $23,342. 
Condition at end of fiscal year. The project was completed 
in November 1986 except for the training wall, 
three tie-up dolphins at Masonboro Inlet and the three remaining 
bridges. The construction contract for Core Creek 
Bridge was awarded September 27, 1991, with completion 
scheduled for June 1994. Design of Hobucken and Fairfield 
Bridges was continued. Total cost of existing project to 
September 30, 1992, was $165,589,642, of which 
$50,958,277 was for new work including $86,851 in contributed 
funds and $114,631,365 was for maintenance, including 
$667,300 in contributed funds. 
3. BEAUFORT HARBOR, N. C. 
Location. The project is just inside Beaufort Inlet, adjacent 
to Morehead City Harbor. (See Coast and Geodetic 
Survey Chart 420.) 
Previous projects. For details see Annual Reports for 
1915 and 1938. 
Existing project. The authorized project provides for 
stopping erosion at Beaufort Inlet by jetties and sand 
fences at Fort Macon and Shackleford points and other 
shore protection; channels 15 feet deep at mean low water 
and 100 feet wide in Bulkhead and Gallants Channels, except 
for a depth of 12 feet in the upper 5,000 feet of 
Gallants Channel; a harbor of refuge in Town Creek 12 feet 
deep, 400 feet wide, and 900 feet long connected to 
Gallants Channel by a channel 12 feet deep, 150 feet wide, 
and 1,400 feet long; a basin 12 feet deep, 600 feet wide in 
front of the town of Beaufort except for a channel 15 feet 
deep, 100 feet wide through the basin; a stone bulkhead 
from Town Marsh across Bird Shoal to the west end of 
Carrot Island; a channel 14 feet deep, 70 feet wide, and 
1,900 feet long from Bulkhead Channel to a turning basin 
14 feet deep, 150 feet wide and 300 feet long near the upper 
end of Morgan Creek; and a channel in Taylors Creek 
15 feet deep, 100 feet wide, extending about 2.6 miles 
easterly from about opposite Marsh Street in Beaufort to 
Lennoxville Point at North River, except for an 800-footlong 
section at the east end which is 12 feet deep. Total 
length of channels is 7.3 miles. Average tidal range is 2.5 
feet at Beaufort and 3.5 feet at the inlet. (See Table 6-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are fifty waterfront facilities 
with a total frontage of 2,000 feet. These facilities are adequate 
for present commerce. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $16,300. 
Condition at end of fiscal year. The project was completed 
in October 1965 except for the Morgan Creek 
modification which was completed November 12, 1983. 
(For further details see Annual Report for 1962.) Costs 
under existing project to September 30, 1992, were 
$827,040 for new work, including $34,000 contributed 
funds and $4,050,182 for maintenance, including $326,225 
contributed funds, a total of $4,877,222. 
4. CAPE FEAR RIVER, N. C. 
ABOVE WILMINGTON 
Location. The river is formed by confluence of the Deep 
and Haw Rivers at Moncure, Chatham County, N. C., and 
empties into the Atlantic Ocean at Cape Fear, near the 
southern extremity of the State. (See Coast and Geodetic 
Survey Chart 426.) 
Previous project. For details see Annual Reports for 
1915 and 1938. 
Existing projects. The authorized project provides for a 
channel 25 feet deep and 200 feet wide from Wilmington to 
a turning basin 400 feet wide and 550 feet long at Navassa 
(2.9 miles); a channel 12 feet deep and 140 feet wide from 
Navassa to mileboard 30 at Acme, with five channel 
cutoffs, 12 feet deep and 150 feet wide to eliminate sharp 
bends; a channel 8 feet deep from mileboard 30 to 
Fayetteville by constructing three locks and dams and by 
dredging river shoals; and recreational facilities at the 
locks and dams. Total length of the project channels is 
6-4

WILMINGTON, N. C., DISTRICT 
113.9 miles. The project was authorized by River and 
Harbor Acts of June 25, 1910; June 26, 1934; August 30, 
1935; August 26, 1937; October 27, 1965; and Section 4, 
Flood Control Act of 1944. For further details see Annual 
Reports for 1962 and 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. There are twelve waterfront 
facilities on the river, with a total frontage of 1,190 feet. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
snagged and cleared and maintained the buoy systems at 
the locks at a cost of $194,430. Periodic inspections of locks 
and dams cost $2,561. Slope failure repairs at Lock and 
Dams 1 and 2 cost $79,954. Repairs at lock gates of Lock and 
Dams 1 and 2 cost $89,638. Investigation of slope failure in 
new rip-rap at Lock and Dam 2 cost $4,118. Between 
October 25, 1991 and March 29, 1992, the contract dredge 
Long Bay removed 33,088 cubic yards from shoals in the 
Cape Fear River above Wilmington at a cost of $90,968. 
Environmental compliance assessments cost $5,408. 
Conditions and operation studies cost $124,270. Operation 
and Maintenance of three locks and dams cost $304,719. 
Condition at end of fiscal year. The project was 
completed in June 1970. Total costs of existing project to 
September 30, 1992, were $20,874,094 of which $3,610,454 
(including $1,226,385 public works) was for new work and 
$17,263,640 for maintenance. 
5. CHANNEL FROM BACK SOUND TO LOOKOUT 
BIGHT, N. C. 
Location. The project is located on the coast of North 
Carolina, 8 miles east of Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 7 feet deep from Back Sound, 
through Shackleford Banks to Lookout Bight. The project 
was authorized by River and Harbor Acts of August 26, 
1937, and March 2, 1945. For details see Annual Report for 
1959. 
Local cooperation. Fully complied with. 
Terminal facilities. Not required. 
Operations and results during fiscal year. Maintenance: 
Between December 17, 1991 and January 14, 1992, the contract 
dredge Richmond removed 54,900 cubic yards from 
shoals in the Channel at a cost of $123,910. Adjustment in 
prior year pipeline dredging costs resulted in a negative 
cost of $2,444. Conditions and operation studies cost 
$4,834. 
Condition at end of fiscal year. The project was completed 
in May 1965. 
6. DRUM INLET, N. C. 
Location. Drum Inlet is an opening through the barrier 
beach which separates Core Sound from the Atlantic 
Ocean. It is about 1,100 feet wide and is about 35 miles 
northeast of Beaufort and opposite the village of Atlantic. 
(See Coast and Geodetic Survey Charts 1233 and 419.) 
Existing project. The project provides for a channel 12 
feet deep at a mean low water and 200 feet wide from the 
gorge in the inlet to the Federally improved channel in Core 
Sound, about 1 mile. The mean range tide is 3.8 feet in the 
ocean and 0.3 foot in Core Sound at Atlantic. The project 
also provides for a channel 150 feet wide and 9 feet deep 
from the gorge in the inlet to deep water in the Atlantic 
Ocean. The Core Sound portion of the project was 
authorized by the River and Harbor Act of June 20, 1938. 
(H.D. 414, 75th Cong., 2nd sess.) The channel from the inlet 
to the Atlantic Ocean was authorized under Section 107 of 
the 1960 River and Harbor Act. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Maintenance: 
Condition and operation studies cost $683. 
Condition at end of fiscal year. The project was completed 
in February 1972. The feasibility of resuming 
maintenance is under investigation. 
7. FAR CREEK, N.C. 
Location. Flows easterly from Engelhard into Pamlico 
Sound, about 95 miles south of Norfolk, Va. (See Coast and 
Geodetic Survey Chart 1232.) 
Existing project. A channel 12 feet deep and 80 to 100 
feet wide from Pamlico Sound to highway bridge at 
Engelhard, with a turning basin 12 feet deep, 200 feet wide 
� and 900 feet long at the head. Project was authorized by 
River and Harbor Acts of July 3, 1930, and May 17, 1950. 
For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Project is served by 12 waterfront 
facilities with a total frontage of 2,300 feet, all privately 
owned. Existing facilities are adequate for present 
commerce. 
Operations and results during fiscal year. Maintenance: 
Cost in connection with prior year pipeline dredging was 
$5,650. 
Condition at end of fiscal year. Project completed June 
1957. 
8. LOCKWOODS FOLLY RIVER, N. C. 
Location. The project is located on the south coast of 
North Carolina about 12 miles west of Cape Fear River. 
(See Coast and Geodetic Survey Chart 1236 and Geological 
Survey Map of North Carolina.) 
Existing project. The authorized project provides for a 
channel 100 feet wide and 6 feet deep at low water from 
the ocean to the bridge at Supply 12.5 miles above, to be 
obtained by dredging through oyster rocks and mudflats. 
The completed river portion of the project above the 
waterway was reclassified to the active category in 1971. 
Lunar tidal ranges in Lockwoods Folly River are 4.5 feet 
at the inlet and 2 feet at the head of navigation at Supply. 
The existing project was authorized by the 1890 River and 
Harbor Act. (See Annual Report for 1887, page 1099.) A 
modification to enlarge the channel from 6 to 12 feet deep 
6-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
and from 100 to 150 feet wide across the ocean bar for a 
distance of 4,700 feet was approved by the Chief of 
Engineers on June 3, 1980, under Section 107 of the 1960 
River and Harbor Act. During dredging operations it 
became apparent that establishment of the 12-foot project 
would not be possible with currently available equipment. 
Therefore, the Chief of Engineers, on December 20, 1983, 
approved the District's recommendation that further construction 
activity for the Lockwoods Folly Inlet project be 
suspended until suitable equipment becomes available and 
that the project be maintained at an 8-foot project depth in 
the interim. 
Local cooperation. For the new modification local 
interests must: (a) pay, contribute in kind, or repay with 
interest, one-half of the first costs of construction allocated 
to recreational boating; (b) hold and save the United States 
free from damages resulting from changes in groundwater 
levels, saltwater intrusion, or wave action due to the 
construction works, except damages due to the fault or 
negligence of the United States or its contractor; (c) 
provide without cost to the United States all lands, 
easements, and rights-of-way necessary for the 
construction and subsequent maintenance of the project 
and for aids to navigation upon the request of the Chief of 
Engineers and, (d) provide depths in berthing areas 
commensurate with the project depths, and provide 
service facilities. 
Terminal facilities. Thirty-one piers and wharves on the 
Atlantic Intracoastal Waterway at Holden Beach, about 
1.25 miles west of Lockwoods Folly Inlet, with a total 
frontage of about 1,980 feet available. At Dixons Landing, 
about 2 miles upstream of the inlet, there are five wharves 
with a total frontage of 240 feet. Numerous natural 
landings are used for loading and unloading small boats. 
Berthing space in the vicinity of Lockwoods Folly Inlet 
totals about 2,220 feet. Facilities are considered adequate 
for present commerce. 
Operations and results during fiscal year. Maintenance: 
During intermittent periods the U. S. debris boat Snell 
conducted clearing and snagging operations and 
maintained dredging ranges and mooring facilities at a 
cost of $2,489. During intermittent periods the U. S. 
sidecasting dredge Fry removed 116,058 cubic yards from 
shoals in Lockwoods Folly River at a cost of $476,755. 
During intermittent periods the U. S. hopper dredge 
Currituck removed 55,665 cubic yards from shoals in 
Lockwoods Folly River at a cost of $132,000. Archeological 
investigations in Lockwoods Folly River cost $308. Design 
cost for future year pipeline dredging in Lockwoods Folly 
River was $7,163. Conditions and operation studies cost 
$44,739. 
Condition at end of fiscal year. The active portion of the 
project was completed in June 1965 except for the latest 
modification. Work was initiated on the latest modification 
on September 23, 1982, with a depth of 8 feet being 
reached in October 1982. The project will be maintained at 
the 8-foot depth until suitable equipment for deepening to 
12 feet becomes available. 
9. MANTEO (SHALLOWBAG) BAY, N. C. 
Location. The project is located on the northeastern side 
of Roanoke Island, North Carolina. (See Coast and 
Geodetic Survey Chart 1229.) 
Existing project. The authorized project provides for a 
channel 14 feet deep and 400 feet wide from the Atlantic 
Ocean through Oregon Inlet with connecting 12-foot channels, 
100 feet wide, to Pamlico Sound, Manteo, and Wanchese; 
and a channel 6 feet deep and 100 feet wide connecting 
the Manteo-Oregon Inlet Channel with Albemarle 
Sound. Length of channels is 25.4 miles. A newly authorized 
modification provides for stabilization of Oregon Inlet 
with a dual rubble-mound jetty system, including means 
for sand transfer to the downdrift beach; a channel, 20 feet 
deep and 400 feet wide, through the ocean bar at Oregon 
Inlet; a channel, 14 feet deep and 120 feet wide, from the 
gorge in Oregon Inlet to and through Roanoke Sound to 
and including a 15-acre basin of the same depth at Wanchese; 
and a channel 10 feet deep and 100 feet wide from 
the 12-foot-deep channel in Manteo (Shallowbag) Bay 
through Roanoke and Albemarle Sounds to deep water 
near the northern end of Croatan Sound. The 12-foot 
Croatan Sound channel has been deferred due to lack of 
economic justification. The estimated Federal cost for the 
modification is $77,700,000 (1992). The project was 
authorized by River and Harbor Acts of June 25, 1910; October 
17, 1940; May 17, 1950; and December 31, 1970; and 
under Section 107 of the 1960 River and Harbor Act. 
Local cooperation. For the new modification, local interests 
must: (a) provide all lands, easements, and rightsof-
way for construction and subsequent maintenance of the 
project, including suitable areas required for initial and 
subsequent disposal of spoil and also necessary retaining 
dikes, bulkheads, and embankments therefor, or the cost 
of such retaining works; (b) hold and save the United 
States free from damages due to the construction works 
and subsequent maintenance; (c) continue to provide and 
maintain adequate terminal and transfer facilities, open to 
all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (d) provide and maintain necessary 
mooring and berthing facilities in any enlarged basin, open 
to all on equal terms, in accordance with plans approved by 
the Chief of Engineers; (e) provide and maintain depths in 
berthing areas and local access channels serving the terminals 
commensurate with depths provided in the related 
project areas; (f) accomplish such alterations as required in 
sewer, water supply, drainage, electrical powerlines, 
telephone lines, or other utility facilities as well as their 
maintenance; (g) establish a competent and properly constituted 
public body empowered to regulate the use, 
growth, and free development of the harbor facilities, with 
the understanding that said facilities will be open to all on 
equal terms; (h) and establish regulations prohibiting the 
discharge of untreated sewage, garbage, and other 
pollutants in the water of the harbor by the users thereof, 
which regulations shall be in accordance with applicable 
laws or regulations of Federal, State, and local authorities 
responsible for pollution prevention and control; (i) pay 
one-half of the separable and joint costs allocated to 
recreational navigation presently estimated at $8,088,000, 
6-6

WILMINGTON, N. C., DISTRICT 
and bear all costs of operation, maintenance and replacement 
of recreational navigation facilities presently 
estimated at $1,125,000 annually; (j) pay 10 percent of the 
costs allocated to navigation during construction presently 
estimated at $7,712,000; (k) pay an additional 10 percent of 
the costs allocated to navigation within a period of 30 
years following completion of construction offset by a 
credit allowed for the value of lands, easements, rights-ofway, 
relocations (except utility relocations), and dredged 
material disposal areas presently estimated at $6,800,000. 
Reasonable assurances have been received. The State of 
N. C. has constructed the Wanchese Harbor portion and 
was reimbursed under Sec. 215, PL 90-483. 
Terminal facilities. The project is served by 33 waterfront 
facilities with a total frontage of 3,320 feet. Additional 
wharves and facilities will be provided with the 
enlarged basin at Wanchese. 
Operations and results during fiscal year. Maintenance: 
Engineering and design for the modification continued at a 
cost of $140,724. Monitoring of the terminal groin built by 
the State of North Carolina cost $12,156. Additional 
engineering and design work is being accomplished under 
preconstruction engineering and design. Maintenance: During 
intermittent periods the U. S. debris boat Snell maintained 
dredging ranges and mooring dolphins at a cost of 
$12,989. During intermittent periods the U. S. sidecasting 
dredge Schweizer removed 602,896 cubic yards from shoals 
in Oregon Inlet at a cost of $1,447,036. During intermittent 
periods the U. S. sidecasting dredge Merritt removed 
66,899 cubic yards from shoals in Oregon Inlet at a cost of 
$184,445. During intermittent periods the U. S. hopper 
dredge Currituck removed 88,802 cubic yards from shoals in 
Oregon Inlet at a cost of $344,552. Between October 1 and 
November 5, 1991, the contract dredge Adco removed 
94,331 cubic yards from shoals in the ocean bar at a cost of 
$709,522. Between July 25 and September 5, 1992, the contract 
dredge Georgia removed 900,592 cubic yards from 
shoals in the vicinity of Oregon Inlet at a cost of $3,042,914. 
Cost in connection with prior year pipeline dredging in Old 
House Channel and Channel to Wanchese was $24,954. Cost 
in connection with prior year maintenance dredging in the 
ocean bar was $119,238. Design cost for future year pipeline 
dredging in Old House Channel and Channel to Wanchese 
was $5,141. Expansion of dispoal island cost $5,076. Environmental 
coordination for realignment of intersection 
from Old House Channel to the inlet cost $6,857. Project 
monitoring cost $21,284. Conditions and operation studies 
cost $176,391. 
Condition at end of fiscal year. The project is complete 
except for the latest modification. (For further details, see 
Annual Report of 1962.) 
10. MOREHEAD CITY HARBOR, N. C. 
Location. The project is located on the northern shore of 
Bogue Sound, adjacent to Beaufort Inlet. (See Coast and 
Geodetic Survey Chart 420.) 
Previous project. For details see page 470 of Annual 
Report for 1935. 
Existing project. The authorized project provides for 
deepening of the channel, from the 42-foot-depth contour in 
the Atlantic Ocean through the ocean bar to the gorge in 
Beaufort Inlet, to 42 feet over a bottom width of 450 feet, 
thence to a depth of 40 feet in the east leg of the turning 
basin including the 1,200-foot diameter turning area, with 
widths of 600 feet in the cutoff channel, and 400 feet wide 
to the turning basin and connecting shallow-draft channels. 
Project deepening was completed on August 2, 1978. Jetties 
at Beaufort Inlet were reclassified to the "active" 
category on March 8, 1972. The jetties were deauthorized 
by the Water Resources Development Act of 1986. In 
general the project as it now exists was authorized by the 
1958 River and Harbor Act (S.D. 54, 84th Cong., 1st sess.) 
and the River and Harbor Act of December 31, 1970. For 
further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Twenty-six waterfront facilities 
serve the port, with a total frontage of 1,250 feet. Marine 
terminals provide 5,300 feet of berthing space, with a 
depth alongside of 35 feet, and facilities for transfer of 
cargoes between rail and water carriers. Improvements to 
facilities were completed in 1969. For further details see 
Port Series No. 12, revised 1987, Corps of Engineers. 
Operations and results during fiscal year. Maintenance: 
Between December 1, 1991, and February 20, 1992, the 
contract dredge Eagle 1 removed 831,637 cubic yards from 
shoals in the ocean bar at a cost of $1,653,281. Cost in connection 
with prior year pipeline dredging of the inner 
harbor was $172,154 and contributed funds cost was 
$18,355. Design cost for future year pipeline dredging cost 
$56. Monitoring at Morehead City Harbor cost $17,852. 
Ocean dumping monitoring in conjunction with EPA cost 
$6,637. Conditions and operation studies cost $121,020. 
Condtion at end of fiscal year. The existing project is 
complete. (For further details, see Annual Report of 1962.) 
Total cost of the existing project to September 30, 1992, 
was $56,768,970 of which $6,501,569 was for new work (including 
$553,477 public works funds) and $50,267,401 for 
maintenance, including $1,373,330 contributed funds. 
11. PAMLICO AND TAR RIVERS, N. C. 
Location. The two names apply to the same river, 
known as the Tar above and as the Pamlico below 
Washington, N. C. This stream rises in Person County, 
flows southeasterly 180 miles to Washington, thence 38 
miles to Pamlico Sound. (See Coast and Geodetic Survey 
Chart 537.) 
Previous project. For details see page 502 of Annual 
Report for 1938. 
Existing project. A channel 12 feet deep at mean low 
water and 200 feet wide from 12-foot contour in the river 
below Washington to Atlantic Coastline Railroad bridge at 
Washington; thence 12 feet deep and 100 feet wide to a turning 
basin of same depth, 200 feet wide, 300 feet long, in 
Hardee Creek, 1,500 feet above its mouth; thence 6 feet 
deep, 75 feet wide to Greenville; thence 20 inches deep, 60 
feet wide to Tarboro; and thence to clear the natural chan- 
6-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
nel to Little Falls. Project was authorized by River and 
Harbor Acts of August 14, 1876; March 3,1879; August 11, 
1888; March 2,1907; July 25,1912; July 3,1930; and August 
26, 1937. For further details see Annual Report for 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 54 wharves on the portion 
of this river under improvement, of which 34 are along the 
waterfront at Washington, 19 between Washington and 
the mouth, and only 1 in usable condition above Washington. 
They have a frontage of 3,570 feet. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Between October 1 thru 3 and October 7 and 8, 1991, the 
U. S. debris boat Snell snagged and cleared at a cost of 
$24,500. 
Condition at end of fiscal year. Project is complete. (For 
details see Annual Report for 1962.) 
12. ROLLINSON CHANNEL, N. C. 
Location. The project is located about 3.5 miles northeast 
of Hatteras Inlet. (See Coast and Geodetic Survey 
Chart 1232.) 
Existing project. The authorized project provides for a 
channel 12 feet deep, 100 feet wide, and about 5.1 miles 
long from deep water in Pamlico Sound to and including a 
basin of the same depth, 80 to 150 feet wide, and 1,450 feet 
long at Hatteras; a rubble-mound breakwater on each side 
of the channel at the entrance to the basin; and a channel 
10 feet deep and 100 feet wide from that depth in Hatteras 
Inlet gorge to Rollinson Channel, in the vicinity of the 
basin at Hatteras. The project was authorized by the 
River and Harbor Acts of August 30, 1935; March 2,1945; 
September 3, 1954; and October 23, 1962. (For further 
details see Annual Report for 1961.) 
Local cooperation. Complied with to date. 
Terminal facilities. Six waterfront facilities serve the 
channel, with a total frontage of 926 feet. Existing facilities 
are adequate for present commerce. 
Operations and results during fiscal year. Maintenance: 
Between February 18 and 26, 1992, the contract dredge 
Richmond removed 19,147 cubic yards from shoals in the 
channel at a cost of $184,640. 
Condition at end of fiscal year. The project was completed 
August 22, 1966. (For further details see Annual 
Report for 1961.) 
13. SHALLOTTE RIVER, N. C. 
Location. A small stream in Brunswick County, N. C., 
rising in the large swamp country between Cape Fear and 
Waccamaw Rivers, known as Green Swamp. Stream is 
about 30 miles long and flows southerly into Atlantic 
Ocean and 20 miles west of mouth of Cape Fear River. (See 
Coast and Geodetic Survey Chart 835.) 
Previous project. For details see page 1806 of Annual 
Report for 1915. 
Existing project. A channel 4 feet deep at mean low 
water and 36 feet wide from the mouth to town of 
Shallotte. Section under improvement is 9 miles long. 
River is tidal, range varying from 5 feet at mouth to 3 feet 
at Shallotte. Hurricane Hazel in 1954 caused a tide about 
16 feet above mean sea level in the river at Shallotte Point. 
Project authorized by River and Harbor Acts of March 4, 
1913, and January 21, 1927. 
Local cooperation. None required. 
Terminal facilities. A marine railway and shop at 
Shallotte Point and another in town of Shallotte with 
facilities for building and repairing boats up to about 60 
feet long. On Shallotte River, there are 17 docks varying 
from 16 to 321 feet of frontage, providing 1,334 feet of 
wharf and docking space. 
Operations and results during fiscal year. Maintenance: 
Design cost for future years pipeline dredging of Shallotte 
River was $9,800. 
Condition at end of fiscal year. Project completed in 
1929. 
14. SILVER LAKE HARBOR, N. C. 
Location. The project is located at the southwest end of 
Ocracoke Island, a portion of the Outer Banks on the 
southeast coast of North Carolina, separating Pamlico 
Sound from the Atlantic Ocean. (See Coast and Geodetic 
Survey Chart No. 1232.) 
Existing project. The authorized project provides for 
basin depths of 12 feet in Silver Lake Harbor; an entrance 
channel 12 feet deep and 60 feet wide, from the basin to 
Teaches Hole Channel; a channel, 12 feet deep and 150 feet 
wide, from the entrance channel through Big Foot Slough 
Bar to the 12-foot contour in Pamlico Sound; a channel, 12 
feet deep and 150 feet wide, from the entrance channel 
through Teaches Hole Channel to the gorge in Ocracoke 
Inlet; a channel, 12 feet deep and 150 feet wide, across 
Bluff Shoal; and for rubble-mound training walls on the 
north and south sides of the entrance channel, 300 feet and 
400 feet long, respectively. Mean tidal ranges are 1.9 feet 
in the throat of Ocracoke Inlet and 1 foot at Ocracoke. 
Variations in the water surface of Pamlico Sound are 
generally due to winds and seldom exceed 1 or 2 feet above 
or below mean stage. Severe storms have raised the water 
surface as much as 7 feet above normal water level at 
Ocracoke. (See Table 6-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Twelve waterfront facilities serve 
the harbor. These facilities are adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Between March 8 and April 28, 1992, the contract dredge 
Hampton Roads removed 215,204 cubic yards from shoals 
in Bigfoot Slough at a cost of $653,748. Conditions and 
operation studies cost $27,252. 
Condition at end of fiscal year. The project was completed 
July 28, 1970. (For further details see Annual 
Report for 1961.) 
6-8

WILMINGTON, N. C., DISTRICT 
15. STUMPY POINT BAY, N. C. 
Location. On southeastern side of the mainland, Dare 
County, N. C. (See Coast and Geodetic Survey Chart 1229.) 
Existing project. A channel 75 feet wide and 10 feet 
deep from that depth in Pamlico Sound to a basin in the 
harbor at Lake Worth, 75 to 100 feet wide, 550 feet long 
and 10 feet deep, plus an irregularly shaped area providing 
access to the public wharf, together with protective 
breakwaters at entrance to the harbor. Project was 
authorized by 1948 River and Harbor Act and under Section 
107, 1960 River and Harbor Act. 
Local cooperation. Fully complied with. 
Terminal facilities. Bulkheads in existing basin provide 
about 550 linear feet of berthing space, and a wholesale 
fishhouse provides about 250 feet. Part of the space along 
the bulkheads is publicly owned. Facilities are considered 
adequate for existing commerce, but any appreciable increase 
will require additional facilities. 
Operations and results during fiscal year. Maintenance: 
Between January 26 and February 29, 1992, the contract 
dredge Richmond removed 159,187 cubic yards from 
shoals at a federal cost of $392,900 and $135,000 contributed 
funds. Work in connection with condition and 
operation studies cost $797. 
Condition at end of fiscal year. Project completed on 
September 20, 1967. (For further details, see Annual 
Report for 1966.) 
16. WATERWAY CONNECTING PAMLICO SOUND 
AND BEAUFORT HARBOR, N. C. 
Location. The project is located in Core Sound, west of 
the outer banks of eastern North Carolina. (See Coast and 
Geodetic Survey Charts Nos. 420 and 1233.) 
Existing project. The authorized project provides for a 
through channel to Core Sound 7 feet deep and 75 feet 
wide from Pamlico Sound to Beaufort Harbor; an alternative 
route of the same dimensions through Back Sound 
by way of channels at the east and west ends of Harkers 
Island; a channel 7 feet deep and 70 feet wide from the 
through channel to the local harbor at Cedar Island, including 
the authorized passage and future maintenance of 
a channel through the existing private basin, and an access 
channel 6 feet deep, 50 feet wide and about 400 feet long to 
a basin the same depth, 60 feet by 100 feet; a channel 7 feet 
deep and 75 feet wide from the through channel to Atlantic; 
a channel 7 feet deep and 75 feet wide, with a basin 200 
feet by 500 feet, the same depth, at Sealevel; a channel 5 
feet deep and 75 feet wide, with basin 150 feet by 130 feet, 
the same depth, at Davis; a channel 6 feet deep and 60 feet 
wide with a basin 100 feet by 600 feet, the same depth, at 
Marshallberg; an entrance channel 6 feet deep and 60 feet 
wide, from Back Sound to harbor of refuge 120 feet by 250 
feet, the same depth in Brooks Creek at the west end of 
Harkers Island; and a channel 7 feet deep and 70 feet wide, 
from the existing side channel at Atlantic, N.C., to the 
mouth of Little Port Brook; thence 7 feet deep and 50 feet 
wide, along the Brook to a basin 600 feet long, 180 feet 
wide, and 7 feet deep, with a breakwater, beginning at a 
point between the mouth of Little Port Brook and White 
Point, running along the channel approximately 2,000 feet. 
Plane of reference is mean low water. The length of the 
authorized channels is about 50.6 miles. (See Table 6-B for 
authorizing legislation.) 
Local cooperation. Fully complied with to date for completed 
portion. 
Terminal facilities. Sixteen small wharves serve the 
waterway. Additional facilities are needed along Core 
Sound. 
Operations and results during fiscal year. Maintenance: 
Between November 16, 1991 and January 14, 1992, the contract 
dredge Richmond removed 128,150 cubic yards from 
shoals at a cost of $486,500. 
Condition at end of fiscal year. The project was completed 
in September 1972. (For further details, see Annual 
Report for 1961.) 
17. WILMINGTON HARBOR, N. C. 
Location. The project is located on the Cape Fear River, 
on southeast coast of North Carolina, between the Atlantic 
Ocean and Wilmington, North Carolina. (See Coast and 
Geodetic Survey Chart No. 426.) 
Previous projects. For details, see page 1804 of Annual 
Report for 1915 and page 533 of Annual Report for 1938. 
Existing project. The authorized project provides for a 
channel 40 feet deep and 500 feet wide from the Atlantic 
Ocean through the ocean bar and entrance channels to 
Southport, thence 38 feet deep and 400 feet wide to the 
upper end of the anchorage basin (foot of Castle Street) at 
Wilmington, thence 32 feet deep and 400 feet wide, to 
Hilton Bridge over Northeast Cape Fear River; a 38-footdeep 
anchorage basin at Wilmington; a 32-foot-deep 
turning basin opposite the principal terminals; a channel 
12 feet deep and 100 feet wide, about 3 miles long, in Cape 
Fear River; and a channel 25 feet deep and 200 feet wide 
from Hilton Bridge over Northeast Cape Fear River to a 
point 1.66 miles above, including a turning basin of the 
same depth, 700 feet wide and 500 feet long, at a point 1.25 
miles above the bridge. The project was authorized by 
River and Harbor Acts of July 3, 1930; March 2, 1945; May 
17, 1950; October 23, 1962; and March 10, 1964; under 
Section 107 of the 1960 River and Harbor Act. A modification 
to widen the existing anchorage basin by 100 feet 
was authorized on July 13, 1982, under Sec. 5 of the Cong. 
Appro. Act of March 4, 1915. A modification to widen the 
38-foot by 400-foot Fourth East Jetty Channel to 500 feet; 
deepen the 32-foot by 400-foot channel between Castle 
Street and the N. C. 133 bridge to 35 feet; widen the 
32-foot by 1000-foot by 800-foot turning basin just above 
the mouth of the Northeast Cape Fear River by 50 feet on 
the west side and deepen to 35 feet; and environmental 
improvements to include acquiring, by easements or fee 
title, about 2,800 acres of wetlands, river bluffs and 
ecotones and provision for a minimum number of specially 
designed corridors across the wetlands for industrial 
access to the river was authorized by the Water Resources 
6-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Development Act of November 17, 1986 (PL 99-662). The 
estimated Federal cost is $14,300,000. (For further details 
of authorization, see 1962 Annual Report.) 
Local cooperation. Fully complied with to date except 
for latest modification. In accordance with the cost-sharing 
and financing concepts reflected in the Water Resources 
Development Act of 1986, the non-Federal sponsor must (1) 
provide all lands, easements, rights-of-way, and dredged 
material disposal areas including necessary retaining 
dikes presently estimated at $1,046,000, and bear all 
operation and maintenance costs for dikes presently 
estimated at $5,000 annually; (2) modify or relocate 
buildings, utilities, roads, bridges (except railroad bridges), 
and other facilities, where necessary in the construction of 
the project, presently estimated at $14,436,000; (3) pay 25 
percent of the costs allocated to deep draft navigation 
during construction presently estimated at $3,353,000 and 
reimburse an additional 10 percent of the costs allocated to 
deep draft navigation within a period of 30 years following 
completion of construction (which is entirely offset by a 
credit allowed for the value of lands, easements, rights-ofway, 
relocations (except utility relocations), and dredged 
material disposal areas; and (4) pay 25 percent of the first 
costs allocated to fish and wildlife enhancement presently 
estimated at $1,425,000, and pay 25 percent of the costs of 
operation, maintenance, and replacement of fish and 
wildlife facilities presently estimated at $15,000 annually. 
Terminal facilities. Forty-three principal wharves, piers, 
and docks at port of Wilmington, with a berthing space of 
about 20,000 linear feet serve the harbor. These facilities 
handle general cargo and petroleum products. (For further 
details, see Port Series No. 12, revised 1987, Corps of. 
Engineers.) 
Operations and results during fiscal year. Maintenance: 
Between November 23, and December 19, 1991, the contract 
dredge Illinois deposited 442,325 cubic yards of sand 
on Bald Head Island under Section 933 at a contributed 
funds cost of $246,261. Between November 23, 1991, and 
February 14,1992, contract dredges Padre Island, Manhatten 
Island and Northerly Island moved 1,051,323 cubic 
yards from shoals in the ocean bar at a cost of $2,711,961. 
Between February 1 and April 5, 1992, the contract 
dredges Enterprise and Hampton Roads removed 
1,027,326 cubic yards from shoals in the anchorage basin at 
a federal cost of $1,920,459 and 88,311 cubic yards from 
shoals at the State Ports at a contributed funds cost of 
$226,076. Between March 12 and April 6,1992, the contract 
dredge Carolina removed rock from the ocean bar at a 
federal cost of $2,586,658 and a State Ports contributed 
funds cost of $252,343. Cost in connection with prior year 
pipeline dredging of the anchorage basin was $11,010 
federal and $6,224 State Ports contributed funds. Design 
for repairs to dikes at Eagle Island was performed at a 
contributed funds cost of $45,238. During intermittent 
periods the U. S. debris boat Snell conducted clearing and 
snagging operations and maintained dredging ranges and 
mooring facilities at a cost of $308,957. Design cost for 
future year pipeline dredging in the anchorage basin was 
$7,271. Design cost for future year ocean bar dredging was 
$3,194. National Ocean Survey Tidal Datum Determination 
cost $1,255. Environmental analysis of proposed dredged 
material disposal sites cost $13,554. Ocean dumping 
monitoring cost $77,804. Rock investigations at Cape Fear 
River entrance cost $9,200. Hilton Wreck damage assessment 
site documentation cost $105,043. Section 933 dredge 
material study for Bald Head Island cost $745. Ocean Bar 
Reevaluation Report and rock dredging study cost $16,519. 
Endangered species study cost $69,399. Conditions and 
operation studies cost $407,042. Environmental Review 
Gide for Operations (ERGO) investigations cost $6,907. 
Condition at end of fiscal year. The active portion of the 
project was completed October 1982 except for latest 
modification. (For further details, see Annual Report for 
1962.) Total cost of the existing project to September 30, 
1992, was $98,911,889 or which $14,089,612 was for new 
work and $78,924,351 was for maintenance, including 
$5,897,926 contributed funds. The remaining uncompleted 
portion of the work authorized under the River and Harbor 
Act of March 2, 1945, was deauthorized in accordance 
with Section 1001(b) (1), PL 99-662. 
Flood Control 
18. CAPE FEAR RIVER BASIN, N. C. 
Location. Work covered by this project consists of a 
series of dams and reservoirs on tributaries of the Cape 
Fear River in North Carolina within a radius of 100 miles 
from Raleigh, North Carolina. (See Geological Survey Map 
of North Carolina.) 
Existing project. Public Law 88-253, approved 
December 30, 1963, authorized three principal dams and 
reservoirs and a series of smaller reservoirs on tributaries 
of the Cape Fear River in accordance with the comprehensive 
plans in House Document 508, 87th Congress, 2d 
session. The act also provides that the appropriate 
agencies of the Departments of the Army and Agriculture 
shall conduct joint investigations and surveys and prepare 
a report on the upper tributaries of the Cape Fear River in 
the interest of watershed protection and flood prevention, 
and the conservation, development, utilization, and 
disposal of water. The report was prepared in compliance 
with provisions of Public Law 87-639. The study was 
unfavorable and has been submitted to Congress. No 
further action will be taken. A list of the dams and 
reservoirs included in the comprehensive plan follows. 
(See Table 6-J on Dams and Reservoirs.) Estimates of cost 
as given are based on 1960 price levels, except the ones for 
B. Everett Jordan Dam and Lake and Randleman Lake, 
which were revised in 1990, and Howards Mill Lake in 
1980. These three projects have been authorized for 
construction in accordance with the above authorization. 
Howards Mill Lake was reclassified to the "deferred" 
category in October 1980 due to the current lack of 
economic justification. 
Local cooperation. Requirements are given in the 
individual project reports. 
6-10

WILMINGTON, N. C., DISTRICT 
18A. B. EVERETT JORDAN DAM AND LAKE, N. C. 
Location. The project is located on the Haw River, N. C., 
4.3 miles above its mouth, and 2.5 miles north of Moncure, 
N.C. 
Existing project. The project provides for an earth dam 
1,330 feet long with a maximum height of 112 feet above 
the streambed, an uncontrolled, unpaved chute spillway, 
and a controlled 19-foot diameter outlet structure. Some 
saddle dikes are required beyond the spillway. The 
reservoir has a gross storage capacity of 753,500 acre-feet, 
of which 538,400 acre-feet is for flood control and a 
conservation pool of 215,100 acre-feet for water-quality 
control, water supply, and sedimentation. The reservoir 
will be operated as a unit of a coordinated system for 
control of floods in the Cape Fear River Basin and for 
water supply, water-quality control, and other purposes. 
Estimated cost for new work is $146,200,000 (1992), 
consisting of $87,795,000 for construction, and $58,405,000 
for lands and damages, including highway, railroad, and 
utility relocations. The existing project was authorized by 
Public Law 88-253 approved December 30, 1963 (H.D. 508, 
87th Cong., 2d sess.). 
Local cooperation. Local interests must protect 
downstream channels from encroachments and obstructions 
which would adversely affect operation of the 
project; reimburse the Federal Government for all costs 
allocated to municipal and industrial water supply, 
presently estimated at $3,700,000 and bear all annual costs 
for operation, maintenance, and major replacements 
allocated to municipal and industrial water supply, an 
amount presently estimated at $46,000 annually; and 
contribute toward the cost of the ranger security 
buildings, an amount presently estimated at $43,000. A 
contract between the State of N. C. and the United States 
for water supply storage space was executed by ASA (CW) 
on April 10, 1988. In addition, the State of N. C. has leased 
the project for public park, recreational, fish, wildlife, and 
other natural resource management purposes and the 
estimated cost to the State for O&M under this lease is 
$806,000 annually. 
Operations and results during fiscal year. New work: 
New Hope Overlook recreation area was continued at a 
cost of $1,034,412. Robeson Creek recreation area was 
continued at a cost of $293,326. Total Federal expenditures 
were $1,902,208, including above items. Adjustments in 
costs of maintenance center ranger security building 
resulted in a contributed funds cost of $5,567. Status of 
plans and specs: Rivers End, 98 percent and Wilderness 
Island O&M roads, 95 percent. Maintenance: Periodic inspection 
cost $1,255. Sedimentation resurveys cost $12,134. 
expenditures were $4,490,985, including the above items. 
$14,711. Replacement of management center septic system 
cost $14,804. Environmental Review Guide for Operations 
(ERGO) investigations cost $16,307. Automatic gate 
control system and piezometer reading equipment cost 
$3,498. Normal operation and maintenance cost $924,317. 
Maintenance and operation of dams cost $79,000. 
Condition at end of fiscal year. All facilities are basically 
complete expect for recreation facilities and project 
operations facilities. Impoundment was completed in 
February 1982 with dedication on May 1, 1982. Project 
completion is scheduled for June 1993. 
18B. RANDLEMAN LAKE, N. C. 
Location. The project is located on Deep River, N. C., 
about 15 miles south of Greensboro and about 2 miles 
upstream from the town of Randleman. The damsite and 
about two-thirds of the reservoir would lie in Randolph 
County. The upper one-third of the reservoir would lie in 
Guilford County. 
Existing project. The authorized project provides for 
construction of an earth dam 2,300 feet long with a maximum 
height of 110 feet above the streambed to create a 
reservoir with gross storage of 108,000 acre-feet, consisting 
of 46,000 acre-feet for flood control and a conservation 
pool of 62,000 acre-feet for water supply, water-quality 
control and sedimentation. Randleman Lake is the second 
project of the comprehensive plan of development for the 
Cape Fear River Basin, providing reservoir storage for 
flood control, water supply, and recreation. Estimated cost 
of new work is $124,000,000 (1992), consisting of 
$62,300,000 for construction and $61,700,000 for lands and 
damages, including relocations. The existing project was 
authorized by the 1968 Flood Control Act (H.D. 343, 90th 
Cong., 2d sess.). 
Local cooperation. Based on the termination of Federal 
interest in the project by the ASA(CW), no local cooperation 
is required. 
Operations and results during fiscal year. New work: 
Project coordination cost $217. 
Condition at end of fiscal year. Preconstruction planning 
was completed in FY 1982. The Piedmont Triad Regional 
Water Authority is building a water supply and possible 
recreation facility at Randleman. All pertinent data that 
may be useful in the construction has been provided. The 
project was reclassified to the deferred category in April 
1992 due to the current lack of economic justification. 
19. CAROLINA BEACH AND VICINITY, N. C. 
Location. The project is in New Hanover County, about 
15 miles southeast of Wilmington, N. C., on the peninsula 
which separates lower Cape Fear River from the Atlantic 
Ocean. (See Coast and Geodetic Survey Map 834.) 
Existing project. The authorized project provides for 
construction of a dune with a base generally bordering at 
or near the building line, with a crown width of 25 feet at 
an elevation of 15 feet above mean low water, together 
with integral construction of a beach berm with a crown 
width of 50 feet at elevation 12, extending about 31,800 
feet from the northern limits of Carolina Beach to the 
southern limits of Kure Beach; initial deposition of sufficient 
material north of Carolina Beach to serve as a feeder 
beach; and Federal participation in the cost of beach 
nourishment for a period not to exceed 10 years from the 
year of completion of initial placement. Along the northern 
6-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
2,050 feet, the project includes a rock revetment at elevation 
12 fronted by a 130-foot-wide berm at elevation 8. The 
area south of Carolina Beach was reclassified to the actin 
category, June 1985. Approved estimated Federal cost for 
new work is $139,349,000 (1992). The project was authorized 
by the 1962 Flood Control Act (H.D. 418, 87th Cong. 2d 
sess.). The Water Resources Development Act of 1986 
authorized Federal participation in future nourishment for 
50 years. This cost for the Carolina Beach portion is not included. 
However, these costs will be included upon completion 
of the reevaulation report. 
Local cooperation. For the Carolina Beach portion, local 
interests must: (a) Provide lands, easements, and rights-ofway 
for construction; (b) make required relocations and 
alterations of streets, utilities, or structures; (c) contribute 
37.9 percent of the total first cost, with credit allowed for 
(a) and (b); (d) hold the United States free from damages; (e) 
maintain all works after completion; (f) maintain continued 
public ownership of the shore; (g) adopt and enforce appropriate 
ordinances to provide for preservation of improvement 
and its protective vegetation; (h) control water pollution 
to extent necessary to safeguard health of bathers; 
and (i) at least annually inform interests affected that project 
will not provide any substantial protection from ocean 
surges higher in elevation than that of Hurricane Hazel, 
October 15, 1954. Requirements have been fulfilled to date 
for the town of Carolina Beach portion of the project only. 
For the Area South portion, local interests must: (a) provide 
lands, easements, rights-of-way, including borrow 
areas; (b) pay 35 percent of the first costs of operation, 
maintenance and replacement of hurricane and storm 
damage reduction facilities; (c) contribute, in cash, 35 percent 
of the total project cost; (d) inform affected interests 
of the limitation of the protection afforded by the project 
no less than once each year; (e) assure that water pollution 
which would endanger the health of bathers will not be 
permitted to the extent of its power; (f) assure the continued 
public ownership of the above shore and its administration 
for public use during the 50 year economic life 
of the project; (g) to the extent of its powers, prescribe and 
enforce regulations to prevent obstruction of or encroachment 
on the project that would reduce the level of protection 
it affords or that would hinder operation or 
maintenance; and (h) provide and maintain necessary access 
roads, parking areas and other public use facilities 
open and available to all on equal terms. 
Operations and results during fiscal year. New work: 
An economic reanalysis of the area south of Carolina Beach 
was continued at a cost of $427,154. An economic 
reanalysis of the Carolina Beach portion was initiated at a 
cost of $167,164. Final cost and adjustments in cost sharing 
for project renourishment in FY 1991 resulted in a 
decrease in Federal cost of $40,716 and an increase in contributed 
funds cost of $42,947. 
Condition at end of fiscal year. Project construction was 
completed August 12, 1982, except for grassing which was 
completed in September 1983. The second increment of 
renourishment was completed in May 1988. The third increment 
of renourishment was completed in July 1991. 
20. NEUSE RIVER BASIN, N. C. 
Location. Works covered by this project consist of a 
series of dams and reservoirs in the Neuse River Basin in 
North Carolina within a radius of 50 miles from Raleigh, 
North Carolina. (See Geological Survey Map of North 
Carolina.) 
Existing project. The Flood Control Act of 1965 
authorized construction of the Falls project as the key 
project in the recommended general plan of development 
of the Neuse River Basin. The plan will serve as a guide for 
immediate and future development of the basin's water 
resources as set forth in House Document 175, 89th Congress, 
1st Session. A list of projects included in the general 
plan of development follows. (See Table 6-J on Dams and 
Reservoirs.) Estimated costs as given are based on 1963 
price levels, except for Falls Lake which was revised in 
1989. 
20A. FALLS LAKE, N. C. 
Location. The project is on the Neuse River about 10 
miles north of the city of Raleigh, North Carolina. 
Existing project. The authorized project provides for an 
earth dam 1,915 feet long with a maximum height of 95 
feet above streambed. The dam has a 30-foot top width. An 
uncontrolled chute spillway, 100 feet wide, is located in the 
east abutment. The reservoir has a gross storage capacity 
of 374,450 acre-feet, of which 243,050 acre-feet is for flood 
control, 45,000 acre-feet for water supply for the city of 
Raleigh, 61,330 acre-feet for water quality control, and 
25,070 acre-feet for sediment storage. The reservoir will be 
operated as the initial unit of a coordinated system for control 
of floods in the Neuse River Basin for water supply, 
water quality control, recreation, and other purposes. 
Estimated cost of new work is $183,000,000 (1992) consisting 
of $88,564,000 for construction and $94,436,000 for 
lands and damages, including highway, railroad, and utility 
relocations. The project was authorized by the 1965 Flood 
Control Act (H.D. 175, 89th Cong., 1st sess.) 
Local cooperation. Local interests must prevent encroachment 
on downstream channels that would interfere 
with the operation of the reservoir; pay the United States 
in accordance with the Water Supply Act of 1958, as 
amended, the entire amount of construction cost allocated 
to water supply, presently estimated at $13,900,000 and 
entire amount of operation, maintenance, and replacement 
costs allocated to water supply, presently estimated at 
$105,000 annually, the final amounts to be determined 
after actual costs are known; administer project land and 
water areas for recreation and fish and wildlife enhancement; 
pay, contribute in kind, or repay (which may be 
through user fees), with interest, one-half of the separable 
cost of the project allocated to recreation and one-fourth of 
the separable cost allocated to fish and wildlife enhancement, 
the amount involved currently being estimated at 
$20,600,000, and bear all costs of operation, maintenance, 
and replacement of recreation and fish and wildlife lands 
and facilities, the amount involved currently being 
estimated at $1,445,000 on an average annual basis. Formal 
assurances have been received. The N. C. Department 
6-12

WILMINGTON, N. C., DISTRICT 
of Natural and Economic Resources has been authorized 
by an act of legislation to assure payment of all non- 
Federal costs allocable to water supply in all Federal projects 
as required by law. The State will require repayment 
of water supply costs, by the users. A contract between 
the city of Raleigh and the United States for water-supply 
storage space was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement for cost 
sharing of recreational lands and facilities in accordance 
with P.L. 89-72 was approved by the Secretary of the Army 
on September 11, 1972. A contract agreement in accordance 
with Section 221 of P.L. 91-611 was executed on October 
10, 1972. 
Operations and results during fiscal year. New work: 
Wildlife subimpoundments were completed at a cost of 
$83,751. Holly Point recreation area was initiated at a cost 
of $618,150. Beaverdam recreation area was continued at a 
cost of $1,302,781. B. W. Wells and Shinleaf recreation 
areas were continued at a cost of $1,446,182. Total Federal 
expenditures were $4,490,985, including the above items. 
Status of plans and specs: Dam Fix, 90 percent; and 
Modifications to Miscellaneous Recreation Areas, 90 percent. 
Maintenance: Periodic inspection cost $15,850. 
Seismologic evaluation report cost $14,182. Intake tower 
gate maintenance cost $32,507. Flood gate indication and 
control system cost $55,673. Normal operation and 
maintenance cost $879,995. Maintenance and operations of 
dams cost $79,000. 
Condition at end of fiscal year. Reservoir filling was 
completed on December 7, 1983. Dedication ceremonies 
were held on April 30, 1983. All facilities are basically complete 
except for fish and wildlife facilities, recreation 
facilities, 0 & M facilities and project modifications due to 
the water storage shortage. Project completion is scheduled 
for July 1994. 
21. HAMLET CITY LAKE, HAMLET, N. C. 
Location. The project is located on Marks Creek within 
the city limits of Hamlet, N. C. (See USGS quadrangle 
sheet, Hamlet, N. C.) 
Existing project. A small earth dam constructed in the 
1930's under the WPA Program impounds the shallow 
50-acre lake. Much of the City's storm runoff empties into 
the lake and has contributed significantly to a sediment 
problem. Local interests desire removal of accumulated 
sediment and debris including construction of sediment 
traps and providing other devices or equipment to prevent 
and abate the further deposit of sediment. Results from 
the bottom sampling and testing program show that contaminants 
are much more widespread than originally 
estimated. The final scope of the project is being 
negotiated with the project sponsor. Approved estimated 
Federal cost for new work is $3,200,000 (1992). The project 
was authorized by the Water Resources Development Act 
of 1986 (Sec. 206, PL 99-662). 
Local cooperation. Local interests must pay 25 percent 
of the total cost of the project estimated at $1,070,000. 
Operations and results during fiscal year. New work: 
Planning, engineering, and design was continued at a cost 
of $210,354. 
Condition at end of fiscal year. Sediment testing was 
completed. Proposed project was drafted and sent to project 
sponsor for review. 
22. LOWER CREEK, LENOIR, N. C. 
Location. The project is located in northwest North 
Carolina near the city of Lenoir in Caldwell County and is 
approximately 60 miles northwest of Charlotte and approximately 
60 miles northeast of Asheville. (See USGS 
quadrangle sheet, Lenoir, N. C.) 
Existing project. The authorized project involves about 
1.4 miles of Lower Creek and .4 miles of Zacks Fort Creek 
of channel widening with a combination of trapezoidal and 
bench channel design. The improved channel bottom widths 
range from 50 to 75 feet, roughtly doubling the size of 
the existing channel. Approved estimated Federal cost for 
construction is $1,940,000 (1992). The project was approved 
by the Assistant Secretary of the Army on September 4, 
1991, under Section 205 of the 1948 Flood Control Act, as 
amended. 
Local cooperation. Local interests must provide all 
lands, easements and rights-of-way, including suitable 
disposal areas as may be determined by the Chief of 
Engineers to be necessary for construction and subsequent 
maintenance and inspection of the project; accomplish 
without cost to the United States all relocations 
and alterations of buildings, transportation facilities, and 
other structures and improvements made necessary by 
the construction; provide, during the process of construction, 
an amount equal to not less than 25 percent of total 
project cost, estimated at $693,000, at least 5 percent of 
which will be cash. The amount to be provided shall include 
the value of cost of all lands, easements, rights-ofway, 
and facility and utility alterations and relocations 
necessary for construction and subsequent maintenance of 
the project, including suitable excavated material disposal 
areas, as may be determined by the Chief of Engineers; 
hold and save the United States free from damages due to 
the construction and subsequent maintenance, except 
damages due to the fault or negligence of the United 
States or its contractors; maintain and operate the project 
after completion without cost to the United States in accordance 
with regulations prescribed by the Secretary of 
the Army; at least annually inform affected interests that 
the channel will not provide complete flood protection and 
assume full responsibility for all project costs in excess of 
the Federal cost limitation of $5,000,000. Fully complied 
with to date. 
Operations and results during fiscal year. New work: 
Real estate planning was continued at a cost of $6,455. 
Engineering and design was continued at a cost of $24,040. 
Condition at end of fiscal year. Plans and specifications 
are substantially complete. The Local Cooperation Agreement 
(LCA) was executed in November 1991. The City of 
Lenoir has begun the rights-of-way acquisition. Contract 
award is scheduled for March 1994. 
6-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
23. NEUSE RIVER, ORIENTAL, N. C. 
Location. The Town of Oriental, North Carolina, is 
located in the Neuse River Drainage Basin near the 
Pamlico Sound. The Hodges Street bulkhead is located at 
the head of the harbor which provides berthing facilities 
for transient craft as well as resident commercial vessels. 
The harbor is part of the Smith's Creek (Pamlico County), 
North Carolina, project which was dredged in 1956. (See 
USGS quadrangle sheet, Oriental, N. C.) 
Existing project. The approved plan is for the replacement 
of 230 linear feet of existing timber bulkhead 
(Hodges Street Bulkhead) with a steel sheet-pile system 
and replacement of attendant features disturbed by construction. 
The project was approved by the Chief of 
Engineers on June 14, 1990, under Section 14, 1946 Flood 
Control Act, as amended. 
Local cooperation. Local interests must provide all 
lands, easements and rights-of-way, including suitable borrow 
and disposal areas as determined by the Chief of 
Engineers to be necessary for construction and subsequent 
maintenance and inspection of the project; accomplish 
without cost to the United States all relocations and 
alterations of buildings, transportation facilities, storm 
drains, utilities, and other structures and improvements 
made necessary by the construction; provide, during the 
period of construction, an amount equal to but not less 
than 25 percent of total project costs, at least 5 percent of 
which will be cash. This amount shall include the value or 
cost of all lands, easements, rights-of-way, and facility and 
utility alterations and relocations necessary for construction 
of the project, including suitable borrow and excavated 
material disposal areas, as may be determined by 
the Chief of Engineers; hold and save the United States 
free from damages due to the construction and subsequent 
maintenance, except damages due to the fault or 
negligence of the United States or its contractors; maintain 
and operate the project after completion without cost 
to the United States in accordance with regulations 
prescribed by the Secretary of the Army and assume full 
responsibility for all project costs in excess of the Federal 
cost limitation of five hundred thousand dollars ($500,000). 
Fully complied with to date. 
Operations and results during fiscal year. New work: 
Adjustments in cost-sharing cost resulted in a decrease in 
Federal cost of $2,705 and an increase in contributed funds 
cost of $2,979. 
Condition at end of fiscal year. A construction contract 
was awarded in December 1990 and was completed in July 
1991. 
24. ROANOKE RIVER UPPER BASIN, VIRGINIA, 
HEADWATERS AREA 
Location. The project is located on the Roanoke River in 
the City of Roanoke, VA. (See USGS quadrangle sheet, 
Roanoke, VA.) 
Existing project. The authorized plan includes about 6.4 
miles of channel widening along the 10-mile project reach 
through the City of Roanoke, VA. Channel widening will 
be accomplished with the construction of a benched channel 
above the elevation of the average streamflow. Other 
flood damage reduction features include floodproofing at 
one location, training walls to prevent floodwater intrusion 
into low areas along the river (total length 7,200 feet), 
replacement of two low-level bridges with constrict 
streamflows and a flood warning system. Recreation 
facilities consist of a 5-mile recreation trail along the project 
reach and access and parking areas. Approved 
estimated Federal cost for new work is $21,800,000. The 
project was authorized by the Water Resources Development 
Act of 1986 (H.R. 6, PL 99-662). 
Local cooperation. Local interests must provide all 
lands, easements, and rights-of-way including spoil 
disposal areas presently estimated at $7,768,000; modify or 
relocate buildings, utilities, roads and other facilities except 
railroad bridges, where necessary for construction of 
the project presently estimated at $2,508,000; pay 25 percent 
of the cost of flood warning system (partially offset by 
a credit for lands, easements, rights-of-way, and relocations) 
presently estimated at $10,000; pay 5 percent of the 
total cost allocated to flood control in cash in addition to all 
lands, easements, rights-of-way and relocations, and bear 
all costs of operation, maintenance, and replacement of 
flood control facilities presently estimated at $1,452,000; 
pay one-half of the separable cost allocated to recreation 
(partially offset by a credit for land, easements, rights-ofway 
and relocations) and bear all costs of operation, 
maintenance and replacement of recreation facilities 
presently estimated at $1,503,000; and pay 25 percent of 
the cost of non-structural floodproofing (partially offset by 
a credit for lands, easements, rights-of-way and relocations) 
presently estimated at $359,000. Fully complied with 
to date. 
Operations and results during fiscal year. New work: 
Real estate planning was continued at a cost of 
$9,172.Logperch monitoring was continued at a cost of 
$70,807. Planning, engineering and design was continued 
at a cost of $880,342. 
Condition at end of fiscal year. The contract for the flood 
warning system was completed in January 1991. The contract 
for the sewage treatment plant floodproofing was 
awarded in August 1991 and is scheduled for completion in 
January 1993. HTW investigations are being accomplished 
by the sponsor. Completion of the total project is scheduled 
for July 1997. 
25. YADKIN RIVER BASIN, N. C. AND S. C. 
Location. The river rises on the eastern slope of the 
Blue Ridge Mountains in western North Carolina, flows 
generally easterly about 100 miles to the vicinity of Donnaha, 
North Carolina, thence southeasterly 104 miles to its 
confluence with Uwharrie River near Badin, North 
Carolina, where its name changes to Great Pee Dee River. 
(See U.S. Geological Survey map of North Carolina.) 
Existing project. The Flood Control Act of July 24,1946, 
authorized construction of four flood control dams in the 
Upper Yadkin River Basin, two on the Yadkin River above 
Wilkesboro, North Carolina, and two on Reddies River, a 
tributary stream. Studies made subsequent to authoriza- 
6-14

WILMINGTON, N. C., DISTRICT 
tion established the economic advantage of providing 
needed flood-control storage in only two reservoirs, one on 
the Reddies and one on the Yadkin. Present planning considers 
only the two-reservoir plan, W. Kerr Scott Dam and 
Reservoir constructed 1962 and Reddies River Lake. W. 
Kerr Scott was transferred to the Wilmington District 
from Charleston in fiscal year 1980. Any future work on 
Reddies River will also be done by the Wilmington 
District. (See Table 6-J on Dams and Reservoirs.) 
25A. W. KERR SCOTT DAM AND RESERVOIR, N. C. 
Location. W. Kerr Scott Dam and Reservoir is on 
Yadkin River, North Carolina, about 6 miles upstream 
from Wilkesboro. At full flood-control pool elevation (1,075 
feet mean sea level), the reservoir extends 15.7 miles 
upstream to the Wilkes-Caldwell County line. 
Existing project. The project consists of a rolled earthfill 
dam 1,740 feet long, with top of dam at elevation 1,107.5 
feet mean sea level or about 148 feet above streambed 
elevation; a spillway near the north abutment of the dam 
in a rock cut with crest elevation 1,075; and outlet works 
consisting of an intake structure, control tower, and a circular 
concrete conduit 12.25 feet in diameter through the 
base of the dam near the south abutment. The reservoir 
has a gross capacity of 153,000 acre-feet of which 112,000 
acre-feet are reserved for flood control, 33,000 acre-feet 
will be used as required for water supply, and 8,000 acrefeet 
being contained in the minimum pool. Estimated cost 
is $9,110,000 (1983) for new work. The existing project was 
authorized by the 1946 Flood Control Act. 
Local cooperation. Requirements fully satisfied. For 
details, see page 413 of Annual Report for 1963. 
Operations and results during fiscal year. Maintenance: 
Installation of underground fuel tanks cost $14,742. 
Replacement of management center cost $29,025. Liquefaction 
study cost $2,137. Indication and control 
system/flood gates cost $48,712. Archeological surveys 
cost $3,600. Commercial activities study of Natural 
Resources management functions cost $9,804. Revision of 
water control manual cost $169,712. Conversion of package 
plants to septic tile fields cost $25,232. Road paving cost 
$158,625. Environmental Review Guide for Operations 
(ERGO) investigations cost $27,879. Normal operation and 
maintenance cost $1,392,457. Maintenance and operation of 
dams cost $79,200. 
Condition at end of fiscal year. The project was commenced 
in August 1960 and placed in operation for flood 
control and water storage purposes in August 1962. 
26. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections 
were made for the following projects during fiscal year 
1992: Ellis Swamp, Gates County, N. C.; Gapway Swamp, 
Columbus County, N. C.; Old Field Swamp, Robeson County, 
N. C.; Gardners Creek, Martin County, N. C.; New 
River, Onslow County, N. C.; Pungo Creek, Beaufort County, 
N. C.; South Creek, Beaufort County, N. C.; Pungo 
River, Beaufort County, N. C.; Filberts Creek, Edenton, 
N. C.; Pantego and Cucklers Creek, Beaufort County, 
N. C.; White Oak Dike, Bladen and Pender Counties, N. C.; 
Ellerbe Creek, Durham County, N. C.; Pasquotank Dike, 
Pasquotank County, N. C.; Perquimans River, Perquimans 
County, N. C.; Core Creek, Craven County, N. C.; 
Princeville Dike, Edgecombe County, N. C.; Swift Creek, 
Pitt County, N. C.; Carolina Beach, New Hanover County, 
N. C.; Wrightsville Beach, New Hanover County, N. C.; 
Goldsboro, Neuse River, Wayne County, N. C.; Broad 
Creek, Beaufort County, N. C.; Little Rockfish Creek, 
Hope Mills, N. C.; Black River, Harnett County, N. C.; Lick 
Run, Roanoke, Va.; Deep Creek, Edgecombe County, N. C.; 
Joyce Creek, Camden County, N. C.; Ararat River, Surry 
County, N. C.; South Mayo River, Stuart, Va; and Leith 
Creek, Scotland County, N. C. Responsible local officials 
were advised of inadequacies in maintenance and operation 
on local flood protection works where appropriate. 
Cost for the period was $13,000. Total cost to September 
30, 1992, was $486,529, charged to operations. 
27. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization). 
(See Table 6-K.) 
Emergency flood control activities and hurricane flood 
and shore-protection activities at Federally authorized 
projects (Public Law 99, 84th Congress, and antecedent 
legislation). 
National Emergency Preparedness Program cost 
$133,483. Disaster Preparedness Program cost $207,918. 
Multiple-Purpose Projects, Including Power 
28. ROANOKE RIVER BASIN, VA. AND N. C. 
Location. The project is on the Roanoke River and its 
tributaries in Virginia and North Carolina within a radius 
of 100 miles from Danville, Virginia. 
Existing project. The Flood Control Act of 1944 approved 
a general plan for the comprehensive development of 
the Roanoke River Basin for flood control and other purposes, 
and authorized construction of John H. Kerr and 
Philpott Reservoirs. (See Table 6-J for a list of dams and 
reservoirs included in the comprehensive plan.) 
Local cooperation. None required. John H. Kerr and 
Philpott Reservoirs are the only projects in the comprehensive 
plan that have been authorized for construction. 
(See Table 6-J on Dams and Reservoirs.) 
28A. JOHN H. KERR DAM AND RESERVOIR, VA. 
AND N. C. 
Location. The project is on Roanoke River, about 178.7 
river miles above its mouth, in Mecklenburg County, 
6-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Virginia, and 20.3 miles downstream from Clarksville, 
Virginia. The reservoir extends upstream on Roanoke 
River 56 miles and on Dan River 34 miles. 
Existing project. The authorized project provides for a 
concrete gravity dam with wing and saddle dikes on the 
right and left banks, with a total length of about 22,285 
feet. The reservoir is operated as a unit of a coordinated 
system of reservoirs in the Roanoke River Basin for 
control of floods, generation of hydroelectric power, 
regulation of low-water flow, and for other purposes. The 
power installation is 204,000 kilowatts. (For further details 
see Annual Report for 1962.) Estimated cost is $67,529,000 
(1983) for construction and $24,521,000 for lands and 
damages, including relocation of highways, railroads, and 
utilities, a total of $92,050,000 for new work. The existing 
project was authorized by the 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Replacement of shoreline bulkhead cost $19,022. Work in 
connection with acquisition of land in South Boston area 
cost $1,209. Archeological salvage at Satterwhite Point 
Historic Site cost $3,332. Replacement of the powerhouse 
computer was continued at a cost of $1,667. Periodic 
inspection of the dam bridge cost $7,887. Adjustments in 
cost for the North Bend Park water system improvements 
resulted in a negative cost of $7,008. Construction of North 
Bend Park lift station cost $2,851. Island Creek Pumping 
Station Abandonment Study cost $81,437. Secondary bus 
damage at Island Creek Pumping Station cost $14,563. 
Safety and removal action plan for removal of DDT cost 
$220,397. Initiation of design for earth dike modification 
cost $11,744. Renovation of Rudds Creek recreation area 
cost $1,114,864. Periodic inspection and evaluation of dam 
cost $3,773. Analysis of swim beaches for contaminated 
soil cost $34,850. Determination of action for contaminated 
soil at reservoir and recreation areas cost $134,309. 
Installation of fuel tanks cost $20,917. Archeological 
survey cost $15,157. Clean and paint tainter gates cost 
$31,993. Waterfowl subimpoundments and environmental 
studies cost $27,894. Sleeve gun equipment to deter 
striped bass from entering power plant turbines cost 
$10,573. Preparation of a drought manangement plan cost 
$1,195. Normal operation and maintenance cost $5,329,975. 
Maintenance and operation of dams cost $79,000. 
Condition at end of fiscal year. Project is complete 
except for additional recreational facilities. Production of 
power and protection from floods are provided by project. 
28B. PHILPOTT LAKE, VA. 
Location. The project is located on Smith River, 
Virginia, 44.3 miles above its junction with Dan River, and 
35 miles upstream from Virginia-North Carolina State line 
in Franklin and Henry Counties. 
Existing project. The authorized project provides for a 
concrete gravity dam 892 feet long and with a maximum 
height of 220 feet. Reservoir is operated as a unit of a coordinated 
reservoir system for flood control in the Roanoke 
River Basin, generation of hydroelectric power, regulation 
of low-water flow, and for other purposes. The powerhouse 
has a total installation of 14,000 kilowatts. (For further 
details see Annual Report for 1962.) Federal cost estimate 
is $13,933,000 (1983) for construction and $1,157,000 for 
lands and damages, a total of $15,090,000. Existing project 
was authorized by 1944 Flood Control Act. 
Local cooperation. None required. 
Operations and results during fiscal year. Maintenance: 
Drought Management Plan cost $7,294. Waterfowl subim-, 
poundment and archeological and cultural resources investigations 
cost $3,873. Historical and archeological 
survey for proposed historical properties management 
plan cost $500. Installation of replacement computer cost 
$8,415. Operation and Maintenance boathouse and docking 
bulkhead cost $92,622. Commercial activities study of 
Natural Resources management functions cost $7,265. 
Normal operation and maintenance cost $1,758,510. 
Maintenance and operation of dams cost $79,000. 
Condition at end of fiscal year. The project is complete 
except for additional recreational facilities, and is providing 
power and flood protection. 
29. SCHEDULING FLOOD CONTROL RESERVOIR 
OPERATIONS 
B. Everett Jordan Dam and Lake, located in the Cape 
Fear River Basin, North Carolina, began fiscal year 1992 at 
elevation 215.24 feet, m.s.l., or 0.76 feet below guide curve. 
Below normal rainfall from October to the latter part of 
December caused the lake level to gradually be drawn 
down to the minimum elevation of the fiscal year at elevation 
212.69 feet, m.s.l. or 3.31 feet below guide curve on 
December 26, 1991. Heavy rainfall then caused the lake 
level to rise to elevation 219.08 feet, m.s.l., on January 6, 
1992. Jordan Lake was drawn down to the normal pool 
elevation of 216.0 feet, m.s.l., on January 13, 1992. The lake 
level remained near guide curve through April 1992 except 
for two peaks of 219.17 and 221.78 feet, m.s.l., on 
February 28, and April 24, 1992, respectively. The latter 
peak elevation was the maximum elevation of the fiscal 
year and was 5.78 feet above guide curve. Jordan Lake 
then remained near normal through the end of August except 
for two minor rises to 217.95 and 216.74 feet, m.s.l., on 
June 11 and August 17, respectively. The lake level was 
gradually drawn down the reminder of the year because 
inflows were only 20 percent of normal. Jordan Lake ended 
the fiscal year at elevation 214.10 feet, m.s.l., or 1.90 feet 
below guide curve. Maximum flood storage utilized during 
the fiscal year was 17 percent and the maximum conservation 
pool drawdown was 30 percent, respectively. Flood 
damages prevented during fiscal year 1992 were $56,400 
making the cumulative total since inception of the project 
in 1981 at $13,892,400. Total cost of functional operation for 
the period was $154,998. 
Falls Lake, located in the Neuse River Basin, North 
Carolina, began fiscal year 1992 at elevation 247.59 feet, 
m.s.l, or 3.41 feet below guide curve. Below normal rainfall 
from October through December 1991 caused the lake 
level to draw down to the minimum elevation of the fiscal 
year at 244.98 feet, m.s.l., or 5.12 feet below the guide 
6-16

WILMINGTON, N. C., DISTRICT 
curve on December 26. Heavy rainfall then caused the lake 
level to rise to 251.20 feet, m.s.l., on January 6, 1992. Falls 
Lake then remained near guide curve through the end of 
June except for three minor rises of 251.55, 252.00 and 
251.54 feet, m.s.l, on February 28, March 8 and April 23, 
respectively. The peak elevation of 252.00 feet, m.s.l., occuring 
on March 8 was the maximum elevation of the fiscal 
year and was 1.90 feet above guide curve. On July 4, the 
lake level rose to 251.82 feet, m.s.l. Afterwards, Falls Lake 
was gradually drawn down for the remainder of the fiscal 
year due to below normal inflows and water quality 
releases to meet downstream minimum flow requirements. 
Falls Lake was at elevation 248.77 feet, m.s.l., 
or 2.23 feet below guide curve at the end of the fiscal year. 
The maximum flood storage utilized during the year was 
10 percent, and the maximum conservation pool drawdown 
was 54 percent. Although, no flood damages were 
prevented during fiscal year 1992, flood damages 
prevented since inception of the project in 1983 total 
$37,850,000. Total cost of functional operation for the 
period was $87,649. 
John H. Kerr Dam and Reservoir, located in the 
Roanoke River Basin, Virginia, and North Carolina, began 
fiscal year 1992 at elevation 298.26 feet, m.s.l., or 1.24 feet 
below the guide curve. Since the guide curve drops from 
300 to 295.5 feet, m.s.l., during October and November, the 
reservoir level met and fluctuated near the guide curve 
through the end of December. Heavy rainfall in early January 
caused a rise to 300.87 feet, m.s.l., on January 7. The 
resevoir level was steadily drawn down to slightly below 
guide curve to elevation 295.36 feet, m.s.l., on January 22 
which was the minimum elevation of the fiscal year. Kerr 
Reservoir remained near guide curve until February 25 
when rainfall caused the reservoir level to rise to 301.22 
feet, m.s.l., on March 30 which was near the rising guide 
curve elevation of 301.0 feet, m.s.l., at the end of March. 
Heavy rainfall produced two peaks of 306.19 feet, m.s.l., 
the maximum elevation of the fiscal year, and 303.06 feet, 
m.s.l., on April 26 and June 10, respectively. The reservoir 
level was near guide curve the remainder of the summer 
and ended the fiscal year at elevation 299.41 feet, m.s.l. In 
cooperation with State and Federal fish and wildlife agencies, 
the Wilmington District continued operating under a 
4-year trial fish flow regime started in fiscal year 1989 in 
the lower Roanoke River to enhance the striped bass 
spawning. Fish flows commenced on April 1 and concluded 
on June 15. Maximum flood pool storage utilized during 
the year was 26 percent. The contractual power pool 
storage remaining at the lowest lake elevation was 32 percent. 
Gross generation for the fiscal year amounted to 
341,024,900 kilowatt hours or 18 percent below normal and 
net marketed power revenue was $5,540,626, making a 
cumulative total of $151,689,510 since inception of the project 
in 1952. Flood damages prevented during fiscal year 
1992 were $2,535,000 making the cumulative total of 
$158,739,000. Total cost of functional operation for the 
period was $391,655. 
Philpott Lake, located on the Smith River in the Dan 
River Basin, Virginia, began fiscal year 1992 at elevation 
969.50 feet, m.s.l., or 2.00 feet below guide curve. Because 
inflows during October were only 30 percent of normal, the 
lake level was drawn down to the minimum elevation of 
the fiscal year at 968.52 feet, m.s.l., or 2.98 feet below guide 
curve on November 1. Philpott Lake returned to guide 
curve on December 30. Minor lake level rises into the flood 
pool occurred on January 4 and March 16 at elevations 
974.32 and 974.58 feet, m.s.l., respectively. Heavy rains on 
April 20 and 21 produced a sharp rise to 982.26 feet, m.s.l., 
on April 22, which was the maximum elevation of the fiscal 
year and, also, the second highest lake elevation on record 
since inception of the project in 1952. The lake level was 
drawn down to guide curve on April 30. Excessive rainfall 
produced two peaks of 975.16 and 977.29 feet, m.s.l., on 
May 18 and June 6, respectively. Philpott Lake elevation 
was near guide curve the remainder of the fiscal year, and 
ended the year at 971.28 feet, m.s.l., or 022 foot below 
guide curve. Maximum flood pool storage utilized during 
the year was 74 percent. The contractual power pool 
storage remaining at the lowest lake elevation was 73 percent. 
Gross generation for the fiscal year amounted to 
28,986,830 kilowatt hours or 14 percent above normal and 
net marketed power revenue was $1,026,716 making the 
cumulative total since inception of $21,716,608. Flood 
damages prevented during fiscal year 1992 were 
$117,270,000, making the cumulative total since inception 
of the project at $272,081,000. Total cost of functional 
operation for the period was $135,757. 
W. Kerr Scott Dam and Reservoir, located in the 
Yadkin-Pee Dee River Basin, North Carolina, began fiscal 
year 1992 at elevation 1,029.38 feet, m.s.l., or 0.62 foot 
below guide curve. The reservoir level was gradually 
drawn down to the minimum elevation of the fiscal year at 
1027.97 feet, m.s.l., or 2.03 feet above guide curve on 
November 6 as the rainfall for October and November was 
below normal. W. Kerr Scott returned to guide curve on 
December 1. Minor rises in the reservoir level to 
elevations 1033.06,1032.32,1031.24 and 1031.58 feet, m.s.l., 
occured on December 4, January 4, February 26 and 
March 7, respectively. Heavy rainfall in April produced 
the maximum elevation of the fiscal year at 1043.11 feet, 
m.s.l., or 13.11 feet above guide curve on April 22. The 
reservoir level returned to guide curve on April 28 and 
remained at or near guide curve the remainder of the fiscal 
year except for one rise to 1038.33 feet, m.s.l., on June 5. 
W. Kerr Scott reservoir was at elevation 1029.99 feet, 
m.s.l., at the end of the fiscal year. Maximum flood storage 
utilitzed during the fiscal year was 20 percent, and the 
maximum conservation pool drawdown was 7 percent, 
respectively. Flood damages prevented during fiscal year 
1992 were $4,354,000 raising the cumulative total since 
inception of the project in 1963 to $89,351,000. Total cost of 
functional operation for the period was $79,540. 
General Investigations 
30. SURVEYS 
Cost for the period was $890,686 of which $333,955 was 
for navigation studies, $10,199 was for flood control 
studies, $230,282 was for beach erosion studies, $147,007 
6-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
was for Albemarle-Pamlico Estuarine Study, $95,000 for 
Special Investigations, $2,278 for FERC licenses review, 
$29,000 for interagency water resources development, 
$11,000 for National Estuary studies, $9,683 for the North 
American Waterfowl Management Plan, $5,000 for Soil 
Conservation Service, $718 for hydrologic studies, and 
$16,564 for cooperation with states. Contributed funds in 
the amount of $42,244 were expended for navigation 
studies, and $7,085 for cooperation with states. 
31. COLLECTION AND STUDY OF BASIC DATA 
Flood plain information studies, as authorized by Section 
206, 1960 Flood Control Act, as amended, comprise 
compilation and dissemination, upon the request of a State 
or a political subdivision thereof, of information on floods 
and flood damages, including identification of areas subject 
to inundation by floods of various magnitudes and frequencies, 
and general criteria for guidance of Federal and non- 
Federal interests and agencies in the use of flood plain 
areas; and provide advice to other Federal agencies and 
local interests for their use in planning to ameliorate the 
flood hazard. Total costs for the period were $289,585. 
Total costs to September 30, 1992 were $5,355,099. Contributed 
funds in the amount of $10,340 were expended for 
flood plain information studies. 
32. PRECONSTRUCTION ENGINEERING AND 
DESIGN 
Preconstruction engineering and design (PED) for 
Wilmington Harbor, Northeast Cape Fear River, N. C., 
was continued at a cost of $221,984. PED was completed on 
Roanoke River Upper Basin, Virginia, Headwaters Area at 
a cost of $448. PED was continued on Brunswick County 
Beaches, N. C., at a cost of $55,647. PED was continued on 
Sugar Creek, N. C. and S. C., at a cost of $105,556. PED 
was continued on West Onslow Beach and New River 
Inlet, N. C., at a cost of $197,954. PED was continued on 
Morehead City Harbor, N. C., at a cost of $331,744. PED 
was accomplished on Manteo (Shallowbog) Bay, N.C., at a 
cost of $214,885. PED was initiated for Wilmington 
Harbor, Ocean Bar, N. C., at a cost of $481,561. PED was 
accomplished on Fort Fisher and Vicinity, N. C., at a cost 
of $217,124. 
6-18

WILMINGTON, N. C., DISTRICT 
TABLE 6-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
1. Aquatic Plant Control 
(R&H Act of 1965) 
(Regular Funds) 
(Contributed Funds) 
2. Atlantic Intracoastal 
Waterway between 
Norfolk, Va. & St. 
Johns River, Fla. 
(Regular Funds) 
(Contributed Funds) 
3. Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
4. Cape Fear River, 
N. C. above 
Wilmington 
5. Channel from Back 
Sound to Lookout 
Bight, N. C. 
6. Drum Inlet, N. C. 
7. Far Creek, N. C. 
8. Lockwoods Folly 
River, N. C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
78,000 
75,645 
570,000 
550,674 
6,375,785 
6,462,571 
106,200 
101,800 
37,000 
46,538 
810,000 
752,765 
7,544,270 
7,660,282 
172,997 
178,369 
9,000 
35,730 
2,198,000 
1,704,957 
5,183,100 
4,757,743 
77,000 
77,000 
750 
577,200 
574,023 
154,800 
156,933 
8,700 
8,700 
346,700 
353,386 
680,207 
674,822 
25,953 
26,328 
2,700 
2,700 
217,763 
217,563 
585,247 
584,312 
836,000 
704,266 
-8,400 
-8,400 
13,300 
12,617 
360,100 
360,300 
540,600 
541,081 
20,000 
47,230 
5,465,000 
5,885,226 
7,555,800 
8,011,687 
621,400 
609,275 
31,809 
31,809' 
51,249,973' 
51,070,133' 
114,113,615' 
114,071,699 ' 
86,851 
86,851' 
667,300 
667,300 
- 818,040' 
- 818,040' 
16,300 3,736,811* 
16,300 3,736,811* 
- 34,000 
- 34,000 
- 326,225 
- 326,225 
- 3,759,573' 
- 3,759,573' 
754,900 17,273,2216 
896,066 17,271,818' 
- 88,328 
- 88,328 
126,300 2,924,324 
126,300 2,924,324 
- 166,119 
- 166,119 
- 1,066,579 
683 1,066,579 
- 164,642 
- 164,642 
5,650 1,774,217 
5,650 1,774,217 
- 241,272' 
- 241,272 '1 
663,000 6,396,893 
663,454 6,396,893 
- 92,650 
- 92,650" 
6-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
9. Manteo (Shallowbag) 
Bay, N. C. 
(Regular Funds) 
(Contributed Funds) 
10. Morehead City 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
11. Pamlico and Tar 
Rivers, N.C. 
12. Rollinson Channel, 
N. C. 
(Regular Funds) 
(Contributed Funds) 
13. Shallotte River, N. C. 
(Regular Funds) 
14. Silver Lake 
Harbor, N. C. 
(Regular Funds) 
(Contributed Funds) 
15. Stumpy Point Bay, N. C. 
(Regular Funds) 
(Contributed Funds) 
16. Waterway Connecting 
Pamlico Sound and 
Beaufort Harbor, N.C. 
(Regular Funds) 
(Contributed Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Contrib: 
Cost 
- 493,000 
- 162,890 
5,526,300 4,630,799 
5,445,397 4,746,173 
418,000 -210,725 
- 192,275 
1,873,400 
1,775,087 
89,778 
82,762 
18,000 
18,000 
669,500 
669,500 
269,200 
269,797 
995,455 
1,137,632 
57,500 
57,500 
8,414 
8,414 
-44,778 
2,840 
466,456 
466,456 
4,500 
4,500 
2,260 
2,636 
464,000 
614,879 
8,411,800 
8,339,095 
484,000 
477,427 
1,040,000 
1,040,000 
111,646 
98,289 
21,000 
21,000 
7,000 
7,000 
416,000 
416,000 
6,254 393,697 
6,254 393,697 
- 150,000 
- 135,000 
4,200 
4,200 
6-20 
152,879 
6,080,310 
6,100,398 
-27,781 
1,973,000 
1,971,000 
-730 
18,355 
24,500 
24,500 
184,640 
184,640 
9,800 
9,800 
681,000 
681,000 
8,606,94512 
8,580,59312 
66,824,916 
66,753,791 
1,891,434 
1,891,434 
6,546,053"3 
6,546,053"3 
49,180,628" 
49,178,628" 
1,375,330 
1,373,330 
674,651 
674,651 
988,205 
988,205 
589,105 
589,105 
1,901,863 
1,901,863 
41,142 
41,142 
18,181 
18,181 
540,197 
540,197 
184,284 
184,284 
7,365,874 
7,365,874 
75,000 
75,000 
268,381 
268,381 
1,141,266 
1,141,266 
274,000 
259,000 
502,567 
502,567 
3,433,669 
3,433,669 
2,452 
2,452 
486,500 
486,500

WILMINGTON, N. C., DISTRICT 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
17. Wilmington Harbor, N. C. New Work: 
(Regular Funds) Approp. 
Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) Maint: 
Contrib. 
Cost 
18A. B. Everett Jordan New Work: 
Dam and Lake, N. C. Approp. 
(Regular Funds) Cost 
Maint: 
Approp. 
Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
18B. Randleman Lake, N. C. New Work: 
Approp. 
Cost 
19. Carolina Beach and New Work: 
Vicinity, N. C. Approp. 
(Regular Funds) Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
20A. Falls Lake, N. C. New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
21. Hamlet City New Work: 
Lake, N. C. Approp. 
Cost 
22. Lower Creek, Lenoir, N.C. New Work: 
Approp. 
(Regular Funds) Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
23. Neuse River New Work: 
Oriental, N. C. Approp. 
(Regular Funds) Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
24. Roanoke River Upper Basin New Work: 
Va. - Headwaters Area Approp. 
(Regular Funds) Cost 
(Contributed Funds) New Work: 
Contrib. 
Cost 
25A. W. Kerr Scott Dam New Work: 
and Reservoir, N. C. Approp. 
Cost 
Maint: 
Approp. 
Cost 
3,868,100 
3,888,351 
422,041 
231,738 
3,647,000 
5,392,728 
1,002,400 
1,050,647 
31,572 
308 
270,000 
176,764 
-120,511 
3,510 
5,0 
6,1 
1,0 
1,1 
3,836,047 
3,761,008 
174,182 
345,635 
2,604,000 
4,111,778 
1,042,587 
982,900 
-105 
-28,208 
6,066,000 
5,936,134 
391,304 
534,125 
928,000 
1,936,246 
921,000 
984,145 
108 
285,000 
262,349 
)50,000 8,479,000 
88,558 5,803,487 
95,000 1,301,061 
121,837 1,286,917 
- 350,000 
- 242,924 
17,000 125,000 
17,876 1,937 
300 0 
e,VU 
8,175 1,325 
30,000 22,800 
32,654 21,367 
- 7,000 
- 6,462 
- 246,000 
- 121,344 
- 496,000 
- 97,856 
1,307,000 1,435,956 
1,351,320 1,412,626 
67 
1,421,000 
1,520,178 
1,263,000 
1,207,696 
3,479,000 
6,637,146 
996,000 
974,643 
- 18,715,226' s 
- 18,715,226" 
8,155,000 79,653,06716 
8,256,978 79,526,96516 
895,614 6,224,744" 
776,142 6,076,977" 
2,300,000 142,444,641 
1,902,208 141,740,498 
1,047,000 10,229,843" 
1,066,026 10,196,705'" 
-56,654 1,764,735 
5,567 1,764,735 
- 4,797,588 
217 4,786,051 
678,000 
553,602 
-12,357 
42,947 
4,434,000 
4,490,985 
1,015,700 
1,077,207 
11,472,533 
11,294,381 
7,925,09720 
7,925,097 � 
168,719,996 
168,302,119 
10,677,361"8 
10,668,598"9 
450,000 - 800,000 
225,380 210,354 678,658 
119,000 - 500,50021 
182,981 30,495 469,97622 
- - 114,00023 
- - 114,00023 
219,000 -3,864 277,936" 
219,274 -2,705 277,9362' 
88,092 -2,582 92,510 
83,069 2,979 92,510 
363,000 745,000 1,354,000 
256,971 880,321 1,258,636 
113,300 17,286 626,586 
334,049 122,389 554,294 
- - 8,841,326 
- - 8,841,326 
1,576,000 1,774,400 21,452,504" 
1,423,951 1,961,125 21,404,56627 
6-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 6-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
28A. John H. Kerr Dam New Work: 
and Reservoir, Va. & N.C. Approp. - - - - 94,402,927 
Cost 2,131 - - - 94,402,927 
Maint: 
Approp. 5,245,400 5,683,442 6,353,400 7,116,000 96,126,78428 
Cost 6,333,731 5,686,512 6,270,462 7,161,602 95,684,76429 
28B. Philpott Lake, Va. New Work: 
Approp. -- - - - 14,796,384 
Cost - - - - 14,796,384 
Maint: 
Approp. 1,796,600 1,772,490 1,957,000 1,913,300 29,998,6965o 
Cost 1,892,879 1,830,346 1,902,895 1,957,479 29,897,03051 
1. Includes $2,369 refund to local interests in FY 82. 
2. Includes $198,707 for previous projects. 
3. Includes $107,634 for previous projects. 
4. Includes $13,934 refund to local interests. 
5. Includes $25,000 for previous projects. 
6. Includes $12,854 for previous projects. 
7. Includes $149,119 for previous projects. 
8. Includes $8,178 for previous projects. 
9. Includes preauthorization study funds: FY 64, $3,000; 
FY 65, -$2,755; FY 71, $8,000; FY 72, $2,000; FY 74, $9,000; FY 
75, $25,000; FY 76 & 76T, $20,000; FY 77, $2,500; FY 78, $8,800; 
FY 79, $3,000; FY 81, $1,680; and preconstruction planning 
funds: FY 80, $15,000 and FY 81, $19,320. 
10. Includes preauthorization study costs: FY 64, $219; FY 
65, $26; FY 71, $8,000; FY 72, $1,448; FY 73, $552; FY 74, $9,000; 
FY 75, $11,925; FY 76 & 76T, $27,977; FY 77, $7,598; FY 78, 
$7,449; FY 79, $4,351; FY 81, $1,680; and preconstruction planning 
costs: FY 80, $5,686 and FY 81, $1,471. 
11. Includes $69,145 refund to local interests. 
12. Adjusted by $6,361 to reflect actual cost. 
13. Includes $44,484 for previous projects. 
14. Includes $284,557 for previous projects. 
15. Includes $4,625,614 for new work on previous projects. 
16. Includes $602,614 for previous projects. 
17. Includes refunds to local interests: FY 78, $92,374; FY 
79, $8,000; FY 80, $14,007; FY 81, $1,847; FY 82, $2,823; FY 85, 
$60,000. 
18. Includes maintenance and operation of Dams funds: 
FY 87, $66,678; FY 88, $75,000; FY 89, $73,000; FY 90, $54,000; 
FY 91, $97,200; FY 92, $79,000. 
19. Includes maintenance and operation of Dams costs: FY 
87, $66,678; FY 88, $75,000; FY 89, $73,000; FY 90, $54,000; FY 
91, $97,200; FY 92, $79,000. 
20. Includes refunds to local interests: FY 83, $400,000; FY 
84, $128,345; FY 85, $82,600. 
21. Includes preauthorization study funds: FY 84, $42,500; 
FY 85, $25,000; FY 86, $20,000; FY 87, $85,000; FY 88, $67,000; 
FY 89, $17,000 and preconstruction planning and construction 
funds: FY 90, $125,000 and FY 91, $119,000. 
22. Includes preauthorization study costs: FY 84, $32,715; 
FY 85, $18,492; FY 86, $31,355; FY 87, $67,544; FY 88, $86,581; 
FY 89, $17,876 and FY 90, $1,937. 
23. All contributed funds and cost thru FY 91 are for 
preauthorization study. 
24. Includes preauthorization study funds: FY 88, $10,000; 
FY 89, $30,000 and preconstruction planning and construction 
funds: FY 90, $22,800. 
25. Includes preauthorization study costs: FY 88, $7,346; 
FY 89, $32,654; and preconstruction planning costs: FY 90, 
$21,367. 
26. Includes Special Recreation Use Fees funds: FY 74, 
$4,000; FY 75, $5,500; FY 76 & 76T, $3,600; FY 77, $5,800; FY 
78, $7,200; FY 79, $8,000; FY 80, $10,000; FY 81, $10,000; FY 82, 
$11,040; FY 83, $7,000; FY 84, $9,000; and maintenance and 
operation of Dams funds: FY 87, $66,678; FY 88, $75,000; FY 89, 
$73,000; FY 90, $54,000; FY 91, $97,200; FY 92, $79,200. 
27. Includes Special Recreation Use Fees costs: FY 74, 
$4,000; FY 75, $4,400; FY 76 & 76T, $4,666; FY 77, $5,193; FY 
78, $6,824; FY 79, $7,506; FY 80, $11,312; FY 81, $9,688; FY 82, 
$9,727; FY 83, $7,000; FY 84, $8,444; FY 85, $2,379; and 
maintenance and operation of Dams costs: FY 87, $66,678; FY 
88, $75,000; FY 89, $73,000; FY 90, $54,000; FY 91, $97,200; FY 
92, $79,200. 
28. Includes Special Recreation Use Fees funds: FY 74, 
$35,000; FY 76 & 76T, $48,000; FY 77, $51,400; FY 78, $115,100; 
FY 79, $63,000; FY 80, $60,000; FY 81, $80,000; FY 82, $67,160; 
FY 83, $77,759; FY 84, $73,000; and maintenance and operation 
of Dams funds: FY 79, $167,646; FY 87, $66,678; FY 88, $75,000; 
FY 89, $73,000; FY 90, $54,000; FY 91, $97,200; FY 92, $79,000. 
29. Includes Special Recreation Use Fees costs: FY 75, 
$35,000; FY 76 & 76T, $13,606; FY 77, $85,692; FY 78, $114,604; 
FY 79, $1,120; FY 80, $118,718; FY 81, $83,760; FY 82, $67,160; 
FY 83, $77,759; FY 84, $67,850; FY 85, $5,149; and maintenance 
and operation of Dams costs: FY 79, $167,350; FY 80, $296; FY 
87, $66,678; FY 88, $75,000; FY 89, $73,000; FY 90, $54,000; FY 
91, $97,200; FY 92, $79,000. 
30. Includes Special Recreation Use Fees funds: FY 75, 
$47,000; FY 78, $40,400; FY 79, $22,000; FY 80, $25,000; FY 81, 
$20,000; FY 82, $20,240; FY 83, $21,000; FY 84, $19,000; and 
maintenance and operation of Dams funds: FY 87, $66,678; FY 
88, $75,000; FY 89, $73,000; FY 90, $54,000; FY 91, $97,200; FY 
92, $79,000. 
31. Includes Special Recreation Use Fees costs: FY 75, 
$13,741; FY 76 & 76T, $31,666; FY 77, $1,593; FY 78, $39,771; 
FY 79, $22,629; FY 80, $24,619; FY 81, $20,381; FY 82, $20,240; 
FY 83, $21,000; FY 84, $19,000; and maintenance and operation 
of Dams costs: FY 87, $66,678; FY 88, $75,000; FY 89, $73,000; 
FY 90, $54,000; FY 91, $97,200; FY 92, $79,000. 
6-22

WILMINGTON, N. C., DISTRICT 
TABLE 6-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 25, 1912 
July 25, 1912 
August 8, 1917 
July 18, 1918 
January 21, 1927 
July 3, 1930 
March 4, 19332 
June 26, 19343 
August 26, 1937 
August 26, 1937 
June 20, 1938 
June 20, 1938 
March 2, 1945 
June 30, 1948 
May 17, 1950 
May 17, 1950 
September 3, 1954 
November 29, 1963, 
sec. 107 
July 14, 1960 
April 7, 1966, 
sec. 107 
July 14, 1960 
November 7, 1966 
November 7, 1966 
December 31, 1970 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA., and ST. JOHNS RIVER, 
FLA. (See Section 2 of textj 
Original route of the Norfolk-Beaufort Inlet section. 
Purchase of canal. 
Change in route; following changes approved by 
Secretary of War, April 14, 1919: 
Albemarle Sound-Pamlico Sound section: Changed from 
"Alligator River-Rose Bay route" to "Alligator River- 
Pungo River route." 
Pamlico Sound-Neuse River section: Changed from 
"Pamlico Sound-Brant Shoal Neuse River route" to 
"Goose Creek-Bay River route." 
Alligator River-Pungo route (proposed land cut 
connecting the rivers): Changed from a straight line to a 
bent line approaching nearer town of Fairfield, N. C. 
A 12-foot channel 90 feet wide from Beaufort to Cape 
Fear River, N. C., including highway bridge and tidal 
lock.' 
An 8-foot channel 75 feet wide from Cape Fear River to 
Winyah Bay, S. C. 
Construct a suitable bridge near Fairfield, N. C. 
Operating and care of works of improvements provided 
for with funds from War Department appropriations for 
rivers and harbors. 
Increasing dimensions of waterway to 12 feet deep and 
90 feet wide. 
A 12-foot side channel 90 feet wide to Swansboro. 
A yacht basin near Southport, 12 feet deep, 230 feet 
wide, and 450 feet long, with connecting channel. 
A 6-foot channel 90 feet wide from New River Inlet to 
Inland Waterway. 
Six mooring basins.5 
A 12-foot channel in New River.," 
Vicinity of Fairfield - drainage. 
Masonboro Inlet and connecting channels, including 
jetties at the inlet.7 
A 12-foot channel and basin in Peltier Creek. 8 
A 6-foot channel 90 feet wide from Intracoastal 
Waterway to Bogue Inlet gorge. 
An 8-foot channel 150 feet wide through New Topsail 
Inlet, thence a 7-foot channel 80 ft. wide to Intracoastal 
Waterway by way of Old Topsail Creek; and a 7-foot 
channel 80 feet wide in Banks Channel from New 
Topsail Inlet, paralleling barrier beach, to Intracoastal 
Waterway. 
Maintenance of a channel, 6 feet deep, 80 feet wide, and 
8,000 feet long, from the through channel of the 
waterway to and including a basin of the same depth, 
130 feet wide and 180 feet long at Carolina Beach. 
Maintenance of general navigation features of N. C. 
State Ports Authority Small Boat Harbor at Southport. 
Replacement of Federally-owned and operated highway 
bridges at Coinjock, Fairfield, Wilkerson Creek, 
Hobucken, and Core Creek. 
H. D. 391, 62d Cong., 2d sess. 
H. D. 589, 62d Cong., 2d sess. 
H. D. 1478, 63d Cong., 3d sess. 
and H. D. 1136, 64th Cong., 1st 
sess.' 
Approved by Secretary of War, 
May 15, 1919. 
H. D. 450, 69th Cong., 1st sess. 
H. D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 5, 72d Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc. 6, 75th Cong., 1st sess.' 
Rivers and Harbors Committee 
Doc. 16, 75th Cong., 1st sess.' 
H. D. 549, 75th Cong., 3d sess.' 
H. D. 691, 75th Cong., 3d sess.' 
H. D. 660, 76th Cong., 3d sess.' 
H. D. 421, 80th Cong., 1st sess.' 
H. D. 723, 80th Cong., 2d sess.' 
H. D. 341, 81st Cong., 1st sess.' 
H. D. 379, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1963. 
Detailed Project Report 
July 1965 
H. D. 515, 89th Cong., 2d sess.' 
H. D. 514, 89th Cong., 2d sess.' 
H. D. 142, 92nd Cong., 1st sess. 
6-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts 
October 22, 1976 
August 13, 1968 
February 18, 1982, 
sec. 107 
July 14, 1960 
September 7, 1983, 
sec 107 
July 14, 1960 
November 17, 1986 
March 3, 1881 
March 2, 1907 
March 3, 1925 
July 3, 1930 
March 2, 1945 
May 17, 1950 
May 21, 1965, 
sec. 107 
July 14, 1960 
August 12, 1983, 
sec. 107 
July 14, 1960 
July 3, 1930 
October 17, 1940 
February 7, 1967, 
sec. 107 
July 14, 1960 
August 30, 1935' 
August 26, 1937 
March 2, 1945 
6-24 
Work Authorized 
Modification of terms of local cooperation to allow for 
full Federal funding of Wilkerson Creek and Coinjock 
Bridges. 
Mitigation of damages caused by north jetty at 
Masonboro Inlet. 
An 8-foot channel 150 feet wide through Carolina Beach 
Inlet to the Intracoastal Waterway. 
An 8-foot channel 150 feet wide from the gorge in 
Bogue Inlet through the ocean bar. 
Modification of terms of local cooperation to allow for full 
Federal funding of Core Creek, Hobucken, and Fairfield 
Bridges. 
BEAUFORT HARBOR, N. C. (See Section 3 of text) 
A 9-foot channel 200 feet wide through Bulkhead Channel 
to Beaufort; a 6-foot channel 100 feet wide to North River 
and Core Sound; and construct jetties on Shackleford 
Point. 
Repairs to Fort Macon jetties and additional jetties and 
shore protection. 
Bulkhead across Bird Shoal. 
Increase in depth to 12 feet in Bulkhead Channel, Gallants 
Channel, and in front of Beaufort. 
Increase in width and length of basin in front of Beaufort, 
all to 12 feet deep. 
Increase in depth to 12 feet and in width to 100 feet in 
Taylors Creek; transfer to Beaufort Harbor project. 
Channels 15 feet deep, 100 feet wide in Bulkhead, Gallants 
and Taylors Creek channels, and through turning basin in 
front of Beaufort; and harbor of refuge in Town Creek, 12 
feet deep, 400 feet wide, and 900 feet long connected to 
Gallants Channel by channel 12 feet deep, 150 feet wide, 
and 1,400 feet long. 
A channel 14 feet deep, 70 feet wide, and 1,900 feet long, 
from Bulkhead Channel to a turning basin 14 feet deep, 
150 feet wide, and 300 feet long near the upper end of 
Morgan Creek. 
SILVER LAKE HARBOR, N. C. (See Section 14 of text) 
Entrance channel, 5 feet deep and 50 feet wide, from 
Pamlico Sound to the 3-foot contour in the lake, and training 
wall at entrance. 
Channel, 10 feet deep, and anchorage basin of same depth, 
100 feet wide across Big Foot Slough and 60 feet wide in 
entrance. 
Basin depth of 12 feet in Silver Lake Harbor; channels 12 
feet deep, 150 feet wide, in Teaches Hole and Big Foot 
Slough Channels and across Bluff Shoal; entrance channel, 
same depth, 60 feet wide; and training wall on south side of 
entrance channel. 
WATERWAY CONNECTING PAMLICO SOUND AND 
BEAUFORT HARBOR, N. C. (See Section 16 of text) 
A 7-foot channel 75 feet wide from Pamlico Sound to 
Beaufort Harbor via Wainright Channel. 
A 7-foot channel 75 feet wide to Atlantic. 
Channels 7 feet deep, 75 feet wide, at east and west 
ends of Harkers Island and side channel 5 feet deep, 75 
feet wide, with basin 150 by 130 feet, same depth, at Davis. 
Documents 
H. D. 597, 94th Cong., 2d sess. 
Approved by OCE Oct. 2, 1980 
Detailed Project Report 
June 1980 
Detailed Project Report 
May 1983 
Annual Report, 1881, p. 1013 
Specified in act. 
Rivers and Harbors Committee 
Doc. 8, 68th Cong., 2d sess.' 
H. D. 776, 69th Cong., 2d sess.1 
H. D. 334, 76th Cong., 1st sess.' 
H. D. 111, 81st Cong., 1st sess.' 
Detailed Project Report 
April 1965 
Detailed Project Report 
June 1983 
Rivers and Harbors Committee 
Doc. 3, 70th Cong., 1st sess. 
H. D. 325, 76th Cong., 1st sess.' 
Detailed Project Report 
July 9, 1965 
H. D. 485, 72d Cong., 2d sess.' 
Rivers and Harbors Committee 
Doc. 92, 74th Cong., 2d sess.' 
H. D. 99, 77th Cong., 1st sess.'

WILMINGTON, N. C., DISTRICT 
TABLE 6-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 2, 1945 A 7-foot side channel 75 feet wide, with basin 200 feet by S. D. 247, 77th Cong., 2d sess.' 
500 feet, same depth, at Sealevel. 
May 17, 1950 A 6-foot side channel 60 feet wide, with basin 100 feet by H. D. 68, 81st Cong., 1st sess.' 
about 600 feet, same depth, at Marshallberg. 
July 11, 1963, A side channel 7 feet deep, 70 feet wide to local harbor at Detailed Project Report 
sec. 107 Cedar Island and an access channel 6 feet deep, 60 feet Dec. 12, 1962 
July 14, 1960 wide and about 400 feet long to a basin same depth, 60 by 
100 feet. 
September 22, 1967, An entrance channel 6 feet deep, 60 feet wide, from Back Detailed Project Report 
sec. 107 Sound to harbor of refuge 120 by 250 feet, same depth, at March 13, 1967 
July 14, 1960 west end of Harkers Island in Brook Creek. 
February 17, 1969, A channel 7 feet deep, 70 feet wide, from existing side Detailed Project Report 
sec. 107 channel at Atlantic to a basin 600 by 180 feet, same depth, Dec. 21, 1967 
July 14, 1960 with a breakwater, between mouth of Little Port Brook 
and White Point. 
April 3, 1975, Deepening the existing 5-foot channel and basin at Davis Detailed Project Report 
sec. 107 to 7 feet. Feb. 8, 1974 
July 14, 19601'0 
1. Contains latest published maps. 
2. Public Law No. 443, 72d Cong. 
3. Permanent Appropriations Repeal Act. 
4. Tidal lock in land cut between Myrtle Sound and Cape 
Fear River, deauthorized September 23, 1986, under authority 
of Sec. 12, PL 93-251. 
5. Deauthorized August 5, 1977 under authority of Sec. 
12, PL 93-251. 
6. A 12-foot by 90-foot channel in New River from 
Intracoastal Waterway to and including a basin at Jacksonville, 
N. C. 
7. Jetties on each side of Masonboro Inlet. 
8. A 6-foot by 50-foot channel provided under Section 3, 
River and Harbor Act of March 2, 1945; 12-foot by 90-foot project 
deauthorized November 17, 1986 under authority of Sec. 
1002, PL 99-662. 
9. Included in the Public Works Administration 
Program, Jan. 3, 1934. 
10. Deauthorized by the Chief of Engineers March 31, 
1982.
11. Deauthorized January 1, 1990, under authority of Sec. 
1001(b) (1), PL 99-662. 
6-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 6-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Project Report for Construction Maintenance 
Aquatic Plant Control' 
(R & H Act of 1958 and 1962) 1969 70,664 - 
Atlantic Beach Channels, N.C. 1990 18,501 232,019 
Avon Harbor, N. C.1 1986 74,096 440,364 
Bay River, N. C.' 1950 44,382 49,627 
Belhaven Harbor, N. C. ' 1989 126,687 376,401 
Black River, N. C. 1969 12,358 124,846 
Cashie River, N. C. 1950 40,403 15,905 
Channel Connecting Thoroughfare Bay 
with Cedar Bay, N. C.' 1975 69,610 25,615 
Channel from Pamlico Sound to Rodanthe, N. C.' 1975 42,029 5,685 
Chowan River, N. C. 1950 - - 
Contentnea Creek, N. C.' 1941 64,395 32,247 
Edenton Harbor, N. C.' 1960 73,750 47,642 
Fishing Creek, N. C.' 1922 22,715 8,633 
Knobb's Creek, N. C.', 2 19613 80,500 48,969 
Mackay Creek, N. C.' 19383 13,375 6,273 
Neuse River, N. C.' 1982 477,223 s 332,107 
Newbegun Creek, N. C. 19283 4,802 247 
Northeast Cape Fear River, N. C.' 1950 10,688 61,139 
Oracoke Inlet, N. C. 1991 346,240 946,110 
Pembroke Creek, N. C. 1976 60,000 - 
Perquimans River, N. C.' 19103 13,750 414 
Roanoke River, N. C.' 1989 404,584 572,409 
Scuppernong River, N. C.' 1950 81,164 80,682 
Smith's Creek (Pamlico County), N. C. ' 1989 113,273 52,945 
Smiths Creek (Wilmington), N. C.' 1950 8,507 18 
South River, N. C.' 1936 12,452 23,686 
Swift Creek, N. C.' 1940 1,600 5,422 
Trent River, N. C.', ' 1968 115,199 143,579 
Wallace Channel, Pamlico Sound, N. C. 1965 132,834 85,299 
Waterway - Norfolk, Va. to Sounds of N. C. 1976 751,196 2,893,812 
Waterway Connecting Swanquarter 
Bay with Deep Bay, N. C. 1984 911,099 182,725 
Wrights Creek, N. C.' 1984 68,325 166,602 
1. Completed. 
2. Transferred from Norfolk District (FY 1970); Meherrin 
River, N. C., Transferred to Norfolk District. 
3. Report of Norfolk District. 
4. 8-foot modification deauthorized August 5, 1977, under 
authority of Sec. 12, PL 93-251. 
5. Includes $1,959 refund to local interests on Dawson 
Creek, N. C. 
6-26

WILMINGTON, N. C., DISTRICT 
OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
TABLE 6-D 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Fort Fisher and Vicinity, N. C. 1984 490,000 - 
Fort Macon Park, N. C.' 1973 620,000 - 
1. Uncompleted portion of project was deauthorized 
November 17, 1986, under authority of Sec. 1002, PL 99-662. 
6-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 6-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Ararat River, Mount Airy, N.C.' 
Black River, Harnett County, N. C.' 
Broad Creek, Beaufort County, N. C.' 
Brunswick County Beaches, N. C. 
(Cape Fear to North Carolina - 
South Carolina State Line)" 
Conetoe Creek, N. C.' 
Contentnea Creek, N. C.' 
Core Creek, N. C.' 
Dan River, Madison Wastewater Treatment Plant, 
N. C.' 
Deep Creek, Edgecombe County, N. C.' 
Ellerbe Creek, Durham County, N. C.' 
Ellis Swamp, Gates County, N. C.' 
Filberts Creek, N. C.' 
Gapway Swamp, N. C. & S. C.','0 
Gardners Creek, N. C.' 
Genoa Sewer Facility, Wayne County, N. C.' 
Goldsboro, Neuse River, N. C. 
Howards Mill Lake, N. C.' 2 
Joyce Creek, Camden County, N. C.' 
Leesville, Va.' 
Leith's Creek, Scotland County, N. C.', '3 
Lick Run, Roanoke, Va.' 
Little Rockfish Creek, Hope Mills, N. C.' 
Little Sugar Creek, Charlotte, N. C.', '� 
New River, N. C.' 
New River, Onslow County, N. C.' 
Northeast Cape Fear River, N. C.' 
Old Field Swamp, N. C.','0 
Pantego Creek and Cucklers Creek, N. C. 
Pasquotank River, N. C. 
Perquimans River, N. C.' 
Pungo Creek, N. C.' 
Pungo River, N. C.' 
Reddies River Lake, N. C.' 3 
Roaring River Lake, N. C.'3 
Simmons Bay, N. C.'0 
South Creek, N. C.' 
Stuart, Va.' 
Swift Creek, Pitt and Craven Counties, N. C.' 
Tar River, N. C. 
Tar River, N. C.' 
Tar River and tributaries, N. C.' 
Tar River, Princeville, N. C. 
Trent River, N. C.' 
Waccamaw River & Seven Creeks, N.C. & S.C.','0 
White Oak Dike, Bladen and Pender 
Counties, N. C.' 
Wrightsville Beach, N. C. 
1987 
1984 
1972 
1976 
1960 
1939-1943 & 1958 
1965 
1989 
1984 
1963 
1971 
1970 
1969 
1972 
1985 
1984 
1980 
1984 
1989 
1982 
1974 
1978 
1979 
1950 & 1956 
1972 
1961 
1969 
1963 
1960 
1961 
1972 
1971 
1980 
1978 
1963 
1971 
1989 
1966 
1964 
1947 
1943 
1967 
1953 
1961 
1963 
1991 
1. Project authorized by Chief of Engineers under special 
continuing authority. 
2. Includes $17,356 refund to local interests. 
3. Adjusted to reflect actual cost. 
4. Includes $3,081 refund to local interests. 
5. Includes $116,508 refund to local interests. 
6. Includes $1,519 refund to local interests. 
7. Includes $387 refund to local interests. 6-: 
8. Includes $338 refund to local interests. 
9. Adjusted $3,000 to include preauthorization cost prior to 
FY 1960. 
10. Transferred from Charleston District, FY 1980. 
11. Reclassified to inactive category February 3, 1976. 
12. Reclassified to deferred category October 2, 1980. 
13. Transferred from Charleston District, FY 1984. 
28 14. Includes $1,057 refund to local interests. 
15. Includes $61,585 refund to local interests. 
4,901,854 
475,574 
283,846 
572,114s 
29,867 
50,889 
236,223s 
175,315 
394,055 
223,413 
138,1176 
37,7773 
374,005 
54,5978 
167,800 
50,430 
698,400 
606,189'" 
367,755 
430,151 
1,280,317 
113,657 
763,022 
51,896 
580,977 
95,873 
86,600 
517,948 
80,931 
6,366 
582,270 
296,6022,3 
985,800 
370,000 
186,435 
194,3677 
2,220,440 
611,096 
81,266 
18,624 
22,660 
390,249 
64,769 
67,821 
214,286 
4,843,284's 
-
-
-
- 
623,687 
61,473

WILMINGTON, N. C., DISTRICT 
TABLE 6-G DEAUTHORIZED PROJECTS 
For Last Full Report Federal Contributed 
See Annual Report Date Funds Funds 
Project For Deauthorized Expended Expended 
Adkin Branch, N. C. 
AIWW - Mooring Basins 
AIWW - New River Onslow 
County, N. C. 
AIWW - Peltier Creek, 
12-foot project 
AIWW - Tidal Lock in Snows Cut 
Bodie Island, N. C. 
Brunswick County Beaches - 
Long Beach Portion, N. C. 
- Berm 
Cape Lookout, N. C. 
Conoho Creek, N. C. 
Contentnea Creek, N. C. 
Davis, N. C. 
Fort Macon State Park, 
N. C., Remaining Work 
Harbor of Refuge, N. C. 
Hominy Swamp, N. C. 
Hyde County Dike, N. C. 
MacKay Creek, N. C. 
Mann's Harbor, N. C. 
Mill Creek, N. C. 
Mocassin Swamp, N. C. 
Morehead City Harbor, N. C., 
Jetties at Beaufort Inlet 
Moyock Creek, N. C. 
Nahunta Swamp, N. C. 
Neuse River, N. C. 
Neuse River Barrier, N. C. 
Neuse River, 300 ft.-wide 
channel in front of 
New Bern 
North River Dike, N. C. 
Ocracoke Inlet Jetty, N. C. 
Ocracoke Island, N. C. 
Roanoke River, 50 mile long 
Channel from Palmyra 
Landing to Weldon 
Rockfish Creek, N. C. 
Scuppernong River, N. C. 
Six Runs Creek, N. C. 
Sweetwater Creek, N. C. 
Thoroughfare Swamp, N. C. 
Topsail Beach and 
Surf City, N. C. 
Tranters Creek, N. C. 
Trent River, Basins and 
Access Channels at 
New Bern, N. C. 
Wilmington Harbor Widening 
and Deepening, N. C. 
1. Deauthorized under authority of Sec. 12, PL 93-251. 
2. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 205 of the 1948 FC Act, as 
amended. 
3. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 208 of the 1954 Flood Control 
Act. 
4. Deauthorized pursuant to the continuing authority provided 
the Chief of Engineers under Sec. 107 of the R&H Act of 1960 
as amended. 
5. Deauthorized under authority of Sec. 1002, PL 99-662. 
6. Deauthorized under authority of Sec. 1001(b)(1), PL 99-662. 
7. Cost-to-date included in remaining authorized portion of 
project (Engineering and Design only). 
6-29 
1982 
None 
1990 
None 
None 
None 
1990 
None 
1974 
1972 
1982 
1973 
1934 
1973 
None 
1976 
1973 
1973 
1973 
1986 
1973 
1973 
None 
None 
None 
None 
1986 
1975 
1983 
1976 
1987 
1971 
1973 
1976 
None 
1974 
None 
1990 
8 Sept. 812 
5 Aug. 771 
1 Jan. 906 
17 Nov. 86 s 
23 Sept. 86' 
5 Aug. 77' 
1 Jan. 906 
5 Aug. 77' 
31 Mar. 782 
31 Mar. 783 
31 Mar. 82' 
17 Nov. 86 s 
1 Nov. 811 
31 Mar. 782 
5 Aug. 77' 
31 Mar. 782 
31 Mar. 78' 
31 Mar. 782 
31 Mar. 782 
17 Nov. 86 s 
31 Mar. 782 
31 Mar. 782 
31 Mar. 78' 
5 Aug. 77' 
5 Aug. 77' 
5 Aug. 77' 
17 Nov. 86 s 
17 Nov. 865 
17 Nov. 865 
31 Mar. 782 
20 Apr. 882 
31 Mar. 782 
31 Mar. 782 
31 Mar. 782 
5 Aug. 77' 
11 Jan. 852 
5 Aug. 77' 
1 Jan. 906 
219,477 
- 
79,782 
4,250 
25,419 
1,396,653 
107,472 
130,900 
7,265 
116,395 
36,680 
64,416 
65,673 
30,911 
- 
129,592 
- 
157,721 
234,032 
64,977 
64,584 
132,767 
139,339 
13 93

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 6-H RECONNAISSANCE AND CONDITION SURVEYS 
Project Date Survey Conducted 
None 
NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public Law 86-645 Ipreauthorization) 
TABLE 6-I 
Study Identification Fiscal Period Cost 
Shallotte Inlet, N. C. 55,036 
Wilmington Harbor, N. C., Passing Lane3 25,022' 
Wilmington Harbor, N. C., Turns and Bends3 16,4672 
1. Includes $8,229 contributed funds. 
2. Includes $12,502 contributed funds. 
3. Combined into one project - Wilmington Harbor, Channel 
Widening, N. C. 
6-30

TABLE 6-J DAMS AND RESERVOIRS 
See Miles Height Reservoir Power Estimated 
Section Project Name Nearest City River Above of Type Capacity Development Construc- Cost Lands Total 
in Text Mouth Dam (ft) (acre-feet) (kilowatts) tion and Damages' 
18. Cape Fear 
River Basin, 
N.C. 
20. Neuse River 
Basin, N.C. 
26. 
29. 
Yadkin River 
Basin, N.C.&S.C. 
Roanoke River 
Basin, Va. and 
N.C. 
B. Everett Jordan
2 
Howards Mill
2 . 14 
Randleman2 
Small reservoirs 
Falls 2 
Wilson Mills 
Beulahtown 
Bakers Mills 
Little Buffalo 
Buckhorn 
Wiggins Mill 
Stantonsburg 
Great Swamp 
Black Creek 
Aycock Swamp 
Hillsboro 
Orange 
W. Kerr Scott, N.C. 
John H. Kerr, Va., and 
N.C.
2 
Philpott, Va.
2 
Gaston, Va. and N.C.
6 
Roanoke Rapids, N.C.
7 
Smith Mountain, Va.
8 
Leesville, Va. 
9 
Taber, Va. 
Melrose, Va. 
Randolph, Va. 
Stuart, Va. and N.C. 
Schoolfield, Va. and N.C. 
Moncure, N.C. 
Carthage, N.C. 
Randleman, N.C. 
Falls, N.C. 
Wilson Mills, N.C. 
Kenly, N.C. 
Princeton, N.C. 
Kenly, N.C. 
Wilson, N.C. 
Wilson, N.C. 
Stantonsburg, N.C. 
Fremont. N.C. 
Wilson, N.C. 
Fremont N.C. 
Durham, N.C. 
Durham, N.C. 
Wilkesboro, N.C. 
Boydton, Va. 
Bassett, Va. 
Roanoke Rapids, N.C. 
Roanoke Rapids, N.C. 
Altavista, Va. 
Altavista, Va. 
Altavista, Va. 
Brookneal, Va. 
Chase City, Va. 
Spray, N.C. 
Danville, Va. 
Haw 
Deep 
Deep 
Various 
Neuse 
Neuse 
Little 
Little 
Little Buffalo Creek 
Contentnea Creek 
Contentnea Creek 
Tisnot Swamp 
Great Swamp 
Black Creek 
Aycock Swamp 
Eno 
Little 
Yadkin Pee Dee 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
Roanoke 
4.3 112 
55.0 106 
85.0 110 
- 20 to 70 + 
- 92 
- 81 
- 50 
- 53 
- 51 
- 63 
- 42 
- 36 
- 39 
- 33 
- 37 
- 136 
- 107 
404.0 148 
E
E
E 
E
E
CG,E 
E
E
E
E
E
E
E
E
E
E
E
E 
753,500 
233,000 
108,000 
923,000 
374,450 
201,000 
81,000 
36,000 
13,000 
119,000 
35,000 
48,000 
18,000 
17,000 
7,000 
123,000 
57,000 
153,000 
- 87,795,000 
- 18.874,000 
- 62,300,000 
- 88,564,000 
5,749,343 3,360,657 
178.7 144 CG.E 2,808.000 204,000 67,529,000 24,521,000 92,050,000' 
336.2 
144.9 
137.0 
314.2 
293.7 
275.0 
262.9 
227.8 
297.2 
265.9 
220 
108 
75 
244 
95 
54 
110 
147 
138 
126 
CG 
1 1 
CG,E 
CG 
CG 
CG,E 
CG 
CG.E 
CG,E 
E
CG,E 
249,800 
432,000 
59,300 
825,000 
76,900 
34,000 
120,000 
350,000 
163,000 
248,000 
14,000 
54,000 
83,000 
41,000 
20,000 
12,000 
43,000 
48,000 
15,000 
80,000 
13,933,000 
27,000,000 
31,300,000 
28,000,000 
9,100,000 
8,000,000 
17,700,000 
22,100,000 
9,000,000 
27,800,000 
1. Includes highway, railroad, and utility relocations. 
2. For details, see individual report. 
3. Includes $3,700,000 presently allocated to water supply to be reimbursed in the future by 
local interests and $100,000 cash contribution for construction of ranger security buildings. 
4. Includes $13,900,000 presently allocated to water supply and $20,600,000 recreation and fish 
and wildlife to be reimbursed in the future by local interests. 
5. Exclusive of transmission lines. 
6. Construction completed in 1963 by Virginia Electric and Power Co. 
7. Based on modified plan developed in fiscal year 1949. Construction completed June 1955 by 
Virginia Electric and Power Co. 
8. Construction completed in February 1966 by Appalachian Power Co. 
9. Construction completed in June 1963 by Appalachian Power Co. 
10. Includes cost of earth dam on Whipping Creek. 
11. Authorizing legislation provided for earth dam; concrete gravity dam constructed. 
12. Includes $1,600,000 presently allocated to recreation and fish and wildlife. 
13. Includes $74,058,000 presently allocated to water supply, $8,646,000 allocated to recreation 
and $8296,000 to flood control to be paid by local interests during construction. 
14. Reclassified to the deferred category October 2, 1980. 
Key 
E - Earth 
C('G - Concrete Gravity 
58,405,000 
14,726,000 
61,700,000 
94,436,000 
164,200,000* 
33,600,000'" 
124,000,000' 
38,454,000 
183,000,000' 
13,000,000 
9,300,000 
6,600,000 
1,100,000 
17,300,000 
6,700.000 
5,100,000 
1,800,000 
1,500,000 
550,000 
8.100,000 
3,500,000 
9,110,000 
1,157,000 
3,500,000 
800,000 
3,800,000 
1.000,000 
1,700,000 
6,0001,000 
4,700,000 
1,100,000 
6,400,000 
15,090,000 
30,500,000 
32,100,000 
31.800,000 
10,100,000 
9,700,000 
23,700,000'* 
26,800,000 
10.100,000 
36,000,000 
r
zy
z
z
A
d
CS) 
tra

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, 
Public Law 858, 80th Congress, as amended 
TABLE 6-K (Preauthorizationl 
Study Identification Fiscal Period Cost 
Adkin Branch, Kinston, N. C. 39,626 
Bear Creek, Robbins, N. C. 6,471 
Blackberry Creek, Henry County, VA. 10,753 
Brake Branch, Montgomery County, VA. 3,333 
Catfish Branch, Kingston, N. C. 6,573 
Crooked Creek, Union County, N. C. 980 
Cross Creek, Fayetteville, N. C. 53,923 
Cumberland County Streams, N. C. 5,577 
Danville, VA. 27,643 
Glade Creek, Roanoke County and Vinton, VA 9,877 
Great Coharie Creek, N. C. 50,468 
Hominy Swamp, Wilson, N. C. 14,506 
Linville River, Avery County, N. C. 65,947 
Little Cross Creek, Fayetteville, N. C. 52,301 
Mason Creek, Franklin County, VA. 3,000 
Mill Creek, Catawba River, Old Fort, N. C. 7,784 
Moravian Creek, Wilkesboro, N. C. 69,544 
6-32

CHARLESTON, S.C. DISTRICT *
This district comprises all of South Carolina (except local 
watersheds draining into the Savannah River). It 
embraces the drainage basins tributary to the Atlantic Ocean 
S.C., DISTRICT* 
between Little River and Port Royal Sound, except 
watersheds of Mackey and Skull Creeks, and excluding 
Hilton Head Island. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control, SC .............. 7-1 
2. Atlantic Intracoastal Waterway Between 
Norfolk, VA and St. Johns River, FL ....... 7-2 
3. Brookgreen Gardens, SC ................ 7-2 
4. Charleston Harbor, SC ................. 7-2 
5. Charleston Harbor Rediversion 
(Fish Lift), SC ........................ 7-3 
6. Cooper River, Charleston Harbor, SC ...... 7-4 
7. Cooper River Seismic Modification, SC ..... .7-4 
8. Folly River, SC ....................... 7-4 
9. Georgetown Harbor, SC ................ 7-5 
10. Jeremy Creek, SC ..................... 7-5 
11. Little River Inlet, NC and SC ............. .7-6 
12. Murrells Inlet, SC ..................... 7-6 
13. Port Royal Harbor, SC .................. 7-7 
14. Shipyard River, SC .................... 7-7 
15. Town Creek, SC ...................... 7-7 
16. Reconnaissance and Condition Surveys ...... 7-8 
17. Other Authorized Navigation Reports ....... .7-8 
18. Navigation Work Under Special 
Authorization ........................ 7-8 
Beach Erosion 
19. Folly Beach, SC ....................... 
20. Other Authorized Beach Erosion 
Control Projects ...................... 
21. Beach Erosion Work Under Special 
Authorization ........................ 
Flood Control 
22. Socastee Creek, SC .................... 
7-8 
7-8 
7-8 
7-8 
23. Inspection of Completed Flood 
Control Projects ...................... 7-9 
24. Other Authorized Flood Control 
Projects ............................. 7-9 
25. Flood Control Work Under Special 
Authorization ........................ 7-9 
Miscellaneous 
26. Streambank Erosion Under Special 
Authorization ........................ 7-9 
General Investigations 
27. Active Investigations ................... 7-9 
Tables 
Table 7-A Cost and Financial Statement ........ 7-10 
Table 7-B Authorizing Legislation ............ 7-13 
Table 7-C Other Authorized Navigation Projects .. 7-17 
Table 7-D Navigation Work Under Special 
Authorization ................... 7-17 
Table 7-E Other Authorized Beach Erosion 
Projects ......................... 7-17 
Table 7-F Other Authorized Flood Control 
Projects ........................ 7-18 
Table 7-G Flood Control Work Under Special 
Authorization ................... 7-18 
Table 7-H Other Authorized Streambank 
Erosion Projects ................. 7-19 
Table 7-I Active General Investigations ........ 7-19 
*All costs and financial statements for projects are listed at 
the end of this chapter. All other tables are referenced in 
text and also appear at the end of this chapter. 
Navigation 
1. AQUATIC PLANT CONTROL, SC 
Location. The project includes all public waters in the 
State of South Carolina. 
Existing Project. The project provides for the control 
and progressive eradication of noxious aquatic plant growths 
from public waters in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, and public health. 
Local Cooperation. Local interests must agree to 
hold the United States free from damages that may occur 
from operations performed in connection with this project 
and contribute 50 percent of the total cost. The South 
Carolina Water Resources Commission is designated as the 
7-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
State's lead agency for aquatic plant management and meets 
local interest requirements. 
Operations and results during fiscal year. 
Aquatic plants now infest approximately 39,000 acres, with 
the worst infestations occurring in Lake Marion and Lake 
Moultrie. During FY 92, 4,400 acres of aquatic plants in 24 
water bodies were treated with herbicides. Grass carp 
(100,000) were purchased and stocked in Lake Marion to 
control aquatic plants in approximately 12,000 acres. 
The total cost of work performed in FY 92 was $1,078,222. 
Condition at end of fiscal year. The project is 
ongoing. Federal costs for the project to date have been 
$6,326,548 for new work. 
2. ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA AND 
ST. JOHNS RIVER, FL 
(CHARLESTON DISTRICT) 
Location. The project starts near Little River at the 
North Carolina-South Carolina state line and extends 
generally south along the coast of South Carolina 62 miles to 
Winyah Bay; thence 63.5 miles to Charleston; thence 84.5 
miles to and including Port Royal Sound; a total of 210 
miles. (See National Ocean Survey Charts Nos. 11513, 
11521, 11531, 11534, and 11535.) 
Previous projects. For further details see page 613 
of Annual Report for 1932. 
Existing project. The project provides for a waterway 
twelve feet deep and not less than 90 feet wide with a branch 
channel of the same dimensions to McClellanville and 
construction of three bridges crossing the waterway in Horry 
County, South Carolina. (See table at end of chapter for acts 
authorizing existing project.) 
Local cooperation. None required. 
Terminal facilities. There are rail-water terminals at 
Georgetown, Charleston, Johns Island, and Port Royal and 
numerous open-pile wharves mostly for shipping agricultural 
products, fish, oysters, pulpwood, wood products, and 
petroleum products. Marinas are located at convenient 
intervals along the waterway where limited supplies and 
repair facilities are available for both commercial vessels and 
pleasure craft. Facilities are considered adequate for existing 
commerce and recreation requirements. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Maintenance dredging was 
performed by pipeline dredge in the AIWW from the Winyah 
Bay to Charleston area during February 1992 - August 1992, 
removing 1,217,116 cubic yards of material at a cost of 
$1,727,785. The mosquito abatement control contract costs 
were $77,350. The cost of operating the Snagboat Snell in 
the Myrtle Beach area was $324,040. Costs of $397,361 were 
incurred for contract dike maintenance. Condition and 
operation studies, inspections and reports, real estate, project 
operations management, lands and damages, water control 
management, planning, engineering and design, and 
supervision and administrative costs were $533,208. 
Condition at end of fiscal year. Existing project 
was completed in 1940; three bridges were completed in 
1936. Federal costs of existing project to date have been 
$7,345,888 for new work and $56,367,447 for maintenance, for 
a total of $63,713,335. 
3. BROOKGREEN GARDENS, SC 
Location. The project is located on the western 
boundary of Brookgreen Gardens near Murrells Inlet in 
Georgetown County, SC. 
Existing project. The project provides for a 3,600 
foot canal with a 30 foot bottom width maintained to a depth 
of four feet mlw. (See table as the end of the chapter for 
acts authorizing the existing project.) 
Local cooperation. None required. 
Operations and results during the fiscal year. 
New Work: None. Maintenance: Easement acquisition 
costs for the year were $1,017. 
Condition at end of fiscal year. The existing 
project was completed in August 1990. Federal costs of 
existing project to date have been $94,700 for new work and 
$1,017 for maintenance, a total of $95,717. 
4. CHARLESTON HARBOR, SC 
Location. The harbor is located on the coast of South 
Carolina about 15 miles south of the midpoint of the 
coastline, 50 miles southwest of Winyah Bay, SC, and 80 
miles northeast of the mouth of Savannah River. (See 
National Ocean Survey Charts Nos. 11521 and 11524.) 
Previous projects. For further details see page 425 of 
the Annual Report for 1962; page 1808 of the Annual Report 
for 1915; page 579 of the Annual Report for 1926; and page 
562 of the Annual Report for 1938. 
Existing project. The project as authorized by the 
1986 Water Resources Development Act provides for 
deepening of the 35-foot channel to 40 feet (42 feet in the 
ocean bar and entrance channel) from the 42-foot ocean 
contour to Goose Creek, a total distance of 27.1 miles, 
construction of one turning basin, modification of existing 
turning basins, deepening and modification of the anchorage 
7-2

CHARLESTON, SOUTH CAROLINA DISTRICT* 
basin, deepening Shipyard River to 38 feet, maintaining the 
Wando River Channel to 35 feet at federal expense and the 
deepening of this channel to 40 feet. (See table at end of 
chapter for acts authorizing existing project.) 
Local cooperation. Local interests have fully 
complied with their responsibility to date. 
Terminal facilities. Piers and slips extend for about 
one mile along the eastern waterfront of the City of 
Charleston with an additional mile of marginal wharves. The 
South Carolina State Ports Authority operates eight piers for 
fruit, wood, cold storage facilities and general cargo, a grain 
elevator and a beltline railway which serves the entire 
Cooper River water-front. Modern facilities are also at 
wharves of seven major petroleum companies including 
storage tank farms. Modern facilities for marine repairs and 
servicing are available at Detyens Shipyard, located 
approximately ten miles northeast of Charleston on the 
Wando River. The U. S. Navy Department has modern 
facilities for maintenance of naval vessels including 
nuclear-powered submarines. Loading docks and storage 
areas for missile-carrying type vessels have also been 
constructed and are being operated by the U. S. Navy. For 
further details see Port Series No. 13, 1980, Corps of 
Engineers. 
Operations and results during fiscal year. New 
Work: All new work is cost shared 75/25, 
Federal/non-Federal respectively. Contract dredging was 
performed: (a) by hopper/clamshell/pipeline dredges in the 
Entrance Channel during August 1991 - August 1992, 
removing 1,125,867 cubic yards of material, at a cost of 
$11,874,210, (b) by pipeline dredge in the Ordnance to Navy 
Yard Reach area during August 1991 - November 1991, 
removing 127,766 cubic yds of material, at a cost of -$13,488 
which reflects adjustments made to accrued earnings for 
work performed in FY 91, (c) in the Town to Tidewater 
Reach area during September 1991- February 1992, at a cost 
of -$2,000 which reflects adjustments made to accrued 
earnings for work performed in FY 91. Engineering and 
design and construction management costs were $411,567, 
and $511,562, respectively. Federal costs for the project were 
$9,586,388. Maintenance: Maintenance dredging was 
performed: (a) by hopper/clamshell/pipeline dredges in the 
Entrance Channel during August 1991 - August 1992, 
removing 1,039,371 cubic yards of material at a cost of 
$2,152,705, (b) by pipeline dredge in the Anchorage Basin 
from September 1991 - November 1991, removing 867,830 
cubic yards of material at a cost of $597,969, (c) by pipeline 
dredge in the Navy Yard to Ordnance Reach area during 
August 1991 - November 1991, removing 318,934 cubic yards 
of material at a cost of $15,308 (Note: The low cost for this 
year reflects an adjustment made for FY 91 costs. 
This figure does not reflect true cubic yards dredging costs.), 
(d) by pipeline dredge in the Tidewater Reach to Ordnance 
Reach area during August 1992, removing 162,000 cubic 
yards of material at a cost of $589,780 (Note: The high cost 
for this year reflects $400,000 for work performed in 
September 1991. This figure does not reflect true cubic 
yards dredging costs.), (e) in the Lower Charleston Harbor 
area during September 1992, at a cost of -$39,500 which 
reflects adjustments made to accrued earning for work 
performed in FY 91, for a total contract cost of $3,316,262. 
Removal of wrecks costs were $920. Condition and 
operation studies, water control management, natural 
resource management, inspections and reports, project 
operations management, lands and damages, planning, 
engineering and design, and construction management costs 
were $673,689. 
Condition at end of fiscal year. At the end of FY 
92, physical construction of the project was 92% complete. 
Federal costs through FY 92 for the existing project have 
been $34,777,673 for new work and $110,711,900 for 
maintenance. 
5. CHARLESTON HARBOR 
REDIVERSION (FISH LIFI), SC 
Location. Cooper River is located in Charleston and 
Berkeley Counties, SC, and empties into the Atlantic Ocean 
at Charleston, SC. (See National Ocean Survey Charts Nos. 
11521 and 11524.) All works of improvement are in Berkeley 
County about 45 miles from Charleston, SC. 
Existing Project. The completed Cooper River, 
Charleston Harbor Project (See Section 6) resulted in 
significant reduction in the transfer of blueback herring into 
the Santee Cooper Lakes. The landlocked striped bass 
fishery, a major tourist attraction, is dependent on these fish 
for forage. A model study, completed in March 1992 at 
CEWES, was conducted to determine how the turbine 
discharge could be prevented from overwhelming the 
attractant flow through the fish lift, plus testing various 
operational and structural modifications to determine how 
best to improve fish passage. Design of the selected 
modification is scheduled for completion by November 1993. 
Construction is expected to be completed during FY 95. 
Monitoring of the fish lift operation for two years after 
modification will be required to gather and analyze data to 
be used to refine the operation of the fish lift and to ensure 
its effectiveness. 
Total estimated cost of the project is $4,825,000, all Federal. 
(See table at end of chapter for acts authorizing existing 
project.) 
Local Cooperation. None required. 
Operations and results during fiscal year. Funds 
of $213,182 were spent in FY 92 for model studies and 
coordination meetings with Federal and State resource 
agencies. 
7-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
6. COOPER RIVER, CHARLESTON 
HARBOR, SC 
Location. Cooper River is located in Charleston and 
Berkeley Counties, SC, and empties into the Atlantic Ocean 
at Charleston (See National Ocean Survey Charts Nos. 11521 
and 11524.) 
Existing project. The major cause of the shoaling 
problem in Charleston Harbor was the diversion of fresh 
water from the Santee River through Pinopolis Dam into the 
salt water of Charleston Harbor, which caused density 
currents which trapped sediments resulting in a phenomenal 
rate of deposition. The most practical solution of the shoaling 
problem was to redivert most of the Santee River waters 
above Pinopolis Dam back into the lower Santee River 
through a canal beginning at Lake Moultrie and extending to 
the Santee River in the vicinity of St. Stephen, South 
Carolina. The project for Cooper River, as authorized by the 
1968 River and Harbor Act, provided that the discharge 
through the existing Pinopolis Hydroplant be reduced to a 
flow which would not establish a density current in the 
harbor. This flow was estimated at 3,000 cubic feet per 
second (cfs) during the design phase of the project, but after 
operational tests this flow is estimated at 4,500 cfs. The 
excess water impounded in Lake Moultrie is being directed 
through a new canal above St. Stephen, South Carolina, to 
enter the Santee River at a point well below the Lake 
Marion Spillway (Wilson Dam). A new hydroelectric facility 
was constructed on the new canal at the edge of the swamp 
adjacent to the Santee River. This plant replaces those 
features made less effective at Pinopolis through curtailment 
of flows. The average flow of 11,000 cfs at the new 
powerplant, plus the 4,500 cfs average release planned for 
Pinopolis, approximates the historical average flow at 
Pinopolis. The three generators at the new plant are rated 
at 28,000 kilowatts each, for a total of 84,000 kilowatts. In 
the interest of fish and wildlife resources of the area, the 
project includes a herring lift at the new powerhouse site and 
a relocated fish hatchery. (See table at end of chapter for 
acts authorizing existing project.) 
Local cooperation. None required. 
Operations and results during fiscal year. New 
Work: Costs during FY 92 were $163 for construction 
management. Maintenance: Funds of $2,455,864 were spent 
for maintenance of completed work. 
Condition at end of fiscal year. Construction was 
initiated March 1977. The power-on-line date was March 
1985. The power plant, channels and canals, and attendant 
work was completed in FY 85. We have a open letter of 
credit with the SC Highway Department until they exercise 
option to initiate construction to widen the existing Highway 
52 bridge over the tailrace canal or until 28 May 2001. 
Federal costs for the existing project to date have been 
$196,874,134 for new work and $25,161,285 for maintenance, 
a total of $222,035,419. 
7. COOPER RIVER SEISMIC 
MODIFICATION, SC 
Location. The Cooper River Seismic Project is located 
in Berkeley County, South Carolina, about 50 miles north of 
Charleston, South Carolina. 
Existing project. The project provides for 
constructing three bolster sections totaling 4,500 feet along 
the downstream side of the dam and strengthening the 
foundation under the toe of the existing dam. The project 
calls for the placement of 1.25 million cubic yards of material 
in three sections which range in length from 700 to 2,200 feet 
and will be approximately the same elevation as the existing 
dam. (See table at end of chapter for acts authorizing 
existing project.) 
Current estimated cost of the project is $30,270,000, of 
which $29,500,000 is Federal and $770,000 is non-Federal. 
Local cooperation. Requirements are fully satisfied. 
Operations and results during fiscal year. New 
Work: FY 92 costs totalled $188,142 with $18,566 being used 
for planning, engineering and design, $94,213 for construction 
management, and $75,363 for the contract. 
Condition at end of fiscal year. Funds to initiate 
preconstruction, engineering and design were appropriated in 
FY 83 and funds to initiate construction were appropriated 
in FY 86. The project was accepted for beneficial occupancy 
on 14 September 1990 and the entire project was accepted by 
Santee Cooper on 9 December 1992. The only remaining 
issue is the resolution of one outstanding claim. Federal 
costs through FY 92 for the existing project have been 
$29,397,454. 
8. FOLLY RIVER, SC 
Location. The project begins in Folly River and Folly 
Creek north of the Town of Folly Beach and follows a 
southwesterly course into the Atlantic Ocean. (See National 
Ocean Survey Chart No. 11521.) 
Existing project. The project provides for an entrance 
channel, eleven feet deep by 100 feet wide extending from 
the Stono River one mile through the ocean bar; a channel 
within Folly River nine feet deep and 80 feet wide, extending 
three miles downstream from U. S. Highway 171 to the 
confluence of Folly and Stono Rivers; and a channel within 
Folly Creek nine feet deep by 80 feet wide extending three 
miles downstream from Highway 171 to the confluence with 
the Folly River. (See table at end of chapter for acts 
authorizing existing project.) 
7-4

CHARLESTON, SOUTH CAROLINA DISTRICT 
Local cooperation. None required. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Maintenance dredging was 
performed by pipeline dredge during July 1992 - August 
1992 removing 73,600 cubic yards of material, at a cost of 
$226,476. Condition and operations studies, water control 
management, planning, engineering and design, and 
supervision and administrative costs were $40,682. 
Condition at end of fiscal year. The existing 
project was completed in FY 79. Federal costs for the 
existing project to date have been $337,736 for new work and 
$3,146,891 for maintenance, a total of $3,484,627. 
9. GEORGETOWN HARBOR, SC 
Location. The harbor is located on the coast of South 
Carolina 50 miles northeast of Charleston Harbor and 90 
miles southwest of the entrance to Cape Fear River, North 
Carolina. (See National Ocean Survey Chart No. 11532) 
Previous projects. For further details see page 1806 
of Annual Report for 1915; page 549 of Annual Report for 
1938; and page 442 of Annual Report for 1944. 
Existing project. The authorizations provide for a 
channel 27 feet deep with varying widths of 600 feet to 400 
feet from the Atlantic Ocean to and including a turning basin 
at the U. S. Highway 17 bridge over Sampit River, with a 
side channel 2,400 feet long and not less than 200 feet wide 
leading to a turning basin at the upper end of the built-up 
portion of the city waterfront, a total of 17.9 miles. The 
project also provides for the continued maintenance to a 
depth of 18 feet and a width of 400 feet for the bypassed 
portion of Sampit River opposite the City of Georgetown. 
(See table at end of chapter for acts authorizing existing 
project.) 
Local cooperation. None required. 
Terminal facilities. Terminal facilities at the Port of 
Georgetown, suitable for oceangoing vessels, consist of one 
marginal concrete pier and one of creosote-timber 
construction. For intracoastal waterway traffic there are a 
number of smaller wharves and landings along the 
Georgetown waterfront on the old channel. For further 
details, see Port Series No. 13, 1980, Corps of Engineers. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Maintenance dredging was 
performed (a) in the Sampit River and Upper Winyah Bay 
area by pipeline dredge during September 1991 - August 
1992, removing 729,107 and 671,351 cubic yards of material, 
respectively, at a cost of $1,633,024, (b) in the Sampit River 
and Upper Winyah Bay area by pipeline dredge during 
September 1990 -January 1992 at a cost of $21,599. Contract 
dike management costs were $29,085. The mosquito 
abatement control contract costs were $8,542. Water control 
management, natural resource management, inspections and 
reports, condition and operation studies, project operations 
management, easement acquisition, planning, engineering and 
design and supervision and administrative costs were 
$584,329. Applied a credit of -$17,459 for funds received for 
disposal area user fees. 
Condition at end of fiscal year. The existing 
project was completed in 1951. The jetties were completed 
in 1903 - 1904. Federal costs for the existing project to date 
have been $4,615,903 for new work and $57,745,057 for 
maintenance, a total of $62,360,960. 
10. JEREMY CREEK, SC 
Location. Jeremy Creek is located at McClellanville, 
SC approximately 40 miles northeast of Charleston and 20 
miles southwest of Georgetown. (See National Ocean Survey 
Charts Nos. 11531 and 11518.) 
Existing project. The project provides for a turning 
basin twelve feet deep and 150 feet in diameter at the head 
of the previously existing Jeremy Creek navigation channel. 
The dredging of Jeremy Creek or "Side Channel to 
McClellanville" was authorized as a part of the channel from 
Charleston to McClellanville (or part of what is now the 
Atlantic Intracoastal Waterway) by the River and Harbor Act 
of 2 March 1907. 
Local cooperation. None required. 
Terminal facilities. There are three shrimping 
facilities, one oyster packing shed, a crabbing operation, an 
icehouse, a fuel dock and a public launching ramp located on 
Jeremy Creek. The commercial facilities are privately 
owned, but are open to all on an equal basis. The existing 
facilities are considered adequate for present and near future 
commerce. There are areas along the east bluff shore 
available for the expansion of existing facilities or the 
construction of new ones. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Maintenance dredging was 
performed by pipeline dredge from February 1992 - August 
1992 removing 6,139 cubic yards of material at a cost of 
$8,718. Condition and operations studies, water control 
management, inspections and reports, planning, engineering 
and design, and supervision and administrative costs were 
$4,121. 
Condition at end of fiscal year. Federal costs of 
existing project to date have been $49,987 for new work and 
$97,343 for maintenance, a total of $147,330. 
7-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
11. LITTLE RIVER INLET, NC AND SC 12. MURRELLS INLET, SC 
Location. The project is located near the North 
Carolina-South Carolina state line. Little River enters the 
Atlantic Ocean at Little River Inlet at the state line and 
affords the only connection between the Atlantic Intracoastal 
Waterway and the ocean along 68 miles of coastline from 
Shallotte, N. C. to Georgetown, S. C. (See National Ocean 
Survey Chart No. 11535.) 
Existing project. The project provides for an entrance 
channel twelve feet by 300 feet across the ocean bar; thence 
a ten by 90-foot inner channel to the Atlantic Intracoastal 
Waterway. The entrance channel is stabilized by jetties 
extending seaward 3,284 feet and 3,830 feet long on the east 
and west sides of the inlet, respectively. 
Emergency dredging on an annual basis was authorized by 
the Water Resources Act of 1974. Previous work was done 
under the authority of the River and Harbor Act of 1945, 
Section 3, P.L. 79-14. 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are eight marinas, 
numerous private docks, and several public boat ramps 
located in or near Little River. It is expected that existing 
facilities will expand and new ones will be added as demands 
for services exceed current capacity. 
Operations and results during fiscal year. New 
work: None. Maintenance: A 5-year monitoring program 
was initiated in 1981 to provide information for management 
of the project and to determine the effect of the project on 
nearby coastal areas. Charleston District (CESAC) collects 
the data and Coastal Engineering Research Center (CERC) 
performs data analysis and interpretation. Following 
conclusion of the initial 5-year monitoring plan (February 
1986), CERC presented results of their preliminary analysis 
to CESAC and CESAD at a meeting in Charleston on 
8 April 1986. The data indicated that coastal processes in 
the vicinity of the inlet have not reached an equilibrium 
condition and recommended continued monitoring at a 
reduced level. This effort is currently underway. Condition 
and operation studies, water control management, inspection 
and reports, project operations management, planning, 
engineering and design, and supervision and administrative 
costs were $80,840. 
Condition at end of fiscal year. The project was 
completed in FY 84. Federal costs for the existing project 
have been $17,037,428 for new work and $2,788,372 for 
maintenance, a total of $19,825,800. 
Location. The project is located on the coast of 
South Carolina, in Georgetown County, about 13 miles 
southwest of the City of Myrtle Beach. The inlet is the 
ocean entrance through a barrier beach to several tidal 
streams in the Murrells Inlet-Garden City estuarine area. 
(See National Ocean Survey Chart No. 11535.) 
Existing project. The project provides for an 
entrance channel twelve feet by 300 feet across the seaward 
bar; thence a ten by 90-foot inner channel to a turning basin 
at the old Army crashboat dock. The entrance channel is 
stabilized by ocean jetties extending seaward 3,445 feet and 
3,319 feet on the north and south sides of the inlet, 
respectively. The recreational project includes a walkway on 
the south jetty with access road and parking area. Emergency 
dredging on an annual basis was authorized by the Water 
Resources Act of 1974. Previous work was done under the 
authority of the River and Harbor Act of 1945, Section 3, 
P.L. 79-14. 
Local cooperation. Requirements fully satisfied. 
Terminal facilities. There are five marinas and 
numerous private docks located about the Murrells Inlet 
Harbor. There are several public boat ramps in the area. 
Facilities are expected to be expanded and new ones added 
as demands for services outstrip capacity. 
Operations and results during fiscal year. 
New Work: None. Maintenance: A monitoring program 
was initiated in April 1978 to provide site specific information 
for proper management of the project and to provide data on 
coastal response to the project. Charleston District collects 
most of the data and Coastal Engineering Research Center 
(CERC) performs data analysis and interpretation. The 
monitoring program has been adjusted several times based 
on CERC recommendations. Currently the program includes 
annual aerial photography, jetty surveys and site inspections, 
semi-annual surveys of beaches and the deposition basin. 
Channel surveys are not scheduled but are conducted on an 
"as needed" basis. 
Results of the monitoring program have led to 
recommendations for dredging the deposition basin, 
nourishment of a reach of eroded beach at North Litchfield 
Beach and erosion protection of a section of the south jetty 
sand dike. Condition and operations studies, water control 
management costs, project operations management, 
inspections and reports, planning, engineering and design, 
breakwater, jetty and seawall maintenance, and supervision 
and administrative costs were $76,925. 
Condition at end of fiscal year. The existing 
project was completed in 1981. Federal costs for the existing 
7-6

CHARLESTON, SOUTH CAROLINA DISTRICT 
project to date have been $15,502,240 for new work and 
$3,712,232 for maintenance, a total of $19,214,472. 
13. PORT ROYAL HARBOR, SC 
Location. The harbor is located on the coast of South 
Carolina 57 miles southwest of Charleston Harbor and 23 
miles northeast of the mouth of the Savannah River. (See 
National Ocean Survey Chart No. 11516.) 
Existing project. The authorized project provides for 
a channel from the ocean through Port Royal Sound to Port 
Royal, South Carolina, 27 feet deep and 500 feet wide across 
the ocean bar and in Port Royal Sound for approximately 
12.7 miles, thence 24 feet deep and 300 feet wide in Beaufort 
River and Battery Creek for approximately 8.3 miles to and 
including a turning basin 27 feet deep and 600 feet wide 
opposite the wharf of the South Carolina State Ports 
Authority. (See the table at the end of the chapter for acts 
authorizing the existing project.) 
Local cooperation. None required. 
Terminal facilities. The South Carolina State Ports 
Authority constructed a marginal concrete wharf and 
operates modern terminal facilities which are considered 
adequate for present commerce of the port. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Maintenance dredging was 
performed by hopper dredge in the entrance channel during 
February 1992 - April 1992, removing 833,820 cubic yards of 
material at a cost of $1,514,418. Natural resource 
management, condition and operation studies, water control 
management, inspections and reports, easement acquisition, 
planning, engineering and design, and supervision and 
administration costs were $117,850. 
Condition at end of fiscal year. The existing 
project was completed in 1959. Federal costs for the existing 
project to date have been $1,786,100 for new work and 
$10,986,099 for maintenance, a total of $12,772,199. 
14. SHIPYARD RIVER, SC 
Location. This waterway is a tidal tributary of 
Charleston Harbor, South Carolina. It has its source about 
one-half mile below the U. S. Naval Base, whence it flows 
southerly about three miles and empties into the Cooper 
River, about three-fourths miles above Drum Island. (See 
National Ocean Survey Chart No. 11524.) 
Previous projects. For details, see page 610 of 
Annual Report for 1932 and page 463 of Annual Report for 
1944. 
Existing project. The authorized project provides for 
a channel 30 feet deep from Cooper River to MacAlloy 
Corporation's plant, including two turning basins, one 
opposite Chevron Oil Corporation Terminal and another at 
the upper end of the project. (See table at end of chapter 
for acts authorizing existing project.) 
Local cooperation. None required. 
Terminal facilities. In the lower three-quarters of 
a mile of the channel are large marginal wharves of the 
Chevron Oil Corporation and Shipyard River Terminal 
Company. These wharves accommodate deep-draft, 
oceangoing vessels for handling petroleum products, coal and 
fertilizer materials. In the upper channel is MacAlloy 
Corporation's wharf for handling ores. For further details 
see Port Series No. 13, 1980, Corps of Engineers. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Water control management, 
project operations management, condition and operations 
studies, natural resource management, planning, engineering 
and design, and supervision and administrative costs were 
$29,523. 
Condition at end of fiscal year. The existing 
project was completed in 1951. Federal costs under the 
existing project to date have been $487,824 for new work and 
$9,783,084 for maintenance for a total of $10,270,908. 
15. TOWN CREEK, SC 
Location. Town Creek Channel begins at the AIWW 
directly south of the Town of McClellanville in Charleston 
County, SC. The channel follows Five Fathom Creek in a 
southerly direction to the Atlantic Ocean. (See National 
Ocean Survey Chart No. 11531.) 
Existing project. The project provides a channel ten 
feet deep by 80 feet wide from the AIWW to the mouth of 
Five Fathom Creek, a distance of 6.2 miles. The project 
includes an entrance channel twelve feet deep by 100 feet 
wide across the ocean bar, a distance of 4.0 miles. (See table 
at end of the chapter for acts authorizing existing projects.) 
Local cooperation. Requirements fully satisfied. 
Operations and results during fiscal year. New 
Work: None. Maintenance: Maintenance dredging was 
performed in the entrance channel by the sidecaster dredge 
Fy during April 1992 - June 1992 at a cost of $413,590. 
Condition and operations studies, water control management, 
inspection and reports, planning, engineering and design, and 
supervision and administrative costs were $22,778. 
Condition at end of fiscal year. The existing 
project was completed in 1975. Federal costs under the 
7-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
existing project to date have been $219,521 for new work and 
$4,808,906 for maintenance, a total of $5,028,427. 
16. RECONNAISSANCE AND 
CONDITION SURVEYS 
Costs incurred for condition surveys were as follows: 
Adams Creek, SC 
Ashley River, SC 
Edisto River, SC 
Great Pee Dee River, SC 
Lynches River & Clark Creek, 
Mingo Creek, SC 
Salkehatchie River, SC 
Santee River, SC 
Village Creek, SC 
Waccamaw River, NC & SC 
Wateree River, SC 
Total 
$ 2,082 
9,596 
975 
975 
SC 975 
975 
1,067 
975 
975 
975 
1,950 
$21,520 
17. OTHER AUTHORIZED 
NAVIGATION REPORTS 
(See Table 7-C.) 
18. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Work Under Special Authorization Pursuant 
to Section 107, Public Law 86-645, as amended 
(Preauthorization) and Section 111, Public Law 90-433, as 
amended. (See Table 7-D.) 
Snagging and clearing for navigation (Sec. 3 of 1934 
River and Harbor Act, Public Law 14, 79th Congress.) 
None. 
Beach Erosion 
19. FOLLY BEACH, SC 
Location. The municipality of Folly Beach, SC is 
located along the Atlantic shoreline of Folly Island, 
approximately 12 miles south of the City of Charleston, SC. 
Folly Island is the second island south of the Charleston 
Harbor entrance channel. (See National Ocean Survey Chart 
No. 11521.) 
Existing project. The plan of improvement provides 
for protection from a 5-year storm event and would place 
about 2.48 million cubic yards of sand over a total project 
reach of 28,200 feet of beach. The project would have an 
initial berm with a top width of 15 feet at an elevation of 9.0 
feet above the national geodetic vertical datum. Nine groins 
constructed of wooden piles, timbers, and large rocks which 
extend perpendicular into the surf for an average distance of 
approximately 250 linear feet will be rehabilitated. The 
rehabilitated groins will be built of steel sheet pile and will 
tie into only the wooden sections of existing groins which are 
deemed salvageable. Initial construction is expected to take 
approximately 6 months with construction expected to begin 
in January 1993. Mean tidal range is 2.8 feet. 
Periodic nourishment will be required approximately every 
eight years with a total volume of 1.74 million cubic yards 
each cycle. Estimated cost (October 1992 price levels) of 
initial construction is $14,290,000 Federal and $2,522,000 non- 
Federal for a total of $16,812,000. Estimated cost of periodic 
nourishment is $84,399,000 Federal and $14,893,000 non- 
Federal for a total project cost of $116,104,000. 
Local cooperation. Local interests must contribute 15 
percent of all costs associated with the initial construction 
and periodic nourishment costs; provide lands, easements and 
rights-of-way; and maintain all project works after 
completion. 
Operations and results during fiscal year. PED 
was completed in July 1992. Funds of $219,709 were spent 
for engineering and design in order to ready the project for 
construction. 
20. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
(See Table 7-E.) 
21. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 103, 
1960 River & Harbor Act, as amended, consisted of one 
reconnaissance study - Edisto Beach, SC. FY 92 costs on 
this study totaled $2,485. 
Flood Control 
22. SOCASTEE CREEK, SC 
Location. Socastee Creek is a small coastal stream 
located 5 miles inland and adjacent to Myrtle Beach, Horry 
County, SC. The creek originates in Big Bay Swamp and 
flows in a southwesterly direction for approximately eight 
miles to its confluence with the Atlantic Intracoastal 
Waterway (AIWW). The total drainage area of the creek 
above the AIWW is 22.5 square miles. 
Existing project. The plan of improvement consists of 
clearing and enlarging approximately 2.1 miles of the existing 
7-8

CHARLESTON, SOUTH CAROLINA DISTRICT 
creek channel with the inclusion of two low flow weirs to 
protect the quality of the existing natural environment. 
Local cooperation. Local interests must provide all 
lands, easements, and rights-of-way; accomplish all alterations 
and relocations of structures, utilities, highways, bridges, 
railroads, sewers, and related and special facilities; provide, 
during the period of construction, an amount equal to not 
less than 25 percent of the total project costs, at least 5 
percent of which will be cash; operate and maintain all 
projects works after construction; hold and save the United 
States free from damages due to the construction and 
subsequent maintenance of the project; publicize flood plain 
information in the area concerned and provide this 
information to zoning and other regulatory agencies for their 
guidance and leadership in preventing unwise future 
development in the flood plain; prescribe and enforce, to the 
extent of its powers, regulations to prevent obstruction of or 
encroachment on the project that would reduce the level of 
protection it affords or that would hinder operation and 
maintenance; and at least annually, inform affected interests 
that the project will not provide complete flood protection. 
Operations and results during fiscal year. 
Construction began in February 1992 and is expected to be 
completed in April 1993. Engineering and design and 
construction management costs were $10,463 and $40,884, 
respectively. Total contract costs were $263,880. Federal 
costs for the project were $261,296. 
Condition at end of Fiscal Year. Federal costs through 
FY 92 for the existing project have been $378,841 for new 
work. 
23. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
To determine the extent of compliance with approved 
regulations for maintenance and operation, inspections were 
made of the following projects during the period: Gapway 
Swamp, Cowpen Swamp, Crab Tree Swamp, Simpson Creek; 
Todd Swamp, Buck Creek, N. Edisto River, Sawmill Branch, 
Shot Pouch Creek, Turkey Creek, Kingstree Branch, Cow 
Castle Creek, Wilson Branch, Eagle Creek, Scotts Creek, and 
Pompion Chapel. Responsible local officials were advised of 
inadequacies in maintenance and operation on local flood 
protection works when appropriate. Cost for the period was 
$24,597. 
24. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 7-F.) 
25. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
(See Table 7-G) 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th Congress, 
and Antecedent Legislation). 
Federal costs for FY 92 were $218,254 for Flood Control 
and Coastal Emergencies and $125,942 for the National 
Emergency Preparedness Program. 
Miscellaneous 
26. STREAMBANK EROSION UNDER 
SPECIAL AUTHORIZATION 
Streambank erosion activity pursuant to Section 14 of the 
1946 Flood Control Act (as amended) was Drayton Hall, 
Charleston County, SC and Middleton Place, Charleston 
County, SC. FY 92 costs for these projects were $40,540 and 
$2,877, respectively. 
(See Table 7-H for previous work in this category.) 
General Investigations 
27. ACTIVE INVESTIGATIONS 
See Table 7-I which covers: Surveys, Collections, and 
Study of Basic Data, and Research and Development 
Activities. 
7-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 7-A COST AND FINANCIAL STATEMENT 
See 
Sect. 
in Total Cost to 
Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
1 Aquatic Plant 
Control, SC 
(Contributed Funds) 
2 Atlantic Intracoastal 
Waterway 
Between Norfolk, 
Va. and the St. 
Johns River, FL 
3 Brookgreen Gardens, 
SC 
(Contributed Funds) 
4 Charleston Harbor, 
SC 
(Contributed Funds) 
5 Charleston Harbor 
Rediversion (Fish 
Lift), SC 
6 Cooper River, 
Charleston Harbor, 
SC 
7 Cooper River Seismic 
Modification, SC 
New Work: 
Approp. 
Cost 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
427,000 
491,838
0
0 
524,000 
666,566
0
0 
1,038,000 
1,036,881
0
0 
0
0 
1,060,000 
1,078,222 
0
0 
0
0 
0
0 
6,332,605 
6,326,548 
52,028 
52,028 
7,455,378 
7,455,378 
2,019,400 1,669,282 2,855,000 2,764,000 56,481,686 
2,337,601 1,648,820 2,650,502 3,059,744 56,436,869 
3,000 
3,971
0
0 
62,100 
49,614 
7,200 
4,489 
-13,900 
-1,192
0
0 
600 
3,311 
00 
4,000 
1,017
0
0 
94,700 
94,700 
4,000 
1,017 
7,800 
7,800 
7,045,000 7,847,000 5,378,000 9,051,000 45,623,564 
8,248,738 6,585,093 6,965,732 9,586,388 45,073,237 
2,914,900 2,804,942 3,138,000 3,984,000 111,247,429 
3,163,395 2,090,648 3,762,453 3,990,871 111,113,889 
2,763,000 2,180,000 2,190,000 3,215,000 11,645,000 
2,749,580 2,195,032 2,321,912 3,195,463 11,385,069 
250,000 
213,182 
125,000 7,043,608 
9,484 7,064,558 
43,000 
1,192 
250,000 
213,182 
0 198,681,191 
163 196,874,134 
3,764,200 3,122,259 3,846,000 2,692,000 25,501,459 
3,745,712 3,095,470 4,020,940 2,455,864 25,161,285 
3,602,000 1,900,000 
13,123,808 11,025,936 
0 
181,588 
0 29,500,000 
188,142 29,397,454 
7-10

TABLE 7-A 
CHARLESTON, SOUTH CAROLINA DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Sect. 
in Total Cost to 
Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
8 Folly River, SC 
9 Georgetown Harbor, 
SC 
10 Jeremy Creek, SC 
11 Little River Inlet, 
NC and SC 
(Contributed Funds) 
12 Murrells Inlet, SC 
(Contributed Funds) 
13 Port Royal Harbor, 
SC 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
0
0 
337,736 
337,736 
260,600 291,107 501,000 266,000 3,147,707 
259,916 123,602 668,469 267,158 3,146,891 
0
0 
7,061,755 
7,061,755 
2,893,400 3,263,737 1,673,000 2,261,000 57,920,917 
2,845,413 3,087,347 1,986,794 2,259,120 57,859,613 
0
0 
51,000 
54,061 
19,675 
13,235 
1,000 12,000 
6,372 12,839
0
0 
49,987 
49,987 
97,675 
97,343 
17,037,428 
17,037,428 
52,000 194,326 109,000 71,000 2,792,002 
57,918 165,296 128,774 80,840 2,788,372 
0
0 
0
0 
0
0
0
0 
50,000 2,033,000 
3,039 2,091,736 
1,521,920 
1,521,920 
15,502,240 
15,502,240 
143,000 118,231 56,000 70,000 3,782,500 
124,252 110,628 81,744 76,925 3,779,232 
156,893 
156,893
0
0 
0
0
0
0 
1,536,893 
1,536,041 
1,786,100 
1,786,100 
474,000 1,711,252 242,000 1,625,000 10,994,660 
473,388 1,671,838 278,022 1,632,268 10,986,099 
7-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 7-A COST AND FINANCIAL STATEMENT 
See 
Sect. 
in Total Cost to 
Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
14 Shipyard River, SC New Work: 
Approp. 0 0 0 0 491,974 8 
Cost 0 0 0 0 491,974 
Maint: 
Approp. 40,000 101,520 363,000 33,000 9,791,212 
Cost 96,188 32,340 430,948 29,523 9,783,084 
15 Town Creek, SC New Work: 
Approp. 0 0 0 0 219,521 
Cost 0 0 0 0 219,521 
Maint: 
Approp. 393,000 414,051 569,000 444,000 4,823,051 
Cost 392,959 354,796 622,612 436,368 4,808,906 
(Contributed Funds) New Work: 
Approp. 0 0 0 8,600 
Cost 0 0 0 8,600 
19 Folly Beach, SC New Work: 
Approp. 0 0 0 300,000 300,000 
Cost 0 0 0 219,709 219,709 
22 Socastee Creek, SC New Work: 
Approp. 69,000 14,000 50,000 741,000 874,000 
Cost 5,909 67,830 43,806 261,296 378,841 
(Contributed Funds) New Work: 
Approp. 0 0 187,000 0 187,000 
Cost 0 0 2,313 53,931 56,244 
1 Includes $109,490 for new work for previous projects. 
2 Includes $69,422 for maintenance of previous projects. 
3 Includes $10,165,564 for previous projects and $752,000 for 
Preconstruction, Engineering and Design. 
4 Includes $401,989 for maintenance of previous projects and $600 for 
maintenance expended from contributed funds for the existing project. 
5 Includes $2,445,852 for new work for previous projects. 
6 Includes $114,556 for maintenance of previous projects 
7 Includes $67,000 accomplished under authority of 
Section 3, P.L. 79-11 incurred through FY 73. 
8 Includes $4,150 for new work on previous projects. 
7-12

CHARLESTON, SOUTH CAROLINA DISTRICT 
AUTHORIZING LEGISLATION 
Date of Authorizing Act Work Authorized Documents 
Oct. 27, 1965 
Sep. 19, 1890 
Jun. 13, 1902 
Mar. 2, 1907 
Mar. 2, 1907 
Mar. 3, 1925 
Mar. 3, 1925 
Jul. 3, 1930 
Aug. 30, 19351 
Aug. 30, 1935 2 
Aug. 30, 1935 2 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 14, 1960 
as amended 
Jun. 18, 1878 
Aug. 8, 1917 
Jul. 18, 1918 
Jan. 21, 1927 
AQUATIC PLANT CONTROL, SC 
(See Section 1 of text.) 
Provides for control and progressive eradication of 
water hyacinth, alligatorweed, Eurasian water-milfoil 
and other obnoxious aquatic plant growths from 
cnhavanignaebllse, waters, tributary streams, connecting and other allied waters of the U.S., m 
combined interest of navigation, flood control, 
drainage, agriculture, fish and wildlife conservation, 
public health and related purposes, including 
continued research for development of most effective 
and economic control measures in cooperation with 
other Federal and state agencies. 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA, AND ST. JOHNS 
RIVER, FL 
See Section 2 of text.) 
hannel from Minim Creek to Winyah Bay. 
Channel from Charleston to a point opposite 
McClellanville. 
Branch channel to McClellanville. 
Extending the channel to Minim Creek, thence 
through the Esterville-Minim Canal to Winyah Bay. 
Cut across the Santee Delta at Four Mile Creek. 
Widening and deepening the waterway from 
Charleston to Beaufort. 
A waterway eight feet deep and 75 feet wide from 
Cape Fear River to Winyah Bay 
Construction of bridges across the waterway in Horry 
County, SC. 
Cutoff between Ashepoo and Coosaw Rivers. 
Enlarging the channel from Winyah Bay to 
Charleston including the branch channel to 
McClellanville, to depth of ten feet and bottom width 
of 90 feet. 
Increasing dimensions of waterway to twelve 
feet deep and 90 feet wide. 
Anchorage Basin 125 feet wide, 335 feet long, 
twelve feet deep, near Myrtle Beich, SC. 
(Deauthorized by 1989 WRDA) 
BROOKGREEN GARDENS, SC 
See Section 3 of text.) 
rovides for a 3,600 foot canal with a 30-foot bottom 
width, maintained to a depth of four feet mlw. 
CHARLESTON HARBOR, SC 
See Secton 4 of text.) 
jetties. 
Increase in depth to 30 feet with width of 500 feet 
between the jetties and 1,000 feet seaward thereof. 
The 40-foot channel to the Naval Base. 
Act provided that the 40-foot channel should not be 
undertaken "until the proposed new drydocks at this 
navy yard, carrying a depth of 40 feet of water over 
the blocks has been authorized." This dock was 
authorized in the Naval Appropriations Act approved 
Jul 1 1918 (40 Stat. L. 725). 
A 30-foot channel from the sea to Goose Creek via 
Cooper River, together with a 30-foot channel 
through Town Creek for commercial purposes. The 
act also provided that the 40-foot channel be 
prosecuted only as found necessary for national 
defense. 
H.D. 251, 89th Cong., 1st Sess. 
P.L. 89-298 
Annual Report, 1889, p. 1184. 
H.D. 84, 56th Cong., 1st sess. 
and Annual Report 1900, p.19 08 
Annual Report 1903, p. 1133 
H.D. 178, 63rd Cong., 1st. sess. 
H.D. 237, 68th Cong., 1st sess. 
S.D. 178, 68th Cong., 2nd sess. 
H.D. 41, 71st Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 14, 72nd Cong., 1st sess. 
H.D. 129, 72nd Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 11, 72nd Cong., 1st sess. 
Rivers and Harbors Committee, 
Doc 6, 75th Cong., 1st sess. 
H.D. 327, 76th Cong., 1st sess. 
Sec. 107, P.L. 86-645. 
Authorized by Chief of 
Engineers, Feb. 19, 1988. 
Annual Report 1878, pp. 
553-572. 
H.D. 288, 62nd Cong., 2nd sess. 
H.D. 1946, 64th Cong., 2nd sess, 
pt.1, pp. 21-29, 57, 58, and 64-68. 
H.D. 249, 69th Cong. 1st sess. 
7-13 
TABLE 7-B

REPORT ON THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 7-B AUTHORIZING LEGISLATION 
Date of Authorizing Act Work Authorized Documents 
Oct. 17, 1940 
Mar. 2, 1945 
Sep. 3, 1954 
Jul. 14, 1960 
Oct. 22, 1976 
Nov. 17, 1986 
Aug. 13, 1968 
Aug. 17, 1991 
Aug. 13, 1968 
Jul 29, 1983 
Jul. 14, 1960 
as amended 
The 35-foot channel depth from the sea to the head 
of the project via Cooper River and Town Creek, 
also a channel in Shem Creek to Mount Pleasant, 
110 feet wide and ten feet deep, including a turning 
basin at the upper end. 
An anchorage area 30 feet deep in the water area 
between Castle Pinckney and ort Moultrie. 
(Deauthorized by 1986 WRDA) 
Deepen the 30-foot channel north and east of Drum 
Island to 35 feet. 
Shem Creek Channel modified by extending 
1,150 feet upstream and downstream from 
mouth to Atlantic Intracoastal Waterway. 
Project is authorized for the Phase I design 
memorandum stage of Advanced Engineering and 
Design. 
Deepening 35 foot channel to 40 feet (42 feet in the 
ocean bar and entrance channel) from the 42 foot 
ocean contour to Goose Creek, a distance of 27.1 
miles, construction of one turmning basin modification 
of existing turning basins,deepenmng and modification 
of the anchorage basin, deepening Shipyard River to 
38 feet, maintamn the Wando River Channel to 35 
feet at Federal expense and the deepening of this 
channel to 40 feet if economically justified. 
CHARLESTON HARBOR REDIVERSION 
(FISH LIFT), SC 
(See Section 5 of text.) 
ee Cooper River Charleston Harbor. 
Modify the fish lift at the Cooper River, Charleston 
Harbor, SC (Rediversion Project) and monitor 
operation of the fish lift for two years following such 
modifications. 
COOPER RIVER, CHARLESTON HARBOR, SC 
(ST. STEPHEN PROJECT) 
(See Section 6 of text.) 
edivert most of the Santee River waters Pinopolis 
Dam into the lower Santee River through a canal 
beginning at Lake Moultrie and extending to the 
Santee River in the vicinity of St. Stephen, South 
Carolina. 
COOPER RIVER SEISMIC MODIFICATION, SC 
See Section 7 of text.) 
onstruct such measures as necessary to improve the 
seismic stability of the Pinopolis West Dam on the 
Cooper River. 
FOLLY RIVER, SC 
ee Section 8 of text.) 
onsists of stable all-tide channel nine feet deep and 
80 feet wide in Folly River and Folly Creek and an 
entrance channel at Stono Inlet 100 feet wide and 
eleven feet deep. 
H.D. 259, 76th Cong., 1st sess. 
H.D. 156, 77th Cong., 1st sess. 
S.D.3 136, 83rd Cong., 2nd 
sess. 
H.D. 35, 86th Cong., 1st sess. 
H.D. 94-436, 94th Cong., 2nd 
sess. 
99th Cong. 2nd sess., 
P.L. 96-662 
S.D. 88, 90th Cong.,P.L. 90-483 
102nd Cong., P.L. 102-104 
S.D. 88, 90th Cong.,P.L. 90-483 
H.D. 3069, 98th Cong., 1st 
sess., P.L. 98-63 
Sec. 107, P.L. 86-645. 
Authorized by Chief of 
Engineers, Dec. 23, 1977. 
7-14

CHARIESTON, SOUTH CAROLINA DISTRICT 
TABLE 7-B 
Date of Authorizing Act 
AUTHORIZING LEGISLATION 
Work Authorized 
GEORGETOWN HARBOR, SC 
See Section 9 of text.) 
etties and earthen dike to protect 
south jetty. 
Aug. 5, 1886 
Jun. 25, 1910 
Mar. 2, 1945 
Jun. 30, 1948 
Jul. 14, 1960 
as amended 
Mar 2. 1945 
Auth. by Senate Public 
Works Comm. and the 
House Public Works Comm. 
on Oct. 12, 1972, under 
auth. of Sec. 201, P.L. 
89-298, 1965 FC Act. 
Mar. 7, 1974 
Mar. 2, 1945 
Auth. by the House 
Committee on Public Works 
on Nov. 10, 1971, and the 
Senate Committee on Public 
Works on Nov 18, 1971, 
under auth. of Sec. 201, 
P.L. 89-298, 1965 FC Act. 
Mar. 7, 1974 
Previous project channel dimensions and training 
wall. 
27-foot channel from ocean, including a turning basin 
in Sampit River. 
Cutoff and side channel in Sampit River. 
JEREMY CREEK, SC 
See Section 10 of text.) 
o provide a turning basin twelve feet deep and 150 
feet in diameter at the head of the previously existing 
Jeremy Creek. 
LITTLE RIVER INLET, NC AND SC 
See Section 11 of text.) 
rovides for an entrance channel twelve feet by 300 
feet across the ocean bar; thence ten feet by 90-foot 
inner channel to the Atlantic Intracoastal Waterway. 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to maintain 
channel depths sufficient to permit free and safe 
movement of vessels until such time as the 
authorized project is constructed. 
MURRELLS INLET, SC 
(See Section 12 of text.) 
Provides for an entrance channel twelve feet by 300 
feet across the seaward bar, thence ten by 90-foot 
inner channel to a turning basin at the old Army 
crash boat dock. 
Authorized emergency dredging operations as the 
Chief of Engineers determines necessary to maintain 
channel depths sufficient to permit free and safe 
movement of vessels until such time as the 
authorized project is constructed. 
H. Ex. Doc. 258 48th Cong., 
2nd sess., and Annual Report 
1885, pp. 1154-1170, and H. 
Ex. Doc. 117, 50th Cong., 2nd 
sess., and Annual Report 1889, 
pp. 1110-1111. 
H.D. 398, 58th Cong., 2nd sess. 
and Annual Report 1904, pp. 
1591-1605. 
H.D. 211, 76th Cong., 1st sess. 
H.D. 21, 81st Cong., 1st sess. 
Sec. 107, P.L. 86-645. 
Authorized by Chief of 
Engineers, 11 Jan 82. 
Sec. 3, P.L. 79-14 
H.D. 362, 92nd Cong. 
H.D. 10203, 93rd Cong., 2nd 
sess., P.L. 93-251 
Sec. 3, P.L. 79-14 
H.D. 137, 92nd Cong. 
H.D. 10203, 93rd Cong., 2nd 
sess., P.L. 93-251 
7-15 
Documents

REPORT ON THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 7-B AUTHORIZING LEGISLATION 
Date of Authoriing Act Work Authorized Documents 
Sep. 3, 1954 
Jul. 25, 1912 
Mar. 3, 1925 
Jul. 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 2 
Mar. 2, 1945 
Jul. 14, 1960 
as amended 
Nov. 17, 1986 
Aug. 17, 1991 
Jun. 30, 1948 
PORT ROYAL HARBOR, SC 
See Section 13 of text.) 
channel from the ocean through Port Royal Sound 
to Port Royal, SC.; 27 feet deep and 500 feet wide 
across the ocean bar and in Port Royal Sound for 
approximately 12.7 miles thence 24 feet deep and 300 
feet wide in Beaufort River and Battery Creek for 
approximately 8.3 miles to and including a turning 
basin 27 feet deep and 600 feet wide opposite wharf 
of the SC State Ports Authority. 
SHIPYARD RIVER, SC 
(See Section 14 of text.) 
Channel depth of 15 feet and width of 100 feet. 
Deepening of channel to 18 feet from deep water in 
Cooper River upstream 1-1/16 miles. 
Channel depths of twelve to twenty feet. 
28-feet from Cooper River to Gulf Oil Corp's 
terminal, and the deepening of the channel above 
that point to twenty feet from the depth of twelve 
feet previously authorized without local cooperation. 
Enlargement of the channel to a depth of 30 feet and 
a width of 200 feet up to the Gulf Oil Corp's 
terminal, with a turnng basin 30 feet deep at the 
latter point. 
Extensioii of the existing 30-foot channel to vicinity 
of the Pittsburg Metallurgical Co. Plant, with a 
turning basin at the upper end. 
TOWN CREEK, SC 
See Section 15 of text.) 
An entrance channel twelve feet deep by 100 feet 
wide across the ocean bar a distance of 4.0 miles and 
a channel ten feet deep by 80 feet wide from the 
mouth of Five Fathom Creek to the Atlantic 
Intracoastal Waterway, a distance of 6.2 miles. 
FOLLY BEACH, SC 
(See Section 19 of text.) 
Shoreline protection. 
Construct hurricane and storm protection measures. 
SOCASTEE CREEK, SC 
(See Section 22 of text.) 
Clearing and enlarging approximately 2.1 miles of the 
existing creek channel with the inclusion of two low 
flow weirs. 
H.D. 469, 81st Cong., 2nd sess. 
S.D. 350, 62nd Cong., 2nd sess. 
H.D. 288, 68th Cong., 1st sess. 
Rivers & Harbors Committee 
Doc. 13, 71st Cong., 2nd sess. 
Rivers & Harbors Committee 
Doc. 43, 73th Cong., 2nd sess. 
Rivers & Harbors Committee 
Doc. 38, 75th Cong., 1st sess. 
H.D. 93, 79th Cong., 1st sess. 
Sec. 107, P.L. 86-645. 
Authorized by Chief of 
Engineers, Feb. 12, 1974. 
P.L. 99-662 
99th Cong., 2nd sess. 
P.L. 102-104 102nd Cong. 
Sec. 205 P.L. 858. Authorized 
by Chief of Engineers, Apr. 26, 
1989. 
1/Included in Public Works Administration 
Program September 6, 1933. 
2/Included in Emergency Relief Administration 
Program May 28, 1935. 
3/ Contains latest published maps. 
4/ Inactive. 
5/ Completed under previous projects. 
6/ For national defense. 
7-16

CHARESTON, SOUTH CAROLINA DISTRICT 
TABLE 7-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 17 of Text) 
For Last 
Full Report 
See Annual Operation & 
Project Report for Construction Maintenance 
Adams Creek, SC 1 1978 $125,697 $29,143 
Aquatic Plant Control, NC and SC 1 '5 1968 379,680 -- 
Archers Creek, Sp 1914 20,646 -- 
Ashley River, SC 1955 260,996 562,195 
Edisto River, SC 1.2 1938 33,103 2,485 
Great Pee Dee River, SC 1 1950 183,712 271,098 
Mingo Creek, SC " 1950 29,050 8,575 
Lynches River and Clark Creek, SC 1 1982 9,500 85,595 
Salkahatchie River, SC 1'2' 1896 15,841 1,847 
Santee River, NC & SC 1 1950 99,750 182,469 
Village Creeks SC 1985 26,500 111,314 
Waccamaw River, NC and SC 1978 262,814 284,347 
Wateree River, SC 1940 60,000 154,559 
1 Completed 
2 No commerce reported 
SCurtailment recommended in 1926 (H.D. 467, 69th Cong., 1st Session) 
4 Abandonment recommended in 1926 (H.D., 69th Cong., 1st Session) 
5 Pilot Program 
TABLE 7-D NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
(See Section 18 of Text) 
Study Identification Section Fiscal Year Costs 
Calabash Creek, Brunswick County, NC 107 $19,224 
Shipyard River, SC 107 -1,354 
OTHER AUTHORIZED 
TABLE 7-E BEACH EROSION PROJECTS 
(See Section 20 of the Text) 
For Last 
Fall Report 
See AnnualOeration & 
Project Report for Construction M ntenace 
Hunting Island Beach, SC 1984 $2,872,7171 -- 
1 Excludes $1,249,336 contributed funds 
7-17

REPORT ON THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 7-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 24 of Text) 
For Last 
Full Report 
See Annual "on & 
Project Report for Construction intenance 
Buck Creek, NC 7 SC 1,2 1970 $298,167 -- 
CowCasCtl e reek, SC '2 1985 250,000 -- 
Cowpens Swamp, SC 1,2 1960 18,679 -- 
Crabtree Swam, SC 12 1969 97,000 -- 
Eagle Creek, SC 1986 1,245,063 -- 
Edisto River, SC 1'3 1947 6,379 -- 
Edisto River, North Fork, SC 1'2 1969 127,660 -- 
Edisto River, Vicinity Canadays Landing, SC 1 2 1958 3,160 -- 
Gapway Swamp, SC" 1969 339,197 -- 
Kingstree Branch, Williamsburg County, SC 1978 247,242 -- 
Leith's Creek, SC 12 1982 430,951 -- 
Reddies River Lake, NC 1980 985,800 -- 
Reedy River, SC 13 1974 4,500 -- 
Roarmg River, Wilkes County, NC 1 4 1978 370,000 -- 
Saluda TRiver SC 12 1963 99,000 -- 
Sawmill Branch, Sc 1'2 1971 248,605 -- 
Scotts Creek, SC 1988 545,000 
Shot Pouch Creek, Sumter Co., SC 1 2 1971 77,400 -- 
Sim son Creek, S~ 2 1957 81,000 -- 
Todd Swamp, SC 1964 29,000 -- 
Turkey Creek, Sumter County, SC 1'2 1974 319,669 -- 
Wilson Creek, Sumter County, SC 1'2 1985 277,111 -- 
1Authorized by Chief of Engineers 3 Discontinued due to lack of interest 
2 Completed 4 Phase I only 
TABLE 7-G FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Preauthorization studies 
(See Section 25 of Text) 
Study Identification Section Fiscal Year Costs 
Alligator Branch, Sumter County, SC 205 3,000 
Cow Castle Orangeburg County, SC 205 8,080 
Eagle Creek, Dorchester County, SC 205 9,784 
Eight Mile Creek, Richland County, SC 205 20,658 
Four Holes Swamp, Orangeburg County, SC 205 68 
Gills Creek Above Lake Katherme, Richland County, SC 205 26,045 
Gills Creek Below Lake Katherine, Richland County, SC 205 23,892 
Green Swamp, Sumter County, SC 205 30,665 
Halfway Branch, Spartenburg, SC 205 6,767 
Horsepen Branch, Sumter County, SC 205 3,000 
Jackson Creek, Richland County, SC 205 6,289 
Jeffries Creek, Darlington County, SC 205 18,777 
Kinley Creek, Lexington County, SC 205 67,585 
Middle Penn, Orangeburg County, SC 205 4,218 
Old Kingstree Canal, Williamsburg County, SC 205 7,903 
Otranto Watershed, Charleston County, SC 205 22,321 
Pleasant Meadow Swamp, Loris, SC 205 573 
Pocotaligo River, Manning, SC 205 11,844 
Popperdam Creek, North Charleston, SC 205 2,830 
Powder Horn Branch, Sumter County, SC 205 6,153 
Rawls Creek, Irmo, SC 205 22,382 
Rumphs Hill Creek, Dorchester County, SC 205 9,979 
Summerville Creek, Dorchester County, SC 205 29,897 
Turkey Creek, Sumter County, SC 205 27,440 
7-18

CHARLESTON, SOUTH CAROLINA DISTRICT 
STEAMBANK EROSION 
TABLE 7-H UNDER SPECIAL AUTHORIZATION 
(See Section 26 of the Text) 
For Last 
Full Report 
See Annual Operation & 
Project Report for Construction M tenance 
Cooper River, Pompion Hill Chapel, SC 1987 $211,1001-- 
1 Completed 
TABLE 7-I ACTIVE GENERAL INVESTIGATIONS 
(See Section 27 of Text) 
ITEM FISCAL YEAR COSTS 
SURVEYS (CATEGORY 100) 
NAVIGATION STUDIES (CATEGORY 110) 
Charleston Harbor Deepening/Widening $ 222,578 
SHORELINE PROTECTION STUDIES (CATEGORY 130) 
South Carolina Shores, North Portion 16,916 
South Carolina Shores, South Portion 451 
MISCELLANEOUS ACTIVITIES (CATEGORY 170) 
Special Investigations $ 66,803 
FERC Licensing Activities 4,035 
Interagency Water Resources Development 29,144 
North American Waterfowl 2,990 
COORDINATION STUDIES WITH OTHER AGENCIES (CATEGORY 180) 
Department of Agriculture, SCS $ 5,052 
Planning Assistance to States 14,162 
TOTAL (CATEGORY 100) $ 362,131 
COLLECTION AND STUDY OF BASIC DATA (CATEGORY 200) 
FLOOD PLAIN MGMT SERVICES (CATEGORY 250) $145,909 
HYDROLOGIC STUDIES (CATEGORY 260) 
Hydrologic Studies 5,098 
TOTAL (CATEGORY 200) $151,007 
CONTINUATION OF PLANNING AND ENGINEERING (CATEGORY 400)$ 
Myrtle Beach, SC $ 8 
TOTAL (CATEGORY 400) $ 8 
ADVANCE ENGINEERING & DESIGN (CATEGORY 600) 
Folly Beach, SC 191,865 
Myrtle Beach, SC 677,764 
TOTAL (CATEGORY 600) $ 869,629 
TOTAL GENERAL INVESTIGATIONS $1,382,775 
7-19

SAVANNAH, GA, DISTRICT* 
The District comprises drainage basins that flow into the Atlantic Ocean between Port Royal Sound, SC, and 
Cumberland Sound, GA and FL, and includes the Atlantic Intracoastal Waterway between these points. This 
area covers the headwaters of the Savannah River in southwestern North Carolina, eastern Georgia, and a 
small portion of northeastern Florida. 
IMPROVEMENTS 
Navigation 
1. Altamaha, Oconee, and Ocmulgee 
Rivers............................8-2 
2. Aquatic Plant Control ............... 8-2 
3. Atlantic Intracoastal Waterway 
Between Norfolk, VA, and St. Johns 
River, FL (Savannah District).......... 8-3 
4. Brunswick Harbor, GA .............. 8-3 
5. Savannah Harbor, GA ................ 8-4 
6. Savannah River Below 
Augusta, GA ..................... . 8-5 
7. Reconnaissance and Condition 
Surveys ........................... 8-5 
8. Other Authorized Navigation 
Projects ........................... 8-5 
9. Navigation Work Under Special 
Authorization ..................... . 8-5 
Beach Erosion Control 
10. Beach Erosion Control Work 
Under Special Authorization .......... 8-6 
11.TybeelIsland,GA .................. 8-6 
Flood Control 
12. Oates Creek, Richmond County, GA ... 8-6 
13. Inspection of Completed Flood 
Control Projects ................... 8-7 
14. Other Authorized Flood Control 
Projects ........................... 8-7 
15. Flood Control Work Under Special 
Authorization ....................... 8-7 
Emergency Streambank and Shoreline Protection 
16. Emergency Streambank and Shoreline 
Protection Under Special Authorization.. 8-7 
Project Modifications for Improvement of 
Environment 
16A.Project Modifications for Improvement of 
Environment Under Special 
Authorization ..................... . 8-7 
16B. Lower Savannah River ............. 8-7 
Multiple-Purpose Projects Including Power 
17. Savannah River Basin, GA and SC ..... 8-8 
17A. J. Strom Thurmond Dam and Reservoir, 
GA and SC (Formerly Clarks Hill Lake, 
GA and SC) ................... . .. . 8-8 
17B. Hartwell Lake, GA and SC .......... 8-8 
17C. Richard B. Russell Dam and Lake, 
GA and SC (Formerly Trotters Shoals 
Lake, GA and SC) .................. 8-9 
18. West Point Lake, Chattahoochee 
River Basin, GA and FL ............. 8-10 
General Investigations 
19. Surveys .................... ..... 8-10 
20. Collection and Study of Basic Data ... 8-10 
21. Research and Development ......... 8-10 
22. Continuation of Planning 
and Engineering .................. . 8-10 
Tables 
Table 8-A Cost and Financial Statement .. 8-11 
Table 8-B Authorizing Legislation ....... 8-13 
Table 8-C Other Authorized Navigation 
Projects ....................... 8-18 
Table 8-D Other Authorized Flood Control 
Projects ...................... 8-19 
Table 8-E Savannah River Basin, GA and 
SC Dams and Lakes ............ 8-19 
8-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
1. ALTAMAHA, OCONEE, AND OCMULGEE RIVERS, 
GA 
Location. These rivers are entirely within the State 
of Georgia. (See National Oceanic and Atmospheric 
Administration Survey Map of Georgia, formerly 
U. S. Geological Survey Map of Georgia.) For 
a full description of these rivers, see page 636, Annual 
Report for 1932. 
Previous projects. Prior projects for the Altamaha 
River have been adopted, and expenditures made 
under them, by the River and Harbor Acts of March 3, 
1881, and September 19, 1890; for the Oconee River 
by the River and Harbor Acts of June 18, 1878, September 
19, 1890, and March 3, 1905; for the Ocmulgee 
River, by the River and Harbor Acts of 
August 14, 1876, and September 19, 1890. 
For Further Details, see page 1815, Annual Report 
for 1915, and page 589, Annual Report for 1938. 
Existing project. This project covers the entire Altamaha 
River (including a channel between the river 
and Darien, GA), a length of 137 miles. The lower 
139 miles of the Oconee River has a mean tidal 
range of 6.4 feet at its mouth which gradually decreases 
to mile 33, where there is no perceptible 
tidal effect. At Doctortown, mile 59, ordinary floods 
attain a height of about 10 feet above low water, and 
at extreme floods, a height of about 15 feet above 
low water. 
On the Oconee River at Dublin the ordinary fluctuations 
attain a height of 22 feet, and the extreme fluctuations 
a height of 32 feet above low water. On the 
Ocmulgee River at Macon the ordinary fluctuations 
attain a height of 15 feet, and the extreme fluctuations 
a height of 25 feet above low water. There is no 
approved estimated cost for improvement or for 
maintenance. 
Published maps of these rivers are in the following 
documents; Altamaha River, HED 282, 51st Cong., 
2d sess., Oconee River, HED 211, 51st Cong., 1st 
sess., Ocmulgee River, HED 215, 51st Cong., 1st 
sess., and Lower Altamaha River and Darien Harbor, 
GA, HD 610, 77th Cong., 2d sess. (See Table 
8-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Along these rivers there are numerous 
natural shore landings which are considered 
ample for existing commerce. Facilities for recreational 
boats have been constructed at several 
points. 
Operations and results during fiscal year. 
Maintenance: There were no maintenance costs 
this fiscal year. 
Condition at end of fiscal year. The existing project 
is such that the percentage of completion cannot 
be stated. Channel depths have been increased 
by excavating rock shoals and sandbars, by constructing 
contraction and bank-protection works, 
and by closing cutoffs. Navigation has been rendered 
safer by removing obstructions. Many of the 
closing dams and contractions and bank-protection 
works need repairs. The notice of availability on 
the Final Environmental Impact Statement appeared 
in the Federal Register October 21, 1977. 
2. AQUATIC PLANT CONTROL 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in 
Savannah District. 
Existing project. The project provides for control of 
water-hyacinth, lyngbya, alligator weed, Eurasian 
water milfoil, and other noxious aquatic plants from 
navigable waters, tributary streams, connecting 
channels, and other allied waters of the United 
States, in the combined interests of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, public health, and related purposes. 
The project provides for continued research for developing 
the most effective and economic control 
measures in cooperation with other Federal and 
State agencies in accordance with report of Chief of 
Engineers, H. S. 251, 89th Cong., 1st sess. The 
authorizing act provides that research costs shall be 
borne fully by the United States. (See Table 8-B for 
Authorizing Legislation.) 
The Final Environmental Impact Statement was filed 
with EPA on August 6, 1979, and its notice of availability 
appeared in the Federal Register August 17, 
1979. (See Table 8-A for Cost and Financial Statement). 
Local cooperation. Local interests must agree to 
hold the United States free from damages that may 
occur from operations performed in connection with 
this project and participate to the extent of 50 percent 
of the cost of the planning and actual control 
operations of the program. Requirements are being 
met. 
Operations and results during fiscal year. The 
Georgia Game and Fish Division, Department of 
Natural Resources, who maintain surveillance of potential 
aquatic plant problem areas, reported nuisance 
aquatic plant infestation in Lakes Jackson, 
Blackshear, Worth, and in Ebenezer Creek. Total 
8-2

SAVANNAH, GA, DISTRICT 
projected cost of the FY92 program was $140,000 of 
which the portion contributed bythe Federal government 
was $70,000. FY 92 treatments include introduction 
of biological control agents and chemical 
applications. 
3. ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA, AND THE ST. JOHNS 
RIVER, FL (SAVANNAH DISTRICT) 
Location. This 161-mile section of waterway connects 
Port Royal Sound, SC, with Cumberland 
Sound, GA and FL. (See NOAA charts 
11489-11507, formerly Coast and Geodetic Survey 
Charts 838-841, inclusive.) 
Previous project. (Between Savannah, GA, and 
Fernandina, FL) For details see pages 1814, 
1821-1823 of Annual Report for 1915 and page 585 
of Annual Report for 1938. 
Existing project. The project provides for a waterway 
12 feet deep at mean low water and not less 
than 90 feet wide between Port Royal Sound, SC, 
and Savannah, GA; 12 feet deep at mean low water, 
with widths of 90 feet in land cuts and narrow 
streams and 150 feet in open waters between 
Savannah, GA, and Cumberland Sound, GA and FL; 
and a suitable anchorage basin at Isle of Hope, GA. 
Mean tidal range between Port Royal, SC, and Cumberland 
Sound, GA and FL is from 6 to 8 feet with 
fluctuations from 1.5 to 2.5 feet due to winds and lunar 
phases. (See Table 8-B for Authorizing Legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Exclusive or adequate terminal 
facilities at port of entry, this improvement serves 
numerous wharves, some of which are open to the 
public on equal terms. Facilities are considered ample 
for existing commerce. 
Operations and results during fiscal year. 
Maintenance: The District prepared plans and 
specifications for the FY93 contract. 
Condition at end of fiscal year. The main channel 
of the existing project, completed in 1941, is maintained 
at 12 feet. The former main channel, now an 
alternate route through the westerly end of the south 
channel and northerly end of Wilmington River, will 
be maintained to a depth of 7 feet mean low water for 
traffic points north and south of Savannah Harbor. 
Relocation of the main channel from the Frederica to 
Mackay Rivers near St. Simons Island, GA, was accomplished 
after construction of a new bridge for 
the Torras Causeway. The notice on the Final Environmental 
Impact Statement appeared in the Federal 
Register October 29, 1976. Total expenditures 
for the FY are $2,285,093. (See Table 8-A for Cost 
and Financial Statement.) 
4. BRUNSWICK HARBOR, GA 
Location. The harbor entrance is 70 statute miles 
south of the entrance to Savannah Harbor, GA, and 
25 statute miles north of the entrance to Fernandina 
Harbor, FL. (See NOAA Chart 11215, formerly Coast 
and Geodetic Survey Chart 447.) 
Previous projects. For details see page 1818 of 
Annual Report for 1915 and page 591 of Annual Report 
for 1938. 
Existing project. The project provides for a stone 
jetty 4,350 feet long at the entrance to East River and 
the following channels: 32 feet deep and 500 feet 
wide across the bar; 30 feet deep and 400 feet wide 
through St. Simons Sound, Brunswick River, and 
East River to the foot of Second Avenue; 30 feet 
deep and 300 feet wide in Turtle River to the Allied 
Chemical Co. wharf, formerly the Atlantic Refining 
Co.; 30 feet deep and 400 feet in South Brunswick 
River;27 feet deep and 350 feet wide in East River 
from Second Avenue to its confluence with Academy 
Creek; 24 feet deep and 150 feet wide from St. 
Simons Sound to the mouth of Mill Creek; and a 
channel in Terry Creek 10 feet deep and 150 feet 
wide from St. Simons Sound to the mouth of Mill 
Creek; and a channel in Terry Creek 10 feet deep 
and 80 feet wide from its mouth to a point immediately 
above the wharf of the former Glynn Canning 
Company. All depths refer to mean low water. Mean 
tidal range on the bar is 6.5 feet, at the City of 
Brunswick 7.3, and 7.6 feet at the upper end of the 
harbor. For further details see Annual Report for 
1962. 
Local cooperation. Complied with to date. 
Terminal facilities. Eighteen wharves and piers, almost 
all privately owned, have a berthing space of 
7,530 linear feet. The Port of Brunswick and the State 
of Georgia have a transit shed and modern docks 
with 1,640 feet of berthing space (three general 
cargo berths) on East River. For further details see 
Port Series No. 14, Corps of Engineers (revised 
1990). 
Operations and results during fiscal year. 
Maintenance: The District used "M" Operating 
Company to dredge the East River during the second 
and fourth quarters of the fiscal year. Their 
dredge, the "Stuart", removed a total of 650,000 cubic 
yards of silt at a total cost of $586,900. The work 
for others consisted of dredging in front of three of 
Georgia Ports Authority's (GPA) docs at the contract 
8-3

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
price. The GPA then reimbursed the District for the 
work performed outside of the Navigation channel. 
The District prepared plans and specifications for 
the FY 93 Brunswick Entrance Channel Contract. 
Total operation and maintenance cost amounted to 
$2,234,587 for FY 92. (See Table 8-A for Cost and 
Financial Statement.) 
Condition at end of fiscal year. The existing project 
was completed in December 1960. General 
condition of the harbor works is satisfactory, providing 
maintenance dredging continues. The notice on 
the Final Environmental Impact Statement appeared 
in the Federal Register October 3, 1975. Authorized 
depths were maintained throughout the fiscal year. 
Costs for existing completed project to September 
30, 1992 were $78,752,596 of which $6,947,412 was 
for new work and $71,805,184 was for maintenance. 
(See Table 8-A for Cost and Financial Statement.) 
5. SAVANNAH HARBOR, GA 
Location. Harbor entrance is 75 statute miles south 
of Charleston, SC, and 70 miles north of Brunswick 
Harbor, GA. (See NOAA Chart 11512, formerly 
Coast and Geodetic Survey Chart 440.) 
Previous projects. For details see page 1810 of 
Annual Report for 1915 and page 578 of Annual Report 
for 1938. 
Existing project. The project provides for a channel 
40 feet deep and 600 feet wide across the ocean bar 
about 7.0 miles; 38 feet deep and 500 feet wide to 
the vicinity of Garden City (Georgia Ports Authority 
terminal) and 36 feet deep and 400 feet wide to the 
vicinity of the Savannah Sugar Refinery of Savannah 
Foods and Industries, Inc. about 22.6 miles; and 30 
feet deep and 200 feet wide to a point 1,500 feet below 
the Atlantic Coastal Highway Bridge, about 1.5 
miles, a total length of 31.1 miles; Fig Island and 
Marsh Island Turning Basins 34 feet deep by 900 
feet wide by 1,000 feet long in the vicinity of the Seaboard 
Coast Line terminal, and American Oil Company 
terminal; Kings Island Turning Basin 38 feet 
deep by 1,500 feet wide by 1,600 feet long in the vicinity 
of the Garden City terminal of the Georgia 
Ports Authority; Argyle Island and Port Wentworth 
Turning Basins 30 feet deep by 600 feet long near 
Savannah Refinery terminal and at the extreme upper 
limit of the project near the Continental Can 
Company terminal; and a 1,200 foot long by 1,050 
foot wide by 40 foot deep Oyster Bed Island Turning 
Basin in the vicinity of Georgia Ports Authority's 
LASH facility. The project also provides for sediment 
control works consisting of a tide gate structure 
across Back River; a sediment basin 40 feet 
deep, 600 feet wide; about 2 miles long, with an entrance 
channel 38 to 40 feet deep and 300 feet wide; 
a drainage canal across Argyle Island 15 feet deep 
and 300 feet wide; control works and canals for supplying 
fresh water to the Savannah National Wildlife 
Refuge; and facilities to mitigate damages to presently 
improved areas other than refuge lands. Mean 
range of tide is 7.9 feet at the upper end of the harbor 
and 6.9 feet at the lower end. Extreme ranges are 
about 11.1 and 10.7 feet, respectively 
The tide gate structure across Back River was taken 
out of operation as of March 1991. The drainage canal 
across Argyle Island, which was part of the original 
tide gate project, was closed as of April 1992 by 
the new cut closure contract. The cost of this contract 
was $1,531,847. 
Local cooperation. Local interests must provide 
suitable disposal areas and retaining dikes for construction 
and future maintenance of the project. The 
Chatham County Board of Commissioners, as local 
assurers, have met all requirements to date. 
Terminal facilities. Sixty-one piers and wharves 
adequately serve existing waterborne commerce of 
the port. These facilities, with use of dolphins, have 
a combined berthing space of 46,930 linear feet at 
mean low water. Included in the berthing space are 
six container berths with 271 acres of handling area. 
All have railway and highway connections. LASH facilities 
are located at the entrance to the harbor and 
have depths ranging up to 38 feet mean low water. 
The berthing space of LASH facilities is included in 
the above combined berthing space. For further details, 
see Port Series No. 14, Corps of Engineers (revised 
1982) and Annual Report for 1990. 
Savannah Harbor Widening. The Savannah Harbor 
Widening project was awarded on 28 September 
1990 for $7,735,512. The scope of work included 
widening 5.6 miles of channel from 400-500 feet 
with 1.8 million cubic yards of material dredged after 
demolition and removal of structures in the riverbank. 
Chatham County, the local assurer, completed 
real estate acquisition prior to award expending 
$3,688,000 in providing LERR as required by the 
LCA. 
Construction was completed on 10 April 1992. Significant 
difficulty was experienced by the contractor 
in removing debris and obstructions, the quantity of 
which was only partially quantified. Six additional 
parcels of real estate had to be acquired during the 
project due to greater than anticipated amounts of 
bank sloughing. One parcel required deletion from 
the contract of 1000 feet of the widened channel due 
to impacts to an existing radio tower. This work will 
be completed under the Savannah Harbor Deepening 
Contract. The total Federal Cost exlusive of con- 
8-4

SAVANNAH, GA, DISTRICT 
tract claims and additional real estate costs was 
$8,270,000 and the Non-Federal cost was 
$6,441,000. A final modification of approximately 
$2.7 million for excessive dredge downtime due to 
debris will be needed to close the contract. 
A PAC report was prepared to seek authorization to 
conduct additional widening in the vicinity of the 
north pier of the old Talmadge Bridge once the north 
pier structure is removed. 
Maintenance. The District dredged the Savannah 
Harbor during FY 92, the navigation channel from 
Station 40 to 112 + 500. The Ship Channel contract 
removed 1,884,327 cubic yards of sediment at a 
cost of $2,167,864. This work was performed by 
Southern Dredging Company. 
Total costs for operation and maintenance for the 
fiscal year was $4,679,913 which included such 
items as salinity monitoring, surveying, cultural resources. 
The Tidegate was taken out of operation in 
1992 to decrease salinity levels in wildlife refuge. In 
addition to this action a Section 1135 program was 
executed to close New Cut. 
Condition at the end of the fiscal year. Training 
walls, jetties, and other structures are in fair condition. 
Authorized channels are maintained by a 
planned dredging program with work at critical areas 
when necessary. The notice on the Final Environmental 
Impact Statement appeared in the Federal 
Register June 25,1976. Notices of availability 
on two Final Supplements to the Environmental Impact 
Statement appeared in the Federal Register 
September 25, 1978, and January 8, 1980. 
6. SAVANNAH RIVER BELOW AUGUSTA, GA 
Location. Savannah River is formed by the confluence 
of the Tugaloo and Seneca Rivers on the 
boundary line between South Carolina and Georgia. 
It flows southeast 314 miles, forming the boundary 
line between two states, and empties into the Atlantic 
Ocean 16.6 miles below Savannah, GA. (See 
NOAA Charts 11514 and 11515, formerly Geological 
Survey maps of South Carolina and Georgia.) 
Previous project. For details see page 1813 of Annual 
Report for 1915 and page 581 of Annual Report 
for 1938. 
Existing project. The authorized project provides 
for a channel 9 feet deep and 90 feet wide (at ordinary 
summer flow of 5,800 second-feet at Augusta, 
GA) from the upper end of the Savannah Harbor to 
the head of navigation at Augusta, above the 13th 
Street Bridge (R.M. 202.6), a total distance of about 
181 miles. A lock and dam is located approximately 
15 miles below the upper limit of the project at New 
Savannah Bluff. Improvement is to be obtained by 
construction of contraction works, closure of cutoffs, 
bank protection, dredging, removal of snags, 
over hanging trees and wrecks, and open-river 
regulation. Mean tidal variation at the mouth of the 
river is 7 feet. Freshet variation above the normal 
pool level (elevation 114.5 mean sea level) of New 
Savannah Bluff Lock and Dam at mile 187 is ordinarily 
about 13 feet with an extreme of 34 feet. Due to 
lack of coimmercial use, the river has not been 
dredged since FY 79. 
Local cooperation. Complied with to date. 
Terminal facilities. The only water terminals served 
by this improvement are at Augusta, Sylvania, and at 
or near Savannah. Augusta provided a municipal 
dock valued at $50,000 and Georgia Ports Authority 
constructed a state port at Augusta, GA, costing 
about $418,000. These facilities were expanded in 
1965 at an additional cost of about $250,000. These 
are supplemented by natural landings along the 
river and extensive facilities at Savannah. 
Operations and results during fiscal year. In general, 
open-channel works are in good condition. 
The notice on the Final Environmental Impact Statement 
appeared in the Federal Register February 18, 
1977. The total cost for the year was $85,943.71. 
There were no dredging projects during this fiscal 
year. 
7. RECONNAISSANCE AND CONDITION SURVEYS 
Survey Section performed condition surveys on the 
following active O&M navigation projects: 
Savannah Harbor 
Brunswick Harbor 
AIWW 
Savannah River Below Augusta 
General regulatory function expenditures for the fiscal 
year were $2,349,529. 
8. OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Table 8-C.) 
9. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Funds of $18,000 were received under Section 107 
of the Continuing Authorities Program for small navigation 
to conduct an initial appraisal of the need for 
deepening the Port Wentworth channel of upper 
Savannah Harbor. 
8-5

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Beach Erosion Control 
10. BEACH EROSION CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
11. TYBEE ISLAND, GA 
Location. Tybee Island is located directly south of 
the Savannah River entrance, about 17 miles east of 
the City of Savannah, GA. (See NOAA Charts 11512, 
11513, and 11509, formerly U. S. Coast and Geodetic 
Survey Charts Nos. 440, 1240, and 1241, and 
on maps included in HD 92-105, 92nd Cong.) The 
only portion of the island that has developed is 
bounded on the north by the south channel of the 
Savannah River, on the east by the Atlantic Ocean, 
and on the south and west by Tybee Creek and other 
small tidal streams. This area, hereinafter referred to 
as "Tybee Island," is occupied by the City of Tybee 
Island. The ocean face of this area has a wide sandy 
beach. Tybee Island is about 3.5 miles long from its 
northerly tip to the mouth of Tybee Creek with an average 
width of about 0.5 mile. Behind the beach lies 
a line of sand dunes, a number of which have been 
removed during the years to make room for improvements 
and for various other reasons. Those that remain 
are from 10 to 20 feet high. The ground elevation 
west of the dunes is from 10 to 18 feet and 
slopes westward to the salt marsh. 
Existing project. The approved project plan of improvement 
provides for an 800-foot rock groin at the 
north end of the island, with a 225-foot tie-in to high 
ground. An additional 1,200-foot extension of this 
groin is deferred, as are two additional intermediate 
groins (480 feet long); these will be added at a later 
date, if needed. The plan also provides for the initial 
restoration of approximately 13,300 feet of beach, 
from the vicinity of 18th Street to the terminal groin 
located at the northern end of the island. Periodic 
nourishment will be provided as needed to maintain 
suitable beach dimensions. In 1981, the plan was 
modified and now calls for the addition of a groin at 
the south end and modification and rehabilitation of 
the north rock groin and renourishment. 
Local cooperation. Local interests must: (a) contribute 
in cash the required percentage of the first 
cost (including costs for construction, engineering 
and design, and administration; and excluding the 
cost of lands, easements, rights-of-way and relocation) 
of all items of work to be provided by the 
Corps of Engineers. The local contribution is presently 
estimated at 51.0 percent to be paid in a lump 
sum prior to start of construction or in installments 
prior to the start of pertinent work items in accordance 
with construction schedules as required by 
the Chief of Engineers, the final apportionment of 
cost to be made after the actual costs have been determined; 
(b) provide maintenance and repair of the 
groins, and provide (after the first 10 years of project 
life) periodic nourishment of the restored beach as 
may be required to serve the intended purpose during 
the life of the project; (c) provide without cost to 
the United States all lands, easements, rights-ofway, 
and relocations required for construction and 
subsequent nourishment of the project; (e) control 
water pollution to the extent necessary to safeguard 
the health of bathers; and (f) provide without cost to 
the United States access and facilities necessary 
for realization of the public benefits upon which Federal 
participation is based, and maintain continued 
public use of the beach and administer it for public 
use during the life of the project, and provide further 
that construction on the project shall not be started 
until local interests furnish lands for beach access 
and parking, satisfactory to the Chief of Engineers, 
for the reach from First Street to the terminal groin. To 
date, local cooperation is being provided as required. 
Condition at the end of the fiscal year. In January 
1987, the South Groin contract was completed at a 
cost of $607,392. In February 1987, the first periodic 
renourishment contract was awarded, calling for the 
placement of approximately 1 million cubic yards of 
sand on two reaches of the island; the south end 
from the mouth of Tybee Creek to 14th Street, and 
the north end from the North terminal groin to about 
6th Street. The contract was completed in May 1987 
at a contract cost of $1,988,843. A Beach monitoring 
program has been performed for three years to 
monitor the performance of the design. The Local 
Sponsor has invested over $200,000 in' additional 
funds for the implementation of a dune building program 
for the North and South ends of the islands. 
Fiscal year costs were $53,953. A reevaluation 
study under Section 934 WRDA 86 was initiated in 
1990 for the Tybee Island Beach Erosion Control 
Project. The purpose of the study is to determine if 
the authorized Tybee Island Beach Erosion Control 
Project should be extended to a project life of 50 
years, and determine if the Federal Government 
should continue to participate in the project. The 
study is using current Federal policy and economic 
guidelines to evaluate the economic and environmental 
feasibility of additional periodic beach nourishment. 
The study is also considering the feasibility 
of adding the south tip beach, from the existing 
south terminal groin to the south end of the island, to 
the authorized project. The study is scheduled for 
completion in February 1993. 
FLOOD CONTROL 
12. SAVANNAH RIVER BASIN AT OATES CREEK, 
GEORGIA. Oates Creek is a major drainage outlet 
for flood water from an urban area of Augusta, GA. A 
flood control study of Oates Creek was authorized 
8-6

SAVANNAH, GA, DISTRICT 
and completed as part of the Savannah River Basin 
study. The Oates Creek study area is located just 
south of Augusta, in Richmond County. 
The recommended plan is a channel and bridge 
modification flood control plan and has received 
support from Federal, State, and local governmental 
agencies with no environmental opposition. In 1987, 
the local sponsor, Richmond County, expressed 
support for the project and intent to participate financially. 
The plan consists of improvements to approximately 
12,300 feet of channel and consists of 
concrete-lined channels, grass-lined channels, a 
low levee, modifications of bridges and culverts, 
and relocation of utilities. The CP&E effort began in 
October 1983 and consisted of the preparation of a 
General Design Memorandum. Upon the completion 
and approval of the General Design Memorandum 
(Sep 1986), negotiations were initiated with the 
local sponsor to develop a Local Cooperation 
Agreement (LCA). The LCA was signed by Richmond 
County and the Assistant Secretary of the 
Army (Civil Works) on 10 March 1988. Fiscal year expenditures 
were $2,486,766. Conditions at end of 
FY92: During FY92, the channel construction contract 
was completed. At the end of the FY, claims 
were being finalized for the Channel Construction 
contract. Anticipate project completion date, with 
fiscal document closeout, i.e. April 1993. 
13. INSPECTION OF COMPLETED FLOOD CONTROL 
PROJECTS 
Expenditures for inspections of completed flood 
control projects amounted to $19,725. (See Table 
8-D.) 
14. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
(See Table 8-D) 
15. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
These Flood Damage Reduction activities are 
acomplished under the authority of Section 205, 
Flood Control Act of 1948 (Public Law 858, 80th 
Congress) as amended. During FY 92 a total of 
$367,741.86 was spent on pre-authorization flood 
damage reduction study effort. Study efforts during 
the FY were as follows: Augusta Canal/Lake 
Olmstead, Auguta, GA, completed Reconnaissance 
Phase -$10,000; Dry Branch Creek, Twiggs 
County, GA completed Reconnaissance Phase - 
$8,930.68; Johnson County, GA completed Reconnaissance 
Phase - $8,000; Kalmia Drainage Basin, 
Aiken County, SC, completed Reconnaissance 
Phase - $26,244.44; Nutgrove Drainage Basin, 
Aiken County, SC, completed Reconnaissance 
Phase - $6,000; Ocmulgee River Levee, Macon, 
GA, Feasibility Phase - Cost Shared funding, 
$81,285.03 (Federal and $88,084.07 (Non-Federal); 
Raes Creek, Augusta, GA, completed Reconnaissance 
Phase - $26,365.95; Reid Creek, Columbia 
County, GA, completed Reconnaissance Phase - 
$14,549.76; Rocky River, Augusta, GA completed 
Reconnaissance Phase - $4,949.21; Springfield 
Canal, Savannah, GA, Plans and Specifications 
Phase -$212,458.16; Wise Hollow Drainage Basin, 
Aiken County, SC, completed Reconnaissance 
Phase - $6,000. 
Emergency Streambank and Shoreline Protection 
16. EMERGENCY STREAMBANK AND SHORELINE 
PROTECTION UNDER SPECIAL AUTHORIZATION. 
During the FY two Emergency Streambank protection 
activities were carried out under the authority of 
Section 14 of the Flood Control Act of 1946, as 
amended. A Feasibility Study of erosion protecion 
at the 5th Street Docks along the Savannah River, in 
Augusta, GA was completed at a cost of $3,047.04. 
An initial Feasibility Study of Streambank erosion 
and protection at Fort Jackson, along the Savannah 
River in Chatham County, GA was begun at a cost of 
$2,207.26. 
Project Modifications for Improvement of Environment 
16A. PROJECT MODIFICATIONS FOR IMPROVEMENT 
OF ENVIRONMENT UNDER SPECIAL 
AUTHORIZATION 
These project modifications are accomplished under 
the authority of Section 1135, Water Resources 
Development Act of 1986 (Public Law 99-662) as 
amended. Environmental modification study efforts 
during FY 92 were as follows: Savannah Harbor, 
Chatham County, GA - Jasper County, SC, completed 
plans and specifications and construction - 
Cost Shared funding, $1,313,748.74 (Federal) and 
$499,783.48 (Non-Federal); Hartwell Lake, 
Stephens County, GA completed Feasibility Phase 
- $10,283.74; Thurmond Lake, McCormick County, 
SC, completed Feasibility Phase - $18,594.67. Total 
FY expenditures on these preauthorized studies 
were $1,842,241.06. 
16B. LOWER SAVANNAH RIVER BASIN ENVIRONMENTAL 
RESTORATION STUDY 
A Reconnaissance Study was initiated on the need 
to conduct environmental restoration activities on 
various cut off bends and oxbow channels formed 
8-7

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
by previous navitation improvements for the Savannah 
River Below Augusta inland navigation project. 
Multiple-Purpose Projects Including Power 
17. SAVANNAH RIVER BASIN, GA AND SC 
Location. Works covered by this project consist of 
a series of 11 dams and lakes on the Savannah 
River and its tributaries in GA and SC. (See Geological 
Survey maps of GA and SC.) 
Existing project. The Flood Control Act of 1944 approved 
the general plan for comprehensive development 
of the Savannah River basin for flood control 
and other purposes (H.D/ 657, 78th Cong., 2d sess.) 
and authorized construction of the J. Strom Thurmond 
Dam and Reservoir Project on the Savannah 
River in Georgia and South Carolina as the initial 
step of this development. The Flood Control Act of 
1950 authorized construction of Hartwell Lake under 
the general plan. Richard B. Russell (formerly Trotters 
Shoals) was authorized for construction by the 
Flood Control Act of 1966 at an estimated cost of 
$84,900,000. J. Strom Thurmond Dam and Reservoir, 
Hartwell Lake, and Richard B. Russell Dam and 
Lake are the only projects in the comprehensive 
plan that have been constructed. (See Table 8-E on 
Dams and Lakes.) 
Duke Power Company has completed construction 
on the Keowee-Toxaway power complex on the 
Keowee River in the headwaters of Hartwell Lake 
and construction of the Jocassee pump-storage 
power project in the headwaters of the Keowee- 
Toxaway project. The Keowee-Toxaway power 
complex is located on the Newry-OId Pickens site 
identified in the approved comprehensive plan. Individual 
reports on J. Strom Thurmond Dam and Reservoir, 
Hartwell, and Richard B. Russell Lakes follow. 
Local cooperation. None required. 
17A. J. STROM THURMOND DAM AND RESERVOIR, 
(formerly Clarks Hill Lake) GA AND SC 
Location. J. Strom Thurmond Dam and Reservoir is 
located at mile 237.7 on the Savannah River about 
22 miles upstream from Augusta, GA. (See Geological 
Survey maps of GA and SC.) 
Existing project. The authorized project provides 
for construction of J. Strom Thurmond Dam and Reservoir, 
the final cost of which was $79,156,300. The 
dam has a concrete section 2,282 feet long with a 
maximum height of 200 feet and a controlled spillway 
1,096 feet long. The concrete section is flanked 
on the west side by a rolled-earth embankment of 
2,069 feet and on the east side by a similar embankment 
of 1,329 feet. 
The total length of the dam is 5,680 feet. The lake 
covers 71,100 acres at maximum power pool elevation 
330. It provides a total storage capacity of 
2,900,000 acre-feet allocated as follows: flood 
control 390,000 acre-feet; hydropower 1,045,000 
acre-feet; dead storage 1,465,000 acre-feet. 
Seven 40,000-kilowatt generators have a combined 
generating capacity of 282,000 kilowatts with an average 
annual output of 700 million kilowatt-hours of 
electrical energy. 
Local cooperation. None required. 
Operations and results during fiscal year. Gross 
generations of electric energy for the period was 
595,476,300 kilowatt-hours, most of which was delivered 
to the Southeastern Power Administration. 
There were no flood damages prevented or incurred 
in FY 92.. 
Maintenance: Operation and maintenance costs 
during the fiscal year amounted to $7,319,291. The 
notice of availability on the Final Environmental Impact 
Statement on J. Strom Thurmond Dam and 
Reservoir Operation and Maintenance appeared in 
the December 18, 1981 Federal Register. In FY 92 
5,787,000 persons visited the facility. 
Condition at the end of the fiscal year. Construction 
is complete except for providing additional recreational 
development.(See Table 8-A for Cost and 
Financial Statement.) 
17B. HARTWELL LAKE, GA AND SC 
Location. Hartwell Lake is on the Savannah River 
305 miles above its mouth and 89 miles upstream 
from Augusta, GA.(See Geological Survey maps of 
GA and SC.) 
Existing project. The dam is a concrete gravitytype 
structure 1,900 feet long with a maximum height 
of 204 feet and a controlled spillway 568 feet in 
length. The concrete section is flanked on the east 
and west abutments by earth embankments totaling 
13,390 feet in length and by a saddle dike 2,590 feet 
long also on the west side. Total length of the dam is 
17,880 feet. At maximum conservation pool elevation 
of 660 feet the lake covers 55,950 acres. Total 
capacity of the lake is 2,843,000 acre-feet of storage 
allocated as follows: flood control - 293,000 
acre-feet, hydropower - 1,416,000 acre-feet, dead 
storage - 1,134,000 acre-feet. Four 66,000 kilowatt 
generators having a generating capacity of 264,000 
kilowatts were installed initially with provisions for a 
future unit. A fifth 80,000 kilowatt generating unit has 
been installed which increased the rated capacity to 
344,000 kilowatts. 
8-8

SAVANNAH, GA, DISTRICT 
Local cooperation. None required. 
Operations and results during the fiscal year. 
Gross generation of electrical energy for the period 
amounted to 450,579,000 kilowatt-hours, most of 
which was delivered to the Southeastern Power Administration. 
There were no flood damages prevented 
or incurred in FY 92. 
Maintenance. Operation and maintenance costs 
during the fiscal year amounted to $7,372,891. The 
notice on the Final Environmental Impact Statement 
on the operation and maintenance of Hartwell Dam 
and Lake appeared in the Federal Register on 
August 21,1978. Approximately 15,688,000 persons 
visited the lake in FY 92. During FY 92, funds were 
expended to examine the need and justification for 
major rehabilitation of the four original units at the 
Hartwell power facility. 
17C. RICHARD B. RUSSELL DAM AND LAKE, GA 
AND SC (Formerly Trotters Shoals Lake, GA AND 
SC) 
Location. Richard B. Russell Dam is located on the 
Savannah River 275.1 miles above its mouth, 29.9 
miles below Hartwell Dam, and about 37.4 miles 
above J. Strom Thurmond Dam (formerly Clarks Hill 
Dam). (See NOAA Survey maps of GA and SC.) 
Existing project. The authorized project provides 
for construction of Richard B. Russell Dam and Lake 
substantially in accordance with the recommendations. 
The latest approved (fiscal year 1992) cost estimate 
for the project is $569,000,000 of which 
$444,590,000 is for construction; $28,594,000 for 
lands and damages; $4,683,000 for cultural resources; 
and $97,016,000 for engineering/design, 
supervision/administration, and all project studies 
including environmental. Approval was received in 
January 1977 to include minimum provisions for 
pumped storage. 
A Feasibility Report and Final Environmental Impact 
Statement to address the installation and operation 
of four 90 MW (uprated from 75 MW) reversible 
pump-turbines were prepared in 1979 with the Record 
of Decision signed in August 1980. The Richard 
B. Russell Fish and Wildlife Mitigation Plan was 
completed in 1981, approved by the Assistant Secretary 
of the Army (Civil Works) in September 1982, 
and the provisions are being implemented. 
Since 1986, the District has conducted various fishery 
studies in the Russell tailrace and J. Strom Thurmond 
Lake (formerly Clarks Hill Lake) downstream. 
In addition, the District is conducting water quality 
studies, hydraulic modeling, and an evaluation of 
various fish protection measures associated with 
hydroelectric projects. The results of these study efforts 
have been used to evaluate the need to develop 
fish protection at the Richard B. Russell Project 
associated with pumped storage operations. 
This evaluation is presented in a supplement to the 
Final Environmental Impact Statement (SEIS) on 
pumped storage. The record-of-decision (ROD) 
was signed September 1991. Installation of pumped 
storage is complete; environmental testing is 
scheduled from Feb 93 thru Oct 94. 
South Carolina McCalla State Park, (a cost-shared 
Recreation Facility) is scheduled to be awarded in 
FY93 or FY 94 pending receipt of State funding. 
During FY 92 408,023,000 kilowatts of power were 
generated. 
Maintenance. The operation and maintenance cost 
for the fiscal year amounted to $4,784,343. These 
funds were for management of lake and power activities. 
Approximately 1,027,700 persons visited 
the lake in FY 92. 
Condition at the end of fiscal year. The project is 
94 percent complete. 
Costs of project to September 30, 1992 were 
$566,579,288 of which $533,499,066 was used for 
new work and $33,080,222 for maintenance. (See 
Table 8-A for Cost and Financial Statement.) 
During FY 92, PED funds were used to locate and 
study potentially suitable Georgia and South Carolina 
lands to be acquired as R. B. Russell mitigation 
lands to compensate for wildlife habitat lost from 
construction of Richard B. Russell Dam and Lake. In 
accordance with the 1982 R. B. Russell mitigation 
plan as authorized by Section 601(a) of the Water 
Resources Development Act of 1986 (PL. 99-662), 
approximately 10,100 acres would be acquired in 
South Carolina and an additional 11,400 acres acquired 
in Georgia. The District worked closely with 
the U. S. Fish and Wildlife Service, the South Carolina 
Wildlife and Marine Resources Department, and 
the Georgia Department of Natural Resources to locate 
and study suitable tracts. Acquisition of land in 
FY 92 in South Carolina consisted of the 3,408 acre 
Donnelly Wildlife Management Area in Colleton 
County. In Georgia, the 1,153 acre R. E. Towns Tract 
in Screven County was acquired along with the 
8,042 acre Di-Lane Plantation in Burke county. Total 
project funding through FY 92 is $11,691,000. The 
acquired tracts are intensively being managed for 
wildlife by the South Carolina Wildlife and Marine 
Resources Department and the Georgia Department 
of Natural Resources respectively. 
8-9

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
18. WEST POINT LAKE, CHATTAHOOCHEE 
RIVER 
Location. The West Point Lake is located on the 
Chattahoochee River, 2.8 miles upstream from West 
Point, GA, and was authorized by the Flood Control 
Act of 1962 (H.D. 570, 87th Cong., 2d sess.). The 
project was designed and constructed for flood control, 
power, recreation, fish and wildlife development, 
and stream flow regulation for downstream 
navigation. Design and construction was accomplished 
by the Savannah District, U. S. Army Corps 
of Engineers for the Mobile District, U.S. Army Corps 
of Engineers. For more detail, see the Mobile, AL, 
District's Report of the Chief of Engineers, U. S. 
Army 1987. 
General Investigation 
19. SURVEYS 
Fiscal year expenditures were $773,400.44 of which 
$364,083.77 was for navigation studies; $9,441.94 
for flood control studies; $57,911.68 for special investigations; 
$57,911.68 for coordination with other 
agencies; $16,324.03 for dam safety criteria studies, 
and $25,536.53 for review of FERC Licenses activities. 
Expenditures for Planning Assistance to 
States were $13,063.59, Shoreline Protection Study 
$226,140.42 and North American Waterfowl Management 
Plan were $2,986.80. 
20. COLLECTION AND STUDY OF BASIC DATA 
During FY 92, under the Flood Plain Management 
Services and Technical Services programs, flood 
hazard related information and assistance were provided 
to state and local goverments on a nonreimbursable 
basis and to other Federal agencies and 
private persons on a cost recovery basis. Federal 
agencies and private persons were not charged for 
services or information that could be provided in 
less than 10 minutes. Total FY 92 expenditures were 
$72,498.34 for Flood Plain Management Services 
and $80,754.92, for Technical Services. These services 
included flood hazard information, flood plain 
analysis and continued support to the hurricane 
evacuation planning efforts along the Coast. 
21. RESEARCH AND DEVELOPMENT 
No funds were expended for research and development 
during the fiscal year. 
22. CONTINUATION OF PLANNING AND 
ENGINEERING 
Savannah Harbor Deepening. Authorized in 
WRDA 1992, the Savannah Harbor Deepening project 
calls for the deepening of the channel 4 feet 
from -40 ft mean low water (mlw) to -44 ft mlw, from 
Station -14 + 000 + -60 + 000, and -38 ft mlw to -42 
ft mlw from -14+000 to + 103+ 000. The Georgia 
Ports Authority (GPA), as local sponsor, has approved 
a draft Local Cooperative Agreement (LCA), 
which is currently in HQUSACE for review and approval. 
Because of a need for the project by the sponsor, 
the GPA has offered to advance to the government 
the necessary funds to allow the project to proceed 
prior to the appropriation of Federal construction 
funds. Reimbursement of the Federal share will not 
take place until the project has been completed and 
all audits are complete. The current schedule calls 
for the advertisement of the Phase I contracts upon 
the signing of the LCA, with construction beginning 
in FY93. The estimated cost of the project is 
$50,050,000. With the accelerated schedule, the 
project is scheduled for completion March 1994. 
8-10

SAVANNAH, GA, DISTRICT 
TABLE 8-A 
See 
Section 
in Text Project 
1. Altamaha, Oconee, 
& Ocmulgee Rivers, 
GA 
2. Aquatic Plant 
Control (1965 
R&H Act) 
3. Atlantic Intracoastal 
Waterway 
between Norfolk, 
VA, and the St. 
John's River, FL 
4. Brunswick Harbor, 
GA 
5. Savannah Harbor, 
GA 
6. Savannah River 
below Augusta, 
GA 
11. Tybee Island, GA 
12. Oates creek, 
Richmond County, 
GA 
13. Inspection of 
Completed Flood 
Control Works 
17.A J. Strom Thurmond 
Dam and Reservoir, 
GA and SC 
COST AND FINANCIAL STATEMENT 
Total Cost 
to 
Funding FY 89 FY 90 FY 91 FY 92 Sep. 30. 1992 - 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
75,000 
39,402 
2,036,500 
2,010,362 
117,000 
210,925 
651,500 
1,063,076 
136,000 
167,606 
3,581,000 
3,620,820 
11,191 
153,550 
212,123 
1,800,000 
271,390 
17,000 
16,852 
)00 
512 
51,000 
74,873 
49,0 
63,5 
968,7 
976,6 
996,7 
1,160,5 
2,972,1 
2,968,1 
205,0 
640,9 
7,125,6 
6,958,4 
28,2 
210,7 
216,8 
200,C 
23,4 
4,036,( 
2,466,7 
17,C 
14,C 
50,000 
97,055 
958,096 
958,096 
2,326,000 
2,285,093 
95,000 
70,801 
2,260,000 
2,234,587 
2,951,000 
3,640,529 
4,458,000 
4,679,913 
6,790,031 
6,790,031 
86,000 
67,028 
30,000 
53,953 
2,568,000 
2,486,766 
16,000 
19,725 
84,884,440 
18,595 
821,457(1) 
821,457(1) 
1,917,982(2,3) 
1,917,982(2,3) 
861,159 
823,678 
958,096(4) 
958,096(4) 
24,064,507(5) 
24,019,518(5) 
6,839,798(6) 
7,018,213(6) 
71,944,928(7) 
71,805,184(7) 
54,656,721(8) 
53,934,525(8) 
174,186,693(9) 
173,949,758(9) 
6,790,031(10) 
6,790,031(10) 
18,196,771 
18,153,352 
4,510,249(11) 
4,499,870(11) 
9,025,000 
8,822,547 
329,064 
328,326 
84,884,440(12) 
84,879,504(12) 
10,508,885 7,307,939 6,796,667 7,256,000 117,466,345(13) 
10,858,490 6,997,183 6,855,050 7,319,291 117,027,799(13) 
8-11 
X86 253,000 
81 284,978 
X50 583,440 
514 642,937 
134 3,568,000 
119 3,564,608 
)00 3,257,000 
)55 2,969,297 
353 9,585,000 
X59 9,402,238 
?74 -- 
729 76,000 
391 85,944 
)00 -77,000 
X22 65,246 
)00 273,000 
735 3,372,056 
)46 58,000 
)82 56,660 
-- 43,150 
-- 20,646

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 8-A (Cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30. 1992 
17.B Hartwell Lake, GA 
and SC 
17.C Richard B. Russel 
Dam and Lake, GA 
and SC (Formerly 
Trotters Shoals) 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
-26,878 
-- -60,000 
280 -- 
-3,000 115,874,985(14,15) 
-114 115,874,985(14,15) 
7,566,035 8,461,499 7,591,667 7,524,900 107,186,527(16) 
8,003,569 7,971,044 7,763,926 7,372,891 107,265,834(16) 
19,983 1,429 
27,950 
21,236 
20,000 
10,284 
12,800,000 20,751,000 12,208,000 14,911,000 
31,104,225 18,772,385 17,067,848 15,152,291 
3,419,698 4,570,705 4,513,666 4,643,900 
3,497,898 4,264,427 4,669,220 4,784,343 
6,666,950 
6,640,536 
535,169,509 
533,499,066 
23,992,191 
33,080,222 
1. Includes $760,610 for previous projects. 
2. Includes $111,950 for previous projects. 
3. Does not include $69,356 contributed funds. 
4. Includes $194,497 for previous projects. 
5. Includes $134,789 for previous projects. Does 
not include $35,000 appropriated but 
unexpended of contributed funds in FY's 86 
and 87. 
6. Includes $643,456 for previous projects and 
$97,521 expended from Public Works Funds 
for existing project. Does not include $10,000 
contributed funds. 
7. Includes $54,414 for previous projects, $4,995 
expended from Public Works Funds for 
existing project, and $2,150,000 under 1983 
Job Bill Act. Does not include contributed 
funds by Brunswick and Georgia Port 
Authority. 
8. Includes $7,260,384 for previous projects. 
Does not include $46,847 for removal of 
sunken vessels or contributed funds. 
9. Includes $298,894 for previous projects and 
$62,727 contributed funds. 
10. Includes $93,480 for previous projects and 
$1,634,562 from Public Works Fund. 
11. Does not include $61,856.45 contributed funds. 
12. Does not include $395,634 accelerated Public 
Works Funds. Includes $4,558,613 appropriated 
under Code 710. Also includes $1,000,000 
expended under the 1983 Job Bill Act. 
13. Includes $576,665 under special recreation use 
fees and $736,000 under the 1983 Job Bill Act. 
14. Includes $17,515,000 appropriated for 
construction of 5th Unit of which $17,469,002 
has been expended. 
15. Does not include $276,200 accelerated Public 
Works Funds. Includes $4,861,000 appropriated 
under Code 710 of which $4,851,306 has been 
expended and $545,000 expended under the 
1983 Job Bill Act. 
16. Includes $797,558 expended special recreation 
use fees. 
8-12

SAVANNAH, GA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorized 
in Text Act Project and Work Authorized Documents 
1. July 25, 1912 
& March 2, 1945 
2. Oct. 27, 1965 
Section 302 
3. June 3, 1896 
Mar. 3, 1899 
July 13, 1892 
Mar. 3, 1905 
July 25, 1912 
Aug. 8, 1917 
Mar. 2, 1919 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 26, 1937 
Aug. 26, 1937 
June 20, 1938 
Mar. 2, 1945 
Oct. 15, 1981 
4. Mar. 3, 1879 
ALTAMAHA, OCONEE, AND OCMULGEE RIVERS, GA 
Channel 3 feet deep and 60 to 100 feet wide. HD 443,62D Cong., 2d sess. 
HD 610, 77th Cong., 2d sess. 
AQUATIC PLANT CONTROL (R&H ACT 1962) 
Provides for control and progressive eradi- HD251, 89th Cong., 1st sess. 
cation of noxious aquatic plant growths. 
ATLANTIC INTRACOASTAL WATERWAY 
BETWEEN NORFOLK, VA, AND ST. JOHNS 
RIVER, FLA, (SAVANNAH DISTRICT) 
Section from Beaufort, SC, to Savannah, GA HD 295, 53d Cong., 3d sess. 
Route No. 2 adopted. 
Route No. 1 adopted. HD 295, 53d Cong., 3d sess. 
Section from Savannah, GA, to Fernandina, HD 41, 52d Cong., 1st sess. 
FL. Original 7-foot channel. 
Provided for Skidaway Narrows. HD 450, 58th Cong., 2d sess. 
Incorporated alternative routes previously HD 1236, 60th Cong.,2d sess. 
improved as separate projects and the 
auxiliary channels. 
Section from Cumberland Sound, GA and FL to 
St. Johns River, FL. Consolidation of the 
3 sections shown above, into "Waterway between 
Beaufort, SC, and St. Johns River, FL." 
Section from Beaufort, SC, to Cumberland HD 581, 63d Cong., 2d sess. 
Sound, GA and FL. Removing logs and snags 
from Generals Cut. 
Improving Back River to provide a channel 7 HD 1391, 62d Cong., 3d sess. 
feet deep and 150 wide. 
Channel 75 feet wide between Beaufort, SC, SD 178, 68th Cong., 2d sess. 
and Savannah, GA. 
Channel from Baileys Cut to Dover Creek. SD 43, 71st Cong., 2d sess. 
A 7-foot protected channel around St. Senate committee print, 74th 
Andrews Sound. Cong., 1st sess. 
A 12-foot channel between Beaufort, SC, and Rivers and Harbors Committee 
Savannah, GA, via Beaufort River and Port Doc. 6, 75th Cong.,3d sess. 
Royal Sound. 
A 12-foot channel between Savannah, GA, and HD 618, 75th Cong., 3d sess. 
Femandina, FL, various cutoffs; and 
anchorage basin at Thunderbolt, GA. 
An alternate route 9 feet deep and 150 feet HD 114, 77th Cong.,1st sess. 
wide in that part of Frederica River, GA, 
not now traversed by the main route, at no 
additional cost to the United States. 
Main channel relocated from Frederica Project authorized by Chief 
River to Mackay River in the vicinity of of Engineers under the Small 
Torras Causeway. Navigation Project Navigation Project Authority, Sec. 
107, PL 86-645 as amended. 
BRUNSWICK HARBOR, GA 
Construction of East River jetty. Annual Report, 1980, p.959. 
8-13 
TABLE 8-B

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Mar. 2, 1907 
Mar. 2, 1919 
July 3, 1930 
July 3, 1930 
June 20, 1938 
May 17, 1950 
Oct. 22, 1976 
July 14, 1981 
July 13, 1983 
Oct. 17, 1986 
5. Mar. 2, 1907 
June 25, 1910 
July 25, 1912 
Aug. 8, 1917 
Jan. 21, 1927 
Jan. 21, 1927 
Channels in the inner and outer harbors 
of 30-foot depth at mean high water, with 
widths varying from 150 feet in Academy 
Creek to 400 feet across the outer bar, 
extension of training wall in East River 
and construction of two spur dikes. 
Channels 27 feet deep at mean low water 
over the bar and at Brunswick point; and 
24 feet deep at mean low water in the inner 
harbor and provides for a cut from Academy 
Creek to Turtle River, if deemed advisable. 
A channel in Back River 230 feet deep and 
150 feet wide. 
Increased Channel dimensions of the bar, 
Brunswick Point, East River, and Turtle 
River, as given in the then existing 
project. 
A 10-foot channel in Terry Creek. 
Increased channel dimensions of the bar, 
St. Simons Sound, Brunswick River, East 
River, and Turtle River, as given in 
the existing project. 
Provides for Phase I AE&D studies for 
deepening portions of existing harbor 
(East River and Entrance Channel) and for 
provision of a navigation channel to 
Colonels Island. 
Enlargement of the maneuvering area of 
the entrance to East River and dredging 
Brunswick and Turtle Rivers to obtain 
depths authorized by the Rivers and 
Harbors Act of May 17, 1950. 
Enlargement of the East River Turning 
Basin to a length of 1,000 feet and 
and a width of 750 feet. 
Incorporated Georgia Port Authority's 
30 foot deep by 300 foot wide by 8000 
foot channel in South Brunswick River 
serving Colonel's Island into Brunswick 
Harbor Navigation Project. 
SAVANNAH HARBOR, GA 
Tentative provisions for a 26-foot channel 
from the Quarantine Station to the Seaboard 
Air Line Ry. Bridge. 
Definite provision for the 26-foot channel. 
A 21-foot channel from the Seaboard Air 
Line Ry. Bridge to the foot of Kings Island. 
A 30-foot depth from the sea to the 
Quarantine Station. 
A 21-foot channel above Kings Island. 
Channel 30 feet deep, with general width 
50 feet, from the ocean to the Quarantine 
Station, thence 26 feet deep, general width 
400 feet, to the Seaboard Air Line Ry. Bridge, 
thence 21 feet deep and 300 feet wide to 
Kings Island. Widening at West Broad and 
Barnard Streets; anchorage basin; mooring 
dolphins; regulating dam across South Channel; 
relocation of the Inland Waterway; dredging 
HD 407,59th Cong., 1st sess. 
HD 393,64th Cong., 1st sess. 
SD 57, 71st Cong., 2d sess. 
SD 132, 71st Cong., 2d sess. 
HD 690, 75th Cong., 3d sess. 
HD 110, 81st Cong.,l1st sess. 
Report of Chief of Engineers 
dated Aug. 18, 1976. 
HD 177, 97th Cong., 
1st sess. 
PL 98-360 
HR 6,99th Cong. 2d sess. 
Section 846 
HD 181,59th Cong.,lst sess. 
HD 563, 62d Cong., 2d sess. 
HD 1471, 64th Cong.,2d sess. 
HD 261,69th Cong., 1st sess. 
HD 262,69th Cong., 1st sess. 
8-14

SAVANNAH, GA, DISTRICT 
July 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Nov. 7, 1945 
July 24, 1946 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
Drakes Cut to 13 feet; widening to 525 ft. at 
Kings Island; extension of training walls, 
revetments, and jetties. Consolidation of 
projects relating to Savannah Harbor. 
Channel 26 feet deep and 300 feet wide 
from the Seaboard Air Line Ry. Bridge to 
the foot of Kings Island. 
Authorized the 30-foot project and eliminated 
from the project (a) the relating dam across 
South Channel; (b) the relocation of the 
Inland waterway; and (c) the further extension 
of training walls, revetments, and jetties. 
Deepening the channel and turning basin above 
the Seaboard Air Line Ry. Bridge from 26 to 
30 feet and widening the channel opposite 
the Atlantic Coast Line Terminals to a 
maximum of 550 feet for a length of 5,000 
feet. 
Deepening the channels to 36 feet deep and 
500 feet wide across the ocean bar; 34 
feet deep and generally 400 feet wide, 
increased to 550 feet opposite the Atlantic 
Coast Line Terminals, with a turning basin 
34 feet deep at the Mexican Petroleum Corp. 
Refinery; and with such modifications 
thereof as the Secretary of War and the 
Chief of Engineers may consider desirable. 
Extending channel 30 feet deep, 200 feet wide 
upstream from Atlantic Creosoting Terminal 
to a point 1,500 feet below the Atlantic 
Coastal Highway Bridge, with turning 
basin 30 feet deep at upper end. 
Deepening the channel to 34 feet and widening 
to 400 feet from the upper end of the 
presently authorized 34-foot channel in the 
vicinity of the American Oil Company 
Refinery wharf, to the Savannah Sugar 
Refinery Corp. with a turning basin at the 
upper end of the proposed improvement, 
made by widening the channel to 600 feet 
for a length of 700 feet and providing 
approaches. 
Enlargement of turning basin near Kings 
Island to a width of 900 feet and a length 
of 1,000 feet, with suitable approaches, 
at a depth of 34 feet. 
Deepening the bar channel from 36 feet to 
40 feet, the channel between the bar channel 
and Garden City Terminal from 34 feet to 38 
feet, and the channel from the Garden City 
Terminal to the vicinity of the Savannah Sugar 
Refining Corp., from 30 feet to 36 feet; 
widening the bar channel from 500 feet to 600 
feet, the channel between Fort Pulaski and the 
Atlantic Coast Line Terminal from 400 feet to 
500 feet, and the channel between Garden City 
Terminal and the Savannah Sugar Refinery Corp. 
from 200 feet to 400 feet; providing necessary 
wideners of the bends; constructing a new 
turning basin 900 feet wide by 1,000 feet long 
8-15 
SD 39,71st Cong., 1st sess. 
HD 276, 73d Cong., 2d sess. 
HD 283,76th Cong., 1st sess. 
HD 227,79th Cong., 1st sess. 
HD 678, 79th Cong., 2d sess. 
HD 110, 83d Cong., 1st sess. 
SD 115,87th Cong., 1st sess. 
HD 226,89th Cong., 1st sess.

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Oct. 27, 1965 
SPCW Resolution 
June 15, 1976 
and HPWTC of 
June 9, 1976 
under authority 
of Sec. 201 of 
Flood Control 
Act of 1965 
July 16, 1984 
Oct. 17, 1986 
6. Sep. 19, 1980 
June 25, 1910 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
May 17, 1950 
11. SPWC Resolution 
June 22, 1971 
HPWC of June 23, 
1972 under 
authority of 
Sec. 201 of FC 
Act of 1965 
by 34 feet deep opposite the Atlantic Coast 
Line Terminals; and enlargement of existing 
turning basin at the American Oil Company 
Terminal from 600 feet wide by 600 feet long 
to 900 feet wide by 1,000 feet long. 
Providing sediment control works consisting 
of tide gate structure across Back River; 
sediment basin 40 feet deep, 600 feet wide 
about 2 miles long; with entrance channel 
38 to 40 feet deep and 300 feet wide; control 
works and canals for supplying fresh water to 
Savannah National Wildlife Refuge; and 
facilities to mitigate damages to presently 
improved areas other than refuge lands. 
Provided for modification of the existing 
project to include (1) incorporation of 
the LASH Turning Basin as an element of 
the existing Federal navigation project for 
maintenance purposes, (2) enlargement of 
Kings Island Turning Basin to 1,500 feet by 
38 feet. 
Construction of three new work curve wideners 
in the inner harbor channel. Curve Widener 
#1 is between mile 11.1 and 11.9. Curve 
widener #2 is between mile 13.2 and 13.8 
and curve widener #3 is between mile 14.0 
and 14.8. The Wideners are located on the 
north side of the channel. 
Savannah Harbor widening as described in 
Report of Chief of Engineers date Dec. 
19, 1978. Widen channel from 400 feet to 
500 feet between Kings Island turning Basin 
and Fig Island Turning Basin. 
Allows planning, engineering and design to 
remove drift and debris as part of 
operations and maintenance. 
SAVANNAH RIVER BELOW AUGUSTA, GA 
For a 5-foot channel. 
Special improvement by bank protection 
work of 20 or 25 miles of the river 
immediately below Augusta. 
The present 6-foot channel project and 
Lock and Dam, GA. 
Provision made for locating the lock 
and dam at New Savannah Bluff. 
Conditions of local cooperation modified. 
Provides for a 9-foot channel. 
TYBEE ISLAND, GA 
Project will provide for beach erosion 
control, consisting of beach restoration, 
groin nourishment. 
HD 223,89th Cong., 1st sess. 
HD 94-520, 94th Cong. dated 
June 8, 1976 
PL 98-360 
HD 6, 99th Cong., 2d sess. 
Dated Oct 17, 1986 
Section 201 
Section 867 
HD 255, 51st Cong., 2d sess. 
HD 962,60th Cong., 1st sess. 
HD 101,70th Cong., 1st sess. 
Senate Committee Print, 73d 
Cong., 2d sess. 
Rivers and Harbors Comn., 
Doc. 39, 75th Cong., 1st sess. 
SD 6, 81st Cong., 1st sess. 
HD 105, 92d Cong. 
8-16

SAVANNAH, GA, DISTRICT 
Oct. 17, 1986 
12A. Water Resources 
Development Act 
of 1986, Oct. 17 
1986. 
17A. Flood Control 
Act of Dec. 22, 
1944 
Oct. 17, 1986 
Jan. 1988 
17B. Flood Control Act 
of May 17, 1950. 
Flood Control Act 
of July 3, 1958. 
Water Resources 
Development Act 
of 1976. 
17C. Flood Control Act 
of Nov. 7, 1966. 
Water Resources 
Development Act 
of 1986 
Extends authority for renourishment with HR 699th Cong., 2d sess. 
Federal participation from 15 to 50 years. Dated Oct.17, 1986 
Section 867 
OATES CREEK, GA 
Provided for construction of the Oates HR 699th Cong., 2d sess. 
Creek Project. dated Oct. 17, 1986 
Section 401 
J. STROM THURMOND DAM AND RESERVOIR 
Approved the general plan for the HD 657, 78th Cong., 2d sess. 
comprehensive development of the Savannah 
River Basin and provided for construction 
of the Project. 
Recreation and fish and wildlife added as HR 699th Cong., 2d sess. 
name changed. (Formerly Clarks Hill Lake). Section 864 
HJR 376 
HARTWELL LAKE, GA AND SC 
Provided for construction of Hartwell HD 657, 78th Cong., 2d sess. 
Project. PL 516, 81st Cong., 2d sess. 
Provided for the completion of the PL 85-500, 85th Cong., 
Hartwell Project. 2d sess. 
Provides for installation of 5th unit. PL 94-587, Sec. 182b. 
85th Cong. 
RICHARD B. RUSSELL DAM AND LAKE, GA 
Provided for construction of the Trotters SD 52, 89th Cong., 1st sess. 
Shoals Project. 
Authorized mitigation plan. HR 699th Cong., 2d sess. 
dated Oct. 17, 1986 
Section 601 
8-17

REPORT TO THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 8-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 8 In text) 
For Last Cost to Sept. 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Bellville Point, GA Completed 
Cedar Point, GA Completed 
Darien Harbor, GA Completed 
Fancy Bluff Creek, GA ! Completed 
St. Mary's River, GA and FL, and Completed 
North River, GA 
Sapelo Harbor, GA 2, 3 Completed 
Satilla River, GA 1 , 5, 6 Completed 
Savannah River above Augusta, GA 2 , 3 , 4 See Notes 
Savannah River at Augusta, GA 2 , 3 , 5 See Notes 
1986 
1982 
1975 
1935 
1951 
1929 
1951 
1929 
1929 
599,379 
656,233 
199,723 
8,000 
15,688 
17,906 
9,452 
69,600 
200,556 
185,433 
7,200 
69,936 
19,594 
57,172 
85,944 
17,444 
1. Channel adequate for commerce. 
2. Project recommended for abandonment in H.D. 467, 69th Cong., 1st sess. 
3. No commerce reported. 
4. About 84 percent completed. Owing to construction of two power dams which submerged much of the work under the 
present and former projects, this improvement cannot be completed as originally planned. 
5. Excludes $185,000 contributed funds ($172,151 for construction and $12,849 for operation and maintenance). 
6. Water Resources Development Act of 1986 authorized demonstration project on the Umbrella Creek - Dover Creek for the 
purpose of reducing shoaling. Monitor for 10 years, develop a hydrodynamic model. 
8-18

SAVANNAH, GA, DISTRICT 
TABLE 8-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 14 in text) 
For Last Cost to Sept. 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report for Construction Maintenance 
Augusta, Savannah River, GA Completed 1941 $643,016 $38,242 
Curry Creek Dam and Lake, GA(1) See Note 1974 ---- ---- 
Dunn Branch, Woodbine, Camden Completed 1977 132,640 5,219 
County, GA Macon, GA Completed 1955 380,043 38,243 
Oates Creek, GA Authorized N/A 12,000,000---- 
Peacock Creek, Liberty County, GA Completed 1976 582,163 5,219 
1. Feasibility report completed. Project not authorized for construction. 
2. Authorized by HR 6, Water Resource Development Act of 1986 dated Oct. 17, 1986. First Federal cost of 
$9,600,000 and non-federal cost of $4,100,000. 
TABLE 8-E SAVANNAH RIVER BASIN, GA AND SC 
DAMS AND LAKES 
(See Section 16 in text) 
Estimated Cost 
Name River Federal Non-Federal Total 
J. Strom Thurmond Dam 
& Reservoir, GA and SC 
Hartwell, GA and SC 
Goat Island, GA and SC(5) 
Middleton Shoals, GA and SC(5) 
Chattooga Units(4), GA and SC 
Tallow Hill, GA 
Anthony Shoals, GA 
Newry-OId Pickens, SC(6) 
Savannah 
Savannah 
Savannah 
Savannah 
Chattooga 
Broad 
Broad 
Keowee 
$79,156,000(4) 
89,240,000 
36,400,000 
16,500,000 
41,700,000 
39,000,000 
18,100,000 
29,500,000 
$79,156,000(1,4) 
89,240,000(2) 
36,400,000(3) 
16,500,000(3) 
41,700,000(3) 
39,000,000(3) 
18,100,000(3) 
29,500,000(3) 
1. Final Cost. (Excludes $127,000 for preauthorization study.) 
2. Approved Aug. 1963. (Excludes $73,000 for preauthorization study.) 
3. Approved July 1954. 
4. Excludes Code 710 funds. 
5. Replaced by Richard B. Russell Dam and Lake (formerly Trotters Shoals Lake). 
6. Site of Duke Power Co. Keowee - Toxaway Project. 
8-19

JACKSONVILLE, FL DISTRICT* 
With the exception of a small area in the northeastern 
section of Florida, this district comprises a 
portion of south-central Georgia and all of peninsular 
Florida, embracing the watersheds tributary to the 
Atlantic Ocean and the Gulf of Mexico from, and 
including the harbor at Fernandina, Florida, to and 
including the Aucilla River. It also includes Puerto Rico 
and the U.S. Virgin Islands. 
IMPROVEMENTS 
Navigation Page 
1. Aquatic Plant Control (R&H Act of 1965) .. 2 
2. Arecibo Harbor, PR ................ 2 
3. Atlantic Intracoastal Waterway between 
Norfolk, VA and St. Johns River, FL ..... 2 
4. Bakers Haulover Inlet, FL ............ 2 
5. Canaveral Harbor, FL ................ 3 
6. Channel from Naples to Big Marco Pass . .. 3 
7. Charlotte Harbor, FL ................. 4 
8. Cross Florida Barge Canal ............. 4 
9. Eau Gallie Harbor, FL ................ 4 
10. Fernandina Harbor, FL .............. 5 
11. Fort Myers Beach, FL ............... 5 
12. Fort Pierce Harbor, FL .............. 5 
13. Intracoastal Waterway, Caloosahatchee 
River to Anclote River, FL ............ 6 
14. Intracoastal Waterway, Jacksonville to 
Miami, FL ........................ 6 
15. Jacksonville Harbor, FL .............. 7 
16. Jacksonville Harbor (Mill Cove), FL ...... 7 
17. John's Pass, FL ................... 8 
18. Longboat Pass, FL ................ 8 
19. Manatee Harbor, FL ................ 8 
20. Mayaguez Harbor, PR ............... 9 
21. Melbourne Harbor, FL .............. 9 
22. Miami Harbor, FL .................. 9 
23. New Pass, Sarasota, FL .............. 10 
24. Okeechobee Waterway, FL ........... 10 
25. Oklawaha River, FL ................ 10 
26. Palm Beach Harbor, FL ............. 11 
27. Ponce de Leon Inlet, FL ............. 11 
28. Ponce Harbor, PR ................. 11 
29. Port Everglades Harbor, FL ........... 12 
30. Removal of Aquatic Growth from Navigable 
Waters in the State of Florida ......... 12 
31. St. Augustine Harbor, FL ............. 13 
32. St. Johns River, Jacksonville to Lake 
Harney, FL ...................... 13 
33. St. Lucie Inlet, FL .................. 13 
34. San Juan Harbor, PR 14 
35. Tampa Harbor, FL 15 
36. Navigation Projects on which Reconnaissance 
and Condition Surveys only were Conducted 
during Period .................... 15 
37. Other Authorized Navigation Projects .... 16 
38. Navigation Work under Special Authorization 16 
Beach Erosion Control Page 
39. Brevard County, FL ................ 16 
40. Broward County, FL Beach Erosion Control 
and Hillsboro Inlet, FL Navigation Project .. 16 
41. Duval County, FL .................. 17 
42. Indian River County, FL ............. 17 
43. Manatee County, FL ................ 17 
44. Nassau County, FL .................. 18 
45. Palm Beach County, FL ............... 18 
46. Pinellas County, FL ................ 19 
47. Sarasota County, FL ............... 20 
48. Other Authorized Beach Erosion Control 
Projects . ....................... 20 
49. Beach Erosion Control Activities under 
Special Authorization ............... 20 
Flood Control 
50. Central and Southern Florida .......... 20 
51. Dade County, FL .................. 21 
52. Dade County, N. of Haulover Beach, FL . . 22 
53. Four River Basins, FL ................ 22 
54. Portugues and Bucana Rivers, PR ....... 23 
55. Inspection of Completed Flood Control 
Projects ........................ 23 
56. Other Authorized Flood Control Projects . . 23 
57. Flood Control Work under Special 
Authorization .................... 23 
General Investigations 
58. Surveys .. ..................... 23 
59. Collection and Study of Basic Data ..... 24 
60. Continuation of Planning and Engineering . . 24 
61. Advance Engineering and Design . ...... 24 
General Regulatory 
62. Permit Evaluation ................... 24 
63. Enforcement ..................... 24 
64. Other Navigation Regs .............. 24 
Project Modifications 
65. Kissimmee River Restoration .......... 25 
*AII cost and financial statements for projects are 
listed at the end of this chapter. All other tables are 
referenced in text and also appear at the end of the 
chapter. 
9-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. AQUATIC PLANT CONTROL 
(R&H ACT OF 1965) 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in Florida. 
Existing project. The authorized project provides for 
control and progressive eradication of water hyacinth, 
alligatorweed, Eurasian water-milfoil, and other noxious 
aquatic plant growths from navigable waters, tributary 
streams, connecting channels, and other allied waters 
of the United States, in combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, public health, and related purposes, 
including continued research for development of most 
effective and economical control measures in 
cooperation with other Federal and State agencies in 
accordance with report of Chief of Engineers, H 
251/89/1. The Water Resource Development Act of 
1986 amended the River and Harbor Act of 1965 
requiring the local sponsor to share 50 percent of 
planning costs and 50 percent of research costs that 
are local in nature. The cost of research that is regional 
or national in scope shall be borne fully by the United 
States. 
Local cooperation. Florida Department of Natural 
Resources holds the United States free from damages 
that may occur from operations performed in connection 
with this project and contributes 50 percent of cost of 
operations. Compliance with requirements of local 
cooperation is on schedule. 
Operations and results during fiscal year. New work: 
There were 10,456 acres of hyacinth and/or water 
lettuce, 3,399 acres of hydrilla and 202 acres of minor 
plant controlled during the period. Costs incurred for 
engineering and design and construction management 
were $304,374 and $63,211 respectively, and 
$1,799,375 for operations. 
Condition at end of fiscal year. Operations by the 
Corps and the State of Florida are in progress, water 
hyacinths within Florida are under maintenance control. 
Hydrilla is continuing to spread throughout the state 
and is causing major problems in some areas. 
2. ARECIBO HARBOR, PR 
Location. The harbor is located on the north shore of 
Puerto Rico about 40 miles west of San Juan Harbor. 
(See NOAA Nautical Chart No. 25668.) 
Previous project. For details see page 504 of 1956 
Annual Report. 
Existing project. The project provides for a channel 25 
feet deep by 400 feet wide, with flare at entrance and 
widening at inner end to form a maneuvering area, and 
a stone breakwater 1,200 feet long. Plane of reference 
is mean low water. Mean tidal range is 1.1 feet. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. A bulkhead wharf 688 by 220 feet 
providing a deep water berthing space of approximately 
500 feet, and a 300 by 100 foot transit shed. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. New work: 
none. 
Maintenance: Project condition sediment survey $51. 
Engineering and design cost $9,649. 
Condition at end of fiscal year. Project was completed 
in 1944. Breakwater was repaired in 1952. Wave action 
has since caused damage. 
3. ATLANTIC INTRACOASTAL 
WATERWAY BETWEEN NORFOLK, VA 
AND ST. JOHNS RIVER, FL 
(JACKSONVILLE DISTRICT) 
Location. That part of Intracoastal Waterway between 
southerly limit of Fernandina Harbor, FL, at junction of 
Lanceford Creek and Amelia River, and St. Johns River, 
FL. (See NOAA Nautical Chart No. 11489.) 
Previous project. For details see page 605 of 1938 
Annual Report. 
Existing project. Channel 12, 90 to 1 50 feet wide from 
Fernandina Harbor to St. Johns River, about 22 miles 
long. Plane of reference is mean low water. Mean tidal 
range is 6 feet at Fernandina and 3.8 feet at St. Johns 
River. (See Table 9-B for Authorizing Legislation.) 
Existing project was authorized by River and Harbor 
Acts of 1913 (H 898/62/2) and 1938 (H 618/75/3). 
Local cooperation. Fully complied with to date. 
Terminal facilities. There is a commercial marina 
located at Sisters Creek. No other facilities exist along 
this section of the waterway and none are currently 
required. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Permanent operating equipment costs 
$5,004. Condition, environmental and operation studies 
costs $19,488. Contract cost for disposal facility 
maintenance was $547,425. Engineering and design 
and construction management costs were $194,436 
and $59,770 respectively. 
Condition at end of fiscal year. Project was completed 
in 1941. 
4. BAKERS HAULOVER INLET, FL 
Location. The inlet connects the Intracoastal Waterway 
and the Atlantic Ocean and is located 2 miles north of 
Miami Beach in Dade County, Florida. 
Existing project. The authorized project provides for an 
entrance channel 11 by 200 feet, thence 8 by 100 feet 
to the Intracoastal Waterway, and a marina basin 8 by 
200 feet. The length of the project is 1.02 miles. Plane 
of reference is mean low water. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project was 
9-2

JACKSONVILLE, FL DISTRICT* 
completed in December 1964. 
5. CANAVERAL HARBOR, FL 
Location. The harbor is located on the east coast of 
Florida in Canaveral Bight, about 146 miles south of the 
entrance to Jacksonville Harbor and 69 miles north of 
the entrance to Fort Pierce Harbor. (See NOAA Nautical 
Chart Nos. 11478 and 11484.) 
Existing project. The authorized project provides for a 
37 foot deep entrance channel and maintenance of the 
44 foot deep Navy channel in the 37 foot channel 
reach; and 35 foot depth turning basin; construction 
and operation of a sand transfer plant; relocation of the 
perimeter dike about 4,000 feet westward and 
extension of the harbor westward; south entrance jetty 
1,100 feet long and the entrance jetty 1,150 feet long; 
a lock; a channel and turning basin 31 feet deep near 
the relocated dike; and a barge canal 12 by 125 feet 
from the turning basin to the Atlantic Intracoastal 
Waterway. Plane of reference is mean low water 
(Banana River) for barge canal. The project is about 
11.5 miles long. 
Mean tidal range is 3.5 feet at the entrance and 
practically non-tidal in Banana and Indian Rivers. (See 
Table 9-1 for Data Relative to Lock.) 
Estimated cost (October 1992 price levels) for 
Canaveral Harbor Deepening project is $6,600,000 
Federal cost and $7,800,000 non-Federal cost 
($2,471,000 contributed funds, $245,000 lands and 
damages, $3,749,000 relocations and $1,335,000 
other costs) and project cost for Canaveral Harbor Sand 
Transfer System is $22,686,000 Federal cost and 
$4,719,000 non-Federal ($167,000 contributed funds 
and $4,552,000 relocations. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must; provide all 
lands, rights-of-way, spoil-disposal areas, retaining 
dikes, and embankments; hold United States free from 
damages; provide and maintain four-lane bridge and 
roadway subject to Federal contribution of 65.3 percent 
of cost of constructing bridge and 51.2 percent of 
constructing roadway; provide public terminal and 
transfer facilities; and make alterations as required in 
berthing facilities. For further details see Senate 
Document 140, 87th Congress, 2nd session. Non- 
Federal contribution for new work is $1,146,500. 
Terminal facilities. Canaveral Harbor has 27 commercial 
waterfront facilities. The General Cargo Facilities consist 
of 1,900 feet of usable berthing space capacity of 
168,000 square feet. The Oil Handling Facilities operate 
with 3,760 feet of usable berthing space and 
1,413,000 barrels of tank storage. Available warehouse 
storage includes 28,000 square feet of dry storage and 
2,500,000 cubic feet of cold storage. Open storage is 
189 acres. 
Three cruise ship berths totaling 1,400 feet long by 34 
foot depth and three 8,800 square foot cruise terminals 
are also located on the south side. the western cruise 
ship berth is equipped with a roll on/off ramp and is 
adjacent to 20 acres of trailer storage area. 
Hoisting facilities consist of one 45 ton floating crane 
and crawler and mobile cranes, with capacities from 70 
to 200 tons, available from local crane rental services. 
There are 2 waterfront marine repair facilities with the 
nearest drydock facilities located at Port Everglades and 
Jacksonville. Two tugs with ratings of 1,600 and 2,250 
horsepower are also available. There is no rail service 
available at the port. The nearest rail service is the 
Florida East Coast Railway located 9 miles away. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 16, Rev. 1982.) 
Operations and results during fiscal year. New work: 
Construction costs $908,107. Engineering and design 
and construction management costs were $38,782 and 
$41,118 respectively. 
Maintenance: Maintenance and operation of lock and 
dam amounted to $165,106 for the fiscal year. 
Operation of service utilities costs $71,843. Natural 
resource management cost $2,674. Condition and 
operation studies cost $161,404. Real estate 
management was $4,830. Project operations cost was 
$ 5,969. Lands and damages cost $7,969. Contract for 
lock maintenance cost $879,617. Contract for channel 
and canal maintenance $2,100,053. Engineering and 
design and construction management cost $251,749 
and $227,447 respectively. 
Condition at end of fiscal year. The mitigation contract 
was completed in May. DM for Harbor Deepening was 
approved March 1992. PED was completed in October 
1992. Work remaining to complete the project is 
completion of the harbor extension and construction of 
the sand transfer plant. 
6. CHANNEL FROM NAPLES TO BIG 
MARCO PASS, FL 
Location. Naples Bay is on the southwestern side of 
the Florida peninsula about 35 miles south of the mouth 
of the Caloosahatchee River and approximately 1 mile 
inland and parallel to the Gulf of Mexico coastline. (See 
NOAA Nautical Chart No. 11430.) 
Existing project. The authorized project provides for an 
interior channel 6 by 70 feet from Naples to Big Marco 
Pass; a channel 12 by 150 feet from the Gulf of Mexico 
to Gordon Pass, thence 10 by 100-70 feet to a 10 foot 
depth turning basin in the upper Naples Bay; and an 8 
foot depth turning basin at the municipal yacht basin. 
Plane of reference is mean low water. Mean tidal range 
is 2.1 feet. (See Table 9-B for Authorizing Legislation.) 
For further details see Annual Report of 1962. 
Local cooperation. Fully complied with to date. 
Contributed funds for new work were $1 59,975. 
Terminal facilities. Four seafood packing houses; 4 
marine repair yards; a municipal pier and basin for use 
by recreational boats; and numerous private piers and 
slips for both commercial and recreational craft are 
available. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Project and condition studies cost $5,921. 
Engineering and design cost $54,551. 
Condition at end of fiscal year. The project is complete. 
9-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
7. CHARLOTTE HARBOR, FL 
Location. The Harbor is located on the west coast of 
Florida about 68 miles south of the entrance to Tampa 
Bay and 150 miles north of Key West. (See NOAA 
Nautical Chart No. 11429.) 
Previous projects. For details, see page 457 of 1959 
Annual Report. 
Existing project. The authorized project provides for a 
channel 32 by 300 feet, increased to 700 feet at the 
bend, from the Gulf of Mexico to Port Boca Grande to 
and including a turning basin at 200 feet square at the 
municipal terminal at Punta Gorda. Plane of reference 
is mean low water. The project is about 29.5 miles 
long. 
Mean tidal range is one foot at Port Boca Grande and 
1.4 feet at Punta Gorda. Extreme range is about 3 feet 
at Port Boca Grande and 3.8 feet at Punta Gorda. 
Strong southwesterly winds raise water levels about 
1.5 feet; strong northerly and easterly winds lower 
water levels about one foot. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local cooperation is fully complied 
with to date. 
Terminal facilities. Existing facilities consist of a 
phosphate wharf at Port Boca Grande and a municipal 
earthfill pier about 850 feet long at Punta Gorda, both 
open to the public. Railway connections are available at 
Port Boca Grande, and highway and railway connections 
are available at Punta Gorda. There is a tank farm at 
Port Boca Grande for storage and rehandling of bunker 
fuel oil and numerous facilities are available in the area 
for docking and servicing small craft. Facilities are 
considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Operation of service utilities cost was $4,586. 
Condition, environmental and operation studies cost 
$44,256. Lands and damages cost $7,238. Engineering 
and design costs was $216,574. 
Condition at end of fiscal year. The project was 
completed in 1959. (See Table 9-A for total project 
costs.) In addition, $15,563 was expended from 
contributed funds for new work in Boca Grande 
entrance channel. 
8. CROSS FLORIDA BARGE CANAL 
Location. The proposed canal extends up the St. Johns 
River, past Palatka, thence up the valley of the 
Oklawaha River across the divide south of Ocala, and 
down the valley of the Withlacoochee River to the Gulf 
of Mexico, about 95 miles north of Tampa, Florida. 
Existing project. The authorized project provides for a 
lock canal with project depth of 12 feet and a minimum 
bottom width of 150 feet, with five locks and two earth 
dams. Project including the section in the St. Johns 
River is 184 miles long. (See Table 9-J for Locks and 
Dams.) 
WRDA 92 authorizes and directs ASA(CW) to offer to 
enter into a contract to operate and maintain the project 
at a level necessary to ensure safe operating conditions 
and to prevent deterioration of the structures. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must furnish lands 
and rights-of-way for construction of canal; hold the 
United States free from damages; and operate and 
maintain all highway bridges and roadways built in 
connection with project. 
Terminal facilities. None. 
Operations and results during fiscal year. New work: 
Engineering and design costs were $73,036. 
Maintenance: (See Table 9-K for work accomplished.) 
Regulation. 
a. Lake Ocklawaha. During the period, the lake 
continued to be regulated at 18.0 feet, NGVD by 
discharging through the Rodman spillway. 
b. Lake Rousseau. During the period, the lake 
continued to be regulated at 27.5 feet, NGVD by 
discharging through the Inglis Main and Bypass 
Spillways. 
Condition at end of fiscal year. Construction of project 
commenced February 25, 1964, and is 36 percent 
completed. Inglis Lock, Dam, and Spillway; Rodman 
Dam and Spillway; Eureka Lock, Dam, and Spillway; 
Henry H. Buckman Lock; and canal from Palatka to Lake 
Ocklawaha and from Withlacoochee River to Gulf of 
Mexico, including Inglis Bypass Channel, are completed. 
Construction work on the project was terminated in FY 
1971 by order of the President. A restudy report and 
environmental impact statement were completed in 
February 1977. 
Project was deauthorized in Water Resources 
Development Act of 1990 (P.L. 101-640) and 
$5,000,000 of prior appropriations were withdrawn. 
9. EAU GALLIE HARBOR, FL 
Location. The Harbor is located on Indian River about 
midway of the State of Florida, 176 miles south of 
Jacksonville Harbor and 174 miles north of Miami 
Harbor. 
Existing project. The authorized project provides for a 
channel 8 by 100 feet from Indian River to and 
including a 300 by 600 foot turning basin in Eau Gallie. 
The project is about 2,700 feet long. Plane of reference 
is mean low water. The harbor is almost nontidal. 
Local cooperation. Fully complied with to date. 
Terminal facilities. A privately owned boatyard in Eau 
Gallie Harbor provides more than 600 feet of docking 
space used chiefly by pleasure boats. There are also 2 
marine railways and repair and storage facilities 
available. The facilities are considered adequate for the 
present needs of navigation. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project was 
completed in 1939. In December 1982, the controlling 
depth of the channel was 5 feet. 
9-4

JACKSONVILLE, FL DISTRICT 
10. FERNANDINA HARBOR, FL 
Location. Entrance to the harbor is located on the 
northeast coast of Florida about 95 miles south of the 
entrance to Savannah Harbor, Georgia, and 22 miles 
north of the entrance to Jacksonville Harbor, Florida. 
(See NOAA Nautical Chart No. 11503.) 
Existing project. The authorized project provides for a 
32 foot depth channel (maximum channel in active 
status: 28 feet) generally 300-400 feet wide from deep 
water in the ocean to the junction of Lanceford Creek 
with Amelia River; an 800 foot wide turning basin at 
the first bend below Lanceford Creek; and 2 jetties, 
19,150 and 11,200 feet long. The project is 7 miles 
long. Plane of reference is mean low water. Mean tidal 
range is 5.8 feet on the bar and 6 feet in the inner 
harbor. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. Non- 
Federal contribution for new work was $892,000. 
Terminal facilities. There are 2 large wharves operated 
by industrial plants; 12 wharves serving fishing boats, 
recreational craft, and other vessels; 3 oil handling 
wharves with pipelines; and a Municipal Marina and 
Sportsman's Wharf with public facilities for small craft. 
Total berthing space is approximately 4,065 feet. Most 
terminals are served by rail, and all have highway 
access. Facilities are considered adequate for existing 
commerce. (See Port Series No. 16 (Part 2), 1964.) 
Operations and results during fiscal year. New work: 
None. 
Maintenance. Operations of service utilities cost 
$5,004. Condition, environmental and operation studies 
cost $60,775. Real estate management cost $5,389. 
Maintenance costs for bank stabilization, revetments 
and dikes was -$723. Engineering and design and 
construction management costs were $719,381 and 
$6,491 respectively. Maintenance dredging by contract 
was $432,024. 
Condition at end of fiscal year. The active portion of 
the existing project is complete. Jetties are in poor 
condition and are badly in need of repair. Remaining 
work is to deepen the inner harbor channel and turning 
basin to 32 feet when and if the presently inactive 
1950 authorization is reactivated. The entrance channel 
has been deepened to 46 feet for the Kings Bay project. 
Authorized depths were restored as of March 1991. 
11. FORT MYERS BEACH, FL 
Location. Fort Myers Beach is on Estero Island near 
the mouth of the Caloosahatchee River, about 20 miles 
below Fort Myers and 110 miles south of Tampa, 
Florida. (See NOAA Nautical Chart No. 11427.) 
Existing project. The authorized project provides for a 
channel 12 by 150 feet from that depth in San Carlos 
Bay into Matanzas Pass, thence 11 by 125 feet in 
Matanzas Pass to and including a turning basin 2,000 
feet upstream from the upper shrimp terminals. Plane of 
reference is mean low water. Project is 2.5 miles long. 
Mean tidal range is 1.7 feet. Spring range is about 
2.3 feet. Strong northerly winds lower the water 
surface 1 to 2 feet; strong southerly winds have an 
opposite effect. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are 3 shrimp-packing houses 
and several fish-packing houses, 2 marine railways, a 
fuel terminal and an ice manufacturing plant in the area. 
There are several commercial facilities for servicing 
shrimp boats. Recreational craft facilities include 9 
marinas, a boat motor testing laboratory which is 
closed, and numerous privately owned piers and 
wharves. All terminals have highway access. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. The project is complete. 
12. FORT PIERCE HARBOR, FL 
Location. On east coast of Florida, about 218 miles 
south of entrance to St. Johns River and about 124 
miles north of entrance to Miami Harbor. (See NOAA 
Nautical Chart No. 11475.) 
Existing project. A channel 350 feet wide at the 27 
foot contour in the ocean, tapering to a width of 200 
feet at Station 100+00, thence 200 feet wide to Sta. 
30 +00, and thence flaring to a turning basin 900 feet 
wide. Entrance channel is 27 feet deep to Sta. 130+00 
and thence 25 feet deep to and including the turning 
basin. Project includes the maintenance of two jetties 
and shore revetments at the inlet. Length of project is 
about 3.5 miles. 
Mean tidal range is 2.6 feet at the entrance and 0.7 
feet at terminals. (See Table 9-B for Authorizing 
Legislation.) 
For further details see 1961 Annual Report. 
Estimated cost of new work (October 1992 price 
levels) $5,936,000 Federal and $2,465,000 non- 
Federal ($2,361,000 contributed funds and $104,000 
lands and damages). 
Local cooperation. Fully complied with to date. Non- 
Federal contribution for new work was $18,574. A 
25% contribution and an additional 10% reimbursement 
over 30 years from locals is required. 
Terminal facilities. Two earth-filled piers forming a slip 
200 by 300 feet, with bulkhead wharf at inner end, 
affording berthing space of about 1,653 feet. The south 
pier and bulkhead wharf are municipally owned. 
Facilities also include a cooling plant, a warehouse and 
a fruit packing house. The north pier is served by 
railway and both piers by highway connections. North 
of the turning basin local interests have provided deepdraft 
berthing and pier facilities. Also available is a 
bulkhead wharf with a depth of 25 feet with ample 
room for open storage and with tank storage for 
petroleum in the rear. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Operations of service utilities was $3,255. 
Condition and environmental studies cost $25,624. 
Lands and damages cost $3,398. Maintenance dredging 
9-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
costs were $90,868. Engineering and design cost was 
$35,998. 
Condition at end of fiscal year. The project was 
completed in 1938 except for the fishing walkway atop 
the south jetty which was completed by local interests 
in 1968. Local interests installed lighting atop the jetty 
in 1969. The south jetty and revetments are in good 
condition. Authorized project depths were restored as of 
November 1990. 
13. INTRACOASTAL WATERWAY, 
CALOOSAHATCHEE RIVER TO 
ANCLOTE RIVER, FL 
Location. The Waterway extends from the mouth of 
the Caloosahatchee River at Punta Rassa, Florida, to 
the mouth of Anclote River, Florida, following in general 
an almost continuous series of protected inside 
waterways along the gulf coast of Florida. (See NOAA 
Nautical Chart Nos. 11411, 11425 and 11427.) 
Previous projects. For details see page 767 of 1945 
Annual Report. 
Existing project. The authorized project provides for a 
channel 9 by 100 feet from Caloosahatchee River to 
Anclote River; deepening the existing channel at Caseys 
Pass to 9 feet; a channel 6 by 80 feet (Cats Point 
Channel) along the southeastern side of Boca Ciega Bay 
past Frenchman Creek and Gulfport; maintenance of 
bulkheads, revetments, and two jetties built at Caseys 
Pass under previous project; and improvement and 
maintenance of Sunshine Skyway Channel. Plane of 
reference is mean low water. The project includes about 
160 miles of channels. 
Mean ranges of tide are 1.7 feet at Punta Rassa, 1 
foot at Port Boca Grands, 1.4 feet in Tampa Bay at 
Anna Maria, and 2 feet at entrance to Anclote River. 
Extreme ranges are about 4.5 feet at Punta Rassa, 
about 3 to 4 feet between Port Boca Grande and Corey 
Causeway over Boca Ciege Bay, and about 5.5 feet at 
entrance to Anclote River. Southerly winds over the 
area generally raise water levels by 1 to 1.5 feet; 
northerly winds lower water levels by 1 to 2 feet. (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Existing facilities include one 
municipal concrete pier, one railway pier, one freight 
wharf, one marginal wharf 500 feet long on terminal 
island, and 11 privately owned landings, all at Sarasota. 
Municipal pier and freight wharf are open to the public. 
All piers have highway connections. There are 6 
wharves along Boca Ciega Bay and a number of small 
privately owned piers and wharves at various points 
along waterway for use by commercial fishing boats 
and recreational craft. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Operation of service utilities cost $2,253. Condition 
surveys cost $33,360. Real estate audits and 
administration costs were $286. Lands and damages 
cost was $11,669. 
Condition at end of fiscal year. Existing project is 
complete. A contract to maintain the jetties at Caseys 
Pass was completed in 1983. 
14. INTRACOASTAL WATERWAY, 
JACKSONVILLE TO MIAMI, FL 
Location. The Waterway extends from Jacksonville to 
Miami, Florida, following the St. Johns River to the 
mouth of Pablo Creek and thence following in general 
an almost continuous series of protected inside 
waterways along the Atlantic coast of Florida to Miami. 
(See NOAA Nautical Chart Nos. 11489, 11485, 11472 
and 11467.) 
Previous projects. For details, see pages 618-619 of 
1938 Annual Report. 
Existing project. The authorized project provides for a 
channel 12 by 125 feet from Jacksonville to Miami, 
modified by Chief of Engineer's report of July 22, 1960; 
side channels at Sebastian and Daytona beach and 
turning basins at Sebastian and Vero Beach, all to an 8 
foot depth, and operation and maintenance of Palm 
Valley highway bridge. Project is 370 miles long, 
including 21 miles in Jacksonville Harbor. Mean range 
of tide is 3.8 feet at St. Johns River, 0.7 foot in Indian 
River at Fort Pierce, 1.8 feet in Lake Worth at Port of 
Palm Beach terminals, 2.3 feet at the Port Everglades 
terminals, and 2 feet in Biscayne Bay. The extreme 
range is about 7 feet at St. Johns River, 1.5 feet at 
Fort Pierce, and 3 feet in Biscayne Bay. Plane of 
reference is mean low water. Tidal effect is 
imperceptible at points along waterway distant from 
inlets. (See Table 9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. Non- 
Federal contribution for new work was $61,000. 
Terminal facilities. There are a number of privately 
owned piers, wharves, and landings at various points 
along waterway. Terminals with railway connections 
are available at Jacksonville, Fort Pierce, West Palm 
Beach, Port Everglades, and Miami. Municipal piers or 
wharves have been constructed at Titusville, Cocoa, 
Melbourne, and Vero Beach for handling general freight 
and at St. Augustine, Daytona Beach, New Smyrna 
Beach, Eau Gallie, West Palm Beach, Delray Beach, Fort 
Lauderdale, and Miami for use of recreational craft. 
Yacht basins, open to the public, have been provided 
at Jacksonville Beach, Daytona Beach, Titusville, Eau 
Gallie, Vero Beach, Fort Pierce, West Palm Beach, Fort 
Lauderdale, Hollywood, and Miami. Facilities are 
considered adequate for existing commerce. (For further 
details on facilities at Jacksonville, see Port Series No. 
15, 1969, and at Palm Beach, Port Everglades, and 
Miami, see Port Series No. 16, Revised 1972.) 
Operations and results during fiscal year. Maintenance: 
Operation of service facilities was $29,088. Condition, 
environmental and operation studies cost $282,373. 
Real estate management cost $31,205. Project 
operations management cost was $138. Lands and 
damages cost was $72,033. Maintenance cost of 
roads, railroads and bridges was $13,860. Maintenance 
of non-recreational buildings, grounds, and utilities cost 
$93. Contract dredging costs were $1,834,817. 
Engineering and design and construction management 
cost $234,620 and $240,423 respectively. 
Condition at end of fiscal year. The existing project as 
modified by the Chief of Engineers is complete. 
(Construction of the channel and turning basin at 
9-6

JACKSONVILLE, FL DISTRICT 
Sebastian, Florida, was deauthorized by W.R.D.A. of 
1988, P.L. 100-676.) 
(See Table 9-A for total project costs.) In addition, 
$2,199,842 has been expended from public works 
funds for new work. 
15. JACKSONVILLE HARBOR, FL 
Location. The authorized project comprises the lower 
24.9 miles of St. Johns River which empties into the 
Atlantic Ocean near the northeasterly corner of the 
Florida peninsula. (See NOAA Nautical Chart No. 
11491.) 
Previous projects. For details, see page 607 of Annual 
Report, 1938. 
Existing project. The authorized project provides for a 
channel 38 feet deep by 400-1,200 feet wide from 
ocean to mile 20 via Dame Point-Fulton Cutoff, thence 
34 feet to Commodore Point, and thence 30 feet deep 
to the FEC railway bridge at Jacksonville, including a 
30 foot channel in Arlington cut in the old Dames Point- 
Fulton channel; maintenance of the existing 42 and 40 
foot depth entrance channel; widening of channel by 
100 feet near mile 5 and by 200 feet near mile 7; 
maintenance of jetties at channel entrance; construction 
of training walls and revetments; a navigation and 
floodway channel 26 by 200 feet along south side of 
Commodore Point; on approach and mooring basin 20 
feet deep, 1,300 feet long at 20 foot depth contour and 
600 feet long at pierhead line near Naval Reserve 
Armory in south Jacksonville; a depth of 24 feet 
between that depth contour and the pierhead line from 
Hogan Creek to the foot of Laura Street; and a depth of 
28 feet to within 60 feet of pierhead line between foot 
of Laura Street and St. Elmo W. Acosta (formerly Upper 
State) bridge. Length of project is about 26.8 miles. In 
addition the Navy has provided funds for a deeper 
Jacksonville Harbor entrance channel 42 feet deep and 
800 feet long, intersecting with the Navy's Mayport 
entrance channel to the Mayport turning basin; also an 
extension of the existing project to provide 38 foot 
depth for the Navy fuel depot, at Drummond Creek. 
Mean tidal range is 5.3 feet on the bar, 4.9 feet at 
Mayport, 2.6 feet at Dame Point, and 1.1 feet at 
Jacksonville. The extreme range varies from about 9 
feet on the bar to about 1.5 feet at Jacksonville. Strong 
northeasterly winds raise the water level about 2 feet at 
Mayport and Jacksonville. Strong southwesterly winds 
lower the water about 1.5 feet at Mayport and one foot 
at Jacksonville. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests have fully complied 
with requirements of local cooperation for work 
performed to date. For work authorized by the 1965 
River and Harbor Act, local interests were required to 
contribute 2.6 percent of the contract price plus 
supervision and administration for work provided by the 
Corps; provide all lands and rights-of-way; save the 
United States free from damages; and provide and 
maintain public terminal and transfer facilities. 
Assurances of local cooperation for this work were 
accepted February 11, 1966. Non-Federal contribution 
for new work was $927,654. 
Terminal facilities. Jacksonville Harbor has 84 
waterfront facilities. Available at the General Cargo 
Facilities are 11,140 feet of usable berthing space and 
12 transit sheds with a total storage space of 
1,009,800 square feet. The Oil Handling Facilities 
consist of 7,843 feet of usable berthing space and 179 
storage tanks providing a total of 8,478,900 barrels of 
tank storage. Warehouse storage at the port includes 
3,266,900 square feet of dry storage and 4,071,100 
cubic feet of cold storage. Available open storage is 
233 acres. 
Four fixed cranes with capacities from 40 to 100 tons 
are located at the port. Available locally are crawler and 
truck cranes with capacities up to 100 tons. Various 
phases of marine repair work are accomplished by 7 
waterfront repair facilities and numerous other 
companies located offwater. Drydock facilities consist 
of 6 floating drydocks with capacities from 800 to 
33,000 tons. Floating equipment includes 25 tugs with 
up to 3,300 horsepower and 16 tank barges with 
capacities up to 20,700 barrels. Three major railroads 
furnish rail service from port docks to all points outside 
of Jacksonville. 
Facilities are considered adequate for existing 
commerce (See Port Series No. 15, Rev. 1978.) 
Operations and results during fiscal year. Maintenance: 
Operation of service facilities cost was $5,004. 
Condition, environmental and operation studies cost 
$176,039. Real estate management cost $3,314. Lands 
and damages cost was $14,252. Channel and canal 
contract maintenance cost was -$210,025. Engineering 
and design and construction management cost 
$301,801 and $390 respectively. 
Condition at end of fiscal year. Construction of the 
modification to the project, authorized by 1965 River 
and Harbor Act, is completed. The north jetty is in fair 
condition and partially submerged at high tide. The 
south jetty was repaired in FY 1985 to prevent further 
damage to the Mayport Naval Station. Revetments and 
retaining walls were in poor condition. Authorized 
project depths were restored as of January 1991. 
(See Table 9-A for total project costs.) In addition, 
$290,013 has been expended from public works funds 
for new work. 
16. JACKSONVILLE HARBOR (MILL 
COVE), FL 
Location. The authorized Mill Cove project comprises 
a 6 square mile body of shallow water on the St. Johns 
River approximately 10 miles from the Atlantic Ocean 
near the northeasterly corner of the Florida peninsula. 
(See NOAA Nautical Chart No. 11491.) 
Previous project. None. 
Existing project. The authorized project provides 
improved flow and circulation through Mill Cove to 
eliminate further shoaling. This large shallow area 
averages about 2 to 4 feet deep, is about 5.5 miles 
long, and varies from 0.5 to 2.0 miles wide. It is 
situated along the St. Johns River near the Dame Point- 
Fulton Cutoff portion of the Jacksonville Harbor 
navigation project. The Mill Cove project includes 
dredging a 650 foot by 3,600 foot flow channel at the 
west end to -12 feet MSL; enlarging the weir opening 
at the eastern end to 1,300 feet wide and -1 2 feet 
MSL; and installing flow diversion features at the west 
9-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
and east ends of the cove. 
Mean tidal range is 4.9 feet at entrance, 4.5 feet at 
Mayport, 3.0 feet at Dame Point, and 1.2 feet at 
Jacksonville. Strong northeasterly winds raise the water 
level about 2 feet at Mayport and Jacksonville. Strong 
southwesterly winds lower the water about 1.5 feet at 
Mayport and 1 foot at Jacksonville (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. In conformance with Section 221, 
Public Law 91-611, and prior to commencement of 
construction, the Jacksonville Port Authority, as local 
sponsor, must provide written agreement to the 
following local cooperation requirements: provide 
without cost to the United States all lands, easements, 
and rights-of-way required for construction and 
subsequent maintenance of the project; hold and save 
the United States free from damages that result due to 
construction and maintenance other than damages due 
to the fault or negligence of the United States or its 
contractors; accomplish without cost to the United 
States such utility and other relocations or alterations as 
necessary for construction. 
Terminal facilities. None. 
Operations and results during fiscal year. New work: 
Engineering and design cost $53,045. 
Maintenance: None. 
Condition at end of fiscal year. Project was completed 
in 1990. 
17. JOHNS PASS, FL 
Location. A natural inlet on the west coast of Florida 
connecting Boca Ciega Bay with Gulf of Mexico. The 
pass is located about 8 miles northwest of lower Tampa 
Bay directly across Boca Ciega Bay from St. Petersburg, 
Florida. (See NOAA Nautical Chart No. 11411.) 
Existing project. Channel 10 by 150 feet in the Gulf, 
thence 8 by 100 feet inside pass, and 6 by 100 feet to 
the Intracoastal Waterway, and suitable protective 
measures over a frontage of approximately 1,000 linear 
feet of shore along the north end of Treasure Island. 
Plane of reference is mean low water. Mean range of 
tide is 1.5 feet. Project is about 2.6 miles long. 
Project was authorized December 2, 1964 by the Chief 
of Engineers under Section 107 of the 1960 River and 
Harbor Act and by Section 110 of the 1966 River and 
Harbor Act. 
Local cooperation. Fully complied with to date. 
Terminal facilities. Only small marinas and repair yards 
for recreational craft are in the general vicinity. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
None. 
Condition at end of fiscal year. Project was completed 
in 1968. Authorized project depths were restored as of 
June 1991. 
18. LONGBOAT PASS, FL 
Location. Longboat Pass is located on the west coast 
of Florida about 11 miles northwest of Sarasota and 23 
miles south of St. Petersburg. Located in Manatee 
County, it is one of several natural inlets connecting 
Sarasota Bay, a tidal estuary, with the Gulf of Mexico. 
(See NOAA Nautical Chart No. 11425.) 
Existing project. The authorized project provides for an 
entrance channel 12 by 150 feet from the Gulf to 
Longboat Pass Bridge, thence a channel 10 by 100 feet 
from Longboat Pass Bridge along a north to 
northeasterly alignment to the Intracoastal Waterway to 
Cortez Bridge. The mean tidal range is 2.2 feet and the 
maximum tidal range is about 5 feet. Currents are 
predominantly tidal. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. See 
1978 Annual Report for detailed local cooperation 
requirements. Contributed funds for new work were 
$172,324. 
Terminal facilities. From Sarasota north to Tampa Bay 
there are about 28 small craft facilities including 
marinas, boat repair yards, and boat basins along the 
Intracoastal waterway. Nine of them are located within 
2 miles of Longboat Pass. Numerous private mooring 
piers and wharves also exist in the area. The marina 
and repair facilities appear adequate for the general 
boating needs of the area. 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $44. Construction management 
cost -$470. 
Condition at end of fiscal year. Construction of the 
project is complete. Authorized project depths were 
restored as of June 1991. 
19. MANATEE HARBOR, FL 
Location. The project is located in Manatee County on 
the east side of Tampa Bay 10 miles form the Gulf of 
Mexico. (See NOAA Nautical Chart No. 11414.) 
Existing project. The authorized project provides for 
maintenance of the existing 40 foot deep draft 
navigation channel and turning basin which extends 
from Tampa Bay Channel to berthing facilities at Port 
Manatee. Also provide initial construction for a widener 
at the northwest end of the Manatee Harbor Channel 
and initial construction to deepen approximately 6.6 
acres adjacent to the southern berthing area to provide 
a larger turning basin. All material from the project will 
be placed on upland sites west and northeast of the 
port slip. 
Estimated cost of new work (October 1992 price 
levels) $13,940,000 Federal and $16,814,000 non- 
Federal ($13,608,000 contributed funds $3,206,000 
lands and damages. 
Local cooperation. Fully complied with to date. A 25 
percent contribution and an additional 10 percent 
reimbursement over 30 years from locals are required. 
Terminal facilities. Existing facilities at Port Manatee 
consist of 675 acres of port operational lands, a ship 
basin 1,500 feet long by 788 feet wide; and an 
approximately 3 mile access channel, with a design 
width of 400 feet, which connects with the Federally 
authorized Tampa Bay Channel. The Manatee project 
was constructed between August 1968 and February 
9-8

JACKSONVILLE, FL DISTRICT 
1970. The required design depth was 40 feet, and the 
dredging contractor was allowed a pay overdepth of 2 
feet. Port Manatee also operates its own terminal 
railroad, which is licensed under the Interstate 
Commerce Commission, and publishes a switching tariff 
as a Class III railroad. It also maintains and operates 2 
switch engines and about 30,000 feet of track which 
connects with the CSX Railroad. 
Operations and results during fiscal year. New Work: 
Engineering and design cost $33,037. 
Condition at end of fiscal year. Plans and specs for 
the first contract are complete. PED completion (SAD 
approval) occurred in June 1992. Due to recent 
maintenance dredging performed by Port Manatee, dikes 
must be raised to provide for adequate capacity for the 
first deepening contract. Submittal of a LCA with a 
revised financial plan is scheduled for December 1992. 
20. MAYAGUEZ HARBOR, PR 
Location. The Project is on the west coast of Puerto 
Rico, about 110 miles by water from San Juan Harbor. 
(See NOAA Nautical Chart No. 25673.) 
Existing project. The authorized project provides for a 
30 by 1,000 foot approach channel to the deep water 
terminal, decreasing to a 500 foot width opposite the 
westerly end of terminal, thence the same width to the 
easterly end of terminal. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. A modern deep water terminal is 
located in the northeast section of the harbor consisting 
of a bulkhead wharf about 1,270 feet long with a 
storage transit shed 800 by 60 feet immediately 
shoreward. The Puerto Rico Industrial Development 
Company, an agency of the Commonwealth of Puerto 
Rico, owns a bulkhead wharf of about 200 feet in line 
with the existing deep water terminal plant located 
within the industrial harbor area. In addition, Bumble 
Bee Packing Company, Inc., owns and operates a dock 
of about 200 feet for docking tuna fish boats. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Condition survey cost $19. Engineering and design cost 
was $8,681. 
Condition at end of fiscal year. Project was completed 
in 1934. 
21. MELBOURNE HARBOR, FL 
Location. The project is on Indian River about midway 
of the State of Florida, 179 miles south of Jacksonville 
Harbor and 171 miles north of Miami Harbor. 
Existing project. The authorized project provides for a 
channel 8 by 100 feet from Indian River to a 400 by 
800 foot turning basin in Crane Creek. Project is about 
3,150 feet long. Plane of reference is mean low water. 
The harbor is almost non-tidal. 
Terminal facilities. The Municipal Marina on the north 
end of the turning basin has a 350 foot steel bulkhead 
with 11 finger piers, each about 40 feet long. There 
are also 2 privately owned storage and repair facilities 
and several privately owned boathouses and docks. The 
facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
None. 
Condition at end of fiscal year. The project was 
completed in 1938. As of September 1984 channel 
depths as authorized were available throughout the 
project. 
22. MIAMI HARBOR, FL 
Location. Miami is near the northern end of Biscayne 
Bay, about 71 miles south of the entrance to Palm 
Beach Harbor. Miami River has its source in the 
Everglades and flows southeasterly to enter Biscayne 
Bay at Miami. (See NOAA Nautical Chart No. 11468.) 
Existing project. The authorized project provides for a 
38 by 500 foot channel from the ocean to the outer 
end of the north jetty, thence 36 by 400 feet through 
the entrance and across Biscayne Bay to and including 
a turning basin at the municipal terminals; a 36 foot 
depth turning basin at Fisher Island; 2 rubblestone 
jetties at the entrance; and a channel 15 feet deep in 
Miami River varying in width from 250 feet at mouth to 
90 feet 5.5 miles inland. Plane of reference is mean low 
water, except for 15 foot channel in Miami River where 
depths are based on flood conditions. Total length of 
the project is about 13 miles. 
Mean tidal variation is 2.5 feet at entrance and 2 feet 
in the bay. Extreme variation is about 4.5 feet at 
entrance and 3 feet in Biscayne Bay. Strong easterly 
winds raise the water level about 1.5 feet at entrance 
and 1 foot in the bay. Strong westerly winds lower 
water level about 1 foot at entrance and about 0.5 foot 
in the bay. Estimated cost (October 1992 price levels) 
for Miami Harbor Channel is $55,757,000 Federal cost 
and $23,867,000 non-Federal ($53,000 Lands and 
damages, $2,397,000 relocations and $21,417,000 
contributed funds.) (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. See 
1978 Annual Report for detailed local cooperation 
requirements. Non-Federal contribution for new work 
was $2,300,710. 
Assurances of local cooperation for the 1968 
modification to the project were accepted December 
18, 1968. 
Terminal facilities. There are 91 commercial waterfront 
facilities serving the port. The General Cargo Facilities 
include 21,373 feet of usable berthing space, 13 transit 
sheds with a total capacity of 474,300 square feet, and 
9 freight stations with a total storage capacity of 
270,400 square feet. Oil Handling Facilities consist of 
2,714 feet of usable berthing space and 36 storage 
tanks with a total storage capacity of 744,475 barrels. 
Available sharehouse storage includes dry storage of 
1,450,500 square feet and cold storage of 11,204,000 
cubic feet. There are 117.1 acres of open storage at 
the port. 
Hoisting Facilities located at the port include two 40 
ton cranes and cranes with capacities up to 200 tons 
available through local rental. Twelve waterfront repair 
yards and 2 offwater yards serve the port. Drydock 
9-9

REPORT OF THE SECRETARY OF THE ARMY ON CMIL WORKS ACTIVITIES FOR FY 1992 
facilities available include 7 marine railways and 4 boat 
lifts with haulout capacities ranging from 40 to 1,000 
tons and lifting capacities ranging from 79 to 500 tons. 
Nine tugs, with ratings up to 3,000 horsepower, and 
13 tank barges, with capacities up to 35,000 barrels, 
are also available. Rail Facilities at the port are served 
by the CSX and the Florida East Coast Railway. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 16, Rev. 1982.) 
Operations and results during fiscal year. 
New work: Engineering and design cost $108,763. 
Construction management cost was $102,252. 
Maintenance: Operation of service facilities cost 
$5,004. Condition, operation and environmental studies 
cost $10,151. Real estate management and audit cost 
was $561. Lands and damages cost $6,161. 
Maintenance dredging cost $177,554. Engineering and 
design and construction management cost $480,165 
and $4,254 respectively. 
Condition at end of fiscal year. Inner harbor portion 
Phase I contract is 60% complete. The Port of Miami is 
modifying contract to bring additional equipment to 
complete the outer portion. Port of Miami is proceeding 
with design and construction of the project on their 
own. 
23. NEW PASS, SARASOTA, FL 
Location. Sarasota Bay is a tidal lagoon along the west 
coast of Florida immediately south of Tampa Bay. New 
Pass is a gulf inlet across the bay from Sarasota, 
Florida. (See NOAA Nautical Chart No. 11425.) 
Existing project. The authorized project provides for an 
entrance channel 10 feet deep and 150 feet wide in the 
Gulf of Mexico diminishing to 8 by 100 feet through 
New Pass and extending across Sarasota Bay to the 
Intracoastal Waterway with side channels to, and 
turning basins at, Payne Terminal and city pier. Plane of 
reference is mean low water. Mean range of tide is 1.3 
feet in Sarasota Bay; mean spring range is 1.7 feet. 
Project is about 4 miles long. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Consist of Payne Terminal, a slip 
200 by 650 feet, and city pier, 400 feet long with 2 
finger piers equipped with adequate facilities at each 
location. 
Operations and results during fiscal year. Maintenance: 
Condition survey cost $21. 
Condition at end of fiscal year. Project was completed 
in 1964. Authorized project depths were restored as of 
April 1991. 
24. OKEECHOBEE WATERWAY, FL 
Location. The waterway traverses the southern part of 
the Florida peninsula via the Caloosahatchee River, Lake 
Okeechobee, and St. Lucie Canal, connecting coastal 
waterways along the Gulf and Atlantic Shores. (See 
NOAA Nautical Chart No. 11428.) 
Previous project. For details, see page 785 of 1949 
Annual Report. 
Existing project. The authorized project provides for 
replacing the old locks on the St. Lucia Canal by a 
single new lock; a channel 10 by 100 feet from Ft. 
Myers for about 5 miles upstream, thence 8 by 80-100 
feet to the Intracoastal Waterway, Jacksonville to 
Miami, near Stuart; a side channel at Ft. Myers; 
operation and care of St. Lucie Lock; and maintenance 
of features completed under previous projects as 
follows: a 12 by 200 foot channel from the Gulf of 
Mexico to Punta Rassa, thence 10 by 100 feet to Ft. 
Myers with a 10 foot depth basin at Fort Myers; a 6 by 
80 foot channel along the south shore of Lake 
Okeechobee from Clewiston to St. Lucie Canal; a 6 by 
60 foot channel in Taylor Creek from the town of 
Okeechobee to the Lake; and operation and care of 
Moore Haven and Ortona Locks. (See Table 9-B for 
Authorizing Legislation.) 
For further details see 1962 Annual Report. 
Local cooperation. Fully complied with for completed 
portion of project. Non-Federal contribution amounted 
to $503,700. 
Terminal facilities. There are 3 freight piers, one 
municipal recreation pier, 4 privately owned piers, and 
a municipal yacht basin on the Caloosahatchee River 
near Fort Myers. The Corps has provided a boat basin, 
launching ramp, and a 120 foot wharf on the 
Caloosahatchee River about one-quarter mile below 
Ortona Lock. There are tie-up dolphins above and below 
all 5 locks. Commercial yacht basins are provided on 
the south side of the Caloosahatchee River about 
halfway between Ortona and Moore Haven Locks and 
about 3 miles east of LaBelle. A commercial/municipal 
yacht basin is provided on the north side of the St. 
Lucie Canal at Indiantown. 
There are numerous small wooden-pile landings along 
the Caloosahatchee River, St Lucia Canal, and on the 
St. Lucie River, including one railroad terminal pier, 
municipal pier, and a pier for handling petroleum 
products at Stuart. Also, 550 feet of wharves have 
been provided on the west side of Taylor Creek 
immediately landward of Hurricane Gate No. 6 and 150 
feet on the east side of the creek. A yacht basin has 
been provided on the west side of the creek 
immediately landward of the hurricane gate. The 
installations on Taylor Creek are privately owned, but 
are open to the public. A breakwater protected harbor 
is available at Pahokee. There is a 440 foot marginal 
wharf on the Industrial Canal at Clewiston; a 125 foot 
wharf at LaBelle; a 150 foot wharf at Belle Glade; a 
125 foot wharf at Moore Haven; a 50 foot wharf at 
Alva; and a 30 foot wharf on Taylor Creek at the town 
of Okeechobee. A docking facility for loading raw sugar 
was constructed in 1967 on Herbert Hoover Dike near 
Belle Glade. All have highway and/or railway 
connections. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. (See Table 
9-L for work accomplished.) 
Condition at end of fiscal year. The project is complete. 
(The 8 foot depth basin at Stuart was deauthorized by 
W.R.D.A. of 1988, P.L. 100-676.) 
25. OKLAWAHA RIVER, FL 
9-10

JACKSONVILLE, FL DISTRICT 
Location. The river has its source in a system of large 
lakes in the central part of the Florida peninsula and 
flows generally northerly, then easterly, emptying into 
St. Johns River 22 miles upstream from Palatka. The 
extreme head of the system is considered to be Lake 
Apopka, 120 miles above the river's mouth. 
Previous projects. For details, see page 613 of 1938 
Annual Report. 
Existing project. The authorized project provides for 
clearing a channel to Lake Griffin; maintaining dikes to 
obtain a navigable depth of about 4 feet to Leesburg 
and construction of a lock and dam at Moss Bluff. The 
project length is about 85.7 miles. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. Several private and public landings 
and boat-launching ramps are located along the river. 
Public recreation craft basins and boat launching ramps 
are near Silver Springs and State Roads 40 and 316 
bridges. There is a municipal wharf on Lake Griffin at 
Leesburg. A dam has created Lake Ocklawaha (13,000 
acres) with egress to the St. Johns River through 
Buckman Lock. Along the lake are 4 launching ramps; 
Payne's Landing, Orange Springs, Kenwood Landing, 
and Rodman Recreation Area. Access below the dam is 
at the Ocklawaha Boat launch ramp and at State Road 
19. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Channel maintenance cost $36,431. 
Condition at end of fiscal year. The project is complete. 
(A 6 foot depth channel from the mouth of the river to 
the head of Silver Springs Run was deauthorized.) The 
Moss Bluff lock and dam structure was replaced under 
the Four River Basins, Florida flood control project. 
26. PALM BEACH HARBOR, FL 
Location. The authorized project is located on the east 
coast of Florida about 71 miles north of the entrance 
to Miami Harbor and about 264 miles southeasterly 
from the entrance to Jacksonville Harbor. (See NOAA 
Nautical Chart No. 11472.) 
Existing project. The authorized project provides for an 
entrance channel 35 by 400 feet merging with an inner 
channel 33 by 300 feet to and including a turning basin; 
tank revetment; and restoring jetties. Plane of reference 
is mean low water. The project is about 1.6 miles long. 
Mean range of tide in the ocean at the entrance is 2.8 
feet and at the turning basin, 2.2 feet. Extreme range 
of tide is about 4.5 feet at the inlet and 3 feet at the 
terminals. Seven foot tidal ranges have occurred during 
storms. For details, see 1962 Annual Report. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Fully complied with to date. For 
requirements, see 1961 Annual Report. 
Terminal facilities. The port has 13 commercial 
waterfront facilities. The General Cargo Facilities include 
5,156 feet of usable berthing space and 6 transit sheds 
with a total of 118,030 square feet of storage capacity. 
The Oil Handling Facilities consist of 10 storage tanks 
with a total capacity of 2,029,600 barrels. Usable 
berthing space is not available at the Oil Handling 
Facilities. Dry storage is available at 150,500 square 
feet, cold storage at 19,200 cubic feet and open 
storage at 27.1 acres. 
Seven cranes with capacities from 15 to 230 tons are 
located at the port. There are no floating cranes, repair 
facilities or drydock facilities located at the port. A 100 
ton vertical boat lift is located on the Intracoastal 
Waterway south of the port for heavy lifts. Two tugs 
with ratings of 900 and 1,000 horsepower are 
available. The Palm Beach Belt Line which connects 
with the Florida East Coast Railway serves the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series No.16, Rev. 1982.) 
Operations and results during fiscal year. Maintenance: 
Operation of service facilities $4,587. Condition, 
operation and environmental studies for the project 
totaled $27,505. Real estate management cost $1,894. 
Lands and damages cost was $4,688. Channel 
maintenance cost $888,270. Engineering and design 
and construction management cost $48,091 and 
$41,943 respectively. 
Condition at end of fiscal year. The project was 
completed in 1967. Jetties and revetment are in need 
of repair. The south jetty was completed in FY 1986. 
Authorized project depths were restored as of 
November 1990. 
27. PONCE DE LEON INLET, FL 
Location. Ponce de Leon Inlet is on the Atlantic coast 
of Florida about 65 miles south of St. Augustine Harbor 
and 57 miles north of Canaveral Harbor. (See NOAA 
Nautical Chart No. 11485.) 
Existing project. The authorized project provides for an 
entrance channel 15 by 200 feet across the ocean bar, 
thence 12 by 200 feet and 12 by 100 feet through the 
inlet; thence southward in Indian River North, 12 by 
100 feet, and northward in Halifax River, 7 by 100 feet, 
each leg continuing to the Intracoastal Waterway; ocean 
jetties on the north and south of the inlet 4,200 and 
2,700 feet long respectively, and weir in the north jetty 
with an impoundment basin inside the jetty. Plane of 
reference is mean low water. Mean range of tide is 4.1 
feet in the ocean and 2.3 feet inside the inlet, the 
project is about 5 miles long. 
Local cooperation. Fully complied with to date. Non- 
Federal contribution for new work was $2,415,600. 
Terminal facilities. None in the immediate area. 
Operations and results during fiscal year. Maintenance: 
Condition, operation and environmental studies for the 
project totaled $37,873. Real estate management and 
audits cost $2,261. 
Condition at end of fiscal year. Construction of the 
project is complete. Repair of the north jetty was 
completed in FY 1986. Authorized project depths were 
restored as of January 1990. 
28. PONCE HARBOR, PR 
Location. Ponce Harbor is an open bay about midway 
9-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
on the south coast of Puerto Rico. From the center of 
the city of Ponce, the harbor is about 3 miles south. 
(See NOAA Nautical Chart No. 25677.) 
Previous project. For details, see page 12 of Annual 
Report for 1975. 
Existing project. The authorized project provides for a 
seawall 362 feet long extending northwesterly across 
the rock reef from near the landward end of the 
municipal pier, 30 feet deep and containing about 18 
acres; a breakwater 2,400 feet long extending 
southwesterly from Punta Carenero; a channel 36 feet 
deep by 600 feet wide extending from the Caribbean 
Sea approximately 2.8 miles up to the port, thence a 
channel 400 feet wide by 36 feet deep into the harbor, 
and a 36 foot deep, irregularly shaped turning basin 
with a diameter of 959 feet. Plane of reference is mean 
low water. Mean tidal range is 0.6 foot, extreme varies 
between about 1 foot below and 2 feet above mean 
low water. (See Table 9-B for Authorizing Legislation.) 
Local cooperation: Should provide all lands, easements 
and rights-of-way; provide and maintain at local expense 
depths in berthing areas and local access channels; hold 
United States free from any damages resulting from 
construction and maintenance of the project; relocate 
without cost to the United States all cables, sewer 
mains, water supply, drainage and other utility 
installations as required; provide adequate public 
terminal and transfer facilities open to all on equal 
terms. A letter has been received from mayor of Ponce, 
assuring compliance with local requirements and to cost 
share the project. Non-Federal contribution for new 
work was $717,304. A 25 percent contribution is 
required and an additional 10 percent reimbursement 
over 30 years from locals. 
Terminal facilities. The municipality of Ponce owns and 
operates the only deep-draft terminal facilities in Ponce 
Harbor, which consist of a municipal pier 515 feet long 
and 108 feet wide, and a bulkhead wharf 3,811 feet 
long. Both are equipped for transfer and storage of 
freight. A 40 ton container lift shore crane is available 
for the handling of loaded containers. The municipal 
pier has a steel transit shed 386 by 85 feet. The 
bulkhead wharf has 4 steel transit sheds totaling over 
103,000 square feet. Three concrete and steel 
warehouses are available providing 800,000 square feet 
for general storage. Open storage areas for structural 
steel, lumber, and other bulk and package commodities 
are also provided. Bulk cement is handled and loaded 
into cement cargo ships by the use of a private pipeline 
loading facility. A tuna fish processing and canning 
factory is located on the premises, with direct access to 
the bulkhead wharf. Existing facilities are open to the 
public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Project condition surveys cost $86. 
Engineering and design cost was 1,314. 
Condition at end of fiscal year. Construction of the 
project is complete. South and north jetties are in fair 
condition. 
29. PORT EVERGLADES HARBOR, FL 
Location. The harbor is on the east coast of Florida 
about 23 miles north of Miami and about 48 miles 
south of Palm Beach Harbor, Florida. (See NOAA 
Nautical Chart No. 11470.) 
Existing project. The authorized project provides for an 
ocean entrance channel 45 by 500 feet through an 
ocean bar tapering to 42 by 450 feet between 
rubblestone entrance jetties, and continuing at that 
depth to an irregularly flared entrance and turning basin 
of same depth; enlarging Pier 7 channel to 36 by 400 
feet for distance of about 1,600 feet; maintenance of 
the locally dredged channel opposite Berth 18 to 36 
feet deep over a length of 700 feet with varying widths 
of 200 to 150 feet; construction of a south jetty fishing 
walkway; and, maintenance of the jetties. Plane of 
reference is mean low water. The project is about 1.9 
miles long. Mean range of tide is 2.5 feet at the 
entrance and 2.3 feet at the terminals; extreme range 
is about 4.5 feet with storm tides of about 6.5 feet. 
Local cooperation. Fully complied with for work 
completed to date. For work under H 144/93/1, local 
interests must: provide all lands, easements and rightsof-
way; save United States free from damages; 
accomplish utility and other relocations or alterations; 
provide depths in berthing areas and local access 
channels serving the terminals commensurate with 
depths provided in the related project areas; establish 
regulations prohibiting discharge of pollutants into 
waters of the channel by users thereof; prohibit erection 
of any structure within 100 feet of project channel as 
authorized at time of construction; provide and maintain 
public terminal and transfer facilities; contribute 50 
percent of total first costs of recreational jetty fishing 
facility; and operate and maintain jetty fishing facility. 
Assurances of local cooperation for the 1974 
authorization have been furnished by the local sponsor. 
Terminal facilities. There are 22 commercial waterfront 
facilities serving the port. The General Cargo Facilities 
include 13,807 feet of usable berthing space, 7 transit 
sheds with a total capacity of 393,870 square feet, and 
6 container yards with space for 3,965 containers. Oil 
Handling Facilities consist of 232 storage tanks with a 
total storage capacity of 9,564,800 barrels. There is 
no usable berthing space located at the Oil Handling 
Facilities. Dry storage is available at 225,000 cubic feet 
and open storage at 100.3 acres. 
Hoisting facilities available from a local firm include 5 
cranes with capacities from 20 to 155 tons. No floating 
cranes or derricks for heavy lifts are available at the 
port. There are 2 marine repair yards. Drydock facilities 
include 2 drydocks with capacities of 2,200 and 3,200 
tons and a 4,270 ton vertical boat lift. Three tugs with 
ratings up to 4,290 horsepower serve the port. The Port 
Everglades Belt Line connects with the CSX railroad to 
serve the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 16, Rev. 1982.) 
Operations and results during fiscal year. New work: 
None. 
Maintenance: None. 
Condition at end of fiscal year. Work required to 
9-12

JACKSONVILLE, FL DISTRICT 
complete the project is construction authorized in H 
144/93/1. 
30. REMOVAL OF AQUATIC GROWTH 
FROM NAVIGABLE WATERS IN 
THE STATE OF FLORIDA. 
Location. Water hyacinth, hydrilla and water lettuce 
are found in freshwater streams and lakes in various 
parts of the district. 
Existing project. The authorized project provides for 
destruction or removal of aquatic growth in navigable 
waters of the State so far as they constitute an 
obstruction to navigation and commerce, using any 
mechanical, chemical or other means not injurious to 
cattle, and use of log booms to close sloughs and 
backwaters as an auxiliary means. No estimate of the 
final cost of work has been made. (See Table 9-B for 
Authorizing Legislation.) 
For further detaile, see 1962 Annual Report. 
Local cooperation. None. required. 
Operations and results during fiscal year. Maintenance: 
Operations continued during the year. (See Table 9-B 
for Authorizing Legislation and Table 9-M for spraying 
operations.) 
Condition at end of fiscal year. The project is for 
maintenance of navigable waterways. During the year 
24,556 acres of floating vegetation (water hyacinth 
and/or water lettuce), and 2,136 acres of hydrilla were 
controlled in approximately 2,200 miles of waterways. 
Hyacinth in Lake Okeechobee and in St. Johns River 
Watershed is under maintenance control. 
31. ST. AUGUSTINE HARBOR, FL 
Location. The harbor is on the east coast of Florida, 
about 35 miles south of the entrance to St. Johns River 
and about 180 miles north of Fort Pierce Harbor. (See 
NOAA Nautical Chart No. 11485.) 
Previous project. For details see page 412 of Annual 
Report for 1958. 
Existing project. The authorized project provides for a 
channel 16 by 200 feet along the best natural new inlet 
bar, thence 12 feet deep to the Intracoastal Waterway; 
a sandtrap groin on the north side of the inlet extending 
seaward from the shore of Vilano Beach, and a sandtight 
jetty on the south side of the channel extending 
seaward from the shore of Conch Island parallel to and 
coextensive with the groin; future landward extension 
of the groin and jetty; and a channel 10 by 100 feet in 
San Sebastian River from the Intracoastal Waterway to 
King Street Bridge, with a turning basin near the upper 
end. Length of the inlet channel is about 1.5 miles, and 
length of the San Sebastian River channel is about 2.6 
miles. Plane of reference is mean low water. The mean 
tidal range is 4.5 feet in the ocean at St. Augustine 
Inlet and 4.2 feet at the city waterfront. Strong 
northerly winds, mostly in the winter, lower the water 
surface about 1 foot. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Fully complied with to date. 
Terminal facilities. There are several timber docks on 
the Matanzas waterfront of St. Augustine. In this area 
of the harbor is a concrete dock which serves as a 
municipal yacht pier. It has fuel facilities, 19 slips and 
accommodates boats up to 60 feet in length. A large 
public boat ramp is also available. The principal 
terminals are the numerous shrimp docks in the San 
Sebastian River which flows southward through the city 
into the Matanzas River south of the bridge. These 
consist of timber wharves, with frame and corrugated 
iron warehouses thereon, and 9 marine railways for 
small boats. There is also a marine supply facility and 
several boat yards. The present terminals have highway 
connections and several of the shrimp docks have rail 
connections. They are considered adequate for existing 
commerce and recreational craft. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Environmental studies cost $1,393. 
Condition at end of fiscal year. Project is complete 
except for the North Jetty which is in a deferred status. 
The groin is in good condition except for the 300 feet 
which has subsided to about elevation 3.0 feet, mean 
low water. The jetty is in good condition, but is 
submerged at high tide. 
32. ST. JOHNS RIVER, FL, 
JACKSONVILLE TO LAKE 
HARNEY 
Location. Rises in marshes of Brevard County, Florida, 
near east coast, and flows northwesterly to 
Jacksonville, thence easterly into the Atlantic Ocean, 
122 miles south of Savannah River. River is about 285 
miles long, of which 161.5 miles are included in project. 
(See NOAA Nautical Chart No. 11492.) 
Previous projects. Adopted by River and Harbor Acts 
of June 14, 1880 and July 5, 1884. For further details 
see Annual Reports for 1915 and 1938. 
Existing project. Channel is 13 by 200 feet from Florida 
East Coast Railway bridge at Jacksonville to Palatka, 
thence 12 by 100 feet to Sanford, and thence 5 by 100 
feet to Lake Harney, with side channel to Enterprise and 
maintenance of two jetties. 
Existing project was authorized by River and Harbor 
Acts of March 2, 1945 (H 445/78/2) and July 24, 
1946 (SD 208/79/2). For further details see Annual 
Report for 1962. 
Terminal facilities. There are 36 piers and wharves 
along project, including municipal piers and wharves at 
Green Cove Springs and Palatka, 12 Navy piers at 
Green Cove Springs, a municipal recreational pier at 
Sanford, and 19 privately owned piers, 5 of which have 
nearby tank storage facilities for petroleum projects. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Active portion is 
complete. Condition of project as a whole is adequate 
for present needs of navigation. (For more detailed 
information refer to 1963 Annual Report.) 
9-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
33. ST. LUCIE INLET, FL 
Location. The inlet is on the east coast of Florida about 
19 miles south of the entrance to Fort Pierce Harbor, 
Florida, and 100 miles north of the entrance to Miami 
Harbor, Florida. (See NOAA Nautical Chart No. 11472.) 
Previous project. For details see page 764 of Annual 
Report for 1949. 
Existing project. The authorized project provides for 
extending the north jetty about 500 feet and modifying 
existing jetty to provide a sand bypass weir section 
about 500 feet long; excavation of a sand impoundment 
basin adjacent to the bypass weir in the north jetty; 
construction of a south jetty consisting of a 
rubblemound structure about 2,400 feet long with a 
walkway for recreational fishing; channel between 
existing bar cut and the Intracoastal Waterway 10 by 
500 feet through the bar cut, tapering to 150 feet 
through the inlet, and 7 by 100 feet to the Intracoastal 
Waterway; and transfer of 380,000 cubic yards of 
material to the south beach during each two year 
maintenance period. Total project length is about 1.9 
miles. Plane of reference is mean low water. Mean tidal 
range is 2.6 feet on the ocean side and about one foot 
on the land side of the inlet. (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. Local interests must: contribute 
19.9 percent of construction cost allocated to 
navigation in the combined project, 23.1 percent 
allocated to beach erosion, and 50 percent of 
construction cost of jetty fishing walkway; provide 39.8 
percent of the annual maintenance cost allocated to 
navigation and 23.2 percent of the annual costs for 
maintenance dredging allocated to beach erosion control 
for periodic beach nourishment and 100 percent of the 
annual jetty maintenance costs allocated to beach 
erosion control; maintain jetty fishing walkway; agree 
that each 5 years the amount of local cost sharing for 
maintenance is to be adjusted; provide all lands, 
easements, and rights-of-way; hold United States free 
from damages; provide marina with mooring facilities 
and utilities; provide and maintain depths in berthing 
area and local access and feeder channels 
commensurate with the depths provided in the project; 
accomplish such alterations as required to sewer, water 
supply, drainage, and other utility facilities, and take 
action to place in effect statutes and/or regulations 
which will protect water quality for the authorized uses 
of the project. Assurances of local cooperation for the 
1974 modification were signed by the local sponsor on 
August 24, 1978. Non-Federal contribution for new 
work was $3,086,026. 
Terminal facilities. A municipal pier provides facilities 
for docking and servicing charter fishing and small 
recreational craft. At Stuart there is a dock for handling 
bulk petroleum products and several marinas which 
provide facilities for mooring, servicing and minor repair 
of small craft. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. New work: 
None. 
Maintenance: Condition and operations studies cost 
$4,827. Maintenance dredging cost was $49,778. 
Engineering and design cost $91,382. 
Condition at end of fiscal year. Work required to 
complete the project is construction authorized in HD 
294/93/1. Authorized project depths were restored as 
of July 1991. 
34. SAN JUAN HARBOR, PR 
Location. San Juan Harbor is on the north coast of 
Puerto Rico and about 35 miles from the east end of 
the island and 1,100 miles southeast of Miami, Florida. 
(See NOAA Nautical Chart No. 25670.) 
Previous projects. For details see Annual Reports for 
1915, 1916, and 1938. 
Existing project. Modification of the authorized project 
to provide the deepening of the Bar Channel to 48 feet 
and shifting its alinement 350 feet west; deepening 
Anegado and Army Terminal to 40 feet; deepening 
Graving Dock Channel, the Cruise Ship Basin, Puerto 
Nuevo Channel, and San Antonio Channel to 36 feet; 
and deepening Anchorage Area E to 38 feet while 
reducing its size and constructing 6 mooring dolphins 
within its limits. A 1,500 foot long extension to San 
Antonio Channel would be added to the Federal project 
and Sabana approach deepened to 32 feet. Estimated 
cost of new work (October 1992 levels) $57,051,000 
Federal and $21,799,000 non-Federal. 
Local cooperation. Should provide all lands, easements 
and rights-of-way; hold the United States free from any 
damages; provide and maintain depths in berthing areas 
and local access and feeder channels; provide 
alterations as required to sewer, water supply, and 
other utility facilities. It is further recommended that 
local interests be reimbursed for work performed by 
them on the project subsequent to project authorization. 
A 25 percent contribution and an additional 10 percent 
reimbursement over 30 years from locals are required. 
Terminal facilities. There are 28 piers and bulkhead 
wharves in the harbor capable of docking deep-draft 
vessels, which have an aggregate berthing length of 
about 23,700 feet. Eleven piers and bulkhead wharves 
are on the north shore, 2 piers and a three-level ramp 
facility for roll-on/roll-off operations at Front Graving 
Dock turning basin and channel, 9 at the eastern side 
and 3 at the western side of the Army Terminal basin 
and channel, and 3 on the south shore of San Antonio 
Channel. One pier and bulkhead wharf are privately 
owned, 7 are U.S. Government property, and 24 are 
owned by the Commonwealth of Puerto Rico. Twenty 
piers and wharves are equipped with mechanical crane 
transfer facilities. Five wharves are equipped with a 
special crane for handling loaded containers. Twentyfour 
are open to the general public. Pier No. 6 was 
repaired and improved in 1985. 
There is an aggregate length of about 1,339 feet of 
berthing space at Catano Point used principally by small 
vessels within the 18 foot draft range. This space is 
also open to the public. In addition, there are 10 piers 
and bulkhead wharves with approximately 6,910 feet 
of berthing space owned and operated by different 
agencies of the Federal Government. This space is not 
open to the public. 
Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
9-14

JACKSONVILLE, FL DISTRICT 
Maintenance contract cost was $1,731,999. 
Engineering and design and construction management 
cost -$453 and $143,302 respectively. 
Condition at end of fiscal year. Remaining work to 
complete project is modification authorized in 1976. 
Existing project includes the entrance channel and 
turning basin to Army Terminal which cost $1,543,712 
(this expenditure was made from military appropriations 
and is not included in Table 9-A costs). 
35. TAMPA HARBOR, FL 
Location. Tampa Harbor is in a large natural indentation 
of the Gulf of Mexico about midway of the west coast 
of Florida. The entrance is about 220 miles north of Key 
West and about 330 miles southeast of Pensacola. (See 
NOAA Nautical Chart Nos. 11413 and 11414.) 
Previous projects. For details see page 665 of 1938 
Annual Report. 
Existing project. The authorized project provides for a 
channel from the Gulf of Mexico to Port Sutton and 
Tampa; 46 by 700 feet from the Gulf of Mexico to 
Mullet Key; 44 by 600 feet in Mullet Key Cut Channel; 
44 by 500 fec in Tnanml pa Bayb yfr om3 Mulfleett Key Cut to 
Hillsborough Bay and Port Tampa Channels; 44by 500 
feet in Hillsborough Bay from junction with Tampa Bay 
and Port Tampa Channels to the junction with Port 
Sutton entrance channel, thence 42 by 400 feet to the 
junction with Seddon and Garrison Channels; 44 by 400 
feet in Port Sutton entrance channel; 42 by 400 feet in 
Sparkman Channel; 40 by 300 feet in Ybor Channel; 42 
by 400 feet in Port Tampa Channel; 44 by 400-500 
feet in East Bay entrance channel; 44 by 300 feet in 
East Bay approach channel; 30 by 300 feet in Seddon 
and Garrison Channels; 30 by 200 feet in Alafia River; 
9 by 100 feet in Hillsborough River to a point 2,000 
feet above Columbus River bridge; a breakwater; a 43 
by 200 foot Port Suttonl Terminal Channel 3,700 feet 
long; turning basins at Ybor Channel, Port Tampa, East 
Bay, mouth of Hillsborough River, and in Alafia River; 
and maintenance of a channel 12 by 200 feet in 
Hillsborough River, a 43 by 200 feet by 3,700 feet long 
in Port Sutton Terminal Channel, and 34 by 300 feet in 
East Bay Channel. (The 46 foot and 44 foot depth 
portions of the project include a 5 foot underkeel 
clearance. Special studies on the project concluded that 
4 feet underkeel is sufficient. Therefore, a one foot 
overdepth has been placed in an inactive status, 
resulting in active project depths of 45 and 43 feet 
respectively.) Plane of reference is mean low water. The 
project is about 87 miles long, including 10 miles in 
Hillsborough River and 3.6 miles in Alafia River. 
Mean range of tide is 1.3 feet at the lower end of the 
bay, 1.6 feet at Port Tampa, and 1.8 feet at Tampa. 
Extreme range is about 3.8 feet at the lower end of the 
bay and 4.8 feet at Tampa. Strong southwesterly winds 
raise the water level about 1.5 feet. Strong northerly 
winds, which usually occur in the winter, lower the 
water level about 2 feet. (See Table 9-B for Authorizing 
Legislation.) 
For further details, see 1962 Annual Report. 
Local cooperation. Local cooperation has been fully 
complied with for work completed to date. See 1978 
Annual Report for requirements for work authorized by 
the River and Harbor Act of 1970, H 401/91/2 and H 
150/91/1. Assurances of local cooperation for the 1970 
authorization were approved by the Secretary of the 
Army on January 10, 1973. The LCA for branch 
channels was signed June 20, 1986. An amendment to 
the LCA reflecting cost sharing requirements of WRDA 
of 1986 for section 6 was signed August 31, 1987. 
Non-Federal contribution for new work was 
$1,009,450. A 25 percent contribution and an 
additional 10 percent reimbursement over 30 years is 
required from locals. 
Terminal facilities. There are 102 commercial 
waterfront facilities serving Tampa Harbor. The General 
Cargo Facilities consist of 7,226 feet of usable berthing 
space and 15 transit sheds with a total of 585,200 
square feet of storage space. The Oil Handling Facilities 
include 16,440 feet of usable berthing space and 316 
storage tanks for a total capacity of 11,610,350 
barrels. Dry storage is available at 1,904,750 square 
feet, cold storage at 14,309,000 cubic feet, and open 
storage at 59.4 acres. There are 2 wharves available for 
coal storage at 750,000 tons total storage and grain 
elevators with a 3,400,000 bushel total capacity. One 
elevator on Ybor Channel has a 1,000,000 bushel 
capacity. 
Hoisting Facilities include 13 cranes, fixed and mobile, 
with capacities from 45 to 150 tons and other crawler 
and mobile cranes available locally. Marine repair yards 
include 9 waterfront repair facilities and numerous other 
offwater companies engaged in various phases of 
marine repair. There are 4 floating and 4 graving docks 
available at the port with capacities ranging from 548 
to 5,400 long tons. Floating equipment includes 24 tugs 
with up to 3,350 horsepower and 4 companies with 
tank barges of capacities up to 14,000 barrels. The 
CSX Railroad serves the port. 
Facilities are considered adequate for existing 
commerce. (See Port Series No. 17, Rev. 1979.) 
Operations and results during fiscal year. New work: 
Continuing dredging contract costs were $50,566 
Federal and $16,855 non-Federal. Engineering and 
design and construction management cost $42,849 and 
$1,238 respectively. 
Maintenance: District Radio Communication Network 
cost $5,004. Condition and operation studies cost 
$281,765. Real estate management cost $4,890. Lands 
and damages $586. Maintenance dredging cost 
$3,885,556. Engineering and design and construction 
management cost $99,637 and $320,626 respectively. 
Condition at end of fiscal year. Work authorized by the 
River and Harbor Act of 1970 (H 401/91/2 is 70 
percent complete). Authorized project depths were 
restored as of December 1990. 
36. NAVIGATION PROJECTS ON 
WHICH RECONNAISSANCE AND 
CONDITION SURVEYS ONLY 
WERE CONDUCTED DURING 
PERIOD. 
(See Table 9-H.) 
37. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
9-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
(See Table 9-C.) 
38. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation Activities Pursuant to Section 107, Public 
Law 86-645 (Preauthorization) 
Fiscal year costs for Aquadilla Harbor, PR, $81,993; 
Benner Bay-Mangrove Lagoon, VI, $2,218; Buena Vista, 
Humacao, PR, $50,962; Canaveral Harbor, Cap Fund 
$66,354; Fernandina Harbor, FL, $119,754; Island of 
Vieques, PR, $43,572; Moore Haven Channel, Glades 
City, FL, $1,621; Punta Tuna, Maunabo, PR, $1,322. 
Snagging and clearing for navigation (Section 3 of 
1945 River and Harbor Act, Public Law 14, 79th 
Congress.) 
No costs incurred. 
Beach Erosion Control 
39. BREVARD COUNTY, FL 
Location. The project is on the east coast of Florida at 
approximately the midpoint of the peninsula. (See 
NOAA Nautical Chart Nos. 11484 and 11476.) 
Existing project. The authorization provides for a 
protective and recreational beach with a berm 50 feet 
wide at elevation 10 feet above mean low water and 
a natural seaward slope as would be shaped by wave 
action, along 14,600 feet of beach at the city of Cape 
Canaveral and 10,600 feet of beach at Indialantic and 
Melbourne beach, and for periodic nourishment of the 
restored beach at Indialantic and Melbourne beach 
limited initially to a period of 10 years. Nourishment of 
the restored beach at the city of Cape Canaveral would 
be provided by the authorized sand-transfer plant for 
construction at Canaveral Harbor. The project also 
provides for improvement of the Federally owned shores 
for beach erosion control or hurricane protection to be 
accomplished by the Federal agencies involved, subject 
to their own determination of economic justification. 
The areas involved include 4.9 miles of shore at 
Kennedy Space Center, 4.0 miles at Cape Kennedy Air 
Force Station, and 2.3 miles at Patrick Air Force Base. 
Mean tidal range in the area is 3.5 feet. (See Table 9- 
B for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 50 
percent of all first costs of the work and 50 percent of 
the nourishment cost at Indialantic and Melbourne 
beach for the first 10 years of the project life; provide 
lands and rights-of-way; provide, after the first 10 years 
of project life, periodic nourishment of the restored 
beach at Indialantic and Melbourne beach during project 
life; maintain continued public ownership of the shore 
upon which the amount of Federal participation is 
based; control water pollution; and hold the United 
States free from damages. Assurances of local 
cooperation were approved by the Secretary of the 
Army on July 9, 1973. Non-Federal contribution for 
new work was $3,460,990. 
Operations and results during fiscal year. New work: 
Engineering and design cost $10,574. 
Maintenance: None. 
Condition at end of fiscal year. Initial beach fill has 
been provided at Indialantic and Melbourne beaches. 
40. BROWARD COUNTY, FL BEACH 
EROSION CONTROL AND 
HILLSBORO INLET, FL 
NAVIGATION PROJECT 
Location. Broward County is on the lower east coast 
of Florida, 300 miles south of Jacksonville and about 
30 miles north of Miami. Hillsboro Inlet is in the 
northern part of Broward County. (See NOAA Nautical 
Chart No. 11466.) 
Existing project. The authorization provides for Federal 
participation toward cost of a shore restoration and 
protection project and a project to maintain a channel 
adequate for small craft navigation. Plan provides for 
restoration of a shoreline protection and recreational 
beach at 4 locations generally 100 feet wide with berm 
elevation of 10 feet above mean low water; a 
navigation channel 8 by 100 feet from the Intracoastal 
Waterway to a point 1,500 feet oceanward in Hillsboro 
Inlet, thence 10 by 150 feet in the ocean; jetties on 
north and south sides of ocean entrance; a permanently 
based floating dredge; and on a deferred basis, a trestlemounted 
sand-transfer plant, if needed. Navigation 
portion of the project is in an inactive status. Mean 
range of tide in areas is 2.5 feet. Plane of reference is 
mean low water. Cost estimate for new work (October 
1992 price levels) is $36,992,000 Federal and 
$36,197,000 non-Federal contribution. (See Table 9-B 
for Authorizing Legislation.) 
Local cooperation. Local interests must contribute 90.5 
percent of the first cost beach restoration in the reach 
between north county line and Hillsboro Inlet, 90 
percent of first cost allocated to beach restoration, and 
50 percent of first cost allocated to navigation for reach 
between Hillsboro Inlet and Port Everglades and 72.4 
percent of beach restoration in reach between Port 
Everglades and south county line; provide all lands and 
rights-of-way; obtain approval of Chief of Engineers of 
plans and specifications if local interests construct 
beach erosion features; and furnish assurances that 
they will hold the United States free from damages; 
provide and maintain adequate public landing or wharf 
at Hillsboro Inlet; establish a public body to cooperate 
financially and to provide and operate local facilities for 
navigation, control water pollution, maintain ownership 
of publicly owned shores, and maintain all project works 
except the jetties (maintenance of the channel to revert 
to the United States if sand-transfer plant is 
constructed). Assurances of local cooperation were 
accepted November 22, 1968. Non-Federal contribution 
for new work was $1,758,841. 
Operations and results during fiscal year. New work: 
Continuing beach nourishment cost $3,983,362. 
Engineering and design and construction management 
cost $62,417 and $3,066 respectively. 
Condition at end of fiscal year. Project was constructed 
by local interests and is complete. 
41. DUVAL COUNTY, FL 
Location. On upper east coast of Florida, within 20 
9-16

JACKSONVILLE, FL DISTRICT 
miles of Florida-Georgia line. Ocean shoreline is about 
16 miles long. (See NOAA Nautical Chart No. 11488.) 
Existing project. Provides for Federal participation 
toward cost of construction with artificial fill, a beach 
60 feet wide at elevation 11 feet above mean low 
water with a natural slope seaward, and for periodic 
nourishment for 10 years. Federal participation to be 
100 percent of the first cost of construction applicable 
to the Federal shore and 50 percent applicable to the 
other publicly owned shore and 55.5 percent of periodic 
nourishment cost for first 10 years of project life. Mean 
tidal range at south jetty in St. Johns River is 4.9 feet. 
Estimated cost of new work (October 1992 price 
levels) $82,250,000 Federal and $54,841,000 non- 
Federal ($52,462,000 contributed funds, $45,000 lands 
and damages and $2,334,000 for relocations). 
Project was authorized by River and Harbor Act of 
1965 (H 273/89/1). 
Local cooperation: Local interests must contribute 50 
percent of first cost of constructing non-Federal publicly 
owned shores; contribute 44.5 percent of periodic 
nourishment costs for first 10 years of project life; 
provide all lands, rights-of-way, and relocations; hold 
the United states free from damages; control water 
pollution; and furnish assurances that they will maintain 
continued public ownership of the shore upon which the 
amount of federal participation is based during economic 
life of project. Assurances of local cooperation were 
accepted on November 29, 1973. Non-Federal 
contribution for new work was $11,609,567. 
Operations and results during fiscal year. New work: 
Beach nourishment continued at a cost of $698,303. 
Engineering and design and construction management 
cost $44,758 and $129,381 respectively. 
Condition at end of fiscal year. Initial beach fill and 4 
year advance nourishment has been completed. 
42. INDIAN RIVER COUNTY, FL 
Location. Indian River County is on the east coast of 
Florida, midway between Jacksonville and Miami. The 
authorized project comprises 2.65 miles of beach along 
the ocean shore of Vero Beach and 1.7 miles along the 
Sebastian Inlet State Park. (See NOAA Nautical Chart 
Nos. 11474 and 11476.) 
Existing project. The authorized project provides 
nourishment for 8,870 feet (1.68) miles) of the State 
Park, south of Sebastian inlet. The initial beach fill 
would consist of 202,000 cubic yards of nourishment 
material. An estimated 202,000 cubic yards of periodic 
nourishment at 5-year intervals would be required. The 
Federal share of the first cost was estimated to be 65 
percent of this segment. 
The plan also provided for nourishment of 9,180 feet 
(1.74 miles) of Vero Beach. The initial beach fill 
consisted of 572,000 cubic yards of material, including 
advance nourishment. The restored beach would have 
a 20 foot wide level berm at an elevation of 15 feet 
above mean low water. The beach fill as designed 
would provide protection against a 10 year return 
interval storm. An estimated 120,000 cubic yards of 
periodic nourishment would be required at 5 year 
intervals. In addition to the beach fill a "Sabecon" reef 
breakwater was recommended. The structure would be 
placed 500 feet offshore of the new beach and would 
be 400 feet in length, with a zero mean low water crest 
elevation. The Federal share of the first cost was 
estimated to be 43.7 percent for this segment. 
The project was authorized on November 17, 1986 
(Public Law 99-662) by the 1986 Water Resource 
Development Act. 
Local cooperation. The authorization of a beach erosion 
control project for Indian River County, Florida was 
made with the provision that the State and local 
interests will, in addition to the general requirements, 
agree to comply with the following requirements: 
provide all necessary lands, easements and rights-of 
way; including borrow areas and disposal areas for 
excavated material, and relocations; hold and save the 
United States free from claims for damages; assure 
continued conditions of public ownership and public use 
of the shore; assure maintenance and repair during the 
economic life of the project; provide and maintain as 
necessary access roads, parking areas and other public 
use facilities; provide a cash contribution for periodic 
nourishments for the life of the project; provide an 
additional cash contribution for the Sebastian Inlet State 
Park Beach. The project, as authorized, provides that 
the work may be accomplished in separate units or 
features and that the written agreement with non- 
Federal interests be obtained. The Indian River County 
Board of Commissioners, by letters dated December 21, 
1984 and January 15, 1987, affirmed their support for 
the project and their willingness and ability to share in 
project costs. 
Operations and results during fiscal year. New work: 
None. 
Condition at end of fiscal year. Continuation of 
planning and engineering. 
43. MANATEE COUNTY, FL 
Location. Manatee County is on the west coast of 
Florida, just south of the entrance to Tampa Bay. The 
county's 14 mile gulf shoreline consists of 2 barrier 
islands, Anna Maria Key and the northern half of 
Longboat Key, separated from the mainland by Tampa 
and Sarasota Bays and from each other by Longboat 
Pass. Project consists of about 7.5 miles of gulf 
shoreline. 
Existing project. Provides for Federal participation in 
the shore protection project for Manatee County which 
includes the entire 7.5 mile gulf shoreline of Anna Maria 
Key. The project consists of restoration of 3.2 miles of 
gulf shore beach to an elevation 6 feet above mean low 
water with a level berm 50 feet wide and a natural 
slope seaward as would be shaped by wave action. The 
project also provides for periodic nourishment of the 
restored beach and such adjacent shoreline as may be 
and justified for the project life. Mean tidal range is 2.3 
feet. 
Estimated cost (October 1992 price levels) is 
$23,262,000 Federal funds and $19,180,000 non- 
Federal funds ($19,124,000 contributed funds and 
$56,000 lands and damages). (See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. The authorization of a shore 
protection project for Manatee County, Florida was 
9-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
made with the provision that Federal cost sharing would 
be in accordance with policy established by existing 
law, and the percentages based on conditions of shore 
ownership and use existing at the time of construction: 
Provided that, prior to construction, local interests 
furnish assurances satisfactory to the Secretary of the 
Army that they will: (a) Provide without cost to the 
United States all lands, easements, and rights-of-way, 
including borrow areas, and relocations necessary for 
construction of the improvements; (b) Provide a cash 
contribution equal to 47 percent of the first cost of 
construction, subject to any credit for eligible 
construction costs incurred by local interests, and 
exclusive of costs for lands, easements, rights-of-way, 
relocations, and alterations, and exclusive of the cost of 
fill placed behind the Corps construction line, the final 
percentage to be based on shore ownership and use 
existing at the time of construction; (c) Provide all costs 
of construction for nourishment landward of the Corps 
construction line; (d) Provide a cash contribution for 
periodic nourishment equal to 41 percent of the cost of 
each nourishment, such contribution to be made prior to 
each nourishment operation, and the final percentage to 
be based on shore ownership and use existing at the 
time of construction; (e) Hold and save the United 
States free from damage due to the construction works, 
except for damages due to the fault or negligence of 
the United States or its contractors; (f) Assure 
continued public ownership and administration of the 
shore upon which the amount of Federal participation is 
based; (g) Provide without cost to the United States 
appropriate access and facilities, including parking and 
sanitation, necessary for realization of the public 
benefits upon which Federal participation is based; (h) 
Adopt appropriate ordinances, or provide other means, 
to insure the intended use of the beach fill areas; (i) 
Control water pollution to the extent necessary to 
safeguard the health of bathers; and (j) Agree to pay 
100 percent of the operation, maintenance, and 
replacement and rehabilitations costs of the project, or 
functional element thereof. 
Operations and results during fiscal year. New work: 
Lands and damages cost $28,082. Engineering and 
design and construction management cost was 
$298,653 and $1,692 respectively. 
Condition at end of fiscal year. The revised GDM for 
construction of 3.2 miles of initial beach fill at Anna 
Maria Island was completed in October 1991. Contract 
awarded August 1992 and is scheduled for completion 
in September 1993. 
44. NASSAU COUNTY, FL 
Location. Nassau County is on the east coast of 
Florida, north of Jacksonville and adjoins the state of 
Georgia. The authorized project comprises 4.3 miles of 
beach along the ocean shore of northern Amelia Island, 
and tightening 1,500 feet of the shoreward end of the 
existing south jetty at the entrance to Fernandina 
Harbor. 
Existing project. The authorized project would provide 
initial restoration of 3.6 miles of eroded beach, starting 
at a point about .7 mile south of the Fernandina Harbor 
south jetty and extending south to Sadler Road; sand 
tightening about 1,500 feet of the shoreward end of the 
south jetty; and periodic nourishment of 4.3 miles of 
shore between the south jetty and Sadler Road. The 
restored beach would have a 20 foot wide level berm at 
an elevation of 13 feet above mean low water. The 
initial beach fill would consist of an estimated 
1,100,000 cubic yards of nourishment material. An 
estimated 240,000 cubic yards of nourishment at 2- 
year intervals would be required. Sand tightening would 
require about 16,700 tons of stone. The Federal share 
of the first cost was estimated to be 77%. (Sand 
tightening, accomplished as part of the Navy's effort to 
deepen and widen the navigation channel, was deleted 
from the plan.) 
Estimated cost of new work (October 1992 price levels) 
$9,874,000 Federal and $2,426,000 non-Federal 
contributed funds. 
Local cooperation. The authorization of a shore 
protection project for Nassau County, Florida was made 
with the provision that the State and local interests will, 
in addition to the general requirements, agree to comply 
with the following requirements: provide without cost to 
the United States all necessary lands, easements, and 
rights-of-way , including borrow areas and disposal 
areas for excavated material and relocations required for 
construction of the project, including that required for 
periodic nourishment; hold and save the United States 
free from claims for damages which may result from 
construction and subsequent maintenance, operation 
and public use of the project, except damages due to 
the fault or negligence of the United States or its 
contractors; assure continued conditions of public 
ownership and public use of the shore upon which the 
amount of Federal participation is based during the 
useful life of the project; assure maintenance and repair 
during the useful life of the project as required to serve 
the project's intended purpose; provide and maintain 
clearly marked beach access, nearby parking areas, and 
other public use facilities, open to all on equal terms, 
and as required to realize the benefits upon which 
Federal participation is based; provide a cash 
contribution for beach erosion control equal to the 
appropriate percentage of the final construction cost 
allocated to this function, exclusive of lands, 
easements, rights-of-way, alterations, and relocations, 
the percentage to be in accordance with existing law 
and based on shore ownership at the time of 
implementation; provide a cash contribution for periodic 
nourishment during the useful life of the project, such 
contribution to be made prior to each nourishment, with 
the actual amount to be based on existing law and 
conditions of ownership at the time of each 
nourishment; and at least annually inform affected 
interests of the limitations of the protection afforded by 
the project. 
Operations and results during fiscal year. None. 
Condition at end of fiscal year. Planning and 
engineering continued. 
45. PALM BEACH COUNTY, FL 
Location. Palm Beach County is on the east coast of 
Florida about 300 miles south of Jacksonville and 70 
miles north of Miami. Project consists of about 30 miles 
of ocean coastline under 2 separate authorizations. (See 
NOAA Nautical Chart No. 11466.) 
Existing project. Project authorization, the River and 
Harbor Act of 1962, provides for Federal participation 
toward the cost of local shore project for restoration of 
beaches to a general width of 100 feet with a berm 
9-18

JACKSONVILLE, FL DISTRICT 
elevation of 10 feet above mean low water, and 
periodic nourishment for 10 years from the year of 
initial nourishment, as follows: 62.1 percent of the cost 
for Martin County line-Jupiter Inlet segment; 55.8 
percent of cost for Jupiter Inlet-Lake Worth Inlet 
segment; and 50 percent for south Lake Worth Inlet- 
Delray Beach; and 53 percent of cost for Delray Beach- 
Boca Raton inlet segment. Mean range of tide is 2.8 
feet in the Atlantic Ocean at Palm Beach and 2.3 feet 
at Boca Raton Inlet. 
The River and Harbor Act of 1958 authorization 
provides for Federal participation in the costs of a plan 
for protection of the shore of Palm Beach Island, 
comprising restoration of a protective beach with berm 
elevation of 10 feet above mean low water, to a 
general width of 150 feet at mean high water from 
Lake Worth Inlet to a point about 1,000 feet south of 
Southern Boulevard extended, thence with a general 
width of 100 feet to South Lake Worth Inlet, 
construction and operation of a sand-transfer plant at 
Lake Worth Inlet, and additional periodic nourishment 
from Lake Worth or other suitable source, substantially 
in accordance with the plan developed by the district 
engineer, with such modifications thereof as may be 
considered advisable by the Chief of Engineers. Federal 
assistance would entail contribution of funds in amount 
of 4.7 percent of the initial construction cost of the 
beach restoration and appurtenant drainage work, and 
of the expenditures for periodic nourishment from Lake 
Worth for a period of 10 years from the year of the 
initial placement, plus 19.3 percent of the expenditures 
for construction, and for operation, maintenance, and 
current replacements of parts of the sand-transfer plant 
for the same period. Mean tidal range is 2.8 feet in the 
Atlantic Ocean at Palm Beach and 2.3 feet at Boca 
Raton Inlet. 
Estimated cost (October 1992 price levels) for Palm 
Beach County is $38,448,000 Federal and 
$32,981,000 non-Federal cash contribution and for 
Palm Beach Island $12,452,000 Federal and 
$88,325,000 non-Federal cash contribution. (See Table 
9-B for Authorizing Legislation.) 
Local cooperation. Federal participation is subject to 
the conditions that responsible local authorities will: (a) 
obtain approval by the Chief of Engineers, prior to 
commencement of work on the project (except the 
sand-transfer plant already under contract), of detailed 
plans and specifications and arrangements for 
prosecution of the work on the project; (b) make 
appropriate modification of the location of the end of 
the discharge line of the sand-transfer plant to 
accomplish satisfactory dispersion of bypassed material; 
(c) provide at their own expense all necessary lands, 
easements, and rights-of-way; (d) furnish assurances 
satisfactory to the Secretary of the Army that they will: 
(1) assure maintenance of the protective measures 
during their economic life as may be required to serve 
their intended purpose, and periodic nourishment of the 
protective beach at suitable intervals, including 
operation of the sand-transfer plant; (2) control water 
pollution to the extent necessary to safeguard the 
health of bathers; and (3) maintain continued public 
ownership of the publicly owned shores upon which a 
part of the recommended Federal participation is based 
and their administration for public use during the 
economic life of the project. 
Operations and results during fiscal year. New work: 
Lands and damages cost $1,592. Engineering and 
design cost $112,188. 
Condition at end of fiscal year. Review is ongoing of 
locally prepared GDM for Jupiter/Carlin with approval 
scheduled for April 1993. The contract for the third 
renourishment of Delray beach is scheduled to be 
completed February 1993. The local sponsor submitted 
a draft GDM in June 1991 for initial construction of 1.5 
miles of beach fill at Midtown. The GDM is currently 
under review in SAD. 
46. PINELLAS COUNTY, FL 
Location. Pinellas County is on the Gulf coast of 
Florida, about midway of the peninsula. It extends 
northerly about 39 miles from the main entrance to 
Tampa Bay to the vicinity of the mouth of Anclote 
River. (See NOAA Nautical Chart No. 11411.) 
Previous project. For details see page 429 of Annual 
Report for 1965. 
Existing project. The authorized project provides for 
Federal participation in preserving and protecting the 
shores of Pinellas County, Florida, by: restoration of 
5,000 feet of beach at Clearwater Beach Island; 
restoration of 49,000 feet of beach at Sand Key; 
restoration of 9,200 feet of beach at Treasure Island; 
construction of 600 feet of revetment at Long Key; and 
advance nourishment of Long Key and periodic 
nourishment of each island. Estimated cost (October 
1992 price levels) is $95,463,000 Federal funds and 
$77,941,000 non-Federal funds ($77,470,000 
contributed funds and $471,000 lands and damages). 
(See Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must (a) contribute 
in cash the required percentages of the first costs of 
work provided by the Corps of Engineers, the 
percentages varying with the type of beach ownership; 
94.1 to 50 percent of the beach restoration at 
Clearwater Beach; 98.1 to 50 percent of the 
improvement at Sand Key; 94.3 to 50 percent of the 
improvement at Treasure Island; and 50 percent of the 
first cost of the revetment at Long Key; (b) contribute 
in cash an amount computed in accordance with the 
cost sharing provision contained in P.L. 826, 84th 
Congress as amended by P.L. 87-874, for beach 
nourishment cost for the first 10 years of the project 
life; (c) provide lands, easements, and rights-of-way; (d) 
assure maintenance and repair of the stone revetment 
of Long Key; (e) assure periodic nourishment of the 
restored beaches; (f) assure public ownership of 
beaches; (g) assure against water pollution; (h) hold the 
United States free from damages; and (i) provide beach 
for public use. Assurances of local cooperation were 
accepted March 22, 1967. 
Operations and results during fiscal year. New work: 
Lands and damages cost was $12,629. Contract costs 
were $6,067,280. Engineering and design and 
construction management cost $229,486 and $579,659 
respectively. 
Condition at end of fiscal year. Sand Key's initial 
construction will be completed in 1993. The WRDA of 
1986 authorization provides for extension of Federal 
participation to 50 years for Long Key, Treasure Island, 
Sand Key, and Clearwater Beach Island. A new countywide 
LCA is under preparation for future periodic 
9-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
nourishments. An addendum to the GDM is under 
preparation for extension of the revetment at the 
northern end of Treasure Island. Completed works 
include groins at Treasure Island, Pass-A-Grille, and 
Johns Pass; breakwaters at Redington Shores and Long 
Key, and initial fill at Treasure Island, Long Key and 
Sand Key. 
47. SARASOTA COUNTY, FL 
Location. Sarasota County is on the Gulf coast of 
Florida about 30 miles south of Tampa Bay. The 
northern most portion of the project adjoins the 
Manatee County Beach Erosion Control Project on 
Longboat Key. The total project consists of about 5.7 
miles of gulf shoreline on Longboat Key and Venice 
Beach. 
Existing project. The authorized project provides for 
Federal participation in the construction of a protective 
beach 12,600 feet long at Longboat Key and a 
protective beach 29,400 feet long at Manasota Key at 
the City of Venice, Florida. Two borrow areas will be 
required. The first is located within 2 shoal areas 
located between 1 to 2 miles offshore of Manasota Key 
south of the project area. This borrow area will be 
supplemented by material located within the ebb tidal 
shoal of Big Sarasota Pass which is about 13 nautical 
miles north of the project beach at Venice. The project 
also provides periodic nourishment of the restored beach 
and such adjacent shoreline as may be needed and 
justified for life of the project. The mean tidal range is 
2.1 feet. 
Estimated cost (October 1992 price levels) is 
$29,036,000 Federal and $17,697,000 non-Federal 
($17,673,000 contributed funds and $24,000 lands and 
damages). The Federal share of each periodic 
nourishment is 72.55 percent for Venice, and 15.4 
percent for Longboat, of applicable nourishment costs. 
Local cooperation. Federal participation is subject to 
the conditions that responsible local authorities will: (a) 
provide without cost to the United States all lands, 
easements, and rights-of-way, including borrow areas, 
and relocations necessary for construction of the 
improvements; (b)provide a cash contribution equal to 
29.3 percent of the first cost of construction, subject 
to any credit for eligible construction costs incurred by 
local interests, and exclusive of costs for lands, 
easements, and rights-of-way, relocations, and 
alterations, and exclusive of the cost of fill placed 
behind the Erosion Control Line (ECL), the final 
percentage to be based on shore ownership and use 
existing at the time of construction; (c) provide all costs 
of construction for nourishment of private lands and 
share in the costs of construction for public lands 
landward of the Erosion Control Line (ECL); (d) provide 
a cash contribution for periodic nourishment equal to 
29.3 percent of the cost of each nourishment, such 
contribution to be made prior to each nourishment 
operation, and the final percentage to be based on 
shore ownership and use existing at the time of 
construction; (e) hold and save the United States free 
from damage due to the construction works, except for 
damages due to the fault or negligence of the United 
States or its contractors;(f) assure continued public 
ownership and administration of the shore upon which 
the amount of Federal participation is based; (g) provide 
without cost to the United States appropriate access 
and facilities, including parking and sanitation, necessary 
for realization of the public benefits upon which Federal 
participation is based; (h) adopt appropriate ordinances, 
or provide other means, to insure the intended use of 
the beach fill areas; (i) control water pollution to the 
extent necessary to safeguard the health of bathers; 
and (j) agrees to pay 100 percent of the operation, 
maintenance, and replacement and rehabilitation costs 
of the project, or functional element thereof. 
Operations and results during fiscal year. New work: 
Engineering and design cost $262,057. 
Condition at end of fiscal year. Plans and specs were 
approved in June 1992. A construction contract is 
scheduled for award in October 1993 following 
coordination of the storm water outfall relocation plan 
by the City of Venice. The plan is expected to be 
completed in March 1993. 
48. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
Key West, FL; Lido Key, FL; Mullet Key, FL; Virginia 
Key and Key Biscayne, FL were deauthorized January 1, 
1990 by the W.R.D.A. of 1988, P.L. 100-676. (See 
Table 9-D.) 
49. BEACH EROSION CONTROL 
ACTIVITIES UNDER SPECIAL 
AUTHORIZATION 
Beach erosion control activities pursuant to section 103, 
Public Law 87-874 (preauthorization) 
Reports incurring costs during the fiscal year were Fort 
Pierce Beach, FL $122,858; Little Talbot Island, FL 
$33,562; Isla de Cabras, PR $51; Northside Drive, 
Fredricksted, VI $10,798; Patillas, PR $9,625; Puerto 
Nuevo Beach, PR $144. 
Beach erosion control activities pursuant to section III, 
Public Law 90-433, Mitigation of Shore Damages 
Attributable to Navigation Projects. 
No costs were incurred under the above authorization. 
Beach erosion control activities pursuant to Shoreline 
Erosion Control Act of 1074, Public Law 93-251. 
No costs were incurred under the above authorization. 
Flood Control 
50. CENTRAL AND SOUTHERN FLORIDA 
Location. The project is generally located within the 
southeastern 18 counties of Florida covering an area of 
about 15,200 square miles. It is comprised of the Upper 
St. Johns River basin in the northeastern section of 
project, Kissimmee River basin in central section north 
of the Lake Okeechobee-Everglades area in the central 
and southwestern section, and the east coast 
Everglades area in southeastern section. 
Previous projects. Completed works for control of Lake 
Okeechobee were included in and constructed under the 
navigation project for Okeechobee Waterway, FL 
(formerly Caloosahatchee River and Lake Okeechobee 
drainage area, FL) and under provisions of River and 
Harbor Acts of July 3, 1930 and August 30, 1935. For 
9-20

JACKSONVILLE, FL DISTRICT 
further information, see Annual Reports for 1948 and 
1949. 
Existing project. The authorized project is for flood 
relief and water conservation and provides principally 
for: an east coast protective levee extending from the 
Homestead area north to the eastern shore of Lake 
Okeechobee near the St. Lucie Canal; three 
conservation areas for water impoundment in the 
Everglades area west of the east coast protective levee 
with control structures to effect transfer of water as 
necessary; local protective works along the lower east 
coast; encirclement of the Lake Okeechobee agricultural 
area by levees and canals; enlargement of portions of 
Miami, North New River, Hillsboro, and West Palm 
Beach Canals; enlargement of the existing Lake 
Okeechobee levees and construction of new levees on 
the northeast and northwest shores of the lake; 
increased outlet capacity for improved control of Lake 
Okeechobee; floodway channels in the Kissimmee River 
basin, with suitable control structures to prevent overdrainage; 
an interrelated system of canals, levees, 
pumping stations, and structures in southwest Dade 
County to control water levels; and facilities for 
regulating floods in Upper St. Johns River basin; a 
system of canals and control structures for gravity 
drainage of Martin County and distribution of available 
water supplies to portions of Martin and St. Lucie 
Counties; and works to improve the supply, distribution, 
and conservation of water resources in central and 
southern Florida, including the Lake Okeechobee 
agricultural area, Everglades National Park, and other 
related areas. The project will provide water control and 
protection from recurrence of the devastating 
floodwaters from the Everglades and local sources, for 
the highly developed urban area along the lower east 
coast of Florida and for the productive agricultural areas 
around Lake Okeechobee (including towns around the 
lake), in the Upper St. Johns and Kissimmee River 
basins, and in South Dade County. 
The project includes a total of 990 miles of levees, 
978 miles of canals, 30 pumping plants, 212 floodway 
control and diversion structures, 56 railroad bridge 
relocations, and 2 highway bridge relocations. 
The project also provides that upon completion, local 
interests assume operation and maintenance of all 
completed works except levees, channels, locks, and 
control works for regulation of Lake Okeechobee and 
the main control structures of conservation areas, which 
will be operated and maintained by the United States. 
The principal features of the hurricane gates, 
constructed under previous projects for Okeechobee 
Waterway and maintained under existing project since 
July 1, 1950, are set forth in Table 9-Q. Also, see 
Table 9-N for principal features of locks and dams. 
Estimated cost for new work (October 1992 price 
levels) is $994,013,000 Federal funds and 
$572,706,000 Non-Federal funds ($241,322,000 
contributed funds, $257,469,000 lands, $73,915,000 
relocations), exclusive of river and harbor funds 
expended on previous projects.(See Table 9-B for 
Authorizing Legislation.) 
Local cooperation. (See Table 9-R for local cash 
contribution.) Local interests must also: provide lands, 
rights-of-way, and spoil disposal areas; hold the United 
States free from damages; bear the cost of maintenance 
and operation of all works except those having to do 
with regulation of Lake Okeechobee and the main 
control structures of conservation areas; construct and 
maintain lateral drainage facilities; prohibit 
encroachment on flood-carrying capacity of the 
improved channels; and assume cost of all new highway 
bridges, relocations of existing bridges and alterations to 
utilities incident to construction of the project. In 
addition, for small boat navigation channels, local 
interests must provide, maintain, and operate adequate 
public landings, sanitary and access facilities, and 
establish regulations prohibiting discharge of pollutants 
into the waters of the locks and channels by users 
thereof. 
Assurances of local cooperation have been accepted 
by the District Engineer for all items of work authorized 
to date. 
Operations and results during fiscal year. (See Table 9- 
S for work accomplished.) 
Operations and care. a. Features completed under 
previous navigation project for Okeechobee Waterway 
and being maintained under this project are: a levee 
about 70 miles long following in general the south shore 
of Lake Okeechobee and a north shore levee 15.8 miles 
long; spillways at Ortona and St. Lucie Locks; 5 
hurricane gates; and 16 spillways along St. Lucie Canal. 
b. Features completed under existing project that are 
to be maintained with operation and maintenance funds 
are: (1) Levees 47, 48, 49 and 50 -- total length 63 
miles and enlargement of existing levees L-D1, L-D2, LD3, 
L-D4, and L-D9, (2) spillway structures S-10, S- 
11, S-12, S-18C, S-77, and S-78 (3) C-43, Section 4 
(Caloosahatchee River), and (4) W.P. Franklin Lock and 
Dam. 
In addition to the actual facilities listed above it is 
necessary under operation and maintenance to continue 
meteorological studies, water level records, stream 
gaging stations, etc., for proper regulation of the level 
of Lake Okeechobee and storage of water in 
Conservation Areas 1, 2 and 3. 
Corps of Engineers - The Corps of Engineers operates 
and maintains the major outlets to Lake Okeechobee 
and Water Conservation Area Nos. 1, 2A and 3A in 
central and southern Florida. 
South Florida Water Management District - SFWMD is 
responsible for operation and maintenance of the project 
facilities, including major pumping stations, spillways, 
locks (except on Okeechobee Waterway), levees and 
culverts. 
Condition at end of fiscal year. The scheduled work of 
project is 77 percent complete. Planning for the entire 
project began in November 1948 and has been 
continued. For construction completed prior to FY 1980 
see Annual Reports for 1960-1979. Construction 
completed under existing project during the fiscal year 
is set forth in Table 9-0. All Federally maintained 
features of the project were generally in good condition 
at the end of the fiscal year. (For status of work under 
contract at end of fiscal year see Table 9-P.) 
51. DADE COUNTY, FL 
Location. Dade County is on the southeast coast of 
Florida. Project area consists of that part of the Atlantic 
9-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
shoreline of the county from Government Cut north to 
Bakers Haulover Inlet and at Haulover Beach Park. (See 
NOAA Nautical Chart No. 11466.) 
Existing project. Project provides for a protective and 
recreational beach having a dune at elevation 11.5 feet 
and a level berm 50 feet wide at elevation 9 feet, mean 
low water, for beach erosion control and hurricane 
protection between Government Cut and Bakers 
Haulover Inlet; a protective and recreational beach with 
a berm elevation of 9 feet for beach erosion control at 
Haulover Beach Park; and Federal participation in the 
initial construction and in periodic nourishment of both 
the above reaches for the first 10 years of project life. 
Plane of reference is mean low water. Mean range of 
tide in the area is 2.5 feet. 
Estimated cost of the project (October 1992 price 
levels) is $109,934,000 Federal cost and $98,292,000 
non-Federal cost ($96,443,000 contributed funds and 
$1,839,000 lands and damages). 
Project was authorized by Flood Control Act of 1968 
(H 335/90/2). 
Local cooperation. Local interests must (a) contribute 
for the first cost of the work: between Government Cut 
and Bakers Haulover Inlet amounts ranging from 60.2 
percent of the cost of the fill within the project limit 
with existing shorefront ownership, and 100 percent of 
the cost of fill required landward of the project limit; 
and for the work at Haulover Beach Park, contribute 
21.3 percent of the entire first cost excluding costs for 
lands, easements, rights-of-way, relocations, and 
preproject work, but including credit for preproject 
work; (b) contribute in cash for the first 10 years of 
project life, amounts ranging from 88.9 percent of the 
nourishment cost for the beach, with existing 
ownership, to 60.7 percent with public ownership, and 
the entire maintenance cost for dune, all between 
Government Cut and Bakers Haulover Inlet; (c) provide 
all lands and rights-of-way; (d) hold United States free 
from damages; (e) assure continued public ownership 
and use of the shore upon which the amount of Federal 
Faparticipation is based; (f) assure maintenance of the 
groin, and after 10 years of project life, periodic 
nourishment of the protective beach and maintenance 
of the dune during the economic life of the project; (g) 
assure that water pollution will not be permitted; (h) 
prevent removal or relocation by man of fill from the 
beach berm and dune; (i) prevent the erection of 
barriers to the littoral movement of material that would 
interfere with the nourishment of the beach; (j) maintain 
at the parks qualifying for 70 percent Federal 
participation a zone that excludes permanent human 
habitation; (k) at least annually inform interests affected 
that the project will not provide complete protection 
from a hurricane tide level equal to or higher in 
elevation than that of the hurricane of September 1926; 
and (1) establish in public ownership for public use the 
beaches within project limits as a requirement for 
Federal participation in the allocated beach erosion 
control costs of improvement of shores presently in 
private ownership. Assurances of local cooperation were 
accepted January 16, 1973. A supplemental agreement 
for Bal Harbour portion was approved June r30, 1976. 
Non-Federal contribution for new work was 
$27,857,335. 
Operations and results during fiscal year. New work: 
Beach renourishment contract cost was $980,581. 
Engineering and design and construction management 
cost $158,137 and $15,145 respectively. 
Condition at end of fiscal year. The local sponsor 
desires renourishment of 6 areas of the 13 mile project 
in 1993. Surveys are underway to determine the 
location and quantity of fill required. Contract scheduled 
for award in August 1993. 
52. DADE COUNTY, NORTH OF 
HAULOVER BEACH, FL 
Location. On the southeast coast of Florida. Project 
area consists of that part of the Atlantic shoreline 
extending 2.5 miles north of Haulover Beach Park. (See 
NOAA Nautical chart No. 11466.) 
Existing project. The existing shore protection project 
for Dade County provides for Federal participation in 
the cost of construction of a beach fill for the purpose 
of erosion control and hurricane protection along 9.3 
miles of shore between Government Cut and Bakers 
Haulover Inlet and for the construction of a beach fill 
for the purpose of erosion control along the 1.2 miles 
of shore fronting Haulover Beach Park and provides for 
protection and nourishment of 2.5 miles of beach shore 
north of Haulover Beach Park and for extension of the 
period of Federal participation from 10 years to the life 
of the project. (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Consistent with the cost-sharing 
and financing concepts agreed to by the administration 
and Senate Majority Leadership, local interests will be 
required to: provide lands, easements, and rights-ofway 
and relocations; pay 50 percent of the separable 
and joint costs allocated to recreation; pay 35 percent 
of the cost allocated to storm damage prevention; hold 
the United States free from damages; control water 
pollution; and furnish assurances that they will maintain 
continued public ownership of the shore upon which 
the amount of Federal participation is based during 
economic life of project. Assurances of local 
cooperation have been requested from local sponsors. 
Non-federal contribution for new work was $7,499,000. 
Operations and results during fiscal year. New work: 
Engineering and design and construction management 
cost $370 and $153 respectively. 
Condition at end of fiscal year. Continuation of 
planning and engineering. 
53. FOUR RIVER BASINS, FL 
Location. The Four River Basins area covers about 
6,000 square miles within 14 counties in central and 
southwest peninsular Florida. Project includes all or part 
of the four main stream basins -- the Hillsborough, 
Oklawaha, Withlacoochee, and Peace Rivers -- and all 
of three smaller coastal basins north of Tampa, Florida, 
drained by the Pithlachascotee and Anclote Rivers and 
Lake Tarpon. 
Existing project. The authorized project provided for 
improvements for control of floods and drainage, and 
for conservation through construction of necessary 
canals, levees, reservoirs, and control structures. More 
specifically, the project provided for: Green Swamp 
Area - a conservation area and 3 storage reservoirs 
9-22

JACKSONVILLE, FL DISTRICT 
with necessary canals and control structures; 
Hillsborough River - 4 flood-storage reservoirs, with 
necessary channels, control structures and levees; 
Ok/awaha River -a levee on the north shore of Lake 
Apopka, improvement of parts of the river channel and 
a west bank levee below Moss Bluff lock and dam, and 
replacement of the lock and dam; Withlacoochee River 
-- one flood-storage reservoir with outlet canals and 
control structures; Peace River -- Peace Creek canal and 
control structures and improvements to the existing 
water control and drainage features; Gulf Coastal Areas- 
Lake Tarpon; outlet canal and control structure; 
Pithlachascotee River: reservoir with outlet canals and 
control structures. (See Table 9-T on Moss Bluff Lock.) 
Estimated cost for new work (October 1992 price 
level) is $171,715,000 Federal funds and 
$147,053,000 non-Federal ($34,508,000 contributed 
funds, $48,018,000 relocations and $64,527,000 for 
lands and damages). (See Table 9-B for Authorizing 
Legislation.) 
Local cooperation. Local interests must furnish all 
lands, and rights-of-way; provide all alterations or 
replacements of public and private utilities, roads, 
bridges (except railroad bridges), etc.; hold the United 
States free from damages; operate and maintain all 
project works after completion; construct and maintain 
such associated works as are necessary to realize 
benefits made available by the project works; and 
contribute in cash 17 percent of the first cost of 
construction and 50 percent of recreation costs. 
Operations and results during fiscal year. New work: 
Engineering and design cost $38,536. 
Condition at end of fiscal year. Construction of the 
project commenced April 18, 1966 and the scheduled 
work is 98 percent complete. 
relocations, and highway bridges and approaches). (See 
Table 9-B for Authorizing Legislation.) 
Local cooperation. Local interests must provide all 
lands, easements, and rights-of-way; hold the United 
States free from damages; operate and maintain all 
project works after completion; repay construction cost 
allocated to water supply in accordance with Water 
Supply Act of 1958; pay one-half of the separable cost 
allocated to recreation and fish and wildlife 
enhancement; prohibit discharge of inadequately treated 
sewage and other pollutants into the reservoir; and 
prevent encroachment on downstream channels. 
Assurances of local cooperation have not been 
completed, except for Cerrillos Reservoir which was 
signed March 15, 1982. Non-Federal contribution for 
new work was $90,000. 
Operations and results during fiscal year. New work: 
Lands and damages cost was $1,080. Contract for 
Cerrillos Dam & Spillway continued at a cost of 
$11,082,388. Contract for the Cerrillos Reservoir 
clearing cost $124,915. Cerrillos Dam instrumentation 
installation contract cost was $167,620. Hired labor 
cost was $1,410,949. Portugues Debris Basin contract 
no. 3 cost $729,793. Bucana Shoal Removal contract 
cost $1,879,405. Hired labor for channels and canals 
cost $8,965. Cultural resource investigations cost 
$33,779. Area office equipment cost $6,689. 
Engineering and design and construction management 
cost $2,329,919 and $1,771,054 respectively. 
Condition at end of fiscal year. Construction of the 
Cerrillos Dam was completed in January 1992. The 
recreation DM is scheduled for approval in November 
1992 with construction in February 1994. Constancia 
Park was awarded in July 1992, and Debris Basin #4 
was awarded in September 1992. Project commenced 
in September 1975 and is 74 percent complete. 
55. INSPECTION OF COMPLETED FLOOD 
54. PORTUGUES AND BUCANA RIVERS, CONTROL PROJECTS 
PR 
(This project authorized as Lago de Cerrillos, Lago de 
Portugues, and Channel Improvement at Ponce.) 
Location. Portugues and Bucana Rivers originate on the 
southern slopes of Cordillera Central divide of Puerto 
Rico and flow from this central ridge of the island to the 
Caribbean Sea. Their drainage areas are 22.6 and 31.4 
square miles, respectively. Ponce, the second largest 
city in Puerto Rico, is located in the lower coastal area 
along Portugues River and is the only urban community 
in the two basins. 
Existing project. The authorized project provides for 2 
multiple-purpose reservoirs for flood control, water 
supply, general recreation, and fish and wildlife 
enhancement - one on Portugues River and the other 
on Cerrillos River, a tributary to the Bucana River; 
enlargement of about 5.7 miles of the Bucana River, 
with an additional 0.2 mile long tieback levee at the 
upstream terminus of the improvement; enlargement of 
2.1 miles of the Portugues River, with an additional 0.5 
mile of tieback levee at the upstream terminus of the 
improvement; and a 1.3 mile diversion channel 
connecting Portugues River to lower Bucana River. 
Estimated cost of the project (October 1992 price 
levels) is $385,927,000 Federal and $135,215,000 
non-Federal ($42,078,000 contributed funds, 
$73,296,000 for lands and damages, $19,841,000 for 
Features transferred to the Central and Southern Florida 
Flood Control District and Southwest Florida Water 
Management District were inspected quarterly during 
the fiscal year at a total cost of $10,976. 
56. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 9-E.) 
57. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, Public 
Law 685, 84th Congress, as amended 
(preauthorization). 
(See Table 9-V.) 
Emergency flood control activities -- repair, flood 
fighting, and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Federal costs for the fiscal year were $319,136 for 
the Disaster Preparedness Program. No costs were 
incurred for Emergency Operations. 
9-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY" 1992 
Emergency streambank and shoreline protection 
activities pursuant to Section 14, Public Law 526, 79th 
Congress as amended (preauthorization). 
Federal cost for the fiscal year was Bradenton Beach, 
FL $3,105; Ft. Clinch, Nassau County, FL $395,323; 
Guanica, PR $39,562; Ponce Regional, PR $11,867; 
and Juan Mendez Channel, PR $1,173. 
General Investigations 
58. SURVEYS 
Hired labor costs during the fiscal year were: 
navigation studies $589,100; flood damage prevention 
studies $1,804,227; shoreline protection studies 
$101,876; review of authorized projects $33,865; 
special investigations $104,199; and coordination with 
other agencies and non-Federal interests $125,484; for 
a total cost of $2,758,801. 
59. COLLECTION AND STUDY OF BASIC 
DATA 
The requirement for preparation of regular flood plain 
information studies has been rescinded. FPI studies that 
deal with land use changes will continue to be prepared. 
FPMS Unit Jacksonville, FL cost $32,602; Technical 
Services $90,029; Hurricane Evacuation Study PR 
$49,491; Hurricane Evacuation Study VI $19,621; 
Quick Responses $6,840; and Hydrologic studies $- 
133; HES Palm Beach $42,677; for a total cost of 
$273,415. 
60. CONTINUATION OF PLANNING AND 
ENGINEERING 
Navigation costs were Canaveral Harbor, FL $548,343; 
Miami Harbor Channel, FL $152,020; and Tampa Bay, 
Port Sutton, FL $1,901. Beach erosion cost was 
Monroe County, FL $110,753. Local protection cost 
was Rio De La Plata, PR $933,968 and Rio Grande De 
Loiza, PR $358,658. 
61. ADVANCE ENGINEERING AND DESIGN 
Navigation cost was Canaveral Harbor Sand Bypass, FL 
$196,188; Miami River Sediments, FL $250,537; and 
San Juan Harbor, PR $466,558. Beach erosion control 
cost was Martin County, FL $167,958; Nassau County, 
FL $217,713; and St. Johns County, FL -$203. Local 
protection cost for Puerto Nuevo River, PR was 
$1,033,419. 
General Regulatory 
62. PERMIT EVALUATION 
(R&H ACT of 1899; CWA of 1977; 
MPRSA of 1972) 
Location. Navigable waters of the United States, 
including tributary systems, headwaters and isolated 
waters, and ocean waters to the limits of the territorial 
seas. 
Existing Program. The program evaluates permit 
applications for work in navigable waters (dredging, 
filling, and other structures) of the United States, and 
the transportation of dredged material to the oceans for 
ocean disposal. Geographic coverage includes Florida, 
Puerto Rico, and the U.S. Virgin Islands. Decision 
making criteria consist of the public interest review, 
Section 404(b)(1) Guidelines, and ocean dumping 
criteria. 
Local Cooperation. Joint application agreement with the 
Florida Department of Environmental Regulation (FDER) 
continues to work smoothly. Future FDER delegation to 
South and Southwest Florida Water Management 
Districts anticipated to work smoothly, with possible 
increased sharing of project review information in the 
future. Started discussions with FDER on developing a 
comprehensive programmatic general permit which 
could move both agencies into joint application review. 
Discussions continue with the USVI Department of 
Planning and Natural Resources to improve the existing 
joint application process. Booklets describing both joint 
application processes have been reviewed and 
extensively revised. The updated Corps/FDER booklet 
has been published. 
Operations and results during fiscal year. A total of 
7339 applications were received during the fiscal year, 
up slightly from 7313 received in FY 1991. Of these, 
1441 were individual or letters of permission (compared 
to 1592 in FY 1991), 1987 were requests for 
nationwide permit verification (versus 1910 in FY 
1991), and 3911 were for regional general permits 
(versus 3811 in FY 1991). FY 1992 cost for permit 
evaluation was $4,019,578. 
Condition at end of fiscal year. A total of 445 
individual or letters of permission permit applications 
were carried forward into FY 1993. 
63. ENFORCEMENT 
(R&H ACT of 1899; CWA of 1977; 
MPRSA of 1972) 
Existing program. The program takes appropriate 
enforcement action against both unauthorized work 
requiring a permit and noncompliance findings on 
issued permits. Operation of the program is making 
increased use of alternative dispute resolution 
processes to remediate violations. Close coordination 
with and cooperation of Department of Justice 
continues, with development of consent orders and 
fines as appropriate. 
Local cooperation. Local memoranda of agreement on 
enforcement have been developed with the 
Environmental Protection Agency (EPA) and FDER. The 
agreement with EPA has allowed considerable 
workload sharing and closer working relations. The 
agreement with FDER is being reviewed for possible 
revision. Negotiations are ongoing for a separate 
agreement with EPA to cover Puerto Rico and U.S. 
Virgin Islands. In addition a Local Cooperative 
Agreement (LCA) has been finalized with Dade County 
to realize permit compliance inspections of rock mining 
activities in Dade County. This agreement will result in 
these site inspections being conducted in FY 1993. 
Operations and results during fiscal year. A total of 
167 unauthorized activities were reported during the 
fiscal year. 225 unauthorized activities were resolved. 
Compliance inspections were performed on 315 
permits. Overall 85 percent were found in compliance. 
9-24

JACKSONVILLE, FL DISTRICT 
Cost incurred this fiscal year for enforcement was 
$974,520. 
Condition at end of fiscal year. 190 enforcement files 
on unauthorized activities are carried into FY 1993. 9 
cases were transferred to the EPA under the 
enforcement MOAs. Approximate settlement terms for 
15 consent orders have been finalized, with total fines 
of $1.7 million, restoration of 32 acres of wetlands 
required; and after-the-fact permitting of 31 acres of 
wetlands authorized. The ATF permits all required 
compensatory mitigation. Cost for enforcement was 
$974,520 for FY 1992. 
64. OTHER NAVIGATION REGS 
(R&H Act of 1899) 
Location. Navigable waters of the United States in 
Florida, Puerto Rico, and the U.S. Virgin Islands. 
Existing program.. This program conducts studies to 
determine geographic extent of navigable waters of 
the United States, and establishment of danger or 
restricted zones in these waters. 
Local cooperation. This program is carried out with 
informal cooperation with the State of Florida and 
cooperation of other Department of Defense agencies 
needing restricted zones in which to conduct their 
defense related missions. 
Operations and results during fiscal year. No tributary 
system navigability studies were conducted during the 
fiscal year, although navigability determinations were 
conducted on the Short Canal. Litigation continues on 
a navigability determination on Fisheating Creek. Cost 
incurred for FY 1992 was $15,868. 
Condition at end of fiscal year. The district has 
conducted 14 navigability studies of State tributary 
systems. State assumption of the Section 404 
program may occur in the next three years. Additional 
navigability studies will be programmed to help 
delineate nonassumable waters as funds permit. 
Project Modification 
65. KISSIMMEE RIVER, FLORIDA 
Location. The Kissimmee River Basin comprises 
3,013 square miles, and extends from Orlando 
southward to Lake Okeechobee, the second largest 
freshwater lake in the United States. The area is 
bounded on the north by the lakes of the Orlando 
area, on the west by the Peace River Basin, on the 
south by Lake Okeechobee, and in the east by the 
Upper St. John's and the Taylor Creek-Nuddin Slough 
Basins. The watershed is about 105 miles long and 
has a maximum width of 35 miles. 
Existing Project. The purpose of this study is to 
determine the extent of Federal participation in the 
Level II Backfilling Plan, as developed by the South 
Florida Water Management District, for restoration of 
the Kissimmee River and flood plain ecosystem. It is 
expected that restoration will restore the ecological 
integrity of the river system. Environmental 
improvements through modification of operations for 
Lake Kissimmee, Cypress, and Hatchineha. The project 
will include canal and/or structure improvements and 
real estate acquisition. The recommended plan consists 
of backfilling approximately 29 miles of C-38. This will 
result in the restoration of almost 29,000 acres in the 
floodplain. Three structures will be removed and two 
bridges and associated utilities will be relocated. Real 
estate interests will be acquired for effected portions 
of the floodplain. 
Estimated cost of the project (October 1992 price 
levels) for Kissimmee Headwaters Revitalization is 
$46,105,000 Federal and $46,105,000 non-Federal. 
Project cost for Kissimmee River Restoration is 
$132,218,000 Federal and $314,988,000 non-Federal 
($183,200,000 contributed funds, $123,088,000 
lands and damages and $8,700,000 relocations). 
Local Cooperation. The South Florida Water 
Management District, an agency of the State of 
Florida, is the feasibility study cost sharing partner, 
and has expressed its intent to be the project sponsor. 
Local cost for the Headwater Revitalization is to be 
credited towards the total project cost. The 
sahuathreodr ization calls for the restoration to be cost- 50%-50% and that the lands be credited 
toward the total cost of the Kissimmee River 
Restoration. A draft Local Cooperation Agreement 
(LCA) has been reviewed by the sponsor and a letter 
of intent has been provided for the Headwaters 
Revitalization. LCA for the River Restoration project is 
scheduled for execution in May 1994. 
Operations and results during fiscal year. New work: 
Lands and damages cost was $36,026, study cost 
was -$213,726 and Engineering and Design cost was 
$768,201. 
Condition at the end of the fiscal year. Section 1135 
report is 27% complete and scheduled for submission 
in July 1994. Initiation of construction is scheduled for 
October 1995. PED is underway and the first 
construction contract for the test fill is scheduled for 
June 1996. 
9-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-A COST AND FINANCIAL STATEMENT 
See Total Cost To 
Sect. PROJECT FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
1. Aquatic Plant 
Control (R&H 
Act of 1965) 
(Federal Funds) 
2. Arecibo Harbor, 
PR 
(Federal Funds) 
3. Atlantic 
Intlracoastal 
Waterway 
between 
orfolk, VA and 
St.Johns River, 
FL 
(Federal Funds) 
4. Bakers Haulover 
Inlet, FL 
(Federal Funds) 
5. Canaveral 
Harbor, FL 
(Federal Funds) 
(Contrib. Funds) 
6. Channel from 
Naples to Big 
Marco Pass, FL 
(Federal Funds) 
(Contrib. Funds) 
7. Charlotte 
Harbor, FL 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
2,450,000 2,125,000 2,048,000 2,180,000 30,964,500 
2,510,571 2,007,829 2,064,140 2,166,960 30,809,757 
- - 1,128,075 1 
- - 1,128,075 1 
- 9,700 4,301,431 
- 9,700 4,301,431 
5,032 
5,032 
195,000 
193,967 
11,902 
4,966,850 
4,945,994 
171 
987 
3,464,569 
3,229,000 
16 
- 42,350 
- 35,281 
183,290 
183,595 
269,118 
261,369 
826,300 
826,123 
1,035,000 25,000 
52,273 973,477 
1,925,000 3,887,000 
2,197,275 3,878,661 
- 4,500 
- 14,530 
15,655 
22,713 
255,000 
261,142 
361,225 2 
361,225 2 
6,322,042 
6,320,832 
243,235 3 
243,235 3 
185,688 
185,688 
15,198,910 * 
15,164,598 ' 
55,456,240 
55,442,351 
1,110,500 
1,106,782 
- 305,290 
- 305,290 
69,000 1,733,535 
60,472 1,724,996 
- 159,975 
- 159,975 
- 533,169 s 
- 533,169 
271,000 12,517,644 
272,654 12,517,606 
9-26

JACKSONVILLE, FL DISTRICT 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost To 
Sect. PROJECT FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
8. Cross-Florida 
Barge Canal 
(Federal Funds) 
9. Eau Gallie 
Harbor, FL 
(Federal Funds) 
10. Fernandina 
Harbor, FL 
(Federal Funds) 
(Contrib. Funds) 
11. Fort Myers Beach 
Channel, FL 
(Federal Funds) 
12. Fort Pierce 
Harbor, FL 
(Federal Funds) 
(Contrib. Funds) 
13. Gulf Intracoastal 
Waterway 
Caloosahatchee 
River to Anclote 
River, FL 
(Federal Funds) 
14. Intracoastal 
Waterway 
Jacksonville to 
Miami, FL 
(Federal Funds) 
(Contrib. Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Aprop. 
Cst 
Maint: 
Approp. 
ost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
A&prop. 
Cst 
Maint: 
Approp. 
Cost 
450,000 
159,241 
3,107,979 
3,096,182 
(5,000,000) 
76,415 
1,774,234 
1,720,057 
28,098 
1,689,000 
1,701,964 
73,036 
1,841,000 
1,892,291 
63,647,473 
63,643,469 
31,984,176 ' 
31,964,068 ' 
9,627 
9,627 
710,900 
710,900 
134,000 
56,997 
766,950 
766,931 
59,000 
17,858 
10,145 
11,488 
506,326 
506,288 
61,209 
63,268 
904,692 
983,309 
148,097 
757,619 
548,015 
17,000 
31,169 
5,000 
10,833 
769,000 
978,529 
4,700 
25,324 
235,000 
119,754 
1,234,700 
1,228,341 
10,345 
4,639,816 ' 
4,523,428 
27,777,288 
27,770,653 
935,000 
934,050 
- 158,140 ' 
- 158,140 ' 
- 1,184,091 
- 1,184,090 
662,555 
651,867 
36,262 
36,262 
734,369 
583,133 
287,500 
48,934, 
93,770 
98,458 
66,750 
63,763 
3,110,500 
3,256,940 
468,000 
644,648 
163,000 
159,143 
45,000 
47,568 
2,788,500 
2,738,650 
718,000 
5,938,686 
5,928,772 
18,574 
18,574 
8,112,557'9 
8,112,557' 
8,123,959 10 
8,123,508 10 
19,251,598 
" 
19,251,598 
38,705,028 1 
38,646,884 n 
61,000 
61,000 
9-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost To 
Sect. PROJECT FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
15. Jacksonville 
Harbor, FL 
(Federal Funds) 
(Contrib. Funds) 
16. Jacksonville Hbr. 
(Mill Cove), FL 
(Federal Funds) 
17. Johns Pass, FL 
(Federal Funds) 
18. Long Boat 
Pass, FL 
(Federal Funds) 
(Contrib. Funds) 
19. Manatee 
Harbor, FL 
(Federal Funds) 
20. Mayaguez 
Harbor, PR 
(Federal Funds) 
21. Melbourne 
Harbor, FL 
(Federal Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
399,700 
415,056 
4,408,579 
4,173,562 
1,169,000 
1,453,730 
293,200 
290,775 
47,596,278 1 
47,596,278 1 
69,468,068 "
14 
69,464,868 14 
- 102,813 
- 102,813 
- 927,654 
- 927,654 
- 25,000 
- 25,000 
450,000 
78,053 
- 112,000 
374,964 46,859 
32,425 63,350 264,000 
32,425 62,319 265,030 
- 49,954 
49,954 
377,350 609,000 
162,033 824,142 
200,000 500,000 
218,089 396,275 
716 
716 
53,045 
4,104,000 
4,091,775 
- 82,098 16 
- 82,098 16 
- 359,775 
- 359,775 
(600) 
(426) 
- (137,000) 
163,325 33,037 
- 8,700 
- 8,700 
1,020,233 
1,020,233 
2,436,191 
2,436,190 
172,324 
172,324 
1,040,500 
1,035,013 
168,187 
168,187 
1,061,561 
1,061,561 
- 17,696 
- 17,696 
- 634,864 
- 634,863 
9-28

JACKSONVILLE, FL DISTRICT 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost To 
Sect. PROJECT FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
22. Miami 
Harbor, FL 
(Federal Funds) 
(Contrib. Funds) 
23. New Pass 
Sarasota, FL 
(Federal Funds) 
24. Okeechobee 
Waterway, FL 
(Federal Funds) 
25. Oklawaha 
River, FL 
(Federal Funds) 
26. Palm Beach 
Harbor, FL 
(Federal Funds) 
27. Ponce de Leon 
Inlet, FL 
(Federal Funds) 
(Contrib. Funds) 
28. Ponce Harbor, 
PR 
(Federal Funds) 
(Contrib. Funds) 
New Work: 
Approp 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
307,194 
203,755 
203,754 
1,562 
1,249,937 
1,233,456 
65,422 1,147,600 
65,414 1,062,377 
2,391,330 
2,952,854 
1,859,725 
1,750,197 
72,595 39,661 
72,535 28,205 
235,644 
435,155 
448,738
- 
100,000 
182,812 
2,062,500 
2,174,033 
341,00 
211,01 
690,00 
683,85 
(2,40(
2 
4,544,25 
4,537,69 
28,000 40,00 
39,140 36,43 
934,651 996,177 180,845 
930,993 976,085 204,172 
2,802,500 817,752 
2,801,297 818,954 
500,000 
1,325,000 
1,954,609 
199,739 
679,406 
1,017,00 
1,016,97 
68,189 37,60 
65,656 40,13 
- (320,000) 
(72,549) 4,741 
(56,764) 
(14,811) 
1,40 
1,40
)0 32,977,066 ' 
5 31,495,082 17 
)0 5,039,517 
0 5,155,522 
- 2,300,710" 
- 2,274,595 " 
- 45,811 " 
- 45,811 19 
0) 4,418,926 
1 4,418,926 
- 21,756,418 w 
- 21,756,418 w 
0 47,264,971 21 
)8 47,262,141 21 
- 315,264 2 
- 315,264 
10 2,341,576 
1 2,337,630 23 
- 6,924,021 
- 6,911,204 2 
)0 14,109,756 
8 14,109,721 
- 1,953,276 
- 1,953,276 
)0 19,229,127 
4 19,208,582 
- 2,415,600 
- 2,415,600 
- 1,379,000 
- 1,379,000 
- 2,462,907 2 
- 2,462,438 2 
)0 1,614,270 
0 1,614,270 
- 717,304 
- 706,607 
9-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See Total CostTo 
Sect. PROJECT FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
29. Port Everglades 
Harbor, FIl 
(Federal Funds) 
30. Removal of 
Aquatic Growth 
(Federal Funds) 
31. St. Augustine 
Harbor, FL 
(Federal Funds) 
32. St. Johns 
River, FL 
Jacksonville to 
Lake Harney 
(Federal Funds) 
33. St. Lucie 
Inlet, FL 
(Federal Funds) 
(Contrib. Funds) 
34. San Juan 
Harbor, PR 
(Federal Funds) 
35. Tampa Harbor, FL 
(Main Channel) 
(Federal Funds) 
(Contrib. Funds) 
35. Tampa Harbor, FL 
(Cont) (East Bay - 
Branch Channels) 
(Federal Funds) 
(Contrib. Funds) 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
(45,000) 
7,266 
20,698 
20,668 
- (37,000) 
- 1,265 
19,700 19,864 
(134)- 
- 54,426,773 
- 54,416,635 27 
- 1,757,742 
- 1,757,742 
2,815,387 2,781,380 2,946,000 2,692,000 44,720,137 
2,820,856 2,617,006 3,082,770 2,721,820 44,719,702 
- 54,000 
- 52,563 
364,279 
363,799 
917 
269,700 
263,126 
342,736 51,553 
2,260,504- 
2,263,294 1 
17,967 
884,410 
857,218 
155,885 
10,000 
37,431 
6,699 
3,688,163 
3,216,680 
335,000 
196,186 
100,000 
35,695 
700,500 
702,981 
110,750 
99,767 
- 1,476,434 ' 
- 1,476,434 
- 4,768,107 
1,393 4,768,063 
- 1,171,243 2 
- 1,171,243 2 
- 1,300,299 
- 1,300,299 0 
102,000 
102,746 
430,000 
43,241 
231,500 1,862,00 
218,514 1,874,84 
2,426,000 
2,898,514 
700,000 
946,332 
330,000 
292,769 
4,656,0 
4,598,06 
(100,000) 
60,804 
16,855 
7,766,689 31 
7,766,489 31 
6,244,485 
6,240,757 
3,516,026 
3,265,643 
- 13,744,968 n 
- 13,744,968 n 
D0 18,790,135 " 
18 18,790,134 n 
- 173,767,490M 
- 173,766,190 
30 33,743.095 
54 35,161,772 U 
- 1,083,162 
- 1,038,711 
1,700,000 
1,689,301 
814,450 
718,406 
9-30

JACKSONVILLE, FL DISTRICT 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Sect. PROJECT 
35. Tampa Harbor, FL 
(Port Sutton) 
(Federal Funds) 
37. Brevard County, 
FL 
(Federal Funds) 
(Contrib. Funds) 
40. Broward County, 
FL Beach Erosion 
Control & Hillsboro 
Inlet, FL 
Navigation Proj. 
(Federal Funds) 
(Contrib. Funds) 
41. Duval County, 
FL 
(Federal Funds) 
(Contrib. Funds) 
42. Indian River 
County, FL 
(Federal Funds) 
43. Manatee County, 
FL 
(Federal Funds) 
44. Nassau County, 
FL 
(Federal Funds) 
45. Palm Beach 
County, FL 
(Federal Funds) 
46. Pinellas County, 
FL 
(Federal Funds) 
(Contrib. Funds) 
Total Cost To 
FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
New Work 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cos 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
16,410 
12,777 
2,511,000 
380,337 
174,579 
100,000 
207,547 
64,028 
2,992,000 
674,349 
135,542 
241,027 
- 
3,750,000 
109,616 
369,577 
1,421,917 
1,699,856 
432,000 
119,360 
400,000 
241,677 
2,005,000 
1,813,682 
3,199,000 
3,168,144 
4,756,700 
2,458,842 
150,000 
139,696 
4,493 
(82,000) 
4,040,811 
1,702,149 
1,702,149 
(1,254,000) 
1,403,906 
512,237 
(331,000) 
11,762 
525,000 
645,686 
125,641 
994,000 
3,999,143 
8,361,000 
5,629,609 
45,000 
33,849 
10,574 
3,916,000 
4,048,845 
250,000 
219,827 
(490,000) 
652,615 
2,100,000 
186,661 
1,800,000 
141,766 
93,000 
113,780 
4,098,000 
3,265,479 
1,501,462 
3,623,575 
9-31 
195,000 
173,545 
2,346,492 
2,324,168 
29,001 
29,001 
2,262,000 
2,257,081 
19,345,100 
19,251,323 
26,884 
26,884 
3,460,990 ' 
3,460,990 ' 
14,463,900 
14,201,776 
11,609,567 
11,414,073 
401,000 
385,208 
3,025,000 
1,074,024 
1,800,000 
141,766 
7,877,834 
7,752,653 
13,621 
13,621 
18,280,693 
16,971,222 
5,625 
5,625 
20,160,345 
17,121,627

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost To 
Sect. PROJECT FUNDING FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
47. Sarasota County, 
FL 
(Federal Funds) 
50. Central and 
Southern Florida 
(Federal Funds) 
(Contrib. Funds) 
51. Dade County, 
FL 
(Federal Funds) 
(Contrib. Funds) 
52. Dade County, 
N. of Haulover 
Beach, FL 
(Federal Funds) 
(Contrib. Funds) 
53. Four River 
Basins, FL 
(Federal Funds) 
(Contrib. Funds) 
54. Portugues and 
Bucana Rivers, 
PR 
(Federal Funds) 
(Contrib. Funds) 
62. General Regulatory 
(Federal Funds) 
65. Kissimmee River, FL 
(Federal Funds) 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
- 400,000 200,000 269,000 
- 238,048 268,548 262,057 
16,100,000 
17,603,265 
4,807,619 
4,685,876 
971,000 
1,407,080 
1,711,000 
149,102 
576,000 
10,408 
351,400 
(576,000) 
2,182,572 
400,000 
342,380 
425,941 
856,061 
29,203,000 
26,063,497 
5,428,010 
5,489,488 
1,066,000 
1,082,021 
1,518,105 
1,721,250 
1,879,876 
18,800,000 
12,324,984 
6,419,000 
6,499,045 
26,000 
115,824 
869,000 
768,653 
7,187,000 377,500,398 n 
7,942,357 376,164,664 " 
6,049,750 83,657,040 
6,035,778 83,588,082 
- 57,624,049 
83,983 57,500,926 
(241,000) 489,000 36,502,430" 
48,291 661,611 36,349,874 " 
- - 27,857,335 " 
- 492,252 27,494,564 " 
- (129,000) 
400,403 189,431 
306,880 103,471 
369,000 171,000 
357,584 (9,568) 
146,046 18,321 
- 6,941,000 
523 6,928,345 
- 7,499,000 
- 7,018,544 
(59,000) 
38,536 
202,145 
74,333,095 
74,145,329 ' 
14,109,946 
13,903,316 
8,500,000 41,254,000 25,336,000 19,380,000 304,621,569 
30,861,960 35,971,382 31,529,182 19,558,294 301,455,847 
50,000 90,000 
22,901 111,366 
3,500 900,000 
56,847 (11,738) 
1,263,500 
351.074 
4,236,100 4,124,000 4,863,500 5,240,000 22,191,200 * 
4,158,774 4,071,922 4,933,661 5,010,334 21,850,787,1 
2,300,000 
656 
-- 600,000 
134,267 1,912,699 590,501 
2,900,000 
2,638,123 
' Excludes $288,000 for contributed funds for new work. 
2 Includes $97,566 for previous project. 
SExcludes $243,235 contributed funds for new work. 
SExcludes $700,000 contributed by NASA in connection with 
construction of lock. 
s Includes $113,000 for new work on previous project; excludes 
$15,563 expended for new work on existing project in Boca Grande 
entrance channel from contributed funds. 
' Excludes $113,744 for maintenance and operations of dams. 
' Includes $905,221 expended for recreation facilities. 
$ Includes $10,128 cost for reconnaissance and detailed project report 
prepared under Section 107 modification to the project. Excludes 
$1,095 contributed funds for new work. 
9 Includes $515,479 for new work for previous projects: $8,472 for 
new work on Sunshine Skyway Channel; and $9,707 for new work 
for Cats Point Channel. Excludes $14,473 contributed funds for new 
work for Sunshine Skyway and Boca Ciega Bay channels. 
10 Includes $450,749 for maintenance for previous project. 
9-32

JACKSONVILLE, FL DISTRICT 
" Includes $94,776 for work for previous projects. 
Excludes $2,199,842 expended from public works funds for new 
work. 
u Includes $213,222 for maintenance on previous projects and $3,179 
operating and care under provisions of permanent indefinite 
appropriation. 
u Includes $3,520,137 new work on previous project and $290,013 
for new work expended from public works funds. 
" Includes $543,399 maintenance on previous projects. 
n Includes unused contributed funds of $64,136 returned to local 
interests. 
" Project authorized December 2, 1964, by Chief of Engineers under 
Section 107 of 1960 R&H Act and by Section 110 of the 1966 R&H 
Act. Cost of new work excludes $53,732 contributed funds. 
" Includes $5,502,126 expended from public work funds for new 
work. Includes costs of $6,777,906 for recreation facilities. 
" Includes $381,479 work-in-kind and $172,314 in costs for north 
jetty recreation facility. 
" Excludes $45,811 contributed funds for new work. 
m Includes $21,101,919 for new work under previous project, 
$626,925 for recreational facilities (Code 710), and $27,574 for 
reconnaissance and detailed project report prepared under Section 
107 modification to the project. 
2' Includes $7,581,150 for maintenance for previous projects. Excludes 
$1,000 for maintenance from contributed funds on previous projects, 
$67,558 which represents services rendered without reimbursement, 
and $113,744 for maintenance and operations of dams. 
SIncludes $3,912 for new work for previous projects. 
a Includes $11,414 for operating and care under provisions for 
permanent indefinite appropriation. 
" Includes $80,000 new work from public works funds. Excludes 
$509,506 contributed funds. 
SIncludes $30,000 for maintenance from public works funds. 
, Includes $11,588 expended for restudy, but excludes $21,960 
expended for new work from contributed funds. 
, Excludes $1,033,069 contributed funds. 
" Includes $71,303 for new work on previous project. Excludes 
$137,500 contributed funds. 
" Baresford cutoff and completion of cutoffs and easing of bends in 
Putnam Lake and Volusia Counties in inactive status were 
deauthorized by Public Law 93-251 section 12. Includes $29,566 
for new work under previous project. 
3 Includes $25,838 under previous project. 
" Includes $26,689 for new work under previous project. 
� Includes $747,684 for new work under previous project. Excludes 
$100,000 expended for new work from contributed funds. 
3 Includes $44,730 for maintenance from public works funds under 
previous project. 
" Includes $853,050 for new work from public works funds under 
previous project & $1,463,000 from emergency relief funds. Excludes 
$270,466 for new work for Hillsborough River and $13,939 for new 
work from contributed funds. 
" Includes $17,107 for maintenance under previous project. 
" Excludes work-in-kind. 
" Excludes $15,543 for property received without reimbursement and 
R&H Funds, expended on previous projects (see cost and financial 
statement for Okeechobee Waterway, FL, project for these costs). 
Excludes $100,000 advanced by local interests toward federal costs. 
Includes. $175,000 appropriation and $175,000 cost for new work at 
C&SP St. Johns Water Management District. 
" Includes $2,294,134 for reimbursement costs to Bal Harbor. 
" Excludes unused contributed funds of $17,969 returned to local 
interests. 
o Includes costs of $89,691 for recreation facilities at Moss Bluff and 
$2,638,272 at Lake Tarpon. 
" Funds appropriated under General Regulatory Functions 96X3126 
only. 
9-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
October 27, 1965 
August 26, 1937 
March 4, 1913 
June 20, 1939 
July 14, 1960 
March 2, 1945 
October 23, 1962 
Report of the 
Chief of Engineers 
October 1985 
June 20, 1938 
July 14, 1960 
July 25, 1912 
March 3, 1925 
July 3, 1930 
August 26, 1937 
AQUATIC PLANT CONTROL (See Section 1 of Text) 
Control and progressive eradication of obnoxious aquatic plants, 
and continued research to develop best method of control. 
ARECIBO HARBOR, PR (See Section 2 of Text) 
Construction of breakwater 1,200 feet long and dredging channel 
25 feet deep and 400 feet wide with flare at entrance and 
widening at inner end to form a maneuvering area. 
ATLANTIC INTRACOASTAL WATERWAY BETWEEN 
NORFOLK, VA AND THE ST. JOHNS RIVER, FL 
(See Section 3 of Text) 
Channel 7 x 100 feet. 
Channel 12 feet deep and 90-150 feet wide with cutoffs. 
BAKERS HAULOVER (See Section 4 of Text) 
Channel 11 x 200 feet in ocean entrance, thence 8 x 100 feet to 
Intracoastal Waterway; Marina basin 8 x 200 feet; reconstruction 
of jetties and protection of inlet shores. 
CANAVERAL HARBOR, FL (See Section 5 of Text) 
Entrance channel jetties, a turning basin enclosed by a dike, 
and a barge canal with a lock. 
Maintain improved channel, turning basin, enlarge barge channel 
and lock, relocate dike, provide channel and turning basin west 
of 35-foot turning basin, construct and operate sand-transfer plant. 
Mitigation of fish and wildlife losses at Port Canaveral West 
Turning Basin Project. 
CHANNEL FROM NAPLES TO BIG MARCO PASS, FL 
(See Section 6 of Text) 
Interior channel 6 x 70 feet. 
Channel 12 x 150 feet from the Gulf to Gordon Pass, thence 10 x 100 
feet to a point 400 feet south of U.S. Highway 41 Bridge, thence 
10 x 70 feet to bridge and two turning basins. 
CHARLOTTE HARBOR, FL (See Section 7 of Text) 
Channel 24 x 300 feet through Gulf through Boca Grande entrance. 
Depth of 27 feet at entrance and width of 500 feet at bend. 
Channel 10 x 100 feet to Punta Gorda and a turning basin. 
Depth of 30 feet at entrance and width of 700 feet at bend. 
H.Doc. 251, 89th Cong., 
1st sess. 
Rivers and Harbors Committee 
Doc. 43, 75th Cong., 
1st sess. 
H.Doc. 898, 62nd Cong., 
2d sess. 
H.Doc. 618, 75th Cong., 
3d sess. 
H.Doc. 189, 86th Cong., 
1st sess. 
H.Doc. 367, 77th Cong., 
1st sess. 
S.Doc. 140, 87th Cong., 
2d sess. 
P.L. 99-662, 17 Nov. 1986 
99th Cong., 2d sess. 
H.Doc. 596, 75th Cong., 
3d sess. 
H.Doc. 183, 86th Cong., 
1st sess. 
H.Doc. 699, 62nd Cong., 
2d sess. 
H.Doc. 113, 66th Cong., 
1st sess. 
Rivers and Harbors 
Committee, Doc. 1, 
70th Cong., 1st sess. 
Rivers and Harbors 
Committee, Doc. 95, 
74th Cong., 2d sess. 
9-34

JACKSOVIILjE, FL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
P.O. 675/77 
July 23, 1942 
W.R.D.A. 
November 17, 
W.R.D.A. 
November 28, 
June 20, 1938 
June 14, 1880 
July 13, 1892 
March 2, 1907 
June 25, 1910 
March 3, 1925 
June 20, 1938 
March 2, 1945 
May 17, 1950 
W.R.D.A. 
November 28, 
July 14, 1960 
Auth. by Chief 
Engineers 
December 6, 1 
under Sec. 107 
1960 R&H Act 
Depth of 32 feet in entrance channel. H 
CROSS-FLORIDA BARGE CANAL (See Section 8 of Text) 
Barge Canal 12 x 150 feet. H 
Establishment of the Cross Florida National Conservation Area. P. 
1986 
Deauthorized project purposes in the Act of July 23, 1942, transferred P. 
1990 lands and completed facilities to the state, and required state payments to 
Citrus, Clay, Duval, Levy, Marion and Putnam counties. 
EAU GALLIE HARBOR, FL (See Section 9 of Text) 
Channel 8 x 100 feet and a turning basin. H. 
FERNANDINA HARBOR, FL (See Section 10 of Text) 
Entrance jetties. A 
Raising and extending jetties to provide a 19-foot depth. An 
Improvement of inner harbor to obtain 20 to 24-foot depth and 400 to H. 
600-foot channel width. 
Combining improvement of Fernandina Harbor and Cumberland 
Sound under the general heading of Fernandina Harbor. 
Provided for a 26-foot channel. H. 
1st sess. 
Provided for the 28-foot channel and turning basin. H.
3 
Provided for reducing the maximum width of turning basin from H. 
1,000 to 800 feet, for shifting channel line in this vicinity 1 
vicinity 50 feet northwesterly and for including in authorized 
project small area dredged by Rayonier, Inc. 
Provided for 32-foot channel and turning basin. H.
2 
Redesignated location of turning basin until Section 107 (R&H Act of P.I 
1990 1960) study is completed and the resulting project constructed. 1 
FORT MYERS BEACH, FL (See Section 11 of Text) 
12 x 150 foot channel in San Carlos Bay, thence 11 x 125 feet in H. 
Matanzas Pass to upper shrimp terminals. 1 
of Extension of 11 x 125 foot channel easterly about 2,000 feet to and 
including a turning basin adjacent to natural deep water in 
968 Matanzas Pass. 
of 
t 
.Doc. 186, 81st Cong., 
1st sess. 
.Doc. 109, 79th Cong., 
1st sess. 
L. 99-662, 17 Nov 1986, 
99th Cong., 2d sess. 
L. 101-640,28Nov. 1990, 
101st Cong., 2d sess. 
.Doc. 497, 75th Cong., 
3d sess. 
nnual Report 1879 
nnual Report 1891 & 1896 
Doc. 388, 59th Cong., 
1st sess. 
Doc. 227, 68th Cong., 
Doc. 548, 75th Cong., 
3d sess. 
Doc. 284, 87th Cong., 
st sess. 
Doc. 662, 80th Cong., 
Zd sess. 
L. 101-640,28 Nov. 1990 
01st Cong., 77?s?e ss. 
Doc. 183, 86th Cong. 
st sess. 
9-35

REPORT OF TEE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Def. Act of 
March 4, 1931 
War Dept. Approp. 
Act, March 4, 1933 
August 30, 1935 
Report of the 
Chief of Engineers 
December 14, 1987 
March 2, 1945 
June 30, 1948 
May 17, 1950 
September 3, 1954 
May 10-16, 1957 
Auth. March 1, 1962 
FORT PIERCE HARBOR, FL (See Section 12 of Text) 
Expenditure of $20,000 for dredging channel, maintenance by local 
interests. 
Expenditure of up to $30,000 for dredging channel. 
Maintaining channels, jetties, and revetments, and enlarging 
channels and turning basin to existing project dimensions. 
Deepening and enlarging channels and turning basin. 
Total cost of $6,742,000. 
INTRACOASTAL WATERWAY, CALOOSAHATCHEE RIVER 
TO ANCLOTE RIVER, FL (See Section 13 of Text) 
9 x 100 foot channel; deepening channel at Caseys Pass to 9 feet 
and construction of highway bridge at Venice. 
Original route may be modified at no excess cost to U.S. 
Any route in Venice-Lemon Bay area may be used. 
Use of alternate Route C-1 in Venice-Lemon Bay area. 
Local interests to bear costs of Venice Avenue highway bridge and 
any other necessary crossing over Route C-1. 
Sunshine Skyway Channel to be improved and maintained to 9 x 100 feet. 
by Senate and House 
Public Works Comm. 
Auth. by Chief of 6 x 80 foot channel in Boca Ciega Bay. 
Engineers, March 
1, 1963, under Sec. 
107 of 1960 R&H Act 
INTRACOASTAL WATERWAY, JACKSONVILLE TO MIAMI, 
(See Section 14 of Text) 
January 21, 1927 Channel 8 x 75 feet from Jacksonville to Miami. 
July 3, 1930 Channel width of 100 feet. 
PARA June 26, 1934 Operation and care of Palm Valley Bridge. 
August 26, 1937 Turning basin at Jacksonville Beach. 
March 2, 1945 
March 2, 1945 
March 2, 1945 
Channel 12 x 125 feet. 
Side channel and turning basin at Sebastian (deauthorized). 
Turning basin at Vero Beach. 
Specified in Act 
Specified in Act 
H.Doc. 252, 72nd Cong., 
1st sess. and Rivers 
and Harbors Committee 
Doc. 21, 74th Cong., 
1st sess. 
P.L. 100-676,17 Nov. 1988, 
100th Cong., 2d sess. 
H.Doc. 371, 76th Cong., 
1st sess. 
Specified in Act 
Specified in Act 
Specified in Act 
H.Doc. 109, 85th Cong., 
1st sess. 
FL
H.Doc. 586, 69th Cong., 
2d sess. 
S.Doc. 71, 71st Cong., 
2d sess. 
Specified in Act 
H.Doc. 180, 75th Cong., 
1st sess. 
H.Doc. 740, 79th Cong., 
2d sess. 
H.Doc. 336, 76th Cong., 
1st sess. 
H.Doc. 261, 76th Cong., 
1st sess. 
9-36

JACKSOWVILLB, FL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Maintenance of side channel at Daytona Beach. H.Doc. 222, 85th Cong., 
1st sess. 
Chief of Engineers Channel 10 x 125 feet from Ft. Pierce to Miami. 
Report of July 22, 1960, 
Mod. 12-foot channel 
March 2, 1907 
November 17, 1986 
JACKSONVILLE HARBOR, FL (See Section 15 of Text) 
ST. JOHNS RIVER, FL OPPOSITE THE CITY OF 
JACKSONVILLE 
The 24-foot area from Hogan Creek to Florida East Coast Railroad H.Doc 663, 59th Cong., 
bridge. 1st sess. 
Deauthorized the 24-foot area from Hogan Creek to Florida East Coast P.L. 99-662,28 Nov. 1986, 
Railroad bridge. 99th Cong., 2d sess. 
JACKSONVILLE HARBOR (MILL COVE), FL 
(See Section 16 of Text) 
Report of the 
Chief of Engineers 
12 Feb. 1982 
Enlarge weir structure and west opening controlling flow into Mill 
Cove, to reduce shoaling and improve navigation as well as 
circulation. 
P.L. 99-662, 17 Nov. 1986 
99th Cong., 2d sess. 
JOHN'S PASS, FL (See Section 17 of Text) 
Auth. by Chief of Channel 10 x 100 feet in gulf, 8 x 100 feet inside pass, 
Engineers Dec. 2, 6 x 100 feet to IWW, 2.6 miles long. 
1964 under Sec. 
107 of 1960 R&H 
Act and Sec. 110 
of 1966 R&H Act 
LONGBOAT PASS, FL (See Section 18 of Text) 
Auth. by Chief of 12 x 150 foot entrance channel from Gulf of Mexico to Longboat 
Engineers, April Bridge; 10 x 100 foot channel from Longboat Bridge northeasterly 
20, 1976 under to IWW; channel from north channel to Cortez Bridge. 
Sec. 107 of 1960 
R&H Act, as amended 
Report of the 
Chief of Engineers 
12 May 1980 
W.R.D.A. 
November 28, 1990 
August 30, 1935 
August 26, 1937 
MANATEE HARBOR, FL (See Section 19 of Text) 
Provide for maintenance of the existing 40-foot deep draft navigation 
channel and turning basin from Tampa Bay to Port Manatee. Initial 
construction of a widener at Manatee Harbor and deepen area adjacent 
to berthing area. 
Modified the project for navigation authorized by the W.R.D.A. of 1986 
to construct substantially in accordance with the post authorization 
change report dated April 1990. 
MAYAGUEZ HARBOR, PR (See Section 20 of Text) 
Approach channel 30 feet deep to and along deep water terminal. 
MELBOURNE HARBOR, FL (See Section 21 of Text) 
Channel 8 x 100 feet and a turning basin. 
P.L. 99-662, 17 Nov. 1986 
99th Cong., 2d sess. 
P.L. 101-640,28 Nov. 1990, 
101st Cong., ?? sess. 
H.Doc. 215, 72nd Cong., 
1st sess. & River and 
Harbor Committee Doc. 1, 
73rd Cong., 1st sess. 
H.Doc. 390, 74th Cong., 
2d sess. 
9-37 
July 3, 1958

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1930 
PWA Program 
Sept. 6, 1933 
June 13, 1902 
March 2, 1907 
March 4, 1913 
March 3, 1925 
July 3, 1930 
August 30, 1935 
August 26, 1937 
March 2, 1945 
March 2, 1945 
July 14, 1960 
August 13, 1968 
W.R.D.A. 
November 17, 1986 
Report of the 
Chief of Engineers 
25 September 1989 
MIAMI HARBOR, FL (See Section 22 of Text) 
MIAMI RIVER 
The 15-foot channel in Miami River, 150 feet wide at the mouth. 
The channel at Dinner Key Airport. 
An 18-foot channel in a land cut across the peninsula and 
construction of the north jetty. 
Construction of the south jetty and increase of channel width 
to 100 feet. 
Modification of local cooperation requirements imposed by the 
Act of July 25, 1912. 
A channel 25 feet deep with present widths from the ocean to Biscayne 
Bay, thence 200 feet wide across the bay to but not including the 
municipal turning basin, and extension of both jetties. 
A channel width of 300 feet across the bay and enlarging the municipal 
turning basin, with expenditures thereon limited to $200,000. 
A depth of 30 feet from the ocean to and in the turning basin, 
with the existing authorized project widths, including the 
300-foot width in the channel across the bay. 
Extending the turning basin 200 feet to the southward. 
Specified in Act 
S.Doc. 95, 72nd Cong., 
1st sess. and 
Specified in Act 
H.Doc. 622, 56th Cong., 
1st sess. (Annual 
Report 1900, p. 1987) 
Specified in Act 
Specified in Act 
H.Doc. 516, 67th Cong., 
4th sess. 
Rivers and Harbors 
Committee Doc. 15, 
71st Cong., 2d sess. 
Sen. Comm. Print. 
73rd Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 86, 
74th Cong., 2d sess. 
The Virginia Key improvement. S.Doc. 251, 79th Cong., 
2d sess. 
For incorporation of the project for Miami River in that for Miami H.Doc. 91, 79th Cong., 
Harbor, the widening at the mouth of Miami River to existing project 1st sess. 
widths; the channels from the mouth of Miami River to the turning basin 
and to Government Cut; and the channel from Miami River to the harbor of 
refuge, provided that local interests contribute one-third of the cost. 
Deletion of Virginia Key development and the Dinner Key approach channel, S.Doc. 71, 85th Cong., 
widening the existing ship channel by easing the ocean bend and 2d sess. 
increasing the width of the 300-foot wide section to 500 feet, 
enlarging the existing turning basin 300 feet along both the south and 
northeasterly sides, and dredging a turning basin along the north side 
of Fisher Island about 39 acres in extent and 30 feet in depth. 
Enlarging existing entrance channel to 38 x 500 feet, deepening existing S.Doc. 93, 90th Cong., 
400-foot wide channel across Biscayne Bay to 36 feet; deepening existing 2d sess. 
turning basins at Biscayne Boulevard terminal and Fisher Island to 36 feet. 
Deauthorized the widening at the mouth of Miami River to existing project P.L. 99-662, 17 Nov. 1986, 
widths; and the channels from the mouth of Miami River to the turning basin, 99th Cong., 2d sess. 
to Government Cut, and to a harbor of refuge in Palmer Lake. 
The project for navigation, Miami Harbor Channel. P.L. 101-640,28 Nov. 1990, 
101st Cong, ?? sess. 
9-38

JACKSOVII, FL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorised Documents 
Auth. by Chief 
of Engineers 
April 20, 1964 
under Sec. 107 
of 1960 R&H Act 
PARA June 26, 1934 
August 26, 1937 
March 2, 1945 
March 2, 1945 
W.R.D.A. 
November 17, 1986 
Auth. by Chief 
of Engineers 
Nov. 5, 1968, 
under Sec. 107 
of 1960 R&H Act 
September 19, 1890 
March 2, 1907 
June 25, 1910 
July 25, 1912 
July 27, 1916 
PARA June 26, 1934 
W.R.D.A. 
November 17, 1986 
March 13, 1934 
December 10, 1934 
August 30, 1935 
NEW PASS, SARASOTA, FL (See Section 23 of Text) 
10 x 150 foot entrance channel; 8 x 100 foot inner channels; and 
8-foot deep turning basins at Payne Terminal and City Pier. 
OKEECHOBEE WATERWAY, FL (See Section 24 of Text) 
Operation and care of locks and dams provided for with funds from 
R&H appropriations. 
New lock and weir structure in St. Lucie Canal. 
Deepening to 8 feet from Ft. Myers to Jacksonville-Miami waterway 
near Stuart via channel across lake from Clewiston. 
Channel to yacht basin at Ft. Myers and a basin at Stuart. 
Deauthorized basin at Stuart. 
Enlarge existing 8 x 90 foot section of Okeechobee Waterway for 
about 5 miles upstream from Ft. Myers to 10 x 100 feet. 
OKLAWAHA RIVER, FL (See Section 25 of Text) 
Clearing obstructions for channel 4 feet deep from mouth to Leesburg. 
Channel 6 feet deep from mouth to head of Silver Springs Run. 
Maintenance of levels in the lakes at head of river. 
Acceptance of certain artificial waterways in lieu of portions of 
natural river bed. 
Operation and care of lock and dam provided for with funds from 
appropriations for rivers and harbors. 
Deauthorized channel 6 feet deep from mouth to head of Silver Springs Run. 
PALM BEACH HARBOR, FL (See Section 26 of Text) 
Maintenance of improvement previously constructed by local 
interests. 
Deepening the channels and turning basin, as constructed by local 
interests, to 20 feet. 
Authorized the work previously approved by Public Works Administration, 
and widening the channels to existing project dimensions, enlarging the 
700-foot square turning basin eastward removing the obstructive point 
Specified in Act 
Rivers and Harbors 
Committee Doc. 28, 
75th Cong., 1st sess. 
H.Doc. 696, 76th Cong., 
3d sess. 
H.Doc. 736, 79th Cong., 
2d sess. 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
Annual Report 1889,p. 1360 
H.Doc. 782, 59th Cong., 
1st sess. 
Specified in Acts 
Specified in Act 
Specified in Act 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
I.Doc. 185, 73rd Cong., 
2d sess. 
Recommended by Chief of 
Engineers to Public 
Works Administration 
October 17, 1934 
I.Doc. 185, 73rd Cong., 
2d sess. and Rivers 
and Harbors Comm. 
9-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 2, 1945 
May 17, 1950 
July 14, 1960 
Report of the 
Chief of Engineers 
10 Dec. 1985 
October 27, 1965 
March 3, 1925 
August 30, 1935 
March 2, 1945 
H.R. September 23, 
1976, S.R. 
October 1, 1976 
July 3, 1930 
August 30, 1935 
June 20, 1938 
July 24, 1946 
July 3, 1958 
on south side of the inlet, reverting the banks of the inlet, and Doc. 42, 74th 
restoring existing jetties. Cong., 1st sess. 
Deepening the channels and turning basin to 25 feet. H.Doc. 530, 78th Cong., 
2d sess. 
Extending the turning basin 550 feet southward over a 900-foot width, with a H.Doc. 704, 80th Cong., 
flare to the east; provided that local interests may be reimbursed not to exceed 2d sess. 
$305,000 for work done by them on this modification subsequent to July 1, 1949. 
An entrance channel 35 feet deep, 400 feet wide, and 0.8 mile long H.Doc. 283, 86th Cong., 
merging with an inner channel 33 feet deep, 300 feet wide and 0.3 1st sess. (contains 
mile long, thence flaring into a turning basin, 1,400 feet latest published map) 
north-south by a minimum of 1,200 feet east-west. 
Assume maintenance of locally expanded turning basin to a depth of P.L. 99-662, 17 Nov. 1986, 
25 feet on north side of existing basin. 99th Cong., 2d sess. 
PONCE DE LEON INLET, FL (See Section 27 of Text) 
Widening and deepening channels; jetties on north and south sides of inlet; H.Doc. 74, 89th Cong., 
a weir in the north jetty and an impoundment basin inside the weir. 1st sess. 
PONCE HARBOR, PR (See Section 28 of Text) 
Dredging 3 continuous areas, aggregating 153 acres, to depths of 30, 18, and 9 H.Doc. 532, 67th Cong., 
feet, and construction of a seawall, costs to be shared by U.S. and local Cong., 4th sess. 
interests. 
Modified conditions of local cooperation to provide that U.S. Rivers and Harbors 
undertake all dredging at Federal expense and return local funds Committee Doc. 18, 
previously contributed for dredging, all other portions of the 72nd Cong., 1st sess. 
improvement hereafter to be at the expense of local interests. 
Eliminate previously authorized 9-foot dredging area, and provided H.Doc. 745, 79th Cong., 
for dredging 30-foot depth area and 18 acres off the municipal 2d sess. 
pier and for construction of the breakwater off Punta Carenero. 
Eliminate previously authorized 18-foot and a portion of the 30-foot H.Doc. 532, 94th Cong., 
project outside the proposed 36-foot and a portion adjacent to the 2d sess. 
municipal bulkhead. Channel 36 x 600 feet from Caribbean Sea to 
harbor; channel 36 x 400 feet into harbor; and a 36-foot turning basin. 
PORT EVERGLADES HARBOR, FL (See Section 29 of Text) 
Maintenance of harbor constructed by local interests. H.Doc. 357, 71st Cong., 
2d sess. 
Enlarge entrance channel and complete turning basin to 1,200 feet Rivers and Harbors 
square. Committee Doc. 25, 
74th Cong., 1st sess. 
Widen turning basin 350 feet on north side. H.Doc. 545, 75th Cong., 
3d sess. 
Widen turning basin 200 feet on north side, 500 feet on south side H.Doc. 768, 78th Cong., 
and enlarge flare at entrance channel. 2d sess. 
Deepen and widen entrance channel on a new alinement and increase H.Doc. 346, 85th Cong., 
turning basin in size and depth. 2d sess. 
9-40

JACKSONVILLE, FL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
H.R. May 9, 1974 
S.R. May 31, 1974 
March 3, 1899 
June 13, 1902 
March 3, 1905 
June 20, 1938 
May 17, 1950 
March 3, 1899 
March 2, 1919 
June 14, 1880 
June 25, 1910 
July 3, 1930 
March 2, 1945 
March 2, 1945 
July 24, 1946 
March 2, 1945 
Deepen and widen entrance channel, enlarge turning basin, widen H.Doc. 144, 93rd Cc 
Pier 7 channel, maintenance of Berth 18 channel, and planning 1st sess. 
for a south jetty fishing walkway with construction contingent 
upon need as developed by detailed post authorization studies. 
REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE 
WATERS IN THE STATE OF FLORIDA (See Section 30 of Text) 
Construction and operation of a suitable vessel and use of log booms Annual Report 1899 
for removal of water hyacinths in the navigable waters of the State. 
Extermination and removal of water hyacinths by any mechanical, Specified in Act 
chemical or other means. 
Prohibits use of any chemical process injurious to cattle. Specified in Act 
ST. AUGUSTINE HARBOR, FL (See Section 31 of Text) 
Channel 27 x 200 feet protected by a groin. H.Doc. 555, 75th C 
Channel 16 x 200 feet across bar, and thence 12 feet deep to Intracoastal 
Waterway; jetty on south side of inlet; future landward extension of 
groin and jetty; and channel 10 x 100 feet in San Sebastian River. 
ST. JOHNS RIVER, FL, JACKSONVILLE TO LAKE 
HARNEY (See Section 32 of Text) 
A channel 13 feet deep and 200 feet wide from Jacksonville to 
Palatka. 
The improvement of Deep Creek. 
Two jetties at Volusia Bar (Maintenance only; new work completed 
under previous project). 
A channel 100 feet wide, 8 feet deep from Palatka to Sanford with a 
side channel to Enterprise, and thence 5 feet deep to Lake Harney. 
Cutoffs at Butcher Bend, Shake Creek, and Starks Landing, and 
easing bends at other points. 
A channel 10 feet deep and 100 feet wide from Palatka to Sanford, 
with a side channel to Enterprise and with cutoffs and easing of 
bends. (Cutoffs deauthorized) 
Combining the two projects above into a single project for St. Johns 
River, FL, Jacksonville to Lake Harney, and for a cutoff 5 feet 
deep and 75 feet wide between Lake Monroe and the vicinity of 
Osteen Bridge (Woodruff Creek Cutoff). 
A channel 12 feet deep and 100 feet wide from Palatka to Sanford, 
and in the branch to Enterprise. 
ST. LUCIE INLET, FL (See Section 33 of Text) 
Channel 10 x 200 feet. 
3d sess. 
H.Doc. 133, 81st Cong., 
1st sess. 
H.Doc. 523, 55th Cong., 
2d sess. and Annual 
Report 1899 p. 1343 
H.Doc. 699, 63rd Cong., 
2d sess. 
Annual Report for 1879, 
pp. 795-798 
H.Doc. 1111, 60th 
Cong., 2d sess. 
H.Doc. 691, 69th Cong., 
2d sess. 
H.Doc. 603, 76th Cong., 
3d sess. 
H.Doc. 445, 78th Cong., 
2d sess. 
S.Doc. 208, 79th Cong., 
2d sess. 
H.Doc. 391, 77th Cong., 
1st sess. 
9-41 
ong., 
ong.,

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
November 7, 1966 Modification to maintain existing channel 6 x 100 feet. 
H.R. May 9, 1974 
S.R. May 31, 1974 
August 8, 1917 
September 22, 1922 
July 3, 1930 
August 30, 1935 
August 26, 1937 
October 17, 1940 
March 2, 1945 
July 3, 1958 
August 4, 1976 
Report of the 
Chief of Engineers 
23 December 1982 
Extending north jetty and modifying existing jetty to provide a sand 
bypass weir section; excavation of sand impoundment basin; 
construction of south jetty with a walkway for recreational 
fishing; channel 10 x 500 feet through bar cut, tapering to 150 
feet through the inlet, and 100 feet and 7 feet deep to the 
Intracoastal Waterway; and transfer of 380,000 cubic yards of 
material to the south beach during each two-year maintenance period. 
SAN JUAN HARBOR, PR (See Section 34 of Text) 
Anchorage (inner harbor) area of 206 acres and San Antonio Channel 
to 30-foot depth. 
Substitution of a 68-acre area 30 feet deep along southeasterly side of 
anchorage area, for one 25 acres in extent and of same depth 
extending easterly from eastern end of the San Antonio project channel. 
Modified condition of local cooperation. 
Entrance channel across outer bar 38 feet deep and 800 feet wide, and thence 
across bay to anchorage area (Anegado Reach Channel) 30 feet deep and 700 
feet wide and increasing anchorage area to 239 acres to 30-foot depth. 
Widening Anegado Reach Channel and increasing anchorage area to 329 acres. 
Removal to 8-foot depth of Anegado, Largo, and Capitanejo Shoals, and 
dredging to 30-foot depth the entrance channel and turning basin to 
the Graving Dock. 
Maintenance of the 30-foot depth entrance channel and turning basin 
to the Army Terminal. 
Deepening portions of entrance and approach channels and basins to 
Army Terminal and San Antonio Pier areas to 35-45 feet; new 32- 
foot depth Puerto Nuevo Channel; new 36-foot depth anchorage. 
A bar channel 48 x 800 feet, shifting the centerline 350 feet west; deepening 
Anegado Channel in steps from 46 to 40 feet while reducing width to 800 
feet; deepening Army Terminal Channel and turning basin to 40 feet while 
widening the channel to 450 feet; deepening Puerto Nuevo Channel to 40 feet 
and widening it to 400 feet; deepening Graving Dock Channel to 40 feet at 
existing 400-foot width; deepening San Antonio Channel to 38 feet at varying 
widths, minimum of 500 feet; deepening cruise ship basin to 36 feet at an 
irregular width; maintaining Sabana Approach Channel at 30 x 250 feet; 
provide a 38-foot aepth in Anchorage Area "E" with irregular width; six 
mooring dolphins for vessels using the area. 
Modification of the authorized project to provide the deepening of the Bar 
Channel to 48 feet and shifting its alinement 350 feet to the west; 
deepening Anegado, and Army Terminal to 40 feet; deepening Graving Dock 
Channel, and Cruise Ship Basin, Puerto Nuevo Channel, and San Antonio 
Channel to 36 feet; and deepening Anchorage Area "E" to 38 feet while 
reducing its size and constructing six mooring dolphins within its 
limits. A 1,500-foot long extension to San Antonio Channel would be 
added to the Federal project and Sabana approach deepened to 32 feet. 
H.Doc. 508, 89th Cong., 
2d sess. 
H.Doc. 294, 93rd Cong., 
1st sess. 
H.Doc. 865, 63rd Cong., 
2d sess. 
Specified in Act 
H.Doc. 45, 71st Cong., 
2d sess. 
R&H Comm. Doc. 38, 
74th Cong., 1st sess. 
R&H Comm. Doc. 42, 
75th Cong., 1st sess. 
H.Doc. 364, 76th Cong., 
1st sess. 
Specified in Act 
H.Doc. 38, 85th Cong., 
1st sess. 
H.Doc. 574, 94th Cong., 
2d sess. 
P.L. 99-662 17 Nov 1986 
99th Cong., 2d sess. 
9-42

JACKSOUVIBL, FL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 3, 1899 
March 3, 1905 
June 25, 1910 
August 8, 1917 
March 3, 1899 
September 22, 1922 
July 3, 1930 
August 30, 1935 
June 20, 1938 
June 20, 1938 
March 2, 1945 
March 2, 1945 
TAMPA HARBOR, FL (See Section 35 of Text) 
TAMPA BAY 
For a channel 27 feet deep from the Gulf of Mexico to Port Tampa, 
500 feet wide across the bar and 300 feet wide in the bay. 
For a channel depth of 26 feet with sufficient width from the Gulf 
of Mexico to Port Tampa. 
TAMPA AND HILLSBOROUGH BAYS 
For a depth of 24 feet in Hillsborough Bay. 
For a 27-foot depth from Gulf of Mexico up to and in the several 
channels of Hillsborough Bay, the widths to be 500 feet on the 
bar, 300 feet in Tampa Bay, Ybor, and Garrison Channels, and 200 
feet in Hillsborough Bay, Sparkman, and Seddon Channels, with 
turning basins at the mouth of Hillsborough and at Ybor Estuary. 
HILLSBOROUGH RIVER 
For a 12 x 200 foot channel to within 100 feet of the Lafayette St. 
highway bridge (maintenance only; new work completed under a 
previous project under title Improving Hillsborough Bay, FL) 
TAMPA HARBOR 
Consolidation of the above projects to form a single project for Tampa Harbor. 
Increasing the depth of Egmont Channel to 29 feet and the width of 
Sparkman Channel to 300 feet. 
H.Doc. 52, 55th Cong., 
3d sess. (Also 
printed in Annual 
Report 1899, p. 1640) 
Channel dimensions 
specified in Act 
Specified in Act 
H.Doc. 634, 61st Cong., 
2d sess. 
H.Doc. 634, 61st Cong., 
1st sess. 
H.Doc. 545, 55th Cong., 
2d sess. and Annual Report 
1998, pp 1357-1360 
Specified in Act 
H.Doc. 100, 70th Cong., 
1st sess. 
For a depth of 32 feet and a width of 600 feet on Egmont Bar, a depth S.Doc. 22, 72nd Cong., 
of 30 feet and a width of 400 feet in Mullet Key Cut, and a depth 1st sess. 
of 30 feet and a width of 300 feet in all other project channels in 
Tampa Harbor (except in Hillsborough River and in the channel leading 
to Alafia River); and for a turning basin 2,000 feet long and 500 feet 
in maximum width at the entrance to the Port Tampa terminals. 
For widening the bend between Sparkman Channel and Cut D of Hillsborough S.Doc. 164, 75th Cong., 
Bay Channel by 250 feet; widening Ybor Channel to 400 feet and extending 3d sess. 
the turning basin at the west end of Garrison Channel (mouth of Hillsborough 
River) easterly for 300 feet. 
For construction of a breakwater at Peter O. Knight Field, Davis Sen. Comm. Print. 
Islands, its maintenance to be assumed by local interest. 76th Cong., 1st sess. 
For widening Sparkman Channel to 400 feet and TYbor Channel to 500 feet; S.Doc. 183, 78th Cong., 
widening the bend between Sparkman and Garrison Channels an additional 2d sess. 
250 feet to extend the turning basin westerly; and widening the bend 
between Seddon and Garrison Channels by 150 feet (in lieu of 300 feet 
previously authorized) to extend the turning basin easterly. 
For a channel 9 feet deep and 100 feet wide in the Hillsborough River for H.Doc. 119, 77th Cong., 
about 2.4 miles above the upper end of the existing 12-foot channel, 1st sess. 
and for the removal of obstructions thence to the Florida Avenue Bridge. 
9-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
March 2, 1945 
May 17, 1950 
September 3, 1954 
October 23, 1962 
December 31, 1970 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
Do. 
For a channel 25 feet deep and 150 feet wide from the Hillsborough S.Doc. 16, 77th Cong., 
Bay channel to and including a turning basin in the Alafia River. 1st sess. 
(Revoked by Act of May 17, 1950). 
For deepening Egmont Channel to 36 feet; enlarging Mullet Key Cut, Tampa H.Doc. 258, 81st Cong., 
Bay Channel, Hillsborough Bay Channel, Port Tampa Channel and Port 1st sess. 
Tampa turning basin to present project dimensions; deepening Sparkman 
Channel and Ybor turning basin to 34 feet; a channel 30 feet deep and 
200 feet wide from Hillsborough Bay Channel to and including a turning 
basin in Alafia River, 700 feet wide and 1,200 feet long (in lieu of 
the improvement previously authorized); and substantial widening at 
entrance, bends, and turns. 
Extended removal of obstructions in Hillsborough River to City Water Works H.Doc. 567, 81st Cong., 
Dam. Maintenance of cleared channel to be assumed by local interests. 2d sess. 
Channel and turning basin at Port Sutton 30 feet deep, Ybor Channel H.Doc. 529, 87th Cong., 
34 x 400 feet. 2d sess. 
For federal maintenance of Port Sutton Channel, 280 feet wide and H.Doc. 150, 91st Cong., 
an irregularly shaped turning basin both to a depth of 34 feet. 1st sess. 
Enlarge entrance channel across Egmont Bar to 46 x 700 feet from the H.Doc. 401, 91st Cong., 
Gulf to Mullet Key. 2d sess. 
Enlarge Mullet Key Cut Channel to 44 x 600 feet. Do. 
Enlarge Tampa Bay Channel to 44 x 500 feet from Mullet Key Cut through Do. 
Tampa Bay to the junction of Hillsborough Bay and Port Tampa Channels. 
Enlarge Hillsborough Bay Channel to 44 x 500 feet from the junction with Do. 
Tampa Bay and Port Tampa Channels to the junction with Port Sutton 
entrance channel, and thence deepening to a depth of 42 feet at the 
existing width of 400 feet to the junction with Seddon and Sparkman Channels. 
Enlarge Port Sutton entrance channel to 44 x 400 feet. Do. 
Enlarge Port Sutton turning basin to a depth of 44 feet and a Do. 
turning diameter of 1,200 feet. 
Deepening Sparkman Channel to 42 x 400 feet. Do. 
Deepening Ybor Channel to 40 x 300 feet. Do. 
Enlarge turning basin at the entrance to Ybor Channel to a depth of 42 feet and Do. 
an additional width of 200 feet on the southwest edge of the present basin. 
Deepening Port Tampa Channel to 42 feet at its existing width from the Do. 
junction with Hillsborough and Tampa Bay Channels to the turning basin. 
Deepening the Port Tampa turning basin to 42 feet over its existing Do. 
length of 2,000 feet and width of 900 feet. 
An entrance channel in East Bay 44 x 400 feet and 500 feet north from Do. 
the Port Sutton turning basin for a distance of about 2,000 feet. 
A turning basin in East Bay at a depth of 44 feet and with a turning Do. 
diameter of 1,200 feet. 
An approach channel in East Bay 44 x 300 feet north from the East Do. 
Bay turning basin for a distance of about 2,500 feet. 
9-44

JACKSOYVIII, FL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Do. Maintenance of Port Sutton Terminal channel to 44 x 200 feet for a 
distance of 4,000 feet. 
August 15, 1985 Maintenance of East Bay channel to 34 x 300 feet for a distance of 
5,500 feet. 
Report of the Port Sutton Channel deepening to 43 feet for a distance of 3,700 
Chief of Engineers feet and a width of 200 feet. 
28 March 1988 
W.R.D.A. Maintenance of Alafia Channel to a depth of 34 feet, if a Non-Federal 
November 28, 1990 Sponsor agrees to reimburse the Secretary 
TAMPA HARBOR BRANCH CHANNELS 
Report of the Enlarging Hillsborough Bay Cut D, Sparkman Channel, Port Tampa Channel 
Chief of Engineers and existing turning basins at the entrance to Ybor Channel and 
25 January 1979 at Port Tampa, all to a depth of 41 feet with varying lengths and 
widths and deepening Ybor Channel to a depth of 39 feet. This work 
will be associated with the Main Channel deepening. 
TAMPA HARBOR EAST BAY CHANNEL 
W.R.D.A. Maintenance dredging at an average annual cost of $471,000. 
17 Nov. 1986 
BEACH EROSION BREVARD COUNTY, FL (See Section 39 of Text) 
CONTROL PROJECTS 
August 13, 1968 Federal participation in cost of shore protection project. 
BROWARD COUNTY, FL BEACH EROSION CONTROL 
AND HILLSBORO INLET, FL, NAVIGATION PROJECT 
(See Section 40 of Text) 
October 27, 1965 Improvement for beach erosion control in Broward County, FL and a 
combined beach erosion and navigation improvement to 
Hillsboro Inlet and the shore south thereof to Port Everglades. 
W.R.D.A. Deauthorized navigation improvement to Hillsboro Inlet. 
November 17, 1986 
W.R.D.A. Continued authorization for Hillsboro Inlet dredging for 5 years. 
November 28, 1990 
CHARLOTTE COUNTY, FL 
Report of the Shoreline protection. 
Chief of Engineers 
2 April 1982 
August 13, 1968 
August 15, 1985 
DADE COUNTY, FL (See Section 48 of Text) 
Federal participation in cost of shore protection and hurricaneflood 
control project. 
DADE COUNTY-NORTH OF HAULOVER BEACH, FL 
(See Section 48 of Text) 
Federal participation in cost of shore protection and hurricaneflood 
control project. 
Do. 
H.Doc. 236, 99th Cong., 
1st sess. 
P.L. 100-676,17 Nov. 1988, 
100th Cong., 2d sess. 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
H.Doc. 352, 90th Cong., 
2d sess. 
H.Doc. 91, 89th Cong., 
1st sess. 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
P.L. 101-640,28 Nov. 1990, 
101st Cong., 2d sess. 
P.L. 99-662 17 Nov. 1986, 
99th Cong., 2d sess. 
H.Doc. 335, 90th Cong., 
2d sess. 
H.Doc. 236, 99th Cong., 
1st sess. 
9-45

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Report of the 
Chief of Engineers 
27 December 1983 
October 27, 1965 
W.R.D.A. 
17 Nov. 1986 
S.R. 31 May 1974 
and H.R. 20 Nov. 
1975 
W.R.D.A. 1990 
November 28, 1990 
Report of the 
Chief of Engineers 
22 April 1984 
Report of the 
Chief of Engineers 
May 19, 1986 
October 23, 1962 
May 17, 1950 
July 3, 1958 
November 7, 1966 
Report of the Board 
of Engineers for 
Rivers and Harbors 
23 April 1985 
Extending of existing shore protection project for Dade County to P.L. 99-662 17 Nov. 1986, 
provide for protective beach fill and subsequent nourishment 99th Cong., 2d sess. 
along 2.5 miles of shore north of Haulover Beach Park. 
DUVAL COUNTY, FL (See Section 41 of Text) 
Federal participation in cost of local shore protection project. H.Doc. 273, 89th Cong., 
1st sess. 
INDIAN RIVER COUNTY, FL (See Section 42 of Text) 
The plans provide for a 2.65 mile beach fill along the ocean shore of P.L. 99-662 17 Nov. 1986, 
Vero Beach, a 1.7 mile beach fill along the ocean shore of Sebastian 99th Cong., 2d sess. 
Inlet State Park and for periodic nourishment of the new beaches. 
MANATEE COUNTY, FL (See Section 43 of Text) 
The plan provides for a level berm 50 feet wide at an elevation 6 feet S.Doc. 37, 93rd Cong., 
(MLW) along 3.2 miles of shore on Anna Maria Island and nourishment 1st sess. 
of entire Gulf shore of that island as needed throughout project life. 
MARTIN COUNTY 
Periodic nourishment over the 50 year life of the project. P.L. 101-640,28 Nov. 1990, 
101st Cong., 2d sess. 
MONROE COUNTY, FL 
Modification of existing project from 6,200-foot long to 8,770-foot P.L. 99-662, 17 Nov. 1986, 
long beach fill stabilized with 2 groins and periodic nourishment. 99th Cong., 2d sess. 
NASSAU COUNTY, FL 
Improvement for beach erosion control on Amelia Island. P.L. 100-676,17 Nov. 1988, 
100th Cong., 2d sess. 
PALM BEACH COUNTY, FL, FROM MARTIN COUNTY 
LINE TO LAKE WORTH INLET AND FROM SOUTH 
LAKE WORTH INLET TO BROWARD COUNTY LINE 
(See Section 44 of Text) 
Federal participation in cost of local shore protection project and H.Doc. 164, 87th Cong., 
sand-transfer plant. 1st sess. 
PALM BEACH COUNTY, FL, FROM LAKE WORTH 
INLET TO SOUTH LAKE WORTH INLET, FL 
(See Section 44 of Text) 
Federal participation in cost of local shore protection project on H.Doc. 772, 80th Cong., 
Palm Beach Island. 2d sess. 
Federal participation in cost of local sand-transfer plant at Lake H.Doc. 342, 85th Cong., 
Worth Inlet and shore protection project. 2d sess. 
PINELLAS COUNTY, FL (See Section 45 of Text) 
Federal participation in cost of shore protection project. H.Doc. 519, 89th Cong., 
2d sess. 
Restoration of 5,000 feet of beach at Clearwater Beach Island, P.L. 99-662 17 Nov. 1986, 
49,000 feet of beach at Sand Key, 92,000 feet of beach at Treasure 99th Cong., 2d sess. 
Island, and construction of 600 feet of revetment at Long Key. 
Also, renourishment of each island. 
9-46

JAK, PL DISTRICT 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
SARASOTA COUNTY, FL (See Section 46 of Text) 
Report of the Shoreline protection along 12,600 feet of shoreline on central 
Chief of Engineers Longboat and 21,100 feet on Manasota Key in the vicinity of 
28 February 1986 Venice, Florida and periodic nourishment of these areas. 
ST. JOHNS COUNTY, FL 
Report of the Shoreline protection along 2.5 miles of problem area in the St. 
Chief of Engineers Augustine Beach and Coquina Gables area and periodic nourishment. 
26 February 1980 
FLOOD CONTROL 
PROJECTS CENTRAL AND SOUTHERN FLORIDA (See Section 49 of 
June 30, 1948 First phase of comprehensive plan for flood control and other 
purposes. 
September 3, 1954 Modification and expansion of authorization to include entire 
comprehensive plan of improvement. 
July 14, 1960 Canals, levees, and water-control and drainage structures in the 
Nicodemus Slough area, Glades County. 
October 23, 1962 Flood protection on Boggy Creek, near Orlando. 
Do. Flood protection in the Cutler Drain area, near Miami. 
Do. Flood control and drainage works for South Dade County. 
Do. Project Shingle Creek between Clear Lake and Lake Tohopekaliga for flood 
control and major drainage, including development of Reedy Creek Swamp. 
Do. Improvement of easterly section of West Palm Beach Canal for flood 
control and major drainage. 
October 27, 1965 Primary works for flood control and major drainage in southwest 
Dade County. 
Do. Primary works for flood control and major drainage in Hendry 
County. 
August 13, 1968 Gravity drainage in Martin County and distribution of available 
water supplies to portions of Martin and St. Lucie Counties. 
Do. Improvement of supply, distribution and conservation of water resources 
in Central and Southern Florida, including Lake Okeechobee 
agricultural area, Everglades National Park and other related areas. 
Approved Navigation improvements suitable for recreational craft. 
December 17, 1970 
under the provisions 
of Section 201 of 
the Flood Control 
Act of 1965 
P.L. 99-662 17 Nov. 1986, 
99th Cong., 2d sess. 
P.L. 99-662 17 Nov. 1986, 
99th Cong., 2d sess. 
Text) 
H.Doc. 643, 80th Cong., 
2d sess. (Contains 
latest published map) 
H.Doc. 643, 80th Cong., 
2d sess. 
S.Doc. 53, 86th Cong., 
1st sess. 
S.Doc. 125, 87th Cong., 
2d sess. 
S.Doc. 123, 87th Cong., 
2d sess. 
S.Doc 138, 87th Cong., 
2d sess. 
S.Doc. 139, 87th Cong., 
2d sess. 
S.Doc. 146, 87th Cong., 
2d sess. 
S.Doc. 20, 89th Cong., 
1st sess. 
H.Doc. 102, 88th Cong., 
1st sess. 
S.Doc. 101, 90th Cong., 
2d sess. 
H.Doc. 369, 90th Cong., 
2d sess. 
H.Doc. 394, 91st Cong., 
2d sess. 
9-47

REPORT OF THE SECRETARY OF TEE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Deauthorized flood protection on Boggy Creek, near Orlando; primary works 
for flood control and major drainage in southwest Dade County; and 
navigation improvements suitable for recreational craft. 
W.R.D.A Extended modified water delivery schedules to Everglades National Park to 
November 17, 1988 January 1, 1992. 
Everglades National 
Park Protection and 
Expansion Act of 
1989 
October 23, 1962 
W.R.D.A. 
November 17, 1986 
Construct modifications to the Central and Southern Florida Project to 
improve water deliveries into the park and shall, to the extent practicable, 
take steps to restore the natural hydrological conditions within the park. 
FOUR RIVER BASINS, FL (See Section 52 of Text) 
Control of floods and improvement of drainage, and for water 
conservation through construction of necessary canals, levees, 
reservoirs, and control structures. 
Deauthorized Anclote River control structure and channel improvement. 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
P.L. 100-676,17Nov. 1988, 
P.L. 101-229, 13 Dec. 1989, 
101st Cong., 2d sess. 
H.Doc. 585, 87th Cong., 
2d sess. 
P.L. 99-662, 17 Nov. 1986, 
99th Cong., 2d sess. 
PORTUGUES AND BUCANA RIVERS, PR 
(See Section 53 of Text) 
December 31, 1970 
LAGO de CERILLOS, PR 
Multiple purpose dam and lake for flood control, water supply and 
recreation. 
H.Doc. 422, 91st Cong., 
2d sess. 
LAGO de PORTUGUES, PR 
Multiple purpose dam and lake for flood control, water supply and recreation. 
PONCE, PR 
Diversion and enlargement of existing channels through Ponce for flood control. 
Report of the 
Chief of Engineers 
25 April 1986 
Report of the 
Chief Engineers 
January 1989 
RIO PUERTO NUEVO, PR 
Project for flood control. 
RIO DE LA PLATA, PR 
Project for flood control. 
P.L. 99-662 17 Nov. 1986, 
99th Cong., 2d sess. 
Sec. 205 of the 
Flood Control 
Act of 1948 
SAVAN GUT, *ST. THOMAS, VI 
Project for flood control. Increased maximum allotment to 
$100,000. 
W.R.D.A. Set maximum amount allotted under Section 205 of the Flood 
November 28, 1990 Control Act of 1948 at $10,000,000. 
W.R.D.A. 
November 28, 1990 
KISSIMMEE RIVER, FL 
Conduct a feasibility study for the purpose of determining modifications of 
the flood control project for central and southern Florida, authorized by 
section 203 of Flood Control Act of 1948 (62 Stat. 1176), which are 
necessary to provide a comprehensive plan for the environmental restoration. 
P.L. 858, 30 Jun. 1948, 
80th Cong, 2d sess. 
P.L. 101-640,28 Nov. 1990, 
101st Cong., 2d sess. 
P.L. 101-640,28 Nov 1990, 
101st Cong., 2d sess. 
9-48 
W.R.D.A. 
November 17, 1986

JACKSONVILLE, FL DISTRICT 
TABLE 9-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 37 of Text) 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Anclote River, FL 1974 $ 267,427 $ 636,427 
Aquatic Plant Control, FL 
(R&H Acts of 1958 & 1962) 1968 1,640,997 2 
Atlantic Gulf Ship Canal, FL 1939 5,099,153- 
Bayport, FL' 1972 58,495 - 
Cedar Keys Harbor, FL 1977 168,569 s 76,023 
Christiansted Harbor, St. Croix, VI' 1964 303,317 58,595 
Clearwater Pass, FL2' 1980 46,349 ' 1,257,684 
Courtnay Channel, FL' 1940 22,846 26,779 
Crystal River, FL' 1941 25,000 135,212 
Everglades Harbor, FL' 1964 221,509 ' 51,034 
Fajardo Harbor, PR' 1945 - - 
Guayanes Harbor, PR' 1945 
Gulf Intracoastal Waterway 
St. Marks to Tampa Bay, FL' 1974 38,850- 
Hillsboro Inlet, FL 1965- 
Homosassa River, FL' 1937 3,999' 26,454 
Horseshoe Cove, FL 1977 347,521 161,864 
Hudson River, FL' 1974 9,889- 
Intracoastal Waterway1 Miami to Key West, FL' 1963 243,079 28,046 
Key West Harbor, FL 1972 1,548,892 " 534,623 
Kissimmee River, FL' 1931 23,479 112,954 
Lake Crescent and Dunns Creek, FL" 1931 10,276 9,035 
Largo Sound Channel, FL' " 1966 117,443 U 51,149 
Little Manatee River, FL".n 1949 11,903 " 
Manatee River, FL"s 1970 123,350 194,516 
New River, FL' 1956 36,518 31,296 
Orange River, FL' 1962 2,000 24,918 
Ozona, FL, channel and turning basin' 1963 105,527 15,089 
Palm Beach, FL, side channel and basin' 1946 - - 
Pass-A-Grille Pass, FL" 6 1966 41,297 ' 60,686 
Pithlachascotee River, FL 1973 400,000 s 261,401 
Rice Creek, FL' 1957 85,208 19 18,814 
St. Petersburg Harbor, FL 1983 255,608 1,570,552 21 
St. Thomas Harbor, VI' 1949 1,989- 
Steinhatchee River, FL' 1940 135,053 44,439 
Suwannee River, FLU 1977 76,418 219,570 
Withlacoochee River, FLU 1969 614,912 23 431,545 
' Complete. 
2 Excludes $1,640,997 contributed funds. 
' Inactive. 
Includes $41,222 for reconnaissance and detailed project reports 
under Section 107 of the R&H Act of 1960. 
s Includes $82,500 expended under previous project. Excludes 
$1,473 contributed funds. 
6 Project as modified by Chief of Engineers in report of June 30, 
1961, is complete. Previously authorized depth of 25 feet in 
inactive status. 
Excludes $42,783 contributed funds. 
' Excludes $36,000 contributed funds. 
'In addition, $1,000 expended from contributed funds. 
10 Includes $27,500 for new work under previous project. 
Excludes $35,371 contributed funds. 
n Deauthorized by Public Law 93-251, Section 12. 
u Authorized April 20, 1964 by Chief of Engineers under Section 
107 of 1960 R&H Act. 
" Includes $25,008 for detailed project report but excludes 
$86,716 expended from contributed funds. 
1 Expended on restudy. 
SInactive portion of project deauthorized by Public Law 93-251, 
Section 12. 
" Authorized November 19, 1964 by Chief of Engineers under 
Section 107 of R&H Act of 1960. 
'7 Excludes $41,297 contributed funds. 
" Excludes $215,728 contributed funds. 
9 Excludes $93,000 contributed funds. 
' Includes $32,689 under previous project. 
21 Includes $20,532 under previous project. 
SIncludes $10,154 expended under previous project. 
2 Includes $30,000 expended under previous project. 
' Authorized by Section 301, R&H Act of 1965 and Section 
107 of P.L. 101-640. 
9-49

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-D OTHER AUTHORIZED BEACH EROSION PROJECTS 
(See Section 48 of Text) 
For Last Cost to Sep 30, 1992 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Cape Florida State Park, FL 1969 $34,862 $ - 
El Tuque Beach, Ponce, PR 1985 1,396,730 
Lee County, FL 1971 - 
Manatee County, FL 1983 217,600 - 
Punta Salinas, PR 1984 855,511- 
Palm Beach County, FL, from Lake Worth Inlet to 
South Lake Worth Inlet 1970 195,140 6,257 
San Juan, PR 1965 - 
TABLE 9-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 56 of Text) 
For Last Cost to Sep 30, 1992 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arch Creek, Dade County, FL 1960 $66,485 1- 
Biscayne Bay, FL, Hurricane Protection 2 1966 - - 
Hillsborough Bay, FL 2 1969 - - 
Phillippi Creek Basin, FL2 1966 - - 
Excludes $11,734 cost of preauthorization studies. Project was authorized February 20, 1959, by Chief of Engineers under Section 
205 of the 1948 Flood Control Act as modified by P.L. 685, 84th Congress. 
2 Deauthorized by Public Law 93-251, Section 12. 
9-50

JACKSONVILLE, FL DISTRICT 
TABLE 9-H NAVIGATION PROJECTS ON WHICH RECONNAISSANCE AND 
CONDITION SURVEYS ONLY WERE CONDUCTED DURING FISCAL YEAR 
(See Section 36 of Text) 
Date Survey Cost Incurred 
Project Conducted During Period 
AIWW, Norfolk to St. Johns River, FL 9-92 -1,519 
Anclote River, FL 11-91 4,910 
Channel, Naples to Big Marco Pass, FL 11-91 22,699 
Cedar Key Harbor, FL 2-91 20,890 
Clearwater Pass, FL 3-92 29,747 
Eau Gallie Harbor,FL 9-91 3,237 
Fort Myers Beach, FL 9-92 5,073 
Key West Harbor, FL 5-91 4,137 
Mayaguez Harbor, PR 12-91 3,362 
Melbourne Harbor, FL 11-91 1,854 
Miami Harbor, FL 9-92 19,043 
Oklawaha River, FL 11-91 87 
Palm Beach Harbor, FL 11-91 75 
Ponce de Leon Inlet, FL 2-92 801 
Ponce Harbor, PR 12-91 2,300 
Port Everglades, FL 3-92 4,138 
St. Johns River to Lake Harney, FL 5-92 497 
St. Lucie Inlet, FL 2-92 24,900 
A/E Contract 195,918 
Total $ 342,149 
9-51

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-I CANAVERAL HARBOR, FL PROJECT 
DATA RELATIVE TO LOCK 
(See Section 5 of Text) 
Distance to nearest town 9.9 miles via 12-foot barge canal and 
Intracoastal Waterway 
Name of nearest town Cocoa, FL 
Distance from Intracoastal Waterway 6.5 miles 
Lock dimensions 90' wide; 600' long' 
Lift Varies with tide 
Depth of Sills (mlw, ocean) 14 feet 
Character of foundation Piles in sand 
Year completed and opened to navigation 1965 
Contract cost $2,979,670 
' 56x400 feet authorized. At request of NASA lock was with increased width. Operation and maintenance of lock is a 
constructed 90 feet wide with NASA bearing additional cost Federal responsibility. 
($700,000). Length increased to 600 feet to be compatible 
TABLE 9-J CROSS-FLORIDA BARGE CANAL PROJECT 
LOCKS AND DAMS 
(See Section 8 of Text) 
R.N. 
Henry H. Buckman Eureka Lock Bert Dosh Dunellon Inglis Lock 
Lock and Dam Lock Lock and Dam 
Nearest town Palatka, Sparr, Ocala, Dunnellon, Inglis, 
(miles) 11.2 15.8 8.9 2.5 3.2 
Miles from Atlantic 
Intracoastal 
Waterway 90.4 111.4 127.7 156.5 168.6 
Lock dimensions (ft.)' 84 x 600 84 x 600 84 x 600 84 x 600 84 x 600 
Normal lift (ft.) 20 20 0-152 12-272 28 
Depth over sills at 
normal pool levels: 
Upper (ft.) 14 17 16-312 16-312 18 
Character of Piles in Piles in Piles in Rock Rock 
foundation sand sand sand 
Kind of dam Movable Movable None None Movable 
Type construction Earth3 Earth' - - Earth3 
Percent complete 100 100 0 0 100 
Estimated contract 
cost $6,094,000 $7,975,000 $7,430,000 $9,500,000 $7,800,000 
Clearwidt.andgreaest.aailale.lngth 
2 Clear width and greatest available length. 
2 Pool level varies with natural ground water profile from 
minimum elevation of 40 feet to maximum elevation of 55 
feet. 
'With concrete spillway and movable gates. 
9-52

JACKSONVILLE, FL DISTRICT 
TABLE 9-K CROSS FLORIDA BARGE CANAL 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 8 of Text) 
Work Performed Cost 
Operation and Maintenance: 
Operations of locks, operations and maintenance of 
dams, spillways, reservoirs and bypasses, debris 
removal, performance monitoring system $ 223,445 
Buildings and grounds maintenance, trash removal, 
potable water testing 217,575 
Natural Resources Management 4,073 
Operation and maintenance of recreation facilities, 
sanitary facilities, service and maintenance of 
traffic counters and contract maintenance of grounds 86,453 
Condition and operations studies and periodic inspections 77,529 
Energy Conservation 0 
Water quality studies, data collection and processing, 
reimbursement to USGS, water control analysis 
Lake Oklawaha and Inglis Bypass, and water 
management control 100,388 
Real Estate audits, inspections and outgrants 27,699 
OSHA medical exams 4,859 
Construction Management 373,272 
Sub-Total $1,115,293 
Maintenance: 
Lands and Damages $ 55,590 
Maintenance of dams and spillways and contract maintenance 59,498 
Maintenance of locks and lock repair contract 119,186 
Maintenance of roads, bridges 44,008 
Maintenance of recreational facilities, roads and bridges 72,692 
Maintenance of levees and floodwalls 35,941 
SRUF 0 
Maintenance of permanent operating equipment (Recreation) 84,282 
Maintenance and purchase of non-recreational permanent 
operating equipment 0 
Bank stabilization-maintenanceof slopes and berms, 
Rodman and Inglis dams, and bank 
stabilization contract 220,094 
Maintenance of canals, clearing and snagging 28,621 
Engineering and Design 498 
Construction Management 58,382 
Income Credits -1,794 
Sub-Total $ 776,998 
Grand Total $1,892,291 
9-53

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-L OKEECHOBEE WATERWAY 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 24 of Text) 
Work Performed Cost 
Operations and Maintenance: 
Operations: 
Operations of Locks, and Permanent 
Monitoring System 
Contract maintenance buildings, grounds, potable 
water testing, repair and replacement of project 
signs, operation and maintenance of District 
communications network 
Natural resource management 
Management of recreation areas and facilities 
Real estate management and energy conservation reports 
OSHA medical exams and inspections 
Condition and operation studies, periodic inspections 
Construction Management 
Sub-Total 
Maintenance: 
Maintenance of locks and dams 
Real estate acquisitions, surveys, and encroachments 
Maintenance of recreational roads 
Maintenance of recreational facilities 
Maintenance of banks, revetments and dikes 
Maintenance of permanent operating equipment 
non-recreational 
Channel and canal maintenance 
Engineering and Design 
Construction Management 
Income Credits 
Sub-Total 
$ 607,479 
313,636 
170,828 
204,494 
26,756 
1,672 
131,860 
103,887 
1,560,612 
64,793 
29,468 
26,083 
1,578,148 
35 
207,973 
510,993 
213,766 
-7,846 
2,984,935 
Total $ 4,537,698 
9-54

TABLE 9-N CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF LOCKS AND DAMS 
(See Section 50 of Text) 
Miles Elevation 
From Lock Normal of Normal Depth Character Kind Kind 
Nearest Nearest Dimensions lift Pool of sills of of of Percent Contract 
Town Town (ft.) (ft.) surface (ft.) (ft.) foundation Dam Construction Complete Cost 
W.P. Franklin At Olga 
Lock and Dam 1 
S-65 Lock Frostproof 
S-65A Lock Avon Park 
S-65B Lock Sebring 
S-65C Lock Sebring 
S-65D Lock Okeechobee 
I S-65E Lock Okeechobee 
U, 
U, 
Moore Haven Moore Haven 
Lock (HGS- 1 
Mod.) 
S-310 Clewiston 
(HGS-2 Mod.) 
S-193 Okeechobee 
(HGS-6 Mod.) 
S-308B Pahokee 
(Port Mayaca) 
S-57 Ashton 
S-58 
S-59 
S-60 
S-61 
S-62 
S-63 
S-63A 
S-96 
S-96A 
S-53 
S-55 
S-157 
S-158 
Ashton 
Kissimmee 
Ashton 
St. Cloud 
Ashton 
Ashton 
Ashton 
Sebastian 
Sebastian 
Eau Gallie 
Christmas 
Sebastian 
Titusville 
0 56 x 400 2.5 3.0 
23 30x90 
26 30x90 
20 30x90 
25 30x90 
14 30 x 90 
10 30 x 90 
0.5 50 x 250 
0.5 50 x 60 
0.5 50 x 60 
11 56 x 400 
9 20x90 
5 20x90 
6 20x90 
6 20x90 
6 20x90 
10 20x90 
12 20 x 90 
14 20x90 
14 20x60 
16 20x60 
8 20x60 
12 20x60 
4 20x60 
15 20x60 
4.2 
6.3 
6.0 
7.2 
5.8 
4.6 
9.4 
5.0 
7.5 
4.0 
1.0 
2.0 
3.0 
2.0 
2.0 
3.0 
5.0 
4.5 
4.0 
7.5 
3.5 
10.0 
20.0 
4.5 
48.5 - 52.3 s 
46.3 
40.0 
34.0 
26.8 
21.0 
15.5 - 17.5 ' 
15.5 - 17.5 ' 
15.5 - 17.5 3 
15.5 - 17.5 ' 
62.0 
64.0 
58.0 
64.0 
55.0 
61.0 
62.0 
57.0 
24.0 
25.0 
17.5 
14.0 
20.0 
4.0 
14 Piles in 
clay 
6 Earth 
foundation, 
sand 
6 Earth 
foundation, 
sand 
6 Earth 
foundation, 
sand 
6 Earth 
foundation, 
sand 
6 Earth 
foundation, 
sand 
6 Earth 
foundation, 
sand 
11 Piles in 
sand 
lockwalls 
12.9 Slab on 
sand 
7.5 Piles in 
sand and 
slab on sand 
18 Slab on 
sand 
6 Earth 
foundation, 
sand 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
6 Do. 
Movable Reinforced 100 $3,803,655 
concrete 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
rigid frame 
None Reinforced 
concrete 
None Steel 
sheet pile 
None Reinforced 
concrete 
None Reinforced 
concrete 
Fixed Reinforced 
concrete 
None Concrete and 
steel sheet 
pileNone 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
None Do. 
$1,211,465 
$1,531,490 
$1,068,397 
$1,357,246 
$1,242,909 
$1,320,040 
$433,000 2 
$3,448,406 
$615,0002 
$8,308,700 
$2,355,000 2 
$2,355,000 2 
$2,349,000 
$2,355,000 2 
$2,355,000 2 
$689,217 2 
$2,355,000 
$2,305,000 2 
$2,063,000 
$1,965,000 2 
$1,908,000 2 
$1,955,000 2 
$2,486,000 2 
$2,247,000 : 
Operation and care of W.P. Franklin Lock and Dam (S-79) is a Federal responsibility. 
SEstimated (Oct 1990). 
C, 4 
0
n
0"
d
H
'1 
H0o 
H 
100 
100 
100 
100 
100 
100 
0 
100 
0 
100 
0
00 
10 
100 
000000000 
lOO 
lO 
1oo 
ooo

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-M REMOVAL OF AQUATIC GROWTH FROM NAVIGABLE WATERS 
IN THE STATE OF FLORIDA 
CONTROL OPERATIONS 
(See Section 30 of Text) 
Locality Acres Controlled Cost 
St. Johns River and tributaries and 
Withlacoochee, Kissimmee and Crystal Rivers 15,800 $ 1,742,536 
Okeechobee Waterway and tributaries 10,892 691,083 
Acquisition and maintenance of airboats, 
engines and work tools -82,229 
Operation of service facilities 15,000 
Income credits - - 
OSHA medical exams - 1,997 
Engineering and Design- 1,191 
Construction Management- 187,784 
Total 26,692 $ 2,721,820 
9-56

JACKSONVILLE, FL DISTRICT 
TABLE 9-0 CENTRAL AND SOUTHERN FLORIDA PROJECT 
CONSTRUCTION COMPLETED DURING FISCAL YEAR 1992 
(See Section 50 of Text) 
Date transferred to 
Flood Control District 
Construction for Operation and 
Feature Period Maintenance 
Channels and Canals: 
C-51 (Kirk Rd to Turnpike) September 1989 - September 1992 
Levees: 
Upper St. Johns L-77 & L-74N (Part) January 1990 - September 1992 
Structures: 
Upper St. Johns S-251, S-254 & S-255 January 1990 - September 1992 
TABLE 9-P CENTRAL AND SOUTHERN FLORIDA PROJECT 
STATUS OF WORK UNDER CONTRACT AT END OF FISCAL YEAR 1992 
(See Section 50 of Text) 
Construction Approx. % 
Feature Started Complete 
Channels and Canals: 
Upper St. Johns S-254 Flow-Way October 1991 86 
Levees: 
Upper St. Johns L-75 & S-5 June 1990 98 
Upper St. Johns L-74W September 1991 99 
Upper St. Johns L-74N (Part) and L-75 (Rem) September 1992 0 
Upper St. Johns Recreation September 1992 0 
Structures: 
Upper St. Johns S-250A, S-250B, 
S-250C & S-250D September 1991 87 
Upper St. Johns S-256 & S-259 September 1992 0 
9-57

REPORT OF THE SECRETARY OF THE ARME ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-Q CENTRAL AND SOUTHERN FLORIDA PROJECT 
PRINCIPAL FEATURES OF HURRICANE GATES 
(See Section 50 of Text) 
Depth Character 
Over of Year 
Gate' Nearest Town Distance Sills Founda- Com- Actual 
No. Name (miles) (feet) tion pleted Cost 
2. Clewiston, FL 0.5 10 Pile 1935 $309,748 
3. Lake Harbor, FL 0.5 10 Rock 1935 316,938 
4. Belle Glade, FL 4.0 10 Rock 1935 350,025 
5. Canal Point, FL 0.0 10 Rock 1935 262,465 
6. Okeechobee, FL 0.5 7 Pile 1936 373,273 
'All are 50 feet wide with available length unlimited. They are constructed of concrete with steel sector gates and have no lift. 
Gate No. 6 has an auxiliary culvert spillway with automatic control. Moore Haven Lock serves as Hurricane Gate Structure 1. 
TABLE 9-R CENTRAL AND SOUTHERN FLORIDA PROJECT 
LOCAL COOPERATION 
(See Section 50 of Text) 
Flood Control Act Work Authorized Cash Contribution1 
Jun. 30, 1948 First phase of comprehensive plan 15.0 
Sep. 3, 1954 Second phase of comprehensive plan 20.0 
Jul. 14, 1960 Nicodemus Slough area 31.5 
Oct. 23, 1962 West Palm Beach Canal 12.8 
Boggy Creek Basin 29.7 
Shingle Creek Basin 25.9 
South Dade County area 19.2 
Reedy Creek Swamp 50.0 
Oct. 27, 1965 Southwest Dade County 46.0 
Hendry County area 19.5 
Aug. 13, 1968 Martin County 
Flood Control Features 34.0 
Irrigation Features 49.0 
Backflow Features 20.0 
P.L. 89-72 Recreation Features 50.0 
Water Resources - St. Lucie 20.0 
Recreation Features 50.0 
Approved Dec. 17, 1970 Navigation improvements suitable for 
under provisions of recreational craft 50.0 
Section 201 of 1965 
Flood Control Act 
(Deauthorized Jan. 1, 1990 
by P.L. 99-662) 
P.L. 99-662 Upper St. Johns River Basin - 
non-structural flood protection 25.0 
Computed on total contract cost and supervision and 
administation except for Reedy Creek Swamp and Recreation 
Features which are computed on all costs, including engineering 
and design and land. 
9-58

JACKSONVILLE, FL DISTRICT 
TABLE 9-S CENTRAL AND SOUTHERN FLORIDA PROJECT 
OPERATIONS AND RESULTS DURING FISCAL YEAR 
(See Section 50 of Text) 
Work Performed 
New Work: 
Lands and damages 
Construction of 
Railroad bridges 
Channels and canals 
Levees 
Floodway control and diversion structures 
Pumping plants 
Buildings, grounds and utilities 
Cultural Resource Preservation 
Equipment operation 
Depreciation 
Engineering and Design 
Construction Management 
Total cost 
Operations: 
Operation of locks, dams, reservoirs and performance system 
Maintenance, buildings and grounds, operation of District 
communications network, repair and replacement of project signs 
Patrol, inspection, and maintenance of Herbert Hoover Dike, 
HGS 3, 4, and 5, operation and maintenance of drainage 
ditches, culverts and 16 spillways, and pumping costs 
Natural resource management 
Operation and maintenance of recreation facilities, service 
and maintenance of traffic counters, master planning 
Condition and operation studies, periodic inspections, 
dam safety studies 
Water quality/water control studies, data collection, 
regulation of Lake Okeechobee and three conservation areas 
Energy conservation 
Real estate outgranting 
OSHA inspections 
Construction Management 
Sub-Total 
Maintenance: 
Maintenance of natural resources 
Maintenance of locks and dams 
Maintenance of non-recreational roads and bridges 
Repair and stabilization of Crown Road, Herbert Hoover Dike, 
removal of weeds, rebuilding and regrading levee slopes, 
modification and maintenance of safety barriers, HGS 3, 4, and 5, 
cleaning landside toe ditches, repair of culverts, replacement 
of fences, removal of trees, topping of trees, control of 
Melaleuca, replacement of rip rap on slopes and berms 
Maintenance of recreational facilities 
Maintenance of hydrometrological network 
Maintenance and purchase of non-recreational permanent 
operating equipment 
Bank stabilization 
Non-dredging channel maintenance and debris removal 
Engineering and Design 
Construction Management 
Income credits 
Sub-Total 
Total 
Special recreation user fees 
9-59 
Cost 
$ -1,204
0 
1,007,092 
2,528,929 
576,047
00 
484
00 
3,089,877 
825,115 
$ 8,026,340 
736,860 
355,015 
541,094 
138,087 
193,206 
68,574 
1,274,089 
6,390 
6,719 
2,412 
148,601 
$ 3,471,047 
1,803 
419,004
0 
597,975 
550,499
0 
458,934 
16,514
0 
260,977 
259,025
0 
2,564,731 
6,035,778 
00

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 9-T FOUR RIVER BASINS, FLORIDA PROJECT 
CONDITION AT END OF FISCAL YEAR 1992 
(See Section 53 of Text) 
Date transferred to 
Construction Southwest Florida 
Feature Period for Operation and Maintenance 
Bridges: 
B-194 
Alteration of Facilities B-195 
B-594 
Alteration of Facilities B-196 
SCL RR Bridge, B-196 
Channels and Canals: 
C-135 
C-135, Sec. 1A 
C-135, Sec. lB 
C-135, Sec. I1C & 2 
C-135, Sec. 3A 
C-135, Sec. 3B 
C-135, Sec. 4A 
C-136 
C-231, Phase I 
C-231, Phase II 
C-331 
C-531 
C-534 
C-135 
Structures: 
S-160 
S-161 
S-162 
S-353 
Moss Bluff Lock and Spillway 
S-551 
Levees: 
L-212, Sec. 1 
L-212, Sec. 2 
L-112 
L-112 & Floodway 
S-155 
S-163 
S-159 Middle & Lower 
S-159 Upper 
Recreation: 
Morris Bridge & 
Flint Creek Sites 
Dead River Sites 
Jul 1968 - Mar 1970 
May 1971 - Jan 1973 
Jan 1973 - Jan 1974 
Oct 1972 - Jan 1975 
Dec 1972 - Jul 1975 
May 1967 - Dec 1968 
Jul 1966 - Aug 1967 
May 1968 - Sep 1972 
Jan 1971 - Dec 1973 
Dec 1972 - Apr 1975 
Feb 1975 - Aug 1977 
Apr 1976- Jan 1979 
Aug 1975 - May 1977 
Jul 1973 - Apr 1975 
Jul 1973 - Jan 1974 
Jul 1967 - Sep 1968 
Apr 1966 - Jan 1969 
Jun 1979 - Jul 1971 
Mar 1977 - Oct 1980 
May 1967 - Dec 1968 
Aug 1975 - May 1977 
Apr 1975 - Jun 1977 
Jul 1967 - Sep 1968 
Apr 1967 - Mar 1969 
Jul 1970 - Feb 1972 
Jun 1968 - Jul 1970 
Jul 1970 - Sep 1971 
Mar 1977 - Oct 1980 
May 1978 - Jul 1981 
May 1978 - Jul 1981 
May 1978 - Jul 1981 
Apr 1979 - Aug 1981 
Jun 1979 - Sep 1981 
Dec 1982 - Aug 1984 
Mar 1985 - Jul 1986 
Not transferred 
Do. 
Do. 
Do. 
Jul 1975 
Dec 1968 
Oct 1967 
Not transferred 
Not transferred 
Oct 1977 
Not transferred 
Not transferred 
Nov 1977 
Dec 1975 
Dec 1975 
Sep 1968 
Apr 1969 
Nov 1971 
Dec 1968 
Nov 1977 
Apr 1977 
Nov 1968 
Dec 1975 
Not transferred 
Dec 1975 
Dec 1975 
Oct 1980 
Jan 1983 
Jan 1983 
Jan 1983 
Oct 1981 
Jan 1985 
Dec 1986 
9-60

JACKSONVILLE, FL DISTRICT 
FOUR RIVER BASINS, FLORIDA PROJECT 
MOSS BLUFF LOCK 
(See Section 53 of Text) 
Nearest town 
Name of nearest town 
Distance above mouth of river 
Lock dimensions 
Normal lift 
Elevation of normal pool surface 
Depth of sills 
Character of foundation 
Kind of dam 
Type of construction 
Percent complete 
Estimated cost (including dam and spillway) 
20 miles 
Ocala, FL 
65.5 miles 
30 x 125 feet 
18.0 feet 
58 feet 
12 feet 
Piles in sand 
None 
Reinforced concrete 
100 
$1,990,138 
TABLE 9-V 'FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
PURSUANT TO SECTION 205, PUBLIC LAW 685, 
(PREAUTHORIZATION) 
(See Section 57 of Text) 
Study Identification Period Costs 
Detailed Project Report: 
Bradenton Beach, FL 
Curiosity Creek, Tampa, FL 
Cano Cacul, Aguadilla, PR 
Cano Madre Vieja, Aguadilla, PR 
Cedar Creek, Jacksonville, FL 
Cedar Hammock, Bradenton, FL 
Cyril E. King Road, St. Thomas, VI 
Estate Mon Bijou, St. Croix, VI 
Fortuna Bay, St. Thomas, VI 
Ft. Clinch State Park, Nassau County, FL 
LaGrange Gut,Frederiksted, St. Croix, VI 
Guanica, PR 
Linderberg Bay Area, St. Thomas, VI 
Long Branch, Jacksonville, FL 
Juan Mendez Channel, PR 
Moncrief Creek, Jacksonville, FL 
Naguabo River, PR 
Ponce Regional, PR 
Rio Anton Ruiz-Runta, Santiago, PR 
Rio Cibuco, Vega Baja, PR 
Rio Culebrinas, Aguada, PR 
Rio Descalabrada, Santa Isabel, PR 
Rio El Ojo De Agua, PR 
Rio Fajardo, PR 
Rio Guadiana, Naranjito, PR 
Rio Guamani, Guayama, PR 
Rio La Plata, Comerio, PR 
Rio Loco, Guanica, PR 
Rio Manati, PR 
Rio Manati, Barceloneta, PR 
Rio Niqua, Arroyo, PR 
Sabana Grande, PR 
Savan Gut, St. Thomas, VI 
Strawberry Hill, St. Croix, VI 
Turpentine Run, St. Thomas, VI 
TABLE 9-U 
3,105
0 
2,882 
621 
45,706 
44,327 
24,688 
54,011 
7,554 
395,323 
70,149 
39,562
0 
4,865 
1,173 
6,438 
11,867 
1,446 
110,236 
47,476 
45,776 
382 
59,927 
54,081 
245 
296 
125 
53,042 
158,124 
158,124
0 
13,422
0 
33,654 
8,752 
9-61

MOBILE, AL., DISTRICT* 
This district comprises a small portion of 
southeastern Tennessee, western Georgia, western 
Florida, all of Alabama south of Tennessee River 
Basin, eastern Mississippi, and a small portion of 
southeastern Louisiana embraced in drainage basins 
tributary to the Gulf of Mexico, west of Aucilla River 
Basin, to and including the Pascagoula River Basin. 
The Pear River Basin, Mississippi was included as 
part of the Mobile District until October 1, 1981, 
when responsibilities were transferred to Vicksburg 
District, Lower Mississippi Valley Division. A 
section of the Gulf Intracoastal Water from St. 
Marks, Florida, to Lake Borgne Light No. 29, 
Louisiana is also within Mobile District. 
IMPROVEMENTS 
Navigation Page 
1. Apalachicola Bay, FL ................................ 10-3 
2. Aquatic Plant Control 
(R & H Act of 1965) .................................... 10-3 
3. Bayou Coden, AL ....................................... 10-3 
4. Bayou La Batre, AL..................................... 10-4 
5. Biloxi Harbor, M S ...................................... 10-4 
6. Black Warrior and Tombigbee 
Rivers, AL ................................................... 10-5 
6A. Jackson Port, 
Vicinity of Jackson, AL .............................. 10-6 
6B. Oliver Lock and Dam 
(Replacement), AL....................................... 10-6 
7. Bon Secour River, AL.................................10-7 
8. Dauphin Island, AL...................................... 10-7 
9. Dog and Fowl Rivers, AL............................ 10-8 
10. East Pass Channel From Gulf of Mexico 
into Choctawhatchee Bay, FL ...................... 10-8 
11. Fly Creek, Fairhope, AL .............................. 10-9 
12. Gulf Intracoastal Waterway between 
Apalachee Bay, FL and 
M exican Border............................................ 10-9 
13. Gulfport Harbor, MS.................................. 10-10 
14. Mobile Harbor, AL ..................................... 10-10 
15. Panama City Harbor, FL ........................... 10-11 
16. Pascagoula Harbor, MS.............................. 10-12 
17. Pensacola Harbor, FL................................. 10-12 
18. Perdido Pass Channel, AL ........................ 10-13 
19. Tennessee-Tombigbee 
Waterway, AL and MS .............................. 10-13 
19A.Tennessee-Tombigbee 
Wildlife Mitigation, AL and MS................ 10-14 
20. Deauthorized Projects ................................ 10-15 
21. Other Authorized 
Navigation Projects .................................... 10-15 
22. Navigation Work Under 
Special Authorization................................. 10-15 
23. Reconnaissance and 
Condition Surveys...................................... 10-15 
Page 
Beach Erosion Control 
24. Beach Erosion Control Projects 
Under Special Authorization...................... 10-15 
25. Other Authorized Beach Erosion 
Control Project ........................................... 10-15 
Flood Control 
26. Boggy Bayou, 
Valparaiso, FL ............................................ 10-15 
27. County Line Road Bridge, 
Itawamba Co., M S .................................... 10-16 
28. Cribbs Mill Creek, 
Tuscaloosa, AL ......................................... 10-16 
29. Eslava Creek, Mobile, AL.......................... 10-16 
30. Fort Toulouse, 
W etumpka, AL........................................... 10-17 
31. Hurricane Creek, 
Prentiss Co., M S ........................................ 10-17 
32. Mill Creek, Dalton, GA.............................. 10-17 
33. Mill Creek, 
Sum rall, M S .............................................. 10-17 
34. Mound State Park, 
M oundville, AL.......................................... 10-18 
35. Murder Creek, Brewton, AL ...................... 10-18 
36. Okatibbee Lake, MS ................................. 10-18 
37. Portersville Bay-East, 
M obile Co., AL ......................................... 10-19 
38. Portersville Bay-West, 
M obile Co., AL .......................................... 10-19 
39. Proctor Creek 
A tlanta, GA ............................................... 10-19 
10-1

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Flood Control Page 
40. Raccoon Creek, Baconton, GA................ 10-20 
41. Silver Creek, 
Rom e, GA ............................................... 10-20 
42. Sowashee Creek, 
M eridian, M S..........................................10-20 
43. Tallahalla Creek, Laurel, MS ................... 10-21 
44. Threemile Creek, Mobile, AL.................. 10-21 
45. Tombigbee River 
(East Fork), MS & AL ............................. 10-21 
46. Tombigbee River and 
Tributaries, MS & AL.............................. 10-22 
47 Upper Gordon Creek, 
Hattiesburg, M S ...................................... 10-22 
48. Village Creek, 
Birmingham, AL......................................10-22 
49. Flood Control Work 
Under Special Authorization.................... 10-23 
50. Inspection of Completed 
Flood Control Projects ............................ 10-23 
51. Other Authorized 
Flood Control Projects ............................ 10-23 
Multiple Purpose Projects Including Power 
52. Alabama-Coosa Rivers, AL & GA ......... 10-24 
52A. Carters Dam and Reservoir, GA ............. 10-24 
52B. Claiborne Lock and Dam, AL.................. 10-25 
52C. Coosa River, Montgomery to 
Gadsden, AL ........................................... 10-25 
52D. Millers Ferry Lock and Dam, AL ........... 10-25 
Tables 
Table 10-A 
Table 10-B 
Table 10-C 
Table 10-D 
Table 10-E 
Table 10-G 
Table 10-H 
Table 10-J 
Cost & Financial Statement ......... 10-33 
Authorizing Legislation .............. 10-39 
Other Authorized 
Navigation Projects...................... 10-49 
Other Authorized Beach 
Control Erosion Control 
Project .......................................... 10-49 
Other Authorized Flood 
Control Projects............................ 10-50 
Deauthorized Projects.................. 10-50 
Navigation Work Under 
Special Authorization................... 10-51 
Flood Control Work Under 
Special Authorization................... 10-51 
Multiple Purpose Projects Includ. Power Page 
52E. Robert F. Henry Lock and Dam, AL........10-26 
53. Allatoona Dam 
Coosa River Basin, GA ........................... 10-26 
54. Apalachicola, Chattahoochee, and 
Flint Rivers, AL, FL & GA.....................10-27 
54A. Buford Dam, 
Lake Sidney Lanier, GA........................... 10-28 
54B. George W. Andrews Lock and 
Dam, AL & GA ....................................... 10-28 
54C. Jim Woodruff Lock and 
Dam, FL & GA.........................................10-29 
54D. Walter F. George Lock and 
Dam, AL & GA ....................................... 10-29 
54E. West Point Lake 
Chattahoochee River Basin, AL & GA .... 10-30 
55. Scheduling Flood Control 
Reservoir Operations................................ 10-30 
56. Deauthorized Projects...............................10-31 
Miscellaneous 
57. Flood Control and Coastal 
Emergencies (FC&CE)............................10-31 
58. National Emergency Preparedness 
Program (NEPP)......................................10-31 
59. Regulatory Functions Program.................10-31 
General Investigations 
60. Surveys....................................................10-31 
61. Collection and Study of Basic Data..........10-31 
62. Advance Engineering and Design ............ 10-31 
63. Continuation of Planning 
and Engineerin g ........................................ 10-32 
64. Rivers and Harbors 
Contributed Funds.................................... 10-32 
Table 10-K 
Table 10-L 
Table 10-M 
Table 10-N 
Table 10-0 
Table 10-P 
Reconnaissance and Condition 
Surveys ........................................ 10-52 
Alabama-Coosa Rivers, AL and GA 
Development Proposed Under 
Existing Project ........................... 10-52 
Apalachicola, Chattahoochee, and Flint 
Rivers, Al, GA, and FL, Locks and Dams 
and Multiple-Purpose Development 
Included In Existing Projects........ 10-53 
Black Warrior and Tombigbee 
Rivers, AL ................................... 10-54 
Tennessee-Tombigbee Waterway, 
AL and M S .................................. 10-55 
Completed Flood Insurance Studies 
And Flood Hazard Information Reports 
For FY 1982 Thru FY 1991......... 10-56 
10-2

MOBILE, ALABAMA, DISTRICT 
Navigation 
1. APALACHICOLA BAY, FL 
Location. The project is on the coast of northwest 
Florida 160 miles east of Pensacola Harbor. (See Coast 
and Geodetic Survey Chart 11401.) 
Previous project. For details, see page 1833, Annual 
Report for 1915, and page 689, Annual Report for 1938. 
Existing project. The existing project provides for: (a) 
A channel 10 feet deep and 100 feet wide from the 10-foot 
depth in Apalachicola Bay, across St. George Island, to 
within 300 feet of the gulf shore, thence increasing 
uniformly in width to 200 feet at the shore and continuing 
with that width to the 10-foot depth in the Gulf of Mexico, 
with twin jetties extending from the dune line to the outer 
end of the channel; (b) an inner bar channel, 10 feet deep 
and 100 feet wide, in Apalachicola Bay; (c) a boat basin 
200 feet by 880 feet and 9 feet deep at Apalachicola, 
Florida, with a connecting channel 9 feet deep and 80 feet 
wide through Scipio Creek to Apalachicola River; (d) a 
channel known as Link Channel, 10 feet deep and 150 feet 
wide, in Apalachicola Bay; (e) a channel generally parallel 
to the shore at Eastpoint, Florida, 6 feet deep, 100 feet 
wide, and about 6,000 feet long, and a connecting channel 
6 feet deep and 100 feet wide to water at the same depth in 
St. George Sound, with twin breakwaters on either side 
parallel to the shore and having a total length of 5,300 feet; 
(f) a channel 10 feet deep and 100 feet wide through 
Bulkhead Shoals, connecting Apalachicola Bay with St. 
George Sound; and (g) a 6-foot by 100-foot channel about 
one mile long, generally parallel to the shore at Two Mile, 
Florida, with a 6-foot by 100-foot connecting channel to 
water of the same depth in Apalachicola Bay. Mean range 
of tide throughout this harbor is 1.6 feet. Extreme range, 
except during storms, is about three feet. Plane of reference 
is mean low water. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. Requirements have been fully complied 
with. 
Terminal facilities. Facilities consist of pile-and-timber 
wharves which are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Condition surveys and other miscellaneous 
costs amounted to $34,558. 
Condition at end of fiscal year. The existing project, 
authorized by the 1954 River and Harbor Act, was completed 
in 1959, including reimbursement to local interests 
for approved work, as authorized by the 1958 River and 
Harbor Act. Improvements at Two Mile except for 
modifications authorized in 1975 were completed in September 
1964. Construction of the breakwater and channel 
improvements authorized in 1975 at Two Mile was completed 
in September 1977. Construction of breakwaters at 
Eastpoint authorized in 1983 was completed in March 
1984. Total Federal cost under existing project as of September 
30, 1992 is $2,033,461 for new work and 
$4,012,778 for maintenance, a total of $6,046,239. 
2. AQUATIC PLANT CONTROL (RIVER 
AND HARBOR ACT OF 1965) 
Location. Navigable water, tributary streams, connecting 
channels and other allied waters in Mobile District. 
Existing project. The existing project provides for 
management and control of water hyacinth, alligatorweed, 
Eurasian watermilfoil, hydrilla, and other obnoxious 
aquatic plant growths from navigable water, tributary 
streams, connecting channels, and other allied waters of 
the United States, in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife conservation, 
public health, and related purposes, including 
continued research for development of the most effective 
and economical control measures to be administered by 
the Chief of Engineers, under the direction of the 
Secretary of the Army, in cooperation with other Federal 
and State agencies. Research and planning cost prior to 
construction shall be borne fully by the United States. (See 
Table 10-B for authorizing legislation). 
Local cooperation. Local interests shall agree to hold 
and save the United States free from claims that may occur 
from control operations and to participate to the extent of 
50 percent of such operations. Requirements are being met 
in the state of Alabama by the Department of Conservation 
and Natural Resources. 
Operations and results during fiscal year. Water 
quality studies and overhead amounted to $5,877. 
Condition at end of fiscal year. Total Federal cost 
under the existing project as of September 30, 1992 is 
$727,588. Contributed funds for maintenance amount to 
$21,225. 
3. BAYOU CODEN, AL 
Location. The project is located in a small tidal stream 
on the southern coast of Mobile County, Alabama, emptying 
into Mississippi Sound about 7.6 miles northwest of 
Cedar Point, the southern tip of western mainland shore of 
Mobile Bay. (See Coast and Geodetic Survey Chart 
11376.) 
10-3

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Previous project. For details see Annual Report for 
1945, page 843. 
Existing project. The existing project provides for a 
channel 8 feet deep by 60 feet wide extending from La 
Belle Avenue bridge south for about 3,000 feet through 
the bayou to Portersville Bay, thence 8 feet deep by 100 
feet wide extending about 2.3 miles westward across 
Portersville Bay to connect with the Bayou La Batre channel, 
and a tumrning basin 8 feet deep by 60 feet wide by 100 
feet long on the west side of the bayou channel about 500 
feet south of the La Belle Avenue bridge. Mean tidal range 
is 1.75 feet, and extreme, except during storms, is 3.5 feet. 
Plane of reference is mean low water. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with fishing industry in 
this locality are adequate for existing commerce. A marina 
which will accommodate about 12 small recreational craft, 
and a slip with facilities for loading oyster shells are located 
near the mouth of the bayou, and are maintained by 
the Alabama Department of Conservation. 
Operations and results during fiscal year. 
Maintenance: Water Control Management cost $420. 
Condition at end of fiscal year. That portion of the 
project authorized prior to the 1969 modification was 
completed in 1956. Construction authorized in 1969 was 
initiated March 31, 1975 and completed March 26, 1976. 
Total Federal cost under existing project as of September 
30, 1992 is $330,701 for new work and $1,150,567 for 
maintenance, a total of $1,481,268. Contributed funds expended 
for new work amount to $100,000 and $50,000 for 
maintenance. 
4. BAYOU LA BATRE, AL 
Location. Bayou La Batre is a tidal stream about 10 
miles long, emptying into Mississippi Sound on the 
southern coast of Mobile County, Al., about 10 miles 
northwest of Cedar Point, the southemrn tip of the western 
mainland shore of Mobile Bay. (See Coast and Geodetic 
Survey Chart 11373.) 
Previous project. For details see Annual Report for 
1945, page 844. 
Existing project. The existing project provides for a 
12-foot by 100-foot channel from the 12-foot depth in 
Mississippi Sound to a point about 2,800 feet south of the 
highway bridge, thence a channel 12 feet deep by 75 feet 
wide to the bridge, an overall distance of about 33,500 
feet, with the channel widened at a point 0.6 mile below 
the bridge to provide a tuming basin 12 feet deep and 
about 2.6 acres in area. Authorized by the Water Resources 
Development Act of 1990, the plan of improvement is 
to deepen channel to 18-foot by 100-foot from the mouth 
through the tumrning basin, a distance of about 1.8 miles; 
deepen channel from turning basin to 0.29 miles above 
highway 188 bridge to 14-feet by 75-feet, a distance of 
about 0.89 miles; extend a 14-foot by 50-foot channel 
from tumrning basin into Snake Bayou for about 730 feet 
and a 12-foot by 50-foot channel within Snake Bayou 
about 790 feet; extend 18-foot by 120-foot channel in Mississippi 
Sound to connect with GIWW, then along GIWW 
alignment to connect with Pascagoula ship channel. This 
channel dimensions would be 18-feet by 120-feet for a 
distance of about 20 miles. Mean tidal range is 1.75 feet, 
and extreme, except during storms, is 3.75 feet. Plane of 
reference is mean low water. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Wooden wharves have been 
provided at seafood processing plants and public launching 
ramps are available. Several boatways for construction 
of small seagoing vessels are also available. Facilities are 
adequate for existing commerce. 
Operations and results during fiscal year. 
New work: Miscellaneous real estate activities cost 
$4,652; engineering and design cost $166,011; and supervision 
and administration amounted to $54,860. A total 
Federal cost of $225,523 for new work. 
Maintenance: Project Condition Surveys cost $10,024. 
Condition at end of fiscal year. The existing project 
was modified December 30, 1966 under the discretionary 
authority of the Chief of Engineers to include a turning 
basin. The project was completed in March 1967. The 
contract for deepening the Sound Channel is scheduled for 
award in March 1993. The plans and specifications for the 
Bayou Channel are scheduled for completion in March 
1993. Total Federal cost under existing project as of September 
30, 1992 is $536,618 for new work and $3,649,737 
for maintenance, a total of $4,186,355. Contributed funds 
from local interests for new work amount to $10,500. 
5. BILOXI HARBOR, MS 
Location. The project is located on Mississippi Sound 
in southeastemrn Mississippi, 32 miles by water west of Pascagoula 
Harbor, Mississippi, and 14 miles east of Gulfport 
Harbor, Mississippi (See Coast and Geodetic Survey Chart 
11373.) 
Previous project. For details see page 584, Annual 
Report for 1962. 
Existing project. The existing project provides for a 
continuous channel 12 feet deep, 150 feet wide and 23 
miles long from the Gulf Intracoastal Waterway through 
10-4

MOBILE, ALABAMA, DISTRICT 
Mississippi Sound east of Deer Island, Biloxi Bay, Back 
Bay, Cranes Neck, and a land cut to Gulfport Lake, including 
a 500-foot by 2,600-foot basin in the lake, thence a 12- 
foot deep by 100-foot wide channel for about two miles 
westward from the west end of the lake, terminating in a 
300-foot by 500-foot basin; a 12-foot by 100-foot channel 
from the main channel in Big Lake to and up Bayou Bernard 
to the Air Force oil terminal at about mile 2.6; a 12- 
foot by 150-foot spur channel from the main channel in 
Biloxi Bay for about one mile, terminating in a 400-foot 
by 600-foot turning basin opposite Ott Bayou; continuation 
of maintenance of the 12- by 150-foot lateral channel 
westward about 2.2 miles to Biloxi's south waterfront; a 
10-foot by 150-foot channel from Mississippi Sound, passing 
west of Deer Island to a point where it connects to the 
12-foot by 150-foot lateral channel at Biloxi's south 
waterfront. Construction for the modifications lateral 
channel authorized by River and Harbor Act of Nov. 7, 
1966 was commenced in FY 1974 and completed in Feb. 
1975. Further modifications to the project were authorized 
by the Chief of Engineers on March 28, 1979, which 
provided for a channel 10 feet deep, 100 feet wide and 300 
feet long extending northward from the Biloxi Lateral 
Channel, and into a rectangular basin, approximately 300 
by 370 feet, for use by commercial small craft, and an East 
Harrison County Canal project which provides for a 12- 
foot project depth, 130-feet wide and about 2,100 feet 
long, and a 300 by 300 foot turning basin also to a 12-foot 
project depth. This work was completed in April 1980. 
Cost of modification as authorized by the 1966 River 
and Harbor Act was $664,390. That portion of the project 
providing for an entrance channel 6 feet deep, 50 feet 
wide, and about 1,800 feet long into Old Fort Bayou, as 
authorized by the 1945 River and Harbor Act, is inactive. 
Estimated cost (1954) of this portion was $6,000. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of wooden piling-andtimber 
piers for small craft and fishing boats, a bulk 
gasoline terminal, several boat ways, and concrete 
products plant are available. 
Operations and results during fiscal year. 
Maintenance: Contract Dredging cost $727,600. Condition 
surveys cost $77,800. Water Quality Studies, and 
miscellaneous costs totaled $125,320. 
Condition at end of fiscal year. The existing project, 
prior to the modification authorized in 1966, was commenced 
in 1931 and completed in 1962. The 1966 
modification was completed in FY 1975. The 1979 
modification was completed in FY 1980. Total Federal 
cost under existing project as of September 30, 1992 is 
$1,431,919 for new work and $10,866,989 for maintenance, 
a total of $12,298,908. Contributed funds for new 
work amount to $102,600. Contributed funds for maintenance 
amount to $238,640. 
6. BLACK WARRIOR AND 
TOMBIGBEE RIVERS, AL 
Location. Black Warrior River rises in northern 
Alabama above Birmingham and flows generally southwesterly 
to unite with the Tombigbee River at Demopolis, 
Alabama. Thence the Tombigbee flows south, uniting with 
the Alabama River to form the Mobile River 45 miles 
above the head of Mobile Bay. Distance by water from 
Mobile to vicinity of Birmingham is about 430 miles. 
Previous project. For details see page 732, Annual 
Report for 1938. 
Existing project. The existing project provides for a 
channel 9 feet deep and 200 feet wide from the mouth of 
the Tombigbee River, 45 miles above Mobile, to the 
vicinity of Birmingham, via the Tombigbee and Black 
Warrior Rivers, to mile 430.4 on Sipsey Fork, mile 429.6 
on Mulberry Fork and mile 407.8 on Locust Fork, and for 
maintenance by snagging of Mobile River above the 
mouth of Chickasaw Creek, a total waterway distance of 
about 408 miles. The total lift of 255 feet is accomplished 
by six locks and dams. The original construction program, 
consisting of 17 dams and 18 lifts, was completed in 1915. 
Replacement of the original structures with new 110- by 
600-foot locks and dams, under the modernization program 
is as follows: William Bacon Oliver replaced locks 
10, 11, and 12; Armistead I. Selden replaced locks 8 and 9; 
Demopolis replaced locks 4, 5, 6, and 7; Coffeeville (Jackson) 
replaced locks 1, 2, and 3; and Holt replaced locks 13, 
14, 15, and 16. Thus, 16 of the original locks have been 
replaced by five new locks. Bankhead Lock and Dam 
(Lock 17) rehabilitation to replace the original double lift 
lock with a single lift lock was completed in 1980. The 
Coffeeville Lock and Dam wildlife refuge, authorized in 
1960, includes 4,250 acres within the reservoir area and 
along its boundaries. A replacement lock for the old Oliver 
Lock located 2,300 feet downstream is under construction. 
The replacement lock has dimensions of 110 feet by 600 
feet. A fixed crest spillway will extend 800 feet across the 
river. Minimum provision will be provided to allow construction 
of a hydropower plant. (See Table 10-B for 
authorizing legislation.) 
Tidal influence extends upstream from Mobile 101.6 
miles to the old lock 1, where tidal effect is apparent only 
at low stages of the river. At Mobile the mean and extreme 
tidal ranges are 1.5 and 3.6 feet, respectively. These are at 
times slightly increased by the effect of winds. The 
greatest fluctuation of river stages is at Demopolis, Ala., 
the maximum being 59.7 feet. Maximum fluctuations at 
other points are 40 feet at lock 1,100.6 miles from Mobile; 
57.8 feet at Tuscaloosa, 346.1 miles from Mobile; 13 feet 
10-5

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
at Birmingport, 404.9 miles from Mobile; and 27 feet at 
Cordova, 424.3 miles from Mobile. Ordinary fluctuations 
at these points are at old lock 1, 20 feet; at Demopolis, 35 
feet; at Tuscaloosa, 40 feet; at Birmingport, four feet; and 
at Cordova, seven feet. Works of improvement reduced 
the amount of fluctuations at different points by three to 
10 feet. 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Docks, storage facilities, and handling 
equipment have been provided as required at most 
loading and unloading points along the waterway. These 
include facilities for handling petroleum and petroleum 
products, coal, ores, sand and gravel, pulpwood, manufactures, 
and various other commodities. While most terminal 
facilities are privately owned, many are available for use 
by the general public. Facilities are considered adequate 
for existing commerce. (See Table 10-N for existing locks 
and dams.) 
Operations and results during fiscal year. 
Maintenance: Contract dredging of the river system cost 
$4,292,700. Condition surveys costs $499,000. Engineering 
and design cost $329,300. Supervision, administration 
and other general charges for the overall river project totaled 
$4,306,532. Natural Resources Management and 
Recreation cost $2,456,200. Recreation attendance CY 
1991 totaled 6,571,553 user days. 
Other O&M costs for the system include: Coffeeville 
Lock and Dam, $735,900; Demopolis Lock and Dam, 
$666,200; Selden Lock and Dam, $760,000; Oliver Lock 
and Dam, $594,900; Bankhead Lock and Dam, $805,200; 
Holt Lock and Dam, $783,700. 
Condition at end of fiscal year. Work on the project, 
commenced in 1887, was essentially completed in 1915. 
Since then three of the original locks and dams (10, 11 and 
12) were replaced by William Bacon Oliver (Tuscaloosa) 
Lock and Dam which was opened to navigation in August 
1939; four original lock and dams (4, 5, 6 and 7) were 
replaced by Demopolis Lock and Dam which was opened 
to navigation in August 1954; two original locks and dams 
(8 and 9) were replaced by Warrior Lock and Dam which 
was opened to navigation in October 1957; three original 
locks and dams (1, 2 and 3) were replaced by Coffeeville 
Lock and Dam which was opened to navigation in August 
1960; and four original locks and dams (13, 14, 15 and 16) 
were replaced by Holt Lock and Dam which was opened 
to navigation in June 1966. Rehabilitation of the spillway 
at John Hollis Bankhead Lock and Dam commenced in 
1966, and physically completed February 6, 1970. Replacement 
of the double lift lock with a single lift lock at 
John Hollis Bankhead Lock and Dam commenced in April 
1970 and was completed in 1980. The power plant at John 
Hollis Bankhead Lock and Dam and Holt Lock and Dam, 
was built and is operated by the Alabama Power Co. Construction 
of the new Oliver Lock and Dam is underway 
with the new lock open to traffic as of July 1991. Project 
construction began in November 1986 and is scheduled for 
completion in January 1993. Total Federal cost under existing 
project as of September 30, 1992 is $88,461,935 for 
new work and $267,417,909 for maintenance, and 
$52,292,880 for major rehabilitation, a total of 
$408,172,724. 
6A. JACKSON PORT, JACKSON, AL 
Location. The project is located on the Tombigbee 
River in Clarke County in southwest Alabama in the city 
of Jackson, Alabama, approximately 90 miles north of 
Mobile, Alabama. 
Existing project. None. The authorized Port would be 
located on the Black Warrior-Tombigbee River System, 
which is a federally authorized 9 by 300 feet navigation 
project connecting Birmingham, Alabama with the Port of 
Mobile. In conjunction with the realignment project on the 
existing navigation project, the district has been directed to 
construct a port at Jackson. 
Local cooperation. Local Cooperation Agreement requirements 
have not been determined. 
Operation and results during fiscal year. 
New work: Engineering and design $89,060; and supervision 
and administration $15,341. A total Federal cost of 
$104,401 for new work. 
Condition at end of fiscal year. Preparation of the 
Design Memorandum is currently underway and is 
scheduled to be approved in March 1993. Design (P&S) is 
scheduled for completion in October 1993. Total Federal 
cost under existing project to September 30, 1992 is 
$447,931. 
6B. OLIVER LOCK AND DAM 
(REPLACEMENT), AL 
Location. The project is located at mile 337.7 on the 
Black Warrior-Tombigbee River System at Tuscaloosa, 
Alabama. 
10-6

MOBILE, ALABAMA, DISTRICT 
Existing project. The existing navigation facilities on 
the Black Warrior and Tombigbee include six (6) locks 
having a total lift of 255 feet. Each of the locks have 
chamber dimensions of 110 by 600 feet. Original work on 
the waterway was authorized by the River and Harbor Act 
of 1884. The 17 original locks have been replaced by the 
existing six (6) locks . Prior to this year, Oliver Lock was 
the only lock in the system with chamber dimensions of 95 
by 460 feet. 
Authorized by the Water Resources Development Act 
of 1986, the plan of improvement was to replace Oliver 
Lock and Dam at a new location 2,300 feet downstream. 
The replacement lock with chamber dimensions of 110 by 
600 feet was opened to traffic in July 1991. The fixed crest 
spillway, which is still under construction, will extend 800 
feet across the river. Minimum provisions are being 
provided to allow construction of a hydropower plant. 
Land Acquisition is complete. Construction was initiated 
in November 1986 with the award of the Alabama Power 
Company relocation contract. The first stage cofferdam 
and river diversion contract was awarded in February 1987 
and the lock and dam construction contract was awarded 
in March 1988 with scheduled completion set for December 
1992. For other information see description of Black 
Warrior and Tombigbee Rivers project. 
Local cooperation. A local cooperation agreement is 
not required. One-half of the total cost of construction of 
the navigation lock and dam will be paid by amounts appropriated 
from the Inland Waterways Trust Fund. 
Operation and results during fiscal year. 
New work: Construction contracts $3,453,372; engineering 
and design $157,845; and $793,851 for supervision 
and administration and miscellaneous expenditures. 
A total Federal cost of $4,405,068 for new work. Contributed 
funds expended in FY 1992 totaled $4,393,130. 
Condition at end of fiscal year. The project is 97% 
complete and scheduled completion date for the entire 
project is January 1993, at an estimated cost of 
$120,000,000. Total Federal (Corps of Engineers) cost 
under existing project to September 30, 1992 is 
$55,738,759 for new work. Contributed funds (Inland 
Waterways Trust) expended total $57,073,773. 
7. BON SECOUR RIVER, AL 
Location. Rises 2 miles south of Foley, Ala., and flows 
southerly about 8 miles, emptying into Bon Secour Bay, 
an arm of Mobile Bay in southwest Alabama. 
Existing project. A 10- by 80-foot channel from Gulf 
Intracoastal Waterway through Bon Secour Bay to mouth 
of Bon Secour River and extending up river to vicinity of 
Swifts Landing, thence 6 by 80 feet up river to a point 
about 600 feet above Oak Landing with two turning and 
maneuvering areas 150 feet wide and 1,100 to 1,200 feet 
long opposite Swifts Landing and ice loading dock. Also a 
10 by 80 foot South Fork channel from the intersection 
with the Bon Secour channel, 1.14 miles to a 150 x 150 
foot turning basin. Plane of reference is mean low water. 
Overall length of improvement is about 4.7 miles. Mean 
tidal range is about 1.5 feet and extreme, except during 
storms, is 3.5 feet. Existing project was authorized by 
Chief of Engineers, May 16, 1963, under authority in Section 
107, River and Harbor Act of 1960. 
Local cooperation. Fully complied with. 
Terminal facilities. A number of pile-and-timber marginal 
wharves used by the seafood industry and a marine 
ways are located along the existing project. These, 
together with numerous privately owned piers, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
New work: Feasibility studies cost $15,255; supervision 
and administration cost $3,340. A total Federal cost of 
$18,595. 
Maintenance: Condition surveys cost $1,755. 
Condition at end of fiscal year. Project was commenced 
in July and completed in October 1964. Total 
Federal cost under existing project as of September 30, 
1992 is $137,210 for new work and $1,378,691 for maintenance, 
a total of $1,515,901. Contributed funds for new 
work amounted to $9,700. 
8. DAUPHIN ISLAND BAY, AL 
Location. The project is located between Dauphin and 
Little Dauphin Island on the west side of the entrance to 
Mobile Bay, about 30 miles south of Mobile, Alabama and 
55 miles west of Pensacola, Florida. (See Coast and 
Geodetic Survey Chart 11376.) 
Existing project. The existing project provides for: (a) 
A channel 7 feet deep and 150 feet wide from Mobile 
Bay to an anchorage basin of the same depth, and about 
7 acres in area, in the marsh just north of Fort Gaines 
on Dauphin Island; a channel 6 feet deep and 40 feet 
wide from the anchorage basin to Dauphin Island Bay; 
and a jetty and revetment to protect the entrance channel; 
and (b) an anchorage basin 7 feet deep and 500 feet 
square at Dauphin Island Village, with an entrance channel 
of like depth, 100 feet wide and about 8,300 feet long, 
extending to the 7 - foot hydrographic contour in Mississippi 
Sound. Mean tidal range is 1.1 feet, and extreme, 
10-7

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
except during storms is about 4 feet. Plane of reference 
is mean low water. (See Table 10-B for authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Several privately-owned wharves 
for handling seafood, a public dock and mooring slip, and 
a pier for recreational craft are located on the village basin. 
A marina, public launching ramp, and a number of private 
piers are located on the bay. Facilities are considered adequate 
for existing commerce. 
Operations and results during fiscal year. 
New work: Feasibility studies cost $18,278; supervision 
and administration cost $4,050. A total Federal cost of 
$22,328. 
Maintenance: Contract Dredging cost of $40,100. Condition 
surveys cost $3,279. 
Condition at end of fiscal year. The project was completed 
in July 1959. Total Federal cost under existing 
project as of September 30, 1992 is $292,864 for new 
work and $2,351,505 for maintenance, a total of 
$2,644,369. 
9. DOG AND FOWL RIVERS, AL 
Location. Dog and Fowl Rivers are primarily tidal 
streams emptying into the west side of Mobile Bay, 8.5 
and 17 miles, respectively, south of central Mobile (See 
Coast and Geodetic Survey Chart 11376.) 
Existing project. The Dog River project provides for a 
7 by 100-foot channel with a total length of 4.5 miles to 
provide access to the Mobile ship channel. 
The Fowl River project provides for a channel 8 feet 
deep and 100 feet wide from Mobile Bay into and up Fowl 
River to deep water about 6,700 feet above its mouth. 
Total length of the channel is about 2.6 miles. Plane of reference 
is mean low water. Mean range of tide is about 1.5 
feet in Dog River. Extreme range during storms is about 
3.6 feet. This segment of the project was completed in 
November 1973. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
boaTtyearrmdi nfoarl ffaabcriilcitaiteisn. g Estxeieslt invges sefla cihliutliless, ncionnes imst arionf asa, 
four marine ways, a yacht basin on Dog River; two 
marinas on Fowl River, and numerous timber piers and 
docks on both rivers. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: Water Control Management, $850. 
Condition at end of fiscal year. The existing Fowl 
River portion of the project was commenced in August 
1973 and completed in November 1973. Work on the Dog 
River channel realignment was initiated and completed 
during FY 1986. Total Federal cost on the existing project 
as of September 30, 1992 is $2,849,080; $391,354 for new 
work and $2,457,726 for maintenance. Contributed funds 
for new work amounted to $195,250. 
10. EAST PASS CHANNEL FROM 
GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL 
Location. East Pass Channel is located in the entrance 
from the Gulf into Choctawhatchee Bay at eastern end of 
Santa Rosa Island, 48 miles east of the entrance into Pensacola 
Bay and 49 miles west of the new entrance to St. 
Andrews Bay. (See Coast and Geodetic Survey Chart 
11388.) 
Previous project. For details see page 672 of Annual 
Report for 1937. 
Existing project. The existing project provides for a 
12-foot by 180-foot channel from the Gulf of Mexico into 
Choctawhatchee Bay, and a 6-foot by 10-foot channel 
from East Pass Channel into Old Pass Lagoon. The project 
consists also of two converging jetties spaced 1,000 feet 
apart at the seaward end. Mean range of tide is 1.3 feet; 
extreme range, except during storms, is 2.5 feet. Plane of 
reference is mean low water. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Responsibilities of local cooperation 
have been complied with to date. 
Terminal facilities. Small privately-owned pile-andtimber 
piers used in connection with the fishing industry in 
this locality are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Dredging cost amounted to $5,000. Condition 
surveys, supervision and administration and miscellaneous 
costs totaled $101,016. 
Condition at end of fiscal year. Construction of the 
1965 modification was commenced October 1967 and 
completed January 1969. Total Federal cost under existing 
project as of September 30, 1992 is $916,715 for new 
work and $8,470,020 for maintenance, a total of 
10-8

MOBILE, ALABAMA, DISTRICT 
$9,386,735. Contributed funds for new work from local interests 
amount to $398,000. 
11. FLY CREEK, AL 
Location. Fly Creek (Volanta Bayou) is a small stream 
about 4.5 miles long rising in Baldwin County, Alabama, 3 
miles east of town of Fairhope, from whence it flows northerly, 
thence westerly and southerly, to form an estuary 
on eastern shore of Mobile Bay just north of Fairhope and 
about 13 miles southeast of Mobile, Alabama. (See U.S. 
Coast and Geodetic Survey Chart No. 11376.) 
Existing project. Provides for a channel 6 feet deep, 80 
feet wide, and about 1,650 feet long from 6-foot depth in 
Mobile Bay to a turning basin of same depth, 100 feet 
wide and 350 feet long, in Fly Creek. Mean tidal range in 
vicinity of project is about 1.3 feet, and extreme, except 
during storms, is 3.5 feet. 
Existing project was authorized by the River and Harbor 
Act of May 17, 1950, (H. Doc. 194, 81st Cong., 1st 
Sess.). The project document contains the latest published 
map. 
Local cooperation. Fully complied with. 
Terminal facilities. Fairhope Yacht Club has facilities 
for small recreational craft on the south bank near mouth 
of creek, consisting of a pile-and-timber service wharves, 
several sheet metal boat sheds, boat slips, and other mooring 
facilities. There is also a commercial marina on north 
bank of creek. 
Operations and results during fiscal year. 
Maintenance: None. 
Condition at end of fiscal year. Project was commenced 
in August and completed in October, 1957. Total 
project costs as of September 30, 1992 amounted to 
$588,907 of which $29,000 was for new work and 
$559,907 for maintenance. 
12. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FL 
AND MEXICAN BORDER 
(MOBILE DISTRICT) 
Location. The project extends westward from 
Apalachee Bay, Florida, along the Gulf coast to the 
Rigolets, Louisiana, via a series of coastal lakes, bays, 
sounds, and land cuts. (For further details see Annual 
Report for 1962.) 
Previous project. For details see page 906, Annual 
Report for 1930. 
Existing project. The existing project provides for a 
waterway 12 feet deep and 125 feet wide at mean low 
water from Apalachee Bay, Florida, to Mobile Bay, 
Alabama, and 12 feet deep and 150 feet wide from Mobile 
Bay, Alabama to Rigolets, Louisiana (Lake Borgne Light 
No. 29), and for a tributary channel (Gulf County Canal), 
12 feet deep, 125 feet wide and about six miles long connecting 
Intracoastal Waterway at White City, Florida, with 
St. Joseph Bay. The waterway between the 12-foot depth 
contours in Apalachee Bay and Lake Borgne Light No. 29 
at the Rigolets is 379 miles long. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. None. 
Terminal facilities. Facilities are available for public 
use at Carrabelle, Apalachicola, Panama City, and Pensacola, 
Florida; Mobile and Bayou LaBatre, Alabama; and 
Pascagoula, Biloxi, Gulfport, Pass Christain, and Bay St. 
Louis, Mississippi. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Maintenance: 
Carrabelle-Apalachicola Bay section: Dredging 
navigation channel maintenance cost $2,400. Condition 
surveys, water quality studies, supervision and administration 
totaled $37,300. 
Apalachicola Bay - St. Andrew Bay section: Dredging 
navigation channel maintenance cost $18,900. Condition 
surveys, supervision and administration and 
miscellaneous cost totaled $34,700. 
St. Andrew Bay - Choctawhatchee Bay section: Condition 
surveys and dredging studies cost $336,300. Dredging 
navigation channel maintenance cost $67,300. Water 
quality studies, supervision and administration and miscellaneous 
totaled $479,500. 
Choctawhatchee Bay - Pensacola Bay section: Condition 
surveys, dredging studies, and bank stabiliziation cost 
$39,800. 
Pensacola Bay - Mobile Bay section: Dredging Contracts 
$1,700. Condition surveys, dredging studies, supervision 
and administration and miscellaneous totaled 
$125,200. 
10-9

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Mobile Bay - Rigolets section: Condition surveys and 
miscellaneous cost totaled $82,700. 
Condition surveys, water quality studies, real estate activities, 
and miscellaneous cost pertaining to the waterway 
in general not site specific totaled $769,062. 
Condition at end of fiscal year. The existing project is 
complete except for the portion between Apalachicola Bay 
and St. Marks, Flonrida, which has been deauthorized. 
Modification of the Gulf County Canal to provide a 12- 
foot by 125-foot channel was commenced July 1968 and 
completed June 1969. Total cost of the existing project to 
September 30, 1992 is $69,700,828, of which $6,480,299 
was for new work and $63,220,529 for maintenance. 
13. GULFPORT HARBOR, MS 
Location. The project is located on Mississippi Sound 
in southeastern Mississippi, about 35 miles west of Pascagoula, 
Mississippi, and 60 miles east of New Orleans. 
(See Coast and Geodetic Survey Chart 11373.) 
Previous project. For details see page 747, Annual 
Report for 1938, and page 995, Annual Report for 1948. 
Existing project. The existing project provides for: (a) 
A channel 32 feet deep, 300 feet wide, and about eight 
miles long across Ship Island Bar, a channel 30 feet deep, 
220 feet wide, and about 11 miles long through Mississippi 
Sound, and an anchorage basin at Gulfport 30 feet deep, 
1,320 feet wide, and 2,640 feet long; and (b) maintenance 
of the existing commercial smallboat harbor about 26 
acres in area, and a straight-approach channel, 100 feet 
wide and about 4,300 feet long, from deep water in Mississippi 
Sound to a smallboat basin, all at a depth of 8 feet. 
Under ordinary conditions mean tidal range is about 1.75 
feet, and extreme range, except during storms, is about 3.5 
feet. Plane of reference is mean low water. The project is 
authorized in the Water Resources Development Act 
(WRDA) 1986, and further amended by WRDA 1988 to 
modify the existing ship channel to 36 by 300 feet in Mississippi 
Sound, and 38 by 400 feet across the bar, with 
changes in the channel alignment and the turning basin for 
safe and unrestricted navigation. The FY 91 construction 
appropriation provided for constructing an increment of 
the authorized project and provide a 36 by 220 feet channel 
in Mississippi Sound and 38 by 300 feet across the bar. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Conditions of local cooperation 
have been fully complied with to date. 
Terminal facilities. Existing modem rail-connected 
terminal facilities at this port are considered adequate for 
existing commerce. (See Port Series 19, revised in 1979.) 
Operations and results during fiscal year. 
New work: Thin-layer contract administration cost 
$9,911,468; Engineering and design cost $119,066; and 
supervision and administration cost $261,132. A total 
Federal cost of $10,291,666. 
Maintenance: Contract dredging at a cost of 
$2,340,800. Condition surveys, supervision and administration 
and miscellaneous costs amounted to 
$460,708. 
Condition at end of fiscal year. The main harbor was 
commenced 1932 and completed April 1950. Maintenance 
for small boat harbor and approach channel, constructed 
by local interests in 1950, was authorized by 1958 River 
and Harbor Act. Awarded thin-layer monitoring contract 
in June 1991 under the authority of WRDA 1986 and 
1988. The channel contract was awarded in April 1992, 
thin-layer monitoring program is continuing. Total Federal 
cost under existing project as of September 30, 1992 is 
$11,328,790 for new work and $42,255,295 for maintenance, 
a total of $53,584,085. Contributed funds for new 
work amounted to $4,069,717. 
14. MOBILE HARBOR, AL 
Location. The project is located along the lower 5 
miles of Mobile River, and channel extends thru Mobile 
Bay and into Gulf of Mexico,in southwestern Alabama, 91 
miles by water west of Pensacola Harbor, Florida, 90 
miles east of Gulfport Harbor, Mississippi, and 144 miles 
by water northeast of mouth of Mississippi River. (See 
Coast and Geodetic Survey Chart 11376.) 
Previous project. For details see page 503, Annual 
Report for 1963. 
Existing project. The existing project provides for: (a) 
A 47-foot by 600-foot channel about 1.5 miles long across 
Mobile Bar, (b) a 45-foot by 400-foot channel in Mobile 
Bay to mouth of Mobile River, (c) a 40-foot channel in 
Mobile River to highway bridge, varying from 500 to 775 
feet wide; (d) a 25-foot channel from highway bridge to 
and up Chickasaw Creek to a point 400 feet south of 
mouth of Shell Bayou, widths being 500 feet in Mobile 
River and 250 feet in Chickasaw Creek; (e) a turning basin 
40 feet deep, 2,500 feet long, and 800 to 1,000 feet wide, 
opposite Alabama State Docks; (f) a turning basin 40 feet 
deep, 1,000 feet wide, and 1,600 feet long opposite 
Magazine Point; (g) a 27-foot by 150-foot channel from 
Mobile Bay Channel along Arlington pier to a turning 
basin 800 feet long and 600 feet wide opposite Brookley 
Complex ocean terminal, and continuing thence a turning 
basin 250 feet wide and 800 feet long in Garrows Bend, 
10-10

MOBILE, ALABAMA, DISTRICT 
thence a 22-foot by 150-foot channel to the causeway linking 
McDuffie Island to the mainland; (h) a channel serving 
the Theodore Industrial Park 40 feet deep and 400 feet 
wide from the main ship channel in Mobile Bay and extending 
northwesterly for about 5.3 miles to the shore of 
Mobile Bay, including an anchorage basin near the 
shoreline, thence a land cut 40 feet deep, 300 feet wide 
and 1.9 miles long to and including a 42 acre trapezoid 
turning basin 40 feet deep, and a barge channel 12-by 100- 
feet, extending 6,500 feet and terminating in a 300-by 300- 
foot tumrning basin; and (i) maintenance of Three Mile 
Creek by snagging, from its intersection with Industrial 
Canal to Mobile River. The project provides also for an 
anchorage area 32 feet deep, 100 feet wide, and 2,000 feet 
long opposite site formerly occupied by the U.S. Quarantine 
Station at McDuffie (Sand) Island. Prior to widening 
the Mobile Bay Channel as authorized in 1954, the 
Quarantine Station anchorage area was maintained to a 
project width of 200 feet. Construction by local interests of 
a solid-fill causeway across Garrows Bend Channel between 
McDuffie Island and the mainland is also provided 
for under existing project. Total length of the bay and river 
channels is about 41.7 miles. Plane of reference is mean 
low water. Under ordinary conditions mean tidal range at 
the lower end of the improvement is 1.2 feet and at the 
upper end 1.5 feet. Extreme tidal range is 3.4 feet at the 
lower end and 3.6 feet at the upper end. 
Further authorization provides for future development 
to deepen and widen entrance channel over the bar to 57 
feet by 700 feet about 7.4 miles long, deepen and widen 
bay channel to 55 feet by 550 feet about 27.0 miles long, 
deepen and widen an additional 3.6 miles of bay channel 
to 55 feet by 650 feet and provide 55 foot deep anchorage 
area and turning basin in vicinity of Little Sand Island. All 
dredged material will be placed in an approved disposal 
area in the Gulf of Mexico. (See Table 10-B for authorizing 
legislation.) 
Local cooperation. A local cooperation agreement was 
signed by the local sponsor to construct the project for the 
first increment of work. 
Terminal facilities. Modern rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 18, revised in 1979.) 
Operations and results during fiscal year. 
New work: Construction contract cost $544,803, engineering 
and design $63,893, and supervision and administration 
cost $20,914. A total Federal cost of 
$629,610. 
Maintenance: Contract dredging at a cost of 
$16,904,900. Condition surveys cost $321,900. Water 
quality studies, engineering and design and supervision 
and administration cost $3,198,495. 
Condition at end of fiscal year. Phase I of the project 
modification was completed in June 1990. A draft supplement 
to the GDM for construction of a turning basin has 
been reviewed and comments received are being incorporated. 
Current estimated Federal cost is $218,548,000, 
and non-Federal cost is $178,452,000. Total Federal cost 
under existing project as of September 30, 1992 is 
$96,077,200 for new work and $153,332,950 for maintenance, 
a total of $249,410,150. Contributed funds expended 
amounted to $18,170,860 for new work. 
15. PANAMA CITY HARBOR, FL 
Location. The project is located on the northwest coast 
of Florida, 102 miles east of entrance to Pensacola Harbor. 
(See Coast and Geodetic Survey Chart 11389.) 
Previous project. For details see page 710, Annual 
Report for 1938. 
Existing project. The existing project provides for a 
channel about 3.5 miles long, extending from deep water 
in St. Andrew Bay through barrier peninsula, known as 
Lands End, to the Gulf of Mexico, 300 feet wide and 32 
feet deep in the bay through Lands End; and 450 feet wide 
and 34 feet deep in the gulf, protected by east, west jetties, 
extending 2,075 feet and 2,896 feet respectively; a channel 
100 feet wide and 8 feet deep in Grand Lagoon to a point 
about 2,400 feet east of State Highway 392 Bridge, with 
branches to serve terminal facilities; and the maintenance 
of a channel in Watson Bayou, an arm of St. Andrew Bay, 
100 feet wide and 10 feet deep from that depth in bay to 
highway bridge. 
Authorized modifications includes branch channels 38 
feet deep and 300 feet wide, leading from the inner end of 
the main entrance channel westward to the Port Authority 
terminal at Dyers Point and eastward to the Bay Harbor 
terminal, about 3.4 and 3.6 miles in length, respectively; 
turning and maneuvering areas comprising about 55 acres 
opposite Dyers Point, and 42 acres opposite Bay Harbor, 
both at a depth of 38 feet; and an anchoring and loading 
basin for LASH type intermodal carriers, 40 feet deep and 
containing about 177 acres in St. Andrew Bay near the 
inner end of the main entrance channel. Mean tidal range 
is about normally 1.3 feet and 3.0 feet extreme. (See Table 
10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
10-11

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Terminal facilities. Available terminal facilities are 
considered adequate for existing commerce. (See Port 
Series No. 19.) 
Operations and results during fiscal year. Maintenance: 
Condition surveys cost $39,100. Engineering and 
design, water quality studies, and miscellaneous costs totaled 
$58,785. 
Condition at end of fiscal year. The existing project 
(prior to modifications) was completed in November 1949. 
Repairs to jetties were commenced in June 1961 and completed 
October 1968. Modifications to the project at Grand 
Lagoon were completed in January 1972. Total Federal 
cost under existing project as of September 30, 1992 is 
$1,638,045 for new work and $9,066,114 for maintenance, 
a total of $10,704,159. Contributed funds expended for 
new work amount to $80,000. 
16. PASCAGOULA HARBOR, MS 
Location. The project is located along lower 6.8 miles 
of Pascagoula River, the lower six miles of Dog River, and 
in Bayou Casotte (about four miles east of the mouth of 
Pascagoula River), and through Mississippi Sound into the 
Gulf of Mexico, in southeastern Mississippi, about 38 
miles west of Mobile, Alabama, and about 100 miles east 
of New Orleans, Louisiana. (See Coast and Geodetic Survey 
Chart 11373.) 
Previous project. For details see page 741, Annual 
Report for 1938. 
Existing project. The existing project provides for (a) 
An entrance channel 40 feet deep and 350 feet wide from 
the Gulf of Mexico through Horn Island Pass, including an 
impounding area for littoral drift, 40 feet deep, 200 feet 
wide, and about 1,500 feet long adjacent to the channel at 
the west end of Petit Bois Island; (b) a channel 38 feet 
deep and 350 feet wide in Mississippi Sound and Pascagoula 
River to the railroad bridge at Pascagoula, including 
a turning basin 2,000 feet long and 950 feet wide 
(including channel area) on the west side of the river 
below the railroad bridge; (c) a channel 38 feet deep and 
225 feet wide from the ship channel in Mississippi Sound 
to the mouth of Bayou Casotte, thence 38 feet deep and 
300 feet wide for about one mile to a tumrning basin 38 feet 
deep, 1,000 feet wide, and 1,750 feet long; (d) a 22-foot 
deep by 150-foot wide channel up Pascagoula River from 
the railroad bridge to the mouth of Escatawpa (or Dog) 
River, then up Escatawpa River to Highway 613 (formerly 
63) bridge; (e) a 12-foot by 125-foot channel from the 
highway bridge, via Robertson and Bounds Lakes, to mile 
6 on Escatawpa River, and (f) a 12-foot by 80-foot channel 
extending from deep water in the Pascagoula River 
(about one-half mile north of the railroad bridge) to a turning 
basin in Krebs Lake a distance of about 1,500 feet, 
then along the south bank of the lake a channel 10-foot by 
60-foot and terminating at a second turning basin, a distance 
of 2,700 feet from the first. Under ordinary conditions 
mean tidal range is 1.75 feet, and extreme range is 
3.75 feet. Plane of reference is mean low water. 
Further authorization provides for deepening and 
widening gulf entrance channel to 44 by 550 feet; widen 
Hom Island channel to 600 feet, relocating that channel 
about 500 feet westwardly; deepen Mississippi Sound portion 
to 42 feet; widen and deepen Bayou Casotte to 42 by 
350 feet and construct tumrning basin. Disposal of all new 
work material in Gulf of Mexico. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modem rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce. (See Port Series No. 19.) 
Operations and results during fiscal year. Maintenance: 
Contract dredging at a cost of $2,615,300. Condition 
surveys cost $21,700. Water quality studies, 
supervision and administration, and miscellaneous costs 
totaled $515,528. 
Condition at end of fiscal year. The existing project 
was completed in August 1965 and the Krebs Lake project 
was completed in November 1983. The General Design 
Memorandum (GDM) was approved in June 1992 for 
deepening and widening channels. Precor.struction Engineering 
and Design was completed September 1992. 
Total Federal cost of existing project to September 30, 
1992 is $6,572,985 for new work and $50,336,544 for 
maintenance, a total of $56,909,529. Contributed funds expended 
for maintenance amounted to $3,788,266. 
17. PENSACOLA HARBOR, FL 
Location. The project is located in a landlocked bay on 
the coast of northwest Florida about 50 miles east of the 
entrance to Mobile Bay. (See Coast and Geodetic Survey 
Charts 490 and 11382.) 
Previous project. For details see Annual Report for 
1938. 
Existing project. The existing project provides for: (a) 
A 35-foot by 500-foot entrance channel about five miles 
long, from the Gulf of Mexico to lower Pensacola Bay; (b) 
10-12

MOBILE, ALABAMA, DISTRICT 
a 33-foot by 300-foot bay channel; (c) two 33-foot by 300- 
foot parallel approach channels to opposite ends of the 
inner harbor channel; (d) an inner harbor channel 500 feet 
wide, 33 feet deep, and 3,950 feet long; (e) a 30-foot by 
250-foot approach channel to the pierhead line south of 
Muscogee wharf; and (f) a 15-foot by 100-foot entrance 
channel into Bayou Chico, thence a channel 14 feet deep, 
75 feet wide, and about 4,400 feet long to a turning basin 
14 feet deep and 500 feet square. Mean range of tide 
throughout the harbor is about 1.1 feet near the entrance 
and about 1.6 feet at the head of bay. Extreme tidal range, 
except during storms, is about three feet. Plane of reference 
is mean low water. Modification of the Bayou Chico 
project to provide for enlarging the entrance channel to 21 
by 100 feet, the bayou channel to 20 feet by 100 feet, and 
deepening the turning basin to 20 feet has been deferred 
for restudy. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Modemrn rail-connected terminal 
facilities at this port are considered adequate for existing 
commerce (See Port Series No. 19, revised in 1979.) 
Operations and results during fiscal year. 
Maintenance: Condition surveys and dredging studies 
cost $65,200. Miscellaneous costs totaled $7,039. 
Condition at end of fiscal year. New work is completed 
except for features which are deferred for restudy. 
The modification authorized in 1962 was commenced in 
March and completed in May 1965. Total Federal cost of 
the existing project to September 30, 1992 is $1,469,693 
for new work and $8,300,456 for maintenance, a total of 
$9,770,149. Contributed funds for maintenance amount to 
$297,587. 
18. PERDIDO PASS CHANNEL, AL 
Location. The project is located about midway between 
Pensacola, Florida and Mobile, Alabama. (See Coast and 
Geodetic Chart 11378.) 
Existing project. The existing project provides for a 
channel 12 feet deep and 150 feet wide for about 1,300 
feet from the Gulf of Mexico into the inlet, thence 9 feet 
deep and 100 feet wide for about 2,200 feet to the highway 
bridge, where the channel branches into two arms, each 
having dimensions of 9 by 100 feet, one of which extends 
about 3,400 feet into Terry Cove and the other about 3,200 
feet into the southem arm of Perdido Bay. The project 
also provides for two jetties spaced 600 feet apart at the 
seaward end. The east jetty has a low weir section, 1,000 
feet long to permit passage of littoral drift into a dredged 
deposition basin 800 feet by 1,200 feet located between 
the east jetty and the navigation channel. Mean tidal range 
is 1.1 feet and extreme is 2.8 feet. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Requirements of local cooperation 
have been fully complied with to date. 
Terminal facilities. Six marinas, numerous timber 
piers, docks, and several launching ramps are available. 
These facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Dredge Contract cost at $891,400. Condition 
surveys and miscellaneous costs totaled $97,599. 
Condition at end of fiscal year. The existing project 
was commenced in May 1968 and completed in March 
1969. Total Federal cost of the existing project to September 
30, 1992 is $629,860 for new work and $7,788,997 for 
maintenance, a total of $8,418,857. Contributions from 
local interest amount to $510,000 for new work and 
$10,325 for maintenance. 
19. TENNESSEE-TOMBGIBEE 
WATERWAY, AL AND MS 
Location. The waterway extends from mile 215 in 
Pickwick pool on the Tennessee River, southerly through 
northeastern Mississippi and western Alabama, a total of 
234 miles, to the confluence of the Black Warrior and 
Tombigbee Rivers at Demopolis, Alabama. 
Previous project. For details see Annual Report for 
1953. 
Existing project. The existing project provides for a 
waterway 234 miles long, connecting the Tennessee and 
Tombigbee Rivers via the East Fork of Tombigbee River 
and Mackeys and Yellow Creeks and consists of three sections 
as follows: (1) the river section, a 9-foot by 300-foot 
channel for 149 miles between Demopolis and Amory, 
Mississippi; (2) the canal section, 12 feet by 300 feet for 
46 miles from Amory to Bay Springs; and (3) the divide 
section, a 12-foot by 300-foot channel (except in the 27 
mile long divide cut in which the bottom width is 280 feet) 
for 39 miles from Bay Springs through the dividing ridge 
to the Tennessee River. The total lift of 341 feet is accomplished 
by 10 locks. (See Table 10-B for authorizing 
legislation.) 
10-13

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Local cooperation. Local interests have made and are 
maintaining alterations in highways and highway bridges 
and in sewer, water-supply, and drainage facilities and 
provide and maintain suitable and adequate river and canal 
terminals. Officials of the State of Mississippi were 
notified of these requirements on December 13, 1949, and 
officials of the State of Alabama were notified on December 
20, 1949. Legislation enabling boards of supervisors of 
the various counties concerned to enter into agreements 
with the United States relative to navigation projects was 
adopted by the State of Mississippi in 1950. A compact 
between the States of Alabama, Mississippi, Tennessee, 
Kentucky and Florida has been formed for the purpose of 
promoting the project. The name of this organization is the 
Tennessee-Tombigbee Waterway Development Authority. 
During its 1962 session the Mississippi Legislature 
authorized the formation of the Tombigbee River Valley 
Water Management District. The District was organized in 
accordance with the enabling legislation and is empowered 
to fulfill the requirements of local cooperation for 
the portion of the project in Mississippi. A satisfactory 
resolution has been furnished. During its 1967 session the 
Alabama Legislature authorized the formation of a public 
corporation to be named the Tombigbee Valley Development 
Authority for the purpose of further development of 
the Tombigbee River and tributary streams. The organization 
was formed in accordance with the enabling legislation 
and in a referendum held December 5, 1967 the voters 
of Alabama authorized a bond issue not to exceed 
$10,000,000 to finance participation in this project and the 
Tombigbee River and Tributaries project. A satisfactory 
resolution has been furnished. 
Terminal facilities. Docks, storage facilities and handling 
equipment are still being developed along this new 
waterway. As of September 30, 1992, twelve such 
facilities were operational, while five were under construction, 
and five more are planned. The operational facilities 
are handling grain, wood chips, and logs. When all 
facilities are complete, about half will be publicly owned 
and operated. Additional ports and terminals must be completed 
before the waterway can achieve its full potential. 
(See Table 10-N for existing locks and dams.) 
Operations and results during fiscal year. 
New work: Project construction cost $3,321,034; 
relocations cost $41,714; recreation facilities $7,814,806; 
real estate $175,558; engineering and design cost 
$395,842 and supervision and administration cost 
$1,227,708, a total of $12,976,662 for new work. 
Maintenance: Contract dredging on the river system 
cost $5,511,600. Total cost for operation and maintenance 
of the project for FY 92 amounted to $21,229,316, which 
included general charges of $6,649,516; Gainesville Lock 
and Dam, $377,600; Tom Bevill Lock and Dam, 
$531,200; Columbus Lock and Dam, $414,700; Aberdeen 
Lock and Dam, $384,100; Lock A, $371,700; Lock B, 
$417,700; Lock C, $360,800; Lock D, $375,700; Lock E, 
$413,300; Bay Springs Lock and Dam, $364,700. Recreation 
costs totaled $5,056,700. Recreation attendance for 
FY 1992 totaled 6,096,944 user days. 
Condition at end of fiscal year. Total Federal cost 
under the existing project as of September 30, 1992 is 
$1,030,087,228 for new work, and $160,724,566 for maintenance 
for a total of $1,190,811,794. Construction formally 
began December 12, 1972 and overall project is 
essentially complete. There are currently 8 contracts underway 
on the project: 6 recreational, 1 relocation, and 1 
contract for grouting water wells. The waterway was 
opened for navigation in January 1985. 
19A. TENNESSEE-TOMBIGBEE 
WATERWAY WILDLIFE MITIGATION 
PROJECT, AL AND MS 
Location. This project is in Alabama and Mississippi at 
the following locations: 
(1) Existing Project Lands - Approximately 72,500 
acres of Tennessee-Tombigbee Project Lands have been 
designated for mitigation purposes. An additional 20,100 
acres have also been designated at Coffeeville Lake, 
Demopolis Lake, Claiborne Lake and Dannelly Reservoirs 
in Alabama and at Okatibbee Lake in Mississippi. 
(2) Separable Lands - Acquisition and management of 
88,000 separable lands in the Mobile-Tensaw Delta, 
Alabama (not less than 20,000 acres); the Pascagoula, 
Pearl, and Mississippi Delta Basins in Mississippi (not less 
than 25,000 acres); and the balance at any location in the 
two states. 
Previous project. None. This project was a new construction 
start in Fiscal year 1990. It was authorized by 
Section 601 of the Water Resources Development Act of 
1986. 
Existing project. The authorized project calls for the 
acquisition of separable lands at the above named locations. 
The Alabama Department of Conservation and 
Natural Resources, Mississippi Department of Wildlife 
Fisheries and Parks, and the U.S. Fish and Wildlife Service 
(FWS) will assist in the selection of separable lands. 
10-14

MOBILE, ALABAMA, DISTRICT 
The selected lands will be purchased from willing sellers 
at fair market value. Emphasis will be placed on forested 
wetlands, with a minimum of 34,000 acres of bottomland 
hardwoods being purchased. 
The separable lands and the existing project lands 
designated for mitigation purposes will be managed for 
wildlife. The States will be primarily responsible for 
managing these lands in accordance with a management 
plan jointly developed by the States, Corps and the FWS. 
However, due to operational constraints it will be necessary 
for the Corps to retain management responsibility for 
some of the existing project lands included in the mitigation 
program. 
Local cooperation. A local cooperation agreement is 
not required since the cost of this project is a 100% 
Federal responsibility. 
Operation and results during fiscal year. Land acquisition 
cost $19,761,880. Engineering and Design 
$574,127. Supervision and administration, $893,309. 
Condition at end of fiscal year. Initial funding for the 
project was received in January 1990. At the end of September 
1992, 20,209 acres had been acquired in the 
Mobile-Tensaw Delta; 28,435 acres in the Pascagoula 
River Basin, and 92 acres along the Tennessee-Tombigbee 
Waterway in northeast Mississippi. Evaluation of tracts 
offered for consideration in the Mississippi Delta, Pearl 
River Basin, and other areas in Alabama and Mississippi 
are completed. A variety of activities were also undertaken 
to begin managing the 92,600 acres of existing 
project lands included in the Mitigation Program. 
Scheduled completion date is September 1996. The total 
project cost is estimated to be $84,600,000. Total Federal 
cost of the existing project to September 30, 1992 is 
$34,913,892. 
20. DEAUTHORIZED PROJECTS 
(See Table 10-G.) 
21. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
(See Table 10-C.) 
22. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645, as amended (Preauthorization). Studies conducted 
under this authority amounted to $151,537 in FY 
1989. (See Table 10-H.) 
23. RECONNAISSANCE AND 
CONDITION SURVEYS 
(See Table 10-K.) 
Beach Erosion Control 
24. BEACH EROSION CONTROL 
PROJECTS UNDER 
SPECIAL AUTHORIZATION 
Studies conducted under Section 103, 1962 River and 
Harbor Act, as amended, amounted to $243 in FY 1989. 
(See Table 10-I.) 
25. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECT 
(See Table 10-D.) 
Flood Control 
26. BOGGY BAYOU, 
VALPARAISO, FL 
Location. The project is located in the city of Valparaiso, 
Florida in Okaloosa County on the west bank of 
Boggy Bayou which indents the north shore of Choctawhatchee; 
about 10 miles northeast of Fort Walton 
Beach. 
Existing project. The project provides for shoreline 
bank protection along 700-feet of shoreline of Boggy 
Bayou and precludes possible destruction of Bayshore 
Drive and utilities. The protective works consist of a stone 
dike having a crest elevation of 3.0 feet NGVD and a 15- 
foot wide base between +1 and -1 foot NGVD. An 18-inch 
thick layer of riprap was placed from the top of the dike to 
elevations 6.0 feet NGVD. The riprap was placed on 6-inches 
of bedding material and filter cloth. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Construction contract $2,226; Engineering 
and design cost $428. Supervision and administration cost 
$72. 
10-15

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Condition at end of fiscal year. Plans and specifications 
were completed in FY 1990. The project was completed 
in July 1991. Estimated Federal cost is $156,300; 
and the non-Federal portion is $52,100. Total Federal cost 
under the existing project as of September 30, 1992 is 
$135,251. 
27. COUNTY LINE ROAD BRIDGE, 
ITAWAMBA COUNTY, MS 
Location. County Line Road Bridge crossed Mantachie 
Creek in Itawamba County, Mississippi and is located approximately 
one mile west of Centerville along an unnumbered 
county road between County Hwy. 363 and the 
county line. The Mantachie Creek drainage area is located 
in northeast Mississippi and is a part of Tombigbee River 
Basin. 
Existing Project. The project provides protection for 
both banks and the channel at the bridge crossing Mantachie 
Creek. The banks and channel were graded and 
protected with 24 inches of riprap on 6 inches of bedding 
material and filter fabric. This precludes any streambank 
erosion from high velocities or from sudden drawdown associated 
with receding floodwaters. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Construction Contract $2,891. 
Condition at end of fiscal year. Construction contract 
was awarded in August 1989 and completed in January 
1990. Estimated Federal cost is $81,800; and the non- 
Federal portion is $33,000. Total Federal cost to date is 
$116,662 for new work. Contributed funds expended for 
new work amounted to $28,109. 
28. CRIBBS MILL CREEK, 
TUSCALOOSA, AL 
Location. Cribbs Mill Creek begins in the northeastern 
part of the city of Tuscaloosa, AL and flows generally 
southwestward through the city into the Black Warrior 
River. 
Existing project. The project consists of channel 
modification of about 7,300 feet of the creek. Modification 
consists of widening the existing channel. The proposed 
plan would extend upstream from 1-359 to the confluence 
of Tributary 1 with the creek. Work would also be performed 
on 600 feet of Tributary 5. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Construction contract $17,125. Engineering 
and design cost $12,871. Supervision and administration 
costs amounted to $2,694. 
Condition at end of fiscal year. Construction contract 
was awarded in November 1989 and was completed in 
July 1991. Estimated Federal cost is $1,605,000; and the 
non-Federal portion is $1,200,000. Total Federal cost to 
date is $1,805,826 for new work. Contributed funds expended 
for new work amounted to $152,932. 
29. ESLAVA CREEK, 
MOBILE, AL 
Location. The city of Mobile, Alabama, which is located 
on the Gulf Coast of Alabama. The project begins at 
Pine Hill Drive and ends 2.1 miles upstream at Emogene 
Street. 
Existing project. None. The plan of improvement consists 
of channel enlargement, bank stabilization measures, 
and increasing the size of the box culvert at Airport 
Boulevard by adding an additional barrel. (See Table 10-B 
for authorizing legislation.) 
Local cooperation. A Local Cooperation Agreement 
with the city of Mobile was signed on September 14, 1987. 
The local sponsor has also agreed to make all required 
payments concurrently with project construction. 
Operation and results during fiscal year. 
New work: Construction contract $11,160; engineering 
and design $44,645; and supervision and administration 
$16,658. 
Condition at end of fiscal year. Preparation of plans 
and specifications on first two phases are complete. The 
first increment of work was awarded in February 1988 and 
completed in August 1988. The second increment of work 
was awarded in September 1990 and completed in September 
1991. Anticipate the third increment contract to be 
awarded in April 1993 and construction to be completed in 
December 1993. Current estimated Federal cost is 
$4,000,000; and the non-Federal portion is $1,046,800 for 
land and relocation, and $190,925 cash contributions. 
Total Federal cost under existing project to September 30, 
1992 is $2,989,060. Contributed funds expended 
$196,004. 
10-16

MOBILE, ALABAMA, DISTRICT 
30. FORT TOULOUSE, 
WETUMPKA, AL 
Location. The project is located near the confluence of 
the Coosa and Tallapoosa Rivers; approximately 20 miles 
north of Montgomery, Alabama. 
Existing project. The project provides bank stabilization 
for the National Historical Landmark and Taskigi Indian 
Mounds and consists of a 1,140-foot section of riprap 
revetment on the upper end of the site and 720-feet of 
stone dike at the lower end of the site. 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. 
New work: Construction Contract $222,129; Engineering 
and design cost $21,206. Supervision and administration 
cost $24,392. 
Condition at end of fiscal year. Completed plans and 
specifications in FY 1990. Construction initiated in FY 
1991 and was completed in March 1992. The project was 
transferred to the sponsor in August 1992. Current estimated 
Federal cost is $721,000 and non-Federal portion 
is $240,000. Total Federal cost under the existing project 
as of September 30, 1992 is $358,797 for new work. Contributed 
funds expended for new work amounted to 
$194,000. 
31. HURRICANE CREEK, 
PRENTISS CO., MS 
Location. Southeast Prentiss County, Mississippi. 
Marietta-Hazeldell Road Bridge crosses Hurricane Creek 
Tributary to Big Brown Creek and is located about 20 
miles northeast of Tupelo, Mississippi. 
Existing project. The project provides emergency 
streambank protection to the banks and the bottoms of the 
channel to retard erosion at the Marietta-Hazeldell Road 
Bridge crossing Hurricane Creek, a tributary to Big Brown 
Creek. The banks and bottoms were graded and protected 
with 12 inches of riprap on 6 inches of bedding material 
and filter fabric upstream of and downstream from the 
bridge. Through the bridge section, 18 inches of riprap 
were placed on 6 inches of bedding materials and filter 
fabric. This precludes any streambank erosion from high 
velocities or sudden drawdown associated with receding 
floodwaters. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New Work: Construction contract $1,108. 
Condition at end of fiscal year. A construction contract 
was awarded in August 1989 and construction was 
completed in December 1989. Total Federal cost to date is 
$52,720. Contributed funds expended for new work 
amounted to $12,892. 
32. MILL CREEK, 
DALTON, GA 
Location. The Mill Creek watershed comprises an area 
of 51.0 square miles in northeastern Walker County and 
west central Whitfield County, Georgia. The creek rises 
about 8 miles southwest of Dalton and flows in a northerly 
direction to its confluence with the North Fork of Mill 
Creek. From this point the creek flows generally in an 
easterly direction through the northern part of Dalton and 
enters Coahulla Creek 5.5 miles above its mouth. 
Existing project. The project consists of clearing and 
snagging Mill Creek from its mouth to downstream face of 
Willowdale Drive or a distance of 8.6 miles. This work involves 
the clearing of all material, trees, shrubs, and any 
underbrush within the creek banks. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Engineering and design cost $3,858. Supervision 
and administration costs amounted to $592. 
Condition at end of fiscal year. The Detail Project 
Report was revised in November 1987. These revisions 
reflected the changes due to cost sharing and contained a 
revised local cooperation agreement. A construction contract 
was awarded on 6 November 1989. Project construction 
was completed in August 1990. Estimated Federal 
cost is $245,000; and the non-Federal portion is $200,000. 
Total Federal cost to date is $474,065 for new work. Contributed 
funds expended for new work amounted to 
$25,000. 
33. MILL CREEK, 
SUMRALL, MS 
Location. Mill Creek originates in Lamar County, 
Mississippi; about 2 miles south of Sumrall. The town of 
Sumrall is located in southeastern Mississippi; about 16 
miles northeast of Hattiesburg. 
Existing project. The project consists of clearing and 
snagging 1.0 mile along Mill Creek with overbank clear- 
10-17

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
ing for 0.63 miles to provide a 50-foot wide floodway 
along the left descending banks. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Construction contract $607; engineering 
and design cost $13,914. Supervision and administration 
cost $2,628. 
Condition at end of fiscal year. The construction contract 
was awarded in August 1992 and is scheduled for 
completion in February 1993. Current estimated Federal 
cost is $83,300 and the non-Federal portion is $59,000. 
Total Federal cost under the existing project as of September 
30, 1992 is $104,104 for new work. 
34. MOUND STATE PARK, 
MOUNDVILLE, ALABAMA 
Location. The bank stabiliziation project is located on 
the left descending bank of the Black-Warrior River, about 
16 miles south of Tuscaloosa, Alabama. 
Existing project. The project provides bank stabilization 
for the Mound State Park National Historical 
Landmark. The plan consists of grading approximately 
800-feet of unstable bank to IV:3H and protect with 
riprap. Steeper upper bank sections around buildings are 
protected with a 250-feet long gabion wall. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Construction contract $232,965; engineering 
and design cost $29,147; supervision and administration 
cost $18,340. 
Condition at end of fiscal year. Completed plans and 
specifications in FY 1990. The construction contract was 
awarded in March 1992 and is scheduled for completion in 
April 1993. Current estimated Federal cost is $803,000 
and non-Federal portion is $268,000. Total Federal cost 
under the existing project as of September 30, 1992 is 
$416,857 for new work. Contributed funds expended for 
new work amounted to $100,044. 
35. MURDER CREEK, 
BREWTON, AL 
Location. The project is located in the city of Brewton, 
AL near the confluence of Murder and Burnt Corn Creeks 
in the commercial district of downtown Brewton. 
Existing project. The existing project provides for 
clearing and snagging in the vicinity of Brewton, Alabama 
on Murder Creek and on Burnt Corn Creek. Clearing was 
accomplished by felling and removing trees leaning more 
than 30 degrees and snagging by removal of snags and 
debris from bottom and sides of the channel. 
A limited stream clearing and snagging project was 
completed in 1980 on portions of both creeks to remove 
obstructions to flows. This interim measure was undertaken 
to reduce flooding in Brewton and East Brewton. 
Further, an evacuation plan for East Brewton was implemented 
under the Section 205 authority. The project involved 
removal of damageable structures from the 
low-lying flood plain of Murder Creek. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: None. 
Condition at end of fiscal year. Total cost of project as 
of September 30, 1992 is $1,178,684. 
36. OKATIBBEE LAKE, MS 
Location. The project is located on Okatibbee Creek 
37.7 miles above its mouth, in Lauderdale County, Mississippi, 
seven miles northwest of Meridian. 
Existing project. The project provides for a dam and 
reservoir for flood control, water supply, water quality 
control, fish and wildlife, and recreation. The dam consists 
of a compacted earth fill 6,540 feet long with the top 
elevation 369.8 feet above national geodetic datum, with 
top width of 18 feet. The spillway, which is located 1,500 
feet east of the east end of the dam, is an unpaved free 
overflow type, 1,500 feet long with a fixed crest at elevation 
359. A sluice intake structure near the center of the 
dam serves a 9.0-foot diameter concrete conduit. Storage 
allocated for water supply and water quality control varies 
seasonally form 21,400 acre-feet to 34,300 acre-feet between 
a minimum elevation of 328 and top-of-conservation-
pool elevation varying from 339 to 343. Storage 
varying from 46,500 to 59,500 acre-feet between the top 
of the conservation pool and elevation 352 has been 
10-18

MOBILE, ALABAMA, DISTRICT 
reserved exclusively for storage of flood waters. (See 
Table 10-B for authorizing legislation.) 
Local cooperation. Complied with to date. 
Operations and results during fiscal year. 
Maintenance: Costs for the year for ordinary maintenance 
and recreational management amount to 
$1,397,215. Recreation attendance at the reservoir during 
CY 1991 totaled 1,648,035 recreational user days. 
Condition at end of fiscal year. Construction began in 
June 1965, and was completed in November 1968. Total 
Federal cost of the existing project as of September 30, 
1992 is $9,739,528 for new work and $15,272,708 for 
maintenance, a total of $25,012,236. 
37. PORTERSVILLE BAY - EAST, 
MOBILE COUNTY, AL 
Location. The project is located in the town of Coden, 
in south Mobile County, Alabama. Portersville Bay, an 
arm of Mississippi Sound, is about 7.6 miles northwest of 
Cedar Point, the southern tip of the western mainland 
shore of Mobile Bay. 
Existing project. None. The project will provide for 
shoreline bank protection along 5,600 feet of Shell Belt 
Road. The protective works will consists of a timber 
bulkhead constructed of 12-inch diameter and 12-foot long 
vertical piles. Treated timber sheeting will penetrate 3 feet 
below the dredged line to prevent scour at the toe. The 
sheeting will be backed by non-woven filter fabric and 
backfilled. 
Local cooperation. The Local Cooperation Agreement 
with Mobile County, Alabama was signed on March 24, 
1992. The non-Federal sponsor has made all required cash 
payments, and all other items of local cooperation have 
been fully complied with. 
Operations and results during fiscal year. 
New work: Engineering and design cost $16,512; and 
supervision and administration cost $2,327. A total 
Federal cost of $18,839. 
Conditions at end of fiscal year. The construction contract 
was awarded on August 11, 1992, and construction of 
the shoreline protection project was commenced in September 
1992. All work on the project is expected to be 
completed by the end of February 1993. 
38. PORTERSVILLE BAY - WEST 
MOBILE COUNTY, AL 
Location. The project is located in the town of Coden, 
in south Mobile County, Alabama. Portersville Bay, an 
arm of Mississippi Sound, is about 7.0 miles northwest of 
Cedar Point, the southern tip of the western mainland 
shore of Mobile Bay. 
Existing project. None. The project will provide for 
shoreline bank protection along 3,500 feet of Coden Belt 
Road. The protective works will consist of a timber 
bulkhead constructed of 12-inch diameter and 12-foot long 
vertical piles. Treated timber sheeting will penetrate 3 feet 
below the dredged line to prevent scour at the toe. The 
sheeting will be backed by non-woven filter fabric and 
backfilled. 
Local cooperation. The Local Cooperation Agreement 
with Mobile County, Alabama was signed on March 24, 
1992. The non-Federal sponsor has made all required cash 
payments, and all other items of local cooperation have 
been fully complied with. 
Operations and results during fiscal year. 
New Work: Engineering and design cost $7,990; and 
supervision and administration cost $1,684. A total 
Federal cost of $9,674. 
Conditions at end of fiscal year. The construction 
contract was awarded on August 11, 1992, and construction 
of the shoreline protection project was commenced in 
September 1992. All work on the project is expected to be 
completed by the end of February 1993. 
39. PROCTOR CREEK, 
ATLANTA, GA 
Location. The Anthony Street area south of Bankhead 
Highway; about a mile west of Georgia Tech in Atlanta, 
Georgia. 
Existing project. The project consists of the evacuation 
of 32 residential structures in the Anthony Street area. 
These structures were purchased and removed. 
Local cooperation. Fully complied with. 
Operating and results during fiscal year. 
New work: Real Estate cost $67,312. Supervision and 
administration cost $310. 
10-19

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Condition at end of fiscal year. Real Estate acquired 
31 residential structures with remaining one under negotiation. 
Construction is scheduled for completion in June 
1992. Total Federal cost under the existing project as of 
September 30, 1992 is $850,243 for new work. 
40. RACCOON CREEK 
BACONTON, GA 
Location. The project is located in the community of 
Baconton in northwest Mitchell County approximately 20 
miles south of Albany and 40 miles northeast of 
Bainbridge, Georgia. 
Exiting project. The flood control project consists of 
raising about 1500 feet of South Jackson Street near the 
West Daniels Street bridge to elevation 176.0 feet NGVD. 
The channel and 30 feet on each overbank of Raccoon 
Creek were cleared and snagged from State Hwy. 3 to U.S. 
Hwy. 19. Raising South Jackson Street prevents overbank 
flows from entering downtown Baconton. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Engineering and design cost $3,786. Supervision 
and administration costs amounted to $646. 
Condition at end of fiscal year. Preparation of plans 
and specifications were initiated in August 1988. A construction 
contract was advertised in May 1989, and a contract 
was awarded on 29 August 1989. The project was 
completed in May 1990. Estimated Federal cost is 
$251,000; and the non-Federal portion is $89,000. Total 
Federal cost to date is $380,645 for new work. Contributed 
funds expended for new work amounted to $35,000. 
41. SILVER CREEK, 
ROME, GA 
Location. Silver Creek is located about 2 1/2 miles 
south of Rome, Georgia in Floyd County. Silver Creek 
originates south of Rome and flows northerly through Lindale 
into the Etowah River downstream of East Second 
Avenue Bridge. 
Existing project. The project provides for non-structural 
flood control measures along Silver Creek. The plan 
consists of purchasing and removing 15 houses from the 2- 
year flood plain. 
Local cooperation. Fully complied with. 
Operation and results during fiscal year. 
New work: Real Estate cost $29,481. 
Condition at end of fiscal year. Real Estate acquired 
15 residences. Construction completed in March 1991. 
Total Federal cost under the existing project as of September 
30, 1992 is $604,719. 
42. SOWASHEE CREEK, 
MERIDIAN, MS 
Location. The project is located in East Central Mississippi, 
Lauderdale County, in the city of Meridian, which is 
approximately 90 miles east of Jackson, Mississippi. 
Existing project. In 1955, the Corps of Engineers completed 
channel improvement on the lower 10.5 miles of 
Sowashee Creek. This work was accomplished under the 
authority of Section 205 of the Flood Control Act of 1948, 
as amended. The plan of improvement consists of a combination 
of channel enlargement (3.9 miles), and clearing 
and snagging (6.6 miles) over a reach of 10.5 miles. One 
(1) railroad bridge and several highway roads and bridges 
and utilities will require modification for the channel improvement. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. A Local Cooperation Agreement 
with the Pat Harrison Waterway District was completed on 
September 23, 1987. The local sponsor has also agreed to 
make all required payments concurrently with project construction. 
Operation and results during fiscal year. 
New work: Relocation contract cost $39,200; Construction 
contract cost $2,277,896; engineering and design 
$572,464; and supervision and administration $159,091. 
Condition at end of fiscal year. All contracts have 
been completed except for the recreation contract. Plans 
and specifications for the expanded recreation will be initiated 
in FY 1993. Upon completion, the project will be 
officially transferred to the city. An Operation and Maintenance 
Manual will be provided within 90 days of the 
transfer. Current estimated Federal cost is $20,145,000; 
and the non-Federal portion is $12,155,000. Total Federal 
cost under existing project to September 30, 1992 is 
$13,658,299 for new work. Contributed funds expended 
$931,493. 
10-20

MOBILE, ALABAMA, DISTRICT 
43. TALLAHALLA CREEK, 
LAUREL, MS 
Location. The project is located in the city of Laurel, 
Mississippi in the Pascagoula River Basin in southeastern 
Mississippi. 
Existing project. None. The project along Tallahalla 
Creek would consist of channel clearing and snagging 
with overbank clearing of brush and trees less than 4 inches 
diameter for a distance of 30 feet on each bank. The 
project would begin about 1.5 miles below Queensburg 
Avenue Bridge and extend 7.25 miles to US Highway 84. 
Also, a flood warning system would be installed in the 
Tallahalla Creek Basin to relay data to a base station. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New work: Engineering and design cost $44,444. Supervision 
and administration costs amounted to $8,081. 
Condition at end of fiscal year. The advertisement for 
bids for clearing and snagging portion of the project was 
cancelled in August, 1989 due to erosion at two sites along 
Masonites Lagoon Dikes. A flood warning system for the 
Tallahala Creek basin was awarded in January 1990 and 
completed in May 1990. The construction contract was 
awarded in September 1992 and is scheduled for completion 
in August 1993. Estimated Federal cost is $713,000; 
and the non-Federal portion is $321,000. Total Federal 
cost to date is $241,365 for new work. Contributed funds 
expended for new work amounted to $40,000. 
44. THREEMILE CREEK, 
MOBILE, AL 
Location. The project is located near the Gulf of 
Mexico in the southwest corner of the state of Alabama 
and in the city of Mobile, approximately 180 miles southwest 
of Montgomery, Alabama. Threemile Creek 
originates in the western part of Mobile and flows easterly 
about 14 miles to enter Mobile River near the Alabama 
State Docks. The drainage area of the basin consists of 39 
square miles of urbanized area. 
Existing project. None. The authorized flood control 
project will consist of channel widening and deepening 
from about 2,000 feet downstream of Stone Street to a 
point about 6,300 feet upstream of Interstate 65 or a total 
distance of 5.6 miles. The plan also includes development 
of certain recreational facilities of the type associated with 
urban parks. (See Table 10-B for authorizing legislation.) 
Local cooperation. The Local Cooperation Agreement 
with the city of Mobile, Alabama was completed on September 
30, 1987. The local sponsor has agreed to make all 
payments concurrently with project construction. 
Operation and results during fiscal year. 
New work: Relocation cost $1,012,055. Construction 
contracts $5,880,465; engineering and design cost 
$117,672; and supervision and administration cost 
$260,815. 
Condition at end of fiscal year. All channel contracts 
have been completed; 3 bridge relocation contracts have 
been completed; and 2 bridge relocation contracts are underway. 
The final bridge relocation contract was awarded 
August 1992, but work will not start until the other bridges 
are complete. Current estimated Federal cost is 
$16,677,000; and the non-Federal portion is $7,923,000. 
Total Federal cost under existing project to September 30, 
1992 is $13,285,884 for new work. Contributed funds expended 
$973,427. 
45. TOMBIGBEE RIVER (EAST FORK), 
MS AND AL 
Location. The project is located on the Tombigbee 
River and its tributaries between the junction of Browns 
and Mackeys Creek in Itawamba County, Mississippi, for 
a distance of 53 miles along the East Fork of the Tombigbee 
River, from Walkers Bridge at the junction of Browns 
and Mackeys Creeks to the Monroe County line. 
Existing project. Provides for alleviation of floods 
from the Tombigbee River by clearing and snagging and 
excavation of 13 cut-off channels, and other related channel 
improvements. (See Table 10-B for authorizing legislation.) 
Local cooperation. Fully complied with on work done 
under the 1936 Flood Control Act. Work to be done under 
authority of the 1941 Flood Control Act requires local interest 
to provide all lands, easements, and rights-of-way 
for project construction; hold and save the United States 
free from damages due to construction of the project; and 
maintain and operate all the works after completion in accordance 
with regulations prescribed by the Secretary of 
the Army. 
Operations and results during fiscal year. 
10-21

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Maintenance: Routine maintenance of channels cost 
$16,062. 
Condition at end of fiscal year. The project for 
Itawamba County, as authorized in the 1936 Flood Control 
Act, was completed during fiscal year 1940. No work has 
been done on the extension of the project authorized in the 
1941 Flood Control Act. Total Federal cost of the existing 
project as of September 30, 1992 is $134,801 for new 
work and $2,943,885 for maintenance, a total of 
$3,078,686. 
46. TOMBIGBEE RIVER 
TRIBUTARIES, MS AND AL 
Location. The Tombigbee River rises in extreme northeast 
Mississippi and flows southerly through eastern Mississippi 
and western Alabama, emptying into the Mobile 
River about 45 miles above its mouth at Mobile, Alabama. 
Tributaries to be improved for flood control are all in 
northeast Mississippi and northwest Alabama. Luxapalila 
Creek is the last project currently being considered under 
the 1958 congressional authority. 
Existing project. The authorized project provides for 
improvement of 22 tributaries of the Tombigbee River 
Basin by means of channel clearing and snagging. The 
Luxapalila Creek project consists of 2.1 miles of completed 
channel modifications. The remaining effort consists 
of approximately 26 miles of various channel work. 
Approved estimate of cost for new work is $42,108,000; 
consisting of $37,743,000 Federal funds, and $4,365,000 
non-Federal funds. (See Table 10-B for authorizing legislation.) 
Local cooperation. Local interests must furnish lands 
and rights-of-way for construction; make all roads, highway 
bridge, and utility changes, alterations, additions, and 
relocations necessary for the project; hold the United 
States free from damages; prevent future encroachments 
along the improved channels; maintain all works after 
completion, with the exception of Twenty Mile Creek 
from mile 11.7 to mile 22.0. 
Operations and results during fiscal year. 
New work: Real estate cost $18,840; engineering and 
design $289,142, and supervision and administration cost 
$54,239. 
Condition at end of fiscal year. Construction commenced 
in July 1965, and is proceeding stream by stream 
as funds are made available. Total project is 85% complete. 
Luxapalila Creek is the only remaining work 
scheduled to be accomplished. Plans and specifications are 
complete and construction contract scheduled for award in 
April 1993. The clearing and snagging contract is 
scheduled for award in June 1993. Total Federal cost of 
existing project as of September 30, 1992 is $25,110,746 
for new work. Contributed funds for new work amounted 
to $63,342. 
47. UPPER GORDON CREEK, 
HATTIESBURG, MS 
Location. The proposed project on Gordons Creek is 
located in Hattiesburg, MS. 
Existing project. A Federal project on the lower 2.5 
miles was constructed in 1979 under the Section 205 of 
the Flood Control Act of 1948. The project consisted of 
clearing and snagging from the creek's confluence with 
the Leaf River upstream to Bay Street and channel widening 
to a 40-foot bottom width between Bay and Broad 
Streets. 
The work will consist of real estate acquisition of ten 
(10) residences on Brookland Street and South 17th 
Avenue and removed from floodplain; habitat mitigation 
and channel enlargement for 1.1 miles between Broad and 
Hardy Streets; and flood damages mitigation downstream 
of Broad Street. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
New Work: Engineering and design cost $63,867. Supervision 
and administration costs amounted to $12,068. 
Work Accomplished to Date: Preparation of Plans and 
Specifications are essentially completed. It is anticipated a 
construction contract would be awarded in July 1992, 
provided necessary right-of-ways for channel improvement 
are available and necessary relocations are performed 
by non-federal sponsors. Also, initiation of the 
mitigation of damages downstream of Broad Street and 
real estate acquisition of nine residences upstream of 
Hardy Street have been initiated. Estimated Federal cost is 
$4,412,250; and the non-Federal portion is $3,087,750. 
Total Federal cost to date is $787,758 for new work. 
48. VILLAGE CREEK, 
BIRMINGHAM, AL 
Location. The project is located in central Alabama, 
Jefferson County, in the city of Birmingham, Alabama. 
Existing project. None. The project is basically nonstructural 
and includes evacuating 642 structures, in six (6) 
10-22

MOBILE, ALABAMA, DISTRICT 
separate neighborhoods, from the floodplain; enlarging 2 
miles of the stream channel in the vicinity of the 
Municipal Airport which also involves modification of 
three (3) bridges, demolishing two (2) unused bridges, and 
relocating two (2) waterlines and other utilities, installing 
three (3) emergency floodwarning devices; and creating an 
area of 210 acres which can be utilized for future recreation 
development. Channel enlargements (2 miles) will 
reduce annual damages near Municipal Airport by 82 percent 
and evacuation of 642 structures will reduce annual 
damages in residential areas by 61 percent. 
Local cooperation. The Local Cooperation Agreement 
with the city of Birmingham, Alabama was executed on 
December 14, 1988. The local sponsor has also agreed to 
make all required payments concurrently with the project 
construction. 
Operation and results during fiscal year. 
New work: Real Estate cost $5,051,145; engineering 
and design $35,866; and supervision and administration 
$471,368. 
Condition at end of fiscal year. Real Estate design 
memorandum complete February 1988. Real Estate acquisition 
started January 1989. The project is 80% complete. 
Acquisition of 479 tracts out of a total of 631 tracts 
have been completed through September 30, 1992. Project 
scheduled to be completed June 1994. Current estimated 
Federal cost is $26,870,000; and the non-Federal portion is 
$10,130,000. Total Federal cost under existing project to 
September 30, 1992 is $18,102,071 for new work. Contributed 
funds for new work amounted to $5,910,642. 
49. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (Preauthorization). 
Snagging and Clearing for flood control pursuant to 
Section 208 of Flood Control Act of 1954, as amended. 
Emergency streambank and shoreline protection pursuant 
to Section 14 of the Flood Control Act of 1946, as 
amended. 
(See Table 10-J) 
Emergency flood control activities - repair, flood fighting, 
and rescue work under Public law 99, 84th Congress, 
and antecedent legislation, and disaster relief and assistance 
under Public law 288, 93d Congress.(See Table 10- 
J) 
50. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Local flood protection works for which inspection is 
performed under this heading consist of levee projects at 
West Point, Georgia, on the Chattahoochee River; Beaver 
Creek at Montezuma, Georgia, in the Flint River Basin; 
Elba and Geneva, Alabama in the Choctawhatchee River 
Basin; Rome, Georgia, and Little Wills Creek at Collinsville, 
Alabama, in the Alabama-Coosa River Basin. 
Channel recitification projects include Little Cove Creek, 
Glencoe, Alabama and Black Creek, Gadsden, Alabama in 
the Alabama-Coosa River Basin; Big Brown Creek, 
Donivan Creek, Twenty Mile Creek and Mantachie Creek, 
near Fulton, Mississippi, Burketts Creek and Stanifer 
Creek near Amory, Mississippi, Houlka Creek and 
Sakatonchee Creek in Chickasaw and Clay Counties, Mississippi, 
James Creek in Monroe County, Mississippi, and 
Luxapalila Creek, Lowndes County, Mississippi, all in the 
Tombigbee River Basin; Sowashee Creek, Meridian, Mississippi 
in the Pascagoula River Basin; Burnt Corn and 
Murder Creeks, Brewton, Alabama in the Conecuh River 
Basin; Autauga Creek, Prattville, Alabama; Poley Bridge, 
Goose Pone and Walnut Creeks, Clanton, Alabama; 
Pinchgut Creek, and Cahaba River, Trussville, Alabama; 
Town Creek, Americus, Georgia; and Lake Douglas in 
Bainbridge, Georgia. Shore protection and erosion control 
projects include Harrison County, Mississippi; Leaf River, 
Mahned, Mississippi; Chattahoochee River at La Grange, 
Troup County, Georgia; Pumpkinvine Creek, Emerson, 
Georgia; and Chickasawbogue Creek, US Highway 43 
Bridge, Linden, Alabama. The project at Rome and Montezuma, 
Georgia and Collinsville, Alabama include pumping 
stations. Inspections were made during FY 91 to 
determine the extent of compliance with approved regulations 
for maintenance and operation of the project. 
Responsible local officials were advised of inadequacies 
in the maintenance and operation of the-local flood protection 
works under their jurisdiction where appropriate. Followup 
for compliance of the deficient projects continued 
during the year. Fiscal year costs were $15,395. Total cost 
to September 30, 1992 is $671,163 charged to maintenance. 
51. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 10-E.)Multiple-Purpose Projects Including 
Power 
10-23

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
52. ALABAMA-COOSA RIVERS, 
AL AND GA 
Location. Alabama River is formed 18 miles above 
Montgomery, Alabama, by the junctions of the Coosa and 
Tallapoosa Rivers. It then flows southwesterly through 
Alabama 318 miles and unites with the Tombigbee River 
about 45 miles north of Mobile, in southwestern Alabama, 
to form the Mobile River. (See Geological Survey maps 
for central and southwest Alabama.) The Coosa River is 
formed at Rome, Georgia, in northwest Georgia, by the 
junction of the Oostanaula and Etowah Rivers, which have 
their sources in southeastern Tennessee and northern 
Georgia. From Rome the Coosa River flows southwesterly 
through Georgia and Alabama 286 miles and unites with 
the Tallapoosa River near Montgomery, Alabama, at about 
the center of the State, to form the Alabama River. (See 
Geological Survey maps for northeast Alabama, southeast 
Tennessee, and northwest Georgia.) 
Previous project. Projects for Alabama River: for 
details see page 1837, Annual Report for 1915; page 725, 
Annual Report for 1938; and page 592, Annual Report for 
1944. Projects for Coosa River: for details see page 1837, 
Annual Report for 1915; page 728, Annual Report for 
1938; and page 594, Annual Report for 1944. 
Existing project. The authorized project provides for 
full development of the Alabama-Coosa Rivers and 
tributaries for navigation, flood control, power, recreation, 
and other purposes, in accordance with plans under 
preparation by Chief of Engineers, subject to modifications 
thereof which may be advisable for increasing 
development of hydroelectric power. (See Table 10-B for 
authorizing legislation.) Public Law 436, 83rd Congress, 
suspended authorization of the comprehensive plan, insofar 
as it provides for development of hydroelectric 
power for Coosa River, to permit non-Federal interests to 
develop the Coosa River by construction of a series of 
dams in accordance with conditions of a license issued 
pursuant to Federal Power Act and in accordance with certain 
other provisions and requirements of the aforementioned 
public law. The plan was further modified by the 
WRDA of 1986 to authorize planning, engineering and 
design for the project generally in accordance with the 
plans contained in Design Memorandum No. 1, General 
Design, dated May 1982. The present phase of improvement 
includes the construction of Robert F. Henry and 
Millers Ferry multiple-purpose improvements, Claibome 
Lock and Dam, and supplemental channel work providing 
for a nine-foot deep navigation channel from the mouth of 
the Alabama River to Montgomery, Alabama, and construction 
of Carters Dam, a multiple-purpose improvement 
on Coosawattee River, Georgia. 
Local cooperation. Requirements of local cooperation 
will be determined as formulation of plans for development 
of projects progress. No action in the matter of local 
cooperation has been initiated. 
Terminal facilities. On the east bank of the river a 
natural landing connects with city streets at Montgomery. 
Wofford Oil Company has a small wharf about 10 miles 
below Montgomery equipped for handling petroleum 
products. There are also various natural landings along the 
river. Facilities and natural landings on Alabama River are 
considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Contract maintenance dredging of the 
river system at a cost of $2,439,500. General charges for 
water control management, condition surveys, engineering 
and design, supervision and administration amounted to 
$4,086,800. Claibome Lock and Dam charges were 
$429,800 with recreation and resource management costs 
of $612,419. 
Condition at end of fiscal year. Construction was initiated 
on Carters Dam in April 1962, on Millers Ferry 
Lock and Dam in April 1962, on Millers Ferry Lock and 
Dam in April 1963, Claibome Lock and Dam in May 
1965, and Robert F. Henry Lock and Dam in March 1966. 
Carters Dam was completed in FY 1980. The authorized 
nine-foot navigation channel to Montgomery, Alabama 
was opened to traffic in January 1972. Overall construction 
is essentially complete at Millers Ferry Lock and 
Dam. Construction of Robert F. Henry Lock and Dam is 
essentially complete. Total Federal cost of the existing 
project as of September 30, 1992 is $82,351,213, including 
$3,245,400 for new work and $79,105,813 for maintenance. 
(See Table 10-L.) 
52A. CARTERS DAM AND 
RESERVOIR, GA 
Location. The damsite is in Murray County, Georgia, 
on the Coosawattee River 26.8 miles above its junction 
with Conasauga River, one of the headwater tributaries of 
the Alabama-Coosa system. It is 60 miles north of Atlanta 
near the town of Oakman, Georgia. The reservoir is in 
both Murray and Gilmer Counties. 
Existing project. The existing project consists of a 
1,950-foot long rockfill dam across the river, three saddle 
dikes on the left bank, a 258-foot long high-level, gated 
spillway on the left bank, a powerhouse on the right bank 
having two conventional units with a generating capacity 
of 125,000 kilowatts each and two pump-generating units 
of the same size, and a regulating dam 2,855 feet long with 
10-24

MOBILE, ALABAMA, DISTRICT 
a gated spillway 208 feet long 1.5 miles downstream from 
the main dam. The lake has an area of 3,220 acres, at maximum 
power pool elevation 1,072, total capacity of 
472,800 acre-feet, of which 134,900 acre-feet is usable for 
power and 95,700 acre-feet reserved for flood control and 
242,200 acre-feet dead storage. For other information see 
description of Alabama-Coosa project. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance of the dam, 
reservoir, powerhouse, service and recreational activities 
and administration totaled $5,412,945. This amount includes 
$2,347,900 for turbine repairs and generator 
rewinding. Gross power generation amounted to 
352,650,000 kilowatt hours during FY 1992, of which 
352,650,000 were delivered to Southeastern Power Administration. 
Recreation attendance during Fy 1992 totaled 
882,628 user days. 
Condition at end of fiscal year. Construction which 
commenced in April 1962 was essentially completed in 
September 1980. Total Federal cost of the existing project 
as of September 30, 1992 is $163,700,083, including 
$111,140,340 for new work and $52,559,743 for maintenance. 
52B. CLAIBORNE LOCK AND DAM, AL 
Location. The site is in Monroe County at mile 81.8 on 
the Alabama River, 15 miles northwest of Monroeville 
and 5.7 miles upstream from the U.S. Highway 84 bridge. 
Existing project. The existing project consists of a 
short earth dike on the right bank, a combination of a 
fixed-crest and gated spillway extending across the river 
channel and into the left bank, a navigation lock and 
mound on the left bank, and an earth dike extending across 
the left overbank to high ground. Normal upper pool is 
elevation 35 and the minimum pool will be elevation 32 to 
provide storage for reregulation of Millers Ferry 
powerplant releases. The 60-mile long reservoir has an 
area of 5,850 acres and a volume of 96,360 acre-feet. For 
other information see description of Alabama-Coosa 
projects. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance of the lock 
and dam totaled $392,200. 
Condition at end of fiscal year. Construction began in 
May 1965 and was completed in FY 1976 at a total cost of 
$27,997,450. 
52C. COOSA RIVER, MONTGOMERY 
TO GADSDEN, AL 
Location. The Coosa River is one of the two major 
tributaries forming the Alabama River approximately 18 
miles northeast of Montgomery, Alabama. From its source 
at the juncture of the Etowah and Oostanaula Rivers in 
northwest Georgia, it flows southwesterly about 286 miles 
to join with the Tallapoosa River in forming the Alabama 
River. 
Existing project. The improvement of the Alabama- 
Coosa River for navigation to Rome, Georgia was 
authorized by Congress in the River and Harbor Act of 
1945. A report in House Document 320, transmitted to 
Congress on January 27, 1960, recommended that the 
navigation project for the Coosa River from Montgomery 
to Gadsden be accomplished after the waterway to 
Montgomery was assured.The plan of improvement identified 
in House Document 320 provided for a waterway 9 
feet deep with widths of 200 feet to Montgomery, 
Alabama, and 150 feet to Rome, Georgia. The waterway 
to Montgomery has essentially been completed. The plan 
for the Coosa River segment of the waterway between 
Montgomery and Gadsden was further modified by the 
WRDA of 1986 to authorize planning, engineering and 
design for the project generally in accordance with the 
plans contained in Design Memorandum No. 1, General 
Design, dated May 1982. Total Federal cost of the existing 
project as of September 30, 1992 is $14,986,400 for new 
work. 
52D. MILLERS FERRY LOCK AND 
DAM, AL 
Location. The site is in Wilcox County at mile 142.2 
on the Alabama River, 10 miles northwest of Camden, 
Alabama, and 30 miles southwest of Selma. 
Existing project. The existing project consists of an 
earth dike on the right bank, a concrete, gravity-gated 
spillway in the river channel, a lock and mound on the left 
bank, an earth dike extending downstream paralleling the 
lock, to the powerhouse intake structure; a powerhouse, 
and an earth dike extending to high ground on the left 
bank. Normal upper pool is at elevation 80. The 
powerplant contains three 25,000 kilowatt units. The 103- 
mile long reservoir has an area of 17,200 areas at normal 
pool level and a total capacity of 331,800 acre-feet. The 
lock chamber is 84 by 600 feet with a 13-foot depth over 
the miter sills. For other information see description of 
Alabama-Coosa project. 
Operations and results during fiscal year. 
10-25

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Maintenance: Operation and maintenance of lock, dam, 
powerhouse, reservoir, and administration cost 
$3,681,102. Gross power generation amounted to 
424,968,000 kilowatt hours during FY 1992, of which 
422,045,000 kilowatt hours were delivered to Southeastern 
Power Administration. Recreation attendance at William 
"Bill" Dannelly Reservoir during FY 1992 totaled 
3,921,634 user days. 
Condition at end of fiscal year. Construction began in 
April 1963. The lock was placed in temporary operations 
in June 1968 and opened to full use in November 1969. 
The powerhouse units were placed on line during April 
and May 1970. The project was essentially completed in 
1980. Total Federal cost of the project as of September 30, 
1992 is $63,125,300 for new work and $49,100,587 for 
maintenance, a total of $112,225,887. 
52E. ROBERT F. HENRY LOCK AN D 
DAM, AL 
Location. The site is in Lowndes and Autauga Counties 
at mile 281.2 on the Alabama River, 26 miles west of 
Montgomery. 
Existing project. The existing project provides for a 
navigation lock, a gated spillway, and a power plant located 
at mile 281.2. The normal upper pool is at elevation 
125.0 and the minimum lower pool due to the Millers 
Ferry Lock and Dam is at elevation 80.0. The structures 
consist of earth dikes and a power plant on the right bank, 
a gated spillway in the river channel, a lock and mound on 
the left bank, and an earth dike extending upstream parallel 
to the Western Railway of Alabama. The total length of 
the structures is about 14,962 feet with maximum height 
above the foundation at the power plant intake about 101 
feet. The power plant contains four 17,000-kw. units. The 
88-mile long reservoir has an area of 12,300 acres at normal 
pool level and a total capacity of 234,200 acre-feet. 
The lock has a chamber 84 feet wide and 600 feet long and 
provides a 12-foot depth over the lower miter sill. For 
other information see description of Alabama-Coosa 
project. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance costs 
amounted to $2,947,285. Gross power generation 
amounted to 357,549,000 kilowatt hours during FY 1992, 
of which 354,391,000 kilowatt hours were delivered to 
Southeastern Power Administration. Recreation attendance 
during FY 1992 totaled 2,592,261 user days. 
Condition at end of fiscal year. Construction began in 
March 1966 and is essentially complete. The first powerhouse 
unit was placed in operation in June 1975, with the 
last unit on line in November 1975. Total Federal cost of 
the project as of September 30, 1992 is $115,387,634, including 
$83,360,800 for new work and $32,026,834 for 
maintenance. 
53. ALLATOONA DAM, COOSA 
RIVER BASIN, GA 
Location. The project is on Etowah River in Bartow 
County, Georgia, about 48 miles upstream from Rome, 
Georgia, about five miles due east of Cartersville, Georgia, 
and about 2,000 feet downstream from mouth of Allatoona 
Creek. The reservoir extends about 28 miles up the 
Etowah River at maximum power-pool elevation of 840 
feet above mean sea level. 
Existing project. The authorized project provides for a 
dam and reservoir for flood control, regulation of 
streamflow for navigation, and development of 
hydroelectric power. Height above the river bottom of the 
concrete, gravity-type dam is about 190 feet, from elevation 
690 feet to 880 feet national geodetic datum. The 
spillway, with crest at elevation 835, is controlled by nine 
tainter gates, 40 feet wide by twenty-six feet high, and two 
tainter gates, 20 feet wide by twenty-six feet high; having 
a combined discharge capacity of 321,000 cubic feet per 
second with the water surface at elevation 870.3 One 48- 
inch diameter sluicing conduit with a free discharge valve 
and four sluices, 5 feet-8 inches wide by 10 feet high, are 
included in dam. Installed generating capacity consists of 
two 36,000 kilowatt units and one 2,000 kilowatt unit, or a 
total of 74,000 kilowatts. The reservoir, covering 19,200 
acres at elevation 860, has a storage capacity of 670,000 
acre-feet. The initial construction cost was $31,424,738, 
excluding the addition of recreation facilities at the completed 
project. (See Table 10-B for authorizing legislation.) 
Local cooperation. None required. (Sec. 2, Flood Control 
Act of June 28, 1938, applies). 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance of the dam, 
reservoir, powerhouse, service and recreational activities, 
and administration totaled $6,281,198. Gross power 
generation amounted to 149,276,400 kilowatt hours during 
FY 1992 of which 146,560,000 kilowatt hours were 
delivered to Southeastern Power Administration. Recreational 
attendance at Allatoona Lake during FY 1992 totaled 
11,934,721 user days. 
10-26

MOBILE, ALABAMA, DISTRICT 
Condition at end of fiscal year. Construction of the 
existing project began in March 1944 and was completed 
in October 1955. Total Federal cost under existing project 
as of September 30, 1992 is $35,709,085 for new work 
and $85,106,560 for maintenance, a total of $120,815,645. 
54. APALACHICOLA, 
CHATTAHOOCHEE, AND FLINT 
RIVERS, AL, GA, AND FL 
Location. The Apalachicola River is formed at the 
southwest corner of the State of Georgia by the junction of 
the Chattahoochee and Flint Rivers and flows south 108 
miles emptying into Apalachicola Bay. Florida River 
enters the Apalachicola River from the east at mile 45.4 
and the River Styz also enters from the east at mile 36.7 
and Chipola River enters from the west at mile 28.2. (See 
Coast and Geodetic Survey Chart 11401.) The Chattahoochee 
River, 418 miles long, rises in northeast Georgia 
and flows southwesterly to West Point, and thence 
southerly to join the Flint River at the southwest corner of 
Georgia, forming the Apalachicola River. (See Geological 
Survey maps for northwest Georgia.) The Flint River, 330 
miles long, rises in west central Georgia, flows generally 
southeasterly to Albany, and thence southwest to the 
southwest corner of the State, where it joins the Chattahoochee 
River to form the Apalachicola River. (See 
Geological Survey maps for southwest Georgia.) 
Previous project. For details see page 484 of Annual 
Report for 1963. 
Existing project. The authorized project provides for 
development of the Apalachicola, Chattahoochee, and 
Flint Rivers for navigation, flood control, hydropower, and 
recreation. Navigation features of the existing project consist 
of a continuous 9-foot by 100-foot channel in the 
Apalachicola River from the intersection of the Gulf Intracoastal 
Waterway to the confluence of the Chattahoochee 
and Flint Rivers, 104 miles, thence to 
Columbus, Georgia, on the Chattahoochee River, 164 
miles, and to Bainbridge, Georgia, on the Flint River, 29 
miles, and a 3-foot by 100-foot channel on the Flint River 
from Bainbridge to Albany, Georgia, 74 miles, thence a 
channel suitable for light draft vessels at moderate stage to 
Montezuma, Georgia, 79 miles to be accomplished by 
dredging, contract works, and construction of three locks 
and dams (Jim Woodruff, George W. Andrews, and Walter 
F. George) along the 9-foot depth channel, two multipurpose 
dams (West Point and Buford) on the 
Chattahoochee River. Three multipurpose dams (Lower 
Auchumpkee Creek, Lazer Creek, and Spewrell Bluff) on 
the Flint River were authorized in the Water Resources 
Development Act of 1986. The project also provides for 
minor improvements of certain streams tributary to the 
Apalachicola River, including a 9-foot by 100-foot side 
channel, approximately 2,000 feet long, from 
Apalachicola River to Apalachicola River Industrial Park 
at Blountstown, Fla. Plane side of reference is mean low 
water. Hydropower and flood control storage are provided 
at Sidney Lanier, Walter F. George, and West Point, and 
hydropower is provided at Jim Woodruff. For further 
details see Annual Report for 1962. The project was 
originally authorized in section 2 of the River and Harbor 
Act of 1945, was further modified by the WRDA of 1986 
(P.L. 99-662). (See Table 10-B for authorizing legislation.) 
Mean range of tide at the mouth of Apalachicola River 
is 1.6 feet. At the point where the river is formed the variation 
between low and high water is about 37 feet. On the 
Chattahoochee River, variation between average low and 
high water is about 20 feet, and extreme fluctuation is 65.3 
feet at Eufaula. On the Flint River the extreme fluctuation 
of stage due to flood is 40 feet, while average variation between 
low and high water is about 21.5 feet. A water 
supply study is currently being conducted on the upper 
portion of the ACF River System. 
Local cooperation. The six Florida Counties that 
originally served as local sponsors for the Florida portion 
of the waterway have all informed the District in writing 
that they no longer wish to serve as local sponsors. The 
State of Florida has also declined assumption of responsibilities 
of local sponsorship. At this time no items of 
local cooperation are being complied with. No local sponsors 
are required for the Alabama and Georgia portions of 
the waterway. 
Terminal facilities. About 200 feet of public docks, in 
addition to private wharves, are available at Apalachicola, 
Florida. There are numerous constructed and natural landings 
along the entire system for launching small craft. For 
details of other terminal facilities, which are considered 
adequate for existing commerce, see individual project 
descriptions. See also Table 10-M on locks and dams and 
multiple-purpose development included in existing 
project. 
Operations and results during fiscal year. 
Maintenance: Contract dredging on the river system 
cost $2,305,900. George W. Andrews Lake recreational 
and resource management costs totaled $334,800. Operation 
and maintenance of George W. Andrews Lock and 
Dam cost $539,200. All other costs for the project 
amounted to $1,971,073. Recreational attendance during 
FY 1992 totaled 349,333 user days. 
10-27

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Condition at end of fiscal year. Improvement of 
Apalachicola River channel by dredging to provide project 
dimensions throughout is complete. All major construction 
on Lake Sidney Lanier Dam, George W. Andrews Lock 
and Dam, Jim Woodruff Lock and Dam, and Walter F. 
George Lock and Dam, is complete. West Point is essentially 
complete with the exception of adding recreation 
facilities. Channel rectification in Apalachicola River was 
completed December 1970. More detailed information 
concerning condition at the end of fiscal year for individual 
locks and dams and multiple-purpose developments 
comprising the system is presented under their 
respective project titles elsewhere in this report. Total 
Federal cost under existing project as of September 30, 
1992 is $4,452,162 for new work and $92,774,060 for 
maintenance, a total of $97,226,222. (See Tables 10-A and 
10-M for fiscal year costs and summaries of overall 
project.) 
54A. BUFORD DAM, 
LAKE SIDNEY LANIER, GA 
Location. Buford Dam is on the Chattahoochee River 
about 348.9 miles above its mouth, 50 miles above Atlanta 
and five miles northwest of Buford, Georgia. The reservoir, 
Lake Sidney Lanier, extends about 47 miles upstream 
along the Chattahoochee River, and about 21 miles up the 
Chestatee River, which enters the Chattahoochee River 
14.5 miles above the dam. 
Existing project. The authorized project provides for a 
rolled-earth dam 1,630 feet long with crest at elevation 
1,106 feet national geodetic datum, or about 192 feet 
above streambed elevation; three earth saddle dikes with a 
total length of 5,406 feet; a chute spillway with crest at 
elevation 1,085; a powerhouse in a deep cut with steel 
penstocks in tunnels, and concrete intake structure at the 
upstream end of the tunnels; and a flood control sluice tunnel 
paralleling the power tunnels. The Lake Sidney Lanier 
reservoir has a gross capacity of 2,554,000 acre-feet of 
which 637,000 acre-feet of storage is reserved for flood 
control storage. The power installations consist of one 
generating unit of 6,000 kilowatts and two units of 40,000 
kilowatts each, or a total of 86,000 kilowatts. (See Table 
10-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance cost 
$7,053,258. Gross power generation amounted to 
174,154,000 kilowatt hours during FY 1992, of which 
171,510,000 kilowatt hours were delivered to Southeastern 
Power Administration. Recreational attendance at Lake 
Sidney Lanier during FY 1992 totaled 18,707,441 user 
days. 
Condition at end of fiscal year. Construction commenced 
in March 1950 and was completed in June 1960. 
The reservoir was in useful operation for flood control in 
February 1956. The first power generating unit was placed 
on the line June 19, 1957; the second on July 26, 1957; 
and the third on October 10, 1957. Total Federal cost 
under existing project as of September 30, 1992 is 
$53,028,418 for new work and $109,831,975 for maintenance, 
a total of $162,860,393. (See also Table 10-M.) 
54B. GEORGE W. ANDREWS LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 46.5 miles above its mouth and about one mile 
below the town of Columbia, Alabama, near the head of 
Jim Woodruff Reservoir. (See Geological Survey maps for 
southeast Alabama). The pool extends up the navigation 
channel about 28 miles upstream to Walter F. George 
Lock and Dam. 
Existing project. This single-purpose project provides 
for a concrete fixed-crest spillway 340 feet long extending 
into the right bank with a crest at elevation 102 feet national 
geodetic datum, a concrete gate spillway adjacent to 
the lock 280 feet long with crest at elevation 82 feet national 
geodetic datum, a single-lift lock with usable chamber 
dimensions of 82 feet by 450 feet, and a maximum lift 
of 25 feet. Depths are 13 feet over the lower sill and 19 
feet over the upper sill at normal pool elevation. The underlying 
foundation is limestone. The project provides for 
maintenance and care. The House Committee on Public 
Works, by resolution adopted May 19, 1953, approved the 
plan as proposed by the Chief of Engineers for a high dam 
at Walter F. George site and a low dam at the Fort Benning 
site and a high dam at the upper Columbia site, construction 
of which was authorized by the 1946 River and 
Harbor Act as the initiation and partial accomplishment of 
the plan for full development of the Apalachicola, Chattahoochee, 
and Flint River system. (See Table 10-B for 
authorizing legislation.) 
Local cooperation. Local interests must operate all 
movable span bridges, provide suitable public terminals, 
and hold the United States free from damages. These conditions 
are being complied with. 
Terminal facilities. At Columbia, Alabama, there is a 
public wharf with concrete deck for handling general 
cargo and a bulk petroleum terminal with an unloading 
10-28

MOBILE, ALABAMA, DISTRICT 
dock. Facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance of lock and 
dam cost $539,200. Maintenance cost included under 
overall Apalachicola, Chattahoochee and Flint project. 
Condition at end of fiscal year. Construction of the 
lock and dam began in March 1959 and was completed in 
November 1963 at a total cost of $13,038,427. (See also 
Table 10-M). 
54C. JIM WOODRUFF LOCK AND DAM, 
GA AND FL 
Location. The project is located on the Apalachicola 
River 107.6 miles above its mouth, about 1,000 feet below 
confluence of the Chattahoochee and Flint Rivers, and 1.5 
miles northwest of Chattahoochee, Florida. Reservoir extends 
about 46.5 miles upstream along the Chattahoochee 
River to the vicinity of Columbia, Alabama, and about 47 
miles upstream along Flint River, or 17 miles above 
Bainbridge, Georgia. (See Geological Survey maps for 
southwest Georgia.) 
Existing project. The existing project provides for a 
concrete open-crest spillway 1,634 feet long on the right 
bank, with a crest at elevation 79 feet national geodetic 
datum; a single-lift lock with usable chamber dimensions 
of 82 by 450 feet, a maximum lift of 33 feet, and depth 
over the sills of 14 feet; a gated spillway 766 feet long 
with the bridge at elevation 107 feet national geodetic 
datum, or about 67 feet above the streambed elevation; a 
powerhouse with an intake section constituting a portion 
of the dam; an earth section 506 feet long to accommodate 
the switchyard and substation; and an overflow dike section 
2,130 feet long on the left bank, with a crest at elevation 
85. The underlying foundation is limestone. At the 
normal pool elevation of 77, the reservoir has a total 
capacity of 406,160 acre-feet. The power installation consists 
of three units of 10,000 kilowatts each, or a total of 
30,000 kilowatts. (See Table 10-B for authorizing legislation.) 
Local cooperation. Required cooperation is being fulfilled. 
Easements for rights-of-way and spoil-disposal 
areas were provided as required along the Apalachicola 
River. Adequate public terminals were constructed by 
local interests at Bainbridge, Georgia, on the Flint River, 
and at Columbia, Alabama, on the Chattahoochee River. 
Facilities are being planned for other localities on the 
project. 
Terminal facilities. A public wharf with concrete deck 
for handling general cargo, a bulk storage terminal for 
petroleum, a grain elevator, and private riverside facilities 
at Bainbridge, Georgia, on the Flint River, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance cost 
$4,390,701. Gross power generation, Jim Woodruff 
Powerhouse, amounted to 217,482,000 kilowatt hours 
during FY 1992, of which 214,599,000 kilowatt hours 
were delivered to Southeastern Power Administration. 
Recreational attendance at Lake Seminole during FY 1992 
totaled 3,038,648 user days. 
Condition at end of fiscal year. Construction of the 
lock was commenced in 1947, and completed in 1957. The 
pool was opened to navigation in May 1954, and the pool 
was raised to project level in January 1957. The first 
power-generating unit was placed on-the-line on February 
1, the second on March 1, and the third on April 26, 1957. 
Total Federal cost under existing project as of September 
30, 1992 is $47,978,751 for new work and $75,600,212 
for maintenance, a total of $123,578,963. (See also Table 
10-M.) 
54D. WALTER F. GEORGE LOCK AND 
DAM, AL AND GA 
Location. The project is on the Chattahoochee River 
about 75.2 miles above its mouth and about 1.5 miles 
above Fort Gaines, Georgia. (See Geological Survey maps 
for southwest Georgia.) 
Existing project. The existing project provides for a 
concrete dam, gated spillway, and single-lift lock, with 
earth embankments at either side. The non-overflow section 
of the dam includes a powerhouse and an intake structure. 
The gated spillway is 708 feet long with a fixed crest 
at elevation 163 feet national geodetic datum. The two 
earth embankments, of almost equal lengths, have a total 
length of 12,128 feet, with a crest elevation at 215, and a 
maximum height of about 68 feet. The nonoverflow section 
of the concrete dam is 200 feet long, with the deck of 
the powerhouse section at elevation 208. The lock, with 
usable chamber dimensions of 82 feet by 450 feet, has a 
lift of 88 feet with the normal upper pool elevation at 190. 
Depths are 13 feet over the lower sill and 18 feet over the 
upper sill at normal pool elevation. The underlying foundation 
is limestone. Total reservoir capacity is 934,400 
acre-feet, with 244,000 acre-feet reserved for power. The 
power installation consists of four units of 32,500 
kilowatts each, or a total of 130,000 kilowatts. The project 
10-29

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
provides for maintenance, including operation and care. 
(See Table 10-B for authorizing legislation.) 
Local cooperation. Local interests must maintain and 
operate all utility and highway facilities which may be 
relocated or otherwise altered as part of the improvement, 
provide suitable public terminal facilities, and hold the 
United States free from damages. Local agencies and other 
organizations have indicated their willingness and ability 
to comply. 
Terminal facilities. Public wharves at Eufaula and 
Phenix City, Alabama, and Columbus, Georgia, are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance cost for FY 
1992 was $6,198,975. Gross power generation amounted 
to 410,322,000 kilowatt hours, of which 402,907,000 
kilowatt hours were delivered to Southeastern Power Administration. 
Recreational attendance during FY 1992 totaled 
6,777,326 user days. 
Condition at end of fiscal year. Construction was 
completed in 1963. The lock was opened to navigation in 
June 1963. The first power generating unit was placed onthe-
line in March, the second in May, the third in September, 
and the fourth in November 1963. Total Federal cost 
under existing project as of September 30, 1992 is 
$88,330,669 for new work, major rehabilitation cost 
$10,617,080 and $105,192,895 for maintenance, a total 
cost of $204,140,644. (See also Table 10-M.) 
54E. WEST POINT LAKE, 
CHATTAHOOCHEE RIVER BASIN, 
GA AND AL 
Location. The damsite is on the Chattahoochee River 
2.8 miles upstream from West Point, Georgia, 201.4 miles 
above the mouth of the Chattahoochee River, and 309.2 
miles above the mouth of the Apalachicola River. At the 
full power pool elevation of 635 feet above national 
geodetic datum, the reservoir would lie in Troup and 
Heard Counties, Georgia, and in Chambers and Randolph 
Counties, Alabama (See Geological Survey maps of Georgia 
and Alabama.) 
Existing project. The existing project provides for 
flood control, power, recreation, fish and wildlife development, 
and streamflow regulation for downstream navigation. 
The project provides for a gravity-type concrete dam 
896 feet long with earth embankments at either end 1,111 
feet long on the east end and 5,243 feet long on the west 
end. The total length of the dam and spillway is 7,250 feet. 
The main dam consists of a concrete non-overflow section, 
185 feet long on the west side and an earth embankment 
retaining wall on the east side; a gravity concrete spillway 
390 feet long, including piers and abutments, with six 
tainter gates, each 50 feet by 41 feet. A monolith intakepowerhouse 
section and erection bay 321 feet long is constructed 
directly west and adjacent to the spillway. At the 
full power-pool elevation of 635 the reservoir provides a 
total storage of 605,000 acre-feet of which 307,000 acrefeet 
is usable. During the critical flood season the reservoir 
is operated with maximum power pool elevation at 625 
feet to provide flood storage between elevations 625 and 
635. The initial power installation of 73,375 kilowatts consisting 
of units 1, 2 and 3 were placed in operation in 
March and April, 1975. The current installation is 108,375 
kilowatts. (See Table 10-B for authorizing legislation.) 
Local cooperation. None required. 
Operations and results during fiscal year. 
Maintenance: Operation and maintenance of the project 
totaled $4,504,052. Gross power generation amounted to 
189,328,000 kilowatt hours during FY 1992, of which 
183,273,000 kilowatt hours were delivered to Southeastern 
Power Administration. Recreational attendance during FY 
1992 totaled 7,950,378 user days. 
Condition at end of fiscal year. Construction of the 
project, which was initiated in June 1966, was essentially 
complete at the end of FY 1984. Total Federal cost under 
existing project as of September 30, 1992 is $131,565,287 
for new work and $61,463,730 for maintenance, a total of 
$193,029,017. (See also Table 10-M.) 
55. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Mobile District monitors flood control operations of 
Alabama Power Company's Weiss, H. Neely Henry, and 
Logan Martin Dams on Coosa River, Alabama, and their 
Lewis Smith Dam on Sipsey Fork (headwaters of Black 
Warrior River, Alabama), for compliance with regulation 
plans prepared in accordance with Public Law 436, 83rd 
Congress, and Federal Power Commission licenses. Fiscal 
year cost for these activities on the Weiss, H. Neely 
Henry, and Logan Martin Dams are included under operation 
and maintenance costs for the Alabama-Coosa Rivers. 
Fiscal year cost for the Lewis Smith Dam is included 
under the overall operation and.maintenance costs for the 
Black Warrior-Tombigbee Rivers System. 
10-30

MOBILE, ALABAMA, DISTRICT 
56. DEAUTHORIZED PROJECTS 
(See Table 10-G.) 
Miscellaneous 
57. FLOOD CONTROL AND 
COASTAL EMERGENCIES (FC & CE) 
Disaster Preparedness Program ........................... $451,959 
Emergency Operations..............................................38,006 
Rehabilitation............................................................62,903 
Total FC & CE $552,868 
58. NATIONAL EMERGENCY 
PREPAREDNESS PROGRAM (NEPP) 
Mobilization Preparedness.................................... $101,755 
Government Preparedness ........................................ 76,309 
Total NEPP $178,064 
59. REGULATORY FUNCTIONS 
PROGRAM 
Perm it Evaluation............................................... $1,573,663 
Enforcem ent ........................................................... 471,060 
Studies ........................................................................ 16,713 
Other Navigation Regulations ................................... 34,053 
Total Regulatory $2,095,489 
General Investigations 
60. SURVEYS 
During FY 1992, costs of $1,002,022 were incurred as 
shown below: 
HFlood Damage Preventive Studies........................ $823,161 
N avigation Studies....................................................48,812 
Interagency Water Resources Development ............ 18,459 
Special Investigations ............................................... 70,265 
Special Studies ............................................................. 0 
Coordination with Other Agencies, 
and non-Federal Interests..................38,928 
Federal Energy Regulatory Commission... ..... 1,477 
Miscellaneous Activities....................920 
Total Surveys $1,002,022 
61. COLLECTION AND STUDY OF 
BASIC DATA 
Collection and study of basic data continued during the 
fiscal year with the initiation of Flood Insurance studies, 
the cost of which was reimbursable by FEMA. In addition, 
HFlood Plain Management services were performed at a 
cost of $212,122. (See Table 10-P for listings of studies 
completed during FY 1992.) 
Costs incurred for hydrologic studies were $516 and 
miscellaneous cost of $0. 
62. ADVANCE ENGINEERING 
AND DESIGN 
Gulfport Harbor, MS. The authorized plan of improvement 
consists of modifying the existing ship channel 
to 36 x 300 feet in Mississippi Sound, and 38 x 400 feet 
across the bar, with changes in the channel alignment and 
the entrance to the anchorage basin for safe and unrestricted 
navigation. Dredged material disposal will be in 
the Gulf of Mexico. 
The General Design Memorandum (GDM) was completed 
in August 1989. Preparation of plans and specifications 
were completed in FY 1991. Fiscal year 1992 
expenditures for AE & D were $3,200. 
Pascagoula Harbor, MS. The authorized plan of improvement 
calls for: Deepening and widening the Gulf 
entrance channel to 44 x 550 feet, relocating that channel 
about 500 feet westwardly, and providing for future 
realignment as conditions warrant. Deepening the main 
ship channel in Mississippi Sound to 42 feet. Deepening 
and widening the Bayou Casotte Channel to 42 x 350 feet, 
and constructing a turning basin at the mouth of Bayou 
Casotte. Provide for bend widening for navigation and 
allow for reconfigurating the impoundment basin at the 
entrance channel. 
A resurvey of project economics and initial coordination 
on environmental issues were completed in FY 1991. 
Indications are that the project is economical. A letter of 
assurance was received from Jackson County Port 
Authority. The General Design Memorandum (GDM) was 
approved in June 1992. Preconstruction, Engineering and 
Design (PED) was completed in September 1992. The 
project is eligible for consideration for a construction new 
start in FY 1995. Fiscal year 1992 expenditures for AE & 
D were $228,789. 
10-31

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Fort Toulouse, AL. The authorized plan consists of a 
curved 4500-foot long cutoff within the inside of the bend 
opposite the unstable slope, 3600 feet of riprap protection 
on the outside of the curved channel, and closure of the 
existing river channel adjacent to the Fort and Indian 
Mounds with two (2) dikes, filled in between with dredged 
material. The recommended plan in the General Design 
Memorandum consists of approximately 1200 feet of 
riprap bank protection adjacent to the Fort and Indian 
Mounds with a 700-foot free standing stone dike from the 
Indian Mound downstream. 
Plans and Specifications were initiated in FY 1990 and 
construction initiated in FY 1991. Fiscal year 1992 expenditures 
for AE & D were $562. 
Panama City Beaches, FL. The authorized plan consists 
of the placement of a protective beach to elevation 4', 
with a storm berm to elevation 7' with an artificial dune 
system having a top width of 30 feet at elevation 15 and 
stabilized by vegetation. 
A comprehensive damage survey was completed during 
FY 1989 as part of the reevaluation effort. Preconstruction, 
Engineering and Design (PED) is currently 47% 
complete. A General Reevaluation Report (GRR) is 
scheduled for completion in December 1993, and PED in 
September 1994. Fiscal year 1992 expenditures were 
$588,843. 
Panama City Harbor. The authorized plan of improvements 
are the same as described in existing project 
(see Section 15 in text). Preconstruction Engineering and 
Design (PED) is currently 43% complete. A General 
Reevaulation Report (GRR) is scheduled for completion in 
October 1994 and PED in September 1996. Fiscal year 
1992 expenditures were $227,804. 
Total fiscal year 1992 expenditures for Advance Engineering 
and Design were $1,108,044. 
63. CONTINUATION OF 
PLANNING AND ENGINEERING 
Bayou La Batre, AL. The authorized plan for the 
project consists of an 18-foot deep channel from the turning 
basin within Bayou La Batre, extending into Mississippi 
Sound then along the Gulf Intracoastal Waterway 
alignment connecting with the existing Pascagoula ship 
channel. Extensions of the existing channel to above the 
Highway 188 bridge at a depth of 14 feet and into Snake 
Bayou at a depth of 12 feet are also incrementally justified. 
The Final Feasibility report was completed, and has 
been through all required Washington level review. The 
project was authorized in the 1990 Water Resources 
Development Act (WRDA). 
Preconstruction Engineering and Design (PED) work 
completed in September 1991. The contract for deepening 
the Sound chanel is scheduled for award in FY 1993. Fiscal 
year 1992 expenditures were $40,885. 
64. RIVERS AND HARBORS 
CONTRIBUTED FUNDS 
Contributed funds required for authorized Federal 
studies included $66,959 for Valley Creek, AL; $5,800 for 
environmental study at Dauphin Island, AL; and $2,996 
for flood plain management a total of $92,845 for contributed 
funds. 
10-32

MOBILE, ALABAMA, DISTRICT 
TABLE 10-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
Navigation 
1. Apalachi icola Bay 
FL 
2. Aquatic Plant 
Control 
(Contributed Funds) 
3. Bayou Coden, AL 
(Contributed Funds) 
(Contributed Funds) 
4. Bayou La Batre, AL 
(Contributed Funds) 
5. Biloxi Harbor, MS 
(Contributed Funds) 
(Contributed Funds) 
6. Black Warrior & 
Tombigbee Rivers, 
AL 
6A. Jackson Port 
Jackson, AL 
6B. Oliver Lock & Dam 
(Replacement), AL 
(Contributed Funds) 
7. Bon Secour River, 
AL 
(Contributed Funds) 
8. Dauphin Island, 
Bay, AL 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
76,000 
76,043 
45,000 
-7,398 
58,000 
52,161 
119,000 
119,415 
1,273,000 
1,268,893 
13,772,500 
13,982,154 
45,000 
67,537 
4,150,000 
12,017,726 
4,150,000 
11,988,032 
94,500 
93,934 
90,251 
88,880 
41,000 
46,598 
338,025 
338,234 
412,594 
410,833 
134,889 
136,753 
14,422,518 
14,305,196 
65,000 
58,259 
15,723,000 
14,107,605 
15,723,000 
14,129,908 
557,080 
551,939 
133,100 
123,010 
17,500 
40,589 
4,000 
5,301 
2,473 
142,000 
132,952 
16,575,000 
16,648,208 
136,000 
138,245 
5,891,000 
7,675,727 
5,891,000 
7,788,927 
40,000 
445,000 
441,544 
23,000 
34,558 
25,000 
5,877 
10,000 
420 
326,000 
225,523 
10,000 
10,024 
950,000 
930,720 
16,430,000 
16,229,632 
148,000 
104,401 
4,887,000 
4,405,068 
4,887,000 
4,393,130 
-8,000 
18,595 
1,755 
2,033,461i 
2,033,461 
4,013,0582 
4,012,778 
781,187 
727,588 
21,225 
21,225 
330,701 
330,701 
1,164,758 
1,150,567 
100,000 
100,000 
50,000 
50,000 
637,095 
536,618 
3,649,746 
3,649,737 
10,5004 
10,500 
1,431,9195 
1,431,9195 
10,898,1956 
10,866,9896 
102,600 
102,600 
238,640 
238,640 
88,461,9357 
88,461,935 
267,836,9948 
267,417,909 
52,292,880 
52,292,880 
514,000 
447,931 
56,607,000 
55,738,759 
57,698,000 
57,073,773 
150,615 
137,210 
1,386,258 
1,378,691 
9,700 
9,700 
292,864 
292,864 
10-33

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project 
9. Dog and Fowl 
Rivers, AL 
(Contributed Funds) 
10. East Pass Channel 
From Gulf of 
Mexico into Choctawhatchee 
Bay, FL 
(Contributed Funds) 
11. Fly Creek, AL 
12. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL 
and Mexican Border 
13. Gulfport Harbor, 
MS 
(Contributed Funds) 
14. Mobile Harbor, AL 
(Contributed Funds) 
15. Panama City 
Harbor, FL 
(Contributed Funds) 
16. Pascagoula Harbor, 
MS 
(Contributed Funds) 
17. Pensacola Harbor, 
FL 
(Contributed Funds) 
Funding 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp.. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Maint: 
Contrib. 
Cost 
FY89 FY90 FY91 FY92 
574,300 
569,979 
461,393 
464,840 
121,251 
120,788 
86,700 
86,873 
4,504 
104 
669,000 
635,698
- 
298,500 
298,700 
3,567 
I1,851 
19,500 
15,287 
101,000 
101,321 
30,000 
39,851 
2,522,000 
2,554,913 
3,540 
415,000 
415,393 
1,000,000 
14,295,571 
5,680,300 
6,146,522 
5,070,000 
5,277,168 
93,000 
94,424 
516,000 
520,634 
163,162 
417,737 
981,000 
978,543 
312,350 
297,587 
2,046,524 3,014,000 
1,955,771 2,991,923 
- 90,000 
- 68,125 
1,831,004 1,873,000 
1,828,231 1,823,602 
- 530,000 
- 236,070 
1,368,000 - 
5,004,390 339,755 
10,875,857 21,754,000 
10,813,901 21,686,655 
1,714,000 -421,000 
1,296,211 3,451 
59,979 590,000 
60,231 558,150 
4,098,972 1,728,000 
4,075,169 1,716,872 
179,000 218,000 
225,512 
52,020 45,000 
48,495 24,175 
10-34 
50,000 
43,379 
850 
155,000 
106,016 
1,000 
1,960,000 
1,994,862 
10,697,000 
10,291,666 
2,881,000 
2,801,508 
3,880,000 
3,833,647 
468,000 
629,610 
20,497,000 
20,425,295 
301,000 
20,000 
67,000 
97,885 
3,194,000 
3,152,528 
253,000 
458,131 
60,000 
72,239 
Total Cost to 
Sept. 30, 1992 
2,358,626 
2,351,505 
391,354 
391,354 
2,458,686 
2,457,726 
197,450 
195,250 
916,715 
916,715 
8,553,111 
8,470,020 
398,000 
398,000 
29,000 
29,000 
561,721 
559,907 
6,480 2999 
6,480,299' 
63,314,24610 
63,220,52910 
11,756,00011 
11,328,79011 
42,387 50212 
42,255,29512 
4,410,000 
4,069,717 
96,101,93513 
96,077,200' 
153,546,34014 
153,332,950' 
18,452,500 
18,170,860 
1,638,04515 
1,638,045 
9,068,01316 
9,066,11416 
80,000 
80,000 
6,572,98517 
6,572,98517 
50,414,59218 
50,336,544 
3,870,884 
3,788,266 
1,469,69319 
1,469,69319 
8,316,3582o 
8,300,4562" 
312,350 
297,587

MOBILE, ALABAMA, DISTRICT 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
18. Perdido Pass New Work: 
(Contributed Funds) 
19. Tennessee- 
Tombigbee 
Waterway 
AL and MS 
19A. Tenn-Tom Wildlife 
Mitigation 
Flood Control 
26. Boggy Bayou 
Valparaiso, FL 
(Contributed Funds) 
27. County Line 
Road Bridge, 
Itawamba Co., MS 
(Contributed Funds) 
28. Cribbs Mill Creek, 
Tuscaloosa, AL 
(Contributed Funds) 
29. Eslava Creek, 
Mobile, AL 
(Contributed Funds) 
30. Fort Toulouse 
Wetumpka, AL 
(Contributed Funds) 
31. Hurricane Creek 
Prentiss Co., MS 
(Contributed Funds) 
32. Mill Creek, 
Dalton, GA 
(Contributed Funds) 
33. Mill Creek, 
Sumrall, MS 
34. Mound State Park 
Moundville, AL 
(Contributed Funds) 
35. Murder Creek, 
Brewton, AL 
Channel, AL 
58,000 
57,732 
151,,100005,,00X1 
19,043,4C 
18,516,2E 
734,400 
733,503 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
Maint.: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work:: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
28,00 
84,000 
20,397 
31,000 
8,000 
85,000 
44,453 
1,435,000 
293,640 
25,500 
34,000 
14,278 
14,000 
10,000 
11,354 
21,300 
4,484 
215,536 
68,52 
,-o 
23,000 
1,555,000 
594,821 
170,000 
150,000 
1,095,000 
97,593 
150,000 
29,781 
14,000 
235,000 
212,803 
25,000 
25,000 
20,000 
30,920 
150,000 
67,392 
9,587 
1,149 
0 18,323,000 
5 8,428,941 
'9 17,984,000 
6 17,553,985 
0 14,481,000 
8 13,620,228 
0 125,200 
- 113,829 
- 16,900 
- 15,407 
- 6,000 
5 14,749 
760,711 
2,877 
1,210,353 
39,800 
82,504 
45,227 
1,000 
603 
534 
5,766 
7,167 
69,014 
8,659 
1,008,000 
988,999 
4,081,000 
12,976,662 
20,660,000 
21,229,316 
17,319,000 
16,342,226 
2,726 
1,274 
1,800 
2,891 
-2,891 
-2,891 
-100,000 
32,690 
55 
-938,900 
72,463 
236,000 
267,727 
193,000 
194,000 
-4,300 
1,108 
-1,108 
-1,108 
-10,000 
4,450 
63,540 
17,149 
578,000 
280,452 
106,000 
100,044 
-25,000 
629,860 
629,860 
7,808,217 
7,788,997 
510,000 
510,000 
10,325 
10,325 
1,035,202,20021 
1,030,087,22821 
160,963,83522 
160,724,56622 
37,000,000 
34,913,892 
153,200 
135,251 
16,900 
16,680 
116,800 
116,662 
28,109 
28,109 
1,924,327 
1,805,826 
170,000 
152,932 
3,040,221 
2,989,060 
235,800 
196,004 
386,000 
358,797 
194,000 
194,000 
52,803 
52,720 
12,892 
12,892 
490,000 
474,065 
25,000 
25,000 
151,340 
104,104 
728,000 
416,857 
106,000 
100,044 
1,215,000 
1,178,684 
10-35 
00 420,00 
15 7,184,96 
00 17,807,67 
61 19,614,11 
- 5,200,00 
- 4,951,43

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 10-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
36. Okatibbee Dam, New Work: 
MS Approp. - - - - 9,739,528 
Cost - - - - 9,739,528 
Maint.: 
Approp. 1,000,000 1,401,043 1,327,000 1,356,000 15,453,735 
Cost 1,057,387 1,347,393 1,182,180 1,397,215 15,272,708 
37. Portersville Bay-East New Work: 
Mobile Co., AL Approp. 30,000 - 75,000 30,000 115,000 
Cost 23,304 8,150 58,632 18,839 87,448 
(Contibuted Funds) New Work: 
Contrib. - - - 327,900 327,900 
Cost - - - 15,000 15,000 
38. Portersville Bay-West New Work: 
Mobile Co., AL Approp. - - - 30,000 30,000 
Cost - - - 9,674 9,674 
(Contributed Funds) New Work: 
Contrib. - - - 162,700 162,700 
Cost - - - - 
39. Proctor Creek New Work: 
Atlanta, GA Approp. 100,000 849,000 -81,000 -40,000 871,000 
Cost 4,361 735,047 1,838 67,622 850,243 
40. Raccoon Creek, New Work: 
Baconton, GA Approp. 261,000 - - -37,000 386,300 
Cost 46,637 195,886 7,184 4,432 380,645 
(Contributed Funds) New Work: 
Contrib. 35,000 - - - 35,000 
Cost - 35,000 - - 35,000 
41. Silver Creek, New Work: 
Rome, GA Approp. 15,000 336,000 29,000 - 609,000 
Cost 2,936 344,480 1,421 29,481 604,719 
42. Sowashee Creek, New Work: 
Meridian, MS Approp. 1,100,000 4,723,000 2,455,000 3,459,000 14,487,000 
Cost 1,553,805 4,487,799 2,634,125 3,048,651 13,658,299 
(Contributed Funds) New Work: 
Contrib. 290,000 388,000 431,000 - 1,599,000 
Cost 59,025 573,387 290,793 -116,711 931,493 
43. Tallahalla Creek, New Work: 
Laurel, MS Approp. 130,000 647,000 - -355,000 464,000 
Cost 46,312 102,326 24,434 52,525 241,365 
(Contributing Funds) New Work: 
Contrib. - 40,000 - - 40,000 
Cost - 40,000 - - 40,000 
44. Three Mile Creek, New Work: 
Mobile, AL Approp. -2,300,000 526,000 4,224,000 7,808,000 14,906,000 
Cost 912,533 460,018 3,418,602 7,271,007 13,285,884 
(Contributed Funds) New Work: 
Contrib. - - 235,000 516,000 1,216,000 
Cost 112,458 - 484,000 348,668 973,427 
45. Tombigbee River New Work: 
(East Fork) Approp. - - - - 134,801 
MS and AL Cost - - - - 134,801 
Maint.: 
Approp. 66,000 62,101 174,000 15,000 2,963,201 
Cost 66,102 56,408 160,044 16,062 2,943,885 
46. Tombigbee River New Work: 
Tributaries, Approp. - -208,000 496,000 331,000 25,184,825 
MS and AL Cost 1,291,495 714,310 427,592 362,221 25,110,746 
(Contributed Funds) New Work: 
Contrib. - - - - 94,700 
Cost - - - - 63,342 
47. Upper Gordon Creek, New Work: 
Hattiesburg, MS Approp. 250,000 - 50,000 60,000 827,000 
Cost 153,585 75,650 27,897 75,935 787,758 
48. Village Creek, New Work: 
Birmingham, AL Approp. 2,310,000 7,446,000 2,897,000 5,933,000 18,861,000 
Cost 2,071,571 5,050,071 5,184,999 5,558,379 18,102,071 
(Contributed Funds) New Work: 
Contrib. 647,000 2,059,710 1,420,000 2,045,000 6,171,710 
Cost 487,000 1,927,886 1,593,457 1,902,299 5,910,642 
10-36

MOBILE, ALABAMA, DISTRICT 
TABLE 10-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY 92 Sept. 30, 1992 
Multiple Purpose Projects, Lock and Dam 
52. Alabama-Coosa 
Rivers, AL and GA 
52A. Carters Dam and 
Reservoir, GA 
52B. Claibome Lock and 
Dam, AL 
52C. Coosa River, 
Montgomery to 
Gadsden, AL 
52D. Millers Ferry Lock 
and Dam, AL 
52E. Robert F. Henry 
Lock and Dam, AL 
53. Allatoona Dam 
Coosa River Basin, 
GA 
54. Apalachicola, 
Chattahoochee 
and Flint Rivers, 
AL and GA 
54A. Buford Dam 
Lake Sidney 
Lanier, GA 
54B. George W. Andrews 
Lock and Dam, 
AL and GA 
54C. Jim Woodruff Lock 
and Dam, GA and 
FL 
54D. Walter F. George 
Lock and Dam, 
AL and GA 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
Major Rehab.: 
Approp. 
Cost 
8,300,100 
8,392,210 
4,905,500 
4,958,589 
3,780,000 
3,917,320 
2,220,000 
2,289,096 
4,977,900 
5,267,320 
3,608,500 
3,633,107 
7,533,100 
8,015,948 
7,576,394 
7,521,290 
7,136,984 
7,108,541 
3,506,013 
3,484,108 
2,734,375 
2,713,471 
5,127,601 
5,058,313 
3,884,587 
3,862,405 
8,193,115 
8,001,686 
-
- 
30 
30 
5,728,500 
6,029,775 
7,421,000 
7,664,649 
1,111 
6,103,000 
5,780,640 
7,003,000 
6,950,332 
3,825,000 
3,552,091 
2,945,000 
2,944,225 
4,673,000 
4,375,042 
3,829,000 
3,635,119 
6,415,000 
6,386,380 
30 
30
- - 
4,589,017 4,521,000 
4,490,448 4,361,962 
- 47,000 
- 30,907 
8,534,233 5,932,000 
8,540,470 5,856,388 
- 165,000 
5,751 153,643 
10-37 
7,427,234 
7,568,519 
5,430,000 
5,412,945 
3,481,333 
3,681,102 
3,150,333 
2,947,285 
6,305,000 
6,281,198 
5,183,000 
5,150,973 
6,933,000 
7,053,258 
3,245,400 
3,245,400 
79,385,188_ 
79,105,813 
111,140,340 
111,140,340 
52,779,584 
52,559,743 
27,997,450 
27,997,450 
14,986 400 
14,986:40023 
63,125,300 
63,125,300 
49,245,211 
49,100,587 
83,360,800 
83,360,800 
32,284,861 
32,026,834 
35,709,085' 
35,709,085" 
85,588,824 
85,106,560 
4,452,162w 
4,452,162 
93,063 96427 
92,774,0602 
53,030,038a 
53,028,418 
110,042,622 
109,831,975 
13,038,42729 
13,038,42729 
30 
30 
47,978,85831 
47,978,75131 
75,887,397 
75,600,212 
88,330,66932 
88,330,66932 
105,367,597 
105,192,895 
10,642,000 
10,617,080 
-39,000 
4,345,000 
4,390,701 
-12,111 
3,983 
6,228,000 
6,198,975

TABLE 10-A 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
54E. West Point Lake, New Work: 
Chattahoochee River Approp. - - - - 131,568,76033 
Basin, GA and AL Cost 35,616 - - - 131,565,28733 
Maint.: 
Approp. 5,753,000 4,449,608 5,012,000 4,658,200 61,881,908 
Cost 5,771,673 4,499,341 4,826,791 4,504,052 61,463,730 
1. Includes $134,613 for previous projects and $28,500 for DPR on 
Two-Mile. 
2. Includes $168,766 for previous projects. 
3. Includes $5,650 for previous projects. 
4. Cost for providing spoil dikes for work authorized by 1965 River 
and Harbor Act. 
5. Includes $44,382 for previous projects of which $5,000 was 
contributed funds. 
6. Includes $96,509 for previous projects of which $10,200 was 
contributed funds. 
7. Includes $606,931 for previous projects and $1,243,661 for 
recreational facilities on completed projects. 
8. Includes $50,000 for previous projects. 
9. Includes $45,605 for previous projects. 
10. Includes $65,137 for previous projects. 
11. Includes $269,017 for previous projects. 
12. Includes $2,312,297 for previous projects and $442,836 Special O 
and M Funds. 
13. Includes $6,683,104 for previous projects, $14,000 Public Work 
funds, and $41,242 Emergency Relief funds. 
14. Includes $4,096,681 for previous projects and $494,136 Special O 
and M funds. 
15. Includes $203,560 for previous projects, $581,959 Public Works 
funds, $457,467 rehabilitation of jetties under existing project and $48,001 
for Grand Lagoon modification. 
16. Includes $513,604 for previous projects. 
17. Includes $904,442 for previous projects. 
18. Includes $412,624 for previous projects, $124,565 Special O and M 
funds, and $829,472 Emergency Work Funds. 
19. Includes $594,688 for previous projects. 
20. Includes $126,649 for previous projects. 
21. Includes $1,993,000 transferred to National Park Service; $210,249 
GI funds expended during FY 1957 thru FY 1961. Previous project cost 
amounted to $197,651. 
22. Includes $234,331 for previous projects. 
23. Includes $3,692,483 for previous projects. 
24. Includes $2,978,050 for previous projects. 
25. Includes $3,347,489 for recreational facilities. 
26. Includes $1,883,193 Federal funds, $1,924 contributed funds for 
previous projects; and $809,553 for Lazer Creek design and $301,310 for 
Rysco Channel. 
27. Includes $2,246,233 for previous projects. 
28. Includes $8,233,325 for recreational facilities. 
29. Includes $84,014 for recreational facilities. 
30. Included under maintenance for overall Apalachicola, 
Chattahoochee and Flint Rivers projects. 
31. Includes $1,515,822 for recreational facilities. 
32. Includes $2,441,029 for recreational facilities. 
33. Includes $35,045 for previous project costs. 
10-38

MOBILE, ALABAMA, DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Jan. 21, 1927 
Sep. 3, 1954 
Sep. 3, 1954 
Jul. 3, 1958 
Nov. 21, 19631 
Feb. 5, 19751 
Aug. 11, 19831 
Jul 3, 1958 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
Jun. 2, 19691 
Oct. 27, 1965 
APALACHICOLA BAY, FL (See Section 1 of Text) 
Channel 18 feet deep through West Pass and Link Channels. 
10 feet deep across the inner bar, and 9 feet deep 
through Bulkhead Shoals. 
Modify project to provide for channel 10 feet deep from 
mouth of inner bar channel to Gulf via Link and West 
Pass Channels, and 10-foot depth in Bulkhead Shoals 
Channel. 
At Eastpoint, Fl., a channel 6 feet deep, 100 feet wide, 
and about 6,000 feet long, parallel to shore, with 
connecting channel 6 feet deep and 100 feet wide to St. 
George Sound, and at Apalachicola, Fl., a small-boat 
basin 200 feet and 9 feet deep, with a connecting 
channel 9 feet deep and 80 feet wide through Scipio 
Creek to the Apalachicola River. 
Modify project to provide for a channel 10 feet deep and 
100 feet wide from the 10-foot depth in Apalachicola 
Bay across St. George Island to within 300 feet of the 
Gulf shore, thence increasing uniformly in width to 200 
feet at shore and continuing at this width to the 10-foot 
depth in the Gulf, with two jetties extending from the 
dune line on St. George Island to the outer end of 
channel, and for abandonment of West Pass Channel upon 
completion of channel through St. George Island. 
Modify improvement of Apalachicola Bay, Fl., authorized 
by River and Harbor Act of Sept. 3, 1954 to provide 
that the Secretary of the Army shall reimburse local 
interests for such approved work as they may have done 
based upon the reduction in the amount of material 
which will have to be removed to provide project 
dimensions at such time as Federal dredging of the 
channel is undertaken. 
A channel 6 feet deep, 100 feet wide and about 1 mile long, 
parallel to shore at Two Mile, Fl., with a 6-by 100-foot 
connecting channel to water of the same depth in 
Apalachicola Bay. 
A channel 6 feet deep and 100 feet wide extending from the 
eastern end of the existing Two Mile channel and 
generally paralleling the shoreline for a distance of 
about 9,000 feet to intersect with the Gulf Intracoastal 
Waterway about 1,650 feet south of Gorrie Bridge at 
Apalachicola, and a breakwater built to elevation 4.0 
feet above mean low water along the seaward side of the 
existing channel parallel to the shore at Two Mile. The 
total length of the breakwater of about 6,150 feet, 
includes two 860-foot legs paralleling the existing 
entrance channel. 
Modify Eastpoint project to include breakwaters with a 
total length of 5,300 feet. 
AQUATIC PLANT CONTROL (See Section 2 of Text) 
Aquatic plant control for N.C., S.C., Ga., Fl., Al., Ms., 
and La. 
Research and planning costs to be borne by U.S. 
Provided for continued research. 
BAYOU CODEN, AL (See Section 3 of Text) 
Channel 4 by 40 feet 
Channel 8 by 60 feet to connect with Bayou La Batre 
channel. 
BAYOU LA BATRE, AL (See Section 4 of Text) 
A 12- by 100-foot channel from that depth in Mississippi 
Sound to a point about 2,800 feet south of the highway 
bridge, thence a channel 12 by 75 feet to the bridge, an 
overall distance of about 33,500 feet. 
10-39 
TABLE 10-B 
H. Doc. 422, 59th Cong., 
1st Sess. 
H. Doc. 106, 69th Cong., 
1st Sess. 
H. Doc. 156, 82d Cong., 
1st Sess. 
H. Doc. 557, 82d Cong., 
2d Sess. 
DPR(Sec. 107) 
DPR (Sec. 107) 
DPR (Sec. 107) 
H Doc 37, 85th Cong., 
1st Sess. 
Public Law 87-874 
87th Cong. 
H. Doc. 251, 89th Cong., 
1st Sess. 
H. Doc. 824, 77th Cong., 
2d Sess. 
DPR (Sec 107) 
H. Doc. 327, 88th Cong., 
2d Sess.

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 28, 1990 
Jul. 3, 1930 
Jun 20, 1938 
Mar. 2, 1945 
Mar. 2, 1945 
May 17, 1950 
Jul. 14, 1960 
Nov. 7, 1966 
Mar. 28, 19791 
Aug. 15, 1985 
Jul. 5, 1884 
Mar. 3, 1899 
Sep. 19, 1890 
Sep. 19, 1890 
Mar. 2, 1907 
Mar. 3, 1909 
Aug. 22, 1911 
Mar. 2, 1919 
Aug. 30, 1935 
Deepen existing channel to 18 feet to the bridge; to 14 feet 
above bridge, and into Snake Bayou at a depth of 12 feet. 
BILOXI HARBOR, MS (See Section 5 of Text) 
Channel 10 feet deep and 150 feet wide from Mississippi 
Sound west and north of Deer Island to deep water in 
Back Bay of Biloxi 
Relocation of channel. 
Entrance channel 6 feet deep and 50 feet wide into Old 
Fort Bayou. 
Entrance channel 8 feet deep and 100 feet wide through 
Cranes Neck into Bayou Bernard. 
Maintain channel 6 feet deep and 40 feet wide from Biloxi 
Harbor to Ott Bayou. 
Continuous channel 12 feet deep from Mississippi Sound 
the Air Force terminal on Bayou Bernard via Back Bay 
and Cranes Neck. 
A 23-mile-long through channel 12 feet deep and 150 feet 
wide from the Gulf Intracoastal Waterway through: 
Mississippi Sound, Biloxi Bay (east of Deer Island), Back Bay, 
Big Lake, and via land cut to Gulfport Lake, including a 500 
by 2,600-foot turning basin in the lake, thence, a channel 
12 by 100 feet from the western end of Gulfport Lake for 
about 2 miles to a 300-by 500- foot turning basin; adoption 
for maintenance of a 12- by 150 foot spur channel from themain 
channel in Biloxi Bay, westward about 1 mile to a 
400-by 600- foot turning basin opposite Ott Bayou, and 
abandonment of the existing 6-by 40- foot channel into 
Ott Bayou; continuation of maintenance of the 12- by 150- 
foot lateral channel westward about 2.2 miles from the main 
channel in Biloxi Bay to a point opposite Oak Street; coninuation 
of maintenance of the channel west of Deer Island. 
A channel 10 feet deep; 100 feet wide and 300 feet long extending 
northward from the Biloxi Lateral Channel and, into a rectangular 
basin approximately 300 feet by 370 feet. 
A channel 12-feet deep; 130-feet wide and 2,100-feet long, and a 
300 by 300 foot turning basin also to a 12-foot depth. 
BLACK WARRIOR AND TOMBIGBEE RIVERS, AL 
(See Section 6 of Text) 
Original appropriation for improving Black Warrior River. 
Original project for slack-water improvement authorized by 
Secretary of War, Apr. 19, 1887 
Construction of the first locks between Tuscaloosa and Demopolis. 
(Maintenance of the section of Tombigbee River below 
lock 1 to its mouth (66 miles) included in the existing project.) 
Construction of locks and dams 1, 2, and 3. Merging of 
the individual project for the Black Warrior and Warrior 
Rivers and the Tombigbee River below Demopolis. 
Construction of locks and dams 14, 15, 16, and 17. 
Provides for reconstruction of obsolete structures, modified 
in plan and location, to provide efficient and economical 
maintenance and operation. 
Lift of lock 17 changed to 63 feet, and construction of locks 
and dams 18 and 19 eliminated from the project. 
Extension of slack-water improvement to Sanders Ferry 
on Mulberry Fork and Nichols Shoal on Locust Fork. 
Raising of various dams 2 feet and raising the lock walls 2 
feet at lock 1 to provide a minimum depth of 8 feet at 
low water, widening the channel to 150 feet where 
practicable. 
For snagging Mobile River from the mouth of Chickasaw 
Creek to the junction of the Alabama and Tombigbee Rivers. 
10-40 
Water Resources 
Development Act 
of 1990 (P.L. 101-640) 
H. Doc. 754. 69th Cong., 
2d Sess. 
H. Doc. 639.75th Cong., 
3d Sess. 
H. Doc. 258.76th Cong., 
1st Sess. 
H. Doc. 326.76th Cong., 
1st Sess. 
H. Doc. 256. 81st Cong., 
1st Sess. 
H. Doc. 271, 86th Cong., 
2d Sess. 
H. Doc. 513, 89th Cong., 
2d Sess. 
DPR (Sec. 107) 
DPR (Sec. 107) 
Annual Report, 1887, 
pt. 2, p. 1302. 
H. Doc. 178, 56th Cong., 
2d Sess., and Annual 
Report, 1901, pt. 3, 
p. 1858 
H. Doc. 165, 57th Cong., 
1st Sess., and Annual 
Report, 1902, p. 1293 
Public Law 317 
H. Doc. 72, 62d Cong., 
1st Sess. 
Annual Report, 1918, 
p. 876 
H. Doc. 728, 71st Cong., 
3d Sess.

TABLE 10-B (Continued) 
MOBILE, ALABAMA, DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 
Aug. 30, 1935 
Jun. 26, 1934 
Dec. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 14, 1960 
Dec. 21, 1982 
Jul. 30, 1983 
Nov. 17, 1986 
Nov. 17, 1986 
Oct. 18, 1986 
Aug. 15, 1985 
Nov. 17, 1986 
May 16, 19631 
Mar. 2, 1945 
Sep. 3, 1954 
Aug. 16, 1991 
Increase channel dimensions to 9 by 200 feet; construct 
crest gates at lock and dam 17; add flashboards at all 
dams; Sunflower Bend Cutoff. 
Construction of a lock and dam below Tuscaloosa to replace 
original locks and dams 10, 11, and 12 
Operation and care of locks and dams provided for with 
funds from War Department appropriations for rivers harbors. 
Recreation facilities. 
Construction of a lock and dam near Demopolis to replace 
existing dams 4, 5, 6, and 7. 
Provide increased spillway capacity at dam 1. 
Coffeeville Lock and Dam Wildlife Refuge. 
Provides for a wider navigation opening at the Franklin 
Ferry Bridge, Jefferson County, Al. 
Authorized to widen, as necessary for safe passage. 
the navigation opening of Franklin Ferry Bridge, Jefferson County, Al. 
Conduct a feasibility study of protection 
from erosion problems on the southern bank from 
river mile 253 to river mile 255. 
MOUND STATE PARK (See Section 38 of Text) 
Correct erosion problems along the 
banks of the Warrior River in order to 
protect Mound State Park, near 
Moundville, Alabama. 
JACKSON PORT, AL (See Section 6A of Text) 
Construct a spur canal 9 feet deep, 280 feet wide, and 680 
feet long in conjunction with the realignment project on 
the existing navigation project. (Jackson Port) 
OLIVER LOCK AND DAM (REPLACEMENT), AL 
(See Section 6B of Text) 
Construction and land acquisition for Oliver Lock 
Replacement 
Construction of a lock and dam to replace the 
William Bacon Oliver Lock and Dam. 
BON SECOUR RIVER, AL (See Section 7 of Text) 
A 10-by 100-foot channel from Gulf Intracoastal Waterway through 
Bon Secour Bay to mouth of Bon Secour River and extending up 
river to vicinity of Swift's Landing, thence 6 by 80 feet up river to a 
point 600 feet above Oak Landing, with two turning and maneuvering 
areas 150 feet wide and 1,100 to 1,200 feet long opposite Swift's 
Landing and ice loading dock. Overall length of improvement is about 4.7 miles. 
DAUPHIN ISLAND BAY, AL (See Section 8 of Text) 
A channel 7 feet deep and 150 feet wide from Mobile Bay to 
an anchorage basin of same depth, about 7 acres in area, in 
marsh just north of Fort Gaines on Dauphin Island; a 
channel 4 feet deep and 40 feet wide from anchorage basin 
to Dauphin Island Bay; and a jetty and revetment to protect 
entrance channel; and (b) an anchorage basin 7 feet deep and 500 
feet square at Dauphin Island Village, with an entrance channel 
of like depth, 100 feet wide and about 8,300 feet long, 
extending to 7-foot hydrographic contour in Mississippi Sound. 
Deepen existing 4-foot channel to 7-feet and 40-feet wide from 
anchorage basin to Dauphin Island Bay. 
10-41 
H. Doc. 56, 73d Cong., 
1st Sess., and Rivers 
and Harbors Committee 
Doc. 45.73d Cong. 
Rivers and Harbors 
Committee Doc. 26. 
74th Cong., 1st Sess. 
H. Doc. 276, 76th Cong., 
1st Sess. 
H. Doc. 382, 76th Cong., 
1st Sess. 
S. Doc. 50, 86th Cong., 
1st Sess. 
Public Law 97,377 
Public Law 98-63 
Water Resource Development 
Act of 1986 
(P.L. 99-662) 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
Energy and Water 
Development Appropriation 
Act 1987 
(P.L. 99-591) 
The Supplemental 
Appropriations Act, 
1985 (P.L. 99-88) 
Water Resources 
Development Act of 
1986 (P.L. 99-662) 
DPR (Sec. 107) 
H. Doc. 333, 76th Cong., 
1st Sess. 
H. Doc. 394, 82d Cong., 
2d Sess. 
DPR (Sec. 107)

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 19, 19691 
Jul. 3, 1930 
Oct. 24, 1951 
Oct. 27, 1965 
Oct. 1, 1980 
May 17, 1950 
Jun. 25, 1910 
Aug. 30, 1935 
Jun. 25, 1910 
Aug. 30, 1935 
Jul. 3, 1930 
Jul 3, 1930 
Jul 3, 1930 
Jul 23, 1942 
Jun. 17, 1943 
Mar. 2, 1945 
May 17, 1950 
Nov. 7, 1966 
Mar. 3, 1899 
DOG AND FOWL RIVERS, AL (See Section 9 of Text) 
To provide small craft navigation on west side of Mobile Bay. 
EAST PASS CHANNEL FROM GULF OF MEXICO INTO 
CHOCTAWHATCHEE BAY, FL (See Section 10 of Text) 
Maintenance of 6-foot channel by 100-foot channel from 
Choctawhatchee Bay into Gulf. 
Maintenance of 12-foot channel from Choctawhatchee Bay 
into Gulf, and maintenance of 6-foot channel into Old Pass Lagoon. 
Construction of twin jetties. 
(Present project dimensions.) 
Modifications to provide a channel length of approximately 3,800 
feet in lieu of 2,000 feet from the East Pass Channel into 
Old Pass Lagoon, with no changes in width and depth. 
FLY CREEK, FAIRHOPE, AL (See Section 11 of Text), 
A channel 6 feet deep, 80 feet wide, and about 1,650 
feet long from 6-foot depth in Mobile Bay to a turning 
basin of same depth, 100 feet wide and 350 feet long, in Fly Creek. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL, AND MEXICAN BORDER 
(Mobile District) (See Section 12 of Text) 
APALACHICOLA RIVER TO ST. ANDREW BAY, FL 
A channel 5 feet deep at mean low water and 65 feet 
wide at the bottom. 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
CHOCTAWHATCHEE BAY TO WEST BAY, FL 
A channel 9 feet deep at mean low water and 100 feet wide 
at the bottom. 
A channel 6 feet deep at mean low water, with no 
reference to width. 
CHOCTAWHATCHEE BAY TO PENSACOLA BAY, FL 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
PENSACOLA BAY, FL., TO MOBILE BAY, AL 
A channel 9 feet deep at mean low water and 100 feet 
wide at the bottom. 
MOBILE BAY, AL, TO NEW ORLEANS, LA 
A channel 300 feet wide and 10 feet from the 10 
foot contour in Mobile Bay to the 10-foot contour 
in Mississippi Sound. 
A channel 100 feet wide and 9 feet deep from Lake 
Pontchartrain to Mississippi Sound. 
APALACHEE BAY, FL, TO NEW ORLEANS, LA 
A channel 12 feet deep and 125 feet wide at mean low 
water, except in the section between Mobile, Al., 
and New Orleans, La., where the width is to be 
150 feet. 
Conditional acquisition of Gulf County Canal, Fl. 
and enlargement of the canal to 9 feet deep and 100 
feet wide. 
Construction of a movable span in the Georgia, Florida 
& Alabama R.R. bridge crossing the Ochlockonee River. 
Abandonment and closure of original channel between 
Big Lagoon and Pensacola Bay and construction of a 
new channel to enter the bay north of original 
entrance. 
Authorized enlargement of Gulf County Canal to 12 by 
125 feet. 
GULFPORT HARBOR, MS (See Section 13 of Text) 
A channel 19 feet deep and 300 feet wide from the 
anchorage basin at Ship Island to Gulfport, Ms., and an 
anchorage basin next to the shore end 19 feet deep and not 
less than 2,640 feet by 1,320 feet in area. 
10-42 
DPR (Sec. 107) 
H. Doc. 209, 70th Congress 
1st Sess. 
H. Doc. 470, 81st Cong., 
2d Sess. 
H. Doc. 194, 88th Cong., 
2d Sess. 
Energy and Water Development 
Appropriation 
H. Doc. 194, 81st Cong., 
1st Sess. 
H. Doc. 670, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 52, 
72d Cong., 2d Sess. 
H. Doc. 259, 72d Cong., 
1st Sess. 
H. Doc. 565, 61st Cong., 
2d Sess. 
Rivers and Harbors 
Committee Doc. 42, 
73d Cong., 2d Sess. 
H. Doc. 42, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
71st Cong., 1st Sess. 
H. Doc. 341, 71st Cong., 
2d Sess. 
Public Law 675, 77th 
Cong., 2d Sess., and 
H. Doc. 96, 79th 
Cong., 1st Sess. 
H. Doc. 257, 76th Cong., 
1st Sess., and Public 
Law 75, 78th Cong. 
1st Sess. 
H. Doc. 442, 76th Cong., 
1st Sess. 
H. Doc. 325, 81st Cong., 
1st Sess. 
Public Law 89-789, 89th 
Cong. 2d Sess. 
H. Doc. 120, 55th Cong., 
3d Sess.

TABLE 10-B (Continued) 
MOBILE, ALABAMA, DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1907 
Feb. 27, 1911 
Jan. 21, 1927 
Jul. 23, 1930 
Jun. 30, 1948 
Jul. 3, 1958 
Aug. 15, 1985 
Nov. 17, 1986 
Nov. 17, 1988 
Aug. 26, 1937 
Mar. 2, 1945 
Sep. 3, 1954 
Sep. 3, 1954 
Jul. 26, 1970 (SR) 
Dec. 15, 1970 (HR) 
Combined Ship Island Pass with Gulfport Harbor project. 
Increased depth to 26 feet and width to 300 feet across 
Ship Island Bar and depth to 19 feet in channel from 
anchorage basin at Ship Island to anchorage basin at Gulfport. 
Authorized relocation of channel across Ship Island Bar. 
Increased depth to 27 feet and width to 300 feet across Ship 
Island Bar, 26 feet deep and 220 feet wide through Ms. 
Sound and depth of 26 feet in the anchorage basin at Gulfport. 
Increased depth of 32 feet and width to 30 feet across Ship 
Island Bar, 30 feet deep and 220 feet wide through Ms. Sound 
and a depth of 30 feet in the anchorage basin at Gulfport. 
Maintenance of the existing commercial small-boat harbor 
and an approach channel 100 feet wide and 4,300 feet 
long, from deep water in Ms. Sound to the small-boat 
basin, all at a depth of 8 feet. 
Modify the existing Ship Channel to 36 x 300 feet in Mississippi 
Sound, and 38 x 400 feet across the bar, with 
changes in the channel alignment and the entrance to 
the anchorage basin for safe and unrestricted navigation. 
Modification of FY 1985 Supplemental Appropriations Act. 
Dredged material from project shall be disposed of in 
open water in the Gulf of Mexico in accordance with all 
provisions of Federal law. 
Modify the WRDA of 1986 and authorize 
disposal of dredged material in open waters 
of the Gulf of Mexico; and by Thin-layer disposal 
in Mississippi Sound under a demonstration program. 
MOBILE HARBOR, AL (See Section 14 of Text) 
For improvement of Threemile Creek by snagging from 
Mobile River to the Industrial Canal. 
Adoption of existing channel through Garrows Bend from 
Choctaw Point to Arlington pier, 27 feet deep and 150 
feet wide, with 2 turning basins. Adoption of the 
existing channel alongside Arlington pier from the 
of Garrows Bend Channel, 27 feet deep and 150 feet wide. 
A channel 25 feet deep and generally 500 feet wide in 
Mobile River from the highway bridge to the mouth of 
Chickasaw Creek, then 25 feet deep and 250 feet wide in 
Chickasaw Creek to a point about 400 feet below Shell Bayou. 
Enlarging Mobile Bay Channel to 42 by 600 feet, 
Enlarging Mobile Bay Channel to 40 by 400 feet. 
Deepening Mobile River Channel below highway bridge to 
40 feet over present widths, including existing 
turning basins and anchorage areas. Widening river 
channel opposite Magazine Point to provide a 40- by 800- 
by 1,400-foot turning basin. The turning basin was 
further modified for maintenance by SAD letter of 
27 November 1973 under authority contained in 
ER-1130-2-307 to increase the turning basin's 
dimensions to 1000' x 1600'. 
Closure of Garrows Bend Channel by construction and 
operation of an earth-filled causeway across said channel 
(work to be done by local interests). 
To provide a channel 40 feet deep and 400 feet wide from 
the main ship channel in Mobile Bay and extending 
northwesterly for about 53 miles to the shore of Mobile 
Bay including an anchorage and turning basin 
near the shoreline, thence a land-cut 40 feet deep, 300 feet 
wide and about 1.9 miles long to and including a 
trapezoidal turning basin 40 feet deep and 
approximately 42 acres, 40 feet deep; a barge channel 
12- by 100-feet extending 6500-feet and terminating in a 
300-foot by 300-foot terminal basin 
H. Doc. 2, 60th Cong., 
1st Sess. 
H. Doc. 692, 69th Cong., 
2d Sess. 
H. Doc. 112, 81st Cong., 
1st Sess. 
S. Doc. 123, 84th Cong., 
2d Sess. 
The Supplemental 
Appropriations 
Act, 1985 (P.L. 99-88) 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
Water Resources 
Development Act 
of 1988 
(P.L. 100-676) 
Rivers and Harbors 
Committee Doc. 69, 
74th Cong., 1st Sess. 
H. Doc. 739, 79th Cong., 
2d Sess. 
H. Doc. 74, 83d Cong., 
1st Sess. 
H. Doc. 74, 83d Cong., 
2d Sess. 
(Under provision of 
Section 201 of the 
1965 Flood Control 
Act) 
10-43

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
OF THE CIVIL WORKS ACTIVITIES FOR FY 1992 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 15, 1985 
Nov. 17, 1986 
Nov. 17, 1986 
Aug. 30, 1935 
Mar. 2, 1945 
Jun. 30, 1948 
Mar. 23, 19671 
Jun. 14, 1972 
Mar. 4, 1913 
Mar. 4, 1915 
May 17, 1950 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 14, 1960 
Jul. 14, 1967 
Oct. 23, 1962 
Deepen and widen entrance channel over the bar to 57 by 
700 feet, a distance of about 7.4 miles, deepen 
and widen Mobile Bay Channel from mouth of 
bay to south of Mobile River, 55 by 550 feet, a distance 
of about 27.0 miles, deepen and widen an additional 
4.2 miles of Mobile Bay Channel to 55 by 650 feet, 
provide 55 foot deep anchorage area and turning 
basin in vicinity of Little Sand Island, and construct 
a 1710 acre disposal area adjacent to the Brookley 
Industrial Complex. 
Modification of FY 1985 Supplemental Appropriations Act. 
Dredged material from project shall be disposed of in 
open water in the Gulf of Mexico in accordance with all 
provisions of Federal law. 
PANAMA CITY BEACHES, FL 
Shoreline protection to provide a 110-foot 
wide beach with an artificial dune system 
and stabilization of vegetation. 
PANAMA CITY HARBOR, FL (See Section 15 of Text) 
Channels 27 and 29 feet deep. Abandonment of project 
adopted by act of June 25, 1910. 
Maintenance of a channel in Watson Bayou 100 feet wide 
and 10 feet deep from that depth in St. Andrew Bay to 
the highway bridge. 
Channels 32 and 34 feet deep. 
A channel 8 by 100 feet in Grand Lagoon from St. Andrew 
Bay to a point about 2,400 feet east of State Highway 
392. Bridge with branches to serve shore facilities 
which terminate at the bridge. 
Channels 38, 40,42 feet deep. 
PASCAGOULA HARBOR, MS (See Section 16 of Text) 
Provides for through channel from the Gulf to mile 4 on 
Dog River, 25 by 300 feet through Horn Island Pass. 
thence 22 by 225 feet across Mississippi Sound and up 
150 feet in Pascagoula River above bridge, and up Dog 
River to mile 4, all subject to financial participation 
by local interests. 
Waived requirement for financial participation by local 
interests. 
Cutoff channel, 12 by 125 feet, from State Highway 63 
bridge to mile 4 on Dog River, via Robertson and 
Bounds Lakes. 
Modification to provide for channel dimensions of 35 by 
325 feet through Horn Island Pass, thence 30 by 275 feet 
across Mississippi Sound and up Pascagoula River to the 
railroad bridge, and a turning basin just below the 
bridge. 
Reimbursement of local interests for work done on Dog 
River cutoff ($44,000). 
Modification to provide for maintenance of 12- by 125-foot 
channel to mile 6 on Dog River, and maintenance of 30- by 
225-foot side channel from main ship channel in 
Mississippi Sound to the mouth of Bayou Casotte, thence 
30 by 300 feet in Bayou Casotte to a turning basin of the 
same depth 1 mile above the mouth. 
Deepening the Horn Island Pass channel to 38 feet and 
deepening the main ship channel in Mississippi Sound, 
the river channel to the railroad bridge, and the 
turning basin all to 33 feet. 
Enlarging Horn Island Pass Channel to 40 by 350 feet 
provision of an impounding area adjacent to and east of 
channel 40 feet deep, 200 feet wide, and about 1,500 feet 
10-44 
The Supplemental 
Appropriations Act, 
1985 (P.L. 99-88) 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
Water Resources Development 
Act of 1986 
(P.L. 99-662) 
H. Doc. 33, 73d Cong., 
1st Sess. 
H. Doc. 555, 76th Cong., 
3d Sess. 
H. Doc. 559, 80th Cong., 
2d Sess. 
DPR (Sec. 107) 
H. Doc. 196, 92d Cong., 
2d Sess. 
H. Doc. 682, 62d Cong., 
2d Sess. 
River and Harbor 
Committee Doc. 12, 
63d Cong., 2d Sess. 
H. Doc. 188, 81st Cong., 
1st Sess. 
H. Doc. 98, 86th Cong., 
H. Doc. 98, 86th Cong., 
1st Sess. 
Chief of Engineers Report 
dated Nov. 3, 1960. 
H. Doc. 560, 87th Cong., 
2d Sess.

TABLE 10-B (Continued) 
MOBILE, ALABAMA, DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 11, 19831 
Nov. 17, 1986 
Jun. 13, 1902 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 27, 1962 
Oct. 27, 1965 
Jul. 24, 1946 
long, enlarging main channel in Mississippi Sound and 
river channel to railroad bridge to 38 by 350 feet, and 
deepening turning basin in river and Bayou Casotte 
channels and basin to 38 feet. 
Modification to provide for channel dimensions 12 x 80 feet 
extending about 2,750 feet from deep waters in the 
Pascagoula River into Krebs Lake to a turning basin, 
thence, along the south bank of the lake a channel with 
dimensions of 10 x 60 feet terminating at a second 
turning basin, a distance of about 2,750 feet. The 
project was constructed by hydraulic dredging with 
the disposal placed in an unpland diked area. 
Deepen and widen gulf entrance channel to 44 by 550 feet; 
widen Horn Island channel to 600 feet, relocating that 
channel about 500 feet westwardly; deepen Mississippi Sound 
portion to 42 feet; widen and deepen Bayou Casotte to 42 
350 feet and construct turning basin. Disposal of all new 
work material in Gulf of Mexico. 
PENSACOLA HARBOR, FL (See Section 17 of Text) 
A channel 30 feet deep at mean low water and 500 feet 
wide from the Gulf of Mexico to the dock line at the 
east end of the city of Pensacola, and also provided 
that $150,000 may be used in constructing or purchasing 
a seagoing suction dredge. 
Modified the existing project for the present inner 
channels and the deepening of the entrance channel to 32 feet. 
Improvement of Bayou Chico. 
Maintenance of the entrance channel from the Gulf of 
Mexico to lower Pensacola Bay, a distance of about 5 
miles to dimensions of 35 feet deep and 500 feet wide; 
maintenance of a channel along the south side of the 
aircraft carrier mooring basin, a distance of about 2.5 
miles, to dimensions of 33 feet deep and 300 feet wide; 
a bay channel 33 feet deep, 300 feet wide, and about 2.1 
miles long; parallel approach channels to opposite ends 
of the inner-harbor channel, about 13 and 1.4 miles in 
length, each 33 feet deep, 300 feet wide, and flared at 
the junctions with the inner-harbor channel; and 
deepening the existing 500-foot wide inner-harbor channel 
to a depth of 33 feet and lengthening it to 3,950 feet, 
PERDIDO PASS CHANNEL, AL (See Section 18 of Text) 
A 12- by 150-foot channel stabilized by twin rubblemount 
jetties, from the Gulf of Mexico into Perdido Pass, 
thence 9 by 100 feet into Perdido Bay with a spur channel 
of the same dimensions into Terry Cove. 
TENNESSEE-TOMBIGBEE 
WATERWAY, AL AND MS (See Section 19 of Text) 
A waterway connecting Tennessee and Tombigbee Rivers via 
East Fork of Tombigbee River, Mackeys and Yellow Creeks. 
Plan of improvement consists of three sections: river section 
9- by 300-foot channel for 149 miles between Demopolis 
and Amory, Ms.; canal section, 12 by 300 feet for 46 miles 
from Amory to Bay Springs; divide section 12 by 300 feet 
(except in the 27 mile-long divide cut in which bottom width 
be 280 feet) for 39 miles from Bay Springs through dividing 
ridge to Tennessee. Total lift of 341 feet to be accomplished 
by 10 locks. Total length of project is 234 miles. 
10-45 
DPR (Sec. 107) 
Water Resources Development 
Act of 1986 
(P.L. 99-662) 
H. Doc. 253, 72d Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 96, 
74th Cong., 2d Sess. 
H. Doc. 528, 87th Cong., 
2d Sess. 
H. Doc. 94, 88th Cong., 
2d Sess. 
H. Doc. 486, 79th Cong., 
2d Sess.

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 17, 1986 
May 4, 19904 
Oct. 7, 19884 
Nov. 17, 19872 
Sep. 10, 19872 
Nov. 17, 1986 
Oct. 7, 19884 
Oct. 13, 19882 
Mar. 14, 19902 
Apr. 18, 19862 
Oct. 23, 1962 
Sep. 27, 19904 
Sep. 27, 19904 
Jan. 10, 19892 
Oct. 13, 19882 
Jan. 10, 19892 
Nov. 17, 1986 
TENNESSEE-TOMBIGBEE WILDLIFE MITIGATION 
Acquire from willing sellers in a timely manner at fair 
market value 88,000 acres of land for mitigation of wildlife 
losses resulting from construction and operation of the 
project for the Tennessee-Tombigbee Waterway. 
BOGGY BAYOU, VALPARAISO, FL (See Section 26 of Text) 
Provide bank protection along 700-feet of shoreline and preclude possible 
destruction of Bayshore Drive and utilities. 
COUNTY LINE ROAD BRIDGE, ITAWAMBA CO., MS 
(See Section 27 of Text) 
Provides protection for both banks and the channel at the bridge 
crossing Mantachie Creek. 
CRIBBS MILL CREEK, TUSCALOOSA, AL 
(See Section 28 of Text) 
Channel modification of about 7,300 feet of the creek. Modification 
consists of widening the existing channel. 
ESLAVA CREEK, MOBILE, AL (See Section 29 of Text) 
Channel enlargement, bank stabilization measures, and increasing the size of 
the box culvert at Airport Boulevard by adding an additional barrel. 
FORT TOULOUSE (See Section 30 of Text) 
Preserve and protect the Fort Toulouse National Historic 
Landmark and Taskigi Indian Mound by instituting 
bank stabilization measures. 
HURRICANE CREEK, PRENTISS CO., MS 
(See Section 33 of Text) 
Provides emergency streambank protection to the banks and the 
bottom of the channel to retard erosion at the Marietta-Hazeldell 
Road Bridge crossing Hurricane Creek. 
MILL CREEK, DALTON, GA (See Section 36 of Text) 
For clearing and snagging Mill Creek from its mouth to downstream 
face of Willowdale Drive or a distance of 8.6 miles. 
MILL CREEK, SUMRALL, MS (See Section 37 of Text) 
Clearing and snagging 1.0 mile along Mill Creek with overbank clearing 
for 0.63 miles 
MURDER CREEK, BREWTON, AL (See Section 39 of Text) 
Non-structural project providing for the alleviation of flood problems 
at Brewton by the removal of 31 damageable structures from the 10-year 
flood plains of Murder and Burnt Corn Creeks. 
OKATIBBEE LAKE, MS (See Section 40 of Text) 
Provides for a dam and reservoir for flood control 
water supply, water quality control, and recreation. 
PORTERSVILLE BAY - EAST, MOBILE CO., AL (See Section 37 of Text) 
Provide shoreline bank protection along 5,600 feet of Shell Belt Road. 
PORTERSVILLE BAY - WEST, MOBILE CO., AL (See Section 38 of Text) 
Provide shoreline bank protection along 3,500 feet of Shell Belt Road. 
PROCTOR CREEK, ATLANTA, GA (See Section 41 of Text) 
Purchase and remove residential structures within flood plain. 
RACCOON CREEK, BACONTON, GA 
(See Section 42 of text) 
Raise about 1500 feet of South Jackson Street Bridge to elevation 176.0 
feet NGVE. Clear and snag from Hwy. 3 to U.S. Hwy. 19. 
SILVER CREEK, ROME, GA (See Section 43 of Text) 
Provide non-structural flood control measures along Silver Creek. 
SOWASHEE CREEK, MERIDIAN, MS (See Section 44 of Text) 
Channel enlargement, and clearing and snagging over a reach of 10.5 miles. 
One railroad bridge and several highway roads and bridges and utilities 
will require modification for the channel improvement. 
Development of recreation facilities. 
10-46 
Water Resources Development 
Act of 1986 
(P.L. 99-662) 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 205) 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 205) 
DPR (Sec. 205) 
H. Doc. 549, 87th Cong., 
2d Sess. 
DPR (Sec. 14) 
DPR (Sec. 14) 
DPR (Sec. 205) 
DPR (Sec. 205) 
DPR (Sec. 205) 
Water Resources 
Development Act of 1986 
(P.L. 99-662)

TABLE 10-B (Continued) 
Acts 
MOBILE, ALABAMA, DISTRICT 
AUTHORIZING LEGISLATION 
Work Authorized 
Sep. 30, 19882 
Nov. 17, 1986 
Aug. 18, 1941 
Jul. 23, 1958 
Jul. 8, 1980 
Oct. 13, 19882 
Nov. 17, 1986 
Nov. 28, 1990 
Mar. 2, 1945 
Jun. 28, 1954 
May 25, 1982 
Nov. 17, 1986 
Aug. 18, 1941 
Dec. 22, 1944 
TALLAHALLA CREEK, LAUREL, MS 
(See Section 45 of Text) 
Channel clearing and snagging with overbank clearing of brush and 
trees less than 4 inches diameter for a distance of 30 feet on each bank. 
THREEMILE CREEK, MOBILE, AL (See Section 46 of Text) 
Channel widening and deepening from about 2,000 feet downstream 
of Stone Street to a point about 6,300 feet upstream of Interstate 65 
or a total distance of 5.6 miles. Development of recreational facilities. 
TOMBIGBEE RIVER (EAST FORK), MS AND AL 
(See Section 47 of Text) 
Provides for alleviation of floods from the Tombigbee River 
by clearing, snagging, and excavation of 13 cut-off 
channels, and other related channel improvements. 
TOMBIGBEE RIVER TRIBUTARIES, MS AND AL 
(See Section 48 of Text) 
Provides for improvement of 22 tributaries of Tombigbee 
River. 
Extends project limits on Twenty Mile Creek and 
eliminates local cooperation for this remedial work. 
UPPER GORDON CREEK, HATTIESBURG, MS 
(See Section 49 of Text) 
Real Estate acquisition of nine (9) residences; habitat mitigation 
and channel enlargement. 
VILLAGE CREEK, JEFFERSON COUNTY, 
BIRMINGHAM, AL (See Section 50 of Text) 
Basically nonstructural and includes evacuating 642 structures in six 
separate neighborhoods from floodplain; enlarge 2 miles of channel 
and relocate necessary facilities; Install flood warning devices. 
Authorized the Secretary to acquire private vacant lands within the 
definite project boundaries established in the Real Estate Design 
Memorandum as a nonstructural element of the project. 
MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
ALABAMA-COOSA RIVERS, AL AND GA 
(See Section 55 of Text) 
Provides for full development of Alabama-Coosa Rivers and 
tributaries for navigation, flood control, power, recreation, and 
other purposes. 
Authorized construction of Carters Lake, GA 
Claibomrne Lock and Dam, AL, Jones Bluff Lock and 
Dam, AL, and Millers Ferry Lock and Dam, AL. 
Suspended comprehensive plan to permit non-Federal interests 
to develop Coosa River by constructing series of dams. 
Designated change of name from Jones Bluff to 
Robert F. Henry Lock and Dam. 
Modification to the plan for the Coosa River segment 
of the waterway between Montgomery and Gadsden, AL to carry 
out planning, engineering, and design in accordance 
with the Montgomery to Gadsden, Coosa River Channel, 
AL, Design Memorandum No. 1, General Design, dated May 1982. 
ALLATOONA LAKE, COOSA RIVER BASIN, GA 
(See Section 56 of Text) 
Provides for dam and reservoir for flood control, regulation 
of stream flow for navigation, development of hydroelectric 
power and recreation. 
10-47 
Documents 
DPR (Sec. 205) 
Water Resources 
Development Act 
of 1986 (P.L. 99-662) 
Special Report on Record 
in OCT. (Public Law 222,) 
77th Cong., 1st Sess. 
H. Doc. 167, 84th Cong., 
1st Sess. 
Supplemental Appropriations 
and Recession Act, 
DPR (Sec. 205) 
1980 (P.L. 96-304) 
Water Resources 
Development Act 
of 1986 (P.L. 99-662) 
Water Resources 
Development Act of 
1990 (P.L. 101-640) 
H. Doc. 414, 77th Cong., 
1st Sess. 
Public Law 436, 83rd 
Cong. 
S.2034 97th 
Cong., 2d Sess. 
Water Resources 
Development Act 
of 1986 
(P.L. 99-662) 
Public law 228, 77th 
Cong., 1st Sess. 
H. Doc. 674, 76 Cong., 
3d Sess.

TABLE 10-B (Continued) 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
RIVERS, AL, GA AND FL (See Section 57 of Text) 
Mar. 2, 1945 Development of Apalachicola, Chattahoochee, and Flint H. Doc. 342, 76th Cong., 
Rivers for navigation, flood control, hydropower, and recreation. 1st Sess. 
Jul. 24, 1946 Modified general plan for full development of H. Doc. 300, 80th Cong., 
Apalachicola, Chattahoochee, and Flint River System and auth- 1st Sess. 
orized construction of Lake Sidney Lanier multipurpose reservoir. 
Dec. 22, 194 Authorized recreation facilities. 
Jan. 27, 1981 Modified the existing project to provide for nine foot DPR (Sec. 107) 
deep by 100-foot wide side channel into the 
Apalachicola River Industrial Park, Blountstown, Fl. 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT 
Nov. 17, 1986 Modified Rivers and Harbors Act of 1945 to restore and Water Resources 
maintain access to bendways and interconnecting waterways Development Act 
in the course of routine maintenance dredging; and of 1986 
to acquire lands for and to construct, operate, and (P.L. 99-662) 
maintain water-related public use and access facilities. 
LAKE SIDNEY LANIER, GA (See Section 57A of Text) 
Jul. 24, 1944 Provision of recreation facilities. 
GEORGE W. ANDREWS LOCK AND DAM, AL AND GA 
(See Section 57B of Text) 
Jul. 24, 1946 Construction of high dam at Walter F. George site H. Doc. 300, 80th Cong., 
and low dam at George W. Andrews site. 1st Sess. 
Dec. 22, 1944 Provided recreation facilities. 
JIM WOODRUFF LOCK AND DAM, GA AND FL 
(See Section 57C of Text) 
Dec. 22, 1944 Provided recreation facilities. 
WALTER F. GEORGE LOCK AND DAM, AL, AND GA 
(See Section 57D of Text) 
May 19, 1953 Authorized construction of high dam at Walter F. George H. Comm. on 
site and low dam at Columbia site. Public Works 
WEST POINT LAKE, CHATTAHOOCHEE RIVER 
BASIN, GA AND AL (See Section 57E of Text) 
Oct. 23, 1963 Authorized construction for flood control, power H. Doc. 570, 87th Cong., 
recreation, fish and wildlife development, and 2d Sess. 
streamflow regulation for downstream navigation. 
1. Authorized by Chief of Engineers under Section 107 of 1960 
River and Harbor Act, as amended. 
2. Authorized by Chief of Engineers under Section 205 of 
Flood Control Act of 1948, as amended. 
3. Authorized by Chief of Engineers under Section 208 of Flood 
Control Act of 1954, as amended. 
4. Authorized by Chief of Engineers under Section 14 of Flood 
Control Act of 1946, as amended. 
10-48

MOBILE, ALABAMA, DISTRICT 
TABLE 10-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Blackwater River, FL 1981 $41,650 $328,614 
Bluff Creek, MS 1963 1,000 6,883 
Cadet Bayou, MS 1984 87,921 1,138,608 
Carrabelle Bar and Harbor, FL 1979 481,627 403,723 
Choctawhatchee River, FL and AL 1973 171,885 291,694 
Escambia-Conecuh Rivers, AL and FL 1981 208,499 1,136,744 
Holmes Creek, FL 1931 8,562 36,800 
LaGrange Bayou, FL 1972 289,496 142,659 
Noxubee River, MS 1902 47,528 14,472 
Panacea Harbor, FL 1979 122,383 101,631 
Pascagoula River, MS 1956 15,000 179,535 
Pass Christian Harbor, MS 1976 59,313 139,653 
Port St. Joe Harbor, FL 1984 1,960,862 2,958,516 
Removing Water Hyacinths 1984 - 1,100,471 
St. Marks River, FL 1965 1,710,809 84,115 
Tombigbee River at Columbus Port, MS 1988 500,500- 
Wolf and Jordan Rivers, MS 1979 29,195 481,515 
1. Abandonment recommended in H. Doc. 467, 69th Cong. 
TABLE 10-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECT 
For Last Cost to September 30,1992 
Full Report 
See Annual Operation and 
Report For Construction Maintenance2 
Harrison County, MS, shore protection1 1953 $1,133,000- 
1. Completed. 
2. Operation and maintenance is the responsibility of local 
interests. 
10-49

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 10-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Report For Construction Maintenance 
Alabama River at Montgomery, AL' 
Armuchee Creek, GA 
Beaver Creek, Montezuma, GA 
Big Brown Creek, Prentiss Co, MS 
Biloxi River at Lorraine Road, Harrison County, MS 
Black Creek, Gadsden, AL 
Black Warrior River, U.S. Hwy. 11 Bridge, Fosters, AL 
Boligee Canal, Boligee, AL 
Burketts Creek, Amory, MS 
Chattahoochee River, Eufaula, AL 
Chickasaw Bogue Creek, U.S. Highway 43 Bridge, Linden, AL 
Clanton, AL 
Collinsville, AL 
Goodfood Creek, Chickasaw Co., MS 
Gordons Creek, Hattiesburg, MS 
Gulf Breeze, Santa Rosa Co., FL 
Highway 39 Bridge, Gainesville, AL 
Hintonville Road Bridge, Perry Co., MS 
Houlka Creek, Chickasaw & Clay Counties, MS 
Houston School Rd. Bridge, Itawamba Co., MS 
Interstate 59 Bridges, Fosters, AL 
Lake Douglas, Decatur County, GA 
Leaf and Bowie Rivers, Hattiesburg, MS 
Leaf River, County Road Bridge, Mahned, MS 
Little Cove Creek, Glencoe, AL 
Magby Creek, Columbus, MS 
Martin Creek, Prentiss County, MS 
Murder and Burnt Corn Creeks, Brewton, AL 
Murder Creek, East Brewton, AL 
Noxubee River Relief Bridge, Shuqualak, MS 
Old Hwy. 82 Bridge, Columbus, MS 
Osborne Creek, Highway 362 Bridge, Prentiss County, MS 
Prattville, Autauga Creek, AL 
Pumpkinvine Creek, Emerson, GA 
Rome, Coosa River, GA 
Sewerline Protection, Valley, AL 
Sope Creek, Marietta, GA 
Sowashee Creek, Meridian, MS 
Sun Creek, Okibbeha County, MS 
Tallabinella Creek, Chickasaw County, MS 
Tallahala Creek, Pascagoula River, MS 
Town Creek, Americus, GA 
Trim Cane Creek, Oktibbeha County, MS 
Trussville, AL 
Twenty Mile Creek, Airport Road Bridge, Frankstown, MS 
West Point, Chattahoochee River, GA 
Whorton's Bend Road, Etowah Co., AL 
Wolf Creek, Highway 362 Bridge, Prentiss County, MS 
Wolf Creek, U.S. Hwy. 45 Bridge, Prentiss County, MS 
Yellow Jacket Creek, Hogansville, GA 
1. Engineering, design, supervision, and administration (no 
construction work has been done. Includes $17,000 for 
1965 
1966 
1958 
1987 
1985 
1953 
1986 
1987 
1984 
1988 
1985 
1964 
1940 
1988 
1985 
1991 
1990 
1991 
1982 
1988 
1987 
1970 
1990 
1986 
1991 
1991 
1988 
1980 
1986 
1988 
1987 
1985 
1946 
1985 
1955 
1989 
1990 
1956 
1984 
1988 
1988 
1965 
1984 
1965 
1986 
1955 
1991 
1985 
1986 
1O6 
$144,194 
115,547 
149,815 
137,500 
132,174 
125,389 
181,500 
178,600 
1,366,454 
206,600 
121,718 
274,024 
71,119 
91,500 
802,026 
147,432 
71,000 
268,691 
238,219 
59,300 
155,200 
164,998 
1,585,000 
231,618 
144,047 
156,508 
78,500 
190,974 
903,474 
119,500 
143,936 
250,000 
649,280 
85,029 
384,550 
180,937 
1,538,555 
142,637 
55,569 
81,000 
3,945,757 
340,409 
145,519 
141,334 
215,860 
599,637 
448,956 
114,753 
154,641 
S37 4 
pre-authorization studies. 
2. Operation and maintenance is the responsibility of local interests. 
TABLE 10-G DEAUTHORIZED PROJECTS 
Year of Last Deauthorization Date 
Project Type Full Report Document Deauthorized 
Buttahatchee Creek, MS Flood Control 19891 Public Law 99-662 Jan. 9, 1992 
(Auth P.L. 96-304) 99th Congress 
Little Browns Creek, AL Flood Control 19891 Public Law 99-662 Jan. 9, 1992 
(Auth. P.L. 96-304) 99th Congress 
1. Deauthorized tributaries of Tombigbee River improvements. 
10-50

MOBILE, ALABAMA, DISTRICT 
TABLE 10-H NAVIGATION WORK UNDER SPECIAL AUTHORIZATON 
Fiscal Year 
Study Authority 1992 Costs 
Eastpoint Channel, FL 107 $ 513 
Fort Gaines, Dauphin Island, AL 107 60,311 
Ocean Springs Harbor, MS 107 32,844 
South Fork, Bon Secour River, AL 107 210 
Total $93,8781 
TABLE 10-J FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Fiscal Year 
Study Authority 1992 Costs 
Alabama River, Montgomery, AL 205 $8,410 
Alabama River, Selma, AL 205 3,871 
Barbour Creek, Eufaula, AL 205 46,415 
Black Warrior River, North Port, AL 205 62,059 
Blackwater River, Milton, FL 205 6,367 
Burkett's Creek, MS 205 46,442 
Carysville, FL 205 170 
Chattooga River, Trion, GA 205 9,942 
Coosa River, Rome, GA 205 47,452 
Flat Branch, Gulfport, MS 205 36,711 
Greens Creek, Petal, MS 205 15,319 
Little Wills Creek, AL 205 587 
Lost Creek, Carbon Hill, AL 205 2,975 
Mill Creek, McGee, MS 205 21,620 
Murder & Burnt Corn Creeks, Brewton, AL 205 27 
North Shore, Santa Rosa Island, FL 205 13,601 
Pea River, Elba, AL 205 280 
Pea & Choctawhatchee Rivers, Geneva, AL 205 8,509 
Peachtree Creek, Basin, Atlanta, GA 205 9,823 
Pensacola Beach, FL 205 13,994 
Sweetwater Creek, Austell, GA 205 530 
Tiger Creek, Columbus, GA 205 21,566 
Tombigbee River, Demopolis, AL 205 9,963 
Vernon Branch, Columbus, MS 205 20,148 
Atkinson Creek, Green Co., MS 14 22,533 
Chattahoochee River, Franklin, GA 14 11 
County Road 55, Etowah Co., AL 14 28 
Fosters Loop Rd., Tuscaloosa Co., Al 14 9,967 
Gordon's Creek, Hattiesburg, MS 14 4,330 
Hancock County, Seawall, MS 14 1,159 
Leaf River Br., Green Co., MS 14 20,491 
Maynor Creek State Park, Wayne, MS 14 944 
Tombigbee Rv Bd #6, Monroe Co., MS 14 37,894 
Total $504,138 
10-51

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 10-K RECONNAISSANCE AND CONDITION SURVEYS 
Cost During 
Project Date of Survey Fiscal Year 
Apalachicola Bay, FL June 1992 $13,074 
Bayou Coden, AL June 1992 10,350 
Bayou La Batre, AL June 1992 8,050 
Biloxi Harbor, MS September 1992 4,655 
Blackwater River, FL March 1992 6,170 
Bon Secour, AL June 1992 14,630 
Cadet Bayou, MS August 1992 7,980 
Carrabelle Harbor, FL April 1992 13,787 
Dauphin Island, AL June 1992 14,630 
Escambia Bay, FL March 1992 24,756 
Fly Creek, AL July 1992 4,600 
Fowl River, AL July 1992 9,200 
La Grange Bayou, FL September 1992 608 
Panacea Harbor, FL April 1992 7,558 
Pensacola Harbor, FL September 1992 15,052 
Perdido Pass, AL April 1992 16,856 
Port St. Joe, FL April 1992 8,920 
St. Marks River, FL April 1992 16,646 
Wolf and Jordan Rivers, MS August 1992 10.640 
Total $208,162 
TABLE 10-L ALABAMA-COOSA RIVERS, ALA. AND GA. 
DEVELOPMENT PROPOSED UNDER EXISTING PROJECT 
(See Section 55 of Text) 
Claiborne Millers Ferry Robert F. Henry Carters Allatoona 
Proposed Structures Lock and Dam Lock and Dam Lock and Dam Lake Dam 3 Dam 
Miles above mouth of river 81.11 42.21 245.41 26.82 47.84 
Nearest town Claiborne, Ala. Camden, Ala. Benton, Ala. Carters, Ga. Cartersville, Ga. 
Distance (miles) 7 10 3 2 4 
Greatest lock length available 
for full width (feet) 600 600 600 -- 
Width of lock chamber (feet) 84 84 84 -- 
Maximum lift (feet) 30 48 47 -- 
Elevation of normal pool surface 
(mean sea level) 35 80 125 1072 840 
Depth over sills at low water 13 Upper 15 Upper 15 -- 
(feet) Lower 13 Lower 12 
Character of foundation Rock Rock Rock Rock Rock 
Kind of spillway Gated and Gated Gated Gated Gated 
Fixed Crest 
Height of dam (feet) 95.5 99.5 94 451 190 
Type of construction Concrete Concrete Concrete Rock-fill Concrete 
Earth Core 
Total reservoir capacity 
(acre-feet) 96,360 331,800 234,200 472,800 670,050 
Power development (kw) - 75,000 68,000 500,000 74,000 
Percent complete 100 100 100 100 100 
Cost to date: $27,997,450 $63,125,300 $83,360,800 $111,140,340 $35,709,085 
1. Above mouth of Alabama River (river miles) 
2. Above mouth of Coosawattee River (river miles). 
3. Reregulation dam (Carters) 25.3 (river miles). 
4. Above mouth of Etowah River (river miles). 
5. Includes cost of added recreation facilities as shown in Table 10A. 
10-52

MOBILE, ALABAMA, DISTRICT 
TABLE 10-M 
APALACHICOLA, CHATTAHOOCHEE, AND FLINT RIVERS, ALA., GA., 
AND FLA., LOCKS AND DAMS AND MULTIPLE-PURPOSE 
DEVELOPMENT INCLUDED IN EXISTING PROJECT 
(See Section 57 of Text) 
Jim 
Woodruff 
Lock 
and Dam 
Miles above mouth 
Nearest town 
Distance (miles) 
Greatest lock length 
available for full width (feet) 
Width of chamber (feet) 
Maximum lift (feet) 
Elevation of normal pool 
surface (msl) 
Depth over sills at low 
water (feet) 
Character of foundation 
Kind of spillway 
Height of dam (feet) 
Type of construction 
Total reservoir capacity 
(acre-feet) 
Power-development 
(kilowatts) 
Percent complete 
Year opened to navigation 
Cost to date:3 
107.61 
Chattahoochee FL., 
1
450 
82 
33 
77 
14 
Limestone 
Fixed-gated 
67 
Concrete 
and Earth 
367,300 
30,000 
100 
1954 
$47,978,751 
Existing Projects 
George W. Walter F. 
Andrews George 
Lock Lock 
and Dam and Dam 
46.52 75.02 
Columbia, Al. Ft. Gaines, Ga. 
1 2 
450 450 
82 
25 
102 
13 
Limestone 
Fixed-gated 
62 
Concrete 
18,180 
100 
1962 
$13,038,427 
82 
88 
190(Summer) 
185(Winter) 
13 
Limestone 
Gated 
114 
Concrete 
and Earth 
934,400 
130,000 
100 
1963 
$98,947,7494 
Buford Dam 
Lake 
West Point Sidney 
Lake Lanier 
201.42 348.32 
West Point, Ga. Buford, Ga. 
2.8 5 
635(Summer) 
625(Winter) 
Rock 
Gated 
95 
Concrete 
and Earth 
604,500 
73,875 
100 
$131,565,287 
1071(Summer) 
1070(Winter) 
Rock 
Fixed 
192 
Earth 
2,554,000 
86,000 
100 
$53,028,418 
1. Above the mouth of Apalachicola River (river miles). 
2. Above mouth of Chattahoochee River (river miles). 
3. Includes cost of added recreational facilities as shown 
in Table 10-A. 
4. Includes $333,198 cost of land for wildlife refuge and 
$10,617,080 for major rehabilitation. 
10-53 
. .

REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 10-N BLACK WARRIOR AND TOMBIGBEE RIVERS, ALA. 
(See Section 6 of Text) 
Armistead I. William John Hollis 
Coffeeville Demopolls Selden Bacon Oliver Holt Bankhead 
Lock Lock Lock Lock & Dam Lock Lock 
and Dam and Dam and Dam (Replacement) and Dam and Dam1 
Miles above Mobile 116.7 213.2 261.1 337.7 347.0 365.5 
Nearest town (Alabama) Coffeeville Demopolis Eutaw Tuscaloosa Tuscaloosa Tuscaloosa 
Distance (miles) 3(within city) 6 15 (within city) 6 30 
Lock: 
Greatest length available 
for full width (feet) 600 600 600 600 600 600 
Width of chamber (feet) 110 110 110 110 110 110 
Maximum lift (feet) 34 40 22 28 64 68 
Depth over sills at low 
water (feet) 13.0 13.0 13.2 18.0 13.0 14.0 
Character of foundation Rock Rock Sand, clay Hard shale Shale, Sandstone 
sandstone 
Kind of spillway Fixed-Gated Fixed Gated Fixed Gated Gated 
Type construction 
Lock Concrete Concrete Concrete Concrete Concrete Concrete 
Dam Concrete Concrete Earth- Concrete Concrete Concrete 
Concrete 
Year completed 1965 1962 1962 19924 1969 1985 
Year opened to navigation 1960 1954 1957 1991 1966 1975 
Actual cost of lock and dam3 $21,597,264 $19,774,583 $13,295,553 $120,000,000 $28,100,000 $52,292,880 
1. Single lift lock. 
2. Navigation mileage from foot of Government Street, Mobile, Ala. 
3. Excludes cost of adding recreation facilities. 
4. Scheduled. 
10-54

MOBILE, ALABAMA, DISTRICT 
TABLE 10-0 
TENNESSEE-TOMBIGBEE WATERWAY, ALABAMA AND MISSISSIPPI 
(See Section 19 of Text) 
Existing Projects 
Gainesville Aliceville Columbus Aberdeen Lock A Lock B Lock C Lock D Lock E Bay Springs 
Lock Lock Lock Lock and and and and and Lock and 
and Dam and Dam and Dam and Dam Spillway Spillway Spillway Spillway Spillway and Dam 
Miles above mouth1 266 307 335 358 371 376 39 398 407 412 
Nearest town Gainesville, AL Aliceville, AL Columbus, MS Aberdeen, MS Amory, MS Smithville, MS Fulton, MS Fulton, MS Belmont, MS Tupelo, MS 
Greatest lock length 600 600 600 600 600 600 600 600 600 600 
available for full 
width (feet) 
Width of Chamber (feet) 110 110 110 110 110 11 0 110 110 110 110 
Maximum lift (feet) 36 27 27 27 30 25 25 30 30 84 
Elevation of normal 109 136 163 190 220 245 270 300 330 (Summer)414 
pool surface (msl) (Winter)409 
Depth over sills at 15 15 15 15 15 18 18 18 18 18 
low water (feet) 
Character of foundation Mooreville Eutaw Form. Eutaw Form. Eutaw Form. Eutaw Form. Eutaw Form. Gordo Form. Eutaw Form. Gordo Form. Sandstone 
Chalk Sand & Clay Sand & Clay Sand Lam. Sand Sand & Clay Clay Sand Clay and Shale. 
Kind of spillway Fixed & Fixed & Gated Gated Gated Gated Gated Gated Gated N/A 
Gated Gated 
Height of dam (feet) 56 57 57 57 46 48 53 52 44.5 103 
Type of construction Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete Concrete 
& Earth & Earth & Earth & Earth & Earth & Earth & Earth & Earth & Earth 
Total reservoir capacity 45,290 655 59,483 31,564 4,400 19,000 13,300 24,900 6,900 (Summer)180,000 
(acre-feet)(Winter)143,000 
Percent complete 100 100 100 100 100 100 100 100 100 100 
Year opened to 1978 1979 1981 1984 1985 1985 1985 1985 1985 1985 
navigation 
Estimated Cost $103,214,000 151,255,000 182,650,000 128,262,000 102,685,000 96,905,000 71,375,000 98,205,000 88,173,000 147,000,000 
Cost to date $100,010,600 143,190,800 174,620,500 112,620,200 92,190,500 93,106,700 62,197,000 89,610,800 76,917,700 130,398,000 
1. Miles above Mobile, Alabama (Mile 0.00 is at Bankhead Tunnel on U.S. Highway 90) 
10-55

TABLE 10-P 
REPORT OF THE SECRETARY OF THE ARMY 
ON CIVIL WORKS ACTIVITIES FOR FY 1992 
COMPLETED FLOOD INSURANCE STUDIES AND FLOOD 
HAZARD INFORMATION REPORTS FOR FY 1983 THRU FY 19921 
Date Federal 
Study Requesting Agency Completed Cost 
Flood Insurance Studies 
Cave Springs, GA Federal Emergency Management Agency (FEMA) Jan 84 22,500 
Floyd County, GA Federal Emergency Management Agency (FEMA) Dec 84 230,000 
Columbus, MS Federal Emergency Management Agency (FEMA) Feb 85 36,000 
Lowndes County, MS Federal Emergency Management Agency (FEMA) Feb 85 229,000 
Aberdeen, MS Federal Emergency Management Agency (FEMA) May 85 35,000 
Amory, MS Federal Emergency Management Agency (FEMA) May 85 50,000 
Cherokee County, GA Federal Emergency Management Agency (FEMA) July 85 168,000 
Monroe County, MS Federal Emergency Management Agency (FEMA) Oct 85 140,000 
Dale County, AL Federal Emergency Management Agency (FEMA) Dec 86 82,000 
Lauderdale County, MS Federal Emergency Management Agency (FEMA) Mar 87 144,000 
Houston County, AL Federal Emergency Management Agency (FEMA) Apr 87 114,000 
St. Clair County, AL Federal Emergency Management Agency (FEMA) Jun 87 43,000 
Marengo County, AL Federal Emergency Management Agency (FEMA) Nov 87 36,000 
Greene County, AL Federal Emergency Management Agency (FEMA) Mar 88 18,550 
Covington County, MS Federal Emergency Management Agency (FEMA) Apr 88 35,000 
Pickens County, AL Federal Emergency Management Agency (FEMA) Apr 88 50,000 
Fulton County, GA Federal Emergency Management Agency (FEMA) May 88 180,000 
Monroe County, AL Federal Emergency Management Agency (FEMA) Jun 88 33,000 
Colquitt County, GA Federal Emergency Management Agency (FEMA) Sep 88 48,000 
Murray County, GA Federal Emergency Management Agency (FEMA) Sep 88 68,000 
Coffee County, AL Federal Emergency Management Agency (FEMA) Apr 89 48,500 
Montgomery County, AL Federal Emergency Management Agency (FEMA) Jul 89 175,000 
Clayton County, AL Federal Emergency Management Agency (FEMA) Nov 89 250,000 
Jefferson County, AL Federal Emergency Management Agency (FEMA) Sep 91 397,000 
Calhoun County, AL Federal Emergency Management Agency (FEMA) Apr 91 200,000 
Special Flood Hazard Information 
Canton Creek, GA City of Canton, GA Dec 82 3,000 
Oktasasi Creek, AL Alexander City, AL Jan 83 3,000 
Cordele Creek & City of Cordele, GA May 83 4,000 
Malcolm Branch, GA 
Hull Branch, MS East Central Planning and Jun 84 7,000 
Development District 
Percosin Creek & Tribs., GA City of Albany, GA Nov 84 14,000 
Coosawattee, Ellijay and Cartecay City of Ellijay, GA Jul 86 22,000 
Rivers, Vicinity of Ellijay, GA 
Rocky Creek and Basie Branch, MS Ellisville, MS Jan 87 19,000 
Springers Branch, MS Starkville, MS May 87 13,000 
Dixie Creek, GA La Grange, GA Jun 87 15,000 
Little Scooba Creek, MS Scooba, MS Jun 87 18,000 
Fishpond Drain & Trib., GA Donalsonville, GA Dec 87 18,000 
Dearmenville & Golden Springs, AL Anniston, AL Mar 88 9,000 
Chickasawhay River, MS Quitman, MS Jun 89 19,000 
Archusa Creek, MS Quitman, MS Jun 89 9,000 
Leaf River, MS New Augusta, MS Sep 89 27,000 
Shades Creek, AL Jefferson County, AL Sep 90 45,000 
Leaf River, MS Taylorsville, MS Sep 91 25,000 
Oostanaula River, GA City of Rome, GA Jan 92 10,000 
Coosa River, GA City of Rome, GA Jul92 10,000 
1. For list of reports completed by Mobile District for FY 1965 thru FY 1974, see FY 1974 Annual Report, page 10-50; reports completed in FT 
1975 see FY 1975 Annual Report, page 10-44; and for reports completed in FY 1976 and FY 1977, see FY 1977 Annual Report, page 10-46. Set 
page 10-48 FY 1978 Annual Report for FY 1978 reports, and see page 10-43 FY 1984 Annual Report for FY 1979 through FY 1984 reports. 
10-56

NEW ORLEANS, LA, DISTRICT* 
District comprises a portion of Louisiana, embraced 
in drainage basins tributary to Mississippi River and 
Gulf of Mexico, except Mississippi River above mile 
325.5 above Head of Passes (AHP), drainage area of 
Ouachita-Black River Basin, and small eastern and 
western portions of Louisiana tributary to Pearl River 
and Sabine River and Lake. The New Orleans District 
territory encompasses 30,000 square miles. 
It includes sections of the Gulf Intracoastal Waterway 
from Lake Borgne Light 29 at the mouth of Pearl 
River to Sabine River, and the Passes of the Mississippi 
River. It exercises jurisdiction over flood control 
work on Mississippi River from mile 325.5 AHP to 
Gulf of Mexico; Atchafalaya River; and in Atchafalaya 
Basin; and maintenance of project navigation channel 
of Mississippi River below mile 325.5 AHP, under 
supervision of President, Mississippi River Commission 
(MRC), and Division Engineer, Lower Mississippi 
Valley Division. 
IMPROVEMENTS 
Page Flood Control (cont.) 
1. Mississippi River-Gulf Outlet, LA ..... 11-2 
2. Mississippi River Ship Channel, 
Gulf to Baton Rouge, LA ............ 11-2 
3. Navigaton work under 
special authorization ............... 11-3 
Flood Control 
4. Grand Isle and vicinity, LA .......... 11-4 
5. Lake Pontchartrain and vicinity, 
LA, (hurricane protection) ........... 11-4 
6. Larose to Golden Meadow, LA 
(hurricane protection) .............. 11-5 
7. Morgan City and vicinity, LA 
(hurricane protection) .............. 11-6 
8. New Orleans to Venice, LA 
(hurricane protection) .............. 11-7 
9. Westwego to Harvey Canal, LA 
(hurricane protection) .............. 11-8 
10. Inspection of completed flood 
control projects .................. 
11. Flood control work under special 
authorization .................... 
Page 
11-9 
11-9 
Tables 
Table 11-A Cost and Financial 
Statement .............. 11-10 
Table 11-B Authorizing Legislation ... 11-12 
Table 11-C Other Authorized Navigation 
Projects ................ 11-15 
Table 11-D Other Authorized Flood 
Control Projects ......... .11-17 
Table 11-E Deauthorized Projects .... 11-18 
Table 11-F Active General 
Investigations ........... 11-19 
11-1 
Navigation

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
1. MISSISSIPPI RIVER-GULF 
OUTLET, LA 
Location. In State of Louisiana and the territorial 
waters of the United States and extends from 
existing Inner Harbor Navigation Canal at a point 
7,500 feet north of existing lock and about 11,000 feet 
from Mississippi River, to a turning basin south of 
Michoud, LA, and then as a land and water cut from 
turning basin south of Michoud, LA, southeasterly to 
and along south shore of Lake Borgne and through 
marshes to and through Chandeleur Sound to 38-foot 
contour in Gulf of Mexico. (Refer to NOAA Coast 
Charts Nos. 11340, 11360, 11363, 11369, 11371, and 
11373. Also see MRC 1989 (57th edition) folio of maps, 
Mississippi River-Cairo, IL, to Gulf of Mexico, LA.) 
Existing project. Provides for a seaway canal, 36 
by 500 feet, extending 76 miles as a land and water 
cut from Michoud southeasterly to and along south 
shore of Lake Borgne, and across Chandeleur Sound 
to Chandeleur Island and increasing gradually to 38 
by 600 feet in Gulf of Mexico, with protective jetties at 
entrance, a permanent retention dike through 
Chandeleur Sound, and a wing dike along islands as 
required. It also provides for an inner tidewater harbor 
consisting of 1,000- by 2,000-foot turning basin 36 
feet deep at landward end of seaway canal, and a 
connecting channel 36 by 500 feet wide extending 
easterly along Gulf Intracoastal Waterway from turning 
basin, including construction of a suitable highway 
bridge with approaches to carry Louisiana State 
Highway 47 (formerly 61) over channel. Plan further 
provides for future construction of a channel and lock 
in the vicinity of Meraux to furnish an additional 
connection between tidewater harbor and Mississippi 
River. Estimated cost for new work (October 1992) is 
$565,500,000 Federal and $316,400,000 non-Federal. 
This does not include modification for Mississippi 
River-Gulf Outlet, Michoud Canal, which is reported 
separately. The Federal cost excludes $45,000 for aids 
to navigation by U.S. Coast Guard. 
Local cooperation. Requirements of local cooperation 
are fully described on page 11-4 of FY 1986 
Annual Report. 
Terminal facilities. A public facility on the waterway 
is the Public Bulk Terminal of New Orleans 
constructed by Board of Commissioners, Port of New 
Orleans, on left descending bank at Mile 63. Two 
cQntainer ship berths are in operation at the Industrial 
Canal end of the seaway. 
Operations and results duringfiscal year. New 
work by hired labor: Engineering and economic studies 
continued for the new lock and connecting channels 
feature. 
Four dredging contracts for removal of 14,450,000 
cubic yards of material from the channel at a cost of 
$11,720,482 were awarded in FY 92. 
Condition as of Sep. 30. Construction was initiated 
March 1958. The channel unit is 90 percent 
complete and the shiplock unit is 0 percent complete. 
The total project is 75 percent complete. The channel 
was opened to navigation Jul. 25, 1963, and completed 
Jan. 20, 1968. Paris Road Bridge was opened to traffic 
Jul. 21, and completed Nov. 14, 1967. Approximately 
3 miles of first- and second-lift stone jetties have been 
constructed on north side of channel and approximately 
8.27 miles of first-lift and 7.34 miles of 
secondlift stone jetties have been constructed on south 
side of channel in Breton Sound. The foreshore protection, 
south bank, Chalmette Area, Station 367+00 to 
Station 1007+00 is complete. Principal work required 
to complete project, raising and extending jetties as 
required and foreshore protection. (Inner Harbor Navigation 
Canal to Bayou Bienvenue), is in a deferred 
status. The site for the lock remained the major problem. 
The Water Resources Development Act of 1986 
authorized the Corps to look at both the Industrial 
Canal site and the Violet site. The studies at the Violet 
site are now complete. The Corps has established an 
Open Planning Process working directly with the local 
affected people at the Industrial Canal site. The aim 
is to develop a comprehensive solution that will benefit 
both the neighborhoods and navigation interests. 
A Site in the Industrial Canal between Claiborne and 
Florida Avenues, north of the existing lock, has been 
tentatively identified as the location that could be the 
only "win-win" solution. Additional studies are being 
focused on this site. An Evaluation Report is scheduled 
for completion in FY 1995. 
2. MISSISSIPPI RIVER 
SHIP CHANNEL, 
GULF TO BATON ROUGE, LA 
Location. The project is located in the southeastern 
portion of Louisiana below Baton Rouge, and 
consists of the Mississippi River and its major outlet 
to the Gulf of Mexico, Southwest Pass. 
Existing project. Provides more efficient deepdraft 
navigation access to the New Orleans and Baton 
Rouge reaches of the Mississippi River via Southwest 
Pass by enlarging the existing channel to a project 
depth of 55 feet and enlarging the adjacent channel 
along the left descending bank in New Orleans Harbor 
to a 40-foot depth, a turning basin at Baton Rouge, 
and training works in the passes to reduce - 
maintenance. 
Estimated cost of existing project (Oct. 1, 1992) is 
$149,000,000 Federal and $375,000,000 non-Federal. 
In addition, Coast Guard is to provide navigation aids 
at an estimated cost of $1,200,000. 
Local cooperatioh. The cost sharing provisions 
contained in the Water Resources Development Act of 
1986 require that prior to initiation of construction, 
11-2

NEW ORLEANS, LA, DISTRICT 
local interests shall: (a) Provide to the Federal Government 
lands, easements, rights-of-way, and 
dredged material disposal areas, and perform the 
necessary relocations required for construction, operation, 
and maintenance of the project; (b) Hold and 
save the United States free from damages due to the 
construction or operation and maintenance of the project 
except for damages due to the fault or negligence 
of the United States or its contractors; (c) Provide to 
the Federal Government, the non-Federal share of all 
other costs of construction of the project. These costs 
include 25 percent of the construction costs incurred 
for construction of the navigation channel to a depth 
of 45 feet, and 50 percent of the construction costs 
incurred for deepening the channel between 45 and 55 
feet. In addition, the local sponsor shall repay the 
Government 10 percent of the construction costs over 
a 30-year period. The local sponsor may be permitted 
to include, toward sums to be reimbursed, all or part 
of the value of any lands, easements, rights-of-way, 
and dredged material disposal areas and relocations, 
including utility relocations contributed or expended 
by the non-Federal sponsor; (d) Be responsible for 50 
percent of the incremental maintenance below 45 feet 
on a channel depth greater than 45 feet. 
A Local Cooperation Agreement (LCA) between 
the Government and the state of Louisiana was 
signed on Jun. 30, 1986. This agreement provided 
for dredging of a 45-foot channel from the Gulf to 
Mile 181 AHP. A supplement to the LCA was executed 
on Jun. 15, 1987, to comply with the cost 
sharing and financing concepts reflected in the 
Water Resources Development Act of 1986, Public 
Law 99-662. A second supplement to the LCA was 
executed on Jun. 25, 1990, to comply with the cost 
sharing and financing concepts reflected in the 
Water Resources Development Act of 1988, Public 
Law 100-676. A third supplement to the LCA addressing 
the Permanent Saltwater Intrusion Mitigation 
Plan has been prepared and is currently 
under review. 
The state of Louisiana has requested that we proceed 
with the construction of the 45-foot channel from 
Mile 181 to Mile 232.4 (Phase II). We have prepared 
a design memorandum that provides for the dredging 
of the deeper channel. This design memorandum is 
under review. 
Terminal facilities. See Mississippi River, 
Baton Rouge to the Gulf of Mexico, LA. 
Operations and results during fiscal year. A 
revised feature Design Memorandum (DM) on the 
45-foot channel from Mile 181 to Baton Rouge was 
submitted in May 1991. The DM reflected a schedule 
of constructing rock dikes at four crossings (to reduce 
maintenance dredging) then dredging the 45- 
foot channel. After being informed of the plan, the 
navigation industry opposed construction of the 
rock dikes. Their main concerns were safety and 
congestion caused by the dikes. Opposition was so 
great that the local sponsor withdrew support for the 
rock dike plan. Therefore, work on the dike plan was 
terminated. In July 1991, we initiated an economic 
analysis to investigate the feasibility of providing the 
45-foot channel to Baton Rouge by dredging only. The 
analysis revealed that the dredging only plan was 
justified. 
The Permanent Saltwater Intrusion Mitigation 
plan (required due to the deepening of the channel 
between the Gulf and Mile 181 AHP) consists of the 
Government providing an underwater sill, when 
needed, and upgrading the existing water distribution 
system in Plaquemines Parish to provide fresh water 
to water treatment plants impacted by increased saltwater 
intrusion caused by the deeper channel. A Supplemental 
Design Memorandum (DM) was submitted 
on Jul. 17, 1990, outlining the details of Permanent 
Saltwater Intrusion Mitigation plan. Between October 
1990 and July 1991, LMVD comments on the DM 
were submitted and resolved. The DM was forwarded 
to HQUSACE for review on Aug. 9, 1991. Substantive 
comments were received from HQUSACE and the 
Washington Level Review center. A response to the 
comments was submitted on Apr. 23, 1992. Additional 
comments were received from HQUSACE on Jul. 30, 
1992 and a response to these comments was submitted 
on Aug. 24, 1992. A draft third Supplement to the 
basic LCA covering this work was submitted on Jul. 
16, 1990. LMVD comments required a complete rewrite 
of the Supplemental LCA. The rewritten Supplemental 
LCA was negotiated with the local sponsor 
and submitted back to LMVD on Apr. 23, 1991. No 
action was taken on the Supplemental LCA since the 
DM had not been approved. Based on comments received 
on the DM, the LCA has been revised and is 
under review. 
Condition as of Sep. 30. The 45-foot channel is 
completed from the Gulf to Mile 181.0 AHP. Studies 
have been completed on the most economical plan to 
mitigate for saltwater intrusion caused by the deeper 
channel. Until the recommended plan is executed, an 
interim plan has been developed that will provide for 
the barging of fresh raw water to two water treatment 
plants in Plaquemines Parish. 
3. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
Preauthorization studies costs as of Sep. 30, 1992, 
were Lake Charles Ship Channel for $6,737; North 
Pass-Pass Manchac, LA, $316; and Vermilion River, 
LA, $1,228. 
11-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Flood Control 
4. GRAND ISLE AND VICINITY, LA 
Location. In south Jefferson Parish, LA, along 
the Gulf of Mexico, about 50 miles south of New 
Orleans and 45 miles northwest of Southwest Pass 
(Mississippi River). 
Existing project. The project provides protection 
from waves driven by hurricanes that have a frequency 
of recurrence of up to once in every 50 years. 
The plan consists of a berm and vegetated dune extending 
the length of Grand Isle's gulf shore and a 
jetty to stabilize the western end of the island at 
Caminada Pass. The dune would have a 10-foot-wide 
crown at an elevation of 11.5 feet NGVD, 1 on 5 side 
slopes, and protective vegetation. The sandfill berm 
would slope from an elevation of 8.5 feet NGVD at the 
toe of the dune 180 feet gulfward to an elevation of 3 
feet NGVD and, from this point, would assume its 
natural slope to the offshore bottom. The jetty provided 
by the plan has a top width of 6 feet at an 
elevation of 4 feet mean sea level, 1 on 2 side slopes, 
and extends approximately 3,600 feet along the western 
end of the island at Caminada Pass. Estimated 
cost of project (October 1991) is $20,321,000 Federal 
and $12,779,000 non-Federal, including $7,547,000 
contributed funds. 
Local cooperation. Local interests have the 
responsibility of providing rights-of-way, 30 percent 
of hurricane protection costs, 75 percent of beach 
erosion costs, and operation and maintenance of the 
completed work. The Louisiana Legislature, by Act 
833 of 1982, authorized the Office of Public Works 
of the Louisiana Department of Transportation and 
Development to provide the non-Federal assurances 
for the Grand Isle Hurricane Protection and Beach 
Erosion Project. On Jan.11, 1983, the Louisiana 
State Government authorized the Office of Public 
Works to execute the required assurances as a cosponsor 
with the town of Grand Isle. The required 
assurances were executed on Mar. 10, 1983, the construction 
rights-of-way were provided on May 4, 
1983, and local interest provided a cash contribution 
of $2,100,000 on Jun. 1, 1983, $70,000 in November 
1985, $368,000 in September 1987 and $259,000 in 
May 1989. An additional $4,750,000 has been deposited 
in escrow to complete restoration of the dune. 
Maintenance of the project is the responsibility of 
the local assurer. The local assurer will receive 
Federal aid for repairing erosion and other damage 
to the project for a period of 15 years. The average 
annual Federal maintenance cost identified in the 
Act of Assurances is $44,000; however, this is not a 
fixed amount. Periodic nourishment to repair erosion 
will not necessarily be conducted every year, 
but as needed, with an estimated frequency of one 
in eight years on the average. It is estimated that 
the Federal share of the maintenance cost will be 12 
percent for the 15-year period. 
Operations and results during the fiscal year. 
No work performed during FY 92. 
Condition as of Sep. 30. The repair and restoration 
of Grand Isle were accomplished by two separate 
contracts. The jetty extensions and sand bar removal 
contract (partial fix), which was completed in early 
1988. The dune repair and structural reinforcement 
contract was physically completed Sep. 4, 1991. An 
O&M Manual has been approved. The project has 
been turned over to the state of Louisiana for operation 
and maintenance. 
5. LAKE PONTCHARTRAIN AND 
VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In southeastern Louisiana, vicinity of 
New Orleans, in St. Charles, Jefferson, Orleans, St. 
Bernard, and St. Tammany Parishes, comprising 
lower land and water area between Mississippi River 
alluvial ridge and the Pleistocene escarpment to north 
and west. The dominant topographic feature is Lake 
Pontchartrain, a shallow tidal basin, about 640 square 
miles in area and averaging 12 feet deep, connecting 
with lesser Lake Maurepas to the west and through 
Lake Borgne and Mississippi Sound to the Gulf to the 
east. The lake drains about 4,700 square miles of 
tributary area. (Refer to Geological Survey quadrangles 
Yscloskey and Malheureaux Point, Drum Bay, 
Door Point, Lake Eugenie, Oak Mound Bayou, Mitchell 
Keys, Lake Eloi, and Morgan Harbor; Engineer 
quadrangles Slidell, Covington, Ponchatoula, Springfield, 
Denham Springs, Donaldsonville, Mt. Airy, Bonnet 
Carre', Spanish Fort, Chef Menteur, Rigolets, St. 
Bernard, New Orleans, and Hahnville; and Coast and 
Geodetic Survey Charts Nos. 1115 and 1116. 
Existing project. Provides protection to the 
greater New Orleans area and other communities 
bordering Lake Pontchartrain from the effects of hurricane-
generated floods. The project is comprised of 
two major features: The Chalmette Area Plan and the 
High Level Plan. The Chalmette Area Plan consists of 
a levee and floodwall system around the Chalmette 
area and along the Mississippi River-Gulf Outlet, with 
connections to the Mississippi River levees. The High 
Level Plan provides for heightening and strengthening 
the existing hurricane protection levee systems in 
Orleans Parish and the east bank of Jefferson Parish, 
repairing and rehabilitating the Mandeville Seawall 
in St. Tammany Parish; building a new mainline 
hurricane levee on the east bank of the St. Charles 
Parish just north of U.S. Highway 61 (Airline Highway); 
raising and strengthening the existing levee 
which extends along the Jefferson-St. Charles Parish 
11-4

NEW ORLEANS, LA, DISTRICT 
boundary between Lake Pontchartrain and Airline 
Highway; and deferring construction of the proposed 
Seabrook lock until its feasibility as a feature of the 
Mississippi River-Gulf Outlet navigation project can 
be determined. Areas which will be enclosed by the 
levee and floodwall construction will be provided protection 
against tidal surge resulting from the Standard 
Project Hurricane (SPH). The estimated project 
cost for work (October 1992) is $501,000,000 Federal 
and $195,000,000 non-Federal. 
Local cooperation. Provide all rights-of-way; 
bear 30 percent of the first cost, consisting of fair 
market value of providing all lands, easements, and 
rights-of-way, including borrow and spoil disposal 
areas for construction, accomplish alteration and relocation 
of roads, railroads, pipelines, cables, wharves, 
drainage structures, and other facilities; maintain 
and operate all works after completion; and hold and 
save the United States free from damages. See H. Doc. 
No. 231, 89th Cong., 1st sess. for more detailed requirements 
of local cooperation. 
Assuring Agency: The Orleans Levee District, 
Lake Borgne Basin Levee District, St. Bernard Parish 
Police Jury, Louisiana Office of Public Works, and 
Pontchartrain Levee District. The State of Louisiana 
formed the East Jefferson Levee District and assigned 
to it the east Jefferson Parish levees, previously the 
responsibility of the Pontchartrain Levee District. 
Basic assurances were received from the following: 
Orleans Levee District for the entire barrier plan and 
that portion of the Chalmette Area Plan in Orleans 
Parish; Pontchartrain Levee District for the Barrier 
Plan; Lake Borgne Levee District and St. Bernard 
Parish Police Jury for the Chalmette Area Plan in St. 
Bernard Parish. Supplemental assurances covering 
Public Law 91-646 have been received from the Orleans 
Levee District and the Pontchartrain Levee 
District. Lake Borgne Basin Levee District, St. Bernard 
Parish Police Jury, and the East Jefferson Levee 
District. The St. Tammany Parish portion of the project 
has been placed in an inactive status since the local 
sponsors have not provided acceptable assurances. 
Supplemental Assurances in connection with the 
High Level Plan were executed by the Orleans Levee 
District on May 29, 1985, and approved by the United 
States Jun. 21, 1985. Supplemental Assurances for 
the High Level Plan were executed by the East Jefferson 
Levee District for the Jefferson Parish portion of 
the project on Jan. 16, 1987. Supplemental Assurances 
for the High Level Plan were executed by the 
Pontchartrain Levee District for the St. Charles Parish 
portion of the project on Apr. 20, 1987, and accepted 
on behalf of the United States on Aug. 7, 1987. 
Supplemental Assurances for the High Level Plan are 
not required from St. Bernard Parish Police Jury and 
the Lake Borgne Basin Levee District for St. Bernard 
Parish. 
Operations and results during fiscal year. 
Preparation of design memorandums and plans and 
specifications continued by hired labor. One design 
memorandum was completed in FY 90. 
A Draft Reevaluation Report (including Draft Environmental 
Impact Statement) recommending the 
tentatively selected High Level Plan (lieu of Barrier 
Plan) was submitted by New Orleans District to the 
Lower Mississippi Valley Division in December 1983. 
The final Reevaluation Report was submitted to 
LMVD on Aug. 8, 1984. A Record of Decision was 
signed in February 1985 by the Office, Chief of 
Engineers. 
The final Environmental Impact Statement was 
filed with the Council on Environmental Quality on 
Jan. 17, 1975. By Court Order dated Dec. 30, 1977, a 
revised Environmental Impact Statement was ordered. 
A draft revised Environmental Impact Statement 
(EIS) for the High Level Plan and reevaluation 
report which documents the proposal to adopt that 
plan instead of the Barrier Plan was released to the 
public and filed with the Environmental Protection 
Agency on Dec. 16, 1983. The final revised Environmental 
Impact Statement was filed with the Environmental 
Protection Agency on Dec. 7, 1984. 
A draft mitigation report with corresponding EIS 
was prepared and distributed for public review on 
Mar. 16, 1988. A series of public meetings and workshops 
were held to facilitate participation in mitigation 
plan formulation by other agencies, environmental 
groups, local sponsors, and other interested 
groups. Prior to selecting the tentative plan, the three 
final plans were presented to the public at a meeting 
on Jul. 29, 1985. A final mitigation report is currently 
being prepared. The Louisiana Department of Natural 
Resources has agreed to fund the Local Sponsor's 
share of mitigation. 
Condition as of Sep. 30. Construction started 
May 1967 and is 80 percent complete. 
Contract work continued on nine contracts in FY 92 
and will continue on 17 contracts in FY 93. Five contracts 
were awarded in FY 92 and ten are scheduled 
for award in FY 93. Plans and specifications are underway 
on four contracts scheduled for award in 
FY 93. 
6. LAROSE TO GOLDEN MEADOW, 
LA (HURRICANE PROTECTION) 
Location. In coastal section of Louisiana, along 
Bayou Lafourche, and includes lands on both banks of 
the bayou from Larose to 2 miles south of Golden 
Meadow. (Refer to Geological Survey quadrangles 
Cutoff, Lake Felicity, Bay Dosgris, Golden Meadow 
Farms, Bay Tambour, Mink Bayou, Caminada Pass, 
Leeville, Belle Pass, Pelican Pass, and Calumet 
11-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Island; Engineer quadrangles New Orleans, Hahnville, 
Point a la Hache, Barataria, and Fort Livingston; 
and Coast and Geodetic Survey Charts Nos. 1115 
and 1116. 
Existing project. Provides a loop levee about 
40 miles long along both banks of Bayou Lafourche 
from Larose to South Golden Meadow; enlargement 
of 3 miles of existing levee at Golden Meadow; floodgates 
for navigation and hurricane protection in 
Bayou Lafourche at upper and lower bayo4 crossings; 
about 8 miles of low interior levees to regulate 
intercepted drainage. Estimated cost for new work 
(October 1992) is $79,800,000 Federal and 
$34,200,000 non-Federal. 
Local cooperation. Provide without cost to the 
United States all lands, easements, and rights-of-way, 
including borrow areas and spoil disposal areas, and 
accomplish alterations to roads, pipelines, cables, 
wharves, oil wells, and any other facilities necessary 
for the construction of the project; all at an estimated 
cost of $12,562,000; bear 30 percent of the total project 
cost, a sum presently estimated at $34,200,000 consisting 
of the items listed above, and a cash contribution 
presently estimated at $21,638,000 or equivalent 
work specifically undertaken as an integral part of the 
project after authorization and in accordance with 
construction schedules as required by the Chief of 
Engineers; hold and save the United States free from 
damages due to the construction works; maintain and 
operate all the works after completion in accordance 
with regulations prescribed by the Secretary of the 
Army; and prevent any encroachment on ponding 
areas unless substitute storage capacity or equivalent 
pumping capacity is provided promptly without cost 
to the United States; comply with the provisions of the 
Uniform Relocations Assistance and Real Property 
Acquisition Policies Act of 1970 (Public Law 91-646) 
and with the provisions of Section 221 of the Flood 
Control Act of 1970 (Public Law 91-611) in acquiring 
real property. 
The Board of Commissioners of the South Louisiana 
Tidal Water Control Levee District executed the 
required Agreement of Local Cooperation on Nov. 13, 
1972, which was executed by the United States on Jul. 
J 0, 1973, and approved on behalf of the Secretary of 
the Army on Aug. 29, 1973. Section 38, Paragraph 
1051 et seq., Louisiana Revised Statutes created the 
South Lafourche Levee District. The South Lafourche 
Levee District assumed the rights and obligations of 
the South Louisiana Tidal Water Control Levee District 
with respect to this project. Local interests have 
requested and received funds from the State of Louisiana 
for right-of-way acquisition and relocations required 
to support construction work. 
Operations and results during fiscal year. 
One contract was completed in FY 92. Plans and 
specifications are underway on two contracts scheduled 
for award in FY 1993. Planning, engineering, and 
design activities will continue in FY 93 for future 
construction work. 
Condition as of Sep. 30. Construction commenced 
in February 1972 and is 73 percent complete. 
7. MORGAN CITY AND 
VICINITY, LA 
(HURRICANE PROTECTION) 
Location. In south-central Louisiana, Morgan 
City proper, and the adjacent areas. It includes the 
land south of Grand Lake, Six Mile Lake, and Lake 
Palourde extending from Morgan City westward to 
Charenton drainage and navigation canal. Lower 
Atchafalaya River and Wax Lake Outlet, the principal 
outlets for Atchafalaya Basin Floodway, traverse the 
area. Gulf Intracoastal Waterway crosses the area in 
an east-west direction. Numerous bayous and artificial 
canals excavated for drainage purposes or for 
access to oil developments exist throughout the area. 
(See Engineer quadrangles Bayou Sale, Jeanerette, 
Foster, Belle Isle, Point Au Fer, Morgan City, and 
Lake Decade; and Coast and Geodetic Survey Chart 
1116.) 
Existing project. Morgan City: Construction of 
about 5.6 miles of new levees along shore of Lake 
Palourde and west bank of Bayou Ramos and about 
0.5 mile of new levee from Southern Pacific railroad 
embankment near Wyandotte to tie in with Bayou 
Boeuf lock levee, and construction of three gravity 
drainage structures. 
Franklin and vicinity: Enlargement of about 21.6 
miles of back levee and construction of about 3.5 miles 
of new levees to effect a complete closure of area to be 
protected, construction of one floodgate and eight 
gravity drainage structures, and alteration of existing 
drainage facilities where necessary. Normal range of 
tide is 1.6 feet. Storm and hurricane tide have produced 
elevations up to 10 feet while northerly storms 
during winter depress the gulf level as much as 3 feet 
below mean sea level. During low water periods on 
Atchafalaya River, generally September through November, 
the effect of tide extends about 35 miles above 
Morgan City. 
Local cooperation. For details see page 11-8 of 
the FY 1986 Annual Report. 
Operations and results during period. The 
GDM for the Morgan City area was completed in FY 
1985. 
Condition as of Sep. 30. Due to lack of financial 
local support this project has been moved to a deferred 
status. 
11-6

NEW ORLEANS, LA, DISTRICT 
8. NEW ORLEANS TO VENICE, LA, 
HURRICANE PROTECTION 
Location. Includes land subject to inundation by 
hurricane tides extending along both banks of the 
Mississippi River below New Orleans from vicinity of 
Phoenix to Venice, LA. 
Existing project. Provides for improvements 
along Mississippi River below New Orleans, LA, for 
prevention of hurricane tidal flood damages by increasing 
heights of existing back levees and modifying 
existing drainage facilities where necessary in three 
separate reaches: Reach A, on the west bank from City 
Price to Empire, 15 miles, 4,340 acres protected; 
Reach B, on the west bank from Empire to Venice, 21 
miles, 4,900 acres protected; and Reach C, on the east 
bank from Phoenix to Bohemia (construction recently 
completed by local agency with credit given as equivalent 
work), 16 miles, 5,470 acres protected, and raising 
the river levee on the west bank (MR&T levee) 
from City Price to Venice, to a grade high enough to 
prevent overtopping by tidal surges from the east, 
generally called the West Bank River Plan. Reach B 
was later divided into two units, Reach B-1 from 
Empire to Fort Jackson and Reach B-2 from Fort 
Jackson to Venice, LA, as a result of a request made 
by the local agency. 
Estimated cost of new work (October 1992) is 
$168,000,000 Federal and $72,000,000 non-Federal, 
including $54,798,000 cash contributions or equivalent 
work. 
Local cooperation. Provide all lands, easements, 
and rights-of-way including borrow areas and spoil 
disposal areas necessary for the construction of the 
project, at costs presently estimated at $7,053,000; 
accomplish all necessary alterations and relocations 
to roads, pipelines, cables, wharves, and other facilities 
required by the construction of the project at costs 
presently estimated at $10,149,000; bear 30 percent 
of the first cost, a sum presently estimated at 
$72,000,000, and cash contribution presently estimated 
at $54,798,000 to be paid either in a lump sum 
prior to initiation of construction or in installments 
prior to start of pertinent work items, in accordance 
with construction schedules as required by the Chief 
of Engineers, or as a substitute for any part of the cash 
contribution, accomplish in accordance with approved 
construction schedules items of work of equivalent 
value as determined by the Chief of Engineers, the 
final apportionment of costs to be made after actual 
costs and values have been determined; hold and save 
the United States free from damages due to the construction 
works; maintain and operate all works after 
completion in accordance with regulations prescribed 
by the Secretary of the Army; prevent any encroachment 
on ponding areas unless substitute storage capacity 
or equivalent pumping is provided promptly; 
and at least annually, notify those affected that the 
project will not provide complete protection from tidal 
flooding and that further local actions must be taken 
during hurricane emergencies. 
Local interests are also required to comply with the 
provisions of the Uniform Relocation Assistance and 
Real Property Acquisition Policies Act of 1970 (Public 
Law 91-646), in acquiring real property. 
Public Law 91-611. Not applicable. Construction 
started prior to Jan. 1, 1972. 
Public Law 91-646. A constitutional amendment 
was provided by the Louisiana Legislature on Feb. 1, 
1972, allowing local interests to comply. The estimated 
cost to local interests is $48,000. 
Assurances of local cooperation for Reaches A, B-i, 
B-2, and C, furnished by the Plaquemines Parish 
Commission Council were accepted on behalf of the 
United States on Apr. 14, 1965. Supplemental assurances 
covering provisions of the Uniform Relocations 
Assistance and Real Property Acquisition Policies Act 
of 1970, Public Law 91-646, furnished by the 
Plaquemines Parish Commission Council were accepted 
on behalf of the United States on Jun. 20, 1973. 
Local interests were requested to furnish separate 
assurances for the East Bank Barrier Levee on Jun. 
10, 1975, Feb. 23, 1976, and again on Aug. 19, 1983. 
By letter dated Feb. 5, 1985, the local sponsor requested 
the Corps of Engineers to defer further work 
on the design of Reach A and direct their efforts 
toward earliest possible construction of the East Bank 
Barrier Levee or a suitable alternative thereto. The 
Corps, with the concurrence of the local sponsor, selected 
a West Bank Levee alternative to the East Bank 
Barrier. On Dec. 29, 1987, the local sponsor provided 
supplemental assurances for the West Bank River 
Levee. These assurances were accepted on behalf of 
the United States on Jan. 28, 1988. By letter dated 
Jul. 28, 1987, the local sponsor also requested the 
Corps of Engineers to advance construction on Reach 
A, based on the results of the geotextile test 
section. 
All negotiations for relocations are the responsibility 
of local interests. These mainly consist of raising 
several petroleum and natural gas pipelines to the 
levee configuration and relocation of privately owned 
frame structures used as fishing and boating camps. 
To assure that there will be no delay in construction 
of levees, local interests are notified well in advance 
so that the owners of the pipelines can be advised. 
The local sponsor has requested that an area extending 
from the upstream limits of Reach A at City 
Price to St. Jude, Louisiana be incorporated into the 
project. This work involves upgrading 3.3 miles of 
existing non-Federal levees to project standards. The 
local sponsor has elected to pay all of the costs of this 
reach of levee. While the sponsor will not receive credit 
for these costs, the increased protected area would be 
eligible for Federally subsidized flood insurance. A 
11-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Postauthorization Change report was prepared for 
this reach and was approved by the Lower Mississippi 
Valley Division on March 6, 1992. 
Assuring Agency: Plaquemines Parish Government. 
Assurances for all reaches of the project have 
been furnished, except for the City Price to St. Jude 
reach. We anticipate that Plaquemines Parish Government 
will execute the assurances for this reach in 
FY 93. 
Operations and results during fiscal year. 
Construction during FY 92 was initiated on two 
contracts and continued on nine others. Plans and 
specifications were initiated on three construction 
items. 
Condition as of Sep. 30. Construction began on 
the project in September 1968 and the total project is 
approximately 62 percent complete. 
9. WESTWEGO TO HARVEY CANAL, 
LA (HURRICANE PROTECTION) 
Location. The project includes the Urban area 
within Jefferson parish between Westwego and the 
Harvey Canal on the west bank of the Mississippi 
River in the vicinity of New Orleans, Louisiana. 
The project area is generally bounded by the Harvey 
Canal to the east, Lakes Cataouatche and Salvador to 
the west, the Mississippi River to the north, and 
Barataria Bay to the south. 
Existing project. The project will provide protection 
for about 43,000 acres of urban land within Jefferson 
Parish, Louisiana, on the west bank of the 
Mississippi River. The plan of protection consists of 
about 22 miles of floodwalls and new and enlarged 
levees designed to protect against tidal floodwaters 
resulting from the Standard Project Hurricane (SPH). 
The SPH has a frequency of recurrence of once in 
about 500 years. The elevation of the SPHIT floodwalls 
and levees varies from 9 feet NGVD to 17 feet NGVD. 
The project plan includes mitigation which consists of 
the construction of a timber pile and tire breakwater 
on the west bank of Lake Cataouatche adjacent to the 
Salvador Wildlife Management Area and the acquisition 
and management of 1,024 acres of wooded 
wetlands. 
The estimated project cost (October 1992) is 
$91,300,000 ($59,300,000 Federal and $32,000,000 
non-Federal). 
Local cooperation. The Local Cooperation 
Agreement between the Department of the Army and 
the West Jefferson Levee District was signed on Dec. 
18, 1990. 
The West Jefferson Levee District has agreed to the 
following items of local cooperation: 
(1) Provide all lands, easements, and rights-ofway, 
including borrow and excavated material disposal 
areas necessary for construction, operation, and 
maintenance of the project. (The current estimate is 
$6,734,000.) 
(2) Accomplish all necessary alteration and relocations 
to roads, railroads, pipelines, cables, wharves, 
and other facilities required by the construction of the 
project. (The current estimate is $8,095,000.) 
(3) Hold and save the United States free from 
damages due to the construction, operation, and maintenance 
of the project, except where such damages are 
due to the fault or negligence of the United States or 
its contractors. 
(4) Bear 35 percent of the first cost of construction. 
(The current estimate is $32,000,000.) Funds provided 
by non-Federal interests for interim hurricane protection 
may be considered beneficial expenditures and 
may be credited as a part of the non-Federal contribution 
of the project pursuant to the Water Resources 
Development Act of 1986 and subsequent policies. 
(5) Maintain and operate all features of the project 
in accordance with regulations prescribed by the Secretary 
of the Army, including levees, floodgates and 
approach channels, drainage structures, drainage 
ditches or canals, floodwalls, and stoplog structures. 
(6) Provide a cash or in-kind contribution for fish 
and wildlife mitigation features of the project in an 
amount equal to the same percentage as the non-Federal 
share of the basic project. 
(7) Comply with the applicable provisions of the 
Uniform Relocations Assistance and Real Property 
Acquisition Policies Act of 1970 (PL 91-646). 
(8) Comply with Section 221 of Public Law 91-611, 
Flood Control Act of 1970; and 
(9) Comply with Section 601 of Title VI of the Civil 
Rights Act of 1964 (PL 88-352) that no person shall be 
excluded from participation in, denied the benefits of, 
or subjected to discrimination in connection with the 
project on the grounds of race, creed, or national 
origin. 
Requirements of PL 91-611 and 91-646: 
(1) Local interest are legally qualified to execute 
the assurances. 
(2) A constitutional amendment was provided by 
the Louisiana legislature on Feb. 1, 1972, allowing 
local interest to comply. 
The local sponsor (West Jefferson Levee District) 
applied for and received ASA (CW) approval (May 13 
1988) for $6.7 million, subject to audit, for work accomplished 
during the 5-year period prior to project 
authorization. 
Operations and results during fiscal year. 
Construction was completed on the mitigation break- 
11-8

NEW ORLEANS, LA, DISTRICT 
water at the west bank of Lake Cataouatche, and 
construction continued on the LA Hwy 45 Levee and 
the East of Vertex Levee (non-Federal contract). All 
three contracts were awarded in FY 91. The Company 
Canal Floodwall contract was awarded in Sep. 1992. 
Conditions as of Sep. 30. Project construction 
began in Feb 1991 and is 10 percent complete. Completion 
is scheduled in 2002. 
10. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(a) Various hurricane protection projects, as well 
as small flood control projects, were inspected during 
FY 1992. Also, periodic inspection and continuing 
evaluation of completed civil works structures was 
conducted in accordance with ER 1110-2-100, at various 
times during the year on an as needed basis. 
Fiscal year costs for the period were $274,965. Total 
costs to Sep. 30, 1992, were $3,607,204. 
(b) Mississippi River and Tributaries floodwalls, 
levees and flood control projects were inspected during 
FY 1992. Also, periodic inspection and continuing 
evaluation of completed civil works structures was 
conducted in accordance with ER 1110-2-100, at various 
times during the year on an as-needed basis. 
Fiscal year costs for the period were $148,231. Total 
costs to Sep. 30, 1992, were $853,010. 
11. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, 
flood fighting, and rescue work. (Public Law 99, 
84th Cong., and antecendent legislation.) 
Disaster preparedness, fiscal year costs for the period 
were $159,096. 
Emergency operations costs for FY 92 were 
$155,353. 
Rehabilitation costs for FY 91 were $85,000. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Detailed studies cost as of Sep. 30, 1992, Bayou 
Chevreuil and Grand Bayou, LA, at a cost of $2,475; 
and Choctaw Bayou, LA, $4,301. 
Flood control activities pursuant to Sec. 14, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Detailed studies costs as of Sep. 30, 1992, on Mississippi 
River at So. University, Baton Rouge, LA, $75; 
and Parish Road 218, Mermentau River at Grand 
Chenier, LA, $301. 
11-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 11-A COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
1. Mississippi 
River-Gulf 
Outlet, LA 
(Regular Funds) 
(Contrib. Funds) 
2. Mississippi 
River Ship 
Channel-Gulf 
to Baton Rouge 
(Contrib. Funds) 
4. Grand Isle 
and Vicinity, 
LA 
(Contrib. Funds) 
5. Lake Pontchartrain 
and Vicinity, 
LA (Hurricane 
Protection) 
(Regular Funds) 
(Contrib. Funds) 
6. Larose to Golden 
Meadow, LA 
(Hurricane 
Protection) 
(Contrib. Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
1,450,000 1,369,000 1,841,000 1,619,000 95,996,200 
1,370,207 1,516,752 1,451,762 1,897,964 95,826,974 
4,469,000 6,456,396 9,740,000 13,269,000 
4,809,722 6,438,802 9,416,764 11,720,482 
149,752,476 
147,858,689 
-- 1,240,4771 
-- 1,196,4771 
1,167,000 894,000 1,250,000 61,000 11,699,000 
820,130 1,194,808 1,295,924 331,875 12,273,202 
318,000 
671,315 
-- 275,000 3,157,000 
-- 247,622 3,057,937 
1,901,000 2,507,000 3,257,000 
1,849,231 1,824,391 3,162,024 
259,000 1,600,000 3,116,000 
258,318 1,422,827 2.754,182 
-- 10,740,776 
-- 10,732,538 
0 18,708,500 
319,518 18,133,535 
0 7,623,000 
185,990 7,159,317 
9,214,000 32,882,000 -4,989,000 9,852,000 
13,770,957 17,751,531 8,979,174 11,257,484 
636,579 
404,647 
389,181 
3,265 
255,070,000 
254,093,848 
505,000 1,200,000 4,920,800 
-- 269,246 3,064,000 
2,675,000 4,316,000 2,644,000 747,000 61,983,000 
2,386,886 4,486,100 2,991,299 1,102,724 61,947,724 
-- 2,000,000 
105,760 -- 2,000,000 
11-10

NEW ORLEANS, LA, DISTRICT 
TABLE 11-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
7. Morgan City and New Work 
Vicinity, LA Approp. -- -- -- 1,953,000 
(Hurricane Cost -- -- -- 1,975,628 
Protection) 
8. New Orleans to New Work 
Venice, LA Approp. 17,200,000 18,325,000 17,682,000 14,006,000 129,331,000 
(Hurricane Cost 16,623,500 14,616,098 19,822,229 15,250,568 128,211,879 
Protection) 
(Regular Funds) 
(Contrib. Funds) New Work 
Contrib. -- 153,720 3,086,488 2,791,000 10,790,197 
Cost -- 153,720 779,420 4,401,640 10,093,769 
9. Westwego to New Work 
Harvey Canal, Approp. 1,050,000 1,085,000 3,341,000 723,000 7,199,000 
LA (Hurricane Cost 1,291,000 911,000 2,119,975 1,974,712 7,055,687 
Protection) 
1. Contributed by Board of Commissioners, Port of New Orleans, for providing fill for future industrial sites 
adjacent to turning basin and for dredging cable and pipeline crossings. 
11-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 11-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Water 
Resources 
Development 
Act, 1986 
Mar. 2, 1945 
Oct. 23, 1962 
Mar. 29, 1956 
Oct. 22, 1976 
Water 
Resources 
Development 
Act, 1986 
Approp. Act of 
1985, dated 
Jul. 2, 1986 
(PL 99-88) 
LAKE CHARLES, LA 
The project for deepening of the project for navigation, Lake 
Charles, Louisiana, to a depth of 45 feet, at a total cost 
of $1,070,000. 
MISSISSIPPI RIVER, BATON ROUGE TO GULF OF 
MEXICO, LA 
Combines projects of Mississippi River, Baton Rouge to New 
Orleans, Mississippi River, South Pass, and Southwest 
Pass, adding thereto project for Mississippi River from New 
Orleans to Head of Passes, to provide a single project, 
"Mississippi River, Baton Rouge to the Gulf of Mexico," 
with channel dimensions as follows: Baton Rouge to New 
Orleans, 35 by 500 feet; port limits of New Orleans, 35 by 
1,500 feet; New Orleans to Head of Passes, 40 by 1,000 feet; 
Southwest Pass, 40 by 800 feet; Southwest Pass Bar 
Channel, 40 by 600 feet; South Pass, 30 by 450 feet; South 
Pass Bar Channel, 30 by 600 feet. 
Deepen existing channel from 35 to 40 feet by 500 feet wide 
from one-tenth mile below Louisiana Highway Commission 
bridge at Baton Rouge to upper limits of Port of New 
Orleans, and also 40 by 500 feet within presently 
authorized 35- by 1,500-foot channel in port limits of New 
Orleans. 
MISSISSIPPI RIVER-GULF OUTLET, LA (See Sec. 1 of 
Text) 
Construct a seaway canal 36 feet deep and 500 feet wide from 
Michoud to 38-foot contour in gulf and an inner tidewater 
harbor consisting of a 1,000- by 2,000-foot turning basin 
36 feet deep and a connecting channel 36 feet deep and 
500 feet wide to Inner Harbor Navigation Canal and 
provides, when economically justified, for construction of a 
lock to Mississippi River in the vicinity of Meraux, LA. 
Amends above Act making the construction of bridge 
relocations a Federal responsibility when required by the 
the construction of the Mississippi River-Gulf Outlet 
channel. 
The Mississippi River-Gulf Outlet feature is modified to 
provide that the replacement and expansion of the existing 
industrial canal lock and connecting channels or the 
construction of an additional lock and connecting channels 
shall be in the area of the existing lock or at the Violet 
site. 
MISSISSIPPI RIVER SHIP CHANNEL, GULF TO 
BATON ROUGE, LA (See Sec. 2 of Text) 
Will provide more efficient deep-draft navigation access to the 
New Orleans and Baton Rouge reaches of the Mississippi 
River via Southwest Pass by enlarging the existing channel 
to a project depth of 55 feet and enlarging the adjacent 
channel along the left descending bank in New Orleans 
Harbor to a 40-foot depth, a turning basin at Baton Rouge, 
and training works in the passes to reduce maintenance. 
Public Law 99-662, 
Nov. 17, 1986 
H. Doc. 215, 
76th Cong., 1st sess. 
S. Doc. 36, 
87th Cong., 1st sess. 
H. Doc. 245, 
82d Cong., 1st sess. 
Sec. 186, Water 
Resources Development 
Act of 1976 
(PL 94-587) 2d sess. 
Public Law 99-662, 
Nov. 17, 1986 
H. Doc. 2577, 
99th Cong., 1st sess. 
11-12

TABLE 11-B 
(Continued) 
NEW ORLEANS, LA, DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 17, 1986 
(PL 99-662) 
Aug. 30, 1985 
Oct. 23, 1962 
Water 
Resources 
Development 
Act, 1986 
Adopted by 
Committee 
Resolutions 
Sep. 23, 1976, 
and Oct. 1, 
19762 
Oct. 27, 1965 
Water 
Resources 
Development 
Act, 1986 
Nov. 17, 1988 
Formalizes the cost sharing provisions of the project, permits 
the State of Louisiana to enact user fees to defray their 
portion of the project costs, and implements harbor 
maintenance fees to help pay for the Federal cost of the 
project. It also provides an option to the local sponsor to 
defer their initial payment for one year following initiation 
of construction. In terms of channel depths up to 45 feet, 
the cost sharing requirements are 75 percent Federal and 
25 percent non-Federal for construction and 100 percent 
Federal for maintenance. For channels deeper than 45 feet, 
the cost sharing requirements are 50 percent Federal and 
50 percent non-Federal for both construction and 
maintenance. 
WATERWAY FROM INTRACOASTAL WATERWAY TO 
BAYOU DULAC, LA (Bayous Grand Caillou and LeCarpe, 
LA) 
Channel 5 by 40 feet from Intracoastal Waterway at Houma 
through Bayou LeCarpe, Bayou Pelton, and Bayou Grand 
Caillou to Bayou Dulac, about 16.3 miles. 
Channel 10 by 45 feet in Bayou LeCarpe from Gulf 
Intracoastal Waterway to Houma navigation canal. 
BAYOU RIGOLETTE, LA 
A project to construct six additional floodgates at Bayou 
Rigolette, LA, adjacent to the existing drainage structure, 
at a total cost of $2,300,000. 
GRAND ISLE AND VICINITY, LA (See Sec. 4 of Text) 
To provide hurricane protection by placement of a berm and 
vegetated dune extending the length of Grand Isle's gulf 
shore and a jetty to stabilize the western end of the island 
at Caminada Pass. 
LAKE PONTCHARTRAIN AND VICINITY, LA 
(HURRICANE PROTECTION) (See Sec. 5 of Text) 
Control of hurricane tides by construction of two independent 
units, the Lake Pontchartrain Barrier plan and the 
Chalmette Area plan. 
LAKE PONTCHARTRAIN, NORTH SHORE, LA 
The project for navigation, Lake Pontchartrain North Shore, 
LA: Report of the Chief of Engineers, dated February 14, 
1979, at a total cost of $1,310,000, with an estimated first 
Federal cost of $655,000 and an estimated first non-Federal 
cost of $655,000. 
Water Resources 
Development Act of 
1986, 99th Cong., 
2d sess. 
H. Doc. 206, 
72d Cong., 1st sess. 
Public Law 99-662, 
Nov. 17, 1986 
H. Doc. 639, 
94th Cong., 2d sess. 
H. Doc. 231, 
89th Cong., 1st sess. 
Public Law 99-662, 
Nov. 17, 1986, 
99th Cong., 2d sess. 
11-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 11-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Oct. 27, 1965 
Oct. 23, 1962 
Water 
Resources 
Development 
Act, 1986 
LAROSE TO GOLDEN MEADOW, LA (HURRICANE 
PROTECTION) (See Sec. 6 of Text) 
A loop levee about 36 miles long along both banks of Bayou 
Lafourche from Golden Meadow to Larose; enlargement of 
3 miles of existing levee at Golden Meadow; floodgates for 
navigation and hurricane protection in Bayou Lafourche at 
upper and lower bayou crossings; about 8 miles of low 
interior levees to regulate intercepted drainage; and seven 
multibarreled culverts controlled by flapgates. 
MORGAN CITY AND VICINITY, LA, HURRICANE 
PROTECTION (See Sec. 7 of Text) 
Construction of new levees along Lake Palourde and Bayou 
Ramos, levee to tie-in with Bayou Boeuf lock levee and three 
gravity drainage structures in Morgan City unit and 
enlargement of bank levee, construction of new levee, and 
construction of one floodgate and five gravity drainage 
structures in Franklin and vicinity unit. 
NEW ORLEANS TO VENICE, LA, HURRICANE 
PROTECTION (See Sec. 8 of Text) 
Improvements along Mississippi River below New Orleans, 
LA, for prevention of hurricane tidal flood damages by 
increasing heights of existing back levees and modifying 
existing drainage facilities where necessary in five separate 
reaches. 
WEST BANK HURRICANE PROTECTION LEVEE, 
JEFFERSON PARISH, LA, Westwego to Havery Canal 
(See Sec. 9 of Text) 
Structural and nonstructural measures to prevent flood 
damage to those areas identified in the Feb. 1984 draft 
Environmental Impact Statement for the West Bank 
Hurricane Protection Levee, Jefferson Parish, LA, at a total 
cost of $61,500,000, with an estimated first Federal cost of 
$40,000,000 and an estimated first non-Federal cost of 
$21,500,000. Funds provided by non-Federal interest for 
interim hurricane protection may be considered beneficial 
expenditures and may be credited as part of the non- 
Federal contribution of the project pursuant to Section 104 
of this Act. 
H. Doc. 184, 
89th Cong., 1st sess. 1 
H. Doc. 167, 
89th Cong., 1st sess. 
H. Doc. 550, 
87th Cong., 2d sess. 
Public Law 99-662, 
Nov. 17, 1986 
1. Contains latest published map. 
2. Permanent Appropriation Repeal Act. 
11-14

NEW ORLEANS, LA, DISTRICT 
TABLE 11-C OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1992 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Alteration of Berwick Bay Bridge1 
Amite River and Bayou Manchac, LA 
Aquatic Plant Control Program, LA 
Atchafalaya River Bayous Chene 
Boeuf, and Black, LA 
Atchafalaya River, Morgan City to Gulf 
of Mexico, LA 
Barataria Bay Waterway, LA 
Bayou Bonfouca, LA 
Bayou Dorcheat, Logy Bayou and 
Lake Bisteneau, LA,3,4,5 
Bayou Dupre, LA 
Bayou Lacombe, LA 
Bayou Lafourche and Lafourche Jump 
Waterway, LA 
Bayou La Lautre, St. Malo, and 
Yscolskey, LA 
Bayou Plaquemine Brule, LA 
Bayou Queue de Tortue, LA 
Bayou Segnette Waterway, LA 
Bayou Teche, LA 
Bayou Teche & Vermilion River, LA 
Bayou Terrebonne, LA3 '7 
Bayou Vermilion, LA3 
Big Pigeon and Little Pigeon Bayous, LA 
Calcasieu River and Pass, LA 
Calcasieu River at Coon Island, LA8 
Calcasieu River at Devil's Elbow, LA 
Cascasieu River Salt Water 
Barrier, LA9 
Cane River, LA2'5 
Chefuncte River and Bogue Falia, LA 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA10 
Freshwater Bayou, LA 
Grand Bayou Pass, LA 
Gulf Intracoastal Waterway between 
Apalachee Bay, FL, & Mexican Border 
Houma Navigation Canal, LA 
Inland Waterway from Franklin 
to Mermentau River, LA1' 11 
Intracoastal Waterway from the 
Mississippi River to 
Bayou Teche, LA12 
Lake Charles Deep Water Channel, LA1 3 
Leland Bowman Lock, LA 
Little Caillou Bayou, LA 
Mermentau River, Bayou Nezpique, 
and Bay Des Cannes, LA 
Mermentau River, LA 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
CoCmompplelteete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
-- 
Complete 
Complete 
Complete 
Complete 
1967 
1978 
1984 
1984 
1981 
1984 
1974 
1887 
1968 
1967 
1984 
1970 
1950 
1970 
1958 
1984 
1983 
1961 
1947 
1936 
1984 
1976 
1981 
1973 
1910 
1967 
1971 
1984 
1950 
1985 
1984 
1960 
1956 
1950 
1987 
1973 
1977 
1985 
$ -- 
28,234 
16,411,921 
30,356,691 
501,963 
1,572,685 
30,997 
5,000 
38,915 
4,716 
1,624,424 
96,916 
33,410 
33,355 
238,828 
754,330 
2,891,822 
120,089 
34,900 
27,830,835 
1,015,81410 
5,856,200 
4,197,262 
2,500 
58,342 
202,817 
7,116,224 
7,676 
$ 
69,087 
-- 
75,947,924 
24,573,336 
320,758 
-- 
104,187 
119,191 
2,172,246 
223,616 
36,780 
28,315 
651,956 
6,680,950 
1,753,062 
251,691 
200,169 
37,169 
128,553,811 
--
.-- 
2,000 
463,401 
452,611 
23,679,484 
14,48010 
1914 
Nov. 1963 
1931 
1939 
1938 
May 1956 
1915 
Mar. 1923 
Mar. 1957 
1916 
1896 
2 
Oct. 1968 
Apr. 1974 
Sep. 1978 
Jan. 1968 
1959 
Dec. 1914 
Aug. 1968 
1939 
63,284,470 442,146,350 
-- 24,123,692 
249,052 
-- 
32,200,010 
77,761 
5,197,97514 
4,672,579 
552,780 
11,699 
241,896 
751,485 
114,519 
26,712,867 
2 
Mar. 1985 
1929 
Jul. 1952 
11-15 
1928

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 11-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(Continued) 
Cost to Sep. 1992 
For Last Mo. and Yr. 
Full Report Operation Completed 
See Annual and Deauthorized 
Project Status Report For: Construction Maintenance or Reclassified 
Mississippi River Baton Rouge to 
Gulf of Mexico, LA -- 1991 84,568,12816 691,607,95317-- 
Mississippi River-Gulf Outlet, 
Michoud Canal, LA Complete 1976 2,499,555 -- Nov. 1974 
Mississippi River Outlets, Venice, LA Complete 1986 10,014,012 18,933,089 Complete 
Navigation work under special 
authorization (Calcasieu Pass 
channel in Old River Bend 
at Cameron, LA) 15 -- 1957 -- 139,755 -- 
Pass Manchac, LA Complete 1950 79,845 13,545 1912 
Petite Anse, Tigre, and 
Carlin Bayous, LA Complete 1981 -- 1,450,172 Nov. 1980 
Removal of Aquatic Growth, LA 1984 -- 32,307,860 
Sulphur River, AR and TX2'5 -- 1919 45,989 -- --. 
Tangipahoa River, LA -- 1985 -- 1,050,201 -- 
Tickfaw, Natalbany, Ponchatoula, 
and Blood Rivers, LA3 Complete 1973 8,115 92,163 1921 
Waterway from White Lake to 
Pecan Island, LA11 -- 1948 10,904 0,742 -- 
Waterway from Empire, 
LA, to Gulf of Mexico Complete 1981 1,068,142 1,510,719 Jun. 1950 
Waterway from Intracoastal Waterway 
to Bayou Dulac, LA Complete 1990 641,608 1,276,032 Aug. 1964 
1. Transferred to Department of Transportation. Authorized under Truman-Hobbs Act. 
2. Completed. Date will be furnished when available. 
3. Includes previous project costs. 
4. No commerce reported. 
5. Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess. 
6. Completed except that portion above mile 10.3 providing for widening from 40 feet to 60 feet, which is inactive. 
7. By Public Law 88-404, that portion of Bayou Terrebonne between point where Barrow Street crosses said stream and a 
line determined by prolonging and extending eastern right-of-way line of New Orleans Boulevard southerly to south bank 
of said stream was declared nonnavigable. 
8. Includes $66,000 contributed funds. 
9. Operation and maintenance of the structure reported under project "Calcasieu River and Pass, LA." 
10. Excludes $50,000 contributed funds. 
11. Not completed; incorporated in navigation project "Mermentau River, LA." 
12. Not completed; superseded for most of it length by present 12- by 125-foot Gulf Intracoastal Waterway, which coincides 
with or parallels it. 
13. Maintenance project; no future work schedules. 
14. Includes $57,555 ($29,974 of which was from Public Works funds) for new work on previous project. Includes $114,519 for 
maintenance of previous project. 
15. Work is under continuing authority. 
16. Includes $1,729,989 for previous project. 
17. Does not include allotment of $40,000 (9613123). 
18. Does not include expenditures of $63,370 (9613123). 
19. Includes $169,055 for previous projects and $3,379,676 from permanent indefinite appropriation. 
11-16

NEW ORLEANS, LA, DISTRICT 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
TABLE 11-D 
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Amite River and Tributaries, LA 1964 3,034,2551 -- Feb. 1964 
Bayou Choupique, LA2 1954 129,930 -- Mar. 1954 
Bayou Rapides, LA2 1952 95,179 -- Dec. 1951 
Harvey Canal, Bayou Barataria Levee, LA 1979 1,018,005 -- -- 
1. In addition, the following was expended from contributed funds: 
Amite River and tributaries ..................... $ 430 
Harvey Canal, Bayou Barataria Levee, LA .......... 425,209 
2. Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act, as amended) 
11-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 11-E DEAUTHORIZED PROJECTS 
For Last Full Date Federal Contributed 
Report See Annual and Funds Funds 
Project Report for Authority Expended Expended 
Baton Rouge Harbor 
Segment Between 
Mi 2.5 and 5.0 
Bayou Grosse Tete, 
LA 
Lake Borgne and 
Chef Menteur 
Bulkheads and Jetties 
Vinton Waterway, LA 
1946 
1969 
1942 
1950 
Nov. 2, 1979 
Section 12, 
Public Law 93-251 
(WRDA 74) 
May 6, 1981 
DAEN-CWP-A Letter 
Subj: Completed 
Action on 5th 
Deauthorization Rpt, 
dated Jun. 17, 1981 
Nov 1979 
Nov. 2, 1979 
Section 12, 
Public Law 93-251 
(WRDA of 1974) 
11-18

NEW ORLEANS, LA, DISTRICT 
TABLE 11-F ACTIVE GENERAL INVESTIGATIONS 
(96X3121) 
Federal Cost Totals by 
Item and CWIS Number FY 92 Categories 
SURVEYS (Category 100) 
Navigation(110) 
Intracoastal Waterway Locks, LA-81289 $ 395,641 
Bayou Lafourche & Lafourche-Jump Waterway, LA-10009 19,406 
GIWW LA & TX Section-10032 8 
Mississippi River-Gulf Outlet, St. Bernard Parish, LA 
(Bank Erosion) - 10241 2,072 
Port of Cameron, LA-10360 123,502 
540,629 
Flood Control Studies(120) 
Amite River & Tributaries, LA-50100 314,595 
Jefferson-Orleans Parishes Urban Flood Control, LA-12863 653,043 
Lake Cataouatche Levee, LA-12864 258,809 
Louisiana Coastal Area, LA, Land Loss & Marsh Creation-12348 34,598 
Mermentau, Vermilion & Calcasieu Rivers & Bayou Teche, LA-34014 64,217 
West Bank of Mississippi River-Vicinity of New Orleans, LA-59360 159,282 
1,484,544 
Special Studies(140) 
Louisiana Coastal Wetlands, LA-14172 -128 
Miscellaneous Activities(170) 
Special Investigations-17250 64,795 
Interagency Water Resources Development 20,168 
National Estuary Program 18,218 
North American Waterfowl Management 4,241 
107,422 
Coordination Studies with Other Agencies(180) 
Planning Assistance to States(186)-14822 13,347 
Planning Assistance to States, LA 
Flood Damage-22001 21,336 
Water Supply-22002 26,876 
Wastewater Facilities Database-22003 8,809 
Digitized Flood Plain Mapping - 
Amite River Basin-22004 70,000 
Livingston Parish-Emergency Response-22005 6,862 
Lake Pontchartrain Wetland Demo-22006 3,224 
E. Baton Rouge Parish Digitized Mapping-22007 2,731 
St. Benard Parish Digitized Mapping-22008 1,760 
154,945 
TOTAL (Category 100) $2,287,412 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services(250) 
Flood Plain Management Services 162,979 
Oakdale, LA - 83003 101 
South East Louisiana Hurricane Evacuation - 83001 1,434 
Special Studies Computer Automation of Flood 
Hazard Data - 83005 18,292 
Sunset, LA-83004 5,897 
188,703 
TOTAL (Category 200) $188,703 
11-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 11-F ACTIVE GENERAL INVESTIGATIONS 
(96X3121) 
Item and CWIS Number 
PROJECTS NOT AUTHORIZED FOR CONSTRUCTION (Category 400) 
Flood Control Projects (450) 
Comite River, LA-77059 
TOTAL (Category 400) 
PROJECTS NOT AUTHORIZED FOR CONSTRUCTION (Category 600) 
Flood Control Projects (650) 
Tangipahoa, Tchefuncte, and Tickfaw Rivers, LA - 75457 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
Federal Cost 
FY 92 
$ 1,411,573 
$ 5,180 
11-20 
Totals by 
Categories 
$ 1,411,573 
$ 5,180 
$3,892,868

VICKSBURG, MS, DISTRICT* 
This district comprises western and central Mississippi, 
southern Arkansas, northern Louisiana, and a 
very small portion of southwestern Tennessee, embraced 
in drainage basins of eastern tributaries of 
Mississippi River south of Horn Lake Creek to and 
including Buffalo River; Pearl River Basin in Mississippi; 
independent tributaries of the Gulf of Mexico 
south of the Buffalo River Basin to the Mississippi- 
Louisiana state line; western tributaries of Mississippi 
River between White and Atchafalaya Rivers 
including Arkansas River Basin below a point 3 miles 
upstream from Pine Bluff and Arkansas River below 
mile 36.1 near Pendleton, AR; Ouachita and Black 
Rivers in Arkansas and Louisiana; and Red River in 
Louisiana and Arkansas to the Texas-Arkansas state 
line. The Vicksburg District territory encompasses 
68,000 square miles. 
IMPROVEMENTS 
Navigation Page 
1. Ouachita and Black Rivers below 
Camden, AR ..................... 12-2 
2. Red River emergency bank 
protection ...................... 12-2 
3. Red River Waterway-Mississippi 
River to Shreveport, La ............ 12-3 
4. Navigation work under special 
authorization ................... 12-3 
Flood Control 
5. Aloha Rigolette, LA ............... 12-3 
6. Bayou Bodcau and tributaries, 
AR and LA ..................... . 12-4 
7. Canal43,AR ..................... 12-4 
8. Chauvin Bayou, LA ................ 12-5 
9. Ouachita River Levees, LA ......... 12-5 
10. Ouachita River and tributaries 
AR and LA ....................... 12-5 
11. Pearl River Basin, MS and LA ...... 12-6 
12. Pearl River, Slidell, St. Tammany 
Parish, LA ....................... 12-7 
13. Porter Bayou, MS ................. 12-7 
14. Red River below Denison Dam 
(Vicksburg Dist.) .................. 12-7 
15. Red River below Denison Dam, levees 
and bank stabilization 
(Vicksburg District) ............... 12-8 
16. Red River Waterway-Shreveport, 
LA, to Index, AR ................. 12-8 
Flood Control (cont) 
17. Inspection of completed Flood 
Control Projects ................ 
18. Flood control work under 
special authorization ............. 
Tables 
Table 12-A 
Table 12-B 
Table 12-C 
Table 12-D 
Table 12-E 
Table 12-F 
Table 12-G 
Table 12-H 
Table 12-I 
Table 12-J 
Page 
12-8 
12-9 
Cost and Financial 
Statement............... 12-10 
Authorizing Legislation ... 12-12 
Ouachita and Black Rivers, 
AR and LA (9-Foot Project), 
Locks and Dams ......... .12-15 
Other Authorized Navigation 
Project .................. 12-16 
Ouachita River and Tributaries 
Existing Project .... 12-18 
Red River Below Denison 
Dam (Vicksburg District) 
New Projects ............ 12-19 
Red River Below Denison 
Dam (Vicksburg District) 
Incorporated Projects ..... .12-20 
Other Authorized Flood 
Control Projects ......... 12-21 
Deauthorized Projects .... 12-23 
Active General 
Investigations ........... .12-24 
12-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. OUACHITA AND BLACK RIVERS 
BELOW CAMDEN, AR 
Location. Ouachita River rises in Polk County, 
AR, and flows southeasterly and southerly about 600 
miles. Below its confluence with the Tensas and Little 
Rivers at Jonesville, LA, it is called Black River, which 
enters Red River 35.5 miles from the Mississippi 
River. 
Previous projects. See page 683 of Annual Report 
for 1962 for details. 
Existing project. See page 684 of Annual Report 
for 1962 for details of the old 6.5-foot navigation 
project. Modified project and project for Red River 
below Fulton, AR, provide for a channel 9 feet deep 
and 100 feet wide in Red River between Old River 
and mouth of Black River, and in Black and 
Ouachita Rivers from mouth of Black River to Camden, 
AR. Authorized features for the modified project 
include four new locks and dams, in-river construction 
dredging to achieve a 9-foot navigation 
channel depth, and channel realignment. All 4 locks 
and dams are complete and in operation and initial 
channel dredging is complete providing 9-foot navigation 
depth. Remaining work consists of realignment 
of 25 restricted bendway sites between river 
miles 195 at Sterlington, LA, and river mile 335 at 
Camden, AR, on the Ouachita River. With these 
improvements in place the river system will be navigable 
by a four-barge tow (two abreast) to Crossett, 
AR, river mile 237, and a two-barge tow (abreast) to 
Camden, AR. Mitigation features include the 
65,000-acre Felsenthal National Wildlife Refuge in 
Arkansas, the 18,000-acre D'Arbonne National 
Wildlife Refuge in Louisiana, a series of recreation 
facilities along the waterway, and improvements to 
Catahoula Lake to preserve it for migratory waterfowl. 
Estimated total cost for the nine-foot navigation 
project is $278,130,000, which includes 
$261,000,000 Federal costs and $17,130,000 non- 
Federal costs. 
Local cooperation. Local interests are required to 
furnish the construction rights-of-way for the realignment 
work. Seven of the 25 sites are within the 
Felsenthal National Wildlife Refuge and are already 
owned by the Federal Government. However, there 
have been no indications that the land for the remaining 
18 sites will be forthcoming because of strong 
opposition to the realignment work by local environmental 
groups. The six remaining recreation facilities 
are unscheduled at this time due to the lack of required 
cost sharing agreements. 
Terminal facilities. Public loading docks are at 
Columbia, LA, and Camden and Crossett, AR. Privately 
owned docks and loading and unloading facilities 
are at Columbia, Monroe, and Sterlington, LA, 
and El Dorado, Calion, and Camden, AR. Two grainhandling 
facilities and a petroleum-loading facility 
are in the vicinity of Jonesville, LA, and a grain-handling 
facility is in the vicinity of Acme, LA. 
Operations and results during fiscal year. 
Construction continued for installation of a hinged 
crest gate in the navigation pass of Felsenthal Lock 
and Dam. 
Maintenance dredging performed by the contract 
dredges Butcher, and Pontchartrain during the FY 92 
removed 676,065 cubic yards of material from the 
waterways. 
Condition as of Sep. 30. The project is 92 percent 
complete and provides limited navigation as far north 
as Camden, AR. All four locks and dams associated 
with the project are complete and in operation. Design 
and construction of the remaining features is on hold 
pending a consensus between the states of Arkansas 
and Louisiana concerning the type of development 
desired or the additional studies needed to reach a 
decision. 
2. RED RIVER EMERGENCY 
BANK PROTECTION 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red and Old 
Rivers between the Mississippi River and the head of 
the levee system above Index, AR. 
Existing project. Provides for realigning the 
banks by means of cutoffs and training works and 
for stabilizing banks by means of revetments, dikes, 
and other methods as emergency conditions may 
require in advance of developing the design for the 
entire Red River Waterway project. Estimated cost 
for this work (October 1992) is $90,762,000 Federal 
and $2,182,000 non-Federal, including a cash contribution 
of $7,000. 
Local cooperation. Fully complied with. For 
details see pages 11-19 to 11-20, Annual Report FY 
80.
Operations and results during fiscal year. 
Work by hired labor consisted of preparing plans and 
specifications, surveys, and general engineering. Slay 
Bend Revetment, river mile 339-R, was completed, 
and below Garland City Dikes Flood Damage Repair, 
Little River/Clipper Flood Damage 8(a), Young, 
Horseshoe, Kenny & Goose, Bear/Goose Lake Flood 
Damage Repair, and Bushy Revetment Flood Damage 
8(a) were initiated and completed. 
Condition as of Sep. 30. Construction was initiated 
in October 1972 and is 91 percent complete. 
12-2

VICKSBURG, MS, DISTRICT 
3. RED RIVER WATERWAY-PROJECT 
Mississippi River to Shreveport, LA Reach 
Location. From east central to northwest Louisiana 
along the Red and Old Rivers between the Mississippi 
River and Shreveport, LA. 
Existing project. Provide a navigation route from 
the Mississippi River at the junction with Old River 
via Old and Red River to Shreveport, LA, developing 
a channel approximately 236 miles long, 9 feet deep, 
and 200 feet wide. The development will include five 
locks and dams, realignment and contraction of the 
river as necessary to develop an efficient channel, and 
bank stabilization as necessary to hold the newly 
developed channel in position. Facilities to provide 
opportunities for recreation and for fish and wildlife 
development are an integral part of the project. Estimated 
cost for new work is $1,753,332,000 Federal 
and $93,503,000 non-Federal, including $47,418,000 
contributed funds. The Federal cost includes $332,000 
for aids to navigation by U.S. Coast Guard. 
Local cooperation. For details see page 11-21, 
Annual Report FY 80. 
The Red River Waterway Commission, governing 
body of the Red River Waterway District, executed 
an act of assurance for all project features in Louisiana 
on Feb. 26, 1969, supported by resolution 
dated Jan. 30, 1969. The assurances were accepted 
for and on behalf of the United States on Apr. 15, 
1969. The Commission furnished amended assurances 
covering the provisions of Public Law 91-646 
and Public Law 91-611 on May 23, 1973, for the 
portion of the project within Louisiana. These were 
accepted for and on behalf of the United States on 
Nov. 14, 1973. 
Terminal facilities. Local interests are to provide 
adequate terminal facilities along the waterway. The 
Corps entered into an agreement with the City of 
Alexandria, LA, whereby material excavated from the 
Philip Bayou Realignment could be used as fill for port 
construction at mile 109. Construction of the realignment 
and port fill are complete. 
Operations and results during fiscal year. 
Hired labor continued work on Design Memoranda, 
Project Cooperation Agreements, Plans and Specifications, 
Surveys, General Engineering, and Model Studies. 
The following contracts were awarded in FY 92: 
Pool 1 - Reinforcement Flood Damage Repair; Pool 2 - 
Lock and Dam 3 Downstream Dikes and Wiggins 
Capout; Pool 3 - Ile Au Vaches Capout; Pool 4 - Lock 
and Dam 4, Phase II; Pool 5 - Lock and Dam 5, Phase 
II, McDade Revetment, Sunny Pt. Dikes, Curtis Revetment, 
Cupples Capout. 
The following contracts were awarded and completed 
in FY 92: Pool 1 - Lock and Dam 1 Access Bridge 
and Boat Ramp, Joffrion Capout; Pool 2 - Deloges Bluff 
Capout; Pool 3- Fausse Capout, Smith Island Capout, 
Lumbra Capout; Pool 4- Carroll capout. 
Contracts continuing in FY 92 included: Pool 2 - 
L&A Railroad Bridge Relocation, Missouri-Pacific 
Railroad Bridge Modification, Lock and Dam 2 Resident 
Office Renovation & POL Building; Pool 3 - 
Grappe Realignment, Ph. II; Pool 4 - Piermont Realignment, 
Westdale Realignment; Pool 5 - Moss Revetment, 
Elm Grove Revetment, Cecile Revetment. 
Contracts continuing included: Pool 2 - Missouri- 
Pacific Railroad Bridge Modification L&A Bridge Relocation, 
L&D 3 Downstream Dikes; 
The following contracts were completed in FY 92: 
Pool 1 - Ben Routh Recreation Facilities, Hog 
Lake/Moncla/Larto Flood Damage Repair; Pool 2 - 
Alexandria Recreation Facilities, Deloges 
Bluff/Marteau Flood Damage Repair; Pool 3 - Lock 
and Dam 3, Ph. III, Socot Capout Campti/St. Maurice 
Flood Damage Repair; Pool 4- Bull Revetment Howard 
Realignment, Lock and Dam 4, Ph. I; Pool 5- Lock 
and Dam 5, Ph. I, Wilkerson Pt./Lucas Bend Flood 
Damage Repair. 
Maintenance dredging was performed by the Contract 
Dredges Butcher, Alabama, Pontchartrain, and 
Jahncke during Fiscal Year 1992. All maintenance 
dredging was below Alexandria, LA. 2,220,256 cubic 
yards of material was removed from the channel. 
Condition as of Sep. 30. Construction was initiated 
in July 1973, and project is 71 percent complete. 
Shreveport, LA to Daingerfield, TX Reach. 
4. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, 
Public Law 87-645, as amended. 
Reevaluation Studies of the authorized project and 
alternative plans were initiated in FY 89 at the direction 
of congress and continued in FY 92. 
Flood Control 
5. Aloha Rigolette, LA 
Location. The project is located in north-central 
Louisiana between the towns of Winnfield and Pineville 
on the left descending bank of the Red River. 
Authorized Project. The recommended plan consists 
of a three-barrel floodgate structure installed at 
the mouth of Bayou Darrow to reopen it to the Red 
River, 8.2 miles of clearing and snagging of Bayou 
Darrow from its mouth upstream, construction of a 
closure and low-flow structure on Bayou Rigolette just 
below its junction with Bayou Darrow, and 
12-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
realignment of Sam's Bayou and appropriate mitigation 
features. 
Local Cooperation. The City of Colfax, LA, has 
agreed to cost share this project. The Project Cooperation 
Agreement is scheduled to be signed in FY 93. 
Operations And Results During Fiscal Year. 
Continued work on plans and specification for the first 
item of work, Item 1. 
Condition as of Sep. 30. 
continuing. 
Design work is 
6. BAYOU BODCAU AND 
TRIBUTARIES, AR AND LA 
Location. In east bank flood plain of Red River. 
Bayou Bodcau rises in vicinity of Hope, AR, and flows 
southerly through Bayou Bodcau Reservoir and 
Bodcau Lake to join Cypress Bayou and form Red 
Chute Bayou, continues through Red Chute Bayou, 
Flat River, and Loggy Bayou to Red River, about 40 
miles below Shreveport, LA. 
Authorized project. Cypress Bayou-Red Chute 
Bayou levee: Extend existing levee from about 8 miles 
southeast of Benton, LA, proceeding southerly to 
junction of Cross and Red Chute Bayous, and then 
parallel to Red Chute Bayou on the right descending 
bank to its junction with Cutoff Bayou for a total 
distance of approximately 25 miles; construct landside 
drainage channel and several culverts with flap gates 
to Red Chute Bayou; construct approximately 5 miles 
of levee on left descending bank of Red Chute Bayou 
extending south from Louisiana Highway 612, and 
relocate utility lines as needed. 
Flat River-Loggy Bayou levee: Extend from lower 
end of existing Red River levee in vicinity of Ninock, 
LA, along high (left descending) bank of Red River to 
a point on right descending bank of Loggy Bayou, 
about 1 mile above its mouth, thence generally along 
right descending bank of Loggy Bayou, Red Chute, 
CutoffBayou, and Flat River to Taylortown to tie into 
existing Red River levee; close Flat River near its 
junction with Cutoff Bayou and install one 36-inch 
round corrugated metal pipe with automatic flap gate 
to drain isolated pockets and provide uninterrupted 
drainage; construct drainage structures on Flat River 
near its junction with Red Chute Bayou and along 
alignment of the Loggy Bayou in the vicinity of Grassy 
Lake; and make necessary utility relocations. 
Flat River channel improvement: Enlarge to average 
bottom width of 50 feet with flat side slopes and 
deepen by 2 to 6 feet from the confluence with Cutoff 
Bayou to junction with Cooper Bayou, 11.6 miles, 
including required relocations and modifications of 
utilities. 
The subject project was one of the Water Resources 
projects reviewed in March 1977 in accordance with 
the President request. As a result of this review, the 
President recommended that project construction be 
halted and the project be deauthorized. Congress subsequently 
directed the Corps to take the following two 
actions: Construct levees on Red Chute Bayou below 
Cutoff Bayou that are required to prevent induced 
flood damage that would otherwise result from the 
abandonment of partly completed project. Initiate 
studies to determine if modifications to the authorized 
project would permit its completion in a form consistent 
with the current executive policy. 
Engineering and design work for the induced flood 
prevention plan below Cutoff Bayou and project modification 
studies were being conducted when President 
Reagan signed, on Dec. 4, 1981, the Energy and Water 
Development Appropriations Bill of 1982, which contained 
language that "reconfirmed without further 
study and analysis" the plan for flood control for the 
project as approved by the Flood Control Act of 1965. 
Resumption of construction was scheduled to begin 
in 1984. The project sponsor, however, requested that 
construction be delayed while a reevaluation of the 
project was made. 
The reevaluation study has been completed. A summary 
of study results was submitted in January 1987 
which recommended no further Federal action. The 
Lower Mississippi Valley Division approved the report 
and a notice of study termination was disseminated 
in June 1987. 
Local cooperation. For details see pages 11-24 
and 11-25, Annual Report for FY 80. 
Operations and results during fiscal year. Red 
Chute Bayou Levee crevassed during the May-June 
1991 flooding and was repaired under contract with 
PL 84-99 funding. 
Condition as of Sep. 30. Construction was initiated 
in October 1974 and is 17 percent complete. 
Reconnaissance Studies of Flood Control Alternatives 
along Red Chute Bayou were initiated in November 
1991, as part of the Bossier Parish, LA, study. The 
reconnaissance phase is scheduled for completion in 
May 1993. Feasibility studies are scheduled for completion 
in 1996. 
7. CANAL 43, AR 
Location. Canal 43 drains into Lake Chicot and is 
located in Lincoln and Desha Counties,.Ar. 
Existing project. The plan of improvement provides 
for enlarging the channel beginning approximately 
1500 feet downstream of State Highway 54 
and extending approximately 11.2 miles upstream; 
and provides a 1-year frequency protection to adjacent 
agricultural lands. Total estimated Federal cost is 
$892,000. 
12-4

VICKSBURG, MS, DISTRICT 
Local cooperation. The Cummins Drainage District 
has provided the necessary rights-of-way for project 
construction plus cash requirements totaling five 
percent of the total project costs. In addition, the 
drainage district is accomplishing all required relocations 
and will operate and maintain the project upon 
completion. 
Condition as of Sep 30. The construction contract 
was awarded Sep. 12, 1989, and construction was 
essentially completed on Aug. 17, 1990. 
8. CHAUVIN BAYOU, LA 
Location. The Chauvin Bayou area is located immediately 
north of the city of Monroe, Louisiana. It is 
bounded on the west by the Ouachita River, on the 
north by Bayou Bartholomew, and on the east by 
Bayou DeSiard. 
Existing Project. The plan of improvement consists 
of a 250-cfs pumping plant located adjacent to 
Chauvin Bayou at the Ouachita River levee and a 
water control structure in Canal L-11. The project will 
provide the Chauvin Bayou area with improved flood 
protection. The total estimated Federal cost of the 
project is $4,248,000. 
Local cooperation. The city of Monroe, Louisiana, 
and the Ouachita Parish Police Jury are the 
local sponsors for the project. They are providing the 
necessary rights-of-way and relocations for project 
construction plus cash requirements totaling 
twenty-five percent of the total project costs. In 
addition, they will operate and maintain the project 
upon completion. 
Condition as of Sep 30. The construction contract 
for the Canal L-11 control structure was awarded Jun. 
29, 1991 and is substantially complete. The construction 
contract for the pumping plant was awarded in 
November 1991. The contract for Chauvin Bayou was 
awarded Nov. 7, 1991, and is approximately 43% 
complete. 
9. OUACHITA RIVER LEVEES, LA 
Location. East bank of Ouachita River between 
Bastrop, LA, and Sandy Bayou. Loop levees on the 
west bank at West Monroe, Columbia, and 
Bawcomville. 
Existingproject. There are 105.8 miles of levee on 
the east bank and 11.6 miles of levee in the three loops 
on the west bank. A letter report, approved by the 
Chief of Engineers, authorized gravel surfacing 40.3 
miles of levee, enlargement of 40.4 miles of levee, and 
a 5.7-mile southward extension of the east bank levee. 
Estimated Federal cost is $17,826,000. Estimated 
non-Federal cost is $5,174,000. 
Local cooperation. Requirements and assurances 
of local cooperation are fully described on page 
12-6 of FY 80 Annual Report. A supplemental agreement 
for the Bawcomville segment was executed in 
FY 90. 
The 1991 Water and Energy Appropriations Act 
gave the Federal government responsibility for the 
repair and/or replacement of the deteriorated drainage 
structures. The Assurances Agreement for Local 
Cooperation was supplemented to reflect this change 
in responsibility. The supplemental agreement covered 
work performed in Fiscal Year 1992. This agreement 
will be further supplemented to cover the work 
to be performed in Fiscal Year 1993. 
Condition as of Sep. 30. Item 1 of the Monroe to 
Sandy Bayou Levee enlargement project was completed 
Jul. 7,1978. Additonal work was deferred pending 
results of a comprehensive study of the entire 
Ouachita River Levee System. A summary report indicating 
that it is economically feasible to raise portions 
of the existing levee to authorized grade and that 
complete rehabilitation of the levee system is necessary 
was approved by LMVD on Oct. 1, 1986. The 
study results were disseminated to the project sponsor 
and interested parties in October 1986. The Project 
was reclassified as an active project on May 7, 1987. 
The final summary report was sent to the Office of the 
Chief of Engineers in July 1988 and design was initiated 
on the Bawcomville segment of the Ouachita 
River levees. A construction contract for the Bawcomville 
levee enlargement was awarded in FY 90, and is 
substantially complete as of Sep. 30, 1992. In FY 92, 
we lined three deteriorated culverts and awarded 
contracts to line nine additional culverts, replace one 
deteriorated drainage structure, and replace the 
headwalls and gates at 16 drainage structures. 
10. OUACHITA RIVER AND 
TRIBUTARIES, AR AND LA 
Location. Improvements comprising comprehensive 
projects are on main stem Ouachita River, AR and 
LA, on its tributaries, Caddo and Little Missouri Rivers, 
and in Pine Bluff, AR. Description of Ouachita 
River Basin is presented in greater detail on page 690 
of Annual Report for 1962. 
Existing project. The authorized general plan for 
flood control and other purposes in the Ouachita River 
Basin includes the projects listed in Table 12-E. The 
1966 Flood Control Act modified the Bayou 
Bartholomew and Tributaries, AR and LA, project to 
include 10 water-retention lakes in the western tributaries 
of Bayou Bartholomew in Arkansas and 6 local 
levee units along the main stem of the bayou in 
Louisiana. 
12-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Local cooperation. Fully complied with for completed 
features of comprehensive project. (See individual 
statements for further details.) 
Operations and results during fiscal year. 
Operations for Blakely Mt. Dam-Lake Ouachita, 
DeGray Lake, Narrows Dam-Lake Greeson, Bayou 
Bartholomew and Tributaries, and Ouachita River 
Levees are shown in individual reports in 1985. 
Condition as of Sep. 30. Pertinent data on those 
features which are complete or not started are in 
Table 12-E. Conditions of Blakely Mt. Dam-Lake 
Ouachita, DeGray Lake, and Narrows Dam-Lake 
Greeson are given in the individual reports in 1985 
report. 
A reconnaissance study for flooding problems in the 
vicinity of Hot Springs, Garland County, AR, has been 
completed. Feasibility studies were recommended and 
were initiated in FY 93. 
Construction on the Chauvin Bayou Project continues. 
Planning and design for the Youngs Bayou Project 
are still on hold due to the Sponsor's inability to 
participate in the project. 
11. PEARL RIVER BASIN, 
MS AND LA 
Location. The basin comprises most of the 
Southcentral portion of Mississippi and a small part 
of southeast Louisiana. The Pearl River begins in 
Neshoba County, MS, and flows southwesterly 113 
miles to the vicinity of Jackson, MS, then southeasterly 
233 miles to the vicinity of Bogalusa, LA. At that 
point, the Pearl River splits into the East and West 
Pearl Rivers, and flows southerly 44 and 48 miles, 
respectively, before entering the Rigolets and Lake 
Borgne. 
Existing projects. The Jackson-East Jackson 
Flood Control Project provides for improvements of 
the Pearl River at Jackson, MS. This project includes 
two levee systems totaling 13.1 miles in length, with 
two pumping stations, four gated outlets, and 5.34 
miles of channel rectification including three cutoffs 
with a total length of 2.2 miles in the Pearl River. This 
project was authorized by the Flood Control Act of Jul. 
14, 1960. Construction began in July 1964 and work 
was completed in FY 68. Total Federal cost of the 
project was $7,190,200. The FY 83 Jobs Bill authorized 
extension of the Jackson-East Jackson West 
Bank levee system along the Fortification Street 1-55 
exit. This extension was initiated and completed in FY 
84.
Public Law 98-63, dated Jul. 29, 1983, authorized 
the vicinity of Jackson project. This authority provided 
for additional measures to prevent recurring 
flood damages along the Pearl River at Jackson and 
included 3.3 miles of floodway clearing and enlarging 
the opening at the Highway 25 Bridge. This work has 
been completed. Mitigation lands for the clearing were 
purchased by the local sponsor in May 1985 and the 
Corps has reimbursed the local sponsor to cover the 
cost of these lands. Total Federal cost of this project is 
$1,800,000. 
Authorized projects. Public Law 99-88, dated 
Aug. 15, 1985, authorized planning, design, engineering, 
and construction of a levee system in Slidell, LA, 
to protect 3,265 residential and commercial structures 
from floods in the West Pearl. Public Law 99-662, 
dated Nov. 17, 1986, authorized construction of 
Shoccoe Dam and various flood control measures for 
Carthage-Leake County, MS. 
Local cooperation. For the Jackson-East Jackson 
and vicinity of Jackson projects, the requirements 
are as prescribed in Section 3 of the Flood Control 
Act of 1936, as amended. This Act requires that a 
local sponsor provide the easements, and rights-ofway 
necessary for construction of the project; hold 
and save the United States free from damages due 
to construction of the project; and maintain and 
operate all works after completion in accordance 
with regulations prescribed by the Secretary of the 
Army. The Slidell levee project authorization required 
cost-sharing and new guidelines for local 
cooperation. A Local Cooperation Agreement consistent 
with Public Law 99-88 was signed by the Slidell 
local sponsor and the Assistant Secretary of the 
Army for Civil Works on Jun. 30, 1986. The local 
sponsors are as follows: Jackson-East Jackson, Rankin-
Hinds Pearl River Flood Control Drainage District; 
Vicinity of Jackson Project, Pearl River Basin 
Development District; Slidell Levee Project, St. 
Tammany Levee Board. 
Condition as of Sep. 30. An overall basin study is 
essentially complete, except for alternative studies to 
Shoccoe Dry Dam as discussed below. Flood control 
feasibility studies for Jackson, MS, recommending 
Shoccoe Dam, and for Slidell, LA, recommending a 
15-mile levee system, have been completed. Detailed 
engineering and design studies were on hold for the 
Slidell levee system, due to the failure of a local 
funding referendum. The local sponsor is now seeking 
alternative funding sources. As a result of upstream 
opposition, Shoccoe Dam is not implementable. In 
response to a request by the local sponsor, the Pearl 
River Basin Development District, reconnaissance 
studies to evaluate alternatives to Shoccoe for flood 
damage reduction in the Jackson Metropolitan Area 
have been completed and a potentially feasible levee 
plan identified. A Feasibility Cost Sharing Agreement 
was signed with the Local Sponsor on Sep. 25, 1991, 
and feasibility studies are underway. Studies of various 
flood control measures for Carthage-Leake 
County, Columbia and Picayune, MS; Bogalusa, LA, 
and the Bogue Chitto Subbasin have been completed. 
12-6

VICKSBURG, MS, DISTRICT 
None were found economically feasible. Navigation 
studies have been conducted on the East and West 
Pearl Rivers. Results of these studies indicate that 
maintenance necessary to reopen the existing West 
Pearl River navigation project is economically justified. 
However, future dredging will depend on the 
outcome of the EIS which is scheduled to be completed 
in late FY 93. Studies also indicate that the East Pearl 
River does not have sufficient existing flows to support 
a 7- to 9-foot-deep navigation channel. The navigation 
study for Port Bienville, MS, has been terminated due 
to withdrawal of the Hancock County Port and Harbor 
Commission as local sponsor. Reconnaissance studies 
of flow distribution between the West Pearl River and 
the East Pearl River (boundary between the States of 
Louisiana and Mississippi) in the Lower Basin have 
been completed. A water resources development plan 
for flow redistribution in the Lower Basin was found 
economically feasible. However, the primary benefit 
of the plan would accrue to recreation. Reconnaissance 
studies did not find any problem that would be 
solved by a Federal project, given the current policies 
and priorities of the Administration. Reconnaissance 
studies of flood damage prevention and erosion control 
along Caney Creek in Jackson, MS, have been completed. 
These studies indicated that flood damages 
attributable to headwater flooding from Caney Creek 
are relatively insignificant and will not economically 
justify a water resource improvement plan under current 
conditions. Studies also found that most of the 
more serious streambank erosion problems along the 
creek have been corrected through actions undertaken 
by other public entities and agencies. 
12. PEARL RIVER, SLIDELL, 
ST. TAMMANY PARISH, LA 
Location. The project is located in the southeastern 
portion of the State of Louisiana and consists of 
the area bounded by the West Pearl River on the east, 
Interstate 10 on the west, and Lake Pontchartrain on 
the south. 
Authorized project. The project is broken into 
two segments of levees. The segment north of 1-10 will 
consist of 4.0 miles of levee, a pumping station, a 
floodgate structure, and minor drainage structures. 
This levee will protect the Slidell area north of 1-10 
from flooding associated with a 200-year hydrological 
event on the Pearl River. The segment south of 1-10 
will consist of 9.0 miles of levees, three pumping 
stations, floodgates, and minor drainage structures. 
This levee will protect the Slidell area south of 1-10 
from flooding associated with a 200-year hydrological 
event on the Pearl River and provides the same level 
of protection against hurricane surges. These two 
levee segments total 13 miles of levee and would 
protect some 3,029 homes. 
Local cooperation. The project sponsor, St. 
Tammany Levee Board, and the Assistant Secretary 
of the Army (Civil Works), in an agreement consistent 
with the Fiscal Year 1985 Supplemental Appropriation 
Act Public Law 99-88) and Senate Report 1567, 
signed the Local Cooperation Agreement Jun. 30, 
1986. 
Operations and results during fiscal year. 
Continued engineering studies to complete General 
Design Memorandum. 
Condition as of Sep. 30. Preparation of final 
General Design Memorandum is on hold pending 
identification of a source of funding for the project by 
locals. No construction has taken place. 
13. PORTER BAYOU, MS 
Location. Porter Bayou is located in Bolivar and 
Sunflower Counties, MS. It lies approximately 25 
miles east of the Mississippi River, is approximately 
5 miles south of Cleveland, MS, and runs through the 
town of Shaw, MS. 
Existing project. The plan of improvement called 
for selective snagging and clearing of Porter Bayou 
from mile 12.5 to mile 32.3. This plan provides a 
0.5-year frequency protection for the Porter Bayou 
area. All construction was performed from one side of 
the stream, leaving the other side undisturbed. The 
total estimated Federal cost of the project is $860,000. 
Local cooperation. Fully complied with. 
Condition as of Sep. 30. The original construction 
contract was completed in November 1983. However, 
the work on one reach of the stream (2.55 miles) 
remains unfinished due to a growth of aquatic weed 
that has never been successfully removed in spite of a 
previous attempt at biological (insect) treatment. 
With the exception of that one reach, the project was 
turned over to the local sponsor for operation and 
maintenance in May 1984. There are plans to treat the 
weed with a herbicide in FY 93 so that the remainder 
of the project can be turned over to the local sponsor 
and the project closed out. 
14. RED RIVER BELOW DENISON 
DAM (VICKSBURG DISTRICT) 
Location. On Red River and its tributaries below 
Denison Dam, in Oklahoma, Arkansas, Texas, and 
Louisiana. (Refer to Geological Survey State maps 
and folio "Maps of Red River" - 1958 edition.) 
Existing project. Flood Control Act of 1946 approved 
general plan for flood control on Red River 
below Denison Dam, TX and OK, which provides for 
construction of six flood control reservoirs in combina- 
12-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
tion with existing or authorized Federal and non-Federal 
levee improvements, modified as required, and 
channel stabilization at locations where levee setbacks 
are impossible or uneconomical. This act further 
authorized incorporation of several separate existing 
projects for flood damage prevention along Red River 
below Denison, above jurisdiction of the MRC, into 
this project. By Public Law 780, 83rd Cong., 2nd sess., 
as amended by Public Law 218, 84th Cong., 1st sess., 
and Public Law 645, 86th Cong., 1st sess., plan of 
improvement was amended to include additional projects 
as indicated in following lists of reservoirs and 
local protection works considered in general flood control 
plan for the Red River below Denison Dam, and 
existing flood control projects incorporated into project 
in Vicksburg District. (See Table 12-H for new 
projects and Table 12-I for incorporated projects.) 
Local cooperation. See individual reports herein. 
15. RED RIVER BELOW DENSION 
DAM, LEVEES AND BANK 
STABILIZATION 
(VICKSBURG DISTRICT) 
Location. Along the main stem of the Red River 
from the head of the levee system immediately above 
Index, AR, through the southwest corner of Arkansas 
to the vicinity of Boyce, LA, on the right bank, and 
Pineville, LA. on the left bank. 
Existing project. Raising and strengthening existing 
and authorized Red River levees to provide 
protection against flooding and bank protection works 
at locations where levee setbacks are impossible or 
uneconomical. The plan consists of raising and 
strengthening existing and authorized Red River levees 
to provide against a flood approximately 20 percent 
greater than the flood of 1945, the flood of record, 
as modified by authorized reservoirs. Bank protection 
works are to be constructed at locations where levee 
setbacks are impossible or uneconomical. Estimated 
cost for new work (October 1992) is $67,105,000 Federal 
and $1,560,000 non-Federal. 
Local cooperation. Requirements of local cooperation 
are fully described on page 12-10 of FY 1984 
Annual Report. 
Operations and results during fiscal year. 
Hired labor forces continued investigations, surveys, 
and preparation of plans and specifications. Construction 
of the McKinney Bayou Replacement floodgate 
and Dutch John Bottom Revetment were completed, 
and construction of Twelve-Mile Bayou Revetment 
was initiatied. 
Condition as of Sep. 30. Construction was initiated 
in February 1948 and the levees are complete and 
bank stabilization is 96 percent complete. 
16. RED RIVER WATERWAY 
SHREVEPORT, LA, TO 
INDEX, AR 
Location. In northwest Louisiana, southwest Arkansas, 
and northeast Texas, along the Red River 
between Shreveport, LA, and Index, AR. 
Existing project. To provide for realigning the 
channels of Red River from Shreveport, LA, to the 
levee system near Index, AR, by means of dredging, 
cutoffs, and training works and for stabilizing its 
banks by means of revetments, dikes, and other methods. 
Facilities to provide opportunities for recreation 
and for fish and wildlife development are an integral 
part of the project. Estimated cost for new work (October 
1989) is $249,000,000 Federal and $29,073,000 
non-Federal. 
Local cooperation. Requirements and assurances 
of local cooperation are fully described on pages 
12-10 and 12-11 of Fiscal Year 1984 Annual Report. 
Operations and results during fiscal year. 
Hired labor forces continued reevaluation studies. 
Condition as of Sep. 30. Construction has not 
been initiated. The reevaluation study was completed 
in January 1991. The study investigated the feasibility 
of providing bank stabilization and recreation features 
in the Shreveport to Index reach of the Red River 
Waterway Project. None of the solutions were found 
to be economically feasible. No further studies are 
planned at this time. 
17. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was accomplished at 
a cost of $270,287 for the fiscal year. Total cost as of 
Sep. 30, 1992, is $3,177,672. 
Emergency bank protection (Sec. 14 of 1956 
Flood Control Act, Public Law 780, 83rd Cong.) 
Total FY costs for emergency bank protection work 
was $183,283. This included work on Highway 119, 
Derry, LA, $28,898: Highway 438 Bridge, Bogue 
Chitto, LA., $139,832; Highway 495, Natchitoches 
parish, LA, $23,269; and Highway 3049, Caddo Parish, 
LA, $29. and Culley-Brashear Ditch, Madison 
County, MS, $11,075. 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Construction work continued on Chauvin Bayou, 
LA, at a cost of $1,721,264. Detailed studies continued 
on Calion, AR, at a cost of $31,343. Studies were 
terminated on Bayou DeSiard, Ouachita Parish, LA, 
12-8

VICKSBURG, MS, DISTRICT 
$3,417; Magnolia, AR, $4,094; Moorhead, MS, $3,063; 
Pine Creek, Franklin Parish, LA, $3,741; and Silver 
Creek, MS, $7,459. 
18. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, 
flood fighting, and rescue work. (Public Law 99, 
84th Cong., and antecedent legislation.) 
FY 92 costs for the period were $466,564 for disaster 
preparedness, $8,002 for advance measures, and 
$6,399 for hazard mitigation team activities. 
Rehabilitation costs for FY 92 were $291,286. 
Flood Emergency Operations costs for FY 92 were 
$2,417,508. This consisted of emergency operations 
conducted in FY 91 and reimbursed in FY 92 in the 
Ouachita/Black, Red, Yazoo, and the Sunflower River 
Basins in Arkansas, Louisiana, and Mississippi. 
Total Public Law 99 cost during FY 92 was 
$3,189,752. 
Snagging and clearing of navigable streams 
and tributaries in the interest of flood control 
(Sec. 208 of 1954 Flood Control Act, Public Law 
780, 83rd Cong.) 
No activity during the period. 
12-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-A COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
1. Ouachita and 
Black Rivers 
below Camden, 
AR (6.5-foot 
navigation 
project) 
Ouachita and 
Black Rivers 
below Camden, 
AR (9-foot 
navigation 
project) 
2. Red River 
Emergency Bank 
Protection 
(Contrib. Funds) 
3. Red River 
Waterway 
Mississippi 
River to 
Shreveport, LA 
(Contrib. Funds) 
5. Aloha- 
Rigolette, LA 
6. Bayou Bodcau 
and Tributaries, 
AR and LA 
7. Canal 43, AR 
(Contrib. Funds) 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
-- $ -- -- $ 5,248,6191 
-- 5,248,6191 
1,033,000 2,263,000 -830,000 100,000 229,974,251 
2,009,983 1,189,516 +874,028 195,727 229,443,265 
4,854,300 4,953,338 4,947,900 5,322,000 98,878,505 
4,953,458 4,797,841 5,047,000 5,341,565 98,625,269 
5,571,000 1,972,000 4,100,000 7,300,000 42,908,000 
4,175,110 2,771,269 2,336,140 4,211,400 35,202,497 
-- -- -- -- 6,825 
-- -- -- -- 6,825 
118,000,000 100,375,000 92,636,000 123,681,000 937,106,000 
121,938,473 96,280,732 91,320,805 135,607,493 917,738,198 
3,686,697 10,426,394 4,449,100 6,221,000 33,209,791 
3,642,852 6,570,884 8,294,163 5,423,654 31,805,347 
647,000 220,104 414,424 
212,000 401,864 493,480 
85,000 627,000 
53,818 696,305 
-- 31,086 
19,191
0 
1,402 
21,716 3,396,244 
-- 3,349,3923 
249,000 249,000 
243,637 243,637 
-- 1,038,000 
-- 1,037,952 
372,000 1,003,000 
400,856 772,921 
0 892,000 
348 870,326 
0 
25 32,473 
12-10

VICKSBURG, MS, DISTRICT 
TABLE 12-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
8. Chauvin Bayou New Work 
Approp. 
Cost 
9. Ouachita River New Work 
Levees, LA Approp. 
Cost 
10. Pearl River 
Vicinity of 
Jackson, MS 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
11. Pearl River, New Work 
Slidell, St. Approp. 
Tammany Parish, Cost 
LA 
12. Porter Bayou, 
MS 
14. Red River 
New Work 
Approp. 
Cost 
New Work 
below Denison Approp. 
Dam Levees and Cost 
Bank Stabilization 
(Vicksburg District) 
15. Red River 
Waterway, 
Shreveport, LA, 
to Index, AR 
New Work 
Approp. 
Cost 
660,000 240,000 1,301,000 700,000 3,261,000 
626,765 351,715 187,560 1,721,264 3,148,780 
292,000 943,000 388,000 2,429,758 6,868,758 
265,208 264,124 612,070 628,042 4,540,602 
3,530
0 
116,973 
-1,000 
--. 215 
-- 2,080,000 
-- 2,079,999 
-- 480,000 577,500 
-- 390,516 390,516 
585,000 750,000 659,000 100,000 3,456,000 
644,866 803,715 562,336 193,639 3,449,690 
0 1,035,278 
414 555,000 1,030,226 
1,300,000 300,000 3,561,000 2,300,000 67,105,000 
835,640 2,070,085 89,171 3,408,656 64,717,552 
-- 1,010,0003 
355,688 -- 855,497~ 
12-11 
1. Includes $674,068 for new work on previous projects. 
2. Includes $3,312,000 PL 98-8 Jobs Bill. Excludes $47,854,000 previously allocated to New Orleans District. 
3. Excludes New Orleans District allocation and cost.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
May 17, 1950 
Jul. 14, 1960 
Dec. 31, 1970 
Aug. 13, 1968 
Aug. 13, 1968 
Nov. 28, 1990 
Oct. 27, 1965 
Jun. 30, 1948 
Nov. 17,1986 
OUACHITA AND BLACK RIVERS BELOW CAMDEN, 
AR (See Section 1 of Text) 
Modification of existing project to provide for 9-foot channel 
and deepening canal to Felsenthal, AR. 
Modification of 9-foot project to provide four new locks and 
dams and channel improvements. 
Migratory waterfowl refuges on Bayou D'Arbonne in 
connection with the pool of the Columbia Lock and Dam 
and in the pool of the Felsenthal Lock and Dam. 
RED RIVER EMERGENCY BANK PROTECTION (See 
Section 2 of Text). 
Realining the banks by dredging cut-offs and training works 
and stabilizing banks by means of revetments and dikes. 
RED RIVER WATERWAY-MISSISSIPPI RIVER TO 
SHREVEPORT, LA (See Section 3 of Text) 
Develop a 9 by 200 feet, approximately 236 miles long from 
Mississippi River at junction of Old River via Old River 
and Red River to Shreveport, LA, consisting of realinement, 
bank stabilization, and construction five locks and dams. 
ALOHA-RIGOLETTE AREA, LA (See Section 5 of Text) 
BAYOU BODCAU AND TRIBUTARIES, AR AND LA 
(See Section 6 of Text) 
Extend Cypress Bayou-Red Chute Bayou levee, construct 
stream closure landside drainage channel and three 
culverts on Red Chute Bayou and clearing and snagging 
channel; extend Flat River-Loggy Bayou levee, close Flat 
River near junction wish Cutoff Bayou, and construct 
control structures on Flat River near junction with Red 
Chute Bayou; and enlarge Flat River channel to 20 to 35 
feet, a distance of 11.6 miles. 
CANAL 43, AR (See Section 7 of Text) 
Channel enlargement 
CANEY CREEK, MS 
Authorizes construction of such bank stabilization measures 
for Caney Creek in the vicinity of Jackson, MS, between 
McDowell Road and Raymond Road as the Secretary 
determines necessary for flood damage prevention and 
erosion control along approximately 3,000 feet of the creek. 
12-12 
S. Doc. 117, 
81st Cong., 1st sess. 
S. Doc. 112, 
86th Cong., 2d sess. 
Report of the Chief of 
Engineers dated 
Nov. 25, 1970, and 
H. Doc. 92-109, 
92d Cong., 1st sess. 
H. Doc. 304, 
90th Cong., 2d sess. 
H. Doc. 304, 
90th Cong., 2d sess. 
Public Law 101- 
101 Cong., 2nd sess. 
H. Doc. 203, 
89th Cong., 1st sess. 
Sec. 205 of the Flood 
Control Act of 1948, 
as amended 
Authorized by Chief 
of Engineers, 
October 31, 1988. 
Public Law 99-662, 
99th Cong., 2d sess.

VICKSBURG, MS, DISTRICT 
TABLE 12-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 30, 1948 
as amended 
Jun. 30, 1948, 
as amended 
Nov. 17, 1986 
May 17, 1950 
Jul. 14, 1960 
Jun. 13, 1983 
Jul. 29, 1983 
Aug. 15, 1985 
CHAUVIN BAYOU, LA (See Section 8 of Text) 
Construction of a 250-cfs pumping plant located adjacent to 
Chauvin Bayou at the Ouachita River levee and a water 
control structure in Canal L-11. 
LEAD BAYOU, MS 
Channel enlargement. 
MONROE AND WEST MONROE, LA, AND OUACHITA 
PARISH, LA 
Authorizes such structural and nonstructural measures as 
the Secretary deems feasible to prevent flood damage to 
the cities of Monroe and West Monroe, LA, and Ouachita 
Parish, LA. 
OUACHITA RIVER AND TRIBUTARIES, AR AND LA 
(See Section 10 of Text) 
Authorized DeGray Lake; Murfreesboro Lake; extension of 
floodwall at Monroe to partially close the existing gap; 
local protection at Bawcomville, LA (subsequently 
constructed under Sec. 6, Act of May 15, 1928, with local 
interests contributing one third of cost); Bayou Bartholomew 
channel improvement, including Deep Bayou and Overflow 
Creek; Pine Bluff local protection; local protection at 
Calion, AR; and incorporation, into the Ouachita River and 
Tributaries project, of all existing projects and portions 
thereof in the basin above the lower end of the levees on 
the east bank of the Ouachita River. In addition, the Chief 
of Engineers authorized on Nov. 14, 1966, additional work 
on the levees. 
PEARL RIVER, MS AND LA (See Section 11 of Text) 
Construction of levee system and channel rectification, Pearl 
River, vicinity of Jackson, MS 
Accomplish the clearing and channel improvements at 
Hwy 25 bridge on the Pearl River in the vicinity of 
Jackson, MS. 
Design and construct protection to prevent flooding along 
the Pearl River in the vicinity of Jackson, MS 
Planning, design, engineering, and construction of a levee 
system for Slidell, LA, pending binding cost-sharing 
arrangements acceptable to the Secretary of the Army or 
under terms and conditions provided in subsequent 
legislation when enacted into law. 
Sec. 205 of the Flood 
Control Act of 1948, 
as amended. 
Authorized by the 
Chief of Engineers 
Feb. 6, 1990. 
Sec. 205 of the Flood 
Control Act of 1948, 
as amended. 
Authorized by Chief 
of Engineers 
Jun. 10, 1980. 
Public Law 99-662, 
99th Cong., 2d sess. 
S. Doc. 117, 
81st Cong., 1st sess. 
H. Doc. 441, 
86th Cong., 1st sess. 
S. Doc. 153, 
98th Cong., 1st sess. 
Public Law 98-63, 
98th Cong., 1st sess. 
Public Law 99-88, 
99th Cong., 2d sess. 
12-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-B 
(Continued) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Nov. 17, 1986 
Nov. 17, 1986 
Jun. 30, 1948, 
as amended 
Nov. 17, 1986 
Jul. 24, 1946 
Aug. 13, 1968 
Aug. 13, 1968 
Authorizes the Pearl River Basin, including Shoccoe, MS, for 
the construction of the Shoccoe Dam plus upstream flood 
control measures at east-central Leake County, south part 
of Carthage, MS, Highway 35 vicinity, upstream reservoirs 
on the Pearl River and upstream channels on the Pearl 
River and elsewhere in Leake County. 
PEARL RIVER, SLIDELL, ST. TAMMANY PARISH, LA 
(See Section 12 of Text) 
Authorizes flood control improvements for Pearl River Basin, 
St. Tammnany, LA, subject to a favorable Chiefs report and 
approval by the Secretary of the Army for Civil Works. 
PORTER BAYOU, MS (See Section 13 of Text) 
Selective snagging and clearing of Porter Bayou, MS, from 
mile 12.5 to mile 32.3 
RED RIVER WATERWAY, LA (See Section 14 of Text) 
Water Resources Development of 1986 authorized for 
construction the project for mitigation of wildlife losses, 
Red River Waterway, LA, which may include all or such 
portion of any land adjacent to the Loggy Bayou Wildlife 
Management Area. 
RED RIVER BELOW DENISON DAM LEVEES AND 
BANK STABILIZATION (VICKSBURG DIST.) (See 
Section 15 of Text) 
Levee and bank stabilization. 
Deauthorization of Morringsport Dam and Reservoir on 
Cypress Creek; realining and stabilizing the banks of the 
Red River; and recreational facilities from the Mississippi 
River to Denison Dam, OK and TX. 
RED RIVER WATERWAY-SHREVEPORT, LA, TO 
INDEX, AR (See Section 16 of Text) 
Provides for realinement of the channels of the Red River 
from Shreveport, LA, to Index, AR. 
Public Law 99-662, 
99th Cong., 2d sess. 
Public Law 99-662 
99th Cong., 2d sess. 
Sec. 205 of the Flood 
Control Act of 1948, 
as amended. 
Authorized by Chief 
of Engineers, 
Feb. 18, 1982. 
Public Law 99-662, 
99th Cong., 2d sess. 
H. Doc. 602, 
79th Cong., 2d sess. 
H. Doc. 304, 
90th Cong., 2d sess. 
H. Doc. 304, 
90th Cong., 2d sess. 
12-14

TABLE 12-C OUACHITA AND BLACK RIVERS, AR AND LA 
(9-FOOT PROJECT), LOCKS AND DAMS 
(See Section 1 of Text) 
Min. 
Depth 
Greatest on 
Available Lower 
Miles Length Max. Elev. Miter 
Above Width for Full Lift Normal Still at 
Miles Mouth of Width at Pool Normal Per- Total 
from of Lock of Lock Low Surface Pool Character cent Estimated 
Nearest Black Chamber Chamber Water (feet Level or Kind of Type of Com- Project 
Location Town River (feet) (feet) (feet) msl) (feet) Foundation Dam Construction plete Cost 
Jonesville, LA 10 25 84 600 30 34 14 Piling Moving Tainter gated dam; 1002 $43,400,000 
bascule gated 
navigation pass; 
steel mitering lock 
gates 
Columbia, LA 5 117 84 600 18 52 13 do do Tainter gated dam; 952 45,200,000 
fixed crest 
navigation pass; 
steel mitering lock 
gates 
Felsenthal, AR 1 227 84 600 18 701 13 Earth do Tainter gated dam; 882 101,600,000 
hinged crest gated 
navigation pass; 
steel mitering lock 
gates. 
Calion, AR 7 283 84 600 12 77 13 do do Tainter gated dam; 882 70,800,000 
(H. K. hinged crest gated 
Thatcher) navigation pass; 
steel mitering lock 
gates. 
Estimated Federal Cost $261,000,000 
Estimated Non-Federal Cost 17,130,000 
Total Estimated Cost 278,130,000 
1. Fish and wildlife impoundment level. Navigation pool elevation 65. 
2. The percent complete reflects all work within the pool. 
or 
Ax 
I2 
0d

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-D OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For Construction Maintenance Completed 
Bayou Bartholomew, LA and AR 1 " 2' 3'4 
-- 1931 $ 45,874 $ 42,857 1 
Bayous D'Arbonne and Corney, LA1'2,4 -- 1941 19,000 37,804 1 
Big Black River, MS" 4'5 -- 1895 15,000 -- 
Big Sunflower River, MS" 4'6'7 -- 1942 560,027 459,328 1 
Boeuf River, LA"13'4'7',89, -- 1949 30,000 103,737 1 
Claiborne County Port, MS -- 1985 2,000,000 270,252 Dec. 1983 
Cypress Bayou and Waterway between 
Jefferson, TX, and Shreveport, LA15 Complete 1971 202,817 452,611 Dec. 1914 
Homochitto River, MS4 -- 1910 15,482 8,518 1 
Lake Providence Harbor, LA -- 1985 208,537 3,943,443 Nov. 1963 
Little Missouri River, AR"14'5 -- 1873 19,992 -- 1 
Little River, LA"4'5"0 -- 1890 1,500 -- 1 
Little Tallahatchie River, MS" 7 -- 1913 19,000 -- 1 
Madison Parish Port, LA -- 1985 656,000 593,571 Dec. 1980 
Mouth of Yazoo River, MS"7"' -- 1953 1,179,211 605,6411 
Ouachita and Black Rivers, AR and LA, 
Felsenthal Canal -- 193712 -- 4,387,1921 
Overton-Red River Waterway, LA -- 1985 -- -- 1 
Pearl River, MS -- 1985 8,562,908 3,011,812 1956 
Red River below Fulton, AR"' 6" 7"8 -- 1978 1,963,806 2,147,8901 
Red River Waterway 
LA, AR, OK, and TX"7,1 8 -- 1969 -- -- 1 
Red River Waterway, Shreveport, LA 
to Daingerfield, TX' -- 1976 150,800 -- 1 
Removings snags and wrecks from 
Mississippi River below mouth of 
Missouri River and from Old and 
Atchafalaya Rivers" -- 1948 -- 272,5001 
Rosedale Harbor, MS -- 1985 2,000,000 3,411,836 Sep. 1978 
Saline River, AR 1 3'4'5 -- 1931 26,900 12,792 x 
Tallahatchie and Coldwater 
Rivers, MS1,4'5 
-- 1939 43,481 173,066 
Tensas River and Bayou 
Macon, LA"8," 2 
-- 1949 38,367 85,352 
12-16

VICKSBURG, MS, DISTRICT 
TABLE 12-D OTHER AUTHORIZED NAVIGATION PROJECTS 
(Continued) 
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Status Report For. Construction Maintenance Completed 
Yalobusha River, MS ,'4,51' 4 -- 1937 7,000 15,936 1 
Yazoo River, MS -- 1987 9,341,826 1,201,895 1 
Yellow Bend Port, AR Complete 1991 3,793,069 -- Aug. 1991 
1. Status and Date unavailable. 
2. Abandonment recommended in H. Doc. 1962, 64th Cong., 2d sess., and H. Doc. 467, 69th Cong., 1st sess. 
3. Channels adequate for existing commerce. 
4. Inactive project. No commerce. 
5. Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess. 
6. Project curtailment recommended by elimination of work between Pentecost and mouth of Hushpuckena River. 
(Abandonment of entire project erroneously recommended in H. Doc. 467, 69th Cong., 1st sess.) 
7. See report of Mississippi River Commission for operations in connection with Yazoo Basin. 
8. Report of New Orleans District, pp. 919-920 for Fiscal Year 1949. 
9. Project curtailment recommended by elimination of work above Girard, LA. (Abandonment of entire project recommended 
erroneously in H. Doc. 467, 69th Cong., 1st sess.) 
10. Due to decline of traffic, local interests not sufficiently interested to provide rights-of-way and dumping privileges. 
11. No additional funds available under this project. Work is being carried on under appropriation flood control, Mississippi 
River and tributaries. 
12. Year authorized. 
13. Inactive. Channel adequate for commerce. 
14. See report of Mississippi River Commission for operations in connection with Yazoo Basin flood control project including 
channel clearing and rectification and Grenada Lake on Yalobusha River. 
15. Excludes $50,000 contributed funds. 
16. Includes $1,553,878 for previous projects. 
17. Incorporated in the project "Red River Waterway-Mississippi River Shreveport, LA" Sept. 30, 1976. 
18. Emergency bank protection on this project is reported separately as "Red River Emergency Bank Protection." Two 
reaches, "Red River Waterway-Mississippi River to Shreveport, LA" and "Red River Waterway-Shreveport, LA, 
Daingerfield, TX," are also reported separately. 
12-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-E OUACHITA RIVER AND TRIBUTARIES: 
EXISTING PROJECT 
(See Section 10 of Text) 
For Last Estimated 
Full Report Federal 
See Annual New Work 
Project Report for: Cost 
Blakely Mt. Dam-Lake Ouachita, AR 1985 $ 44,100,000 
DeGray Lake, AR 1985 72,034,0002 
Narrows Dam-Lake Greeson, AR 1985 20,900,000 
Calion, AR 1960 970,9963 
Columbia, LA 1941 204,7403 
Existing levees and extensions thereto from Bastrop, LA, to mouth 
of Boeuf River and at West Monroe, LA 1961 3,025,1813 
Little Missouri River below Murfreesboro, AR 1957 354,8023 
Ozan Creek, AR 1957 57,7423 
Terre Noire Creek, AR 1948 123,7003 
Pine Bluff, AR, local protection 1954 172,5823 
Monroe, LA, floodwall extension (Plan B) 1984 2,561,0003 
Ouachita River Levees (additional work) (1) 9,400,000 
Total $153,904,7434 
1. 
2. 
3. 
4. 
See individual reports herein. 
Includes $5,800,000 for water supply to be reimbursed by local interests. 
Actual cost of completed project. 
Excludes the authorized Murfreesboro Lake, AR, project, which is inactive. The latest estimated cost 
(1954)was $4,190,000. 
12-18

VICKSBURG, MS, DISTRICT 
TABLE 12-F RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): NEW PROJECTS 
(See Sec. 14 of Text) 
Drainage Conserva- Flood 
Area tion Control Estimated 
(square Storage (acre- Federal 
Project Stream miles) (acre-feet) feet) Cost 
Bayou Bodcau and tributaries, AR2 and LA -- 1,158 -- -- $25,100,0003 
Bayou Nicholas-Coushatta, LA -- -- -- -- 70,7174 
Bayou Pierre in vicinity of Shreveport, LA5 -- -- -- -- 243,3363 
Caddo Lake, LA' Caddo Lake -- -- -- 3,586,000 
Campti-Clarence Area in 
Natchitoches Parish, LA Red River -- -- -- 1,950,0003 
Garland City, AR1"6 -- -- -- -- 1,450,0003 
Maniece Bayou, AR -- -- -- -- 970,0323 
McKinney Bayou, AR7'8 -- -- -- -- 5,610,0003 
Posten Bayou, AR and LA2 '6'9 -- -- -- -- 560,000 
Red River below Denison Dam levees 
and bank stabilization, TX, AR, and LA1 "3 -- -- -- -- 66,775,0003 
Total 99,191,885 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
9. 
Details presented in individual report herein. 
Construction on this project not started. 
In addition, non-Federal funds are: 
Bayou Bodcau and tributaries, AR and LA ................................................... $5,300,000 
Bayou Pierre in vicinity of Shreveport, LA (cash contribution) ..................................... 89,047 
Caddo Lake, LA ....................................................................... 28,000 
Campti-Clarence Area in Natchitoches Parish, LA ............................................. 480,000 
East Point ......................... .................................................... 67,000 
Garland City, AR . ......... ............................................................ 6,000 
Maniece Bayou, AR (cash contribution) ...................................................... 18,000 
McKinney Bayou, AR (cash contribution)......................................................... 508,000 
Red River below Denison Dam, levees and bank stabilization, TX,AR, and LA ........................ 1,560,000 
For last full report, see Annual Report for 1964. 
For last full report, see Annual Report for 1951. 
Inactive. 
Includes $4,330,200, Code 711, and $399,739 accelerated Public Work funds. 
Joint-use pool (sediment). 
Deauthorized by resolution Dec. 17, 1970, which also authorized new project "Posten Bayou, AR," under provision of 
Sec. 201 of Flood Control Act of 1965. 
12-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-G RED RIVER BELOW DENISON DAM 
(VICKSBURG DISTRICT): INCORPORATED 
PROJECTS (See Sec. 14 of Text) 
For Last 
Flood Estimated Full Report 
Control Federal See Annual 
Project Type of Work Act Cost Report For: 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA Levee and appurtenances 1941 $ 1,653,2371 1956 
Bayou Bodcau Reservoir, LA2 Flood-control reservoir 1938 5,120,7401 4 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA Channel improvement 1941 319,200' 1948 
Bayou Pierre, LA Channel enlargement 1936 255,5291 4 
Black Bayou Lake, LA5'6 Flood-control reservoir 1936 714,000 1945 
Colfax, Grant Parish, LA Cutoff 1938 70,3481' 1938 
Grant Parish, below Colfax, LA Levees 1938 38,8091 1941 
Hempstead County levee district 
No.1, AR Levee enlargement 1938 88,006' 1941 
Natchitoches Parish, LA Levee and appurtenances 1936 1,529,92718 1956 
Pineville, Red River, LA Levee and appurtenances 1941 232,4261 1953 
Red River in vicinity of 
Shreveport, LA Bank protection 1944 3,908,0001 1953 
Red River Parish, LA Levee enlargement 1936 149,4351 1939 
Saline Point, LA Cutoff 1936 124,1111 1945 
Wallace Lake, LA Flood-control reservoir 1936 1,219,3711'3 4 
Total $15,467,134 
1. Actual cost. 
2. Project transferred to Vicksburg District, August 1982. 
3. Includes amounts indicated for recreational facilities under Code 711, Bayou Bodcau Reservoir, LA, 
$1,027,000; Wallace Lake, LA, $17,164. 
4. Included in this report. 
5. Work not started. 
6. Inactive. 
7. Completed under provisions of Sec. 7 of Flood Control Act of 1928, as amended by Sec. 9 of Flood Control 
Act of 1936, and included in 1939 Annual Report of President, Mississippi River Commission, p. 2214. 
8. In addition, $25,000 was expended from contributed funds. 
12-20

VICKSBURG, MS, DISTRICT 
TABLE 12-H OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Aloha-Rigolette Area, Grant and 
Rapides Parishes, LA1 1956 $ 1,896,826 $ -- Apr. 1955 
Bayou Bodcau, Red Chute, and 
Loggy Bayou, LA' 1948 319,200 -- Jan. 1948 
Bayou Bodcau Reservoir, LA 1985 -- 4,234,577 Apr. 1961 
Bayou Pierre, LA 1985 -- 278,255 FY 1939 
Bayou Pierre in vicinity of 
Shreveport, LA1 "2 1951 243,3362 - Jun. 1939 
Big Black River, MS3 1956 910,185 670,750 3 
Big Choctaw Bayou, LA3'4 1966 248,823 -- 
Black Bayou Reservoir, LA1 " 5'6 1945 -- -- -- 
Blakely Mt. Dam - Lake 
Ouachita, Ouachita River, AR 1985 34,023,108 65,793,736 Oct. 1955 
Caddo Lake Dam, LA 1986 -- 1,185,922 -- 
Campti-Clarence Area in 
Natchitoches Parish, LA 1978 1,655,700 -- Jul. 1978 
Colfax, Grant Parish, LA"' 1938 70,348 -- -- 
DeGray Lake 
Caddo River, AR 1985 72,033,992 43,813,077 Dec. 1971 
East Point, LA 1969 286,069 3,051,536 Aug. 1968 
Garland City, AR 1976 1,335,841 -- Jul. 1974 
Grant Parish below Colfax, LA"3 1941 38,809 -- 3 
Hempstead County Levee District 
No. 1, AR"3 1941 88,006 -- 
Homochitto River, MS3 1956 205,000 144,6503 
Maniece Bayou, AR1 "2 1970 970,9322 -- Aug. 1969 
Monroe Floodwall, LA 1984 2,560,000 -- -- 
Murfreesboro Dam and Lake4 1951 -- -- -- 
Narrows Dam-Lake Greeson, 
Little Missouri River, AR 1985 16,516,689 46,547,745 May 1950 
Natchez Port Area, MS 3'4 1969 538,000 -- 5 
Natchitoches Parish, LA"2 1956 1,529,478 -- Aug. 1955 
Pearl River, Jackson-East 
Jackson, MS 1986 290,000 -- -- 
Pineville, Red River, LA3'4 1953 232,426 -- Dec. 1951 
Lead Bayou, MS 1991 1,961,089 -- Nov. 1988 
12-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-H 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Posten Bayou, AR8 1973 -- -- -- 
Poverty Point, LA 1986 250,000 -- Oct. 1985 
Red River Parish, LA13 1939 149,435 -- 3 
Red River in vicinity of 
Shreveport, LA' 1953 3,908,000 -- Mar. 1953 
Saline Point, LA1,3 1945 124,111 -- -- 
Twelvemile Bayou, LA4 1966 335,433 -- May 1965 
Wallace Lake, LA 1985 -- 1,228,755 Dec. 1946 
1. Authorized under project "Red River Below Denison Dam." 
2. In addition, the following was expended from contributed funds: 
Amite River and tributaries ................................................................ $ 430 
Bayou Pierre in vicinity of Shreveport, LA ....................................................... 89,047 
Choctaw Bayou and Tributaries, LA ............................................................ 170,799 
Harvey Canal, Bayou Barataria Levee, LA ....................................................... 425,209 
M aniece Bayou, AR ....................................................................... 39,293 
Natchitoches Parish, LA ................................................................... 250,000 
3. Completion Date Unavailable. 
4. Authorized by Chief of Engineers under authority of Sec. 205, Flood Control Act of 1948, as amended. 
5. Construction not initiated. 
6. Inactive. 
7. Completed under provisions of Sec. 7 Flood Control Act of 1928, as amended by Sec. 9, Flood Control 
Act 1936, and included in 1939 Annual Report of President, Mississippi River Commission, p. 2214. 
8. Posten Bayou Project, authorized by Senate and House Resolutions, Dec. 17 and 15, 1970, deleted the plan authorized by 
the Flood Control Act dated Aug. 3, 1955. 
12-22

VICKSBURG, MS, DISTRICT 
TABLE 12-I DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contrib 
See Annual And Funds Funds 
Project Report For Authority Extended Exp 
Bayou Bartholomew and Tributaries, AR and LA 1990 May 17, 1950 974,000 -- 
S. Doc. 117, 
81st Cong., 
1st sess. 
Buffalo River, MS1 1940 Nov 1986 -- -- 
McKinney Bayou, Finn 19632 Aug 1977 -- -- 
Bayou Segment, AR 
1. Deauthorized by Sec. 1002, Water Resources Development Act of 1986. 
2. Date Authorized. 
12-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 12-J ACTIVE GENERAL INVESTIGATIONS 
(96X3121) 
Federal Cost Totals by 
Item and CWIS Number FY 92 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention (120) 
Bossier Parish, LA -12956 
Hot Springs, Garland Co., AR -12737 
Jackson Metro Area, MS -12742 
Subtotal 
Miscellaneous Activities (170) 
Interagency Water Resources (173) -14713 
Special Investigations (171) -17250 
North American Waterfowl Management Plan (175) -53904 
Subtotal 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 
Hydrologic Studies (260) 
Hydrologic Studies (260) -53820 
Subtotal 
TOTAL (Category 200) 
CONTINUATION OF PLANNING & ENGINEERING (Category 400) 
Flood Control Projects (450) 
Aloha Rigolette (451) -12123 
Subtotal 
TOTAL (Category 400) 
ADVANCE E&D (Category 600) 
Locks and Dams (622) 
RRWW Shreveport to Daingerfield (622) -75024 
Flood Control Projects (650) 
Aloha Rigolette, LA -12123 
Subtotal 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
$ 322,914 
40,331 
445,514 
808,759 
17,768 
24,036 
3,979 
45,783 
185,564 
130,999 
316,563 
1,010 
1,010 
2,635,318 
150,000 
150,000 
2,785,318 
$ 3,957,433 
12-24

MEMPHIS, TN, DISTRICT* 
This district comprises a portion of southeastern 
Missouri and southern Illinois, western portions of 
Kentucky and Tennessee, a small portion of northern 
Mississippi, and the northeastern portion of Arkansas; 
includes area embraced in drainage basins of 
eastern tributaries of the Mississippi River south of 
Ohio River Basin to Nonconnah and Horn Lake 
Creeks, inclusive, and those of western tributaries 
south of Little River diversion channel and Commerce, 
MO, including St. Francis River Basin and 
White River and tributaries below Peach Orchard 
Bluff, AR, on the right bank and below Augusta, AR, 
on the left bank; also includes left bank Mississippi 
River levee from vicinity of Memphis south to about 
mile 620, and right bank levees from Cape Girardeau, 
MO, to about mile 605. 
IMPROVEMENTS 
Navigation P 
1. Navigation work under special 
authorization ...................... 
'age Tables 
13-1 
Flood Control 
2. Fletcher Creek at Memphis, TN ...... 13-1 
3. Millington, TN .................... 13-2 
4. Nonconnah, Creek at Perkins, 
Memphis, TN ..................... 13-2 
5. Quince Road Bridge Memphis, TN .... 13-2 
6. Inspection of completed flood control 
projects ......................... 13-2 
7. Flood control work under special 
authorization ...................... 13-2 
Navigation 
1. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
During this period $14,982 was expended on reconnaissance 
studies on Cairo Harbor, IL and 
$1,612 on feasibility studies on DeValls Bluff Harbor, 
AR. 
Table 13-A 
Table 13-B 
Table 13-C 
Table 13-D 
Table 13-E 
Table 13-F 
Page 
Cost & Financial 
Statement .............. 
Authorizing Legislation .... 
Other Authorized Navigation 
Projects ............. 
Other Authorized Flood 
Control Projects .......... 
Deauthorized Projects ..... 
Active General 
Investigations ............ 
13-4 
13-4 
13-5 
13-6 
13-7 
13-8 
Flood Control 
2. FLETCHER CREEK AT 
MEMPHIS, TENNESSEE 
Location. Fletcher Creek is a major tributary of 
the Wolf River located in the northeast portion of 
Memphis, Tennessee. 
Existing project. The project was approved for 
construction Mar. 22, 1991, under the authority of 
Section 14 of the 1946 Flood Control Act, as amended. 
13-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Streambank erosion was threatening public utilities 
along Fletcher Creek. The project consists of stabilizing 
the channel slopes and bed via stone armoring for 
a distance of 725 feet along the channel approximately 
3,000 feet downstream from its intersection with Germantown 
Road. 
Local cooperation. A Local Cooperation Agreement 
was executed with the Memphis Light, Gas and 
Water Division on Apr. 26, 1991. The sponsor was 
required to provide lands, easements, rights-of-way, 
and relocations required for project construction and 
a cash contribution sufficient to bring the non-Federal 
share to 25 percent of the total project cost. 
Condition as of Sep. 30. Construction was initiated 
Aug. 12, 1991, and completed Sep. 6, 1991. 
3. MILLINGTON, TN 
Location. Millington is located in north Shelby 
County, TN. 
Existing project. The project was approved for 
construction on May 14, 1990, under the authority of 
Section 205 of the 1948 Flood Control Act, as 
amended. The project consists of 5,600 feet of levee 
along the right (north) bank of Big Creek in the reach 
between U. S. Highway 51 and the I.C. Railroad. The 
levee is designed to provide a 100-year frequency level 
of protection to the leveed area from backwater 
flooding. The estimated construction cost for the project 
is $809,000. A contract for project construction was 
awarded in August 1990. 
Local cooperation. A Local Cooperation Agreement 
was executed with the city of Millington on May 
15, 1990. The sponsor is required to provide the lands, 
easements, rights-of-way and relocations required for 
project construction and a cash contribution sufficient 
to bring the non-Federal share to 25 percent of total 
project cost. 
Condition as of Sep. 30. Project flood protection 
was provided in February 1991. Remaining project 
related drainage modifications are scheduled to be 
completed early in calendar year 1993. 
4. NONCONNAH CREEK AT 
PERKINS STREET, 
MEMPHIS, TN 
Location. The project is located in southeast 
Memphis. 
Existing project. The project was approved for 
construction Oct. 28, 1988, under the authority of 
Section 14 of the 1946 Flood Control Act, as amended. 
The project consists of the placement of stone, gabions, 
and concrete to armor the streambank and channel 
bed against erosion which had placed the Perkins 
Street bridge in imminent danger. 
Local cooperation. A Local Cooperation Agreement 
was executed with the City of Memphis on Jan. 
10, 1989. The sponsor was required to provide the 
lands, easements, rights-of-way, and relocations required 
for project construction and a cash contribution 
sufficient to bring the non-Federal share to 25 percent 
of the total project cost. 
Condition as of Sep. 30. Construction was initiated 
Jan. 27, 1989, and completed May 26, 1989. 
Because of shifting in the protection, additional stone 
was added on Feb. 4-6, 1992. 
5. QUINCE ROAD BRIDGE 
MEMPHIS, TENNESSEE 
Location. Quince Road Bridge is located in east 
Memphis on an unnamed tributary of Nonconnah 
Creek about 250 feet from the confluence with the 
Creek. 
Existing project. The project was approved for 
construction Mar. 5, 1991, under the authority of 
Section 14 of the 1946 Flood Control Act, as amended. 
Stream bank and bed erosion was threatening Quince 
Road Bridge. The project consists of stabilizing the 
stream banks and bed beneath the bridge and along a 
reach from 30 feet upstream to 60 feet downstream of 
the bridge, a total distance of 140 feet, by means of a 
combination of stone-filled gabions, revetment mattresses, 
and riprap. 
Local cooperation. A Local Cooperation Agreement 
was executed with the city of Memphis on Aug. 
8, 1991. The sponsor provided lands, easements, 
rights-of-way, and relocations required for project construction 
and a cash contribution sufficient to bring 
the non-Federal share to 25 percent of the total project 
cost. 
Condition as of Sep. 30. Construction was initiated 
on Dec. 13, 1990, and completed Jul. 31, 1991. 
6. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspected completed projects at a cost of $134,952 in 
the period. Total cost as of Sep. 30, 1992, was $1,866,694. 
This included in-depth inspection of projects. 
7. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
13-2

MEMPHIS, TN, DISTRICT 
During this period $184 was expended on Crow 
Creek, Forrest City, AR; $7,457 on Raft Creek, AR; 
$5,111 on Obion, TN; $4,888, North Fork, Obion River, 
Rivers, TN; $662,815 on Mayfield Creek Tributaries; 
and $49,996 on Bono, AR. 
Emergency bank stabilization activities pursuant 
to Sec. 14, Public Law 526, 79th Cong., as 
amended. 
During FY 1992, $29 was expended on Harrington 
Creek; $20,126 on Wolf River at U.S. Highway 51, 
Memphis, TN; $16,274 on Ward Road over Big Creek, 
Shelby County, TN; $11,204 on Oakland, TN; $18,267 
on Bart Road Harrington Creek; $1,746 on Highway 
79 at Obion; and $14,846 at Royster Creek. 
Emergency flood control activities, Public 
Law 99, 84th Cong. 
Federal cost was $210,789 for disaster preparedness 
in FY 92. Also, $100,684 was spent for private 
levee rehabilitation; and $12,401 for Emergency 
Operations. 
Flood control activities pursuant to Sec. 208, 
Public Law 780, 83rd Cong., as amended. 
No work was accomplished this period under this 
authority. 
Project Modifications for improvement of environment 
pursuant to Sec. 1135, Public Law 
99-662, as amended (preauthorization). 
During this period $49,944 was expended on Tunica 
Cutoff Weir, Tunica County, MS, and Lee County, AR. 
13-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 13-A COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
2. Fletcher Creek New Work 
Memphis, TN Approp. $ 6,000 $ 54,000 $310,000 39,200 $423,200 
Cost 14,982 21,266 340,372 41,318 421,892 
3. Millington, TN New Work 
Approp. 105,000 607,000 22,500 0 809,500 
Cost 116,203 108,020 513,840 1,074 802,876 
4. Nonconnah Creek New Work 
at Perkins, Approp. 292,000 0 0 0 357,000 
Memphis, TN Cost 259,385 3,784 3,042 51,449 342,245 
5. Quince Road New Work 
Bridge Approp. 5,000 10,000 121,000 0 160,000 
Memphis, TN Cost 10,898 13,507 106,693 14,902 160,000 
TABLE 13-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 24, 1946 Fletcher Creek, Memphis, TN (See Sec. 2 
as amended of Text) Streambank protection Approved Apr. 4, 19912 
Jun. 30, 1948 Millington, TN (See Sec. 3 of Text), Levee in City 
as amended of Millington. Approved May 14, 19901 
Jul. 24, 1946 Nonconnah Creek at Perkins Street, Memphis, TN 
as amended (See Sec. 4 of Text), Streambank protection Approved Oct. 28, 19882 
Jul. 24, 1946 North Second Street at Wolf River, Memphis, TN 
as amended Streambank protection. Approved Oct. 18, 19882 
Jul. 24, 1946 Plainview Road Bridge, Chester Co., TN 
as amended Streambank protection. Approved Jul. 26, 19902 
Jul. 24, 1946 Quince Road Bridge Memphis, TN (See Sec. 5 of Text), 
as amended Streambank protection Approved May 16, 19912 
13-4 
1. Authorized under authority of Sec. 205 of the 1948 Flood Control Act, as amended. 
2. Authorized under authority of Sec. 14 of the 1946 Flood Control Act, as amended.

MEMPHIS, TN, DISTRICT 
TABLE 13-C OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Caruthersville Harbor, MO 1984 $768,992 $3,201,208 Dec. 1980 
Forked Deer River, TN, including South Fork"2 1912 25,000 425,857 -- 
Helena Harbor, AR 1984 90,847 6,135,084 Sep. 1963 
Elvis Stahr Harbor, KY 1984 149,827 5,755,866 Jan. 1963 
New Madrid Harbor, MO6 1984 196,373 395,493 Oct. 1970 
Obion River, TN1'3 1911 28,716 -- -- 
Osceola Harbor, AR 1984 269,115 7,090,029 Nov. 1974 
Removing snags and wrecks from Mississippi River 
below mouth of Missouri River and from Old and 
Atchafalaya Rivers4'* 1948 -- 318,833 4 
St. Francis and L'Anguille Rivers and Blackfish 
Bayou, AR 1'2 1942 92,000 300,449 -- 
White River, AR (below Newport) 1984 169,994 27,859,983 -- 
Wolf River (Memphis Harbor), TN 1984 586,500 11,721,299 1959 
1. No commerce. 
2. Existing project is for maintenance only. 
3. Recommended for abandonment in H. Doc. 467, 69th Cong., 1st sess. 
4. Completion date not available. 
5. No funds available under this project. Work being carried on under "Appropriation, Flood Control, Mississippi River and 
Tributaries." 
6. WRDA 92 (Section 102) modified authorization by directing the Secretary to assume responsibility for maintenance of 
New Madrid County Harbor constructed by non-Federal interest. 
13-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 13-D OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Big Creek Canal, Millington, TN 1977 $ 70,363 $ -- -- 
Bradford, TN 1984 95,061 -- Dec. 1983 
Cottonwood Slough pumping plant, IL1 1964 147,000 -- Feb. 1964 
Drinkwater Sewer, MO 1984 1,494,828 -- Jun. 1980 
Dyersburg, TN 1 1962 229,6492 -- Jun. 1962 
Dyersburg, TN (SW) 1981 1,820,869 -- Oct. 1976 
Grays Creek Canal Shelby Co., TN 1985 155,280 -- Aug. 1985 
Hatchie River, Alcorn Co., MS 1987 85,200 -- Feb. 1986 
Humboldt, TN 1989 1,141,407 -- Apr. 1988 
Memphis, Wolf River, and Nonconnah Creek, TN 1960 11,141,199 -- May 1959 
Mounds and Mound City, Ohio River Basin, IL3 1955 1,132,704 -- Oct. 19594 
Nixon Creek, TN1 1952 62,821 -- Dec. 1951 
Nonconnah Blvd. Nonconnah Creek, TN 1983 249,999 -- Nov. 1981 
Nonconnah Creek, Interceptor Sewer, Memphis, TN 1987 259,000 -- Dec. 1986 
N. Second St., Memphis, TN (Wolf River Bridge) 1983 249,999 -- Sep. 1980 
N. Second St. at Wolf River, Memphis, TN 1991 367,012 -- Jan. 1990 
Plainview Road Bridge, Chester County, TN 1991 124,954 -- Sep. 1990 
Sandy Creek Jackson, TN 1985 238,000 -- Dec. 1984 
St. Francis River Highway No. 90, AR 1985 161,000 -- Sep. 1985 
Treasure Island, MO 1981 861,528 -- Mar. 1978 
Turner Creek, Corinth, MS 1987 100,600 -- Mar. 1987 
US Hwy 51, Nonconnah Creek, TN 1984 369,200 -- Mar. 1983 
W. Hickman, Area, Hickman, KY 1983 1,674,180 -- Oct. 1976 
1. Authorized by Chief of Engineers under small project authority, Sec. 205, Flood Control Act of 1948, as amended. 
2. Includes $21,863 contributed funds. 
3. Work being completed under Mississippi River and Tributaries project. 
4. Exclusive of Cache River Pumping Station. 
13-6

MEMPHIS, TN, DISTRICT 
TABLE 13-E DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For: Deauthorized Expended Expended 
Big Creek and L'Anguille River, White River 
Basin, AR 1977 May 6, 81 -- -- 
Clarendon to Laconia Circle White River 
Basin, AR 1937 May 6, 81 -- -- 
Huntingdon, TN 1983 Sep 80 2,900,281 -- 
Long Lake Area, Helena, AR 1983 Jul 83 61,281 -- 
13-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 13-F ACTIVE GENERAL INVESTIGATIONS 
(96X3121) 
Federal Cost Totals by 
Item and CWIS Number FY 92 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Hickman Bluff, KY 77067 $178,699 
$178,699 
Miscellaneous Activities (170) 
Special Investigations (171) -17250 $23,279 
Dam Safety Criteria Studies (173) 11,841 
North American Waterfowl Mgmt (176) - 539043,627 
38,747 
Coordination Studies with Other Agencies (180) 
Dept. of Agriculture (181) - 77067 $1,535 
Planning Assistance to States (186) 47 
$1,582 
TOTAL (Category (100) $219,028 
COLLECTIONS AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Services 176,562 
TOTAL (Category 200) $176,562 
GRAND TOTAL GENERAL INVESTIGATIONS $395,590 
13-8

ST. LOUIS, MO, DISTRICT* 
This district comprises those portions of southwestern 
Illinois and eastern Missouri embraced in drainage 
basin of Mississippi River and its western tributaries, 
exclusive of the Missouri River, from the mouth 
of the Ohio River to mile 300, and of its eastern 
tributaries to Hamburg Bay at mile 261 on left bank, 
exclusive of tributary basin of Illinois Waterway upstream 
of new La Grange Lock and Dam at mile 80.15 
above confluence of the Illinois and Mississippi Rivers. 
The St. Louis District territory encompasses 
27,000 square miles. District also includes drainage 
basin in Missouri tributary to the Little River diversion 
channel. Report on the Mississippi River between 
the Missouri River and mile 300 is included in separate 
report on the Mississippi River between the Missouri 
River and Minneapolis, MN. Report on the portion 
of the Illinois River downstream of new La 
Grange Lock and Dam is included in report of the 
Chicago District on the Illinois Waterway, Illinois and 
Indiana. 
IMPROVEMENTS 
Page Flood Control (cont) 
1. Illinois Waterway, IL 
(St. Louis Dist.) ................... 14-2 
2. Mississippi River between 
Missouri and Minneapolis, MN 
(St. Louis Dist.) (Includes Melvin 
Price Locks & Dam) ............... 14-2 
3. Mississippi River between Ohio 
and Missouri Rivers, 
MO and IL ..................... . 14-2 
4. Southeast Missouri Port, MO ....... .14-2 
5. St. Louis Harbor, MO and IL ........ 14-3 
6. Navigation work under 
special authorization .............. 14-3 
Flood Control 
7. Alton to Gale Organized 
Levee Districts, IL & MO ........... 14-3 
8. Cape Girardeau-Jackson,MO ........ 14-4 
9. Coldwater Creek, MO .............. 14-4 
10. East St. Louis and vicinity, IL ....... 14-4 
11. Kaskaskia Island Drainage and 
Levee District, IL ................ 14-5 
12. Maline Creek, MO ................ 14-5 
13. Meramec River Basin 
Valley Park, MO .................. 14-5 
14. Pine Ford Lake, MO ............... 14-6 
15. River des Peres, MO .............. 
16. Inspection of completed flood 
control projects .................. 
17. Flood control work under 
special authorization ............. 
Multiple-Purpose Project 
Including Power 
18. Clarence Cannon Dam and Mark 
Twain Salt River, MO ............. 
19. Upper Mississippi River 
Environmental Management 
Program ........................ 
Tables 
Table 14-A 
Table 14-B 
Table 14-C 
Table 14-D 
Table 14-E 
Table 14-F 
Page 
14-6 
14-6 
14-7 
14-7 
14-7 
Cost and Financial 
Statement ............... .14-9 
Authorizing Legislation ... 14-11 
Other Authorized 
Navigation Projects ...... 14-15 
Other Authorized Flood 
Control Projects ......... 14-16 
Deauthorized Projects .... 14-18 
Active General 
Investigations (96X3121) .. 14-19 
14-1 
Navigation ]

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. ILLINOIS WATERWAY, IL 
(ST. LOUIS DIST.) 
See report on Illinois Waterway, IL and IN, under 
Rock Island District. 
2. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN (ST. LOUIS 
DIST.) (INCLUDES MELVIN 
PRICE LOCKS & DAM) 
See separate section entitled "Mississippi River 
between Missouri River and Minneapolis, MN," 
printed in the Annual Report of the Chief of 
Engineers. 
3. MISSISSIPPI RIVER BETWEEN 
OHIO AND MISSOURI RIVERS, 
MO AND IL 
Location. Mississippi River rises in Lake Itasca, 
MN, and from that lake flows southerly about 2,340 
miles and empties into the Gulf of Mexico. Portion 
included in this report embraces the 195-mile section 
known as middle Mississippi, between tributary Ohio 
and Missouri Rivers about 974 to 1,169 miles from the 
gulf. See folder by Corps of Engineers of Navigation 
Charts, Middle and Upper Mississippi River, Cairo, 
IL, to Minneapolis, MN. 
Previous projects. For details see page 1879 of 
Annual Report for 1915, and page 1014 of Annual 
Report for 1938. 
Existingproject. The existing project provides for 
obtaining and maintaining a minimum channel depth 
of not less than 9 feet, a minimum width of not less 
than 300 feet at low water, with additional widths in 
bends from mouth of Ohio River (about 974 miles from 
gulf) to northern boundary of city of St. Louis, mile 
191, thence 200 feet wide, with additional width in 
bends to mouth of Missouri River, mile 195; to be 
obtained: (1) by regulating works, for closing secondary 
channels, contracting river by building new banks 
where river width is excessive and protecting new and 
old banks from erosion where necessary to secure 
permanency at an estimated total Federal cost (Oct 
1992 price level) of $211,000,000; (2) by dredging to 
maintain project channels; (3) by construction of 
works authorized for Chain of Rocks reach in 1945 
River and Harbor Act, which approved a comprehensive 
plan for development of the river at Chain of Rocks 
to provide for construction of a lateral canal at a cost 
of $59,720,600; and (4) by construction of a fixed-crest 
rock-fill dam about 900 feet below Chain of Rocks 
Bridge, authorized by 1958 River and Harbor Act, at 
cost of $4,353,000, excluding $7,000 costs to Coast 
Guard for aids to navigation. Estimated total Federal 
project cost (1992) is $275,073,600. A small boat harbor 
opposite Chester, IL, was deauthorized and excluded 
from foregoing cost estimate. See H. Doc. 669 
(76th Cong., 3rd sess.) for report of Chief of Engineers 
dated Feb. 27, 1940, containing a general plan for 
improvement of Mississippi River between Coon Rapids 
Dam and mouth of Ohio River for purposes of 
navigation, power development, flood control, and 
needs of irrigation. 
Local cooperation. None required. 
Terminal facilities. Existing facilities are considered 
adequate for existing commerce. 
Operations and results during fiscal year. 
Regulating Works: contracts continue on stone dike 
and revetment construction as is engineering and 
design and supervision and administration. Construction 
on existing project began in 1881 and project 
has been in beneficial use practically from its 
inception. Projects on Dam 27 and Chain of Rocks 
are complete. Work on the project is about 82 percent 
complete. Channel as a whole has been greatly 
improved by the work completed to date. Dredging 
is required at low stages to remove temporary shoals 
and maintain required channel depths. River is generally 
above 10-foot stage, St. Louis gage, from latter 
part of February to the latter part of August, 
during which time project channel depths generally 
prevail without dredging. During FY 1988 through 
FY 1990 low water conditions (drought) increased 
maintenance dredging. To improve navigation 
depths a rock removal contract began Oct. 1988 and 
was completed in July 1991. 
Maintenance. Work consists of approximately 
2,000 feet of dike repair and 5,000 feet of revetment 
repair yearly. U.S. plant and hired labor plus contract 
dredging perform channel dredging removing 
5,000,000 to 10,000,000 cubic yards of material from 
main channel. Condition and operation studies, recreation 
planning, engineering and design, and operation 
and maintenance of Lock and Dam 27 continued. 
4. SOUTHEAST MISSOURI PORT, 
MISSOURI 
Location. The project is located on the right bank 
of the Mississippi River between river mile 47.5 to 48.8 
above the Ohio River in the counties of Scott and Cape 
Girardeau in Southeast Missouri. 
Existing project. Pursuant to Sec. 107, Public 
Law 86-645, as amended, a slackwater channel, 2,000 
feet long, 230 feet wide, and 9 feet deep is being 
constructed. This project will provide a navigation 
channel for development of a port and related facilities 
14-2

ST. LOUIS, MO, DISTRICT 
at this location. Total estimated cost is $5,405,600 
($2,139,000 non-Federal). 
Location cooperation. On May 22, 1987, a 
Local Cooperation Agreement was signed between 
the Port District and the St. Louis District, Corps of 
Engineers. 
Results during fiscal year. Construction of the 
harbor project is complete. The local sponsor has completed 
construction of and is currently operating docking 
facilities. Maintenance dredging of the harbor is 
being performed by the St. Louis District in accordance 
with the terms of the Local Cooperation 
Agreement. 
5. ST. LOUIS HARBOR, MO 
AND IL 
Location. The project area includes both sides of 
the Mississippi River from miles 138.8 to 208.8 above 
the Ohio River (generally, the limits of the Port of 
Metropolitan St. Louis). 
Existing project. The project was authorized by 
the Water Resources Development Act of 1986. The 
authorized project includes improvements in two 
areas: the North Riverfront area in Missouri (which 
is served by the St. Louis Municipal Docks) and the 
Tri-City Port area along the east bank of the Chain 
of Rocks Canal in Illinois. The principal project at 
the St. Louis Municipal Docks is an L-dike sediment 
control structure in the river to provide reliable 
water access to the dock when the river is low. The 
principal project at the Tri-City Port area is a 210 
ft. wide harbor along 6,900 ft. of the Chain of Rocks 
Canal. The North Riverfront project and half the 
Tri-City harbor (3.450 ft.) would be constructed in 
Phase 1, and the second half of the Tri-City harbor 
in Phase 2 approximately 10 years later. Estimated 
cost of the project (1992) is $12,900,000 Federal and 
$25,474,000 Non-Federal. A March 1986 Reevaluation 
Report described model tests which showed 
that the L-dike sediment control structure recommended 
for the St. Louis Municipal Docks would not 
be effective but that appropriate configuration of a 
new outer wall for the docks, referred to as the 
Prototype River Access Improvement Structure 
(PRAIS), would divert currents so as to control scour 
and sedimentation and maintain sufficient water 
depths for the needs of the harbor. 
Local cooperation. The District coordinated with 
the two local sponsors and found that (1) the city of St. 
Louis Port Authority supports the PRAIS project and 
(2) the Tri-City Regional Port Authority wants the 
Corps to consider the possibility of reducing the length 
of their Phase I harbor to 1,800 ft. and shifting its 
location so that it is a northern extension of the existing 
Tri-City harbor (the authorized project length of 
6,900 ft. would be maintained by increasing the length 
of the Phase 2 harbor to 5,100 ft.). 
Operations and results during the fiscal year. 
In January 1992 District completed a letter report 
that documented a preliminary analysis of the costs 
and benefits of the PRAIS and the Tri-City harbor 
projects. Headquarters reviewed the letter report and 
directed that new economic studies and other work be 
accomplished and documented in a General Reevaluation 
Report with an Engineering Project Management 
Plan which will describe how the reevaluation 
studies will be accomplished. The District also prepared 
the storage site for sheet pile from the third 
stage cofferdam at Melvin Price Locks and Dam, 
which may be used in the PRAIS as described in a 
January 1987 value engineering study and the January 
1987 value engineering study and in the January 
1992 letter report. 
6. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
Initial appraisal study cost for Jackson-Union 
Counties Port, IL, was $5,732. The report was 
negative. 
Flood Control 
7. ALTON TO GALE ORGANIZED 
LEVEE DISTRICTS, IL & MO 
Location. The levee system is located adjacent to 
the Mississippi River between Alton and Gale, 
Illinois. 
Existing Project. The project is authorized by the 
Flood Control Acts of 1936, 1938 and 1946. Construction 
of the Alton to Gale levee system was 
completed in 1977. Some reaches of this levee system 
have, for many years, been experiencing a significant 
number of slides associated with design 
deficiencies increasing the probability of levee failure 
during flood events. The recommended plan will 
correct these slides by a lime stabilization procedure. 
Estimated cost (1992) is $18,030,000 Federal 
and $3,848,000 non-Federal. 
Local cooperation. The cost sharing applicable 
for the Alton to Gale Levee Slide repairs is in accordance 
with policies established for the Water Resources 
Development Act of 1986, PL 99-662, the Local 
sponsor is required to operate and maintain all works 
after completion. Supplemental assurances have been 
executed for the portion of the remedial work that is 
100% federally funded. 
14-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Operations and results during fiscal year. Repair 
of levee slides on the Federally funded reaches 
was completed. 
8. Cape Girardeau-Jackson, MO 
Location. The project is located in Cape Girardeau 
County, Missouri, along the right bank of the Mississippi 
River between River Miles 50 and 55 above the 
Ohio River. 
Existing Project. The project includes a 157 acre 
dry detention reservoir; approximately one mile of 
channel improvements on Cape La Croix Creek and 
two miles of channel improvements on Walker 
Branch, eight bridge replacements; recreational/environmental 
features and non structural features which 
are not going to be implemented at this time. The 
project is authorized by the Water Resources Development 
Act of 1986 (PL 99-662). The estimated Federal 
project cost (1992) is $29,300,000. Non-Federal cost is 
$11,800,000. 
Local Cooperation. The city of Cape Girardeau, 
MO, local sponsor, is strongly supportive of the project. 
The Local Cooperation Agreement (LCA) was 
executed on May 25, 1990 with a modification to the 
LCA executed on Oct. 27, 1992. Requirements of local 
cooperation are fully described in the FY 1991 Annual 
Report. 
Operations and results during fiscal year. 
Contract was awarded in Sep. 1991 for Cape La Croix 
segment of the project, design continued on the remainder. 
A problem with gasoline contaminated soil 
at one location has delayed the Walker Branch #1 
Channel construction contract. 
9. COLDWATER CREEK, MO 
Location. The 47 square mile Coldwater Creek 
watershed is located in St. Louis County, Missouri, 
and had a 1980 population of 158,000 residents. The 
stream flows through Overland, Breckenridge Hills, 
and St. Ann; under Lambert-St. Louis International 
Airport; and through Hazelwood, Florissant, and 
other communities and empties into the Missouri 
River. 
Existing Project. The project was authorized by 
the Water Resources Development Act of 1990 and 
would afford protection to the area. About 1,400 structures 
or units would be flooded by a 100-year flood. 
Significant flood damages occurred in the area in 
1957, 1978, 1979, 1982, and 1986. The problems addressed 
by the Feasibility Study included flood damages, 
outdoor recreation needs, and environmental 
degradation. The authorized project includes ten 
miles of channel widening, five tunnels through a 
downstream railroad embankment, two small levees, 
a flood forecasting and warning system, and recreation 
features along the channel widening project. 
Estimated cost of the project (1992) is $18,300,000 
Federal and $7,868,000 Non-Federal. 
Local cooperation. A letter of intent was received 
from the Metropolitan Sewer District on Jun. 
25, 1987, expressing willingness to be local sponsor 
of the project. The most recent Schedule and Cost 
Change Request was signed by the sponsor on Oct. 
20, 1992. 
Operation and results during fiscal year. The 
Feasibility Report was completed in 1987, the Chief of 
Engineers Report was issued in 1988. Because of 
radioactive material in channel sediments downstream 
from a Superfund site at Lambert Airport, the 
Corps of Engineers and the Metropolitan Sewer District 
(MSD), divided the Coldwater Creek project into 
two parts and will implement it in two phases. The 
first phase is channel widening upstream of Lambert 
Airport in St. Ann and Breckenridge Hills. The St. 
Louis Airport Authority is studying major expansion 
plans which could effect the project design. 
10. EAST ST. LOUIS AND 
VICINITY, IL 
Location. Project is in St. Clair and Madison Counties, 
IL, on the left bank of the Mississippi River 
between river miles 175 and 195 above the Ohio River. 
Project includes all bottom lands between bluffs on the 
east and Mississippi River and Chain of Rocks Canal 
on the west, and extends from Cahokia diversion 
channel on the north to Prairie du Pont Creek on the 
south. (See Corps of Engineers Navigation Charts, 
Middle and Upper Mississippi River, Cairo, IL, to 
Minneapolis, MN.) 
Existing project. The 1936 Flood Control Act authorized 
raising and enlarging existing levee systems 
by construction or reconstruction of 19.8 miles of levee, 
including 3.1 miles of floodwall, together with necessary 
appurtenant works consisting of gravity drainage 
structures, highway and railroad closure structures, 
alterations and reconstruction of existing 
pumping plants, alterations to railroad bridges and 
approaches at levee crossings, service roads on levee 
crown, and seepage control measures. Work under 
this authorization provides the area protection 
against a flood of about 200-year frequency. The completed 
10 miles of levee along Chain of Rocks Canal 
and Lock 27 provide flood protection on the landward 
side integral with and to the same degree as the East 
St. Louis levee. Final cost of work under this authorization 
is $22,550,100. The Flood Control Act of 1965 
modified existing project to provide for channel improvements, 
diversion ditches, flood plain detention 
areas, a reservoir on Little Canteen Creek, and a 
14-4

ST. LOUIS, MO, DISTRICT 
pumping plant to considerably reduce damages resulting 
from interior flooding. This act also authorized 
reconstruction of a channel stabilization dam in 
Cahokia Creek diversion channel to provide protection 
to adjacent levees and bridges from scour and 
eventual loss. Post authorization studies have indicated 
that flood plain detention areas, the reservoir on 
Little Canteen Creek and other related flood control 
measures in the Cahokia-Harding Ditch Area are not 
economically feasible. Also, further studies of the 
channel stabilization dam in Cahokia Creek diversion 
channel have been deferred due to lack of support from 
the local sponsor of the project. Estimated total Federal 
project cost of work under this authorization is 
$33,600,000 (1985), $22,020,000 for Cahokia-Harding 
Ditch Area, and $11,580,000 for Blue Waters Ditch. 
Non-Federal cost is $20,770,000. The 1988 Energy 
and Water Development Appropriations Act authorized 
repair and rehabilitation of pump stations and 
appurtenant works, channels and bridge structures. 
The estimated total cost of this work (1992) is 
$25,400,000 Federal and $11,100,000 Non-Federal. 
Local cooperation. For work under the Energy 
and Water Development Appropriations Act of 1988, 
PL 100-202, local interests have entered into three 
Local Cooperation Agreements (LCA) which cover all 
of the work in the Flood Protection Rehabilitation 
project. Construction work under the first LCA is 
complete, and construction work under the remaining 
two LCA's is under way. 
Operations and results during fiscal year. 
Contracts for rehabilitation of gravity drains and 
some of the closure structures and pump stations have 
been awarded. Contracts for rehabilitation of relief 
wells and additional pump stations are scheduled for 
award in the near future. 
11. KASKASKIA ISLAND DRAINAGE 
AND LEVEE DISTRICT, IL 
Location. In Randolph County, IL, on the right bank 
of the Mississippi River between miles 111 and 116 above 
the mouth of the Ohio River. (See Paducah, KY, IL, MO, 
IN, map published byArmy Map Service, scale 1:250,000.) 
Previous project. For details, see page 1375 of 
Annual Report for 1950. 
Existing project. Project area contains about 
9,460 acres only partially protected against flood stage 
of 38.5 feet on the Chester, IL, gage. Flooding occurs 
about once in every 7.3 years with an average duration 
of 26 days, causing substantial damage. The 1962 
Flood Control Act (H. Doc. 519, 87th Cong., 2nd sess.) 
provides for enlarging and raising the existing levee 
about 8 feet to provide protection against a flood 
having a frequency of once in 50 years. Estimated total 
Federal project cost (1986) is $14,100,000. Non-Federal 
cost is $2,100,000. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-6 of Fiscal Year 
1980 Annual Report. Formal assurances from the 
Kaskaskia Island Drainage and Levee District were 
accepted on behalf of the United States on Jan. 23, 
1980. 
Operations and results during fiscal year. All 
construction of gravity drains, levee embankment and 
installation of wildlife plantings is complete. Project 
is complete. 
12. MALINE CREEK, MO 
Location. Maline Creek is located in a small northern 
part of the City of St. Louis, portions of incorporated 
St. Louis County and all or part of 22 municipalities. 
The 25 square mile Maline Creek watershed 
originates near Lambert Airport and flows in an 
easterly direction through Berkeley, Kinloch, Ferguson, 
Moline Acres, Bellefontaine Neighbors, and other 
communities and empties into the Mississippi River. 
The Maline Creek flood plain encompasses approximately 
1600 acres of mostly urban development. This 
highly urbanized area had a population of 126,000 
people in 1980. 
Existing project. The project was authorized by 
the Water Resources Development Act of 1986 (PL 
99-662) and would afford protection to the area. The 
present plan includes approximately 2.95 miles of 
channel widening, 3.35 miles of clearing, replacement 
or modification of 7 bridges, 14.4 acres of open space, 
a flood forecasting and warning plan and 2.64 miles of 
recreation trails. At October 1992 price levels, including 
an allowance for inflation, estimated cost of the 
project is $7,700,000 Federal and $2,727,000 Non- 
Federal. (Authorized but not funded for construction.) 
Local cooperation. The Metropolitan Sewer District 
of St. Louis is the present local sponsor of the 
project. 
Operation and results during fiscal year. 
Funding will be requested to advance Preconstruction 
Engineering and Design (PED) when the Metropolitan 
Sewer District, local sponsor, indicates financial 
capability to proceed. 
13. MERAMEC RIVER BASIN 
(VALLEY PARK), MISSOURI 
Location. The project is located in St. Louis 
County, Missouri, adjacent to the left bank of the 
14-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Meramec River between miles 20.7 and 22.1 above the 
confluence with the Mississippi River. 
Existing project. The project was authorized for 
construction by Section 2(h), Public Law 97-128, Dec. 
29, 1981, and Water Resources Development Act of 
1986 and would afford partial flood protection to the 
area. The project provides for construction of 3.1 miles 
of earthen levee with four gravity drains, three closure 
structures interior ponding areas, 36 relief wells 
would be required for under seepage control, recreational 
a features consisting of standard play equipment, 
multi-user courts, play field areas, picnic tables, 
comfort stations, parking, hiking/biking trails, and 
lands, easements and rights-of-way required for public 
access, health and safety. Estimated total project 
cost is $15,400,000; $11,420,000 Federal, and 
$3,980,000 non-Federal. The LCA for this project was 
executed on Aug. 12, 1992. 
Local cooperation. The Board of Alderman for the 
City of Valley Park, Missouri, authorized the mayor 
to issue a Letter of Intent to sponsor the project. The 
letter dated Feb. 18, 1987, acknowledged that city 
officials were aware of cost sharing requirements and 
of the items of local cooperation and favored construction 
of the project. A Local Cooperation Agreement 
was executed on August 12, 1992. 
Operations and results during fiscal year. A 
Plan Formulation Report and General Design Memorandum 
was issued in March 1987. A feature design 
memorandum is scheduled for submittal in January 
1993. 
14. PINE FORD LAKE, MO 
Location. Proposed dam is on Big River at mile 
43.8, about 45 miles southwest of St. Louis. The Big 
River is a tributary of the Meramec. Lake would 
extend about 34 miles up Big River. (See St. Louis, 
MO, sheet of maps of the United States, published by 
Army Map Service, scale 1:250,000.) 
Existingproject. Project provides for construction 
of a compacted earth-fill dam with a concrete chute 
spillway. Dam will be 141 feet high and 2,070 feet 
long. Construction of new roads, improvements of 
existing roads, alterations to pipeline, power and telephone 
lines, and construction of recreational facilities 
are included. Maximum storage capacity will be 
285,000 acre-feet. Estimated total project cost (1984) 
is $147,000,000, of which $8,173,200 and $22,900,000 
are local reimbursements for water supply and recreation 
and fish and wildlife respectively. 
Local cooperation. Local interests must contribute 
toward cost of project for storage allocation to 
water supply in accordance with the Water Supply Act 
of 1958. 
Operations and results during fiscal year. Preconstruction 
planningpreviously funded but not completed. 
15. RIVER DES PERES, MISSOURI 
Location. The 111 square mile River des Peres 
watershed includes all or part of 42 municipalities 
within St. Louis County plus the city of St. Louis, 
Missouri. 
Existing project. The project was authorized by 
the Water Resources Development Act of 1990 and 
would afford protection to the area. The authorized 
project includes channel modifications in the Deer 
Creek and University City Branch of River des Peres. 
The Deer Creek segment of the project would reduce 
flood damages in the cities of Rock Hill, Brentwood, 
Webster Groves and Maplewood, Missouri, by providing 
channel enlargement and stabilization along approximately 
2.5 miles of Deer Creek. The University 
City Branch segment of the project would reduce flood 
damages in the city of University City, Missouri, by 
providing channel enlargement and bank stabilization. 
The authorized project also includes: flood proofing 
along the Kirkwood Branch of Gravois Creek; a 
flood forecasting/warning plan; and complementary 
outdoor recreation features. At October 1992 price 
levels, the estimated cost of the project is $17,400,000 
Federal and $6,100,000 Non-Federal. 
Local cooperation. The Metropolitan St. Louis 
Sewer District (MSD) is the local sponsor. 
Operation and results during fiscal year. The 
Preconstruction Engineering Design (PED) work was 
initiated in FY 89 and is scheduled for completion in 
FY 94. The local sponsor has indicated that it will be 
able to finance initiation of this project beginning in 
FY 94 through project completion. No requests for 
funding were made for fiscal years 1992 or 1993 due 
to the MSD's funding shortages. 
16. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed work was accomplished at 
a cost of $506,933 for the Fiscal Year 1992. Total cost 
as of end of fiscal year is $8,003,740. 
14-6

ST. LOUIS, MO, DISTRICT 
17. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Sec. 205, 
Public Law 858, 80th Cong., as amended (preauthorization). 
Preauthorization study costs for Fiscal Year 1992 
were $143,108 for St. Peters, MO; $12,590 for Boise 
Brule Levee and Drainage District, MO; and $43,177 
on Grand Tower Drainage and Levee District, IL. 
Emergency bank stabilization activities pursuant 
to Sec. 14, Public Law 526, 79th Cong., as 
amended. 
During FY 1992, $4,320 was expended on Pomme 
Creek, Arnold, MO. 
Emergency flood control activities--repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal costs for the fiscal year were $310,490 for 
Disaster Preparedness, $146,195 for Emergency Operations, 
and $11,739 for Rehabilitation. 
Multiple-Purpose Project 
Including Power 
18. CLARENCE CANNON DAM AND 
RESERVOIR, SALT RIVER, MO 
Location. Salt River rises in Schuyler County, 
about 12 miles south of Missouri-Iowa State line. It 
flows southeasterly about 192 miles and empties into 
Mississippi River about 2 miles above Louisiana, MO, 
or about 284 miles above mouth of Ohio River. (See 
Kansas City and Quincy sheets of maps of United 
States published by Army Map Service, scale 
1:500,000, and Geological Survey quadrangle maps, 
1:250,000.) 
Previous project. For details, see page 645 of 
Annual Report for 1968. 
Existingproject. Project provides for construction 
of a multiple-purpose reservoir, including power, flood 
control, water supply, navigation storage, pollution 
abatement, fish and wildlife conservation, and recreation. 
Dam consists of a compacted earth embankment 
with a concrete spillway controlled by tainter 
gates. Dam and spillway are about 1,700 feet long. 
Spillway structure consists of an ogee overflow section 
surmounted by four 50- by 30-foot tainter gates. Reservoir 
will have a storage capacity of 1,428,000 acrefeet 
for use of flood control, future domestic and industrial 
water supply, sediment storage, and power generation. 
Project plan provides for installation of one 
27,000 KW conventional unit and one 31,000 KW 
reversible unit for pumped storage operations. Total 
Federal project cost estimate (1984) is $330,000,000 of 
which $22,420,000 is for lands and damages; 
$14,300,000 for water supply; $76,000,000 for 
hydropower. 
Local cooperation. Requirements of local cooperation 
are fully described on page 14-13 of Fiscal Year 
1980 Annual Report. Assurances have been received 
from the state of Missouri and approved by the Chief 
of Engineers. 
Operations and results during fiscal year. 
Work is complete on all major items. Lands acquired 
to date are 55,277 acres in fee and 10,068 acres in 
easements. Project is essentially complete. 
19. UPPER MISSISSIPPI RIVER 
ENVIRONMENTAL 
MANAGEMENT PROGRAM 
Location. The portion of the Upper Mississippi 
River within the boundaries of the St. Louis District 
extends from the mouth of the Ohio River (river mile 
0) to river mile 300, downstream of Lock and Dam 22. 
Existing project. The project is composed of five 
elements: Habitat Rehabilitation and Enhancement 
Projects, Long-term Resource Monitoring, Recreation 
Projects, Studies of Recreation Impacts and Navigation 
Traffic Monitoring. (The St. Louis District's involvement 
has been limited to Habitat Rehabilitation 
and Enhancement Projects and Long Term Resource 
Monitoring.) The overall program, involving five 
states, three engineer districts and two Corps of Engineers 
Divisions, is administered by the North Central 
Division. In the St. Louis District, three habitat 
rehabilitation projects have been constructed. These 
are Clarksville Management Area, Missouri, Dresser 
Island, Missouri, and Pharrs Island, Missouri. All 
projects are being operated and maintained by the 
state of Missouri. Through FY 1992, funds allocated 
to the St. Louis District have amounted to $7,424,000 
for design and construction of Habitat Rehabilitation 
and Enhancement Projects (HREP), $432,000 for 
Long Term Resource Monitoring (LTRM) and 
$670,000 for Program Management. The authorization 
limit for the overall program projected over a 
10-year period is $191,415,000. 
Local cooperation. The terms of local cooperation, 
as established by Public Law 99-662, will vary 
according to the nature of the project, land ownership 
and pre-existing management responsibilities. The 
Local Sponsor for Habitat Rehabilitation and Enhancement 
projects is usually the U.S. Fish and Wildlife 
Service in coordination with the state of Missouri 
or the state of Illinois. 
Operations and results during the fiscal year. 
The Dresser Island, Missouri, HREP construction contract 
was completed ahead of schedule and the project 
14-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
was turned over to the U.S. Fish and Wildlife Service 
and state of Missouri for operation and maintenance. 
The construction contract for the Pharrs Island, Missouri, 
HREP was completed in May 1992. The Definite 
Project Report (DPR) for Stump Lake, Illinois, HREP 
was approved and preparation of plans and specifications 
was initiated. The DPR for the Swan Lake, 
Illinois, HREP, is approved pending minor changes 
and plans and specifications will be initiated this year. 
Planning and design (DPR level) continued on four 
additional HREP projects. 
14-8

ST. LOUIS, MO, DISTRICT 
TABLE 14-A COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY92 1992 
3. Mississippi River 
Between Ohio and 
Missouri Rivers 
(Includes Chain 
of Rocks) 
4. Southeast 
Missouri Port, MO 
(Contrib. Funds) 
6. Alton to Gale 
Organized Levee 
Districts, IL & 
MO 
7. Cape Girardeau 
Jackson, MO 
(Contrib. Funds) 
9. East St. Louis 
and Vicinity, IL 
(Contrib. Funds) 
10. Kaskaskia Island 
Drainage & Levee 
District, IL 
12. Meramee R. Basin 
Valley Park, MO 
13. Pine Ford 
Lake, MO 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
$ 3,948,000 $ 9,021,000 $ 6,729,000 
17,569,473 9,268,135 8,733,282 
22,520,500 20,395,596 
22,533,237 20,168,279 
1,180,000 
1,155,537 
0 
267 
$5,949,000 $159,127,0001 
4,233,884 157,103,537' 
15,091,000 10,480,600 309,232,8292 
15,405,737 8,932,078 307,482,9862 
0 
12,048 
0 3,465,000 
11,891 3,459,697 
201,403 225,000 76,000 
201,000 225,330 75,777 
178,894 
241,387 
502,403 
502,107 
0 0 1,879,105 
0 5,600 1,874,885 
901,000 1,211,000 3,170,000 1,235,000 8,471,000 
208,758 1,410,532 3,493,997 1,208,634 8,275,921 
493,000 2,423,000 5,149,000 8,065,000 
450,851 1,052,621 6,327,460 7,830,932 
210,000 241,200 831,200 1,282,400 
190,506 20,241 774,685 985,431 
150,000 2,226,000 1,547,000 1,999,000 23,270,3263 
596,594 2,006,525 1,661,279 1,815,004 22,955,5984 
0
0 
-500,000 
143,107
0
0 
97,600
0 
4,326
0
0 
0 510,000 
85,700 409,999 
0 
4,007 
607,600 
495,699 
0 16,188,000 
0 16,188,000 
456,000 650,000 1,106,000 
392,606 664,921 1,057,527 
3,644,000 
3,644,000 
14-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 14-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Funds 
Section to Sep. 30, 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
18. Clarence Cannon New Work 
Dam and Approp. 0 34,000 50,000 141,000 312,917,028 s 
Reservoir, Salt Cost 325,533 384,441 39,034 129,094 312,846,3175 
River, MO 
Maint. 
Approp. 4,727,000 3,867,796 5,171,750 4,807,600 43,465,128 
Cost 5,126,986 3,834,524 4,967,641 4,653,410 43,007,252 
1. Excludes previous project cost of $1,416,620. 
2. In addition $3,109 was expended for rehabilitation. 
3. Includes $8,072,326 for work authorized by Flood Control Act of 1965. 
4. Includes $7,921,939 for work authorized by Flood Control Act of 1965. 
5. Includes $216,628 for definite project study under 1938 Flood Control Act. 
14-10

ST. LOUIS, MO, DISTRICT 
TABLE 14-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 23, 1962 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 19071 
Mar. 3, 19051 
Jun. 25, 1910 
Jan. 21, 1927 
Jul. 3, 1930 
Mar. 2, 1945 
Sep. 3, 19542 
Jul. 3, 19583 
Oct. 21, 1978 
Dec. 29, 1981 
Aug. 15, 1985 
and Nov. 17, 
1986 
Nov. 28, 1990 
1960 River and 
Harbor Act as 
amended. 
Section 107 
Nov 26, 1986 
KASKASKIA RIVER, IL 
Construct canal, lock, and dam to provide a 9-foot navigation 
channel from mouth to Fayetteville, IL. 
MISSISSIPPI RIVER BETWEEN OHIO AND MISSOURI 
RIVERS (See Section 3 of Text) 
Project for regulating works in 1881. (To obtain a minimum 
depth of 8 feet.) 
Dredging introduced as part of the project. 
These acts practically abrogated that part of project for 
middle Mississippi which proposed regulating works. 
Regulating works restored to project and appropriations 
begun with a view to completion of improvement between 
Ohio and Missouri Rivers within 12 years at an estimated 
cost of $21 million, exclusive of amounts previously 
expended. 
For 9 feet deep and 300 feet wide from Ohio River to northern 
Rivers and Harbors boundary of city of St. Louis. 
Project between northern boundary of St. Louis and Grafton 
(mouth of Illinois River) modified to provide a channel 
9 feet deep and generally 200 feet wide with additional 
width around bends. 
Modified to provide construction of a lateral canal with lock 
at Chain of Rocks. 
Modified to provide construction of a small-boat harbor 
opposite Chester, IL. 
Modified to provide construction of a fixed crest rockfill dam 
900 feet below Chain of Rocks Bridge. 
MELVIN PRICE LOCKS & DAM (FORMERLY LOCK 
AND DAM NO. 26 (REPLACEMENT)) 
Construct new dam and a 1,200-foot lock approximately 
2 miles downstream of the existing structure. 
Change name from "Lock and Dam No. 26" to "Melvin Price 
Lock and Dam" upon termination of service in 
U.S. Congress. 
Construct a second lock, 600 feet long at the Lock and Dam 
No. 26. (Replacement) Project. 
Modified to provide construction of cost-shared recreation 
facilities within the state of Illinois 
SOUTHEAST MISSOURI PORT, MO (See Section 4 of Text) 
Construct harbor channel with adjacent landfill. 
ST. LOUIS HARBOR, MO & IL (See Section 5 of Text) 
As outlined in the Report of the Chief of Engineers, 
dated Apr. 30, 1984, the Water Resources 
Development Act of 1986 authorizes navigation 
improvements. 
S. Doc. 44, 87th Cong., 
1st sess. 
Annual Report, 1881, 
p. 1536. 
Committee Doc. 9, 
69th Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 12, 
70th Cong., 1st sess. 
H. Doc. 231, 
76th Cong., 1st sess. 
H. Doc. 230, 
83d Cong., 1st sess. 
Public Law 95-502, 
95th Cong. 
Public Law 97-118, 
97th Cong. 
Public Law 99-88 and 
Public Law 99-662, 
99th Cong. 
Public Law 101-640, 
101st Cong. 
Public Law 99-662 
99th Cong., 2d sess. 
14-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 14-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 22, 1936 
Jun. 28, 1938 
1946 
Nov. 17, 1986 
Nov. 28, 1990 
Jun. 22, 1936 
Oct. 27, 1965 
Oct. 22, 1976 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 17, 1986 
ALTON TO GALE ORGANIZED LEVEE DISTRICTS, 
IL & MO (See Section 7 of Text) 
Authorized construction of levees to protect area from 
flooding from the Mississippi River. 
CAPE GIRARDEAU, JACKSON METROPOLITAN 
AREA, MO (See Section 8 of Text) 
As outlined in the Report of the Chief of Engineers dated 
Dec. 8, 1984, the Water Resources Development Act of 1986 
authorizes flood control and related recreational 
improvements in the Cape La Croix Creek Watershed. 
COLDWATER CREEK, MO (See Section 9 of Text) 
As outlined in the report of the Chief of Engineers dated 
Aug 9, 1988, the Water Resources Development Act of 1990 
authorizes flood control. 
EAST ST. LOUIS AND VICINITY, IL (See Section 10 
of Text) 
Raise and enlarge existing levee. 
Construct pumping plant and other modifications to reduce 
interior flooding. 
Construct Blue Waters Ditch as independent section. 
Repair and rehabilitate pump stations and appurtenant 
works, channels, and bridges. 
ELDRED AND SPANKEY DRAINAGE AND LEVEE 
DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
HARTWELL DRAINAGE AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
HILLVIEW DRAINAGE AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
KASKASKIA ISLAND DRAINAGE AND LEVEE 
DISTRICT, IL (See Section 11 of Text) 
Raise and enlarge existing levee. 
MALINE CREEK, MO (See Section 12 of Text) 
As outlined in the Report of the Chief of Engineers dated 
Nov. 2, 1982, the Water Resources Development Act of 
1986 authorizes flood control, recreation, and environmental 
improvements. 
Special report on 
record in OCE 
Flood Control 
Committee Doc. 1, 
75th Cong., 1st sess. 
Public Law 99-662, 
99th Cong., 2d sess. 
Public Law 101-640 
101st Cong. 
Special report on 
record in OCE. 
H. Doc 329, 
88th Cong., 2d sess. 
Public Law 94-587, 
94th Cong. 
Public Law 100-202, 
100th Cong. 
H. Doc. 472, 
87th Cong., 2d sess. 
H. Doc. 472, 
87th Cong., 2d sess. 
H. Doc. 472, 
87th Cong., 2d sess. 
H. Doc. 519, 
87th Cong., 2d sess. 
Public Law 99-662, 
99th Cong., 2d sess. 
14-12

ST. LOUIS, MO, DISTRICT 
TABLE 14-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 14, 1984 
Jun. 28, 1938 
Nov. 7, 1966 
Dec. 29, 1981 
Nov. 28, 1990 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 23, 1962 
Nov. 17, 1986 
Jun. 28, 1938 
MAUVAISE TERRE DRAINAGE AND LEVEE 
DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
MERAMEC RIVER BASIN, MO (See Section 13 of Text) 
Construct reservoirs and local protection project. 
Construct Pine Ford, Irondale, and 1-38 dams and 
19 Angler-use sites. (See Section 14 of Text) 
Undertake structural and nonstructural flood control 
measures. 
RIVER DES PERES, MO (See Section 15 of Text) 
As outlined in the report of the Chief Engineers 
dated May 23, 1989, the Water Resources Development 
Act of 1990 authorizes flood control. 
MCGEE CREEK DRAINAGE AND LEVEE DISTRICT, IL 
Reconstruct existing levee and construct pumping plant to 
reduce flooding. 
MEREDOSIA LAKE AND WILLOW CREEK DRAINAGE 
AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
NUTWOOD DRAINAGE AND LEVEE DISTRICT, IL 
Raise and enlarge existing levee and other modifications. 
REND LAKE, BIG MUDDY RIVER, IL 
Construct dam at Benton, IL, and subimpoundment dams on 
upper arms of reservoir. 
STE. GENEVIEVE, MO 
As outlined in the Report of the Board of Engineers for 
Rivers and Harbors dated Apr. 16, 1985, the Water 
Resources Development Act of 1986 authorizes construction 
of a levee and a pumping plant to protect the city from 
Mississippi River and Gabouri Creek floods. 
WOOD RIVER DRAINAGE AND LEVEE DISTRICT, IL 
Construct reservoirs and local protection projects. 
Energy and Water 
Development Approp. 
Act of 1985, 
98th Cong., 2nd sess. 
Flood Control 
Committee, Doc. 1, 
75th Cong., 1st sess. 
H. Doc. 525, 
89th Cong., 2d sess. 
Public Law 97-128, 
97th Cong. Amended 
Section 1128, 
Public Law 99-662, 
99th Cong. 
Public Law 101-640 
101st Cong. 
H. Doc. 472, 
87th Cong., 2d sess. 
H. Doc. 472, 
87th Cong., 2d sess. 
H. Doc. 472, 
87th Cong., 2d sess. 
H. Doc 541, 
87th Cong., 2d sess. 
Public Law 99-662, 
99th Cong., 2d sess. 
Flood Control 
Committee Doc. 1, 
75th Cong., 1st sess. 
14-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 14-B 
(CONTINUED) 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
CLARENCE CANNON DAM AND RESERVOIR, SALT 
RIVER, MO (See Section 18 of Text) 
Oct. 23, 1962 Modified act of Jun. 28, 1938 by deleting the reservoir H. Doc. 507, 
therefrom and reauthorizing it as a separate multiple- 87th Cong., 2d sess. 
purpose project. 
Oct. 27, 1965 Changes name of project from Joanna Dam to present Public Law 89-298, 
designation. 89th Cong. 
1. Also joint resolution, Jun. 29, 1906. 
2. Inactive. 
3. All work completed. 
14-14

ST. LOUIS, MO, DISTRICT 
TABLE 14-C OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Cuivre River, MO' 1883 $ 12,000 $ -- -- 
Moccasin Springs, MO 1969 76,4362 -- 
Wabash Railroad Bridges, Illinois River, 
Meredosia, and Valley City, IL 1961 2,653,194 1961 -- 
1. Inactive. River declared nonnavigable by act of Mar. 23, 1900. 
2. Excludes $56,605 contributed funds. 
14-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 14-D OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Cache River Diversion, IL 1953 2,837,114 -- 1953 
Cape Girardeau, MO, No. 2 1965 5,157,805 -- 1964 
Carlyle Lake, IL 1981 42,819,400 58,974,202 Oct. 1976 
Chouteau, Nameoki, and Venice Drainage 
and Levee District, IL 1955 185,700 -- 1955 
Columbia Drainage and Levee 
District No. 3, IL 1981 2,818,000 -- Aug. 1981 
Degognia and Fountain Bluff Levee and 
Drainage District, IL 1959 5,889,500 -- 1959 
Dively Drainage & Levee District, IL 1976 1,720,000 -- 1976 
Emergency bank protection for certain 
highway and railroad facilities at Price 
Landing, MO (see Flood Control 
Act of 1944)1 1950 55,415 -- Oct. 1949 
Emergency repairs to levees on Mississippi, 
Illinois, and Kaskaskia Rivers and flood 
fighting and rescue work (Sec. 5, Flood 
Control Act of 1941, as amended)' 1953 -- -- 1951 
Emergency protection for certain highway 
and railroad facilities at Chester, IL, 
bridge (Sec. 12, Flood Control Act of 1944) 1952 50,000 -- Jan. 1952 
Emergency protection for Illinois approach, 
Chain of Rocks Bridge (Sec. 12, Flood 
Control Act of 1944) 1946 25,000 -- Aug. 1945 
Fort Chartres and Ivy Landing Drainage 
District No. 5, IL 1970 1,154,800 -- 1958 
Grand Tower Drainage and 
Levee District, IL 1959 4,677,900 -- 1959 
Harrisonville Levee and 
Drainage District, IL 1981 6,829,069 -- Mar. 1981 
Kaskaskia Island Drainage and 
Levee District, IL 1959 297,460 -- 1949 
Kaskaskia River, IL2 1989 147,387,000 18,941,196 1988 
Lake Shelbyville, IL 1981 44,000,000 61,474,923 Sep. 1978 
Mauvaise Terre Drainage 
and Levee District, IL 1989 589,000 -- 1988 
McGee Creek Drainage 
and Levee District, IL 1989 25,043,300 -- 1989 
Meredosia Lake and Willow Creek Drainage 
and Levee District, IL 1944 249,738 -- 1944 
Miller Pond Drainage District, IL 1955 164,183 -- 1955 
Mississippi River Agricultural 
Area 8, MO 1987 2,137,000 -- -- 
Mississippi River at St. Louis, MO 1980 79,265,166 -- Jan. 1980 
Mississippi River Agricultural Area 
No. 12, MO 1967 -- -- -- 
Mississippi River, Alton to Gale, IL, 
underseepage measures -- 85,422 -- Oct. 1962 
North Alexander Drainage and 
Levee District, IL 1957 939,569 -- 1957 
14-16

ST. LOUIS, MO, DISTRICT 
TABLE 14-D 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS
Cost to Sep. 1992 
For Last 
Full Report Operation 
See Annual and Mo. and Yr. 
Project Report For: Construction Maintenance Completed 
Nutwood Drainage and 
Levee District, IL 1989 670,000 -- 1984 
Perry County Drainage and Levee3 
District Nos. 1, 2, and 3, MO 1987 7,968,700 -- 1986 
Prairie du Pont Levee and 
Sanitary District, IL4 1970 6,005,127 -- 1970 
Prairie du Rocher and vicinity, IL 1959 3,882,600 -- 1959 
Preston Drainage and Levee District, IL 1959 1,866,910 -- 1959 
Rend Lake, Big Muddy River, IL5'6 1989 43,700,900 45,155,575 1988 
Strington, Ft. Chartres, and Ivy 
Landing, IL 1957 2,123,700 -- Aug. 1956 
Urban areas at Alton, IL 1960 192,000 -- -- 
Village of New Athens, IL 1981 1,983,000 -- Sep. 1981 
Valley City Drainage & Levee District, IL7 1967 91,952 -- 1967 
Wood River Drainage and Levee District, IL' 1989 17,163,821 -- 1988 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
8. 
Work complete, now performed under Public Law 99. 
Excludes $10,461 expended on previous project. 
Excludes $6,800,700 for previous project. 
Includes $5,235,927 for previous project. 
Excludes $550,000 Area Development Administration Funds allotted to the State of Illinois for increased construction costs 
of Interstate Highway 57 to meet project requirements, and excludes $449,093 Area Redevelopment Administration Funds 
allotted to the Corps. 
Includes $6,103,711 credit to State of Illinois for work in kind. 
Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act, as amended). 
Funds are for work authorized by Flood Control Act of 1938. 
14-17

REPORT OF THE SECRETARY OF THE ALA. .... - CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 14-E 
For Last 
Full Report Date Federal Contrib 
See Annual And Funds Funds 
Project Report For Authority Extended Exp 
Angler-use sites, Meramec Basin, MO 
Big Swan D&L District Illinois River, IL 
Cape Girardeau, MO Reaches Nos 1, 3, and 4 
Clear Creek Drainage and Levee District, IL 
East Cape Girardeau and Clear Creek D&L 
District, IL 
Eldred, IL 
Fort Chartres & Ivy Landing D&L District No. 5 
and Stringtown Drainage and Levee District 
No. 4, IL 
Grafton Small Boat Harbor, IL 
1-38 Lake, MO 
1967 
1959 
1964 
1963 
1962 
1971 
19621 
Indian Creek Area Illinois River, IL 
Irondale Lake, MO 
Keach Drainage and Levee District, IL 
Levee Districts between Carlyle and New Athens, 
IL, Nos. 2, 5, 6 and 7 
Levee Districts between Carlyle and New Athens, 
IL Nos. 3, 4, 8, 10 and 13 
Levee Districts between Cowden and Vandalia, IL 
Meramec Park Lake, MO 
Mississippi River Agricultural Area No. 10, MO 
Mississippi River at Alton, IL 
Small Boat Harbor 
Preston Drainage and Levee District, IL 
Richland Creek, IL 
Riverland Levee District, MO 
Scott County D&L District Illinois River, IL 
Small Boat Harbor opposite 
Chester, IL 
Small Boat Harbor opposite 
Hamburg, IL 
Ste. Genevieve County Drainage and Levee District 
No. 1, MO 
St. Louis County Drainage and Levee District 
No. 1, MO 
Union Lake, MO 
Wiedmer Chemical Drainage and Levee 
District, MO 
1979 
1979 
1978 
1967 
19581 
1959 
1969 
1936 
19541 
19501 
1936 
1936 
1979 
1936 
1 Year authorized. 
14-18 
DEAUTHORIZED PROJECTS 
Oct 86 
Oct 86 
Oct 78 
PL100-676 
Jan 90 
PL100-676 
Jan 90 
Nov 79 
Oct 86 
Nov 77 
PL100-676 
1 Jan 1990 
Nov 81 
PL100-676 
1 Jan 1990 
Oct 86 
Nov 79 
Nov 79 
Oct 78 
Dec 81 
Nov 79 
Nov 77 
PL100-676 
1 Jan 1990 
PL100-676 
10 Aug 89 
Aug 77 
Oct 86 
Nov 77 
Nov 77 
Nov 77 
Nov 77 
Jan 90 
Nov 77 
$ 22,000 
4,984,500 
1,920,600 
-- 
496,000 
35,784,122 
-- 
1,866,910 
401,000 
4,931,154

ST. LOUIS, MO, DISTRICT 
TABLE 14-F ACTIVE GENERAL INVESTIGATIONS 
(96X3121) 
Federal Cost Totals by 
Item and CWIS Number FY 92 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies(120) 
Alexander and Pulaski Counties, IL-12217 $ 4 
Apple Creek, MO-12869 282,345 
Cuivre River, MO-12744 24,490 
Dardenne Creek, MO-12452 21,563 
Kaskaskia River Basin, IL-99192 204,355 
Plattin Creek, MO-12785 1,711 
St. Louis County, MO-12866 38,995 
St. Louis Metropolitan Area, MO and IL-55040 71,284 
Subtotal 644,747 
Special Studies (140) 
Jefferson County, MO-12865 149,002 
Miscellaneous Activities(170) 
Dam Safety Criteria Studies-14713 18,994 
Review of FERC Licenses 2,064 
Special Investigations-17250 29,195 
Waterfowl Management Plan-53904688 
Subtotal 54,941 
Coordination Studies with Other Agencies(180) 
Plan Assist to State of IL-14817 6 
Plan Assist to State of MO-1482913423 
Subtotal 13,429 
TOTAL (Category 100) $655,700 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250)-82030, and -82040 172,879 
Hydrology Studies (260)-538209227 
TOTAL (Category 200) 182,106 
ADVANCE ENGINEERING AND DESIGN (Category 600) 
Coldwater Creek, MO-12252 159,647 
Maline Creek, MO-12297 6,240 
River Des Peres, MO-12638 111,921 
St. Louis Harbor, MO & IL-10184 89,668 
Ste. Genevieve, MO-75453 13644 
TOTAL (Category 600) 381,120 
GRAND TOTAL GENERAL INVESTIGATIONS $1,918,614 
14-19

NASHVILLE, TN, DISTRICT* 
This district comprises portions of southern 
Kentucky, southwestern Virginia, western North 
Carolina, northern Georgia and Alabama, northeastern 
Mississippi and practically all of Tennessee except 
western portion, and embraces drainage basins of 
Tennessee and Cumberland Rivers and their tributaries. 
IMPROVEMENTS 
Navigation Page 
1. Cumberland River, TN and KY.....................15-2 
2. Tennessee River, TN, AL and KY.................15-3 
3. Tennessee-Tombigbee Waterway, AL 
and M S ........................................................... 15-3 
4. Navigation Work Under Special 
Authorization ................................................. 15-4 
Alteration of Bridges 
5. Authorized Alteration of Bridges .................. 15-4 
Flood Control 
6. Big South Fork National River and 
Recreation Area, KY and TN.........................15-4 
7. Martins Fork Lake, KY ................................. 15-4 
8. Middlesboro, Cumberland River Basin, KY..15-5 
9. Tug and Levisa Forks of the Big Sandy 
River and Cumberland River, W VA, 
VA and KY ...................................................... 15-5 
10. Ohio River Basin (Nashville Dist.)................15-5 
11. Inspection of completed flood control 
projects ........................................................... 15-5 
12. Flood control work under special 
authorization..................................................15-6 
Multiple-Purpose Projects, Including Power 
13. Center Hill Lake, Ohio River Basin, TN ....... 15-6 
14. Dale Hollow Lake, Ohio River Basin, 
TN and KY ..................................................... 15-6 
15. J. Percy Priest Dam and Reservoir, Ohio 
River Basin, TN ............................................. 15-6 
16. Laurel River Lake, Ohio River Basin, KY.....15-7 
17. Wolf Creek Dam - Lake Cumberland, Ohio 
River Basin, KY ............................................. 15-7 
18. Dam Safety Program ..................................... 15-7 
General Investigations 
19. Surveys...........................................................15-7 
20. Collection and study of basic data ................ 15-8 
Tables Page 
Table 15-A Cost & Financial Statement.............15-9 
Table 15-B Authorizing Legislation..................15-11 
Table 15-C Other Authorized Navigation 
Projects............................................15-13 
Table 15-D Not Applicable........................................... 
Table 15-E 
Table 15-F 
Other Authorized Flood Control 
Projects............................................15-13 
Other Authorized Multiple-Purpose 
Projects, Including Power...............15-14 
Table 15-G Deauthorized Projects ..................... 15-14 
Table 15-H Cumberland River, TN & KY, 
Principal Features...........................15-15 
Table 15-I Tennessee River Lock Dimensions .15-16 
Table 15-J 
Table 15-K 
Tennessee River Total Cost of 
Existing Project...............................15-17 
Ohio River Basin (Nashville 
District) Local Protection ............... 15-17 
Table 15-L Reservoirs........................................15-17 
Table 15-M Inspection of Completed Flood 
Control Projects ............................... 15-18 
Table 15-N Flood Control Work Under Special 
Authorization .................................. 15-18 
15-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
Navigation 
1. CUMBERLAND RIVER, TN AND KY 
Location. Formed by junction of Poor and Clover 
Forks in Harlan County, KY, about 694.2 miles above 
its mouth, and flows west to Burnside, KY, from 
whence it makes a loop southwestward into Tennessee, 
passes Nashville, and returns northwestward to 
Kentucky, emptying into Ohio River near Smithland, 
KY (See Geological Survey base maps of Tennessee and 
Kentucky.) 
Previous projects. For details see pages 1898 and 
1901 of Annual Report for 1915, and page 1208 of 
Annual Report for 1938, and pages 1069 and 1070 of 
Annual Report for 1962. 
Existing project. Below Nashville: Improvement 
of Cumberland River between mouth and Nashville 
was authorized for 9-foot navigation; increased project 
depth to be obtained by construction of three moderate 
height dams with lockage facilities, designated as 
Kuttawa (Eureka), Dover, and Cheatham, to replace 
existing locks A to F inclusive below Nashville and lock 
1 above Nashville. (See table 15-B for authorizing legislation.) 
Subsequent authorities provide for construction 
of hydroelectric power-generating facilities at 
Cheatham Dam, rivermile 148.7, and modification of 
project for navigation on Cumberland River, TN and 
KY, to provide, in lieu of previously authorized works 
at Kuttawa, mile 32.2, and Dover, mile 100.1, for construction 
of a multiple-purpose improvement consisting 
of a dam, lock, and powerplant near mile 30.6 on lower 
Cumberland River and a canal for navigation and other 
purposes connecting this reservoir with reservoir 
formed by Kentucky Dam on the Tennessee River. The 
project is known as Barkley Dam and Lake Barkley. 
Provision of interconnecting canal, involving excavation 
of a channel through narrow watershed divide 
about 2.5 miles upstream from damsite, permits alternatives 
routes available for navigation between either 
Cumberland or Tennessee Rivers and Ohio River, and 
affords integrated operation of Barkley and Kentucky 
Reservoirs through diversion of flows in interests of 
flood control and power production. Cost of modified 
project for 9-foot navigation and multiple-purpose 
development is $178,181,406 Federal funds and 
$102,966 non-Federal funds for recreation facilities 
under the completed projects program. (See table 15-H 
for listing of principal features.) 
Under flood conditions as regulated by upstream 
reservoirs, extreme fluctuation in stage of river below 
Nashville, TN, varies at different localities from about 
16 to 55 feet above minimum pool levels. Ordinary 
fluctuations vary with power flows from as much as the 
allowable 3-foot drawdown below normal pool elevation 
385 at Cheatham Lock and Dam to a range of about 7 
feet at Nashville. Seasonal variation in normal headwater 
levels at Lake Barkley is 5 feet, which in combination 
with power flows produces fluctuations up to 10 
feet below Cheatham Lock and Dam. 
Above Nashville: See pages 1693 thru 1696 of 
Annual Report for 1950 for information including statistical 
data on locks and dams 1 to 17 and 21. 
Completion information is shown on pages 1454 of the 
report for 1951. See Table 15-B for Authorizing 
Legislation. Construction of Old Hickory, Carthage, 
and Celina Dams above Nashville was also authorized 
for navigation and power. The dam and reservoir 
authorized for construction on Cumberland River near 
Carthage, TN, has been redesignated as Cordell Hull 
Dam and Reservoir. Cost of Old Hickory and Cordell 
Hull projects, including locks, is $132,140,900. 
Estimated cost of Celina Dam (1985) is $213,000,000. 
(See table 15-H at end of chapter for listing of principal 
features.) 
Under flood conditions as presently regulated, 
including effect of surcharge operation of Old Hickory 
project, extreme fluctuations of stage in this section of 
river vary from a range of 35 feet at Nashville (mile 
191) to a maximum of 46 feet immediately below Old 
Hickory Dam (mile 216.2), and from an 8-foot variation 
in headwater at dam to 36 feet in vicinity of Carthage, 
TN, (mile 313.5), present head of navigation; with variations 
up to 35 feet at Celina, TN (mile 380.8) and 29 
feet in tail water at Wolf Creek Dam (mile 460.9). 
Maximum fluctuations under ordinary conditions from 
power flows vary from about 7 feet at Nashville to 14 
and 3 feet, respectively, in tailwater and headwater of 
Old Hickory Dam, and at other key points as follows: 
13 feet at Carthage; 18 feet at Celina; and 19 feet at 
Wolf Creek Dam. 
Further details on project authorization for river 
sections below and above Nashville as shown on Table 
15-B. 
Local cooperation. Under modified project for 9- 
foot navigation and multiple-purpose development, 
recreation features of reservoir components are subject 
to certain conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Terminal facilities. There are 42 terminals on the 
Cumberland River (5 Municipally owned and open for 
public use; 4 government owned facilities and 33 privately 
owned facilities). A total of 19 terminals have 
railroad connections. Principal commodities handled 
are petroleum products, stone, sands, gravel, coal, 
coke, iron, steel, chemicals and grain. Facilities considered 
adequate for existing commerce. For further information 
see page 695 of Annual Report for 1969. 
Operations during fiscal year. New work: None. 
Maintenance: Barkley, Cheatham, Cordell Hull, 
and Old Hickory locks and dams were operated as 
required. Operation and Maintenance improvements 
included completion of a contract to design and instal 
of self-cleaning trash rack system at Cheatham. 
Removal and disposal of the debris began this fiscal 
year. This system will serve as a demonstration project 
for other sites. Contracts were awarded for fishing 
access improvements at the Old Hickory Dam site and 
15-2

NASHVILLE, TN, DISTRICT 
construction of a comfort station at the Old Hickory 
Beach. At Barkley a contract was awarded for toe 
drainage improvements, and one for ceiling and air 
conditioning replacement. A contract for roofing the 
powerhouse at Cheatham was awarded, and at 
Cheatham and Old Hickory work began to remove 
paint containing lead. 
Total net energy generated at Barkley Dam 
(774,831,914 kw-hr) was made available through 
Department of the Interior to the Tennessee Valley 
Authority, Southern Illinois power Cooperative, Big 
Rivers Rural Electric Cooperative Corporation, and 
Indiana a Statewide Rural Electric Cooperative, Inc, 
Hosier energy Division. Total net energy generated at 
Cheatham Dam (197,446,027 kw-hr), Cordell Hull 
(368,605,025 kw-hr), and Old Hickory (467,250,140 kwhr) 
was made available for distribution. Activities 
under reservoir management program comprising 
malaria control, shoreline sanitation, land management 
and disposal, and maintenance of public-use facilities 
continued. 
2. TENNESSEE RIVER, TN, AL AND KY 
Location. Formed by junction of French Broad and 
Holston Rivers in eastern Tennessee, 4.4 miles above 
Gay Street Bridge at Knoxville, flows southwest into 
northern Alabama, thence in a generally westerly 
course across north Alabama, to northeast boundary of 
Mississippi, thence nearly due north across Tennessee 
and Kentucky, entering Ohio River at Paducah, 652.1 
miles from junction of French Broad and Holston 
Rivers. (See Geological survey base map of Tennessee 
River Basin.) 
Previous projects. For details see pages 1902- 
1906, Annual Report for 1915; pages 1190-1194, 1196- 
1216, and 1220-1222, Annual Report for 1929; and 
page 1216, Annual Report for 1938. 
Existing project. Originally provided for permanent 
improvement of river for a navigable depth of 9 
feet at low water from mouth about 650 miles to 
Knoxville, TN. Only work performed by the Corps was 
construction of lock at General Joe Wheeler Dam and 
miscellaneous appurtenant improvements at a new 
work cost of $2,244,236. Tennessee Valley Authority 
program provided for obtaining authorized 9-foot project 
by construction of high dams and locks and utilization 
of certain locks and dams previously constructed 
under jurisdiction of the Corps. (See Table 15-B for 
Authorizing Legislation.) Subsequent construction by 
the TVA of Melton Hill Dam extends navigable channel 
of Tennessee River system up the Clinch River about 
38 miles above damsite (mile 23.1) to vicinity of 
Clinton, TN. (See table 15-I on Tennessee River.) 
In accordance with general navigation laws placing 
control and supervision over navigable waters under 
direction of Secretary of the Army, the Corps of 
Engineers operates and maintains all locks, and maintains 
navigation channels and safety harbors by performing 
all necessary maintenance dredging and snagging 
operations. For information concerning other 
functions of the Corps under division of responsibilities 
for Tennessee River since adoption of Tennessee Valley 
Authority Act of 1933, see page 1084 of Annual Report 
for 1962. 
Local cooperation. Authorization requires no local 
cooperation in construction of alternate system of low 
dams. It does, however, provide that if high dams are 
built before the United States builds projected locks 
and low dams which are to be replaced, the United 
States shall contribute to cost of substituted structures 
an amount equal to estimated cost of works of navigation 
for which substitution is made. 
Terminal facilities. There are 143 terminals on 
the Tennessee River (16 municipally owned, 15 government 
owned facilities and 112 privately owned facilities). 
A total of 79 terminals have railroad connections. 
Principal commodities handled are petroleum products, 
stone, sand, gravel, coal, coke, grain, chemicals, iron, 
and steel. Facilities considered adequate for existing 
commerce. A list of terminals is revised annually and 
can be obtained from Division Engineer, Ohio River 
Division, Corps of Engineers, Cincinnati, Ohio. For 
further information see page 698 of Annual Report for 
1969. 
Operations during fiscal year. Channel work by 
government plant and hired labor consisted of dredging 
and snagging at various locations, and maintenance of 
mooring facilities and safety harbors. Cost of channel 
maintenance was $991,246. Maintenance: All locks 
were operated and lock appurtenances and standby 
plant maintained as required. Major maintenance 
included unwatering and repairs to Pickwick Main and 
Auxiliary locks, Wheeler, Nickajack, and Kentucky 
Main locks, replacement of lock operating machinery at 
Wheeler Auxiliary and valves and two gates at 
Wheeler Main Lock. Culvert bulkheads and valves 
were replaced at Fort Loudon, Watts Bar and 
Chickamauga. Dredging of the navigation channel at 
several sites was performed. Approximately 44 million 
tons of commodities were locked through the Tennessee 
River locks. 
3. TENNESSEE-TOMBIGBEE 
WATERWAY, AL AND MS 
Location. West Central Alabama and Northeastern 
Mississippi; in Marengo, Sumter, Greene and Pickens 
Counties, Alabama, and Noxubee, Lowndes, Clay, 
Monroe, Itawamba, Prentiss and Tishomingo Counties, 
Mississippi. 
Existing project. Provides for a waterway 234 
miles in length, connecting the Tombigbee and 
Tennessee Rivers by way of the East Fork of 
Tombigbee River, Mackeys and Yellow Creeks, affording 
a channel not less than 9 feet deep and 280 feet in 
bottom width, with 10 locks each having clear chamber 
dimensions of 110 x 600 feet. Construction for the 
15-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
divide section, including Bay Springs lock and dam, is 
assigned to the Nashville District; whereas, the prosecution 
of work on the river and canal sections is under 
the jurisdiction of the Mobile District. Only activities 
of the Nashville District are reported herein. 
Estimated Federal cost of new work under jurisdiction 
of the Nashville District is $751,000,000. (See 15-B for 
authorizing legislation). 
Local cooperation. Authorization requires local 
interests to construct, maintain and operate all highway 
bridges, construct and maintain all highway relocations 
or alterations, make and maintain alterations 
as required to sewer, water supply and drainage facilities, 
assume cost of operation and maintenance of utility 
crossings, provide and maintain as required suitable 
and adequate river and canal terminals in accordance 
with plans approved by the Secretary of the Army and 
the Chief of Engineers. 
Operations during fiscal year. Construction continued 
at the Crow's Neck Environmental Education 
Center at Bay Springs. Construction at the Holcut 
Park, Divide Overlook & Natchez Trace Site, and the 
Damsite West Bank Recreation site was completed. 
The Environmental Education Center represents the 
final scheduled recreation construction. The project is 
more than 99% complete. Navigation features are 
100% complete. 
4. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Sec. 107, Public 
Law 86-645, as amended (preauthorization). 
During the period $5,237 was expended for a design 
of an access channel to Port of Florence, AL. 
Alteration of Bridges 
5. AUTHORIZED ALTERATION OF 
BRIDGES 
Work on Woodland Street bridge, under Truman- 
Hobbs Act, was initiated in 1965 and completed in 
1966. Costs were $987,632. For details see page 922 of 
Annual Report for 1967. 
Flood Control 
6. BIG SOUTH FORK NATIONAL RIVER 
AND RECREATIONAL AREA, KY 
AND TN 
Location. The project is located in Northeastern 
Tennessee and Southeastern Kentucky along the Big 
South Fork River and its tributaries in Pickett, Scott, 
Fentress, and Morgan Counties, Tennessee, and 
McCreary County, Kentucky. 
Existing project. A National Recreation Area was 
established in accordance with the concept included in 
the interagency report prepared pursuant to section 
208 of Flood Control Act of 1968. Total acreage was 
not to exceed 125,000 acres. The act specifically established 
the National Area for the purpose of preserving 
and interpreting the scenic, biological, archeological 
and historical resources of the river gorge area and 
developing the natural recreational potential of the 
area. The project was authorized by the Water 
Resource Development Act of 1974, 1976 and Water 
Resources Development Act of 1986. (See table 15B for 
authorizing legislation). The authorized cost (ceiling) 
for the project was $156,122,000. $112,123,900 was 
appropriated to The Corp of Engineers for design and 
construction of park facilities. The first construction 
contract was awarded in June 1981. 71% of the authorized 
project is complete. By Memorandum of 
Agreement dated 1 October 1990 jurisdiction of the 
area was transferred to The Department of Interior. 
Local cooperation. None required. 
Operation during fiscal year. The Memorandum 
of Agreement between the Department of Army and 
the Department of Interior, transferring jurisdiction of 
the Big South Fork National River and Recreation 
Area, itemized activities to be completed by the Army. 
The Memorandum of Agreement between the 
Department of Army and the Department of Interior, 
transferring jurisdiction of the Big South Fork 
National River and Recreation Area, itemized activities 
to be completed by the Army. In accordance with this 
agreement, miscellaneous minor construction items 
were completed. An outstanding real estate claim will 
be the responsibility of the Corps. 
7. MARTINS FORK LAKE,KY 
Location. Dam located at mile 15.6 on Martins 
Fork of Clover Fork, Cumberland River, about 10 miles 
southeast of city of Harlan, with reservoir extending 
about 6 miles upstream within Harlan County, southeastern 
Kentucky. 
Existing project. Multiple-purpose improvement 
combining flood control with water quality control and 
recreation development adopted by 1965 Flood Control 
Act (H. Doc.244, 89th Cong.), in general accordance 
with recommendations. Dam is concrete type, 504 feet 
long and rising 97 feet above streambed. Outlet works 
provide for release of water from reservoir at varying 
levels. Drainage area above damsite is 55.7 square 
miles. At full pool level, spillway crest at elevation 
1341 above mean sea level, reservoir will cover 578 
acres and contain 21,120 acre-feet of storage capacity. 
Provision is made for 17,450 acre-feet of reservoir 
capacity between elevations 1341 and 1300 for control 
of floods in winter and spring season, and 14,360 acrefeet 
(El. 1341-1310) during summer and fall, in conjunction 
with which storage of 3,090 acre-feet would be 
available on a seasonal basis to meet streamflow 
requirements for water quality control and fish life 
15-4

NASHVILLE, TN, DISTRICT 
below the dam. A minimum permanent pool of 3,670 
acre-feet, 274 acres in extent, is available during the 
potential flood seasons; and during late spring and 
summer when flood storage can be reduced, the lake is 
operated generally at a higher level (El. 1310) to maintain 
a larger surface area of 340 acres for recreation 
and provide the required seasonal storage for releases 
of water during critical low-flow periods. Project prevents 
a major portion of average annual flood losses at 
Harlan and results in significant stage reductions with 
related benefits along rural reaches and to other urban 
areas downstream. Actual cost of project including 
$95,000 code 710 funds is $20,479,911. First construction 
contract awarded in December 1972. Project completed 
for beneficial use in September 1978. 
Local cooperation. Federal Water Project 
Recreation Act of 1965 (P.L. 89-72) applies in regard to 
non-Federal participation in recreation development, 
in addition to which local interests are to provide certain 
safeguards to ensure functioning of reservoir as 
intended. In May 1981 a final recreation cost-sharing 
contract with Harlan County was approved and certain 
recreation facilities have been jointly developed by the 
Corps and the County. These facilities, consisting of a 
swimming beach and a picnic area are now operated 
and maintained by Harlan County. Recreation investment 
to date (Corps and Local) is about $100,000. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures operated 
as required. 
8. MIDDLESBORO, CUMBERLAND 
RIVER BASIN, KY 
Location. At Middlesboro, Ky., on Yellow Creek, a 
tributary entering Cumberland River about 660 miles 
above its mouth. 
Existing project. A system of canals and levees 
around one side of town, arranged so as to divert most 
headwaters of Yellow Creek away form present channel 
through heart of city. Protection is thus afforded in 
large measure to life and property within business district 
and a large part of residential section. For project 
details, see page 1088 of Annual Report for 1962. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Work on levees, canals, and appurtenances was accomplished 
by hired labor. 
9. TUG AND LEVISA FORKS OF THE 
BIG SANDY RIVER AND UPPER 
CUMBERLAND, WV, VA AND KY 
Location. The project is located in the State of West 
Virginia and the Commonwealths of Kentucky and 
Virginia. The Cumberland portion consists of the 
Upper Cumberland River Basin, above Cumberland 
Falls, KY. The basin is approximately 100 miles in 
length, averaging 30 miles in width at the lower portion 
and 10 miles in width upstream at Harlan KY. 
The Big Sandy Basin is within the Huntington District 
and the Cumberland within the Nashville District. 
Existing project. Provides for flood control measures 
for communities in the Tug and Levisa Forks and 
Upper Cumberland River Basins. The Cumberland 
portion has been assigned to the Nashville District. 
Only activities of the Nashville District are reported 
herein. Estimated Federal cost of new work under 
jurisdiction of the Nashville District is $306,400,000. 
The project was authorized by the Energy and Water 
Development Appropriation Act of 1981, Section 202 of 
PL 96-367. 
Local cooperation. Authorizing legislation 
requires that non-Federal interests shall hold and save 
the United States free from damages due to construction 
works and maintain and operate all such works 
after their completion in accordance with regulations 
by the Secretary of the Army. 
Operations during fiscal year. Engineering and 
design continued. Acquired 6.27 acres fee and 1.53 
acres easement. At Harlan construction of the diversion 
tunnels continued, and a contract was awarded for 
a levee/floodwall. Real estate acquisition and design of 
future phases of work continued. At Barbourville a 
contract for construction of the levee, and a contract for 
the floodwall and closure structures continued. Real 
estate acquisition continued. Non-structural evacuations 
continued at Pineville, Harlan and Barbourville, 
and floodproofing was initiated at Barbourville and 
Harlan. 
10. OHIO RIVER BASIN 
(NASHVILLE DISTRICT) 
Location. A series of levees, floodwalls, channel 
improvements, and reservoirs in Ohio River Basin 
within Nashville District. 
Existing project. The general comprehensive plans 
approved for flood control and other purposes in Ohio 
River Basin is set forth in legislation listed in Table 15- 
B. Individual projects, local protection projects and 
lakes, considered in comprehensive plan within 
Nashville District are listed in Table 15-K 
11. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts, requires local interests furnish assurances they 
will maintain and operate certain local protection projects 
after completion in accordance with regulations 
prescribed by Secretary of the Army. District 
Engineers are responsible for administration of these 
regulations within their respective districts. 
Maintenance inspections were made during fiscal year 
of completed protective works in localities transferred 
to local interests for maintenance and operation. Local 
interests were advised, as necessary, of measures 
15-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
required to maintain projects in accordance with standards 
prescribed by regulations. Fiscal year cost was 
$11,699. Total cost to September 30, 1992 was 
$376,743. For project inspection data see table 15-M. 
An additional $206,789 was expended under authority 
of Section 216 of 1970 Flood Control Act (PL 91-611) 
for an Initial Appraisal Report of The Cross Creeks 
National Wildlife Refuge. 
12. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control and coastal emergencies (Public Law 
99, 84th Cong., and antecedent legislation). 
Actual Federal cost for the fiscal year was $228,225 
for disaster preparedness. 
Multiple-Purpose Projects, Including 
Power 
13. CENTER HILL LAKE, OHIO 
RIVER BASIN, TN 
Location. Dam is on Caney Fork River, 26.6 miles 
above its confluence with Cumberland River (mile 
309.2) at Carthage, TN. It is in DeKalb County, TN., 
about 55 miles east of Nashville, and 14 miles southeast 
of Carthage, TN. Reservoir extends about 64 
miles up main stream and about 10 miles up Falling 
Water River and lies within DeKalb, Putnam, White, 
and Warren Counties, TN. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and power 
production, with a permanent pool for public use and 
conservation purposes. In addition to main dam structure, 
provision was made for a rolled-earth dike to 
close a saddle in reservoir rim near damsite. For further 
details, see page 1099 of 1962 Annual Report. 
Actual cost of project including $8,940,642 code 710 
funds is $53,412,022. 
Local cooperation. None required on completed 
project. Recreation development subject to certain conditions 
of non-Federal cost-sharing under Federal 
Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structure and its 
appurtenance maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy generated 
(792,306,800 kw-hr) was made available through 
Department of the Interior to Tennessee Valley 
Authority for distribution. Activities under reservoir 
management involved land management, public relations, 
and maintenance of public use facilities. 
14. DALE HOLLOW LAKE, OHIO 
RIVER BASIN, TN AND KY 
Location. Dam is on Obey River, 7.3 miles above its 
confluence with Cumberland River (mile 380.9) at 
Celina, TN. It is in Clay County, TN, and about 80 
miles northeast of Nashville, TN 28 miles north of 
Cookeville, TN, and 3 miles east of Celina, TN. 
Reservoir extends about 51 miles up main stream, 10 
miles up East Fork, and 6 miles up West Fork of Obey 
River, and lies within Cumberland and Clinton 
Counties, KY, and Clay, Pickett, Overton, and Fentress 
Counties, TN. 
Existing project. A concrete gravity-type dam, 
hydroelectric powerplant, and reservoir for primary 
purposes of flood control and power production with a 
permanent pool for public use an conservation purposes. 
See page 1096 of 1962 Annual Report for project 
details. Cost of project including $2,195,600 code 710 
funds and $150,000 non-Federal funds recreation facilities 
under the completed projects program is 
$28,317,746. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Total net energy generated 
(103,793,300 kw-hr) was made available through 
Department of the Interior to Tennessee Valley 
Authority for distribution. Activities under reservoir 
management program involved public relations, and 
management and maintenance of public-use facilities. 
A contract was awarded for construction of a comfort 
station at Pleasant Grove Beach. 
15. J.PERCY PRIEST DAM AND 
RESERVOIR, OHIO, RIVER 
BASIN, TN 
Location. Damsite is on Stones River, 6.8 miles 
above its confluence with Cumberland River (mile 
205.9); in Davidson County, TN.; and about 7 miles 
east of Nashville, TN. Reservoir extends southeasterly 
from dam about 32 miles along main stream, 10 miles 
up East Fork, 6.5 miles up West Fork, and for shorter 
distances up other tributaries of Stones River; and lies 
within Davidson, Rutherford, and Wilson Counties, 
TN. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control, power production 
and recreation. For further details see page 
703 of 1969 Annual Report. Cost of project including 
$3,260,400 under code 710 funds and $46,000 non- 
Federal funds for recreation facilities under the com- 
15-6

NASHVILLE, TN, DISTRICT 
pleted projects program is $56,914,039. 
Local cooperation. Recreation development subject 
to certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Total net energy 
generated (71,213,500 kw-hr) was made available 
through Department of the Interior to Tennessee 
Valley Authority for distribution. Activities under 
reservoir management program involved public relations, 
fish and wildlife management,and maintenance 
of public-use facilities. Paving of roads and parking 
areas were completed. 
16. LAUREL RIVER LAKE, OHIO 
RIVER BASIN, KY 
Location. Damsite is at mile 2.3 on Laurel River, a 
tributary of Cumberland River, in southcentral 
Kentucky. The two streams meet about 9 miles below 
Cumberland Falls, a prominent physiographic feature 
at head of Lake Cumberland which is formed by Wolf 
Creek Dam. Reservoir extends 19.2 miles upstream to 
site of Corbin, KY water-supply dam and lies within 
Laurel and Whitley Counties. 
Existing project. Project approved in general 
accordance with recommendations of House Document 
413, 86th Congress, by 1960 Flood Control Act, as 
amended by Public Law 88-253, was designed for purposes 
of flood control, power, and recreation as an integral 
unit of a coordinated plan for development of 
water resources of Cumberland River Basin. With the 
view of net gain in power potential on a system basis, 
the plan of improvement incorporated appropriate flood 
control storage in the proposed project and corresponding 
adjustment in operations of Wolf Creek Dam - Lake 
Cumberland for flood control and power, which in effect 
constituted a transfer of reservoir capacity without 
entailing a change in flood control benefits. Further 
detailed study giving full consideration to power capabilities 
and marketing arrangements indicated the 
advantage of maintaining present storage allocation at 
Wolf Creek and use of all available storage capacity of 
Laurel River Lake for power. The power plant is complete. 
Recreation was completed in FY 1986. Total 
cost is $56,741,232. 
Local cooperation. None required. 
Operations during fiscal year. New work: None. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Total net energy 
generated (58,196,000 kw-hr) was made available 
through Department of the Interior for distribution. 
17. WOLF CREEK DAM - LAKE 
CUMBERLAND, OHIO RIVER 
BASIN, KY 
Location. Wolf Creek Dam is on Cumberland River 
at mile 460.0 (above mouth) in Russell County, KY, 
about 10 miles southwest of Jamestown and 12 miles 
north of Albany, KY. Lake Cumberland extends 101 
miles up main stream, 48 miles up South Fork of 
Cumberland River, in Russell, Clinton, Wayne, 
Pulaski, McCreary, Laurel, and Whitley Counties, KY. 
Existing project. A combination earth and concrete 
gravity-type dam, hydroelectric powerplant, and reservoir 
for primary purposes of flood control and power 
production, with a permanent pool for public-use and 
conservation purposes. See page 1094 of 1962 Annual 
Report for project details. Cost of project is 
$188,267,195. This cost includes $3,259,3472 code 710 
funds, $880,000 non-Federal funds for recreation facilities 
under the completed program, and $104,999,237 
for major rehabilitation. 
Local cooperation. None required on completed 
project; future recreation development subject to certain 
conditions of non-Federal cost-sharing under 
Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. New work: 
Activity involving the integrity of the structure began 
in 1968 when a leak or seepage developed in the 
embankment. The major rehab embankment contract 
was physically completed in September 1982. 
Maintenance: Dam was operated and structures and 
appurtenances maintained as required. Operation of 
powerplant was continuous except for normal interruptions 
and necessary shutdowns for inspection and 
maintenance purposes. Major maintenance work items 
included switchyard repairs and replacement of intake 
gate cables. Total net energy generated (810,521,024 
kw-hr) was made available through Department of the 
Interior for distribution. Activities under reservoir 
management program involved land management 
activities, public relations, and maintenance of publicuse 
facilities. 
18. DAM SAFETY PROGRAM 
$549,503 was expended in FY 92 to design remedial 
measures for the main dam and increased spillway 
capacity at Center Hill Dam. Proposed modifications 
will prevent sudden failure of the dam in the event of 
catastrophic flooding on The Caney Fork and 
Cumberland Rivers. 
General Investigations 
19. SURVEYS 
Costs for this period were $1,131,078 for which 
$522,390 was for navigation $496,885 for flood damage 
prevention studies, $56,585 for special investigations, 
$30,413 for coordination studies with other agencies, 
$22,637 for interagency water resource development, 
and $2,168 for American Waterfowl Management Plan. 
15-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
20.COLLECTION AND STUDY OF vices to others, $19,723 for floodplain management ser- 
BASIC DATA vices, $4,688 for quick responses, and $9,988 for services 
to Jackson County, Sumner County and 
Costs for this period were $37,917 for technical ser- Hendersonville, TN. 
15-8

NASHVILLE, TN, DISTRICT 
TABLE 15-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project 
1. Cumberland River 
TN and KY 
2. Tennessee River, 
TN, AL, and KY 
3. Tenn.-Tombigbee 
Waterway, AL and MS 
5. Big South Fork National 
River and Rec. Area, 
KY and TN 
6. Martins Fork Lake, KY 
7. Middlesboro, Cumberland 
River Basin, KY 
8. Tug & Levisa Forks of 
the Big Sandy & Cumberland 
River, WV, VA and KY 
11. Cumberland, KY 
12. Center Hill Lake, 
Ohio River Basin, TN 
13. Dale Hollow Lake 
Ohio River Basin, 
TN and KY 
14. J. Percy Priest Dam and 
Reservoir, Ohio River 
Basin, TN 
15. Laurel RiverLake, 
Ohio River Basin, KY 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 89 FY90 FY 91 FY 92 Sep30,1992 
c
4
4 
15-9 
- - - - 320,252,240 1,2,3 
- - - - 320,252,240 1,2,3 
23,167,200 24,829,886 21,669,000 23,482,000 310,630,262 4 
23,648,733 24,363,546 22,003,257 22,865,774 309,337,254 5 
- - - - 16,251,428 6 
- - - - 16,251,428 6 
17,036,700 11,486,397 11,843,000 12,110,000 201,749,048 7 
17,383,402 11,567,723 11,929,274 11,407,949 200,840,863 8 
- - - - 400,000 
- - - - 400,000 
300,000 1,580,000 7,838,000 -500,000 749,813,050 
2,030,026 1,510,465 1,999,758 5,997,359 748,395,013 
7,969,000 300,000 0 0 112,123,920 9 
6,158,684 1,557,103 1,322,452 204,073 111,744,837 10 
- - - - 20,479,911 
- - - - 20,479,911 
598,500 591,840 542,000 575,000 6,829,340 
619,139 524,979 560,045 597,510 6,788,745 
- - - - 817,830 11 
- - - - 817,830 11 
66,000 159,322 -30,000 60,000 2,099,166 
61,772 47,039 72,515 69,123 2,087,053 
12,312,000 27,210,000 29,303,500 22,387,000 173,654,500 12 
17,561,130 20,104,313 24,997,924 22,129,538 159,307,524 13 
- - - - 66,642 
- - - - 66,642 
- - - - 53,412,022 14 
- - - - 53,412,022 15 
3,615,000 3,961,809 3,502,000 5,174,000 63,429,976 16 
3,750,028 3,951,194 3,446,491 4,570,127 62,690,549 17 
- - - - 28,317,746 18 
- - - - 28,317,746 19 
3,350,100 3,560,720 3,238,000 4,078,000 59,746,627 20 
3,413,865 3,430,747 3,251,233 4,017,319 59,467,427 21 
- - - - 56,914,039 22 
- - - - 56,914,039 23 
3,324,800 2,946,865 2,984,000 3,253,000 43,313,251 24 
3,341,459 3,116,459 2,865,245 3,241,627 43,138,444 25 
- - - - 56,741,232 
- - - - 56,741,232 
1,406,100 1,102,343 1,079,000 1,210,000 12,695,443 26 
1,422,959 1,068,074 1,076,441 1,212,062 12,636,477 26

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
TABLE 15-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 1992 
16. Wolf Creek Dam and New Work 
Lake Cumberland, Approp. - - - - 83,267,958 27 
Ohio River Basin, KY Cost - - - - 83,267,958 27 
Maint. 
Approp. 5,085,400 4,154,392 3,582,000 5,268,000 83,231,233 28 
Cost 5,271,224 4,003,632 3,703,287 4,910,334 82,775,462 29 
Rehab. 
Approp. - - - - 104,999,237 30 
Cost - - - - 104,999,237 30 
1. Includes $9,707,354 for abandoned and/or replaced works 
under the old Cumberland River system. (Amount includes 
$826,253 for new work and $3,266,706 for maintenance on previous 
project.) 
2. Includes $61,733 public works acceleration funds, and 
$102,966 contributed by the State of Kentucky and $6,750 contributed 
by metropolitan Nashville, TN. 
3. Includes $298,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
4. Includes $955,889 for special recreation use fees, and 
$2,236,657 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Act (PL 
98-8) of 1983. 
5. Includes $955,889 for special recreation use fees, and 
$2,236,657 for maintenance and operation of dams and other 
improvements of navigable waters, and $1,892,000 funds provided 
from the Productive Employment Appropriation Act (PL 
98-8) of 1983. 
6. Includes $14,007,193 for new work and $4,005,175 for 
maintenance on previous projects. 
7. Includes $495,763 for maintenance and operation of 
dams and other improvements of navigable waters, and 
$764,000 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
8. Includes $495,763 for maintenance and operation of 
dams and other improvements of navigable waters, and 
$764,000 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
9. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
10. Includes $300,000 funds provided from the Productive 
Employment Appropriation Act (PL 98-8) of 1983. 
11. Includes $33,876 Emergency Relief Funds. 
12. Includes $19,043,000 contributed by the State of 
Kentucky. 
13. Includes $18,626,638 contributed by the State of 
Kentucky. 
14. Includes $35,896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
15. Includes $35,896 public works acceleration funds, and 
$148,000 funds provided from the Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
16. Includes $292,280 funds for special recreation use fees, 
and $692,078 for maintenance and operation of dams and other 
improvements of navigable waters, and $91,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
17. Includes $292,280 funds for special recreation use fees, 
and $692,078 for maintenance and operation of dams and other 
improvements of navigable waters, and $91,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
18. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98- 
8) of 1983. 
19. Includes $51,789 public works funds and $150,000 contributed 
by the State of Tennessee, and $341,000 funds provided 
from the Productive Employment Appropriation Act (PL 98- 
8) of 1983. 
20. Includes $339,480 funds for special recreation use fees, 
and $692,078 for maintenance and operation of dams and other 
improvements of navigable waters, and $482,000 funds provided 
from the Productive Employment Appropriation Act (PL 98- 
8) of 1983. 
21. Includes $339,480 funds for special recreation use fees, 
and $692,078 for maintenance and operation of dams and other 
improvements of navigable waters, and $482,000 funds provided 
from the Productive Employment Appropriation Act (PL 98- 
8) of 1983. 
22. Includes $46,000 contributed by the Metropolitan 
Government, Nashville, TN. 
23. Includes $46,000 contributed by the Metropolitan 
Government, Nashville, TN. 
24. Includes $260,680 for special recreation use fees, and 
$635,378 for maintenance and operations of dams and other 
improvements of navigable waters, and $40,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
25. Includes $260,680 for special recreation use fees, and 
$635,378 for maintenance and operations of dams and other 
improvements of navigable waters, and $40,000 funds provided 
from the Productive Employment Appropriation Act (PL 98-8) 
of 1983. 
26. Includes $66,678 for maintenance and operations of 
dams and other improvements of navigable waters. 
27. Includes $96,920 public works acceleration funds, and 
$880,000 contributed by the State of Kentucky. 
28. Includes $82,048 public works acceleration funds, and 
$198,578 for maintenance and operation of dams and other 
improvements of navigable waters, and $278,780 funds for special 
recreation use fees, and $293,000 fund provided from the 
Productive Employment Appropriation Act (PL 98-8) of 1983. 
29. Includes $82,048 public works acceleration funds, and 
$198,578 for maintenance and operation of dams and other 
improvements of navigable waters, and $278,780 funds for special 
recreation use fees, and $293,000 funds provided from the 
Productive Employment Appropriation Act (PL 98-8) of 1983. 
30. Includes $203,757 for claim paid on initial construction 
of switchyard. 
15-10

NASHVILILE, TN, DISTRICT 
TABLE 15-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorized Project and Work Authorized Documents 
in Text Act 
CUMBERLAND RIVER BELOW NASHVILLE 
Jul 13, 1892 Provision made for lock A 
Jun 25, 1910 
Aug 30, 1935 
Jul 24, 1946 
Jun 19, 1952 
Sep. 3, 1954 
Provision made for locks B to F, and for dredging 
below lock F. 
Repairing dams A to F, inclusive, and surmounting 
same with movable crests 
Provision of 9-foot channel by the construction 
of 3 moderate height dams below Nashville, via, 
Kuttawa (Eureka), Dover, and Cheatham. 
Provision for hydroelectric power production as a 
function of Cheatham Dam. 
Construction of Barkley (Lower Cumberland) dam 
and reservoir project for navigation, flood control, 
hydroelectric power, and related purposes in lieu of 
Kuttawa and Dover navigation-only structures. 
Jul 14, 1960 Authorized change in alignment of Illinois Central 
Railroad. 
CUMBERLAND RIVER ABOVE NASHVILLE 
Aug. 5, 1886 Provision made for locks and dams; the Secretary of 
War to determine the final plan of improvement. 
Dimensions of the locks fixed in accordance with 
reports of Mar. 30, 1887, and Nov. 25, 1890. 
Mar 2, 1907 
Mar 2, 1919 
Jun 5, 1920 
Jul 3, 1930 
Jun 26, 19342 
Jul 24, 1946 
Oct 1, 1980 
Jul 3, 1930 
May 18, 1933 
Adoption of the report of the Board of Engineers, 
dated Feb. 26, 1906, limiting the lock and dam 
construction to locks and dams 1 to 7, and 21. 
Provision made for locks and dams 8 to 17. 
Authorizes work to proceed in Tennessee without 
waiting for action of local interests in Kentucky. 
Raising dam 1, 3 feet. 
Operation and care of locks and dams provided for 
with funds from War Department appropriations 
for rivers and harbors. 
Construction of Old Hickory, Cordell Hull (Carthage), 
and Celina Dams above Nashville for navigation and 
the development of power resources. 
Design and construct flood control measures for 
communities in the Upper Cumberland River basins. 
TENNESSEE RIVER 
Authorized navigable depth of 9 feet from mouth about 
650 miles to Knoxville, Tennessee to be obtained by 
construction of low dams. 
Authorized TVA to construct such dams in the 
Tennessee River as will provide a 9 foot channel. 
Annual Report, 1890, p. 2151 
H. Does. 758, 60th Cong., 1st sess.; 
and 1481, 60th Cong., 2d sess. 1 
H. Doc. 38, 73d Cong., 1st sess. 
H. Doc. 761, 79th Cong., 
2d sess. 
S. Doc 81, 83d Cong., 
2d sess. 
H. Doc. 56, 86th Cong., 
2d sess. 
Annual Report 1884, p. 1663 
Annual Report 1888, p. 
1622, and Annual Report 
1892, p. 1933. 
H. Doc. 699, 59th Cong., 1st sess. 
Rivers and Harbors Committee 
Doc. 10, 63d Cong., 2d sess. 
Rivers and Harbors Committee 
Doc. 26, 70th Cong., 2d sess. 
H. Doc. 761, 79th Cong., 2d sess. 
Sec. 202, PL 96-367 
H. Doc. 328, 71st Cong., 2d sess. 
15-11 
L

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
AUTHORIZING LEGISLATION 
See Section Date of 
in Text Authorized Act Project and Work Authorized Documents 
OHIO RIVER BASIN, NASHVILLE DISTRICT 
Construct levees, floodwalls, and drainage structures 
for protection of cities and towns in Ohio River Basin. 
Project to be selected by Chief of Engineers with 
approval of Secretary of War at a cost not to exceed 
$24,877,000 for construction. 
Approved general comprehensive plan for flood control 
and other purposes in Ohio River Basin as may be 
advisable at discretion of Secretary of War and Chief of 
Engineers and for initiation and partial accomplishment 
of plan, authorized $75million for reservoirs and 
$50,300,000 for local flood protection works. 
Flood Control Committee Doc. 1, 
75th Cong., 1st sess. 
Flood Control Committee Doc. 761, 
75th Cong., 3d sess. 
Aug 18, 1941 Additional $45 million for prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $70 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $125 million for further prosecution of 
comprehensive plan. 
Additional $100 million for prosecution of 
comprehensive plan for Ohio River Basin. 
H. Doc. 762, 77th Cong., 2d sess. 
H. Doc. 506, 78th Cong., 1st sess. 
Dec 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for flood control and other purposes 
in Ohio River Basin. 
Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Jun 19, 1970 Additional $69 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
Authorized Big South Fork National 
River and Recreation Area, KY and TN. 
Total area not to exceed 125,000 acres. 
Additional $120 million for further prosecution of 
comprehensive plan for Ohio River Basin. 
TENNESSEE-TOMBIG WATERWAY 
Jul 24, 1946 Construction of waterway to connect above rivers 
and provide a 9 foot channel and minimum bottom 
width of 170 feet in river and canal sections and 
150 feet in the divide cut, with locks 110 by 600 
feet clear inside dimensions. 
Subsequent studies determined most practical 
plan consists of channel with bottom width of 
300 feet (280 feet in divide cut), fewer locks with 
higher lifts resulted in reducing number of lifts from 
18 to 10 and reduced length from 260 to 253 miles. 
H. Doc. 6755, 89th Cong., 1st sess. 
S. 3710, 90th Cong., 2d sess. 
H. R. 15166 91st Cong., 2d sess. 
H. R. 10203 93rd Cong. Water 
Resources Develop. Act of 1974 
Amended by PL 94-587, 94th Cong. 
H. R. 10203 93rd Cong. River 
Basin Monetary Authorization 
Act of 1974. 
H. Doc. 486, 79th Cong. 2d sess. 
Page 1343, Part I, FY 1968 
House Hearings 
1. Contains latest published maps. Included in Public 
Works Administration program Sept. 6, 1933. 
2. Permanent Appropriation Repeal Act. 
15-12 
TABLE 15-B 
(continued) 
9. 
Aug 28, 1937 
Jun 28, 1938 
Dec 22, 1944 
Jul 24, 1946 
May 17, 1950 
Jun 18, 1965 
Aug 13, 1968 
Mar 7, 1974 
Mar 7, 1974 
3.

NASHVILLE, TN, DISTRICT 
TABLE 15-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(All Projects not Specifically Identified in Text) 
For last Full Ca~t to Sept, 1992 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Caney Fork River, TN abandoned 1895 $ 27,828- 
Clinch River, TN and VA abandoned 1923 53,949 $ 7,873 
Duck River, TN abandoned 1887 13,000 - 
Elk River, AL and TN abandoned 1904 4,000- 
French Broad and Little 
Pigeon Rivers, TN abandoned 1931 249,605 33,554 
Holston River, TN abandoned 1911 5,714- 
Little Tennessee River, TN abandoned 1888 5,510- 
Obey River, TN abandoned 1887 11,500- 
Red River, TN abandoned 1884 5,000- 
South Fork of Cumberland 
River, KY abandoned 1892 11,967- 
TABLE 15-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects not Specifically Identified in Text) 
For last Full Cost to Sept, 1992 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Barbourville, KY completed 1963 $2,088,147 - 
Coal Creek and Tributaries 
(Lake City), TN completed 1962 460,134- 
Corbin (Lynn Camp Creek), 
KY completed 1969 567,703- 
Middlesboro (Yellow Creek), 
KY completed 1949 26,309- 
Paint Rock River, AL completed 1967 544,173- 
Pineville, KY completed 1963 1,679,126- 
1. Includes $9,950 contributed funds. 
15-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
TABLE 15-F OTHER AUTHORIZED MULTIPLE-PURPOSE PROJECTS 
(Including Power) 
For last Full Cost to Sept. 1992 
Report see Operation and 
Project Status Annual Report Construction Maintenance 
Barkley Dam and Lake beneficial use - $146,498,644 99,704,016 1 
Barkley, KY and TN 
Celina Dam, KY inactive 222,575 - 
Cheatham Lock and Dam, TN beneficial use - 31,682,762 75,924,974 
Cordell Hull Lock and Dam, TN beneficial use - 79,874,492 48,447,281 1 
Old Hickory Lock and Dam, TN beneficial use - 52,266,412 85,260,983 1 
1. Details given under "Cumberland River, TN and KY" See Table 15-H 
TABLE 15-G DEAUTHORIZED PROJECTS 
For last Full Federal Contributed 
Report see Funds Funds 
Project Annual Report Date and Authority Expended Expended 
Three Islands Reservoir, 1970 Authorized: FC Act 1938, PL 761, $111,855 
Ohio River Basin, TN 75 Cong., 3rd sess.; FC Act 1946, 
PL 525, 79th Cong., 2d sess. 
Deauthorized: 5 Aug 1977. 
Middlesboro, Yellow Creek - Authorized: FC Act, Dec 22, 
Bell County, KY 1944, PL 534, 78th Congress. - - 
Deauthorized: 17 Oct 1986. Water 
Resources Development Act of 1986, 
PL 99-662, 99th Cong., 2d sess. 
Cumberland River above - Authorized: River & Harbor Act, - - 
Nashville, TN Aug 5, 1886. 
Deauthorized: 17 Oct 1986. Water 
Resources Development Act of 1986, 
PL 99-662, 99th Cong., 2d sess. 
Hiwassee River, Polk and 1923 Authorized: River & Harbor Act 123,065- 
Bradley Counties, TN Aug 14, 1876. 
Deauthorized: 17 Oct 1986. Water 
Resources Development Act of 1986, 
PL 99-662, 99th Cong., 2d sess. 
Ressview Lake, Tennessee - Authorized: FC Act, Jan 28, 1938, 6,779- 
and Kentucky PL 761, 75th Congress. 
Deauthorized: 17 Oct 1986. Water 
Resources Development Act of 1986, 
PL 99-662, 99th Cong., 2d sess. 
15-14

NASHVILLE, TN, DISTRICT 
TABLE 15-H CUMBERLAND RIVER, TN AND KY: PRINCIPAL FEATURES 
(See Section 1 of Text) 
Dam and Reservoir Barkley Cheatham Old Hickory Cordell Hull Celina 
Nearest town 
Miles above mouth of rjver 
Lock dimensions (feet) 
Lift at normal pool levels (feet) 
Depths on guard-sills at 
minimum pool levels (feet) 
Character of foundation 
Dam: 
Type 
Height 
Length, exclusive of lock 
section (feet) 
Spillway: 
Gross length (feet) 
Net length opening (feet) 
Crest gates: 
Type 
Number 
Size (feet) 
Operating levels at dam 
(feet, mean sea level): 
Maximum regulated 
Normal operation: 
Full pool 
Minimum pool 
Minimum pool in advance 
of floods 
Reservoir area (acres) 
Reservoir capacity (acre-feet): 
Flood control 
Power drawdown 
Dead storage 
Total 
Canel: 
Length (mile) 
Bottom width (feet) 
Depth a minimum pool 
level (feet) 
Power development: 
Number of units 
Generator rating (kilowatts) 
Total installation (kilowatts) 
Percent of project completion 
Year9opened to navigation 
Cost 9 
Kuttawa, KY 
11 miles. 
30.6 
110 by 800 
57 
11, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthflll 
157 
9,959 
804 
660 
Tainter 
12 
55 by 60 
375 
359 
354 
346 
93,430 
1,213,0003, 4 
259,000 
610,000 
2,082,00 
1.75 
400 
11 
4
32,500 
130,000 
8
1964 
$146,5000,000 
Ashland City, 
TN, 9 miles 
148.7 
110 by 800 
26 
14, upper; 
17, lower 
Rock 
Concrete 
gravity 
75 
800 
480 
420 
Tainter 
7
60 by 27 
Old Hickory 
TN, 3 miles 
216.2 
84 by 400 
60 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
98 
3,6052 
325 
270 
Tainter 
6
45 by 41 
4503 
385 
382 
442 
7,450 27,450 
19,8007 
84,200 
104,000 
3
12,000 
36,000 
$213,000,000 
125,0005 
63,000 
357,000 
545,000 
4
25,000 
100,000 
8
1952 
$31,700,000 
Carthage, TN 
5 miles 
313.5 
84 by 400 
59 
14, upper; 
13, lower 
Rock 
Concrete 
gravity and 
earthfill 
93 
1,1382 
291 
225 
Tainter 
5
45 by 41 
5083 
508 
501 
499 
13,920 
85,6005,6 
20,500 
204,800 
310,900 
3
33,333 
100,000 
8
1973 
$79,874,500 
1. Clear width and length available for full width. 
2. Exclusive of lock section. 
3. Surcharge. 
4. Normal operation (elev. 375-359) during nonflood season; 
flood control allowance to be increased to 1,472,000 acre-feet 
(elev. 375-354) during season of major floodflows. 
5. Surcharge storage 
6. During flood season (elev. 508-501); minimum 51,800 
acre-feet (elev. 508-504) with normal operation during non-flood 
season. 
7. Daily pondage allowance; run-of-river project. 
8. Completed for full beneficial use. 
9. Includes recreation facility costs. 
15-15 
Celina, TN 
5 miles 
385.4 
Rock 
Concrete 
gravity and 
earthfill 
86 
2,298 
290 
250 
Tainter 
5
50 by 37 
5643 
560 
559 
559 
16,960 
55,9505 
14,700 
287,300 
357,950 
3
36,000 
108,000 
8
1954 
$52,266,000

REPORT OF THE SECRETARY OF THE ARMY OF CIVIL WORKS ACTIVITIES, FY 1992 
TABLE 15-I 
Project1 
Miles 
Above 
Mouth 
Miles from 
Nearest Town 
Kentucky 22.4 0.5 above Gilbertsville, K 
Pickwick Landing: 
Auxiliary lock 206.7 4.4 above Hamburg, TN 
Main lock 206.7 4.4 above Hamburg, TN 
Wilson: 
Auxiliary lock 259.4 2.9 above Florence, AL 
Main lock 259.4 2.9 above Florence, AL 
General Joe 
Wheeler: 
Auxiliary lock 274.9 18.4 above Florence, AL 
Main lock 274.9 18.4 above Florence, AL 
Guntersville: 
Auxiliary lock 
Main lock 
TENNESSEE RIVER 
(SEE SECTION 2 OF TEXT) 
Lock Dimension 
Length Minimum Depth 
Width Avail- Lift on Guard Sills 
of able for Year 
Cham- Full Nor- Maxi- Opened 
ber Width mal mum Lower Upper Character of Navi- 
(feet) (feet) (feet) (feet) (feet) (feet) Foundation gation 
Y 110 600 56 73.3 12.7 11.0 Limestone 1942 
110 600 55 63.0 12.8 10.0 Limestone 1937 
110 1000 55 63.0 12.8 10.0 Limestone 1984 
60 292 94 100.0 11.04 11.2 Limestone 1927 
300 
110 600 94 100.0 13.0 13.0 Limestone 1959 
60 400 
110 600 
349.0 9.1 below Guntersville, AL 60 360 
349.0 9.1 below Guntersville, AL 110 600 
Nickajack: 
Auxiliary lock 424.7 39.4 below Chattanooga, TN 110 600 
Main lock 424.7 39.4 below Chattanooga, TN 110 800 
Chickamauga 471.0 6.9 above Chattanooga, TN 60 360 
Watts Bar 529.9 6.8 above Breedenton, TN 60 360 
Fort Loudon 
Melton Hill 
(Clinch R.) 
602.3 1.3 above Lenoir City, TN 
23.1 22.1 above Kingston, TN 
48 51.5 13.2 14.7 Limestone 1934 
48 51.5 13.0 13.0 Limestone 1963 
39 45.0 11.8 13.0 Limestone 1937 
39 45.0 12.7 13.0 Limestone 1965 
39 41.0 13.0 13.0 Limestone 1967 
39 41.0 13.0 13.0 Limestone 
49 53.0 13.0 10.0 Limestone 1939 
58 70.0 11.8 12.0 Shale 1941 
60 360 72 80.0 11.8 12.0 Limestone 1943 
75 400 54 60.0 13.0 13.0 Limestone 1963 
Kind 
of Dam 
Fixed 
Cost of 
Type of Each Lock 
Construction and Dam 
Concrete and 2 
earthfill 
Fixed Concrete and 
earthfill 
Fixed Concrete and 3 
earthfill 
Fixed Concrete and $46,973,5405 
earthfill7 
Fixed 
Fixed 
Concrete and 1,796,2956 
earthfill 
Concrete and 7 
earthfill 
Fixed 
Fixed Concrete and 
earthfill 
Fixed 
Fixed 
Fixed 
Fixed 
Concrete 
Concrete 
Concrete and 
earthfill 
Fixed Concrete and 
earthfill 
Fixed Concrete 
3&7 
7
7
7 
3&7 
3 
Cong., 1st 
15-16 
1. H. Doc. 328, 71 Cong., 2d sess, contains table, pp. 98 and 99, giving pertinent information concerning low dams contemplated 5. Constructed by the Corps under authority of sec. 124, National Defense Act of June 3, 1916, (H. Doc. 1262, 64th 
under 1930 project. Annual Report for 1938, pp. 1218 and 1219, contains similar information pertaining to low dams in addition to sess.). Actual cost of lock and dam. 
exiting locks and dams, including those constructed or under construction by Tennessee Valley Authority. 6. Actual cost of lock only as constructed by the Corps; dams constructed by Tennessee Valey Authority. 
2. Lock and dam constructed by Tennessee Valley Authority. 7. Constructed by Tennessee Valley Authority. 
3. Lock and dam constructed by Tennessee Valley Authority. Design for lock prepared with Corps forces and funds. 
4. Tailwater in canal; flight of 2 locks.

NASHVILLE, TN, DISTRICT 
TABLE 15-4 TENNESSEE RIVER, TN, AL, AND KY 
TOTAL COST OF EXISTING PROJECTS TO SEP 30, 1992 
(See Section 2 of Text) 
Channel Operation & 
Funds New Work Maintenance Maintenance Total 
Regular $2,244,236 $10,747,026 $186,076,992 $199,068,254 1,2 
Maintenance - - 11,665 11,665 
Increase of compen- 5 - 5 
sation, rivers and 
harbors, 1919 
(certified claims) 
Total $2,244,236 $10,747,031 $186,088,657 $199,079,9241,2 
1. In addition, surplus property valued at $54,336 was ation and care of works of improvement under provisions of 
transferred from the project without reimbursement. Excludes appropriation for such purposes. 
$4,005,175 expended betweenl890 and June 30, 1935, on oper- 2. Excludes $14,007,192 previous construction cost. 
TABLE 15-K OHIO RIVER BASIN (NASHVILLE DISTRICT) 
LOCAL PROTECTION PROJECTS 
Type of Estimated Cost 
Location Protection Federal Non-Federal Total 
Cumberland, KY Channel Improvement 520,000 240,000 760,0001 
1. Deferred 
TABLE 15-L RESERVOIRS 
Tributary Basin and Reservoir 
Center Hill Lake, TN 
Dale Hollow Lake, TN and KY 
J. Percy Priest Dam & Reservoir, TN 
Laurel River Lake, KY 
Martins Fork Lake, KY 
1. Details of this project are in individual report. 
2. Formerly Stewarts Ferry Reservoir. 
Total 
Federal 
Steam Cost 
Caney Fork River $53,412,0221 
Obey River 28,167,7461 
Stones River 56,868,0391,2 
Laurel River 56,741,232 3 
Martins Fork 20,479,911 
3. See "Other authorized multiple-purpose projects." 
15-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES, FY 1992 
TABLE 15-M INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 10 of Text) 
Project Date of Inspection 
Barbourville, KY Apr 1992 and Oct 1992 
Corbin, KY Apr 1992 and Oct 1992 
Lake City, TN Apr 1992 and Oct 1992 
Middlesboro, KY (Yellow Creek) Apr 1992 and Oct 1992 
Middlesboro, KY (Diversion Canal) Apr 1992 and Oct 1992 
Paint Rock River, AL 
Pineville, KY Apr 1992 and Oct 1992 
Spring City, TN May 1992 and Oct 1992 
Sunbright, TN (Whiteoak Creek) Apr 1992 and Oct 1992 
TABLE 15-N FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 205 
P.L. 858, 80th Congress, as amended 
Project FY 92 Cost 
Browns Creek, Nashville, TN $ 2,485 
Dry Creek, Goodlettsbille, TN 21,256 
Lytle Creek, Murfreesboro, TN 4,300 
Rock Creek, Unicoi County, TN 9,379 
Whites and Ewing Creeks, TN 477 
Doe & Watanga River, Elizabethtown, TN 4,196 
Little Harpeth River, Brentwood, TN 7,618 
Beaver Dam Creek, Damascus, VA 16,943 
East Fork of Clarks River, KY 6,505 
Harpeth River, Williamson Co., TN 10,013 
Martins Creek, Unicoi Co., TN 5,466 
Piney Creek, Spring City, TN 206 
Reedy Creek, Sullivan County, TN 31,926 
Caney Fork River, Carthage, TN 1,158 
Gibson Creek, TN 51 
Emergency Bank Protection (Section 14 of the 1946 
Flood Control Act, P.L 526, 79th Congress 
Project FY 92 Cost 
Emory River, Harriman, TN $ 3,672 
Sheffield Water Intake, AL 37,944 
Duck River, Hickman Co., TN 23,138 
Pond Creek,Cheatham Co., TN - 1,533 
Whitesburg Br., Morgan County, AL 2,872 
Cumberland River Metro Nashville Landfill 45,397 
Duck Island Water Refuge, Lake Barkley, KY 902 
Fair Grounds Park, Clarksville, TN 1,266 
Savannah City Park, TN 11,270 
Sequoyah Hills Park, Knoxville, TN 61,060 
Tennessee River, Chattanooga, TN 8,061 
McGregor Park, Montgomery Co., TN 19,628 
South HolstonRiver, Kingsport, TN 20,572 
15-18

LOUISVILLE, KY DISTRICT* 
This district comprises a portion of southwestern 
Ohio, west central Kentucky, a small portion of north 
central Tennessee, Indiana except northern part, and 
southeastern Illinois except Cairo-Mounds-Mound City 
area, all included in drainage basin of Ohio River and its 
tributaries (exclusive of Tennessee and Cumberland 
Rivers) from mile 438 (below Pittsburgh) immediately 
upstream from Foster, KY., to mouth. 
All cost and financial statements for projects are 
listed at the end of this chapter. All other tables are 
referenced in text and also appear at the end of this 
chapter. 
IMPROVEMENTS 
Navigation - Channels and Habors Page 
1. Open Channel Work, Licking River, KY..... 16-2 
Navigation - Locks and Dams 
2. Construction of Locks and Dams, Ohio 
R iver ........................................................... 16-2 
3. Green and Barran Rivers, KY: .................... 16-2 
4. Kentucky River, KY .................................... 16-2 
5. Open Channel Work, Ohio River ................ 16-3 
6. Other Authorized Navigation Projects ........ 16-3 
7. Navigation Work Under Special 
Authorization.............................................. 16-3 
Flood Control - Local Protection 
8. Evansville, IN ............................................. 16-3 
9. M ill Creek, OH ........................................... 16-4 
10. Salyersville, KY ........................................... 16-4 
11. Southwestern Jefferson County, KY.......... 16-4 
Flood Control - Reservoirs 
12. Barren River Lake, KY ............................... 16-5 
13. Brookville Lake, KY .................................... 16-5 
14. Buckhorn Lake, KY ..................................... 16-6 
15. Caesar Creek Lake, OH .............................. 16-6 
16. Cagles Mill Lake, IN ................................... 16-6 
17. Carr Fork Lake, KY .................................... 16-7 
18. Cave Run Lake, KY ..................................... 16-7 
19. Cecil M. Harden Lake, IN ........................... 16-7 
20. Clarence J. Brown Dam & Reservoir, OH.. 16-8 
21. Green River Lake, KY .................................. 16-8 
22. Huntington Lake, IN ................................... 16-8 
23. Mississinewa Lake, IN ............................... 16-9 
24. Monroe Lake, IN ......................................... 16-9 
25. Nolin Lake, KY ........................................... 16-9 
26. Ohio River Basin (Louisville District)....... 16-10 
27. Patoka Lake, IN ....................................... 16-10 
28. Rough River Lake and Channel 
Improvement, KY ...................................... 16-10 
Page 
29. Salamonie Lake, IN .................................... 16-11 
30. Taylorsville Lake, KY ............................... 16-11 
31. W abash River Basin .................................. 16-12 
32. West Fork of Mill Creek Lake, OH ........... 16-12 
33. William H. Harsha Lake, OH ................... 16-12 
34. Inspection of Completed 
Flood Control Projects ............................... 16-13 
35. Other Authorized Flood Control Projects .. 16-13 
36. Flood Control Works Under Special 
Authorization ............................................ 16-13 
General Investigations 
37. Surveys ...................................................... 16-13 
38. Collection and Study of Basic Data............ 16-13 
39. Precontruction Engineering and Design ... 16-13 
Tables 
Table 16-A Cost and Financial Statement .... 16-14 
Table 16-B Authorizing Legislation .............. 16-19 
Table 16-C Other Authorized Navigation 
Projects ....................................... 16-22 
Table 16-D Not applicable 
Table 16-E Other Authorized Flood Control 
Projects ...................................... 16-23 
Table 16-F Not applicable 
Table 16-G Deauthorized Projects ................ 16-26 
Table 16-H Principal Features of Green 
and Barren Rivers and Kentucky 
River Navigation Systems .......... 16-28 
Table 16-I Ohio River Basin - Total Cost 
of Basin Plan .............................. 16-29 
Table 16-J Wabash River Basin - Total 
Cost of Basin Plan ..................... 16-33 
Table 16-K Inspection of Completed Flood 
Control Projects ......................... 16-34 
Table 16-L Flood Control Work Under Special 
Authorization .............................. 16-37 
16-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation - Channels and Harbors 
1. OPEN CHANNEL WORK, LICKING 
RIVER, KY 
Location. The Licking River originates in southeast 
ern Kentucky and flows generally northwesterly to its 
confluence with the Ohio River at Covington, KY, mile 
470.2 below Pittsburgh, PA. The Licking River Basin 
includes the drainage area of the Licking River, and all 
other left bank tributaries of the Ohio River from 
Markland Locks and Dam (Ohio River Mile 531.5) 
upstream to Meldahl Locks and Dam (Ohio River Mile 
436.2). 
Existing project. There are no locks and dams on 
the Licking River. However, a navigable depth of 9 feet 
is maintained up to mile 7.0 on the Licking River. 
Local cooperation. None. 
Terminal facilities. Facilities for bulk commodities, 
oil products, and coal are considered adequate for 
existing traffic. 
Operations during fiscal year. New Work: None. 
Maintenance: Dredging was done where required to 
provide an adequate and dependable channel. 
Navigation - Locks and Dams 
2. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
For report on this improvement, see the heading 
under Ohio River. 
3. GREEN AND BARREN RIVERS, KY 
Location. Green River rises in Casey County,'KY, 
flows northwesterly 370 miles, and empties into Ohio 
River about 8 miles above Evansville, IN. Barren River 
rises in Monroe County, KY, flows northwesterly 130 
miles, and empties into Green River 1/2 mile above Lock 
4 and 149.5 miles above mouth of Green River. 
Existing project. Six locks and dams on Green 
River and one on Barren River to give, with channel 
work in pools of dams, a navigable depth of 9 feet and 
width of 200 feet from Ohio River to mile 103 Green 
River, 3.2 miles upstream from Paradise, KY; a navigable 
depth of 5.5 feet from mile 103 Green River to 
Mammoth Cave, KY, mile 197.8 Green River, and from 
mouth of Barren River mile 149.5 Green River, to 
Bowling Green, KY, mile 30.1, Barren River. 
Fluctuations in stage vary considerably at different 
locks. At Lock 3, Green River, ordinary high stages are 
from 12 to 15 feet above pool level, and at Lock 1, Barren 
River, from 7 to 10 feet above pool. Maximum stages of 
record are 34 feet above normal pool stage at Lock 3, 
Green River, and 29 feet at Lock 1, Barren River, 
obtained during floods of 1937 and 1913, respectively. 
(See Table 16-B for authorizing legislation and Table 16- 
H for principal features of the locks and dams.) 
Local cooperation. Fully complied with. 
Terminal facilities. Coal handling facilities located 
on the Green River between miles 81.5 and 108.1 near 
South Carrollton, Rockport, Paradise and Rochester, 
Kentucky, are considered adequate for existing commerce. 
Operations during fiscal year. New Work: None. 
Maintenance: Consisted of operation and maintenance 
of Locks and Dams 1 and 2, Green River, and removal 
of shoals, snags, and slides as required to maintain 
adequate channel for existing traffic between mouth of 
Green River and Dam 3 at mile 103 Green River. 
Routine maintenance was performed. 
Condition at end of fiscal year. Locks and Dams 1 
and 2, Green River, are in good condition. Lock and Dam 
3, Green River, and Lock and Dam 1, Barren River are 
in fair condition, and Lock 4, Green River, is in poor 
condition. Dam 4, Green River, failed May 24, 1965, 
when 120 feet washed out. Breach later widened, and 
repairs were deferred pending completion of survey 
report for navigation on Green River. Pool of Dam 1, 
Barren River, is maintained for local small boat use, but 
navigation through lock is suspended because of loss of 
lower pool. Operation activity was discontinued at Lock 
4 Green River and Lock and Dam 1 Barren River in 
January 1974 and at Lock 3, Green River in September 
1981. The residences and associated buildings and 
certain real estate at Lock 4 Green River and Lock and 
Dam 1 Barren River were disposed of in January 1975. 
Operation of Locks 5 and 6, Green River, was discontinued 
August 1951, as they were no longer used by river 
traffic. Controlling project depth in lower 103 miles of 
Green River is 9 feet; controlling depth from mile 103 to 
Bowling Green, KY, is 5.5 feet. Under permit issued by 
District Engineer on August 20, 1963, private interests 
dredged channel of Green River to extend 9-foot-depth 
to coal loading terminal at mile 108.1. Channel of Green 
River above Lock 3 is no longer maintained. 
4. KENTUCKY RIVER, KY 
Location. Formed by confluence of its North and 
Middle Forks about 4 miles east of Beattyville in east 
central Kentucky, (South Fork joins the main stream at 
that location), flows northwesterly and empties into 
Ohio River at Carrollton, KY, mile 545.8 below Pittsburgh, 
PA. 
Existing project. Provides for 14 locks and fixed 
dams to give, in connection with improvement of Ohio 
River, slack water navigation of 6 feet minimum depth 
from Ohio River to places on the three forks that are 
short distances above Beattyville, KY. Length of 6-footdepth 
project on main stem of Kentucky River is 258.6 
miles to confluence of Middle and North Forks. Cost of 
completed new work is $4,176,749. River frequently 
rises to 35 feet or higher. Extreme height at Lock 1 due 
to flood backwater from Ohio River is 60.3 feet, while 
extreme floods reach height of 47.6 feet at Lock 4, and 
35.5 feet at Lock 14. At some intermediate locks 
16-2

LOUISVILLE, KY, DISTRICT 
extreme height of floods exceeds 40 feet. All flood 
heights refer to upper pool gages. Existing project was 
adopted by 1879 River and Harbor Act (H. Ex. Doc. 47, 
45th Cong., 3d Sess., and Annual Report, 1879, p. 1398). 
Operation and care of locks and dams were included in 
project July 1, 1935, under provision of Permanent 
Appropriations Repeal Act of June 26,1934. (See Table 
16-H for principal features of the locks and dams.) 
On December 19, 1976, the lock operation schedules 
for commercial traffic and recreational craft on the 
Kentucky River System were reduced from continuous 
24-hour year-round operation to two-shift year-round 
operation of Locks 1 through 4, intermittent daily 
operation of Locks 5 through 10, and intermittent 
operation five days weekly of Locks 11 through 14. 
Since that time the hours for operation of Locks 5 
through 14 have been reduced in several increments. 
On October 1, 1981, Locks 5 through 14 were closed to 
traffic and placed in caretaker status. Locks 5, 6, 8, 9, 
and 10 were in operation for 15 weekends during fiscal 
year 1982 and was again closed at the end of this period. 
Locks 5 through 14 were leased to the State of Kentucky 
on May 21, 1985. The State of Kentucky operated these 
locks on weekends during the summer boating seasons 
through the Fiscal Year. The lease expired on October 
15, 1989, and Locks 5 through 14 were closed to traffic 
and placed in caretaker status. During the fiscal year 
Locks 1 through 4 continued a two-shift, year-round 
operation. 
Licenses. Federal Regulatory Commission License 
No. 539, to Kentucky Utilities Co., at Dam 7, Kentucky 
River, Annual charge, $4,400; total collections through 
September 30, 1989, $293,205. 
Terminal facilities. Facilities for bulk commodities 
and gasoline are considered adequate for existing traffic.
Operations during fiscal year. New Work: None. 
Maintenance: Consisted of operation and maintenance 
of Locks and Dams 1 through 4 and removal of shoals, 
snags, and slides as required to maintain an adequate 
channel for existing traffic between mouth of river and 
Dam 5 at mile 82.2 Kentucky River. Maintenance: 
Routine maintenance was performed. 
Condition at end of fiscal year. Existing project 
was completed in 1917. Work accomplished was rehabilitation 
of the five old State locks and dams and 
construction of new Locks and Dams 6 to 14 inclusive. 
Repairs have been made to deteriorated locks and dams 
as required to keep locks in operation and miaintain pool 
levels above dams except in extreme dry weather, when 
some pools fall below normal levels, details in Annual 
Reports for 1963, 1964, and 1965. Channel work was 
performed as required to provide for existing river 
traffic. Controlling navigable depth in length of river 
covered by existing project was 6 feet at end of fiscal 
year. 
5. OPEN CHANNEL WORK, OHIO 
RIVER 
For report on this improvement, see this heading 
under Ohio River. 
6. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 16-C. 
7. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
None. 
Flood Control - Local Protection 
8. EVANSVILLE, IN 
Location. In Vanderburgh County, IN,. on right 
bank of Ohio River, 792.2 miles below Pittsburgh, PA. 
(See U.S. Geological Survey map of Evansville-South, 
IN.) 
Existing project. Construction of a system of levees 
and concrete floodwalls, together with pumping plants 
for disposal of interior drainage, at Evansville. For 
further details, see Annual Report for 1962, page 1127. 
Project will provide protection for City of Evansville, IN, 
against Ohio River floods equal to 1937 flood (maximum 
of record), with a 3-foot freeboard. Estimated total cost 
ofnewwork(1992)is $44,654,000 Federal, and $5,500,000 
non-Federal. Existing project selected for construction 
under general authorization for Ohio River Basin 1937 
Flood Control Act. 
Local cooperation. Section 3 of Flood Control Act 
of June 22, 1936, as amended, applies. Fully complied 
with for Howell Unit 1 and Knight Township sections. 
Assurances for Pigeon Creek Section, Unit 2, Parts 1,2, 
and 3 have been furnished. 
Operations during fiscal year. New Work: Engineering 
and design studies continued. Construction of 
Pigeon Creek Section, Unit 2, was started in April 1974 
is complete except for Unit 2, Part 4. US Highway 41W 
Pump Plant construction contract advanced to 100 
percent completion. Contract for Diamond Avenue, 
North 1stAvenue, and Stringtown Road pumping plants 
and associated levee and floodwall advanced to 100 
percent completion. Maintenance: During the 1992 
flood season no benefits were accomplished. 
Condition at end of fiscal year. Knight Township, 
Howell, Unit 1 and Pigeon Creek, Unit 1, and Levee 
Unit 2 Part 3 Sections are complete. Howell Section, 
Unit 2, was reclassified from the "active" category to the 
"inactive" category July 7, 1977 based on studies that 
indicated this part of the project is not economically 
justified. Project is about 99 percent complete overall. 
16-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
9. MILL CREEK, OH 
Location. Project is located along the 18-mile length 
of Mill Creek and three-fourths mile length of East Fork 
in Hamilton County, OH. Lower Mill Creek is in the 
commercial and industrial heart of the Cincinnati metropolitan 
area in the southwestern portion of the State. 
Existing project. Eighteen miles of channel improvement, 
2 miles of levees, two pumping plants, 
modification of 29 bridges, and the addition of two 
pumping units at the present Mill Creek Barrier Dam, 
located near the Ohio River, are included in the project. 
Acquisition and development with appropriate landscaping 
of 620 acres along the creek will be provided for 
high-density urban oriented recreational use. 
Local cooperation. Section 3, Flood Control Act of 
1936 as amended, applies. In addition, local interests 
must provide without cost to the United States all 
modifications and relocations of buildings, utilities, 
street and foot bridges, sewers, and related and special 
facilities as necessary for construction of project; prevent 
encroachment on improved channels and on 
ponding areas which would impair capacities; at least 
annually inform interests affected as to degree of protection 
afforded by project, and provide guidance and 
leadership in preventing unwise and uneconomical 
development of flood plain areas by encouraging prudent 
use of floodproofing, land regulation planning, or 
other flood plain management techniques to reduce 
flood losses. Further, with respect to the recreational 
aspects of the project, local interests are required to 
furnish assurances that they will, if necessary, pay or 
contribute in kind, a portion of the cost of recreational 
facilities which, when added to the cost of recreation 
land, would amount to at least 50 percent of the total 
first cost of the recreation land and recreational facilities, 
and assure access to the recreation facilities to all 
on equal terms. An assurance agreement covering local 
cooperation requirements for the project consistent 
with Section 221 of the 1970 Flood Control Act and the 
Uniform Relocation Assistance and Real Property Acquisition 
Policies Act of 1970 was executed by the 
Millcreek Valley Conservancy District February 6, 1975, 
and for the Secretary of the Army March 28, 1975. A 
recreation cost sharing contract was executed by the 
Conservancy District February 25, 1975, and approved 
by the Secretary of the Army May 28, 1975. 
Operations during fiscal year. New Work: Construction 
of Section 1 advanced to 95 percent completion. 
At the direction of the Assistant Secretary of the 
Army for Civil Works, the Corps has initiated a study 
that will lead to a termination of further Federal activity 
on the project. This study will determine the best 
method to accomplish this termination. No further 
design or construction activities are anticipated. Maintenance: 
Flood damages estimated at $67,000 were 
prevented during the 1992 flood season. 
Condition at end of fiscal year. DM #1, Hydrology 
& Hydraulics; DM #2, Phase 1, Plan Formulation; DM 
#3, Phase II, General Project; DM #4, Construction 
Materials; DM #5, Railroad Relocations, and DM #6, 
Barrier Dam Pumps are complete. DM#7, Public Use is 
scheduled for completion in FY 1992. Construction 
channel and levee-Sections 2,3,4A, and 7A, Phase 1, are 
complete. Project is about 44 percent complete overall. 
10. SALYERSVILLE, KY 
Location. Project is located along the banks of the 
Licking River from approximately mile 269 and 271 in 
Magoffin County, Kentucky along the Mountain Parkway 
about 75 miles southeast of Lexington, Kentucky. 
Existing project. The most cost-effective and feasible 
plan to provide the authorized level of protection 
(1978 flood protection) is called the "Cut-Thru Plan" and 
includes two channel cut-thrus, a barrier dam at the 
upstream cut-thru, an 0.8 mile reach of channel improvement 
connecting the two cut-thrus, and 4.7 miles 
of clearing and snagging. Estimated total cost of new 
work (1992) is $10,400,000 of which $8,730,000 is Federal 
and $1,670,000 is non-Federal. 
Local cooperation. The recommended plan is 
strongly supported by the local sponsors, the City of 
Salyersville and Magoffin County. This support is 
documented in letter of intent dated April 26, 1988, 
which provided the initial financial capability statement 
and acknowledge receipt of the draft LCA. It is 
anticipated that the LCA will be executed in October 
1993, with physical construction initiating FY 1994. 
The local sponsor will be required to provide all lands, 
easement, and rights of way, pay a percentage of the 
costs allocated to flood control to bring the total non- 
Federal share of flood control cost to 25 percent, and 
bear all cost of operation, maintenance, repair, rehabilitation, 
and replacement of flood control facilities which 
is partially offset by a credit allowed based on the non- 
Federal sponsor's ability to pay, Section 103 (m) of the 
1986 Water Resource Development Act. 
Operations during the fiscal year. Engineering 
studies and the development of the LCA continue. 
Conditions at the end of fiscal year. Project is 
about 5 percent complete overall. 
11. SOUTHWESTERN JEFFERSON 
COUNTY, KY 
Location. In Jefferson County, KY, on left bank of 
Ohio River from mile 616 to 628.6. 
Existing project. Construction of 68,500 feet of 
levee, 1,550 feet of concrete wall, four pumping plants, 
and other necessary appurtenances. Project provides 
protection for 24,100 acres against Ohio River floods 
equal to 1937 flood of record with 3-foot freeboard. 
Estimated cost of new work (1992) is $69,776,183, of 
which $59,917,183 is Federal, and $9,859,000 is non- 
16-4

LOUISVILLE, KY, DISTRICT 
Federal. Project was authorized under Flood Control 
Act of August 1968. Recreation as a project purpose has 
been deferred until such time as a water quality problem 
on Pond Creek is corrected. 
Local cooperation. Section 3 Flood Control Act of 
1936 as amended applies. In addition, local interests 
agree to administer project land and water areas for 
recreation and fish and wildlife enhancement; and to 
pay, contribute in kind or repay (which may be through 
user fees) with interest, one-half of the separable first 
cost of the project allocated to recreation and fish and 
wildlife enhancement; and bear all costs of operation, 
maintenance and replacement of lands and facilities for 
recreation and fish and wildlife enhancement. Jefferson 
County Fiscal Court expressed intent to fulfill requirements 
by resolution dated April 4, 1967. Formal assurances 
oflocal cooperation for the flood protection portion 
of the project was executed by resolution of Jefferson 
County Fiscal Court, adopted September 17, 1971, and 
assurances for the recreation portion of the project were 
executed by similar resolution, adopted September 14, 
1971. Authorization-of-entry for levee and floodwall 
sections 1,2,3,4,4A,5 and Pond Creek Pump Plant have 
been furnished. Project was transferred to local interest 
on September 8, 1989. 
Operations during fiscal year. New Work: A 
contract to construct the Pond Creek Pumping Station 
was completed. A contract to make repairs to the levee 
was completed. A contract to repair deficient pumps and 
motors at the Pond Creek Pumping Station continued. 
Project is 99 percent complete overall. During the 1992 
flood season no benefits were accomplished. 
Flood Control - Reservoirs 
12. BARREN RIVER LAKE, KY 
Location. Dam is on Barren River, 79.5 miles above 
its confluence with Green River and 10 miles northeast 
of Scottsville, KY. At flood control pool reservoir extends 
upstream about 40 miles in Barren and Allen 
Counties, KY. (See U.S. Geological Survey map of 
Lucas, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rolled earth and rockfill, 146 
feet high and 3,970 feet long, with gate-controlled outlet 
works and uncontrolled open-cut spillway. Total storage 
capacity is 815,200 acre-feet (768,000 for flood 
control and 46,600 for water supply storage). For 
further details, see page 1125 ofAnnual Report for 1962. 
Cost of the completed project is $27,479,717 including 
$2,335,055 Federal funds and $108,418 non-Federal 
funds for construction of recreation facilities under the 
completed projects program. Project was authorized by 
Flood Control Act of 1938. 
Local cooperation. None required by authorizing 
act. Under provision of Water Supply Act of 1958, 
contract with City of Glasgow for water supply storage 
was approved by Secretary of Army on October 4, 1965. 
Terms require City to pay $23,433, which is project cost 
allocated to water storage plus capitalized prepayment 
of proportionate share of operation, maintenance, and 
major replacement costs. A contract, with the Common 
wealth of Kentucky for development of additional campsites, 
shoreline protection and breakwater extension at 
Barren River Lake State Park under the cost-sharing 
category of the completed projects program was approved 
by the Secretary of the Army November 4, 1977. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1992 flood season 
prevented damages of $2,002,000. 
Condition at end of fiscal year. Construction 
started in March 1960 and all major construction and 
relocation items were completedin October 1964. Project 
was placed in operation in March 1964. Land acquisition 
is complete. 
13. BROOKVILLE LAKE, IN 
Location. Damsite is on East Fork of Whitewater 
River, 2.4 miles above confluence with West Fork, and 
about 1-1/2 miles north of Brookville, Indiana. The 
reservoir lies in Franklin and Union Counties, Indiana. 
(See U.S. Geological Survey map of Brookville, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earthfill, 182 feet high and 
3,004 feet long, with gate-controlled outlet works, and 
uncontrolled open spillway. Total storage capacity is 
359,600 acre-feet (214,700 for flood control, 89,300 for 
water supply, and 35,500 for conservation). A minimum 
pool of 20,100 acre-feet is maintained. Cost of completed 
new work is $45,402,565 of which $37,905,073 is Federal 
cost and $7,497,492 is non-Federal contribution for 
water supply storage. Project was authorized by 1938 
Flood Control Act. 
Local cooperation. None required by authorizing 
act. Contract with State of Indiana for water supply 
storage under provisions of Water Supply Act of 1958 
was approved by Secretary of Army, August 5, 1965. 
Under terms of contract, State paid initial costs allocated 
to water supply feature of project plus capitalized 
prepayment of proportionate share of operation and 
maintenance costs. 
Operation during fiscal year. New work: None. 
Maintenance: A stilling basin floor contract to repair 
erosion problems and exposed rebar advanced to 100 
percent completion. A tailwater area contract to pave 2" 
bituminous concrete surface to eliminate cracks and 
potholes advanced to 100 percent completion. A control 
tower contract to replace roof because of interior leaks 
and damage was advanced to 100 percent completion. 
During 1992 flood season no benefits were accomplished. 
Routine maintenance was performed. 
Condition at end of fiscal year. Construction was 
started in November 1965 and project was placed in 
16-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
operation January 1974. Construction and land acquisition 
are complete. 
14. BUCKHORN LAKE, KY 
Location. Dam is on Middle Fork of Kentucky River, 
43.4 miles above mouth, and 0.5 mile upstream from 
Buckhorn, Perry County, KY. Reservoir extends upstream 
about 34 miles and lies in Leslie and Perry 
Counties, Kentucky. (See U.S. Geological Survey map 
of Buckhorn, KY.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill type, with gate 
controlled outletworks. Total storage capacityis 168,000 
acre-feet, of which 157,600 is for flood control. For 
further details, see page 1120 ofAnnual Report for 1962. 
Cost of completed new work is $11,766,206 including 
$386,707 for construction of recreation facilities under 
the completed projects program. Existing project was 
authorized by general authorization for Ohio River 
Basin in 1938 Flood Control Act. 
Local cooperation. Department of Parks of the 
Commonwealth of Kentucky has undertaken management 
of lands and recreational facilities in accordance 
with license granted by Secretary of the Army on June 
29, 1962. 
Operations during fiscal year. New work: None. 
Maintenance: A contract to make repairs to the stilling 
basin advanced to 100 percent completion. A contract to 
remove talus build-up in the spillway was awarded and 
advanced to 70 percent completion. Routine maintenance 
was performed. Operation for flood control during 
1992 flood season prevented damages of $1,205,000. 
Condition at end of fiscal year. Construction 
started in September 1956 and project was placed in 
operation in August 1960. All construction and land 
acquisition is complete. 
15. CAESAR CREEK LAKE, OH 
Location. Damsite is on Caesar Creek, about 3.0 
miles above its confluence with Little Miami River, in 
Warren County, OH, about 3.5 miles southeast of 
Waynesville, OH, and 10.5 miles northeast of Lebanon, 
OH. Reservoir lies in Warren, Clinton, and Green 
Counties, OH. (See U.S. Geological Survey map of 
Oregonia, OH.) 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It includes 
an earth and rockfill dam, four saddle dams, 
outlet works and an uncontrolled saddle spillway. Total 
storage capacity of reservoir is 242,200 acre-feet, of 
which 148,500 acre-feet is reserved for flood control 
storage. Estimated cost ofnew work (1992) is $62,893,882 
and $5,037,000 non-Federal reimbursement for water 
supply storage. Existing project was authorized by 
general authorization for Ohio River Basin in 1983 
Flood Control Act. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of 
storage for future municipal and industrial water supply 
uses. Contract with State of Ohio for water supply 
storage under provisions ofWater Supply Act of 1958, as 
amended, was approved by Secretary of the Army, May 
20, 1970. Under terms of contract, State will reimburse 
the Federal Government for costs allocated to water 
supply storage over a period not to exceed 50 years after 
use of this storage is initiated plus estimated annual 
amount for cost of operation, maintenance and major 
capital replacements required for the water supply 
facilities. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Flood damages estimated at $531,000 were prevented 
during the 1992 flood season. 
Condition at end of fiscal year. Construction was 
started in January 1968 and the project was placed in 
operation January 1978. Land acquisition is complete. 
All relocation and construction features are complete. 
Project is about 99 percent complete overall. 
16. CAGLES MILL LAKE, IN 
Location. Dam is on Mill Creek, 2.8 miles above its 
confluence with Eel River, in Putnam County, IN, and 
about 25 miles east of Terre Haute, IN. Reservoir 
extends upstream about 11 miles and is in Putnam and 
Owen Counties, IN. (See U.S. Geological Survey map of 
Poland, IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam is earth and rockfill embankment. 
Total storage capacity is 228,100 acre-feet, of which 
201,000 acre-feet are for flood control. For details, see 
Annual Report for 1962, page 1136. Estimated project 
cost ofnew work (1992) is $4,376,278 including $155,416 
Federal funds, $113,094 contributed funds for construction 
of recreation facilities under the completed 
projects program. Existing project was selected for 
construction under general authorization for Ohio River 
Basin in 1938 Flood Control Act. 
Local cooperation. None required. State of Indiana 
has undertaken development and management of 
recreation facilities for use of the public in reservoir 
area in accordance with license granted by Secretary of 
the Army on January 17, 1952. A contract with the 
Indiana Department of Natural Resources for expanding 
the boat ramp and parking area at Site 3, Lieber 
State Park, under the cost sharing category of the 
completed projects program was signed by the State of 
Indiana on August 26,1981 and approved bythe Deputy 
Chief of Engineers on March 26, 1982. 
Operations during fiscal year. New Work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1992 flood season 
prevented damages of $3,417,000. 
Condition at end of fiscal year. Construction 
started in July 1948 and completed in June 1953. 
Recreation facilities constructed under the cost sharing 
16-6

LOUISVILLE, KY, DISTRICT 
category of the completed projects program are completed 
except for administrative action to financially 
closeout the project. 
17. CARR FORK LAKE, KY 
Location. Damsite is 8.8 miles above mouth of Carr 
Fork, a tributary of North Fork of Kentucky River, 16 
miles upstream from Hazard, KY. The reservoir lies 
entirely within Knott County. (See U.S. Geological 
Survey maps of Carrie and Vicco, KY.) 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. Dam is 
rock and earth fill with impervious core, 720 feet long 
and 130 feet high, with uncontrolled open cut spillway 
through left abutment. Outlet works has two control 
gates and 8-foot diameter conduit to stilling basin. Total 
storage capacity is 47,700 acre-feet (31,600 for flood 
control and 4,300 for water quality control). A higher 
level seasonal pool for recreation is provided. Cost of 
completed work is $50,854,826 including $76,724 for 
recreation facilities under the completed projects program. 
Project was authorized by the 1962 Flood Control 
Act. 
Local cooperation. None required for reservoir 
project. Division of Flood Control and Water Usage of 
Commonwealth of Kentucky gave assurance that encroachments 
on downstream channel capacity will be 
prevented. 
Operations during fiscal year. New work: None. 
Maintenance: A contract to pave 2" bituminous concrete 
surface to eliminate cracks and potholes at Irishman 
Creek site was awarded and advanced to 99 percent 
complete. Routine maintenance was performed. Operation 
for flood control during the 1992 flood season 
prevented damages of $728,000. 
Condition at end offiscal year. Project was placed 
in operation January 1976. Construction started in 
January 1966 is complete. 
18. CAVE RUN LAKE, KY 
Location. Damsite is on Licking River, about 4 miles 
upstream from U.S. Highway 60 near Farmers, KY, and 
7 miles southwest of Morehead, KY. Reservoir will be in 
Rowan, Bath, Morgan, and Menifee Counties, KY. (See 
U.S. Geological Survey maps of Salt Lick and Morehead, 
KY.) 
Existing project. Plan provides for construction of 
a reservoir for flood control and allied purposes. Dam is 
rolled earthfill, with gate controlled outlet works and 
uncontrolled open spillway. Total storage capacity is 
614,700 acre-feet (438,500 for flood control and 28,300 
for water quality control). Estimated Federal cost of 
new work (1992) is $109,475,282 of which $35,213,000 
is U.S. Forest Service cost. Project was authorized by 
Flood Control Acts of June 22, 1936 and June 28, 1938. 
Local cooperation. None required. 
Operations during fiscal year. New work: An 
audit to close out the project continued. Maintenance: 
Routine maintenance was performed. Operation for 
flood control during the 1992 flood season prevented 
damages of $2,026,000. 
Condition at end of fiscal year. Project has been in 
operation since February 1974. Construction was started 
in June 1965 and is about 99 percent complete. Land 
acquisition is complete. All relocation and construction 
features are complete. Administrative procedures to 
financially closeout the project are in progress. 
19. CECIL M. HARDEN LAKE, IN 
Location. Dam is on Raccoon Creek, 32.4 miles 
above its confluence with Wabash River, and 25 miles 
northeast of Terre Haute, IN. At flood control pool, 
reservoir extends upstream about 15 miles in Parke and 
Putnam Counties, Indiana. (See U.S. Geological Survey 
Map of Mansfield, IN.) 
Existing project. A rolled earth dam and reservoir, 
for flood control and allied purposes. Total storage 
capacity is 132,800 acre-feet of which 116,600 acre-feet 
area for flood control. For details, see Annual Report for 
1962, page 1132. Cost of completed new work is 
$6,987,807 made up of $6,260,134 for the initial project 
and $373,678 Federal cost and $353,995 non-Federal 
contribution in kind for recreation facilities under the 
completed projects program. Project was selected for 
construction under general authorization for Ohio River 
Basin in 1938 Flood Control Act. Project name was 
changed from Mansfield Lake to Cecil M. Harden Lake 
by Public Law 93-521, December 14, 1974. 
Local cooperation. State of Indiana has undertaken 
management of lands and recreational facilities 
in accordance with license granted by Secretary of the 
Army on April 19, 1961. A contract with the Indiana 
Department of Natural Resources, approved by the 
Secretary of the Army in May 1974, provided for that 
agency to design and construct certain additional recreation 
facilities at Cecil M. Harden, Huntington, 
Mississinewa, Monroe and Salamonie Lakes under the 
cost sharing category of the completed projects program. 
Operation during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Flood damages of $962,000 were prevented during the 
1992 flood season. 
Condition at end of fiscal year. Construction 
started in October 1956 and all major items ofwork were 
completed December 1961. Land acquisition is complete. 
Project has been in operation since August 1960. 
Cost shared recreation facilities constructed by the 
State of Indiana under the completed projects program 
are completed. 
16-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
20. CLARENCE J. BROWN DAM & 
RESERVOIR, OH 
Location. Damsite is just east of Springfield, Clark 
County, OH, at mile 7.3 of Buck Creek, a tributary of 
Mad River. (See U. S. Geological Survey maps of New 
Moorefield and Springfield, OH.) 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, 6,620 feet 
long and 72 feet high, with gated outlet works and open 
cut spillway with concrete chute through right abutment. 
Total storage capacity of reservoir is 63,700 acrefeet 
(32,900 for flood control and 20,800 for water 
quality control). Federal cost of completed project is 
$22,083,660. Project was authorized by 1962 Flood 
Control Act. Project name was changed from Buck 
Creek Dam and Reservoir to Clarence J. Brown Dam 
and Reservoir by Public Law 90-46, July 4, 1967. 
Local cooperation. Assurances from City of Springfield, 
Springfield Conservancy District, and Clark 
County, Ohio, covering protection against detrimental 
channel encroachment below dam to mouth of Buck 
Creek, were accepted March 5, 1964. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Flood damages of $80,000 were prevented during the 
1992 flood season. 
Condition at end of fiscal year. Construction 
started in September 1966. Land acquisition and all 
major project features were completed in November 
1973. The project was placed in operation in January 
1974. 
21. GREEN RIVER LAKE, KY 
Location. Damsite is 305.7 miles above mouth of 
Green River in Taylor County, KY, about 8 miles south 
of Campbellsville. Reservoir lies in Taylor and Adair 
Counties. (See U.S. Geological Survey map of Cane 
Valley, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth and rockfill, 141 feet high 
and 2,350 feet long. Outlet works is slide gate-controlled 
and spillway open and uncontrolled. Total 
storage capacity is 723,200 acre-feet (560,600 for flood 
control and 64,500 for low-flow augmentation). Cost of 
completed new work is $33,462,330, consisting of 
$33,105,184 initial project funds, $40,001 for water 
supply, and $317,145 Federal funds for construction of 
recreation facilities under the completed projects program. 
Existing project was authorized under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. 
Local cooperation. None required by authorizing 
act. Taylor County, by lease approved by Secretary of 
Army February 15, 1968, undertook operation and 
maintenance of Smith Ridge public access area. In May 
1980, the lease was amended to turn back responsibility 
for maintenance and operation of 99 percent of the site 
to the Corps, with the County retaining responsibility 
for the marina area. Under provision of Water Supply 
Act of 1958, contract with City of Campbellsville for 
water supply storage was approved by Secretary of 
Army April 23, 1969. Terms require city to repay, with 
interest and annual charges for operation, maintenance 
and major replacement, the investment cost of $85,765 
allocated to its water supply storage space. Total 
payments receivedthrough fiscal year 1984 was $21,504. 
The Department of Parks of the Commonwealth of 
Kentucky, by lease approved by Secretary of Army, 
October 4, 1971, has undertaken the management ofthe 
Lone Valley public access area. 
Operations during fiscal year. New work: None. 
Maintenance: A contract to pave 2" bituminous concrete 
surface to eliminate cracks and potholes at Smith 
Ridge site was awarded and advanced to 99 percent 
complete. Routine maintenance was performed. Operation 
for flood control prevented damages estimated 
at $1,423,000 during 1992 flood season. 
Condition at end of fiscal year. Construction 
began in August 1965 and all major construction and 
relocation items were completed in 1972. Project has 
been in operation since February 1969. Project including 
all land acquisition complete in 1973. Construction 
of sanitary dump station for boats at Dam Site in 
conformance with EPA and State standards and rehabilitation 
of sewage treatment facilities, washhouses 
and restrooms at Smith Ridge site is complete. 
22. HUNTINGTON LAKE, IN 
Location. Damsite is on Wabash River, about 2 
miles from Huntington, IN, and 411.4 miles above 
mouth. Reservoir is in Huntington and Wells Counties, 
IN. (See U.S. Geological Survey maps of Majenica and 
Mt. Etna, IN.) 
Existing project. A reservoir for flood control and 
recreation. Dam consists of a rolled earth embankment 
4,700 feet long and 89 feet high, a concrete spillway and 
outlet section 155 feet long, and a concrete gravity 
section 310 feet long. Spillway is controlled by three 
gates, and outlet works by six sluices. Project also 
provides local flood protection for Markle, IN. Total 
storage capacity of reservoir is 153,100 acre-feet, of 
which 149,000 acre-feet is reserved for flood control 
storage. Estimated cost for new work (1992) is 
$19,622,509 made up of $19,273,252 Federal cost for the 
initial project and $193,903 non-Federal contributed 
funds for low flow augmentation storage, and $155,354 
non-Federal contribution in kind for ties recreation facili- under the completed projects program. Project was 
authorized by Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana has met this obligation. Contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army May 17, 1974, 
provided for that agency to design and construct certain 
16-8

LOUISVILLE, KY, DISTRICT 
additional recreational facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost shared category of the completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: A contract to pave 2" bituminous concrete 
surface to eliminate cracks and potholes at the 
Observation Mound site was advanced to 100 percent 
completion. Routine maintenance was performed. 
Operation for flood control prevented damages estimated 
at $2,990,000 during 1992 flood control season. 
Condition at end of fiscal year. Land acquisition 
and all major construction complete. Project was placed 
in operation January 9, 1969. Cost shared recreation 
facilities constructed by the State of Indiana under the 
completed projects program are complete. 
23. MISSISSINEWA LAKE, IN 
Location. Damsite is 7.1 miles above mouth of 
Mississinewa River, which flows into Wabash River 
about 2 miles upstream from Peru, IN. At flood control 
pool level, reservoir extends upstream about 28 miles, in 
Wabash, Grant, and Miami Counties, IN. (See U.S. 
Geological Survey map of Peoria, IN.) 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It includes 
an earthfill dam 137 feet high and 8,100 feet long, 
gate-controlled outlet works, and an uncontrolled open 
spillway through right abutment. Total storage capacity 
of reservoir is 368,400 acre-feet, of which 345,100 
acre-feet are reserved for flood control storage. Cost for 
completed new work is $24,381,129 made up of 
$23,793,145 Federal cost forthe initial project, $239,200 
non-Federal contributed funds for low flow augmentation 
storage. $174,392 Federal cost and $174,392 non- 
Federal contribution in kind for recreation facilities 
under the completed projects program. Project was 
authorized by the Flood Control Act of 1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to 1 percent of project first cost. 
State of Indiana assumed this obligation. A contract 
with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 1974, 
provided for that agency to design and construct certain 
additional recreation facilities at Cecil M. Harden, Huntington, 
Mississinewa, Monroe and Salamonie Lakes 
under the cost sharing category ofthe completed projects 
program. 
Operations during fiscal year. New work: None. 
Maintenance: A control tower contract to replace roof 
because of interior leaks and damage was advanced to 
100 percent completion. A contract was awarded at the 
end of the fiscal year to correct erosion problems in the 
stilling basin outlet channel. Routine maintenance was 
performed. Operation for flood control prevented damages 
of $8,103,000 during 1992 flood season. 
Condition at end of fiscal year. Construction and 
land acquisition is complete. Project was placed in 
operation in May 1968. Cost shared recreation facilities 
constructed by the State of Indiana under the completed 
projects program are complete. 
24. MONROE LAKE, IN 
Location. Dam is on Salt Creek, a tributary of White 
River, 25.9 miles above mouth, and 2 miles each of 
Harrodsburg, Monroe County, IN. At flood control pool 
level, reservoir will extend upstream 44 miles in Monroe, 
Brown, and Jackson Counties. (See U.S. Geological 
Survey map of Clear Creek, IN.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam is earth core and rock shell, with 
gate-controlled outlet works and uncontrolled open 
spillway. Total storage capacity is 441,000 acre-feet 
(258,800 for flood control and 159,900 for low flow 
augmentation.) Cost of completed new work is 
$16,570,774 consisting of $7,032,484 Federal funds, 
$7,797,604 non-Federal contributed funds for low-flow 
regulation storage and $870,343 Federal cost and 
$870,343 non-Federal contribution in kind for recreation 
facilities under the completed projects program. 
Project was authorized by 1958 Flood Control Act, 
modifying comprehensive plan for Ohio River Basin. 
Local cooperation. Section 3, 1944 Flood Control 
Act applies. Local interests must contribute 54.1 percent 
of project cost, this being the proportion allocated 
to low-flowregulation feature, plus a capitalized amount 
representing that part of average annual maintenance 
and operation cost allocated to low-flow regulation. 
State of Indiana assumed this cost sharing obligation. A 
contract with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 
1974, provided for that agency to design and construct 
certain additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe and Salamonie Lakes 
under the cost sharing category of the completed projects 
program. 
Operations during fiscal year. New work. None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control prevented damages of 
$167,000 during 1992 flood season. 
Condition at end of fiscal year. Project is complete 
and was placed in operation in February 1965. Cost 
shared recreation facilities constructed by the State of 
Indiana under the completed projects program are 
complete. 
25. NOLIN LAKE, KY 
Location. Dam is on Nolin River 7.8 miles above its 
confluence with Green River, about 70 air miles southwest 
of Louisville, KY. Reservoir extends upstream 
about 57 miles and is in Edmonson, Grayson, Hart, and 
Hardin Counties, KY. (See U.S. Geological Survey 
maps of Nolin Reservoir and Dickeys Mill, KY.) 
16-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. A reservoir for flood control and 
allied purposes. Dam is rockfill-earth core type with 
gate-controlled outlet works, and uncontrolled open 
spillway. Total storage capacity is 609,400 acre-feet, of 
which 545,600 acre-feet is for flood control. For further 
details of project, see Annual Report for 1962, page 
1124. Estimated Federal cost of new work (1992) is 
$17,193,381 including $2,594,377 for construction of 
recreation facilities. Project was selected for construction 
under general authorization for Ohio River Basin 
in 1938 Flood Control Act. 
Local cooperation. None required for authorized 
project. State of Kentucky contributed $18,195 for 
increased width of dam for public road. 
Operations during fiscal year. New work: None. 
Maintenance: Contracts to repair cathodic protection 
and to pave Wax and Dog Creek sites were awarded at 
the end of the fiscal year. Routine maintenance was 
performed. Operation for flood control during the 1992 
flood season prevented damages estimated $562,000. 
Condition at end of fiscal year. Construction 
started in January 1959. Project was completed and 
placed in operation in March 1963. 
26. OHIO RIVER BASIN 
(Louisville District) 
Location. Works covered by this project are a series 
of levees, floodwalls, channel improvements, and reservoirs 
in Ohio River Basin within Louisville District. 
Existing project. Individual projects considered in 
comprehensive plan within the Louisville District. (See 
Table 16-B for authorizing legislation and Table 16-I for 
cost and listing of projects in the basin plan.) 
Operations during fiscal year. No costs were 
incurred except for these projects for which individual 
reports are given. 
27. PATOKA LAKE, IN 
Location. Damsite is in Dubois County, IN, 118.3 
miles above mouth of Patoka River, and 50 miles westnorthwest 
of New Albany, IN. Reservoir extends into 
Dubois, Orange, and Crawford Counties. (See Geological 
Survey map of Cuzco, IN.) 
Existing project. Reservoir for flood control and 
allied purposes. Dam is earth and rock fill, 1,550 feet 
long and P5 feet high, with gate-controlled outlet works 
and uncontrolled open spillway. Total storage capacity 
is 301,600 acre-feet (121,000 for flood control and 167,500 
for water supply and water quality control). Estimated 
cost of new work (1992) is $73,664,159 of which 
$53,095,790 is Federal cost for other construction, and 
$20,568,369 is non-Federal contribution for water supply 
storage and recreation facilities. Project was authorized 
by 1965 Flood Control Act, and emergency measures 
and snagging and clearing the Patoka River 
downstream of Patoka Lake to ensure effective operation 
of the project for flood control was directed by 1981 
Appropriation Act for Energy and Water Development. 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated 
to water supply storage is initiated, presently estimated 
at 29.316 percent of the joint-use facilities cost, exclusive 
of interests, plus $287,000 for the cost of operating 
and maintaining water supply storage for a period of 50 
years, plus $42,000 for the cost of major capital replacements 
required for water supply storage space for a 
period of 50 years. Local interests are also required to 
pay, contribute in kind, or repay (which may be through 
user fees) with interest, one-half of the separable first 
cost of the project allocated to recreation. Present laws 
of the State of Indiana require that agency to make cash 
contributions during construction of the project. Local 
interests must also agree to prevent encroachments on 
channel of Patoka River from dam to mouth, and to pay 
allocated initial and annual maintenance and operation 
costs for water supply storage. Formal assurances of 
local cooperation, executed by the Indiana Natural 
Resources Commission, were accepted August 27, 1970. 
Contracts with State of Indiana for water supply and 
recreation were approved by the Secretary of the Army 
November 2, 1970. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control duringthe 1992 flood season 
prevented damage estimated at $233,000. 
Condition at end of fiscal year. Construction was 
started in July 1972. Engineering studies are complete. 
Real Estate relocation work is about 99 percent complete. 
All major features are complete. Permanent 
impoundment was started in February 1978 and the 
project was placed in operation about August 1980. The 
project is about 99 percent complete overall. 
28. ROUGH RIVER LAKE AND 
CHANNEL IMPROVEMENT, KY 
Location. Dam is on Rough River, 89.3 miles above 
its confluence with Green River, 160.3 miles above Ohio 
River, and about 60 miles southwest of Louisville, KY. 
Reservoir extends upstream about 30 miles and is in 
Breckinridge, Hardin, and Grayson Counties, KY. 
Channel improvement work is on Rough River, Barnett 
Creek, and West Fork of Barnett Creek. (See U.S. 
Geological Survey maps of McDaniels and Falls of 
Rough, KY.) 
Existing project. Reservoir is for flood control and 
allied purposes. Dam is rolled earthfill type, with gatecontrolled 
outlet works. Storage capacity is 334,380 
acre-feet, of which 314,210 acre-feet is for flood control. 
Project also includes channel clearing of lower Rough 
River, and channel improvement on Barnett Creek, a 
tributary of Rough River. For further details, see page 
1126 of Annual Report for 1962. Cost of completed new 
work is $10,643,001 including $890,008 Federal funds 
and $22,612 non-Federal funds for construction of rec- 
16-10

LOUISVILLE, KY, DISTRICT 
reation facilities under the completed projects program. 
Existing project was selected for construction under 
general authorization for Ohio River Basin in 1938 
Flood Control Act. Modification of previously approved 
plan to include channel improvement items was authorized 
by the 1944 Flood Control Act. 
Local cooperation. None required for construction 
of reservoir unit. Provisions of Section 3, Flood Control 
Act of 1936, are applicable to channel improvements. 
Assurances were obtained from Ohio County for channel 
improvement. Department of Parks, Commonwealth 
of Kentucky, has undertaken management of 
certain lands and recreation facilities in accordance 
with license granted by Secretary of the Army on 
August 18,1961. A contract with the Commonwealth of 
Kentucky to improve and pave road at the Below Dam 
Area - State Park under the cost sharing category of the 
completed projects program was approved by the Secretary 
of the Army November 4, 1977. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during the 1992 flood season 
prevented damages estimated at $1,161,000. 
Condition at end of fiscal year. Construction 
started in November 1955 and reservoir was placed in 
operation in June 1959. Land acquisition and all major 
items of construction and relocation are complete. 
29. SALAMONIE LAKE, IN 
Location. Damsite is 3.1 miles above mouth of 
Salamonie River which enters Wabash River about 6 
miles upstream from Wabash, IN. Reservoir extends 
upstream about 27 miles at flood control pool and lies in 
Wabash and Huntington Counties, IN. (See U.S. Geological 
Survey maps of Lagro and Majenica, IN.) 
Existing project. Provides for construction of a 
reservoir for flood control and allied purposes. It includes 
an earthfill dam with a maximum height of 133 
feet and length of 6,100 feet, gate-controlled outlet 
works with a 16-foot-diameter conduit and an uncontrolled 
open spillway through right abutment. Total 
storage capacity of reservoir is 263,600 acre-feet, of 
which 250,500 acre-feet is for flood control storage. 
Estimated project cost for new work (1992)is $17,046,151 
made up of $16,244,356 Federal cost for the initial 
project and $170,697 non-Federal contributed funds for 
low-flow augmentation storage and $315,549 Federal 
cost and $315,549 non-Federal contribution in kind for 
recreation facilities under the completed projects program. 
Project was authorized by Flood Control Act of 
1958. 
Local cooperation. Local interests must contribute 
in cash an amount equal to one percent of project first 
cost. State of Indiana assumed this obligation. A 
contract with the Indiana Department of Natural Resources, 
approved by the Secretary of the Army in May 
1974, provided for that agency to design and construct 
certain additional recreation facilities at Cecil M. Harden, 
Huntington, Mississinewa, Monroe, and Salamonie 
Lakes under the cost sharing category of the completed 
projects program. 
Operations during fiscal year. New work: None. 
Maintenance: A contract to replace the emergency 
generator system located at the spillway structure was 
awarded at the end of the fiscal year. A contract to 
replace to control tower roof was awarded and advanced 
to 99 percent completion. Routine maintenance was 
performed. During the 1992 flood season, operation for 
flood control prevented damages of $3,565,000. 
Condition at end of fiscal year. Land acquisition 
and all major construction and relocation contracts are 
complete. Reservoir was placed in operation- in spring 
1967. Cost shared recreation facilities constructed by 
the State of Indiana under the completed projects program 
are complete. 
30. TAYLORSVILLE LAKE, KY 
Location. Damsite is in Spencer County, KY, 60.0 
miles above the confluence of Salt River and Ohio River, 
4 river miles above Taylorsville and 36.9 river miles 
above Shepherdsville, KY. (See U.S. Geological Survey 
map of Taylorsville, KY.) 
Existing project. A reservoir for flood control and 
allied purposes. Dam will be an earth and rock fill 
structure, 164 feet high and 1,280 feet long. Outlet 
works will be slide gate controlled and spillway will be 
uncontrolled open cut. Total storage capacity will be 
291,670 acre-feet (211,230 for flood control, winter 
months), and 52,245 for water quality and fish and 
wildlife. Estimated cost of new work (1992) is 
$122,090,000 made up of $92,980,000 Federal cost for 
the initial project and $17,020,000 non-Federal contributed 
funds for initial recreation facilities and $6,045,000 
Federal cost and $6,045,000 non-Federal contributed 
funds for recreation facilities under the completed 
projects program. Project was authorized by 1966 Flood 
Control Act. 
Local cooperation. Local interests must agree to 
administer project land and water areas for recreation; 
pay, contribute in kind, or repay (which may be through 
user fees) with interest one-half of the separable first 
costs of the project allocated to recreation; bear all costs 
of operation, maintenance, and replacement of recreation 
lands and facilities. Local interests must also 
agree to prevent encroachments on flow-carrying capacities 
of stream channels below the reservoir to the 
extent needed to provide reasonably effective reservoir 
operation. Commonwealth of Kentucky has indicated 
intent to fulfill requirements for recreation cost sharing 
and has assumed responsibility for channel encroachments 
and pollution control. The Commonwealth furnished 
assurance agreements covering prevention of 
encroachment on capacity of stream channels in April 
16-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
and May 1973 and executed the recreation cost sharing 
contract in April 1973. On April 2, 1980, the U.S. 
District Court for the Western District of Kentucky 
ruled that the 1973 recreation cost sharing contract 
between the Commonwealth and the United States that 
provided for repayment after completion was invalid 
under the Kentucky Constitution which prohibits one 
General Assembly from obligating future appropriations 
that would be binding on a subsequent legislature. 
In response to the Court's ruling, the Commonwealth 
and the United States entered into a new contract 
providing for cash contributions. Contract was approved 
by the Secretary of the Army June 11, 1980. The 
contract was found to be valid and enforceable by the 
Court July 14, 1980. 
Operations during fiscal year. New work: 
Contractor's claim for damages to the Dam and Spillway 
construction contract were settled. Maintenance: A 
contract to reseal and restrip the shop and office parking 
lots and access roads was awarded and advanced to 
99 percent complete. Routine maintenance was performed. 
During the 1992 flood season operation for 
flood control prevented damages of $1,351,000. 
Condition at end of fiscal year. Engineering and 
design studies are complete except for design of a 
comfort station. Land acquisition is 100 percent complete. 
Construction was started in June 1974. All major 
construction items are complete except recreation facilities. 
The dam gates were closed in January 1983 for 
permanent impoundment. Dedication ceremony was 
May 28, 1983. The project is about 99 percent complete 
overall. 
31. WABASH RIVER BASIN 
Location. Works covered by this project are located 
in the Wabash River Basin, a drainage area of 33,100 
square miles, covering parts of Indiana, Illinois, and 
Ohio. 
Existing project. One local protection project and 
five reservoir projects were authorized for this basin 
plan. (See Table 16-B for authorizing legislation and 
Table 16-J for project list and total cost of basin plan.) 
32. WEST FORK OF MILL CREEK 
LAKE, OH 
Location. Dam is on West Fork of Mill Creek 6.5 miles 
above its junction with Mill Creek and 2 miles northeast 
of Mount Health, OH, and 10 miles north of downtown 
Cincinnati. Reservoir extends upstream about 3 miles 
and is in Hamilton County, OH. (See U. S. Geological 
Survey map of Glendale, OH.) 
Existing project. An earth embankment dam and 
a reservoir for flood control, recreation, and reduction of 
pumping requirements at Mill Creek barrier dam in 
Cincinnati. Total storage capacity of reservoir is 11,300 
acre-feet, of which 9,850 acre-feet is for flood control. 
For further details, see page 1119 of Annual Report for 
1962. Cost of completed new work is $4,722,463 made 
up of $3,092,941 Federal cost for the initial project, 
$520,800 non-Federal cost for sewer relocation and 
dam, $50,000 non-Federal contributed funds in fulfillment 
of project authorization and $529,361 Federal cost 
and $529,361 non-Federal contribution in kind for recreation 
facilities under the completed projects program. 
Existing project selected for construction under additional 
authorization for Ohio River Basin in 1946 Flood 
Control Act. 
Local cooperation. Local interests were to release 
necessary land under their control and give assurance 
that future channel encroachment below damsite would 
be prevented. For enlargement of reservoir to include a 
conservation pool, local interests would contribute onehalf 
additional cost of such pool, including one-half cost 
of relocation of sanitary sewer, and agree to hold the 
United States free from damages resulting from its 
provision. Board of County Commissioners of Hamilton 
County, Ohio, adopted a resolution October 8, 1947, 
signifying willingness to fulfill requirements including 
provision of conservation pool. Assurances were executed 
on same date. A contract with the United States 
for relocation of sanitary sewer outside reservoir area in 
order to include conservation pool in project was accepted 
by Hamilton County, in which the United States 
paid one-half cost of such relocation work. Hamilton 
County Commissioners furnished $50,000, required as 
a local contribution toward additional cost of providing 
conservation pool. Hamilton County Park District has 
undertaken development and management of recreation 
facilities in reservoir area for use of the public in 
accordance with the license granted by Secretary of the 
Army on October 31, 1951. Contract for cost shared 
recreation development under the completed works 
program was executed by the Board of Park Commissioners, 
Hamilton County Park District, Ohio, in September 
1975 and approved by the Chief of Engineers in 
December 1975. 
Operations during fiscal year. New work: None. 
Maintenance: Routine maintenance was performed. 
Operation for flood control during 1992 flood season 
prevented damages estimated at $2,000. 
Condition at end of fiscal year. Construction 
started in March 1949 and reservoir was placed in 
operation in December 1952. Project is complete. Cost 
shared recreation development under the completed 
projects program is complete. 
33. WILLIAM H. HARSHA LAKE, OH 
Location. Damsite is on East Fork of Little Miami 
River between Batavia and Williamsburg, OH, about 
6.0 miles above Batavia and 32.6 miles above mouth of 
the Little Miami River. Entire project lies in Clermont 
County, OH. (See U.S. Geological Survey map of 
Batavia,OH.) 
16-12

LOUISVILLE, KY, DISTRICT 
Existing project. A reservoir for flood control and 
allied purposes. It includes an earthfill dam, outlet 
works, an uncontrolled saddle spillway, and a dike to 
close a saddle north of spillway. Total storage capacity 
of reservoir is 294,800 acre-feet, of which 210,600 acrefeet 
is reserved for flood control storage. Cost of completenew 
workis $52,023,157 and a estimated $3,485,840 
non-Federal reimbursement for water supply storage. 
Existing project was authorized by general authorization 
for Ohio River Basin in 1938 Flood Control Act. 
Project name was changed from East Fork Lake to 
William H. Harsha Lake effective January 4, 1981, by 
Public Law 96-383, October 6, 1980. 
Local cooperation. None required. However, the 
State of Ohio requested inclusion in the project of 
storage for future municipal and industrial water supply 
uses. Contract with State of Ohio for water supply 
storage under provisions ofWater SupplyAct of 1958, as 
amended, was approved by Secretary of the Army, May 
20, 1970. Under terms of contract, State will reimburse 
the Federal Government for costs allocated to water 
supply storage over a period not to exceed 50 years after 
use of this storage is initiated plus estimated annual 
amount for cost of operation, maintenance, and major 
capital replacements required for the water supply 
facilities. 
Operations during fiscal year. New work: None. 
Maintenance: A contract to replace the control tower 
roof because of interior leaks advanced to 100 percent 
completion. Routine maintenance was performed. 
Operation for flood control during 1992 flood season 
prevented damages estimated at $366,000. 
Condition at end of fiscal year. Construction was 
started in May 1970. Project is complete and reservoir 
was placed in operation in February 1978. 
34. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to maintain and operate local 
protection projects in accordance with regulations prescribed 
by Secretary of the Army. Inspections were 
made to determine extent of compliance and to advise 
interests as necessary to measures required to correct 
deficiencies. (See Table 16-K for the latest dates of 
inspection performed on the local protection projects, 
channel improvements, and bank revetments). 
Fiscal year costs were $169,529. Total costs to September 
30, 1992, were $3,589,035. 
35. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 16-E. 
36. FLOOD CONTROL WORKS UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities pursuant to Public 
Law 99, 84th Congress, and antecedent legislation. 
Costs for fiscal year were $304,589 for disaster preparedness. 
In addition, $211,735 was expended on 
emergency repairs on one federally-authorized and 
completion ofthree non-federal flood protection projects 
damaged during flooding events. 
Small navigation activities pursuant to Section 107, 
1960 River and Harbor and Flood Control Act, Public 
Law 86-645, 86th Congress, as amended. Costs for fiscal 
year were $19,324 for two reconnaissance studies. 
See Table 16-L. 
Flood control activities pursuant to Section 205, 1948 
Flood Control Act, Public Law 858, 80th Congress, as 
amended. Costs for fiscal year were $151,451 for preparation 
of thirteen Reconnaissance Studies, $99,999 for 
five Detailed Project Reports, $9,634 for Plans and 
Specifications on one project and $89,662 for two construction 
projects. 
See Table 16-L. 
Snagging and clearing navigable streams and tributaries 
in interest of flood control (Section 208, 1954 
Flood Control Act, Public Law 780, 83rd Congress). 
Costs for fiscal year were $1,932 for construction on one 
project. 
See Table 16-L. 
Emergency bank protection (Section 14, 1946 Flood 
Control Act, Public Law 526, 79th Congress. Costs for 
fiscal year were $197,788 for preparation of three Reconnaissance 
Studies, eight Detailed Project Reports, 
start of Plans and Specifications on four projects, and 
construction of one projects. 
See Table 16-L. 
General Investigations 
37. SURVEYS 
Fiscal year costs were $3,666,800 consisting of 
$1,204,148 for three Navigation Studies at Green River, 
Ky, Louisville, Ky, and Uniontown, KY, IN; $2,242,348 
for thirteen Flood Damage Prevention Studies; $84,919 
for Special Investigations; $22,463 for Review of Federal 
Energy Regulatory Commission Licenses; $31,880 
for Intra-Agency Water Resource Development; $5,350 
for a North American Waterfowl Management Plan; 
$9,018 for Coordination with other Federal Agencies; 
and $66,674 for Planning Assistance to States. 
38. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $126,778 for Floor Plain Management 
Services and $6,248 for Hydrologic Studies. 
39. PRECONSTRUCTION 
ENGINEERING AND DESIGN 
Fiscal year costs were $1,941,399 consisting of 
$1,093,802 for navigation studies at Olmsted, IL and 
Louisville, KY; $847,597 for local protection studies at 
Fairfield, OH, Frankfort, KY, and Hazard, KY Holes 
Creek, OH; and West Fork Mill Creek, OH. 
16-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-A 
See 
Section 
in Text 
COST AND FINANCIAL STATEMENT 
Project Funding 1989 1990 1991 
Total to 
1992 Sept. 30, 1992 
Navigation - Channels and Harbors 
1 Open Channel Work, New Work 
Licking River Approp. $ 
Cost 
Maint. 
Approp. 
Cost 
Navigation - Locks and Dams 
3 Green and Barren New Work 
Rivers, KY Approp. 
Cost 
Maint. 
Approp. 
Cost 
- $ 
12,000 
12,000 
12,311 
12,311 
13,000 14,700 
13,000 14,700 
1,440,900 1,466,171 1,152,000 1,088,367 
1,297,228 1,544,346 1,105,338 1,246,490 
83,011 
83,011 
13,808,222 1 
13,808,222 1 
35,566,750 2,3 
35,555,381 
4 Kentucky River, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Flood Control, Local Protection 
8 Evansville, IN New Work 
Approp. 
Cost 
-- - - 4,176,749 
-- - - 4,176,749 
1,565,200 1,100,852 931,500 725,500 56,017,341 4. 
1,479,695 1,231,846 800,341 873,149 56,000,709 4ss 
-- - - 556,956 
-- - 556,956 
5,002,000 6,523,000 2,263,000 305,000 43,494,043 6 
2,864,214 5,382,915 4,938,572 652,605 43,069,238 ' 
9 Mill Creek, OH 
10 Salyersville, KY 
11 Southwestern 
Jefferson County, 
KY 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Flood Control - Reservoirs 
12 Barren River Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
10,865,000 2,456,000 6,140,000 6,396,000 
6,350,916 8,129,179 8,933,891 6,715,773 
-_ 400,000 280,000 
- - 197,484 317,890 
1,777,000 570,000 1,350,000 1,300,000 
1,739,587 943,109 540,274 2,293,877 
1,269,700 
1,424,926 
1,150,838 
1,118,208 
1,295,000 
1,263,645 
1,284,757 
1,302,491 
93,844,742 
93,748,114 
680,000 
515,374 
59,917,183 
59,532,423 
27,479,717 8 
27,479,717 8 
21,623,721 q io, 1 
21,521,914 9, o1101, 
16-14

LOUISVILLE, KY, DISTRICT 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding 1989 1990 1991 1992 Sept. 30, 1992 
13 Brookville Lake, IN New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
14 Buckhorn Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
15 Caesar Creek Lake, OH New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
16 Cagles Mill Lake, IN New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
17 Carr Fork Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
18 Cave Run Lake, KY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
19 Cecil M. Hardin Lake, New Work 
IN Approp. 
Cost 
Maint. 
Approp. 
Cost 
- $ - $ (13,815) - $ 45,402,56512 
- - - - 45,402,565 12 
533,100 504,108 682,000 599,227 7,024,524 
567,567 453,527 514,106 815,199 7,007,324 
- - - - 11,766,206 13 
- - - - 11,766,206 13 
675,100 874,833 703,000 972,780 13,404,323 14 
724,265 801,127 738,810 966,271 13,329,205 14 
(3,725) 
650,900 
666,348 
- - - 62,893,882 
(1,549) (2,229) - 62,881,010 
734,271 644,000 736,474 8,153,408 
710,737 669,046 713,160 8,098,805 
- - - 4,376,278 15 
- - - - 4,369,997 16 
343,900 398,111 459,000 400,200 7,358,017 
377,443 397,439 421,615 440,382 7,350,848 
772 2,638 
882,400 912,067 
915,926 880,911 
17,417 
517,800 
515,762 
17,879 
566,087 
557,766 
- - 50,854,826 17 
15 - 50,854,826 17 
859,000 928,118 11,881,785 18 
789,973 998,174 11,831,201 18 
- - 74,262,282 
33,794 7,885 74,259,541 
507,000 612,188 7,549,921 
528,062 616,762 7,536,660 
- - - 6,987,807 19 
- - - - 6,987,807 19 
683,800 510,044 656,000 609,800 9,183,840 
706,592 528,545 648,587 633,745 9,179,275 
16-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
Project 
20 Clarence J. Brown 
Dam & Reservoir, 
OH 
21 Green River Lake, KY 
22 Huntington Lake, IN 
23 Mississinewa Lake, IN 
24 Monroe Lake, IN 
25 Nolin Lake, KY 
26 Ohio River Basin 
Louisville District 
Funding 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
1989 1990 1991 
$ - $ 
Total to 
1992 Sept. 30, 1992 
- $ 22,083,660 
- 22,083,660 
425,400 460,567 488,000 425,331 6,287,645 
449,834 445,390 477,582 448,396 6,268,952 
-- - - 33,462,330 20 
-- - - 33,462,330 20 
962,397 1,069,965 1,171,000 1,105,383 17,939,294 21 
1,018,736 998,018 1,127,966 1,161,530 17,847,465 21 
19,622,509 22 
13 19,621,777 23 
453,100 486,128 441,100 445,848 7,986,388 
495,401 477,245 435,631 462,027 7,968,349 
- - - - 24,381,129 24 
- - - - 24,379,800 25 
446,700 453,811 430,000 635,777 7,275,293 
456,896 408,100 436,517 644,908 7,233,373 
- - - - 16,570,774 26 
- - - - 16,570,774 26 
629,700 608,143 837,000 688,250 8,772,418 27 
624,204 585,632 843,847 662,999 8,713,061 27 
- - 1,836 - 
1,291,100 1,244,859 1,466,000 1,614,400 
1,297,261 1,207,782 1,402,619 1,678,145 
17,193,381 28 
17,193,277 29 
25,269,574 30 
25,159,150 30 
1,526,142 
1,526,142 
16-16 
See 
Section 
in Text

LOUISVILLE, KY, DISTRICT 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
Total to 
1992 Sept. 30,1992 
27 Patoka Lake, IN 
27 Rough River Lake & 
Channel Improvment, 
KY 
28 Salamonie Lake, IN 
29 Taylorsville Lake, KY 
31 West Fork of Mill 
Creek Lake, OH 
32 William H. Harsha 
Lake, OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,480 
431,600 
432,867 
1,575,300 
1,602,455 
"- - 73,664,159 31 
- - 148 73,316,892 32 
469,885 436,000 398,861 4,950,377 
449,317 419,228 443,840 4,932,929 
1,170,502 1,650,000 1,090,955 
1,177,644 1,489,621 1,284,058 
10,643,001 33 
10,643,001 3 
23,313,667 34 
23,263,394 34 
- - - - 17,046,151 3 
S. . 17,039,321 36 
408,768 415,839 424,000 497,300 7,180,320 
421,912 404,919 414,595 515,770 7,160,780 
486,000 497,000 
904,636 526,392 
500 160,000 86,754,809 37 
331,528 634,371 86,482,765 38 
626,800 712,271 578,000 664,903 5,332,874 
626,165 681,542 606,915 672,843 5,300,435 
- - 4,722,463 39 
- - - - 4,722,463 3s 
280,000 379,747 271,000 292,967 5,671,403 
305,440 339,931 289,742 311,550 5,652,440 
- - 52,023,157 40 
885 " " " 52,023,157 40 
453,335 521,836 492,000 592,500 6,126,437 
473,034 503,165 473,388 604,544 6,082,859 
1 Includes $85,000 public works funds 
2 Includes $2,000 emergency relief funds, $204,444 
"maintenance and operation of dams and improvements of 
navigable waters" and $3,842,667 expended from 1888 to 30 
June 1936, for operation and care from permanent indefinite 
appropriation. 
3 Includes $725,715 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
4 Includes $316,871 under"maintenance and operation 
of dams and other improvements of navigable waters", and 
$6,405,372 expended between July 5, 1885 and June 30,1937 
on operation andcare from permanentindefinite appropriation. 
6 Includes $149,700 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
6 Includes $11,812 emergency relief funds and $63,187 
contributed funds. 
7 Includes $11,812 emergency relief funds and $63,169 
contributed funds. 
8 Includes $2,224,948 Code 711 funds, $110,107 Code 
713 Federal funds and $108,418 Code 713 non-Federal funds. 
16-17 
See 
Section 
in Text Project Funding 1989 1990 1991 I

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-A 
CONTINUED 
COST AND FINANCIAL STATEMENT 
9 Includes $100,000 Supplemental funds. 
10 Includes $326,900 Special Recreation Use Fees. 
11 Includes $365,925 "maintenance & operation of dams 
anid other improvements of navigable water". 
12 Includes $7,497,492 contributed funds and $100,706 
Code 711 funds. 
13 Includes $61,451 public work acceleraton executive 
1963 funds, $143,088 Code 711 funds, and$243,619 Code 712 
funds. 
14 Includes $52,240 Special Recreation Use Fees. 
15 Includes $35,814 Code 711 funds, $119,602 Code 713 
funds, and $113,094 contributed funds. 
16 Includes $35,814 Code 711 funds, $119,602 Code 713 
funds, and $106,813 contributed funds. 
17 Includes $76,724 Code 711 funds. 
18 Includes $51,854 Special Recreation Use Fees. 
19 Includes $19,683 Code 711 funds, $353,995 Code 713 
funds, & $353,995 non-Federal contributions in kind for 
recreation facilities. 
20 Includes $133,413 Code 711 funds, $183,732 Code 713 
funds, and $40,001 contributed funds. 
21 Includes $114,280 Special Recreation Use Fees and 
$365,925 under "maintenance and operation of dams and 
other improvements of navigable water". 
22 Includes $155,354 Code 713 funds and $193,903 
contributed funds. 
23 Includes $155,354 Code 713 funds and $193,812 
contributed funds. 
24 Includes $215,000 Code 711 funds, $174,392 Code 713 
funds, $239,200 contributed funds and $174,392 non-Federal 
contribution in kind for recreational facilities. 
25 Includes $215,000 Code 711 funds, $174,392 Code 713 
funds, $237,871 contributed funds and $174,392 non-Federal 
contribution in kind for recreational facilities. 
26 Includes $1,185 Code 711 funds, $869,158 Code 713 
funds, $7,797,604contributedfunds and $870,343 non-Federal 
contribution in kind for recreational facilities. 
27 Includes $54,460 from Productive Employment 
Appropriation Act (PL 98-8) of 1983. 
28 Includes $21,897 public works acceleration executive 
1963 funds and $2,594,377 Code 711 funds. 
29 Includes $21,897 public works acceleration executive 
1963 funds and $2,592,274 Code 711 funds. 
30 Includes $204,920 Special Recreation Use Fees, $52,000 
Supplement Funds, and $292,925 "maintenance and operation 
of dams and other improvements of navigable water". 
31 Includes $20,568,369 contributed funds. 
32 Includes $20,221,129 contributed funds. 
33 Includes $196,306 public works acceleration executive 
1963 funds, $867,396 Code 711 funds, $22,612 Code 713 funds, 
and $22,612 contributed funds. 
34 Includes $236,640 Special Recreation Use Fees and 
$365,925 under "maintenance and operation of dams and 
other improvements of navigable water". 
35 Includes $315,549 Code 713 funds, $170,697 contributed 
funds and $315,549 non-Federal contribution in kind for 
recreation facilities. 
36 Includes $315,549 Code 713 funds, $163,867 contributed 
funds and $315,549 non-Federal contribution in kind for 
recreation facilities. 
37 Includes $4,128,831 contributed funds. 
38 Includes $4,006,484 contributed funds. 
39 Includes $529,361 Code 713 funds, $50,000 contributed 
funds, $529,361 non-Federal contribution inkindfor recreation 
facilities, and $520,800 non-Federal cost for sewer relocation 
and dam. 
40 Includes $58,571 for preconstruction planning, 
engineering and design completed before FY 1953. 
16-18

LOUISVILLE, KY, DISTRICT 
TABLE 16-B AUTHORIZING LEGISLATION 
Work Authorized 
Aug 11, 1888 
Mar 3, 18931 
Jul 13, 1892 
Jul 13, 1902 
Mar 3, 19052 
Mar 3, 1909 
Jul 3, 19302 
Jun 26, 1934 3 
Aug 30, 1935 2 
Sep 3, 1954 
Aug 28, 1937 
Jun 28, 1938 
Aug 18, 1941 
Dec 22, 1944 
Jul 24, 1946 
May 17, 1950 
Jul 3, 1958 
GREEN AND BARREN RIVERS, KY (See Section 3 of Text) 
Purchase of original improvement H. Doc 111, 49th Cong., 2d 
Sess., Ann. Rept. 1887, p.1903 
Construction of Lock 2, Green River Annual Report, 1891, p. 2439 
Construction of Lock 5, Green River 
Construction of Lock 6, Green River Annual Report, 1891, p. 2478 
Appropriated $5,000 for continuing improvements of Green River 
above mouth of Big Barren River, with provision "That the Secretary 
of War may, in his discretion, expend such portion of said amount as 
may be necessary for removal of snags in Nolin River." 
Construct new Lock 1 and new Lock and Dam 2, Green River S. Doc. 82, 83d Cong., 2d Sess. 
Construct new locks at Dam 5, Green River and Dam 1, Rivers and Harbors Committee 
Barren River; modification of Dam 5, Green River, Doc. 2, 71st Cong., 1st Sess.,and 
widens bends in Bear Creek, KY H. Doc. 685, 69th Cong., 2d Sess. 
Operation and care of locks and dams with War 
Department Appropriations for rivers and harbors 
Improvement of Nolin River H.D. 480, 72d Cong., 2d Sess. 
Channel enlargement of lower 103 miles of Green River revocation of S.D. 82, 83d Congress, 2d Sess. 
authorities for improvement of Bear Creek and Nolin River 
OHIO RIVER BASIN (Louisville Dist.) (See Section 26 of Text) 
Construct levee, floodwalls, and drainage structures for protection Flood Control Committee 
of cities and towns in Ohio River Basin, projects to be selected Document 1, 75th Congress, 
by Chief of Engineers with approval of Secretary of War, at a cost 1st Session 
not to exceed $24,877,000 for construction 
Approved general comprehensive plan for flood control and other purposes Flood Control Committee 
in Ohio River Basin as may be advisable in discretion of Secretary Document 1, 75th Congress, 
of War and Chief of Engineers, and for initiation and partial 1st Session 
accomplishment of plan, authorized $75 million for reservoirs and $50.3 
million for local protection works, individual projects to be selected and 
approved by Chief of Engineers, subject to provision that authorization 
shall include diversion of Cache River above Cairo, Illinois, and protection 
of area north of Cairo drainage district by levees at an estimated cost 
of $2 million 
Additional $45 million for further prosecution of comprehensive plan 
for Ohio River Basin 
Additional $70 million for further prosecution of comprehensive plan H. Doc. 504, 78th Congress, 
for Ohio River Basin, including plan of improvement for flood control 2d Session 
and other purposes in Kentucky River Basin 
Flood protection works at Taylorsville, KY at an estimated cost of $129,350 S.D. 105, 78th Cong., 1st Sess. 
Channel improvement of lower Rough River and Barnett Creek at an H.D. 535, 78th Congress 
estimated cost of $360,000 2d Session 
Additional $125 million for further prosecution of comprehensive plan, H.D. 197, 80th Congress 
including plan of improvement for flood control in Wabash River 1st Session 
Basin, Illinois, and Indiana, at an estimated cost of $9,629,000 
Also, West Fork of Mill Creek at an estimated cost of $1,527,000. H.D. 198, 80th Cong., 1st Sess. 
Additional $100 million for prosecution of comprehensive plan for Ohio 
River Basin, including necessary bank stabilization measures at New 
Harmony Bridge, Indiana, at an estimated cost of $500,000. 
Flood control Act of 1958 modified comprehensive plan to provide for H.D. 192, 85th Congress, 
Monroe Reservoir on Salt Creek, White River Basin, Indiana, at an 1st Session 
estimated cost to the United States of $4,350,000; cost to local 
interests, $5,141,000. 
16-19 
Acts Documents

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-B 
CONTINUED 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct 23, 1962 Flood Control Act of 1962 deleted Jessamine Creek Reservoir on 
Kentucky River, Kentucky, from comprehensive plan for 
Ohio River Basin 
Dec 30, 1963 Additional $150 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Jun 18, 1965 Additional $89 million for further prosecution of 
comprehensive plan for Ohio River Basin 
May 12, 1967 Additional $38 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Aug 13, 1968 Additional $35 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Jun 19, 1970 Additional $69 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Mar 7, 1974 Additional $120 million for further prosecution of 
comprehensive plan for Ohio River Basin 
Fifty-four local protection projects and one reservoir project in 
comprehensive plan for Ohio River Basin were deauthorized 
August 5, 1977, under Section 12, Water Resources 
Development Act of 1974 
Two additional local protection projects in comprehensive plan for 
Ohio River Basin were deauthorized November 6, 1977, under 
Section 12, Water Resources Development Act of 1974 
Aug 13, 1968 
Dec 29, 1981 
Nov 17, 1986 
Nov 17, 1988 
Nov 28, 1990 
WABASH RIVER BASIN (See Section 31of Text) 
Construction of five multipurpose reservoirs and one local protection 
project in Wabash River Basin, IL & IN, with provision that construction 
of Big Walnut Lake, IN, project must be approved by the President. 
Authorization of $50 million for initiation of partial accomplishment 
of project 
Two multiple purpose reservoirs in Wabash River were deauthorized. 
MIAMI RIVER BASIN, PLEASANT RUN, VICINITY 
FAIRFIELD, OH 
Three dry bed reservoirs and a channel improvement were authorized 
in Section 401 of the Water Resource Development Act of 1986. 
HAZARD, KENTUCKY 
Approximately 6 miles of channel improvement were authorized in 
Section 3 of the Water Resources Development Act of 1988. 
Flood control measures to prevent a January 1957 flood reoccurrance in 
the vicinity of Hazard, Kentucky at a total cost of $30,000,000 was 
authorized for design and construction in Section 108 of the Water 
Resource Development Act of 1990. 
H.D. 423, 87th Congress, 
2d Session 
Pub. Law 88-253, 88th Cong., 
1st Session 
Public Law 89-42, 89th Cong., 
1st Session 
Public Law 90-17, 90th Cong., 
1st Session 
Public Law 90-483, 90th Cong., 
2d Session 
Public Law 91-282, 91st Cong., 
2d Session 
Public Law 93-251, 93rd 
Congress, 2d Session 
S.D. 96, 90th Congress, 
2d Session 
Public Law 97-128, 97th 
Congress, 2d Session 
Public Law 99-662, 99th 
Congress, 2d Session 
Public Law 100-676, 100th 
Congress, 2d Session 
Public Law 101-640, 101st 
2nd Session 
16-20

LOUISVILLE, KY, DISTRICT 
TABLE 16-B 
CONTINUED 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
SALYERSVILLE, KENTUCKY 
Flood control measures to prevent a December 1978 flood reoccurrence in the 
vicinity of Salyersville, Kentucky at a total project cost of $7,000,000 was 
authorized for design and construction in section 401(e)(1) of the Water 
Resource Development Act of 1986. With respect to the project, Congress 
has determined that the benefits exceed the cost of such flood control 
measures. 
Provided $400,000 to construct the Salyersville, Kentucky cut-through as 
authorized by PL 99-662 401(e)(1) in accordance with the Special Project 
Report for Salyersville, Kentucky, concurred in by the Ohio River Division 
Engineer on or about July 26, 1989. 
Provided $600,000 to continue construction of the Salyersville, Kentucky 
cut-through as authorized by PL 99-662 section 401(e)(1) in accordance 
with the Special Project Report for Salyersville, Kentucky, concurred in 
by the Ohio River Division Engineer on or about July 26, 1989. 
SOUTH FRANKFORT, KENTUCKY 
Flood protection in accordance with Plan R-1 of the Louisville District 
Commander's Re-evaluation Report, dated June 1990 and a executed LCA 
no later than October 1991 was authorized in Section 102 of the Water 
Resource Development Act of 1990. 
Public Law 99-662, 99th 
Congress, 2d Session 
Public Law 101-514, 101st 
Congress, 2d Session 
Public Law 102-104, 102nd 
Congress, 1st Session 
Public Law 101-640, 101th 
Congress, 2nd Session 
1Deficiency act. Act of Sep. 3, 1954 
2Authorization for Nolin River and Bear Creek revoked by 3Permanent Appropriations Repeal Act. 
16-21 
Nov 17, 1986 
Nov 5, 1990 
Aug 17, 1991 
Nov 28, 1990

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6) 
Name of Project Status 
For Last 
Full Report 
See Annual 
Report 
Cost to Sep 30, 1992 
Operation and 
Construction Maintenance 
Licking River Completed 1901 $ 13,045 
Rough River, KY Completed 1951 105,500 
Tradewater River, KY Completed 1858 18,568 
White River, IN Completed 1909 119,312 
16-22 
$- 
101,196 
33,331

LOUISVILLE, KY, DISTRICT 
TABLE 16-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep 30, 1992 
Full Report 
See Annual Operation and 
Project and Status1 Report Construction Maintenance 
Local Protection: 
Completed: 
Boone County, KY (Ohio River, Rabbit Hash) 
Brevoort Levee, IN (Wabash River) 
Brookport, IL 
Cannelton, IN 
Canoe Creek, Henderson, KY2 
Chaplin River, Perryville, KY2 
Cincinnati, OH 
Covington, KY 
Dayton, KY 
Delphi, IN (Wabash River) 
England Pond Levee, IL (Wabash River) 
English, IN (Little Blue River)2 
Frankfort, KY (North Frankfort) (Kentucky River) 3 8 
Gill Township Levee, IN (Wabash River) 
Golconda, IL 
Grassy Creek, Jackson County, IN (Muscatatuck River)2 
Harrisburg, IL 
Hawesville, KY 
Indianapolis, IN (Fall Creek Section) (White River) 
Indian Creek, Corydon, IN2 
Jackson, KY (Kentucky River) 
Jeffersonville-Clarksville, IN 
Lawrenceburg, IN 
Lebanon Junction, KY (Salt River) 2 
Levee Unit No. 5, Wabash River, IN 
Levee Unit No. 8, White River, IN 
Louisville, KY4 
Lyford Levee Unit, IN (Wabash River) 
Mason J. Niblack Levee, IN (Wabash River)5 
Mill Creek, Jefferson County, KY2 
Mount Carmel, IL (Wabash River) 
Muncie, IN (White River) 
Neon-Fleming, KY (Kentucky River) 
New Albany, IN 
New Harmony Bridge, IL & IN (Wabash River) 2 7 
Newburgh, IN (Ohio River)6 
Newport, KY 
Paducah, KY 
Panther Creek, KY (Green River) 2 
Portland, IN (Salamonie River)2 
Reevesville, IL (Cache River) 
Rochester & McCleary's Bluff Levee, IL (Wabash River) 
Rosiclaire, IL 
Saline River & Tributaries, IL 
Shawneetown, IL7 
Sturgis, KY 
Taylorsville, KY (Salt River) 
Tell City, IN 
Terre Haute (Conover Levee), IN (Wabash River) 7 
Town Creek, Harrodsburg, KY 2 
1977 
1954 
1958 
1959 
1957 
1965 
1987 
1953 
1972 
1965 
1979 
1948 
1960 
1953 
1959 
1955 
1953 
1964 
1957 
1959 
1953 
1967 
1987 
1952 
1975 
1944 
1987 
1973 
1972 
1956 
1963 
1957 
1959 
1974 
1959 
1959 
1970 
1962 
1954 
1972 
1954 
1981 
1972 
1952 
1956 
1965 
1967 
$ 392,443 
1,240,299 
597,493 
2,068,391 
1,206,852 
832,700 
10,150,935 
7,862,937 
13,177,345 
144,563 
734,498 
372,353 
2,960,970 
561,200 
565,333 
70,304 
870,015 
969,318 
1,788,840 
300,143 
130,952 
4,226,361 
2,473,414 
130,417 
7,440,987 
700,534 
26,721,438 
267,391 
5,892,329 
292,710 
1,980,675 
887,835 
86,532 
5,375,471 
297,624 
52,061 
7,512,987 
4,761,551 
254,031 
237,657 
600,300 
1,079,236 
622,544 
7,826,219 
91,000 
1,826,778 
378,050 
932,229 
14,913 
56,505 
16-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
CONTINUED 
For Last Cost to Sep 30, 1992 
Full Report 
See Annual Operation and 
Project and Status' Report Construction Maintenance 
Local Protection, Completed (Cont'd) 
Triplett Creek, Morehead, KY (Licking River) 2 
Uniontown, KY 
Vincennes, IN (Wabash River) 7 
West Terre Haute, IN (Wabash River) 
Active: 
Frankfort, KY (South Frankfort) (Kentucky River) 89 
Greenfield Bayou, IN (Wabash River) 
Hazard, KY' 
Holes Creek, West Carrollton, Ohio (Great Miami River) 9 
Indianapolis, IN (Warfleigh Section) (White River) 
Louisville, KY9' 
Miami River Basin, Pleasant Run, Vicinity Fairfield, OH' 
(Great Miami River) 
Russell & Allison Levee, IL (Wabash River). 
West Fork Mill Creek, OH (Winton Road) 9 
Inactive: 
Blue River, Salem, IN 
Cache River, Upper Basin, Ill 
Columbus, IN 
Frankfort, KY (Benson Creek) (Kentucky River) 
Island Levee, IN (Wabash River) 
Kentucky River National Recreation Area 
Licking River, KY 
Mount Vernon, IN 
New Harmony Bridge, IL & IN (Wabash River) 2 
Southwest Ohio Urban Waterfront Development 
Tell City, IN 
Vincennes, IL (Wabash River) 
Wabash River, York Township, Clark County, IL 
West Fork Drakes Creek, TN & KY 
Westpoint, KY 
Whitewater River & Tributaries, IN & OH 
Deferred: 
Grayville, IL 
Reservoirs: 
Active: 
Camp Ground Lake, KY (Salt River) 
Inactive: 
Big Pine Lake, IN (Wabash River) 
Big Walnut Lake, IN (Wabash River) 
Booneville Lake, KY (Kentucky River) 
Downyville Lake, IN (Wabash River) 
Eagle Creek Lake, KY 
Falmouth Lake, KY (Licking River) 
Lafayette Lake, IN (Wabash River) 
Louisville Lake, IL (Wabash River) 
Mining City Lake, KY (Green River) 
Red River Lake, KY (Kentucky River) 
16-24 
1972 
1956 
1964 
1977 
1979 
1976 
1979 
1959 
1964 
1983 
1977 
1980 
1976 
1975 
1981 
1977 
1983 
1976 
$ 893,094 
1,070,926 
3,308,941 
1,095,704 
1,068,606 
157,935 
491,768 
493,846 
153,410 
415,000 
514,964 
52,088 
477,649 
15,000 
44,000 
283,000 
355,963 
30,000 
50,000 
58,000 
4,490 
112,000 
235,615 
1,270,590 
1,009,188 
1,038,595 
702,471 
944,386 
1,200,920 
2,355,395 
350,474 
1,794,308

LOUISVILLE, KY, DISTRICT 
TABLE 16-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
CONTINUED 
For Last Cost to Sep 30, 1992 
Full Report 
See Annual Operation and 
Project and Status" Report Construction Maintenance 
1All projects are on Ohio River unless otherwise noted. 
2 Authorized by the Chief of Engineers under Section 205, 
1984 Flood Control Act, as amended. 
s Cost includes $161,098 cash contribution consisting of 
$105,118 from the City ofFrankfort, KY and $55,980 from the 
Commonwealth of Kentucky. 
4Cost includes $1,716,301 cash contributions from the City 
of Louisville, KY. 
b Cost shown are for levee and pump plants. 
6 The Water Resources Development Act of 1974 modified 
the Newburgh Locks & Dam project to include the bank 
protection works at Newburgh Locks & Dam project to include 
the bank protection works at Newburgh, IN. 
' Partially completed to form a useful unit. Remaining 
portions of project inactive. 
8 Partially completed to form a useful unit. Remaining 
portions of project are active and inactive. 
9 Advance Engineering and Design funded with General 
Investigations Appropriation. 
16-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Flood Control - Local Protection: 
Adams Levee, IN (Wabash River) - 1978 $ - - 
Alton, IN - 1977 - - 
Anderson, IN (White River) 1940 1986 5,724 - 
Aurora, IN - 1977 35,420 - 
Bellevue, KY - 1977 19,023 - 
Bonpas Creek, IL (Wabash River) - 1981 - - 
Bromley, KY - 1977 - - 
California (Cincinnati), OH - 1977 16,465 - 
Carrollton, KY - 1977 9,713 - 
Caseyville, KY - 1986 - - 
Cave-in-Rock, IL - 1977 - - 
Cincinnati, OH (Unit 2) - 1977 - - 
Cincinnati, OH (Unit 4) - 1977 - - 
Cleves, OH - 1977 6,343 - 
Clinton, IN - 1977 6,848 - 
Cloverport, KY - 1986 - - 
Concordia, KY - 1986 - 
Deer Creek, Prairie Levee, IN - 1977 - - 
Derby, IN - 1977 - - 
Elizabethtown, IL - 1977 - - 
Fletcher & Sunshine Gardens Levee, IN - 1977 3,361 - 
Grandview, IN - 1977 8,497 - 
Honey Creek Levee, IN - 1977 - - 
Leavenworth, IN - 1977 - - 
Levee Unit 1, Eel River, IN - 1977 - - 
Levee Unit 2, Eel River, IN - 1977 - - 
Levee Unit 2, East Fork White River, IN - 1977 - - 
Levee Unit 3, East Fork White River, IN 1938 1977 275 - 
Levee Unit 1, IL (Wabash River) 1973 1986 60,000 - 
Levee Unit 1, Little Wabash River, IL - 1977 - - 
Levee Unit 2, Little Wabash River, IL - 1977- 
Levee Unit 2, Wabash River, IL - 1977 - - 
Levee Units 3 and 4, Wabash River, IL 1938 1977 216 - 
Levee Unit 6, Wabash River, IL - 1977 9,922 - 
Levee Unit 17, Wabash River Basin, IN - 1977 - - 
Levee Unit 1, White River, IN - 1977 - - 
Levee Unit 7, White River, IN - 1977 - - 
Levee Unit 9, White River, IN - 1977 
Levee Unit 10, White River, IN - 1977 
Lewisport, KY - 1990 
Louisville, KY (Partial) - 1986 
Ludlow, KY - 1977 14,503 - 
Madison, IN - 1977 - - 
Mauckport, IN - 1977 
Marion, IN (Wabash River) 1979 1986 209,975 - 
McGinnis Levee, IN 1950 1977 71,049 - 
Metropolis, IL - 1986 10,575 - 
Milton, KY - 1977 - - 
16-26

LOUISVILLE, KY, DISTRICT 
TABLE 16-G 
CONTINUED 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Flood Control - Local Protection (Cont'd.) 
Moscow, OH - 1977 $ - - 
New Amsterdam, IN - 1977 - - 
New Harmony, IN - 1977 - - 
New Richmond, OH - 1977 7,104 - 
Newport-Wilder, KY - 1990 -- 
Orleans, IN 1972 1977 13,158 - 
Owensboro, KY - 1990 - - 
Patriot, IN - 1977 -- 
Prestonville, KY - 1977 - - 
Raccoon Creek Levee, IN - 1977 - - 
Rising Sun, IN - 1977 -- 
Rockport, IN - 1977 - - 
Rome, IN - 1977 - - 
Shawneetown, IL - 1986 25,367 - 
Shoals, IN (East Fork White River) 1938 1977 - - 
Shufflebarger Levee, IN 1950 1977 64,487 - 
Smithland, KY - 1990- 
Sugar Creek Levee, IN 1961 1977 28,061 - 
Terre Haute, IN - 1977 - - 
Tolu, KY - 1986 - - 
Tri Pond Levee, IL 1972 1977 65,510 - 
Troy, IN - 1977 - - 
Utica, IN - 1978 -- 
Vevay, IN - 1977 -- 
Vincennes, IN (Partial) 1964 1986 - - 
Westport, KY - 1977 - - 
Flood Control - Reservoirs 
Big Blue Lake, IN 1980 1981 1,079,867 - 
Clifty Creek Lake, IN 1979 1981 1,016,358 - 
Helm Lake, IL 1976 1981 41,616 - 
Lincoln Lake, IL 1979 1981 1,331,844 - 
Metamora Lake, IN - 1977 - - 
16-27

TABLE 16-H
Miles 
Lock above 
and Mouth of Distance from 
Dam River Nearest Town 
NAVIGATION LOCKS AND DAMS 
PRINCIPAL FEATURES - GREEN & BARREN RIVERS 
AND KENTUCKY RIVER NAVIGATION SYSTEMS 
Lock Dimensions 
Greatest Length 
Available 
Width of For Full 
Chamber Width 
(feet) 
Upper Depth of Year 
Normal Pool Miter Sills Character of Percent Opened to Cost of 
Lift Elevation Upper Lower Foundation Complete Navigation Lock and Dam 
(feet) (feet msl) (feet) (feet) 
CONSTRUCTION OF LOCKS AND DAMS, OHIO RIVER - For report on this improvement see this heading under Ohio River. 
GREEN AND BARREN RIVERS, KY (See Section 3 of Text) 
Green River 
New 1 9.1 Spottsville, KY 84.0 
New 2 63.1 0.3 miles below Calhoun, KY 84.0 
3 108.5 0.3 miles below Rochester, KY 35.8 
4 149.0 Woodbury, KY 35.8 
5 168.1 0.3 miles below Glenmore, KY 56.0 
6 181.7 2.8 miles above Brownsville, KY 36.0 
Barren River 
1 15.0 1 0.3 miles above Greencastle, KY 56.0 
. KENTUCKY RIVER, KY (See Section 4 of Text) 
Kentucky River 
) 1 4.0 3.8 miles above Carrolton, KY 38.0 
2 31.0 Lockport, KY 38.0 
3 42.0 Gest, KY 38.0 
4 65.0 1.0 mile below Frankfort, KY 38.0 
5 82.2 2.8 miles below Tyrone, KY 38.0 
6 96.2 21.6 miles below High Bridge, KY 52.0 
7 117.0 0.8 mile below High Bridge, KY 52.0 
8 139.9 4.7 miles above Camp Nelson, KY 52.0 
9 157.5 Valley View, KY 52.0 
10 176.4 1.0 mile below Ford, KY 52.0 
11 201.0 17.2 miles below Irvine, KY 52.0 
12 220.0 Ravenna, KY 52.0 
13 239.9 2.2 miles below Willow, KY 52.0 
14 249.0 Heidelberg, KY 52.0 
600.0 
600.0 
137.5 
138.0 
360.0 
145.0 
360.0 
145.0 
145.0 
145.0 
145.0 
145.0 
147.0 
147.0 
146.0 
148.0 
148.0 
148.0 
148.0 
148.0 
148.0 
11.8 1 
14.3 
17.0 
16.4 
15.2 
92 
349.1 
363.4 
380.4 
396.8 
412.0 e 
421.1 
15.2 412.0 
8.2 14 
13.9 
13.2 
13.2 
15.0 
14.0 
15.3 
18.7 
17.3 
17.0 
18.0 
17.0 
18.0 
17.0 
430.0 
443.9 
457.1 
470.3 
485.3 
499.3 
514.6 
533.6 
550.6 
567.6 
585.6 
602.6 
620.6 
637.6 
12.1 11.3 
15.0 11.7 
7.3 5.6 
7.1 6.5 
12.0 9.3 
8.0 8.8 
Shale and Coal 100 
Shale 100 
Rock 100 
Rock 100 
Piles and Rock 100 
Gravel 100 
12.0 9.3 Gravel 
8.2 4.8 
7.6 6.1 
8.6 6.5 
6.4 6.3 
10.0 6.4 
9.4 6.4 
9.1 6.8 
10.6 6.0 
10.0 6.6 
9.0 6.0 
10.0 6.0 
9.6 6.0 
9.6 6.0 
8.6 6.0 
1956 2 $5,101,978 s 
1956 a 4,799,271 b 
1836 6 121,377 
1839 ' 125,718 
1934 9 1,020,868 to 
1905 9 168,415 
100 1841 12 871,565 13 
Rock and Clay 100 
Rock 100 
Rock 100 
Rock 100 
Rock 100 
Rock and Piles 100 
Rock 100 
Rock 100 
Rock 100 
Rock 100 
Rock 100 
Rock 100 
Rock 100 
Rock 100 
1839 15- 
1839 15- 
1844 15 1,350,385 16 
1844 15- 
1844 15 17 - 
1894 "17 314,847 
1897 17 290,788 
1900 17 275,463 
1907 17 237,646 
1907 17 221,500 
1906 17 296,593 
1910 1 425,693 
1915 17 461,476 
1971 "17 392,902 
'At normal pool Dam 48, Ohio River, Elev. 337.3, Green River datum (Elev. 9 Operation discontinued August 1, 1951. 
338.0 Ohio River datum) o Does not include $179,434 cost of old Lock and Dam 5. 
2New Lock 1 placed in operation May 25, 1956, old Dam 1, completed 1835-40, nDistance from mouth of Green River is 164.5 miles. Lock closed to navigation 
replaced with new cellular concrete masonry dam constructed 1970-71 with as the result of loss of pool at Green River Lock and Dam 4 on May 24, 1965. 
O&M funds at cost of $822,000. 12 Piles in old gravel dam completed in 1934. 
'Does not include $179,110 cost of old Lock and Dam 1. 13Includes $729,269 for new large lock completed in 1934. 
4 New Lock and Dam 2, placed in operation June 18, 1956. 14At normalpool McAlpine Dam, Ohio River Elev. 421.8 KentuckyRiver datum 
e (Elev. 420 Ohio River datum). 
6 Does not include $295,696 cost of old Lock and Dam 2. (Reconstruction completed by United States in 1882. 
Operationdiscontinued September 30,1981. 1 7 Built by State ofKentucky. Cost given is for repairs by United States to Locks BreachingofdamonMay24,1965, stopped throughtraffic toBowlingGreen, and Dams 1 through 5. Original construction costs to State were: L&D 1, 
KY. $220,300; L&D 2, $151,983; L&D 3, $135,857; L&D 4, $131,607; and L&D 5, 
SWith moveable A-frame crest 3 feet high. $137,436. 
S7Lock was closed to traffic and placed in caretaker status in September 1982.

LOUISVILLE, KY, DISTRICT 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section 26 of Text) 
LOCAL PROTECTION 
Project and Status 1 
Type of 
Construction Federal 
Estimated Cost 
Non-Federal 2 
Completed: 
Barnett Creek, KY (Rough River) 3 
4 
Brookport, IL 5 
6 
Cannelton, IN5 ' 
Cincinnati, OH 5 s 
Covington, KY 5 9 
Dayton, KY 
Delphi, IN (Wabash River) 5 10to 
England Pond Levee, IL 
(Wabash River) 11 
Frankfort, KY,North Frankfort 
(Kentucky River) 5 
Golconda, IL 5 12 
Harrisburg, IL 5 to10 
Hawesville, KY 5 13 
Jackson, KY (Kentucky River) 5 8 
Jeffersonville-Clarksville, IN 7 
Lawrenceburg, IN 0 
Louisville, KY 5 14 
Mason J. Niblack Levee, IN 
(Wabash River) 5 
New Albany, IN 5 8 
New Harmony Bridge, IL & IN 
(Wabash River) 5 7 
Newport, KY 5 7 
Paducah, KY 5 7 
Reevesville, IL (Cache River) 5 15 
Rochester and McCleary's Bluff Levee, IL 
(Wabash River) 11 
Rough River, KY 3 4 
Sturgis, KY (Tradewater River) 11 
Taylorsville, KY (Salt River) 5 16 
Tell City, IN 5 14 
Uniontown, KY 
Vincennes, IN 5 17 
(Wabash River)(completed portion) 5 
West Terre Haute, IN 
(Wabash River) 
Active: 
Evansville, IN 4 
Frankfort, KY 
(Kentucky River) South Frankfort 5 
Russell & Allison Levee, IL 
(Wabash River) 9 
Inactive: 
Frankfort, KY 
(Kentucky River) Benson Creek 5 
New Harmony Bridge, IL and IN 
(Wabash River) 5 7 
Channel improvement 
Wall and levee 
Wall and levee 
Wall and barrier dam 
Wall and levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Cutoff channel 
Wall and levee 
Wall and levee 
Wall and levee 
Levee and pump plants 
Wall and levee 
Bank Protection 
Wall and levee 
Wall and levee 
Levee 
Levee 
Channel improvement 
Levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Levee 
Wall and levee 
Wall 
Levee 
Wall and levee 
Bank protection 
597,493 
2,068,391 
10,150,935 
7,862,937 
13,117,345 
144,563 
734,498 
2,960,970 
565,333 
870,015 
969,318 
130,952 
4,226,361 
2,473,414 
25,005,137 
4,337,617 
5,375,471 
297,624 
7,512,987 
4,761,551 
600,300 
1,079,236 
1,826,778 
378,050 
932,229 
1,070,926 
3,308,941 
1,095,704 
44,654,000 
8,630,000 
19,400,000 
3,340,000 
664,376 
8,500 
29,105 
1,309,146 
1,051,102 
2,013,000 
17,164 
107,000 
272,100 
10,900 
20,000 
42,593 
3,000 
590,888 
284,725 
1,716,301 
605,993 
2,097,496 
11,460,081 
8,914,039 
15,130,345 
161,727 
841,498 
3,233,070 
576,233 
890,015 
1,011,911 
133,952 
4,817,249 
2,758,139 
26,721,438 
109,200 4,446,817 
740,000 6,115,471 
298,506 
232,000 
40,000 
100,000 
93,000 
63,309 
32,707 
72,153 
285,000 
150,000 
297,624 
7,811,493 
4,993,551 
640,300 
1,179,236 
1,919,778 
441,359 
964,936 
1,143,079 
3,593,941 
1,245,704 
5,500,000 50,164,000 36 
2,880,000 11,510,000 36 
2,340,000 21,740,000 21 
1,150,000 4,490,000 22 
99,000 763,376 25 
16-29 
TABLE 16-I 
Total

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section 26 of Text) 
LOCAL PROTECTION 
Project and Status1 
Deauthorized: 
Adams Levee, IN (Wabash River) 32 
Alton, IN 30 
Aurora, IN 31 
Bellevue, KY 30 
Bonpas Creek, IL (Wabash River) 5 33 
Bromley, KY 30 
California (Cincinnati), OH 31 
Carrollton, KY 30 
Caseyville, KY 6 34 
Cave-in-Rock, IL 30 
Cincinnati, OH (Unit 2) 30 
Cincinnati, OH (Unit 4) 30 
Cleves, OH 30 
Clinton, IN (Wabash River) 30 
Cloverport, KY 5 
34 
Concordia, KY 5 
34 
Deer Creek Prairie Levee, IN 
(Wabash River) 30 
Derby, IN 30 
Elizabethtown, IL 30 
Fletcher and Sunshine Gardens Levee, 
IN (Wabash River) 30 
Grandview, IN 30 
Greenfield Bayou Levee, IN 
(Wabash River) 53 5 
Honey Creek Levee, IN 30 
Island Levee, IN (Wabash River) 63s 
Leavenworth, IN 30 
Levee Unit 1, Eel River, IN 30 
Levee Unit 1, Little Wabash River,IL 30 
Levee Unit 1, White River, IN 30 
Levee Unit 17, IN 30 
Levee Unit 2, Eel River, IN 30 
Levee Unit 2, Little Wabash River, IL so30 
Levee Unit 2, White River, IN 30 
Levee Unit 6, Wabash River, IL 30 
Levee Unit 7, White River, IN 30 
Lewisport, KY 35 
Ludlow, KY 30 
Madison, IN 30 
Mauckport, IN so30 
McGinnis Levee, IN (Wabash River) 30 
Metropolis, IL 5 34 
Milton, KY 30 
Moscow, OH 30 
New Amsterdam, IN 30 
New Harmony, IN (Wabash River) 30 
New Richmond, OH 30 
Owensboro, KY 5 35 
Patriot, IN 30 
Type of 
Construction 
Levee 
Levee 
Wall and levee 
Wall and levee 
Channel Improvement 
Wall and levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall 
Levee 
Levee 
Wall and levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Wall and levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Levee 
Levee 
Levee 
Wall and levee 
Wall 
Levee 
Levee 
Levee 
Wall and levee 
Wall and levee 
Levee 
Estimated Cost 2 
Federal 
$ 292,000 
255,000 
4,300,000 
1,570,000 
1,080,000 
1,250,000 
1,750,000 
2,220,000 
396,000 
661,000 
16,800,000 
14,900,000 
1,240,000 
77,000 
728,000 
590,000 
213,000 
553,000 
559,000 
548,000 
580,000 
4,600,000 
653,000 
4,630,000 
1,470,000 
204,000 
2,850,000 
2,180,000 
1,580,000 
2,090,000 
3,410,000 
724,000 
1,160,000 
1,490,000 
610,000 
2,540,000 
3,820,000 
506,000 
1,820,000 
3,070,000 
2,480,000 
1,170,000 
476,000 
616,000 
3,200,000 
886,000 
753,000 
Non-Federal 
$ 14,000 $ 
40,000 
1,190,000 
400,000 
630,000 
925,000 
720,000 
97,000 
35,000 
125,000 
2,900,000 
621,000 
67,000 
9,000 
193,000 
55,000 
10,000 
67,000 
153,000 
26,000 
133,000 
1,087,000 
32,000 
528,000 
266,000 
40,000 
164,000 
116,000 
118,000 
715,000 
136,000 
73,000 
56,000 
88,000 
243,000 
745,000 
360,000 
105,000 
104,000 
431,000 
41,000 
372,000 
13,000 
25,000 
720,000 
195,000 
372,000 
Total 
306,000 27 
295,000 
5,490,000 
1,970,000 
1,710,000 28 
2,175,000 
2,470,000 
2,317,000 
431,000 
786,000 
19,700,000 
15,521,000 
1,307,000 
86,000 
921,000 
645,000 
223,000 24 
620,000 
712,000 
574,000 24 
713,000 
5,687,000 23 
685,000 
5,158,000 23 
1,736,000 
244,000 
3,014,000 27 
2,296,000 27 
1,698,000 28 
2,805,000 
3,546,000 28 
797,000 27 
1,216,000 
1,578,000 27 
853,000 24 
3,285,000 
4,180,000 
611,000 
1,924,000 
3,501,000 
2,521,000 
1,542,000 
489,000 
641,000 
3,920,000 
1,081,000 
1,125,000 
16-30

LOUISVILLE, KY, DISTRICT 
TABLE 16-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section. 26 of Text) 
LOCAL PROTECTION Estimated Cost2 
Type of 
Project and Status1 Construction Federal Non-Federal Total 
Prestonville, KY 30 Wall and levee $ 1,710,000 $ 55,000 $ 1,765,000 
Raccoon Levee, IN (Wabash River) 30 Levee 426,000 37,000 463,000 24 
Rising Sun, IN 30 Wall and levee 896,000 280,000 1,176,000 
Rockport, IN 3o Wall and levee 466,000 133,000 599,000 
Rome, IN 30 Levee 359,000 67,000 426,000 
Shawneetown, IL 5 34 Wall and levee 1,810,000 361,000 2,171,000 
Shufflebarger Levee, IN 
(Wabash River) 30 Levee 2,380,000 90,000 2,470,000 
Smithland, KY5 3 Wall and levee 864,000 414,000 1,278,000 
Sugar Creek Levee, IN 
(Wabash River) 3s0o Levee 418,000 29,000 447,000 24 
Tolu, KY 5 34 Levee 303,000 35,000 338,000 
Tri-Pond Levee, IL (Wabash River) 30 Levee 2,050,000 191,000 2,241,000 25 
Troy, IN 30 Wall and levee 502,000 133,000 635,000 
Utica, IN 5 32 Levee 1,570,000 120,000 1,690,000 
Vevay, IN 30 Levee 1,170,000 146,000 1,316,000 
Vincennes, IN (Wabash River) 
(Uncompleted Portion) 5 34 Wall and levee 3,340,000 - 3,340,000 28 
West Point, KY 634 Wall and levee 3,283,000 400,000 3,683,000 24 
Westport, KY 30 Wall 1,610,000 41,000 1,651,000 
Wilders, KY 35 Wall and levee 10,800,000 959,000 11,759,000 26 
1 All projects are on an Ohio River unless otherwise 
noted. 
2 Latest cost estimate revision 1954 unless otherwise 
noted. 
3 Part of Rough River Reservoir and Channel 
Improvement Project, KY. 
4 Details of this project are in individual report. 
s Also see "Other authorized flood control projects." 
6 See Annual Report for 1958 for details. 
? See Annual Report for 1959 for details. 
8 See Annual Report for 1957 for details. 
9 See Annual Report for 1965 for details. 
10 See Annual Report for 1953 for details. 
11 See Annual Report for 1972 for details. 
12 See Annual Report for 1960 for details. 
13 See Annual Report for 1955 for details. 
14 See Annual Report for 1962 for details. 
15 Substitute project for Belknap, Karnak, and Ullin, IL, 
complete. See Annual Report for 1954 for details. 
16 See Annual Report for 1952 for details. 
17 See Annual Report for 1956 for details. 
18 Latest cost estimate revision 1988. 
19 Latest cost estimate revision 1986. 
20 Latest cost estimate revision 1984. 
21 Latest cost estimate revision 1983. 
22 Latest cost estimate revision 1976. 
23 Latest cost estimate revision 1978. 
24 Latest cost estimate revision 1960. 
25 Latest cost estimate revision 1971. 
26 Latest cost estimate revision 1977. 
27 Latest cost estimate revision 1961. 
28 Latest cost estimate revision 1973. 
29 Latest cost estimate revision 1989. 
o3D0e authorized Aug 05, 1977 under Section 12, Water 
Resources Development Act of 1971 (P.L. 93-251). 
31 Deauthorized Nov 06, 1977 under Section 12, Water 
Resources Development Act of 1974 (P.L. 93-251). 
32 Deauthorized Oct 03, 1978 under Section 12, Water 
Resources Development Act of 1974 (P.L. 93-251). 
33 Deauthorized May 06, 1981 under Section 12, Water 
Resources Development Act of 1974 (P.L. 93-251). 
34 Deauthorized Nov 17, 1986 under Section 12, Water 
Resources Development Act of 1974 (P.L. 93-251). 
35 Deauthorized Jan 01, 1990 under Section 1001 (b)(1), 
Water Resources Development Act of 1986 (P.L. 99-662). 
36 Latest cost estimate revision 1992. 
16-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-I 
CONTINUED 
OHIO RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(See Section 26 of Text) 
RESERVOIRS 
Tributary Basin 
Reservoirs 
Great Miami River: 
Great Miami River: 
Brookville Lake, IN 2 
Metamora Lake, IN 
Green River: 
Barren River Lake, KY 2 
Green River Lake, KY 2 
Mining City Lake, KY 
Nolin Lake, KY 2 
Rough River Kentucky 2 
Kentucky River: 
Booneville Lake, KY 
Buckhorn Lake, KY 2 
Carr Fork Lake, KY 2 
Licking River: 
Cave Run Lake, KY 2 
Falmouth Lake, KY 
Little Miami River: 
Caesar Creek Lake, OH 2 
William H. Harsha 
Lake, OH 2 
Mill Creek: 
West Fork of 
Mill Creek Lake, OH 2 
Wabash River: 
Cagles Mill Lake, IN 2 
Cecil M. Harden Lake. IN 2 
Monroe Lake, IN 2 
Patoka Lake, IN 2 
Estimated Cost 1 
Status 
Complete 
Deauthorized 
Complete 
Complete 
Inactive 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Stream 
East Fork of Whitewater 
River 
West Fork of Whitewater 
River 
Barren River 
Green River 
Green River 
Nolin River 
Rough River 
South Fork of Kentucky 
River 
Middle Fork of Kentucky 
River 
North Fork of Kentucky 
River 
Licking River 
Licking River 
Caesar Creek 
East Fork of Little Miami 
River 
West Fork of Mill Creek 
Mill Creek 
Raccoon Creek 
Salt Creek 
Patoka River 
Federal Non-Federal 
$ 37,905,073 
35,300,000 
27,371,299 
33,238,597 
69,100,000 
17,193,381 
10,620,389 
60,700,000 
11,766,206 
50,854,826 
109,475,282 
125,000,000 
Total 
$ 7,497,492 3 $ 45,402,565 
108,418 8 
223,733 13is 
22,612 
35,300,000 4 
27,479,717 
33,462,330 
69,100,000 4 
17,193,381 
10,643,001 
- 60,700,000 8 
- 11,766,206 
- 50,854,826 
- 109,475,282 7 
- 125,000,000 8 
62,893,882 5,037,000 9 67,930,882 
52,023,157 3,485,840 9 55,508,997 
3,622,302 1,100,161 o10 4,722,463 
4,263,184 
6,633,812 
7,902,827 
113,094 
353,995 
8,666,762 
4,376,278 
6,987,807 
16,569,589 
53,095,790 20,568,369 73,664,159 
1Latest cost estimate revision 1989 unless otherwise noted. 
2Details of this project given in individual report. 
3Cash contributions for water supply storage. 
4Latest cost estimate revision 1954. 
5For Code 713 recreaton development. 
6Latest cost estimate revision 1975. 
'Includes $35,213,000 United States Forest Service cost. 
8Latest cost estimate revision 1979. 
9Reimbursement for water supply storage. 
10 Includes $520,800 for non-Federal cost for sewer 
relocation and dam, $50,000 for contributed funds in fulfillment 
ofproject authorization, and $529,361for Code 713 recreation 
development. 
11 Includes $7,797,604 cash contribution for storage for 
low-flow regulation and $869,158 for Code 713 recreation 
development. 
12 Includes $14,180,677 cashcontributionforwater supply 
storage, and $6,387,692 for initial recreation development. 
13 For $183,732 Code 713 recreation development and 
$40,001 contributed funds. 
16-32

LOUISVILLE, KY, DISTRICT 
TABLE 16-J WABASH RIVER BASIN 
TOTAL COST OF BASIN PLAN 
(FLOOD CONTROL) 
(See Section 31 of Text) 
Type of Estimated Cost 
Construction 
Project or Stream Status Federal Non-Federal Total 
LOCAL PROTECTION 
Marion, IN Wall and Levee Inactive $ 3,900,000 $ 854,000 $ 4,754,000 2 
RESERVOIRS 
Big Blue Lake, IN Big Blue River Deauthorized 87,200,000 53,836,000 3 141,036,000 4 
Big Walnut Lake, IN Big Walnut Creek Inactive 81,800,000 45,069,000 5 126,869,000 4 
Downeyville Lake, IN Flatrock and Little 
Flatrock Rivers Inactive 74,200,000 64,448,000 6 138,648,000 1 
Helm Lake, IN Skillet Fork Deauthorized 25,171,000 14,829,000 ' 40,000,000 8 
Louisville Lake, IL Little Wabash River Inactive 113,000,000 14,435,000 9 127,435,000 10 
1Latest cost revision 1984 unless otherwise noted. 
2Latest cost estimate revision 1977. 
3Includes $38,190,000 reimbursable by non-Federal 
interests for water supply and $15,656,000 reimbursable for 
initial recreation facilities. 
4Latest cost estimate revision 1979. 
5Includes $26,663,000 reimbursable by non-Federal 
interests for water supply and $18,406,000 reimbursable for 
initial recreation facilities. 
6Includes $53,084,000 reimbursable by non-Federal 
interests for water supply, $8,749,000 reimbursable for initial 
recreation facilities. 
7Includes $12,696,000 reimbursable by non-Federal 
interests for water supply and $2,133,000 reimbursable for 
initial recreation facilities. 
8Latest cost estimate revision 1975. 
9Includes $8,402,000 reimbursable by non-Federal 
interests for water supply and $6,033,000 reimbursable for 
initial recreation facilities. 
10 Latest cost estimate revision 1982. 
16-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-K INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 34 of Text) 
Date of 
Projects Inspection 
Local Protection Projects 
Brevoort Levee, IN Aug 1992 
Brookport, IL Sep 1992 
Cache River Levee, IL Sep 1992 
Cannelton, IN Feb 1991 
Cincinnati, OH May 1992 
Covington, KY Nov 1991 
Dayton, KY Apr 1992 
Delphi, IN Mar 1992 
England Pond Levee, IL Aug 1992 
Evansville, IN Sep 1992 
Frankfort, KY, North Frankfort Feb 1991 
Gill Township Levee, IN Jun 1992 
Golconda, IL Nov 1991 
Harrisburg, IL Nov 1991 
Hawesville, KY Feb 1991 
Indianapolis, IN Mar 1992 
Jeffersonville-Clarksville, IN Feb 1991 
Lawrenceburg, IN Apr 1992 
Lebanon Junction, KY Feb 1991 
Levee Unit No. 5, Wabash River, IN Apr 1992 
Levee Unit No. 8, Wabash River, IN Jun 1992 
Louisville, KY Sep 1992 
Lyford Levee, IN Mar 1992 
Mason J. Niblack Levee, IN Aug 1992 
Mount Carmel, IL Aug 1992 
Muncie, IN Apr 1992 
Perryville, KY Aug 1992 
New Albany, IN Feb 1991 
Newport, KY Nov 1991 
Paducah, KY Sep 1992 
Reevesville, IL Dec 1991 
Rochester-McClearys Bluff Levee, IL Nov 1991 
Rosiclare, IL Nov 1991 
Shawneetown, IL Nov 1991 
Southwestern Jefferson County, KY Sep 1992 
Sturgis, KY Apr 1992 
Taylorsville, KY Feb 1991 
Tell City, IN Feb 1991 
Terre Haute (Conover Levee), IN Jun 1992 
Uniontown, KY Apr 1992 
Vincennes, IN Aug 1992 
West Terre Haute, IN Mar 1992 
Channel Improvements (Cont'd.) 
Canoe Creek, Henderson, KY Apr 1992 
Cypress Creek, McLean County, KY Jun 1992 
Eel River, Brazil Waterworks, IN Mar 1992 
English, IN (Little Blue River) Jul 1990 
Grassy Creek, Jackson County, IN Jul 1990 
Harrodsburg, KY (Town Creek) Aug 1992 
Indian Creek, Corydon, IN Aug 1991 
Jackson, KY (North Fork Kentucky River) May 1992 
16-34

LOUISVILLE, KY, DISTRICT 
TABLE 16-K INSPECTION OF COMPLETED 
CONTINUED FLOOD CONTROL PROJECTS 
(See Section 34 of Text) 
Date of 
Projects Inspection 
Lick Creek, Hartford City (Blackford County), IN Mar 1992 
Mill Creek, Jefferson County, KY Jul 1988 
Muscatatuck River, Crothersville, IN Jul 1990 
Neon-Fleming, KY (North Fork Kentucky River) May 1992 
Nicholasville (Town Fork) Vicinity, KY Aug 1992 
Panther Creek, Curdsville, KY Jun 1992 
Plum Creek, Spencer County, KY Aug 1992 
Portland, IN (Salamonie River) Mar 1992 
Rough River, Hartford, Ohio County, KY Jun 1992 
Salamonie River, Wells County, IN Apr 1992 
Saline River and Tributaries, IL Oct 1989 
Tripplett Creek, Morehead, KY May 1992 
Troublesome Creek, Hindman, KY May 1992 
Wabash River, Adams County, IN Apr 1992 
Whitesburg, KY (North Fork Kentucky River) May 1992 
Bank Revetments 
East Fork White River, Brownstown 
(Jackson County), IN Jun 1992 
Eighteen Mile Island, Oldham County, KY Mar 1992 
Great Miami River, Sidney, OH Apr 1992 
Green River, Calhoun, KY Jun 1992 
Licking River, Butler, KY Dec 1990 
Lusk Creek, Golconda, IL Nov 1991 
Little Miami River, Indian Hill, OH Apr 1992 
Little Miami River, Milford, OH Apr 1992 
Ohio River, Brandenburg, KY Aug 1992 
Ohio River, Cloverport, KY Jun 1992 
Ohio River, Daviess County, KY Jun 1992 
Ohio River, Fort Massac State Park, IL Dec 1991 
Ohio River, Hawesville, KY Jun 1992 
Ohio River, Lewisport, KY Jun 1992 
Ohio River, Madison, IN Aug 1989 
Ohio River, Moscow, OH Dec 1990 
Ohio River, Mount Vernon, IN Apr 1992 
Ohio River, Newburgh, IN May 1992 
Ohio River, Ohio Street, Evansville, IN May 1992 
Ohio River, Otter Creek Park, KY Aug 1991 
Ohio River, Owensboro, KY Jun 1992 
Ohio River, Owensboro Riverport Authority, KY Jun 1989 
Ohio River, Rabbit Hash, Boone County, KY Apr 1992 
Ohio River, Rockport/Rockport Landing, IN Apr 1992 
Ohio River, Sellersburg, IN Sep 1986 
Ohio River, SR 66, Cannelton, IN Oct 1991 
Ohio River, Troy, IN Apr 1992 
Ohio River, Upper River Road, Jefferson County, KY Jul 1991 
Ohio River, Vanderburg County, IN May 1992 
Patoka River, Jasper, IN Sep 1992 
Patoka River, Winslow, IN Aug 1992 
South Fork of Wildcat Creek, County Road 7 East, Tippecanoe County, IN Mar 1992 
Stoner Creek, North Middletown, KY May 1992 
Wabash River, near Merom, IN Jun 1992 
16-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 16-K 
CONTINUED 
Projects 
Wabash River, New Harmony, IN 
Wabash River, Vigo County, County Road 83 West 
Wabash River, Vigo County, Little Road 
White River, Petersburg (Pike County), IN 
Whitewater River, Levee Road, near Brookville, IN 
Wastewater Treatment Plant, Great Miami River, Ross, OH 
INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 34 of Text) 
Date of 
Inspection 
Sep 1992 
Mar 1992 
Mar 1992 
Aug 1992 
Apr 1992 
Apr 1992 
16-36

LOUISVILLE, KY, DISTRICT 
TABLE 16-L FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 36 of Text) 
Fiscal Year Cost 
Federal Non-Fed Total 
Small Navigation (Section 107) 
Clark Maritime Center, Jeffersonville, IN' 17,760 17,760 
Southwind Maritime Center, Mt. Vernon, IN ' 1,564 1,564 
Flood Control (Section 205) 
Bailey Creek, Indianapolis, IN 2 23,179 4,145 27,324 
Cilley Creek, Cincinnati, OH' 13,754 13,754 
Duck Creek, Elwood, IN 2 27,196 27,196 
East Fork, Deer Creek, Slaughters, KY' 15,000 15,000 
Falcon/Little Eagle Creeks, IN' 6,765 6,765 
Great Miami River, Port Jefferson, OH5 89,107 11,776 100,883 
Hutto Creek, Austin, IN' 6,605 6,605 
Kentucky River, Frankfort, KY 1 14,495 14,495 
Lancassange Creek, Clark Co., IN 3 9,634 9,634 
Little Miami River, South Lebanon, OH 14,977 14,977 
Lost River, Orleans & Orange Counties, IN ' 5,730 5,730 
Owl Creek, West Carrolton, OH ' 15,000 15,000 
Penitentiary Jones Run, KY 2 47,148 8,055 55,203 
Pipe Creek, Alexandria, IN 4,034 4,034 
Pogues Run, Indianapolis, IN ' 14,576 14,576 
Rolling Fork, Lebanon Junction, KY 2 2,435 2,435 
Sugar Creek, Bellbrook, OH 2 41 41 
West Fork, Blue River, Salem, IN' 6,198 6,198 
White River, Elnora, IN' 8,262 8,262 
White River, Hagerstown, IN 4 555 3,148 3,703 
White River, Hazleton, IN ' 3,730 3,730 
White River, Petersburg, IN1 22,325 22,325 
Snagging and Clearing for Flood Control (Section 208) 
Salamonie River, Montpelier, IN 5 1,932 1,932 
Emergency Bank Protection (Section 14) 
Big Walnut Creek, 500 W, Putnam Co., IN3 1,627 1,627 
Blue Bluff Rd., Morgan Co., IN 5 18,416 13,140 31,556 
Crooked Creek, City Garage, Madison, IN 2 11,924 11,924 
Crooked Creek, J. Paul Park, Madison, IN 2 12,039 12,039 
Indian Creek, Burton Road, Morgan Co., IN3 9,742 9,742 
Little Wabash River, Carmi, IL'1 11,055 11,055 
Nameless Creek, County Road 850 N, IN 3 17,241 17,241 
Ohio River, Brandenburg, KY 2 12,078 12,078 
Ohio River, City Park, West Point, KY2 3,133 3,133 
Ohio River, Daviess County, KY2 12,244 12,244 
Ohio River, Ohio County, IN 2 8,482 8,482 
Ohio River, Switzerland County, IN2 8,195 8,195 
Sugar Creek, Watermelon Hollow Road, Montgomery Co., IN 2 5,070 5,070 
Wabash River, New Harmony, IN' 26,500 26,500 
Wabash River, Terre Haute, IN 3 36,402 36,402 
White River, Franklin County, IN 1 3,252 3,252 
White River, Road 400W, Pike Co., IN2 388 388 
1 Reconnaisance Study 
2 Detail Project Report 
3 Plans and Specification 
4 Construction Funds Received 
5 Construction Completed 
16-37

HUNTINGTON, WV, DISTRICT* 
All cost and financial statements for projects are listed 
at the end of this chapter. All other tables are referenced 
in the text and also appear at the end of this chapter. 
The Huntington District includes central and 
southeastern Ohio, allofWest Virginia except the northern 
panhandle and northeastern portion, the eastern portion 
of Kentucky, a portion of midwestern Virginia, a very 
small portion ofmidwestern Virginia, a very small portion 
ofnorthwesternNorthCarolina, embracedinthe drainage 
basin of the Ohio River and its tributaries from 
approximate river mile 127 (below Pittsburgh, PA) to 
approximate river mile 438, immediately upstream from 
Foster, KY. The drainage area ofthe Huntington District 
is approximately 44,914 square miles. 
IMPROVEMENTS 
Navigation Page 
1. Construction of Locks and Dams 
on Ohio River................................................ 17-2 
2. Kanawha River, WV ..................................... 17-2 
3. Open Channel Work, Ohio River .................. 17-2 
4. Other Authorized Navigation Projects .......... 17-2 
Flood Control 
5. Alum Creek Lake, OH .................................. 17-2 
6. Beech Fork Lake, WV .................................... 17-3 
7. Bluestone Lake, Ohio River Basin, WV ........ 17-3 
8. Burnsville Lake, Ohio River Basin, WV ....... 17-3 
9. Deer Creek Lake, Ohio River Basin, OH ...... 17-3 
10. Delaware Lake, Ohio River Basin, OH ......... 17-4 
11. Dewey Lake, Ohio River Basin, KY ............. 17-4 
12. Dillon Lake, Ohio River Basin, OH .............. 17-4 
13. East Lynn Lake, Ohio River Basin, WV ....... 17-5 
14. Fishtrap Lake, Ohio River Basin, KY .......... 17-5 
15. Grayson Lake, KY ........................................ 17-5 
16. John W. Flannagan Dam and Reservoir, 
Ohio River Basin, VA ................................... 17-6 
17. Levisa and Tug Forks of the Big Sandy and 
Cumberland Rivers, KY, WV and VA .......... 17-6 
18. M assillon, OH ............................................... 17-6 
19. Muskingum River Lakes, OH.......................17-7 
20. Newark, OH .................................................. 17-7 
21. North Branch of Kokosing 
River Lake, OH ............................................. 17-8 
22. North Fork of Pound River Lake, VA............ 17-8 
23. Ohio River Basin (Huntington District)........ 17-8 
24. Paint Creek Lake, Ohio River Basin, OH ..... 17-8 
25. Paintsville Lake, KY ..................................... 17-8 
26. R.D. Bailey Lake, WV ................................... 17-9 
27. Roseville, OH ................................................. 17-9 
28. Summersville Lake, 
Ohio River Basin, WV .................................... 17-9 
29. Sutton Lake, Ohio River Basin, WV .............. 17-10 
30. Tom Jenkins Dam, Ohio River Basin, OH .... 17-10 
31. Yatesville Lake, KY ...................................... 17-10 
32. Inspection of Completed 
Flood Control Projects..................................17-10 
33. Flood Control Work Under 
Special Authorization ................................... 17-11 
General Investigations 
34. Surveys ......................................................... 17-11 
35. Collection and Study of Basic Data .............. 17-11 
Tables 
Table 17-A 
Table 17-B 
Table 17-C 
Table 17-D 
Table 17-E 
Table 17-F 
Table 17-G 
Table 17-H 
Cost & Financial Statement ............ 17-12 
Authorization Legislation ................ 17-17 
Other Authorized 
Navigation Projects ......................... 17-20 
Not Applicable 
Other Authorized Flood 
Control Projects ................................ 17-21 
Not Applicable 
Deauthorized Projects ..................... 17-22 
Inspection of Flood 
Control Projects ............................... 17-24 
17-1 
Page

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON THE OHIO RIVER 
See this heading under Chapter 19- Ohio River. 
2. KANAWHA RIVER, WV 
Location. The Kanawha River is approximately 97 
miles in length and is formed by the junction of the New 
and Gauley Rivers, a short distance above Kanawha 
Falls, WV, and flows generally northwesterly to the 
confluence with the Ohio River at Point Pleasant, WV. 
Previous projects. For details ofprevious projects 
see the Annual Reports for 1875, 1915 and 1938. 
Existing project. The existing project consists of 
three navigation structures on the Kanawha River. 
London Locks and Dam are located approximately 83 
miles above the mouth of the Kanawha River and 
approximately two miles downstream from Montgomery, 
WV. Marmet Locks and Dam are located approximately 
68 miles above the mouth of the Kanawha River at 
Marmet, WV. Winfield Locks and Dam are located 
approximately 31 miles above the mouth of the Kanawha 
River at Winfield, WV. Each structure has twin locks 
with usable dimensions of 56 feet by 360 feet. Another 
structure is located on the Ohio River at approximate 
river mile 279 and approximately nine miles below 
Gallipolis, OH. This structure has two parallel locks, the 
main lock is 110 feet by 360 feet. This system of locks and 
dams provides a navigable depth of nine feet from the 
mouth of the Kanawha River to a point approximately 91 
miles upstream. The existing project was completed at a 
cost of $23,403,201. Construction was initiated in 1931 
and completed in 1937. For further cost details see Table 
17-B, see also, Appendix C. Public Law 99-88 authorized 
the initiation of Engineering and Design and Real Estate 
Acquisition for Winfield Locks and Dam Replacement. 
Feasibilitystudiesformodernizationhavebeencompleted. 
The plan includes construction of an additional lock 
chamber (800'x110') adjacent to the existing locks and 
continued use of the riverward lock chamber and the 
navigation dam. The contract for Lock Replacement - 
Phase I was awarded in April 1990 and is 98% complete. 
The full funding estimate for new work is $236,000,000, 
which is 50 percent Federal cost and 50 percent Inland 
Water Ways Trust Fund cost. 
Local cooperation. None required. 
30 miles east of Charleston, WV. These terminals are 
constructed principally of steel and wood mooring piles 
and steelpilemooringcells. Seventeenoftheseterminals 
have railroad connections. One terminal, a paved wharf, 
is owned by the City of Charleston, WV. The remaining 
terminals areprivatelyowned. Theprincipalcommodities 
handled are coal, chemicals, acids, cement, gasoline and 
oil, and sand and gravel. For further details seethe 1962 
Annual Report. 
Operations during the fiscal year. The Locks 
and Dams were operated as required and necessary 
repairs and improvements were made to the locks and 
dams as well as to the appurtenant structures and 
grounds. Channel inspections were conducted 
periodically. 
3. OPEN CHANNEL WORK, 
OHIO RIVER 
See this heading under Chapter 19- Ohio River. 
4. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 17-C. 
5. ALUM CREEK LAKE, OH 
Location. The damsite is located in Delaware 
County, OH, on Alum Creek, a tributary of Big Walnut 
Creek, approximately 26 miles above the mouth of Alum 
Creek and 15 miles north of Columbus, OH, and 
approximately 157 miles above the mouth of the Scioto 
River.
Existing project. The existing project consists of 
a rolled earthfill dam 93 feet in height and 10,000 feet in 
length with agate controlled spillway located in the right 
abutment. The reservoir provides a total storage of 
134,800 acre-feet and controls a drainage area of 
approximately 123 square miles. See also Appendix A. 
Construction of the dam and appurtenant works was 
initiated in August 1970 and completed in July 1974. The 
405 tracts of land required for the project have been 
acquired. TheFederalcostoftheprojectwas $56,267,422. 
The Sponsorwillreimbursethe Government anestimated 
$27,880,000, exclusive of interest, for cost allocated to 
water supply. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Terminal facilities. There are 79 terminals along Operations and Maintenance. The entire project 
the Kanawha River located from the mouth of the river to is complete. The project was operated for the benefit of 
17-2

HUNTINGTON WEST VIRGINIA DISTRICT 
flood control as required, and necessary repairs were 
made to the structure and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $505,000. To date, the project has prevented an 
estimated $61,046,000 in flood damages. 
6. BEECH FORK LAKE, WV 
Location. The damsite is locatedin Wayne County, 
WV, on Beech Fork Creek, a tributary of Twelvepole 
Creek, approximately four miles above the mouth of 
Beech Fork Creek and 20 miles above the confluence of 
Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of 
a rolled earth-fill dam 86 feet in height and 1,080 feet in 
length, an uncontrolled spillway landward of the left 
abutment of the dam with a control structure at the 
upstream end. The reservoir provides a total storage of 
37,540 acre-feet and controls a drainage area of 
approximately 78 square miles. Construction of the dam 
was initiated in December 1972 and completed in February 
1977. See also Appendix A. A total of 485 tracts of land 
were acquired for the project. The total cost of the project 
was $41,987,500. 
Local cooperation. None required. 
Operations and maintenance. The entire project 
is complete. The project was operated for flood control as 
requiredandnecessaryrepairsweremadetothe structure 
and appurtenances. To date the project has prevented an 
estimated $3,666,000 in flood damages. 
7. BLUESTONE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located on the New River 
in Summers County, WV, approximately three miles 
above Hinton, WV, and one mile from the confluence of 
the New and Greenbrier Rivers. The reservoir is located 
in Summers County, WV, and Giles County, VA. 
Existing project. The existing project consists of 
a concrete gravity dam 180 feet in height and 2,048 feet 
in length. Appurtenant structures consist of a gated 
spillway 790 feet in length located in the channel section 
of the dam. The stilling pool is formed by a 23-foot-high 
weir located 364 feet downstream of 16 gated sluices 
through the spillway section and discharging into the 
stilling pool. Penstocks were installed at the time of 
construction to permit the future installation of 
hydropower. The reservoir provides for a total storage of 
631,000 acre-feet. See also Appendix A. Construction of 
the dam was initiated in January 1942 and completed in 
April 1952. A total of 338 tracts of land was acquired for 
the project. The Federal cost of the project was 
$29,458,652, which includes expenditures under the 
recreation at completed projects program. For further 
details see the 1939 and 1962 Annual Reports. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. The entire project is complete. The 
reservoir was operated for flood control as required and 
necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $746,000. To 
date, the project has prevented an estimated $588,154,000 
in flood damages. 
8. BURNSVILLE LAKE, 
OHIO RIVER BASIN, WV 
Location. ThedamsiteislocatedinBraxtonCounty, 
WV, on the Little Kanawha River, approximately two 
miles above Burnsville, WV, and 124 miles above the 
confluence of the Little Kanawha River and the Ohio 
River. 
Existing project. The existing project consists of 
an earth embankment dam 80 feet in height and 1,000 
feet in length with a gated spillway in the left abutment. 
The outlet works is an integral part of the spillway, 
consisting of five sluice gates and one low flow sluice. The 
reservoir provides for a total storage of 65,400 acre-feet 
and controls a drainage area of approximately 165 square 
miles. Construction of the dam was initiated in June 
1973 and completed in February 1976. See also Appendix 
A. The 357 tracts of land required for the project have 
been acquired. The Federal cost ofthe project to date has 
been $57,163,138. 
Local cooperation. None required. 
Operations during the fiscal year. The project 
is completed. The project was operated for flood control 
as required and necessary repairs were made to the 
structure and appurtenances. During the fiscal year the 
project preventedflood damages estimatedtobe $492,000. 
To date, the project has prevented an estimated 
$28,916,000 in flood damage. 
9. DEER CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Pickaway 
County, approximately seven miles south of Mount 
Sterling, OH, on Deer Creek, a tributary of the Scioto 
River, approximately 21 miles above the mouth of Deer 
17-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
Creek and approximately 106 miles above the mouth of 
the Scioto River. 
Existing project. The existing project consists of 
a rolled earth-filled dam 93 feet in height and 3,880 feet 
in length, a 741-foot concrete gravity channel section 
controlled by three tainter gates, an outlet works 
consistingoffivegated sluicesthrough a concrete spillway 
section discharging into a stilling basin and an earth dike 
15 feet by 4,600 feet in a saddle located approximately 
four miles southwest of the damsite. The reservoir 
provides a total storage of 102,540 acre-feet and controls 
a drainage area of approximately 278 square miles. 
Construction ofthe dam was completed in May 1968. The 
138 tracts of land required for the project have been 
acquired. For further project details seethe 1965 Annual 
Report. See also Appendix A. The Federal cost of the 
project is $20,406,545, including expenditures under the 
recreation at completed projects program. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. Theprojectpreventedanestimated$35,000 
in flood damages during the fiscal year. To date, the project 
has prevented an estimated $21,618,000 in flood damages. 
10. DELAWARE LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located on the Olentangy 
River, approximately six miles above and north of 
Delaware, OH, and approximately 32 miles above the 
confluence of the Olentangy and Scioto Rivers at 
Columbus, OH. The reservoir is located in Delaware, 
Marion and Morrow Counties, OH. 
Existing project. The existing project consists of 
a rolled earth-fill dam with a gate controlled ogee type 
spillway and five outlet conduits in the channel. The dam 
is 18,600 feet in length and 92 feet in height. The project 
provides for storage of 132,800 acre-feet and controls a 
drainage area of approximately 381 square miles. 
Construction of the dam was initiated in April 1946 and 
completed in July 1948. For further details see the 1962 
Annual Report. See also Appendix A. Total real estate 
requirements of 7,703 acres of fee acquisition and 2,428 
acres of flowage easements have been completed. The 
Federal cost for the project was $7,631,821. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for the benefit of flood control 
as required, and necessary repairs were made to the 
structure and appurtenances. The project prevented an 
estimated $174,000 in flood damages during the fiscal 
year. To date, the project has prevented an estimated 
$63,868,000 in flood damages. 
11. DEWEY LAKE, 
OHIO RIVER BASIN, KY 
Location. The damsite is located on Johns Creek, 
approximately seven miles southeast of Paintsville, KY, 
and approximately six miles above the confluence of 
Johns Creek and the Levisa Fork of the Big Sandy River. 
Existing project. The existing project consists of an 
earthfill dam 118 feet in height and 913 feet in length, a 
controlled outlet works discharging through a channel 
excavatedinthe left abutment, and a rolled earth-fill dike 
blocking a low divide to Brandykeg Creek and the Levisa 
Fork. The reservoir provides a total storage of 93,300 acrefeet 
and controls a drainage area of approximately 207 
square miles. Construction of the dam was initiated in 
March 1946 and completed in July 1949. For further 
project detail seethe l965AnnualReport. See alsoAppendix 
A. Total real estate requirements for the project were 
12,458 acres in fee and 1,170 acres in flowage easements. 
The Federal cost of the project was $7,845,547, including 
expendituresfrrecreatiundercompletedprojectprogran 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction activities are 
complete. The reservoir was operated for the benefit of 
flood control as required and necessary repairs were 
made to the structure and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $163,000. To date, the project has prevented an 
estimated $53,590,000 in flood damages. 
12. DILLON LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located on the Licking 
River, approximately six miles above the confluence of 
the Licking and Muskingum Rivers at Zanesville, Ohio. 
Existing project. The existing project consists of a 
rolled earth-fill dam 118 feet in height and 1,400 feet in 
length, a controlled outlet works discharging through a 20- 
foot conduit in the right abutment, and an ungated 280-foot 
spillway adjacent to the left abutment ofthe dam, and two 
17-4

HUNTINGTON WEST VIRGINIA DISTRICT 
rolled earthfill dikes. The reservoir provides for a total 
storage of 261,110 acre-feet and controls a drainage area of 
approximately 748 square miles. Construction of the dam 
was completed in July 1959. For further project details see 
the 1962 Annual Report. See also AppendixA. Total real 
estate required for the project consists of 8,232 acres in fee 
and 5,380 acres of flowage easements. See also Appendix 
A. Federal cost of the project was $30,218,135. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated as required for flood control, 
and necessary repairs were made to the structure and 
appurtenances. To date, the project has prevented an 
estimated $185,690,000 in flood damages. 
13. EAST LYNN LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsiteis locatedin Wayne County, 
WV, approximately six miles southeast ofWayne, WV, 10 
miles above the mouth of East Fork and 42 miles above 
the confluence of Twelvepole Creek and the Ohio River. 
Existing project. The existing project consists of 
an earth-fill dam 113 feet in height and 638 feet in length, 
an uncontrolled spillway near the left abutment of the 
dam, and a 13-foot reinforced concrete tunnel in the right 
abutment with a control structure at the upstream end. 
The reservoir provides for a total storage of 82,500 acrefeet 
and controls a drainage area of approximately 133 
square miles. The required 552 tracts of land have been 
acquired. See also Appendix A. The Federal costs of the 
project was $85,872,963. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated forflood control as required and 
necessary repairs were made to the structure and 
appurtenances. To date, the project has prevented an 
estimated $37,770,000 in flood damages. 
14. FISHTRAP LAKE, 
OHIO RIVER BASIN, KY 
Location. The damsite is located in Pike County, 
KY, on the Levisa Fork of the Big Sandy River, 
approximately 15 miles upstream from Pikeville, KY, 
approximately three miles above the confluence of Levisa 
and Russell Forks and 103 miles above the mouth of the 
Levisa Fork. 
Existing project. The existing project consists of 
a rock-fill dam 195 feet in height and 1,100 feet in length, 
a controlled spillway containing four tainter gateslocated 
in the valley wall adjacent to the left abutment of the 
dam, the outletworks consists of anintake structure with 
three conduits controlled by slide gates and discharging 
into a horseshoe shaped tunnel. The reservoir provides 
for a total storage of 164,360 acre-feet and controls a 
drainage area of approximately 395 square miles. The 
dam was completed in February 1969. The 1,301 tracts 
of land required for the project have been acquired. See 
also Appendix A. The Federal costs for the project was 
$54,670,126, which includes expenditures under the 
recreation at completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required, 
and necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $5,844,000. To 
date, the projecthas preventedanestimated $273,591,000 
in flood damages. 
15. GRAYSON LAKE, KY 
Location. The damsiteis locatedin Carter County, 
KY, on the Little Sandy River approximately 49 miles 
above the confluence with the Ohio River, and 11 miles 
upstream from Grayson, KY. 
Existing project. The existing project consists of 
a random earthfill dam 120 feet in height and 1,460 feet 
in length, a controlled outlet works discharging though a 
14-foot spillway beyond the left abutment. The reservoir 
provides for a total storage of 119,000 acre-feet and 
controls a drainage area of approximately 196 square 
miles. The dam was completed in January 1968. The 484 
tracts of land required for the project have been acquired. 
See also Appendix A. Federal costs for the project was 
$19,162,741, which includes expenditures for recreation 
facilities under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and necessary repairs were made to the structure and 
appurtenances. During the fiscal year the project 
prevented flood damages estimated to be $21,000. To 
date, the project has prevented an estimated $44,110,000 
in flood damages. 
17-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
16. JOHN W. FLANNAGAN 
DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Location. The damsite is located in Dickenson 
County, VA, approximately four miles northwest ofHaysi, 
VA, on the Pound River approximately two miles above 
the confluence of the Pound River and Russell Fork and 
approximately 150 miles above the mouth of the Big 
Sandy River. 
Existing project. The existing project consists of 
a rock-fill dam 252 feet in height and 970 feet in length, 
an outlet tunnel located near the left abutment ofthe dam 
with a control structure at the upstream end, a spillway 
controlled by six tainter gates located in a saddle just 
upstream from the damsite. The reservoir provides for a 
total storage of 145,700 acre-feet and controls a drainage 
area of approximately 222 square miles. The project was 
modified to include water quality control by adding 
control gates to the previously uncontrolled spillway, 
which increased the total storage capacity by 39,000 acrefeet. 
The dam was completed in December 1963. The 382 
tracts of land required for the project have been acquired. 
See also Appendix A. The Federal cost for the project was 
$20,444,383, which includes expenditures for recreation 
under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The project was operated for flood control as required and 
necessary repairs were made to the structure and 
apputenances. Duringthe fiscalyear the project prevented 
flood damages estimated to be $28,000. To date, the project 
haspreventedanestimated$139,177,000inflooddamages. 
17. LEVISA AND TUG FORKS OF THE 
BIG SANDY AND CUMBERLAND 
RIVERS, WV, VA, AND KY 
Location. The Levisa and Tug Forks form the Big 
Sandy River at Louisa, KY. The Cumberland portion is 
the Upper Cumberland River Basin above Cumberland 
Falls, KY. The basin is approximately 100 miles in length 
and averages approximately 30 miles in width in the 
lower portion and approximately 10 miles in width above 
Harlan, KY. The Big Sandy Basin is within the 
Huntington District, and the Cumberland Basin is within 
the Nashville District. This report covers that portion of 
the project located in the Huntington District. 
Existingproject. Theauthorizationlanguagedirects 
the Corps of Engineers to design and construct, at full Federal 
expense, such flood control measures as are determined to 
be necesssary and advisable for the communities in the Tug 
and Levisa Forks and Upper Cumberland River basins. 
The authorization further states that such flood control 
measures wouldbe located at orinthevicinityofPikeville, 
KY; and Grundy, VA, on the Levisa Fork; Pineville, KY, 
on the Cumberland River; and Williamson and Matewan 
ontheTugFork, in orderto affordthe namedcommunities 
and other flood damaged locations and their immediate 
environs a level of protection against flooding at least 
sufficient to prevent any future losses from the likelihood 
of flooding such as occurred in April 1977. The full 
funding estimate for the project is $1,011,400,000, which 
includes $54,100,000 non-Federal contributions. 
Local cooperation. None required. 
Operations during the fiscal year. Additional 
engineering studies are now underway to determine what 
isnecessaryandadvisabletoaddressthefloodingproblems 
inboththeLevisaForkBasinandintheTugForktributary 
stream areas. The contract for construction of the Pump 
Station at West Williamson, WV, was awarded in April 
1983 and is complete. The contract for construction of the 
floodwall at West Williamson, WV, was awarded in July 
1986 andis complete. The contract forthe WilliamsonArea 
Clearing was awarded in September 1987 and is complete. 
The contract for the Williamson Housing Development, 
Valley View Site, was awarded in September 1987 and is 
complete. The contract for the Floodwall and Pump 
Stations for the Williamson Central Business District 
was awarded in June 1988 and is complete. 
The contract for South Williamson Housing 
Development, Pond Creek Site, was awarded in September 
1990 and is complete. The contract for Replacement 
Cafeteria, South Williamson, was awarded in June 1991 
and is complete. The contract for Construction of Local 
Protection Project, South Williamson, Kentucky, was 
awarded in December 1991 and is 45% complete. The 
contract for Construction of Local Protection Project, 
Matewan, West Virginia, was awarded in August 1992. 
18. MASSILLON, OH 
Location. The project is located in Stark County, 
on the Tuscarawas River, approximately 200 miles above 
the mouth of the Muskingum River. 
Existing project. The existing project consists of 
channel improvement to the Tuscarawas River, combined 
with the construction of drainage facilities, levees and 
pump stations. For further details see the 1962 Annual 
Report. Construction was initiated in July 1940 and 
completed in October 1951. 
17-6

HUNTINGTON WEST VIRGINIA DISTRICT 
Local cooperation. None required. See the 1962 
Annual Report for details of local contribution of work 
beyond the scope of the project. 
Operations during the fiscal year. Routine 
inspections were conducted to determine that the improved 
channel was maintained in satisfactory condition. 
19. MUSKINGUM RIVER LAKES, OH 
Location. The Muskingum River lies in Southeast 
Ohio and including tributaries, drains approximately 
8,000 square miles. The headwaters rise about 25 miles 
south of Lake Erie and flow into the Ohio River at 
Marietta, OH, 172 miles below Pittsburgh, PA. 
Existing project. The existing project consists of 
the construction and operations and maintenance of 14 
reservoirs and appurtenant works in the Muskingum 
River Basin. The existing project originally authorized 
by the Public Works Administration in February 1934. 
Construction of the system was initiated in January 1935 
and completed in November 1938. The system was 
initially operated and maintained by the Muskingum 
Watershed Conservancy District of Ohio, the sponsoring 
agency, from July 1938 to August 1939 when operation 
and maintenance became the responsibility of the Corps 
of Engineers in accordance with the provisions of the 
1939 Flood Control Act. For further project details, see 
the 1962 Annual Report. See also Appendix A. The cost 
of the project was $41,247,815, which includes 
expenditures for recreation facilities under the completed 
project program. A significant Major Rehabilitation 
program was approved in December 1977 in order to 
assure the integrity of the existing 14 structures under 
the originally designed maximum pool conditions. 
Underseepage and abutment seepage problems are being 
correctedthroughtheinstallationofdownstreamblankets 
and/or relief wells and grouting. The estimated full 
funding cost of the rehabilitation program is $39,100,000 
intotal, with $25,500,000 from the Construction, General 
Appropriation and $13,600,000 from the Operations and 
Maintenance, General Appropriation. A related but 
separate program entitled Dam Safety Assurance has 
been initiated. Under current hydrologic design 
standards, deficiencies exist in the spillways at all the 14 
projects in the system. Corrective measures include 
widening present spillways, constructing new spillways 
and installing parapet walls on top of the dams. The full 
funding estimate for the Dam Safety Assurance Program 
is $60,870,000. 
Local cooperation. All requirements for local 
cooperation have been met. For further details see the 
1942 Annual Report. 
Operations during the fiscal year. New Work: 
The Major Rehabilitation is continuing as scheduled. 
Thus far, twenty-one contracts have been awarded and 
the program is 65% complete. The Dam SafetyAssurance 
program was initiated during FY 1982. Thus far ten 
contracts have been awarded and the Dam Safety 
Assurance program is 48% complete. 
Operations and Maintenance. The reservoirs 
were operated for flood control as required, and the 
necessary repairs were made to the structures and 
appurtenances. The system prevented an estimated 
$1,930,000 in flood damages during the fiscal year. To 
date, the system has prevented an estimated 
$1,378,649,000 in flood damages. 
20. NEWARK, OHIO 
Location. The project is located in Licking County 
at the junction of the North and South Forks of the 
Licking River, approximately 29 miles above the 
confluence with the Muskingum River at Zanesville, OH. 
Existing project. For details ofthe existing project 
see the 1981 Annual Report. Construction of the existing 
project was initiated in July 1940 and completed in 
November 1941. As a result ofthe 1968 Flood ControlAct 
the existing project was modifiedto include improvement 
of the interior drainage facilities, construction of Log 
Pond Run diversion channel and modification of the 
North Fork Channel. Construction of the Log Pond Run 
diversion channel was awarded in September 1980 and 
completed in December 1981. The full funding estimate 
for the project is $11,100,000 Federal cost and $4,215,000 
non-Federal. 
Local cooperation. For details of required and 
completed local cooperation see the 1981 Annual Report. 
Operations during the fiscal year. New Work: 
North Fork Channel- As a result of withdrawal of State 
support for the Utica Lake project (now inactive) and the 
interdependency of the operation of Utica with the North 
Fork Channel, the North Fork Channel portion of the 
projectrequired re-formulation. Areanalysis is complete. 
Engineering studies continued. The contract for 
construction ofNorth Fork Channel (Phase I) was awarded 
in September 1986 and is complete. The contract for 
construction of the remaining portion of North Fork 
Channel was awarded in February 1988 is complete. The 
contract for Remedial Treatment for Erosion was awarded 
in September 1991 and is 87% complete. 
Operations and Maintenance: Routine 
inspectionswereconductedtodeterminethattheimproved 
channel was maintained in satisfactory condition. 
17-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
21. NORTH BRANCH OF KOKOSING 
RIVER LAKE, OH 
Location. The damsite is located in Knox County, 
OH, ontheNorthBranchofKokosingRiver, approximately 
nine miles above the confluence of the Kokosing and 
North Branch Rivers, and two miles northwest of 
Fredericktown, OH. 
Existing project. The existing project consists of 
a rolled-earth dam, 70 feet in height and 1,400 feet in 
length with an uncontrolled spillway adjacent to the 
right abutment, and an uncontrolled, reinforced concrete 
outlet work located in the right abutment of the dam. The 
reservoir provides for a total storage of 14,885 acre-feet 
and controls a drainage area of approximately 45 square 
miles. The 56 tracts of land required for the project have 
been acquired. Construction ofthe dam was completed in 
May 1972. See also Appendix A. The Federal cost for the 
project was $6,665,985, which includes expenditures 
under the recreation at completed projects program. 
Local cooperation. None required. 
22. NORTH FORK OF POUND 
RIVER LAKE, VA 
Location. The damsite is located in Wise County, 
VA, on the North Fork of Pound River, approximately one 
mile upstream from the confluence of the North and 
South Forks which form the Pound River and 
approximately three miles upstream from Pound, VA. 
Existing project. The existing project consists of 
a rockfill dam, 130 feet in height and 600 feet in length, 
an uncontrolled spillway in a saddle upstream from the 
dam, and an outlet tunnel in the right abutment with a 
control structure at the upstream end. The reservoir 
provides a total storage of 11,300 acre-feet and controls a 
drainage area of approximately 17 square miles. The 127 
tracts of land required for the project have been acquired. 
Construction of the dam was completed in January 1966. 
See also Appendix A. The Federal costs for the project 
was $6,186,901, which includes expenditures for 
recreation under the completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. Operations 
and Maintenance. All construction is complete. The 
project was operated as required for flood control and the 
necessary repairs were made to the structure and 
appurtenances. The project prevented an estimated 
$129,000 in flood damages during the fiscal year. To date, 
the project has prevented an estimated $4,883,000 in 
flood damages. 
23. OHIO RIVER BASIN 
(HUNTINGTON DISTRICT) 
Location. The work coveredby this project consists 
of a series of levees, floodwalls, channel improvements 
and dams and lakes in the Ohio River Basin within the 
Huntington District. 
Existing project. The existing project consists of 
the individual projects considered in the Ohio River 
BasincomprehensiveplanwithintheHuntingtonDistrict. 
Operations during the fiscal year. The 
completed local protection projects, which are operated 
and maintained by local interest, except for those local 
protection projects for which individual reports have 
been included. To date the project has prevented flood 
damages ofan estimated cumulative totalof$645,195,000. 
24. PAINT CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. The damsite is located in Ross County, 
OH, on Paint Creek, a tributary of the Scioto River, 
approximately 37 miles above the mouth of Paint Creek 
and 100 miles above the mouth of the Scioto River and 
approximately four miles east of New Parkersburg, OH. 
Existing project. The existing project cansistsofa rock 
and random earth fill dam, 118 feet in height and 700 feet in 
length,agalecontroledspillwaylocatedneartheightabutment, 
an outlet tunnel located in the right abutment with a control 
structure at the upstream end, and a random rockfill dike 
located at the right abutment of the spillway. The reservoir 
provides foratotal storage of 145,000 acre-feet andcontrols 
adrainageareaofapproximately576squaremiles.Construction 
ofthe dam was completed in July 1973. The 257 tracts ofland 
requiredfortheprjecthavebeenacquired. See alsoAppendix 
A. Federalcostsfor theprojectwas$26,969,962,whichincludes 
expendituresundertherecreationatcompletedprojectspmgram. 
Local cooperation. For details of required local 
cooperation see the 1981 Annual Report. 
Operations during the fiscal year. Operations 
and Maintenance. All construction work is complete. 
The reservoir was operated for flood control as required 
and the necessary repairs were made to the structure and 
appurtenances. During thefiscalyeartheprojectprevented 
an estimated $76,000 in flood damages. To date, the project 
has prevented flood damages estimated to be $41067,000. 
25. PAINTSVILLE LAKE, KY 
Location. The damsiteislocatedin Johnson County, 
KY, on Paint Creek, a tributary ofthe Levisa Fork of the 
17-8

HUNTINGTON WEST VIRGINIA DISTRICT 
BigSandyRiver,approximatelyeightmilesabovethemouth of 
Paint Creek, and four miles west of Paintsville, KY. 
Existing project. The existing project consists of 
a rockfill dam 153 feet in height and 1,560 feet in length, 
an uncontrolled spillway located southwest of the right 
abutment of the dam, and an outlet tunnel in the right 
abutment with a control structure at the upstream end. 
The reservoir provides for a total storage of 76,642 acrefeet 
and controls a drainage area of approximately 93 
square miles. The 635 tracts of land required for the 
project have been acquired. Construction of the dam was 
initiated in September 1976 and was completed in 
September 1980. See also Appendix A. The full funding 
estimate for new work is $66,478,000, which includes 
$3,028,000 non-Federal Costs. The local sponsor has 
reimbursedthe Government $377,000 forthe cost sharing 
portion of recreation development. 
Operations during the fiscal year. New Work: 
Construction ofthe project is well advanced. The remaining 
work items include landscaping and final cleanup. 
Operations and Maintenance. The reservoir was 
operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
During the fiscal year the project prevented flood damages 
estimated to be $110,000. To date, the project has 
prevented flood damages estimated to be $5,976,000. 
26. R. D. BAILEY LAKE, WV 
Existing project. The damsite is located in 
Wyoming County, WV, on the Guyandotte River 
approximately 108 miles above the confluence with the 
Ohio River and one mile east of Justice, WV. 
Existing project. The existing project consists of a 
rolled rockfill dam with a concrete face, 305 feet in height 
and 1,330 feet in length, an uncontrolled spillway located 
in a saddle in the right abutment ofthe dam, and anoutlet 
tunnel in the left abutment with a control structure 
located at the upstream end. The reservoir provides for 
a total storage of203,700 acre-feet and controls a drainage 
area of approximately 540 square miles. Construction of 
the dam was initiated in November 1973 and completed 
in December 1979. See also Appendix A. A total of 2,109 
tracts of land were acquired for the project. The total cost 
of the project to date has been $261,310,398. 
Local cooperation. None required. 
Operations and Maintenance. The reservoir 
was operated for flood control as required and necessary 
repairs were made to the structure and appurtenances. 
Todate,theprojecthaspreventedflooddamages estimated 
to be $68,261,000. 
27. ROSEVILLE, OH 
Location. The project is located in Muskingum 
and Perry Counties, on Moxahala Creek, approximately 
six miles the confluence with Jonathan Creek, a tributary 
of the Muskingum River. 
Existing project. The existing project consists of 
7,291 feet of channel improvement; 6,400 feet of levee and 
railroad embankment enlargements; and the necessary 
appurtenances for interior drainage. Total Federal cost 
of the project was $910,785. Construction was initiated 
in August 1959 and completed in October 1960. 
Local cooperation. All requirements for local 
cooperation have been completed. See also the 1962 
Annual Report. Total costs of local requirements were 
$62,000. 
Operations during the fiscal year. Routine 
inspections of the improved portion of the project were 
conducted to determine that the project was maintained 
in satisfactory condition. 
28. SUMMERSVILLE LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located at Ruckers Bend 
in Nicholas County on the Gauley River approximately 
35 miles above the confluence of the Gauley and New 
River at Gauley Bridge, WV. 
Existing project. The existing project consists of 
a rockfill dam having a height of 357 feet and a length of 
2,280 feet, an outlet tunnel in the right abutment with a 
control structure located at the upstream end, an 
uncontrolled spilway located west of the right abutment 
and two earthfill dikes. The reservoir provides for a total 
storage of 413,800 acre-feet and controls a drainage area 
of 803 square miles. See also Appendix A. Construction 
of the dam was initiated in March 1960 and completed in 
March 1966. A total of 9,346 acres of land were acquired 
for the project. The Federal costs of the project was 
$48,375,884, which includes expenditures under the 
recreation at completed projects program. 
Local cooperation. None required. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necesssary repairs were 
made to the structures and appurtenances. During the 
fiscal year the project prevented flood damages estimated 
to be $20,281,000. To date, the project has prevented an 
estimated $280,905,000 in flood damages. 
17-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
29. SUTTON LAKE, 
OHIO RIVER BASIN, WV 
Location. The damsite is located on the Elk River 
in Braxton County approximately one mile above Sutton, 
WV, and 101 miles above the mouth of the Elk River. 
Existing project. The existing project consists of 
a concrete gravity dam having a height of 220 feet and a 
length of 1,178 feet, a gated spillway in the channel 
sectionofthedam, comprisedofsixtaintergates supported 
by piers, an outlet works comprised of five gate sluices 
through the spillway section. The reservoir provides for 
a storage of 265,300 acre-feet and controls a drainage 
area of 537 square miles. See also Appendix A. 
Local cooperation. None required. See the 1981 
Annual Report for contributed funds. 
Operations duringthe fiscalyear. Allconstruction 
work is complete. The project was operated for flood control 
asrequiredandnecessaryrepairsweremadetothestructure 
andappurtenances. Duringthefiscalyeartheprojectprevented 
flooddamagesestimatedtobe$11,711,000. Todatetheproject 
haspreventedanestimated$194,793,000inflooddamages. 
30. TOM JENKINS RESERVOIR, 
OHIO RIVER BASIN, OH 
Location. The damsiteis locatedinAthens County, 
on the East Branch of Sunday Creek, a tributary of the 
Hocking River, approximately three miles northofGlouster, 
OH, and 57 miles above the mouth of the Hocking River. 
Existing project. The existing project consists of 
a rolled-earth dam, 84 feet in height and 944 feet in 
length, a controlled works discharging through a tunnel 
in the left abutment, and an uncontrolled spillway in the 
ridge running south from the damsite. The reservoir, 
known as Burr Oak Lake, provides for a total storage of 
26,900 acre-feet and controls a drainage area of 
approximately 33 square miles. See also Appendix A. 
Construction of the project was initiated in March 1948 
and completed in February 1950. A total of 100 acres of 
land were acquired for the project. The Federal costs of 
the project were $2,086,503, which includes expenditure 
for recreation at completed project. 
Local cooperation. All requirements of local 
cooperation have been met. See also the 1962 Annual 
Report. Contributed funds in the amount of $575,000 
have been received from the State of Ohio. 
Operations during the fiscal year. All 
construction work is complete. The project was operated 
for flood control as required and necessary repairs were 
made to the structure and appurtenances. To date, the 
project has prevented an estimated $11,233,000 in flood 
damages. 
31. YATESVILLE LAKE, KY 
Location. The damsite is located in Lawrence 
County, on Blaine Creek, a tributary of the Big Sandy 
River, approximately five miles west of Louisa, KY, and 
18 miles above the mouth of Blaine Creek. 
Existing project. The existingproject provides for 
the construction of an earthfill dam, 104 feet in height 
and 770 feet in length, an uncontrolled spillway located 
approximately one-halfmile east ofthe right abutment of 
the dam, and an outlet tunnel through the left abutment 
of the dam with a control structure at the upstream end. 
The reservoir will provide a total storage of 86,951 acrefeet 
and control a drainage area of 208 square miles. The 
full funding estimate for new work is $115,700,000, 
which will be allocated and expended by the Federal 
Government. The sponsorwillreimbursetheGovernment 
an estimated $6,615,000 for the cost sharing portion of 
the recreation development. The local sponsor has 
reimbursed the Government $580,000forthecost sharing 
portion of recreation development. To date, 775 of the 
required 778 real estate tracts have been acquired. A 
contract for construction of the dam was awarded in 
January 1977 and was terminated for the convenience of 
the Government in August 1977. 
Operations during the fiscal year. New Work: 
The contract for Construction of Dam and Appurtenant 
Works, Phase I, was awarded in March 1984 and is 
complete. Contracts with the Commonwealth and the 
County for relocation and/or abandonment of roads 
affected by the project are complete. The contract for 
construction of Dam and Appurtenances (Phase II) was 
awarded in April 1986 and is complete. The contract for 
Relocation of SR 32-2 was awarded in February 1986 and 
is complete. The contract for Reservoir Clearing was 
awarded in June 1989 is complete. The contract for 
Relocating Remaining Highways was awarded in October 
1988 is complete. The contract for Cemetery Relocation, 
Part III, was awarded in February 1989 is complete. The 
contract for Barker Boat Launch Area and Spillway 
Concrete Wall Linings was awarded in July 1990 and is 
complete. 
32. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
The Flood Control Act of June 22, 1936, and 
subsequent acts require local interest to furnish 
17-10

HUNTINGTON WEST VIRGINIA DISTRICT 
assurances that they will operate and maintain certain 
local protection projects after completion in accordance 
with regulations prescribed by the Secretary of the Army. 
District Engineers are responsible forthe administration 
of these regulations within their respective districts. 
Maintenance inspections were made during the fiscal 
yearofthose completedunits transferredtolocalinterests 
for operation and maintenance. Local interests were 
advised, as necessary, of measures required to maintain 
the projects in accordance with the standards prescribed 
by regulations. Total costs for fiscal year 1991 were 
$81,950. Total costto September 30,1991, were $1,707,326. 
The flood control works inspected and the dates of 
inspection are tabulated in Table H. 
33. FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Emergency bank protection activities pursuant to 
Section 14 of the 1946 Flood Control Act, Public Law 526, 
79th Congress are tabulated as follows: 
Location FY 1992 Cost 
Apple Creek, Apple Creek, OH $ 58 
Big Sandy River, Kenova, WV 7,348 
Cheshire, OH 414 
Jardin Manor, Licking County, OH -6,290 
Kanawha River, Rt. 60, South Charleston, WV 19,610 
Kanawha River, Saint Albans, WV 12,932 
Mud River, Barboursville, WV 16,917 
Nimishillen Creek, East Sparta, OH 10,176 
Ohio River, Gallipolis, OH 238 
Ohio River, Route 2, Near Pt. Pleasant, WV 13,618 
Ohio River, Village of Middleport, OH 399,195 
Point Pleasant State Park, WV 1,086 
Riverside Drive, Saint Marys, WV 704 
Russell, KY 807 
Sewerline, Sistersville, WV 1,112 
State Route 62, Buffalo, WV 7,992 
Storm Sewers, Sistersville, WV 939 
WaterStreet, Barboursville, WV 2,475 
Flood control activities pursuant to Section 205 of 
the 1948 Flood ControlAct, Public Law 853, 80th Congress 
are tabulated as follows: 
Location 
Big Horse Creek, Lansing, NC 
Blackfork Mohican River, Shelby, OH 
Blacklick Creek, Franklin Co., OH 
Buffalo Creek, Lawrence Co., OH 
Elk River at Addison, Webster Springs, WV 
Hargus Creek, Circleville, OH 
FY 1992 Cost 
$ 1,162 
32 
84,338 
21,358 
1,879 
43,791 
Hocking River, Chauncey, OH 4,136 
Horse Creek, Jackson, OH 5,867 
Krouts Creek, Huntington, WV 65 
Licking River, Utica, OH 23,392 
Murry City, OH 5,800 
Muskingum River, Mansfield, OH 14,142 
Olentangy River, Galion, OH 23 
Scippo Creek, Pickaway Co., OH 844 
Soldia Creek, Lawrence Co., OH 27,699 
Spring Creek, Spencer, WV 3,059 
White Oak Creek, Russell, KY 107 
SnaggingandclearingactivitiespursuanttoSection 
208 of the 1954 Flood Control Act, Public Law 780, 83rd 
Congress are tabulated as follows: 
Location 
Hocking River, Rockbridge, OH 
Shope Creek, Ashland, KY 
Whetstone Creek, Mt. Giledd, OH 
FY 1992 Cost 
$ 20 
497 
32 
Work performed under special legislation pursuant 
to Water Resources Development Act of 1986 as follows: 
Location FY 1992 Cost 
Bridges, Massillon, OH $ 96 
Kanawha River, Charleston, WV 5,694 
Kanawha River, St. Albans, WV 17,217 
Flood control and coastal emergency activities 
pursuant to Public Law 99, 84th Congress were conducted 
as required during FY 1992 at a cost of $229,791. 
National emergency management activities were 
accomplished by the district as required. The costs for 
these activities during FY 1992 were $151,314. 
34. SURVEYS 
Fiscal year 1992 costs were $1,696,334 itemized as 
follows: 
Location FY 1992 Cost 
Navigation Studies $1,120,922 
Flood Damage Prevention Studies 102,804 
Special Studies 333,117 
Comprehensive Basin Studies 6,301 
Miscellaneous Activities 89,016 
Coordination Studies 44,174 
Advance Engineering and Design 3,478,054 
35. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $109,988. 
17-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
TABLE 17-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
2. Kanawha River, New Work 
WV Approp. - - - - 
(Existing Project) Cost - - - - 
Maint. 
Approp. 5,045,900 6,836,284 5,981,600 9,277,000 
Cost 4,956,717 6,640,967 6,310,071 9,265,713 
Rehab. 
Approp. - - - - 
Cost - - - - 
2. Winfield L&D New Work 
Approp. 
Cost 
5. Alum Creek Lake, New Work 
OH Approp. 
Cost 
Maint. 
Approp. 
Cost 
6. Beech Fork Lake, New Work 
WV Approp. 
Cost 
Maint. 
Approp. 
Cost 
7. Bluestone Lake, New Work 
Ohio River Basin, Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
8. Burnsville Lake, New Work 
Ohio River Basin, Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
9. Deer Creek Lake, New Work 
Ohio River Basin, Approp. 
OH Cost 
Maint. 
Approp. 
Cost 
10. Delaware Lake, New Work 
Ohio River Basin, Approp. 
OH Cost 
Maint. 
Approp. 
Cost 
5,860,000 17,984,000 14,634,000 8,214,000 
5,257,766 14,967,287 16,683,556 8,014,027 
496,800 523,808 
492,537 514,157 
732,200 628,410 
748,714 638,370 
990,700 940,038 
1,027,535 919,671 
1,279,100 1,204,142 
1,225,891 1,265,398 
378,800 384,557 
362,294 397,027 
527,600 511,939 
527,210 490,649 
517,800 617,000 
529,708 630,933 
758,700 791,200 
766,030 810,092 
971,200 1,189,700 
957,153 1,204,816 
971,000 - 
951,386 15,913 
1,298,800 1,392,700 
1,339,379 1,377,257 
493,500 510,100 
502,821 502,300 
669,700 921,800 
588,469 1,007,063 
27,853,6991 
27,853,6991 
101,872,4682 
101,806,4382 
130,984$ 
130,984$ 
50,782,000' 
48,760,731s 
56,267,422 
56,267,422 
7,657,973 
6,630,330 
41,987,500 
41,987,500 
9,004,049 
8,993,364 
29,458,6526 
29,450,6526 
17,599,716 
17,570,659 
57,166,839 
57,163,138 
13,158,947? 
13,120,332? 
20,406,5458 
20,406,5458 
8,321,182' 
8,302,6069 
7,631,821 
7,631,821 
11,150,25810 
11,116,25010 
17-12

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-A (cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
11. Dewey Lake, New Work 
Ohio River Basin, Approp. 
KY Cost 
Maint. 
Approp. 
Cost 
12. Dillon Lake, New Work 
Ohio River Basin, Approp. 
OH Cost 
Maint. 
Approp. 
Cost 
13. East Lynn Lake, New Work 
Ohio River Basin, Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
1,028,200 1,146,347 1,615,900 1,242,000 
1,076,456 1,141,740 1,605,739 1,277,492 
426,300 340,712 365,800 404,300 
463,478 347,484 358,463 393,360 
775,000 84,995 - 47,987,000 
774,512 - 33,005 112,140 47,993,348 
995,100 884,144 1,150,800 1,344,800 
1,123,898 877,552 1,150,555 1,311,440 
14. Fishtrap Lake, New Work 
Ohio River Basin, Approp. - - - 50,000 
KY Cost - - - - 
Maint. 
Approp. 1,039,300 956,962 1,109,600 1,201,200 
Cost 1,076,769 948,010 1,100,529 1,202,034 
15. Grayson Lake, 
KY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
16. John W. Flannagan New Work 
Dam & Reservoir, Approp. 
Ohio River Basin, Cost 
VA Maint. 
Approp. 
Cost 
628,800 624,072 779,400 894,600 
639,720 642,060 768,001 901,028 
935,600 1,012,470 1,198,700 1,419,000 
979,894 987,086 1,210,025 1,413,607 
17. Levisa & Tug Forks New Work 
of the Big Sandy & Approp. 41,100,000 34,566,000 22,123,000 17,654,000 
Cumberland Rivers, Cost 43,081,654 30,563,339 22,808,014 14,736,411 
KY, WV, & VA 
18. Massillon, OH New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
10,000 
9,587 
12,940 
9,359 
19,800 
19,895 
800 
2,984 
7,845,54711 
7,845,54711 
18,824,423" 
18,821,092 2 
30,218,135 
30,218,135 
7,203,1558 
7,175,78418 
85,872,963 
85,872,963 
15,886,55114 
15,827,01514 
54,720,12615 
54,670,1261s 
12,110,26016 
12,060,85516 
19,162,74117 
19,162,74117 
12,121,442 
12,095,321 
20,444,3831 
20,444,38318 
15,722,43219 
15,666,97519 
214,256,000" 
204,938,8830 
8,139,40621 
8,139,40621 
346,248 
343,849 
17-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
TABLE 17-A (cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
19. Muskingum River 
Dams & Lakes, 
OH 
20. Newark, OH 
(Previous Project) 
(Existing Project) 
21. North Branch of 
Kokosing River 
Lake, OH 
22. North Fork of 
Pound River Lake, 
Ohio River Basin, 
VA 
23. Ohio River Basin 
24. Paint Creek Lake, 
Ohio River Basin, 
OH 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
(Rehab.) 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Dam Safety 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
4,222,500 3,835,753 4,380,000 5,003,800 
4,354,381 3,832,053 4,365,582 4,925,831 
200,000 
209,502 
50,000 
375,383 
2,410,000 
3,921,597 
-900 
550,000 
1,638,974 
5,000 
79,459 
1,211,000 
668,997 
-69 
-5,000 
30,334 
-10,000 
2,081 
783,000 
1,591,722 
145 
-42,000 
11,683 
849,000 
1,639,648 
300,000 -90,000 
60,599 271,308 
154,000 128,225 394,900 265,000 
157,555 130,644 171,338 492,144 
265,700 241,487 290,400 342,200 
275,188 245,709 288,030 338,307 
504,700 474,528 505,300 598,100 
503,067 452,429 513,638 600,810 
17-14 
41,247,815" 
41,247,815 
82,098,4033 
81,871,156 
S982,300 
982,300 
22,172,94524 
22,171,0683 
27,258,000 
27,037,992 
845,916 
845,916 
758,673 
758,673 
10,879,512 
10,772,565 
6,665,985w 
6,665,985" 
2,598,042 
2,594,712 
6,186,901" 
6,186,901" 
6,530,0463 
6,517,2233 
355,861" 
355,861" 
26,969,9622 
26,969,9623 
7,984,7843 
7,954,047"

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-A (cont'd) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
25. Paintsville Lake, New Work 
KY Approp. 
Cost 
Maint. 
Approp. 
Cost 
26. R. D. Bailey Lake, New Work 
WV Approp. 
Cost 
Maint. 
Approp. 
Cost 
635,000 1,247,000 -500,000 10,000 
182,694 1,104,675 31,793 137,508 
626,600 553,332 669,296 763,300 
629,138 559,467 679,296 757,973 
- 100,000 - 225,000 
- -61,408 153,504 1,069 
1,178,000 1,244,693 1,252,900 1,289,800 
1,236,457 1,232,038 1,253,244 1,310,489 
60,201,147 
60,186,972 
6,654,632 
6,634,555 
261,542,23381 
261,310,39881 
16,116,00788 
16,066,1898 
27. Roseville, OH 
28. Summersville Lake, New Work 
Ohio River Basin, Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
29. Sutton Lake, New Work 
Ohio River Basin, Approp. 
WV Cost 
Maint. 
Approp. 
Cost 
30. Tom Jenkins Dam, New Work 
OH Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,040,100 966,752 1,144,200 1,310,200 
1,086,289 968,860 1,158,242 1,312,501 
1,293,900 1,158,258 1,335,100 1,465,100 
1,356,331 1,180,160 1,323,179 1,440,660 
242,500 300,864 247,100 218,000 
226,493 302,982 249,453 226,249 
31. Yatesville Lake, New Work 
KY Approp. 17,627,000 6,799,000 2,070,000 1,749,000 
Cost 18,798,052 5,313,333 4,752,263 1,442,034 
Maint. 
Approp. - 7,050 623,100 906,300 
Cost - 4,739 618,770 898,495 
48,375,884" 
48,375,884u 
22,264,166k 
22,238,612k 
37,029,585" 
37,029,585u 
25,431,145" 
25,371,842" 
2,086,503$' 
2,086,503$' 
5,107,339 
5,098,859 
96,628,500 
95,519,466 
1,536,450 
1,522,004 
See page 17-17 for footnotes. 
17-15 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
22,700 25,009 
40,653 
19,800 
20,210 
-1,200 
4,419 
910,785 
910,785 
236,277 
234,878

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
'Includes $4,294,612 for new work for previous projects, 
$4,498,636 Emergency Relief funds, $9,004,800 Public Works 
funds and $686,317 Code 713 funds. 
2Includes $3,883,513 for maintenance of previous projects 
and $546,090 Maintenance and Operation funds. 
$Public Works Acceleration funds. 
'Includes $25,391,000 Inland Waterways Trust funds. 
$Includes $34,352,114 Inland Waterways Trust Fund. 
6Includes $543,960 Emergency Relief funds, $9,698 Public 
Works Acceleration funds, $211,850 Code 711 funds and $75,000 
Code 713 funds. 
'Includes $444,928 Maintenance and Operations Funds. 
8Excludes $225,090 contributed funds. Includes $590,000 
Code 711 funds. 
9l'Includes $130,000providedbytheProductiveEmployment 
Act of 1983. 
'l�Includes $240,000 providedbythe Productive Employment 
Act of 1983. 
"Includes $23,087 Public Works Acceleration funds, 
$1,089,940 Code 711 funds and $231,105 Code 713 funds. 
12Includes $82,900 Special Recreation Use Fee Funds and 
$444,928 Maintenance and Operations Funds. 
'sIncludes $100,000 provided from the Productive 
Employment Act of 1983. 
"Includes $209,918 Special Recreation Use Fee Funds and 
$444,928 Maintenance and Operations Funds. 
'5Includes $362,649 Code 711 funds and $10,000 Code 712 
funds. 
'6Includes $38,000 Special Recreation Use Fee Funds and 
$445,029 Maintenance and Operations Funds. 
'?Includes $406,919 Code 711 funds and $2,317 Code 713 
funds. 
8sIncludes $422,983 Code 711 funds. 
19'Includes $88,710 special recreation use fees. 
"Includes Cost from Ohio River Division of $696,000. 
21Includes $477,813 contributed funds. 
Includes $27,190,000 National Industrial Recovery funds 
and $528,288 Code 711 funds. 
"Includes $198,578 Maintenance and Operations funds. 
"Includes $61,945 Public Works Acceleration funds. 
TIncludes $45,177 Code 711 funds. 
TIncludes $64,233 Code 711 funds. 
"Includes $68,200 special recreation use fees. 
"Includes $10,920 Emergency Relief funds. 
"Includes $14,153 Code 711 funds. 
S"Includes $31,496 special recreation use fee funds. 
1lncludes $5,534 Consolidated Army funds. 
32Includes $60,000 provided from the Productive 
Employment Act of 1983, and $66,678 Maintenance and 
Operations Funds. 
"Includes $300,062 Code 711 funds. 
"'Includes $214,112 special recreation use fee funds, 
$300,000 provided from the Productive Employment 
Appropriations Act of 1983, and $66,678 Maintenance and 
Operation Funds. 
"Includes $1,837,337 Code 711 funds and $287,843 
Accelerated Public Works funds. Excludes $62,800 contributed 
funds. 
T Includes $267,634 special recreation use fee funds, 
$215,000 provided from the Productive Employment 
Appropriations Act of 1983, and $142,078 Maintenance and 
Operations Funds. 
87Includes $8,064 Code 711 funds and $30,000 Public 
Works Acceleration funds. Excludes $575,000 contributed funds. 
17-16

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
2. Aug. 30, 1935 
Aug. 15, 1985 
5. Oct. 23, 1962 
6. Oct. 23, 1962 
7. Jun. 28, 1938 
Dec. 22, 1944 
8. Jun. 28, 1938 
Dec. 22, 1944 
9. Jun. 28, 1938 
10. Jun. 28, 1938 
Dec. 22, 1944 
11. Jun. 28, 1938 
Dec. 22, 1944 
12. Jun. 28, 1938 
Dec. 22, 1944 
KANAWHA RIVER LOCKS AND DAMS, WV 
Construction of three locks and dams on the Kanawha 
River and one on the Ohio River. 
Engineering and Design and Land Acquisition for 
Winfield Locks and Dam. 
ALUM CREEK LAKE, OH 
Construction of Flood Control Reservoir. 
BEECH FORK LAKE, WV 
Construction of Flood Control Reservoir. 
BLUESTONE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
Deleted Power 
BURNSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
DEER CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
DELAWARE LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DEWEY LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
DILLON LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
H. Doc. 31, 73rd Cong., 
1st Sess. 
P.L. 88, 99th Cong., 
1st Sess. 
H. Doc. 587, 87th Cong., 
2nd Sess. 
H. Doc. 520, 87th Cong., 
2nd Sess. 
H. Doc. 91, 74th Cong., 
2nd Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong. 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
17-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
TABLE 17-B (cont'd) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
13. Jun. 28, 1938 
Dec. 22, 1944 
14. Jun. 28, 1938 
Dec. 22, 1944 
15. Jul. 14, 1960 
16. Jun. 28, 1938 
Dec. 22, 1944 
17. Oct. 1, 1980 
18. Jun. 28, 1938 
19. Feb. 20, 1934 
Jun. 28, 1938 
Aug. 11, 1939 
20. Jun. 28, 1938 
Aug. 13, 1968 
21. Oct. 23, 1962 
EAST LYNN LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation. 
FISHTRAP LAKE, OHIO RIVER BASIN, KY 
Construction of Flood Control Reservoir. 
Added Recreation. 
GRAYSON LAKE, KY 
Construction of Flood Control Reservoir. 
JOHN W. FLANNAGAN DAM AND RESERVOIR, 
OHIO RIVER BASIN, VA 
Construction of Flood Control Reservoir. 
Added Recreation. 
LEVISA AND TUG FORKS OF THE BIG SANDY 
RIVER, AND CUMBERLAND RIVER, KY, WV 
Construction of such Flood Control Measures as deemed 
Necessary and Advisable. 
MASSILLON, OHIO 
Construction of Channel Improvement Project. 
MUSKINGUM RIVER LAKES, OH 
Construction of 14 Flood Control Reservoirs. 
Reimbursement to the Muskingum Conservancy 
District a sum not to exceed actual expenditures 
for project construction. 
Operations and Maintenance assigned to 
the Corps of Engineers. 
NEWARK, OHIO 
Construction of Channel Improvement Project. 
Modification to Existing Project and Additional 
Channel Improvement and Drainage Facilities. 
NORTH BRANCH OF KOKOSING RIVER LAKE, OH 
Construction of Flood Control Reservoir. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 440, 86th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Sect. 202, P.L. 367, 
96th Cong., 2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Ses. 
Public Works Admin. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 396, 76th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Ses. 
H. Doc. 337, 90th Cong., 
2nd Sess. 
H. Doc. 220, 87th Cong., 
2nd Sess. 
17-18

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-B (cont'd) AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
22. Jul. 14, 1960 
24. Jun. 28, 1938 
Dec. 22, 1944 
25. Oct. 27, 1965 
26. Oct. 23, 1962 
27. Jun. 28, 1938 
28. Jun. 28, 1938 
Dec. 22, 1944 
29. Jun. 28, 1938 
Dec. 22, 1944 
30. Dec. 22, 1944 
31. Oct. 27, 1965 
32. Jun. 22, 1936 
NORTH FORK OF POUND RIVER LAKE, VA 
Construction of Flood Control Reservoir. 
PAINT CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
Added Recreation 
PAINTSVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
R. D. BAILEY LAKE, WV 
Construction of Flood Control Reservoir. 
ROSEVILLE, OH 
Construction of Channel Improvement Project. 
SUMMERSVILLE LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
SUTTON LAKE, OHIO RIVER BASIN, WV 
Construction of Flood Control Reservoir. 
Added Recreation 
TOM JENKINS DAM, OHIO RIVER BASIN, OH 
Construction of Flood Control Reservoir. 
YATESVILLE LAKE, KY 
Construction of Flood Control Reservoir. 
INSPECTIONS OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspection of Local Maintenance of Federally 
Constructed Local Protection Projects. 
H. Doc. 645, 86th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 246, 89th Cong., 
1st Sess. 
H. Doc. 569, 87th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
Flood Control Comm. 
Doc. 1, 75th Cong., 
1st Sess. 
P.L. 534, 78th Cong., 
2nd Sess. 
H. Doc. 762, 78th Cong., 
2nd Sess. 
H. Doc. 246, 89th Cong., 
2nd Sess. 
P.L. 738, 74th Cong., 
1st Sess. 
17-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
TABLE 17-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Big Sandy River 
WV and KY including 
Levisa and Tug Forks2 1952 1,586,236 1,569,8111 131,473 
Elk River, WV' 1903 30,259 
Gauley River, WV' 1903 14,761 
Guyandotte River, WV5 1915 27,500 
Little Kanawha River, WV6 1960 470,536 1,023,854 
Muskingum River, OW 1955 301,912 6,171,897 6,041 
New River, WA and VA5 1899 109,691 
Scioto River at Portsmouth, OH8 1953 10,951 16,593 
1In addition, $140,068 expended from funds transferred 
from Department of Commerce, under accelerated public works 
program, for repairs of eroded bank at lock 3 on Big Sandy 
River, at Louisa, KY. 
'Operation and Maintenance suspended June 30,1952. 
'Work closed September 1902. Property transferred to 
Kanawha River improvements. 
'WorkclosedSeptember 1902.Abandonmentrecommended 
in H. Doc. 467, 69th Congress. 
'Work suspended. 
6Operation and maintenance suspended June 30, 1951. 
'Collections fromlicense non-Federalhydroelectric utilities 
for use of dams on Muskingum River for fiscal years 1923-1953 
were $79,154. 
Private Law 954, August 31,1954, authorized Secretary of 
Treasury to pay Portsmouth Sand and Gravel Co. $75,000 in 
17-20

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Local Protection Projects 
Ashland, KY 1954 3,718,839 ----- 
Athens, OH 1979 5,313,700 ----- 
Cattletsburg, KY 1963 3,854,361 ----- 
Ceredo-Kenova, WV 1955 2,753,551 ---- 
Chillicothe, OH 1986 20,373,314 --.-- 
East Rainelle, WV 1962 614,598 ------ 
Galax, VA 1953 480,536 ----- 
Huntington, WV 1956 7,172,840 ----- 
Ironton, OH 1952 2,604,646 ----- 
Maysville, KY 1959 6,493,747 --- 
Parkersburg, WV 1955 6,652,827 ----- 
Pt. Pleasant, WV 1955 2,919,578 ----- 
Portsmouth-New Boston, OH 1956 9,806,424 --- 
Princeton, WV 1962 808,750 --- 
Russell, KY 1953 552,493 --- 
Williamson, WV 1964 1,056,166 ----- 
Inactive Local Protection Projects 
Augusta, KY --- 11,577 ----- 
Coal River, WV 1979 472,229 --- --- 
Vanceburg, KY --- --- -- 
Deferred Local Protection Projects 
Newark, OH (Interior Drainage) 1983 --- ----- 
Oceana, WV 1981 611,000 ----- 
Inactive Reservoirs and Lakes 
Haysi, VA --- 2,656 -- 
Deferred Reservoir and Lakes 
Kehoe Lake, KY 1981 1,272,740 -- 
Active Authorized Projects with no current year expenditures. 
Martin, KY 1983 212,048 ----- 
17-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
TABLE 17-G DEAUTHORIZED PROJECTS 
All projects listed in this table have been deauthorized in accordance with Section 12 of the Water Resources Development Act 
of 1974, P.L. 251, 93rd Congress. 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds 
Local Protection Projects Report For Date Expended Expended 
Aberdeen, OH --- May 1981 1,334 -- 
Athalia, OH --- Aug 1977 --- 
Belpre, OH --- Nov 1977 --- 
Brooklyn, WV --- Nov 1979 ----- 
Buena Vista, OH --- Aug 1977 -- -- 
Chambersburg, OH --- Aug 1977 ---- 
Chesapeake, OH --- Nov 1986 --- 
Cheshire, OH--- Nov 1977 --- 
Chilo, OH --- Aug 1977 -- -- 
Clifton, WV --- Aug 1977 11,237 -- 
Coal Grove, OH --- Jan 1990 3,389 -- 
Columbus, OH --- Aug 1977 ---- 
Dover, KY --- Jan 1990 -- -- 
Friendly, WV --- Aug 1977 ---- 
Fullerton, KY --- Jan 1990 -- 
Gallipolis, OH --- Aug 1977 ---- 
Greenup, KY --- Jan 1990 4,962 -- 
Hanging Rock, OH --- Aug 1977 ---- 
Hartford, WV --- Aug 1977 ---- 
Henderson, WV --- Aug 1977 ---- 
Higginsport, OH --- Oct 1978 ----- 
Hockingport, OH --- Aug 1977 -- -- 
Letart, WV --- Aug 1977 -- -- 
Letart Falls, OH --- Aug 1977 -- 
Lower Guyandotte River Basin, WV --- Nov 1986 17,721 -- 
Manchester, OH --- May 1981 -- -- 
Mapleshade, OH --- Oct 1978 --- 
Marietta, OH --- Nov 1981 -- -- 
Mason, WV --- Aug 1977 -- -- 
Middleport, OH --- May 1981 9,783 -- 
Miller, OH --- Aug 1977 --.-- 
Millwood, WV --- Aug 1977 -- -- 
New Martinsville, WV -- Nov 1979 -- -- 
New Matamoras, OH --- Aug 1977 ----- 
Newport, OH --- Aug 1977 -- --. 
Normal, KY --- Jan 1990 -- -- 
Pomeroy, OH --- Aug 1977 --- 
Portland, OH --- Aug 1977 -- -- 
Proctorville, OH --- Nov 1986 -- -- 
Racine, OH --- Aug 1977 --- -- 
Ripley, OH --- Oct 1978 7,523 --- 
Riverview, WV --- Aug 1977 ---- 
St. Mary's, WV --- Aug 1977 ----- 
Sardis, OH --- Aug 1977 -- -- 
Sciotoville, OH --- Aug 1977 -- -- 
Sistersville, OH --- Aug 1977 ---- 
South Point, OH--- Nov 1986 ---- 
South Portsmouth, KY --- Jan 1990 .--- 
Syracuse, OH --- Aug 1977 ----- 
Waverley, WV --- Aug 1977 -- -- 
Williamstown, WV --- Nov 1979 -- -- 
Zanesville, OH --- May 1981 -.--- 
17-22

HUNTINGTON WEST VIRGINIA DISTRICT 
TABLE 17-G (cont'd) DEAUTHORIZED PROJECTS 
All projects listed in this table have been deauthorized in accordance with Section 12 of the Water Resources Development Act 
of 1974, P.L. 251, 93rd Congress. 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds 
Local Protection Projects Report For Date Expended Expended 
Reservoirs and Lakes 
Big Bend, WV --- Aug 1977 --- 
Big Darby, OH 1969 Nov 1979 3,349,568 -- 
Birch, WV --- Nov 1986 ----- 
Frazeysburg, OH --- May 1981 5,000 -- 
Leading Creek, WV 1974 Jan 1990 272,880 -- 
Logan, OH -- Oct 1985 ----- 
Millersburg, OH --- May 1981 -- -- 
Mill Creek, OH 1981 Nov 1981 1,602,702 - 
Moores Ferry, VA --- Nov 1986 22,879 -- 
Mud River, WV --- Nov 1979 -- -- 
Panther Creek, WV 1976 Nov 1986 -- -- 
Poca, WV --- May 1981 -- -- 
Rocy Fork, OH 1950 Aug 1977 91,321 -- 
Salt Creek, OH 1975 Nov 1986 1,089,943 --- 
Utica, OH 1975 Jan 1990 757,550 -- 
West Fork, WV 1974 Jan 1990 663,192 -- 
White Oak Creek, OH --- Nov 1981 --- --- 
17-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY-1992 
TABLE 17-H INSPECTION OF FLOOD CONTROL PROJECTS - See Section 32 of Text 
Flood Control Works Inspected Dates of Inspection 
Ashland, KY May 92 Nov 92 
Athens, OH May 92 
Bramwell, WV Oct 92 
Cairo, WV Sep 92 
Canton (Nimishillen), OH Aug 92 
Cattletsburg, KY Apr 92 Oct 92 
Ceredo-Kenova, WV Apr 92 Sep 92 
Chillicothe, OH May 92 Oct 92 
East Rainelle, WV Oct 92 
Fishing Creek, Pine Grove, WV Sep 92 
Fourpole Creek, WV Oct 92 
Galax, VA Oct 92 
Grahn, KY Sep 92 
Griffithsville-Yawkey, WV 
Hutchins, KY 
Huntington, WV May 92 Sep 92 
Inez, KY May 92 
Ironton, OH Apr 92 Sep 92 
Jacksonsburg, Fishing Creek, WV Sep 92 
Maysville, KY May 92 Dec 92 
Montcalm, WV Oct 92 
Newark, OH Jun 92 Nov 92 
Olive Hill, KY Sep 92 
Paint Creek at Chillicothe, OH Nov 92 
Paint Creek at Washington Court House, OH Nov 92 
Parkersburg, WV May 92 Dec 92 
Pax, WV Oct 92 
Point Pleasant, WV May 92 Dec 92 
Portsmouth-New Boston, OH Jul 92 Nov 92 
Prestonsburg, KY Jun 92 
Princeton, WV Dec 92 
Richwood and Fenwick, WV Sep 92 
Right and Left Forks of Beaver Creek, KY 
Ripley, WV Sep 92 
Roseville, OH May 92 Nov 92 
Russel, KY Apr 92 Sep 92 
Smithfield, WV Sep 92 
South Williamson, KY Jun 92 Oct 92 
Utica, OH Aug 92 
West Union, Middle Island, WV Sep 92 
Williamson, WV Jun 92 Oct 92 
17-24

PITTSBURGH, PA DISTRICT* 
This District comprises part of eastern Ohio, western 
Pennsylvania, southwestern New York, northern 
West Virginia, and northwestern Maryland embraced in 
drainage basin of Ohio River and Tributaries above mile 
127 (below Pittsburgh), immediately upstream from New 
Martinsville, W. Va. 
IMPROVEMENTS 
Navigation - Locks and Dams .......... Page 
1. Allegheny River, PA.... . . . . . . . . . . . . . 18-2 
2. Construction of locks and dams,Ohio River... . 18-2 
3. Monongahela River, PA and WV... . . . . . . . 18-2 
4. Open-channel work, Ohio River... . . . . . . . 18-3 
5. Tygart Lake, WV... . . . . . . . . . . . . . . 18-3 
6. Other authorized navigation projects . . . . . 18-4 
Flood Control - Local Protection 
7. Chartiers Creek, PA... . . . . . . . . . 
8. Elkins, WV... . . . . . . . . . . . . . . 
9. Johnstown, PA............... 
10. Punxsutawney, Ohio River Basin, PA... 
11. Turtle Creek, PA . . . . . . . . . . . . 
.... 18-4 
. . . . 18-4 
.... 18-4 
.... 18-5 
.... 18-5 
Flood Control - Reservoirs 
12. Berlin Lake, Ohio River Basin, OH... . . . .. 18-6 
13. Conemaugh River Lake,Ohio River Basin, PA. 18-6 
14. Crooked Creek Lake, Ohio River Basin, PA.. . 18-6 
15. East Branch, Clarion River Lake, 
Ohio River Basin, PA................18-6 
16. Kinzua Dam and Allegheny Reservoir, 
Ohio River Basin, PA and NY . . . . . . . . . 18-7 
17. Loyalhanna Lake, Ohio River Basin, PA...... 18-7 
18. Mahoning Creek Lake, 
Ohio River Basin, PA . . . . . . . . . . . . .. 18-7 
19. Michael J. Kirwan Dam and Reservoir, 
Ohio River Basin, OH.. . . . . . . . . . . . 18-8 
20. Mosquito Creek Lake, Ohio River Basin, OH . 18-8 
21. Ohio River Basin (Pittsburgh District) . . . .. 18-9 
22. Shenango River Lake, Ohio River Basin, PA 
and OH ............... ..... 18-9 
23. Stonewall Jackson Lake, 
Ohio River Basin, WV................18-9 
24. Tionesta Lake, Ohio River Basin, PA ..... 18-10 
25. Union City Dam, Ohio River Basin, PA. . . . 18-10 
26. Woodcock Creek Lake, Ohio River Basin, PA. 18-10 
27. Youghiogheny River Lake, Ohio River Basin, PA 
and MD . .. .. . . . . . . ..... .... . 18-11 
28. Inspection of completed flood control projects. 18-11 
29. Other authorized flood control projects . . . . 18-11 
30. Flood control work under special 
authorization . . . . . . . . . . . . . . . . . 18-11 
General Investigations 
31. Surveys..................... 
32. Collection and study of basic data... . . . . 
33. Preconstruction, Engineering and Design... 
34. Research and development... . . . . . . . . 
Tables 
Table 18-A Cost & Financial Statement. . . 
Table 18-B Authorizing Legislation . . . . . . 
Table 18-C Other Authorized Navigation 
Projects ............... 
Table 18-D Not Applicable. 
Table 18-E Other Authorized Flood Control 
Projects... . . . . . . . . . . . . . . 
Table 18-F Not Applicable. 
Table 18-G Deauthorized Projects . . . . . . . 
Table 18-H Allegheny River Statistics ...... 
Table 18-I Monongahela River Statistics. . . . 
Table 18-J Monongahela River Total Costs. . 
Table 18-K Ohio River Basin Reservoirs . . . 
Table 18-L Inspection of Completed Flood 
Control Projects. ........... 
Table 18-M Flood Control Work Under Special 
Authorization.............. 
18-12 
18-12 
18-12 
18-12 
S18-13 
S18-17 
18-21 
S18-22 
S18-24 
. 18-25 
. 18-26 
. 18-28 
. 18-28 
. 18-29 
. 18-30 
18-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation - Locks and Dams 
1. ALLEGHENY RIVER, PA 
Location. The Allegheny River is 325 miles long. It 
rises in northern Pennsylvania, flows northwestward 
into New York, thence generally southwestward to Pittsburgh, 
PA, where it joins with Monongahela River to form 
the Ohio. (See Geological Survey Charts for western 
Pennsylvania and southwestern New York.) 
Existing project. The project consists of eight locks 
and dams to afford slack-water navigation for a length of 
72 miles from Pittsburgh, PA to above East Brady, PA. 
Controlling depth through canalized portion is 9 feet at 
normal pool level. Channel width varies from a minimum 
of 200 feet to full width of river at mouth. Existing project 
is complete, the last lock, No. 9, was placed in service in 
1938. All locks and dams are in fair condition. Navigation 
channel has been widened at certain points and, in general, 
maintained to project depth, thus affording adequate 
depth for passage of commercial tows. 
Local cooperation. Fully complied with. 
Terminal facilities. City of Pittsburgh constructed a 
modern wharf for river freight. There are numerous 
privately maintained terminals and docks, consisting of 
tipples, various types of hoists, chutes, and pipelines for 
use in loading and unloading coal, stone, sand, gravel, 
petroleum products, steel products, and other commodities. 
Transshipment of freight between river and railroads 
is handled at privately owned river-to-rail 
terminals. Existing private terminals are adequate for 
shipments and receipt in Pittsburgh District of type of 
commerce now in existence. 
Operations during fiscal year. Operations & Maintenance, 
General: The 8 locks on the Allegheny River 
have had no major additions or rehabilitation efforts 
since being put into service. A program to provide for 
needed repairs to Locks and Dams 2 through 9 for the 
continuation of safe and reliable navigation has been 
initiated. The required work will generally consist of the 
following: Replace deteriorated concrete on an as needed 
basis; provide necessary stabilization for the lock walls; 
replace filling and emptying valves and anchorages; replace 
hydraulic and electrical systems; replace gate operating 
machinery and anchorages; furnish and install tow 
haulage units and appurtenant items of work. 
Major work that was physically completed during the 
fiscal year included renovation of the 7' x 8' penstock 
valve in the turbine raceway at L/D 4 for $356,865; 
dewatering the 56' x 360' lock chamber to repair quoin 
seals, miter sills, hydraulic crossovers, install new downstream 
lock gates, and install an air bubbler system at 
L/D 6 for $1,115,932; installation and alignment of renovated 
downstream lock gates at L/D 3 for $275,232; 
renovation of the 8' x 10' river wall filling valve and 8' x 
10' land wall emptying valve and operating machinery at 
L/D 9 for $318,811; rewiring of the electrical system and 
installation of new lock wall lighting at L/D 8 for 
$126,892; and the completion of concrete repair work at 
L/D 5 for a total contract cost of $1,383,879. 
2. CONSTRUCTION OF LOCKS AND 
DAMS, OHIO RIVER 
See this heading under Ohio River portion. 
3. MONONGAHELA RIVER, PA 
AND WV 
Location. Formed by junction of Tygart and West 
Fork Rivers about 1 mile south of Fairmont, WV, and 
flows northerly for 128.7 miles to its junction with Allegheny 
River, forming Ohio River at Pittsburgh, PA (See 
Geological Survey Charts for southwestern Pennsylvania 
and northern West Virginia.) 
Previous project. For details see Annual Report for 
1963, page 1070. 
Existing project. Provides for improvement of river 
by 9 locks and dams to afford slack-water navigation for 
its entire length from Pittsburgh to above Fairmont, WV. 
Original locks and dams 7,8 and 9 were replaced by new 
locks and dams 7 and 8 in 1925. Increased traffic necessitated 
enlargement and improvement of locks and dams 
1 to 6 between Pittsburgh and Rices Landing, PA, by 
building two parallel chambers and fixed concrete dams 
during 1905 and 1932. Locks and dam 1 were eliminated 
in 1938 by raising Emsworth Dam, Ohio River. Reconstruction 
of lock 2 was completed in 1953 to provide two 
modern navigation chambers. The existing locks and dam 
2 were originally completed in 1907; major modifications 
were made in 1923 and 1924, and in 1926 the upper guard 
and guide walls were extended. Construction of Maxwell 
locks and dam and the reconstruction of dam 4 have 
allowed for removal of obsolete locks and dams 5 and 6. 
Small and antiquated original locks and dams 10 to 15, 
inclusive, have been replaced by three modern structures. 
Morgantown lock and dam, initial step in replacement 
program, was completed in 1950 replacing locks 
and dams 10 and 11. Hildebrand lock and dam, next 
upstream, was completed in 1959 replacing locks and 
dams 12 and 13. Raising crest of dam 8 was also completed 
in 1959 as part of upper river improvement and 
eliminates restricted depth in upper reach of pool. Opekiska 
lock and dam was completed in 1967 replacing locks 
and dams 14 and 15. Completion of this link in upper 
river replacement program provides for entire river 
length of minimum channel depth of 9 feet, varying in 
width from a minimum of 250 feet to practically full width 
at mouth. 
Locks and dam 3 showed advanced stages of deterioration 
and, because of its strategic location and its importance 
to industry throughout the Greater Pittsburgh area 
and the nation, emergency remedial work had to be done 
in 1977. Major rehabilitation of locks and dam 3 was 
completed on Oct. 27, 1980. 
The Water Resources Development Act of 1986 authorized 
the replacement of Lock and Dam 7 with Grays 
Landing Lock and Dam and the construction of a new lock 
landward of the existing lock at Lock and Dam 8 (to be 
renamed Point Marion Lock and Dam). In accordance 
with the provisions of this act, 50% of the total cost of 
construction for the Grays Landing and Point Marion 
projects will be derived from the Inland Waterways Trust 
Fund. 
18-2

PITTSBURGH, PA., DISTRICT 
Local cooperation. None required. 
Terminal facilities. City of Pittsburgh constructed 
a modern wharf for freight. Boat landings are maintained 
by some municipalities along the river. A large number 
of tipples at mines and various types of hoists at manufacturing 
plants and sand and gravel supply companies 
are maintained for private use in loading and unloading 
coal, coke, billets, steel products, sand, gravel, and other 
commodities. These terminals and docks are not available 
for general commerce. A number of docks and pipelines 
are also privately maintained for petroleum and 
acid products. Marine ways are maintained by some of 
the larger industries. These are also several terminals for 
rail-to-river and river-to-rail transfer. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year: New Work: The 
right bank excavation at Grays Landing Lock and Dam 
was completed in November, 1989 at a cost of 
$12,400,000. All land for the lock site has been acquired. 
Work continues on cultural resources and the acquisition 
of real estate for the remainder of the project. A contract 
for the construction of the lock was awarded on March 1, 
1990 for $78,600,000 and is approximately 90% complete. 
The estimated total cost of the project, which is scheduled 
to be complete in August, 1995 is $171,800,000. 
A contract for the construction of the new lock for the 
Point Marion Project was awarded on March 26, 1990 for 
$78,800,000 and is approximately 83% complete. All real 
estate for the project has been acquired. The estimated 
total cost of the Point Marion project, which is scheduled 
to be complete in September, 1994 is $101,500,000. 
The Chief of Engineers report of the structural problems 
and future traffic conditions at Locks and Dams 2, 
3 and 4 was sent to the Secretary of the Army in June 
1992 recommending the most economical replacement 
plan, known as the National Economic Development 
(NED) plan. The NED plan would consist of the replacement 
of the fixed-crest dam at L/D 2 with a gated dam 
having 5 - 110' tainter gates, rehabilitation of the locks 
in the year 2020 and the replacement of the floodway 
bulkhead structure for the small lock chamber; raising 
existing Pool 2 by 5 feet; major adjustments or possible 
reconstruction of a major railroad bridge; the construction 
of new twin 84' x 720' locks at L/D 4; the removal of 
L/D 3; lowering existing Pool 3 by 3.2 feet; associated 
miscellaneous federal and non-federal private relocations 
and channel dredging; and the establishment by the 
Coast Guard of a reduced bridge clearance height of 42.5 
feet for the Monongahela River. The project has a first 
cost of approximately $750 million. 
Operations and Maintenance, General: Major 
work that was completed during the fiscal year includes: 
renovation and replacement of a tainter valve, dewatering 
and renovation of upper lock gates at Hildebrand L/D 
for $1,452,391; renovation and replacement of a culvert 
valve at L/D 4 for $234,406; renovation of upstream gate 
operating machinery on the auxiliary chamber at L/D 3 
for $129,718; repair of the damaged guardwall at Maxwell 
L/D for $221,872; repair and replacement of upstream 
mooring cells at L/D 2, 4 and Maxwell L/D for 
$657,261; fabrication of 56' chamber lock gates for 
$1,064,112; enlargement of railroad grade crossing at 
Morgantown for $114,000; purchase of new air compressor 
and dryer for LID 2 for $24,299; renovation of dam 
machinery housings at Opekiska L/D for $36,120; and 
renovation of concrete surfaces on abutment wall at Morgantown 
L/D for $110,958. 
4. OPEN-CHANNEL WORK, 
OHIO RIVER 
See this heading under Ohio River portion. 
5. TYGART LAKE, WV 
Location. Tygart Lake is located on the Tygart River 
in Taylor and Barbour Counties, northcentral WV. The 
lake is approximately 26 road miles due east of 
Clarksburg, WV and 30 road miles south of Morgantown. 
The dam is situated 22.7 river miles above the mouth of 
the Tygart River at Fairmont, or 2.25 miles upstream 
from Grafton, WV, and about 78 miles south of Pittsburgh, 
PA. (See Geological Survey Charts for Fairmont, 
Thornton, and Belington, WV.) 
Existing project. A reservoir for low water regulation 
and flood control. Dam is concrete gravity type with an 
uncontrolled center spillway flanked by abutment sections 
joining valley sides. Project was authorized by Public 
Works Administration January 11, 1934, and adopted 
by 1935 River and Harbor Act. For further project description 
see Annual Report for 1962. Authorized project 
is complete. Reservoir is in operation for low water control 
in Monongahela River and for purpose of flood protection 
in Monongahela and Ohio Valleys. Construction 
of dam was started in 1935 and placed in operation in 
1938. Land acquired for project consists of 2,662.9 acres 
in fee, flowage easements over 1,216.9 acres and 1,731.9 
acres of other easements. 
Local cooperation. The State of West Virginia has 
assumed responsibility for the development and operation 
of hunting and fishing areas as well as the Tygart 
Lake State Park. Controlled releases for downstream 
navigation and recreation are also coordinated with others 
to the extent feasible. No local cooperation is required 
at completed project; however, future recreational developments 
are subject to certain conditions of non-Federal 
cost-sharing under Federal Water Project Recreation Act 
of 1965. A cost-sharing agreement was executed with the 
West Virginia Department of Recreation in May 1981. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low water regulation, as required, and 
project structures were operated and maintained in a 
serviceable condition throughout the year. Estimated 
flood control benefits achieved by this reservoir for FY 92 
were $42,000. Total flood control benefits for this reservoir 
through September 30, 1992 are $554,384,000. Activities 
under reservoir management program 
comprising sanitation measures, conservation, land 
management, and operation and maintenance of publicuse 
facilities continued. This work was limited in scope 
as State of West Virginia has jurisdiction over most of the 
recreation in reservoir area. 
Tygart Dam is a priority candidate for a major rehabilitation 
effort which will provide for repair and restora- 
18-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
tion of the 51 year old structure. In addition to deteriorated 
concrete repairs, other major project components 
identified to date for study include: replacement of sluice 
liners, follower legs and gates; replacement of the 42-inch 
gate valve; modernization of the hydraulic gate operating 
system; redesign of the maintenance bulkhead system; 
upgrading the electrical system and installation of a 
service bridge. A stability analysis of the structure will 
also be undertaken to assure that all major structural 
issues will be addressed. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 18-C on other authorized navigation projects. 
Flood Control - Local Protection 
7. CHARTIERS CREEK, PA 
Location. Within Washington and Allegheny Counties, 
southwestern Pennsylvania, a tributary of Ohio 
River. (See Geological Survey Chart for Carnegie, PA) 
Existing project. Project was authorized by Flood 
Control Act of 1965 and provides for channel widening, 
deepening and realignment, construction of a major 
channel cutoff, and relocations in two separate and independent 
reaches. James G. Fulton project in Allegheny 
County would be about 13.4 miles long and Canonsburg- 
Houston reach in Washington County about 4.7 miles 
long. Completed improvements would contain within 
banks, all floods up to the 1912 maximum of record, but 
with some residual damage, and would greatly reduce 
flood stages and damages resulting from higher floods. 
James G. Fulton Flood Control Project-Construction of 
Unit 1 was started in July 1968, completed in September 
1970, and turned over to local interests for operation and 
maintenance on June 25, 1971. Construction of Unit 2 
was started in April 1970, completed in April 1973, and 
turned over to local interests on November 22, 1974. 
Construction of Unit 3 was started in July 1971 and was 
completed in December 1974. Construction of Unit 5 was 
started in June 1972 and was completed in December 
1973. Construction of Unit 4 channel improvement was 
started in July 1978, completed in June 1981 and turned 
over to local interests on 18 November 1981. A contract 
for Environmental Improvement, Unit 4, James G. Fulton, 
was awarded in Sep 1981 and completed in Dec 1981. 
Canonsburg-Houston Reach-Construction of Unit 1 was 
started in December of 1968, completed in March 1970, 
and turned over to local interests for operation and maintenance 
on August 10, 1970. Construction of Unit 2A was 
started January 17, 1976, completed December 16, 1976, 
and turned over to local interests on June 9, 1977. Construction 
plans and specifications for Unit 2B, the remaining 
unit of the reach, are 99% complete. Remaining 
work on project has been delayed due to the inability of 
local cooperating agency to provide the necessary rightsof-
way. Major flooding in Houston, PA in September, 
1990 has generated renewed interest in completion of the 
project. 
Estimated cost for new work (1985) is $41,850,000 of 
which $32,750,000 is Federal cost and $9,100,000 non- 
Federal cost. 
Local cooperation. Requirements are described in 
full on page 26-3 of FY 1981 Annual Report. Local cooperating 
agency (Washington County) has been unable to 
provide the necessary rights-of-way for the remaining 
Unit 2B. Direct non-Federal contributions have been 
made in the amount of $4,225,188. 
Operations during fiscal year. Regular inspections 
were made at completed units. Estimated flood control 
benefits achieved by the Chartiers Creek project for this 
period were $300,000. Total benefits achieved through 
September 30, 1992 were estimated to be $20,407,000. 
8. ELKINS, WV 
Location. On Tygart River in north-central Randolph 
County, WV, about 155 miles south of Pittsburgh, PA. It 
is at downstream end of a long, broad reach of upper 
Tygart Valley, about 75 miles above mouth of river. (See 
Geological Survey Chart for Elkins, WV). 
Existing project. Provides flood protection by diverting 
flood discharges from upstream arm of loop of natural 
river channel into an artificial cutoff channel, thereby 
bypassing City of Elkins. Improvement is designed to 
accommodate discharges equivalent to maximum flood of 
reasonable expectancy. Project construction was started 
in May 1946 and completed in May 1949. Completed 
works, except that portion of.channel maintained by Federal 
Government, has been operated and maintained by 
City of Elkins since March 31, 1949. Land acquired for 
project consists of 32.04 acres in fee and 526.01 acres in 
easements. Project was authorized by 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1222. Federal cost of completed project was 
$1,772,627; estimated non-Federal cost for lands, easements, 
and rights-of-way was $40,000. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and 
maintenance, general: Routine investigations and inspections 
were made. Project was last inspected in September 
1992. Cumulative total flood damages prevented 
to September 30, 1992, totaled $14,311,000. 
9. JOHNSTOWN, PA 
Location. Project is located in southwestern Cambria 
County, PA, about 58 miles east of Pittsburgh, PA. It is 
in a deep and comparatively narrow valley at junction of 
Stoney Creek and Little Conemaugh River, which unite 
to form Conemaugh River. (See Geological Survey Chart 
for Johnstown, PA.) 
Existing project. Provides for increased channel capacity 
by enlarging and realigning channels and protecting 
banks with concrete pavement. Improvement 
designed to accommodate discharges equivalent to those 
of March 1936 flood, maximum natural flow of record, 
minimum of overbank flow and to practically eliminate 
damages therefrom. Project construction began in August 
1938 and was completed in November 1943. Footer 
protection for Unit 4 was completed in November 1949. 
Land acquired for project consists of easements over 192 
acres. Project was authorized by Flood Control Acts of 
1936 and 1937. For further project description see Annual 
Report for 1962, page 1215. 
18-4

Local cooperation. The rules of local cooperation for 
the rehabilitation of the existing project are governed by 
the FY 91 Energy and Water Resources Appropriations 
Act. Pursuant to this Act, the City of Johnstown will have 
a limited role in securing the needed rights of access to 
non-federal structures included in the line of protection 
and will hold and save the United States from damages 
due to construction or operation and maintenance of the 
work on the non-federal structures, except for damages 
due to the fault or negligence of the United States or its 
contractors. 
Operations during fiscal year. Operations and 
maintenance, general: The FY 1991 Energy and Water 
Resources Appropriations Act authorized and directed 
the Corps to undertake a major rehabilitation of the 
existing project. Work was initiated on a Rehabilitation 
Evaluation Report on the rehabilitation measures required 
to ensure the project's capability of providing the 
degree of protection for which it was originally constructed. 
During FY 92, the City of Johnstown secured 
the needed rights of entry for investigative work required 
for the preparation of the Rehabilitation Evaluation Report, 
which is scheduled for completion in November of 
1993. 
A contract was awarded in November, 1991 for miscellaneous 
repairs of the concrete slope lining. The work 
was essentially complete on 30 September 1992; the 
estimated final cost is $689,322. 
Cumulative flood damages prevented by the project 
were estimated to be $418,010,000 through September, 
1992. 
10. PUNXSUTAWNEY, 
OHIO RIVER BASIN, PA 
Location. Borough of Punxsutawney is on Mahoning 
Creek in Jefferson County, PA, about 85 miles northeast 
of Pittsburgh, PA. It is on a comparatively wide, alluvial 
flood plain about 52 miles above mouth of stream and 30 
miles above Mahoning Creek flood control dam. (See 
Geological Survey Charts for Punxsutawney and 
Smicksburg, PA.) 
Existing project. Provides flood protection by channel 
enlargement, dikes, and walls. Improvement is designed 
to accommodate discharges 20% greater than that 
of maximum flood of record. Construction was accomplished 
by construction of four units. Construction 
started May 1946 and was completed June 1950. Land 
acquired for project consists of perpetual easements over 
72.6 acres. Completed works, except that portion of channel 
maintained by the Federal Government have been 
operated and maintained by Borough of Punxsutawney 
since July 31, 1950. Project was authorized by 1938 Flood 
Control Act. For further project description see Annual 
Report for 1962, page 1209. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Operation and 
maintenance, general: operation activities continued and 
routine investigations and inspections were made. A contract 
was awarded in December 1991 for removal of bar 
deposits and clearing. Work was essentially completed in 
July 1992, estimated final cost is $168,000.
PITTSBURGH, PA., DISTRICT 
Cumulative flood damages prevented by project were 
estimated to be $29,561,000 to end of September 1992. 
11. TURTLE CREEK, PA 
Location. In Allegheny and Westmoreland Counties, 
adjacent to Pittsburgh, PA, along lower reaches of Turtle 
Creek and Thompson Run, a tributary of Turtle Creek. 
(See Geological Survey Chart for Pittsburgh, PA). 
Existing project. The existing channel improvement 
project was constructed during the period 1962-1967 and 
provided for flood protection by widening, deepening, and 
streamlining channel of lower Turtle Creek for about 6.3 
miles and channel of Thompson Run for about 1 mile 
above its mouth. Appurtenant work consists of channel 
streambed and side slope protection where required, retaining 
walls, drop structures, floodgates, alteration, removal 
or reconstruction of restrictive structures and 
adjustments of affected utilities. Project was designed to 
accommodate a design flood corresponding to an estimated 
100 year frequency. Project was authorized by 
Flood Control Act of 1958. Federal cost for completed 
project was $15,350,000; non-Federal cost was 
$1,840,000. The Fiscal Year 1985 Supplemental Appropriations 
Act specified that the Secretary of the Army, 
acting through the Chief of Engineers, is authorized and 
directed to repair and restore the Turtle Creek, Pennsylvania, 
local protection project. Estimated Federal cost for 
repair and restoration work is $6,600,000; non-federal 
cost is $1,650,000. 
Local Cooperation. The Turtle Creek Flood Control 
Authority was the local sponsor for the existing project. 
However, they are not financially able to sponsor the 
project restoration, nor to subsequently perform any required 
project maintenance. 
Allegheny County is the local sponsor for the project 
rehabilitation and 11 other requirements for local cooperation 
for the future maintenance of the project. A local 
cooperation agreement was executed with the county on 
August 4, 1992. 
Operations during fiscal year. New work: The 
proposed project consists of debris and sediment removal 
from the Turtle Creek and Thompson Run channels and 
debris basin; clearing trees and brush from channel side 
slopes, restoration of channel side slopes, repairs to concrete 
retaining walls, debris dams, trashracks, spalled 
concrete joints and drainage appurtenances; and removal 
of vegetative growth from weepholes. During FY 92, a 
directed economic analysis was initiated to determine if 
the project was still economically justified. The analysis 
was completed and resulted in a favorable benefit-to-cost 
ratio of 1.9 with future growth. The favorable benefit-tocost 
ratio resulted in the release of the local cooperation 
agreement to the district for final execution. The local 
cooperation agreement was fully executed by the 
ASA(CW) in August 1992. Real estate acquisition is 
continuing and is currently scheduled for completion in 
May 1993. Contract award is scheduled for August/September 
1993. 
Estimated total flood damages prevented through September 
1992 were $83,659,000. 
18-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Flood Control - Reservoirs 
12. BERLIN LAKE, 
OHIO RIVER BASIN, OH 
Location. Dam is on Mahoning River about 73 miles 
above its confluence with Shenango River. It is about 10 
miles above existing Milton Reservoir Dam and 35 miles 
upstream from Warren, Ohio. Reservoir is in Portage, 
Mahoning and Stark Counties, OH. (See Geological Survey 
charts for Warren, Ravenna, and Alliance, OH.) 
Existing project. A reservoir for flood control and 
water supply. Dam consists of a partially controlled, 
concrete gravity, center spillway flanked by rolled-earthfill 
abutment sections joining valley sides. Authorized 
project is complete and in operation for flood control and 
low water regulation purposes in industrialized Mahoning 
Valley below. Construction of dam was started in 
January 1942 and completed in June 1943. Present project 
lands consists of 6,885.3 acres in fee and 1,098.7 acres 
in easements. For further project description, see Annual 
Report for 1962, page 1233. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject 
to certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. Operations and 
maintenance, general: A contract for paving, resurfacing 
and reconditioning of existing roads, awarded in July 
1992 for $319,640, was 33% complete at end of FY 92. 
Reservoir was operated as required and necessary repairs 
were made to structures and appurtenances. Estimated 
flood control benefits achieved in FY 92 were 
$957,000; total through FY 92 were $245,163,000. Activities 
under reservoir management program comprising 
sanitation measures, conservation, land management, 
and operation and maintenance of public-use facilities 
continued. 
13. CONEMAUGH RIVER LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Conemaugh River in Indiana and 
Westmoreland Counties, PA, 7.5 miles above junction of 
Conemaugh River and Loyalhanna Creek, which form 
the head of the Kiskiminetas River. It is about 2 miles 
northeast of Tunnelton, PA, and about 42 miles east of 
Pittsburgh, PA. Reservoir is in Westmoreland and Indiana 
Counties, PA. (See Geological Survey Charts for 
Latrobe, New Florence, and Elders Ridge, PA.) 
Existing Project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides 
and an earth embankment ending in right abutment. 
Authorized project is complete. Reservoir system is designed 
for protection of Pittsburgh and reduction of flood 
heights in upper Ohio Valley, generally. Land acquired 
for dam, reservoir and railroad relocation consists of 
7608.7 acres in fee and 522.8 acres in easements. Project 
authorized by Flood Control Acts of 1936 and 1938. For 
further project description see Annual Report for 1962, 
page 1217. 
Local cooperation. None required by law. 
18-6 
Licenses. A non-Federal hydropower project utilizing 
Conemaugh Lake was constructed downstream of the 
dam under FERC Licenses 3207. The 15-megawatt project 
began commercial operation on February 6, 1989. It 
is owned by Pennsylvania Renewable Resources, Inc. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control as required, and necessary repairs were 
made to structures and appurtenances. Estimated flood 
control benefits achieved by this reservoir for this fiscal 
year were $15,000; total flood control benefits through 
September 30, 1992 were $581,515,000. Activities under 
reservoir management program comprising sanitation 
measures, conservation, land management and operation 
and maintenance of public use facilities were continued. 
14. CROOKED CREEK LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Crooked Creek 6.7 miles above 
junction of creek with Allegheny River near Ford City, 
PA, and about 32 miles northeast of Pittsburgh, PA. (See 
Geological Survey Charts for Freeport and Elders Ridge, 
PA.) 
Existing project. A flood control reservoir dam of 
earth-fill type with separate uncontrolled saddle spillway 
and tunnel outlet works. Authorized project is complete. 
Reservoir is in operation as a unit of a coordinated reservoir 
system designed for protection of Pittsburgh and 
reduction of flood heights in upper Ohio Valley, generally. 
Construction of dam was started in March 1938 and 
completed in October 1940. Present project lands consist 
of 2,561.7 acres in fee and 100.22 acres in easements. 
Project was authorized by Flood Control Acts of 1936 and 
1938. For further project description see Annual Report 
for 1962, page 1213. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: A contract for construction of new 
main access roadway, awarded in January 1992 for 
$262,263, was 95% complete at end of FY 92. Reservoir 
was operated for benefit of flood control, as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
reservoir for this fiscal year were $6,000; total benefits 
achieved through September 30, 1992 were 
$130,044,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management, and operation and maintenance of 
public-use facilities continued. 
15. EAST BRANCH, CLARION RIVER 
LAKE, OHIO RIVER BASIN, PA 
Location. Dam is in Elk County, PA on East Branch 
of Clarion River above Middle Fork, 7.3 miles above 
junction of East and West branches of Clarion River at 
Johnsonburg, PA, and about 105 miles northeast of Pittsburgh, 
PA. Reservoir is in Elk County, PA. (See Geological 
Survey Chart for Mount Jewett, PA.)

PITTSBURGH, PA., DISTRICT 
Existing project. A reservoir for flood control and 
low-water regulation. Dam is rolled-earthfill type with 
gate-controlled concrete tunnel under right abutment 
and a paved uncontrolled spillway on left abutment slope. 
Authorized project is complete. Reservoir is in operation 
for low-water regulation purposes in Clarion River Valley 
below and for flood control as a unit of a coordinated 
reservoir system for protection of Pittsburgh and upper 
Ohio Valley, generally. Construction of dam was started 
in June 1947 and completed in July 1952. Present project 
lands consist of 287.2 acres in fee and 1,296.7 acres in 
easements. Project was selected for construction under 
general authorization for Ohio River Basin in Flood Control 
Acts of 1938 and 1944. For further project description 
see Annual Report for 1962, page 1206. 
Local Cooperation. None required by law. 
Operations during fiscal year. Operations and 
maintenance, general: Reservoir was operated for flood 
control and low-water regulation, as required; and necessary 
repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this reservoir 
during this fiscal year were $331,000; total benefits 
through September 30, 1992 were $33,740,000. Some 
reservoir management activity was performed throughout 
the year comprising sanitation measures, conservation, 
land management and operation of public-use 
facilities. Work was limited in scope as bulk of reservoir 
lands are owned by Commonwealth of Pennsylvania. 
16. KINZUA DAM AND 
ALLEGHENY RESERVOIR, 
OHIO RIVER BASIN PA AND NY 
Location. Dam site is on Allegheny River 9 miles 
above Warren, PA, and 198 miles above mouth of river at 
Pittsburgh, PA. Reservoir is in Warren and McKean 
Counties, PA., and Cattaraugus County, NY. (See Geological 
Survey Charts for Warren and Kinzua, PA-NY, 
and Randolph and Salamanca, NY.) 
Existing project. Reservoir provides flood control, 
low water regulation, and recreation. Dam consists of a 
combination concrete gravity structure and rolled earth 
embankment with gate-controlled spillway and discharge 
conduits controlled by slide-gates in gravity section. 
Construction of project, initiated in February 1960, 
is complete. Construction of dam was started in September 
1960 and completed in December 1965. Development 
of recreation area at Onoville under a cost-sharing agreement 
with Cattaragus County was completed in June 
1978. Land acquired for project consists of 2,651.5 acres 
in fee and easements over 22,159.1 acres. For further 
details see Annual Report for 1962, page 1202. Project 
was authorized by Flood Control Acts of 1936, 1938 and 
1941. 
Local cooperation. None required by law. 
Licenses. The Federal Power Commission granted a 
license to Pennsylvania Electric Company and Cleveland 
Electric Illuminating Company on December 28, 1965, for 
the joint construction, operation and maintenance of a 
325-megawatt pumped-storage installation (FPC Project 
No. 2280). The project is complete. 
Operation during fiscal year. Operation and maintenance, 
general: Reservoir was operated for benefit of 
flood control and low water regulation, as required, and 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
reservoir for this period were $4,000; total to end of this 
fiscal year, $350,317,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management, and operation and 
maintenance of public-use facilities continued. 
17. LOYALHANNA LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Loyalhanna Creek, 4.5 miles 
above junction of creek with Conemaugh River at 
Saltsburg, PA, and about 29 miles east of Pittsburgh, PA. 
Reservoir is in Westmoreland County PA. (See Geological 
Survey Chart for Latrobe, PA). 
Existing project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides, 
and an earth embankment section ending in left abutment. 
Authorized project is complete. Reservoir is in 
operation as a unit of a coordinated reservoir system 
designed for protection of Pittsburgh and reduction of 
flood heights in upper Ohio Valley, generally. Construction 
of dam was started in October 1939 and completed 
in June 1942. Land acquired for project consists of 3,331.7 
acres in fee and easements over 86.7 acres. Project was 
authorized by Flood Control Acts of 1936 and 1938. For 
further project description see Annual Report for 1962, 
page 1219. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control, as required, and necessary repairs were 
made to structures and appurtenances. Estimated flood 
control benefits achieved by this reservoir for this fiscal 
year were $10,000; total benefits to September 30, 1992; 
$170,924,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and maintenance of 
public-use facilities continued. 
18. MAHONING CREEK LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Mahoning Creek in Armstrong 
County, PA, 21.6 miles above junction of creek with 
Allegheny River. It is about 6.50 miles southeast of New 
Bethlehem, PA, and about 51 miles northeast of Pittsburgh, 
PA. Reservoir is in Armstrong, Indiana, and Jefferson 
Counties, PA. (See Geological Survey Charts for 
Rural Valley and Smicksburg, PA). 
Existing project. A flood control reservoir dam of 
concrete gravity type with a gate-controlled center spillway 
flanked by abutment sections joining valley sides. 
Authorized project is complete. Reservoir is in operation 
as a unit of a coordinated reservoir system designed for 
protection of Pittsburgh and reduction of flood heights in 
upper Ohio Valley, generally. Construction of dam 
started in February 1939 and was completed in June 
18-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
1941. Land acquired for projects consists of 2,519.36 
acres in fee and easements over 83.5 acres. Project was 
authorized by Flood Control Acts of 1936 and 1938. For 
further project description see Annual Report for 1962, 
page 1210. 
Local cooperation. None required at completed project. 
On November 4, 1977 a contract for Wildlife development 
at Mahoning Creek Lake was executed between 
the U.S. Government and the Pennsylvania Game Commission. 
Each party will pay or contribute in kind 50% of 
the first cost of initial wildlife development. Cost-sharing 
for construction of fishing access area awarded in September 
1980 was completed in July 1981 for $335,405.75. 
On June 7, 1979, a contract for fishing and boating 
development at Mahoning Creek Lake was executed between 
the U.S. Government and Pennsylvania Fish Commission. 
Each party will pay or contribute in kind 50% of 
the first costs of initial fishing and boating development. 
On September 9, 1980, a contract for camping and dayuse 
recreational development was executed between the 
U.S. Government and the County of Armstrong. Each 
party will pay or contribute in kind 50% of the first costs 
of initial camping and day-use recreational development 
and 50% of the costs for future development. Each cooperation 
authority is responsible for operation, maintenance 
and replacement without cost to the Government 
of all facilities developed with their support. 
Operations during fiscal year. Operations and 
maintenance, general: Reservoir was operated for benefit 
of flood control as required, and necessary repairs were 
made to structures and appurtenances. Estimated total 
flood damages prevented by this project through September 
30, 1992 were $163,265,000. Activities under 
reservoir management and maintenance for public-use 
facilities continued. 
19. MICHAEL J. KIRWAN DAM 
AND RESERVOIR, OHIO RIVER 
BASIN, OH 
Location. Dam site is on West Branch of Mahoning 
River which joins Mahoning River at Newton Falls, OH. 
It is 11 miles above mouth of branch and about 15 miles 
upstream from Warren, OH. Reservoir is in Portage 
County, OH. (See Geological Survey Charts for Ravenna, 
Garrettsville, Chagrin Falls, and Kent, OH.) 
Existing project. Reservoir provides flood control, 
low-water regulation and recreation. Dam consists of a 
rolled-earth embankment structure with gate-controlled 
outlet works and an uncontrolled side-hill spillway 
through left abutment. Authorized project is completed 
and in operation for flood control and low water regulation 
purposes. Land acquired for project consists of 
6,298.9 acres fee and easements over 27.9 acres. For 
further description see Annual Report for 1962, page 
1231 (West Branch Reservoir, Mahoning River, Ohio). 
Project was authorized by 1958 Flood Control Act (H. Doc. 
191, 85th Cong. 1st sess.), with local contribution requirements 
modified by Flood Control Act of 1960. Federal 
costs of completed project is $17,370,000. Local interests 
contributed $3,230,000 during period of construction 
bringing initial project cost to $20,600,000. 
Local cooperation. Local interests must contribute 
$5,200,000 for water pollution abatement and for municipal 
and industrial water supply purposes, of which 
$3,230,000 was paid in cash during construction. Unpaid 
balance at time project is placed in operation, $1,970,000, 
will be paid in cash at that time or on an annual basis. Of 
the unpaid balance of contributed funds due and payable, 
payment in full of Trumbull County's share in the amount 
of $663,040 has been received. Mahoning County elected 
to pay their share ($1,306,960) in 50 annual installments 
of $50,323.32, including interest, and has paid 
$671,571.02 toward principal to date. Local interests 
have now contributed $4,559,626.74 towards total of 
$5,200,000 non-Federal costs. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low-flow augmentation, as required, 
and necessary repairs were made to structures 
and appurtenances. Estimated flood control benefits 
achieved by this project for this fiscal year are $320,000. 
Total flood control benefits for this reservoir through 
September 30, 1992 were $90,199,000. Activities under 
reservoir management program comprising sanitation 
measures, conservation, land management, and operation 
and maintenance of public-use facilities continued.
This work was limited in scope as State of Ohio has 
jurisdiction over most of the recreation in reservoir area. 
20. MOSQUITO CREEK LAKE, 
OHIO RIVER BASIN, OH 
Location. Dam is on Mosquito Creek, 9 miles above 
junction of creek with Mahoning River at Niles, OH, and 
about 18 miles northwest of Youngstown, OH. (See Geological 
Survey Charts for Bristolville and Kinsman, OH, 
and Pennsylvania.) 
Existing project. A reservoir for flood control, lowwater 
regulation and water supply storage. Dam is 
rolled-earthfill type with outlet facilities through dam, 
and an uncontrolled natural wasteway to discharge overflow 
from reservoir. Authorized project is complete and 
in operation for flood control and low-water regulation 
purposes in industrialized Mahoning and Beaver Valleys 
below. Construction of dam was started in July 1943 and 
was ready for beneficial use in January 1944. Land acquired 
for project consists of 11,180.4 acres in fees and 
easements over 276.0 acres. State of Ohio has a license 
from Secretary of the Army for development and operation 
of recreation facilities in reservoir area. Project was 
selected for construction under general authorization for 
Ohio River Basin in 1938 Flood Control Act. For further 
project description see Annual Report for 1962, page 
1228. 
Local cooperation. None required at completed project; 
however, future recreational developments are subject 
to certain conditions of non-Federal cost-sharing 
under Federal Water Project Recreation Act of 1965. 
Operations during fiscal year. Operation and 
maintenance, general: Reservoir was operated for benefit 
of flood control and low-flow regulation as required, and 
18-8

PITTSBURGH, PA., DISTRICT 
necessary repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this 
project for this fiscal year were $48,000. Total flood control 
benefits for this reservoir through September 30, 
1992 were $71,257,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and 
maintenance of certain public-use facilities continued. 
This work was limited in scope as State of Ohio has 
jurisdiction over most of the recreation in reservoir area. 
21. OHIO RIVER BASIN 
(PITTSBURGH DISTRICT) 
Location. A series of dikes, floodwalls, channel improvements, 
and reservoirs/lakes in Ohio River Basin 
within Pittsburgh District. 
Existing project. Individual projects considered in 
comprehensive plan within Pittsburgh District. (See Tables 
18-B, 18-E and 18-K on Acts authorizing existing 
projects, local protection projects and reservoirs.) 
Operations during fiscal year. New work: None by 
the United States except as stated in individual projects. 
Completed local protection projects operated and maintained 
by local interests, including those projects for 
which individual reports have been included, prevented 
flood damages of an estimated $4,944,000 during this 
fiscal year. Total flood damages prevented through September 
30, 1992 are $743,975,000. 
22. SHENANGO RIVER LAKE, OHIO 
RIVER BASIN, PA AND OH 
Location. Dam is on Shenango River about 0.8 mile 
above Sharpsville, PA, and about 33 miles above junction 
of river with Mahoning River, which unite near New 
Castle, PA, to form Beaver River. Reservoir is in Mercer 
County, PA and Trumbull County, Ohio. (See Geological 
Survey Chart for Kinsman, Ohio, and Shenango, PA.) 
Existing project. A reservoir for flood control, lowflow 
augmentation and recreation. Dam consists of a 
concrete gravity structure with gate-controlled outlet 
works and an uncontrolled center spillway section. 
Authorized project is complete. Reservoir is in operation 
for low-water regulation purposes in Shenango River 
valley below and for flood control as a unit of a coordinated 
reservoir system for protection of Shenango River 
valley and the Beaver and upper Ohio River Valley, 
generally. Construction of dam was started in March 
1963 and completed in May 1965. Land acquired for 
project consists of 14,221.06 acres in fee and easements 
over 239.88 acres. Future work consists of completion of 
project lands of any additional recreation facilities as 
required to serve the public needs. For further project 
description, see Annual Report for 1962, page 1230. Project 
was authorized by 1938 Flood Control Act. 
Local cooperation. None required by law. 
Operations during fiscal year. Operations and 
maintenance, general: A contract for maintenance area 
improvements and new stacking lane, awarded in June 
1992, was 15% complete at end of FY 92. Reservoir was 
operated for benefit of flood control and low-flow augmentation, 
as required, and necessary repairs were made to 
structures and appurtenances. Estimated flood control 
benefits achieved in FY 92 were $235,000; total benefits 
achieved through September 30, 1992 were $26,022,000. 
Activities under reservoir management program comprising 
sanitation measures, conservation, land management 
and operation and maintenance continued. 
23. STONEWALL JACKSON LAKE, 
OHIO RIVER BASIN, WV 
Location. In Lewis County, North Central West Virginia, 
on the West Fork River, which joins the Tygart 
River at Fairmont, West Virginia to form the Monongahela 
River. Damsite is located at Brownsville, West Virginia, 
about 4 miles south of Weston and 72 miles above 
mouth of West Fork River at Fairmont, WV. (See Geological 
Survey Charts for Weston and Crawford, WV.) 
Existing project. Provides for construction of a reservoir 
for flood control, water supply, water quality control, 
area redevelopment and recreation. Dam is concrete 
gravity type, 95 feet high and 620 feet long. Outlet works 
consist of five multi-level sluices, spillway is uncontrolled. 
Storage capacity is 74,650 acre-feet controlling an 
area of 102 square miles. Project was authorized by 1966 
Flood Control Act. Estimated initial Federal cost for new 
work (1991) is $231,000,000 (includes an estimated 
$24,900,000 reimbursement by non-Federal interests.) 
Surface land acquired for project consists of 20,451 
acres. 
Local cooperation. Local interests are required to 
make arrangements for repayment, under the provisions 
of the Water Supply Act of 1958, as amended, of that part 
of the construction cost and annual operation, maintenance 
and replacement costs allocated to municipal and 
industrial water supply, an amount presently estimated 
at $4,350,000 for construction; and $15,000 annually for 
operations, maintenance and replacements. Also, in accordance 
with Federal Water Project Recreation Act, 
local interests are required to administer project land and 
water areas for recreation and fish and wildlife enhancement, 
pay, contribute in kind or repay (which may be 
through user fees) with interest, one-half of the separable 
first costs of the reservoir project allocated to recreation 
and fish and wildlife enhancement, an amount presently 
estimated at $24,810,000, bear all costs of operation, 
maintenance and replacement of recreation and fish and 
wildlife land and facilities, the amount involved being 
currently estimated on an average annual basis to be 
$457,000, exercise to the full extent of their legal capability, 
control against removal of streamflow made available 
for water quality control; and contribute to the control of 
pollution of streams subject to low-flow augmentation by 
adequate treatment or other methods of controlling 
wastes at their source. The requirements of Section 221 
were amended in 1971 to exempt assurances for future 
demands for water supply pursuant to the Water Supply 
Act of 1958 from the contractual requirements of the Act. 
Accordingly, the city of Weston, West Virginia, has provided 
assurances that it will enter into a water supply 
contract with the Department of the Army within a period 
of time which will permit paying out the costs allocated 
to the water supply storage within the life of the project. 
A recreation cost-sharing contract, in accordance with 
18-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
the requirements of the Federal Water Project Recreation 
Act, P.L. 89-72, was executed by the State of West Virginia 
on March 27, 1977. Local cooperation assurances 
for recreation cost-sharing were executed by the Governor 
and Attorney General of West Virginia on May 29, 
1973. In this connection, Section 8 of P.L. 92-222 deleted 
the requirement that the State of West Virginia "hold and 
save the United States free from damages resulting from 
water rights claims due to construction and operation of 
the project." Legislation relieving Stonewall Jackson 
Lake, WV, project of the requirements of Section 221, P.L. 
96-611 was contained in Water Resources Development 
Act of 1974 signed by the President on March 7, 1974. 
Operations during fiscal year. New Work: The 
1992 Energy and Water Appropriations Act amends the 
1977 cost-sharing contract to include all of the facilities 
requested by the State (lodge, cabins) except the golf 
course. The District and the State completed revisions to 
the project Master Plan to include these additional facilities. 
A contract for bridge repairs at the dam access road, 
awarded in FY 1990 for $139,366 was completed in FY 92. 
Estimated flood control benefits achieved for this project 
for FY 92 were $4,297,000. Total flood control benefits 
for the reservoir through September 30, 1992 were 
$45,702,000. 
24. TIONESTA LAKE, 
OHIO RIVER BASIN, PA 
Location. Dam is on Tionesta Creek, 1.25 miles above 
junction of creek with Allegheny River at Tionesta, PA, 
and about 78 miles northeast of Pittsburgh, PA. Reservoir 
is entirely in Forest County, PA. (See Geological 
Survey Charts for Tionesta, Tidioute and Sheffield, PA.) 
Existing project. A flood control reservoir dam of 
earthfill type with separate uncontrolled saddle spillway 
and tunnel outlet works. Authorized project is complete. 
Reservoir is in operation as a unit of a coordinated reservoir 
system designed for protection of Pittsburgh and 
reduction of flood heights in upper Ohio Valley, generally. 
Construction of dam was started in May 1938 and completed 
in January 1941. Land acquired for project consists 
of 2,797.3 acres in fee and easements over 13.1 acres. 
Future work consists of provision on project lands of 
additional recreational facilities as required to serve public 
needs. Project was authorized by Flood Control Acts 
of 1936 and 1938. For further project description see 
Annual Report for 1962, page 1203. 
Local cooperation. None required by law. 
Operations during fiscal year. Operation and 
maintenance general: Reservoir was operated for benefit 
of flood control and low-flow augmentation, as required, 
and necessary repairs were made to structures and appurtenances. 
Total flood control benefits for this reservoir 
through September 30, 1992 were $178,998,000. Activities 
under reservoir management program comprising 
sanitation measures, conservation, land management 
and operation and maintenance of public-use facilities 
continued. 
18-10
25. UNION CITY DAM, 
OHIO RIVER BASIN, PA 
Location. In Erie County, northwestern Pennsylvania, 
on French Creek, a tributary of Allegheny River. 
Damsite is 24 miles upstream from Cambridge Springs, 
PA, and 41 miles upstream from Meadville, PA. (See 
Geological Survey Chart for Union City, PA - NY.) 
Existing project. A flood control reservoir dam of 
earth embankment nongated type with uncontrolled 
side-channel spillway. Outlet works consist of a lower 
outlet located in valley floor constructed of reinforced 
concrete conduit 8 feet by 4.5 feet and an upper outlet 
consisting of an uncontrolled slot 9.5 feet wide through 
the north end of the ogee weir in the spillway. Dam is 
1,420 feet long at top rising 88 feet above streambed and 
provides gross capacity of 47,640 acre-feet from a drainage 
area of 222 square miles. Project authorization was 
modified to provide for a conservation pool and addition 
of recreation facilities. On November 5, 1974, a referendum 
proposal was defeated by the constituents of Erie 
County in regard to the cost-sharing for construction of 
recreation facilities. In view of the foregoing, all action 
toward implementation of the authorized project modification 
was discontinued. Reservoir is operated as one of 
a two-reservoir system for reduction of flood stages in 
French Creek Basin between damsite and mouth, Allegheny 
River from Franklin, PA, to Pittsburgh, PA, inclusive, 
and upper Ohio River Valley. Initial highway 
relocations were completed in October 1968 and remaining 
highway relocations were completed in May 1972. 
Construction of the dam was started in July 1968 and 
completed in September 1971. Land acquired for project 
consists of 161.4 acres in fee and easements over 2,410.3 
acres. Existing project was authorized by 1962 Flood 
Control Act. 
Local cooperation. Local interests are required to 
inform affected interests in French Creek Basin at least 
annually, that the system of reservoirs of which Union 
City Dam is a part, will not provide protection against 
maximum floods. On November 10, 1964 the Department 
of Forests and Waters of the Commonwealth of Pennsylvania 
furnished formal assurances of local cooperation in 
respect to notifying local interests at least annually that 
the system of reservoirs will not provide protection 
against maximum floods. A referendum on the ballot 
during the November 1974 election regarding the approval 
to cost-share the maintenance of a summer pool 
was defeated by the local voters. 
Operations during fiscal year. Operation and 
maintenance, general: Maintenance of the structure and 
appurtenances was performed as required. This dam 
acted as an uncontrolled detention type dam during the 
fiscal year. Estimated flood control benefits achieved by 
this reservoir for this period were $10,000. Total flood 
control benefits for this reservoir through September 30, 
1992 were $18,249,000. 
26. WOODCOCK CREEK LAKE, 
OHIO RIVER BASIN, PA 
Location. In Crawford County, northwestern Pennsylvania, 
on Woodcock Creek, a tributary of French

PITTSBURGH, PA., DISTRICT 
Creek. Damsite is about 4.1 miles above mouth of Woodcock 
Creek and about 5 miles northeast of Meadville, PA. 
(See Geological Survey Chart for Meadville, PA.) 
Existing project. A flood-control reservoir dam of 
rolled-earth embankment type, gate-controlled outlet 
works with a 6 foot-wide by 7.75 foot-high conduit and 
uncontrolled saddle spillway on the left abutment. Dam 
is 4,650 feet long at top rising 90 feet above streambed 
and provides for gross capacity of 20,000 acre-feet from a 
drainage area of 46 square miles. Reservoir is operated 
as one of a two-reservoir system for reduction of flood 
stages in French Creek Basin between damsite and 
mouth. Allegheny River from Franklin, PA, to Pittsburgh, 
PA, inclusive, and upper Ohio River Valley. 
Authorized project is complete. Construction of dam was 
started in July 1970 and completed in July 1973. Land 
acquired for project consists of 1,731.5 acres in fee and 
easements over .56 acres. Project was authorized for flood 
control and recreation by 1962 Flood Control Act. Storage 
for water quality control was added to the project during 
the preconstruction planning stage. 
Local cooperation. Local interests must inform affected 
interests in French Creek Basin at least annually, 
in a manner satisfactory to District Engineer, that a 
system of reservoirs of which Woodcock Creek is a part, 
will not provide protection against maximum floods. 
Pennsylvania Department of Forests and Waters assumed 
responsibility of local cooperation for project. 
Operations during fiscal year. Operation and 
maintenance, general: Maintenance of the structure and 
appurtenances was performed as required. Estimated 
flood control benefits achieved by this project for FY 92 
were $2,000. Total flood control benefits achieved by this 
reservoir through September 30, 1992 were $2,600,000. 
Activities under reservoir management program comprising 
sanitation measures, conservation, land management 
and operation and maintenance of public use 
facilities continued. 
27. YOUGHIOGHENY RIVER LAKE, 
OHIO RIVER BASIN, PA AND MD 
Location. Dam is on Youghiogheny River about 74.2 
miles above its junction with Monongahela River at 
McKeesport, PA. It is 1.2 miles upstream from Confluence, 
PA, and about 57 miles southeast of Pittsburgh, PA. 
Reservoir is in Fayette and Somerset Counties, PA, and 
Garrett County, MD. (See Geological Survey Charts for 
Confluence, PA, Accident, MD, West Virginia and Pennsylvania.) 
Existing project. Reservoir for flood control, low-flow 
augmentation, and pollution abatement purposes. Dam 
is rolled-earthfill type with separate uncontrolled side 
channel spillway and tunnel outlet works. Authorized 
project is complete. For flood control, reservoir is operated 
as a unit of a coordinated reservoir system designed 
for protection of Pittsburgh and reduction of flood heights 
in upper Ohio Valley, generally. Construction of dam was 
started in June 1940 and completed in May 1944. Land 
acquired for project consists of 3,914.9 acres in fee and 
easements over 0.62 acre. A license was issued to the 
Commonwealth of Pennsylvania covering fish conservation 
and management in Pennsylvania portion of reservoir. 
Future work consists of provision on project lands of 
additional recreational and sanitary facilities as required 
to serve the public needs. 
Project was selected for construction under general 
authorization for Ohio River Basin in 1938 Flood Control 
Act. For further project description see Annual Report for 
1962, page 1223. 
Local cooperation. None required. 
Licenses. A non-Federal hydropower project utilizing 
releases from Youghiogheny River Lake was constructed 
in accordance with FERC License 3623. D/R 
Hydro Company is the authorized representative of the 
Licensee, Youghiogheny Hydroelectric Authority, and is 
responsible for operation of the plant. It has a 10-megawatt 
capacity. The plant began commercial operation on 
December 7, 1989. 
Operations during fiscal year. Reservoir was operated 
for benefit of flood control, as required, and necessary 
repairs were made to structures and appurtenances. 
Estimated flood control benefits achieved by this reservoir 
for this period were $9,000. Total flood control benefits 
achieved by this project through September 30, 1992 
were $160,717,000. Activities under reservoir management 
program comprising sanitation measures, conservation, 
land management and operation and 
maintenance of public use facilities continued. 
28. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to furnish assurances that 
they will maintain and operate certain local protection 
projects after completion in accordance with regulations 
prescribed by Secretary of the Army. District Engineers 
are responsible for administration of these regulations 
within boundaries of their respective districts. Inspections 
were made of completed units transferred to local 
interests for maintenance and operation and local interests 
were advised, as necessary, of measures required to 
maintain these projects in accordance with standards 
prescribed by regulations. (See Table 18-L for dates of 
inspections.) 
Costs for this fiscal year, $92,015. Total cost to September 
30, 1992 was $1,407,562. 
29. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 18-E on other authorized flood control projects. 
30. FLOOD CONTROL WORKS 
UNDER SPECIAL AUTHORIZATION 
For flood control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended 
(preauthorization) 
See Table 18-M. 
For emergency bank protection (Sec. 14 of 1946 
Flood Control Act, Public Law 526, 79th Cong.) 
See Table 18-M. 
18-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Flood control and coastal emergencies (Public 32. COLLECTION AND STUDY 
Law 99, 84th Cong., and antecedent legislation.) OF BASIC DATA 
Corps Statutory Authorities 
Activities in Support of Others 
Facilities 
Inspections 
Total Cost for Fiscal Year: 
General Investigations 
3L SURVEYS 
Navigation studies 
Flood control studies 
Coordination Studies with other agencies 
Interagency Water Resource Development 
Special investigations 
Federal Energy Regulatory Commission 
Special Studies 
Total cost for fiscal year 
$249,730 
48,827 
5,456 
$$332211,,99747641 
$ 0 
1,165,588 
67,904 
31,994 
128,008 
34,967 
560 
$1,429,021 
Costs this fiscal year were $133,130 for flood plain 
management services and $19 for related hydrologic 
studies. 
33. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
Locks and Dams 2, 3 and 4, 
Monongahela River 
Rochester, PA 
Saw Mill Run, Pittsburgh, PA 
Total cost for fiscal year 
$1,346,910 
10,974 
315,453 
$1,673,337 
34. RESEARCH AND DEVELOPMENT 
None. 
18-12

PITTSBURGH, PA., DISTRICT 
TABLE 18-A C 
See 
Section 
In Text Project 
Navigation - Locks and Dams 
1. Allegheny River 
PA 
3. Monongahela 
River, PA and 
WV 
5. Tart Lake, 
Flood Control - Local Protection 
7. Chartiers 
Creek, PA 
(Federal Funds) 
Contributed 
unds) 
8. Elkins, WV 
9. Johnstown, PA 
10. Punxsutawney, 
Ohio River 
Basin, PA 
11. Turtle Creek, 
PA 
Flood Control - Reservoirs 
12. Berlin Lake 
Ohio River 
Basin, OH 
COST AND FINANCIAL STATEMENT 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. (O&M) 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. (O&M) 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
FY 89 
7,375,589 
7,318,418 
17,218,000 
17,718,346 
11,866,029 
11,873,521 
FY 90 
5,976,672 
6,006,794 
34,410,000 
32,750,727 
11,592,422 
11,590,143 
FY91 
8,827,600 
8,778,797 
54,996,000 
58,104,503 
11,638,300 
11,711,453 
699,244 755,668 755,900 
688,409 766,703 763,615 
-- -3,000 -- 
-- -- 12,561 
-- -- -5,221 
5,000 
3,704 
236,533 
211,155 
4,000 
1,247 
130,000 
254,486 
1,517,900 
1,498,246 
-795 
161 
-- 
2,200 
3,223 
50,152 26,000 
74,649 28,798 
-- 900,000 
-- 497,516 
38,909 25,000 
37,485 29,237 
222,000 345,000 
290,489 344,075 
FY92 
Total Cost to 
Sept. 30, 
1992 
-- 18,157,8601 
-- 18,157,860 
7,902,900 101,982,5232 
7,982,512 101,953,665 2 
72,408,000 321,394,085 3 
72,331,548 320,733,4914 
12,298,200 216,715,5576 
12,195,303 216,583,533 
-- 15,857,000 
-- 15,857,000 
-- 19,077,9327 
-- 19,077,932 
784,100 13,342,4518 
777,643 13,332,280 
60,000 60,000 
19,820 19,820 
u
2
2
2
2 
-- 26,583,186 
10,329 26,583,077 
-- 4,219,967 
-- 4,204,498 
-- 1,772,627 
-- 1,772,627 
4,800 269,192 
944 265,286 
-- 8,865,388 
-- 8,865,388 
780,800 5,440,190 
741,749 5,400,688 
552,000 1,452,000 
925,729 1,423,245 
-- 3,586,10710 
-- 3,586,10710 
209,800 1,312,59711 
203,412 1,306,09411 
z1142,,102010 1166,,552265,,365124338 
1,613,532 1,347,400 1,829,500 
1,669,700 1,348,713 1,734,360 
8,739,98712 
8,739,987 
24,091,11513 
23,980,303 
18-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-A COST AND FINANCIAL STATEMENT (Continued) 
See Total Cost to 
Section Sept. 30, 
In Text Project 
13. Conemaugh 
River Lake, Ohio 
River Basin, PA 
14. Crooked Creek 
Lake, Ohio 
River Basin, PA 
15. East Branch, 
Clarion River 
Lake, Ohio 
River Basin, PA 
16. Kinzua Dam and 
Allegheny 
Reservoir, Ohio 
River Basin, PA 
and NY 
17. Loyalhanna 
Lake, Ohio River 
Basin, PA 
18. Mahoning Creek 
Lake, Ohio 
River Basin, PA 
19. Michael J. Kirwan 
Dam and 
Reservoir, Ohio 
River Basin, OH 
20. Mosquito Creek 
Lake, Ohio River 
Basin, OH 
21. Ohio River Basin 
Pittsburgh, PA 
District Consolidated 
22. Shenango River 
Lake, Ohio River 
Basin, PA 
23. Stonewall Jackson 
Lake, Ohio 
River Basin, WV 
Funding 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
11 
1
1 
FY 89 FY 90 FY 91 FY92 1992 
--- -- -- 46,012,41114 
-- -- -- -- 46,012,411 
868,671 1,037,626 982,600 1,147,700 13,176,176 
847,810 1,038,306 1,013,042 1,144,476 13,162,266 
-- -- 8,409 -- 4,482,93315 
-- -- 41,226 10,184 4,482,9331 
,383,449 1,346,788 1,167,600 1,621,400 22,498,75816 
,391,136 1,331,971 1,190,264 1,597,259 22,446,04916 
-- -- -- -- 9,539,58617 
-- -- -- -- 9,539,586 
804,600 1,046,827 1,010,500 860,900 12,506,28418 
819,123 1,051,905 997,041 854,531 12,473,64618 
-- -- -- -4,000 109,305,07619 
-- -- 6,184 686 109,305,07619 
,133,200 1,197,365 1,290,700 1,384,500 21,817,143 
,111,672 1,196,098 1,284,595 1,397,443 21,793,898 
-- -19,000 0 -- 2,921,000 
279 -- 442 -- 2,921,000 
-- -- -- -- 5,727,53120 
-- -- -- -- 5,727,531 
880,449 1,003,288 832,400 1,041,700 16,118,39321 
872,417 979,047 9788977,0224,,711 9977 11,,003311,,225555 116,0,09977,,666688 1872,417 
55 
720,708 
733,871 
--- 686,538 
691,431 
617,100 
619,118
-- 
-- 
735,300 653,238 807,900 
710,880 678,474 795,169 
824,400 794,907 882,200 
815,786 805,845 887,672 
1,812,800 
1,872,160 
2,428,000 
12,400,043 
749,800 
758,230 
21 
1,810,730 
1,800,274 
8,539,434 
6,413,720 
800,213 
770,106 
5,624 
1,811,000 
1,812,040 
-1,700,000 
1,120,438 
773,400 
805,547 
1, 
-. 7,144,97322 
-- 7,144,97323 
-- 7,144,973 
782,000 11,808,962 
775,977 11,801,186 
-- 47,033 
-- 47,033 
-- 17,376,09724 
--. 17,376,09724 
745,700 11,101,23425 
756,177 11,086,154 25 
---- 44,,225533,,002299 2266 2 
121,400 11,622,571 
985,943 11,482,007 
-- 985,19727 
-- 985,1972 
-10,000 
1,662 
2,163,300 
1,999,087 
14,000 
432,797 
909,900 
882,370 
40,217,20128 
40,217,20128 
28,302,64729 
28,099,91929 
209,169,634 
208,608,154 
3,889,813 
3,859,782 
18-14

PITTSBURGH, Pk, DISTRICT 
TARTBE 18-A 
See 
Section 
In Text Project 
24. Tionesta Lake, 
Ohio River 
Basin, PA 
25. Union City 
Dam, Ohio 
River Basin, PA 
COST AND FINANCIAL STATEMENT (Continued) 
Funding 
New Work 
Aprop. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
26. Woodcock Creek 
Lake, Ohio 
River Basin, PA 
27. Youghiogheny 
River Lake 
Ohio River 
Basin, PA and 
MD 
FY 89 
230 
FY 90 FY 91 FY92 
Total Cost to 
Sept. 30, 
1992 
-- 7,792,37830 
-- 7,792,37831 
1,308,979 1,113,296 1,017,500 1,106,900 18,084,92832 
1,316,393 1,123,154 1,000,711 1,137,445 18,076,49032 
-- -- -- -- 14,559,800 
-- -- -- -- 14,559,800 
244,547 221,904 213,400 260,000 4,673,668 
262,236 221,268 218,242 254,276 4,665,230 
-- -8,409 -- 20,545,06533 
-- 20,545,0654 
775,600 675,988 754,100 655,100 9,287,157s 
769,170 686,627 754,720 647,790 9,274,85135 
---- -- -- 12,521,16736 
-- -- -- --. 12,521,16736 
2,271,800 1,348,398 1,485,300 1,696,700 26,484,16337 
2,287,890 1,372,982 1,484,772 1,671,995 26,437,296 3 
1. Includes $2,453,737 from emergency relief funds and 
$1,250,049 from public works funds. 
2. Includes $64,365 public works acceleration, executive 
funds (1963) and $191,400 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. Also includes 
$995,000 appropriated through FY 92 and $987,603 
expended through FY 92 for major maintenance at L/D 2, 3 
and 4. 
3. Includes $5,420,541 for new work for previous projects, 
$77,627,400 appropriated to date for Point Marion, I/D 8, PA 
($38,677,400 - CG funds, $38,950,000 from the Inland Waterways 
Trust Fund), and $110,563,600 appropriated to date for 
Gray's Landing, L/D 7, PA ($56,818,600- CG funds, $53,745,000 
from the Inland Waterways Trust Fund). Also includes AE & 
D costs for Gray's Landing ($803,000) and Point Marion 
($618,758). 
4. Includes $77,362,465 expended to date on Point Marion, 
L/D 8, PA ($38,433,779- CG funds, $38,928,686 from the Inland 
Waterways Trust Fund), and $114,167,943 expended to date for 
Gray's Landing, LID 7, PA ($56,428,223- CG funds, $57,739,720 
from the Inland Waterways Trust Fund). Also includes AE & D 
costs for Gray's Landing ($803,000) and Point Marion 
($618,758). 
5. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$582,000 provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds. 
6. Includes $22,549 public works acceleration, executive 
funds (1963), $742 for maintenance for previous project and 
$464,508 provided from the Productive Employment Appropriations 
Act (PL 98-8) 1983 funds. 
7. Includes $1,999,995 emergency relief funds, $10,000,000 
public work funds, $234,000 Code 711 funds and $412,088 Code 
713 funds; excludes $409,622 contributed by local interest. 
8. Includes $89,000 provided from the Productive Employment 
Appropriations, Act (PL 98-8) 1983 funds. 
9. Includes $33,423 from emergency relief funds. 
10. Excludes $180,485 for new work expended from contributed 
funds. 
11. Includes $283,988 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
12. Includes $1,542,500 Code 711 funds, $809,700 Code 712 
funds and $99,111 Code 713 funds; excludes $100,000 contributed 
by local interest. 
13. Includes $40,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
14. Includes $5,351 from emergency relief funds and 
$328,000 Code 711 funds. 
15. Includes $63,788 from emergency relief funds. Also 
includes $278,044 Code 711 funds. 
16. Includes $45,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
17. Includes $156,812 Code 711 funds. 
18. Includes $322,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
19. Includes $2,791 from emergency relief funds, $14,622 
Code 711 funds and $568,265 Code 713 funds; excludes 
$389,370 contributed by local interest. 
20. Includes $7,339 from emergency relief funds and 
$274,669 Code 711 funds. 
21. Includes $256,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
22. Includes $25,671 emergency relief funds, $162,381 Code 
711 funds and $561,247 Code 713 funds; excludes $500,086 
contributed by local interests. 
23. Includes $25,671 emergency relief funds, $162,381 Code 
711 funds and $561,247 Code 713 funds; excludes $456,611 
contributed by local interests. 
24. Includes $74,900 Code 711 funds; excludes 
$4,532,929.02 for new work contributed by local interest. 
25. Includes $315,500 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
26. Includes $122,729 Code 711 funds and $94,900 Code 713 
funds. 
27. Includes $8,914 from emergency relief funds. 
18-15 
i L i/i/ iV-L i 
i v; ir v r s s a yi vi a -'s 
Y Y i i Y

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-A COST AND FINANCIAL STATEMENT (Continued) 
28. Includes $1,730,100 Code 711 funds and $1,618,300 
Code 713 funds. 
29. Includes $152,000 provided from the Productive Employment 
Appropriations Act. (PL 98-8) 1983 funds. 
30. Includes $2,303,076 Code 711 funds ($256,760 provided 
from the Productive Employment Appropriations Act PL 98-8, 
1983 funds), $275,900 Code 712 funds, and $24,201 emergency 
relief funds. 
31. Includes $2,303,077 Code 711 funds, ($256,531 provided 
from the Productive Employment Appropriations Act PL 98-8, 
1983 funds), $275,900 Code 712 funds, and $24,201 emergency 
relief funds. 
32. Includes $203,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
33. Includes $1,671,366 Code 711 funds. 
34. Includes $1,671,366 Code 711 funds. 
35. Includes $85,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds). 
36. Includes $2,846,263 Code 711 funds ($293,000 provided 
from the Productive Employment Appropriations Act. (PL 98-8) 
1983 funds). 
37. Includes $591,000 provided from the Productive Employment 
Appropriations Act (PL 98-8) 1983 funds. 
38. Includes $15,350,352 original construction cost. 
18-16

PITTSBURGH, PA., DISTRICT 
TABLE 18-B AUTHORIZATION LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug 5, 1886 
June 3, 1896 
July 25, 1912 
July 3, 1930 
Aug 30, 19 3 51 
Aug 30, 19 3 51 
June 26, 19342 
3. 
Mar 3, 1899 
June 13, 1902 
Mar 3, 1905 
Mar 3, 1905 
Mar 2, 1907 
Mar 4, 1913 
Sep 22, 1922 
July 3, 1930 
Jan 31, 19313 
June 26, 19342 
ALLEGHENY RIVER, PA. (See Section 1 of Text) 
For lock and dam 1. (Fixed dam contemplated. Sep 29, 1891 
Secretary of War authorized change to a moveable dam.) 
For locks and dams 2 and 3. 
For locks and dams 4 to 8 inclusive. 
For a depth of 9 feet in the lower 61 miles. 
Replace lock and dam 1 by a dredged channel, 9 feet deep and 
200 feet wide up to lock 2, and construct new locks and 
dams 2 and 3, to replace existing locks and dams 2 and 3. 
Construct lock and dam 9, raising crest of dam 8, and dredging 
a navigable channel to head of pool 8. 
Operation and care of locks and dams provided for with funds 
from War Department appropriation for rivers and harbors. 
MONONGAHELA RIVER, PA AND WV 
Enlarge and improve lock and dam 6; additional works at lock 
3; new repair steamer and new dredge boat with equipment; 
all at an estimated cost of $185,556. 
Rebuild lock and dam 2 at estimated cost of $655,961. (Estimate 
increased in 1910 to $698,961.) 
Acquisition of land and additional improvements at 5 and 6 at 
a cost of $7,850. 
Rebuild lock and dam 3 at estimated cost of $589,196. 
Reconstruct lock and dam 5 at estimated cost of $756,042. 
Reconstruct lock and dam 6 at estimated cost of $356,400. 
(Estimate increased in 1916 to $418,860.) 
Additional improvements at estimated cost as follows: 
Guide walls and guard walls, 1 to 6, $1,255,130; 
Lengthen land chamber of lock 3 to 720 feet, $787,722; 
New chamber (360 feet long), lock 4, $699,786; 
Lock and dam 7, $1,161,241; Lock and dam 8, $1,165,758; 
Lock and dam 7 (second chamber), $419,126; 
Lock and dam 8 (second chamber), $504,465; 
Reconstruction dam 4, $397,211; Marine ways, repair 
plant, office and warehouse, $250,000, for a total 
of $6,640,439. 
Construct new locks and dam 2.5 miles below existing structure, 
at estimated cost of $2,175,000 in lieu of work authorized 
at old lock and dam 4. 
Chief of Engineers authorized to locate new locks and dam 4 
above existing structure and on such site as they may deem 
most desirable. 
Operation and care of locks and dams provided for with funds 
from War Department appropriations for rivers and harbors. 
Annual Report 1886, 
. 1545, 
Annual Report 1891, 
p. 2366 
H. Doc. 204, 54th Cong., 
1st Sess., and Annual 
Report 1896, p. 2212 
H. Doc. 540, 62d Cong., 
2d Sess. 
H. Doc. 356, 71st Cong., 
2d Sess. 
Rivers and Harbors 
Committee, Doc. 16, 
72d Cong., 1st Sess. 
H. Doc. 721, 71st Cong., 
3d Sess., and Rivers and 
Harbors Committee, Doc. 
27,73d Cong., 2d Sess. 
Annual Report 1897, 
p. 2423 
Annual Report 1909, 
p. 1756 
Annual Report 1904, 
p. 460 
H. Doc. 209, 58th Cong., 
2d Sess. 
H. Doc. 209, 58th Cong., 
2d Sess. 
H. Doc. 1217, 62d Cong., 
3d Sess. 
H. Doc. 288, 67th Cong., 
2d Sess. 
Rivers and Harbors 
Committee, Doc. 22, 
70th Cong., 2d Sess. 
18-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-B AUTHORIZATION LEGISLATION (Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
May 17, 1950 
Nov 17, 1986 
Jan 11, 1934 
Aug 30, 1935 
Jun 28, 1938 
Jun 28, 1938 
Jun 28, 1938 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Modification of existing project as follows: 
Provide 2 new locks and dams similar to Morgantown lock 
and dam to replace existing locks and dams 12 to 15 inclusive. 
Provide a movable crest on existing dam 8 to raise existing 
pool-full elevation 4 feet. 
Provide a navigation channel of 300-foot minimum bottom 
width and a 9-foot project depth above lock and dam 8. 
Provide an extension of navigable channel of upper Monongahela 
River, into lower Tygart River for 2.1 miles at a 
maximum bottom width of 200 feet and a 9-foot project 
depth. 
Construct new lock and dam 7 (Grays Landing Lock and Dam) 
as follows: 
The Grays Landing Lock and Dam will be located 3.0 miles 
downriver from existing Lock and Dam 7. It will consist of a 
single lock chamber, 84 feet wide by 720 feet long, with a 
fixed crest dam 576 feet in length. The existing Maxwell 
Pool at elevation 763.0 will be shortened three miles and 
the existing Pool 7 at elevation 778.0 will be extended downriver 
to the new dam. There will be no change in pool elevation 
above existing Dam 7. Upon completion of the new 
replacement lock and dam, existing Lock and Dam 7 will be 
removed. Total authorized cost is $123,000,000. 
Replace existing 56'x360' lock chamber at Point Marion Lock 
and Dam (Lock and Dam 8) with new 84'x720' chamber. Existing 
movable crest dam to remain; no change in pool elevations. 
Total authorized cost is $82,900,000. 
TYGART RIVER LAKE, WV 
Construction of a dam and reservoir for low water regulation 
and flood control 
ELKINS, WV 
For construction of local flood protection projects. 
JOHNSTOWN, PA 
For construction of local flood protection projects. 
PUNXSUTAWNEY, OHIO RIVER BASIN, PA 
For construction of local flood protection projects. 
BERLIN LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Construction, operation & maintenance of recreation facilities. 
S. Doc. 100, 81st Cong., 
1st Sess. 3. 
Supplemental Appropriations 
Act of 1985 for Engineering 
and Design 
and Land Acquisition 
and Water Resources Development 
Act of 1986; 
Public Law 99-662 Sec. 
301(a). 
Supplemental Appropriations 
Act of 1985 for Engineering 
and Design 
and Land Acquisition 
and Water Resources Development 
Act of 1986; 
Public Law 99-662 Sec. 
301(a). 
H. Doc. 1792, 64th Cong. 
2nd Sess. 
H. Doc. 106, 76th Cong. 
1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 306, 74th Cong. 1st 
Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
18-18 
5. 
8. 
9. 
10. 
12.

PITTSBURGH, PA., DISTRICT 
TABLE 18-B AUTHORIZING LEGISLATION (Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
modified by 
Aug 18, 1941 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jun 22, 1936 
amended by 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Jul 3, 1958 
Jul 14, 1960 
13. CONEMAUGH RIVER LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
CROOKED CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
EAST BRANCH CLARION RIVER LAKE, 
OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control and low 
water regulation. 
Construction, operation & maintenance of recreation facilities. 
KINZUA DAM AND ALLEGHENY RESERVOIR, 
OHIO RIVER BASIN, PA AND NY 
Construction of a dam and reservoir for flood control and low 
water regulation and recreation. 
Construction of a dam and reservoir for flood control, pollution 
abatement, low water regulation and recreation. 
Construction, operation & maintenance of recreation facilities. 
LOYALHANNA LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
MAHONING CREEK LAKE, OHIO RIVER BASIN, PA 
Construction of a dam and reservoir for flood control. 
Construction, operation & maintenance of recreation facilities. 
MICHAEL J. KIRWAN DAM AND RESERVOIR, OH 
Construction of a dam and reservoir for flood control, water 
supply, low water regulation and recreation. 
To define cost-sharing arrangement for municipal & industrial 
water supply & water for pollution abatement purposes. 
18-19 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No.1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No.1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
H. Doc. 300, 76th Cong. 
1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
H. Doc. 191, 85th Cong. 
1st Sess. 
Pub. Law 86-645 
14. 
15. 
16. 
17. 
18. 
19.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-B AUTHORIZING LEGISLATION (Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Aug 28, 1937 
Jun 28, 1938 
Aug 18, 1941 
Dec 22, 1944 
Jul 24, 1946 
May 17, 1950 
Dec 30, 1963 
Jun 18, 1965 
May 12, 1967 
Aug 13, 1968 
Jun 19, 1970 
Mar 7, 1974 
Oct 22, 1976 
Jun 28, 1938 
Dec 22, 1944 
as amended 
Nov 7, 1966 
20. 
21 
18-20 
MOSQUITO CREEK LAKE, OHIO RIVER BASIN, OH 
Construction of a dam and reservoir for flood control, low 
water regulation and water supply storage. 
Construction, operation & maintenance of recreation facilities. 
OHIO RIVER BASIN - Pittsburgh District 
Construct levees, floodwalls, and drainage structures for protection 
of cities and towns in Ohio River Basin. Projects to 
be selected by Chief of Engineers with approval of Secretary 
of War at a cost not to exceed $24,877,000 for construction. 
Approved general comprehensive plan for flood control and 
other purposes in Ohio River Basin as may be advisable in 
discretion of Secretary of War and Chief of Engineers, and 
for initiation and partial accomplishment of plan, authorized 
$75 million for reservoirs and $50,300,000 for local 
flood protection works. 
Additional $45 million for prosecution of comprehensive plan 
for Ohio River Basin. 
Additional $70 million for further prosecution of comprehensive 
plan for Ohio River Basin, including additional projects 
in tributary basins. 
Additional $125 million for further prosecution of comprehensive 
plan including additional projects in tributary basins. 
Additional $100 million for prosecution of comprehensive plan 
for Ohio River Basin. 
Additional $150 million for further prosecution of comprehensive 
plan for flood control and other purposes in Ohio River 
Basin. 
Additional $89 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $38 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $35 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $69 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Additional $120 million for further prosecution of comprehensive 
plan for Ohio River Basin. 
Authorized phase I design memorandum stage of advanced engineering 
and design of the project for abatement of acid 
mine drainage in the Clarion River Basin, Pa. 
SHENANGO RIVER LAKE, OHIO RIVER BASIN, PA 
AND OH 
Construction of a dam and reservoir for flood control, low 
water regulation and recreation. 
Construction, operation & maintenance of recreation facilities. 
STONEWALL JACKSON LAKE, WV 
Construction of a dam and reservoir for flood control, water 
supply, water quality control, area redevelopment and recreation. 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
Flood Control Committee, 
Doc. 1, 75th Cong., 
1st Sess. 
Flood Control Committee, 
Doc. 1, 75th Cong., 
1st Sess. 
H. Doc. 300, 76th Cong. 
1st Sess. 
H. Doc. 762, 77th Cong. 
2d Sess. 
H. Doc. 506, 78th Cong. 
1st Sess. 
S. Doc. 20, 81st Cong. 
1st Sess. 
Public Law 88-253, 
88th Cong., 1st Sess. 
H. Doc. 6755, 89th Cong., 
90th Cong. 1st Sess. 
Public Law 90-17. 
90th Cong., 1st Sess. 
Public Law 90-483, 
90th Cong., 2d Sess. 
H. Doc. 15166, 91st Cong., 
2d Sess. 
H. Doc. 10203, 93rd Cong. 
River Basin Monetary 
Authorization Act of 
1974. 
Water Resources Development 
Act of 1976; Public 
Law 94-587, Sec. 101(a). 
H. Doc. 306, 74th Cong. 
1st Sess. 
FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Sec. 4, Flood Control Act of 
1944 
S. Doc. 109, 89th Cong. 
2nd Sess. 
22. 
23.

PITTSBURGH, PA., DISTRICT 
TABLE 18-B AUTHORIZING LEGISLATION (Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
24. TIONESTA LAKE, OHIO RIVER BASIN, PA 
Jun 22, 1936 Construction of a dam and reservoir for flood control and low H. Doc. 306, 74th Cong. 
amended by water regulation. 1st Sess. 
Jun 28, 1938 FCC Doc. No. 1, 75th 
Cong. 1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act of 
as amended 1944 
25. UNION CITY DAM, PA 
Oct 23, 1962 Construction of a dam and reservoir for flood control. S. Dec. 95, 87th Cong. 
2nd Sess. 
26. WOODCOCK CREEK LAKE, PA 
Oct 23, 1962 Construction of a dam and reservoir for flood control, recrea- S. Doc. 95, 87th Cong. 
tion and storage for water quality control. 2nd Sess. 
27. YOUGHIOGHENY RIVER LAKE, OHIO RIVER BASIN, 
PA AND MD 
Jun 28, 1938 Construction of a dam and reservoir for flood control, low-flow H. Doc. 306, 74th Cong. 
augmentation, and pollution abatement, purposes. 1st Sess. 
FCC Dec. No. 1, 75th 
Cong. 1st Sess. 
Dec 22, 1944 Construction, operation & maintenance of recreation facilities. Sec. 4, Flood Control Act of 
as amended 1944 
1. Included in the Emergency Relief program April 8, 1935. 
2. Permanent Appropriations Repeal Act. 
3. Public Res. 117, 71st. Cong., 3d Sess. 
TABLE 18-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6 of Text) 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operations and 
Project Status Report For Construction Maintenance 
Allegheny River, PA, opl-channel work Completed 1934 197,000 133,940 
Buckhannon River,2WV Completed 1893 5,500 -- 
Cheat River, WV Completed 1895 12,997 -- 
Pittsburgh Harbor, PA Completed 1922 110,663 81,613 
1. Abandonment recommended in H. Doc. 467, 69th 
Cong., 1st Sess. 
2. No Commerce reported. 
18-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(All Projects Not Specifically Identified in Text) 
For Last Cost to September 30, 1992 
Full Report 
See Annual Construction Non-Federal Operation and 
Project and Status Report For (Federal Cost) Cost Maintenance 
Flood Protection 
Specifically Authorized Projects 
Completed: 
Bradford, PA 
Brookville, PA 
Buckhannon, WV 
Butler, PA 
DuBois, PA 
Elkins, WV4 
Johnsonburg, PfA 
Johnstown, PA 
Kittanning, PA, Part I 
Latrobe, PA 
Latrobe, PA 
Olean, NY 
Portage, PA 
Portville, NY 
Punxsutawney, PA4 
Reynoldsville, PA 
Ridgeway, PA (Elk Creek) 
Salamanca, NY 
Turtle Creek, PA3 
Washington, PA 
Wellsville, OH, Section I 
Wellsville, OH, Section II 
Youngstown, OH 
Active: 
Saw Mill Run, PA 
Deferred: 
Benwood, WV 
Authorized by Chief of Engineers 
Completed: 
Amsterdam, OH 
Big Run, PA 
Burgettstown, PA 
Friendsville, MD 
Girty's Run, Millvale, PA 
Granville, PA 
Leetonia, OH 
Oil City, PA 
Oil City Ice Control Structures 
Root Creek, Bolivar, NY 
Slovan, PA 
Sykesville, PA 
Tarentum, PA 
Tenmile Creek at Marianna, PA 
West Little Pine Creek, Etna, PA 
Wilmore, PA 
7,601,763 
964,976 
1,568,661 
1,556,181 
4,464,607 
1,772,627 
674,664 
8,865,388 
130,317 
207,659 
2,556,652 
3,217,531 
150,386 
2,070,484 
3,586,107 
385,494 
628,888 
2,880,535 
16,525,614 
789,093 
483,910 
157,633 
3,621,134 
1,895,000 
289,000 
75,000 
534,000 
910,000 
40,000 
130,000
-- 
2,000 
44,400 
698,000 
597,000 
14,900 
353,000 
180,485 
26,000 
72,000 
465,000
-- 
323,000 
113,000 
152,1522,02000 
1962 
1963 
1972 
1970 
1979 
1958 
1949 
1951 
1970 
1954 
1965 
1954 
1959 
1964 
1972 
1972 
1964 
1956 
1956 
1976 
1954 
1964 
1965 
1986 
1987 
1986 
1964 
1981 
-- 
-- 
81,028 
183,072 
364,208 
83,129 
41,529 
2,655,934 
75,908 
89,299 
43,595 
3,927,792 
1,591,436 
57,811 
184,246 
136,591 
1,554,428 
2,021,852 
96,853 
22,500 
35,900
-- 
2,200 
701,722 
3,000 
17,200
-- 
25,000
-- 
9,000 
24,600
-- 
86,200 
1,300 
18-22

PITTSBURGH, PA., DISTRICT 
TABLE 18-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to September 30, 1992 
Full Report 
See Annual Construction Non-Federal Operation and 
Project and Status Report For (Federal Cost) Cost Maintenance 
Active: 
Ridgeway & Vicinity (on Clarion River)2 1979 132,464 -- -- 
Inactive: 
Black Fork at Hendricks, WV 1972 6,800 - -. 
Oakdale, PA -- 14,127 -- -. 
Rouseville, P -- 1,642 -- -- 
Wallace, WV -- 11,035 --. -- 
Weston Mills, Olean, NY -- 50,100 -- -- 
Weston Mills, Portville, NY -- 52,100 -- -- 
Reservoirs 
Other: 
Rowlesburg Lake, WV 1977 2,857,575 -- -- 
1. Lacks local support. 
2. No longer economically justified. 
3. Includes $15,350,352 original construction cost. 
4. Reported in detail in an individual report. 
18-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Adena, OH Short Creek) 
Allegany, NY Unit I (Allegheny River) 1 
Allegany, NY Unit II (Five Mile Creek Area) 
Bellaire, OH 
Brackenridge, Tarentum and Natrona, PA1 
Brilliant, OH 
Brockway, PA (Allegheny River Basin) 
Clarington, OH 
Coraopolis, PA 
Dillonvale, OH (Short Creek) 
Eagle Creek Reservoir, OH 
Empire-Stratton, OH 
Follansbee, WV 
Freeport, PA (Allegheny River) 
Industry, PA 
Kittanning, PA, part II (Allegheny River) 
Lake Chautauqua and Chadakoin River, NY 
Lake Erie-Ohip Canal, OH and PA - 1935 Act 
Leetsdale, PA 1 
Martins Ferry, OH' 
McKees Rocks, PA 
Mingo Junction, OH 
Moundsville, WV" 
Muddy Creek Dan, PA' 
Neville Island, PA 
New Cumberland, WV 
New Kensington and Parnassus, PA' 
Pittsburgh, PA (Golden Triangle) 
Pittsburgh, PA (North Side) 
Pittsburgh, PA (The Strip) 
Powhaten Pqint, OH 
Proctor, WV 
Redbank Creel Lake, PA 
Rochester, PA 
St. Marys, PA (Allegheny River Basin) 
Smith Ferry, PA 
Uniontown, P4 
Warwood, WV 
Wellsburg, WV 
West Bridgewater, PA 
Wheeling, WV 
Wheeling, WV (North Wheeling)'1 
Wheeling, VV (Wheeling Island)1 
Wilcox, PA 
Woodlands, WV' 
Youghiogheny River, PA and MD (Canalization)' 
1975 
1965 
1972 
1941 
1977 
1956 
1954 
1971 
Aug 5, 1977 
Nov 17, 1986 
Nov 17, 1986 
May 6, 1981 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Jan 1, 1990 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Aug 5, 1977 
Nov 6, 1977 
Mar 2, 1970 
May 6, 1981 
Nov 17, 1986 
Nov 17, 1986 
Oct 3, 1978 
Aug 5, 1977 
Nov 17, 1986 
Nov 17, 1986 
Nov 17, 1986 
Aug 5, 1977 
Nov 17,1986 
Oct 3, 1978 
Oct 3, 1978 
Oct 3, 1978 
Nov 17 ,1986 
Nov 17, 1986 
Aug 5, 1977 
Nov 17, 1986 
Aug 5, 1977 
Aug 5, 1977 
Jan 1, 1990 
Nov 17,1986 
Aug 5, 1977 
Aug 5, 1977 
Nov 17, 1986 
Nov 17, 1986 
Nov 17, 1986 
Mar 5, 1955 
Nov 17, 1986 
Nov 17, 1986 
1. Deauthorized under Water Resources Development Act 
of 1986 (PL99-662). 
2. Local Interests failed to meet requirements of cooperation, 
authority for project expired Mar. 2, 1970. 
3. Local interests failed to meet requirements of cooperation, 
authority for project expired Mar. 5, 1955. 
4. Includes $47,195 construction costs expended under 
previous project and $1,700 O&M costs expended under previous 
project. 
18-24 
13,452 
4,100 
64,851 
76,487
-- 
-- 
194
-- 
-- 
16,884 
100,000 
33,031
-- 
190,722 
1,342,000 
25,164 
402,459
-- 
-- 
-- 
-- 
-- 
156,377
-- 
13,529
-- 
-- 
-- 
6,387
-- 
189,067
-- 
21,700 
16,761 
2322,3826,8363

TABLE 18-H ALLEGHENY RIVER, PA.: LOCKS AND DAMS 
(See Section 1 of Text) 
Dimensions Upper Depths on Mi- 
Avail- Normal ter Sills 
Width able Lift at Pool Ele- at Normal Character of Type of Year 
of LengthNormal vation Pool Level1 Foundation Construction Per- Opened 
Miles Cham- to Full Pool (feet, cent to 
Above ber Width Level mean sea Lower Upper Kind Coin- Naviga- 
No Mouth Nearest Town (Feet) (Feet) (Feet) level). (Feet) (Feet) Lock Dam of Dam Lock Dam plete tion Actual Cost 
2 6.7 Aspinwall, PA 
3 14.5 Cheswick, PA 
4 24.2 Natrona, PA 
5 30.4 Freeport, PA 
6 36.3 Clinton, PA 
7 45.7 Kittanning, PA 
8 52.6 Templeton, PA 
9 62.2 Rimer, PA 
Total 
Abandoned lock and dam 1 
Abandoned lock and dam 2 
Abandoned lock and dam 3 
0 Demolishing old dam 1 
S Dredging channel 
mTotal 
56 
56 
56 
56 
56 
56 
56 
56 
360 11.0 721.0 12.0 10.9 Rock Rock Fixed Concrete Concrete 100 19342 
360 13.5 734.5 10.8 11.8 Rock Pile-Rock Fixed Concrete Concrete 100 19342 
360 10.5 745.0 10.0 8.5 Rock Rock Fixed Concrete Concrete 100 1927 
360 11.8 756.8 10.5 10.3 Piling Crib-Pile Fixed Concrete Concrete 100 1927 
360 12.2 769.0 10.6 10.8 Rock Crib-Pile Fixed Concrete Concrete 100 1928 
360 13.1 782.1 9.8 10.9 Piling Steel Sheet Fixed Concrete Concrete 100 1930 
Piling 
360 17.9 800.0 10.4 13.8 Rock Rock Fixed Concrete Concrete 100 1931 
360 22.0 822.0 10.5 11.3 Rock Rock Fixed Concrete Concrete 100 1938 
1. All depths as shown are on guard sills and are controlling depth. 
2. Dates shown represent replacement structures. 
$ 1,763,485 
$ 1,875,665 
1,707,690 
1,940,537 
1,523,959 
1,460,008 
2,848,920 
2,510,373 
$15,630,637 
591,187 
544,929 
310,103 
26,001 
1,055,003 
$18,157,860 0

TABLE 18-I 
Miles 
Above Nearest 
No Mouth Town 
2 11.2 Braddock, PA 56 
1103 
3 23.8 Elizabeth, PA 56 
4 41.5 Monessen, PA 563 
-- 61.2 Maxwell locks 843 
and dam, 
Maxwell, PA 
-- 82.2 Grays Landing 84 
lock and dam, 
Grays Landing, PA 
7 85.0 Greensboro,PA 56 
8 90.8 Point Marion, PA 56 
-- 102.0 Morgantown lock 84 
and dam, 
Morgantown, WV 
-- 108.0 Hildebrand lock 84 
and dam, 6 
miles above 
Morgantown, WV 
-- 115.4 Opekiska lock 842 
and dam, 13.4 
miles above 
Morgantown, WV 
MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(see Section 3 of Text) 
Dimensions Normal 
Pool 
Avail- Eleva- Depths on Miable 
Lift at tion ter Sills at 
Width Length Normal (feet, Normal Pool Character of Type of Perof 
Cham- to Full Pool mean Level Foundation Construction cent Year 
ber Width Level sea Lower Upper Kind Corn- Opened to Actual 
(feet) (feet) (feet) level) (feet) (feet) Lock Dam of Dam Lock Dam plete Navigation Cost 
360 8.7 718.7 
720 
360 8.2 726.9 
720 
360 16.6 743.5 
720 
720 19.5 763.0 
720 15.0 778.0 
360 15.0 778.0 
360 19.0 797.0 
600 17.0 814.0 
600 21.0 835.0 
600 22.0 857.0 
16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 
16.0 15.95 Rock Crib Pile Fixed Concrete Concrete 100 
10.7 20.0 Piles Piles Movable Concrete Concrete 100 
15.0 20.5 Rock Rock Movable Concrete Concrete 100 
15.0 26.0 Rock Rock Fixed Concrete Concrete -- 
10.0 10.5 Rock Rock Fixed Concrete Concrete 100 
10.0 14.5 Rock Rock Movable Concrete Concrete 100 
14.5 17.8 Rock Rock Movable Concrete Concrete 100 
15.0 14.0 Rock Rock Movable Concrete Concrete 100 
14.0 17.75 Rock Rock Movable Concrete Concrete 100 
Marine ways, etc 
Abandoned lock and dam 1 
Abandoned lock and dam 4 
Abandoned lock and dam 5 
Abandoned lock and dam 6 
Abandoned lock and dam 7 
Abandoned lock and dam 8 
Abandoned lock and dam 9 
Abandoned lock and dam 10 
Abandoned lock and dam 11 
Abandoned lock and dam 12 
Abandoned lock and dam 13 
Abandoned lock and dam 14 
Abandoned lock and dam 15 
Dredging 
Total 
0 
19532 $17,872,212s H 
2 58 19532 17,538,536s 
19322 17,254,0715 6 
19642 30,110,8895 y 
-- 114,970,9419' 
0 
19252 2,639,804. 
1925 83,389,718 
19502 8,778,0005 
19592 12,506,8295 
Oz 
19642 25,179,6225 
r
0 
250,0005 
1,019,9075 
780,816s 
1,074,812 
770,449 
213,7765 
245,900 
191,000 C 
210,445s O 
227,6685 
200,550 
190,691 
210,1275 
175,829 C 
587,899 t 
$336,590,4915

TABLE 18-I MONONGAHELA RIVER, PA. AND W. VA.: LOCKS AND DAMS 
(see Section 3 of Text) 
1. All depths as shown are on guard sills and are controlling depths. 5. Actual cost: may include estimated costs which have been footnoted a 
2. Dates shown for locks and dams No. 2 to 8 inclusive, represent reconstruc- necessary. 
tion. 6. Includes $2,173,767 for original reconstruction (1931-2), and $15,080,30 
3. 2 Chambers for reconstruction of dam (1963-1967). 
4. Includes $3,322,057 for raising crest of dam, (1958-9), $2,086,438 for 7. Includes $16,967,114 for reconstruction of locks. 
original reconstruction (1923-1926), $618,758 AE&D costs for replacement of 8. Includes $15,857,000 for major rehabilitation. 
lock, and $38,928,686 expended from the Inland Waterways Trust Fund. 9. Includes AE&D costs for proposed lock ($803,000) and $57,739,718 ex 
pended from the Inland Waterways Trust Fund. 
l8 
4
- 
b== 
y

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-J MONONGAHELA RIVER, PA AND WV: 
TOTAL COSTS OF EXISTING PROJECT TO END OF FISCAL YEAR 
(See Section 3 of Text) 
Operation and 
Maintenance, 
Funds New Work General Total 
Regular $331,169,95013 $195,661,0022 $526,830,952 12 3 
Maintenance and operation 452,623 452,623 
Public Works acceleration, executive (1963) -- 22,549 22,549 
Total $331,169,950 $196,136,1742 $527,306,12412 3 
1. Excludes $5,420,541 for new work for previous pro- 3. Includes $15,857,000 for major rehabilitation of IUD 
jects. 3, $114,167,941 for replacement of LID 7 ($57,739,718 pro- 
2. Excludes $20,446,587 expended between July 7, 1897 vided by the Inland Waterways Trust Fund), and $77,362,465 
and June 30, 1937, on operation and care of works of improve- for replacement of lock at Point Marion Lock and Dam 
ment under provisions of permanent appropriation for such ($38,928,686 provided by the Inland Waterways Trust Fund). 
purposes and excludes $742 for maintenance of previous projects. 
TABLE 18-K OHIO RIVER BASIN (PITTSBURGH DISTRICT): RESERVOIRS 
(See Section 21 of Text) 
Total 
Estimated 
Tributary Basin and Reservoir Stream Cost 
Allegheny: 
Conemaugh River, PA Conemaugh River $46,012,411 
Crooked Creek, PA Crooked Creek 4,482,933 
East Branch Clarion River, PA Clarion River 9,539,586 
Kinzua Dam and Allegheny Reservoir, PA and NY Allegheny River 112,226,0761 
Loyalhanna, PA Loyalhanna Creek 5,727,531 
Mahoning Creek, PA Mahoning Creek 7,144,973 
Tionesta, PA Tionesta Creek 7,792,378 
Union City, PA French Creek 14,559,800 
Woodcock Creek, PA Woodcock Creek 20,545,065 
Beaver: 
Berlin, OH Mahoning River 8,739,987 
Michael J. Kirwan, OH Mahoning River 17,376,097 
Mosquito Creek, OH Mosquito Creek 4,253,029 
Shenango River, PA and OH Shenango River 40,217,201 
Monongahela: 
Stonewall Jackson Lake, WV West Fork River $208,608,1542 
Youghiogheny River, PA and MD Youghiogheny River 12,521,167 
1. Includes $2,921,000 actual cost for dam rehabilitation. 
2. Actual cost. Latest cost estimate (1991) is $231,000,000. 
18-28

PITTSBURGH, PA., DISTRICT 
TABLE 18-L INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 28 of Text) 
Project 
Amsterdam, OH 
Big Run, PA 
Bolivar, NY 
Bradford, PA 
Brookville, PA 
Buckhannon, WV 
Burgettstown-Slovan, PA 
Butler, PA 
Chartiers Creek, PA 
Cannonsburg-Houston Reach 
James G. Fulton Reach 
Colliers, WV 
DuBois, PA 
Eldred, PA 
Etna, PA 
Friendsville, MD 
Granville, PA 
Johnsonburg, PA 
Kittaning, PA 
Latrobe, PA 
Leetonia, OH 
Dates of Inspection 
Aug 1991 
Aug 1992 
Sep 1992 
Aug 1991 
Sep 1991 
Sep 1992 
Sep 1986 
Apr 1992 
Sep 1989 
Mar 1992 
Apr 1992 
Sep 1992 
Apr 1987 
Sep 1989 
Apr 1992 
Jun 1990 
May 1992 
Jul 1991 
Sep 1992 
Jun 1992 
Project 
Marianna, PA 
Millvale, PA 
Oil City 
Ice Control Structure, 
Allegheny River, PA 
Oil City LPP-(Dike), PA 
Olean, NY 
Portage, PA 
Portville, NY 
Reynoldsville, PA 
Ridgway, PA 
Salamanca, NY 
Stonewood-Nutter Fort, WV 
Sykesville, PA 
Tarentum, PA 
Turtle Creek, PA 
Washington, PA 
Wellsville, OH 
Weston, WV 
Wilmore, PA 
Youngstown, PA 
Dates of Inspection 
Apr 1990 
Jul 1990 
Sep 1991 
Sep 1991 
Sep 1992 
Oct 1990 
Sep 1992 
Aug 1992 
Oct 1991 
Sep 1992 
Jun 1992 
Jul 1992 
Nov 1976 
Sep 1987 
Sep 1986 
Jul 1991 
Jul 1992 
Nov 1991 
Jun 1992 
18-29 
--

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 18-M FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 30 of Text) 
Flood Control Activities pursuant to Section 205, 
Public Law 858, 80th Congress, as amended (preauthorization) 
Project/Study Identification 
Allegheny River, Oil City, PA (construction completed) 
Belington, WV (reconnaissance) 
Charleroi, PA (complete) 
Clarion River, Ridgeway, PA (reconnaissance) 
Connellsville, PA (reconnaissance) 
Connoquenessing Creek, Marion Twp., PA (reconnaissance) 
Connoquenessing Creek, Sewickley Twp., PA (reconnaissance) 
Hickman Run, Little Tyrone Twp., PA (reconnaissance) 
Jackson Township, Butler Co., PA (reconnaissance) 
Little Yankee Creek, Hubbard, OH (reconnaissance) 
McGary Hollow Run, Weston, WV (reconnaissance) 
Oil Creek, Oil City, Venango County, PA (reconnaissance) 
Parsons, Hambleton, Hendricks, WV (complete) 
Penn Township, Butler Co., PA (complete) 
Phillipi, WV (terminated) 
Short Creek, Connorville, OH (complete) 
Stoneycreek River, Johnstown, PA (complete) 
Weegie/Pipe Creeks, Shadyside, Oh (complete) 
Total cost for current fiscal year: 
Fiscal Year Costs 
$40,978 
9,558 
7,027 
21 
7,052 
1,025 
1,491 
582 
14,469 
8,591 
5,714 
232 
136 
14,625 
6,046 
14,958 
361,.509536 
$170,154 
Emergency Bank Protection - Section 14 of the 
1846 Flood Control Act, Public Law 526, 79th Congress 
Project/Study Identification 
Brush Creek, Jeannette, PA (plans and specifications) 
Chadakoin River, Jamestown, NY (plans and specifications) 
Chubb Run, Franklin, PA (detailed project report underway) 
Conneaut Lake, PA (detailed project report underway) 
Cox Run, Wellsburg, WV (construction) 
Downers Run, Fayette City, PA (terminated) 
French Creek, Wattsburg, PA (detailed project report underway) 
Mahoning River, Hwy. 139a, Trumbull Co., OH (construction completed) 
Main Street, Wellsburg, WV (construction) 
Middle School, Wellsburg, WV (construction) 
Mill Run, Sinclairville, NY (plans and specifications) 
Miller Run, Cecil Twp., PA (detailed project report underway) 
Mon River, Sewage Treatment Plant, Pt. Marion, PA (detailed project report underway) 
Mon River, Water St., Pt. Marion, PA (detailed project report underway) 
Nelson Run, Ross Twp., PA (detailed project report completed) 
Neshannock Creek, New Castle, PA (terminated) 
Ohio River, Chester, WV (detailed project report completed) 
Ohio River, Moundsville, WV (detailed project report underway) 
Orange Road, Mercer Co., PA (terminated) 
Plum Creek, Oakmont, PA (plans and specifications) 
Saw Mill Run Road, Salamanca, NY (plans and specifications) 
Sewer Outfall, Glendale, WV (construction completed) 
Shupe Run, Mt. Pleasant, PA (construction completed) 
Spruce Run, Ben Avon, PA (detailed project report underway) 
Walnut Bottom Run, Beaver Falls, PA (detailed project report underway) 
Water Works, Park and Pool, Wellsburg, WV (construction) 
West Fork River, Clarksburg, PA (detailed project report underway) 
Yough, Turkeyfoot Twp., PA (terminated) 
Total Cost for Current Fiscal Year: 
Fiscal Year Costs 
$9,832 
1,566 
19,658 
15,424 
24 
10,623 
19,303 
289 
(339) 
3,598 
3,416 
13,387 
953 
1,608 
19,530 
85 
17,471 
1,506 
69 
9,759 
7,611 
69,498 
16,669 
1,363 
5,337 
3,943 
15,699 
$267$,286978,898 
18-30

OHIO RIVER 
For actual construction of locks and dams, and operation 
and care of completed structures, river is divided 
into three sections under immediate supervision and 
direction of District Engineers at Pittsburgh, Huntington, 
and Louisville. Pittsburgh section extends 127 
miles from head of river at Pittsburgh, PA, to a point 
immediately upstream from New Martinsville, WV, and 
includes Emsworth, Dashields, Montgomery, New 
Cumberland, Pike Island, and Hannibal Locks and Dams. 
Huntington section extends 311 miles from mile 127 to 
438 immediately upstream from Foster, KY, and includes 
Willow Island, Belleville, Racine, Robert C. Byrd, 
Greenup, and Captain Anthony Meldahl Locks and 
Dams. Louisville section extends 543 miles from mile 
438 to mouth of river, and includes Markland and 
McAlpine Locks and Dams (with Louisville and Portland 
Canal), Cannelton, Newburgh, Uniontown, and 
Smithland Locks and Dams, and Locks and Dams 52 and 
53. 
Improvements 
Navigation 
1. Construction of locks and dams on 
O hio R iver ......................................................... 19-1 
2. Open channel work, Ohio River ...................... 19-3 
Tables 
Table 19-A Cost and Financial Statement ..... 19-5 
Table 19-B Authorizing Legislation ................ 19-6 
Table 19-C Not Applicable 
Table 19-D Not Applicable 
Table 19-E Not Applicable 
Navigation 
1. CONSTRUCTION OF LOCKS AND 
DAMS ON OHIO RIVER 
Location. Ohio River is formed by junction of Allegheny 
and Monongahela Rivers at Pittsburgh, PA, and 
flows generally southwesterly for 981 miles to join Mississippi 
River near Cairo, IL. For description of river see 
page 1227, 1932 Annual Report. 
Previous Projects. For details see page 1907 of 
Annual Report for 1915. 
Existing project. Provides for improvement of entire 
river by construction of locks and dams to provide channel 
depth of 9 feet and for widening Louisville and 
Portland Canal at Louisville, KY. Project provides for a 
lock with usable dimensions of 110 by 600 feet at each of 
the dams and, in addition, an auxiliary lock 56 by 360 feet 
is available at Emsworth, Dashields, Montgomery, and 
McAlpine Locks and Dams with an auxiliary lock at 
Robert C. Byrd being 110 by 360 feet. Dashields is a fixed 
dam, while Emsworth, Montgomery, and Robert C. Byrd 
are fixed dams with movable crests. Remaining dams 
are movable type, with navigable pass varying in width 
from 600 to 1,248 feet. In addition to navigable pass, 
movable-type dams are also provided with one or more 
regulating weirs. At McAlpine Locks and Dam, a canal 
(Louisville and Portland) extends along left bank for 2 
miles, with locks at lower end. Modifications to existing 
Table 19-F Not Applicable 
Table 19-G Not Applicable 
Table 19-H Construction of Locks and Dams on 
Ohio River, Total Cost of Existing 
Project ............................................. 19-7 
Table 19-I Federal Energy Regulatory 
Commission Licenses of Locks 
and Dams, Ohio River .................. 19.7 
Table 19-J Ohio River Locks and Dams 
Statistics ........................................ 19-8 
project under purview of Section 6, March 3, 1909 Act, 
provide for fixed dams with movable crests with two 
locks (110 by 1,200 feet and 110 by 600 feet) at New 
Cumberland, Pike Island, Hannibal, Willow Island, 
Belleville, Racine, Greenup, Captain Anthony Meldahl, 
Markland, Cannelton, Newburgh, and Uniontown; two 
locks 110 by 1,200 feet at Smithland; 110- by 1,200-foot 
temporary locks in addition to the existing locks at Locks 
and Dams 52 and 53, and reconstruction to provide a 
110- by 1,200-foot lock in addition to existing locks and 
a fixed dam with two section of movable crest at McAlpine 
Locks and Dam; widening Louisville and Portland Canal 
to 500 feet. Auxiliary lock 56 by 360 feet at McAlpine 
Locks and Dam has been inoperative since failure of 
downstream lock gates in December 1972. Rehabilitation 
of existing Locks and Dams 52 and 53 was started 
in September 1979 under the purview of Section 6, 
March 1909 Act. Mound City was also considered 
authorized under purview of 1909 Act, and 
preconstruction planning was performed in the period 
1965 to 1972. The ruling of the U.S. District Court, 
District of Columbia, on September 6, 1974, with reference 
to Lock and Dam 26, Mississippi River, would also 
apply to this project. Consequently, it is no longer 
considered authorized. Operation and care of locks and 
dams were included in project July 1, 1935, under 
provisions of Permanent Appropriations Repeal Act of 
June 26, 1934. Estimated Federal cost of new work 
(existing project, 1983), is $1,739,921,050; estimated 
19-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
non-Federal cost is $14,999,000. Foregoing estimate 
does not include expenditures on previous projects. 
Various items previously included in this project are 
considered inactive or unnecessary and are excluded 
from foregoing cost estimate. See page 693, Annual 
Report, 1968, for items and estimated cost. Under authority 
of 1910 River and Harbor Act, Louisville and 
Portland Canal was widened to 200 feet; Locks and 
Dams 40 and 42 eliminated; Locks and Dams 1 and 2 
replaced by Emsworth Locks and Dam; Lock and Dam 3 
replaced by Dashields Locks and Dam; and Locks and 
Dams 4, 5, and 6 replaced by Montgomery Locks and 
Dam. Locks and Dams 24, 25, and 26 were replaced by 
Robert C. Byrd Locks and Dam authorized by August 30, 
1935, Act, and constructed under project for improving 
lower Kanawha River. Locks and Dams 7, 8, and 9 were 
replaced by New Cumberland Locks and Dam; Locks 
and Dams 10 and 11 were replaced by Pike Island Locks 
and Dam; Locks and Dams 12, 13, and 14 were replaced 
by Hannibal Locks and Dam; Locks and Dams 15,16, and 
17 were replaced by Willow Island Locks and Dam; Locks 
and Dams 18, 19, and 20 were replaced by Belleville 
Locks and Dam; Locks and Dams 21, 22, and 23 were 
replaced by Racine Locks and Dam; Locks and Dams 27, 
28, 29, and 30 were replaced by Greenup Locks and Dam; 
Locks and Dams 31, 32, 33, and 34 were replaced by 
Captain Anthony Meldahl Locks and Dam; Locks and 
Dams 35, 36, 37, 38, and 39 were replaced by Markland 
Locks and Dam; the Louisville and Portland Canal at 
McAlpine Locks and Dam were widened to 500 feet. 
Locks and Dams 43, 44, and 45 were replaced by 
Cannelton Locks and Dam; Locks and Dams 46 and 47 
were replaced by Newburgh Locks and Dam; Locks and 
Dams 48 and 49 were replaced by Uniontown Locks and 
Dam, and Locks and Dams 50 and 51 were replaced by 
Smithland Locks and Dam, as modifications to existing 
project under purview of Section 6, March 3, 1909 Act, 
reducing total number of structures to 20. The Water 
Resources Development Act of 1974 combined the 
Newburgh Bank Protection Works project with the 
Newburgh Locks and Dam project. A December 1981 Act 
established the Falls of the Ohio National Wildlife Conservation 
Area near McAlpine Locks and Dam to protect 
and preserve existing fossilized coral and a diversity of 
wildlife. A November 17, 1988 Act authorized a replacement 
structure for Locks & Dams 52 & 53 at Olmsted, IL. 
A November 28, 1990 Act authorized an interpretive 
center at the Falls of the Ohio National Wildlife Conservation 
Area near McAlpine Locks & Dam and a modernization 
of the existing 110 foot x 600 foot lock at McAlpine 
Locks & Dam, IN & KY. Table 19-J contains data 
relative to various features of locks and dams included in 
existing project. For list of principal towns and cities 
along Ohio River with their mileage below Pittsburgh, 
PA, see page 1060, 1962 Annual Report. See Table 19- 
I for licenses. 
Navigation system of 21 locks and dams is in operation 
and 9-foot navigation throughout length of river is generally 
available at all times. At certain unstable bars 
project depth is maintained by dredging, supplemented 
by contraction works. (See "Open Channel Work, Ohio 
River.") Table 19-J shows cost and year completion of 
locks and dams now in operation. Existing project does 
not provide adequate facilities for present day navigation 
due to obsolescence of structures. Since repair and 
modernization of these facilities would be extremely 
costly, replacement and reconstruction is being accomplished 
as rapidly as funds are made available for the 
purpose. Construction of lock and dam replacement 
program was initiated in Fiscal Year 1955. New Cumberland, 
Pike Island, Hannibal, Willow Island, Belleville, 
Racine, Greenup, Captain Anthony Meldahl, Markland, 
McAlpine, Cannelton, Newburgh, Uniontown, 
and Smithland replacement locks and dams are in operation, 
replacing 39 old low-lift locks and dams. For 
total cost of existing project, see Table 19-H. 
Terminal facilities. Modern public terminals, with 
warehouses, equipped with operating machinery for 
transferring materials, have been constructed by private 
interests at some of the larger cities and towns. A 
list of terminals on Ohio River is revised annually and 
can be obtained from Division Engineer, U.S. Army 
Engineer Division, Ohio River, Cincinnati, Ohio. 
Operations during fiscal year. New work by contract 
and hired labor: 
Montgomery Locks and Dam (Rehabilitation): Major 
rehabilitation was completed in February 1989. Total 
cost of rehabilitation work was $32,016,696. Expenditures 
during fiscal year 1992 for construction, engineering 
and design of project were $1,801. 
Dashields Locks and Dam (Rehabilitation): Major 
rehabilitation was completed in December 1990 at a cost 
of $33,914,252. 
Willow Island Locks and Dam: Construction was 
initiated in January 1967. All work is complete. 
Belleville Locks and Dam: Construction was initiated 
in May 1962. All work is complete. 
Racine Locks and Dam: Construction initiated in 
June 1964 is complete. 
Robert C. Byrd Locks and Dam: The existing project, 
constructed under project for improving lower Kanawha 
River, was placed in operation in August 1937. The 
dimensions of the existing locks chambers and poor 
approach conditions, particularly to downstream traffic, 
have created a higher than normal accident rate to the 
structure with corresponding hazards and delays to 
traffic. The Water Resources Development Act of 1976 
authorized Phase I studies for 1,200-foot locks in a 
bypass canal. These studies are complete. 
Initial Construction, General funds for the continuation 
of Engineering activities were received in September 
1985. During the fiscal year real estate acquisition 
continued. The project was advertised and bids were 
opened in September 1987. The contract was awarded in 
October 1987 and is 96 percent complete. The total 
estimated cost of the project is $384 million, which is 50 
percent Federal cost and 50 percent Inland Waterways 
Trust Fund cost. 
Greenup Locks and Dam: Construction was initiated 
in October 1954. All work is complete. 
19-2

OHIO RIVER 
Captain Anthony Meldahl Locks and Dam: Construction 
work complete. 
Markland Locks and Dam: Project is complete including 
a public highway bridge across the navigation structure, 
as authorized by the Federal Aid Highway Act of 
1970 (Public Law 91-606). For details of bridge see page 
22-3 of Annual Report for 1978. 
Falls of the Ohio National Wildlife Conservation Area 
was authorized by Public Law 97-137 on December 29, 
1981 and modified by Public Law 101-640 on November 
28, 1990 to design and construct an interpretive center. 
The Conservation Area will protect 1,000 acres which 
consists of birdlife and other wildlife. Planning consisted 
of efforts to define facilities to be cost shared with 
local interests. All Real Estate tracts have been acquired 
and condemnation trials continue. $99,631. 
McAlpine Locks and Dam: Project is complete except 
for alteration of lift section of railroad bridge that spans 
the upper end of the Louisville and Portland Canal 
which work is presently deferred. A modernization of 
the existing 110 foot x 600 foot lock with a new 110 foot 
x 1,200 foot lock was authorized by Public Law 101-640. 
Advanced Engineering and Design was continued. 
$1,082,519. 
Cannelton Locks and Dam: Project is complete. 
Newburgh Locks and Dam: Construction initiated in 
October 1962 is complete except for financially closing 
out the project. $148. 
Uniontown Locks and Dam: Project is complete except 
for financially closing out the project. $873. 
Smithland Locks and Dam: All major construction 
features are complete and the project was advanced to 99 
percent completion. Real Estate activity is complete 
except for audit work and Title Opinions. $1,965. 
Locks and Dam No. 52 (New Lock): Construction 
initiated in December 1967 is complete. 
Locks and Dam No. 53 (Temporary Lock): Construction 
initiated in December 1972 is complete. 
Locks and Dam No. 52 (Rehabilitation): Construction 
initiated in June 1979 is complete. 
Locks and Dam No. 53 (Rehabilitation): Constructed 
initiated in June 1979 is complete. 
Olmsted Locks & Dam: A replacement structure for 
Locks and Dams 52 & 53 was authorized by the WRDA 
of 1988 in Public Law 100-676 on 17 November 1988. 
Advanced Engineering and Design continued. 
$4,824,918. 
Operation and maintenance, general. Locks and dams 
operated as required and necessary repairs and improvements 
made thereto and to operator's quarters, 
grounds and esplanades. Costs were $12,786,833 for 
Huntington District, $16,695,308 for Louisville District, 
and $10,719,076 for Pittsburgh District. 
2. OPEN CHANNEL WORK, 
OHIO RIVER 
Location. Under jurisdiction of district engineer in 
whose district work is located. Portion of river included 
in project extends 974.7 miles from head of river at 
Pittsburgh, PA, to mouth of Cache River (Mound City, 
IL). Open channel improvement from mouth of Cache 
River to mouth of Ohio River is under jurisdiction of 
Mississippi River Commission. 
Existing Projects. Before completion of canalization 
project, no project depth had been fixed by Congress 
under project for open channel work; but, in order to 
properly aid packet and barge navigation, it was necessary 
to secure a low-water channel with a minimum 
depth of 4 to 6 feet, and a width, depending upon 
difficulty of running channel, of 400-600 feet; also, to 
permit movement of large coal tows, which movement 
occurred at stages of water exceeding 10 feet, it was 
necessary to remove points of projecting bars which 
formed at various locations along river. Accomplishment 
of this purpose involved concentration of current 
by closing back channels at islands with low dams, 
contraction and straightening wide open channels by 
low dikes, dredging bars and shoals, and removal of 
snags and wrecks. Incidental to direct improvement of 
Ohio River is construction and maintenance of ice piers 
as required for protection of river craft. Stage of extreme 
high water on Ohio River varies from 46 feet at Pittsburgh, 
PA, to 80 feet at Cincinnati, OH, with 57.2 feet at 
Louisville, KY (head of falls, 53.8 feet at Evansville, IN, 
and 59.5 feet at Cairo, IL (mouth of river). Estimated 
cost of new work (1960) is $16.16 million, exclusive of 
following items which are considered inactive: Ice piers 
authorized by 1927 River and Harbor Act; reforestation 
of sloughs of Kentucky Peninsula near Evansville, IN, 
authorized by 1930 River and Harbor Act; dredging to 
widen channel at certain points; and placing revetment 
at various points. Estimated cost of these items (1954 is 
$6,565,000. Operation of snag boats on Ohio River below 
Pennsylvania State line was included in project July 1, 
1935, under provisions of Permanent Appropriations 
Repeal Act of June 26, 1934. See Table 19-B for authorizing 
legislation. 
New work under this project is substantially complete, 
since it is not anticipated that work on inactive 
portion of project will be accomplished. In addition to 
dredging, local stabilization of channel has been effected 
at various points by construction of dikes and revetment. 
Work which remains consists of dredging to widen channels 
at certain points to project depth. 
Local cooperation. River and Harbor Act of January 
21, 1927, authorizing construction of ice piers for 
general open channel work, imposes condition that before 
work is begun on any pier, local interests convey to 
the United States free of cost such riparian rights as may 
be deemed necessary in connection with the improvements 
at locality (H. Doc. 187, 67th Congr., 2nd Sess.). 
19-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing ice piers are adequate for present purposes and 
local cooperation is not needed since no additional construction 
is under consideration. River and Harbor Act 
of July 3, 1930, provides for reforestation of sloughs of 
Kentucky Peninsula and bank protection and that no 
expense shall be incurred by the United States for 
acquiring lands required for purpose of this improvement 
(H. Doc. 409, 69th Congr., 1st Sess.). However, 
since no serious overbank erosion has occurred since 
bank revetment in 1933-34, reforestation is not considered 
justifiable at this time and no local cooperation is 
required. 
Operations during fiscal year. Operation and 
maintenance, general: Dredging was done where required 
to provide an adequate and dependable channel 
of project depth at minimum pool conditions. Dikes and 
revetments were maintained and routine work of maintaining 
navigation aids, removing snags, making channel 
studies, hydrographic surveys and mapping was 
performed as required. Channel soundings, hydrographic 
surveys, stream gaging operations, channel 
inspections and aids to navigation, and miscellaneous 
inspections and reports cost $1,489,421. There was no 
dredging by hired labor on the Ohio River in FY 92. 
Dredging by contract: Huntington District 4,813,807 
cubic yards at $1,073,479 and Louisville District 
1,050,380 cubic yards at $2,335,850. 
19-4

OHIO RIVER 
Cost and Financial Statement 
See 
Section 
in Text Project Funding FY 89 FY 90 FY91 
Total Cost To 
FY 92 Sep 30, 1992 (footnotes) 
1. Construction of 
Locks and Dams 
on Ohio River 
2. Open Channel 
Work, Ohio River 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Rehab. (O&M 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
$43,833,000 $75,703,005 
48,444,774 74,080,673 
$58,847,815 $25,770,000 $1,666,162,592 1 3 5 10 17 21 
60,229,469 28,822,023 1,664,308,380 1 3 6 11 12 15 16 18 22 
34,279,987 35,342,477 36,184,500 39,641,315 802,800,613 2 4 19 
34,103,524 34,314,742 36,584,217 40,201,217 801,711,324 2 13 14 19 20 
275,000 
448,866 
-24,434 
61,188 
14,129,500 3,846,551 
14,103,501 3,864,999 
0 
10,522 
-3,500 
44,807 
0 82,972,138 
1,801 82,972,138 
0 
84 
33,914,252 
33,914,252 
- 15,962,260 8 
- 15,962,260 8 
4,394,700 4,526,955 4,990,300 4,826,500 
4,547,207 4,297,674 5,055,533 4,898,751 
79 
79 
944,649 
944,649 
1 Includes $17,003,761 for previous 6-foot canalization 
project. 
2 Includes $36,943,217 expended from 1885 to 1937 on 
operation and care ofworkofimprovement under provisions of 
permanent indefinite appropriations for such purposes. 
3 Includes $215,812 public works acceleration, executive 
1963.
4 Includes $38,766 public works acceleration, executive 
1963.
6 Excludes $251,769 contributed funds for new work. 
6 Excludes $250,102 contributed funds for new work. 
7 Excludes $1,621,349 expended in operation of snag 
boats under provisions ofpermanent indefinite appropriation 
for such purposes, and $267 transferred to project without 
reimbursement. 
8 Includes $1,040,236 Public Works funds. 
9 Includes $1,000 for removal of obstructions in Licking 
River under authority of Section 3, R&H Act of 1930. 
OI1n0c ludes $100,000 placed in Fiscal Year 1971 Budget 
Reserve. 
n1E1 xcludes $3,899 transferred from project without 
reimbursement. 
12 Surplus property valued at $3,553 transferred to project 
without reimbursement. 
13iEs xcludes $2,140 transferred to project without 
reimbursement. 
14 Excludessurpluspropertyvaluedat$73,832transferred 
to project without reimbursement. 
15 Includes $87,724,158 prior construction cost. 
e1E6x cludes surplus property valued at $297,385 
transferred to project without reimbursement. 
17 Includes $549,392 Code 710 Funds, $572,162 Code 711 
Funds, $532,677 Code 712 Funds, and $1,759,812 Code 713 
funds. 
18iIsn cludes $549,392 Code 710 Funds, $342,162 Code 711 
Funds, $532,677 Code 712 Funds, and $1,989,812 Code 713 
Funds. 
19 Includes $2,158,073 Funds provided from The 
Productive Employment Appropriations Actof 1983 (PL 98-8). 
20 Includes $920,945 cost for operations and care of 
previous projects. 
21 Includes $135,498,000 Inland Waterways Trust Funds. 
22 Includes $134,882,764 Inland Waterways Trust Funds. 
19-5 
Table 19-A 
_ _ 
)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Table 19-B Authorizing Legislation 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. Open Channel Work, Ohio River 
March 3, 1827 
January 21, 1927 
July 3, 1930 
July 3, 1958 
December 29, 1981 
H. Doc. 187, 67th Cong., 2nd Sess. 
H. Doc. 409, 69th Cong., 1st Sess. 
H. Doc. 434, 84th Cong., 2nd Sess. 
Project adopted by this act originally 
covered entire length of Ohio River 
from its mouth near Cairo to 
Pittsburgh, a distance of 981 miles. 
It provided for removal of all 
obstructions which tend to endanger 
steamboat navigation. 
Construct ice piers as a part of 
allotted from appropriations for 
general open channel work. 
Reforestation of sloughs on Kentucky 
Peninsula near Evansville, IN, and 
a 200-foot strip along bank and for 
bank protection, at an estimated cost 
of $200,000. 
Act of March 3, 1827, modified to 
include maintenance of existing 
Licking River Channel within lower 
3-mile limit of river slack water, 
at an estimated increase of $1,000 
in cost of average annual maintenance. 
Locks and Dams, Ohio River 
Act of December 29, 1981, established 
the 1,000-acre Falls of the Ohio 
National Wildlife Conservation Area, 
at a cost not to exceed $300,000. 
Act of November 17, 1988 authorized 
a replacement structure for Locks 
and Dams 52 and 53 at Olmsted, 
Illinois. 
Act of November 28, 1990, modified 
PL 97-137 by authorizing an 
interpretive center at Falls of the 
Ohio National Wildlife Conservation 
Area, at a estimated total cost of 
$3,200,000. 
Act of November 28, 1990 authorized 
a modernization of the existing 110 
foot x 600 foot lock at McAlpine 
Locks and Dam, Indiana and 
Kentucky at a total cost of $219,600,000 
with one-half appropriated from the 
Treasury and one-half from the 
Inland Waterways Trust Fund. 
19-6 
H.R. 2241, PL97-137, Title II, 
95 Stat. 1710 
PL 100-676, 100th Cong., 
2nd Sess. 
PL 101-640, 101st Cong., 
2nd Sess. 
PL 101-640, 101st Cong., 
2nd Sess. 
November 17, 1988 
November 28, 1990 
November 28, 1990

OHIO RIVER 
TABLE 19-H Construction of Locks and Dams on Ohio River 
Total Cost of Existing Project to September 30, 1992 
(See Section 1 of Text) 
Operations and 
Maintenance 
Funds New Work General Rehabilitation 
Regular 
Public Works 
Emergency Relief 
Maintenance & Operation 
Public Works Acceleration 
Executive 1963 
Total 
$1,571,911,205 
3,258,368 
1,198,837 
215,812 
$1,576,584,222 3 
$760,749,607
0 
19,000 
3,039,789 
38,766 
$763,847,162 12 
$116,886,390 
Total 
$2,449,547,202 
3,258,368 
1,217,837 
3,039,789 
254,578
0 
$116,886,390 4 $2,457,317,774 
'Excludes $36,943,217 expended from 1885 to 1937 under 
permanent indefinite appropriation. 
2Excludes $920,945 cost for operation and care ofprevious 
projects. 
Table 19-I Federal Energy Regulat 
3Excludes $87,724,158 prior construction cost. 
4Includes $33,914,252 cost for O & M Rehabilitation. 
Note:All other cost variations are listed in the Footnotes 
of Table 19-A. 
tory Commission Licenses 
At Locks and Dams, Ohio River 
Markland Dam McAlpine Dam Racine Dam Greenup Dam Hannibal Dam 
F.E.R.C License 
License 
Annual Charge 
Collections to end 
of Fiscal Year 1991 
Public Service Co. 
of Indiana 
$ 45,950.00 
$1,192,811.64 
Louisville Gas 
and Electric Co. 
$ 95,000.00 
$ 8,625,353.84 
Ohio Power Co. 
$ 64,232.00 
$ 671,065.00 
City of Vanceburg, City of New 
Kentucky Martinsville, WV 
$ 261,103.00 
$ 2,527,987.00 
-0- 
$197,589.03 
19-7 
2,211 289:1,000 2,570 2,614 3,206 
$

Ohio River Locks and Dams 
(See Section 1 of Text) 
Lock Miles 
and Below Distance From 
Dam Pittsburgh Nearest Town 
Width 
of 
Chamber 
(feet) 
Lock Dimensions 
Greatest 
Length 
Available 
For Full 
Width 
(feet) 
Lift 
(feet) 
Upper 
Normal 
Pool 
Elevation 
(feet, 
mean 
sea 
(level) 
Depth on 
Miter.Sills 
Character of 
Upper Lower Foundation 
(feet) (feet) Lock Dam 
Actual Cost 
Year to Date of 
Percent Opened to Each Lock 
Complete Navigation 'and Dam 
1 - Replaced 
6.2 Emsworth Locks 
and Dam, 
Emsworth, PA 
2 - Replaced 
3 - Replaced 
13.3 Dashields Locks 
and Dam 
1.6 miles below 
Sewickley, PA 
4 - Replaced 
5 - Replaced 
6 - Replaced 
31.7 Montgomery 
Locks and Dam, 
1.4 miles above 
Industry, PA 
7 - Replaced 
8 - Replaced 
54.4 New Cumberland 
Locks and Dam, 
Stratton, OH 
9 - Replaced 
10 - Replaced 
11 - Replaced 
84.3 Pike Island Locks 
and Dam, 2 miles 
upstream from 
Warwood, WV 
12 - Replaced 
13 - Replaced 
14 - Replaced 
126.4 Hannibal Locks 
and Dam, 1.6 miles 
upstream from New 
Martinsville, WV 
15 - Replaced 
16 - Replaced 
161.7 Willow Island 
Locks and Dam, 
2.7 miles above 
Waverly, WV 
110 
56 
110 
56 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
600 
360 
600 
360 
600 
360 
1,200 
600 
1,200 
600 
1,200 
600 
1,200 
600 
18.0 710.0 17.014 12.9 Rock Rock 
15.5 15 12.9 3 
- - $ 870,034 
100 1921 $ 43,347,635 2 14 
and 
Piles 
976,767 
1,144,588 
10.0 692.0 13.41 17.53 Rock Rock 100 1929 37,447,328 11 
1,071,472 
1,080,132 
1,123,442 
17.5 682.0 
20.5 664.5 
16.01 14.63 Rock Rock 
and and 
Piles Piles 
7.01 14.83 Rock Rock 
100 1936 37,754,307 6 
- - 1,075,000 
- - 1,167,456 
100 1959 39,099,688 
1,177,100 
1,138,000 
1,162,165 
21.0 644.0 
21.0 623.0 
17.01 
38.0 
18.01 Rock Rock 
17.0 Rock Rock 
100 1968 56,623,946 
- - 1,166,104 
- 1,222,389 
- - 1,133,371 
99 1972 87,840,211 
1,180,478 
1,275,532 
20.0 602.0 35.0 15.0 Rock 
and 
Piles 
Rock 100 1972 78,173,881 
00 
0
0
0
I
0 
l
7
J 
Table I9-J

Table 19-J 
(Continued) 
Ohio River Locks and Dams 
(See Section 1 of Text) 
Lock Dimensions 
Lock Miles 
and Below Distance From 
Dam Pittsburgh Nearest Town 
Width 
of 
Chamber 
(feet) 
Greatest 
Length 
Available 
For Full 
Width 
(feet) 
Lift 
(feet) 
Upper 
Normal 
Pool 
Elevation 
(feet, 
mean 
sea 
(level) 
Depth on 
Miter Sills Actual Cost 
Character of Year to Date of 
Upper Lower Foundation Percent Opened to Each Lock 
(feet) (feet) Lock Dam Complete Navigation 'and Dam 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
103.9 Belleville 
Locks and Dam, 
0.3 mile below 
Reedsville, OH 
- Replaced 
- Replaced 
- Replaced 
237.5 Racine Locks 
and Dam, 1.5 
miles below 
Letart Falls, OH 
- Replaced 
- Replaced 
- Replaced 
279.2 Robert C. Byrd 
Locks and Dam, 
0.7 mile below 
Hogsett, WV 
Robert C. Byrd 
Modernization 
110 1,200 
110 600 22.0 582.0 
110 
110 
110 
110 
1,200 
600 22.0 560.0 
600 
360 23.0 538.0 
37.0 15.0 
3 
Rock Rock 
and Piles 
18.0 15.0 Rock Rock 
and Piles 
18.0 15.0 Rock Rock 
100 1968 62,591,255 
- - 1,484,562 
- - 1,218,798 
- - 1,851,488 
100 1971 64,922,680 
100 1937 
110 1,200 
27 - Rehab 
Dam and New Lock 
- Replaced 
- Replaced 
- Replaced 
341.0 Greenup Locks 
and Dam, 4.9 
miles below 
Greenup, KY 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
436.2 Captain Anthony 
Meldahl Locks 
and Dam, 2.2 miles 
110 
110 
110 
110 
110 
600 
1,200 
600 
1,200 
23.0 538.0 
30.0 515.0 
600 30.0 485.0 
18.0 
18.01 
18.01 
15.0 
13.0 Rock Rock 
15.0 Rock Rock 
100 1959 57,464,191 
1,359,231 
2,951,216 
1,937,166 
3,437,057 
100 1962 74,188,216 
17 
18 
19 
20 
21 
22 
23 
N 
24 
25 
26 
$ 1,362,591 
927,091 
1,213,848 
936,696 
28 
29 
30 
31 
32 
33 
34 
1,187,542 
1,925,205 
1,307,241 
3,452,066 
253,416,627 17 
1,063,133 
1,088,802 
1,579,618

Table 19-J 
(Continued) 
Ohio River Locks and Dams 
(See Section 1 of Text) 
Lock Miles 
and Below Distance From 
Dam Pittsburgh Nearest Town 
above Foster, KY 
35 
36 
37 
38 
39 
40 
41 
I. 
I-A 
0 
42 
43 
44 
45 
- Replaced 
- Replaced 
- Replaced 
- Replaced 
531.5 Markland Locks 
and Dam, 1 mile 
above Markland, IN 
- Replaced 
- Eliminated 
Falls of the 
Ohio, 1 mile 
above McAlpine 
604.0 McAlpine Locks 
and Dam 
(Reconstruction 
of Locks and 
Dam 41) 
- Eliminated 
- Replaced 
- Replaced 
- Replaced 
720.7 Cannelton Locks 
and Dam, 
3 miles above 
Cannelton, IN 
46 - Replaced 
776.1 Newburgh Locks 
and Dam, 16 
miles above 
Evansville, IN 
47 
48 
49 
- Replaced 
- Replaced 
- Replaced 
846.0 Uniontown 
Locks and Dam, 
3.5 miles below 
Uniontown, KY 
LockDimensions 
Greatest 
Length 
Width Available 
of For Full 
Chamber Width 
(feet) (feet) 
Lift 
(feet) 
Upper 
Normal 
Pool 
Elevation 
(feet, 
mean 
sea 
(level) 
Depth on 
Miter Sills Actual Cost 
Character of Year to Date of 
Upper Lower Foundation Percent Opened to Each Lock 
(feet) (feet) Lock Dam Complete Navigation 'and Dam 
1,894,942 
3,704,535 
1,297,924 
2,857,040 
110 1,200 
110 600 
N/A N/A 
110 
110 
56 
110 
110 
200 
600 
360 
1,200 
600 
110 1,200 
110 600 
110 
110 
1,200 
600 
35.0 455.0 50.0 15.0 Rock Piles 100 1963 63,019,403 
N/A N/A N/A N/A 
N/A N/A 
49.0 
37.0 420.0 
25.0 383.0 
12.0 
19.0 
19.0 
38.0 
11.0 Rock Rock 
11.0 
13.0 Rock Rock 
0 N/A 
2,222,448 
7,658,134 ' 
2,069,193 
1008 1961 45,726,189 ' 
- - 2,592,242 
- - 2,819,930 
- - 3,202,890 
99 1972 99,032,866 1o 
3,129,028 
16.0 358.0 32.0 16.0 Rock Pile 99 1975 104,497,621 
4,415,526 
3,062,710 
3,325,964 
22.0 342.0 34.0 12.0 Rock Rock 99 1975 100,326,373 
0V 
0
y
0
0
0 
~I 
0
0
I-a

Table 19-J 
(Continued) 
Ohio River Locks and Dams 
(See Section 1 of Text) 
Lock Miles 
and Below Distance From 
Dam Pittsburgh Nearest Town 
50 - Replaced 
51 - Replaced 
918.5 Smithland Locks 
and Dam, 2 
miles above 
Smithland, KY 
52 938.9 1.4 miles below 
Brookport, IL 
938.9 1.4 miles below 
Brookport, IL 
(New lock) 
964.4 Olmsted Locks & 
Dam at Olmsted, IL 
53 962.6 10.8 miles 
above Mound 
City, IL 
962.6 10.8 miles 
above Mound 
City, IL 
(New lock) 
974.2 Mound City 
Lock and Dam, 
1 mile below 
Mound City, IL 
Width 
of 
Chamber 
(feet) 
110 
110 
Greatest 
Length 
Available 
For Full 
Width 
(feet) 
1,200 
1,200 
110 600 
110 1,200 
110 1,200 
110 600 
110 1,200 
Lift 
(feet) 
22.0 
Upper 
Normal 
Pool 
Elevation 
(feet, 
mean 
sea 
(level) 
324.0 
12.0 302.0 
12.0 302.0 
21.0 300.0 
13.4 290.0 
13.4 290.0 
Depth on 
MiterSills 
Character of 
Upper Lower Foundation 
(feet) (feet) Lock Dam 
34.0 12.0 Rock 
Actual Cost 
Year to Date of 
Percent Opened to Each Lock 
Complete Navigation 'and Dam 
- - $ 3,571,762 
- - 4,370,566 
Rock 99 1980 273,725,471 
15.4 11.0 Pile Pile 100 1928 13,337,747 n 
15.4 11.0 Pile Pile 100 1969 10,197,516 
18.0 18.0 Pile Pile 1 2006 20,730,539 18 19 
15.4 9.69 Pile Pile 100 1929 10,004,240 12 
15.4 9.6 Pile 100 1982 38,570,920 
1,539,470 " 
O
0 
TOTAL $1,774,200,535 " 
'Depths are on emergency dam foundation and recontrolling depths. "SFor preconstruction planning 1965 to 1972. No longer conslidered authorized.(See Section 1 of Text.) 
2Change from fixed dam to lift-gate dam completed in 1938. '4Includes $37,485,870 for major rehabilitation completed in FY 85. 
3Depths are on poiree dam foundation and are controlling depths. "Includes $33,914,252 for major rehabilitation completed in FY 91 (O&m funds). 
4Land chamber. "Includes $32,016,696 for major rehabilitation completed in FY 89. 
'River chamber. "Includes $127,175,225 Inland Waterways Trust Funds. 
'Roller-gate dam. Cost not included in total. Constructed under project for improving lower Kanawha River. $13,023,000 Preconstructioonn Eclnugdiense ering & Design funds. 
'Lock and Dam 41 completed with 110- by 600-foot lock in 1921. Completed with new dam and raised canal "9I ncludes $7,707,539 Inland Waterways Trust Funds. 
and lock wallin 1928. Auxiliary 56- by 360-foot lock constructed in 1929-30. Reconstruction and modernization 20 Exclusive of $6,994,235 details below. 
began 1956, renamed McAlpine Locks and Dam in 1960. Operation of auxiliary lock suspended in 1971. 
8Completed except for deferred alteration of railroad bridge. Additional Features Entering into Cost of Project 
9Dam below not yet constructed. Depth on lower miter sill at lower water. Louisville and Portland Canal and Indiana chute $ 5,359,203 
�Excludes $2,219,975 payment for settlement of damage to dam caused by barge accident in April 1978. (under previous project) 
"Includes $8,876,000 for major rehabilitation initiated in FY 79 is complete. Examinations, survey contingencies, plants, and miscellaneous 966,232 
"Includes $4,593,572 for major rehabilitation initiated in FY 79 is complete. Recreation facilities, pool area, Robert C. Byrd Locks and Dam 668,235 
TOTAL 
GRAND TOTAL 
6,994,235 
$1,781,194,770

BUFFALO, N Y DISTRICT* 
The District comprises Ohio, northwestern Pennsylvania and 
western and northern New York, embracing U.S. waters of Lake 
Erie exclusive of small portion of western end, Lake Ontario, and 
St. Lawrence River, with their tributary drainage basins 
from boundary between the states of Ohio and Michigan to 
international boundary line east of Frontier, New York. 
IMPROVEMENTS 
Navigation 
1. Ashtabula Harbor, OH 
2. Black Rock Channel and 
Tonawanda Harbor, NY 
3. Buffalo Harbor, NY 
4. Buffalo Small Boat Harbor, NY 
5. Cattaraugus Harbor, NY 
6. Cleveland Harbor, OH 
7. Conneaut Harbor, OH 
8. Dunkirk Harbor, NY 
9. Erie Harbor, PA 
10. Fairport Harbor, OH 
11. Great Sodus Bay Harbor, NY 
12. Huron Harbor, OH 
13. Irondequoit Bay, NY 
14. Little Sodus Bay Harbor, NY 
15. Lorain Harbor, OH 
16. Oak Orchard Harbor, NY 
17. Olcott Harbor, NY 
18. Oswego Harbor, NY 
19. Ottawa River Harbor, MI, OH 
20. Port Ontario Harbor, NY 
21. Rochester Harbor, NY 
22. Rocky River, OH 
23. Sandusky Harbor, OH 
24. Toledo Harbor, OH 
25. Vermilion Harbor, OH 
26. West Harbor, OH 
27. Wilson Harbor, NY 
28. Reconnaissance and condition surveys 
29. Other authorized navigation projects 
30. Navigation work under 
special authorization 
Page 
20-2 
20-2 
20-2 
20-3 
20-3 
20-3 
20-4 
20-5 
20-5 
20-5 
20-6 
20-6 
20-6 
20-6 
20-7 
20-7 
20-7 
20-8 
20-8 
20-8 
20-9 
20-9 
20-49 
20-9 
20-10 
20-10 
20-10 
20-10 
20-11 
20-11 
Beach Erosion Control 
31. Maumee Bay State Park, Ohio 
32. Presque Isle Peninsula, Erie, PA 
33. Other authorized beach erosion 
control projects 
34. Beach erosion work under 
special authorization 
Flood Control 
35. Ellicott Creek, NY 
36. Mount Morris Lake, NY 
Genesee River 
37. Reno Beach-Howard Farms Area, 
OH 
38. Inspection of completed flood 
control projects 
39. National Emergency Preparedness 
40. Other authorized flood control 
projects 
41. Flood control work under 
special authorization 
Deauthorized projects 
42. Deauthorized Projects 
General Investigations 
43. Surveys 
44. Collection and study of basic data 
45. Advance Engineering & Design 
20-1 
Page 
20-11 
20-11 
20-12 
20-12 
20-12 
20-13 
20-13 
20-13 
20-13 
20-13 
20-13 
20-14 
20-14 
20-14 
20-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Navigation 
1. ASHTABULA HARBOR, OH 
Location. On the south shore of Lake Erie, at mouth of 
Ashtabula River, 59 miles easterly from Cleveland, Ohio. (See 
NOAA Nautical Chart 14836.) 
Previous projects. For details see page 1963 of Annual Report 
for 1915, and page 1593 of Annual Report for 1938. 
Existing project. For description see pages 1297- 99 of Annual 
Report for 1966. Federal cost of completed project is 
$12,240,147. Non-Federal costs of $5,743,000, including 
contribution of $47,000, were for construction of access roads, 
docks, storage and handling facilities and dockside dredging. See 
Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $47,000 for work authorized by 1936 and 1970 acts. 
Terminal facilities. There are 16 piers and wharves. One facility 
is owned by Coast Guard. Ten facilities are along banks of 
Ashtabula River and six are on southside of outer harbor. Eleven 
terminals have railroad connections and six have mechanical 
handling facilities. Facilities are considered adequate for existing 
commerce. (See Port Series No. 42, revised 1972, Corps of 
Engineers.) 
Operations and results during fiscal year. Maintenance: Real 
estate activities, project condition sediment surveys, reformulation 
and economic analysis regarding dredging of toxic materials from 
upper River, and continuing investigation for Letter Report 
regarding construction of new Confined Disposal Facility for 
outer harbor sediment, by Government plant and hired labor cost 
$301,489. Environmental testing, by contract, cost $65,747. 
Cultural resources contract in conjunction with new CDF, by 
contract, cost $15,500. Finalization of FY90 dredging contract 
resulted in a credit of $3,959. U.S. derrickboat McCauley 
repaired 45 l.f. of the outer west breakwater at cost of $201,234. 
Engineering and design effort for dredging upper River cost 
$19,344. 
2. BLACK ROCK CHANNEL AND 
TONAWANDA HARBOR, NY 
Location. Improvement is essentially that of upper 13.5 miles 
of Niagara River from its head at Lake Erie, Buffalo, NY, to and 
including Tonawanda Harbor, NY. It comprises improvements 
formerly designated by three titles; viz, Lake Erie entrance to 
Black Rock Harbor and Erie Basin, NY, Black Rock Harbor and 
Channel, NY and Tonawanda Harbor and Niagara River, NY 
(See NOAA Nautical Chart 14832 .) 
Previous projects. For details see item 5 and 7, page 1970 of 
Annual Report for 1915, and page 1612 of Annual Report for 
1938. 
Existing project. For description of existing project and 
Federally owned Black Rock ship lock, see page 1548 of Annual 
Report for 1962. Improvement of guide pier at Black Rock Lock, 
as authorized by 1935 act was deauthorized by Congress in 
August 1977. Cost for completed portion of new work is 
$10,457,093. Enlarging of existing 21-foot turning basin and 
deepening lower 1,500 feet of Tonawanda Inner Harbor 
from 16 to 21 feet, authorized by the 1954 act, was 
deauthorized by Congress in May 1981, and is excluded from 
foregoing cost. Non-Federal costs are estimated at $1,540,000 
for costs incurred by New York State for construction of 
Erie Basin and protecting breakwater, and construction and 
extension of Bird Island Pier, and by other local interest for 
relocation of utilities. See Table 20-B for authorizing 
legislation. 
Local cooperation. Fully complied with for existing project. 
Contract for cost-shared recreation development at 
completed projects (Code 713 program) was executed by the 
New York State Department of Environmental Conservation, 
Albany, NY on April 16, 1985, and was approved by the 
Assistant Secretary of the Army and Chief of Engineers on 
May 3, 1985. 
Terminal facilities. Two facilities are along upstream end 
of channel. Below Black Rock Lock and at Tonawanda 
Harbor there are 13 privately owned terminals. There are 
two State-owned barge canal terminals at Tonawanda, NY, 
and several marine service and supply docks for recreational 
and other small craft. The Corps owns a wharf adjacent to 
Black Rock Lock which is private. Ten terminals have 
railroad connections and six mechanical-handling facilities. 
Facilities considered adequate for existing commerce. (Port 
Series No. 41, revised 1971, Corps of Engineers.) 
Operations and results during fiscal year. Operation and 
care (Black Rock Lock): Lock was in operation 284 days and 
closed for annual winter maintenance from January 12, 1992 
through April 5, 1992. Ordinary maintenance and repair of 
structures and grounds was accomplished throughout the 
year by Government plant and hired labor. Total costs of 
$3,664,062 were distributed as follows: Operation and care: 
operation of lock, ordinary maintenance and repair $446,089; 
maintenance of grounds $39,475; real estate activities, project 
condition sediment surveys, and support of Water Control 
Center $63,011. A/E contract for stability analyses of 
lockwall was finalized at cost of $2,700. Lockwall 
maintenance by hired labor cost $194,114. Repairs to 60 1.f. 
of Bird Island Pier by U.S. derrickboat McCauley cost 
$65,520. Contract to pressure grout lockwall foundation to 
fill voids cost $2,177,489. Snagging and clearing at lock cost 
$65,520. Engineering and design for lockwall maintenance 
cost $334,401. Supervision and administration cost $275,743. 
3. BUFFALO HARBOR, NY 
Location. At eastern end of Lake Erie, at head of 
Niagara River, 176 miles easterly from Cleveland, Ohio. (See 
NOAA Nautical Charts 14820 and 14833.) 
Previous projects. For details see page 1967 of Annual 
Report for 1915 and page 1606 of Annual Report for 1938. 
Existing project. For description see page 1368 of Annual 
20-2

BUFFALO, N Y DISTRICT 
Report for 1963. In addition, on December 15, 1980, OCE 
authorized the removal of bridge abutments of South Michigan 
Avenue Bridge. New work for completed project cost 
$18,837,601. Estimated non-Federal costs were $9,188,000 for 
deepening, widening, and improving Buffalo River and ship canal, 
constructing piers, retaining walls, and dikes and performing 
dock-side dredging. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. There are 45 wharves and piers of which 4 
piers, owned by Niagara Frontier Port Authority, and 9 privately 
owned and operated facilities are on outer harbor and along 
sides of Lackawanna and Union ship canal, 4 along banks of 
Buffalo ship canal, and 26 along Buffalo River. Coast Guard 
facilities are at mouth of Buffalo River along left bank. City of 
Buffalo owns a slip on right bank of Buffalo River just north of 
Michigan Avenue Bridge for mooring city fireboat. Thirty-four 
terminals have railroad connections and 29 mechanical-handling 
facilities. Facilities considered adequate for existing commerce. 
(See Port Series Nevised 1971, Corps o. 41, rof Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, project condition sediment 
surveys by Government plant and hired labor, water control 
management, and real estate activities cost $205,077. 
Environmental testing, by contract, and supervision and review 
of those contracts cost $223,970. Repairs to about 651.f. of South 
breakwater by U.S. derrickboat McCauley cost $273,363. Snagging 
and clearing cost $29,189. Approximately 120,000 cubic yards of 
material was dredged from Buffalo River at a cost of $867,441. 
A demonstration of dredging methods to evaluate the 
effectiveness of dredge methods in minimizing sediment 
resuspension was conducted as part of the dredging in Buffalo 
River. Monitoring activities and sample collection were 
conducted during the field demonstration. Maintenance at Dike 
4 disposal area cost $85,524. Engineering and design effort cost 
$174,622. Supervision and administration cost $41,572. 
4. BUFFALO SMALL BOAT HARBOR, NY 
Location. At eastern end of Lake Erie, at head of Niagara 
River, 176 miles easterly from Cleveland, Ohio (See NOAA 
Nautical Charts 14820 and 14833). 
Existing project. For details of the existing project, see page 
20-3 of Annual Report for 1991. Construction was completed in 
May 1992. See Table 20-B for authorizing legialation. 
Local cooperation. A Local Cooperation Agreement between 
the Federal Government and the local sponsor, the Niagara 
Frontier Transportation Authority, was executed by the Assistant 
Secretary of the Army on July 11, 1991. The local sponsor will 
provide 50% of project costs. 
Operations and results during fiscal year. New Work: Federal 
costs were $9,680 for in-house engineering effort, $850 for real 
estate and $216,144 for construction contract, including 
supervision and administration. Non- Federal costs were $1,696 
for in-house engineering effort and $454,008 for construction 
contract, including suervision and administration. Construction 
was completed in May 1992. 
5. CATARAUGUS HARBOR, NY 
Location. At mouth of Cattaraugus Creek on south shore 
of Lake Erie about 12 miles northeasterly from Dunkirk 
Harbor, NY and 24 miles southwesterly from Buffalo 
Harbor, NY (See NOAA Nautical Chart 14823.) 
Existing project. For details of the existing project, see 
page 32-4 of Annual Report for 1983. Construction was 
completed in January 1983. Total Federal cost for new work 
was $4,804,060. Total non-Federal cost for new work was 
$2,566,529, excluding $20,000 for lands. Existing project was 
authorized by 1968 River and Harbor Act (H. Doc. 97, 90th 
Cong., 1st sess.) 
Local cooperation. See page 32-5 of Annual Report for 
1976 for details of requirements of local cooperation. The 
cash contribution paid was $2,566,529. The State of New 
York executed local cooperation agreement in July 1981. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys, real estate activities and 
engineering and design effort cost $10,424. 
6. CLEVELAND HARBOR, OH 
Location. On south shore of Lake Erie, at mouth of 
Cuyahoga River, 176 miles westerly from Buffalo, NY (See 
NOAA Nautical Chart 14839). 
Previous projects. For details see page 1962, Annual 
Report for 1915, and page 1585, Annual Report for 1938. 
Existing Project. For description of existing project, as 
authorized through the 1966 modification, see page 1269 of 
Annual Report for 1967. Further improvements in the 
interest of commercial navigation and recreational navigation 
were authorized in the 1985 Supplemental Appropriations 
Act (PL 99-88), at a cost not to exceed $36,000,000. The 
commercial navigation portion of the overall project consists 
of: (a) enlarging and deepening to 31 feet LWD the east 
entrance channel; (b) deepening the east basin channel to 27 
feet LWD; and (c) expanding the capacity of Dike Site 14 to 
contain the polluted dredged material resulting from the 
project. This portion of the project is currently on hold as 
the local sponsor has assigned this aspect a lower priority. 
The recreational navigation portion of the overall project 
consists of: an entrance channel 100 feet by 540 feet in 
length with a depth 8.0 feet below Low Water Datum 
(LWD) and the associated 360 feet of rubble mound 
revetment along the west side of Pier 34; removal of a 
portion of the east and west dock walls of Pier 34; removal 
of the south dock wall of Slip 32; construction of a 386 foot 
breakwater with a 20-foot top width and shore arm 
connection to Pier 32 and 406 feet of associated bulkheading; 
construction of a 455 foot breakwater and 640 feet of 
associated bulkheading along the north end of Pier 34 
extending to and along the west end of Pier 36, and 1.8 acres 
of fill between Pier 34 and Pier 36; a 6.4 acre turning basin, 
20-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
anchorage area, and harbor-of-refuge with a dredged depth 
varying between 7.0 and 8.0 feet below LWD and the 1,223 feet 
of associated bulkheading; 2,098 feet of walkway 10.0 feet wide 
along the anchorage area and the west and north face of Pier 34 
to include along the north face of the filled portion of the former 
Slip 34; 1,733 linear feet of suitable handrail along the 
breakwater and anchorage area; and 875 linear feet of bollards 
and chain along the north and west face of Pier 34 as generally 
described in a report entitled "Technical Report, North Coast 
Harbor/Pier 34, Cleveland Harbor, Ohio" prepared by the 
District Commander, U.S. Army Engineer District, Buffalo, New 
York, dated February 1992. A portion of the recreational 
navigation project has been completed by the Ohio Department 
of Natural Resources. The recreational navigation project was 
also authorized by the Water Resources Development Act of 
1986 (PL 99-662) and the FY88 Energy and Water 
Appropriations Act (PL 100-202). These acts also authorized 
additional undefined improvements to Cleveland Harbor. A 
portion of the project was deauthorized by the Intermodal 
Surface Transportation Efficiency Act of 1991. Estimated total 
Federal cost of the existing project is $33,852,100 (Oct.1991) 
exclusive of undefined, inactive and deferred portions of the 
project. The amount of $29,315,100 is for completed work and 
the balance of $4,537,000 is for new work. Estimated non-Federal 
cost is $13,740,000 (Oct. 1991) of which $9,203,000 is actual cost 
for completed work and the balance of $4,537,000 is required for 
work authorized by PL 99-88, PL 99-662, and PL 100-202. 
Remaining work authorized by 1946 River and Harbor Act, 
consisting of widening and deepening the right bank of Cuyahoga 
River at the downstream end of Cut 4, is considered inactive and 
excluded from foregoing cost estimate. Estimated Federal cost 
(1966) of this portion is $85,600 and non-Federal cost (1966) 
$5,000,000. Remaining work authorized by 1958 R&H Act, 
consisting of planning and replacement of bridges number 19 
(E.L.R.R.) and 32 (B. & O.R.R.) and widening Cuyahoga and 
Old River channels, and remaining work authorized by the 1960 
R&H Act, consisting of deepening the remainder of Cuyahoga 
River from bridge number 1 to and including the Old River to 
a depth of 27 feet, has been classified as deferred and is also 
excluded from foregoing estimate. Estimated Federal cost (Oct. 
1976) of this portion is $18,033,300 and estimated non-Federal 
cost (Oct. 1976) is $21,251,000. The 1989 Energy and Water 
Development Appropriations Act (PL 101-101) authorized the 
Corps to begin a Reconnaissance study of the Cuyahoga River, 
to address the concerns of boat traffic congestion and related 
risks, accidents and safety of the public. Preliminary plans were 
studied to alleviate the commercial navigation problem and 
inadequate width and depth, in the Old and Cuyahoga Rivers. 
The cost of this Reconnaissance study was $250,000. The 
Reconnaissance Report recommended a feasibility study for one 
plan which had the potential for commercial (priority) outputs. 
The non-Federal sponsor did not commit to provide its share of 
the cost of the feasibility phase of the study; therefore, this study 
will be terminated. See Table 32-B for authorizing legislation. 
Local cooperation. For details of local cooperation, see page 
32-4 of FY 87 Annual Report. 
Terminal facilities. There are 65 piers and wharves. 
Fourteen are located in the outer harbor, 11 on banks of Old 
River, 40 along the deep-draft section of Cuyahoga River. 
Forty-one terminals have both railroad connections and 
mechanical-handling facilities. The Corps owns a wharf at 
the foot of East 9th Street. Facilities are considered 
adequate for existing commerce. (See Port Series No. 43, 
revised 1981, Corps of Engineers). 
Operations and Results during fiscal year. New Work: FY 
92 costs for North Coast Harbor/Pier 34 for in-house 
engineering effort were $25,896. Real estate activities cost 
$9,064. Review of construction contract awarded late in FY 
1992 cost $7,225. FY 92 costs for the Cuyahoga River study 
were $30 for in-house reconnaissance effort. Maintenance: 
Miscellaneous inspection services, condition sediment 
surveys, letter report on new confined disposal facility 
(CDF), economics report and real estate activities cost 
$397,287. Environmental testing, by contract, cost $121,300. 
Repairs to 125 l.f. of east breakwater and 30 l.f. of CDF by 
U.S. derrickboat Simonsen cost $628,318. Breakwater repair 
by contract cost $2,064,032. Removal of approximately 
220,000 cubic yards of shoaled material from the Cuyahoga 
River, by contract, cost $1,687,302. Settlement of claim from 
FY78 dredging contract cost $303,126. Engineering and 
design costs for dredging, new CDF, and breakwater repairs 
were $244,690. Supervision and administration costs were 
$286,753. 
7. CONNEAUT HARBOR, OH 
Location. On the south shore of Lake Erie, at mouth of 
Conneaut River, 73 miles easterly from Cleveland, Ohio. 
(See NOAA Nautical Chart 14824.) 
Previous projects. For details see page 1964, Annual 
Report for 1915. 
Existing project. For description see page 1274 of Annual 
Report for 1967. Actual costs for new work for completed 
portion of the project were $7,541,369. See page 1274, 
Annual Report for 1967, for complete description of project 
modification authorized by 1966 R&H Act. Authorization of 
this modification was continued by the 1990 Water 
Resources Development Act. Estimated cost (1970) for this 
modification is $717,000. For completed work, non-Federal 
costs were $200,000 for dockside dredging and removal of 
existing dolphins. Estimated non-Federal cost of $2,877,000 
(1970) includes cash contribution of $717,000 and the 
remainder is for construction of service facilities for the 1966 
project modification. See Table 20-B for authorizing 
legislation. 
Local cooperation. Fully complied with for completed 
portion of project. See page 32-6 of Annual Report for 1971 
for requirements of local cooperation for project 
modification as authorized by the River and Harbor Act of 
1966. 
Terminal facilities. There are seven piers and wharves. Six 
20-4

BUFFALO, N Y DISTRICT 
are privately owned and operated and located in inner harbor. 
Remaining facility is city owned on the south side of outer 
harbor. Six terminals have railroad connections and four 
mechanical-handling facilities. (See Port Series No. 42, revised 
1972, Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, project condition sediment 
surveys, real estate activities and economic study by Government 
plant and hired labor cost $45,255. Finalization of FY91 dredging 
contract cost $207. Repairs to 70 i.f. of east and west 
breakwaters by U.S. derrickboat McCauley cost $301,274. 
Engineering and design costs for breakwater repair were $39,998. 
8. DUNKIRK HARBOR, NY 
Location. On south shore of Lake Erie, 37 miles southwesterly 
from Buffalo, NY (See NOAA Nautical Chart 14823.) 
Previous projects. For details see page 1966 of Annual Report 
for 1915, and page 1604 of Annual Report for 1938. 
Existing project. For description of completed portion of 
existing project see page 32-8 of Annual Report for 1976. For 
description of small boat harbor project as authorized under 
Section 201 of Flood Control Act of 1965, see page 32-8 of 
Annual Report for 1978. Actual costs for completed work are 
$3,010,024. Actual non-Federal costs are $1,961,000. See Table 
20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys and real estate activities cost 
$14,110. Finalization of environmental testing contract cost 
$4,910. U.S. derrickboat McCauley repaired 120 1.f. of the U.S. 
breakwater at cost of $112,731. Engineering and design effort 
cost $866. 
9. ERIE HARBOR, PA 
Location. On southerly side of bay formed by Presque Isle 
Peninsula, on south shore of Lake Erie, 78 miles westerly from 
Buffalo, NY. (See NOAA Nautical Chart 14835.) 
Previous projects. For details see page 1965 of Annual Report 
for 1915 and page 1600 of Annual Report for 1938. 
Existing projects. For description see pages 1363-64 of Annual 
Report for 1963. Entire project modification authorized by 1945 
River and Harbor Act, providing for deepening channel and 
basin, both 23 feet deep, to Penn Central Company coal docks 
at westerly end of harbor, was deauthorized by Congress in 
August 1977. Actual costs for new work for completed portion of 
project were $2,860,906. Extension of north pier portion, 
authorized by 1899 Act was deauthorized in November 1981. A 
portion of work authorized by 1960 Act, deepening strips 
adjacent to north and south piers, was deauthorized in August 
1982. Non- Federal costs for completed work were $51,000 for 
providing ore dock and dredging slip adjacent thereto. See Table 
20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Sixteen piers and wharves, of which 12 
are privately owned and operated. Erie International Marine 
Terminal No. 1 owned by Port Commission, city of Erie, is 
along main waterfront on southside of Presque Isle Bay and 
Coast Guard facilities are on north side. Two offshore oil 
docks are on Lake Erie. Eight terminals have railroad 
connections and six mechanical-handling facilities. Facilities 
are considered adequate for existing commerce. (See port 
Series No. 42, revised 1972, Corps of Engineers.) 
Operations and result during fiscal year. Maintenance: 
Miscellaneous operations services, project condition sediment 
surveys, and real estate activities by Government plant and 
hired labor cost $47,403. Environmental testing, by contract, 
cost $36,023. Engineering and design effort relative to north 
pier tierod bolts cost $11,253. 
10. FAIRPORT HARBOR, OH 
Location. On south shore of Lake Erie at mouth of Grand 
River, 33 miles easterly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14837.) 
Previous projects. For details see page 1963 of Annual 
Report for 1915, and page 1590 of Annual Report for 1938. 
Existing project. For description of existing project as 
authorized through the 1960 modifications, see page 1526 of 
Annual Report for 1962; for description of small boat harbor 
as authorized by Sec. 201 of 1965 Flood Control Act, see 
page 32-10 of Annual Report for 1977. Authorization of this 
modification was continued by the 1990 Water Resources 
Development Act. Estimated total Federal cost of new work 
is $4,931,000 (Oct. 1980) of which $2,591,000 is actual cost 
for completed portion of project and the balance of 
$2,340,000 is for proposed work authorized by See. 201 of 
the 1965 Flood Control Act, which is deferred. Entire project 
modification authorized by 1960 River and Harbor Act, 
providing for deepening lake approach channel, 800-foot 
wide channel through outer harbor and channel in Grand 
River, and enlargement of turning basin, is classified inactive 
and is excluded from foregoing cost. This authorization was 
also continued by the 1990 Water Resources Development 
Act. Estimated Federal cost of this modification is $7,870,000 
(Mar. 1991). Estimated non-Federal cost is $4,991,000, of 
which $101,000 was for bulkheads and dockside dredging for 
completed portion of project and $2,560,000 which includes 
cash contribution of $2,330,000, is for work authorized by 
Sec. 201 of the 1965 Flood Control Act. For the inactive 
1960 project modification, estimated non-Federal cost of 
$26,400,000 (Mar. 1991) is for lands, relocations, utility 
changes, dock dredging and bulkhead modifications. See 
Table 20-B for authorizing legislation. 
Local cooperation. See page 32-11 of 1976 Annual Report 
regarding assurances of local cooperation for work 
authorized by R&H Acts of 1927 and 1960 and page 32-11 
of 1977 Annual Report for requirements of local cooperation 
for work authorized by Sec. 201 of 1965 Flood Control Act. 
20-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Terminal facilities. Sixteen piers and wharves, all along banks 
of Grand River. One facility is owned by Coast Guard. Nine 
terminals have railroad connections and ten mechanical-handling 
facilities. Facilities considered adequate for existing commerce. 
(See Port Series No. 42, revised 1972, Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous operations services, real estate activities, and 
project condition sediment surveys by Government plant and 
hired labor cost $51,636. Removal of approximately 145,000 cubic 
yards of shoaled material, by contract, cost $649,480. 
Environmental testing, by contract, cost $20,295. Engineering and 
design effort cost $36,125. Supervision and administration cost 
$48,454. 
11. GREAT SODUS BAY HARBOR, NY 
Location. On Sodus Bay, which is a nearly land-locked 
indentation on south shore of Lake Ontario, 29 miles westerly 
from Oswego, NY. (See NOAA Nautical Chart 14814.) 
Previous projects. For details see page 1972 of Annual Report 
for 1915 and page 1526 of Annual Report for 1938. 
Existing project. For description, see page 1380 of Annual 
Report for 1963. Improvements authorized by 1962 act, consisting 
of deepening lake approach channel, entrance channel and inner 
approach channel were deauthorized by Congress in August 
1977. Actual costs of new work for completed portion of project 
were $249,187. Costs incurred by local interests are not available. 
See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: Real 
estate activities by hired labor cost $6,031. U.S. derrickboat 
McCauley repairs inititated in FY91 were completed at cost of 
$34,580. 
12. HURON HARBOR, OH 
Location. On south shore of Lake Erie at mouth of Huron 
River, 47 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14843.) 
Previous project. For details, see page 1961 of Annual Report 
for 1915, and page 1576 of Annual Report for 1938. 
Existing project. For description, see page 1347 of Annual 
Report for 1963 and page 32-12 of Annual Report for 1978. Cost 
of completed portion of existing project was $4,834,006. 
Construction of detached breakwater as authorized by 1962 R&H 
Act was deauthorized January 1, 1990. Non-Federal costs of 
$163,000 were incurred by local interests in 1963 for dockside 
dredging of areas between Federal improvement and terminal 
facilities. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Six privately owned wharves and docks, one 
along left bank of Huron River and remainder along right bank. 
Four terminals have railroad connections and four 
mechanical-handling facilities. Facilities are regarded as adequate 
for existing commerce. (See Port Series No. 42, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous operations services, project condition sediment 
surveys, economic study and real estate activities by 
Government plant and hired labor cost $68,387. Removal of 
approximately 230,000 cubic yards of shoaled material, by 
contract, cost $913,924. Environmental testing, by contract, 
cost $25,870. Engineering and design effort cost $23,462. 
Supervision and administration cost $27,943. 
13. IRONDEQUOIT BAY, NY 
Location. On south shore of Lake Ontario, 4 miles east of 
Rochester, NY at mouth of Irondequoit Creek, Monroe 
County, NY (See NOAA Nautical Charts 14804 and 14815). 
Existing project. For details of existing project, see page 
32-7 of Annual Report for FY87. Total estimated project 
cost is $15,363,000 (Oct. 1984) including $3,582,000 Federal 
(which includes the CoE $3,536,000 and the USCG $46,000) 
and $11,781,000 non-Federal, including a cash contribution 
of $2,661,000, lands and damages $290,000 and the cost of a 
movable highway bridge $8,830,000. Existing project was 
authorized by 1958 River and Harbor Act (H. Doc. 332, 84th 
Cong., 2d sess.). 
Local cooperation. The Buffalo District has a properly 
executed Local Cooperation Agreement with New York 
State, executed April 20, 1983. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, real estate activities and 
project condition sediment surveys by Government plant and 
hired labor cost $2,127. Cost for U.S.derrickboat McCauley 
passage through Welland Canal to Lake Ontario was $52. 
Environmental activities cost $13,274. Engineering and 
design cost for FY93 dredging were $21,658. 
14. LITTLE SODUS BAY HARBOR, NY 
Location. Little Sodus Bay, on south shore of Lake 
Ontario, 15 miles west of Oswego, NY (See NOAA Nautical 
Chart 14803.) 
Previous projects. For details see page 1973 of Annual 
Report for 1915, and page 1628 of Annual Report for 1938. 
Existing project. For description see page 1378 of Annual 
Report for 1958. New work for completed project cost 
$69,066. Non-Federal costs of $6,000 were incurred for 
channel dredging. See Table 20-B for authorizing legislation. 
Local cooperation. Not required. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and project condition 
sediment surveys by Government plant and hired labor cost 
20-6

BUFFALO, N Y DISTRICT 
$6,013. Finalization of stone purchase for FY91 derrickboat work 
cost $1,029. Engineering and design effort for repair to east 
breakwater cost $4,818. 
15. LORAIN HARBOR, OH 
Location. On south shore of Lake Erie at mouth of Black 
River, 25 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14841.) 
Previous projects. For details, see page 1961 of Annual Report 
for 1915, and page 1580 of Annual Report for 1938. 
Existing project. For description see pages 1319-22 of Annual 
Report for 1966. Federal cost of new work is $20,475,000. 
Deepening and widening remainder of Black River Channel at 
Cut 1 and construction of bank stabilization, authorized by 1960 
Act and modified by 1965 Act was deauthorized January 1, 1990. 
A portion of work authorized by 1960 act, dredging of 15-to-25 
foot wide strips adjacent to the U.S. East and West piers was 
also deauthorized January 1, 1990. Total non-Federal cost is 
$3,000 contributed by local interests towards construction of west 
shorearm. See Table 20-B for authorizing legislation. The Water 
Resources Development Act (WRDA) of 1986 (PL 99-662) 
authorized construction of commercial navigation improvements 
consisting of two bend cuts on the Black River to widen and 
straighten the channel between the Norfolk and Western 
Railroad Bridge and the 21st Street Bridge. These cuts are to be 
excavated to the existing channel depth of 27 feet. The 
authorized plan also includes widening the Upper Turning Basin 
at the existing depth of 21 feet. Estimated costs for this work are 
$2,290,000 Federal and $1,510,000 non-Federal (Oct. 1989). This 
portion of the project has been classified deferred. On March 12, 
1986, the Chief of Engineers under authority of Section 107 of 
the 1960 River and Harbors Act, as amended, authorized 
construction of a small boat harbor which was completed in July 
1987. The project consists of a 225-foot detached rubblemound 
breakwater and an 800-foot long rubblemound breakwater 
attached to the east breakwater shorearm in the east basin of the 
outer harbor. Construction costs for this project, including 
supervision and administration, were $775,025 Federal and 
$775,025 non-Federal. 
Local cooperation. For completed work, local interests 
contributed $3,000. Work authorized by 1960 Act (and modified 
by 1965 Act) is deauthorized. All other conditions fully complied 
with. On March 25, 1986, the city of Lorain, Ohio signed the 
Local Cooperation Agreement (LCA), for the Section 107 
project. For details see page 32-7 of Annual Report for 1986. For 
details of LCA for deferred project authorized by the 1986 
WRDA, see page 32-9 of Annual Report for FY 87. 
Terminal facilities. There are 23 piers and wharves, of which 
three are on outer harbor and remainder are along banks of 
Black River. Two are owned by the city. Eight terminals have 
railroad connections and 15 mechanical-handling facilities. 
Facilities are considerd adequate for existing commerce. (See 
Port Series No. 42, revised 1972, Corps of Engineers .) 
Operations and results during fiscal year. New Work: FY 92 
costs of $92 were for in-house engineering effort (Advance 
Engineering and Design Preconstruction Engineering and 
Design). Maintenance: Miscellaneous inspection services, 
real estate activities and project condition sediment surveys 
by Government plant and hired labor cost $78,761. A/E 
contract for monitoring movement of lighthouse on 
breakwater cost $4,244. Repairs to 100 1.f. of east breakwater 
by U.S. derrickboat Simonsen cost $792,532. Removal of 
approximately 170,000 cubic yards of shoaled material from 
the upper portion and turning basin of Black River by 
contract cost $463,733. Engineering and design effort for 
dredging and foundation repair for lighthouse cost $134,818. 
Supervision and administration cost $13,090. 
16. OAK ORCHARD HARBOR, NY 
Location. On south shore of Lake Ontario at mouth of 
Oak Orchard Creek, 33 miles westerly of Rochester, NY. 
(See NOAA Nautical Chart 14805.) 
Previous project. For details see page 628 of Annual 
Report for 1905. 
Existing project. For description of completed existing 
project see page 32-14 of 1975 Annual Report. Actual 
Federal cost for completed project was $1,613,500. Estimated 
non-Federal cost is $270,000 (July 1971) including cash 
contribution of $170,700 and $54,002 for recreational 
facilities and remainder for lands and construction of wharf. 
Existing project was authorized by the 1945 River and 
Harbor Act (H. Doc. 446, 78th Cong., 2d sess.). 
Local cooperation. Fully complied with. Local interests 
contributed $224,702. 
Terminal facilities. There is no commercial navigation at 
Oak Orchard Harbor. Terminal facilities consist of private 
docks for recreational craft. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys and real estate activities 
cost $1,525. Finalization of FY91 dredging contract cost 
$947. Environmental testing, by contract, cost $34,687. 
17. OLCOTT HARBOR, NY 
Location. On south shore of Lake Ontario, at mouth of 
Eighteen Mile Creek, about 18 miles east of mouth of 
Niagara River and 63 miles by water west of Rochester, NY. 
(See NOAA Nautical Chart 14806.) 
Previous project. For details see page 1971 of Annual 
Report for 1915 and page 1621 of Annual Report for 1938. 
Existing project. For description, see page 1555 of Annual 
Report for 1962. Cost of new work for completed project 
was $1,500 exclusive of amount expended on previous 
projects, all of which was contributed by local interests. See 
Table 20-B for authorizing legislation. The authorized 
modification to the existing project consists of breakwaters 
to provide optimum harbor protection, a stone jetty and 
recreational fishing facilities including a foot bridge, 
walkways and guardrails, access facilities, sanitary facilities 
and parking areas. The estimated cost of the authorized 
modification is $17,000,000 (Oct. 1990) of which $8,500,000 
20-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
is Federal and $8,500,000 is non-Federal. Modification of the 
existing project was authorized by the 1986 Water Resources 
Development Act (WRDA) (PL 99-662). 
Local cooperation. Fully complied with for completed project. 
Local interests contributed $1,500. Modifications authorized by 
the 1986 WRDA will require local interests to pay 50% of 
project cost including lands, easements, rights-of-way and dredge 
disposal areas. They are also responsible for construction of 
necessary docks and berthing spaces, construction of launching 
ramp, parking areas, sanitary facilities, and necessary access 
roads. After construction, non-Federal responsibilities would 
include fishing facility maintenance, except for the aids to 
navigation. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. New Work: In-house 
engineering effort for Advance Engineering and Design 
Preconstruction Engineering and Design for FY 92 was $98,719. 
Real estate activities cost $3,163. Maintenance: Project condition 
sediment surveys and real estate activities cost $7,861. 
18. OSWEGO HARBOR, NY 
Location. On south shore of Lake Ontario, at mouth of 
Oswego River, 59 miles easterly from Rochester, NY. (See 
NOAA Nautical Chart 14813.) 
Previous projects. For details see page 1973 of Annual Report 
for 1915, and page 1630 of Annual Report for 1938. 
Existing project. For description see pages 1383-84 of Annual 
Report for 1963. Completed portion of project cost $7,242,039 
and non-Federal costs for completed work were $4,440,000 for 
lands, dockside dredging, construction of terminal wharves, and 
cargo handling facilities. Deepening a 200-foot wide strip along 
harbor line east of mouth of Oswego River, remaining feature of 
work authorized by the 1930 Act, was deauthorized January 1, 
1990. Deepening to 22 feet a 150-foot wide strip along harbor 
line in west outer harbor, remaining feature of work authorized 
by 1940 Act, was deauthorized in May 1981. See Table 20-B for 
authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Seven piers and wharves in harbor and 
along river channel. In addition, Port of Oswego Authority owns 
two public terminals, one of which is west of river and includes 
a grain elevator and warehouse for miscellaneous freight. Other 
terminal is east of river and used for handling aluminum and 
general cargo. State of New York owns a river terminal used for 
mooring vessels. City of Oswego owns one dock and shore 
facilities for recreational craft. Facilities considered adequate for 
existing commerce. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services, real estate activities and 
project condition sediment surveys by Government plant and 
hired labor cost $2,206. Finalization of environmental testing cost 
$3,159. U.S. derrickboat McCauley completed structure repairs 
inititated in FY91 at cost of $49,198. Engineering and design 
effort cost $1,523. 
19. OTTAWA RIVER HARBOR, MI & OH 
Location. At westerly end of Lake Erie, at Toledo, OH, 99 
miles westerly from Cleveland, OH (See NOAA Nautical 
Chart 14847). 
Existing project. A reevaluation study and report 
investigated the authorized project as described in the 1976 
Phase I General Design Memo (GDM) and developed 
several scaled down alternatives including: (1) No Action, (2) 
the 1976 GDM plan: (a) a bay channel 8 feet deep, 100 feet 
wide and 16,700 feet long between the Toledo Harbor 
channel and the mouth of the Ottawa River; (b) A river 
channel 6 feet deep, 80 feet wide and 8,260 feet long 
between the mouth of the river and the Summit Street 
bridge and 5 feet deep, 80 feet wide and about 7,630 feet 
long between the Summit Street and Suder Avenue bridges; 
and (c) A confined diked facility (CDF) for dredged 
material. (3) Dredging Ottawa River channel from Summit 
Street to 4 feet deep and the Bay Channel to 5 feet deep 
with disposal in Island 18. (4) Same as 3 except disposal in 
a new CDF. (5) Dredging Ottawa River Channel from 
Summit Street to 5 feet deep and the Bay Channel to 6 feet 
deep with disposal in Island 18. (6) Same as 5 except 
disposal in a new CDF. Currently the selected alternative is 
the No Action plan since there is no letter of intent to cost 
share in this project and project is not economically justified. 
The project was originally authorized under provisions of 
Section 201 of the 1965 Flood Control Act (PL 89-298) by 
the House and Senate Committees on Public Works 
Resolutions dated December 15 and 17, 1970, respectively. 
Authorization was continued by the 1990 Water Resources 
Development Act (PL 101-640). 
Local cooperation. The potential local sponsor is Lucas 
County Port Authority, Toledo, OH. The local sponsor must 
provide 50% of the total project cost which includes lands, 
easements, rights-of-way, relocations and a disposal area for 
dredged material (LERRD). 
Operations and results during fiscal year. New Work: 
FY92 cost was $47,586 for real estate and $43,479 for 
in-house engineering effort to write the Reevaluation Report. 
20. PORT ONTARIO HARBOR, NY 
Location. On southeasterly end of Lake Ontario, 19 miles 
northeasterly of Oswego, NY and 32 miles southerly of 
Sackets Harbor, NY. (See NOAA Nautical Chart 14803.) 
Previous projects. Adopted by the River and Harbor Act 
July 4, 1836. Only information available is the index to the 
report of the Chief of Engineers. 
Existing project. For description see page 32-17 of Annual 
Report for 1978 and and page 32-16 of Annual Report for 
1976. Non-Federal cost for new work was $1,467,132 
including cash contribution of $1,431,507. Existing project 
was authorized by the River and Harbor Act of March 2, 
1945 (H. Doc 446, 78th Cong., 2d sess.). 
20-8

BUFFALO, N Y DISTRICT 
Local cooperation. See page 32-16 of Annual Report for 1976 
for details of requirements of local cooperation. Assurances were 
received from the New York State Office of Parks, Recreation 
and Historic Preservation. The LCA was executed on June 24, 
1986. 
Terminal facilities. The only commercial navigation at Port 
Ontario is charter boat fishing. Terminal facilities consist of 
private docks for recreational craft. 
Operations and results during fiscal year. New Work: Actual 
construction of the project was completed in October 1987. FY92 
Federal cost was $4,656 for real estate activities. Maintenance: 
Project condition sediment surveys and real estate activities cost 
$5,607. 
21. ROCHESTER HARBOR, NY 
Location. On south shore of Lake Ontario, at mouth of 
Genesee River, 59 miles westerly from Oswego, NY. (See NOAA 
Nautical Chart 14815.) 
Previous project. For details see page 1471 of Annual Report 
for 1915, and page 1623 of Annual Report for 1938. 
Existing project. For description see page 1556 of Annual 
Report for 1962. Actual cost for new work for completed project 
is $2,191,514. Non-Federal costs are estimated at $2,260,000, all 
for 1960 Act, for lands, relocation of submarine cable crossing, 
relocations of small docks and boathouses, dockside dredging, 
structure modifications, and replacement of Baltimore & Ohio 
coal loader. See Table 20-B for authorizing legislation. 
Local cooperation. Complied with except provision for 
replacement of coal loading facility as required by River and 
Harbor Act of July 14, 1960. 
Terminal facilities. One terminal facility at mouth of Genesee 
River has been leased to the Great Lakes Division of Pittston 
Stevedoring Corp. Facilities also consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. Facilities 
are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous operations services, real estate activities, 
environmental activities, and project condition sediment surveys 
by Government plant and hired labor cost $74,687. Removal of 
165,251 cubic yards of shoaled material, by contract, from the 
Genesee River and entrance channel cost $527,119. Engineering 
and design effort cost $28,766. Supervision and administration 
cost $48,036. 
22. ROCKY RIVER HARBOR, OH 
Location. At mouth of Rocky River which empties into Lake 
Erie 7 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14826.) 
Existing project. For description see page 1329 of Annual 
Report for 1966. Federal cost for completed project was $343,494 
and non-Federal cost was a cash contribution of $249,346. See 
Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $249,346 for new work. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately-owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and project condition 
sediment surveys by Government plant and hired labor cost 
$7,615. Finalization of FY91 dredging contract cost $22,175. 
Engineering and design effort cost $2,263. Supervision and 
administration cost $11,637. 
23. SANDUSKY HARBOR, OH 
Location. On south shore of Lake Erie, in southeastern 
portion of Sandusky Bay, 50 miles westerly from Cleveland, 
Ohio. (See NOAA Nautical Chart 14845.) 
Previous project. For description see pages 1511-12 of 
Annual Report for 1962. Actual costs for new work for 
completed project were $6,250,121, excluding $325,000 
contributed by local interests. Non-Federal costs for 
completed project are estimated at $675,000, including 
$325,000 cash contribution and the remaining $350,000 is for 
dockside dredging adjacent to deepening channels authorized 
by 1960 Act. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $325,000 for new work. 
Terminal facilities. Fourteen piers and wharves, three at 
west end of harbor and remainder along dock channel. One 
is a base for State-owned fish research and patrol boats. One 
publicly owned and six privately owned used for mooring 
fishing boats and recreational craft and for ferry service. Five 
terminals have railroad connections and five mechanicalhandling 
facilities. Facilities are considered adequate for 
existing commerce. (See Port Series No. 42, revised 1972, 
Corps of Engineers.) 
Operations and results during fiscal year. Maintenance: 
Miscellaneous inspection services and project condition 
sediment surveys by Government plant and hired labor cost 
$122,941. Environmental activities cost $15,212. Removal of 
approximately 240,000 cubic yards shoaled material, by 
contract, cost $749,466. Repairs to rock dike by U.S. 
derrickboat McCauley cost $17,131. Engineering and design 
effort cost $36,747. Supervision and administration cost 
$16,572. 
24. TOLEDO HARBOR, OH 
Location. Comprises lower 7 miles of Maumee River and 
channel through Maumee Bay to Lake Erie. Maumee River 
has its source in northern Indiana and empties into Lake 
Erie. Harbor is at the westerly end of Lake Erie, 99 miles 
westerly from Cleveland, Ohio. (See NOAA Nautical Chart 
14847.) 
Previous projects. For details see page 1959 of Annual 
Report for 1915, and page 1565 of Annual Report for 1938. 
Existing project. For description of existing project see 
pages 32-18 and -19 of Annual Report for 1978. Cost of 
completed existing project was $15,567,147. See table 20-B 
20-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Maumee River through city of Toledo has 
been developed extensively for deep-draft navigation. Detailed 
information on actual port and harbor facilities are in Port Series 
No. 44 (revised 1972) prepared and published as Part 2, by board 
of Engineers for River and Harbors. Information on port 
administration and Federal services, port and terminal services 
and charges, and steamship services is prepared and published as 
Part 1 by Port Development Staff, U.S. Department of 
Commerce. Facilities are considered adequate for existing 
commerce. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys, real estate activities, and 
various operations studies, including Long-Term Dredged 
Disposal Management Plan, cost $560,324. Removal of 
approximately 1,700,000 total cubic yards of shoaled material, by 
contract, cost $2,332,032. Repairs to existing CDF by hired labor 
cost $106,904. Construction contract to enlargen CDF was 
awarded in September 1992. Contract costs were $200,000. 
Engineering and design cost were $317,455. Supervision and 
administration cost $75,082. 
25. VERMILION HARBOR, OH 
Location. On south shore of Lake Erie at mouth of Vermilion 
River, 37 miles westerly from Cleveland, Ohio. (See NOAA 
Nautical Chart 14826.) 
Existing project. For description of existing project see pages 
32-17 and 32-18 of Annual Report for 1975. Actual Federal cost 
for the completed existing project was $1,156,118. Estimated non- 
Federal cost for new work is $754,679 including cash contribution 
of $740,679 and remainder for relocation of submarine cable and 
construction of public wharf. See Table 20-B for authorizing 
legislation. 
Local cooperation. Fully complied with. Local interests 
contributed $740,679. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Operations and results during fiscal year. Maintenance: 
Miscellaneous studies, project condition sediment surveys and 
real estate activities by Government plant and hired labor cost 
$17,281. Environmental testing, by contract, cost $44,214. 
Finalization of FY91 dredging contract cost $8,880. Engineering 
and design effort cost $1,831. Supervision and administration cost 
$17,635. 
26. WEST HARBOR, OH 
Location. On southwest shore of Lake Erie, 13 miles northwest 
of Port Clinton, Ohio. (See NOAA Nautical Chart 14847.) 
Existing project. For description of existing project, see page 
32-10 of Annual Report for 1983. Total Federal cost for new 
work was $3,303,898. Total non-Federal cost for new work was 
$3,922,000 including cash contribution of $3,795,000. Existing 
project was authorized by 1965 River and Harbor Act (H. Doc. 
245, 88th Cong., 2d sess.) 
Local cooperation. See pages 32-20 of 1978 Annual Report 
for requirements of local cooperation. By letter dated 
January 31, 1978, State of Ohio stated its intent to furnish 
assurances of local cooperation, and executed LCA was 
received on March 9, 1981. 
Terminal facilities. Commerce at the harbor presently 
consists of recreational boating and affiliated activities. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys, real estate activities, and 
economic study cost $91,709. Finalization of FY91 
environmental testing contract cost $4,066. Engineering and 
design effort cost $4,670. 
27. WILSON HARBOR, NY 
Location. At mouth of east branch of Twelve Mile Creek, 
which enters Lake Ontario 12 miles easterly of mouth of 
Niagara River, and 67 miles westerly of Rochester Harbor, 
NY (See NOAA Nautical Chart 14806.) 
Previous project. For details see page 2395 of Annual 
Report for 1889, and page 628 of Annual Report for 1905. 
Existing project. For description see page 32-18 of Annual 
Report for 1975. Actual Federal cost for completed existing 
project was $477,904. Estimated non-Federal costs are 
$774,000 which includes cost of $16,000 for previously 
completed work. Remainder of non-Federal costs are for 
work required for 1968 R&H Act including cash contribution 
of $166,988. See Table 20-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities consist of private docks for 
recreational craft and privately owned servicing and storage 
handling facilities for recreational and other small craft. 
Facilities are considered adequate for existing commerce. 
Operations and results during fiscal year. Maintenance: 
Project condition sediment surveys and real estate activities 
cost $4,445. Environmental testing, by contract, cost $26,093. 
Finalization of FY91 dredging contract cost $1,389. 
28. RECONNAISSANCE AND 
CONDITION SURVEYS 
Condition surveys were performed by the Buffalo District 
at a cost of $38,918. Real estate activities, to include 
utilization inspection, cost $1,560. Supervision and 
administration, to include program management and project 
map updates, cost $5,740. Environmental activities cost 
$27,762. 
Project 
Barcelona, NY 
Niagara River, NY 
Ogdensburg, NY 
Pt. Clinton, OH 
Put-in-Bay, OH 
Date of Survey 
Jul 1992 
Nov 1991 
Aug 1992 
Sep 1992 
May 1992 
20-10

BUFFALO, N Y DISTRICT 
29. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 20-C. 
30. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
See Table 20-G. 
STURGEON POINT, EVANS, NY 
Location. On south shore of Lake Erie, 17 miles southwest of 
Buffalo, NY and 22 miles northeast of Dunkirk, NY (See 
Geological Survey map of Angola, NY.) 
Existing project. For description of existing project, see page 
20-11 of Annual Report for FY1991. Federal project cost is 
$1,460,000. Non-Federal project cost is $1,475,000. In addition, 
the local sponsor provided associated costs for upland 
development of $1,000,000. 
Local cooperation. The Buffalo District has a properly executed 
Local Cooperation Agreement with the Town of Evans, NY, 
signed October 26, 1987. 
Operations and results during fiscal year. Maintenance: Cost 
of study on sand by-passing procedures was $4,775. Reimbursement 
to Town of Evans, NY, for Federal share of maintenance 
dredging cost $7,815. 
TOUSSAINT RIVER, CARROLL TWSP, OH 
Location. At westerly end of Lake Erie, 8 miles west of Port 
Clinton and 22 east of Toledo, Ohio (See NOAA Nautical Chart 
14847.) 
Existing project. For description of existing project, see page 
20-12 of Annual Report for 1991. See Table 20-B for authorizing 
legislation. 
Local cooperation. The Buffalo District has a properly executed 
Local Cooperation Agreement with Carroll Twsp., OH, signed 
April 3, 1991. 
Operations and results during fiscal year. New Work: Project 
is 100% complete. FY92 Federal costs were $45,742 for 
construction contract, including supervision and administration, 
and $26,057 for in-house engineering effort. Non-Federal costs 
were $10,158 for construction contract, including supervision and 
administration. 
Navigation work pursuant to Section 1135, Public law 99-662. 
Sandusky Bay, OH - Cost of $146 were incurred to finalize 
preauthorization studies. 
Beach Erosion Control 
31. MAUMEE BAY STATE PARK, OH 
Location. Maumee Bay State Park is located in Lucas County, 
OH approximately 5 miles east of Toledo. The 1,855 acre park 
has 11,000 feet of shoreline along the southerly end of Maumee 
Bay (Lake Erie). (See U.S. Geological Survey Map, Oregon, 
OH.) 
Existing project. For description of existing project, see 
page 20-12 of Annual Report for FY 1991. The remaining 
project cost of $21,044,000 (Oct. 1991) includes $8,317,000 
Federal and $12,727,000 non-Federal of which $4,440,000 is 
non-Federal cost for lands, utilities, and recreation facilities. 
Local cooperation. For details of local cooperation see 
page 32-14 of FY 87 Annual Report. A Local Cooperation 
Agreement was negotiated with the local sponsor (ONDR) 
and executed August 8, 1990 by the Assistant Secretary of 
the Army. 
Operations and results during fiscal year. New Work: The 
plan described in the General Design memorandum was 
completed September 1991. FY 92 costs were $26,388 
Federal and $22,608 non-Federal for completion of "as-built" 
drawings, operation and maintenance manual, and initiation 
of project monitoring which will be cost-shared 50% Federal 
cost and 50% non-Federal cost. 
32. PRESQUE ISLE PENINSULA, ERIE, PA 
Location. At Erie, Pa., on south shore of Lake Erie, 78 
miles southwest of Buffalo, NY and 102 miles east-northeast 
of Cleveland, Ohio. (See NOAA Nautical Charts 14824 and 
14835.) 
Existing project. For description of completed portion of 
existing project see page 1393 of Annual Report for 1963. 
For details of project authorized by the 1974 Water 
Resources Development Act (WRDA), 1976 WRDA and 
1986 WRDA, see page 32-14 of Annual Report for FY 87. 
Actual Federal cost for the authorized beach nourishment 
project modifications through FY 92 is $16,879,000 which 
includes $5,646,000 for completed work authorized by the 
1954 and 1960 R&H Acts and 1974 WRD Act and 
$11,233,000 for completed work authorized by the 1976 
WRD Act. Actual non-Federal cost for the authorized 
project and modifications through FY 92 is $8,798,000 which 
includes $3,983,000 for completed work authorized by 1954 
and 1960 R&H Acts and 1974 WRD Act and $4,815,000 for 
completed work authorized by the 1976 WRD Act. Beach 
nourishment as authorized by the 1976 WRDA was 
completed in FY91. The estimated Federal cost (Oct. 1992) 
for the 55 breakwater project is $61,200,000. This estimate 
includes $13,750,000 for the initial construction and 
$47,450,000 for 50 years of post-construction beach 
nourishment. The estimated non-Federal cost (Oct 1992) for 
the breakwater project is also $61,200,000. See Table 32-B 
for authorizing legislation. 
Local cooperation. Fully complied with for completed 
project as authorized by 1954 and 1960 R&H Acts and 1974 
WRD Act. An agreement between the United States of 
America and the Commonwealth of Pennsylvania, acting 
through the Department of Environmental Resources was 
entered into on February 21, 1979 for the annual 
nourishment which was extended by the 1976 WRD Act. A 
20-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Local Cooperation Agreement between the United Stated of 
America and the local sponsor for construction of the 58 
breakwater project was executed by the Secretary of the Army on 
June 22, 1989. See page 20-10 of Annual Report for FY89 for 
details of local cooperation. 
Operations and results during fiscal year. New Work: Beach 
nourishment as authorized by the 1976 WRD Act was completed 
in FY 91. Final balancing of Federal and non-Federal funds 
resulted in a credit of $13 in Federal funds and a cost of $13 in 
non-Federal funds. Construction of the breakwater project was 
continued. The sand replenishment was completed with 
placement of 328,000 tons, yielding a total of 560,000 tons of 
sand placed. During the year, 28 breakwaters were constructed 
for a total of 47 breakwaters completed. FY92 costs were a total 
of $9,584,001 ($4,794,619 Federal and $4,789,382 non-Federal) 
was expended for construction of the breakwater project. Of this 
total, contract costs were $4,664,429 Federal and $4,664,442 non- 
Federal, including monitoring contract and construction 
management. Aerial photogrametric contract cost $4,893 in 
Federal funds and $4,893 in non-Federal funds. In-house 
engineering effort cost $116,779 Federal and $116,730 non- 
Federal. A total of $8,518 Federal and $3,318 Non-Federal was 
expended for real estate activities. The Commonwealth of 
Pennsylvania contributed $3,104,075 in FY 92 toward this project. 
33. OTHER AUTHORIZED BEACH EROSION 
ONTROL PROJECTS 
See Table 20-D. 
34. BEACH EROSION WORK UNDER SPECIAL 
AUTHORIZATION 
CENTURY PARK, LORAIN, OH 
Location. On south shore of Lake Erie, 25 miles westerly from 
Cleveland, Ohio. (See NOAA Nautical Chart 14841.) 
Existing project. For decription of existing project see page 20- 
13 of Annual Report for 1991. 
Local cooperation. The Local Cooperation Agreement was 
executed with the local sponsor, the city of Lorain, OH, in July 
1989. 
Operations and results during fiscal year. New Work: FY 92 
Federal costs were $2,378 for in-house engineering effort. Non- 
Federal costs resulted in a credit of $848, which was the result of 
balancing Federal and Non-Federal shares. 
LAKESHORE PARK, ASHTABULA, OH 
Location. Lakeshore Park is located in Ashtabula, Ashtabula 
County, Ohio about 40 miles southwest of Erie, Pennsylvania, 
and about 50 miles northeast of Cleveland, Ohio. (See U.S. 
Geological Survey Map, Ashtabula north, OH.) 
Existing project. For description of existing project, see page 
32-12 of Annual Report for 1983. Construction was completed in 
July 1983. 
Local cooperation. For details of local cooperation 
requirements, see page 32-12 of Annual Report for 1983. 
Operation and results during fiscal year. New Work: FY 
92 Federal cost was $2,105 for supervision and 
administration of beach nourishment contract. 
SIMS PARK, EUCLID, OH 
Location. On south shore of Lake Erie in the city of 
Euclid, Cuyahoga County, OH, 10 miles east of downtown 
Cleveland. (See U.S. Geological Survey Map for East 
Cleveland, OH). 
Existing project. The project was authorized for 
construction by the Chief of Engineers pursuant to Section 
103 of the 1962 River and Harbors Act, as amended, on 
January 10, 1991. The project consists of an approximate 
800-foot long by 180-foot wide artificial headlands beach. 
The project provides approximately 108,000 square feet of 
improved beach surface area; fronted by three segmented 
rubblemound breakwaters, typically 125 feet in length with 
160 feet spacing between breakwaters, and a crest height at 
10 feet above LWD; and, east and west terminal groins. The 
crest of the west groin is at 10 feet above LWD and the 
crest height at the east groin is at 11 feet above LWD to 
minimize sand overtopping. The beach sand berm crest is 
at 8.5 feet above LWD. Estimated Federal cost is $1,494,000; 
non-Federal cost is the same. 
Local cooperation. The Local Cooperation Agreement was 
executed with the local sponsor, the city of Euclid, on 
February 6, 1991. 
Operations and results during fiscal year. New Work: 
FY92 Federal costs were $1,735 for real estate activities, a 
credit of $15,181 in-house engineering effort which resulted 
from balancing of Federal and non-Federal costs, and 
$526,983 for construction contract including supervision and 
administration. Non-Federal costs for FY92 were $1,076 for 
real estate activities, $526,983 for construction contract 
including supervision and administration, and $39,427 for inhouse 
engineering. 
Flood Control 
35. ELLICOTT CREEK, NY 
Location. The channel improvement is located on the 
downstream portion of Ellicott Creek in the towns of 
Amherst and Tonawanda, Erie County. (See Geological 
Survey maps of Tonawanda East and Buffalo Northeast, 
NY.) 
Existing project. For detailed description of the original 
project authorized by Section 201 of the 1970 Flood Control 
Act, see page 32-24 of Annual report for 1973 and page 20- 
14 Annual Report for 1992. 
Local cooperation. For details of local cooperation see 
page 32-22 of Annual Report for 1976 and page 20-14 of 
Annual Report for 1991. 
20-12

BUFFALO, N Y DISTRICT 
Operations and results during fiscal year. New Work: Federal 
costs for FY 92 were $50 for real estate activities and $717 for 
"as-built" drawings reproduction. 
36. MT. MORRIS LAKE, GENESEE RIVER, NY 
Location. Dam is on Genesee River 66.9 miles above river 
mouth and about 32 miles southwesterly of Rochester, NY. 
Reservoir is in Livingston and Wyoming Counties, NY (See 
Geological Survey maps of Nunda and Portage, NY). 
Existing project. For description of existing project, as 
authorized by 1944 Flood control Act, see page 1575 of Annual 
Report for 1962. New work for completed project cost 
$23,365,559. In addition, $5,000 contributed funds were expended 
for new work. 
Local cooperation. None required. Local interests contributed 
$5,000 for new work. 
Operations and results during fiscal year. Maintenance: 
Operation and ordinary maintenance of dam, reservoir and 
service facilities, condition and operation studies, real estate 
activities and miscellaneous reports, were accomplished by hired 
labor at a cost of $514,497. Co-Operative Stream Gaging 
Program accomplished by U.S. Geological Survey and national 
Weather Service reporting and hydroclimatic network cost 
$100,762. Operation of the Water Control Center cost $301,444. 
Initiation of conversion of existing building to Visitor Center cost 
2,818. Finalization of debris removal contract cost $4,009. 
Elevator maintenance cost 1,609. Engineering and design effort 
cost $102,238. Supervision and administration cost $21,153. 
37. RENO BEACH-HOWARD 
FARMS AREA, OH 
Location. Area is located in Lucas County, on the south shore 
of Lake Erie about 15 miles east of Toledo, Ohio. (See U.S. 
Geological Survey map for Reno Beach and Metzger Marsh, 
OH.) 
Existing project. For description of existing project, see page 
20-14 of Annual Report for 1991. 
Local cooperation. A Local Cooperation Agreement (LCA) 
was executed with the local Sponsor on July 22, 1988 and by the 
Assistant Secretary of the Army for Civil Works on September 
30, 1988. Availability of lands, easements, and rights-of-way was 
received on June 5, 1990 from the local sponsors. Discussions 
continue with the local sponsors on credit for LERRD's based on 
independent appraisals and the amount of cash contribution. 
Operations and results during fiscal year. New Work: 
Construction is 100% complete. FY92 costs were $12,150 for real 
estate, $1,748,234 for the construction contract including 
supervision and administration and $9,496 for in-house 
engineering effort. Non-Federal costs were $105,272 for 
construction contract, including supervision and administration. 
38. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspection of completed flood control works for compliance 
with Federal requirements were made during the period at 
a cost of $123,320. This includes updating the hydraulics and 
hydrology of various local flood control projects. Total cost 
to September 30, 1992 was $1,924,765. 
39. NATIONAL EMERGENCY 
PREPAREDNESS 
FY92 costs were $120,191. 
40. OTHER AUTHORIZED 
FLOOD CONTROL PROJECTS 
See Table 20-E. 
41. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
CONESUS LAKE, LIVONIA, NY 
Location. Conesus lake is situated in western New York 
State about 25 miles south of the city of Rochester. (See 
U.S. Geological Survey map, Livonia, NY.) 
Existing project. For description of existing project, see 
Annual Report of 1991. See Table 20-B for Authorizing 
Legislation. 
Local cooperation. On September 25, 1985, the New York 
State Department of Environmental Conservation signed the 
Local Cooperation Agreement. For details see page 32-16 of 
Annual Report for FY86. 
Operations and results during fiscal year. New Work: 
Balancing of Federal and non-Federal shares of cost resulted 
in a credit of $5 in Federal funds. 
EUCLID CREEK, CLEVELAND, OH 
Location. Euclid Creek has a drainage area of 
approximately 25 square miles and is located east of 
Cleveland in Cuyahoga County and a small portion in Lake 
County, Ohio. (See U.S. Geological Survey Map, East 
Cleveland, OH.) 
Existing project. For details of existing project, see page 
32-14 of the Annual Report for 1983. Initial construction of 
project was completed in 1986. Repairs to failed bank were 
completed in May 1988. 
Local cooperation. For details of local cooperation 
requirements, see page 32-13 of Annual Report for 1984. 
Operations and results during fiscal year. New Work: FY 
92 costs were $94 for project administration. 
KEUKA LAKE, PENN YAN, NY 
Location. Keuka Lake is located in the southwestern part 
of New York State in the Oswego River Basin between 
Canandaigua Lake and Seneca Lake in the village of Penn 
Yan in Yates County. (See U.S. Geological Survey Map, 
Penn Yan, NY.) 
20-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Existing Project. Project was authorized for construction by the 
Chief of Engineers pursuant to Section 205 of the Flood Control 
Act of 1948, as amended, on January 25, 1991. The 
recommended plan of improvement consists of removal of an 
existing earthen and masonry dam located just upstream of the 
Main Street Bridge. In order to provide additional capacity and 
to aid in regulating lake levels, additional slide gates will be 
constructed in its place. The project will consist of a sheetpile 
structure with three slide gates, each 6 feet high and 6 feet wide. 
The new control structure will tie into the existing races located 
on each side of the stream. The operational policy will be to 
make releases through the dam to 1,000 CFS or the control 
structure's capacity, whichever is less. This policy will not induce 
additional adverse downstream flood impacts. Total Federal cost 
of the project is $369,800. Total non-Federal cost is $123,200. 
Local cooperation. The Local Cooperation Agreement was 
executed with the local sponsor, New York State Department of 
Environmental Conservation, on October 11, 1991. 
Operations and results during fiscal year. New Work: 
Balancing of Federal and non-Federal shares of cost for 
preparing plans and specifications resulted in a credit of $15,288 
Federal funds and a cost of $17,493 non-Federal funds. 
SWAN CREEK, TOLEDO, OH 
Location. Swan Creek is located in the city of Toledo, Lucas 
County, OH. (See NOAA Nautical Chart 14847). 
Existing Project. The project was authorized for construction 
by the Chief of Engineers pursuant to Section 205 of the FLood 
Control Act of 1948, as amended, on May 15, 1991. The project 
is a combination of levees and steel sheetpile floodwalls along 
3,100 linear feet of the left bank of Swan Creek, a small ponding 
area with three outfalls which provides for interior drainage, and 
relocation of about 500 linear feet of channel bottom. Total 
estimated cost is $1,486,000 Federal and $392,500 non-Federal. 
Local cooperation. The Local Cooperation Agreement was 
executed with the local sponsor, the city of Toledo, OH, on May 
1, 1989. 
Operations and results during fiscal year. New Work: FY 92 
costs were $150 for real estate activities and $41,644 for in-house 
engineering efforts. 
Flood Control and Coastal Emergencies (Public Law 89, 84th 
Congress, as amended by Sec. 206 of Flood Control Act of 1962). 
FY 92 costs for the Disaster Preparedness Program were 
$283,108. Costs to support Emergency Operations totaled $6,409, 
which included reconnaissance efforts, liaison activities and 
providing technical advice to local response agencies in flood 
flight operations. FY 92 costs for the Emergency Rehabilitation 
Program totaled $178,268. This includes $174,949 to complete the 
emergency rehabiitation of concrete slope protection along 
Euclid Creek in the city of Cleveland, Cuyahoga County, Ohio. 
Non-Federal cost for that construction in FY 92 was $41,958. FY 
92 Federal in-house engineering effort cost $212. Real estate 
activities cost $100 and contract costs, including supervision and 
administration were $174,638. Non-Federal cost was $41,958 
for construction contract and supervision and administration. 
This project provides for the repair of 550 feet of damaged 
concrete slope protection located adjacent to the Section 205 
Euclid Creek Flood Control Project completed in 1984. The 
emergency rehabilitation of flood control levees and 
streambank protection along Canaseraga Creek, in the town 
of West Sparta, Livingston County, NY will be terminated 
due to lack of non-Federal commitment. 
42. DEAUTHORIZED PROJECTS 
See Table 20-I. 
General Investigations 
43. SURVEYS 
During FY 92 costs of $345,987 were incurred as shown 
below: 
Navigation Studies 
Flood Damage 
Prevention Studies 
Shoreline Protection 
Studies 
Special Studies 
Miscellaneous 
Investigations 
Coordination Studies 
Phase I, GDM Studies 
Comprehensive Studies 
Review of Authorized 
Projects 
$ 76,919 
30,573
0 
143,804 
91,105 
3,587
00 
0 
44. COLLECTION AND STUDY 
OF BASIC DATA 
During the period, costs of $175,034 were incurred in 
connection with International Water Studies under the 
General Investigations appropriation and $551,945 incurred 
under the Operations and Maintenance appropriation for a 
total cost of $726,979. Flood plain managment services were 
performed during the year at a cost of $190,542. During the 
year, flood hazard elevation studies were essentially 
completed for the towns of Greece and Hanover, NY, 
Cuyahoga Falls, OH, and the counties of Lucas and Geauga, 
OH. The results of these studies will enable local officials to 
encourage and enforce prudent use of the identified flood 
plains. Also hundreds of technical assistance requests 
regarding flood plain matters were completed during the 
year responding to individuals, corporations, real estate 
companies, insurance agents, engineering firms and local 
agencies. Costs for General Hydrologic Studies were $6,921. 
20-14

BUFFALO, N Y DISTRICT 
45. ADVANCE ENGINEERING 
AND DESIGN 
Costs during the period were $193,039 for Preconstruction 
Engineering and Design Advance Engineering and Design 
projects. For details of individual projects, see sections 15, 17, 
and 19 in text. 
7 
20-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
1. Ashtabula Harbor, OH 
2. Black Rock 
Channel and 
Tonawanda 
Harbor, NY 
(Federal Funds) 
(Contrib.Funds) 
3. Buffalo 
Harbor, NY 
4. Buffalo Small Boat 
Harbor, NY 
(Federal Funds) 
(Contrib.Funds) 
5. Cattaraugus 
Harbor, NY 
(Federal Funds) 
(Contrib.Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New, Work 
Contrib. 
Cost 
898,500 
900,683 
574,896 
734,621 
150 
793,383 
728,505 
247,000 
256,262 
- 12,805,339 1 
- 12,805,339 1 
542,500 13,695,329 
599,355 13,679,225 
- 6,077,000 
- 6,077,000 
- 11,135,1202 
- 11,135,1202 
1,073,524 1,638,600 
1,070,271 1,538,005 
3,567,500 44,573,4853 
3,664,062 44,542,4863 
- 620,000 
- 620,000 
- 23,115,1874 
- 23,115,1874 
768,000 1,555,250 
771,923 1,467,633 
502,000 
619,756 
2,089,000 59,527,765 s 
1,900,758 59,299,754 s 
- 295,457 
- 295,457 
125,000 350,000 
124,284 198,457 
- 500,000 
- 178,386 
33,864 
41,882 
6,754 
20,256 
23,090 
31,121 
245,000 
226,674 
212,500 
455,704 
9,707 
10,424 
720,000 
549,415 
712,500 
634,090 
4,804,060 
4,804,060 
183,720 
181,760 
2,566,529 
2,566,529 
20-16

BUFFALO, N Y DISTRICT 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
6. Cleveland Harbor, OH 
(Federal Funds) 
(Contributed Funds) 
7. Conneaut Harbor, OH 
8. Dunkirk 
Harbor, NY 
(Federal Funds) 
(Contrib.Funds) 
9. Erie Harbor, PA 
10. Fairport Harbor, NY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
127,579 
2,986,000 
3,440,654 
335,000 3,316,000 
321,423 3,208,526 
4,079,074 4,272,000 
4,433,578 3,961,820 
250,000 36,047,2996 
42,214 35,698,8266 
5,678,500 165,678,059' 
5,732,808 165,368,370' 
- 16,404,903 
- 16,404,903 
- 1,351,000 
- 325,676 
1,351,000 
325,676 
- 8,346,6418 
- 8,346,641' 
126,000 
137,871 
70,881 
71,935 
336,000 
323,633 
375,000 10,487,4839 
386,734 10,486,8299 
- 651,850 
- 651,850 
- 3,010,02410 
- 3,010,02410 
119,460 
166,661 
296,238 244,500 
249,795 283,052 
125,793 
132,617 
2,771,865 
2,770,529 
- 1,950,000" 
- 1,950,00011 
- 3,597,87312 
- 3,597,87312 
400,512 
404,352 
288,129 
288,593 
82,000 
77,754 
99,000 
94,679 
17,063,40313 
17,054,83113 
1,154 
1,154 
843,000 
895,406 
130,047 1,032,000 
137,961 999,660 
948,917 
805,990 
2,959,61114 
2,959,611's 
16,827,636 
16,650,944 
20-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
11. Great Sodus Bay 
Harbor, NY 
12. Huron Harbor, OH 
(Federal Funds) 
(Contrib. Funds) 
13. Irondequoit Bay, NY 
(Contrib. Funds) 
14. Little Sodus Bay 
Harbor, NY 
15. Lorain Harbor, OH 
(Federal Funds) 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,629 
2,629 
8,898 
8,891 
80,973 
80,543 
40,212 
40,610 
610,95915 
610,95915 
2,600,673 
2,600,641 
713,544 
713,54 
-22,000 
30,624 
815,423 
802,901 
84,000 
92,099 
1,070,000 
1,059,587 
96 
18,204 
24,760 
59,346 
62,683 
2,491 
2,491 
12,406 
9,642 
27,000 
26,209 
39,356 200,842 
34,086 204,220 
35,271 
37,111 
11,500 
11,860 
5,103,79516 
5,103,79516 
18,181,349 
18,165,429 
247,030 
247,030 
63,079 
63,079 
3,535,800 
3,535,713 
465,381 
463,666 
2,720,186 
2,720,039 
301,39417 
301,39417 
3,350,497 
3,348,965 
742,822 
742,822 
208,000 
281,336 
545,000 
539,352 
23,000 
42,957 254 
1,195,964 909,000 
624,133 1,433,251 
- 22,240,07318 
92 22,239,77018 
1,481,500 
1,487,178 
29,089,893 
29,038,300 
20-18

BUFFALO, N Y DISTRICT 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
(Contrib. Funds) 
16. Oak Orchard 
Harbor, NY 
17. Olcott Harbor, NY 
18. Oswego Harbor, NY 
19. Ottawa River 
Harbor, MI & OH 
20. Port Ontario 
Harbor, NY 
(Federal Funds) 
(Contrib. Funds) 
21. Rochester Harbor, 
NY 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp,. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
845,551 
845,551 
10,440 
10,440 
400,000 
494,360 
16,374 
16,374 
24,240 
24,240 
12,208 
12,208 
376,000 
430,663 
16,465 
16,465 
343,269 
331,713 
164,267 
142,431 
334,000 
354,780 
23,686 
23,577 
590,447 
562,665 
16,316 
37,159 
425,000 
101,882 
7,755 
7,861 
17,196 
56,086 
1,586,99619 
1,586,99619 
441,332 
440,339 
2,025,2100 
1,700,0280 
625,9582 
625,9551 
14,477 
14,477 
8,430,0163 
8,430,016m 
7,588,237 
7,587,789 
307,590 
- 307,590 
16,150 
4,893 
4,893 
556 
38,000 
77,136 
393 
3,526 
3,526 
84,000 
83,892 
800 
9,481 
9,481 
159,000 
91,065 
-9,379 
4,656 
5,607 
5,607 
342,000 
273,957 
2,390,621" 
2,380,247= 
23,866 
23,866 
- 1,350,000 
- 1,335,591 
- 2,439,308" 
- 2,439,308" 
1,019,209 
1,018,151 
941,000 
923,684 
663,500 21,216,525" 
678,609 21,213,243" 
20-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
22. Rocky River Harbor, 
OH 
23. Sandusky Harbor, 
OH 
(Federal Funds) 
(Contrib. Funds) 
24. Toledo Harbor, OH 
25. Vermilion Harbor, 
OH 
26. West Harbor, OH 
(Federal Funds) 
(Contrib. Funds) 
27. Wilson Harbor, NY 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
- 343,494 
- 343,494 
18,301 
18,301 
446,000 
437,085 
-4,554 
2,894,800 
2,779,048 
31,941 
31,941 
210,275 
487,428 
30,303 
28,171 
275,038 
275,400 
41,942 
43,690
- 6,727,270 
- 6,727,270 
1,317,845 1,015,000 
1,056,371 1,280,209 
973,200 18,241,484 
958,069 18,198,179 
-4,555 
3,794,923 3,495,000 
3,309,950 4,116,988 
9,238 323,484 
9,238 309,863 
46,832 
46,785 
70,771 
66,826 
4,581,000 
3,591,797 
78,052 
89,841 
98,417 
100,445
- 535,24632 
- 535,24632 
20-20 
2,599,890 
2,598,868 
675,606 
675,606 
15,445 
15,445 
17,191,8422 
17,191,8429 
95,272,27630 
94,281,27830 
1,156,11831 
1,156,11831 
2,437,614 
2,435,782 
139,775 
139,775 
3,303,898 
3,303,898 
1,244,314 
1,242,350 
3,795,000 
3,795,000

BUFFALO, N Y DISTRICT 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
30. Lake Erie 
Sturgeon Pt., NY 
(Federal Funds) 
(Contrib. Funds) 
30. Toussaint River 
Carroll Twsp., OH 
(Federal Funds) 
(Contrib. Funds) 
31. Maumee Bay State 
Park, OH 
(Federal Funds) 
(Contrib. Funds) 
32. Presque Isle 
Peninsula, Erie, PA 
(Federal Funds) 
(Contrib. Funds) 
34. Century Park, 
Lorain, OH 
(Federal Funds) 
(Contrib. Funds) 
34. Lakeshore Park, 
Ashtabula, OH 
(Federal Funds) 
(Contrib. Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
22,591 
22,591 
-15,000 
-143,915 
-108,000 
948,684 
9,747 
9,747 
-100,000 
26,603 
3,000 
1,901 
1,647 
134,278 
118,769 
19,048 
31,928 
425 
5,000 
5,412 
334,500 
217,578 
171,800 
94,041 
15,000 
136,816 
100,000 2,269,000 
110,260 2,255,609 
183,621 
169,527 
New Work 
Approp. 3,608,000 
Cost 1,264,281 
Maint. 
Approp. - 
Cost- 
New Work 
Contrib. 2,956,429 
Cost 593,922 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
174,000 
16,618 
202,250 
12,351 
2,870 
3,846,000 2,522,000 
3,162,578 4,914,497 
2,920,000 3,305,571 
2,923,894 4,824,766 
174,000 
16,618 
202,250 
12,351 
2,870 
120,000 
274,921 
189,831 
30,000 
25,893 
13,500 
12,590 
-40,000 
71,799 
10,158 
39,379 
26,388 
-34,000 
22,608 
4,177,047 29,283,609 
4,794,605 29,245,092 
3,952,000 19,890,284 
4,789,383 19,859,776 
2,378 
-848 
2,105 
20-21 
717,078" 
714,449" 
1,686,9003 
1,662,822" 
21,500 
19,903 
1,356,858 
1,354,726 
294,500 
289,377 
171,800 
104,199 
2,786,379 
2,758,850 
149,621 
192,135 
4,978 
4,978 
418,500 
418,255 
202,250 
202,182 
951,844 
947,343 
249,707 
249,707

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY89 FY90 FY91 FY92 Sept 30, 1992 
34. Sims Park, Euclid, 
OH 
(Federal Funds) 
(Contrib. Funds) 
35. Ellicott Creek, NY 
(Federal Funds) 
(Contrib. Funds) 
36. Mt. Morris Lake, NY 
Genesee River 
37. Reno Beach-Howard 
Farms Area, OH 
(Federal Funds) 
(Contrib. Funds) 
41. Conesus Lake, 
Livonia, NY 
(Federal Funds) 
(Contrib. Funds) 
41. Euclid Creek, OH 
41. Keuka Lake, NY 
(Federal Funds) 
41. Swan Creek, Toledo, 
OH 
(Federal Funds) 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
15,000 
3,915 
70,000 
57,584 
547,000 
29,421 
- 678,700 
- 22,001 
1,081,000 
987,246 
253,000 
238,554 
1,233,500 
1,092,381 
335,000 
163,353 
71,785 
166 
22,167 
513,537 
567,486 
767 
759,500 
731,957 
678,700 
589,486 
11,193,767 
11,191,758 
- 653,000 
- 638,620 
- 23,365,559" 
- 23,365,5593s 
1,392,838 1,209,000 
1,519,711 1,205,414 
237,093 2,260,000 
129,669 2,531,449 
250,000 
62,500 
38,400 
47,510 
1,000 
12,462 
35,000 
31,260 
8,000 
11,783 
37,253 
125,000 
292,079 
65,000 
64,996 
1,177,283 17,714,930 
1,048,530 17,530,086 
1,864,000 
1,769,880 
57,500 
105,272 
5,531,560 
5,427,228 
432,500 
397,351 
- 2,134,400 
-5 2,134,365 
36
- 3,456,000 
94 3,456,000 
35,000 
38,571 
78,000 
46,939 
90 
102,000 
130,215 
-15,288 
38,000 
41,794 
187,036 
171,632 
561,500 
561,500 
1. Includes $565,192 for 
contributed funds. 
previous projects. Excludes $47,000 
2. Includes $58,027 for previous projects. 
3. Includes $4,922 emergency relief authority adminstrative costs 
tranferred for new work to maintenance upon 
conversion to programming and budgeting system 
July 1, 1953, by direction of Office, Chief of 
Engineers. Also includes appropriations and costs 
20-22 
35,000 
35,000

BUFFALO, N Y DISTRICT 
under appropriation titles 96x3123 Operations and Maintenance 
and 96x5125 Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters. 
4. Includes $4,277,586 for previous projects. Excludes 
expenditures of $239,305 for work authorized by Section 107. 
5. Includes $1,883,647 for previous projects. Excludes $446,805 
contributed funds. 
6. Includes $1,564,154 for previous project and appropriations 
and costs of $16,596 for modification authorized for construction 
under authority of Sec. 107, 1960 R&H Act. 
7. Includes appropriations and costs under appropriation titles 
96x3123 Operations and Maintenance and 96x5125 Maintenance 
and Operations of Dams and Other Improvements of Navigable 
Waters. Excludes $201,960 contributed funds. 
8. Includes $805,272 for previous projects. 
9. Includes $39,784 for previous projects. 
10. Includes $811,250 for previous projects. Exludes $11,000 
contributed funds. 
11. Includes $176,520 for previous projects. 
12. Includes $736,967 for previous projects. 
13. Includes $104,900 for previous projects. Excludes $154,500 
contributed funds. 
14. Includes $368,940 for previous projects. 
15. Includes $361,772 for previous projects. 
16. Includes $269,789 for previous projects. 
17. Includes $232,328 for previous projects. 
18. Includes $292,203 for new work for previous projects. 
Excludes $3,000 contributed funds. Also excludes appropriation 
and cost of $29,570 under authority of Section 107, 1960 R&H 
Act. 
19. Excludes $224,702 contributed funds. 
20. Includes $140,210 for previous projects. Excludes 
$1,500 contributed funds. 
21. Includes $38,959 for previous projects. Excludes 
$5,000 contributed funds. 
22. Excludes $186,000 Public Works Acceleration 
Act. 
23. Includes $1,187,977 for previous projects. 
24. Includes $945,684 for previous projects. 
25. Includes $50,000 for previous projects. 
26. Includes $247,794 for previous projects. 
27. Includes $617,529 for previous projects and $478 
emergency relief authority administration costs 
transferred from new work to maintenance upon 
conversion to programming and budgeting system, 
July 1, 1953, by direction of Office, Chief of 
Engineers. 
28. Includes $477,149 for previous projects. Excludes 
$325,000 contributed funds. 
29. Includes $1,624,695 for previous projects. 
30. Includes $16,914 for previous projects. 
31. Excludes $740,679 contributed funds. 
32. Includes $57,342 for previous projects. Excludes 
$166,998 contributed funds. 
33. Includes $16,914 for previous projects. 
34. Includes $341,900 study funds under authority 
Section 107, 1960 R&H Act. 
35. Excludes $5,000 contributed funds. 
20-23 
__

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
June 3, 1896 
Mar. 3, 1905 
June 25, 1910 
Mar. 2, 1919 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 27, 1965 
Aug 11, 1888 
June 3, 1896 
June 13, 1902 
June 13, 1902 
Aug 8, 1917 
Mar. 3, 1905 
ASHTABULA HARBOR, OH (See Section 1 of Text) 
Construction of breakwater. 
Enlarge outer harbor by extending west breakwater and 
constructing new east breakwater pierheads on lakeward 
ends of breakwaters; and remove part of old east 
breakwater. 
Extend west breakwater to shore; dredge outer harbor to a 
depth of 20 feet. 
Remove portion of east breakwater to, extend breakwaters 
to present dimensions and dredging restrictions in 
portion of west basin. 
Dredge channel through outer harbor, channel of approach to 
Penn Central Co. slip, channel Ashtabula River, to and in 
turning basin all to present project dimensions; remove 
portion of old east inner breakwater and maintenance to 
24-foot depth of portion of outer harbor. 
Extend river channel to present project limit. 
Dredging approach channel and turning basin in east outer 
harbor 25-foot depth. 
A depth of 29 feet in soft and 30 feet in hard material in 
entrance channel to just inside outer ends of breakwaters, 
thence 28 feet in soft and 29 feet in hard material in a 
channel to inner breakwater, thence 27 feet in soft and 28 
feet in hard materials in a channel extending to Penn Central 
Co. slip and extending 2000 feet up Ashtabula River, 22 feet 
in hard material in turning area; and 28 feet in soft and 29 
feet in hard material in areas adjacent to 250-foot section of 
inner breakwater when that section is removed as now 
authorized. 
Dredging approach, channel and turning basin in east outer 
harbor to 28 feet in soft material and 29 feet in hard material. 
BLACK ROCK CHANNEL AND TONAWANDA 
HARBOR, NY (See Section 2 of Text). 
Dredging channel through horseshoe reef at outlet of Lake 
Erie and Tonawanda Inner Harbor to 16 feet. 
Deepening Tonawanda Creek to 16 feet. 
Dredging channel from Buffalo outer harbor to foot of 
Maryland St., Buffalo, to 21 feet. 
Dredging channel from foot of Maryland St., Buffalo, to 
natural deepwater pool upstream from Tonawanda Harbor to 
21 feet; construction of ship lock and bridge; and repair 
of Bird Island pier towpath wall. 
Annual Report,1895,p.2132 
H. Doc. 654. 61st Cong., 
2d sess. 
H.Doc. 997, 64th Cong., 
1st sess. 
H. Doc. 43, 73rd Cong., 
1st sess.Rivers and Harbors 
Committee Doc. 78, 74th 
Cong., 2d sess. 
H. Doc. 321, 77th Cong., 
1st sess. 
H. Doc. 486, 83rd Cong., 
2d sess. 
H. Doc. 148, 86th Cong., 
1st sess. 
H. Doc. 269, 89th cong., 
1st sess. 4 
H. Ex. Doc. 83, 50th 
Cong., 1st sess. Annual 
Report, 1888, p.2066, 
and Annual Report, 1897, 
pp. 3116-3120. 
H. Doc. 143, 56th Cong., 
1st sess. and Annual 
Report, 1900 p. 4 15 2 . 
H. Doc. 125, 56th Cong., 
2d sess., and Annual 
Report 1901, p. 3 3 4 3 . 
H. Doc. 428, 58th Cong., 
2d sess. 
20-24

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
July 27, 1916 
Mar. 2, 1919 
Mar. 2, 1945 
Sept. 22, 1922 
Mar. 3, 1925 
June 26, 1934s 
Aug. 30, 19356 
Mar. 2, 1945 
Sept. 3, 1954 
May 20, 1826 
June 23, 1866 
June 23, 1874 
June 3, 1896 
Mar. 3, 1899 
Mar. 3, 1909 
June 6, 1900 
June 13, 1902 
Mar. 2, 1907 
Mar. 2, 190710 
June 25, 1910 
July 25, 1912 
Mar. 2, 1919 
Dredging channel along Tonawanda Island, with turning basin 
at its downstream end at the foot of the Island, to 21 feet. 
Dredging triangular area at junction with Buffalo north 
entrance channel. 
Widening channel at foot of Maryland St., Buffalo. 
Widening canal south of International Bridge and removal of 
westerly end of Rattlesnake Island shoal. 
Operation and care of improvements provided for with funds 
from War Department appropriations for rivers and harbors. 
Removal of rock shoals in Lake Erie entrance to canal, and in 
canal south of Ferry Street Bridge, to 22 feet; enlargement of 
North Tonawanda turning basin; extension of Bird Island Pier 
improvement of guide pier at the lock; and elimination of 
upper 150 feet of Tonawanda Creek channel from the 
project. 7 
Widening Lake Erie entrance to canal. 
Deepen lower 1,500 feet of Tonawanda inner harbor and 
enlarge turning basin. 
BUFFALO HARBOR, NY (See Section 3 of Text) 
Construction of south pier (extended in 1868)'. 
Construction of old breakwater.9 
Extension of old breakwater. 9 
Stony Point and south breakwater.9 
North breakwater. 9 
Deepening entrance channel to inner harbor and removing 
rock shoal therein. 
Dredging at entrance to canals at South Buffalo in outer 
harbor.' 
South entrance breakwater.9 
Extension of Federal project to Commercial St. and removal 
of Watson elevator site.9 
Deepening areas A, B, D, in outer harbor to 21 feet, C in 
north entrance to 23 feet. 
Deepening areas F and G in outer harbor to 21 feet. 
H. Doc. 658, 63rd Cong., 
2d sess. 
H. Doc. 1004, 65th Cong., 
2d sess. and H. Doc. 92, 
79th Cong., 1st sess. 
H. Doc. 981, 66th Cong., 
2d sess. 
H.Doc.289,68th Cong., 1st 
seas. 
H. Doc. 28, 73rd Cong., 
1st sess. 
H. Doc. 92, 79th Cong., 
1st sess. 4 
H. Doc. 423, 83rd Cong., 
2d sess. 4'8 
Annual Report, 1868, pp. 
222 and 232. 
Annual Report, 1868, pp. 
232 and 236. 
Annual Report, 1876, pt. 2, 
pp. 569 and 573. 
Annual Report, 1895, p. 
3153. 
H. Doc. 72, 55th Cong., 
1st sess., and Annual 
Report, 1897, p. 3245. 
Specified in acts. 
Specified in act. 
H. Doc. 240, 59th Cong., 
1st sess. 
H. Doc. 298, Rivers and 
Harbors Committee Doc. 2, 
61st Cong., 2nd sess. 
H. Doc. 550, 62d Cong., 
2d sess. 
H. Doc. 1139, 64th Cong. 
1st sess. 
20-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 1945"1 
July 14, 1960 
Oct. 23, 1962 
July 14, 1960 
as amended 
Nov. 17, 1988 
Aug. 13, 1968 
Mar. 3, 1875 
Removal of shoal between entrance channel to Buffalo River 
and Erie Basin to 21 feet. 
Deepening areas H, I, and K in outer harbor 21 feet. 
Extension of south entrance and south breakwaters, 
deepening outer harbor to present project dimensions, 
and removal of shoals on approach to south entrance. 
Maintenance of channels in Buffalo River and Buffalo ship 
canal to 21 feet in cooperation with city of Buffalo. 
Deepening North and Buffalo River entrance channels, 
and deepening and maintaining Buffalo River and 
Buffalo ship canal to present project dimensions. 
Deepening approach to south entrance channels, and deepen 
to 30 feet in outer area and 29 feet in inner area of 
southerly part of outer harbor. 
Deepening portion of outer harbor to 27 feet over a 
width of 500 feet for 2,500 feet northward from 
28-foot project area, widening within 1,700 feet to 
limits within 150 feet of breakwater axis and 75 feet 
from harbor line and ontinuing within these limits for 
7,000 feet. Elimination of 25-foot wide strip between 
presently authorized and proposed easterly dredging 
limits. Elimination of easterly 50-foot wide undredged 
strip in existing 23-foot depth project area, extending 
northerly from 27-foot depth to Buffalo River entrance 
channel. Previously authorized but uncompleted portions 
of work authorized by 1935 act, combined within this 
act as a single improvement. 
Removal of abandoned abutments of South Michigan 
bridge. 
BUFFALO SMALL BOAT HARBOR, N Y 
(See Section 4 of Text). 
Repair dike at small boat harbor. 
CATTARAUGUS HARBOR, N Y (See Section 5 of Text). 
Construction of arrowhead breakwaters at mouth of Creek 
entrance channel 200 feet wide at lakeward end, 100 feet 
wide and 8 feet deep from that depth in lake to point 
1,575 feet upstream; channel 100 feet wide, 6 feet deep 
an additional 3,425 feet upstream; and recreational 
fishing facilities at mouth. 
CLEVELAND HARBOR, OH (See Section 6 of Text). 
West breakwater. 
H.Doc. 481,68th Cong.,2d 
seas. 
Rivers and Harbors 
Committee Doc. 1, 71st 
Cong., 1st sess. 
H. Doc. 46, 73d Cong., 1st 
sess. 
Rivers and Harbors 
Committee Doc. 54, 74th 
Cong., 1st sess. 
H. Doc. 352, 78th Cong., 
1st sess. 
H. Doc. 151, 86th Cong., 
1st sess. 
H. Doc. 451, 87th Cong., 
2d sess. 
Sec. 107, PL 86-645. 
Authorized by Chief of 
Engineers Dec. 15, 1980. 
Sec. 18, PL 100-676. 
H. Doc. 97, 90th Cong., 
1st sess. 
Annual Report,1876, p.558. 
20-26

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Aug. 5, 1886 
Aug. 11, 1888 
Part of east breakwater.9 
Extension of east breakwater. 
H. Ex. Doc. 116, 48th 
Cong., 2d sess, and Annual 
Report, 1886, p. 1865.H. 
Ex. Doc. 189, 50th Cong., 
2d sess., and Annual 
Report, 1888, p. 2005. 
June 3, 1896 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1907 
June 25, 1910 
July 25, 1916 
Aug. 8, 1917 
Aug. 29, 1937 
Aug. 30, 193512 
Aug. 30, 193511 
Mar. 2, 19451' 
July 24, 1946 
July 3, 1958 
Reconstruction of piers.9 H. Doc. 326, 54th Cong., 
1st sess., and Annual 
Report, 1896, p. 2949. 
Dredging channel between piers and outer harbor to depth of 
19 feet; dredging to depth of 23 feet in any portion of harbor 
in discretion of Secretary of War. 
Arrowhead breakwater and extension of east breakwater. 
Removal of deflecting arm of old east breakwater and closure 
of gap between old and new east breakwaters. 
Pierhead at easterly end of east breakwater. 
Maintenance and improvement of channels in Cuyahoga and 
Old Rivers to a depth of 21 feet to a point 2,000 feet 
upstream from Clark Ave. viaduct and 18-foot turning basin. 
Deepening outer harbor and channel between piers to present 
project dimensions, construction of 400-foot spur breakwater 
at gap in shore arm of west breakwater, removal of easterly 
150 feet of west breakwater, elimination from project of a 
298-foot southerly extension on west pier, and abandonment 
of inner 932 feet of shore arm of west breakwater. 
Maintenance dredging in Cuyahoga and Old Rivers for 1 year 
as an emergency measure. 
Maintenance of extension of Cuyahoga River channel. 
Extension, maintenance, and improvement to a depth of 21 feet 
feet of Cuyahoga River channel to present project limit. 5"6 
Improvement of Cuyahoga and Old Rivers to a depth of 23 
feet and replacement or pier construction of 7 railroad 
bridges. 2 
Deepening channel 25 feet through east basin of outer harbor; 
replacement of Erie-Lackawanna Railroad bridge over 
Cuyahoga River at mile 4.1 and widening of channel at that 
point, with elimination of reconstruction of east pier of bridge 
as previously authorized; and replacement of Baltimore and 
Ohio Railroad Bridge over Old River near its mouth and 
Willow Avenue Highway Bridge about 800 feet above mouth 
and widening channel at four locations along lower, 2,000 
feet of river.3 
H. Doc. 156, 55th Cong., 
2d sess., and Annual 
Report 1899, p. 30 7 5 and 
3078. 
H. Doc. 118, 56th Cong., 
2d sess. 
No printed report. 
H. Doc. 891, 63d cong., 2d 
sess. 
H. Doc. 707, 63d Cong., 
2d sess., and Rivers and 
Harbors Committee Doc. 
84, 74th Cong., 2d sess. 
H. Doc. 477, 72d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 39, 74th 
Cong., 1st sess. 
Specified in act. 
H. Doc. 95, 79th Cong., 
1st sess. 
H. Doc. 629, 79th Cong., 
2d sess. 
H. Doc. 107, 85th Cong., 
1st sess. 
20-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
July 14, 1960 
Oct. 23, 1962 
July 14, 1960 
as amended 
Oct. 22, 1976 
H. Doc. 152, 86th Cong., 
1st sess. 
H. Doc. 527, 87th Cong., 
2d sess. 4 
Sec. 107, PL 86-645. 
Authorized by Chief of 
Engineers Dec. 6, 1966. 
Sec. 175, PL 94-587 
Depth of 29 feet in lake approach to main entrance; 28 feet 
in entrance channel to lakeward ends of piers at mouth of 
Cuyahoga River; 27 feet in river to a point just above its 
junction with Old River, and in Old River to upstream limit 
of present 23-foot project; 28 feet in west basin within 
existing project limits as modified to eliminate a triangular 
area at west end and to extend limits to a line parallel to and 
75 feet from harbor line; and 28 feet in westerly 800 feet of 
east basin. 
An area in east basin 27 feet deep extending 3,800 feet easterly 
of 28-foot area with project limits 380 feet from east 
breakwater and on landward side generally by a line 75 feet 
lakeward of and parallel to harbor line. A dock channel to 
Nicholson Cleveland Terminal Co. pier, at easterly end of 
east basin, from 25-foot contour to a limit 75 feet north of 
pierhead line, 400 feet wide at shoreward end and flared 
toward the lake. 
Deepening upper end of Old River channel from 21 to 27 feet. 
Preparation of Phase I design memorandum for improvements 
consisting of removal of portions of entrance breakwater; 
construction of breakwater; construction of breakwater 
extension of east entrance; deepening approach and entrance 
channels; construction of diked disposal area; and, installation 
of recreational fishing facilities on west breakwater. 
Deepening and widening east entrance and approach channels, 
channels, deepening the east basin channel and disposing of 
dredge material in an existing disposal site, as described 
in the Report to the Board of Engineers for Rivers and 
Harbors January 22, 1985, including bulkheading and other 
necessary repairs at Pier 34 and approach channels and 
necessary protective structures for mooring basins for 
transient vessels in the area south of Pier 34 and including 
such modifications as may be recommended by the Chief of 
Engineers at a cost not to exceed $36,000,000. 
Bulkheading and other necessary repairs at Pier 34 and 
approach channels and necessary protective structures for 
mooring basins for transient vells in the area south of Pier 
34. 
Appropriates and directs the Secretary of the Army to use the 
sum of $11,000,000 which is to remain available until 
expended to carry out the provisions for the harbor 
modifications contained in PL 99-662. 
Sec. 202, PL 99-662. 
PL 100-202. 
20-28 
Aug. 15, 1985 PL 99-88 
Nov. 17, 1986 
Dec. 21, 1987

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Acts Work Authorized Documents 
June 25, 1910 
Aug. 8, 1917 
Aug. 30, 1935n" 
Oct. 23, 1962 
Nov. 7, 19668 
Nov. 28, 1990 
Mar. 2, 1827 
Mar. 2, 1867 
June 3, 1896 
June 25, 1910 
June 30, 1948 
CONNEAUT HARBOR, OH (See Section 7 of Text) 
Extension of east breakwater, construction of new west 
breakwater, removal of portion of old west breakwater, 
and dredging of outer harbor to 19 feet. 
Realignment of west breakwater, removal of remainder of 
old west breakwater, and deepening outer harbor to 20 feet. 
Removal of Bessemer & Lake Erie R.R. Co. of inner 635 
feet of west pier.17 
Removal of portion of west breakwater, extension of 
breakwaters to present project dimensions, construction 
of pierheads on outer ends of breakwaters, deepening outer 
harbor to present project dimensions; removal of portions 
of river pier, and elimination from project of a 255-foot 
shoreward extension of west breakwater. 
Deepening easterly part of outer harbor to 28 feet in soft 
material and 29 feet in hard material; deepening remaining 
triangular area of outer harbor to 22 feet in soft material 
and 23 feet in hard material; deepening inner harbor for 
2,450 feet upstream of outer end of west pier to 27 feet in 
soft material and 28 feet in hard material; removal of east 
pier, extension of east breakwater to shore; and an access 
channel 8 feet deep in outer harbor to city dock. Previously 
authorized, but uncompleted portion of work authorized by 
1917 and 1935 acts combined with this act for accomplishment 
as a single improvement. 
Recreational small boat harbor provided by: a stone dike 
about 2,200 feet long; acess channels 6 feet deep, 2,800 
feet long and 100 feet wide; closing of 100-foot gap in 
existing west breakwater, and personnel guardrail on west 
breakwater. 
Continuation of 1966 authorization. 
DUNKIRK HARBOR, NY (See Section 8 of Text). 
Construction of west pier. 9"8 
Breakwater and evacuation of entrance channel to 13 
feet. 9 
Deepening of entrance channel and harbor basin to a depth 
of suitable for vessels of 16-foot draft. 
Removal of rock reef bordering the inner entrance channel. 
Deepening outer entrance channel to present project depths; 
removal of rock shoal on the west side of the entrance 
channel to a depth of 17 feet, and changed limits of the 
inner entrance channel and basin to present project 
dimensions. 
Doc. 653, 61st Cong., 2d 
seas. 
H. Doc. 983, 64th Cong., 
1st sess. 
H. Doc. 48, 73d Cong., 1st 
sess. 
H. Doc. 415, 87th 
Cong.,2d sess. 
H. Doc. 484, 89th Cong., 
2d sess.4 
Sec. 107, PL 101-640. 
S.Ex.Doc.42, 35th Cong., 
1st sess. and Annual Report 
1866 pt. IV, p.155 
Annual Report,1871,p. 214 
H. Doc. 63, 54th Cong., 
1st sess. 
H. Doc. 720, 61st Cong. 
2d sess. 4 
H. Doc. 632, 80th Cong., 
2d sess. 
20-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Dec. 15, 1970 
(House Public 
Works Committee) 
June 22, 1971 
(Senate Public 
Works Committee) 
Sec. 201 of 
F.C.Act of 1965 
May 26, 1824 
Mar. 3, 1899 
June 15, 1910 
Nov. 28, 192020 
Aug. 30, 1935 
Mar. 2, 1945 
Sept. 3, 1954 
July 14, 1960 
Oct. 23, 1962 
Mar. 3, 182521 
June 3, 1896 
Mar. 3, 1905 
Construction of small-boat harbor. 
ERIE HARBOR, PA (See Section 9 of Text). 
Breakwaters and piers; dredging entrance channel; and 
brushwood protection of beach of Presque Isle peninsula.9 
Deepening channel and harbor basin too 18 feet; repair and 
extension of piers; and plant growth and emergency 
protection of work on peninsula. 
Deepening channel and part of harbor to 20 feet. 
Reconveyed Presque Isle Peninsula to the State of 
Pennsylvania for park purposes. 
Deepening, widening, and straightening entrance channel, 
dredging channel at easterly end of harbor basin, all to 
present project dimensions; elimination of north breakwater 
from project; and limitation of south breakwater to a length 
of 1,200 feet. 
Protection of the peninsula south of the waterworks settling 
basin. 
Widen 25-foot deep approach channel to ore dock. 
Depth of 29 feet in the entrance channel to a point opposite 
the inner end of the north pier, thence 28 feet in soft 
material and 29 feet in hard material in the remainder of the 
entrance channel, within the general limits of the 25-foot 
basin and inner channel opposite the ore dock except as 
modified to eliminate from the project a triangular area 
along the easterly side; and a depth of 28 feet over 300-foot 
westward extension of the 25-foot basin. 
Depth of 27 feet in soft material and 28 feet in hard material 
in approach area to Duquesne Marine Terminal. Previously 
authorized but uncompleted portion of work authorized by 
1935 act is combined with this act as a single improvement. 
FAIRPORT HARBOR, OH (See Section 10 of Text). 
Construction of piers. 
Breakwaters and dredging outer harbor to a depth of 18 feet. 
H. Doc. 91-423, 91st 
Cong., 2d sess. 
Annual Report, 1915, p. 
1965. 
H.Doc.70,55th Cong.,1st 
sess. and Annual Report, 
1896,p.3237.19 
Rivers and Harbors 
Committee Doc. 26, 61st 
Cong., 2d sess. 
H. Doc. 52, 73d Cong., 1st 
sess. 
Specified in act. 
H. Doc. 345, 83d Cong., 
2d sess. 
H. Doc. 199, 86th Cong., 
1st sess. 
H. Doc. 340, 87th Cong., 
2d sess. 4 
Annual Report, 1889, pp. 
2147-2153. 
H.Doc.347,54th Cong.,1st 
sess. and Annual Reports, 
1896, p.2956; 1903, p. 
2084; 1905, p. 2349. 
20-30

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Mar. 2, 1919 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935" 
Aug. 26, 1937 
July 24, 1946 
July 14, 196032 
May 10, 1977 
(House Public 
Works Comm.) 
Oct. 1, 1976 
(Senate Public 
Works Comm.) 
Sec. 201 of F.C. 
Act of 1965 
Nov. 28, 1990 
Mar. 2, 1829 
Aug. 2, 1882 
Mar. 3, 1925 
July 3, 1930 
1,400-foot extension of east breakwater, present project 
dimension of east pier, and deepening of to 19 feet. 
4,000-foot extension of east breakwater at limit of cost to 
the United States of $715,000. 
Deepening of outer harbor and entrance channel to present 
dimensions; extending the west breakwater to present 
project dimensions with pierhead at its outer end; removal 
of west pier, and construction of bulkhead on west side of 
river channel. 
Dredging of 21- and 24-foot river channels and turning basin 
in Grand River to present project dimensions. 
Dredging of 8-foot river channel. 
Depth of 29 feet in the approach channel from the lake; a 
depth of 28 feet over a width of 800 feet in outer harbor; 
a depth of 27 feet in soft and 28 feet in hard material in 
Grand River, over a width of 200 feet to upstream limit of 
the turning basin, with suitable widening at the bends, 
thence over widths reducing from 200 to 100 feet to the 
upstream limit of the existing Federal project, except in 
the 8-foot channel; enlargement of the turning basin, 
including deepening of the entire basin to 21 feet; and 
minor modification of the existing project limits in the 
outer harbor. 
Construction of a small boat harbor. 
Continuation of 1960 and 1965 authorizations. 
GREAT SODUS BAY HARBOR, NY 
(See Section 11 of Text). 
Construction of piers and breakwater. 9 
Extension of piers to 15-foot contour in the lake. 
Deepening and widening of channel to 18-foot depth and 
150-foot width. 
Widening channel lakeward of piers to 250 feet. 
H. Doc. 206, 63d Cong., 
1st sess. 
H. Doc. 592, 69th Cong., 
2d sess., Rivers and 
Harbors Committee Doc. 
13, 70th Cong., 1st sess. 
H. Doc. 472, 72d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 79, 74th 
Cong., 2d sess.4 
H. Doc. 706, 79th Cong., 
2d sess. 4 
H. Doc. 347, 86th Cong., 
2d sess. 4 
H. Doc. 627, 94th Cong., 
2d sess. 
Sec. 107, PL 101-640 
Annual Report, 1876 pt. II 
p. 589. 
Annual Report, 1881, p. 
2442. 
H. Doc. 192, 68th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc. 17, 70th 
Cong., 1st sess. 
20-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Aug. 30, 1935 
Mar. 2, 1905 
Mar. 2, 1919 
Aug. 30, 1935" 
Oct. 23, 1962 
July 3, 1958 
Aug. 30, 1852 
June 23, 1866 
Mar. 3, 1871 
Mar. 3, 1881 
June 13, 1902 
Mar. 3, 1899 
Dredging channel to present project dimensions. 
HURON HARBOR, OH (See Section 12 of Text). 
Extension of west pier, construction of east breakwater, 
removal of part of old east pier; deepening of channel to 
19 feet; and dredging of sheltered area. 
Widening river to 200 feet; removal of remainder of old east 
pier, construction of new spur pier, enlargment of sheltered 
area; and closure of beach at shore end of west pier. 
Extension of west pierhead at its outer end; removal of outer 
end of east breakwater and contruction pierhead on new 
outer end; widening and deepening channel to present 
project dimensions; enlargement of turning basin at head 
of channel; shore protection west of west pier, and 
elimination from project constuction of spur pier and 
dreding shelterd area outside channel limits. 
Depths of 29 feet in approach channel, 28 feet in entrance 
channel, 27 feet in river channel, 21 feet in turning basin 
and abandonment of lakeward end of existing approach 
channel. 
IRONDEQUOIT BAY, NY (See Section 13 of Text). 
Construction of entrance channel 9 feet deep and 100 feet 
wide, extending from 9-foot depth in Lake Ontario to 
junction with inner bay channels, a distance of about 
1,300 feet; inner channel, 8 feet deep and 100 feet wide, 
from entrance channel to deep water in bay, a distance of 
about 3,035 feet, access channel 8 feet deep, 100 feet wide 
and 500 feet in length from the inner bay channel to the 
west; two stone rubblemound structures 1,350 feet and 750 
in length at the natural entrance; and recreational 
facilities. 
LITTLE SODUS BAY HARBOR, NY 
(See Section 14 of Text). 
West entrance pier.9 
Extension of west pier and construction of west 
breakwater, and dredging channel to 12 feet deep, 400 
feet wide.9 
East pier and east breakwater.9 
Extension of piers lakeward to 15.5-foot contour, and 
dredging channel to 15.5 feet. 
Extension of east pier 300 feet lakeward. 
LORAIN HARBOR, OH (See Section 15 of Text). 
Breakwaters and extension of piers to present dimensions. 
Rivers and Harbors 
Committee Doc. 23, 72d 
Cong., 1st sess. 
H. Doc. 
2d sess. 
H. Doc. 
sess. 
H. Doc. 
2d sess. 
122, 58th Cong., 
5, 63d Cong., 1st 
478, 72d Cong., 
H. Doc. 165, 87th Cong., 
1st sess. 4 
H. Doc. 332, 84th Cong., 
2d sess. 
Annual Report,1874, p.256 
Annual Report, 1874, p. 
256. 
Annual Report,1871,p.234 
Annual Report, 1881, pp. 
2444 and 2446. 
Annual Report, 1901, p. 
3364. 
H. Doc. 131,55th Cong., 
2d sess., and Annual 
Report 1898, p. 2718. 
20-32

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Mar. 2, 1907 
June 25, 1910 
Aug. 8, 1917 
Aug. 8, 1917 
July 3, 1930 
Aug. 3b, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Mar. 2, 1945 
July 14, 1960 
July 14, 1960 
as amended 
Nov. 17, 1986 
Mar. 2, 1945 
Extend 18-foot channel from inner end of piers to Erie 
Avenue Bridge. 
Extend breakwaters and dredge to depth of 19 feet in outer 
harbor. 
Extend breakwaters to present dimensions. 
Deepen outer harbor and river channel of Erie Avenue Bridge 
to 20 feet. 
Extend 20-foot channel to American Shipbuilding Co. 
drydock. 
Widen 2 bends in river and enlarge turning basin opposite 
National Tube Co. dock.' 2 
Approach channel to municipal pier. 
Deepen outer harbor and river channel to American 
Shipbuilding Co. drydock 2 present project dimensions 
and extension of river channel to upper end of National 
Tube Co. dock with turning basin opposite that dock. 
Maintenance dredging in Black River from American 
Shipbuilding Co. drydock 2. Upper end of National Tube 
Co. dock was authorized Apr. 7, 1934, by Public Works 
Administration. 
Enlarging turning basin opposite National Tube Co. dock 
to present project dimensions. 
Turning basin in bend of Black River immediately upstream 
from Baltimore & Ohio RR coal dock. 
Replace Norfolk and Western Railway swing bridge with a 
vertical lift bridge; construct two detached arrowhead 
breakwaters lakeward of existing breakwaters; construct 
extension of east breakwater, to shore; remove 300 feet of 
lakeward end of west breakwater; remove outer 1,100 feet 
east pier; deepen lake approach to 29 feet, 800-foot wide 
outer harbor channel to 27 feet; widen river channel at 
bends; and construct a new turning basin 21 feet deep near 
upstream limit of existing project.27 
Construction of a 225 foot detached rubblemound breakwater 
and an 800 foot long rubblemound breakwater attached to 
the east breakwater shorearm in the east basin of the outer 
harbor. 
Two bed cuts on Black River between the Norfolk and 
Western Railroad Bridge and 21st Street Bridge, excavated 
to existing channel depth of 27 feet. Widening Upper 
Turning Basin at existing authorized depth of 21 feet.8 
OAK ORCHARD HARBOR, NY(See Section 16 of Text) 
Harbor of refuge. 
H. Doc. 560, 60th Cong., 
1st sess. 
H. Doc. 644, 61st Cong., 
2d sess. 
H. Doc. 980, 64th Cong., 
1st sess. 
H. Doc. 985, 64th Cong., 
1st sess. 
H. Doc. 587, 69th Cong., 
2d sess. 
H. Doc. 469, 72d Cong., 
2d sess. 
Senate Committee print, 
73d Cong., 2d seas. 
Rivers and Harbors 
Committee Doc. 51, 74th 
Cong., 1st sess. 
Specified in act. 
H. Doc. 161, 77th Cong., 
1st sess. 
H. Doc. 166, 86th Cong., 
1st. sess. 
Sec. 107, PL 86-645. 
Authorized by Chief of 
Engineers Mar 12, 1986 
H. Doc. 124, 99th Cong., 
1st sess. 
H. Doc. 446, 78th Cong., 
2d sess. 
20-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Mar. 2, 1867 
Mar. 4, 1913 
Nov. 17, 1986 
July 11, 1870 
Mar. 2, 1907 
July 3, 1930 
Aug. 30, 1935 
Oct. 17, 1940 
June 30, 1948 
Sept. 3, 1954 
Oct. 23, 1962 
Dec. 17, 1970 
Nov. 28, 1990 
OLCOTT HARBOR, NY (See Section 17 of Text). 
Dredging a channel 11 feet deep between parallel piers.9 
Deepening channel to 12 feet and maintenance of west pier. 
Construct the project for Navigation, Report of the Chief of 
Engineers dated June 11, 1980. 
OSWEGO HARBOR, NY (See Section 18 of Text). 
Construction of outer west breakwater. 9 
Repair of outer west breakwater under Plan (A).3 
Construction of arrowhead breakwaters; deepening outer 
harbor between breakwaters; west outer harbor east of 
Erie-Lackawanna coal dock, and Oswego River north of 
Seneca St., 21 feet; and deepening west outer harbor, west 
of Erie-Lackawanna coal dock, to 16 feet."9 
Widening channel to harbor line in Oswego River north of 
Seneca Street. 
Closing gap in west breakwater, deepening west outer harbor, 
west of east line of Erie-Lackawanna coal dock, to project 
depth.3 
Construction of east outer breakwater; removal of the inner 
end of east arrowhead breakwater; and dredging channel 
and basin in east outer harbor.31 
Construction of detached breakwater at harbor entrance and 
removal of shoals in approach to harbor entrance to 25 feet 
deep. 
Depth of 27 feet in lake approach channel; 25 feet deep in 
outer harbor channel 800 feet wide from entrance gap to a 
turning basin 25 feet deep about 750 by 1,100 feet, at 
mouth of Oswego River; depth of 24 feet in earth and 25 
feet in hard material in river channel from turning basin 
to upstream end of Port of Oswego Authority's east side 
terminal, a distance of about 1,600 feet; relocation of 
Federal project limits in Oswego River upstream of 24-foot 
channel to Federal project limit at north line of West 
Seneca St., on lines parallel to 50 feet channel ward of 
established harbor lines; elimination of modification 
authorized by River and Harbor Act of 1948. 
OTTAWA RIVER HARBOR,MI,OH (See Section 19 of 
Text). 
6-foot deep, 16,500-foot long channel in Ottawa River and 
8-foot deep, 15,000-foot channel in Maumee Bay. 
Continuation of authorization. 
Annual Report, 1866, pt. 
III, p. 15 pt. IV, p. 158. 
H. Doc. 780, 62d Cong., 
2d seas. 4 
Sec. 601, PL 99-662 
Annual Report, 1870, pp. 
54, 220 and 221. 
H.Doc.55,58th Cong.2d 
sess. 
Rivers and Harbors 
Committee Doc. 24, 71st 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 7, 74th 
Cong., 1st sess. 
H. Doc. 96, 76th Cong., 
1st sess. 
H. Doc. 722, 80th Cong., 
2d sess. 
H. Doc. 487, 81st Cong., 
2d sess. 
H. Doc. 471, 87th Cong., 
2d sess. 
H. Doc. 396, 91st 
Cong.,2d sess. 
Sec. 107, PL 101-640. 
20-34

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Mar. 2, 1945 
Nov. 17, 1986 
Mar. 2, 1829 
Aug. 2, 1882 
June 25, 1910 
Aug. 30, 19356 
Mar. 2, 1945 
July 14, 1960 
June 10, 1872 
Aug. 26, 1937 
Oct. 27, 1965 
Mar. 3, 1899 
June 13, 1902 
Mar. 2, 1919 
Jan. 21, 1927 
Aug. 30, 19352 
PORT ONTARIO, NY (See Section 20 of Text). 
Construct harbor of refuge. 
Maintain harbor of refuge. 
ROCHESTER HARBOR, NY (See Section 21 of Text). 
Construction of piers.9 
Extension of piers to 15-foot contour in the lake. 
Concrete superstructure on piers.9 
Deepening channel to 20 feet. 
Dredging of the entrance channel and turning basin, 
and the elimination of the inner ends of the east and 
west piers, all to present project dimensions. 
Maintenance of existing channel upstream of the Penn 
Central Co. bridge. 
Depth of 24 feet in the channel from the lake to the 
west pier, a depth of 23 feet beween the piers and in 
the lower river to the Penn Central Co. bridge, 
including the existing turning basin; a depth of 21 feet 
from the bridge to the upstream project limit, with 
suitable widening at the bends; and, upstream turning 
basin 21 feet deep and 650 feet wide adjacent to the 
improved channel, with two mooring dolphins. 
ROCKY RIVER HARBOR, OH (See Section 22 of Text). 
East pier and dredging of channel. 
Extension of east pier and deepening channel to present 
project dimensions. 
Realign and extend channel and construct an anchorage 
basin. 
SANDUSKY HARBOR, OH (See Section 23 of Text). 
Construction of channel protection works. 
Widening of Straight and Dock channels and deepening 
to 19 feet. 
Extension of east jetty to toal length of 6,000 feet, with 
pierhead on outer end; deepening of the outer, straight, 
and easterly portion of Dock channel to 20 feet. 
Deepening of Dock Channel to 22 feet. 
Enlargement of turning basin and construction of rock 
dike. 
H. Doc. 446, 78th Cong., 
2d sess. 
Sec. 615, PL 99-662. 
Annual Report,1874,p.247. 
Annual Report, 1881,p.2437 
Annual Report, 1905,p. 2 3 8 3 
H. Doc. 342, 61st Cong., 
2d sess. 
H. Doc. 484, 72d Cong., 
2d sess. 
H. Doc. 139, 76th Cong., 
1st sess. 
H. Doc. 409, 86th Cong., 
2d sess. 4 
Annual Report 1871, p. 2 1 1 
H. Doc. 70, 75th Cong., 
1st sess. 
H. Doc. 352, 88th Cong., 
2d sess. 4 
H. Doc. 362, 55th Cong., 
2d sess. and Annual Report 
1898, p. 2708. 
H. Doc. 120, 56th Cong., 
2d sess. 
H. Doc. 982, 64th Cong., 
1st sess. 
H. Doc. 584, 69th Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc. 2, 73d 
Cong, 1st sess. 
20-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Mar. 2, 1945 
July 14, 1960 
Mar. 3, 1899 
June 25, 1910 
Aug. 30, 1935 
May 17, 1950 
Sept. 3, 1954 
July 3, 1958 
July 14, 1960 
July 4, 1836 
Maintenance of Bay Channel to 22 feet; and elimination 
from project of portion of turning basin and rock 
dike. 
Extending Moseley Channel and deepening that channel 
and the outer end of Straight channel to 26 feet, 
from deep water in the lake to the vicinity of 
Cedar Point dock; widening the bend at the junction 
of the Moseley and Straight channels to 25 feet from 
the vicinity of Cedar Point dock to junction Bay 
channel; deepening the Bay channel from the junction 
with the Straight channel to the outer end of the 
Pennsylvania Coal dock No. 3 to 24 feet, thence from 
outer end of the coal dock to the turning basin to 24 
feet in soft material and 25 in hard, with no Federal 
dredging within 50 feet of the dock; and enlarging the 
turning basin, including removal of approximately 300 
feet of the rock dike, and deepening to 24 feet in soft 
material and 25 feet in hard. 
TOLEDO HARBOR, OH (See Section 24 of Text). 
A channel 400 feet wide and 21 feet deep from 25-foot 
contour in Maumee Bay to Fassett Street Bridge, 200 
feet wide and 19 feet deep above that point and a 500 
-foot turning basin at Upper End. A stone revetted 
earth dike in Maumee Bay Channel. 
Act 1899 modified to insure a navigable channel to 21 
feet from Fassett Street Bridge to Lake. 
Channel 25 feet deep and 500 feet wide from 25-foot 
contour to mouth of Maumee River (300 feet wide on 
each side of center dike in Bay Channel), thence 400 
feet wide to Fassett Street Bridge, 200 feet wide above 
that point and a turning basin at Upper end 18 feet 
deep. 
Widening at bend of mouth of River opposite 
Chesapeake and Ohio Railway Dock. 
Removal of center dike in Maumee Bay Channel. 
Enlarge widening at bend opposite Chesapeake and 
Ohio dock and turning basin opposite American 
Shipbuilding Co. dock. 
Deepening Bay Channel including widenings to 28 feet, 
deepen River channels to New York Central Railroad 
Bridge to 27 feet and construct new turning basin 
below Anthony Wayne Bridge. 8 
VERMILION HARBOR, OH (See Section 25 of Text). 
Parallel piers and dredging channel to 8 feet deep. 
H. Doc. 328, 76th Cong., 
1st sess. 
H. Doc. 144, 86th Cong., 
1st sess. 4 
H. Doc. 198, 55th Cong., 
2d sess. and Annual Report 
1898, p. 2693. 
H. Doc. 865, 60th Cong., 
1st sess. 
River and Harbors 
Committee Doc. 21, 72d 
Cong., 1st sess. 
H. Doc. 189, 81st Cong., 
1st sess. 
H. Doc. 620, 81st Cong., 
2d sess. 
H. Doc. 436, 84th Cong., 
2d sess. 
H. Doc. 153, 86th Cong., 
1st sess. 4 
Annual Report, 1880. 
20-36

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Mar. 3, 1875 
Mar. 3, 1905 
July 3, 1958 
Oct. 27, 1965 
Mar. 2, 1945 
Aug. 3, 1968 
July 14, 1960 
July 14, 1960 
Nov. 17, 1986 
Sept. 3, 1954 
July 14, 1960 
Mar. 7, 1974 
Deepening of channel to 12 feet. 
Reconstruction of piers. 
New entrance formed by two overlapping arrowhead 
breakwaters and extension of existing river channel 
upstream to Liberty St. Bridge. 
WEST HARBOR, OH (See Section 26 of Text). 
Construction of arrowhead breakwaters, entrance 
channel and access channel. 
WILSON HARBOR, NY (See Section 27 of Text). 
Entrance channel 80 feet wide and 8 feet deep; and 
restore east amd west piers. 
Extend existing channel 300 feet; and construct new 
channel 3,800 feet long through Tuscarora Bay. 
STURGEON POINT, EVANS, NY (See Section 30 of 
Text). 
Rehabilitate existing breakwater, construct rubblemound 
west breakwater extension, construct rubblemound east 
breakwater, a shore revetment and dredging. 
TOUSSAINT RIVER, CARROLL TWSP., OH 
(See Section 30 of Text). 
Dredged channel from the mouth of the Toussaint River, 
2,100 feet into the Lake Erie, 4 feet below LWD, 150 
feet wide in Lake Erie and tapered to 100 feet at the 
river mouth. 
MAUMEE BAY STATE PARK BAY, OH (See Section 31 
of Text). 
Protective sand beach stabilized by rubblemound 
offshore breakwaters and jetties alongs the west half of 
park shoreline and rubblemound revetment at the east 
end of the park. 
PRESQUE ISLE PENINSULA, ERIE, PA (See Section 32 
of Text). 
Construction of groin system, seawall, bulkhead, 
placement of beach material at waterworks reservation 
and along remainder of peninsula; removal of portions 
of existing structures. 
Periodic nourishment of shores for a 10-year period. 
Periodic nourishment of shore for a 5-year period. 
Annual Report,1874,p.219 
H. Doc. 252, 58th Cong., 
2d sess. 
H. Doc. 231, 85th Cong., 
1st sess. 
H. Doc. 245, 88th Cong., 
2d sess. 
H. Doc. 679, 76th Cong., 
2d sess. 
H. Doc. 112, 90th Cong., 
1st sess. 
Sec. 107, PL86-645. 
Authorized by Chief of 
Engineers Oct. 21, 1987 
Sec. 107, PL 86-645. 
Authorized by Chief of 
Engineers Sept. 29, 1990. 
Sec. 501, PL 99-662. 
H. Doc. 231, 81st Cong., 
1st sess. 
H.Doc. 397,86th Cong.,2d 
sess. 
H. Doc. 796, 93d Cong., 
2d sess. 
20-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
Oct. 22, 1976 
Nov. 17, 1986 
Oct. 23, 1962 
Oct. 23, 1962 
as amended 
Oct. 23, 1962 
as amended 
Dec. 31, 1970 
Mar. 7, 1974 
Dec. 22, 1944 
June 30, 1948 
June 30, 1948 
as amended 
June 30, 1948 
as amended 
Preparation of Phase I design memorandum for 
improvements consisting of construction of five sections 
of spaced offshore breakwaters and replenishment of 
beach area with sandfill. 
Construct offshore breakwaters and restore beaches. 
CENTURY PARK, LORAIN, OH (See Section 34 of 
Text). 
Construction of two stone groins, removal of a stone 
deflection wall and placement of clean beach fill 
material. 
LAKESHORE PARK, ASHTABULA, OH (See Section 34 
of Text). 
Construction of offshore breakwaters, restoration of an 
800-foot long beach, and subsequent periodic 
nourishment as necessary. 
SIMS PARK, EUCLID, OH (See Section 34 of Text) 
Construction of approximately 800-foot long by 180-foot wide 
artificial headlands beach; approximately 108,000 square 
feet of improved beach surface area; fronted by three 
segmented rubblemound breakwaters, and east and west 
terminal groins. 
ELLICOTT CREEK, NY (See Section 35 of Text). 
Widening, straightening and deepening channel in 
Ellicott Creek Park; construct diversion channels; 
construct 3 highway bridges; modify utilities and 
drainage outlets; and construct recreation facilities. 
MT. MORRIS LAKE, GENESEE RIVER, NY 
(See Section 36 of Text). 
Construction of a concrete gravity dam and reservoir. 
RENO BEACH-HOWARD FARMS AREA, OH 
(See Section 37 of Text). 
Construction of dike and levees. 
CONESUS LAKE, LIVONIA, NY 
(See Section 41 of Text). 
Construction of sheetpiling, concrete control structure, 
outlet channel, and creek channelization. 
EUCLID CREEK, CLEVELAND, OH (See Section 41 of 
Text). 
Construction of diversion channel, levees, and creek 
channelization. 
Sec. 101, PL 94-587 
Sec. 501, PL 99-662. 
Sec. 103, PL 87-874, 
Authorized by Chief of 
Engineer July 11, 1989. 
Sec. 103, PL 87-874. 
Authorized by Chief of 
Engineers April 26, 1982. 
Sec. 103, PL 87-874. 
Authorized by Chief of 
Engineers Jan. 10, 1991 
Sec. 201, PL 91-611 
Sec. 14, PL 93-251 
H.Doc 615,78th Cong., 2d 
sess. 
H. Doc. 554, 80th Cong., 
2d sess. 
Sec. 205, PL 80-858. 
Authorized by Chief of 
Engineers July 22, 1985. 
Sec. 205, PL 80-858. 
Authorized by Chief of 
Engineers Oct. 9, 1981. 
20-38

BUFFALO, N Y DISTRICT 
Table 20-B Authorizing Legislation 
Acts Work Authorized Documents 
June 30, 1948 
as amended 
June 30, 1948 
as amended 
KEUKA LAKE, PENN YAN, NY (See Section 41 of Text). 
Removal of an existing earthen and masonry dam located just 
upstream of the Main Street Bridge and replace with 
additional slide gates tied into existing races located on each 
side of the stream. 
SWAN CREEK, TOLEDO, OH (See Section 41 of Text). 
Construct levees and sheetpile floodwalls along 3,100 linear 
feet of the left bank, a small ponding area with three outfalls 
for interior drainage, and relocation of about 500 linear feet 
of channel bottom. 
Sec 205, PL 80-858. 
Authorized by Chief of 
Engineers Jan. 25, 1991. 
Sec 205, PL80-858. 
Authorized by Chief of 
Engineers May 15, 1991. 
1. Authorized by Public Works Administration, Sept. 6, 1933. 
2. Widening Cuyahoga River downstream at end of Cut 4 classfied inactive. 
3. Replacement of bridges 19 and 32, widening Cuyahoga and Old River 
Channels, classified deferred. 
4. Contains latest published map. 
5. Permanent Appropriations Repeal Act. 
6. Authorized May 28, 1935 by Emergency Relief Administration Act of 1935. 
7. Improvement of guide pier at Black Rock Lock was deauthorized by Congress 
in August 1977. 
8. Classified deferred. 
9. Completed under previous projects. 
10. Also Sundry Civil Act of Mar. 3, 1905. 
11. Authorized in part by Public Works Administration, Sept. 6, 1933. 
12. Authorized by Public Works Administration, Sept. 6, 1933. 
13. Previously authorized by Public Works Administration. 
14. First Deficiency Appropriations Act approved April 1, 1944. 
15. Authorized by Defense Plant Corp., May 19, 1942. 
16. Deepening left half of channel extension was eliminated from project by 1962 
R&H Act. 
17. Permit of Secretary of War, Aug. 5, 1927. 
18. Modified 1828 and 1852. 
19. Extension of north pier portion of this modification was deauthorized Nov. 
1981. 
20. Public Law 366. 
21. Modified 1830, 1881, and 1890. New work completed under previous 
projects. 
22.Partly included in Public Works Administration program, 
Nov. 15, 1933. 
23. First Supplemental National Defense Appropriation Act, 1944 approved 
Dec. 23, 1943. 
24. Deepening remainder of Cuyahoga River from bridge 1 to and including 
Old River, classified deferred. 
25. Included in Public Works Administration program, Nov. 15, 1933. 
26. Deepening strips adjacent to north and south piers was deauthorized Aug. 
1982. 
27. Deepening and widening remainder of Black River channel at Cut 1 has 
been deauthorized. 
28. The 27-foot project extended 2,800 feet an turning basin relocated under 
authority of Chief of Engineers. 
29. Deepening a 200-foot strip along harbor line east of mouth of Oswego 
River is deauthorized. 
30. Deepening to 22 feet a 150-foot wide strip in west outer harbor 
deauthorized in May 1981. 
31. Modification eliminated by River and Harbor Act of Oct. 26, 1962. 
32. Modification classfied inactive. 
20-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 29 of Text)
Construction 
Cost to 
September 30, 1992 
Operations and 
Maintenance 
Barcelona Harbor, NY 
Big (Cunningham) Creek, OH' 
Black River Harbor, NY4 
Cape Vincent Harbor, NY 
Cattaraugus Creek, NY5s 
Geneva-on-the-Lake, OH 
Grasse River (Massena),NY 
Kelleys Island, OH 
Little River at Cayuga Island, NY 
Morristown Harbor, NY 
Niagara Remedial Works, NY' 
Niagara River, NY'3 
Ogdensburg Harbor, NY 
Port Clinton Harbor, NY 
Pultneyville Harbor, NY" 
Put in Bay, OH 
Sackets Harbor, OH 
Sandusky River, OH4 
Completed 
Completed 
Completed 
Completed 
Active 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1989
2 
_2 
1962
2 
1990 
1891 
197412 
1969 
1949 
1966 
1964 
1987 
1985 
1934 
195112 
1982 
1894 
$ 1,185,85316 
19,763' 
42,401 
275,082 
57,410 
3,145,17617 
9,0003 
129,874 
46,804' 
6,221 
6,069,395 
559,4579 
1,720,46614 
71,950 
68,219 
51,609 
25,010 
58,0003 
$ 1,934,834 
1,565,262 
3,249 
5,949 
12,364 
510,819 
225,415 
1,399,363's 
942,532 
20,087 
14,050 
27,955 
557 
1. No commerce reported. 
2. Only information available is in index to reports of Chief of Engineers. 
3. Amount includes maintenance; not separable. 
4. Abandonment recommended in H. Doc. 467, 69th Cong., 1st sess. 
5. Abandonment recommended in Ex. Doc. 16, 35th Cong., 1st sess. 
6. Channel improved by local interests. 
7. Includes local interests contribution of $25,742. 
8. Costs of operation and maintenance of this project will be settled directly by 
concerned power agencies. No further appropriations will be made to this 
project. 
9. Includes local interest contribution of $27,563. 
10. Includes local interests contribution of $5,000. 
11. Abandonment recommended in H. Doc. 375, 64th Cong., 1st sess. 
12. Annual Report for Detroit District. 
13. Construction of compensating works as authorized by 1930 R&H Act 
was authorized by Congress in August 1977. 
14. Includes $271,380 for previous projects. Excludes $57,000 contributed 
funds. 
15. Includes $130,512 for previous projects. 
16. Includes $56,616 for previous projects. Excludes $181,500 contributed 
funds. 
17. Excludes $3,261,375 contributed funds. 
20-40 
Project Status 
For Last 
Full Report 
See Annual 
Report For

BUFFALO, N Y DISTRICT 
TABLE 20-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
(See Section 33 of Text) 
For Last 
Fuall Report 
See Annual 
Project Report For Construction 
Cost to 
September 30, 1992 
Operations and 
Maintenance 
Hamlin Beach State Park, NY Completed 1976 $ 1,769,600 - 
Lakeview Park, Lorain, OH Completed 1987 1,741,1252- 
Selkirk Shore State Park, 
Lake Ontario, NY' Completed 1963 58,978 $ 2,946 
1. Federal participation was limited to one-third of first cost when project was 
authorized by 1954 River and harbor Act. Federal participation was changed 
from one-third to 70 percent of remaining work under Public Law 87-874. 
2. Does not include $739,700 contributed funds. 
20-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 40 of Text) 
For Last Cost to 
Full Report September 30, 1992 
See Annual Operations and 
Project Status Report For Construction Maintenance 
Auburn, NY, Owasco Oulet Completed 1962 $ 371,985- 
Batavia and vicinity, 
Tonawanda Creek, NY Completed 1957 335,385 - 
Camp Perry, OH Completed 19678 275,000- 
Cayuga Creek, 
Cheektowaga, NY2 Completed 1984 1,404,500 
Cuyahoga River Basin, OH Active 1985 1,117,000 
Dansville and vicinity, 
Canaseraga Creek, NY Active 1985 490,300- 
Fremont, OH, Sandusky River Completed 1976 8,589,8246 
Ithaca, Cayuga Inlet, NY Completed 1978 3,929,30(0?- 
Lackawanna, NY, Smokes Creek Completed 1971 3,542,0684 
Lancaster, Cayuga Creek, NY Completed 1954 797,300 
Marsh Creek, Geneva, NY Completed - 226,429- 
Montour Falls, 
Oswego River Basin, NY Completed 1954 1,681,785 
Onondaga Creek, Nedrow, NY2 Completed 1964 330,231 
Ottawa, OH Deferred 1989 374,000- 
Owasco Inlet and Outlet, 
Montville and Dry Creek, 
State Ditch and Crane Inactive 
Brook, NY' Deferred 1950 281,559 
Point Place, Toledo, OH Completed 1990 9,885,733" 
Scajaquada Creek, NY Completed 1985 4,944,852 
Syracuse, Oswego River 
Basin, NY Completed 1954 3,349,248 
Warsaw, NY, Oatka Creek2 Completed 1969 558,317- 
Wellsville, NY, Genesee River Completed 1978 3,145,30310 
1. In active portion of work for State Ditch has been done by local interest and 
work on Crane Brook has been deferred at the request oflocal intersts. 
2. Project authorized by Chief of Engineers. 
3. Excludes costs of $188,732 under Public Law 88-99, Flood Control and Coastal 
Emergencies Appropiration, incurred for project rehabilitation as a result of 
damages due to storm Agnes, June 1972. 
4. Includes local intersts contribution of $50,000. 
5. Excludes costs of $26,807 under Public Law 84-99, Flood Control and Coastal 
Emergencies Appropriation, incurred for project rehabilitation as a result of 
damages due to storm Agnes, June 1972. 
6. Includes local interests contribution of $,944. Excludes cost of $383,786 under 
Public Law 84-99. Flood Control and Coastol Emergencies Appropriation, for 
emergency restoration of levees damaged during 1973. 
7. Includes local interest contribution of $125,000. 
8. Annual Report for Detroit District. 
9. Includes local intersts contribution of $99,000. Excludes costs of $104,005 
under Public Law 84-99. Flood Control and Coastal Emergencies 
Appropriation, incurred for project rehabilitation as a result of damages due 
to storm Agnes, June 1972. 
10. Includes local interests contribution of $50,000. 
Excludes costs of $374,042 under Public Law 84-99, Flood Control and 
Coastal Emergencies Appropriation, incurred for project rehabilitation as a 
result of damages due to storms. 
11. Excludes $1,871,631 contributed funds. 
20-42

BUFFALO, N Y DISTRICT 
TABLE 20-G NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(See Section 30 of Text) 
Navigation Activities Pursuant to Section 107, Public Law 86-645 
(Preauthorization) 
Study Identification Fiscal Year Cost
$ 
East Harbor State Park, OH 14,187 
Henderson Harbor Cut, NY 19,568 
Lake Erie, Cooley Canal, Lucas, OH 8,213 
North Sandy Pond, Oswego County, NY 12 
TABLE 20-H FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 41 of Text) 
Flood Control Activities pursuant to Sec. 205 
Public Law 858, 80th Congress, as amended (preauthorization) 
Study Identification Fiscal Year Cost
$ 
Avon, OH 9,751 
Beaver Run/Walnut Creek, Milicreek, PA 5,677 
Black Creek, Town of Chili, NY 34,173 
Canadaway Creek, Fredonia, NY 2 
Cazenovia Creek, NY 170 
Cross Lake, NY 15,907 
Cuyahoga River, Tinkers Creek, OH 14,733 
Cuyahoga River, Valley View, OH 29,568 
Cuyahoga River, West Creek, Independence, OH 9,339 
Limestone Creek, Fayetteville, NY 38,104 
Murder-Goose Neck Creek, Corfu, NY 8,104 
Murder-Goose Neck Creek, Pembroke, NY 9,648 
North Ridgeville, OH 18,705 
Oneida Creek, NY 5,098 
W. Br. Limestone Creek, Manlius, NY 181,127 
20-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY1992 
TABLE 20-H(Cont.) FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(See Section 41 of Text) 
Emergency bank protection (Sec. 14 of 1986 Flood Control Act, 
Public Law 526, 79th Cong.) 
Study Identification Fiscal Year Cost 
$ 
Auburn Water Pump Fac'l, Auburn, NY 3,511 
Auglaize River, Paulding County, OH 3,023 
Beechwood Girl Scout Camp, Sodus, NY 2,079 
Butternut Creek, E. Syracuse, NY 3,688 
Canadaway Creek, Fredonia, NY 8,708 
Canaseraga Creek, Dansville, NY 11,894 
Cattaraugus Creek, Village of Arcade, NY 34,764' 
Chagrin River, Solon Rd., OH -4,052 
Chagrin River, East Branch, Route 84, OH 18,5222 
Cuyahoga River, Akron Peninsula Rd., OH -6,3383 
Cuyahoga River, Brecksville Rd., OH 35,9444 
Cuyahoga River at Co. Hwy. 10, OH 10,151 
Domonakas Library, Sheffield, OH 19,684 
Ganargua Creek, Plasermill Rd., NY 17,787 
Genesee River, Back River Rd., Amity, NY 4,7694 
Lake Erie, Eastlake, OH 3,986 
Lake Erie, Fredonia, NY 9 5 ,6 2 6s 
Lake Erie, Middle Bass Island, Deist Rd., OH -21,4536 
Lake Erie, SR 531, Ashtabula, OH 13,650 
Lake Sawyer, Camp Miakonda, Toledo, OH 8,854 
Maumee River, Providence Metropark, OH 2,815 
Maumee River, Wallbridge Park, OH 3,939 
Seneca Falls, NY 29,614 
Thatcher Brook, Gowanda, NY 60 
Warrenville Township, Mill Creek, OH 0' 
1. Does not include $11,030 in contributed funds. 4. Does not include $27,063 in contributed funds. 
2. Does not include $13,128 in contributed funds. 5. Does not include $25,655 in contributed funds. 
3. Does not include $7,781 in contributed funds. 6. Does not include $21,453 in contributed funds. 
7. Does not include $2,816 in contributed funds. 
20-44

BUFFALO, N Y DISTRICT 
TABLE 20-I DEAUTHORIZED PROJECTS 
(See Section 42 of Text) 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Black Rock Channel and Tonawanda Harbor, NY 
1935 R&H Act' 1962 Aug 1977 - - 
Black Rock Channel and Tonawanda Harbor, NY 
1954 R&H Act 1962 May 1981 -- 
Buffalo Harbor Drift Removal, NY - Dec 1992 - - 
Buffalo Ship Canal, Buffalo, NY - Dec 1992 - - 
Caledonia, Genesee River, NY 1950 FC Act 1950 Jan 1990 - - 
Cape Vincent Harbor, NY 1945 R&H Act 1962 Nov 1986 -- 
Chittenango Creek and Tributaries, NY 1944 FC Act 1948 Jan 1990 $ 12,464 - 
Crane Creek State Park, OH 1962 R&H Act 19683 Nov 1979 -- 
Dunkirk Harbor, NY WRDA 1986 Dec 1992- 
Eastlake, Chagrin River, OH 1965 FC ACt 1976 Jan 1990 506,344 - 
Edgewater Park, OH 1954 R&H Act - Jan 1990 - - 
Elk Creek Harbor, PA 1966 R&H Act 1978 Dec 1992 101,500 - 
Erie Harbor, PA 1899 R&H Act 1963 Nov 1981- 
Erie Harbor, PA 1945 R&H Act 1963 Aug 1977- 
Erie Harbor, PA 1960 R&H Act 1963 Aug 1982 -- 
Fairhaven Beach State Park, NY 1958 R&H Act - Jan 1990 - - 
Fort Niagara State Park, NY, Sec. 201 1965 FC Act - Jan 1990 - - 
Grandview Bay Harbor, NY 1945 R&H Act 1948 Aug 1977 1,524 - 
Great Sodus Bay Harbor, NY 1941 R&H Act 1963 Aug 1977 -- 
Hamlin Beach Harbor, NY 1968 R&H Act 1973 Jan 1990 72,052 - 
Hammondsport, Oswego River Basin, NY 
1941 FC Act 1951 Nov 1983 29,000- 
Huron Harbor, OH 1962 R&H Act6 1963 Jan 1990 
Ithaca, NY - Cascadilla Creek 1941 FC Act 1950 Aug 1977 8,159 - 
Ithaca, NY - Fall Creek 1941 FC Act 1950 Aug 1977 12,300 - 
Lorain Harbor, OH 1960 R&H Act, modified by 1966 Jan 1990 - 
1965 R&H Act5 
Maumee River, above Toledo, OH 1872 Act 19713 Nov 1977 12,000- 
Niagara River, Compensating Works, 
1930 R&H Act 1964 Aug 1977 
Ogdensburg Harbor, NY 1935 R&H Act 1986 Nov 1986 
Oswego Harbor, NY 1930 R&H Act 1963 Jan 1990 -- 
Oswego Harbor, NY 1940 R&H Act2 1963 May 1981 - 
Port Bay, NY 1950 R&H Act - Jan 1990 -- 
Red Creek, NY 1966 FC Act 1975 Nov 1986 361,241 - 
Sackets Harbor, NY 1945 R&H Act 1948 May 1981 19,010 - 
Selkirk Shores State Park, OH 1954 R&H Acts 1963 Jan 1990 - - 
Sheffield Lake Community Park, OH 1962 R&H Act - Aug 1977 - 
Watkins Glenn, NY 1941 FC Act 1958 Aug 1977 43,182- 
White City Park, OH 1954 R&H Act - Jan 1990 - 
1. Extension of guide pier only; other improvements completed. 4. Deepen East Outer Harbor. 
2. Deepening of west outer harbor, other improvements completed. 5. Uncompleted portion. 
3. Annual Report for Detroit District. 6. Breakwater. 
20-45 
I

DETROIT, MI DISTRICT* 
The district is composed of the upper and lower 
peninsulas of Michigan and portions of Indiana, Wisconsin 
and Minnesota, which border the lakes. It includes U.S. 
waters of Lakes Superior, Michigan, Huron, St. Clair and 
western Lake Erie. Unless otherwise indicated, all depths 
stated in this report are referred to low water datum as 
follows: Lake Superior, 601.1 feet; Lake Michigan- 
Huron, 577.5 feet; Lake Erie, 569.2 feet; and Lake St. 
Clair, 572.3 feet. These elevations are in feet above the 
mean water level at Rimouski, Quebec -- International 
Great Lakes Datum, 1985 (IGLD 1985). The IGLD 1985 
is a datum or reference system used to define water levels 
within the Great Lakes - St. Lawrence River system. This 
datum was implemented in January 1992, officially 
replacing IGLD 1955. At the time IGLD 1955 was 
established, it was recognized that this datum would have 
to be periodically revised due to isostatic rebound. 
Isosatic rebound is the gradual rising or bouncing back of 
the earth's crust from the weight of the glaciers that 
covered the Great Lakes region during the last ice age. 
IMPROVEMENTS 
Navigation 
1. Alpena Harbor, MI.................. 
2. Arcadia Harbor, MI ................ 
3. Ashland Harbor, WI ................ 
4. AuSable Harbor, MI ................ 
5. Bayport Harbor, MI ................ 
6. Big Bay Harbor, MI ................ 
7. Black River, (Port Huron) MI .......... 
8. Black River Harbor, (U.P.) MI ......... 
9. Bolles Harbor, MI ................. 
10. Caseville Harbor, MI ............... 
11. Charlevoix Harbor, MI .............. 
12. Clinton River, MI ................. 
13. Cornucopia Harbor, WI.............. 
14. Detroit River, MI ................. 
15. Duluth-Superior Harbor, MN and WI ..... 
16. Fox River, WI .................. 
17. Frankfort Harbor, MI .............. 
18. Grand Haven Harbor and Grand River, MI. 
19. Grand Marais Harbor, MI ........... 
20. Grand Marais Harbor, MN .......... 
21. Grand Traverse Bay Harbor, MI ....... 
22. Green Bay Harbor, WI ............. 
23. Hammond Bay Harbor, MI .......... 
24. Harbor Beach Harbor, MI ........... 
25. Holland Harbor, MI ............... 
26. The Inland Route, MI .............. 
27. Kenosha Harbor, WI .............. 
28. Kewaunee, WI .................. 
29. Keweenaw Waterway, MI ........... 
30. LaPointe Harbor, WI .............. 
31. Lake St. Clair, MI, Channels in ....... 
2
2
2
2
2
2
2
2
2
2
2
2t 
2,
Page 
21-2 
21-3 
21-3 
21-3 
21-4 
21-4 
21-4 
21-5 
21-5 
21-6 
21-6 
21-7 
21-8 
21-8 
21-9 
21-10 
21-11 
21-11 
21-12 
21-13 
21-13 
21-13 
21-14 
21-15 
21-15 
21-16 
21-16 
21-17 
21-17 
21-18 
21-18 
Navigation (Continued) 
32. Leland Harbor, MI ...... 
33. Lexington Harbor, MI .... 
34. Little Lake Harbor, MI .... 
35. Ludington Harbor, MI .... 
36. Manistee Harbor, MI ..... 
37. Manistique Harbor, MI .... 
38. Manitowoc Harbor, WI .... 
39. Marquette Harbor, MI . . . 
40. Menominee Harbor and River, 
41. Milwaukee Harbor, WI .... 
42. Monroe Harbor, MI ...... 
43. Muskegon Harbor, MI .... 
44. New Buffalo Harbor, MI .. . 
45. Oconto Harbor, WI ...... 
46. Ontonagon Harbor, MI .... 
47. Pensaukee Harbor, WI .... 
48. Pentwater Harbor, MI..... 
49. Port Austin Harbor, MI .... 
50. Port Sanilac Harbor, MI ... 
51. Port Washington Harbor, WI 
52. Port Wing Harbor, WI .... 
53. Presque Isle Harbor, MI . . . 
54. Rouge River, MI ........ 
55. Saginaw River, MI ....... 
56. St. Clair River, MI ...... 
57. St. Joseph Harbor, MI .... 
58. St. Marys River, MI ...... 
59. Saugatuck Harbor and Kalamaz 
60. Sebewaing Harbor, MI .... 
61. Sheboygan Harbor, WI .... 
62. South Haven Harbor, MI . . . 
Page 
......... 21-19 
......... 21-19 
......... 21-20 
......... 21-20 
......... 21-20 
......... 21-21 
. . .... ... 21-21 
...... ... 21-22 
MI and WI . 21-23 
......... 21-23 
......... 21-24 
......... 21-25 
......... 21-25 
......... 21-26 
......... 21-26 
......... 21-27 
......... 21-27 
......... 21-28 
......... 21-28 
......... 21-28 
......... 21-29 
......... 21-29 
......... 21-29 
......... 21-30 
......... 21-31 
......... 21-31 
......... 21-32 
:oo River, MI 21-34 
21-35 
21-35 
21-36 
21-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation (Continued) 
63. Sturgeon Bay & 
Lake Michigan Ship Canal, WI .... 
64. Two Harbors, MN ............. 
65. Two Rivers Harbor, WI ......... 
66. White Lake Harbor, MI ......... 
67. Reconnaissance and Condition Surveys 
68. Other Authorized Navigation Projects . 
69. Navigation Work Under 
Special Authorization ........... 
Page 
... 21-36 
... 21-37 
. . 21-37 
) 1 _3Q 
Beach Erosion Control 
70. Authorized Beach Erosion Control Projects. 21-38 
71. Emergency Shore Protection ......... 21-38 
72. Beach Erosion Work Under 
Special Authorization .............. 21-39 
73. Mitigation of Shore Damages ......... 21-39 
Flood Control 
74. Saginaw River, MI ................ 21-39 
75. Sebewaing, Sebewaing River, MI ....... 21-41 
76. Inspection of Completed 
Flood Control Projects ............. 21-41 
77. Other Authorized Flood Control Projects . . 21-41 
Navigation 
1. ALPENA HARBOR, MI 
Location. At mouth of Thunder Bay River which 
empties into Thunder Bay, Lake Huron. Harbor is 100 
miles southeast of Cheboygan Harbor, MI. River has its 
source in Montmorency and Alpena Counties, MI. (See 
NOAA Nautical Chart 14864.) 
Previous project. For details see page 1957 of Annual 
Report for 1915 and page 1548 of Annual Report for 
1938. 
Existing project. Provides for a bay channel 200 feet 
wide and 25 feet deep from deep water in Thunder Bay to 
a point 300 feet lakeward of the Alpena Light; thence an 
entrance channel 24 feet deep, narrowing to a width of 
100 feet at a point 700 feet upstream from the light; a 
river channel 100 feet wide, 23 feet deep to Second 
Avenue Bridge; thence 18.5 feet deep and 75 feet wide for 
1,600 feet to upper limit of Federal project; a turning 
Flood Control (Continued) 
78. Flood Control Under 
Special Authorization ............. 
79. Surveillance of Northern Boundary Waters 
and International Water Studies ...... 
. 1 JO- 
. . 21-38 General Investigations 
.. 21-38 80. Surveys ..................... 
81. Preconstruction Engineering and Design 
. 21-38 82. Collection and Study of Basic Data .... 
Page 
S21-41 
. 21-42 
S21-46 
S21-46 
S21-47 
Tables 
Table 21-A Cost & Financial Statement ..... 21-48 
Table 21-B Authorizing Legislation ........ 21-67 
Table 21-C Other Authorized 
Navigation Projects ........... 21-80 
Table 21-D Not Applicable ................ 
Table 21-E Other Authorized Flood 
Control Projects ............. 21-81 
Table 21-F Multiple Purpose Projects, including 
Power, St. Marys River, MI: 
Existing Project ............. 21-81 
Table 21-G Deauthorized Projects ......... 21-82 
Table 21-H Features of Existing Project ..... 21-84 
Table 21-I Fox River, WI: Locks & Dams . . . 21-85 
Table 21-J Reconnaissance & Condition Surveys 21-86 
basin at upstream end of project, basin at river mouth 19 
feet deep, trapezoidal in shape, with a maximum width of 
700 feet including the channel width and a maximum 
length of 900 feet along the channel line, including 
removal of existing rubble breakwater; and a breakwater 
about 550 feet long paralleling lakeward side of new 
turning basin. Work authorized by the 1965 River and 
Harbor Act, which consists of the proposed turning basin 
and breakwater reconfiguration, was deauthorized by the 
Water Resources Development Act (WRDA) of 1986; 
Public Law (PL) 99-662, Nov. 17, 1986, 99th Congress, 
Title X. 
Local cooperation. Fully complied with. 
Terminal facilities. Several commercial docks along 
Thunder Bay River used primarily for receipt of coal and 
petroleum products. Also a municipal marina basin about 
0.25 mile southwest of river mouth. Facilities are 
considered adequate for existing commerce. 
21-2 
.
. 
.

DETROIT, MI DISTRICT 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $12,582. Engineering and design for 
maintenance dredging was performed at a cost of $15,825. 
Existing project was completed in 1939. The 
modification of existing project at Alpena Harbor, as 
authorized by the 1965 River and Harbor Act, was 
reclassified into an inactive status May 22, 1969 based on 
an unfavorable benefit-cost ratio. In 1975 the 
modification was recommended and reviewed for 
deauthorization, which was withdrawn by Congressional 
Resolution the same year. Subsequently, the work 
authorized by the 1965 Act was deauthorized by the 
WRDA of 1986. Project features are in good condition. 
Total costs to end of FY for existing project were 
$1,326,696 of which $337,394 was for new work and 
$989,302 for maintenance. 
2. ARCADIA HARBOR, MI 
Location. On east shore of Lake Michigan, 193 miles 
northeasterly from Chicago, IL, and 15 miles northerly 
from Manistee, MI. (See NOAA Nautical Chart 14907). 
Existing project. Provided for maintenance dredging of 
the existing harbor built by private interests, for a period 
of five years. The five years covered by this project were 
the calendar years 1905 to 1909, inclusive. Funds were 
also appropriated and maintenance was performed in 
calendar years 1911, 1912, 1913 and 1915, inclusive. 
There is at present no approved project for the 
improvement of this harbor. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Dock facilities are considered 
adequate for existing recreational traffic. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $26,953. Safety 
maintenance was performed by hired labor at a cost of 
$1,955. A contract was awarded and completed for 
maintenance dredging at a cost of $12,182, removing 
approximately 3,703 cubic yards of shoal material by 
hydraulic dredge. Engineering, design, surveys, real 
estate, supervision and administration cost $22,973. 
Existing project was completed in 1909. Varying depths 
of 5-12 feet exist in the channel at present. Maintenance 
of the harbor is based on providing a 9-foot depth. Piers 
and revetments are in excellent condition. Total cost for 
existing project to end of FY was $4,353,052. 
3. ASHLAND HARBOR, WI 
Location. At head of Chequamegon Bay, on south 
shore of Lake Superior, about 65 miles east of Duluth, 
MN. (See NOAA Nautical Chart 14974.) 
Existing project. A west channel 20 and 21 feet deep 
and an east basin 25 and 27 feet deep, both all protected 
by an 8,000-foot breakwater. For additional details see 
page 1008 of Annual Report for 1965. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. City of Ashland owns 4,150 feet of 
waterfront for future public needs. Wharves for handling 
coal, ore, limestone, logs and pulpwood are served by 
railroads. Facilities are considered adequate for existing 
commerce. Handling of ore and logs has been 
discontinued for the present. 
Operations during fiscal year. Maintenance: 
Condition surveys, real estate activities, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $33,788. 
Work authorized prior to 1960 Act was completed in 
1950. Work authorized by 1960 Act was completed in 
November 1962. Total cost for existing project to end of 
FY was $5,014,265, of which $1,695,645 was for new 
work and $3,318,620 for maintenance. 
4. AUSABLE HARBOR AT AUSABLE 
RIVER (OSCODA), MI 
Location. The AuSable River and village of Oscoda, 
MI, are on the west shore of Lake Huron, 8 miles north 
of AuSable Point, northeast limit of Saginaw Bay. (See 
NOAA Nautical Chart 14863.) 
Previous project. For details see pages 336 and 2453 of 
Annual Report for 1892. 
Existing project. Riprapping outer 200 feet of north 
pier at mouth of AuSable River, dredging an entrance 
21-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
channel 12 feet deep and dredging between piers and 
upstream to State highway bridge 10 feet deep. (See 
Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small timber pile wharves 
used primarily by commercial fishermen and pleasure craft 
operators; also a private marina basin east of Highway 23 
Bridge. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $8,749. An adjustment of 
-$18,144 was made in contract cost for maintenance 
dredging completed last FY. Supervision and 
administration to close out contract cost $532. 
Existing project was completed in 1962. Total cost for 
existing project to the end of FY was $3,033,621, of 
which $209,776 was for new work (includes $16,400 
contributed funds) and $2,823,845 for maintenance. 
5. BAY PORT HARBOR, MI 
Location. On Wild Fowl Bay on east shore of Saginaw 
Bay about 10 miles south of Caseville, MI. (See NOAA 
Nautical Chart No. 14863.) 
Existing project. Provides for a channel 6 feet deep 
and 50 feet wide extending 5,750 feet from 6-foot contour 
in Saginaw Bay to intersection of private service channels 
to be dredged by local interests. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several small wharves used 
primarily by commercial fishermen. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $916. A contract was awarded and 
completed for maintenance dredging, removing 
approximately 27,364 cubic yards of shoal material at a 
cost of $165,491. Construction of dikes for the disposal 
area and removal of approximately 4,957 cubic yards of 
shoal material outside the project limits, a non-federal 
responsibility, was performed at the request of the State of 
Michigan at a cost of $88,906. Engineering, design, real 
estate, supervision and administration of the contract cost 
$55,424. Of the funds expended $97,117 was contributed 
by the State of Michigan. 
Existing project was completed in 1967. Total cost for 
existing project to end of FY was $639,505, of which 
$93,597 was for new work and $545,908 for maintenance 
(which includes $120,286 contributed funds). 
6. BIG BAY HARBOR, MI 
Location. On south shore of Lake Superior 33 miles 
northwesterly from Marquette, MI, and 38 miles easterly 
from Portage entry to Keweenaw Waterway. (See NOAA 
Nautical Chart 14964.) 
Existing project. Provides for two converging piers 
extending from shore, an entrance channel between piers 
and rectangular harbor basin. Project depths are 12 feet 
in entrance channel and 10 feet in harbor basin. For 
details see page 1009 of Annual Report for 1965 and page 
1261 of Annual Report for 1962. (See Table 21-B for 
authorizing legislation.) 
Local Cooperation. Fully complied with. 
Terminal facilities. A State-owned launching ramp and 
dock for small craft. 
Operations during fiscal year. Maintenance: 
Condition surveys, miscellaneous inspections and reports 
were performed by Government forces and contract at a 
cost of $4,438. Supervision and administration in 
connection with close-out of maintenance dredging 
contract completed last FY cost $665. 
Project was completed in June 1961 except for 
protection at inner end of east breakwater, completed in 
November 1961. Total cost to end of FY was $1,757,093 
of which $390,433 was for new work and $1,366,660 for 
maintenance. 
7. BLACK RIVER (PORT HURON), MI 
Location. This river has its source in the northern part 
of Sanilac County, MI, is about 60 miles long, and flows 
21-4

DETROIT, MI DISTRICT 
in a southeasterly direction into the St. Clair River. (See 
NOAA Nautical chart 14852.) 
Previous project. For details see page 1441 of Annual 
Report for 1916, and page 1554 of Annual Report for 
1938. 
Existing project. Provides for a channel 20 feet deep 
from deep water in St. Clair River to the Grand Trunk 
Western Railroad Bridge, 160 feet wide at the mouth, 
decreasing to 100 feet, about 800 feet from the mouth, 
thence 100 feet wide for 2,600 feet, decreasing to 75 feet 
for a distance of 4,800 feet; widening two bends to 100 
feet, one at the foot of 12th Street, and the other below 
the Grand Trunk Western Railroad Bridge; for a settling 
basin 75 feet wide and 20 feet deep, beginning at the 
Grand Trunk Western Railroad Bridge in Port Huron and 
extending upstream a distance of about 2,300 feet; and 
then for a distance of 2.6 miles as a 100-foot wide river 
channel, 8 feet deep to the 1-94 bridge where it decreases 
to 6 feet deep and continues to the vicinity of the Black 
River Drainage Canal with suitable widening where 
required at bends in the channel. The project modification 
authorized by the Act of August 30, 1935, is considered 
to be inactive and is excluded from the foregoing cost for 
new work. The cost of this modification was last revised 
in 1954 and was estimated to be $194,000 exclusive of 
$194,000 to be contributed by local interests. (See Table 
21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are docks on both sides of 
Black River, near its mouth, and between these docks and 
the upper limit of improvement there are 5 other docks 
varying in length from 100 to 500 feet. All docks are 
privately owned and are restricted to the use of the 
owners. The facilities are considered adequate for existing 
commerce. Public recreational boating facilities 
constructed by the State and local agencies are available, 
as are privately owned and operated marinas. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $11,755. Removal of obstructions by 
the U. S. Derrickbarge HURON was performed at a cost 
of $7,964. Supervision and administration of the project 
cost $1,582. An adjustment of -$9,660 was assessed the 
contractor that performed maintenance dredging last FY. 
All work, except that authorized by Act of August 30, 
1935, and the latest modification, has been completed. 
Total cost for existing project to end of FY was 
$2,149,149, of which $830,165 was for new work 
(includes $349,921 contributed funds) and $1,318,984 for 
maintenance. 
8. BLACK RIVER HARBOR (UPPER 
PENINSULA), MI 
Location. At mouth of Black River on south shore of 
Lake Superior 39 miles westerly from Ontonagon, MI, 
and 47 miles easterly from Ashland, WI. (See NOAA 
Nautical Chart 14965.) 
Existing project. Two converging breakwaters, an 
entrance channel between breakwaters, an inner channel, 
and an irregular harbor basin. For additional details see 
page 1092 of Annual Report for 1966. Project depths are 
12 feet in the approach channel and 8 feet in the river 
channel and basin. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Full complied with. Local interests 
furnished easements on 0.85 acre of land. 
Terminal facilities. Wharves constructed on both sides 
of river. Wharf on east bank has frontage of 400 feet; on 
west bank, a frontage of 750 feet. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, monitoring, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $7,243. A maintenance 
dredging contract was awarded and completed this FY, 
removing approximately 7,295 cubic yards of shoal 
material at a cost of $37,829. Engineering, design, 
surveys, supervision and administration cost $44,326. 
Project was completed in June 1958. Total costs for 
existing project to end of FY was $1,185,604 of which 
$383,350 was for new work and $802,254 was for 
maintenance. 
9. BOLLES HARBOR, MI 
Location. On west shore of Lake Erie at mouth of La 
Plaisance Creek 7 miles southwest of Monroe, MI. (See 
NOAA Nautical Chart 14846.) 
21-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. Provides for an entrance channel in 
Lake Erie, 8 feet deep and 80 feet wide from deep water 
to a point opposite the outer end of existing jetty, thence 
widening to 100 feet at creek mouth; an access channel in 
La Plaisance Creek, 6 feet deep and 100 feet wide at the 
mouth widening to 120 feet and extending to the first 
bend, thence narrowing to 50 feet wide and continuing at 
that width to the La Plaisance Road bridge; a steel sheet 
pile revetment, about 200 feet long, located along 
Michigan State Conservation Department property on west 
side of channel at creek mouth. Project also provides for 
inclusion of existing 400-foot long steel sheet pile jetty 
constructed by Michigan State Waterways Commission at 
the mouth of La Plaisance Creek. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. The Monroe Boat Club and three 
marinas provide facilities adequate for existing recreational 
boat traffic. There is also a public launching ramp and 
parking area at the Conservation Department fishing site 
at creek mouth. 
Operations during fiscal year. Maintenance; 
Condition surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$16,657. An adjustment of 2,218 cubic yards of shoal 
material and -$19,847 was made in cost of maintenance 
dredging contract completed last FY. Engineering, 
design, surveys, supervision and administration cost 
$10,751. 
The existing project was completed in 1970. Total cost 
for existing project to the end of FY was $3,601,434, of 
which $426,413 was for new work (includes $255,000 
contributed funds) and $3,175,021 for maintenance. 
10. CASEVILLE HARBOR, MI 
Location. At mouth of Pigeon River on south shore of 
Saginaw Bay about 17 miles southwest of Port Austin, 
MI. (See NOAA Nautical Chart 14860.) 
Existing project. A small craft harbor of refuge 
consisting of a breakwater protected channel extending 
from the 10-foot contour in Saginaw Bay into Pigeon 
River. Project depths are 10 and 8 feet. For additional 
details see page 1320 of Annual Report for 1963. 
Widening river channel from 50 to 60 feet for about 1,000 
feet, with widening to 80 feet in upper 300-foot reach, is 
considered inactive. Estimated (1963) cost of this portion 
of project is $30,000 (See Table 21-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Complete public boating facilities 
constructed by State and local agencies are available in 
addition to privately owned and operated marinas. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $4,333. An adjustment of -$8,209 was 
made in contract cost for maintenance dredging completed 
last FY. Cost to close out the contract, surveys, 
supervision and administration were $9,592. 
The existing project was completed in 1964 except for 
the inactive portion of the project. Total cost to end of 
FY was $1,919,671, of which $587,314 was for new 
work (including $293,657 contributed funds) and 
$1,332,357 for maintenance. 
11. CHARLEVOIX HARBOR, MI 
Location. On east shore of Lake Michigan, 276 miles 
northeasterly from Chicago, IL, and 75 miles northerly 
from Frankfort, MI. (See NOAA Nautical Chart 14942.) 
Existing project. A channel 24 feet deep in Lake 
Michigan and a river channel 23 feet deep in the lower 
and upper channels connecting Lake Michigan with Lake 
Charlevoix via Round Lake. The channels are protected 
where needed by piers and revetments. For additional 
details see page 1476 of Annual Report for 1962. (See 
Table 21-B for authorizing legislation.) Section 25 of the 
WRDA of 1988 provides authorization pertaining to the 
South Pier to Charlevoix Harbor. It states, "The 
Secretary shall take such action as may be necessary to 
restore recreational uses established prior to May 1, 1988, 
or provide comparable recreation uses at the South Pier to 
Charlevoix Harbor project, Charlevoix, Michigan in order 
to mitigate any adverse impact on recreational uses 
resulting from reconstruction of the South Pier..." 
Local cooperation. None required except the latest 
project modification is subject to the following: Provide 
without cost to the United States, all lands, easements, and 
rights-of-ways required for construction and subsequent 
maintenance of the modified project upon the request of 
21-6

DETROIT, MI DISTRICT 
the Chief of Engineers, including suitable areas 
determined by the Chief of Engineers to be required in the 
general public interest for initial and subsequent disposal 
of excavated materials and any necessary retaining dikes, 
bulkheads, and embankments, therefor, or the cost of such 
retaining works; hold and save the United States free from 
damages due to the constructing and maintenance of the 
modified project, except for damages due to the fault or 
negligence of the United States or its contractors; provide 
and maintain without cost to the United States depths in 
berthing areas and local access channels serving the 
terminal commensurate with the depths provided in the 
related project areas; accomplish, without cost to the 
United States, such alterations of submarine utility 
crossing as are required by the modified project; establish 
regulations prohibiting discharge of pollutants into the 
waters of the harbor by users thereof which regulations 
shall be in accordance with applicable laws or regulations 
of Federal, State and local authorities responsible for 
pollution prevention and control; if acquiring lands, 
easements and rights-of-ways for construction of the 
project, local interests will comply with the applicable 
provisions of the Uniform Relocation Assistance and Real 
Property Acquisition Policies Act of 1971; PL 91-646, 
approved January 2, 1971; contribute all costs in excess of 
$1,000,000 should the total cost of construction of the 
general navigation facilities exceed that amount, in 
accordance with provisions of Section 107 of the 1960 
River and Harbor Act, as amended. The total first cost of 
construction (1975) is estimated at $625,000. 
Terminal facilities. Several small landing places in 
Round Lake at Charlevoix for handling fish and 
miscellaneous commodities, a wharf for petroleum 
products at west end of Lake Charlevoix, and coal 
wharves at Advance and Boyne City. Charlevoix, Boyne 
City, and East Jordan provide public docks for small craft. 
Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed at 
a cost of $57,110. The U.S. Cranebarge MANITOWOC 
performed removal of obstructions along the entrance 
channel at a cost of $18,679. Location and removal of 
obstructions was performed by contract at a cost of 
$7,966. Repairs to safety features were performed by 
hired labor at a cost of $6,928. Engineering and design 
for construction of a recreational bridge was completed at 
a cost of $76,033. A contract was awarded and completed 
at a cost of $162,919. Engineering and design was 
initiated on repair of the Pile Cluster, Sections I, J, and B, 
at a cost of $33,932. Surveys, real estate, engineering 
and design during construction, supervision and 
administration cost $31,172. 
Existing project was completed in 1939 except for the 
latest modification. Total cost for existing project to the 
end of FY was $9,955,100, of which $180,623 was for 
new work, $8,645,081 for maintenance (Bank Stabilization 
$46,352) and $1,129,396 for rehabilitation. 
12. CLINTON RIVER, MI 
Location. Has its sources in Oakland County, MI, 
flows easterly about 60 miles and empties into Anchor Bay 
in northwestern part of Lake St. Clair. (See NOAA 
Nautical Chart 14850.) 
Previous project. For details see page 1958 of Annual 
Report for 1915, and page 1556 of Annual Report for 
1938. 
Existing project. An entrance channel in Anchor Bay 
8 feet deep, 300 feet wide at 8-foot depth contour in the 
bay, gradually decreasing to 50 feet wide at about 1,000 
feet upstream from mouth of Clinton River, a length of 
about 4,600 feet; a channel 8 feet deep and 50 feet wide 
in the river about 38,700 feet long from entrance channel 
upstream to Mt. Clemens at Cass Avenue; closing old 
channel and making a cutoff at Shoemakers Bend; closing 
Catfish Channel; construction of revetments as needed in 
the river; and a harbor basin, 5 feet deep and 11 acres in 
area at entrance along bay channel, protected by 
breakwaters on north and south sides. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. River is used exclusively by 
recreational craft. There are numerous public and private 
wharves along the river below the city. They are 
considered adequate. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces and contract at a cost of $103,108. The 
maintenance dredging contract awarded last FY is 
approximately 84% complete at a cost of $763,113, 
removing approximately 74,674 cubic yards of shoal 
material. Maintenance of the disposal area was performed 
21-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
by hired labor at a cost of $2,543. Engineering, design, 
surveys, real estate, supervision and administration cost 
$249,583. 
Existing project was completed in 1966. Total cost for 
existing project to end of FY was $7,312,965, of which 
$549,798 was for new work (includes $289,752 
contributed funds) and $6,763,167 for maintenance. 
13. CORNUCOPIA HARBOR, WI 
Location. At mouth of Siskiwit River on south shore of 
Lake Superior, 49 miles east from Duluth, MN. (See 
NOAA Nautical Chart 14973.) 
Existing project. Provides for an entrance channel 
between piers; an irregular-shaped turning basin; two 
inner channels, and reconstruction and Federal 
maintenance of deflection dike and entrance piers 
constructed by local interests. Project depths are 10 feet 
between piers and 8 feet in turning basin and inner 
channels. For additional details see page 1010 of Annual 
Report for 1965. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. About 1,000 linear feet of privately 
owned docking space is available. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $12,457. A maintenance dredging 
contract was awarded and completed at a cost of $38,015, 
removing approximately 7,848 cubic yards of material. 
Engineering, design, surveys, supervision and 
administration cost $12,724. 
Work authorized by earlier Act was completed in 1939. 
Work authorized in 1954 was completed in 1963. Total 
costs to end of FY were $1,445,382, of which $462,653 
was for new work and $982,729 for maintenance. 
14. DETROIT RIVER, MI 
Location. One of the Great Lakes connecting channels, 
31 miles long, flows south from Lake St. Clair to Lake 
Erie. (See NOAA Nautical Chart 14848.) 
Previous project. For details see page 1958 of Annual 
Report for 1915, and page 1541 of Annual Report for 
1938. 
Existing project. Improving Detroit River main 
channels to provide 25.5-foot draft navigation; improving 
certain auxiliary and side channels; and construction of 
various water level and crosscurrent control structures. 
Details are in accompanying Table 21-H. Project depths 
are referred to local low water datum planes which 
correspond to low water datums for Lakes St. Clair and 
Erie, 572.3 and 569.2 feet above mean water level at 
Rimouski, Quebec, IGLD 1985. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. No local 
cooperation is required for modifications authorized by 
Acts of July 1946 and March 1956. The uncompleted 
portion of the project authorized by the 1946 and 1956 R 
& H Acts, construction of the Compensating Works, with 
the uncompleted portion of the Trenton Channel 
modification approved August 13, 1968, were 
deauthorized December 31, 1989, in accordance with 
Section 1001 of the WRDA of 1986 (PL 99-662). 
Terminal facilities. Numerous commercial installations 
used for handling coal, iron ore, limestone, steel products, 
petroleum products, and other items such as overseas 
general cargo. Detail on actual port and harbor facilities 
is in Port Series No. 45 (revised 1984) prepared and 
published by the Water Resources Support Center. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, Hi-Fix surveys, environmental studies, 
support of water control center, miscellaneous inspections 
and reports were performed by Government forces and 
contract at a cost of $1,461,709. Underground storage 
tanks removed by contract cost $47,523. Location and 
removal of obstructions performed by the U. S. 
Derrickbarge HURON and the U.S. Cranebarge VELER 
cost $1,750,856. Maintenance of disposal area was 
performed by hired labor at a cost of $155,892. A 
contract was awarded for dredging the turning basin at 
Pointe Mouillee channel in the amount of $756,799. The 
contract was 4% complete at the end of FY, removing 
4,113 cubic yards of material at a cost of $28,789. 
Another contract was awarded and completed this FY for 
maintenance dredging East Outer and Lower Livingstone 
channels removing approximately 471,934 cubic yards of 
material at a cost of $2,181,999. Engineering, design, 
21-8

DETROIT, MI DISTRICT 
real estate, surveys, supervision and administration cost 
$313,254. 
Latest modification of connecting channels project in the 
Detroit River is complete except for compensating works. 
Pertinent data concerning channels covered by project at 
end of FY are set forth in Table 21-H. Total cost for 
existing project to end of FY was $217,480,163, of which 
$76,877,357 was for new work ($75,346,669 regular 
funds and $1,530,688 Public Works Funds) and 
$140,602,806 (includes $361,235 Section 150 contributed 
funds) for maintenance. 
15. DULUTH-SUPERIOR HARBOR, MN 
ANDW 
Location. At extreme western end of Lake Superior. 
Cities of Duluth, MN, and Superior, WI, are on north and 
south sides, respectively. (See NOAA Nautical Chart 
14975.) 
Previous projects. See page 1246 of Annual Report for 
1962. 
Existing project. Provides for rebuilding canal piers at 
Duluth entry, replacement or construction of piers and 
breakwater at Superior entry and dredging approaches and 
channels within harbor, St. Louis Bay, and St. Louis 
River. Channels vary in depth from 32 to 28 feet in 
entrances, are 27 feet deep in iron-ore route channels, and 
are from 20 to 23 feet deep in inner channels. (See Table 
21-B for authorizing legislation.) 
For details of authorized channel dimensions and 
dimensions of structures, see pages 1246 and 1247 of 
Annual Report for 1962 and page 1011 of Annual Report 
for 1965. Portion of project for deepening Twenty-first 
Avenue West channel was deauthorized December 31, 
1989, in accordance with Section 1001 of the WRDA of 
1986 (PL 99-662). 
The WRDA of 1986 authorized modifications to the 
project to deepen the western portions of North and South 
Channels, the entire Upper Channel and the Minnesota 
Channel to 27 feet LWD; widen the Cross Channel to 
provide a minimum turning basin of 1,500 feet; widen the 
bend at the Arrowhead Bascule Bridge to 600 feet; and 
construct an upland confined disposal facility. Estimated 
cost (Oct. 90) is $15,200,000; which includes $8,400,000 
Federal and $6,800,000 non-Federal. 
Local cooperation. Fully complied with for completed 
portion of project. Local cooperation items for the newly 
authorized project in the WRDA of 1986 (PL 99-662), are 
as described in House Document 150, 86th Congress, 1st 
Session and also includes, as a result of PL 99-662, 
construction cost sharing as follows: 
a. Contribute in cash 25 percent of the total cost of 
construction of general navigation facilities, exclusive of 
aids to navigation, a contribution presently estimated at 
$2,801,000. The estimated cash contribution of 
$2,801,000 to be paid in lump sum prior to initiation of 
construction, or in annual installments during the 
construction period at a rate proportionate to the proposed 
or scheduled expenditure of Federal funds as required by 
the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final 
apportionment of cost to be made after actual costs have 
been determined; and 
b. Repay, with interest, over a period of up to 30 years 
following project completion, 10 percent of the total cost 
of construction of general navigation facilities, an amount 
presently estimated at $1,520,000. The Secretary of the 
Army may count against all or part of the 10 percent 
repayment, the amount of the local contribution for lands, 
easements, rights-of-ways, dredged/demolition material 
disposal sites and relocations. In no case are these costs 
to count against the cash payment during construction, and 
in no case would the amount waived exceed 10 percent of 
project cost. 
Terminal facilities. There are 113 docks or terminals 
including some 54 major ones; all but one privately 
owned. Facilities for handling iron ore, coal, limestone, 
petroleum, steel and scrap iron, cement, general cargo, 
and grain are believed adequate for most existing 
commerce. 
Operations during fiscal year. New work: 
Construction General funds in the amount of $69,902 were 
utilized in FY 92 for the efforts to resolve the singlebeneficiary 
and North vs. South Channel issues. The 
authorized project involves deepening approximately four 
miles of navigation channels (North, South, Upper and 
Minnesota Channels) in the St. Louis River to 27 feet, 
widening the Cross Channel to a minimum of 1,500 feet, 
widening the bend at the site of the old Arrowhead Bridge 
a maximum of 500 feet, constructing a 130-acre upland 
disposal site in the Superior Municipal Forest, and 
disposal of the Arrowhead material in the Erie Pier CDF 
21-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
with disposal of the remainder of the dredged material in 
the Superior Municipal Forest site. Total project cost is 
estimated at $15,374,000, of which $8,585,500 and 
$6,788,500 are the Federal and non-Federal shares, 
respectively. Rehabilitation: Supervision and 
administration to close-out FY 85 contract for the 
rehabilitation of North and South Piers, Sections O, N-i, 
N and M cost $8,235. Maintenance: Condition and 
structure surveys, environmental studies, support of water 
control center, miscellaneous inspections and reports were 
performed by Government forces and contract at a cost of 
$303,572. Operation and maintenance of the Museum 
was performed by Government forces at a cost of 
$412,131. Operation and maintenance of service facilities 
and pier was performed at a cost of $174,988. Repairs to 
Duluth and Superior entry breakwaters and seawalls were 
performed by the U. S. Derrickbarge COLEMAN at a 
cost of $480,829. Safety maintenance was performed by 
hired labor at a cost of $61,847. Maintenance of the 
disposal area was performed by hired labor at a cost of 
$605. Engineering and design for a contract to be 
awarded next FY for the expansion of the existing 
confined disposal facility cost $61,219. An adjustment of 
-$8,005 was made in contract costs for maintenance 
dredging of clean material completed last FY. The 
contract awarded last FY for maintenance dredging of 
contaminated material was completed this FY at a cost of 
$1,046,285, removing 149,202 cubic yards of material. 
A contract was awarded this FY for maintenance dredging 
of contaminated material in the amount of $534,575. The 
contractor was 75% complete at end of FY at a cost of 
$399,999 removing 42,636 cubic yards of shoal material. 
Engineering, design, surveys, supervision and 
administration cost $293,989. 
Work authorized prior to 1960 Act was completed in 
June 1956. Under the 1960 Act, work on the outer 
harbor, included in House Document 150, was completed 
in June 1965. Work in the inner harbor, included in 
House Document 196, started in May 1963, was 
completed in November 1968 except for 21st Avenue 
West channel portion which was deauthorized December 
31, 1989. 
The United States owns 34.90 acres of land in fee in 
Minnesota and Wisconsin of which 2.15 acres are used for 
a vessel yard. Total cost for existing project to end of FY 
was $82,812,602, of which $16,179,160 was for new 
work, $55,078,081 for maintenance, and $11,555,361 for 
rehabilitation. 
16. FOX RIVER, WI 
Location. Rises in Columbia County, WI, and flows 
about 176 miles northerly into Green Bay. Wolf River, 
physically a main river but by designation a tributary of 
Fox River, rises in central part of Fort County, WI and 
flows southerly. (See NOAA Nautical Chart 14916 for 
Lake Winnebago and lower Fox River.) 
Previous projects. See page 1368 of Annual Report for 
1962. 
Existing project. Deepening and widening channel of 
Fox River from DePere 7 miles above mouth to 
confluence of Wolf River, a total length of 59 miles, to 6 
feet, with 9.6 feet in rock cut below DePere lock and 7 
feet in other rock cuts on lower river below Menasha 
lock; construction and reconstruction of 19 locks and 9 
dams; a concrete retaining wall at Kaukauna; construction 
and maintenance of harbors having depths of 6 feet on 
Lake Winnebago; widening Neenah Channel to 100 feet, 
with a 6-foot depth for about 1 mile; and dredging, 
snagging, and otherwise improving Wolf River 47 miles 
from its mouth to New London, depth to be 4 feet. 
Cost of completed portion of project is $513, 424 for the 
lower river exclusive of previous projects. The 
uncompleted portion of the project authorized by the River 
and Harbor Act of 1925, was deauthorized December 31, 
1989, in accordance with Section 1001 of the WRDA of 
1986 (PL 99-662). (See Table 21-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. Wharf and landing facilities are, in 
general, adequate for existing needs. (See Table 21-1 on 
locks and dams, Fox River, WI.) 
Operations during fiscal year. Maintenance: 
Condition surveys, miscellaneous inspections and reports, 
safety training and plans for flood emergencies were 
performed at a cost of $72,340. Federal canal banks at 
various locations were repaired at a cost of $112,032. An 
archaeological study for disposal was undertaken, totaling 
$79,991. Real Estate inspections and outgranting were 
performed at a cost of $61,241. The operation and 
maintenance of nine (9) dams and ten (10) overflow weirs 
and caretaker status maintenance of seventeen (17) locks 
and two (2) guard locks totaled $804,205. Fox River 
O.S.H.A. Program and major miscellaneous items of 
21-10

DETROIT, MI DISTRICT 
supply totaled $5,044. Water control studies, monitoring 
and regulation of water levels were performed at a cost of 
$287,351. Supervision and administration costs were 
$258,800. 
Existing project is complete except for the inactive 
portion. Nineteen original locks and nine original dams 
have been rebuilt. (See Table 21-I for year of completion 
of each). Structures and dredging in pools have increased 
original depths generally about 2 feet. Work remaining 
to complete project consists of dredging in upper portion 
of Wolf River, and rock removal and deepening of 
Neenah Channel on lower Fox River, which are no longer 
considered necessary. Existing locks and dams are 
generally in fair to good condition. Total cost for existing 
project to end of FY was $49,631,430, of which 
$3,753,334 was for new work and $45,878,096 for 
operation and maintenance. Funds in the amount of 
$3,706,187 were expended between July 5, 1884, and 
June 30, 1935, on operation and care of works of 
improvement under provisions of permanent indefinite 
appropriation for such purposes. 
17. FRANKFORT HARBOR, MI 
Location. On east shore of Lake Michigan, 204 miles 
northeasterly from Chicago, IL, and 28 miles northerly 
from Manistee, MI. (See NOAA Nautical Chart 14907.) 
Existing project. Provides for constructing an exterior 
basin in Lake Michigan formed by two breakwaters, 450 
feet apart at the outer ends, diverging at an angle of about 
90 degrees, the main arm and shore connection on north 
breakwater are 972 and 1,000 feet long, respectively, and 
the main arm and shore connection of south breakwater 
1,188 and 1,400 feet long, respectively; for removing 801 
feet of north and 1,172 feet of south pier; dredging basin 
20 feet deep and 800 feet wide at entrance, decreasing 
toward new pier heads to 600 feet wide, dredging 
approach and entrance channel through outer basin to a 
depth of 24 feet from deep water in Lake Michigan to a 
point 500 feet landward of opening between breakwaters, 
over the entire width outside the breakwaters; thence to 
maximum width of 500 feet inside the breakwaters and to 
23 feet deep through inner portion of outer basin to outer 
end of north pier, over widths decreasing from 500 to 160 
feet; and thence to 22 feet deep between the piers to the 
inner basin in Lake Betsie; dredging an 18-foot deep 
interior basin in Lake Betsie from within 50 feet of 
existing structures on the west and extending eastward 
about 1,550 feet to easterly boundary and from within 50 
feet of existing structures on the north and extending 
southward 800 feet to the southerly boundary; dredging a 
recreational craft anchorage area 10 feet deep and 300 feet 
wide, extending 600 feet eastward of the east limit of the 
interior basin, with its north side in line with the north 
limit of the basin. Breakwaters and shore connections are 
built of concrete caissons and piling capped with concrete. 
Inner piers and revetments are built of stonefilled timber 
cribs and piling, all capped with concrete, except for 476 
feet of south revetment which consists of steel sheet 
piling. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car ferry slips on south shore 
and several docks along north shore of Lake Betsie. The 
City and State provide a recreational docking facility on 
north side of Lake Betsie which is open to all on equal 
terms. There is also a marine railway capable of handling 
small craft. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, miscellaneous inspections 
and reports were performed by Government forces and 
contract at a cost of $56,780. Safety maintenance was 
performed by hired labor at a cost of $352. Repairs to the 
North and South Breakwater, Sections A, B, and C, were 
performed using the U. S. Cranebarge MANITOWOC at 
a cost of $196,695. Engineering and design was initiated 
on repair of the South connector, Sections F, G, and H at 
a cost of $95,333. Supervision and administration cost 
$2,962. 
Existing project was completed in 1939, with exception 
of the latest modification which was completed in 1969. 
Navigation structures are in good condition and 
programmed for major repair on an as needed basis. For 
additional details on completion of existing project see 
page 1474 of Annual Report for 1962. Total cost for 
existing project to end of FY was $10,693,971, of which 
$1,955,159 (includes $31,709 contributed funds) was for 
new work, $8,464,036 for maintenance, and $274,776 for 
rehabilitation. 
18. GRAND HAVEN HARBOR AND 
GRAND RIVER, MI 
Location. Harbor is on east shore of Lake Michigan, 
108 miles northeasterly from Chicago, IL, and 23 miles 
northerly from Holland, MI. River rises in Jackson 
21-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
County, MI, and flows 260 miles westerly into Lake 
Michigan. (See NOAA Nautical Chart 14933, and 
Geological Survey Grand Rapids quadrangle.) 
Previous project. For details see page 1949 of Annual 
Report for 1915, and page 1481 of Annual Report for 
1938. 
Existing project. An entrance channel protected by 
parallel piers and revetments at mouth of Grand River, a 
deep draft channel in river extending to Spring Lake, a 
turning basin, and a shallow draft channel in river 
extending 14.5 miles upstream to Bass River. Project 
depths are 23 feet in entrance channel, 21 feet in river to 
turning basin, 18 feet in turning basin and channel to 
Spring Lake, and 8 feet in upper Grand River channel. 
For additional details see page 1461 of Annual Report for 
1962. Dredging on northerly side of inner channel is 
considered inactive. Estimated cost of this portion (1954) 
is $38,600. The WRDA of 1986 authorized modifications 
to deepen the harbor entrance and river channels to 29 and 
27 feet, respectively; and provides for a new and larger 
turning basin. Estimated cost (Oct 90) is $20,400,000, 
which includes $11,754,000 Federal and $8,646,000 non- 
Federal. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed 
portions of project. Local cooperation items for the newly 
authorized project in the WRDA of 1986 (PL 99-662), are 
as described in House Document 661, 76th Congress, 3d 
Session, and also includes, as a result of PL 99-662, 
construction cost sharing requirements as follows: 
a. Contribute in cash 25 percent of the total cost of 
construction of general navigation facilities, exclusive of 
aids to navigation, a contribution presently estimated at 
$4,246,000. The estimated cash contribution of 
$4,246,000 to be paid in lump sum, prior to initiation of 
construction, or in annual installments during the 
construction period at a rate proportionate to the proposed 
or scheduled expenditure of Federal funds as required by 
the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final 
apportionment of cost to be made after actual costs have 
been determined; and 
b. Repay, with interest, over a period of up to 30 years 
following project completion, 10 percent of the total cost 
of construction of general navigation facilities, an amount 
presently estimated at $2,040,000. The Secretary of the 
Army may count against all or part of the 10 percent 
repayment, the amount of the local contribution of lands, 
easements, rights-of-ways, dredged/demolition material 
disposal sites and relocations. In no case are these costs 
to count against the cash payment during construction, and 
in no case would the amount waived exceed 10 percent of 
project cost. 
Terminal facilities. Several wharves exist for handling 
coal, limestone, sand and gravel, petroleum products, fish, 
and miscellaneous commodities. There is also a car ferry 
slip which is inactive. The State and local agencies 
provide recreational boating facilities which are open to all 
on equal terms. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $417,601. 
Safety maintenance was performed by hired labor at a cost 
of $7,133. Maintenance of the disposal area by hired 
labor cost $2,528. A contract was awarded and completed 
this FY for maintenance dredging the outer harbor, 
removing 57,018 cubic yards of shoal material at a cost of 
$306,587. This contract was also for Section 111 beach 
nourishment. Another contract was awarded for 
maintenance dredging contaminated material and dike 
construction in the amount of $360,640. The contract was 
27% complete at the end of FY at a cost of $98,799. 
Engineering, design, real estate, surveys, supervision and 
administration cost $163,493. Monitoring in connection 
with Section 111 of PL 90-483 was performed at a cost of 
$26,271. Beach nourishment in conjunction with above 
maintenance dredging contract cost $54,104. Engineering, 
design, and supervision and administration for Section 111 
cost $1,750. 
Existing project was substantially completed in 1949. 
For additional details on completion of existing project see 
page 1463 of Annual Report for 1982. Structures are 
generally in good condition; repairs are made on an as 
needed basis. Total cost for existing project to end of FY 
was $30,088,142, of which $1,458,469 was for new 
work, $27,816,060 for maintenance (includes $15,585 
contributed funds), and $813,613 for rehabilitation. 
19. GRAND MARAIS HARBOR, MI 
Location. On south shore of Lake Superior, 93 miles 
west of Sault Ste. Marie, MI. (See NOAA Nautical Chart 
14962.) 
21-12

DETROIT, MI DISTRICT 
Existing project. Provides for a channel protected by 
parallel piers and for closing natural entrance channel with 
a pile dike. Project depths are 18 feet between piers and 
20 feet in lake approach. For additional details see page 
1449 of Annual report for 1962. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small piers, a Coast Guard 
Station, and a small boat pier and launching ramp built by 
the State of Michigan provide facilities adequate for 
present traffic. 
Operations during fiscal year. Maintenance: 
Condition surveys and miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$5,293. Completion of extensive repairs to West 
Breakwater (outer end) and Section B of the East Pier 
performed by the U.S. Derrickbarge COLEMAN cost 
$1,137. 
Existing project is complete except for widening a 
portion of channel from 250 to 300 feet. Project now 
being maintained to 19 and 15 feet below I.G.L.D., in 
lieu of 20 and 18 feet, which is adequate for current 
usage. Total cost for existing project to end of FY was 
$3,619,271, of which $1,055,871 was for new work and 
$2,563,400 for maintenance. 
20. GRAND MARAIS HARBOR, MN 
Location. On north shore of Lake Superior, 106 miles 
northeasterly from Duluth, MN. (See NOAA Nautical 
Chart 14967.) 
Existing project. Provides breakwater piers to narrow 
the entrance; concrete seawalls across ledge at southeast 
corner of harbor; an anchorage area and a small-boat 
basin protected by a rubblemound breakwater. Project 
depths are 16 feet in anchorage area increasing to 20 feet 
near entrance and 8 feet in small-boat basin. For 
additional details see page 1014 of Annual Report for 
1965. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two inactive pulpwood wharves 
and several fish wharves, all privately owned. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys were performed by Government forces 
at a cost of $24,385. Repairs to the West Breakwater 
Section D were performed by the U. S. Derrickbarge 
COLEMAN at a cost of $175,193. Supervision and 
administration cost $4,540. 
Existing project is complete. Total costs for existing 
project to end of FY was $3,877,895, of which $450,972 
was for new work, $2,196,923 for maintenance, and 
$1,230,000 for rehabilitation. 
21. GRAND TRAVERSE BAY HARBOR, 
MI 
Location. At mouth of Traverse River on eastern shore 
of Keweenaw Peninsula about 20 miles northeasterly from 
Portage entry to Keweenaw Waterway. (See. NOAA 
Nautical Chart 14964.) 
Existing project. Provides two parallel piers, an 
entrance channel between piers and a harbor basin. 
Project depths are 12 feet between piers and 10 feet in 
basin. Project area extended 200 feet upstream in 1966. 
For additional details see page 1015 of Annual Report for 
1965. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
interests furnished easements on 5.1 acres of land. 
Local 
Terminal facilities. Several privately owned fishing 
wharves. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $2,560. 
Existing project was completed in 1950 except for 
extension of north pier completed in 1964. Steel cells and 
piers are in good condition. Total cost of existing project 
to end of FY was $2,154,362, of which $266,037 was for 
new work and $1,888,325 for maintenance. 
22. GREEN BAY HARBOR, WI 
Location. At mouth of Fox River, at head of Green 
Bay, about 180 miles from Milwaukee, WI, via Sturgeon 
Bay Canal, and about 49 miles southwest of Menominee 
Harbor, MI, and WI. (See NOAA Nautical Chart 14918.) 
21-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Previous projects. See page 1366 of Annual Report for 
1962. 
Existing project. See Chicago District 1979 Annual 
Report, Table 30-C, p. 30-30. 
For more detailed description of project see page 1216 
of Annual Report for 1963. 
Cost of completed portion of project is $9,335,000 
Federal, and non-Federal cost is $490,000 including 
$100,000 contributed funds. Local interests requested that 
the inactive portion of the 1962 River and Harbor Act, 
consisting of dredging the reach from 150 feet 
downstream of the C. & N.W. Railway Bridge to 1,700 
feet upstream of this bridge, be reactivated and the 
authorization modified to include deepening the adjacent 
turning basin and modifying the Chicago & Northwestern 
Railway Bridge to provide increased horizontal clearance. 
Estimated cost of this portion (1990) is $6,130,000; 
$4,030,000 Federal and $2,100,000 non-Federal which 
includes $1,970,000 local contribution. Section 601c of 
the WRDA of 1986 authorized deepening the Fox River 
Channel, Green Bay, WI, to 27 feet. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with for existing 
project. 
Terminal facilities. There are 16 wharves for handling 
coal, petroleum products, cement, limestone, general 
overseas cargo and miscellaneous commodities. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $400,457. 
Maintenance of the disposal area was performed by hired 
labor at a cost of $11,874. The contract awarded last FY 
for maintenance dredging the outer critical shoals was 
completed removing 111,739 cubic yards of material at a 
cost of $426,008. A contract was awarded this FY for 
maintenance dredging the outer harbor in the amount of 
$1,784,050. Approximately 37,570 cubic yards of 
material was removed this FY at a cost of $511,799. 
Engineering, design, real estate, surveys, supervision and 
administration cost $124,753. Engineering and design for 
construction of a confined disposal facility continued at a 
cost of $233,418. 
Existing project is complete. The 1962 modification 
was started in November 1966 and completed in 
September 1973, except for dredging the reach from 150 
feet downstream of the Chicago & Northwestern Railway 
Bridge to 1,700 feet upstream of this bridge. Dredging of 
the turning basin above Chicago & Northwestern Railway 
Bridge was commenced in August 1938. The turning 
basin was enlarged under authority of Section 5 of the 
Rivers and Harbors Act of March 4, 1915, in order to 
provide sufficient area for the large ships that use it. The 
work was performed as part of a maintenance dredging 
contract in September and October 1973. East revetment 
at Grassy Island was entirely removed in July 1935. 
Dredging Fox River and entrance channel to Tail Point 
Light was completed in September 1967. Total cost of the 
existing project to end of FY was $44,297,876, of which 
$43,357,076 were regular funds and $940,800 Public 
Works funds; $9,946,395 for new work and $34,351,481 
for maintenance. The new work cost does not include 
$100,000 contributed funds. 
23. HAMMOND BAY HARBOR, MI 
Location. On northwest shore of Lake Huron, 35 miles 
southeast of Straits of Mackinac. (See NOAA Nautical 
Chart 14881.) 
Existing project. Provides for a harbor of refuge, 
protected by breakwater structures, extending to 12-foot 
depth contour in the lake; for dredging a harbor basin 10 
feet deep; and for dredging an entrance channel 12 feet 
deep. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Public facilities being planned by 
State and local agencies. Plans and specifications are 
complete, but construction has not started. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, and monitoring 
were performed by Government forces at a cost of 
$27,196. Engineering and design for maintenance 
dredging to be performed next FY cost $21,224. 
The existing project was completed in 1965. Total costs 
of existing project to end of FY were $1,646,950, of 
which $1,092,366 was for new work, and $554,584 for 
maintenance. 
21-14

DETROIT, MI DISTRICT 
24. HARBOR BEACH HARBOR, MI 
Location. On west shore of Lake Huron about 60 miles 
north of Port Huron, MI. (See NOAA Nautical Chart 
14862.) 
Existing project. Harbor of refuge protected by three 
breakwaters; a main entrance 23 feet deep; and an 
anchorage area 21 feet deep. For additional details see 
page 1485 of Annual Report for 1962. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Coal and limestone are received at 
a private wharf. In addition, there is a public recreational 
craft pier, a Coast Guard pier, and several small 
installations engaged in docking and servicing light-draft 
commercial and recreational vessels. These facilities 
satisfy current commerce and traffic requirements. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces and contract at a cost of $22,034. Engineering and 
design for the third phase of repairing the Main 
Breakwater was completed at a cost of $93,271. A 
contract in the amount of $2,162,565 was awarded for this 
work. The contract was approximately 80% complete at 
the end of the FY at a cost of $1,667,300. Supervision 
and administration of the breakwater contract cost 
$73,978. A maintenance dredging contract was awarded 
and completed at a cost of $432,537. Engineering, 
surveys, supervision and administration of dredging 
contract cost $66,638. 
Existing project was completed in 1928. For additional 
details on completion of existing project see page 1485 of 
Annual Report for 1962. Total cost for existing project to 
end of FY was $15,902,003, of which $1,200,598 was for 
new work, $14,506,901 for maintenance, and $194,504 
for rehabilitation. 
25. HOLLAND HARBOR, MI 
Location. On east shore of Lake Michigan 95 miles 
northeasterly from Chicago, IL, and 23 miles southerly 
from Grand Haven, MI. (See NOAA Nautical Chart 
14932.) 
Previous project. For details see page 1948 of Annual 
Report for 1915, and page 1478 of Annual Report for 
1938. 
Existing project. An outer breakwater protected 
approach channel in Lake Michigan, an entrance channel 
to Lake Macatawa protected by piers and revetments, a 
channel through Lake Macatawa into Black River, and a 
turning basin. Project depths are 23 feet in outer portion 
of approach channel decreasing to 21 feet at outer end of 
inner piers, 21 feet to upper end of project, and 18 feet in 
turning basin. For additional details see page 1458 of 
Annual Report for 1962. 
The uncompleted portion of the project, widening bend 
of entrance channel into Lake Macatawa, was deauthorized 
December 31, 1989, in accordance with Section 1001 of 
the WRDA of 1986 (PL 99-662.) (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with for completed 
portions of project. 
Terminal facilities. Wharves are at inner end of Lake 
Macatawa, and used for handling coal, building materials, 
petroleum products, and miscellaneous commodities. Two 
shipbuilding yards are on south shore of the lake. Holland 
provides a public wharf for small craft. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $259,177. 
Safety maintenance was performed by hired labor at a cost 
of $8,873. Repairs to the North Connector were 
performed by the U. S. Cranebarge MANITOWOC at a 
cost of $56,592. Maintenance of the disposal area by 
hired labor cost $5,404. The contract awarded last FY for 
repairs to the North Connector, Section Q, was completed 
at a cost this FY of $90,989. Another contract was 
awarded and completed this FY for repair of South 
Connector, Section Q, at a cost of $170,169. Engineering 
and design for repairs to the North and South Connectors, 
Section Q, was performed at a cost of $74,485. A 
contract was awarded and completed this FY for 
maintenance dredging of the outer harbor at a cost of 
$108,329, removing 28,120 cubic yards of dredge 
material. This contract was also for beach nourishment. 
Engineering, design, surveys, supervision and 
administration cost $89,355. Monitoring in connection 
21-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
with Section 111 of PL 90-483 was performed at a cost of 
$28,866. Beach nourishment in conjunction with above 
maintenance dredging contract cost $27,083. Engineering 
and design for Section 111 cost $2,099. 
Existing project, with exception of widening bend in 
revetted entrance channel authorized by Act of September 
3, 1954, was completed in 1957. For additional details on 
completion of existing project, see page 1460 of Annual 
Report for 1962. Total cost of existing project to end of 
FY was $26,548,857, of which $1,392,827 was for new 
work ($1,180,502 regular funds, $176,620 for previous 
project and $35,705 contributed funds), $24,653,578 
for maintenance, and $502,452 for rehabilitation. 
26. THE INLAND ROUTE, MI 
Location. A series of interconnected lakes and streams 
stretching across northern tip of Lower Peninsula of 
Michigan, and extends from Conway near Lake Michigan 
to Cheboygan on Lake Huron; a distance of 35 miles. 
Crooked and Indian Rivers are connecting channels in the 
waterway. (See NOAA Nautical Chart 14886.) 
Existing project. Provides for a channel 30 feet wide 
and 5 feet deep, with necessary widening at bends, 
through Crooked and Indian Rivers, and Crooked, Burt, 
and Mullett Lakes, and from Conway (west end of 
Crooked Lake) to navigation lock at Cheboygan; in 
Pickerel Channel from Pickerel Lake to Crooked Lake. 
It also provides for suitable jetties at head of Indian River. 
The addition of a lock and dam was approved by the Chief 
of Engineers on September 2, 1964, to correct a design 
deficiency. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. None exist for commercial cargohandling 
along the Crooked and Indian Rivers. Numerous 
small privately owned timber piers and wharves, some 
equipped with covered boat wells for serving and storing 
recreational craft, have been constructed. Landings 
maintained by hotel and resort operators are open to the 
public for transfer of passengers. Public docks are at 
Conway and Oden on Crooked Lake; the village of Indian 
River, Topinabee, and Mullett Lake Village on Mullett 
Lake; and at Cheboygan. About 30 highways dead end at 
water's edge, permitting public access for various marine 
activities. Dock facilities are considered adequate for 
existing traffic. 
Operations during fiscal year. Maintenance: The 
navigation lock was operated and maintained by the State 
of Michigan at no cost to the Government. In FY 92, the 
lock was operated from 9:00 a.m. to 5:00 p.m. April 24- 
26, May 2, 3, 9, 10, 16, 17, 26-31, September 16-30. 
The lock was operated 8:00 a.m. to 9:00 p.m. May 23-25, 
June 1-30, September 1-15. The lock was operated from 
8:00 a.m. to 10:00 p.m. July 1 - August 31. In October, 
the lock was open on weekends only from 9:00 a.m. to 
5:00 p.m. The lock closed at 5:00 p.m. on October 18. 
Water control activities at the lock and weir performed 
under contract by the State of Michigan cost $7,000. 
Winter operation and shut down of Alanson Locks cost 
$1,955. Condition surveys, real estate, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $36,241. 
The existing project was completed in 1958. The lock 
and dam was completed in FY 1968. For additional 
details see page 1382 of Annual Report for 1960. Total 
cost for existing project to end of FY was $3,838,058, of 
which $918,222 was for new work (includes $148,000 
contributed funds) and $2,919,836 for maintenance. 
27. KENOSHA HARBOR, WI 
Location. On west shore of Lake Michigan about 35 
miles south of Milwaukee and about 54 miles north of 
Chicago. (See NOAA Nautical Chart 14904.) 
Previous project. See page 1390 of Annual Report for 
1962. 
Existing project. For detailed description see page 
1237, Annual Report for 1963. Estimated (1986) Federal 
cost is $455,000 exclusive of amounts expended on 
previous projects, and $195,000 non-Federal which 
includes $155,000 local contribution. (See Table 21-B for 
authorization legislation.) 
The uncompleted portion of the project authorized by the 
1962 River and Harbor Act, dredging of 25-foot wide 
strips adjacent to the north and south piers, was 
deauthorized December 31, 1989, in accordance with 
Section 1001 of the WRDA of 1986 (PL 99-662). 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves used for 
miscellaneous foreign overseas commodities and autos, 
and also several fish wharves. While these facilities are 
21-16

DETROIT, MI DISTRICT 
considered generally adequate for existing commerce, 
more efficient use of existing terminals and utilization of 
available frontage for development of additional terminals 
should be made. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $19,722. Repairs to 
Confined Disposal Facility (filter cells) were performed by 
hired labor at a cost of $597. Real estate, supervision and 
administration cost $11,143. 
Existing project is complete except for dredging 25-foot 
strips adjacent to the north and south piers which was 
deauthorized December 31, 1989. The north and south 
piers were completed in 1900 and the breakwater in 1909. 
Total cost of the existing project to end of FY was 
$13,014,399, of which $12,986,741 were regular funds 
and $27,658 Emergency Relief funds; $988,969 being for 
new work, $10,755,155 for maintenance, and $1,270,275 
for rehabilitation. The new cost does not include $3,000 
contributed funds. 
28. KEWAUNEE HARBOR, WI 
Location. On west shore of Lake Michigan, about 105 
miles north of Milwaukee, WI, and about 78 miles from 
Green Bay, via Sturgeon Bay Canal. Harbor is at mouth 
of Kewaunee River. (See NOAA Nautical Chart 14908.) 
Previous projects. See page 1375 of Annual Report for 
1962. 
Existing project. See Chicago District 1979 Annual 
Report, Table 30-C, page 30-31. 
Costs of completed project are $603,021 Federal, and 
$9,000 non-Federal, exclusive of amount expended on 
previous projects. Uncompleted portion (estimated 
$200,000, July 1965) of 1935 River and Harbor Act is 
considered inactive, and excluded from present cost 
estimate. The portion authorized by the 1960 River and 
Harbor Act was deauthorized in 1977. (See Table 21-B 
for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two car-ferry slips, a petroleum 
tank farm, a Corps of Engineers project office, and 
several fishing wharves. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
real estate activities, miscellaneous inspections and reports 
were performed by Government forces and contract at a 
cost of $159,218. Safety maintenance was performed by 
hired labor at a cost of $10,250. Repairs to confined 
disposal facility, north breakwater and east revetment were 
performed by the U.S Cranebarge MANITOWOC at a 
cost of $104,260. A maintenance dredging contract was 
awarded and completed at a cost of $309,710 removing 
approximately 66,991 cubic yards of shoal material. 
Engineering, design, supervision and administration cost 
$75,818. 
Active portion of existing project is complete. The 
north pier was completed in 1897 and the remaining 
portion is in generally good condition. Rehabilitation of 
the south pier was completed in June 1967. Construction 
of north breakwater and shore connection, except for a 
gap of 150 feet about 830 feet from shoreward end, and 
removal of outer 706.5 linear feet of north pier was 
commenced in September 1935 and completed in June 
1937. Removed 500 linear feet of north pier in 
April/May 1963 and widened and deepened the adjacent 
channel in 1965. Outer end of the north pier was struck 
and severely damaged by car ferry vessel in October 1973 
and a 24-foot section at outlet end was subsequently 
removed, thus reducing the structure to a length of 626 
feet. Dredging entrance channel in interior basin to 
existing project depth was commenced in April and 
completed in October 1938. Kewaunee River is navigable 
to about 6.5 miles above mouth for craft drawing not 
more than 4 feet. Total cost of existing project to end of 
FY was $10,666,405, of which $758,333 was for new 
work ($338,333 regular and $420,000 Emergency Relief 
funds) $9,290,772 regular funds for maintenance and 
$617,300 regular funds for rehabilitation. 
29. KEWEENAW WATERWAY, MI 
Location. In Lake Superior across Keweenaw Peninsula 
in upper peninsula of Michigan. The west entrance is 169 
miles east of Duluth, MN. (See NOAA Nautical Chart 
14972.) 
Existing project. A navigable channel, minimum width 
300 feet, 25 miles long, partially natural and partially 
artificial, across Keweenaw Peninsula via Portage Lake. 
21-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
For details see page 1121 of Annual Report for 1963. 
(See Table 21-B for authorizing legislation.) 
The uncompleted portion of the project for navigation at 
Keweenaw Waterway, Houghton County, MI, authorized 
by the River and Harbor Act of Aug. 30, 1935, PL 409, 
73rd Congress, which consists of extending the lower 
entrance breakwater by 2,000 feet, including the necessary 
alteration or replacement of structures due to channel 
deepening, was deauthorized by the WRDA of 1986; PL 
99-662, Nov. 17, 1986, 99th Congress, Title X. 
Local cooperation. None required. 
Terminal facilities. Six coal docks, a petroleum dock, 
and several general merchandise and miscellaneous 
wharves, all privately owned. Facilities are considered 
adequate for existing commerce. Also present is a 
government constructed recreational area with facilities to 
include a picnic area and small boat landing range. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $186,837. 
The U.S. Derrickbarge COLEMAN performed breakwater 
and revetment repairs at a cost of $253,036. Engineering 
and design for major repair of East Breakwater Lower 
Entry was continued at a cost of $97,354. Real estate, 
supervision and administration cost $19,743. 
Active portion of the project is complete. Breakwaters 
are in generally good condition except for a weakness 
occurring in about 300 feet of substructure of breakwater 
lower entrance. The flared revetment at the upper entry 
should be modified to restrict wave action from the stilling 
basin entrance. Total cost for existing project to end of 
FY was $30,520,952, of which $5,974,141 was for new 
work, and $24,546,811 for maintenance. 
30. LAPOINTE HARBOR, WI 
Location. At westerly end of Madeline Island in the 
Apostlelsland group off the south shore of Lake Superior. 
(See NOAA Nautical Chart 14973.) 
Existing project. Provides for reconstruction of 73.5 
feet of the existing breakwater, extending the breakwater 
126.24 feet with 5 new steel sheet pile cells, harbor 
dredging and related work. The harbor is 10 feet deep in 
the entrance and 8 feet deep in the basin. Project was 
authorized by Section 107 of the 1960 River and Harbor 
Act (PL 645, 86th Congress), as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. A 400-foot L-shaped dock was 
constructed and rehabilitated by local interests, not as a 
part of the Federal project. 
Operations during fiscal year. Maintenance: 
Condition surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$6,079. A contract was awarded and completed for 
maintenance dredging removing approximately 3,806 
cubic yards of shoal material at a cost of $45,303. 
Engineering, design, surveys, supervision and 
administration cost $17,850. 
The existing project was completed in 1967. Total cost 
of existing project at end of FY was $259,799, of which 
$139,874 was for new work and $119,925 for 
maintenance. 
31. LAKE ST. CLAIR, MI, CHANNELS IN 
Location. Lake St. Clair, a section of Great Lakes 
connecting channels, is an expansive shallow basin having 
a vessel track length of about 15 miles from mouth of St. 
Clair River to head of Detroit River. (See NOAA 
Nautical Chart 14850.) 
Previous project. For details see page 2882, Annual 
Report for 1896; pages 1957-58, Annual Report for 1915; 
and page 1539, Annual Report for 1938. 
Existing project. An improved channel through Lake 
St. Clair 800 feet wide, 27.5 feet deep, and about 14.5 
miles long; extending from mouth of Southeast Bend 
cutoff channel at lower end of St. Clair River to head of 
Detroit River Channel. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. None. 
Operations during fiscal year. Maintenance: 
Condition surveys, support of Water Control Center, 
environmental studies, miscellaneous inspections and 
reports were performed by Government forces at a cost of 
$159,878. Maintenance of disposal area was performed 
21-18

DETROIT, MI DISTRICT 
by the U. S. Derrickbarge HURON at a cost of $25,074. 
A contract in the amount of $114,770 was awarded for 
maintenance dredging. The contract was approximately 
36% complete at the end of the FY, removing 
approximately 5,132 cubic yards of shoal material at a 
cost of $41,749. Engineering, design, real estate, 
supervision and administration cost $24,762. 
Total cost for existing project to end of FY was 
$20,736,732, of which $7,675,357 was for new work 
($6,666,762 regular funds and $1,008,595 Public Works 
Funds) and $13,061,375 for maintenance. 
32. LELAND HARBOR, MI 
Location. A light-draft harbor on eastern shore of Lake 
Michigan at mouth of Carp River, about 40 miles north of 
Frankfort, MI, and 40 miles southwest of Charlevoix, MI. 
(See NOAA Nautical Chart 14912.) 
Existing project. Provides for a harbor of refuge 
consisting of a breakwater about 1,200 feet long, a 
protected anchorage and maneuver area about 3 acres in 
extent and 10 feet deep, a 12-foot deep flared approach 
channel decreasing in width to 90 feet, an existing south 
pier 440 feet long, a 35-foot long cellular extension to 
south pier, an entrance channel 6 feet deep and 40 feet 
wide extending to mouth of Carp River, and for 
elimination of existing north pier. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned wharves on each 
side of river below the dam which is 400 feet above the 
river mouth. These wharves serve the local fishing 
interests and recreational craft. Public facilities are 
operated by the State and local agencies. All available 
dockage space is utilized. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
and miscellaneous inspections and reports were performed 
by Government forces and contract at cost of $36,672. A 
contract was awarded and completed for maintenance 
dredging removing 19,409 cubic yards of shoal material 
at a cost of $67,320. Safety maintenance was performed 
by hired labor at a cost of $897. Engineering, design, 
surveys, supervision and administration cost $28,830. 
The existing project was completed in 1932 except for 
the 1962 authorization which was completed in 1967. 
Total cost for existing project to end of FY was 
$3,426,188, of which $1,027,089 was for new work, 
$2,328,421 for maintenance, and $70,678 for 
rehabilitation. 
33. LEXINGTON HARBOR, MI 
Location. On southwest shore of Lake Huron, 20 miles 
north of Port Huron, MI. (See NOAA Nautical Chart 
14862.) 
Existing project. Provides for two offshore 
breakwaters opening to the southeast and totaling about 
2,400 feet long with provisions for recreational fishing on 
the main breakwater; an anchorage and maneuver area of 
about 5 acres, 8 feet deep; and a flared approach channel 
10 feet deep, decreasing to 160 feet in width through the 
breakwaters. Project also provides for recreational fishing 
facilities. Estimated (1979) Federal cost of new work is 
$1,647,306 excluding $1,088,888 to be contributed by 
local interests. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Assurances of local cooperation 
were furnished by the Michigan Department of Natural 
Resources to the Secretary of the Army. The cash 
contribution was $1,088,888. 
Terminal facilities. An existing public fishing pier of 
open pile construction is not adequate for existing and 
prospective commerce. Complete boating facilities are 
planned by State and local agencies in connection with the 
harbor construction. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, real estate 
activities, miscellaneous inspections and reports were 
performed by Government forces at a cost of $5,620. An 
adjustment of 1,118 cubic yards and $4,193 was made in 
dredging contract completed last FY. Surveys, 
supervision and administration cost $2,934. Monitoring 
under Section 111 mitigation was performed by 
Government forces at a cost of $19,605. 
The existing project was completed during FY 1977. 
Total cost for existing project to end of FY was 
$4,926,423, of which $3,107,192 (includes $1,088,888 
contributed funds) was for new work and $1,819,231 for 
maintenance. 
21-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
34. LITTLE LAKE HARBOR, MI 
Location. On south shore of Lake Superior 21 miles 
west of Whitefish Point and 30 miles east of Grand 
Marais, MI. (See NOAA Nautical Chart 14962.) 
Existing project. Provides for a small-craft harbor of 
refuge by dredging an entrance channel 12 feet deep from 
Lake Superior into Little Lake, suitably protected by 
breakwaters and revetments. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Only terminal facility at project 
consists of a public dock built by the State of Michigan for 
light-draft craft. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, and 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $11,517. A maintenance 
dredging contract was awarded and completed at a cost of 
$49,506 removing approximately 15,895 cubic yards of 
shoal material. Repair of the breakwater was performed 
by the U. S. Derrickbarge COLEMAN at a cost of 
$123,823. Engineering, design, supervision and 
administration cost $47,463. 
This project is considered complete; however, because 
of shifting sand, the harbor entrance shoals rapidly with 
the result that full project depth is not usually available. 
Total cost for existing project to end of FY was 
$4,453,486, of which $600,478 was for new work and 
$3,853,008 for maintenance. 
35. LUDINGTON HARBOR, MI 
Location. On east shore of Lake Michigan, 156 miles 
northeasterly from Chicago, IL, and 67 miles northerly 
from Grand Haven, MI. (See NOAA Nautical Chart 
14937.) 
Previous project. For details see page 1951 of Annual 
Report for 1915, page 1491 of Annual Report for 1938, 
and page 1307 of Annual Report for 1963. 
Existing project. Provides for an exterior basin in Lake 
Michigan protected by north and south breakwaters, north 
breakwater is 1,800 feet long and south breakwater 1,700 
feet long, 550 feet apart at outer ends, diverging at an 
angle of 90 degrees, with shore connections, 1,103 and 
2,004 feet long, respectively; for dredging exterior basin 
to 18 feet deep with a maximum width of 1,500 feet; for 
a channel with a depth of 29 feet from deep water in Lake 
Michigan decreasing to 27 feet at the west end of the 
north pier, over a maximum width of 600 feet; thence a 
channel with a depth of 27 feet, over a minimum width of 
230 feet with necessary widening at Pere Marquette Lake; 
and for inner piers and revetments, 1,649 feet long on 
north and sufficiently long on the south for turn at Pere 
Marquette Lake. The estimated (1977) Federal cost for 
new work is $8,250,000. Estimated total cost for local 
interests is $147,000. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. In addition to main terminal of 
Chesapeake & Ohio Railway Company consisting of three 
car ferry slips, a wharf, and warehouses, there are several 
wharves which handle coal, limestone, and miscellaneous 
commodities. Facilities adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $72,614. Safety 
maintenance was performed at a cost of $2,785. 
Engineering and design for repair of the North and South 
Breakwaters, Sections A and E, was continued at a cost of 
$94,172. Real estate activities, surveys, supervision and 
administration cost $3,018. 
Existing project was completed in 1918. For additional 
details on completion of existing project see page 1469 of 
Annual Report for 1962. Total cost for existing project to 
end of FY was $22,021,701, of which $8,532,202 was for 
new work, $13,131,586 for maintenance, and $357,913 
for rehabilitation. 
36. MANISTEE HARBOR, MI 
Location. On east shore of Lake Michigan, 179 miles 
northeasterly from Chicago, IL, and 26 miles northerly 
from Ludington, MI. (See NOAA Nautical Chart 14938.) 
Previous project. For details see page 1952 of Annual 
Report for 1915, and page 1493 of Annual Report for 
1938. 
21-20

DETROIT, MI DISTRICT 
Existing project. An entrance channel in Lake 
Michigan protected by a breakwater, piers, and revetment; 
a channel in Manistee River to Manistee Lake; and 
Federal participation in cost of replacing Maple Street 
Bridge. Project depths are 25 feet in entrance channel and 
23 feet in river channel. For additional details see page 
1470 of Annual Report for 1962. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Installations are on both sides of 
river and on Manistee Lake. Commerce handled includes 
coal, sand, salt, and general cargo. In addition, there is 
a Government wharf and a State and City owned 
recreational craft pier which is open to the public. These 
facilities satisfy current commerce requirements. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, miscellaneous inspections 
and reports were performed by Government forces at a 
cost of $57,845. Repairs to South breakwater, Section B, 
was performed by the U. S. Cranebarge MANITOWOC 
at a cost of $243,731. Safety maintenance was performed 
by hired labor at a cost of $2,852. Engineering and 
design for repairs to South Connector and South Pier was 
initiated at a cost of $79,010. A contract was awarded 
and completed for maintenance dredging removing 
approximately 84,003 cubic yards of shoal material at a 
cost of $249,123. Engineering, design, surveys, 
supervision and administration cost $66,753. 
Existing project was completed in August 1967. For 
additional details on completion of existing project see 
page 1470 of Annual Report for 1962. Total cost for 
existing project to end of FY was $11,763,123, of which 
$2,696,522 was for new work, $7,692,437 for 
maintenance, and $1,374,164 for rehabilitation. 
37. MANISTIQUE HARBOR, MI 
Location. On the north shore of Lake Michigan, 135 
miles northeasterly from Green Bay Harbor, WI, and 220 
miles northerly from Milwaukee, WI. (See NOAA 
Nautical Chart 14908.) 
Previous project. For details see page 1933 of Annual 
Report for 1915, and page 1422 of Annual Report for 
1938. 
Existing project. A breakwater protected entrance 
channel in Lake Michigan, a channel in Manistique River, 
and a pier at river mouth. Project depths are 19 feet in 
outer portion of entrance channel, 18 feet in inner portion 
of entrance channel, and 18 feet in river channel. For 
additional details see page 1451 of Annual Report for 
1962. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A car ferry slip, two coal and 
building material wharves, two fishing wharves, and 
numerous lumberyard slips. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, real estate 
activities, and miscellaneous inspections and reports were 
performed by Government forces at a cost of $23,068. 
Total cost for existing project to end of FY was 
$3,843,199, of which $1,299,355 was for new work, 
$2,227,511 for maintenance and $316,333 for 
rehabilitation. 
38. MANITOWOC HARBOR, WI 
Location. On west shore of Lake Michigan about 79 
miles north of Milwaukee and about 106 miles from Green 
Bay Canal. (See NOAA Nautical Chart 14922.) 
Previous projects. See page 1379 of Annual Report for 
1962. 
Existing project. The total estimated (Oct. 1981) 
project cost is $3,080,000; the Federal cost is $1,085,000 
and non-Federal cost is $1,995,000, which is a cash 
contribution. See Chicago District Annual Report for 
1979, Table 30-C. 
For detailed description see page 1228 of Annual Report 
for 1963. Estimated costs (1970) of new work for 1968 
modification are $81,000 Federal and $30,000 non-Federal 
which includes a cash contribution of $18,000. Work on 
the 1968 modification was postponed until 1982. The 
portion authorized by the 1962 River and Harbor Act was 
deauthorized December 31, 1989, in accordance with 
Section 1001 of the WRDA of 1986 (PL 99-662). (See 
Table 21-B for authorizing legislation.) 
21-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Construction of a small boat harbor within the existing 
harbor was authorized by the Chief of Engineers, June 26, 
1979, and 720-foot channel extension affirmed in July 
1982, under authority of Section 107, 1960 River and 
Harbor Act, as amended. 
Local cooperation. Fully complied with for completed 
modifications. For 1968 modification local interests must 
make an annual cash contribution equivalent to 50% of the 
annual costs associated with construction and maintenance 
of the channel extension until such time that a second user 
utilizes the channel extension. Such a contribution is 
presently estimated at $14,200; additional assurances 
require that the sponsor provide without cost to the United 
States all lands, easements, and rights-of-way required for 
construction and subsequent maintenance, including 
suitable areas determined by the Chief of Engineers to be 
required in the general public interest for initial and 
subsequent disposal of dredged materials, and the 
necessary retaining dikes, bulkheads and embankments 
therefor or the costs of such retaining works; hold and 
save the United States free from damages due to the 
construction works and subsequent use, operation, and 
maintenance of the project, not including damages due to 
the fault or negligence of the United States or its 
contractors; provide and maintain without cost to the 
United States adequate berthing areas at the docks adjacent 
to the improvement; accomplish at no cost to the United 
States all relocations and alterations of utilities necessary 
for the project; assume full responsibility for all project 
first costs in excess of the Federal cost limitation of 
$2,000,000; and comply with the Uniform Relocation 
Assistance and Real Property Acquisition Policies Act of 
1970. 
Terminal facilities. Three car-ferry slips, a grain 
elevator, one shipbuilding yard, and three other wharves 
used for handling coal, building materials, cement, and 
miscellaneous commodities. While these facilities are 
considered adequate for existing commerce, it is believed 
the city should provide a suitable wharf with warehouse 
and railway connection open to the general public. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $77,044. Repairs to North 
Breakwater, South Breakwater, Section F, Section 107 
Causeway, and Confined Disposal Facility were performed 
by the U. S. Cranebarge MANITOWOC at a cost of 
$178,471. An adjustment of $2,351 was made in contract 
cost for maintenance dredging completed last FY. 
Engineering and design for repair of South Breakwater, 
Section B, was initiated at a cost of $21,330. Supervision 
and administration cost $12,852. 
Existing project is complete except for the 1962 and 
1968 modifications. The 1962 modification was 
deauthorized December 31, 1990. Work on the 1968 
modification was essentially completed in FY 83. The 
Federal modification, adopted July 15, 1985, included the 
expansion of the new entrance channel to the Section 107 
project and extension of the rubblemound breakwater. 
Dredging a channel through the outer basin to existing 
project depth and removal of a portion of old north stub 
pier at the river entrance were completed in December 
1937. Dredging river channel was completed in July 
1942. Cost for existing project to end of FY was 
$13,725,333, of which $3,960,044 was for new work 
(includes $1,911,130 contributed funds) and $9,765,289 
for maintenance. 
39. MARQUETTE HARBOR, MI 
Location. In Marquette Bay on south shore of Lake 
Superior, 160 miles west of Sault Ste. Marie, MI, and 265 
miles east from Duluth, MN. (See NOAA Nautical Chart 
14970.) 
Existing project. Provides for a breakwater, and a 
harbor basin 26.5 feet deep, giving a protected area of 350 
acres. Project was modified in 1960 to provide a 27-foot 
depth in harbor area. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. None required for earlier 
authorizations. Fully complied with for the 1960 Act. 
Terminal facilities. One ore dock, unused at present; 
two coal docks; one petroleum dock; and three other 
unused docks. There are also several small fish wharves 
without railroad connections. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Real 
estate activities and miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$9,301. Repairs to East Breakwater, Sections C, D, E, 
and F, were performed by the U. S. Derrickbarge 
COLEMAN at a cost of $377,684. Supervision and 
administration cost $6,535. 
21-22

DETROIT, MI DISTRICT 
Total cost for existing project to end of FY was 
$4,358,192, of which $1,282,893 was for new work, 
$2,609,542 for maintenance and $465,757 for 
rehabilitation. 
40. MENOMINEE HARBOR AND RIVER, 
MI AND WI 
Location. On Lake Michigan at the mouth of 
Menominee River on the western shore of Green Bay, 16 
miles northwest of the mouth of Sturgeon Bay, and 49 
miles northeast of Green Bay Harbor, about 155 miles 
from Milwaukee via Sturgeon Bay Canal. The river 
forms the boundary between the commercial harbors at 
Marinette, WI, and Menominee, MI. (See NOAA 
Nautical Chart 14917.) 
Previous projects. See page 1361 of Annual Report for 
1962. 
Existing project. See Chicago District Annual Report 
for 1979, Table 30-C, page 30-26. 
For detailed description see page 1214, Annual Report 
for 1963. The portion authorized by 1960 River and 
Harbor Act is inactive and estimated (1964) at $442,000 
Federal, and $105,000 non-Federal. Costs of completed 
new work, exclusive of inactive work and amount 
expended on previous projects, are $221,053 Federal and 
$40,762 non-Federal, which includes a cash contribution 
of $36,762. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with for completed 
work. 
Terminal facilities. There are 9 wharves for handling 
coal, limestone, pulp and miscellaneous commodities. 
City of Marinette, WI, provided a public wharf. Facilities 
are considered fairly adequate for existing commerce, 
except that there is need for a public wharf owned by city 
of Menominee, with warehouse and railway connection. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, and miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $29,442. Repairs to the North Pier, 
Sections A, B, C, and D, were performed by the U. S. 
Cranebarge MANITOWOC at a cost of $87,004. Safety 
maintenance was performed by hired labor at a cost of 
$1,542. Supervision and administration cost $8,934. 
The project in effect prior to the modification of March 
2, 1945, was completed in 1938. No additional work was 
necessary under the modification of March 2, 1945, to 
provide a depth of 12 feet in the extension of the channel 
to the vicinity of the Marinette Yacht Club, as project 
depth or more was available. The entrance piers were 
completed in 1884, were rehabilitated (1954-1964) and are 
in excellent condition. Dredging of the channel below the 
Marinette municipal wharf, together with enlarging the 
turning basin to existing project depth, was commenced in 
May 1938. Modification of the project authorized by the 
1960 River and Harbor Act is inactive. Construction for 
the 1967 modifications was started August 17, 1968, and 
completed in October 1968. The cost of the existing 
project to end of FY was $5,059,755, of which $570,238 
was for new work (includes $36,762 contributed funds), 
$3,137,665 for maintenance and $1,351,852 for 
rehabilitation. 
41. MILWAUKEE HARBOR, WI 
Location. On west shore of Lake Michigan about 85 
miles north of Chicago, IL, and about 83 miles west of 
Grand Haven, MI. (See NOAA Nautical Chart 14924.) 
Previous projects. See page 1385 of Annual Report for 
1962. 
Existing project. See Chicago District Annual Report 
for 1979, Table 30-C, page 30-26. For detailed 
description see page 1232 of Annual Report for 1963. 
Completed new work costs are $6,934,804 Federal and 
$478,000 non-Federal, exclusive of amount expended on 
previous projects. The uncompleted portion authorized by 
the 1935 River and Harbor Act was deauthorized 
December 31, 1989, in accordance with Section 1001 of 
the WRDA of 1986 (PL 99-662). Uncompleted portion of 
1945 River and Harbor Act was deauthorized in 1977. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Complied with for Acts of March 
2, 1945, October 23, 1962, and July 14, 1960, except 
deauthorized portion of 1945 Act. Act of August 30, 
1935, provided that original dredging of outer harbor area 
be done by city of Milwaukee and city of Milwaukee be 
reimbursed at actual cost but not to exceed 10 cents per 
cubic yard, place measurement, for original dredging done 
subsequent to authorization of work by Congress. 
Agreement covering dredging was executed by Secretary 
of War, February 23, 1934, after this work was originally 
21-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
authorized as part of public, works program. City was 
reimbursed for 10 percent of dredging. 
Terminal facilities. Four car-ferry slips, and 57 other 
wharves, private and municipal, used for handling coal, 
grain, building materials, cement, petroleum products, and 
miscellaneous commodities. As facilities in inner harbor 
were inadequate for existing commerce, Milwaukee 
Harbor Commission has constructed nine docks in the 
outer harbor for handling general cargo. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $275,007. Safety 
maintenance was performed by hired labor at a cost of 
$3,422. Obstruction removal, repairs to North Detached 
Breakwater, North Revetment, and the Diked Disposal 
Facility were performed by the U. S. Cranebarge 
MANITOWOC at a cost of $273,993. Engineering and 
design for repair of spalling, South Breakwater, Section E, 
continued at a cost of $50,737. Supervision and 
administration cost $11,815. An adjustment of $1,043 
was made in contract cost for construction of a 
recreational walkway completed last FY. Supervision and 
administration for close-out cost $14,593. Includes 
$2,486 Contributed Funds. 
Existing project is complete except for inactive portions. 
The 1962 modification was completed in July 1967. North 
breakwater and shore connection, 9,954 feet long, was 
completed in August 1925. North pier was completed in 
1905 and construction of south pier was completed in 
November 1910. Construction of south breakwater and 
shore connection was completed in October 1929. Before 
modification of August 30, 1935, the city of Milwaukee 
also dredged most of the area in the outer harbor south of 
inner entrance piers and lakeward of pierhead line to more 
than 21 feet below datum without cost to the United 
States. City of Milwaukee also dredged a portion of the 
area of the outer harbor north of inner entrance piers to 
provide an approach channel to the passenger and auto 
pier opposite East Claybourn Street. Work on the 1945 
modification was completed in August 1957, except for 
the uncompleted portion which consists of dredging the 
Milwaukee River from Buffalo Street to upper limit of the 
project at Humboldt Avenue. The uncompleted portion of 
the project authorized by the 1945 Rivers and Harbors Act 
was deauthorized in 1977. Total cost for existing project 
to end of FY was $58,991,446, of which $8,231,024 was 
for new work, $38,044,862 for maintenance, and 
$12,715,560 for rehabilitation. 
42. MONROE HARBOR, MI 
Location. On lower reach of River Raisin, which 
empties into Lake Erie and is 36 miles south of Detroit, 
MI. (See NOAA Nautical Chart 14830.) 
Existing project. Provides for a channel in Lake Erie 
and River Raisin to city of Monroe, for a turning basin, 
and for riprapping protecting dikes at river mouth. 
Project depths are 21 feet to turning basin, 18 feet in 
turning basin, and 9 feet to upstream end of project. For 
additional details see page 1490 of Annual Report for 
1962. Project feature for riprapping protecting dikes is 
considered inactive. Estimated cost of this feature (1954) 
is $90,000. (See Table 21-B for authorizing legislation.) 
The WRDA of 1986 authorized modifications to deepen 
the River Raisin portion of the existing 200-foot 
navigation channel from 21 to 27 feet between existing 
turning basin and the river's mouth; deepen the lake 
channel from 21 to 28 feet, and widen the channel from 
200 to 500 feet, for a distance of approximately 47,000 
feet from the river's mouth to the Maumee Bay Entrance 
Channel; dredge a new turning basin 24 feet deep, with 
a diameter of at least 1,600 feet, at the river's mouth; and 
construct a 190 acre confined disposal area in Plum Creek 
Bay behind which would enable the creation of a 700 acre 
marsh. Estimated total cost (Oct. 88) is $150,200,000; 
$59,000,000 Federal and $91,200,000 non-Federal, which 
includes a cash contribution of $19,650,000. 
Local cooperation. Fully complied with for completed 
portion of project. Local cooperation items for the newly 
authorized project in the WRDA of 1986 (PL 99-662), are 
as described in the Rivers and Harbors Committee 
Document 22, 71st Congress, 1st Session; R & H Comm. 
Doc. 12, 72d Congress, 1st Session, and 45, 75th 
Congress, 1st Session, and also includes, as a result of PL 
99-662, construction cost sharing as follows: 
a. Contribute in cash 25 percent of the total cost of 
construction of general navigation facilities, exclusive of 
aids to navigation, a contribution presently estimated at 
$19,650,000. The estimated cash contribution of 
$19,650,000 to be paid in lump sum prior to initiation of 
construction, or in annual installments during the 
construction period at a rate proportionate to the proposed 
or scheduled expenditure of Federal funds as required by 
21-24

DETROIT, MI DISTRICT 
the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final 
apportionment of cost to be made after actual costs have 
been determined; 
b. Repay, with interest, over a period of up to 30 years 
following project completion, 10 percent of the total cost 
of construction of general navigation facilities, an amount 
presently estimated at $7,860,000. The Secretary of the 
Army may count against all or part of the 10 percent 
repayment, the amount of the local contribution for lands, 
easements, rights-of-way, dredged/demolition material 
disposal sites and relocations. In no case are these costs 
to count against the cash payment during construction, and 
in no case would the amount waived exceed 10 percent of 
project cost; and 
c. The confined dike area construction is a non-Federal 
responsibility and is estimated to cost $70,156,000. 
Terminal facilities. Several privately owned docks and 
a municipal terminal. Port of Monroe Authority built a 
steel and concrete wharf on southeast side of turning basin 
for commercial use. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, Hi-Fix surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $88,142. Maintenance of 
the disposal facility was performed by hired labor at a cost 
of $825. A contract was awarded and completed for 
maintenance dredging, removing approximately 222,000 
cubic yards of material at a cost of $965,999. 
Engineering, design, surveys, supervision and 
administration cost $124,962. An adjustment of -$8,027 
was made in costs under the dike disposal program. 
Total cost for existing project to end of FY was 
$58,139,377, of which $987,340 was for new work 
(includes $300,000 contributed by the Port Commission of 
Monroe) and $57,152,037 for maintenance (includes 
$166,667 contributed funds, $125,000 by Consolidated 
Paper Company and $41,667 by River Raisin Company). 
43. MUSKEGON HARBOR, MI 
Location. On east shore of Lake Michigan, 114 miles 
northeasterly from Chicago, IL, and 80 miles easterly 
from Milwaukee, WI. (See NOAA Nautical chart 19434.) 
Previous project. For details see page 1950 of Annual 
Report for 1915; page 1399, Annual Report for 1924; and 
page 1484, Annual Report for 1938. 
Existing project. A breakwater protected outer basin in 
Lake Michigan and an entrance channel from Lake 
Michigan to Muskegon Lake protected by piers and 
revetments. Project depths vary from 29 feet in the 
lakeward portion of the outer basin to 27 feet in the 
channel between the inner piers to Muskegon Lake. For 
additional details see page 1303 of Annual Report for 
1963. (See Table 21-B for authorizing legislation. 
Local cooperation. Fully complied with. 
Terminal facilities. Several privately owned wharves 
primarily for commercial use. Details on actual port and 
harbor facilities are in Port Series, NO. 48 (revised 1981) 
prepared and published by the Water Resources Support 
Center. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, miscellaneous inspections 
and reports were performed by Government forces and 
contract at a cost of $109,320. Safety maintenance was 
performed by hired labor at a cost of $13,547. An 
adjustment of -$615 was made in contract cost to 
maintenance dredging completed last FY. Supervision and 
administration cost $1,853. 
Existing project, including latest project modification, 
was completed in 1965. For additional details on 
completion of existing project see page 1465 of Annual 
Report for 1962. Total cost for existing project to end of 
FY was $26,628,191, of which $3,017,110 was for new 
work, $9,786,781 for maintenance, and $13,824,300 for 
rehabilitation. 
44. NEW BUFFALO HARBOR, MI 
Location. At mouth of Galien River on southeast shore 
of Lake Michigan in Berrien County, about 45 miles 
easterly from Chicago, IL. (See NOAA Nautical Chart 
14905.) 
Existing project. Provides for an entrance channel 10 
feet deep by 80 feet wide and 850 feet long, to mouth of 
Galien River; new north and south breakwaters 1,305 and 
740 feet long, respectively, and deepening inner channel 
21-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
to Galien River to 8 feet and 80 feet wide and 1,250 feet 
long. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One village owned boat ramp and 
three privately operated marinas, and a private boat club 
facility. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
monitoring, miscellaneous inspections and reports were 
performed by Government forces at a cost of $52,124. 
Repairs to safety features cost $1,752. An adjustment of 
$21 was made in contract cost for beach nourishment 
completed last FY. A contract was awarded and 
completed for maintenance dredging, removing 
approximately 11,931 cubic yards of shoal material at a 
cost of $71,231. Engineering, design, surveys, real 
estate, supervision and administration cost $57,222. 
Existing project is complete. "Total cost for existing 
project to end of FY was $6,642,342, of which 
$2,472,183 was for new work (includes $1,186,467 
contributed funds) and $4,170,159 for maintenance. 
45. OCONTO HARBOR, WI 
Location. On the west shore of Green Bay, about 31 
miles northeasterly from Green Bay Harbor, WI, and 
about 25 miles southwesterly from Menominee Harbor, 
MI and WI, at mouth of Oconto River. (See NOAA 
Nautical Chart 14910.) 
Previous project. For details see page 1187 of Annual 
Report for 1958. 
Existing project. See Chicago District Annual Report 
for 1979, Table 30-C, page 30-27. For detailed 
description see page 1187, Annual Report for 1958. (See 
Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Two municipally owned wharves 
of 400 and 100 feet frontage, respectively, for 
miscellaneous freight, open to general public use. 
Facilities considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $48,013. Repairs to the South Pier, 
Sections B, C, D, and E, performed by the U. S. 
Cranebarge MANITOWOC cost $170,822. A contract for 
maintenance dredging was awarded this FY in the amount 
of $433,300. Contractor will begin dredging next FY. 
Engineering, design, real estate, supervision and 
administration cost $63,735. 
Total cost for existing project to end of FY was 
$1,638,649, of which $130,754 was for new work and 
$1,507,895 for maintenance. 
46. ONTONAGON HARBOR, MI 
Location. About 140 miles east of Duluth, MN, on 
south shore of Lake Superior, at mouth of Ontonagon 
River; provides the only refuge for small craft between the 
Keweenaw Waterway upper entrance and Black River 
Harbor. (See NOAA Nautical Chart 14965.) 
Previous project. For details see page 1931 of Annual 
Report for 1915, and page 1406 of Annual Report for 
1938. 
Existing project. Provides for approach channel 16 feet 
deep, a channel between piers with 17 and 15-foot depths, 
an inner basin 12 feet deep, and maintenance of channels, 
basin, and entrance piers. Completed project cost 
$19,619. See page 1100 of Annual Report for 1966 for 
details. A modification authorized by 1962 River and 
Harbor Act provides for increasing depths of channels, 
construction of an inner basin and a sedimentation basin. 
(See Table 21-B for authorized legislation.) 
The turning basin feature of the project for navigation at 
Ontonagon Harbor, Ontonagon County, MI, authorized by 
the River and Harbor Act of 1962, was deauthorized by 
the WRDA of 1986; PL 99-662 (Section 1002) Nov. 17, 
1986, 99th Congress, Title X. The channel modification 
project authorized by the 1962 River and Harbor Act was 
deauthorized December 31, 1989, in accordance with 
Section 1001 of the WRDA of 1986 (PL 99-662). 
Local cooperation. None required. 
Terminal facilities. There are no publicly owned 
wharves. There are three coal wharves, an oil receiving 
facility, and a few small fish wharves. Facilities are 
considered adequate for existing commerce. 
21-26

DETROIT, MI DISTRICT 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $30,947. Maintenance of lighthouse 
was performed by hired labor at a cost of $8,387. The 
lighthouse roof repair contract awarded last FY was 
completed this FY with adjustments of -$137 in costs. 
Repairs to the East and West Pier, Sections A and B, were 
performed by the U. S. Derrickbarge COLEMAN at a 
cost of $114,743. The contract for repair of West 
Revetment, Section E, awarded in FY 91 was completed 
at the end of this FY at a cost of $1,334,810. 
Engineering and design during construction cost $82,889. 
Engineering and design for repair of East and West Piers, 
Section A, was initiated at a cost of $111,724. An 
adjustment of $3,181 was made in contract costs to 
maintenance dredging completed last FY. A contract for 
maintenance dredging was awarded and completed this FY 
at a cost of $214,856 removing 41,619 cubic yards of 
material. Engineering and design for maintenance 
dredging to be performed by contract next FY cost 
$10,695. Engineering, design, real estate, surveys, 
supervision and administration cost $188,614. 
All work authorized under previous Acts was completed 
in 1938. Total cost for existing project to end of FY was 
$13,874,411, of which $953,903 was for new work and 
$12,920,508 for maintenance. 
47. PENSAUKEE HARBOR, WI 
Location. On west shore of Green Bay, about 22 miles 
northeasterly from Green Bay Harbor, and about 33 miles 
southwesterly from Menominee Harbor, MI and WI. (See 
NOAA Nautical Chart 14910.) 
Previous projects. For details, see Annual Report for 
1899, page 2734, and Annual Report for 1938, page 
1429. 
Existing project. An entrance channel 100 feet wide 
and 8 feet deep at low water datum from the depth in 
Green Bay about 4,300 feet to mouth of Pensaukee River. 
Fluctuations of water level are seasonal changes of about 
one-half foot above or below the annual mean stage, and 
extreme fluctuations of a temporary nature, due to wind 
and barometric pressure, of about 2 feet above or below 
mean lake level prevailing at the time. New work for 
completed project cost $24,851, exclusive of amounts 
expended under previous projects. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. Small private wharves along lower 
half mile of river, used by the local fishing interests. 
Ample space is available for additional fishing wharves 
when required. Facilities considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys and miscellaneous inspections and 
reports were performed by Government forces and 
contract at a cost of $78,581. Engineering and design for 
a maintenance dredging contract to be awarded next FY 
cost $55,947. 
The existing project was complete in 1938. Total costs 
at the end of FY were $424,216 of which $34,035 was for 
new work and $390,181 was for maintenance. 
48. PENTWATER HARBOR, MI 
Location. On east shore of Lake Michigan, 146 miles 
northeasterly from Chicago, IL, and 14 miles southerly 
from Ludington, MI. (See NOAA Nautical Chart 14907.) 
Existing project. Provides for widening old entrance 
channel to 150 feet between parallel piers and revetments, 
channel to extend from Lake Michigan to Pentwater Lake, 
with a depth of 16 feet. Piers and revetments are built of 
stone filled timber cribs and piling and capped with 
concrete. The 200-foot extension to south pier portion of 
project is considered inactive. Estimated cost (1954) of 
this portion is $65,100. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. None required. 
Terminal facilities. Several small privately owned 
wharves on west end of Pentwater Lake. The City and 
Michigan Waterways Commission jointly constructed a 
dock on northwest side of Pentwater Lake for public use. 
Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $39,598. 
Repairs to safety features cost $7,007. A maintenance 
dredging contract was awarded and completed removing 
24,000 cubic yards of shoal material at a cost of $81,500. 
21-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Engineering, design, surveys, supervision and 
administration cost $29,417. 
Existing project was completed in 1959 except for a 
200-foot extension to the south pier which is not 
considered necessary under present conditions. For 
additional details see page 1468 of Annual Report for 
1962. Total cost for existing project to end of FY was 
$4,391,576, of which $179,899 was for new work, and 
$4,211,677 for maintenance. 
49. PORT AUSTIN HARBOR, MI 
Location. On west shore of Lake Huron at extreme 
southeastern limit of Saginaw Bay, and 29 miles south of 
AuSable River (Oscoda). (See NOAA Nautical Chart 
14863.) 
Existing project. A harbor of refuge at the mouth of 
Bird Creek, consisting of a harbor basin dredged to a 
depth of 10 feet protected by a breakwater structure, and 
for dredging an entrance channel to the harbor basin to a 
depth of 12 feet. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A number of docks near mouth of 
Bird Creek and a State-owned dock inside breakwater. 
Facilities accommodate recreational craft and are 
considered adequate for existing traffic. 
Operations during fiscal year. New Work: Funds 
were received from the State of Michigan for its half of 
the total construction cost for construction of the 
breakwater completed in FY 90. Maintenance: Condition 
surveys and environmental studies were performed by 
Government forces at a cost of $2,957. 
Total cost for existing project to end of FY was 
$5,296,856, of which $3,363,334 was for new work 
(includes $1,239,219 contributed funds) and $1,933,522 
for maintenance. 
50. PORT SANILAC HARBOR, MI 
Location. On southwest shore of Lake Huron, 30 miles 
north of Port Huron, MI. (See NOAA Nautical Chart 
14862.) 
Existing project. Provides for a harbor of refuge 
protected by breakwater structures extending to 12-foot 
depth contour in lake; for dredging a harbor basin 10 feet 
deep; for dredging an entrance channel 12 feet deep; a 70- 
foot extension of the south breakwater; a 300-foot arm 
added to the north breakwater; and riprap placed at the 
lakeward side of the breakwater addition. (See Table 21- 
B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There is one privately owned dock 
used principally as a fishing terminal by owner and a 
municipally owned pier for recreational craft. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys and miscellaneous inspections and 
reports were performed by Government forces and 
contract at a cost of $4,669. Repairs to safety features 
cost $1,737. Adjustments of -$9,743 were made in costs 
for maintenance dredging contract completed last FY. 
Supervision and administration to close-out contract cost 
$2,279. Monitoring under Section 111 mitigation cost 
$22,216. 
The project was completed in 1951 except for latest 
modification which was completed in FY 76. The 
breakwaters are in good condition. Total cost for existing 
project to end of FY was $5,056,321, of which 
$1,733,071 was for new work (includes $487,108 
contributed funds) and $3,323,250 for maintenance 
(includes $115,000 contributed funds). 
51. PORT WASHINGTON HARBOR, WI 
Location. On the west shore of Lake Michigan, about 
53 miles south of Manitowoc and about 29 miles north of 
Milwaukee, WI. (See NOAA Nautical Chart 14904.) 
Previous project. For details, see page 1938 of Annual 
Report for 1915, page 1459 of Annual Report for 1938, 
and page 30-14 of Chicago District Annual Report for 
1975. 
Existing project. See Chicago District Annual Report 
for 1979, Table 30-C, page 30-27. 
Construction of a small boat harbor within the existing 
harbor was authorized by the Chief of Engineers, June 12, 
21-28

DETROIT, MI DISTRICT 
1975, under authority of Section 107, 1960 River and 
Harbor Act, as amended. 
Local cooperation. Fully complied with. 
Terminal facilities. There is one coal wharf, a 
petroleum tank farm and several fishing wharves. City 
provided a wharf which is open to public use. Facilities 
are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$17,560. Repairs to the North Breakwater, Sections A, 
B, C, and D, were performed by the U. S. Cranebarge 
MANITOWOC at a cost of $181,402. Safety maintenance 
was performed by hired labor at a cost of $1,711. 
Supervision and administration cost $6,479. 
The existing project was completed in 1936. The 1958 
modification was deauthorized in 1977. Total cost for 
existing project to end of FY was $7,068,431, of which 
$4,206,204 was for new work (includes $1,624,000 
contributed funds) and $2,862,227 for maintenance. 
52. PORT WING HARBOR, WI 
Location. On south shore of Lake Superior, 34 miles 
easterly from Duluth, MN. (See NOAA Nautical Chart 
14966.) 
Existing project. Provides for two parallel piers at 
entrance, 835 and 1,017 feet long, respectively, 200 feet 
apart; an entrance channel between piers 150 feet wide 
with 15-foot depth; an irregular-shaped turning basin 15 
feet deep at inner end of piers from which two inner 
channels with 8-foot depth extend. One of these is 60 feet 
wide extending southerly for 340 feet and one 70 feet 
wide extending easterly 1,170 feet. 
Portion of dredging of entrance channel to complete 
project width and depth is considered unnecessary to meet 
present navigation requirements. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are four privately owned 
fishing wharves which are considered adequate for existing 
conditions. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, and 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $6,428. 
Existing project is complete, except channel between 
piers, and has been dredged to only a 100-foot width. 
Widening the channel an additional 50 feet was considered 
unnecessary to meet present navigation requirements. 
That work was classified inactive and deauthorized on 
August 5, 1977, under Section 12 of PL 93-251. Land 
owned by the United States totals 7.80 acres. Total cost 
for existing project to end of FY was $1,054,541, of 
which $63,393 was for new work and $991,148 for 
maintenance. 
53. PRESQUE ISLE HARBOR, MI 
Location. On south shore of Lake Superior at 
Marquette, MI. It is an indentation about 1.5 miles long 
and one-half mile wide in shore behind Presque Isle Point. 
(See NOAA Nautical Chart 14970.) 
Existing project. A breakwater off Presque Isle Point 
and dredging harbor to depth of 28 feet at inner portion 
with 30 feet at entrance. For details see page 1021 of 
1965 Annual Report. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. One merchandise and petroleum 
receiving wharf and one ore dock. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Environmental studies, real estate activities, and 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $26,885. Engineering and 
design for repair of Breakwater, Section B, continued at 
a of cost $93,960. 
Total cost of existing project to end of FY was 
$2,446,887, of which $1,252,192 was for new work, 
$1,118,195 for maintenance and $76,500 for 
rehabilitation. 
54. ROUGE RIVER, MI 
Location. Rises in Oakland and Washtenaw Counties, 
MI, 30 miles long, flows southeasterly through Wayne 
21-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
County, and joins Detroit River at westerly limit of city of 
Detroit. (See NOAA Nautical Chart 14854.) 
Previous project. For details see page 1530 of Annual 
Report for 1932, and page 1558 of Annual Report for 
1938. 
Existing project. Provides for: (a) Main channel from 
Detroit River through Short Cut Canal extending to 
upstream limit of the project, a distance of 3.5 miles. 
Project depths are 25 and 21 feet in navigation channel, 21 
feet in turning basin, and 13 feet in upper reach of 
project. (b) Old Channel from Detroit River extending to 
junction of Old Channel with Short Cut Canal. Project 
depths are 25, 18, 17, and 21 feet. For additional details 
see page 1324 of Annual Report for 1963. In 1973, work 
authorized by the 1962 River and Harbor Act was 
reclassified from the active to inactive category. 
Estimated cost (1972) of this work is $880,000. Except 
for dredging 25-foot channel 1,150 feet upstream from 
mouth of Old Channel, work authorized in Act of August 
30, 1935, is considered inactive. Estimated cost (1958) of 
inactive portion is $255,000. Work authorized by Act of 
July 3, 1958, is considered inactive. Estimated cost 
(1960) of this work is $210,000. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Act of October 23, 1962, requires 
local interests to provide lands and rights-of-way for 
construction upon request of the Chief of Engineers; hold 
the United States free from damages; provide terminal 
facilities to accommodate prospective commerce 
considered in report of District Engineer; dredge and 
maintain areas between the Federal improvement and 
terminal facilities to depths commensurate with improved 
Federal channel; make alterations in docks, bulkheads and 
other structures, and take such other measures as may be 
necessary to assure stability of banks adjacent to channel; 
and provide bridge protection. The assurances of local 
cooperation for the River and Harbor Act of 1962 were 
furnished by the Michigan State Waterways Commission 
and accepted on January 7, 1965. Fulfillment of all items 
of local cooperation has not been accomplished. 
Terminal facilities. Numerous large commercial docks 
for handling various type cargo. Details on actual port 
and harbor facilities are contained in the Port Series No. 
45 (revised 1984) prepared and published by the Water 
Resources Support Center. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspections and reports were performed by Government 
forces and contract at a cost of $101,107. A contract was 
awarded for dredging the turning basin in the amount of 
$220,978. Approximately 5,744 cubic yards of shoal 
material was removed this FY at a cost of $40,209. 
Engineering, design, surveys, supervision and 
administration cost $34,542. 
Work authorized before 1962 modification is complete 
or deauthorized. For additional details on completion of 
existing project see Annual Report for 1962. Total cost 
for existing project to end of FY was $35,936,418, of 
which $675,251 was for new work and $35,261,167 for 
maintenance. In addition, $29,563 was expended from 
Emergency Relief Act Funds for new work. 
55. SAGINAW RIVER, MI 
Location. Formed by union of Tittabawassee and 
Shiawassee Rivers, 22 miles long, and flows northerly into 
extreme inner end of Saginaw Bay, Lake Huron. Cities 
of Saginaw and Bay City are on the river. (See NOAA 
Nautical Chart 14867.) 
Previous project. For details, see page 1957 of Annual 
Report for 1915; and page 1550 of Annual Report for 
1938. 
Existing project. Provides for an entrance channel 27 
feet deep and 350 feet wide from 27-foot contour in 
Saginaw Bay to river mouth; thence a channel 26 feet 
deep and 200 feet wide to New York Central Railroad 
Bridge at Bay City; thence 22 feet deep and 200 feet wide 
to C&O Railroad Bridge in Saginaw; thence 16.5 feet 
deep and 200 feet wide to upstream limit at Green Point. 
Project also provides for five turning basins; one 25 feet 
deep at Essexville, 600 feet wide with a maximum length 
of 1,850 feet; one 22 feet deep on east side of channel 
about 1 mile upstream from Cass Avenue in Bay City, 650 
feet wide and 1,000 feet long; one 20 feet deep at 
Carrollton, 100 to 300 feet wide and 900 feet long; one 20 
feet deep downstream from C&O Bridge in Saginaw, 650 
feet wide and 1,000 feet long; and one 15 feet deep 
between Bristol Street Bridge and New York Central 
Railroad Bridge in Saginaw. (See Table 21-B for 
authorizing legislation.) 
Local cooperation. Fully complied with. 
21-30

DETROIT, MI DISTRICT 
Terminal facilities. Numerous large commercial docks 
for handling a great variety of cargo. Details on actual 
port and harbor facilities are in Port Series No. 45 
(revised 1984) prepared and published by the Water 
Resources Support Center. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, support of 
water control center, miscellaneous inspections and reports 
were performed by Government forces and contract at a 
cost of $460,775. An adjustment of $127,972 and 46,705 
cubic yards was made to the contract for maintenance 
dredging completed last FY. A contract for maintenance 
dredging of the Bay and River Section was awarded this 
FY in the amount of $2,370,000. The contract was 
approximately 4% complete at the end of the FY at a cost 
of $86,000, removing 11,509 cubic yards of shoal 
material. Maintenance of disposal area performed by the 
U. S. Cranebarge VELER cost $320,457. Engineering, 
design, real estate, surveys, supervision and administration 
cost $102,578. Engineering, design, and real estate for 
construction of a diked disposal area for upper Saginaw 
was continued at a cost of $292,307. 
Existing project is complete except for small part of the 
work authorized by the Act of October 23, 1962. Section 
D (Sixth Street Turning Basin) of the 1962 Act is 
complete except for the channel portion, which is pending 
modification. Total cost for existing project to end of FY 
was $80,241,410, of which $14,930,727 was for new 
work and $65,310,683 for maintenance. 
56. ST. CLAIR RIVER, MI 
Location. A 40 mile long section of Great Lakes 
connecting channels which flows southerly from Lake 
Huron and discharges into Lake St. Clair. (See NOAA 
Nautical Chart 14852.) 
Existing project. Provides for channels through St. 
Clair River, which, at low water datum, are suitable for 
vessels drawing 25.5 feet. Project also provides for 
improvement of North Channel outlet, 100 feet wide and 
10 feet deep, for recreational craft. Project depths are 
referred to low water datums for Lakes Huron and St. 
Clair; 577.5 and 572.3 feet above mean water level at 
Rimouski, Quebec, IGLD 1985. (See Tables 21-B and 
21-H for authorizing legislation and features of existing 
project.) Act of July 24, 1946, provides for widening and 
deepening of southeast bend and improvement of outlet of 
north channel at an estimated cost (1986) of $870,000; 
$435,000 Federal and $435,000 non-Federal. On June 
16, 1969, the Director of Civil Works approved 
substitution of the middle channel of the St. Clair River 
for the authorized north channel. Subsequently, however, 
the work authorized by the River and Harbor Act of July 
24, 1946, was deauthorized by the WRDA of 1986; PL 
99-662, Nov. 17, 1986, 99th Congress, Title X. 
Local cooperation. None required. 
Terminal facilities. This improvement serves through 
commerce, between upper and lower Great Lakes, and has 
not materially influenced terminal facilities along its route. 
A number of privately owned piers and wharves are at 
Port Huron, Marysville, St. Clair, and Marine City, MI, 
which handle coal, limestone, petroleum products, woodpulp, 
salt and general cargo. These installations satisfy 
present commerce requirements. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, support of 
water control center, miscellaneous inspections and reports 
were performed by Government forces and contract at a 
cost of $195,934. A contract in the amount of $841,650 
was awarded for maintenance dredging. The contract was 
approximately 67% complete at the end of the FY, 
removing 68,187 cubic yards of shoal material at a cost of 
$566,688. Location and removal of obstructions, and 
dock repairs performed by the U. S. Derrickbarge 
HURON and the U. S. Cranebarge VELER, respectively, 
cost $552,141. Maintenance of the disposal area was 
performed by hired labor at a cost of $21,452. 
Engineering, design, real estate, surveys, supervision and 
administration cost $88,297. 
Existing project is complete. Total cost for existing 
project to end of FY was $41,165,813, of which 
$19,213,246 was for new work and $21,952,567 for 
maintenance. 
57. ST. JOSEPH HARBOR, MI 
Location. On east shore of Lake Michigan, 60 miles 
easterly from Chicago, IL, and 24 miles southerly from 
South Haven, MI. (See NOAA Nautical Chart 14930.) 
Previous project. For details see page 1945 of Annual 
Report for 1915, and page 1470 of Annual Report for 
1938. 
21-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. Provides for protecting mouth of St. 
Joseph River by two piers, 250 to 325 feet apart at their 
inner and outer ends, respectively, having lengths of 2,758 
feet on north side and 2,603 feet on south side; for a 
channel 21 feet deep from Lake Michigan to mouth of 
Benton Harbor Canal, a length of about 6,900 feet with 
widths of 265 feet at outer end of piers, 190 feet at inner 
end of piers and revetments, thence generally 215 feet to 
lower end of turning basin, increasing to 250 feet above 
the turning basin to mouth of Paw Paw River, thence 
generally 110 feet in Paw Paw River to mouth of Benton 
Harbor Canal; for dredging channel in Benton Harbor 
Canal up to west line of Riverview Drive extended 
northerly, to 18 feet deep and 80 feet wide; and a turning 
basin 18 feet deep on north side of channel above mouth 
of Morrison Channel and a turning basin 18 feet deep near 
mouth of Paw Paw River. Public Law 88-88 declared a 
portion of Benton Harbor Canal a non-navigable stream. 
(See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several commercial wharves for 
handling coal, building materials, petroleum products, and 
miscellaneous commodities. A package freight terminal 
and a public docking facility is also available. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces at a cost of $220,728. Hired labor 
cost for maintenance of disposal area and safety features 
was $21,204. A contract was awarded and completed this 
FY for maintenance dredging the Outer Channel, 
removing approximately 33,644 cubic yards of material at 
a cost of $106,501. This contract was also for beach 
nourishment. Another contract was awarded and 
completed for emergency maintenance dredging of the 
Inner Harbor and excavation and landfill disposal. 
Approximately 21,182 cubic yards of dredged material 
was removed at a cost of $96,624, and excavation of 
23,734 cubic yards of existing material cost $196,473. 
Engineering, design, surveys, real estate, and supervision 
and administration cost $118,632. Engineering, design 
and real estate for disposal area and polluted dredged 
material continued at a cost of $79,527. Under the 
Section 111 PL 90-483 program, $41,297 was expended 
for monitoring, condition surveys, miscellaneous 
inspections and reports. An adjustment of $5,067 was 
made in contract cost for the placement of sand and stone, 
under Section 111, awarded last FY. Beach nourishment 
in conjunction with above maintenance dredging contract 
cost $18,794. Engineering and design to place sand on 
the beach next FY cost $4,126. Engineering, design, 
supervision and administration cost $14,744 for Section 
111. 
Existing project was completed in 1956. The structures 
are in generally good condition. For additional details on 
completion of existing project see page 1454 of Annual 
Report for 1962. Total cost for existing project to end of 
FY was $23,719,929, of which $1,804,485 was for new 
work, $20,953,228 for maintenance and $962,216 for 
rehabilitation. 
58. ST. MARYS RIVER, MI 
Location. A Great Lakes connecting channel about 63 
miles long, flows southeasterly between State of Michigan 
and Providence of Ontario, Canada, from eastern end of 
Lake Superior into northern end of Lake Huron. (See 
NOAA Nautical Charts 14882, 14883, and 14884.) At 
Sault Ste. Marie, MI, about 14 miles downstream from 
Lake Superior, there are four parallel locks and a 
hydroelectric powerplant. 
Previous project. For details see page 1955, Annual 
Report for 1915; and page 1529, Annual Report for 1938. 
Existing project. Channels permitting 25.5 foot draft 
navigation in St. Marys River and Lake Superior and Lake 
Huron approaches thereto; constructing an operating four 
locks and two canals; constructing an electric plant of 
14,000 kilowatt capacity (45,000 kilowatt ultimate 
capacity) constructing anchorage areas in river above and 
below locks; and constructing various other works in 
conjunction with project. Subsequently, in 1932, the Unit 
10 powerhouse was installed raising the capacity to 18,400 
kilowatts (45,000 ultimate capacity). Original State Locks 
were operated and maintained under permanent indefinite 
appropriation from June 9, 1881, to November 2, 1886, 
after which they were destroyed by excavation for the Poe 
Lock in 1896. Weitzel Lock, destroyed in 1942 by 
excavation for MacArthur Lock, was operated and 
maintained under the same appropriation from September 
1, 1881, to June 30, 1935. Poe Lock was operated and 
maintained under the same appropriation from August 3, 
1896, Davis Lock from October 21, 1914, and Sabin Lock 
from September 18, 1919, to end of FY 1935. The 1,200 
foot by 110 foot new Poe Lock was authorized in 1962 
21-32

DETROIT, MI DISTRICT 
and put into operation in 1968. Details of existing project 
are set forth in Table 21-F. 
Project depths are referred to low water datum 
corresponding to sloping surface of river as follows: 
Above locks: When water surface of Lake Superior is at 
elevation 601.1 feet and at upstream side of locks is 600.6 
feet above mean water level at Rimouski, Quebec, IGLD 
1985. Below locks: When water surface at downstream 
side of locks is at elevation 578.4 feet and Lake Huron is 
577.5 feet above mean water level at Rimouski, Quebec, 
IGLD 1985. Estimated (1974) cost for new work is 
$163,087,000. (See Table 21-B for authorizing 
legislation.) 
The WRDA of 1986 authorized construction of a second 
lock 1,294 feet in length, 115 feet in width, and 32 feet in 
depth, adjacent to the existing lock. The replacement lock 
is to be located in the North Canal of the St. Marys Falls 
Canal at Sault Ste. Marie, MI, on the site of the existing 
Davis and Sabin Locks. Material removed during 
construction of the replacement lock will be placed on the 
Northwest Pier to serve as a windbreak for downbound 
vessels approaching the lock. Estimated cost (Oct. 90) is 
$174,200,000 Federal and $93,800,000 non-Federal. 
Local cooperation. Fully complied with for completed 
portion of project. Local cooperation items for the newly 
authorized project in the WRDA of 1986 (PL 99-662), are 
as follows: 
(a) Provide without cost to the United States all lands, 
easements, and rights-of-way necessary for implementation 
and later maintenance of the proposed project, and for aids 
to navigation upon the request of the Chief of Engineers, 
including suitable areas determined by the Chief of 
Engineers to be required in the general public interest for 
initial and later disposal of dredged/demolition material 
and including necessary retaining dikes, bulkheads, and 
embankments therefor, or the costs of such retaining 
works; 
(b) Hold and save the United states free from damages 
due to the implementation and maintenance of the project, 
not including damages due to the fault or negligence of the 
United States or its contractors; 
(c) Accomplish without cost to the United States such 
alterations and relocations of pipelines, powerlines, cables, 
sewer, water supply, drainage, and other utilities, 
structures, and improvements made necessary by the 
project. (Any such costs of the items on Federal property 
at the locks, would be part of the total construction cost 
and not separable local sponsor cost.); 
(d) Contribute in cash 25 percent of the total cost of 
construction of general navigation facilities, exclusive of 
aids to navigation, a contribution presently estimated at 
$67,000,000. The estimated cash contribution of 
$67,000,000 to be paid in lump sum prior to initiation of 
construction, or in annual installments during the 
construction period at a rate proportionate to the proposed 
or scheduled expenditure of Federal funds as required by 
the Chief of Engineers, or under another arrangement 
satisfactory to the Secretary of the Army, the final 
apportionment of cost to be made after actual costs have 
been determined; 
(e) Repay, with interest, over a period of up to 30 years 
following project completion, 10 percent of the total cost 
of construction of general navigation facilities, an amount 
presently estimated at $26,800,000. The Secretary of the 
Army may count against all or part of the 10 percent 
repayment, the amount of the local contribution for lands, 
easements, rights-of-way, dredged/demolition material 
disposal sites and relocations. In no case are these costs 
to count against the cash payment during construction, and 
in no case would the amount waived exceed 10 percent of 
project cost; and 
(f) Any construction needed to prevent/mitigate for 
erosion or shoaling attributed to the lock would be cost 
shared in the same proportion as the project. 
Terminal facilities. This improvement serves through 
commerce between Lake Superior and lower lakes and has 
not materially influenced terminal facilities at localities 
along its route. Three piers at Sault Ste. Marie receive 
coal and petroleum products. Limestone is shipped from 
a pier at Drummond Island. Vessel refueling stations are 
at Lime Island and village of DeTour; they receive coal 
and petroleum products. Present terminals satisfy current 
traffic requirements. 
Operations during fiscal year. Operations, 
maintenance, and care of locks: Two canals and three 
locks were operated (the fourth lock, Davis, was out of 
service) as required. Necessary repairs and improvements 
were made thereto and to appurtenant structures and 
equipment. Canals were open to navigation 295 days 
during the period October 1, 1991 through September 30, 
1992. A total of 11,386 vessels, aggregating 86,058,560 
21-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
short tons of freight and 231,688 passengers passed 
through the MacArthur, Poe and Sabin Locks. Cost for 
operation, maintenance, and care of the locks during the 
FY was $7,471,880, which includes construction of a 
building to house the generator at a cost of $93,764, 
preparation of a reconnaissance report for major 
rehabilitation of the Davis Lock at $76,350, extended 
season operation and maintenance at a cost of $299,101, 
and $118,756 for operation and maintenance of the 
Gatelifter PAUL BUNYAN. 
Powerhouse and equipment: A total of 156,300,930 
kilowatt-hours of power was generated this FY. Income 
from the sale of power, sent to the U.S. Treasury, 
amounted to $1,837,763. Two hydroelectric powerhouses 
were operated and maintained at a cost of $903,375 during 
the FY which includes a deduction of $70,096 for 
interdepartmental electricity sold but not paid for. Total 
costs also includes supervision and administration to closeout 
contract completed last FY for the repair and testing 
of the hydroelectric Unit 10 generator at a cost of $3,080, 
assistance from the Hydroelectric Design Center continued 
benchmark testing of the generators and turbines, 
completion of plans and specifications and award of a 
contract in the amount of $628,400 (to be performed next 
FY) for replacement of four (4) main power feeder cables, 
and completion of a reconnaissance letter report and plans 
and specifications for generator rewind of Units 1, 2, 3 
and 3A all at a cost of $179,242. 
Other operation and care items: Building and grounds 
were operated and maintained, condition surveys, 
operations studies, real estate, environmental studies, 
miscellaneous inspections and reports were performed at 
a cost of $2,184,479, which includes a custodial, snow 
removal and grounds upkeep contract for $302,886 and a 
service contract for security measures for $477,984. 
Work performed on the Compensating Gates cost $35,959. 
A contract for construction of a flammable liquid storage 
building was awarded and completed at a cost of 
$108,539. Completion of plans and specifications, and 
engineering and design performed during construction of 
the flammable liquid storage building was performed at a 
cost of $6,618. Supervision and administration of the 
contract cost $20,495. Winter and extended navigation 
season studies, ice measurements, and weather monitoring 
cost $388,127. 
Channels and canals: St. Marys River channels and 
canal approach depths were surveyed by sweeping. 
Removal of shoals in the St. Marys River channels and 
canal approaches was accomplished by hired labor with 
U.S. Derrickbarge NICOLET and the U. S. Cranebarge 
HARVEY at a cost of $1,662,582. Supervision and 
administration cost $242,387. 
Other miscellaneous items: Engineering and design for 
the master plan for the facility was performed at a cost of 
$29,875. Plans and specifications for various repair 
contracts to be awarded next FY cost $147,100. 
Recreational facilities: Information center, comfort 
stations, park, fountain, observation and overlook 
platforms were maintained at a cost of $101,398 and a 
janitorial contract for the Information Center cost 
$25,874. A contract for the operation of the Visitors 
Center cost $29,634. A grand total of 862,950 people 
visited the Soo Locks. 
Total project costs in FY 92 amounted to $13,358,322. 
Project in effect prior to modification of March 21, 
1956, is complete and work authorized by 1956 
modification to provide a safe draft of 25.5 feet for both 
upbound and downbound traffic is also complete. Public 
Works Acceleration Funds used for maintenance were 
$118,000. Total cost for existing project to end of FY 
was $407,891,319, of which $160,657,070 was for new 
work and $247,234,249 for maintenance. 
59. SAUGATUCK HARBOR AND 
KALAMAZOO RIVER, MI 
Location. Harbor is on east shore of Lake Michigan, 
90 miles northeasterly from Chicago, IL, and 22 miles 
northerly from South Haven, MI. (See NOAA Nautical 
Chart 14906.) 
Previous project. For details see page 1947 of Annual 
Report for 1915, and page 1475 of Annual Report for 
1938. 
Existing project. Entrance channel protected by parallel 
piers at mouth of Kalamazoo River and a river channel to 
village of Saugatuck, MI. Project depths: 16 feet in 
entrance channel, 14 feet in river channel. Additional 
details on page 1456 of 1962 Annual Report. (See Table 
21-B for authorizing legislation.) 
21-34

DETROIT, MI DISTRICT 
Local cooperation. None required. 
Terminal facilities. At village of Saugatuck, MI, there 
are several landing places for recreational craft and one 
for small commercial vessels. At village of Douglas, MI, 
there is a landing pier. Facilities are considered adequate 
for present traffic. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, miscellaneous inspections 
and reports were performed by Government forces at a 
cost of $19,596. Repairs to the North and South Pier 
Heads were performed by the U. S. Cranebarge 
MANITOWOC at a cost of $131,401. Safety maintenance 
performed by hired labor cost $100. Supervision and 
administration cost $5,544. 
Existing project was completed in 1903. Total cost for 
existing project to end of FY was $3,912,255, of which 
$364,527 was for new work and $3,547,728 for 
maintenance. 
60. SEBEWAING RIVER, MI 
Location. At mouth of Sebewaing River on south shore 
of Saginaw Bay about 10 miles south of Bay Port, MI. 
(See NOAA Nautical Chart 14863.) 
Previous project. For details see page 1007 of Annual 
Report for 1912. 
Existing project. Provides for an entrance channel 8 
feet deep, 100 feet wide, and about 15,000 feet long in 
Saginaw Bay. (See Table 21-B for authorizing 
legislation.) 
Terminal facilities. A number of small wharves used 
by fishing vessels and other light-draft craft are along the 
river. Facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, environmental studies, miscellaneous 
inspection and reports were performed by Government 
forces at a cost of $12,472. 
Existing project was completed in 1903. Total cost for 
existing project to end of FY was $3,530,756, of which 
$35,573 was for new work and $3,495,183 for 
maintenance. 
61. SHEBOYGAN HARBOR, WI 
Location. On west shore of Lake Michigan about 26 
miles south of Manitowoc and about 55 miles north of 
Milwaukee, WI. (See NOAA Nautical Chart 14922.) 
Previous project. See page 1381 of Annual Report for 
1962. 
Existing project. See Chicago District Annual Report 
for 1979, Table 30-C, page 30-27. 
For detailed description see page 1230 of Annual Report 
for 1963. New work for project as completed cost 
$648,271, exclusive of amounts expended on previous 
projects. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Three wharves for handling coal, 
petroleum products and miscellaneous commodities. City 
provided a public wharf. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $55,138. 
Repairs to the North Breakwater, Sections G and H, and 
South Pier, Sections I, G, J, and K, were performed by 
the U. S. Cranebarge MANITOWOC at a cost of 
$95,196. Minor safety repairs cost $319. Engineering 
and design for repair of South Pier, Section N, continued 
at a cost of $54,869. Engineering and design was initiated 
for repair of North Pier, Sections A and B, at a cost of 
$5,063. An adjustment of $5,000 was made in contract 
cost for maintenance dredging completed last FY. 
Supervision and administration for close-out cost $12,653. 
Existing project was completed in 1904. Construction 
of north breakwater was commenced in October 1913 and 
completed in October 1915. Dredging entrance channel 
to existing project depth was commenced in June and 
completed in July 1938. Work on 1954 modification was 
completed in December 1956. Piers and breakwaters are 
in generally good condition. Inner 260 feet of south pier 
was replaced with a revetment by private interests under 
permit granted July 16, 1931, by the Secretary of War. 
Piers, therefore, are maintained only for a length of about 
2,490 feet. Sheboygan River is navigable about 2.4 miles 
above its mouth for craft drawing not more than 2 feet. 
21-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Total cost for existing project to end of FY was 
$9,150,645, of which $1,136,088 was for new work, 
$7,405,529 for maintenance and $609,028 for 
rehabilitation. 
62. SOUTH HAVEN HARBOR, MI 
Location. On east shore of Lake Michigan, 77 miles 
northeasterly from Chicago, IL, and 24 miles northerly 
from St. Joseph, MI. (See NOAA Nautical Chart 14906.) 
Previous project. For details see page 1947 of Annual 
Report for 1915, and page 1473 of Annual Report for 
1938. 
Existing project. An entrance channel protected by 
parallel piers and revetments at mouth of Black River, a 
river channel and a turning basin. Project depths are 21 
feet in entrance channel and 19 feet in river channel and 
turning basin. For additional details see page 1455 of 
Annual Report for 1962. (See Table 21-B for authorizing 
legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. Several wharves for handling coal, 
building materials, wood-pulp, fish, and miscellaneous 
commodities will have warehouses. Facilities satisfy 
current commerce requirements. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $48,415. 
Repair of South Pier, Sections A, and K-M, was 
performed by the U. S. Cranebarge MANITOWOC at a 
cost of $81,982. Safety maintenance performed by hired 
labor cost $3,464. Engineering and design was initiated 
for repairs to South Pier and Revetment, Sections A, M-1, 
and N, at a cost of $5,365. Supervision and 
administration cost $3,382. Condition surveys in 
connection with Section 111 were performed at a cost of 
$404. 
Existing project was completed in 1960. Project now 
being maintained to 14-foot and 12-foot depths, 
respectively (in lieu of the 21 feet and 19 feet authorized), 
which is adequate for current usage. For additional details 
on completion of existing project see page 1456 of Annual 
Report for 1962. Total cost for existing project to end of 
FY was $7,847,335, of which $984,426 was for new 
work, $5,230,833 for maintenance and $1,632,076 for 
rehabilitation. 
63. STURGEON BAY AND LAKE 
MICHIGAN SHIP CANAL, WI 
Location. On west shore of Lake Michigan about 52 
miles northeast of Green Bay and about 128 miles north 
of Milwaukee, WI. (See NOAA Nautical Chart 14919.) 
Previous project. See page 1373 of Annual Report for 
1962. 
Existing project. See Chicago District Annual Report 
for 1979, Table 31-C, page 30-27. For detailed 
description, see page 1223, Annual Report for 1963. (See 
Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. As the canal and connecting 
channel is a through waterway, only terminal facilities are 
in city of Sturgeon Bay, 4 miles from west end of revetted 
portion of canal. These facilities consist of two wharves 
for handling coal, petroleum products and miscellaneous 
commodities, and four shipbuilding yards. City of 
Sturgeon Bay provided a public wharf about 5 miles 
northwesterly from city of Sturgeon Bay. Two major 
shipyards are located in Sturgeon Bay where repair 
facilities are available including dry docks, marine 
railways and hoists. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, environmental studies, 
miscellaneous inspections and reports were performed by 
Government forces and contract at a cost of $143,109. 
Repairs to the North Breakwater, Sections A, B, C, and 
D, South Detached Breakwater, Section E, and South 
Revetment, Section H, performed by the U. S. 
Cranebarge MANITOWOC cost $189,780. Safety 
maintenance was performed by hired labor at a cost of 
$18,110. Engineering and design for construction of 
offloading disposal facility to be performed by contract 
continued at a cost of $22,678. Engineering and design 
was initiated for repair of South Detached Breakwater, 
Sections D and E, and South Revetment, Section N, at a 
cost of $9,692. Supervision and administration cost 
$11,537. 
21-36

DETROIT, MI DISTRICT 
Total cost for existing project to end of FY was 
$10,806,928, of which $1,059,722 was for new work, 
$8,862,307 for maintenance and $884,899 for 
rehabilitation. In addition, $235,940 was expended 
between April 25, 1893, and June 30, 1917, on operating 
and care of works of improvements under provision of 
permanent indefinite appropriations for such purposes. 
64. TWO HARBORS, MN 
Location. Harbor is on north shore of Lake Superior, 
27 miles northeasterly from Duluth, MN. (See NOAA 
Nautical Chart 14966.) 
Existing project. Narrowing natural entrance by 
construction of two breakwaters, 1,628 and 900 feet long, 
from eastern and western points of bay, respectively; and 
dredging a maneuvering area on north side of harbor to 28 
and 30 feet deep. A walkway on east breakwater is 
provided for public recreational use. For details see page 
1026 of Annual Report for 1965. Dredging to deepen 
areas along easterly and northerly edges of channel was 
completed in 1980. This portion of project was 
reclassified from the "inactive" to "active" category in 
1973. (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. A section 
221 local cooperation agreement was entered into with the 
city of Two Harbors on August 14, 1978. 
Terminal facilities. No publicly owned wharves. 
Three ore docks, tug wharf, an unused coal dock, and 
merchandise wharf are privately owned. Facilities 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$7,899. A contract awarded in FY 91 for the repair of 
the West Pier, Section C, was 99% complete at the end of 
FY at a cost of $1,211,032. Engineering, design, and 
supervision and administration cost $154,421. 
The existing project is complete. Total cost for existing 
project to end of FY was $9,220,286, of which 
$4,170,710 was for new work and $5,049,576 for 
maintenance. 
65. TWO RIVERS HARBOR, WI 
Location. On west shore of Lake Michigan about 82 
miles north of Milwaukee and about 101 miles from Green 
Bay, WI, via Sturgeon Bay Canal. (See NOAA Nautical 
Chart 14903.) 
Previous project. See page 1377, Annual Report for 
1962. 
Existing project. See Chicago District Annual Report 
for 1979, Table 30-C, page 30-28. 
For detailed description see page 1226 of Annual Report 
for 1963. Completed project cost $147,463, exclusive of 
the amount expended on previous projects. The 1935 
River and Harbor Act portion of project is essentially 
complete, except for dredging a 10-foot width along each 
side of the entrance channel between the piers. The 
uncompleted portion of the project authorized by the 1935 
R & H Act was deauthorized December 31, 1989, in 
accordance with Section 1001 of the WRDA of 1986 (PL 
99-662). (See Table 21-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. A coal wharf and several fishing 
wharves. City provided a wharf for receipt of petroleum 
products and public use. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, miscellaneous inspections 
and reports were performed by Government forces at a 
cost of $15,021. Repairs to the North Pier, Sections CD 
and D2, and South Pier, Sections C, D and DlI, were 
performed by the U. S. Cranebarge MANITOWOC at a 
cost of $139,248. Minor safety repairs cost $693. 
Supervision and administration cost $6,660. 
Existing project is complete except for portion 
deauthorized in December 1989. Present width of channel 
is considered adequate for present and reasonably 
prospective commerce. South Pier was completed in 1883 
and is in generally good condition. North Pier was 
completed in 1908. North Revetment, completed in 1917, 
was rebuilt in May to August 1962. Dredging entrance 
channel and inner basin to existing project depth was 
21-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
commenced in March and substantially completed in May 
1937. Total cost for existing project to end of FY was 
$7,644,771, of which $360,320 was for new work, 
$7,226,394 for maintenance, and $58,057 for minor 
rehabilitation. 
66. WHITE LAKE HARBOR, MI 
Location. On east shore of Lake Michigan 120 miles 
northeasterly from Chicago, IL, and 45 miles southerly 
from Ludington, MI. (See NOAA Nautical chart 14935.) 
Existing project. Parallel piers, revetments, and a 
channel 16 feet deep, 200 feet wide, 1,950 feet long, 
extending from Lake Michigan to White Lake. For 
additional details see page 1465 of Annual Report for 
1962. (See Table 21-B for authorizing legislation.) 
Local cooperation. None required. 
Terminal facilities. A privately owned chemical 
shipping dock on north side of lake about 3 miles from 
inner end of reverted entrance channel. Across lake, at 
village of Whitehall, there are several installations serving 
light draft vessels. These terminals satisfy present 
recreational and commercial traffic requirements. 
Operations during fiscal year. Maintenance: 
Condition and structure surveys, and miscellaneous 
inspections and reports were performed by Government 
forces at a cost of $17,567. Monitoring in connection 
with Section 111 of PL 90-483 was performed at a cost of 
$4,315. Supervision and administration for close-out of 
beach nourishment contract completed last FY cost $512. 
Existing project was completed in 1908. Stone was 
placed on the north and south revetments in FY 1972. 
The structures are in generally good condition. Project 
now being maintained to 14-foot depth authorized, which 
is adequate for current usage. Total cost for existing 
project to end of FY was $3,975,263, of which $457,562 
was for new work and $3,517,701 for maintenance. 
67. RECONNAISSANCE AND CONDITION 
SURVEYS 
See Table 21-J. 
68. OTHER AUTHORIZED 
NAVIGATION PROJECTS 
See Table 21-C. 
69. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to section 107. Public 
Law 86-645 (pre-authorization.) None. 
Beach Erosion Control 
70. AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
A beach erosion control project for 9,550 feet of 
publicly owned shore of Lake Michigan in Manitowoc 
County, WI, from Two Rivers to Manitowoc, was 
authorized by the River and Harbor Act of 1958. The Act 
authorized Federal participation in the project, which was 
completed by the Wisconsin State Highway Department in 
1963. The total cost of the project was $182,500, of 
which $60,500 was contributed by the Federal 
government, including $56,000 in reimbursement to the 
State of WI in 1964. 
71. EMERGENCY SHORE PROTECTION 
Authority for emergency streambank and shoreline 
protection of public works and non-profit services 
(Section 14 Flood Control Act of 1946, as amended). 
Baraga County, MI - Funds in the amount of $1,169 
were used in FY 92 for financial close-out of the 
completed project, which involved the construction of a 
stone revetment to protect 400 feet of Lake Superior 
shoreline adjacent to Highway U.S. 41. The project was 
completed July 31, 1991. 
Baraga County, Arnheim Bridge, MI - In FY 92, 
funds in the amount of $25,156 were used toward a 
feasibility study to determine if there is a Federal interest 
in providing shoreline erosion protection along three 
stretches of the Sturgeon River. The study was initiated 
in FY 91. 
21-38

DETROIT, MI DISTRICT 
Bay View, Bear Creek Township, MI - Funds in the 
amount of $25,709 were used in FY 92 for a feasibility 
study to determine if there is a Federal interest in 
providing shoreline erosion protection to approximately 
3,000 feet of sanitary sewer adjacent to Lake Michigan. 
The study was initiated in FY 91. 
Charlevoix County, East Jordan River, MI - In FY 
92, funds in the amount of $2,703 were used to financially 
close out the project. The project was completed in FY 
90. 
Fair Haven, MI - Due to real estate problems, the 
project was divided into two contracts. The first contract 
provided for construction of a stone revetment to protect 
222 feet of shoreline adjacent to State Highway M-29. 
The project was completed and its facilities turned over to 
the State on April 17, 1992. Costs in FY 92 were 
$23,516. 
Lakeshore Drive, Allegan County, MI - A feasibility 
study to determine if there is a Federal interest in 
providing shoreline erosion protection to 1,800 feet of 
Lakeshore Drive was completed. The project was 
terminated August 4, 1992, due to lack of economic 
justification. Costs in FY 92 were $6,616. 
Lake Michigan Shoreline, South Milwaukee, WI - A 
feasibility study to determine if there is a Federal interest 
in providing shoreline erosion protection to the outfall 
pipe of the city's Wastewater Treatment Plant, was 
completed; however, in addition to the shoreline erosion 
problems, unstable bluff conditions were identified which 
would have to be remedied prior to construction of any 
Federal shoreline protection project. Bluff modification 
options are being coordinated with the sponsor. Costs in 
FY 92 were $348. 
Memorial Drive, McKinley Park, WI - Funds in the 
amount of $3,228 were used in FY 92 to complete the 
plans and specifications. The project involves the 
construction of a stone revetment to protect 825 feet of the 
Lake Michigan shoreline adjacent to Lincoln Memorial 
Drive. 
Memorial Drive, Muskegon, MI - In FY 92, funds in 
the amount of $14,347 were used to complete the 
feasibility study to determine if there is a Federal interest 
in providing shoreline erosion protection along the eastern 
shoreline of Lake Michigan for 850 feet of erosion of 
Scenic Drive at Memorial Drive, and to initiate the Plans 
and Specifications for the project. 
Milwaukee South Shore Park, WI - Construction to 
protect 430 feet of Lake Michigan shoreline adjacent to 
the County's pavilion/bathhouse complex and its parking 
lot, was completed in FY 92 at a cost of $108,515. 
Scenic Drive, Duck Lake, MI - The completed project 
was turned over to the local sponsor on May 21, 1991. 
The Operation and Maintenance manual and financial 
close-out of the project were completed in FY 92. Funds 
of $2,695 were expended in FY 92. 
Sheboygan, WI - The plans and specifications for 
protection of 7,400 feet of Lake Michigan shoreline 
adjacent to the city's sanitary pump station and a 60-inch 
Sanitary Interceptor Sewer and related manholes were 
completed in FY 92. Costs in FY 92 were $772. 
St. Joseph River, Buchanan Township, MI - The 
feasibility study, to determine if there is a Federal interest 
in providing streambank erosion protection to 3,600 feet 
of Red Bud Trail, was continued in FY 92 at a cost of 
$16,824. 
72. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Beach erosion activities pursuant to Section 103 of the 
1962 River and Harbor Act. None. 
73. MITIGATION OF SHORE DAMAGES 
Mitigation of Shore Damages pursuant to Section 111 
of the River and Harbor Act of 1968. None. 
Flood Control 
74. SAGINAW RIVER, MI 
Location. Saginaw River Basin including its tributaries, 
Tittabawasee, Shiawassee, Flint and Cass Rivers, drains 
an area of 6,260 square miles in the east central part of 
Michigan and empties into Saginaw Bay, an arm of Lake 
Huron. Bay City, near mouth of river, and Saginaw, 22 
miles upstream from mouth, are on Federally improved 
deep-draft Saginaw River navigation channel (See Saginaw 
and Flint Geological quadrangles and NOAA Nautical 
Chart 14867). 
21-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. Provides for improvements in 
Saginaw River Basin for flood control and other purposes: 
(a) at Sanilac Flats, MI, Middle Branch and South Branch, 
Cass River, to provide for major drainage improvements 
by channel improvements on Middle and South Branches, 
including a short reach of East Branch. This feature of 
the project for flood control, Saginaw River, MI, 
authorized by the Flood Control Act of 1958, was 
deauthorized by the WRDA of 1986; PL 99-662 - Nov. 
17, 1986, 99th Congress, Title X; (b) at Vassar on Cass 
River, to provide for flood protection of areas on north 
and south sides of river by channel improvement, levee 
construction floodwalls, modifications of Moore Drain, 
and related work at an estimated U.S. cost (Oct. 1984) of 
$8,620,000 and non-Federal cost of $579,000 for 
construction; (c) at Frankenmuth on Cass River, to 
provide for flood protection of areas on north side of river 
by channel improvement, levee construction, and related 
work, at an estimated U.S. cost (July 1974) of $410,900 
for construction; (d) at Flint on Flint River, to provide for 
flood protection of areas on both sides of main stem of 
Flint River and its tributaries, Swartz and Thread Creeks 
by channel improvement, bridge alterations, floodwall and 
levee construction, and related work, at an estimated U.S. 
cost (Oct. 1984) of $18,251,600 and non-Federal cost of 
$2,580,000 for construction; provided local interests 
contribute in cash 1 percent of first cost of project, 
exclusive of cost of rights-of-ways; (e) at Corunna on 
Shiawassee River, to provide for flood protection by 
channel improvement, levee construction, and related 
work. This features of the project for flood control, 
Saginaw River, MI, authorized by the Flood Control Act 
of 1958, was deauthorized by the WRDA of 1986; PL 99- 
662 - Nov. 17, 1986, 99th Congress, Title X; (f) at 
Owosso on Shiawassee River, to provide for flood 
protection by channel improvement. This feature of the 
project for flood control, Saginaw River, MI, authorized 
by the Flood Control Act of 1958, was deauthorized by 
the WRDA of 1986, PL 99-662 - Nov. 17, 1986, 99th 
Congress, Title X; (g) at Midland on Tittabawassee River, 
to provide for flood protection through non-structural 
(permanent evacuation) measures at an estimated U.S. cost 
(Apr. 1982) of $5,125,000 and non-Federal cost of 
$1,611,500 for implementation; however, project was 
reclassified to the "inactive" category on December 15, 
1982; (h) at Shiawassee Flats along lower reaches of the 
four principal tributaries of Saginaw River, to provide for 
flood protection, including fish and wildlife areas; by 
channel improvement, levees, lateral reservoirs with 
control structures and related work at an estimated U.S. 
cost (Oct. 1984) of $23,417,500 Federal and non-Federal 
cost of $2,705,000 which includes a cash contribution of 
$1,237,000; provided local interests contribute in cash 5 
percent of cost of rights-of-way for flood control and other 
work required as local cooperation, and furnish one-half 
of land required for fish and wildlife areas; provided that 
the Federal allocation for conservation does not exceed 
amount obtained by taking 28 percent of project cost for 
Shiawassee Flats unit and subtracting therefrom one-half 
cost of lands for conservation; and provided further that 
before starting work for flood control to Shiawassee Flats, 
Chief of Engineers and Director, Fish and Wildlife 
Service, prepare a plan mutually acceptable to Secretary 
of the Army and Secretary of the Interior for operation of 
fish and wildlife areas to required degree of controlled 
storage of flood waters while preserving the maximum fish 
and wildlife benefits. Total estimated cost for new work, 
for active portion (1984) is $50,700,000 Federal and 
$1,421,000 to be contributed by local interests. Total 
estimated cost (1984) to local interests is $5,870,000. 
Local cooperation. Responsible local interests must 
make cash contributions as called for above; furnish lands, 
and rights-of-way, including removal of buildings, for 
construction; hold the United States free from damage; 
maintain and operate all works after completion; establish 
and enforce regulations designed to prevent encroachments 
in improved channels; and bear expense of constructing 
highway relocations and highway bridges, alter bridge 
approaches and existing highway bridge approaches and 
existing highway bridges (except under pinning and bridge 
raising), and alter utilities. Required assurances for Flint 
River at Flint were furnished by city of Flint and accepted 
by the United States on November 23, 1962. Estimated 
required cash contribution for Flint ($56,000) was 
furnished February 20, 1963. An additional $117,000 
was furnished by the City to cover increased construction 
costs. Required assurances for Cass River at 
Frankenmuth were accepted on September 8, 1964. All 
necessary lands, easements, and rights-of-way have been 
provided. The Midland City Council adopted a resolution 
on June 7, 1982, declaring its intent not to sponsor the 
Flood Control project on the Tittabawassee River at 
Midland. The Vassar City Council, in a letter dated 
January 26, 1982, indicated a willingness and capability to 
provide the assurances of local cooperation for the Vassar 
Flood Control Project. Saginaw County, in a resolution 
dated August 11, 1982, indicated a willingness and 
capability to provide the assurances of local cooperation 
for the Shiawassee Flats Flood Control Project. 
21-40

DETROIT, MI DISTRICT 
Operations during fiscal year. The Frankenmuth and 
Flint portions of the project are complete. However, for 
the Flint River Segment at Flint, MI, for the project 
originally authorized under the Flood Control Act of 1958 
(PL 85-500), FY 92 maintenance repairs were authorized 
under the Energy and Water Development Appropriations 
Act of 1992 (PL 102-104), with $1 million provided. 
The flood protection project was completed September 
5, 1979. In accordance with the 1962 LCA, the city of 
Flint is responsible to operate and maintain the project. 
Due to the lack of maintenance, the project requires 
extensive repairs. The total cost of repairs is estimated at 
$7.5 million. 
The FY 92 authorization was intended to provide a onetime 
repair and rehabilitation of this project to restore the 
project to original design dimensions; however, the 
allocation in FY 92 was only $1 million. Federal FY 92 
work included field work, preparing a Letter Report, 
preparing plans and specifications, and awarding four 
construction contracts. Total FY 92 costs were $505,883. 
The Energy and Water Resources Appropriation Act of 
1993 provides $2 million under the Operations & 
Maintenance General appropriation to continue the repair 
and rehabilitation of this flood control project. Under the 
current plan, the District can utilize only $500,000 in FY 
93, for engineering and design, supervision and 
inspection, and initiation of construction. The remainder 
would be used in FY 94 to complete E & D and award 
construction contracts. 
75. SEBEWAING, SEBEWAING RIVER, 
MI 
Location. Sebewaing River drains an area of 105 
square miles in Huron and Tuscola Counties on the 
westerly side of Thumb area of Lower Peninsula of 
Michigan and discharges into Saginaw Bay, an arm of 
Lake Huron, 20 miles northeast from mouth of Saginaw 
River. Village of Sebewaing is near mouth of River. 
(See NOAA Nautical Chart 14863.) 
Existing project. Enlarging present channel of 
Sebewaing River through village of Sebewaing, MI, to a 
capacity of 7,500 cubic feet per second from junction of 
Columbia and State drains to a point 4,500 feet lakeward 
from railroad bridge near mouth; altering railroad bridge 
and three highway bridges to permit free passage of ice; 
and removal of present dike on south side of channel 
lakeward from railroad bridge. Project is designed to 
provide protection for village of Sebewaing from floods 
with a frequency of once in 15 years and with a magnitude 
greater than the maximum flood of record. (See Table 21- 
B for authorizing legislation.) 
Local cooperation. Complied with except for 
furnishing easements and rights-of-way for removal of 
remaining portion of dike on south side of channel 
lakeward from railroad bridge. 
Operations during fiscal year. Maintenance: 
Condition surveys, miscellaneous inspections and reports 
were performed by Government forces at a cost of 
$13,872. Total costs to the end of FY were $792,292. 
76. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
NAME OF PROJECT 
Battle Creek, Kalamazoo 
River, MI 
Burr Oak, Prairie River, MI 
Fort Wayne, IN 
Kawkawlin River, MI 
Mt. Clemens, MI, Clinton Riv 
Spillway 
Red Run, Clinton River, MI 
River Rouge, MI 
Saginaw River & Tributaries 
Frankenmuth 
Flint River 
Paw Paw Lake & River 
Watervliet, MI 
Sebewaing River, MI 
DATE OF INSPECTION 
July 1992 
August 1992 
August 1992 
October 1990 
er 
July 1992 
July 1992 
October 1992 
June 1992 
January 1990 
September 1992 
June 1992 
Costs in FY 92 were $64,765. Total costs to end of FY 
were $1,975,561. 
77. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 21-E. 
78. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency Flood Control Activities, Flood Fighting 
(Public Law 84-99 and PL 93-288 and Antecedent 
Legislation). 
21-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Fiscal Year Costs 
to September 30. 1992 
$ 259,825 
$ -0- 
$ -0- 
$ 5,025 
-0- 
Flood control activities pursuant to Section 205 of the 
1948 Flood Control Act. 
Grand Pointe, Eaton County, MI - The 
Reconnaissance Report was completed and approved on 
March 28, 1991, and preliminary discussions were 
initiated with the Windsor Charter Township, concerning 
negotiation of a Feasibility Cost Sharing Agreement. The 
local sponsor withdrew on October 4, 1991. The study 
was terminated December 13, 1992. Costs in FY 92 were 
$69. 
Kawkawlin River, MI - Further work to upgrade the 
completed abbreviated reconnaissance report to a full scale 
reconnaissance report was delayed pending receipt of 
additional funds. No funds were expended in FY 92. 
LaPorte, Pine Lake, IN - The Reconnaissance Report 
was completed and approved on July 24, 1991, and 
preliminary discussions were initiated with the city of 
LaPorte concerning the scope of the Feasibility effort and 
the related negotiations leading to a Cost Sharing 
Agreement. Due to the costs associated with the study 
and implementation of the project, the local sponsor 
withdrew on September 1, 1992. The study was 
terminated on September 22, 1992. Costs in FY 92 were 
$23,265. 
Flood control activities pursuant to Section 208 of the 
1954 Flood Control Act. None. 
Aquatic plant control activities pursuant to Section 
302 of the River and Harbor Act of 1965 (PL 89-298). 
None. 
79. SURVEILLANCE OF NORTHERN 
BOUNDARY WATERS 
Field Operations. The following field operations, 
which were complemented by office activities, were 
conducted during the reporting period. Within the realm 
of support to others, the District conducted current 
Project and Location 
Disaster Preparedness 
Emergency Operations 
Rehabilitation 
Advance Measures 
Advance Measures 
(Contributed Funds) 
21-42
velocity and discharge measurements on the Niagara River 
for the New York Power Authority (NYPA). These 
measurements were part of NYPA's program to develop 
mathematical and physical models, leading to the design 
of structural and/or operational measures to mitigate the 
effects of potential ice jamming and flooding in the upper 
Niagara River. This effort was necessary to satisfy a 
requirement of the Federal Energy Regulation Commission 
(FERC) prior to implementation of upgraded plans for the 
Niagara Power Project. Discharge measurements were 
also made at the head of the Niagara River and below 
Niagara Falls, in support of the International Niagara 
Board of Control. Further field measurement programs 
are scheduled for the St. Marys, Detroit, St. Clair, and 
Niagara Rivers during FY 93. 
During the winter months, the District monitors, as an 
ongoing mission, the presence and intensity of ice in the 
St.. Marys, St. Clair, and Detroit Rivers. Water levels are 
monitored continuously at key gages in these rivers for 
automated updating of hydrographs used for detecting 
possible ice jams and the associated potential for flooding. 
This information can be used to provide advance warning 
to area residents and to trigger emergency actions by the 
Corps and other governmental agencies in support of 
respective Flood Alert Plans. Currently, data are obtained 
from water level gages via direct land-line communication 
with the gages or from a satellite downlink station using 
portable lap-top personal computers. This provides water 
level information to the District office within minutes of 
data collection. During FY 92, several steps were taken 
to convert the gages to the new International Great Lakes 
Datum 1985, and to record data in metric units. This 
process will be completed in early FY 93. 
International Activities. The Detroit District has 
successfully supported the International Joint Commission 
(IJC) for many years. This support has included a myriad 
of engineering and scientific assignments. The District is 
associated with several boards of control, working 
committees, and study boards. 
The following activities were conducted by the Detroit 
District specifically for the IJC Boards and Committees: 
a. Members of the Detroit District staff attended the 
semi-annual meetings of the Great Lakes boards of 
control. They also attended the spring appearances of the 
Boards before the Commission in Washington, D.C. 
(April 1992).

DETROIT, MI DISTRICT 
b. IJC Water Level Reference Study. As a result of 
the record high Great Lakes levels in 1985-86, the 
governments of the United States and Canada issued the 
UC a Reference on August 1, 1986, requesting a new 
water level study. Under this study, the IJC was asked to 
examine and report upon methods of alleviating the 
adverse consequences of fluctuating water levels in the 
Great Lakes-St. Lawrence River basin. The IJC released 
an interim report in October 1988, which addressed crisis 
intervention and intermediate measures which could be 
taken to aid interests harmed or threatened by high water 
levels. Detroit District personnel were involved in 
preparing many of the findings and recommendations. 
The main study has been divided into two phases. Phase 
I, which was completed in May 1989, identified the major 
types of measures, which address the problems brought on 
by lake level fluctuations, and developed a comprehensive 
framework for the systematic evaluation of these 
measures. The Detroit District was heavily involved in 
providing support to several of the study groups under 
Phase I. Phase II commenced in July 1991 and will lead 
to specific responses to issues explicitly identified in the 
Reference. Personnel from the Detroit District were 
assigned tasks under, and hold positions on, Working 
Committee 2 - Land Use and Management, and Working 
Committee 3 - Existing Regulation, System-Wide 
Regulation and Crises Conditions. Specifically, the Chief 
of the Geographic Data Resources Section is a member of 
Working Committee 2, is the U.S. Co-chair of the task 
group for "Land Use and Management," and is a member 
of the "Erosion Processes" and "Potential Damages" task 
groups. Under Working Committee 3, the Chief of the 
Great Lakes Hydraulics and Hydrology Branch is U.S. 
Co-chair of the "Crisis Condition Plan" task group; and 
the Chief of the International Hydrologic Section is U.S. 
Co-chair of the task group for "Regulation Studies," and 
a member of the "Climate Change, Lake Level Frequency 
and Forecasting, and H & H Data" task group. 
Phase II work started in FY 91 continued into FY 92. 
These efforts include: identifying possible crises measures 
for times of extreme water levels and developing these 
into crises response plans; reviewing the present operating 
plan for the regulation of Lake Superior and developing 
and testing modifications; developing and testing 
regulation plans to manage all or additional parts of the 
Great Lakes system; assessing and improving water level 
forecasts and statistics; inventorying land use patterns and 
trends; and estimating potential damages caused by 
extreme levels. Phase II of the Reference Study is 
scheduled for completion in March 1993. 
c. International Lake Superior Board of Control. 
The Detroit District Engineer is the United States 
Regulation Representative of this Board. In support of the 
U.S. section of the Board, the District provided monthly 
Lake Superior outflow recommendations based upon a 
review of the hydrologic factors which influence the future 
regulation of Lake Superior. These recommendations 
were based on the use of probability forecasts of water 
supplies routed through the lakes using the approved 
operating rule, Plan 1977-A. Plan 1977-A was accepted 
by the Commission on a test basis and has been used in 
operation since June 1990. Further proposed 
modifications of the regulation plan are being explored by 
the Detroit District under its association with the IJC 
Reference Study. 
During FY 92, the District was involved in the Board's 
conversion of operations to the new vertical datum, 
International Great Lakes Datum (IGLD) 1985, and to the 
metric system. The new Great Lakes datum was instituted 
in January 1992. At the Board's April 1992 meeting it 
was agreed that operations should be converted to the 
metric system within the same time frame as conversion 
to IGLD 1985. The District's involvement has included 
determining appropriate conversions for the water level 
criteria in the IJC Order of Approval, and all numeric 
values and mathematical relationships used in the Board's 
operations. Conversion of the computer models of the 
regulation plans, Plan 1977 and Plan 1977-A, will be 
initiated in early FY 93. The Board is expected to be 
fully operational in both metric and the new datum by 
January 1993. 
d. International Niagara Board of Control and 
International Niagara Working Committee. The Chief 
of the Great Lakes Hydraulics and Hydrology Branch is a 
member of the U.S. section of the Working Committee. 
Under the auspices of the International Niagara 
Committee, the Detroit District computes, coordinates and 
publishes, with Canada, the monthly flows in the Niagara 
River. The District also provides direct technical support 
and consulting engineering services to the Board and 
Committee. 
During FY 92, District personnel conducted, jointly with 
Water Survey of Canada, a series of discharge 
measurements in the upper Niagara River at the 
International Bridge Section for verification of Lake Erie 
21-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
outflow equations. Information to date indicates that the 
existing equations are adequate during average flow 
ranges, but still require verification at the very high and 
very low extremes. Future measurements are presently 
scheduled for this section in FY 95, in accordance with 
the Board's recommendation to continue making them 
every three years. Due to the dynamic nature of the 
Niagara River, the District is involved with the periodic 
verification of the rating curves for the Ashland Avenue 
and American Falls gages. The Ashland Avenue 
relationship measures the total flow over the American and 
Canadian falls to ensure that the Board operates within the 
terms of the Niagara Treaty. Discharge measurements for 
the Ashland Avenue rating curve are scheduled every 
three years. Measurements were made in FY 92, and 
continued to show good correlation to the relationship. 
The next series is scheduled for FY 95. The American 
Channel relationship provides a measure of the flow over 
the American Falls. Measurements are taken in the 
American Channel every five years. The last 
measurements were made in FY 90 with the next series 
scheduled for FY 95, or possible FY 93 in order to update 
the relationship to IGLD 1985. Beginning in FY 93, all 
future measurement series will be based upon using IGLD 
1985 and metric. 
Also during FY 92, the District was involved in the 
conversion of Board operations to the new vertical datum, 
IGLD 1985, and the metric system. This has included 
review of the proposed conversions of various limits, 
parameters and flow relationships. The Board expects to 
be operational in both metric and the new datum by 
January 1993. 
e. International St. Lawrence River Board of 
Control. When requested, the Detroit District conducts 
flow measurements in the St. Lawrence River for 
development of mathematical models of critical sections in 
the river. In FY 96, flow distribution measurements are 
scheduled to calibrate the existing mathematical model of 
the river. This Board is also charged to complete both 
metric and IGLD 1985 conversion by January 1993. 
f. International Great Lakes Diversions and 
Consumptive Uses Study Board. The UC submitted its 
recommendations, based on the Board's report and 
subsequent public hearings, to the governments of the 
United States and Canada, in a report dated January 1985. 
A former Detroit District Engineer was Chairman of the 
U.S. section of the Working Committee. Until such time 
as the Board is either dissolved or continued, certain 
personnel within the District continue to hold membership 
on the Diversions and Environmental Evaluation 
Subcommittees and on the Public Involvement Ad Hoc 
Group. The District expects to continue to provide 
support to the UC relative to the evaluation of 
consumptive uses. 
g. International Great Lakes Technical Information 
Network Board. Although the Board is inactive at this 
time, the Chief of the Great Lakes Hydraulics and 
Hydrology Branch remains the Secretary to the U.S. 
Section, as well as a member of both the Hydraulics and 
Hydrology Committees. The Board completed its study 
and provided a report of its findings and recommendations 
to the IJC in December 1984. In January 1985, the IJC 
informed the governments of the United States and Canada 
of the findings of the Board. One of the recommendations 
of this Board, to create a modeling group, has since been 
adopted by the Coordinating Committee on Great Lakes 
Basic Hydraulic and Hydrologic Data. 
Coordinating Committee on Great Lakes Basic 
Hydraulic and Hydrologic Data. The Chief of the Great 
Lakes Hydraulics and Hydrology Branch is the U.S. 
Secretary to this Committee, as well as a member of 
several subcommittees. Other Branch personnel also hold 
membership on various subcommittees. The District 
continued its support of Committee operations pertaining 
to the coordination of basic hydraulic and hydrologic data 
with Canada. Following the completion of the IJC's 
Reference Study, a concerted effort is expected to update 
and modernize the collection, modelling and presentation 
of the various data bases and products of the Committee. 
District efforts continue to more closely coordinate the 
format of the U.S. and Canadian water level bulletins, in 
order to avoid confusion and to better inform the public. 
An update of International Great Lakes Datum (IGLD) 
was completed in FY 92. The new IGLD was instituted 
in January 1992 and evolves around the epochal year 
1985. During FY 92, the District was involved in the 
publication and distribution of a brochure on IGLD 1985, 
and participated in a public workshop on the new datum 
in November 1991. The Great Lakes Hydraulics and 
Hydrology Branch has begun to convert its forecasting and 
regulation operations to the new datum, and should be 
fully operational on the new datum early in FY 93. In FY 
92, District personnel continued to finalize a Coordinating 
Committee report which will document all the discharge 
measurements (U.S. and Canadian) made on the Great 
Lakes Connecting Channels and St. Lawrence River 
during the period 1860 to the present. It is expected to be 
21-44

DETROIT, MI DISTRICT 
completed in FY 93. Work continued on a program to 
analyze the current configuration of and design future 
modifications to hydrometeorological data collection over 
the Lake Ontario basin. This work is expected to be 
completed in FY 93. A similar study may be done for the 
Lake Superior basin. Work on a hydraulics/hydrology 
modeling inventory is expected to begin in FY 93. 
North Central Division Master Plan for the Water 
Control Data System. During FY 92, the District 
continued to implement the Great Lakes Water Control 
Data System, using a Harris-800 minicomputer and an 
extensive system of automated gaging stations. Presently, 
the Harris-800 computer collects data from the District's 
data collection platforms (DCP's), from dedicated lines to 
the National Weather Service's telecommunication 
network, and from NOAA/NOS and Canadian water level 
computer systems. The District has 30 active DCP's and 
plans to install as many as three additional DCP's in the 
near future. In FY 92, the District continued the work to 
transfer the Water Control Data System to a network 
UNIX environment, in accordance with the Master Plan 
Update. 
Great Lakes Information Management. The District 
has continued development of capabilities for processing 
satellite and aerial photography and encoding of mapped 
information into a Geographic Information System (GIS) 
for the U.S. portion of the Great Lakes. The GIS is being 
generated to contain multiple information layers on the 
physiographic, economic, sociologic, environmental, and 
hydrologic characteristics of the Great Lakes region. The 
GIS is designed to create a "corporate data base" to 
support various District operations and studies, including 
improved monitoring of hydrometeorologic conditions 
over the basin. In FY 91, GIS data layers were completed 
for a comprehensive lake use inventory of the U.S. Great 
Lakes shorelines, along with information on public land 
ownership, and flooding and erosion hazard areas. In FY 
92, this base was used to generate information on the 
social and economic impacts of potential flooding and 
erosion along the U.S. Great Lakes shorelines and likely 
benefits from alternative water level regulation scenarios. 
These activities were carried out in association with the 
UC Reference Study. 
Hydraulics and Hydrology of the Great Lakes. Water 
supply forecasts are used routinely by the Great Lakes 
Hydraulics and Hydrology Branch in forecasting water 
levels and regulating the outflows from Lakes Superior 
and Ontario. Studies to improve the existing Great Lakes 
water level forecasting system, including investigations 
into the factors affecting the Great Lakes water balance 
relationship (i.e., runoff, over water precipitation, 
evaporation, ice retardation, etc.) and use of real-time 
hydrologic data were continued by the staff of the Branch. 
Some of these activities were carried out in association 
with the UIJC Reference Study. District personnel, in 
cooperation with National Weather Service personnel, are 
continuing to assess water supply conditions over both 
Lakes Superior and Ontario, through use of airborne snow 
and soil moisture surveys, and processed satellite imagery. 
Levels of the Great Lakes. The Great Lakes 
Hydraulics and Hydrology Branch continued to make 
routine short-term (15 days to one month) and long-term 
(six months) Great Lakes still water level forecasts. These 
forecasts are distributed in the form of weekly, bimonthly, 
and monthly news releases and bulletins. The publication 
of an internationally coordinated (U.S. and Canada) 
forecast of Great Lakes water levels, under the auspices of 
the Coordinating Committee on Great Lakes Basic 
Hydraulic and Hydrologic Data, was continued during the 
period. The circulation of this publication is about 10,000 
copies monthly in the U.S. alone. Branch personnel 
provided technical information and expertise regarding 
recorded lake levels and still water lake level forecasts to 
many interested parties, such as Congressmen, State and 
local officials, news media, navigation and power 
interests, concerned property owners, and recreational 
boaters. Upon request, water level information was 
supplied to the public in the form of direct answers to 
numerous inquiries, addresses to various civic groups, and 
interviews with the news media. Currently, daily reports 
on present water levels, precipitation and significant 
events on the Great Lakes basin, are being made available 
on the District's Harris-800. Forecasted and historical 
water level data are also available on this system. 
Interested agencies and individuals can retrieve this 
information at any time via a telecommunication device. 
As the Branch moves its operations from the Harris-800 
machine to the UNIX based network environment, the 
above noted products will also be moved. Access to this 
information will continue to be open to interested parties. 
The total cost for FY 92 under Surveillance of Northern 
Boundary Waters was $2,025,027. Under International 
Water Studies, $142,009 was expended in FY 92. 
21-45

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
General Investigations 
80. SURVEYS 
Fiscal year costs of $34,001 were expended for a 
navigation study at Saginaw Bay and Saginaw River, MI, 
to complete Reconnaissance Report investigations. A 
Limited Reconnaissance Report was prepared for Bolles 
Harbor, MI, at a cost of $34,999. Negotiations of a 
feasibility cost sharing agreement were continued for the 
commercial navigation study at St. Joseph Harbor, MI, at 
a cost of $65. Flood Damage Prevention investigations 
were continued for Milwaukee Metropolitan Area, WI, at 
a cost of $137 to complete Reconnaissance phase studies, 
and Federal funds in the amount of $218,912 were 
expended to initiate the cost shared Feasibility phase. In 
FY 92, costs of $55,999 were expended for a shoreline 
protection study at Bay City, MI, to prepare a Limited 
Reconnaissance Report. 
A comprehensive study for the Rouge River, MI, was 
completed in FY 92 at a cost of $118,000, to investigate 
streamflow enhancement. 
Coordination Studies with other Agencies include: 
Special Investigations, $53,000, which includes 
engineering and technical assistance given to local citizens 
because of fluctuating lake levels of the Great Lakes; 
FERC, $6,000; and Interagency Water Resources 
Development, $17,000; North American Water Fowl 
Management Planning, $4,000; Soil Conservation Service, 
$2,000; and Planning Assistance to States (Section 22), 
$90,680. Studies and tasks under the Planning Assistance 
to States (PAS) program included: Allen County, IN - 
$12,000; Decatur, IN - $12,373: Auburn, IN - $6,952; 
Lake Superior Harbor, MN - $35,169; New Haven, IN - 
$14,258; PAS-MI - $928; and PAS-General - $9,000. 
Funds in the amount of $310,906 were expended to 
continue the Section 216 restudy of Federal interest for 
Fox River, WI. Funds of $20,001 were also used to 
continue a Section 216 restudy of Federal interest for 
Clinton River Spillway, MI. Fiscal year 92 funds of 
$1,800 were used to complete a reconnaissance restudy of 
the deferred project at Menominee Harbor, MI. 
81. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
ECORSE CREEK DRAINAGE BASIN, MI 
Fiscal year 1992 costs were $99,974 for continuation of 
preparation of the General Design Memorandum. Due to 
concerns with the original retention basin site and inability 
to provide an acceptable alternate site, further work is 
suspended at request of the non-Federal sponsor. 
The project, as authorized in the WRDA of 1990, calls 
for construction of a storm water retention basin along the 
North Branch of Ecorse Creek. This basin would have a 
storage capacity of approximately 275 acre-feet and would 
collect flood waters in excess of the bank capacity. This 
plan would generally provide 2- to 7-year frequency flood 
protection upstream of Interstate Highway 94 for the 
communities of Dearborn Heights, Taylor, and Allen 
Park. 
The total (1992) project cost is estimated to be 
$11,735,000; $8,586,000 Federal and $3,149,000 non- 
Federal. 
FORT WAYNE, IN 
Funds in the amount of $483,054 were expended in FY 
92 for the continuation of preparation of the General 
Design Memorandum, to be completed in FY 93. 
The project will provide a 100-year level of protection 
utilizing approximately 50,000 linear feet of floodwall and 
levee along the St. Marys, St. Joseph, and Maumee 
Rivers, and Spy Run Creek. In addition, slope protection 
and interior flood control improvements will be made as 
necessary. An existing 1.3 miles of hiking/biking trails 
will be expanded to 4.8 miles. 
The total fully funded project cost is estimated to be 
$41,059,000; $30,624,000 Federal and $10,435,000 non- 
Federal. 
GRAND HAVEN HARBOR, MI 
The WRDA of 1986 authorized harbor modifications 
including construction of a new turning basin and 
deepening of the navigation channel up to 27 feet. 
21-46

DETROIT, MI DISTRICT 
Preconstruction, engineering, and design (PED) efforts 
were initiated in FY 92, with the expenditure of $274,999. 
These PED funds were used to reevaluate the economic 
and environmental feasibility of the project consistent with 
current and future conditions. Reevaluation efforts 
incorporated a ship simulation model and the local 
sponsor's cost-saving interest in downsizing the authorized 
project, by examining eight alternative scenarios to the 
authorized project modifications. The PED efforts for FY 
92 were presented in a September 1992 report, currently 
under review, titled, "Preliminary Reevaluation of 
Authorized Modifications to Grand Haven Harbor, 
Michigan," recommending no further action at this time 
due to lack of economic justification. 
GREAT LAKES CONNECTING CHANNELS AND 
HARBORS 
Funds in the amount of $288,675 were expended in FY 
92 to continue the Preconstruction Engineering and Design 
work activities. The Design Memorandum for the Upper 
St. Marys River was submitted to North Central Division 
in FY 92, with approval scheduled for March 1993. The 
current approved schedule shows a FY 95 Construction 
New Start. 
The recommended plan involves the deepening of 
navigation channels in the Upper St. Marys River and in 
Duluth Harbor to: (a) permit a maximum safe vessel draft 
of 26.5 feet below LWD for downbound vessels; (b) 
dispose of an estimated 341,000 CY of dredged material 
from the Upper St. Marys River in an environmentallyacceptable 
manner by creating an island in Izaak Walton 
Bay to provide habitat for the Federally endangered 
species, the Piping Plover; (c) deepening in the Cross and 
South Channels, West and East Gate Basins, Duluth 
Harbor Basin (North and South Sections) and Duluth Ship 
Canal; (d) construction of an upland disposal area in the 
Lakehead area, and (e) dispose of an estimated 286,500 
CY of dredged material in the Lakehead upland site. 
The Superior Harbor portion of the project has not been 
authorized, since a local sponsor has not been determined. 
The total fully funded cost of the project is estimated at 
$15,370,000, with $10,285,000 and $5,085,000 being the 
Federal and non-Federal shares, respectively. 
82. COLLECTION AND STUDY OF 
BASIC DATA 
Flood Plain Management Services. Fiscal year 92 
costs in the amount of $162,588 were associated with the 
following tasks under the Flood Plain Management 
Services Program; Unit - $35,000; Technical Services - 
$40,000; National Flood Proofing Committee - $5,000; 
Quick Responses - $8,000; and Special Studies for 
Eldorado Marsh, WI, Dam Break Analysis - $15,394; 
Menominee River, MI, Flood Profile Study - $15,342; 
HEC I Basic Workshop in Indiana - $18,852; HEC II 
Basic Workshop in Indiana - $13,000; and the 
continuation of the Flood Plain Geographical Information 
System Data Base for Michigan - $12,000. 
Flood Insurance Studies. One Michigan Flood 
Insurance Study for the Saginaw River Basin, Bay and 
Saginaw Counties, was completed in FY 92. The FY 92 
costs associated with this study were $69,153. The study 
was completed at a total cost of $113,190. Michigan 
Flood Insurance Studies for Farmington Hills, Oakland 
County and Isabella County (Unincorporated Area) will be 
completed in FY 93. The FY 92 costs associated with 
these studies were $1,666 and $2,535, respectively. Final 
coordination meetings were held on eight completed 
Michigan Flood Insurance Studies for the communities of 
Alpena Township, Alpena County; Baldwin Township, 
losco County; Fraser Township, Bay County; Greenbush 
Township, Alcona County; Kawkawlin Township, Bay 
County; Pinconning Township, Bay County; Sims 
Township, Arenac County; and Tawas City, losco 
County. The FY 92 costs for these activities were $264, 
$374, $201, $50, $118, $135, $236, and $306, 
respectively. 
Costs in FY 92 in support of the Federal Emergency 
Management Agency's Community Assistance and Limited 
Map Maintenance Programs were $31,023 and $82,538, 
respectively. 
21-47

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
1. Alpena Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
2. Arcadia Harbor, MI 
3. Ashland Harbor, WI 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
2,134,000 
2,158,207 
79,170 123,500 
84,180 121,443 
0
0 
87,254 212,227 
82,952 213,755 
4. Au Sable Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
5. Bayport Harbor, MI 
Contributed Funds 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
49,346 
49,346 
21-48 
0 125,000 
0 23,169 
40,410 
28,695 
20,000 
97,117 
76,000 201,000 
61,232 213,620 
0
0 
8,249 
8,249 
5,137 
5,137 
12,057 
12,057 
337,394' 
337,394' 
991,508 
989,302 
30,613 
28,407 
62,000 
64,063 
4,359,031 
4,353,052 
1,695,645 
1,695,645 
3,326,905 
3,318,620 
600 
3,301 
42,000 
33,788 
7,000 
61,333 
15,039 
11,736 
247,241 
249,407 
209,7762 
209,7762 
2,823,845 
2,823,845 
(10,000) 
(8,863) 
93,597 
93,597 
145,000 
120,000 
438,693 
424,830

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
5. Bayport Harbor, MI 
(Continued) 
6. Big Bay Harbor, MI 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
7. Black River Harbor, MI 
(P.H.) 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
66,435 
69,106 
0
0 
146,301 562,996 
80,490 626,892 
8. Black River Harbor, MI 
(U.P.) 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
9. Bolles Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
(1,000) 
141,632
0
0 
5,997 305,620 
5,599 301,551 
21-49 
0
0
0
0 
0
0
0
0 
792 
792 
390,4333 
390,4333 
1,370,134 
1,366,660 
15,579 
15,579 
993 
993 
152,000 
143,424 
0 
5,103 
830,165� 
830,165k 
1,325,244' 
1,318,984 
15,000 
11,641 
0
0 
(14,000) 
(2,480) 
1,433 
1,463 
2,310 
2,310 
383,350 
383,350 
819,615 
802,254 
106,759 
89,398 
426,4136 
426,4136 
1,986,426 
1,984,471 
1,190,550 
1,190,550 
5,447 
7,561
0
0

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
10. Caseville Harbor, MI 
11. Charlevoix Harbor, MI 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
0
0 
4,873 
4,873 
290 236,000 
290 235,344 
11,000 
5,716 
0
0 
1,523,000 111,668 230,000 436,000 
1,528,061 110,507 230,972 394,739 
0
0 
12. Clinton River, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
0
0 
122,935 129,078 493,000 1,208,000 
126,559 103,183 491,436 1,118,347 
966,100 
1,109,377 
(98,120) 
(95,512) 
(13,000) 
(7,571) 
13. Cornucopia Harbor, WI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
587,314 
587,314 
1,338,297 
1,332,357 
180,623 
180,623 
8,687,568 
8,645,081 
1,129,396 
1,129,396 
549,7987 
549,7987 
3,085,381 
2,966,987 
3,796,180 
3.796,180 
0
0 
3,748 
3,748 
4,346 
4,346 
53,000 
46,536 
462,653 
462,653 
986,455 
982,729 
60,458 
63,196 
21-50

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
14. Detroit River, MI 
Contributed Funds 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
3,680,100 4,668,085 4,239,000 6,118,390 
3,709,048 4,704,968 4,191,494 5,940,222 
768,600 301,291 
765,570 307,351 
76,877,357' 
76,877,357' 
98,030,899 
97,770,986 
0 42,470,585 
0 42,470,484 
361,235 
361,235 
15. Duluth-Superior Harbor, 
MN & WI 
16. Fox River, WI 
17. Frankfort Harbor, MI 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0 69,902 
0 69,902 
2,665,000 4,054,372 2,340,200 3,188,000 
2,684,950 3,965,833 2,394,153 3,227,459 
0
0
0 
18,330 
63,410 535,000 
49,547 546,706 
0 
8,235 
1,383,000 1,485,453 1,694,500 1,655,000 
1,355,554 1,461,849 1,708,128 1,681,004 
16,179,160' 
16,179,160' 
53,543,942 
53,521,832 
1,556,249 
1,556,249 
11,556,410 
11,555,361 
3,753,33410 
3,753,334 
t 
10 
45,904,726"1 
45,878,096" 
0 1,955,15912 
0 1,955,15912 
74,449 176,487 205,000 401,000 
80,360 175,652 203,471 352,122 
7,311,832 
7,259,536 
21-51

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
17. Frankfort Harbor, MI 
(Continued) 
18. Grand Haven Harbor, MI 
Section 111 
Section 111 
Contributed Funds 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Approriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0
0
0 
274,776 
274,776 
0 1,204,500 
0 1,204,500 
0
0
0
0 
979,000 543,454 626,000 1,071,000 
993,902 547,850 623,863 996,141 
0
0
0
0 
65,000 
60,379 
56,177 
55,691 
59,000 
63,472 
87,000 
82,125 
(11,615) 
0 
1,283,469 I3 
1,283,46913 
175,000'a 
175,000'a 
24,948,909 
24,867,468 
813,613 
813,613 
780,400 
780,400 
2,160,861 
2,152,607 
15,585 
15,585 
19. Grand Marais Harbor, MI 
20. Grand Marais Harbor, MN 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
0
0 
0 1,055,871 
0 1,055,871 
27,936 161,000 657,000 
5,643 175,017 663,290 
5,384 
6,430 
00 
2,564,340 
2,563,400 
21-52 
450,972 
450,972

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
20. Grand Marais Harbor, MN 
(Continued) 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
10,409 
10,909 
674 
674 
179 209,274 
179 204,118 
0
0 
21. Grand Traverse Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
22. Green Bay Harbor, WI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
2,796,200 1,182,657 1,621,600 1,485,000 
2,803,935 1,153,571 1,670,116 1,474,891 
0 
402 
76,940 395,000 187,000 
65,238 351,405 233,418 
9,946,39515.16 
9,946,39515".16 
26,909,692" 
26,892,512" 
7,472,747 
7,458,969 
23. Hammond Bay Harbor, MI 
Section 111 
Section 111 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0
0
0 
4,056 
4,056 
0 11,577 
0 11,577 
0
0 
0
0 
21-53 
2,202,079 
2,196,923 
1,230,000 
1,230,000 
23,000 
29,756 
86,099 
76,808 
75,295 
79,304 
266,037 
266,037 
1,888,325 
1,888,325 
(2,722) 
2,560 
1,015,366 
1,015,366 
77,000 
77,000 
506,736 
504,584 
50,000 
50,000 
50,572 
48,420

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
24. Harbor Beach Harbor, MI 
25. Holland Harbor, MI 
Section 111 
Section 111 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
0
0 
330,900 2,311,649 289,000 2,360,610 
363,060 2,300,101 293,271 2,355,758 
0
0
0
0
0
0
0
0 
0
0
0
0
0
0
0
0 
3,915,000 972,492 1,469,300 898,000 
3,961,525 971,391 1,439,060 863,373 
22,000 
19,829 
68,216 
65,437 
70,000 
74,158
0
0
0
0 
61,000 
58,048
0
0
0
0 
26. Inland Route, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
1,200,598 
1,200,598 
14,278,239 
14,263,801 
194,504 
194,504 
243,100 
243,100 
771,827'8' 9 
621,000 
621,000 
21,253,104 
21,184,705 
1,810,916 
1,805,573 
502,452 
502,452 
1,663,300 
1,663,300 
46,000 
63,861 
27,728 
29,858 
918,22220 
918,22220 
31,500 
29,210 
42,000 
45,196 
2,517,116 
2,515,536 
21-54

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
26. Inland Route, MI 
(Continued) 
27. Kenosha Harbor, WI 
28. Kewaunee Harbor, WI 
29. Keweenaw Waterway, MI 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
404,300 
404,300 
216,200 705,160 931,300 
232,834 699,775 934,272 
38,000 
31,462 
6,386,128" 
6,376,555m 
0 1,270,275 
0 1,270,275 
0 4,378,600 
0 4,378,600 
559,500 235,877 204,000 651,000 
562.078 251.075 199.753 659.256 
758,33324 
758,33324 
6,330,168" 
6,329,3118 
617,300 
617,300 
2,961,461 
2,961,461 
5,974,141 
5,974,141 
4,588,700 2,272,831 731,000 531,000 
4,564,738 2,285,292 686,394 556,970 
15,000 
30,149 
21-55 
23,081,215" 
23,023,31126 
1,523,500 
1,523,500

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
30. La Pointe Harbor, WI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
31. Lake St. Clair, MI, 
Channels 
32. Leland Harbor, MI 
33. Lexington Harbor, MI 
Contributed Funds 
Section 111 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0 7,675,357 
0 7,675,357 
54,100 
100,244 
80,686 
73,273 
43,000 250,000 
50,075 251,463 
7,941,870" 
7,941,5752 
5,119,800 
5,119,800 
0 1,027,089 
0 1,027,089' 
129,500 127,011 191,500 127,000 
128,479 120,917 193,978 133,719 
0
0
0
0
0
0 
10,000 
19,955 
21-56 
0
0
0
0
0
0 
5,622 174,509 
5,622 171,966 
20,165 
12,747 
2,328,522 
2,328,421 
70,678 
70,678 
1,646,304 
1,646,304 
1,088,888 
1,088,888 
372,000 
372,000 
577,340 
567,379 
2,327 
2,327 
7,128 
7,128 
50,000 
41,238 
139,874 
139,874 
123,709 
119,925 
64,254 
69,232

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
33. Lexington Harbor, MI 
(Continued) Section 111 
Maintenance 
Appropriation 
Cost 
294,000 
375,817 
24,986 
21.075 
(3,000) 27,000 
1,388 19,605 
34. Little Lake Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
162,500 158,357 
163,102 154,452 
154,000 259,000 
154,957 232,309 
35. Ludington Harbor, MI 
Section 111 
Section 111 
36. Manistee Harbor, MI 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
0
0
0
0 
0
0
0
0 
150,500 544,682 838,000 237,000 
132,183 569,842 832,555 172,589 
10,000 
2,769 
454,000 
458,202 
(7,000) 
231
0
0 
0
0
0
0 
25,958 286,000 746,000 
27,391 282,675 699,314 
7,912,20231 
7,912,20231 
620,000 
620,000 
12,485,74832 
12,414,24632 
357,913 
357,913 
717,340 
717,340 
2,696,52233 
2,696,52233 
7,742,69134 
7,692,4373 
0 1,374,164 
0 1,374,164 
21-57 
1,259,986 
1,251,852 
600,47830 
600,4783 
3,883,972 
3,853,008

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
37. Manistique Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
38. Manitowoc Harbor, WI 
Contributed Funds 
39. Marquette Harbor, MI 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
134,000 200,149 637,000 335,000 
134,498 197,759 640,472 292,048 
2,048,9143 
2,048,914" 
1,911,130 
1,911,130 
6,729,6643' 
6,683,53337 
0 3,081,756 
0 3,081,756 
0 1,282,893" 
0 1,282,893k 
6,741 196,901 
7,810 194,387 
14,000 415,000 
13,779 393,520
0
0 
2,633,75739 
2,609,54239 
465,757 
465,757 
40. Menominee Harbor & 
River, MI & WI 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
114,500 136,029 208,800 125,000 
115,121 110,088 235,258 126,922 
21-58 
172,400 
168,966 
96,820 
59,313 
27,000 
65,935 
27,000 
23,068 
1,299,355"3 
1,299,355" 
2,233,450 
2,227,511 
316,333 
316,333 
533,476 
533,476 
2,544,669 
2,544,005

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
40. Menominee Harbor & 
River, MI & WI 
(Continued) 
Contributed Funds 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
41. Milwaukee Harbor, WI 
Contributed Funds 
42. Monroe Harbor, MI 
Contributed Funds 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
o 8,231,024� 
o 8,231,024�0 
442,400 878,539 1,531,800 664,000 
426,799 889,184 1,531,795 628,124 
784,000 
901,866 
(2,650) 
24,914
0
0 
275,000
0 
514,800 1,071,398 
699,862 1,060,591 
50,000 
271,809
0
0 
0 
2,486
0
0 
60,000 1,177,000 
67,155 1,179,928 
31,436,314~' 
31,389,6420' 
12,715,560 
12,715,560 
6,380,925 
6,380,925 
325,000 
274,295 
987,34042 
987,3402 
18,466,81803 
18,462,48203 
0 (8,000) 38,606,400 
9 (8,027) 38,606,373 
83,182 
83,182 
21-59 
0 
2,646 
1,351,852 
1,351,852 
593,660 
593,660 
36,762 
36,762

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
43. Muskegon Harbor, MI 
Section 111 
Section 111 
44. New Buffalo Harbor, MI 
Contributed Funds 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
0
0
0
0 
0
0
0
0 
245,000 214,326 828,000 112,000 
242,196 218,406 814,046 124,105 
305,700 
337,972
0 
804 
0 
7,312
0
0 
10,000 
10,573
0
0
0
0 
109,800 142,813 359,000 180,000 
121.175 140.988 357.202 182.350 
0
0 
45. Oconto Harbor, WI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
14,254 
14,254 
50,629 
50,629 
23,000 308,000 
22,180 282,570 
21-60 
2,912,110" 
2,912,110"4 
105,000 
105,000 
7,455,441 s 
7,452,081 s 
2,334,700 
2,334,700 
13,824,300 
13,824,300 
1,285,716 
1,285,716 
1,186,467 
1,186,467 
3,993,137 
3,988,659 
181,500 
181,500 
130,754" 
130,754" 
1,534,180 
1,507,89547

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
46. Ontonagon Harbor, MI 
47. Pensaukee Harbor, WI 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
8,000 
18,525 
0 
1,733 
691,000 795,031 697,000 2,119,000 
701,989 810,605 633,707 2,100,709 
13,494 
13,494 
890 
890 
33,267 147,227 
33,267 134,528 
12,999,884" 
12,899,508"9 
21,000 
21,000 
34,035 
34,035 
402,880 
390,181 
48. Pentwater Harbor, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
0
0 
261,500 115,513 
268,761 110.454 
0
0 
146,000 155,000 
149,337 157,522 
49. Port Austin Harbor, MI 
Contributed Funds 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
1,245,000 800,000 
1,272,186 813,539 
79,824 
140,401 
17,519 
22,130
0
0 
21-61 
953,903e 
953,903' 
179,899 
179,899 
4,212,268 
4,211,677 
(12,000) 
11,326 
4,742 
7,879
0
0 
0
0 
2,439 
2,957
0
0 
3,363,334" 
3,363,33450 
1,774,522 
1,774,522 
159,000 
159,000

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
50. Port Sanilac Harbor, MI 
Contributed Funds 
Section 111 
Contributed Funds 
Section 111 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
87,000 
92,717 
4,205 163,000 
9,291 161,521 
(1,000) 21,251 
11,545 18,858 
51. Port Washington Harbor, 
WI 
Contributed Funds 
52. Port Wing Harbor, WI 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
106,506 
106,506 
56,944 
53,142 
23,460 211,945 
27,191 207,152
0
0
0
0 
21-62 
909,963 
909,963 
487,108 
487,108 
336,000 
336,000 
2,139,490 
2,131,322 
5,000 
(1,058) 
115,000 
115,000 
9,158 
9,158 
11,000 
12,696 
28,000 
22,216 
1,074,251 
1,067,770 
2.582.204' 
2,582,204' 
2,856,47052 
2,851,60652 
10,621 
10,621 
1,624,000 
1,624,000 
63,393 
63,393

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
52. Port Wing Harbor, WI 
(Continued) 
53. Presque Isle Harbor, MI 
Section 111 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
3,598 
4,140 
52,004 
46,102 
4,336 
4,221 
61,500 
61,677
0
0
0
0 
5,298 
6,428
0
0
0
0 
77,000 126,000 
76,968 120,845 
54. Rouge River, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
817,500 145,838 870,000 214,000 
827,076 143,626 868,088 175,858 
247,000 136,495 
246,608 143,493 
675,251" 
675,251 
20,397,941s 
20,353,8495 
0 14,907,318 
0 14,907,318 
55. Saginaw River, MI 
(Federal Funds) 
Contributed Funds 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
1,642,100 2,110,968 3,007,000 1,142,000 
1,634,544 2,128,629 2,999,291 1,097,782 
21-63 
995,920 
991,148 
1,190,492 
1,190,492 
61,700 
61,700 
1,106,997 
1,101,695 
76,500 
76,500 
16,500 
16,500 
14,917,127" 
14,917,127" 
13,600 
13,600 
45,136,363 
45,073,847

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
55. Saginaw River, MI 
(Continued) 
56. St. Clair River, MI 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
188,000 205,990 180,000 283,000 
198,388 182,907 181,910 292,307 
573,500 979,596 718,000 1,438,000 
605,737 1,001,891 720,792 1,424,512 
57. St. Joseph Harbor, MI 
Section 111 
Section 111 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0
0
0 
527,100 682,973 953,500 865,000 
633,865 674,010 943,981 839,689 
0
0
0
0 
0
0
0
0 
74,800 162,350 613,000 
331,988 158,797 583,781 
0
0
0
0 
55,000 
84,028 
58. St. Marys River, MI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
0
0 
10,527,500 11,265,113 12,062,000 13,402,000 
10,499,775 11,046,875 12,024,075 13,358,322 
0
0 
21-64 
20,248,896 
19,213,246 
19,213,246 
21,984,109 
21,952,567 
976,4855' 
976,485" 
828,000 
828,000 
15,266,738 
15,216,446 
962,216 
962,216 
638,076 
638,076 
5,102,450 
5,098,706 
160,657,071 
160,657,070" 
248,046,421 
247,222,149 
13,100 
13,100

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
59. Saugatuck Harbor & 
Kalamazoo River, MI 
60. Sebewaing River, MI 
61. Sheboygan Harbor, WI 
62. South Haven Harbor, MI 
Section 111 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
134,973 
88,532 
522,051 
670,660 
40,126 
88,838 
28,412 156,950 
32,729 156,641 
(11,104) 55,754 
(10,765) 55,754 
17,151 
12,472 
364,527' 
364,527' 
3,548,178w 
3,547,728b0 
35,57361 
35,57361 
3,499,861 
3,495,183 
0 1,136,08862 
0 1,136,08862 
61,500 220,086 668,900 222,000 
61,112 215,787 663,412 228,238 
116,500 
116,801 
11,503 
11,803 
12,107 154,556 
12,107 142,608 
0 0 
0 0 
6,501,87863 
6,497,7373 
609,028 
609,028 
907,792 
907,792 
452,426" 
452,426" 
532,000 
532,000" 
4,041,467 
4,029,519 
1,632,076 
1,632,076 
21-65

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
62. South Haven Harbor, MI 
(Continued) 
Section 111 
63. Sturgeon Bay, WI, and 
Lake Michigan Ship 
Canal, WI 
Diked Disposal 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
0
0 
13,000 
13,725
0
0 
0
0 
1,933 
2,956
0
0 
246,000 257,036 
271,429 252,213 
0
0
0 
1,409
0
0 
0
0
0 
404
0
0 
149,000 436,000 
151,308 394,906 
0
0
0
0 
64. Two Harbors, MN New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
0
0 
160,722 
203,960 
75,446 1,361,000 1,371,000 
75,806 1,357,434 1,373,352 
65. Two Rivers Harbor, WI New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Diked Disposal 
Appropriation 
Cost 
Rehabilitation 
Appropriation 
Cost 
159,992 283,764 
134,581 309,764 
16,888 164,000 
16,888 161,622 
360,320" 
360,320" 
6,041,300� 
6,038,9227� 
0 1,187,472 
0 1,187,472 
0
0 
21-66 
42,381 
42,381 
1,158,933 
1,158,933 
1,059,722" 
1,059,722" 
8,597,45167 
8,551,18867 
311,119 
311,119 
884,899 
884,899 
4,170,710 
4,170,710! 
5,054,882 
5,049,576 
58,057 
58,057

DETROIT, MI DISTRICT 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
66. White Lake Harbor, MI 
Section 111 
Section 111 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
166,900 
170,793 
23,000 
23,587 
9,226 
9,526 
5,130 
5,130 
32,615 159,000 
34,470 157,962 
74. Saginaw River-1958 Act 
Flint, MI
(Contributed Funds) 
75. Sebewaing River, MI 
New Work 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
New Work 
Appropriation 
Cost 
Maintenance 
Appropriation 
Cost 
207,862 
207,862 
249,700 
249,700 
2,591,286 
2,591,286 
926,415 
926,415 
17,567 
17,567 
1,000 
4,827 
(58,000) 
40,269
0
0 
0
0
0
0
0
0 
0 
148,628
0
0
0
0
0
0 
7,500 
7,243 
1,000,000 
505,883 
24,755,359 
24,755,359 
173,000 
173,000 
1,000,000 
505,883 
365,642 
365,642 
426,455 
426,384 
0
0 
0
0 
5,311 
4,891 
15,000 
13,872 
(2,000) 
(266) 
21-67

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
79. Surveillance of North New Work 
Boundary Waters Appropriation 0 0 0 0 0 
Cost 0 0 0 0 0 
Maintenance 
Appropriation 1,440,000 1,483,500 1,848,000 1,988,000 49,648,8347' 
Cost 1,458,207 1,440,678 1,853,588 2,025,027 49,571,509" 
'Includes $18,889 for previous projects. 
21ncludes $114,786 for previous projects. 
3Excludes $56,500 contributed funds. 
4Includes $85,849 for previous projects. 
Slncludes $12,008 for maintenance of previous projects. 
'Includes $255,000 contributed funds. 
7Includes $25,500 for previous projects and $289,752 
contributed funds for existing projects. 
5Includes $2,097,254 for previous projects. 
9lncludes $1,547,195 for new work for previous projects. 
1llncludes $3,239,910 for previous projects. 
"Includes $89,309 for previous projects. 
'2 lncludes $31,709 contributed funds. 
'3 lncludes $311,329 for previous projects. 
'4lIncludes $13,437 for previous projects. 
s5s'lncludes $396,974 for previous projects. 
6"Includes $109,463 for previous projects. 
'7Includes $8,918 for previous projects. 
"Includes $176,620 for new work, $127,598 for maintenance. 
'lncludes $35,705 contributed funds. 
2"Includes $148,000 contributed funds for existing project. 
2'Ilncludes $453,839 for previous projects. 
22Excludes $3,000 contributed funds. 
23Includes $21,818 for previous projects. 
24Includes $149,312 for previous projects. 
2SIncludes $88,364 for previous projects. 
MIncludes $402,242 for previous projects. 
27Includes $656,000 for previous projects. 
2Includes $235,346 for previous projects. 
Includes $354,139 contributed funds. 
3"Includes $57,670 contributed funds. 
3 tlIncludes $491,416 for previous projects. 
32Excludes $136,286 contributed funds. 
"Includes $354,999 for previous projects. 
"Includes $150,910 for previous projects. 
"Includes $3,955 for previous projects. 
36Includes $400,126 for previous projects. 
37"Includes $54,288 for previous projects. 
3Includes $312,423 for previous projects. 
"Includes $36,194 for previous projects. 
40Includes $1,293,220 for previous projects. 
41Includes $459,305 for previous projects. 
42Includes contributed funds of $3,000,000 
for new work, and 
x3$166,667 for maintenance contributed by: 
Port Commission of Monroe, $300,000; 
Consolidated Paper Co. $125,000; and 
River Raisin Co., $41,667. 
"Includes $613,408 for previous projects. 
45 
Includes $446,183 for previous projects. 
"46Includes $84,569 for previous projects. 
47 ncludes $8,161 for previous projects. 
"Includes $284,802 for previous projects. 
49Includes $113,326 for previous projects. 
l"Includes $172,100 contributed funds. 
51lncludes $188,495 for previous projects. 
52Includes $15,123 for previous projects. 
53"Includes $50,084 for previous projects. 
"Includes $56,608 for previous projects. 
SSIncludes $962,556 for previous projects. 
"Includes $1,671,660 Public Works funds and 
$49,419 Emergency Relief funds. 
7"Includes $503,113 for previous projects. 
"Includes $2,904,807 for previous projects. 
59lncludes $90,232 for previous projects. 
60Includes $117,554 for previous projects. 
61"Includes $15,000 for previous projects. 
62Includes $487,817 for previous projects. 
63Includes $87,131 for previous projects. 
"Includes $187,233 for previous projects. 
6SIncludes $131,239 for previous projects. 
6"Includes $323,419 for previous projects. 
67lIncludes $219,730 for previous projects. 
"Includes $48,404 National Recovery Act for 
new work funds. 
"Includes $212,857 for previous projects. 
70lIncludes $33,113 for previous projects. 
71 lncludes $3,973,897 for previous projects. 
21-68

TABLE 21-B 
DETROIT, MI DISTRICT 
AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Sep. 19,1890 
Mar. 2, 1919 
Sep. 22, 1922 
Aug. 30, 1935 
Oct. 27, 1965 
Nov. 17, 1986 
Mar. 3, 1905 
Aug. 5, 1886 
Aug. 11, 1888 
Mar. 3, 1899 
Jun. 6, 1990 
Aug. 8, 1917 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Mar. 2, 1945 
May 20, 1965 
Mar. 2, 1945 
Sep. 19, 1890 
Jul. 13, 1892 
Sep. 22, 1922 
ALPENA HARBOR, MI (See Section 1 of Text) 
Channel depth of 16 1/2 feet. 
Rubblemound breakwater for protecting channel 
on south side and widening entrance channel. 
21 and 18 1/2 foot channel depths and turning basin. 
Present project dimensions. New turning basin. 
Removal of old breakwater and construction of new breakwater. 
Deauthorization of the feature authorized by the 1965 River and 
Harbor Act. 
ARCADIA HARBOR, MI (See Section 2 of Text) 
Maintenance of existing 12-foot channel. 
ASHLAND HARBOR, MI (See Section 3 of Text) 
Breakwater 7,900 feet long and dredging to remove a shoal. 
Appropriation of $60,000 for 'Continuing improvements on enlarged 
project' (On completion of Poe Lock in 1896, with available depth of 
20 feet, dredging at Ashland Harbor was carried to a similar depth.) 
Detached breakwater extending 4,700 feet out from shore at a point 
2,600 feet east of main breakwater (prolonged) and parallel thereto. 
Project modified by omitting detached breakwater and defining depth 
and extent of channel to be dredged. 
Widening part of present channel for entrance channel and for basin 
in eastern part of harbor. 
Deepening east basin to 25 feet and west channel, as far as 8th Ave. 
West, extended to 21 feet. 
Widening west channel to 750 feet at its westerly end. 
Deepening portions of east basin and west channel to 27 and 21 feet, 
respectively. 
AU SABLE HARBOR AT AU SABLE RIVER (OSCODA), MI 
(See Section 4 of Text) 
Dredging channels 12 and 10 feet deep and riprapping North Pier. 
BAY PORT HARBOR, MI (See Section 5 of Text) 
Channel 6 feet deep and 50 feet wide. 
BIG BAY HARBOR, MI (See Section 6 of Text) 
Provides for converging piers extending from shore, an entrance channel 
between piers and a rectangular harbor basin. Project depths are 
12 feet in entrance channel and 10 feet in harbor basin. 
BLACK RIVER (PORT HURON), MI (See Section 7 of Text) 
Channel from mouth of Grand Trunk R.R. Bridge. 
Channel from Grand Trunk R.R. Bridge to Washington Ave. 
Consolidation of projects for Black River at Port Huron and 
Mouth of Black River. 
Annual Report, 1889, p. 2288. 
H. Doc. 830, 65th Cong., 2d Sess., 
and Rivers & Harbors Comm. 
Doc. 1, 67th Cong., 1st Sess. 
Rivers and Harbors Comm. 
Doc. 42, 72d Cong., 1st. Sess. 
H. Doc. 151, 88th Cong., 1st. Sess.' 
H.R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986). 
H. Doc. 194, 58th Cong., 2d Sess. 
H. Ex. Doc. 89, 48th Cong., 2d Sess. 
Annual Reports, 1886, p. 1674; and 
1887, p. 1966. 
H. Doc. 1698, 64th Cong., 2d Sess. 
S. Doc. 133, 71st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 46, 82d Cong., 1st Sess. 
H. Doc. 337, 77th Cong., 1st Sess. 
H. Doc. 165, 86th Cong., 1st Sess.' 
H. Doc. 446, 78th Cong., 2d Sess.' 
Section 107, 1960 Rivers and 
Harbors Act. 
H. Doc. 446, 78th Cong., 2d Sess.' 
Annual Report, 1889, p. 2291. 
No Printed Report. 
H. Doc. 436, 64th Cong., 1st Sess. 
21-69

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 3, 1930 
Aug. 30, 1935 
Apr. 23, 1970 
Settling Basin 
Deepening channel and settling basin to 20 feet, and widening to 100 feet 
2 bends; 1 at the foot of 12th St., the other below the Grand Trunk R.R. 
Bridge. 
Extension of existing channel. 
BLACK RIVER HARBOR, MI (UPPER PENINSULA) 
(See Section 8 of Text) 
Two converging breakwaters, an entrance channel between breakwaters, 
an inner channel, and an irregular harbor basin. Project depths 12 feet 
in approach channel and 8 feet in the river channel and basin. 
BOLLES HARBOR, MI (See Section 9 of Text) 
Entrance channel in Lake Erie, Access channel in LaPlaisance Creek, 
Steel sheet pile revetment. 
CASEVILLE HARBOR, MI (See Section 10 of Text) 
Channel 10 to 8 feet deep protected by Breakwater. 
CHARLEVOIX HARBOR, MI (See Section 11 of Text) 
Channel from Lake Michigan to Round Lake protected where needed 
by piers and revetments. 
Channel from Round Lake to Lake Charlevoix. 
Project depth increased to 15 feet. 
Project depth increased to 18 feet. 
Restore recreational uses or provide comparable recreational uses at the 
South Pier. 
Project depth increased to 24 and 23 feet, and construction of revetment 
upstream of Highway Bridge. 
CLINTON RIVER, MI (See Section 12 of Text) 
Channel in River and Lake St. Clair, Pile Dike, Closing channels and 
making Cutoff, and revetments as needed. 
Widening entrance channel and constructing protected harbor basin. 
CORNUCOPIA HARBOR, WI (See Section 13 of Text) 
Entrance channel 50 feet wide and 10 feet deep between existing piers 
from bay to a turning basin 200 feet long, 8 feet deep, with maximum 
width of 180 feet, with 150- and 300-foot inner channels each 50 feet 
wide and 8 feet deep. 
Reconstruction and Federal maintenance of east and west entrance piers, 
a 25-foot extension of west pier and a 300-foot extension of existing 
westerly inner channel at a depth of 8 feet and a width of 50 feet. 
21-70 
H. Doc. 162, 71st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
54, 72d Cong., 2d Sess. 
Section 107, 1960 Rivers and 
Harbors Act. 
H. Doc. 446, 78th Cong., 2d Sess.' 
Section 107, 1960 Rivers and 
Harbors Act. 
H. Doc. 64, 87th Cong., 1st Sess.' 
S. Ex. Doc. 16, 44th Cong., 1st Sess. 
and Annual Report 1876, p. 523. 
No Prior Survey of Estimates. 
No Prior Survey of Estimates. 
S. Doc. 163, 75th Cong., 3rd Sess.' 
H. Doc. 1098, 100th Cong., 2d Sess., 
Sec. 25 of the WRDA of 1988. 
Section 107, 1960 Rivers and 
Harbors Act. 
S. Doc. 199, 46th Cong., 2d Sess. 
Annual Report, 1880, p. 2062, and 
H. Doc. 210, 44th Cong., 2d Sess., 
and Annual Report, 1886, p. 219. 
Section 107, 1960 Rivers and 
Harbors Act. 
S. Committee, 75th Cong., 1st. Sess. 
H. Doc. 434, 83rd Cong., 2d Sess.' 
Mar. 2, 1945 
Jul. 6, 1965 
Oct. 23, 1962 
Aug. 14, 1876 
Aug. 2. 1882 
Jun 13, 1902 
Jun. 20, 1938 
Nov. 17, 1988 
Mar. 29, 1977 
Aug. 5, 1886 
Jul. 19, 1963 
Aug. 26, 1937 
Sep. 3, 1954

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 13, 1902 
Mar. 3, 1905 
Jun. 25, 1910 
Mar. 4, 1913 
Mar. 2, 1907 
Jun. 25, 1910 
Mar. 2, 1919 
Jul. 3, 1930 
Aug. 30, 1935 3 
Aug. 26, 1937 
Mar. 2, 1945 
Jul. 24, 1946 * 
May 17, 1950 ' 
Mar. 21, 1956 " 
Jul. 14, 1960 
Aug. 13, 1968 32 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 1907 
May 28, 1908 s 
Jul. 27, 1916 
Mar. 2, 1919 
Jan. 21, 1927 
Jul. 30, 1930 3 
DETROIT RIVER, MI (See Section 14 of Text) 
Amherstburg Channel and removal of Grosse lie Shoal. 
Fighting Island Channel. 
Livingstone Channel. 
Channel Depths of 26 and 25 feet. 
Channel to Wyandotte 21 feet deep and 300 feet wide through Middle 
Ground opposite Head of Fighting Island. 
Trenton Channel and Turning Basin (West of Grosse Ile). 
American Channel North of Belle Isle between Windmill Point and 
Fairway Slip, Detroit. 
Deepen Westerly 300 feet of Amherstburg Channel and Ballards Reef 
Channel below Livingstone Channel to 27 feet to provide depths 
adequate for 24-foot draft navigation when governing Lakes are at 
Datum, with necessary widening at approaches and bends and 
construction of necessary compensating works, Detroit River. 
Extend Turning Basin in Trenton Channel 600 feet. Dredge through 
East Draw of lower Grosse Ile Bridge and extend 300-foot width of 
Channel North of lower Grosse Ile Bridge. 
Channel Depth of 28.5 feet throughout downbound and Two-Way 
Channels, except in upper (27.7-foot depth) and lower (29-foot depth), 
Livingstone Channel, and in upbound Channel; 27-foot depth in Ballards 
Reef Channel below junction with Livingstone Channel, 27.5-foot depth 
in westerly 300-foot width of Limekiln Crossing and Amherstburg 
Reaches, and 28.5-foot depth in westerly 300-foot width of Hackett 
Beach, with necessary compensation works. Also 28.5-foot depth in 
Lake Erie from Detroit River to Pelee Passage Shoal, inclusive. 
Trenton Channel: Deepen to 25 feet, where necessary, Wyandotte Reach 
from Detroit River to Upper Grosse lie Bridge, about 5.5 miles, deepen 
to 28 feet and widen to 300 feet below Upper Grosse lie Bridge to and 
including a Turning Basin 28 feet deep and 15 feet across in area outside 
project limits. 
Trenton Channel: Deepen to 28 feet and widen to 300 feet from Upper 
Turning Basin at Trenton to Gibraltar, about 20,500 feet from downstream: 
Construct a Turning Basin at Gibraltar at a depth of 28 feet, 
width of 830 feet, and length of 1,500 feet: Build compensating works 
to maintain water levels. 
DULUTH-SUPERIOR HARBOR, MN AND WI 
(See Section 15 of Text) 
Dredging. 
Rebuilding piers at Superior Entry. 
Enlarge plan for Superior Entry and additional dredging near draw 
span of Burlington Northern railway bridge. 
Dredging additional area of basin inside Duluth entrance to 22-foot 
depth. 
Enlarging Superior Harbor Basin. 
Removal of shoal point at southerly end of East Gate Basin. 
Howards Bay Channel, 20 feet deep. 
H. Doc. 712, 56th Cong., 1st. Sess. 
and 40, 58th Cong., 3rd Sess. 
H. Doc. 17, 62d Cong., 1st Sess. 
H. Doc. 266, 59th Cong., 1st Sess.; 
676, 61st Cong., 2d Sess.; and 
322, 65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st. Sess. 
Rivers and Harbors Committee Doc. 
1, 72d Cong., 1st Sess.' 
H. Doc. 205, 75th Cong., 1st Sess. 
H. Doc. 734, 79th Cong., 2d Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 30, 81st Cong., 1st Sess.' 
S. Doc. 71, 84th Cong., 1st Sess.' 
H. Doc. 319, 86th Cong., 2d Sess.' 
H. Doc. 338, 90th Cong., 2d Sess.' 
H.Ex. Doc. 59, 53d Cong., 3rd Sess. 
and Annual Report, 1895, p. 2538. 
H. Doc. 82, 59th Cong., 2d Sess. 
H. Doc. 221, 60th Cong., 1st Sess. 
H. Doc. 651, 64th Cong., 1st Sess. 
H. Doc. 1018, 64th Cong., 1st Sess. 
H. Doc. 145, 69th Cong., 1st Sess., 
and Rivers and Harbors Committee 
Doc. 32, 71st Cong., 2d Sess. 
21-71

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1930 3 
Jul. 16, 1952 4 
Jul. 14, 1960 .2 
Oct. 4, 1961 
Nov. 17, 1986 
Aug. 5, 1886 
Sep. 19, 1890 
Jun. 3, 1896 
Jun. 3, 1896 
Jun. 13, 1902 
Mar. 2, 1907 
Mar. 3, 1925 " 
Jun. 26, 1934 9 
Jul. 3, 1958 o10 
Jun. 23, 1866 " 
Mar. 3, 1925 
Aug. 26, 1937 
Oct. 27, 1965 
Jun. 23, 1866 
Jun. 14, 1880 
Sep. 19, 1890 
Jul. 13, 1892 
Jul. 3, 1930 
Aug. 26, 1937 
Mar. 2, 1945 
Nov. 17, 1986 
Deepening and widening channels and basins. 
Deepen Superior Front Channel and a portion of East Gate Basin to 
25 feet. 
Present project dimensions of channels and basin. 
Abandons northerly portion of 21st Avenue West Channel. 
Deepen portions of the North and South Channels, the entire Upper 
Channel and Minnesota Channel to 27 feet; widen the Cross Channel 
turning basin to 1,500 feet; widen the bend at the Arrowhead Bascule 
Bridge to 600 feet, and construct an upland CDF. 
FOX RIVER, WI (See Section 16 of Text) 
Improvement of Fox River. 
Dredging Fond du Lac Harbor on Lake Winnebago. 
Improvement of Wolf River. 
Improvement of Stockbridge, of Calumet and Miller Bay, and of 
Brothertown Harbor, on Lake Winnebago. 
Increased depth in rock cuts on lower river, widen Neenah Channel, and 
a concrete retaining wall at Kaukauna. 
Operation and care of locks and dams provided for with funds from War 
Department appropriations for rivers and harbors. 
Sec. 108, that Federal project structure, appurtenances, and real property 
of Upper Fox River, WI, be disposed of to State of Wisconsin. 
FRANKFORT HARBOR, MI (See Section 17 of Text) 
A New Outlet 12 feet deep protected by Piers and Revetments. 
Exterior Breakwaters, removal of portions of Piers, Project 
Dimensions of Outer Basin. 
Dredge the area in Lake Betsie. 
Deepen approach and entrance channels. Extend Inner Basin and 
Dredge recreational anchorage area. 
GRAND HAVEN HARBOR, MI (See Section 18 of Text) 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Piers and Revetments. 
Present Project dimensions of Harbor channel to Grand Trunk Car Ferry 
Slip and River Channel. Eliminating all of that portion of Grand River 
above Bass River, Consolidation of Projects for Harbor and River. 
Channel to Spring Lake. 
Present Project Dimensions of Harbor Channel from Car Ferry Slip to 
Grand Trunk Railway Bridge and Turning Basin. 
Deepen the harbor entrance channel and harbor river channel to 29 and 
27 feet, respectively; provide a new and larger turning basin, 
trapezoidal in shape, 1,200 feet long at the channel, 300 feet long at 
the shore, 800 feet at a right angle to the channel, and 18 feet deep. 
H. Doc. 482, 72d Cong., 2d Sess. 
H. Doc. 374, 82d Cong., 2d Sess. 
H. Doc. 150, 86th Cong., 1st Sess.; 
H. Doc. 196, 86th Cong., 1st Sess. 
H. Doc. 204, 99th Cong., 2d Sess. 
Sec. 202a of WRDA of 1986. 
Annual Report, 1885, pp. 2041-2045 
(plan of a board approach Dec. 10, 
1884, as modified by Corps of 
Engineers, May 14, 1886). 
H. Ex. Doc. 24, 51st Cong., 1st Sess. 
Annual Report, 1890, p. 2390. 
No prior survey or estimates. 
No prior survey or estimates. 
No prior survey or estimates. 
H. Doc. 294, 68th Cong., 1st Sess.' 
S. Bill 3910, 85th Cong., 2d Sess. 
H. Doc. 482, 5th Cong., 2d Sess. 
H. Doc. 208, 68th Cong., 1st Sess. 
H. Doc. 511, 74th Cong., 2d Sess., 
S. Doc 16, 89th Cong., 1st Sess.' 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Ex. Doc. 42, 35th Cong., 1st Sess. 
S. Doc. 88, 71st Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
1, 75th Cong., 3rd Sess.' 
H. Doc. 661, 76th Cong., 3rd Sess.' 
21-72

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 14, 1880 
Jun. 14, 1880 
May 17, 1950 
Mar. 3, 1879 
Aug. 30, 1935 
May 17, 1950 
Mar. 2, 1945 
Jun. 23, 1866 
Jul. 13, 1892 
Jun. 26, 1910 
Aug. 8, 1917 
Mar. 3, 1925 
Aug. 30, 1935 2 
Aug. 26, 1937 
Mar. 2, 1945 
Oct. 23, 1962 
Nov. 17, 1986 
Mar. 2, 1945 
Mar. 3, 1871 
Jan. 21, 1927 
Jul. 16, 1984 
GRAND MARAIS HARBOR, MI (See Section 19 of Text) 
Existing Project, except for pile dike. 
For Pile Dike. 
800-foot extension of West Pier. 
GRAND MARAIS HARBOR, MN (See Section 20 of Text) 
Breakwaters and dredging of anchorage area of 26 acres to 16 feet. 
Seawalls across ledge in southeast corner of harbor, enlarging anchorage 
basin and deepening of entrance. 
Small-boat basin with breakwater. 
GRAND TRAVERSE BAY HARBOR, MI (See Section 21 of Text) 
Two parallel piers, an entrance channel between piers and a harbor basin. 
Project depths are 12 feet between piers and 10 feet in basin. Project 
area extended 200 feet upstream in 1966. 
GREEN BAY HARBOR, WI (See Section 22 of Text) 
Outer Channel and revetment at Grassy Island. 12 
Inner channel. 3 
Turning basin at DePere. 
Maintenance of turning basin at DePere. 
Increasing depth of inner channel and turning basin to 18 feet. 
Deepen outer channel to 22 feet with widening and straightening inside 
of Tail Point Bend, widen channel in Fox River through city of Green 
Bay to 22 feet. 
Turning basin above Chicago & North Western R.R. Bridge. 
Turning basin at mouth of East River. 
Deepen and widen 9 miles of entrance channel to 26 by 500 feet; 
3.6 miles of entrance channel to 24 by 300 feet; and 3.2 miles of 
existing Fox River to 24 feet deep. 
Deepen the Fox River channel at Green Bay, WI, to 27 feet. 
HAMMOND BAY HARBOR, MI (See Section 23 of Text) 
Harbor of Refuge, breakwaters, 10-foot depth in harbor basin, 12-foot 
depth in entrance channel. 
HARBOR BEACH, LAKE HURON, MI (See Section 24 of Text) 
Adopted Site and made provision for harbor. Closing North Entrance and 
dredging Main Entrance and Anchorage Area. 
Removal of portion of Breakwater in interest of sanitation. 
Deepen the waterway within the Marina facility. 
Specified in Act. Annual Report 
1881, p. 2050. 
Annual Report, 1895, p. 351. 
H. Doc. 751, 80th Cong., 2d Sess. 
H. Ex. Doc. 75, 43rd Cong., 2d 
Sess.; Annual Report, 1875, p. 184 . 
Rivers and Harbors Committee Doc. 
22, 72d Cong., 1st Sess.' 
H. Doc. 187, 81st Cong., 1st Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report, 1867, p. 70. 
Unpublished report approved 
Aug. 3, 1892. 
H. Doc. 222, 61st Cong., 2d Sess. 
H. Doc. 1017, 64th Cong., 1st Sess. 
H. Doc. 294, 68th Cong., 1st Sess. 
Rivers and Harbors Committee Doc. 
40, 72d Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
73, 74th Cong., 2d Sess. 
H. Doc. 95, 76th Cong., 1st Sess. 
H. Doc. 470, 87th Cong., 2d Sess.' 
H.R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986, 
Sec. 601c). 
H. Doc. 446, 78th Cong., 2d Sess. 
Annual Report, 1873, p. 282; 
H. Doc. 1700, 64th Cong., 2d Sess. 
H.R. 5653, 98th Cong., 2d Sess.; 
P.L. 98-360 (98 Stat. 405) Sec. 105. 
21-73

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1852 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 3, 1905 
Jul. 3, 1930 
Aug. 30, 1935 
Sep. 3, 1954 22 
Sep. 3, 1954 
Sep. 2, 1964 
Mar. 3, 1899 
Mar. 2, 1907 
Aug. 30, 1935 2 
May 17, 1950 
Oct. 23, 1962 22 
Mar. 3, 1881 
Jun. 25, 1910 
Aug. 30, 1935 2.14 
Jul. 14, 1960 
Sep. 19, 1890 
Jun. 25, 1910 
Mar. 2, 1919 
HOLLAND HARBOR, MI (See Section 25 of Text) 
Artificial channel between Lakes Macatawa and Michigan.'2 
Piers and Revetments.' 2 
Extending Inner Piers. 
Converging Breakwater. 
Channel to Holland and Turning Basin at Holland. 
Present Project Dimensions of Channels at Turning Basin. 
Widen Bend in Revetted Entrance Channel into Lake Macatawa, 
Dredge Channel in Black River, and Widen and Extend Turning Basin. 
THE INLAND ROUTE, MI (See Section 26 of Text) 
Channel 30 feet wide and 5 feet deep through Lakes and Rivers with 
suitable jetties. 
Lock and Dam. 
KENOSHA HARBOR, WI (See Section 27 of Text) 
Parallel piers and 600 feet of breakwater.' 2 
Extending Breakwater 200 feet. 
Present project dimensions of entrance channel and basin. 
Channel northwesterly from basin. 
Deepen lake approach channel to 27 feet and 800 feet wide; deepen 
approach channel to 26 feet, entrance channel and inner basin to 25 feet. 
KEWAUNEE HARBOR, WI (See Section 28 of Text) 
Entrance piers. 
Turning basin. 
North breakwater, remove old north pier, widen and deepen entrance 
channel and turning basin to 20 feet and remove outer south shoal. 
Enlarge existing turning basin, extend existing project into north basin, 
and increase depth of north basin to 20 feet at a maximum width of 
500 feet and eliminate removal of outer shoal. 
KEWEENAW WATERWAY, MI (See Section 29 of Text) 
Acquision of waterway; for a 16-foot channel of 70-foot bottom width, 
renew canal revetments, reconstruct and extend piers at upper entrance 
to 30-foot depth of water, and at proper time for increase of channel 
depth to 20 feet with bottom width of not less than 120 feet (increase 
in width and depth of channel approved May 15, 1898). 
Anchorage basin just within lower entrance about one-half mile long, 
800 feet wide; a mooring pier on its westerly side 2,000 feet in length, 
and for purchase of necessary land. 
Princess Point Cutoff channel. 
S. Ex. Doc. 41, 35th Cong., 1st Sess. 
Annual Report, 1866, p. 106. 
H. Doc. 272, 51st Cong., 2d Sess.; 
and Annual Report 1887, p. 2950. 
Annual Report, 1905, p. 2176; 
H. Doc. 588; 69th Cong., 2d Sess. 
Rivers and Harbors Committee Doc. 
48, 74th Cong., 1st Sess. 
H. Doc. 282, 83rd Cong., 2d Sess. 
H. Doc. 142, 82d Cong., 1st Sess.' 
Chief of Engineers. 
H. Doc. 328, 54th Cong., 2d Sess.; 
Annual Report, 1897, p. 2772; 
H. Doc. 164, 55th Cong., 3rd Sess.; 
Annual Report, 1899, p. 1817. 
H. Doc. 62, 59th Cong., 2d Sess. and 
Rivers and Harbors Committee 
Doc. 3, 5th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 19, 74th Cong., 1st Sess. 
H. Doc. 750, 80th Cong., 2d Sess. 
H. Doc. 496, 87th Cong., 2d Sess.' 
Annual Report, 1881, p. 2082. 
H. Doc. 324, 60th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 43, 72d Cong., 1st Sess.' 
S. Doc. 19, 86th Cong., 1st Sess.' 
H. Ex. Doc. 105, 49th Cong., 2d 
Sess.; and Annual Report, 1887, 
p. 1977. 
H. Doc. 325, 60th Cong., 1st Sess. 
H. Doc. 835, 63rd Cong., 2d Sess. 
21-74

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 30, 1935 '" 
Nov. 17, 1986 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Mar. 2, 1919 
Jul. 3, 1930 
Aug. 30, 1933 3 
Mar. 21, 1956 
Aug. 30, 1935 
Oct. 23, 1962 
Oct. 27, 1965 
Mar. 2, 1945 
Mar. 2, 1867 
Mar. 3, 1899 
Mar. 2, 1907 
Dec. 31, 1970 
Mar. 2, 1867 
Sep. 19, 1890 
General deepening, widening and straightening of channels and basins 
to provide 25-foot depth with additional overdepth at entrances, extend 
lower entrance breakwater, and necessary alteration or replacement of 
structures due to deepening channels. 
Deauthorization of the uncompleted portion of the project authorized by 
the 1935 Rivers and Harbors Act. 
LA POINTE HARBOR, WI (See Section 30 of Text) 
Provides for reconstruction of 73.5 feet of the existing breakwater, 
extending the breakwater 126.24 feet with 5 new steel sheet pile cells, 
harbor dredging and related work. The harbor is 10 feet deep in the 
entrance and 8 feet deep in the basin. 
LAKE ST. CLAIR, MI, CHANNELS (See Section 31 of Text) 
Two Dikes. 
Deepening Canal and dredging Channel at Grosse Pointe. 
Second Canal for downbound vessels. 
21-foot depth in Grosse Pointe Channel for about 5.25 miles. 
25-foot depth through Canals and Channel through Lake St. Clair. 
Removal of Center Dike and widening Channel to 700 feet. 
Deepening Channel to 27.5 feet and abandonment of Channel above 
mouth of Southeast bend cutoff Channel. 
LELAND HARBOR, MI (See Section 32 of Text) 
Entrance Channel protected by Piers. 
Outer Breakwater, Anchorage Area, Approach Channel and removal 
of North Pier. 
LEXINGTON HARBOR, MI (See Section 33 of Text) 
Approach Channel and Maneuver Area Protected by Breakwaters.' 
LITTLE LAKE HARBOR, MI (See Section 34 of Text) 
12-foot deep Channel from Lake Superior into Little Lake Breakwaters 
and Revetments. 
LUDINGTON HARBOR, MI (See Section 35 of Text) 
Entrance Piers. 
Pier Extension, Reconstruction and repairs to existing structures 
and present project dimensions of Channel. 
Breakwaters, Shore Connections, and Removal of outer ends of the 
two inner piers. 
Deepen Channels and widen opening between breakwaters. 
MANISTEE HARBOR, MI (See Section 36 of Text) 
Entrance Piers. 
Extending Channel 8,000 feet to connect with Manistee Lake, and 
further Pier extension. 
H. Doc. 55, 73rd Cong., 1st Sess.' 
H.R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986). 
Section 107 of the 1960 Rivers 
and Harbors Act; P.L. 645, 86th 
Cong., as amended. 
Annual Report, 1885, p. 2150. 
H. Doc. 297, 51st Cong., 2d Sess. 
H. Doc. 234, 56th Cong., 2d Sess. 
H. Doc. 188, 65th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 3, 72d Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess.' 
Rivers and Harbors Committee 
Doc. 23, 74th Cong., 1st Sess. 
H. Doc. 413, 87th Cong., 2d Sess. 
H. Doc. 301, 88th Cong., 2d Sess. 
H. Doc. 446, 78th Cong., 2d Sess.' 
Annual Report, 1867, p. 114."16 
H. Doc. 273, 54th Cong., 2d Sess.; 
and Annual Report, 1897, p. 2951. 
H. Doc. 62, 59th Cong., 1st Sess.; 
and Rivers and Harbors Committee 
Doc. 3, 59th Cong., 2d Sess."16 
H. Doc. 342, 91st Cong., 2d Sess. 
Annual Report, 1867, p. 115. 
Annual Report, 1891, P. 2678. 
21-75

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 25, 1912 
Jul. 3, 1920 
Mar. 2, 1945 
Jul. 14, 1960 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 2, 1907 
Aug. 30, 1935 '" 
Aug. 26, 1937 
Oct. 23, 1962 30 
Dec. 31, 1968 
(Sec. 107 of 
1960 R & H) 
Jun. 26, 1979 
Mar. 2, 1867 
Aug. 11, 1888 
Jun. 25, 1910 
Aug. 30, 1935' 
Jul. 11, 1960 
Mar. 3, 1871 
Jun. 13, 1902 
Mar. 4, 1913 
Depth of 20 feet in Outer Harbor 570 feet wide to Outer end of South 
Pier 18 feet deep in river, South Breakwater with shore connection, 
and extend North Pier if required. 
23-foot depths in entrance channel and 21-foot depths in River Channel. 
Remove old South Revetment, Construct new South Pier and Revetment, 
and widen river entrance Channel. 
Present project dimensions of Channel through Outer Basin and River, 
and Federal participation in cost of replacing Maple Street Bridge. 
MANISTIQUE HARBOR, MI (See Section 37 of Text) 
Breakwaters and Outer Harbor. 
Present location of West Breakwater and Pier at River Mouth. 
MANITOWOC HARBOR, WI (See Section 38 of Text) 
Breakwaters. 
Present project dimensions of channel through outer basin, removal of 
old north stub pier, and approach channel to a proposed city terminal 
south of shore end of south breakwater. 
Channel in river. 
Deepen Lake approach to 25 feet by 800 feet wide, deepen outer harbor 
to 25 feet, river channel to 23 feet to 8th Street, and Upper River 
Channel to 22 feet to Soo Line R.R. 
Dredge River Channel to 12 feet from Soo Line R.R. 720 feet upstream. 
Construct 765-foot long stone Breakwater, and rubblemound bulkhead; 
construct 360-foot long entrance Breakwater; dredge 16,500 cubic 
yards for entrance channel. 
MARQUETTE HARBOR, MI (See Section 39 of Text) 
Breakwaters, 2,000 feet long. 
Extending the breakwater 1,000 feet. 
Additional 1,500-foot extension to breakwater and removing a shoal 
in northerly part of harbor. 
Deepening harbor to 25 feet. 
Deepening harbor to 27 feet. 
MENOMINEE HARBOR AND RIVER, MI AND WI 
(See Section 40 of Text) 
Entrance piers. 
Consolidation of project for harbor and river, and a channel 18 feet deep. 
Partial restoration of work above bridge which had been eliminated by 
Act of May 3, 1905. 
H. Doc. 599, 62d Cong., 2d Sess. 
S. Doc. 131, 71st Cong., 2d Sess. 
H. Doc. 380, 77th Cong., 1st Sess. 
H. Doc. 358, 86th Cong., 2d Sess. 
H. Doc. 429, 58th Cong., 2d Sess. 
Annual Report, 1908, p. 648, and 
Unpublished Report of Mar. 13, 
1908; Approved by Secretary of War, 
Apr. 3, 1908. 
H. Doc. 62, 59th Cong., I1st Sess., as 
modified by Rivers and Harbors 
Comm. Doc. 3, 59th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 39, 73rd Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 80, 74th Cong., 2d Sess. 
H. Doc. 479, 87th Cong., 2d Sess. 
Jun. 1967 Detailed Project Report 
Apr. 1982 Supplement.' 
Sec. 107, 1960 Rivers and 
Harbors Act. 
H. Ex. Doc. 56, 39th Cong., 2d 
Sess., pts. I and 2; and Annual 
Report, 1866, pp. 8 and 77. 
Annual Report, 1889, pp. 272 
and 2021. 
H. Doc. 573, 61st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 20, 72d Cong., 1st Sess. 
H. Doc. 154, 86th Cong., 1st Sess.' 
Annual Report, 1867, p. 132. 
H. Doc. 419, 56th Cong., 1st Sess. 
21-76

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Jun. 27, 1967 
(Sec. 107) 
Aug. 30, 1852 
Mar. 3, 1883 
Mar. 2, 1907 
Sep. 22, 1922 
Aug. 30, 1935 2 
Mar. 2, 1945 1' 
Jul. 14, 1960 
Oct. 23, 1962 
Feb. 24, 1835 17 
Jul. 3, 1930 
Jul. 14, 1932 21 
Nov. 17, 1986 
Jun. 13, 1902 
Mar. 3, 1925 
Aug. 30, 1935 
Oct. 23, 1962 
Oct. 23, 1962 
20-foot depth in channel and 18-foot depth in turning basin. 
21-foot depth in channel and turning basin and enlarge turning basin. 
Extend channel 12 feet deep to vicinity of Marinette Yacht Club. 
Deepen existing approach channel to 26 feet, entrance and river channels 
to 24 feet and enlarge turning basin. 
Deepen 1,100 feet of river channel generally north of Marinette Corp. 
facilities to 19 feet. 
MILWAUKEE HARBOR, WI (See Section 41 of Text) 
North Pier.12 
Inner 7,600 feet of breakwater.'2 
South pier. Extending north breakwater 1,000 feet. 
Extend north breakwater; a south breakwater; present project 
dimensions of inner entrance channel. 
Dredging a portion of outer harbor to 21-foot depth. 
Dredging river channels to 21-foot depth. 
Deepen South Menominee and Burnham Canals to 21 feet. 
Deepen an approach channel to 30 feet by 800 feet wide and 300 feet wide 
through breakwater; deepen entrance channel 28 feet through piers, 
outer harbor to 28 feet south of entrance channel, and a channel to 
27 feet in Milwaukee River to Buffalo Street, and in Kinnickinnic River 
to Chicago & North Western R.R. bridges. 
MONROE HARBOR, MI (See Section 42 of Text) 
9-foot channel, protecting Revetments and Piers. 
21-foot channel, dikes and turning basin.2� 
Modified Conditions of Local Cooperation imposed by Act of 
Jul. 3, 1930. 
Deepen portion of existing navigation channel to 27 feet; deepen lake 
channel to 28 feet; widen the channel from 200 to 500 feet; dredge a 
new turning basin 24 feet deep, 1,600 feet wide at river's mouth; and 
construct a 190 acre CDF in Plum Creek Bay to enable creation of a 
700 acre marsh behind the CDF. 
MUSKEGON HARBOR, MI (See Section 43 of Text) 
Piers and Revetments. 
Breakwaters. 
Repairing Revetments around Car Ferry Slip. 
Channel deepening and present project dimensions of channel. Piers 
and Revetments. 
NEW BUFFALO HARBOR, MI (See Section 44 of Text) 
Entrance channel 10 feet deep by 80 to 180 feet wide and 850 feet long 
to mouth of Galien River, new north and south breakwaters 1,305 and 
740 feet, respectively, deepening inner channel to Galien River to 
8 feet and 80 feet wide and 1,250 feet long. 
H. Doc. 171, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 28, 73rd Cong., 2d Sess. 
H. Doc. 228, 76th Cong., 1st Sess. 
H. Doc. 113, 86th Cong., 1st Sess. 
Detailed Project Report, Dec. 1966. 
S. Doc. 175, 25th Cong., 2d Sess. 
Annual Report, 1881, p. 2122. 
Annual Report, 1906, p. 1752 (No 
prior survey or estimate affecting 
breakwater extensions). 
H. Doc. 804, 66th Cong., 2d Sess. 
H. Doc. 289, 72d Cong., 1st Sess. 
S. Doc. 29, 76th Cong., 1st Sess. 
H. Doc. 285, 86th Cong., 2d Sess. 
H. Doc. 134, 87th Cong., 1st Sess.' 
Annual Report, 1872, p. 237. 
Rivers and Harbors Committee 
Doc. 22, 71st Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 12, 72d Cong., 1st Sess.; 
45, 75th Cong., 1st Sess.' 
H. R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986). 
H. Doc. 104, 56th Cong., 2d Sess. 
H. Doe. 494, 67th Cong., 4th Sess. 
Rivers and Harbors Committee 
Doc. 64, 75th Cong., 1st Sess.' 
H. Doc. 474, 87th Cong., 2d Sess.' 
H. Doc. 474, 87th Cong., 2d Sess. 
21-77

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Aug. 2, 1882 
Jun. 25, 1910 
Jun. 25, 1910 
Aug. 26, 1937 
Oct. 23, 1962 30 
Nov. 17, 1986 
Aug. 2, 1882 
1883 
Aug. 30, 1935 
Mar. 2, 1945 
Jul. 14, 1960 
Jun. 27, 1967 
Sec. 107 
Mar. 2, 1945 
Jul. 16, 1984 
Jul. 11, 1987 
Mar. 2, 1945 
Jul. 11, 1870 
Aug. 14, 1876 
Aug. 30, 1935 a 
Jul. 3, 1958 29 
OCONTO HARBOR, WI (See Section 45 of Text) 
Piers, except for inner 300 feet of south pier and 250 feet north pier 
built by city. 
Present project dimensions of channel and turning basin. 
ONTONAGON HARBOR, MI (See Section 46 of Text) 
Channel 17 feet deep and 150 feet wide through bar and 15 feet deep 
and 100 feet wide between piers, and pier maintenance. 
Modified project widths and provide inner basin. 
Enlarging and deepening the existing harbor basin. 
Deauthorization of the turning basin feature of the project authorized 
by the 1962 Rivers and Harbors Act. 
PENSAUKEE HARBOR, WI (See Section 47 of Text) 
Construction of slab pier 2,500 feet long on the north side of the 
channel and dredging a channel 100 feet wide and 10 feet deep. 
Extending pier to 10-foot contour (2,700 feet) and dredging to 
10 feet below Datum. 
Dredging entrance channel 100 feet wide and 8 feet deep. 
PENTWATER HARBOR, MI (See Section 48 of Text) 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Piers and revetments, dredging. 
Present project depth of channel. 
PORT AUSTIN HARBOR, MI (See Section 49 of Text) 
Breakwater, Anchorage Basin, Channel Dredging. 
Construct a breakwater access for recreation purposes. 
Breakwater. 
PORT SANILAC HARBOR, MI (See Section 50 of Text) 
Entrance Channel 12 feet deep, Anchorage Basin, Breakwater. 
PORT WASHINGTON HARBOR, WI (See Section 51 of Text) 
North pier and south basin.'2 
North basin. 
North breakwater, removal of 650 feet of north pier, outer turning 
basin, present project dimensions of channel and basin and extension 
of south breakwater. 
Extending and raising of north breakwater and placing rubble along 
sides; removing 456 feet of south breakwater and dredging in outer basin. 
Annual Report, 1881, p. 2066. 
H. Doc. 538, 61st Cong., 
2d Sess., Plan C.' 
H. Doc. 602, 61st Cong., 2d Sess. 
S. Committee print, 74th Cong., 
2d Sess. 
H. Doc. 287, 87th Cong., 2d Sess. 
H. R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986). 
H. Doc. 153, 42d Cong., 3rd Sess. 
R & H Act, Aug. 2, 1882 Modified. 
H. Doc. 478, 74th Cong., 2d Sess.' 
H. Ex. Doc. 70, 39th Cong., 2d Sess 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Ex. Doc. 70, 39th Cong., 2d Sess. 
H. Doc. 181, 39th Cong., 2d Sess.' 
H. Doc. 446, 78th Cong., 2d Sess. 
H.R. 5653, 98th Cong., 2d Sess., 
P.L. 98-360 (98 Stat. 405) Sec. 106. 
P.L. 100-71. 
H. Doc. 446, 78th Cong., 2d Sess. 
H. Ex. Doc. 28, 41st Cong., 2d Sess. 
and Annual Report, 1879, p. 119. 
Annual Report, 1876, pt. 2, p. 379. 
H. Doc. 168, 72d Cong., 1st Sess. 
and Rivers and Harbors Committee 
Doc. 41, 74th Cong., 1st Sess. 
H. Doc. 446, 83rd Cong., 2d Sess.' 
21-78

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jun. 13, 1902 
Jun. 30, 1948 
Aug. 5, 1977 
Jun. 3, 1896 
Jun. 13, 1902 
Aug. 30, 1935 
Jul. 14, 1960 
Aug. 8, 1917 
Aug. 30, 19352,24. 
Jul. 3, 1958 2 
Oct. 23, 1962 2 
Jun. 25, 1910 
Jul. 3, 1930 
Aug. 26, 1937 
Jun. 20, 1938 
Sep. 3, 1954 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 13, 1892 
Jul. 8, 1930 
Mar. 2, 1945 
Jul. 24, 1946 2 
PORT WING HARBOR, WI (See Section 52 of Text) 
Construction of parallel piers and dredging. 
Dredging inner channels and abandonment of certain revetments 
and channels. 
Deauthorization of 50 feet of entrance channel widening. 
PRESQUE ISLE HARBOR, MI (See Section 53 of Text) 
Breakwater, 1,000 feet long. 
Shore extension, 216 feet long. 
For dredging and rubblemound extension to breakwater 1,600 feet 
long; Changed designation of project. 
Deepening harbor from 26 and 28 feet to 28 and 30 feet, respectively. 
ROUGE RIVER, MI (See Section 54 of Text) 
21-foot channel via the Shortcut Canal. 
25-foot channel at mouth of Old Channel, 1,425 feet long and adjacent 
to latter; 21-foot channel extending from junction of Old Channel and 
Shortcut Canal into Old Channel to Detroit, Toledo & Ironton R.R. 
Bridge. 
Old Channel; 100 feet wide from Peerless Cement Corp. to Junction with 
Shortcut Canal widened to 150 feet at 2 bends. 
25-foot channel over modified limits from Detroit River to Jefferson 
Avenue (via Shortcut Canal). 
SAGINAW RIVER, MI (See Section 55 of Text) 
Channel 200 feet wide, with depth of 18.5 feet in Bay and 16.5 feet 
in River. 
Project Depth of 18.5 feet extended up River to Saginaw. 
Turning Basin. 
Present project channel dimensions from Bay to Sixth Street Bridge 
in Saginaw. 
New Channel in Bay, 350 feet wide and 24 feet deep from 24-foot 
contour to River Mouth, Project Depth of 24 feet in River Channel 
up to Detroit & Mackinac Railway Bridge, Project Depth of 22 feet 
in River Channel up to Sixth Street Bridge, Turning Basins at 
Essexville and Carrollton, and elimination of present Channel in Bay. 
Deepen Bay Channel, Deepen River Channel to Detroit & Mackinac 
Bridge, Extend 22-foot project above Sixth Street Bridge, Deepen 
Essexville Turning Basin, and Construct 2 new Turning Basins. 3 
Deepen River Channel to 25 feet, from Detroit & Mackinac Bridge 
to New York Central Railroad Bridge. 
ST. CLAIR RIVER, MI (See Section 56 of Text) 
20-foot Channel in the River. 
Deepen Channel to 25 and 26 feet, and Compensating Works. 
Widening Channel at Southeast Bend to 700 feet. 
Widen and deepen Southeast Bend and improve Outlet of North 
Channel, St. Clair River. 
H. Doc. 114, 56th Cong., 1st Sess. 
H. Doc. 668, 80th Cong., 2d Sess. 
H. Doc. 318, 54th Cong., 1st. Sess.; 
Annual Report, 1903, pp. 474, 1823 
H. Doc. 473, 72d Cong., 2d Sess. 
H. Doc. 145, 86th Cong., 1st Sess. 
H. Doc. 1063, 64th Cong., 2d Sess. 
H. Doc. 125, 85th Cong., 1st. Sess. 
H. Doc. 509, 87th Cong., 2d Sess.' 
H. Doc. 740, 61st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 30, 71st Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 21, 75th Cong., 1st Sess. 
H. Doc. 576, 75th Cong., 3rd Sess. 
H. Doc. 500, 83rd Cong., 2d Sess. 
H. Doc. 554, 87th Cong., 2d Sess. 
H. Doc. 240, 89th Cong., 1st Sess.' 
H. Doc. 207, 51st Cong., 2d Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
H. Doc. 309, 77th Cong., 1st Sess. 
H. Doc. 335, 80th Cong., 1st Sess. 
21-79

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 21, 1956 " 
Nov. 17, 1986 
Mar. 3, 1875 
Jun. 14, 1880 
Mar. 3, 1899 
Aug. 30, 1935 
Jun. 2, 1937 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 11, 1870 
Aug. 5, 1886 
Jul. 13, 1892 
Jun. 13, 1902 
Jun. 13, 1902 
Mar. 3, 1907 
Mar. 3, 1909 
Jul. 25, 1912 
Mar. 4, 1915 
Sep. 22, 1922 
Jan. 21, 1927 
Jul. 3, 1930 
Jun. 26, 1934 9 
Aug. 30, 1935 
Mar. 7, 1942 
Jun. 15, 1943 
Mar. 2, 1945 
Deepen and further improve Channels in St. Clair River between limits 
of 27.1 to 30 feet to provide safe navigation by vessels with drafts 
of 25.5 feet. A cutoff Channel in Canada at Southeast Bend and 
abandon old Southeast Bend Channels. 
Deauthorization of the work authorized by the Rivers and harbors Act 
of Jul. 24, 1946. 
ST. JOSEPH HARBOR, MI (See Section 57 of Text) 
Interior Revetments.2 
Benton Harbor Canal. s 
Present project dimensions of piers and a turning basin. 
Present project dimensions of the channel and turning basin near 
mouth of Paw Paw River. 
Abandon easterly 1,000 feet of canal above west line of 9th Street. 
Turning basin above mouth of Morrison Channel and eliminate turning 
basin near mouth of Paw Paw River. 
Maintenance of turning basin near mouth of Paw Paw River. 
ST. MARYS RIVER, MI (See Section 58 of Text) 
Weitzel Lock (Replaced in 1943 by MacArthur Lock), widen and 
deepen existing State Channel. 6 
Poe Lock.' 
Dredging through shoals above falls and shoals below falls between 
lower end of Canal and upper entrance Channel into Lake Nicolet 
(formerly Hay Lake). 
Enlarging the Old Channel. 
Lake Nicolet and Neebish Channels work in that section of River 
below Locks. 
Davis Lock Second Canal, and Emergency Dam. 
Lease of Waterpower at Falls, Lease entered into with Michigan Northern 
Power Company provided for construction of remedial and compensating 
works. 
Fourth Lock (Renamed 'Sabin' Lock in 1943). 
Deepen Tailrace of Power Plant. 
Widen upper approach to Canals through Vidal Shoals, extend 
anchorage and maneuver area below locks. 
Remove Round Island, middle ground extension of Northwest Canal 
Pier, and widen Channels Middle Neebish Route. 
Deepen Channels throughout downbound Route. 
Operation and Care of Canal and Locks provided from War Department 
Appropriations for Rivers and Harbors. 
Widen Brush Point Turn and Channel from Brush Point to Point Louise. 
Construct new (MacArthur) Lock on site of former Weitzel Lock, deepen 
approach Channels to 27 feet, and reconstruct approach Piers. 
Name 'MacArthur' Lock and changed name of 'Fourth' Lock to 
'Sabin' Lock. 
Remove Bridge Island and construct new Hydroelectric Power Plant. 
S. Doc. 71, 84th Cong., 1st Sess. 
H. R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986). 
H. Ex. Doc. 160, 43rd Cong., 2d 
Sess., and Annual Report, 1875, 
pt. 1, p. 162. 
Annual Report, 1880, pp. 2030, 
2031, 2049, and 2055. 
H. Doc. 307, 55th Cong., 2d Sess., 
and Annual Report, 1898, p. 2496. 
Rivers and Harbors Committee 
Doc. 52, 74th Cong., 1st Sess. 
H. Doc. 129, 76th Cong., 1st Sess. 
S. Doc. 95, 84th Cong., 2d Sess.' 
Report by Maj. O.M. Poe, Corps of 
Engineers, not published. 
H. Ex. Doc. 72, 49th Cong., 2d Sess. 
H. Ex. Doc. 207, 51st Cong., 2d 
Sess., and Annual Report, 1891, 
p. 2810. 
H. Doc. 138, 56th Cong., 2d Sess., 
and 215, 58th Cong., 3rd Sess. 
H. Doc. 128, 56th Cong., 2d Sess. 
H.Doc. 333, 59th Cong., 2d Sess. 
(Plan 3). 
H. Doc. 65, 62d Cong., 1st Sess. 
District Engineer Report, Oct. 
29, 1920. 
H. Doc. 270, 69th Cong., 1st Sess. 
H. Doc. 253, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 53, 74th Cong., 1st Sess. 
H. Doc. 218, 77th Cong., 1st Sess. 
H. Doc. 679, 78th Cong., 2d Sess., 
and 339, 77th Cong., 1st Sess. 
21-80

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 24, 1946 
Mar. 21, 1956 
Jul. 9, 1956 
Nov. 17, 1986 
Jun. 3, 1896 
Mar. 2, 1907 
Jun. 25, 1910 
Jun. 3, 1896 
Mar. 2, 1907 
Jan. 21, 1927 
Aug. 30, 1935 
Sep. 3, 1954 
Aug. 11, 1888 
Mar. 3, 1905 
Aug. 30, 1935 
Mar. 3, 1873 
Replace Poe Lock at St. Marys Falls Canal with a new structure 800 feet 
long, 100 feet wide and 32 feet deep with necessary construction of 
Nose and Center Piers, and widen and deepen Channel across Point 
Iroquois Shoals and in Lake Nicolet to provide wider anchorage and 
maneuver areas in St. Marys River. 
Deepen to provide a Project Safe Draft of 25.5 feet over full width to 
downbound and 2-way Channels (including anchorage areas) and over 
Westerly 300-foot width of upbound Middle Neebish Channel, when 
levels of Lakes Superior and Huron are at their respective LWD's. 
Repeal Authorization of Bridge as a part of Project, authorize alteration 
with cost to be apportioned by Sec. 6, Truman Hobbs Act, 
Jun. 21, 1940. 
Construct a second large lock 1,294 feet in length, 115 feet in width, 
and 32 feet in depth, adjacent to the existing lock. The replacement 
lock is to be located in the North Canal of the St. Marys Falls Canal 
at Sault Ste. Marie, MI, on the site of the existing Davis and Sabin 
Locks. 
SAUGATUCK HARBOR AND KALAMAZOO RIVER, MI 
(See Section 59 of Text) 
Entrance Channel, Piers and Revetments. 
Deepening entrance to 16 feet. 
Deepening Channel in River to 14 feet. 
SEBEWAING RIVER, MI (See Section 60 of Text) 
Entrance Channel 8 feet deep, 100 feet wide and 15,000 feet 
long in Saginaw Bay. 
SHEBOYGAN HARBOR, WI (See Section 61 of Text) 
North breakwater. 
Preserving south pier as part of project, providing turning basin, and 
elimination of proposed south breakwaters. 
Present project dimensions of channel. 
Widen and deepen outer harbor entrance channel to 450 feet, widen and 
deepen river channel from present project limit to north side of 
Jefferson Avenue. 
SOUTH HAVEN HARBOR, MI (See Section 62 of Text) 
Channel from Inner End of Piers to Highway Bridge. 12 
Present dimensions of Piers and for a Turning Basin. 
Present project dimensions of Channel and Turning Basin. 
STURGEON BAY AND LAKE MICHIGAN SHIIP CANAL, WI 
(See Section 63 of Text) 
Breakwaters. 2 
H. Doc. 335, 80th Cong., 1st Sess. 
S. Doc. 71, 84th Cong., 1st Sess.' 
None. 
H. R. 6 (formerly S. 1567), 99th 
Cong., 2d Sess. (WRDA of 1986). 
H. Doc. 912, 54th Cong., 1st Sess.; 
Annual Report, 1896, Vol. 2, Pt. 5, 
p. 2739. 
Annual Report, 1907, p. 6416. 
H. Doc. 635, 61st Cong., 2d Sess. 
H. Doc. 71, 54th Cong., 1st Sess. 
H. Doc. 62, 59th Cong., 1st Sess. 
H. Doc. 475, 68th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 47, 74th Cong., 1st Sess. 
H. Doc. 554, 82d Cong., 2d Sess.' 
No Prior Survey or Estimate. 
H. Doc. 119, 58th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 9, 73rd Cong., 1st Sess.' and 
Unpublished review Report of Chief 
of Engineers, dated Dec. 21, 1934. 
H. Ex. Doc. 34, 42d Cong., 2d Sess.; 
Annual Report, 1872, p. 171. 
21-81

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Jul. 13, 1892 
Jun. 13, 1902 
Aug. 30, 1935 
Nov. 7, 1945 
Jul. 14, 1960 
Aug. 5, 1886 
Aug. 5, 1886 
Aug. 30, 1935 
Nov. 7, 1945 
Jul. 14, 1960 
Mar. 3, 1871 
Mar. 2, 1907 
Aug. 30, 1935 * 
Jul. 3, 1958 
Mar. 2, 1867 
Mar. 3, 1873 
Jul. 5, 1884 
Jul. 13, 1892 
Mar. 2, 1907 
Jul. 3, 1958 
Aug. 17, 1991 
Oct. 8, 1992 
Aug. 18, 1941 
Acquision of the canal. 
Canal revetments and consolidation of canal and harbor works. 
Present project dimensions of channels and elimination of turning 
basin immediately west of revetted canal. 
Turning basin between city and Bushman wharves. 
TWO HARBORS, MN (See Section 64 of Text) 
Breakwater and dredging. 
Construction of two breakwater piers. 
Shore connection to east breakwater and dredging maneuvering area. 
Construct new east breakwater and enlargement of maneuvering basin. 
Deepen harbor project depths from 26 and 28 feet to 28 and 30 feet, 
respectively. 
TWO RIVERS HARBOR, WI (See Section 65 of Text) 
South pier, 750 feet of north pier, and about 44 feet of north 
revetment. '2 
Remainder of north pier and stilling basin. 
Deepening entrance channel and inner basin to 18 feet. 
Extend existing project in West Twin River to 18 feet deep and in 
East Twin River to 10 feet deep to 22d Street Bridge. 
WHITE LAKE HARBOR, MI (See Section 66 of Text) 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
New Channel, with Piers and Revetments. 
Present project depth of Channel. 
SAGINAW RIVER, MI, FLOOD CONTROL 
(See Section 74 of Text) 
Flood control improvements to Saginaw River and its tributaries 
including Tittabawassee, Shiawassee, Flint, and Cass Rivers. 
One-time O&M repairs at Flint Unit to restore project to original 
dimensions. 
Provides funding for continuing O&M repairs at Flint Unit. 
SEBEWAING, SEBEWAING RIVER, MI (See Section 75 of Text) 
Enlarging present Channel of Sebewaing River, altering Railroad and 
Highway Bridges, removal of Dike. 
H. Doc. 106, 49th Cong., 2d Sess. 
H. Doc. 117, 56th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 9, 74th Cong., 1st Sess. 
H. Doc. 421, 78th Cong., 2d Sess. 
H. Ex. Doc. 94, 48th Cong., 2d Sess. 
Annual Report, 1887, p. 1952. 
Rivers and Harbors Committee 
Doc. 17, 72d Cong., 1st Sess. 
H. Doc. 805, 78th Cong., 2d Sess. 
H. Doc. 146, 86th Cong., 1st Sess.' 
Annual Report, 1871, p. 123 (as 
modified by Chief of Engineers, 
Feb. 17, 1897). 
H. Do. 730, 59th Cong., 1st Sess., 
Modification of Plan A. 
Rivers and Harbors Committee 
Doc. 25, 73rd Cong., 2d Sess. 
H. Doc. 362, 84th Cong., 2d Sess.' 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
Unpublished Survey Report of 1868. 
No Prior Survey or Estimate. 27 
H. Doc. 346, 84th Cong., 2d Sess. 
Energy and Water Development 
Appropriation Act of 1992, 
(P.L. 102-104). 
Energy and Water Resources 
Appropriation Act of 1993, 
H.R. 5373, (P.L. 102-377). 
H. Doc. 286, 76th Cong., 1st Sess.' 
21-82

DETROIT, MI DISTRICT 
TABLE 21-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
'Contains latest published map. 
2Including Emergency Relief Administration Work authorized 
May 28, 1935. 
'Included in Public Works Administration Program September 
6, 1933. 
4This modification deauthorized August 5, 1977, under Section 
12, Public Law 93-251. 
SAdministrative Act, Section 4. 
6Public Law 568, 82d Congress. 
7Public Law 388, 87th Congress. 
s'This portion inactive. 
9Permanent Appropriations Repeal Act. 
"'Transfer completed June 1962. 
"Amended 1868, 1879, 1892. 
12Completed under previous project. 
3"Included in Public Works Administration Program January 
3, 1934. 
14 
Inactive portion; removal of 200 linear feet of north pier, 
widening inner 200 feet of channel through outer basin, and 
closing gap in north shore connection of breakwater. 
IsLatest published map is in Annual Report, 1914, p. 2974. 
6Latest published map in Annual Report, 1914, p. 2914. 
'Superseded by Act of October 23, 1962. 
"Uncompleted portion was deauthorized in 1977 (dredging 
Milwaukee River from Buffalo Street Bridge to North 
Humboldt Avenue Bridge). 
'9Modified by Act of June 10, 1872. 
2"Riprapping of protecting dikes portion of project is inactive. 
2'War Department Appropriations Act. 
22Uncompleted portion deauthorized December 31, 1989, under 
Section 1001, P.L. 99-662. 
23Contains latest published maps. See also map with Rivers and 
Harbors Committee Doc. 19, 72d Cong., 1st Sess. 
24Except for dredging 25-foot channel to 1,150 feet upstream of 
mouth of old channel, work authorized in this Act is considered 
inactive. 
2yThis modification deauthorized August 5, 1977, under Section 
12, Public Law 93-251. 
26Completed under previous projects. Public Law 130, 75th 
Cong., 1st Sess. 
"72Latest published map is in H. Doc. 2053, 64th Cong., 2d Sess. 
2Work recommended in H. Doc. 588, 64th Cong., 1st Sess. 
9Deauthorized in 1977. 
This modification deauthorized December 31, 1989, under 
Section 1001, P.L. 99-662. 
21-83

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-C OTHER AUTHORIZED NAVIGATION PROJECTS 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation & 
Project Status Report for Construction Maintenance 
Algoma Harbor, WI Completed 1981 205,010' 1,017,728 
Bayfield Harbor, WI Completed 1979 183,855 112,621 
Belle River, MI Completed 1980 24,301 92,106 
Beaver Bay, MN Active 1982 293,000 2,818 
Big Suamico Harbor, WI Completed 1989 20,243 800,070 
Black River (Alcona Co), MI Inactive 1907 0 0 
Cedar River Harbor, MI Active 1982 215,000 0 
Channels in Straits 
of Mackinac, MI Completed 1991 2,832,629 224,832 
Cheboygan Harbor, MI Completed 1988 504,236 924,375 
Chippewa Harbor, Isle Royale, MI Completed 1959 125,629 13,528 
Cross Village, MI Active 1983 364,000 0 
Detour Harbor, MI Completed 1989 2,559,346 140,024 
Eagle Harbor, MI Completed 1990 205,1642 92,548 
Grays Reef Passage, MI Completed 1970 190,521 812,424 
Greilickville Harbor, MI Completed 1976 366,579 159,639 
(Formerly Traverse City Harbor, MI) 
Harrisville Harbor, MI Completed 1988 2,639,392 1,071,545 
Knife River Harbor, MN Active 1986 412,945 291,168 
Lac La Belle Harbor, MI Completed 1989 269,270 559,026 
Les Cheneaux Island Channels, MI Completed 1980 399,478 324,036 
Little Bay De Noc, Gladstone Harbor, MI Completed 1966 332,832 105,000 
Lutsen Harbor, MN Active 1982 357,000 0 
Mackinac Island Harbor, MI Completed 1989 334,089 1,812,044 
Mackinaw City Harbor, MI Completed 1986 136,2863 87,640 
Northport Harbor, WI Inactive ---- 0 0 
Petoskey Harbor, MI Completed 1986 123,839 561,058 
Point Lookout Harbor, MI Completed 1991 2,642,584 3,469,5854 
Pine River, MI Completed 1980 13,649 58,868 
Portage Lake Harbor, MI Completed 1990 256,129 2,001,065 
St. James, Beaver Island, MI Completed 1957 49,171s 85,814 
St. Joseph River, MI Completed 1975 54,555 19,185 
Saxon Harbor, WI Completed 1991 1,094,3776 726,147 
Tawas Bay Harbor, MI Completed 1986 1,955,745 31,520 
Washington Island, WI Completed 1950 62,838 77,792 
Whitefish Point Harbor, MI Completed 1991 771,639 401,596 
'Includes $92,774 for previous projects. 
2Excludes $27,800 for previous projects. 
3Excludes $136,286 Contributed Funds. 
4Includes $9,257 Contributed Funds. 
SExcludes $7,500 Contributed Funds. 
6Excludes $50,193 Contributed Funds. 
21-84

DETROIT, MI DISTRICT 
TABLE 21-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Cost to September 30, 1992 
For Last 
Full Report 
See Annual Operation & 
Project Status Report for Construction Maintenance 
Kalamazoo River (Battle Creek) MI' Deferred 1975 4,471,235 -- 
Kawkawlin River, MI Completed 1991 469,663' --- 
Mount Clemens, Clinton River, MI Completed 1953 1,136,008' --- 
Paw Paw Lake, MI Completed 1989 3,589,000 --- 
Upper River Rouge, MI' Inactive 1968 7,935 ---- 
River Rouge, MI Completed 1981 31,960,332 ---- 
'Includes $108,335 Contributed Funds. 'Includes $202,996 Contributed Funds. 
'Uncompleted portion deauthorized Dec. 31, 1989, in accordance with 5Planning indefinitely suspended due to lack of 
Section 1001 of the W.R.D.A. of 1986 (PL 99-662). local cooperation. 
'Includes $113,963 Contributed Funds. 
TABLE 21-F MULTIPLE PURPOSE PROJECTS, INCLUDING POWER 
ST. MARYS RIVER, MI: EXISTING PROJECT 
(SEE SECTION 58 OF TEXT) 
Lock Davis Sabin MacArthur New Poe 
Miles Above Mouth 47 47 47 47 
Clear Width of Chamber Feet 80 80 80 110 
Length Between Gate Quoins Feet 1,350 1,350 800 1,200 
Lifts Feet 21.7 21.7 21.7 21.7 
Depth Over Upper Breast Walls' Feet 24.3 24.3 31 32 
Depth Over Lower Breast Walls' Feet 23.1 23.1 31 32 
Foundation Rock Rock Rock Rock 
Type of Construction Concrete Concrete Concrete Concrete 
Estimated Coat $6,200,000' $3,275,000' $12,909,440 $39,000,000 
Actual Cost $2,200,0005 $1,750,000' $12,718,806 '" $34,813,066 
Completed (Open to Commerce) Oct. 21, 1914 Sep. 18, 1919 Jul. 11, 1943 Jun. 26, 1969 
Emergency Dam for South Canal North Canal 
Miles Above Mouth 47 47 
Estimated Cost -' $300,000 
Type Stel SolgsRecessed Stel SgoplsRecessed 
Coat Completed -' $169,224' 
Year Completed 1943 1922 (Modified 1963) 
'At low water datum 600.6 above and 578.4 below. 
'Includes cot of North Canal. 
'Includes cost of canal excavations to provide necessary approaches 
to lock, canal walls, piers, and emergency dam, $662,919. 
'Excludes cost of deepening and enlarging South Canal, 
$1,653,378. 
'Excludes cost of North Canal, $2,572,611. 
Note: Limiting draft to locks is determined by depth over breast walls. 
'Excludes cost of canal excavation to provide necessary approaches to lock, 
canal walls, piers, and emergency dam, $662,919. 
7Excluding cost of lower guard gates which were never installed. 
'Including engineering office, and inspection. 
'Not separate from cost of locks. 
21-85

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Berrien County, MI 1963 Nov 1986 0 0 
(St. Joseph Shore) beach erosion 
control (1958 Flood Control Act) 
Black River Harbor, Alcona County, 1971 Dec 1989 0 0 
MI (Authorized Dec. 17, 1979, 
under Section 201 of the 1965 
Flood Control Act) 
Black River Harbor, MI 1976 Nov 1977 0 0 
(Aug. 30, 1936 R&H Act) 
Detroit River, Trenton Chnl., MI 1976 Aug 1977 0 0 
(May 17, 1950 R&H Act) 
Detroit River, Trenton Chnl., MI 1976 Dec 1989 159,300,000 0 
(Uncompleted portion) 
(Aug. 13, 1968 R&H Act) 
Duluth-Superior Inner Harbor, 1990 Dec 1989 14,562,100 0 
MN and WI (Jul. 14, 1960 R&H Act) 
Forestville Harbor, MI (1968 R&H Act) 1969 Nov 1986 0 0 
Grand Haven Harbor, MI 1976 Nov 1977 0 0 
(Mar. 2, 1945 R&H Act) 
Grand River at Grandville, MI 1966 Nov 1977 0 0 
(Oct. 27, 1965 Flood Control Act) 
Great Lakes Connecting Channels, MI' 1990 Dec 1989 93,993,349 0 
(Uncompleted portion) 
(R&H Acts of 1946 and 1956) 
Harbors of Washington Island, WI 1950 Dec 1989 62,838 0 
(R&H Act of 1937) 
Holland Harbor Entrance Channel, MI 1962 Dec 1989 0 0 
(Uncompleted portion) 
(Sep. 3, 1954 R&H Act) 
Kalamazoo River, Battle Creek, MI 1975 Dec 1989 6,656,668 108,332 
(Uncompleted portion) 
(1954 Flood Control Act) 
Kalamazoo River, Kalamazoo, MI 1975 Dec 1989 416,822 0 
(Jul. 3, 1958 Flood Control Act) 
Kenosha Harbor, WI 1990 Dec 1989 552,000 43,000 
(Uncompleted portion) 
(Oct. 23, 1962 R&H Act) 
Kewaunee River, WI 1976 Aug 1977 0 0 
(1960 R&H Act) 
Lansing (Grand River), MI 1971 Jun 1981 7,000 0 
(Jul. 3, 1958 Flood Control Act) 
21-86

TABLE 21-G DE 
DETROIT, MI DISTRICT 
AUTHORIZED PROJECTS 
For Last 
Full Report 
See Annual Dal 
Report For Deauth 
1990 Dec 1 
990 
1990 
Project 
Lower Fox River, WI 
(Uncompleted portion) 
(Mar. 3, 1925 R&H Act) 
Manitowoc Harbor, WI 
(Oct. 23, 1962 R&H Act) 
Milwaukee Outer Harbor, WI 
(Uncompleted portion) 
(R&H Act of 1935) 
Northport Harbor, WI 
(Authorized in 1972 under Section 201 
of the 1965 Flood Control Act) 
Ontonagon Harbor, MI 
(R&H Act of 1962) 
Pentwater Harbor, MI 
(Jul. 13, 1892 R&H Act) 
Racine Harbor, WI 
(Mar. 2, 1907; Aug. 26, 1937; and 
Mar. 2, 1945 R&H Acts, and 
Section 107 of the 1960 R&H Act) 
Red Run Drain, Lower Clinton River, MI 
(1970 Flood Control Act) 
Rogers City Harbor, MI 
(Jun. 25, 1910 R&H Act) 
Rouge River, MI 
(Oct 23, 1962 R&H Act) 
Rouge River, MI 
(Jul. 3, 1958 R&H Act) 
Rouge River, MI 
(Aug. 30, 1935 R&H Act) 
St. Clair River Compensating Works, MI 
(Jul. 3, 1930 R&H Act) 
South Milwaukee Harbor, WI 
(1836 Flood Control Act) 
St. Marys River (MacArthur Lock Guard 
Gates), MI (Mar. 7, 1942 R&H Act) 
Two Rivers Harbor, WI 
(Uncompleted portion) 
(Aug. 30, 1935 R&H Act) 
te 
orized 
989 
Dec 1989 
Dec 1989 
Dec 1989 
Dec 1989 
Nov 1977 
May 1986 
Nov 1986 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Aug 1977 
Oct 1978 
Dec 1989 
21-87 
CEoxnFptuernnibddusetded 
478,000 
'Includes Detroit and St. Clair Rivers. 
Federal 
Funds 
Expended 
3,753,334 
0 
6,937,804 
132,000 
27,482 
0 
9,441,554 
3,823,000 
5,892 
22,000 
12,000 
0
0
0
0 
147,463 
Contributed 
Funds 
Expended 
0
0 
478,000 
0
0
0
0
0
0
0
0
0
0
0
0
0 
1990 
1976 
1963 
1983 
1926 
1976 
1976 
1976 
1976 
1906 
1977 
1990

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-H FEATURES OF EXISTING PROJECT 
Length Miles Upbound Project 
of from or Down- Project Project Datum Planes Year 
Channel River bound Width Depth IGLD 1985 Com- 
Name of Channel (Feet) Mouth Vessels (Feet) (Feet) (Feet) plete 
DETROIT RIVER, MI (SEE SECTION 14 OF TEXT) 
Channel North of Belle Isle' 
Channel at Head of Detroit River 
Misc. Shoals and Obstructions 
Belle Isle to Fighting Island Channel 
Fighting Island Channel 
Ballards Reef Channel North of 
Junction with Livingstone Channel 
Livingstone Channel Upper 
Livingstone Channel Lower: 
CS 260+00 to 368+87 
CS 368 +87 to 492+00 
East Outer Channel 
Misc. Shoals and Obstructions, 
Detroit River to Pelee Passage 
Pelee Passage Shoal 
Amherstberg Channel: 
Upper Section, Ballards Reef Channel 
Middle Section 
Lower Section, Hackett Range 
West Outer Channel 
Trenton Channel: 
Wyandotte Reach 
Trenton Channel (Upper) 
Trenton Reach (Lower) 
Grosse Ile Shoal 
2 
38,800 
44,500 
30 
32 
25 
Both 200 
Both 800 
Both - 
24,800 17 Both 800 
12,200 12 Both 600 
26,000 10 Down 450 
10,887 
12,313 
42,000 
5 Down 
Both 
Both 
Both 
450-800 
800-1,200 
1,200 
--- 
Both --- 
6,500 
12,000 
24,000 
21,000 
31,500 
5,100 
600 
600 
10 
17 
14 
Up 
Up 
Up 
Down 
Local 
Local 
Local 
Local 
600 
600 
600 
800 
300 
300 
250-300 
ST. CLAIR RIVER, MI (SEE SECTION 56 OF TEXT) 
Channel at Foot of Lake Huron 
Channel North of Blue Water Bridge 
Port Huron to Stag Island: 
Widening at Upper and Lower 
Ends of Stag Island 
St. Clair to Russell Island 
Russell Island to Southeast Bend 
Southeast Bend: 
CS 324+00 to 250+00 
Cutoff Channel 
North Channel Outlet 
26,500 44 Both 800 
4,100 39 Both 800 
38,000 
37,600 
77,000 
20,600 
7,400 
30,300 
8,000 
38 
31 
24 
11 
5
--
.-- 
Both 
Both 
Both 
Both 
Both 
Both 
Small 
Craft 
1,000-1,400 
900-1,000 
1,000 
700-1,000 
700 
700 
100 
'This is a side channel. 
2Extends from deep water near Windmill Point to a point 
opposite Fairview Slip, about 3,000 feet. 
'Project depth 29.5 feet over Rock Shoals and 28.5 feet 
over other than Rock Shoals. 
'Project depth 21 feet in easterly 300-foot width of 
channel and 27.5 feet in westerly 300-foot width. 
3Project depth 21 feet in easterly 300-foot width of 
channel and 28.5 feet in westerly 300-foot width. 
'Project complete except for work authorized by 
Rivers and Harbors Act of 1950. 
21-88 
21.0 
28.5 
28.5 
28.5 
28.5 
27.7 
29.0 
29.0 
28.5 
28.5-29.53 
571.9 
572.1-571.5 
571.5-570.9 
570.4 
570.4 
570.4-569.2 
569.2 
569.2 
569.2 
569.2 
569.2 
570.4-570.1 
570.1-569.5 
569.5-569.2 
569.2 
570.3-570.2 
570.2-569.4 
570.4 
29.5 
1964 
1964 
1964 
1962 
1964 
1964 
1961 
1961 
1964 
1964 
1960 
1960 
1960 
1929 
19646 
1964 
1941 
1904 
27.5 
21-27.5' 
21-28.55 
22.0 
27.0 
28.0 
28.0 
20.0 
30.0 
30.0 
27.4 
27.3 
27.3 
27.2 
27.1 
27.1 
10.0 
577.5-577.1 
577.1-576.5 
577.1-575.3 
575.3-574.3 
574.3-572.6 
572.6-572.3 
572.3-572.2 
572.2 
572.2 
1961 
1962 
1961 
1962 
1962 
1962 
1962 
1962

DETROIT, MI DISTRICT 
TABLE 21-I FOX RIVER, WI: LOCKS AND DAMS 
(SEE SECTION 16 OF TEXT) 
Depth at 
Normal Pool 
Miles Avail- Lower 
from Dis- Clear able Breast Miter Ye 
Green Nearest tance Width Length Lift Wall' Sill Character of Kind of Type of Co 
Name of Lock and Dam Bay Town (miles) (feet) (feet) (feet) (feet) (feet) Foundation Dam Construction ple 
DePere lock' 7.1 DePere --- 36.0 146.0 8.9 10.3 12.0 Rock -- Concrete 193 
DePere dam' 7.2 DePere --- --- --- --- --- --- Rock Fixed3' Concrete 192 
Little Kaukauna lock' 13.0 DePere 6 36.0 146.0 7.2 8.0 9.5 Clay -- Concrete 193 
Little Kaukauna dam2 13.1 DePere 6 --- --- -- --- --- Clay and gravel Fixed3' Piers and concrete 192 
Rapide Croche lock2 19.2 Wrightstown 2 36.0 146.0 8.3 8.8 9.3 Rock -- Concrete 193 
Rapide Croche dam2 19.3 Wrightstown 2 .--- --- -- --- - Rock Fixed3' Concrete 193 
Kaukauna fifth lock2 22.8 Kaukauna --- 35.6 144.0 9.1 6.7 9.3 Rock -- Composite 189 
Kaukauna fourth lock2 23.1 Kaukauna --- 36.6 144.1 10.2 6.9 6.0 Rock -- Stone masonry 187 
Kaukauna third lock2 23.3 Kaukauna --- 30.6 144.0 10.2 6.9 6.3 Rock -- Stone masonry 187 
Kaukauna second lock 2 23.4 Kaukauna --- 35.0 144.0 9.6 6.0 6.0 Rock -- Stone masonry 190 
Kaukauna first lock2 23.6 Kaukauna --- 35.1 144.4 11.0 6.9 6.0 Rock --- Stone masonry 188 
Kaukauna dam2 24.0 Kaukauna --- --- --- --- --- - Rock Fixed' Concrete 193 
Kaukauna guard lock 24.0 Kaukauna --- 40.0 --- --- 9.4 --- Rock -- Stone masonry 189 
Little Chute combined lock: 
Lower 24.4 Little Chute 1 35.4 146.5 10.9 6.0 8.6 Rock --- Stone masonry 187 
Upper 25.4 Little Chute 1 36.3 144.1 10.6 7.6 6.0 Hardpan -- Stone masonry 187 
Little Chute second lock2 26.4 Little Chute --- 35.0 144.2 13.8 8.0 6.1 Rock -- Stone masonry 188 
Luttle Chute first (guard) lock' 26.5 Little Chute --- 35.4 --- --- 6.6 --- Rock --- Stone masonry 190 
Little Chute dam 2 26.6 Little Chute --- --- --- --- --- --- Rock Fixed' Concrete 193 
Cedars lock' 27.3 Little Chute 1 35.0 144.0 9.8 6.8 7.3 Rock --- Stone masonry 188 
Cedars dam' 27.4 Little Chute 1 --- --- --- --- --- Rock Fixed 3' Concrete 193 
Appleton fourth lock2 30.7 Appelton 1 35.0 144.0 7.6 8.1 7.9 Rock --- Stone masonry 190 
Appleton lower dam2 30.9 Appleton 1 --- --- --- --- --- Rock Fixed3' Concrete 193 
Appleton third lock' 31.3 Appleton --- 35.0 144.0 8.7 6.0 8.6 Rock --- Stone masonry 190 
Appleton second lock2 31.6 Appleton --- 35.1 144.6 9.6 6.9 6.0 Clay -- Stone masonry 190 
Appelton first lock2 31.9 Appleton --- 35.0 144.7 10.0 6.6 6.0 Rock --- Stone masonry 188 
Appleton upper dam 32.2 Appleton-.. --- ---- --- - Rock Fixed3 Concrete 194 
Menasha lock2 37.0 Menasha --- 35.4 144.0 8.5 7.2 8.0 Clay -- Composite 189 
Menasha dam2 37.8 Menasha --- --- --- --- --- --- Hardpan Fixed3 Concrete 193 
ar 
m- Actual 
te Cost 
6 $229,308 
9 209,536 
8 362,427 
6 179,398 
4 228,738 
0 118,975 
8 13,310' 
9 37,536 
9 39,948 
3 24,313 
3 38,704 
1 123,763 
1 12,630 
9 102,304 
9 --- 
1 48,555 
4 7,817' 
2 82,554 
8 34,972 
3 84,973 
7 40,893 
4 73,903 
0 32,238 
1 22,940 
4 36,004 
0 151,558 
9 19,326' 
84,686 
'Depth shown is on breast wall, which is controlling depth for 
upper pool. 
2Original structure built prior to assumption of control by 
United States on Sep. 18, 1872. 
'Provided with sluices. 
*Flash boards used. 
'Partially rebuilt. 
21-89

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 21-J RECONNAISSANCE & CONDITION SURVEYS 
21-90 
Name of Project 
BAYFIELD HARBOR, WI 
BIG SUAMICO HARBOR, WI 
CHEBOYGAN HARBOR, MI 
EAGLE HARBOR, MI 
GRAYS REEF PASSAGE, MI 
GREILICKVILLE HARBOR, MI 
HARRISVILLE HARBOR, MI 
LAC LA BELLE HARBOR, MI 
MACKINAW CITY HARBOR, MI 
POINT LOOKOUT HARBOR, MI 
PORT AUSTIN HARBOR, MI 
PORTAGE LAKE HARBOR, MI 
SAXON HARBOR, WI 
ST. JAMES HARBOR, MI 
TAWAS BAY HARBOR, MI 
WHITE LAKE HARBOR, MI 
Date Survey Conducted 
OCTOBER 1991 
MAY 1992 
MAY 1992 
OCTOBER 1991 
JULY 1992 
APRIL 1992 
JUNE 1992 
APRIL 1992 
AUGUST 1992 
JUNE 1992 
JUNE 1992 
JUNE 1992 
JUNE 1992 
JULY 1992 
JULY 1992 
JULY 1992

CHICAGO, ILLINOIS, DISTRICT* 
The district comprises Cook, Mc Henry, Lake, Kane, Du Page, and Will Counties in Illinois, and Lake and Porter 
Counties in Indiana, including a portion of La Porte County along Lake Michigan in Indiana. 
IMPROVEMENTS 
Navigation 
1. Burns Waterway Harbor, IN 
2. Burns Waterway SBH, IN 
3. Calumet Harbor and River, IL and IN 
4. Chicago Harbor, IL 
5. Chicago River, IL 
6. Indiana Harbor, IN 
7. Michigan City Harbor, IN 
8. Waukegan Harbor, IL 
9. Lake Michigan Diversion 
10. Reconnaissance and Condition Surveys 
11. National Emergency Preparedness 
Alterations of Bridges 
12. Other Authorized Bridge Alteration 
Beach Erosion Control 
13. Casino Beach, IL 
14. Illinois Beach State Park, IL 
15. Indiana Dunes National Lakeshore, Bank 
Protection, Beverly Shores, IN 
16. Indiana Shoreline Erosion, IN 
17. Other Authorized Beach Erosion Projects 
18. Beach Erosion Control Under 
Special Authorization 
Page 
22-2 
22-2 
22-2 
22-3 
22-4 
22-4 
22-5 
22-5 
22-6 
22-6 
22-6 
22-6 
22-6 
22-6 
22-7 
22-7 
22-7 
22-7 
Flood Control 
19. Chicago River, IL 
(North Branch) 
20. Lake George, Hobart, IN 
21. Little Calumet River, IN 
22. Little Calumet River Basin, 
Cady Marsh Ditch, IN 
23. McCook and Thornton Reservoirs, IL 
24. North Branch, Chicago River, IL 
25. O'Hare Reservoir, IL 
26. Other Authorized Flood Control Projects 
27. Flood Control Work Under Special 
Authorization 
General Investigations 
28. Surveys 
29. Collection and Study of Basic Data 
Title 
Cost and Financial Statement 
Authorizing Legislation 
Existing Navigation Projects 
Other Authorized Bridge Alteration 
Other Authorized Beach Erosion Projects 
Other Authorized Flood Control Projects 
Deauthorized Projects 
TABLES
Table 
Numbers 
22-A 
22-B 
22-C 
22-D 
22-E 
22-F 
22-G 
Pages 
22-12 Thru 14 
22-15 Thru 18 
22-19 
22-20 
22-20 
22-20 
22-21 
22-1 
Page 
22-7 
22-8 
22-8 
22-8 
22-9 
22-10 
22-10 
22-11 
22-11 
22-11 
22-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. BURNS WATERWAY HARBOR, IN 
Location. Northwestern Indiana on the southern 
shore of Lake Michigan in Porter County, 28 
miles southeast of Chicago Harbor. (See NOAA 
Nautical Chart Numbers 14905 and 14926.) 
Existing Project. Provides for (a) a 
rubblemound north breakwater 4,630 feet long 
and a rubblemound breakwater west arm 1,200 
feet long, for a total breakwater length of 5,830 
feet; (b) an approach channel 30 feet deep and 
400 feet wide; (c) an outer harbor 28 feet deep; 
(d) an east harbor arm 27 feet deep and 620 feet 
wide; and (e) a west harbor arm 27 feet deep and 
620 feet wide. The project was authorized by the 
River and Harbor Act of October 27, 1965 (Public 
Law 89-298; House Document Number 160, 88th 
Congress, 1st Session). The authorizing act also 
provided the Secretary of the Army with the 
authority to reimburse the State of Indiana for 
expenditure of funds used to construct such 
portions of the project as approved by the Chief 
of Engineers and constructed under supervision 
of the Chief of Engineers (See table 22-C). 
Local Cooperation. Fully complied with. 
Terminal Facilities. Eleven berths are available 
at the facilities owned and administered by 
the Indiana Port Commission. One berth, committed 
to grain, is located on the outer harbor. Four 
berths on the East Harbor Arm are dedicated to 
handling dry and liquid bulk commodities. The 
East Harbor Arm also includes a small-boat 
harbor designed to accommodate working tugs for 
vessel assistance and barge movement. On the 
West Arm there are six berths. Although one 
berth is available for dry bulk cargoes, these 
berths are primarily used for the shipment and 
receipt of general cargo. Additionally, the Indiana 
Port Commission, through a lease, administers 
the west side of the West Harbor Arm for 
barge fleeting. The remaining available harbor 
berthing on the east side of the East Harbor Arm 
is privately owned. 
Operations and Results During Period. 
Maintenance: Hydrographic surveys and studies 
were performed by hired labor at a cost of 
$38,147 and by contract at a cost of $43,620. 
Project management and real estate costs were 
performed by hired labor at a cost of $49,000 and 
$2,580, respectively. Major Rehabilitation Evaluation 
Reports were prepared by other COE at a 
cost of $98,718 and by hired labor at a cost of 
$40,519. 
Condition at End of Fiscal Year. The 
existing project is complete. Total costs to 
September 30, 1992 were $19,471,380 of which 
$13,599,900 was for new work ($13,584,000 federal 
and $15,900 non-federal) and $5,871,480 for maintenance. 
2. BURNS WATERWAY SBH, IN 
Location. Northwestern Indiana on the southeast 
shore of Lake Michigan in Porter County, at the 
mouth of the Burns Waterway, approximately 35 
miles southeast of Chicago. (See NOAA Nautical 
Chart Numbers 14905 and 14926.) 
Previous Projects. None 
Existing Project. Provides for (a) a rubblemound 
west breakwater 1,003 feet long; (b) a rubblemound 
north breakwater 678 feet long; and (c) channel 
improvements of 5,200 linear feet with 145,000 cubic 
yards of dredged material used for beach nourishment 
(See table 22-C). 
Local Cooperation. Fully complied with. 
Terminal Facilities. There are several marinas 
located along Burns Waterway and Burns Ditch. 
The commodities handled at this harbor are fresh 
fish caught as a result of charter boat fishing. 
Operations and Results During Period. Maintenance: 
Beach monitoring analysis and surveys 
were performed by hired labor at a cost of $89,558 
and by contract at a cost of $16,897. Project management 
and real estate costs were $3,335 and 
$2,824, respectively. 
Condition at End of Fiscal Year. Total costs of 
the existing project to September 30, 1992 were 
$4,482,787 of which $3,770,558 was for new work 
($2,000,000 federal and $1,770,558 non-federal), 
and $712,229 for maintenance. 
3. CALUMET HARBOR AND RIVER, 
IL AND IN 
Location. Northeastern Illinois, on the southwest 
shore of Lake Michigan in Cook County, 15 
miles south of Chicago Harbor, within the corporate 
limits of the City of Chicago, except for breakwaters, 
and approach channel and an anchorage area 
which are in Illinois and Indiana. (See NOAA 
Nautical Chart Numbers 14926 and 14929.) 
22-2

CHICAGO, IL, DISTRICT 
Previous Projects. For details see page 1400 of 
Annual Report for 1962. 
Existing Project. Provides for (a) a stone-filled 
timber crib breakwater 6,714 feet long; (b) a stonefilled 
double-row steel sheet pile detached breakwater 
5,007 feet long; (c) a north pier 3,460 feet long; 
(d) a south pier 2,961 feet long; (e) an approach 
channel 29 feet deep and 3,200 feet wide; (f) an 
outer harbor anchorage area 28 feet deep and 3,000 
feet wide; (g) an entrance channel 27 feet deep and 
230 to 290 feet wide; (h) a channel in the Calumet 
River 27 feet deep and at least 200 feet wide to the 
north side of 130th Street; (i) three turning basins 
designated as numbers, 1, 3, and 5; and (j ) a 
channel extending into Lake Calumet at a width of 
about 1,000 feet. The project was authorized by the 
River and Harbor Act of March 3, 1899, June 13, 
1902, August 30, 1935, July 14, 1960, October 23, 
1962, and October 27, 1965 (See table 22-C). 
Local Cooperation. Fully complied with. 
Terminal Facilities. Thirty six docks, wharves, 
and terminals are available. The Chicago Regional 
Port District owns four wharves, two grain elevators, 
one dock, and one terminal. The United States 
Government owns one stone dock. The most important 
cargoes handled are iron ore and concentrates, 
coal, and lignite. 
Operations and Results During Period. Maintenance: 
Sediment surveys and studies were performed 
at a cost of $100,120. Water quality studies 
were continued at a cost of $77,221. Maintenance of 
the confined disposal facility and Reach C breakwater 
was performed by hired labor at a cost of $36,875 
and $7,979, respectively. The ERGO project was 
initiated at a cost of $10,095. FY 1988 dredging 
contract was completed at a cost of $43,464. Hired 
labor cost for claims associated with this contract 
was $15,771. Project management and real estate 
costs were $249,605 and $18,533, respectively. 
Condition at End of Fiscal Year. The existing 
project is 100 percent complete pursuant to Section 
100 (b), Public Law 99-662, approved January 1990. 
Total costs of the existing project to September 30, 
1992, were $56,934,532 of which $22,578,567 was 
for new work ($19,541,964 regular funds and 
$3,036,603 public works funds), $28,091,297 regular 
funds for maintenance, $836,667 non-federal 
funds for maintenance, and $5,428,001 regular funds 
for rehabilitation. 
4. CHICAGO HARBOR, IL 
Location. Northeastern Illinois on the southwest 
shore of Lake Michigan in Cook County, within 
the corporate limits of the City of Chicago. (See 
NOAA Nautical Chart Numbers 14926, 14927, and 
14928.) 
Previous Projects. See page 1396 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a stone-filled 
timber crib shore and extension breakwater 2,250 
feet long; (b) a stonefilled timber crib exterior 
breakwater 5,421 feet long; (c) a rubblemound and 
stone-filled concrete caisson southerly extension to 
the exterior breakwater 4,944 feet long, exclusive of 
a 582foot entrance gap enclosing an outer basin of 
about 970 acres; (d) a stone-filled timber crib north 
pier 960 feet long; (e) a stone-filled timber crib 
north inner breakwater 4,034 feet long with a 304- 
foot shore return and a 754-foot gap; (f) a stonefilled 
timber crib south inner breakwater 2,544 feet 
long, enclosing an inner basin of approximately 224 
acres; (g) a lake approach channel 29 feet deep and 
800 feet wide; (h) a channel and maneuver area 
inside the exterior breakwater and southerly extension 
breakwater 28 feet deep with a maximum width 
of 1,300 feet; and (i) an entrance channel 21 feet 
deep. The project was authorized by the River and 
Harbor Acts of July 11, 1870, June 14, 1880, March 
3, 1899, July 25, 1912, March 2, 1919 and October 
23, 1962 (See table 22-C). 
The Chicago Lock was constructed in 1938 by the 
Metropolitan Water Reclamation District of Greater 
Chicago. The deep-draft lock is 600 feet long, 80 
feet wide, and 23 feet deep and is of steel cellular 
design. Operation and maintenance responsibilities 
in the interest of navigation were transferred 
to the Federal Government pursuant to Public Law 
90-63 approved July 30, 1983, Section 107 of the 
Public 97-88, and Memorandum of Agreement between 
the Department of Army and the Metropolitan 
Water Reclamation District of Greater Chicago. 
Local Cooperation. Fully complied with. 
Terminal Facilities. There are three docks, two 
for passenger excursion boats and one for cargo. 
The most important cargoes handled are sugar and 
non-metallic minerals. 
Operations and Results During Period. Maintenance: 
The lock operations contract was continued 
with International Research and Development, 
Inc. at a cost of $577,038. Other costs associated 
with the lock operation amounted to $229,372. Surveys 
and studies were performed by hired labor at a 
cost of $117,809, by other COE at a cost of $84,769, 
and by contract at a cost of $28,016. E&D and 
preparation of plans and specs for the southerly 
breakwater were performed by hired labor at a cost 
of $270,543. Supervision and administration costs 
for repairs of the east gate were $23,719. Real estate 
costs were $22,337, and project management costs 
were $219,797. 
22-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Condition at End of Fiscal Year. The existing 
project is complete. Total costs to September 30, 
1992 were $24,407,374 of which $4,788,827 was for 
new work, $18,291,947 for maintenance and 
$1,326,600 for rehabilitation. 
5. CHICAGO RIVER, IL 
Location. Northeastern Illinois, in Cook County 
within the corporate limits of the City of Chicago. 
(See NOAA Nautical Chart Numbers 14926, 14927 
and 14928.) 
Previous Projects. See page 1394 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a channel 21 
feet deep in the main river from its mouth at Rush 
Street to the junction of the North and South 
Branches (0.7 miles); (b) a channel 21 feet deep in 
the North Branch from the junction to North Avenue 
(2.22 miles); (c) a channel 21 feet deep on the 
North Branch Canal (1.04 miles); (d) a 21-foot 
deep North Branch Turning Basin just south of 
North Avenue; and (e) a channel 9 feet deep in the 
North Branch from North Avenue to Addison Street. 
The project was authorized by the River and Harbor 
Acts of March 3, 1899, June 13, 1902, March 2, 
1907, and July 24, 1946 (See table 22-C). The 
portion of project authorized by River and Harbor 
Act of 1946 is presently being restudied to confirm 
economic feasibility. 
Local Cooperation. Fully complied with for 
completed modifications. River and Harbor Act of 
July 24, 1946, which provided the improvement of 
the channel, is subject to condition that local interests 
furnish assurances that they will hold the 
United States free from damages which may result 
from construction and maintenance of the improvement. 
Requirement has not been complied with. 
Terminal Facilities. Six docks are available. 
The most important cargoes handled are sand, gravel 
and crushed rock. 
Operations and Results During Period. Maintenance: 
Sediment surveys were performed by 
hired labor at a cost of $9,858 and by contract at a 
cost of $31,768. Water control activities were performed 
by hired labor at a cost of $119,166, by other 
COE at a cost of $22,204, by contract at a cost of 
$68,991, and by other federal agencies at a cost of 
$118,380. Project management and real estate 
costs were $79,742 and $7,402, respectively. 
Condition at End of Fiscal Year. The project 
is complete except for dredging the channel between 
North Avenue and Addison Street as authorized 
by the 1946 River Harbor Act. Head of navigation 
for deep-draft vessels is North Avenue, 5.97 
miles from the Michigan Avenue bridge. Total costs 
of the existing project to September 1992 were 
$15,209,639 of which $1,500,565 was for new work 
and $13,709,074 was maintenance. 
6. INDIANA HARBOR, IN 
Location. Northwestern Indiana, on the southwest 
shore of Lake Michigan in Lake County, 19 
miles southeast of Chicago Harbor. (See NOAA 
Nautical Chart Numbers 14926 and 14929.) 
Previous Projects. For details see page 1943 of 
Annual Report for 1915, and page 1520 of Annual 
Report for 1938. 
Existing Project. Provides for (a) a northerly 
rubblemound breakwater 1,120 feet long; (b) an 
easterly concrete capped caisson breakwater 201 
feet long with a rubblemound extension 2,324 feet 
long; (c) a lake approach channel 29 feet deep and 
800 feet wide; (d) an anchorage and maneuver basin 
28 feet deep; (e) a main canal entrance channel 27 
feet deep and 280 feet wide; (f) a main canal 22 feet 
deep; (g) a turning basin 22 feet deep; (h) the Forks 
Turning Basin 22 feet deep; (i) the Lake George 
Branch 22 feet deep; and (j) the Calumet River 
Branch 22 feet deep. The project was authorized by 
the River and Harbor Acts of March 4, 1913, March 
2, 1919, March 20, 1922, July 3, 1930, August 30, 
1935, August 28, 1937, and July 14, 1960 (See table 
22-C}. 
Local Cooperation. Substantially complied 
with. See FY 1986 Annual Report for full requirements. 
Terminal Facilities. Fifteen docks and wharves 
are available. Six docks handle iron ore and limestone. 
Six docks are for handling petroleum products 
and three docks for handling gypsum, scrap 
metal and steel, and bulk products. However, not 
all docks are presently being used for the shipment 
or receipt of waterborne commodities. 
Operations and Results During Period. Maintenance: 
Environmental studies and surveys were 
continued by hired labor at a cost of $322,122, by 
contract at a cost of $1,632, and by other COE at a 
cost of $22,000. Project management and real 
estate costs were $43,577 and $4,268, respectively. 
Condition at End of Fiscal year. The existing 
project is complete. Total costs of the existing 
project to September 30, 1992 were $15,565,830 of 
which $4,909,648 was for new work and $10,656,182 
was for maintenance. 
22-4

CHICAGO, IL, DISTRICT 
7. MICHIGAN CITY HARBOR, IN 
Location. Northwestern Indiana, on the southeast 
shore of Lake Michigan in La Porte County, 38 
miles southeast of Chicago Harbor. (See NOAA 
Nautical Chart Numbers 14905 and 14926. ) 
Previous Projects. See page 1407 of Annual 
Report for 1992. 
Existing Project. Provides for (a) a stone-filled 
timber crib detached breakwater 1,304 feet long; (b) 
a pile and steel sheeting west pier 835 feet long; (c) 
a stone-filled timber crib, opile and steel sheeting 
east pier 2,276 feet long; (d) a stonefilled timber 
crib east breakwater 1,000 feet long; (e) an entrance 
channel 18 feet deep and 425 feet wide; (f) a 
turning basin No. 1, 18 feet deep; (g) a channel in 
Trail Creek 18 feet deep; (h) a turning basin No. 2, 
18 feetdeep (i) an outer basin 12 feet deep in the 
northerly portion and 8 feet deep in the southerly 
portion; and (j) a channel in Trail Creek 6 feet deep 
and 50 feet wide from turning basin No. 2 to the E 
Street bridge. The project was authorized by the 
Rivers and Harbors Acts of March 3, 1899, March 3, 
1905, January 21, 1927, August 30, 1935, and 
Section 107 of July 14, 1960, Rivers and Harbors 
Acts approved on September 30, 1966 (See table 22- 
C).
Local Cooperation. Fully complied with. 
Terminal Facilities. There are several marinas 
in the lower mile of Trail Creek. The commodity 
handled at this harbor is fresh fish. 
Operations and Results During Period. Maintenance: 
Sediment surveys and studies of the Trail 
Creek basin were continued by hired labor at a cost 
of $125,694, by federal agencies at a cost of $21,971, 
by contract at a cost of $33,446 and by other COE at 
a cost of $136,372. Contract placement and supervision 
and administration for construction of the 
east pier were $489,363 and $92,909, respectively. 
E&D costs during construction were $2,797. Value 
engineering costs were $14,169. The costs to prepare 
plans and specs for dredging the outer harbor 
were $26,831. Contract placement and supervision 
and administration costs were $387,484 and $22,490, 
respectively. Real estate costs were $7,518 and program 
management costs were $120,125. 
Condition at End of Fiscal Year. The existing 
project is complete. Total costs of the existing 
project to September 30, 1992 were $12,478,310 of 
which $1,574,446 was for new work ($1,543,646 
federal and $30,800 non-federal funds), $9,285,194 
for maintenance, and $1,618,670 for rehabilitation. 
8. WAUKEGAN HARBOR, IL 
Location. Northeastern Illinois on the west 
shore of Lake Michigan in Lake County, 38 miles 
north of Chicago Harbor. (See NOAA Nautical 
Chart Numbers 14904 and 14905.) 
Previous Projects. See page 1392 of Annual 
Report for 1962. 
Existing Project. Provides for (a) a northerly 
stone-filled timber crib breakwater 588 feet long; 
(b) a stone-filled reinforced concrete caisson shore 
connection 270 feet long; (c) a stone-filled doublerow 
steel sheeting shore connection 640 feet long; 
(d) a single-row steel sheeting shore connection 398 
feet long; (e) a stone-filled timber crib north pier 
998 feet long; (f) a single-row steel sheet piling 
north pier 444 feet long; (g) a steel piling revetment 
632 feet long; (h) a stone-filled timber crib pier 
1,399 feet long; (i) a stone-filled double-row pile 
and sheeting south pier 1,712 feet long; (j) an 
entrance channel 22 feet deep and 390 feet wide; (k) 
a channel between the piers 18 feet deep and 200 
feet wide; (1) an inner basin 13 feet deep; and (m) an 
anchorage area in the southwest corner of the inner 
basin 8 feet deep. The project was authorized by the 
River and Harbor Acts of June 3, 1902, July 13, 
1930, and March 2, 1945 (See table 22 -C). 
Local Cooperation. Fully complied with. 
Terminal Facilities. Four docks are available. 
The commodities handled at this harbor are gypsum 
and building cement. 
Operations and Results During Period. Maintenance: 
Environmental studies and monitoring 
activities were performed by hired labor at a cost of 
$97,641, by other COE at a cost of $50,126 and by 
contract at a cost of $16,871. Water quality costs 
were $63,035 and real estate costs were $11,920. 
Preparation of a letter report and engineering and 
design costs associated with resurfacing the South 
Pier were $146,901. Prior year dredging contract 
was decreased by $10,000. Contract administration 
and project management costs were $2,424 and 
$104,327, respectively. 
Condition at End of Fiscal Year. The existing 
project is complete except for the 1970 modification 
which is being restudied. Total costs of existing 
project to September 30, 1992 were $9,875,384 of 
which $823,026 was for new work and $9,052,358 
was for maintenance. 
22-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
9. LAKE MICHIGAN DIVERSION 
Location. Northeastern Illinois on the southwest 
shore of Lake Michigan in Cook County, 
within the corporate limits of the City of Chicago. 
(See NOAA Nautical Chart Numbers 14926, 14927, 
and 14928.) 
Previous Projects. See page 22-3 of Annual 
Report for 1988. 
Operations and Results During Period. 
Maintenance: Studies and preparation of reports 
were performed by hired labor at a cost of $332,109, 
by other COE at a cost of $14,540, by other federal 
agencies at a cost of $47,810 and by contract at a 
cost of $95,043. 
Condition at End of Fiscal Year. Under Section 
1142, PL 99-662, the Corps of Engineers assumed 
responsibility for monitoring the Diversion 
of Lake Michigan water into the Illinois Waterway. 
The Corps of Engineers assumed full water diversion 
accounting responsibility in FY 1988. Total 
costs of the existing project to September 30, 1992 
were $489,502 for maintenance. 
10. RECONNAISSANCE AND 
CONDITION SURVEYS 
Condition surveys were performed at a cost of 
$115,275. 
11. NATIONAL EMERGENCY 
PREPAREDNESS 
Fiscal Year costs of $135,367 were for: 
Training and Exercises 
Management and Mobilization Planning 
$ 5,315 
130,052 
Alteration of Bridges 
12. OTHER AUTHORIZED BRIDGE 
ALTERATIONS, 
See table 22-D. 
Beach Erosion Control 
13. CASINO BEACH, IL 
Location. Casino Beach is located along the 
Lake Michigan shoreline at Jackson Park in Chicago, 
Illinois. 
Existing Project. The Casino Beach project was 
authorized by Section 501 (a) of the 1986 Water 
Resources Development Act. The project consists of 
rehabilitating 1,800 feet of the Casino jetty by encasing 
the existing timber pile and stone structure 
in steel sheet piling and a concrete cap. The 
estimated cost (1992) for new work is $7,820,000 of 
which $3,680,000 is federal and $4,140,000 is nonfederal. 
Local Cooperation. The local project sponsor is 
the Chicago Park District. The local sponsor is 
required to provide all lands, easements and rightsof-
way; complete all necessary relocations; hold and 
save the United States free from damages due to 
construction or operation of the project; operate and 
maintain the completed project; and make cash contribution 
toward the cost of construction. 
Operations and Results During the Period. 
New Work: Preconstruction engineering and 
design was continued at a cost of $152,230. 
Condition at the End of Fiscal Year. 
Preconstruction engineering and design is in 
progress. The total cost of the existing project to 
September 30, 1992 was $246,388. 
14. ILLINOIS BEACH 
STATE PARK, IL 
Location. Northeastern Illinois on the west shore 
of Lake Michigan along the 9-mile reach of shoreline 
immediately south of the Illinois-Wisconsin State 
line. (See NOAA Nautical Chart Numbers 14901 
and 14904.) 
Previous Projects. None. 
Existing Project. Provides for (a) construction 
of 46 rubblemound, offshore breakwaters approximately 
150 feet long and spaced about 300 feet 
apart; (b) initial beach nourishment consisting of 
placement of 100,000 cubic yards of coarse graded 
beach material; and (c) periodic renourishment of 
100,000 cubic yards approximately every five years. 
The project was conditionally authorized in Section 
501 (b) of the 1986 Water Resources Development 
Act subject to a report by the Corps of Engineers and 
approval by the Secretary of the Army. 
Local Cooperation. The local project sponsor 
would be required to provide all lands, easements 
and rights-of-way; accomplish all required relocations; 
hold and save the United State free from 
damages; and provide a cash contribution. 
Operatiops and Results During Period. None. 
Condition at End of Fiscal Year. Work on this 
project has been terminated. 
22-6

CHICAGO, IL, DISTRICT 
15. INDIANA DUNES NATIONAL 
LAKESHORE BANK PROTECTION, 
BEVERLY SHORES, IN 
Location. Northwestern Indiana, on the southeast 
shore of Lake Michigan in Porter County, approximately 
35 miles southeast of Chicago Harbor. 
(See NOAA Nautical Chart Numbers 14095 and 
14926. ) 
Existing Project. Provides for placement 13,000 
feet of stone revetment and periodic repair of riprap 
to maintain the full length of beach front at Beverly 
Shores, Indiana. The current project was authorized 
by Public Law 97-88 and Public Law 98-63. 
Local Cooperation. Fully complied with. 
Operations and Results During Period. 
Maintenance: E&D and project management 
costs were $21,193. 
Condition at End of Fiscal Year. Total costs of 
existing project to September 30, 1992 were 
$1,127,000 of which $660,000 was for new work and 
$467,000 was for maintenance. 
16. INDIANA SHORELINE 
EROSION, IN 
Location. On the south end of Lake Michigan 
along a two mile reach of shore west of Michigan 
City Harbor, Indiana. (See NOAA Nautical Chart 
Numbers 14095 and 14926.) 
Existing Project. The project consists of beach 
nourishment along approximately two miles of beach 
between Michigan City Harbor and Beverly Shores, 
Indiana, requiring an initial placement of 264,500 
cubic yards of sand. Periodic replenishment of 
about 264,500 cubic yards of sand at five year intervals 
would be required throughout the life of the 
project. The project was authorized for construction 
by Section 501 of the Water Resources Development 
Act of 1986. Estimated federal cost (1992) for 
new work is $183,000,000, including future beach 
nourishments. 
Local Cooperation. None required. 
Operations and Results During Period. 
New Work: Advance engineering and design was 
continued at a cost of $1,160. 
Condition at End of Fiscal Year. 
Preconstruction planning and engineering was initiated 
in fiscal year 1984. Total cost of the existing 
project to September 30, 1992 is $353,274. 
17. OTHER AUTHORIZED BEACH 
EROSION CONTROL PROJECTS 
See table 22-E. 
18. BEACH EROSION CONTROL 
UNDER SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103 of the Rivers and Harbors Act of 1962, as 
amended. None. 
Flood Control 
19. CHICAGO RIVER, IL 
(NORTH BRANCH) 
Location. Northern Illinois, in Cook and Lake 
Counties. 
Existing Project. Provides for clearing the 
channel of the North Branch of the Chicago River, 
Illinois, of fallen trees, roots, and other debris and 
objects which contribute to the flooding, unsightliness, 
and pollution of the river. The project extends 
from Wolf Point in Chicago, Illinois, to its source 
just south of Rockland Road east of Libertyville, 
Illinois. The project was authorized by the River 
and Harbor Act of December 31, 1970 (Section 116) 
and amended by the River and Harbor Act of March 
7, 1974 and the Water Resources Development Act 
of 1986. 
Local Cooperation. The 1970 Act provided that 
local interests furnish without cost to the United 
States all lands, easements, rights-of-way, and disposal 
areas necessary for construction of the project; 
hold and save the United States free from damages 
due to construction; maintain and operate all works 
after completion without cost to the United States; 
and agree to bear all costs in excess of $200,000 for 
completing construction. The 1974 Act provided that 
the United States will maintain the channel free of 
trees, roots, debris and objects at a cost not to 
exceed $150,000 per year with non-federal interests 
paying 25 percent of the cost of maintenance. The 
1986 Water Resources Development Act changed 
the cost sharing to require that nonfederal interests 
pay 50 percent of the cost of maintenance plus cost 
of disposal. 
Operations and Results During Period. 
Maintenance: FY 91-92 contract costs were 
$100,447. Supervision and administration costs were 
$4,901. E&D was performed by hired labor at a cost 
of $23,410. Real estate cost was decreased by 
$12,304 and the FY 1990 contract cost was decreased 
by $3,211. The total federal and non- 
22-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
federal expenditures were $113,243 and $118,720, 
respectively. 
Condition at End of Fiscal Year. Total cost of 
existing project to September 30, 1992 was 
$3,294,656 of which $231,884 was for new work 
($191,884 regular funds and $40,000 contributed 
funds), and $3,062,772 was for maintenance 
($2,150,039 federal funds and $912,733 non-federal 
contributed funds). 
20. LAKE GEORGE, HOBART, IN 
Location. Lake George in Hobart, Indiana and 
Deep River watershed upstream of the lake through 
Lake Station, Indiana. 
Existing Project. The project consists of the 
removal of silt, aquatic growth and other material 
and the construction of silt traps or other devices to 
prevent and abate the deposition of sediment. Estimated 
cost (1992) for new work is $5,710,000 
federal and $1,900,000 to be contributed by local 
interests. Project was authorized by Section 602 of 
the Water Resources Development Act of 1986. 
Local Cooperation. Section 602 (b), Water 
Resources Development Act of 1986 applies. By 
letter dated March 9, 1987 the City of Hobart, Indiana 
indicated that it was a potential local project 
sponsor and applied for credit for previous work 
applicable to the project under the provisions of 
Section 104 (d) of the 1986 WRDA. 
Operations and Results During Period. 
New Work: Preconstruction engineering and 
design was continued at a cost of $98,645. 
Condition at End of Fiscal Year. 
Preconstruction engineering and design is in 
progress. Total cost of the existing project to 
September 30, 1992 is $194,497. 
21. LITTLE CALUMET RIVER, IN 
Location. Little Calumet River is located in 
northwest Indiana between the Illinois-Indiana 
State line and the Conrail Railroad in east Gary, 
Indiana. 
Existing Project. The project consists of replacing 
9.5 miles of existing spoil bank levees with 12.2 
miles of new levees, floodwalls, closure and 
appurtant structures between the Illinois-Indiana 
State line and Cline Avenue; construction of 9.7 
miles of set-back levees in Gary; a diversion structure 
at Hart Ditch; permanent evacuation of 29 
structures in the Black Oak area of Gary; flood 
proofing 38 residential structures in Gary; modifying 
7 miles of channel and 3 accompanying bridge 
culvert modifications; modifying 1 highway bridge; 
construction of 16.8 miles of hiking trails and accompanying 
recreation support facilities; and preservation 
of 788 acres of wetlands with wildlife 
mitigation measures. Estimated federal cost (1992) 
for new work is $110,000,000; $30,700,000 is to be 
contributed by local interests. The project was 
authorized by Section 401 of the Water Resources 
Development Act of 1986. 
Local Cooperation. The local sponsor is the Little 
Calumet River Basin Development Commission. The 
local cooperation agreement was signed on August 
16, 1990. The local sponsor is required to provide 
all lands, easements and rights-of-ways; provide all 
required relocations; and hold and save the United 
States from any damages due to construction or 
operation of the project. In addition, the local 
sponsor is required to pay a five percent cash contribution 
for structural flood control measures, fifty 
percent for recreation features and twenty-five percent 
for fish and wildlife enhancements. 
Operations and Results During Period. The 
third nonstructural contract was awarded on September 
30, 1992. Construction for Stage II-1 levee 
segment from Harrison Street to Broadway (North) 
was completed on July 15, 1992. The construction 
contract for the Stage II-2 levee segment from Grant 
to Harrison Streets (North) was awarded on August 
20, 1992. The construction contract for the Stage 
III levee segment from Chase to Grant Streets was 
awarded on September 30, 1992. Real estate 
management costs were $153,659 ($143,239 federal 
and $10,420 nonfederal). Engineering and design 
costs were $2,941,111 ($2,430,780 federal and 
$510,331 non-federal which includes $2,123,680 
hired labor, $252,893 performed by other COE, 
$1,525 by other agencies and $563,013 by contract. 
Construction contract costs were $371,740 ($220,789 
federal and $150,951 non-federal) . Construction 
management costs were $129,545 ($116,453 federal 
and $13,092 non-federal). Total federal and nonfederal 
costs were $2,911,261 and $684,794, respectively. 
Condition at End of Fiscal Year. Construction 
is in progress. Total cost of existing project to 
September 30, 1992 was $10,581,612 for new work. 
Federal costs total $9,805,712; non- federal costs 
total $775,900. 
22. LITTLE CALUMET RIVER 
BASIN, CADY MARSH DITCH, IN 
Location. Cady Marsh is located in Lake County, 
Indiana. The Ditch is a tributary of the Little Calu- 
22-8

CHICAGO, IL, DISTRICT 
met River system in northwest Indiana and flows 
through the Towns of Griffith and Highland. 
Existing Project. The Cady Marsh Ditch flood 
control project was authorized by Section 401 (a) of 
the 1986 Water Resources Development Act. The 
project provides for diverting flood flows from Cady 
Marsh Ditch to the Little Calumet River through a 
diversion system under Arbogast Avenue in Griffith. 
Specifically, the project consists of improving 1,290 
feet of Cady Marsh Ditch between Colfax and 
Arbogast Avenues in Griffith, constructing approximately 
5,000 feet of large conduct pipes under 
Arbogast Avenue, excavating an open channel approximately 
2,850 feet long from the north end of 
Arbogast Avenue to the Little Calumet River, and 
constructing interior drainage improvements. The 
estimated cost (1992) for new work is $10,300,000 
of which $6,830,000 is federal and $3,470,000 is 
nonfederal. 
Local Cooperation. The local project sponsor is 
the Town of Griffith, IN. The local sponsor is 
required to provide all lands, easements and rightsof-
way; complete all required utility relocations; 
hold and save the United States free from damages 
due to construction or operation of the project; provide 
the required interior drainage improvements; 
operate and maintain the completed project; and 
make a cash contribution toward the cost of construction. 
Operations and Results During the Period. 
New Work: Preconstruction engineering and 
design was continued at a cost of $160,368. 
Condition at End of Fiscal Year. 
Preconstruction engineering and design is in 
progress. The total cost of the existing project to 
September 30, 1992 was $213,307. 
23. McCOOK AND THORNTON 
RESERVOIRS, IL 
Location. The McCook Reservoir will be located 
within the communities of McCook and Hodgkins, 
Illinois at the existing McCook Quarry. The 
Thornton Reservoir will be located in the community 
of Thornton, Illinois at the existing Thornton 
Quarry. 
Existing Project. The project consists of converting 
two quarries into flood storage reservoirs. 
The McCook Reservoir will have a storage volume of 
32,100 acre-feet (9.8 billion gallons); the Thornton 
Reservoir will have a volume of 14,600 acre-feet (4.8 
billion gallons). The reservoirs will store floodwater 
from tunnels constructed or under construction 
by the U.S. Environmental Protection Agency and 
the Metropolitan Water Reclamation District of 
Greater Chicago as part of the Tunnel and Reservoir 
Project (TARP). Estimated project cost (1992) is 
$636,000,000, including a federal cost for new work 
of $477,000,000, and $159,000,000 to be contributed 
by non-federal interests. Project was authorized 
by Section 3 of the Water Resources Development 
Act of 1988. 
Local Cooperation. By letter dated 13 November 
1986, the Metropolitan Water Reclamation District 
of Greater Chicago indicated that it would be 
the local sponsor and provide the required local 
cooperation. 
Operations and Results During Period. 
New Work: Preconstruction engineering and 
design was continued at a cost of $2,227,749, including 
$35,091 for real estate activities, $758,584 for 
A-E contracts, $438,497 performed by other COE 
and $995,577 for hired labor. 
Condition at End of Fiscal Year. 
Preconstruction planning, engineering and design 
was in progress. Total costs of the existing project 
to September 30, 1992 were $5,127,411. 
24. NORTH BRANCH, CHICAGO 
RIVER, IL 
Location. The North Branch Chicago River 
Basin is located north of the City of Chicago in 
suburban Cook and Lake Counties. 
Existing Project. The project consists of constructing 
two excavated floodwater storage reservoirs 
on the West Fork and one excavated reservoir 
on the Middle Fork. The Water Resources Development 
Act of 1986, Section 401, also includes authorization 
to reimburse non-federal interests 50 percent 
of the costs of planning and construction for 
three existing reservoirs on the West Fork, known 
as Techny Reservoirs, and the existing Mid Fork 
Reservoir on the Middle Fork. Reservoir 27 in the 
Village of Bannockburn, is located on the West 
Fork, 12.7 miles above its confluence with the 
North Branch Chicago River. It has a floodwater 
storage capacity of 525 acre-feet. Approximately 
700 feet of the West Fork channel was improved and 
relocated for construction of the diversion structure. 
Reservoir 29A is located 9.6 miles above the 
mouth of the West Fork and 3.1 miles south of 
Reservoir 27. The reservoir floodwater storage 
capacity is 575 acre-feet. Two project features, 
channel relocation and construction of two bridges, 
are non-federal responsibility. Reservoir 15 is located 
near the City of Green Oaks on the Middle 
Fork, 22.1 miles above its confluence with the North 
Branch Chicago River. The design floodwater storage 
capacity is 500 acre-feet.The reservoir is approximately 
42 feet deep except in the sedimentation 
pool area which will be about 15 feet deeper. 
Estimated federal cost (1992) for new work is 
22-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
$19,564,000. An additional $9,980,000 will be the 
required contribution by local interests. The nonfederal 
improvements for Reservoir 29A will require 
a $550,000 cash contribution from local interests. 
The non-federal clean-up of soils contaminated 
with lead shot pellets at Reservoir 29A may 
cost between $5.0 and $8.0 million. The project was 
authorized by the Water Resources Development 
Act of 1986. 
Local Cooperation. The local sponsor is required 
to provide all lands, easements and rightsof-
way; provide all required relocations; and hold 
and save the United States government free from 
any damages due to construction or operation of the 
project. In addition, local sponsors are required to 
pay a cash contribution to bring the total nonfederal 
share of the flood control improvements to 
twenty-five percent of the total project cost. 
Operations and Results During Period. 
New Work: Construction of Reservoir 15 was 
substantially completed on May 15, 1992. Total 
costs for Reservoir 15 were $1,126,300 ($868,884 
federal and $257,416 non-federal). Costs include 
$864,120 for construction contract; $130,242 for 
construction management; $495 for real estate management; 
$98,743 for engineering and design and 
$32,700 was provided to the Cook County Forest 
Preserve for fish and wildlife mitigation. Total 
costs for Reservoir 27 were $13,705 ($13,582 federal 
and $123 non-federal). Costs included $124 for 
construction contract; $10,417 for construction management 
and $3,164 for engineering and design. 
Total costs for Reservoir 29A were $1,060,707 
($438,586 federal; $287,586 non-federal cash; 
$59,491 non-federal improvements; and $275,044 
for non- federal clean-up of soils contaminated with 
lead shot pellets). The authorized project costs for 
Reservoir 29A included $615,345 for construction 
contract; $90,334 for construction management; 
$3,031 for real estate management and $17,462 for 
engineering and design. Nonfederal bridge and 
channel improvements costs were $59,491 for construction. 
The lead shot clean-up costs were $87 for 
the construction. A total of $41,440 for construction 
management and $233,517 for engineering and 
design of which $95,473 was for A-E contract and 
$138,044 was for hired labor. 
Condition at End of Fiscal Year. The existing 
project is 85 percent complete. Construction of 
Reservoir 27 is complete, except for some limited 
reservoir side slope stabilization which will be completed 
in Fiscal Year 1993. Reservoir 15 is substantially 
complete except for some landscaping. 
Reservoir 29A is approximately 83 percent complete. 
Total costs of the existing project to September 
30, 1992 were $21,232,566, of which $19,342,877 
was federal and $1,889,689 was non- federal, excluding 
the $4,493,298 non-federal cost for the 
Techny and Mid Fork Reservoirs. A total $469,580 
in non-federal funds have been expended on bridge 
and channel betterments at Reservoir 29A. An 
additional $688,500 in non-federal funds have been 
expended on investigations in connection with the 
clean-up of soils contaminated with lead shot pellets 
at Reservoir 29A. 
25. O'HARE RESERVOIR, IL 
Location. The reservoir will be located in an 
unincorporated portion of Elk Grove Township in 
northwestern Cook County, Illinois about 1 mile 
northwest of Chicago O'Hare International Airport. 
Existing Project. The project consists of a 1,050 
acre-foot capacity reservoir, excavated to a depth of 
80 feet. The reservoir would be constructed at the 
terminus of the existing system of 6.6 miles of deep 
tunnels, constructed under the U.S. Environmental 
Protection Agency and the Metropolitan Water Reclamation 
District of Greater Chicago Tunnel and 
Reservoir Project (TARP). estimated project cost 
(1992) is $25,600,000 including a federal cost for 
new work of $17,400,000 and $8,200,000 to be contributed 
by local interests. The project was authorized 
by Section 401 of the Water Resources Development 
Act of 1986. 
Local Cooperation. The local sponsor is the 
Metropolitan Water Reclamation District of Greater 
Chicago. The local cooperation agreement for the 
first construction contract, creek relocation, was 
signed on July 31, 1990. The local sponsor is 
required to provide all lands, easements and rightsof-
way; provide all required relocations; and hold 
and save the United States government free from 
any damages due to construction or operation of the 
project. In addition, the local sponsor is required to 
pay a cash contribution of five percent of the total 
project costs. The local cooperation agreement for 
the second construction contract, reservoir excavation 
and lining, was signed July 29, 1991. 
Operations and Results During Period. Construction 
was continued at a cost of $1,298,271 
($1,225,770 federal and $72,501 non-federal). The 
utility relocations were initiated at a nonfederal 
cost of $848,999. Real estate management activities 
costs were $38,015 ($37,668 federal and $347 nonfederal). 
engineering and design costs were $369,858 
($34,337 federal and $335,521 non-federal). Construction 
management costs were $187,096 
($176,579 federal and $10,517 non-federal). Total 
federal and non-federal costs were $1,474,354 and 
$1,267,885, respectively. 
Condition at End of Fiscal Year. 
Preconstruction planning and engineering is completed. 
Construction is in progress. Total costs of 
the existing project to September 30, 1992 were 
22-10

CHICAGO, IL, DISTRICT 
$5,877,177 for new work. Federal costs total 
$4,550,626; nonfederal costs total $1,326,551. 
26. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See table 22-F. 
27. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities, repair, flood 
fighting and rescue work (Public Law 99, 84th Congressional 
antecedent legislation). 
Fiscal Year Costs 
Program to September 30, 1992 
Disaster Preparedness 
Emergency Operations 
Disaster Assistance (FEMA) 
$ 250,298 
18,077 
5,928,947 
Flood control activities pursuant to Section 205 of 
Flood Control Act of 1965, as amended. 
Fiscal year costs were $90,088 federal and $24,267 
non-federal for flood control activities. The initial 
appraisals were continued for Kankakee River, Lake 
and Newton Counties, IN ($2,754); and for Little 
Calumet River South Holland, IL ($2,625). The 
initial appraisals were initiated for the City of Oak 
Forest, Cook County, IL ($5,504) and for the 
Village of Palos Park, Cook County, IL ($6,852). The 
reconnaissance report was continued for Tinley 
Creek ($1,202). The work in developing the Feasibility 
Cost Sharing Agreements was continued for 
Monticello Avenue ($5,676) and for McCook Levee 
($7,469). The feasibility phase was continued for 
North Libertyville Estates at a cost of $13,064 federal 
and $8,537 non-federal, and for the Fox River 
McHenry County ($6,126). The work on the feasibility 
phase was initiated for Valley View at a cost of 
$38,816 federal and $15,730 non-federal. 
Flood control activities specifically directed in FY 
1990 Energy and Water Development Appropriations 
Act (Public Law 101-101). 
Kankakee River Icebreaker, Wilmington, IL $3,740 
28. SURVEYS 
Fiscal Year 1992 costs were $232,771 federal and 
$74,983 non-federal itemized as follows: 
Flood Damage 
Prevention Studies $ 
Shoreline 
Protection Studies 
Miscellaneous Activities 
Coordination Studies 
Federal Non-federal 
104,587 $ 61,488 
13,006 
72,625 
42,553 
0 
10,061 
3,434 
29. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal Year 1992 costs of $160,422 were for: 
Flood Plain Management Services 
International Water Studies 
Hydrologic Studies 
$ 97,622 
59,800 
3,000 
22-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 22-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
1. Burns Waterway 
Harbor, IN 
(Federal Funds) 
(Contributed 
Funds) 
2. Burns Waterway 
Small Boat 
Harbor, IN 
(Federal Funds) 
(Contributed 
Funds) 
3. Calumet Harbor 
and River, IL 
and IN 
(Federal Funds) 
(Contributed 
Funds) 
4. Chicago Harbor, 
IL 
(Federal Funds) 
5. Chicago River, IL 
6. Indiana Harbor, IN 
New Work 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
Maint: 
Contib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint 
Approp. 
Cost 
O 13,584,000 
0 13,584,000 
1,041,000 12,311 163,000 310,000 
1,172,824 62,051 160,792 272,584
0
0
0 2,000,000 
0 2,000,000 
185,000 199,435 168,500 118,000 
173,282 218,288 175,244 112,614
0
0
0
0 
446,500 914,963 665,000 710,500 
1,458,542 926,474 737,628 559,663 
2,185,000 
3,612,977
0
0
0
0 
0 
139,973
0
0
0
0 
0
0
0
0
0
0 
0
0
0
0
0
0 
1,327,000 1,437,160 1,814,600 1,506,500 
1,333,944 1,527,448 1,661,435 1,573,400
0
0
0
0 
0
0 
1,076,000 981,657 909,000 480,000 
1,347,097 1,042,749 929,254 457,511
0
0 
611,000 290,200 322,000 408,000 
745,455 299,862 334,762 393,599 
22-12 
5,911,104 
5,871,480 
15,900 
15,900 
720,935 
712,229 
1,770,558 
1,770,558 
22,578,5671 
22,578,5671 
28,276,237 2 
28,091,297 2 
5,428,001 
5,428,001 3 
836,667 
836,667 
4,788,827 4 
4,788,827 4 
18,530,546 
18,291,947 
1,326,600 
1,326,600 
1,500,565 5 
1,500,565 6 
13,766,394 6 
13,709,074 6 
4,897,148 ' 
4,897,148 ' 
10,675,988 8 
10,656,1828

CHICAGO, IL, DISTRICT 
TABLE 22-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
(Contributed New Work: 
Funds) Approp. 0 0 0 0 12,500 
Cost 0 0 0 0 12,500 
7. Michigan City New Work: 
Harbor, IN Approp. 0 0 0 0 1,543,646 9 
Cost 0 0 0 0 1,543,646 9 
Maint: 
Approp. 270,000 832,542 752,000 1,749,000 9,685,054 
Cost 275,935 847,323 623,165 1,481,169 9,285,194 
Rehab: 
Approp. 0 0 0 0 1,618,670 
Cost 0 0 0 0 1,618,670 
(Contributed New Work: 
Funds) Contrib. 0 0 0 0 30,800 
Cost: 0 0 0 0 30,800 
8. Waukegan New Work: 
Harbor, IL Approp. 0 0 0 0 823,026 10O 
Cost 0 0 0 0 823,026 10o 
Maint: 
Approp. 201,000 616,788 826,000 456,000 9,123,768 11 
Cost 173,840 576,487 836,025 483,245 9,052,358 11 
9. Lake Michigan 
Diversion Maint: 
Approp. 0 0 0 530,000 530,000 
Cost 0 0 0 489,502 489,502 
13. Casino Beach, IL New Work: 
Approp. 0 0 220,000 375,000 595,000 
Cost 0 0 94,158 152,230 246,388 
14. Illinois Beach New Work: 
State Park, IL Approp. 0 0 50,000 0 50,000 
Cost 0 0 10,548 0 10,548 
15. Indiana Dunes New Work: 
Nat'l Lakeshore Approp. 0 0 0 0 660,000 
Beverly Shores, Cost 0 0 0 0 660,000 
IN Maint: 
Approp. (10,000) 0 18,500 21,000 467,000 
Cost 1,679 915 18,307 21,193 467,000 
16. Indiana Shore- New Work: 
line Erosion, IN Approp. 15,000 90,000 79,000 0 399,000 
Cost 49,092 90,000 32,114 1,160 353,274 
19. Chicago River, IL New Work: 
(North Branch) Approp. 0 0 0 0 191,884 
(Federal Funds) Cost 0 0 0 0 191,884 
Maint: 
Approp. 33,000 247,350 150,000 145,000 2,223,350 
Cost 40,327 228,339 190,755 113,243 2,150,039 
(Contributed New Work: 
22-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 22-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
Funds) 
19. Lake George, 
Hobart, IN 
20. Little Calumet 
River, IN 
(Federal Funds) 
(Contributed 
Funds) 
21. Little Calumet 
River Basin, Cady 
Marsh Ditch, IN 
22. McCook and 
Thornton Reservoirs, 
IL 
23. North Branch 
Chicago River, IL 
(Federal Funds) 
(Contributed 
Funds Required) 
(Non-Federal 
Improvements) 
(Non-Federal 
Lead shot 
Clean-up) 
24. O'Hare Reservoir, 
IL 
(Contributed 
Funds) 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp: 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
0 350,000 171,681 175,000 
11,575 46,898 265,626 118,720 
89,000 125,000 330,000 
23,534 72,318 98,645 
337,000 2,366,000 2,703,000 3,013,000 
329,053 2,181,140 2,709,311 2,911,261 
160,000 344,000 304,000 
0 91,106 684,794 
220,000 170,000 
52,939 160,369 
1,107,000 617,000 2,000,000 2,000,000 
599,850 1,065,821 1,179,226 2,227,749 
1,476,500 7,097,000 6,497,000 
4,094,037 6,960,007 4,884,474 
0 
1,321,052 
183,000 374,000 1,118,250 159,017 
185,118 238,159 921,287 545,125 
173,752 327,000 
21,789 388,300 
0 
59,491 
458,900 1,071,967 
413,456 275,044 
493,000 1,504,000 4,300,000 4,000,000 
545,928 973,620 1,024,652 1,474,354 
80,500 220,000 3,640,700 
0 58,666 1,267,885 
1 Includes $855,973 for previous projects. 
2 Excludes contributed funds in settlement pursuant 
to decree (No. 54-C-1608) regarding removal of flue dust 
and includes $45,230 for previous projects. 
3 Includes $689,001 in settlement pursuant to decree 
regarding removal of flue dust. 
4) Includes $446,005 for previous projects. 
5 Includes $955,886 for previous projects. 
6 Includes $109,463 for previous projects. 
7 Includes $60,668 for previous projects. 
8 Includes $2,509 for previous projects. 
9 Includes $287,389 for previous projects. 
o1In0c ludes $218,233 on previous projects. 
11 Includes $15,711 on previous projects. 
22-14 
40,000 
40,000 
1,222,079 
912,733 
214,000 
194,497 
10,094,000 
9,805,712 
808,000 
775,900 
390,000 
213,307 
5,874,000 
5,127,411 
20,053,500 
9,342,877 
2,089,267 
1,889,689 
500,752 
469,580 
1,530,867 
688,500 
10,882,000 
4,550,626 
3,941,200 
1,326,551

CHICAGO, IL, DISTRICT 
TABLE 22-B AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Oct. 27, 1965 
Jul. 14, 1960 
Section 107 
Mar. 3, 1899 
Jun. 13, 1902 
Mar. 3, 1905 
Jun. 25, 1910 
Sept. 22, 1922 
Aug. 30, 19351,2 
Aug. 30, 19351,2 
Mar. 2, 19453 
Jul. 14, 196013 
Oct. 23, 196213 
Oct. 27, 196513 
Jul. 11, 1870 
Jun. 14, 1880 
Mar. 3, 1899 
Jul. 25, 1912 
Mar. 2, 1919 
BURNS WATERWAY HARBOR, IN 
(See Section 1 of Text) 
Provides for breakwater and channel to present dimensions and depths, a 
north breakwater, west bulkhead, approach channel and outer harbor, 
east and west harbor arms. 
BURNS WATERWAY SBH, IN 
(See Section 2 of Text) 
Provides for a 700-foot north breakwater,a 950-foot west breakwater, an 
entrance channel 11-feet deep, a harbor-of-refuge area 10 feet deep, and 
a channel in Burns Waterway 6 feet deep. 
CALUMET HARBOR AND RIVER, IL AND IN 
(See Section 3 of Text) 
Outer harbor protected by breakwaters. 
Five turning basins. 
Provided for shape and dimensions of turning basins. 
Consolidated the 2 projects for Calumet Harbor and Calumet River. 
Detached breakwater, dredging outer harbor to existing project depth and 
dimensions; deepen river-entrance channel and river to existing project 
depths; widen and straighten river channel; 5 turning basins to same 
depth as adjacent channel. 
Dredging area A and B in south end of Lake Calumet and an entrance 
channel 300 feet wide and 21 feet deep. 
An approach channel to harbor 3,200 feet wide and 28 feet deep through 
shoals outside breakwater and closing existing gap between breakwaters. 
Depth of 29 feet in lake approach to 28 feet in outer harbor, and 27 feet in 
river entrance up to E.J. & E. Ry. Bridge 
Deepen, widen, and straighten channel in Calumet River from E.J. and E. 
Ry. Bridge, to and including turning basins 1, 3, and 5 to 27 feet; enlarge 
turning basins 3 and 5; a channel into Lake Calumet to 27 feet deep for 
3,000 feet and a width of 1,000 feet; and eliminate turning basins 2 and 4 
from project. 
Modification of Act of Oct. 23, 1962. Protection for Elgin, Joliet and Eastern 
Railway Bridge over the Calumet River, to permit dredging to full 
width of the south draw to depth of 27 feet, and temporary protection for 
center pier and south abutment of the New York, Chicago, and St. Louis 
Railroad Bridge (Nickle Plate) to permit dredging of full width of south 
bridge draw to depth of 27 feet prior to its replacement. 
CHICAGO HARBOR, IL 
(See Section 4 of Text) 
Inner breakwaters and inner basin. 
Exterior Breakwater. 
Present project depth in basin, and entrance to Chicago River. 
Shore-arm and southerly extension of exterior breakwater 
Modification of area to be dredged in inner basin. 
Mar. 3, 1931 Shore-arm extension of exterior breakwater transferred to Lincoln Park 
Commissioners. 
Public Law, 89-298, H Doc. 
160. 88th Cong., 1st Sess. 
Detailed Project Report 
dated February 1983. 
Annual Report, 1896, pp. 
2584 et Seq. and H. Doc 277, 
54th Cong., 1st Sess. 
H. Doc. 172. 54thCong., 
2d Sess. 
H. Doc. 346, 60th Cong., 
1st Sess. 
H. Doc.494, 72d Cong., 
2nd Sess. 
H. Doc., 180. 73rd Cong., 
2d Sess. 
H. Doc. 233, 76th Cong., 
1st Sess. 
H. Doc.,149, 86th Cong., 
1st Sess.8 
H. Doc., 87thCong., 
2d Sess.5 
H. Report No. 973, 89th Cong., 
1st Sess. 
H. Ex. Doc. 114,41st Cong.,2d 
Sess. and Annual Report 1879, 
pp. 1562-1567 
Annual Report, 1870 pp 
1562-1567 
Annual Report, 18 9 7,pp 
2790-2791 
H.Doc. 710, Cong., 2d Sess. 
H.Doc.1303,64th Cong., 1st 
Sess. 
Public Law 797, 71st Cong. 
22-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 22-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
Mar. 2, 1945 
Oct. 23, 1962 
Dec. 4, 1981 
Jul. 30, 1983 
Mar. 3, 1899 
Jun. 13, 1902 
Mar. 2, 1907 
Mar. 2, 1919 
Jul. 24, 1946 
Nov. 17, 1986 
Jun. 25, 1910 
Mar. 4, 1913 
Mar. 2, 1919 
Mar. 20, 1922 
Mar. 3, 1925 
Mar. 2, 1929 
July 3, 193010 
Jul. 30, 1932 
Aug. 30, 193511 
Aug. 28, 1937 
Jul. 14, 1960 
Oct. 27, 196512 
Resumption of jurisdiction over shore-arm extension breakwater and over 
certain navigable waters in Lake Michigan which lie in northwestern 
part of outer harbor. 
Deepen a lake approach channel to 29 by 800 feet wide for 6,600 feet; and 
deepen a channel and maneuver area inside harbor entrance to 28 by 
1,300 feet wide. 
Provides for lock operations and maintenance responsibilities in the 
interests of navigation 
CHICAGO RIVER, IL 
(See Section 5 of Text) 
For project depth of 21 feet in lieu of that fixed by act of June 3, 1896. 
Turning basins. 
Interpreted by Chief of Engineers, April 11, 1908 as adopting new work of 
the then existing project for 21-foot depth. 
Eliminated all work except maintenance of main river. 
Dredging channel 9 feet deep to within 30 feet of existing bulkheads and 
river banks from North Ave. to Belmont Ave., thence 9 feet deep and 
50 feet wide to Addison St. 
LAKE MICHIGAN DIVERSION 
(See Section 9 of Text) 
Responsible for monitoring of Lake Michigan Diversion 
INDIANA HARBOR, IN 
(See Section 6 of Text) 
Maintenance of outer harbor. Maintenance of inner harbor channel 
when deeded free of cost to and accepted by the United States. 
Breakwaters. 
Lighthouse crib, present length and alignment easterly and northerly 
breakwaters. 
Reduce length of channel to be maintained in extension to Lake George. 
Authorized Secretary of War to modify project so far as relates to length 
and alignment of breakwaters and to sell Youngstown Steel and Tube Co. 
about 1,180 linear feet of shoreward end of existing north breakwater. 
Accept 2.3 acres of land for construction of the Forks Turning Basin. 
Existing project channel width and depth in Lake George Branch and 
turning basin at the Forks. 
Authorized Secretary of War to sell Inland Steel Co., about 1,903 linear 
feet of southerly end of existing east breakwater. 
Extended easterly breakwater, dredge entrance channel and outer harbor, 
deepen channel between bulkhead fills, widen main stem of canal and 
portion of Calumet River Branch to 141st St. 
Modified conditions of local cooperation required before enlargement of 
Indiana Harbor Canal is undertaken by United States. 
Increase authorized depths of 29 feet in outer harbor entrance channel; 28 
feet in outer harbor, and 27 feet in canal entrance channel to first E.J. & 
E. Ry, Bridge. 
Deepen main canal from landward end of canal entrance channel to a point 
lakeward of Dickey Place Bridge over a modified channel width of 190 
feet, except through bridge openings. 
22-16 
Public Law 14, 79th Cong. 
H. Doc.485,87th Cong., 
2d Sess 4 
Section 107 of Public Law 
97-88 Public Law 98-63. 
Specified in act. 
Specified in act. 
H. Doc.95, 56th Cong. 
1st Sess. (Annual Report, 
1900 p. 3863 and Annual 
Reportl909, p. 709) 
H.Doc.,1294,64th Cong., 
1st Sess. 
H.Doc. 767, 78th Cong., 
2d Sess.6,7 
Section 1142, Water Resources 
Development Act of 1986 
H. Doc. 1113, 60th Cong., 
2d Sess. 
H. Doc. 690, 62d Cong., 
2d Sess. 
Rivers and Harbors Committee 
Doc. 6, 65th Cong., 2d Sess. 
Public Law 176, 67th Cong. 
Rivers and Harbors Committee 
Doc. 21, 71st Cong., 2d Sess. 
Public Law 219, 72d Cong. 
Rivers and Harbors Committee 
Doc. 29, 72d Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 13, 75th Cong., 1st Sess. 
H. Doc., 195, 86th Cong., 
1st Sess. 
H. Doc 227, 89th Cong., 
1st Sess.

CHICAGO, IL, DISTRICT 
TABLE 22-B (Continued) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
MICHIGAN CITY HARBOR, IN 
(See Section 7 of Text) 
East breakwater and old east pier inclosing the outer basin. 
Extension of east pier. 
Mar. 3, 1889 
Mar. 3, 1905 
Jan. 21, 1927 
Aug. 30, 1935 
Jul. 14, 1960 
Sec. 107 
Extend east pier and construct detached breakwater. 
Lower turning basin. 
Rebuild west pier as at present located. 
Present project dimensions of entrance channel. 
Existing project depth in channel, and in lower and middle turning basins, 
eliminated improvement of Trail Creek above middle turning basin and 
uncompleted portion of detached breakwater, abandonment of old east 
breakwater and old east pier inclosing outer basin. 
Restore and repair westerly 1,000 feet of east breakwater, dredging outer 
basin, and enlarging entrance to basin through east pier. 
Recommendations of a Board 
of Engineers. Annual Report 
1870. p. 123. 
Reports of Boards of Engineers. 
Annual Report 1851, 
pp 218 7-2189; Annual Report 
1882. p. 2264-2266. 
Annual Report 1897, pp. 
2903-2904. 
Joint Resolution of Congress 
approved May 13, 1908. 
Public Law 23. 
H. Doc. 279, 69th Cong., 
1st Sess. 
Rivers and Harbors Committee 
Doc. 34, 74thCong., 1st Sess. 
Dredge river channel 50 feet wide and 6 feet deep from upper turning basin Detailed Project Report dated 
to E. Street Bridge. June 19658 
WAUKEGAN HARBOR, IL 
(See Section 8 of Text) 
Jun. 14, 1880 Parallel piers and basins.9 
Aug. 3, 1882 Modified location of harbor entrance. 
Jun. 13, 1902 Detached breakwater, extend piers, increase width of harbor at inner end 
of north pier, and dredge channel and basin to depth of 20 feet. 
Jul. 3, 1930 Extension of breakwater to shore, dredging near outer end of north piers 
Mar. 2, 1945 
Dec. 17, 1970 
Sec. 201 
Oct. 27, 1965 
Nov. 17, 1986 
Nov. 17, 1986 
and enlarging inner basin. 
Dredge an entrance channel to existing project dimensions from outer end 
of north pier to project depth in lake, and dredge an anchorage area in 
southwest corner of inner basin to existing project depth. Abandonment of 
dredging triangular area in southwest corner of inner basin to 18 feet deep. 
Provides for deepening the existing entrance channel in the outer harbor to 
25 feet and extending to the depth in Lake Michigan, at widths varying 
from 380 feet to 500 feet; deepening the channel between piers to a depth 
to 23 feet at a width of 180 feet, and deepening the inner basin to 23 feet 
and extending its limits approximately 275 feet northward. 
CASINO BEACH, IL 
(See Section 13 of Text) 
Provides for encasing approximately 1,800 feet of the existing 
Casino Beach jetty in steel sheet piling and a concrete cap, and 
replacing beach fill. 
ILLINOIS BEACH STATE PARK, IL 
(See Section 14 of Text) 
Provides for 46 offshore breakwaters approximately 150 feet long, 
inital beach nourishment of 100,000 cubic yards, and periodic 
nourishment of 100,000 cubic yards at 5-year intervals. 
Annual Report 1880, p. 142 
Annual Report,1882, 
pp. 277, 2162. 
H. Doc. 343, 56th Cong., 
1st Sess. 
Rivers and Harbors Committee 
Doc. 27, 71st Cong., 2d Sess.. 
H. Doc. 116, 77th Cong., 
1st Sess. 
H. Doc. 368, 90th Cong., 
2d Sess. 
Feasibility Report 
dated February 1983. 
Draft Feasibility Report 
dated June 1982. 
IINDIANA DUNES NATIONAL LAKESHORE, 
BEVERLY SHORES, IN 
(See Section 15 of Text) 
Dec. 4, 1981 Provides for emergency shore protection repairs to stone revetment initially Public Law 97-88 
constructed in 1973. 22-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 22-B (Continued) AUTHORIZING LEGISLATION 
Work Authorized Documents 
Jul. 30, 1983 
Nov. 17, 1986 
Nov. 17, 1986 
Nov. 17, 1986 
Nov. 17, 1986 
Nov. 17, 1988 
Nov. 17, 1986 
Dec. 31, 1970 
Nov. 17, 1986 
Provides for operations and maintenance of the shore protection measures. 
INDIANA SHORELINE EROSION, IN 
(See Section 16 of Text) 
Provides for beach nourishment along a two-mile reach of shore west of 
Michigan City Harbor, Indiana. 
LAKE GEORGE, HOBART, IN 
(See Section 20 of Text) 
Provides for removal of silt, aquatic growth and construction of silt traps. 
LITTLE CALUMET RIVER, IN 
(See Section 21 of Text) 
Provides for levee construction, a diversion control structure at the mouth 
of Hart Ditch. Permanent evacuation of a portion of the Black Oak area 
of Gary and non-structural flood proofing measures in Gary. 
LITTLE CALUMET RIVER BASIN, 
CADY MARCH DITCH, IN 
(See Section 22 of Text) 
Provides for widening and deepening 1,250 feet of Cady Marsh Ditch, 
installing 4,880 feet of pipe, and excavating 2,850 feet of open channel. 
McCOOK AND THORNTON RESERVOIRS, IL 
(See Section 23 of Text) 
Provides for construction of two floodwater storage reservoirs in the 
quarries of the same name. 
NORTH BRANCH CHICAGO RIVER, IL 
(See Section 19 and 24 of Text) 
Construction of three reservoirs and reimbursement to locals for 50 percent 
of the costs of Techny and Mid-Fork Reservoirs. 
Clearing fallen trees, roots and other debris and objects which contribute 
flooding. 
O'HARE RESERVOIR, IL 
(See Section 25 of Text) 
Provides for a 1,050 acre-foot excavated reservior. 
Public Law 98-63 
Sec. 501, Water Resources 
Development Act of 1986. 
Sec. 602. Water Resources 
Development Act of 1986. 
Sec. 401. Water Resources 
Development Act of 1986 
Feasibility Report 
dated April 1984. 
Sec. 3 Water Resources 
Development Act of 1988. 
H. Doc. 100-72, 100th Cong. 
1st Sess., Sec. 401, Water 
Resources Development Act 
of 1986. 
River and Harbor Act.(Sec.116) 
Sec. 401, Water Resources 
Development Act of 1986. 
1. Included in Public Works Administrative Program 
September 6, 1943, and Dec. 16, 1933. 
2. Uncompleted portion was deauthorized in 1977 
(dredging in front of U.S. Steel Corp.) 
3. Uncompleted portion was deauthorized in 1977 
(breakwater closure). 
4. Contains latest map of harbor. Uncompleted portion is 
inactive. 
5. Contains latest map of river. 
6. Latest published map is an Annual Report for 1914, 
opposite p. 2928. 
7. Contains latest published map of North Branch 
above North Ave. 
8. Contains latest published map. 
9. Completed under previous project. 
10. Uncompleted portion was deauthorized in 1977 
(widen and deepen Lake George Branch). 
11. Included in Public Works Administration Program Sept. 
6, 1933, and July 25, 1934. Uncompleted portion was 
deauthorized in 1977 (widen and deepen main canal and the 
Calumet River Branch). 
12. Project deauthorized in 1977. 
13. Project deauthorized in 1989. 
22-18 
Acts

CHICAGO, IL, DISTRICT 
TABLE 22-C EXISTING NAVIGATION PROJECTS 
See 
Section Length Width Depth 
in Text Project Item (feet) (feet) (feet) 
1. Burns Waterway 
Harbor, IN 
2. Burns Waterway 
SBH, IN 
3. Calumet Harbor 
and River, IL 
and IN 
4. Chicago Harbor, 
IL 
5. Chicago River, 
IL 
6. Indiana Harbor, 
IN 
7. Michigan City 
Harbor, IN 
8. Waukegan Harbor, 
IL 
North Breakwater 
West Breakwater 
Approach Channel 
Outer Harbor 
East Harbor Arm 
West Harbor Arm 
North Breakwater 
West Breakwater 
Approach Channel 
Burns Waterway 
Northerly Crib Breakwater 
Southerly Steel Breakwater 
North Pier 
Chicago Confined Disposal Facility 
Approach Channel 
Outer Harbor 
River Entrance 
Elgin, Joliet & Eastern Railway Bridge 
to turning basin No. 3 
Turning Basin No. 3 to Turning Basin No. 5 
Approach into Lake Calumet 
Extension in Lake Calumet 
Turning Basins 1, 3, and 5 
Shore arm extension 
Exterior breakwater 
Exterior breakwater southerly ext. 
North inner breakwater 
South inner breakwater 
North Pier 
Approach Channel 
Channel and maneuver 
Lock 
Inner Basin 
Entrance Channel 
Main Branch of Chicago River 
North Branch of Chicago River 
North Branch Canal 
North Branch Turning Basin 
Northerly Breakwater 
Easterly Breakwater 
Approach Channel 
Outer Harbor 
Entrance Channel 
Main Channel 
Turning Basin 
Lake George Branch 
Calumet River Branch 
Detached Breakwater 
West Pier 
East Pier 
East Breakwater 
Entrance Channel 
Main Channel 
Outer Basin 
Trail Creek 
Trail Creek 
North Breakwater and Shore Connection 
North Pier and North Revetment 
South Pier 
Entrance Channel 
Channel to Inner Basin 
Inner Basin 
Anchorage Area 
1Area of about 6 acres. 
22-19 
4,630 
1,200 
2,200 
3,700 
2,100 
3,800 
678 
1,043 
1,200 
5,593 
400 
Varies 
620 
620 
200 
100 
7
0
0 3,200 
3 2,000 
290 
0 200 
and variable 
Variable 
3 400 
3 1,000 
30 
28 
27 
27 
11
9 
29 
28 
27 
27 
earth 
28 
rock 
27 
27 
27 
27 
6,719 
5,007 
2,45C 
2,97 
9,70( 
10,500 
3,000 
21,10( 
8,000 
4,000 
3,000 
29 
28 
23 
21 
21 
21 
21 
21 
21 
29 
28 
27 
22 
22 
22 
22 
2,250 
5,421 
4,944 
4,034 
2,544 
960 
6,600 
2,200 
600 
1,270 
7,300 
3,800 
11,100 
5,500 
1,120 
2,525 
7,200 
4,200 
3,600 
7,400 
3,700 
2,500 
1,304 
835 
1,276 
1,000 
1,900 
2,400 
900 
3,000 
2,300 
1,896 
2,074 
3,111 
3,250 
1,700 
1,650 
1 
800 
1,300 
80 
740 
190-470 
190-390 
91-390 
56-210 
800 
Varies 
65-280 
61-210 
64-160 
160-260 
150-425 
120-150 
900 
50-100 
50 
390 
200 
375-500
1 
18 
18 
8-12
86 
22 
18 
18
8

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 22-D OTHER AUTHORIZED BRIDGE ALTERATION 
(See Section 11 of Text) 
Cost to Septmber 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Calumet River Bridges' 1967 $ 1,625,068 
1Transferred to Department of Transportation in accordance with Section 6(g) of the Act of October 16, 1966, 
P.L. 89-670 
TABLE 22-E OTHER AUTHORIZED BEACH EROSION PROJECTS 
Cost to Septmber 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Mt. Baldy, Indiana Dunes National 
Lakeshore, IN 1984 $1,500,000 
Hollywood-Ardmore Beach, Chicago, IL 1982 237,271 
Evanston, IL 1979 766,052 
Lake Michigan-Lake Bluff, IL 1976 244,889 
Lake Michigan-Lake Forest, IL' 1975 65,611 
Illinois Shore of Lake Michigan, Kenilworth, IL2 1975 5,200 
'Authorized by River and Harbor Act of 1954. 
2Uncompleted portion deauthorized in 1977. 
TABLE 22-F OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Cost to Septmber 30, 1992 
For Last 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Lake Michigan, Edgewater/Rogers Park 
Communities, Chicago, IL 1989 $2,062,347 
Little Calumet River, IL 1984 583,000 
22-20

CHICAGO, IL, DISTRICT 
TABLE 22-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Report For Deauthorized Expended Expended 
Calumet Harbor and River, IL and IN 
Widening and straightening the Calumet 
River in the vicinity of 106th Street 
and closing the gap between breakwaters, 
and dredging minor shoals in the outer 
harbor. 1990 Jan. 1, 1990 
Illinois Shore of Lake Michigan, Winnetka, IL 1975 1977 
Illinois Shore of Lake Michigan, Chicago, IL 1975 1977 
Kankakee River, IL and IN 
Levee between Shelby Bridge and 
Baum's Bridge in IN 1938 Nov. 17, 1986 
Little Calumet River, IL and IN 
Little Calumet River and Tributaries, 
IL and IN 1968 Nov. 17, 1986 53,136 
Wilmington Ice Control Demonstration Nov. 18, 1991 
22-21

ROCK ISLAND, IL, DISTRICT* 
This district comprises most of the northern half of 
Illinois, portions of southern Wisconsin, southern and 
southwestern Minnesota, eastern and central Iowa, and 
northeastern Missouri, embraced in drainage basin of 
Mississippi River and its eastern and western tributaries 
between mile 300 (above mouth of Ohio River) and 614, and 
of its eastern tributaries only, between Hamburg Bay, at 
mile 261 and 300. This district also includes the Illinois 
Waterway above mile 80 with its tributaries and drainage 
basins. The section of the Mississippi River between river 
miles 300 and 614 is included in the report on Mississippi 
River between Missouri River and Minneapolis, MN. 
IMPROVEMENTS 
Navigation Page 
1. Illinois and Mississippi Canal, IL..............23-2 
2. Illinois Waterway, IL and IN.................. 23-2 
3. Mississippi River between Missouri River 
and Minneapolis, MN.......................23-3 
4. Upper Mississippi River - Illinois 
Navigation Study............................ 23-3 
5. Upper Mississippi River System Environmental 
Management Program (UMRS-EMP), 
IL, IA, MN, MO, WI.......................23-3 
6. Other Authorized Navigation Projects......... 23-4 
Flood Control 
7. Coralville Lake, IA...........................23-4 
8. Des Moines Recreational River and 
Greenbelt, IA . ........... ................. 23-4 
9. Farm Creek, IL ............... ............... 23-4 
10. Hannibal, M O ............................... 23-4 
11. Loves Park, IL .............................. 23-5 
12. Red Rock Dam and Lake Red Rock, IA....... 23-5 
13. Saylorville Lake, IA ....................... 23-5 
14. West Des Moines, IA.....................23-6 
15 Inspection of Completed Flood 
Control Projects.............................23-6 
16. Other Authorized Flood Control Projects ....... 23-6 
17. Flood Control Work Under Special 
Authorization............................23-6 
General Investigations 
18. Surveys................... .................. 23-6 
19. Collection and Study of Basic Data........... 23-6 
20. Preconstruction Engineering and Design....... 23-6 
Tables Page 
Table 23-A Cost and Financial Statement......... 23-7 
Table 23-B Authorizing Legislation...............23-8 
Table 23-C Other Authorized Navigation 
Projects ........................... 23-11 
Table 23-D Not Applicable 
Table 23-E Other Authorized Flood 
Control Projects.................... 23-11 
Table 23-F Not Applicable 
Table 23-G Deauthorized Projects..............23-13 
Table 23-H Inspection of Completed Flood 
Control Projects ................... 23-14 
Table 23-I Flood Control Work Under Special 
Authorization .................... . 23-15 
Table 23-J Illinois Waterway: Existing 
Locks and D4ms.................... 23-17 
Table 23-K Illinois Waterway: Lock and Dam 
Construction, Foundations, Cost..... 23-17 
Table 23-L Illinois Waterway: Additional 
Features Entering into Cost.......... 23-18 
Table 23-M Illinois Waterway: Existing Project... 23-19 
Table 23-N Illinois Waterway: Total Cost of 
Existing Project...................23-20 
23-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. ILLINOIS AND MISSISSIPPI 
CANAL, IL 
Location. T[his canal extends for 75 miles from the Illinois 
River near LaSalle, IL, to the Mississippi River at Rock 
Island, IL. A feeder canal, 29 miles in length, extends from 
the summit level of the canal to the Rock River at Rock Falls, 
IL.
Existing project. See pages 1306-1308 of Annual Report 
for 1962 for details regarding project. The canal was constructed 
in the period 1892-1918. The canal has not been 
operated for navigation since June 1951 in accordance with 
Corps policy to discontinue operation of waterways affording 
little or no benefit to navigation. The River and Harbor 
Act of 1958 authorized the appropriation of $2,000,000 for 
the purpose of placing the canal in proper condition for public 
recreational use and to convey and transfer the canal to the 
State of Illinois as part of the State park system. 
The repair and modification program was initiated in 1961, 
and a number of canal features have been repaired or 
modified. In connection with this program, fee title to 1,062 
acres and recreational flowage easements over 309 acres of 
land in Rock River at Rock Falls, formerly under navigation 
flowage easement, have been acquired. The State of Illinois 
accepted title to the canal as of August 1, 1970. The River 
and Harbor Act of 1970 authorized the additional appropriation 
of $6,528,000 to be expended for the repair, modification, 
and maintenance of bridges, title transfer, modification 
or rehabilitation of hydraulic structures, fencing, clearing auxiliary 
ditches, and for the repair and modification of other 
canal property appurtenances. 
The repair and modification work was underway until a 
suit was filed by three Illinois counties and their Commissioners 
of Highway against the Federal Government and the 
State in 1974 over maintenance of highway bridges crossing 
the canal. After the lawsuit was filed, further rehabilitation 
work by the Federal Government on the canal was suspended. 
On November 4, 1981, the Corp of Engineers deposited 
$3,722,572 with the Clerk of the U.S. District Court in 
Chicago in full satisfaction of the Court's judgment. These 
funds were used by the counties to complete bridge rehabilitation 
work as directed in the court order. Rehabilitation work 
by the Federal Government in coordination with the state was 
resumed in 1984 with the remaining authorization expended 
in 1987. 
The Water Resources Development Act of 1986 authorized 
an additional appropriation of $8,472,000 to accomplish 
the work described in the 1970 River and Harbor Act. 
The State of Illinois filed an additional lawsuit against the 
United States on July 6, 1987 in the U.S. Claims Court in 
the amount of $8,472,572. In a preliminary decision on 
September 22, 1988, the court dismissed the claim for 
$3,722,572. A settlement agreement between the State of Illinois 
and the United States was signed on November 14, 1991. 
The agreement provided that Illinois release all claims against 
the United States as stipulated in the claims court and that 
the United States provide $4,750,000 to Illinois as reimbursement 
for previous repair work performed upon the canal 
bridges by Illinois. On December 16, 1991, the U. S. Claims 
Court entered a judgment for $4,750,000 in favor of the State 
of Illinois. This judgment was paid in FY92. 
Once funds are received, principal work features to restore 
the canal to acceptable conditions consist of the repair or 
resonstruction of retaining walls, embankmenets, protions of 
the lock and dam structures, culverts, drainage ditches, and 
other related work features which the United States has maintained 
or has been obligated to maintain under previous 
agreements. These features are consistent with a Master 
Management Plan prepared by the Illinois Department of 
Conservation. NEPA documentation to assess remaining 
work items must be completed prior to initiation of 
construction. 
Local cooperation. A revised Supplemental Agreement with 
all work items remaining will be coordinated in FY 93. Additional 
funding is needed prior to the District continuing 
design and construction on the canal. 
Operations during fiscal year. Engineering and Design work 
was performed and the court claim for a total cost of 
$2,979,556. 
2. ILLINOIS WATERWAY, IL AND IN 
Location. Illinois River (entirely within State of Illinois), 
formed by confluence of Kankakee and Des Plaines River, 
flows southwesterly and enters Mississippi at Grafton, IL, 
about 38 miles above St. Louis. Illinois Waterway comprises 
Illinois River from its mouth to confluence of Kankakee and 
Des Plaines Rivers (273 miles), Des Plaines River to Lockport 
(18.1 miles) and Chicago Sanitary and Ship Canal and South 
Branch of Chicago River to Lake Street, Chicago (34.5 miles). 
Also from a point 12.4 miles above Lockport, II, waterway 
comprises Calumet-Sag Channel and Little Calumet and 
Calumet Rivers to turning basin 5, near entrance to Lake 
Calumet (23.8 miles); and Grand Calumet River from junction 
to 141st Street, deep (lake) draft navigation (9 miles) and 
to Clark Street, Gary, IN (4.2 miles). 
Previous projects. For details, see page 1945 of Annual 
Report for 1915 and page 1172 of Annual Report for 1932. 
Existing project. See table 23-K and page 1255 of Annual 
Report for 1963. Cost of new work was $124,041,436 and includes 
$445,000 for Recreation Facilities under Code 711. 
Calumet-Sag Modification, Part III, placed in the deferredfor-
restudy category in March 1972, cost of $33,000,000 (July 
1971) Federal and $20,700,000 (July 1971) non Federal; is excluded 
from present cost estimate. See Table 23-B for 
authorizing legislation. 
(See Table 23-J through 23-N on existing locks and dams; 
lock and dam construction, foundations, cost; additional 
features entering into cost of project; existing project and total 
cost of existing project.) 
Local cooperation. Complied with for completed modifications 
and Part I of Calumet-Sag Modification. 
All pools above Alton Pool: 
Maintenance: Channel dredging by the contract cutterhead 
pipeline dredge was performed in the Starved Rock, Peoria 
and LaGrange pools at various locations at a cost of 
23-2

ROCK ISLAND, IL, DISTRICT* 
$1,689,800, with a total of 297,561 cubic yards of material 
being removed. Dredging inspection and reports were completed 
at a cost of $231,000. Strike removal and snagging and 
clearing was accomplished in various locations by hired labor 
at a cost of $401,800. Maintenance of the Lucas-Berg Disposal 
Facility cost $4,800. Lucas-Berg mitigation costs were 
$373,100. Structural repairs to locks and dams were performed 
by hired labor at a cost of $2,024,600. Repairs to Lockport 
Approach Dike were continued at a cost of $435,600. Construction 
of protection cells above Marseilles Dam was completed 
at a cost of $225,900. Construction of stairway access 
to tainter gate at Peoria and La Grange were completed at 
a cost of $3,300. Replacement of tow haulage units were initiated 
at a cost of $395,900. Dredged material disposal activities 
and other environmental concerns in connection with 
dredging cost $53,800. Real Estate support of maintenance 
activities cost $28,000. Installation of fuel tanks at locks and 
dams was continued at a cost of $31,000. Construction of 
LaGrange maintenance building was completed at a cost of 
$114,300. Buildings, grounds, and utility maintenance at the 
locks and dams and Illinois Waterway Project Office at Peoria 
totaled $11,200. Permanent operating equipment costs were 
$115,300. Engineering and design work cost $533,800, and 
supervision, administration, and inspection for the 
maintenance features totaled $367,900. Total maintenance 
costs were $7,041,100. Net credits to the project were $16,800. 
Operation and Care: Operation of the locks and dams and 
routine maintenance and minor repairs thereto were made at 
a cost of $6,973,400. Illinois Waterway Project Office at 
Peoria was continued at a cost of $648,700. Real Estate 
management services were provided at a cost of $53,700. 
Visitor's Center at Starved Rock Lock and Dam was operated 
at a cost of $187,500. OSHA inspections and medical examinations 
were accomplished at a cost of $15,700. Surveys, 
studies, and other inspections were performed at a cost of 
$856,300; natural and cultural resource costs were $52,000; 
and water control management costs were $688,800. Supervision 
and administration for the operation features totaled 
$249,600. Total operation costs were $9,725,700. 
Total operation and maintenance costs were $16,766,800 
for all pools above Alton Pool. 
Rehabilitation: Rehabilitation work at LaGrange, Peoria, 
Marseilles, and Brandon Road Locks and Dams was continued. 
Costs at LaGrange were $50,469; Peoria $35,959; 
Marseilles, $15,817; and Brandon Road, $4,189; for a total 
of $106,434. 
Alton Pool Operation: Costs for the year were $33,121 for 
natural resource management; $699 for recreation management; 
$126,285 for condition and operation studies; $94,247 
for water control management, and $68,771 for supervision 
and administration. 
Alton Pool Maintenance: Costs for the year were $151,352 
for dredging and $10,668 for supervision and administration. 
Total cost for work in the Alton Pool was $485,143. 
Total operation and maintenance costs for all pools above 
Alton Pool were $16,766,800. Rehabilitation costs were 
$106,434. Alton Pool operation and maintenance costs were 
$485,143. Total cost incurred $17,358,377. 
3. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement, see chapter on "Mississippi 
River between Missouri River and Minneapolis, MN." 
4. UPPER MISSISSIPPI - ILLINOIS 
NAVIGATION STUDY 
Location. The study includes both the Upper Mississippi 
River and the Illinois Waterway. The study area covers over 
600 miles of navigable waterways and 29 locks and dams of 
the Upper Mississippi River from the headwaters at St. Anthony 
Falls near Minneapolis-St. Paul, Minnesota; 
downstream to just above Melvin Price Lock and Dam at 
Alton, Illinois; and the Illinois Waterway (eight locks and 
dams) from Lake Michigan in Chicago, Illinois, southwest 
to where the waterway joins with the Mississippi River at 
Grafton, Illinois, 327 miles long. The Upper Mississippi River 
system meanders through the states of Minnesota, Wisconsin, 
Iowa, Illinois, and Missouri, and over 40 counties. The 
Illinois Waterway is located entirely within the State of Illinois. 
Existing project. The project consists of investigating problems 
associated with navigation on the river system. Undertaken 
by three Corps Districts (St. Paul, Rock Island, and 
St. Louis), the purpose of the study is to examine information 
related to the existing condition of the structures and investigate 
system congestion (lockage delalys, inadequate 
capacity, and recreation/commercial locking conflicts). The 
review of this completed project is authorized by Section 216, 
Flood Control Act of 1970, PL 91-611. 
Local cooperation. None required. 
Operations during fiscal year. The initial Project Management 
Plan which details the scope of the feasibility study was 
revised. Total costs incurred were $1,596,549. 
5. UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM (UMRS-EMP), 
IL, IA, MN, MO, WI 
Location. The Program is authorized for those river reaches 
having commercial navigation channels on the Upper 
Mississippi River, Illinois River, Minnesota River, St. Croix 
River, and Kaskaskia River in the states of Illinois, Iowa, Minnesota, 
Millouri, and Wisconsin. 
Existing project. The purpose of the UMRS-EMP as stated 
in the authorizing legislation is to ensure the coordinated 
development and enhancement of the Upper Mississippi River 
system, recognizing its several purposes. The program includes 
habitat rehabilitation and enhancement projects to 
counteract the effects of backwater sedimentation. Long Term 
Resource Monitoring will provide the means.for more informed 
management of the UMRS. Also authorized are a study 
of the economic impacts of recreation, navigation traffic 
23-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
monitoring, and recreation projects (currently unfunded). The 
program was initiated in 1986 utilizing funds provided by PL 
99-88, FY 1985 Supplemental Appropriation Act. PL 99-662, 
Water Resources Development Act of 1986, further defined 
the program and provided for a 10 year implementation 
period. The implementation period was extended to 15 years 
by PL 101-640, Water Resources Development Act of 1990. 
Local Cooperation: Local cooperation agreements are obtained 
for habitat projects for such projects not located on 
lands managed as a national wildlife refuge, within the meaning 
of Section 906(e) of the 1986 WRDA. 
Operations During Fiscal Year. Costs during the year totaled 
$15,476,800. The majority of funds was expended on two 
program elements: habitat projects and long term resource 
monitoring. Design was initiated on five projects and continued 
on 21; construction was initiated on four projects, continued 
on five, and completed on two projects. Construction 
has been completed on a total of nine projects since the program 
was initiated. Funds were also used for economic impacts 
of recreation study and continuing coordination of the 
General Plan for the UMRS-EMP. 
6. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
See Table 23-C 
Flood Control 
7. CORALVILLE LAKE, IA 
Location. Coralville Lake is formed by the Coralville Dam 
on the Iowa River, several miles upstream from Iowa City, 
Johnson County, IA, about 83 miles above the confluence 
of the Iowa River with the Mississippi River. 
Existing project. See page 28-4, Annual Report for 1981, 
for project details. Construction began in July 1949 and the 
project has. been in operation since February 1958. About 
24,406 acres of land were acquired in fee and flowage 
easements obtained for 24,427 acres. The project was 
modified to provide for construction of a highway bridge 
crossing the lake at the Mehaffey site, which was begun in 
June 1964 and completed in October 1966. See Table 23-B 
for authorizing legislation. 
Local cooperation. None required, except in connection 
with the Mehaffey Bridge which has been fully complied with. 
Operations during fiscal year. New work: Additional land 
acquisition to provide for the present plan of reservoir operation 
performed at a cost of $5,293. Operation and 
Maintenance: Routine maintenance activities continued at a 
-cost of $2,665,670. Reservoir maintenance and operation cost 
$73,200. Expenditures from return of recreation use fees were 
$189,195. 
8. DES MOINES RECREATIONAL 
RIVER AND GREENBELT, IA 
Location. The greenbelt area is located along both banks 
of the Des Moines River in central IA and extends from a 
point at which relocated U.S. Highway 92 crosses the Des 
Moines River near Harvey, upstream approximately 169 river" 
miles to U.S. Highway 20 at Fort Dodge, IA. It includes the 
Corps' operated Lake Red Rock and Sayorville Lake projects. 
Existing project. The project will include, but not be limited 
to: (1) the construction, operation, and maintenance of recreational 
facilities and streambank stabilization structures; (2) 
maintenance of all structures constructed before the date of 
authorization of this project (other than any such structure 
operated and maintained by any person under a permit or 
agreement with the Secretary); (3) such tree plantings, trails, 
vegetation, and wildlife protection and development for 
recreational purposes; and (4) the prohibition or limitation 
by the Secretary of the killing, wounding, or capturing at any 
time of any wild bird or animal in such areas as may be 
directed by the Secretary. In carrying out the project the 
Secretary may acquire by purchase, donation, exchange, or 
otherwise, land and interests therein, as the Secretary determines 
are necessary to complete the project. 
The authorization requires that an Advisory Committee be 
established for consultation with the Department of the 
Army consisting of 47 members: three Corps of Engineers 
appointees, one person from the city of Des Moines, and one 
from each other incorporated municipality within the 
greenbelt, two from each of the nine counties in the greenbelt, 
and five from the State of Iowa. See Table 23-B for authorizing 
legislation. 
Local Cooperation. Letters of assurance have been received 
for nine separable elements. Local cooperation Agreements 
have been executed for four separable elements. 
Operations during fiscal year. Coordination was maintained 
with the Advisory Committee in accordance with Public Law 
99-88. Construction of Red Rock Trails Segment I and 
Lutheran Hospital Trail Improvements were completed. Construction 
continued on the Red Rock Trails Segment IIA. A 
construction contract was awarded for Red Rock Trails Segment 
IIB. Work continued on the Feature Design Memoranda 
for Dragoon Trail Scenic Road Route, Red Rock Trails 
Segment III, Downtown Riverfront Plaza/Amphitheater, Red 
Rock Trails Segment IV, Botanical Center Park; Johnston 
Trails/Access and the Raccoon River Regional Park. Costs 
incurred were $1,533,701. 
9. FARM CREEK, IL 
Location. Farm Creek watershed in Tazewell County, IL, 
is 60 square miles in extent. Stream empties into Illinois 
Waterway at mile 162 above mouth. 
Existing project. See page 28-5, Annual Report for 1983 
for description of project. See Table 23-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance: Routine 
maintenance activities were continued at a cost of $218,992. 
10. HANNIBAL, MO 
Existing project. The project provides a 500-year level of 
23-4

ROCK ISLAND, IL, DISTRICT 
protection for Hannibal by construction of levees and floodwalls 
along Front and Collier Street. The project is approximately 
0.7 of a mile long with an average levee height of 12.5 
feet. Concrete floodwalls are being used in confined areas. 
There are four street closure structures and six gatewells. Provisions 
for interior drainage includes a new 3,000 foot interceptor 
sewer, together with a 1.0 acre ponding area and 
a 40,000 GPM station. The area to be protected includes 19 
blocks of the city's downtown area, including the historic 
Mark Twain District. The estimated cost is $7,997,000 which 
includes $1,999,000 non-federal costs. See Table 23-B for 
authorizing legislation. 
Local cooperation. Local cooperation agreement for the 
project was executed on December 27, 1988. 
Operations during fiscal year. Work was essentially completed 
on Stages I, IA, and the Archaeological Mitigation contract. 
Work was initiated on the Stage II Beautificataion contract. 
Costs incurred were $2,136,298. 
11. LOVES PARK, IL 
Location. The Loves Park project is located in Winnebago 
County, IL on the northeast boundary of the city of 
Rockford, IL. Loves Park is 17 miles south of the Illinois- 
Wisconsin state line. 
Existing project. The project provides 100-year level of protection 
against flooding along Loves Park Creek. Protection 
measures consist of 17,900 feet of channel improvements, a 
16,300 GPM pump plant, and ponding. The estimated project 
cost is $30,500,000 including $8,900,000 non-federal 
costs. See Table 23-B for authorizing legislation. 
Local cooperation: The local cooperation agreement was 
executed on March 26, 1991. 
Operation during fiscal year. Planning, Engineering and 
Design were completed at a cost of $419,561. A construction 
contract for Stage IIA was awarded in September 1992 at a 
cost of $1,048. Total costs incurred were $420,609. 
12. RED ROCK DAM AND LAKE RED 
ROCK, IA 
Location. The site of this project is on the Des Moines 
River, chiefly in Marion County, but extending into Jasper, 
Warren, and Polk Counties. The dam is 142.9 miles above 
the mouth of the Des Moines River, which empties into the 
Mississippi River at mile 361.4 above the mouth of the Ohio 
River. The city of Des Moines lies northwesterly from the site, 
about 60 miles upstream. 
Existing project. See page 28-6, Annual Report for 1981 
for description of the project. Construction began in May 
1960, and the dam was placed in beneficial use for storage 
of flood water in January 1969. Land acquired for the project 
consisted of 49,152 acres in fee and 27,880 acres in 
flowage easement. Landowner complaints, that lake operation 
have flooded their lands more frequently than what they 
were told to expect when flowage easements were initially acquired, 
led Congress to modify the project authorization. 
Language in PL 99-190 authorizes acquisition from willing 
sellers fee simple title in real property, which is subject to 
periodic flooding in connection with the operation of the project. 
Potentially there are approximately 1,000 tracts consisting 
of about 30,000 acres. Estimated Federal cost is 
$42,000,000. See Table 23-B for authorizing legislation. 
Local Cooperation. None required. 
Operations during fiscal year. New Work: Land Acquisition 
costs were $698,111. The REDM 5AA was approved July 
1992. REDM 5BB will be forwarded for approval in 
November 1992. Operation and maintenance activities were 
continued at a cost $3,388,964. Flood control reservoir 
maintenance and operation cost $73,200. Expenditures from 
the return of recreation use fees were $215,530. 
13. SAYLORVILLE LAKE, IA 
Location. The project site is chiefly in Polk County, IA, 
but portions extend into Dallas and Boone Counties. The dam 
is about 213.7 miles above the mouth of the Des Moines River 
and about 5 miles upstream from the city of Des Moines, IA. 
Existing project. The dam is an earth embankment 6,750 
feet long at crest with a height of 120 feet. Outlet works are 
a single circular concrete conduit, 22 feet in diameter, located 
at eht toe of the west bluff. Control structure is at upstream 
end of conduit and huses three gates. A stilling basin is probided 
to dissipate energy of discharge from outlet conduit. 
Spillway is in west bluff, weir 430 feet long. Water flowing 
over the spillway weir discharges into a paved chute aand 
thence into an excavated earth channel to the Des Moines 
River. Top of spillway is about 31 feet below top of earth 
embankment secton, and flow over weir is uncontrolled when 
water in reservoir reaches its cres. Watershed area above dam 
site is 5,823 square miles. With pool at spillway crest elevation, 
lake area is 16,700 acres and contains about 676,000 
acre-feet of water at that height (602,000 for flood control 
and 74,000 for a conservation pool to maintain minimum 
flows at sownstream points). Lake supplements capacity of 
downstream Lake Red Tock at river mile 142.9. The two lakes 
provide a high degree of flood protection to the lower Des- 
Moines River Valley. Reaches along the Mississippi Tiver 
downstream from the mouth of the Des Moines River are also 
benefited. 
A project modification plan to minimize the adverse environmental 
effects at Ledges State Park, located upstream 
from the dam, was authorized in 1976. The project modification 
included relocation of affected park facilities, acquisition 
of additional park land, and the development of a floodway 
corridor, with recreational facilities, from the dam 
downstream to Sixth Avenue in Des Moines. Improvements 
to Highway 415, the main accrss road to existing facilities on 
the east side of the reservoir, were added to the project by 
Congress in 1984. Segments A and B of Highway 415 have 
been completed. Segment C of Highway 415 is scheduled to 
be completed in 1993. 
Construction began in June 1965, and the dam was placed 
in operation for the storage of flood water in April 1977. 
Remedial work in Big Creek Valley, consisting of diversion 
dam and channel and a barrier dam, for the protection of 
the town of Polk City was completed in December 1974. The 
23-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
land acquisition program involved 26,624 acres acquired in 
fee and flowage easements for 1,950 acres. The estimated project 
cost is $116,470,000 including $2,820,000 in non-Federal 
costs from the State of Iowa and the City of Des Moines, 
for recreational development. See Table 23-B for authorizing 
legislation. 
Local cooperation. Fully complied with. 
Operations during fiscal year. New work: The principal 
work item was the continuation of construction (Stages I, II, 
and III) and continued real estate acquisition for Segment C 
of Highway 415. Costs incurred were $6,866,504. Operation 
and Maintenance activities were continued at a cost of 
$3,458,691. Reservoir maintenance and operation cost 
$73,200. Expenditures from return of recreation use fees were 
$116,676. The project is about 97 percent completed, excluding 
deferred work. 
14. WEST DES MOINES, IA 
Location. The city is located in Polk County in central 
Iowa. 
Existing project. The project will provide flood protection 
from the Raccoon River, Jordan Creek, and Walnut Creek 
for 927 urban acres. The project will consist of three stages: 
Stage I - 3,100 feet of levees and floodwalls; Stage II - 9,000 
feet of levees with a pump station; and Stage III - 10,300 feet 
of levees and floodwalls with a pump station. See Table 23-B 
for authorizing legislation. 
Local cooperation. The local cooperation agreement was 
signed August 27, 1992. 
Operations during fiscal year. Planning and Engineering 
were completed at a cost of $71,422. Plans and specifications 
for Stage II was initiated at a cost of $244,051. Total costs 
incurred were $315,473. 
15. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Federal flood control regulations (part 208 of title 33, Code 
of Federal Regulations) provide that the structures and 
facilities constructed by the United States for local flood protection 
shall be continuously maintained in such a manner 
and operated at such times and for such periods as may be 
necessary to obtain the maximum benefits. Costs during the 
period for inspections of projects turned over to local interests 
to ascertain compliance with Federal requirements were 
$195,900. (See Table 23-H for list of completed flood control 
projects inspected.) 
17. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control Activities, Section 205, Public Law 84-685. 
See Table 23-I 
Snagging and Clearing of Navigable Streams and 
Tributaries in Interest of Flood Control, Section 208, Public 
Law 83-780. See Table 23-I. 
Emergency Bank Protection (Section 14 of the 1946 Flood 
Control Act, Public Law 526.) See Table 23-I. 
Emergency Flood Control Activities, Public Law 99, 84th 
Congress. See Table 23-I. 
General Investigations 
18. SURVEYS 
There were two flood prevention studies (Black Hawk 
County, IA; Wyaconda River Basin, MO and IA) in progress 
during FY 92 at a cost of $48,025. Special Investigations, 
FERC, Dam Safety Criteria Studies, North American Water 
Fowl Management, SCS Coordination and Planning 
Assistance to States efforts totaled $161,629. Total cost of 
surveys was $209,654. 
19. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management services cost $180,183. Sedimentation 
and streamgaging studies were completed during FY 
92 at a cost of $6,772. Total cost for collection and study of 
basic data was $186,995. 
20. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
Located in Muscatine and Louisa Counties, the Muscatine 
Island Levee District and the Muscatine-Louisa County 
Drainage District No. 13, together with the city of Muscatine, 
Iowa form a joint drainage and flood protection area for 
30,700 acres of bottom land. The project was authorized by 
the Water Resources Development Act of 1986 subject to a 
favorable Chief's Report and approval by the Secretary of 
the Army. The project will provide flood protection by increasing 
the height of the existing main stem levee and flank 
levee. Work continued with the approval of the General 
Design Memorandum in FY 92 at a cost of $69,159. See Table 
23-B for authorizing legislation. 
Total cost for preconstruction engineering and design was 
$69,159. 
16. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 23-E. 
23-6

ROCK ISLAND, IL, DISTRICT 
TABLE 23-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project 
1. Illinois and 
Mississippi Canal, 
IL 
2. Illinois Waterway 
IL and IN 
4. Upper Mississippi 
-Illinois Navigation 
Study 
5. Upper Mississippi 
River System Environmental 
Management 
Program, IL, IA, MN, 
MO, WI 
7. Coralville Lake, IA 
8. Des Moines 
Recreational River 
and Greenbelt, IA 
9. Farm Creek, IL 
10. Hannibal, MO 
11. Loves Park, IL 
12. Red Rock Dam and 
Lake Red Rock, IA 
13. Saylorville Lake 
IA 
Funding 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Contributed Funds: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Contributed Funds: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Contributed Funds: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Contributed Funds: 
Approp. 
Cost 
FY 89 FY 90 FY 91 FY 92 September 1992 
115,000 
105,286 
12,730,200 
13,238,903 
10,865,000 
11,457,670 
7,364,000 
6,300,372 
100,000 
180,546 
2,774,000 
2,990,552 
480,000 
371,106 
145,984 
4,916 
115,600 
148,814 
395,000 
303,889 
193,000 
227,046 
1,057,000 
227,006 
2,531,000 
2,475,492 
1,522,000 
1,448,816 
4,568,800 
4,594,994 
168,033 
44,640 
- 3,000,000 
7,884 2,979,556 
16,760,000 17,226,000 
16,453,396 16,749,997 
272,000 (30,000) 
291,441 106,434 
939,000 1,962,000 
966,028 1,596,549 
15,177,000 13,672,000 
12,685,543 15,476,800 
153,880 
143,763 
14,531,426 
14,432,494 
3,758,100 
3,702,453 
976,000 
849,217 
14,860,000 
15,706,110 
110,000 
173,944 
2,210,047 
1,968,063 
1,802,000 
674,166 
45,365 
150,097 
139,209 
130,849 
1,152,000 
862,427 
198,000 
149,336 
296,000 
306,481 
418,180 
2,234,542 
2,326,831 
850,000 
1,588,884 
2,987,976 
3,209,190 
168,033 
173,253 
5,293 
2,727,600 
2,665,670 
750,000 
1,533,701 
20,025 
148,364 
214,000 
218,992 
1,915,000 
2,136,298 
15,000 
128,499 
370,307 
420,609 
698,111 
3,527,800 
3,388,964 
19,850 
18,422 
900,000 
6,866,504 
3,580,800 
3,458,691 
168,033 
39,426 
28,395 
2,305,000 
2,497,808 
550,000 
841,766 
137,342 
26,619 
252,000 
233,382 
1,318,000 
1,344,286 
335,000 
253,741 
319,000 
289,510 
2,189,000 
240,758 
3,097,000 
2,948,753 
11,968,000 
2,794,528 
3,187,000 
3,121,475 
169,269 
46,231 
23-7 
7,605,143' 
7,605,143 
21,202,248- 
21,163,805' 
126,707,751 
126,706,419 
315,425,573� 
311,712,038 
138,239,925 
136,989,696 
3,877,000 
3,411,794 
59,511,000 
56,830,586 
30,179,488 
30,171,153 
38,075,674 
35,911,616 
4,446,000 
4,188,623 
384,766 
364,614 
9,859,0206 
9,859,020 
3,633,541 
3,503,305 
5,692,993 
5,559,693 
548,000 
531,576 
2,394,307 
2,371,779 
99,049,484 
96,978,105 
41,523,687 
38,875,175 
19,850 
18,422 
127,527,887 
123,643,061' 
44,052,441 
40,780,268 
3,258,141 
2,666,164
1
I

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 23-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 September 1992 
14. West Des Moines, IA New Work: 
Approp. 250,000 376,000 249,000 286,000 1,486,000 
Cost 273,269 417,041 190,610 315,473 1,444,051 
20. Muscatine Island, IA New Work: 
Approp. 150,000 72,000 - 55,000 602,000 
Cost 68,127 148,264 51,923 69,159 601,813 
1. Includes $25,000 Emergency Relief Funds. 5. Includes cost of Mehaffey Bridge, $1,365,074 (excluding $100,000 con- 
2. Includes $4,143,282 for Operating and Care under the "Permanent tributed funds). 
Indefinite Appropriation." 6. Excludes $161,813 contributed funds. 
3. Includes $2,569,102 for previous projects. 7. Excludes $950,000 non-Federal cost. 
4. Includes $1,028,468 for previous projects. 
TABLE 23-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. January 21, 1927 
July 3, 1930 
June 26, 1934' 
August 30, 1935 
August 30, 19353 
June 14, 1937 
June 20, 1938 
October 23, 1943 
March 2, 1945 
ILLINOIS WATERWAY, IL AND IN 
Channel 9 feet deep and 200 feet wide from mouth 
of Illinois River to Utica, 231 miles, modification 
of 2 U.S. locks and dams, removal of 2 State 
dams. (Act authorized appropriation of not to exceed 
$3,500,000 for carrying on work.) 
Channel 9 feet deep from Utica, IL, to heads of 
present Federal projects on Chicago and Calumet 
Rivers 94.6 miles to Lake Street, and 96.3 miles to 
turning basin 5, respectively, to be secured by means 
of completed dams, locks, lateral canals, and dredging 
begun by State of Illinois in general accordance with 
present plans of State for that work. Act adopting 
project authorized appropriation of not to exceed 
$7,500,000 for carrying on work. 
Operation and care of locks and dams provided for 
with funds from War Department appropriation for 
rivers and harbors. 
Construct modern locks and dams at LaGrange and 
Peoria and a channel 9 feet deep and 300 feet wide 
below Lockport, exact location and details of design 
of all structures to be left to discretion of Chief of 
Engineers, and, for time being, that no change be 
made in water authorized for navigation of Illinois 
River by act of July 3, 1930. 
Also provides for 3 passing places along Sag 
Channel and authorized channel in Calumet-Sag 
route to turning basin 5, and dredging at entrance of 
Lake Calumet. 
Realign portion of Calumet River and abandonment 
of bypassed section of Calumet River. 
Modifies local cooperation requirements in 1935 act. 
Pay damages to levee and drainage districts due to 
seepage and other factors, not to exceed $503,500. 
Enlarge Calumet-Sag Channel to 160 feet wide and 
a usable depth of 9 feet. Dredge a barge channel 160 
feet wide with a usable depth of 9 feet in Grand 
Calumet and Little Calumet River Branch of Indiana 
Harbor Canal to deep (lake) draft through 141st St., 
East Chicago, IN. Construct in Little Calumet River 
Rivers and Harbors 
Committee Doc. 69th Cong., 
1st sess., and S. Doc. 130, 
69th Cong., 1st sess. 
S. Doc. 126, 71st Cong., 
2nd sess. 
H. Doc. 184, 73rd Cong., 
2nd sess.2 
H. Doc. 180, 73rd Cong., 
2nd sess. 
Rivers and I larbors Committee 
Doc. 19, 75th Cong., 1st sess. 
H. Doc. 711, 77th Cong., 
2nd sess. 
H. Doc. 145, 76th Cong., 
1st sess. 
23-8

ROCK ISLAND, IL, DISTRICT 
TABLE 23-B (Continued) AUTHORIZING LEGISLATION 
See 
Section 
in Text 
Date 
Authorizing 
Act Project and Work Authorized 
March 2, 1945 
(Continued) 
a lock of suitable dimensions for large navigation. 
Rebuild or otherwise alter at Federal expense all 
obstructive railroad bridges across Calumet-Sag 
Channel, Little Calumet River, Calumet River, Grand 
Calumet River, and Indiana Harbor Canal, so as to 
provide suitable clearance, except that no Federal 
funds shall be expended fir removal or alteration 
of Illinois Central RR. bridge at mile 11.20 of Little 
Calumet River. 
Substitute following work for that authorized by act 
of March 2, 1945; replace emergency dam in Chicago 
Sanitary and Ship Canal; enlargement of that canal 
thence to Sag Junction and of Calumet Sag Channel 
to afford channels 225 feet wide and usable depth of 
9 feet; construct along general route depth of 9 feet 
to 225 feet wide between Little Calumet River and 
junction with Indiana Harbor Canal and 160 feet wide 
thence to Clark St., Gary, IN, with a turning basin at 
Clark St., enlarge Indiana harbor Canal to 225 feet 
wide and usable depth of 9 feet between Grand 
Calumet River and vicinity of 141st St., inclusive; 
remove Blue Island lock and construct a lock and control 
works in Calumet River near its head, and 
similar structures in proposed Grand Calumet 
Channel west of Indiana Harbor Canal; alter or eliminate 
railroad bridges across three channels lakeward 
of Chicago Sanitary and Ship Canal, or construct 
new railroad bridges to provide suitable 
clearance. 
A small-boat harbor in vicinity of Peoria, IL, by 
construction of a basin 510 by 250 feet, dredged to 
7 feet deep. 
$48,933 to reimburse Nutwood Drainage and Levee 
District for additional pumping operation; supplementing 
$58,750 authorized in October 1943 act. 
Federal participation in alteration of highway 
bridges, Calumet-Sag Modification, Part I, which 
constitute unreasonable obstructions to navigation, in 
accordance with Public Law 647, 76th Cong., as 
amended. 
Federal participation in alteration of highway 
bridges, Calumet-Sag Modification, Part II, which 
constitute unreasonable obstructions to navigation, 
in accordance with Public Law 647, 76th Cong., as 
amended. 
Illinois River at Peoria, IL modification of navigation 
project to include an adjacent downstream water 
area. 
UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM, IL, IA, MN, MO, WI 
Provide for a 10-year environmental program to 
include habitat rehabilitation and enhancement; longterm 
resource monitoring with computerized inventory 
and analysis; recreational development; assessment 
of economic benefits from recreational activities; 
and navigation system traffic monitoring. 
23-9 
Documents 
IH. Doc. 677, 79th Cong.. 
2nd sess. 
H. Doe. 698, 79th Cong., 
2nd sess. 
IH. Doc. 144, 81st Cong., 
1st sess. 
H. Doc. 45, 85th Cong., 
1st sess.4 
Specified in Act. Also 
H. Doc. 45, 85th Cong., 
1st sess. 
Sec. 857, II.R.6, Water 
Resources Development 
Act of 1986. 
H. Doc. 2577, 99th Cong., 
1st sess. 
July 24, 1946 
July 24, 1946 
July 17, 1953 
July 3, 1958 
August 18, 1968 
November 17, 1986 
August 15, 1985 
(P.L. 99-88)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 23-B (Continued) AUTHORIZING LEGISLATION 
Date 
Authorizing 
Act 
November 17, 1986 
7. June 28, 1938 
July 14, 1960 
8. August 15, 1985 
(P.L. 99-88) 
November 17, 1986 
9. 1944 Flood Control 
Act 
10. October 23, 1962 
11. November 17, 1986 
12. June 28, 1938 
December 19, 1985 
13. July 3, 1958 
October 22, 1976 
14. November 17, 1986 
20. November 17, 1986 
See 
Section 
in Text Project and Work Authorized 
Approves 1982 Upper Mississippi River Master Plan, 
authorizes interstate agreements between Upper 
Mississippi River states, directs Secretary to implement 
GREAT II recommendations for disposal of 
dredged material and facilitate the productive use of 
dredge material, directs and interagency agreement 
with the Department of Interior for its participation in 
the plan, authorizes second lock at Lock and Dam No. 6. 
CORALVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Highway bridge across Coralville Lake at or near the 
Mehaffey site. 
DES MOINES RECREATIONAL RIVER AND 
GREENBELT, IA 
Recreational development; environmental enhancement; 
and related streambank stabilization. 
Defines area of work. 
FARM CREEK, IL 
Two flood detention dams and channel improvements. 
HANNIBAL, MO 
Levee, floodwall, closure structures, and pumping plant 
for flood control. 
LOVES PARK, IL 
Improved channel, pumping plant and pond storage. 
RED ROCK DAM AND LAKE RED ROCK, IA 
Reservoir for flood control and recreation. 
Land Acquisition 
SAYLORVILLE LAKE, IA 
Reservoir for flood control and recreation. 
Modification to minimize adverse project impact on 
Ledges State Park. 
WEST DES MOINES, IA 
Construct levees and floodwall. 
MUSCATINE ISLAND LEVEE DISTRICT AND MUSCATINE-LOUISA COUNTY DRAINAGE DISTRICT, NO.13, IA 
Raise existing levees 
1. Permanent Appropriations Repeal Act 
2. Contains latest published map of Illinois and Des Plaines 
Rivers. 
3. Included, in part, in Public Works Administrative Program 
October 31, 1934, and February 28, 1935. 
4. Contains latest published maps of Calumet - Sag portion. 
23-10 
Documents 
Sec. 1103, H.R.6, Water 
Resources Development 
Act of 1986. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
None 
H. Doc. 2577, 99th Cong., 
1st sess. 
Sec. 604, H.R.6, Water 
Resources Development 
Act of 1986. 
H. Doc. 802, 78th Cong., 
2nd sess. 
H. Doc. 564, 87th Cong., 
2nd sess. 
Sec. 401, H.R.6, Water 
Resources Development 
Act of 1986. 
Flood Control Committee 
Doc. 1, 75th Cong., 1st sess. 
PL 99-190 
S. Doc. 9, 85th Cong., 
1st sess. 
H. Doc. 487, 94th Cong., 
2nd sess. 
Sec. 401, H.R.6, Water 
Resources Development 
Act of 1986 
Sec. 401, H.R.6, 
Water Resources 
Development Act of 1986.

ROCK ISLAND, IL, DISTRICT 
TABLE 23-C OTHER AUTHORIZED NAVIGATION PROJECTS 
(See Section 6 of Text) 
For Last Cost To September 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Hannibal SBH, MO Completed 1958 $ 108,7004 $ 58,000 
Squaw Chute at Quincy, IL Completed 1967 70,979' 9,345 
Muscooten Bay, Illinois River, IL Completed 1985 265,499' 171,000 
Quincy, IL, Harbor Access Channel Completed 1970 35,4772 37,700 
Muscatine Harbor, IA Completed 1964 353,000 85,999 
1. Excludes $25,851 contributed funds. 3. Excludes $137,869 contributed funds. 
2. Excludes $35,350 contributed funds. 4. Excludes $20,300 contributed funds. 
TABLE 23-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 16 of Text)
Cost To September 30, 1992 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Projects 
Banner Special Drainage and Levee Districts, IL 
Bear Creek Dam (City of Hannibal, MO) 
Bettendorf, IA 
Big Lake Drainage and Levee District, IL 
Canton, MO' 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
Des Moines and Mississippi Levee District 
No. 1, MO 
Des Moines, IA 
Drury Drainage District, IL 
Dubuque, IA 
East Liverpool Drainage and Levee District, IL 
1943 
1962 
1987 
1943 
1964 
1991 
1954 
1941 
1969 
1972 
1964 
1974 
1941 
$ 247,822 
1,679,056 
14,930,085 
144,910 
1,496,555 
26,237,690 
1,923,145 
68,898 
1,492,016 
4,993,224 
1,144,875 
10,861,170 
207,826 
23-11 
$ 228,073 
839,615 
23,323 
145,415

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 23-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) (See Section 16 of Text)
Cost To September 30, 1992 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
Completed Projects 
East Moline, IL 1984 $ 9,692,097 - - 
East Peoria Drainage and Levee District, IL 1946 279,963 - - 
Elkport, IA 1951 34,200 - - 
Evansdale, IA 1983 4,409,088 - - 
Fabius River Drainage District, MO 1941 60,500 - - 
Fabius River Drainage District, MO 1963 1,621,841 - - 
Farmers Levee and Drainage District, IL 1942 155,562 - - 
Fulton, IL 1984 18,017,200 - - 
Galena, IL 1952 844,100 - $118,000 
Green Bay Levee and Drainage District No. 2, IA 1949 299,000 - - 
Green Bay Levee and Drainage District No. 2, IA 1967 1,727,711 - - 
Gregory Drainage District, MO 1940 77,100 - - 
Gregory Drainage District, MO 1972 1,538,963 - 20,626 
Henderson County Drainage District No. 1, IL 1968 1,453,217 - - 
Henderson County Drainage District No. 2, IL 1968 1,043,902 - - 
Henderson County Drainage District No. 3, IL 1949 42,700 - - 
Hennepin Drainage and Levee District, IL 1940 109,593 - - 
Hunt Drainage District and Lima Lake Drainage 
District, IL 1972 4,772,498 - - 
Indian Grave Drainage District, IL 1972 3,551,961 - - 
Iowa River-HFlint Creek Levee District No. 16, IA 1972 6,044,693 - - 
Kishwaukee River at DeKalb, IL' 1957 123,300 - - 
Lacey Langellier, West Mantanzas and Kerton 
Valley Drainage and Levee District, IL 1954 1,290,000 - - 
Liverpool Drainage and Levee District, IL 1943 117,731 - - 
Lost Creek Drainage and Levee District, IL 1938 152,000 - - 
Marengo, IA' 1981 2,447,001 - - 
Marion County Drainage District, MO 1967 873,748 - - 
Marshalltown, IA 1978 8,437,511 - 252,136 
Mason and Menard Drainage District, IL 1940 93,808 - - 
Meredosia Levee and Drainage District, IL' 1977 1,995,322 - 269,739 
Milan, IL 1988 13,437,663 - 213,554 
Muscatine, Mad Creek, IA' 1983 1,129,800 - - 
Muscatine Island Levee District and Muscatine- 
Louisa County Drainage District No. 13, IA 1970 3,293,276 - 220,000 
Near Springfield on Sangamon River, IL 1941 - - - 
Oakford Special Drainage District, IL 1940 38,417 - - 
Okabena Creek at Worthington, MN' 1957 72,432 - - 
Ottumwa, IA 1977 233,145 - - 
Pekin and La Marsh Drainage and Levee 
District, IL 1955 158,383 - - 
Penny Slough, Rock River, IL 1940 85,800 - - 
Rock Island, IL 1979 7,582,373 - - 
Rockford, IL 1989 9,993,778 - 514,188 
Rocky Ford Drainage and Levee District, IL 1941 108,797 - - 
Sabula, IA 1958 411,915 - - 
Sangamon River (Mouth), IL 1980 1,048,990 272,848 15,122 
Seahorn Drainage and Levee District, IL 1945 32,281 - - 
Sid Simpson Project, IL 1968 5,789,800 - - 
Sny Basin, IL 1972 14,003,560 - - 
Sny Island Levee Drainage District, IL 1942 61,400 - - 
Sny Island Levee Drainage District, IL 1968 4,956,749 - - 
23-12

ROCK ISLAND, IL, DISTRICT 
TABLE 23-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 16 of Text)
Cost To September 30, 1992 
For Last 
Full Report Operation Contributed 
See Annual and Funds 
Project Report For Construction Maintenance Expended 
South Beardstown and Valley Drainage and 
Levee District, IL 1942 $ 220,729 - - 
South Beardstown Drainage and Levee District, IL 1942 171,839 - - 
South Quincy Drainage and Levee District, IL 1940 61,200 - - 
South Quincy Drainage and Levee District, IL 1968 1,231,243 - - 
South Quincy Drainage and Levee District, IL 1991 7,150,161 - $ 2,103,886 
South River Drainage District, MO 1941 55,300 - - 
South River Drainage District, MO 1966 1,106,056 - - 
Spring Lake Drainage and Levee District, IL 1941 185,980 - - 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1, IL 1967 3,306,695 - - 
Union Township Drainage District, MO 1947 116,576 - - 
Van Meter, IA' 1965 113,842 - - 
Waterloo, IA 1987 48,620,099 - 83,300 
Waterloo, IA (Bridges) 1991 1,122,757 - 1,156,982 
Authorized Projects Not Constructed 
Ames Dam and Reservoir, Skunk River, IA 1987 1,400,800 - - 
Davenport, IA 1987 - - - 
Freeport, IL 1979 - - - 
Moline, IL 2 1987 - - - 
Peoria, IL 1973 534,580 - - 
Rock River Agricultural Levees, IL 1984 858,000 - - 
1. Authorized by Chief of Engineers (Sec. 205, 1948 Flood Control Act). 
2. FY 89 funds of $5,639 were expended to close out project. 
TABLE 23-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Cal.-Sag Channel, Part II 
Illinois Waterway, IL and IN 
Campbells Island 
Mississippi River, IL 
Carroll County Levee 
and Drainage District, IL 
Central City Lake, 
Wapsipinicon River, IA 
Farmers Drainage and Levee 
District (Sangamon River), IL 
Green Island Levee and 
Drainage District, IA 
Henderson River, IL 
Illinois Waterway, IL and IN 
Duplicate Locks 
Illinois Waterway 
Navigation Project (Pekin, IL) 
Janesville and Indian 
Ford Dams, WI 
1986 
1969 
1938 
1970 
1942 
1938 
1964 
1982 
1986 
1938 
1986 
1979 
1977 
1977 
1986 
1977 
1977 
1981 
1986 
1977 
$ 76,664 
55,664 
102,310 
23-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 23-G (Continued) DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Keithsburg Drainage 
District, IL 1938 1977 - - 
Pecatonica River at 
Darlington, WI - 1977 - - 
Rochester Lake, 
Cedar River, IA 1977 - - 
South Beloit, IL 1979 1986 $ 270,000 - 
William L. Springer Lake 
Decatur, IL 1979 1986 - - 
Illinois Waterway, 
Marseilles Canal, IL 1989 1990 - - 
Peoria Levees, IL - 1990 - - 
TABLE 23-H INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 15 of Text) 
Date 
Project Inspected 
Alpine Dam and Page Park Dam, Rockford, IL 
Banner Special Drainage and Levee District, IL 
Bear Creek Reservoir, Hannibal, MO 
Bettendorf, IA 
Big Lake Drainage and Levee District, IL 
Burlington, IA 
Canton, MO 
Clinton, IA 
Coal Creek Drainage and Levee District, IL 
Crane Creek Drainage and Levee District, IL 
DeKalb, IL 
Des Moines, IA 
Des Moines and Mississippi Levee District No. 1, MO 
Drury Drainage District, IL 
Dubuque, IA 
East Liverpool Drainage and Levee District, IL 
East Moline, IL 
East Peoria Drainage and Levee District, IL 
East Peoria Sanitary District, IL 
Elkport, IA 
Evansdale, IA 
Fabius River Drainage District, MO 
Farmers Drainage and Levee District, IL 
Fulton, IL 
Galena, IL 
Green Bay Levee and Drainage District No. 2, IA 
Gregory Drainage District, MO 
Henderson County Drainage District No. 1, IL 
Henderson County Drainage District No. 2, IL 
Hennepin Drainage and Levee District, IL 
Hergot Drainage and Levee District, IL 
Hunt Drainage District & Lima Lake Drainage District, IL 
Indian Grave Drainage District, IL 
November 1991 
January 1992 
November 1991 
October 1991 
February 1992 
December 1991 
November 1991 
December 1991 
January 1992 
January 1992 
November 1991 
December 1991 
November 1991 
December 1991 
October 1991 
January 1992 
October 1991 
December 1991 
December 1991 
October 1991 
October 1991 
November 1991 
January 1992 
November 1991 
October 1991 
December 1991 
November 1991 
December 1991 
December 1991 
January 1992 
February 1992 
November 1991 
November 1991 
23-14

ROCK ISLAND, IL, DISTRICT 
TABLE 23-H INSPECTION OF COMPLETED FLOOD CONTROL 
(Continued) (See Section 15 of Text) 
Project 
Iowa River-Flint Creek Levee District No. 16, IA 
Kerton Valley Drainage and Levee District, IL 
Lacey Drainage and Levee District, IL 
Langellier Drainage and Levee District, IL 
Liverpool Drainage and Levee District, IL 
Lost Creek Drainage and Levee District, IL 
Mad Creek, Muscatine, IA 
Marengo, IA 
Marion County Drainage District, MO 
Marshalltown, IA 
Mason and Menard Drainage District, IL 
Meredosia Levee and Drainage District, IL 
Milan, IL 
Muscatine Island, L&DD, & Louisa DD No. 13, IA 
Oakford Special Drainage and Levee District, IL 
Pekin-LaMarsh Drainage and Levee District, IL 
Penny Slough Drainage and Levee District, IL 
Rock Island, IL 
Sabula, IA 
Sanitary District of Beardstown, IL 
Seahorn Drainage and Levee District, IL 
Sny Island Levee Drainage District, IL 
South Beardstown Drainage and Levee District, IL 
South Quincy Drainage and Levee District, IL 
South River Drainage District, MO 
Spring Lake Drainage and Levee District, IL 
Subdistrict No. 1 of Drainage District Union No. I 
and Bay Island Levee and Drainage District No. 1, IL 
The Sny Basin, IL 
Valley Drainage and Levee District IL 
Van Meter, IA 
Volga, IA 
Waterloo, IA 
West Matanzas Drainage and Levee District, IL 
Worthington, MN 
PROJECTS 
Date 
Inspected 
December 1991 
January 1992 
January 1992 
January 1992 
January 1992 
February 1992 
December 1991 
October 1991 
November 1991 
October 1991 
February 1992 
November 1991 
October 1991 
December 1991 
December 1991 
January 1992 
November 1991 
October 1991 
October 1991 
February 1992 
January 1992 
November 1991 
January 1992 
November 1991 
November 1991 
December 1991 
December 1991 
January 1992 
November 1991 
October 1991 
October 1991 
January 1992 
September 1991 
TABLE 23-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 
858, 80th Congress, as Amended (Preauthorization) 
(See Section 17 of Text) 
Study Identification Fiscal Year Costs 
Blackhawk Creek, Davenport, IA 
Cedar Falls, Cedar River, IA 
Duck Creek, Scott County, Davenport, and Bettendorf, IA 
East Peoria, IL 
Fourmile Creek, Des Moines, IA 
Illinois River, Liverpool, IL 
23-15 
$ 18,032 
20,170 
3,789 
220 
4,762 
31,239 
I

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
Flood Control Activities Pursuant to Section 205, Public Law 
858, 80th Congress, as Amended (Preauthorization) 
(See Section 17 of Text) 
Study Identification 
Iowa River, Chelsea, IA 
Oelwein, Fayette County, IA 
Ottawa, IL 
Panther Creek, Sangamon River, Chandlerville, IL 
Raccoon River, Des Moines, IA 
Rock Creek, Maxwell, IA 
S. River Drainage District, Marion County, MO 
Sny Island Levee and Drainage District, IL 
Stevens Creek, Decatur, IL 
Stevens Creek, Macon County, IL 
Stevens Creek, Village of Forsyth, IL 
Tama, IA 
Turkey River, Elkader, IA 
West Branch, Indian Creek, Neveda, IA 
Wolf Creek, LaPorte City, IA 
Fiscal Year Costs 
$ 39,450 
14,870 
14,946 
24,481 
27,699 
5,743 
12,323 
8,806 
10,000 
10,000 
9,117 
1,620,679 
21,325 
9,920 
10,093 
TABLE 23-I Snagging and Clearing Navigable Streams and 
Tributaries in the Interest of Flood Control (Preauthorization) 
(Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress) 
(See Section 17 of Text) 
Project and. Location Fiscal Year Costs 
Henderson Creek, Warren County, IL $ 9,521 
South Skunk River Logjam, Keokuk, IA 10,892 
TABLE 23-I Emergency Bank Protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
(See Section 17 of Text) 
Project and Location Fiscal Year Costs 
Bear Creek, County Route 276, Marion County, MO $ 17,101 
Clayton County Bridge, Osterdock, IA 2,935 
Clayton County, Elkport, Osterdock, IA 12,952 
Clayton County Road Creek ClX, Site 1, IA 5,383 
Clayton County Road Creek, Site 2, IA 13,413 
Clayton County Road, NW, Osterdock, IA 8,451 
Farmington, Des Moines River, IA 24 
Fox River, Bridge Site #4, Davis Co., IA . 39,908 
Fox River, Bridge Site #7, Davis Co., IA 3,481 
Fox River, Route J40 Bridge, Davis Co., IA 35,452 
Maquoketa River Co. Road 47 Bridge, IA 79,452 
Mazon River, Goose Lake, Grundy County, IL 1,464 
Mississippi River, First Avenue, Hampton, IL 20,000 
Monroe County, IA -1,980 
N. Fork, Maquoketa River, Cascade, IA 5,503 
Soap Creek, Bridge Site #3, Davenport, IA 33,825 
West Fork, Des Moines River, MN 8,940 
23-16 
TABLE 23-I 
(Continued)

ROCK ISLAND, IL, DISTRICT 
TABLE 23-I FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(Continued) Emergency Flood Control Activities - Repair, Flood Fighting, and 
Rescue Work (Public Law 99, 84th Congress and Antecedent Legislation) 
(See Section 17 of Text) 
Project and Location Federal Cost 
Advance Preparation: $ 159,364 
Emergency Operations: 61,978 
Rehabilitation: 100 
TABLE 23-J ILLINOIS WATERWAY: 
EXISTING LOCKS AND DAMS 
(See Section 2 of Text) 
Depth on 
Dimensions Miter Sills 
at Low Water 
Available Lift at 
Miles Width of Length for Low 
Above Chamber Full Width Water' Lower Upper 
Lock Mouth Miles to Nearest Town (feet) (feet) (feet) (feet) (feet) 
LaGrange Lock 80.2 7.8 below BUeardstown, IL 110 600 10.0 13.0 15.5 
Peoria Lock 157.7 4.1 below Peoria, IL 110 600 11.0 12.0 15.5 
Starved Rock Lock 231.0 Utica, IL 110 600 18.5 14.0 16.8 
Marseilles Lock 244.6 Marseilles, IL 110 600 24.45 14.0 18.6 
Dresden Island Lock 271.5 8 above Morris, IL 110 600 21.75 12.25 16.85 
Brandon Road Lock 286.0 Joliet, IL 110 600 34.0 13.8 17.85 
Lockport Lock 291.1 Lockport, IL 110 600 30.5-39.52 15.0 11.0-20.02 
T.J. O'Brien Lock 326.5 Chicago, IL 110 1,000 - 14.0 14.0 
1. Lifts and depth on miter sills are those obtained with 2. Variation in lift and depth on upper miter sill at 
flat pools. Lockport is due to fluctuation of water surface in the sanitary 
district canal. 
TABLE 23-K ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 2 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
Illinois River, $ 2,733,499' 
mouth to Utica; 
channel improvement 
by dredging 
in Illinois River 
below Starved Rock 
modification of two 
U.S. locks and 
dams, and removal 
of two State dams. 
23-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 23-K 
(Continued) 
ILLINOIS WATERWAY, IL AND IN 
LOCK AND DAM CONSTRUCTION, FOUNDATIONS, COST 
(See Section 2 of Text) 
Lock Dam Estimated 
Federal Cost 
Under 
Type of Character of Type of Character of Year Existing 
Name Construction Foundation Kind Construction Foundation Complete Project 
LaGrange Concrete Piles in sand Movable Concrete Piles in sand 1939 $ 2,744,592' 
Concrete Piles in sand 
Starved Rock 
Marseilles 
Dresden Island 
Brandon Road 
Lockport 
T.J. O'Brien 
Lock and dam 
equipment 
Total locks 
and dams 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Concrete Rock 
Concrete 
and sheet 
piling 
(wicket 
with A. 
frame-crest) 
Movable 
(wicket 
type) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Movable 
(tainter 
gates) 
Movable 
(Bear trap) 
(Bear trap) 
Piles in clay Fixed 
and timber 
Concrete 
and timber 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Concrete 
and 
structural 
steel 
Concrete 
and sheet 
piling 
Piles in sand 
Rock 
Rock 
Rock 
Rock 
Rock 
Piles in clay 
1939 
1933 
1933 
1933 
1933 
1933 
1960 
3,381,030' 
885,315' 
1,853,725' 
2,503,376' 
2,031,683' 
1:1:3,608' 
6,954,700' 
1,250,304' 
- $ 24,471,832 
1. Actual cost. 
TABLE 23-L ILLINOIS WATERWAY, IL AND IN 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 2 of Text) 
Dredging: 
Little Calumet and Calumet Rivers 
Calumet-Sag, 3 passing places 
Starved Rock to Lockport 
Starved Rock to Grafton 
Calumet-Sag Channel 
Peoria small boat harbor 
Peoria 
$ 2,135,358' 
813,318' 
6,007,335 
2,917,607 
19,238,200 
24,937' 
23-18

ROCK ISLAND, IL, DISTRICT 
ILLINOIS WATERWAY, IL AND IN 
ADDITIONAL FEATURES ENTERING INTO COST 
(See Section 2 of Text) 
Protection piers at all locks 
Calumet-Sag modification engineering and design 
Calumet-Sag modification, supervision and administration 
Rebuild highway bridges 
Rebuild railway bridges: 
Calumet-Sag Channel 
Little Calumet and Calumet Rivers 
Recreation Facilities, Code 711 
Removal of Blue Island lock 
Grand Calumet River controlling works 2 
St. Louis District 
Total additional features 
Total existing project 
1. Actual cost. 
TABLE 23-M 
77,613' 
5,141,474 
5,466,804 
19,327,850 
20,828,435' 
18,362,041' 
445,000 
288,600' 
1,081,600' 
$100,442,142 
$124,913,974 
2. Placed in inactive status November 19, 1974. 
EXISTING PROJECT 
See 
Section 
in Text Project Item Length (feet) Width (feet) Depth (feet) 
2. Illinois Waterway, Nine locks and six dams - - 
IL and IN 
Grafton to Lockport, IL 291.1 miles 300 9 
Lockport to controlling works 2.0 miles 200-300 9 
Controlling works to junction with 10.0 miles 225 9 
Calumet-Sag Channel 
Calumet-Sag Channel to lock in Blue 16.0 miles 225 9 
Island 
Calumet and Little Calumet Channel, 7.7 miles 300 9 
from Blue Island to turning basin 5 
Grand Calumet River Channel from 9.0 miles 9 
junction with Little Calumet River 
to and in Indiana Harbor Canal to 
141st, East Chicago, IN 
Also, Grand Calumet River Channel 4.2 miles 160 9 
from junction of Indiana Harbor 
Canal and Grand Calumet River to 
Clark St. in Gary, IN, with a turning 
basin at Clark St. 
A channel in Chicago Sanitary and 22.1 miles 175-300 9 
Ship Canal and South Branch 
Chicago River from Sag-Junction to 
Lake St. in Chicago, IL 
23-19 
TABLE 23-L 
(Continued)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 23-N ILLINOIS WATERWAY, IL AND IN 
TOTAL COST OF EXISTING PROJECT 
TO SEPTEMBER 30, 1992 
(See Section 2 of Text) 
New Work Maintenance Rehabilitation Total 
Regular Funds $120,886,748 $312,757,028 $136,989,696 $570,633,472 
Public Works Funds 3,960,735 - - 3,960,735 
Emergency Relief Funds 1,858,936 - - 1,858,936 
Total $126,706,419 $312,757,028 $136,989,696 $576,453,143' 
1. Includes $1,735,890 expended between 1927 and 1936 on the of the permanent indefinite appropriation for such purposes. 
operation and care of the works of improvement under the provisions
23-20

ST. PAUL, MN DISTRICT* 
District comprises western Wisconsin, major portion of Minnesota, 
northern and eastern North Dakota, and small portions of 
northeastern South Dakota and northern and northeastern Iowa 
embracing drainage basins of Mississippi River and tributaries 
from its source to mile 614 above mouth of Ohio River; Red 
River of the North and tributaries; those streams north of 
Missouri River Basin in North Dakota; and U.S. waters of Lake 
of the Woods and its tributaries. That section of Mississippi 
River above mile 614 is included in report on Mississippi River 
between Missouri River and Minneapolis, Minnesota. 
IMPROVEMENTS 
Navigation Page 
1. Minnesota River, MN ................. 24-2 
2. Mississippi River between Missouri River 
and Minneapolis, MN ................. 24-2 
3. Reservoirs at Headwaters of Mississippi 
River, MN ......................... 24-2 
4. Upper Mississippi River System Environmental 
Management Program (UMRS-EMP)........ 24-3 
5. Zippel Bay, Lake of the Woods County, MN... 24-3 
Flood Control 
6. Bassett Creek, MN.................... 24-4 
7. Big Stone Lake and Whetstone River, MN 
and SD ........................... 24-4 
8. Chaska, MN........................ 24-5 
9. Devils Lake, ND .................... 24-5 
10. Eau Galle River, WI................... 24-5 
11. Emerson, Manitoba--Noyes, MN .......... 24-6 
12. Grand Mound-State Historical Site, MN ...... 24-6 
13. Homme Lake and Dam, ND ............. 24-6 
14. Houston, MN ....................... 24-7 
15. Lac qui Parle Lakes, Minnesota River, MN .... 24-7 
16. La Farge Lake and Channel Improvement, WI . . 24-8 
17. Lake Ashtabula and Baldhill Dam, 
Sheyenne River, ND ................... 24-8 
18. Lake Traverse and Bois de Sioux River, 
SD and MN ....................... 24-9 
19. Mankato and North Mankato, MN ......... 24-9 
20. Marshall, MN ....................... 24-9 
21. Middle River at Argyle, MN ............ 24-10 
22. Minnesota River at Henderson, MN ....... 24-10 
23. Portage, WI ....................... 24-10 
24. Red Lake River, MN including Clearwater 
River, MN........................ 24-11 
25. Red River of the North at Fargo, ND - 
Moorhead, MN .................... 24-11 
26. Red River of the North Drainage Basin, 
MN,SD,andND .................... 24-11 
27. Rochester, MN ..................... 24-12 
28. Root River at Hokah, MN ............. 24-12 
29. Roseau, River, MN ................. 24-13 
Page 
30. Sheyenne River, ND ................... 24-13 
31. Souris River Basin, ND ................. 24-13 
32. State Road and Ebner Coulees, WI ......... 24-14 
33. St. Paul, MN ........................ 24-15 
34. Wabasha, Mississippi River, MN .......... 24-15 
35. Warner Road at Sibley Street, Mississippi 
River, St. Paul, MN ................... 24-15 
36. Zumbro River at Genoa, MN ............. 24-16 
37. Inspection of Completed Flood Control 
Projects .......................... 24-16 
Miscellaneous 
38. Other Work Under Special Authority ........ 24-16 
General Investigations 
39. Surveys .......................... 24-16 
40. Collection and Study of Basic Data ......... 24-16 
41. Advance Engineering and Design .......... 24-17 
Tables 
Table 24-A Cost and Financial Statement ........ 24-18 
Table 24-B Authorizing Legislation ........... 24-22 
Table 24-C Other Authorized Navigation Projects .. 24-23 
Table 24-D Not Applicable 
Table 24-E Other Authorized Flood 
Control Projects ................ 24-24 
Table 24-F Not Applicable 
Table 24-G Deauthorized Projects ............ 24-26 
Table 24-H Reservoirs at Headwaters of 
Mississippi River ............... 24-27 
Table 24-I Red River of the North Drainage 
Basin: Active Units in 
Comprehensive Basin Plan ......... 24-28 
Table 24-J Inspection of Completed Flood 
Control Projects ................ 24-29 
Table 24-K Flood Control Work Under 
Special Authorization ............ 24-30 
Table 24-L Project Modifications for Improvement 
of Environment ................ 24-31 
Table 24-M General Investigations ............ 24-32 
24-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. MINNESOTA RIVER, MN 
Location. Rises in Big Stone Lake, MN and SD, and 
flows southeasterly about 224 miles to Mankato, MN, thence 
northeasterly about 106 miles to join the Mississippi River 
opposite St. Paul, MN. (For general location see Geological 
Survey map of Minnesota.) 
Previous Projects. For details see page 1890 of Annual 
Report for 1915, and page 1105 of Annual Report for 1938. 
Existing Project. Provides 9-foot depth below flat pool 
level of Mississippi River lock and dam 2 from mouth to 
mile 14.7, one-half mile above the railway bridge at Savage, 
MN, and 4-foot depth from mile 14.7 to 25.6 at Shakopee, 
MN. For details see page 1018 of Annual Report for 1965. 
(See Table 27-B for authorizing legislation.) 
Local Cooperation. Fully complied with. See also page 
1074 of Annual Report for 1967. 
Terminal Facilities. There are privately-owned terminals 
at miles 9, 13.1, 14.5, and two at mile 14.7. 
Operations and Results During Fiscal Year. Maintenance: 
Dredging by hired labor cost $144. Hydrographic 
surveys cost $7,325. Administrative costs amounted to 
$3,372. 
Condition at End of Fiscal Year. Work on project for 
4-foot depth was completed in 1931. The United States 
owns 10 acres of land in fee 2 miles east of Savage, MN, 
and easements on 123.08 acres of land. 46.20 acres have 
been transferred from the Department of the Army and 
Department of the Air Force to the project. Navigation from 
mouth to Shakopee was practicable for drafts not in excess 
of 3 feet. A contract for work under 1958 authorization for 
a 9-foot channel started in May 1966 and was terminated in 
January 1967 when 56 percent complete. A channel 
dredging contract awarded in June 1967 was completed in 
August 1968. Total costs for existing project to September 
30, 1992, were $4,697,723, of which $1,940,180 was for 
new work and $2,757,543 for maintenance. In addition, cost 
from contributed funds was $139,671 for dredging to 9-foot 
depth under provisions of Section 4, River and Harbor Act 
of 1915, and $219,531 for work done for the State of 
Minnesota relative to modification of the project. 
2. MISSISSIPPI RIVER BETWEEN 
MISSOURI RIVER AND 
MINNEAPOLIS, MN 
For report on this improvement see chapter on Mississippi 
River between Missouri River and Minneapolis, Minnesota. 
3. RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER, MN 
Location. Reservoirs are on the Mississippi River and 
several of its tributaries in Itasca, Beltrami, Hubbard, Aitkin, 
Cass and Crow Wing Counties, MN. (See Table 24-H on 
reservoirs.) 
Previous Projects. For details see page 1888 of Annual 
Report for 1915, and page 1098 of Annual Report for 1938. 
Existing Project. Provides for reconstruction from timber 
to concrete at Winnibigoshish, Leech Lake, Pokegama, 
Sandy Lake and Pine River Dams, and construction of a 
concrete dam at Gull Lake. Pokegama was built on bedrock 
and the others on pile foundations. A portion of Leech Lake 
Dam from piers 26 to 39 was replaced with an earth fill. 
Constructed three dikes at Winnibigoshish, four at 
Pokegama, two at Sandy Lake, and 16 at Pine River. Sandy 
Lake Dam includes a lock 160 feet long, 30 feet wide, with 
a maximum lift of 9.5 feet and a depth of 2.5 feet on lower 
sill at low water which was converted to use as a spillway. 
(See Table 24-B for authorizing legislation.) 
Local Cooperation. Fully complied with. 
Terminal Facilities. None. 
Operations and Results During Fiscal Year. Maintenance: 
Reservoirs were operated as required, recreation 
facilities and equipment maintained, and surveys, repairs, 
and reports were made by hired labor at a cost of 
$1,369,175. Reservoirs were operated by contract at a cost 
of $303,189. Physical security cost $327 by hired labor. 
Periodic inspection and dam safety costs were $120,634 by 
hired labor, $46 by contract and $-6,470 by other Corps. A 
bridge replacement construction contract at Winnibigoshish 
cost $1,010. Cultural resource investigation cost $11,669 by 
contract and $34,363 by hired labor. Environmental review 
and survey analysis cost $22,494 by hired labor. Data 
collection, water analysis, structural inventory for drought 
planning and maintenance of stream gauging cost $200,542 
24-2

ST. PAUL, MINNESOTA DISTRICT 
by hired labor, $4,188 by contract, $4 by other Corps, and 
$27,630 by U.S. Geological Survey. Miscellaneous 
engineering and design cost $82,063 by hired labor, and 
$450 by contract. Real estate was managed at a cost of 
$43,923. Lands and damages cost $61,653 by hired labor 
and $29,699 by contract. Supervision and inspection costs 
were $257,835 by hired labor and $11,729 by contract. 
Condition at End of Fiscal Year. Existing project was 
completed in 1937. Flowage rights were acquired on all 
lands affected by construction, maintenance, and operation 
of reservoirs. A total of 1,672.26 acres in fee are owned by 
the United States. The United States has easements, flowage 
rights, and other rights of use on another 296,334.44 acres. 
Structures are in fair condition. Recreation facilities for 
public use are being constructed intermittently at all reservoir 
areas. (See Table 24-H for capacities and costs by 
reservoir.) 
4. UPPER MISSISSIPPI RIVER SYSTEM 
ENVIRONMENTAL MANAGEMENT 
PROGRAM (UMRS-EMP) 
Location. The program is authorized for the commercially 
navigable portions of the Upper Mississippi River System. 
In the St. Paul District, this includes the Mississippi, 
Minnesota, Black, and St. Croix Rivers in the states of 
Minnesota, Wisconsin and Iowa. 
Existing Project. The purpose of the UMRS-EMP as 
stated in the authorizing legislation is to ensure the 
coordinated development and enhancement of the Upper 
Mississippi River System, recognizing its several purposes. 
It is intended to protect and/or enhance the river resources 
and guide future river management. The primary emphasis 
of the program is on habitat rehabilitation and enhancement 
projects. Long term resource monitoring will provide the 
means for more informed management of the UMRS. Also 
authorized, are a study of the economic impacts of 
recreation, navigation traffic monitoring, and recreation 
projects (currently unfunded). The program was initiated in 
FY 1986 utilizing funds provided by the FY 1985 
Supplemental Appropriations Act. The execution of the 
program is being closely coordinated with the Upper 
Mississippi River Basin Association, the U.S. Fish and 
Wildlife Service, and the three affected states in the St. Paul 
District. See Rock Island District Tables 23-A and 23-B for 
total program costs and authorizing legislation. 
In the St. Paul District, five habitat projects have been 
completed. These are the Guttenberg Waterfowl Ponds (IA), 
Island 42 (MN), Lake Onalaska (WI), Blackhawk Park (WI), 
and Pool 8 Islands (WI). The projects are being operated 
and maintained by the U. S. Fish and Wildlife Service, 
except for Blackhawk Park which is managed by the 
Wisconsin Department of Natural Resources. Through FY 
1992, funds allocated to the St. Paul District have amounted 
to $8,851,000 for design, construction and monitoring of 
habitat rehabilitation and enhancement projects, $421,000 
for long term resource monitoring, $740,000 for economic 
impacts of recreation study, and $791,000 for program 
management. The allocations for the overall program 
projected over a 10-year period for the St. Paul District are 
about $34 million. The Water Resources Development Act 
of 1990, Section 405, authorized an additional 5 years for 
the EMP program to the year 2002. 
Local Cooperation. Local cooperation agreements are 
obtained for habitat projects for such projects not located on 
lands managed as a national wildlife refuge, within the 
meaning of Section 906(e) of the 1986 WRDA. 
Operations During Fiscal Year. Costs during the year 
totaled $4,083,082. The majority of funds were expended 
on the planning, design, construction and monitoring of 
habitat projects. Design was initiated on two projects and 
continued on ten; construction was initiated on three projects, 
continued on one, and completed on one project. Funds 
were also used for the economic impacts of recreation study, 
program management, and long term resource monitoring 
elements. 
5. ZIPPEL BAY, LAKE OF THE WOODS 
COUNTY, MN 
Location. Zippel Bay is a natural harbor located in 
northwestern Minnesota on the south shore of Lake of the 
Woods near Williams, Minnesota. The navigation project is 
located in Zippel Bay State Park. 
Existing Project. Boats based at a state park, resort, 
marina, and a number of private residences use Zippel Bay 
to provide access to the lake. However, the natural channel 
between the bay and Lake of the Woods varied in depth and 
width and restricted navigation. The plan of improvement 
provides a small-boat access channel 50-70 feet wide and 
approximately 1,800 feet long between Zippel Bay and Lake 
of the Woods. Jetties have been constructed on both sides of 
the channel to minimize the amount of maintenance dredging. 
The project was approved by the Chief of Engineers for 
construction in October 1985 under the authority contained 
in Section 107 of the Rivers and Harbors Act of 1960, as 
amended. 
Local Cooperation. Fully complied with. 
Operations and Results During Fiscal Year. Maintenance: 
An adjustment was made on a dredging contract for 
$-348. Administrative costs were $782. 
Condition at End of Fiscal Year. Construction of the 
small boat navigation project is completed. Responsibility 
24-3

REPORT OF THE SECRETARY OF TIlE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
for the project was transferred to the local sponsor, the State 
of Minnesota Department of Natural Resources, in July 
1988. 
HFlood Control 
6. BASSETT CREEK, MN 
Location. In Hennepin County and Minneapolis, 
Minnesota, on Bassett Creek, a tributary of the Mississippi 
River. (For general location, see Geological Survey map of 
Minnesota.) 
Existing Project. The proposed project consists of 
nonstructural and structural flood control measures. 
Nonstructural measures include continuation of existing 
floodplain regulations, flood insurance and forecasting, and 
flood warning. Principal structural measures consist of six 
small control structures in the upper watershed to 
temporarily impound floodwaters and a new tunnel (part of 
which is being constructed on a cooperative basis with the 
Minnesota Department of Transportation) in a highly 
urbanized area of Minneapolis to replace the existing tunnel 
outletting Bassett Creek to the Mississippi River. Also 
included in the plan are a limited reach of channel widening, 
bridge removals, culvert replacements, a weir structure, a 
flood storage area, and a railroad bridge replacement. 
Estimated Federal cost (1992) for new work is $29,000,000 
and $11,600,000 is to be contributed by local interests. 
Project was authorized by the 1976 Water Resources 
Development Act. 
Local Cooperation. See Annual Report for 1977 for 
requirements. Under current cost sharing policies, when the 
costs of lands, easements, and rights- of-way are less than 20 
percent of total project costs, local interests are required to 
furnish the standard local cooperation requirements plus a 
cash contribution, the total of the two to amount to a 
minimum of 25 percent of the total project costs. On June 
27, 1986, the City of Minneapolis entered into a local 
cooperation agreement with the Department of the Army. 
Operations and Results During Fiscal Year. New Work: 
Miscellaneous real estate costs were $16,694. Railroad 
relocations, Stage 2C1, and Stage 4 construction contracts 
cost $16,000, $352,209, and $1,082,582, respectively. 
Engineering and design cost $4,124 by contract, and 
$414,760 by hired labor. Construction management cost 
$8,695 by contract and $203,758 by hired labor. Total 
Federal costs were $1,841,549 and non-Federal $257,273. 
Condition at End of Fiscal Year. Construction of the 
first control structures is complete. The Minnesota 
Department of Transportation (MnDOT) has completed 
construction of the downstream portion of the tunnel 
including the last 4,800 feet and outlet to the Mississippi 
River. The amount of $3,642,888 was reimbursed to 
MnDOT for the Federal share of the work. Construction 
work was completed on the tunnel segment located in 
sandstone (Stage 3). Construction work on the tunnel 
segment in soft ground (Stage 4) and construction on a small 
upstream embankment and some channel modification work 
(Stage 2C1) has also been completed. 
7. BIG STONE LAKE AND WHETSTONE 
RIVER, MN AND SD 
Location. On Minnesota River near Ortonville and 
Odessa, MN, and Big Stone City, SD, at the outlet of Big 
Stone Lake and in Big Stone and Lac qui Parle Counties, 
MN, and Grant County, SD. (For general location, see 
Geological Survey map of Minnesota.) 
Existing Project. Provides for a dam and reservoir on 
Minnesota River above U.S. Highway 75, modification of 
Big Stone Lake outlet dam and silt barrier, bank stabilization 
along lower reach of Whetstone River, channel improvement 
on Minnesota River for 3 miles below outlet control dam at 
Big Stone Lake along with necessary relocations and 
acquisition of lands. These improvements would be made 
for wildlife conservation and development, flood control, and 
recreation. For additional details see Annual Report for 
1970. Project was authorized by 1965 Flood Control Act 
(H. Doc. 579, 87th Cong., 2d sess., contains latest map; and 
H. Doc. 193, 88th Cong., 2d sess.). 
Local Cooperation. Fully complied with. 
Operations and Results During Fiscal Year. Maintenance: 
Structure was operated and maintained and 
inspections and evaluations performed at a cost of $67,756 
by hired labor. Data collection and water control analysis 
cost $32,142. Data collection by other government agencies 
cost $33,520. Real estate management cost $628. 
Supervision and inspection were $10,106. 
Condition at End of Fiscal Year. Construction of the 
project is complete. A general plan between the Secretary 
of the Army and the Secretary of the Interior for 
administrating the use of waters, land, or interests therein 
has been consummated, and a cooperative agreement between 
the Corps of Engineers and the U.S. Fish and Wildlife 
Service was approved. On March 31, 1975, the Secretary 
of the Army transferred lands in the project not required for 
Corps of Engineers operation and maintenance to the 
Department of Interior. The transfer of property was 
24-4

ST. PAUL, MINNESOTA DISTRICT 
accepted by the Department of the Interior on May 21, 1975. 
The project was transferred to the Upper Minnesota River 
Watershed District for operation and maintenance. 
8. CHASKA, MN 
Location. In Carver County in south-central Minnesota on 
the Minnesota River. (For general location, see Geological 
Survey map of Minnesota.) 
Existing Project. The plan of improvement consists of a 
levee and interior drainage works along the Minnesota River, 
flood diversion channels on Chaska Creek and East Creek, 
and appropriate floodplain regulation measures. Principal 
project features include: approximately 1.1 miles of 
upgraded levee, 1.5 miles of new levee, and one pumping 
station on the Minnesota River; 1.1 miles of diversion 
channel on Chaska Creek; and 1.0 mile of diversion channel 
on East Creek. Approximately 2.9 miles of paved recreation 
trails on top of the levee and around Courthouse Lake are 
also included in the proposed plan. Estimated Federal cost 
(1992) for new work is $29,700,000 and $10,100,000 is to 
be contributed by local interests. Project was authorized by 
the 1976 Water Resources Development Act. (H. Doc. 644, 
94th Congress, 2d sess., contains latest published map.) 
Local Cooperation. See Annual Report for 1977 for 
requirements. A local cooperation agreement was executed 
on September 12, 1988. The agreement included cost 
sharing provisions in accordance with the 1986 Water 
Resources Development Act. 
Operations and Results During Fiscal Year. New Work: 
Real estate activities cost $13,195. Stage 2 construction 
contract cost $592,961. Engineering and design cost 
$488,280 by contract, $824,201 by hired labor, $3,000 by 
the Fish and Wildlife Service, and $31,483 by Missouri 
River Division. Construction management costs were 
$90,060. Cultural resources cost $9,008 by contract and 
$3,562 by hired labor. Total Federal costs were $950,558 
and non-Federal, $1,105,192. 
Condition at End of Fiscal Year. A contract for Stage 2 
of the flood control project was awarded in September, 1989 
and is substantially complete. Stage 1 construction is 
complete. Engineering work for remaining stages is 
underway. 
9. DEVILS LAKE, ND 
Location. In Ramsey County in north central North 
Dakota about 80 miles west of Grand Forks, North Dakota. 
(For general location, see Geological Survey map of North 
Dakota.) 
Existing Project. Involves a system of levees and interior 
flood control facilities at the head of Creel Bay. The main 
embankment across Creel Bay is 1,810 feet long and varies 
from 0 to 27 feet high. The south Creel Bay tieback 
embankment is 1,030 feet long and varies from 0 to 3 feet 
high. The north Creel Bay tieback embankment is 2,400 feet 
long and varies from 0 to 8.5 feet high. The south 
embankment is 3,100 feet long and varies from 0 to 9.5 feet 
high. 
The interior flood control system consists of temporary 
stormwater retention ponds immediately north and south of 
the city's sewage lagoons, a 16,000 gallon per minute 
pumping station and a system of ditches and culverts linking 
the ponds to the pumping station. 
The project was approved by the Chief of Engineers for 
construction August 15, 1983, under the authority contained 
in Section 205 of the 1948 Flood Control Act, as amended. 
Local Cooperation. See Annual Report for 1983 for 
requirements. A local assurance agreement required by 
Public Law 91-611 was adopted by the city of Devils Lake 
in August 1983. 
Operations and Results During Fiscal Year. New Work: 
Engineering and design cost $21,031. Construction 
management cost $12,245. 
Condition at End of Fiscal Year. Construction is 
complete. The project was turned over to the local interests 
by letter dated July 24, 1992. 
10. EAU GALLE RIVER, WI 
Location. At and in vicinity of Spring Valley, WI, on Eau 
Galle River 30 miles above its mouth at Chippewa River, 
and its tributary, Mines Creek, which flows through the 
village. Spring Valley is about 45 miles east of St. Paul, 
MN, and 36 miles west of Eau Claire, WI. (See Geological 
Survey map for Wisconsin for general location.) 
Existing Project. Authorized plan of improvement as 
modified by further studies includes a retarding dam and 
reservoir on Eau Galle River immediately upstream from 
Spring Valley, and remedial works on Mines Creek including 
channel enlargement, a low levee, and a drop structure. 
Project provides for earth and rock-fill dam, an uncontrolled 
outlet and an uncontrolled spillway emerging above Mines 
Creek. See page 1030 of Annual Report for 1965 for further 
details. Proposed improvements on Burghardt Creek were 
eliminated. Improvements provide complete protection near 
Spring Valley for standard project flood, and below that 
point in decreasing value in proportion to distance from 
24-5

REPORT OF THE SECRETARY OF TIlE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
reservoir. Permanent conservation pool will serve a local 
need for a recreational area. Project was authorized by 1958 
Flood Control Act (S. Doc. 52, 84th Cong., 1st sess., 
contains latest published map.) 
Local Cooperation. Fully complied with. See page 1083 
of Annual Report for 1967. 
Operations and Results During Fiscal Year. Maintenance: 
Structure and recreation facilities were operated and 
maintained, and inspections, investigations and evaluations 
were performed at a cost of $360,706 by hired labor and 
$69,889 by contract. Real estate management cost $2,908. 
Data collection cost $12,977 by hired labor and $7,150 by 
other government agencies. Water control analysis and 
water quality by other Corps of Engineer districts cost 
$10,997 and $-7,931, respectively. Water quality support 
for WES cost $7,781. Supervision and inspection costs were 
$29,521. 
Condition at End of Fiscal Year. Mines Creek 
improvements were substantially completed in 1964; minor 
work was accomplished in 1966. A contract for dam, 
spillway, and discharge channel, started July 1, 1965, was 
completed in October 1968. Recreational facilities have been 
provided. Remedial work to repair eroded gutters and road 
ditches was completed in September 1973. Repair of failing 
discharge conduit by installing a steel liner was completed in 
April 1982. 
11. EMERSON, MANITOBA--NOYES, MN 
Location. The unincorporated village of Noyes is located 
in Kittson County in extreme northwestern Minnesota about 
80 miles north of Grand Forks, North Dakota. Noyes is 
situated on the right overbank of the Red River of the North, 
approximately one-half mile from the channel. 
Existing Project. The project consists of a "ring" levee 
which protects both Noyes and the city of Emerson, 
Manitoba, Canada. The project comprised three basic 
components: upgrading the existing Emerson, Manitoba, 
emergency levee to provide 100-year flood protection; 
constructing a 3,800-foot-long levee at Noyes, Minnesota, to 
provide 100-year flood protection; and constructing a 
2,000-foot-long International levee in Minnesota parallel to 
the International boundary. The levees provide a complete 
and continuous levee system around the two communities. 
The levees have a 10-foot top width, side slopes of 1 vertical 
on 3 horizontal, and vary in height from 7 to 12 feet. The 
interior flood control facilities consist of two ponding areas 
and two gravity outlets. The project was approved by the 
Chief of Engineers for construction on July 26, 1988, under 
the authority contained in Section 205 of the 1948 Flood 
Control Act, as amended. 
Local Cooperation. See Annual Report for 1988 for 
requirements. A local cooperation agreement was signed by 
St. Vincent Township, Minnesota, the local sponsor, in 
August 1988. 
Operations and Results During Fiscal Year. New Work: 
Engineering and design cost $2,101. Federal costs were 
$-80,643, non-Federal $82,744. 
Condition at End of Fiscal Year. Construction is 
complete. The project was turned over to local interests by 
letter dated December 10, 1991. 
12. GRAND MOUND, STATE HISTORIC 
SITE, MN 
Location. Along the left (south) bank of the Rainy River 
on the northern boundary of the Grand Mound State Historic 
Site, about 17 miles west of International Falls, MN, at the 
confluence of the Rainy and Big Fork Rivers. 
Existing Project. The Grand Mound site is on the 
National Register of Historic Places because of its 
irreplaceable Indian burial mounds and other artifacts from 
the prehistoric Laurel and Blackduck cultures. Serious 
erosion is causing loss of skeletal remains and artifacts. A 
Feasibility Report and Environmental Assessment was 
completed in September 1989 under the authority of Section 
14 of the 1946 Flood Control Act, as amended. This report 
recommended riprap protection along 1,500 feet of riverbank 
with all work taking place from a "bench" constructed along 
the riverbank to keep equipment from disturbing the Indian 
mounds. The project was approved for construction by the 
Chief of Engineers on March 22, 1990. 
Local Cooperation. See Annual Report for 1990 for 
requirements. A local cooperation agreement was executed 
with the Minnesota Historical Society on June 20, 1990. 
Operations and Results During Fiscal Year. New Work: 
Engineering and design cost $3,028 by hired labor and $202 
by contract. Federal costs were $8,940, non-Federal -5,710. 
Condition at End of Fiscal Year. Construction is 
complete. The project was turned over to the local sponsor 
by letter dated January 15, 1992. 
13. HOMME LAKE AND DAM, ND 
Location. Dam is on South Branch of Park River about 4 
miles upstream from Park River, ND, and 62.1 miles above 
mouth of Park River. South, Middle, and North Branches, 
headwater streams of Park River, rise in Cavalier County in 
northeastern North Dakota and flow easterly to an almost 
common confluence near Grafton, ND, forming main stream 
24-6

ST. PAUL, MINNESOTA DISTRICT 
which flows easterly 35 miles to join Red River of the North 
about 35 miles south of the international boundary. (For 
general location, see Geological Survey map of North 
Dakota.) 
Existing Project. See Annual Report for 1962. Project 
was authorized as Park River Reservoir by 1944 Flood 
Control Act (S. Doc. 194, 78th Cong., 2d sess.), and 
redesignated Homme Reservoir and Dam by Public Law 435, 
80th Congress, 2d session. Project restoration of wetland 
habitat conditions is taking place under the authority 
contained in Section 1135 of the 1986 Water Resources 
Development Act, as amended. Latest published map is in 
project document. 
Local Cooperation. Fully complied with. Total costs for 
all requirements of local cooperation under terms of project 
authorization, including required non-Federal contributions, 
were $62,800. In addition, local interests contributed 
$16,220 for construction of a water supply outlet through 
dam and incurred other costs of $19,600. The North Dakota 
Game and Fish Department has agreed to serve as the non- 
Federal sponsor for the environment improvement to the 
project. 
Operations and Results During Fiscal Year. New Work: 
Engineering and design cost $8,939. Maintenance: 
Structure was operated and maintained, and inspections and 
evaluations performed at a cost of $106,578. 
Condition at End of Fiscal Year. Project completed in 
June 1956 except for additional recreational facilities which 
have been done intermittently since that time. Construction 
began in April 1948 and major structures completed in May 
1951. Structures are in good condition. Government has 
acquired 395 acres of land in fee and easements over 7.8 
acres of land for project. An additional 6.3 acres of land 
have been donated for recreational development and 3.75 
acres have been acquired due to bank erosion bordering the 
project. A construction contract for habitat improvement 
(under Section 1135 authority) was awarded in September 
1992. 
14. HOUSTON, MN 
Location. In Houston County in southeastern Minnesota 
on the Root River in the city of Houston, Minnesota. 
Existing Project. The plan of protection provides levee 
flood protection together with appropriate floodplain 
regulation measures. Main features of the project include 
3.1 miles of levee, one-half mile of road raises, channel 
excavation, interior drainage facilities, a flood warning 
system, utility modifications and a recreational trail. 
Estimated Federal cost (1992) for new work is $4,330,000 
and $1,540,000 is to be contributed by local interests. The 
project was approved for construction by the 1986 Water 
Resources Development Act (Public Law 99-662) and has 
been reevaluated based on changes since the 1975 Feasibility 
Report. 
Local Cooperation. See Annual Report for 1988 for 
requirements. By a resolution dated April 8, 1991, the city 
of Houston expressed its commitment to the financial 
requirements of the project. The city reaffirmed its 
commitment by letter dated May 6, 1992. 
Operations and Results During Fiscal Year. New Work: 
Preconstruction engineering and design continued at a cost of 
$338,239. 
Condition at End of Fiscal Year. 
engineering and design is in progress. 
Preconstruction 
15. LAC QUI PARLE LAKES, MINNESOTA 
RIVER, MN 
Location. Works covered by this project lie along Marsh 
Lake and Lac qui Parle and the Minnesota River between 
head of Marsh Lake and Granite Falls, MN. (For general 
location, see Geological Survey map of Minnesota.) 
Existing Project. See Annual Report for 1962. 
Local Cooperation. None required. 
Operations and Results During Fiscal Year. Maintenance: 
Project was operated and maintained, and inspections 
and evaluations were performed at a cost of $234,421 by 
hired labor and $5,805 by contract. Data collection cost 
$63,331 by hired labor, $770 by contract, and $43,040 by 
U.S. Geological Survey. Water control analysis cost 
$38,003. Water quality analysis cost $30,767 by hired 
labor, $24,990 by other Corps offices and $485 by contract. 
Real estate cost $3,643. Engineering and design and 
supervision and inspection cost $867 and $28,399, 
respectively. 
Condition at End of Fiscal Year. Project has been 
operated by the Government since transfer from State of 
Minnesota to the United States in September 1950. The 
United States owns fee title to 517.62 acres of land and 
easements on 19,859.47 acres of land. In 1957, 60.1 acres 
were withdrawn from public lands for use by the Department 
24-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
of the Army. Land acquisition is complete. Construction 
under present plan of improvement was started in September 
1941 and completed in December 1951 except for 
recreational facilities. All structures are in good condition. 
16. LA FARGE LAKE AND CHANNEL 
IMPROVEMENT, WI 
Location. On the Kickapoo River which rises in Monroe 
County in southwestern Wisconsin and flows south and 
southwest through Vernon, Richland, and Crawford Counties 
emptying into Wisconsin River about 16 miles above junction 
of latter stream with Mississippi River. (For general 
location see Geological Survey map of Wisconsin.) 
Existing Project. Provides for a dam and impoundment of 
the Kickapoo River about 1 mile upstream from village of La 
Farge, operated for flood control, fish and wildlife 
conservation, general recreation, and a reduction of 
aggradation downstream from the dam, and supplemental 
protection at Soldiers Grove and at Gays Mills by means of 
levees, supplementary channel improvement, and interior 
drainage facilities. See Annual Report for 1975 for details. 
Estimated Federal cost (1976) for new work is 
$55,400,000. Project was authorized by 1962 Flood Control 
Act (H. Doe. 557, 87th Cong., 2d sess., contains latest 
published map.) 
Local Cooperation. None required for construction of La 
Farge Lake. See Annual Report for 1967 for requirements 
for local protection works. Local interests have not been 
requested to furnish assurances. 
Operations and Results During Fiscal Year. Maintenance: 
Project was operated and maintained at a cost of 
$81,092. 
Condition at End of Fiscal Year. General and Real 
Estate design memorandums and detailed plans for the La 
Farge Dam and spillway and for relocations have been 
completed. Land acquisition negotiations began in December 
1968. The first land payment was made on January 15, 
1969, and the land acquisition program is 80 percent 
complete. Contracts for excavation of the left abutment, for 
test wells, and for construction of the outlet works and right 
abutment have been completed. A study of alternatives has 
been completed. All further construction has been 
indefinitely suspended. Work has been accomplished to 
provide for completion of relocation work left partially 
completed when construction was suspended. Soldiers Grove 
has relocated out of the floodplain area after receiving funds 
from other agencies. A study of a modified dry dam was 
completed in early FY 1985. On the basis of the study 
results, it was recommended that no further work be done to 
establish the economic feasibility of a dry or wet dam at La 
Farge and that the La Farge Lake and channel improvement 
project be deauthorized. 
17. LAKE ASHTABULA AND BALDHILL 
DAM, SHEYENNE RIVER, ND 
Location. Baldhill Dam is on the Sheyenne River, 16 
miles upstream from Valley City, ND, and about 271 miles 
above mouth. Sheyenne River rises in central North Dakota 
and flows 500 miles generally southeast to enter Red River 
of the North about 10 miles north of Fargo, ND. (For 
general location see Geological Survey map of North 
Dakota.) 
Existing Project. See Annual Report for 1962. Project 
was authorized by Flood Control Act of 1944 (S. Doc. 193, 
78th Cong., 2d sess., contains latest published map). 
Reservoir above Baldhill Dam was designated as Lake 
Ashtabula by Public Law 772, 81st Congress, 2d session. 
Local Cooperation. See Annual Report for 1962. 
Complied with. 
Operations and Results During Fiscal Year. Dam 
Safety: Engineering and design cost $19,977 by hired labor, 
and $5 by other Corps and an adjustment of $-29,406 was 
made on a contract. Maintenance: Project was operated and 
maintained, and inspections, investigations, monitoring and 
evaluations were performed at a cost of $515,423 by hired 
labor and $34,124 by contract. Real estate management cost 
$35,117. Data collection cost $55,166 by hired labor, 
$60,320 by other government agencies, and $22,005 by 
contract. A law enforcement contract cost $6,800. Water 
quality analysis by hired labor cost $4,944. Spurge control 
cost $16,197 by contract and $10,934 by hired labor. 
Engineering and design cost $135,983 by hired labor and 
$174,559 by other Corps offices. Supervision and inspection 
and other costs were $99,669. 
Condition at End of Fiscal Year. Project completed in 
March 1956 except construction of recreational facilities 
which is being accomplished intermittently. United States 
owns 7,816.5 acres of land in fee and easements on 666.2 
acres. Construction initiated in July 1947 and major features 
completed in November 1950. Dam was placed in 
permanent operation in spring of 1951. Structures are in 
good condition. Baldhill Dam has been classified as a large, 
high hazard dam under the National Program for the 
inspection of dams. A risk assessment report prepared in 
June 1986 indicated a serious spillway discharge capacity 
24-8

ST. PAUL, MINNESOTA DISTRICT 
deficiency. A General Design Memorandum which 
recommended increasing the spillway capacity was approved 
by OCE in July 1987. 
18. LAKE TRAVERSE AND BOIS DE SIOUX 
RIVER, SD AND MN 
Location. Works covered by this project lie along Lake 
Traverse and Bois de Sioux River between upper end of 
Lake Traverse at Browns Valley, MN, and the mouth of 
Bois de Sioux River at Breckenridge, MN. Lake drains 
through river to Red River of the North, and two waters 
form a portion of boundary between State of Minnesota and 
States of North and South Dakota. (For general location, see 
Geological Survey map of Minnesota.) 
Existing Project. See Annual Report for 1962. Existing 
project was authorized by Flood Control Act of June 22, 
1936. 
Local Cooperation. None required. 
Operations and Results During Fiscal Year. Maintenance: 
Project and related facilities were operated and 
maintained, and inspections and evaluations performed at a 
cost of $399,599. 
Condition at End of Fiscal Year. Existing project was 
completed in June 1948, except for minor recreational 
facilities. Fee title to 1,144.13 acres and easements on 
6,172.25 acres of land have been acquired. White Rock 
Dam and Reservation control structures are in operation, and 
structures and appurtenances are in good condition. 
Remedial work for repair of apron at White Rock Dam was 
completed in November 1968. Roadways across structure 
are open to public travel. 
19. MANKATO AND NORTH MANKATO, 
MN 
Location. Along Minnesota River between miles 103.5 
and 109.5 near Mankato, North Mankato, and Le Hillier, in 
south-central Minnesota. (For general location see 
Geological Survey map of Minnesota.) 
Existing Project. As modified as a result of severe 1965 
flood, provides for protection of communities of Mankato, 
North Mankato, and Le Hillier by means of levees and 
floodwalls with pumping plants and interior drainage 
facilities. See page 1090 of Annual Report for 1967 for 
further details. Additional channel improvement, levees, 
pumping, and interior drainage features have been included 
in the Mankato unit of the project for protection from the 
high flows of Indian Creek. Expansion of Indian Creek 
improvements were made during detailed studies as a result 
of updated hydrologic data. Highway bridge relocations 
made necessary by the project have been authorized at 
Federal expense. Project was authorized by 1958 Flood 
Control Act (H. Doe. 437, 84th Cong., 2d sess., contains 
latest published map.) Project was modified by 1965 Flood 
Control Act, and by the Water Resources Development Acts 
of 1974 and 1976. 
Local Cooperation. Fully complied with. 
Operations and Results During Fiscal Year. 
Miscellaneous contract adjustments were made for 
$-326,435. Administration, audit and other miscellaneous 
costs were $4,925. 
Condition at End of Fiscal Year. Construction of the 
project is complete. 
20. MARSHALL, MN 
Location. In Lyon County in southwestern Minnesota 
along the Redwood River about 68 miles above its 
confluence with the Minnesota River at the city of Marshall, 
Minnesota. (For general location see Geological Survey map 
for Minnesota.) 
Existing Project. See page 1059 of Annual Report for 
1964 for completed channel improvement project authorized 
by 1960 Flood Control Act. Federal costs amounted to 
$1,802,866. The existing flood control project was 
completed in 1963. In response to a need for additional 
flood control, a feasibility study was completed in 1979. 
The project recommended in the feasibility report was 
authorized by the Water Resources Development Act of 
1986, Public Law 99-662, Section 401(a) and reauthorized 
by the Water Resources Development Act of 1988, Public 
Law 100-676. Improvements include 4.7 miles of additional 
levees, 3.8 miles of bank protection, 0.3 mile of new 
high-flow diversion channel, an interbasin overflow 
structure, modifications to the existing diversion and drop 
structures, and a recreation plan. The recreation plan 
consists of 2.5 miles of biking/walking trail, five miles of 
cross-country skiing/hiking trail, and related picnic and rest 
area facilities. The project would provide protection against 
a flood having an occurrence interval of about once in 115 
years. Estimated Federal cost (1992) for new work is 
$6,600,000 and $2,500,000 is to be contributed by local 
interests. 
Local Cooperation. Fully complied with for completed 
work. Project was transferred to local interests on 
December 23, 1963. 
For new work, see Annual Report for 1985 for 
requirements. By letter dated June 26, 1989, the city of 
24-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Marshall indicated its willingness to participate financially in 
construction of a project consistent with the cost sharing and 
financing concepts reflected in the 1986 Water Resources 
Development Act. 
Operations and Results During Fiscal Year. New Work: 
Preconstruction engineering and design was continued at a 
cost of $24,292. 
Condition at End of Fiscal Year. Construction of 
completed work was initiated August 1962 and completed 
December 1963. Preconstruction engineering and design for 
the new work is in progress. 
21. MIDDLE RIVER AT ARGYLE, MN 
Location. In Marshall County in northwestern Minnesota 
on the Middle River within the city limits of Argyle, 
Minnesota. 
Existing Project. The plan of protection includes a system 
of levees, road raises along with interior drainage facilities 
to provide main developed parts of the city of Argyle with 
one percent chance flood protection. Also included is the 
evacuation of 12 residences which are located outside of the 
line of flood barrier protection. The project was approved 
for construction on August 1, 1985 by the Chief of 
Engineers. The project is being constructed under the 
authority of Section 205 of the 1948 Flood Control Act, as 
amended. 
Local Cooperation. See Annual Report for 1985 for 
requirements. A local assurance agreement required by 
Public Law 91-611 was adopted by the city of Argyle in 
August 1985. 
Operations and Results During Fiscal Year. New Work: 
Real estate costs were $1,582. A construction contract cost 
$2,240. Engineering and design cost $12,558 by hired 
labor. Construction management costs were $43,163. 
Condition at End of Fiscal Year. Construction is 
complete. 
22. MINNESOTA RIVER AT HENDERSON, 
MN 
Location. In Sibley County in southeastern Minnesota 
about 50 miles southwest of Minneapolis, Minnesota. (For 
general location, see Geological Survey map of Minnesota.) 
Existing Project. The project at Henderson involves a 
system of levees to protect the flood prone areas of the city 
from floods on the Minnesota River. The proposed levee is 
about 1.6 miles long and has an average height of 12 feet. 
Appurtenant interior flood control facilities include a system 
of interceptor stormsewers and ditches, and two ponding 
areas each with a gravity outlet and a pumping station 
designed to discharge impounded storm water during flood 
periods when exterior flood levels would require the gravity 
outlets to be closed. Provisions for the temporary closure of 
two state highways and a county highway are also included 
as project features. The project was approved by the Chief 
of Engineers for construction June 26, 1987, under the 
authority contained in Section 205 of the 1948 Flood Control 
Act, as amended. 
Local Cooperation. See Annual Report for 1988 for 
requirements. A local assurance agreement was adopted by 
the City of Henderson, the local sponsor, in May 1988. 
Operations and Results During Fiscal Year. New Work: 
Real estate costs were $817. A construction contract cost 
$47,307. Equipment was purchased for $4,644. 
Engineering and design cost $8,321 by hired labor. 
Construction management cost $347. Federal costs were 
$10,248 while non-Federal were $51,188. 
Condition at End of Fiscal Year. Construction of the 
project was substantially complete at the end of the fiscal 
year. 
23. PORTAGE, WI 
Location. In Columbia County in central Wisconsin along 
the Wisconsin River about 35 miles north of Madison, 
Wisconsin. (For general location see Geological Survey map 
for Wisconsin.) 
Existing Project. The recommended plan provides for 
improvement to the existing levee system along the left bank 
of the Wisconsin River at Portage. The plan includes 1.2 
miles of existing levee improvement; 1.7 miles of new levee; 
2 tie-back levees; one highway and two railroad closures; 
cultural mitigation; and recreation features. The project 
would protect against a flood having an occurrence interval 
of about once in 500 years. Estimated Federal cost (1992) 
for new work is $6,400,000 and $2,240,000 is to be 
contributed by local interests. Project was authorized by the 
Water Resources Development Act of 1986 (Public Law 
99-662). 
Local Cooperation. See Annual Report for 1989 for 
requirements. By Council Resolution dated June 25, 1992, 
the city of Portage indicated a willingness and intention to 
meet the requirements of local cooperation for flood control 
and recreation, subject to reaching agreement with the state 
of Wisconsin on cost-sharing responsibilities. A draft local 
cooperation agreement will be prepared during 
preconstruction planning and will be negotiated and finalized 
prior to initiation of construction. 
24-10

ST. PAUL, MINNESOTA DISTRICT 
Operations and Results During Fiscal Year. New Work: 
Preconstruction engineering and design was continued at a 
cost of $480,801. 
Condition at End of Fiscal Year. 
engineering and design is in progress. 
Preconstruction 
24. RED LAKE RIVER, MN, INCLUDING 
CLEARWATER RIVER, MN 
Location. Works covered by this project lie along upper 
reach of Red Lake River and also along Clearwater River, 
a tributary of Red Lake River, between a point near 
Plummer, MN, and a point just above the mouth of Ruffy 
Brook. Red Lake River, principal tributary of the Red River 
of the North, has its source at the outlet of Lower Red Lake 
in northwestern portion of Minnesota and flows westerly 
about 196 miles to its junction with Red River of the North 
at East Grand Forks, MN. Clearwater River has a general 
westerly course from its source near Ebro, MN, about 205 
miles to its junction with Red Lake River at Red Lake Falls, 
MN. (For general location, see Geological Survey map of 
Minnesota.) 
Existing Project. See Annual Report for 1962. Project 
was authorized by 1944 Flood Control Act (H. Doc. 345, 
78th Cong., 1st sess., contains latest published map.) 
Local Cooperation. Fully complied with. 
Operations and Results During Fiscal Year. Maintenance: 
Structures were operated and maintained and 
inspections and evaluations performed at a cost of $85,482. 
Condition at End of Fiscal Year. Construction of major 
improvements on Red Lake River and the Clearwater River 
were completed in June 1956. Replacement of rock and 
brush dam on Red Lake River at Indian boundary with a 
concrete structure and appurtenant work was completed in 
June 1959 to restore marshes in the area to better wildlife 
conditions. Construction of a bridge on Clearwater Road 
was completed by the Indian Service in July 1965. A 
contract for improvements on Red Lake River was completed 
in November 1966, and a contract for restoration of water 
levels in Red Lake River marshes was completed in 
November 1968. Operation of Red Lake Dam was assumed 
by the Corps on April 1, 1951. Channels are in good 
condition and indicate effectiveness of project as a flood 
control measure. 
25. RED RIVER OF THE NORTH AT 
FARGO, ND - MOORHEAD, MN 
Location. A 9.7-mile reach of the Red River of the North 
within the Fargo, ND - Moorhead, MN metropolitan area. 
Existing Project. Dutch elm disease is causing an 
epidemic of dead and dying trees along the riverbanks. 
When these trees topple into the river, they get hung up at 
bridges, sharp bends, and sandbars. The resulting increases 
in channel roughness and number and size of flow blockages 
raise flood stages and escalate flood damages. The Detailed 
Project Report dated March 1989 was conducted under the 
authority of Section 208 of the 1954 Flood Control Act, as 
amended. This report recommended removing fallen trees 
from the channel and riverbanks and standing, but dead or 
dying, trees close to the edge of the riverbank to alleviate 
existing and potential threats. The project was approved for 
construction by the Chief of Engineers on December 27, 
1989. 
Local Cooperation. See Annual Report for 1990 for 
requirements. A local cooperation agreement was executed 
with the Fargo-Moorhead Metropolitan Council of 
Governments on January 9, 1990. 
Operations and Results During Fiscal Year. New Work: 
Engineering and design cost $2,864. Total Federal costs 
were $4,469, non-Federal $-1,605. 
Condition at End of Fiscal Year. Construction is 
complete. The project was turned over to the local sponsor 
by letter dated December 30, 1991. 
26. RED RIVER OF THE NORTH 
DRAINAGE BASIN, MN, SD & ND 
Location. Red River of the North Basin, within the United 
States, includes northeastern corner of South Dakota and 
much of eastern North Dakota and northwestern Minnesota. 
Red River of the North, formed by confluence of Otter Tail 
and Bois de Sioux Rivers, flows northward through this 
region, forming boundary between North Dakota and 
Minnesota. (For general location of basin, see Geological 
Survey maps of Minnesota and South Dakota.) 
Previous project. See Annual Report for 1962 for 
navigation and flood control projects in the basin, not part of 
this project. 
Existing Project. Project includes improvements for local 
protection in interests of flood control and major drainage 
accomplished by channel improvement, levees, etc., in 
addition to construction of a multiple purpose reservoir on 
Otter Tail River to control floods and, in conjunction with 
previously authorized Federal reservoir project at Baldhill 
site of Sheyenne River and at Red Lake, to increase low 
flows for water supply and pollution abatement. (See Table 
27-I for active units in comprehensive basin plan.) 
Project was authorized by Flood Control Acts of 1948 and 
1950. Public Works Authorization Act, 1957, authorized 2- 
24-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Chief of Engineers to acquire such lands as were beyond 
legal authority of the city of Grand Forks to acquire. 
Section 205 of the Flood Control Act of 1970 provided for 
extension of the expiration date for the East Grand Forks 
project. Authorization of the Sheyenne River (Kindred Lake) 
project by the 1970 Flood Control Act provided for the 
deletion of channel improvement on the lower 48.8 miles of 
the Sheyenne River authorized under the Flood Control Acts 
of 1948 and 1950. Latest published map is in House 
Document 185, 81st Congress, 1st session. 
Local Cooperation. See Annual Report for 1965. 
Following the flood of 1965, the city of East Grand Forks 
requested reactivation of the project and furnished a 
resolution adopted May 11, 1965, indicating its willingness 
to meet the requirements of local cooperation. Expiration 
date for the East Grand Forks project was extended to April 
17, 1975, permitting local interests additional time to furnish 
assurances of local cooperation. A local assurance 
agreement was passed by the city on March 27, 1975, and 
accepted by the acting Director of Real Estate, OCE for the 
Secretary of the Army on April 9, 1975. In a July 9, 1986 
letter, the city of East Grand Forks withdrew support for the 
project presented in the General Design Memorandum. 
Operations and Results During Fiscal Year. Maintenance: 
Orwell Lake and Dam were operated as required and 
miscellaneous inspections, reports, and repairs were made at 
a cost of $289,179 by hired labor, $1,999 by other 
government, and $12,487 by contract. Real estate 
management cost $2,595. Data collection cost $17,284 by 
hired labor and $19,140 by U.S. Geological Survey. Water 
control cost $15,888 and drought contingency planning 
$5,750 by hired labor and $6,995 by other Corps. 
Engineering and design for dam safety cost $35,368 by hired 
labor. An adjustment for engineering and design for a 
spillway GDM was made for $-11,964 by other Corps. 
Supervision and inspection and other miscellaneous costs 
were $31,462. 
Condition at End of Fiscal Year. Major construction for 
all active units except for East Grand Forks, MN, is 
complete. The East Grand Forks project was reclassified 
from active to inactive status on August 19, 1988. A total 
of 1,985 acres of land for Orwell Lake and Dam is owned in 
fee by the United States. See page 1281 of Annual Report 
for 1962 for periods of completion at active units of project 
other than Fargo. Work at Fargo, ND, started in May 1959, 
was completed in July 1963. (See Table 24-I at end of 
chapter for total costs of new work to date.) 
27. ROCHESTER, MN 
Location. In Olmsted County in southeastern Minnesota 
on the South Fork of the Zumbro River. (For general 
location, see Geological Survey map of Minnesota.) 
Existing Project. Provides for stream channel 
modifications and levees functioning in combination with a 
system of seven headwaters reservoirs. Principal features, 
in addition to the reservoirs, include 5.7 miles of riprapped 
or gabion-lined channels, 0.7 mile of architecturally-treated 
concrete channels, 0.5 mile of dredged channel, three drop 
structures, 1.8 miles of levee, and 6.5 miles of hiking and 
biking trails. Estimated cost (1992) to the United States for 
new work is $79,400,000 and $29,000,000 is to be 
contributed by local interests. Project was authorized by the 
Water Resources Development Act of 1986 (H. Doc. 156, 
93rd Cong., 1st sess., contains latest published map.) 
Local Cooperation. See Annual Report for 1974 for 
requirements. A local cooperation agreement was signed 
August 27, 1987 by the city of Rochester. 
Operations and Results During Fiscal Year. New Work: 
Construction contracts for Stage 1A2A, 1B1, 1B3, 2A and 
2B cost $4,414, $7,402, $1,079,375, $111,999, and 
$5,900,101, respectively. Engineering and design cost 
$727,080 by contract and $1,833,570 by hired labor. 
Construction management cost $572,453 by hired labor and 
$47,218 by contract. Total Federal costs were $9,426,457 
and non-Federal costs were $857,155. 
Condition at End of Fiscal Year. Construction is 
complete on Stages 1A2A, 1A2B, 1A1, 1B1, and 1B3. 
Construction is underway on Stages 2A and 2B. 
28. ROOT RIVER AT HOKAH, MN 
Location. In Houston County in southeastern Minnesota 
on the Root River at Hokah about 140 miles southeast of 
Minneapolis - St. Paul. 
Existing Project. Provided for erosion control along about 
1,500 feet of the south bank of the Root River at the 
wastewater treatment plant serving Hokah. The project 
consisted of clearing and snagging, excavation, placing rock 
fill and extending the concrete pipe outfall at the treatment 
plant. The project was approved for construction by the 
Chief of Engineers on April 27, 1990 under the authority 
contained in Section 14 of the 1946 Flood Control Act, as 
amended. 
Local Cooperation. See Annual Report for 1990 for 
requirements. A local cooperation agreement was executed 
by Houston County on May 1, 1990. 
Operations and Results During Fiscal Year. Funds in 
the amount of $4,373 were returned to the U.S. Treasury. 
Condition at End of Fiscal Year. Project was completed 
and transferred to the local sponsor in January 1991. 
24-12

ST. PAUL, MINNESOTA DISTRICT 
29. ROSEAU RIVER, MN 
Location. In Roseau County on the Roseau River in 
northwestern Minnesota near the city of Duxby. (For 
general location see Geological Survey map of Minnesota.) 
Existing Project. See Annual Report for 1988 for 
description of project as authorized by the Flood Control Act 
of 1965. The project, as modified by the Water Resources 
Development Act of 1988, provided for construction of about 
6 miles of flood control levee approximately 3 feet high in 
the vicinity of Duxby, Minnesota. Estimated cost (1990) to 
the United States for new work on the modified project is 
$356,000 and $119,000 is to be contributed by local 
interests. 
Local Cooperation. See Annual Report for 1968 for 
requirements of project as authorized by the Flood Control 
Act of 1965. See Annual Report for 1991 for requirements 
of modified project. 
Operations and Results During Fiscal Year. New Work: 
Construction contract costs were $65,795. Engineering and 
construction management costs were $10,109 and $8,350, 
respectively. Total Federal costs were $61,799 and non- 
Federal costs were $22,455. 
Condition at End of Fiscal Year. A construction contract 
for the Duxby levee project was awarded in July 1991. 
Construction is essentially complete. 
30. SHEYENNE RIVER, NDI) 
Location. The Sheyenne River Basin is included in 16 
counties in the southeastern portion of North Dakota and 
drains an area of 7,140 square miles into the Red River of 
the North near Fargo, North Dakota. The principal area of 
flood damages in the basin is located at the lower end within 
Cass County and the city of West Fargo. (For general 
location, see Geological Survey map of North Dakota.) 
Existing Project. The project as authorized by the 1986 
Water Resources Development Act consists of three major 
components for Federal implementation: 1) 11.9 miles of 
levee and a 6.7 mile flood diversion channel at West Fargo; 
2) 7.5 miles of flood diversion channel from Horace to West 
Fargo; and 3) a five-foot raise of the Baldhill Dam flood 
control pool. The Water Resources Development Act of 
1986 stipulated that the project shall also include a dam and 
reservoir of approximately 35,000 acre-feet of storage for the 
purpose of flood protection on the Maple River. There are 
several items of local cooperation required to implement the 
plan, and several components identified for non-Federal 
implementation which would supplement the recommended 
plan. Estimated cost (1992) to the United States for new 
work is $29,580,000 and $15,980,000 is to be contributed by 
local interests. 
Local Cooperation. See Annual Report for 1988 for 
requirements. Project consists of three separable components 
each requiring a local cooperation agreement. The Southeast 
Cass Water Resource District is the local sponsor for the 
West Fargo Unit and the Horace to West Fargo Unit. The 
local cooperation agreement for the West Fargo Unit was 
executed on July 25, 1988, and for the Horace to West 
Fargo unit on March 6, 1990. The State Water Commission 
will serve as the quasi-sponsor for the Baldhill Dam flood 
control pool raise unit until a formal sponsorship is 
determined by benefiting entities. The Maple River 
Reservoir Unit has been deleted from the project. 
Operation and Results During Fiscal Year. New Work: 
Construction contracts at West Fargo for railroad relocations, 
channels, levees, pumping plants and diversion structures 
cost $4,000, $1,466,775, $70,000, $5,000 and $1,939, 
respectively. An adjustment was made for the railroad 
bridge construction contract, which resulted in a decrease of 
$36,027. Engineering and design cost $100,700 by hired 
labor and $38,702 by contract. Construction management 
cost $50,557 by contract and $244,536 by hired labor. 
Construction contracts at Horace for channels and levees 
cost $1,132,307 and $290,857, respectively. Engineering 
and design at Horace cost $57,610. For Baldhill Dam, 
engineering and design cost $12,978. 
For the Maple River Reservoir, engineering and design cost 
$3,274. Total Federal costs were $3,050,299 and non- 
Federal costs were $392,909. 
Condition at End of Fiscal Year. Construction of both 
the West Fargo and Horace to West Fargo Units are under 
way. Evaluation of real estate needs for the raise of the 
flood pool at Baldhill Dam has been initiated. The Maple 
River Reservoir unit has been deleted from the project due 
to lack of economic justification. 
31. SOURIS RIVER BASIN, ND 
Location. On the Souris River in Ward, Renville, 
McHenry, and Bottineau Counties in northwestern North 
Dakota. The existing Lake Darling Dam is located about 20 
miles northwest of Minot, North Dakota. The project also 
includes features at the communities of Sawyer and Velva 
and at various locations along the 358-mile U.S. portion of 
the Souris River. (For general location see Geological 
Survey map of North Dakota.) 
Existing Project. The current plan of improvement 
authorized by the Water Resources Development Act of 1986 
24-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
is the one-time purchase of 377,800 acre-feet of flood 
storage in Rafferty and Alameda Dams in Saskatchewan, 
Canada and the operation of these dams with the existing 
Boundary Dam and Lake Darling Dam to provide 100-year 
flood protection at Minot, North Dakota. The Act also 
authorizes those flood control measures upstream and 
downstream of the dam which are necessary for effective 
operation of the project. The 4-foot raise of the Lake 
Darling design pool (authorized by Section III of the Energy 
and Water Development Appropriations Act, 1982, PL 97- 
88) and the construction of Burlington Dam (authorized by 
PL 91-611) will no longer be authorized upon completion of 
the structure(s) in Canada. An International Agreement 
between Canada and the United States was signed in October 
1989. 
The work under the current plan authorized by PL 99-662, 
consists of either one or two reservoirs in Saskatchewan, 
Canada (known as the Rafferty and Alameda projects); a 
modified outflow structure at Lake Darling Dam; a flood 
warning system for Minot; levee and channel improvements 
at Sawyer and six subdivisions from Burlington to Minot; 
levee and diversion channel at Renville County Park; flood 
proofing of about 90 rural homes in the basin and the 
purchase of flowage easements; modifications to dams 87 
and 96 in the Upper Souris National Wildlife Refuge; and 
modifications to dams 320, 326, 332, 341 and 357 in the J. 
Clark Salyer National Wildlife Refuge. Estimated Federal 
cost (1992) for new work is $118,400,000 and $8,180,000 
is to be contributed by local interests. 
Local Cooperation. See Annual Report for 1983 for 
requirements. Representatives of the water resource districts 
from Ward, Renville, McHenry, and Bottineau Counties area 
agreed to become members of a Souris River Joint Board for 
flood control, which would serve as local sponsor for the 
project. A local cooperation agreement for construction at 
Velva was signed in November 1984. A local cooperation 
agreement for the remainder of the project as authorized by 
the Water Resources Development Act of 1986 was signed 
in October 1989. 
Operation and Results During Fiscal Year. New Work: 
Engineering and design and supervision and administration 
costs for Velva were $17,070. Preconstruction planning for 
the Souris River basin reservoir continued. Respective costs 
for the applicable sub-projects are as follows: 
Miscellaneous contracts and work by others costs were 
$265,635. Burlington to Minot stages 1, 2, 3, and 4, costs 
were $217,445 by hired labor and $1,913,190 by contract. 
Sawyer improvement costs were $26,751 by hired labor and 
an adjusted decrease of $1,136 by contract. Rural 
improvement costs were $67,935 by hired labor and 
$173,198 by contract. Refuge structures costs were 
$402,007 by hired labor and $5,399,077 by contract. 
Renville County Park improvement costs were $96,061 by 
hired labor and $1,074,133 by contract. Cash contributions 
for the Rafferty and Alameda Dams were $9,178,887 and 
$6,257,909 respectively. Canadian dams design and 
construction review costs were $8,459. Lake Darling Dam 
improvement costs were $933,932 by hired labor and 
$68,054 by contract. Flood warning systems costs were 
$42,480 by hired labor. Study and project management costs 
were $145,610 by hired labor. Rural flowage easements 
costs were $32,126 by hired labor and $12,773 by contract. 
Total Federal costs were $22,613,290, non-Federal costs 
$3,718,306. 
Condition at End of Fiscal Year. Construction of the 
channel and levee improvement work at Velva, Sawyer, 
Burlington to Minot Stages 1, 2, and 3 is complete. 
Construction at Rafferty Dam is complete. Construction at 
Alameda Dam is nearly complete. Engineering and design 
is continuing on modifications at Lake Darling Dam and the 
flood warning system at Minot. Construction on rural 
improvements Stage 1, road raises and acquisitions, is 
complete. Construction on improvements to Fish and 
Wildlife Service refuge dams is substantially complete. 
Renville County Park construction is nearing completion. 
32. STATE ROAD AND EBNER COULEES, 
WI 
Location. In La Crosse County in west-central Wisconsin, 
on the south side of the City of La Crosse. (For general 
location, see Geological Survey map of Wisconsin.) 
Existing Project. The plan of improvement for local 
protection (flood control) consists of channel deepening and 
enlarging downstream from Hagen Bridge to the mouth of 
Pammel Creek and includes 13,600 feet of concrete-lined 
rectangular channel, a drop chute inlet structure, a side 
channel inlet structure, a stilling basin, a terminus structure, 
and three new street bridges. The upper 4,000 feet of 
rectangular channel is designed for supercritical flow and the 
remaining 9,600 feet of channel is designed for subcritical 
flow. When completed, the project will provide Standard 
Project Flood (SPF) protection. The city replaced a fourth 
bridge in 1980 that was previously included in the authorized 
plan. The city also replaced a railroad bridge in 1985 that 
was also included in the authorized plan. In 1986, the city 
constructed 450 feet of rectangular channel in the 
downstream reach to SPF protection. Estimated cost (1992) 
to the United States for new work, exclusive of the Ebner 
Coulee portion of the project which was deleted due to lack 
of economic feasibility, is $21,200,000 and $7,100,000 is to 
be contributed by local interests including a credit of 
$1,000,000 for advance construction work. Project was 
authorized by 1968 Flood Control Act (H. Doc. 360, 90th 
Cong., 2d sess., contains published map.) 
24-14

ST. PAUL, MINNESOTA DISTRICT 
Local Cooperation. See Annual Report for 1969 for 
requirements. The local sponsor withdrew support for the 
project in 1976 citing increased non-Federal costs and lack 
of agreement on local cost sharing between three local units 
of government located within the project area. The project 
was reclassified as inactive on April 7, 1977, but was 
reactivated on November 8, 1978, after the La Crosse 
County Board of Supervisors, the La Crosse City Council, 
and the Town of Shelby passed separate resolutions on 
September 17, 1978, July 13, 1978, and July 10, 1978, 
respectively, which requested continuance of the project. A 
local cooperation agreement between the Department of the 
Army and the City of La Crosse, Wisconsin, for the 
construction of the State Road flood control project was 
entered into August 11, 1988. 
Operations and Results During Fiscal Year. New Work: 
A stage 2 construction contract cost $2,919,333 and a stage 
3 contract cost $3,099,991. Real estate costs were $34,643. 
Cultural resources cost $37,592 by hired labor and $23,568 
by contract. Engineering and design cost $206 by contract, 
$166,701 by hired labor and $4,500 by other Corps. 
Construction and management costs were $280,791 by hired 
labor and $10,309 by contract. Total Federal costs were 
$4,630,130, non-Federal $1,947,504. 
Condition at End of Fiscal Year. A construction contract 
for Stage 1 (outlet structure to Broadview Place) was 
completed in July 1990. A construction contract for Stage 
2 (middle segment) was completed in September 1992. 
Construction of the last stage is continuing. 
33. ST. PAUL, MN 
Location. In Ramsey County at St. Paul, Minnesota, on 
the Mississippi River. (For general location see Geological 
Survey map of Minnesota.) 
Previous project. For details see page 27-20 of Annual 
Report for 1974. 
Existing Project. Since completion of the St. Paul and 
South St. Paul flood control project in 1964, the protected 
area has experienced two floods greater than the previous 
flood of record. The plan of protection provides for a 
nominal 4-foot barrier raise along the existing project 
alignment. Estimated cost (1992) to the United States for 
new work is $10,900,000 and $8,740,000 is to be 
contributed by local interests. Project was authorized by the 
Water Resources Development Act of 1986 (Public Law 
99-662) and reauthorized by the Water Resources 
Development Act of 1990 (Public Law 101-640). 
Local Cooperation. See Annual Report for 1988 for 
requirements. The local cooperation agreement was executed 
on August 22, 1991. 
Operations and Results During Fiscal Year. New Work: 
Real estate activities cost $22,363. Construction contract 
costs were $792,479. Engineering and construction 
management costs were $1,460,879 and $234,247, 
respectively. Total Federal costs were $1,740,367 and non- 
Federal costs were $769,601. 
Condition at End of Fiscal Year. Construction of Stage 
1 is underway. Preconstruction engineering and design is 
continuing for the remaining two stages. 
34. WABASHA, MISSISSIPPI RIVER, MN 
Location. The erosion site is located on the eastern edge 
of the city of Wabasha, Minnesota, in Wabasha County along 
the right (west) bank of the Mississippi River. Wabasha is 
located in southeastern Minnesota, approximately 80 miles 
southeast of Minneapolis-St. Paul, Minnesota. 
Existing Project. The project is designed to protect the 
right bank of the main navigation channel on the Mississippi 
River where erosion is threatening Lawrence Boulevard, a 
sewer line located under the street, and a sanitary sewer lift 
station. The project involves minor excavation and the 
placement of rock fill along approximately 1,150 feet of 
eroding riverbank. The project was approved by the Chief 
of Engineers for construction in March 1991 under the 
authority contained in Section 14 of the 1946 Flood Control 
act, as amended. 
Local Cooperation. The city of Wabasha has agreed to 
serve as the non-Federal sponsor for this project. A local 
cooperation agreement between the Department of the Army 
and the city of Wabasha was fully executed on April 4, 
1991. See Annual Report for 1991 for requirements. 
Operations and results during the fiscal year. New 
Work: A construction contract cost $57,938. Engineering 
and design by hired labor cost $19. Construction 
management cost $7,273. Total Federal costs were $36,647, 
non-Federal $28,583. 
Condition at the end of fiscal year. Construction of the 
project was complete in June 1992. 
35. WARNER ROAD AND SIBLEY STREET, 
MISSISSIPPI RIVER, ST. PAUL, 
MN 
Location. Along the left bank of the Mississippi River at 
approximately river mile 839.1 in St. Paul, MN. 
Existing Project. The project site consisted of a sheetpile 
wall supporting a 30-foot embankment on which Warner 
Road is built. This highway is a vital artery serving over 
24-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
17,000 vehicles per day entering and leaving downtown St. 
Paul. The Mississippi River's 9-foot commercial navigation 
channel is just riverward of this site. About 100 feet of the 
wall was kicked out at the base, and a 32-foot section had 
broken away from the top and bowed out into the river. 
Embankment material was being lost and threatening to 
undermine the roadway. Sudden catastrophic failure could 
have resulted in blockage of the 9-foot commercial 
navigation channel. The Feasibility Report and 
Environmental Assessment dated January 1990 was prepared 
under the authority of Section 14 of the 1946 Flood Control 
Act, as amended. This report recommended installing an 
additional sheetpile wall 3-feet riverward of the existing wall, 
tying the new wall back into the existing structure, filling the 
space between the two walls with pervious fill, and capping 
the unit with concrete. 
Local Cooperation. See Annual Report for 1990 for 
requirements. The local sponsor, the city of St. Paul, signed 
a local cooperation agreement on March 15, 1991. 
Operation and Results During Fiscal Year. New Work: 
A construction contract cost $51,950. Engineering and 
design cost $13,888. Construction management cost $22,496 
by hired labor and $1,176 by contract. Total Federal costs 
were $70,375 and non-Federal costs were $19,135. 
Condition at the end of fiscal year. Construction is 
complete. The project was turned over to the local sponsor 
by letter dated June 1, 1992. 
36. ZUMBRO RIVER AT GENOA, MN 
Location. In New Haven Township, Olmsted County in 
southeastern Minnesota about 60 miles south of Minneapolis- 
St. Paul. 
Existing Project. Provided for erosion control along the 
west bank of the Zumbro River to protect Township Road G. 
The project involved clearing and shaping the bank and 
placement of rock protection along 300 feet of riverbank. 
The project was approved by the Chief of Engineers for 
construction in May, 1990 under authority contained in 
Section 14 of the 1946 Flood Control Act, as amended. 
Local Cooperation. A local cooperation agreement was 
signed by the New Haven Township, Minnesota in July 
1990. See Annual Report for 1990 for requirement. 
Operation and Results During Fiscal Year. Funds of 
$11,000 were returned to the treasury. 
Condition at End of Fiscal Year. Construction of the 
project was completed in January 1991. The project was 
transferred to the local sponsor in April 1991. 
37. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Flood control projects turned over to local interests were 
inspected to determine that project channels are kept clean 
and unobstructed, dikes and revetments are in good 
condition, and structures are in good repair and operable. 
Deficiencies, if any, were minor unless noted. (See Table 
24-J on inspection of completed flood control projects.) 
Cost for the period was $86,465. Total cost to September 
30, 1992, is $1,250,210. 
Miscellaneous 
38. OTHER WORK UNDER SPECIAL 
AUTHORITY 
In the Aquatic Plant Control program (Section 302, Public 
Law 298, 89th Congress) study and program management 
cost $18,483 by hired labor. A contract for aquatic plant 
control operations at Buffalo Lake, Wisconsin cost $69,526. 
Work by other Corps offices cost $142. 
Condition and operation studies for removal of silt and 
aquatic growth in Sauk Lake, Minnesota (Section 602, Water 
Resources Development Act of 1986) cost $8,409 by hired 
labor. Weed harvesting equipment contract cost $104,485 
and aquatic plant removal cost $536. It cost $11,411 to 
establish a work plan with the sponsor. Supervision and 
inspection and other miscellaneous costs were $19,989. 
Total Federal costs for the Sauk Lake project were $135,405 
and non-Federal, $9,425. 
General Investigations 
39. SURVEYS 
Fiscal year cost was $850,832 which included five flood 
damage prevention studies, miscellaneous activities, and 
coordination with both Federal and non-Federal agencies. 
Table 24-M provides a specific list and respective fiscal year 
expenditures. 
40. COLLECTION AND STUDY OF BASIC 
DATA 
Fiscal year cost was $217,094 which included the items 
concerning international water studies, flood plain 
management services and hydrologic studies. Table 24-M 
provides a specific list and respective fiscal year 
expenditures. 
24-16

ST. PAUL, MINNESOTA DISTRICT 
41. ADVANCE ENGINEERING AND DESIGN 
Fiscal year cost was $843,332 which included three local 
protection projects. Table 24-M provides a specific list and 
respective fiscal year expenditures. For details of the 
individual projects see sections 14, 20, and 23. 
24-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-A COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30, 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
1. Minnesota River, MN 
3. Reservoirs at Headwaters 
of Mississippi River, MN 
5. Zippel Bay, Lake of the 
Woods County, MN 
6. Bassett Creek, MN 
7. Big Stone Lake and 
Whetstone River, MN 
and SD 
8. Chaska, MN 
9. Devils Lake, ND 
10. Eau Galle River, WI 
11. Emerson, Manitoba- 
Noyes, MN 
12. Grand Mound - State 
Historical Site, MN 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Maj. Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
$2,057,722 
2,057,722' 
35,546 115,700 
35,639 114,499 
10,965 
11,459 
24,000 2,747,097 
24,312 2,746,702 
- - - - 4,398,628 
- - - - 4,398,6282 
2,413,600 2,406,809 2,358,500 2,536,000 37,485,355 
2,538,360 2,400,986 2,355,190 2,576,153 37,426,8923 
- - - - 425,000 
- - - - 425,000 
515,000 
- 515,000a 
-115,000 
-59,318 
26,000 
24,409 
-1,100 
434 
24,900 
24,843 
1,051,000 5,548,000 7,460,000 1,654,000 26,496,000 
2,883,210 3,696,101 9,288,845 1,841,549 26,489,3065 
- - - - 12,175,000 
- - - - 12,174,9156 
197,300 167,354 131,000 157,100 3,078,954 
195,915 159,260 130,722 144,152 3,055,818 
901,000 6,218,000 3,179,000 916,000 13,274,000 
891,512 5,460,941 3,916,715 950,558 13,272,1107 
25,000 
38,903 
30,000 
17,455 -9,595 
- 2,732,000 
33,276 2,732,000 
- - - - 9,039,250 
- - - - 9,039,250 
597,200 475,285 485,000 553,900 7,981,490 
591,644 477,131 478,579 493,998 7,899,548 
336,071 -30,256 
10,000 255,000 
9,999 41,653 
- -97,000 343,000 
27,875 -80,643 343,000' 
- -23,000 242,000 
181,408 8,940 242,000 9 
24-18

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30, 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
13. Homme Lake and 
Dam, ND 
14. Houston, MN 
15. Lac qui Parle Lakes, MN 
16. La Farge Lake and Channel 
Imp., WI 
17. Lake Ashtabula and 
Baldhill Dam, 
Sheyenne River, ND 
18. Lake Traverse and Bois 
de Sioux River, SD 
and MN 
19. Mankato and North 
Mankato, MN 
20. Marshall, MN 
21. Middle River at Argyle, 
MN 
22. Minnesota River at 
Henderson, MN 
23. Portage, WI 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Dam Safety: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
8,000 
7,163 
77,500 99,435 
82,812 85,034 
180,000 217,000 
222,100 267,028 
- - 
- - 
462,200 385,245 
520,713 362,954 
- - 
- - 
16,300 29,357 
16,300 23,598 
25,000 1,429,097 
8,939 1,412,199
1t0 
86,000 105,000 2,720,556 
91,107 106,578 2,711,832 
367,000 340,000 1,583,000 
411,012 338,239 1,581,232 
- - 964,873 
- - 964,873 
497,000 443,000 7,736,908 
485,733 474,521 7,727,445 
- - 18,642,000 
- - 18,642,000 
33,000 
34,036 
79,000 418,457 
81,092 415,225 
3,325,638 
3,325,63811 
724,600 792,879 
761,998 783,328 
401,000 1,200,000 
554,671 1,210,664 
Maint: 
Approp. 331,900 
Cost 348,094 
New Work: 
Approp. 1,298,000 
Cost 2,139,574 
New Work: 
Approp. 25,000 
Cost 33,569 
New Work: 
Approp. 990,000 
Cost 77,750 
New Work: 
Approp. 350,000 
Cost 712,016 
New Work: 
Approp. 300,000 
Cost 280,668 
332,213 
329,426 
927,000 1,151,000 18,505,531 
886,109 1,171,241 18,462,685 
-400,000 100,000 2,381,000 
56,666 -9,424 2,268,795 
- - 1,339,727 
- - 1,339,727 
270,500 413,000 5,378,032 
284,753 399,599 5,361,049 
- -108,000 - 97,270,500 
9,089 223,521 -321,510 96,851,6372 
25,000 
25,156 
360,000 
1,067,432 
100,000 
247,526 
311,000 
311,462 
25,000 25,000 2,570,866 
25,652 24,292 2,570,1231s 
- -18,000 2,357,000 
151,237 59,543 2,355,331 
44,136 
- 1,847,500 
10,248 1,846,45914 
168,000 481,000 1,260,000 
185,772 480,801 1,258,703 
24-19

REPORT OF THE SECRETARY OF TIlE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-A (Continued) COST AND FINANCIAL STATEMENT 
See Total Cost to 
Section September 30, 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 1992 
24. Red Lake River, MN 
including Clearwater 
River, MN 
25. Red River of the North 
at Fargo, ND - 
Moorhead, MN 
26. Red River of the North 
Drainage Basin, MN, 
SD and ND 
27. Rochester, MN 
28. Root River at Hokah, MN 
29. Roseau River, MN 
30. Sheyenne River, ND 
31. Souris River Basin, ND 
32. State Road & Ebner 
Coulees, WI 
33. St. Paul, MN 
34. Wabasha, Mississippi 
River, MN 
35. Warner Road at Sibley 
Street, St. Paul, MN 
36. Zumbro River at Genoa, 
MN 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
140,400 
154,746 
59,025 
50,846 
35,000 165,000 
19,898 121,574 
54,000 
58,603 
11,500 
80,559 
- 3,120,079 
- 3,120,07915 
93,000 1,437,627 
85,482 1,426,443 
-5,000 226,500 
4,469 226,50016 
- - - - 8,138,984 
- - - - 8,138,98417 
428,900 529,852 252,000 433,000 5,711,386 
461,120 529,304 259,272 426,183 5,691,725 
5,514,000 7,852,000 8,221,000 9,445,000 38,318,000 
6,461,148 9,015,991 8,236,115 9,426,457 38,296,44318 
22,000 
20,727 
222,000 
93,213 125,687 
- 25,000 172,000 
9,193 187,613 102,743 
-4,373 239,627 
- 239,62719 
- 2,325,000 
61,799 2,310,008 
780,000 4,755,000 8,021,000 3,018,000 20,207,000 
759,579 3,808,885 8,889,031 3,050,300 20,138,1432 
1,500,000 23,000,000 25,432,000 22,500,000 81,504,000 
1,879,501 22,266,870 26,102,157 22,613,290 81,322,05121 
4,582,000 1,313,000 4,322,000 4,608,000 17,652,000 
5,543,747 993,167 4,624,720 4,630,130 17,585,397" 
475,000 513,000 750,000 1,714,000 3,852,000 
479,221 511,006 667,125 1,740,367 3,787,527 
32,000 
6,850 7,574 
90,700 
71,546 
30,000 103,500 366,500 
19,179 37,222 373,224 
3,371 
39,500 
9,407 
- 122,700 
36,647 122,617 
- 500,000 
70,375 500,00023 
-11,000 
21,502 
34,500 
34,5004 
24-20

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-A (Continued) COST AND FINANCIAL STATEMENT 
lIncludes $117,542 for new work for previous project. Excludes 
$359,202 contributed funds. 
2Includes $681,805 for new work for previous projects. 
3Includes $100,857 for maintenance for previous projects. 
4Excludes $307,556 contributed funds. 
SExcludes $2,434,482 contributed funds. In addition, 
$409,689 in other contributed funds have been expended for 
betterments. 
6Excludes $152,247 contributed funds. In addition, $486,313 in 
other contributed funds have been expended for work under 
Government contract paid for by the Ottertail Power Company. 
7Excludes $2,257,013 contributed funds. 
SExcludes $201,544 contributed funds. 
9Excludes $77,290 contributed funds. 
1mExcludes $56,220 contributed funds. Includes $16,102 expended 
during FY91-FY92 under Section 1135 authority. 
"Excludes $208,000 contributed funds. 
n2Excludes $79,537 contributed funds. 
3lncludes $1,802,866 for new work for previous project. 
'4Excludes $244,756 contributed funds. 
'sExcludes $30,020 contributed funds.16Excludes $61,895 
contributed funds. 
'7Includes cost of the Wahpeton-Breckenridge unit $11,239, which 
is classed as "deferred" and the units on which authorization has 
expired: Maple River, $1,241; Moorhead, $27,700; Sheyenne, 
$37,956. In addition, $203,874 special deposit funds and $146,160 
in other contributed funds have been expended for work under 
Government contract paid for by local interests. 
18Excludes $4,445,244 contributed funds. In addition, $92,821 in 
other contributed funds have been expended for betterments. 
19Excludes $67,014 contributed funds. 
2Excludes $1,150,000 sunk costs for deauthorized Kindred Lake 
unit (see Table 24-G). Excludes $395,475 contributed funds for 
Horace to West Fargo unit and $895,756 for West Fargo unit. 
21Excludes $4,919,000 sunk costs for deferred Lake Darling Dam 
unit (see Table 24-E). 
22Excludes $225,000 sunk costs for inactive Ebner Coulee unit (see 
Table 24-E) and $3,576,461 contributed funds. 
23Excludes $184,709 contributed funds. 
24Excludes $11,066 contributed funds. 
24-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-B AUTHORIZING LEGISLATION 
See Date of 
Sec. Authorizing 
in Text Act Project and Work Authorized Documents 
1. MINNESOTA RIVER, MN 
July 13, 1892 Open-channel improvement from mouth to Shakopee to obtain a Annual Report 1891. 
channel of 4-foot depth to accommodate vessels with 3-foot draft. P. 2209 
July 3, 1958 Dredging to provide channel of 9-foot depth from mouth to S. Doc. 144. 84th. 
mile 14.7 Cong., 2nd sess.l 
3. RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER, MN 
Mar. 3, 1899 Reconstruct 4 of the 5 original dams and surveys to determine 
extent of lands overflowed by reservoirs. 
Mar. 2, 1907 Reconstruct Sandy Lake Dam and construct Gull Lake Reservoir. 
June 25, 1910 Construct an equalizing canal between Winnibigoshish and Leech H. Doc. 363, 61st 
Lake Reservoirs (no work was done and this part of the project Cong., 2nd sess. 
abandoned in Act of Mar. 4, 1915.) 
July 27, 1916 Abandonment of ditches connecting Long Lake, Round Lake, and H Doc. 413, 64th 
Gull Lake. Cong., 1 sess.' 
June 26, 19342 Operation and maintenance provided for with funds from War 
Department appropriations for rivers and harbors. 
'Contains latest published map. 
2Permanent Appropriations Repeal Act. 
24-22

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30. 1992 
Full Report 
See Annual Operation 
Project Status Report for Construction and Maintenance 
Baudette Harbor, MN Completed 1961 $36,415 $57,768 
Black River, WI ' 1950 67,585 - 
Lake Traverse, MN and SD 3, 1921 92 - 
Mississippi and Leech Rivers, MN Completed3 1929 277,615 40,251 
Mississippi River between Brainerd 
and Grand Rapids, MNs 1925 47,794 3,891 
Pine Creek, Angle Inlet, MN Completed 1978 38,700 102,196 
Red Lake and Red Lake River, MN Completed3 1923 9,070 - 
Red River of the North, MN and ND 3. 6 1921 293,344 76,209 
St. Croix River, MN and WI Completed 1991 150,410 1,183,312 
Wisconsin River, WI 2, 3 1888 - - 
Warroad Harbor and River, MN Completed 1989 86,105 1,221,4497 
Zippel Bay Harbor, MN Inactive 1928 27,941 22,180' 
1Existing channel adequate for commerce (see Table 24-G for 
deauthorized portion of project.) 
2Originally included in project 'Fox and Wisconsin River, WI'. 
Abandonment of improvement of Wisconsin River by channel 
contraction works recommended in 1886 and 1887 (H. Doc. 65, 
49th Cong., 2nd sess.) Expenditures included under 'Fox and 
Wisconsin Rivers, WI'. No breakdown available. 
3No commerce reported. 
4Abandonment recommended in 1915 (H. Doc. 439, 64th Cong., 
1st sess.) and June 24, 1926 (H. Doc. 467, 69th Cong 1st sess.) 
5Abandonment recommended June 24, 1926 (H. Doc. 467, 69th 
Cong. 1st sess.) 
6Abandonment recommended in 1915 (H. Doc. 1666, 63d Cong., 
3d ses.) 
7Includes $1,662 for condition surveys for FY 1990. 
'Includes $11,041 for condition surveys for FY 1990. 
24-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation 
Project Status Report for Construction and Maintenance 
Black Bear & Miller Lakes, Crow Wing Cty, MN2 Completed 1988 $471,000 - 
Bonnes Coulee, Velva, ND' Completed 1985 58,500 - 
Burlington Dam, Souris River, ND Deferred 1983 5,568,600 4- 
Cannon River at Faribault, MN' Completed 1991 62,585 s - 
Dry Run, IA Completed 1966 1,790,759 6 - 
Elk River, MN Completed 1970 259,700 - 
Enderlin, Maple River, ND 2 Completed 1990 4,000,0008 - 
Grafton Pumping Station, ND' Completed 1990 92,865 9- 
Guttenberg, IA Completed 1974 2,361,915 - 
Hanover, Hennepin County, MN' Completed 1988 259,500 - 
Irving Township, Jackson County, WI' Completed 1984 189,600 - 
Irving Township at Nicols Road, Completed 1986 158,500 - 
Jackson County, WI' 
Kickapoo River, Gays Mills, WI' Completed 1987 33,000 - 
Lake Andrusia, Mississippi River, MN' Completed 1989 61,326 to - 
Lake Darling Dam, ND Deferred 1987 4,919,000" - 
Lake Pulaski, Wright County, MN2 Completed 1991 1,187,50012 - 
Lost River, MN Completed 1967 517,5191 3- 
Lower Branch Rush River, ND2 Completed 1974 1,000,000 14 - 
Minnesota River at LeSueur, MN' Completed 1986 250,0 0 0 
5 
- 
Minneota, MN2 Completed 1963 161,545 - 
Minot, ND Completed 1983 21,479,500 16 - 
Mississippi River near Aitkin, MN Completed 1957 1,675,835 - 
Pembina River, ND Active3 1983 - - 
Pettibone Park, La Crosse, WI' Completed 1989 62,762 - 
Prairie du Chien, WI Completed 1991 3,529,000 - 
Red Lake River at Gentilly, MN Completed 1991 311,000' 8 
- 
Red Lake River at Huot, MN' Completed 1984 64,500 - 
Red Lake River at Red Lake Falls, MN' Completed 1984 131,000 - 
Red River of the North at Argusville, ND2 Completed 1990 1,534,000 - 
Red River of the North at Breckenridge, MN' Completed 1990 85,665 9 - 
Red River of the North at Breckenridge, MN' Completed - 27,500 - 
Red River of the North at Halstad, MN2 Completed 1986 2,012,000 - 
Red River of the North at Oslo, MN2 Completed 1984 1,960,200 - 
Red River of the North at Pembina, ND2 Completed 1979 2,000,000 - 
Redwood River below Marshall, MN2 Completed 1960 202,400 - 
Rushford, MN Completed 1980 3,192,333 - 
Shepard Road, Mississippi River, St. Paul, MN' Completed 1985 250,00020" - 
Sheyenne River, Valley City, ND Completed 1988 111,000 - 
Souris River, Velva, ND' Completed 1988 137,500 - 
St. Paul and South St. Paul, MN Completed 1974 8,476,0122 - 
State Road & Ebner Coulees, WI Inactive 1987 225,000 - 
(Ebner Coulee Unit) 
Twin Valley Lake, MN Inactive 1988 2,115,700 - 
Upper Iowa River, IA Completed 1964 888,445 - 
Velva, ND 2 Completed 1970 334,628 - 
Vermillion River, Hastings, MN2 Completed 1980 999,900 - 
Veteran's Memorial Levee, Mississippi River, Completed 1985 182,000 - 
Hastings, MN' 
Warner Road, Mississippi River, St. Paul, MN' Completed 1987 250,000 - 
Wild Rice River, South Branch and Felton Ditch, MN Completed 1989 5,620,700 - 
Winona, MN Completed 1989 32,741,131- 
24-24

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30,. 1992 
Full Report 
See Annual Operation 
Project Status Report for Construction and Maintenance 
Zumbro River, MN Completed 1975 1,284,100 - 
Zumbro River at Jarrett and Millville, MN' Completed 1990 141, 4 40 - 
'Project authorized by Chief of Engineers under small project 
authority, Section 14, Flood Control Act of 1946, as amended. 
2Project authorized by Chief of Engineers under small project 
authority, Section 205, Flood Control Act of 1948, as amended. 
3Preconstruction planning has not started. Phase I completed under 
General Investigations. 
�Advance engineering and design costs only. Project deferred with 
authorization of Lake Darling project. Additional authorization 
required for implementation of recommended plan. The Senate 
Report 97-256 states that the Corps is to take no further action to 
construct Burlington Dam until directed to do so by Congress. 
5Excludes $18,362 contributed funds. 
'Excludes $42,766 contributed funds. 
71n addition $87,878 was expended from Public Law 99 funds in 
the spring of 1969 for emergency protection and incorporation into 
the permanent project. 
'Excludes $150,191 contributed funds. 
9Excludes $27,583 contributed funds. 
'0Excludes $20,441 contributed funds. 
"Advance engineering and design costs only. Project deferred with 
authorization of Souris River Basin Project (see Section 31 and 
Table 24-A for costs for active project). 
2Excludes $61,540 contributed funds. 
'3Excludes $46,034 for the Ruffy Brook unit for which 
authorization expired in April 1966 (see Table 24-G). Excludes 
$246,911 contributed funds. 
14Excludes $35,000 contributed funds. 
I5Excludes $130,300 contributed funds. 
"16Excludes $4,167 contributed funds. 
"Excludes $20,920 contributed funds. 
'"Excludes $92,402 contributed funds. 
19Excludes $26,055 contributed funds. 
2Excludes $62,620 contributed funds. 
21Excludes $545,637 contributed funds for new work and $38,000 
expended by South St. Paul for work in lieu of required cash 
contribution. Excludes an additional $206,629 expended for work 
done at request of local interests. 
22Excludes $589,316 contributed funds. In addition, $717,809 in 
other contributed funds have been expended for work under 
Government contract paid for by local interests. 
23Excludes $38,173 contributed funds. 
24-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Black River, WI1 1950 Aug. 5, 1977 - - 
Black River Lake, WI 1950 Aug. 5 1977 - - 
Grafton, ND 1983 Nov. 18, 1991 - - 
Hudson Harbor, WI2 1986 Nov. 17, 1986 - - 
Kindred Lake, ND3 1987 Nov. 17, 1986 $1,150,000 - 
La Crosse, WI 1983 Nov. 17, 1986 - - 
Maple River, ND 1981 Oct. 6, 1961 1,241 - 
Moorhead, MN5 1981 Oct. 30, 1961 27,700 - 
Pembina River Lake, ND 1950 Jan. 1, 1990 50,000 - 
Ruffy Brook, MN 1967 Apr. 1966 46,034 - 
Sheyenne River, ND5 1981 Dec.31, 1970 37,956 - 
Tongue River Lake, ND 1950 Jan.1, 1990 23,695 - 
Warroad River and Bulldog Creek, MN 1974 Nov. 17, 1986 182,000 - 
Warroad Harbor and River, MN6 1981 Aug. 5, 1977 - - 
IPortion of project for removal of obstructions at various points 
outside the dredged area to clear channel to full project width (see 
Table 24-C for costs for completed portion of the project). 
2Part of the St. Croix River, Minnesota and Wisconsin project. 
3Previously part of Sheyenne River, ND project (see Section 30 and 
Table 24-A for costs for active project). 
4Authorized for further study by a House Committee on Public 
Works Resolution dated March 15, 1988. 
5Part of Red River of the North Drainage Basin (see Section 26 in 
text and Table 24-I for costs for active units of project). 
6Portion of dredging of entrance channel and turning basin to 
complete project width and depth (see Table 24-C for costs for 
completed portion of project). 
24-26

TABLE 24-H RESERVOIRS AT HEADWATERS OF 
MISSISSIPPI RIVER 
(See Section 3 of Text) 
Outlet Watershed Area (Square miles) Capacity Previous Proiects Existint Projects 
at 
Minimum Above Watershed Maximum 
Stages St. Paul (Square Original Stage Total 
Reservoir (feet) ' River (miles) miles) Lake Reservoir (acre-feet) Completed Cost Completed Cost Cost 
Winnibigoshish 6 Mississippi 408 1442 117 179.4 967,930 1884 $214,000 1900 $173,470 $387,470 
Leech Lake 0 Leech 410 1163 173 205.9 743,320 1884 171,805 1902 84,380 256,185 
Pokegama 6 Mississippi 344 6602 24 35.0 120,750 1884 85,000 1904 126,030 211,030 
Sandy Lake 7 Sandy 267 421 8 16.6 72,500 1895 114,000 1909 117,020 231,020 
Pine River 9 Pine 199 562 18 23.7 177,520 1886 97,000 1907 133,320 230,320 
Gull Lake 5 Gull 168 287 20 20.5 70,820 - - 1913 86,826 86,826 
Surveys and flowage rights - - - - 160,939 160,939 
Recreational facilities - - - - 2,834,838 2,834,838 
Total new work - - 681,805 - 3,716,823 4,398,628 
Total operating and care - - 100,857 - 36,358,837 36,459,694 
Permanent indefinite - - - - 967,197 967,197 
appropriation for operation 
and care, Feb. 1, 1895 to end of 
fiscal year 1936 
Rehabilitation - - - - 425,000 425,000 
Total 2,152,840 - $782,662 - $41,467,857 $42,250,519 
'Lower operating limits by regulations approved February 4, 1936, as modified December 29, 1944. 
2Exclusive of area controlled by Winnibigoshish and Leech Lake Dams. 
N% 
vr 
*
M. 
l

REPORT OF THE SECRETARY OF TIHE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-I RED RIVER OF THE NORTH DRAINAGE BASIN: 
ACTIVE UNITS IN COMPREHENSIVE BASIN PLAN 
(See Section 26 of Text) 
Cost to Total 
September 30, Estimated 
State Type 1992 Federal Cost 
Orwell River (Otter Tail River) Minnesota Reservoir $1,916,753 $1,916,700' 
Wild Rice and Marsh Rivers Minnesota Channel improvement 405,056 405,100 
Rush River North Dakota Channel improvement 287,686 287,700 
Sand Hill River Minnesota Channel improvement 548,778 548,800 
Mustinka River Minnesota Channel improvement 440,778 440,800 
Otter Tail River Minnesota Channel improvement 174,768 174,800 
Red River at Grand Forks North Dakota Levees and floodwall 948,895 948,900 
Red River at East Grand Forks Minnesota Levees, floodwall 1,698,200 17,500,0002 
pumping plants 
Red River at Fargo North Dakota Channel improvement 1,639,924 1,639,9003 
Total Cost to Date $8,060,8484 
Total Estimate Cost $23,862,000s 
'Includes $181,713 for lands and $25,045 for recreation facilities. 
2The East Grand Forks unit was reclassified from active to inactive 
on August 19, 1988. The cost of this unit was last revised in 1987. 
3Includes $67,900 for lands. 
4Costs of $11,239 for the Wahpeton-Breckenridgedeferred unit not 
included. Authorization of the Sheyenne River, Moorhead, and 
Maple River units has expired. Cost of these units also not 
included total $66,897. 
5The Wahpeton-Breckenridge unit of the project is classed as 
'deferred' and is excluded from the estimate. The cost of this unit, 
last revised in 1955, was estimated to be $666,000. The Flood 
Control Act approved December 31, 1970 (H. Doc. 330-91-2) 
provided for deletion of the Sheyenne River unit, and authorization 
of the Maple River and Moorhead units expired at the end of the 
5-year period within which local interests were required to furnish 
assurances of local cooperation. Authorization of these units, not 
included, expired on the dates indicated in Table 24-G. In FY 89, 
the Wahpeton-Breckenridge unit was included as part of the 
General Investigation program under restudy of deferred projects. 
24-28

ST. PAUL, MINNESOTA DISTRICT 
Table 24-J INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 37 of Text) 
Project Date Inspected 
Big Stone Lake and Whetstone River, MN and SD ............ ............................ September 1992 
Black River, (North Bend), WI ......................... ............................. September 1992 
Black River Falls, WI. ............................................................ September 1992 
Black Bear and Miller Lakes, Crow Wing County, MN .......... . ............................ August 1992 
Cannon River, Fairbault, MN .................. ... .............................. September 1992 
Cochrane, Mississippi River, WI ............. ........................................ October 1991 
Decorah, (Dry Run), IA ............................ . .. .......... ................ December 1991 
Devils Lake, ND ................................... ................................ August 1992 
Elk River, MN ............... .. .... .............................................. July 1992 
Emerson, Manitoba- Noyes, MN ..... ............ ...................................... August 1992 
Fargo, ND ....... .................................................................... July 1992 
Grafton, ND ................ ... . ......... .... . .................................. August 1992 
Grand Forks, ND ............... ......... ......................... ............... August 1992 
Grand Mound - State Historic Site, MN ........ ................ .......................... August 1992 
Guttenberg, IA ................. .. . ... ........................................ December 1991 
Halstad, MN .............. . ........................................ ................... July 1992 
Hanover, MN .......... . .... ............................................... September 1992 
Hokah, MN .............. . . . ............................................... September 1992 
Huot,M N .............. ..................................................... August 1992 
Kickapoo River, Gays Mills, WI .......... ......................................... December 1991 
Lake Andrusia, Mississippi River, MN ........... ..................................... August 1992 
LeSueur, MN ..................................................................... August 1992 
Mahnomen, MN .............. ............... . .. .. ..................... ........ July 1992 
Mankato, North Mankato, and LeHillier, MN .......... ................................. September 1992 
Maple River, Enderlin, ND .......... .............................................. August 1992 
Marshall, MN ........................................................................ September 1992 
Mines Creek, Spring Valley, WI ............ ........................................ September 1992 
Minneota, MN ......................................................... ............... September 1992 
Mississippi River near Aitkin, MN ............ .. ...................................... August 1992 
Oslo, MN ............. .. .. .................................................. August 1992 
Pembina, ND................. ... ..... . .. . ............................................ August 1992 
Pettibone Park, LaCrosse, WI................. .... .... ....................................... July 1992 
Plum Creek at New Haven Township, MN ........... .................................. September 1992 
Prairie du Chien, WI ................. . .. . ............................... ....... December 1991 
Red River of the North at Argusville, ND .................................................. July 1992 
Red Lake River, Gentilly, MN ........... . . ......................................... August 1992 
Red Lake Falls,MN ........ ....................... .. ................................. August 1992 
Red River of the North at Breckenridge, MN .......... ..................................... July 1992 
Rushford, MN ................................................... . .............. October 1991 
Shepard Road, Mississippi River, St. Paul, MN ......................................... September 1992 
Sheyenne River, Valley City, ND .............................................................. August 1992 
Souris River, Velva, ND ................ .................. July 1992 
Trempealeau River, Arcadia, WI ............................. September 1992 
Upper Iowa River, New Albin, IA ................................. September 1992 
Velva, ND .............. .................. July 1992 
Velva (Bonnes Coulee), ND ........... .................................................. July 1992 
Vermillion River, Hastings, MN ................... .... ........... July 1992 
Veterans Memorial Levee, Mississippi River, Hastings, MN .......................................... July 1992 
Warner Road, Mississippi River, St. Paul, MN ............................................. September 1992 
Wild Rice River at Mahnomen County, MN ....... ....... ...................................... July 1992 
Winona, MN .............................................. .September 1992 
Zippel Bay, MN ................................................................... August 1992 
Zumbro River at Jarret and Millville, MN ........... ..................................... September 1992 
Zumbro River at Genoa, MN ........... ...................... September 1992 
Zumbro River, Kellogg, MN ............ .............................................. July 1992 
24-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-K FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public Law 858, 
80th Congress, as amended (preauthorization) 
Study/Project and Location Fiscal Year Costs 
BeebeLake, Frankfort, M N .......................................................... $ 11 
Chippewa River, Montevideo, MN ...................................................... 685 
Crow River, Rockford, M N ......................................................... 7,714 
Des Lacs River, Burlington, ND ..................................................... 22,025 
Devils Lake, ND .............................................................. 33,276 
Duncan Creek, Bloomer, W I ....................................................... 12,017 
Elk River, Lake Orono, M N . .................... ................................... 4,334 
Emerson, Manitoba - Noyes, MN ..................................................... -80,643 
Garvin Brook, Stockton, M N ........................................................ 9,160 
Gilmore Creek, W inona, MN ...................................................... 158,742 
Kawishiwi River, M N ..... ............................... ....................... 4,741 
Lac Qui Parle, M N ............................................................. 59,541 
Middle River at Argyle, MN ....................................................... 59,543 
Minnesota River, Henderson, MN .................................................... 10,248 
M ississippi River, Fridley, M N........................................................ 5,134 
M orais River, ND................................................................ 8,251 
Pelican Lake, Frankfort, M N .......................... .............................. 5,238 
Red Lake River, East Grand Forks, MN ................................................. 16,576 
Red River of the North, Grand Forks, ND ................................... ............. 7,714 
Red River of the North, Walsh County, ND ........................... ...... .............. 9,636 
Sanders Creek, Boscobel, WI .......... ............................. .. .............. 41,546 
Snake River, Alvarado, MN ............................. ........................... 265,130 
Wild Rice River, Hendrum/Lee, MN .................................................... 2,678 
W ild Rice River, Lake Ida, M N .......................... ............................. 6,458 
Zumbro River, Lake Zumbro, MN .......................... ............................ 4,993 
Emergency bank protection (Section 14 of 
the 1946 Flood Control Act, Public Law 526, 79th Congress) 
Study/Project and Location Fiscal Year Costs 
Big Fork River, M N ....... ...................... .............................. $4,828 
Black River, Amsterdam, WI ................ . . ...................................... 5,567 
Foxholm,ND ............................................ . ... ...... ..... ......... 2,430 
Grand Mound, State Historical Site, MN ........... ....... . .................................. 8,940 
Little Fork River, Hwy 75, MN .............. ... . ......... ............ 8,809 
Minnesota River, Belgrade, MN ..................... ................................ ..... 25,216 
Mississippi River, Wabasha, MN...................... .. .................. 36,647 
RatRootRiver,MN .................................... . . . ............................ 7,193 
Red Lake River, State Hwy 32, MN. ................ ............................. 45,219 
Red Lake River, Red Lake County, Hwy 3, MN .......... ............ .................. 20,000 
Red River of the North, County Road 2, ND .......... ................................. 4,874 
St. Croix River, Stillwater, M N .......... .. ..... .......... .. ... .... .......... 6,313 
St. Hilaire, M N ............... ... ... . .. ......... .. ...... .. ......... 25,828 
Wabasha County, Hwy 11, MN .................. ...................... ......... 20,986 
Warner Road at Sibley, St. Paul, MN .............. .... ..... . .......... 70,376 
24-30

ST. PAUL, MINNESOTA DISTRICT 
TABLE 24-K (Continued) FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Snagging and clearing navigable streams and tributaries in the interest of flood 
control (Section 208, 1954 Flood Control Act, Public Law 780, 83rd Congress) 
Study/Project and Location Fiscal Year Costs 
Big Coulee to Devils Lake, ND............ . ......................... ................ $9,000 
Lower Mauvais Coulee / Devils Lake, ND .............................................. 6,000 
Red Lake River, East Grand Forks, MN ............ .. ..... .. . . .................................. 2 
Red River of the North, Fargo, ND .......... ......... ... .................................. 4,469 
Red River of the North, Walsh County, ND .............................................. 3,104 
Red River of the North, Grand Forks, ND ...................... ............................ 16 
Snake River, Vega / Sandsvile, MN .......... . . ...................................... 4,216 
Snake River, Warren, MN.............. ... .... .. ......................................... 20,161 
Wild Rice River, Lake Ida, MN ........... .......................................... 1,431 
Emergency flood control activities - repair, flood fighting, and rescue work 
(Public Law 99, 84th Cong., and antecedent legislation) 
Study/Project and Location Fiscal Year Costs 
Disaster Preparedness ........... . ............................................... $171,462 
Emergency Operations ......... ...................................................... 74,097 
Rehabilitation.................................................................... 8,925 
Advance Measures... .......................................................... 2,119 
Total emergency flood control activities ................ ............................... $256,603 
TABLE 24-L PROJECT MODIFICATIONS FOR IMPROVEMENT 
OF ENVIRONMENT 
Modifications of projects for the purpose of improving the 
quality of the environment in the public interest 
(Section 1135, Public Law 99-662, 99th Congress, as amended) 
Study/Project and Location Fiscal Year Costs 
Homme Lake, ND...................................................................... $8,939 
Reservoirs at Headwaters, Mississippi River, MN 
Leech Lake ................ ... ........... 59,052 
Lake Winnibigoshish ................. . . . . . .. ............. 2,145 
Lac qui Parle Lakes, MN (Marsh Lake)........... ........ .... ............ 304 
Orwell Lake, MN ..................... 6,006 
24-31

REPORT OF THE SECRETARY OF TIlE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 24-M GENERAL INVESTIGATIONS 
(See Sections 39, 40 and 41 of Text) 
Study/Project and Location Fiscal Year Costs 
SURVEYS 
Flood Damage Prevention Studies 
Crookston, M N ......................... ................................. $23,762 
GrandForks, ND ...................... .................................. 65,981 
La Crosse, W I ... ...................... ................................... 528 
Little Falls, M N .......................................................... 68,451 
Red River Basin Technical Resource Service ........................................ 112,849 
Red Lake and Clearwater Rivers, MN .............................................. 3,799 
Special Studies 
Devils Lake, ND ....................... ................................... 87,262 
Miscellaneous Activities 
Special Investigations ..... .................. ............................... 97,169 
FERC Licensing Activities ...... ............... .............................. 14,049 
Intra Agency Water Resources Development ......................................... 16,827 
North American Waterfowl Management Plan ........................................ 10,708 
Coordination with Other Agencies 
Soil Conservation Services ................ .................................... 2,036 
Bureau of Reclamation .................... . ................................... 5,349 
Planning Assistance to States-MN .... ........... ............................... 224,370 
Planning Assistance to States-ND ............... ................................ 117,573 
Planning Assistance to States-WI .............. ..................................... 119 
TOTAL SURVEYS ........................... ................................ $850,832 
COLLECTION AND STUDY OF BASIC DATA 
International W ater Studies ............. .......................................... 55,7791 
Flood Plain Management Services 
Flood Plain Management Services Unit ..... ...................................... 31,797 
Technical Services, General ................. .................................. 59,198 
Quick Responses ................... ........................................ 7,945 
Special Studies ............... ............................................ 59,198 
Hydrologic Studies 
Stream Flow Data .............................. .............................. 3,083 
TOTAL COLLECTION AND STUDY OF BASIC DATA ................................... $217,094 
ADVANCE ENGINEERING AND DESIGN 
Houston, M N ........... ......................... ......................... 338,239 
M arshall, M N .............................................................. 24,292 
Portage, W I ................................................................. 480,801 
TOTAL ADVANCE ENGINEERING AND DESIGN ........................ ........... $843,332 
'Includes $45,771 for International Water Studies under O&M Appropriation. 
24-32

MISSISSIPPI RIVER 
BETWEEN MISSOURI RIVER 
AND MINNEAPOLIS, MN 
Section of river covered in this report is divided into three 
reaches, under supervision and direction of District Engineers 
at St. Louis, Rock Island, and St. Paul. Section in St. Louis 
District extends 105 miles from Mouth of Missouri River to 
Location. Mississippi River rises in northern Minnesota, 
flows about 2,360 miles southerly and empties into Gulf of 
Mexico. Portion included in this report extends about 663 
miles from mouth of Missouri River to Soo Line Railroad 
bridge, Minneapolis. The latest map and profile showing this 
section of river are in House Document 669, 76th Congress, 
3d session. A map showing Lake Pepin is in House Document 
511, 79th Congress, 2d session. A map of section Minneapolis 
to Dubuque is in House Document 515, 79th Congress, 
2d session. A map showing location of drainage districts 
(Bellevue, Iowa, to Missouri River) is in River and Harbors 
Committee Document 34, 75th Congress, 1st session. 
Previous projects. See page 1199 of Annual Report for 
1963. 
Existing project. Provides for a channel of 9-foot depth 
and adequate width between mouth of Missouri River (1,179 
miles from the gulf) and Soo Line Railroad at Minneapolis, 
by construction of a system of locks and dams, supplemented 
by dredging. Project also provides for further improvements 
at St. Paul to provide a 2.7 mile basin extending downstream 
from Robert Street Bridge, and at Minneapolis to provide adequate 
terminal facilities, and for other harbor improvements 
and miscellaneous work. Pertinent data on locks and dams, 
harbor improvements, additional features entering into cost 
of project, and authorizing legislation are given in Tables 
25-C, 25-D, 25-E and 25-G. All dams are concrete. Three 
dams (Upper St. Anthony Falls, 1 and 19) are fixed, remainder 
are movable. See House Document 669, 76th Congress, 
3d session, for a report of Chief of Engineers dated 
February 27, 1940, containing a general plan for improvement 
of Mississippi River between Coon Rapids Dam and 
mouth of Ohio River for purposes of navigation, power 
development, flood control, and irrigation needs. 
Local cooperation. Small-boat harbors authorized in the 
River and Harbor Act of 1962 are subject to conditions that 
local interests make a cash contribution toward cost of construction 
(except in case of Quincy Harbor which involves 
maintenance only of an existing harbor); furnish lands and 
rights-of-way for construction and future maintenance; hold 
the United States free from damages; provide and maintain 
mooring facilities and utilities; reserve accommodations for 
transient small boats; accomplish all necessary relocations and 
alterations; and establish public bodies empowered to regulate 
use, growth and development of the harbors. 
Rectification of seepage damages to privately owned lands 
in the Sny Island Levee Drainage District, IL, was contingent 
upon the conditions that local interests acquire all lands, 
easements, and rights-of-way necessary for construction and 
Upper Mississippi River mile 300 above Ohio River; Rock 
Island District extends about 314 miles from mile 300 to 614; 
and St. Paul District extends about 244 miles from mile 614 
to Soo Line Railroad bridge, Minneapolis (mile 857.6). 
maintenance of the project; comply with applicable provisions 
of the Uniform Relocation Assistance and Real Property Acquisition 
Policies Act of 1970; accept, operate, and maintain 
the project upon its completion; and hold and save the United 
States free from damages arising from the construction and 
operation of the completed project; provided further that the 
local public entity shall be reimbursed by the Government in 
the amounts actually expended by it in the acquisition of real 
estate and for payments required under Public Law 91-646 
if said amounts have been previously submitted to and approved 
by the Government. 
Local cooperation requirements have been complied with 
for improvement of commercial harbor at Dubuque, IA; for 
improvement of Beaver Slough at Clinton, IA, for navigation; 
and for general navigation facilities at small-boat harbors 
at Rock Island, IL; Hannibal, MO; Fort Madison, IA; 
Davenport (Lindsay Park), IA; Muscatine, IA (including 
freight terminal approach channel); Andalusia, IL; Warsaw, 
IL; Moline, IL; Clinton, IA; and Savanna, IL. 
Licenses. Federal Energy Regulatory Commission collects 
from non-Federal licensees annually to recompensate the 
United States for use of government dams for generation of 
hydroelectric power. Amounts collected are returned to U.S. 
Treasury. (See Table 25-F for license fees collected through 
the end of the fiscal year.) 
St. Paul District. New Work: Studies were continued under 
Section 107, small navigation project authority for establishment 
of a small boat harbor at Guttenberg, Iowa and Prairie 
du Chien, Wisconsin at a cost of $5,380, and $9,031, 
respectively. 
Maintenance: Channel dredging to remove shoal areas was 
performed. Government pipeline dredge WILLIAM A. 
THOMPSON removed 546,914 cubic yards of material at 11 
locations at a cost of $2,607,797. Government derrick barge 
HAUSER/WADE removed 29,909 cubic yards of material 
at 8 locations at a cost of $147,095. Mechanical dredging contractors 
removed 228,048 cubic yards of material at 18 locations 
at a cost of $1,380,544. A water injection dredging contractor 
removed 2,941 cubic yards of materials at one site at 
a cost of $97,037. Dredging surveys cost $590,464. Water 
quality testing for dredging cost $75,149. Disposal site restoration 
by hired labor cost $17,122. Dredging work at Weaver 
Bottoms cost $1,205 by contract and $159,522 by hired labor. 
Dredge material relocation at Blackhawk Park and Indian 
Slough cost $183,500 by contract and $547 by hired labor. 
Dredging at St. Paul small boat harbor cost $100,780 by hired 
labor. Other dredging and snagging cost $139,221. 
25-1

REPORT OF THE SECRETARY OF THE ARMY FOR CIVIL WORKS ACTIVITIES FOR FY 1992 
A contract to repair the rock breakwater at Lake Pepin small 
boat harbor cost $12,604. Painting at locks and dams cost 
$500,195. Contracts installation of riprap at Lock and Dam 
9, dewatering of Lock and Dam 8, general lock maintenance, 
and boundary surveys at Lock and Dam 3 cost $24,699, 
$659,100, $55,057, and $18,221, respectively. A herbicide service 
contract cost $30,889. Contracts for dam machinery installation 
at Lock and Dam 2, for dam work and for gate 
hoist machinery at Locks and Dams 2,4 and 5, cost $521,441, 
$3,924, and $7,007,680, respectively. Contracts for lock work 
at Lock and Dam 3, for bubbler piping and for recreation 
road maintenance at Blackhawk Park cost $66,308, $27,497, 
and $129,362, respectively. Contracts for equipment replacement 
and for development of data management software cost 
$76,758 and $87,906. Railroad crossing contracts at Lock and 
Dam 4 and at Lock and Dam 8 cost $110,373 and $27,191. 
Contracts for pickup beams for bulkheads at Locks and Dams 
2, 4, 5, and 10 cost $151,000. Engineering work and 
miscellaneous surveys, reports, and other work were carried 
on by hired labor for $2,589,364 and by contract for $872,754. 
Project condition surveys cost $4,350. Other miscellaneous 
hired labor, payments, supplies and equipment cost 
$3,448,143. The total cost of maintenance was $21,924,799. 
Rehabilitation: Contracts for electrical work at Lock and 
Dam 3, electrical controls for Locks and Dams 3, 5A, 7-9 
and lock work for Lock and Dam 5A cost $7,667, $697,631, 
and $1,452,522, respectively. Supply contract for valve 
machinery at Lock and Dam 1 and for roller gate chains cost 
$379,999 and $720,733 respectively. Engineering, administration 
and other work were accomplished by hired labor for 
$538,460 and by contract for $45,087. Total rehabilitation 
costs were $3,842,099. 
Operating and care: Locks and Dams were operated as required 
and necessary repairs were made thereto. Other studies, 
reports, and miscellaneous engineering work were also accomplished. 
Total cost of operating and care was $12,999,788. 
Costs to St. Paul were $14,411 for new work; $34,924,587 
for operation and maintenance; and $3,842,099 for rehabilitation, 
for a total cost of $38,781,097. 
Rock Island District. New Work: None. 
Maintenance: Channel dredging by Government cutterhead 
pipeline dredge WILLIAM A. THOMPSON was performed 
at various locations in Pools 11, 13, 14, 16, 18, 21 and 22 
at a cost of $1,337,000 with 450,200 cubic yards of material 
being removed. Dredging inspection and reports were completed 
at a cost of $69,800. Snagging, clearing, and excavation 
was performed by hired labor at various locations at a 
cost of $506,400. Dredged material disposal activities and 
other environmental concerns in connection with dredging and 
channel maintenance activities cost $16,300. Repair of channel 
regulating works structures was performed at a cost of 
$2,725,300. Structural repairs, including sandblasting and 
painting were performed by hired labor at locks and dams 
at a cost of $3,788,300. Repairs to spillways and dikes cost 
$99,500. The Stage I contract for major maintenance to the 
dams at Locks and Dams 17 and 18 continued at a cost of 
$378,600. The work includes repairs to the structural components 
of the dams, placement of additional rock fill 
upstream and downstream of the gated sections of the dams, 
repairs to the spillways and removal of silt from the auxiliary 
lock bays. The Stage II major maintenance contract for electrical/
mechanical system replacement at Lock and Dam 17 
was completed at a cost of $19,800. The Stage II major 
maintenance contract to the dam at Lock and Dam 16 was 
initiated at a cost of $140,000. Installation of fuel tanks at 
Lock and Dams was continued at a cost of $600. Scour protection 
at Dam 16 was initiated at a cost of $277,900. The 
Stage III major maintenance contract for electrical/
mechanical system replacement at Lock and Dam 18 
was continued at a cost of $5,736,900. The Stage III major 
maintenance contract for electrical/mechanical system 
replacement at Lock and Dam 16 was initiated at a cost of 
$1,600,000. Bulkhead slots were constructed at Lock and Dam 
16 at a cost of $508,600. The hydraulic cylinder replacement 
at Lock 19 was completed at a cost of $4,700. Modifications 
to mooring cells at Lock and Dam 22 were completed at a 
cost of $13,600. Resurfacing access roads at Locks and Dams 
17, 18, and 20 were initiated at a cost of $99,300. Construction 
of Canton Chute and Andalusia Slough boat ramps were 
completed at a cost of $33,000. Resurfacing of roads at Grant 
River, Thompson Causeway, Clarks Ferry, and Shady Creek 
Recreation Areas were accomplished at a cost of $100,000. 
Septic system at Shady Creek Recreation Area was repaired 
at a cost of $46,700. The replacement of transformers at Lock 
19 was initiated at a cost of $15,500. Construction of restroom 
facilities at Lock and Dam 21 were initiated at a cost of 
$15,000. Maintenance of roads and bridges, buildings, 
grounds and utilities cost $1,500. Maintenance of public use 
areas was performed at a cost of $504,200. Maintenance and 
purchase of permanent operating equipment cost $137,400. 
Maintenance of levees cost $59,100. Real estate activities 
relating to maintenance were performed at a cost of $92,900. 
Engineering and design work was performed at a cost 
$1,757,800. Supervision, administration, and inspection for 
maintenance features cost $1,594,800. Total maintenance 
costs were $21,680,500. Net credits to the project were 
$272,800, primarily as a result of collection from towboat 
companies for damages to lock and dam structures. 
Operating and care: Operation of locks and dams and 
routine maintenance and minor repairs thereto were performed 
at a cost of $10,770,200. Real Estate management services 
were performed at a cost of $159,500. Natural and cultural 
resource activities were performed at a cost of $338,700. 
Public use areas and Mississippi River Visitors' Center were 
operated at a cost of $1,447,100, with contract law enforcement 
provided at a cost of $56,900. OSHA inspections and 
medical examinations were accomplished at a cost of $15,800. 
Surveys, various condition and operation studies and structural 
inspections cost $1,122,800. Water control management 
costs were $887,900 and the amount of $25,600 was expended 
on Master Plans. Supervision and administration for 
operations features cost $296,000. Total operation costs were 
$15,120,500. 
Total operation and maintenance costs were $36,801,000. 
Rehabilitation: Rehabilitation continued at Locks and 
Dams 20, 21, and 22 at a cost of $1,171,815, $164,895, and 
$275,039, respectively. Total rehabilitation costs were $1,611,749. 
25-2

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN * 
Costs to the Rock Island District were $36,801,000 for 
operations and maintenance and $1,611,749 for major 
rehabilitation for a total cost of $38,412,749. 
St. Louis District. New Work: Costs incurred for Melvin 
Price Locks and Dam, formerly Lock and Dam 26 Replacement, 
were $170,202 for real estate acquistion, $95,618 for 
relocations, $53,990 for reservoirs, $10,575,536 for the dam, 
$2,565,546 for the lock, $27,477 for roads, $4,293 for channels, 
-$108,077 for recreation facilities, $291,089 for buildings, 
grounds, and utilities, $52,542 for permanent operating equipment, 
$1,735,206 for engineering and $1,014,693 for supervision 
and administration. Costs incurred for 2nd lock were 
$41,508,677 for the lock, $1,363,379 for engineering and 
$3,430,255 for supervision and administration. Total cost of 
new work was $62,780,426. 
Rehabilitation: None. 
Operating and care: The locks and dams were operated as 
required and necessary repairs were made thereto. Other work 
accomplished was management of natural resources, operation 
of recreation areas, condition and operation studies, 
water control management and other studies and reports for 
a total cost of $6,051,890. 
Costs to St. Louis District were $62,780,426 for new work 
on the Melvin Price Locks and Dam; $6,051,890 for operation 
and care; $7,134,224 for maintenance for a total cost of 
$75,966,540. 
Condition of the channel at end of fiscal year: The controlling 
depths of nine feet at low water and minimum widths 
suitable for long-haul common carrier service were maintained 
in all pools. 
St. Paul District. Work completed: Locks and Dams at St. 
Anthony Falls and 1 to 10, inclusive, except for relatively 
minor appurtenant work; major improvements of channels 
and harbors at St. Paul and Minneapolis; commercial harbors 
at Lake City, Red Wing, and Winona, MN; and Prairie 
du Chien, WI; small-boat harbors at St. Paul, Hastings, Red 
Wing, Wabasha, Lake City and Winona, MN; Lansing, IA; 
and Bay City, Pepin, and Prairie du Chien, WI; a remedial 
drainage ditch at Cochrane, WI; miscellaneous channel dredging 
and realignment; channel markers; pool clearing; and construction 
of various facilities for recreation use. Seepage 
damages totaling $90,027 were paid to 210 claimants. 
Status of land and flowage acquisition; Approximately 
50,293.54 acres of land in fee, including 47,305 acres used 
by the Department of the Interior in accordance with a 
cooperative agreement and general plans, and easements of 
15,549.63 acres of land are owned or controlled in pools 1 
to 10, inclusive, at end of fiscal year. In addition, fee title 
to 12.46 acres and perpetual easements on 2.98 acres of land 
for St. Anthony Falls and perpetual easements over 244.39 
acres of land for harbors have been obtained and Department 
of the Army holds special rights over 62,954.74 acres owned 
by the Department of the Interior in pool Nos. 3 to 10, inclusive. 
Land acquisition is complete. 
Work remaining to complete portion of project in St. Paul 
District: None. 
Condition of channel at end of fiscal year: The controlling 
depths of nine feet at low water and minimum widths for 
long-haul common carrier service were maintained in all 
pools. 
Rock Island District. Work completed: Major construction 
items including all locks and dams, are completed and in 
operation. The following related work has also been completed: 
construction of small-boat harbors at Rock Island, 
IL; Moline, IL; Andalusia, IL; Warsaw, IL; Fort Madison, 
IA; Davenport (Lindsay Park), IA; Muscatine, IA; Clinton, 
IA; and Hanibal, MO; improvement of Beaver Slough at 
Clinton, IA, for navigation; improvement of commercial harbor 
at Dubuque, IA; rehabilitation of old auxiliary lock at 
Lock and Dam 14; permanent closure of old Lock 19 and 
drydock; rock and conglomerate excavation in Pools 15 and 
16; rectification of seepage damage in the Sny Island Levee 
Drainage District, IL; recreational facilities; and construction 
of visitor center at Lock and Dam 15. 
Status of land and flowage acquisition: Acquisition of land 
in Pools 11 to 22, inclusive consisting of 93,601 acres in fee 
and 10,541 acres in flowage easement, has been completed. 
Condition of the channel at end of fiscal year: The controlling 
depths of nine feet at low water and minimum widths 
suitable for long-haul common carrier service were maintained 
in all pools. 
Work remaining to complete portion of project in Rock 
Island District: None. 
St. Louis District. Work completed: Locks and Dams 24, 
25, and Melvin Price Locks and Dam, except for guidewall 
extensions at Locks 24 and 25, have been completed as have 
recreation facilities at the three pools. Payments for rectification 
of damages have been completed. Other work remaining 
consists of construction guidewall extensions at Locks 24 
and 25. Melvin Price Locks and Dam are under construction. 
Status of land and flowage acquisition: Acquisitions of 
lands in Pools 24, 25, and 26, involving 4,448 acres of land 
in fee and flowage easements over 6,600 acres, is complete. 
A total of 4,121 acres has been acquired for the Melvin Price 
Locks and Dam project. 
Condition of channel at end of fiscal year: The controlling 
depth of nine feet at low water and generally suitable 
widths for long-haul common carrier services were maintained 
in all pools and between Melvin Price Locks and Dam and 
Missouri River. 
Work remaining to complete portion of project in St. Louis 
District: Work remaining on the Melvin Price Locks and Dam 
project includes completion of the third stage, (600 foot lock 
and 1 V2 gatebays of the dam). Other work includes construction 
of miscellaneous alterations to the lock, minimum 
facilities for public health and safety and West Alton Access 
Area rehabilitation, removal of a lockwall at old Locks and 
Dam No. 26 and construction of recreation facilities at Alton, 
IL. Approximately 80 acres remain to be acquired for mitigation 
purposes for terrestrial wildlife losses and three acres for 
project navigation purposes. 
Total Federal Costs of existing project to the end of fiscal 
year for the three Districts were $154,960,490: $62,794,837 
for new work; $86,711,806 regular funds for operation and 
maintenance; and $5,453,847 regular funds for rehabilitation. 
25-3

REPORT OF THE SECRETARY OF THE ARMY FOR CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 25-A COST AND FINANCIAL STATEMENT 
Total Cost to 
Project Funding FY89 FY90 FY91 FY92 September 1992 
Mississippi River New Work' 
between Missouri River Approp.2 $36,641,700 $87,951,000 $90,959,000 $62,790,000 $1,104,911,621 
and Minneapolis, Cost3 47,598,654 90,175,203 96,348,541 62,789,022 1,104,889,469 
Minnesota (Federal Maint.4 
Funds) Approp. 57,726,400 70,295,150 80,693,444 88,146,700 1,139,013,682 
Cost 61,399,510 69,715,421 81,122,738 86,711,806 1,116,766,614 
Rehab. 
Approp. 24,729,200 18,519,770 7,332,400 4,981,000 143,188,057 
Cost 24,918,657 18,315,662 6,701,105 5,453,847 142,640,369 
(Contributed Funds) New Work 
Approp. 0 0 0 0 2,041,140 
Cost 0 0 0 0 2,041,140 
1. Includes $72,426,653 for new work on previous projects. 
2. Includes Melvin Price Locks and Dam funds $871,732,000. 
3. Includes Melvin Price Locks and Dam funds $869,971,942. 
4. Includes $10,453,327 for maintenance on previous project. 
TOTAL COSTS OF EXISTING PROJECT 
TABLE 25-B TO SEPTEMBER 30, 1992 
Regular Public Work Emergency 
District Cost Funds Funds Relief Funds Total 
St. Paul New Work' $ 60,165,2782 $24,210,071 $9,071,214 $93,446,563 
Maintenance3 470,994,521 - - 470,994,521 
Rehabilitation 59,613,403 - - 59,613,403 
Total 590,773,202 24,210,071 9,071,214 624,054,487 
Rock New Work' 71,307,945' 17,403,322 11,338,865 100,050,132 
Island Maintenance' 429,265,238 - - 429,265,238 
Rehabilitation 83,026,966 - - 83,026,966 
Total 583,600,149 17,403,322 11,338,865 612,342,336 
St. Louis New Work8 899,076,158' 10,282,566 2,440,266 911,798,990 
Maintenance 225,739,684 - - 225,739,684 
Total 1,124,815,842 10,282,566 2,440,266 1,137,538,674 
1. Excludes $2,041,140 contributed funds. Includes $7,673 expended 
in pool No. 11. 
2. Includes $159,359 transferred from Rock Island District covering 
pro rata share of cost of derrick boat Hercules. 
3. Includes $762,196 expended between 1930 and 1936 on operating 
and care of works of improvement under provisions of permanent 
indefinite appropriation for such purposes. Excludes $797,670 contributed 
funds. 
4. Excludes $58,999 contributed funds. 
5. $687,709 was transferred to St. Louis District in fiscal year 1958. 
Excludes $201,167 transferred to St. Paul and St. Louis Districts 
covering their pro rata share of cost of derrick boat Hercules. 
6. Costs subsequent to FY 1953 included with operating and care. 
Includes the sum of $395,442, expended between 1930 and 1934 on 
the operating and care of the works of improvement under the provisions 
of the permanent indefinite appropriation for such purposes. 
7. Includes $47,800 transferred from Rock Island District covering 
pro rata cost of derrick boat Hercules and $687,709 transferred from 
Rock Island District. 
8. Includes $869,971,942 for Melvin Price Locks and Dam. 
25-4

TABLE 25-C LOCKS AND DAMS 
Lock Dimensions 
Greatest Depth on Character of Foundation Percent 
Width Length Upper Miter Sill Complete 
Miles of Available Normal Locks, Year Estimated Cost of 
Above Cham- for Full Pool Dams, and Opened Each Lock and 
Ohio Miles from ber Width Lift Eleva- Upper Lower Work in to Navi- Dam Including 
Lock and Dam River Nearest Town (feet) (feet) (feet) tion (feet) (feet) Lock Dam Pool gation Work in Pool 
St. Anthony 853.9 In city of 56 400 49.2 799.2 15.7 13.7 Some lime- Limestone. 1002 - $ 18,203,000 
Falls, upper 
Lock 
St. Anthony 
Falls, lower 
Lock and dam 
Lock and dam 
1 
Lock and dam 
2 
Lock and dam 
3 
Lock and dam 
4 
Lock and dam 
5 
Lock and dam 
N 5A 
S Lock and dam 
6 
Lock and dam 
7 
Lock and dam 
8 
Lock and dam 
9 
Lock and dam 
10 
Lock and dam 
11 
Lock and dam 
12 
Lock and dam 
13 
Lock and dam 
14 
Le Claire Lock 
tCanal) 
Lock and dam 
15 
Lock and dam 
16 
Minneapolis, 
MN 
853.3 In city of 
Minneapolis, 
MN 
847.6 Minneapolis- 
St. Paul, MN 
815.2 1.3 above 
Hastings, MN 
796.9 6.1 above Red 
Wing, MN 
752.8 Alma, WI 
738.1 Minneiska, MN 
728.5 3 above 
Winona, MN 
714.3 Trempealeau, 
WI 
702.5 Dresbach, MN 
679.2 Genoa, WI 
647.9 3.3 below 
Lynxville, WI 
615.1 Guttenberg, IA 
583.0 3.7 above 
Dubuque, IA 
556.7 Bellevue, IA 
522.5 4.3 above 
Clinton. IA 
493.3 3.7 below 
Le Claire. IA 
493.1 3.9 below 
Le Claire. IA 
482.9 Foot of Arsenal 
Island, Rock 
Island, IL 
457.2 1.8 above 
Muscatine. IA 
stone, mainly 
sandstone. 
No piles. 
56 400 26.9� 750.0 13.7 10.3 Sandstone. No Sandstone. 
piles. 
56 400 35.94 725.1 13.5� 10.1 Rock and piles Piles in gravel. 
56 400 35.9 - 12.5' 7.6 in gravel. 
110 500 12.2 - 16.0 15.1 Piles in sand, Piles in sand, 
1108 6008 12.2 687.2 22.2 13.0 silt and clay. silt and clay. 
110 600 8.0 675.0 17.0 14.0 Piles in sand, Piles in sand. 
silt and clay. 
110 600 7.0 667.0 17.0 13.0 Piles in sand Piles in sand 
and gravel, and gravel. 
110 600 9.0 660.0 18.0 12.0 Piles in sand Piles in sand. 
and gravel. 
.10 600 5.5 651.0 18.0 12.5 Piles in sand. Piles in sand. 
110 60) 6.5 645.5 17.0 12.5 Piles in sand, Piles in sand 
gravel and and clay. 
silt. 
110 600 8.0 639.0 18.0 12.0 Piles in sand Piles in sand. 
and gravel. 
110 600 11.0 631.0 22.0 14.0 Piles in sand, Piles in sand 
gravel and and gravel. 
broken rock. 
10 600 9.0 620.0 16.0 13.0 Piles in sand. Piles in sand. 
110 600 8.0 611.0 15.0 12.0 Piles in sand. Piles in sand. 
110 600 11.0 603.0 18.5 12.5 Piles in sand, Piles in sand. 
gravel and 
silt. 
110 600 9.0 592.0 17.0 13.0 Piles in sand Piles in sand 
and gravel, and gravel. 
.10 600 11.0 583.0 19.0 13.0 Piles in sand, Piles in sand 
clay and and gravel. 
gravel. 
110 600 11.0 527.0 20.5 13.5 Rock. Rock. 
80 320 11.0 - 17.6 10.9 Rock. Rock. 
110 600 16.0 561.0 24.011 11.0 Rock. Rock. 
L10 360 16.0 - 17.011 11.0 
L10 600 9.0 545.0 17.0 12.0 Piles in sand Piles in sand 
and gravel, and gravel. 
100 1959 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
99 
99 
100 
92 
100 
100 
1917 
1930 
1948 
1938 
1935 
1935 
1936 
1936 
1937 
1937 
1938 
1936 
1937 
1938 
1938 
1939 
1922 
1934 
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1 
12,382,0008 
CID 
2,358,000' 
6,492,000' 
5,596,000 
4,865.000 
5,081,000 
4,549,000 Z 
4.874,000 U, 
O 
5,574,000 
6.061,000 z 
6,539,000 
z
z 
4,750,000 
7,428,000 0 
5,580,000 
7,502,000 
6,284,000
_o 
14,201,000 
98 1937 9,788,000

TABLE 25-C (Cont'd) LOCKS AND DAMS 
Lock Dimensions 
Greatest Depth on Character of Foundation Percent 
Width Length Upper Miter Sill Complete 
Miles of Available Normal Locks, Year Estimated Cost of 
Above Cham- for Full Pool Dams, and Opened Each Lock and 
Ohio Miles from ber Width Lift Eleva- Upper Lower Work in to Navi. Dam Including 
Lock and Dam River Nearest Town (feet) (feet) (feet) tion' (feet) (feet) Lock Dam Pool gation Work in Pool 
Lock and dam 437.1 4.2 above New 110 600 8.0 536.0 16.0 13.0 Piles in sand Piles in sand. 99 1939 $ 5,843,000 
17 Boston, IL and gravel. 
Lock and dam 410.5 6.5 above 110 600 9.8 528.0 16.5 13.7 Piles in sand. Piles in sand. 90 1937 10,308,000 
18 Burlington, 
IA 
Lock and dam 364.2 Keokuk, IA 110 358 
19 110 1,200 
Lock and dam 343.2 0.9 above 110 600 
20 Canton, MO 
Lock and dam 324.9 2.1 below 110 600 
21 Quincy, IL 
Lock and dam 301.2 1.5 below 110 600 
22 Saverton, MO 
Lock and dam 273.4 Clarksville, MO 110 600 
24 
Lock and dam 241.4 Cap Au Gris, 110 600 
t 25 MO 
Lock and dam 202.9 Alton, IL 110 600 
' 26 (Henry T. 110 360 
Rainey Dam)"' 
Melvin Price 200.8 Alton, IL 110 1,200 
Locks and Dam 
Melvin Price 200.8 Alton, IL 110 600 
Locks and Dam 
(2nd Lock) 
Total, Locks 
and dams 
38.2 518.2 4.5 9.2 Rock. 
5.0 13.0 
10.0 480.0 15.0 12.0 Rock. 
Rock. 
Rock and 
piles in 
sand and 
gravel. 
10.5 470.0 16.5 12.0 Piles in sand Piles in sand 
and gravel, and gravel. 
10.2 459.5 18.0 13.8 Rock. Rock. 
15.0 449.0 19.0 12.0 Rock and piles. Piles in sand. 
15.0 434.0 19.0 12.0 Piles in sand Piles in sand 
and gravel, and gravel. 
24.0 419.0 19.0 10.0 Piles in sand. Piles and 
24.0 - 16.0 10.0 sand. 
24.0 419.0 23.0 18.0 Piles to 
bedrock. 
24.0 419.0 42.0 18.0 Piles to 
bedrock. 
Piles to 
bedrock. 
Piles to 
bedrock. 
100 
99 
97 
95 
99 
1913 
1957 
1936 
1938 
1938 
9914 1940 
9914 1939 
100 1938 
92 
84 
1990 
0
0
O 
1. Elevation of pools 1 to 22 and at St. Anthony Falls are mean sea level 9. In addition, $1,965,300 expended from previous projects. 
1912 adjustment: pools 24, 26 are mean sea level 1929 adjustment. 10. Existing Le Claire Canal lock is used as auxiliary to lock 14; previous 
2. Includes existing dam, owned by Northern States Power Co. project cost $540,000. 
3. Includes dredging above upper lock. (Federal cost only.) 11. Depth over upper poiree sill. Depth over upper miter sill is 27 feet, at 
4. Based on pool elevation 723.1 in pool 1 which is crest of dam. Pool lock 15. 
is normally maintained at elevation 725.1 by flashboards. 12. $640,868 for first lock was reported by Mississippi River Power Com- 
5. Includes lower approach dredging and dredging between upper and lower pany, transferred to Government free in lieu of improvements destroyed. 
rock. (Federal cost only.) (Annual Report, 1928, pp. 1118-1119.) Present estimate includes 
6. In addition $1,948,000 expended from previous projects and $1,349,600 $13,132,600 for main lock and appurtenant work. 
from O & C appropriation for first of twin locks. Excludes lock and 13. Includes cash contribution of $4,850,000 
dam rehabilitation program. 14. Complete except for guidewall extensions. 
7. Old upper guard sill. 15. Lock and Dam 26 has been replaced by the Melvin Price Locks and 
8. Landward lock. Dam at which full pool was raised 1 February 1990. Lock and Dam 
26 has been removed. 
14,813,0002 
6,281,000 
8,065,000 
0 
5,275,000 
10,337,000 
13,694,000 
12,824,000 
750,850,000 
212,600,000 
$ 1,188,997,000 
0
0
0
N
.r 
C
ru 
O

TABLE 25-D HARBOR IMPROVEMENTS 
Miles above Project Approximate size (feet) Actual or 
Name Miles above Location Type depth Percent Estimated 
(feet) Width Length Complete Cost 
St. Paul Harbor, MN 
Hastings Harbor, MN 
Red Wing Harbor, MN 
Red Wing Harbor, MN 
Bay City Harbor, WI 
Lake City Harbor, MN 
Pepin Harbor, WI 
Wabasha Harbor, MN 
Alma Harbor, WI 
Winona Harbors, MN 
Lansing Harbor, IA 
Prairie du Chien 
Harbor, WI 
Dubuque Harbor, IA 
Savanna Harbor, IL 
Clinton Harbor, IA 
Moline Harbor, IL 
Davenport Harbor, IA 
(Lindsay Park) 
Rock Island Harbor, IL 
Andalusia Harbor, IL 
Muscatine Harbor, IA 
Fort Madison Harbor, 
IA 
836.5-839.2 In city of St. Paul, MN 
839.7 Channel improvement, 
Small-boat harbor and 
channel enlargement. 
813.2 Lower end of city of 
Hastings, MN 
791.4 In city of Red Wing, MN 
791.1 In city of Red Wing, MN 
785.9 Upper end of Bay City, 
WI 
773.0 In city of Lake City, MN 
767.1 
760.0 
751.3 
726.0 
726.2 
663.3 
635.5 
635.0 
579.4 
537.3 
519.0 
488.0 
484.2 
479.8 
473.0 
455.5 
455.6 
In city of Pepin, WI 
Upper end of city of 
Wabasha, MN 
Upper end of Alma, WI 
In city of Winona, MN 
Latsch Island 
Crooked Slough 
Upper end of city of 
Lansing, IA 
Upper end of city of 
Prairie du Chien, WI 
In Marais de St. Friol 
East Channel below 
Hwy bridges. 
At Dubuque, IA 
At Savanna, IL 
At Clinton, IA 
At Moline, IL 
At Lindsay Park 
At Rock Island, IL 
Andalusia Slough 
At Muscatine, IA 
383.7 At Fort Madison, IA 
Commercial 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Commercial' 
Small-boat' 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
Commercial 
Small-boat 
Small-boat 
Commercial 
Commercial 
Small-boat 
Small-boat 
Small-boat 
Small-boat 
9 400-1,000 2.7(mile) 100 S 217,100 
5 300 400 100 230,200 
200 
300 
450 
50-100 
400 
500 
500 
50 
175-400 
300 
200 
200 
170 
400 
500 100 
1,200 100 
800 100 
5,990 100 
600 
1,000 
850 
600 
800 
100 
100 
100 
100 
100 
500 100 
1,000 100 
6,000 100 
500 100 
800 100 
1,000 
frontage 
340 
280 
400 
230 
200 
100 
40 
150 
200 
250 
1,500 
910 
1,400 
660 
1,150 
100 
100
0 
78 
100 
1,100 100 
435 100 
950 100 
1,890 100 
74,300 
146,800' 
8,700 C 
39,400'2 
cI 
93,500 
1,077,000' 
205,500' 
41,700 
56,300 
89,800 y 
84,700 
95,300 Z 
85,500 
93,100 
55,200 Z 
310,000 
101,912 
110,328 Z2 
262,100 
31,000 
O 
21,000 
353,000 .c
2 
900 100 184,200 
12
5555 
Entrance channel 
small-boat harbor 
Small-boat 
Small-boat 
Freight terminal 
approach channel 
Small-boat 
N

Project Approximate size (feet) Actual or 
Name Miles above Location Type Depth Percent Estimated 
Ohio River (feet) Width Length Complete Cost 
Warsaw Harbor, IL 359.1 At Warsaw, IL Small-boat 5 100 600 100 $ 73,000 
Quincy Harbor, IL 327.3 In Quincy Bay, IL Small-boat 5 200-300 9,000 0 
Hannibal Harbor, MO 308.8 At Hannibal, MO Small-boat 5 180-260 600 100 129,000 
Total $4,269,640 
1. In addition, local interests contributed $3,455. 
2. In addition, local interests contributed $9,533. 
3. Commercial harbor converted to small-boat harbor under authority 
of Section 107 of 1960 River and Harbor Act, as amended. Primary 
use is small-boat, although some commercial activity exists. 
4. In addition, local interests contributed $812,599. 
5. In addition, local interests contributed $32,344. 
6. Maintenance only, estimated at $5,000 annually. 
N
00 
l
6 
0
0
0
0
0
cJ 
nl) 
0
7d
d 
TABLE 25-D (Cont'd) HARBOR IMPROVEMENTS

TABLE 25-E 
MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
ADDITIONAL FEATURES ENTERING INTO 
COST OF PROJECT 
Facilities for public use, convenience and safety 
Rectification of damages caused by seepage and backwater 
Regulating works between Melvin Price Locks and Dam and Missouri River 
Improvement of Beaver Slough at Clinton, Iowa, for navigation 
Miscellaneous 
Total additional features 
Total existing project (new work) 
$ 13,040,500 
8,580,000' 
545,000 
193,600 
5,936,9002 
18,705,9003 
$ 516,183,512 
1. Includes a lump-sum payment of $2,146,800 (O&M appropriation) paid 
to the Sny Island Levee Drainage District, IL, for rectification of seepage 
damages. Also includes $140,000 Construction General funds for project 
studies, evaluation, and report preparation. 
2. Includes $686,500 for repairs to Stone Arch Bridge, Minneapolis, MN. 
(FY 1969) 
3. Excludes $227,000 (1965) for inactive remedial measures at Sandy 
Slough, MO. 
LICENSE FEES COLLECTED 
TABLE 25-F THROUGH FISCAL YEAR 1992 
Annual Collections to 
Dam Licensee Charge Sept. 30, 1992 
St. Anthony Falls Lower Northern States Power $ 3,300 $ 99,877 
Lock and Dam Co. (No. 2056) 
Lock and Dam No. 1 Ford Motor Co. 95,400 6,393,840 
Lock and Dam No. 2 City of Hastings, MN. 24,163 108,373 
TOTAL $ 6,602,090 
25-9

REPORT OF THE SECRETARY OF THE ARMY FOR CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 25-G AUTHORIZING LEGISLATION 
Acts Work Authorized I)ocuments 
Sep. 22, 1922 
July 3, 1930 as 
amended by P.R. 
No. 10, Feb. 24, 
1932 
June 26, 1934 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 30, 1935 
Aug. 26, 1937 
Dl)c. 22, 1944 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
None 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Sep. 3, 1954 
Sep. 3, 1954 
July 3, 1958 
July 3, 1958 
MISSISSIPPI RIVER BETWEEN MISSOURI RIVER AND 
MINNEAPOLIS, MN 
Dredging channels to landing places. 
Project adopted from Illinois River to Minneapolis; Chief of 
Engineers granted discretionary authority to make such 
modification in plan as may be deemed advisable. 4 
Operation of snag boats and operation and care of locks and dams 
to be provided for with funds from Department of the Army 
appropriations for rivers and harbors. 
Missouri River established as lower limit of project. 
Extension of 9-foot channel above St. Anthony Falls, MN, 
including adequate terminal facilities for Minneapolis, MN 
St. Paul, MN harbor. 
Determine damages to drainage and levee districts caused by 
seepage and backwater, and cost of making rectification thereof. 
Public park and recreational facilities. 
Red Wing, MN harlor. 
Remedial works to correct damages caused by seepage and 
backwater at Cochrane, WI 
Such changes or additions to payments, remedial works, or land 
acquisitions authorized by River and Harbor Act of Aug. 26, 
1937 (River and Harbor Committee Doc. 34, 75th Cong., 1st 
sess.), as Chief of Engineers deems advisable. 
St. Paul, MN channel enlargements, small boat harbor, and 
roadway. 
Vertical bridge clearance at Minneapolis to 26 feet above 
estimated stage for discharge of 40,000 c.f.s. 
Winona, MN basin. 
Future modification of lock and dam No. 2 for power 
development. 
Provides for cash contribution by local interests in lieu of 
alteration of privately owned bridges and utilities for St. 
Anthony Falls project. 
Lake City, MN harbor. 
Wabasha, MN harbor. 
Payment of damages caused by backwater and seepage, pools 3 
to 11. 
Hastings, MN harbor. 
Lansing, IA harbor. 
Fort Madison, IA harbor. 
Payment of damages caused by pool No. 14 at Clinton, IA. 
Davenport, IA harbor. 
Muscatine, IA harbor. 
Alma, WI harbor. 
Hannibal, MO harbor. 
Prairie du Chien, WI harbors. 
Opposite Ilamburg, II,ha rbor.' 
Permits such change in location of Winona, MN small boat basin 
authorized by River and Harbor Act of Mar. 2, 1945 (II. Doc. 
263, 77th Cong., 1st sess.), as Chief of Engineers deems advisable. 
Construction of Crooked Slough Harbor at Winona, MN, in lieu 
of previously authorized commercial harbor. 
Payment of damages caused by pool No. 24 at Louisiana, MO. 
Permits modification of vertical bridge clearances and authorizes 
completion of St. Anthony Falls project. 
Small boat and commercial harbors at Alton, IL.2 
None 
H. Doc. 290, 71st Cong., 2d sess. 
None 
H. Doc. 137, 72nd Cong., 1st sess. 
H. Doc. 137, 72nd Cong. Ist 
sess. 
Rivers and Harbors Committee 
Doc. 44, 74th Cong., Ist sess. 
Rivers and hlarbors Committee 
Doc. 34, 75th Cong., 1st sess. 
None 
11. I)oc. 103, 76th Cong., Ist 
sess. 
H. Doc. 137, 76th Cong., 1st 
sess. 
None 
H. Doc. 547, 76th Cong., 3rd 
sess. 
S. Doc. 54, 77th Cong., 1st sess. 
H. Doc. 263, 77th Cong., 1st 
sess. 
11. Doc. 4:32, 77th Cong., Isl.t 
sess. 
H. Doc. 449, 78th Cong., 2d sess. 
H. Doc. 511, 79th Cong., 2(d ses. 
H. Doec. 514, 79th Cong., 2d sess. 
H. Doc. 515, 79th Cong., 2d sess. 
H. Doc. 559, 79th Cong., 2d sess. 
S. Doc. 192, 79th Cong., 2d sess. 
H. Doe. 661, 80th Cong. 2d sess. 
S. Doc. 197, 80th Cong., 2d seas. 
H. Doc. 642, 80th Cong., 2d sess. 
H. Doc. 733, 80th Cong., 2d sess. 
H. Doc. 66, 81st Cong., 1st sess. 
H. Doc. 67, 81st Cong., 1st sess. 
H. Doc. 71, 81st Cong., Ist seas. 
1l. Doe. 254, 81st Cong., Ist sess. 
None 
H. Doc. 347, 83rd Cong., 2d 
H. Doc. 251, 82nd Cong., Ist 
sess. 
H. Doc. 33, 85th Cong., 1st sess. 
H. Doc. 136, 84th Cong., 1st sess. 
25-10

MISSISSIPPI RIVER BETWEEN MISSOURI AND MINNEAPOLIS, MN 
TABLE 25-G (Cont'd) AUTHORIZING LEGISLATION 
Acts Work Authorized Documents 
July 3, 1958 Payment of lump sum amounts for damages to drainage and levee H. Doc. 135, 84th Cong., 1st sess. 
districts caused by operation of navigation pools. 
July 3, 1958 Improvement and maintenance of Beaver Slough at Clinton, IA. H. Doc. 345, 84th Cong., 2d sess. 
Mar. 3, 1959 Reconstruction of structures as may be necessary to provide None 
adequate facilities for existing navigation. 
July 14, 1960 Construction of Industrial Harbor at Red Wing, MN. H. Doc. 32, 86th Cong., 1st sess. 
Oct. 23, 1962 Construction of small-boat harbors at Savanna2, Moline, H. Doc. 513, 87th Cong., 2d sess. 
Andalusia, New Boston5, Warsaw, Quincy, and Grafton, IL; 
Bellevue', Clinton, Davenport, and Keokuk3, IA; St. Paul 
(Harriet Island), MN'; and Bay City, Pepin, and Cassville', WI. 
Oct. 23, 1962 Payment of damages caused by pool 24 at Clarksville, MO. H. Doc. 552, 87th Cong., 2d sess. 
Oct 23, 1962 Remedial works at Sandy Slough, MO. H. Doc. 419, 87th Cong., 2d sess. 
Nov. 7, 1966 Repair of Stone Arch Bridge at Minneapolis, MN. None 
Oct. 21, 1978 Replacement of Lock and Dam 26 Public Law 95-502 
Dec. 29, 1981 Change name of Lock and Dam 26 to Melvin Price Locks and Dam Public Law 97-118 
effective on the date of Melvin Price's death. 
(Apr. 22, 1988 - date of death) 
1. Deauthorized FY 75. 
2. Inactive. 
3. Deauthorized FY 87 (WRDA of 1986). 
4. Guidewalls at Locks 3, 4, 5, 5A, 7, 8, 9, and 10 deauthorized FY 87 (WRDA of 1986). 
5. Deauthorized FY 90 (WRDA of 1986). 
6. Guidewall extensions at Locks 16, 18, and 21; construction of mooring facilities at Locks and Dams 11, 12, 14, 15, 16, 17, and 18; 
upper approach improvement at Lock 19 and Lock and Dam 20; and rock and/or conglomerate excavation in Pools 14, 18, and 21 
deauthorized FY 90 (WRDA of 1986). 
25-11

OMAHA, NE, DISTRICT* 
This district comprises portions of Montana, Wyo- drainage basin of Missouri River along main stem and 
ming, North Dakota, South Dakota, Minnesota, Colo- tributraries to Rulo, NE. 
rado, Nebraska, Iowa, and Missouri, all embraced in 
IMPROVEMENTS 
Navigation Page 
1. Missouri River, Sioux City, IA 
to Rulo, NE ................................. 26-2 
2. Navigation Work Under Special 
Authorization ............................... 26-2 
Flood Control 
3. Bear Creek Lake, CO ....................... 26-2 
4. Bowman-Haley Lake, ND .................... 26-2 
5. Chatfield Lake, CO ........... ......... 26-2 
6. Cherry Creek Lake, CO ...................... 26-3 
7. Fall River Basin, SD ........................ 26-3 
8. Little Sioux River, IA ....................... 26-3 
9. Lost Creek at Columbus, NE ................ 26-3 
10. Missouri National Recreational 
River, NE and SD .................... 26-3 
11. Missouri River, Kenslers Bend, 
NE to Sioux City, IA ..................... 26-4 
12. Missouri River Levee System, 
Sioux City, IA to Rulo, NE ................. 26-4 
13. Papillion Creek and Tributaries 
Lakes, NE ................................ 26-4 
14. Pebble Creek, Scribner, NE ................... 26-4 
15. Pick-Sloan Missouri River Basin 
Program (Omaha Dist) ....................... 26-5 
16. Pipestem Lake, ND ........................ 26-5 
17. Salt Creek & Tributaries, NE .............. 26-5 
18. South Platte River Basin, CO ................ 26-5 
19. Westerly Creek, CO ......................... 26-5 
20. Inspection of Completed Flood 
Control Works .................... ....... 26-5 
21. Scheduling Flood Control 
Resrvoir Operations ......................... 26-6 
22. Flood Control Activities Under 
Special Authorization ........................ 26-6 
Multiple Purpose Projects Including Power Page 
23. Big Bend Dam-Lake Sharpe, 
Missouri River Basin, SD ................... 26-6 
24. Fort Peck Lake, MT ........................ 26-6 
25. Fort Randall Dam-Lake Francis Case, 
Missouri River Basin, SD ................... 26-6 
26. Garrison Dam-Lake Sakakawea, 
Missouri River Basin, ND ................. 26-7 
27. Gavins Point Dam-Lewis and Clark Lake, 
Missouri River Basin, NE and SD............26-7 
28. Oahe Dam-Lake Oahe, Missouri 
River Basin, SD and ND ................... 26-7 
29. Missouri River Master Water 
Control Manual Review and Update.......... 26-7 
Miscellaneous 
30. National Emergency Preparedness ............ 26-8 
General Investigations 
31. See Table 26-K ........................... .... 26-8 
Tables 
26-A Cost and Financial Statement ............ 26-9 
26-B Authorizing Legislation ................... 26-12 
26-C Other Authorized Navigation Projects......26-15 
26-D Not Applicable 
26-E Other Authorized Flood Control Projects...26-15 
26-F Other Multiple Purpose Projects 
Including Power ........................ 26-17 
26-G Deauthorized Projects .................... 26-17 
26-H Missouri River Levee System, 
Sioux City, IA to Rulo, NE ............... 26-18 
26-I Pick-Sloan Missouri Basin Program........ 26-18 
26-J Inspection of Completed Local 
Protection Projects ....................... 26-18 
26-K Active General Investigations ............. 26-21 
26-L Flood Control Activities 
Under Special Authorization ............. 26-23 
26-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA 
TO MOUTH (SIOUX CITY, IA 
TO RULO, NE) 
Location. Channel of the Missouri River extending 
from Sioux City, IA to Rulo, NE. 
Previous projects. For details see page 1893, Annual 
Report for 1915, and page 1175, Annual Report for 1938. 
Existing project. Provides for a navigation channel of 
9-foot depth and width not less than 300 feet, obtained by 
revetment of banks, rock dikes to contract and stabilize 
waterway, cutoffs to eliminate long bends, closing minor 
channels, and removal of snags and dredging as required. 
Construction was initiated on this section of the project 
(Sioux City to Rulo) in fiscal year 1928, the bank stabilization 
work was completed in April 1979, and the navigation 
feature was completed in September 1980. A reliable 
channel suitable for navigation is available through this 
section. Controlling depth at ordinary stages of the river is 
9 feet, with additional depths available during high stages. 
Commercial navigation was inaugurated on this section in 
May 1939, and common carrier transportation service 
was inaugurated in October 1946. Seven riverside recreation 
sites are complete and in operation. Total cost was 
$189,226,000, of which $187,639,000 is the Federal cost of 
construction and $1,587,000 is the non-Federal cost, exclusive 
of amounts expended on previous projects. 
Local cooperation. Requirements are described in full 
on page 26-2 of fiscal year 1988 Annual Report. 
Terminal facilities. Terminal facilities for loading and 
unloading grain, liquids and dry bulk products are maintained 
by private interests at various locations on this 
section of the river. A complete list of terminal facilities 
are included in the Missouri River Navigation Maps and 
can be obtained from the Omaha District for a small fee. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Local interests 
operate and maintain the recreation sites. 
2. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Small Navigation Projects Not Specifically Authorized 
by Congress (Sec. 107 of the River and Harbor Act of 
1960, as amended, Public Law 645, 86th Congress). 
No work during the period. 
Flood Control 
3. BEAR CREEK LAKE, CO 
Location. Damsite is on Bear Creek in Jefferson 
County, CO about 8 miles above the confluence of Bear 
Creek with the South Platte River at Denver. 
Existing project. Earthfill dam 180 feet high, with a 
crest length of about 5,300 feet, and a supplementary 
earthfill dike with a height of 65 feet and a crest length of 
2,100 feet, to the south of the main dam, and an uncon- 
*trolled earth and rock-cut emergency spillway. The lake 
provides storage capacity of 28,831 acre-feet for flood 
control and 1,979 acre-feet for sediment and recreation. 
Construction of the project was initiated in October 1973 
and was completed in September 1982, exclusive of recreation 
facilities. The total cost of the project was 
$61,518,608. Recreation facilities were developed utilizing 
cost sharing funds at an additional cost of $500,000. 
Local cooperation. Requirements are described in full 
on page 21-3 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Annual project 
visitation hours were estimated at 425,700. 
4. BOWMAN-HALEY LAKE, ND 
Location. Damsite is on North Fork of Grand River in 
southwestern North Dakota, about 6 miles above Haley, 
ND. 
Existing project. A dam 79 feet high, with a crest length 
of 5,730 feet, and reservoir with a storage capacity of 
about 19,780 acre-feet for sediment storage, fish and wildlife 
conservation, recreation, and future water supply for 
communities of Bowman, Reeder, Scranton, and Gascoyne, 
ND. Construction was initiated in July 1964, and 
the project was completed in 1970. (See Table 26-A for 
total cost of construction.) 
Local cooperation. Requirements are described in full 
on page 26-2 of fiscal year 1988 Annual Report. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Annual project 
visitation hours were estimated at 62,700. 
5. CHATFIELD LAKE, CO 
Location. On the South Platte River, just below the 
mouth of Plum Creek, about eight miles upstream from 
Denver, CO. 
Existing project. Consists of rolled earth-fill dam with a 
maximum height of 148 feet, a crest length of 12,500 feet, 
and a reservoir with flood control capacity of 204,737 
acre-feet and sediment capacity of 26,692 acre-feet, which 
will be used for recreation, and an enlarged channel from 
the dam downstream to Denver to accommodate reservoir 
flood releases. 
The Corps participated with local interests in acquisition 
of lands and development of recreation facilities immediately 
downstream of the Chatfield Dam in lieu of a 
portion of the channel improvement. Construction of the 
project was initiated in August 1967 and is essentially 
complete. Estimated cost through construction of the project 
is $104,487,700 (1992) of which $95,472,700 is the 
Federal cost for construction, $6,115,000 local cost in connection 
with the downstream channel improvement, and 
$2,900,000 is the local cost for acquisition of water for the 
recreation pool. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies to the downstream channel improvement. 
The Colorado Water Conservation Board 
provided assurances of local cooperation for the downstream 
improvement on December 13, 1967. Local interests 
must provide water for filling the sediment reserve 
pool for recreation use which the state agreed to on April 
25, 1967. 
26-2

OMAHA, NE, DISTRICT 
Operations during fiscal year. Continued design by 
hired labor. Maintenance: Continued routine operation 
and maintenance activities. Annual project visitation 
hours were estimated at 4,267,100. 
6. CHERRY CREEK LAKE, CO 
Location. Damsite is on Cherry Creek in Arapahoe 
County, CO, approximately 6 miles southeast of Denver, 
CO just outside of city limits. Cherry Creek joins South 
Platte River within city limits of Denver. 
Existing project. A rolled earth-fill dam with maximum 
height of 141 feet above streambed and 14,300 feet long. 
Project includes a reinforced concrete outlet works and an 
uncontrolled side channel spillway canal discharging into 
adjacent Toll Gate Creek. Cherry Creek project provides 
reservoir storage capacity of 93,920 acre-feet below spillway 
canal invert and, in addition, a surcharge storage of 
134,470 acre-feet. Plan of operation in ultimate development 
for multiple-purpose uses includes 13,960 acre-feet 
for sediment storage and 79,960 acre-feet for conservation 
purposes. Construction began in fiscal year 1946 and was 
completed in June 1961, exclusive of recreation facilities. 
Federal cost of the project was $15,220,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Continued 
routine operation and maintenance activities. Annual project 
visitation hours were estimated at 6,934,400. 
7. FALL RIVER BASIN, SD 
Location. In Custer and Fall River Counties, in and 
near the town of Hot Springs, SD. Hot Springs unit is in 
the town of Hot Springs, immediately south of the junction 
of Cold Brook and Hot Brook which combine to 
form the Fall River. Cold Brook Lake unit is approximately 
1.25 miles north of the town of Hot Springs on 
Cold Brook; and Cottonwood Springs Lake unit is approximately 
4.5 miles west of the town of Hot Springs on 
Cottonwood Springs Creek, one-half mile upstream from 
its confluence with Hot Brook. 
Existing project. The general plan of improvement 
provides flood protection for Hot Springs, SD. The Hot 
Springs channel improvement unit consisted of widening, 
deepening and straightening 6,000 feet of channel of Fall 
River. The Cold Brook Lake unit, an earth-fill dam with 
appurtenant structures, controls an area of 70.5 square 
miles. The Cottonwood Springs Lake unit consists of an 
earth-fill dam with appurtenant structures and controls an 
area of 26 square miles. Construction of Hot Springs unit 
was completed during fiscal year 1951. Construction of 
Cold Brook unit dam and appurtenances was completed 
in fiscal year 1953 with exception of a road and parking 
area which were completed in fiscal year 1955. Construction 
of the Cottonwood Springs unit dam was completed 
in fiscal year 1970, with the exception of the recreation 
facilities which were completed in fiscal year 1972. (See 
Table 26-A for total cost of construction.) 
Local cooperation. Local cooperation requirements 
have been fully complied with. 
Operations during fiscal year. Maintenance: Routine 
operation and maintenance activities were continued on 
the Cottonwood Springs and Cold Brook Dams and structures. 
Annual project visitation hours were estimated at 
663,100. 
8. LITTLE SIOUX RIVER, IA 
Location. The project is located in the lower portion of 
the Little Sioux River Basin in Harrison and Monona 
Counties, IA, near the confluence of the Little Sioux and 
Missouri River. 
Previous project. For details see page 646, Annual Report 
for 1970. 
Existing project. Construction of the original project 
was completed in June 1966. Sill No. 4 was identified as a 
design deficiency in a June 17, 1981 report by the Omaha 
District, approved by OCE. Based on that report, design 
studies for a permanent solution to the problem were 
completed. Estimated cost through construction of the 
project is $23,630,000 (1991) of which $20,630,000 is the 
Federal cost of construction, and $3,000,000 is the local 
cost for lands, relocations, and associated E&D. 
Local cooperation. The Little Sioux Inter-County 
Drainage District was sponsor of that portion of the original 
project where the remedial work is being accomplished. 
Remedial work was 100 percent Federally 
funded. 
Operations during fiscal year. Project is financially 
complete. 
9. LOST CREEK AT COLUMBUS, NE 
Location. On Lost Creek just north of the City of 
Columbus in Platte County, NE. 
Existing project. This project provides levee and channel 
improvements on the north side of Columbus and 
provides protection to commercial and residential areas. 
The estimated cost of the construction is $4,439,518 
(1992) of which $3,579,518 is the Federal cost, and 
$860,000 is non-Federal contributed funds -other, that 
provides for all necessary right of way, utility, and bridge 
relocations. 
Local cooperation. A contract with the City of Columbus 
to sponsor the project was approved on February 18, 
1982. 
Operations during fiscal year. A contractor's claim was 
denied in July 1990 by the contracting officer. Subsequently, 
the contractor appealed this decision to the U.S. 
Claims Court, where it is presently being litigated by the 
Justice Department. 
10. MISSOURI NATIONAL RECREATIONAL 
RIVER, NE AND SD 
Location. NE and SD. The Missouri River between 
Gavins Point Dam and Ponca State Park, NE. This includes 
Cedar and Dixon Counties in Nebraska, and Yankton, 
Clay, and Union Counties in South Dakota. 
Existing project. The designation as a National Recreational 
River will preserve outstanding and important 
26-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
scenic values and will provide additional opportunities for 
river access and recreation use. Erosion control, consisting 
of bank stabilization and river management techniques 
designed to preserve the existing environment, will 
at the same time preserve high bank flood plain lands. 
Estimated total cost of construction is $21,640,000 (1992) 
of which $21,000,000 is the Federal cost of construction 
and $640,000 is the non-Federal contributed funds - 
other costs. 
Local cooperation. All construction on this project will 
be done in accordance with the cost sharing and financing 
concepts reflected in the Water Resources Development 
Act of 1986. A cost-sharing contract with the State of 
South Dakota for the Myron Grove access site was signed 
on June 24, 1986 and the Yankton-Riverside Park Section 
215 Agreement was signed on April 24, 1989. 
Operations during fiscal year. Efforts to protect Federally 
listed threatened and endangered species continued. 
11. MISSOURI RIVER, KENSLERS 
BEND, NE, TO SIOUX CITY, IA 
Location. Project is along Missouri River between 
Ponca Bend, NE, and combination bridge at Sioux City, 
IA.
Existing project. Construction of dikes, revetments and 
channel improvement along Missouri River from Miners 
Bend and vicinity, SD and NE, to Sioux City, IA. Project 
was started in June 1946 and completed in June 1961. (See 
Table 26-A for total costs.) 
Operations during fiscal year. Routine operation and 
maintenance activities continued. 
12. MISSOURI RIVER LEVEE SYSTEM, 
IOWA, NEBRASKA, KANSAS AND 
MISSOURI (SIOUX CITY, IA 
TO RULO, NE) 
Location. On both banks of the Missouri River from 
Sioux City, IA to St. Louis, MO. Active portion of the 
project in Omaha District extends from Council Bluffs, 
IA to Rulo, NE. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from 
Sioux City, IA, to mouth, for protection of agricultural 
lands and small communities against floods. Construction 
was initiated June 1948. (See Table 26-H for status of 
active units). Cost estimate for active portion of project 
from Council Bluffs, IA to Rulo, NE is $42,582,000 (1991) 
of which $37,964,000 is Federal cost for construction and 
$4,618,000 local costs for lands and damages. 
Local cooperation. Section 3, Flood Control Act of 
June 22, 1936 applies. Fully complied with for all completed 
units. Local interests have furnished assurances of 
their willingness and ability to fulfill local cooperation 
requirements for the remaining active units. 
Operations during fiscal year. Work continued on the 
O&M manuals. 
13. PAPILLION CREEK AND 
TRIBUTARIES LAKES, NE 
Location. The Papillion Creek basin is located in Washington, 
Douglas, and Sarpy Counties, NE. Big Papillion 
Creek rises west of Blair, flows southeasterly through 
metropolitan Omaha area where it is joined by the Little 
Papillion Creek just above Offutt AFB, forming Papillion 
Creek. The combined creek flows along the side of Offutt 
AFB to its confluence with the Missouri River. 
Existing project. The active project consists of a series 
of four dams and reservoirs, channel improvement and a 
flood warning system on tributaries of Papillion Creek. 
Construction was initiated in FY 1972. Completed projects 
include Standing Bear Lake (Site 16), Glenn Cunningham 
Lake (Site 11), and Wehrspann Lake (Site 20). 
Remaining work includes construction of recreational 
facilities, fish and wildlife facilities and channel improvement 
on the Big Papio Channel and recreational facilities 
on Ed Zorinsky Lake (Site 18). Estimated total costs for 
the project are $68,659,000 consisting of $64,325,000 in 
Federal funds ($5,721,000 to be reimbursed by the non- 
Federal sponsor) and $4,334,000 non-Federal other costs 
and cash contributions. 
Local cooperation. Requirements are described in full 
on page 21-6 of fiscal year 1981 Annual Report. 
Operations during fiscal year. Initiated construction of 
Phase II recreation facilities at Ed Zorinsky Lake (Site 
18), initiated construction on Phase II B and prepared 
plans and specifications for Phase II A for the Big Papio 
Channel. Maintenance: Routine operations and maintenance 
activities continued at all four dam sites. Annual 
project visitation hours were estimated at 3,364,100. 
14. PEBBLE CREEK, SCRIBNER, NE 
Location. Scribner, Nebraska, is located in Dodge 
County about 47 miles northwest of Omaha, Nebraska. 
Pebble Creek is a right-bank tributary to the Elkhorn 
River. 
Existing project. The plan includes a 3.6-mile-long 
levee with an average height of about eight feet providing 
100-year flood protection plus 3 feet of freeboard from 
Pebble Creek, a closure structure at U.S. Highway 275 at 
the northern edge of Scribner, four road ramps over the 
levee, an automated flood warning system, and appropriate 
land use zoning and continued flood insurance for 
unprotected areas. Construction on the Pebble Creek 
levee was completed in October 1989. In the process of 
providing FEMA the necessary data to revise the flood 
insurance rate maps to reflect the Pebble Creek levee, it 
was determined that Scribner is subject to greater residual 
flooding from the Elkhorn River than was previously determined. 
In April 1989 additional studies were began to 
correct the problem. The studies concluded that it would 
be feasible to construct the Elkhorn River levee which will 
be 2.1 miles long with an average height of 4 feet and will 
provide 100-year level of protection with 3 feet of freeboard. 
Local cooperation. The city of Scribner is the non- 
Federal sponsor of the project. The city has obtained costsharing 
assistance from the Nebraska Natural Resources 
Commission and the Lower Elkhorn Natural Resources 
District. 
26-4

OMAHA, NE, DISTRICT 
Operations during fiscal year. Plans and specifications 
for the Elkhorn River levee were completed during FY 
1992. Construction is scheduled for initiation in late 
spring 1993. The total estimated cost of the project is 
$2,884,000. The non-Federal portion of this estimate is 
$688,000 which includes $353,000 for lands, easements 
and rights-of-way. 
15. PICK-SLOAN MISSOURI BASIN 
PROGRAM (OMAHA DISTRICT) 
Location. Flood control improvements in this project 
are along Missouri River and several of its principal tributaries 
and in states comprising Missouri River Basin. 
Existing project. A general comprehensive plan for 
flood control and other purposes in Missouri River Basin 
provides for levees along Missouri River between Sioux 
City, IA, and mouth and reservoirs on main stem of Missouri 
River and tributaries. See individual reports and 
Table 26-I for projects in the Omaha District included in 
the program. 
16. PIPESTEM LAKE, ND 
Location. On Pipestem Creek in Stutsman County, 
ND, 3 miles upstream from where Pipestem Creek joins 
the James River at Jamestown, ND. 
Existing project. The project consists of a rolled earthfill 
dam approximately 108 feet high with a crest length of 
4,000 feet and outlet works of a gated reinforced concrete 
conduit. The reservoir provides 146,880 acre-feet of storage. 
The miltipurpose pool provides space for silt storage 
and 885 acres of water surface for fish, wildlife and recreation 
needs. Construction of the project was initiated in FY 
1970 and completed in FY 1977. (See Table 26-A for total 
construction costs.) 
Local cooperation. Requirements are described in full 
on page 26-6 of fiscal year 1988 Annual Report. 
Operations during fiscal year. Routine operation and 
maintenance activities continued. Annual project visitation 
hours were estimated at 317,200. 
17. SALT CREEK AND TRIBUTARIES, NE 
Location. Salt Creek Basin comprises an area of about 
1,627 square miles in and around Lincoln in southeastern 
Nebraska. 
Existing project. The authorized project consists of a 
system of 10 dams and reservoirs, channel clearing, enlarging 
and realignment, levees and necessary bridge alterations. 
Pursuant to Senate Resolution adopted August 7, 
1964, which authorized a review of Salt Creek survey report, 
remaining units were placed in "inactive" classification. 
Construction of the project began in the spring of 
1962. All work under the active portion of the project, 
consisting of the 10 dams and reservoirs and the channel 
improvements and levees through Lincoln, was completed 
in 1969. Funds were transferred to the project in FY 1980 
with concurrence of Congressional Committees. These 
funds were used to determine an effective method of correction 
for the dispersive clay problem in the completed 
downstream levees through Lincoln. (See Table 26-A for 
total construction costs.) 
Local cooperation. Requirements are described in full 
on page 26-6 of fiscal year 1988 Annual Report. 
Operations during fiscal year. Maintenance: Routine 
operation and maintenance activities continued. Annual 
visitation hours to the system of dams were estimated at 
12,035,600. 
18. SOUTH PLATTE RIVER BASIN, CO 
Location. Flood control improvements in this project 
are along the South Platte River and its tributaries in 
Colorado. 
Existing project. General plan for flood control and 
other purposes provides for construction of Chatfield 
Lake on the South Platte River, Bear Creek Lake on Bear 
Creek, and levee and channel improvements on the South 
Platte River. (See individual reports and Table 26-B 
for authorizing legislation). 
19. WESTERLY CREEK, CO 
Location. Westerly Creek Dam impounds the Westerly 
Creek on Lowry Air Force Base, CO. Lowry Air Force 
Base is just east of Denver, CO. 
Existing project. The project consists of 2 major phases 
and a minor follow-on contract. Phase I involved construction 
of four new buildings and associated utilities. 
Phase II is the embankment and spillway contract which 
includes demolishing existing buildings, utility relocations, 
construction of an embankment, spillway; relocation 
of four golf course greens, relocation of one tee box, 
construction of channels adjacent to the golf course, and 
repair of an existing 48 inch conduit. The follow-on contract 
(construction physically complete) corrected some 
erosion to the collector channel system. 
Local cooperation. The non-Federal sponsor is the Urban 
Drainage and Flood Control District (UDFCD) of 
the Metropolitan Denver area. UDFCD requested credit 
for $6,353,000 in downstream channel improvements, 
which were constructed between 1 January 1978 and 6 
August 1984. The Assistant Secretary of the Army (Civil 
Works) on 14 March 1988 approved credit for the construction 
accomplished by the local sponsor in an amount 
equivalent to the cost of the relocations and collector 
channels. Appropriate adjustments have been made to the 
Federal and non-Federal costs. The local cooperation 
agreement was executed on 2 August 1988. 
Operations during fiscal year. All work is complete with 
the exception of incorporating the final review comments 
into the O&M manuals. 
20. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Flood Control Act of June 22, 1936, and subsequent 
acts require local interests to furnish assurances that they 
will maintain and operate certain local protection projects 
after completion, in accordance with regulations prescribed 
by Secretary of the Army. District Engineers are 
responsible for administration of these regulations within 
the boundaries of their respective districts. 
26-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Inspections of completed local protection projects 
which have been turned over to local interests for maintenance 
and operation during the fiscal year are set forth 
in Table 26-J, Inspections of Completed Local Protection 
Projects. Fiscal year costs were $223,432. 
21. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, Flood Control Act of December 
22, 1944, Corps of Engineers is responsible for detailed 
scheduling of operations involving storage capacity 
reserved for or assigned to flood control in reservoirs constructed 
by Bureau of Reclamation as well as those constructed 
by Corps of Engineers. Costs for FY 1992 were 
$350,362 and total costs to September 30, 1992 were 
$6,713,158. 
22. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency Flood Control Activities - Repair, Flood 
Fighting and Rescue Work (Public Law 99, 84th Cong., 
and antecedent legislation.) 
Federal costs for FY 1992 were $442,825 for disaster 
preparedness and $7,978 for rehabilitation. 
Small Flood Control Projects Not Specifically Authorized 
by Congress (Sec. 205, 1948 Flood Control Act 
as amended, Public Law 858, 80th Cong., June 30, 1948). 
Federal costs for FY 1992 were $204,494 for reconnaissance 
studies, $197,449 for feasibility studies, $121,384 for 
plans and specifications and construction measures and 
$15,475 for litigation on a completed project. See Table 
26-L for detailed breakdown by project. 
Emergency Bank Protection (Sec. 14, 1946 Flood Control 
Act, Public Law 526, 79th Cong., July 24, 1946.) 
Operations under this heading were as follows: Federal 
costs for FY 1992 were $69,169 for projects in the feasibility 
phase and $279,007 for projects in the plans and specifications 
and construction phase. See Table 26-L for detailed 
breakdown by project. 
Multiple-Purpose Projects Including Power 
23. BIG BEND DAM-LAKE SHARPE, 
MISSOURI RIVER BASIN, SD 
Location. On Missouri River, 987.4 miles above 
mouth, near Fort Thompson, SD, and approximately 20 
miles upstream from Chamberlain, SD. Dam is located in 
the upstream reach of Fort Randall Reservoir. Big Bend 
Reservoir extends upstream to Pierre, SD. 
Existing project. A rolled earth-fill dam 95 feet high, 
with a crest length of 10,570 feet, a hydroelectric generating 
plant consisting of eight 58,500 kilowatt units, and a 
chute-type gated spillway. Reservoir provides gross storage 
of 1,883,000 acre-feet. Federal cost of the project was 
$107,498,000. Construction began in September 1959 and 
was completed in September 1977, except for Code 710 
recreation facilities. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, power production and other 
multiple uses. Normal operation and maintenance procedures 
were accomplished during the fiscal year. During 
the period, 647,704,000 net kilowatt-hours of electricity 
were produced. Annual project visitation hours were estimated 
at 5,310,100. 
24. FORT PECK LAKE, MT 
Location. Reservoir is in Missouri River Valley in Mc- 
Cone, Valley, Garfield, Phillips, Petroleum, and Fergus 
Counties, MT. Dam is approximately 1,771.6 miles above 
mouth of Missouri River. Nearest towns are Glasgow, 17 
miles northwest, and Nashua, 9 miles north. 
Existing project. A hydraulic earthfill dam with a maximum 
height of 251 feet, with a crest length of 21,026 feet, 
and a reservoir for flood control, irrigation, navigation, 
hydroelectric power, and other purposes, with a gross 
storage capacity of 18,909,000 acre-feet at maximum operating 
pool. Work started on original project in October 
1933 and on second power plant in August 1956. The 
project was completed in 1965. The power installations at 
the project were uprated in FY 1979. The 5 generators 
have a total output of 185,250 KW, 2 generators at 40,000 
KW each, 2 generators at 43,500 KW each and 1 generator 
at 18,250 KW. See page 818 of 1965 Annual Report 
and page 905 of 1958 Annual Report for project details. 
Federal cost of the project was $158,428,000. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with the other Missouri 
River reservoirs for flood control, navigation, power production, 
and other multi-purpose uses. Major Repair 
Work: Replacement of the penstock system for Power 
Plant No. 1 was essentially completed during the year at a 
cost of $19,000,000. Normal operation and maintenance 
procedures were accomplished during the fiscal year. 
Generating facilities produced 718,838,000 net kilowatt 
hours of electricity. Annual project visitation hours were 
estimated at 3,495,400. 
25. FORT RANDALL DAM-LAKE FRANCIS 
CASE, MISSOURI RIVER BASIN, SD 
Location. On Missouri River in Charles Mix and 
Gregory Counties, SD, about 82 miles above Yankton, 
SD. Site is 880 miles above mouth of Missouri River and 
148 miles above Sioux City, IA. 
Existing project. A rolled earth-fill dam with a maximun 
height of 165 feet, a crest length of 10,700 feet, and a 
reservoir for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage 
capacity of 5,574,000 acre-feet at maximum operating 
pool. The power installation consists of eight units rated 
at 40,000 kilowatts each. Construction began in May 1946 
and was completed in 1969, except for Code 710 recreation 
facilities. Federal cost of the project was 
$199,066,000. Non-Federal contribution for constructing 
approaches to the Platte-Winner Bridge was $720,000. 
26-6

OMAHA, NE, DISTRICT 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple uses. Normal operation and 
maintenance procedures were accomplished during the 
fiscal year. Generating facilities produced 1,310,548,000 
net kilowatt-hours of electricity. Annual project visitation 
hours were estimated at 7,014,800. 
26. GARRISON DAM-LAKE SAKAKAWEA, 
MISSOURI RIVER BASIN, ND 
Location. On Missouri River in McLean and Mercer 
Counties, ND, about 11 miles south of Garrison, ND, and 
9 miles west of Coleharbor, ND. 1,389.9 miles above 
mouth of river and 75 miles above Bismarck, ND. 
Existing project. A rolled earth-fill dam 11,300 feet 
long with a maximum height of 210 feet and a reservoir 
for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage capacity 
of 24,137,000 acre-feet. It provides five power units, three 
units rated at 109,250 kilowatts each, and two units rated 
at 95,000 kilowatts each, three flood control tunnels and 
a gated spillway. Federal cost of the project was 
$299,938,000 including $4,208,000 for major rehabilitation. 
Non-Federal contribution in connection with widening 
Snake Creek Embankment was $687,000. Construction 
of the project was initiated in April 1946 and 
completed in 1966, except for recreational development 
using Code 710 funds. 
Local cooperation. None required except cost-sharing 
with the State of North Dakota for widening the Snake 
Creek Embankment and recreation cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 
1,777,007,000 net kilowatt-hours of electricity. Annual 
project visitation hours were estimated at 9,137,600. 
27. GAVINS POINT DAM-LEWIS AND 
CLARK LAKE, MISSOURI RIVER 
BASIN, NE AND SD 
Location. On Missouri River in Yankton County, SD, 
and Knox County, NE, about 4 miles upstream from 
Yankton, SD, and 811.1 miles above mouth of river. 
Existing project. A concrete and rolled earth-fill dam 
with a maximum height of 74 feet and a reservoir for 
flood control, irrigation, navigation, hydroelectric power, 
and other purposes with a gross storage capacity of 
504,000 acre-feet at maximum operating pool. The power 
installation consists of three units rated at 44,099 kilowatts 
each. Federal cost of the project was $49,617,000. 
Construction of original project was initiated in March 
1952 and was completed in 1964. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 612,824,000 
net kilowatt-hours of electricity during fiscal year. Annual 
project visitation hours were estimated at 10,525,500. 
28. OAHE DAM-LAKE OAHE, MISSOURI 
RIVER BASIN, SD AND ND 
Location. Dam is on Missouri River in Hughes and 
Stanley Counties, SD, about 6 miles northwest of Pierre, 
SD, and 1,072.3 miles above mouith of river. 
Existing project. A rolled earth-fill dam with maximum 
height of 245 feet, a crest length of 9,300 feet, and reservoir 
for flood control, irrigation, navigation, hydroelectric 
power, and other purposes, with a gross storage 
capacity of 23,337,000 acre-feet at maximum operating 
pool. It contains seven power units rated at 112,290 kilowatts 
each. Federal cost of the project was $346,521,000. 
Construction was initiated August 1948 and project 
placed in operation June 1963. 
Local cooperation. None required except for recreation 
cost-sharing. 
Operations during fiscal year. Maintenance: Project 
was operated in conjunction with other Missouri River 
reservoirs for flood control, navigation, power production, 
and other multiple purpose uses. Normal operation 
and maintenance procedures were accomplished during 
the fiscal year. Generating facilities produced 
1,623,503,000 net kilowatt-hours of electricity. Annual 
project visitation hours were estimated at 11,489,900. 
29. MISSOURI RIVER MASTER WATER 
CONTROL MANUAL REVIEW 
AND UPDATE 
Location. The area being studied is the Missouri River 
basin, to include the Missouri River main stem system. 
States included in the study area include Nebraska, Montana, 
North Dakota, South Dakota, Iowa, Kansas, and 
Missouri. 
Existing Project. During the past six years, the Misssouri 
River basin has experienced a moderate to severe 
drought, impacting upon the Missouri River main stem 
projects for the first time since filled in 1967. The drought 
has had severe impacts on people and industries who use 
the Missouri River and the main stem reservoirs for navigation, 
hydropower, water supply, and recreation. Some 
of the people impacted by the drought have stated that the 
current Master Water Control Manual for the Missouri 
River main stem system of reservoirs does not adequately 
take into consideration the contemporary needs of the 
basin. The purpose of the Missouri River Master Water 
Control Manual Review and Update study is to determine 
the water control plan that best meets the needs of the 
Missouri River basin. 
Local Cooperation. None required. 
Operations/Activities during fiscal year. During FY 92, 
a Scope-of-EIS document for the Master Manual review 
26-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
was completed and distributed. This document is a compilation 
of the issues brought forth in the scoping meetings 
held in FY 91, as well as numerous other meetings and 
communications since that time. The technical studies to 
determine the value functions for each resource category 
under study were completed. Computer interface construction 
and quality control runs were completed and the 
water control plan alternatives were run through the interface. 
The first draft of the Initial Evaluation Report and 
draft supporting technical reports were completed. 
Miscellaneous 
30. NATIONAL EMERGENCY 
PREPAREDNESS 
The total fiscal year cost for this category amounted to 
$174,909. 
31. GENERAL INVESTIGATIONS 
Fiscal Year 1992 costs totaled $2,313,572 for all 
General Investigation activities. See Table 26-K which 
covers Surveys, Collection and Study of Basic Data, Research 
and Development, Preconstruction Engineering 
and Design (projects not fully authorized), Planning and 
Engineering under Proposed Program Legislation, and 
Preconstruction Engineering and Design (fully authorized 
projects). 
26-8

TABLE 26-A 
See 
Section 
in Text Project 
1. Missouri River, 
Sioux City, IA 
to Rulo, NE 
3. Bear Creek Lake, 
CO 
4. Bowman-Haley 
Lake, ND 
5. Chatfield Lake, 
CO 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
6. Cherry Creek 
Lake, CO 
7. Fall River 
Basin, SD 
8. Little Sioux River 
and Tributaries, IA 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
9. Lost Creek, 
Columbus, NE 
(Required 
Contributed 
Funds) 
(Consolidated 
Summary) 
10. Missouri National 
Recreational River 
NE & SD 
OMAHA, NE, DISTRICT 
COST AND FINANCIAL STATEMENT 
Funding 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Total Thru 
FY 89 FY 90 FY 91 FY 92 Sep 30, 1992 
1,926,284 
1,927,227 
40,000 
11,538 
244,000 
244,269 
177,000 
176,890 
360,000 
341,698 
360,000 
341,698 
502,000 
500,802 
425,000 
501,292 
288,000 
291,312 
16,782 
16,782 
150,000 
67,625 
150,000 
67,625 
68,000 
71,561 
200,000 
345,793 
1,532,748 
1,466,877 
-15,000 
3,471 
250,609 
226,794 
161,227 
135,848 
654,000 
513,862 
-7,549 
37,979 
646,451 
551,841 
642,430 
587,374 
754,963 
591,509 
331,860 
308,771 
6,973 
6,973 
60,567 
60,567 
611,000 
565,852 
100,000 
70,662 
1,455,000 
1,489,134 
-9,992 
394,000 
356,429 
191,000 
162,001 
300,000 
386,780 
80,302 
76,706 
380,302 
463,486 
649,000 
711,930 
583,000 
731,638 
403,000 
342,799 
665 
665 
18,421 
18,421 
183,000 
173,812 
216,000 
67,505 
26-9 
- 189,225,9911 
- 189,225,9911 
1,600,000 115,318,450 
1,590,008 115,268,485 
- 62,018,608 
- 62,018,608 
272,000 3,263,609 
313,839 3,243,260 
- 4,372,174 
- 4,372,174 
142,000 2,792,270 
169,372 2,763,423 
15,000 95,472,700 
87,021 95,443,554 
- 1,318,924 
- 1,302,599 
15,000 96,791,624 
87,021 96,746,153 
1,358,000 7,178,230 
1,360,634 7,174,999 
- 15,220,364 
- 15,220,364 
477,000 9,066,474 
472,666 9,043,597 
- 5,538,432 
- 5,538,432 
308,200 4,974,201 
377,049 4,956,441 
- 20,629,920 
381 20,629,920 
- 8,380 
- 8,380 
- 20,638,300 
381 20,638,300 
-40,000 3,579,518 
15,475 3,561,651 
4,615 151,915 
4,615 151,915 
-35,385 3,731,433 
20,090 3,713,566 
- 1,713,800 
52,123 1,706,234 
193,000 1,461,000 
261,733 1,341,058

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
Missouri River 
Funding 
New Work: 
FY 89 FY 90 FY 91 FY 92 Sep 30, 1992 
Kenslers Bend, Approp. - - - - 11,294,414 
NE, to Sioux Cost - - - - 11,294,414 
City, IA Maint. 
Approp. 41,000 47,350 47,000 49,000 4,671,419 
Cost 41,318 42,504 44,167 51,378 4,665,517 
12. Missouri River New Work: 
Levees, IA Approp. - 33,000 - - 37,964,1776 
NE, KS & MO Cost 178,349 63,630 16,404 1,508 37,963,6856 
(Required New Work: 
Contributed Approp. - - - - 38,810 
Funds) Cost - - - - 38,810 
(Consolidated New Work: 
Summary) Approp. - 33,000 - - 38,002,987 
Cost 178,349 63,630 16,404 1,508 38,002,495 
13. Papillion Creek New Work: 
and Tributaries Approp. 1,671,000 3,055,000 2,323,000 1,802,000 57,606,7625 
Lakes, NE Cost 1,511,524 2,516,780 1,591,309 1,716,285 56,045,9045 
(Required New Work: 
Contributed Approp. - - 185,000 - 185,000 
Funds) Cost - - - 120,000 120,000 
(Consolidated New Work: 
Summary) Approp. 1,671,000 3,055,000 2,508,000 1,802,000 57,791,762 
Cost 1,511,524 2,516,780 1,591,309 1,836,285 56,165,904 
Maint. 
Approp. 710,000 581,444 498,000 598,000 5,444,444 
Cost 721,885 487,355 527,621 619,452 5,391,798 
14. Pebble Creek New Work: 
Scribner, NE Approp. 1,067,000 74,487 70,244 30,000 1,938,728 
Cost 1,071,987 95,868 110,886 55,408 1,936,603 
(Required New Work: 
Contributed Approp. - - -40,244 - 164,756 
Funds) Cost 179,559 20,844 -37,644 - 162,760 
(Consolidated New Work: 
Summary) Approp. 1,067,000 74,487 30,000 30,000 2,103,484 
Cost 1,251,546 116,712 73,242 55,408 2,099,363 
16. Pipestem Lake, New Work: 
ND Approp. - - - - 9,277,545 
Cost - - - - 9,277,545 
Maint. 
Approp. 267,000 280,404 309,000 429,000 4,813,404 
Cost 268,752 263,878 311,015 416,390 4,785,634 
17. Salt Creek and New Work: 
Tributaries, NE Approp. - - - - 12,197,6212 
Cost - - - - 12,197,6212 
Maint. 
Approp. 749,000 703,801 600,000 426,000 10,951,276 
Cost 690,683 636,656 574,536 568,760 10,941,448 
19. Westerly New Work: 
Creek, CO Approp. 3,480,000 2,852,000 1,652,458 183,000 8,642,458 
Cost 1,298,121 4,332,448 1,887,644 647,106 8,619,646 
(Required New Work: 
Contributed Approp. 89,000 358,000 96,000 189,890 799,890 
Funds) Cost - 447,000 - 100,059 613,441 
(Consolidated New Work: 
Summary) Approp. 3,569,000 3,210,000 1,748,458 372,890 9,442,348 
Cost 1,298,121 4,779,448 1,887,644 747,165 9,233,087 
20. Inspections of Maint. 
Completed Local Approp. 184,000 212,128 209,000 218,000 3,751,476 
Protection Projects Cost 183,728 195,159 219,953 223,432 3,750,473 
21. Scheduling Flood Maint. 
Control Reservoir Approp. 274,000 344,708 386,000 353,000 6,739,684 
Operations Cost 274,342 331,338 375,595 350,362 6,713,158 
26-10 
in Text Project 
11.

OMAHA, NE, DISTRICT 
TABLE 26-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Thru 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 1992 
23. Big Bend Dam- 
Lake Sharpe, 
Missouri River 
Basin, SD 
24. Fort Peck Lake 
MT 
25. Fort Randall 
Dam-Lake Francis 
Case, Missouri 
River Basin, SD 
26. Garrison Dam- 
Lake Sakakawea, 
Missouri River 
Basin, ND 
(Federal Funds) 
(Contributed 
Funds) 
27. Gavins Point 
Dam-Lewis & 
Clark Lake, 
Missouri River 
Basin, SD 
and NE 
28. Oahe Dam-Lake 
Oahe, Missouri 
River Basin, 
SD & ND 
29. Missouri River 
Master Manual 
Review & Update 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
Major Rehab 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
4,770,000 
4,729,117 
4,087,000 
3,936,406 
- - - 107,497,597 
- - - 107,497,597 
5,130,530 6,605,000 5,822,400 74,089,1043 
4,847,516 6,616,064 6,051,036 73,955,7913 
- - - 158,428,080 
- - - 158,428,080 
4,452,469 
4,094,921 
7,032,000 6,899,147 
6,786,599 6,948,032 
6,620,000 7,317,057 
6,465,668 6,915,221 
4,753,000 4,022,805 
4,791,142 3,941,812 
3,135,000 3,458,000 
3,342,107 3,136,266 
73,369,4233 
72,687,1153 
- - 199,065,883 
- - 199,065,883 
6,416,000 6,822,500 121,153,5993 
6,206,030 6,723,347 120,556,2773 
6,221,788 
6,376,807 
5,066,000 
4,882,599 
- 295,729,613 
- 295,729,613 
7,466,725 135,371,9703 
7,519,345 134,972,5933 
5,204,000 
5,337,876 
4,208,310 
4,208,310 
686,961 
686,961 
49,617,239 
49,617,239 
88,452,2553 
88,197,9493 
- 346,520,603 
- 346,517,696 
7,945,000 7,453,851 7,440,000 
7,929,133 7,194,099 7,642,307 
- 1,060,000 4,900,000 
- 776,984 4,721,045 
8,365,000 
8,369,210 
2,939,000 
2,946,307 
130,018,5963 
129,802,1443 
8,899,000 
8,444,336 
1. Includes $18,325,581 National Industrial Recovery Act 
funds, $8,625,718 Emergency Relief Funds, and $1,181,125 for previous 
project. 
2. Includes $123,000 of government cost applicable to that 
portion of the project which is currently being carried in a deferred 
status. 
3. Includes Special Recreation Use Fees. 
4. Includes $110,000 transferred to inactive portion for 
planning cost. 
5. Does not include $1,854,338 cost of inactive sites. 
6. Does not include $2,228,211.50 cost of inactive sites. 
26-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 26-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
1. 
Jan 12, 1927 
July 3, 1930 
Aug 30, 1935 
Mar 2, 1945 
Aug 13, 1968 
Flood Control 
Act of 1962 
Flood control 
Act of 1950 
Water Resources 
Development Act 
of 1986 
Aug 18, 1941 
Dec 22, 1944 
Dec 22, 1944 
Aug 18, 1941 
Flood Control 
Act of 1954 
June 30, 1948 
National Parks 
and Recreation 
Act of 1978 
Aug 18, 1941 
June 30, 1948 
MISSOURI RIVER, SIOUX CITY, IA TO RULO, NE 
Appropriation of $12 million authorized for 
securing a 6 foot depth from Quindaro Bend 
(Kansas City, MO to Sioux City, IA). 
Appropriation of $15 million additional allotments 
totaling $29,153,108 made by Public Works 
Administration under provisions of National 
Industrial Recovery Act of 1933, and $9,669,791 
alloted under provisions of Emergency Relief 
Appropriations Act of 1935. 
For completion of project from mouth to Sioux City, IA. 
For a channel of 9-foot depth and 300-foot width. 
BEAR CREEK LAKE, CO 
A flood control reservoir for protection of 
metropolitan Denver, CO. 
BOWMAN-HALEY LAKE, ND 
Flood control reservoir and water supply. 
CHATFIELD LAKE, CO 
Flood control reservoir and channel improvements 
to provide downstream protection for Denver, CO. 
Modified 1950 Flood Control Act to operate dam 
and other Federal improvements to achieve 
authorized level of protection, beginning at dam 
and ending 82 miles downstream. Reassigns a 
portion of the storage space in the lake project to 
joint flood control-conservation purposes. Modified 
1974 WRDA to exemp prohibition of encroachments 
for Mineral Ave/Ken Caryl Rd. ext & 
transmission line. 
CHERRY CREEK LAKE, CO 
Initiation and partial accomplishment of project. 
Completion of plan approved in Act of Aug 18, 1941. 
General comprehensive plan, Missouri River Basin. 
FALL RIVER BASIN, SD 
Provide flood control to the town of Hot Springs, SD. 
LITTLE SIOUX RIVER, IA 
Correction of design deficiency. 
H. Doc. 1120, 60th Cong. 
PL 70-560 
PL 71-520 
PL 73-67 
H. Doc 238, 73rd Cong. 
PL 74-409 
H. Doc. 214, 76th Cong. 
PL 79-14 
S. Doc. 87, 90th Cong. 
PL 90-483 
H. Doc. 574, 87th Cong. 
PL 87-874 
H. Doc. 669, 80th Cong. 
PL 81-516 
H. Doc. 1013, 99th Cong. 
PL 99-662 
H. Doc. 426, 76th Cong. 
PL 77-228 
H. Doc. 426, 76th Cong. 
PL 78-534 
H. Doc. 475, and S. Docs. 
191 and 247, 78th Cong. 
PL 78-534 
H. Doc. 655, 76th Cong. 
PL 77-228 
PL 341, 80th Cong. 
PL 83-780 
LOST CREEK AT COLUMBUS, NE 
Levee and channel improvement for local PL 858, 80th Cong. 
protection - Section 205. 
MISSOURI NATIONAL RECREATIONAL RIVER, NE AND SD 
Preservation and enhancement of the Missouri PL 95-625 
River between the reaches from Gavins Point 
Dam, NE & SD to Ponca State Park, NE. 
MISSOURI RIVER, KENSLERS BEND, NE TO SIOUX CITY, IA 
Construction of dike, revetments. H. Doc. 821, 76th Cong. 
PL 77-228 
PL 80-858 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, KS, AND MO. 
Levees along both sides of river from Sioux City, IA to 
Kansas City, MO. 
Extended project from Kansas City, MO to mouth 
and provided for increased protection. 
H. Doc. 821, 76th Cong. 
PL 77-228 
H. Doc. 475, 78th Cong. 
PL 78-534 
S. Docs. 191 and 247, 78th 
Cong. 
26-12 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
Aug 18, 1941 
Dec 22, 1944

OMAHA, NE, DISTRICT 
TABLE 26-B (Continued) 
See Date of 
AUTHORIZING LEGISLATION 
Section Authorizing 
in Text Act 
13. 
14. 
15. 
Flood Control 
Act of 1968 
Water Resources 
Development Act 
of 1986 
June 30, 1948 
June 28, 1938 
Aug 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sep 3, 1954 
Sep 3, 1954 
May 2, 1956 
July 3, 1958 
July 14, 1960 
Dec 30, 1963 
June 18, 1965 
May 12, 1967 
Aug 13, 1968 
June 19, 1970 
Dec 24, 1970 
Dec 31, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Project and Work 
Authorized 
PAPILLION CREEK AND TRIBUTARIES LAKES, NE 
Series of flood control reservoirs, providing protection 
for the metropolitan areas of Omaha, NE. 
Authorized additional $4.8 million for channel 
improvement on Big Papillion Creek, and to 
Union Pacific RR bridge, rec trail and flood 
warning system. 
PEBBLE CREEK, SCRIBNER, NE 
Levee and channel improvement for local 
protection - Section 205. 
PICK-SLOAN MISSOURI BASIN PROGRAM (OMAHA DIST.) 
Adopted general comprehensive plan for Missouri 
River basin and authorized $9 million for 
initiation and partial accomplishment. 
Modified general comprehensive plan to include 
Harlan County Dam and Reservoir on Republican 
River, NE and authorized additional $7 million. 
Expanded general comprehensive plan for Missouri River 
Basin and authorized additional $200 million. 
Authorized additional $150 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $250 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional $217,710,000 
Authorized $5,384,014 to compensate Sioux Indians for 
reservation lands required for Oahe, South Dakota project. 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of 
construction of Wilson Dam and Reservoir, KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized additional $200 million. 
Authorized additional $207 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $80 million for prosecution of 
general comprehensive plan for Missouri River 
Basin and modified the plan to include work protection 
and rectification works below Garrison Dam. 
Authorized additional $116 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $20 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $38 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Authorized additional $109 million for prosecution 
of general comprehensive plan for Missouri River Basin. 
Changed comprehensive plan name to Pick-Sloan 
Missouri Basin Program. 
Oahe Dam and Reservoir, ND. 
Authorized additional $101 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $72 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $85 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Authorized additional $59 million for prosecution 
of Pick-Sloan Missouri Basin Program. 
Documents 
H. Doc. 349, 90th Cong. 
PL 90-485 
H. Doc. 1013, 99th Cong. 
PL 99-662 
PL 858, 80th Cong. 
Flood Control Committee 
Doc. 1, 75th Cong. 
PL 75-761 
H. Doc. 842, 76th Cong. 
PL 77-228 
H. Doc. 475, and S. Does. 191 
and 247, 78th Cong. 
PL 78-534 
PL 79-526 
PL 81-516 
H. Does. 549 and 642, 81st 
Cong. PL 83-780 
PL 83-776 
PL 84-505 
H. Doc. 409, 84th Cong. 
PL 85-500 
PL 86-645 
PL 88-253 
PL 89-042 
PL 90-17 
PL 90-483 
H. Doc. 91-748 and 
S. Doc. 91-895 
PL 91-282 
S. Doc. 91-1100, 91st Cong. 
PL 91-576 
H. Doc. 91-23 and 
PL 91-611 
PL 92-222 
PL 93-251 
PL 94-347 
PL 95-189 
26-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 26-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
Flood Control 
Act of 27 Oct 1965 
July 3, 1958 
May 17, 1950 
May 12, 1967 
Aug 13, 1968 
June 19, 1970 
Dec 23, 1971 
Mar 7, 1974 
July 8, 1976 
Nov 16, 1977 
Nov 17, 1986 
Dec 22, 1944 
June 16, 1933 
Aug 30, 1935 
May 18, 1938 
Dec 22, 1944 
June 3, 1948 
Water Resources 
Development Act 
of 1986 
Dec 22, 1944 
Dec 22, 1944 
PWA 1968 
Dec 22, 1944 
Dec 22, 1944 
16. 
17. 
18. 
PIPESTEM LAKE, ND 
Provide flood control for Jamestown, ND and 
downstream areas. 
SALT CREEK AND TRIBUTARIES, NE 
Series of dams and channel improvements for flood 
control around Lincoln, NE. 
SOUTH PLATTE RIVER BASIN, CO 
Adopted plan of improvement for South Platte 
River Basin and authorized $26.3 million for 
initiation and partial accomplishment. 
Authorized additional $2 million for prosecution of plan. 
Authorized additional $12 million for prosecution of plan. 
Authorized additional $21 million for prosecution of plan. 
Authorized additional $37 million for prosecution of plan. 
Authorized additional $15 million for prosecution of plan. 
Authorized additional $22 million for prosecution of plan. 
Authorized additional $3 million for prosecution of plan. 
WESTERLY CREEK, CO 
Provide flood control for metropolitan Denver, CO 
BIG BEND DAM - LAKE SHARPE, SD 
Expanded general comprehensive plan for flood control 
and other purposes in the Missouri River Basin 
FORT PECK LAKE, MT 
Construction of earth dam, as recommended by Chief of 
Engineers Sep 30, 1933, was approved by Executive Order by 
the President and included in Public Works Administration 
program, Oct 14, 1933 as authorized by the National Industrial 
Recovery Act of 1933 and adopted by the River and Harbor 
Act of 1935 (PL 74-409). 
Completion, maintenance, and operation of a hydroelectric 
power plant, subject to certain provisions in act respecting 
transmission and sale of electric energy. Also authorizes 
installation of additional power-generating facilities by 
Secretary of War when deemed necessary in judgment of 
Bureau of Reclamation. 
Modified authorization to provide for full multiple purpose 
operation. 
Payments to be made to school districts serving project as 
reimbursement for educational facilities (including transportation 
to and from school) for pupils who are dependents 
of persons engaged in construction, operation, and maintenance 
of projects. 
Modified authorization to include recreation as a 
project purpose. 
FORT RANDALL DAM - LAKE FRANCIS CASE, SD 
Expanded general comprehensive plan for flood control 
and other purposes in the Missouri River Basin. 
GARRISON DAM - LAKE SAKAKAWEA, ND 
Expanded general comprehensive plan for flood control H. Doc. 475, S. Doc. 247, 
and other purposes in the Missouri River Basin. 78th Cong. PL 78-534 
GAVINS POINT DAM - LEWIS AND CLARK LAKE, NE & SD 
Expanded general comprehensive plan for flood control H. Doc. 475, S. Doc. 247, 
and other purposes in the Missouri River Basin. 78th Cong. PL 78-534 
OAHE DAM - LAKE OAHE, SD & ND 
Expanded general comprehensive plan for flood control H. Doc. 475 and S. Does. 191 
and other purposes in the Missouri River Basin. and 247, 78th Cong. 
PL 78-534 
26-14 
H. Doc. 266, 89th Cong. 
PL 89-298 
H. Doc. 396, 84th Cong. 
PL 85-500 
H. Doc. 669, 80th Cong. 
PL 81-516 
PL 90-17 
PL 90-843 
PL 91-282 
PL 92-222 
PL 93-251 
PL 94-347 
PL 95-189 
PL 99-662 
H. Doc. 475, S. Doc. 247, 
78th Cong. PL 78-534 
H. Doc. 238, 73rd Cong. 
PL 74-409 
PL 75-529 
H. Doc. 475 and S. Docs. 191 
and 247, 78th Cong. 
PL 78-534 
PL 80-586 
H. Doc. 1013, 99th Cong. 
PL 99-662 
H. Doc. 475 and S. Docs. 191 
and 247, 78th Cong. 
PL 78-534 
19. 
23. 
24. 
25. 
26. 
27. 
28.

OMAHA, NE, DISTRICT 
TABLE 26-B (Continued) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing Project and Work 
in Text Act Authorized Documents 
29. MISSOURI RIVER MASTER WATER CONTROL 
MANUAL REVIEW AND UPDATE 
Dec 22, 1944 Expanded general comprehensive plan for flood control H. Doc. 475 and S. Docs. 191 
and other purposes in the Missouri River Basin. and 247, 78th Cong. 
PL 78-534 
TABLE 26-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Missouri River, Sioux City, IA to 
Fort Benton, MT Complete 1948 3,123,141 644,863 
Small Navigation Project at 
Sioux City, IA Complete 1970 43,582 88,716 
TABLE 26-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Belle Fourche, Cheyenne River, SD' Complete 1940 37,410 
Big Sioux River at Sioux City, IA Complete 1982 7,458,934 
Blackbird Creek Near Macy, NE2 Complete 1970 262,479 
Buffalo Creek, 
Meadow Grove, NE2 Complete 1974 293,016 
Buffalo Creek, Scranton, ND2 Complete 1960 102,980 - 
Cedar Canyon Dam, Rapid City, SD Complete 1960 120,482 - 
City of Aurora, 
Westerly Creek, CO Complete 1955 150,000 - 
Clarkson, NE, Maple Creek Complete 1967 191,282 - 
Council Bluffs, IA (Act of 1936) Complete 1939 - - 
Council Bluffs, IA (Act of 1944) Complete 1954 2,557,680 - 
Deadman's Gulch, Sturgis, SD2 Complete 1981 3,000,000 - 
Dry Creek, Hawarden, IA Complete 1964 400,000 - 
East Nishnabotn River 
at Red Oak, IA Complete 1986 2,154,016 - 
Floyd River, Sioux City, IA Complete 1970 11,556,667 - 
Forsyth, MT Complete 1950 255,177 - 
Frazer-Wolf Point, MT Complete 1982 435,000 - 
Gering Valley, NE Complete 1971 5,989,663 - 
Glasgow, MT Complete 1939 16,832 - 
Great Falls, MT Complete 1991 11,905,000 - 
Greybull, WY Complete 1960 248,507 
Havre, MT Complete 1958 1,825,881 - 
Herreid, Spring Creek, SD Complete 1954 50,216 - 
26-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 26-E (Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Hooper, NE2 
Ida Grove, IA2 
Indian Creek at Emerson, IA 2 
Jamestown Reservoir, ND 
Linton, ND 2 
Little Papillion Creek, NE 
Loup River, Columbus, NE2 
Lower Big Sioux River, IA and SD 
Lower Heart River, ND 
Lower Heart River, Mandan, ND2 
Madison, NE, Union and 
Taylor Creeks 2 
Mandan, Heart River, ND 
Marmarth, ND 
McCook Lake, SD 
Miles City, MT 
Missouri River, Aten, NE 
Missouri River, Niobrara, NE 
Mott, ND 
Mud Creek, Broken Bow, NE2 
Nishnabotna River at 
Hamburg, IA 
Norfolk, NE 
Omaha, NE 
Pierce, NE 
Platte River Near Schuyler, NE2 
Platte River and Lost Creek, 
Schuyler, NE 
Platte River and Tributaries, NE 
Rapid Creek, Rapid City, SD 
Saco, MT 
Sacred Heart Hospital, 
Yankton, SD 
Sheridan, WY 3 
Shields River, 
Near Clyde Park, MT2 
Sioux Falls, SD 
South Platte River Levees and 
Channel Improvements, Chatfield 
Lake to Ft. Morgan, CO 
Vaughn, MT, Sun River2 
Waterloo, NE 
West Point, NE 
Yellowstone River, 
W. Glendive, MT 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Deferred 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
Complete 
Complete 
Inactive 
Complete 
Complete 
Complete 
Complete 
1. Completed as a Public Works Administration project. 
2. Authorized by Chief of Engineers. 
3. Includes inactive segment. 
26-16 
326 
522, 
333, 
3,643, 
1,000, 
1,961, 
1,153,
,667 - 
,344 - 
,000 - 
,111 - 
,000 - 
,173 - 
,430 - 
1968 
1972 
1986 
1950 
1973 
1976 
1973 
1966 
1964 
1991 
1967 
1960 
1960 
1958 
1956 
1951 
1945 
1976 
1948 
1971 
1954 
1967 
1948 
1971 
1980 
1958 
1978 
1976 
1951 
1966 
1957 
1971 
1970 
1966 
1960 
5,633 
234,839 
676,916 
169,498 
147,627 
578,791 
99,370 
1,000,000 
236,000 
3,400,504 
5,903,640 
296,597 
74,940 
257,398 
1,538,269 
1,004,000 
67,793 
184,380 
2,618,809 
25,747 
5,288,707 
457,582 
237,883 
149,596 
230,294

OMAHA, NE, DISTRICT 
TABLE 26-F OTHER MULTIPLE PURPOSE PROJECTS INCLUDING POWER 
For Last 
Full Report 
See Annual 
Cost to September 30, 1992 
Operation and 
Project Status Report For Construction lMaintenance 
Gavins Point Dam-Lewis and Clark Lake, 
Relocation of Niobrara, NE Complete 1980 13,516,459 - 
Springfield, SD Water Intakel Active - - - 
Williston, ND Water Intake Complete 1981 988,583 - 
1. Project was reported to the Speaker of the House and the be deauthorized 30 months from date of that report unless federal 
President of the Senate by ASA (CW) as meeting the deauthoriza- funds are obligated for planning, design, or construction. 
tion eligibility criteria of Sec 1001(b) (2) as of 30 Sep 91. Project will 
TABLE 26-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Deauthorization Funds Funds 
Project Report For Document Expended Expended 
Billings, MT 1976 Sec. 201, FC Act 1950 75,000 - 
23 Mar 81 
Boulder, CO 1976 FC Act 1950 142,666 - 
WRDA of 1986 
17 Oct 86 
Buffalo, Johnson County 1961 FC Act 1950 -- 
Diversion Channel, WY WRDA of 1986 
17 Oct 86 
Castlewood Lake, 1943 PL 77-228 - - 
Douglas County, CO WRDA of 1986 
17 Oct 86 
Davids Creek Lake, IA 1972 Sec. 203, PL 90-483 - - 
WRDA of 1986 
17 Oct 86 
Dayton, WY 1956 Sec. 12, PL 93-251 - - 
WRDA of 1974 
5 Aug 77 
Giles Creek, Elkhorn, NE 1952 Sec. 12, PL 93-251 - - 
WRDA of 1974 
6 Nov 77 
Indian Creek Lake, IA 1969 Sec. 12, PL 93-251 135,000 - 
WRDA of 1974 
4 Jan 74 
Lake Herman N/A Sec 1001(a), PL 89-298 - - 
(Dredging), SD WRDA of 1986 17 Oct 86 
Little Nemaha River, 1973 Sec. 204, PL 89-298 - - 
Nemaha County, NE WRDA of 1986 
17 Oct 86 
Milk River, N/A Sec 1001(a), PL 89-298 - - 
Havre, MT WRDA of 1986 17 Oct 86 
Morrison, Bear Creek, CO 1950 Sec. 12, PL 93-251 30,000 - 
WRDA of 1974 
5 Aug 77 
Redwater River and 1966 Sec. 12, PL 93-251 1,000 
Hay Creek, Bell Fourche, SD WRDA of 1974 
4 Jan 74 
Shell Creek, NE 1962 Sec. 12, PL 93-251 71,000 - 
WRDA of 1974 
3 Oct 78 
Upper Missouri River, SD N/A Sec 1001(a), PL 89-298 - - 
Strambank Erosion Control Project WRDA of 1986 17 Oct 86 
Vermillion River and Tribs, SD 1968 Sec. 12, PL 93-251 208,000 - 
WRDA of 1974 
4 Jan 74 
The following investigations for flood control called for by Flood Control Acts and committee resolutions were deauthorized by WRDA of 1986, 
17 Oct 86: Aowa & South Creek, NE; Bow Creek, NE; Cannonball River, ND; James River, ND & SD; Judith River Basin, MT; Niobrara River 
Basin, NE, SD & WY; Omaha Creek, NE; South Dakota Lakes, SD; Weeping Water Creek, NE; Windpower at Ft. Peck Lake, MT; Yellowstone 
River below Billings, MT; South Platte River, Denver-Ft. Lupton-Ft. Morgan, CO; Lower Big Sioux River, IA & SD; Eagle Bay Highway Bridge, 
Missouri River Basin, ND; Sheridan, WY (Stage III); Missouri River Levee System Units: R531, R540, R553, R555, R577, R589, R603, R610, 
R623, R644, R645, R652, R661, R669, R676, R682, R686, R703, R717, R719, R725, R728, R742, R750. 
26-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
MISSOURI RIVER LEVEE SYSTEM, SIOUX CITY, IA 
TABLE 26-H (See Section 12 of Text) 
TO RULO, NE 
Miles of 
Unit Levee Status 
L627-624 Mosquito Creek Levee 14.2 Complete 1950 
L601 Watkins-Waubonsie Ditch Levees 15.0 Complete 1966 
L594 Pleasant Valley Levee 11.4 Complete 1964 
R580 Nebraska City Levee 0.2 Complete 1950 
L575 Thurman-Hamburg Levee 45.8 Complete 1950 
R573 Otto County Drainage District No. 2 5.9 Complete 1950 
R562 Peru Dike 7.6 Complete 1950 
L561-550 Atchison County Levee District No. 1 41.3 Complete 1952 
R548 Brownville-Nemaha Levee 19.5 Complete 1952 
L536 Mill Creek Levee 13.6 Complete 1952 
R520 Richardson County Drainage Dist. No. 8 6.3 Complete 1960 
R613 Papillion Creek-Platte River Levee 14.0 Complete 1971 
R616 Bellevue-Papillion Creek Levees 4.5 Complete 1987 
L611-614 Mosquito-Keg Creek Levees 22.0 Complete 1988 
L627, L624, Remedial Studies on Completed Units L561-550 Studies Complete 
Comprehensive Restudy of Levee System Studies Complete 
PICK-SLOAN MISSOURI BASIN PROGRAM 
TABLE 26-I (See Section 15 of Text) 
Estimated Estimated 
Project Federal Cost Non-Federal Cost 
Fort Peck Lake, MTI,2 158,428,000 1,103,000 
Garrison Dam, Lake Sakakawea, ND1I,2 299,938,000 1,516,000 
Missouri River Levee System, I, NE, KS and MO 
(Sioux City, IA to Rulo, NE) , 37,931,000 4,618,000 
Oahe Dam-Lake Oahe, SD and NDI,2 346,521,000 2,320,000 
Big Bend Dam-Lake Sharpe, SDI,2 107,498,000 302,000 
Fort Randall Dam, Lake Francis Case, SD I,2 199,066,000 1,609,000 
Gavins Point Dam, Lewis & Clark Lake, SD & NEl, 2 49,617,000 137,000 
Gavins Point Dam, Lewis & Clark Fake, SD 
& NE-Relocation of Niobrara, NE 13,516,000 - 
Omaha, NE2 5,904,000 362,000 
Council Bluffs, IA 2 2,558,000 146,000 
Missouri River, Garrison Dam to Lake Oahe, ND2 9,413,000 270,000 
Cherry Creek Lake, CO 1 ,2 15,220,000 285,000 
1Details presented on individual report. 2Completed. 3 Active portion of project. 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (See Section 20 of Text) 
Location Month Inspected 
Montana 
Glasgow, Milk River Sep 92 
Saco, Beaver Creek Sep 92 
Havre, Milk River Jun 92 
Havre, Scott Coulee-Bull Hook Dam Jun 92 
Clyde Park, Shields River Aug 92 
Three Forks, Lower Madison River Sep 92 
Forsythe, Yellowstone River Aug 92 
West Glendive, Yellowstone River Sep 92 
Vaughn, Sun River Sep 92 
*Yellowsatone River, Water Plant, Livingston Aug 92 
Sun River, Great Falls Sep 92 
26-18

OMAHA, NE, DISTRICT 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (Continued) (See Section 20 of Text) 
Location 
*Yellowstone River, Reedpoint Bridge 
*Yellowstone River, Greycliff Bridge 
*Yellowstone River, Springdale Bridge 
*Yellowstone River, Near Miles City 
Water Intake & Sewage Lagoon 
*Yellowstone River, Bank Protection, Billings 
*Yellowstone River, Yellowstone County Bridge, Near Billings 
*Yellowstone River, Voges Bridge, Near Big Timber 
*Jefferson River, Willow Creek Bridge, Near Three Forks 
*Jefferson River, Bank Protection, Near Waterloo 
*Big Hole River, Pennington Bridge, Near Twin Bridges 
*Ruby River, Wheatly Bridge, Near Twin Bridges 
*Big Horn River, Two Leggin Bridge, Near Hardin 
*Missouri River, Bank Stabilization, Fort Benton 
*Yellowstone River, Glendive 
Madison River, Quake Lake 
Milk River, Malta 
Wyoming 
Greybull, Big Horn River 
Sheridan, Big and Little Goose Creeks 
*Shoshone River, Bank Protection, Lovell 
*Shoshone River, Byron 
North Dakota 
Mandan, Lower Heart River 
Marmarth, Little Missouri River 
Scranton, Buffalo 
South Dakota 
Big Sioux River, Union County 
Big Sioux River, North Sioux City 
Sioux Falls, Big Sioux River 
Belle Fourche, Belle Fourche River 
Rapid City, Cedar Canyon Dam 
Hot Springs, Fall River Channel 
Herreid, Spring Creek 
*Missouri River, Bank Protection, Greenwood 
*Bad River, Bank Protection, Fort Pierre 
*Big Sioux River, Schofield Bridge, Near Flandreau 
*Big Sioux River, Fink Bridge, Near Flandreau 
Rapid Creek, Rapid City 
Sacred Heart Hospital, Yankton 
*Vermillion River, Vermillion 
*Big Sioux River, Harrisburgh 
*Big Sioux River, Jefferson 
Deadman Gulch, Sturgis 
*Marne Creek, Yankton 
*White River, Winner 
Colorado 
Aurora, Westerly Creek-Kelley Road Dam 
*Plum Creek, Bank Stabilization, Aurora 
*Cache La Poudre River, Windsor 
*South Platte River, Kersey 
*South Platte River, Merino 
*South Platte River, Iliff 
*South Platte River, Platteville 
*Big Thompson River, Johnstown 
Cache La Poudre River, Ft. Collins (Water Treatment Plant) 
South Platte River, Adams County, No. Washington St. 
Water and Sanitary District 
Month Inspected 
Aug 92 
Aug 92 
Inactive 
Inactive 
Inactive 
Aug 92 
Aug 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Inactive 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Aug 92 
Aug 92 
Aug 92 
Aug 92 
Sep 92 
Sep 92 
Sep 92 
Aug 92 
Aug 92 
Aug 92 
Sep 92 
Sep 91 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Jul 92 
Jul 92 
Sep 91 
Jul 92 
Jul 92 
Jul 92 
Jul 92 
Sep 92 
Jul 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
Sep 92 
26-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (Continued) (See Section 20 of Text) 
Location Month Inspected 
Nebraska 
*Blackbird Creek, Decatur May 92 
Omaha, Missouri River Jul 92 
Waterloo, Elkhorn River Sep 92 
West Point, Elkhorn River Jun 92 
Pierce, Elkhorn River Jun 92 
Clarkson, Middle Fork, Maple Creek Jan 92 
Hooper, Elkhorn River Aug 92 
Norfolk, North Fork, Elkhorn River Jan 92 
Madison, Union & Taylor Creeks Jun 92 
*Platte River, M.U.D. Protection, Cedar Island Feb 92 
*Platte River, Bank Protection, Louisville Feb 92 
*Elkhorn River, Q Street Bridge, Near Gretna Aug 92 
*Elkhorn River, Ray Bridge, Near Norfolk Mar 92 
*North Platte River, Bank Stabilization, Minatare Oct 91 
*Logan Creek, Bank Protection, Near Bancroft Mar 92 
*Battle Creek, Bank Protection, Battle Creek Feb 92 
Schuyler, Lost Creek & Platte River Sep 92 
Little Papillion, Little Papillion Creek Jun 92 
Gering Valley, Gering Drain & Tributaries Sep 92 
Macy, Blackbird Creek May 92 
Lincoln, Salt Creek & Tributaries Mar 92 
Meadow Grove, Buffalo Creek May 92 
Columbus, Loup River Sep 92 
Broken Bow, Mud Creek Sep 92 
*Little Nemaha River, Tangeman Mar 92 
*Julian, Rock Creek Inactive 
*Muddy Creek Near Syracuse Mar 92 
*Platte River, Hansen-Chris Lakes, Bellevue Feb 92 
*Platte River, Brady Apr 92 
*Elm Creek, Decatur Mar 92 
*Wiggle Creek, Homer Mar 92 
*Elk Creek, Jackson Mar 92 
*South Creek, Martinburg Apr 92 
*Elk Creek, Willis Mar 92 
Columbus Flood Control Project, Lost Creek, Columbus Sep 92 
*Shell Creek, County Road Near Columbus Mar 92 
*Middle Pebble Creek, Snyder Apr 92 
*Elm Creek, Burt County Mar 92 
*Redbird Creek, O'Neill Sep 92 
*Salt Creek Sewage Treatment Plant, Lincoln Jan 92 
*Platte River, Ashland Mar 92 
*West Branch Papillion Creek, Omaha, NE Aug 92 
*Niobrara River, Bassett, NE Sep 92 
*Niobrara River-Cams Bridge, Bassett, NE Sep 92 
*Elkhorn River Bridge, Norfolk Jun 92 
*West Branch Papillion Creek, Omaha Aug 92 
*Logan Creek, Near Bancroft Mar 92 
*Platte River, Near North Bend Apr 92 
*Platte River, Ginger Cove Near Valley Sep 92 
*Elkhorn River, Near Beemer Mar 92 
*Elkhorn River, Ewing, Holt County Sep 91 
Pebble Creek, Scribner Sep 92 
Iowa 
Council Bluffs, Missouri River Sep 92 
Ida Grove, Maple River-Odebolt Creek Jul 92 
Sioux City, Floyd River Sep 92 
Hawarden, Dry Creek May 92 
Hamburg L575, Nishnabotna River May 92 
Intercounty D.D., Little Sioux River Aug 92 
Nagel D.D., Little Sioux River Sep 92 
26-20

OMAHA, NE, DISTRICT 
INSPECTION OF COMPLETED LOCAL PROTECTION PROJECTS 
TABLE 26-J (Continued) (See Section 20 of Text) 
Location Month Inspected 
Bennett-McDonald-Smithland D.D., Little Sioux River Aug 92 
*West Nishnabotna River, Mills County Bridge, Near Malvern Mar 92 
*West Nishnabotna River, Mills County Bridge, Near Hastings Mar 92 
*East Nishnabotna River, Page County Bridge, Near Essex Feb 92 
*Missouri River, Marina, Sioux City Sep 92 
*West Nishnabotna River, Near Hancock Jan 92 
*East Nishnabotna River, Near Griswold Jan 92 
East Nishnabotna River, Red Oak Mar 92 
Big Sioux River, Sioux City Aug 92 
* Mucky Creek, Mapleton, IA Apr 92 
Emerson, Indian Creek, Mills County Jan 92 
*East Fork of Boyer River, Near Vail Feb 92 
Monona-Harrison Ditch Control, Monona County Aug 92 
*Little Sioux River, Anthon Feb 92 
*Big Sioux River, Plymouth County Jul 92 
*Keg Creek, Minden Feb 92 
*Waterman Creek, Near Sutherland Mar 92 
*Soldier River, Near Ute Mar 92 
*West Nishnabotna River, Near Oakland Jan 92 
*R.B. West Nishnabotna River, Mills County Bridge, Near Malvern Mar 92 
*Big Sioux River, Plymouth County Jul 92 
Missouri River Levees 
L624 & L627, Mosquito Creek & Sieck Levees Aug 92 
L601, Watkins Levee District May 92 
L601, Miller-Sturgeon Levee District Jun 92 
L601, Missouri River Levee District #1 Jun 92 
L594, Waubansie Drainage District Jun 92 
L594, Pleasant Valley Levee District Jun 92 
L575, Benton-Washington Levee District Jun 92 
L575, Northwest Atchison Levee District Jul 92 
L575, McKissock Island Levee District Jul 92 
L575, Buchannan Levee District Jul 92 
L561, L550, L536, Atchison County Levee District Apr 92 
L611-614, M & P Missouri River Levee District May 92 
R613, Papio Natural Resources District Aug 92 
R562, Peru Levee District May 92 
R548, Brownville-Nemaha Levee District May 92 
R548, Little Nemaha Levee District May 92 
R520, Richardosn Co. Levee Dist. #8 Apr 92 
R573, Otoe County Drainage Dist. #2 Apr 92 
R616, Sarpy County Papio Natural Resources District Aug 92 
*Denotes Section 14 Projects 
ACTIVE GENERAL INVESTIGATIONS 
TABLE 26-K (See Section 31 of Text)
Federal Cost Totals By 
Item FY 92 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Antelope Creek, Lincoln, NE 47,122 
Big Sioux River, Sioux Falls, SD 37,501 
Thurman to Hamburg, IA 36,166 
Aberdeen and Vicinity, SD 112,394 
Vermillion River Basin, SD 145,146 
Ft. Collins, CO 65,786 
Goose Creek, Boulder, CO 8,516 
Ralston & Leydon Creeks, CO 137,264 
Burt-Washington Counties, NE 42,723 
Watertown and Vicinity, SD -15,694 
Wood River, Grand Island, NE 113,546 
Subtotal 730,470 
26-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
ACTIVE GENERAL INVESTIGATIONS 
TABLE 26-K (Continued) (See Section 31 of Text)
Federal Cost Totals By 
Item FY 92 Categories 
Special Studies (140) 
Big Bend Wildlife Restoration 15,862 
James River Environmental, SD 99,565 
Oahe Wildlife Restoration 45,097 
Subtotal 160,524 
Review of Authorized Projects (160) 
None 
Miscellaneous Activities (170) 
Special Investigations 143,717 
FERC Licensing 2,384 
Interagency Water Resources Development 8,352 
North American Waterfowl Management Plan 3,605 
Subtotal 158,058 
Coordination Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) 1,380 
Bureau of Reclamation, Dept. Interior (182) 11,208 
River Basin & Reg. Plan. Comm. (183) 13,953 
Planning Assistance to States (186) 293,861 
Subtotal 320,402 
TOTAL (Category 100) 1,369,454 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 47,637 
SS - Council Bluffs, IA (250) 18,784 
SS - Jefferson Co. (250) 8,969 
Newcastle, WY (250) 272 
NFPC (250) 4,043 
Quick Responses (250) 10,832 
Risk Canyon, CO (250) 2,803 
SS - Yankton, SD (250) 12,285 
Upper Bear Creek, CO (250) 2,075 
White Earth, ND (250) 272 
Technical Services, General (250) 166,674 
Hydrologic Studies (260) 24,132 
TOTAL (Category 200) 298,778 
RESEARCH AND DEVELOPMENT (Category 300) 
None 
PRECONSTRUCTION ENGINEERING AND DESIGN - 
PROJECTS NOT FULLY AUTHORIZED (Category 400) 
None 
PLANNING AND ENGINEERING UNDER PROPOSED 
LEGISLATION (Category 500) 
None 
PRECONSTRUCTION ENGINEERING AND DESIGN - 
FULLY AUTHORIZED PROJECTS (Category 600) 
Missouri River F&W Mitigation (621) 10,460 
Perry Creek, IA (650) 598,534 
Platte River Bank Stab., NE (650) 55 
Ft. Yates Bridge, ND (660) 36,291 
TOTAL (Category 600) 645,340 
GRAND TOTAL GENERAL INVESTIGATIONS 2,313,572 
26-22

OMAHA, NE, DISTRICT 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 26-L (See Section 22 of Text) 
Fiscal Year 
Project Name Stage Cost 
Flood Control and Coastal Emergencies 
Disaster Preparedness - 442,825 
Flood Flight and Rescue Operations - - 
Rehabilitation - 
Emergency Water Supply & Drought Assistance - 7,978 
Advance Measures - - 
Total (FCCE) 450,803 
Section 205: 
Cache La Poudre River, Greeley, CO R 8,481 
Cedar Creek at Cedar Lodge, NE R 387 
Corporation Gulch, Norfolk, NE R 89 
Bluegrass Creek, Audubon, IA R 19,977 
Otto Creek, Lashara, NE R 13,914 
Unnamed Creek, Tioga, ND R 13,597 
West Branch Pebble Creek, Dodge, NE R 27,289 
Deadman's Run, NE R 8,818 
Logan Creek, Pender, NE R 19,874 
Maple Creek East Fork, Howells, NE R 39,859 
Maple Creek, Nickerson, NE R 12,841 
Nishnabotna River, Hamburg, IA F 39,630 
Beal Slough, NE R 7,915 
Hay Creek, Belle Fourche, SD R 256 
Indian Creek, Hastings, IA F 465 
Salt Creek, Levees, Lincoln, NE F 51,952 
Lost Creek at Columbus, NE L 15,475 
Medicine Knoll, Blunt, SD R 8,042 
Milk River, Malta, MT F 60,770 
Pebble Creek, Scribner, NE C 55,408 
Platte River, Cedar Creek, NE F 823 
Powder River, Broadus, MT R 19,186 
Lodgepole Creek, Sidney, NE P 65,976 
Van Bibber Creek, Arvada, CO F 43,809 
Wet Spottedtail Creek, Mitchell, NE R 3,969 
Total (Section 205's) 538,802 
Section 14: 
Big Sioux River/ Dakota Dunes, SD F 4,940 
Bldwn, Sqw Crk Lndr Swg Lgn, WY C 8,173 
Cannonball River, Shields, ND C 21,762 
Cedar Creek, Spaulding, NE C 37,281 
East Nishnabotna River, Page Bny Brdg, IA C 7,500 
Fort Lupton, CO (Lagoon) C 3,518 
Gallatin River, Gallatin County, MT C 25,943 
Nine Mile Drain, Scottsbluff, NE C 6,430 
Plum Creek, Norden Dam Access Road, NE C 22,014 
Powder River, Arvada, WY C 1,353 
Shields River, Park County, MT (US 89) C 6,633 
South Fork Elkhorn River, Ewing, NE C 54 
South Platte River, Logan County Bridge, NE C 38,393 
South Platte River/ Merino, Logan City, CO P 7,663 
South Platte River, Weld County Bridge 28, CO C 4,889 
South Platte River, Weld County Bridge 61, CO C 5,298 
South Platte River, Weld County Bridge 87, CO C 3,904 
South Table Creek, Nebraska City, NE C 87 
Teton RV/Chateau/Teton County, MT F 16,060 
26-23 
Union Creek/ Stanton Bridge, NE P 10,454

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
FLOOD CONTROL ACTIVITIES UNDER SPECIAL AUTHORIZATION 
TABLE 26-L (Continued) (See Section 22 of Text) 
Fiscal Year 
Project Name Stage Cost 
Badger Creek, Glacier City, MT 
Beaver Creek, Platte County, NE 
Elkhorn River, Beemer, NE Bridge 
Dearborn River, Lewis-Clark County, MT 
East Bow Creek, Cedar County Bridge, WY 
Little Popo Agie River, Lander, WY 
Muddy Creek, Cascade, Vaughn, MT 
Niobrara River (Carns Bridge), NE 
Road Knife River, Staton, ND 
Teton River, Teton County, MT 
Teton River, Chateau/Teton County, CO 
White River, Tripp County Road, SD 
Yellowstone River, Route 11, Livingstone, MT 
Yellowstone River, Highway 89 Bridge, MT 
Yellowstone River, MT 
Total (Section 14's) 
Total Flood Control Activities 
L = Litigation 
R = Recon 
P = Plans & Specs 
C = Construction 
F = Feasibility 
- Does Not Apply 
14,274 
5,479 
53 
9,824 
17,254 
13,523 
11,732 
7,596 
35 
6,500 
469 
2,289 
20,333 
6,520 
1,050 
348,176 
1,337,781 
26-24

KANSAS CITY, MO, DISTRICT* 
The district comprises a portion of southwestern Iowa; 
northwestern, central, and western Missouri; northern Kansas; 
southern Nebraska; and a portion of northeastern 
Colorado embraced in drainage basin of the Missouri River 
and tributaries from Rulo, Nebraska, to the mouth. Report 
on navigation project for section of Missouri River from 
Sioux City, Iowa, to Rulo, Nebraska, is in report of Omaha 
District. 
IMPROVEMENTS 
Navigation 
1. Missouri River, Sioux City, IA to 
Mouth (Rulo, NE, to Mouth)...... 
2. Missouri River Fish and Wildlife 
Mitigation, IA, NE, KS, and MO.. ........... 27-2 
Flood Control 
3. Blue River Channel, Kansas City, MO ........ 27-2 
4. Brush Creek, Kansas City, MO...............27-3 
5. Clinton Lake, Wakarusa River, KS ........... 27-3 
6. Harlan County Lake, Republican 
River, NE .............. ..... .......... 27-3 
7. Hillsdale Lake, Big Bull Creek, KS...........27-3 
8. Kanopolis Lake, Smoky Hill River, KS ........ 27-4 
9. Little Blue River Lakes, MO ................ 27-4 
10. Long Branch Lake, Little Chariton 
River, MO ................... ........ 27-4 
11. Melvern Lake, Marais des Cygn'es 
(Osage) River, KS..................... 27-5 
12. Milford Lake, Republican River, KS ......... 27-5 
13. Missouri River Levee System, IA, NE, 
KS, and MO (Rulo, NE, to Mouth) ........... 27-5 
14. Perry Lake, Delaware River, KS ............. 27-5 
15. Pick-Sloan Missouri Basin Program 
(Kansas City Dist.) ..................... 27-6 
16. Pomme de Terre Lake, Pomme de Terre 
River, MO .. ...... ................... 27-6 
17. Pomona Lake, One Hundred Ten Mile 
Creek, KS .......... ................. 27-6 
18. Rathbun Lake, Chariton River, IA ............ 27-6 
19. Smithville Lake, Little Platte River, MO ...... 27-6 
20. Tuttle Creek Lake, Big Blue River, KS ........ 27-7 
21. Wilson Lake, Saline River, KS............... 27-7 
Flood Control (cont.) Page 
22. Scheduling of Flood Control 
Reservoir Operations ....................... 27-7 
23. Inspection of Completed Flood 
Control Projects ........................... 27-7 
24. Disaster Preparedness Program ............. 27-7 
25. Flood Control Activities under Special 
Authorization ........................ 27-7 
Multiple Purpose Projects Including Power 
26. Harry S. Truman Dam and Reservoir, 
Osage River, MO ......................... 27-8 
27. Stockton Lake, Sac River, MO...............27-9 
General Investigations 
28. General Investigations ...................... 27-9 
Tables 
Table 27-A Cost & Financial Statement.......... 27-10 
Table 27-B Authorizing Legislation ............ 27-13 
Table 27-C Other Authorized Navigation 
Projects ...................... 27-16 
Table 27-D Not Applicable 
Table 27-E Other Authorized Flood Control 
Projects ........... ........... 27-17 
Table 27-F Not Applicable 
Table 27-G Deauthorized Projects ............. 27-18 
Table 27-H Missouri River Levee System ........ 27-19 
Table 27-I Kansas City District Projects 
Included in Pick-Sloan Missouri 
Basin Program ..................... 27-20 
Table 27-J Inspection of Completed Flood 
Control Projects .................... 27-20 
Table 27-K Active General Investigations ........ 27-21 
Table 27-L Flood Control Activities Under 
Special Authorization ............... 27-22 
27-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. MISSOURI RIVER, SIOUX CITY, IA, 
TO MOUTH (RULO, NE, TO MOUTH) 
Location. Jefferson, Madison, and Gallatin Rivers conjoin 
at Three Forks, Montana, to form the Missouri River, 
which flows southeasterly 2,315 miles (1960 mileage) across 
or along seven states to the Mississippi River, 17 miles above 
St. Louis. For description see page 1149, Annual Report 
for 1932. The river is commercially navigable from Sioux 
City, Iowa, to the mouth, a distance of 732 miles. The portion 
of project in Kansas City District extends from Rulo, 
Nebraska, to the mouth, a distance of 498 miles. 
Previous Projects. For details see page 1891 of Annual 
Report for 1915, and pages 1153 and 1175 of Annual Report 
for 1938. 
Existing Project. A channel of 9-foot depth and width 
not less than 300 feet, obtained by revetment of banks, construction 
of permeable dikes to contract and stabilize the 
channel, cutoffs to eliminate long bends, closing minor channels, 
removal of snags, and dredging as required. The 
improved reach within the Kansas City District extends 
from the mouth to Rulo, Nebraska, a distance of 498.4 miles. 
The Bank Stabilization and Navigation features of the 
project were completed in September 1980. For the reach 
from Rulo, Nebraska, to the mouth, the total construction 
cost was $237,942,190 including $8,665,594 for previous 
project. River access sites have been completed at 11 locations. 
Ordinary and extreme stage fluctuations are 16 and 
38 feet, respectively. 
Local cooperation. Cooperation from benefited localities 
may be required where any improvement may confer special 
benefit. The receipt of contributions from private parties 
are to be expended along with Government funds upon 
authorized work where such work would be in the interest 
of navigation, as authorized by 1915 Rivers and Harbors 
Act. Secretary of the Army approved general principle of 
cooperative construction on Missouri River below Kansas 
City on basis that 25 percent of cost of any special installation 
shall be paid by the United States and 75 percent by 
local interests. Tbtal contributed by local interests in 
cooperation with the United States from 1918 to June 30, 
1964, was $675,663, of which $8,647 was returned to contributors. 
Local interests must share in cost of recreation 
facilities in accordance with provisions of the Federal Water 
Project Recreation Act of 1965. Local interests have contributed 
$171,816 for cost sharing on construction of recreation 
in addition to constructing portions of the facilities. 
Terminal facilities. A listing of terminal facilities are included 
in Missouri River Navigation Charts and can be obtained 
from Kansas City District Engineer for a small fee. 
Operations during fiscal year. The 1974 Base Line 
Study of the reach of the Missouri River in the Kansas City 
District estimated recreation use on the river at 1,250,000 
recreation days annually. The projected tonnage on the river 
for CY 1992 was approximately 1.5 million, excluding sand, 
gravel, and waterway improvement materials. Maintenance: 
Repair of dikes and revetments by contract. In addition, 
following work was accomplished by field hired labor: Construction 
of environmental gaps, dike and revetment repair. 
Also, the following work was accomplished by District 
personnel: real estate management, channel reconnaissance, 
condition studies, surveys and mapping, stream gauging, 
engineering and design, surveys and layout of construction, 
and supervision and administration. One construction contract 
was awarded in 1992; Miami Bend to Amazon. 
2. MISSOURI RIVER FISH AND 
WILDLIFE MITIGATION, IA, NE, 
KS, and MO 
Location. This project extends along the Missouri River 
from Sioux City, Iowa, to the Mouth near St. Louis, a river 
distance of 732 miles. This location is coincident with the 
Bank Stabilization and Navigation Project on the river. 
Existing project. The project is to mitigate losses of fish 
and wildlife habitat resulting from construction and operation 
of the Missouri River Bank Stabilization and Navigation 
Project. The four major components of the plan are 
restoration of aquatic habitat on public and non-public lands 
(2,500 acres), preservation of aquatic habitat on public and 
non-public lands subject to the effects of riverbed degradation 
(700 acres), acquisition and development of existing 
undeveloped habitat on private lands (28,000 acres), and 
development of terrestrial wildlife habitat on existing 
undeveloped public lands (16,900 acres). Estimated fully 
funded cost of the project (1992) is $67,700,000, all Federal. 
Both the Kansas City and Omaha Districts are involved in 
the implementation of the project, with Kansas City District 
involvement directed mainly to sites in Kansas and Missouri. 
Local cooperation. There is no non-Federal sponsor 
for the project. The states of Iowa, Nebraska, Kansas, and 
Missouri are voluntarily serving on a coordinating team 
which is actively involved in ongoing project activities. 
Operations during fiscal year. Initial funding was 
received for land acquisition and construction of mitigation 
features. Mitigation work was begun in January 1992 on 
the Grand Pass Wildlife Area, a site owned by the Missouri 
Department of Conservation. That work was completed in 
August 1992. Design was completed for mitigation on 
another site, Louisville Bend Wildlife Area, Iowa. Negotiations 
with landowners were initiated preparatory to the purchase 
of lands in all four states with FY 1993 funds. 
Flood Control 
3. BLUE RIVER CHANNEL, 
KANSAS CITY, MO 
Location. Along the Blue River and tributaries in 
Jackson County, Missouri. 
Existing project. Preliminary plans consist of 12.5 miles 
of improved channel along the Blue River within Kansas 
City, Missouri. Estimated Federal cost through construction 
of the project (1992) is $182,000,000, and estimated 
non-Federal cost of lands, damages and relocations is 
$29,500,000. 
Local cooperation. Section 2, Flood Control Act of 
June 22, 1936 applies. The City of Kansas City, Missouri, 
passed a resolution of intent on December 9, 1975 to provide 
the required assurances of local cooperation when 
requested. The Section 221 agreement was signed by the 
Kansas City District Engineer on September 8, 1983. 
27-2

KANSAS CITY, MO., DISTRICT 
Operations during fiscal year. Preconstruction planning 
is complete and final designs are underway. The first and 
second channel contracts are complete. A contract for pile 
stabilization is complete. Railroad relocations are completed 
in the reach of Stages 1 and 2, and are being negotiated 
in the Stage 3 reach. A contract for removal of contaminated 
sediments is complete. The contract for the Paved Reach 
was awarded, and construction will be completed in early 
1994. The Stage 3 Features Design Memorandum was 
approved and preparations for the plans and specifications 
for the 12th-23rd Street contract are underway. 
4. BRUSH CREEK, KANSAS CITY, MO 
Location. A major tributary of the Blue River in Kansas 
City, Missouri, and Johnson County, Kansas, draining 
a highly urbanized 29-square-mile.area in the two states. 
Existing project. The authorized project consists of improving 
about 7,500 feet of the channel from near Roanoke 
Parkway downstream to near Troost Avenue in Kansas City. 
At the request of the sponsor, Kansas City, Missouri, a 
modified project will be built which provides identical flood 
protection, but which also accommodates park and recreation 
development in the authorized reach. Estimated fully 
funded Federal cost of the modified project (1992) is 
$20,070,000, and estimated non-Federal cost of lands, 
damages, relocations, and cash is $23,330,000. 
Local cooperation. The City of Kansas City and the 
Corps of Engineers entered into a Local Cooperation 
Agreement (LCA) on the project in March 1991. 
Operations during fiscal year. The Stage 1 construction 
contract which consisted of removal of a railroad bridge and 
the Volker Park conduit was completed in April of 1992. 
Stage 2 plans and specifications were advertised in August 
1992, with contract award being completed on 3 November 
1992. Stage 2 includes all remaining structural project 
features. The sponsor (Kansas City, Missouri) is approximately 
80 percent complete on its Oak Street bridge, with 
opening scheduled for April 1993. Replacement by the sponsor 
of Main-Brookside bridge is fully designed and will begin 
construction in 1993. 
5. CLINTON LAKE, WAKARUSA 
RIVER, KS 
Location. Damsite is on Wakarusa River about 4 miles 
southwest of Lawrence, in Douglas County, Kansas. Lake 
extends into Shawnee and Osage Counties, Kansas. 
Existing project. An earthfill dam about 9,250 feet long 
constructed to a height of about 114 feet with an uncontrolled 
spillway in left abutment. Total reservoir storage 
capacity 397,200 acre-feet (258,300 for flood control, 28,500 
for sediment reserve, and 110,400 of multipurpose storage 
for municipal and industrial waste supply and recreation). 
Cost of constructing the completed project was $57,415,433. 
Construction was initiated in January 1972, and the project 
was placed in operation in November 1977. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Reimbursement in the estimated 
amount of $6,768,000 is required for water supply storage 
in accordance with Water Supply Act of 1958. A contract 
was signed by the State on September 6, 1978 and was 
approved by the Secretary of the Army on October 30, 1978. 
Utilization of storage was initiated in December 1979. 
Repayment also began at that time. 
Operations during fiscal year. Visitation for FY 1992 
was 5,528,574 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
6. HARLAN COUNTY LAKE, 
REPUBLICAN RIVER, NE 
Location. Dam is on main stem of Republican River 
about 235 miles above confluence of stream with Smoky 
Hill River. Site is in Harlan County, 11/2 miles south of 
Republican City and 13 miles west of Franklin, Nebraska. 
Existing project. An earthfill dam about 107 feet above 
streambed with a total length of 11,827 feet, including a 
gate-controlled, concrete, gravity-type spillway section near 
center of dam. Reservoir provides storage capacity of 
850,000 acre-feet (500,000 for flood control and 350,000 for 
irrigation and sedimentation allowance). Initial cost of constructing 
the project was $45,279,532. Total Federal cost 
of project, including $1,017,623 for major rehabilitation 
work and $1,832,394 supplemental recreation development 
(Code 710), is $48,129,549. Construction of the project was 
initiated in August 1946. Project was placed in operation 
in December 1952. Major rehabilitation work was completed 
in FY 1968. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 4,364,516 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance and installation 
of instrumentation system in the spillway structure. 
Study of future operation. In FY 1991 the study of 
Future Operation at Harlan County Lake was initiated. 
Since 1965 inflows to Harlan County Lake have declined 
due to conservation practices and ground water development 
in the Republican River basin upstream of the project. 
The reduced inflow resulted in lake levels below elevation 
1,932.8 feet, m.s.l., (bottom of irrigation pool and top of 
sediment pool) in 1991. The low lake levels resulted in 
negative impacts to the irrigation, recreation, and fish and 
wildlife uses of the lake. It is unlikely that inflows will improve 
in the future. Therefore, a study is needed to develop 
a detailed inflow operating plan for Harlan County Lake 
that is in the best public interest. 
7. HILLSDALE LAKE, BIG BULL 
CREEK, KS 
Location. The project is located approximately 12 miles 
above the mouth of Big Bull Creek, a tributary of the Marais 
des Cygnes River and about 21/2 miles west of Hillsdale, in 
Miami County, Kansas. 
Existing project. An earthfill embankment about 11,600 
feet long (including approximately 3,300 feet of dike section) 
about 75 feet above rising valley flood plain. The 
spillway is gravity type uncontrolled and the outlet works 
are controlled. The total reservoir storage capacity is 
160,000 acre-feet (81,000 for flood control, 11,000 for 
sediment reserve, and 68,000 for multipurpose storage 
for water supply, water quality control, and recreation). 
27-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Construction was initiated in December 1974 and project 
was placed in operation in October 1981. Federal cost of 
construction was $64,161,400. 
Local cooperation. Section 2, Flood Control Act 1938, 
applies. Local interests must make reimbursement of 
$23,342,756 for water supply storage in accordance with 
Water Supply Act of 1958. The Kansas Water Resources 
Board signed a contract in January 1974, approved by the 
Secretary of the Army in April 1974, for the entire 53,000 
acre-feet of water supply storage. The Kansas Department 
of Wildlife and Parks has a 50-year lease on 12,880 acres 
for management of land and water areas for public park, 
recreational, and fish and wildlife purposes. 
Operations during fiscal year. Visitation for FY 1992 
was 503,675 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance and repair of south 
access road. 
8. KANOPOLIS LAKE, SMOKY 
HILL RIVER, KS 
Location. Dam is on Smoky Hill River about 205 river 
miles above mouth of stream, and about 11 miles northwest 
of Marquette, Kansas. 
Existing project. An earthfill dam about 131 feet above 
streambed, having a total length of 15,360 feet, including 
4,070 feet of dike section on the left abutment and 2,550 
feet of dike section on right abutment. The reservoir provides 
storage capacity of 450,000 acre-feet, (400,000 for 
flood control and 50,000 for recreation and streamflow 
regulation). Outlet works and spillway are in right abutment. 
Initial cost of constructing the project was $12,327,735. 
Ibtal Federal cost of project, including $249,492, supplemental 
recreational development (Code 710), was $12,577,227. 
Construction was initiated in June 1940, and project was 
placed in operation in May 1948. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 2,304,587 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
9. LITTLE BLUE RIVER LAKES, MO 
Location. This project consists of two lakes in Jackson 
County, Missouri, located in Kansas City, Missouri, and 
suburban communities. The Blue Springs Lake site is on 
the East Fork of the Little Blue River about 1/2 mile south 
of U.S. Highway 40, and the Longview Lake site is on the 
main stem at approximately 109th Street. 
Existing project. The Blue Springs dam is an earthfill 
embankment about 2,500 feet long and rising about 78 feet 
above the streambed, with an uncontrolled service spillway 
and uncontrolled outlet conduit. The total reservoir storage 
capacity is 26,600 acre-feet (15,700 for flood control, 10,600 
for multipurpose storage for water quality and recreation, 
and 300 for sedimentation). 
The Longview dam is an earthfill embankment about 
1,900 feet long and rising about 120 feet above the streambed, 
with an uncontrolled service spillway and an uncontrolled 
outlet conduit. The total reservoir storage capacity 
is 46,900 acre-feet (24,300 for flood control and 20,600 for 
multipurpose storage for water quality and recreation, and 
2,000 for sedimentation). Federal cost (1992) for both lakes 
through construction of the project was $140,809,200. Construction 
was initiated in September 1977, and the project 
became operational in September 1988. 
Local cooperation. Section 2 of the Flood Control Act 
of June 28, 1938 applies. Local interests must share in 
separable cost allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. The Jackson 
County Legislature approved a recreation cost-sharing contract 
on July 5, 1974 which was approved by the Secretary 
of the Army on June 24, 1976. A supplemental agreement, 
signed by Jackson County officials on June 5, 1978, and 
approved by the Secretary of the Army January 10, 1979, 
revised the existing contract to include additional costs 
involved in raising the multipurpose pool elevation at the 
Blue Springs Lake. Reimbursement for recreation was 
$15,047,000 of which $450,000 was accomplished during 
construction by local interests. 
Operations during fiscal year. Project is complete. Land 
acquisition is complete. Visitation for FY 1992 was 
9,426,138 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
10. LONG BRANCH LAKE, LITTLE 
CHARITON RIVER, MO 
Location. Damsite is on East Fork of Little Chariton 
River in north-central Missouri about 2 miles west of Macon 
in Macon County. 
Existing project. An earthfill dam about 3,800 feet long 
and about 71 feet high with an uncontrolled outlet conduit 
and an uncontrolled service spillway in right abutment.'Ibtal 
reservoir storage capacity is 65,000 acre-feet (29,000 for 
flood control, 4,000 for sediment reserve, and 32,000 of 
multipurpose storage for water supply, water quality control, 
fish and wildlife, and recreation). Estimated Federal 
cost (1992) is $20,279,000, and estimated non-Federal cost 
is $3,626,000. Construction was initiated in March 1973. 
Project was placed in useful operation for flood control on 
September 1, 1980. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Local interests must make reimbursement 
of $5,567,000 for water supply storage in accordance 
with Water Supply Act of 1958 and share in separable 
cost of $3,626,000 allocated to recreation in accordance with 
Federal Water Project Recreation Act of 1965. On 
September 15, 1972 the Secretary of the Army approved 
a contract signed by the City of Macon, Missouri, for water 
supply and recreation development. Missouri state agencies 
indicated their intent to sponsor future water supply and 
signed a contract on June 17, 1977 to sponsor recreational 
development in lieu of City of Macon. After review by the 
Office of the Secretary of the Army, the state signed the 
contract in December 1979, and it was approved by the 
Secretary of the Army on April 18, 1980. 
Operations during fiscal year. Visitation for FY 1992 
was 1,190,911 visitor hours. Project is 100 percent complete 
on scheduled work. The remaining unscheduled work is construction 
of recreation facilities. Maintenance: Activities 
consisted of ordinary operation and maintenance. 
27-4

KANSAS CITY, MO., DISTRICT 
11. MELVERN LAKE, MARAIS DES 
CYGNES (OSAGE) RIVER, KS 
Location. Damsite is on Marais des Cygnes (Osage) River 
in Osage County, Kansas, about 4 miles west of Melvern, 
Kansas. 
Existing project. An earthfill dam about 9,700 feet long 
and about 98 feet high with an uncontrolled chute-type 
spillway in left abutment. Total reservoir storage capacity 
is 363,000 acre-feet (200,000 for flood control, 26,000 for 
sediment reserve, and 137,000 of multipurpose storage for 
water quality control, and recreation). Cost of constructing 
the completed project was $37;436,530. Construction was 
initiated in July 1967, and the project was placed in operation 
in August 1972. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 6,801,720 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
12. MILFORD LAKE, REPUBLICAN 
RIVER, KS 
Location. Damsite is on Republican River near village 
of Alida about 10 miles above confluence of Republican and 
Smoky Hill Rivers which form Kansas River; and about 4 
miles northwest of Junction City, Kansas. 
Existing project. An earthfill dam about 6,300 feet long 
and 126 feet high with an uncontrolled service-chute 
spillway in a saddle on right abutment. Total reservoir 
storage capacity is 1,160,000 acre-feet (700,000 for flood 
control, 160,000 for sediment reserve and 300,000 of 
multipurpose storage for water supply, water quality control, 
and recreation). Water supply storage is included in 
project at request of Governor of Kansas under provisions 
of Federal Water Supply Act of 1958. Initial cost of constructing 
the completed project was $48,268,843. Total 
Federal cost of project, including $1,297,649 supplemental 
recreational development (Code 710), was $49,566,492. Construction 
was initiated in July 1961. Project was placed in 
operation in June 1965. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must make reimbursement of 
$13,045,576 for water supply storage in accordance with 
Water Supply Act of 1958. Utilization of storage has not 
been initiated. Reimbursement was initiated, at the option 
of the State, in September 1976. 
Operations during fiscal year. Visitation for FY 1992 
was 9,679,550 visitor hours. Maintenance: Activities included 
ordinary operation and maintenance. 
13. MISSOURI RIVER LEVEE 
SYSTEM, IA, NE, KS, AND MO 
(RULO, NE, TO MOUTH) 
Location. On both banks of Missouri River from Sioux 
City, Iowa, about 760 miles to mouth near St. Louis, 
Missouri. Portion of project in Kansas City District 
extends from Rulo, Nebraska, 498 miles to mouth. 
Existing project. A series of levee units and appurtenant 
works along both sides of Missouri River from Sioux 
City, Iowa, to the mouth, for protection of agricultural lands 
and small communities against floods. Estimated cost 
(1992) for the active portion of the project from Rulo, 
Nebraska, to mouth is $116,169,000, including $85,389,000 
Federal and $20,412,000 non-Federal contributions. Costs 
of $10,368,000 for lands and damages are to be borne by 
local interests. Remaining portion of project consists of units 
on which planning and construction are being delayed pending 
completion of restudy to assure that additional levee 
construction is economically justified. Current cost estimate 
for deferred, inactive, and deauthorized portion of project 
Rulo, Nebraska, to mouth is $255,259,000 (1964, 1986, and 
1987 price levels), of which $231,233,000 is Federal cost for 
construction and $24,026,000 for lands and damages to be 
borne by local interests. Construction of the project was 
initiated in June 1948. 
Local cooperation. Section 3, Flood Control Act of 1936 
applies. Fully complied with for all completed units and 
units under construction. Local sponsors provide all operation 
and maintenance. 
Operations during fiscal year. Status of individual units 
of active portion of project at end of fiscal year is shown 
in Table 27-H on Missouri River Levee System. Planning 
on Unit L385 and Unit L142 continued. 
14. PERRY LAKE, DELAWARE 
RIVER, KS 
Location. Damsite is on Delaware River about 5 miles 
above mouth in Jefferson County, and about 3 miles 
northwest of Perry, Kansas 
Existing project. An earthfill dam about 7,750 feet long 
constructed to an elevation about 95 feet above valley floor 
with gated-outlet works and an uncontrolled spillway in left 
abutment. Tobtal reservoir storage capacity is 770,000 acrefeet 
(480,000 for flood control, including 140,000 for sediment 
reserve and 150,000 of multipurpose storage for water 
supply, water quality control, and recreation). Water supply 
storage is included in project plan at request of State 
of Kansas under provisions of Federal Water Supply Act 
of 1958. Initial cost of constructing the completed project 
was $48,371,706. Total Federal cost of project, including 
$724,212 supplemental recreational development (Code 
710), is $49,095,918. Construction was initiated in March 
1964, and the project was placed in operation in January 
1969. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Local interests must make reimbursement of 
$9,208,342 for water supply storage in accordance with 
Water Supply Act of 1958. Utilization of storage has not 
been initiated. Reimbursement was initiated at the option 
of the State in September 1978. 
Operations during fiscal year. Visitation for FY 1992 
was 11,359,353 visitor hours. Maintenance: Activities included 
award of contract for construction of Slough Creek 
washhouse, renovation of relief wells, and ordinary operation 
and maintenance. 
27-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
15. PICK-SLOAN MISSOURI BASIN 
PROGRAM (KANSAS CITY DIST.) 
Location. Flood control improvements included in this 
project are on and along the Missouri River and several of 
its principle tributaries, in states comprising the Missouri 
River Basin. 
Existing project. The Pick-Sloan Missouri Basin program 
for flood control and other purposes in Missouri River 
Basin provides for levees along Missouri River between 
Sioux City, Iowa, and the mouth, flood-protection works at 
certain municipalities, and reservoirs on main stem of 
Missouri River and on tributaries for control of flooding. 
(See Table 27-B for authorizing legislation and Table 27-I 
on Kansas City District projects included in Pick-Sloan 
Missouri Basin program.) See individual project reports. 
16. POMME DE TERRE LAKE 
POMME DE TERRE RIVER, MO 
Location. Dam is on main stem of Pomme de T'rre River, 
about 44 miles above mouth of stream in Hickory County, 
Missouri. The lake extending upstream into Polk County, 
Missouri. Site is about 4 miles south of Hermitage, Missouri, 
and 20 miles north of Bolivar, Missouri. 
Existing project. An earth and rockfill dam about 4,630 
feet long constructed to about 155 feet above riverbed and 
a dike section on left abutment about 2,790 feet long, providing 
storage capacity of 650,000 acre-feet (407,000 for 
flood control and 243,000 for sedimentation and multipurpose). 
Initial cost of constructing the completed project 
was $14,946,784. Tobtal Federal cost of project, including 
$329,140 area redevelopment and $2,089,529 supplemental 
recreational development (Code 710), is $17,365,453. 
Construction was initiated in January 1957, and the project 
was placed in useful operation in October 1961. 
Operations during fiscal year. Visitation for FY 1992 
was 11,508,593 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
17. POMONA LAKE, ONE HUNDRED 
TEN MILE CREEK, KS 
Location. Dam is on One Hundred Ten Mile Creek, a 
tributary of Marais des Cygnes (Osage) River, 7 miles above 
mouth of stream in Osage County, Kansas, about 8 miles 
northwest of Pomona, Kansas, and 34 miles upstream from 
Ottawa, Kansas. 
Existing project. An earthfill dam 7,750 feet long constructed 
to an average height of about 85 feet above 
streambed, with gated-outlet workes and an ungated chutetype 
spillway near left abutment. Total reservoir storage 
capacity is 230,000 acre-feet (160,000 for flood control, 
14,000 for sediment reserve, and 56,000 of multipurpose 
storage for water quality control, and recreation). Initial 
cost of constructing the completed project was $13,272,108. 
Total Federal cost of project, including supplemental recreational 
development $731,130 (Code 710), was $14,003,238. 
Construction began in July 1959, and the project was placed 
in operation in October 1963. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. Pomona has water supply reimbursement under 
Water Supply Act of 1958 totaling $71,018. 
Operations during fiscal year. Visitation for FY 1992 
was 9,318,408 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance 
18. RATHBUN LAKE, CHARITON 
RIVER, IA 
Location. Damsite is on Chariton River about 7 miles 
north of Centerville and 1 mile north of Rathbun, Appanoose 
County, Iowa. 
Existing project. An earthfill dam 10,600 feet long constructed 
to an elevation about 86 feet above valley floor, with 
gated-outlet works and an uncontrolled service chute with 
paved sill spillway about a mile upstream from left abutment. 
Total reservoir storage capacity is 552,000 acre-feet 
(339,000 for flood control, 24,000 for sediment reserve and 
189,000 of multipurpose storage for navigation, water 
quality control, and recreation). Initial cost of constructing 
the project was $27,033,210. Total Federal cost of project, 
including $588,948 supplemental recreation development 
(Code 710), was $27,622,158. Construction of the project 
was initiated in September 1964 and completed in 
November 1969. The operating plan for this project was 
revised to reduce flood control releases during critical times 
of the year to allow local farmers better access during planting 
and harvesting and to facilitate field drainage and drying 
out. The revised plan has resulted in more frequent high 
pool elevations than anticipated, which has inundated roads 
and recreation facilities. A shoreline erosion study was 
accomplished; and a supplement to the master plan was 
approved, which resulted in relocation of recreation facilities 
and bank stabilization work to compensate for the higher 
lake levels. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 5,354,010 visitor hours. Maintenance: Activities included 
boundary rectification and ordinary operation and 
maintenance. 
19. SMITHVILLE LAKE, LITTLE 
PLATTE RIVER, MO 
Location. Damsite is on Little Platte River about 1 mile 
northeast of Smithville and about 5 miles north of Kansas 
City, in Clay and Clinton Counties, Missouri. 
Existing project. Earthfill dam about 4,200 feet long and 
95 feet high with an uncontrolled service spillway. A dike 
about 2,400 feet long crosses a saddle in the left abutment. 
Total reservoir storage capacity is 246,500 acre-feet (92,000 
for flood control, 52,300 for sediment reserve, and 102,200 
of multipurpose storage for water supply, water quality control, 
and recreation). Cost of constructing the project was 
$87,685,314. Construction was initiatedin November 1973, 
and the project was placed in operation in March 1982. 
Local cooperation. Section 2, Flood Control Act of 
June 28, 1938 applies. Reimbursement of $24,000,000 will 
be required for water supply storage in accordance with 
Water Supply Act of 1958, and reimbursement of $7,500,000 
will be required for recreation development in accordance 
27-6

KANSAS CITY, MO., DISTRICT 
with Federal Water Project Recreation Act of 1965. Additional 
non-Federal contribution for recreation amounts to 
$737,000. All contracts for local cooperation were approved 
by the Secretary of the Army on November 27, 1972. 
Operations during fiscal year. Visitation for FY 1992 
was 6,658,106 visitor hours. Maintenance: Activities consisted 
of ordinary operation and maintenance. 
20. TUTTLE CREEK LAKE, 
BIG BLUE RIVER, KS 
Location. Dam is on main stem of Big Blue River, 
about 12 miles above the mouth of stream in Riley and 
Pottawatomie Counties, Kansas. Site is about 5 miles north 
of Manhattan, Kansas. 
Existing project. An earth and rock dam 7,500 feet long 
and 157 feet high. Total reservoir storage capacity is 
2,346,000 acre-feet (1,933,000 for flood control, 228,000 for 
sediment reserve and 185,000 for multipurpose storage, for 
low-flow regulation, navigation, and recreation). Initial cost 
of constructing the completed project was $80,051,031. Total 
Federal cost of project, including $533,048 supplemental 
recreational development (Code 710), was $80,584,079. Construction 
began in October 1952. Project was placed in 
operation in July 1962. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 2,807,728 visitor hours. Maintenance: Activities included 
ordinary operation and maintenance. 
21. WILSON LAKE, SALINE RIVER, KS 
Location. Dam is on Saline River about 130 miles above 
its mouth, near eastern edge of Russell County, Kansas, 
about 50 miles west of Salina, 10 miles north of Wilson, and 
20 miles east of Russell, Kansas. 
Existing project. An earthfill dam about 5,600 feet long 
and 160 feet high with a gated-outlet works, chute spillway, 
storage capacity is 776,000 acre-feet (511,000 for flood control, 
40,000 for sediment reserve and 225,000 multipurpose 
storage for irrigation, navigation, and low flow regulation). 
Initial cost of constructing the project was $20,015,023. 
Total Federal cost of project, including $448,344 supplemental 
recreational development (Code 710), is $20,463,367. 
Construction began in April 1961 and the project was placed 
in operation in December 1964. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 3,767,310 visitor hours. Maintenance: Activity included 
replacement of relief wells and ordinary operation and 
maintenance. Also, a Congressional add of $900,000 was 
included in FY 92. Renovation of recreation facilities was 
completed this fiscal year, and contract was awarded for 
construction of Lucas Park washhouse to be completed in 
FY 93. 
22. SCHEDULING OF FLOOD CONTROL 
RESERVOIR OPERATIONS 
Under sections 7 and 9, 1944 Flood Control Act, the Corps 
is responsible for detailed scheduling of operations concerning 
storage capacity reserved for or assigned to flood control 
in reservoirs constructed by Bureau of Reclamation as 
well as those constructed by the Corps. 
23. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Flood Control Act of June 22, 1936, P.L. 738, and subsequent 
acts require local interests to furnish assurances 
that they will maintain and operate certain local protection 
projects after completion in accordance with regulations 
prescribed by the Secretary of the Army. District Engineers 
are responsible for administration of these regulations 
within boundaries of their respective district. (See T'Pable 
27-J on inspection of completed flood control projects.) 
24. DISASTER PREPAREDNESS 
PROGRAM 
Includes planning, training, inspection, supplies and 
equipment, and personnel. Inspections of non-Federal flood 
control projects to assure compliance with eligibility and 
maintenance requirements were performed during FY 92. 
Damaged Federal flood control projects are also inspected 
for eligibility for repair. 
25. FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and 
Antecedent Legislation). 
Operations for period 1 October 1991 thru 30 September 
1992 were as follows: 
Disaster Preparedness Program. See paragraph 24, 
above. 
Emergency Operations. Flooding during the last quarter 
of FY 92 resulted in considerable costs incurred under the 
Emergency Operations feature; however, funds to cover 
reimbursement activities were not received during this 
fiscal year. Full reimbursement for those events will be 
received during FY 93. 
Rehabilitation of Non-Federal Flood Control Works. 
Although no costs were incurred for repair of non-Federal 
levees during the fiscal year, one Federal levee was repaired 
at a cost of $33,136. In addition, the surplus amount of 
$1,827 of sponsor's contributed funds were revoked as a 
result of a rehabilitation done in FY 91 of a non-Federal 
levee. 
(See Table 27-L for costs.) 
27-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Small Flood Control Projects Not Specifically 
Authorized by Congress (Sec. 205, 1948 Flood Control 
Act, Public Law 858, 80th Cong., June 30, 1948, as 
amended). 
Each project selected must be complete in itself, 
economically and environmentally justified, and limited to 
a Federal cost of not more than $5 million. The local sponsoring 
agency must agree to provide without cost to the 
Department of the Army, all lands, easements, and rightsof-
way, including highway, highway bridge, and utility relocations 
and alterations; hold and save the Department of the 
Army free from damages; maintain and operate the project 
after completion; assume all project costs in excess of 
the Federal cost limit; and prevent future encroachments 
on improved channels. 
The Water Resources Development Act of 1986 requires 
the non-Federal sponsors of Section 205 projects to pay 50 
percent of the cost of the feasibility study. For structural 
flood control projects, the sponsor must pay in cash during 
the construction at least 5 percent of the construction cost. 
The sponsor's cash and other contributions must equal 25 
percent of the total construction cost, but will not be required 
to exceed 50 percent. 
There was one Section 205 project under construction in 
Fiscal Year 1992. 
Blue River Basin, Overland Park, KS, Indian Creek 
Channel Modification - Construction was started in May 
1992 on approximately 1 mile of channel widening of 
Indian Creek, a tributary of the Blue River in Overland 
Park. Construction was approximately 90 percent complete 
as of September 1992. The City of Overland Park, Kansas, 
and the Corps of Engineers entered into a Local Cooperation 
Agreement (LCA) in May 1991. 'Ital estimated Federal 
cost is $770,000 and $257,000 non-Federal for lands, relocations, 
and cash. 
See Table L for expenditures under Section 205 during 
Fiscal Year 1992. 
Emergency Streambank Protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th Cong., July 24, 
1946) as amended. 
Each project selected must be complete in itself, engineeringly 
feasible, economically justifiable, environmentally 
acceptable, and limited to a Federal statutory cost of not 
more than $500,000. The local sponsoring entity must agree 
to provide without cost to the Department of the Army, all 
lands, easements, and rights-of-way, including highway, 
highway bridge, and utility relocations and alterations required 
for project construction; provide over the period of 
construction, an amount equal to not less than 25 percent 
or more than 50 percent of total project cost, at least 5 percent 
of which will be cash; operate, maintain, repair, replace, 
and rehabilitate the project upon completion; hold and save 
the Department of the Arrmy free from damages arising 
from the construction, operation, and maintenance of the 
completed project; and assume all project costs in excess 
of the Federal statutory cost limit. 
Projects that were physically complete in FY 1991 and 
financially complete in FY 1992 are as follows (for project 
description, see FY 91 Annual Report): 
Big Blue River, Blue Springs, NE, Sewerline and Road 
Little Blue River, Thayer County, NE, Gilead North 
Bridge 
Little Blue River, Washington County, KS, County Road 
Little Blue River, Washington County, KS, Spence 
Bridge 
Projects that were physically and financially complete in 
FY 1992 are as follows: 
102 River, Nodaway County, MO, South Pickering 
Bridge - Construction was completed in October 1991 to 
protect a county bridge and road. The project consists of 
a stone-fill revetment along the left streambank. 
Tkibutary to Kill Creek, DeSoto, KS, Sewage Treatment 
Plant - Construction was completed in April 1992 to 
protect a city sewage treatment plant. The project consists 
of a stone-fill revetment along the right streambank. 
Republican River, Clifton, KS, Sewage Lagoons - Construction 
was completed in February 1992 to protect a city 
sewage lagoon. The project consists of a stone-fill revetment 
along the left streambank. 
See Table 27-L for Emergency Streambank Protection 
expenditures during FY 1992. 
Multiple Purpose Projects 
Including Power 
26. HARRY S. TRUMAN DAM AND 
RESERVOIR, OSAGE RIVER, MO 
Location. Damsite is on main stem of Osage River about 
1.5 miles northwest of Warsaw, Benton County, Missouri. 
Reservoir extends into Bates, Henry, Hickory, St. Clair, and 
Vernon Counties, Missouri. 
Existing project. An earthfill dam about 5,000 feet long 
constructed to an average height of about 96 feet above 
streambed, including a gate-controlled overfall spillway and 
a power installation consisting of six inclined pumpgenerating 
units with a combined generating capability of 
160,000 kilowatts. Total reservoir storage capacity is 
5,202,000 acre-feet (3,918,000 for flood control, 244,000 for 
sediment reserve, and 1,040,000 multipurpose storage for 
power, low-flow regulation, and recreation). Public Law 
91-267, approved May 26, 1970, authorized a change in project 
name from Kaysinger Bluff Dam and Reservoir, Osage 
River Basin, Missouri, to the Harry S. Truman Dam and 
Reservoir. Estimated cost (1992) through construction of 
the project is $547,710,000. Construction of relocated 
Missouri Highway M-13 was initiated September 1964 and 
completed May 1966. Construction of the dam and reservoir 
was initiated in October 1964. The embankment has 
been completed including the paved roadway on top of the 
dam. The spillway was completed in October 1979. The 
Southwestern Power Administration powerline needed for 
final testing and commercial operation of the generators 
was completed in December 1979. The first power unit was 
placed on line on December 22, 1979. Subsequent problems 
with the turbine bearings required remedial design on the 
bearings. Restricted commercial power production began 
in April 1982. Through September 1992, power generation 
totaled 3,185,154,800 kilowatt hours. Of the gross income 
27-8

KANSAS CITY, MO., DISTRICT 
From the sale of power by Southwestern Power Administration, 
$66,043,862 was allocated to the Corps of Engineers 
for project power operating costs, interest, and investment 
recovery. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operation during fiscal year. Visitation for FY 1992 
was 13,917,693 visitor hours. Work was continued on real 
estate activities and construction of powerplant features. 
Project is 99 percent complete. During FY 1992, 
138,781,000 kilowatt-hours of electrical power were generated. 
Maintenance activities consisted of continuation of 
repair of turbine blades, and ordinary operation and 
maintenance. 
27. STOCKTON LAKE, SAC RIVER, MO 
Location. Damsite is on Sac River about 49.5 miles above 
its confluence with Osage River, and about 1 mile east of 
Stockton, Cedar County, Missouri, lake extending into Dade 
and Polk Counties. 
Existing project. A rock-shell dam with impervious core 
about 5,100 feet long constructed to an average height of 
about 128 feet, with a gated overfall spillway and a 
45,200-kilowatt power installation. Total reservoir storage 
capacity is 1,674,000 acre-feet (774,000 for flood control, 
25,000 for sediment reserve and 875,000 multipurpose 
storage for power and recreation). Initial cost of constructing 
the completed project was $75,715,300. Cost of the 
project, including $3,758,000 for downstream channel 
work and $502,057 for supplemental recreational development 
(Code 710), was $79,975,357. Construction was 
initiated in October 1963, and the project was placed in 
operation in December 1969. Power operation problems 
were encountered with the initial operation in March 1973 
because the downstream channel did not have the capacity 
which earlier observations and computations indicated. As 
a result, it has been necessary to restrict the power operation 
to about the 30,000 kilowatt level. Right-of-way for construction 
of a channel cutoff and bridge at Horseshoe Bend 
were acquired, and construction completed. Sloughing 
easements downstream to Caplinger Mills were acquired. 
Completion assured downstream channel capacity to Caplinger 
Mills of 8,000 c.f.s. for powerplant operation. 
Discharge in this range will accommodate power operations 
at a 39,500-kilowatt level. Through September 1992, power 
generation totaled 1,160,812,800 kilowatt-hours. Of the 
gross income from the sale of power by Southwestern Power 
Administration, $22,936,835 was allocated to the Corps of 
Engineers for project operating costs, interest, and investment 
recovery. 
Local cooperation. Section 2, Flood Control Act of 1938, 
applies. 
Operations during fiscal year. Visitation for FY 1992 
was 8,103,433 visitor hours. The project is complete and in 
operational status. During FY 1992, 40,211,000 kilowatthours 
of electrical power were generated. Maintenance: 
Activities consisted of renovation of Ruark Bluff public use 
area and ordinary operation and maintenance. 
General Investigations 
28. GENERAL INVESTIGATIONS 
Fiscal year 1992 costs totaled $960,387 for all General 
Investigations activities. See Table 27-K which covers 
Surveys, Collection and Study of Basic Data, and Preconstruction 
Engineering and Design. 
27-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
COST AND FINANCIAL STATEMENT 
ii 
See 
Section 
27-10 
TABLE 27-A 
n Text Project Funding 
1. Missouri River, New Work: 
Sioux City, IA Approp. 
to Mouth (Rulo, Cost 
Nebr., to Mouth) Maint. 
(Federal Funds) Approp. 
Cost 
Contributed Funds New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Consolidated New Work: 
Summary Approp. 
Cost 
Maint. 
Approp. 
Cost 
2. Missouri River Fish New Work: 
& Wildlife Mitigation, Approp. 
IA, NE, KS & MO Cost 
3. Blue River Channel New Work: 
Kansas City, MO Approp. 
(Federal Funds) Cost 
Contributed Funds New Work: 
Approp. 
Cost 
Consolidated New Work: 
Summary Approp. 
Cost 
4. Brush Creek, New Work: 
Kansas City, MO Approp. 
(Federal Funds) Cost 
Contributed Funds New Work: 
Authorized Project Approp. 
Cost 
Expanded Project4 New Work: 
Approp. 
Cost 
Consolidated New Work: 
Summary Approp. 
Cost 
5. Clinton Lake, New Work: 
Wakarusa Approp. 
River, KS Cost 
Maint. 
Approp. 
Cost 
6. Harlan County New Work: 
Lake, Republican Approp. 
River, NE Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
7. Hillsdale Lake, New Work: 
Big Bull Approp. 
Creek, KS Cost 
Maint. 
Approp. 
Cost 
Total Cost to 
FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
- - - - 237,942,1901 
- - - - 237,942,1901 
5,424,000 4,052,460 3,954,000 4,355,000 297,775,7742 
5,274,000 4,200,762 3,955,698 4,355,000 297,775,7742 
- - - - 816,190 
- - - - 816,190 
- - - - 22,642 
- - - - 22,642 
- - - - 238,758,3801 
- - - - 238,758,3801 
5,424,000 4,052,460 3,954,000 4,355,000 297,798,416 
5,274,000 4,200,762 3,955,698 4,355,000 297,798,416 
223,000 219,000 572,000 1,014,000 
167,395 263,858 580,300 1,011,553 
7,031,000 5,141,000 8,154,000 14,703,000 62,949,171 
9,982,519 5,170,969 8,158,558 14,703,356 62,948,1733 
- - 32,400 - 32,400 
- - 20,000 12,381 32,381 
- - 8,186,400 14,703,000 62,981,571 
- - 8,178,558 14,715,737 62,980,5543 
255,000 380,000 695,000 1,078,000 3,973,000 
259,530 297,961 777,092 1,077,856 3,972,815 
- - 342,000 - 342,000 
- - 11,721 328,936 340,657 
- - 3,445,000 2,867,000 6,312,000 
- - 130,800 536,721 667,5214 
- - 4,482,000 3,945,000 10,627,000 
- - 919,613 1,943,513 4,980,9934 
- - - - 57,415,433 
- - - - 57,415,4335 
1,300,000 1,291,100 1,557,000 1,342,000 15,720,600 
1,301,490 1,291,110 1,524,937 1,374,063 15,720,600 
- - - - 47,111,926 
- - - - 47,111,9266 
1,203,000 1,229,923 1,553,000 1,810,000 25,145,684 
1,202,000 1,219,576 1,565,597 1,810,000 25,145,684 
- - - - 1,017,623 
- - - - 1,017,623 
- - 64,161,400 
- - - - 64,161,400 
807,000 577,670 829,000 1,310,500 7,426,870 
817,000 560,739 845,931 1,310,500 7,426,870

KANSAS CITY, MO., DISTRICT 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
8. Kanopolis Lake, 
Smoky Hill 
River, KS 
9. Little Blue River 
Lakes, Little Blue 
River, MO 
10. Long Branch Lake 
Little Chariton 
River, MO 
Contributed 
Funds 
Consolidated 
Summary 
11. Melvern Lake 
Osage (Marais des 
Cygnes) River, KS 
12. Milford Lake, 
Republican River, 
KS 
13. Missouri River 
Levee System 
IA, NE, KS 
and MO 
14. Perry Lake, 
Delaware River, KS 
16. Pomme de Terre 
Lake, Pomme de 
Terre River, MO 
17. Pomona Lake, One 
Hundred Ten Mile 
Creek, KS 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
2,: 
2,' 
1,
222,000 2,681,302 
222,000 2,644,205 
742,000 -100,000 
642,178 1,470,599 
838,000 761,084 
837,970 743,328 
- -70,000 
15,371 697 
627,000 564,412 
627,000 563,110 
- 11,554 
- 28,393 
- -58,446 
15,371 29,090 
1,205,000 
1,242,097 
185,000 
160,008 
951,000 
968,787 
161 
603,000 
604,302 
1,239,300 
1,206,465 
-26,000 
88,066 
793,000 
793,000 
623,000 
623,000 
161 - 
1,292,000 1,324,694 1,462,000 1,682,000 
1,292,000 1,321,419 1,465,275 1,582,000 
1,631,000 
1,630,995 
655,000 
809,164 
1,829,616 
1,818,913 
387,000 
384,449 
1,660,000 
1,670,708 
400,000 
402,316 
1,517,800 
1,517,800 
1,270,000 
1,260,993 
12,577,227 
12,577,2277 
24,530,212 
24,497,377 
140,809,200 
140,809,2008 
4,260,784 
4,260,784 
18,216,177 
18,216,177 
6,618,112 
6,618,112 
1,108,0759 
1,032,717 
19,324,252 
19,248,894 
37,436,530 
37,436,530 
19,731,054 
19,631,054 
49,566,492 
49,566,492 
25,676,940 
25,676,940 
62,630,851 
62,621,560 
- - - - 49,095,918 
- - - - 49,095,918 
1,651,000 1,565,189 1,915,000 2,178,000 27,883,173 
1,630,496 1,585,369 1,917,824 1,789,990 27,495,163 
- - - - 17,365,452 
- - - - 17,365,452 
1,346,000 1,345,489 1,537,000 1,710,000 25,258,101 
1,347,500 1,333,858 1,548,631 1,684,494 25,232,595 
- - - - 14,003,238 
- - - - 14,003,238 
1,262,000 1,223,287 1,336,000 1,540,000 21,681,420 
1,274,229 1,201,462 1,355,418 1,542,407 21,681,420 
27-11 
i
i

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 27-A (Continued) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
18. Rathbun Lake, 
Chariton River, 
IA 
19. Smithville Lake, 
Little Platte 
River, MO 
20. Tuttle Creek Lake 
Big Blue 
River, KS 
21. Wilson Lake, 
Saline River, 
KS 
22. Scheduling Flood 
Control Reservoir 
Operations 
23. Inspection of 
Completed Flood 
Control Projects 
24. Disaster Preparedness 
Program- 
Inspections 
26. Harry S. Truman 
Dam & Reservoir 
Osage River, MO 
27. Stockton Lake, 
Sac River, MO 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
M aint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
1,535,000 1,408,793 1,811,000 1,923,000 
1,535,500 1,367,746 1,852,047 1,923,000 
1,246,000 936,848 1,073,000 983,000 
1,246,000 932,462 1,077,386 950,500 
1,666,000 1,596,153 2,240,000 1,527,000 
1,672,600 1,571,371 2,264,782 1,527,000 
1,234,000 1,251,658 1,450,000 2,034,000 
1,209,540 1,258,428 1,467,690 1,838,084 
180,000 225,969 
180,000 225,969 
338,000 324,616 
338,000 324,616 
200,25010 
200,241 
2,660,000 
2,359,661 
200,000 
180,922 
243,000 242,000 
243,000 242,000 
375,000 
375,000 
180,913 
200,000 
427,000 
427,000 
182,000 
181,955 
27,622,159 
27,622,159 
25,732,711 
25,732,711 
87,685,314 
87,685,314 
10,999,448 
10,966,948 
80,584,079 
80,584,079 
27,664,432 
27,664,432 
20,463,367 
20,463,367 
20,441,504 
20,245,588 
55,246,452 
55,246,452 
6,111,431 
6,111,431 
1,393,16310 
1,393,118 
2,746,000 3,552,000 2,526,000 544,441,900 
2,873,772 4,278,405 2,724,080 544,431,741 
6,012,500 7,822,962 6,172,000 7,810,800 67,113,162 
6,026,000 7,659,290 6,329,552 7,464,705 66,760,947 
9,756 178 6,737 
79,975,357 
79,975,357 
2,777,500 3,031,371 2,919,000 3,666,800 38,174,671 
2,775,794 3,013,528 2,938,376 3,639,973 38,147,671 
1. Includes $8,665,594 costs of new work for previous 
project. 
2. Includes $738,109 for maintenance of previous 
project. 
3. Excludes $35,296 non-Federal contribution not required 
for authorized Blue River Channel project (Blue River Channel 
Mobay Chemical 1984-1987). 
4. Corps is building Brush Creek Expanded Project requested 
by sponsor, City of Kansas City, MO, with all costs 
of betterments and enhancements not required by Authorized 
Project funded by sponsor. Excludes sponsor's contributions 
of $1,374,829 during Preconstruction and Engineering phase, 
and $162,459 for Park Features Design during construction. 
5. Excludes $118,805 non-Federal contribution not required 
for authorized Clinton Lake project (1973-1979). 
6. Excludes cost of materials furnished Harlan County 
project without charge in the amount of $24,198. 
7. Excludes cost of materials furnished Kanopolis Lake 
project without charge in the amount of $7,885. 
8. Excludes $2,732,554 thru FY 1990 non-Federal contributions 
not required for authorized Little Blue River Lakes 
project. 
9. Corrected total. Excludes $42,149 interest during 
construction at Long Branch Lake project. 
10. After FY 1988 inspections of non-Federal levees 
previously funded under O&M are funded under FC&CE, 
96X3125 (910-140) Disaster Preparedness Program- 
Inspections which had a carryover into FY 1989 of $250. 
27-12

KANSAS CITY, MO., DISTRICT 
TABLE 27-B AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
Jul. 25, 1912 
Aug. 8, 1917 
Mar. 3, 1925 
Jan. 12, 1927 
Jul. 3, 1930 
Aug. 30, 1935 
Mar. 2, 1945 
Nov. 17, 1986 
Dec. 31, 1970 
Nov. 17, 1986 
Nov. 28, 1990 
Oct. 23, 1962 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
MISSOURI RIVER, SIOUX CITY, IA, TO 
MOUTH (RULO, NE, TO MOUTH) 
Project adopted for securing a permanent navigable 
channel of 6-foot depth from Kansas City, MO to 
mouth. 
Fixed upstream limit of improvement at upper end of 
Quindaro Bend (374.8 miles from mouth) and provided 
for dredging. 
For a mimimum width of 200 feet and depth of 6 feet, 
with a reasonable additional width around bends, 
mouth to upper end of Quindaro Bend, Kansas City, 
MO. 
Appropriation of $12 million authorized for securing a 
6-foot channel depth between Kansas City, MO, 
Quindaro bend, and Sioux City, IA. 
Appropriation of $15 million additional authorized; 
additional allotments totaling $29,153,108 were made 
by Public Works Administration under provisions of 
National Industrial Recovery Act of 1933, and 
$9,669,791 allotted under provisions of Emergency 
Relief Appropriation Act of 1935. 
Completion of improvement from mouth to Sioux City, 
IA. 
Securing a navigable channel of 9-foot depth and a 
minimum width of 300 feet. 
MISSOURI RIVER.FISH AND WILDLIFE 
MITIGATION MO, KS, IA, & NE 
Project for mitigation of fish and wildlife losses 
Missouri River Bank Stabilization and Navigation 
Project, MO, KS, IA, & NE: April 24, 1984, Report 
of Chief of Engineers, authorized at estimated cost 
of $51,900,000. 
BLUE RIVER CHANNEL, KANSAS CITY, MO 
Adopted plan for Blue River Basin and authorized 
$40,000,000 for initiation and partial accomplishment. 
BRUSH CREEK, KANSAS CITY, MO 
Project for flood control on Brush Creek, a tributary of 
the Blue River, Kansas City, MO, authorized at 
estimated total cost of $16,100,000. 
Modified to authorize the Secretary of the Army to 
construct the project substantially in accordance 
with the Post Authorization Change Report, dated 
April 1989 (revised January 1990), at a total cost of 
$26,200,000. 
CLINTON LAKE, WAKARUSA RIVER, KS 
The project for the Kansas River, KS, NE, and CO is 
authorized at an estimated cost of $88,070,000. 
HARLAN COUNTY LAKE, REPUBLICAN 
RIVER, NE 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure 
H. Doc. 1287, 61st Cong., 
(contains latest published 
map). P.L. 241-62. 
H. Doc 463, 64th Cong., 
(contains latest published 
map). 
P.L. 585-68. 
H. Doc. 1120, 60th Cong., 
P.L. 560-70. 
P.L. 67-73 
H.R.11781 
P.L. 520-71 
H. Doc 238, 73d Cong., 
(contains latest published 
map). P.L. 409-73 
H. Doc. 214, 76th Cong., 
(contains latest published 
map). P.L. 14-79. 
Title VI, Section 601(a), 
Water Resources Development 
Act of 1986, P.L. 
99-662. 
H. Doc. 91-332, 91st Cong. 
Sec. 401(a), Water Resources 
Development Act of 1986, 
P.L. 99-662 
Water Resources Development 
Act of 1990, 
P.L. 101-640. 
1962 Flood Control Act 
S. Doc 122, H. Doc 578, 
87th Cong., P.L. 87-874. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
H. Doc 842, 76th Cong.; 
P.L. 77-228. 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong., 
P.L. 534. 
27-13 
2. 
3. 
5. 
6.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 27-B (Continued) 
See Section 
in Text 
Date of 
Act 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
8. 
Sep. 3, 1954 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Aug. 13, 1968 
Oct. 27, 1965 
Sep. 3, 1954 
Sep. 3, 1954 
Aug. 18, 1941 
Dec 22, 1944 
Sep. 3, 1954 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
Jul. 24, 1946 
HILLSDALE LAKE, BIG BULL CREEK, KS 
The comprehensive plan for the Missouri River Basin. 
approved by the Act of June 28, 1938, and as 
amended and supplemented is further modified to 
include the project for flood protection on the 
Kansas River and tributaries. It is further modified 
to include the project for flood protection on the 
Osage River and tributaries. 
KANOPOLIS LAKE, SMOKY HILL RIVER, KS 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
LITTLE BLUE RIVER LAKES, MO 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
LONG BRANCH LAKE, LITTLE CHARITON 
RIVER, MO 
The project for flood protection on the Chariton and 
Little Chariton Rivers and tributaries, IA and MO, 
is authorized at an estimated cost of $9,167,000. 
MELVERN LAKE, MARAIS DES CYGNES 
(OSAGE) RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217.710,000 additional 
expenditure. 
MILFORD LAKE, REPUBLICAN RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
MISSOURI RIVER LEVEE SYSTEM, IA, NE, 
KS, AND MO 
Levees along both sides of river from Sioux City to 
Kansas City. 
Extended project from Kansas City to the mouth and 
provided for increased protection. 
PERRY LAKE, DELAWARE RIVER, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(KANSAS CITY DIST.) 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for 
initiation and partial accomplishment. 
Modified general comprehensive plan to include Harlan 
County Dam and Reservoir on Republican River, 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $150 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
27-14 
Documents 
P.L. 780, 83rd Cong., H. Doc. 
549, 81st Cong. 
Flood Control Committee 
Doc. 1, 75th Cong., 
P.L. 761. 
H. Doc. 842, 76th Cong.; 
P.L. 77-228. 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong., 
P.L. 534. 
P.L. 90-483 (H. Doc. 169, 
90th Cong. 
1965 Flood Control Act, 
P.L. 89-298, (H. Doc. 238, 
89th Cong. 
H. Does. 642, 549k and 561, 
83rd Cong., P.L. 780 
H. Doc. 549k 83rd Cong., 
P.L. 780 
H. Doc. 821, 76th Cong. 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong. 
H. Does. 642, 549k and 561, 
83rd Cong., P.L. 780. 
Flood Control Committee 
Doc. 1, 75th Cong. 
H. Doc. 842, 76th Cong.; 
P.L. 77-228 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
r

TABLE 27-B (Continued) 
See Section Date of 
in Text Act 
May 17, 1950 
Sep. 3, 1954 
May 2, 1956 
Jul. 3, 1958 
Jul. 14, 1960 
Dec. 30, 1963 
Jun. 18, 1965 
May 12, 1967 
Aug. 13, 1968 
Dec. 24, 1970 
Dec. 23, 1971 
Mar. 7, 1974 
16. Jun. 28, 1938 
Dec. 22, 1944 
Sep. 3, 1954 
17. 
18. 
19. 
Sep. 3, 1954 
Sep. 3, 1954 
Oct. 27, 1965 
KANSAS CITY, MO., DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
Additional expenditure of $250 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
Modified general comprehensive plan for Missouri 
River Basin by deletion of construction of Red 
Willow Dam and Reservoir, NE, and addition of 
construction of Wilson Dam and Reservoir, KS. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Additional expenditure of $207 million for prosecution 
of general comprehensive plan for Missouri River 
Basin. 
Additional expenditure of $80 million for prosecution 
of general comprehensive plan for Missouri River 
Basin and modified plan to include bank protection 
or rectification works below Garrison Dam. 
Additional $116 million for prosecution on general 
comprehensive plan for Missouri River Basin. 
Additional $20 million for prosecution of general 
comprehensive plan for Missouri River Basin. 
Additional $38,000,000 for prosecution of general 
comprehensive plan for Missouri River Basin. 
Change comprehensive plan name to Pick-Sloan 
Missouri River Basin program. 
Additional $101,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri 
Basin Program. 
Additional $72,000,000 for prosecution of general 
comprehensive plan for Pick-Sloan Missouri 
Basin Program. 
POMME DE TERRE LAKE, POMME DE TERRE 
RIVER, MO 
Adopted general comprehensive plan for Missouri 
River Basin and authorized $9 million for initiation 
and partial accomplishment. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $200 million additional 
expenditure. 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,000,000 additional 
expenditure. 
POMONA LAKE, ONE HUNDRED TEN MILE 
CREEK, KS 
Expanded general comprehensive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure. 
RATHBUN LAKE, CHARITON RIVER, IA 
Expanded general comprehenssive plan for Missouri 
River Basin and authorized $217,710,000 additional 
expenditure 
SMITHVILLE LAKE, LITTLE PLATTE 
RIVER, MO 
The project for flood protection on the Platte River 
and tributaries, MO and IA, is authorized at an 
estimated cost of $26,889,000. 
27-15 
Documents 
H. Docs. 642 and 549k 
83rd Cong. 
H. Doc. 409, 84th Cong. 
S. Doc. 91-1100, 91st Cong. 
S. Doc. 92-222, 92nd Cong. 
Flood Control Committee 
Doc. 1, 75th Cong., 
PL. 761. 
H. Doc. 475 and S. Does. 
191 and 247, 78th Cong., 
P.L. 534. 
H. Does. 642, 5491 and 561, 
83rd Cong., P.L. 780. 
H. Doc. 5491 561, 83rd 
Cong., P.L. 780. 
H. Doc. 561, 83rd Cong., 
PL. 780. 
1965 Flood Control Act, 
P.L. 89-298 (H. Doc. 262, 
89th Cong.)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 27-B (Continued) AUTHORIZING LEGISLATION 
See Section Date of 
in Text Act Project and Work Authorized Documents 
TUTTLE CREEK LAKE, BIG BLUE RIVER, KS 
20. Jun. 28, 1938 Adopted general comprehensive plan for Missouri Flood Control Committee 
River Basin and authorized $9 million for initiatiion Doc. 1, 75th Cong., 
and partial accomplishment. P.L. 761. 
Aug. 18, 1941 Modified general comprehensive plan to include Harlan H. Doc. 842, 76th Cong.; 
County Dam and Reservoir on Republican River, P.L. 77-228. 
NE, other supplemental flood control works on 
upper Republican River, and authorized $7 million 
additional expenditure. 
Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Does. 
River Basin and authorized $200 million additional 191 & 247, 78th Cong., 
expenditure. P.L. 534. 
WILSON LAKE, SALINE RIVER, KS 
21. Dec. 22, 1944 Expanded general comprehensive plan for Missouri H. Doc. 475 and S. Does. 
River Basin and authorized $200 million additional 191 & 247, 78th Cong., 
expenditure. P.L. 534. 
Jul. 14, 19602 Additional expenditure of $207 million for prosecution S. Doc. 96, 86th Cong., 
of general comprehensive plan for Missouri River P.L. 645. 
Basin. 
HARRY S. TRUMAN DAM AND RESERVOIR, 
OSAGE RIVER, MO 
26. Sep. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 549 , 83rd Cong., 
River Basin and authorized $217,710,000 additional P.L. 780. 
expenditure. 
Oct. 23, 1962 The Kaysinger Bluff Reservoir is hereby modified in 1962 Flood Control Act, 
accordance with recommendations of the Chief of H. Doc. 578, 87th Cong., 
Engineers in H. Doc. 578, 87th Cong., at an P.L. 87-874. 
estimated additional cost of $43,245,000; provided, 
that nothing in this Act shall be construed as 
authorizing the acquisition of additional lands for 
the establishment of a national wildlife refuge at 
the reservoir. 
STOCKTON LAKE, SAC RIVER, MO 
27. Sep. 3, 1954 Expanded general comprehensive plan for Missouri H. Doc. 549 , 83rd Cong., 
River Basin and authorized $217,710,000 additional P.L. 780. 
expenditure. 
1. Contains latest published maps of Missouri River. 2. Report of Chief of Engineers on justification of Wilson Dam 
and Reservoir, submitted in compliance with Public Law 505, 
84th Congress, published as Senate Document 96, 86th Congress, 
was approved July 14, 1960 (Public Law 645). 
TABLE 27-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last' Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Fort Leavenworth Bridge removal Complete 1965 270,393 - 
Gasconade River, MO '1, 2 Complete 1931 139,003 85,077 
Osage River, MO, lock and dam3 Complete 1952 658,076 850,495 
1. Improvement adequate for existing needs. Project for 
maintenance only. Curtailment of project in H. Doc. 467, 69th 
Cong. 
2. Inactive portion of project deauthorized Jan. 1, 1990 in 
accordance with Section 1001(b)(1) of Water Resources Development 
Act (WRDA) of 1986 (P.L. 99-662). 
3. Operation of lock and dam placed in standby status in July 
1952; deauthorized on Jan. 1, 1990 in accordance with Section 
1001(b)(1) of WRDA (P.L. 99-662). 
27-16

KANSAS CITY, MO., DISTRICT 
TABLE 27-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Abilene, KS 
Atchison, KS 
Barnard, KS' 
Bartley, NE 
Bedford, East Fork, 102 River, IA' 
Big Blue River, Seward, NE' 
Big Stranger Creek, KS' 
Braymer Lake, Shoal Creek, MO2 
Brookfield Lake, Yellow Creek, MO2 
Chariton-Little Chariton Basin, MO (1965 Act)3 
Chariton River, MO (1944 Act) 
East Muddy Creek, MO2 
Elk Creek, Clyde, KS' 
Fairbury, Little Blue River, NE 
Fort Scott Lake, Marmaton River, KS 
Frankfort, Black Vermillion River, KS 
Gypsum, Gypsum Creek, KS' 
Harry S. Truman Dam and Reservoir, MO 
(Downstream Fish and Wildlife Mitigation) 
Indianola, NE 
Kansas City, Kansas River, KS (62 Mod) 
Kansas Citys on MO and KS Rivers, 
MO and KS4 
Lawrence, Kansas River, KS5 
Little Blue River Channel Improvement, 
Little Blue River, MO 
Lower Grand River, MO2 
Manhattan, Kansas River, KS 
Mercer Lake, Weldon River, MO2 
Missouri River at New Haven, MO 
(Sec 212, 1950 Act) 
Osawatomie, Pottawatomie Creek, KS 
Ottawa, Osage (Marais des Cygnes) River, KS 
Pattonsburg Lake, Grand River, MO2 ' 6 
Perry Lake Area (Road Improvements), KS 
Platte River, MO, Channel Improvement 
Rathbun Lake Fish Hatchery 
Salina, Smoky Hill River, KS 
Seward, NE' 
Smithville Channel, Little Platte River, MO 
Stonehouse Creek, Jefferson Co., KS' 
Topeka, Kansas River, KS 
Trenton Lake, Thompson River, MO2 
Trimble Wildlife Area, Smithville Lake, MO 
Upper Grand River, MO2 
1. Authorized by the Chief of Engineers under Section 205, 
Public Law 858, 80th Congress, as amended. 
2. Grand River Basin reconnaissance study (authorized by 
resolution of Committee on Public Works and Transportation, 
U.S. House of Representatives on July 3, 1987) reviewed and 
updated costs for these projects authorized in the Flood Control 
Act of 1965, and found no economically feasible plan. 
3. Inactive units Little Chariton River (East and Middle 
Fork) and Mussell Fork were deauthorized 1 Jan. 1990 by Section 
1001(b)(1) of the Water Resources Development Act of 
1986, P.L. 99-662. Construction cost includes $481,106 cost of 
completed Shoal Creek Unit and $211,600 cost of deauthorized 
Little Chariton River and Mussell Fork units. 
4. Includes $619,787 non-Federal contributions for work 
desired by local interests, but not required under the project. 
The project as a whole is complete except for Turkey Creek 
facilities in Central Industrial District Unit. 
5. Includes $153,377 non-Federal contributions. 
6. Pattonsburg Lake Highway Relocation and Town 
Relocation portions of the project were deauthorized 1 Jan. 1990 
in accordance with Section 1001(b)(1) of the Water Resources 
Development Act of 1986, P.L. 99-662. 
27-17 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Inactive 
Completed 
Completed 
Completed 
Inactive 
Completed 
Deferred 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Inactive 
Completed 
Inactive 
1965 
1973 
1953 
1974 
1966 
1976 
1977 
1973 
1966 
1984 
1973 
1976 
1966 
1984 
1950 
1984 
1980 
1985 
1989 
1966 
1967 
1976 
1973 
1966 
1976 
1982 
1973 
1975 
1967 
1973 
1972 
1974 
1966 
1990 
1966 
1,099,350 
4,099,590 
127,860 
118,269 
652,414 
126,887 
337,131 
451,400 
692,7063 
8,052,990 
989,015 
726,966 
757,500 
1,271,025 
2,782,793 
67,275 
25,010,500 
42,434,197 
8,773,488 
25,530,083 
2,488,585 
432,245 
139,883 
2,036,624 
4,462,661 
5,315,168 
222,193 
700,000 
3,878,668 
126,887 
6,896 
246,995 
21,174,593 
1,570,000

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 27-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds Date 
Project Report For Date and Authority Expended Expended Deauthorized 
Arlington Lake, MO 1948 Flood Control Act approved June 28, $8,651 - Aug. 5, 1977 
Beatrice, Big Blue River, NE 
Chariton-Little Chariton Basin, 
MO (1965 Act) - Inactive 
Units Little Chariton River 
(East and Middle Fork) and 
Mussell Fork Units only 1 
Dry Fork and East Fork 
Lakes, Fishing River, MO 
Garnett Lake, Pottawatomie 
Creek, KS 
Grove Lake, Soldier Creek, KS 
Hackleman Corners Lake, 
Cedar Creek, MO 
Hays, Big Creek, KS2 
Indian Lake, Blue River, KS 
Kansas River Navigation 
Marysville, KS 
Melvern Lake and Pomona 
Lake (Road Improvements) 
KS (1974 Act) 
Merriam, Turkey Creek, KS 
Mill Lake, Blue River, MO 
Missouri River Levee System, 
IA, KS, MO, and NE 
Deauthorized by Section 1002 
Water Resources Development 
Act of 1986, P.L. 99-662, 
Section 1002: Units R402; 
R393-395; and R414 
Deauthorized in accordance 
with WRDA Section 1001(b)(1): 
Units L36; R42; L51; R55-59-61; 
L68-92; R70; L78; R87; L94; 
L99; L103; R104; R107; R112; 
L117; L121; L124; L129; L134; 
L137-139; L145; R150; L154; 
L157; R161; L164; R169; L175; 
R179-184; L191-196; L205; 
L217; R226; R240; R251; 
L256; R259; R263-270; R272; 
R284; R302; R336; L353; L357; 
R361; L362; L392; L419-426; 
L435; R512-513, Section III 
Ona a Lake, Vermillion Creek, 
Pattonsburg Lake, Grand River, 
MO3 
I-35 Highway Relocation 
Town Relocation 
Pioneer Lake, KS 
1938, as modified by Flood Control 
Act approved August 18, 1941, and 
expanded by Flood Control Act 
approved December 22, 1944 
Flood Control Act approved 
September 3, 1954 
1965 Flood Control Act P.L. 89-298 
(H. Doc. 238, 89th Cong., 1st sess.) 
1974 1965 Flood Control Act P.L. 89-298 
(H. Doc. 281, 89th Cong., 1st sess.) 
1973 Flood Control Act approved 
September 3, 1954 
1977 1962 Flood Control Act (S. Doc. 122, 
87th Cong. 2d sess.) 
- Authorized by Flood Control Act 
approved September 3, 1954 
1974 Flood Control Act of 1965 approved 
October 27, 1965 
1976 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.) 
1980 1965 Flood Control Act, P.L. 89-298, 
Sec. 201 
- Flood Control Act of September 3, 
1954 
- Water Resources Development Act 
of 1974, Section 17 
1970 Flood Control Act approved 
September 3, 1954 
1971 1970 Flood Control Act (H. Doc. 
332, 91st Cong., 2d sess.) 
- Flood Control Act of August 18, 
1941, P.L. 228, 77th Cong. 
- Flood Control Act of August 18, 
1941, P.L. 228, 77th Cong. 
Flood Control Act of 1962, 
October 23, 1962 (P.L. 87-874) 
1976 1965 Flood Control Act, P.L. 89-298 
1976 (H. Doc. 241, 89th Cong., 1st sess.) 
1952 Flood Control Act approved June 28, 
1938, as modified by Flood Control 
Act of August 18, 1941, and 
expanded by Flood Control Act 
approved December 22, 1944 
1965 
1977 
- May 6, 1981 
- Jan. 1, 1990 
- Jan. 1, 1990 
- Nov. 17, 1986 
- Nov. 17, 1986 
- Aug. 5, 1977 
Jan. 18, 1978 
16,317 
211,600 
51,989 
71,466 
1,754,019 
499,200 
127,297 
259,900 
133,682 
39,708 
57,500 
1,631,700 
2,178,261 
393,623 
91,929 
95,692 
27-18 
- Nov. 17, 1986 
- Nov. 17, 1986 
- Jan. 1967 
- Jan. 1, 1990 
- Nov. 27, 1973 
- Nov. 17, 1986 
- Nov. 17, 1986 
- Jan. 1, 1990 
- Nov. 17, 1986 
- Jan. 1, 1990 
- Jan. 1, 1990 
- Aug. 5, 1977

TABLE 27-G (Continued) 
KANSAS CITY, MO., DISTRICT 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Funds Funds Date 
Project Report For Date and Authority Expended Expended Deauthorized 
Pomme de Terre Lake 1954- Flood Control Act of 1954 - - Nov. 17, 1986 
(Power Addition), MO 1974 (H. Doc. 549, 81st Cong., 2d sess.) 
Richland Lake, MO 1948 Flood Control Act approved June 28, 8,548 - Aug. 5, 1977 
1938, as modified by Flood Control 
Act approved August 18, 1941, 
and expanded by Flood Control 
Act approved December 2, 1944 
Tomahawk Lake, 1976 1970 Flood Control Act (H. Doc. 77,189 - Nov. 17, 1986 
Blue River, KS 332, 91st Cong., 2d sess.) 
Tuttle Creek Lake, KS (Road 1977 Sec. 18 of Water Resources 3,000 - Nov. 17, 1986 
Improvement - 1974 Mod.) Development Act of 1974 
Tuttle Creek Lake, KS - Water Resources Development Act - - Jan. 1, 1990 
Road and Bridge (1976 Act) of 1976, Section 189, P.L. 94-587 
Wolf-Coffee Lake, Blue River, 1976 1970 Flood Control Act (H. Doc. 1,095,020 - Nov. 17, 1986 
KS 332, 91st Cong., 2d sess.) 
1. For completed Shoal Creek unit of Chariton-Little 3. Pattonsburg Lake portion of project is inactive. See 
Chariton Basin, MO, see Table 27-E. Table 27-E. 
2. Hays, Lincoln Draw, KS, Section 205 feasibility study 
terminated in March 1991 due to lack of identifiable project that 
would meet dam safety concerns. 
TABLE 27-H MISSOURI RIVER LEVEE SYSTEM 
(See Section 13 of Text) 
Miles of 
Unit Levee Status 
R512-513 Richardson Co. Drainage Dist #7' 19.1 Complete-1958 
R500 Iowa Point Drainage Dist #4 4.1 Complete-1954 
Kimsey Holly Creek 4.4 Complete-1970 
L497 Forest City Levee Dist 16.0 Complete-1962 
L488 Holt Co. Drainage Dist #7 11.5 Complete-1955 
R482 Burr Oak Drainage Dist #3 8.2 Complete-1954 
L476 Amazonia Levee Dist 10.8 Complete--1956 
R460-471 Elwood-Gladden Levee Dist 13.8 Complete-1968 
L455 S. St. Joseph Levee Dist 15.6 Complete-1967 
L443-448 Halls Levee Dist 17.3 Complete- 1957 
R440 Atchison & Doniphan Co. Drainage Dist 10.7 Complete-1959 
L408 Farley-Beverly Drainage Dist 12.2 Complete (Levee raise modification)-1972 
L400 Waldron Levee Dist 7.6 Complete-1957 
R351 Atherton Levee Dist 15.9 Complete-1966 
L246 Brunswick-Dalton Drainage Dist 20.0 Complete-1983 (Restudy initiated Feb 92) 
434.5 Atchison, KS, Railroad Bridge Inactive 
408.2 Leavenworth, KS, Railroad Bridge Inactive 
R331 Inactive 
L330-345 Orrick Levee Dist 43.4 Inactive 
R328 Inactive 
L319-325 Henrietta-Crooked River Drainage Dist 35.0 Inactive 
L100 Inactive 
R30 Inactive 
L15 North County Levee Dist 40.0 Inactive 
L504-512-519 Deferred 
L294 Wakenda Creek Area Deferred 
L385 Riverside-Quindaro Drainage Dist 6.5 Recommended for new construction start FY 94 
L142 Jefferson City, MO Reclassified to Active May 91, planning continues 
Remaining units Detailed planning not initiated 
1. Section III of R512-513 was not constructed and was 
deauthorized Jan. 1, 1990. 
27-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 27-I KANSAS CITY DISTRICT PROJECTS INCLUDED IN 
PICK-SLOAN MISSOURI BASIN PROGRAM 
(See Section 15 of Text) 
Project 
Abilene, Smoky Hill River, KS 
Bartley, Republican River, NE 
Fort Scott Lake, Marmaton River, KS' 
Garnett Lake, Pottawatomie Creek, KS" 
Harlan County Lake, Republican River, NE 
Harry S. Truman Dam and Reservoir, Osage River, MO 
Hillsdale Lake, Big Bull Creek, KS 
Indianola, Republican River, NE 
Kanopolis Lake, Smoky Hill River, KS 
Lawrence, Kansas River, KS 
Manhattan, Kansas River, KS 
Melvern Lake, Osage (Marais des Cygnes) River, KS 
Melvern Lake and Pomona Lake (Road Improvement). 
KS (1974 Authorization)4 
Milford Lake, Republican River, KS 
Missouri River Levee System, Rulo to the Mouth " 
Osawatomie, Osage (Marais des Cygnes) River, KS 
Ottawa, Osage (Marais des Cygnes) River, KS 
Perry Lake, Delaware River, KS 
Pomme de Terre Lake, Pomme de Terre River, MO 
Pomona Lake, Osage River Basin, KS 
Salina, Smoky Hill River, KS 
Stockton Lake, Sac River, MO 
Topeka, Kansas River, KS 
Tuttle Creek Lake, Big Blue River, KS 
Tuttle Creek Lake, KS-Road and Bridge (1976 Act)' 
Tuttle Creek Lake (Road Improvement), KS (1974 Modification) ' 
Wilson Lake, Saline River, KS 
$1,099,350 
118,269 
90,500,000 
71,466' 
48,129,549 
548,700,000 
64,161,400 
67,275 
12,577,227 
8,620,111 
2,488,585 
37,436,530 
500,000 
49,566,492 
85,389,000 
2,036,624 
4,462,661 
49,095,918 
17,365,453 
14,003,238 
3,878,668 
79,975,357 
21,174,593 
80,584,079 
630,000 
500,000 
20,463,367 
1. Inactive. 
2. Deauthorized by Water Resources Development Act of 
1986, P.L. 99-662 (See Table 27-G). 
3. Total Federal funds expended. 
4. Deauthorized Jan. 1, 1990. in accordance with WRDA 
of 1986, Section 1001(b)(1). 
TABLE 27-J INSPECTION C 
5. Active portion of project. Deferred portion of project is 
currently estimated to cost (1992) $46,753,000 Federal and 
$4,336,000 non-Federal. Inactive portion of project is currently 
estimated to cost (1990) $182,791,000 Federal and 
$19,690,000 non-Federal. Actual cost of deauthorized units 
(1990) is $1,689,000 Federal. 
)F COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 23 of Text) 
Missouri River Main Stem 
Missouri River Levees: R512-513, R500, Kimsey Holly Creek, L497, L488, 
R482, L476, R460-471, L455, L443-448, R440, L408, L400 and R351, L246 
Kansas Citys, Missouri and Kansas: Argentine, Armourdale, 
Birmingham, CID (Mo & Kans), East Bottoms, Fairfax-Jersey 
Creek, North Kansas City Units, and GSA Federal Complex 
Osage River, Kansas and Missouri 
Ottawa, Kansas 
Osawatomie, Kansas 
Kansas River and Minor Tributaries 
Topeka, Kansas; Auburndale, North Topeka, Oakland, Soldier 
Creek, South Topeka, and Waterworks Units 
Republican River, Nebraska and Kansas 
Bartley, Nebraska 
Smoky Hill, Saline, and Solomon Rivers 
Abilene, Kansas 
27-20 
Estimated 
Federal 
Cost 
Estimated 
Non-Federal 
Cost 
$287,000 
9,500 
44,800,000 
138,385,000 
23,342,756 
7,592 
2,130,000 
265,000 
214,300 
20,412,000 
348,300 
876,000 
1,960,000 
17,458,000 
10,383,492 
610,000 
214,300 
Location Month Inspected 
Mar/Sep 92 
May/Sep 92 
Mar/Sep 92 
Mar/Sep 92 
Mar/Sep 92 
Mar/Oct 92 
Mar/Oct 92

TABLE 27-K 
KANSAS CITY, MO., DISTRICT 
ACTIVE GENERAL INVESTIGATIONS 
(See Section 28 of Text) 
Item and CWIS Number 
SURVEYS (Category 100) 
Flood Damage Prevention Studies (120) 
Blue River Basin, Kansas City, MO - 12563 
Dry Fork and East Fork, Fishing River, MO - 12815 
Marysville, KS - 12820 
Turkey Creek Basin, KS & MO - 12381 
Subtotal 
Special Studies (140) 
Ft. Leonard Wood Solid Waste Mgmt - 14149 
Kansas Water Supply - 14149 
Subtotal 
Review of Authorized Projects (160) 
MRLS, Unit L246, Cutoff Lake, MO - 53899 
Miscellaneous Activities (170) 
Special Investigations - 17250 
FERC Licensing Activities - 53857 
Dam Safety Criteria Studies 
North American Waterfowl Mgmt - 53904 
Subtotal 
Coordinate Studies with Other Agencies (180) 
Soil Conservation Service, Dept. Agric. (181) - 51840 
Bureau of Reclamation, Dept. Interior (182) - 51820 
Regional Planning (183) - 53847 
Cooperation with States (186) 
Negotiation Funds, KS - 14800 
Negotiation Funds, MO- 14880 
Planning Assistance to States, MO Wetlands Inventory - 29001 
Planning Assistance to States, Kansas - 14820 
Subtotal 
TOTAL (Category 100) 
COLLECTION AND STUDY OF BASIC DATA (Category 200) 
Flood Plain Management Services (250) 
Flood Plain Management Service Unit - 82030 
Overland Park, KS - 83020 
Quick Responses - 82045 
Special Studies - Kansas City, MO - 83010 
Technical Services, General - 82040 
Hydrology Studies (260) 
Hydrology Studies - 53820 
TOTAL (Category 200) 
PRECONSTRUCTION ENGINEERING AND DESIGN 
(Category 600) 
Navigation Projects (620) 
Missouri River Fish & Wildlife Mitigation (621) - 14105 
TOTAL (Category 600) 
GRAND TOTAL GENERAL INVESTIGATIONS 
27-21 
Federal Cost 
FY 92 
Totals By 
Categories 
$39,000 
54,395 
35,289 
319,000 
$447,684 
$9,073 
8,685 
$17,758 
$132,055 
$80,000 
5,000 
8,000 
20,049 
$113,049 
$5,624 
14,000 
14,000 
5,488 
5,283 
904 
1,413 
$46,712 
$757,258 
$30,000 
20,382 
7,454 
31,338 
81,209 
22,000 
$192,383 
$10,746 
$10,746 
$960,387

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 27-L FLOOD CONTROL ACTIVITIES 
UNDER SPECIAL AUTHORIZATION 
(See Section 25 of Text) 
Fiscal 
Year 
Study Status' Cost 
Flood Control Activities Pursuant to Section 205, Public Law 858, 
80th Congress, as Amended 
Mill Creek, Olathe, KS R $42,649 
Blackwater River and Davis Creek, Sweet Springs, MO R 31,756 
Eureka Valley Tributary of Seven-Mile Creek, Manhattan/Riley County, KS R 25,920 
Cross Creek, Rossville, KS P 439,354 
Blue River Basin, Overland Park, KS C 531,094 
TOTAL FOR 5 ACTIVE PROJECTS: $1,070,773 
1 Section 205 study (terminated in FY 1991), financially completed 722 
TOTAL ALL PROJECTS $1,071,495 
Emergency Streambank Protection - Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Congress 
July 24, 1946, as Amended 
Little Blue River, Washington County, KS, Spence Bridge O $1,376 
Little Blue River, Washington County, KS, County Road O 1,594 
Little Blue River, Thayer County, NE, Gilead North Bridge 0 1,324 
Big Blue River, Blue Springs, NE, Sewerline and Road 0 1,045 
102 River, Nodaway County, MO, South Pickering Bridge 0 14,201 
Tributary of Kill Creek, DeSoto, KS, Sewage Treatment Plant 0 26,009 
Republican River, Clifton, KS, Sewage Lagoons 0 90,151 
Rock Creek, Pottawatomie County, KS, County Bridge P 3,301 
West Nodaway River, Page 1 Rural Water District, Clarinda, IA P 7,133 
West Fork Grand River, MO Highway and Transportation Dept., Route 46A P 15,366 
Hinkson Creek, Columbia, MO, Sewerline F 9,048 
Blackwater River Tributary, Warrensburg, MO, 10-Inch Sewerline F 1,675 
Blackwater River Tributary, Warrensburg, MO, 15-Inch Sewerline F 1,202 
Blue River, Gregory Boulevard, Kansas City, MO F 9,653 
Bear Creek, Warrensburg, MO, 24-Inch Sewerline F 3,140 
Bear Creek, Warrensburg, MO, 27-Inch Sewerline F 2,971 
West Fork Grand River, Worth County, MO, County Road and Bridge F 1,206 
Grand River, Brunswick Levee District, MO, Levee F 530 
TOTAL FOR 18 ACTIVE PROJECTS: $190,925 
5 Section 14 studies were terminated in FY 1992. total 8,981 
TOTAL ALL PROJECTS $199,906 
Emergency Flood Control Activities - Repair, Flood 
Fighting, and Rescue Work - Public Law 99 
84th Congress and Antecedent Legislation 
FLOOD CONTROL AND COASTAL EMERGENCIES (Appropriation 96X3125) 
Disaster Preparedness Program - 100 
Corps Statutory Activities $166,841 
Activities in Support of Others 123,355 
Facilities 143,350 
Inspections 181,956 
Total Disaster Preparedness Program $615,502 
Emergency Operations - 200 0 
Rehabilitation- 300 
Federal Flood Control Works $33,136 
Non-Federal Flood Control Works -1,827 
Total Rehabilitation $31,309 
TOTAL ALL ACTIVITIES $646,811 
1. Status: R = Recon; F = Feasibility; P = P&S: C = Construction; O = Operational 
27-22

LITTLE ROCK, ARKANSAS DISTRICT* 
The civil works portion of this District covers an area of 
approximately 36,414 square miles in northern, western, 
and southwestern Arkansas and a portion of Missouri within 
the Arkansas River, Little River, and White River basins. In 
Arkansas River Basin, the District is responsible for those 
areas embraced in the drainage basin of the Arkansas River 
and its tributaries above and exclusive of Pine Bluff, AR, and 
below the mouth of the Poteau River, near Fort Smith, AR. 
The District has responsibility for planning, design, construction, 
and operation and maintenance of the navigation 
portion of the McClellan-Kerr Arkansas River Navigation 
System in the State of Arkansas (including that portion 
below Pine Bluff). In Little River Basin, the District is 
responsible for those portions of the drainage basin of the 
Arkansas portion of Little River and its tributaries above its 
mouth near Fulton, AR. In White River Basin, the District 
is responsible for those portions in southern Missouri and 
northern and eastern Arkansas embraced in the White River 
drainage basin and its tributaries above Peach Orchard Bluff, 
AR. The Memphis District is responsible for navigation 
maintenance on the White River below Newport, AR, to the 
mouth of Wild Goose Bayou, in Arkansas County, AR. The 
White River downstream from the mouth of Wild Goose 
Bayou is part of the McClellan-Kerr Arkansas River Navigation 
System. 
IMPROVEMENTS 
Navigation 
1. AR River Basin, AR, OK, and KS .................... 28-2 
2. Arthur V. Ormond Lock and Dam (No.9), AR ...... 28-2 
3. Bank Stabilization & Channel Rectification, AR ... 28-3 
4. David D. Terry Lock and Dam (No.6), AR ........... 28-3 
5. Emmett Sanders Lock and Dam (No.4) ........... 28-3 
6. James W. Trimble Lock and Dam (No.13) .......... 28-3 
7. Lock No. 2 and Wilbur D. Mills Dam (No.2), AR.. 28-3 
8. Joe Hardin Lock and Dam (No.3), AR ................ 28-4 
9. Lock and Dam No.5, AR ................................. 28-4 
10. Maintenance and Repair Fleet and Marine 
Terminals, AR ........................................ 28-4 
11. Murray Lock and Dam (No.7), AR ...................... 28-4 
12. Navigation Work Under Special Authorization ..... 28-4 
13. Norrell Lock and Dam (No.1) and Entrance 
Channel, AR ............ ........................ 28-4 
14. Other Authorized Navigation Projects ........ 28-4 
15. Toad Suck Ferry Lock and Dam (No.8), AR........ 28-4 
Flood Control 
16. Black River Obstruction Removal, 
Butler Co., MO ........................................ .. 28-5 
17. Blue Mountain Lake, AR ................................. 28-5 
18. Clearwater Lake, MO ................................... .. 28-5 
19. DeQueen Lake, AR ........................................ 28-6 
20. Dierks Lake, AR ..................................... 28-6 
21. Flood Control Work Under Special 
Authorization ..................................... 28-6 
22. Fourche Bayou Basin, Little Rock, AR ............ 28-6 
23. Gillham Lake, AR ........................................... 28-7 
24. Inspection of Completed Flood 
Control Projects ..................................... 28-7 
25. Little Red River and Tributaries, Clinton, AR ...... 28-7 
26. Little River Basin, AR ..................................... 28-7 
27. Mill Creek, Fort Smith, AR .............................. 28-7 
28. 
29. 
30. 
31. 
32. 
33. 
34. 
35. 
M illwood Lake, AR ............................................... 28-8 
Nimrod Lake, AR .................. .............. ..28-8 
Other Authorized Flood Control Projects...............28-8 
Petit Jean River, Highway 309, AR......................28-8 
Red River, 1-30, Little River Co., AR......................28-9 
Red River, Hwy 71, Little River Co., AR................28-9 
White River Basin (Little Rock Dist, AR & MO)......28-9 
White River, Batesville, AR ............................... 28-10 
Multiple-Purpose Projects Including Power 
36. Beaver Lake, AR .............................................. 28-10 
37. Bull Shoals Lake, AR ..................................... 28-10 
38. Dardanelle Lock and Dam (No.10), AR................. 28-11 
39. Greers Ferry Lake, AR...................................... 28-11 
40. Norfork Lake, AR ..................................... 28-12 
41. Ozark-Jeta Taylor Lock and Dam (No.13), AR ...28-12 
42. Table Rock Lake, MO ................................... 28-12 
General Investigations 
43. Surveys ..................................... 28-13 
44. Collection and Study of Basic Data ................ 28-13 
Tables 
Table 28-A, Cost and Financial Statement................... 28-14 
Table 28-B, Authorizing Legislation............................ 28-18 
Table 28-C, Other Authorized Navigation Projects....... 28-21 
Table 28-E, Other Authorized Flood 
Control Projects................................ 28-22 
Table 28-G, Deauthorized Projects............................ 28-23 
Table 28-H, Arkansas River Basin; AR, OK, and KS: 
Navigation............................ 28-24 
Table 28-1, Arkansas River Basin; AR, OK, and KS: 
Lakes.............................. 28-28 
Table 28-J, Little River Basin, AR: Lakes ................. 28-29 
Table 28-K, White River Basin, AR & Mo: Lakes......... 28-30 
28-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. ARKANSAS RIVER BASIN, AR, OK, AND KS 
Location. Arkansas River rises in Rocky Mountains near 
Leadville, CO, and flows southeastward 1,396 miles through 
Colorado, Kansas, Oklahoma, and Arkansas to join Mississippi 
River 599 miles above Head of Passes, LA. (See 
Geological Survey state maps, 1:24,000, and flood control 
and navigation maps of Mississippi River, Cairo, IL, to Gulf 
of Mexico, 1970 edition scale 1:62,500.) 
Previous projects. For details see page 1066, Annual 
Report for 1932, and pages 744, 864, and 881, Annual Report 
for 1943. 
Existing project. Provides for improvement of Arkansas 
River Basin by construction of coordinated developments for 
navigation, hydroelectric power, flood control, water supply, 
sediment control, recreation, and fish and wildlife propagation. 
McClellan-Kerr Arkansas River Navigation System 
provides a channel 9 feet deep and 444.8 miles long, beginning 
at mouth of WhiteRiver, which enters Mississippi River 
599 miles above Head of Passes, LA, thence 9.8 miles 
upstream to mouth of Wild Goose Bayou; thence 9.2 miles by 
a land cut, designated as Arkansas Post Canal to mile 42 
(1943 survey) on Arkansas River; thence 376.0 miles along 
channel of latter stream to mouth of Verdigris River at 
navigation mile 395.0; thence 49.8 miles up Verdigris River 
to head of navigation at Catoosa, OK. 
The waterway is canalized throughout its length by 17 
locks and dams with total lift of 420 feet. Dardanelle, Ozark- 
Jeta Taylor, Robert S. Kerr, and Webbers Falls are multiplepurpose 
projects including power. Lock chambers are 110 by 
600 feet. A minimum channel width of 150 feet is provided 
for Verdigris River, 225 feet for San Bois Creek, 250 feet for 
Arkansas River, and 300 feet for Arkansas Post Canal and 
White River Entrance Channel. 
Other coordinated developments consist of 15 lakes, of 
which 13 are in Tulsa District, Kansas and Oklahoma, and 
two in Little Rock District. Pertinent data and estimated 
Federal cost are summarized in tables 28-H and 28-I, Arkansas 
River Basin; AR, OK, and KS: Navigation and Arkansas 
River Basin; AR, OK, and KS: Lakes,respectively. See table 
28-B for authorizing legislation.) 
Local cooperation. For McClellan-Kerr Arkansas River 
Navigation System, local interests must provide adequate 
terminal and transfer facilities and bear the increased costs 
of maintenance and operation of all altered rail and highway 
routes, including bridges and appurtenances, utilities, and 
other existing improvements, other than federally owned. 
For lakes see requirements for each individual lake. 
Terminal facilities. Public port facilities are in operation 
at Pine Bluff (Jefferson County), Little Rock, and Fort Smith, 
AR, and Muskogee and Catoosa (Tulsa-Rogers County), 
OK. Port authorities have been organized to develop public 
facilities at North Little Rock, Dardanelle-Russellville, 
Morrilton, Clarksville, Ozark, and Van Buren, AR, and 
Sallisaw, OK. Terminal facilities are in operation or being 
built at 35 locations in Arkansas and at 25 locations in 
Oklahoma along the improved waterways. 
Operations and results during fiscal year. Continued 
operation and maintenance. (See tables 28-H and 28-I for 
navigation and lake listings.) For details of McClellan-Kerr 
Arkansas River Navigation System and lakes in Oklahoma 
and Kansas, see the Tulsa District report. Flood damages 
prevented by Little Rock District projects in the Arkansas 
River Basin during FY 92 are estimated at $6,574,180; flood 
losses prevented through FY 92 are estimated $478,354,680. 
Projections on navigation activities in calendar year 1992 
indicated that about 9.2 million tons of commerce were to be 
moved on the Arkansas portion of the McClellan-Kerr 
Arkansas River Navigation System. This represents about 
the same level of activity reported for calendar year 1991. 
Details of the McClellan-Kerr Arkansas River Navigation 
System and lakes in Arkansas are shown on the following 
pages. 
Condition at end of fiscal year. (See tables 28-H and 28- 
I, Arkansas River Basin; AR, OK, and KS: Navigation/ 
Lakes, respectively, for status for individual items, navigation 
project, lakes, and basin plan.) Work continues on the 
Arkansas River project in this District including construction 
of a meander cutoff levee between the Arkansas and 
White Rivers, extension of the stilling basin at Wilbur D. 
Mills Dam (No. 2) and land acquisition studies. 
Tow haulage equipment has been added to David D. Terry 
Lock and Dam (No. 6), Lock and Dam No. 5, Emmett 
Sanders Lock and Dam (No. 4), and Joe Hardin Lock and 
Dam (No. 3); this equipment will be operational in June 
1993. The project design for the low-stage water problem on 
the White River at Montgomery Point is in progress. 
2. ARTHUR V. ORMOND LOCK & DAM 
(NO. 9), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Continued 
operation and maintenance. Construction of a non-Federal 
hydropower project, under the authority provided by the 
Federal Energy Regulatory Commission, is scheduled to be 
placed into operation by August 1993 with overall completion 
scheduled for May 1994. Rockefeller Lake (pool 9) has 
four developed parks which in FY 92 experienced public 
visitation exceeding 3.1 million visitor-hours that resulted in 
$10,000 fee revenue. 
28-2

LITTLE ROCK, AR DISTRICT 
Condition at end of fiscal year. Construction began in 
April 1965 and lock and dam was placed in operation in 
July 1969. Construction of Holla Bend closure structure 
(fish and wildlife mitigation) began in July 1986 and was 
completed in September 1987. 
3. McCLELLAN-KERR ARKANSAS RIVER 
NAVIGATION SYSTEM, BANK STABILIZATION & 
CHANNEL RECTIFICATION, AR 
Location. Several bank stabilization and channel rectification 
projects are laid out in various reaches extending from 
fixed point to fixed point on Arkansas River from 33.7 to 362 
miles above mouth and across the Arkansas-White cutoff, a 
4- to 5-mile natural channel joining Arkansas and White 
rivers about 18 and 12 miles above their respective mouths. 
Existing project. Bank stabilization and channel rectification 
is a part of McClellan-Kerr Arkansas River Navigation 
System. For a complete description of reach and location 
of each bank stabilization and channel rectification project, 
see the FY 81 Annual Report. Total Federal cost to date is 
$119,300,184 for existing project in Little Rock District. 
(See table 28-B for authorizing legislation.) 
4. DAVID D. TERRY LOCK AND DAM 
(NO. 6), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Condition at end of fiscal year. Construction began in 
January 1965 and lock and dam project was placed in 
operation in August 1968. Tow haulage equipment has been 
added and will be operational in June 1993. Currently has 
two developed parks which in FY 92 experienced public 
visitation exceeding 3.6 million visitor-hours that resulted in 
$12,300 fee revenue. 
5. EMMETT SANDERS LOCK AND DAM 
(NO. 4), AR 
Location, existing project, local cooperation and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Continued 
operation and maintenance. Pool4 has two developed parks 
which in FY 92 experienced public visitation exceeding 1.3 
million visitor-hours that resulted in $1,800 fee revenue. 
Condition at end of fiscal year. Construction began in 
May 1964 and lock and dam project was placed in operation 
in December 1968. Construction of a 40-foot wide, 9,600 
long highway bridge crossing the lock and dam began 
February 1992 and is scheduled for completion in October 
1993. The Corps of Engineers, as the Federal agency, has 
jurisdiction and custody of the dam (23 U.S.C. 320 [Public 
Law 85-67]). The project is 100 percent funded by the 
Arkansas State Highway and Transportation Department 
and the Federal Highway Administration. Tow haulage 
equipment has been added and scheduled to be operational 
in June 1993. 
6. JAMES W. TRIMBLE LOCK AND DAM 
(NO. 13), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Continued 
operation and maintenance. In FY 92, the project's three 
developed parks experienced public visitation exceeding 
3.6 million visitor-hours which resulted in $26,000 fee 
revenue. 
Condition at end of fiscal year. Construction began in 
October 1965 and lock and dam were placed in operation in 
April 1969. Bridge across dam was completed in July 1968. 
Construction of a non-Federal hydropower facility at the 
project was completed in November 1988 under the authority 
provided by the Federal Energy Regulatory Commission. 
7. LOCK NO. 2 AND WILBUR D. MILLS DAM 
(NO. 2), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Operation 
and maintenance continued. Wilbur D. Mills has four developed 
parks which in FY 92 experienced public visitation 
exceeding 4.6 million visitor-hours that resulted in $72,300 
fee revenue. 
Condition at end of fiscal year. Construction began in 
May 1963. Lock was placed in operation in March 1968. 
Emergency repairs to the scour protection features and 
tainter gates at the dam that resulted from a barge accident 
in December 1982 were completed in FY 85. The barges that 
clogged the dam gates during the December 1982 flood 
showed that, with a certain set of circumstances (higher than 
normal head combined with the clogged gates resulted in 
high current velocity that caused both upstream and downstream 
scouring), the structure could fail. This condition 
exists primarily because the structure was constructed on 
piling and designed for all of the gates to operate in unison. 
A model study by the Waterways Experiment Station 
determined the most feasible solution to this problem is to 
extend the stilling basin downstream. A contract to extend 
the stilling basin was awarded in June 1990; completion is 
scheduled for December 1993. Project costs are estimated at 
$21.6 million. 
28-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
8. JOE HARDIN LOCK AND DAM (NO. 3), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Continued 
operation and maintenance. Pool 3 has three developed 
parks which in FY 92 experienced public visitation exceeding 
2.6 million visitor-hours that resulted in $11,000 fee 
revenue. 
Condition at end of fiscal year. Construction began in 
May 1963 and lock and dam were placed in operation in 
December 1968. Tow haulage equipment has been installed 
and will be operational in 1993. 
9. LOCK AND DAM NO. 5, AR 
Location, existing project, local cooperation and terminal 
facilities. (See section 1.) 
Operation and results during fiscal year. Continued 
operation and maintenance. Pool 5 has two developed parks 
which in FY 92 experienced public visitation exceeding 1.2 million 
visitor-hours that resulted in $26,100 fee revenue. 
Condition at end of fiscal year. Construction began in 
November 1964 and lock and dam were placed in operation 
in December 1968. Tow haulage equipment has been added 
and will be operational in June 1993. 
10. MAINTENANCE AND REPAIR FLEET 
AND MARINE TERMINALS, AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Operation 
and maintenance continued. 
Condition at end of fiscal year. Construction of Pine 
Bluff Marine Terminal began March 1968 and was placed in 
operation in April 1969. Construction of Dardanelle Marine 
Terminal began June 1968 and was placed in operation in 
November 1969. 
11. MURRAY LOCK AND DAM (NO. 7), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Operations and results during fiscal year. Operation 
and maintenance continued. Murray has five developed 
parks which in FY 92 experienced public visitation exceeding 
6.4 million visitor-hours that resulted in $132,000 fee 
revenue. 
Condition at end of fiscal year. Construction began in 
November 1964 and lock and dam was placed in operation 
in October 1969. Construction of a non-Federal hydropower 
facility at the project was completed in May 1988 under the 
authority provided by the Federal Energy Regulatory Commission. 
12. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Preauthorization studies under the small project continuing 
authorities program, navigation activities, Section 107, 
Public Law 86-645, as amended. No activity during this 
fiscal year. 
13. NORRELL LOCK AND DAM (NO. 1) 
AND ENTRANCE CHANNEL, AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
Recommended modification. The White River Entrance 
Channel is the first reach in the McClellan-Kerr Arkansas 
River Navigation System project. The water surface elevation 
in the entrance channel is controlled by the elevation of 
the Mississippi River. Feasibility studies were conducted to 
determine a solution to a low-stage water problem. 
The Waterways Experiment Station (WES), Vicksburg, 
MS, conducted a test model which showed that an additional 
lock and dam in the entrance channel would relieve restrictions 
on the navigation system during low flows. WES 
determined that other alternatives tested would not solve the 
low-flow problem. 
Operations and results during fiscal year. Operation 
and maintenance continued. The project currently has one 
developed park which in FY 92 experienced public visitation 
exceeding 130,000 visitor-hours; no fee revenue was 
realized. 
Condition at end of fiscal year. Construction began in 
May 1963, and lock and dam were placed in operation in 
June 1967. 
14. OTHER AUTHORIZED NAVIGATION 
PROJECTS 
(See table 28-C for other authorized navigation projects.) 
15. TOAD SUCK FERRY LOCK AND DAM 
(NO. 8), AR 
Location, existing project, local cooperation, and terminal 
facilities. (See section 1.) 
28-4

LITTLE ROCK, AR DISTRICT 
Operations and results during fiscal year. Continued 
operation and maintenance. In FY 92, the project's 
five developed parks experienced public visitation exceeding 
4.2 million visitor-hours that resulted in $46,000 fee 
revenue. 
Condition at end of fiscal year. Construction began in 
July 1965 and lock and dam was placed in operation in 
November 1969. Conway water supply project was completed 
and transferred to the city for operation and maintenance 
in July 1983. 
Flood Control 
16. BLACK RIVER OBSTRUCTION REMOVAL, 
BUTLER COUNTY, MO 
Location. The project area begins approximately 6 miles 
south of Poplar Bluff, MO, and extends to Arkansas State 
line. This area is about 160 miles south of St. Louis, MO. 
Existing project. The Detailed Project Report recommends 
removing all major blockages from the channel just 
upstream of the Hargrove Bridge (R.M. 198.4) to the Arkansas 
State line (R.M. 170.9). The plan also involves the 
cutting of dead, dying or damaged rooted trees which are 
leaning over the channel at an angle greater than 30 degrees 
and in danger of falling and creating a blockage to flows. 
Local cooperation. The local cooperation agreement was 
signed May 15, 1992, by the Butler County Commission, the 
project sponsor, in accordance with Section 3 of the Flood 
Control Act of 1936, and amendments thereto. 
Operations and results during fiscal year. The feasibility 
study was completed and Detailed Project Report was 
prepared and approved in April 1991. Plans and specifications 
have been completed. 
Condition at end of fiscal year. Project contract is 
scheduled to be awarded in early 1993, and construction 
completion is scheduled in late FY 93. Project construction 
will be accomplished under Section 205 of the 1948 Flood 
Control Act, as amended. 
17. BLUE MOUNTAIN LAKE, AR 
Location. (See Table 28-1: Arkansas River Basin, AR, 
OK, and KS: Lakes.) 
Existing project. Construction cost was approximately 
$5.1 million. For further information see pages 906 and 907 
of 1962 Annual Report. (For authorization see table 28-B.) 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Flood damages 
prevented during FY 92 are estimated at $1,314,530; cumulative 
benefits through September 30, 1992, are estimated at 
$23,693,280. The project's seven developed parks experienced 
public visitation exceeding 2.5 million visitor-hours 
that resulted in $47,000 fee revenue. 
Condition at end of fiscal year. Project is complete 
except for additional recreational sanitary facilities. Construction 
of the project began in May 1940 and was placed in 
operation in March 1947. 
18. CLEARWATER LAKE, MO 
Location. (See Table 28-K: White River Basin, AR & 
MO: Lakes.) 
Existing project. Construction cost, including the cost of 
modifying the project, is estimated at $22.4 million. For 
further information see pages 897 and 898 of 1962 Annual 
Report. (See table 28-B for authorizing legislation.) 
Major rehabilitation. Construction began in November 
1987 on a seepage berm on the upstream face of the dam, a 
grout curtain on the right abutment, and a parapet wall along 
the dam. 
An additional 9 acres of land was acquired to widen the 
spillway from 190 feet to 370 feet. The widened spillway 
will pass about 90 percent of the probable maximum flood 
with water surface at the top of existing dam and parapet 
wall, preventing waves from overtopping dam. 
The cost of the modification is estimated at $11 million. 
Construction was essentially complete in September 1989. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Operation 
and maintenance continued. Flood damages prevented 
during FY 92 are estimated at $2,775,020; cumulative benefits 
through September 1992 are estimated at $85,321,680. 
Releases made from the lake during low-water periods were 
sufficient to supply municipal water for Piedmont, Poplar 
Bluff and other usages. Project currently has seven developed 
parks which in FY 92 experienced public visitation 
exceeding 4.2 million visitor-hours thatresultedin $161,383 
fee revenue. 
Condition at end of fiscal year. Project is complete 
except for additional and improvement to sanitary facilities 
in recreation areas. Construction of project began in June 1940 
and was ready for beneficial use in March 1948. 
28-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
19. DEQUEEN LAKE, AR 
Location. On Rolling Fork River, river mile 22.8, a 
tributary of Little River, in Sevier County, about 4 miles 
northwest of DeQueen, AR. (See Geological Survey map for 
Chapel Hill, AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,360 feet long, 
constructed to 160 feet above streambed. An uncontrolled 
spillway, 200 feet wide, is about 1,400 feet east of main 
embankment. Outlet works consist of a gated conduit, 
12 feet in diameter. The lake controls 169 square miles of 
drainage area and provides a total storage of 136,100 acrefeet 
(101,200 for flood control storage and 34,900 for 
conservation and sedimentation reserve). Federal cost of 
project is estimated at $19,623,752. (See table 28-B for 
authorizing legislation.) 
Local cooperation. Section 2, Flood Control Actof 1938, 
and Section 301, Water Supply Act of 1958, as amended, 
apply. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. Flood damages 
prevented during FY 92 are estimated at $213,630; cumulative 
benefits through September 30, 1992, are estimated at 
$5,835,000. In FY 92, the project's seven developed parks 
experienced public visitation exceeding 1.8 million visitorhours 
that resulted in $30,000 fee revenue. 
Condition at end of fiscal year. Construction began 
April 1966. Project was placed in useful operation in 
August 1977. 
20. DIERKS LAKE, AR 
Location. On Saline River, river mile 56.6, a tributary of 
Little River, about 5 miles northwest of Dierks, Howard 
County, AR. (See Geological Survey map for Dierks Dam, 
AR, quadrangle, scale 1:24,000.) 
Existing project. An earthfill dam, 2,760 feet long, about 
153 feet above streambed. An uncontrolled spillway 800 feet 
wide is in a saddle at west end of dam. Outlet works 
consisting of a gated 6- by 9-foot oblong conduit, one 24- 
inch low-flow pipe, and one 30-inch water supply pipe are 
provided. The lake controls a drainage area of 114 square 
miles and provides for storage of 67,100 acre-feet for flood 
control and 29,700 acre-feet for water supply, conservation, 
and sedimentation reserve, a total of 96,800 acre-feet. Federal 
cost of project is estimated at $16,002,781. (See table 
28-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Actof 1938, 
and Water Supply Act of 1958, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $275,860; cumulative benefits 
through September 30, 1992, are estimated at $3,864,470. 
During the year, 276 acre-feet of water supply storage were 
withdrawn by Tri-Lakes Water District. Currently has four 
developed parks which in FY 92 experienced 835,000 visitor- 
hours that resulted in $51,000 fee revenue. 
Condition at end of fiscal year. Construction began in 
June 1968. In May 1975, the embankment closure was 
completed and the project placed in useful operation. 
21. FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION 
(1) Emergency bank protection, Section 14, 1946 Flood 
Control Act. Fiscal year costs: State Hwy. 211, Current 
River, Clay Co., $6, 381; Hwy 71, Red River, Little River, 
Co., AR,$67,657 $; Interstate 30, Red River, Little River, 
Co., AR, $103,239; Jacks Fork River, Shannon Co., MO, 
$2,230; and, Petit Jean River, Yell Co., AR, $5,621; and 
Sewage Lagoon, Little Red River, Judsonia, AR, $14,483. 
(2) Snagging and clearing, Section 208, 1954 Flood 
Control Act. Fiscal year costs: Black River, Butler Co., MO, 
$18,824. 
(3) Flood control activities, Section 205, 1948 Flood 
Control Act. Fiscal year costs: Brown's Creek, Sharp Co., 
AR, $3,326; Cato Springs Branch, Fayetteville, AR, $32,537; 
DPR Little Red River, $23,325; Crooked Creek, Harrison, 
AR, Reconnaissance Report, $85,532; May Branch, Fort 
Smith, AR, $27,145; Mill Creek, Fort Smith, AR, $1,113,425; 
Rice-Carden Levee, Arkansas River, $36,176; Rock Creek, 
Pulaski Co., AR, $32,082; White River, Batesville, AR, 
$47,302; and, White River, Old Grand Glaise, AR, $15,000. 
22. FOURCHE BAYOU BASIN, LITTLE ROCK, AR 
Location. On Fourche, Rock and Grassy Flat Creeks in 
vicinity of Little Rock, Pulaski County, AR. 
Existing project. The project, authorized by the Water 
Resources Development Act of 1986 (PL 99-662), consists of 
widening, clearing and snagging with alteration of highway 
and railroad bridges. The estimated project cost is $29 million: 
Federal, $19.1 million; non-Federal, $9.9 million. 
Local cooperation. The city of Little Rock, the project 
sponsor, signed the local cooperation agreement in August 
1987. 
Operations and results during the fiscal year. Construction 
continued on the remaining two channel improvement 
contracts. The final construction contract was awarded 
on June 28, 1991. Overall project completion is scheduled 
for October 1993. 
28-6

LITTLE ROCK, AR DISTRICT 
23. GILLHAM LAKE, AR 
Location. Damsite is on Cossatot River, river mile 49.0, 
in Howard County, about 5 miles northeast of Gillham in 
Sevier County, AR. (See Geological Survey quadrangle map 
for Gillham Dam, AR, scale 1:24,000.) 
Existing project. For description of completed improvement, 
see pages 19-12 of Annual Report for 1977 (Tulsa 
District). Federal cost of project is estimated at $17,826,703. 
(See table 28-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Actof 1938, 
and Section 301, Water Supply Act of 1958, as amended, 
apply. Tri-Lakes Water District furnished a resolution of 
intent to repay costs allocated to water supply storage. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $318,390; total cumulative flood 
damages prevented are estimated at $7,457,330. During the 
year, Tri-Lakes Water District withdrew 787 acre-feet of 
water supply storage. In FY 92, the project's five developed 
parks experienced public visitation exceeding 1.7 million 
visitor-hours that resulted in $27,000 fee revenue. 
Condition at end of fiscal year. Construction began in 
June 1968. The embankment closure was completed in 
May 1975, and the project was placed in useful operation. 
24. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Approved regulations for operation and maintenance of 
flood control works, Part 208 of Title 33, Code of Federal 
Regulations, provide for periodic inspection of completed 
projects transferred to local interests for operation and 
maintenance. Inspections of local flood protection projects 
were made to determine extent of compliance with approved 
regulations for maintenance and operation of these projects. 
Responsible officials of improvement districts concerned 
were advised of inadequacies in maintenance and operation 
of local flood protection works under their jurisdiction where 
appropriate. Costs for FY 92 were $102,127. Total costs 
through September 30, 1992, were $1,504,647. 
25. LITTLE RED RIVER AND TRIBUTARIES, 
CLINTON, AR 
Location. In Clinton, Van Buren County, AR, along the 
tributaries of the Little Red River. The city lies between the 
tributaries of Archey Fork and South Fork and is bisected by 
Town Branch. 
Existing project. The flood damage reduction project 
consists of 100-foot bottom-width channel for 1.35 miles on 
Archey Fork Creek and a 300-foot bottom-width channel for 
1.99 miles on South Fork, Little Red River. 
Local cooperation. Fully complied with. 
Operations and results during the fiscal year. Mitigation 
measures to compensate for damages to the walleye pike 
fishery are being coordinated with the U.S. Fish and Wildlife 
Service and the Arkansas Game and Fish Commission. 
Condition at end of fiscal year. Mitigation measures 
continued. Construction of the project began in 1985 and 
was transferred to the city of Clinton in August 1986 for 
operation and maintenance. An operation and maintenance 
manual was furnished the city of Clinton. 
26. LITTLE RIVER BASIN, AR 
Location. Improvements are on Little River and tributaries 
in Arkansas. More definite location of individual items is 
shown in table 28-J. 
Existing project. Part of a six-lake system for flood 
control and other purposes in the Little River Basin. The 
system consists of four lakes in Arkansas: Millwood on the 
main stem, Dierks on the Saline River, DeQueen on the 
Rolling Fork River, and Gillham on the Cossatot River; and, 
two lakes in Oklahoma: Broken Bow on the Mountain Fork 
River and Pine Creek on the Little River. Under a District 
boundary change, effective in October 1980, the four projects 
in this system in Arkansas were reassigned from the Tulsa 
District to the Little Rock District. 
Local cooperation. Section 2, Flood Control Act of 1938, 
and Section 301, Water Supply Act of 1958, as amended, 
apply. Tri-Lakes Water District (DeQueen, Gillham, and 
Dierks) furnished a resolution of intent to repay costs allocated 
to water supply storage. The Southwest Arkansas 
Water District is currently repaying costs allocated to water 
supply storage at Millwood Lake. 
Operations and results during fiscal year. Operation 
and maintenanceofprojects continued. See individual projects 
for details. Flood damages prevented by the Little River 
Basin reservoirs during FY 92 are estimated at $853,900; 
cumulative benefits through September 30, 1992, are estimated 
at $26,918,020. 
Condition at end of fiscal year. Millwood, DeQueen, 
Gillham, and Dierks Lakes are complete and in operation. 
27. MILL CREEK, FORT SMITH, AR 
Location. In southwest Fort Smith, Sebastian County, 
AR. 
28-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. The project was constructed under 
Section 205 of the Continuing Authority Program. The 
project included improvements on 3.9 miles of the Mill 
Creek channel and modifications on three bridges. The 
estimated project cost is $8,233,000: $4,291,000, Federal; 
$3,942,000, non-Federal. 
Local cooperation. The city of Fort Smith, the local 
sponsor, signed the local cooperation agreement in November 
1988. 
Operations during the fiscal year. The contract for 
channel construction was awarded in August 1990. Project 
construction was completed in November 1992. Project 
fiscal completion was initiated. 
28. MILLWOOD LAKE, AR 
Location. On Little River, river mile 16.0, approximately 
7 miles east of Ashdown, Little River County, AR, and about 
2 miles northeast of Millwood, Little River County, AR. (See 
Geological Survey quadrangle map for Red Bluff, AR, scale 
1:24,000.) 
Existing project. For description of completed improvement 
and authorizing legislation see the 1969 Annual Report 
(Tulsa District). Federal cost of project is $46,100,082. (See 
table 28-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. A total of 66,231 acrefeet 
of water was released from the lake for water supply to 
Southwest Arkansas Water District. Flood damages prevented 
during FY 92 are estimated at $46,020; cumulative 
benefits through September 30, 1992, are estimated at 
$9,761,220. Millwood Lake has 12 developed parks which 
in FY 92 experienced public visitation exceeding 2.0 million 
visitor-hours that resulted in $17,000 fee revenue. 
Condition at end of fiscal year. Construction began in 
September 1961 and the project was placed in full floodcontrol 
operation in August 1966. Remaining work consists 
of additional recreational facilities. 
29. NIMROD LAKE, AR 
Location. (See Table 28-1: Arkansas River Basin, AR, 
OK, and KS: Lakes.) 
Existing project. Estimated cost is $4,005,627. For 
further information see pages 908 and 909 of 1962 Annual 
Report. See table 28-B for authorizing legislation. 
Local cooperation. Section 2 of the 1938 Flood Control 
Act applies. 
Operations and results during fiscal year. Operation 
and maintenance of project continued. Addition and improvement 
to existing recreation sanitary facilities continued. 
In FY 92, seven parks experienced public visitation 
exceeding 2.6 million visitor-hours that resulted in $68,000 
fee revenue. During FY 92, flood damages prevented on an 
average of 1,978 acres of improved land are estimated at 
$729,940; cumulative benefits through September 30, 1992, 
are estimated at $15,944,090. Ninety-three acre-feet of 
water was withdrawn by the city of Plainview, AR. 
Condition at end of fiscal year. Project is complete 
except for addition of and improvement to sanitary recreation 
facilities. A vault rest room was converted to waterborne 
with shower at Sunlight Bay Park. 
Construction of project began in January 1940 and was 
ready for beneficial use in January 1942. 
30. OTHER AUTHORIZED FLOOD CONTROL 
PROJECTS 
(See Table 28-E: Other Authorized Flood Control 
Projects.) 
31. PETIT JEAN RIVER, HIGHWAY 309, AR 
Location. On the north bank of the Petit Jean River 
upstream of the Arkansas State Highway 309 bridge and 
approaches. The bridge is approximately 1.5 miles south of 
Waveland in Yell County and 0.75 mile downstream from 
Blue Mountain Dam. 
Existing project. Project consists of the excavation of a 
75-ft. bottom-width channel to provide a straight approach 
to the bridge and construction of a revetment along the left 
side of the excavated channel to maintain the alignment. 
This work extends for 600 feet upstream of the Highway 309 
bridge. The lands required for the project are owned by the 
Federal Government. 
Local cooperation. The Arkansas State Highway and 
Transportation Department executed a local cooperation 
agreement on May 6,1991, to construct an emergency stream 
bank protection project under Section 14 of the 1946 Flood 
Control Act, as amended. 
Operations during the fiscal year. A feasibility study 
was completed and a detailed project report prepared in 
September 1990,recommended construction ofastreambank 
protection project upstream of the Highway 309 bridge on the 
Petit Jean River. Plans and specifications were completed in 
February 1991; a construction contract was awarded in June 
1991; and, construction was completed in August 1991. 
28-8

LITTLE ROCK, AR DISTRICT 
Condition at end of fiscal year. Modification is pending 
due to some overruns by the contractor for additional clearing 
and grubbing work required to complete the project. 
32. RED RIVER, I-30, LITTLE RIVER CO., AR 
Location. Red River at Interstate 30 in Hempstead 
County, located in southwestern Arkansas. 
Existing project. Plans consisted of construction of two 
stone-filled baffle dikes from the high top bank to the top of 
the existing pile revetment, which is capped out with stone. 
Construction authorized under Continuing Authority, Section 
14, Flood Control Act of 1946, as amended; emergency 
streambank erosion protection. 
Local Cooperation. The Arkansas State Highway and 
Transportation Department signed a local cooperative agreement 
April 3, 1992, and contributed $32,474 to project cost. 
The Federal share is $87,423. Total project cost estimated at 
$119,897. 
Operations and results during fiscal year. Construction 
contract was awarded in July 1992. 
Condition at end of fiscal year. Construction was completed 
in October 1992. 
33. RED RIVER, HWY 31, LITTLE RIVER CO., AR 
Location. Red River at Hwy. 71 in Little River Co., 
located in southwestern Arkansas. 
Existing project. Plans consisted of construction of a 
bankhead around the riverward piers for both the north and 
south bound bridges of Hwy. 71. The two bankheads have a 
100-foot radius turnbacks on the upstream and downstream 
ends. Construction includes paving the existing drains at 
both bridges, and the scour holes around the southbound 
bridge pier. 
Construction authorized under Continuing Authority, 
Section 14, Flood Control Act of 1946, as amended; emergency 
streambank erosion protection. 
Local Cooperation. The Arkansas State Highway and 
Transportation Department signed a local cooperative agreement 
April 3, 1992, and contributed $40,457 to project cost. 
The Federal share is $104,371. Total project cost estimated 
at $144,828 
Operations and results during fiscal year. Construction 
contract was awarded in June 1992. 
Condition at end of fiscal year. Construction was completed 
in October 1992. 
34. WHITE RIVER BASIN 
(LITTLE ROCK DISTRICT), AR & MO 
Location. Improvements are on White River and tributaries, 
Arkansas and Missouri. More definite location of 
individual items is shown in Table 28-K: White River Basin. 
Existing project. A general comprehensive plan for 
flood control and other purposes in White River Basin. The 
plan includes seven lakes; two are flood control only projects 
and five are multiple-purpose projects. Beaver, Table Rock, 
Bull Shoals, Norfork, Clearwater, Greers Ferry and Bell 
Foley lakes were selected and approved for construction by 
Chief of Engineers, and individual reports on six of these 
seven lakes are presented on subsequent pages. The Bell 
Foley project, the remaining unbuilt authorized project, was 
reevaluated in FY 89; the project continues to have a favorable 
benefit-to-cost ratio since its formulation in 1968. The 
lakes in the plan are listed in Table 28-K: White River Basin. 
(For authorization see table 28-B. ) 
Local cooperation. Section 2, Flood Control Act of 1938 
applies, Water Supply Act of 1958, as amended, applies to 
Beaver, Greers Ferry, and Norfork projects. 
Operations and results during fiscal year. Operation 
and maintenance of projects continued. Flood damages 
prevented by the White River Basin lakes during FY 92 are 
estimated at $13,519,840; cumulative benefits through September 
30, 1992, are estimated at $358,862,960. Flood 
damages prevented by the White River Basin levees during 
FY 92 are estimated at $1,754,300; cumulative benefits 
through September 30, 1992, are estimated at $69,362,200. 
Electric energy delivered to Southwestern Power Administration 
for marketing during FY 92 totaled 1,697,099,000 
kilowatt-hours. 
Water releases for fish hatcheries were: 28,960 acre-feet 
from Norfork Lake for Fish and Wildlife Service trout 
hatchery; 14,480 acre-feet from Table Rock Lake for Missouri 
Conservation Commission trout hatchery; and, 
14,480 acre-feet from Greers Ferry Lake for U.S. Fish and 
Wildlife Service trout hatchery. 
Withdrawals for water supply purposes were: Beaver 
Water District, AR, 31,460 acre-feet, and Carroll-Boone 
Water District, AR, 4,972 acre-feet, from Beaver Lake; 
Marion County Regional Water District, AR, 724 acre-feet 
from Bull Shoals Lake; Water and Sewer Improvement 
District No. 3 of Mountain Home, AR, 3,322 acre-feet from 
Norfork Lake; the city of Clinton, AR, 1,153 acre-feet, and 
the Community Water Treatment System, Cleburne County, 
AR, 946 acre-feet, from Greers Ferry Lake. 
Condition at end of fiscal year. Beaver, TableRock, Bull 
28-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Shoals, Norfork, Clearwater, and Greers Ferry lakes are 
complete and in operation. Progress on these lakes is shown 
in individual reports. Bell Foley lake project is in a deferred 
status. Water Valley and Lone Rock lakes have been 
deauthorized. 
35. WHITE RIVER, BATESVILLE, AR 
Location. On White River, within the city of Batesville, 
Independence County, AR. 
Existing project. The Definite Project Report, recommending 
construction of a levee and floodwall to protect the 
industrial area, under Section 205 of the 1948 Flood Control 
Act, was approved in June 1988. 
Local cooperation. Section 3 of the 1936 Flood Control 
Act, as amended, applies. 
Operations and results during the fiscal year. Revised 
plans and specifications for the National Economic Development 
(NED) alignment were initiated and are scheduled for 
completion in July 1993. Pending the completion of the 
Local Cooperation Agreement negotiations and acquisition 
of real estate, the award of a construction contract is scheduled 
for October 1994. Construction is scheduled for completion 
in October 1995. 
Multiple-Purpose Projects Including Power 
36. BEAVER LAKE, AR 
Location. (See Table 28-K: White River Basin.) 
Existing project. Estimated cost is $50,797,000. For 
further information see 788 and 789 of 1966 Annual Report. 
(For authorization see table 28-B. ) 
Major rehabilitation. Since the dam was constructed 
there has been a seepage problem below Dike No. 1. Based 
on detailed investigation, it was determined that the limestone 
foundation under dike 1 and 200 feet of the north end 
of the main dam embankment is the main problem. The plan 
of improvement was a concrete seepage cutoff in dike 1 and 
the north end of the main dam. A $16.9-million contract to 
construct a concrete cutoff wall was awarded in June 1989; 
the notice to proceed was issued in October 1989. The 
contract period was estimated to be 760 days. However, the 
contractor ceased productive work due to inability to excavate 
rock and was been placed in default. An $18.8 
reprocurement contract was awarded in April 1992, and 
work began in May 1992 to complete the work. Construction 
completion is scheduled for June 1994. Project cost is 
estimated at $26.2 million. 
Water Quality Enhancement. Congress directed the 
Corps to implement best management practices (BMP's) in 
the Beaver Lake watershed and monitor the effects of these 
practices on water quality. A study was completed and a 
project report was approved in July 1989. The BMP's and 
water quality monitoring are being concurrently implemented 
over a 5-year period which began in May 1991 with 
a project completion date of June 1996. 
The BMP's are being implemented under the terms of a 
memorandum of agreement between the Corps and the Soil 
Conservation Service with the assistance of the Agricultural 
Stabilization and Conservation Service. The local cost 
sharing for the BMP's are being obtained from the non- 
Federal participants (farmers) primarily by work-in-kind 
credit. The water quality monitoring is being implemented 
under terms of a local cost-sharing agreement with the 
Arkansas Soil and Water Conservation Commission. Water 
quality monitoring is being performed in consultation with 
the Environmental Protection Agency by a Corps administered 
contract. Project agreements were signed on May 11, 
1991, at Rogers, AR. BMP's are being implemented by SCS 
and AS&WCC obtained leases of the real estate for the water 
quality monitoring sites November 6, 1991. The water 
quality monitoring contract was awarded on January 29, 
1992. Water quality sampling began in May 1992. 
Local Cooperation. Section 2 of the 1938 Flood Control 
Act, and Section 301 the 1958 Water Supply Act, as amended, 
apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $961,000; cumulative benefits are 
estimated at$27,497,690. During the year, 139,795,500 kilowatt-
hours of electrical energy were delivered to the Southwestern 
Power Administration for marketing. Water supply 
storage withdrawn during the year was 36,433 acre-feet. 
The project has 9 developed parks which in FY 92 experienced 
public visitation exceeding 17 million visitor-hours 
that resulted in $455,200 fee revenue. 
Condition at end of fiscal year. Project is complete 
except for modifications to existing recreation and sanitary 
facilities. Alterations to existing parks to enhance fee collections, 
improve efficiency, and reduce the maintenance effort 
or rehabilitate the 25-year old park operation through operation 
and maintenance and SRUF funds, as appropriate. 
Construction of project began in October 1959 and was 
placed in operation for flood control in December 1963, 
hydroelectric power generation with both units in May 1965, 
and water supply in January 1966. Work on a dam seepage 
problem is described above. 
37. BULL SHOALS LAKE, AR 
Location. (See Table 28-K: White River Basin, AR & 
MO.) 
Existing project. Estimated cost with eight generating 
28-10

LITTLE ROCK, AR DISTRICT 
units is $96,356,000. For further information see pages 725 
and 726 of 1965 Annual Report. For authorization see 
table 28-B. 
Local cooperation. Section 2, Flood Control Act of 1938 
applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $5,121,480; total cumulative 
flood damages prevented are estimated at $114,078,090. 
During the year, 721,158,000 kilowatt-hours of electrical 
energy were delivered to Southwestern Power Administration 
for marketing. Water supply storage withdrawn during 
the year was 724 acre-feet. The project has 18 developed 
parks which in FY 92 experienced public visitation exceeding 
18.7 million visitor-hours that resulted in $275,000 fee 
revenue. 
Condition at end of fiscal year. Project is complete 
except for modifications to existing recreation and sanitary 
facilities. Alterations are needed to existing parks to enhance 
fee collections, to improve efficiency, to reduce maintenance 
effort or to rehabilitate 36-year-old park facilities through 
operations and maintenance or SRUF funds, as appropriate. 
Low dissolved oxygen readings in the downstream area of 
Bull Shoals Dam in October 1990 have resulted in ongoing 
studies to be undertaken to minimize harmful effects on the 
trout fishing of the White River. Unguaranteed short-term 
solutions to the problem, consisting of limiting generation, 
will sustain the existing fishery, but long-term guaranteed 
changes will require congressional authorization. Construction 
of project began in April 1946 and was ready for 
beneficial flood control use in June 1951 and generation of 
electrical energy in September 1952. Units 1 through 8 were 
placed in operation September 1952, December 1952, 
June 1953,January 1962,February 1962,August 1963,and 
September 1963, respectively. 
38. DARDANELLE LOCK AND DAM (NO. 10), AR 
Location. (See Table 28-H: Arkansas River Basin; AR, 
OK, and KS: Navigation.) 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. Dam is 2,683 feet long 
and 68 feet high. It has a spillway with 20 tainter gates 
50 feet long and 39 feet high. Navigation lock is 110 by 
600 feet with a lift of 54 feet. Powerhouse contains four 
31,000 kilowatt generators. Lake has a storage capacity of 
486,200 acre-feet. Estimated cost is $86,507,000. (See table 
28-B for authorizing legislation.) 
Local cooperation. (See section 1.) 
Operations and results during fiscal year. Continued 
operation and maintenance. Pool fluctuated within 2-ft. 
power pondage, elevation 336.0 to 338.0. Power generation 
continued. During FY 92, 905,820,400 kilowatt-hours of 
electrical energy were delivered to the Southwestern Power 
Administration for marketing. In FY 92, the project's 15 developed 
parks experienced public visitation exceeding 
23.1 million visitor-hours that resulted in $113,000 fee 
revenue. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. The hydraulic turbines at the Dardanelle 
powerplant will require extensive rehabilitation in the near 
future. Complete disassembly of the turbines will be required 
to replace the turbine blade bearings and oil seals. Several 
repair alternatives are being examined including replacement 
of the turbines to increase the available power output 
of the generating units. Index testing to determine new 
turbine design is underway. Construction began June 1957. 
Power units were placed on line in April, May, and September 
1965, and January 1966. Lock became operable in 
December 1969. Visitors Center and resident office were 
completed in May 1985. 
39. GREERS FERRY LAKE, AR 
Location. (See Table 28-K: White River, AR & MO.) 
Existing project. Estimated cost is $55,125,000. For further 
information see page 740 of 1964 Annual Report. (See 
table 28-B for authorizing legislation.) 
Local cooperation. Section 2, 1938 Flood Control Act and 
1988 Water Supply Act, as amended, apply. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $889,860; total cumulative flood 
damages prevented are estimated at $24,682,560. In FY 92, 
194,027,000 kilowatt-hours of electrical energy were delivered 
to the Southwestern Power Administration for marketing. 
In FY 92, 2,095 acre-feet of water supply storage was 
withdrawn. The project has 18 developed parks which in 
FY 92 experienced public visitation exceeding 27.2 million 
visitor-hours that resulted in $527,000 fee revenue. The 
project's operational management plan provides means by 
which the natural resources, including water quality, aesthetic 
value, forestry, fish and wildlife are managed and 
protected for future generations. An all-volunteer environmental 
program (annual cleanup) has been most successful 
and serves as a model for the Nation. During the past 23 years 
the program has won 24 national awards. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities. Construction ofprojectbegan in June 1957 
and was ready for beneficial flood control use in January 
1962. Power units 1 and 2 were operable in March and 
28-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
May 1964, and water supply was operable in April 1971. 
The Visitors Center was completed in June 1983 at a cost of 
$813,000. 
40. NORFORK LAKE, AR 
Location. (See Table 28-K: White River Basin, AR & 
MO.) 
Existing project. Total estimated cost is $111,624,000, 
including $38,700,000 for addition of power units 3 and 4, 
and $40,000,000 for highway bridge construction. For further 
information see page 896 of 1962 Annual Report. (See 
table 28-B for authorizing legislation.) 
Local cooperation. Section 2, Flood Control Act of 1938 
and Water Supply Act of 1958, as amended, applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $1,412,130; total cumulative 
flood damages prevented through September 30, 1992, are 
estimated at $37,026,990. During the year, 183,993,700 
kilowatt-hours of electrical energy were delivered to the 
Southwestern Power Administration for marketing. Water 
supply withdrawn by the city of Mountain Home, AR, totaled 
3,322 acre-feet. The project's 18 developed parks experienced 
public visitation exceeding 16.2 million visitor-hours 
that resulted in $237,000 fee revenue during FY 92. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreation 
sanitary facilities, and addition of power units 3 and 4. 
Construction of project began in October 1940, ready for 
beneficial flood control use in June 1943, and for generation 
of electrical energy with one unit in June 1944. Second unit 
was added in February 1950. Water supply was added as a 
purpose in December 1969. Construction of two highway 
bridges over Norfork Lake to replace ferries was completed 
in November 1982. The bridges were transferred to the 
Arkansas Highway and Transportation Department for operation 
and maintenance in July 1984. 
41. OZARK-JETA TAYLOR LOCK AND DAM 
(No. 12), AR 
Location. (See Table 28-H: Arkansas River Basin, AR, OK, 
and KS: Navigation.) 
Existing project. Project is a unit of McClellan-Kerr 
Arkansas River Navigation System. The dam is 2,480 feet 
long and 58 feet above streambed; spillway has 15 tainter 
gates 50 feet long and 46 feet high. Navigation lock is 110 
by 600 feet with a lift of 34 feet. Powerhouse contains five 
20,000 kilowatt generators. Lake has a storage capacity of 
148,400 acre-feet. In addition, 1 foot of power pondage is 
provided in pool 13 between elevations 391.0 and 392.0. 
Estimated cost is $86,167,000. (For authorization see 
table 28-B.) 
Local cooperation. (See section 1.) 
Operations and results during fiscal year. Continued 
operation and maintenance. Delivered 540,173,300 kilowatt-
hours of electrical energy to Southwestern Power Administration 
for marketing. Ozark Lake has 10 developed 
parks which in FY 92 experienced public visitation exceeding 
1.6-million-visitor-hours that resulted in $40,000 fee 
revenue. 
Condition at end of fiscal year. Construction began in 
December-1964. Project is complete except for addition and 
improvement to existing recreation sanitary facilities. Lock 
and dam was placed in operation in November 1969. Power 
units were placed on line as follows: unit 1, November 1972; 
unit 2, August 1973; unit 3, October 1973; unit 4, December 
1973; and unit 5, May 1974. Remaining work consists 
principally of modifications to the powerplant. 
42. TABLE ROCK LAKE, MO 
Location. (See Table 28-K: White River Basin, AR & 
MO.) 
Existing project. Estimated cost is $71,233,000. For 
further information see page 893 of 1962 Annual Report. 
(For authorization see table 28-B. ) 
Local cooperation. Section 2 of the 1938 Flood Control 
Act applies. 
Operations and results during fiscal year. Continued 
operation and maintenance. Flood damages prevented during 
FY 92 are estimated at $2,359,390; total cumulative 
flood damages prevented are estimated at $70,255,950. 
During the year, 458,126,900 kilowatt-hours of electrical 
energy were delivered to the Southwestern Power Administration 
for marketing. The District and the Waterways 
Experiment Station are investigating the possibilities of 
improving the quality of Table Rock releases with a 
hypolimnetic oxygenation system. Table Rock Lake has 
16 developed parks which in FY 92 experienced public 
visitation exceeding 38.4 million visitor-hours that resulted 
in $482,000 fee revenue. This project's operational management 
plan provides means by which the natural resources, 
including forestry, fish and wildlife, are managed and protected 
for future generations. 
Condition at end of fiscal year. Project is complete 
except for addition and improvement to existing recreational 
sanitary facilities. Construction of project began in October 
1954. The project was ready for beneficial flood control 
use in November 1958, and for generation of electrical 
energy with units 1 and 2 in May 1959. Units 3 and 4 were 
28-12

LITTLE ROCK, AR DISTRICT 
added in April and June 1961. 
General Investigations 
43. SURVEYS 
Expenditures for surveys in FY 91 totaled $385,898: 
Navigation studies.White River and Tributaries, AR, 
$4,381. 
Flood damage prevention studies. Arkansas River 
Basin Studies, AR and OK, $46,178; Central Arkansas 
Study, AR, $8,504; Little River County, AR, $142,024. 
Review of completed projects. Village Creek Taylor 
Bay, $73,100. 
Miscellaneous activities. Special investigations, $35,000; 
review of FERC licenses, $2,000; interagency water resource 
development, $17,629. 
Coordination studies with other agencies. Department 
of Agriculture, Soil Conservation Service, $2,000; Planning 
assistance to states, $42,082. 
44. COLLECTION AND STUDY OF BASIC DATA 
Flood plain management services (FPMS). The authority 
for the Flood Plain Management Services program is 
Section 206 of the 1960 Flood Control Act, PL 86-645, as 
amended.Under the authority of Section 321 of the Water 
Resources Development Act of 1990, PL 101-640, technical 
services and planning assistance are (1) provided to states 
and local governments without charge and (2) offered to 
Federal agencies and private persons on a cost recovery basis. 
Through these technical services and planning guidance, the 
program encourages comprehensive flood plain management 
planning at all levels to reduce the potential for losses 
to life and property from floods. 
Federal and non-Federal agencies and the private sector 
are assisted with planning and development information for 
flood hazard areas. This assistance is in the form of local 
flood plain regulations, Federal Insurance Program requirements, 
and Executive Order 11988 guidelines. Such assistance 
may include factual flood information (available or 
determined) and interpretation of flood frequencies, extent 
of flooding, flood-water velocity, duration of flooding and 
floodway limits. 
Hydrologic studies. During FY 92, 117 stations were 
operated; 78 cooperatively with USGS and 39 by the Corps. 
The total cost for streamflow and some sediment data from 
all sources of funding was $633,430, of which $464,910 was 
transferred to USGS. The District also participated in a 
cooperative program with National Weather Service for 
rainfall and/or river reporting stations for use in forecasting 
streamflow for flood warning and operation of lake projects. 
Records were also collected at certain hydroclimate rainfall 
stations under a cooperative program between the two agencies. 
For these services, $45,382 was transferred to the 
National Weather Service. 
28-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-A COST AND FINANCIAL STATEMENT 1'2 
See Total Cost 
Section to 
in Text Project Funding FY 89 FY 90 FY91 FY92 Sept.30,1992M 
1. Arkansas River 
Basin, AR 
OK & KS 
3. McClellan-Kerr 
Arkansas River 
Bank Stabilization 
& Channel 
Rectification, 
AR 
2,4-9, McClellan-Kerr 
11,13,15 Arkansas River 
Navigation 
Locks & Dams, 
AR 
16. Black River, Obstruc. 
Removal, 
Butler Co., MO 
17. Blue Mountain 
Lake, AR 
New Work 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Maint. 
Approp. 
Dams 
Navigation 
Cost 
Dams 
Navigation 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Special Funds 
Cost 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Other 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
$7,481,000 
7,481,000 
4,256,220 
4,256,220 
68,731,146 
13,230,308 
51,500,838 
20,319,918 
13,699,711 
56,620,207 
$2,369,690 
2,369,690 
2,389,514 
2,389,514 
76,824,993 
17,676,594 
59,148,399 
70,427,194 
17,077,747 
53,349,447 
$13,161,000 $1,492,416,743 
13,161,000 163,479,533 
4,852,926 1,328,937,210 
13,041,996 1,487,904,151 
163,321,500 
13,041,996 1,324,587,651 
56,035,960 
11,968,850 
44,067,110 
59,936,450 
12,040,914 
47,895,536 
63,710,984 
15,498,300 
48,212,684 
62,773,752 
15,194,861 
47,578,891 
988,301,499 2 
215,500,245 
772,801,254 
989,441,467 2 
214,407,7632 
775,033,704 
291,106 
291,106 
1,609,842 
1,609,842 
_ -_ 19,926,755 
- -. 19,926,755 
- -. _ 531,336 
_ -. _ 531,336 
119,300,184 
- -. 119,300,184 
- _. 4,561,666 
- _. 4,561,666 
7,481,000 6,657,000 9,445,000 13,161,000 465,050,472 
4,238,604 7,056,291 12,205,094 13,041,996 465,021,597 
19,445,600 26,793,291 19,059,039 20,817,284 320,051,604 2 
20,251,720 22,855,943 21,710,994 20,269,430 317,581,433 2 
161,481 
21,256 
395,123 
193,633 
247,625 
494,725 
2,171,734 3,954,348 
997,656 2,670,837 
531,336 
531,336 
40,000 
38,024 
25,900 
14,940 
8,000 
18,824 
73,900 
71,788 
_ 5,069,974 
_ 5,069,974 
747,000 
750,783 
762,082 
671,231 
880,400 
883,204 
958,200 14,592,098 2 
903,965 14,485,621 2 
28-14

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-A COST AND FINANCIAL STATEMENT1'2 
(Continued) 
See Total Cost 
Section to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept.30,19921" . 
18. Clearwater 
Lake, MO 
19. DeQueen Lake, 
Little River 
Basin, AR 
20. Dierks Lake, 
Little River 
Basin, AR 
22. Fourche Bayou 
Basin, 
Little Rock, AR 
23. Gillham Lake, 
Little River 
Basin, AR 
25. Little Red River 
& Tributaries, 
Clinton, AR 
26. Little River 
Basin, (Little 
Rock Dist.), 
AR 
27. Mill Creek, Fort 
Smith, AR 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
1,590,000 1,483,556 1,768,800 
1,654,116 1,418,673 1,806,030 
3,660,000 
3,674,652 
501,910 
391,123 
779,000 
893,713 
- 11,073,403 
S 11,060,204 
1,943,600 30,152,500 
1,763,943 30,198,9281 
60,000 11,467,910 
64,553 11,468,164 
- 19,629,753 
S 19,623,752 
834,000 
823,817 
798,952 
654,521 
834,400 
956,492 
946,300 10,016,201 2 
952,856 9,995,468 2 
S 16,002,904 
S 16,002,781 
881,000 
919,005 
818,159 
721,818 
793,600 
805,733 
949,300 10,381,043 2 
1,001,592 10,371,9652 
2,252,000 5,706,000 5,807,000 2,417,000 18,767,000 3 
1,313,562 3,983,326 3,882,948 4,543,525 17,881,903 3 
166,900 
61,900 
847,360 
847,710 
170,000 
200,000 
862,837 
690,717 
9,281 
558,200 
468,103 
887,300 
945,719 
9,942 
400,000 1,731,678 
359,064 1,525,645 
S 17,827,111 
S 17,826,703 
904,400 9,701,643 
970,716 9,654,0802 
3,999,500 
23,325 3,932,5383 
_ 99,959,850 
S- _ 99,544,384 
4,129,360 4,317,745 4,218,000 4,468,300 59,236,829 2 
4,210,494 3,343,168 4,794,137 4,770,664 58,984,912 2 
119,000 
60,955 
68,400 
30,254 
3,465,000 
354,230 
120,000 
111,844 
435,000 
2,408,684 
312,892 
341,822 
- 4,291,000 3 
1,113,425 4,116,5123 
79,360 580,652 
15,055 498,975 
28-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-A COST AND FINANCIAL STATEMENT1 ,2 
(Continued) 
See Total Cost 
Section to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept.30,19921.2 
28. Millwood Lake, Little River 
Basin, AR 
29. Nimrod Lake, 
AR 
31. Petit Jean River, 
Highway 309, 
AR 
32. Red River, Hwy 71 
Little River Co, 
AR 
33. Red River, I-30 
Little River Co, 
AR 
34. White River 
Basin, AR &MO 
(Little Rock 
District) 
35. White River 
Batesville, AR 
36. Beaver Lake, 
AR 
-- Beaver Lake 
Water Quality 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Appropr. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Appropr. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Appropr. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
46,087,318 
46,091,248 
1,567,000 1,837,795 
1,619,963 1,276,115 
1,702,700 
2,086,195 
1,668,300 28,743,178 2 
1,845,500 28,966,403 2 
4,092,826 
4,005,627 
1,085,000 1,062,917 
1,122,311 972,960 
16,000 
15,583 
15,000 
15,000 
1,030,500 
1,051,070 
78,000 
72,796 
28,250 
25,264 
17,000 
21,580 
10,000 
19, 
1,285,000 17,869,217 2 
1,146,947 17,730,5672 
5,621 
823 
115,000 
67,657 
56,200 
15,621 
99,300 
103,240 
153,700 
88,879 
94,000 
94,000 
28,250 
26,087 
132,000 4 
89,237 4 
56,200 
15,621 
124,300 4 
103,2404 
153,700 
88.879 
_. 335,651,873 
.. 335,378,666 
23,919,340 15,807,440 18,573,700 23,286,600 363,113,051 1 
24,188,550 14,119,499 19,561,136 22,575,704 363,774,196' 
104,200 
101,699 48,433 854 
3,000,640 3,234,847 3,942,200 
3,070,175 2,899,252 4,081,426 
221,000 4,362,320 
169,363 4,140,246 
340,400 
17,161 
S 100,000 1,256,000 
38,877 205,687 
85,000 
47,302 
431,700 
394,005 
- 46,183,033 
46,112,07 
3,657,000 51,953,6982 
3,841,602 51,169,3632 
2,092,000 7,015,720 
1,834,472 6,161,242 
1,000,000 2,356,000 
1,025,263 1,269,828 
28-16

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-A COST AND FINANCIAL STATEMENT1'2 
(Continued) 
See Total Cost 
Section to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept.30,19921o2 
37. Bull Shoals 
Lake, AR 
38. Dardanelle Lock 
& Dam (No. 10) 
AR 
39. Greers Ferry 
Lake, AR 
40. Norfork Lake, 
AR 
41. Ozark-Jeta Taylor 
Lock & Dam 
(No.12), AR 
42. Table Rock 
Lake, MO 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
6,227,200 
6,219,380 
3,909,515 
3,780,267 
88,858,711 
88,858,707 
4,287,400 4,299,000 84,084,3092 
4,323,288 4,287,539 83,719,746 
84,270,124 
84,261,240 
4,736,000 
4,862,558 
4,743,000 
4,789,616 
3,229,000 
3,268,163 
4,675,000 
4,688,530 
5,129,500 
5,187,103 
4,311,019 
4,074,968 
4,106,295 
4,014,869 
3,046,931 
2,378,574 
4,078,320 
3,672,220 
4,132,592 
3,642,737 
4,814,200 6,132,000 72,086,687 2 
4,668,761 6,021,095 71,651,7122 
48,865,512 
48,865,512 
4,460,500 5,122,000 69,384,195 2 
3,909,714 4,920,459 68,374,437 
70,701,628 
70,701,628 
3,507,100 3,094,000 58,003,1042 
3,926,314 3,191,017 58,044,0942 
85,629,412 
85,629,412 
3,388,200 3,577,000 58,212,397 
3,926,390 3,350,848 57,744,697 
67,224,000 
67,224,000 
5,068,200 5,171,000 78,123,580 2 
5,424,081 4,571,144 77,235,5532 
1. For more details on project funds, see text for individual projects. 
2. Beginning data shown in Table 28-A includes special recreation use fees. 
3. Includes funds for plans and specifications. 
4. Includes total project cost, including study cost. 
28-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-B AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
June 28, 1938 
August 18, 1941 
July 24, 1946 
July 24, 1946 
June 30, 1948 
May 17, 1950 
ARKANSAS RIVER BASIN, AR, OK, & KS 
(See Section 1 of text) 
Approved General comprehensive plan: 
Mannford Reservoir, OK 
Oologah Lake, OK 
Canton Lake, OK 
Tenkiller Ferry Lake, OK 
Wister Lake, OK 
Blue Mountain Lake, AR 
Nimrod Lake, AR 
Modified comprehensive plan to include reservoirs in 
Grand (Neosho) River Basin, OK, and Mo, and in 
Verdigris River Basin: 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Pensacola Reservoir Lake O' The Cherokees, OK 
Fall River Lake, KS 
Elk City Lake, KS 
Toronto Lake, KS 
Neodosha Lake, KS 
Authorized Chief of Engineers to provide in the Canton 
Lake 69,000 acre-feet of irrigation storage, subject to 
certain conditions. 
Approved multiple-purpose plan: 
Oologah Lake, OK 
Markham Ferry Reservoir, OK 
Fort Gibson Lake, OK 
Blackburn Reservoir, OK 
Mannford Reservoir, OK 
Taft Reservoir, OK 
Bank stabilization 
Dardanelle Lock and Dam, AR 
Eufaula Lake, OK 
Navigation locks and dams 
Ozark Lock and Dam, AR 
Short Mountain Lock and Dam, OK 
Webbers Falls Lock and Dam, OK 
Tenkiller Ferry Lake, OK 
Modified Arkansas River navigation comprehensive plan to 
include bank protection works at Bradens Bend, OK. 
Modified comprehensive plan authorized in 1938 Flood 
Control Act and multiple-purpose plan authorized in 
River and Harbor Act of 1946 to provide for substituting 
Keystone Lake for Mannford, Blackburn and Taft 
Reservoirs. 
28-18 
Flood Control Com. 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 107 and 440, 
76th Cong. 1st sess. 
H. Doc 758, 79th Cong., 
2d sess. 
H. Doc 758, 79th Cong., 
2d sess. 
S. Doc 107, 81st Cong., 
1st sess.

LITTLE ROCK, AR DISTRICT 
TABLE 28-B 
(Continued) AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
Authorized incorporation of River and Harbor and Flood 
Control plans into a single plan of development and made 
Authorized incorporation of River and Harbor and Flood 
Control plans into a single plan of development and made 
all pervious authorizations applicable to combined 
plan of development. 
November 17, 1986 
June 10, 1948 
Fourche Bayou Basin, Little Rock, AR 
(See Section 21 of text.) 
Mill Creek, Fort Smith, AR 
(See Section 26 of text.) 
Water Resources 
Development Act of 
1986, P.L. 99-662, 
Sec. 401. 
Section 205, P.L. 80-858. 
Authorized by Asst. Sec. of 
the Army (CW), 10/14/88. 
RED RIVER BELOW DENISON DAM INCLUDING 
LITTLE RIVER BASIN, OK AND AR 
(See Section 25 of text) 
Construct Boswell, Hugo, and Millwood Lakes, and Bank 
Stabilization. 
Modified Millwood: Construct Pine Creek, Lukfata, 
Broken Bow, DeQueen, Gillham, Dierks Lakes 
July 24, 1946 
July 3, 1958 
H. Doc. 602, 79th Cong., 
2d sess. 
H. Doc. 170, 85th Cong., 
1st sess. 
WHITE RIVER BASIN 
(LITTLE ROCK DISTRICT) 
(See Section 30 of text) 
June 28, 1938 
August 18, 1941 
September 3, 1954 
October 23, 1962 
March 1, 1974 
Approved comprehensive plan for White River Basin: 
Lone Rock Lake, AR, Norfork Lake, AR, 
Clearwater Lake, MO, Water Valley Lake, AR, 
Bell Foley Lake, AR, Greers Ferry Lake, AR, 
and White River emergency. 
Modified comprehensive plan to include Bull Shoals 
Lake, AR, and MO, Table Rock Lake, MO, and 
AR, and Norfork Lake, AR, and MO (power). 
Authorized power in Greers Ferry Reservoir and added 
Beaver Lake to the plan. 
Authorizing clearing and straightening of channel for 
Village Creek, Jackson and Lawrence Counties. 
Authorizing highway bridge construction across 
Norfork Lake. 
Flood Control Com. 
Doc 1, 75th Cong.,lst sess. 
H. Doc. 917, 76th Cong., 
3d sess. 
H. Doc. 290, 77th Cong., 
1st sess. 
H. Doc. 499, 83d Cong., 
2d sess. 
H. Doc 352, 87th Cong., 
2d sess. 
Flood Control Com. 
Doc. 1, 75th Cong., 
1st sess. 
28-19 
July 14, 1960 
July 14, 1960

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-B 
(Continued) AUTHORIZING LEGISLATION 
Date of 
Authorizing Act Project and Work Authorized Documents 
June 30, 1948 
October 22, 1976 
June 30, 1948 
August 28, 1937 
Little Red River and Tributaries, 
Clinton, AR (See Section 24 of text.) 
White River Fish Hatchery, Arkansas provides for 
trout production facilities downstream from 
Beaver Dam. 
White River, Batesville, AR. 
(See Section 31 of text.) 
White River, St. Paul, AR. 
(See Section 32 of text.) 
Section 205, P.L. 80-858. 
Authorized by the Chief of 
Engineers, 10/11/84. 
Water Resources 
Development Act of 
1976, P.L. 94-587, 
Sec. 105. 
Section 205, P.L. 80-858, construction 
to be approved by ASA 
(CW). 
Section 208, P.L. 75-406. 
Authorized by the Asst. Sec. of 
the Army (CW), 10/29/88. 
28-20

LITTLE ROCK, AR DISTRICT 
TABLE 28-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Federal Cost to Sept. 30, 1992 
Full Report 
See Annual Operation and 
Project Report For Construction Maintenance 
Arkansas River, Little Rock Slackwater Harbor, AR 1 1988 $736,869 
Black River, AR and MO 2 1950 80,000 $ 930,324 
Current River, AR and MO 2 1964 17,0003 132,178 
Upper White River, AR '4 1952 813,197 1,788,374 
1950 785,666 
White River, AR (above Peach Orchard Bluff) 2 5 
1984 43,110 
White River, Jacksonport, AR 6 
1. Completed. Authorized by Chief of Engineers under authority of Sec. 
107, 1960 R & H Act, as amended, (P.L.86-645). 
2. Channel adequate for existing commerce; completion not contemplated. 
3. Includes $7,000 for previous project. 
4. Federal operation and maintenance terminated June 30, 1952, due to 
lack of commerce. Facilities at Locks and Dams Nos. 1,2, and 3 disposed 
of in accordance with authority in Public Law 996, 84th Congress. 
5. Completed. 
6. Responsibility for maintenance of project downstream from Newport, 
AR; transferred to Memphis District in FY 62. 
28-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 28-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept. 30, 1992 
Full Report 
See Annual Operations and 
Project Status Report For Construction Maintenance 
Bell Foley Lake, White River, AR' Inactive 1975 $1,432,116 
Black River, Butler County Road 607, MO Completed 1985 44,500 
Black River, Poplar Bluff, MO, to 
Knobel, AR Completed 1958 84,315 
Butler County Drainage District 3, MO Completed 1983 42,172 
Carden's Bottom Drainage District No. 2, 
Arkansas River, AR Completed 1951 919,955 
Clarksville, AR Completed 1962 271,717 
Conway County Drainage and Levee District 
District No. 1, Arkansas River, AR Completed 1959 187,440 
Conway County Levee Districts Nos. 1, 
2, and 8, Arkansas River, AR Completed 1952 1,018,840 
Conway County Levee District No. 6, 
Arkansas River, AR Completed 1952 390,952 
Crawford County Levee District, AR Completed 1983 53,506 
Crawford County Levee District, Arkansas 
River, AR Completed 1954 2,001,820 
Curia Creek Drainage District, 
Independence County, AR Completed 1983 117,898 
East Poplar Bluff and Poplar Bluff, MO Completed 1958 304,699 
Faulkner County Levee District No. 1, 
Arkansas River, AR Completed 1941 99,511 
Fort Smith, Arkansas River, AR Completed 1951 1,077,546 
From North Little Rock to Gillett, AR 
(above Plum Bayou) Completed 1954 845,300 
Fourche Creek, Little Rock, AR2 Cancelled 1973 22,890 
Jackson Couinty Levee District 2, 
White River, AR Completed 1986 131,699 
Little Massard Creek, Fort Smith, AR Completed 1983 198,096 
Little Red River District 1, AR Completed 1988 28,968 
Little Red River, White County Road 
Bridge, Judsonia, AR Completed 1983 63,355 
Little Rock Levee, AR, East End 
Fourche Bayou, AR Completed 1975 1,901,899 
McLean Bottom Levee District No. 3, 
Arkansas River, AR Completed 1950 422,549 
Near Dardanelle, Arkansas River, AR Completed 1953 198,069 
Newport, White River, AR Completed 1941 314,276 
North Little Rock, Arkansas River, AR Completed 1958 512,001 
Otter Creek and Tributaries, 
Shannon Hills, AR Completed 1987 162,204 
Petit Jean River, AR Completed 1966 84,350 
Petit Jean River, AR Completed 1991 88,379 
Pine Mountain Lake, AR3 Inactive 1985 1,432,331 
Point Remove Levee and Drainage 
District, Conway County, AR Completed 1983 86,943 
Red River, !-30, Little River Co., AR Completed 1992 119,897 
Red River, Hwy. 31, Little River Co., AR Completed 1992 144,828 
Roland Drainage District, Arkansas River, Completed 1950 269,907 
AR 
Rolling Fork River, Sevier Coiunty, AR Completed 1983 64,500 
28-22

LITTLE ROCK, AR DISTRICT 
TABLE 28-E 
(Continued) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sept. 30, 1992 
Full Report 
See Annual Operations and 
Project Status Report For Construction Maintenance 
Skaggs Ferry, Black River, AR Completed 1941 81,023 
South Bank, Arkansas River (Head Fourche 
Island to Pennington Bayou), AR Completed 1964 1,404,852 
South Bank, Arkansas River, Little Rock to 
Pine Bluff, AR, Tucker Lakes Completed 1961 409,115 
Swan Creek Bank Stab., Taney County, MO Completed 1986 76,800 
Van Buren, Arkansas River, AR Completed 1952 438,222 
Village Creek, White River, and Mayberry 
Levee Districts, AR4 Completed 1972 1,567,156 
Village Creek, Jackson and 
Lawrence Counties, ARS Inactive 1977 510,217 
West of Morrilton, Arkansas River, AR Completed 1962 1,269,959 
White River, at Hwy 14, 1/4 mile east 
of Oil Trough, AR Completed 1981 214,308 
White River Bank Stab., Batesville, AR Completed 1986 101,100 
White River, Jacksonport, AR Completed 1987 277,600 
White River, Newport, AR Completed 1989 93,929 
White River, St. Paul, AR Completed 1990 22,400 
1. Reclassified as inactive in Jun '77; reviewed & deferred in May'85; 3. Reclassified as inactive in Jul '85. 
funded for reevaluation (draft report dated Sep '89). 4. See H Doc 577,87th Cong for description. 
2. Construction of project cancelled because local interests failed to 5. Reclassified in Jun '77; local interests unable to meet local 
provide right-of-way for construction and maintenance, cooperation requirements; funded for reevaluation in FY 89; recommended 
to be placed in the inactive status. 
TABLE 28-G DEAUTHORIZED PROJECTS 
For Last Funds Expended 
Full Report 
See Annual Date Federal Contributed 
Project Report For Authority Deauthorized Funds Funds 
Crooked Creek Lake 
& Levee, AR 1969 1968 FCA 1990 
Lone Rock, Buffalo 
River, AR 1959 1938 FCA 1977 $130,653 
Prosperity Lake, MO PL93-251 1989 864,000 
Water Valley, Eleven 
Point River, AR & MO 1959 1963 FCA 1977 414,011 
28-23

TABLE 28-H ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Depth on Char- Year 
Up- Upper Miter Sill acter Opened 
stream Lock Pool of to Tot 
from Miles to Dimension Lift (feet, Upper Lower Foun- Kind of Type of Naviga- Estim 
Feature Mouth Nearest Town (feet) (feet) MSL) (feet) (feet) dation Dam Construction tion Co! 
LITTLE ROCK 
DISTRICT 
Norrell Lock and 
Dam No.1 
Entrance Channel 
Lock No. 2 
Wilbur D. Mills Dam 
(No. 2) 
00 
Joe Hardin Lock and 
Dam No. 3 
10.3 8 east of Arkansas 
Post, AR 
First 10.3 miles of system 
13.3 6 east of Arkansas 
Post, AR 
40.5 3 southeast Arkansas 
Post, AR 
50.2 5 north of Grady, AR 
110 by 600 30max 142 16 15 Piles in Fixed 
sand overflow 
Concrete 1967 $22,472,000 
43,646,000 
110 by 600 20 nom 
28 max 
162 18 14 Piles in 1967 70,229,000 
sand 
Piles in 
sand 
110 by 600 20 182 18 14 Piles in 
sand 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Emmett Sanders Lock 
and Dam (No. 4) 
Lock and Dam No. 5 86.3 
66.0 7 east of Pine Bluff, 
AR 
4 southeast of 
Redfield, AR 
110 by 600 14 196 
110 by 600 17 213 
18 14 Piles in Movable Gated concrete 
sand spillway with 
embankment 
ends 
18 14 Clay Movable Gated concrete 
spillway with 
embankment 
ends 
1968 45,105,000 
1968 31,603,000 
David D. Terry Lock 108.1 12 southeast of Little 
and Dam (No. 6) Rock, AR 
110 by 600 18 231 18 14 Piles in Movable 
sand 
Gated concrete 
spillway with 
embankment 
ends 
al 
ated 
st 
1968 
1968 37,936,000 
0O
0
tI 
0'T. 
0z 
0
0
N) o
od 
oC 
o
t,,, 
to 
1968 68,645,000

TABLE 28-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Depth on Char- Year 
Up- Upper Miter Sill acter Opened 
stream Lock Pool of to To 
form Miles to Dimension Lift (feet, Upper Lower Foun- Kind of Type of Naviga- Estin 
Feature Mouth Nearest Town (feet) (feet) MSL) (feet) (feet) dation Dam Construction tion Co
tal 
hated 
)st 
Murray Lock and Dam 125.4 6 northwest of Little 
(No.7) Rock, AR 
Toad Suck Ferry 
Lock and Dam 
(No. 8) 
155.9 6 west of Conway, AR 
110 by 600 18 249 
110 by 600 16 265 
18 14 Shale Movable Gated concrete 
spillway with 
embankment 
ends 
18 14 Shale Movable Gated concrete 
spillway with 
embankment 
ends 
Arthur V. Ormond 
Lock and Dam 
(No. 9) 
Dardanelle 
Lock and Dam 
(No. 10) 
Lock and Dam No. 11 
Ozark-Jeta Taylor 
Lock and Dam 
(No. 12) 
James W. Trimble 
Lock and Dam 
(No. 13) 
176.9 3 southwest of 
Morrilton, AR 
205.5 2 northwest of 
Dardanelle, AR 
110 by 600 19 284 
110 by 600 54 338 
18 14 Shale Movable 
18 14 Sandstone 
Deleted 
256.8 1 east of Ozark, AR 
292.8 7 east of Fort Smith, 
AR 
110 by 600 
110 by 600 
34 372 
20 392 
18 15 Sandstone 
and 
shale 
18 14 Sandstone 
and 
shale 
Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
Movable Gated concrete 
spillway with 
embankment 
ends 
1969 38,045,000 
1969 84,270,124 
1969 85,629,412 
1969 56,279,000 
1969 $45,878,000 
1969 57,828,000 
0
>:

TABLE 28-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Miles Elevation Depth on Char- Year 
Up- Upper Miter Sill acter Opened 
stream Lock Pool of to To 
form Miles to Dimension Lift (feet, Upper Lower Foun- Kind of Type of Naviga- Esti 
Feature Mouth Nearest Town (feet) (feet) MSL) (feet) (feet) dation Dam Construction tion Ci 
TULSA DISTRICT3 
James W. Trimble 
Lock and Dam 
(No. 13) (part) 
W.D. Mayo Lock 
and Dam (No. 14) 
Robert S. Kerr Lock 
and Dam (No. 15) 
Webbers Falls Lock 
and Dam (No. 16) 
Chouteau Lock and 
Dam (No. 17) 
1970 $6,858,000 
319.6 4 east of Redland, 
OK 
336.2 1 north of Cowlington, 
OK 
366.6 1 northwest of Gore, 
OK 
401.4 4 northwest of Okay, 
OK 
Newt Graham Lock 421.6 8 southwest of Inola, 
and Dam (No. 18) OK 
110 by 600 20 
110 by 600 48 
412 
460 
110 by 600 30 490 
110 by 600 
14 15 Rock Movable 
18 14 Rock Movable 
19 16 Rock Movable 
21 511 15 14 Rock Movable 
110 by 600 21 532 15 14 Rock Movable 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
Gated concrete 
spillway with 
embankment 
ends 
1970 32,655,000 
1970 94,578,237 
1970 83,738,277 
1970 31,619,000 
1970 44,355,000 
)tal 
nated 
ost 
00 
0
O
0
7d 
O
n
r
0
r
0
0 
----

TABLE 28-H 
(Continued) 
ARKANSAS RIVER BASIN; AR, OK, AND KS: NAVIGATION 
(See Section 1 of Text) 
Additional features entering into cost of project 
Little Rock District: 
Bank stabilization and channel rectification, mile 33.7 to 362 and 
Arkansas-White Cutoff, 100 percent complete ............ $119,300,184 
Maintenance and repair fleet and marine terminals, 
complete ................................ 7,497,000 
Total, Little Rock District ....................... 814,362,720 
Navigation aids (U.S. Coast Guard) ....................... 2,268,000 
Tulsa District: 
Bank stabilization and channel rectification, Short Mountain 
to Fort Smith, complete ............................. 12,700,038 
Maintenance and repair fleet and marine terminals, 
complete ........................................ 2,750,000 
Subtotal ......................................... $309,253,552 
Upstream Lakes:2 
Oologah, 90.2 miles upstream from mouth, Verdigris River 
complete ......................................... $46,722,329 
Keystone, 638.8 miles upstream from mouth, Arkansas River, 
complete .......................................... 123,170,773 
Eufaula, 27 miles upstream from mouth, Canadian River, 
complete ........................................ 124,130,747 
Subtotal ....................................... 294,023,849 
Total, Tulsa District .......................... 603,277,401 
Total Project Cost 96 percent complete ........... $1,419,908,121 
1. Navigation mileage from mouth of White River, except Dam No. 2, is 40.5 miles above mouth of Arkansas River. 
2. Details in Tulsa District report. 
r
O
nI 
v
M 1 
l3

Table 28-I ARKANSAS RIVER BASIN; AR, OK, AND KS: LAKES 
(See Section 1 of Text) 
Miles Drainage Height Reservoir Power Year or To 
Above Area of Dam Capacity Development Percent Estin 
Lake and State River Mouth Nearest Town (sq mi) (feet) Type (acre-feet) (kilowatts) Complete C 
Blue Mountain, AR Petit Jean 74.4 Paris, AR 488 115 Earthfill 257,900 - 1947 $ 5,06 
Canton, OK North Canadian 384.3 Canton, OK 12,483 68 Earthfill 383,300 1948 11,20 
Elk City, KS Elk 8.7 Independence, KS 634 107 Earthfill 284,300 _ 1966 19,05 
(Table Mound) 
Eufaula, OK 1 2 Canadian 27.0 Eufaula, OK 47,522 114 Earthfill 3,798,000 90,000 1964 123,35 
Fall River, KS Fall 54.2 Fall River, KS 585 94 Earthfill 256,400 1949 10,55 
Fort Gibson, OK' Grand (Neosho) 7.7 Fort Gibson, OK 12,492 110 Concrete- 1,284,400 45,000 1953 42,59 
Keystone, OK 1 2 3 Arkansas 538.8 Sand Springs, OK 74,506 121 gravity 1,836,500 70,000 1964 123,17 
Markham Ferry, OK1 I Grand (Neosho) 47.4 Pryor, OK 11,533 90 Earthfill 444,500 100,000 1968 6,90 
Neodesha, KSS Verdigris 222.8 Neodesha, KS 1,152 74 Earthfill 90,000 - 0 9 
Nimrod, AR Fourche La Fave 62.6 Plainview, AR 680 103 Earthfill 336,010 _ 1942 4,09 
Oologah, OK2 Verdigris 90.2 Claremore, OK 4,339 137 Concrete- 1,519,000 - 1974 46,72 
Pensacola, OK1 ( Grand (Neosho) 77.0 Disney, OK 10,298 147 gravity 2,197,000 86,400 1940 5 
Tenkiller Ferry, OKi 3 Illinois 12.8 Gore, OK 1,610 197 Earthfill 1.230,800 34,000 1953 24,01 
Toronto, KS Verdigris 271.5 Toronto, KS 730 90 Concrete arch 199,700 1960 13,89 
Wister, OK Poteau 60.9 Wister, OK 993 99 Earthfill 427,900 1949 10,50 
Subtotal, exclusive of Eufaula, Keystone, and Oologah. 148,0 
Arkansas River Basin; AR, OK and KS: Navigation (Table 28-H). 1,419,9 
Total, Arkansas River Basin, 96 percent complete. 1,567,9 
)tal 
nated 
ost 
9,974 
9,834 
2,990 
0,791 
0,873 
1,298 
1,173 
8,756 
7,910 
2,826 
!2,329 
2,126 
7,724 
6,324 
11,226 
41,861 
08,121 
49,982 
1. Project includes facilities for production of hydroelectric power. 
2. Cost included in navigation project. 
3. Details in Tulsa District report. 
4. Constructed by State of Oklahoma under the name of Robert S. Kerr Dam (Lake Hudson). Estimate shown is for Federal participation 
5. Inactive. Estimate is based on 1954 price levels. 
6. Constructed by State of Oklahoma under the name Grand River Dam (Lake O'The Cherokees). Estimate shown is for Federal participation. 
No00 
00

LITTLE ROCK, AR DISTRICT 
TABLE 28-J LITTLE RIVER BASIN, AR: LAKES 
(See Section 26 of Text) 
Project River Sitel Nearest Town 
DeQueen Lakel Rolling Fork River 22.8 DeQueen, AR 
Gillham Lake' Cossatot River 49.0 Gillham, AR 
Dierks Lake' Saline River 56.6 Dierks, AR 
Millwood Lake' Little River 16.0 Millwood, AR 
1. Project is reported separately herein. 
28-29

WHITE RIVER BASIN; AR, AND MO: LAKES 
TABLE 28-K (See Section 34 of text) 
Miles Drainage Reservoir Power Tot; 
Above Area Height of Dam Above Streambed Capacity Development Estim; 
Lake River Mouth Nearest Town (sq mi) and Type (acre-feet) (kilowatts) Cos 
Beaver' White 609.0 Eureka Springs, AR 1,186 228 feet concrete-gravity and earthfill 1,952,000 112,000 $ 52,6 
Bell Foley2 Strawberry 27.2 Poughkeepsie, AR 519 136 feet concrete-gravity and earthfill 518,000 93,7 
Bull Shoals White 418.6 Mountain Home, AR 6,036 258 feet concrete-gravity 5,408,000 340,000 96,3 
Clearwater' Black 257.4 Piedmont, MO 898 154 feet earthfill 413,000 _ 22,4 
Greers Ferry' Little Red 79.0 Heber Springs, AR 1,146 243 feet concrete-gravity 1,844,000 96,000 55,1 
Norfork' North Fork 4.8 Norfork, AR 1,806 216 feet concrete-gravity 1,983,000 80,550 111,6 
Table Rock' White 523.8 Branson, MO 4,020 252 feet concrete-gravity and earthfill 3.462.000 200.000 71,2 
Total 15,580,000 828,550 503,0 
1. For details see individual reports. 
2. Inactive--placed in a deferred status in May 1985. Estimate based on 1983 price levels. 
al 
ated 
ti 
31,472 
00,000 
56,000 
62,553 
25,000 
i24,000 
33,000 
)69,472 
00 
o

TULSA, OKLAHOMA, DISTRICT* 
The civil works portion of this District covers an area 
of approximately 160,000 square miles which includes 
Oklahoma and parts of Kansas and Texas within the 
Arkansas and Red River Basins. The District's 
responsibilities within the Arkansas River Basin cover 
southern Kansas, northern Oklahoma, and the Texas 
Panhandle. These areas are embraced in the drainage 
basin of the Arkansas River and its tributaries above the 
mouth of the Poteau River, 
extending to the Kansas-Colorado State line, exclusive of 
that portion of the South Canadian River Basin and its 
tributaries west of the Texas-New Mexico State line. The 
District's responsibilities within the Red River Basin 
cover the northern portion of Texas, and the southern 
portion of Oklahoma. These areas are embraced in the 
drainage basin of the Red River and its tributaries above 
Fulton, AR. 
IMPROVEMENTS 
Navigation 
1. McClellan-Kerr Arkansas River 
Navigation System, OK 
2. OtherAuthorizedNavigationProj ects 
Flood Control 
3. Arcadia Lake, OK 
4. Arkansas-Red River Basins Chloride 
Control Projects, KS, OK, and TX 
4a. Area V, Estelline Springs 
4b. Area VIII 
4c. Red River Basin Chloride 
Control, TX & OK 
5. Birch Lake, OK 
6. Candy Lake, OK 
7. Canton Lake, OK 
8. Copan Lake, OK 
9. Council Grove Lake, KS 
10. El Dorado Lake, KS 
11. Elk City Lake, KS 
12. Fall River Lake, KS 
13. Fort Supply Lake, OK 
14. Great Bend, KS 
15. Great Salt Plains Lake, OK 
16. Halstead, KS 
17. Heyburn Lake and Polecat Creek, OK 
18. Hugo Lake, OK 
19. Hulah Lake, OK 
20. John Redmond Dam and Reservoir, KS 
29-2 
29-2 
29-2 
29-3 
29-3 
29-3 
29-4 
29-4 
29-4 
29-4 
29-4 
29-5 
29-5 
29-5 
29-5 
29-5 
29-5 
29-6 
29-6 
29-6 
29-6 
29-6 
29-7 
21. Kaw Lake, OK 
22. Lake Kemp, TX 
23. Lake Wichita, Holliday Creek, TX 
24. Marion Reservoir, KS 
25. Mingo Creek, OK 
26. Oologah Lake, OK 
27. Optima Lake, OK 
28. Parker Lake, OK 
29. Pat Mayse Lake, TX 
30. Pearson-Skubitz Big Hill Lake, KS 
31. Pine Creek Lake, TX 
32. Sardis Lake, OK 
33. Skiatook Lake, OK 
34. Toronto Lake, KS 
35. Tulsa & West Tulsa, OK 
36. Waurika Lake, OK 
37. Wister Lake, OK 
38. Other Authorized Flood Control Projects 
39. Inspection of Completed Local 
Flood Protection Projects 
40. Scheduling Flood Control 
Reservoir Operations 
41. Emergency Flood Control Activities 
42. Flood Control Work Under 
Special Authorization 
29-1 
Page 
29-7 
29-7 
29-7 
29-7 
29-7 
29-8 
29-8 
29-8 
29-8 
29-9 
29-9 
29-9 
29-9 
29-9 
29-9 
29-10 
29-10 
29-10 
29-10 
29-10 
29-10 
29-10 
29-10

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1992 
Multiple-Purpose Projects Including Power Tables 
43. Broken Bow Lake, OK 
44. Eufaula Lake, OK 
45. Fort Gibson Lake, OK 
46. Keystone Lake, OK 
47. Lake Texoma (Denison Dam), OK and TX 
48. Robert S. Kerr Lock and Dam 
and Reservoir, OK 
49. Tenkiller Ferry Lake, OK 
50. Webbers Falls Lock and Dam, OK 
General Investigations 
51. 
52. 
53. 
Surveys 
Collection and Study of Basic Data 
Preconstruction Engineering and Design 
29-10 29-A Cost and Financial Statement 
29-11 29-B Authorizing Legislation 
29-11 29-C Other Authorized Navigation Projects 
29-11 29-D Not Applicable 
29-11 29-E Other Authorized Flood Control Projects 
29-F Not Applicable 
29-11 29-G Deauthorized Projects 
29-12 29-H Arkansas River Basin 
29-12 Multiple-Purpose Plan 
29-I Inspection of Completed Local 
Flood Protection Projects 
29-J Flood Control Work Under 
29-12 Special Authorization 
29-K General Investigations 
29-12 
Navigation 
1. McCLE LL AN-KERR ARKANSAS 
RIVER NAVIGATION SYSTEM 
(Tulsa District Portion), OK. 
Location. The Tulsa District portion of the McClellan- 
Kerr Arkansas River Navigation System provides a 
navigation route up the Arkansas River from the 
Oklahoma-Arkansas State line to the head of navigation 
at Catoosa, OK, near Tulsa, OK. The total length of the 
Tulsa District portion of the system is 137 navigation 
miles. Descriptions and costs for the entire navigation 
system can be found in Little Rock District's entry in this 
Annual Report. 
Existing projects. The McClellan-Kerr Arkansas 
River navigation project is a component of the multiplepurpose 
plan for the Arkansas River Basin which provides 
for the improvement of the basin through the 
construction of coordinated developments for navigation, 
hydroelectric power, flood control, water supply, 
water quality control, sediment control, recreation, and 
fish and wildlife propagation. The McClellan-Kerr project 
consists of bank stabilization, channel straightening, 
and cutoffs as required. The navigation channel has a 
minimum depth of 9 feet and minimum widths of 250 feet 
on the Arkansas River and 150 feet on the Verdigris 
River. The Tulsa District portion of the navigation 
system consists of Arkansas River Bank Stabilization 
and Channel Rectification, Chouteau Lock and Dam, 
Newt Graham Lock and Dam, Robert S. Kerr Lock and 
Dam and Reservoir, Robert S. Kerr Marine Terminal, 
Sans Bois Navigation Channel, W.D. Mayo Lock and 
Dam, Webbers Falls Lock and Dam, and the pool in 
Oklahoma which was created by Lock and Dam 13 in 
Arkansas. The other parts of the multiple-purpose plan 
for the Arkansas River Basin are listed in Table 29-H. 
Local cooperation. Fully complied with. 
Terminal facilities. Public port facilities are in 
operation at Muskogee and Catoosa, OK, and at Fort 
Smith, AR. At Sallisaw, OK, a port authority has been 
active in seeking development of public facilities at that 
location. Other private commercial port facilities are 
complete and in operation at eight Oklahoma locations. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
2. OTHER AUTHORIZED NAVIGATION 
PROJECTS. 
See Table 29-C. 
Flood Control 
3. ARCADIA LAKE, OK 
Location. On the Deep Fork River at river mile 218.3 
in the metropolitan area of Oklahoma City and Edmond, 
OK, about 1.5 miles west of Arcadia, in Oklahoma County, 
OK. (See Arcadia, OK, Geological Survey map, scale 
1:24,000.) 
29-2 
29-13 
29-20 
29-23 
29-24 
29-25 
29-26 
29-27 
29-27 
29-29

TULSA, OKLAHOMA, DISTRICT 
Existing project. The plan of improvement provides 
for flood control, water supply, and recreation by construction 
of an earthfill dam approximately 102 feet high 
and 5,250 feet long with a high-level uncontrolled 
spillway. Outlet works consist of a gated tower and 
conduit. The lake has a total capacity of 92,000 acre-feet 
(27,380 for conservation, 64,430 for flood control, and 190 
for sedimentation reserve), and controls a 105-squaremile 
drainage area. Construction began in October 1980 
and the project became operational for flood control in 
November 1986. 
Local cooperation. Section 2 of the Flood Control Act 
of 1938, the Water Supply Act of 1958, the Federal Water 
Project Recreation Act of 1965, and Section 221 of the 
Flood Control Act of 1970 apply. 
Operations and results during fiscal year. The 
project is 99 percent complete. Estimated cost is 
$93,100,000 (October 1990 price level base). Funds of 
$100,000 were transferred to the project in FY 92. 
Remaining recreation is unscheduled. The United States 
filed suit February 14, 1989, to seek enforcement of the 
local cooperation requirements. However, the issue was 
mutually resolved by a Consent Decree entered into 
CIV 89-1507-A in United States District Court for the 
Western District of Oklahoma, on February 10,1992. The 
Decree was for the City of Edmond and the Edmond 
Public Works Authority to reimburse the Government 
$7,207,636 over a period of 40 years for the recreation 
contract and $16,253,644 for the water supply contract 
over a period of 43 years. 
4. ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL PROJECTS, KS, 
OK, AND TX 
Location. On certain tributary streams of the Arkansas 
and Red Rivers in the western half of the Tulsa 
District. 
Existing project. Provided for studies involving the 
control of water pollution caused by 15 natural salt 
sources identified in 1957 by the U.S. Public Health 
Service. The Arkansas and the Red Rivers represent 
major national and regional water resources severely 
limited due to poor water quality primarily caused by the 
natural pollutant, sodium chloride. The Arkansas River 
is polluted by five naturally occurring salt sources 
located in northwestern Oklahoma and southwestern 
Kansas. The Red River Basin is polluted by ten naturally 
occurring salt sources located in northwestern Texas and 
southwestern Oklahoma. These studies included the 
construction and subsequent maintenance of an injection 
well and a ring dike used for data collection. 
Preauthorization studies completed in 1966 and 1970 
recommended construction of project features at 13 of the 
15 sites. For a detailed discussion of the chloride control 
projects, see the page 19-4 of the Annual Report for 1983. 
The Water Resources Development Act of 1986 (PL99- 
662) authorized the Red River Basin and the Arkansas 
River Basin as separate projects with separate authority 
under Section 203 of the Flood Control Act of 1966. The 
Arkansas River portion of the project was deferred in 
1982 (not economically justified). 
4a. AREA V, ESTELLINE SPRINGS. 
Location. Chloride Control Area V is located about 0.5 
mile east of Estelline,TX, on the Prairie Dog Town Fork 
of the Red River. 
Existing project. For a description of the completed 
improvement, see the Annual Report for 1987. Construction 
started in 1963 and the structure was completed in 
1964. 
Local cooperation. Descriptive text concerning local 
cooperation requirements is given on page 19-5 of the 
Annual Report for 1983. 
4b. AREA VIII 
Location. Chloride Control Area VIII is located at 
river mile 74.9 of the South Fork of the Wichita River in 
King County, TX, about 5 miles east of Guthrie, TX. 
Existing project. The plan of improvement consists of 
two low-flow collection dams with attendant pumping 
stations and pipeline facilities. These two dams (the 
Bateman Low Flow Dam and the Ross Ranch Low Flow 
Dam) would be equipped with an inflatable fabric-type 
weir located in the spillway section which would be 
deflated to pass relatively good quality high flows. The 
collected brine would be pumped to the storage reservoir 
behind the Truscott Brine Dam. This brine dam, located 
at river mile 3.6 on Bluff Creek (a tributary of the North 
Fork of the Wichita River) about 3 miles northwest of 
Truscott, TX, would contain the collected brine from this 
area as well as future collections from Area X. Construction 
was initiated at Area VIII and Truscott Brine Dam 
in 1976. The first of the two low-flow dams was completed 
and put into full operation in May 1987. The second was 
to be constructed after initial operation of the first to 
determine the effectiveness of the operation. 
Local cooperation. Descriptive text concerning local 
cooperation requirements is given on page 19-5 of the 
Annual Report for 1983. 
Operations and results during fiscal year. The 
Water Resources Development Act of 1986 authorized 
construction of the remaining areas of the Red River 
Chloride Control project pending transmittal of a report 
of a favorable finding of the effectiveness of the operation 
of Area VIII. Public Law 99-662 established a panel to 
assess the improvement in water quality downstream of 
29-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1992 
Area VIII as a measure of its effectiveness. A favorable 
report was submitted by the panel to the Secretary of the 
Army (CW) and to the Public Works Committees of the 
House and Senate in August 1988. 
4c. RED RIVER BASIN CHLORIDE CONTROL, 
TX & OK 
Location. The project is located in Cottle, Hall and 
King Counties, Texas and Harmon County, Oklahoma, 
along the Wichita and Red River. AreaVI is located on 
the Elm Fork of the Red River in Harmon County, 
Oklahoma; AreaVII is on the North Fork of the Wichita 
River, Cottle County, Texas; Crowell Brine Dam is on 
Canal Creek, a tributary of the Pease River; Area IX is on 
the Middle Pease River, Cottle County, Texas; Area X is 
on the Middle Fork of the Wichita River, King County, 
Texas; and Areas XIII-XIV are on the Jonah and Salt 
Creeks of Prairie Dog Town Fork of the Red River, Hall 
County, Texas. 
Existing project. The plan of improvement consists 
of 1 deep-well injection system, 3 brine storage reservoirs, 
4 low-flow brine collection dams, 2 well collection 
facilities, 6 pumping plants, and 56.3 miles of pipeline. 
Construction was initiated at Area X, low-flow dam, 
pump station and access road in 1991. Construction is 
scheduled to be completed in April 1993. A Limited 
Reevaluation Report containing a project economic reevaluation 
has been submitted for review. Construction 
funds of $6,000,000 were provided by Congress for FY 93. 
Local Cooperation. The Water Resources Development 
Act authorized the project at full Federal expense. 
Operation and results during fiscal year. 
Estimated cost of the project is $204,000,000 (October 
1992 price level base). The contract for Area X was 
awarded September 27, 1991. 
5. BIRCH LAKE, OK. 
Location. On Birch Creek at river mile 0.8, about 1.5 
miles south of Barnsdall in Osage County, OK. (See 
Barnsdall, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see the Annual Report for 1979. Construction 
began in November 1973 and the project was placed 
in useful operation in March 1977. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
6. CANDY LAKE, OK. 
Location. On Candy Creek, a tributary of Bird Creek 
in the Verdigris River Basin, at river mile 1.9. The 
damsite is about 1.5 miles northeast of Avant in Osage 
County, OK. (See Avant, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. The plan of improvement provides 
for an earthfill dam about 4,200 feet long, including an 
uncontrolled concrete spillway, with a maximum height 
of 103 feet above streambed. Outlet works will consist of 
a gated intake structure, a 10-by 11.25-foot conduit, and 
a stilling basin. An 18-by 24-inch low-flow pipe and an 
18-inch water supply pipe will be provided. The lake will 
have a total capacity of 75,420 acre-feet (44,160 for 
conservation and sediment reserve and 31,260 for flood 
control). The drainage area above the damsite is 43 
square miles. Candy Lake will be operated as a unit of a 
seven-lake system for flood control in the Verdigris River 
Basin in Oklahoma. Construction began in September 
1976. 
Local cooperation. Section 2 of the Flood Control Act 
of 1938, the Water Supply Act of 1958, and Section 221 of 
the Flood Control Act of 1970 apply. 
Operations and results during fiscal year. The 
project was about 13 percent complete when construction 
was delayed because the U.S. Justice Department 
decided to withdraw condemnation proceedings to 
acquire mineral rights. Estimated cost of the project was 
$38,300,000 (October 1984 price level base). The project 
was deferred in January 1984. Project land has been 
made available for low intensity recreation use. Routine 
operation and maintenance continued. 
7. CANTON LAKE, OK. 
Location. On the North Canadian River at river mile 
394, about 2 miles north of Canton in Blaine County, OK. 
(See Canton, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 590 of the Annual Report for 
1969. Construction began in December 1940 and the 
project was placed in useful operation in April 1948. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
8. COPAN LAKE, OK. 
Location. On the Little Caney River, a tributary of the 
Caney River in the Verdigris River Basin, at river mile 
29-4

TULSA, OKLAHOMA, DISTRICT 
7.4, about 2 miles west of Copan in Washington County, 
OK. (See Copan, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-7 of the Annual Report for 
1983. Copan Lake is operated as a unit of a seven-lake 
system for flood control in the Verdigris River Basin in 
Oklahoma. Construction began in November 1972 and 
the project was placed in useful operation in April 1983. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
9. COUNCIL GROVE LAKE, KS. 
Location. On the Grand (Neosho) River at river mile 
450, about 1.5 miles northwest of Council Grove in Morris 
County, KS. (See Council Grove Lake, KS, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 519 of the Annual Report for 
1969. Construction began in June 1959 and the project 
was placed in useful operation in July 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
10. EL DORADO LAKE, KS. 
Location. On the Walnut River, a tributary of the 
Arkansas River, at river mile 100.2, about 4 miles northeast 
of El Dorado in Butler County, KS. (See El Dorado, 
KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-7 of the Annual Report for 
1983. El Dorado Lake was authorized as a unit of a threelake 
system for flood control in the Walnut River Basin. 
Construction began in October 1973, and impoundment 
began in June 1981. Project is complete. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
11. ELK CITYLAKE, KS 
Location. On the Elk River at river mile 8.7, about 7 
miles northwest of Independence in Montgomery County, 
KS. (See Table Mound, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 593 of the Annual Report for 
1969. Construction began in February 1962 and the 
project was placed in useful operation in March 1966. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
12. FALL RIVER LAKE, KS. 
Location. On the Fall River at river mile 54.2, about 
4 miles northwest of Fall River in Greenwood County, 
KS. (See Severy, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 953 of the Annual Report for 
1969. Construction began in May 1946 and the project 
was placed in full operation in April 1949. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
13. FORT SUPPLY LAKE, OK. 
Location. On Wolf Creek, a tributary of the North 
Canadian River, at river mile 5.5, about 12 miles northwest 
of Woodward in Woodward County, OK. (See Fort 
Supply, OK, Geological Survey Map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 594 of the Annual Report for 
1969. Construction began in October 1938 and the 
project was placed in full flood control operation in May 
1942. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
14. GREAT BEND, KS. 
Location. In Barton County, KS, on the north bank of 
the Arkansas River about 4.5 miles above its confluence 
with Walnut Creek. (See Great Bend, KS, Geological 
Survey map, scale 1:24,000.) 
Existing project. The plan, authorized by the Flood 
Control Act of 1965, provides for 6.2 miles of leveed 
channel to divert Walnut Creek flood flow around Great 
Bend into the Arkansas River upstream from the city; a 
1.5-mile leveed channel to divert Little Walnut Creek 
29-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1992 
flood flow into the Walnut Creek diversio n levees along 
the Arkansas; a tie-back levee 4.3 miles long on the 
Arkansas left bank upstream from the junction of the 
Walnut diversion channel; and appurtenant facilities. 
Local cooperation. In accordance with the cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, the city of Great 
Bend, KS, agreed to participate in project construction. 
Operations and results during fiscal year. 
Estimated cost of the project is $36,900,000 (October 
1992 price level base). The contract for Phase III was 
awarded July 7, 1991. Project completion is scheduled 
for August 1993. 
15. GREAT SALT PLAINS LAKE, OK. 
Location. On the Salt Fork of the Arkansas River at 
river mile 103.3, about 12 miles east of Cherokee in 
Alfalfa County, OK. (See Jet, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 594 of the Annual Report for 
1969. Construction of the project began in September 
1938 and was completed in July 1941. The project was 
placed in full flood control operation in May 1941. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
16. HALSTEAD, KS. 
Location. In the city of Halstead in Harvey County, 
KS, along the Arkansas River. (See Halstead, KS, 
Geological Survey Map, scale 1:24,000.) 
Existing project. Provides for channel modification 
and construction of about 4 miles of levee in combination 
with clearing and snagging and straightening and widening 
approximately 3.6 miles of the Little Arkansas 
River channel to a 50-foot-bottom width in the vicinity of 
Halstead. Channel modification will be restricted to one 
side of the channel except in transition areas. Tree 
planting and revegetation will be done and ten pool riffle 
areas will be established to minimize environmental 
impacts. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Funds 
provided in FY 92 were used to continue construction. 
The Local Cooperation Agreement was signed in October 
1989. Estimated project cost is $11,100,000 (October 
1992 price level base). 
17. HEYBURN LAKE AND POLECAT 
CREEK, OK. 
Location. On Polecat Creek, a minor tributary of the 
Arkansas River, at river mile 48.6, about 11 miles west 
of Sapulpa in Creek County, OK. (See Lake Heyburn, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 599 of the Annual Report for 
1969. Construction started in March 1948 and the 
project was placed in useful operation in October 1950. 
Channel improvements below the lake were completed 
in September 1952. 
Local cooperation. The channel improvement project 
below the lake was never maintained by the sponsor, 
Joint Drainage District N o. 1, Tulsa and Creek Counties, 
Oklahoma. For this reason, the channel returned to its 
pre-project condition and does not provide flood protection 
for the affected area. The Corps of Engineers 
discontinued maintenance inspections of the channel 
project in 1982 due to the condition of the project and lack 
of cooperation on the part of the sponsor. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
18. HUGO LAKE, OK. 
Location. On the Kiamichi River at river mile 17.6, 
about 7 miles east of Hugo in Choctaw County, OK. (See 
Hugo Dam, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-12 of the Annual Report for 
1977. Construction began in October 1967 and the 
project was placed in useful operation in January 1974. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
19. HULAH LAKE, OK. 
Location. On the Caney River at river mile 96.2, 
about 15 miles northwest of Bartlesville, near Hulah, in 
Osage County, OK. (See Bowring, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 595 of the Annual Report for 
1969. Construction began in May 1946 and was completed 
in June 1950. The project was placed in full flood 
control operation in September 1951 
Local cooperation. Fully complied with. 
29-6

TULSA, OKLAHOMA, DISTRICT 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
20. JOHN REDMOND DAM AND 
RESERVOIR, KS. 
Location. The dam is located on the Grand (Neosho) 
River at river mile 343.7, about 2 miles northwest of 
Burlington in Coffey County, KS. (See John Redmond 
Dam, KS, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 581 of the Annual Report for 
1970. Construction was initiated in July 1959 and was 
completed in December 1965. The project was placed in 
flood control operation in July 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
21. KAW LAKE, OK. 
Location. On the Arkansas River at river mile 653.7, 
about 8 miles east of Ponca City in Kay County, OK. (See 
Charley Creek West, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-13 of the Annual Report for 
1977. Construction began in June 1966 and the project 
was placed in operation in May 1976. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
22. LAKE KEMP, TX. 
Location. On the Wichita River at river mile 126.7, 
about 40 miles southwest of Wichita Falls, TX. (See 
Northeast Lake Kemp, TX, Geological Survey Map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-14 of the Annual Report for 
1977. Construction began in May 1970 and the project 
was placed in useful operation in October 1972. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
23. LAKE WICHITA, 
HOLLIDAY CREEK, TX. 
Location. The project is located in Wichita and Archer 
Counties, TX. The Lake Wichita dam and the Holliday 
Creek channel are located in the city of Wichita Falls, TX. 
(See Wichita Falls, TX, Geological Survey Map, scale 
1:24,000.) 
Existing project. The proposed plan includes the 
replacement of the existing Lake Wichita dam with an 
earthen dam approximately 16,000 feet long, a concrete 
spillway, an auxiliary spillway, and low-flow outlet works. 
The plan also includes channel improvements along 
Holliday Creek from the new spillway to the Wichita 
River, a distance of 9.3 miles. 
Local cooperation. The city has essentially 
completed their requirements for local cooperation in 
accordance with the cost sharing and financing concepts 
reflected in the Water Resources Development Act of 
1986. 
Operations and results during fiscal year. The 
Phase III contract was awarded in August 1992 and 
construction was initiated in Nov 1992. Estimated 
project cost is $48,200,000 (October 1992 price level 
base). 
24. MARION RESERVOIR, KS. 
Location. On the Cottonwood River at river mile 
126.7, about 3 miles northwest of Marion in Marion 
County, KS. (See Pilson, KS, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 597 of the Annual Report for 
1969. Construction began in June 1964 and the project 
was placed in flood control operation in February 1968. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
25. MINGO CREEK, OK. 
Location. On the right-bank tributary of Bird Creek 
in Tulsa County, OK. (See Tulsa, OK, Geological Survey 
Map, scale 1:24,000.) 
Existing project. The recommended plan will consist 
of 23 detention sites which would capture peak flows and 
hold them temporarily until downstream flows subside. 
There would be about 9.4 miles of channelization in 
selected locations on the tributaries and main stem of 
29-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1992 
Mingo Creek. This plan will provide a minimum of 65- 
year protection in the major damage area. 
Local cooperation. In accordance with the cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, the non-Federal 
sponsor must provide lands, easements, rights-of-way, 
and dredged material disposal areas; modify or relocate 
buildings, utilities, roads, bridges (except railroad 
bridges), and other facilities where necessary in the 
construction of the project; pay five percent of the costs 
allocated to flood control; and bear all costs of operation, 
maintenance, and replacement of flood control facilities. 
The non-Federal sponsor has also agreed to make all 
required payments concurrently with project construction. 
The local sponsor is the city of Tulsa, OK. On 
August 26, 1983, the city of Tulsa adopted a Resolution 
of Assurance to provide a minimum share equal to 35 
percent or the traditional lands, easements, and rightsof-
way, whichever is greater, and will be required to 
assist in the actual financing of construction. The city 
has constructed 4.75 miles of channel and placed two 
excavated detention facilities into flood control operation 
prior to initiation of federal construction in September 
1988. The project is currently 38% complete. 
Operations and results during fiscal year. One 
reimbursement for work completed by the city of Tulsa 
was made for $8,232,000. Estimated project cost is 
$143,300,000 (October 1992 price level base). 
26. OOLOGAH LAKE, OK. 
Location. On the Verdigris River at river mile 90.2, 
about 2 miles southeast of Oologah in Rogers County, 
OK. (See Oologah, OK, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-15 of the Annual Report for 
1972. Construction began in July 1950, but the project 
was placed in standby status in October 1951. Construction 
resumed in December 1955 and was completed in 
May 1963 for initial development. Construction, for 
ultimate (second stage) development was initiated in 
July 1967 and was completed in 1974. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
27. OPTIIMA LAKE, OK. 
Location. On the North Canadian River at river mile 
623.2, about 4.5 miles northeast of Hardesty in Texas 
County, OK. (See Optima Dam, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the existing 
improvement, see page 19-16 of the Annual Report for 
1979. Construction began in March 1966 and impoundment 
began in October 1978. Construction was 
completed in 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
28. PARKER LAKE, OK. 
Location. On Muddy Boggy Creek, a tributary of the 
Red River, about 23 miles east of Ada in Coal County, OK. 
(See Parker, OK, Geological Survey map, scale 1:24,000.) 
Existing project. Parker Lake, when constructed, 
will be a multipurpose element in a plan of improvement 
for the Upper Muddy Boggy Creek Basin, OK. The 
project consists of an earthfill dam about 2,200 feet long, 
a gated outlet works for flood control and water supply, 
and a 100-foot-wide spillway. The lake created would 
have a total storage capacity of 220,240 acre-feet and 
would yield 42 million gallons per day for municipal and 
industrial water supply. The project was authorized by 
the Water Resources Development Act of 1986. 
Local cooperation. The Oklahoma Water Resources 
Board, the sponsor, has agreed to cost share in the flood 
control portion of the project if enough interested users 
for the water supply can be identified. 
Operation and results during fiscal year. Work 
in FY 92 included continued coordination with the sponsor. 
Estimated project cost is $71,400,000 (October 1992 
price level base). 
29. PAT MAYSE LAKE, TX. 
Location. On Sanders Creek, a tributary of the Red 
River, at river mile 4.6, about 12 miles north of Paris in 
Lamar County, TX. (See Grant, TX, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 584 of the Annual Report for 
1970. Construction began in March 1965 and the project 
was placed in full flood control operation in September 
1967. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
29-8

TULSA, OKLAHOMA, DISTRICT 
30. PEARSON-SKUBITZ BIG HILL 
LAKE, KS. 
Location. On Big Hill Creek at river mile 33.3, about 
4.5 miles east of Cherryvale, KS. (See Dennis, KS, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-11 of the Annual Report for 
1983. Construction began in April 1974 and impoundment 
began in March 1981. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
31. PINE CREEK LAKE, OK. 
Location. On the Little River at river mile 145.3, 
about 5 miles northwest of Wright City in McCurtain 
County, OK. (See Wright City, OK, Geological Survey 
map, scale 1:24,000. 
Existing project. For a description of the completed 
improvement, see page 584 of the Annual Report for 
1970. Construction began in February 1963 and the 
project was placed in useful operation in June 1969. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
32. SARDIS LAKE, OK. 
Location. On Jackfork Creek, a tributary of the 
Kiamichi River, at river mile 2.8, about 2.5 miles north 
of Clayton in Pushmataha County, OK. (See Yanush, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-11 of the Annual Report for 
1983. Sardis Lake is operated as a unit of a two-lake 
system for flood control in the Kiamichi River Basin. 
(The other lake in the system is Hugo Lake). Construction 
began in August 1975 and the project became operational 
in January 1983. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
33. SKIATOOK LAKE, OK. 
Location. On Hominy Creek, a tributary of Bird 
Creek in the Verdigris River Basin, at river mile 14.3, 
about 5 miles west of Skiatook in Osage County, OK. (See 
Avant S.E., OK, Geological Survey map, scale 1;24,000.) 
Existing project. For a description of the completed 
improvement, see Page19-8 of the Annual Report for 
1987. Construction began in January 1974, impoundment 
began in October 1984, and the project became 
operational in November 1984. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
34. TORONTO LAKE, KS. 
Location. On the Verdigris River at river mile 271.5, 
about 4 miles southeast of Toronto in Woodson County, 
KS. (See Fredonia, KS, Geological Survey map, scale 
1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 600 of the Annual Report for 
1969. Construction began in November 1954 and the 
project was placed in full operation in March 1960. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
35. TULSA AND WEST TULSA, OK. 
Location. On the banks of the Arkansas River near 
Tulsa, Oklahoma. On the left bank, the levee extends 
from river mile 531.0 near Sand Springs, Oklahoma, 
downstream to river mile 521.4 at Tulsa. On the right 
bank, the levee extends from near river mile 526.7 
downstream to river mile 521.3 and is adjacent to the 
major portion of the business and residential districts in 
West Tulsa, Tulsa County, Oklahoma. 
Existing project. The Tulsa and West Tulsa levees 
were completed by the Tulsa District in 1945. The project 
was turned over to the Tulsa County Drainage District 
No. 12 for operations and maintenance. The project 
consists of 3 levees with a total length of about 20 miles 
and an average height of 10 feet. The levees provide 
protection from flooding to property valued at approximately 
$1.0 billion dollars. Many of the pipes that pass 
under the levee have deteriorated and levee material has 
eroded into the pipes leaving small cavities in the embankment. 
The Tulsa District completed an evaluation 
29-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1992 
of the levees in September 1989 which determined that 
rehabilitation would be required for the levees to operate 
as designed. 
Local cooperation. The LCA was executed in March 
1992 and Tulsa County and Levee District No. 12, the 
non-Federal sponsors, provided funds of $325,000 in 
March 1992. 
Operations and results during fiscal year. 
Phase I contract for repair of 23 of the 48 deficient pipes 
was awarded July 30, 1992. Contract completion is 
scheduled for May 1993. 
36. WAURIKA LAKE, OK. 
Location. On Beaver Creek, a tributary of the Red 
River, at river mile 27.0, about 6 miles northwest of 
Waurika in Jefferson County, OK. (See Hastings, OKTX, 
Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-12 of the Annual Report for 
1983. Waurika Lake is operated as a unit of a coordinated 
lake system for flood control in the Red River 
Basin. Construction began in July 1971 and impoundment 
began in August 1977. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operations and maintenance continued. 
37. WISTER LAKE, OK. 
Location. On the Poteau River at river mile 60.9, 
about 2 miles south of Wister in LeFlore County, OK. 
(See Wister, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 601 of the Annual Report for 
1969. Construction began in April 1946 and was completed 
in May 1949. The project was placed in full flood 
control operation in October 1949. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operations and maintenance continued. 
38. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS. 
See Table 29-E. 
39. INSPECTION OF COMPLETED 
LOCAL FLOOD PROTECTION 
PROJECTS. 
Inspections of completed, Federally constructed local 
flood protection projects which are owned, operated, and 
maintained by local interests are made to determine the 
extent of compliance with approved regulations for operations 
and maintenance. The inspections assist the 
Corps of Engineers in determining if the project provides 
the flood protection for which it was constructed. See 
Table29- I for a list of projects inspected in FY 92. Fiscal 
year cost was $69,805. 
40. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS. 
The Tulsa District, Corps of Engineers is responsible 
for flood control operations at 12 non-Corps projects. 
These include nine Bureau of Reclamation lakes, two 
Grand River Dam Authority lakes, and one city-county 
owned lake. All of these projects were constructed wholly 
or in part with Federal funds. Routine flood control 
releases were required at several of the projects. Fiscal 
year costs for scheduling flood control reservoir operations 
totaled $590,772. 
41. EMERGENCY FLOOD CONTROL 
ACTIVITIES. 
Fiscal year cost for national emergency preparedness 
was $111,127 and for advance preparation was $130,000. 
42. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION. 
See Table 29-J for FY 92 expenditures for Small Flood 
Control Projects Not Specifically Authorized by Congress 
(Section 205); Emergency Streambank and Shoreline 
Projects (Section 14); and Snagging and Clearing. 
Multiple-Purpose Projects 
Including Power 
43. BROKEN BOW LAKE, OK. 
Location. On the Mountain Fork River at river mile 
20.3, about 9 miles northeast of Broken Bow in McCurtain 
County, OK. (See Broken Bow, OK, Geological Survey 
map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvements, see page 29-17 of the Annual Report for 
1971. Construction began in November 1961 and the 
29-10

TULSA, OKLAHOMA, DISTRICT 
project was placed in useful operation in October 1969. 
Power units 1 and 2 were placed in operation in January 
and June 1970, respectively. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
44. EUFAULA LAKE, OK. 
Location. On the Canadian River at river mile 27.0, 
about 12 miles east of Eufaula in McIntosh County, OK. 
(See Porum, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 588 of the Annual Report for 
1970. Construction began in December 1956 and the 
project was placed in full flood control operation in 
February 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. Routine 
operation and maintenance continued. 
45. FORT GIBSON LAKE, OK. 
Location. On the Grand (Neosho) River at river mile 
7.7, about 5 miles north of Fort Gibson in Muskogee 
County, OK. (See Fort Gibson Dam, OK, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 604 of the Annual Report for 
1969. Construction began in March 1942 but was held in 
abeyance during World War II. Construction resumed in 
May 1946 and was completed in June 1950. The fourth 
generator was installed and the project placed in full 
operation in September 1953. The Water Resources 
Development Act of 1986 authorized the construction of 
hydropower units 5 and 6. Authorization required 100 
percent non-Federal financing and will be financed by 
the Grand River Dam Authority (GRDA). Project design 
is postponed pending resolution of turbine selection by 
GRDA. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
46. KEYSTONE LAKE, OK. 
Location. On the Arkansas River at river mile 538.8, 
near Sand Springs, OK, and about 15 miles west of Tulsa, 
OK. (See Keystone Dam, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 589 of the Annual Report for 
1970. Construction began in January 1957 and the 
project was placed in flood control operation in 
September 1964. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
47. LAKE TEXOMA (DENISON DAM), OK 
AND TX. 
Location. On the Red River at river mile 725.9, about 
5 miles northwest of Denison, TX. (See Denison Dam, 
OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 603 of the Annual Report for 
1969. Lake Texoma is operated as a unit of a coordinated 
lake system for flood control in the Red River Basin. 
Construction started in August 1939 and was completed 
in February 1944. Commercial power generation was 
started in March 1945. Authorized work is complete 
except for installation of the third, fourth, and fifth 
power units. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
48. ROBERT S. KERR LOCK AND DAM 
AND RESERVOIR, OK. 
Location. On the Arkansas River at navigation mile 
336.2, about 8 miles south of Sallisaw in LeFlore County, 
OK. (See Robert S. Kerr, OK, Geological Survey map, 
scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-21 of the Annual Report for 
1972. The Robert S. Kerr Lock and Dam and Reservoir 
is a unit of the McClellan-Kerr Arkansas River Navigation 
System. Construction began in April 1964 and 
closure was completed in October 1970. The lock and 
dam became operational for navigation in December 
1970. Generating units 1, 2, 3, and 4 were placed in 
operation in October, July, September, and November 
1971, respectively. 
Local cooperation. See section 1 of this report. 
29-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 1992 
Terminal facilities. Five sites have been developed 
for handling coal, grain, construction aggregates, and 
miscellaneous cargo. The facilities are considered adequate 
for present traffic. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
49. TENKILLER FERRY LAKE, OK. 
Location. On the Illinois River at river mile 12.8, 7 
miles northeast of Gore in Sequoyah County, OK. (See 
Gore, OK, Geological Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 606 of the Annual Report for 
1969. Construction began in June 1947 and was completed 
in July 1953. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Routine operation and maintenance continued. 
50. WEBBERS FALLS LOCK AND DAM, 
OK. 
Location. On the Arkansas River at navigation mile 
366.6, about 5 miles northwest of Webbers Falls in 
Muskogee County, OK. (See Webbers Falls, OK, Geological 
Survey map, scale 1:24,000.) 
Existing project. For a description of the completed 
improvement, see page 19-23 of the Annual Report for 
1977. The Webbers Falls Lock and Dam is a unit of the 
McClellan-Kerr Arkansas River Navigation System. Construction 
began in January 1965, and the project was 
placed in useful operation in November 1970. The lock 
and dam became operational for navigation in December 
1970. Generating units 1, 2, and 3 were placed in 
operation in August, September, and November 1973, 
respectively. 
Local cooperation. See section 1 of this report. 
Terminal facilities. Facilities at the Port of Muskogee 
include: A cargo pier, mooring dolphins, warehouse, 
terminal building, and fuel facility built by the Muskogee 
City-County Port Authority; a liquid cargo loading facility 
and a steel unloading facility built by Frontier Steel 
Company; grain holding facilities built by Conagra, Inc.; 
and a general-purpose private dock built by the Fort 
Howard Paper Company. 
Operations and results during fiscal year. 
tine operation and maintenance continued. 
Rou- 
General Investigations 
51. SURVEYS. 
Fiscal year cost was $557,063 which included 11 flood 
damage prevention studies; 1 special study, 2 restudies 
of deferred projects; miscellaneous activities-special investigations, 
review of FERC licenses, and intragency 
water resources development; and coordination with 
other Federal agencies, States, and non-Federal interests. 
Table 29-K provides a specific list and respective 
fiscal year expenditures. 
52. COLLECTION AND STUDY OF 
BASIC DATA. 
Fiscal year cost was $259,488 which includes floodplain 
management services and hydrologic studies. Table 
29-K provides a specific list and respective fiscal year 
expenditures. 
53. PRECONSTRUCTION 
ENGINEERING AND DESIGN. 
Fiscal year cost was $1,133,384 which includes two 
navigation projects and five local protection projects. 
Table 29-K provides a specific list and respective fiscal 
year expenditures. 
29-12

TULSA, OKLAHOMA, DISTRICT 
Table 29-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30,19922 
1. McClellan-Kerr Arkansas New Work 
River Navigation System, Approp 
OK, (Tulsa District Portion) Cost 
Maint 
Approp 
Cost 
3. Arcadia Lake, OK New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
130,936,6382 
130,936,6382 
130,936,6382 
130,936,6382 
4,207,100 3,505,573 3,079,178 3,461,500 142,553,312 
4,224,784 3,447,239 3,267,423 3,559,308 137,650,691 
768,000 
1,323,780 
0 3,131,000 
145,748 3,298,138 
417,500 312,182 308,900 
392,488 344,939 312,533 
1,000,000 
169,161 
379,000 
373,861 
85,339,289 
85,271,011 
1,880,982 
1,871,056 
4. Arkansas-Red River 
BasinsChloride Control, 
KS, OK, and TX 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
4a. Area V, 
Estelline Springs, TX 
- 25,705,208 
376 - 25,705,068 
3,635 
4,288 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
3,300 
5,288 
3,788 
2,995 
1,200 
1,979 
3,000 
1,987 
3,533,506 
3,646,832 
300,028 
300,028 
177,099 
190,661 
4b. Area VIII, TX 
189,000 - 46,682,000 
23,649 46,679,756 
Maint 
Approp 
Cost 
4C Red River Basin Chloride 
Control, TX & OK 
5. Birch Lake, OK 
770,300 638,748 583,300 
802,076 632,946 582,900 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
- 2,550,000 
- 756,974 
759,972 714,177 
771,336 701,214 
29-13 
651,450 
676,088 
New Work 
Approp 
Cost 
840,500 
823,381 
2,450,000 
2,650,261 
685,000 
681,326 
4,113,148 
4,080,009 
5,000,000 
3,397,235 
13,549,170 
13,549,296 
9,019,200 
12,311,868

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
Table 29-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY90 FY91 FY92 Sep 30,19921 
6. Candy Lake, OK 
7. Canton Lake, OK 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
19,000 
19,242 
9,200 
18,712 
30,400 
18,712 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
8 Copan Lake, OK New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
9. Council Grove Lake, KS 
1,403,400 1,436,982 1,595,250 
1,508,298 1,340,993 1,566,840 
353,133 
-35,000 
36,198 
-130,000 
10,484 
903,200 739,178 759,600 
875,777 755,231 812,715 
New Work 
Approp 
Cost 
843,900 761,899 756,800 1,017,000 14,357,643 
864,027 740,635 772,331 850,373 14,156,585 
10. El Dorado Lake, KS 
24,332 
72,600 
86,971 
- 92,505,068 
- 92,376,652 
Maint 
Approp 
Cost 
11. Elk City Lake, KS 
536,208 411,680 448,900 
539,477 424,463 456,288 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
1,005,708 652,118 732,200 
1,026,682 671,250 726,541 
29-14 
33,000 
33,431 
4,927,922 
4,927,714 
115,700 
115,300 
11,209,834 
10,918,727 
26,757,626 
26,814,183 
88,509,751 
92,035,258 
6,133,779 
6,099,078 
11,810,509 
11,810,509 
3,825,800 
3,934,771 
-2,248 
873 
884,000 
878,128 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
131,000 
318,066 
419,500 
422,471 
4,207,988 
4,204,515 
19,052,990 
19,052,990 
12,888,532 
12,835,457 
733,400 
714,407

Table 29-A 
(Continued) 
TULSA, OKLAHOMA, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
in Text Project Funding FY 89 
12. Fall River Lake, KS New Work 
Approp - 
Cost - 
Maint 
Approp 1,054,600 
Cost 1,132,283 
13. Fort Supply Lake, OK New Work 
Approp - 
Cost - 
Maint 
Approp 1,024,500 
Cost 970,456 
14. Great Bend, KS New Work 
Approp 1,500,000 
Cost 1,247,994 
15. Great Salt Plains Lake, OK New Work 
Approp - 
Cost - 
Maint 
Approp 1,033,200 
Cost 1,119,370 
16. Halstead, KS New Work 
Approp 200,000 
Cost 203,551 
17. Heyburn Lake and New Work 
Polecat Creek, OK Approp - 
Cost - 
Maint 
Approp 826,000 
Cost 787,096 
18. Hugo Lake, OK New Work 
Approp 
Cost 4,023 
Maint 
Approp 1,328,700 
Cost 1,343,855 
FY 90 FY 91 
- - 
720,496 958,400 
735,620 872,159 
753,624 751,600 
820,457 788,347 
5,398,000 4,985,400 
5,225,004 4,065,797 
- - 
- - 
434,679 325,800 
399,847 351,078 
259,000 262,000 
244,356 202,957 
601,250 611,300 
628,135 680,453 
3,456,700 
3,748,348 
1,219,694 1,250,500 
1,245,018 1,323,840 
Total to 
FY 92 Sep 30,1992' 
- 10,550,873 
- 10,550,873 
956,800 13,821,691 
996,806 13,944,027 
- 7,724,134 
- 7,723,127 
737,500 12,996,698 
727,659 12,952,847 
4,786,000 18,029,400 
5,548,146 17,245,330 
- 4,626,270 
- 4,626,270 
337,000 8,179,786 
326,261 8,149,788 
2,828,000 4,174,000 
2,808,865 4,071,405 
- 2,560,572 
- 2,560,572 
683,000 10,692,473 
665,157 10,768,587 
- 41,216,442 
- 41,180,456 
1,410,500 20,627,544 
1,307,664 20,444,569 
29-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
Table 29-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 19922 
19. Hulah Lake, OK 
20. John Redmond Dam 
and Reservoir, KS 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Minor Rehab 
Approp 
Cost 
New Work 
Approp 
Cost 
595,300 404,921 389,700 
597,517 454,003 385,644 
1,546,200 1,078,323 961,800 
1,562,032 1,050,865 1,049,933 
1,022,000 21,863,800 
1,021,250 21,969,139 
21. Kaw Lake, OK 
109,430,750 
-390 109,429,274 
Maint 
Approp 
Cost 
22. Lake Kemp, TX 
1,772,700 1,562,033 1,515,600 
1,884,007 1,488,022 1,703,701 
1,775,200 24,175,923 
1,724,787 24,069,805 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
23. Lake Wichita, 
Holliday Creek, TX 
24. Marion Reservoir, KS 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
150,680 122,278 174,700 
158,216 110,666 183,575 
6,755,000 12,071,000 3,594,000 
6,826,669 10,009,893 4,597,273 
889,800 894,872 939,900 
910,507 958,866 949,944 
137,000 
125,281 
-349,000 24,580,000 
890,417 24,277,853 
907,600 
907,012 
29-16 
11,388,150 
11,182,433 
12,195,900 
12,165,189 
306,000 
317,347 
Maint 
Approp 
Cost 
135,718 
135,718 
28,151,515 
28,151,515 
New Work 
Approp- 
Cost 
7,637,702 
7,637,702 
2,420,892 
2,403,871 
13,420,817 
13,420,817 
14,752,718 
14,705,820

TULSA, OKLAHOMA, DISTRICT 
Table 29-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 19922 
25. Mingo Creek, OK 
26. Oologah Lake, OK 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
4,884,000 5,090,000 6,221,000 12,183,000 30,465,000 
2,268,007 7,904,520 6,540,605 12,359,164 29,518,714 
46,722,3293 
46,721,5563 
1,135,100 1,496,487 1,485,800 
1,143,974 1,270,804 1,699,766 
1,427,500 23,761,213 
1,423,709 23,725,890 
27. Optima Lake, OK New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
28. Parker Lake, OK 
29. Pat Mayse Lake, TX 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
30. Pearson-Skubitz 
Big Hill Lake, KS 
561,000 443,728 454,700 
578,602 441,111 462,093 
-654,000 
119,194 40,871 2,238 
805,100 812,641 906,800 
869,122 779,710 903,262 
429,500 
427,111 
2,258 
939,400 
965,137 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
31. Pine Creek Lake, OK New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
1,025,700 919,818 804,600 
1,033,793 851,358 870,861 
-202 
937,000 
925,070 
170 
1,008,600 924,395 1,051,900 1,162,600 
999,405 933,647 1,054,204 1,137,726 
29-17 
Maint 
Approp 
Cost 
47,173,438 
47,273,438 
6,086,350 
6,118,928 
522,000 
509,009 
9,310,661 
9,310,661 
13,817,450 
13,792,678 
16,879,166 
16,879,166 
8,362,618 
8,345,266 
20,628,049 
20,627,847 
14,195,553 
14,126,019

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
Table 29-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 19922 
32. Sardis Lake, OK New Work 
Approp 
Cost 
1,350,000 1,075,000 -169,000 
4,273,156 2,626,250 226,259 
888,800 882,840 832,700 
887,629 853,845 874,352 
- 68,799,479 
4,068 68,616,930 
926,000 
862.618 
6,844,390 
6,768,125 
33. Skiatook Lake, OK 
20,000 
130,038 471 
- 106,201,282 
141 106,268,739 
987,700 1,191,638 1,127,000 1,256,000 
1,002,919 1,215,888 1,160,717 1,076,141 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
35. Tulsa & West Tulsa, OK 
36. Waurika Lake, OK 
New Work 
Approp 
Cost 
New Work 
Approp 
Cost 
211,900 277,303 239,700 
233,835 273,670 240,867 
135,000 
65,703 
-8,034 
- 2,911,000 
- 2,911,338 
263,000 
264,871 
840,000 
153,044 
6,764,938 
6,533,948 
13,896,324 
13,896,324 
6,066,106 
6,063,346 
975,000 
218,747 
-323,752 69,740,298 
-313,970 69,739,869 
Maint 
Approp 
Cost 
37. Wister Lake, OK New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Major Rehab 
Approp 
Cost 
1,209,100 1,129,587 1,233,400 1,235,600 
1,212,261 1,141,034 1,210,457 1,261,658 
802,800 733,693 715,100 
805,894 689,495 772,332 
940,000 6,195,529 3,996,000 
922,683 5,756,325 4,095,199 
720,000 
716,466 
270,394 
29-18 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
433,000 
2,189,460 
Maint 
Approp 
Cost 
34. Toronto Lake, KS 
12,422,553 
11,397,783 
10,501,226 
10,501,226 
13,032,653 
13,066,574 
11,131,529 
11,044,601

TULSA, OKLAHOMA, DISTRICT 
Table 29-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 19922 
43. Broken Bow Lake, OK New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
44. Eufaula Lake, OK New Work 
Approp 
Cost 
1,626,200 1,644,380 1,740,400 1,752,200 
1,779,734 1,623,572 1,671,878 1,860,381 
17,617 
41,222,692 
41,222,692 
23,653,521 
23,629,372 
- 123,350,7474 
19,824 - 123,051,2034 
3,666,000 3,861,000 4,366,794 4,038,400 
3,403,633 4,121,612 4,385,849 3,923,005 
45. Fort Gibson Lake, OK 
- 42,591,2986 
- 43,497,7916 
3,230,500 2,989,814 3,055,000 3,734,000 55,348,002 
3,354,424 3,052,430 3,087,214 3,533,649 56,451,929 
46. Keystone Lake, OK 
- 123,171,1736 
- 123,170,6756 
2,902,200 2,745,433 2,680,100 
3,024,825 2,752,389 2,742,665 
3,022,685 48,225,685 
3,050,124 48,288,977 
47. Lake Texoma 
(Denison Dam),OK and TX 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
Minor Rehab 
Approp 
Cost 
48. Robert S. Kerr Lock and New Work 
Dam and Reservoir, OK Approp 
Cost 
Maint 
Approp 
Cost 
68,168,9607 
68,019,1097 
5,350,600 7,078,815 5,252,000 6,265,000 100,396,986 
5,473,749 5,667,880 6,557,106 6,303,084 100,233,511 
46,237 
46,237 
-- - - 94,578,237 
-- - - 94,578,237 
4,592,584 4,233,112 2,811,100 2,900,500 52,523,533 
4,781,357 3,612,433 3,288,901 3,104,279 52,131,836 
29-19 
Maint 
Approp 
Cost 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost 
63,146,560 
59,803,902 
New Work 
Approp 
Cost 
Maint 
Approp 
Cost

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
Table 29-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 19922 
49. Tenkiller Ferry Lake, OK New Work 
Approp - - - - 24,017,7208 
Cost - - - - 24,057,7188 
Maint 
Approp 2,739,000 2,837,232 2,757,300 3,005,000 49,804,646 
Cost 2,831,687 2,906,764 2,835,767 2,965,843 47,751,489 
50. Webbers Falls New Work 
Lock and Dam, OK Approp - 2,369,690 - - 86,107,967 
Cost - 2,369,690 - - 86,108,391 
Maint 
Approp 2,433,300 2,152,027 2,382,700 2,809,000 47,098,491 
Cost 2,728,735 1,964,705 2,534,989 2,875,685 47,196,511 
1. Includes $2,077,900 expended by the Jobs Act (P.L. 98-8 dated, 6. Excludes $5,366,231 special funds. 
March 24, 1983) for projects listed in Table 29-M of the FY 85 7. Includes $433,539 Emergency Relief Funds. 
Annual Report. Exchange $1,256,068 from special contributed funds. 
2. Includes $12,700,038 for Bank Stabilization and 8. Excludes $946 contributed funds. Includes $39,999 Public 
Channel Rectification. Works acceleration funds. 
3. Excludes $81,460 contributed funds and $1,348,816 special funds. 9. The cost for Grand Lake 0' the Cherokees has been added to 
4. Excludes $299,803 contributed funds and $13,211,728 special funds. amount reported in paragraph 41, Scheduling Reservoir 
5. Excludes $134,919 contributed funds. Includes $49,581 Public Operations. 
Works acceleration funds. 
TABLE 29-B AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
July 24, 1946 
October 22, 1976 
November 17, 1986 
December 31, 1970 
October 22, 1976 
McCLELLAN-KERR ARKANSAS 
RIVER NAVIGATION SYSTEM 
Big and Little Sallisaw 
Creeks Navigation Project 
W.D. Mayo Hydropwer 
ARCADIA LAKE 
Changed water quality to 
water supply 
29-20 
3. 
HD 79-758 
PL 79-525 
PL 94-587 
PL 99-662 
HD 91-299 
PL 94-587

TULSA, OKLAHOMA, DISTRICT 
TABLE 29-B 
(Continued) 
AUTHORIZING LEGISLATION 
Date of 
Authorizing 
Act 
October 23, 1962 
November 7, 1966 
December 31, 1970 
November 17, 1986 
October 23, 1962 
October 23, 1962 
June 28, 1938 
July 24, 1946 
June 30, 1948 
October 23, 1962 
May 17, 1950 
October 27, 1965 
August 18, 1941 
August 18, 1941 
June 22, 1936 
November 17, 1986 
June 22, 1936 
November 17, 1986 
July 24, 1946 
July 24, 1946 
June 22, 1936 
May 17, 1950 
February 15, 1958 
October 23, 1962 
October 23, 1962 
See 
Section 
In Text 
4. 
4a. 
4b.&4c. 
HULAH LAKE 
JOHN REDMOND DAM AND RESERVOIR 
Authorized name change 
KAW LAKE 
LAKE KEMP 
Documents 
Project 
and Work 
Authorized 
ARKANSAS-RED RIVER BASINS 
CHLORIDE CONTROL 
Authorized Area V 
(Estelline Springs) 
Authorized Areas VII, VIII, and X P 
Authorized Areas I, II-III, 
VI, IX, XIII, XIV, and XV 
Authorized the Red River Basin 
and the Arkansas River Basin as 
separate projects with separate 
authority. 
BIRCH LAKE 
CANDY LAKE 
CANTON LAKE 
Approved Irrigation Storage 
Approved Water Supply Storage 
COPAN LAKE 
COUNCIL GROVE LAKE 
EL DORADO LAKE 
ELK CITY LAKE 
FALL RIVER LAKE 
FORT SUPPLY LAKE 
GREAT BEND 
GREAT SALT PLAINS LAKE 
HALSTEAD 
HEYBURN LAKE AND POLECAT CREEK 
HUGO LAKE 
HD 74-308 
HD 80-442 
PL 85-327 
HD 87-143 
HD 87-144 
29-21 
SD 87-107 
'L 89-789, SD 110 
PL 91-611 
PL 99-662 
HD 87-563 
HD 87-563 
HD 75-569 
HD 87-563 
HD 80-442 
HD 89-232 
HD 76-440 
HD 76-440 
HD 74-308 
PL 99-662 
HD 74-308 
PL 99-662 
HD 80-290 
HD 79-602 
5. 
6. 
7. 
8. 
9. 
10. 
11. 
12. 
13. 
14. 
15. 
16. 
17. 
18. 
19. 
20. 
21. 
22.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
TABLE 29-B 
(Continued) 
AUTHORIZING LEGISLATION 
See 
Section 
In Text 
23. 
24. 
25. 
26. 
27. 
28. 
29. 
30. 
31. 
32. 
33. 
34. 
35. 
36. 
29-22 
37. 
43. 
44. 
-- 
Date of 
Authorizing 
Act 
November 17, 1986 
May 17, 1950 
March 14, 1990 
November 17, 1986 
June 28, 1938 
June 22, 1936 
November 17, 1986 
October 23, 1962 
October 23, 1962 
November 10, 1978 
July 3, 1958 
October 23, 1962 
December 4, 1981 
October 23, 1962 
August 18, 1941 
August 18, 1941 
December 30, 1963 
June 28, 1938 
July 30, 1983 
July 3, 1958 
October 23, 1962 
July 24, 1946 
Project 
and Work 
Authorized 
LAKE WICHITA, HOLLIDAY CREEK 
MARION RESERVOIR 
Authorized name change 
MINGO CREEK 
OOLOGAH LAKE 
OPTIMA LAKE 
PARKER LAKE 
PAT MAYSE LAKE 
PEARSON-SKUBITZ BIG HILL LAKE 
Authorized name change 
PINE CREEK LAKE 
SARDIS LAKE 
Authorized name change 
SKIATOOK LAKE 
TORONTO LAKE 
TULSA & WEST TULSA, OK 
WAURIKA LAKE 
WISTER LAKE 
Changed conservation pool 
elevation 
BROKEN BOW LAKE 
EUFAULA LAKE 
Documents 
PL 99-662 
HD 80-442 
PL 101-253 
PL 99-662 
Committee Doc. 
No. 1, 75th 
Cong., 1st Session 
HD 74-308 
PL 99-662 
HD 88-71 
HD 87-472 
PL 95-265 
HD 85-170 
SD 87-145 
PL 97-88 
HD 87-563 
HD 76-440 
PL 77-228 
PL 101-514 
SD 88-33 
PL 88-253 
Committee Doc. 
No. 1, 75th 
Cong., 1st Session 
PL 98-63 
HD 85-170 
SD 87-137 
HD 79-758

TULSA, OKLAHOMA, DISTRICT 
TABLE 29-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date of Project 
Section Authorizing and Work 
In Text Act Authorized Documents 
45. August 18, 1941 FORT GIBSON LAKE HD 76-107 
July 24, 1946 Incorporated into the PL 76-228 
multiple-purpose plan for 
the Arkansas River Basin 
November 17, 1986 Added hydropower units 5 & 6 PL 99-662 
46. May 17, 1950 KEYSTONE LAKE SD 81-07 
47. LAKE TEXOMA (Denison Dam) 
June 28, 1938 Flood control and power HD 75-541 
October 17, 1940 Navigation and regulating flows PL 76-868 
Sepember 30, 1944 Authorized name PL 78-454 
August 14, 1953 Water supply PL 83-273 
November 17, 1986 Recreation PL 99-662 
48. July 24, 1946 ROBERT S. KERR LOCK AND HD 79-758 
DAM AND RESERVOIR 
July 8, 1963 Authorized name change PL 88-62 
49. June 28, 1938 TENKILLER FERRY LAKE Committee Doc. 
No. 1, 75th 
Cong., 1st Sess. 
June 24, 1946 Power HD 79-758 
50. July 24, 1946 WEBBERS FALLS LOCK AND DAM HD 79-758 
Table 29-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Big and Little Sallisaw Inactive 
Navigation Project 
Poteau River Navigation Project, Complete 1983 536,952 
OK and AR 
Red River from Fulton, AR, Complete 1924 378,574 182,157 
to Mouth of Washita River 
29-23

TABLE 29-E 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last 
Full Report Cost to September 30, 1992 
See Annual Operation and 
Project Report For Construction Maintenance 
Augusta LPP, KS', 2 1938 - 84,217 
Big Pine Lake, TX3 1984 1,701,670 
Boswell Lake, OK3 1952 
Cherry and Red Fork Creeks LPP, OK2 1970 261,448 
Crutcho Creek LPP, OK3 1972 213,016 
Dodge City LPP, KS2 
Enid LPP, OK2 1963 743,612 14,599 
Flat Rock and Valley View Creeks LPP, 1975 1,741,000 
Tulsa, OK2, 4 
Florence LPP, KS2 1965 369,782 
Hutchinson LPP, KS2 1956 3,497,718 
Iola LPP, KS2 1939 22,290 
Jenks LPP, OK2 1950 344,797 
Joe Creek LPP, OK2 - 308,041 
Lamed LPP, KS2 
Lukfata Lake, OK3 1983 1,424,685 
Marion, KS 1988 5,488,618 
McGrath Creek, Wichita Falls, TX5 
Oklahoma City LPP, OK2 1960 8,047,512 
Red River Bank Stabilization Below Denison, 1953 222,105 
OK and TX2 
Sand Creek LPP, KS2 1968 545,996 
Sand Lake, OK3 1963 
Shidler Lake, OK3 1983 568,191 
Tulsa and West Tulsa LPP, OK2 1954 2,785,070 
Turtle Creek LPP, Yukon, OK3 1975 144,853 
Tuskahoma Lake, OK3 1963 
West Branch Chisholm Creek LPP, KS2 1965 364,200 
Wichita and Valley Center LPP, KS2 1960 12,247,379 
Winfield LPP, KS', 2 1937 
LPP - Local Protection Project. 
1. Completed by Kansas Works Progress Administration. 
2. Complete. 
3. Deferred. 
4. Federal cost limited to $1,000,000. 
5. Active with no current year expenditures. 
29-24

TABLE 29-G 
Project 
Cedar Point Lake, KS 
Cow Creek, Hutchinson, KS 
El Dorado, West Branch, 
Walnut River, KS 
Neodesha Lake, KS 
Towanda Lake, KS 
TULSA, OKLAHOMA, DISTRICT 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Day 
See Annual and 
Report For Authority 
1980 November 17, 1986 
Public Law 99-662 
1971 November 17, 1986 
Public Law 99-662 
1977 November 17, 1986 
Public Law 99-662 
1952 November 17, 1986 
Public Law 99-662 
1981 November 17, 1986 
Public Law 99-662 
29-25 
Federal 
Funds 
Expended 
0 
363,720 
92,319 
97,910 
392,361 
Contribu 
Funds 
Expended 
0
0
0
0
0 
Cotib -

TABLE 29-H 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
ARKANSAS RIVER BASIN MULTIPLE-PURPOSE PLAN 
(See Section 1 of Text) 
Feature River River Mile' Nearest Town 
LAKES 
Canton North Canadian 394.3 Canton, OK 
Elk City Elk River 8.7 Elk City, KS 
Eufaula Canadian 27.0 Eufaula, OK 
Fall River Fall River 54.2 Fall River, KS 
Fort Gibson Grand (Neosho) 7.7 Fort Gibson, OK 
Grand Lake 0' the Cherokees Grand (Neosho) 77.0 Disney, OK 
Keystone Arkansas 538.8 Sand Springs, OK 
Lake Hudson (Markham Ferry) Grand (Neosho) 47.4 Locust Grove, OK 
Neodesha Verdigris 222.8 Neodesha, KS 
Oologah Verdigris 90.2 Oologah, OK 
Tenkiller Ferry Illinois 12.8 Gore, OK 
Toronto Verdigris 271.5 Toronto, KS 
Wister Poteau 60.9 Wister, OK 
McCLELLAN-KERR ARKANSAS RIVER NAVIGATION SYSTEM, OK 
(Tulsa District Portion) 
Bank Stabilization and Verdigris and N/A2 Fort Smith, AR, 
Channel Rectification Arkansas to Catoosa, OK 
Chouteau Lock and Dam (17), OK Verdigris 401.5 Okay, OK 
Lock and Dam 13, AR Arkansas 292.8 Fort Smith, AR 
Newt Graham Lock and Dam (18), OK Verdigris 421.6 Inola, OK 
Robert S. Kerr Lock and Dam (15), OK Arkansas 339.0 Sallisaw, OK 
Robert S. Kerr Marine Terminal, OK Arkansas 336.2 Cowlington, OK 
Sans Bois Navigation Channel, OK Sans Bois Creek 341.0 Keota, OK 
W.D. Mayo Lock and Dam (14), OK Arkansas 319.6 Redland, OK 
Webbers Falls Lock and Dam (16), OK Arkansas 366.6 Gore, OK 
1. On the McClellan-Kerr Arkansas River Navigation System, these are navigation miles. 
2. As required for a channel 9 feet deep. 
29-26

TULSA, OKLAHOMA, DISTRICT 
Projects Inspected in Fiscal Year Inspection Date 
South Deer Creek,OK 
Dodge City, KS 
Florence, KS 
Hutchinson, KS 
Iola, KS 
Lamed, KS 
Marion, KS 
Sand Creek, City of Newton, KS 
Cherry/Red Fork Creeks, OK 
Flat Rock/Valley View Cks, OK 
Haikey Creek, OK 
Jenks, OK 
Joe Creek, OK 
Tulsa/West Tulsa Levees, OK 
Enid Diversion Channel, OK 
Oklahoma City Floodway, OK 
Park City, KS 
West Branch Chisholm Creek, KS 
Wichita/Valley Center 
October 1991 
December 1991 
November 1991 
May 1992 
December 1991 
December 1991 
November 1991 
November 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
October 1991 
December 1991 
December 1991 
May 1992 
May 1992 
May 1992 
TABLE 29-J FLOOD CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
(See Section 42 of Text) 
Fiscal Year 
Study Identification/Name Cost 
SMALL FLOOD CONTROL PROJECTS NOT SPECIFICALLY 
AUTHORIZED BY CONGRESS (Section 205) 
Arkansas River, Moffett, OK 
Blackboy Creek, Tulsa County, OK 
Chickasha, OK 
Chikaskia River, Blackwell, OK 
Coal Creek, Henryetta, OK 
Cowskin Creek, Haysville, KS 
Gordon Creek, Iowa Park, TX 
Little Arkansas River, Sedgwick, KS 
Manard Bayou, Muskogee County, OK 
Merkle Creek, Norman, OK 
Muskogee, OK 
North Canadian River Wastewater Plant, Oklahoma City, OK 
Rock Island Slough, Wellington, KS 
Sycamore Creek, Coffeyville, KS 
Walnut Creek, Purcell, OK 
Whiskey and Rock Creeks, Independence, KS 
Wichita Falls, TX, Plum Creek 
Wolf Creek, Lawton, OK 
TOTAL SMALL FLOOD CONTROL PROJECTS 
29-27 
TABLE 29-I INSPECTION OF COMPLETED LOCAL FLOOD 
PROTECTION PROJECTS 
(See Section 39 of Text) 
0 
215 
7,076
0 
1,772 
4,570 
10,418 
49
0
0
0 
333 
42 
21,222
0
0 
40,639 
496 
86,832

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
TABLE 29-J FLOOD CONTROL WORK 
(Continued) UNDER SPECIAL AUTHORIZATION 
(See Section 42 of Text) 
Fiscal Year 
Study Identification/Name Cost 
EMERGENCY STREAMBANK AND SHORELINE PROTECTION (Section 14) 
Camp Facility, Red River, Telephone, TX 13,864 
Chikaskia River, Ft Oakland, OK 270 
Chikaskia River, Blackwell, OK -21 
City Dam, Little Caney River, KS 3,540 
County Bridge, Walnut River, Arkansas City, KS 17 
County Road (Sec. 2), Deer Creek, KS 7,003 
County Road (Sec. 6), Deer Creek, KS 413 
County Road, Washita River, Caddo 2,365 
County Bridge Elk River, Elk City, KS 2,682 
County Road, Washita River, Caddo City, OK 14,627 
County Road, North Canadian River, OK 4,651 
County Road, Tyner Creek, Adair 0 
Cow Creek, Comache, OK 10,032 
County Road, Washita River, Carter County (-136) 
Dam and Bridge, Neosho River, KS 6,216 
Fisher Creek, Tulsa County 210 
Kiowa Tribe Housing Developement, Andarko, OK 11,439 
Levee, Arkansas River, Tulsa, OK 1,111 
North Canadian River, Okfuskee County, OK 9,709 
Poteau River, LeFlore County, OK 1,899 
Section 20 Aqueduct Washita River, Caddo County, OK 6,170 
Section 24 Aqueduct Washita River, Caddo County, OK 3,964 
Section 24 Road North Canadian River, Pottawatomie County, OK 924 
Section 27 Road North Canadian River, Pottawatomie County, OK 2,230 
Sewage Lagoon, South Canadian River, New Castle 315 
Sewage Lagoons, North Canadian River 6,553 
State Highway 156, Kay County, OK 0 
Verdigris River City Dam, Independence, KS -522 
Walnut River, Cowley County, KS -988 
TOTAL EMERGENCY STREAMBANK AND SHORELINE PROTECTION 108,537 
SNAGGING AND CLEARING 
Boggy Creek, Bryan County, OK 19,726 
Little Deep Fork Creek, OK 1,624 
TOTAL SNAGGING AND CLEARING 21,350 
29-28

TULSA, OKLAHOMA, DISTRICT 
TABLE 29-K GENERAL INVESTIGATIONS 
(See Sections 51, 52, and 53 of Text) 
Fiscal Year 
Study Identificatiorn/Name Cost 
SURVEYS 
Flood Damage Prevention Studies 
Arkansas River, Great Bend, KS, to Tulsa, OK 397 
Arkansas River Basin, AR and OK 5,811 
Canadian River, OK, TX, NM 35 
Crutcho Creek, OK 43 
Grand Neosho River Basin, KS and OK 69 
Kaw Dam to Keystone Lake 8,557 
Lake Texoma, OK and TX 338 
Miami and Vicinity, OK 8 
North Canadian Above Lake Overholser 9 
North Canadian River, OK 247,995 
Pecan Bayou, TX 208,740 
Special Studies 
Fed Strategy America Infrastructure 4,232 
Review of Authorized Projects 
Restudy of Deferred Projects 
Lukfata Lake, OK 4 
Winfield, KS 50 
Miscellaneous Activities 
Special Investigations 44,538 
Review of FERC Licenses 1,713 
Intragency Water Resources Development 19,981 
North American Water Fowl Management 3,926 
Coordination with Other Federal Agencies, States, and Non-Federal Interests 
Soil Conservation Service 3,006 
Bureau of Reclamation 5,715 
Planning Assistance to States - Texas 21 
Planning Assistance to States - Oklahoma 1,875 
TOTAL SURVEYS 557,063 
COLLECTION AND STUDY OF BASIC DATA 
Flood Plain Management Services 
Claremore OK, FW/P 4,704 
Flood Plain Management Services 44,076 
Ponca City, OK, Flood Forecast Map 26 
Quick Responses 9,946 
Chickasha, OK 3,762 
Moore, OK 7,873 
Sterling, KS 14,963 
Wichita, KS 29,946 
Shawnee, OK 11,409 
Skiatook, OK 19,464 
Technical Services General 100,075 
Tulsa Forecast Maps 5 
Wagoner County, CO 11,111 
Hydrologic Studies 
Storm Studies 2,128 
TOTAL COLLECTION AND STUDY OF BASIC DATA 259,488 
29-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS FOR FY 92 
TABLE 29-K 
(Continued) 
GENERAL INVESTIGATIONS 
(See Sections 51, 52, and 53 of Text) 
Fiscal Year 
Study Identification/Name Cost 
PRECONSTRUCTION ENGINEERING AND DESIGN 
Navigation Projects 
Big and Little Sallisaw Creeks 
Red River Waterway to Denison Dam, TX 
Flood Control Projects 
Local Protection 
Arkansas City, KS 
Fry Creeks, Bixby, OK 
McGrath Creek, TX 
Upper Little Arkansas River Watershed, KS 
Winfield, KS 
TOTAL PRECONSTRUCTION ENGINEERING AND DESIGN 
1,312 
179,075 
390,333 
184,219 
151,599 
6,768 
220,078 
1,133,384 
29-30

FORT WORTH, TX, DISTRICT* 
District includes that portion of Texas south of Red 
River drainage basin exclusive of drainage basin of Rio 
Grande and its tributaries above and including Pecos 
River; exclusive of drainage basins to all short streams 
arising in coastal plain of Texas and flowing into the Gulf 
of Mexico, including entire basins of Buffalo Bayou, San 
Jacinto, San Bernard, Lavaca, Navidad, Mission, and 
Arkansas Rivers; exclusive of lower basins of major 
streams flowing into the gulf as follows: Sabine River, 
Texas and Louisiana, downstream from U.S. Highway 
190 crossing at Bon Wier, Texas; Neches River downstream 
from Town Bluff gaging station; Trinity River downstream 
from Texas State Highway 45 crossing at Riverside, Texas; 
Brazos River downstream from confluence with Navasota 
River; Colorado River downstream from gaging station at 
Austin; Guadalupe River downstream from confluence 
with San Marcos River; San Antonio River downstream 
from confluence with Escondido Creek; Nueces River 
downstream from confluence with Frio and Atascosa 
Rivers; and exclusive of Agua Dulce, San Fernando, and 
Olmos Creek basins draining into Baffin Bay; coastal area 
south thereof to Rio Grande and south to the northern 
boundaries of Newton, Jasper, Tyler, Polk, Trinity, Walker, 
Waller, Austin, Fayette, Gonzales, Karnes, Live Oak, Jim 
Hogg, Zapata; the northern and western boundaries of 
McMullan; and the western boundaries of Montgomery 
and Duval Counties, Texas. District also includes those 
portions of the Sulphur River and Cypress Creek 
Watershed located in the State of Texas; that portion of 
western Louisiana in Sabine River drainage basin 
upstream from U.S. Highway 190 crossing at Bon Wier, 
Texas. 
30-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
IMPROVEMENTS 
Navigation Page 
1. Trinity River Project, TX ................... 30-2 
Flood Control 
2. Aquilla Lake, TX.......................... 30-3 
3. Bardwell Lake, TX ...................... 30-3 
4. Belton Lake, TX ........................... 30-3 
5. Benbrook Lake, TX. ..................... 30-4 
6. Boggy Creek, TX .......................... 30-4 
7. Canyon Lake,TX ......................... 30-4 
8. Cooper Lake and Channels, TX .............. 30-4 
9. Ferrells Bridge Dam- 
Lake O' The Pines, TX .................... 30-6 
10. Grapevine Lake, TX ...................... 30-6 
11. Hords Creek Lake, TX ..................... 30-6 
12. Joe Pool Lake, TX ........................ 30-6 
13. Lavon Lake, TX...... .................. 30-7 
14. Lavon Lake Modification and East Fork 
Channel Improvement, TX ................. 30-7 
15. Lewisville Dam, TX ...................... 30-7 
16. Navarro Mills Lake, TX ................... 30-8 
17. O.C. Fisher Dam and Lake, TX .............. 30-8 
18. Proctor Lake, TX........................ .30-8 
19. Ray Roberts Lake, TX................ . 30-8 
20. San Antonio Channel Improvement, TX . ..... 30-9 
21. San Gabriel River, TX .................... 30-9 
22. Somerville Lake, TX ................... .30-10 
23. Stillhouse Hollow Dam, TX ................ 30-10 
24. Waco Lake, TX ........................ .30-10 
25. Wright Patman Dam and Lake, TX.......... 30-10 
26. Inspection of Completed Flood Control 
Projects .............................. 30-11 
Navigation 
1. TRINITY RIVER PROJECT, TX 
The project authorized by the River and Harbor Act 
of 1965 (H. Doc 276, 89th Cong., 1st Sess.) consists of five 
major components: Multiple-Purpose Channel, Tennessee 
Colony Lake, Dallas Floodway Extension, West Fork 
Floodway, and Water Conveyance Facilities. For the last 
full report on the project as authorized, see Annual Report 
of 1978. The project information present herein is based 
on the tentatively selected project plan presented in the 
Draft General Design Memorandum. The plan consists of 
three structural components: Dallas Floodway Extension, 
Tennessee Colony Lake, and Channel to Liberty in the 
lower basin. The estimated cost of the improvements is 
$1,060,000,000 including $44,000,000 non-Federal cost for 
land acquisition and relocation required for the local 
protection features (Oct. 1, 1987, base price). 
Operations during fiscal year. Channel to Liberty 
and Tennessee Colony Lake have been dormant for several 
years due to lack of local support. The Dallas Floodway 
Extension has advanced to the Preconstruction 
Flood Control (Cont) Page 
27. Scheduling Flood Control Reservoir 
Operations ............................. 30-11 
28. Other Authorized Flood Control Projects ..... 30-11 
29. Work Under Special Authorization .......... 30-11 
Multiple-Purpose Projects Including Power 
30. Robert Douglas Willis Hydropower, TX ..... 30-11 
31. Sam Rayburn Dam and Reservoir, TX ....... 30-11 
32. Sam Rayburn Spillway 
(Dam Safety Assurance), TX ............... 30-12 
33. Town Bluff Dam- 
B.A. Steinhagen Lake, TX ................. 30-12 
34. Whitney Lake, TX ....................... 30-12 
General Investigations 
35. Surveys ........................... 
36. Preconstruction Engineering and Design 
37. Collection and Study of Basic Data ..... 
..... 30-12 
..... 30-12 
..... 30-13 
Tables 
Table 30-A Cost and Financial Statement ...... 30-15 
Table 30-B Authorizing Legislation ........... 30-19 
Table 30-C Other Authorized Flood Control 
Projects ......................... 30-22 
Table 30-D Inspection of Completed Flood 
Control Projects .................. 30-22 
Table 30-E Work Under Special 
Authorization .................... 30-23 
Engineering and Design stage and is described in 
Preconstruction Engineering and Design section. 
CHANNEL TO LIBERTY: 
Location. The Channel to Liberty begins at the 
Houston Ship Channel, crosses the bay area in an easterly 
direction to intersect the existing Double Bayou Channel 
turns northward along the coastline to Wallisville Lake 
and then continues northward through the lake area along 
the course of the Trinity River to River Mile 45 above 
Liberty, Texas. 
Existing project. The navigation portion of the 
channel will have a width of 200 feet with a depth of 12 
feet and will extend from the Houston Ship Channel in 
Galveston Bay to the port of Liberty, Texas. The flood 
control portion of the channel will have a bottom width of 
200 feet with a depth of 30 feet, and will extend from 
Wallisville Lake to River Mile 45 above Liberty, Texas. 
Estimated Federal cost of the improvements is 
$147,000,000 and estimated non-Federal cost is 
$44,000,000 for a total estimated cost of $191,000,000 
(Oct. 1, 1987, base price). 
30-2

FORT WORTH, TEXAS DISTRICT 
Local cooperation. Local interests are required to: 
(a) provide, without cost to the Federal Government, all 
lands, easements and rights-of-way required for 
construction, operation and maintenance of the project, 
(b) accomplish, without cost to the Federal Government, 
all relocations and alterations to existing improvements, 
other than highway bridges over new land cuts and 
railroad bridges required for the construction of the 
project, (c) maintain and operate the flood control portion 
of the channel upstream of Liberty, Texas, and (d) 
reimburse the Federal Government for one-half of the 
separable costs allocated to recreation and fish and wildlife 
enhancement. This reimbursement is presently estimated 
at $34,000, exclusive of interest. 
TENNESSEE COLONY LAKE: 
Location. The Tennessee Colony dam site is located 
at River Mile 341.7 on the Trinity River about 22 miles 
west of Palestine, Texas. The lake would extend into 
Freestone, Anderson, Henderson, and Navarro Counties, 
and would control a drainage area of 12,302 square miles. 
Existing project. The plan of improvement provides 
for the construction of an earthfilled dam with a maximum 
height of 123 feet above the streambed and a total 
embankment length of 42,350 feet with a gated concrete 
spillway. The lake will have a total controlled storage of 
3,455,000 acre-feet and a water surface area of 114,400 
acres at the top of the flood control pool and 68,100 acres 
at the top of the conservation pool. The total storage 
includes 2,269,500 acre-feet for flood control, 1,040,000 
acre-feet for conservation, and 145,500 acre-feet for 
sediment reserve. Estimated Federal cost of the 
improvement is $913,000,000 (Oct. 1, 1983, base price). 
Local cooperation. Local interests are required to 
reimburse the Federal Government for costs allocated to 
water supply storage and one-half of the separable cost 
allocated to recreation and fish and wildlife enhancement. 
This reimbursement is presently estimated at 
$461,754,000 for water supply and $9,533,000 for 
recreation (excluding future recreation facilities), for a 
total cost of $471,287,000, exclusive of interest. 
Flood Control 
2. AQUILLA LAKE, TX 
Location. On Aquilla Creek in Hill County, Texas, 
with the dam at River Mile 23.3, about 6.8 miles southwest 
of Hillsboro, Texas, and about 24.0 miles north of Waco, 
Texas. 
Existing project. For description of completed 
improvements and authorizing Acts see Annual Report 
for 1984. Construction was started March 1977, and 
project was ready for beneficial use April 29, 1983. 
Estimated cost is $46,100,000. 
Local cooperation. The Water Supply Act of 1958, 
as amended, and the Federal Water Project Recreation 
Act of 1965 and Section 221, Flood Control Act of 1970 
apply. A contract with the Brazos River Authority for 
water supply storage was approved by the Secretary of 
the Army, June 29, 1976. To date, the Authority has paid 
$162,272 toward principal and $33,437 to operation and 
maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continue. 
Benefits accrued to Aquilla Lake project: Accumulated 
flood damages prevented through FY 1992 were 
$17,353,051. 
3. BARDWELL LAKE, TX 
Location. Dam is on Waxahachie Creek, 5 river miles 
upstream from its confluence with Chambers Creek, a 
tributary of the Trinity River, and about 5 miles south of 
Ennis, Ellis County, Texas. 
Existing project. For a description of completed 
improvement and authorizing act see Annual Report of 
1969. Construction of project was started August 1963 
and completed for beneficial use in November 1965. 
Estimated cost of project is $12,941,000. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs allocated to increased 
water supply storage under the terms of the Water Supply 
Act of 1958. A Contract was approved by the Secretary of 
the Army on June 24, 1963, and the Trinity River 
Authority, a State agency, agreed to fulfill all 
requirements of local cooperation. To date the authority 
has paid $852,640 toward principal and $1,032,886 toward 
annual cost of operation and maintenance of project, 
including cost of operating 10-foot conduit. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Bardwell Lake project: 
Accumulated flood damages prevented through FY 1992 
were $25,601,801. 
4. BELTON LAKE, TX 
Location. Dam is on Leon River about 16.7 miles 
above confluence of Leon and Lampasas Rivers and about 
3 miles north of Belton, Texas. 
Existing project. For a description of completed 
improvement and authorizing acts see Annual Report of 
1962. Construction started June 1949 and project was 
ready for beneficial use in March 1954. Raising water 
supply pool: Construction started in July 1970 and the 
pool raise is complete. Estimated cost of project is 
$18,410,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with Brazos River Authority, a 
State agency, for remaining water supply storage in 
reservoir was approved by Secretary of the Army on 
January 15, 1958, at an estimated cost of $1,602,822. To 
date $1,383,547 has been paid. Under the contract Brazos 
River Authority must also pay annually 11.2 percent of 
actual annual cost of operation and maintenance. To date 
$1,605,680 has been paid. An interim contract with Brazos 
River Authority for emergency use of water supply storage 
in project was approved by Secretary of the Army on 
January 2, 1957. Amount of $433,083 paid by authority 
on March 21, 1957 for use of these facilities was credited 
to interest and principal payable under formal water 
supply contract. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
30-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Benefits accrued to Belton Lake project: Accumulated 
flood damages prevented through FY 1992 were 
$491,982,756. 
5. BENBROOK LAKE, TX 
Location. Dam is in Tarrant County, Texas, on Clear 
Fork of Trinity River 15 river miles upstream from its 
confluence with West Fork of Trinity River about 10 miles 
southwest of downtown Fort Worth, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Construction of project was started May 1947 and 
ready for beneficial use in September 1952. Estimated 
cost of project is $14,544,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. No water supply storage is included in 
project. In 1956, Congress passed legislation enabling the 
city of Fort Worth to purchase conservation storage space 
in Benbrook Lake. Contracts have been negotiated with 
the city of Fort Worth and the Benbrook Water and Sewer 
Authority for the use of portions of the navigation storage 
for water supply purposes until such storage is required 
for Trinity River Navigation. To date $379,685 has been 
paid by the city of Fort Worth and $136,425 by Benbrook 
Water and Sewer Authority. A cost sharing contract with 
the city of Benbrook for Recreation Development was 
approved by the Secretary of the Army May 20, 1977. To 
date, $19,024 has been paid. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to system consisting of Benbrook 
Lake, Clear Fork and West Fork Floodways: Accumulated 
flood damages prevented through FY 1992 are estimated 
at $2,153,991,920. 
6. BOGGY CREEK, AUSTIN, TX 
Location. The project is located on Boggy Creek in 
southeast portion of the city of Austin, Texas. 
Existing project. The Boggy Creek Channel 
Improvement Project consists of approximately 2 miles of 
concrete and gabion lined channel beginning just upstream 
of Webberville Road and extending downstream almost 
to Jain Lane. From there the Channel is about 1.0 mile 
of grasslined trapezoidal channel to Ed Bluestein 
(Highway 183) where it transitions back into the natural 
channel. The project includes a 54 acre tract near the 
lower end of the project which serves as a mitigation and 
environmental quality enhancement area. Approximately 
1.0 mile of nature trail is included in the mitigation/ 
enhancement area. The project required the replacement 
or modification of four bridges. It also included the 
replacement of two railroad bridges with one bridge. 
Estimated Federal cost is $16,660 and $8,000,000 non- 
Federal cost. 
The flood control channel provides capacities for the 
100 year flood. Design provided for containment of flows 
within the banks of the improved channels. Bottom widths 
for the concrete channel vary from 60 feet to 90 feet, and 
top widths from 80 feet to 120 feet. 
Local cooperation. In accordance with the cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, the City of Austin is 
required to continue routine operation and maintenance. 
Operations during fiscal year. Specific authorization 
for construction of Boggy Creek is found in FY 1985 
Supplemental Act. Construction of project was started in 
1986 and completed in April 1991. 
7. CANYON LAKE, TX 
Location. Dam is on Guadalupe River, 303 miles 
above its mouth, and about 12 miles northwest of New 
Braunfels, Comal County, Texas. 
Existing project. For a description of completed 
improvement and authorizing act see Annual Report of 
1969. Construction started April 1958 and project 
completed for beneficial use June 1964. Estimated cost of 
project is $21,732,000, including $1,400,000 contributed 
by local interests. 
Hydropower: The Guadalupe-Blanco River Authority 
(GBRA) was licensed by the Federal Energy Regulatory 
Commission to construct a 6,070 kilowatt plant which is 
located adjacent to the existing outlet channel. The project 
operates utilizing conservation releases, i.e., no change 
from the present operating regiment is anticipated. GBRA 
has an agreement with the Pedernales Electric 
Cooperative for sale of power. Construction of the 
hydropower was completed in 1989 with non-Federal 
funds. 
Local cooperation. Local interests (Guadalupe- 
Blanco River Authority) will utilize water impounded for 
water supply and streamflow regulation for development 
of electric power. In a formal contract approved by Chief 
of Engineers on October 24, 1957, Guadalupe-Blanco River 
Authority agreed to fulfill all requirements of local 
cooperation. Required contribution of $1,400,000 was 
made in full by Guadalupe-Blanco River Authority. The 
estimated cost of the water storage contract is about 
$9,000,000. To date $2,293,469 has been paid. In addition, 
$22,848 was contributed for installation and operation of 
reservoir leakage gages. Under the contract the authority 
must pay 34.8 percent of actual annual cost of operation 
and maintenance. To date $1,374,958 has been paid. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Canyon Lake project: Accumulated 
flood damages prevented through FY 1992 were 
$141,941,892. 
8. COOPER LAKE AND CHANNELS, TX 
Location. Cooper Dam is located in northeast Texas 
about 4 miles southeast of Cooper, 13.0 miles north of 
Sulphur Springs, and is at river mile 23.2 on the South 
Sulphur River. The South Sulphur River rises in Fannin 
County, Texas, and flows generally east for about 80 miles 
to its confluence with the North Sulphur River to form 
the Sulphur River. 
Existing project. The authorized plan of 
improvement consists of a multipurpose reservoir with 
levee and channel improvements on the Sulphur River. 
The reservoir consists of a rolled earthfill dam with a 
maximum height of about 79 feet, 28,070 feet long at its 
crest, a single conduit 10.5 feet in diameter, 530 feet 
30-4

FORT WORTH, TEXAS DISTRICT 
long, two 10.5 foot by 4.75 foot sluices, and a 700 foot 
wide uncontrolled concrete spillway. The reservoir surface 
area will be 22,740 acres at the top of the flood control 
pool, 19,305 acres at the top of the water supply pool, 
and 5,084 acres at the top of the sediment pool. The 
reservoir will contain 131,400 acre-feet of flood control 
storage, 273,000 acre-feet of municipal and industrial 
water supply storage, and 37,000 acre-feet of sediment 
storage. 
Construction of the project began in July 1958 and, 
to date, approximately 99 percent of the lands required 
for project construction have been acquired and 100 
percent of the levees and 100 percent of the channel work 
have been completed. Approximately 14.8 miles of the 
South Sulphur River and 6.3 miles of the Middle Sulphur 
River channels have been excavated. Approximately 3.4 
miles of levee embankment on the South Sulphur River 
and 7.3 miles on the Middle Sulphur River have been 
constructed upstream of the Cooper Lake. About 10.5 
miles of levee on the North Sulphur River, 8.2 miles of 
levee on the Sulphur River, 14 miles of levee on Cuthand 
Creek, and 4.2 miles of levee on Brushy Creek were 
strengthened; 0.5 mile of levee on Kickapoo Creek was 
enlarged; and 15.3 miles of new channel in Cuthand 
Creek, 0.8 mile of new channel in Brushy Creek, and 0.2 
mile of cutoff channel in Kickapoo Creek were excavated; 
all downstream from Cooper Lake. 
Lack of funds and spending limitations prevented 
construction of the levees and channel work between April 
1964 and February 1971. Construction was started again, 
however, in May 1971. The Texas Committee on Natural 
Resources, et. al., secured an injunction to halt 
construction on the project pending preparation of an 
Environmental Impact Statement (EIS), required by the 
National Environmental Policy Act of 1969. A statement 
was prepared and filed on June 24, 1977. The plan 
recommended, in the Final EIS, minimized further 
construction of the authorized channels and provided for 
construction of the lake and downstream levees. The 
sufficiency of the Final EIS was challenged in the court 
and in December 1978 the U.S. District Court for the 
Eastern District of Texas ruled the statement inadequate, 
citing five deficiencies and halting all further construction. 
A Supplemental EIS to comply with the court's decision 
was prepared and filed with the Environmental Protection 
Agency in March 1981. The recommended plan of 
improvement consists of the multipurpose lake, 48.2 miles 
of levee, and the acquisition of 24,724 acres of wildlife 
mitigation lands. All remaining channel and levee work 
was deleted from the recommended plan. The 
Supplemental EIS was filed with the court in July 1981 
and numerous motions, documents, affidavits, and briefs 
were subsequently filed. After the Supplemental EIS was 
filed in July 1981, numerous motions, documents, 
affidavits, and briefs were filed through October 1982. 
On December 30, 1982, the U.S. District Court issued a 
95-page order continuing the permanent injunction. On 
March 22, 1983, the order was revised and Judge William 
Wayne Justice issued an Amended Memorandum Opinion 
and a Permanent Injunction against the construction of 
Cooper Lake. The Government filed a Notice of Appeal 
with the court in May 1983. On July 16, 1984, litigation 
was resolved and the injunction was released. The project 
was transferred to the Fort Worth District at the end of 
FY 1979. Public Law 101-101, H. R. 101-235, approved 
September 29, 1989, authorized $5 million for additional 
recreation. Estimated Federal cost (Oct. 1, 1992 base price) 
is $144,000,000, non-Federal cost for land for the levees 
is $227,000 and in addition $55,100,000 is to be 
reimbursed by water supply users over a 50-year period. 
Local cooperation. Local interests (North Texas 
Municipal Water District, Sulphur River Municipal Water 
District, City of Irving) will utilize water impounded for 
present and future water supply. The total cost allocated 
to water supply to be reimbursed is $55,100,000. North 
Texas Municipal Water District, NTMWD, has contracted 
for 36.859 percent of the water supply storage for future 
use with deferred payments for ten years. Under the 
contract NTMWD must pay 13.803 percent of actual 
annual cost of operation and maintenance. Sulphur River 
Municipal Water District, SRMWD, has contracted for 
6.5 percent of the water supply storage for initial use and 
19.78 percent for future use for a total of 26.282 percent 
of the water supply storage. To date $77,463 has been 
paid. Under the contract SRMWD must pay 2.435 percent 
of actual annual operation and maintenance. To date 
$4,581 has been paid. The City of Irving has contracted 
for 16.923 percent of the water supply storage for initial 
use and 19.936 for future use for a total of 36.859 of the 
water supply storage. To date $166,854 has been paid. 
Under the contract Irving must pay 6.337 percent of actual 
annual operation and maintenance. To date $11,924 has 
been paid. 
The Texas Parks and Wildlife and the Corps of 
Engineers have entered into or have agreed to formal 
Operation and Maintenance contracts for recreation 
facilities and wildlife conservation and management. 
Under the contracts for recreation facilities dated 7 
November 1988 and 11 September 1990, Texas Parks 
and Wildlife will be responsible for 100 percent of the 
O&M of two state parks that are being constructed with 
Federal funds. Under the contracts for wildlife 
conservation and management, currently being finalized, 
the State will be responsible for 24.14 percent of the 
operations, maintenance and replacement annual costs 
for areas totaling approximately 35,500 acres. The 
remaining balance will be the responsibility of the Project 
Sponsors and the Government. 
Operations during fiscal year. During FY 1992 
the State of Texas Parks and Wildlife Department 
awarded recreation contracts. Other contracts awarded 
during the year were project and maintenance buildings. 
Cooper Lake and Channels is approximately 85 percent 
complete overall. Major items completed through FY 1992 
are Relocations of Railroads, 100 percent; Channels and 
Canals, 100 percent; Levees and Floodwalls, 100 percent; 
and Lands and Damages, 99 percent. Land Acquisition, 
Engineering and Design and construction continues. 
Deliberate Impoundment began 29 September 1991 and 
project completion is scheduled for February 1995. 
Benefits accrued to Cooper Lake and Channels project: 
Accumulated flood damages prevented through FY 1992 
are estimated at $946,258. 
30-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
9. FERRELLS BRIDGE DAMLAKE 
O' THE PINES, TX 
Location. Dam is on Cypress Creek in Marion, 
Harrison, Upshur, Morris, Camp, and Titus Counties, 
Texas, 8 miles west of Jefferson, Texas. 
Existing project. An earth-fill dam 10,600 feet long 
and 77 feet high includes a 200-foot spillway with a 
capacity of 68,200 cubic feet per second. Reservoir controls 
runoff from 850 square miles of drainage area, and has a 
gross storage capacity of 842,100 acre-feet, including 
587,200 acre-feet flood control storage, 3,800 acre-feet 
conservation storage, and 251,000 acre-feet for municipal 
and industrial water supply. Reservoir extends 28 miles 
upstream. Project affords substantial flood protection of 
Cypress Creek Valley from damsite to confluence with 
Red River and, together with operation of other reservoirs 
proposed in Red River Basin, will provide flood protection 
along main stem of Red River below Denison Dam. 
Construction commenced in January 1955 and was 
completed June 1960. Estimated Federal cost of project 
is $17,231,700 (Oct. 1, 1983, base price), including 
$4,349,200 for Code 711 and $399,739 accelerated Public 
Works fund. This project transferred to the Fort Worth 
District as of the end of FY 1979. 
Local cooperation. None required. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Ferrells Bridge Dam-Lake O' The 
Pines project: Accumulated flood damages prevented 
through FY 1992 were $30,753,763. 
10. GRAPEVINE LAKE, TX 
Location. Dam is in Tarrant County, Texas, on 
Denton Creek, 11.7 river miles upstream from its 
confluence with Elm Fork of Trinity River and about 20 
miles northwest of City of Dallas, Texas. 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report for 
1962. Construction of project was started December 1947 
and ready for beneficial use in July 1952. Estimated cost 
of project is $18,896,000, including $2,040,000 contributed 
by local interests. A contract for modification of 
Embankment and Spillway was awarded September 30, 
1983 and completed FY 1990. The improvements provided 
for spillway modification by construction of spillway chute 
and stilling basin and a berm on the downstream side of 
the main embankment. 
Local cooperation. A contract with Dallas County 
Park Cities Water Control and Improvement District No. 
2 for 50,000 acre-feet of water supply storage was 
approved by Secretary of the Army on March 21, 1955. 
Park Cities paid the required $607,000. A contract with 
City of Dallas for 85,000 acre-feet of water supply storage 
was approved by Secretary of the Army on March 17, 
1954. Dallas paid the required $1,433,026. A contract 
with City of Grapevine, Texas, for 1,250 acre-feet of water 
supply storage was approved by Secretary of the Army 
on September 14, 1953, at an estimated cost of $22,654. 
A contract for Interim Use of Navigation Storage with 
city of Grapevine was approved by Secretary of the Army 
on February 27, 1981, at an estimated cost of $684,000. 
To date, $121,478 has been paid. Above contracts include 
payment of operation and maintenance costs as follows: 
Dallas County Park Cities Water Control and 
Improvement District No. 2, a pro rata part of the actual 
annual cost, which part is to be not less than $2,000 nor 
more than $3,000; Dallas, 9.2 percent of actual annual 
cost; and Grapevine, its pro rata part of actual annual 
cost (estimated at $79.55 annually and included in total 
annual payment). Following operation and maintenance 
payments have been made: Park Cities $118,231, Dallas 
$588,999, and Grapevine $189,573 
Operations during fiscal year. Routine operation 
and maintenance continue. 
Benefits accrued to system comprised of Grapevine 
Lake and Dallas Floodway: Accumulated flood damages 
prevented through FY 1992 were $3,763,097,543. 
11. HORDS CREEK LAKE, TX 
Location. On Hords Creek, a tributary of Pecan 
Bayou, about 13.5 miles west of Coleman, Texas, and 
about 27.8 miles upstream from mouth of Hords Creek. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Construction of project was started January 1947 
and completed for beneficial use in April 1948. Estimated 
cost of project is $4,337,000 including $105,000 contributed 
by local interests. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Hords Creek project: Accumulated 
flood damages prevented through FY 1992 were 
$4,825,993. 
12. JOE POOL LAKE, TX 
Location. Dam site is located at River Mile 11.2 on 
Mountain Creek, a right bank tributary of the West Fork 
of the Trinity River, and is adjacent to the city limits of 
Grand Prairie, Dallas County, Texas, which is one of the 
rapid growing cities in the Dallas-Fort Worth Metropolitan 
area. 
Existing project. The project provides for 
construction of an earthfill dam with a maximum height 
of 108.5 feet above the streambed and a total length of 
22,360 feet, including 50-foot type spillway, which will 
control 232 square miles of drainage area. The reservoir 
will have a total controlled storage of 304,000 acre-feet 
and a water surface area of 10,940 acres at the top of the 
flood control pool and 7,470 acres at the top of the 
conservation pool. The total storage includes 123,100 acrefeet 
for flood control, 142,900 acre-feet for conservation 
and 38,000 acre-feet for sediment reserve. Estimated cost 
of the project is $226,390,000 (Oct. 1, 1992, base price) 
including $11,260,000 non-Federal first cost. Project is a 
unit in the general comprehensive plan for development 
and control of the water resources of the Trinity River 
Basin. 
Local cooperation. The Water Supply Act of 1958 
as amended, and the Federal Water Project Recreation 
Act of 1965 apply. Contracts for water supply storage 
and recreation with the Trinity River Authority were 
30-6

FORT WORTH, TEXAS DISTRICT 
approved by the Acting Secretary of the Army, June 15, 
1977. The recreation contract with Trinity Valley 
Authority was modified March 28, 1979, to allow the Corps 
to participate with the State of Texas and approved by 
the Assistant Secretary of the Army March 21, 1980. 
Recreation development contract with the State of Texas 
was approved by the Assistant Secretary of the Army 
March 21, 1980. Reimbursement is currently estimated 
at $57,150,000 for water supply and $8,660,000 for 
recreation (excluding future recreation facilities) for a total 
of $65,810,000 exclusive of interest. To date $40,465 has 
been paid. Of the actual annual cost of operation and 
maintenance, $4,107 has been paid. 
Operations during fiscal year. The project has 
been under construction since FY 1975 and through FY 
1992 is approximately 99 percent complete overall. All 
major items are complete thru FY 1992 except for the 
State Park recreation and the Penn Site restoration. 
Deliberate Impoundment began January 1986. Project 
completion is scheduled for May 1993. Public Law 97- 
400, H.R. 7377, 97th Congress, effective December 31, 
1982, changed the name of Lakeview Lake to Joe Pool 
Lake. 
Benefits accrued to Joe Pool Lake project: 
Accumulated flood damages prevented through FY 1992 
were $342,996,323. 
13. LAVON LAKE, TX 
Location. Dam is in Collin County, Texas, on East 
Fork of Trinity River 55.9 miles above its confluence with 
Trinity River and about 22 miles northeast of Dallas, 
Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Construction of project was started January 1948 
and ready for beneficial use in September 1953. Project 
is complete. See following section for Lavon Lake 
Modification and East Fork Channel Improvement 
authorized by Flood Control Act of 1962. Estimated cost 
of project is $15,470,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with North Texas Municipal 
Water District for water supply storage, including cost of 
intake structure, was approved by Secretary of the Army 
July 8, 1954, at an estimated cost of $1,405,753. Contract 
was revised in 1973 and final revised contract amount is 
$1,445,261.67. To date North Texas Municipal Water 
District has paid $3,505,688. Under the contract North 
Texas Municipal Water District must pay annually 13.6 
percent of actual annual cost of operation and 
maintenance, and to date has paid $743,445. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Lavon Lake project: Accumulated 
flood damages prevented through FY 1992 were 
$305,217,862. 
14. LAVON LAKE MODIFICATION AND 
EAST FORK CHANNEL 
IMPROVEMENT, TX 
Location. Existing dam is in Collin County, Texas, 
on East Fork of Trinity River, 55.9 miles above its 
confluence with Trinity River and about 22.0 miles 
northeast of Dallas, Texas. Channel improvement of East 
Fork extends from its mouth to River Mile 31.8. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1988. Construction of project was initiated in May 1970 
and ready for beneficial use in December 1975. Estimated 
Federal cost of the modification and improvement is 
$69,750,000 and $220,000 local interests, a total of 
$69,970,000. Project is complete. 
Local cooperation. Local interests must reimburse 
the Federal Government for costs allocated to increased 
water supply storage under the terms of the Water Supply 
Act of 1958. The North Texas Municipal Water District 
has contracted for 43 percent of the water supply 
(approved September 22, 1967, by the Secretary of the 
Army) and to date $3,492,486 has been paid. North Texas 
Municipal Water Supply District has submitted assurance 
to contract for 57 percent of future water supply. 
Reimbursement is currently estimated at $37,825,004. 
Levee Districts 4 and 5, which comprise the lower 10 
miles of the East Fork Channel, entered into agreements 
as required by Section 221 of the Flood Control Act of 
1970 on January 28, 1972 and have furnished all 
necessary construction easements. 
Levee Districts 6, 8, 10, 13, and 15, which comprise 
the upper 15 miles of the East Fork Channel, have 
declined to provide the necessary assurances. On 
December 8, 1972, this portion of the project was 
reclassified from "active" to "inactive" category. 
Operations during fiscal year. Improvement of the 
lower ten miles of the East Fork Channel and Levees and 
total project are 100 percent complete. 
15. LEWISVILLE DAM, TX 
Location. Dam is in Denton County, Texas, on Elm 
Fork of Trinity River 30 river miles above its confluence 
with Trinity River and about 22 miles northwest of City 
of Dallas, Texas at a site downstream from old Garza 
Dam. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Construction of project was started November 1948 
and ready for beneficial use in November 1954. Estimated 
cost of project is $25,902,000, including $3,677,000 
contributed by local interests. 
Hydropower: The city of Denton, Texas (COD) was 
licensed by the Federal Energy Regulatory Commission 
to construct a 2,000 kilowatt plant which is located 
adjacent to the existing outlet channel. The project 
operates utilizing conservation releases, i.e., no change 
from the present operating regiment is anticipated. COD 
Utilities Department utilizes this power for its local 
customers. Construction of the hydropower was completed 
in 1991 with non-Federal funds. 
Local cooperation. A contract with City of Dallas 
for 415,000 acre-feet of water supply storage land rights 
and interests to Garza Dam and Reservoir was approved 
by the Secretary of the Army on July 16, 1953. Local 
contributions have been made in full. A contract with 
city of Denton, Texas, for remaining 21,000 acre-feet of 
30-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
water supply storage was approved by the Secretary of 
the Army on May 20, 1954, with an estimated cost of 
$250,064. Local contributions have been paid in full. 
Under above contracts, cities of Dallas and Denison must 
pay annually 21.9 and 1 percent, respectively, of actual 
annual cost of operation and maintenance. To date Dallas 
has paid $3,507,626 and Denison $147,600. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to system comprised of Lewisville 
Lake: Accumulated flood damages prevented through FY 
1992 were $4,615,514,998. 
16. NAVARRO MILLS LAKE, TX 
Location. Dam is in Navarro County, Texas, at River 
Mile 63.9 on Richland Creek, a tributary of Trinity River, 
about 16.0 miles southwest of Corsicana, Texas. 
Existing project. For description of completed 
improvement and authorization acts see Annual Report 
for 1965. Construction started December 1959 and project 
completed for beneficial use March 1963. Estimated cost 
of project is $13,154,000, including $300,000 contributed 
by local interests. 
Local cooperation. The Water Supply Act of 1958, 
as amended applies. A formal contract with the Trinity 
River Authority was approved March 3, 1966, by the 
Secretary of the Army at an estimated cost of $2,260,800. 
To date the Authority has paid $995,286 for water supply 
and $1,055,682 for operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Navarro Mills Lake project: 
Accumulated flood damages prevented through FY 1992 
were $95,375,634. 
17. O.C. FISHER DAM AND LAKE, TX 
Location. Dam is on North Concho River, a tributary 
of Concho River, about 6.6 miles above mouth of North 
Concho River near city of San Angelo, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Name was changed from San Angelo Dam and 
Reservoir to O.C. Fisher Dam and Lake January 3, 1975 
by Public Law 93-634. Construction of project was started 
May 1947 and ready for beneficial use February 1952. 
Estimated cost of project is $17,111,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A water-supply contract with Upper 
Colorado River Authority for water-supply storage in 
reservoir was approved by Secretary of the Army on 
October 11, 1948. The Authority has contributed $860,444 
toward cost of project and $64,336 toward operation and 
maintenance for a 50-year period. The Authority must 
pay additional contributions of $1 a year for useful life of 
project, beginning January 1, 1965. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to O.C. Fisher Dam and Lake project: 
Accumulated flood damages prevented through FY 1992 
were $15,646,213. 
18. PROCTOR LAKE, TX 
Location. Dam is at River Mile 238.9 on Leon River, 
a tributary of Brazos River, about 8.0 miles northeast of 
Comanche in Comanche County, Texas. 
Existing project. For description of completed 
improvement and authorization act see Annual Report of 
1969. Construction of project was started July 1960 and 
completed for beneficial use 1963. Estimated cost of project 
is $16,249,000. 
Local cooperation. The Water Supply Act of 1958 
applies. A formal contract with the Brazos River 
Authority, a State agency, was approved by Secretary of 
the Army, July 1, 1960, and was modified and approved 
May 9, 1966, at an estimated cost of $1,707,900. To date 
the Authority has paid $445,329 for water supply and 
$415,517 for operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance were continued. 
Benefits accrued to Proctor Lake project: Accumulated 
flood damages prevented through FY 1992 were 
$50,809,796. 
19. RAY ROBERTS LAKE, TX 
Location. Damsite is located at River Mile 60.0 on 
the Elm Fork of the Trinity River, Denton County, 
between Sanger and Aubrey, Texas and 30 miles upstream 
from Lewisville Dam. 
Existing project. The plan of improvement provides 
for construction of an earthfilled dam with a maximum 
height of 141 feet above the streambed, a length of 15,250 
feet including an uncontrolled broadcrested spillway 100 
feet long, controlling 682 square miles of drainage area. 
The lake will have a total controlled storage of 1,064,600 
acre-feet, with a water surface area of 36,900 acres. The 
total storage includes 260,800 acre-feet for flood control, 
749,200 acre-feet for water supply, and 54,600 acre-feet 
for sediment reserve. The Water Resource Development 
Act of 1990 authorized the Greenbelt Corridor between 
Lewisville and Ray Roberts Lakes. Estimated Federal 
cost of the project is $302,800,000 (Oct. 1, 1992, base 
price). Public Law 96-384, 96th Congress, H.R. 8094, 
effective January 4, 1981, changed the name of Aubrey 
Lake to Ray Roberts Lake. 
Hydropower: At the request of the City of Denton 
and the approval of the Secretary of the Army, the 
penstock was added to the embankment as a minimum 
facility for future hydropower. The city of Denton, Texas 
(COD) was licensed by the Federal Energy Regulatory 
Commission to construct a 1,000 kilowatt plant which is 
located adjacent to the existing outlet channel. The project 
operates utilizing conservation releases, i.e., no change 
from the present operating regiment is anticipated. COD 
Utilities Department utilizes this power for its local 
customers. Construction of the hydropower was completed 
in 1991 with non-Federal funds. 
Local cooperation. The Water Supply Act of 1958 
as amended and the Federal Water Project Recreation 
Act of 1965 and Section 221, Flood Control Act of 1970 
apply. Contracts with the cities of Dallas and Denton, 
Texas, for water supply storage and recreation were 
30-8

FORT WORTH, TEXAS DISTRICT 
approved by the Secretary of the Army September 16, 
1980. To date the city of Dallas has paid $4,308,632 and 
the city of Denton has paid $1,513,807 toward principal. 
Dallas has paid $99,217 and Denton has paid $34,859 
toward annual cost of operation and maintenance of 
project. 
Operations during fiscal year. The project is about 
97 percent complete overall. Through FY 1992 about 94 
percent of the land acquisition, the road and utility 
relocations and the embankment, spillway and outlet 
works have been completed. Major work items remaining 
to be completed are boundary delineation at Lewisville 
Lake, flood damage repairs, seepage control, recreational 
facilities, wetlands, and the Greenbelt. Deliberate 
Impoundment began 30 June 1987 at Ray Roberts Lake, 
the pool raise at Lewisville Lake was 30 November 1988. 
The project is scheduled to be completed in July 1996. 
Benefits accrued to Ray Roberts Lake project: 
Accumulated flood damages prevented through FY 1992 
were $923,196,379. 
20. SAN ANTONIO CHANNEL 
IMPROVEMENT, TX 
Location. Floodway is in city of San Antonio, Bexar 
County, Texas, on San Antonio River and San Pedro, 
Apache, Alazan, Martinez Creeks, and Espada Aqueduct 
located in vicinity of Six Mile Creek. 
Existing project. The project consists of 30.7 miles 
of channel and associated improvements on six separate 
streams. Completion of detailed engineering and design 
studies revealed that the least costly alternative for the 
remaining channel improvements would consist of two 
tunnels. The San Pedro Creek tunnel would be 6,040 feet 
in length and the San Antonio River tunnel would be 
16,360 feet in length, and construction and alteration of 
railroad bridges. Estimated Federal cost of these 
modifications is $137,100,000 (Oct. 1, 1992, base price), 
and estimated cost to local interests is $72,800,000 which 
includes $3,600,000 cash contributions and $69,200,000 
for lands, damages, and construction, a total of 
$209,900,000. Existing project was authorized by 1954 
Flood Control Act. The Water Resources Act of 1976 added 
authorization to the existing project for construction of 
flood control measures needed to preserve and protect 
the Espada Aqueduct located in the vicinity of Six Mile 
Creek. Construction was started in October 1957 and the 
project is about 93 percent complete. The Federal portion 
of the project is scheduled to be completed in November 
1995. 
Local cooperation. Local interests must furnish 
lands and rights-of-way for construction, including 
purchase and removal of buildings, relocation or 
reconstruction of bridges (exclusive of railway bridges), 
channel dams where applicable, and utility lines; hold 
the United States free from damages; maintain and 
operate all works after completion; and provide a cash 
contribution for enhancement benefits of 2.65 percent of 
actual Federal construction cost. San Antonio River 
Authority furnished assurances that it will comply with 
all requirements of local cooperation. These assurances 
were accepted by the District Engineer on April 15, 1957. 
To date $3,239,000 has been contributed by San Antonio 
River Authority. In addition, $30,000 has been contributed 
and accepted, under the authority of Civil Functions 
Appropriations Act of 1958, for vehicular crossings over 
the San Antonio Channel. 
Operations during fiscal year. FY 1992 funds were 
used to continue construction and engineering and design 
studies. 
Benefits accrued to San Antonio project: Accumulated 
damages prevented through FY 1992 were $192,965,446. 
21. SAN GABRIEL RIVER, TX 
Location. Project is a system of three reservoirs in 
Williamson County in the central portion of Brazos River 
Basin, which consists of Granger Dam at River Mile 31.9 
on San Gabriel River, about 7.0 miles east of Granger, 
Texas; North San Gabriel Dam at River Mile 4.3 on North 
Fork of San Gabriel River, about 3.5 miles northwest of 
Georgetown, Texas; and South Fork Dam at River Mile 
4.7 on South Fork of San Gabriel River, about 3.0 miles 
southwest of Georgetown, Texas. 
Existing project. Granger Lake was authorized by 
1954 Flood Control Act, and North (North San Gabriel 
Dam and Lake Georgetown) and South Fork Lakes were 
authorized by 1962 Flood Control Act. Estimated total 
Federal cost of project is $181,400,000 (Oct. 1, 1986, base 
price) and estimated non-Federal cost of $90,600,000 for 
a project total of $272,000,000. Plan of improvement 
provides for the following: Granger: An earthfilled dam 
16,320 feet long, including spillway with maximum height 
of 115 feet above streambed, which controls 709 square 
miles of drainage area. Reservoir provides a total storage 
capacity of 244,200 acre-feet, of which 162,200 acre-feet 
are for flood control, 37,900 acre-feet for water supply 
storage, and 44,100 acre-feet for sediment reserve. 
Estimated cost of project is $62,062,000. North San 
Gabriel Dam: A rockfill dam 6,700 feet long, including 
spillway with maximum height of 164 feet above 
streambed, which controls 246 square miles of drainage 
area. Reservoir provides a total storage capacity of 130,800 
acre-feet of which 87,600 acre-feet are for flood control, 
29,200 acre-feet for water supply storage, and 14,000 acrefeet 
for sediment reserve. Estimated cost of project is 
$38,765,000. South Fork: A rockfill dam 5,620 feet long, 
including spillway with maximum height of 152 feet above 
streambed, which controls 123 square miles of drainage 
area. Reservoir provides a total storage capacity of 82,600 
acre-feet (45,700 for flood control, 28,900 for water supply 
storage, and 8,000 for sediment reserve). Estimated cost 
of project is $171,173,000. Public Law 96-575, 96th 
Congress, H.R. 4941 effective January 4, 1981, changed 
the name of North Fork Lake to North San Gabriel Dam 
and Lake Georgetown. 
Local cooperation. Construction is subject to 
condition that local interests reimburse the Federal 
Government for costs allocated to water supply at Granger, 
Lake Georgetown, and South Fork Lakes. Reimbursement 
currently estimated at $13,315,000 for Granger, 
$6,295,000 for Lake Georgetown, and $50,563,000 for 
South Fork, for a total of $70,172,000 exclusive of interest. 
Brazos River Authority, a State agency, is the local 
interests' sponsor of project, and by letter dated April 18, 
30-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
1966, indicated its acceptance of the proposed plan of 
development and its willingness to pay for the costs 
allocated to water supply in each reservoir in the ultimate 
plan. Such water supply assurances for Granger and Lake 
Georgetown Lakes were approved May 24, 1968 as 
satisfactory in accordance with requirements of the Water 
Supply Act of 1958, as amended. Contract negotiations 
for South Fork Lake will be deferred until the need for 
water supply develops and the reservoir is scheduled for 
construction. 
Operations during fiscal year. Through 1983 all 
work has been completed. Deliberate impoundment of 
water commenced at Granger and Lake Georgetown Lakes 
on January 21, 1980 and March 3, 1980, respectively. In 
FY 1982, studies on South Fork Lake were resumed in 
preparation of General Design Memorandum to provide 
reaffirmation prior to construction. A Draft Reevaluation 
Report on South Fork Lake was submitted to headquarters 
in October 1986. The report recommended no Federal 
action and defer further studies indefinitely. Future water 
supply needs of the area would be addressed by 
reallocating storage at Granger Lake. The South Fork 
Lake project was placed on inactive status and would be 
eligible for deauthorization in FY 1997 if no funds are 
obligated by then. 
Benefits accrued to project consisting of Granger and 
Lake Georgetown: Accumulated flood damages prevented 
through FY 1992 were $38,569,917. 
22. SOMERVILLE LAKE, TX 
Location. Dam is on Yegua Creek 20 miles upstream 
from its confluence with Brazos River and about 2 miles 
south of Somerville, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report of 
1969. Construction started in June 1962 and project was 
ready for beneficial use in January 1967. Estimated cost 
of project is $30,227,000. 
Local cooperation. The Water Supply Act of 1958, 
as amended, applies. A contract with the Brazos River 
Authority, a State agency, for water supply storage 
approved May 10, 1962, by the Secretary of the Army, 
has paid $1,632,406 to date. Also under the contract, the 
authority must pay annually 28.655 percent of the actual 
annual cost of operation and maintenance. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Somerville Lake project: 
Accumulated flood damages prevented through FY 1992 
were $90,100,141. 
23. STILLHOUSE HOLLOW DAM, TX 
Location. Dam is on Lampasas River 16 miles 
upstream from its confluence with Little River, a tributary 
of the Brazos River, and about 5 miles southwest of Belton, 
Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report of 
1969. Construction was initiated in July 1962 and the 
project was ready for beneficial use in February 1968. 
Estimated cost of project is $23,670,000. 
Local cooperation. The Water Supply Act of 1958 
applies. A contract with the Brazos River Authority, a 
State agency, for water supply storage was approved April 
13, 1962, by the Secretary of the Army, at an estimated 
cost of $6,912,430. To date the Authority has paid 
$2,063,969. Also under the contract the Authority must 
pay annually 27.748 percent of the actual annual cost of 
operation and maintenance. To date the Authority has 
paid $913,056. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Stillhouse Hollow Dam Project: 
Accumulated estimate of flood damages prevented through 
FY 1992 is $55,871,623. 
24. WACO LAKE, TX 
Location. Dam is on Bosque River, 4.6 river miles 
above its confluence with Brazos River, at City of Waco, 
McLennan County, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report of 
1969. Estimated cost of project is $50,853,000 including 
$250,000 contributed by local interests and $2,500,000 
other non-Federal cost. Construction was started in July 
1958, and project was ready for beneficial use in February 
1965. 
Local cooperation. Section G of the Flood Control 
Act of December 1944 applies. A contract with the Brazos 
River Authority, a State agency, for water supply storage 
and the contract with the City of Waco transferring the 
existing Lake Waco to the Government for their water 
storage, was approved by the Secretary of the Army on 
April 15, 1958. To date, the Authority for their portion of 
the water supply storage has paid $2,209,548. Also under 
the contract the Authority and the City must pay 14.706 
and 2.087 percent respectively of the actual cost of 
operation and maintenance. To date the Authority has 
paid $1,016,710 and the City has paid $157,681. A contract 
with the Brazos River Authority, for additional storage 
for municipal and industrial water supply, was approved 
by the Acting Assistant Secretary of the Army, September 
28, 1984. 
Operations during fiscal year. Routine operations 
and maintenance continued. 
Benefits accrued to Waco Lake project: Accumulated 
flood damages prevented through FY 1992 were 
$266,324,638. 
25. WRIGHT PATMAN DAM AND 
LAKE, TX 
Location. Dam is on Sulphur River in Cass and 
Bowie Counties, Texas. Dam is 45 miles above mouth of 
Sulphur River, and about 8 miles southwest of Texarkana, 
Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report of 
1984. Estimated cost of project is $51,945,000 which 
includes $5,449,100 Code 711, $399,939 accelerated public 
works funds, and $13,138,004 to be reimbursed by local 
interests, over a period not to exceed 50 years, for water 
supply storage, and including $2,092,040 for pro rata share 
30-10

FORT WORTH, TEXAS DISTRICT 
of original reservoir cost. Construction was initiated in 
August 1948 and completed in March 1962, except real 
estate activities, construction under Code 711, and 
conversion of 120,000 acre-feet to water supply storage 
after completion of Cooper Reservoir. This project 
transferred to the Fort Worth District as of the end of FY 
1979. 
Local cooperation. A contract with the city of 
Texarkana, Texas, for reserving water supply storage 
space was approved by the Secretary of the Army 
December 17, 1968. To date, the City has paid $597,708. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
Benefits accrued to Wright Patman Dam and Lake 
project: Accumulated flood damages prevented through 
FY 1992 were $70,524,686. 
26. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection of completed local flood protection projects 
is made periodically in compliance with Section 208.10, 
of Title 33, Code of Federal Regulations, which contains 
regulations for operation and maintenance of local floodprotection 
works approved by Secretary of the Army in 
accordance with authority in Section 3, Flood Control Act 
of June 22, 1936. See Table 30-D for inspections made 
this fiscal year. 
Inspection costs for FY from regular funds for 
maintenance were $65,215. Total costs to September 30, 
1992 were $982,939. 
27. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with Flood Control Act of 1944, 
expenditures were made for scheduling flood control 
reservoir operations and preparation of reservoir 
regulation manual for Marshall Ford Dam, on the 
Colorado River, near City of Austin, Texas, and for 
preparation of reservoir regulation manual for Twin 
Buttes Dam, on Middle and South Concho Rivers near 
City of San Angelo, Texas. Marshall Ford Dam was 
authorized by 1937 River and Harbor Act. Project was 
constructed jointly by Bureau of Reclamation and Lower 
Colorado River Authority and was completed during FY 
1942. Twin Buttes Reservoir was authorized for 
construction by Department of Interior by Public Law 
152, 85th Congress. Construction was initiated in June 
1960; closure of dam started in June 1962; deliberate 
impoundment was started January 23, 1963. 
Accumulated damages prevented by Marshall Ford 
Reservoir through FY 1992 were $256,108,000 and by 
Twin Buttes through FY 1992 were $418,000. Twin Buttes 
Reservoir consists of two separate pools, one on South 
Concho River and the other on Middle Concho River and 
Spring Creek. Equalizing channel between these two pools 
is at elevation 1925.0. Costs for fiscal year from regular 
funds for operation of both reservoirs were $41,449. 
28. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
(See Table 30-C.) 
29. WORK UNDER SPECIAL 
AUTHORIZATION 
(See Table 30-E.) 
Flood control activities pursuant to Section 205, Public 
Law 585, 80th Congress, as amended (preauthorization); 
emergency streambank protection under Section 14, Public 
Law 526, 79th Congress, as amended; Snagging and 
Clearing of navigable streams and tributaries in interest 
of flood control, Section 208, Public Law 780, 83rd 
Congress, as amended. Emergency flood control, 
hurricane-flood, and shore protection activities (Public 
Law 99, 84th Congress, and antecedent legislation). 
Fiscal year costs were $117,496 for disaster 
preparedness; no levee repair. 
Multi-Purpose Projects Including Power 
30. ROBERT DOUGLAS WILLIS 
HYDROPOWER, TX 
Location. For location of completed dam see Town 
Bluff Dam-B.A. Steinhagen Lake, Texas in this chapter. 
Existing project. Installation of hydroelectric power 
generating facilities at Town Bluff Dam was authorized 
by the River and Harbor Act of 1945 (Public Law 79-14), 
March 2, 1945, but deferred in the original construction. 
Town Bluff Dam was completed and placed in operation 
in 1951. A Design Analysis Report completed in April 
1982 and a Feasibility Report was approved September 
9, 1983 indicated that installing hydropower at this project 
is now economically feasible. The hydropower facilities 
will include a 6,000 kilowatt power plant (two units at 
3,000 kilowatts each), intake and outlet facilities, and 
necessary switchgear equipment to be located in the main 
embankment at the old diversion channel and will be 
operated remotely from the Sam Rayburn project. The 
installation and operation of hydropower facilities will 
not result in the altering of the existing operation at 
Town Bluff. The project will produce an estimated 35,900 
megawatt hours of energy per year. There is no Federal 
cost on this project. It is completely funded by non-Federal 
funds. The estimated non-Federal cost is $18,900,000. 
101st Congress House Report 923, effective February 7, 
1989, changed the name of Town Bluff Hydropower to 
Robert Douglas Willis Hydropower. 
Local cooperation. A contract with the Sam 
Rayburn Municipal Power Authority was approved by 
Secretary of the Army, June 28, 1985, relative to 
financing, escrow agreement, and power sales agreement. 
Operation during fiscal year. Construction was 
initiated July 1986 and completed in December 1991. 
Project completion date is scheduled for 1993. 
31. SAM RAYBURN DAM AND 
RESERVOIR, TX 
Location. Dam is on Angelina River 25.2 miles 
upstream from its confluence with Neches River and about 
10.0 miles northwest of Jasper, Texas. 
Existing project. For description of completed 
improvements and authorizing act see Annual Report 
1969. Construction was started August 1956 and project 
30-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
was ready for beneficial use in March 1965. Estimated 
cost of project is $68,683,000 including $3,000,000 
contributed by local interests. 
Local cooperation. A contract with the Lower 
Neches Valley Authority, a State agency, to contribute 
$3,000,000 toward the first cost and an additional 
$200,000 annually for 50 years after completion of the 
project was approved by the Secretary of the Army on 
January 22, 1957. Contribution of $3,000,000 was made 
in full and annual payments to date of $4,400,000 have 
been made by the Authority. 
A contract with the City of Lufkin for water supply 
storage was approved May 27, 1969 by the Secretary of 
the Army at an estimated cost of $525,600. To date the 
City has paid $163,883. Also under the contract the City 
of Lufkin must pay annually 0.692 percent of the annual 
cost of operation and maintenance. To date the City has 
paid $143,672. 
Operations during fiscal year. Continued routine 
operation and maintenance. 
Benefits accrued to Sam Rayburn project: 
Accumulated flood damages prevented through FY 1992 
were $410,195,686. 
32. SAM RAYBURN SPILLWAY (DAM 
SAFETY ASSURANCE), TX 
Location. For location of completed dam see Sam 
Rayburn Dam and Reservoir, Texas in this chapter. 
Existing project. The existing 2200-foot wide 
uncontrolled spillway is constructed through erodible loose 
sand, shaley clay, and sandstone. Based on experience of 
significant erosion at other uncontrolled and unlined 
spillways constructed through less erodible material, the 
spillway at Sam Rayburn Dam would experience severe 
erosion damage and probably breach during passage of 
floods in excess of the 150-year flood frequency (25 percent 
of Probable Maximum Flood). The modification of the 
spillway consists of constructing a new reinforced concrete 
weir, stilling basin and outfall channel at or near the 
existing spillway structure. The proposed weir would have 
a width of 640 feet, an overall length of 433 feet, an 
outfall channel approximately 5,000 feet long and a crest 
elevation of 176.0 feet NGVD. Estimated Federal cost for 
the spillway modification is $42,000,000 (Oct. 1, 1992, 
base price) and $1,000,000 is to be reimbursed by 
hydropower sponsor. 
Operations during fiscal year. Engineering and 
Design continues. 
33. TOWN BLUFF DAMB.
A. STEINHAGEN LAKE, TX 
Location. Dam is on Neches River about 12.4 miles 
below mouth of Angelina River, one-half mile north of 
Town Bluff, Texas, and 93.0 river miles north of 
Beaumont, Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Construction started March 1947 and project was 
ready for beneficial use in April 1951. Estimated cost of 
project is $9,888,000, including $2,000,000 contribution 
by local interests. 
Local cooperation. Completed as required. 
Operations during fiscal year. Routine operation 
and maintenance continued. 
34. WHITNEY LAKE, TX 
Location. Dam is on Brazos River, about 442 miles 
above mouth of river, 5.5 miles southwest of Whitney, 
Texas, and about 38 miles upstream from City of Waco, 
Texas. 
Existing project. For description of completed 
improvement and authorizing acts see Annual Report for 
1962. Construction of project was started June 1946 and 
ready for flood control use in December 1951. First power 
was placed on-the-line in June 1953. Raise power pool is 
complete. Estimated cost of project is $46,306,000. 
Local cooperation. Section 2, Flood Control Act of 
1938, applies. A contract with the Brazos River Authority, 
a State agency, for water supply storage was approved by 
the Secretary of the Army November 3, 1982. To date, 
the authority has paid $241,115. 
Operations during fiscal year. Continued routine 
operation and maintenance. 
Benefits accrued to Whitney Lake project: 
Accumulated flood damages prevented through FY 1992 
were $649,729,351. 
General Investigations 
35. SURVEYS 
Fiscal year costs were $2,220,488 for flood damage 
prevention studies; $43,384 for coordination with other 
agencies; $0 for review of authorized projects; $98,052 for 
miscellaneous activities; and $0 for preauthorization 
studies Phase I for a total of $2,361,924. 
36. PRECONSTRUCTION 
ENGINEERING AND DESIGN 
BEALS CREEK, BIG SPRING, TX: 
Beals Creek is located in the city of Big Spring, 
Howard County, Texas. The project includes local 
protection features including channel improvement and 
relocations. The channel will be a trapezoidal grass-lined 
channel with an average depth of about 11 feet and a 
bottom width of 20 feet. The estimated planning and 
engineering estimate is $1,160,000. Planning and 
engineering studies were initiated in Fiscal Year 1988. 
Fiscal year costs were $83,882. 
DALLAS FLOODWAY EXTENSION, TX: 
Dallas Floodway Extension is located on the Trinity 
River in the City of Dallas, Dallas County, Texas. The 
plan of improvement provides for extending the existing 
Floodway downstream about 9 miles to the confluence of 
the Trinity River and Five Mile Creek. The plan consists 
of a leveed floodway and flood conveyance improvement 
(channel) along the main stem, Five Mile Creek and White 
Rock Creek. Maintained free of encroachments, the levees 
and channels would provide Standard Project Flood 
protection for approximately 7,300 acres of urban lands 
30-12

FORT WORTH, TEXAS DISTRICT 
currently subject to flooding. The estimated planning and 
engineering estimate is $5,000,000. Planning and 
engineering studies were initiated in Fiscal Year 1991. 
Fiscal year costs were $425,100. 
FIVE MILE CREEK, DALLAS, TX: 
Five Mile Creek is located in the southwestern portion 
of Dallas County, entering the Trinity River just north of 
Hutchins, Texas. The plan consists of enlarging the 
channel in the middle portion of the watershed, possible 
channelization of some major tributaries, and detention 
ponds in the upper portion of the watershed. The 
estimated planning and engineering estimate is 
$1,600,000. Planning and engineering studies were 
initiated in Fiscal Year 1989. Fiscal year costs were 
$48,605. 
SHOAL CREEK (HANCOCK CREEK), AUSTIN, TX: 
Hancock Creek, a tributary to Shoal Creek, Austin, 
Texas, flows through a highly urbanized area of Austin. 
The authorized project will consist of approximately 4,700 
feet of grass-lined channel, concrete-lined channel, and 
selective clearing along Hancock Creek from Houston 
Street to its confluence with Shoal Creek with bottom 
widths varying between 25 and 50 feet. The project will 
also include alteration to or replacement of three highway 
bridges, construction of a 10-foot by 10-foot box culvert to 
divert flows around a shopping center, relocation of utility 
lines, and acquisition of approximately 4 acres of lands 
and easements for construction purposes. The estimated 
planning and engineering estimate is $780,000. Planning 
and engineering studies were initiated in Fiscal Year 1992. 
Fiscal year costs were $204,672. 
37. COLLECTION AND STUDY OF 
BASIC DATA 
Work was continued under the Flood Plain 
Management Services on the compilation of information 
on floods and potential flood damages, including 
identification of those areas subject to inundation. Fiscal 
year expenditures for these activities totaled $226,913. 
Fiscal year costs were $11,056 for hydrologic studies. 
30-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
This page intentionally left blank. 
30-14

FORT WORTH, TEXAS DISTRICT 
COST AND FINANCIAL STATEMENT 
in Text Project 
1. Trinity River Project, 
TX Includes Channel to 
Liberty, Tennessee 
Colony Lake, and Dallas 
Floodway Extension 
2. Aquilla Lake, TX 
3. Bardwell Lake, TX 
4. Belton Lake, TX 
5. Benbrook Lake, TX 
6. Boggy Creek, TX 
(Federal Costs) 
(Contributed Funds) 
7. Canyon Lake, TX 
8. Cooper Lake and 
Channels, TX 
(Contributed Funds) 
9. Ferrells Bridge Dam 
Lake O' The Pines, TX 
10. Grapevine Lake, TX 
Funding 
New Work: 
Approp. 
Cost 
Total Cost To 
FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992"n 
- 22,574,865 
- 22,574,865 
New Work: 
Approp. - - - - 45,506,300 
Cost - - - - 45,506,300 
Maint. 
Approp. 532,500 520,507 516,000 544,000 4,182,107 
Cost 529,579 438,501 534,383 600,262 4,154,794 
New Work: 
Approp. - - - - 10,934,505 
Cost - - - - 10,934,505 
Maint. 
Approp. 1,194,800 1,632,675 1,156,938 1,964,000 19,415,82218 
Cost 1,183,423 1,168,319 1,601,315 1,977,376 18,222,19818 
New Work: 
Approp. - - - - 16,960,549 
Cost - - - - 16,960,5491 
Maint. 
Approp. 1,716,300 2,533,345 1,791,000 2,845,000 27,688,10918 
Cost 1,761,276 1,638,622 2,638,460 2,398,521 27,070,89218 
New Work: 
Approp. - - - - 13,130,463 
Cost - - - - 13,069,9912 
Maint. 
Approp. 1,245,400 2,262,948 1,581,950 1,495,000 25,416,33518 
Cost 1,376,992 1,505,796 1,002,687 1,557,277 23,979,34118 
New Work: 
Approp. 4,205,000 6,651,000 1,392,000 (-)75,000 17,338,000 
Cost 2,769,539 7,585,800 2,732,816 56,482 17,334,619 
New Work: 
Approp. 35,132 1,215,500 399,321 - 2,589,221 
Cost 281,160 1,158,253 756,071 (-)35,792 2,517,193 
New Work: 
Approp. - - - - 19,088,5243 
Cost - - - - 19,088,524 
Maint. 
Approp. 1,186,900 1,306,478 1,292,000 1,544,000 19,387,50418 
Cost 1,169,578 1,266,674 1,352,930 1,397,919 18,957,00218 
New Work: 
Approp. 20,534,000 23,265,000 12,846,000 9,102,000 116,922,887 
Cost 24,757,172 22,945,751 13,279,210 11,132,249 113,820,838 
New Work: 
Approp. - - - - 227,000 
Cost - - - - 227,000 
Maint. 
Approp. - - 5,000 541,000 546,000 
Cost - - - 520,741 520,741 
New Work: 
Approp. - - - - 14,175,1974 
Cost - - - - 14,175,19756 
Maint. 
Approp. 1,680,700 2,780,974 2,180,998 2,276,000 32,690,02518 
Cost 1,721,149 2,073,792 2,838,139 2,257,701 32,603,64318 
New Work: 
Approp. - - - - 21,317,790 
Cost 6,050 512 - - 21,317,790 
Maint. 
Approp. 1,912,100 2,624,949 1,715,000 1,665,600 29,862,93916 
Cost 1,903,328 1,734,685 2,621,486 1,625,900 29,765,22018 
30-15 
TABLE 30-A 
See 
Section 
SSeeection

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 30-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 89 FY 90 
11. Hords Creek Lake, TX New Work: 
Approp. - - 
Cost - - 
Maint. 
Approp. 769,600 732,748 
Cost 772,873 707,564 
12. Joe Pool Lake, TX New Work: 
Approp. 5,182,000 2,087,000 
Cost 10,379,003 2,496,541 
Maint. 
Approp. 529,900 496,620 
Cost 532,438 480,658 
13. Lavon Lake, TX New Work: 
Approp. - - 
Cost - - 
Maint. 
Approp. 1,841,300 3,058,296 
Cost 1,850,509 1,934,149 
14. Lavon Lake Modification New Work: 
& East Fork Channel Approp. - - 
Improvement, TX Cost - - 
15. Lewisville Dam, TX New Work: 
Approp. - - 
Cost - - 
Maint. 
Approp. 2,108,300 4,814,960 
Cost 2,133,211 3,251,393 
16. Navarro Mills Lake, TX New Work: 
Approp. - - 
Cost - - 
Maint. 
Approp. 1,311,800 1,423,654 
Cost 1,286,746 1,223,316 
17. O.C. Fisher Dam and New Work: 
Lake, TX Approp. - - 
Cost - - 
Maint. 
Approp. 867,400 907,035 
Cost 851,790 885,734 
18. Proctor Lake, TX New Work: 
Approp. - - 
Cost - - 
Maint. 
Approp. 1,401,800 2,111,287 
Cost 1,413,347 1,221,199 
19. Ray Roberts Lake, TX New Work: 
Approp. 15,583,000 16,427,000 
Cost 13,682,191 18,602,293 
Maint. 
Approp. 449,600 581,002 
Cost 456,846 523,614 
30. Robert Douglas Willis New Work: 
Hydropower, TX Contrib. 3,458,000 104,000 
(Contributed Funds) Cost 3,385,422 157,592 
31. Sam Rayburn Dam and New Work: 
Reservoir, TX Approp. - - 
Cost - - 
Maint. 
Approp. 2,305,100 2,201,218 
Cost 2,288,354 1,956,530 
32. Sam Rayburn Spillway New Work: 
(Dam Safety Assurance), Approp. - 200,000 
TX Cost - 101,856 
FY 91 FY 92 Sep. 30, 199217 
809,000 
778,039 
230,000 
925,867 
668,988 
669,718 
2,079,000 
3,182,751 
3,099,300 
4,507,035 
981,959 
1,187,582 
1,495,000 
1,540,284 
1,193,998 
2,034,878 
7,964,000 
9,360,490 
555,000 
547,667 
50,000 
123,828 
2,733,000 
2,919,386 
400,000 
177,798 
- 2,731,0898 
- 2,731,089 
928,000 13,844,21718 
954,698 13,730,12218 
426,000 187,914,000 
595,234 187,818,145 
555,000 3,162,608 
557,343 3,128,282 
- 12,864,796 
- 12,864,796 
2,721,000 32,815,93618 
2,138,896 32,141,69618 
- 69,796,862 
- 69,796,862 
- 25,333,988 
- 25,333,9889 
2,950,600 44,455,08518 
2,889,361 41,692,41918 
- 9,846,759 
- 9,846,75911 
1,283,500 18,310,91318 
1,246,410 18,199,25718 
- 16,027,467 
- 16,027,467 
1,258,000 16,694,92518 
1,230,446 16,623,26918 
- 14,469,585 
- 14,469,585 
1,369,000 19,196,93918 
1,294,068 18,834,46618 
4,534,000 291,754,700 
5,900,903 290,200,514 
601,000 2,542,402 
635,492 2,498,826 
- 18,672,000 
1,255 18,628,463 
- 60,670,957 
- 60,670,95712 
4,553,279 49,090,53318 
4,502,139 48,598,57118 
884,000 1,484,000 
1,049,007 1,328,661 
30-16

FORT WORTH, TEXAS DISTRICT 
TABLE 30-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 199217 
20. San Antonio Channel 
Improvement, TX 
(Federal Funds) 
(Contributed Funds) 
21. San Gabriel River, TX 
Granger 
Lake Georgetown 
22. Somerville Lake, TX 
23. Stillhouse Hollow Dam, 
TX 
33. Town Bluff Dam- 
B.A. Steinhagen Lake, 
TX 
24. Waco Lake, TX 
34. Whitney Lake, TX 
25. Wright Patman Dam 
and Lake, TX 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
19,891,000 14,698,000 5,713,000 15,000,000 124,176,048 
17,605,602 16,386,648 15,692,809 16,762,775 123,645,946 
- - 668,955 805,621 3,238,786 
- - 668,955 512,911 2,946,076 
- - - - 101,796,100 
- - - - 101,796,100 
1,116,200 1,116,673 998,000 1,774,000 13,186,95118 
1,130,161 1,045,321 1,091,454 1,751,570 13,132,25118 
1,181,000 1,127,269 1,096,000 1,141,000 12,114,82318 
1,180,248 1,096,518 1,094,698 1,134,548 12,043,59418 
- - - - 27,790,438 
- - - - 27,790,436 
1,590,400 1,647,480 2,063,000 2,127,500 29,604,33818 
1,637,136 1,497,359 2,170,664 2,006,947 26,907,07718 
- - - - 20,522,084'a 
- - - - 20,522,084 
1,405,000 1,269,499 1,192,000 1,352,000 17,918,547 '8 
1,452,494 1,083,861 1,334,128 1,278,094 17,736,54918 
- - - - 6,602,737 
- - - - 6,602,73714 
1,158,000 1,578,368 1,249,000 1,055,621 18,018,45718 
1,191,374 1,129,621 1,679,080 1,049,431 17,906,98118 
- - - - 49,521,12115 
- - - - 49,521,121 
1,694,700 2,512,419 1,611,990 1,815,000 28,233,51418 
1,681,788 1,840,041 2,249,353 1,813,450 28,044,84218 
- - - - 42,952,938 
- - - - 42,952,93816 
2,717,800 4,717,063 3,687,999 2,897,000 48,582,66418 
2,713,466 3,551,733 4,592,861 3,158,294 48,162,81318 
- - - - 35,731,626 
- - - - 35,731,626 
1,743,100 1,860,546 1,224,885 1,577,000 30,791,94518 
1,751,522 1,390,881 1,460,554 1,728,512 30,650,01118 
'Excludes $47,309 receipts from reconveyance of 
land deposited to miscellaneous receipts. 
2 Excludes $322,346 receipts from reconveyance of 
land deposited to miscellaneous receipts. 
3 Excludes $1,422,848 expended for new work from 
contributed funds, including $22,848 "Contributed Funds 
Other" for installation and operation of gages for leakage 
study. 
4 Includes $1,378,486 for Code 711, $52,808 for Code 
713, and $399,739 accelerated Public Works Act funds. 
Excludes $1,711,200 contributed funds. 
5 Includes $1,376,322 for Code 711, $52,808 for Code 
713, and $399,739 accelerated Public Works Act funds. 
Excludes $4,137 reimbursed in Fiscal Year 1973. 
6 Claim Northeast Texas Municipal Water District 
$16,546. Three payments of $12,410 less real estate charges 
of $1,325, making a total of $2,811 reimbursed in Fiscal 
Year 1972, Fiscal Year 1973, and Fiscal Year 1974. 
7 Excludes $146,795 receipts from reconveyance of 
land deposited to miscellaneous receipts, and $2,040,026 for 
new work expended from contributed funds. 
30-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 30-A COST AND FINANCIAL STATEMENT 
8 Excludes $105,079 expended from contributed 
funds. 
9 Excludes receipts from reconveyance of land of 
$426,606 which were deposited to miscellaneous receipts, 
and $3,676,661 for new work expended from contributed 
funds. 
10 Includes $130,000 under appropriation 96X5125. 
11 Excludes $300,000 expended from contributed 
funds. 
12 Excludes $3,000,000 expended from contributed 
funds. 
13 Includes receipts from disposals and revocation of 
funds related thereto. 
14 Excludes $2,000,000 contributed funds expended. 
15 Excludes $2,750,000 expended for contributed 
funds. 
16 Excludes $188,282 receipts from reconveyance of 
lands deposited to miscellaneous receipts. 
17 Includes funds provided by the Jobs Act (PL 98-8, 
dated March 24, 1983). 
18 Beginning Fiscal Year 1985 data shown on Table 
A includes Special Recreation Use Fees. Data for previous 
fiscal years have been changed to conform to the new 
procedure. 
30-18

FORT WORTH, TEXAS DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
2. Aug. 13, 1968 
3. Mar. 31, 1960 
4. Jul. 24, 1946 
Sep. 3, 1954 
5. Mar. 2, 1945 
Jun. 22, 1936 
Mar. 2, 1945 
Sep. 3, 1954 
8. Aug. 3, 1955 
9. Jul. 24, 1946 
10. Mar. 2, 1945 
11. Aug. 18, 1941 
12. Oct. 27, 1965 
AQUILLA LAKE, TX 
Construction of a dam on Aquilla Creek, about 6.8 miles 
southwest of Hillsboro, Texas and about 24 miles north 
of Waco, Texas. 
BARDWELL LAKE, TX 
Construction of a dam on Waxahachie Creek about 5 miles 
south of Ennis, Texas. 
BELTON LAKE, TX 
Construction of a dam on the Leon River about 3 miles 
north of Belton, Texas. 
Modification of the dam to provide for generation of 
hydroelectric power. 
BENBROOK LAKE, TX 
Construction of a dam on the Clear Fork of the Trinity 
River about 10 miles southwest of Fort Worth, Texas. 
BOGGY CREEK, TX 
Construction of a concrete trapezoidal channel on Boggy 
Creek beginning just above Webberville Road and 
extending downstream about 2.2 miles to just below 
Bolm Road. From there, a grass lined channel would 
extend further downstream and transition with the 
natural channel at Ed Bluestein Boulevard, a distance 
of about 1.7 miles. 
CANYON LAKE, TX 
Construction of a dam on the Guadalupe River about 12 
miles northwest of New Braunfels, Texas. 
COOPER LAKE AND CHANNELS, TX 
Construction of earth-fill dam and reservoir area; channel 
clearing, realignment, and enlargement; enlargement 
and extension of existing levees; construction of 
appurtenant drainage works along main stem of Sulphur 
River above mile 126; channel clearing, realignment, 
and enlargement and levee enlargement and 
modification of appurtenant drainage works on Cuthand 
Creek below mile 24, on Sulphur River below mile 70, 
except in proposed Cooper Reservoir, miles 29 to 42, 
and on Middle Sulphur River below mile 8; channel 
clearing and realignment of Brushy Creek below mile 
5; and levee enlargement on North Sulphur River 
between miles 1 and 5. 
FERRELLS BRIDGE DAM-LAKE O' THE PINES, TX 
Provides for construction of an earth-fill dam and reservoir 
area. 
GRAPEVINE LAKE, TX 
Construction of a dam on Denton Creek, a tributary of the 
Trinity River, about 20 miles northwest of Dallas, Texas. 
HORDS CREEK LAKE, TX 
Construction of a dam on Hords Creek, a tributary of Pecan 
Bayou, near the city of Coleman, Texas. 
JOE POOL LAKE, TX 
Construction of a dam on Mountain Creek, adjacent to the 
city limits of Grand Prairie, Texas, about 3 miles above 
the existing Mountain Creek Dam. 
S. Doc. 52, 90th Cong., 
1st Sess. 
H. Doc. 424, 82nd Cong., 
2nd Sess. 
H. Doc. 88, 81st Cong., 
1st Sess. 
H. Doc 535. 81st Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
Flood Control Act of 1936 
(PL 738) 
H. Doc. 247, 76th Cong., 
1st Sess. 
H. Doc. 488, 83rd Cong., 
2nd Sess. 
H. Doc. 602, 79th Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 370, 76th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
30-19 
TABLE 30-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 30-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
13. Mar. 2, 1945 
14. Oct. 23, 1962 
Mar. 7, 1974 
15. Mar. 2, 1945 
16. Sep. 3, 1954 
Dec. 31, 1970 
17. Aug. 18, 1941 
18. Sep. 3, 1954 
19. Oct. 27, 1965 
31. Mar. 2, 1945 
32. Mar. 2, 1945 
20. Sep. 3, 1954 
21. Sep. 3, 1954 
Jan. 3, 1975 
22. Sep. 3, 1954 
23. Sep. 3, 1954 
LAVON LAKE, TX 
Construction of a dam on the East Fork of the Trinity 
River about 22 miles northeast of Dallas, Texas. 
LAVON LAKE MODIFICATION AND EAST FORK 
CHANNEL IMPROVEMENT, TX 
Enlarge Lavon Dam and enlargement and realignment of 
the lower 25 miles of the East Fork of the Trinity River, 
including rehabilitation of existing levees. 
Improvement of Collin County Road 115. 
LEWISVILLE DAM, TX 
Construction of a dam on the Elm Fork of the Trinity 
River near the city of Lewisville, Texas. 
NAVARRO MILLS LAKE, TX 
Construction of a dam on Richland Creek, a tributary of 
the Trinity River, about 16 miles southwest of 
Corsicana, Texas. 
Alteration of FM Highway 3164 in Wolf Creek Park. 
O.C. FISHER DAM AND LAKE, TX 
Construction of a dam on the North Concho River just 
above San Angelo, Texas. 
PROCTOR LAKE, TX 
Construction of a dam on the Leon River about 8 miles 
northeast of Comanche, Texas. 
RAY ROBERTS LAKE, TX 
Construction of a dam on the Elm Fork of the Trinity 
River between Sanger and Aubrey, Texas, about 30 
miles upstream from the existing Lewisville Dam. 
SAM RAYBURN DAM AND RESERVOIR, TX 
Construction of a dam on the Angelina River about 10 
miles northwest of Jasper, Texas. 
SAM RAYBURN SPILLWAY (DAM SAFETY 
ASSURANCE), TX 
Modification of the spillway and embankment. 
SAN ANTONIO CHANNEL IMPROVEMENT, TX 
Channel improvement of the San Antonio River and 
tributaries in and near the city of San Antonio, Texas. 
SAN GABRIEL RIVER PROJECT, TX 
Construction of: (1) a dam (Granger Dam and Lake) on 
the San Gabriel River about 7 miles east of Granger, 
Texas, (2) a dam (North Fork Lake) on the north Fork 
of the San Gabriel River about 3.5 miles northwest of 
Georgetown, Texas and (3) a dam (South Fork Lake) 
on the South Fork of the San Gabriel River about 3 
miles southwest of Georgetown, Texas. 
SOMERVILLE LAKE, TX 
Construction of a dam on Yegua Creek about 2 miles 
south of Somerville, Texas. 
STILLHOUSE HOLLOW DAM, TX 
Construction of a dam on the Lampasas River about 5 
miles southwest of Belton, Texas. 
H. Doc. 533, 78th Cong., 
2nd Sess. 
H. Doc. 554, 87th Cong., 
2nd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
H. Doc. 498, 83rd Cong., 
2nd Sess. 
H. Doc. 315, 76th Cong., 
1st Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
S. Doc. 98, 76th Cong., 
1st Sess. 
S. Doc 98, 76th Cong., 
1st Sess. 
H. Doc. 344, 83rd Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess., and 
H. Doc. 591, 87th Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
H. Doc. 535, 81st Cong., 
2nd Sess. 
30-20

FORT WORTH, TEXAS DISTRICT 
TABLE 30-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
TOWN BLUFF DAM-B. A. STEINHAGEN LAKE, TX 
33. Mar. 2, 1945 Construction of a dam on the Neches River near Jasper, S. Doc. 98, 76th Cong., 
Texas. 1st Sess. 
ROBERT DOUGLAS WILLIS HYDROPOWER, TX 
30. Mar. 2, 1945 Construction of two units at 3,000 kilowatts each of S. Doc. 98, 76th Cong., 
hydroelectric power generating facilities connected with 1st Sess. 
Town Bluff Dam-B.A. Steinhagen Lake, Texas. 
TRINITY RIVER PROJECT, TX 
1. Oct. 27, 1965 Construction of Tennessee Colony Dam located at river H. Doc. 276, 89th Cong., 
mile 339.2 on the Trinity River about 16 miles west of 1st Sess., and 
Palestine, Texas; a multiple purpose channel from the H. Doc. 364, 90th Cong., 
Houston, Texas ship channel to Fort Worth, Texas; a 2nd Sess. 
distance of approximately 363 miles, an extension of 
the existing Dallas, Texas, Floodway downstream approximately 
9.0 miles; a realignment and enlargement 
of the West Fork of the Trinity River from the mouth 
of the West Fork to the existing Fort Worth, Texas, 
Floodway, a distance of approximately 31 miles; and 
water conveyance facilities involving construction of 
about 98 miles of pipeline from Tennessee Colony Lake 
to the existing Benbrook Lake. 
WACO LAKE, TX 
24. Sep. 3, 1954 Construction of a dam on the northwest edge of Waco, H. Doc. 535, 81st Cong., 
Texas, below the confluence of the North, South, and 2nd Sess. 
Middle Bosque Rivers. 
WHITNEY LAKE, TX 
34. Aug. 18, 1941 Construction of a dam on the Brazos River, about 19 H. Doc. 390, 76th Cong., 
miles southwest of Hillsboro, Texas. Raise the power 1st Sess. 
pool 13.0 feet. 
WRIGHT PATMAN DAM AND LAKE, TX 
25. Jul. 24, 1946 Construction of an earth-fill dam and reservoir. H. Doc. 602, 79th Cong., 
2nd Sess. 
30-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 30-C 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(See Section 28 of Text) 
Project 
Belton Lake Modification, TX3 
Big Fossil Creek, TX' 
Big Sandy Lake, TX4 
Big Spring, TX2 
Brownwood Channel Improvement, TX5 
Carl L. Estes Dam and Lake, TX4 
Dam "A" Lake, TX5 
Duck Creek Channel Improvement, TX5 
Elm Fork Floodway, TX 
Fort Worth Floodway (Clear Fork), TX' 
Fort Worth Floodway (West Fork), TX' 
Grand Prairie, TX (Landfill)' 
Grand Prairie, TX (Meyers Road)' 
Greenville, TX' 
Lake Brownwood Modification, TX' 
Lake Fork Lake, Sabine River, TX5 
Millican, TX2 
Navasota Lake, Navasota River, TX5 
Roanoak Lake, TX5 
Rockland Lake, TX5 
Rutledge Hollow Creek Channel Improvement, Poteet, TX' 
Zacate Creek Channel, TX' 
Calloway Branch, Hurst, TX' 
For Last Full 
Report See 
Annual Report 
For 
1988 
1969 
1986 
1979 
1979 
1987 
1983 
1987 
1971 
1971 
1987 
1989 
1983 
1983 
1988 
1979 
1988 
1969 
1983 
1986 
Construction 
Operation and 
Maintenance 
- 
'Completed 4Recommended for Deauthorization 
2Inactive 5Deauthorized 
"Deferred 
INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
TABLE 30-D (See Section 26 of Text) 
Location Dates of Inspection 
Big Fossil Creek ........................ .............................. Nov. 20, 1991 
Calloway Branch, Hurst ....................................................................... AAuugg. .15,1990 
Cat Claw Creek, Abilene................................................................. Jun. 4, 1992 
Dallas Floodway ................. .............. ................................. Dec. 10, 1991 
East Fork .............................................................................. Jun. 24, 1991 
Fort Worth Floodway ........................................................................ Oct. 2, 1991 
Grand Prairie Landfill ................................................................... Aug. 14, 1990 
Grand Prairie Meyers Road ..................................... ........................ Aug. 14, 1990 
Greenville ................................................................. Jun. 10, 1992 
Munday .................................................................. ............. Jun. 3, 1992 
Pleasanton ............................................................................... Jun. 19, 1991 
Poteet ................................................................................... Jun. 20, 1991 
San Antonio Floodway ............................ .............. ............................ Jun. 17, 1991 
Wheeler Creek ........................................................................... May 24, 1990 
Zacate Creek ........................................................ .... ........... Dec.4,1991 
30-22 
Cost to September 30, 1992

FORT WORTH, TEXAS DISTRICT 
WORK UNDER SPECIAL AUTHORIZATION 
TABLE 30-E (See Section 29 of Text) 
Project Flood Control Activities - Section 205 Cost 
Arlington, Grand Prairie, TX .............................................................. ... $ 110,612 
Beverly Hills, McLennan Cnty, TX.............. ......... ...... ..... ......................... O0 
Browder Creek, Springton, TX ......... ......... ...... .... .. ........ ... ....... ......... 857 
Calloway Branch, Richland Hills, TX ........................................................... 3,894 
Chacon Creek, Laredo, TX ................................................................... 0 
Delaware Creek, Dallas, TX .................................................................. 18,629 
Dry Branch Creek, Grand Prairie, TX .......................................................... 105,106 
Duck Creek, Garland, TX .................................................................... 108,914 
Farmers Branch, White Settlement, TX................. ................... ..................... 8,165 
Jackson Brand, Dallas, TX .................... ............................. .......... .... (-)4,314 
Johnson Creek, Grand Prairie, TX ................................................. ........ .... 211,740 
Lake Creek, Round Rock, TX ................................................. ............... 6,813 
Little Walnut Creek, Austin, TX .............................................................. O0 
Lorean Branch, Hurst, TX .................................................................. 62,023 
Mary's Creek, Fort Worth & Benbrook, TX ..................................................... 33,754 
Plants Creek, Seymour, TX .............................................................. ....... 241 
Post Oak Creek, Corsicana, TX ................................... .............. ........ 10,883 
Red Arroyo, San Angelo, TX .................. ............................................ ... 1,289 
Rush Creek, Arlington, TX ................................................................... 91,913 
Seymour Creek, Seymour, TX ........................................................... ............ 27 
Singing Hills Creek, Watauga, TX ......................... ........................... ....... .. 65,592 
Stream 5B13, Dallas, TX .................. ................................................... 10,793 
Sulphur Branch, Euless, TX .......................................... ......... .......... 111,673 
Ten Mile Creek, De Soto, TX ...................................... ........................... 12,945 
Ten Mile Creek, Lancaster, TX ............................................... ........ ....... .. 9,322 
Town Branch Creek, Lockhart, TX ..................................................... ....... O0 
Upper Zacate Creek, Laredo, TX ............................................................ 138,522 
Valley View Branch, Hurst, TX .............................................................. 769 
Waco Creek, Waco, TX .............................. ... ............ ........ .. .......... .. 66 
Walnut Creek, Mansfield, TX ................. ................................................................... .. (-)11,397 
Walnut Creek, Seguin, TX .............. ........ . ... ........... ....... .............. 404 
Walnut Creek, Springtown, TX ................................................................ 2,582 
Project Emergency Bank Protection - Section 14 Cost 
Little River, Cameron, TX ............................ ........ ............ . ........ .......... 1,416 
Beltline Road, Cottonwood Creek, TX ......................................................... $ 30,035 
Bridge, Mary Creek, TX .................................................... ................. 20,375 
Broadway Street, Pecan Creek, Gainesville, TX .......................... .......................... 183 
Cat Claw Creek, Abilene, TX ....................... ............. ............... ............ ... O 
Dice Grove, Lampasas River, Bell Co., TX ....................................................... 2,168 
Moss Street, Pecan Creek, Gainesville, TX ..................... ...................... . .. ....... 183 
Park Row, Arlington, TX............................ ......................... .. .......... .... 21,779 
Roaring Springs Rd., Bridge, TX .................................... ................... ....... 28,858 
W ashington Street Bridge, Laredo, TX ................ ................... ..................... 21,786 
Project Snagging and Clearing of Flood Control - Section 208 Cost 
Maxwell Creek, Parker County, TX ........................................... $ (-)259 
Sulphur RW Red Riv., Franklin City, TX ............... ......................................... 19,922 
30-23

GALVESTON, TEXAS, DISTRICT* 
Galveston District comprises drainage basins of all 
short streams arising in coastal plain of Texas and flowing 
into the Gulf of Mexico, including the entire basin of 
Buffalo Bayou, San Jacinto, San Bernard, Lavaca, 
Navidad, Mission, and Aransas Rivers. It embraces Agua 
Dulce, San Fernando, and Olmos Creek Basins draining 
into Baffin Bay, and coastal area south thereof to the Rio 
Grande and east of western Boundary of Starr County, 
Texas. It includes lower basins of major streams flowing 
into the Gulf of Mexico: Sabine River, Texas and Louisiana, 
downstream from U.S. Highway 190 crossing at Bon Wier, 
Texas; Neches River downstream from Town Bluff gaging 
station; Trinity River downstream from Texas State 
Highway 19 crossing at Riverside, Texas; Brazos River 
downstream from confluence with Navasota River; 
Colorado River downstream from northern boundary of 
Fayette County; Guadalupe River downstream from 
confluence with San Marcos River; San Antonio River 
downstream from confluence with Escondido Creek; 
Nueces River downstream from confluence with Frio and 
Atascosa River. 
IMPROVEMENTS 
Navigation 
1. Aquatic Plant Control (Southwestern 
Division) .............................. 
2. Brazos Island Harbor, TX ................ 
3. Channel to Port Bolivar, TX .............. 
4. Corpus Christi Ship Channel, TX .......... 
5. Freeport Harbor, TX ................. 
6. Galveston Harbor and Channel, TX ........ 
7. Gulf Intracoastal Waterway between 
Apalachee Bay, FL, and the Mexican 
Border ............................... 
8. Houston Ship Channel, TX ............... 
9. Matagorda Ship Channel, TX ............ 
10. Sabine-Neches Waterway, TX .............. 
11. Texas City Channel, TX .................. 
12. Trinity River and Tributaries, TX. ........ . 
12A. Anahuac Channel, TX ................. 
12B. Channel to Liberty, TX ................. 
12C. Wallisville Lake, TX................... 
13. Reconnaissance and Condition Surveys .... 
14. Navigation Work Under Special 
Authorization .................... 
Beach Erosion Control 
15. Corpus Christi Beach, TX ............... 
Flood Control 
16. Buffalo Bayou and Tributaries, TX ........ 
16A. Addicks and Barker Reservoirs, TX ....... 
16B. Brays Bayou, TX ...................... 
16C. GreensBayou, TX .................... 
16D. Halls Bayou, TX ....................... 
16E. Hunting Bayou, TX .................... 
16F. Little White Oak Bayou, TX ........... . 
16G. Carpenters Bayou, TX .................. 
17. Clear Creek, TX ...................... 
18. Cypress Creek, TX .................. 
19. Falfurrias, TX ................ ........ 
20. Kirbyville, TX ......................... 
21. Lower Rio Grande Basin, TX. ........... . 
Page Flood Control (cont.) Page 
21A. Arroyo Colorado, TX.................... 31-14 
31-2 21B. South Main Channel, TX................ 31-14 
31-2 21C. Raymondville Drain, TX ................ 31-14 
31-2 22. Port Arthur and Vicinity, TX 
31-3 Hurricane-Flood Protection ............. 31-14 
31-3 23. SimsBayou,TX ....................... 31-14 
31-4 24. State Highway 111 Bridge, 
Lake Texana, TX .................. .... 31-15 
25. Taylors Bayou, TX ..................... 31-15 
31-5 26. Texas City and Vicinity, TX 
31-6 Hurricane-Flood Protection .............. 31-15 
31-7 27. U.S. 190 Bridge, Sabine River, 
31-7 Merryville, LA ........................ 31-16 
31-8 28. Vince and Little Vince Bayous, TX ........ 31-16 
31-8 29. Inspection of Completed Flood Control 
31-8 W orks ................ .............. 31-16 
31-9 30. Flood Control Work Under Special 
31-9 Authorization ......................... 31-16 
31-10 31. Emergency Stream Bank and Shoreline 
Erosion Work and Snagging and Clearing 
31-10 Under Special Authorization ............ 31-16 
32. Project Modifications for Improvement 
of Environment......................... 31-17 
31-10 
31-10 
31-11 
31-11 
31-11 
31-12 
31-12 
31-12 
31-12 
31-12 
31-13 
31-13 
31-13 
31-13 
General Investigations 
33. Surveys........................... 
34. Planning and Engineering............... 
35. Collection and Study of Basic Data ........ 
31-17 
31-17 
31-18 
Tables 
31-A Cost and Financial Statement... 31-19 thru 31-22 
31-B Authorizing Legislation ........ 31-23 thru 31-37 
31-C Other Authorized Navigation Projects ..... .31-38 
31-D Other Authorized Flood Control Projects ... 31-38 
31-E Total Cost of Existing Projects ........... 31-39 
31-F Channel Dimensions .......... 31-40 thru 31-42 
31-G Channel Dimensions, GIWW 
Tributary Channels ........... 31-43 thru 31-44 
31-H Dredging Operations .......... 31-45 thru 31-46 
31-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. AQUATIC PLANT CONTROL 
(SOUTHWESTERN DIVISION) 1965 
ACT 
Location. Navigable waters, tributary streams, 
connecting channels, and other allied waters in Texas. 
Previous project. For details see page 699 of Annual 
Report for 1963. 
Existing project. A comprehensive project to provide 
for control and progressive eradication of water-hyacinth, 
alligatorweed, Eurasian watermilfoil, hydrilla, and other 
obnoxious aquatic plant growths, from navigable waters, 
tributary streams, connecting channels, and other allied 
waters in Texas in the combined interest of navigation, 
flood control, drainage, agriculture, fish and wildlife 
conservation, public health, and related purposes, 
including continued research for development of the most 
effective and economic control measures. Control of 
hydrilla, water-hyacinth and alligatorweed continues in 
the Nueces River Basin, North Coastal Area, Guadalupe 
River Basin, Sabine River Basin, Trinity River Basin, 
Cypress Creek Basin, Neches River Basin, South Coastal 
Area, San Jacinto River Basin, Rio Grande Basin, 
Colorado River Basin and Brazos River Basin. 
Local cooperation. Sec. 302, 1965 River and Harbor 
Act, amended by Water Resources Development Act of 
1986, applies. 
Operations during fiscal year. Control work by 
the State of Texas continued. The contract was renewed 
for an additional year and has the option to renew for 
another two years. Monitoring of the biological control 
nursery areas was maintained and increased with the 
successful overwintering of the Hydrellia fly at Sheldon 
reservoir. The fly populations were supplemented with 
further introductions throughout the summer. 
2. BRAZOS ISLAND HARBOR, TX 
Location. At extreme south end of coast of Texas, 
about 7 miles north of mouth of Rio Grande and about 5 
miles east of Brownsville, Texas. (See National Ocean 
Survey Chart 11301.) 
Previous project. For details see page 1017 of 
Annual Report for 1932. 
Existing project. Provides for channel dimensions 
in various sections of the waterway as shown in Table 
15F.
Project also provides for dual jetties at the gulf 
entrance, a north jetty 6,330 feet long, a south jetty 5,092 
feet long, and 1,000-foot extension to existing north jetty 
and for maintenance of 3rd fishing harbor constructed by 
local interests. Under ordinary conditions, mean tidal 
range is about 1.5 feet, and extreme range is about 2 
feet. All depths refer to mean low tide. To some extent, 
height of tides is dependent on the wind, and during 
strong "northers" in winter season, water surface in 
southern end of Laguna Madre may be raised 4 feet or 
more above mean low tide in the gulf. Estimated cost for 
new work is: Federal (Corps) $30,024,647, exclusive of 
amount expended on previous projects, and non-Federal 
$17,340,258, including $7,964,258 contributed funds, 
$1,099,000 lands, $2,349,000 relocations, and $5,928,000 
other costs, exclusive of amount expended on previous 
projects. (October 1, 1992 base price). 
Widening Brownsville Channel from Goose Island to 
Brownsville turning basin and deepening southeast corner 
of Brownsville turning basin to 36 feet was completed in 
April 1980. The 1,000-foot extension to existing north 
jetty was deauthorized under Section 1001 of the Water 
Resources Development Act of 1986. Work remaining 
consists of enlarging 14.8 miles of the existing Brownsville 
Channel from 36 feet by 200 feet to 42 feet by 250 feet 
and by enlarging 2.5 miles of the entrance channel from 
38 feet by 300 feet to 44 feet by 300 feet. The turning 
basin would be enlarged to 1,200 feet at a depth of 36 
feet. (See Table 31-E for total cost of existing project to 
September 30, 1992.) 
Local cooperation. Complied with for the completed 
work. For the 42 foot project authorized by the Water 
Resources Development Act of 1986, local interests are 
required to provide lands, easements, rights-of-way, and 
material disposal areas; levees and spillways for disposal 
areas; modify or relocate utilities, roads, and other 
facilities, except railroad bridges; pay one-half of the 
separable and joint costs allocated to recreation; and pay 
25 percent of the costs allocated to deep-draft navigation, 
during construction, and pay an additional 10 percent of 
the costs allocated to navigation within a period of 30 
years following completion if not offset by credit allowed 
for lands, easements, rights-of-way, relocations and 
dredged material disposal areas. 
Terminal facilities. Numerous terminal facilities for 
bulk and liquid cargo are available. (See Port Series No. 
26, revised 1980.) Facilities are adequate for existing 
commerce. 
Operations during fiscal year. New Work: 
Construction contract for dredging the entrance channel, 
Stations 13+00 to 1+000 was awarded February 4, 1992 
and completed at a cost of $1,351,401. Contract for 
dredging Inshore Reach No. 1, Stations 1+000 to 23+000 
was awarded July 16, 1992 and continued through Fiscal 
Year 1992 at a cost of $1,479,066. Also see Section 34, 
Planning and Engineering for preconstruction, engineering 
and design work for Fiscal Year 1992. 
Maintenance: A contract for jetty repairs was awarded 
August 9, 1991 and completed June 24, 1992 at a cost of 
$2,243,766. (See Table 31-H for dredging operations.) 
3. CHANNEL TO PORT BOLIVAR, TX 
Location. Port Bolivar is at end of Bolivar Peninsula 
and 4 miles north of city of Galveston. Channel connects 
the port with channel in Galveston Harbor. (See National 
Ocean Survey Chart 11324.) 
Previous project. For details see page 1856 of 
Appendix to Annual Report for 1915. 
Existing project. Existing project dimensions for 
channel are shown in Table 31-F. (Also see Table 31-B 
for authorizing legislation.) 
Under ordinary conditions mean tidal range is about 
1.3 feet and extreme range about 2 feet. Height of tides is 
dependent largely on the wind, and during strong 
31-2

GALVESTON, TEXAS, DISTRICT 
"northers" in the winter season water surface may be 
depressed as much as 2 feet below mean low tide. 
Enlargement of turning basin from 1,000 to 1,600 feet is 
inactive. A channel 14 feet deep, 200 feet wide, and 
approximately 950 feet long is maintained across the east 
end of the turning basin to accommodate the Galveston- 
Port Bolivar ferry. Project is complete except for inactive 
portion. Project dimensions have not been maintained in 
the completed part since lesser dimensions are adequate 
for existing commerce. (See Table 31-E for total cost of 
existing project to September 30, 1992.) 
Local cooperation. None required. 
Terminal facilities. Terminals are privately owned 
and consist of 2 slips and 2 piers. The piers, 400 feet 
wide by 1,200 feet long and 210 feet wide by 1,200 feet 
long, are badly deteriorated and not in use. The slips are 
used as anchorage by shallow-draft vessels. A highway 
ferry landing owned by the State of Texas is located at 
south end of turning basin. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. No maintenance 
required for fiscal year. 
4. CORPUS CHRISTI SHIP 
CHANNEL, TX 
Location. This project, formerly known as the Port 
Aransas-Corpus Christi Waterway, Texas, was changed 
to Corpus Christi Ship Channel, Texas, by 1968 River 
and Harbor Act. This is a consolidation of old 
improvements of Port Aransas, Texas, and channel from 
Aransas Pass to Corpus Christi, Texas. Aransas Pass is 
on southern portion of Texas Coast, 180 miles southwest 
of Galveston and 132 miles north of mouth of Rio Grande. 
Aransas Pass connects Corpus Christi Bay with the gulf. 
Waterway extends from deep water in the gulf through 
Aransas Pass jettied entrance, thence westerly 20.75 miles 
to and including a turning basin at Corpus Christi, thence 
westerly 1.75 miles through Industrial Canal to and 
including turning basin at Avery Point, thence westerly 
4.25 miles to and including a turning basin near Tule 
Lake, thence northwesterly 1.8 miles to and including a 
turning basin at Viola, Texas. (See National Ocean Survey 
Charts 11308, 11309, 11311, and 11314.) 
Previous project. For details see page 1861 of 
Annual Report for 1915. 
Existing project. (See Table 31-F for existing project 
dimensions provided for in various channels and basins 
comprising this waterway.) 
Project also provides for two rubblestone jetties at 
Aransas Pass entrance, extending into the gulf from St. 
Joseph and Mustang Islands, project lengths of which 
are 11,190 and 8,610 feet, respectively. Project further 
provides for a stone dike on St. Joseph Island about 20,991 
feet long, connecting with north jetty and extending up 
this island to prevent a channel being cut around jetty. 
Project also provides for a breakwater at the entrance to 
the harbor area at Port Aransas, and for the realignment 
of the existing 12-foot by 100-foot project channel to Port 
Aransas. The breakwater consists of two overlapping 
sections. The one on the east side of the realigned entrance 
channel has a length of 830 feet and the second, located 
on the west side of the entrance channel, has a length of 
1,290 feet. The channel to Port Aransas was relocated in 
the 300-foot clear distance between the overlapping 
sections. The portion of the channel remaining inside the 
breakwaters was widened to 150 feet. Under ordinary 
conditions, mean tidal range at Aransas Pass is about 1.1 
feet and extreme range about 2 feet, and at Corpus Christi 
mean range about 1 foot and extreme about 1.5 feet. 
Heights of tides are dependent largely on strength and 
directions of winds, and during strong "northers" in the 
winter season water surface may be depressed as much 
as 3 feet below mean low tide. Estimated cost for new 
work is: Federal (Corps) $74,938,515, including $456,515 
for Port Aransas Breakwaters and exclusive of amount 
expended on previous projects: and non-Federal 
$18,977,431 (includes $768 for Port Aransas Breakwaters) 
including $7,644,435 contributed funds and value of useful 
work performed, $3,320,228 lands, $6,027,000 relocations 
and $1,985,000 other cost. (October 1, 1992 base price.) 
The Port Aransas-Corpus Christi 40-foot project was 
completed in 1966. The Jewel Fulton Canal was completed 
in 1963. The Port Aransas Breakwaters were completed 
in July 1973. Deepening deep-draft channels to 45 feet 
from Tule Lake Turning Basin through Viola Turning 
Basin was completed in 1989, and constructing a mooring 
area at Port Ingleside with dolphins has been deferred. 
Entrance and jetty channels have been dredged to project 
depth and width, and dredging of channel from Harbor 
Island to and through the Chemical Turning Basin at 45- 
foot depth has been completed. Initial mooring dolphins 
were completed in May 1979. Disposal area levees, Area 
1 and Rincon were completed in August 1984. First stage 
disposal area levees, South Shore, were completed in 
September 1984. (See Table 31-E for total cost of existing 
project to September 30, 1992.) 
Local cooperation. Fully complied with. 
Terminal facilities. Terminal facilities on Harbor 
Island at head of Aransas Pass, Ingleside, Corpus Christi, 
La Quinta, Avery Point, and Viola, are considered 
adequate for existing commerce. (See Port Series, No. 25, 
revised 1979, Corps of Engineers.) 
Operations during fiscal year. Maintenance: 
Routine maintenance. (See Table 31-H for dredging 
operations.) 
5. FREEPORT HARBOR, TX 
Location. Formed by improvement of Brazos River, 
Texas, from mouth to about 6 miles upstream to Freeport, 
Texas. (See National Ocean Survey Charts 11321 and 
11322.) 
Previous projects. For details see page 1860 of 
Annual Report for 1915, and page 872 of Annual Report 
for 1938. 
Existing project. Existing project dimensions for 
various channels and basins are shown in Table 31-F on 
channel dimensions at end of chapter. 
Existing project also provides for: Dual jetties and a 
diversion canal for the Brazos River, including a dam, a 
lock in the dam and necessary auxiliary equipment. Also 
provides for rehabilitation of southwest jetty and the 
relocation of the northeast jetty (about 640 feet to the 
31-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
northeast); realignment of the channel between the Jetty 
Channel and Brazosport Turning Basin; realignment of 
the channel between Brazosport Turning Basin and Upper 
Turning Basin; relocation of Upper Turning Basin; and 
public use facilities adjacent to the Freeport Jetties. The 
30-foot channel from Upper Turning Basin to Stauffer 
Chemical Plant, including the turning basin, was 
deauthorized by Sec. 12 of PL 93-251. Construction of 
lock in diversion dam at local expense is considered 
inactive. 
The 38-36 foot project was completed in 1962. Work 
remaining consists of realigning, deepening and widening 
the Outer Bar and Jetty Channels; relocating the 
northeast jetty; rehabilitating the southwest jetty; 
realigning and deepening the harbor channel between 
the jetty channel and the Upper Turning Basin; relocating 
and enlarging the Upper Turning Basin; constructing a 
turning point near the northwesterly end of the jetty 
channel; enlarging Brazosport Turning Basin; deepening 
Brazos Harbor Channel; and enlarging and deepening 
Brazos Harbor Turning Basin, as authorized by the R&H 
Act of 1970. The initial contract for the 45 foot project, 
construction of 3,700 feet of the North Jetty, was awarded 
in May 1987. (See Table 31-E for total cost of existing 
project to September 30, 1992.) 
Under ordinary conditions mean tidal range is about 
1.5 feet and extreme range is about 2.5 feet. Except under 
extreme conditions, rises on river and in diversion channel 
do not cause greater variations in water surface than 
those caused by tidal action. Estimated cost of new work 
is: $63,035,000 Federal (Corps); and $31,666,000 non- 
Federal, including $21,158,303 contributed funds, 
$360,249 contributed work, $6,587,448 lands, $2,990,000 
levees and spillways, and $570,000 relocations. (October 
1, 1992 base price.) 
Local cooperation. Fully complied with except for 
Section 101 of River and Harbor Act of 1970, modified by 
the Water Resources Development Act of 1986. Local 
Cooperation Agreement, executed 26 June 1986, along 
with Amendments 1, 2 and 3, executed 19 March 1987, 
19 June 1991 and 19 June 1991, respectively, require 
that local interest provide lands, easements, rights-ofway, 
including land for recreation, and dredged material 
disposal areas, presently estimated at $9,260,000, modify 
or relocate utilities, roads, and other facilities, except 
railroad bridges, where necessary for construction of the 
project, presently estimated at $570,000, contribute in 
cash one-half of the separable and joint costs allocated to 
recreation, presently estimated at $420,000; and, during 
construction, pay 25 percent of the construction costs 
allocated to deep-draft navigation, presently estimated at 
$19,100,000. 
Terminal facilities. Small privately owned wharves, 
two oil docks, one acid dock, two shell unloading docks 
and one caustic dock. Brazos River Navigation District 
has one large dock with four transit sheds over rail 
facilities permitting all-weather work. Facilities considered 
adequate for existing commerce. (See Port Series No. 26, 
revised 1980, for additional facilities.) 
Operations during fiscal year. New Work: 
Dredging the Entrance Channel, Station -230+00 to 
50+35.91 was continued at a cost of $3,622,045. The 
contract for dredging Main Channel and Basins was 
completed at a cost of $6,044,795. The contract to 
rehabilitate the South Jetty and add 500 feet to the North 
Jetty continued through the fiscal year at a cost of 
$7,830,000. Contract for clearing U.S. Coast Guard Station 
was awarded September 20, 1991 and completed in Fiscal 
Year 1992 for a cost of $191,756. Construction contract 
for grading and stone protection of the Public Use Facility 
at Surfside, Texas was awarded April 10, 1992 and 
completed at a cost of $436,704. 
Maintenance: Routine maintenance. (See Table 31-H 
for dredging operations.) 
6. GALVESTON HARBOR AND 
CHANNEL, TX 
Location. A consolidation of authorized 
improvements at Galveston, Texas, which includes projects 
formerly identified as Galveston Harbor, Texas; Galveston 
Channel, Texas; and Galveston seawall extension. 
Entrance to Galveston Harbor is on Gulf of Mexico on the 
northern portion of the Texas Coast. Galveston Channel 
extends from a point in Galveston Harbor between Bolivar 
Peninsula and Fort Point to and along wharf front 
Galveston, Texas, and is about 5 miles long and 1,200 
feet wide. (See National Ocean Survey Chart 11324/5.) 
Previous projects. For details see page 1854 of 
Annual Report for 1915. 
Existing project. Provides for channel dimensions 
in sections of the waterway shown in Table 31-F. 
Also provided are: two rubble-mound jetties, the south 
one extending from Galveston Island and the north one 
extending from Bolivar Peninsula, for distances of 35,900 
feet and 25,907 feet, respectively, into the Gulf of Mexico; 
a concrete seawall from the angle at Sixth Street and 
Broadway, in the city of Galveston, to the south jetty, 
and a 16,300-foot extension of the concrete seawall in a 
southwesterly direction from 61st Street; for 11 groins 
along the gulf shore between 12th Street and 61st Street; 
and for maintenance of seawall from the angle at 6th 
Street and Broadway to the south jetty. Under ordinary 
conditions, mean tidal range in Galveston Harbor is 1.6 
feet on outer bar and 1.4 feet on inner bar with extreme 
ranges of 2.3 and 2.1 feet, respectively. Mean range in 
Galveston channel is about 1.3 feet and extreme range 
about 2 feet under ordinary conditions. Height of tides in 
both Galveston harbor and channel is dependent largely 
on the wind, and during strong "northers" water surface 
may be depressed 2 feet below mean low tide. 
Existing project is complete. Dredging of Galveston 
channel to 36 foot depth was completed in November 
1966.. Dredging of the realigned entrance and Outer Bar 
Channel was completed in October 1967. Rehabilitation 
of the Beach Front Groins was completed June 1970. 
Dredging of Galveston channel to 40 feet was completed 
in March 1976. See Section 12. TEXAS CITY CHANNEL, 
TX regarding work authorized by Water Resources 
Development Act of 1986. (See Table 31-E for total cost of 
existing project to September 30, 1992.) 
Local cooperation. Complied with. 
31-4

GALVESTON, TEXAS, DISTRICT 
Terminal facilities. None on Galveston Harbor, 
which is entrance channel leading to terminal facilities 
on Galveston, Texas City, and Houston Ship Channels. 
Galveston Channel terminal facilities are mostly on south 
side of channel. Principal wharves, owned by the city of 
Galveston, extend from 10th to 41st Street (see Port Series 
No. 23, revised 1979). A containership terminal equipped 
with a crane capable of stacking containers three units 
high on the deck of any normal containership has been 
completed and placed into operation by the city of 
Galveston at Piers 10 and 11, on the south side of 
Galveston Channel. The city of Galveston has also placed 
into operation a barge terminal equipped with two 35-ton 
and one 5-ton cranes for loading and unloading barges on 
Lash and Seabee ships at Pier 35 and a docking and 
holding area for Lash and Seabee barges on Pelican 
Island, directly across the channel from Piers 35 and 36. 
Present facilities are considered adequate for existing 
commerce. 
Operations during fiscal year. Routine 
maintenance. (See Table 31-H for dredging operations.) 
7. GULF INTRACOASTAL 
WATERWAY BETWEEN 
APALACHEE BAY, FL, AND 
MEXICAN BORDER 
Location. Extends from a point on Sabine River 
about 3 miles below Orange, Texas, to Brownsville, Texas, 
about 421 miles; a navigation channel, about 7 miles 
long, in Colorado River, extending from Matagorda, Texas, 
to Gulf of Mexico; a tributary channel in San Bernard 
River, extending from Intracoastal Waterway crossing to 
State highway bridge some 30 miles above crossing; a 
tributary channel in Colorado River extending from 
Intracoastal Waterway upstream 15.5 miles; a tributary 
channel extending about 14 miles from Intracoastal 
Waterway to Palacios, Texas; a tributary channel 
extending about 2 miles from Intracoastal Waterway to 
Rockport, Texas; a tributary channel extending about 6 
miles from Intracoastal Waterway near Port Aransas, 
Texas, to town of Aransas Pass, Texas; a tributary channel 
about one-fourth mile long extending from Intracoastal 
Waterway near Port O'Connor, Texas, into Barroom Bay; 
a tributary channel extending about 38.8 miles from 
Intracoastal Waterway via Seadrift to a point in 
Guadalupe River 5.5 miles below Victoria, Texas; a harbor 
of refuge for small craft at Seadrift; a channel extending 
from gulf to Port Mansfield, Texas, about 11 miles; and a 
tributary channel in Arroyo, Colorado extending from 
Intracoastal Waterway to a point near Harlingen, Texas, 
about 31 miles; side channels in vicinity of Port Isabel, 
Texas, and a small boat basin at Port Isabel, Texas, and 
a tributary channel extending from Intracoastal Waterway 
main channel at a point in West Galveston Bay into 
Offatts Bayou about 2.2 miles with a west turnout (wye 
connection) 12 feet deep and 125 feet wide between Offatts 
Bayou Channel and the Gulf Intracoastal Waterway. (See 
National Ocean Survey Charts 11302, 11303, 11305, 
11306, 11308, 11309, 11314, 11315, 11317, 11319, 11322, 
11326, and 11331.) 
Previous project. For details see page 1859 of 
Annual Report for 1915. (West Galveston Bay and Brazos 
River Canal, Texas.) 
Existing project. Existing project dimensions 
provided for in main channel of waterway: A channel 12 
feet deep (below mean low tide) and 125 feet wide from 
the Sabine River to Brownsville, Texas. Relocation of 
channel 12 feet deep by 125 feet wide in Matagorda Bay, 
miles 454.3 to 471.3, relocation of channel 12 feet deep 
by 125 feet wide in Corpus Christi Bay, miles 539.4 to 
549.7 (mileage is west of Harvey Lock, Louisiana); and 
alternate channel, 12 feet deep (below mean low tide) 
and 125 feet wide via Galveston Channel and Galveston 
Bay to the Galveston causeway; maintenance of existing 
channel 12 feet deep by 125 feet wide through Lydia Ann 
Channel, between Aransas Bay and Aransas Pass; 
provisions of such passing places, widening of bends, locks 
and guard locks, railway bridges over artificial cuts as 
are necessary, and the tributary channels shown in 
tabulation. The authorized channel 16 feet deep and 125 
feet wide from Sabine River to Houston Ship Channel is 
inactive. (See Table 31-G on existing project dimensions 
provided for in tributary channels.) 
Removal of the railroad bridge across the canal at 
Mud Bayou was completed and operation and care of the 
facility was discontinued on April 14, 1969. Deepening 
the existing 6 foot by 60 foot side channels at Port Isabel 
to 12 feet was completed February 22, 1972, Offatts Bayou 
channel was completed January 1974. Relocation of main 
channel across Corpus Christi Bay was completed in 
September 1976. The 14 foot by 175 foot Channel to 
Aransas Pass was completed in April 1979. Dredging 
Chocolate Bayou Channel was completed in January 1981. 
Construction of a saltwater barrier in Chocolate Bayou 
was completed in February 1981. The 12 foot by 125 foot 
channel relocation route in Matagorda Bay has been 
deauthorized. The Harbor of Refuge at Seadrift, Texas, 
has been placed in the inactive category. Construction of 
jetties at mouth of Colorado River was completed in 1986. 
Construction of a navigation channel from the Gulf to 
the GIWW and an impoundment basin were fiscally 
completed in Fiscal Year 1991. Construction of Tiger 
Island Dam and recreation facilities were also completed 
in Fiscal Year 1991. Active authorized work remaining 
consists of the following: (1) Mouth of Colorado River, 
construction of a diversion dam and channel; construction 
of an oyster cultch; and recreation facilities; (2) Work 
authorized by the Water Resources Development Act of 
1988 for enlarging the existing Channel to Victoria from 
a depth of 9 feet and width of 100 feet to a depth of 12 
feet and width of 125 feet. (See Table 31-E for total cost 
of existing project to September 30, 1992.) 
Mean tidal variation is 0.5 foot at Orange, 1 foot at 
Port Arthur, 1.3 feet in Galveston Bay, 1.5 feet at Freeport, 
1 foot in Matagorda Bay, 1 foot in San Antonio Bay, 1 
foot at Corpus Christi, 1.5 feet at Port Isabel, and 1.5 feet 
at Brownsville. Extreme ranges of tide under ordinary 
conditions are 1 foot at Orange, 1.5 feet at Port Arthur, 2 
feet in Galveston Bay, 2 feet at Freeport, 1.5 feet in 
Matagorda and San Antonio Bays, 1.5 feet at Corpus 
Christi, 2 feet at Port Isabel, and 1.5 feet at Brownsville. 
31-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Height of tides is dependent largely on wind. Strong north 
winds have depressed water surface as much as 2 feet 
below mean low tide. Estimated cost for new work is: 
$102,828,000 (excluding $212,000 Department of 
Transportation cost for Channel to Victoria) Federal 
(Corps), including $8,414 for Port Isabel Side Channel, 
$46,559 for Port Isabel Small Boat Basin, $356,466 for 
Offatts Bayou, and $658,573 for Channel to Aransas Pass 
and excluding expenditures on previous projects; non- 
Federal $24,991,174 ($395,000 voluntarily expended on 
Gulf Intracoastal Waterway, $46,559 contributed funds 
for Port Isabel, $49,665 contributed funds for Offatts 
Bayou, $347,950 contributed funds for channel to Aransas 
Pass, $3,529,000 contributed funds for Mouth of Colorado 
River, $2,456,000 contributed funds for Channel to 
Victoria, $6,022,000 lands for Gulf Intracoastal Waterway, 
$11,000 lands for Port Isabel, $4,242,000 relocations for 
Gulf Intracoastal Waterway, and $5,457,000 other costs 
for Gulf Intracoastal Waterway). (October 1, 1992 base 
prices.) 
Local cooperation. Fully complied with except for 
provisions of Section 101, 1968 River and Harbor Act and 
Water Resources Development Act of 1988. Non-Federal 
contributions are $395,000 for Gulf Intracoastal 
Waterway, $46,559 for Port Isabel, Texas, $49,665 for 
Offatts Bayou, Texas, $347,950 for Channel to Aransas 
Pass, Texas, and $3,529,000 for Mouth of Colorado River, 
Texas, and $2,093,000 for Channel to Victoria. 
Terminal facilities. There are terminal facilities at 
Aransas Pass, Port Arthur, Galveston, Port Isabel, and 
Brownsville. See Port Series No. 22 (revised 1981), Port 
Series No. 23 (revised 1979), Port Series No. 25 (revised 
1979) and Port Series No. 26 (revised 1980), Corps of 
Engineers. Local interests constructed terminal facilities 
at Port Mansfield and Port Harlingen. There are 
numerous privately owned piers and wharves along the 
waterway. A 330-foot navigation district owned general 
cargo dock, a 770-foot private dock and a 760-foot private 
timber trestle have recently been completed at the upper 
end of the Channel to Victoria. Facilities are adequate 
for existing commerce. 
Operations during fiscal year. Mouth of Colorado 
River New Work: Contract for construction of Jetty Park 
was financially completed at a cost of $3,500. Contract 
for construction of diversion dam and connecting channel 
was awarded December 9, 1991 and continued through 
fiscal year 1992 at a cost of $1,594,246. Channel to Victoria 
New Work: See Section 34, Planning and Engineering. 
Sargent Beach New Work: See Section 34, Planning and 
Engineering. 
Maintenance: A contract to remove reference line in 
Cameron, Willacy and Kenedy Counties was awarded 
September 6, 1991 and was physically completed March 
13, 1992 for a fiscal year cost of $615,952. Contract for 
shoreline protection along the Aransas National Wildlife 
Refuge was awarded August 19, 1992 and completed in 
fiscal year 1992 at a cost of $299,780. The Brazos River 
Floodgates were operated and maintained at a cost of 
$1,255,698 including engineering and design, supervision 
and administration, and real estate activities. Contract 
for rehabilitation of Sector Gates for Brazos River 
Floodgates and Colorado River Locks was financially 
completed with a reduction of cost in the amount of 
$30,411. A contract to replace Guidewalls for the West 
Gate, Brazos River Floodgates was awarded in August 
1990. The 1992 fiscal year costs were $630,501. A contract 
to replace mooring anchors at Brazos River Floodgates 
was awarded June 21, 1991 and completed June 30, 1992 
with a 1992 fiscal year cost of $304,898. The Colorado 
River Locks were operated and maintained at a cost of 
$1,328,406 including engineering and design and 
supervision and administration. A contract to replace 
guidewalls for the West Lock East Gate, Colorado River 
Locks was physically completed in July 1992. The 1992 
fiscal year costs were $2,627,138. A contract for 
demolition of abandoned government facilities was 
awarded in August 1992 and completed in September 
1992. The cost at Brazos River Floodgate was $49,765 
and at Colorado River Locks, the cost was $31,981. 
Contract for dredging Port Isabel to Port Mansfield and 
tributaries was financially completed at a cost of $4,680. 
Dredging contract for Corpus Christi Bay to Mud Flats 
was financially completed for a cost of $46,929. Contract 
for dredging Port Isabel to Port Mansfield and tributaries 
was completed for $127,363. (See Table 31-H for dredging 
operations.) 
8. HOUSTON SHIP CHANNEL, TX 
Location. Connects Galveston Harbor, at a point 
opposite Port Bolivar, with city of Houston, Texas, 
extending 50 miles northwesterly across Galveston Bay 
through San Jacinto River and Buffalo Bayou to a turning 
basin at head of Long Reach with light-draft channel 5 
miles long from turning basin to Jensen Drive, Houston. 
(See National Ocean Survey Charts 11324/5, 11327, 11328, 
and 11329.) 
Previous project. For details see page 1856 of 
Annual Report for 1915. 
Existing project. Provides for channel dimensions 
in sections of the waterway shown in Table 31-F. 
Also provides for certain cut-offs, for easing sharp 
bends, an earthen dam across the upper end of Turkey 
Bend, and for off-channel silting basins as deemed 
necessary by the Chief of Engineers. Construction of 
26,000 linear feet of pile dike to protect the channel in 
upper Galveston Bay was deauthorized by Sec. 12 of PL 
93-251. The 40-foot project was completed in March 1966. 
Dredging a channel in Greens Bayou to Mile 1.57 was 
completed in 1970. Dredging Greens Bayou, Mile 1.57 to 
Mile 2.73, has been deauthorized. (See Table 31-E for 
total cost of existing project to September 30, 1992.) 
Mean tidal range under ordinary conditions is 0.6 
foot to 1.3 feet in lower part of Galveston Bay; 0.6 foot to 
1.3 feet in upper bay; and 0.5 to 1 foot in San Jacinto 
River and Buffalo Bayou. Extreme ranges under ordinary 
conditions are about 2 feet, 1.2 feet and 1 foot, respectively. 
Freshets caused rises of over 12 feet in Buffalo Bayou; 
however, this condition has not occurred since completion 
of Addicks and Barker Dams for flood control on upper 
watershed of Buffalo Bayou. Height of tides is dependent 
largely on the wind, and during strong "northers" in winter 
season the water surface may be depressed 2 feet below 
mean low tide. 
31-6

GALVESTON, TEXAS, DISTRICT 
Local cooperation. Fully complied with for Houston 
Ship Channel. Local Cooperation Agreements were being 
developed for assumption of maintenance on Bayport Ship 
Channel, Barbour Terminal Channel and Greens Bayou 
Channel. 
Terminal facilities. City of Houston and Port of 
Houston Authority operate modern terminals which 
supplement privately owned wharves, piers, and docks, 
as described in Port Series No. 24 (revised 1980), Corps 
of Engineers. Facilities are considered adequate for 
existing commerce. 
Operations during fiscal year. Contract for 
rehabilitation of the Spillman Island disposal area was 
financially completed at a cost of $800. An erosion 
protection contract was awarded December 16, 1991, for 
placing cloth material, blanket stone and riprap along 
the shoreline of Spillman Island. The contract was 
completed in May 1992 for a cost of $1,017,292. A dredging 
contract was awarded September 11, 1992 for dredging 
Houston Ship Channel, Morgans Point to Carpenters 
Bayou. The amount of $349,274 has been expended in 
fiscal year 1992 for mobilization cost. Routine 
maintenance included mosquito control spraying at a cost 
of $55,524. (See Table 31-H for dredging operations.) See 
Section 34, Planning and Engineering. 
9. MATAGORDA SHIP CHANNEL, TX 
Location. This is a consolidation of shallow draft 
channel improvements of "Channel from Pass Cavallo to 
Port Lavaca, Texas," and deep draft channel 
improvements authorized under "Matagorda Ship 
Channel, Texas." Bar at Pass Cavallo is 125 miles 
southwest of Galveston entrance and 54 miles north of 
Aransas Pass. It connects Matagorda Bay with the gulf. 
Project extends across Matagorda Bay and Lavaca Bay to 
towns of Port Lavaca and Point Comfort. These two towns 
are on opposite sides of Lavaca Bay and both are about 
26 miles northwest from Pass Cavallo. (See National 
Ocean Survey Chart 11316.) 
Existing project. Existing project dimensions 
provided for in various channels and basins are listed in 
Table 31-F on channel dimensions. 
Project also provides for dual jetties at entrance, south 
jetty extending 6,000 feet to 24-foot depth in the gulf and 
north jetty extending 5,900 feet to 24-foot depth. Under 
ordinary conditions mean tidal range is about 1 foot and 
extreme range about 2 feet. Height of tide is dependent 
largely on the wind, and during strong "northers" in winter 
season the water surface may be depressed 2 feet below 
mean low tide. Estimated cost for new work is: 
$18,058,777 Federal (Corps), and $12,859,000 non- 
Federal, including $12,259,619 contributed funds, 
$182,000 for lands, $220,000 for relocations, and $196,581 
other costs. The project was completed in March 1967. 
(See Table 31-E for total cost of existing project to 
September 30, 1992.) 
Local cooperation. Fully complied with. 
Terminal facilities. Privately owned facilities at Port 
Lavaca, municipally owned facilities at mouth of Lynn 
bayou, privately owned and publicly owned facilities at 
Point Comfort, Texas. These facilities are considered 
adequate for present commerce. Facilities at Point Comfort 
consist of a channel, turning basin with wharfs, oil dock 
and loading equipment, all owned by Aluminum Company 
of America; and a wharf built by local interest at Point 
Comfort turning basin. 
Operations during fiscal year. Routine 
maintenance. (See Table 31-H for dredging operations.) 
10. SABINE-NECHES WATERWAY, TX 
Location. This is a consolidation of old improvements 
of "Harbor at Sabine Pass and Port Arthur Canal" and 
"Sabine-Neches Canal, including Sabine River to Orange 
and Neches River to Beaumont, Texas." Sabine Pass is 
on Gulf of Mexico about 58 miles east of Galveston and 
280 miles west of Southwest Pass, Mississippi River. It 
connects Sabine Lake with gulf. Port Arthur canal extends 
7 miles from near upper end of Sabine Pass to Port Arthur 
docks at mouth of Taylors Bayou. Near its upper end, 
Sabine-Neches canal joins and extends to mouths of 
Neches and Sabine Rivers. Waterway next extends up 
Neches River to Beaumont and up Sabine River to Orange. 
(See National Ocean Survey Charts 11341, 11342, and 
11343.) 
Previous projects. For details see page 1863 of 
Annual Report for 1915, page 985 of Annual Report for 
1916, and page 873 of Annual Report for 1926. 
Existing project. Existing project dimensions 
provided for in various channels and basins are set forth 
in Table 31-F on channel dimensions. Project also provides 
for two stone jetties at Sabine Pass entrance from the 
gulf, western jetty to be 21,905 feet long and eastern 
jetty 25,310 feet long. Project further provides for removal 
of guard lock in Sabine-Neches Canal, construction of 
suitable permanent protective works along Sabine Lake 
frontage owned by city of Port Arthur to prevent dredged 
material from entering Sabine Lake and to prevent erosion 
of material deposited, reconstruction of Port Arthur 
Bridge, and relocation of Port Arthur field office. Mean 
tidal variation at entrance is about 1.5 feet, at Port Arthur 
about 1 foot, and at Orange and Beaumont about 0.5 
foot. Prolonged north winds during winter season have 
depressed water surface as much as 3.4 feet below mean 
low tide while tropical disturbances have caused heights 
as much as 8 feet above mean low tide. 
Existing project is complete. Removal of obstructive 
bridge at Port Arthur was completed May 1969. The high 
level fixed bridge across Sabine-Neches Canal was 
completed October 1970. Deepening project to 40 feet was 
completed April 1972. (See Table 31-E for total cost of 
existing project to September 30, 1992.) 
Local cooperation. Complied with. 
Terminal facilities. See volume 2, Port Series No. 
22 (revised 1981), Corps of Engineers. Facilities are 
considered adequate for present commerce. 
Operations during fiscal year. Contract for 
rehabilitation of East Jetty was completed at a fiscal year 
cost of $2,250,585. Contract for dredging Sabine Pass 
Channel, Port Arthur Turning Basin and Junction area 
was awarded July 10, 1992. A fiscal year cost of $345,000 
was expended for levees, spillways and ditches on Disposal 
areas 8 and 9, and dredging mobilization expenditures. 
31-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Routine maintenance included mosquito control spraying 
at a cost of $28,734. (See Table 31-H for dredging 
operations.) 
11. TEXAS CITY CHANNEL, TX 
Location. Texas City is on the mainland of Texas on 
west side of Galveston Bay, about 10 miles northwest of 
city of Galveston. (See National Ocean Survey Charts 
11324/5.) 
Previous projects. For details see page 1856 of 
Annual Report for 1915. 
Existing project. Provides for channel 40 feet deep, 
400 feet wide and about 6.75 miles long, from Bolivar 
Roads to a turning basin at Texas City, 40 feet deep, 
1,000 feet to 1,200 feet wide and 4,253 feet long; and an 
Industrial Canal, 40 feet deep and 300-400 feet wide 
extending a distance of 1.7 miles southwestward from 
the south end of Texas City Turning Basin, and a turning 
basin, 40 feet deep, 1,000 feet wide and 1,150 feet long. 
Project also provides for easing the approach to the 
turning basin; a pile dike 28,200 feet long, parallel to 
and north of the channel; and a rubble-mound dike, 27,600 
feet long, along the southerly side of the pile dike. 
The 40-foot channel was completed in June 1967. 
Widening the Texas City Turning Basin; realigning the 
Texas City Turning Basin to a location 85 feet easterly 
from its present position; and enlargement through 
widening and deepening of the Industrial Canal and 
basins was initiated in July 1980 and completed in June 
1982. The only work remaining is deferred construction 
consisting of widening the Industrial Canal from 250 feet 
to 300 feet at 40 foot depth. 
Work authorized by Water Resources Development 
Act of 1986 would modify the project by providing for 
deepening the Texas City Turning Basin to 50 feet, 
enlarging the 6.7-mile long Texas City Channel to 50 feet 
by 600 feet, deepening the existing 800-foot wide Bolivar 
Roads Channel and Inner Bar Channel to 50 feet, 
deepening the existing 800-foot wide Outer Bar and 
Galveston Entrance Channel to a 52-foot depth for 4.1 
miles at a width of 800 feet and an additional reach at a 
width of 600 feet to the 52 foot contour in the Gulf of 
Mexico. Establishment of 600 acres of wetland and 
development of water-oriented recreational facilities on a 
90-acre enlargement of the Texas City Dike are also 
proposed. At the request of local sponsor, City of Texas 
City, the project has been placed in the "deferred" category. 
(See Table 31-E for total cost of existing project to 
September 30, 1992.) 
Under ordinary conditions mean tidal range is about 
1.3 feet and extreme range is about 2 feet. Height of tide 
is dependent largely on the wind and during strong 
"northers" water surface may be depressed 2 feet below 
mean low tide. Estimated cost for new work is 
$123,300,000 Federal (Corps), excluding expenditures on 
previous projects, and $74,393,700 non-Federal, including 
$62,027,741 contributed funds, $248,000 work 
contribution, $427,959 lands, $10,737,000 levees and 
spillways, $6,000 for removal of barge mooring facilities 
from Shoal Point (formerly known as Snake Island), 
$561,000 for berthing areas, and $386,000 relocations. 
Local cooperation. Fully complied with for 
completed work. For work authorized by the Water 
Resources Development Act of 1986, local interests are 
required to provide levees for disposal areas and wetlands; 
relocate utilities, roads, and other facilities, except railroad 
bridges; provide berthing areas; pay one-half of the 
separable and joint costs allocated to recreation; and bear 
all costs of operation, maintenance and replacement of 
recreation facilities, and, during construction, pay 25 
percent of the costs allocated to deep-draft navigation to 
a depth of 45 feet plus 50 percent of the costs allocated to 
deep-draft navigation deeper than 45 feet; pay an 
additional 10 percent of the costs allocated to deep-draft 
navigation within a period of 30 years following completion 
if not offset by credit allowed for lands, easements, rightsof-
way, relocations and disposal areas; and pay 50 percent 
of the costs incurred for operation and maintenance below 
the 45-foot depth. 
Terminal facilities. Privately owned terminal 
facilities are on the mainland at inner end of this channel 
and are considered adequate for existing commerce. A 
deep-draft channel and turning basin extend about 1.9 
miles southwestward from south end of Texas City 
Turning Basin have been constructed by local interests. 
See Port Series No. 23 (revised 1979), Corps of Engineers. 
Operations during fiscal year. Maintenance: A 
contract for dredging Texas City Channel Turning Basin 
was awarded September 8, 1992. Funds in the amount of 
$100,000 have been expended for mobilization costs. 
12. TRINITY RIVER AND 
TRIBUTARIES, TX 
Location. The main stem of the Trinity River is 
formed at Dallas by the confluence of the West Fork and 
the Elm Fork at river mile 505.5. The mouth of the Trinity 
is about one-half mile west of Anahuac, Texas. (See 
Geological Survey base map, Texas, scale 1:500,000.) 
Previous project. For details of abandoned locks 
and dam construction see page 986 of Annual Report for 
1932. 
Existing project. See individual detailed reports on 
Anahuac Channel, Channel to Liberty and Wallisville 
Lake. Project includes the existing Federal project 
designated as "Mouth of Trinity River, Texas," which was 
completed in 1907 at a cost of $80,000 (no cost to local 
interest). Project is not being maintained. (See Table 
31-E for total cost of existing project to September 30, 
1992.) 
Local cooperation. See individual detailed reports 
on Channel to Liberty and Wallisville Lake. There is no 
local cooperation required for Anahuac Channel. 
Terminal facilities. Privately owned wharves and 
piers at Anahuac, Moss Bluff, Wallisville, and Liberty, 
Texas, are adequate for existing commerce. 
12A. ANAHUAC CHANNEL, TX 
Location: Extends from 6-foot depth in Galveston 
Bay to Anahuac, Texas, opposite mouth of Trinity River 
38 miles north of Galveston, Texas. (See National Ocean 
Survey Chart 11323.) 
31-8

GALVESTON, TEXAS, DISTRICT 
Existing project. No project dimensions authorized 
by 1905 River and Harbor Act. A 6- by 80-foot channel, 
16,000 feet long was dredged in 1905. At present a 6- by 
100-foot channel is maintained. Under ordinary conditions 
tidal range is 0.6 to 1.2 feet. Height of tide is dependent 
largely on wind. Strong north winds depress water surface 
1.5 feet below mean sea level. Latest published map is in 
House Document 440, 56th Congress, 1st Session. Project 
was completed in 1911. 
Local cooperation. None required. 
Terminal facilities. Privately owned wharves and 
piers are the only terminal facilities at Anahuac. 
Operations during fiscal year. Routine maintenance. 
12B. CHANNEL TO LIBERTY, TX 
Location. Improvement is located in Galveston Bay 
and tidal reach of lower Trinity River. (See Geological 
Survey Maps for Anahuac, Cove, Moss Bluff, and Liberty, 
Texas.) 
Previous projects. For details see page 986 of 
Annual Report for 1932. 
Existing project. Provides for a 6-foot channel from 
Anahuac to Liberty which was completed in 1925. A 
navigable channel from the Houston Ship Channel near 
Red Fish Bar in Galveston Bay to Liberty, Texas, with 
depth of 9 feet and width of 150 feet, extending along the 
east shore of Trinity Bay to the mouth of the Trinity 
River at Anahuac, thence in the river channel to a turning 
basin at Liberty, Texas, and a protective embankment 
along the west side of the channel in Trinity Bay. 
The 6-foot Channel to Liberty was completed in 1925. 
The 9-foot Channel to Liberty has been dredged from 
junction with Houston Ship Channel to a point one mile 
below Anahuac, Texas. Work remaining consists of 
dredging a 9- by 150-foot channel from one mile below 
Anahuac, Texas to Liberty, Texas. 
Local cooperation. Fully complied with for portion 
of "Channel to Liberty" between Houston Ship Channel 
and 1 mile below Anahuac, Texas, as required by 1946 
River and Harbor Act (H. Doc. 634, 79th Cong., 2nd Sess.), 
but not complied with for remaining portion of "Channel 
to Liberty" as required by River and Harbor Act of 1945 
(H. Doc. 403, 77th Cong., 1st Sess.) at an estimated total 
cost of $550,000, of which $460,000 is for lands and rightsof-
way and $90,000 for pipeline relocations for 9- by 150- 
foot channel. 
Terminal facilities. Privately owned wharves and 
docks at Anahuac, Wallisville, Texas Gulf Sulphur Co.'s 
slip, Moss Bluff and Liberty, Texas, are adequate for 
existing commerce. 
Operations during fiscal year. Routine 
maintenance including mosquito control spraying for a 
cost of $6,475. (See Table 31-H for dredging operations.) 
12C. WALLISVILLE LAKE, TX 
Location. Dam is at river mile 3.9, about 4 miles 
northwest of Anahuac, Texas. (See National Ocean Survey 
Chart 11323.) 
Existing project. Provides for construction of a dam 
and overflow spillway approximately 8 miles long to 
prevent salinity intrusion and create a 3,800 acre 
reservoir. The maximum pool elevation will be 2 feet above 
National Geodetic Vertical Datum. (The reservoir was 
reduced from 5600 acres with a maximum pool elevation 
of 4 feet N.G.V.D. by agreement to protect the endangered 
bald eagle.) Project provides for an 84 foot by 600-foot 
navigation lock to facilitate navigation on Channel to 
Liberty. The sill has a depth of minus 16 feet below 
National Geodetic Vertical Datum. Project also provides 
for two recreational areas. Dam controls a drainage area 
of 1,262 square miles below Livingston Dam (non-Federal 
project at channel mile 99.2) and has a storage capacity 
of 14,000 acre-feet. Under ordinary conditions mean tidal 
range in bay is from 0.6 foot to 1.2 feet. Height of tide is 
dependent largely on wind. Strong northerly winds 
depress water surface 1.5 feet below mean sea level. Total 
estimated cost of authorized project is $77,290,000 Federal 
(Corps). (October 1, 1992 base price.) 
A contract for construction of access road, Big Hog 
intake structure, intake canal and access bridge was 
completed in October 1968. Work started in July 1970 on 
construction of the lock and dam, roads, diversion channel, 
and navigation channel. Work was suspended in February 
1973 because of an injunction halting construction. 
Protective work on the lock and dam was permitted and 
was completed in April 1973. An exception to the 
injunction was granted for plugging oil wells which was 
completed in August 1973. Notice of appeal to the Court 
of Appeals for the Fifth Circuit was filed in April 1973. 
In August 1974, the Court of Appeals reversed the 
judgment and remanded the case with directions that a 
revised or supplemental statement be prepared and judged 
anew. Final supplement to the Environmental Impact 
Statement for the modified project authorized in the 
Supplemental Appropriations Act, 1983 (PL 98-63) was 
submitted to the Environmental Protection Agency on 
September 21, 1983. 
In March 1986, the Court rendered its Memorandum 
of order continuing the injunction and directing the Corps 
to re-commence the administrative process at the time 
when the first departure from standard NEPA procedures 
occurred prior to the 1983 legislative action. The Corps 
and local sponsors perfected an appeal to the U.S. Court 
of Appeals and on May 11, 1987, the Court of Appeals 
ruled in favor of the Corps and dismissed the suit in its 
entirety. 
The Energy and Water Development Appropriation 
Act of 1991 provided $9,200,000 for the project and 
directive language for continuation of construction. 
In the fall of 1989, a pair of bald eagles were 
discovered nesting at the project site which led to 
additional consultation under the Endangered Species Act. 
Solicitation of the contract for the non-overflow dam was 
postponed to allow for environmental coordination. An 
Environmental Assessment was prepared with a Finding 
of No Significant Impact (FONSI) which was signed in 
September 1991. Environmental documents were 
approved and construction was resumed. 
Local cooperation. Local interest must contribute 
an amount equal to cost allocated to water supply, onehalf 
of cost allocated to salinity control and cost allocated 
31-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
to recreation less cost of basic facilities and less 15 percent 
of total project cost. Local interest reimbursement is 
estimated at $11,246,000. 
Operations during fiscal year. New Work: Contract 
for construction of non-overflow dam was awarded 
September 20, 1991. The contract continued through 
Fiscal Year 1992 with a cost of $1,757,129. A contract 
was awarded August 30, 1991 to construct an 
instrumentation platform. The contract was completed 
for a total cost of $28,507. 
Maintenance: Ranger surveillance, administration of 
project, and administration of duck blind permit program 
was conducted. 
13. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and Condition Surveys were 
conducted on the following projects: 
Project 
Galveston Harbor 
and Channel 
Freeport Harbor 
Texas City 
Channel 
Clear Creek 
Channel to Port 
Bolivar 
Houston Ship 
Channel 
Gulf Intracoastal 
Waterway 
Matagorda Ship 
Channel 
Trinity River 
and Trib. 
Date of Survey 
Oct 1991 - Jun 1992 
Oct 1991 - May 1992 
Nov 1991 - Sep 1992 
Feb 1992 to
Feb 1992 
May - Jul 1992 
Jun 92 
Jun 1992 and Sep 1992 
Jul 1992 
11,925 
$47,141 
14. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (preauthorization). 
Reconnaissance study for navigation channel 
improvements on Sabine-Neches Waterway, Texas was 
performed in fiscal year 1992 at a cost of $59,917. The 
study has been terminated for the lack of sponsorship. 
Beach Erosion Control 
15. CORPUS CHRISTI BEACH, TX 
(RESTORATION PROJECT) 
Location. Corpus Christi Beach, a shore area having 
a length of about 2 miles, is located on the west side of 
Corpus Christi Bay in Nueces County at Corpus Christi, 
Texas. (See National Ocean Survey Charts 11309 and 
11311.) 
Existing project. The plan of improvement provided 
for initial restoration of eroded areas of Corpus Christi 
Beach, over a shore length of 1.4 miles, located on the 
easterly side of Rincon Peninsula, with periodic 
nourishment as required. Construction was completed in 
March 1978. Periodic nourishment and construction of 
sand retention groin was completed in November 1985. 
Estimated cost of new work is $2,150,000 Federal (Corps) 
and $2,265,000 non-Federal consisting of $2,150,000 
Contributed funds, $43,000 relocations, and $72,000 lands. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Section 934 of 
Water Resources Development Act of 1986 provides for 
extension of nourishment period to 50 years for beach 
nourishment projects. A study to determine the 
appropriateness of such an extended nourishment period 
for the Federal beach nourishment project was completed. 
The study indicated that there was no economic 
justification for continued Federal participation in the 
program. The responsibility for beach monitoring and 
maintenance was transferred to the City of Corpus Christi 
in July 1990. 
Flood Control 
16. BUFFALO BAYOU AND 
TRIBUTARIES, TX 
Location. Improvements are on Buffalo Bayou 
watershed, a part of San Jacinto River watershed, in 
Harris County, west and northwest of city of Houston, 
Texas. (See Geological Survey quadrangle sheets for 
Harris County.) 
Existing project. Provides for improvements of 
Buffalo Bayou and its tributaries above turning basin of 
Houston Ship Channel to control floods for protection of 
city of Houston, and prevent deposition of silt in turning 
basin of ship channel by construction of detention 
reservoirs, enlargement and rectification of channels and 
construction of control works. Cost of new work is 
$127,000,000 Federal (Corps) and $86,891,000 non- 
Federal for lands and relocations. (October 1, 1986 base 
price.) 
Channel rectification on Brays Bayou with an 
improved channel length 25.4 miles was completed in 
March 1971. Channel rectification on White Oak Bayou 
was completed in 1976. Work remaining consists of 
31-10

GALVESTON, TEXAS, DISTRICT 
rectification of approximately 22 miles of main stem of 
Buffalo Bayou. 
See individual detailed reports on Addicks and Barker 
Reservoirs; and Brays, Greens, Halls, Hunting, Little 
White Oak, and Carpenters Bayous. 
Local cooperation. Section 203, 1954 Flood Control 
Act applies. Local interests have accomplished all required 
local cooperation on Brays Bayou and White Oak Bayou. 
On Buffalo Bayou, local interests purchased interests that 
the United States had in 7 miles of rectified channel 
below Barker and Addicks Dams for $256,651. Of the 
remaining required rights-of-way on Buffalo Bayou, local 
interests have acquired about 40 percent. About 53 percent 
of required bridge relocations and 3 percent of the required 
bridge relocations have been accomplished. Advance of 
$4,400,000 by the Harris County Flood Control District 
was refunded in September 1956. Public Law 86-53 
authorized reimbursement of $38,726 to Galveston, 
Houston. and Henderson Railroad Company for bridge 
alterations at Brays Bayou. Non-Federal contributions 
totaled $63,661 for project betterment. Recreation 
development is subject to conditions of non-Federal costsharing 
under Federal Water Project Recreation Act of 
1965. 
See individual detailed reports on Addicks and Barker 
Reservoirs; and Brays, Greens, Halls, Hunting, Little 
White Oak, and Carpenters Bayous. 
16A. ADDICKS AND BARKER 
RESERVOIRS, TX 
Location. Reservoirs are located in and west of the 
City of Houston in Harris, Waller, and Fort Bend 
Counties, Texas. 
Existing project. Construction of Barker Dam was 
complete in February 1945. Construction of Addicks Dam 
and 7.4 miles of channel rectification downstream from 
Addicks and Barker Dams was completed in October 1948. 
Modification of Barker and Addicks Dams consisting of 
gating of two uncontrolled conduits in each dam, was 
complete in 1969. Major rehabilitation of Addicks and 
Barker Dams to prevent seepage through the embankment 
was completed in 1982. Estimated cost of new work is 
$11,214,000 Federal (Corps) for Dam Safety Assurance 
and $11,900,000 for recreational facilities at completed 
projects (Code 713 funds). Non-Federal funds consist of 
$11,900,000 contributions for recreational facilities. 
(October 1991 base price.) 
Work under the Dam Safety Assurance program was 
initiated in Fiscal Year 1986. Work to be accomplished 
includes raising approximately 32,400 feet of Addicks Dam 
1 to 3 feet and raising approximately 57,600 feet of Barker 
Dam 3 to 5 feet and armor-plating low ends of both dams. 
A contract with the city of Houston for cost-sharing in the 
construction of recreation facilities was entered into in 
November 1981. The lease for approximately 10,534 acres 
of land and water areas was approved in February 1983. 
Local cooperation. None required. 
Operations during fiscal year. Recreation: Community 
Park West (Phase IB) and the velodrome were 
completed in November 1986. Grading and clearing for 
an archery range was performed by the City of Houston 
in March and April 1987. Work has been initiated on a 
construction contract, awarded for Community Park West 
(Phase 2) in 1988. Harris County Precinct 3, Cullen- 
Barker Park, completed Community Park 2 which 
includes soccer fields and parking lots. The plans for 
Community Park West, Phase III, were approved in 1989. 
Construction on Phase III was initiated in 1990. 
Dam Safety Assurance: Contract for armor plating 
the ends of the dams, awarded in May 1987, was 
financially completed at a cost of $1,283,854. Construction 
contract to raise main dam at Addicks Dam was 
financially completed at a cost of $45,087. 
Maintenance: Routine operations and maintenance 
at Addicks and Barker Dams. A contract to repair roadway 
at Addicks Dam was awarded May 29, 1992. The contract 
was completed at a 1992 fiscal year cost of $241,282. 
16B. BRAYS BAYOU, TX 
Location. The project is located in the south-central 
portion of Buffalo Bayou, Harris County, TX. 
Existing project. The authorized plan of 
improvement consists of 3 miles of stream improvements, 
3 flood detention basins, and 7 miles of stream diversion 
channels. Aesthetic vegetation is included. Recreation 
facilities include trails, picnic facilities, sports fields, 
comfort stations and parking areas. The estimated cost 
for new work is $158,251,000 Federal (Corps) and 
$158,251,000 non-federal consisting of $17,230,000 cash 
contributions, and $141,021,000 for lands and relocations 
(October 1992 base price). 
Location cooperation. Local sponsor for the project 
is Harris County Flood Control District. Local sponsor is 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $17,230,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control and recreation facilities. 
Operations during fiscal year. New Work: The 
project was authorized for construction in the Water 
Resources Development Act of 1990 (PL 101-640). See 
Section 34, Planning and Engineering. 
16C. GREENS BAYOU, TX 
Location. The project is located in the north-central 
portion of Buffalo Bayou, Harris County, TX, and does 
not include the Halls Bayou tributary. 
Existing project. The authorized plan of 
improvement consists of 25 miles of stream enlargements, 
14 miles of stream clearing and 4 flood detention basins. 
Aesthetic vegetation and mitigation is included. Recreation 
facilities include trails, picnic facilities, sports fields, 
launches, ramps, comfort stations and parking areas. The 
estimated cost for new work is $153,837,000 Federal 
(Corps) and $68,499,000 non-Federal consisting of 
$12,923,000 cash contributions, and $55,576,000 for lands 
and relocations (October 1992 base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. Local sponsor is 
31-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $12,923,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control and recreation facilities. 
Operations during fiscal year. New Work: The 
project was authorized for construction in the Water 
Resources Development Act of 1990 (PL 101-640). See 
Section 34, Planning and Engineering. 
16D. HALLS BAYOU, TX 
Location. Halls Bayou is a major tributary of Greens 
Bayou, located in the north-central portion of Buffalo 
Bayou, Harris County, TX. 
Existing project. The authorized plan of 
improvement consists of 18 miles of stream improvements. 
Recreation facilities include trails, picnic facilities, boat 
ramps, a comfort station and parking areas. The estimated 
cost for new work is $54,576,000 Federal (Corps) and 
$44,760,000 non-Federal consisting of $6,696,000 cash 
contributions, and $38,064,000 for lands and relocations 
(October 1992 base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. Local sponsor is 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $6,696,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control and recreation facilities. 
Operations during fiscal year. New Work: The 
project was authorized for construction in the Water 
Resources Development Act of 1990 (PL 101-640). Project 
is awaiting Planning and Engineering funds. 
16E. HUNTING BAYOU, TX 
Location. Hunting Bayou is located in Houston, 
approximately 4 to 5 miles from the central business 
district. 
Existing project. The authorized plan of 
improvement consists of 14.3 miles of stream 
improvements. Recreation facilities include trails, picnic 
facilities, a comfort station and parking areas. The 
estimated cost for new work is $54,332,000 Federal (Corps) 
and $52,251,000 non-Federal consisting of $5,681,000 cash 
contributions, and $46,570,000 for lands and relocations 
(October 1992 base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. Local sponsor is 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $5,681,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control and recreation facilities. 
Operations during fiscal year. New Work: The 
project was authorized for construction in the Water 
Resources Development Act of 1990 (PL 101-640). Project 
is awaiting Planning and Engineering funds. 
16F. LITTLE WHITE OAK BAYOU, TX 
Location. Little White Oak Bayou is a tributary of 
White Oak Bayou in north-central Houston. 
Existing project. The authorized plan of 
improvement consists of 6.0 miles of stream enlargements. 
Recreation facilities include trails and picnic facilities. 
The estimated cost for new work is $17,958,000 Federal 
(Corps) and $17,957,000 non-Federal consisting of 
$1,996,000 cash contributions, and $15,961,000 for lands 
and relocations (October 1990 base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. Local sponsor is 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $1,996,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control and recreation facilities. 
Operations during fiscal year. New Work: The 
project was authorized for construction in the Water 
Resources Development Act of 1990 (PL 101-640). Project 
is awaiting Planning and Engineering funds. 
16G. CARPENTERS BAYOU, TX 
Location. Carpenters Bayou is a tributary of Buffalo 
Bayou in northeastern Houston. 
Existing project. The authorized plan of 
improvement consists of 9.7 miles of stream enlargements. 
Recreation facilities include trails and picnic facilities. 
The estimated cost for new work is $3,900,000 Federal 
(Corps) and $1,950,000 non-Federal consisting of $370,000 
cash contributions, and $2,320,000 for lands and 
relocations (October 1990 base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. Local sponsor is 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $370,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control and recreation facilities. 
Operations during fiscal year. New Work: The 
project was authorized for construction in the Water 
Resources Development Act of 1990 (PL 101-640). Project 
is awaiting Planning and Engineering funds. 
17. CLEAR CREEK, TX 
Location. The project is located about midway 
between the two metropolitan centers of Houston, Texas, 
on the north and Galveston-Texas City on the south in 
Harris and Galveston Counties above and below existing 
Clear Lake. 
Existing project. The authorized plan of 
improvement consists of an improved channel from Mile 
3.8 to Mile 34.8 to contain within its banks all flood flows 
up to and including that of a 100-year flood. The selected 
plan provides channel enlargement and easing of bends 
within the existing stream from Mile 3.8 to Mile 26.05 to 
contain at least the 10-year frequency storm, and 
31-12

GALVESTON, TEXAS, DISTRICT 
additional outlet with gated structure from Clear Lake to 
Galveston Bay, restriction of development in the residual 
100-year flood plain and measures to mitigate 
environmental effects. In 1986, at the request of Brazoria 
County Drainage District No. 4, that portion of the project 
upstream of the Brazoria/Galveston County line, 
approximate improved Mile 19.1, was placed in the 
"inactive" category. Estimated cost for new work, excluding 
"inactive" portion, is $61,255,000 Federal (Corps) and 
$50,656,000 non-Federal consisting of $5,596,000 cash 
contributions, $22,600,000 for lands, and $22,460,000 for 
relocations (October 1, 1992 base price). 
Local cooperation. Local sponsors for the project 
are Galveston and Harris counties. The Local Cooperation 
Agreement, executed 30 June 1986, requires local interests 
to provide lands, easements, rights-of-way, and material 
disposal areas; modify or relocate building, pipelines, 
utilities, roads and other facilities, except railroad bridges, 
where necessary in the construction of the project; make 
a cash contribution for mitigation measures consistent 
with the non-Federal share of total project costs without 
mitigation measures; pay five percent of the total costs 
allocated to flood control; and bear all costs of operation 
and maintenance of flood control facilities. 
Operations during fiscal year. Engineering and 
Design is underway. 
18. CYPRESS CREEK, TX 
Location. The project is located north of Houston, 
Texas in Harris County. 
Existing project. The authorized plan of 
improvement consists of enlargement of the lower 29.4 
miles of the Cypress Creek Channel, incorporating grassed 
side slopes and channel bottom and appropriate erosion 
control measures; application of floodplain management 
techniques in the residual floodplain; construction of 
project-oriented recreation features, including 11.5 miles 
of hike-and-bike trails and related facilities for health, 
safety, and public access; and habitat management 
measures on 844 acres of Harris County Parkway land, 
creation of wooded and brush habitat along 100 acres of 
the project right-of-way, acquisition of 329 acres of wildlife 
habitat along the creek, and creation of 35 acres of ponds 
and marshes. Estimated cost for new work is $100,271,000 
Federal (Corps) and $34,601,000 non-Federal consisting 
of $12,471,000 cash contribution, $15,698,000 for lands, 
and $6,432,000 for relocations (October 1, 1992 base price). 
Local cooperation. Local sponsor for the project is 
Harris County. Local sponsor is required to provide lands, 
easements, and rights-of-way; modify or relocate buildings, 
pipelines, utilities, roads and other facilities, except 
railroad bridges; provide a cash contribution presently 
estimated at $12,471,000; and bear all costs of operation, 
maintenance, and replacement of flood control and 
recreation facilities. 
Operations during fiscal year. See Section 34, 
Planning and Engineering. 
19. FALFURRIAS, TX 
Location. The city of Falfurrias is located near the 
confluence of Palo Blanco and Cibolo Creeks, intermittent 
streams that drain a 600-square-mile area in south Texas. 
Existing project. The authorized plan of improvement 
consists of a 5.6 mile long diversion levee; a 1.8 
mile long pilot channel; a flowage easement of 11,000 
acres of land subject to overflows from the pilot channel; 
and a 0.8 mile long ring levee around the sewage 
treatment plant. Estimated cost for new work is 
$16,870,000 Federal (Corps) and $16,870,000 non-Federal 
consisting of $1,687,000 cash contribution, $13,013,000 
for lands, and $2,170,000 for relocations (October 1, 1991 
base price). 
Local cooperation. The local sponsor would be 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipeline, utilities, roads and 
other facilities, except railroad bridges; provide a cash 
contribution presently estimated at $1,687,000 and bear 
all costs of operation, maintenance and replacement of 
flood control facilities. 
Operations during fiscal year. See Section 34, 
Planning and Engineering. 
20. KIRBYVILLE, TX 
Location. The project is located in Southeast Texas 
in the Sabine River basin on Trout Creek and Pin Oak 
Creek in the vicinity of Kirbyville, Texas, about 45 miles 
north of Beaumont, Texas. 
Existing project. The plan of improvement is a 
combination channelization and floodplain management 
plan for Trout and Pin Oak Creeks. The structural element 
consists of a slightly enlarged channel and clearing and 
straightening of Trout Creek. The non-structural part 
consists of controls on future development in the residual 
100-year floodplains along Trout and Pin Oak Creeks. 
Channel improvements in Trout Creek begin about 0.8 
mile downstream from the Jasper-Newton County line 
and end about 0.4 mile upstream from the U.S. Highway 
96 bridge. The improved, grass-lined channel will be 2.7 
miles long, and generally follow the existing alignment of 
Trout Creek. A steel sheet pile and riprap drop structure 
will be constructed on Pin Oak Creek near its confluence 
with Trout Creek. Drainage culverts will be constructed 
along the improved channel on Trout Creek to facilitate 
lateral drainage and control erosion. Work includes some 
alterations to a Santa Fe Railroad bridge to accommodate 
the project and a new roadway bridge providing 
approximately 2,000 square feet of opening for passage of 
floodwaters. Estimated cost for new work is $1,468,950 
Federal (Corps) and $501,050 non-Federal consisting of 
$98,500 cash contribution, $402,550 for lands and 
relocations. (1 October 1991 base prices) 
Local cooperation. Local sponsor for the project is 
the City of Kirbyville, Texas. A Local Cooperation 
Agreement was signed by the sponsor in August 1987. 
Operations during fiscal year. Contract for 
channelization of Trout Creek, awarded in August 1989, 
was financially completed at a 1992 fiscal year cost of 
$3,800. 
21. LOWER RIO GRANDE BASIN, TX 
Location. The project is located in Willacy, Hidalgo, 
and Cameron Counties. The basin is bounded on the east 
by the Gulf of Mexico, on the south by the Rio Grande 
which forms the international boundary between the 
31-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
United States and Mexico, on the west by Starr County, 
and on the north by Brooks and Kenedy Counties. 
Existing project. See individual detailed reports on 
Arroyo Colorado, South Main Channel, and Raymondville 
Drain. 
Local cooperation. See individual detailed reports 
on Arroyo Colorado, South Main Channel, and 
Raymondville Drain. 
21A. ARROYO COLORADO, TX 
Location. The project is located in Hidalgo and 
Cameron Counties, Texas. 
Existing project. The authorized project will provide 
flood protection along Highway 83 and erosion protection 
for the banks of the Arroyo Colorado in the city of 
Harlingen. The project consists of a gated water control 
structure, 1.4 miles of channel improvements, and stone 
armoring of selected reaches in Harlingen. The estimated 
cost for new work is $5,716,000 Federal (Corps) and 
$1,906,000 non-Federal consisting of $1,803,000 cash and 
$103,000 for lands and relocations. 
Local cooperation. Local sponsor for the project is 
Hidalgo County Drainage District #1. Local sponsor is 
required to provide lands, easements, and rights-of-way; 
modify or relocate buildings, pipelines, utilities, roads and 
other facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $1,803,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control facilities. 
Operations during fiscal year. New Work: See 
Section 34, Planning and Engineering. 
21B. SOUTH MAIN CHANNEL, TX 
Location. The project is located in Hidalgo and 
Willacy Counties, Texas. 
Existing project. The authorized project consists of 
channel improvements which will provide flood protection 
to the cities of McAllen, Edinburg, Edcouch, La Villa and 
Lyford, as well as the rural areas of Hidalgo and Willacy 
Counties north of U.S. Highway 83. The estimated cost 
for new work is $104,460,000 Federal (Corps) and 
$63,619,000 non-Federal consisting of $8,394,000 cash and 
$28,107,000 lands and $27,118,000 relocations. 
Local cooperation. Local sponsors for the project 
are Hidalgo County Drainage District #1 and Willacy 
County Drainage District #1. Local sponsor is required to 
provide lands, easements, and rights-of-way; modify or 
relocate buildings, pipelines, utilities, roads and other 
facilities, except for railroad bridges; provide a cash 
contribution presently estimated at $8,394,000 and bear 
all costs of operation, maintenance, and replacement of 
flood control facilities. 
Operations during fiscal year. New Work: See 
Section 34, Planning and Engineering funds. 
21C. RAYMONDVILLE DRAIN, TX 
Location. The project is located in northern Hidalgo 
and Willacy Counties, Texas. 
Existing project. The authorized project will provide 
a drainage outlet to the Laguna Madres for northern 
Hidalgo and Willacy Counties. The project consists of 43.8 
miles of channel work, including enlargement of existing 
channels and construction of new channels, a 3.88-mile 
long levee, and diversion ditches along the west side of 
Raymondville. The estimated cost for new work is 
$48,665,000 Federal (Corps) and $16,225,000 non-Federal 
consisting of $3,900,000 cash and $6,142,000 lands and 
$6,183,000 relocations. 
Local cooperation. Local sponsor for the project is 
Hidalgo County Drainage District #1 and Willacy County 
Drainage District #1. Local sponsor is required to provide 
lands, easements, and rights-of-way; modify or relocate 
buildings, pipelines, utilities, roads and other facilities, 
except for railroad bridges; provide a cash contribution 
presently estimated at $3,900,000 and bear all costs of 
operation, maintenance, and replacement of flood control 
facilities. 
Operations during fiscal year. New Work: Project 
is awaiting Planning and Engineering funds. 
22. PORT ARTHUR AND VICINITY, TX 
(HURRICANE-FLOOD 
PROTECTION) 
Location. Port Arthur is on west shore of Sabine 
Lake in extreme southeast part of Texas, about 14 miles 
from the gulf. Area under consideration is comprised of 
about 38,500 acres, and includes cities of Port Arthur 
and Groves, towns of Griffin Park, Pearl Ridge, and 
Lakeview, and adjacent industrial areas. 
Existing project. Authorized plan provides for 
raising and reconstructing 6.3 miles of existing concrete 
and steel sheet-pile seawall; constructing 0.3 mile of new 
concrete and sheet-pile seawall; raising and improving 
3.0 miles of existing earth levees; constructing 20.3 miles 
of new earth levees and constructing five interior drainage 
pumping plants. Raising and strengthening of levees 
surrounding Gulf Oil Company's fresh water reservoir 
was placed in the "inactive" category in December 1980. 
The project was initiated in March 1966 and the active 
portion of the project was completed in 1984. Estimated 
cost for new work, excluding "inactive" portion, is 
$62,350,000 Federal (Corps) and $27,150,000 non-Federal 
consisting of $17,342,000 cash contributions, $3,403,000 
for lands, $6,405,000 for relocations, and $449,000 for 
pumping station betterments and levee realignment 
betterments. 
Local cooperation. Fully complied with. 
Operation during fiscal year. A severe settlement 
problem exists in the Chevron Sabine Road Tank Farm 
area. The Galveston District continued to conduct 
investigations and monitoring of the settlement to help 
determine appropriate corrective actions of Federal 
interest. 
23. SIMS BAYOU, TX 
Location. The project is located in Harris County, in 
the southern portion of Houston, Texas. 
Existing project. The authorized plan of 
improvement provides for enlargement and rectification, 
with appropriate erosion control measures, of 19.3 miles 
31-14

GALVESTON, TEXAS, DISTRICT 
of Sims Bayou to provide 25-year flood protection; 
environmental measures and riparian habitat 
improvement along the entire alignment; and recreational 
development to include 27 miles of hike-and-bike trails 
connecting to existing public parks, together with picnic, 
playground, and other leisure facilities. Estimated cost 
for new work is $182,474,000 Federal (Corps) and 
$85,346,000 non-Federal consisting of $15,703,000 cash 
contributions, $33,431,000 for lands, $33,618,000 for 
relocations and $2,594,000 other cost (October 1, 1992 
base price). 
Local cooperation. Local sponsor for the project is 
Harris County Flood Control District. In accordance with 
the cost-sharing and financing concepts reflected in the 
Water Resources Development Act of 1986, local interests 
are required to provide lands, easements, and rights-ofway; 
modify or relocate buildings, pipelines, utilities, 
roads, and other facilities, except railroad bridges, where 
necessary for the construction of the project; pay one-half 
of the separable and joint costs allocated to recreation; 
and bear all costs of operation, maintenance and 
replacement of recreation facilities; and pay 5 percent of 
the costs allocated to flood control; and bear all costs of 
operation, maintenance and replacement of flood control 
facilities. The Local Cooperation Agreement for flood 
control was executed on October 19, 1990. The recreation 
Local Cooperation Agreement is pending. 
Operations during fiscal year. New Work: Fiscal 
Year 1992 operations include coordination of real estate 
requirements with the local sponsor and continuation of 
design work. 
24. STATE HIGHWAY 111 BRIDGE, 
LAKE TEXANA, TX 
Location. The project is located 8.5 miles Southeast 
of Edna, Texas and 31 miles Northeast of Victoria, Texas. 
Existing project. The plan of improvement requires 
placement of granular fill and stone protection along the 
embankment slope at the southwest end of the East Relief 
Bridge to form a slope of 1 on 4. Stone protection will 
consist of an 18-inch layer of riprap placed on a 6-inch 
layer of graded blanket stone. The work will require 
placement of 2400 tons of granular fill, 390 tons of blanket 
stone and 1170 tons of stone riprap. Estimated cost for 
new work is $276,000 Federal (Corps) and $92,000 non- 
Federal consisting of $91,600 cash contribution and $400 
for land. 
Local cooperation. The State of Texas is the local 
sponsor for the project. The Local Cooperation Agreement 
was executed on July 17, 1992. 
Operations during fiscal year. New Work: Plans 
and specifications were completed in April 1992. 
25. TAYLORS BAYOU, TX 
Location. Watershed of Taylors Bayou is in extreme 
southeast corner of Texas adjoining basins of Neches River 
and Sabine Lake on the east. City of Port Arthur is about 
8 miles from the main stream of Taylors Bayou. 
Existing project. Improvement consists of enlarging 
and rectifying approximately 53 miles of natural and 
artificial channels on Taylors Bayou and tributary water 
courses. Phase I consists of constructing a gated structure 
to prevent saltwater intrusion and 2.9 miles of new 
diversion channel and enlarging 1.8 miles of Gulf 
Intracoastal Waterway and a 1.9 mile section of the 
Outfall Canal. Phase II consists of enlarging 6.0 miles of 
Taylors Bayou, 14.3 miles of Hillebrandt Bayou, 1.5 miles 
of Pivitot Bayou, 2.3 miles of Bayou Din, and 3.5 miles of 
Willow Marsh Bayou. Phase III consists of enlarging 7.0 
miles of North Fork Taylors Bayou, 7.8 miles of South 
Fork Taylors Bayou and 4.4 miles of Mayhaw Bayou. The 
Phase III portion of the project was placed in the "inactive" 
category in November 1980. Initial contract on the "active" 
portion of the project was awarded in August 1982. 
Estimated cost for new work, excluding inactive portion, 
is $38,188,000 Federal (Corps) and $40,318,000 non- 
Federal, including $13,122,000 cash contribution, 
$3,648,000 lands, and $23,548,000 for relocations. (October 
1, 1992 base price.) 
Local cooperation. Section 204, 1965 Flood Control 
Act, applies. 
Operation during fiscal year. Contract for 
construction of Disposal Area 10N-B was completed at a 
fiscal year cost of $17,805. Contract for channel 
rectification of Bayou Din and Pivitot Bayou was awarded 
November 4, 1991 and continued through fiscal year 1992 
at a cost of $1,267,814. Channel rectification contract for 
Hillebrandt Bayou Station 543+50 to Station 751+00 was 
awarded January 13, 1992 and continued through fiscal 
year 1992 at a cost of $1,867,597. A contract for channel 
rectification on Willow Marsh Bayou, Stations 12+00 to 
135+00 was awarded December 12, 1991 and incurred a 
cost of $994,259 in fiscal year 1992. Construction contract 
for a water control structure at Star Lake was financially 
completed at a cost of $2,630. 
26. TEXAS CITY AND VICINITY, TX 
(HURRICANE-FLOOD 
PROTECTION) 
Location. On the west and southwest shore of 
Galveston Bay, about 9 miles northwest of Galveston, 
Texas. Project fronts on the west side of Galveston Bay 
and protects a land area of about 36 square miles. 
Existing project. Plan provides for construction of 
improvements for control of storm tides. Improvements 
consist of 15.9 miles of new levees, 1.3 miles of concrete 
floodwall, related drainage and stoplog structures, one 
tide control structure, and two pumping plants. The 
project was initiated in 1962, and physically completed 
in 1987; however, remedial measures required to 
approximately 1.7 miles of levee toe to avoid further 
erosion were made in 1990. Estimated cost for new work 
is $38,983,000 Federal (Corps) and $17,023,000 non- 
Federal, including $14,603,000 cash contribution, 
$1,071,000 work contribution, and $1,349,000 for lands, 
and $256,000 for ramps in lieu of closure structures and 
increased low flow pumping capacity for La Marque 
Pumping Plant. 
Local cooperation. Fully complied with. 
Operations during fiscal year. None required. 
31-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
27. U.S. 190 BRIDGE, SABINE RIVER, 
MERRYVILLE, LA 
Location. The project area is located about 52 miles 
north of Beaumont, Texas on the border between 
Louisiana and Texas. 
Existing project. The plan of improvement is to 
place riprap to protect the most eroded bridge piers, the 
streambed between the piers, and the eastern streambank. 
Also included was riprap protection 200 feet upstream 
and 100 feet downstream to protect the streambank from 
erosion during periods of high velocity flow. The estimated 
cost for new work is $800,000 which includes $423,000 
Federal (Corps) and $377,000 non-Federal cash 
contribution. 
Local cooperation. The local sponsor for the project 
is the State of Louisiana. Coordination is maintained with 
the Louisiana Department of Transportation and 
Development, the Texas Highway Department and the 
United States Fish and Wildlife Services. The Local 
Cooperation Agreement was executed May 31, 1991. 
Operations during fiscal year. New Work: Contract 
for erosion protection was awarded September 30, 
1991 and was completed in July 1992 for a cost of 
$607,381. 
28. VINCE AND LITTLE VINCE 
BAYOUS, TX 
Location. Watershed of Vince Bayou and tributary, 
Little Vince Bayou, has an area of about 17 square miles 
and lies entirely within Harris County. Vince Bayou is a 
minor tributary of Buffalo Bayou in San Jacinto River 
Basin on upper gulf coast of Texas. 
Existing project. Project provides for enlarging and 
rectifying channel of Vince Bayou from mouth to a point 
about 7.3 miles upstream and Little Vince Bayou from 
mouth to a point about 4.2 miles upstream, a total distance 
in both streams of about 11.5 miles. The project was 
initiated in 1968. All work on Vince Bayou is complete. 
Estimated cost for new work is $19,347,000 Federal 
(Corps) and $17,300,000 non-Federal, consisting of 
$5,100,000 for lands and $12,200,000 for relocations. 
Local cooperation. Fully complied with. 
Operations during fiscal year. None required. 
29. INSPECTION OF COMPLETED 
FLOOD CONTROL WORKS 
Inspections of completed projects operated and 
maintained by local interests were made on the following 
projects. Fiscal year cost was $212,788. 
Date of 
Project Inspection 
Brays Bayou, TX - Channel 
Rectification 
Freeport and Vicinity, TX - 
Hurricane Flood Protection 
White Oak Bayou, TX - 
Channel Rectification 
October 1991 
October 1991 
October 1991 
Lavaca and Navidad Rivers, TX 
- Flood Protection 
Highland Bayou, TX - 
Flood Control 
Vince Bayou, TX - Flood 
Protection 
Little Vince Bayou, TX - 
Flood Protection 
Big Hog Bayou, TX - 
Intake Structure 
Colorado River, TX - 
Flood Protection at 
Matagorda 
Port Arthur Hurricane 
Flood Protection, TX 
Texas City Hurricane Flood 
Protection, TX 
30. 
December 1991 
January 1992 
January 1992 
January 1992 
February 1992 
May 1992 
May 1992 
August 1992 
FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205 of 
1970 Flood Control Act, Public Law 858, 80th Congress, 
as amended: 
Construction of a flood control project at Kirbyville, 
Texas is discussed in Section 20. 
Feasibility studies continued at a fiscal year cost of 
$113,257 on the Lower Guadalupe River at Victoria, 
Texas. Funds in the amount of $118,726 were spent from 
contributed funds on the project. 
The following reconnaissance studies of flood control 
projects were completed at the fiscal year costs shown: 
Chiltipin Creek, Sinton, Texas 
City of Wharton, Texas 
Timber Lake, Montgomery County, 
Texas 
$4,361 
$15,000 
$1,276 
All of the above studies have been terminated. 
Emergency flood control - repair, flood fighting, and 
rescue work (Public Law 99, 84th Congress and antecedent 
legislation): 
Cost was $347,695 for disaster preparedness and 
$23,919 for emergency operations. National Emergency 
Preparedness Program fiscal year cost was $89,503. 
31. EMERGENCY STREAM BANK AND 
SHORELINE EROSION WORK AND 
SNAGGING AND CLEARING 
ACTIVITIES UNDER SPECIAL 
AUTHORIZATION 
Stream bank and shoreline erosion activities pursuant 
to Section 14 of the 1946 Flood Control Act, Public Law 
525, as amended: 
Construction of the erosion control project at State 
Highway Bridge 111, Lake Texana, Texas is discussed in 
Section 24. 
Construction of the erosion control project at U.S. 
190 Bridge, Sabine River, Merryville, Louisiana is 
discussed in Section 27. 
31-16

GALVESTON, TEXAS, DISTRICT 
Feasibility studies of streambank protection at Buffalo 
Bayou at Piney Point Village, Texas and Colorado County, 
Texas were completed at a fiscal year cost of $15,921 and 
$2,685 respectively. 
Snagging and clearing activities for flood control 
pursuant to Section 208 of the Flood Control Act of 1954, 
Public Law 780, as amended: 
No new feasibility studies of snagging and clearing 
activities for flood control improvements were performed 
in fiscal year 1992. 
32. PROJECT MODIFICATIONS FOR 
IMPROVEMENT OF ENVIRONMENT 
Project modifications for improvement of environment 
activities pursuant to Section 1135 of the Water Resources 
Development Act of 1986, Public Law 99-662, as amended: 
An integrated project modification report and an 
environmental assessment was completed for Salt Bayou, 
McFadden Ranch Wetlands, Texas at a fiscal year cost of 
$150,405. 
A project modification report and an environmental 
assessment was completed for the Laguna Madre Seagrass 
Restoration project, a demonstration project to plant 
seagrass in Laguna Madre, Texas. A total cost of $24,238 
was incurred for fiscal year 1992. 
General Investigations 
33. SURVEYS 
Fiscal year costs were $1,367,129 of which $4,920 
was for navigation studies; $29,007 was for flood damage 
prevention studies; $1,513 was for shoreline protection 
studies; $1,140,048 was for Review of Completed Projects; 
$3,863 was for coordination with other agencies; $75,138 
was for Special Investigations; $21,603 for Interagency 
Water Resources; $10,665 was for National Estuary 
Studies; $3,940 for the American Waterfowl Management 
Plan; and $76,432 was for Planning Assistance to States. 
Funds in the amount of $2,528 were expended from 
contributed funds for the Cameron County flood damage 
prevention study. Contributed funds in the amount of 
$7,539 were expended for the State of Texas Coastal 
Management study. 
34. PLANNING AND ENGINEERING 
Brazos Island Harbor, Texas (42-Foot Project) - The 
project will provide for enlargement of the entrance 
channel from deep water in the Gulf of Mexico to the 
Laguna Madre (approximately 2.5 miles) to a depth of 44 
feet and a width of 300 feet; enlarging 14.8 miles of the 
existing Brownsville Channel to a depth of 42 feet and 
width of 250 feet; enlargement of the Turning Basin 
Extension to a point 800 feet beyond the grain elevator to 
a depth of 42 feet at widths varying from 250 to 300 feet; 
removal of Brownsville Navigation District Wharves 5, 6, 
and 9 to permit widening of the adjacent portion of the 
Turning Basin to 1,200 feet at a depth of 36 feet. 
Estimated planning and engineering estimate is 
$2,150,000. Planning and engineering studies were 
initiated in Fiscal Year 1987. Fiscal year costs were 
$96,995. 
Channel to Victoria, Texas - The project will provide 
for enlarging the existing Channel to Victoria from a depth 
of 9 feet and width of 100 feet to a depth of 12 feet and a 
width of 125 feet, the same dimensions as the Gulf 
Intracoastal Waterway, with disposal of the dredged 
materials in upland areas. In addition, the project includes 
creation of additional marsh along the landlocked reach 
of the channel. Estimated planning and engineering 
estimate is $1,420,000. Planning and engineering studies 
were initiated in Fiscal Year 1989. Fiscal year costs were 
$505,203. 
Houston-Galveston Navigation Channels, Texas - The 
project will provide for enlargement of the Houston Ship 
Channel and Galveston Ship Channel. The recommended 
plan for the Houston Ship Channel consists of a 50-foot 
deep by 600-foot wide channel to the vicinity of the Shell 
Docks at Boggy Bayou in Houston with additional 
widening to the Clinton Island Turning Basin. The 
recommended plan for the Galveston Channel consists of 
a 50-foot deep by 450-foot wide channel within the existing 
1,125-foot channel. The 50-foot by 800-foot entrance 
channel, previously authorized with the Texas City 
Channel but unconstructed, is also incorporated into this 
project. The project will be constructed in two phases, 
with Phase I enlarging the Houston Ship Channel to 45 
by 530 feet, the Galveston Ship Channel enlarged to 45 
by 450 feet, and deepening the entrance channel to 45 
feet. Phase II will deepen both channels to 50 feet and 
widen the Houston Ship Channel to 600 feet. A locally 
preferred dredged material disposal plan for Galveston 
Bay has been incorporated with the plan of improvement. 
The plan would utilize confined or beneficial uses of 
dredged material in the bay and/or offshore disposal for 
Phase I and Phase II construction activities and the 
operations and maintenance resulting from them. 
Estimated planning and engineering estimate is 
$13,750,000. Estimated planning and engineering studies 
were initiated in Fiscal Year 1990. Fiscal year costs were 
$3,674,692, which included a contract for constructing 
submerged mounds in Galveston and Chambers Counties, 
Texas, to study experimental benthic recovery. The cost 
of the contract was $1,035,063. 
Brays Bayou, Texas - The project will provide for 3 
miles of stream improvements, 3 flood detention basins, 
and 7 miles of stream diversion channels. Aesthetic 
vegetation is included. Recreation facilities include trails, 
picnic facilities, sports fields, comfort stations and parking 
areas. Estimated planning and engineering estimate is 
$6,010,000. Planning and engineering studies were 
initiated in Fiscal Year 1990. Fiscal year costs were 
$430,265. 
Greens Bayou, Texas - The project will provide for 
25 miles of stream enlargements, 14 miles of stream 
clearing and 4 flood detention basins. Aesthetic vegetation 
and mitigation is included. Recreation facilities include 
trails, picnic facilities, sports fields, launches, ramps, 
comfort stations and parking areas. Estimated planning 
and engineering estimate is $3,940,000. Planning and 
engineering studies were initiated in Fiscal Year 1990. 
Fiscal year costs were $567,116. 
31-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Cypress Creek, Texas - The project will provide for 
enlargement of the lower 29.4 miles of the channel. 
Project-oriented recreation features include 11.5 miles of 
hike-and-bike trails and related recreation facilities, 
habitat management measures on 844 acres of Harris 
County Parkway project land, creation of wooded and 
brush habitat along 100 acres of project right-of-way, 
acquisition of 329 acres of wildlife habitat, and creation 
of 35 acres of ponds and marshes. Estimated planning 
and engineering estimate is $7,800,000. Planning and 
engineering studies were initiated in Fiscal Year 1990. 
Fiscal year costs were $216,496. 
Arroyo Colorado, Texas - The project will provide 
flood protection along Highway 83 and erosion protection 
for the banks of the Arroyo Colorado in the city of 
Harlingen. The project consists of a gated water control 
structure, 1.4 miles of channel improvements, and stone 
armoring of selected reaches in Harlingen. Estimated 
planning and engineering estimate is $1,000,000. Planning 
and engineering studies were initiated in Fiscal Year 1990. 
Fiscal year costs were $495,282. 
South Main Channel, Texas - The project consists of 
channel improvements which will provide flood protection 
to the cities of McAllen, Edinburg, Edcouch, La Villa and 
Lyford, as well as the rural areas of Hidalgo and Willacy 
Counties north of U.S. Highway 83. Estimated planning 
and engineering estimate is $2,880,000. Planning and 
engineering studies were initiated in Fiscal Year 1990. 
Fiscal year costs were $131,083. 
Falfurrias, Texas - The project consists of a levee 
and pilot channel to divert Standard Project Flood flows 
in Palo Blanco and Cibolo Creeks around the west side of 
Falfurrias to Baluarte Creek. Major plan elements include 
water control structures in Palo Blanco and Cibol Creeks, 
a 5.6-mile long diversion levee, a 1.8-mile long pilot 
channel, flowage easements on 11,000 acres of land and 
0.8 mile of ring levee around the sewage treatment plant. 
Estimated planning and engineering estimate is $690,000. 
Planning and engineering studies were initiated in Fiscal 
Year 1990. Fiscal year costs were $425. 
Sargent Beach, Texas - The project consists of 
construction of approximately 8 miles of concrete-block 
revetment with two concrete sheetpile wall segments and 
tow protection on the barrier between a 10-mile reach of 
the Gulf Intracoastal Waterway in the vicinity of Sargent, 
Texas and the Gulf of Mexico. Estimated planning and 
engineering estimate is $2,260,000. Planning and 
engineering studies were initiated in Fiscal Year 1992. 
Fiscal year costs were $517,373. 
35. COLLECTION AND STUDY OF 
BASIC DATA 
Flood plain management, technical services and quick 
responses were performed at a cost of $10,394, $39,797 
and $2,976, respectively. 
Hydrologic studies cost $6,975. 
31-18

GALVESTON, TEXAS, DISTRICT 
TABLE 31-A COST AND FINANCIAL STATEMENT 
SS
ee 
ection 
in Text Project 
1. Aquatic Plant Control 
(Southwestern Division) 
1965 Act 
2. Brazos Island Harbor, 
TX 
3. Channel to Port 
Bolivar, TX 
4. Corpus Christi Ship 
Channel, TX 
(Regular Funds) 
(Contributed Funds) 
5. Freeport Harbor, TX 
6. Galveston Harbor and 
Channel, TX 
7. Gulf Intracoastal 
Waterway between 
Apalachee Bay, FL and 
the Mexican Border 
(Galveston District) 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Minor Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
Minor Rehab: 
Approp. 
Cost 
31-19 
Total Cost To 
FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992" 
280,000 296,000 232,500 235,000 3,681,6001 
377,075 301,148 229,030 209,979 3,571,0611 
500,000 742,000 315,000 1,971,000 15,978,5022 
376,918 831,456 305,088 1,887,976 15,798,2452 
1,598,700 2,009,715 1,337,400 2,267,000 47,740,4763 
1,711,336 1,961,671 1,077,977 2,571,235 47,737,2383 
- - - - 2,170,080 
- - - - 2,170,080 
- - - - 133,9254 
- - - - 133,9254 
- - 62,000 (-)10,400 1,225,5015 
- (-)180 51,707 - 1,225,4195 
6,441,000 - (-)100,000 - 76,535,3596 
7,018,984 790,564 56,878 28,046 76,499,8616 
2,692,300 1,775,990 2,007,100 5,110,000 97,366,7487 
2,704,984 1,759,261 1,642,951 5,481,015 97,347,2267 
- - - - 3,576,684 
- - - - 3,576,684 
948,000 - - - 6,279,088 
858,215 66,190 - - 5,959,162 
9,758,000 7,924,000 10,140,000 13,534,000 52,432,1528 
3,556,541 11,764,019 12,707,229 13,967,880 52,133,6558 
3,400,400 49,700 297,000 1,095,000 51,580,4159 
3,403,677 44,541 301,318 958,033 51,440,8469 
- - - - 8,935 
- - - - 8,935 
- - - - 29,096,39210 
- - - - 29,096,39210 
2,515,000 3,229,365 3,846,000 279,000 90,458,088"1 
2,540,953 3,130,578 3,933,178 270,875 90,425,43611 
- - - - 7,969,329 
- - - - 7,969,329 
5,339,000 4,636,000 1,279,000 2,557,000 78,195,30312 
4,953,438 4,286,153 2,127,947 2,565,623 77,974,63112 
15,842,600 10,723,994 25,255,600 23,302,700 295,740,94213 
15,954,354 9,852,912 24,499,694 24,079,198 294,661,63214 
- - - - 434,638 
- - - - 434,638 
- - - - 835,873 
- - - - 835,873

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
in Text Project 
8. Houston Ship Channel, 
TX 
(Regular Funds) 
9. Matagorda, Ship 
Channel, TX 
(Regular Funds) 
10. Sabine-Neches 
Waterway, TX 
(Regular Funds) 
11. Texas City Channel, TX 
12. Trinity River and 
Tributaries, TX (Includes 
Wallisville) 
15. Corpus Christi Beach, 
TX (Restoration Project) 
(Contributed Funds) 
16. Buffalo Bayou and 
Tributaries, TX 
17. Clear Creek, TX 
(Contributed Funds) 
Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 19922 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Recreation: 
Approp. 
Cost 
Maint: 
Approp. 
Cost 
Major Rehab: 
Approp. 
Cost 
Dam Safety: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
5,807,400 
6,258,038 
2,668,600 
2,691,027 
2,191,200 
2,215,722 
169,500 
193,258 
25,900 
38,062 
78,000 
26,757 
426,400 
395,234 
79,360 
(-)12,151 
1,291,000 
1,288,343 
1,587,000 
725,846 
1,700,000 
2,394,973 
100,000 
28,723 
31-20 
- - - 35,760,38215 
- - - 35,760,38215 
9,231,155 6,190,000 2,380,500 131,727,77816 
9,047,821 6,457,007 2,311,819 131,649,81216 
- - - 18,058,77717 
- - - 18,058,77717 
1,027,350 425,300 2,364,200 46,168,738 
1,040,131 399,742 2,393,060 46,166,943 
- - - 56,136,81518 
- - - 56,136,81518 
3,716,320 15,507,600 4,952,000 170,835,54019 
3,701,954 14,305,233 5,893,587 170,553,46419 
- - - 15,131,97220 
2,346 2,761 - 15,131,97220 
867,050 - 201,000 24,682,51121 
860,271 5,315 166,220 24,644,89921 
- - - 726,158 
- - - 726,158 
3,944,000 - - 33,223,67622 
299,842 214,608 2,257,188 31,932,34422 
2,030,711 710,000 795,000 15,222,01423 
1,865,559 841,233 819,140 15,155,60023 
- - - 2,120,641 
20,914 - - 2,120,641 
- - - 2,038,345 
- - - 2,009,710 
928,000 756,000 1,249,100 60,139,42424 
629,956 713,744 1,018,131 59,568,15524 
- - - 377,804 
7,605 333 11,500 377,623 
1,233,702 1,077,000 1,642,000 24,904,115 
1,215,140 1,035,815 1,678,401 24,788,241 
- - - 12,475,000 
- - - 12,475,000 
166,000 193,000 1,450,000 12,773,000 
699,348 810,185 1,449,168 12,687,903 
3,000,000 1,182,000 460,000 12,862,361 
2,801,151 1,954,817 758,300 12,672,721 
- 140,000 - 640,000 
159,673 120,200 - 618,596

GALVESTON, TEXAS, DISTRICT 
TABLE 31-A COST AND FINANCIAL STATEMENT 
SE 
in
ee 
ection 
Text Project 
18. Cypress Creek, TX 
19. Falfurrias, TX 
20. Kirbyville, TX 
(Regular Funds) 
(Contributed Funds) 
21. Lower Rio Grande 
Basin, TX 
22. Port Arthur and 
Vicinity, TX Hurricane- 
Flood Protection 
(Regular Funds) 
(Contributed Funds) 
23. Sims Bayou, TX 
24. State Highway 111 
Bridge, Lake Texana, 
TX 
25. Taylors Bayou, TX 
(Regular Funds) 
(Contributed Funds) 
26. Texas City and 
Vicinity, TX Hurricane- 
Flood Protection 
(Regular Funds) 
(Contributed Funds) 
27. U.S. 190 Bridge, 
Sabine River, 
Merryville, LA 
28. Vince and Little Vince 
Bayous, TX 
Funding 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost. 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Total Cost To 
FY 89 FY 90 FY 91 FY 92 Sep. 30, 19922 
935,00 
123,92 
90,00 
11,38 
150,00 
67,47 
22,25 
605,00 
728,07 
12,0( 
8,74 
2,763,0( 
2,712,0' 
735,0( 
870,7( 
70,0( 
65,5 
26,0( 
21,4 
20,0( 
1 9 , 7 
61,0( 
288,81 
214,000 564,000 
127,009 473,731 
171,000 (-)67,000 
95,343 7,686 
- 30,000 
711,902 200,759 
31 64,272 
- 175,000 
- 167,567 
)0 - 
73 71,628 
56 22,935 
)0 1,158,000 
79 917,100 
D0 - 
[4 4,056 
)0 2,942,000 
71 3,314,535 
)0 1,275,000 
)3 1,316,854 
00 930,000 
12 863,748 
DO 150,000 
55 133,823 
00 49,000 
76 22,491 
)O (-)16,000 
80 5,645 
14,347 
341,000 
283,803 
56,644 
2,164 
3,047,000 
3,193,103 
27,000 
20,486 
750,000 
216,496 
424 
26,198 
5,984 
726,900 
626,365 
96,000 
77,157 
41,000 
32,850 
1,190,000 
1,301,424 
9,000 
7,131 
1,091,000 2,903,000 
1,184,924 3,158,775 
- 1,491,000 
155,027 1,798,713 
(-)35,000 (-)56,000 
13,607 (-)14,073 
5,831 
423,000 
33,216 
(-)24,000 
38,127 
- 14,401,10027 
14,073 14,396,30727 
- 492,000 
411,638 487,12128 
- 19,307,100 
- 19,307,100 
1 Excludes $1,272,098 credit for contributed work. 
2 Includes $675,855 for previous projects. In addition, 
$3,971,702 expended from contributed funds, of which 
$123,361 was for previous projects. 
3 In addition, $1,352,092 expended from contributed 
funds. 
4 Includes $48,711 for previous projects. 
s Includes $46,101 for previous projects. 
6 Includes $1,372,534 for previous projects. Includes 
$456,515 for Sec. 107 project for Port Aransas Breakwaters. 
In addition $768 expended from contributed funds for Port 
Aransas Breakwaters. 
7 Includes $62,452 for previous projects. In addition, 
$647,922 expended from contributed funds. 
8 Includes $147,098 for previous projects. In addition, 
$17,903,141 expended from contributed funds. ($581,615 
on 45' project.) 
s In addition, $229,311 expended from contributed 
funds. 
toI0n cludes $8,421,996 for previous projects. In addition, 
$3,648,932 expended from contributed funds. 
11 Includes $86,126 for previous projects. In addition, 
$2,122,583 expended from contributed funds. 
31-21 
1,528,000 
817,236 
104,000 
103,453 
1,488,000 
1,462,615 
95,984 
90,000 
1,242,900 
1,077,735 
59,998,509 
59,968,482 
16,332,97525 
16,322,63625 
7,785,000 
7,759,25026 
58,000 
49,566 
31,666,198 
31,192,532 
9,800,000 
9,700,240 
38,891,400 
38,882,087 
)0 
I1 
-n

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-A COST AND FINANCIAL STATEMENT 
12 Includes $706,709 for previous projects. Includes 
Sec. 107 projects for Port Isabel Small Boat Basin ($46,559); 
Port Isabel Side Channel ($8,414); Offatts Bayou ($356,466); 
and Channel to Aransas Pass ($658,573). In addition contributed 
funds expended for Port Isabel Small Boat Basin 
($46,559); Offatts Bayou ($49,665); Channel to Aransas Pass 
($347,950); Chocolate Bayou ($658,310); and Mouth of Colorado 
River ($3,340,601). 
13 Includes $1,526,564 for previous projects. In addition 
$22,672 expended from contributed funds. Includes 
following amounts for tributary channels separately funded 
starting in fiscal year 1987: Channel to Victoria $5,513,680. 
Channel to Aransas Pass $2,600. Chocolate Bayou Channel 
$1,091,500. Includes following amounts for tributary channels 
separately funded starting in fiscal year 1989: Channel 
to Harlingen $2,663,150. Channel to Port Mansfield 
$2,753,785. Starting in fiscal year 1990 includes Channel to 
Red Bluff $802,700. Also includes $460,000 for Mouth of 
Colorado River, separately funded beginning in fiscal year 
1992. 
14 Includes $1,526,564 for previous projects. In addition 
$22,672 expended from contributed funds. Includes 
following amounts for tributary channels separately funded 
starting in fiscal year 1987: Channel to Victoria $5,511,143, 
Channel to Aransas Pass $2,600, Chocolate Bayou Channel 
$1,091,500. In addition $566,875 was expended from contributed 
funds for Chocolate Bayou Channel. Also includes 
amounts for tributary channels separately funded starting 
in fiscal year 1989: Channel to Harlingen $2,543,389. Channel 
to Port Mansfield $2,695,424. Includes funds in the 
amount of $767,173 expended for Channel to Red Bluff, separately 
funded in fiscal year 1990. Also includes an expended 
amount of $344,219 for Mouth of Colorado River, separately 
funded in fiscal year 1992. 
15 Includes $4,105,157 for previous projects. In addition, 
$2,591,939 expended from contributed funds, of which 
$1,209,179 was for previous projects. 
16 Includes $1,213,142 for previous projects. In addition, 
$534,641 expended from contributed funds, of which 
$200,000 was for previous projects. Includes appropriated 
funds for tributary channels separately funded starting in 
fiscal year 1992: Greens Bayou Channel $31,000. Barbour 
Terminal Channel $22,500. Bayport Ship Channel $94,000. 
Expenditures for tributary channels separately funded starting 
in fiscal year 1992: Greens Bayou Channel $17,706. 
Barbour Terminal Channel $6,244. Bayport Ship Channel 
$60,021. 
17 In addition, $12,259,619 expended from contributed 
funds and $182,800 for contributed lands. 
18 Includes $5,180,832 for previous projects. In addition, 
$2,680,942 expended from contributed funds, of which 
$577,507 was for previous projects. 
19 Includes $2,379,677 for previous projects. In addition, 
$3,660,026 expended from contributed funds. 
20 Includes $366,823 for previous projects. In addition, 
$1,023,819 expended from contributed funds, of which 
$99,000 was for mitigation measures. 
21 Includes $195,083 for previous projects. 
22 Includes $1,966,306 for previous projects. In addition, 
$66,000 expended from contributed funds. 
23 Includes $543,662 for previous projects. 
24 Includes $4,400,000 of advanced funds repaid to 
Harris County Flood Control District. In addition, $63,661 
contributed funds expended for Brays Bayou and $12,900 
Federal funds and $19,104 contributed funds expended for 
enlargement of Clodine Ditch. 
25 Excludes $3,402,588 estimated value of contributed 
lands, $6,168,360 for relocations, and $217,000 credit 
given local sponsor for work-in-kind. 
26 Excludes $53,484 expended from contributed funds 
for real estate acquisition for the local sponsor. 
27 Excludes $1,349,069 estimated value of contributed 
lands and $1,070,959 credit given local sponsor for workin-
kind. 
28 Excludes $245,382 expended from contributed 
funds. 
29 Includes funds ($12,544,400) provided by the Jobs 
Act (P.L. 98-8, dated March 24, 1983) for projects listed in 
Table 15-I of Annual Report for 1985. 
31-22

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 27, 1965 
Nov. 17, 1986 
Jun. 3, 1930 
May 24, 1934 
(PWA) 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 24, 1946 
May 17, 1950 
Jul. 14, 1960 
Nov. 17, 1986 
AQUATIC PLANT CONTROL 
Provides for control of progressive eradication of aquatic 
plant growth from the navigable waters and streams 
in the U.S. 
Amended cost sharing requirements to provide for 50 percent 
Federal and 50 percent non-Federal participation 
in control operations. 
BRAZOS ISLAND HARBOR, TX 
Jetties and jetty channel, inside channels and basins. 
Local cooperation requirement modified to provide contribution 
of funds to cover cost of original dredging of 
all inside channels and basins. 
Deepen jetty channel to 31 feet and inner channels and 
Brownsville and Port Isabel turning basins to 28 feet. 
Enlarge Port Isabel turning basin. 
Deepen entrance channel to 35 feet; deepen to 33 feet 
channel across Laguna Madre; deepen to 32 feet channels 
from Laguna Madre to turning basins at 
Brownsville and Port Isabel; widen turning basins; and 
dredging present shallow-draft channel south of Port 
Isabel from railroad bridge to Laguna Madre and connecting 
channel to Port Isabel turning basin. 
Additional connecting channel between Port Isabel and 
Brownsville channels; and transfer shallow-draft channels 
at Port Isabel to GIWW. 
Deepen to 38 feet in outer bar channels and 36 feet in all 
other authorized channels and basins; extend existing 
turning basins at Brownsville and Port Isabel; and 
construct small-boat basin with a connecting channel 
next to Brownsville ship channel. 
Widen Brownsville Channel to 300 feet at a depth of 36 
feet from former Goose Island passing basin to turning 
basin extension, thence at a width of 500 feet and 
same depth to turning basin proper, deepen to 36 feet 
in area in southeast corner of turning basin, maintain 
two existing basins of fishing harbor, and a connecting 
channel, and construct a third basin, with necessary 
connecting channel and extend Brazos Island Harbor 
north jetty seaward 1,000 feet.27 
Enlargement of the entrance channel from deep water in 
the Gulf of Mexico to the Laguna Madre to a depth of 
44 feet and a width of 400 feet; enlargement of the 
Turning Basin Extension to a point 800 feet beyond 
the grain elevator to a depth of 42 feet at widths varying 
from 325 to 400 feet; removal of Brownsville Navigation 
District Wharves 5, 6, and 9 to permit widening 
of the adjacent portion of the Turning Basin to 1,200 
feet at a depth of 36 feet; construction of asphalt walkways 
with handrails on the crown of the North and 
South Jetties, and construction of park-type public use 
facilities at the inner end of the North Jetty. 
H. Doc. 251, 89th Cong., 
1st Sess. 
Sec. 103(c), PL 99-662 
Rivers and Harbors 
Committee Doc. 16, 
71st Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 10, 
71st Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 32, 
75th Cong., 1st Sess. 
H. Doc. 335, 76th Cong., 
1st Sess. 
H. Doc. 347, 77th Cong., 
1st Sess. 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 192, 81st Cong., 
1st Sess. 
H. Doc. 428, 86th Cong., 
2nd Sess.1 
Sec. 201, PL 99-662 
31-23 
TABLE 31-B 
2.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B 
See Date 
Section Authorizing 
in Text Act 
3. Jun. 25, 1910 
Mar. 4, 1919 
4. Mar. 3, 1899 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 19132 
Sep. 23, 1922 
Jul. 3, 19303 
Jul. 3, 1930 
Aug. 30, 19354 
Aug. 30, 1935 
Aug. 30, 1935 
Aug 30, 1935 
Jun. 20, 1938 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
CHANNEL TO PORT BOLIVAR, TX 
A channel 30 feet deep and 200 feet wide from deep water 
in Galveston Harbor extending to a turning basin 
1,000 feet square and 30 feet deep.31 
Enlargement, extension and protection of turning basin.3' 
CORPUS CHRISTI SHIP CHANNEL, TX 
Acquisition of old curvey portion of north jetty previously 
constructed by private parties. 
Complete north jetty in accordance with builder's plans. 
Complete north jetty in accordance with builder's plans. 
Connect old curve to St. Joseph Island, and construct 
south jetty. 
Dredge roadstead in Harbor Island Basin to 20 feet deep 
and construct 10,000 linear feet of stone dike on St. 
Joseph Island. 
Channel between jetties and Harbor Island Basin to 25 
feet deep, extend jetties seaward, extend dike on St. 
Joseph Island 9,100 feet, and dredge approach channel 
12 feet deep to town of Port Aransas. 
Dredging channel from Aransas Pass to Corpus Christi, 
25 feet deep, 200 feet bottom width. 
Deepen entrance channel from gulf to Harbor Island and 
provide an inner basin at Harbor Island of reduced 
area but greater depth. 
Channel from Aransas Pass to Corpus Christi Channel 
with depth 30 feet. 
Enlarge all channels from gulf to western end of basin 
dredge by Humble Oil and Refining Co., at its docks 
on Harbor Island. 
Maintain channel and maneuvering basin between breakwater 
and western shoreline of Corpus Christi Bay. 
Maintain 30-foot depth of approach channel, turning basin 
at Corpus Christi, Industrial Canal and turning 
basin at Avery Point. 
Maintain and deepen to 32 feet channel from deep water 
at Port Aransas to and including turning basin at 
Corpus Christi. 
Extend main turning basin at Corpus Christi westward 
2,500 feet at its present width and depth, deepen existing 
Industrial Canal and turning basin to 32 feet 
and extend this canal at a depth of 32 feet and general 
width of 150 feet, westward along Nueces Bay shore to 
a turning basin 32 feet by 900 feet, and 1,000 feet long 
near Tule Lake. 
Documents 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1122, 65th Cong., 
2nd Sess.' 
Specified in Act. 
Specified in Act. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 5, 
59th Cong., 2nd Sess. 
H. Doc. 1094, 61st Cong., 
3rd Sess. 
H. Doc. 1125, 62nd Cong., 
3rd Sess. 
H. Doc. 321, 67th Cong., 
2nd Sess. 
H. Doc. 214, 70th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 9, 
71st Cong., 1st Sess. 
Committee Does. 35, 72nd 
Cong., 1st Sess., and 40, 
73rd Cong., 2nd Sess. 
H. Doc. 130, 72nd Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 13, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 63, 
74th Cong., 1st Sess. 
H. Doc. 574, 75th Cong., 
3rd Sess. 
31-24

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1945 
Jun. 30, 1948 
Sep. 3, 1954 
Sep. 3, 19545 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 3, 1958 
Jul. 14, 1960 
(As amended by 
Dec. 31, 1970) 
Aug. 13, 1968 
Provide depth of 34 feet in all project channels and basins 
from Port Aransas to and including Tule Lake 
turning basin, for a width of 250 feet from Port Aransas 
to breakwater at Corpus Christi, for a width of 200 
feet in Industrial Canal and in channel between Avery 
Point and Tule Lake turning basins, and widen Avery 
Point turning basin to 1,000 feet. 
Deepen entrance channel to 38 feet from gulf to outer 
end of jetty; 38 feet decreasing to 36 feet thence to 
station 90 north jetty; and 36 feet in all other deep 
water channels and basins except 2,000-foot undredged 
part of inner basin at Harbor Island, and a width of 
400 feet in channel from Port Aransas to Maneuvering 
basin at Corpus Christi. 
An anchorage basin 12 feet deep, from 300 to 400 feet wide, 
and 900 feet long in Turtle Cove at Port Aransas, Texas. 
Branch channel 32 feet by 150 feet, extending northerly 
from main channel in vicinity of Port Ingleside, along 
north shore of Corpus Christi Bay to Reynolds Metals 
Co. plant and turning basin 32 feet deep and 800 feet 
square near plant in general vicinity of LaQuinta, 
Texas. 
An entrance channel 36 by 400 feet on a tangent alignment 
from 400-foot channel in Corpus Christi Bay, 
near Corpus Christi breakwater to flared approach 
channel to Corpus Christi turning basin. 
Deepen and widen LaQuinta Channel to 36 by 200 feet; 
enlarge LaQuinta turning basin to 36 by 800 by 1,000 
feet; a flared entrance to channel; and widening at 
curves. 
Deepen entrance channel to 42 feet from gulf to outer 
end of jetty; 40 feet in all other deep-water channels 
and basins except undredged northward extension to 
inner basin at Harbor Island and branch channel to 
LaQuinta; and widen Industrial Channel to 400 feet 
with flared entrances to Corpus Christi and Avery Point 
turning basins. 
Channel 40 by 200 feet extending 2.2 miles from Tule 
Lake turning basin to a turning basin 40 feet deep, 
700 to 900 feet wide, 1,000 feet long at Viola, Texas. 
Depth of 12 feet and a width of 100 feet in locally dredged 
Jewel Fulton Canal from LaQuinta Channel to a turning 
basin 12 by 200 by 400 feet, and assumption of 
maintenance by United States. 
Construction of a breakwater at entrance to harbor area 
at Port Aransas, and realignment of existing 12-foot 
by 100-foot project channel. 
Provides for a project depth of 45 feet in the existing 
deep-draft channels and basins, for construction of a 
new deep-draft turning point, for construction of a deep 
draft mooring area and mooring facilities and for widening 
of the channels and basins at certain locations. 
The Act also deauthorized the undredged northward 
extension of Inner Basin at Harbor Island and the 
undredged west turnout (Wye connection) between the 
LaQuinta Channel and the main channel of the waterway. 
H. Doc. 544, 78th Cong., 
2nd Sess. 
H. Doc. 560, 80th Cong., 
2nd Sess. 
H. Doc. 654, 81st Cong., 
1st Sess. 
H. Doc. 89, 83rd Cong., 
1st Sess. 
H. Doc. 487, 83rd Cong., 
2nd Sess. 
S. Doc. 33, 85th Cong., 
1st Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
H. Doc. 361, 85th Cong., 
2nd Sess. 
Sec. 107, PL 86-645 
S. Doc. 99, 90th Cong., 
2nd Sess.' 
31-25 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 22, 1976 
Mar. 3, 1899 
Mar. 2, 1907 
Feb. 27, 1911 
Mar. 4, 1913 
Aug. 8, 1917 
Mar. 3, 19256 
Jul. 3, 1930 
Aug. 30, 19357 
Aug. 30, 1935 
May 17, 1950 
Jul. 3, 1958 
Oct. 5, 1961 
Dec. 31, 1970 
Nov. 17, 1986 
Modified local cooperation requirements for 1968 Act. 
Shifted responsibility for cost of disposal areas and 
confinement works from sponsor to joint 75 percent 
Federal and 25 percent non-Federal responsibility. 
FREEPORT HARBOR, TX 
Dredging and other work necessary in judgment of 
Secretary of War for improving harbor; for taking over 
jetties and privately built works at mouth of river. 
Examination authorized. Work later confined to maintenance 
of jetties. 
Repairs to jetties and dredging. 
Construct seagoing hopper dredge. 
Purchase of one 15-inch pipeline dredge and equipment, 
its operation of 3 years, operation of seagoing dredge 
one-half time for 3 years, and repairs to jetties. 
Diversion dam, diversion channel, and necessary auxiliary 
works. 
Maintenance of diversion channel at expense of local interest. 
Deepening channels and basins. 
Maintenance of present project dimensions of channels 
and basins at Federal expense. 
Deepen outer bar channel to 38 feet from gulf to a point 
within jetties, thence 36 feet in authorized channels to 
and including upper turning basin. 
Relocate outer bar channel on straight alignment with 
jetty channel and maintain Brazos Harbor entrance 
channel and turning basin (constructed by local 
interests). 
Modification of HD 1469. Revoking certain provisions of 
local cooperation. 
Relocation of entrance channel and deepen to 47 feet; 
enlargement to a depth of 45 feet and relocation of 
jetty channel and inside main channel; deepening to 
45 feet of channel to Brazosport; enlargement of the 
widened area of Quintana Point to provide a depth of 
45 feet with a 750-foot diameter turning area; 
Brazosport turning basin to 45 feet deep with a 1,000 
foot turning area; a new turning basin with a 1,200 
foot diameter turning area and 45 feet deep; deepening 
Brazosport channel to 36 by 750 feet diameter; 
flared approaches from Brazos Harbor Channel; relocation 
of north jetty and rehabilitation of south jetty. 
Modified local cooperation requirements for the 1970 Act. 
Sec. 124, PL 94-587 
Specified in Act. 
H. Doc. 1087, 60th Cong., 
2nd Sess. 
Specified in Act. 
Specified in Act. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 10, 
68th Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 18, 
70th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 15, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Does. 15, 
72nd Cong., 1st Sess., 
and 29, 73rd Cong., 
2nd Sess. 
H. Doc. 195, 81st Cong., 
1st Sess. 
H, Doc. 433, 84th Cong., 
2nd Sess. 
H. Doc. 289, 93rd Cong., 
2nd Sess.2 
Sec. 101, PL 99-662 
31-26 
PL 394, 87th Cong.

GALVESTON, TEXAS, DISTRICT 
TABLE 31-B 
See Date 
Section Authorizing 
in Text Act 
6. Aug. 5, 1886 
Jun. 13, 1902 
Mar. 3, 1905 
Mar. 2, 1907 
Mar. 2, 1907 
Jun. 25, 19109 
Jul. 27, 1916 
Jul. 18, 1918 
Sep. 22, 1922 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 30, 1935 
Apr. 4, 1938 
Jun. 30, 1948 
May 17, 1950 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
GALVESTON HARBOR AND CHANNEL, TX 
Construct 2 rubblestone jetties at entrance to Galveston 
Harbor. 
A channel 1,200 by 30 feet from Bolivar Roads (outer end 
of old inner bar near Fort Point) at 51st Street.8 
Purchase or construct hydraulic pipeline dredge. 
Extension of jetties to present project length and construction 
and operation of a dredge. 
Extension of Galveston Channel from 51st to 57th Sts., 
with depth of 30 feet and width of 700 feet. 
Conditional extension of Galveston Channel between 51st 
and 57th Sts., 30 feet deep and 1,000 feet wide. 
Extend seawall at Galveston from angle at 6th St., and 
Broadway to vicinity of Fort San Jacinto. 
Deepen harbor channel to 35 feet and widen to 800 feet. 
Further extension of seawall at Galveston to a junction 
with south jetty; and repairing seawall in front of Fort 
Crockett reservation. 
Deepen Galveston Channel to 32 feet; and maintain 
Galveston Harbor channels to dimensions of 800 feet 
wide, 35 feet deep on outer bar and 34 feet deep in 
inner bar.10 
Maintain State Highway Ferry Landing Channels to dimensions 
of 12 by 100 feet. 
Construct 13 groins along gulf shore from 12th to 61st 
Sts. in city of Galveston at a limited cost of $234,000 
(10 groins constructed). 
Deepen Galveston Channel to 34 feet (Bolivar Roads to 
43rd St.). 
Deepen Galveston entrance channel to 36 feet. 
Completion of project for construction of 13 groins. 
Deepen Galveston Harbor to 38 feet from gulf to a point 2 
miles west of seaward end of north jetty; thence 36 
feet to Bolivar Roads; revoking authority for maintenance 
of ferry channels; and Galveston channel to 36 
feet deep from Bolivar Roads to 43rd Street. 
Deepen outer bar channel to 38 feet from gulf to a point 
within jetties, thence 36 feet in authorized channels to 
and including upper turning basin. 
Documents 
H. Doc. 85, 49th Cong., 1st 
Sess., and Annual 
Report, 1886, p. 1311. 
H. Doc. 264, 56th Cong., 
2nd Sess. 
Specified in Act. 
H. Doc. 340, 59th Cong., 2nd 
Sess., and Rivers and 
Harbors Committee Doc. 
11, 59th Cong., 2nd Sess. 
H. Doc. 768, 59th Cong., 
2nd Sess. 
H. Doc. 328, 61st Cong., 
2nd Sess. 
H. Doc. 1390, 62nd Cong., 
3rd Sess. 
H. Doc 758, 65th Cong., 
2nd Sess. 
H. Doc. 693, 66th Cong., 
2nd Sess. 
H. Doc. 307, 69th Cong., 
1st Sess. 
River and Harbors 
Committee Doc. 31, 
72nd Cong., 1st Sess. 
H. Doc. 400, 73rd Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 61, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 57, 
74th Cong., 1st Sess. 
PL 463, 75th Cong. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 195, 81st Cong., 
1st Sess. 
31-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B AUTHORIZING LEGISLATION 
See 
Section 
in Text 
Date 
Authorizing 
Act 
Jul. 3, 1958 
Jun. 23, 1971 
(House Res.) 
Nov. 18, 1971 
(Senate Res.) 
7. Mar. 2, 1907 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 26, 1937 
Jun. 20, 193813 
Jun. 20, 1938 
Jun. 20, 1938 
Jun. 20, 1938 
Jun. 20, 1938 
Mar. 23, 1939 
Jul. 23, 1942 
Mar. 2, 1945 
Mar. 2, 19459 
Mar. 2, 1945 
Mar. 2, 1945 
Mar. 2, 1945"1 
31-28 
Project and Work Authorized --- 
Relocate outer bar channel on straight alignment with 
jetty channel and maintain Brazos Harbor entrance 
channel and turning basin (constructed by local 
interests). 
Deepen Galveston Channel to 40 feet from Bolivar to 
43rd Street. 
GULF INTRACOASTAL WATERWAY BETWEEN 
APALACHEE BAY, FL AND MEXICAN BORDER'2 
Channel 4 by 100 feet from West Galveston Bay across 
Chocolate Bay to 4 feet of water in Chocolate Bay. 
Channel 9 by 100 feet, Sabine River to Galveston Bay, 
and a 20-inch pipeline dredge. Such passing places, 
widening at bends, locks or guard locks and railway 
bridges over artificial cuts as are necessary. 
Channel 9 by 100 feet, Galveston Bay to Corpus Christi. 
Maintenance of a flood-discharge channel in Colorado 
River. 
Channel 9 by 100 feet in San Bernard River, Texas. 
Channel in Colorado River, 9 by 100 feet, with basin. 
Channel 9 by 100 feet from Palacios through Trepalacios 
and Matagorda Bays. 
Channel 9 by 200 feet from main channel to harbor at 
Rockport and improve harbor to 9-foot depth. 
Channel 6 by 100 feet from main channel to Aransas 
Pass, Texas. 
Enlarge waterway to depth of 12 feet and a width of 125 
feet from Sabine River to Corpus Christi. 
Enlarge waterway from Corpus Christi to vicinity of Mexican 
border to provide a depth of 12 feet and width of 
125 feet throughout. 
Channel 6 by 60 feet from GIWW to a point in Chocolate 
Bayou near Liverpool. 
Channel 6 feet deep and 60 feet wide from main channel 
near Port O'Connor, Texas, in Barroom Bay. 
Enlarge channel from main channel to Aransas Pass, 
Texas, providing a depth of 9 feet and width of 100 
feet. 
Channel 12 by 125 feet from main channel to Red Fish 
Landing, Texas, with basin. 
Channel 12 feet deep and 125 feet wide from main channel 
to vicinity of Harlingen, Texas, via Arroyo Colorado 
with basin. 
Documents 
H. Doc. 433, 84th Cong., 
2nd Sess. 
H. Doc. 121, 92nd Cong. 
H. Doc 445, 56th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
H. Doc. 238, 68th Cong., 
1st Sess. 
S. Committee print, 
75th Cong., 1st Sess. 
H. Doc. 640, 75th Cong., 
3rd Sess. 
H. Doc. 642, 75th Cong., 
3rd Sess. 
H. Doc. 564, 75th Cong., 
3rd Sess. 
H. Doc. 641, 75th Cong., 
3rd Sess. 
H. Doc. 643, 75th Cong., 
3rd Sess. 
H. Doc. 230, 76th Cong., 
1st Sess. 
PL 675, 77th Cong. 
H. Doc. 337, 76th Cong., 
1st Sess. 
H. Doc. 428, 76th Cong., 
1st Sess. 
H. Doc. 383, 77th Cong., 
1st Sess. 
S. Doc 248, 78th Cong., 
2nd Sess. 
H. Doc. 402, 77th Cong., 
1st Sess. (See PL 14, 
79th Cong.) 
.

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 24, 1946 
Jul. 24, 1946 
May 17, 1950 
May 17, 1950 
May 17, 1950 
Jul. 12, 1952 
Sep. 3, 195415 
Sep. 3, 1954 
Sep. 9, 1959 
Jul. 14, 1960 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Jul. 14, 1960 
(As amended 
Dec. 31, 1970) 
Fill a portion of shallow-draft channel adjacent to Port 
Isabel Turning Basin, construct a channel to connect 
shallow-draft channel with main channel near shoreline 
of Laguna Madre, and enlarge shallow-draft channel 
west of this connection, all to 12-foot depth and bottom 
width of 125 feet. 
Reroute main channel to north shore of Red Fish Bay 
between Aransas Bay and Corpus Christi Bay; deepen 
tributary channel from Port Aransas to Aransas Pass, 
Texas, 12 feet and extended basin at same depth. 
Deauthorized 6 by 60 foot channel in Chocolate Bayou 
and reauthorized the 4 by 100-foot channel. 
Alternate channel across South Galveston Bay between 
Port Bolivar and Galveston causeway. 
"Red Fish Landing" changed to "Port Mansfield, Texas." 
Incorporate as part of Intracoastal Waterway a channel 9 
by 100 feet from main channel via Seadrift to point on 
Guadalupe River 3 miles above Victoria, Texas, authorized 
by River and Harbor Act of 1945. 
Small craft harbor 9 by 200 by 1,000 feet at Seadrift with 
an entrance channel 9 by 100 feet. 
Widen tributary channel between Port Aransas and 
Aransas Pass, Texas, to 125 feet; straighten and widen 
to 125 feet connecting channel to Conn Brown Harbor, 
and maintain Conn Brown Harbor at Federal expense, 
all to 12 feet deep. 
Improve channels and basins comprising channel to Port 
Mansfield constructed in part by Federal Government 
and in part by local interest; constructing turnout 
curves at Gulf Intracoastal Waterway intersection and 
bend easing at entrance to turning basin; construct 
parallel jetties at gulf entrance; maintenance of locally 
dredged jetty channel 16 by 250 feet; and maintenance 
of small craft basin. 
Entrance channel 7 feet deep by 75 feet wide from main 
channel to Gulf of Mexico to inside shoreline at Port 
Isabel, Texas, an inner channel 6 feet deep by 50 feet 
wide from entrance channel to East Harbor Basin, and 
an irregular-shaped harbor basin 6 feet deep having a 
surface area of about 7 acres. 
Deepen the existing 6-foot channel at Port Isabel to 12 
feet and removing the submerged bars at each end of 
the island to a depth of -12 feet MLT. 
Deepening the existing channel to 12 by 125 feet, and 
extend southeasterly from the Gulf Intracoastal 
Waterway main channel in West Galveston Bay, into 
Offatts Bayou, a distance of 2.2 miles, and a west 
turnout 12 by 125 feet between the proposed Offatts 
Bayou Channel and the Gulf Intracoastal Waterway. 
Deepening Aransas Pass tributary channel to 14 feet from 
mile 0 at Harbor Island to mile 6.1 at the city of 
Aransas Pass; widening to 175 feet between miles 3.5 
and 4.6; and deepening Conn Brown Harbor, turning 
basin and connecting channel between Conn Brown 
Harbor and turning basin. 
H. Doc. 627, 79th Cong., 
2nd Sess. 
H. Doc. 700, 79th Cong., 
2nd Sess. 
H. Doc. 768, 80th Cong., 
2nd Sess. 
H. Doc. 196, 81st Cong., 
1st Sess. 
PL 516, 81st Cong. 
PL 527, 82nd Cong., 
2nd Sess. 
H. Doc. 478, 81st Cong., 
2nd Sess. 
H. Doc. 376, 83rd Cong., 
2nd Sess. 
S. Doc. 11, 86th Cong., 
1st Sess. 
Sec. 107, PL 645, 86th 
Cong. 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
Sec. 107, PL 86-645 
31-29 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 23, 196216 
Oct. 23, 1962 
Oct. 23, 1962 
Oct. 27, 196517 
Aug. 13, 1968 
Nov. 17, 1986 
Nov. 17, 1988 
Oct. 31, 1992 
8. Mar. 5, 1905 
Mar. 2, 1919 
Mar. 3, 1925 
Jul. 3, 1930 
Improve main channel 16 feet deep and 150 feet wide 
from Sabine River to Houston Ship Channel; with two 
relocations; relocate main channel in Matagorda Bay 
and Corpus Christi Bay; and maintaining existing 
Lydia Ann Channel. 
Deepen and widen channel to Palacios; construct two 
protective breakwaters; maintain and deepen existing 
basins; and deepen, enlarge and maintain existing 
approach channel to basin No. 2. 
Eliminates requirement of local interest to construct bridge 
at mile 29.2 turning basin at Victoria, and maintain 
turning basins at Victoria and Seadrift; provide: Federal 
construction of vertical-lift railroad bridge at Missouri- 
Pacific Railroad mainline crossing, mile 29.2; 
construction and future maintenance of basin near 
Victoria, Texas, and maintenance of basin constructed 
by local interests at Seadrift, Texas. 
Modify existing Federal navigation project to provide a 
channel extending from Gulf Intracoastal Waterway 
through Chocolate Bay and Chocolate Bayou to project 
channel mile 8.2, thence to a turning basin near channel 
mile 13.2 and for salt water barrier in Chocolate 
Bayou about 3.7 miles upstream from basin (channel 
mile 16.9). 
Entrance channel 15 feet deep and 200 feet wide at the 
mouth of Colorado River Channel protected by an east 
jetty 3,500 feet long extending to 12-foot depth and a 
west jetty 2,900 feet long extending to 5-foot contour; 
make channel 12 feet by 100 feet from gulf shore to 
Matagorda, including recreation facility, a turning basin 
12 feet by 300 feet wide and 1,450 feet long, and a 
new diversion channel 250 feet wide and varying in 
depth from 20 to 23 feet including a closure dam across 
the present river channel. 
Modified 1968 authorization to provide that diversion features 
be constructed at Federal expense and operation 
and maintenance be shared 75 percent Federal and 25 
percent non-Federal. 
Enlarge existing Channel to Victoria from a depth of 9 
feet and width of 100 feet to a depth of 12 feet and 
width of 125 feet. 
Provide 8 miles of erosion protection for the existing waterway 
in the vicinity of Sargent, Texas. 
HOUSTON SHIP CHANNEL, TX 
Easing or cutting off sharp bends and construction of a 
pile dike.18 
A channel 30 feet deep, widen bend at Manchester and 
enlarge turning basin. 
A light-draft extension of channel to mouth of White Oak 
Bayou. 19 
Widen channel through Morgan Point and to a point 4,000 
feet above Baytown and widen certain bends. 
H. Doc. 556, 87th Cong., 
2nd Sess. 
H. Doc. 504, 87th Cong., 
2nd Sess. 
H. Doc. 288, 87th Cong., 
2nd Sess. 
H. Doc. 217, 89th Cong., 
1st Sess. 
S. Doc. 102, 90th Cong., 
2nd Sess. 
Sec. 812, PL 99-662 
Sec. 3, PL 100-676 
Sec. 101 (20), PL 102-580 
Rivers and Harbors 
Committee Doc. 35, 
61st Cong., 2nd Sess. 
H. Doc. 1632, 65th Cong., 
3rd Sess. 
H. Doc. 93, 67th Cong., 
1st Sess. 
H. Doc. 13, 71st Cong., 
1st Sess. 
31-30

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Aug. 30, 193511 
Aug. 30, 1935 
Mar. 2, 1945 
Mar 2, 1945 
Mar. 2, 1945 
Jun. 30, 1948 
Jul. 3, 195820 
Jul. 14, 1960 
Oct. 27, 1965 
Nov. 17, 1986 
9. Jun. 25, 1910 
Aug. 30, 1935 
Aug. 26, 1937 
Mar. 2, 1945 
Mar. 2, 1945 
Jul. 3, 1958 
Jul. 3, 1958 
Deepen to 32 feet in main channel and turning basin, 
and a 400-foot width through Galveston Bay. 
Deepen to 34 feet in main channel and widen from Morgan 
Point to turning basin. 
Branch channel 10 by 60 feet behind Brady Island. 
Widen channel from Morgan Point to lower end of Fidelity 
Island with turning points at mouth of Hunting Bayou 
and lower end of Brady Island. 
Widen channel from lower end of Fidelity Island to Houston 
turning basin and dredge off-channel silting basins. 
Deepen to 36 feet from Bolivar Roads to and including 
main turning basin at Houston, Texas, including turning 
points at Hunting Bayou and Brady Island. 
Deepen to 40 feet from Bolivar Roads to Brady Island, 
construct Clinton Island turning basin, a channel 8 by 
125 feet at Five Mile Cut, and improve shallow-draft 
channel at Turkey Bend. 
Barbour Terminal at Morgan Point. 
Restoring existing locally dredged channel from mile 0 to 
0.34 to 36 feet deep and dredging a 15-12 ft. channel 
from mile 0.34 to 2.81, in Greens Bayou.21 
Maintenance of Greens Bayou, Barbour Terminal Channel, 
and Bayport Ship Channel to forty-foot depths at 
Federal expense. 
MATAGORDA SHIP CHANNEL, TX 
Channel to Port Lavaca, Texas 7 feet deep and 89 feet 
bottom width. 
Extend 7-foot channel to shoreline of Lavaca Bay at mouth 
of Lynns Bayou. 
Deepen and widen channel to present project dimensions. 
Extend channel 6 by 100 feet from Port Lavaca via Lavaca 
Bay, Lavaca and Navidad Rivers to Red Bluff, a 
distance of 20 miles. 
A harbor of refuge 9 feet deep near Port Lavaca and an 
approach channel 100 feet wide and equal depth. 
Deepen to 12 feet and widen to 125 feet Port Lavaca 
Channel and approach channel to harbor of refuge; 
deepen to 12 feet Port Lavaca turning basin and basins 
at harbor of refuge. 
An entrance channel 38 by 300 feet, a channel 36 by 200 
feet, 22 miles long across Matagorda and Lavaca Bays 
to Point Comfort, Texas, a turning basin 36 feet deep 
and 1.000 feet square at Point Comfort, and dual jetties 
at entrance from gulf. 
Rivers and Harbors 
Committee Doc. 28, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 58, 
74th Cong., 1st Sess. 
H. Doc. 226, 76th Cong., 
1st Sess. 
H. Doc. 226, 76th Cong., 
1st Sess. 
H. Doc. 737, 79th Cong., 
2nd Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess. 
H. Doc. 350, 85th Cong., 
2nd Sess.' 
Sec. 107, PL 86-645 
H. Doc. 257, 89th Cong., 
1st Sess. 
Sec. 819, PL 99-662 
H. Doc. 1082, 60th Cong., 
2nd Sess. 
Rivers and Harbors 
Committee Doc. 28, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 37, 
75th Cong., 1st Sess. 
H. Doc. 314, 76th Cong., 
1st Sess. 
H. Doc. 731, 79th Cong., 
2nd Sess. 
H. Doc. 131, 84th Cong., 
1st Sess. 
H. Doc. 388, 84th Cong., 
2nd Sess. 
31-31 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
10. Jul. 25, 1912 
Sep. 22, 1922 
Sep. 22, 1922 
Mar. 3, 1925 
Jan. 21, 1927 
Aug. 30, 193511 
Aug. 30, 1935"11 
Aug. 30, 1935 
Aug. 26, 1937 
Aug. 26, 1937 
Jun. 20, 193822 
Oct. 17, 1940 
Mar. 2, 1945 
Mar. 2, 1945 
SABINE-NECHES WATERWAY, TX 
Existing project dimensions of jetties, a 26-foot channel 
through Sabine Pass, Port Arthur Canal and Port 
Arthur turning basin; and a 26-foot turning basin at 
Port Arthur. A depth of 25-feet in Sabine-Neches Canal, 
Neches River to Beaumont and Sabine River to Orange, 
including cutoffs and widening channels. 
Deepen channels to 30 feet from gulf to Beaumont, with 
increased widths and an anchorage basin in Sabine 
Pass. 
Deepen Port Arthur east and west turning basins and 
approach channel to 30 feet. Take over and deepen to 
30 feet channel connecting west turning basin with 
Taylors Bayou turning basin. For a 30-foot depth in 
channel from mouth of Neches River to cutoff in Sabine 
River near Orange. 
Removal of guard lock in Sabine-Neches Canal. 
Widen Sabine Pass and jetty channel, Port Arthur Canal, 
and Sabine-Neches Canal. For dredging 2 passing 
places in Sabine-Neches Canal, easing of bends, removal 
and reconstructing Port Arthur field office, extending 
Beaumont turning basin upstream 200 feet 
above new city wharves, and an anchorage basin in 
Sabine Pass. 
A depth of 32 feet in channels from gulf to Beaumont 
turning basin, including all turning basins at Port 
Arthur. 
Deepen channels to 34 feet with increased widths from 
gulf to Beaumont turning basin. 
Construct suitable permanent protective works along 
Sabine Lake. Maintain Taylors Bayou turning basin. 
Maintain channel from Sabine River to Orange Municipal 
wharf. 
Dredging 500 feet from eastern end of Harbor Island and 
abandonment of channel south and west of Harbor 
Island. 
Increased widths of channels from gulf to Beaumont turning 
basin and channel connecting Port Arthur west 
turning basin and Taylors Bayou turning basin, deepen 
Beaumont turning basin and Beaumont turning extension 
to 34 feet; and dredge a new cutoff from Smith's 
Bluff cutoff to McFadden Bend. 
Abandon Orange turning basin; dredge a channel 25 by 
150 feet, suitably widened on bends to highway bridge, 
and dredge a cutoff channel opposite Orange. 
Extend Beaumont turning basin upstream 300 feet. 
Widen Port Arthur west turning basin to 600 feet. 
H. Doc. 773, 61st Cong., 
2nd Sess. 
H. Doc. 975, 66th Cong., 
3rd Sess. 
S. Doc. 152, 67th Cong., 
2nd Sess. 
H. Doc. 234, 68th Cong., 
1st Sess. 
H. Doc 287, 69th Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 27, 
72nd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 12, 
74th Cong., 1st Sess. 
Specified in Act. 
Rivers and Harbors 
Committee Doc. 3, 
75th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 20, 
75th Cong., 1st Sess. 
H. Doc. 581, 75th Cong., 
3rd Sess. 
S. Doc 14, 77th Cong., 
1st Sess. 
H. Doc. 685, 76th Cong., 
3rd Sess. 
S. Doc 60, 77th Cong., 
1st Sess. 
31-32

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1945 
Jul. 24, 194623 
Jul. 24, 194624 
Jul. 24, 1946 
May 17, 1950 
Sep. 3, 195425 
Oct. 23, 196226 
11. Mar. 4, 1913 
Dredge a channel from Beaumont turning basin to vicinity 
of Pennsylvania Shipyard. 
Deepen Sabine Pass outer bar channel to 37 feet, Sabine 
Pass jetty channel to 36 feet at inner end, deepen to 
36 feet Sabine Pass Channel, Port Arthur Canal, Port 
Arthur east and west turning basins, Taylors Bayou 
turning basin and channel from Port Arthur west turning 
basin to Taylors Bayou turning basin, deepen to 36 
feet and widen to 400 feet Sabine-Neches Canal from 
Port Arthur Canal to mouth of Neches River except 
through Port Arthur Bridge; deepen Neches River channel 
from mouth to Beaumont turning basin to 36 feet 
widening to 350 feet from Smith's Bluff to Beaumont 
turning basin; deepen junction area on Neches River 
at Beaumont turning basin to 36 feet; and widen 
Sabine-Neches Canal between Neches and Sabine Rivers 
to 150 feet. 
Improve Cow Bayou, Texas, by construction of a channel 
100 feet wide and 13 feet deep extending from navigation 
channel in Sabine River to a point 0.5 mile above 
county bridge at Orangefield, Texas, with a turning 
basin. 
Improve Adams Bayou, Texas, to provide a channel 12 
feet deep and 100 feet wide extending from 12-foot 
depth in Sabine River to first county highway bridge 
across bayou. 
Deepen to 36 feet and widen to 400 feet the Sabine-Neches 
Canal near Port Arthur bridge; reconstruct Port Arthur 
Bridge and relocate Port Arthur field office. 
Rectification of certain reaches of existing Sabine Pass 
Channel, Sabine-Neches Canal, and Neches River and 
Sabine River Channel; widen to 350 feet entrance 
channel to Port Arthur turning basins; widen curve at 
junction of Port Arthur and Sabine-Neches Canals; 
relocate and enlarge Sabine Pass anchorage basin to 
34 by 1,500 by 3,000 feet; widen to 200 feet Sabine- 
Neches Canal from mouth of Neches River to mouth of 
Sabine River and Sabine River Channel to upper end 
of existing project at Orange, except for channel around 
Harbor Island at Orange; deepen to 30 feet Sabine 
River Channel from cutoff near Orange municipal slip 
to upper end of project, except around Harbor Island; 
and enlarge area at entrance to Orange municipal slip 
to provide a maneuvering basin. 
Improve outer bar channel to 42 and 40 feet for all inland 
channels to Port Arthur and Beaumont; width of 500 
feet in Port Arthur Canal and 400 feet in Neches River 
Channel to Beaumont with three turning points in 
Neches River; a channel, 12 by 125 feet, extending in 
Sabine River to Echo; and replace an obstructive bridge 
at Port Arthur, Texas. Deauthorization of uncompleted 
portion of channel between Port Arthur west turning 
basin and Taylors Bayou turning basin and 
enlargement of entrance channel to Port Arthur turning 
basins. 
TEXAS CITY CHANNEL, TX 
A channel 300 by 30 feet and construct a pile dike 28,200 
feet long north to channel. 
S. Doc 158, 77th Cong. 
2nd Sess. 
H. Doc. 571, 79th Cong., 
2nd Sess. 
H. Doc. 702, 79th Cong., 
2nd Sess. 
H. Doc. 626, 79th Cong., 
2nd Sess. 
H. Doc. 174, 81st Cong., 
1st Sess. 
S. Doc. 80, 83rd Cong., 
2nd Sess. 
H. Doc. 553, 87th Cong., 
2nd Sess.1 
H. Doc. 1390, 62nd Cong., 
3rd Sess. 
31-33 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 3, 1930 
Aug. 30, 1935" 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
Jun. 30, 1948 
Jul. 14, 1960 
Oct. 12, 1972 
(Senate Res.) 
Oct. 12, 1972 
(House Res.) 
Nov. 17, 1986 
12. Mar. 3, 1905 
Jul. 25, 1912 
Sep. 22, 1922 
Mar. 2, 1945 
A harbor 800 by 30 feet at Texas City, and construct a 
rubblemound dike. 
Extension of rubblemound dike to shoreline. 
Deepen channel and harbor to 32 feet. 
Deepen channel and harbor to 34 feet. 
Extend harbor 1,000 feet southward, 800 by 34 feet. 
Deepen channel and harbor to 36 feet, widen channel to 
400 feet and harbor to 1,000 feet and changing name 
of project to '"TEXAS CITY CHANNEL, TEXAS." 
Deepen channel and turning basin to 40 feet and construct 
16-foot Industrial Barge Canal. 
Widen the existing main turning basin to 1,200 feet 
including relocation of the basin 85 feet to the east; 
providing a 40-foot deep channel in the Industrial Canal 
at widths of 300-400 feet, with a turning basin at the 
head of the canal 40 feet deep, 1,150 feet long, and 
1,000 feet wide, and easing of the bend at the entrance 
to the canal, and deauthorization of shallow-draft 
Industrial Barge Canal not incorporated in the plan of 
improvement above. 
Deepening the Texas City Turning Basin to 50 feet, enlarging 
the 6.7 mile long Texas City Channel to 50 feet 
by 600 feet; deepening the existing 800-foot wide 
Bolivar Roads Channel and Inner Bar Channel to 50 
feet; deepening the existing 800-foot wide Outer Bar 
and Galveston Entrance Channels to 52 feet; extending 
the Galveston Entrance Channel to a 52 foot depth 
for 4.1 miles at a width of 800 feet and an additional 
reach at a width of 600 feet to the 52 foot contour in 
the Gulf of Mexico; and establishment of 600 acres of 
wetland and development of water-oriented recreational 
facilities on a 90-acre enlargement of the Texas City 
Dike. 
TRINITY RIVER AND TRIBUTARIES, TX 
Anahuac Channel. 
Six-foot channel to Liberty. 
Abandon improvements above Liberty and terminate all 
improvements by lock and dam, leaving a 6-foot channel 
from Liberty to mouth. 
Provides for a navigable channel from the Houston Ship 
Channel near Red Fish Bar in Galveston and Trinity 
Bays to the mouth of Trinity River and 9 feet deep and 
150 feet wide in the river section, with a turning basin 
at Liberty. 
H. Doc. 107, 71st Cong., 
1st Sess. 
Rivers and Harbors 
Committee Doc. 4, 
73rd Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 46, 
73rd Cong., 2nd Sess. 
Rivers and Harbors 
Committee Doc. 62, 
74th Cong., 1st Sess. 
Rivers and Harbors 
Committee Doc. 47, 
75th Cong., 1st Sess. 
H. Doc. 561, 80th Cong., 
2nd Sess.' 
H. Doc. 427, 86th Cong., 
2nd Sess. 
H. Doc. 199, 92nd Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
Sec. 201, PL 99-662 
H. Doc. 989, 66th Cong., 
3rd Sess. 
H. Doc. 403, 77th Cong., 
1st Sess. 
31-34

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jul. 24, 1946 
Oct. 23, 1962 
Oct. 27, 1965 
Jul. 30, 1983 
15. Dec. 15, 1970 
(House Res.) 
Dec. 17, 1970 
(Senate Res.) 
16. Jun. 20, 1938 
Sep. 3, 1954 
Oct. 27, 1965 
Nov. 28, 1990 
17. Aug. 13, 1968 
Nov. 17, 1986 
18. Nov. 17, 1988 
Modification of the project to provide for a channel 9 feet 
deep and 150 feet wide from the Houston Ship Channel 
near Red Fish Bar in Galveston Bay extending 
along the east shore of Trinity Bay to the mouth of the 
Trinity River at Anahuac, including protective spoil 
embankment on the bay side of the channel in lieu of 
the 9 by 200-foot channel in Galveston and Trinity 
Bays. 
Provides for the multiple-purpose Wallisville Reservoir, 
including a navigation lock in the Wallisville Dam at 
Channel Mile 28.30 and advancement of the Channel 
to Liberty from one mile below Anahuac (Mile 23.2) to 
the Texas Gulf Sulphur Company's slip at Channel 
Mile 35.8, and incorporation into existing project 
Anahuac Channel and mouth of Trinity River projects. 
Reevaluation of navigation benefits. 
Modified Wallisville Reservoir by reducing the size to 5,600 
acres and confining the reservoir to east side of Trinity 
River. 
CORPUS CHRISTI BEACH, TX (RESTORATION 
PROJECT) 
Restoration and periodic nourishment of 1.4 miles of beach. 
BUFFALO BAYOU AND TRIBUTARIES, TX 
Barker and Addicks Reservoirs, Texas. 
Clearing, straightening, enlarging and lining of Buffalo, 
Brays, and White Oak Bayous. 
Extend upper limits of White Oak Bayou upstream about 
2.1 miles from BRI RR bridge to mouth of Cole Creek. 
Flood damage reduction improvements and recreational 
development for the Houston, Texas urban area, divided 
into six separable elements - Brays, Greens, Hunting, 
Halls, Carpenters and Little White Oak Bayous. Flood 
control improvements consist of 75.3 miles of stream 
enlargement, 14 miles of stream clearing, 7 flood 
detention basins, 7 miles of diversion channels and 
environmental revegetation. Recreation features consist 
of 14.7 miles of trails, 502 picnic facilities, 12 group 
pavilions, 2 boat launching ramps, 10 restrooms, playgrounds, 
exercise stations and parking facilities. 
CLEAR CREEK, TX 
Channel enlargement and rectification from upper end of 
Clear Lake at Mile 3.8 to improved channel Mile 34.8.30 
Modified local cooperation requirements of the 1968 
authorization. 
CYPRESS CREEK, TX 
Enlargement and rectification of lower 29.4 miles of 
Cypress Creek channel and recreational development. 
H. Doc. 634, 79th Cong., 
2nd Sess. 
H. Doc. 215, 87th Cong., 
1st Sess. 
H. Doc. 276, 89th Cong., 
1st Sess. 
PL 98-63 
H. Doc. 415, 91st Cong., 
2nd Sess. 
(Sec. 201, PL 89-298) 
H. Doc. 456, 75th Cong., 
2nd Sess. 
H. Doc. 250, 83rd Cong., 
2nd Sess.' 
H. Doc. 169, 89th Cong., 
1st Sess. 
Sec. 101, PL 101-640 
H. Doc. 351, 90th Cong., 
2nd Sess. 
Sec. 1001, PL 99-662 
Sec. 3, PL 100-676 
31-35 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
19. Nov. 17, 1988 
21. Nov. 17, 1986 
22. Oct. 23, 1962 
23. Nov. 17, 1986 
25. Oct. 27, 1965 
26. Jul. 3, 1958 
28. Oct. 23, 1962 
FALFURRIAS, TX 
Construction of a 5.6-mile long diversion levee west of 
Falfurrias; a 1.8-mile long pilot channel west of 
Falfurrias; a flowage easement; and a 0.8-mile long 
ring levee around the sewage treatment plant. 
LOWER RIO GRANDE BASIN, TX 
Channel improvements to provide drainage protection for 
the area in Hidalgo and Willacy Counties north of U.S. 
Highway 83, and for the area between U.S. Highway 
83 and the Rio Grande in Hidalgo County; and to provide 
flood protection for the cities of McAllen, Edinburg, 
Raymondville, Edcouch, La Villa, and Lyford. 
PORT ARTHUR AND VICINITY, TX (HURRICANEFLOOD 
PROTECTION) 
Raising and reconstructing 6.3 miles of existing seawall; 
constructing 0.3 mile of new seawall, 20.3 miles new 
levees and five pumping plants; and raising and improving 
7.5 miles of existing levees.28 
SIMS BAYOU, TX 
Enlargement and rectification, with appropriate erosion 
control measures of 19.31 miles of Sims Bayou; environmental 
measures and riparian habitat along entire 
alignment, and recreational development. 
TAYLORS BAYOU, TX 
Enlarging and rectifying channels; construction of diversion 
channel; a salt water gate; enlargement of GIWW 
1.3 miles and alteration of State Highway 87 bridge.29 
TEXAS CITY AND VICINITY, TX (HURRICANEFLOOD 
PROTECTION) 
Construction of improvements for control of storm tides, 
consisting of new and enlarged levees and floodwalls 
approximately 14.1 and 2.1 miles in length; related 
drainage and stoplog structures; a navigation opening 
and pumping plants. 
VINCE AND LITTLE VINCE BAYOUS, TX 
Enlarging and rectifying channel of Vince Bayou and Little 
Vince Bayou upstream for a total of 11.5 miles for both 
streams. 
Sec. 3, PL 100-676 
Sec. 401, PL 99-662 
H. Doc. 505, 87th Cong., 
2nd Sess.' 
Sec. 401, PL 99-662 
H. Doc. 206, 89th Cong., 
1st Sess.1 
H. Doc. 347, 85th Cong., 
2nd Sess.1 
H. Doc. 441, 87th Cong., 
2nd Sess.1 
' Contains latest published maps. 
2 Extension of north jetty 1,950 feet and south jetty 
1,265 feet considered inactive. 
3 Dredging 2,000 by 650-foot northerly extension of 
inner basin deauthorized. 
4 Included in Public Works Administration program 
September 6, 1933 and February 16, 1935. 
5 West leg of Wye junction with main channel 
deauthorized. 
6 Construction of lock in diversion dam at local 
expense considered inactive. 
Dredging upper .5 mile of channel to vicinity of 
Stauffer Chemical plant was deauthorized under Sec. 12 of 
PL 93-251. Included in Public Works Administration program 
September 6, 1933. 
8 Dredging 43rd to 51st Streets was deauthorized 
under Sec. 12 of PL 93-251. 
9 Deauthorized under Sec. 12 of PL 93-251. 
to0D eepening 43rd to 57th Streets was deauthorized 
under Sec. 12 of PL 93-251. 
" Previously authorized September 6, 1933 by Public 
Works Administration. 
12 H. Doc. 230, 76th Cong., 1st Sess. and project 
documents contain latest published maps. 
13 Dredging upper 3.5 miles was deauthorized under 
Sec. 12 of PL 93-251. 
14 Dredging upper 5 miles was deauthorized under 
Sec. 1001 of PL 99-662. 
15 Inactive. 
16 Portion of 16-foot by 150-foot channel from Sabine 
River to Houston Ship Channel is inactive. Relocation of 
channel in Matagorda Bay deauthorized under Sec. 12 of PL 
93-251. 
17 The 9 feet by 100 feet channel from Mile 8.2 to 
Mile 13.2 in Chocolate Bayou was deauthorized under Sec. 
1001 of PL 99-662. 
31-36

GALVESTON, TEXAS, DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
18 Construction of pile dike was deauthorized under 
Sec. 12 of PL 93-251. 
'9 Hill Street Bridge to mouth of White Oak Bayou 
was deauthorized under Sec. 12 of PL 93-251. 
20 Deepening channel to 40 feet from Southern 
Pacific Slip to Brady Island was deauthorized under Sec. 12 
of PL 93-251. 
21 The 12-foot channel from mile 1.65 to mile 2.81 
deauthorized under Sec. 12 of PL 93-251. 
22 Complete widening of channel between Port 
Arthur west turning basin and Taylors Bayou turning basin 
deauthorized by 1962 R&H Act. 
23 Complete deepening of channel between Port 
Arthur west turning basin and Taylors Bayou turning basin 
deauthorized by 1962 R&H Act. 
24 Channel extension above Cow Bayou turning basin 
near Orangefield was deauthorized under Sec. 12 of PL 
93-251. 
25 Widening to 350 feet entrance channel to Port 
Arthur turning basin deauthorized by 1962 R&H Act. 
26 The 12-foot channel in Sabine River from Orange 
to Echo, Texas deauthorized under Sec. 12 of PL 93-251. 
27 Jetty extension was deauthorized under Sec. 1001 
of PL 99-662. 
28 Raising and strengthening of levees surrounding 
Gulf Oil Company's fresh water reservoir is inactive. 
29 Enlarging 7.0 miles of North Fork Taylors Bayou, 
7.8 miles of South Fork Taylors Bayou and 4.4 miles of 
Mayhaw Bayou are inactive. 
30 Portion of project upstream of Brazoria/Galveston 
County line, approximately mile 18.5, in inactive category. 
31 Turning basin was deauthorized under Sec. 1001 
of PL 99-662. 
31-37 
TABLE 31-B

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-C OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to September 30, 1991 
Report See 
Annual Report Operation and 
Project For Construction Maintenance 
Aquatic Plant Control (1958 and 1962 River and Harbor 
Acts)6 1967 38,2521 - 
Bastrop Bayou, TX2 1931 9,920 27,129 
Brazos River, TX, Velasco to Old Washington3 1924 216,9894 223,010 
Cedar Bayou, TX 1990 681,2638 2,809,8169 
Clear Creek and Clear Lake, TX 1982 66,934 537,139 
Corpus Christi, TX, Channel to Navy Seaplane Base Encinal 
Peninsula 1968 1,194,344 26,467 
Dickinson Bayou, TX 1954 33,942 57,553 
Double Bayou, TX 1987 226,558 1,412,07810 
East Bay (Hanna Reef), TX5 1922 2,476 847 
Johnson Bayou, LA6 1933 2,261 54,042 
Little Bay, TX7 1979 - 252,728 
Neches River and Trib., Salt Water Barrier at Beaumont, 
TX (Advance Engineering & Design) 1984 1,503,843 - 
Oyster Creek, TX 1922 6,942 7,556 
Sabine River and Tributaries, TX (Echo to Morgan Bluff)3 1971 - 
1 Excludes $1,672 work contribution. Aransas County Navigation District, Rockport, TX, 
2 Widening from 60 feet to 100 feet at 4-foot depth Acocnt st(rHu.c teDdo cp. ro1je1c4t, a8s1 astu thCoornigze.,d by 1950 River and Harbor 1st Sess.) in 1955 under 
was deauthorized under Sec. 12 of PL 93-251. Department of Army permit. 
3 Deauthorized under Sec. 1001 of PL 99-662. 8 Includes $39,087 for previous projects. In addition 
4 Includes $123,6n796 for previous projects. $25,000 expInenclduedde sf r$o6m9 ,c7o8n4t rfiobru pteredv ifouunsd sp.rojects. 
5 In inactive category for maintenance. '0 In addition, $102,325 expended from contributed 
6 Channel adequate for existing commerce. funds. 
TABLE 31-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Full Cost to September 30, 1991 
Report See 
Annual Report Operation and 
Project For Construction Maintenance 
Arroyo Colorado, Rio Hondo, Texas 1986 201,300 - 
Baytown, Texas' 1980 245,400 - 
Colorado River, Matagorda, Texas2 1963 273,757 - 
Freeport and Vicinity, Texas, Hurricane-Flood Protection 2 1984 29,285,0423 - 
Guadalupe River (Remove Log Jams), Texas2 1978 505,749 - 
Highland Bayou, Texas2 1984 12,254,390 - 
Lavaca-Navidad River, Texas: 
Hallettsville Project 1961 256,043 - 
General channel project 1952 21,086 - 
Liberty Local Protection Project, Texas 6 1971 98,517 - 
Mill Creek, Texas' 1952 24,753 - 
Peyton Creek, Texas4 1975 66,377 - 
San Diego Creek, Alice, Texas2 1963 135,175 - 
Tranquitas Creek, Kingsville, Texas2 1956 130,239 - 
Three Rivers, Texas5 5 5,835,927 - 
Upper White Oak Bayou, Texas 1989 972,300 - 
1Inactive. 
2 Completed. 
3 In addition, $8,695,438 expended from contributed 
funds, $1,126,905 estimated value of contributed lands, and 
$2,726,446 for relocations by local interests. 
4 Deauthorized under Sec. 12 of PL 93-251. 
5 See Annual Report for 1983, Fort Worth District, 
page 16-12. 
6 Deauthorized under Sec. 1001 of PL 99-662. 
31-38

GALVESTON, TEXAS, DISTRICT 
TABLE 31-E TOTAL COST OF EXISTING PROJECTS 
See Total Cost 
Section to 
in Text Project Funds New Work Maintenance Rehabilitation Sep. 30, 1992 
2. Brazos Island Harbor, TX 
3. Channel to Port Bolivar, TX 
4. Corpus Christi Ship 
Channel, TX 
5. Freeport Harbor, TX 
6. Galveston Harbor and 
Channel, TX 
7. Gulf Intracoastal Waterway 
betw,een Apalachee Bay, FL 
and the Mexican Border 
8. Houston Ship Channel, TX 
10. Sabine-Neches Waterway, TX 
11. Texas City Channel, TX 
12. Trinity River and 
Tributaries, TX 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Total cost of project 
Regular 
Channel 
Seawall 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Public Works 
Contributed 
Total 
Value of useful work 
performed 
Contributed land 
Total cost of project 
Regular 
Public Works 
Contributed 
Total cost of project 
Regular 
Contributed 
Total cost of project 
12,273,830 
2,848,560 
3,848,341 
18,970,731 
85,214 
85,214 
74,803,040 
324,287 
5,959,930 
81,087,257 
1,716,695 
276,720 
83,080,672 
51,869,982 
116,575 
17,898,572 
69,885,129 
360,249 
70,245,378 
11,920,187 
8,754,209
0 
3,648,932 
24,323,328 
76,801,445 
466,477 
4,443,085 
81,711,007 
395,000 
139,776 
82,245,783 
29,042,293 
2,612,932 
1,382,760 
33,037,985 
49,592,331 
1,363,652 
2,103,435 
53,059,418 
32,000 
116,760 
53,208,178 
14,628,853 
136,296 
1,023,819 
15,788,968 
29,966,038 
66,000 
30,032,038 
47,737,238
0 
1,352,092 
49,089,330 
1,179,318 
1,179,318 
97,284,774
0 
647,922 
97,932,696
0
0 
97,932,696 
51,440,845
0 
229,311 
51,670,156
0 
51,670,156 
89,814,026 
512,163 
13,121 
2,122,583 
92,461,893 
293,135,078
0 
22,672 
293,157,750
0
0 
293,157,750 
130,352,699
0 
334,641 
130,687,340 
168,173,787
0 
3,660,026 
171,833,813
0
0 
171,833,813 
24,449,816
0
0_ 
24,449,816 
14,611,938
0 
14,611,938 
12,170,080
0
0 
2,170,080 
62,181,148 
2,848,560 
5,200,433 
70,230,141 
0 1,264,532 
0 1,264,532 
3,576,684
0
0 
3,576,684
0
0 
3,576,684 
8,935
0
0 
8,935
0 
8,935 
7,373,356 
595,973
0
0 
7,969,329 
1,270,511
0
0 
1,270,511
0
0 
1,270,511 
726,158
0
0 
726,158 
175,664,498 
324,287 
6,607,852 
182,596,637 
1,716,695 
276,720 
184,590,052 
103,319,762 
116,575 
18,127,883 
121,564,220 
360,249 
121,924,469 
109,107,569 
9,862,345 
13,121 
5,771,515 
124,754,550 
371,207,034 
466,477 
4,465,757 
376,139,268 
395,000 
139,776 
376,674,044 
159,394,992 
2,612,932 
1,717,401 
163,725,325 
217,766,118 
1,363,652 
5,763,461 
224,893,231 
32,000 
116,760 
225,041,991 
39,804,827 
136,296 
1,023,819 
40,964,942 
44,577,976 
66,000 
44,643,976 
31-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-F CHANNEL DIMENSIONS 
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Depth in 
Feet Feet 
See (Below (Below Bottom 
Section Mean Low Bottom Mean Low Width Length 
in Text Project Section of Waterway Tide) Width (Feet) Tide) (Feet) Feet Miles 
2. Brazos Island Outer Bar and Jetty Channel 
Harbor, TX Padre Island to Long Island 
Long Island to Goose Island 
Goose Island to Turning 
Basin Extension 
Turning Basin Extension 
Brownsville Turning Basin 
Port Isabel Channel via East 
Turnout 
West Wye, from Brownsville 
Channel 
Port Isabel Turning Basin 
Fishing Boat Harbor: 
West Basin 
Middle Basin 
East Basin 
Connecting Channel 
Entrance Channel 
4. Corpus Christi Aransas Pass Outer Bar 
Ship Channel, Channel 
TX Aransas Pass Jetty Channel 
Inner Basin at Harbor Island 
Channel to Port Aransas 
Port Aransas Turning Basin 
Anchorage Basin at Port 
Aransas 
Inner Basin to Mile 8.5 
Mile 8.5 to LaQuinta 
Junction 
LaQuinta Junction to Corpus 
Christi Turning Basin 
Corpus Christi Turning Basin 
Industrial Canal 
Avery Point Turning Basin 
Channel to Chemical 
Turning Basin 
Chemical Turning Basin 
Tule Lake Channel 
Tule Lake Turning Basin 
Viola Channel 
Viola Turning Basin 
Channel to LaQuinta 
LaQuinta Turning Basin 
Turning Point at LaQuinta 
Channel Junction 
Jewel Fulton Canal 
Jewel Fulton Turning Basin 
Mooring Area at Ingleside: 
Mooring Area (a) 
Mooring Area (b) 
5. Freeport Outer Bar Channel 
Harbor, TX Jetty Channel 
Quintana Turning Basin 
Channel to Brazosport 
Turning Basin 
Brazosport Turning Basin 
Channel to Upper Turning 
Basin 
Upper Turning Basin 
Channel to Stauffer Chemical 
Plant 
Stauffer Turning Basin 
Brazos Harbor Channel 
44-42 400 38-36 300 
42 
42 
42 
42 
36 
36 
36 
36 
15 
15 
15 
15 
15 
47 
45 
45 
12 
12 
12 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
45 
12 
12 
45 
45 
47 
45 
45 
45 
45 
45 
45 
30. 
30 
36 
300 
300 
300 
500 
1,000 
200 
200 
1,000 
370-305 
370-305 
370 
270 
100. 
700 
600-730 
730-1,720 
100-150 
200-4002 
300-400 
600-500 
500 
400 
800 
400 
975 
400 
1,2006 
300 
1,200 
300-350 
1,200 
300-400 
1,200 
1,2503 
100 
200 
150 
150 
400 
400 
7504 
400 
1,0004 
375 
1,2004 
200 
500 
200 
36 
36 
36 
36 
36 
36 
36 
36 
15 
15 
15 
15 
15 
47 
45 
45 
12 
12 
12 
45 
45 
40-45 
45 
45 
45 
45 
45 
40 
40 
40 
40 
45 
45 
45 
12 
12 
45 
38 
36 
36 
36 
36 
36 
30 
25 
30 
200 
200 
200 
500 
1,000 
200 
200 
1,000 
370-305 
370-305 
370 
265 
100 
700 
600 
Irregular 
100 
2002 
300-400 
600-500 
500 
400 
1,000 
400 
1,000 
350 
1,0506 
200 
900 
200-250 
700-900 
300-400 
1,200 
1,2503 
100 
200 
150 
300 
200 
200-350 
744-800 
350-375 
600 
200 
500 
200 
31-40 
2.5 
2.1 
9.6 
3.2 
1.3 
2,670 0.5 
1.4 
0.8 
1,300 0.2 
1,470 0.3 
1,200 0.2 
1,470 0.3 
1,230 0.2 
770 0.1 
1.8 
1.0 
1,550 
0.1 
200 
900 0.2 
8.5 
3.6 
8.6 
5,423 1.0 
1.1 
1,150 0.2 
0.6 
1,690 0.3 
3.1 
1,000 0.2 
1.8 
1,000 0.2 
5.6 
800 0.1 
1,250 0.2 
- 0.8 
400 0.1 
- 0.8 
- 3.0 
- 0.8 
- 1.2 
667 0.1 
- 1.4 
600 0.1 
- 1.1 
500 0.1 
- 0.5

GALVESTON, TEXAS, DISTRICT 
TABLE 31-F CHANNEL DIMENSIONS 
Basin 
Entrance Channel 
Outer Bar Channel 
Inner Bar Channel 
Anchorage Basin 
Bolivar Roads Channel 
Bolivar Roads Channel to 
43rd St. 
Bolivar Roads to Morgan 
Point 
Morgan Point to Boggy 
Bayou 
Boggy Bayou to Greens 
Bayou 
Greens Bayou to Sims Bayou 
Hunting Bayou Turning 
Point 
Clinton Island Turning 
Basin 
Sims Bayou to Southern 
Pacific Slip 
Southern Pacific Slip to 
Houston Turning Basin 
Houston Turning Basin 
Upper Turning Basin 
Brady Island Channel 
Barbour Terminal Channel 
Turning Basin 
Bayport Ship Channel 
Turning Basin 
Anchorage Area 
Five-Mile Cut Channel 
Light-Draft Channel: 
Upper Turning Basin to 
Jensen Drive 
Turkey Bend Channel 
Greens Bayou Channel: 
Mile 0 to Mile 0.36 
Mile 0.36 to Mile 1.57 
9. Matagorda Ship Outer Bar and Jetty Channel 
Channel, TX Channel to Point Comfort 
Approach Channel to 
Turning Basin 
Turning Basin 
Channel to Port Lavaca 
Lynn Bayou Turning Basin 
Channel to Harbor of Refuge 
North-South Basin 
East-West Basin 
Channel to Red Bluff 
10. Sabine-Neches Sabine Bank Channel 
Waterway, TX Sabine Pass Outer Bar 
Channel 
Sabine Pass Jetty Channel 
Sabine Pass Anchorage 
Basin 
Sabine Pass Channel 
Port Arthur Canal 
Entrance to Port Arthur 
Turning Basins 
Port Arthur East Turning 
Basin 
6. Galveston 
Harbor and 
Channel, TX 
8. Houston Ship 
Channel, TX 
7504 
800 
800 
800 
2,8751 
800 
1,125 
36 
52 
52 
50 
36 
50 
40 
40 
40 
40 
40 
40 
40 
40 
36 
36 
36 
10 
40 
40 
40 
40 
40 
8 
10 
10 
40 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12 
6 
42 
42 
40 
40 
40 
40 
40 
40 
30 
42 
42 
40 
36 
40 
40 
40 
40 
40 
40 
40 
40 
40 
36 
36 
36 
10 
40 
40 
40 
40 
40
8 
10 
10 
40 
15 
38 
36 
36 
36 
12 
12 
12 
12 
12 
6 
42 
42 
40 
40 
40 
40 
40 
40 
525-675 
800 
800 
800 
2,875 
800 
1,125 
675 0.1 
- 4.7 
- 1.7 
- 3.2 
- 1.81 
- 1.0 
- 3.9 
400 - 26.2 
400 - 12.8 
300 - 2.4 
300 - 5.3 
948-1,0009 1,375 - 
965-1,0709 1,592 - 
300 - 0.6 
300 - 2.9 
400-1,000 3,100 0.6 
150 1,000 0.2 
60 - 0.9 
300 - 3.1 
2,000 2,000 0.4 
300 - 3.8 
1,600 1,000 0.3 
150 - - 
125 - 1.9 
400 
400 
300 
300 
900-1,0009 
8009 
300 
300 
400-1,000 
150 
60 
300 
2,000 
300 
1,600 
150 
125 
60 
60 
175 
100 
300 
300-200' 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
800 
800 
800-500 
1,500 
500 
500 
275-678 
420 
- 4.1 
- 0.8 
- 0.3 
- 1.3 
- 3.2 
- 20.9 
- 1.1 
1,000 0.2 
- 4.1 
532 0.1 
- 1.9 
1,682 0.3 
1,750 0.3 
- 20.2 
- 14.7 
- 3.4 
- 4.1 
3,000
- 5.6 
- 6.2 
- 0.3 
1,765 0.3 
31-41
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Depth in 
Feet Feet 
See (Below (Below Bottom 
Section Mean Low Bottom Mean Low Width Length 
in Text Project Section of Waterway Tide) Width (Feet) Tide) (Feet) Feet Miles 
5. (Continued) Brazos Harbor Turning 
60 
60 
175 
100 
300 
300-2006 
200-300 
1,000 
125 
27-340 
125 
300 
250 
100 
800 
800 
800-500 
1,500 
500 
500 
275-678 
370-547

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-F CHANNEL DIMENSIONS 
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Depth in 
Feet Feet 
See (Below (Below Bottom 
Section Mean Low Bottom Mean Low Width Length 
in Text Project Section of Waterway Tide) Width (Feet) Tide) (Feet) Feet Miles 
10. (Continued) Port Arthur West Turning 
Basin 40 600 40 350-550 1,610 0.3 
Channel connecting Port 
Arthur West and Taylors 
Bayou Turning Basins 40 200-250 40 200-250 - 0.6 
Taylors Bayou Turning Basin 40 150-1,000 40 90-1,233 3,470 0.7 
Sabine-Neches Canal, Port 
Arthur Canal to Neches 
River 40 400 40 400 - 11.2 
Turning Point at Mile 19.5 40 9004 40 9004 - 8 
Neches River, Mouth to 
Maneuvering Area Beaumont 
Turning Basin 40 400 40 400 - 18.3 
Turning Point, Mile 31.1 40 1,0004 40 1,000 700 8 
Turning Point, Mile 36.6 40 1,0004 40 1,000 930 8 
Turning Point, Mile 40.3 40 1,0004 40 1,300 1,530 8 
Channel Extension, Mile 
40.3 36 350 36 350 1,265 0.2 
Maneuvering Area at 
Beaumont Turning Basin 40 Irregular 40 Irregular 1,300 0.2 
Beaumont Turning Basin 34 500 34 160-535 1,500 0.3 
Beaumont Turning Basin 
Extension 34 350 34 300 - 0.4 
Beaumont Turning Basin 
Extension to End of Project 
Channel Vicinity 
Bethlehem Steel Company 30 200 30 200 - 0.7 
Sabine-Neches Canal, Neches 
River to Sabine River 30 200 30 200 - 4.4 
Sabine River Channel, Mouth 
to Foot of Green Ave. 30 200 30 200 - 9.5 
Orange Turning Basin 30 Irregular 30 Irregular 1,550 0.3 
Orange Municipal Slip 30 200 30 150-200 2,435 0.5 
Old Channel Around Harbor 
Island 25 150-200 25 150-200 - 2.4 
Channel to Echo' 12 125 - - - - 
Adams Bayou 12 100 12 100 - 1.7 
Cow Bayou 13 100 13 100 - 7.0 
Orangefield Turning Basin 13 300 13 300 500 0.1 
1 Average. 
2 Includes 100-foot channel width. 
3 Includes 450-foot channel to Corpus Christi. 
4 Diameter. 
5 Includes 350-foot channel width. 
6 300-foot width through Matagorda Peninsula. 
7 Deauthorized. 
8 Included in channel length. 
9 Includes 300-foot channel width. 
31-42

GALVESTON, TEXAS, DISTRICT 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Adopted Project 
Dimensions Improved Projec 
Depth in Depth in 
Feet (Below Bottom Feet (Below 
Mean Low Width Mean Low Bottom 
Tributary Channel 
Offats Bayou 
Main Channel 
West Wye 
Chocolate Bayou Channel 
12-Foot Channel via 
East Turnout 
West Turnout 
9-Foot Channel 
Turning Basin 
San Bernard River Channel 
Colorado River Channel 
Turning Basin 
Silting Basin 
Mouth of Colorado River 
Navigation Channel, GIWW to Gulf 
Turning Basin at Matagorda 
Channel to Palacios 
Turning Basin No. 1 
Turning Basin No. 2 
Connecting Channel 
Channel to Barroom Bay 
Channel to Victoria Main Channel via 
East Turnout 
Turning Basin 
West Turnout Channel 
Channel to Seadrift via South Turnout 
Turning Basin 
North Turnout Channel 
Harbor of Refuge at Seadrift Channel 
Basin 
Channel to Rockport 
Turning Basin 
Channel to Aransas Pass 
Turning Basin 
Channel to Conn Brown Harbor 
Conn Brown Harbor 
Channel to Port Mansfield 
Entrance Channel 
Approach Channel to Hopper Dredge 
Turning Basin 
Hopper Dredge Turning Basin 
Channel Across Padre Island and 
Laguna Madre 
Turnout Channels, East Side of Main 
Channel, GIWW 
North Turnout 
South Turnout 
Channel West Side of Main Channel, 
GIWW, to P.T. of Turnout Channels 
Turnout Channels, West Side of Main 
Channel, GIWW 
North Turnout 
South Turnout 
Channel from P.T. of Turnout Channels to 
Approach 
Channel to Main Turning Basin 
Approach Channel to Main Turning Basin 
Main Turning Basin 
Turning Basin Extension 
Small Craft Basin 
Shrimp Basin 
Tide) (Feet) Tide) Width (Fee 
12 
12 
2 12 
3 12 
4 99 
5 9 
6 9
99 
15-12 
12 
8 12 
12 
12 
12 
9 12 
12 
12
99999999 
14 
14 
14 
14 
to 
16 
16 
16 
14 
12 
12 
14 
12 
12 
14 
14 
14 
14
8 
12 
125 
125 
125 
125 
100 
600 
100 
100 
400 
150 
200-100 
350 
125 
200 
300 
150-480 
60 
100 
600(AVG) 
100 
100 
250 
100 
100 
200 
200 
475 
175 
300 
125 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
125 
200 
400 
1,000 
160 
350 
12 
12 
12 
12
9
999 
12 
12 
12 
12
9
9
9999 
99 
14 
14 
14 
14 
16 
16 
16 
14 
12 
12 
14 
12 
12 
14 
14 
14 
14
8 
12 
125 
125 
125 
125 
100 
100 
400 
150 
125 
200 
300 
130-400 
100 
500(AVG) 
100 
100 
200 
100
- 
200 
342(AGvo 
125-175 
300 
0.2 
300 
250 
100 
300 
100 
100 
100 
100 
200 
200 
125 
200 
400 
1,000 
160 
350 
t Dimensions 
Length 
t) Feet Miles 
2.3 
2,200 0.4 
8.2 
0.8 
26.0 
15.5 
0.1 
1.0 
16.1 
0.1 
0.2 
0.1 
500 
635 
1,130 
1
2
1 
- 34.8 
80 0 iAVG) 0.1 
- 0.8 
- 2.0 
230
-- 0.5 
- 2.1 
,225 0.2 
- 6.1 
,212 0.4 
125 - 
,800 0.3 
- 0.8 
- 0.4 
300 0.1 
- 7.7 
- 0.6 
- 0.6 
- 0.6 
- 0.6 
- 0.6 
1,250 
580 
860 
1,450 
0.6 
0.3 
0.2 
0.1 
0.2 
0.3 
31-43 
TABLE 31-G

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-G 
GULF INTRACOASTAL WATERWAY 
APALACHEE BAY, FLORIDA TO MEXICAN BORDER 
EXISTING PROJECT DIMENSIONS, PROVIDED 
FOR IN TRIBUTARY CHANNELS 
Adopted Project 
Dimensions Improved Project Dimensions 
Depth in Depth in 
Feet (Below Bottom Feet (Below 
Mean Low Width Mean Low Bottom Length 
Tributary Channel Tide) (Feet) Tide) Width (Feet) Feet Miles 
Channel to Harlingen via South Turnout 
from Main Channel, GIWW 12 125 12 12511 - 25.812 
Turning Basin near Rio Hondo 12 400 12 400 500 0.1 
North Turnout from Main Channel 12 200 12 200 - 0.7 
Port Isabel Side Channels 
Main Channel 12 125 12 125-90 - 0.6 
Main Channel 12 233-60 12 233-60 - 0.4 
South Leg 12 125 12 125 - 0.2 
Port Isabel Small Boat Harbor 
Entrance Channel 7 75 7 75 - 1.4 
Harbor Channel 6 50 6 50 - 0.3 
Boat Basin 6 Variable 6 72-501 1,308 0.2 
1 Includes the construction of a salt water barrier at 
Mile 16.9.
2 Constructed 10 feet deep by 100 feet wide by local 
interests. East turnout channel constructed 150 feet wide. 
3 Constructed by local interests. 
4 Authorized to mile 13.2. Mile 8.2 to Mile 13.2 was 
deauthorized. 
6 Authorized to Mile 31 above mouth (channel mile 29.41). 
Upper 3.4 miles was deauthorized under Section 12 of PL 93-251. 
6 Includes a discharge channel from Matagorda, Texas, to 
the gulf which was dredged by local interests in 1939. (Maintenance 
will be discontinued upon completion of improvements authorized 
by R&H Act of 1968.) 
7 Authorized by R&H Act of 1968. Also provides for a 
dam across the present discharge channel, a new 250-foot wide by 
20 to 23-feet deep discharge channel into Matagorda Bay, and a 15- 
foot by 200-foot wide entrance channel with parallel jetties from the 
gulf shoreline into the Gulf of Mexico. East jetty to be 3,500 feet 
long and west jetty 2,900 feet long. 
8 Includes two protective breakwaters at entrance to 
turning basins. 
9 In the inactive category for maintenance. 
10 Also provides for two stone jetties at the gulf entrance 
about 1,000 feet apart. (North jetty constructed 2,300 feet long and 
south jetty constructed 2,270 feet long.) 
11 South turnout is 200 feet wide. 
12 Authorized to mile 31. Mile 25.8 to Mile 31 was 
deauthorized. 
31-44

GALVESTON, TEXAS, DISTRICT 

Brazos Island Harbor, TX 
(New Work) 

Dredging Brazos Island Harbor, 
TX - Entrance Channel

February 20, 1992 to 
September 30, 1992 

575,054

$810,841  

Dredging Inshore Reach No. 1, 
Station 1+000 to 23+000 

July 25, 1992 to 
September 30, 1992 

148,750 

$181,475



Corpus Christi Ship Channel, 
TX (Maintenance) 

Dredging Beacon 82 through 
Avery Point Turning Basin 

October 30, 1991 to 
March 18, 1992 

1,791,652 

$2,160,690

Dredging Inner Basin to 
La Quinta Junction 

December 6, 1991 to 
January 26, 1992 

850,951 

$680,336 

Emergency dredging Corpus 
Christi Entrance Channel 
(US Hopper Dredge Wheeler) 

September 4, 1992 to 
September 30, 1992

866,228

$2,220,000 


Freeport Harbor, TX 
(New Work) 

Dredging Main Channel, Brazosport 
Turning Basin & Jetty Channel

October 1, 1991 to 
June 24, 1992 

1,280,280 

$4,177,161


Freeport Harbor, TX 
(New Work) (Maintenance) 

Dredging Entrance Channel - 
Sta 260+00 to Sta 50+35.91 

October 1, 1991 to 
April 1, 1992

346,757 

$2,716,534 


Freeport Harbor, TX 
(New Work) (Maintenance) 

Dredging Entrance Channel - 
Sta 260+00 to Sta 50+35.91 

October 1, 1991 to 
April 1, 1992

46,804

$105,309 


Freeport Harbor, TX 
(Maintenance) 

Dredging Freeport Harbor and 
Entrance Channel 

August 28, 1992 to 
September 30, 1992

802,095 

$768,607 


Gulf Intracoastal Waterway, 
TX (New Work) 

Dredging Mouth of the Colorado 
and Tiger Island Channel Dam 

December 9, 1991 to 
September 30, 1992

935,867 

$1,068,166  

Gulf Intracoastal Waterway, 
TX (Maintenance)
 
Dredging Channel to Victoria 
and Channel to Seadrift 

October 1, 1991 to 
October 29, 1991

737,639 

$355,212  

Dredging Port Isabel to Port 
Mansfield and Tributary Channels

October 1, 1991 to 
November 25, 1991 

61,430 

$78,395  

Dredging Texas City Junction to 
Galveston Causeway 

October 1, 1991 to 
January 7, 1992

977,293 

$718,882  

Dredging Main Channel in 
Matagorda Bay 

September 17, 1992 to
September 30, 1992 

163,000 

$271,900

Dredging Channel to Palacious 

March 1, 1992 to 
June 8, 1992

1,826,634 

$652,495

Emergency dredging Brazos River 
crossing and vicinity 

January 27, 1992 to
April 26, 1992

1,228,079 

$1,271,852 

Emergency dredging Colorado 
River crossing 

March 16, 1992 to 
March 30, 1992

110,347 

$243,625

Dredging Galveston Causeway to 
Bastrop Bayou and West Bay Demo 

April 7, 1992 to 
September 27, 1992 

639,934 

$3,699,980 

Dredging Channel to Harlingen

March 2, 1992 to 
September 30, 1992  

440,166 

$1,400,480 

Dredging Colorado River Channel 
and basins 

April 5, 1992 to 
May 13, 1992 

210,313 

$276,086

Dredging Main Channel across 
Aransas Bay 

May 22, 1992 to 
August 1, 1992 

868,017 

$458,126

31-45 

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 31-H DREDGING OPERATIONS 

Gulf Intracoastal Waterway, 
TX (Maintenance) 

Dredging Vicinity FM 467 to 
Boggy Bayou and Colorado 
River to Matagorda Bay 

June 17, 1992 to 
September 30, 1992

567,190 

$1,424,222

Dredging Channel to Port 
Mansfield to Mud Flats

July 1, 1992 to 
July 10, 1992 

 
416,612 

$286,182 
 
Dredging Matagorda Bay to 
San Antonio Bay 

July 21, 1992 to 
September 30, 1992 

497,534 

$694,180 

Dredging Main Channel in 
Matagorda Bay 

September 19, 1992 to
September 30, 1992 

163,000 

$271,900 


Houston Ship Channel, TX 
(Maintenance) 

Dredging Turning Basin and 
Light Draft Channel and 
Miscellaneous Work 

October 1, 1991 to 
October 1, 1991

1,745 

$35,552


Matagorda Ship Channel, TX 
(Maintenance) 

Dredging Matagorda Peninsula 
to Point Comfort 

October 1, 1991 to 
May 1, 1992 

4,454,331 

$1,805,734 

Dredging Channel to Port Lavaca 
and Channel to Harbor of Refuge

November 11, 1991 to 
February 27, 1992  

1,256,587 

$370,588


Sabine-Neches Waterway, TX 
(Maintenance) 

Dredging Sabine-Neches Canal 
(Section B) and Sabine River 
Channel 

October 1, 1991 to 
October 19, 1991

340,236 

$426,798 

Dredging Sabine Pass Outer 
Bar Channel

September 11, 1992 to
September 30, 1992

1,056,381 

$700,391 
 
Dredging Sabine Bank Channel 
(US Dredge Wheeler)

October 1, 1991 to
October 21, 1991 

2,026,140 

$1,554,000


Trinity River and Tributaries, 
TX (Maintenance)
 
Emergency Dredging Anahuac 
Channel 

May 10, 1992 to 
June 18, 1992 

332,218 

$295,841


Taylors Bayou, TX 
(New Work) 

Dredging Bayou Din and 
Pivitot Bayou 

December 4, 1991 to 
September 15, 1992

283,136 

$633,907

Dredging Hillebrandt Bayou 
Sta. 543+50 to 751+00 and 
Willow Marsh Bayou Sta. 0+00 
to 12+00 
 
February 3, 1992 to 
September 30, 1992 

371,446 

$1,061,178
 

31-46

ALBUQUERQUE, NM, DISTRICT* 
The district comprises the watershed of the Canadian River 
and its tributaries in New Mexico; the watershed of Arkansas 
River and its tributaries in Colorado; the watershed of Rio 
Grande and its tributaries including the Pecos River and its 
tributaries upstream of Amistad Lake; and the San Juan River 
Basin in New Mexico; and the watersheds of the Gila, San 
Francisco and Mimbres Rivers and its tributaries in New 
Mexico. 
Note: The district watershed boundaries were revised in June 
1986 to include the portion of New Mexico west of the 
Continental Divide. 
IMPROVEMENTS 
Flood Control 
1. Acequias Irrigation System, NM ......... 
2. Alamogordo, NM .................. 
3. Alamosa, CO .................... 
4. Cochiti Wetfields, NM ............... 
5. Albuquerque Diversion Channels, NM ..... 
6. Conchas Lake, NM ................. 
7. El Paso, TX ..................... 
8. Fountain Creek, Pueblo, CO ........... 
9. John Martin Reservoir, CO ............ 
10. Puerco River, Gallup, NM ............ 
11. Rio Grande Basin, NM .............. 
11A. Abiquiu Dam, NM ................. 
11B. Cochiti Lake, NM ................. 
11C. Galisteo Dam, NM ................. 
11D. Jemez Canyon Dam, NM ............. 
11E. Middle Rio Grande Flood Protection, 
Bernalillo to Belen, NM ............. 
11F. Rio Grande Floodway, NM ............. 
11G. Rio Grande Floodway, San Acacia 
to Bosque del Apache Unit, NM ........ 
Page 
32-1 
32-2 
32-2 
32-2 
32-2 
32-3 
32-3 
32-4 
32-4 
32-5 
32-5 
32-5 
32-6 
32-6 
32-7 
Flood Control (Continued) 
11H. Truth or Consequences Unit, NM ........ 
12. Santa Rosa Dam and Lake, NM .......... 
13. Trinidad Lake, CO ................... 
14. Two Rivers Dam, NM ............... 
15. Inspection of completed flood 
control projects ................... 
16. Scheduling flood control 
reservoir operations ................. 
17. Other authorized flood 
control projects .................... 
18. Flood control work under 
special authorizations ................ 
General Investigations 
19. Surveys ............................. 
20. Collection and study of basic data ........ 
32-7 21. 
32-7 22. 
Continuation of Planning and Engineering . . . 
Advance Engineering and Design .......... 
32-8 
Flood Control 
1. ACEQUIAS IRRIGATION SYSTEM, NM 
Location. There are about one thousand acequias throughout 
the state of New Mexico, most of which are located in northcentral 
New Mexico. 
Proposed project. Authorized by the Water Resources 
Development Act of 1986, Section 1113, the project consists of 
about one thousand acequias throughout the state of New 
Mexico. These community ditch systems provide irrigation 
water to about 160,000 acres on an estimated 12,000 farms. 
*All costs and financial statements for projects are listed at the end of this chapter. All other tables are referenced in text and also appear at the end of this chapter. 
32-1 
Page 
32-8 
32-8 
32-9 
32-10 
32-10 
32-10 
32-11 
32-11 
32-12 
32-12 
32-12 
32-12

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Acequias have been in existence since the early Spanish 
Colonization period of the 17th and 18th Centuries and 
represent one of the oldest forms of cooperative institutions in 
the United States. They are an integral part of the culture and 
heritage of New Mexico. Diversion structures, many of which 
are constructed of available materials such as rock and brush, 
are frequently destroyed by flows greater than normal resulting 
from spring runoff or summer thunderstorms. Disruption of 
the ditches usually occurs during peak irrigation season and 
severely impacts crop production. The Water Resources 
Development Act of 1986 directs the U.S. Army Corps of 
Engineers to undertake measures, without regard to economic 
analysis, as are necessary to protect and restore the river 
diversion structures and associated canals. 
Local Cooperation. The local sponsor, the State of New 
Mexico, has a law whereby the State of New Mexico provides 
17.5% of the project costs, and low interest loans to the local 
Acequias for the remaining 7.5%. The State of New Mexico 
has appropriated, and will appropriate on an annual basis, the 
funds necessary to meet the requirements of local sponsorship. 
Operation and results during fiscal year. Funds to initiate 
construction were received in Fiscal Year 1988. Construction 
contracts were awarded in FY 1988, FY 1989, FY 1990, FY 
1991, and FY 1993. 
Condition at end of fiscal year. Construction was 
completed on structures for five projects in FY 1992: Ojo del 
Gallo, Vadito, Questa South, Reservoir Martinez, and Coyote. 
2. ALAMOGORDO, NM 
Location. The project is located south central New Mexico 
in Otero County, in and near Alamogordo, NM. The city is 
situated at the foot of the Sacramento Mountains near the 
eastern edge of the Tularosa (Closed) Basin. 
Proposed Project. The authorized project consists of a 
concrete and rip-rap lined diversion channel with a Standard 
Project Flood flow capacity, which will intercept flows from 
the Sacramento Mountains east of the City. For a description 
of the complete improvement and authorizing legislation see 
page 694 of Annual Report for 1966. 
Local Cooperation. The Water Resources Development Act 
of 1986 applies. 
Operation and Results during fiscal year. An Interim 
Letter Report, which addressed locally preferred alternatives 
for the 100-year flood protection, was prepared and submitted. 
The letter report was approved and a Limited Reevaluation 
Report will be prepared. 
Condition at the end of the fiscal year. Design efforts will 
continued through FY 1992. 
3. ALAMOSA, CO 
Location. The project lies in south central Colorado along the 
Rio Grande, in the community of Alamosa, CO. 
Proposed Project. The project consists of a levee system 
which will replace and augment the existing spoil bank levees. 
(See Table 32-B for authorizing legislation.) 
Local Cooperation. The Water Resources Development Act 
of 1986 applies. 
Operation and results during fiscal year. Preconstruction, 
Engineering and Design activities were initiated in FY 1990 and 
continued through the fiscal year. 
Condition at the end of the fiscal year. 
continued during FY 1992. 
Design efforts 
4. COCHITI WETFIELDS, NM 
Location. Cochiti Dam and Lake is in north-central New 
Mexico approximately 50 miles north of Albuquerque, New 
Mexico. The Pueblo de Cochiti is located immediately 
downstream of the dam. 
Proposed Project. The project consists of installing an 
underground drainage system on 625 acres, the establishment of 
an operation, maintenance, and replacement sinking fund, 
settlement of past crop losses sustained by Pueblo de Cochiti, and 
wetland mitigation. (See Table 32-B for authorizing legislation.) 
Local Cooperation. None required. 
Operation and results during fiscal year. Operation and 
maintenance funds were received in FY 91 for design and 
preparation of plans and specifications of the sub-drain system. 
Condition at the end of the fiscal year. Design efforts 
continued during FY 1992. 
5. ALBUQUERQUE DIVERSION 
CHANNELS, NM 
Location. The project is located in an area which comprises 
watersheds of ephemeral streams entering a 15-mile reach of the 
Rio Grande from the east at Albuquerque, NM, and vicinity. 
32-2

ALBUQUERQUE, NM, DISTRICT* 
Combined drainage area of the tributaries is about 276 square 
miles. The Sandia range of the Rocky Mountains, which is 
about 12 miles east of the Rio Grande, forms the eastern 
border of the watersheds. The crest of this mountain range 
rises more than a mile over the river to an elevation of 10,692 
feet above mean sea level. (See Geological Survey Map, 
Albuquerque, NM, quadrangle, scale 1:62,500.). 
Existing project. Improvements consist of north and south 
diversion channels on high ground east of and parallel to the 
valley. Channels are designed to carry floods equal in 
magnitude to standard project flood from all tributaries. For 
a description of the complete improvement and authorizing 
legislation see page 17-15 of Annual Report for FY 1973. 
Local cooperation. Section 2 of the Flood Control Act of 
1938 applies. For details of local cooperation requirements see 
page 17-2 of the Annual Report for FY 1973. 
Operations and results during fiscal year. The North 
Diversion Channel prevented $13,818,000 in flood damages 
during FY 1991. The estimated total accumulated flood 
damages prevented are $134,785,000. Peak flood flows 
recorded during FY 1991 were: North Diversion Channel near 
Alameda 8,150 c.f.s.; South Diversion Channel 813 c.f.s. 
Condition at end of fiscal year. Construction of the North 
and South Diversion Channels began in March 1965, and was 
completed in March 1972. The South Diversion Channel is in 
good condition and well maintained by the local interests. The 
North Diversion Channel has experienced severe arching and 
cracking of the concrete lined portion. Construction to correct 
this problem was initiated and completed in FY 1987. 
Additionally, a hydraulic flow problem exists on the North 
Diversion Channel. A model study, completed in February 
1986, identified corrective measures. 
6. CONCHAS LAKE, NM 
Location. The dam is in San Miguel County, NM, on the 
Canadian River, just below the confluence of the Canadian and 
Conchas Rivers. (See Geological Survey State map of New 
Mexico, scale 1:500,000, and Geological Survey topographic 
map, Tucumcari quadrangle, scale 1:250,000.) 
Existing project. A concrete gravity main dam section 
1,250 feet long with a maximum height of 200 feet above 
streambed located in the Canadian River Canyon together with 
earth dikes on each side have an overall length of about 3.7 
miles. The main section contains conduits in its base for the 
release of water from the reservoir, and an overflow, ungated 
spillway 300 feet long. The earth dikes vary in height up to 
100 feet and the north dike contains a concrete ogee-type 
emergency spillway 3,000 feet long. The reservoir has a gross 
storage capacity of 513,900 acre-feet (198,170 for flood control, 
254,200 for water conservation and irrigation, and 61,530 dead 
storage). The dam controls 7,409 square miles of drainage area. 
(See page 17-16 of Annual Report of 1973 for authorizing 
legislation.) 
Local cooperation. None Required. 
Operations and results during fiscal year. The reservoir was 
operated for storage of floodwater and releases for irrigation 
purposes. $86,000 in sediment damages were prevented during 
FY 1992 while no flood damages were prevented. Estimated 
total accumulated flood and sediment damages prevented by the 
project through FY 1992 were $3,477,100. Estimated irrigation 
benefits for FY 1992 were $113,700. Estimated total 
accumulated irrigation benefits through FY 1992 were 
$9,868,800. The pool elevation at the start of FY 1992 was 
4,196.66 feet with corresponding storage of 276,143 acre-feet. 
Total releases for this reporting period were 84,745 acre-feet. 
Releases of 81,818 acre-feet were made to Arch Hurley 
Conservancy District and 2,926 acre-feet to Bell Ranch. The 
pool elevation on September 30, 1992 was 4,197.04 feet with 
corresponding storage of 279,437 acre-feet. Sediment deposition 
during the fiscal year was 759 acre-feet. 
Condition at end of fiscal year. The existing project was 
essentially complete in 1939. Irrigation of some lands 
downstream from the project began in November 1945. A cost 
sharing agreement between the Government and the State of New 
Mexico for additional Recreation Development at Conchas Lake 
was completed in August 1977. Costs of the facilities are 50 
percent State of New Mexico and 50 percent Federal. Construction 
of recreation facilities was initiated in FY 1978 and 
completed in FY 1983. The project structures are in good 
condition and in operation. 
7. EL PASO, TX 
Location. The project is located at El Paso, El Paso County, 
TX, which is on the left bank of the Rio Grande in the reach that 
forms part of the international boundary between the United 
States and the Republic of Mexico. (Geological Survey map for 
El Paso, TX; New Mexico quadrangle, scale 1:250,000.) 
Existing project. This project consists of a single-purpose 
flood control system of detention dams, diversion dikes, conduits 
and channels to collect, regulate and discharge arroyo runoff into 
the Rio Grande. Runoff from the tributary arroyos on the 
eastern, southern, and western slopes of the adjacent Franklin 
Mountains often inundates sections of the city and its outlying 
32-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
suburban developments. The project is divided into three 
independent elements: Northwest area, Central area, and 
Southeast area. The project plan satisfies the 1933 U.S. and 
Mexico agreement on limited tributary discharge into the Rio 
Grande in El Paso, Texas. (See Table 32-B for authorizing 
legislation.) 
Local cooperation. Section 2 of the Flood Control Act of 
June 28, 1938 applied for the Northwest and Central areas. 
The Local Cooperation Agreement for the Southeast area 
reflects the cost sharing requirements contained in the Water 
Resources Development Act of 1986. 
Operations and results during fiscal year. Flood control 
dams in operation during FY 1992 and dates of completion of 
construction are as follows: Northgate and Range Dams 
(February 1973); Sunrise and Mountain Park Dams (October 
1974); and Pershing Dam (March 1977); Fort Bliss Diversion 
Channel (November 1978); Oxidation Pond and Buena Vista 
Diversion and Oxidation Pond Outlet Conduit (November 
1980); Mulberry and Thorn Drive Dams (June 1982); Mesa 
Dam (September 1982); McKelligon Canyon Dam (October 
1982); Keystone Dam (September 1983); Keystone Outlet 
Conduit (March 1984); Highway Diversion Channel (May 
1985); Dam Safety Assurance Program to the existing Range 
and Northgate Dams (May 1986); Borderland Diversion 
Channel (September 1986); and Phelps Dodge Basin (January 
1990). During FY 1992 flood flows and flood control storage 
were minimal, however, damages which would have resulted 
from these flows were prevented. 
Condition at end of fiscal year. Construction has 
temporarily ended in the Central Area. The only remaining 
work is the Pershing Dam, Dam Safety Assurance. The 
Northwest Area of the project for all practical purposes is 100 
percent complete. 
The General Design Memorandum for the Southeast Area 
was completed in September 1987. Construction was 
completed in January 1990 on the Phelps Dodge Basin, and 
construction was initiated in August 1990 on Phelps Dodge 
Channel, with an anticipated completion date of May 1992. 
Construction continued in 1992 on Americas Basin. 
8. FOUNTAIN CREEK, PUEBLO, CO 
Location. The project is located on Fountain Creek 
approximately 1 mile above the confluence of the Arkansas 
River and Fountain Creek in the city of Pueblo in southeastern 
Colorado. Pueblo is approximately 30 miles east of the Wet 
Mountains of the Rocky Mountains. (See Geological Survey 
Map, Northeast Pueblo, CO quadrangle, scale 1:24,000.) 
Proposed project. Authorized by the Water Resources 
Development Act of 1986, PL 99-662, the project comprises 
11,500 feet of channel modification and 9,700 feet of levee 
which will provide a 200-year level of protection at an estimated 
first cost of $8,880,000 ($6,410,000 Federal and $2,470,000 
non-Federal). (See Table 32-B for authorizing legislation.) 
Local cooperation. The Water Resources Development Act 
of 1986 applies. 
Operations and results during fiscal year. Funds for 
initiation of construction were initially received in fiscal year 
1987. A construction contract for recreation was awarded in 
September 1987. The remaining construction contract for levees 
and channel work was awarded 21 June 1988. Construction was 
substantially complete in July 1989. 
Condition at end of year. Construction on the levees and 
channel began in July 1988 and the entire project was completed 
in April 1991. 
9. JOHN MARTIN RESERVOIR, CO 
Location. The project is located on the Arkansas River, in 
Bent County, 1,159 miles upstream from its mouth, 300 miles 
downstream from its source, about 18 miles upstream from the 
city of Lamar, CO. (See Geological Survey maps for Lamar and 
Las Animas, CO quadrangles, scale 1:125,000.) 
Existing project. The project consists of a concrete and 
earthfill structure about 2.6 miles long with a maximum height 
of 106 feet above streambed and an overflow, gated spillway 
1,174 feet long. Total capacity of the reservoir at the top of 
flood control is 608,250 acre-feet (259,800 for flood control and 
348,450 for conservation and recreation storage). This reservoir 
controls a contributing drainage area of 18,130 square miles and 
is operated as a unit of the coordinated reservoir system for flood 
control in the Arkansas River Basin. Public Law 89-298 
modified the act of June 22, 1936 (49 Stat. 1570) to authorize 
10,000 acre-feet of reservoir flood control storage space for fish 
and wildlife and recreation purposes. For details of the 
completed improvement and authorizing legislation see page 17- 
16 of Annual Report for FY 1973. 
Local cooperation. Section 3 of the Flood Control Act of 
June 22, 1936, applies. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. Regulation of conservation storage 
continued under rules and regulations of the Arkansas River 
Compact. $107,300 in sediment damages were prevented during 
FY 1992. Estimated total flood and sediment damages prevented 
32-4

ALBUQUERQUE, NM, DISTRICT 
by this project through FY 1992 were $92,129,300. Estimated 
irrigation benefits for FY 1992 were $232,300. Estimated total 
accumulative irrigation benefits were $25,220,500. Maximum 
pool elevation of 3,815.99 feet with corresponding storage of 
70,800 acre-feet occurred on April 4, 1992. Total releases for 
FY 1992 were 172,989 acre-feet. Releases attributed to 
irrigation benefits amounted to 59,097 acre-feet. Sediment 
deposition was 958 acre-feet in FY 1992. 
Condition at end of fiscal year. Storage and operation of 
the reservoir for irrigation began in March 1943. A contract 
to rehabilitate the controls on sixteen tainter gates on the main 
dam was completed in FY 1991. Rehabilitation of the primary 
and secondary electrical distribution system is scheduled to be 
done in FY 1992. The project structures are in good condition 
and operational. 
10. PUERCO RIVER, GALLUP, NM 
Location. The project is located on the Puerco River in the 
city of Gallup in northwestern New Mexico in McKinley 
County. 
Proposed project. This project was authorized by the Water 
Resources Development Act of 1986, PL 99-662 and the 
Energy and Water Development Appropriations Act of 1988. 
The project consists of improvement of existing levees, 
construction of new levees and limited channel rectification. 
The project will provide the 100-year level of protection at an 
estimated first cost of $6,670,000 ($5,000,000 Federal and 
$1,670,000 non-Federal) 1 October 1989 price levels. (See 
Table 32-B for authorizing legislation.) 
Local cooperation. The Water Resources Development Act 
of 1986 applies. 
Operation and results during fiscal year. Funds to initiate 
construction were received in Fiscal Year 1988. A 
construction contract for the I-40 Auxiliary Levee was awarded 
in September 1988. The remaining construction contracts for 
the construction of the levees and channel improvement were 
awarded in June 1989. The entire project was completed in 
July 1991. 
Condition at end of year. The construction contract for 
levee and channel improvement was awarded in June 1989. 
The project was completed in July 1991. 
11. RIO GRANDE BASIN, NM 
Location. Improvements are on the Rio Grande and 
tributaries in New Mexico. More definite locations and 
descriptions of individual projects are in following paragraphs 
and individual reports by projects. 
Existing project. The Flood Control Act of 1948 authorized 
the flood control phase of the comprehensive plan of 
development of water resources of the Rio Grande basin in New 
Mexico (H. Doc 243, 81st Cong., 1st sess.) with the exception 
of Chiflo Dam and Reservoir and spillway gate structure at 
Chamita Dam. Although recommended, Chiflo Dam and 
Reservoir was deleted from the authorized plan. It was excluded 
without prejudice from future consideration by Congress. It was 
requested at that time, by the States of Colorado and Texas, that 
the project be deferred for restudy regarding required storage and 
methods of operation. By the same act, Congress also authorized 
for the construction irrigation phase of the comprehensive plan 
as recommended by the Bureau of Reclamation (H. Doc. 653, 
81st Cong., 2nd sess.). The act also stipulated that work should 
be prosecuted in accordance with a joint agreement approved by 
the Secretary of the Army and Acting Secretary of the Interior on 
November 21, 1957. In addition, under that agreement the 
Bureau of Reclamation was given responsibility for construction, 
operation, and maintenance of channel rectification, and drainage 
rehabilitation and extension phases of the unified plan of 
improvement. Authority for the Chamita Dam and Reservoir 
was abrogated when Cochiti Dam and Reservoir was authorized. 
(See Table 32-B for authorizing legislation and Table 32-C for 
existing projects.) 
All operations and costs for projects contained in the authorized 
plan are reflected in individual reports on the following pages. 
11A. ABIQUIU DAM, NM 
Location. The project is one unit of the flood control plan for 
the Rio Grande and tributaries, New Mexico. Abiquiu Dam is 
on the Rio Chama near the town of Abiquiu, NM, about 32 miles 
upstream from the confluence of Rio Chama and Rio Grande. 
(See Geological Survey Map for plan and profile of Rio Chama, 
NM, from mouth to mile 103, sheet 1, and Army Map Service, 
Aztec, NM; Colorado NJ 13-1, scale 1:250,000.) 
Existing project. This project consists of an earthfill dam 
1,540 feet long, 325 feet high, with a 12-foot diameter controlled 
outlet, and an uncontrolled spillway in a natural saddle about one 
mile north of the left abutment. The reservoir provides 568,000 
acre-feet of flood control and sediment storage. Total capacity 
at the spillway crest is 1,198,500 acre-feet. For a detailed 
description of the completed improvements and authorizing 
legislation see Annual Report of 1973. A major rehabilitation 
project was completed in September, 1980 and the recreation 
facilities were completed in FY 1981. A non-Federal 
hydropower plant was completed in 1990 by the County of Los 
32-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Alamos. The capacity of this plant is 13.2 MW. Drainage 
adits were completed in 1990 to alleviate seepage problems in 
the north and south abutments. 
Local cooperation. None required. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. Storage and flows were 
regulated in accordance with Section 203, Flood Control Act of 
1960. On October 1, 1991, the pool elevation was 6,205.49 
feet. The maximum pool (6,223.12 feet) and storage (202,266 
acre-feet) occurred on May 31, 1992. On September 30, 1992, 
the pool elevation was 6,205.81 feet with a corresponding 
storage of 135,148 acre-feet. There was 1,455 acre-feet of 
sediment deposition during FY 1992. 
There were $7,320,700 in flood damages prevented during 
FY 1992. 
Sediment damages prevented were $163,000. Accumulated 
flood and sediment damages prevented by the project since 
completion were $241,323,200 through FY 1992. 
Condition at end of fiscal year. The project was placed in 
operation in February 1963. In March 1989 construction was 
started on two drainage adits to alleviate seepage problems in 
the North and South abutments. Construction was completed 
in February 1990. Rehabilitation of the primary electrical 
distribution system was started in FY 1991 and is scheduled for 
completion in mid FY 1992. Project structures are in good 
condition and in operation. 
Emergency gates were not installed in the outlet conduit of 
Abiquiu Dam during its construction. A plan for the Abiquiu 
Dam emergency gates has been prepared in accordance with 
Section 1112 of the Water Resources Development Act of 
1986. Construction of the emergency gates is necessary to 
increase safety and enhance flood and sediment control. A 
Design Memorandum was prepared in FY 1991. 
1IB. COCHITI LAKE, NM 
Location. The dam is at river mile 340 on the Rio Grande 
(river mile 0 being at the intersection of the New Mexico-Texas 
State line with international boundary at El Paso, TX), near 
Pueblo de Cochiti, which is about 50 miles upstream from 
Albuquerque, NM. (See Geological Survey Maps, Cochiti 
Dam, NM, quadrangle and Santo Domingo Pueblo, NM, 
quadrangle, scale 1:24,000.) 
Existing project. This project consists of an earthfill dam 
about 5.4 miles long with a maximum height of 251 feet above 
streambed. The project extends generally in an east-west line 
across the Rio Grande to a point about 2 miles east of the Rio 
Grande and then southward across the Santa Fe River. An 
uncontrolled spillway with a 460-foot-long ogee-weir and a 160- 
foot notch 10.5 feet deep in the center is part of the embankment 
on the south side of the Santa Fe River. Operational releases for 
flood control and irrigation are made through a 3-barrel gated 
conduit in the left abutment on the Rio Grande. The reservoir 
has a storage capacity of 597,000 acre-feet at the spillway crest, 
of which 155,000 acre-feet is dedicated for recreation and 
sediment control. The project controls flood waters from a 
11,695 square mile drainage area. For more improvement 
details see page 17-7 of Annual Report for 1980. See page 17- 
14 of fiscal year 1981 Annual Report for authorizing legislation. 
Local cooperation. None required. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. The project was completed in June 
1975. On October 1, 1991, the pool elevation was 5,332.04 feet 
with a corresponding storage of 49,866 acre-feet. The maximum 
pool elevation was 5,360.67 feet with a storage of 93,552 acrefeet 
on April 19, 1992. On September 30, 1992 the pool 
elevation was 5,334.71 feet with a corresponding storage of 
49,436 acre-feet. There was 1,296 acre-feet of sediment 
deposition during FY 1992. There were $10,913,400 flood 
damages prevented during FY 1992. Sediment damages 
prevented were $145,200. Accumulated total damages prevented 
are $264,232,200. 
Conditions at end of fiscal year. The dam and appurtenances 
were placed in operation in 1975. The Cochiti Recreation area 
was completed in 1976, with the Visitors Center completed in 
1977. The Tetilla Peak recreation area was completed in 1981. 
Slope stabilization work on Sile Canal was completed in FY 
1991. Rehabilitation of recreation shelters began in FY 1991 and 
is scheduled to be completed in the first quarter of FY 1992. 
Project structures are in good condition and in operation. 
11C. GALISTEO DAM, NM 
Location. The dam is at river mile 12 on Galisteo Creek, a 
tributary of the Rio Grande. The reservoir will extend upstream 
from the dam for about 4 miles, near the village of Waldo, NM. 
(See Geological Survey Map,. San Pedro 1, NM quadrangle, 
scale 1:24,000.) 
Existing project. This project consists of an earthfill dam 
2,820 feet long with a maximum height of 158 feet above the 
streambed. The outlet works consist of a 10-foot diameter 
uncontrolled outlet with a discharge capacity of 4,980 cubic feet 
per second with a pool at the spillway crest elevation. The 
32-6

ALBUQUERQUE, NM, DISTRICT 
spillway is a broad crested weir 250 feet long in the right 
abutment. The project has 79,600 acre-feet of flood control 
storage and 9,868 acre-feet of sediment space. For more 
details of completed improvements and authorizing legislation 
see page 17-17 of Annual Report for 1973. 
Local cooperation. None required. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. Operation of the project began 
on October 11, 1970. The reservoir was empty on October 1, 
1990. No storage occurred during FY 1992. Peak inflow was 
210 c.f.s. and maximum outflow was 210 c.f.s. There was 18 
acre-feet of sediment deposition during the year and the 
reservoir was empty on September 30, 1992. Sediment 
damages prevented during the FY were $2,000 totaling 
$135,400 through FY 1992. 
Condition at end of fiscal year. The project was placed in 
operation in October 1970. The project structures are in good 
condition and in operation. 
11D. JEMEZ CANYON DAM, NM 
Location. The project is located in Sandoval County, NM, 
on the Jemez River about 2 miles upstream from the confluence 
of the Jemez River and the Rio Grande, about 5 miles 
northwest of Bernalillo, NM. (See Geological Survey map for 
Bernalillo quadrangle, scale 1:125,000.) 
Existing project. This project consists of an earthfill dam 
780 feet long with maximum height of 146.6 feet above 
streambed, and off-channel uncontrolled saddle spillway 400 
feet wide, and a 13-foot diameter gated outlet in the left 
abutment with discharge capacity of 8,340 cubic feet per 
second with a pool at spillway crest elevation. The dam was 
raised 14.1 feet and the spillway widened 28 feet in 1986 and 
1987 to provide adequate discharge capability to accommodate 
the revised probable maximum flood. The reservoir has a 
capacity of 100,485 acre-feet at spillway crest (73,000 acre-feet 
for flood control and 33,100 acre-feet for sediment control). 
For more detailed description of completed improvements and 
authorizing legislation see page 17-17 of Annual Report for 
1973. 
Local cooperation. None required. 
Operations and results during fiscal year. On October 1, 
1991, the pool elevation was 5,194.50 feet with a 
corresponding storage of 26,398 acre-feet. The maximum pool 
elevation was 5,208.41 feet with a storage of 45,536 acre-feet 
on April 23, 1992. On September 30, 1992 the pool elevation 
was 5,193.87 feet with a corresponding storage of 23,650 acrefeet. 
The reservoir was regulated for sediment control during 
FY 1992. Sediment deposition during FY 1992 was 905 acrefeet. 
There were no flood damages prevented during FY 1992. 
Sediment benefits during FY 1992 were $101,400. Estimated 
total accumulated flood and sediment damages prevented by the 
project through FY 1992 were $12,129,100. 
Condition at end of fiscal year. The project was placed in 
operation in October 1953. An inspection in FY 1990 revealed 
some concrete deterioration on the bridge abutment and stilling 
basin wall. A study to determine structural integrity was recently 
completed. Repair recommendations have been addressed. 
Design plans and specifications are currently underway. 
Construction is planned in FY 1993. All other project structures 
are in good condition and all structures are in operation. 
11E. MIDDLE RIO GRANDE FLOOD 
PROTECTION, BERNALILLO 
TO BELEN, NM 
Location. The project is composed of 45 square miles of 
floodplain lying along the Rio Grande from the vicinity of 
Corrales to Belen, New Mexico. 
Proposed project. The project is authorized by the Water 
Resources Development Act of 1986. The project consists of 
raising and rehabilitating 51.5 miles of levees to provide the 270- 
year level of protection, and the creation of 75 acres of wetlands 
from borrow areas within the bosque, and acquisition of 200 
acres to satisfy fish and wildlife mitigation requirements. The 
proposed project will be constructed at an estimated total cost of 
$59,300,000 ($44,600,000Federal and $14,700,000non-Federal) 
1 Oct 92 price levels. (See Table 32-B for authorizing 
legislation.) 
Local cooperation. Water Resources Development Act of 
1986 applies. 
Operations and results during fiscal year. A Limited 
Reevaluation Report was completed and draft LCA negotiated. 
Both will be submitted July 1993. 
11F. RIO GRANDE FLOODWAY, NM 
Location. This project is one unit of the flood control phase 
of the comprehensive plan of improvement for the Rio Grande 
Basin in New Mexico. It is on the Rio Grande and covers a 
section of the river commencing near Truth or Consequences 
(formerly Hot Springs) at about river mile 123 and extends 
upstream to Espafiola, NM, about river mile 394. (See Table 
32-D on Rio Grande Floodway.) 
32-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. This project consists of flood protection 
and major drainage improvements by channel rectification, 
levee enlargement and construction, and bank stabilization work 
where needed to protect the levees. Construction of the project 
is a joint undertaking by the Bureau of Reclamation and the 
Corps. Portions to be done by the Corps will consist of levee 
enlargement, construction, and bank protection work, with 
channel-rectification and drainage-rehabilitation work being the 
responsibility of Bureau of Reclamation. Levees constructed 
by local interests exist throughout the reach of the river 
involved, but are not uniform as to grade, section, or standard 
of construction, and in many places are threatened by the 
meandering river. (See Table 32-D on existing project and 
Table 32-B for authorizing legislation.) 
Local cooperation. In addition to the usual requirements, 
local interests are responsible for all highway, bridge, and 
public utility relocations or replacements required in 
construction of the project. Local interests will also be 
required to comply with requirements of Section 221, 1970 
Flood Control Act, Section 401, 1986 Water Resource 
Development Act, and PL 91-646 Uniform Relocation 
Assistance Act of 1970. Total costs for all requirements for 
the completed Albuquerque unit under terms of project 
authorization were $75,000. There were no non-Federal costs 
in connection with the construction of the Cochiti to Rio Puerco 
unit of floodway. The Espanola Valley unit is in the deferred 
category. Neither the city of Espanola nor Santa Clara Pueblo 
have given any indication that they plan any positive action to 
solve the flooding problem. For more details see page 17-8 of 
Annual Report for 1980. 
Operations and results during fiscal year. There were 
$393,300 flood damages prevented by the completed floodway 
project during FY 1992. Estimated total accumulated flood 
damages prevented by the floodway project through FY 1992 
amounted to $44,977,100. The peak flow of the Rio Grande 
through the middle valley was 6,110 c.f.s. at Albuquerque on 
April 29, 1992. The peak at San Acacia was 6,170 c.f.s. on 
May 12, 1992. 
Condition at end of fiscal year. Construction of the 
Albuquerque unit of the Rio Grande Floodway project is 
complete. The General Design Memorandum for the Bernalillo 
to Belen unit was completed in June 1986. The General 
Design Memorandum for the San Acacia to Bosque del Apache 
unit was approved in August 1990. Construction was initiated 
on the Truth or Consequences Unit in fiscal year 1989. The 
Espanola Valley unit was reclassified to deferred category on 
17 October 1973. 
11G. SAN ACACIA TO BOSQUE 
DEL APACHE UNIT, NM 
Location. The project is located along the Rio Grande, 
extending from the upper end of the Rio Grande low-flow 
conveyance channel at the San Acacia diversion works to the 
head of Elephant Butte Reservoir. 
Proposed project. The project was authorized by the Flood 
Control Act of 1948. The project consists of the reconstruction 
of 55 miles of existing spoil bank levee which separates the Rio 
Grande low-flow conveyance channel from the cleared floodway. 
The proposed project will be constructed at an estimated total 
cost of $55,600,000 ($48,650,000 Federal and $6,950,000 non- 
Federal) 1 Oct 92 price levels. (See Table 32-B for authorizing 
legislation.) 
Local Cooperation. The Water Resources Development Act 
of 1986 and the Water Resources Development Act of 1992 
apply. The Water Resources Development Act of 1992 modified 
the Local Sponsor's required contribution. 
11H. TRUTH OR CONSEQUENCES UNIT, NM 
Location. This project is located on Cuchillo Negro Creek in 
the vicinity of the city of Truth or Consequences, New Mexico. 
Proposed project. The project is authorized by the Flood 
Control Act of 1948 and 1950, modified by the Water Resources 
Development Act of 1986, to provide that the Secretary is 
authorized to construct a flood control dam on Cuchillo Negro 
Creek, a tributary of the Rio Grande in lieu of the originally 
authorized floodway. The project has been constructed at an 
estimated total cost of $17,200,000 ($12,910,000 Federal and 
$3,400,000 Non-Federal) 1 October 1991 price levels. (See 
Table 32-B for authorizing legislation.) 
Local cooperation. Water Resources Development Act of 
1986 applies. 
Operations and results during fiscal year. Construction of 
this unit of the Rio Grande Floodway project was completed in 
July 1991. 
12. SANTA ROSA DAM AND LAKE, NM 
Location. The project is located on a lake in Guadalupe 
County, on Pecos River, at river mile 766.4 approximately 
32-8

ALBUQUERQUE, NM, DISTRICT 
7 miles north of Santa Rosa, NM. (See U.S. Geological 
Survey map, Corazon, NM, sheet, scale 1:125,000.) 
Existing project. Operation of the project began in 
November 1979. It consists of an earth and rock fill dam 
1,950 feet long and 212 feet maximum height above the 
streambed. The purposes of the project are flood control, 
irrigation and sediment retention. An unlined, open rock cut 
about 1,000 feet back from the left abutment serves as an 
uncontrolled spillway. The outlet works, located in the left 
abutment, consists of a control tower, intake structure with 
gates, and a 10-foot diameter concrete lined tunnel with a 
terminal flip bucket energy dissipator. Storage capacity at the 
spillway crest is 439,860 acre-feet which includes 72,860 acrefeet 
sediment reserve, 200,000 acre-feet irrigation and 167,000 
acre-feet flood control storage. The surface area of the 
reservoir at the spillway crest is 10,594 acres. The 
contributing drainage area at the dam site is 2,434 square 
miles. 
For a more detailed report of the authorized project including 
the modification to existing Sumner Lake see page 17-8 of 
fiscal year 1981 Annual Report. For authorizing legislation see 
page 17-14 of fiscal year 1981 Annual Report. 
Local cooperation. In addition to first costs, operation and 
maintenance of both reservoirs is the responsibility of the 
Federal Government; however, the Carlsbad Irrigation District 
is required to contribute to operation and maintenance costs an 
equal amount to what they now pay toward Sumner Lake. The 
Carlsbad Irrigation District also agreed to use Sumner Lake for 
flood control. Because they realize equivalent benefits from 
storage capacity in Santa Rosa Dam and Lake, they will 
continue to fulfill their repayment obligation. The New Mexico 
Division of Parks manages the recreation facilities. Activities 
include camping, picnicking, boating and hiking. 
For more requirements and details on final approval in 1974 
for transfer of irrigation storage from Sumner Lake to Santa 
Rosa Dam and Lake (formerly Los Esteros Lake) see page 17-5 
of Annual Report for 1980. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. The project was completed in 
late 1979 and reservoir operation for irrigation was started in 
March 1980. Pool elevation at the start of the fiscal year was 
4,743.83 feet with storage of 92,869 acre-feet. Total releases 
for the fiscal year were 74,026 acre-feet. Pool elevation on 
September 30, 1992 was 4,745.00 acre-feet with a storage of 
97,056 acre-feet. The maximum elevation was 4,745.58 feet 
with a storage of 99,181 acre-feet on August 21, 1992. There 
was 1,115 acre-feet of sediment deposition during the fiscal 
year. No flood damages were prevented in FY 1992. 
Sediment damages prevented during the fiscal year were 
$124,700. Releases attributed to irrigation benefits were 9,170 
acre-feet. Irrigation benefits for the fiscal year were $32,100 
with an accumulative total of $1,953,300 through FY 1992. 
Condition at end of fiscal year. Construction of the 
recreation area was completed in October 1980. Design studies 
for spillway modification were initiated in FY 1979 and 
construction was completed in FY 1982. A contract for 
replacing the main waterline servicing the project was awarded 
in FY 1991 and will be completed in the first quarter of FY 
1992. The project structures are in good condition and in 
operation. 
13. TRINIDAD LAKE, CO 
Location. This project is located on the Purgatorie River 
about 161 miles above its junction with the Arkansas River. The 
Project is about 4 miles upstream from the city of Trinidad, CO. 
(See Geological Survey map, Trinidad, CO, quadrangle, scale 
1:24,000.) 
Existing project. The project consists of an earthfill dam 
6,610 feet long with a maximum height of 200 feet above the 
streambed, an uncontrolled spillway 1,000 feet wide in the left 
abutment, and a 10-foot diameter, gate-controlled conduit in the 
right abutment with discharge capacity of 5,800 c.f.s. with a 
water surface at top of the flood control pool. In 1985, a 3-foot 
high parapet wall on top of the upstream face of the dam and a 
supplemental 700-foot wide rock cut emergency spillway located 
on the right abutment were constructed to provide adequate discharge 
capability and freeboard allowance to accommodate the 
revised probable maximum flood. The reservoir provides for 
storage of 63,698 acre-feet for flood control, 37,325 acre-feet for 
sediment, 20,000 acre-feet for irrigation, and 4,500 acre-feet for 
recreation, a total of 125,523 acre-feet. The reservoir controls 
a drainage area of 671 square miles and is operated for flood and 
sediment control, irrigation, and recreation purposes. For 
authorizing legislation see page 17-14 of fiscal year 1981 Annual 
Report. 
Local cooperation. Assurances of local cooperation received 
from City of Trinidad and Purgatorie River Water Conservancy 
District were formally accepted May 11, 1967, after execution of 
irrigation repayment contract. For complete details of 
requirements and costs pertaining to the execution of the 
irrigation repayment contract and the addition of permanent 
storage for recreation facilities see page 17-9 of fiscal year 1980 
Annual Report. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. On October 1, 1991 the pool 
32-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
elevation was 6,157.21 feet with a corresponding storage of 
9,614 acre-feet. The maximum pool elevation was 6,176.68 
feet with a corresponding storage of 19,559 acre-feet on April 
27, 1992. On September 30, 1992 the pool elevation was 
6,145.00 feet with a corresponding storage of 5,006 acre-feet. 
Sediment deposition during FY 1992 was 175 acre-feet. 
Sediment damages prevented during FY 1992 was $41,700. 
Accrued sediment benefits are $2,224,700. Irrigation benefits 
for FY 1992 were $92,000. Accrued irrigation benefits 
through FY 1992 were $1,516,700. Irrigation benefit releases 
for the year were 23,408 acre-feet. 
Conditions at end of fiscal year. The project was placed in 
operation in 1977. The recreation facilities were completed in 
1980. The Dam Safety Assurance Contract was completed in 
May 1983. The project structures are in good condition and in 
operation. 
14. TWO RIVERS DAM, NM 
Location. The project is located about 14 miles southwest of 
Roswell, NM on the Rio Hondo and the Rocky Arroyo. The 
Rio Hondo is formed at the confluence of the Rio Ruidoso and 
the Rio Bonito, near the village of Hondo, NM, in the foothills 
region east of Sierra Blanca in the southeastern part of Lincoln 
County, NM, and flows generally easterly to its confluence 
with the Pecos River near Roswell, NM. (See Geological 
Survey map, Hondo Reservoir quadrangle, scale 1:24,000.) 
Existing project. The Two Rivers project consists of two 
dams: Diamond "A" and Rocky. The Diamond "A" Dam is an 
earthfill structure, 4,885 feet long and 98 feet high, with a 
gated outlet. The Rocky Dam is an earthfill structure 2,940 
feet long and 118 feet high with an uncontrolled outlet. No 
provision is made for water storage, except for flood control. 
Flood releases will be controlled so that flows through Roswell 
will not exceed the Rio Hondo channel capacity which is about 
600 c.f.s. The capacity of the Two Rivers Reservoir at its 
spillway crest is 163,775 acre-feet, of which 13,775 acre-feet 
are provided for sediment reserve. Together these dams 
regulate runoff from 1,027 square miles of drainage area. For 
details of completed improvement and authorizing legislation 
see page 17-18 of Annual Report for 1973. 
Local cooperation. Section 2 Flood Control Act of 1938 
applies and compliance is satisfactory. 
Operations and results during fiscal year. Operation of the 
dam and reservoir continued. The reservoir was empty on 
October 1, 1991. There were no flood damages prevented 
during 1992. Sediment damages prevented were $46,400. 
Estimated total accumulated flood and sediment damages 
prevented through FY 1992 were $84,938,800. There were 414 
acre-feet of sediment deposition during FY 1992. The accrued 
sediment benefits through FY 1992 are $1,017,600. 
Condition at end of fiscal year. The project is complete and 
was placed in operation July 1963. The project structures are in 
good condition and in operation. 
15. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Included under this heading is inspection of completed flood 
control projects transferred to local interests for operation and 
maintenance. The projects in Texas, Colorado, and New Mexico 
were inspected. Federal costs for fiscal year 1992 were 
$144,019. 
16. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Pursuant to Section 7, Flood Control Act of 1944, five projects 
are operated by others for flood control. These projects are 
Platoro, Pueblo, Sumner, Navajo, and Brantley Dams. 
Platoro Dam on the Conejos River above the town of Platoro, 
Conejos County, CO controls runoff from 40 square miles of 
high mountain area. The authorized purposes are irrigation 
storage and flood control. Total storage is 59,571 acre-feet with 
the top 6,000 acre-feet solely for flood control. The 53,571 
acre-feet is joint use storage with flood control on a forecast 
basis during spring runoff. Platoro Dam was authorized by the 
Interior Appropriation Act of 1941. (See H Doc 693, 76th 
Cong., 3rd Sess.) Construction of this project was completed by 
the Bureau of Reclamation in 1952. 
On October 1, 1991 storage in Platoro Reservoir was 19,187 
acre-feet at elevation 9,981.51 feet. Maximum storage of 44,428 
acre-feet at elevation 10,017.25 feet occurred on June 30, 1992. 
On September 30, 1992, storage was 29,898 acre-feet at 
elevation 9,998.48 feet. Peak flow at Mogote gage was 2,210 
c.f.s. on August 24, 1992. There were no flood damages 
prevented by the project during FY 1992. Total flood damages 
prevented to date are at $4,507,500. Total cost for activity, by 
the Corps of Engineers during FY 1992 was $14,266. 
Pueblo Dam is part of the Fryingpan-Arkansas project which 
was authorized under Public Law 87-590, 87th Congress, HR 
2206 on August 16, 1962. The project was completed in August 
1975. Pueblo is operated by the Bureau of Reclamation and is 
located at river mile 1,293.7 on the Arkansas River in Pueblo 
County, Colorado. Pueblo Reservoir has 27,000 acre-feet 
exclusive flood space and 66,000 acre-feet joint use space. 
32-10

ALBUQUERQUE, NM, DISTRICT 
Operation of Pueblo Reservoir began on February 10, 1974. 
Storage on October 1, 1991 was 78,270 acre-feet, elevation 
4,824.42 feet. Maximum storage during the year was 168,083 
acre-feet at elevation 4,856.47 feet on April 1, 1992. Storage 
on September 30, 1992 was 103,776 acre-feet at elevation 
4,834.95 feet. There were $266,300 flood damages prevented 
in FY 1992. Total flood damages prevented to date are 
$3,600,600. Total cost for FY 1992 activity, by the Corps of 
Engineers, was $14,391. 
Sumner Dam is located on the Pecos River at river mile 
710.8 in DeBaca County, New Mexico. Sumner Dam was 
authorized as Alamogordo Dam by the Secretary of the Interior 
under a Finding of Feasibility approved by the President of the 
USA on 6 November 1935, under the Federal Reclamation 
laws. The original project was completed in 1937. Modification 
work of raising the dam 16 feet, adding a spillway and 
limiting the service spillway floor to 56,000 c.f.s. was 
completed in 1957. A twenty-four inch bypass line was 
installed in 1977 to pass flows less than 100 c.f.s. Storage on 
October 1, 1991 was 43,570 acre-feet at elevation 4,260.93 
feet. Maximum storage for FY 1992 was 64,038 acre-feet at 
elevation 4,267.30 feet on February 16, 1992. Storage on 
September 30, 1992 was 22,130 acre-feet at elevation 4,251.58 
feet. Total cost for FY 1992 activity, by the Corps of 
Engineers, was $12,913. 
Navajo Dam and Reservoir is located on the San Juan River 
at river mile 298.6 in San Juan County, New Mexico. Navajo 
Dam was authorized as part of a Colorado River Storage 
Project by an act of 84th Congress, 11 April 1956 (PL 485). 
The Bureau of Reclamation constructed and is responsible for 
operation of the project. Construction was initiated in June 
1958 and the project was completed and placed in operation in 
March 1963. Total capacity at spillway crest is 1,708,600 
acre-feet. The project controls a drainage area of 3,230 square 
miles. Storage on October 1, 1991 was 1,585,800 acre-feet, 
elevation 6,077.72 feet. Maximum storage for FY 1992 was 
1,644,300 acre-feet, elevation 6,081.62 feet on April 16, 1992. 
Storage on September 30, 1992 was 1,579,400 acre-feet, 
elevation 6,077.29 feet. Total Corps of Engineers cost for FY 
1992 activity was $22,179. 
Brantley Dam on the Pecos River above the town of Carlsbad 
in Eddy County, NM controls runoff from 13,208 square miles 
of uncontrolled area. The authorized purposes are irrigation, 
flood control, Fish and Wildlife and Recreation and for the 
elimination of the hazards of failure of the McMillan and the 
Avalon Dams. The total storage is 348,544 acre-feet with 
189,700 acre-feet for flood control. The Brantley Dam was 
authorized for construction on 20 October 1972 by Public Law 
92-514 with the cost ceiling raised for the project in October 
1980 by Public Law 96-375. On September 6, 1988 the 
conduits were closed and Brantley Dam started its initial filling. 
On September 30, 1992, the storage was 14,259 acre-feet at 
elevation 3,240.67 feet. Total Corps of Engineers cost for FY 
1992 activity was $44,874. 
17. OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
See Table 32-E. 
18. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, Public Law 
858, 80th Congress, as amended (preauthorization). 
Costs during FY 1992 were: Alamo Canyon, Alamogordo, 
NM, $5,542; Drake Arroyo, Socorro, NM, $1,589; Hobbs, NM, 
$32,171; Kistenmacher Arroyo, U.HGTS, SD., Las Cruces, 
NM, $17,951; Little Puerco River, Gallup, NM, $48,475; Oak 
Creek, Florence, CO, $23,294; Walnut Creek, San Antonio, 
NM, $458; Zuni River at Zuni, NM, $19,755. 
Emergency flood control activities; repair, flood fighting, 
and rescue work. (Public Law 99, 84th Cong., and 
antecedent legislation.) 
Federal costs for FY 1990 were $201,258 for advance 
preparation, none for flood emergency operations, and there were 
no repair and restoration costs. 
Emergency bank protection (Sec. 14, 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Alameda Street, Santa Fe, NM, $32,101; Pifion Bridge, 
Fountain Creek, CO, $72; Camino Alire Bridge, Santa Fe River, 
Santa Fe, NM, $20,108; Hampton Arroyo at McCoy Street, 
Aztec, NM; $220,583; Highway 62 Bridge, Santa Fe River, 
Santa Fe, NM, $13,764; Highway 75, Embudo Creek, Rio 
Arriba, NM, $6,104; I-25 Fountain Creek, Security, CO, 
$4,953; Overton Road, Fountain Creek, Pueblo, CO, $14,972; 
Santa Fe River, NM, $508; State Highway 194, Bents Old Fort, 
Arkansas Road, La Junta, CO, $13,645; Southern Boulevard, 
Black's Arroyo, Rio Rancho, NM, $19,821; Southmoor Drive, 
Fountain Creek, CO, $1,481; and State Road 12, Starkweather 
Road, Reserve, NM, $15,026. 
Snagging and Clearing for Flood Control (Section 208 of 
the 1954 Flood Control Act, 83rd Cong.) 
Costs during FY 1992 were: Gallinas River, City of Las 
Vegas, NM $5,468. 
32-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
General Investigations 
19. SURVEYS 
Costs for the fiscal year were $401,081 for flood damage 
prevention studies, $69,589 for special studies (coordination 
studies with other agencies). 
20. COLLECTION AND STUDY 
OF BASIC DATA 
Fiscal year costs were $232,256 for flood plain management 
and technical services. 
Hydrologic studies involving collection and study of basic 
data, such as stream flow data, collection of suspended 
sediment samples, recording rain gage data, special study for 
Pikes Peak flood warning systems, hydrometeorological studies, 
sedimentation studies, and environmental data studies continued. 
Costs during the fiscal year were $4,647. 
21. CONTINUATION OF PLANNING AND 
ENGINEERING 
Continuation of Planning and Engineering costs in FY 1992 
were $268,434. 
22. ADVANCE ENGINEERING AND 
DESIGN 
Advance Engineering and Design Costs for FY 1992 were 
$1,169.00. 
TABLE 32-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
1. Acequias Irrigation New Work 
System, NM 
Alamogordo, NM 
Alamosa, CO 
Cochiti Wetfields, NM 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
2,000,000 200,000 1,972,000 
1,142,950 1,323,966 1,403,995 
200,000 
44,385 
291,723 
155,641 
299,233 
364,930 
230,000 
209,013 
259,000 
242,776 
851,000 
1,245,399 
6,701,000' 
5,595,573' 
241,000 2,259,000 
250,751 2,227,525 
270,000 
268,438 
- 300,000 
15,939 206,200 
529,0002 
511,2142 
1,050,0003 
952,8403 
32-12 
4.

ALBUQUERQUE, NM, DISTRICT 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
Albuquerque 
Diversion Channels 
Project, NM 
(Federal Funds) 
(Contributed Funds) 
(Other Contributed 
Funds) 
Conchas Lake, NM 
El Paso, TX 
Fountain Creek 
Pueblo, CO 
John Martin 
Reservoir 
10. Puerco River, 
Gallup, NM 
5. 
181,000 
111,811 
95,000 17,845,450 
88,537 17,769,798 
518,356 
518,356 
854,664 
854,664 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
894,725 
942,571 
879,000 
891,397 
- 13,821,4994 
- 13,821,4994 
1,044,000 17,877,519 
901,113 17,714,596 
3,206,000 3,483,000 2,138,000 6,095,000 75,266,2945 
3,056,377 1,276,426 4,869,596 6,021,890 74,522,394 s 
3,032,000 200,000 
4,673,143 367,812 
160,000 
7,463 
- 6,570,0006 
190,341 6,564,2856 
S- - - 15,555,3587 
S- - - 15,555,3587 
2,010,500 1,297,295 1,687,400 1,527,826 22,119,218 
2,176,195 1,259,238 1,738,677 1,460,533 22,117,377 
2,792,000 1,434,000 225,000 
396,592 3,277,977 758,598 
- 4,701,00089 
22,745 4,677,1058.9 
32-13 
TABLE 32-A 
(Continued) 
903,300 
886,032 
6. 
8. 
9.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 32-A COST AND FINANCIAL STATEMENT 
(Continued) 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
11. Rio Grande Basin, NM 
Abiquiu Dam, NM 
Cochiti Lake, NM 
Galisteo Dam, NM 
Jemez Canyon 
Dam, NM 
Middle Rio Grande 
Flood Protection, 
Bernalillo to Belen, NM 
Rio Grande Floodway 
Rio Grande Floodway, 
San Acacia to Bosque 
del Apache, NM 
Rio Grande Floodway 
T or C Unit, NM 
11A. 
11B. 
- - - - 26,745,028 
- - - - 26,745,028 
3,864,200 2,434,626 1,035,000 1,550,100 27,648,253 
3,974,747 2,128,878 1,216,334 1,618,868 27,587,381 
- - - - 97,084,559 
- - - - 97,084,559 
1,266,200 1,159,945 1,587,000 1,791,900 17,937,967 
1,454,062 1,065,137 1,540,779 1,699,299 17,702,379 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
179,948 
164,243 
193,000 
209,635 
- 14,275,053 
- 14,275,053 
171,000 2,521,924 
162,257 2,512,468 
6,293,972 
6,293,972 
371,800 635,281 
370,477 575,245 
49,099 
10,000 
25,631 
430,000 
489,518 
50,000 
40,697 
723,000 7,983,632 
458,915 7,717,407 
200,000 1,437,00010 
132,037 1,359,73410 
4,794,868" 
4,794,868" 
250,000 317,000 351,000 
412,292 359,626 380,527 
3,422,000 3,600,000 4,042,000 
772,829 4,575,047 5,219,452 
450,000 2,108,00012 
389,372 2,047.37212 
180,000 13,005,000'"'4 
573,136 12,880,2691314 
32-14 
211,600 
215,037 
11C. 
11D. 
liE. 
11F. 
11G. 
11H.

ALBUQUERQUE, NM, DISTRICT 
TABLE 32-A COST AND FINANCIAL STATEMENT 
(Continued) 
See Total Cost 
Section to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sept. 30, 1992 
12. Santa Rosa Dam New Work 
& Lake, NM Approp. - -1,821 - - 41,039,741 
Cost -660 - - - 41,039,056 
Maint. 
Approp. 731,600 597,936 787,000 769,000 7,260,136 
Cost 750,828 505,525 870,253 754,693 7,236,491 
13. Trinidad Lake, CO New Work 
Approp. - - - - 55,774,758 
Cost - - - - 55,774,758 
Maint. 
Approp. 363,500 519,429 465,000 557,000 6,685,529 
Cost 374,903 464,825 514,772 523,991 6,645,530 
14. Two Rivers Dam, New Work 
NM Approp. - - - - 4,847,244 
Cost - - - - 4,847,244 
Maint. 
Approp. 280,300 246,409 418,000 171,000 3,819,722 
Cost 290,782 277,087 363,255 237,213 3,810,772 
'Reflects PED funding appropriations beginning in FY 1986. 
include non-Federal contributions of $1,529,000. 
2PED activities were initiated in FY 1991. 
3Includes $750,000 FY 88 Construction General Funds and 
$300,000 O&M funds, added in FY 1992. 
4Includes $3,492,696 maintenance and improvement costs and 
$869,978 for emergency relief, excludes $2,279,326, cost of 
initiating project under the authority of Emergency Relief Appropriation 
Act of 1935 and $222,669, the cost for work 
performed with funds transferred to the Corps under Public 
Works acceleration Act of 1962. 
5Does not include non-Federal contributions of $1,130,000. 
6Does not include non-Federal contributions of $1,295,000. 
'Excludes $59,977 emergency relief funds for new work. 
Includes $30,000 for Code 710. 
8Reflects PED funding appropriations beginning in FY 1986. 
Does not include $1,397,000 non-Federal contribution. 
9FY 1986 PED funds were appropriated to and expended by 
Los Angeles District. 
'�Includes $1,177,000 PED funds. 
"Includes funds for preconstruction planning of Espanola Valley 
unit. Excludes $1,000,011 appropriated funds transferred to 
Bureau of Reclamation under memorandum of agreement 
between that agency and the Corps. 
12Includes $1,658,000 PED funds. 
"3Starting in FY 1982, AE&D programs are funded through GI 
appropriations. 
14Does not include non-Federal contributions of $3,425,000. 
32-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 32-B AUTHORIZING LEGISLATION 
See 
Section 
TIn Tevt 
Date 
Authorizing 
Act 
Nov. 17, 1986 
Oct. 31, 1992 
Aug. 26, 1992 
Oct. 27, 1965 
Nov. 17, 1986 
Nov. 17, 1986 
1. 
32-16 
3. 
4. 
8. 
10. 
111 1 I AI Project and Work Authorized 
ACEQUIAS IRRIGATION SYSTEM 
An Irrigation System dating back to the eighteenth century with 
significant engineering works in the settlement and development of the 
western portion of the United States. Restoration and preservation of this 
system has cultural and historic values to the region. Measures are 
necessary to restore and protect the river division structures and 
associated canals. 
ALAMOSA, COLORADO 
Authorized a flood control project for Alamosa, Colorado. 
COCHITI WETFIELDS, NEW MEXICO 
Authorized and directed the construction of an underground drainage 
system necessary to correct the high ground water problem at the Pueblo 
de Cochiti. 
EL PASO, TX 
A single-purpose flood control system of detention dams, diversion 
dikes and channels to collect, regulate and discharge arroyo runoff in the 
Rio Grande. Consists of four independent units (NW Area, Central 
Area, and two units, Copper System and Bluff Channel of the SE Area.) 
FOUNTAIN CREEK, PUEBLO, CO 
Channel improvements and levee construction on both sides of 
Fountain Creek approximately 1 mile above the confluence of the 
Arkansas River and Fountain Creek. 
PUERCO RIVER, GALLUP, NM 
Channel rectifications, improvement of existing levees and construction 
of new levees on both sides of Rio Puerco in the city of Gallup, NM. 
Documents 
Public Law 662, 
99th Cong., 2nd 
sess. (Sec. 1113) 
Public Law 102-580 
102d Congress 
(Sec. 101) 
Public Law 102-358 
102d Cong, 
(H.R. 4437) 
H. Doc. 207, 89th 
Cong., 1st 
sess.' 
Public Law 662, 
99th Cong. 2nd 
sess. 
Public Law 662, 
99th Cong., 2nd 
sess.

ALBUQUERQUE, NM, DISTRICT 
TABLE 32-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
11. Jun. 30, 1948 
May 17, 1950 
Jul. 14, 1960 
Nov. 17, 1986 
Nov. 17, 1986 
Jun. 30, 1948 
and 
May 17, 1950 
Oct. 31, 1992 
RIO GRANDE BASIN, NM 
Authorized to be appropriated $3,500,000 to be expended by the 
Dept. of the Army for partial accomplishment of approved general 
comprehensive plan for the Rio Grande Basin in NM and Colorado. 
Authorized to be appropriated an additional $39,000,000 for 
Department of the Army for prosecution of comprehensive plan for the 
Rio Grande Basin. 
Authorized Cochiti Dam on Rio Grande and Galisteo Dam on 
Galisteo Creek as additions to authorized comprehensive plan for Rio 
Grande Basin (Cochiti Dam was authorized in lieu of Low Chamita 
Dam of Chamita Reservoir Project on Rio Chama under "substitute 
plan"). Also authorized to be appropriated an additional $58,300,000 
for Dept. of the Army for this addition to comprehensive plan for the 
Rio Grande Basin. 
Authorized installation of the Abiquiu Dam Emergency Gates by 
the Water Resources Development Act of 1986 (PL 99-662) 
MIDDLE RIO GRANDE FLOOD PROTECTION, 
BERNALILLO TO BELEN, NM 
Authorized project for flood control, Middle Rio Grande Flood 
Protection, Bernalillo to Belen, NM. Authorized increase of flood 
protection through the dredging of the bed of the Rio Grande in the 
vicinity of Albuquerque, NM to an elevation lower than existed on the 
date of enactment of this Act. The project shall include the 
establishment of 75 acres of wetlands for fish and wildlife habitat and 
the acquisition of 200 acres of land for mitigation of fish and wildlife 
losses. 
RIO GRANDE FLOODWAY, NM 
Channel rectification, levee enlargement and construction, and 
bank stabilization on Rio Grande between river mile 123 and 394 (San 
Acacia to Bosque Del Apache Unit.) 
RIO GRANDE FLOODWAY, SAN ACACIA TO 
BOSQUE DEL APACHE UNIT, NM 
Modified the cost sharing to more equitably reflect the non-Federal 
contribution for the project by that percentage of benefits which 
is attributable to the Federal properties; except that, for purposes 
of this subsection, Federal property benefits may not exceed 50 percent 
of the total project benefits. 
32-17 
H. Doc. 243, 81st 
Cong.,1st sess. 
Public Law 516, 
81st Cong., 2nd 
sess. 
S. Doc. 94, 86th 
Cong. 
Public Law 662 
99th Cong., 2nd 
sess. 
Public Law 662, 
99th Cong., 2nd 
sess. 
Cong., 1st sess.' 
and Public Law 
516, 81st Cong., 
2nd sess. 
Public Law 102-580 
102d Congress 
(Sec. 102(e)) 
11lE. 
11F. 
11G.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 32-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
In Text Act Project and Work Authorized Documents 
11H. Jun. 30, 1948 TRUTH OR CONSEQUENCES UNIT, NM H. Doc. 243, 81st 
Approved comprehensive plan for Rio Grande Basin is set forth Cong., 1st sess. 
in the Report of the Chief of Engineers dated April 15, 1948, for flood 
control of Rio Grande Basin. 
May 17, 1950 In addition to previous authorizations, the completion of the plan H. Doc. 243, 81st 
approved in the Flood Control Act of 1948, for the Rio Grande Basin, Cong., 1st sess. 
at an estimated cost of $39,000,000. 
Nov. 17, 1986 Modify previous authorizations to provide that the Secretary is Public Law 662, 
authorized to construct a flood control dam on Cuchillo Negro Creek 99th Cong., 2nd 
in lieu of the authorized floodway. sess. (Sec 871) 
'Contains latest published maps. 
RIO GRANDE BASIN, NM 
TABLE 32-C RIO GRANDE BASIN, NM: EXISTING PROJECT 
(See Section 8 of Text) 
Miles Drainage Total 
Above Nearest Area (square Estimated 
Project River Mouth Town mile) Description Cost 
Abiquiu Dam Rio Chama 32 Espanola, 2,147 Earthfill 325 feet high, 30,397,0963 
NM 1,212,000 
acre feet capacity 
Jemez Canyon Jemez Dam 2 Bernalillo, 1,034 Earthfill 136 feet high, 106,100 4,217,206 
NM acre-feet capacity 
Rio Grande Rio Grande 123 - - Channel rectification, levee 25,744,0002 
Floodway to 394' enlargement and 
construction 
Cochiti Lake Rio Grande 340' Cochiti, NM 11,695 Earthfill 251 feet high, 596,300 96,900,000 
acre-feet capacity 
Galisteo Dam Galisteo Creek 8 Waldo, NM 596 Earthfill 158 feet high, 89,000 14,340,280 
acre-feet capacity 
'River mile 0 is at intersection of New Mexico-Texas State Line with international boundary at El Paso, Texas. 
2Does not include non-Federal costs. 
3Includes $5,383,000 major rehabilitation, $138,900 for recreation facilities and $3,600,000 for emergency gates. 
32-18

ALBUQUERQUE, NM, DISTRICT 
TABLE 32-D OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1990 
Full Report 
See Annual Operation & 
Project Report For Construction Maintenance 
Alamogordo Diversion Channel, Tularosa (closed) Basin, New Mexico 1966 189,356 - 
Alpine, Texas3 1977 130,488 - 
Cibolo Creek, Texas' 1983 829,500 
Colorado Springs, Fountain que Bouille River, Colorado 
(Templeton Gap Floodway)' 1959 881,262 - 
Creede, Willow Creek, Colorado (floodway)' 1952 219,789 - 
Highway 12, Colorado' 1985 120,500 - 
Holly, Colorado' 1985 2,021,400 - 
Las Animas, Colorado2 1980 4,956,000 - 
Las Cruces, New Mexico2 1980 4,815,236 - 
Pecos, Texas3 1977 480,273 - 
Pinon Canyon Dam, Trinidad, Colorado (Sec.212)' - 130,678 - 
Pueblo, Arkansas River, Colorado (floodway levee extension)' 1954 201,958 - 
Santa Fe River and Arroyo Mascaras, New Mexico3 1983 1,123,900 - 
Smith Creek, Colorado' 1985 219,000 - 
Socorro Diversion Channel, Tributaries of Rio Grande, New Mexico' 1965 2,259,328 - 
'Completed. 2Responsibility of local interests. 3 'Inactive. 4Deferred. 
32-19

LOS ANGELES, CA, DISTRICT* 
This district (total area about 230,000 square miles) 
comprises those drainage basins tributary to the Pacific 
Ocean that are in California between the Mexican 
boundary and Cape San Martin (about 265 Miles north 
of the entrance to the Los Angeles Harbor). The lower 
Colorado River drainage basin (below Lee Ferry, AZ.) 
which is southeastern California, southeastern Nevada, 
southwestern Utah, and all of Arizona, except the 
northeastern corner; that part of the Great Basin that is 
in southern Nevada and southeastern California;and the 
southern Arizona that drain southward into Mexico. 
IMPROVEMENTS 
Navigation 
1. Channel Islands Harbor, CA 
2. LA-LB Harbor, CA 
3. Marina Del Rey, CA 
4. Morro Bay Harbor, CA 
5. Oceanside Harbor, CA 
6. Oceanside Sand By-pass, CA 
7. Port Hueneme, CA 
8. Redondo Beach Harbor (King Harbor), CA 
9. San Diego Harbor, CA 
10 San Diego River & Mission Bay, CA 
11. Santa Barbara Harbor, CA 
12. San Luis Rey River, CA 
13. Ventura Harbor, CA 
14. Reconnaissance and Condition Surveys 
Flood Control 
15. Cucamonga Creek, Santa Ana River Basin, CA 
16. Gila River Basin, AZ 
16A Painted Rock Dam (Gila River), AZ 
16B Phoenix, AZ, and Vicinity (Stage 2) 
17. Los Angeles County Drainage Area, CA 
18. Los Coches Creek, CA 
19. Lytle & Warm Creeks, Santa Ana Basin, CA 
20. Mojave River Dam, Mojave River Basin, CA 
21. Pine & Mathews Cnyns Dam, Colo River Basin, NV 
22. Santa Ana Mainstem, CA 
23. Santa Ana River Basin and Orange County, CA 
24. Whitewater River Floodwarning, San Bernadino & 
Riverside County, CA 
25. Inspection of Completed Flood Control Projects 
26. Scheduling Flood Control Reservoir Operations 
27. Flood Control work under Special Authorization 
Page 
33-02 
33-02 
33-02 
33-03 
33-03 
33-03 
33-03 
33-04 
33-04 
33-04 
33-04 
33-05 
33-05 
33-05 
33-05 
33-05 
33-05 
33-06 
33-06 
33-06 
33-06 
33-06 
33-07 
33-07 
33-07 
33-07 
33-07 
33-08 
33-08 
General Investigations Page 
28. Surveys 33-08 
29. Collection and Study of Basic Data 33-08 
30. Research and Development 33-08 
Preconstruction, Engineering & Design 
31. Carneros Creek, CA 33-08 
32. Clifton, AZ 33-09 
33. Hansen Dam, CA 33-09 
34. Holbrook, AZ 33-09 
35. Lake Elsinore, CA 33-09 
36. Lower Mission Creek 33-09 
37. Lower Santa Cruz, AZ 33-10 
38. Nogales Wash, AZ 33-10 
39. Rillito, AZ 33-10 
40. Santa Ana River Mainstem, CA 33-10 
41. Santa Paula Creek, CA 33-11 
42. Sweetwater River Basin, CA 33-11 
43. Tropicana and Flamingo Washes, NV 33-11 
Tables 
Table 33-A Cost and Financial Statement 33-12 
Table 33-B Authorizing Legislation 33-16 
Table 33-C Other Authorized Navigation Projects 33-28 
Table 33-D Other Authorized Beach Erosion Control Project 33-29 
Table 33-E Other Authorized Flood Control Projects 33-31 
Table 33-F Not Applicable 
Table 33-G Deauthorized Projects 33-32 
33-1 
'it . 
.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
Navigation 
1. CHANNEL ISLANDS HARBOR, 
CA 
Location: On the coast of southern California about a 
mile northwest of Port Hueneme, 65 miles northwest 
of Los Angeles Harbor, and 345 miles south of San 
Francisco. (See Coast and Geodetic Survey Charts 
5007 and 5202). 
Existing project: For details see page 33-2 of Annual 
Report for 1981. 
Location cooperation: Fully complied with. 
Terminal facilities: For details see page 33-2 of 
Annual Report for 1989. 
Operations during fiscal year. Began maintenance 
dredging. 
2. LOS ANGELES AND LONG 
BEACH HARBORS, CA 
Location. On coast of southern California in San 
Pedro bay about 25 miles south of the City of Los 
Angeles, about 96 miles northwest of San Diego 
Harbor, and about 410 miles southeast of San 
Francisco Harbor. 
Previous projects. For details see page 1977 of 
Annual Report for 1915 and page 1646 of Annual 
Report 1984. 
Existing project. For Details, see page 33-3 of Annual 
Report for 1984. 
Local cooperation. All items of local cooperation 
required under the terms of the previous authorizing 
acts have been fully complied with. See page 33-3 of 
Annual report for 1981 for requirements under the 
terms of the 1976 Water Resources Development act. 
The revised recommended project has changed due to 
the withdraw of the Port of Long Beach. The Port of 
Los Angeles might receive credit, contingent upon the 
Secretary of the Army's approval, for advance work 
performed per WRDA 88 (Sec. 4d). 
Terminal Facilities. In Los Angeles Harbor, 82,553 
feet of wharves, if which 75,729 feet are owned by 
the city and 6,824 feet are owned by private interest, 
In Long Beach Harbor, 58,985 feet of wharves, if 
which 51,775 feet are owned by the city and 7,210 
feet are owned by private interests. In Long Beach 
Harbor, Federal Government owns 19,700 feet of 
waterfront inside the Navy Mole, exclusive of finger 
piers. The Final report presented four project 
increments. Increment No. 2 would deepen the 
existing Los Angeles Harbor approach and entrance 
channels to Pier 300 to provide better access to dry 
bulk facilities. Increment No. 3 would further deepen 
the Los Angeles approach and entrance channel to Pier 
300 and part of Pier 400, and deepen a south channel 
to provide access to the eastern side of Pier 400 and 
liquid bulk facilities. Increments No. 4 & 5 would 
extend Increment No. 3 of Los Angeles to provide 
access to container terminals that would be located on 
part of Pier 300 and pier 400. 
3. MARINA DEL REY, CA. 
Location. Marina Del Rey is located on Santa Monica 
Bay, 15 miles west of downtown Los Angeles, 29 
miles northwest of Los Angeles Harbor and 390 miles 
southeast of San Francisco Bay . 
Existing Project. For details see page 33-3 of Annual 
Report for 1981. 
Local Cooperations. Fully complied with. 
Terminal Facilities. Approximately 5,797 permanent 
slips and end ties are located in the marina. There are 
28 additional transient slips located at Chace Park. A 
Coast Guard Station with a permanently assigned 82- 
foot cutter; a firefighting detachment with a fire boat, 
a pumper, a ladder truck; and a Sheriff's Harbor Patrol 
with five patrol boats and five auxiliary vessels are on 
24-hour duty. A fuel dock is located on the west side 
of the main channel. A 10-lane public launching ramp 
with parking for 740 cars and trailers; dry storage for 
396 trailer-borne boats; and several commercial hoists 
are in operation as well as two haul-out yards, one 
containing a 100-tone and a 60-ton marine travel lift. 
Six hotels, 14 public parking lots, 26 restaurants, 19 
apartment complexes, a ship chandlery, a fisherman's 
village shopping and tourist center, 26 restaurants, 
several snack bars, five coffee shops, and eight yacht 
clubs called the marina home port. Also included are 
sailing instruction, boat rental, repair and storage, 
33-2

LOS ANGELES, CA, DISTRICT 
harbor tours, sportfishing, yacht clubs, and retail 
facilities. 
Operations during fiscal year. The Corps is 
completing a study analyzing present and project boat 
traffic conditions in Marina Del Rey. The study was 
prepared to evaluate the potential impacts of expansion 
of additional slips into the existing Federal channel. 
Sediment analysis preparatory to maintenance dredging 
was completed. 
4. MORRO BAY HARBOR, CA 
Location. On coast of southern California 110 miles 
south of Monterey Bay 120 miles northwest of Santa 
Barbara Harbor, and nearly midway between San 
Francisco and Los Angeles. ( see Coast and Geodetic 
Survey Chart 5387). 
Existing Project. For details, see page 33-4 of Annual 
Report for 1980. 
Local cooperation. The City of Morro Bay. 
Terminal facilities. Facilities which are adequate for 
existing commerce, comprise 640 feet of existing piers 
and 150 feet of floating docks constructed by San Luis 
Obispo County; 263 feet of floating docks constructed 
by California Department on Parks and Recreation; 
1,396 feet of floating docks constructed by the city of 
Morro Bay; 1,398 feet of privately owned piers; and 
5,435 feet of privately owned floating docks. 
Operations during the fiscal year. Performed 
maintenance dredging. 
5. OCEANSIDE HARBOR, CA 
Location. On the coast of southern California at 
Oceanside, about 30 miles north of City of San Diego 
and 80 miles south of Los Angeles. 
Existing project. For details, see page 33-4 of Annual 
report for 1981. 
Local cooperation. Fully complied with. 
Terminal Facilities. Berthing for 957 boats, single-tie 
slips, 38 double-tie slips and 136 side-ties, of which 54 
are visitors' slips); 12 dry storage spaces at Oceanside 
Marine Center; a fuel dock; a boat hoist; a launching 
ramp, which can accommodate 4 launchings at the 
same time; parking for 1,732 cars; with temporary 
parking for about 141 boat trailers; a boat-repair 
facility; a pump-out facility; a Coast Guard cutter; 
restaurants; retail stores; yacht brokers; a boatel/motel; 
condominiums; and a sport-fishing facility. 
Operations during the fiscal year. DM completed Aug 
92. Draft P&S submitted to SPD Oct 92. Dredging 
contract scheduled for award Aug 93. 
6. OCEANSIDE HARBOR SAND 
BYPASS, CA 
Location. On the coast of southern California along 
Oceanside Beach near Jetty, about 30 miles north of 
City of San Diego and 80 miles south of Los Angeles. 
Existing project. Underwater experimental pumping 
system with het pumps, fluidizers, and submerged 
pipeline to remove sand from harbor entrance and 
deposit it to downcoast beaches, on a continual basis. 
Phase I and Phase II have both been completed and 
successfully tested. Phase II evaluation was prepared 
after data was available from the first full year of Phase 
II operation (Sept 92). Final completion (Phase III) is 
scheduled for FY94 and will be designed to maximize 
the system's production, complete the experiment, and 
evaluate the ultimate effeteness that the bypassing 
technology has on maintaining the harbor channel. 
Local cooperation. Fully complied with. We have 
currently been asked to further evaluate the 
compatibility of the Bypass system with the authorized 
Harbor Improvement Project before finalizing the 
Evaluation Report. 
7. PORT HUENEME, CA 
Location. On the coast of southern California about 
65 miles northwest of Los Angeles and Long Beach 
Harbors. about one mile southeast of Channel Islands 
Harbor, immediately west of the City of Port Hueneme, 
four miles southwest of the City of Oxnard, and 10 
miles southeast of the City of Ventura. 
Existing project. Authorized in 1968, The harbor 
serves both military and commercial uses with port 
facilities consisting of terminals, wharves, and 
33-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
warehouses servicing a wide variety of products. The 
existing Federal project consists of an approach 
channel, entrance channel, central basin, and two 
rubblemound jetties. 
Local cooperation. Requirements are described in full 
on page 33-3 of Annual Report for 1976. The Oxnard 
Harbor District expressed strong support of the study 
8 Dec 92. 
Operations during the fiscal year. None. 
Local cooperation. Requirements are described in full 
on pages 33 to 35 of Annual Report for 1980. 
Terminal facilities. Consist of 45,070 feet of 
wharves, exclusive of Government-owned and 24,000 
feet are privately owned. Government-owned wharves 
at North Island are restricted to military use only. 
Operations during fiscal year. Performed 
hydrographic condition survey of the Federal navigation 
channels in September 1992. 
8. REDONDO BEACH HARBOR 10. SAN DIEGO RIVER & MISSION 
(KING HARBOR), CA BAY, CA 
Location. On the coast of southern California on the 
southern portion of Santa Monica Bay, about 17 miles 
northwest of Los Angeles. 
Existing project. For details, see page 33-4 of Annual 
Report for 1981. WRDA of 86 (H.R. 6) Conference 
bill, Title VIII - Project Modification, Sec 809 - King 
Harbor, Redondo Beach, CA Modifies the King Harbor 
project in order to carry out maintenance dredging & 
for breakwater construction, & authorized the 
Secretary to restore the breakwater to a height of 22-ft 
& maintain breakwater at such height to provide 
greater protection from heavy wave action. 
Local cooperation. City of Redondo Beach officials 
are in full support of the study and have indicated 
desire to construct improvements to reduce continued 
storm related damages. 
Operations during fiscal year. Construction contract 
for the modifications was completed. 
9. SAN DIEGO HARBOR, CA 
Location. On the coast of southern California just 
north of the Mexican border, about 109 miles 
southeast of Los Angeles and Long Beach Harbors. 
(See Coast and Geodetic Survey Chart 5107). 
Previous projects. For details, see page 1976 of 
Annual Report for 1915 and page 1642 of Annual 
Report for 1938. 
Existing project. For details, see pages 33 and 34 of 
annual Report for 1980. 
Location. The San Diego River has its source on the 
tableland in the Cuyamaca Mountains near Santa 
Ysabel, CA, and flows southwestward 52 miles to the 
Pacific Ocean, 6 miles northwest of San Diego. 
Mission Bay Harbor is adjacent to the outlet of the San 
Diego River, 77 miles southeast of Los Angeles and 
Long Beach Harbors. The Bay has a perimeter of about 
11 miles and area of about 2,00 acres. 
Existing project. For details, see page 33-3 of Annual 
report for 1991. Authorized work consisted of Levied 
channel, entrance channel, main channel, altered 
railroad bridge, Anchorage Basins (West Anchorage & 
Quivira) and three jetties. Re-evaluation of 
constructing a WEIR in middle jetty. 
Local cooperation. Letter dated February 1989 from 
the city of San Diego stated desire to proceed on weir 
based on cost-sharing requirements of WRDA 86. The 
City desires Federal assistance for improvements to 
reduce storm damage potential and shore erosion in 
Mission Bay area. 
Operations during the fiscal year. New disposal 
location for rock removed from middle jetty required 
supplemental environment assessment & approvals 
from resource agencies & CA Coastal Commission. 
11 SANTA BARBARA HARBOR, CA 
Location. On the coast of southern California, 90 
miles northwest of Los Angeles Harbor. 
Existing Project. For details on original, see page 33- 
4 Annual Report for 1983. For re-evaluation details see 
33-4

LOS ANGELES, CA, DISTRICT 
WRDA, 1986. Recommended plan includes acquiring 
a dredge for the City and they will assume the 
maintenance of the channel. 
Local cooperation. See page 1015 of Annual Report 
for 1969 for items of local cooperation under 1962 
authorized modification of existing project. The City 
reaffirmed its support Nov 90. 
Operations during fiscal year. Performed maintenance 
dredging. PGM received 4 Mar 92. Revised Dft Rpt 
submitted 2 Oct 92 Awaiting approval from 
HQUSACE. 
12. SAN LUIS REY RIVER, CA 
Location. Along the lower 7.2 miles of the river, in 
and around the city of Oceanside, San Diego County, 
about 86 miles south of Los Angeles. 
Existing project. A double levee, 5.4 miles long; 
stone protected channel with a soft bottom; 1,330 feet 
of parapet walls at the ocean on the north and south 
levees; six interior drainage ponds; and a five-mile bike 
trail. 
Local cooperation. Fully complied with. 
Operations during fiscal year. Completed plantings 
for the forty-two acre mitigation plan for the 
endangered species, least bell's vireo. 
13. VENTURA HARBOR, CA 
Location. Located 65 miles northwest of Los Angeles 
and 6 miles northwest of Channel Island Harbor. 
Existing project. For details, see page 33-5 of the 
Annual Report for 1981. Re-evaluation under WRDA 
1990 consists of modification to the exiting harbor by 
constructing a separate South Beach groin, extending 
the offshore breakwater, adding a spur groin to the 
north jetty, and deepening and extending the entrance 
channel and sand trap. 
Local cooperation. LCA scheduled to be executed 
Apr 93. Construction contract scheduled for award in 
July 93. 
Operations during fiscal year. Project condition is fair; 
hydro survey performed Apr 92. Plans and Spec 
completed Jun 92. 
14. RECONNAISSANCE AND 
CONDITION SURVEYS 
Flood Control 
15. CUCAMONGA CREEK, SANTA 
ANA RIVER BASIN, CA 
Location. In and near the cities of Upland, Rancho 
Cucamonga, and Ontario, and the communities of Alta 
Loma and San Antonio Heights, San Bernardino and 
Riverside Counties, Ca. 
Existing project. For details, see page 33-5 of the 
Annual Report for 1987. 
Local cooperation. Requirements are described in full 
on Annual Report for 1981. 
16. GILA RIVER BASIN, AZ 
16A. PAINTED ROCK DAM (GILA 
RIVER), AZ. 
Location. About 20 miles northwest of Gila Bend, 
and 120 miles southwest of Phoenix, AZ. 
Existing Project. For details, see page 33-9 of Annual 
Report for 1981. 
Local Cooperation. Requirements are described in full 
on 33-9 of Annual Report for 1981. 
Operations during fiscal year. Project condition is 
good. Releases into the downstream unimproved 
channel are predicated upon the amount of water in 
storage and the amount of damages occurring 
downstream. Downstream interests have made 
substantial improvements to bridges and crossing, 
which will allow larger releases than in the past. We 
still cannot follow the schedule of release without 
consideration for downstream damages. 1 Recreation 
Area (downstream at borrow pit area) has been closed 
due to high levels of pesticide contamination in the Gila 
River system. 
33-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
16B. PHOENIX, AZ, AND VICINITY 
(INCLUDING NEW RIVER) (STAGE 2 
AND REMAINING WORK) 
Location: Project located in Maricopa County, AZ, 
adjacent to metropolitan Phoenix, AZ. 
Existing Project: For details see Annual Report FY91 
page 33-7. Map of Modified plan is in "Design 
Memorandum No.3, General Design Memorandum- 
Phase I, plan Formulation for New River and Phoenix 
City Streams, Arizona," Prepared by Los Angeles 
District in March 1981. 
Local Cooperation: Requirements are described in full 
on page 33-9 Annual Report for 1981. LCA relating to 
covered channel executed 8 July 92. 
Operations during fiscal year. LOA executed with 
Ariz State University on 15 Jun 92. Heavy rains on 23 
Jul 92 caused some damage to ACDC. Most damage 
occurred on north side between Central Ave and 7th 
St. Some deflection of wall occurred, and some base 
of maintenance road washed away with accompanying 
collapse of asphalt pavement. Cause determined to be 
due, in part, to a storm drain pipe, flowing full, that 
disconnected from wall. Investigation is underway, 
with assistance from independent consulting engineer. 
Temporary repair completed and road opened to traffic. 
DRAINAGE AREA, CA 
Location: Along Los Angeles and San Gabriel Rivers, 
Rio Hondo, and Ballona Creek, and tributaries thereof 
in Los Angeles County, CA. 
Previous Project: For Details, see pages 1768 to 
1772 of Annual Report for 1942; page 1602 of Annual 
Report for 1942; and page 1535 of Annual Report for 
1943. For details on units see Annual Report for 1962. 
For details on re-evaluation see Annual Report for 
1991. 
Existing project: Project will consist of channel 
improvement to Lower Los Angeles & Rio Hondo Rivers 
& Compton Creek and modification/replacement of as 
many as 27 Bridges necessitated by the channel 
improvements. A map of the rehabilitation plan is in 
"General Design Memorandum, Los Angeles River 
Rehabilitation under the Major Rehabilitation Program," 
dated January 1984 and revised in March 1984. 
Local cooperation: The Los Angeles County 
department of Public Works has actively participated in 
extensive briefings for Rep of Los Angeles County 
Board of Supervisors and most of the affected 
Congressmen. They reaffirmed support Feb 92. 
Operations during fiscal year. Model tests are 
(underway at WES) critical to schedule determining 
overall plan. 
18. LOS COCHES CREEK, CA 
Location. In the community of Lakeside, San Diego, 
County, CA 
Existing Project. Plan provides for a 1.8 mile-long 
rectangular concrete channel; an inlet structure just 
downstream from the Los Coches and Ha-Hana Roads; 
and an outlet structure at the confluence of the San 
Diego River. Plan also provides for 5 double box 
culverts and 1 triple box culvert. 
Local cooperation. Requirements are described in full 
on page 33-8 of Annual Report for 1985. 
1 IVI ANl WAIARM CREEKS, 
Location: Near San Bernardino and Colton, San 
Bernardino County, CA. 
Existing project: Authorized project was modified by 
Design Memorandum No. 1, approved in May 1972, 
which contains a map of modified project plan. 
Supplement to Design Memorandum No. 1 was 
approved in August 1985. 
Local cooperation: Requirements are described on 
page 33-13 of Annual Report for 1981. 
20. MOJAVE RIVER DAM, MOJAVE 
RIVER BASIN, CA 
Location: On Mojave River at the Forks site, just 
downstream from the mouth of Deep Creek and about 
33-6 
1L. U U I CYl~ WVFEI II V 
17. LOS ANGELES COUNTY SANTAANABASINCA

LOS ANGELES, CA, DISTRICT 
14 miles upstream from Victorville, in Mojave River 
Basin, CA. 
Existing project: For details, see page 33-8 of Annual 
Report for 1983. 
Local cooperation: Requirements are described in full 
on page 33-13 of Annual Report for 1981. 
21. PINE AND MATHEWS 
CANYONS DAMS, COLORADO 
RIVER BASIN, NV 
Location: In Lincoln County, NV, about 100 miles 
north of Hoover Dam and about 17 and 20 miles, 
respectively, east of Caliente, NV. 
Existing project: For details, see page 33-13 of 
Annual Report for 1981. 
Local cooperation: Fully complied with. 
22. SANTA ANA MAINSTEM, CA 
Location. Along a 75-mile reach of the Santa Ana 
River in San Bernardino, Riverside, and Orange 
Counties, emptying into the Pacific Ocean between the 
cities of Newport Beach and Huntington Harbor, 50 
miles south of Los Angeles, and 90 miles north of San 
Diego. 
Existing project. For details, please see Page 33-9 of 
the Annual Report for 1987. 
Local cooperation. Counties of San Bernardino, 
Riverside, and Orange. 
Operations during fiscal year. The contract for the 
construction of Mill Creek was completed March 1992. 
The construction contract for the first reach of the 
lower Santa Ana River and the Greenville-Banning 
Channel was completed December 1992. The Intake 
Structure Excavation contract at Seven Oaks was 
completed June 1992. Bids were opened in Feb 1992 
for the outlet works/diversion contract at Seven Oaks, 
and awarded Apr 1992. Bids were opened in March 
1992 for Reach 2 of the Lower Santa Ana River and 
was awarded April 1992. 
23. SANTA ANA RIVER BASIN AND 
ORANGE COUNTY, CA. 
Location. On the Santa Ana River and tributaries and 
on other streams in Orange, Riverside, and San 
Bernardino Counties, CA. 
General plan of improvement. For details, see page 
33-14 of Annual Report for 1981. 
Existing project. For details on units, see Annual 
Report for 1968. For other pertinent information, see 
Table 33-G, "Deauthorized Projects." 
Local cooperation. Fully complied with. Orange 
County Water District advocated an increase in water 
conservation at Prado Dam up to elevation 505'. Prado 
Basin includes significant riparian wetlands, including 
nesting areas of the endangered least Bell's vireo. The 
Basin is currently under review as proposed critical 
habitat for the vireo. 
Operations during fiscal year. The conditions of dams 
and channels is good. 
24. WHITE WATER RIVER BASIN 
FLOODWARNING SYSTEM, CA 
Location. The Coachella Valley area of San Bernadino 
and Riverside Counties, about 100 miles east of the 
city of Los Angeles. 
Existing project. Rain and stream gages have been 
installed in appropriates locations in the Whitewater 
River tributary basin. Receiving and processing stations 
are operational at two local emergency agency offices. 
Local 
District 
August 
cooperation. The Coachella Valley Water 
signed the local cooperation agreement in 
1989. 
Operations during fiscal year. The local sponsors 
installed 99 per cent of the equipment. 
25. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Inspection costs for fiscal year from regular funds for 
maintenance were $557,621. (See table 33-1 on 
33-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
inspection of completed flood control project.). 
26. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with section 7, Flood Control Act of 
1944, studies of reservoir operations for flood control 
were conducted; and preparation of regulations for the 
use of storage allocated for flood control was 
continued. Cost for fiscal year from regular funds for 
maintenance were $252,378. 
27. 
flood prevention studies; $448,157 were for surveys; 
$13,614 were for special studies involving coordination 
with other agencies; $140,872 were for review of 
authorized projects; and $141,519 were for 
miscellaneous activities. 
29. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year costs were $00.00 for technical services; 
and $151,415 for flood plan management 
FLOOD CONTROL WORK 30. RESEARCH AND DEVELOPMENT 
UNDER SPECIAL AUTHORIZATION 
Flood control activities pursuant to section 205, 
Public Law 80-858, as amended (preauthorization) 
See table 33-J on flood control work under special 
authorization. 
Emergency bank protection (sec. 14 of 1946 Flood 
Control Act, Public Law 526, 79th Cong.) 
Federal cost for fiscal year was $126,989 for 
Emergency flood control activities - repair, flood 
fighting, and rescue work (Public Law 99, 84th Cong., 
and antecedent legislation) 
Federal cost for fiscal year was $103,476 for 
advance preparation. 
Flood insurance activities (sections 1301-1377, 1968 
Housing and Urban Development Act, Public Law 90- 
448, as amended) 
In coordination with flood control activities, flood 
insurance studies were continued in accordance with 
Inter-Agency Agreements under Housing and Urban 
Development reimbursable order. 
General Investigations 
28. SURVEYS 
Fiscal year cost was $4,577,012 regular funds, of 
which $1,022,483 were for navigation studies; $ 0 
were for shore protection studies; $2,810,366 were for 
Fiscal year cost was $6,266 for hydrologic studies. 
PRECONSTRUCTION ENGINEERING AND 
DESIGN 
31. CARNEROS CREEK, CA 
Location. Located in Goleta Valley area, 6 miles west 
of Santa Barbara, and 90 miles northwest of Los 
Angeles. 
Description. Carneros Creek is one of several streams 
in the 48-square mile area of Goleta Valley which flow 
from southern slopes of Santa Ynez Mountains through 
residential, commercial and industrial areas of the 
Goleta Valley, converging in the Goleta Slough before 
flowing into the Pacific Ocean at Goleta Beach property 
to be protected is primarily industrial. 
Local Cooperation. Santa Barbara Co. Flood Control 
& Water Conservation District. Under WRDA of 1992 
H.R. 6167, the recommended project consists of an 
off-line excavated debris basin in combination with a 
diversion channel connecting to an existing borrow pit 
that will be modified slightly to become a detention 
basin north of U.S. Highway 101. 
Operations during fiscal year. 11 month delay caused 
by inability to obtain right-of-entries for PED in FY92. 
Obtaining through sponsor was unsuccessful. 
Currently obtaining through Federal condemnation 
process. 
33-8

LOS ANGELES, CA, DISTRICT 
32. CLIFTON, AZ 
Location. Clifton is in Greenlee County, AZ, about 
170 miles northeast of Tucson. 
Existing project. The project consists of both 
structural and nonstructural elements, including an 
earthfill levee about 3,000 feet long, with floodgates. 
Implementation will involve flood proofing of 11 
businesses, flood plain evacuation plans, and recreation 
development. 
Local cooperation. The State of Arizona is the local 
sponsor. An April 27, 1984 letter from Governor Bruce 
Babbit asked the Corps to act as lead agency in flood 
recovery. Governor Evan Mecham sent a letter of 
intent and support dated January 26, 1987, to provide 
all local requirements including costs. Governor Rose 
Mofford included funding for right-of-way acquisition in 
the State's FY 91 budget. Construction funding is 
expected in the State's FY93 budget. 
Operations during fiscal year. Preconstruction 
engineering and design, to finalize levee plans and 
specifications. 
33. HANSEN DAM, CA 
Location. In the San Fernando Valley area of the city 
of Los Angeles. 20 miles northwest of Downtown Los 
Angeles. Recreation lake and facilities lie within Flood 
Control Basin boundaries. 
Existing project. Original project authorized under 
Flood Control Act 1936, and modified by WRDA 1986, 
Section 847 Energy & Water Development Act 1992 
(PL 102-104). Proposed plan is to construct a 15-acre 
recreation lake, picnic facilities, access roads and 
parking lots. The lake and recreational facilities will be 
constructed with full Federal funding with royalties 
earned from the sale of Debris removal from the basin. 
The city of Los Angeles will construct remaining 
facilities. 
Local cooperation. The City of Los Angeles will be 
independently funding and constructing portions of the 
lake development; no LCA needed. An agreement will 
be needed between the Corps and the City for the City 
to operate and maintain the facilities. The City will 
provide remining facilities (water supply & treatment), 
that will be necessary for the lake to be useable. 
Operations during fiscal year. Master Plan completed. 
Feature Design Memorandum and Plans and 
Specifications are to be prepared and completed FY93. 
34. HOLBROOK, AZ 
Location. In the city of Holbrook, AZ, about 150 
miles northeast of Phoenix. 
Existing project. The plan will provide 100-year-flood 
protection by raising and extending the existing Corps 
of Engineers levee on the north side of the Little 
Colorado River, building a ring levee around the 
McLaws area, relocating residents of the south bank 
flood plain east of the Apache Railroad, acquisition of 
ponding areas and wildlife mitigation. It is the NED 
plan. 
Local cooperation. The City of Holbrook agree with 
the draft Local Cooperation Agreement (LCA). The 
LCA will be signed on 31 May 92. 
35. LAKE ELSINORE, CA 
Location. In Riverside County, about 70 miles 
southeast of Downtown Los Angeles, and 30 miles 
southeast of the city of Corona. 
Existing project. The plan consists of an earthen-trap 
outlet channel about 2.5 miles long, with a 30-foot to 
80-foot base and IV on 3H side slopes. Will relieve 
flooding at the 100-year-flood level in the downtown 
area, as well as around the perimeter of the lake. The 
final plan includes building six bridges and protecting an 
endangered species habitat. 
Local cooperation. Riverside County Flood Control 
and Water Conservation District signed a Local 
Cooperation Agreement on 27 March 92. 
Operations during fiscal year. Complete acquisition of 
Real Estate. Award and initiate construction contract. 
36. LOWER MISSION CREEK, CA 
Location. In Santa Barbara County, about 100 miles 
northwest of Los Angeles. 
33-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
Existing project. The project is designed to prevent 
100-year flood damages. The recommended plan, 
authorized under Water Resources Development Act of 
1988, consists of approximately 1.2 miles of 
rectangular concrete channel improvements from an 
inlet at Carrillo Street to the ocean. The project will 
impact eleven street crossings and one railroad bridge 
crossing. 
Local cooperation. Local Sponsor is Santa Barbara 
Co. Flood Control and Water Conservation District. 
Operations during fiscal year. Completion of PED. 
Filed FEIS. 
37. LOWER SANTA CRUZ, AZ 
Location. Study area in lower reach of Santa Cruz 
River in Pinal County about 50 miles south Phoenix, AZ 
and lies between town of Red Rock and confluence of 
Gila River. Damage area is experiencing accelerated 
urbanization as a result of growth pressure from the 
Phoenix and Tucson metro areas. 
Local cooperation. Authorized under Flood Control 
Act 28 June 38 (Gila River & Tribs). Local Sponsor 
Pinal County Flood Control District and Pinal County 
Board of Supervisors passed resolution to continue 
study 7 Jul 92, and we received resolution of support 
from Tohano-O'odham Community 10 Jul 92. 
Operations during fiscal year. Serious geotech 
problems found in much of study area - requires 
rescoping of study to avoid these areas. SPL 
developing FCSA amendment, revised scope and 
schedule. Technical work was halted until decision 
from locals to continue study resulting in unobligated 
carryover. 
38. NOGALES WASH, AZ 
Location. At the Mexican Border, in extreme southern 
Arizona in central and northern portions of the city of 
Nogales, about 60 miles south of Tucson. 
Existing project. Plans include a lateral collector 
channel to capture Overland Street flow and divert it 
into the existing covered channels; a 3,300-foot-long 
grouted stone/concrete channel system in the Chula 
Vista community; and a flood warning system and 
recreation component associated with Chula Vista 
channels. 
Local cooperation. The Santa Cruz Flood Control 
District has signed a cost-sharing agreement. 
39. RILLITO RIVER, AZ 
Location. The north portions of the Tucson 
metropolitan area of Pima County, AZ. 
Existing project. Provide flood protection by building 
soil cement for bank erosion control and grade-control 
structures in the channel bottom to prevent 
degradation along 13.2 miles of the river. 
Local cooperation. Pima County Transportation and 
Flood Control District submitted letters of assurance on 
February 24, 1986 and May 6. 1987. 
40. SANTA ANA RIVER MAINSTEM, 
CA 
Location. Along a 75-mile reach of the Santa Ana 
River in San Bernardino, Riverside, and Orange 
Counties, emptying into the Pacific Ocean between the 
cities of Newport Beach and Huntington Harbor, 50 
miles south of Los Angeles, and 90 miles north of San 
Diego. 
Existing project. For details, please see Page 33-9 of 
the Annual Report for 1987. 
Local cooperation. Counties of San Bernardino, 
Riverside, and Orange. 
Operations during fiscal year. The contract for the 
construction of Mill Creek was awarded on April 30, 
1991 and completed on 19 March 1992. Marsh 
contract completed 29 March 1991, abutment stripping 
contract completed 30 Nov 1991. The construction 
contract for the first reach of the lower Santa Ana 
River and the Greenville-Banning Channel was awarded 
on April 15, 1991, and is scheduled for completion in 
December 1992. The Intake Structure Excavation 
contract at Seven Oaks was awarded on August 14, 
1991 and is scheduled for completion on 3 June 1992. 
Bids were opened on 25 Feb 1992 for the outlet 
works/diversion contract at Seven Oaks, with award 
scheduled for 1 Apr 1992. Bids were opened on 26 
March 1992 for Reach 2 of the lower Santa Ana River. 
Award is scheduled for 30 April 1992. 
33-10

LOS ANGELES, CA, DISTRICT 
41. SANTA PAULA CREEK, CA 
Location. Santa Paula Creek is a tributary of the 
Santa Clara River in the vicinity of the city of Santa 
paula, Ventura County, about 16 miles from the ocean 
and approximately 60 miles northwest of Los Angeles. 
Existing project. Authorized by Flood Control Act of 
1970, Public Law 91-611 (HD 443/80/1), for details 
see Annual Report FY91, page 33-10. 
Local cooperation. Ventura County Flood Control 
District. If a new project authorization is required as a 
result of the ongoing GRR process, the local sponsor 
will be required to cost share in accordance with 
WRDA 1986. 
Operations during fiscal year. Modified Mupu Plan 
consisting of 2.9 miles of concrete channel from Santa 
Clara River to single debris basin located near Mupu 
School. was locally preferred plan in 1983 report. 
Awaiting GRR recommendation from Channel 
Stabilization Committee since channel inspection Aug 
92. 
42. SWEETWATER RIVER, CA 
Location. Empties into San Diego Bay in the cities of 
Chula Vista and National City and unincorporated San 
Diego County, four miles south of the city of San 
Diego, and eight miles north of the Mexican Border. 
Existing project. Construction of 3.2 miles of channel 
improvements along the Sweetwater River from 
Interstate 805 to San Diego Bay, in combination with 
State Route 54 and Interstate 5 construction; and 
construction of two railroad bridges and 188 acres of 
preservation and mitigation land. 
Local cooperation. San Diego County is cost-sharing. 
Operations during fiscal year. Construction resumed 
when channel completion contract was awarded in 
September 1990. 
43. TROPICANA AND FLAMINGO 
WASHES, NV 
Location. West of and through urbanized Las Vegas 
community along both washes. 
Existing project. Study structural and nonstructural 
means of reducing flood damage and provide erosion 
control, water supply, recreation and enhancement. 
Local cooperation. The Clark County Regional Flood 
Control District approved the Feasibility Cost-Sharing 
Assessment in July 1985. 
Operations during fiscal year. Formulated tentatively 
recommended plan; 4 Detention Basins, 4 Debris 
Basins, 28 miles of Concrete Primary Channel, 32 miles 
of Earthen Lateral Channels. Estimated cost = $252 
Million (Funded) to be cost shared 25% non-Fed, 75% 
Fed., plus sponsor pays for Laterals ($28 Million Fully 
Funded). Expect to complete Feasibility Study in 
January 1992. 
33-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 30 Sep 92 
1. Channel Islands, 
CA 
2. Los Angeles and 
Long Beach 
Harbor, CA 
(Regular Funds) 
(Required 
Contrib. Funds) 
Model Study 
3. Marina del Rey, 
CA 
(Regular Funds) 
4. Morro Bay 
Harbor, CA 
Maint: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work: 
Contrib. 
Cost 
3,053,480 90,912 2,635,131 
3,085,940 74,111 2,635,000 
602,296 
760,456 
- 749,459 1,036,777 
243,494 1,150,000 2,000,000 
257,000 1,136,664 
1,287,455 243,494 
394,995 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
876,615 
143,394 
785,628 478,901 
268,785 409,430 
205,937 350,000 
53,942 
187,987 70,000 
Maint.: 
Approp. 
Cost 
5. Oceanside 
Harbor, CA 
6. Oceanside Sand 
By-pass 
7. Port Hueneme, 
CA 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
882,806 2,385,889 
129,715 1,672,000 
96,798 
97,731 
106,733 
23,348 
658,000 
590,619 
10,000 
98,937 
75,949 
143,394 
- 
292,207 
15,510 
757,969 
- 
300 
736,834 
6,659 
1,286,134 1,105,237 2,729,235 1,536,676 6,657,282 
22,000 
66,307 
152 
2,002 
114,587 
69,922 
856,184 
852,000 
2,472 
22,000 
73,862 
33-12 
6,539,979 
5,795,051 
1,786,236 
3,995,790 
2,260,279 
1,674,343 
1,180,623 
821,609 
555,937 
346,149 
253,497 
2,559,684 
1,801,715 
130,446 
1,591,502 
778,960 
22,000 
70,781 
992,923 
995,784

LOS ANGELES, CA, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 30 Sep 92 
8. Redondo Beach, 
(King Harbor) 
9. San Diego 
Harbor, CA 
10. San Diego River 
& Mission Bay, 
CA 
11. Santa Barbara 
Harbor, CA 
12. San Luis Rey 
River, CA 
13. Ventura Marina 
(Ventura 
Harbor), CA 
15. Cucamonga 
Creek, Santa 
Ana River Basin, 
CA 
16A. 
16B. 
Painted Rock, 
AZ 
Phoenix, AZ and 
Vicinity 
Maint: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
226,298 
873,000 
880,854 
65,000 
91,094 
158,806 
541,898 
- 984,963 
185,889 2,926 
15,000 
24,333 
28,410 
23,092 
837,435 
756,948 
886,562 
132,292 
71,369 
70,000 
87,324 
97,000 
139,383 
130,000 
831,034 
865,000 
136,292 
16,212 
4,633,000 2,270,000 2,672,999 16,562,010 
6,284,196 1,586,807 1,765,000 1,820,000 
921,364 
936,799 
22,734 
6,435 
681,019 
717,117 
53,069,000 
30,548,322 
414,015 
264,530 
4,462 
1,593 
751,360 
30,054,000 
32,288,943 
984,963 
415,113 
1,910,854 
1,037,479 
71,369 
70,000 
196,946 
211,086 
139,383 
130,000 
1,827,275 
2,163,846 
26,138,009 
11,456,003 
950,774 1,888,498 4,174,651 
270,668 904,700 2,376,697 
10,218 
627,459 
625,800 
33,233,917 
29,816,000 
37,414 
8,028 
754,849 
25,543,262 
2,063,327 
2,094,274 
116,356,917 
118,196,527 
33-13 
TABLE 33-A

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 30 Sep 92 
17. Los Angeles 
County 
Drainage Area, 
18. Los Coches 
Creek, CA 
19. Lytle & Warm 
Creeks, Santa 
Ana Basin 
20. Mojave River 
Dam, Mojave 
River Basin 
21. Pine & Mathews 
Canyons Dam, 
Colo River 
Basin, NV 
22. Santa Ana River 
Mainstem 
23. Santa Ana River 
Basin OC 
24. Whitewater 
River 
Floodwarning 
System 
31. Carneros Creek 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost. 
New Work: 
Approp. 
Cost. 
Maint.: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
Maint.: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
2,556,319 2,271,931 2,473,742 2,500,897 
- 2,174,188 2,327,400 1,812,395 
3,539,763 
7,778 
14,689 
758,939 
900,000 
1,482 
2,475 
183,000 663,188 
206,282 245,819 
105,000 
98,228 
7,614,580 
261,643 
71,972 
20,136 
670,769 - 
221,800 209,774 
117,835 
61,000 
10,250,887 50,609,693 
- 993,347 
17,292,000 
10,250,887 
239,716 
93,000 
96,138 
9,802,889 
6,313,983 
4,398,702 
900,000 
9,260 
17,164 
1,516,957 
883,675 
390,945 
179,364 
103,771 68,574,931 
64,717,151 1,254,990 
78,200 
64,717 
1,815,061 2,124,199 1,738,763 1,995,217 
1,939,254 2,025,348 1,586,000 - 
250,000 
50,038 25,640 
188,013 288,722 
- - 
334,977 
600,000 
317,916 
17,449,717 
10,250,887 
7,673,230 
5,550,602 
1,726,735 
75,678 
334,977 
600,000 
33-14

LOS ANGELES, CA, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 30 Sep 92 
Clifton, AZ 
Hansen Dam 
Holbrook, AZ 
Lake Elsinore 
Lower Mission 
Creek 
Lower Santa 
Cruz, AZ 
Nogales Wash, 
AZ 
39. Rillito River, 
AZ 
41. Santa Paula 
Creek 
42. Sweetwater 
River Basin 
43. Tropicana/ 
Flamingo, NV 
32. 
33. 
34. 
35. 
36. 
37. 
38. 
813,030 466,484 
- - 
171,198 
645,082 
280,412 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp, 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
New Work: 
Approp. 
Cost 
164,559 
92,928 
380,340 
76,419 
463,707 
370,285 
441,173 
366,774 - 
798,446 298,378 
- 164,510 
298,308 
50,000 
1,125 
173,823 
200,000 
- 2,169,000 6,056,291 
364,149 925,668 4,492,000 
1,197,676 169,185 
318,836 
306,613 
502,189 
72,802 
184,785 
455,172 
900,000 
300,000 
1,006,469 
711 
611,667 
1,978,690 
76,419 
474,172 
171,198 
1,703,906 
72,802 
835,482 
896,345 
900,000 
834,982 
1,096,824 
481,695 
224,534 
813,579 
6,456,306 14,681,597 
- 5,781,817 
97,501 1,197,676 2,652,038 
33-15 
TABLE 33-A 
168,108 
317,185 
340,880 
787

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 3, 1954 
June 3, 1896 
June 25,1896 
July 25, 1912 
Aug. 8, 1917 
Sep. 22, 1922 
Mar. 3, 1925 
July 3, 1930 
CHANNEL ISLANDS HARBOR, CA 
Harbor for light-draft vessels and shore 
protection works. 
LOS ANGELES AND LONG BEACH 
HARBORS, CA 
A breakwater 8,500 feet long, east of Point 
Ferman. 
Extend said breakwater to shore, making a 
total length of 11,152 feet from Point 
Fermin. 
Dredge Los Angeles outer harbor west of 
entrance channel. 
For silt-diversion works. 
Triangular area approach to Los Angeles 
inner harbor entrance channel. 
Dredge Los Angeles Harbor main channel 
and entrance 35 feet deep and 1,000 feet 
wide; dredge inner harbor turning basin 35 
feet deep; and reclamation of Reservation 
Point. 
A detached breakwater 12,500 feet long in 
prolongation of existing breakwater 
(authorized by act of 1896). 
H.Doc. 362,83d Cong., 
2d sess. 
S.Doc. 18,55th 
Cong.,1st sess. 
H.Doc. 969, 60th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc.8, 62d 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc.9, 64th 
Cong.,2d sess. 
H.Doc. 1013, 66th 
Cong.,3d sess. 
H. Doc.349, 68th 
Cong., 1st sess. 
Rivers and Harbors 
Committee Doc.33, 71st 
Cong., 2d sess. 
33-16 
1. 
2.

LOS ANGELES, CA, DISTRICT 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Widen fairway on east side of entrance to 
Los Angeles inner harbor; dredge a channel 
35 feet deep and 400 feet wide in Cerritos 
channel from U.S. station 406 to Long 
Beach turning basin; entrance channel to 
Long Beach Harbor 35 feet deep and 500 
feet wide; and maintenance of the Long 
Beach breakwater south of outer end pier 
A. This act provides that in no case shall 
dredging be done within 50 feet of 
established pierhead lines of existing piers 
and wharves. 
Dredge 1,000-foot wide entrance channel 
to Los Angeles outer harbor to 40-foot 
depth and a turning basin 3,500 feet long 
and 1,500 feet wide to same depth; and 
enlarge entrance to inner harbor by 
dredging to 35-foot depth a triangular area 
at its junction with turning basin. 
Dredge to a depth of 40 feet area A and B 
adjacent to 40-foot-depth entrance channel; 
construct and maintain a rubblemound 
breakwater of composite type 21,000 feet 
long in eastward therefrom to Belmont pier; 
maintenance dredging of A and B, and at 
mouth of Los Angeles River diversion 
channel; all subject to such modifications as 
in discretion of the Chief of Engineers may 
be advisable to meet requirements of the 
Navy. 
S. Doc.130, 71st 
Con.,2d sess. 
S.Committee print, 74th 
Cong., 1st sess. 
H.Doc.843, 76th Cong., 
3d sess. 
33-17 
Do. 
Aug. 30, 1935 
Oct. 17,1940

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Sep. 3, 1954 
July 14, 1960 
Oct. 22, 1976 
H.Doc.161, 83d Cong., 
1st sess. 
H.Doc.401,86th Cong., 
2d sess. 
H.Doc.94-594, 94th 
Cong., 2d sess.1 
33-18 
Dredge to a depth of 35 feet in East Basin 
as a modification of existing project. This 
act provides that the Secretary of the Army 
is authorized to reimburse local interests for 
work they have done upon this project prior 
to July 1, 1953, at actual cost to local 
interests so far as same shall be approved 
by Chief of Engineers and found to have 
been done in accordance with the project 
hereby adopted and that such 
reimbursement shall be subject to 
appropriations applicable thereto or funds 
available therefor and shall not take 
precedence over other pending projects of 
higher priority for harbor improvements; and 
that such payments shall not exceed 
$500,000. 
Dredge to a depth of 35 feet in West Basin 
as a modification of existing project. 
Dredge Los Angeles Harbor entrance 
channel 45 feet deep, 1,000 feet wide, and 
about 5,500 feet long; Los Angeles channel 
45 feet deep, 750 feet wide, and about 
12,500 feet long; inner harbor turning basin 
45 feet deep, 1,350 feet wide, and about 
1,650 feet long; East Basin channel 45 feet 
deep, 400 feet wide, and about 6,000 feet 
long; West Basin 45 feet deep, from 350 to 
1,350 feet wide, and about 3,800 feet 
long; and East Basin 45 feet deep, from 
400 to 950 feet wide, and about 2,000 
feet long. This act provides that no 
dredging shall be done within 125 feet of 
established pierhead lines, wharves, or 
other structures.

LOS ANGELES, CA, DISTRICT 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
If non-Federal interest carry out any work 
associated with such project which is later 
recommended by the Chief of Engineers 
and approved by the Secretary, the 
Secretary may credit such non-Federal 
interest an amount equal to the Federal 
share of the cost of such work, without 
interest. In analyzing costs and benefits of 
such project, the Secretary shall consider 
the costs and benefits produced by any 
work which is carried out under the 
preceding sentence by non-Federal interests 
and which the Secretary determines is 
compatible with such project. The 
feasibility report for such project shall 
include consideration and evaluation of the 
following proposed project features: Long 
Beach Main Channel, Channel to Los 
Angeles Pier 300, Channels to Los Angeles 
Pier 400, Long Beach Pier "K" Channel, and 
Los Angeles Crude Transshipment Terminal 
Channel. 
The Secretary is directed to perform 
maintenance dredging of the existing 
Federal project at the mouth of the Los 
Angeles River, CA, to the authorized depth 
of 20 feet for the purpose of maintaining 
the flood control basin and navigaton 
safety. 
Public Law 100-676 
Public Law 100-676- 
Nov.17, 1988 
Sep. 3, 1954 MARINA DEL REY, LOS ANGELES 
COUNTY, CA 
Harbor for light-draft vessels. 
H.Doc.389, 83d Cong., 2d sess. 
33-19 
Nov. 17, 1988 
Nov. 17, 1988 
3.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Mar. 2, 1945 
Oct. 8, 1992 
Oct. 27, 1965 
Oct. 27, 1965 
Aug. 13, 1968 
Nov. 17, 1986 
Mar. 03, 1875 
Sep. 19, 1875 
4. H.Doc.283, 77th Cong., 
1st sess. 
H.R.6167 
MORRO BAY HARBOR, CA 
Adoption and improvement of existing 
entrance channel to bay, a breakwater 
extending south by west from Morro Rock, 
and bay channels and basins at locations 
and of dimensions substantially as shown 
on the Navy Department map on file in the 
Office of the Chief of Engineers. 
Is authorized to be carried out by the 
Secretary substantially in accordance with 
the plans and subject to the conditions. 
This project is for navigation. 
OCEANSIDE HARBOR, CA 
Maintenance of general navigation features 
of Del Mar Boat Basin and of Oceanside 
Harbor. 
OCEANSIDE SAND BYPASS, CA 
Maintenance of general navigation features 
of Del Mar Boat Basin and of Oceanside 
Harbor. 
PORT HUENEME, CA 
Adoption and maintenance of existing 
harbor for deep-draft vessels; dredged 
central basin to 35 feet deep, and extend 
southern-most interior channel. 
KING HARBOR, REDONDO BEACH, CA 
Provides for cost sharing in accordnace 
with WRDA '86. P ermits construction of 
breakwater > 22' in accordance with plans 
approved by Aray. 
SAN DIEGO HARBOR, CA Diversion dike. 
Annual Report 1973; p.1142 Sep. 19, 
1890. 
Jetty on Zuniga Shoal. 
(Annual Report, 1888;p.2114). 
33-20 
H.Doc.76, 89th Cong., 
1st sess. 
Rivers and Harbor Act 
1965 (79 Stat. 1092) 
H.Doc.76, 89th Cong., 
1st sess. 
Rivers and Harbor Act 
1965 (79 Stat. 1092) 
H.Doc.362, 90th Cong., 
2d sess. 
H.Doc.362, 90th Cong., 
2d sess. 
H.Doc.362, 90th Cong., 
2d sess. 
H.Doc.177, 50th Cong., 
1st sess. 
5. 
6. 
7. 
8. 
9.

LOS ANGELES, CA, DISTRICT 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 25,1910 
Mar. 4, 1913 
July 27, 1916 
Aug. 8, 1917 
Aug. 8, 1917 
Sep. 22, 1922 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 2 
Aug. 26, 1937 
Dredge channel through outer bar 30 feet 
deep and 600 feet wide, and a channel 
through middle ground to 30 feet deep. 
Dredge channel through outer bar 570 feet 
wide and 35 feet deep, and a channel 
through middle ground 32 feet deep. 
Widen approach (area B) to San Diego 
municipal pier by dredging area C (north of 
area B). 
Dredging area A (south of area B). 
Dredge 35-foot channel through middle 
ground. 
Dredging areas D and E. 
Widen approach (area C) to San Diego 
municipal pier 1 by dredging an portion of 
area F (north of area C). 
Deepen to 40 feet channel through outer 
bar; along south and north banks, main 
channel; dredge turning basin, widen area 
H, and dredge a channel to National City 
and Chula Vista 
Widen bay channel to 2,200 feet with 
depth of 35 feet from the vicinity of 
Whalers Bight in lower bay to Naval Air 
Station opposite turning basin. 
Dredging areas Q.Q-1, M, N, and 0. 
H.Doc.961, 60th Cong., 
1 st session. 
H.Doc.1309, 62d Cong., 
3d sess. 
H.Doc.648, 64th Cong., 
1st sess. 
Rivers and Harbors 
Committee Doc.8, 64th 
Cong., 2d sess. 
H.Doc.140, 65th Cong., 
1st sess. 
H. Doc.1000, 66th 
Cong., 3d sess. 
River and Harbors 
Committee Doc.2, 68th 
Cong., 1st sess. 
S.Doc.81, 71st Cong., 
2d sess. 
H.Doc.223, 73d Cong., 
2d sess. 
Rivers and Harbors 
Committee Doc.89, 
74th Cong., 2d sess. 
33-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 17, 1940 
Mar. 2, 1945 
Aug. 13, 1968 
July 24, 1946 
11. Dec. 17, 1970 3 
Nov. 17, 1986 
12. Aug. 30, 1935 
Mar. 2, 1945 
Dredge a seaplane basin (area S.) of about 
3,000 acres, 10 feet deep, and fill an area 
of about 110 acres adjacent to southern 
end of basin. 
Dredge triangular approaches to 26-and 35- 
foot anchorages, area M. 
Deepen and extend existing navigation 
channels, delete uncompleted parts, and 
extend maintenance. 
SAN DIEGO RIVER AND MISSION BAY, CA 
Modification of existing flood control 
project for San Diego River, CA, to include 
a multiple-purpose project for flood control 
on San Diego River and small-boat 
navigation on Mission Bay. 
SAN LUIS REY RIVER, SAN LUIS REY 
RIVER BASIN, CA 
Channel and levee, and beautification 
features. 
Authorized non-Federal project cost sharing 
at a minimum of 25 percent and a 
maximum of 50 percent. 
SANTA BARBARA HARBOR, CA 
Maintenance dredging present depths into 
harbor formed by breakwater constructed 
by local interests. 
Permits maintenance by means of a fixed 
sand-intercepting plant to be provided and 
operated by and at expense of local 
interests. United States to contribute to 
operating expense an amount not to exceed 
$30,000 annually, whenever funds are 
allotted therefor; funds thus contributed to 
be reduced by actual cost of harbor 
maintenance if and when intercepting plant 
has been installed. 
H.Doc.844, 
3d sess, 
H.Doc.390, 
1st sess. 
H.Doc.365, 
2d sess. 1 
H.Doc.760, 
2d sess. 1 
76th Cong., 
77th Cong., 
90th Cong., 
79th Cong., 
S.Doc.91-106, 91st 
Cong., 2d sess. 
None 
S.Committee Print, 73d 
Cong., 2d sess. 
H.Doc.348, 77th Cong., 
1st sess. 
33-22 
10.

LOS ANGELES, CA, DISTRICT 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 23, 1962 
Dec. 31, 1970 
13. Aug. 13, 1968 
Nov. 17, 1988 
15. Aug. 13, 1968 
16A. 
16B. 
May 17, 1950 
Oct. 27, 1965 
17. June 22, 1936 
Modification of existing project. 
Dredging and maintenance by United 
States. 
VENTURA HARBOR (VENTURA MARINA), 
CA 
Adoption and maintenance of existing 
general navigation features of harbor, 
excluding interior basins; construction of an 
offshore breakwater; dredging a sand trap 
in lee of breakwater; repairing existing 
north and middle jetties; and construction 
of recreational fishing facilities on jetty 
crests. 
The Harbor commonly known as Ventura 
Marina, located in Ventura County,CA, and 
adopted and authorized by section 101 of 
Public Law 90-483, shall hereafter be 
known and designated as "Ventura 
Harbor". 
CUCAMONGA CREEK, SANTA ANA RIVER 
BASIN, CA 
Debris-collection facilities, with a system of 
channels, and a diversion system. 
PAINTED ROCK DAM (GILA RIVER), GILA 
RIVER BASIN, AZ 
Dam and flood control basin. 
PHOENIX, AZ., AND VICINITY (INCLUDING 
NEW RIVER), GILA RIVER BASIN 
Detention basins, diversion channels, and 
channel improvements. 
LOS ANGELES COUNTY DRAINAGE AREA, 
CA 
Reservoirs and flood channels for flood 
control and related purposes at an 
estimated construction cost not to exceed 
$70 million. 
H.Doc.518, 87th Cong., 
2d sess. 1 
None 
H.Doc.356, 90th Cong., 
2d sess. 
Public Law 100-676 
H.Doc.323, 90th Cong., 
2d sess. 
H.Doc.331, 81st Cong., 
1 st sess. 
H.Doc.216, 89th Cong., 
1st sess. 
None 
33-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
May 15, 1937 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 24, 1946 
May 17, 1950 
Sep. 3, 1954 
July 3, 1958 
July 14, 1960 
Added flood channels on Ballona Creek and 
tributaries to project 
Provision of lands, easements, and rightsof-
way and relocations by Federal 
Government instead of by local interests. 
(Resultant additional cost to the United 
States, $12,541,000). 
Project extended to include additional flood 
control reservoirs, flood control channels, 
and debris basins for flood control and 
related purposes. Also authorized to be 
appropriated $25 million for further 
accomplishment of plan. 
Authorized to be appropriated an additional 
$25 million for prosecution of 
comprehensive plan approved in Flood 
Control Act of Aug. 18, 1941. 
Authorized to be appropriated an additional 
$25 million for further prosecution of 
comprehensive plan. 
Rio Hondo channel improvement, Whittier 
Narrows Reservoir to Los Angeles River (in 
lieu of enlarging channel and bridges on San 
Gabriel River downstream from reservoir). 
Also authorized to be appropriated an 
additional $40 million for further 
prosecution of comprehensive plan. 
Authorized to be appropriated an additional 
$12,500,000 for further prosecution of 
comprehensive plan. 
Authorized to be appropriated an additional 
$44 million for further prosecution of 
comprehensive plan. 
Authorized to be appropriated an additional 
$32 million for further prosecution of 
comprehensive plan. 
None 
None 
H.Doc.838, 76th Cong., 
3d sess. 
None 
None 
None 
None 
None 
None 
33-24

LOS ANGELES, CA, DISTRICT 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 23, 1962 
Dec. 30, 1963 
June 18, 1965 
Nov. 17, 1986 
Nov. 17, 1988 
Feb. 7, 1985 
19. Oct. 27, 1965 
20. July 14, 1960 
21. May 17, 1950 
Authorized to be appropriated an additional 
$3,700,000 for further prosecution of 
comprehensive plan. 
c 
Authorized to be appropriated an additional 
$30 million for further prosecution of 
comprehensive plan. 
In addition to all previous authorizations, 
completion of improvements under to 
comprehensive plan for flood control in the 
Los Angeles River Basin at a presently 
estimated cost of $31 million for 
completion. 
Authorized modification of Hansen Dam by 
removing and selling dredged material to 
facilitate flood control, recreation, and 
water conservation. 
The Secretary may convey to the city of 
South El Monte, CA, approximately 7.778 
acres of real property, together with 
improvements theron, located within the 
Whittier Narrows Flood Control Basin. 
LOS COCHES CREEK, SAN DIEGO 
COUNTY, CA 
Channel improvement. 
LYTLE AND WARM CREEKS, SANTA ANA 
RIVER BASIN, CA 
Channels and levees. 
MOJAVE RIVER DAM, MOJAVE RIVER 
BASIN, CA 
Dam and reservoir, and an earthfill dike. 
PINE AND MATHEWS CANYONS DAMS, 
COLORADO RIVER BASIN, NV 
Dams and flood control basins. 
None 
None 
None 
None 
Public Law 100-676 
None 
S.Doc.53, 89th Cong., 
1st sess. 
H.Doc.164, 86th Cong., 
1st sess. 
H.Doc.530, 81st Cong., 
2d sess. 
33-25 
18.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
22. June 22, 1936 
June 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944 
July 3, 1958 
SANTA ANA MAINSTEM, CA 
Reservoirs and flood channels for flood 
control and related purposes for protection 
of metropolitan area of Orange County, at 
an estimated construction cost not to 
exceed $13 million. 
San Antonio and Chino Creeks channel 
portion of improvement. Authorized to be 
appropriated $6,500,000 for initiation and 
partial accomplishment of plans for those 
creeks. Rescinded provisions of Flood 
Control Act of 1936, providing that local 
interests pay for relocations, lands, 
easements, and rights-of-way. (Estimated 
resultant additional cost to United States. 
$3,500,000). 
Authorized to be appropriated an additional 
$2,500,000 for prosecution of projects 
approved in above flood control acts. 
Authorized to be appropriated an additional 
$10 million for prosecution of projects 
adopted in above-mentioned flood control 
acts, including projects on Lytle and Cajon 
Creeks for local flood protection at San 
Bernardino and Colton, CA. 
Authorized to be appropriated an additional 
$8 million for prosecution of projects 
approved in above-mentioned flood control 
acts. 
None 
H.Doc.688, 75th Cong., 
3d sess. 
None 
H.Doc.534, 78th Cong., 
2d sess. 1 
None 
33-26

LOS ANGELES, CA, DISTRICT 
TABLE 33-B AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Nov. 28, 1990 
Aug. 13, 1968 
The project for flood control, Santa Ana 
Mainstem, including Saniago Creek, CA, is 
modified to authorized the Secretary to 
develop recreational trails and facilities on 
lands between Seven Oaks Dam and Prado 
Dam, including flood plain management 
areas. 
SWEETWATER RIVER, SWEETWATER 
RIVER BASIN, CA 
Channel improvement, as part of a 
combined flood control and highway 
project. 
H.Doc.148, 90th Cong., 
1st sess. 
1. Contains latest published map. 
2. Date approved by Chief of Engineers under provisions of section 205. Public Law 80-858, as 
amended. 
3. Final date of approval by House and Senate Public Works Committees resolution under provisions of 
section 201, Public Law 89-298. 
33-27 
22.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to 30 Sep 1991 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Avalon Active 1990 $ 43,960 
Dana Point, Harbor, CA Completed 1984 4,737,550 709,908 
Harbor office at Morro Bay, CA 1 
Newport Bay Harbor, CA Active 1990 796,897 4,497,131 
Port San Luis, CA Completed & 1990 1,426,050 5,539,483 
Active (mod) 
Redondo Beach Harbor Completed & 1990 4,766,8982 1,991,550 
(King Harbor), CA Active 
Sunset Harbor (Bolsa Chica Bay), CA 1 
1. Authorized by Water Resources Development Act of 1986, Public Law 99-662, November 17, 1986, 
subject to favorable report. 
2. Excludes Coast Guard costs. 
10. Includes $20,517 for reconnaissance and condition survey costs since FY58. Includes $293,167 
expended in FY87. 
33-28

LOS ANGELES, CA, DISTRICT 
TABLE 33-D OTHER AUTHORIZED BEACH EROSION 
CONTROL PROJECTS 
For Last Cost to 30 Sep 1991 
Full Report 
See Annual Operation and Project 
Status Report For Construction Maintenance 
Anaheim Bay Harbor Orange Completed 1967 $ 89,119 
County, CA' 
Bird Rock area, La Jolla Completed 1967 25,881 
San Diego County, CA 
Cabrillo Beach Active 1990 9,998 
Coast of California, Point Mugu, Completed 1972 1,253,594 
to San Pedro breakwater, CA 
Doheny Beach State Park (Doheny Completed 1968 578,717 
State Beach), CA 
Imperial Beach, CA Active 1990 2,629,602 
Las Tunas Beach, San Diego Co, CA Active 1976 107,484 
Mission Beach Active 1990 971 
Ocean Beach, San Diego County, CA Completed 1960 7,912 
Oceanside, San Diego County, CA Completed 1982 4,367,442 
Oceanside Sand By-Pass, CA Active 1990 3,440,161 
Port San Luis Shore & Bluff Erosion Active 1990 58,235 
San Diego (Sunset Cliffs), CA Active 1979 365,000 
San Gabriel River to Newport Bay Active 1985 9,722,100 
(Surfside-Sunset and Newport Beach), 
Orange County, CA 
Ventura-Pierpont area, CA Completed (part) 1969 715,819 
& Deferred (part) 
1. The project authorized by the Act of Congress of October 23, 1962, H.Doc.602, 87th Cong., 2d 
sess., in lieu of part of the original Anaheim Bay Harbor project is covered under San Gabriel River to Newport 
Bay (Surfside-Sunset and Newport Beach), Orange County, CA. 
33-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to 30 Sep 1991 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Allenville, AZ C 
City Creek Levee, San C 
Bernardino County, CA 
Clifton, San Francisco River, AZ 
Coyote and Berryessa Creeks CA 
Gila River Basin, AZ: C 
Camelsback Dam (Gila River) 
Gila and Salt Rivers Levee A 
and Channel Improvements D 
Indian Bend Wash C 
Lower Gila River Levee & Ir 
Channel Improvements (Gila 
River and tributaries downstream 
from Painted Rock Dam) 
Middle Gila River Channel P 
Improvements, upper end of Safford 
Valley to Buttes damsite (Camelsback 
damsite to Salt River) 
Pinal Creek Channel Improvements C 
(Globe) 
Santa Rosa Wash (Tat Momolikot C 
Dam and Lake St. Clair) 
Tucson Diversion Channel C 
Goleta, CA, and vicinity 
Hansen Dam, Los Angeles County 
Drainage Area, CA (mod) 
Holbrook Levee Little Colorado C 
River, Colorado River Basin, AZ 
Little Colorado River at Holbrook 
Needles, San Bernardino Co. C 
Nogales Wash and Tributaries, AZ 
Oceanside Harbor, CA 
Oro Grande Wash Channel Improve- C 
ments, Mojave River Basin, CA 
Quail Wash Levee, Joshua Tree, C 
San Bernardino Co. CA 
Rose Creek Channel Improvements, C 
San Diego, CA 
San Diego River (Mission Valley), Ir 
San Diego River Basin, CA 
Santa Ana River Basin, CA: 
Devil, East Twin, and Warm C 
Creeks Channel Improvements & 
Lytle Creek Levee 
:ompleted 
;ompleted 
Active 
Active 
)eferred 
\ctive (part) & 
)eferred (part) 
:ompleted 
nactive 
\ctive 
)eferred 
:ompleted 
:ompleted 
Active 
Active 
:ompleted 
.ompleted 
Active 
Active 
.ompleted 
:ompleted 
:ompleted 
nactive 
.ompleted 
1984 
1988 
1989 
1963 
1966 
1990 
1975 
1970 
1968 
1982 
1986 
1982 
1990 
1950 
1973 
1989 
1989 
1970 
1972 
1978 
1962 
$ 3,000,000 
400,000 
12,510,000 
56,300,000 
73,201 
32,488,487 
2,413,051 
402,867 
121,509 
10,218,900 
6,922,633 
500,000 
335,757 
335,000 
1,000,000 
11,100,000 
5,100,000 
1,000,000 
212,745 
982,432 
1,708,437 
7,753,937 
33-30

LOS ANGELES, CA, DISTRICT 
TABLE 33-E (CONT) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to 30 Sep 1991 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Mill Creek Levees 
Riverside Levees 
San Jacinto River Levee & 
Bautista Creek Channel 
Santa Clara River Levee Improvement, 
Santa Clara Rvr Basin, CA 
Santa Clara Rvr, Fillmore, CA 
Santa Maria Valley Levees, Santa 
Maria River Basin, CA 
Santa Paula Creek Channel & 
Debris Basins (including Mud 
Creek), Santa Clara Rvr Basin, CA 
Sespe Creek at Fillmore, Ventura 
County, CA 
South Fork of the Santa Clara 
Rvr, Santa Clarita Valley, CA 
Telegraph Canyon Creek, Chula 
Vista, CA 
Tijuana River Basin, CA 
Ventura Harbor, CA 
Ventura River Basin, CA: 
Stewart Canyon Debris Basin & 
Channel 
Ventura River Levee 
Whitewater River, CA: 
Banning Levee-San Gorgonio 
River, Riverside County' 
Chino Canyon Improvements, Palm 
Springs' 
Tahchevah Creek Detention Basin 
and Channel Improvements 
Tahquitz Creek 
Winslow (tributaries of Little 
Colorado River), Little Colorado 
River Basin, AZ 
Completed 
Completed 
Completed 
Completed 
Active 
Completed 
Active 
Completed 
Active 
Active 
Completed 
Active 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed (part) 
& Deferred (part) 
1961 
1959 
1985 
1961 
1989 
1984 
1983 
1984 
1985 
1985 
1979 
1990 
1964 
1950 
1966 
1973 
1967 
1974 
1973 
617,890 
2,104,478 
9,258,207 
2,126,672 
2,112 
10,079,927 
4,790,173 
4,000,000 
632,158 
844,732 
1,703,031 
6,455,000 
939,908 
1,349,638 
97,868 
819,878 
1,420,552 
1,063,600 
1,831,300 
1. Authorized by Chief of Engineers under authority 
of section 205, Public Law 80-858, as amended. 
33-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 92 
TABLE 33-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report For Authority Expended Expended 
Hodges Dam, San Dieguito 
River Basin, CA 
Las Vegas Wash tributaries, 
Colorado River Basin, NV 
Aliso Creek Dam 
San Juan Dam 
Trabuco Dam 
Villa Park Dam 
Sierra Madre Wash Channel, 
Los Angeles County drainage 
area, CA 
1958 
1964 
1986 
1950 
1978 
Sec. 12, Public 
Law 93-251 
1977 
Sec. 12, Public 
Law 93,251 
Sec. 1002 Public 
Law 99-662 
1986 
Sec. 1002, Public 
Law 99-662 
1986 
Sec. 1002, Public 
Law 99-662 
1978 
Sec. 12, Public 
Law 93-251 
1986 
Sec. 1002, Public 
Law 99-662 
1986 
Sec. 1002, Public 
1986 
University Wash and Spring 1975 
Brook, Riverside, CA 
33-32 
$295,191 
67,361 
213,313

SAN FRANCISCO, CA, DISTRICT* 
This district comprises the Klamath River Basin in 
southern Oregon and portions of northern and western 
California consisting of drainage basins tributary 
to the Pacific Ocean from the Oregon-California 
State line on the north to Cape San Martin, CA, on 
the south, except for basins tributary to the San 
Francisco Bay system which lie east of the Benicia- 
Martinez Bridge. 
IMPROVEMENTS 
Navigation Page 
1. Oakland Harbor, CA ................ 34-1 
2. Richmond Harbor (Deepening), CA ..... 34-2 
3. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels) ..................... 34-3 
4. San Francisco Bay and Delta Model, CA.. 34-3 
5. San Francisco Bay Long Term 
Management Strategy (LTMS), CA .... .34-4 
6. Reconnaissance and Condition Surveys... 34-5 
7. Navigation Work under Special 
Authorization ...................... 34-5 
8. Beach Erosion Control Work under Special 
Authorization ...................... 34-5 
Flood Control 
9. Inspection of Completed Flood 
Control Projects .................... 34-5 
10. Flood Control Work under Special 
Authorization ..................... 34-5 
Navigation 
1. OAKLAND HARBOR, CA 
Location. Oakland Harbor is located in the City of 
Oakland, California, on the eastern shore of central 
San Francisco Bay immediately south of San 
Francisco-Oakland Bay Bridge. 
Existing project. Adopted by Acts of June 23, 
1874, June 25, 1910, September 22, 1922, January 
21, 1927, April 28, 1928, July 3, 1930, March 2, 
1945 and October 23, 1962. The project was 
completed February 1975, except for deepening the 
tidal canal to 35 feet from Fortman Basin to Park 
Street, and to 25 feet above Park Street which was 
deauthorized November 1977. Reconstruction of the 
Fruitvale Avenue Highway Bridge was completed in 
December 1973 and turned over to local interests for 
operation and maintenance. Project consists of 
entrance channel to Oakland Outer Harbor, 35 feet 
deep from deep water in San Francisco Bay and 800 
feet wide across the shoal southeast of Yerba Buena 
Island, narrowing to 600 feet at Oakland Mole; 
thence, a channel and turning basin 35 feet deep and 
from 600 to 950 feet wide in outer harbor to the Army 
11. Miscellaneous Work under Special 
Authorization ...................... 34-5 
General Investigations Page 
12. Surveys ........................... 34-5 
13. Collection and Study of Basic Data ...... 34-6 
14. Preconstruction Engineering and Design.. 34-6 
Tables 
Table 34-A 
Table 34-B 
Table 34-C 
Table 
Table 
Table 
Table 
Table 
34-D 
34-E 
34-F 
34-G 
34-H 
Cost and Financial 
Statement ................ 34-7 
Authorizing 
Legislation .............. 34-11 
Other Authorized 
Navigation Projects ........ 34-13 
Not Applicable 
Not Applicable 
Not Applicable 
Deauthorized Projects ...... 34-13 
Inspection of Completed Flood 
Control Projects .......... 34-14 
Base. Project also provides entrance channel to 
Oakland Inner Harbor, 35 feet deep and 600 feet 
wide to west end of Government Island, with 
additional widening to within 75 feet of the pierhead 
line in front of Grove and Market Street (formerly 
municipal) piers and along the south side of the 
channel from Harrison Street eastward to harbor line 
point 119 in Brooklyn Basin; a channel 35 feet deep 
and 500 feet wide through Brooklyn Basin; for a 
triangular area 35 feet deep about 2,700 feet long and 
maximum width of 300 feet at western end of 
Brooklyn Basin; a channel along north side of 
Brooklyn Basin which is 35 feet deep and 300 feet 
wide for 1,300 feet, thence 25 feet deep and 300 feet 
wide for 3,700 feet to a turning basin at east end of 
Brooklyn Basin which is 35 feet deep, 500 feet wide, 
and 1,200 feet long; a channel in the tidal canal 35 
feet deep and 275 feet wide from Brooklyn Basin to 
Park Street, thence 18 feet deep to San Leandro Bay; 
a total channel length of 8-1/2 miles from San 
Francisco Bay to San Leandro Bay. Project also 
includes parallel rubblemound jetties at entrance to 
inner harbor, north jetty 9,500 feet long and south 
jetty 12,000 feet long; three highway bridges across 
the tidal canal, two of which (at Park Street and High 
Street) have been replaced by local interests and the 
34-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Fruitvale Avenue Bridge constructed by Federal 
Government has been transferred to Alameda 
County. The railroad bridge has been transferred to 
the County for operation and maintenance. The 
Federal Government will reimburse the County for 
the cost of operating and maintaining the railroad 
bridge. 
Water Resources Development Act (WRDA) of 
1986 authorized deepening the 4 mile Inner and 3.4 
mile Outer Harbors channels to 42 feet deep and 
widening the entrance channel to 1,000 feet; 
relocation of the Outer Harbor turning basin 3,000 
feet westward; and widening the turning basin to 
1,800 feet and constructing a 1,200 foot turning basin 
in the Inner Harbor, 42 feet deep, at mile 3.7. 
Present estimated total cost for the authorized 
improvements is $80,200,000 of which $60,150,000 
is Federal cost (includes $100,000 Coast Guard cost) 
and $20,050,000 is non-Federal cost. Under WRDA 
1986, the Bar Channel and Inner Harbor were 
deepened to 38 feet deep up to Howard Terminal as a 
separable element of the authorized 42-foot deep 
project. 
Local cooperation. The Port of Oakland has 
indicated its intent to sign the Local Cooperation 
Agreement satisfying the requirements of the Water 
Resources Development Act of 1986, PL 99-662. 
The local sponsor must comply with the following 
requirements: (1) provide lands, easements, 
rights-of-way, and dredged material disposal areas; 
(2) pay 25 percent of the costs allocated to deep draft 
navigation during construction; and (3) pay 
additional 10 percent plus interests of the costs 
allocated to deep draft navigation within a period of 
30 years following completion of construction. 
Terminal facilities. The port occupies 19 miles 
on the mainland shore of San Francisco Bay. There 
are 550 acres of marine terminal facilities, 28 
deepwater berths and 25 container cranes, including 
5 of the post Panamax type. On-dock covered 
storage space exceeds 600,000 square feet. Three 
major railroads, Santa Fe, Southern Pacific and 
Union Pacific serve the port. 
Operations during fiscal year. New Work: 
Sediment testing, ocean site baseline and initial monitoring 
studies, preparation of SEIS draft and GDM 
draft. Maintenance: Operations and maintenance of 
Fruitvale Avenue R.R. Bridge including engineering 
and design by hired labor, cost $755,359; and new 
work dredging removing 517,100 cubic yards of material 
from the Inner Harbor, cost $665,319. 
2. RICHMOND HARBOR 
(DEEPENING), CA 
Location. Richmond Harbor is located in central 
San Francisco Bay, in Contra Costa County in the 
City of Richmond. 
Existing project. The existing navigation channel 
extends from deep water in San Francisco Bay into 
the Port of Richmond. The Southhampton Shoal 
Channel and Long Wharf Maneuvering Area, at the 
entrance to the harbor channels are maintained to 
-45 feet MLLW. The Entrance Channel, Potrero 
Reach Channel, Potrero Sharp Turn, Inner Harbor 
and about half of the Santa Fe Channel, to -35 feet 
and the remainder of the Santa Fe Channel to -30 
feet. The width of the navigation channel is 600 feet 
for most of its length to Point Richmond with two 
maneuvering areas: one in front of the Long Wharf 
and the other at Point Richmond. At Potrero Reach, 
the 500 foot width flares to about 600 feet at Point 
Potrero with a turn at the point, 1,150 feet wide and 
35 feet deep except for a depth of 30 feet at the 
southerly apex of the bend. Thence, the channel 
continues into the inner harbor at a width of 850 feet 
in a northerly direction to the entrance of the Santa 
Fe Channel. The Santa Fe Channel extends 
northwesterly at a width of 200 feet into the upper 
basin terminus. A turning basin is provided at Point 
Richmond, and a rubble-mound training wall 
extending 10,000 feet westerly from Brooks Island is 
also provided in the Potrero Reach. For details, see 
page 1977 of Annual Report for 1915 and page 1646 
of Annual Report for 1938. 
Proposed improvements consist of a two-phased 
construction plan involving four and one-half miles of 
channel between Richmond Long Wharf and the 
Santa Fe Channel. Phase I would deepen the existing 
35-foot channels to 38 feet, and provide a turning 
basin of 1,200 feet in diameter near Point Potrero. 
Approximately 1,500,000 cubic yards of sediment 
are to be dredged and transported to an aquatic and 
upland disposal site, depending on the sediment 
quality. 
The estimated cost of Phase I is $19,300,000 of 
which $15,050,000 is Federal cost (includes $50,000 
Coast Guard costs) and $4,250,000 is non-Federal 
cost. Phase II has been deferred and is reclassified to 
the inactive category. 
The existing project was authorized on October 27, 
1965. Previous projects were authorized by Acts 
adopted in 1917, 1930, 1935, 1938, 1945 and 1954. 
The proposed improvements are authorized by the 
Water Resources Development Act of 1986, PL 
99-662. 
Local cooperation. In accordance with the cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, the local 
sponsor must comply with the following requirements: 
(1) pay 10 percent of the costs to 20 feet below mean 
lower low water and 25 percent of costs between 20 
and 45 feet below mean lower low water and (2) 
reimburse an additional 10 percent of the costs 
allocated to general navigation facility of the project 
within a period of 30 years following completion of 
construction; and (3) provide all lands, easements, 
rights-of-way, relocation and dredged material 
34-2

SAN FRANCISCO, CA, DISTRICT 
disposal areas necessary for the projects. The value 
of lands, easements, rights-of-way and dredge 
disposal areas can be credited toward the payment 
required under item (2) above. The agreement is 
scheduled to be executed in August 1994. 
Terminal activities. The Port of Richmond encompasses 
nine privately-owned terminals and seven 
terminals owned by the Port. 
Operations during fiscal year. New Work: 
Continued preconstruction planning and engineering. 
Maintenance: Operations and maintenance of 
Richmond Inner, Outer Harbors including 
engineering and design and U.S. Hopper dredge 
Essayons. Essayons removed 171,193 cubic yards 
of shoal material from Inner Harbor and 175,014 
cubic yards from the Outer Harbor, cost $2,441,777. 
3. SAN FRANCISCO BAY TO STOCKTON, 
CA (JOHN F. BALDWIN AND STOCKTON 
SHIP CHANNELS) 
Location. John F. Baldwin Ship Channel. 
Navigation channels extending from entrance to San 
Francisco Bay to Suisun Bay near Martinez through 
San Francisco, Marin, Contra Costa, and Solano 
Counties. (See National Ocean Service Charts 18649, 
18654 and 18656 for respective areas.) 
Existing project. Project provides for 
modification of the existing San Francisco Harbor, 
Richmond Harbor, San Pablo Bay and Suisun Bay 
Channels to the vicinity of Martinez to provide depths 
of 55 feet for San Francisco Bar Channel, 45 feet 
(currently 35 feet) for main internal bay channels 
upstream to the vicinity of Martinez; enlargement and 
deepening to 45 feet (currently 35 feet) of 
maneuvering areas adjacent to major petroleum 
refinery terminals along the channel route. San 
Francisco Harbor Main Channel was completed in 
February 1974. The South Hampton Shoal Channel 
and the Richmond Long Wharf manevering area was 
completed in December 1986. For the approved cost 
estimate (1991) of Federal cost (Corps), see 
Sacramento District Annual Report. Existing project 
was adopted by 1965 River and Harbor Act (H. Doc. 
208, 89th Cong., 1st sess., contains latest published 
map). 
Local cooperation. See Sacramento District 
Annual Report. The local sponsor, Contra Costa 
County, supports the project. 
Terminal facilities. See Port Series No. 30, 
revised 1991, No. 31, revised 1982, and No. 32, 
revised 1986, titled respectively: "The Ports of San 
Francisco, Redwood City, and Humboldt Bay, 
Calif."; "The Ports of Oakland, Alameda, 
Richmond, and the Ports on Carquinez Strait, 
Calif."; and "The Ports of Sacramento, Stockton, 
Pittsburg, and Antioch, Calif." Facilities are 
considered adequate for existing commerce and will 
be adequate for future commerce upon completion of 
new terminal facilities. 
Operations during fiscal year. New Work: 
Continued planning engineering and design activities. 
4. SAN FRANCISCO BAY-DELTA 
MODEL STRUCTURE, CA 
Location. The model, including a Class A regional 
visitor center, is located in Sausalito, CA, adjacent to 
San Francisco Bay about two miles north of the 
Golden Gate Bridge. 
Existing project. The San Francisco Bay/Delta 
Model, which covers 17 miles of the Pacific Ocean 
beyond the Golden Gate, all of San Francisco Bay 
proper, San Pablo Bay, Suisun Bay, and all of the 
Sacramento-San Joaquin Delta east of Suisun Bay to 
the cities of Sacramento on the northeast and 
Stockton and Tracy on the south, was constructed in 
a rehabilitated warehouse at Sausalito, CA, as a part 
of the San Francisco Bay and Tributaries, CA, Study 
authorized by the River and Harbor Act of May 17, 
1950 (PL 81- 516, Section 110). The model was 
authorized as an operation and maintenance project 
in the Water Resources Development Act of 1974 
(PL 93-251, Section 8). The model successfully 
reproduces to the proper scale the rise and fall of the 
tide, flow and currents of water, salinity intrusion, 
and trends in disposition of sediments. It is a useful 
tool to examine forces existing in the bay and 
estuarine system and to predict results of proposed 
changes. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: 
Operation and maintenance of the model continues. 
A contract with U.C. Berkeley was consummated 
December 1991 for the joint operation and 
management of the physical Bay Model for a 
one-year period with two option years available 
depending on the anticipated cost savings of the 
program. 
Historical summary. Original model construction 
was initiated 1956 and completed 1957. The addition 
of the Sacramento-San Joaquin Delta to the original 
model was initiated 1966 and completed 1969. 
Annual visitation to the model averages between 
100,000 to 125,000 people. The central exhibits 
were completed in December 1981. Extensive 
exhibit upgrade for the Visitor Center and development 
of Cooperative Association completed September 
30, 1989. The Cooperative Association provides 
financial and educational support to visitor center 
programming. An active volunteer program exists at 
the Visitor Center providing approximately 80 
man-days of effort monthly. Continued testing of 
proposals affecting the environmental quality of the 
region including, but not limited to: salinity intrusion, 
dispersion of pollutants, water quality, improvements 
for navigation, dredging, bay fill, physical structures, 
34-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
and other shoreline changes. Total cost of regional 
visitor exhibits and model as of September 30, 1992, 
was $22,413,233, of which $8,504,456 was for the 
regional visitor center, $1,288,219 for exhibits, and 
$12,620,558 for maintenance. 
5. SAN FRANCISCO BAY LONG TERM 
MANAGEMENT STRATEGY (LTMS), 
CA 
Location. The San Francisco Bay Long-Term 
Management Strategy (LTMS) for dredged material 
disposal covers deep and shallow draft navigation 
channels of the San Francisco Bay region including 
Central San Francisco Bay, South Bay, San Pablo 
Bay and Suisun Bay environs. 
Existing project. The San Francisco Bay region 
has an annual disposal requirement of approximately 
8 million cubic yards (mcy) to maintain navigation 
channels. The Bay also has a one-time new civil 
works requirement of approximately 19 mcy for the 
Oakland Harbor, Richmond Harbor, and John F. 
Baldwin Phase III ship channel as well as two Navy 
deepening projects. In January 1990, the Army 
Corps of Engineers, the Environmental Protection 
Agency, Region IX, the San Francisco Bay Water 
Quality Control Board and the San Francisco Bay 
Conservation and Development Commission 
convened with thirty interested agencies and 
organizations with concerns regarding dredged 
material disposal in San Francisco Bay. These four 
agencies have the responsibility for regulation of the 
waters of the US and California for disposal of 
dredged material. 
The four agencies and the concerned navigation 
interests formed the LTMS to develop technically 
feasible, economically prudent and environmentally 
acceptable long range solutions to the dredging and 
disposal needs for the San Francisco Bay region over 
the next fifty years. In determining acceptable 
dredged material disposal locations, the LTMS 
evaluated a broad array of potential ocean, in-Bay 
and non-aquatic disposal alternatives. The 
combined study and staff cost of the effort is 
$16,185,000 and is scheduled for completion in 
August 1994. 
Local cooperation. Pursuant to their regulatory 
responsibilities, the Division commander of the South 
Pacific Division, Corps of Engineers; the Regional 
Administrator of the Environmental Protection 
Agency, Region IX; the Chair of the San Francisco 
Bay Regional Water Quality Board and the Chair of 
the San Francisco Bay Conservation and 
Development Commission agreed to jointly 
undertake the development and implementation of a 
Long Term Management Strategy (LTMS) for 
dredging and disposal of dredged materials from the 
region, Based on the outputs from the LTMS, the 
Regional Water Quality Control Board and the Bay 
Conservation and Development Commission will 
consider modifications to the dredging elements of 
their respective Basin and Bay Plans for San 
Francisco Bay. 
Terminal facilities. Besides identifying 
implementable disposal options, the LTMS will: (1) 
develop coordinated regional disposal policies 
between federal and state agencies; (2) provide a 
local decision-making framework for dredging and 
disposal projects; (3) streamline existing permit and 
testing procedures; and (4) provide a long term site 
monitoring apparatus and feedback mechanism. 
Operations during fiscal year. The LTMS has 
three work groups investigating disposal options. 
Their progress and accomplishments for FY 1992 are 
listed below: 
(1) In-Bay Studies Work Group - 
A. A standard methods manual for 
chemical analyses was developed and scheduled for 
review in FY 1993. 
B. Sediment toxicity contract was awarded 
to look at toxicity test interferences and review 
approaches for assessing sub-lethal, chronic 
sediment evaluations. 
C. Field work necessary to enhance current 
numerical model predictions of the fate of discharged 
dredged material was completed. 
D. Detailed plan for future field and 
laboratory work to evaluate bioaccumulation 
potential in Central Bay from Alcatraz disposal was 
completed. 
E. Field study to assess contaminant 
concentrations in salmon traversing San Francisco 
Bay, currently being conducted by the National 
Marine Fishery Services (NMFS), was partially 
funded. 
(2) Nonaquatic/reuse Studies Work Group - 
A. A comprehensive list of nonaquatic sites 
was developed for the region identifying 
approximately ninety options - the list was narrowed 
to 3 to 5 sites in the fall. 
B. Land Use and Engineering Elements 
contracts were awarded; the first looked at laws 
(Federal/State) and policies (local land use) 
influencing upland disposal and the second analyzed 
the sediment reuse alternatives from rehandling 
facilities.
C. Some portion of material destined for 
upland disposal may be unsuitable for open water 
disposal or defined as "contaminated" thus there will 
be a need to identify public benefits (eg., wetland, 
levee stabilization, etc.) to offset public concerns. 
Work was begun on identifying these benefits. 
(3) Ocean Studies Work Group - 
A. Ocean study areas and potential sites 
within these study areas were investigated as well as 
the proposed Monterey Bay Sanctuary boundary for 
physical and biological parameters. 
B. Velocity plots to display current patterns 
in the study areas were developed at four depths - 
no stratification was seen but that flow was fairly 
constant to the North. 
C. Numerical models to predict depositional 
patterns were used to generate a 10-mm footprint 
34-4

SAN FRANCISCO, CA, DISTRICT 
which in turn was used to delineate potential site 
boundaries. 
D. Benthic and trawl samplings were used to 
characterize the biological communities at the various 
study areas and these studies indicated that organisms 
proved to be depth stratified with the richest 
communities found at shallower depths. 
E. EPA and its consultants prepared an 
administrative draft and public draft of the 
Environmental Impact Statement for the ocean site 
designation process. 
6. RECONNAISSANCE AND 
CONDITION SURVEYS 
Reconnaissance and condition surveys of channels 
to be dredged in years other than Fiscal Year 1992 
and jetty structures were conducted on the following 
projects: Bodega Bay; Fisherman's Wharf; Monterey 
Harbor; Moss Landing Harbor; Napa River; Petaluma 
River; Pillar Point Harbor; San Francisco Harbor; 
San Leandro Marina; San Rafael Creek; Santa Cruz 
Harbor; and Suisun Channel; all in California. Fiscal 
year costs were $755,796 of which $105,000 was for 
jetty condition surveys and $650,796 for project condition 
surveys. 
7. NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
Navigation activities pursuant to Section 107, 
Public Law 86-645 (preauthorization). 
Fiscal year cost for preauthorization studies was 
$30,694 for San Leandro Channel, CA. 
Mitigation of shore damages activities pursuant 
to Section 111, Public Law 90-483 (preauthorization). 
Fiscal year cost for preauthorization studies was 
$43,122 for Moss Landing Harbor, CA. 
8. BEACH EROSION CONTROL WORK 
UNDER SPECIAL AUTHORIZATION 
Beach erosion control activities pursuant to Section 
103, Public Law 87-874 (preauthorization). 
Fiscal year cost for preauthorization studies was 
$33,675 for Emeryville, Alameda County, CA. 
9. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Section 3, Flood Control Act of June 22, 1936, as 
amended and supplemented, included a requirement 
that local interests maintain and operate completed 
flood control works in accordance with regulations 
prescribed by the Secretary of War. Inspections made 
throughout the year to determine effectiveness of 
operation and maintenance by local interests of 
completed local protection projects and works 
constructed under emergency and special authorities 
of Sections 205 and 208 of the 1948 Flood Control 
Act, Section 14 of the 1946 Flood Control Act, and 
Public Law 99, 84th Congress. Fiscal year cost was 
$124,227. Total cost to September 30, 1992 was 
$2,776,130. See Table 34-H for inspections made 
this fiscal year. 
10. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood Control activities pursuant to Section 
205, Public Law 858, 80th Congress, as amended 
(preauthorization). 
Fiscal year costs were $282,409 for 
preauthorization studies of which $48 was for Las 
Gallianas Creek, Marin County, CA; $268,955 for 
Petaluma River, Sonoma County, CA; $152 for 
Rohner Creek, Fortuna, CA; $9,676 for San Pedro 
Creek, Pacifica, CA; and $3,578 for White Slough, 
CA. 
Emergency flood control activities-repair, flood 
fighting and rescue work (Public Law 99, 84th 
Congress, and antecedent legislation). 
Fiscal year cost incurred for emergency flood 
control activities was $402,688 for disaster 
preparedness. Technical assistance was provided on 
the East Bay fire to prevent soil erosion using PL-99 
funds. FY 1992 costs $17,240; estimated damages 
prevented $20,000,000. 
Emergency bank protection (Section 14, 1946 
Flood Control Act, Public Law 526, 79th 
Congress). 
Fiscal year total costs were $25,265, of which 
$23,167 was for Salinas River, San Ardo, CA; and 
$2,098 for Shelter Cove, CA. 
11. MISCELLANEOUS WORK UNDER 
SPECIAL AUTHORIZATION 
Project Modification for Improvement 
Environmental (Section 1135, PL 99-662). 
of 
Fiscal year total costs were $62,196, of which 
$1,581 was for Redwood Creek, CA and S60,615 for 
Sonoma Bay Wetlands, CA. 
General Investigations 
12. SURVEYS 
Fiscal year costs for surveys were $2,335,548, of 
which $728,153 was for navigation studies; 
$1,139,192 for flood damage prevention; $124,155 
for miscellaneous activities; $206,878 for special 
studies; $135,474 for shoreline protection studies; 
and $1,696 for coordination studies with other 
agencies. 
34-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
13. COLLECTION AND STUDY OF 
BASIC DATA 
Fiscal year total costs of $18,255 were incurred, of 
which $10,966 was for flood plain management service 
program; $5,414 for hydrologic studies; and 
$1,875 for environmental data studies. 
14. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
NOYO RIVER AND HARBOR, CA 
Noyo River rises in the Coast Range, flows westerly, 
and empties into Noyo Harbor. Noyo Harbor is a 
cove on the California Coast about 87 miles south of 
Humboldt Bay and 135 miles northwest of San 
Francisco. The 1962 Rivers and Harbors Act, 
modified by the 1976 Water Resources Development 
Act, authorized up to two breakwaters as necessary to 
provide protection. The 1976 Water Resources 
Development Act, as modified by the Water 
Resources Development Act of 1986, authorized 
construction of additional channel improvements. 
Recommended plans of improvement for the 
breakwater and channel improvement were previously 
considered as a single project. Due to 
significant differences in the time required for 
planning and construction, each part is now reported 
separately. 
The plan of improvement for Noyo River and 
Harbor (Breakwater), CA provides for one detached 
offshore 400-foot breakwater aligned in a northsouth 
direction along the southern portion of Noyo 
Cove, west of the entrance channel in Noyo Harbor. 
Estimated preconstruction planning cost is 
$4,460,000. Total costs during the fiscal year were 
$238,490 with General Investigation funds. Planning 
is about 55 percent complete. A Project 
Management Plan was prepared to outline the work 
remaining on this project. The breakwater will be 
ready for construction in February 1996, at an 
estimated cost of $15,300,000. 
The plan of improvement for Noyo River and 
Harbor (Channel Extension), CA provides for a 
60-foot wide channel, 7 feet deep, for a distance of 
about 3,000 feet upstream from the end of the 
existing Federal project to the Dolphin Isle Marina. 
Estimated preconstruction planning cost is $580,000. 
This project has been put in an inactive category at 
the request of the sponsor. 
34-6

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
Bodega Bay, CA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major rehab. 
Approp. 
Cost 
Crescent City New Work 
Harbor, CA Approp. 
Cost 
Maint. 
Approp 1 
Cost 1 
Major rehab. 
Approp. 
Cost 
Fisherman's Wharf New Work 
Areas, San Francisco Approp. 
Harbor, CA Cost 
Maint. 
Approp. 
Cost 
Humboldt Harbor New Work 
and Bay, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
Moss Landing New Work 
Harbor, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
Napa River, CA New Work 
Approp. 
Cost 
Maint. 
Approp. 1 
Cost 1 
Noyo River and New Work 
Harbor, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
Oakland Harbor, New Work 
CA Approp. 1 
Cost 2, 
(Federal Funds) Maint. 
Approp. 2, 
Cost 2 
(Contrib. Funds) New Work 
Contrib. 
Cost 
- - - - $1,226,765 1 2 40 
- - - - 1,226,765 1 3 40 
$34,358 158,835 839,307 155,052 2,343,708 4 40 
34,362 158,835 664,823 253,491 2,267,663 4 40 
- - - - 397,779 5 
- - - - 397,779 5 
- - - - 9,454,972 6 40 
- - - - 9,454,972 6 40 
,213,875 201,711 725,489 971,927 23,984,354 7 4o 
,210,973 207,212 719,206 984,935 23,968,981 7 40 
- - - - 525,000 8 
- - - - 525,000 8 
- - - - 9,199,000 41 48 50 
2,057 - - 9,199,000 41 49 50 
7,894 17,610 29,376 382,007 436,877 51 
7,894 17,610 29,376 269,691 324,571 51 
- - - - 9,847,299 9 40 
- - - - 9,847,299 9 40 
853,000 3,358,159 3,701,945 2,076,040 68,920,785 10 40 
814,563 3,287,440 2,973,797 2,917,775 68,910,333 10 40 
- - - - 338,215 11 40 
- - - - 338,215 11 40 
59,018 534,403 83,897 41,472 5,165,574 12 40 
65,968 526,338 91,838 41,596 5,165,574 12 40 
- - - - 1,021,274 13 40 
- - - - 1,021,274 13 40 
,321,300 2,948 253,046 227,360 4,375,288 13 14 40 
,291,094 34,770 253,046 227,360 4,375,288 13 14 40 
141,000 109,000 - 354,000 2,705,482 15 16 40 
474,448 114,670 8,068 238,490 2,589,972 15 1740 
53,875 498,562 219,600 33,000 7,843,691 18 19 40 
65,482 496,742 228,602 24,862 7,832,416 18 1940 
- - - - 222,810 20 40 
- - - - 222,810 20 40 
,976,000 
,836,782 
,009,000 
,053,312 
- 
3,364,000 
3,066,269 
2,355,098 
2,369,732 
5,245,000 1,930,000 
5,492,399 1,946,689 
1,592,900 1,380,011 
1,529,707 1,451,690 
- 1,010,000 
- 400,000 
27,317,684 21 
27,154,741 21 
40,592,355 22 
40,590,246 22 
1,010,000 
400,000 
34-7 
1.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
Petaluma River, CA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Pillar Point New Work 
Harbor, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
Redwood City New Work 
Harbor, CA Approp. 
Cost 
Maint. 
Approp 
Cost 
2. Richmond Harbor, New Work 
CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor rehab. 
Approp. 
Cost 
3. San Francisco Bay New Work 
to Stockton, CA Approp. 
(John F. Baldwin Cost 
and Stockton Ship 
Channels) 
4. San Francisco Bay New Work 
and Delta Model, Approp. 
CA Cost 
Maint. 
Approp. 
Cost 
5. San Francisco Bay Maint. 
Long Term Approp. 
Management Cost 
Strategy (LTMS), CA 
San Francisco New Work 
Harbor, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
San Francisco New Work 
Harbor and Bay, CA Approp. 
(Removal of Drift) Cost 
Maint. 
Approp. 
Cost 
San Leandro New Work 
Marina, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
297,146 23 40 
297,146 23 40 
736,454 
857,991 
4,604 
6,159 
61,554 
61,554 
448,576 2,704,180 
444,208 2,684,564 
437,000 778,000 
975,507 635,180 
- 1,046,000 11,484,711 24 40 
-947 651,685 11,088,867 24 40 
- - 6,697,396 4 44 
- - 6,697,396 43 44 
8,731 
8,731 
367 2,167,846 44 45 
367 2,167,846 44 45 
- 1,672,722 25 40 
- 1,672,722 25 40 
144,629 790,142 
116,657 842,097 
878,000 831,000 
924,710 855,848 
11,565,519 26 40 
11,565,518 26 40 
8,114,527 27 28 
8,034,259 27 28 
2,589,440 1,195,171 2,187,020 2,392,165 27,357,738 29 40 
2,596,465 1,167,042 2,193,492 2,441,777 27,356,989 29 40 
- - - - 164,689 
- - - - 164,689 
1,186,000 2,500,000 835,000 1,142,000 33,488,200 
1,759,997 1,262,488 1,983,042 1,277,722 33,451,719 
1,880,000 1,668,234 1,750,100 
1,820,403 1,590,145 1,555,679 
- - 5,134,000 
- - 4,161,254 
2,622,883 
2,623,639 
2,623,000 
2,408,495 
22,833,917 
22,413,235 
7,757,000 
6,569,749 
- - - - 2,689,356 283040 
- - - - 2,689,356 28 30 40 
1,282,785 3,577,625 -737,420 1,184,069 32,001,789 31 40 
1,438,119 2,113,134 765,563 1,191,122 32,000,593 31 40 
1,317,000 1,740,098 1,666,300 1,948,000 30,522,580 40 
1,426,004 1,671,508 1,792,754 1,902,153 30,436,186 40 
815,663 303,167 29,349 66,617 2,533,141 32 
815,127 303,683 29,369 66,617 2,533,141 32 
34-8

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
San Pablo Bay New Work 
and Mare Island Approp. - - - - 1,369,372 28 33 40 
Strait, CA Cost - - - - 1,369,372 28 33 40 
Maint. 
Approp. 994,034 851,430 1,129,300 1,031,000 39,107,943 40 
Cost 1,120,892 857,128 1,110,685 1,046,892 39,100,345 34 40 
San Rafael, CA New Work 
Approp. - - - - 32,359 40 47 
Cost - - - - 32,359 40 47 
Maint. 
Approp. - - 691,825 104,684 4,613,471 40 4 
Cost 4,026 1,047 376,634 420,311 4,613,471 40 48 
Santa Cruz New Work 
Harbor, CA Approp. - - - - 4,126,808 2 
(Federal Funds) Cost 755 - - - 4,126,808 s2 
(Contrib. Funds) New Work 
Contrib. - - - - 160,000 36 
Cost - - - - 160,000 3 
Maint. 
Approp. - 22,821 - 5,527 9,629,008 40 3 
Cost 8,808 22,821 - 5,527 9,629,008 40 5 
Suisun Bay New Work 
Channel, CA Approp. - - - - 200,928 " 
Cost - - - - 200,928 3 
Maint. 
Approp. 250,717 875,268 402,700 662,917 5,424,162 37 40 
Cost 253,884 864,137 407,427 623,374 5,378,014 37 40 
Suisun Channel, CA New Work 
Approp. - - - - 217,677 3 
Cost - - - - 217,677 38 
Maint. 
Approp. 88,765 491,711 466,600 78,810 2,717,028 39 
Cost 88,765 470,441 481,652 85,028 2,717,028 39 
1. Includes $641,800 for jetties, bulkheads, 
main Bodega Bay Channel and turning basin completed 
in 1943. 
2. Includes $585,000 for Preconstruction Planning 
($456,000 Construction, General funds and 
$129,000 General Investigation funds). 
3. Includes $585,000 Preconstruction Planning 
costs ($456,000 Construction General costs and 
$129,000 General Investigation costs). 
4. Includes $497, 158 for reconnaissance and 
condition surveys, FY 1956-1992. Excludes contribution 
funds of $245,895. 
5. Excludes contribution funds of $2,000. 
6. Excludes contributed funds of $271,116 and 
$2,138 surplus material from Corps military activities. 
7. Excludes contributed funds of $44,340. 
Includes $80,284 for reconnaissance and condition 
surveys, FY 1956-1992. 
8. Excludes $2,000 contributed funds in lieu of 
royalty-free rock. 
9. Includes $2,261,371 for previous project. 
Excludes $95,000 contributed funds for existing 
project. 
10. Includes $98,206 for previous project and 
$1,710 for reconnaissance and condition surveys, 
FY 1956-1992. 
11. Excludes $5,337 previous project costs. 
12. Excludes $8,539 surplus material from Corps' 
military activities. Includes $211,180 for reconnaissance 
and condition surveys, FY 1956-1992. Excludes 
contributed funds of $180,200. 
13. Excludes previous project costs. 
14. Includes $757,862 for reconnaissance and 
condition surveys, FY 1956-1992. Excludes $492,788 
contributed funds. 
15. Includes $11,985 for previous project. 
Excludes $7,180 contributed funds for previous 
project. 
16. Includes $2,407,000 for Preconstruction 
Planning ($1,827,000 for Breakwater of which 
$500,000 allocated under Construction, General and 
$1,327,000 under General Investigations); ($580,000 
for Channel Extension of which $165,000 allocated 
under Construction, General and $415,000 under 
General Investigations). 
17. Includes $2,291,490 Preconstruction cost 
($1,711,490 for Breakwater of which $500,000 was 
under Construction, General and $1,211,490 under 
General Investigations); ($580,000 for Channel 
Extension of which $165,000 was under Construction, 
34-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 34-A (Cont'd) COST AND FINANCIAL STATEMENT 
General and $415,000 under General Investigations). 
18. Includes $32,097 for previous project and 
$19,311 for reconnaissance and condition surveys, FY 
1956-1992. Excludes contributed funds of $820 for 
previous project. 
19. Excludes contributed funds of $4,000 in lieu 
of providing dike disposal areas on existing project. 
20. Excludes contributed funds of $1,700. 
21. Includes $2,899,232 for previous projects. 
Excludes $397,266 contributed funds on existing project.
22. Includes $684,028 for previous projects and 
$31,785 for reconnaissance and condition surveys, FY 
1956-1992. 
23. Includes $212,083 for previous project. Excludes 
contributed funds of $15,559 for previous project.
24. Includes $314,692 for previous project and 
$156,190 for reconnaissance and condition surveys, 
FY 1956-1992. Excludes contributed funds of 
$192,424. 
25. Includes previous project costs $31,443. Excludes 
$119,572 contributed funds for existing project. 
26. Includes $380,789 for reconnaissance and 
condition surveys, FY 1956-1992. 
27. Excludes contributed funds of $524,778. 
Includes $105,000 Public Works Administration funds. 
28. Excludes modification authorized October 
27, 1965, under project "San Francisco Bay to Stockton, 
CA (John F. Baldwin and Stockton Ship Channels)." 
29. Excludes $34,800 contributed funds. Includes 
$3,364 for reconnaissance and condition surveys, 
FY 1956-1992. 
30. Includes $1,030,399 for previous projects. 
Excludes $134,591 contributed funds for existing 
project. Includes $193,000 Public Works Administration 
funds. 
31. Includes $475,321 for previous projects and 
$407,492 for reconnaissance and condition surveys, 
FY 1956-1992. 
32. Authorized by FC Act of 1965 (Sec. 201); 
Maintenance R&H Act of 1970 (Sec. 103). Includes 
$245,885 for reconnaissance and condition surveys FY 
1979-1992. See FY 1977 Annual Report for last full 
report. Excludes contributed funds of $879,454. 
33. Includes $1,086,703 for previous projects. 
34. Includes $1,359,380 for previous projects and 
$32,832 for reconnaissance and condition surveys, FY 
1956-1992. 
35. Excludes $810,046 contributed funds on previous 
project. 
36. See Sacramento District FY 1974 Annual 
Report for detail. 
37. Project maintenance responsibility to Point 
Edith was transferred to San Francisco District January 
1, 1974. Excludes Sacramento District's portion. 
Includes $48,735 for reconnaissance and project condition 
surveys, FY 1976-1992. 
38. Project maintenance assigned to San Francisco 
District from Sacramento District January 1, 
1974. See Sacramento District 1972 Annual Report 
for full report. 
39. Includes $451,208 for reconnaissance and 
condition surveys, FY 1978-1992. Includes $727,510 
for previous project. Excludes $121,386 contributed 
funds. 
40. See FY 1981 Annual Report for last full 
report. 
41. Excludes Contributed Funds of $709,624. 
42. See Sacramento District FY 1985 Annual 
Report for full report. 
43. Excludes $100,000 contributed funds and 
$105,000 contributed in lieu of royalty-free rock. 
44. See FY 1979 Annual Report for last full 
report. 
45. Includes $101,046 for reconnaissance and 
condition surveys, FY 1970-1992. 
46. Includes $186,699 for reconnaissance and 
condition surveys, FY 1970-1992. Excludes $93,500 
contributed funds. 
47. Excludes $41,094 contributed funds. 
48. Includes $9,199,000 funds of which 
$8,499,000 was under Construction, General and 
$700,000 under General Investigations. 
49. Includes $9,199,000 costs of which 
$8,499,000 was under Construction, General and 
$700,000 under General Investigations. 
50. See FY 1987 Annual Report for last full 
report. 
51. Includes $55,562 for reconnaissance and 
condition surveys, FY 1989-1992. 
52. See FY 1988 Annual Report for last full 
report. 
53. Includes $28,348 for reconnaissance and condition 
surveys, FY 1992. 
34-10

TABLE 34-B 
SAN FRANCISCO, CA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
June 23, 1874 
June 25, 1910 
Sep. 22, 1922 
Jan. 21, 1927 2 
Apr. 28, 1928 
July 3, 1930 
Mar. 2, 1945 
Mar. 2, 1945 
Oct. 23, 1962 3 
Nov. 17, 1986 
2. 
Aug. 8, 1917 
July 3, 1930 
Aug. 30, 1935 4 
OAKLAND HARBOR, CA 
Jetties. 
North channel in Brooklyn Basin, 25 feet deep, 
and tidal canal to 18 feet. 
Channel across shoal southeast of Yerba Buena 
Island and thence to Webster St.; South 
channel in Brooklyn Basin; Turning Basin at 
east end of Brooklyn Basin; and channel in 
Tidal Canal from Brooklyn Basin to Park St., 
30 feet deep. 
Channel from Webster St. to Brooklyn Basin, 
maintain area to within 75 feet of pierhead 
line south of channel from Harrison St. to 
Harbor Line Point 119 in Brooklyn Basin; 
dredge a triangular strip about 2,700 feet long 
and maximum width of 300 feet at western 
end of Brooklyn Basin, 30 feet deep. 
Local cooperation requirements modified to 
provide alteration or replacement of bridges by 
local interests shall apply only to that feature of 
project covering deepening tidal canal to 25 feet. 
Drawbridges across Tidal Canal were required by 
1882 Decree of Court in condemnation proceedings 
whereby title was obtained to rightof-
way for tidal canal. 
Entrance channel to outer harbor, 800 to 600 
feet wide. 
Eliminated requirement that local interests contribute 
10 cents per cubic yard toward deepening 
tidal canal. 
Maintenance of 35-foot depth in channel to outer 
harbor and in outer harbor channel and turning 
basin. 
Deepen inner harbor 35-foot channels and lower 
1,300 feet of north channel in Brooklyn Basin 
to 35 feet. 
Deepen Inner and Outer Harbor channels to 42 
feet. Widen entrance channel to 1,000 feet; 
relocate Outer Harbor turning basin 3,000 feet 
westward and widen turning basin to 1800 feet. 
Construct 1,200 foot turning basin in Inner 
Harbor. 
RICHMOND HARBOR, CA 
Channel 24 feet deep and 600 feet wide from San 
Francisco Bay to Ellis Slough (Santa Fe Channel); 
a turning basin at Point Potrero; a training wall. 
A 30-foot channel with lessened widths; a turning 
basin at head of navigation. 
Increase project widths in inner harbor, maintenance 
of Santa Fe channel to 30 feet; approach areas 
in outer harbor to 32 feet. 
Annual Report, Part II, 
1874, p. 378. 
H. Doc. 647, 61st 
Cong., 2d sess. 
H. Doc. 144, 67th 
Cong., 2d sess. 
H. Doc. 407, 69th 
Cong., 1st sess. 1 
Public Res. 28, 
70th Cong. 
Rivers and Habors 
Committee Doc. 43, 
71st Cong., 2d sess. 
H. Doc. 466, 77d 
Cong., 1st sess. 
Report on File in Office, 
Chief of Engineers 
H. Doc. 353, 87th 
Cong., 2d sess. 1 
1986 WRDA, Public 
Law 99-662 
H. Doc. 515, 63rd 
Cong., 2d sess. 
Rivers and Harbors 
Committee Doc. 16, 
70th Cong., 1st sess. 
Rivers and Harbors 
Committee Doc. 7, 
73d Cong., 1st sess., 
and 10, 74th Cong., 
1st sess. 
34-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 34-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
June 20, 1938 Widen channel at Point Potrero and north thereof; H. Doc 598, 75th Cong., 
enlarge and maintain to 30-foot depth turning 3d sess. 
basin at Terminal No. 1. 
Mar. 2, 1945 Channel 20 feet deep, 150 feet wide, in San Pablo H. Doc. 715, 76th 
Bay north of Point San Pablo. Cong., 3d sess. 
Sep. 3, 1954 Channel 35 feet deep and 600 feet wide adjacent H. Doc. 395, 83rd 
to Southampton Shoal; enlarge and deepen to 35 Cong., 2d sess. 1 
feet approach area to Richmond Long Wharf; 
widen and deepen inner harbor and entrance 
channels; deepen turning basin at Point Richmond 
and southerly 2,000 feet of Santa Fe Channel. 
Eliminate restriction that widening north of 
Point Potrero will not be undertaken until local 
interests furnish assurances industries will avail 
themselves of improved navigation facilities. 
and reclamation of Reservation Point. 
Oct. 27, 1965 West Richmond channel 45 feet deep, 600 feet H. Doc. 208, 89th 
wide; enlarge and deepen to 45 feet maneuvering Cong., 1st sess. 1 
area at Richmond Long Wharf (Sacramento Dist. 
"San Francisco Bay to Stockton, Calif. (John 
F. Baldwin and Stockon Ship Channels)"). 
Nov. 17, 1986 Deepen channel to 38 feet between Richmond 1986 WRDA, Public 
Long Wharf and Santa Fe Channel. Construct Law 99-662 
1,200 feet turning basin. 
1. Contains latest published map. 
2. Included deepening of tidal canal above Park 
Street Bridge to 25 feet, which was deauthorized 
November 6, 1977. 
3. Reconstruction of Fruitvale Avenue Highway 
Bridge (S. Doc. 75, 87th Cong., 2d sess.) which was 
deauthorized November 6, 1977. 
4. Included in part in Public Works Administration 
Program, September 6, 1933. 
34-12

SAN FRANCISCO, CA, DISTRICT 
TABLE 34-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Berkeley Harbor, CA 1 Completed 1966 $155,550 2 $6,120 9 
Berkeley Marina, CA 1 Completed 1979 505,201 3 - 
Monterey Harbor, CA Completed 1971 1,108,182 4 126,551 6 
San Francisco Harbor (Islais 
Creek), CA 1 Completed 1976 848,227 7 
San Francisco Marina (Gas 
House Cove), CA Completed 1974 180,472 6 5,114 10 
San Leandro Marina (Breakwater), 
CA 1 Completed 1976 210,390 8a 
Saucelito Canal, Richardson Bay, CA Inactive 1963 103,095 70,165 
1. Authorized by Chief of Engineers (Sec. 107, condition survey for FY 1956-1992. 
Public Law 86-645). 6. Includes preauthorization costs $26,855 and 
2. Excludes $155,551 contributed funds. excludes contributed funds $153,618. 
3. Excludes $378,989 contributed funds. 7. Includes $94,550 preauthorization costs. 
4. Includes $207,800 Public Works Administra- 8. Includes $72,000 preauthorization costs and 
tion funds and breakwater modifications (1960 Act) excludes contributed funds $138,189. 
placed inactive 1974. The barrier groin and sandtrap 9. Includes $6,120 for jetty condition surveys for 
feature of the project was deauthorized November 17, FY 1987-1992. 
1986, by WRDA of 1986. 10. Includes $5,114 reconnaissance and condition 
5. Includes $40,317 for reconnaissance and survey for FY 1990-1992. 
TABLE 34-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Humboldt Bay (Buhne Point), CA 1958 Jan. 1, 1990 $ 2,000 - 
Lower San Francisco Bay, CA 1935 Jan. 1, 1990 - - 
Knights Valley Lake, R.R. 
Basin, CA 1974 Aug. 5, 1977 - 
Oakland Harbor, CA (Deepen 
Tidal Canal) 1981 Nov. 6, 1977 - 
Oakland Harbor, CA (Fruitvale 
Avenue Bridge) 1981 Nov. 6, 1977 - 
San Lorenzo Creek, CA 
(Upper Portion) 1962 Nov. 6, 1977 - 
San Pablo Bay and Mare 
Island Strait, CA (Approaches 
to Vallejo and South Vallejo) 1982 Nov. 6, 1977 - - 
Santa Cruz County, CA 1966 Jan. 1, 1990 245,639 - 
34-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 34-H INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
(See Section 9 of Text) 
Location Dates of Inspection 
Corte Madera Creek 
Coyote Creek 
East Weaver Creek 
Eel River at Sandy Prairie 
Klamath River 
Mad River 
Mad River at Blue Lake 
Pajaro River 
Pinole Creek 
Redwood Creek 
Rheem Creek 
Rodeo Creek 
Russian River 
Wildcat Creek 
34-14 
May 1992 
June 1992 
May 1992 
May 1992 
May 1992 
May 1992 
May 1992 
June 1992 
June 1992 
May 1992 
June 1992 
June 1992 
June 1992 
June 1992

SACRAMENTO, CA, DISTRICT* 
This district comprises basins of Suisun Bay and 
San Joaquin and Sacramento Rivers in California; 
Goose Lake in Oregon; basins of the Great Salt Lake 
and Sevier Lake in Utah; an intervening portion of 
Great Basin in northern Nevada, northern California, 
and southeastern Idaho; and the upper Colorado 
River basin, which is in southwestern Wyoming, 
eastern Utah, northeastern Arizona, and western 
Colorado, west of the Continental Divide. 
IMPROVEMENTS 
Navigation Page 
1. Sacramento River, CA ............... 35-2 
2. Sacramento River Deep Water 
Ship Channel, CA ................... 35-3 
3. San Francisco Bay to Stockton, CA 
(John F. Baldwin and Stockton 
Ship Channels) .................... 35-3 
4. San Joaquin River, CA ................ 35-4 
Flood Control 
5. Buchanan Dam-H.V. Eastman Lake, 
Chowchilla River, CA ................ 35-5 
6. Cache Creek Settling Basin, CA ........ 35-6 
7. Calaveras River and Littlejohn Creek and 
tributaries, including New Hogan Lake and 
Farmington Dam, CA ................ 35-6 
8. Corte Madera Creek, CA ............. 35-7 
9. Fairfield Vicinity Streams, CA .......... 35-8 
10. Guadalupe River, CA ................ 35-9 
11. Hidden Dam-Hensley Lake, Fresno 
River, CA ......................... 35-10 
12. Isabella Lake, Kern River, CA ........ 35-10 
13. Kaweah and Tule Rivers, including 
Terminus Dam and Success Lake, CA... 35-11 
14. Little Dell Lake, UT. ................ 35-13 
15. Lower San Joaquin River, CA ......... 35-13 
16. Martis Creek Lake, Martis Creek, 
NV and CA ....................... 35-14 
17. Merced County Streams ............. 35-14 
18. Merced County Stream Group, CA ..... 35-15 
19. Pajaro River, CA ................... 35-15 
20. Pine Flat Lake and Kings River, CA ..... 35-16 
21. Redbank and Fancher Creeks, CA ..... 35-17 
22. Russian River Basin, including Dry Creek 
(Warm Springs Lake) and Lake 
Mendocino (Coyote Valley Dam), CA .. 35-18 
23. Sacramento River and tributaries, CA 
from Collinsville to Shasta Dam ........ 35-19 
24. Walnut Creek, CA ................. 35-21 
25. Wildcat and San Pablo Creeks, CA ..... 35-22 
26. Inspection of Completed Flood 
Control Projects ................... 35-22 
Flood Control (Cont'd) Page 
27. Flood Control Work under Special 
Authorization ..................... 35-23 
28. Scheduling Flood Control 
Reservoir Operations ............... 35-23 
Multiple-Purpose Projects Including Power 
29. New Melones Lake, CA.............. 35-23 
General Investigations 
30. Surveys.. ........................ 35-25 
31. Collection and Study of Basic Data ..... 35-25 
32. Research and Development .......... 35-25 
33. Preconstruction Engineering and Design. 35-25 
34. Other Work under Special Authority... 35-26 
Tables 
Table 35-A 
Page 
Cost and Financial 
Statement ............... 35-27 
Table 35-B Authorizing 
Legislation .............. 35-35 
Table 35-C Other Authorized 
Navigation Projects ....... 35-37 
Table 35-D Not Applicable 
Table 35-E Other Authorized Flood 
Control Projects .......... 35-38 
Table 35-F Not Applicable 
Table 35-G Deauthorized Projects ..... 35-40 
Table 35-H Sacramento River, CA: 
Tidal and Flood Conditions 
Prevailing ............... 35-40 
Table 35-I San Joaquin River, CA: 
Total Cost of New Work 
for Project .............. 35-41 
Table 35-J San Joaquin River, CA: 
Project Units (1950 Modification) 
Reclassified and Excluded from 
Project Cost ............. 35-41 
Table 35-K Merced County Stream Group, 
CA, Maximum Inflow, Storage, 
and Outflow for Projects ... .35-42 
Table 35-L Russian River Basin, CA: Estimated 
Cost for New Work ....... 35-42 
35-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
IMPROVEMENTS (Cont'd) 
Tables Page Tables 
Table 35-M Russian River Basin, CA: 
Project Features and 
Estimated Costs .......... 35-43 
Table 35-N Sacramento River and 
Tributaries, CA, Collinsville 
to Shasta Dam: Project Units 
Units Reclassified and Excluded 
from Cost Estimate ....... 35-43 
Table 35-0 Sacramento River and 
Tributaries, CA, from Collinsville 
Navigation 
1. SACRAMENTO RIVER, CA 
Location. Rises in Trinity Mountains in 
north-central California, flows generally southerly 
about 374 miles and empties into Suisun Bay, an arm 
of San Francisco Bay, at Collinsville, CA. (See 
Geological Survey topographic map of Sacramento 
Valley, CA.) 
Previous projects. For details see page 1985 of 
Annual Report for 1915 and page 1708 of Annual 
Report for 1938. 
Existing project. For description of Sacramento 
Deep Water Ship Channel, see Annual Report for 
1969. Total first cost for completed portion was 
$43,932,558 ($39,560,558 Federal (Corps), 
$300,000 (Coast Guard), and $4,072,000 non-Federal 
for lands and damages, including relocations) 
and excludes local interests cost $10,741,000 (June 
1963) for 30-foot deep water ship channel and 
13-foot deep connecting canal basic terminal 
facilities required under terms of project authorization. 
Project also provided for a shallow-draft 
channel 10 feet deep at mean lower low water 150 to 
200 feet bottom width, from Suisun Bay to 
Sacramento, CA, 60 miles; a depth of 6 feet at low 
water between Sacramento and Colusa, 85 miles; a 
depth of 5 feet at low water between Colusa and 
Chico Landing, 50 miles; and such depths as 
practicable between Chico Landing and Red Bluff, 
53 miles, a total distance of 248 miles. However, 
shallow-draft channel feature Colusa to Red Bluff 
(including Colusa to Chico Landing, 50 miles and 
Chico Landing to Red Bluff, 53 miles) was 
deauthorized by 1986 Water Resources Development 
Act on November 17, 1986 (Public Law 99-662). 
(See table 35-H on tidal and flood conditions 
prevailing.) 
Table 35-P 
Page 
to Shasta Dam: Construction 
Accomplished and Contract 
Costs .................. 35-44 
Flood Control Work Under 
Special Authorization Flood 
Control Activities Pursuant 
to Section 205, Public Law 
80-858, as Amended 
(Preauthorization) ........ 35-44 
Table 35-Q Surveys ................ 35-45 
Local cooperation. Fully complied with for deep 
water ship channel project. None required on 
shallow-draft feature. 
Terminal facilities. Piers, wharves, and docks at 
Port of Sacramento for shallow-draft navigation are 
open-pile structures with timber decks, some of 
which are designed to meet extreme high waters of 
flood stages. All main wharves at Sacramento have 
rail connections. Three of above facilities are owned 
by city of Sacramento and remainder by private 
interests; all are privately operated. For full 
description see "Port and Terminal Facilities at the 
Ports of Sacramento, Stockton, Pittsburg and 
Antioch, Calif., 1986." Deep water terminal facilities 
comprise wharves and piers, administration and 
storage buildings, and belt railroad facilities. Majority 
of these facilities are owned and operated by 
Sacramento-Yolo Port District; remainder are 
privately owned and operated. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. New work, Deep 
Water Ship Channel: None. Maintenance: Shallow 
Draft Channel: Maintenance and operation activities 
continued in Sacramento River, Sacramento upstream 
to Colusa. Deep Water Ship Channel: 
Maintenance and operation activities continued. 
Stone protection on levees was initiated at contract 
cost of $150,000. 
Historical summary. Construction of 7-foot 
shallow-draft channel below Sacramento was initiated 
in September 1899 and completed in 1904. 
Modified 10-foot shallow-draft channel up to 
Sacramento was initiated in FY 1928 and completed 
in 1931. Shallow-draft channel above Sacramento 
was begun in April 1946 but new work was 
discontinued when about 48 percent complete. In 
February 1974, remaining work for shallow-draft 
portion of project, provision of a 5-foot depth 
between Colusa and Chico Landing (50 miles), was 
reclassified as "deferred." Channel is navigable all 
year; however, there is no regular navigation above 
35-2

SACRAMENTO, CA, DISTRICT 
Colusa, 145 miles above river mouth. On November 
17, 1986, remaining shallow-draft feature, Colusa to 
Red Bluff (including Colusa to Chico Landing, 50 
miles and Chico Landing to Red Bluff, 53 miles) was 
deauthorized by 1986 Water Resources Development 
Act (Public Law 99-662). Construction of 30-foot 
deep water ship channel was initiated in July 1949; 
improvement dredging by continuing contracts 
resulted in provision of an operational facility for 
oceangoing vessels during June 1963. Bascule bridge 
was completed in April 1960, barge lock in August 
1961, barge canal in November 1961, and entire 
deep water ship channel in June 1970. 
2. SACRAMENTO RIVER DEEP WATER 
SHIP CHANNEL, CA 
Location. On the Sacramento River between 
Collinsville and the Port of Sacramento, a distance of 
about 43 miles, in the counties of Sacramento, 
Contra Costa, Solano, and Yolo, CA. 
Existing project. Project provides for deepening 
to 35 feet the Suisun Bay and Sacramento River Deep 
Water Ship Channels from New York Slough to the 
Port of Sacramento, and the Avon to New York 
Slough reach to 35 feet which will be accomplished 
under the San Francisco Bay to Stockton (John F. 
Baldwin and Stockton Ship Channels) project, and 
widening the channel as necessary. 
Current selected plan also provides for a water 
quality monitoring program, and establishment of 
wetland habitat and upland habitat to mitigate for 
losses of such habitat. 
Project estimate (October 1992) is $45,700,000 
(includes an allowance for estimated inflation 
through the construction period) comprising Federal 
cost (Corps) of $22,700,000; Federal cost (Coast 
Guard) for navigation aids $300,000; and non-Federal 
cost of $22,700,000 for lands and damages, 
relocations, and spoil retention dikes, including the 
cash contribution ($7,740,000) that local interests 
must pay. Existing project was adopted by 
Supplemental Appropriations Act of 1985, August 
15, 1985 (Public Law 99-88), 99th Cong., 1st sess. 
and modified by 1986 Water Resources Development 
Act, November 17, 1986 (Public Law 99-662) 
99th Cong., 2d sess. 
Local cooperation. Local interests, through a 
public body legally authorized and financially 
capable, must give assurances they will furnish lands, 
easements, rights-of-way, and dredged material 
disposal areas; modify or relocate buildings, utilities, 
roads, and other facilities where necessary in the 
construction of the project; and provide retention 
dikes for dredged material disposal area; and pay 25 
percent of the costs allocated to deep draft navigation 
during construction, presently estimated at 
$7,740,000. Local interests have agreed to make all 
required payments concurrently with project 
construction. A Local Cooperation Agreement 
(LCA) (sec. 221) was executed June 27, 1986. An 
LCA modification necessitated by the Water 
Resources Development Act of 1986 was executed 
December 6, 1988. 
Terminal facilities. All main wharves at 
Sacramento have rail connections. Three of above 
facilities are owned by city of Sacramento and 
remainder by private interests; all are privately 
operated. For full description see "Port and Terminal 
Facilities at the Ports of Sacramento, Stockton, 
Pittsburg and Antioch, Calif., 1986." Deep water 
terminal facilities comprise wharves and piers, 
administration and storage buildings, and belt 
railroad facilities. Majority of these facilities are 
owned and operated by Sacramento-Yolo Port 
District; remainder are privately owned and 
operated. Facilities are considered adequate for 
existing commerce. 
Operations and results during fiscal year. 
Engineering was continued. 
Historical summary. General Design Memorandum 
was approved and Record of Decision was 
signed in May 1987. Local Cooperation Agreement 
(LCA) modification was approved and was signed by 
Port of Sacramento on August 19, 1987. LCA 
modification was executed December 6, 1988. First 
construction contract was awarded February 2, 1989 
and completed in July 1990; second contract was 
awarded September 12, 1990 and completed in 
August 1991. 
3. SAN FRANCISCO BAY TO STOCKTON, 
CA, (JOHN F. BALDWIN AND 
STOCKTON SHIP CHANNELS) 
Location. On navigation channels extending from 
entrance to San Francisco Bay to Port of Stockton 
through San Francisco, Marin, Contra Costa, 
Solano, Sacramento, and San Joaquin Counties. 
(See Coast and Geodetic Charts 5527 and 
5532-5534 for respective areas.) 
Existing project. Project provides for modification 
of existing San Francisco Harbor, Richmond 
Harbor, San Pablo Bay and Mare Island Strait, 
Suisun Bay Channel, and San Joaquin River 
navigation projects to provide depths of 55 feet for 
San Francisco Bar Channel, 45 feet for main internal 
bay channels upstream to vicinity of Avon, and 35 
feet from Avon to Stockton; enlargement and 
deepening to 45 feet of maneuvering areas adjacent 
to major petroleum refinery terminals along channel 
route; widening Suisun Bay Channel; reclaiming 
shoreline marshes and inundated or low-lying areas 
by spoil deposit for public recreation and for 
industrial use; providing basic recreation facilities on 
some of the reclaimed areas for public use; and 
placing additional rock revetment on waterside of 
levees bordering channels. 
35-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Project estimate (October 1992) is $174,100,000 
(includes an allowance for estimated inflation 
through the construction period) comprising Federal 
cost (Corps) of $145,200,000, including basic 
recreation facilities; Federal cost (Coast Guard) for 
navigation aids $1,100,000; and non-Federal cost of 
$27,800,000 for lands and damages, relocations, 
berthing areas, and spoil retention dikes, including 
the cash contribution ($20,000) that local interests 
must make for land enhancement at time of 
construction. Local interests must also pay, 
contribute in kind, or repay with interest one-half of 
separable cost of project allocated to recreation. 
Existing project was adopted by 1965 River and 
Harbor Act (H. Doc. 208, 89th Cong., 1st sess., 
contains latest published map). 
Local cooperation. Local interests, through a 
public body legally authorized and financially 
capable, must give assurances they will furnish lands, 
easements, and rights-of-way for construction and 
future maintenance of the project and for aids to 
navigation, including spoil-disposal areas designated 
by the Chief of Engineers; provide necessary spoil 
retention dikes, bulkheads, and embankments 
except as applicable to spoil-disposal areas designated 
as public recreation areas; make utility 
modifications and relocations required for construction, 
including new bridges or bridge alterations 
(except for railroad bridges), and absorb any 
increased annual maintenance and operation costs 
resulting there from; provide and maintain all 
necessary berthing areas, at a depth commensurate 
with project depth, at all terminals and wharves to be 
served by the deepened channels; and in recognition 
of the local land enhancement benefits to result from 
landfill during dredging, contribute to the United 
States 4 cents per cubic yard of all spoil material 
placed during initial construction for modification of 
Suisun Bay Channel project on areas not developed 
for public use. Local interests must also give 
satisfactory assurances, before starting construction 
of the affected units, that they will maintain and 
operate the Federally provided recreation areas and 
facilities, continue to maintain to adequate standards 
the levees altered, set back or provided revetment 
protection, and hold the U.S. Government free from 
damages due to deposition of spoil and construction 
of new levees or reconstruction of existing levees. 
Local interests, represented by Board of Supervisors 
of Contra Costa County and Stockton Port District, 
must, at time of construction, contribute $20,000 in 
cash for land enhancement; pay, contribute in kind, 
or repay with interest one-half of separable cost of 
project allocated to recreation; and maintain and 
operate basic recreation facilities after construction 
and install additional basic facilities required as 
demands on area expand. No work shall be 
undertaken on a modification of Suisun Bay Channel 
project unit to deepen the channel to more than 35 
feet between Avon and a proposed refinery or 
manufacturing plant, until local interests furnish 
formal assurances and definite plans for such 
installation within the Avon-Chipps Island reach of 
channel. Also, no work shall be undertaken on 
modification of San Joaquin River navigation project 
unit, regarding access channels in vicinity of Antioch, 
until local interests furnish formal assurances and 
definite plans for Port of Antioch. Formal assurances 
for deepening and otherwise improving the Stockton 
Deep Water Ship Channel from Pittsburg to Stockton 
were furnished by Stockton Port District April 9, 
1970. The Stockton Port District, in August 1980, 
formally provided their intent to sponsor the Avon to 
Pittsburg reach (Suisun Bay Channel) and recreational 
development on Roberts Island. The Port of 
Stockton, by letter of October 20, 1981, stated that 
they would furnish the necessary assurances for fish 
and wildlife mitigation and enhancement, and on 
April 13, 1982, provided formal updated assurances 
for the Avon to Stockton portion. A sec. 221 
agreement satisfying all requirements of local 
cooperation for Southampton Shoal and Richmond 
Long Wharf maneuvering area was obtained from 
Contra Costa County Board of Supervisors and 
signed by District Engineer July 31, 1984. On May 3, 
1988, Board passed a resolution of continued 
support for construction in West Richmond, Pinole 
Shoal, Carquinez Strait, and Suisun Bay Channels. 
A Memorandum of Agreement between the 
Department of the Army, San Francisco District and 
Contra Costa County to sample berthing areas of 
project was executed September 12, 1989. 
Terminal facilities. See Port Series No. 30, 
revised 1991, and 31, revised 1982, titled respectively: 
"The Ports of San Francisco, Redwood City, 
and Humboldt Bay, Calif." and "The Ports of 
Oakland, Alameda, Richmond, and Ports on 
Carquinez Strait, Calif."; and Port Series No. 32, 
revised 1986,"The Ports of Sacramento, Stockton, 
Pittsburg and Antioch, Calif." Facilities are considered 
adequate for existing commerce and will be 
adequate for future commerce upon completion of 
new terminal facilities. 
Operations and results during fiscal year. New 
work: Sacramento District: Engineering continued. 
A dissolved oxygen mitigation contract was continued 
at fiscal year cost of $324,498 and contract for 
modification of Simmons Island, Area C, was 
initiated at fiscal year cost of $899,850. San 
Francisco District: planning activities continued 
including initiation of hydrologic studies at the San 
Francisco Bay Hydrologic model in Sausalito; 
continuation of a vessel simulation navigation study; 
and continuation of sediment quality testing for 
ocean, upland and wetland disposal. 
Historical summary. Construction of project was 
initiated in June 1971 and is about 37 percent 
complete. 
4. SAN JOAQUIN RIVER, CA 
Location. Rises in east central California and 
flows westerly and northwesterly about 340 miles to 
35-4

SACRAMENTO, CA, DISTRICT 
its confluence with Sacramento River at head of 
Suisun Bay, 48 miles northeast of San Francisco. 
Deep water channel in San Joaquin River extends 41 
miles from its mouth in Suisun Bay at Pittsburg to city 
of Stockton. Waterborne access to city provided by 
Stockton Channel, an artificial cut extending from 
river about 2 miles into city. (See Coast and Geodetic 
Survey Sheet 5527.) 
Existing project. For description of completed 
improvement, modifications, and authorizing acts, 
see Annual Report for 1967. (See table 35-I for total 
cost of new work for project completed in May 
1960.) 
Projects units (1950 modification) reclassifed and 
excluded from project cost are set forth in table 35-J. 
Modification of existing project is included as one 
unit of San Francisco Bay to Stockton, CA, (John F. 
Baldwin and Stockton Ship Channels) project, 
authorized by 1965 River and Harbor Act (H. Doc. 
209, 89th Cong., 1st sess.); this modification is 
reported in detail under Sacramento District, 
Improvement No. 3. 
Local cooperation. Fully complied with for 
completed portion of project; for details of required 
cash contributions on completed, inactive and 
deferred portions of project, see Existing project 
paragraph, Annual Report for 1967. 
Terminal facilities. For description of harbor 
facilities at Port of Stockton, CA, see Port Series 32, 
"The Ports of Sacramento, Stockton, Pittsburg and 
Antioch, Calif.," revised 1986. Downstream from 
Stockton, traffic is accommodated by bank landings 
and sheds except at Antioch and near Pittsburg, 
where there are wharves for shallow- and deep-draft 
vessels. Terminal transfer facilities at public ocean 
terminal of Port of Stockton are adequate for present 
and immediate future. 
Operations and results during fiscal year. 
Maintenance: Condition studies and miscellaneous 
inspections and reports were accomplished by hired 
labor. Stone protection maintenance on Stockton 
Deep Water Ship Channel was initiated and 
completed at contract cost of $310,724; and 
dredging was initiated and completed at contract cost 
of $569,999. (Repair or restoration of wavewash 
protection is required by legislation authorized by 
Improvement No. 3.) 
Historical Summary. Active portion of existing 
project was completed in May 1960. Construction of 
project was initiated in December 1877. 
Flood Control 
5. BUCHANAN DAM-H.V. EASTMAN 
LAKE, CHOWCHILLA RIVER, CA 
Location. On Chowchilla River about 36 miles 
above its mouth and about 16 miles northeast of city 
of Chowchilla, CA. (See Geological Survey quadrangles 
for area.) 
Existing project. Provides for construction of a 
205-foot high rockfill dam to create a reservoir with 
gross storage capacity of 150,000 acre-feet for flood 
control, irrigation, recreation, and fish and wildlife. 
In conjunction with dam, project plan provides for 
about 12 miles of downstream levee and channel 
construction on Ash Slough to accommodate a 
project design flow of 5,000 cubic feet per second 
within slough and 7 miles of levee and channel 
improvement on Berenda Slough. Operation and 
maintenance of dam and reservoir is the responsibility 
of the Federal Government. Total first cost for 
existing project is $28,919,597, of which 
$27,369,597 is Federal cost, including $4,580,000 
for basic recreation facilities, and $1,550,000 
non-Federal costs for lands and damages, including 
relocations for downstream levee and channel 
improvements. Local interests have contracted with 
the Bureau of Reclamation for irrigation service. For 
future non-Federal reimbursement, see Local 
cooperation paragraph. 
Local interests have also, over a period of years, 
expended about $500,000 for construction of low 
levees and clearing downstream channels to provide 
some local flood protection in project area. This 
work is inadequate during major floods. Existing 
project was adopted by 1962 Flood Control Act (S. 
Doc. 98, 87th Cong., 2d sess., contains latest 
published map). Lake formed by Buchanan Dam on 
Chowchilla River was designated "H.V. Eastman 
Lake" by Public Law 93-217. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and 
operation activities were continued. When hydrilla 
was discovered in Madera and Mariposa counties at 
Eastman Lake and in Chowchilla River in June 1989, 
Eastman Lake was quarantined. In August 1992, the 
western shore of the Lake was opened to limited 
fishing and swimming. Runoff of Chowchilla River 
above Buchanan Dam was below normal for the year. 
Maximum storage of 28,218 acre-feet occurred 
May 7, 1992. Maximum bihourly inflow to reservoir 
was 2,626 cubic feet per second on February 15, 
1992. Maximum release of 408 cubic feet per second 
on July 23, 1992, was below maximum permissible 
flood release. During the year, a total of 17,752 
acre-feet of water was released for irrigation and 
other purposes. 
Historical summary. Construction began in July 
1971 and was completed in May 1979. Construction 
of Buchanan and Hidden dam and appurtenances 
was combined under one contract. Project was 
completed in September 1983, except for installation 
of piezometers (now deferred indefinitely). Dam 
35-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
closure was in March 1975; dam was completed in 
January 1976. Reservoir clearing and boundary 
marking were completed May 1975. Bifurcation 
structure was completed in February 1976. Channel 
improvement, Ash and Berenda Sloughs, was 
completed in March 1976. Recreation areas: Phase I 
was completed in January 1976; Phase II was 
completed in February 1978. Residences, administration 
building, and visitors center contract was 
completed in May 1978. Landscaping was completed 
in May 1979 and erosion control was completed in 
April 1979. A resources interpretive display and road 
relocation were completed in FY 1982. Dam safety 
assurance studies were initiated in FY 1981. Solar 
heating was installed at Chowchilla recreation area in 
FY 1984. An hydrilla eradication (spraying) program 
was initiated in FY 1989. Final land audit was 
approved on December 3, 1985. 
6. CACHE CREEK BASIN, CA (CACHE 
CREEK SETTLING BASIN) 
Location. At the mouth of Cache Creek in Yolo 
County where it enters the Yolo Bypass about 2 miles 
east of city of Woodland and about 15 miles 
northwest of city of Sacramento, CA. 
Existing project. Provides for raising the 
perimeter levees of the existing settling basin an 
average of 12 feet, extending the levees upstream to 
County Road 102 to provide 50-year sediment 
storage capacity, enlarging and reconstructing the 
cobble weir, and degrading existing training levees 
and rebuilding them adjacent to western perimeter 
levee to provide 50 years of sediment storage capacity 
(340 acre-feet annually.). Estimated cost (October 
1992) for existing project is $20,130,000 (includes 
an allowance for estimated inflation through the 
construction period), of which $11,710,000 is 
Federal and $8,420,000 is non-Federal (which 
includes $1,010,000 cash contribution). For future 
non-Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted by Water 
Resources Development Act of 1986, Public Law 
99-662, November 17, 1986 (HD 98-134, 98th 
Cong., 1st sess., contains published map.) Project as 
authorized included development of a national 
wildlife refuge within the settling basin; however, the 
Department of the Army determined that such refuge 
would be more appropriately funded and developed 
by the U.S. Fish and Wildlife Service. Refuge 
feature was reclassified to deferred category on 
April 11, 1988. 
Local cooperation. Local interests are required 
to provide lands, easements, rights-of-way, and 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, bridges (except railroad 
bridges) and other facilities where necessary in 
construction of the project; pay 5 percent of cost 
allocated to flood control to bring total non-Federal 
share of flood control costs to 25 percent of which 
$1,010,000 is cash contribution, and bear all costs of 
operation, maintenance and replacement of flood 
control facilities. Local interests have agreed to 
make all required payments concurrently with 
project construction. Local Cooperation Agreement 
was executed March 12, 1990. 
Operations and results during fiscal year. 
Engineering activities were continued. Cache Creek 
Settling Basin enlargement (multicomponent) contract 
was initiated at a contract cost of $7,924,339. 
Historical summary. Local Cooperation Agreement 
was executed March 12, 1990. Cache Creek 
Settling Basin enlargement (multicomponent) construction 
contract was awarded August 5, 1991. 
7. CALAVERAS RIVER AND 
LITILEJOHN CREEK AND 
TRIBUTARIES, INCLUDING 
NEW HOGAN LAKE AND 
FARMINGTON DAM, CA 
Location. Streams comprising Calaveras River 
and Littlejohn Creek groups rise in Sierra Nevada 
and its foothills, flow easterly across flatlands of San 
Joaquin Valley and empty into San Joaquin River 
directly, or through various sloughs, in vicinity of 
Stockton, CA. Littlejohn Creek is in Calaveras, 
Stanislaus, and San Joaquin Counties. The three 
principal stream systems of the group are, from south 
to north, Lone Tree Creek, Littlejohn Creek, and 
Duck Creek. Calaveras River group is in Calaveras 
and San Joaquin Counties. The two principal streams 
of the groups are, from south to north, Calaveras 
River and Bear Creek. (See Geological Survey Valley 
Springs quadrangle for New Hogan reservoir area 
and Trigo and Bachelor Valley quadrangles for 
Farmington reservoir area.) 
Existing project. For description of completed 
improvements consisting of Farmington Dam, New 
Hogan Lake, and Bear Creek levee and channel 
improvement, and authorizing act, see Annual 
Report for 1967. (a) Farmington: Total first cost 
(July 1955) for project was $3,995,684, of which 
$3,676,384 was Federal and $319,300 non-Federal 
for lands and damages including relocations. (b) New 
Hogan: Federal cost for project is $15,906,150, 
including $543,514 for basic recreation facilities. For 
future non-Federal reimbursement, see Local 
cooperation paragraph. Federal cost for recreation 
facilities funded from Code 710 appropriations is 
$897,742. (c) Bear Creek: Project cost is 
$6,485,734, of which $3,242,867 is Federal, 
including reimbursement ($488,096) to local interests 
of one-half of excess local interest cost of lands, 
rights-of-way, and relocations over estimated 
Federal construction cost in accordance with section 
3, Public Law 738, 74th Congress. Non-Federal cost 
included in above amount is $3,242,867 for 
relocations and lands and damages, exclusive of 
above Federal reimbursement. 
35-6

SACRAMENTO, CA, DISTRICT 
Local cooperation. Fully complied with. New 
Hogan: Local interests must pay portion of first cost 
and annual operation and maintenance costs 
allocated to conservation functions of project. These 
costs are estimated at 36.2 percent of first cost and 38 
percent of annual costs. In addition, local interests 
contributed land, the (July 1964) market value of 
which was $556,000. For years 1961 through 1970, 
an interim contract between the Bureau of 
Reclamation and local water users provided for 
storage and payment of irrigation water; a long-term 
contract between that agency and local water users 
was executed August 25, 1970. Local interests paid 
$3,703,575 through December 31, 1991. A 
concessionaire at New Hogan Marina provided 
public use facilities in accordance with lease 
agreement with the Secretary of the Army at an 
estimated cost to date of $234,000. 
Operations and results during fiscal year. New 
work: New Hogan Lake, regular funds: None. Code 
710 funds: None. Bear Creek, San Joaquin County: 
None. Maintenance: Farmington Dam-Maintenance 
and operation activities continued; structures 
were maintained in serviceable condition. During 
rainflood season, maximum flow of Duck Creek 
Diversion was 1,546 cubic feet per second on 
February 15, 1992. Maximum flow of Littlejohn 
Creek at Farmington was 1,910 cubic feet per second 
on February 15, 1992. Maximum storage in 
reservoir was 11,078 acre-feet on February 15, 
1992, and maximum estimated inflow to reservoir 
was 9,515 cubic feet per second on February 15, 
1992. Maximum release of 1,384 cubic feet per 
second on February 17, 1992, was below maximum 
permissible flood release. During the year, 24,622 
acre-feet was released for flood control and 1,562 
acre-feet released for irrigation and other purposes. 
Project prevented an estimated $715,000 in damages 
from the February 1992 rainflood. New Hogan 
Lake-Maintenance and operation activities continued. 
Dam safety assurance studies were continued at 
a fiscal year cost of $144,380. Structures were 
maintained in serviceable condition. Runoff of 
Calaveras River above New Hogan was below normal 
for the year. Maximum storage of 72,814 acre-feet 
occurred April 26, 1992. Maximum hourly inflow to 
reservoir was 10,581 cubic feet per second on 
February 15, 1992. Maximum release of 322 cubic 
feet per second on August 8, 1992, was below 
maximum permissible flood release. During the year, 
52,900 acre-feet was released for irrigation and 
other purposes. 
Historical summary. Farmington Dam: Construction 
of Farmington project was initiated in July 
1949 and completed for beneficial flood control 
operation in 1952. Duck Creek channel improvement 
was completed in November 1951; and channel 
improvement on south Littlejohn Creek was 
completed in May 1955. There are no recreation 
facilities or public-use areas. All work completed. 
Dam safety assurance studies were initiated in FY 
1982. New Hogan Lake: Construction was initiated 
May 1960, main dam closure November 1963, 
project completed for operational use in June 1964, 
and all work completed October 1973. Recreation 
facilities have been provided from Code 710 
appropriations. Seepage measurement weir 
constructed in June 1980. Dam safety assurance 
studies were initiated in FY 1980. Bear Creek, San 
Joaquin County: Construction began in June 1963 
and was completed in June 1967. Final cash 
contribution was made to local interests December 
23, 1970. Solar heating was installed at recreation 
facilities in FY 1984. A cultural resources survey was 
completed in FY 1984. 
8. CORTE MADERA CREEK, CA 
Location. Creek and tributaries drain an area of 
28 square miles in Marin County, CA, and flow into 
west side of San Francisco Bay about 9 miles north of 
Golden Gate. (See Geological Survey quadrangle 
San Rafael.) 
Existing project. Provided for about 11 miles of 
channel improvements, including realignment, enlargement, 
levees, riprapping, rectangular concrete 
sections, interior drainage facilities, bridge relocations, 
and debris removal on Corte Madera Creek 
and lower reaches of its tributaries, and a continuous 
channel rights-of-way to deep water in San 
Francisco Bay reserved to assure channel outlet in 
the event of future tideland reclamation. Water 
Resources Development Act of 1986 modified 
existing project to direct construction of Unit 4 from 
Lagunitas Road Bridge to Sir Francis Drake 
Boulevard, and to include construction of 
floodproofing measures as necessary to individual 
properties and other necessary structural measures in 
vicinity of Lagunitas Road Bridge to insure proper 
functioning of completed portions of authorized 
project. Portion of project upstream of Sir Francis 
Drake Boulevard previously classified inactive was 
modified on November 17, 1986 to eliminate any 
channel modification. Current project has 3 miles of 
channel enlargement and levees, about 1.8 miles of 
rectangular concrete channel improvements, and 
450,000 cubic yards of redredging on lower Corte 
Madera Creek. Approved estimated cost for new 
work in Unit 4 and previously constructed features 
(October 1992) is $31,800,000, of which 
$18,000,000 is Federal cost and $13,800,000 is 
non-Federal cost (includes $760,000 to be contributed 
by local interests.) (See table 34-B for 
authorizing legislation.) 
Local cooperation. Local interests must provide 
lands and rights-of-way, including suitable areas for 
disposal of waste material, modify or relocate all 
bridges and utilities necessary for construction and 
maintenance; hold and save the United States free 
from damages due to the construction works; 
maintain and operate the project after completion in 
accordance with the regulations prescribed by the 
35-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Secretary of the Army, and prevent encroachment 
on flood channels that would result in decreasing the 
effectiveness of project for flood control; adjust all 
claims regarding water rights that might be affected 
by the project; and contribute in cash 1.5 percent of 
Federal construction cost of Ross Valley unit and 
tidal areas, an estimated $760,000. Marin County 
Flood Control and Water Conservation District 
previously furnished resolution of local assurances 
dated March 29, 1966, March 28, 1967, August 15, 
1967, and July 8, 1969, and Marin County Board of 
Supervisors reaffirmed by letter dated September 28, 
1978. Project was authorized by the State of 
California by 1965 Statute, Chapter 1388. Board of 
Supervisors of Marin County Flood Control and 
Water Conservation District furnished assurances of 
willingness and ability to meet requirements for 
portion of project below Sir Francis Drake 
Boulevard. 
On December 13, 1983, Marin County Board of 
Supervisors reconfirmed assurances of local cooperation 
because a Superior Court Judgment ordered that 
county to take all steps required by law to complete 
channel downstream of Sir Francis Drake Boulevard 
(Unit 4) and maintain entire project as agreed. A 
Local Cooperation Agreement for redredging the 
lower reach of Corte Madera Creek was executed on 
June 29, 1985. Marin County also provided support 
for Ross Valley Unit 4 by resolution on March 24, 
1987 and by the resolution on September 13, 1988. 
Operations and results during fiscal year. New 
work: All work was suspended pending coordination 
with local communities on selection of a plan to 
complete the project. 
Historical summary. Project responsibility was 
transferred from San Francisco District on April 1, 
1982. Project is about 77 percent complete 
considering the portion being held in abeyance 
upstream of Sir Francis Drake Boulevard. Work 
remaining: Design construction of the remaining 
3,000 feet of channel downstream of Sir Francis 
Drake Boulevard and Ross Creek. In lieu of the 
authorized concrete channel, an alternative plan 
consisting of wing walls and individual house 
floodproofing is being recommended in the Significant 
Post-Authorization Change Report. The portion 
of Corte Madera Creek upstream of intersection of 
Sir Francis Drake Boulevard and Corte Madera 
Creek in Ross, near the city of San Anselmo, was 
classified as "inactive" on July 11, 1984, due to lack 
of local support. A Local Cooperation Agreement for 
redredging lower reach of Corte Madera Creek was 
executed June 29, 1985. Construction on Lower 
Corte Madera Creek Channel was completed and 
transferred to Marin County Flood Control and 
Water Conservation District by letter of May 28, 
1987. San Francisco District monitors maintenance 
and operation of the project. 
9. FAIRFIELD VICINITY STREAMS, CA 
Location. On five streams in vicinity of cities of 
Fairfield and Suisun, Solano County, CA. 
Existing project. Provides for channel improvement 
on Ledgewood, Laurel, and McCoy Creeks and 
diversion of three creeks upstream from Fairfield 
(Pennsylvania Avenue Creek into Ledgewood Creek, 
Union Avenue Creek into Laurel Creek, and Laurel 
Creek into McCoy Creek). Project related recreation 
facilities such as access roads, parking areas, a 
boat-launching ramp and hiking, bicycle, and 
horseback trails would also be constructed. Estimated 
cost (October 1992) for existing project is 
$39,400,000 (includes an allowance for estimated 
inflation through the construction period), of which 
$14,770,000 is Federal and $24,630,000 is 
non-Federal (includes $560,000 cash contribution). 
For future non-Federal reimbursement, see Local 
cooperation paragraph. Existing project was adopted 
by sec. 201, 1965 Flood Control Act (1970 Senate 
and House Public Works Committee resolutions) and 
Further Continuing Appropriations Act for FY 1986 
(Public Law 99-190), December 19, 1985, and 
Supplemental Appropriations Act of 1987. (HD 
91-159, 91st Cong., 1st sess., contains published 
map). 
Local cooperation. Local interests are required 
to provide lands, easements, rights-of-way, and 
dredged material disposal areas, modify or relocate 
buildings, utilities, roads, and other facilities, except 
railroad bridges, where necessary in the construction 
of the project, pay one-half of the separable costs 
allocated to recreation, presently estimated at 
$560,000 (cash contribution); and bear all costs of 
operation, maintenance, and replacement of recreation 
facilities and flood control facilities. Ultimate 
non-Federal cost for flood control will be reduced by 
a Federal reimbursement of one-half of the 
non-Federal costs in excess of the Federal 
construction costs. Local interests have agreed to 
make all required payments concurrently with 
project construction. 
Project had been in "deferred" status since 
September 15, 1977, due to lack of local assurances. 
In April 1982, the cities of Fairfield and Suisun 
affirmed their support and intent to provide 
necessary assurances of local cooperation for a 
modified version of the authorized project from 
200-year to 100-year flood protection. On June 23, 
1982, project was reclassified from "deferred" to 
"active" status. The State of California Reclamation 
Board has provided a letter of intent to the Assistant 
Secretary of the Army, November 8, 1982, to 
cooperate with the Federal Government to begin 
construction of the project. In accordance with FY 
1985 Supplemental Appropriations Act (Public Law 
99-88) and sec. 117 of the Further Continuing 
Appropriations Act for FY 1986 (Public Law 
99-190), a Local Cooperation Agreement for flood 
control and recreation (sec. 221) was executed 
June 3, 1986. 
35-8

SACRAMENTO, CA, DISTRICT 
Sec. 117 of Further Continuing Appropriations 
Act for FY 1986 contained the following authorization 
language which will be reflected in any future 
modified agreements: "The Secretary shall include as 
part of the non-Federal contribution of the project 
for flood control, Fairfield Vicinity Streams, 
California, authorized in accordance with sec. 201 of 
Flood Control Act of 1965, the cost of any work 
carried out by non-Federal interests on the project 
after December 31, 1973, and before the date of the 
enactment of this joint resolution if the Secretary 
determines such work is reasonably compatible with 
the project. Costs and benefits resulting from such 
work shall continue to be included for purposes of 
determining economic feasibility of the project." 
Prior local expenditures of $6,600,000 have been 
reported by the sponsor. The Corps is evaluating 
costs and benefits of all completed works by 
non-Federal interests after December 31, 1973. 
Operations and results during fiscal year. 
Ledgewood Creek Channel, Phase IV, contract was 
completed at a fiscal year cost of $429,717 and 
transferred to local interests in December 1991 for 
maintenance. Construction of Laurel Creek 
pedestrian bridge overcrossing was initiated at a fiscal 
year cost of $73,337. 
Historical summary. Local Cooperation Agreement 
was executed on June 3, 1986. Construction 
was initiated in October 1986. Enlargement of 
McCoy Creek and construction of Laurel Creek 
Diversion Channel, Phase I, was transferred to local 
interests in July 1987; Laurel Creek Diversion 
Channel, Phase II, was transferred to local interests 
in November 1988; Laurel Creek Diversion Channel, 
Phase III, was transferred to local interests in April 
1990; and Laurel Creek Diversion, Phase IIA, was 
transferred to local interests in December 1990 for 
maintenance. Channel improvement contract for 
Ledgewood Creek Channel, Phase IV, was completed 
and transferred to local interests in December 
1991 for maintenance. Construction of Laurel Creek 
pedestrian bridge overcrossing was initiated. 
10. GUADALUPE RIVER, CA 
Location. On Guadalupe River in downtown area 
of city of San Jose, Santa Clara County, CA. 
Existing project. Authorized plan provides for 
widening and deepening one or more sides of 
Guadalupe River for 2.5 miles from Interstate 
Highway 280 to Interstate Highway 880 in downtown 
San Jose, CA, and channel modifications with 
provisions for fish and wildlife mitigation, as 
necessary. Non-Federal sponsor must pay 100 
percent of incremental construction cost of locally 
preferred plan. Project is an integral component of a 
much larger regional park plan being undertaken by 
the San Jose Redevelopment Agency. 
Estimated cost (October 1992) is $133,400,000 
(which includes an allowance for estimated inflation 
through the construction period) of which 
$60,600,000 is Federal and $72,800,000 is 
non-Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted by Water 
Resources Development Act of 1986 and Energy and 
Water Development Appropriation Act of 1990 
which directed the Secretary of the Army to 
construct the project notwithstanding sec. 902 of the 
Water Resources Development Act of 1986 regarding 
project cost limitations. 
Local cooperation. Local interests, through a 
public body legally authorized and financially 
capable, must give assurances they will furnish lands, 
easements, rights-of-way, and dredged material 
disposal areas, which are partially offset by a credit 
($5,700,000) allowed for prior work (sec. 104, 
Water Resources Development Act of 1986); credit 
was approved by the Assistant Secretary of the Army; 
modify or relocate buildings, utilities, roads, bridges 
(except railroad bridges), and other facilities, where 
necessary in the construction of the project; pay 5 
percent of the costs allocated to flood control; and 
bear all costs of operation, maintenance, and 
replacement of flood control facilities. Federal 
reimbursement will be made to non-Federal sponsor 
for one-half of non-Federal costs allocated to flood 
control in excess of Federal costs. Local interests 
have agreed to make all required payments 
concurrently with project construction. 
On June 2, 1989, the local sponsor, the Santa 
Clara Valley Water District, expressed intent to 
provide all needed cost sharing funds. On September 
21, 1990, the San Jose Redevelopment Agency 
requested modification of project to include 
recreation facilities and confirmed that they intend to 
participate as local sponsor for recreation. Local 
Cooperation Agreements for both flood control and 
recreation were executed March 30, 1992. 
Operations and results during fiscal year. The 
final General Design Memorandum, reflecting the 
locally preferred plan, was approved by the Assistant 
Secretary of the Army on March 26, 1992, with 
comments. Revision of GDM to address comments 
was initiated and scheduled for completion in April 
1993. First construction contract for channel 
improvement (Highway 880 to Hedding Street) was 
awarded in August 1992. 
Historical summary. Final General Design 
Memorandum (GDM) reflecting locally preferred 
plan, was approved by the Assistant Secretary of the 
Army on March 26, 1992, with comments. Revision 
of GDM to address comments was initiated. Local 
Cooperation Agreements for both flood control and 
recreation were executed March 30, 1992. First 
construction contract for channel improvement 
(Highway 880 to Hedding Street) was awarded 
August 10, 1992. 
35-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
11. HIDDEN DAM-HENSLEY LAKE, 
FRESNO RIVER, CA 
Location. On Fresno River about 50 miles above 
its mouth and about 15 miles northeast of Madera, 
CA (See Geological Survey quadrangles for area.) 
Existing project. Provides for construction of a 
163-foot high earthfill dam to create a reservoir with 
gross storage capacity of 90,000 acre-feet for flood 
control, irrigation, recreation and other purposes. In 
conjunction with the dam, the project provides for 
about 13 miles of downstream levee and channel 
improvements on Fresno River immediately upstream 
of Chowchilla Canal crossing to accommodate 
project design flow of 5,000 cubic feet per second. 
Operation and maintenance of dam and reservoir is 
the responsibility of the Federal Government. Total 
first cost for existing project is $31,785,426, of which 
$30,555,426 is Federal cost, including $3,564,168 
for basic recreation facilities, and estimated 
$1,230,000 non-Federal cost for lands and damages 
including relocations for downstream levee and 
channel improvements. Local interests have contracted 
with the Bureau of Reclamation for irrigation 
service. For future non-Federal reimbursement, see 
Local cooperation paragraph. Local interests have 
also, over a period of years, expended about 
$300,000 for construction of low levees and clearing 
downstream channels to provide some local flood 
protection in the project area. This work is 
inadequate during major floods. Existing project was 
adopted by 1962 Flood Control Act (S. Doc. 37, 
87th Cong., 1st sess., contains latest published map). 
Lake created by Hidden Reservoir project on Fresno 
River was designated "Hensley Lake" by Public Law 
93-603. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work. None. Maintenance: Maintenance and 
operation activities were continued. Runoff of 
Fresno River below Hidden Dam was below normal 
for the year. Maximum storage of 26,884 acre-feet 
occurred May 30, 1992. Maximum hourly inflow to 
the reservoir was 1,115 cubic feet per second on 
February 15, 1992. Maximum release of 254 cubic 
feet per second on July 22, 1992, was below 
maximum permissible flood release. During the year, 
19,880 acre-feet of water was released for irrigation 
and other purposes. 
Historical summary. Construction began in July 
1971 and was completed in January 1979. Dam 
closure was in March 1975; dam was completed 
November 1975. Instrumentation was completed in 
January 1976. Downstream channel improvement, 
Fresno River, was completed April 1976. Recreation 
areas: Phase I was completed in March 1976; Phase 
II was completed in June 1978. Residences, 
administration building, grounds, and utilities 
contract was completed in February 1978. Landscaping 
was completed in December 1978 and erosion 
control was completed in January 1979. Project was 
completed in September 1980. Final land audit was 
approved February 5, 1980. Dam safety assurance 
studies were initiated in FY 1980. Piezometer 
installation was completed in September 1982. Solar 
heating was installed at recreation areas in FY 1984. 
12. ISABELLA LAKE, KERN RIVER, CA 
Location. About 35 miles northeast of city of 
Bakersfield, CA, near confluence of north and south 
forks of Kern River; auxiliary dam is about one-half 
mile east of main dam. (See Geological Survey 
quadrangles of area.) In 1991, Isabella Lake and 
16,000 acres of surrounding land was transferred to 
the Forest Service in exchange for about 2,500 acres 
of Forest Service land near Pine Flat Lake. 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1967. Federal cost for new work is $22,027,452. 
For future non-Federal reimbursement see Local 
cooperation and Licenses paragraphs. Federal cost 
funded from Code 710 appropriations is $2,199,085. 
Operation and maintenance of dam and reservoir is 
Federal responsibility. 
Local cooperation. California officially adopted 
project by chapter 1514 of statutes of 1945, State of 
California. Local interests, represented by North 
Kern, Buena Vista, and Tulare Lake Basin Water 
Storage Districts and La Hacienda Water District, 
were required to reimburse the Federal Government 
the portion of first cost and annual operation and 
maintenance costs allocated to irrigation functions of 
project. These costs, based on a cost allocation study 
completed in December 1955, are $4,573,000 of first 
cost and 21.7 percent of annual operation and 
maintenance cost. For the years 1956 through 1964, 
an interim contract between the Bureau of 
Reclamation and local water users provided for 
storage and payment of irrigation water. Under 
provisions of this interim contract, local interests paid 
$1,936,229 through December 31, 1964. A 
long-term contract between the Bureau and local 
water users was executed October 23, 1964. Balance 
due on allocated first cost of $4,573,000 was paid by 
the water users on March 31, 1965. Kern County 
assumed administration of recreation and development 
and maintenance of public use areas at project 
in accordance with a 25-year license February 15, 
1955. The agreement with Kern County provided for 
joint operation and development by the Corps and 
Kern County including permits granted to concessionaires 
by the county to provide certain services. As 
of September 30, 1971, Kern County relinquished all 
administration of recreation and development and 
maintenance of public use areas at the project. A 
State law permitting the Department of Boating and 
Waterways (known as the Department of Navigation 
and Ocean Development prior to January 1979) to 
35-10

SACRAMENTO, CA, DISTRICT 
participate in inland water development with Federal 
agencies was signed by the Governor on August 11, 
1972. Isabella Lake and surrounding land, 16,000 
acres around the lake currently being used for park 
and recreation purposes, was turned over to the 
Forest Service by the Corps on May 15, 1991, in 
exchange for approximately 2,500 acres of Forest 
Service recreation land near Pine Flat Lake. This 
was accomplished by using a memorandum of 
understanding (MOU) between the Secretary of the 
Army and the Secretary of Agriculture (Forest 
Service). The MOU requires an exchange of land 
between departments. Three Corps maintenance 
employees, under supervision of the Success Lake 
park manager, will stay at Isabella to operate the dam 
for flood control and water conservation purposes. 
Authority for new concessionaire operating permits 
to be issued, as well as those previously granted by 
the Corps, will be transferred to the Forest Service. 
Total cost to date of present recreation facilities 
developed by the county and the marina concessionaires 
is about $965,000; $235,000 of this was a grant 
from the California Wildlife Conservation Board and 
about $534,000 is investment by marina 
concessionaires. 
Licenses. In accordance with Federal Power 
Commission Docket No. E-6578, issued April 1, 
1963, payment of $377,426 was made to the Federal 
Government by Pacific Gas and Electric Co. 
($108,352) and Southern California Edison Co. 
($269,074) for headwater benefits to downstream 
existing plants from Isabella Dam to cover benefits 
from April 15, 1954, to December 31, 1962. 
Between 1962 and 1982, the power companies have 
in the aggregate made annual payments of $44,650 
for headwater benefits. That amount was to be paid 
each year until changes in operation, development, 
or costs indicated some modification to be advisable. 
Federal Power Commission Docket No. E-6578 was 
revised by Docket No. HB07-75-4-000 (order 
issued July 11, 1983 under 24 FERC, paragraph 
62052) which modified cumulative use charges after 
1974, effective retroactively. Such charges will now 
vary each year. An adjustment (years 1974 through 
1984) was included in 1984 payment of $244,790. 
The 1985 payment was $52,747; 1986 payment was 
$51,905. No payment was received in 1987. The 
1988 payment was $58,187. No payment was 
received in 1989. Two payments ($60,894 and 
$55,443) were received in 1990; $60,983 was 
received in 1991; and $65,975 was received in 
October 1991 (FY 1992). Cumulative use charges 
collected by the Federal Power Commission (known 
as the Federal Energy Regulatory Commission since 
January 9, 1978) and returned to the U. S. Treasury 
through period ending September 30, 1992, 
amounted to $2,010,650. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation continued. 
Structures were maintained in good condition. 
Runoff of Kern River above Isabella Dam was below 
normal for the year. Maximum storage of 153,942 
acre-feet occurred June 5, 1992. Maximum hourly 
inflow to the reservoir was 2,027 cubic feet per 
second on May 5, 1992, and maximum outflow of 
904 cubic feet per second occurred July 31, 1992. 
During the year, 272,416 acre-feet was released for 
irrigation and other purposes. 
Historical summary. Construction began in 
March 1948 and was completed in June 1968. Main 
dam, Borel Canal outlet works and appurtenances, 
and auxiliary dam were completed in April 1953. 
Storage impoundment began December 1952. 
Piezometer was installed in August 1982. Project is 
operating to provide flood protection and irrigation 
benefits for which it was designed. Recreation 
facilities were provided by Code 710 funds. Dam 
safety assurance studies were initiated in FY 1979. A 
cultural resources survey was completed in FY 1984. 
On May 15, 1991, Isabella Lake and surrounding 
land, 16,000 acres around the lake currently being 
used for park and recreational purposes, was turned 
over to the Forest Service by the Corps in exchange 
for approximately 2,500 acres of Forest Service 
recreation land near Pine Flat Lake. A memorandum 
of understanding (MOU) between the Secretary 
of the Army and the Secretary of Agriculture (Forest 
Service) was used. The MOU requires an exchange 
of land between departments. Three Corps 
maintenance employees, under supervision of the 
Success Lake park manager, will stay at Isabella to 
operate the dam for flood control and water 
conservation purposes. 
13. KAWEAH AND TULE RIVERS, 
INCLUDING TERMINUS DAM 
AND SUCCESS LAKE, CA 
Location. Terminus Dam is on Kaweah River 
about 20 miles east of Visalia, CA. Success Lake is 
on Tule River about 5 miles east of Porterville, CA. 
(See Geological Survey quadrangles of area.) 
Existing project. Terminus Dam: For description 
of completed improvement and authorizing act, see 
Annual Report for 1975. Federal cost of new work is 
$19,302,957, including $242,605 for basic recreation 
facilities and excluding spreading works 
constructed by local interests at an estimated (July 
1957) cost of about $750,000. Spreading works 
portion of project has been deauthorized. The 
90-day Congressional project review period, required 
by sec. 12, Public Law 93-251, as amended, 
ended August 5, 1977, and resulted in deauthorization 
of that portion of project. Federal cost of 
recreation facilities funded from Code 710 appropriations 
is $700,004. Success Lake: For description 
of completion improvement and authorizing act, see 
Annual Report for 1975. Federal cost of new work 
for Success Lake is $14,247,221, including $253,697 
for basic recreation facilities. Federal cost of 
35-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
recreation facilities funded from Code 710 appropriations 
is $747,048. For future non-Federal 
reimbursements, see Local cooperation paragraph. 
Operation and maintenance of reservoirs is Federal 
responsibility. 
Local cooperation. California officially adopted 
projects by chapter 1514 of statutes of 1945, State of 
California. Local interests for Terminus Dam are 
represented by Kaweah Delta Water Conservation 
District. Local interests for Success Lake are 
considered to be represented by the Vandalia, 
Porterville, and Lower Tule River Irrigation Districts, 
the Tulare Lake Basin Water Storage District, and 
Pioneer Water Co., which represent over 90 percent 
of irrigated land and water-right holders along Tule 
River below damsite. Local interests must reimburse 
the Federal Government the portion of first cost and 
annual operation and maintenance costs allocated to 
irrigation functions of projects. These costs are 
estimated at 14.1 percent of first and annual costs for 
Terminus and 9.5 percent of first and annual costs 
for Success. Local interests for Terminus stated they 
will continue to operate and maintain spreading 
works and downstream channel systems to provide 
required capacity for disposal of floodwaters. Local 
interests for Success stated they will continue to 
maintain downstream channel systems to provide 
required capacity for disposal of floodwaters. 
Repayment contracts between the Bureau of 
Reclamation and local water users for irrigation 
supply from Terminus and Success reservoirs were 
executed January 11, 1965, and April 30, 1965, 
respectively. Reservoirs are being operated for 
irrigation storage as well as flood control and 
incidental recreation use. Tulare County acquired 
water for recreation pools at the projects. Local 
interests paid the following total amounts for 
irrigation services from the reservoirs through 
December 31, 1991: Terminus, $1,990,957 and 
Success, $946,403. Tulare County was granted a 
25-year license for planning, development, and 
management of public recreation areas at Success, 
July 10, 1960, and at Terminus, June 5, 1961. Basic 
public-use facilities constructed by Corps at the 
Success reservoir were transferred to jurisdiction of 
Tulare County on January 18, 1962; facilities at 
Terminus were transferred June 20, 1962. In March 
1967, an amendment to the license agreements was 
approved by the Assistant Secretary of the Army. 
Under these amended licenses, Tulare County 
retained administration of only specified land areas 
and operation and maintenance of recreation 
facilities in these areas. In addition, they continued 
their program of water safety, boat inspection, and 
law enforcement at both reservoirs. The Corps took 
over the administration of the remainder of the 
project land areas and the operation and maintenance 
of recreation facilities in these areas. Calif. 
Department of Fish and Game expended funds to 
improve fishery resources of the Terminus reservoir. 
As of April 1, 1972, Tulare County relinquished all 
planning, development, and management of public 
recreation areas at Terminus Dam. Tulare County by 
expenditure of county funds and by a lease to a 
marina concessionaire has aided in the development 
of recreation facilities at an estimated cost of 
$199,000. Calif. Department of Fish and Game 
expended funds in conjunction with Tulare 
Sportsman's Council and developed a habitat for 
upland game birds at Success Lake. As of April 1, 
1972, Tulare County relinquished all planning, 
development, and management of public recreation 
areas at Success Lake, except for the Bartlett Park 
recreation area. Tulare County has aided in 
development of recreation facilities. Total cost to 
date of present recreation facilities developed by the 
county ($360,000) and the marina concessionaires 
($373,000) is about $733,000. 
Operations and results during fiscal year. New 
work: Terminus Dam, regular funds: None. Code 
710 funds: None. 
Success Lake, regular funds: None. Code 710 
funds: None. 
Maintenance: Terminus Dam: Maintenance and 
operation continued. Structures were maintained in 
serviceable condition. Runoff of Kaweah River above 
Terminus Dam was below normal for the year. 
Maximum storage of 89,484 acre-feet occurred on 
May 28, 1992. Maximum hourly inflow to the 
reservoir on May 7, 1992, was about 1,557 cubic feet 
per second. Maximum outflow of 1,413 cubic feet 
per second occurred June 6, 1992. Water released 
for irrigation and spreading releases totaled 146,744 
acre-feet. Success Lake: Maintenance and operation 
continued. Dam safety assurance studies were 
continued at a fiscal year cost of $8,391. Structures 
were maintained in serviceable condition. Runoff of 
Tule River above Success Dam was below normal 
during the year. Maximum hourly inflow to the 
reservoir was 449 cubic feet per second on 
February 15, 1992, and maximum outflow of 234 
cubic feet per second occurred on July 13, 1992. 
Maximum storage of 27,581 acre-feet occurred on 
May 14, 1992. Water released for irrigation and 
spreading releases amounted to 34,326 acre-feet. 
Historical summary. Terminus Dam: Construction 
of project began in July 1957 and was completed 
in June 1968. Final land audit was approved on April 
20, 1987. Construction of main dam and appurtenances, 
initiated in February 1959, was completed in 
June 1962. Dam has been operating since November 
1961 to provide flood protection for which it was 
designed; conservation impoundment was commenced 
May 1962. Appurtenances are in good 
condition. Recreation facilities were provided by 
Code 710 funds. Dam safety assurance studies were 
initiated in FY 1979 and completed in FY 1989. 
Piezometer installation and a cultural resources 
survey were completed in FY 1984. Success Lake: 
Construction of project began in November 1956, 
was completed in June 1968, and final audit of 
historical land record was approved December 17, 
1979. Construction of main dam and appurtenances, 
initiated in October 1958, was completed in May 
35-12

SACRAMENTO, CA, DISTRICT 
1961. Dam has been operating since October 1960 
to provide flood protection for which it was designed; 
conservation impoundment was commenced March 
1962. Recreation facilities were provided by Code 
710 funds. Dam safety assurance studies were 
initiated in FY 1979 and completed in FY 1989. A 
cultural resources survey was completed in FY 1984. 
14. LITTLE DELL LAKE, UT 
Location. On Dell Creek, a tributary of Parleys 
Creek, about 8 miles east of Salt Lake City upstream 
of Mountain Dell Reservoir in Salt Lake County, UT. 
Existing Project. Project providing for construction 
of a dam about 253 feet high to create a reservoir 
with a gross capacity of 30,000 acre-feet for flood 
control, municipal and industrial water supply, 
recreation and fish and wildlife was authorized by the 
1968 Flood Control Act (S. Doc. 53, 90th Cong., 1st 
sess., contains published map) as modified by sec. 
170, Water Resources Development Act of 1976, 
Public Law 94-587, October 22, 1976. Facility 
would be operated in conjunction with existing 
downstream 3,200 acre-foot Mountain Dell Reservoir 
on Parleys Creek for flood control and water 
supply. 
Authorized project has been reexamined and 
scaled down to reflect local interests' ability to pay. 
Current plan of improvement includes only flood 
control and water supply purposes. Recreation was 
deferred as of May 30, 1986, and Emigration Creek 
Diversion was deleted and placed in an inactive 
status. Project includes an earthfill dam 224 feet 
high, a 20,500 acre-foot reservoir, and 10,035 feet 
of pipeline to divert water from Parleys Creek. 
Estimated project cost (October 1992) is 
$60,000,000 (includes an allowance for estimated 
inflation through the construction period) of which 
$34,600,000 is Federal and $25,400,000 is non- 
Federal for lands and damages and includes a cash 
contribution of $19,200,000. Project is included in 
FY 1985 Supplemental Appropriations Act (Public 
Law 99-88) August 15, 1985. 
Local cooperation. Local interests are required 
to provide lands, easements, rights-of-way, and 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, bridges (except railroad 
bridges), and other facilities where necessary in the 
construction of the project; pay all costs allocated to 
municipal and industrial water supply; pay 13 percent 
of costs allocated to flood control to bring total 
non-Federal share of flood control costs to 25 
percent, bear all costs of operation, maintenance, 
and replacement of flood control facilities; and pay a 
cash contribution presently estimated at 
$19,200,000. By letters of January 22, 1986, and 
January 24, 1986, the Metropolitan Water District of 
Salt Lake City and Salt Lake County indicated their 
support and willingness to proceed with a reduced 
scale project based on their "ability to pay." A Local 
Cooperation Agreement (sec. 221) was executed on 
June 10, 1986. Water Revenue Bonds were issued 
August 27, 1986, and proceeds from the sale in the 
amount of $14,300,000 have been deposited in the 
Little Dell Construction Fund Account. 
Operations and results during fiscal year. 
Engineering activities continued. Main dam and 
appurtenances construction contract was continued 
at contract fiscal year cost of $10,670,447. 
Historical summary. A Local Cooperation 
Agreement (sec. 221) was executed June 10, 1986. 
Construction was initiated in April 1988. Construction 
of core trench and test fill was completed in 
February 1989. Main dam and appurtenances 
contract was awarded May 12, 1989. 
15. LOWER SAN JOAQUIN RIVER, CA 
Location. On Lower San Joaquin River, CA, 
from city of Stockton, CA, extending about 225 miles 
upstream to Friant Dam (about 19 miles northeast of 
Fresno) and along Kings River North for approximately 
25 miles upstream from Mendota Dam. 
Existing project. This project is a modification 
and extension of the previous Lower San Joaquin 
River and Tributaries project (see Annual Report for 
1976) to provide clearing and snagging on San 
Joaquin River from Stockton, CA, upstream to Friant 
Dam. Estimated first cost (October 1992) is 
$29,776,000, of which $22,876,000 is Federal and 
$6,900,000 is non-Federal for lands and damages 
(includes an allowance for estimated inflation 
through the construction period as well as 
$12,976,000, Federal, and $5,000,000, non-Federal, 
for work completed by 1974). Existing project was 
included in the 1983 Supplemental Appropriations 
Act, Public Law 98-63, July 29, 1983, which states 
that project for flood protection on Lower San 
Joaquin River, CA, authorized by the Flood Control 
Act approved December 22, 1944, as amended, is 
modified to authorize the Secretary of the Army, 
acting through the Chief of Engineers, to perform 
clearing and snagging on San Joaquin River from 
Stockton, CA, to Friant Dam, at an estimated cost of 
$5,000,000. The Energy and Water Development 
Appropriation Act of 1988, Public Law 100-202, 
December 22, 1987 (H.J. Res. 395) modifies 
Supplemental Appropriations Act of 1983 to include: 
clearing and snagging in area of North Fork of Kings 
River in Mendota Pool from southerly boundary of 
James Reclamation District Number 1606 to 
Mendota Dam; fish and wildlife mitigation; and such 
riprapping in area of clearing and snagging on such 
rivers as may be necessary to prevent erosion from 
such clearing snagging; and increase estimated cost of 
clearing and snagging on Lower San Joaquin River, 
including activities above, from $5,000,000 to 
$8,000,000. 
Local cooperation. Prior to initiation of 
construction, a non-Federal entity shall furnish 
35-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
adequate assurance for providing all lands, easements, 
rights-of-way and dredged material disposal 
areas; modify or relocate buildings, utilities, roads, 
bridges (except railroad bridges), and other facilities, 
where necessary in construction of project at no 
expense to the Federal Government, execute a local 
cooperation agreement pursuant to sec. 221 Public 
Law 96-611; agree to operate and maintain the 
project works upon completion of construction in 
accordance with rules and regulations prescribed by 
the Department of the Army; and hold and save the 
United States free from damages due to construction, 
operation, and maintenance of the project, not 
including damages due to the fault or negligence of 
the United States or its contractors. Non-Federal 
sponsor, the California State Reclamation Board, has 
agreed to make all required payments concurrently 
with project construction. 
Operations and results during fiscal year. 
Minor coordination with local interests and pertinent 
agencies was continued. Lack of consensus of 
support by Federal, State and local entities led to 
request for reclassification of the project to deferred 
status. 
Historical summary. A Plan of Action, February 
1984, has been prepared. Design Memorandum No. 
5 for Eastside Bypass at San Joaquin River was 
prepared in September 1984. First construction 
contract, dredging Eastside Bypass, was awarded 
October 12, 1984 and completed in May 1985. 
16. MARTIS CREEK LAKE, MARTIS 
CREEK, NV AND CA 
Location. Reservoir is on Martis Creek a tributary 
of Truckee River, near Truckee, CA; intermittent 
channel improvements are on Truckee River in 
Reno, NV. (See Geological Survey quadrangles for 
areas.) 
Existing project. For description of completed 
improvement and authorizing act, see Annual Report 
for 1975. Federal cost for project was $8,503,789 
including $289,506 for basic recreation facilities. 
Federal cost of recreation facilities funded from 
Code 710 appropriations was $1,200. Construction 
of recreation facilities under Code 710 was 
determined to be infeasible. Operation and maintenance 
of reservoir is Federal responsibility. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. New 
work: None. Maintenance: Maintenance and 
operation of project, including recreation facilities, 
was continued. Structures were maintained in 
serviceable condition. Runoff above Martis Creek 
Dam was below normal for the year. Maximum 
storage of 824 acre-feet occurred on February 21, 
1992. Maximum inflow to the reservoir was 67 cubic 
feet per second on February 22, 1992, and maximum 
outflow of 43 cubic feet per second occurred 
February 22, 1992. During the year, 633 acre-feet 
was released for flood control and 4,167 acre-feet 
was released for irrigation purposes. 
Historical summary. Project construction began 
in August 1967; dam closure was in October 1971; 
dam completed in August 1972; basic recreation 
facilities were completed in December 1972; and 
project was completed in June 1974. Recreation 
facilities under Code 710 funding were considered 
infeasible. Dam safety assurance studies were 
initiated in FY 1981. 
17. MERCED COUNTY STREAMS, CA 
Location. In vicinity of city of Merced, CA, on 
streams draining from Mariposa County foothills of 
the Sierra Nevada into Merced County. Streams lie 
easterly of and drain into the San Joaquin River 
between Chowchilla River on the south and Merced 
River on the north. Drainage area represents about 
1,000 square miles; nearly 700 square miles of 
foothills and mountains in Mariposa County and 
about 300 square miles of flood plain in Merced 
County. (See Geological Survey quadrangles for 
area.) 
Existing project. Project is a modification of 
Merced County Stream Group, Calif., Improvement 
No. 18, authorized by 1944 Flood Control Act (H. 
Doc. 473, 78th Cong., 2d sess.) and completed in FY 
1957. Existing project provides for construction of 
three new reservoirs-Castle, Haystack Mountain, 
and Marguerite on Canal, Black Rascal, and 
Deadman-Dutchman Creeks, respectively, and 
enlargement of four existing reservoirs-Burns, 
Bear, Owens, and Mariposa, providing a total 
capacity of 126,700 acre-feet for multipurpose 
storage; and about 52 miles of levee and channel 
improvements in lower reaches of Bear, Black 
Rascal, Mariposa, and Deadman Creeks, thereby 
tying the existing project channels into Eastside 
Bypass of San Joaquin River flood control system. 
Haystack Mountain, Bear, and Owens projects 
would provide flood control only; Castle and Burns 
projects, flood control and recreation; Marguerite 
project, flood control and irrigation; and Mariposa 
project, all three purposes. Existing project was 
adopted by 1970 Flood Control Act (Document not 
yet printed.) 
Current plan of improvement would defer 
enlargement of existing Burns reservoir, Mariposa 
reservoir, construction of Marguerite Dam, and the 
irrigation function associated with the latter two 
facilities, enlargement of existing Owens reservoir 
and about 32 miles of levee and channel 
improvement on Owens, Mariposa, and Deadman- 
Dutchman Creeks. Estimated total project cost 
(October 1992) is $112,300,000 (includes an 
allowance for estimated inflation through the 
construction period), of which $76,100,000 is 
35-14

SACRAMENTO, CA, DISTRICT 
Federal and $36,200,000 is non-Federal (which 
includes a $5,790,000 cash contribution). 
Local cooperation. Local interests are required 
to provide lands, easements, and rights-of-way and 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, and other facilities, where 
necessary in the construction of the project; pay 
one-half of the separable and joint costs allocated to 
recreation, presently estimated at $260,000, of 
which $220,000 is a cash contribution and $40,000 is 
for lands; and bear all costs of operation, 
maintenance, and replacement of flood control 
facilities. Total non-Federal share of Castle Dam 
first cost is $4,290,000 and includes cash contribution 
of $480,000. 
The California Reclamation Board and the City of 
Merced are the local sponsors of the authorized 
project. The Reclamation Board will serve as sole 
sponsor for the Castle Dam Unit. Merced County 
Board of Supervisors reaffirmed their support for the 
project by letter of April 4, 1986. City of Merced by 
letter of March 13, 1986, reaffirmed its support for 
and intent to furnish assurances for recreation 
aspects of the project. California Reclamation Board 
reaffirmed its support for total project by letter of 
April 9, 1986. A Local Cooperation Agreement (sec. 
221) was executed for Castle Dam Unit on June 27, 
1986. State of California legislation (AB3369) was 
enacted on September 14, 1986 which enabled the 
Reclamation Board to financially participate in the 
project. A new Local Cooperation Agreement 
(LCA) was signed by the Assistant Secretary of the 
Army November 30, 1988, in accordance with the 
Water Resources Development Act of 1986. The 
California Reclamation Board and the Merced 
County Board of Supervisors have indicated support 
for balance of the project by letters of intent dated 
August 29, 1991 and August 20, 1991, respectively. 
Operations and results during 
Engineering activities continued. 
multicomponent construction was 
contract cost of $1,617,553. 
fiscal year. 
Castle Dam 
continued at 
Historical summary. Castle Dam multicomponent 
construction contract was awarded February 26, 
1991, and construction was initiated in April 1991. 
18. MERCED COUNTY STREAM 
GROUP, CA 
Location. Reservoirs and channel improvements 
are on Bear, Burns, Mariposa, and Owens Creeks, in 
foothills of Sierra Nevada about 15 to 20 miles east of 
city of Merced, CA. (See Geological Survey 
Haystack Mountain quadrangle for Burns and Indian 
Gulch quadrangle for Bear, Owens, and Mariposa 
areas.) 
Existing project. For description of completed 
improvements and authorizing act, see Annual 
Report for 1962. Improvements consist of reservoirs 
at Mariposa, Owens, Burns and Bear Creeks and 
diversions from Black Rascal Creek to Bear Creek 
and from Creek to Mariposa Creek. Total first cost 
for project was $3,899,259, of which $2,751,259 was 
Federal and $1,148,000 non-Federal for lands 
including relocations and channel improvement. 
Local cooperation. Fully complied with. 
Operations and results during fiscal year. 
Maintenance: Ordinary maintenance and operation 
of the four completed reservoirs continued. Structures 
were maintained in a serviceable condition. 
Runoff from drainage areas above Merced County 
stream group reservoirs was below normal for the 
year. See Table 35-K for maximum inflow storage 
and outflow for the projects. Outflows were less than 
channel capacity rates in the project streams. Project 
prevented an estimated $910,000 in damages from 
the February 1992 rainflood. 
Historical summary. Construction was initiated 
March 1948, with construction of Mariposa project, 
which was completed in November 1948. Construction 
of Owens project, initiated in March, was 
completed in October 1949; Burns project, initiated 
in July 1949, was completed in January 1950; and 
Bear project initiated in April, was completed in 
December 1954. Black Rascal and Owens Creek 
diversion channels and stream-gaging stations were 
completed in April 1956. Local interests completed 
channel enlargement and restoration of channel 
capacities of Miles, Bums, Owens, and Mariposa 
Creeks in 1956 at their expense. Improvement of 
Bear Creek and Black Rascal Slough, below their 
confluence, was deferred pending possible improvements 
downstream, outside limits of project. 
19. PAJARO RIVER, CA 
Location. In the Uvas-Camadero and Llagas 
Creeks watersheds of the upper Pajaro River Basin in 
south Santa Clara County in vicinity of the city of 
Gilroy about 75 miles south of San Francisco, CA. 
Existing project. Provides for construction of a 
2-mile levee along the north side of Uvas Creek from 
a point about 2,000 feet downstream of Thomas 
Road to about 3,500 feet upstream of Miller Avenue. 
Project will also include a bikeway and hiking trail. 
Estimated cost (October 1992) for existing project is 
$13,814,000 (includes an allowance for estimated 
inflation through the construction period), of which 
$6,907,000 is Federal and $6,907,000 is non-Federal 
(which includes $565,000 cash contribution). 
For future non-Federal reimbursement, see Local 
cooperation paragraph. Existing project was adopted 
by Flood Control Act of 1944, December 21, 1944 
(HD 505-78, 78th Cong., 2d sess., contains 
published map.) 
Local cooperation. Local interests are required 
to provide lands, easements, right-of-way, and 
35-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, bridges (except railroad 
bridges) and other facilities where necessary in 
construction of project; pay one-half of separable 
costs allocated to recreation and bear all cost of 
operation, maintenance, and replacement of recreation 
facilities; and pay 5 percent of cost allocated to 
flood control and bear all costs of operation, 
maintenance and replacement of flood control 
facilities. Local interests will receive an estimated 
Federal reimbursement of $5,649,000 for one half of 
non-Federal costs allocated to flood control in 
excess of Federal costs. Local interests have agreed 
to make all required payments concurrently with 
project construction. 
Operations and results during fiscal year. The 
third and final construction contract (landscaping) 
was completed. Final accounting is underway. 
Historical summary. Responsibility for remaining 
portions of advance engineering and design, plans 
and specifications, and construction was transferred 
to Sacramento District in April 1982. Local 
Cooperation Agreement (LCA) for flood control was 
executed with the Santa Clara Valley Water District 
on June 25, 1987, and LCA for recreation was 
executed with the City of Gilroy on July 27, 1987. 
Construction began in October 1987. Construction 
for the first contract (levee work and bike path 
upstream of Thomas Road Bridge), second contract 
(levee work and hiking trails), and third and final 
contract (landscaping) has been transferred to local 
interests for operation and maintenance. Total 
reimbursement of $5,068,994 has been made to the 
local sponsor as of September 30, 1992. 
20. PINE FLAT LAKE AND KINGS 
RIVER, CA 
Location. Reservoir is on Kings River, about 25 
miles east of Fresno, CA, and channel improvements 
are on Kings River downstream from Lemoore weir, 
about 25 miles south of Fresno. (See Geological 
Survey quadrangles of area.) Project also includes 
2,500 acres of Forest Service recreation land near 
Pine Flat Lake. 
Existing project. Improvement is a unit in 
comprehensive plan for flood control and other 
related purposes for Sacramento-San Joaquin 
Basins. Project consists of a 429-foot high concrete 
gravity dam, including a gated overflow section with a 
maximum discharge capacity of 391,000 cubic feet 
per second, creating a reservoir with gross storage 
capacity of 1 million acre-feet, for flood control, 
irrigation, and related purposes. Outlet provisions for 
future power development are included in dam, but 
Federal construction of power-generating facilities is 
not authorized. Improvement also includes levee and 
channel work on Kings River and its distributaries on 
valley floor about 25 miles south of Fresno. Channel 
improvement work will enlarge channel capacities 
and regulate flows in lower branches of the Kings 
River. There are nine public-use and recreation 
areas: One maintained by the Corps, four by the 
Forest Service, three jointly by the Corps and 
concession, and one by Fresno County. Also, five 
boat access-only areas are maintained by the Corps 
on the south side of the reservoir. Project cost is 
$42,072,330, of which $41,502,330 is Federal 
(including $13,700 for basic recreation facilities) and 
$570,000 non-Federal for rights-of-way for downstream 
channel improvements. For future non-Federal 
reimbursement, see Local cooperation paragraph. 
Federal cost of recreation facilities for Pine 
Flat Lake, funded from Code 710 appropriations is 
$1,595,100 exclusive of recreation facilities previously 
provided at a cost of $13,700. In addition, 
Federal cost of recreation facilities for Pine Flat 
Lake, funded from Public Works Acceleration 
Executive Act of 1962 appropriations, was $239,235 
(July 1963). Operation and maintenance of dam and 
reservoir is Federal responsibility. Existing project 
was adopted by 1944 Flood Control Act (H. Doc. 
630, 76th Cong., 3d sess., contains latest published 
map). 
Local cooperation. Local interests must 
reimburse the Federal Government for first costs 
allocated to irrigation functions of reservoir portion 
of project in accordance with reclamation law. Under 
provision of War Department Civil Appropriations 
Act of 1947, the Secretary of War, with concurrence 
of the Secretary of the Interior, determined 
allocation of cost to irrigation should be set at an 
amount not to exceed $14,250,000. In addition, 
local interests must pay 37.4 percent of annual 
maintenance, operation, and replacement costs of 
dam and reservoir allocated to irrigation function. 
Repayment contracts between the Bureau of 
Reclamation and the local water users for the 
irrigation use of the reservoir were executed 
December 23, 1963. The Bureau is administering the 
contracts in accordance with reclamation law as 
amended by the Reclamation Reform Act of October 
12, 1982. That act generally exempts the limitations 
under the early reclamation laws as being applicable 
to projects constructed by the Corps with two 
exceptions; however, all existing contracts to share 
construction and maintenance costs remain in effect. 
Prior to execution of the final contracts, the Bureau 
provided conservation water to local interests under 
an interim contract. Irrigation interests paid 
$13,464,130 for irrigation services through 
December 31, 1991. With respect to the downstream 
channel improvements, sec. 3, Flood Control Act of 
June 22, 1936, applies. King River Conservation 
District represents local interests; assurances were 
accepted November 20, 1959. Local interests have 
furnished all requirements for construction 
rights-of-way for construction of channel improvements 
required to date. Three concessionaires each 
at Lakeridge Marina (Deer Creek), Pine Flat Marina 
and Trimmer Marina provided public-use facilities in 
accordance with lease agreements with the Secretary 
35-16

SACRAMENTO, CA, DISTRICT 
of the Army. Estimated cost to date of facilities 
installed by these concessionaires is $1,727,000. 
Fresno County developed public-use facilities on an 
85-acre tract immediately downstream from dam for 
picnicking, camping, swimming, and playground 
activities, at an estimated cost to date of $476,000 
under provisions of a license agreement. The U.S. 
Forest Service developed and operates a picnic area 
at the upper end of reservoir. Cost of site 
development is about $37,500. Installation of a 
hydroelectric powerplant, located at the downstream 
toe of the Corps Pine Flat Dam, was completed in 
January 1984 by Kings River Conservation District. 
Project consists of an outdoor-type powerhouse 
containing three generating units with capacities of 55 
megawatts each for a total of 165 megawatts. 
Conservation District would make use of the three 
existing 13.5-foot diameter penstocks that were 
installed in Pine Flat Dam when constructed in 1954. 
Licenses. License No. 1988, effective April 1, 
1955, was issued by Federal Power Commission to 
Pacific Gas and Electric Co. for hydroelectric power 
development of North Fork Kings River by the 
company upstream from the Pine Flat reservoir. 
Under interim Contract No. DA-04-167-eng-1182 
with the Department of the Army, Pacific Gas and 
Electric Co. paid for storage of power water in the 
Pine Flat reservoir May 15, 1954, through March 31, 
1955. Current Contract No. DA-04-167-eng-1328 
with the Department of the Army provides for storage 
of power water at the rate of 0.1375 per acre-foot; 
the contract covers April 1, 1955, through March 31, 
2005. By an agreement of January 1972, supplementing 
the December 1954 contract, Pacific Gas 
and Electric Co. transferred ownership of most of its 
Kings River system water to the Kings River Water 
Association. Accordingly, no further significant 
storage service to Pacific Gas and Electric Co. by the 
reservoir at Pine Flat is anticipated. Total payment 
under these contracts through June 30, 1972, (last 
year of payment), amounts to $2,478,798; these 
funds were paid to Sacramento District and deposited 
for return to the Treasury. License No. 2741, 
effective September 25, 1979, was issued by the 
Federal Energy Regulatory Commission to the Kings 
River Conservation District for hydropower development 
at the downstream toe of the Corps Pine Flat 
Dam. Payment to the Department of the Army for 
construction and installation of the penstocks in the 
amount of $1,044,685 was made to Sacramento 
District and deposited for return to the Treasury in 
November 1985. 
Operations and results during fiscal year. New 
work, regular funds: None. Code 710 funds: None. 
Maintenance: Maintenance and operation activities 
continued. Contract for paving of recreation roads 
and parking areas at Island Park recreation area was 
completed at fiscal year cost of $16,359. ($255,678 
payment in FY 1991). Structures were maintained in 
serviceable condition. Runoff of Kings River above 
Pine Flat Dam was below normal for the year. 
Maximum storage of 357,024 acre-feet occurred on 
May 31, 1992. Maximum hourly inflow to the 
reservoir was 5,357 cubic feet per second on May 6, 
1992, and maximum outflow of 5,377 cubic feet per 
second occurred on June 7, 1992. During the year, 
758,484 acre-feet was released for irrigation and 
spreading. 
Historical summary. Construction began in April 
1947 and project, including channel improvement, 
was completed in September 1977. Main dam was 
initiated in January 1950, completed in June 1954, 
and has been operating since February 1954 to 
provide flood protection for which it was designed. 
Total of 35.2 miles of new and reconstructed levees 
and 13.2 miles of channel clearing have been 
transferred to the Kings River Conservation District 
for maintenance. Recreation facilities for various 
recreation areas under Code 710 appropriation are 
complete. Completed preliminary design and cost 
estimates for Pine Flat fish barrier were reviewed by 
the State, but the State was unable to provide 
necessary assurances of local cooperation. Dam 
safety assurance studies were initiated in FY 1982. A 
cultural resources survey was completed in FY 1984. 
On May 15, 1991, Pine Flat Lake acquired 
additional acreage as part of a memorandum of 
understanding (MOU) between the Secretary of the 
Army and Secretary of Agriculture (Forest Service). 
The Corps exchanged Isabella Lake and the 16,000 
acres around that lake currently being used for park 
and recreational purposes for approximately 2,500 
acres of Forest Service recreation land near Pine Flat 
Lake. 
21. REDBANK AND FANCHER 
CREEKS, CA 
Location. Northeast and adjacent to the 
Fresno-Clovis Metropolitan Area in Fresno County 
about 170 miles southeast of Sacramento, CA. 
Existing project. Provides for flood control 
detention basins on Redbank Creek, Pup Creek, and 
Alluvial Drain; construction of a dam 45.5 feet high 
to create a reservoir with gross capacity of 10,300 
acre-feet for flood control on Fancher Creek; and 
enlargement of Big Dry Creek project to provide 
increased flood protection and recreational development. 
Since the local sponsor does not support 
recreational development at this time, the recreation 
feature of the project is considered to be inactive. 
The authorization Act states "measures determined 
appropriate by the Secretary of the Army to minimize 
benefits to groundwater recharge" shall be included 
in the project. Estimated cost (October 1992) for 
existing project is $66,000,000 (includes an 
allowance for estimated inflation through the 
construction period), of which $48,600,000 is 
Federal and $17,400,000 is non-Federal (which 
includes $3,290,000 cash contribution). For future 
non-Federal reimbursement, see Local cooperation 
paragraph. Existing project was adopted by sec. 401, 
Water Resources Development Act of 1986, Public 
35-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Law 99-662, November 17, 1986. (HD 98-147, 
98th Cong., 2d sess., contains published map.) 
Local cooperation. Local interests are required 
to provide lands, easements, rights-of-way, and 
dredged material disposal areas; modify or relocate 
buildings, utilities, roads, bridges (except railroad 
bridges) and other facilities where necessary in 
construction of the project; pay 5 percent of cost 
allocated to flood control to bring total non-Federal 
share of flood control costs to 25 percent, of which 
$3,290,000 is cash contribution, and bear all costs of 
operation, maintenance and replacement of flood 
control facilities. Local interests have agreed to make 
all required payments concurrently with project 
construction. 
Operations and results during fiscal year. 
Engineering activities were continued. Construction 
contract for Fancher Creek Dam was completed at 
fiscal year cost of $1,793,526 and was transferred to 
local interests for operation and maintenance on 
March 13, 1992. Construction contract for Big Dry 
Dam, Pup and Alluvial detention basins was awarded 
March 18, 1992. Construction was initiated at 
contract cost of $6,614,313. 
Historical summary. Local Cooperation Agreement 
was executed on August 1, 1987. Project 
construction was begun in September 1987 with 
initiation of archaeological work on Cultural 
Resources Preservation. Construction contract for 
Dry Creek Crossing was completed and transferred to 
local interests for operation and maintenance on 
January 10, 1989. Construction at Redbank Creek 
Detention Basin was completed and transferred to 
local interests for operation and maintenance on 
August 23, 1990. Construction contract for Fancher 
Creek Dam awarded May 23, 1990, was completed 
and transferred to local interests for operation and 
maintenance on March 13, 1992. Construction 
contract for Big Dry Dam, Pup and Alluvial detention 
basins was awarded March 18, 1992. 
22. RUSSIAN RIVER BASIN, CA 
Location. Russian River rises in Coast Range in 
northwestern California, flows southerly for 87 miles, 
and then turns westerly to flow for 23 miles to Pacific 
Ocean at Jenner, 60 miles northwest of San 
Francisco, CA. (For general location see Geological 
Survey map for California.) 
Existing project. Active authorized project 
provides for construction of a dam on East Fork of 
Russian River at Coyote Valley to a height of 160 
feet; a dam on Dry Creek at Warm Springs to a height 
of 319 feet; and channel stabilization works on 
Russian River between mouth and mile 98, on lower 
reaches of several tributaries, and on Dry Creek 
downstream from dam. Project also provides for 
expansion of fish hatchery capacity at Dry Creek, 
Warm Springs, to compensate for fish losses on 
Russian River attributed to operation of Coyote Dam 
component of project. Coyote Valley Dam (Lake 
Mendocino), completed in 1959, is operated and 
maintained by the United States. (See tables 35-L 
and 35-M for latest approved estimated costs.) 
Local cooperation. Fully complied with for 
Coyote Valley Dam and channel improvements 
accomplished to date. For the Dry Creek portion, 
local interests are required by the authorizing act to 
comply with the usual a., b., c. requirements for 
channel improvements and, in addition, prevent any 
encroachment in the channel of Dry Creek which 
would interfere with proper functioning of the 
channel improvement works; adjust all claims 
concerning water rights arising from the construction 
and operation of the improvements, including 
acquisition of water rights needed for preservation of 
fish and wildlife resources affected by the project; 
and reimburse the United States in accordance with 
the Water Supply Act of 1958, as amended, for that 
part of the joint-use construction cost, (30.2 percent 
currently estimated at $103,100,000) and an 
ultimate 32.5 percent of the annual operation, 
maintenance, and replacement joint-use costs 
allocated to municipal and industrial water supply. 
The estimated annual cost to local interests for 
maintenance of channel improvement works is 
$80,000. Sonoma County Water Agency (formerly 
Sonoma County Flood Control and Water Conservation 
District) provided assurances of willingness and 
ability to meet requirements by Resolutions No. DR 
00793-1, September 25, 1961, No. DR 4770-1, 
December 17, 1962, and No. DR 45759, August 5, 
1974, for Dry Creek (Warm Springs) Lake and 
Channel. By letter dated March 7, 1967, Sonoma 
County Flood Control and Water Conservation 
District further indicated their interest in optimization 
of the Dry Creek (Warm Springs) damsite to 
provide additional water supply storage. Reimbursement 
to the United States for Dry Creek (Warm 
Springs) Lake and Channel costs allocated to 
212,000 acre-feet of water supply storage is specified 
in a water supply contract with the local sponsor 
approved in October 1982. Local interests have 
expended approximately $1,000,000 to provide 
partial flood protection in project area and have 
constructed facilities at an approximate cost of 
$20,000,000 to distribute water from the completed 
Coyote Valley reservoir. 
Operations and results during fiscal year. New 
work: Coyote Valley Dam: None. Dry Creek (Warm 
Springs) Lake and Channel: Engineering activities 
continued. Major items of contract work included: 
Initiation of fish hatchery emergency water supply at 
fiscal year cost of $847,978, and completion of the 
fish hatchery expansion including roofing, at fiscal 
year cost of $268,160. Maintenance: Coyote Valley 
Dam: Operation and maintenance continued. 
Structures were maintained in serviceable condition. 
Runoff of East Fork Russian River at Coyote Dam 
was below normal for the year. Maximum storage of 
93,272 acre-feet occurred on April 20, 1992. 
35-18

SACRAMENTO, CA, DISTRICT 
Maximum hourly inflow to reservoir was 4,626 cubic 
feet per second on February 12, 1992. Maximum 
release of 2,525 cubic feet per second occurred on 
February 15, 1992. During the year, 83,194 
acre-feet was released for flood control, and 91,347 
acre-feet was released for irrigation and other 
purposes. Project prevented an estimated $60,000 in 
damages from the February 1992 rainflood. Dry 
Creek (Warm Springs) Lake and Channel: 
Operation and maintenance continued. Structures 
were maintained in serviceable condition. Runoff of 
Dry Creek at Warm Springs Dam was below normal 
for the year. Maximum storage of 242,151 acre-feet 
occurred April 19, 1992. Maximum hourly inflow to 
reservoir was 6,216 cubic feet per second on 
February 12, 1992. Maximum release of 257 cubic 
feet per second occurred March 12, 1992. During 
the year, 63,087 acre-feet was released for irrigation 
and other purposes. Project prevented an estimated 
$50,000 in damages from the February 1992 
rainflood. 
Historical summary. Entire project, exclusive of 
recreation facilities at completed project (Lake 
Mendocino), is about 99 percent complete. Coyote 
Valley Dam, initiated November 1958, was completed 
April 1959 (cost $17,550,000, of which 
$11,952,000 was Federal; and $5,598,000 contributed). 
Work, including removal of slides resulting 
from storms in 1958, was completed April 1959. 
Bank stabilization work on Russian River near 
Geyserville was completed in 1957 and channel 
improvements in remaining reaches on Russian River 
and East Fork of Russian River were completed in 
1974 (cost $2,483,900). In April 1982, responsibility 
was transferred to the Sacramento District. 
Warm Springs construction completions include 
fish hatchery in December 1980, reservoir clearing in 
July 1981, project overlook in May 1981, downstream 
stabilization sills in October 1981, dam 
closure in October 1982, spillway repair at Warm 
Springs Dam in September 1985, boat launching 
facilities, Phase I, in September 1985 and Rockpile 
Road Upgrade, Yorty Creek Beach, and remedial 
work at Liberty Glen camping area in September 
1990, and fish hatchery expansion in September 
1992. Initial filling of Warm Springs reservoir was 
commenced on November 1, 1984. Major items of 
work remaining include emergency water supply, 
control tower grout, spillway stabilization, paving of 
dam access road and Liberty Glen sewer treatment 
repairs. Responsibility for construction was transferred 
to Sacramento District in August 1983. Dam 
safety assurance studies were initiated at Coyote 
Valley Dam in fiscal year 1984. 
23. SACRAMENTO RIVER AND 
TRIBUTARIES, CA, FROM 
COLLINSVILLE TO SHASTA DAM 
Location. Rises in Trinity Mountains in 
north-central California, flows generally southerly 
about 374 miles and empties into Suisun Bay, an arm 
of San Francisco Bay at Collinsville, CA. Works 
covered by this improvement are on Sacramento 
River and tributaries from Collinsville to Shasta Dam, 
about mile 312. Drainage area above Rio Vista is 
26,500 square miles (See Geological Survey 
quadrangles of area for Sacramento River and Upper 
Butte Basin; Flournoy and Fruto quadrangles for 
Black Butte Lake; and Tuscan Buttes, Tehama, 
Redding, and Hooker quadrangles for Table 
Mountain Lake.) 
Existing project. Improvement of Sacramento 
River and tributaries, from Collinsville to Shasta Dam 
was authorized as a unit of a comprehensive plan for 
flood control and other related purposes in 
Sacramento River Basin. (a) Sacramento River and 
major and minor tributaries, for flood control 
purposes: Enlargement of existing levees on 
Sacramento River between vicinity of Moulton weir 
and Ord Bend; construction of new levees from 
present levee terminus to vicinity of Chico Landing; 
construction of a weir near Chico Landing, extension 
of Moulton weir, and construction of a bypass 
through Upper Butte Basin; construction of new 
levees in Lower Butte Basin; enlargement of existing 
levees in Sutter, Tisdale, Sacramento, and Yolo 
Bypasses; and levee construction and/or channel 
enlargement on following minor tributaries of 
Sacramento River: Antelope Creek; Chico and Mud 
Creeks and Sandy Gulch; Butte and Little Chico 
Creeks; Cherokee Canal; Elder Creek; Deer Creek 
(Tehama County); Thomes Creek; and Willow 
Creek. Improvement provides for about 155 miles of 
channel improvement and about 294 miles of levees 
with an average height of 12 feet and a freeboard of 3 
feet. Improvement also provides for revetment as 
required for protection of bypass levee slopes against 
erosion. Total first cost for project is $18,300,000 
(October 1988), of which $11,900,000 is Federal, 
and $6,400,000 non-Federal for lands and damages, 
including relocations. (See table 35-N on project 
units classified and excluded from cost estimate.) (b) 
Sacramento River, Chico Landing to Red Bluff, CA: 
An extension of the existing Sacramento River Flood 
Control project which provides for construction of 
bank protection works and minor channel improvements 
as required on Sacramento River between 
Chico Landing and Red Bluff for flood control 
purposes. Estimated first cost (October 1987) for 
project work in Tehama, Butte, and Glenn Counties 
is $31,000,000, of which $25,700,000 is Federal cost 
and $5,300,000 non-Federal cost for lands and 
damages including relocations and cash contribution 
of $3,435,000. (c) Sacramento River, CA, Bank 
Protection Project: Includes initial phase covering 
430,000 lineal feet of bank protection and a second 
phase covering 405,000 lineal feet of bank protection 
under a long range program of bank protection, 
erosion control works, and setback levees at critical 
locations within limits of authorized or existing levees 
included in the Sacramento River Flood Control 
project to protect integrity of levee system for flood 
35-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
control purposes. Total estimated (October 1992) 
first cost for project is $155,000,000, (includes an 
allowance for estimated inflation through the 
construction period) of which $109,100,000 is 
Federal (including $2,670,000 for recreation facilities) 
and $45,900,000 non-Federal comprising for 
lands and damages including relocations and 
$23,100,000 required cash contribution toward first 
cost. Construction in (a), (b), and (c) above 
supplements program of levee improvements as 
accomplished pursuant to 1917 Flood Control Act, 
as amended by subsequent acts, including 1941 
Flood Control Act, and which are reported on page 
35-3A under Sacramento River, CA, flood control. 
(d) Authorization also provided for Black Butte 
Lake. For description of completed project see 
Annual Report for 1975. Federal first cost for project 
is $14,508,820, including $475,507 for basic 
recreation facilities. For future non-Federal reimbursement, 
see Local cooperation paragraph. 
Federal cost for recreation facilities funded from 
Code 710 appropriations is $1,000,162. A concessionaire 
at Black Butte Marina provided public use 
facilities in accordance with lease agreement with the 
Secretary of the Army at an estimated cost to date of 
$87,000. (e) Authorization also provided for 
construction of Table Mountain (Iron Canyon) 
project, an earthfill dam on Sacramento River about 
3 miles north of Red Bluff, CA. This project unit was 
deauthorized August 5, 1977. For details, see 
Annual Report for 1978. 
Local cooperation. (a) Sacramento River and 
major and minor tributaries: Sec. 3, Flood Control 
Act of June 22, 1936, applies. Fully complied with 
for all work completed or under contract, and local 
interests indicated they will be able to fulfill 
requirements for remaining work as scheduled. 
Levee construction (107 miles) total requirement for 
the "active" project has been completed, transferred 
to, and accepted by the State. (b) Sacramento River, 
Chico Landing to Red Bluff: Sec. 3, Flood Control 
Act of June 22, 1936, applies; local interests must 
also assume responsibility for flood plain zoning. 
Fully complied with for portions completed in 
Tehama, Butte, and Glenn Counties; completed 
work, bank protection at 36 sites, was transferred to 
and accepted by the State. (c) Sacramento River 
Bank Protection Project: Sec. 3, Flood Control Act 
of June 22, 1936, applies. Local interests must also 
contribute an amount in cash that, when added to 
costs of lands, easements, rights-of-way and utility 
modifications, equals one-third of cost of each unit 
of remedial work; this contribution is estimated 
(October 1992) at $23,100,000. Local interests fully 
complied with requirements for all work completed 
or under contract, and indicated they will be able to 
fulfill requirements for remaining work as scheduled. 
In addition, for reaches where local interests request 
bank stabilization in lieu of more feasible levee 
setbacks, local interests will contribute costs over and 
above costs of setbacks, and provide local 
contribution indicated above. Completed units 
transferred to and accepted by the State. (d) Black 
Butte Lake: None required for construction. Local 
interests must pay the portion of first cost and annual 
operation and maintenance costs allocated to the 
conservation functions of the project; these costs are 
estimated at 39.9 percent of first cost and 40.2 
percent of annual costs. From March 2, 1960, to 
October 22, 1970, contract between the Bureau of 
Reclamation and the State of California provided for 
repayment of irrigation storage costs; Bureau 
administered contract in accordance with reclamation 
law. Local interests paid a total of $77,205 for 
irrigation services during this period. Public Law 502, 
91st Cong., 2d sess., October 23, 1970, provided 
that Black Butte project be financially integrated with 
the Central Valley project, coordinated operationally 
with other Central Valley project storage units by the 
Bureau under the Secretary of the Interior, and that 
dam and reservoir at Black Butte be physically 
operated and maintained by the Corps in a manner 
compatible with recreational use of the reservoir. 
Operations and results during fiscal year. New 
work: (a) Sacramento River and major and minor 
tributaries-None. (b) Sacramento River Bank 
Protection Project-Engineering and design activities 
continued. (See table 35-0 for construction 
accomplished and contract costs.) (c) Sacramento 
River, Chico Landing to Red Bluff. None. (d) Black 
Butte Lake, regular funds: None. Code 710 funds: 
None. Maintenance: Maintenance and operation 
activities continued. Paving of recreation roads and 
parking areas at Buckhorn recreation area, Black 
Butte Lake, was completed at contract cost of 
$11,734. Structures were maintained in serviceable 
condition. Runoff above Black Butte Dam was below 
normal for the year. Maximum storage of 127,030 
acre-feet occurred February 27, 1992. Maximum 
hourly inflow to Black Butte reservoir was 8,926 
cubic feet per second on March 15, 1992, and 
maximum outflow of 2,144 cubic feet per second 
occurred on March 16, 1992. During the year, 
46,735 acre-feet was released for flood control and 
142,899 acre-feet was released for irrigation and 
other purposes. (e) Table Mountain (Iron Canyon) 
Lake: None. 
Historical summary. (a) Sacramento River and 
major and minor tributaries (active portions): 
Construction was initiated in May 1949 on Deer 
Creek and Butte Creek units; Cherokee Canal, Elder 
Creek, Chico and Mud Creeks, and Sandy Gulch 
units have been completed. Active portion of this 
improvement is about 99 percent complete. Work 
remaining is bypass levee revetment as required, 
which will accomplished under Sacramento River 
Bank Protection project. (b) Sacramento River Bank 
Protection Project: Construction of first unit was 
initiated in June 1963; initial phase of project was 
completed in November 1974. Phase II is underway, 
and overall project is about 90 percent complete. (c) 
Sacramento River, Chico Landing to Red Bluff: 
Active portion of project, bank protection in Tehama 
County, was initiated in June 1963 and completed in 
35-20

SACRAMENTO, CA, DISTRICT 
March 1964. Project was reopened in June 1968 to 
place additional necessary bank protection. Work at 
36 sites was completed in Tehama, Butte, and Glenn 
Counties as of September 1985 and transferred to 
State for maintenance. Bank protection on Sacramento 
River, Tehama County-one site, mile 215, 
(Unit 5), was completed November 1982, two sites, 
mile 209.5 and mile 217.5, (Unit 6), were completed 
in November 1983, and four sites, 241.0, 237.9, 
237.7, and 237.5 (Unit 7) were completed in 
February 1985. (d) Black Butte Lake: Construction 
began in March 1960 and project is complete. Final 
land acquisition was completed in December 1966. 
Construction of main dam was initiated in June 1960 
and completed in December 1963. Dam has been 
operating since November 1962 to provide the flood 
protection for which it was designed. Final cost 
allocation approved May 3, 1977. Dam safety 
assurance studies were initiated in FY 1980 and 
completed in FY 1986. Piezometer installation and 
slope for protection at the dam were completed in FY 
1983. A cultural resources survey was completed in 
FY 1984. (e) Table Mountain (Iron Canyon) Lake: 
Project unit deauthorized as of August 5, 1977. 
24. WALNUT CREEK, CA 
Location. Project is on Walnut Creek and lower 
reaches of its principal tributaries, Pacheco, 
Grayson, San Ramon, Las Trampas, Galindo, and 
Pine Creeks in Contra Costa County, CA. Improvement 
will extend from Suisun Bay to head of project 
about 1 mile above southern limits of city of Walnut 
Creek. City of Walnut Creek is about 10 miles south 
of Suisun Bay. (See Geological Survey quadrangles 
for area.) 
Existing project. Comprises extension of existing 
levees, construction of new levees and concrete 
channels, channel rectification and enlargement, and 
utilization of improvements constructed or planned 
by local interests. Plan provides for about 21.8 miles 
of channel improvement, two reinforced-concrete 
drop structures, two stilling basins, and 13.8 miles of 
levees. Cost estimate (October 1992) is $98,100,000 
(includes an allowance for estimated inflation 
through the construction period), of which 
$71,630,000 is Federal cost and $26,470,000 is 
non-Federal cost (includes $20,945,000 for lands 
and damages and relocations except railroad 
facilities, and $5,840,000 required cash contribution 
for land enhancement benefits provided by the 
project). Local interests have expended about $3 
million for flood control in the project area during 
the period 1955-1965, including the concrete 
conduits constructed through the city of Walnut 
Creek at an estimated cost of $1,000,000 considered 
a preproject condition to be incorporated in the 
Corps project. In addition, local developers have 
made channel improvements for Upper Pine Creek 
valued at $5,050,000. The cost thereof is not 
included in above costs of local cooperation. 
Improvement adopted by 1960 Flood Control Act 
(H. Doc. 76, 86th Cong., 1st sess., contains latest 
published map). 
Local cooperation. Section 3, Flood Control Act 
of June 22, 1936, applies, except that relocation of 
railroad facilities is a Federal responsibility. In 
addition, local interests must make a cash contribution 
to the United States, in amount of 7.4 percent of 
cost of construction for land enhancement benefits 
provided by project. Cash contribution is estimated 
(October 1992) at $5,840,000. Local interests are 
represented by Contra Costa County Flood Control 
and Water Conservation District; formal assurances, 
including evidence of financial and legal ability to 
fulfill requirement for the cash contribution, were 
accepted by the Sacramento District Engineer on 
November 15, 1963. The Flood Control District 
furnished all rights-of-way required to date and 
indicated that it will furnish all requirements as 
needed for future construction. The Flood Control 
District will arrange for highway bridge modifications 
and utility relocations before start of work by the 
Corps contractor. Payment of required contributed 
funds will be made in installments in amounts equal 
to 7.4 percent of the estimated construction 
expenditure for each fiscal year. Flood Control 
District and city of Walnut Creek have requested that 
recreation be added as a project purpose and will 
share costs in accordance with Water Resources 
Development Act of 1986. Post Authorization 
Change was approved July 27, 1987. To date, 
$5,612,681 has been furnished. 
Operations and results during fiscal year. New 
work: Engineering, design, and coordination for the 
recreation and erosion control mitigation and 
channel cover retrofit is continuing. Construction on 
San Ramon Bypass Channel was split into three 
contracts. The last contract, Contract No. 3, was 
completed in October 1991 at fiscal year contract 
cost of $3,714. Contract No. 2 was constructed with 
a channel cover at 100 percent local cost. The 
sponsor requested an investigation into the excessive 
deflection and roadway noise after the cover was 
constructed. The Corps investigated the problem 
and initiated design of a channel cover retrofit. 
Contract No. 1 had an outstanding claim with 
Liongate Corporation, which was essentially settled at 
a fiscal year cost of $600,632. 
Historical summary. Construction was initiated 
June 1964; project is about 98 percent complete. 
Total of 17.7 miles of channel improvement, 9.2 
miles of levee construction, part of channel 
improvement landscaping, Drop Structures No. 1 
and 2 and construction under San Ramon Bypass 
Contract No. 1, Contract No. 2 and Contract No. 3 
and Upper Pine Creek Channel contact have been 
transferred to local interests for operation and 
maintenance. Due to contractor difficulties with 
Contract No. 1 (Lionsgate claims and court action) 
part of the contract work was completed under 
Contract No. 1A with a different contractor. Work 
35-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
remaining consists of recreation, and erosion control 
mitigation. 
Construction responsibility was transferred from 
San Francisco District on April 1, 1982. 
25. WILDCAT AND SAN PABLO 
CREEKS, CA 
Location. Project is located in vicinity of San 
Pablo and Richmond, Contra Costa County, CA, 
about 20 miles northeast of San Francisco, CA. 
Existing project. Current plan of improvement 
reflects only Reach 1, which is from San Pablo Bay to 
AT&SF Railroad tracks on both Wildcat and San 
Pablo Creeks; Reach 1 consists of 9,900 lineal feet of 
channel improvements on Wildcat Creek and 10,000 
lineal feet of channel improvements on San Pablo 
Creek. Improvements include channel deepening, 
levees, stilling basins, and flow control weirs. 
Additionally, about 20 acres will be planted for 
mitigation of fish and wildlife. Reach 2, which is 
upstream of AT&SF Railroad tracks and consists of 
9,400 lineal feet of channel and levee work on 
Wildcat Creek, 1,800 lineal feet of channel and levee 
work on San Pablo Creek, and mitigation for fish and 
wildlife on 8 acres, was determined to be 
economically infeasible, excluded from total project 
cost, and reclassified as inactive. Project also 
includes recreation features on Wildcat Creek. 
Approved estimated cost of new work (1992) is 
$29,400,000 (includes an allowance for estimated 
inflation through the construction period), of which 
$16,200,000 is Federal cost, and $13,200,000 is 
non-Federal cost (includes $1,320,000 cash contribution). 
Improvements adopted by House and 
Senate Public Works Committee Resolutions June 9 
and 15, 1976, respectively, under provisions of sec. 
201 of Flood Control Act of 1965 (H. Doc. 511, 94th 
Cong., 2d sess., contains latest published map).For 
details on units, see Annual Report for 1968. 
Local cooperation. In accordance with cost 
sharing and financing concepts reflected in the Water 
Resources Development Act of 1986, local interests 
are required to provide lands, easements, rights of 
way, and dredged material disposal areas; modify or 
relocate buildings, utilities, roads, bridges (except 
railroad bridges), and other facilities, where 
necessary in the construction of project; pay 
one-half of the separable costs allocated to 
recreation and bear all costs of operation, maintenance, 
and replacement of recreation facilities; pay 5 
percent of the costs allocated to flood control and 
bear all costs of operation, maintenance, and 
replacement of flood control facilities. Local 
interests have agreed to make all required payments 
concurrently with project construction. The Board of 
Supervisors of Contra Costa County by Resolution 
73-466, June 25, 1973, agreed to assume obligations 
of local cooperation. On November 9, 1976, the 
Board reaffirmed sponsorship by Resolution 76-960. 
Contra Costa County Flood Control and Water 
Conservation District Board of Supervisors formed 
an Assessment District, August 3, 1982, which 
assures availability of funds for local share of 
non-Federal portion of flood control project costs 
for a modified plan of improvement. A flood control 
Local Cooperation Agreement satisfying all requirements 
of sec. 221, Flood Control Act of 1970 (Public 
Law 91-661) and consistent with the Water 
Resources Development Act of 1986 (Public Law 
99-662), was executed on June 20, 1986 between 
the Department of the Army and the Contra Costa 
County Flood Control and Water Conservation 
District. By Resolution No. 1985-12-351, adopted 
December 17, 1985, the East Bay Regional Park and 
Recreation District stated support for development of 
trail and recreational improvements for the project 
and indicated its intent to share in 50 percent of the 
cost of such improvements and perform operation 
and maintenance responsibility. A recreation Local 
Cooperation Agreement (LCA) was signed by the 
Assistant Secretary of the Army on April 15, 1992. 
Operations and results during fiscal year. 
Construction on Reach 1, Contract 2, of channel 
improvement on Wildcat and San Pablo Creeks was 
completed. Mitigation on Reach 1 was continued at 
a fiscal year contract cost of $14,921. 
Historical summary. Local interests withdrew 
support of project in 1979. Project responsibility was 
transferred from San Francisco District on April 1, 
1982. After 1982-1983 floods, local interests again 
indicated support of the project, and in October 
1983, project work was resumed by Sacramento 
District. A revised final environmental impact 
statement was filed March 28, 1986, and a General 
Design Memorandum was approved May 29, 1986. 
Flood Control Local Cooperation Agreement was 
executed June 20, 1986. Recreation Design 
Memorandum was approved on February 19, 1992, 
and the recreation LCA was signed on April 15, 
1992. Construction work under Contract No. 1 and 
Contract No. 2 for Reach No. 1 of Wildcat and San 
Pablo Creeks has been transferred to local sponsor 
for operation and maintenance. In March 1990, 
Reach 2 was declared infeasible and is now inactive. 
All costs have been deleted from project cost 
estimate. Overall project is about 80 percent 
complete. 
26. INSPECTION OF COMPLETED 
FLOOD CONTROL PROJECTS 
Approved regulations for operation and maintenance 
of flood control works, part 208, title 33, Code 
of Federal Regulations, provide for inspection of 
completed projects transferred to local interests for 
operation and maintenance to determine status of 
project and insure compliance with regulations. 
During fiscal year, inspections were made of: 
Completed units of Fairfield Vicinity Streams; 
completed units of Sacramento River and major and 
minor tributaries; completed units of Sacramento 
35-22

SACRAMENTO, CA, DISTRICT 
River, Chico Landing to Red Bluff; completed units 
of Sacramento River flood control project, Kings 
River Channel Improvement (Pine Flat Lake 
project), and Walnut Creek project; American River 
levees; Merced County Stream group; Middle Creek 
(Lake County); Chester, North Fork Feather River; 
levee and channel improvements on Chowchilla 
River (Buchanan project) and Fresno River (Hidden 
project); Duck Creek diversion, Green Valley Creek, 
Littlejohn Creek, Mormon Slough, Bear Creek, 
Kern River-California Aqueduct Intertie, and North 
Fork, Pit River at Alturas, all in California; Truckee 
River, CA and NV; completed units of lower San 
Joaquin River and tributaries, CA; completed units of 
Red Bank and Fancher Creeks including Big Dry 
Creek Dam and diversion, and Fancher Dam and 
Redbank detention basin, CA; Reese River, Battle 
Mountain, NV; Sevier River, Redmond and vicinity, 
Jordan River, Big Wash near Milford, and Kays 
Creek, all in Utah; various emergency flood control 
works under authority of sec. 208, Flood Control Act 
of June 30, 1948, and September 3, 1954; Public 
Law 99, June 28, 1955, and antecedent legislation; 
and sec. 14 of Flood Control Act of July 24, 1946. 
Maintenance inspections conducted indicate that 
existing agreements and regulations are being 
complied with on completed flood control works. 
Continuing effort is required to improve maintenance 
practices and active steps are being taken by 
responsible State and local agencies to achieve 
desired results. Local agencies were advised, as 
necessary, of measures required to maintain these 
projects in accordance with standards prescribed by 
regulations. Total cost of inspection for fiscal year of 
$1,734,789 included continuation of dam safety 
assurance program for Folsom Lake, CA ($544,684) 
and $76,393 for Big Dry Creek, CA. 
27. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to sec. 205, 
Public Law 858, 80th Congress, as amended 
(Preauthorization). 
Costs for preauthorization studies for fiscal year 
were $324,279. See Table 35-P for list of studies. 
Emergency flood control activities-repair, 
flood fighting, and rescue work (Public Law 99, 
84th Cong., and antecedent legislation). 
Federal cost for fiscal year was $370,557, all of 
which was for disaster preparedness. 
Emergency bank protection (sec. 14, 1946 
Flood Control Act, Public Law 526, 79th Cong.). 
Federal cost for fiscal year was $2,044 to complete 
bank protection on Duchesne River, UT. 
Snagging and clearing navigable streams and 
tributaries in interest of flood control (sec. 208, 
1954 Flood Control Act, Public Law 780, 83d 
Cong.). 
No snagging and clearing activities this fiscal year. 
Flood insurance activities (sec. 1301-1377, 
1968 Housing and Urban Development Act, 
Public Law 90-448 as amended). 
In coordination with flood control activities, two 
flood insurance studies were continued. Inter- 
Agency Agreements EMW-E-2226 and 2994, 
respectively, at a fiscal year cost of $1,284 under 
Federal Emergency Management Agency 
reimbursable order. 
28. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
In accordance with sec. 7, Flood Control Act of 
1944, summaries of monthly reservoir operations at 
Big Dry Creek, Boca, Camanche, Del Valle, Folsom, 
Friant (Millerton Lake), Indian Valley, Los Banos 
Detention, New Bullards Bar, New Don Pedro, New 
Exchequer (Lake McClure), New Melones, Oroville, 
Prosser, Shasta, and Stampede, CA; East Canyon, 
Echo, Lost Creek, Pineview, Red Fleet, Starvation, 
and Wanship, UT; and Blue Mesa, Lemon, Paonia, 
and Vallecito, CO, were prepared. Water control 
manual revisions were continued for Big Dry Creek, 
CA, and McPhee, CO, reservoirs. Work was 
continued on the Little Dell, UT, water control 
manual. Corps personnel provided advice as 
requested during flood control operations at all sec. 7 
reservoirs. Fiscal year cost was $944,144. Total cost 
to September 30, 1992, was $6,692,829. 
Multiple-Purpose Projects including Power 
29. NEW MELONES LAKE, CA 
Location. On Stanislaus River about three-quarters 
mile downstream from existing Melones Dam 
and about 35 miles northeast of city of Modesto. 
(See Geological Survey quadrangles of the area.). 
Existing project. Provides for construction of (a) 
an earth and rockfill dam about 625 feet high to 
create a reservoir with gross storage capacity of about 
2,400,000 acre-feet for flood control, irrigation, 
power, general recreation, fish and wildlife, and 
other purposes, and (b) a powerplant below the dam 
with an installed capacity of 300,000 kilowatts. Upon 
completion of construction of dam and powerplant 
by the Corps, the project became an integral part of 
Central Valley project and is being operated and 
maintained by the Secretary of the Interior pursuant 
to Federal reclamation laws, except that the flood 
control operation of the project shall be in 
accordance with rules and regulations prescribed by 
the Secretary of the Army. Maintenance of 
Stanislaus River channel from Goodwin Dam to San 
Joaquin River to a capacity of at least 8,000 cubic 
feet per second will also be Corps responsibility. 
35-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Approved estimated (October 1992) Federal cost is 
$400,500,000 (includes an allowance for estimated 
inflation through the construction period). For future 
non-Federal reimbursement, see Local cooperation 
paragraph. In addition, local interests expended 
$300,000 for levees along lower reaches of Stanislaus 
River. Existing project was adopted by 1962 Flood 
Control Act (H. Doc. 453, 87th Cong., 2d sess., 
contains latest published map). This act modified 
original authorization adopted by 1944 Flood 
Control Act. (H. Flood Control Committee Doc. 2, 
78th Cong., 2d sess., contains latest published map.) 
The 1944 Flood Control act established $8 million 
monetary limitation for partial accomplishment of 
project. Further monetary authorizations of $2.5 
million, $5 million, $13 million, $2 million, $17 
million, $18 million, $44 million, $83 million, $46 
million, $6 million, and $61 million were provided 
for this project by Public Laws 235 and 780, 83d 
Cong., and 85-500, 90-17, 90-483, 91-282, 
92-222, 93-251, 94-397, 95-104, and 95-189, 
making a total monetary authorization of 
$305,500,000 available for the basin plan comprising 
Lower San Joaquin River and tributaries, including 
Tuolumne and Stanislaus Rivers, CA. Since FY 
1979, appropriations have not been subject to the 
river basin monetary limitation. 
Local cooperation. Based on approved preliminary 
cost allocation studies (July 1965) local interests 
will be required to pay 35.2 percent of first cost and 
12.7 percent of annual operation and maintenance 
costs allocated to irrigation. In addition, 31.1 percent 
of first cost and 62.5 percent of annual cost would be 
allocated to power. Local interests must also 
maintain existing private levees along Stanislaus River 
from Goodwin Dam to San Joaquin River and 
prevent encroachment on channel and floodway 
between levees to preserve safe carrying capacity 
throughout the reach of at least 8,000 cubic feet per 
second. Recovery of costs allocated to irrigation and 
power will be the responsibility of the Bureau of 
Reclamation. Reimbursement of costs will be in 
accordance with Bureau policies and procedures for 
the Central Valley project. State of California 
officially adopted project by chapter 918 of statutes 
of 1963, and by chapter 1438 of those statutes 
authorized State Reclamation Board to furnish 
required assurances. The Board, by letter dated 
December 13, 1963, stated it would furnish required 
assurances when formally requested to do so. 
Assurances were requested by letter of December 30, 
1977. On October 2, 1979, the Board reaffirmed its 
intent to furnish the required assurances. On 
January 6, 1983, the Board provided formal 
assurances of local cooperation. 
Operations and results during fiscal year. New 
work: Engineering activities continued. Fiscal year 
costs for major items of work included: Continuation 
of land activities, $304,102; completion of administration 
building contract, $947,871; completion of 
Glory Hole recreation area force main contract, 
$594,777, and award of Parrotts Ferry Bridge 
modification contract on August 19, 1992. 
Maintenance: Maintenance and operation activities 
continued on Lower Stanislaus River. 
Historical summary. Construction was initiated 
in August 1966. Main dam contract which was 
awarded in March 1974 has been completed; dam 
dedication ceremonies were held July 14, 1979. 
Cultural resources preservation, water intake facilities, 
flood control and irrigation tailrace modification, 
reservoir area clearing, Tuttletown Phase I 
recreation area, Oakdale recreation, Glory Hole 
Phase I and Phase II recreation area, and operations 
access road contracts have all been completed. Glory 
Hole minimal recreation facilities contract has been 
completed. Boundary fencing, Lower Stanislaus 
Phase I and Phase II minimal recreation facilities, 
Lower Stanislaus Corporation Yard, and Lower 
Stanislaus Administration Building contracts have 
been completed. Tuttletown minimal recreation 
facilities, McHenry recreation area, Tuttletown 
wastewater treatment, Knights Ferry recreation 
area,Knights Ferry Covered Bridge, Glory Hole 
recreation area sanitary system, Two-Mile Bar 
recreation, administration building, and Glory Hole 
recreation area force main contracts have been 
completed. Overall project is nearing completion 
except for Lower Stanislaus River recreation 
facilities. Remaining recreation facilities were unscheduled 
pending development of cost sharing 
agreements and/or specific Congressional appropriation 
of funds. A Memorandum of Understanding 
between the Department of the Interior and the 
Department of the Army transferring the New 
Melones dam and reservoir from the Corps of 
Engineers to the Bureau of Reclamation was 
executed on November 20, 1979. Agreement 
provides that the Corps complete land acquisition 
actions and retain budgeting, design, and construction 
responsibility for reservoir clearing and recreation 
development; completion of cultural resources 
mitigation in project area was vested in the 
Department of the Interior. The California State 
Water Resources Control Board's Decision 1422 of 
April 1973 established conditions which impacted on 
the planned filling and operation of the project by the 
Department of the Interior. As a result, the 
Department of Interior brought suit against the State 
of California claiming State limitations on project 
operation were contrary to Congressional intent and 
authority. The case was heard before the U.S. 
District Court in Fresno, CA, and in early March 
1981, a Federal judge ruled that the Federal 
Government could fill the New Melones reservoir for 
purpose of generating electrical power, but not for 
agricultural or other purposes. Both the Government 
and the California State Resources Control Board 
appealed this decision to the 9th Circuit Court of 
Appeals in San Francisco, CA. 
On December 20, 1982, the Court upheld all 25 
requirements placed on the Federal Government by 
the State Water Resources Control Board. The 
35-24

SACRAMENTO, CA, DISTRICT 
decision reversed the lower court's decision to permit 
filling of the reservoir for generating electrical power. 
The Bureau of Reclamation subsequently filed for a 
permit from the State Water Resources Control 
Board to fill the reservoir. Permit was approved. The 
Bureau had originally started generating power on a 
limited basis on July 1, 1979; however, after the 
filling of the reservoir in spring of 1983, full power 
generating benefits have been attained. Project is 
about 99 percent complete. 
General Investigations 
30. SURVEYS 
See Table 35-Q. 
31. COLLECTION AND STUDY OF 
BASIC DATA 
Technical assistance was performed for other 
Federal agencies as well as non-Federal agencies in 
connection with Flood Plain Management Services 
Program at fiscal year costs of $256,000. No Flood 
Plain Information Studies were prepared after FY 
1980. 
Fiscal year costs for hydrologic studies were 
$6,000. 
32. RESEARCH AND DEVELOPMENT 
The Hydrologic Engineering Center was designated 
as a separate Field Operating Agency as of 
January 1, 1979, in accordance with OCE permanent 
orders 1-1, January 10, 1979, but Sacramento 
District is continuing to provide advisory and 
administrative support services to HEC as specified in 
local support agreement DACW05-79-A-0038 of 
March 1979. Fiscal year costs were $1,507,494, of 
which $18,128 was for collection and study of basic 
data (including flood plain management service), 
$1,457,925 was for research and development, and 
$31,441 was for automatic data processing. 
33. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
CACHE CREEK BASIN, CA 
Project is located on eastern slope of the Coast 
Range. Clear Lake unit is about 110 miles north of 
San Francisco and Settling unit is about 15 miles 
northwest of Sacramento. 
Plan of improvement consists of two project units: 
Upper basin at Clear Lake (selected plan)-widening 
and/or deepening 4.5 miles of existing 5 mile long 
Clear Lake outlet channel to a capacity of 8,000 
cubic feet per second, and nonstructural measures; 
and lower basin at the mouth of Cache Creek-enlarging 
existing perimeter levees of Cache Creek 
Settling Basin an average of 12 feet to provide 50 
years of sediment storage capacity and enlarging 
existing project levees from settling basin mouth 
upstream to County Road 102, reconstructing and 
enlarging existing Cobble weir, degrading the existing 
training levees and rebuilding them adjacent to the 
western perimeter levee to allow utilization of entire 
basin for sediment deposition, acquiring easements 
for 3,600 acres of existing settling basin and 
establishing a wildlife refuge; however, the refuge 
feature was reclassified to deferred category on 
April 11, 1988. The second project unit--Cache 
Creek Settling Basin-is reported under Improvement 
No. 6. 
General Design Memorandum for the Clear Lake 
Outlet Channel (Upper Basin) indicated that project 
was not economically feasible and preconstruction 
planning was terminated. Studies for possible 
solutions to Clear Lake flooding are being pursued in 
the Cache Creek Basin reconnaissance study. 
COYOTE CREEK, CA (KNOWN AS 
COYOTE AND BERRYESSA CREEKS) 
Project is located in the cities of San Jose and 
Milpitas immediately south of San Francisco Bay in 
Santa Clara County, CA. 
Plan of improvement on Coyote Creek consists of 
overflow channels and offset levees. Improvement 
on Berryessa Creek includes two sedimentation 
basins at the upstream end of the concrete lined 
trapezoidal channel and offset levees. Combined 
plan would provide flood protection from Coyote and 
Berryessa Creeks to cities of San Jose and Milpitas, 
which include large industrial complexes and some 
residential development. 
Separate General Design Memorandums were 
continued on Coyote and Berryessa Creeks. Draft of 
General Design Memorandum for Coyote was 
completed. Local interests have initiated construction, 
which is integral project work, under sec. 26 of 
the Water Resources Development Act of 1988. 
Estimated preconstruction planning cost is 
$4,000,000. 
TRUCKEE MEADOWS, NV 
Project is located in metropolitan area of Reno and 
Sparks in Washoe County, NV. 
Current plan of improvement consists of about 7 
miles of levees, 5 miles of floodwalls, 3 bridge 
replacements along Truckee River and includes 
limited channel excavation, a detention dam on 
Steamboat Creek at Huffaker Narrows, and 
backwater levees along Steamboat Creek, Boynton 
Slough, and the North Truckee Drain just north of 
the Interstate Highway 80 crossing. Plan also 
includes recreation facilities with bicycle and 
pedestrian paths, river overlooks, and picnic sites; 
mitigation measures (31 acres of riparian plantings to 
35-25

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
replace vegetation losses); and fish and wildlife 
features. Project will provide flood protection from 
Truckee River to cities of Reno and Sparks and 
Truckee Meadows urban areas. 
Project has been deferred and preconstruction 
planning has been terminated as project is 
economically infeasible. Coordination with local 
agencies and sponsors was continued and curation of 
cultural resource materials at the Nevada State 
Museum was initiated. Estimated preconstruction 
planning cost is $4,300,000. 
NAPA RIVER, CA 
Project is located in city and county of Napa, CA. 
Current plan of improvement consists of channel 
excavation, floodwalls, set-back levees, bypass 
channels, and related environmental mitigation 
measures. The improvements on Napa River would 
extend about 5.7 miles, from Trancas Street to 
Kennedy Park. Approximately 4,200 feet of Napa 
Creek, from its mouth to Jefferson Street, would also 
be improved. 
Project will provide 100-year level of flood 
protection from Napa River and Napa Creek to city 
of Napa. 
A hazard and toxic waste investigation is a new 
requirement and is being included in the current 
General Design Memorandum. Estimated preconstruction 
planning cost is $9,200,000. 
34. OTHER WORK UNDER 
SPECIAL AUTHORITY 
AQUATIC PLANT CONTROL 
Under the Aquatic Plant Control Program (River 
and Harbor Act of 1958, sec. 104, Public Law 500, 
85th Congress) a reconnaissance report regarding the 
hydrilla problem in Sacramento District was initiated 
in October 1989. On December 16, 1991, a policy 
decision regarding benefit evaluations was received. 
Decision was that benefits other than recreation must 
be the primary benefits for aquatic plant control 
programs. Previous recommendations for Federal 
involvement in these programs were based primarily 
on recreation benefits. A request for necessary 
additional funds was denied and reconnaissance 
report was terminated in FY 1992 at a fiscal year cost 
of $753. (For detailed description of study, see 
Annual Report for FY 1991). 
YOLO BASIN WETLANDS, SACRAMENTO 
RIVER, CA (Section 1135) Project Modification 
for Improvement of Environment 
The Yolo Basin Wetlands area is primarily located 
within the boundaries of the Yolo Bypass, an 
operative feature of the Sacramento River Flood 
Control Project. Yolo Bypass extends 43 miles from 
Fremont Weir on the Sacramento River, south to the 
town of Rio Vista where it rejoins the river. 
Project will include restoration of wetlands, and 
contribute to a larger program now in the planning 
stage, proposed by an interagency group of state and 
local governments and organizations. Proposed work 
will include physical improvements to help create a 
mixture of native marsh, permanent and seasonal 
wetlands, and riparian forest through modification of 
existing drainage canals or construction of small 
dikes and weirs to redirect available water sources to 
proposed wetland areas. Also to be included is 
preparation of a flood plain hydraulic management 
model to assess hydraulic impacts of furture wetland 
projects proposed in the Yolo Bypass. Estimated 
project cost is $6,820,000. Project was authorized by 
the Water Resources Development Act (WRDA) of 
1986, Public Law 99-662, sec. 1135(b), as amended 
by sec. 304 of WRDA 1990. 
The California State Department of Fish and 
Game is the project sponsor for 3,480 acres located 
within the Yolo Bypass. 
A Project Modification Report and an Environmental 
Assessment/Initial Study was completed in 
April 1992. Three existing sites have been identified 
for possible wetlands restoration: Putah Creek Sink 
(3,000 acres), Yolo Causeway (480 acres) and 
Willow Slough Bypass (345 acres). Willow Slough 
Bypass site was later withdrawn due to difficulty in 
acquiring lands. 
Fiscal year costs were $303,598. 
35-26

SACRAMENTO, CA, DISTRICT 
TABLE 35-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
1. Sacramento River New Work 
CA (Federal Approp. 
Funds) Cost 
Maint. 
Approp. 
Cost 
(Contrib. Funds, Maint. 
Other) Contrib. 
Cost 
2. Sacramento River New Work 
Deep Water Ship Approp. 
Channel, CA Cost 
(Required Contrib. New Work 
Funds) Contrib. 
Cost 
3. San Francisco Bay New Work 
to Stockton, CA Approp. 
(John F. Baldwin Cost 
and Stockton Ship 
Channels) 
4. San Joaquin New Work 
River, CA Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Buchanan Dam- New Work 
H.V. Eastman Lake, Approp. 
Chowchilla River, Cost 
CA (Federal Maint. 
Funds) Approp. 
Cost 
(Contrib. Funds, New Work 
Other) Contrib. 
Cost 
- - - - $40,331,192 1 
- - - - 40,331,192 1 
$150,700 $851,029 $964,200 526,400 45,637,960 2 
188,435 435,174 1,353,399 443,966 45,510,023 s 
- - - - 85,000 4 
1,400,000 
1,520,808 
750,000 
600,803 
509,000 
-6,476 
700,000 
631,142 
3,269,000 
3,799,847 
1,500,000 
1,266,274 
119,443 
-15,000 
39,815 
7,631,474 5 
7,524,433 5 
2,935,000 
2,538,034 
1,676,000 2,901,000 1,635,000 2,136,000 61,488,000 6 
2,635,686 1,645,007 2,311,808 2,770,443 61,272,911 7 
48,500 
54,591 
- - - 5,833,117 8 
- - - 5,833,117 8 
109,661 450,000 1,096,000 14,522,137 s 
105,669 442,440 1,098,445 14,502,816 s 
- - - - 27,369,597 
- - - - 27,369,597 
1,224,800 1,031,893 938,700 1,196,000 13,574,393 
1,238,494 988,885 1,073,433 1,224,513 13,556,387 
- - - - 111,187 10 
- - - - 111,187 10 
6. Cache Creek 
Settling Basin, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
7. Calaveras River 
and Littlejohn 
Creek and Tributaries 
including 
New Hogan Lake 
& Farmington Dam, 
CA (Federal Funds) 
(Contrib. Funds, 
Other) 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
486,000 438,000 3,900,000 
294,407 493,798 426,525 
- - 400,000 
- - 40,335 
- - 400,000 
5,379,000 
7,320,728 
415,000 
622,305 
353,000 
557,361 
9,946,000 
8,082,854 
815,000 
662,640 
753,000 11 
557,361 12 
- - - - 23,723,144 13 
- - - - 23,723,144 13 
1,779,600 1,542,127 1,576,315 1,613,000 22,908,711 14 
1,715,926 1,409,970 1,824,621 1,632,124 22,867,079 14 
- - - - 1,398,251 15 16 17 
- - - 1,398,251 15 16 17 
35-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
-80,0 307000 17000 
8. Corte Madera 
Creek, CA 
(Federal Funds) 
Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
9. Fairfield Vicinity 
Streams, CA 
(Federal Funds) 
Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
10. Guadalupe River, 
CA 
(Required Contrib. 
Funds) 
11. Hidden Dam - 
Hensley Lake, 
Fresno River, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
12. Isabella Lake, Kern 
River, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
13. Kaweah and Tule 
Rivers including 
Terminus Dam and 
Success Lake, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
14. Little Dell 
Lake, UT 
(Federal Funds) 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work: 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
-800,000 
414,832 
7,888 
2,939,000 
4,260,133 
9,000 
13,115 
1,886,000 
961,970 
307,000 170,000 
230,864 217,142 
- - 
3,510 10,814 
- 24,700 
2,135,000 
2,556,001 
22,000 
15,211 
525,000 
1,354,036 
2,447,000 
2,001,354 
18,605 
463,000 
576,362 
- 12,483,725 18 
82,507 12,434,030 18 
- 186,095 19 
- 185,831 19 
786,921 20 
786,921 20 
771,000 
871,404 
475,370 
99,416 
85,000 
119,004 
661,000 1,081,000 1,200,000 1,798,000 
717,234 877,152 1,138,152 1,933,535 
- - - 430,000 
14,833,000 
14,382,942 
533,370 
155,965 
3,779,000 21 
3,619,810 22 
6,129,000 
5,939,819 
430,000 
- - - - 30,555,426 
- - - - 30,555,426 
1,126,100 1,130,718 1,035,700 1,306,000 14,477,818 
1,096,138 1,085,236 1,124,821 1,318,900 14,451,617 
- - - - 165,112 23 
- - - - 165,112 23 
2,145,000 
2,027,598 
105,000 
109,422 
2,125,600 
2,053,516 
51,000 
107,190 
1,962,566 
1,874,165 
60,000 
74,314 
2,266,701 
2,113,057 
64,000 
62,501 
2,216,900 
2,548,784 
40,000 
39,911 
2,252,500 
2,452,863 
26,000 
27,518 
- 24,450,537 24 
- 24,450,537 24 
673,000 36,130,062 25 26 
683,359 36,113,974 25 26 
2,500 745,500 27 
2,575 744,427 28 
- 34,997,230 * 
- 34,997,230 29 
2,583,853 34,546,879 3 
2,629,169 34,478,781 3 
- 628,420 31 32 34 
3,135 625,598 31 33 35 
7,025,000 9,770,000 2,985,000 5,884,000 34,058,900 
4,213,530 8,566,097 4,731,928 8,121,629 33,490,515 
35-28

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
15. Lower San Joaquin 
River, CA 
16. Martis Creek Lake, 
Martis Creek, NV, 
and CA 
17. Merced County 
Streams, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
18. Merced County 
Stream Group, CA 
19. Pajaro River Basin, 
CA (Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
20. Pine Flat Lake and 
Kings River, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
21. Redbank and 
Fancher Creeks, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
2,840,000 
1,762,627 
50,465 
25,546 
-49,000 
450,299 
6,100,000 2,050,000 4,400,000 16,050,000 
4,138,434 4,027,430 5,009,731 15,434,462 
- - - 4,320,465 " 
24,528 14,724 1,259 4,300,147 s7 
- - -13,000 4,036,000 
249,048 16,417 3,335 4,036,000 
- - - - 8,504,989 " 
- - - - 8,504,989 M 
266,100 306,033 326,400 291,500 5,443,383 
273,026 293,537 325,688 313,889 5,428,781 
3,602,000 
333,016 
2,582,500 
615,811 
117,000 
122,833 
2,713,000 
237,189 
-469,000 1,612,000 2,100,000 
461,860 2,996,121 3,034,139 
- - 430,000 
- - 291,000 
- 270,000 707,125 
285,153 582,769 969,395 
13,945,000 
13,737,581 
430,000 
291,000 
3,559,625 39 
2,453,127 39 
- - - 2,751,259 40 
- - - 2,751,259 40 
100,534 134,800 117,000 2,129,840 
98,652 123,702 135,193 2,120,015 
- 1,122,000 
3,709,447 1,184,685 
127,268 325,214 
127,268 325,214 6,007 
5,663 
- 8,206,968 41 
18,798 8,184,698 41 
- 610,000 
989 562,363 
- 37,250 42 
- 31,553 42 
- - - - 43,356,265 44 
- - - - 43,356,265 44 
1,387,000 1,393,797 2,324,800 1,916,000 28,679,382 45 
1,450,874 1,337,111 2,398,853 1,943,666 28,632,928 45 
- - - - 110,000 46 
- - - - 110,000 46 
4,053,000 
1,101,483 
202,500 
124,396 
10,270,000 
12,714,707 
1,340,000 
1,121,482 
11,500,000 
10,746,289 
785,000 
1,060,100 
10,471,000 
9,844,812 
425,000 
449,417 
38,928,065 47 
36,598,574 47 
3,012,500 
2,893,468 
35-29

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
(Contrib. Funds, 
Other) 
22. Russian River Basin, 
CA, Coyote Valley 
Dam (Lake 
Mendocino) and 
Channel Improvements 
(Federal 
Funds) 
(Contrib. Funds, 
Other) 
Dry Creek (Warm 
Springs) Lake 
and Channel 
Improvements, CA 
(Federal Funds) 
(Contrib. Funds, 
Other) 
23. Sacramento River 
and Tributaries, CA 
from Collinsville to 
Shasta Dam 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
24. Walnut Creek, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
25. Wildcat and San 
Pablo Creeks, CA 
(Federal Funds) 
(Required Contrib. 
Funds) 
(Contrib. Funds, 
Other) 
28. Lower San 
Joaquin River 
and Tributaries, 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
- 620,000 - 135,000 755,000 4 
- 95,000 392,298 156,516 643,814 4 
- - - - 14,435,869 49 
- - - - 14,435,869 49 
1,646,600 1,566,640 1,693,000 2,175,000 35,015,424 50 51 
1,614,367 1,540,757 1,879,266 2,158,612 34,969,261 5so s 
2,000 
430 
1,900,000 
2,701,746 
2,244,700 
2,254,939 
20,000 
31,714 
4,450,000 
5,634,386 
1,242,100 
1,183,415 
1,210,000 
1,921,720 
15,000 
17,604 
4,400,000 
2,544,540 
260,000 
238,792 
1,958,714 
1,513,579 
1,621,000 
2,515,019 
-190,000 
150,107 
465,000 
528,470 
2,500,000 
2,039,696 
1,500 
3,720 
5,035,000 3,111,000 
3,732,002 5,226,418 
2,279,643 2,701,800 
1,959,296 3,013,313 
- 10,174 
1,555 20,658 
3,550,000 
2,294,494 
1,217,694 
1,178,635 
277,500 
456,274 
9,000 
7,439 
8,324,000 
8,456,104 
410,000 
529,722 
2,285,886 
2,983,724 
865,000 
2,072,816 
74,000 
96,745 
516,000 
550,355 
1,101,000 
2,677,698 
1,217,300 
1,331,790 
275,800 
622,674 
31,500 
3,049 
1,936,000 
3,561,848 
422,600 
379,198 
1,477,100 
1,703,646 
-609,000 
1,253,364 
235,504 
68,112 
16,951 
1,500 12,386 260,797 52 
1,968 12,444 260,744 sa 
5,217,000 
3,291,802 
2,579,000 
2,705,031 
12,400 
1,234,000 
1,750,674 
1,402,000 
1,452,100 
-29,434 
156,109 
39,434 
62,949 
300,000 
839,262 
25,000 
52,958 
259,457 
31,614 
327,982,645 54 
325,041,281 54 
21,275,143 ss 
21,221,598 58 
230,574 57 
228,732 58 
119,769,008 so so 
119,322,388 s so80 
21,137,928 81 
21,098,407 e1 
23,165,404 
22,520,071 
2,886,296 82 63 
2,879,761 82 
63 84 
70,042,430 85 
69,999,834 88 
5,612,681 87 
5,546,827 88 
14,854,344 89 
14,552,541 89 
1,067,000 12,861,000 
893,311 12,632,976 
- 859,662 
43,293 570,088 
- 1,666,000 70 
- 1,582,383 71 
- 5,223,000 3,651,000 370,024,996 72 73 
1,352,753 5,400,459 2,669,051 366,373,026 73 
35-30

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
CA including Maint. 
Tuolumne and Approp. 602,400 689,716 692,000 798,000 6,922,316 
Stanislaus Rivers, Cost 600,157 579,537 808,000 827,141 6,902,493 
CA, New Melones 
Lake, CA 
(Federal Funds) 
(Contrib. Funds, New Work 
Other) Contrib. - - - - 80,000 74 
Cost - - - 67,415 80,000 74 
1. Includes the following amounts for new work: 
Regular Funds: Previous project, $185,198; existing 
project, $585,436 for shallow-draft and $39,560,558 
for deep-draft. 
2. Includes the following funds for maintenance: 
Regular Funds: Previous project, $553,720; existing 
project, $16,141,432 for shallow-draft and 
$28,872,808 for deep-draft; and deferred maintenance 
funds, $70,000 for shallow-draft. 
3. Includes the following costs for maintenance: 
Regular Funds: Previous project, $552,720; existing 
project, $16,138,185 for shallow-draft and 
$28,748,118 for deep-draft; and deferred maintenance 
funds, $70,000 for shallow-draft. 
4. Includes $85,000 contributed funds, other, from 
Sacramento-Yolo Port District for clearing and grubbing 
on dredged material deposit areas to be used on ship 
channel maintenance dredging work. 
5. Includes unobligated carryover for continuation 
of planning and engineering (CP&E) funds as of 
September 30, 1985 ($33,474) for Sacramento River 
Deep Water Ship Channel to be included in project cost 
(for cost sharing) per TWX of September 9, 1985. 
6. Includes $27,999,800 funds for Sacramento 
District and $33,488,200 for San Francisco District. 
7. Includes $27,821,192 costs for Sacramento 
District and $33,451,719 for San Francisco District. 
8. Includes $1,158,348 public work funds, of which 
$207,198 was for work done along 30-foot channel in 
Suisun Bay Channel; excludes $19,000 expended for 
engineering for inactive portion of 1950 modification. 
In addition, $1,342,500 was expended from required 
contributed funds; 
9. In addition, $1,250 was expended from required 
contributed funds for maintenance. 
10. Contributed funds, other, from State of 
California for design and construction of downstream 
channel improvements on Ash and Berendo Sloughs 
below Buchanan Dam. 
11. Includes $753,000 contributed funds, other, 
from State of California for relocation activities 
including demolition or salvage of various pipes and 
facilities, construction of ramps, turnouts, pipe gates 
and bank protection at Cache Creek Settling Basin. 
12. Includes $557,361 contributed funds, other, 
costs for relocation activities for State of California. 
13. Includes Code 710 funds and costs for recreation 
facilities at New Hogan Lake: total to date $897,742. 
14. Includes $99,000 special recreation use fees and 
costs at New Hogan Lake, and $491,000 maintenance 
and operation of dam funds and costs (96X5125) at 
New Hogan Lake beginning in FY 1988. 
15. For miscellaneous construction under local 
cooperation requirements, primarily for Bear Creek, 
San Joaquin County; includes $10,056 as related to 
Duck and Littlejohn Creeks channel improvements as 
part of Farmington Dam project unit. 
16. Includes $393,195 contributed funds, other, 
from California Department of Boating and Waterways 
for design and construction of boat launching and 
related facilities, and $30,000 for design and 
construction of a boarding float at North Shore 
recreation area at New Hogan Lake. 
17. Includes $104,000 contributed funds, other, and 
costs from Calaveras County Water District for New 
Hogan hydropower studies. 
18. Includes $6,999,725 San Francisco District 
construction funds and costs for Corte Madera Creek. 
19. $8,695 contributed funds transferred to 
Sacramento District in FY 1983. Includes $97,400 San 
Francisco District required contributed funds and costs. 
20. Contributed funds, other, and costs, from Marin 
County including $536,921 for miscellaneous bridge 
and road relocations and $250,000 for additional 
expenses for disposal sites at Corte Madera Creek. 
21. Includes $3,643,000 contributed funds, other, 
from the State of California for relocations (automotive 
type bridges) at Laurel Creek Diversion near Fairfield, 
$23,000 from City of Fairfield for Phase III contract for 
channel development on Laurel Creek, and $113,000 
from City of Suisun for Phase IIA contract for widening 
of Railroad Avenue. 
22. Includes $2,880,231 contributed funds, other, 
costs for relocations at Laurel Creek Diversion, $18,454 
contributed funds, other costs for Phase III contract, 
and $112,687 for Phase IIA contract. 
23. Contributed funds, other from the State of 
California for miscellaneous design and construction at 
Hidden Dam. 
24. Includes $2,199,085 Code 710 funds and costs 
for recreation facilities at Isabella Lake and $224,000 
Code 713 funds and costs for improvement at Tillie 
Creek and Live Oak campgrounds. 
35-31

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
25. Includes $407,640 special recreation use fees 
and costs at Isabella Lake. 
26. Includes $131,900 maintenance and operation 
of dam funds and costs (96X5125) at Isabella Lake 
beginning in FY 1985. 
27. Includes $438,000 contributed funds, other, 
from California Department of Boating and Waterways 
for design and construction of boat launching and 
related facilities at Old Isabella Road and Isabella 
Peninsula and $330,000 for Isabella Dam hydropower 
studies. 
28. Includes $438,000 contributed funds, other, 
costs for boat launching and related facilities at Old 
Isabella Road and Isabella Peninsula, and $306,516 
costs for Isabella Dam hydropower studies. 
29. Includes Code 710 funds and costs for recreation 
facilities: Success Lake: Total to date $747,048. 
Terminus Dam: Total to date: $704,000. 
30. Includes $165,000 special recreation use fees 
and costs at Success Lake. 
31. Contributed funds, other, from State of 
California Department of Boating and Waterways and 
cost for acquisition of a boarding float at Success Lake, 
$30,000 and at Terminus Dam, $12,420. 
32. Includes $418,000 contributed funds, other, 
from the Kaweah River Power Authority, Visalia, 
California, for Terminus Dam hydropower studies. 
33. Includes $416,844 contributed funds, other, 
costs for Terminus Dam hydropower studies. 
34. Includes $168,000 contributed funds, other, 
from DITT, Inc., Paris, France, for hydropower studies 
at Success Lake. 
35. Includes $166,334 contributed funds, other, 
costs for Success Lake hydropower studies. 
36. Includes $4,320,465 contributed funds, other 
from the Metropolitan Water District of Salt Lake City 
for relocation of State Highway 65 at Little Dell Lake. 
37. Includes $4,300,147 contributed funds, other, 
costs for relocation of State Highway 65 at Little Dell 
Lake. 
38. Includes $1,200 initiation of plans and 
specifications for Code 710 recreation facilities, for FY 
1978. construction of recreation facilities at Martis 
Creek Lake under Code 720 was determined to be 
infeasible. 
39. Includes contributed finds, other, for lands, 
easements and rights-of-way for Castle Dam from State 
of California. 
40. In addition, $66,532 expended for new work 
from contributed funds, other, miscellaneous 
construction under local cooperation requirements as 
related to acquisition of right-of-way and utility 
alterations for Merced County Stream Group. 
41. Include $1,949,968 San Francisco construction 
funds and costs and $260,000 Sacramento general 
investigation funds and costs for Pajaro River. 
42. Includes contributed funds, other, from Santa 
Clara Valley Water District for bridge relocation at 
Pajaro River. 
43. Includes Code 710 funds and costs for recreation 
facilities at Pine Flat Lake: Total to date: $1,595,100. 
44. Includes Public Work Acceleration, Executive 
(PL 87-658) (Transfer to Corps of Engineers, Civil) 
1963 funds and costs ($239,235) for recreation facilities 
and $19,600 Code 713 funds and costs for Pine Flat fish 
barrier. 
45. Includes $158,300 special recreation fees and 
costs at Pine Flat Lake and $364,185 maintenance and 
operation of dam funds and costs at Pine Flat Dam. 
46. Miscellaneous construction and engineering and 
design services (non-project) accomplished at expense 
of State of California under local cooperation 
requirements in connection with acquisition of 
rights-of-way and utility alterations at Pine Flat Lake. 
47. Includes unobligated carryover for continuation 
of planning and engineering (CP&E) funds as of 
September 30, 1985 ($29,065) and FY 1986 allocation 
for Redbank and Fancher Creeks to be included in 
project cost (for cost sharing) per TWX of September 9, 
1985. 
48. Includes contributed funds, other, from Fresno 
Metropolitan Flood Control District for road relocation 
(Nees Avenue) at Fancher Dam. 
49. Excludes $5,598,000 contributed funds; 
$400,000 for recreation facilities at completed projects 
funded under Public Works Acceleration Program; and 
$1,628,411 for recreation facilities at completed 
projects funded under Code 711 at Coyote Valley Dam, 
Lake Mendocino. 
50. Includes $94,459 special recreation use fees and 
costs (FY 1982-1983), but excludes prior special 
recreation fees and cost for Coyote Valley Dam, Lake 
Mendocino. 
51. Includes $1,289,680 maintenance and operation 
of dam funds and costs at Coyote Valley Dam, Lake 
Mendocino for FY 1985 through FY 1992. 
52. Includes $248,411 contributed funds, other 
from City of Ukiah for Coyote Valley Dam, Lake 
Mendocino, hydropower studies; and $12,386 from 
California Department of Boating and Waterways for 
launching facility at Lake Mendocino. 
53. Includes $248,358 contributed funds, other, 
costs for Coyote Valley Dam, Lake Mendocino, 
hydropower studies. 
54. Includes $253,421,793 San Francisco construction 
funds and costs through August 1983 for Dry 
Creek, Warm Springs Dam. 
55. Includes $964,114 San Francisco maintenance 
funds and costs through April 1982 for Dry Creek, 
Warm Springs Dam. 
56. Includes $75,400 maintenance and operation of 
dam funds and costs at Dry Creek, Warm Springs Dam. 
57. Includes $208,074 contributed funds, other, 
from Sonoma County for Dry Creek, Warm Springs, 
hydropower studies; and $22,500 from City of Ukiah 
for hatchery pump design at Lake Mendocino. 
58. Includes $195,674 contributed funds, other, 
costs for Dry Creek, Warm Springs hydropower studies; 
and $20,658 cost for hatchery pump design. 
59. Excludes $614,608 for Table Mountain (Iron 
Canyon) project, deauthorized August 5, 1977, and 
$531,000 for Sacramento River and Major and Minor 
Tributaries portions which are considered inactive and 
deferred. 
35-32

SACRAMENTO, CA, DISTRICT 
TABLE 35-A (Cont'd) COST AND FINANCIAL STATEMENT 
60. Includes Code 710 funds and cost for recreation 
facilities at Black Butte lake: Total to date $1,000,162. 
61. Includes $104,100 special recreation use fees 
and costs at Black Butte Lake. 
62. Miscellaneous construction and engineering and 
design services (non-project) accomplished at expense 
of State of California under local cooperation 
requirements in connection with acquisition of 
rights-of-way and utility alterations (primarily for 
Sacramento River and Major and Minor Tributaries 
project). Includes State Highway Commission payment, 
$789,008, for use of excess excavation from Chico and 
Mud Creeks and Sandy Gulch (Sacramento River and 
Major and Minor Tributaries) for freeway embankment 
through city of Chico. 
63. Includes $41,984 contributed funds, other, from 
State of California for required modification of existing 
private facilities and salmon rearing habitat, Sacramento 
River, Chico Landing to Red Bluff; $15,977 contributed 
funds, other, from State of California Department of 
Boating and Waterways for replacing a boarding float at 
Orland Buttes boat launching ramp at Black Butte Lake; 
$350,500 contributed funds, other, from the City of 
Santa Clara for hydropower studies at Black Butte Lake; 
and $59,334 contributed funds, other from State of 
California for relocations. 
64. Includes $343,965 contributed funds, other, 
costs for Black Butte hydropower studies; and $59,334 
costs for relocations. 
65. Includes $8,849,825 San Francisco construction 
funds for Walnut Creek. 
66. Includes $9,049,609 San Francisco construction 
costs for Walnut Creek. 
67. Includes $450,268 San Francisco required funds 
for Walnut Creek. 
68. Includes $525,846 San Francisco required costs 
for Walnut Creek. 
69. Includes $400,348 San Francisco contributed 
funds, other, and contributed funds costs for Walnut 
Creek. 
70. Includes $1,666,000 contributed funds, other, 
from Contra Costa Flood Control and Water 
Conservation District for replacement of sewerline in 
Richmond for Wildcat and San Pablo Creeks project. 
71. Include $1,582,383 contributed funds, other, 
costs for replacement of sewerline in Richmond for 
Wildcat and San Pablo Creeks project. 
72. Excludes funds applicable to other units of this 
basin authorization (Lower San Joaquin River and 
Tributaries, and Tuolomne River Basin, California). 
(See Table 35-E). 
73. Includes $110,000 utilized for preparation of 
1957 Economic Feasibility Report and of Revised 
Feasibility Report (FY 1960, 1961, and 1962) 
applicable to 1962 reauthorization of project. 
74. Includes $80,000 contributed funds, other, and 
costs, from the Bureau of Reclamation for visitors center 
at Mark Twain area, New Melones Lake. 
35-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-A COST AND FINANCIAL STATEMENT 
PRECONSTRUCTION ENGINEERING AND DESIGN 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep 30, 1992 1 2 
American and New Work 
Sacramento Rivers, Approp. - - - $1,600,000 $1,600,000 
CA Cost - - - 1,177,627 1,177,627 
Cache Creek Basin, New Work 
CA Approp. 293,000 269,000 - -13,000 2,067,336 
Cost 356,775 309,365 11,842 -7,588 2,063,790 
Caliente Creek, CA New Work 
Approp. 60,000 - - - 60,000 
Cost 58,303 1,688 - 9 60,000 
Coyote and Berryessa New Work 
Creeks, CA Approp. 714,000 535,000 1,160,000 885,000 3,394,000 
Cost 357,290 695,054 1,066,409 835,620 3,018,658 
Napa River, CA New Work 
Approp. 750,000 1,313,000 560,000 2,000,000 4,623,000 3 
Cost 455,470 1,399,940 532,776 1,933,885 4,322,071 a 
Truckee Meadows, New Work 
NV Approp. 1,528,000 1,356,000 786,000 -307,000 3,803,000 
Cost 1,105,270 1,600,783 818,804 67,736 3,772,970 
Upper Jordan New Work 
River, CA Approp. - 200,000 525,000 375,000 1,100,000 
Cost - 177,236 352,887 346,138 876,262 
1. Beginning in FY 1982, Advance Engineering 
and Design (Preconstruction, Engineering and Design) 
programs are funded under General Investigations 
Appropriations. 
2. Includes FY 1985 unobligated carryover and 
FY 1986 allocation for CP&E funds and all AE&D 
funds to be included in project cost (for cost sharing) 
per TWX of September 9, 1985. 
3. Excludes $2,639,955 funds and costs for a 
previous flood control project on Napa River. (See 
Table 35-E.) 
35-34

TABLE 35-B 
SACRAMENTO, CA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
Mar. 3, 1899 
July 25, 1912 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 30, 1935 
Aug. 26, 1937 
July 24, 1946 
Nov. 17, 1987 
8. 
Oct. 23, 1962 
Nov. 7, 1966 
Nov. 17, 1986 
22. 
May 17, 1950 
Feb. 10, 1956 
SACRAMENTO RIVER, CA 
A depth of 7 feet below Sacramento. H. Doc. 186, 55th Cong., 
works. 2d sess., and 48, 55th 
Cong., 3d sess. (Annual 
Report 1898, p. 2844 
and 1899, p. 3171). 
For work above Sacramento. H. Doc. 76, 62d Cong., 
1st sess. 1 
The 10-foot channel up to Sacramento. H. Doc. 123, 69th Cong., 
1st sess. 
A depth of 6 feet between Sacramento and Colusa Rivers and Harbors 
and 5 feet between Colusa and Chico Landing Committee Doc. 35, 
at a cost of $390,000 provided flow of rivers 73d Cong., 2d sess. 
is increased to minimum flow of 5,000 cubic 
feet per second after Shasta Reservoir is built. 
Authority for a special direct participation of Rivers and Harbors 
Federal Government of $12 million in cost Committee Doc. 35, 
of Shasta Reservoir. 73d Cong., 2d sess. 
Transfer of authority for expenditure of above $12 
million from Secretary of War to Secretary of the 
Interior. 
Modified existing navigation project for Sacramento S. Doc. 142, 79th Cong., 
River, CA, to provide for construction of a ship 2d sess. 
channel 30 feet deep and 200 to 300 feet wide 
from deep water in Suisun Bay to Washington Lake, 
including such works as may be necessary to compensate 
for or alleviate any detrimental salinity 
conditions resulting from ship channel; a triangular 
basin of equal depth, 2,400 by 2,000 by 3,400 feet 
at Washington Lake; and connecting channel 13 feet 
deep and 120 feet wide, with lock and drawbridge, 
thence to Sacramento River. 
Deauthorization of shallow-draft channel, Colusa Sec. 1002, 1986 WRDA 
to Red Bluff, feature of project for navigation, 
Sacramento River, California. 
CORTE MADERA CREEK, CA 
Levees and channel improvements, lower 11 miles H. Doc. 545, 87th Cong., 
of Corte Madera Creek and tributaries, as 2d sess. 
modified by Chief of Engineers. 
Local cooperation requirements modified to Sec. 204, 1966 Flood 
provide 1.5 percent cash contribution toward Control Act. 
cost of Ross Valley unit. 
Modify existing project to direct construction of Unit Sec. 823, 1986 WRDA 
4 from Lagunitas Road Bridge to Sir Francis Drake 
Boulevard, and to include construction of floodproofing 
measures in vicinity of Lagunitas Road 
Bridge to insure proper functioning of completed 
portions of authorized project. Further modify 
project to eliminate any channel modifications 
upstream of Sir Francis Drake Boulevard. 
RUSSIAN RIVER BASIN, CA 
Coyote Valley Dam (Lake Mendocino): Channel H. Doc. 585, 81st Cong., 
improvements on lower 98 miles of Russian River 2d sess. 
and lower reaches of tributaries. 
Increased appropriation authorization for initial PL 404, 84th Cong., 
stage of project development. 2d sess. 
35-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-B (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 23, 1962 
Mar. 7, 1974 
Dry Creek (Warm Springs) Lake; Channel 
Improvements on Dry Creek below dam. 
Dry Creek (Warm Springs) Lake and channel; 
compensate for fish losses on the Russian River 
which may be attributed to the operation of the 
Coyote Dam component of the project through 
measures such as possible expansion of the 
capacity of the fish hatchery at the Warm 
Springs Dam component of the project. 
H. Doc. 547, 87th Cong., 
2d sess. 
Sec. 95, 1974 WRDA 
23. 
Dec. 22, 1944 
May 17, 1950 
July 3, 1958 
July 3, 1958 
July 14, 1960 
May 12, 1967 
Mar. 7, 1974 
June 19, 1975 
SACRAMENTO RIVER AND TRIBUTARIES, 
CA, FROM COLLINSVILLE TO SHASTA 
DAM 
Modify Sacramento River Flood Control Project H. Doc. 649, 78th Cong., 
to provide for extensions in levees and other 2d sess. 2 
structures along Sacramento River and major 
and minor tributaries; construct Black Butte 
Dam and Reservoir; construct low-level Table 
Mountain Dam and Reservoir with power 
facilities; and provision of monetary authorization 
of $15 million for initiation of modification. 
Improvements for protection of Upper Butte Basin H. Doc. 367, 81st Cong., 
(included full monetary authorization). 1st sess. 2 
Extend existing Sacramento River Flood Control H. Doc. 272, 84th Cong., 
Project to Keswick Dam for purposes of zoning 2d sess. 2 
area below dam and modification of project by 
construction of bank protection and incidental 
channel improvements between Chico Landing 
and Red Bluff (included full monetary authorization). 
Additional authorization of $17 million for comprehensive 
plan approved in act of December 22, 
1944. 
Further modification of Sacramento River Flood S. Doc. 103, 80th Cong., 
Control Project by construction of initial 10- 
year phase of bank erosion control works and 
setback levees on Sacramento River and 
authorization of $14,240,000 for prosecution 
of modification. 
Additional authorization of $7 million for bank PL 90-17 
protection approved in act of July 14, 1960. 
Initiation of construction of second phase of bank PL 93-251 
erosion control works and setback levees on 
Sacramento River as approved in act of July 14, 
1960, and additional authorization of $16 
million for such purpose. 3 
Deauthorization of Table Mountain Dam and H. Doc. 94-192, 94th 
Reservoir. 4 Cong., 1st sess. 
1. Contains latest published map of section above 
Sacramento. For map of section below Sacramento, see 
H. Doc. 1123, 60th Cong., 2d sess. and S. Doc. 142, 
79th Cong., 2d sess. 
2. Contains latest published map. 
3. Total monetary authorization available, exclusive 
of preauthorization studies from general investigations 
appropriations, amounts to $72,740,000. 
4. The 90-day Congressional project review 
period, required by sec. 12, PL 93-251, as amended by 
sec. 157, PL 94-587, ended August 5, 1977, and 
resulted in deauthorization of project unit. 
35-36

SACRAMENTO, CA, DISTRICT 
TABLE 35-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Feather River, CA 1951 - $ 5,7521 2 
Middle River and Connecting 
Channels, CA Completed 1974 $ 8,354 93,4944 
Mokelumne River, CA Completed 1974 8,500 189,152 
Navajo Reservoir, NM Completed - 2,1325 s6 
Old River, CA Completed 1970 23,185 7 631,128 
Stockton and Mormon 
Channels, CA Completed 1970 253,151 8 218,854 
Suisun Bay Channel, CA Completed 1974 200,928 10 11 3,316,62212 13 
Suisun Channel, CA Completed 1973 217,677 733,48913 14 
Suisun Point Channel, CA Completed 1965 191,728 15 - 
1. Maintenance project, channels adequate for 
commerce. 
2. Includes $10 for maintenance for previous 
project. Excludes $6,160 for previous project and 
$3,840 for existing project for maintenance expended 
from contributed funds. 
3. Includes $1,600 for previous project. 
4. Includes $790 for previous project. 
5. Authorized by Chief of Engineers under 
authority of sec. 107, Public Law 86-645, as amended. 
6. All costs transferred from Los Angeles District 
in FY 1968. 
7. Estimated cost to local interests was $3,600 for 
lands, damages and public landings. Remaining portion 
of project, consisting of side channel at Orwood and 
completion of project channels from mouth of Old River 
to Lammers Ferry road and from Crocker Cut to Holly 
Sugar Factory was deauthorized November 17, 1986, by 
WRDA of 1986. 
8. Upon completion of Mormon Slough, 
Calaveras River, CA in February 1970, local interests 
accepted maintenance responsibility for Mormon 
Slough as well as for Stockton and Mormon Channels 
CA, and Federal maintenance was discontinued. No 
Federal maintenance costs have been incurred since FY 
1969. 
9. Includes $58,901 for previous project. 
10. Excludes $59,551 expended from required 
contributed funds for previous project. 
11. Excludes work accomplished under existing 
project at a cost of $207,198 from Public Works 
Administration funds allotted to San Joaquin River, CA. 
12. Includes $59,817 for previous projects. 
Excludes $5,449 expended from required contributed 
funds for previous project. 
13. Maintenance responsibility transferred to San 
Francisco District, January 1, 1974. 
14. Includes reconnaissance and condition surveys 
of $5,496 and $483 for fiscal year 1963 and 1964, 
respectively. 
15. Estimated cost (July 1964) to local interests was 
$12,000 for lands, damages, and spoil retention dikes. 
35-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual Operation and 
Project Status Report For Construction Maintenance 
Alameda Creek, CA Completed 
American River, CA Completed 
Aquatic Plant Control, CA Completed 
Big Dry Creek Dam and 
diversion, CA Completed 
Big Wash, Milford, Beaver 
County, UT Completed 
Burch Creek, Weber County, UT 
Chester, CA Active/no FY 92 
expenditure 
Cottonwood Creek, CA Active/no FY 92 
expenditure 
Coyote Creek, CA Completed 
Duck Creek, San Joaquin 
County, CA Completed 
East Weaver Creek, CA Completed 
Folsom Lake, American River, CA Completed 
Green Valley Creek, Solano 
County, CA Completed 
Kays Creek, UT Completed 
Kern River-California Adqueduct 
Intertie, CA Completed 
Klamath River, CA Completed 
Lake Camanche, CA Completed 
Lake Oroville, CA Completed 
Lakeport Lake, CA Active/no FY 92 
expenditure 
Lower San Joaquin River and 
Tributaries, including Tuolumne 
and Stanislaus Rivers, CA Completed 
Marysville Lake, CA Active/no FY 92 
expenditure 
Merced River, CA Completed 
Middle Creek, CA Completed 
Mormon Slough, CA Completed 
Napa River Basin, CA Active/no FY 92 
expenditure 
New Bullards Bar, CA Completed 
North Fork, Pit River at 
Alturas, CA Completed 
Pinole Creek, CA Completed 
Redwood Creek, Humboldt 
County, CA Completed 
Reese River, Battle Mountain, NV Completed 
Rheem Creek, CA Completed 
Rodeo Creek, CA Completed 
Salinas River, CA Inactive 
Salt Lake City, Jordan River, UT Completed 
San Leandro Creek, CA Completed 
San Lorenzo Creek, CA Completed 
San Lorenzo River, CA Completed 
Sevier River near Redmond, UT Completed 
Sonoma Creek, CA Inactive 
Truckee River and tributaries, Active/no FY 92 
CA and NV expenditure 
1978 
1959 
1967 
1955 
1961 
1964 
1981 
1991 
1968 
1967 
1965 
1957 
1963 
1973 
1977 
1972 
1976 
1981 
1976 
1976 
1980 
1976 
1967 
1976 
1979 
1972 
1974 
1968 
1970 
1969 
1962 
1966 
1952 
1961 
1973 
1962 
1966 
1952 
1973 
1968 
$26,995,350 
2, 125,818 3 
1,000 
1,369,931 4 
217,879 5 6 
26,049 5 
3,570,000 7 
15,765,000 
705,6221 5 
664,825 5 
220, 6361 59 
63,014,81010 
136,026 5 11 
407,9895 12 
1,503,073 5 13 
4,838,000 1 
10,252,950 14 
70,425,470 15 
2,353,003 18 
27,835,263 17 
- 18 
10,918,796 19 
2,643,49920 
2,965,402 21 
2,639,955 1 22 
12,890,625 23 
904,278 5 24 25 
885,7501 5 
4,620,070 1 28 
133,339 5 27 
400,000 1 5 28 
974,100 1 5 
94,213 1 29 
1,227,57030 
1,000,000 1 31 
5,130,821 1 32 
4,314,406 1 33 
919,00034 
781,500 1 35 
1,038,960 
35-38 
$54,778 1 2

SACRAMENTO, CA, DISTRICT 
TABLE 35-E (Cont'd) OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
1. Project responsibility transferred from San 
Francisco District to Sacramento District April 1, 1982. 
2. Scheduling of reservoir operations costs. 
3. Excludes $54,919 other contributed funds for 
miscellaneous construction for local interests pursuant to 
requirements of local cooperation were $951,000 
(1959) for lands and relocations. 
4. Excludes $44,008 other contributed funds for 
construction in connection with bridge construction 
pursuant to requirements of local cooperation. Total 
cost to local interests for all requirements of local 
cooperation was $370,000 (1959) for lands and 
relocations. 
5. Authorized by Chief of Engineers under 
authority of sec. 205, Public Law 80-858, as amended. 
6. Excludes $22,000 for preauthorization studies. 
7. Excludes $69,262 other contributed funds from 
State of California for two low water crossings and 
appurtenances at Chester. A fish ladder modification 
study was continued under sec. 1135 in FY 1992 at fiscal 
year cost of $40,624. 
8. Excludes $50,000 for preauthorization studies. 
Estimated costs to local interests were $665,000 for 
lands and damages including relocations. 
9. Includes $174,938 Public Works Acceleration 
Program Funds. 
10. Transferred to Bureau of Reclamation in May 
1956 for operation and maintenance by that agency in 
conjunction with other units of Central Valley project. 
11. Excludes $20,000 for preauthorization studies. 
12. Includes $30,000 for preauthorization studies. 
Estimated costs (FY 1973) to local interests for all 
requirements of local cooperation were $150,117 for 
lands and damages including relocations. 
13. Includes $73,000 for preauthorization studies. 
Non-Federal (Kern County Water Agency) cost for 
road relocation was $18,260 (required contributed 
funds). 
14. Constructed by East Bay Municipal Utility 
District. Final Federal contribution of $51,202 made 
July 18, 1978 (total $10,111,684). Non-Federal costs 
$34,988,536. 
15. Constructed by State of California. Final 
Federal contribution of $64,186 was made on 
February 9, 1981 (total $69,994,105) for flood control 
reservation. 
16. Lakeport Lake was deauthorized November 17, 
1986, and was reauthorized November 17, 1988. 
17.Cherry Valley and New Don Pedro Reservoirs 
constructed by local interests. Federal contributions of 
$9,000,000 and $5,464,000, respectively, for flood 
control reservation. Final Federal contribution of 
$308,898 was made on January 18, 1972, for New Don 
Pedro. Excludes $3,004,946, contributed funds, other, 
for miscellaneous engineering and construction (nonproject) 
at local interest expense under local cooperation 
requirements for acquisition of rights-of-way for 
levee and channel improvements on Lower San Joaquin 
River and tributaries. 
18. Planning and any future development is 
uncertain awaiting State of California's position on 
support of Marysville project. 
19. Constructed by Merced Irrigation District, Final 
Federal contribution of $839 was made December 2, 
1975 (total $10,818,638) for flood control reservation. 
20. Estimated costs (FY 1967) to local interests for 
all requirements of local cooperation were $1,340,000 
for lands and damages including relocations. 
21. Non-Federal cost $2,965,402 (FY 1976) for 
lands and relocations. Federal contribution of $599,336 
made to State Reclamation Board. 
22. This project was reclassified as "active" on 
August 3, 1987. 
23. Constructed by Yuba County Water Agency. 
Final Federal contribution of $33,470 was made in FY 
1972 (total $12,759,127) for flood control reservation. 
24. Includes $41,800 for preauthorization studies. 
25. Excludes $146,000 other contributed funds for 
miscellaneous construction and engineering and design 
services under local cooperation requirements in 
connection with acquisition of rights-of-way, relocation, 
and utility alterations. 
26. Includes $107,000 costs for remedial work to 
drainage system completed in FY 1977. 
27. Includes $19,000 for preauthorization studies. 
28. Excludes $52,549 contributed funds. 
29. Cost includes engineering and design prior to 
June 30, 1952 and costs of $4,288 (FY 1962 - 1963) to 
determine if project classification to an active category 
was justified. 
30. Estimated costs to local interests for all 
requirements of local cooperation were $463,000 (July 
1962) for lands and damages including relocations. 
Project prevented $370,000 in damages from the 
April-May 1992 snowmelt runoff. 
31. Excludes $285,329 contributed funds. 
32. Excludes $200,000 estimated value of work 
performed in lieu of cash contribution. 
33. Excludes $421,182 contributed funds. 
34. Excludes $48,000 required contributed funds 
toward first cost. Costs to local interests for all 
requirements of local cooperation, including required 
contributions, were $118,000 (1951). Project prevented 
$372,000 in damages from the April-May 1992 
snowmelt runoff. 
35. Placed inactive 1974. 
35-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Alhambra Creek, CA 1981 1986 $300,000 - 
Bear River, CA 1980 1986 - - 
Eel River, CA 1971 1986 1,272,816 - 
Gleason Creek, NV 1977 1986 215,826 - 
Humboldt River and 
Tributaries, NV 1982 1986 1,532,932 - 
Little Valley Wash, Magna, UT 1951 1977 - - 
Mad River Basin, CA 1973 1986 4,243,750 - 
Spanish Fork River, UT 1955 1977 20,000 - 
Weber River and Tributaries, UT 1974 1972 75,120 - 
(Morgan County) 
TABLE 35-H SACRAMENTO RIVER, CA: 
TIDAL AND FLOOD CONDITIONS PREVAILING 
(See Section 1 of Text) 
Range in Feet 
Miles from Mean Extreme Ordinary Extreme 
Mouth of Tidal 1 Tidal 2 Flood a Flood 4 
Place River 
Collinsville 0 4.3 7 8 10 
Sacramento 59 2.0 2 3 20 28 
Verona (Mouth of Feather River) 80 - Trace 22 30 
Colusa 144 - - 26 32 
Chico Landing 193 - - 20 25 
Red Bluff 248 - - 24 30 
1. Mean lower low water to mean higher high 
water. 
2. Tide at low water season only. 
3. Mean lower low water to flood stage. 
4. Extreme low water to indicated flood condition. 
35-40

SACRAMENTO, CA, DISTRICT 
TABLE 35-I SAN JOAQUIN RIVER, CA: 
TOTAL COST OF NEW WORK FOR PROJECT 1 
(See Section 4 of Text) 
Federal Non-Federal 2 
Modification 
Corps of 
Engineers 
(Construction) 
Coast 
Guard 
(Construction) 
Required 
Cash 
Contribution 
Lands and 
Damages (including 
Relocations) 
Prior to 1950 
Modification $4,009,938 $80,000 $1,307,500 $1,042,000 $2,349,500 $6,439,438 
1950 Modification 1,823,179 - 35,000 135,000 170,000 1,993,170 
Total $5,833,117 $80,000 $1,342,500 $1,177,000 $2,519,500 $8,432,617 
1. Completed in May 1960. 
2. Excludes $5,865,000 (Feb. 1954) local interests 
costs for Stockton Deep Water Channel terminal 
facilities required under terms of project authorization. 
TABLE 35-J SAN JOAQUIN RIVER, CA: 
PROJECT UNITS (1950 MODIFICATION) RECLASSIFIED AND 
EXCLUDED FROM PROJECT COST 
(See Section 4 of Text) 
Non-Federal 
Federal Required Lands and 
Corps of Cash Damages (includ- Total 
Unit Engineer Contribution ing Relocations) Total Project 
Settling Basin above head 
of Burns Cutoff 1 $1,073,000 $30,000 $200,000 $230,000 $1,303,000 
Burns Cutoff improvement; 
new turning basin; dredging 
Mormon Channel 2 5 7,882,0003 431,000 1,455,000 1,886,000 9,768,000 
Upper Stockton Channel 
enlargement 4 5 535,000 34,000 15,000 49,000 584,000 
1. July 1959 price index. Deauthorized August 5, 
1977.
2. Deferred; July 1960 price index. 
3. For lands and construction. 
4. Deleted by 1965 River and Harbor Act 
authorization of San Francisco Bay to Stockton 
Channel, Sacramento District, Improvement No. 3. 
5. Deauthorized November 17, 1986. 
35-41 
Total Total 
Project

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-K MERCED COUNTY STREAM GROUP, CA, 
MAXIMUM INFLOW, STORAGE, AND OUTFLOW FOR PROJECTS 
(See Section 18 of Text) 
Maximum 
Inflow Maximum Maximum 
(c. f.s.) Storage Outflow 
Stream (hourly) (acre-feet) (c.f.s.) 
Burns 1,830 120 1,260 
Bear 2,530 230 1,060 
Owens 440 130 90 
Mariposa 2,530 1,890 650 
TABLE 35-L RUSSIAN RIVER BASIN, CA: ESTIMATED 
COST FOR NEW WORK 
(See Section 22 of Text) 
Estimated Cost 
Non-Federal 
Project Feature Federal Contribution Total 
Coyote Valley Dam (Lake Mendocino): 
Channel Improvements below Dam 
on lower 98 miles of Russian River $14,436,000 $5,598,000 $20,034,000 1 
Dry Creek (Warm Springs) Lake: 
Channel Improvements below Dam 259,500,000 103,117,0002 362,617,000 
Total $273,936,000 $108,715,000 $382,651,000 
1. Exclusive of $1,628,000 for recreation facilities 
at completed projects. 
2. Reimbursement by local interests to Federal 
Government for costs allocated to water supply storage 
to be paid over a period not to exceed 50 years after use 
of storage is initiated and exclusive of lands and 
damages. 
35-42

SACRAMENTO, CA, DISTRICT 
TABLE 35-M RUSSIAN RIVER BASIN, CA: PROJECT 
FEATURES AND ESTIMATED COSTS 
(See Section 22 of Text) 
Height of Reservoir 
Nearest City Distance Dam and Capacity Estimated 
Name (California) Above Mouth Type (Acre-Ft) Cost 
Coyote Valley Dam (Lake Ukiah Mile 0.8-East Fork 160 Feet- 122,500 $17,550,000 1 
Mendocino) of Russian River Earthfill 
Channel Improvements (East Ukiah Mile 0 to 0.8 East - - 2,484,000 
Fork) Fork 
below Coyote Valley Dam Guerneville Mile 0 to 98, Russian - - - 
and lower 98 miles of River 
Russian River) 
Dry Creek (Warm Springs) Healdsburg Mile 14.4 Dry Creek 319 Feet- 381,000 359,770,000 
Earthfill 
Channel Improvements (Dry Healdsburg Mile 1 to 14.4 Dry - - 2,847,000 
Creek) below Dry Creek Creek 
(Warm Springs Dam) 
1. Exclusive of $1,628,000 for recreation facilities 
at completed projects. 
TABLE 35-N SACRAMENTO RIVER AND TRIBUTARIES, CA, 
COLLINSVILLE TO SHASTA DAM: 
PROJECT UNITS RECLASSIFIED AND EXCLUDED FROM COST ESTIMATE 
(See Section 23 of Text) 
Current Estimated Cost 
Unit Classification Federal Non-Federal 1 Total 
1944 Modification: 
Antelope Creek 2 Inactive $1,400,000 $340,000 $1,740,000 
Lower Butte Basin 3 Deferred 7,286,000 2,285,000 9,571,000 
Thomas Creek 2 Deferred 1,140,000 140,000 1,280,000 
Willow Creek 2 Inactive 1,290,000 120,000 1,410,000 
Bypass Levees 4 Deferred 7,100,000 940,000 8,040,000 
Bypass Levees 4 Inactive 3,010,000 - 3,010,000 
1950 Modification: 
Upper Butte Basin 2 Deferred 3,530,000 1,787,000 5,317,000 
1. For lands and damages, including relocations. 
2. July 1960 price level. 
3. Excludes work applicable to extension of 
Moulton weir (July 1954 price level). 
4. July 1961 price level. 
35-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-0 SACRAMENTO RIVER AND TRIBUTARIES, CA, 
FROM COLLINSVILLE TO SHASTA DAM: 
CONSTRUCTION ACCOMPLISHED AND CONTRACT COSTS 
(See Section 23 of Text) 
Required 
Contract Federal Contributed Total 
No major construction contracts in FY 92 
TABLE 35-P FLOOD CONTROL WORK UNDER SPECIAL 
AUTHORIZATION FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, PUBLIC LAW 80-858, 
AS AMENDED (PREAUTHORIZATION) 
(See Section 27 of Text) 
Fiscal Year 
Study Stage Cost 
(Federal) 
Antelope and Blackburn Creeks, CA 1 Reconnaissance 18,837 
Bitter Creek at Rock Springs, WY 1 Feasibility 21 
Burch and Jewett Creeks near Corning, CA Reconnaissance 17,897 
Carson River below Lahontan Dam, Fallon, NV 1 Reconnaissance 545 
City of Isleton, CA Reconnaissance 14,897 
Colorado River at Grand Junction, CO Feasibility 2,377 
Colorado River at Riverside, CO 1 Reconnaissance 9,720 
Cottonwood Creek near Walker Lake 
Community, NV 1 Reconnaissance 23,115 
Elder and Unionhouse Creeks, CA 1 Reconnaissance 12,523 
Henson Creek, Lake City, CO 1 Reconnaissance 4,359 
Magpie and Don Julio Creeks, CA Reconnaissance 45,222 
Mill Creek, City of Moab, UT Reconnaissance 57,982 
Sacramento River, Tehama, CA 1 Reconnaissance 16,487 
Salado Creek near Patterson, CA 1 Reconnaissance 8,769 
Smithneck Creek, Loyalton, CA Reconnaissance 40,494 
Thomas Creek, Reno, NV 1 Reconnaissance 48,034 
West Antioch Creek, CA 1 Reconnaissance 3,000 
$324,279 
1. No further studies recommended. 
35-44

SACRAMENTO, CA, DISTRICT 
TABLE 35-Q SURVEYS 
(See Section 30 of Text) 
Fiscal year costs were as follows: 
Flood damage prevention studies $3,956,943 
Required cost contributions 553,686 
Non-Federal contributions (not required) 30,248 
Sacramento-San Joaquin Rivers special study 512,004 
Special investigations 115,000 
Review of FERC licenses 39,906 
Interagency Water Resources Development 51,000 
American Waterfowl Management Plan 11,999 
Coordination with Soil Conservation Service 3,000 
Coordination with Bureau of Reclamation 9,000 
Planning assistance to states 90,655 
(California - $33,000, including Delta Water Stage study - $28,000)) 
(Colorado - $57,655) 
Total $5,373,441 
35-45

PROJECTS SPECIFICALLY AUTHORIZED UNDER THE 
FORMER CALIFORNIA DEBRIS COMMISSION 
The California Debris Commission, consisting of 
three Corps officers appointed by the President with 
the consent of the Senate, created by act of March 1, 
1893 (27 Stat. L., p. 507), was organized in San 
Francisco, CA, on June 8, 1893, and has jurisdiction 
and duties extending over drainage area of 
Sacramento and San Joaquin Rivers, comprising great 
central valley of California and extending from crest 
of the Sierra Nevada on the east to that of the Coast 
Range on the west, and from Mount Shasta and Pit 
River Basin on the north to Tehachapi Mountains on 
the south. These rivers empty into head of Suisun Bay 
ultimately discharging into the Pacific Ocean through 
connecting bays and straits and the Golden Gate. 
Duties of the Commission comprise regulation of 
hydraulic mining in drainage area of Sacramento and 
San Joaquin Rivers, CA, so that debris will not be 
carried into navigable waters or otherwise cause 
damage; jurisdiction over construction and control of 
water storage facilities for domestic, irrigation, and 
power development purposes; and direction of 
improvements for control of floods on Sacramento 
River. On November 19, 1986, the Commission was 
abolished by the Water Resources Development Act 
of 1986 (PL 99-662) and all authorities, powers, 
functions, and duties were transferred to the 
Secretary of the Army. All acquired lands and other 
interests presently under jurisdiction of the 
Commission were authorized to be retained and 
administered under direction of the Secretary. 
IMPROVEMENTS 
Navigation Page 
1. Regulation of hydraulic mining and 
preparation of plans ................ 35-1A 
2. Sacramento River and tributaries, CA 
(debris control) ................... 35-2A 
3. Treatment of Yuba River debris 
situation-restraining barriers, CA ...... 35-2A 
Flood Control 
4. Sacramento River, CA .............. 35-3A 
Tables 
Table 35-AA Cost and Financial 
Page 
Statement ............... 35-5A 
Table 35-BB Authorizing 
Table 35-CC 
Table 35-DD 
Legislation .............. 35-7A 
Sacramento River, CA: Total 
Cost of Existing Project .... 35-8A 
Sacramento Urban Area 
Levee Restoration, CA 
New Work: Major Contracts 
and Fiscal Year Costs ... . 35-9A 
Navigation 
1. REGULATION OF HYDRAULIC 
MINING' AND PREPARATION 
OF PLANS 
Location. Operations largely limited to territory 
between Mount Lassen on the north and Yosemite 
Valley on the south, on western watershed of Sierra 
Nevada. (See Geological Survey sheets for the area, 
25 in number.) 
Existing project. Provided for regulating 
hydraulic mining operations, planning improvement 
of conditions upon Sacramento and San Joaquin 
Rivers and their tributaries affected by such 
operations, and preparation of plans to enable 
hydraulic mining to be resumed in their drainage 
areas. In addition, the Secretary of the Army is 
authorized to enter into contracts to supply storage 
for water and use of outlet facilities from 
debris-storage reservoirs for domestic and irrigation 
purposes and power development upon such 
conditions of delivery, use, and payment as he may 
approve. Applications of prospective miners were 
fully investigated by the former California Debris 
Commission and permits to operate were issued to 
those who provide satisfactory debris-restraining 
basins by construction of suitable dams where 
necessary or agree to make payment for storage in 
Government-constructed debris-restraining reservoirs 
constructed under act of June 19, 1934, as set 
forth below. For location and description of 
Government-constructed, debris-restraining reservoirs 
for general hydraulic mining, see Improvement 
2. 
Local cooperation. Mineowners bore all expenses 
incurred in complying with orders of the former 
35-1A

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Commission for regulation of mining and restraint of 
debris. 
Operations and results during fiscal year. 
Minor administrative duties were accomplished. 
Administrative work overlaps that of improvements 2, 
3, and 4, hereunder, and that of Sacramento District. 
Historical summary. The former Commission 
received 1,292 applications for hydraulic mining 
licenses; 1 mine is licensed, but does not use storage 
behind Government debris dams. Work remaining is, 
in general, continuation of above or similar 
operations. 
2. SACRAMENTO RIVER AND 
TRIBUTARIES, CA (DEBRIS 
CONTROL) 
Location. Project reservoirs are to be constructed 
in watersheds of Yuba, Bear, and American Rivers, 
CA (See Geological Survey sheets for basin areas, 
seven in number.) 
Existing project. For description of completed 
North Fork and Harry L. Englebright projects and 
authorizing act, see Annual Report for 1975. Initial 
recreation facilities were provided in FY 1959. 
Recreation areas at Harry L. Englebright Dam are 
maintained by the Corps. Recreation areas at North 
Fork Dam are no longer maintained and operated by 
Auburn Recreation Park and Parkway District, but 
have been turned over to the Bureau of Reclamation 
(known as the Water and Power Resources Service 
between November 6, 1979, and May 18, 1981) on a 
permit basis. Total Federal cost of new work for 
construction of these reservoirs was $4,646,872, 
including $40,000 and $25,000, respectively, for 
basic recreation facilities at Englebright Dam and 
North Fork Dam. Reservoir project sites on Middle 
Fork of American River and on Bear River have been 
deauthorized and excluded from foregoing cost. The 
90-day Congressional project review period, required 
by sec. 12, Public Law 93-251, as amended, ended 
August 5, 1977, and resulted in deauthorization of 
that portion of the project. Estimated cost of that 
portion is $1,820,000 (1935). 
Local cooperation. Fully complied with. 
Improvements made to facilities at North Fork Dam 
by Auburn Recreation Park and Parkway District 
under a lease agreement with the Secretary of the 
Army and Auburn Boat Clubs (concessionaire) at an 
estimated cost of $46,000 since September 1953. On 
March 1, 1979, lands and waters at North Fork Dam 
were turned over to the Bureau of Reclamation on a 
5-year renewable basis. On March 1, 1984, Permit 
No. DACW05-4-79-527 was renewed for 5 years, 
was again renewed for 5 years on March 1, 1989, and 
will be effective until February 28, 1994. Bureau will 
operate and maintain such use until Auburn project is 
completed, then a fee transfer will be made. Actual 
operation and maintenance of the recreation 
resource is being done by State of California by 
contract with the Bureau. 
Licenses. Under provisions of Contract No. 
W-1105-eng-2998 with Pacific Gas and Electric Co., 
payment is to be made to the Federal Government of 
$18,000 per year for the first 30 years (December 29, 
1942 through December 28, 1972) and $48,000 per 
year between December 29, 1972, and December 28, 
1992, in return for use of head at Englebright Dam 
and generation of hydroelectric power. Total 
payment through September 30, 1992, amounts to 
$1,470,393; these funds are now paid to the 
Secretary of the Army and deposited for return to the 
Treasury. License No. 2246, effective April 9, 1970 
(date New Narrows powerplant was put in operation) 
was issued by Federal Power Commission (known as 
the Federal Energy Regulatory Commission since 
January 9, 1978) to Yuba County Water Agency for 
hydroelectric power development of Yuba River by 
the company upstream from Englebright Dam. Under 
provisions of Contract No. DA-04-167-CIVENC-
66-95 with Yuba County Water Agency, 
payment is to be made to the Federal Government of 
$100,000 per year for no more than 50 years. First 
payment (partial) of $73,151 was made April 1, 
1971; total payment through September 30, 1992, 
amounts to $2,173,151. These funds are paid to 
Sacramento District and deposited for return to the 
Treasury. 
Operations and results during fiscal year. New 
work: Maintenance: Maintenance and operation 
activities continued at Harry L. Englebright Dam at a 
cost of $677,921, including recreation facilities. Dam 
safety assurance studies at Englebright Dam have 
been completed. 
Historical summary. Construction of dams was 
initiated in 1937; North Fork project was completed 
and in use at end of FY 1939, and Harry L. 
Englebright project was completed in January 1941. 
The two debris-control structures are in good 
condition. Public use of these reservoir recreation 
areas greatly overtaxes present capacities. Dam safety 
assurance studies were initiated at Englebright Dam in 
FY 1981 and were completed in FY 1987. 
3. TREATMENT OF YUBA RIVER 
DEBRIS SITUATION-RESTRAINING 
BARRIERS, CA 
Location. Works are on Yuba River between 
Marysville and where the river emerges from the 
foothills, near Hammonton, some 10 miles easterly 
from Marysville, or about 9 miles below the Narrows. 
(See Geological Survey Topographic map of 
Sacramento Valley, CA) 
Existing project. For description of completed 
project and authorizing act, see Annual Report for 
1975. Total cost of new work was $723,259, of which 
$361,482 was U.S. funds and $361,777 required 
contributed funds by State of California. (For details 
35-2A

SACRAMENTO, CALIFORNIA, DISTRICT 
of project in its original form, see Annual Report, 
1917, p. 1810.) In February 1963, center section of 
dam failed and major rehabilitation of structure was 
completed in December 1964. Total cost for required 
rehabilitation was $1,660,000, of which $830,000 
was Federal cost and $830,000 required contribution 
by State of California toward rehabilitation cost. 
During the December 24, 1964, floodflows on the 
Yuba River, the rehabilitated Daguerre Point Dam 
sustained considerable damage. (See 1965 Annual 
Report, p. 1647 "Operations and results during fiscal 
year,") The reconstructed portion of the dam completed 
earlier in December 1964 was undamaged by 
the flood. Permanent repair of Daguerre Point Dam 
abutment and fish facilities was completed in October 
1965 at a cost of $447,808 with Federal and required 
State contributed funds on a matching basis. 
Local cooperation. Fully complied with for new 
work and major rehabilitation work. Total first cost to 
local interests for new work was $361,777 (required 
contribution by State of California). In addition, 
training walls were built on each bank below Daguerre 
Point for 11,250 feet and just above Daguerre Point, 
on the south bank, for 11,000 linear feet by two 
gold-dredging companies in connection with their 
dredging operations. To build these training walls 
would have cost the United States $450,000 (1902 
estimate). Flood channels were also built by 
gold-dredging companies within confines of project 
works. Cost to the United States of equally effective 
works to restrain debris movement would have been 
more than $776,000 (1926 estimate). Total costs to 
local interests for initial and permanent major 
rehabilitation works were $830,000 and $223,904, 
respectively, (required contribution by State of 
California). State of California must contribute 
annually an amount equal to the Federal allotment 
for maintenance. 
Operations and results during fiscal year. 
Maintenance: Operations consisted of condition and 
operation studies by hired labor; and bank protection, 
Yuba River, various locations upstream from 
Marysville completed by contract, $9,845. 
Historical summary. Construction of project 
works was initiated in November 1902. Construction 
of Daguerre Point Dam was completed in May 1906; 
diversion of river over dam was completed in 1910; 
training walls and dikes were completed in 1935. 
About 149 million cubic yards of debris are held in 
lower 7 miles of Yuba River between Marysville and 
downstream end of training walls. About 20 million 
cubic feet, are confined in river channel by Daguerre 
Point Dam. Additional millions of yards of loose 
material are in mine tailing fields adjacent to project 
training walls in upper 7-mile reach of project. Initial 
rehabilitation of Daguerre Point Dam begun in July 
1963 was completed in December 1964. Contract for 
permanent rehabilitation of structure was initiated in 
July and completed in October 1965. 
Flood Control 
4. SACRAMENTO RIVER, CA 
Location. Works covered by this improvement are 
on Sacramento River and tributaries in north-central 
California from Collinsville to Ordbend, a distance of 
184 miles. 
Previous project. For details see page 1815 of 
Annual Report for 1917, page 1995 of Annual Report 
for 1938, and page 2262 of Annual Report for 1907. 
Existing project. Sacramento River flood control 
project is a comprehensive plan of flood control for 
Sacramento River and lower reaches of its principal 
tributaries. Improvement extends along Sacramento 
River from Ordbend in Glenn County, CA, 184 miles 
downstream to its mouth at Collinsville at upper end 
of Suisun Bay, and comprises a system of levees, 
overflow weirs, drainage pumping plants, and flood 
bypass channels or floodways designed to carry surplus 
floodwaters without inundation of valley lands. 
About 980 miles of levee construction, with an average 
height of 15 feet and 98 miles of bank protection 
are involved in project. For further details, see Annual 
Report for 1962, page 2115. (See table 35-BB 
for authorizing legislation.) 
Estimated (October 1987) cost for original project 
(exclusive of supplemental levee improvements), 
including new work and maintenance, is 
$163,925,000 of which $68,925,000 is Federal cost 
and $95 million non-Federal ($90,050,562 for lands 
and damages and relocations and $4,949,438 
required contributed funds for levee construction, 
bank protection works, and levee setbacks). Of this 
amount, $4,939,752 was for new work and $9,686 
for maintenance. Estimated October 1992 total 
project cost is $250,639,000, of which $123,129,000 
is Federal and $127,510,000 is non-Federal. Total 
estimate now includes remedial levee work for Yolo 
Bypass and Cache Slough (Unit 109); Colusa Basin 
Drain (Unit 132); Knights Landing Ridge Cut (Unit 
127); Marysville/Yuba City Area levees; Mid-Valley 
Area; and Lower Sacramento Area (engineering and 
design only), but excludes Sacramento Urban Area 
Levee Reconstruction. In addition to project 
requirements, local interests constructed several 
pumping plants for drainage of agricultural and urban 
land protected by project levees. Some channel 
clearing work was accomplished by State of California 
and other local interests to supplement project levee 
construction. Dredging below Cache Slough and 
reconstruction of Cache Creek settling basin weir are 
considered deferred and excluded from foregoing 
cost estimate. Estimated cost (July 1962) of these 
project units is $2,560,000 and $520,000, respectively, 
a total of $3,080,000 plus U.S. costs, for 
construction. Operation and maintenance of completed 
project will be responsibility of local interests; 
as units of project are completed, they are transferred 
to agencies of State of California for operation and 
maintenance. Existing project was adopted by 1917 
35-3A

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Flood Control Act (H. Doc 81, 62d Cong., 1st sess., 
as modified by Rivers and Harbors Committee Doc. 
5, 63d Cong., 1st sess.), 1928 Flood Control Act (S. 
Doc. 23, 69th Cong., 1st sess.), River and Harbor Act 
of 1937 (S. Committee print 75th Cong., 1st sess.), 
and 1941 Flood Control Act (H. Doc. 205, 77th 
Cong., 1st sess.). 
Phase I - Sacramento River Flood Control System 
Evaluation recommended reconstruction of 32 miles 
of Sacramento area levees. Report was approved and 
in March 1989, Sacramento Urban Area Levee 
Reconstruction project was established under authority 
of Sacramento River Flood Control Project. New 
project is located within boundaries of Sacramento 
River Flood Control System in highly urbanized area 
around city of Sacramento, near confluence of 
Sacramento and American Rivers. It includes 
Natomas area levees from Natomas Cross Canal 
Bypass through Reclamation District 900 and portions 
of the Yolo Bypass east levee in West Sacramento; 
and, in South Sacramento, the east bank of 
Sacramento River from Miller Park to town of 
Freeport. Estimated (October 1992) cost for 
Sacramento Urban project is $38,600,000 of which 
$22,700,000 is Federal and $15,900,000 is 
non-Federal (including a cash contribution of 
$1,920,000). 
Sacramento River Flood Control Project 
(Glenn-Colusa Irrigation District) (G.C.I.D.) is part 
of the fishery/irrigation enhancement project being 
developed by G.C.I.D. Project is located between 
River Mile 202 and 206 on Sacramento River near 
the Glenn-Tehama county line. The Corps riffle 
restoration project includes multiple weir structures in 
the river to restore river hydraulic gradient to 
pre-1970 conditions. This will stabilize river 
hydraulics. Estimated (October 1992) project cost is 
$8,200,000, of which $6,150,000 is Federal and 
$2,050,000 is non-Federal. Project was established 
under authority of the 1917 Sacramento River Flood 
Control Project (see Energy and Water Development 
Appropriations Act of 1990). 
Local cooperation. Local interests have fully 
complied with requirements for all work completed 
and indicated they will be able to fulfill requirements 
for remaining work. Local interest costs from required 
contributed funds for project work total 
$4,949,438 for levee construction, bank protection 
works, and levee setbacks, of which $4,939,752 was 
for new work and $9,686 for maintenance. 
Operations and results during fiscal year. New 
work: (a) Sacramento Urban Area Levee 
Reconstruction: For major contracts and fiscal year 
costs, see Table 35-DD. (b) Sacramento River 
Flood Control Project (Glenn Colusa Irrigation 
District (G.C.I.D.): Engineering was initiated on 
riffle restoration on Sacramento River including 
building of multiple weir structures to restore river 
hydraulic gradient to pre-1970 conditions. 
Historical summary. Construction of existing 
project began in FY 1918 and is about 99 percent 
complete. Channel improvement to date has 
produced a channel with a capacity of 579,000 cubic 
feet per second in Sacramento River below Cache 
Slough. In addition, discharges up to 21,000 cubic 
feet per second can be diverted from Sacramento 
River through Georgiana Slough. Completed major 
project items include about 977 miles of levees; five 
weirs with a combined discharge capacity of 602,000 
cubic feet per second; two cutoff channels; two sets of 
outfall gates; channel improvement and clearing in 
Sacramento River, Butte Creek, Putah Creek, and 
Sutter and Tisdale Bypasses; construction of two main 
bypasses or floodways and secondary bypasses at 
Tisdale and Sacramento weirs and at Wadsworth 
Canal; construction of Knights Landing ridge cut and 
of Cache Creek settling basin; installation of gaging 
stations; and enlargement of Sacramento River below 
Cache Slough. Cutoffs at Collins Eddy and between 
Wild Irishman and Kinneys Bends were made in 1918 
and 1919, respectively. Sacramento weir was 
completed in 1917, Fremont weir in 1924, Tisdale 
and Moulton weirs in 1932, and Colusa weir in 1933. 
Outfall gates at Knights Landing were constructed in 
1930 and at mouth of Butte Slough in 1936. Pumping 
plants on Sutter Bypass were completed in 1944. 
Work items with reference to clearing, snagging, 
rectification of channels, and bank protection on 
Sacramento River and tributaries in Tehama County 
and from Red Bluff southerly, provided for by 1941 
Flood Control Act were accomplished in fiscal years 
1947, 1948, 1949, and 1951. Yolo Bypass and Cache 
Slouth (Unit 109) was completed in 1990. Work 
remaining comprises completion of levee stage 
construction, Colusa Basin Drain (Unit 132); Knights 
Landing Ridge Cut (Unit 127); Marysville/Yuba City 
Area levees; Mid-Valley Area; and Lower Sacramento 
Area. (See Table 35-CC for total cost of 
existing project to September 30, 1992.) 
35-4A

TABLE 35-AA 
SACRAMENTO, CALIFORNIA, DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
1. Regulation of 
Hydraulic Mining 
and Preparation 
of Plans 
2. Sacramento River 
and Tributaries, 
CA (Debris 
Control) 
(Contributed 
Funds, Other) 
3. Treatment of 
Yuba River 
Debris Situation 
Restraining 
Barriers, CA 
(Federal Funds) 
(Required 
Contributed 
Funds) 
(Contributed 
Funds, Other) 
4. Sacramento 
River, CA 
including 
Sacramento River 
Flood Control 
Project (Federal 
Funds) 
(Contributed 
Funds) 
Sacramento 
Urban Area Levee 
Reconstruction 
(Federal Funds) 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
$821,325 
821,325 
- - - - 5,093,999 1 2 
- - - - 5,093,999 1 2 
$706,300 571,490 681,300 700,000 11,088,933 3 
691,157 582,877 695,998 725,921 11,070,022 4 
- - - - 12,420 
- - - - 12,420 6 
361,482 
361,482 
20,000 
36,360 
-16,325 
5,257 
14,700 2,000 1,813,0316 
347 18,634 1,805,072 8 
1,053,904 
1,053,904 
361,777 
361,777 
43,163 5,257 
12,000 1,813,838 
347 8,790 1,783,453 
1,053,904 
1,053,904 
34,000 7 
34,000 7 
2,285,000 425,000 950,000 1,221,000 75,691,835 8 
3,536,455 1,026,885 1,221,226 1,515,322 75,684,4538 
- - - - 1,979,104 
- - - - 1,979,104 
- - - - 10,724,085 
- - - - 10,724,085 9 
- - - - 9,686 10 
- - - - 9,686 10 
1,200,000 3,600,000 10,663,000 3,371,000 18,834,000 
- 2,478,099 5,005,372 8,823,196 16,306,668 
35-5A

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-AA (Cont'd) COST AND FINANCIAL STATEMENT 
See 
Section Total Cost to 
in Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
(Required New Work 
Contributed Contrib. - 390,000 1,000,300 514,900 1,905,200 
Funds) Cost - 54,411 395,330 634,064 1,083,805 
(Contributed New Work 
Funds, Other) Contrib. - 510,000 2,615,000 2,196,712 5,321,712 11 
Cost - 10,559 929,456 2,227,152 3,167,168 11 
Sacramento New Work 
River Flood Approp. - 493,000 500,000 300,000 1,293,000 12 
Control Cost - 107,838 329,783 662,724 1,100,355 12 
(G.C.I.D.), 
CA (Federal 
Funds) 
1. Exclusive of $644,503 appropriation and cost 
on inactive portion of project. 
2. Includes $477,127 for recreational facilities at 
North Fork ($32,473) and Harry L. Englebright 
($414,654), Code 710 appropriations and costs. 
3. Includes $1,416,082 from regular funds and 
$9,672,851 from Hydraulic Mining in California funds. 
4. Includes $9,653,940 from regular costs and 
$1,416,082 from Hydraulic Mining in California costs. 
5. Funds from State of California Department of 
Navigation and Ocean Development for acquisition of a 
boarding float at Englebright Dam. 
6. Includes deferred maintenance funds in 
amount of $207,500. 
7. Miscellaneous engineering and construction 
accomplished at expense of local interests in 
connection with rehabilitation of Daguerre Point Dam 
necessitated by December 1964 floodflows. 
8. Includes appropriation and cost of $680,000 
for new work for previous project and $1,486,469 
public works funds for new work for existing project. 
9. Includes $680,000 required contribution funds 
for previous project; $4,939,752 required contributed 
funds for existing project; and $310,801 voluntary 
contribution for bank protection for existing project. 
10. Includes $9,686 required contributed funds for 
existing project. 
11. Includes contributed funds, other, from the 
State of California for relocation of utilities, irrigation 
ditch, access ramps, and miscellaneous small structures 
in the Natomas, Greenhaven Pocket and West 
Sacramento areas. 
12. Construction funds received in FY 1991, but 
no costs were incurred. Includes $493,000 total funds 
and costs under General Investigations for Preconstruction 
Engineering and Design. 
35-6A

TABLE 35-BB 
SACRAMENTO, CALIFORNIA, DISTRICT 
AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
Ex. Doc. 267, 51st 
Cong., 2d sess., Ex. 
Doc. 98, 47th Cong., 
1st sess. 1 
(Amendment of sec. 13, 
Act of Mar. 1, 1893.)1 
Mar. 1, 1893 
Feb. 27, 1907 
35-7A 
REGULATION OF HYDRAULIC MINING 
AND PREPARATION OF PLANS 
Created California Debris Commission and 
authorized: (a) Hydraulic mining under its 
regulation in drainage areas of Sacramento 
and San Joaquin Rivers, if possible without 
injury to navigability of these river systems or 
to lands adjacent thereto; and (b) preparation 
of plans by Commission for improvement 
of navigability of these river systems, and 
flood and debris-control therein. 
Authorized California Debris Commission to 
permit hydraulic mining without construction 
of impounding works, provided there is no 
injury to navigability of above river systems 
or lands adjacent thereto. 
Amended act of Mar. 1, 1893, which provides 
for construction of debris dams or other restraining 
works by California Debris Commission 
and collection of a 3-percent tax on 
gross proceeds of each mine using such 
facilities, so as to eliminate this tax and 
substitute an annual tax per cubic yard 
mined, obtained by dividing total capital 
cost of each dam, reservoir, and rightsof-
way, by total capacity of reservoir for 
restraint of debris; and authorized revocation 
of Commission orders permitting 
such mining, for failure to pay this annual 
tax within 30 days after its due date; and 
also authorized receipt of money advances, 
from mineowners to aid such construction, 
to be refunded later from annual payments 
of yardage taxes on material mined. 
Added at end of sec. 23 of above act, a provision 
that the Secretary of the Army is 
authorized to enter into contracts to supply 
storage for water and use of outlet facilities 
from debris-storage reservoirs for domestic 
and irrigation purposes and power development, 
upon such conditions of delivery, use, 
and payment as he may approve, these payments 
are to be deposited to credit of such 
reservoir project, reducing its capital cost to 
be repaid by tax on mining operations. 
Abolished the California Debris Commission 
and transferred all authorities, powers, 
functions, and duties to the Secretary of 
the Army. Authorized all acquired land 
and other interests presently under jurisdiction 
of the Commission to be retained 
and administered under direction of the 
Secretary. 
Sec. 1001, 1986 WRDA 
June 19, 1934 
June 25, 1938 
Nov. 17, 1986

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 35-BB (Cont'd) AUTHORIZING LEGISLATION 
See Date of 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
4. SACRAMENTO RIVER, CA 
Dec. 22, 1944 Additional levee construction and reconstruction, H. Doc. 649, 78th 
and May 17, 1950 including levee protection of Upper Butte Basin, Cong., 2d sess., and 
and multipurpose reservoirs. 2 367, 81st Cong., 
1st sess. 
July 3, 1958 Bank protection and incidental channel improve- H. Doc. 272, 84th 
ments, Sacramento River from Chico Landing Cong., 2d sess. 
to Red Bluff, and local interests flood plain 
zoning above Chico Landing. 2 
July 14, 1960 Bank protection works at critical locations, S. Doc. 103, 86th 
Sacramento River. 2 Cong., 2d sess. 
1. For latest published map, see Annual Report 2. This supplemental work is reported in detail 
for 1913, p. 3170, and Rivers and Harbors Committee under Sacramento District, Improvement No. 23. 
Document 50, 74th Cong., 1st sess. 
TABLE 35-CC SACRAMENTO RIVER CA: TOTAL COST OF 
EXISTING PROJECT TO SEPTEMBER 30, 1992 
(See Section 4 of Text) 
Funds New Work Maintenance Total 
Regular $73,517,984 $1,979,104 $75,497,088 1 
Public Works 1,486,469 - 1,486,469 
Total U.S. 75,004,453 1,979,104 76,983,557 
Contributed Project Work 4,939,752 9,686 4,949,438 
Contributed, Other 5,104,333 -- 5,104,333 
Total All Funds 85,048,538 1,988,790 87,037,328 2 
1. Includes $429,671 representing book value of 
plant purchased with previous project funds and 
transferred to existing project without reimbursement. 
2. Excludes financial information for Sacramento 
Urban Area Levee Reconstruction and Glenn-Colusa 
Irrigation District (G.C.I.D.) projects, both authorized 
under the Sacramento River Flood Control Project. 
(See Table 35-AA). 
35-8A

SACRAMENTO, CALIFORNIA, DISTRICT 
TABLE 35-DD SACRAMENTO URBAN AREA 
LEVEE RECONSTRUCTION, CA 
NEW WORK: MAJOR CONTRACTS AND FISCAL YEAR COSTS 
(See Section 4 of Text) 
Required Contributed 
Contributed Funds 
Item Federal Funds Other Total 
Greenhaven Pocket 
Phase II $2,050,488 $122,423 $ 551,442 $2,724,353 
Repair Boil - Greenhaven 
Pocket Phase II 484,886 32,069 - 516,955 
Natomas South 548,074 40,735 173,878 762,687 
Natomas North 2,171,472 213,687 1,363,174 3,748,333 
West Sacramento 522,380 280,158 53,790 856,328 
Greenhaven Pocket 
Phase I 916,546 51,852 67,148 1,035,546 
35-9A

PACIFIC OCEAN DIVISION 
The Pacific Ocean Division is an operating division with 
both district and division functions. Its civil works responsibilities 
encompass the State of Hawaii, the Territory 
of Guam, the Territory of American Samoa, and the 
Commonwealth of the Northern Mariana Islands. The 
division is unique in that the area of responsibility is 
totally comprised of islands dispersed over an ocean 
environment exceeding 6 million square miles. 
IMPROVEMENTS 
Navigation 
1. Kawaihae Small Boat Harbor, 
Hawaii, Hawaii ....................... 
2. Maalaea Harbor, Maui, Hawaii ........... 
3. Reconnaissance and Condition Surveys .... 
4. Navigation Work Under Special 
Authorization ......................... 
Erosion Control 
5. Saipan Beach Road, CNMI, .............. 
6. Sand Island Shore Protection 
Oahu, Hawaii ....................... . 
7. Beach Erosion Work Under Special 
Authorization .......................... 
Flood Control 
8. 
9. 
Alenaio Stream, Hawaii, Hawaii .......... 
Flood Control Work Under Special 
Authorization ....................... 
Multiple-Purpose Projects, 
Including Power 
10. Nanpil River Hydropower, Pohnpei, 
Federated States of Micronesia ........... 
Page General Investigations 
11. Surveys ............................. 
36-2 12. Collection and Study of Basic Data ........ 
36-2 
36-2 Tables 
Table 36-A 
36-2 Table 36-B 
Table 36-C 
36-2 Table 36-D 
36-2 Table 36-E 
36-3 Table 36-F 
Table 36-G 
Table 36-H 
36-3 Table 36-I 
36-3 
Table 36-J 
Table 36-K 
36-3 
Page 
36-4 
36-4 
Cost and Financial Statement .... 36-5 
Authorizing Legislation .......... 36-6 
Other Authorized Navigation 
Projects ...................... 36-7 
Other Authorized Beach 
Erosion Control Projects ......... 36-8 
Other Authorized Flood 
Control Projects ................ 36-9 
Not Applicable 
Deauthorized Projects ........... 36-10 
Navigation Activities Pursuant 
to Section 107 ................. 36-11 
Emergency Streambank and 
Shoreline Protection Activities 
Pursuant to Section 14 .......... 36-11 
Beach Erosion Control Activities 
Pursuant to Section 103 ......... 36-12 
Flood Control Activities Pursuant 
to Section 205 .................. 36-12 
36-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Navigation 
1. KAWAIHAE SMALL BOAT HARBOR, 
HAWAII, HAWAII 
Location. Kawaihae Harbor is located on the west 
coast of the island of Hawaii, approximately 85 nautical 
miles northeast of Hilo, County of Hawaii. (See NOAA 
Chart 19320) 
Existing project. For a description of the existing 
project, see page 36-2 of the FY89 Annual Report. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. A Local Cooperation Agreement 
(LCA) will be prepared during the plans and specifications 
phase. 
Terminal facilities. None. 
Operations during fiscal year. The estimated cost 
of preconstruction engineering and design (PED) is 
$408,000. Total costs incurred during the Fiscal Year 
were $153,136. Work included drafting of a limited 
reevaluation report to document the project rescoping 
process to reduce the harbor capacity from 300 to a 
90-boat facility. A draft environmental assessment was 
completed in FY92 and submitted for public review. 
Plans and specifications were approximately 89% complete 
as of September 30, 1992. 
2. MAALAEA HARBOR, MAUI, HAWAII 
Location. Maalaea Bay is situated on the southwest 
coast of Maui, approximately 7 miles south of Wailuku, 
the county seat of Maui. (See NOAA Chart 19350) 
Existing project. For a description of the existing 
project, see page 36-3 of the FY89 Annual Report. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. A Local Cooperation Agreement 
(LCA) will be prepared during the plans and specifications 
phase. 
Terminal facilities. There is an existing 1,000-foot 
long south breakwater, a 870-foot long east breakwater, 
300-foot long wharf, 90-foot wide entrance channel, and 
a single lane launch ramp, all constructed by the State of 
Hawaii. 
Operations during fiscal year. Total costs incurred 
during the Fiscal Year were $233,505. Work 
continued on the Environmental Impact Statement currently 
scheduled for completion in early FY93. The plans 
and specifications phase was approximately 90% complete 
as of September 30, 1992. 
3. RECONNAISSANCE AND CONDITION 
SURVEYS 
Condition surveys were conducted by the Portland 
District at Barbers Point Deep Draft Harbor, Oahu; 
Kaulapapa Landing, Molokai; Nawiliwili Deep Draft and 
Small Boat Harbors, Kauai; and Port Allen Harbor, Kauai; 
during March and April 1992 for $28,265. Surveys were 
also conducted in February 1992 at Aunuu and Ofu 
Harbors in American Samoa by the Portland District for 
$16,681. In addition, a contract survey was completed in 
August 1992 for $15,127 at Port Allen Harbor, Kauai. 
4. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public 
Law 86-645 (Preauthorization). See Table 36-H. 
Beach Erosion Control 
5. SAIPAN BEACH ROAD, CNMI 
Location. The study area is located on the western 
coast along the southern half of Saipan Island, Commonwealth 
of the Northern Mariana Islands (CNMI). See 
U.S. Defense Mapping Agency Hydrographic Map No. 
81067) 
Existing project. For a description of the existing 
project, see page 36-3 of the FY91 Annual Report. 
Local cooperation. Requirements are described in 
full on page 36-3 of the FY91 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. A construction 
contract was awarded in August 1991 and completed in 
May 1992 at a total cost of $176,000, all Federal funds. 
6. SAND ISLAND SHORE PROTECTION, 
OAHU, HAWAII 
Location. Sand Island is located on the southern 
coast of Oahu. Sand Island is approximately 520 acres in 
area and shelters Honolulu Harbor from the open sea. It 
is connected to the Kapalama peninsula by a bascule 
bridge at its western end. There is approximately 4,700 
feet of shoreline on the south side of the island adjacent to 
the State park. (See Coast and Geodetic Survey Chart 
4109) 
36-2

PACIFIC OCEAN DIVISION 
Existing project. For a description of the existing 
project, see page 36-3 of the FY89 Annual Report. 
Local cooperation. Requirements are described in 
full on page 36-4 of the FY88 Annual Report. 
Terminal facilities. None. 
Operations during fiscal year. A construction 
contract was awarded in September 1990 and completed 
in October 1991 at a total cost of $1,313,400 of which 
$1,226,486 were Federal funds and $726,532 were 
non-Federal funds. 
7. BEACH EROSION WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency streambank and shoreline protection activities 
pursuant to Section 14, Public Law 79-526 (Preauthorization). 
See Table 36-I. 
Beach Erosion control activities pursuant to Section 
103, Public Law 87-874 (Preauthorization). See Table 
36-J. 
Flood Control 
8. ALENAIO STREAM, HAWAII, HAWAII 
Location. The Alenaio watershed is located in the 
South Hilo District on the island of Hawaii. Hilo is the 
principal urban center in the South Hilo district and the 
County seat for the County of Hawaii. (See NOAA Chart 
81408) 
Existing project. For a description of the existing 
project, see page 36--4 of the FY89 Annual Report. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. A Local Cooperation Agreement 
was executed on April 27, 1992. The local sponsor has 
agreed to: (a) provide during the period of construction, 
a cash contribution of 5 percent of total project costs; (b) 
provide all lands, easements, rights-of-way, and suitable 
borrow and dredged material disposal areas, and perform 
all relocations (excluding railroad bridges and approaches 
thereto) determined by the Government to be necessary 
for construction of the Project; (c) provide during the 
period of construction, an additional cash contribution in 
the amount necessary to make its total contribution equal 
to 25 percent of the total project costs if the value of the 
contributions provided represents less than 25 percent of 
total project costs; (d) participate in and comply with 
applicable Federal flood plain management and flood 
insurance programs; (e) inform affected interests of the 
limitations of the protection afforded by the project no less 
than once each year; (f) publicize flood plain information 
in the area concerned and provide this information to 
zoning and other regulatory agencies for their guidance 
and leadership in preventing unwise future development 
in the flood plain and in adopting such regulations as may 
be necessary to prevent unwise future development and 
to ensure compatibility with protection levels provided by 
the project; (g) accept the project or functional portion and 
be solely responsible for operating, maintaining, repairing, 
replacing, and rehabilitating the project or functional 
portion. 
Terminal facilities. None 
Operations during fiscal year. Work in FY92 included 
continuing coordination with the local sponsor for 
land acquisition required for construction of the project. 
Work was also initiated for the investigation of possible 
Hazardous and Toxic Waste materials in an area of the 
project location. Plans and specifications were approximately 
91% complete as of September 30, 1992. 
9. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 80-858. (Preauthorization). See Table 36-K. 
Emergency flood control activities pursuant to Public 
Law 84-99. 
Federal cost during the fiscal year for Flood Control and 
Coastal Emergencies appropriation was $303,300 ofwhich 
$227,455 was for disaster preparedness, $68,634 for rehabilitation 
and $7,211 for emergency operations. 
Multiple-Purpose Projects, 
Including Power 
10. NANPIL RIVER HYDROPOWER, 
POHNPEI, FEDERATED STATES OF 
MICRONESIA 
Location. Nanpil River is located on the island of 
Pohnpei in the Federated States of Micronesia (See State 
of Hawaii, the New Pacific map). 
Existing project. For a description of the existing 
project see page 36-4 of the FY85 Annual Report. (See 
Table 36-B for Authorizing Legislation) 
Local cooperation. Requirements are described in 
full on page 36-5 of the FY85 Annual Report. 
Terminal Facilities. None. 
Operations during fiscal year. Modifications to 
the existing facility were completed, which included installation 
ofguardrails on the access road, construction of 
a sound suppression wall, and creation of additional storage 
space. A self cleaning trash rack at the intake 
structure will be constructed once installation of the necessary 
transmission lines are completed by the local 
government. A contract to provide training for the operation 
and maintenance of the project will continue through 
FY93. 
36-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
General Investigations 
11. SURVEYS 
Fiscal year costs were $534,601 of which $267,962 was 
for flood damage prevention studies; $2,486 for restudy of 
deferred projects; $100,003 for miscellaneous activities; 
and $164,150 for coordination with other agencies. 
12. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain management services. Flood Plain 
Management Services Program comes under Section 206, 
PL 86-645,1960 Flood Control Act, as amended. Through 
technical services and planning guidance, the program 
provides information on floods and flood related information 
to improve planning for the careful use of the nation's 
flood plains, thereby reducing the potential for losses to 
life and property from floods and wave actions. 
Non-Federal agencies are assisted with flood hazard 
evaluation and planning information for flood and coastal 
hazard areas without charge. Beginning November 21, 
1991, Federal agencies and private entities were also offered 
these services on a cost recovery basis. This assistance 
is in the form of local flood plain regulations, 
National Flood Insurance requirements, and Executive 
Order 11988 requirements for federal agencies. Such 
assistance may include flood information and timing, 
floodwater velocity, extent of flooding, duration of flooding, 
flood frequency and regulatory floodway limits. 
Services accomplished during fiscal year. 
Requests and responses for technical services and planning 
assistance totaled 3,560, which included services to 
Federal and non-Federal agencies, individuals, realtors, 
corporations, lending institutions, engineers, architects 
and others. Costs for providing these services during the 
fiscal year were $200,139. 
Hydrologic Studies. Storm studies cost was $5,005. 
Total costs for collection and study of basic data during 
the fiscal year were $205,144. 
36-4

PACIFIC OCEAN DIVISION 
TABLE 36-A COST AND FINANCIAL STATEMENT 
See 
Section Total Cost To 
In Text Project Funding FY89 FY90 FY91 FY92 Sept. 30, 1992 
1. Kawaihae Small New Work: 
Boat Harbor, Approp. 170,000 156,000 260,000 130,000 716,000 
Hawaii, HI Cost 149,759 175,904 237,196 153,136 715,995 
(Federal Funds) 
2. Maalaea Harbor New Work: 
Maui, HI Approp. 200,000 88,000 250,000 119,000 852,000 
(Federal Funds) Cost 125,660 151,254 126,373 233,505 831,792 
6. Sand Island Shore New Work: 
Protection, HI Approp. --- 10,000 1,110,900 20,000 1,313,400 
(Federal Funds) Cost 177 -55 1,100,083 42,044 1,313,400 
(Contributed Contrib. --- --- 1,219,833 6,653 1,226,486 
Funds) Cost --- --- 1,199,735 26,751 1,226,486 
8. Alenaio Stream, New Work: 
Hawaii, HI Approp. 96,000 358,000 265,000 256,000 1,275,000 
(Federal Funds) Cost 261,384 259,599 276,943 344,714 1,250,028 
10. Nanpil River New Work: 
Hydropower, Approp. --- 120,000 412,000 126,000 7,862,000 
Pohnpei, FSM Cost 290,511 183,039 293,310 205,628 7,706,901 
(Federal Funds) 
36-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 36-B AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Oct. 27, 1965 
2. 
Aug. 3, 1968 
Nov. 17, 1986 
Nov. 28, 1990 
Mar. 20, 1980 
Dec. 8, 1983 
KAWAIHAE SMALL BOAT HARBOR, HAWAII, HAWAII 
An 850-foot long, 120-foot wide, and 12-foot deep 
entrance channel; a 1.2 acre and 12-foot deep existing 
turning basin; a 640-foot long, 80-foot wide, and 8-foot 
deep access channel; a 1,225-foot long west protective revetstructure; 
a 1,050-foot long east protective revetted structure 
a 400-foot long wave absorber; and a 2.5 acre, 650-foot long 
revetted offshore island. 
MAALAEA HARBOR, MAUI, HAWAII 
A 620-foot long extension of the south breakwater, 
a new 610-foot length, 150 to 180-foot width, 12 to 
15-foot depth entrance channel, a 1.7 acre and 12-foot 
depth turning basin and a 720-foot length, 80-foot 
width and an 8-foot deep access channel. 
ALENAIO STREAM, HAWAII, HAWAII 
Project consists of approximately 1,640-feet of 
concrete-lined channel; floodproofing five individual 
structures, relocation of one public and six residential 
structures and incorporating floodplain management 
regulations for undeveloped areas. 
Modified by the General Design Memorandum and 
Environmental Assessment dated March 1990, at a 
total cost of $12,060,000, with an estimated first Federal 
cost of $7,730,000 and an estimated first non-Federal 
cost of $4,330,000. 
NANPIL RIVER HYDROPOWER, POHNPEI, FSM 
Construction of a hydroelectric power facility. 
Appropriation of funds for a feasibility study 
and construction of a hydroelectric project. 
Sec 301, PL 89-298 
Cong., 1st sess. 
Sec 101, PL 90-438 
Cong., 2nd sess. 
Sec 401, PL 99-662 
Sec 102, PL 101-640 
Sec. 101, PL 96-205 
Sec. 2, PL 98-213 
36-6 
8. 
10.

PACIFIC OCEAN DIVISION 
TABLE 36-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Agana Small Boat Harbor, Guam Completed 1978 $ 937,7981 $ 52,555 
Agat Harbor, Guam Completed 1989 2,000,000 2 
Auasi Harbor, American Samoa Completed 1982 1,033,015 3 21,868 
Aunuu Harbor, American Samoa Completed 1982 1,783,129' 278,007 
Barbers Point Harbor, Oahu, Hawaii Completed 1990 53,508,709 6 485,551 
Haleiwa Small Boat Harbor, Oahu, Hawaii Completed 1978 527,047 6 208,902 
Hilo Harbor, Hawaii, Hawaii Completed 1991 5,512,440 4,091,308 
Honokohau Small Boat Harbor, Hawaii, Hawaii Completed 1971 781,036 7 63,693 
Honolulu Harbor, Oahu, Hawaii Completed 1985 16,044,095 8 2,777,972 
Kahului Beach Road, Maui, Hawaii Completed 1976 751,867 g --- 
Kahului Harbor, Maui, Hawaii Completed 1984 7,203,22110 7,287,654 
Kalaupapa Harbor, Molokai, Hawaii Completed 1968 157,997 9 3,127 
Kaulana Bay Boat Harbor, Hawaii, Hawaii Active 1990 171,400 --- 
Kawaihae Harbor, Hawaii, Hawaii Completed 1981 5,983,50111 61,800 
Keehi Lagoon, Oahu, Hawaii Completed 1956 3,348,00012 41,857 
Kikiaola Small Boat Harbor, Kauai, Hawaii Active 1981 193,000 --- 
Laupahoehoe Harbor, Hawaii, Hawaii Completed 1990 3,623,45013 
Manele Bay Small Boat Harbor, Lanai, Hawaii Completed 1986 372,00014 495,256 
Nawiliwili Harbor, Kauai, Hawaii Completed 1987 2,127,72415 10,116,779 
Nawiliwili Small Boat Harbor, Kauai, Hawaii Completed 1976 584,51316 30,707 
Ofu Small Boat Harbor, American Samoa Completed 1976 980,01817 800,760 
Pohoiki Bay, Hawaii, Hawaii Completed 1979 432,523 9--- 
Port Allen Harbor, Kauai, Hawaii Completed 1984 752,645 18 1,648,057 
Rota Harbor, CNMI Completed 1985 2,000,00019 436,200 
Saipan Small Boat Harbor, CNMI Active 1982 194,000 --- 
Tau Small Boat Harbor, American Samoa Completed 1985 1,991,569 20 546,600 
Waianae Small Boat Harbor, Oahu, Hawaii Completed 1979 1,940,01121 92,900 
Welles Harbor, Midway Island Completed 1950 2,448,056 22 2,111 
1Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $282,474 for Construction. 
2In addition, Contributed Funds of $1,239,364 for Construction. 
3Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $86,563 for Construction. 
'Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $231,437 for Construction. 
5In addition, Contributed Funds of $2,400,003 for Construction. 
6Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $410,077 for Construction and $84,388 for Operation and 
Maintenance. 
7In addition, Contributed Funds of $630,568 for Construction. 
8In addition, Contributed Funds of $201,282 for Construction. 
9Authorized by the Chief of Engineers. 
10In addition, Contributed Funds of $30,200 for Construction. 
11In addition, Contributed Funds of $62,102 for Construction. 
12Abandonment authorized by R & H Act of 1965 (HI) 98, 89th 
Congress, 1st Session). 
13Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $364,757 for Construction. 
14In addition, Contributed Funds of $370,845 for Construction. 
15In addition, Contributed Funds of $223,261 for Construction. 
16Authorized by the Chief of Engineers and completed in November 
1974. In addition, Contributed Funds of $405,471 for Construction. 
"1Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $61,953 for Construction. 
isIn addition, Contributed Funds of $200,000 for Construction. 
1"Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $774,373 for Construction. 
2 0Authorized by the Chief of Engineers. In addition, Contributed 
Funds of $54,034 for Construction. 
2 1In addition, Contributed Funds of $1,791,068 for Construction. 
2 2Completed in 1941 and Maintenance transferred to Department 
of Navy. 
36-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 36-D OTHER AUTHORIZED BEACH EROSION CONTROL PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Afono Area and Aoa Area, American Samoa Completed 1978 $ 254,0151 $--- 
Asquiroga Bay, Guam Completed 1986 227,1812 --- 
Haleiwa Beach, Oahu, Hawaii Completed 1967 240,148 -- 
Kaaawa Beach, Oahu, Hawaii Completed 1976 176,488 4 --- 
Kapaa Town, Kauai, Hawaii Completed 1977 158,916 --- 
Kekaha Beach, Kauai, Hawaii Completed 1981 999,996 --- 
Kihei Beach, Maui, Hawaii Completed 1972 154,313' --- 
Kualoa Regional Park, Oahu, Hawaii Terminated 1982 355,4728 -- 
Lepua Area, American Samoa Completed 1992 1,513,678 g --- 
Masefau Bay, American Samoa Completed 1992 436,252 2 
Matafao Shoreline, American Samoa Completed 1984 225,000 2 
Ofu Airstrip, American Samoa Completed 1987 189,500 --- 
Pago Pago Airport, American Samoa Completed 1984 174,9412 
Pago Pago to Nuuuli, American Samoa Deferred 1978 394,18710 
Poloa Area, American Samoa Completed 1978 136,040 11--- 
Sand Island, Oahu, Hawaii Completed 1981 301,87912 
Vatia Area, American Samoa Completed 1978 154,309 13 
Waikiki Beach, Oahu, Hawaii Deferred 1979 729,08714 183,000 
1Authorized by the Chief of Engineers. In addition, $209,549 in 
Contributed Funds. 
2Authorized by the Chief of Engineers. 
3In addition, $160,098 in Contributed Funds. 
4Authorized by the Chief of Engineers. In addition, $97,075 in 
Contributed Funds. 
5Authorized by the Chief of Engineers. In addition, $56,916 in 
Contributed Funds. 
6Authorized by the Chief of Engineers. In addition, $1,672,524 in 
Contributed funds. 
7Authorized by the Chief of Engineers. In addition, $1,672,524 in 
Contributed Funds. 
8Authorized by the Chief of Engineers and terminated in April 
1980 as a Circuit Court ruled sand mining to be illegal. In addition, 
$177,300 in Contributed Funds. 
9Authorized by the Chief of Engineers. In addition, $381,727 in 
Constibuted Funds. 
10Authorized by the Chief of Engineers. In addition, $312,480 in 
Contributed Funds. 
11Authorized by the Chief of Engineers. In addition, $101,547 in 
Contributed Funds. 
1 2Authorized by the Chief of Engineers. In addition, $255,728 in 
Contributed Funds. 
13Authorized by the Chief of Engineers. In addition, $132,075 in 
Contributed Funds 
14In addition $82,000 in Advanced Funds and $17,640 in Contributed 
Funds. 
36-8

TABLE 36-E 
PACIFIC OCEAN DIVISION 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to September 30, 1992 
Full Report 
See Annual Operations and 
Project Status Report for: Construction Maintenance 
Agana River, Guam Inactive 1989 $ 250,000 $ --- 
Asan Village, Guam Completed 1986 1,275,500 --- 
Hanapepe River, Kauai, Hawaii Completed 1967 784,8671 _ 
Iao Stream, Maui, Hawaii Completed 1985 12,285,000 28,239 
Kahawainui Stream, Oahu, Hawaii Completed 1990 3,910,0002 --- 
Kahoma Stream, Maui, Hawaii Completed 1990 10,665,758 s --- 
Kaneohe-Kailua Area, Oahu, Hawaii Completed 1985 25,552,400 --- 
Kaunakakai Stream, Molokai, Hawaii Completed 1950 73,478 s 
Kawainui Swamp, Oahu, Hawaii Completed 1967 1,265,567 --- 
Kuliouou Stream, Oahu, Hawaii Completed 1971 1,000,000 --- 
Namo River, Guam Completed 1982 2,416,314 5 --- 
Paauau Stream, Hawaii, Hawaii Completed 1985 1,978,514 --- 
Wailoa Stream and Tributaries, Hawaii, Hawaii Completed 1966 1,044,888 --- 
lIn addition, $11,953 in Contributed Funds. 
2Authorized by the Chief of Engineers. In addition, $459,001 in 
Contributed Funds. 
3In addition, $518,272 in Contributed Funds. 
4 Includes Non-Federal reimbursement of recreation construction 
cost of $5,668,300. In addition, $8,175 in Contributed Funds. 
sAuthorized by the Chief of Engineers. 
6Authorized by the Chief of Engineers. In addition, $540,335 in 
Contributed Funds. 
36-9

36-10 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 36-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report for: Authority Expended Expended 
Ala Wai Harbor, Oahu, Hawaii 1976 November 1986 $ 40,117 
PL 99-662 
Hana Small Boat Harbor, Maui, Hawaii 1967 November 1977 
HD #94-413 
Hanalei Small Boat Harbor, Kauai, Hawaii 1967 November 1981 
HD #97-59 
Hanapepe Bay, Kauai, Hawaii 1965 November 1986 
PL 99-662 
Heeia-Kea Small Boat Harbor, Oahu, Hawaii 1972 January 1990 1,481 
PL 99-662 
Kailua Small Boat Harbor, Oahu, Hawaii 1967 January 1990 
PL 99-662 
Kaimu Black Sand Beach, Hawaii, Hawaii 1975 July 1981 86,235- 
Director of 
Civil Works 
Kapaakea Homestead Flood Control, 1979 July 1981 221,500 
Molokai, Hawaii Director of 
Civil Works 
Kaunakakai Deep Draft Harbor, 1966 January 1990 133,188 292,441 
Molokai, Hawaii PL 99-662 
Kaunakakai Small Draft Harbor, --- January 1990 
Molokai, Hawaii PL 99-662 
Kewalo Harbor, Oahu, Hawaii 1976 September 1975 98,800 
Director of 
Civil Works 
Lahaina Small Boat Harbor, Maui, Hawaii 1977 January 1990 186,937 
PL 99-662 
Maunalua Bay Small Boat Harbor, 1972 January 1990 30,378 
Oahu, Hawaii PL 99-662 
Nawiliwili Deep Draft Harbor, Kauai, Hawaii --- January 1990 
PL 99-662 
Rainmaker Hotel, American Samoa --- November 1991 
PL 99-662 
Reeds Bay Small Boat Harbor, Hawaii, Hawaii 1967 January 1990 
PL 99-662 
Saipan Harbor, Northern Marianas --- November 1991 
PL 99-662 
1J 
J
i

TABLE 36-G (Cont'd) 
PACIFIC OCEAN DIVISION 
DEAUTHORIZED PROJECTS 
For Last 
Full Report Date Federal Contributed 
See Annual and Funds Funds 
Project Report for:. Authority Expended Expended 
Talofofo Bay Shore Protection, Guam --- August 1981 80,764 
Director of 
Civil Works 
Waimea Beach, Kauai, Hawaii --- November 1986 
PL 99-662 
Wake Island Harbor, Wake Island 1950 November 1986 
PL 99-662 
TABLE 36-H NAVIGATION ACTIVITIES 
PURSUANT TO SECTION 107, 
PUBLIC LAW 86-645, AS AMENDED 
(PREAUTHORIZATION) 
Study Fiscal Year Costs 
Apra Harbor, Guam $ 649 
Kahului Small Boat Harbor, Maui, Hawaii 30,574 
Kaumalapau Harbor, Lanai, Hawaii 20,000 
Mahukona (North Kohala), Hawaii, Hawaii 91,004 
TOTAL $142,227 
TABLE 36-I EMERGENCY STREAMBANK AND SHORELINE 
PROTECTION ACTIVITIES 
PURSUANT TO SECTION 14, 
PUBLIC LAW 79-526, AS AMENDED 
(PREAUTHORIZATION) 
Study Fiscal Year Costs 
Alii Drive, Hawaii, Hawaii $ 39,568 
Haaula Highway, Oahu, Hawaii 31,947 
Inarajan Shoreline, Guam 1,862 
Kaaawa Highway, Oahu, Hawaii 31,136 
Lauliifou Shoreline Protection, American Samoa 30,670 
Launiupoko, Maui, Hawaii 51,130 
Ofu Airstrip (West End) American Samoa 14,573 
Punaluu Highway, Oahu, Hawaii 27,990 
South Agat (Route 2), Guam 5,340 
Umatac Shoreline, Guam 3,106 
TOTAL $237,322 
36-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 364J BEACH EROSION CONTROL ACTIVITIES 
PURSUANT TO SECTION 103, 
PUBLIC LAW 87-874 
(PREAUTHORIZATION) 
Study Fiscal Year Costs 
Canneries to Breakers Point, American Samoa $ 3,027 
Lauliituai-Aumi, American Samoa 3,027 
Nua-Amaluia, American Samoa 3,027 
TOTAL $9,081 
TABLE 36-K FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, 
PUBLIC LAW 80-858, AS AMENDED 
(PREAUTHORIZATION) 
Study Fiscal Year Costs 
Agana Bayfront, Guam $ 34,865 
Commercial Port Road, Guam 68,002 
East Agana, Guam 110,852 
Kaelepulu Stream, Oahu, Hawaii 12,356 
Kawainui Marsh, Oahu, Hawaii 393 
Wailele Stream, Oahu, Hawaii 27,596 
Waihanau Stream, Molokai, Hawaii 5,005 
Total $259,069 
36-12

PORTLAND, OR DISTRICT* 
The territorial limits of the Portland District include the 
Pacific coastal drainage area of the State of Oregon, the 
portions of the States of Oregon and Washington which lie 
within the Columbia River watershed downstream of the 
Umatilla Bridge below McNary Dam, and south central 
Oregon west of the Malheur River and the Steens 
Mountains, but not including that part which drains into the 
Klamath Lake and River. 
IMPROVEMENTS 
Navigation Page 
1. Bonneville Navigation Lock, Bonneville Dam, 
OR and WA ............................. 37-2 
2. Chetco River, OR ........................ 37-2 
3. Columbia and Lower Willamette Rivers below 
Vancouver, WA and Portland, OR ........... 37-2 
4. Columbia River at Baker Bay, WA ........... 37-3 
5. Columbia River between Chinook, WA and 
Head of Sand Island ....................... 37-4 
6. Columbia River at the Mouth, OR and WA ... 37-4 
7. Columbia River between Vancouver, 
WA and The Dalles, OR ................... 37-4 
8. Columbia River, Seafarers Memorial, 
Hammond, OR ............................ 37-5 
9. Coos Bay, OR ............................ 37-5 
10. Coquille River, OR ....................... 37-6 
11. Depoe Bay, OR .......................... 37-6 
12. Navigation Work Under Special Authorization . 37-6 
13. Port Orfor d, OR ......................... 37-6 
14. Project Condition Surveys ................... 37-7 
15. Rogue River Harbor at Gold Beach, OR ...... 37-7 
16. Siuslaw River, OR ......................... 37-7 
17. Skipanon Channel, OR ................... 37-8 
18. Tillamook Bay and Bar, OR ................ 37-8 
19. Tongue Point, OR ......................... 37-8 
20. Umpqua River, OR ....................... 37-9 
21. Willamette River at Willamette Falls, OR ..... 37-9 
22. Yaquina Bay and Harbor, OR .............. 37-10 
Flood Control 
23. Applegate Lake, Rogue River Basin, OR ..... 37-10 
24. Blue River Lake, OR .................... 37-11 
25. Cottage Grove Lake, OR ............... 37-11 
26. Dorena Lake, OR ..................... 37-11 
27. Elk Creek Lake, Rogue River Basin, OR ..... 37-11 
28. Fall Creek Lake, OR ...................... 37-12 
29. Fern Ridge Lake, OR .................. .. 37-13 
30. Flood Control Work Under 
Special Authorization .................... 37-13 
31. Inspection of Completed Flood Control Projects 37-13 
32. Lower Columbia River Basin Bank Protection, 
OR and WA. .......................... 37-13 
33. Mill Creek, Salem, OR ................... .37-14 
34. Mt. St. Helens Sediment Control, WA ....... 37-14 
Page 
35. Scheduling Flood Control Reservoir Operations 37-14 
36. Willamette River Basin Bank Protection, OR . 37-14 
37. Willow Creek Lake, Heppner, OR .......... 37-15 
Multiple-Purpose Projects, Including Power 
38. Bonneville Lock and Dam - 
Lake Bonneville, OR and WA. ............. 37-15 
39. Columbia and Snake Rivers Ports Dredging, 
OR and WA ............................. 37-16 
40. Columbia River Juvenile Fish Mitigation 
Program (The Dalles Project), OR and WA... 37-16 
41. Cougar Lake, OR ...................... 37-17 
42. Detroit Lake- Big Cliff, OR .............. 37-17 
43. Green Peter-Foster Lakes, OR ........... 37-17 
44. Hills Creek Lake, OR ................... 37-18 
45. John Day Lock and Dam - 
Lake Umatilla, OR and WA ................ 37-18 
46. Lookout Point-Dexter Lakes, OR ......... 37-19 
47. Lost Creek Lake, Rogue River Basin, OR .... 37-19 
48. The Dalles Lock and Dam - 
Lake Celilo, WA and OR ................ 37-20 
General Investigations 
49. Surveys ............................... 
50. Collection and Study of Basic Data .......... 
51. Preconstruction Engineering and Design ..... 
37-21 
37-21 
37-21 
Tables 
Table 37-A Cost & Financial Statement ....... 37-22 
Table 37-B Authorizing Legislation ........... 37-29 
Table 37-C Other Authorized Navigation Projects 37-36 
Table 37-D Not Applicable 
Table 37-E Other Authorized Flood 
Control Projects ................ 37-37 
Table 37-F Other Authorized Multiple Purpose 
Projects, Including Power ......... 37-39 
Table 37-G Deauthorized Projects ........... 37-40 
Table 37-H Columbia and Lower Willamette River 
Below Vancouver, WA and 
Portland, OR ................. 37-41 
Table 37-I Navigation Work Under Special 
Authorization ................... 37-41 
37-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Table 37-J Project Condition Surveys ......... 37-41 
Table 37-K Willamette River at Willamette Falls, 
OR, Principal Features of Existing 
Canal and Locks ................. 37-42 
Table 37-L Flood Control Work Under Special 
Authorization .................. 37-42 
Table 37-M Flood Control Reservoir Operations 37-43 
Table 37-N Principal Data Concerning Navigation 
Lock Spillway Dam and Powerplant 37-43 
Navigation 
1. BONNEVILLE NAVIGATION LOCK, 
BONNEVILLE DAM, OR AND WA 
Location. On Columbia River 40 miles east of Portland, 
OR about 146 miles above mouth of river. 
Existing project. The existing lock chamber is 76 feet wide 
and 500 feet long with 24.2 feet depth of water over the sill. 
Construction of a new navigation lock just south of the existing 
lock was authorized in the FY 1985 Supplemental Appropriations 
Act, Public Law 99-88, August 15, 1985. Inland 
Waterways Trust Fund will fund 50 percent of the project 
cost in accordance with the Water Resources Development 
Act of 1986, Public Law 99-662, November 17, 1986. The 
new lock chamber will be 86 feet wide and 675 feet long with 
19 feet depth of water over the sill. Estimated cost for construction 
of the new navigation lock is $341,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New Work: Construction of 
the lock structure, electrical control systems and switchgear 
continued. Contract for fabrication of the floating guidewall 
was awarded. 
2. CHETCO RIVER, OR 
Location. Rises in Siskiyou Mountains of Coast Range at an 
elevation of 4,000 feet, flows for about 51 miles in a circuitous 
route, and empties into Pacific Ocean at Brookings, OR, 300 
miles south of entrance to Columbia River and 345 miles 
north of San Francisco Bay. (See National Oceanic and Atmospheric 
Administration Charts 18600 and 18203.) 
Existing project. Provides for two jetties at the mouth of 
the river. Modification of 1965 authorized an entrance channel 
120 feet wide by 14 feet deep; a barge turning basin about 
250 feet wide, 650 feet long, and 14 feet deep; and a small 
boat access channel 100 feet wide by 12 feet deep. Also 
authorized was a 450-foot extension of north jetty with an 
increase in elevation of existing portion and a protective dike 
about 1,800 feet long with a top elevation of 18 feet. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 6.9 feet 
and extreme is about 12 feet. Construction of jetties was 
completed December 1957. Removal of rock pinnacles and 
an abandoned bridge structure was accomplished in June 
1959. Under authorized modification of October 1965, two 
contracts were completed. Construction of entrance channel 
and extension of north jetty was completed in July 1969. 
Construction of a protective dike, turning basin and small 
boat access channel was completed in March 1970. 
Local cooperation. Fully complied with. 
Terminal facilities. The Port of Brookings has developed 
two large boat basins, one for commercial fishing boats and 
the other for sport boats, and a public boat launching ramp. 
There are four fish receiving docks and a sea-going barge 
dock for lumber loading and storage. There is also a privately 
owned marina and a Coast Guard Station. 
Operations during fiscal year. Maintenance: A total of 
27,802 cubic yards of material was removed by the U.S. hopper 
dredge Yaquina. The channel flusher Sandwick spent 5 
days working at the project. 
3. COLUMBIA AND LOWER WILLAMETTE 
RIVERS BELOW VANCOUVER, WA, AND 
PORTLAND, OR 
Location. The Columbia River rises in British Columbia, 
through which it flows for 425 miles. It enters the United 
States in northeastern Washington, and empties into the 
Pacific Ocean 645 miles north of San Francisco Bay and 160 
miles south of Strait of Juan DeFuca. Total length of river is 
1,210 miles. (See NOAA Charts 18520, 18521, 18522, 18523, 
18524, 18526, and 18531; also Geological Survey Map of 
Washington.) Willamette River rises in Cascade Range in 
western Oregon, flows northerly, and empties into Columbia 
River about 100 miles from the sea. Its length from source of 
Middle Fork is about 294 miles. Project embraces 103.5 miles 
of Columbia River below Vancouver, WA, and 14.6 miles of 
Willamette River below Portland, OR. (See NOAA Chart 
18526 and Geological Survey Map, State of Oregon.) 
Existing project. Provides for a channel 35 feet deep and 
500 feet wide from River Mile 106.5 to 105.5, the distance 
between existing highway and railroad bridges; a channel 40 
feet deep and 600 feet wide from Vancouver, WA, River Mile 
105.5 to mouth of Columbia River, River Mile 3; a turning 
basin at Vancouver, WA, 41 feet deep, 800 feet wide, and 
about 5,000 feet long; a turning basin at Longview, WA, 40 
feet deep, average width of 1,200 feet, and about 6,000 feet 
long; and a channel 40 feet deep in the Willamette River with 
varying widths of 600 to 1,900 feet from the mouth (River 
Mile 0) to Broadway Bridge (River Mile 11.6) which encompasses 
Portland Harbor area, subject to provisions that channel 
from mouth of Willamette River to turning basin at Vancouver, 
WA, be limited to 500 feet in width until need for 
additional width is demonstrated by developed traffic. Existing 
project also provides for auxiliary channels 10 feet deep 
and 300 feet wide near Cathlamet, WA; 30 feet deep and 300 
feet wide in St. Helens, (Oregon); and 30 feet deep and 500 
37-2

PORTLAND, OREGON DISTRICT 
feet wide connecting upper end of St. Helens Channel with 
main ship channel of Columbia; 24 feet deep and 200 feet 
wide along frontage of town of Rainier, OR, extended to its 
upper and lower ends to deep water in Columbia River, 8 feet 
deep and 150 feet wide from this depth in Columbia River 
through old mouth of Cowlitz River to a point about 3,000 
feet upstream from present terminus of harbor line; a channel 
from Longview Port dock downstream along pierhead 
line and past Weyerhaeuser Timber Co. plant at Longview to 
a connection with main ship channel below Mount Coffin, the 
downstream 2,400 feet of this channel to be 30 feet deep and 
300 feet wide and remainder to be 28 feet deep and 250 feet 
wide; construction of a small boat mooring basin at Astoria, 
OR, to include a sheet pile, sand-filled breakwater about 
2,400 feet long with a 30-foot roadway along its full length, 
and steel pile shore wings totaling about 1,460 feet long and 
for stone-and-pile dikes and revetments. Plane of reference 
in estuary from mouth of Harrington Point is mean lower low 
water; thence to Portland and Vancouver, adopted low water. 
Tidal range between mean lower low water and mean higher 
high water at mouth of Columbia is about 8 feet, and at 
Portland and Vancouver, about 3 feet at low stage of rivers. 
Extreme tidal ranges are about 13 and 3 feet, respectively. 
Annual freshets have little effect on stage of tide at mouth of 
Columbia; at Portland and Vancouver, they average about 12 
feet, while highest know reached a stage of 33 feet above 
water at Portland. 
Work on the 40-foot channel in Columbia River from 
Portland, OR, and Vancouver, WA, to the sea was completed 
in 1976. Auxiliary channel in vicinity of Longview was completed 
in 1949, and improvement of mouth of Cowlitz River 
and small boat mooring basin at Astoria were completed in 
1950. Project depths are maintained all year except for the 
period immediately following the annual freshet in May- 
June when shoaling occurs at several locations. Timing of 
vessel movement with tidal fluctuations permit maximum 
draft conditions. In Columbia and Willamette Rivers between 
mouth and Broadway Bridge at Portland a depth of 40 
feet at low tide and 42 feet at high tide is practicable all year. 
In Columbia River between mouth of Willamette river and 
Vancouver, WA, depths of 40 and 42 feet at low and high tide, 
respectively, are practicable all year. (For details relating to 
previous project, see pages 1995 and 1998 of Annual Report 
for 1915 and page 1746 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 37-3 of FY 1981 Annual Report. 
Terminal facilities. At Portland, OR, there are six Port of 
Portland terminals consisting of 43 berths equipped to handle 
general cargo, bulk cargo, lumber, automobiles, lift-on-liftoff 
and roll-on-roll-off containers, and breakbulk vessels. 
The Port of Portland owns and operates a major ship repair 
yard, which includes the West Coast's largest, and the world's 
third largest, floating dry dock. Also available in the harbor 
area are privately operated facilities for receiving, storing and 
outloading petroleum, wood chips, grain, logs, sand and 
gravel, cement, and steel products. 
At Astoria, OR, there is a terminal with facilities for receiving 
and handling all types of general cargo. 
At Vancouver, WA, there are municipal facilities capable 
of berthing five ships simultaneously. Each berth is completely 
outfitted with mechanical and lift facilities for receiving 
and handling all types of cargo. The port has a low dock to 
handle roll-on-roll-off and side-port discharging vessels. 
The grain terminal has a storage capacity of 4,500,000 bushels. 
Port of Longview has a public terminal on Columbia River 
and a privately owned grain elevator with a capacity of 
6,900,000 bushels. This port also has a heavy lift facility, with 
a capacity of 600 tons. 
Port of Kalama has two berthing areas, one port owned and 
one private. 
At other locations on Columbia River between Portland 
and Columbia River entrance there are sufficient private 
facilities to accommodate river vessels and fishing craft. 
These facilities, with planned extensions, are considered adequate 
for existing commerce. (For details, see Port Series 
Nos. 33 and 34, Corps of Engineers, published in 1974 and 
1975 respectively.) 
Operations during fiscal year. Maintenance: Regular 
maintenance continued through the year. A total of 
4,876,355 cubic yards of material was removed. The U.S. 
hopper dredge Essayons removed 2,170,551 cubic yards, the 
U.S. hopper dredge Yaquina removed 414,114 cubic yards, 
the pipeline dredge Oregon removed 2,211,150 cubic yards, 
and the contract dredge Newport removed 80,540 cubic 
yards. The channel flusher Sandwick spent 34 days working at 
the project. 
4. COLUMBIA RIVER AT BAKER BAY, WA 
Location. Baker Bay is a shallow body of water about 15 
square miles in extent on the north side of Columbia River 
near its mouth. The bay is separated from the river by Sand 
Island, a low-lying sand bar only a few feet above high tide 
level. (See NOAA Chart 18521.) 
Existing project. A mooring basin 10 and 12 feet deep, 
about 20 acres in extent with protecting breakwaters; and a 
west channel 16 feet deep and 200 feet wide for the first 2000 
feet, then 16 feet deep and 150 feet wide to the boat basin; a 
channel east of Sand Island to Port of Ilwaco, a distance of 
about 4 miles. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean higher 
high water is about 8 feet, and extreme about 13 feet. 
Channel extending through easterly passage of Sand Island 
was completed in 1934. This portion of authorized project is 
not passable and is not maintained at the present time. 
Dredging west channel to 8 feet was accomplished September 
1948, Deepening west channel to 10 feet, and boat basin 
and breakwater construction at Ilwaco, WA, was finished 
December 1957, and again, deepening of the west channel to 
16 feet completed in August 1985 under Section 107, finished 
the project. 
Local cooperation. Fully complied with. 
Terminal facilities. Wharves, floats, ramps, and berths, for 
fishing craft, barges and tow-boats. Small-boat basin and 
protecting breakwater provides moorings for numerous fish- 
37-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
ing and recreational craft all year. Facilities are considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
surveys were performed. 
5. COLUMBIA RIVER BETWEEN CHINOOK, 
WA, AND HEAD OF SAND ISLAND 
Location. At easterly end of Baker Bay, lying on north side 
of Columbia River near mouth. (See Coast and Geodetic 
Survey Chart 6151.) 
Existing Project. Channel 10 feet deep and 150 feet wide, 
extending from head of Sand Island to Chinook; a turning and 
mooring basin at upper end of channel, 10 feet deep, 660 feet 
long, and ranging from 275 to 500 feet wide; reconstruction of 
easterly 393 feet of existing breakwater; and extension of 
existing breakwater easterly and thence northerly to connect 
with shore in vicinity of Portland Street, Chinook, WA. Tidal 
range between mean lower low water and mean higher high 
water is about 8 feet and extreme about 13 feet. 
Project as originally authorized was completed in 1940. The 
10-foot channel depth modification was accomplished September 
1958. Rehabilitation of existing breakwater was completed 
September 1962. 
Local cooperation. Fully complied with. 
Terminal facilities. Chinook Packing Company owns a 
wharf for receiving fresh fish, and one additional fish buying 
company is located at Chinook. A portion of wharf is also 
used as a public landing. At upper end of channel there is a 
turning and mooring basin with facilities for mooring 350 
fishing and recreational craft. Adequate terminal and mooring 
facilities include a public launching ramp, hoist with 
10-ton capacity and suitable supply facilities. 
Operations during fiscal year. Maintenance: Contract 
clamshell dredge DB Hawk removed 91,000 cubic yards. 
6. COLUMBIA RIVER AT THE MOUTH, OR 
AND WA 
Location. The Columbia River entrance is 645 miles north 
of San Francisco Bay. Project is about 120 miles downstream 
of Portland, OR, and Vancouver, WA. For description of 
Columbia River see Section 4. 
Existing project. Provides for a one-half- mile-wide channel 
across a bar 55 feet deep (mean lower low water) for the 
northernmost 2,000 feet, and 48 feet deep (mean lower low 
water) along the southern 640 feet, to be secured by two 
rubblemound jetties, spur jetty "A" on the north shore and by 
dredging. The north jetty is about 2.5 miles long and the south 
jetty about 6.6 miles long, spur jetty "A" is about 0.3 miles 
long. Tidal range on bar between mean lower low water and 
mean higher high water is about 8 feet, and extreme about 13 
feet. 
The originally authorized project depth of 40 feet was completed 
in 1918; south jetty completed in 1914 and north jetty 
in 1917. A spur jetty (jetty "A") was completed in 1939 (repaired 
in 1961) for the purpose of channel stabilization. Spur 
jetty "B" currently is classified "inactive." Dredging of the 
48-foot bar channel started April 1956 was completed in 
September 1957. South jetty rehabilitation started June 1962 
was completed September 1964. North jetty rehabilitation 
started January 1965 was completed April 1965. Additional 
rehabilitation of the south jetty was initiated in May 1982 and 
completed in September 1982. Deepening bar channel to 55 
feet completed September 1984. Project dimensions were 
available at end of fiscal year. (For details relating to previous 
projects, see page 1999, Annual Report for 1915 and page 
1740 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Local interests 
contributed $500,000 toward construction of the north jetty 
which was completed in 1917. 
Operations during fiscal year. Maintenance: A total of 
5,129,304 cubic yards of material was removed. The U.S. 
hopper dredge Essayons removed 4,229,959 cubic yards of 
material, and the contract dredge Newport removed 899,345 
cubic yards. 
7. COLUMBIA RIVER BETWEEN 
VANCOUVER, WA, AND THE DALLES, OR 
Location. On Columbia River, between Interstate Bridge 
at Vancouver, WA, 106.5 miles above mouth and The Dalles, 
OR, mile 191, a distance of 84.5 miles. For description of 
Columbia River, See Section 4, "Columbia and Lower Willamette 
Rivers Below Vancouver, WA, and Portland, OR." 
Existing project. Channel 27 feet deep at low water and 300 
feet wide between Vancouver, WA, and The Dalles, OR, 
84.5 miles; a channel 10 feet deep at low water and 200 feet 
wide at upstream entrance to Oregon Slough, OR; a suitable 
turning basin adjacent to site of port development in vicinity 
of Camas and Washougal, WA; a boat basin at Hood River, 
OR, 500 by 1,300 feet and 10 feet deep at normal Bonneville 
pool level, with a connecting channel of same depth to deepwater, 
and a protecting breakwater on easterly side; a barge 
channel to waterfront at Bingen, WA, 10 feet deep at normal 
Bonneville pool level, 200 feet wide and about 1 mile long, 
and an access channel 7 feet deep at normal Bonneville pool 
level, 100 feet wide and about 1,000 feet long, to a natural 
mooring basin for small boats near east end of channel; and 
construction of The Dalles small boat basin, to provide a 
breakwater and shear boom protected basin about 400 by 800 
feet in size with depth of 8 feet below a pool elevation of 72.5 
feet at mean sea level. Tidal range between mean lower low 
water and mean higher high water at Vancouver is about 3 
feet and at Bonneville about 0.2 foot at low stages of the river. 
Extreme tidal ranges are about 4 feet and 0.4 foot, respectively. 
Existing project is complete. Construction of The Dalles 
small boat basin, was completed in 1949. Channel dredging at 
upper end of Oregon Slough was accomplished in 1957. Project 
depth of 27 feet between Bonneville and The Dalles, 
OR, was achieved April 1959. The 27-foot channel depth 
between Vancouver, WA, and Bonneville, OR, was completed 
May 1938. Improvement of lower entrance of Bonneville 
Dam lock was completed in May 1961. At the present 
37-4

PORTLAND, OREGON DISTRICT 
time, the channel is maintained to a depth of 16 feet, which is 
adequate for using traffic. Construction of a boat basin at 
Hood River, OR, and of Camas-Washougal, WA, turning 
basin was accomplished February 1962. Construction of a 
barge channel in Columbia River near Bingen, WA, was 
completed September 1963. Small boat recreation channel 
100 feet wide 6 feet deep at South Channel Government 
Island completed 1985 under section 107. 
Local cooperation. Fully complied with. 
Terminal facilities. At Vancouver, WA, upstream of Interstate 
Highway bridge at River Mile 108.1 on site of former 
shipyard are numerous ship-building facilities equipped with 
railway and river moorage facilities. Also in this area are a 
paper-storage warehouse with barge slip, two boat building 
businesses, and a storage dock with gantry crane. Sites are 
available for development to suit lessee. 
At Camas, Wa, about 13.5 miles upstream from Vancouver, 
there is a private wharf used for transfer of papermill 
supplies and paper to and from barges, and facilities for 
discharging bulk oils from barges. 
At Port of The Dalles (mile 44 above Bonneville) there is a 
municipal wharf 125 by 1,100 feet for use by tugs and barges. 
There is a one-story timber and corrugated iron warehouse, 
94 by 461 feet, on this wharf. A private elevator with a capacity 
of 40,000 bushels and a public elevator of 1,113,800- 
bushel capacity for handling bulk grain to barges are also at 
The Dalles. Public elevator has rail, truck, and water connections. 
There is a port owned rail connection about threefourths 
mile below municipal wharf where certain types of 
cargo may be handled between railroad cars and barges. 
At numerous locations along the entire waterway there are 
facilities for transfer of logs to water from trucks and public 
and private boat basins. Facilities are considered adequate 
for present commerce. 
Operations during fiscal year. Maintenance: The U.S. 
hopper dredge Yaquina removed 48,963 cubic yards of material. 
8. COLUMBIA RIVER, SEAFARERS 
MEMORIAL, HAMMOND, OR 
Location. The memorial will be located at Point Adams, in 
the City of Warrenton, OR, at River Mile 8.5 on the Columbia 
River approximately 50 yards off shore and adjacent to an 
existing Corps of Engineers pile dike. 
Existing project. None. 
Local cooperation. A Local Cooperation Agreement 
(LCA) with the local sponsor, City of Warrenton, OR, is 
being developed. This LCA will require the sponsor to pay 
for all costs above the authorized $150,000 for engineering, 
design, acquisition and construction of a support structure to 
serve as the foundation for the Seafarers Memorial. In addition, 
the sponsor is providing the statue for which the foundation 
structure is being built. 
Operations during fiscal year. All work has been suspended 
until the LCA has been approved by all parties and 
the local sponsor has raised sufficient funds for purchase of 
the statue and any costs above the $150,000 limit for the 
support structure. 
9. COOS BAY, OR 
Location. On Oregon coast 200 miles south of mouth of 
Columbia River and 445 miles north of San Francisco Bay. It 
is about 13 miles long and 1 mile wide, with an area at high 
tide of about 15 square miles. (See NOAA Charts 18580 and 
18587.) 
Existing project. Two rubblemound, high- tide jetties at 
entrance; a channel across the outer bar 45 feet deep and 700 
feet wide, reducing gradually to 35 feet deep and 300 feet 
wide near River Mile 1 and continuing to about mile 9; thence 
a channel 35 feet deep and generally 400 feet wide to mile 15; 
an anchorage area 35 feet deep, 800 feet wide, and 1,000 feet 
long at Empire (River Mile 5.5); turning basins at North Bend 
(River Mile 12.5) and Coalbank (River Mile 14.7) 35 feet 
deep, 650 feet wide and 1,000 feet long; a channel 22 feet 
deep and 150 feet wide from Smith's Mill (River Mile 15) to 
Millington (River Mile 17); a small boat basin, about 500 by 
900 feet at Charleston, with a connecting channel, 16 feet 
deep, 150 feet wide and 6,200 feet long, to deep water in Coos 
Bay, and construction of a protecting breakwater and bulkhead. 
Plane of reference is mean lower low water. Tidal range 
between mean lower low water and mean higher high water is 
7 feet and extreme is about 11 feet at both the entrance and at 
Coos Bay. 
South jetty was completed in 1928, north jetty in 1929, and 
24-foot channel in 1937. The south jetty was restored in 1941 
and 1942 by construction of a concrete cap for full length of 
the jetty. Excavation of channel to 30 feet deep and generally 
300 feet wide from entrance of Isthmus Slough was completed 
in 1951. Dredging outer bar channel to a depth of 40 
feet, decreasing to 30 feet at Guano Rock was completed in 
1952. Construction of the Charleston Channel and smallboat 
basin was completed in September 1956. Rehabilitation 
of south jetty was started in June 1962 and completed December 
1963. Repair of north jetty was completed in August 
1989. Construction of the deeper and wider channel to mile 
15 was completed in 1979. Deepening of Charleston channel 
and turning basin completed in 1985 under Section 107. (For 
details relating to previous projects, see page 1987 to Annual 
Report for 1915 and page 1728 of Annual Report for 1938.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 37-5 of FY 1981 Annual Report. 
Terminal facilities. At North Bend there is a municipal 
dock 649 feet long fronting on channel, about 2,380 feet of 
privately owned mill docks, and three oil receiving terminals 
in vicinity. 
At Coos Bay there is a privately owned dock with a frontage 
of 1,345 feet, open to the public on equal terms; several small 
landings for fishing and harbor craft; and three lumber docks 
with 1,300,576, and 500-foot frontages, respectively. 
In the North Spit industrial area, there is one woodchip 
loading facility having a frontage of 1200 feet and a smaller 
T-dock operated by the Port of Coos Bay. 
37-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
At Eastside, on Isthmus Slough, there is a 200-foot dock. 
At Empire there is a privately owned lumber dock with 
frontage of 510 feet, and an oil terminal, owned by Port of 
Coos Bay, for receipt of petroleum products by barge. A 
barge slip also owned by the Port was completed in 1986. 
At Charleston there are wharves, for receipt of fresh fish 
and shellfish and a large seafood receiving and processing 
plant. There are also two municipally owned small-boat basins, 
open to all on equal terms, capable of mooring 250 
fishing and recreation craft. Servicing facilities for small craft 
are available at all facilities, and public launching ramps have 
been constructed in Charleston area by private interests. A 
privately owned floating moorage on Joe Ney Slough has 
facilities for mooring about 50 fishing vessels. 
At Jordan Cove area there is a dock, 248 feet long, for wood 
chip ships. 
These facilities are considered adequate for existing commerce. 
(For details see Port series No. 33, Corps of Engineers, 
published in 1975.) 
Operations during fiscal year. Maintenance: A total of 
1,394,391 cubic yards of material was removed. U.S. hopper 
dredge Yaquina removed 322,890 cubic yards, the U.S. hopper 
dredge Essayons removed 571,501 cubic yards, and the 
contract clamshell dredge Super Scoop removed 500,000 cubic 
yards. The sand-bypasser Sandwick displaced sand from 
shoal areas in Charleston entrance channel. 
10. COQUILLE RIVER, OR 
Location. Rises in Coast Range, flows generally westerly 
for about 100 miles, and empties into Pacific Ocean at Bandon, 
OR, 225 miles south of mouth of Columbia River and 
420 miles north of San Francisco Bay. (See NOAA Charts 
18580 and 18186.) 
Existing project. Two rubblemound high- tide jetties at 
river mouth, south jetty 2,700 feet long and the north, 3,450 
feet long; and a channel 13 feet deep at mean lower low water 
and of suitable width from the sea to a point 1 mile above old 
Coquille River Lighthouse, and snagging to State highway 
bridge at city of Coquille. Mean lower low water is plane of 
reference. Tidal range between mean lower low water and 
mean higher high water at mouth is 7 feet and extreme about 
10 feet. 
Jetties were completed in 1908 and entrance channel in 
1933. North jetty was reconstructed in 1942 and a 750-foot 
extension to easterly end was constructed in 1951. South jetty 
was repaired in 1954 and north jetty in 1956. Coquille Lighthouse 
rehabilitation was completed June 21, 1976. Port of 
Bandon constructed boat basin facility in conjunction with 
protective breakwater and entrance channel construction in 
1985, under Section 107. (For details relating to previous 
projects, see page 1986 of Annual Report for 1915 and page 
1727 of Annual Report for 1938.) 
A plan to deepen the entrance channel of the Coquille 
River from 13 feet to 18 feet was approved in May 1988. 
Construction is planned for FY 93. 
Local cooperation. None required. However, restoration of 
lighthouse using Code 710, Recreation Facilities at Completed 
Projects, funding required 50 percent cost sharing with 
non-Federal sponsor (Oregon State Parks). 
Terminal facilities. At Bandon: A privately owned mill 
dock used exclusively for shipping lumber on coastwise vessels, 
a publicly owned wharf, and a small-boat basin open to 
all on equal terms. 
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 93,732 cubic yards of material from 
entrance channel. 
11. DEPOE BAY, OR 
Location. Harbor on Oregon coast 100 miles south of 
mouth of Columbia River. (See Coast and Geodetic Survey 
Chart 5902.) 
Existing project. Two breakwaters north of entrance; an 
entrance channel 8 feet deep and 50 feet wide; an inner basin 
750 feet long, 390 feet wide and 8 feet deep with retaining 
wall along easterly side; and a stone spending beach. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 8 feet 
and extreme is about 12 feet. Project as originally authorized 
was completed in 1939 and project modifications, enlarging 
the basin and deepening to 8 feet, was accomplished in June 
1952 and August 1966. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, in inner basin, consist of 
landings and floats to accommodate operators of excursion 
and commercial fishing boats. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Monitored 
the concrete retaining wall for deterioration. 
12. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public Law 
86-645 (preauthorization): 
Construction of a channel and turning basin at Tongue 
Point, OR is discussed in Section 19. 
Feasibility and reconnaissance studies continued. See Table 
37-I for expenditures under Section 107 during the fiscal 
year. 
Mitigation of Shore Damages pursuant to Section 111, 
Public Law 90-433 (preauthorization): 
Feasibility and reconnaissance studies continued. See Table 
37-I for expenditures under Section 111 during the fiscal 
year. 
13. PORT ORFORD, OR 
Location. On Oregon coast 250 miles south of Columbia 
River entrance and 390 miles north of San Francisco Bay. 
(NOAA Chart 18203 and Geological Survey Quadrangle, 
Port Orford, OR) 
37-6

PORTLAND, OREGON DISTRICT 
Existing project. Improvement of harbor by 55-foot extension 
of existing locally constructed breakwater and dredging 
of a turning basin, 340 feet long, 100 feet wide and 16 feet 
deep. Breakwater was completed October, 1968. Turning 
basin was completed September 1971. 
Local cooperation. Fully complied with. 
Terminal facilities. A dock which is a timber piling structure 
about 210 by 70 feet, equipped with hydraulic crane for 
lifting boats from the water to dock for repairs and/or storage 
and removing fish catches from boats. Expansion of the dock 
structure to 210 x 220 feet is complete. The installation of the 
second hydraulic crane was completed in FY 1986. About 150 
fishing and private boats use this dock each year. 
Operations during fiscal year. Maintenance: During the 
summer months the sand-bypasser Sandwick worked 41 days, 
and the contract dredge Kerr removed 587 cubic yards. 
14. PROJECT CONDITION SURVEYS 
Surveys were conducted during the fiscal year at a cost of 
$121,024; (See Table 37-J). 
15. ROGUE RIVER HARBOR AT GOLD 
BEACH, OR 
Location. Rises in Cascade Range in southwestern Oregon; 
flows westerly through Coast Range, and empties into Pacific 
Ocean 264 miles south of mouth of Columbia River and 381 
miles north of San Francisco Bay. (See NOAA Chart 18202.) 
Existing project. Two jetties at entrance, and a channel 13 
feet deep and 300 feet wide from ocean to a point immediately 
below State highway bridge, about 1 mile, including 
widening channel at a point about 0.25 mile below bridge to 
form a turning basin 13 feet deep, 500 feet wide, and 650 feet 
long. At request of local interests, turning basin was located 
in south portion of estuary downstream from a point 0.25 mile 
below bridge. This change was effected to permit adequate 
terminal facilities to be constructed adjacent to turning basin. 
Mean lower low water is plane of reference. Range of tide 
between mean lower low water nd mean higher high water is 
7 feet, and extreme about 14 feet. 
Project as authorized has been completed. Construction of 
two jetties at entrance was completed September 1960. 
Dredging river channel by contract and entrance bar by government 
plant was completed October 1961. North jetty rehabilitation 
along channel side was completed October 1966. 
Breakwater construction and dredging, under contract 
awarded in September 1964, was 17 percent accomplished 
when flood of December 1964 destroyed all completed 
works. Contract was terminated as further construction at 
that location was considered Unfeasible. Bank protection 
work at Wedderburn location was completed in October 
1972. A breakwater, constructed by Port of Gold Beach, was 
completed during 1973. In 1985, three pile dikes, located on 
the south side of channel oceanward of the boat basin entrance, 
were completed. 
Local cooperation. Fully complied with. 
Terminal facilities. There are various landings for fishing 
and recreational craft. At Wedderburn, across river from 
Gold Beach, is a facility to accommodate excursion passengers 
and small freight items destined for various private landings 
between Wedderburn and Agness, OR. Facilities considered 
adequate for existing commerce. 
Operations during fiscal year. Maintenance: A total of 
111,188 cubic yards of material was removed. The U.S. hopper 
dredge Yaquina removed 32,747 cubic yards, and the 
contract dredge Nehalem removed 78,441 cubic yards. The 
channel flusher Sandwick spent 20 days working at the project. 
16. SIUSLAW RIVER, OR 
Location. Rises in coast range, flows about 110 miles westerly 
and empties into Pacific Ocean about 160 miles south of 
entrance of Columbia River and 485 miles north of San 
Francisco Bay, CA. (See NOAA Charts 19583 and 18580.) 
Existing project. Provides for 2 high-tide, rubblemound 
jetties 750 feet apart at the outer end, the north jetty 8,390 
feet long (600 feet unconstructed) and the south jetty 4,200 
feet long; an entrance channel 18 feet deep and 300 feet wide 
from deep water in ocean to a point 1,500 feet inside the 
outer end of existing north jetty; thence a channel 17 feet 
deep, 200 feet wide with additional widening at bends, and 
about 5 miles long, to a turning basin, 16 feet deep, 200 feet 
wide with additional widening at bends, and about 5 miles 
long, to a turning basin, 16 feet deep, 400 feet wide, and 600 
feet long, opposite Siuslaw dock at Florence; a channel 12 
feet deep, 150 feet wide from Florence to mile 16.5; and at 
River Mile 15.5 a turning basin 12 feet deep, 300 feet wide, 
and 500 feet long. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean 
higher high water at mouth of river is 7 feet and extreme 
about 11 feet. During low stages of river, tidal effect extends 
to Mapleton, 20.5 miles above mouth. (For details relating to 
previous project, see page 1988 of Annual Report for 1915.) 
A modification to the existing project was authorized by 
Public Law 96-367, October 1, 1980. North and south jetty 
modifications were completed in FY 85. Modifications provide 
for extending the north and south jetties by 1,900 and 
2,300 feet respectively. The jetty extensions terminate at 
approximately the minus 25-foot contour. Spur jetties were 
constructed on each jetty extension to reduce longshore currents 
from transporting material around the heads of the 
jetties. Each spur jetty is 400 feet long and originate approximately 
900 feet shoreward of the jetty head. The north jetty 
spur is oriented 45 degrees to the north of the existing jetty 
alignment and the south jetty spur 45 degrees to the south of 
the jetty alignment. Work on the extension of the north and 
south jetties was completed on 31 December 1986. 
Local cooperation. Fully complied with. 
Terminal facilities. Port dock at Florence, 150 feet wide 
and 350 feet long, is about 5.3 miles above river entrance and 
accommodates a fish-receiving station at east end of wharf 
which maintains a 2-ton capacity winch and supplies gasoline, 
oil and ice to fishermen. Other facilities at Florence consist of 
various floatways which provide docking facilities for fishing 
37-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
vessels and other small craft and a floating dock with accommodations 
for 75 commercial fishing vessels. Adjacent to 
commercial basin is mooring basin with accommodations for 
200 sport boats of all sizes. 
Modern docks for loading ocean-going barges with packaged 
lumber is maintained at Mapleton and owned by the 
Davison Lumber Company. 
There are also a number of private landings and log booms 
between Cushman and Mapleton to accommodate river traffic. 
These facilities are considered adequate for existing traffic.
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 244,344 cubic yards of material. 
17. SKIPANON CHANNEL, OR 
Location. In tidal waterway extending south 2.7 miles from 
deep water in Columbia River. Channel enters Columbia 
about 10 miles above mouth and 4 miles below Astoria, OR. 
(See NOAA Chart 18523.) 
Existing project. Channel 30 feet deep and generally 200 
feet wide extending from deep water in Columbia River to 
railroad bridge at Warrenton, OR, distance of 1.8 miles, 
turning basin of same depth, mooring basin 12 feet deep at 
mean lower low water at Warrenton, OR, and channel 7 feet 
deep, generally 40 feet wide, with increased widths at log 
dumps and terminals, for 4,500 feet via cutoff channel above 
railroad bridge. Channel is maintained to 16 feet which is 
adequate for user traffic. Mean lower low water is plane of 
reference. Tidal range between mean lower low water and 
mean higher high water is about 8 feet, extreme is about 13 
feet. 
Project as authorized is complete. Dredging river channel 
and turning basin was completed in 1939. Construction of 
small-boat mooring basin at Warrenton, OR, was completed 
October 1957, and fill stabilization work was accomplished in 
August 1958. 
Local cooperation. None required. 
Terminal facilities. City of Warrenton owns wharf with a 
300-foot frontage open to pubic on equal terms. One privately 
owned cannery wharf with a 300-foot frontage is used 
for unloading fish and handling fish nets. One privately 
owned boatyard has floats and moorage facilities for use by a 
maximum of 80 small boats. Small-boat basin has facilities 
for numerous fishing and recreation craft, and a privately 
owned lumber mill has a barge loading facility for chips and 
lumber. Facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: A condition 
survey was performed. 
18. TILLAMOOK BAY AND BAR, OR 
Location. Bay is on Oregon coast about 50 miles south of 
mouth of Columbia River. (See NOAA Charts 18520 and 
18558.) 
Existing project. Provides for a jetty about 5,700 feet long 
on north side of entrance and a jetty 8,000 feet long on south 
side; a channel through bar 18 feet deep and of such width as 
can be practically and economically obtained; for a channel 
200 feet wide and 18 feet deep from deep water in bay to 
Miami Cove; and for initial dredging to 12 feet deep of a 
small-boat basin and approach thereto at Garibaldi, OR. 
Project also provides for improvement of Bayocean Peninsula, 
OR, by construction of sand and rockfill dike 1.4 miles 
long, on alignment extending between Pitcher Point and 
town of Bayocean. Mean lower low water is plane of reference. 
Tidal range between mean lower low water and mean 
higher high water is 8 feet, extreme is about 14 feet. Hobsonville 
Channel portion of project is inactive. 
Except for construction of Hobsonville Channel portion, 
classified inactive, channels were completed in 1927, north 
jetty in 1933, improvement of Bayocean Peninsula in 1956 
and small-boat basin in 1958. Rehabilitation of the north 
jetty was completed in 1965. South jetty construction was 
initiated in 1969, extended in 1974, and completed to the 
authorized 8,000 feet in 1978. 18 foot channel to Miami Cove 
is inactive due to mill closure. (For details relating to previous 
projects, see page 1989 of Annual Report for 1915 and 
page 1474 of Annual Report for 1936.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 37-9 of FY 1981 Annual Report. 
Terminal facilities. At Garibaldi: A facility owned by the 
Port of Bay City, for shipping lumber and receiving logs, a 
public landing suitable for mooring fishing vessels, towboats, 
and other craft. Small-boat basin has adequate facilities for 
mooring fishing and recreational craft. A privately owned 
boat ramp and moorage is available for recreational craft. 
At Bay City: A privately owned wharf used exclusively for 
receipt of fresh fish and shellfish. Facilities considered adequate 
for existing commerce. 
Operations during fiscal year. Maintenance: Condition 
studies and miscellaneous inspections performed. 
19. TONGUE POINT, OR 
Location. The northwest corner of Oregon at river mile 18 
on the Columbia River, five miles east of the city of Astoria, 
OR. 
Existing Project. Tongue Point is located adjacent to the 
congressionally authorized Columbia River 40-foot deepdraft 
navigation channel. The harbor and port facilities were 
first developed in the 1930's as a U.S. naval base. After 
World War II, the site served as a temporary berthing area. 
The improvements, however, have not been actively maintained 
for 25 years. The State of Oregon obtained the majority 
of the port development in 1980 from the Federal Government, 
including five finger piers. The remaining acres and 
three finger piers are still Federally owned and used by the 
U.S. Department of Commerce as a Job Corps Center and 
the U.S. Coast Guard as a lifeboat station. Construction of a 
34-foot deep by 350-foot wide channel 1.75 miles long from 
the existing Columbia River channel to Tongue Point docks 
was authorized in July 1989 under Section 107 of the 1960 
River and Harbor Act, as amended. A 25-foot deep (mllw)by 
37-8

PORTLAND, OREGON DISTRICT 
1,050-foot wide turning basin was also constructed and is 
located near the piers.The cost for preparation of the plans 
and specifications and construction of the project was 
$4,293,103, of which $2,576,117 was Federal and $1,716,986 
non-federal. The non-federal cost includes $19,159 for inkind 
services. 
Local cooperation. The State of Oregon, acting through 
the Division of State Lands, was the non-federal sponsor. 
Terminal facilities. The State of Oregon owns five 30-foot 
wide concrete finger piers between 1,300 and 1,500 feet long. 
The site is served by a 12-inch water main, and electricity and 
sewage lines also exist at the site. Additional development of 
these existing port facilities, which will facilitate the movement 
of an estimated 225,000 automobiles annually, is the 
responsibility of the local sponsor. 
Operations during fiscal year. New Work: The project was 
fiscally completed. 
20. UMPQUA RIVER, OR 
Location. Rises in Cascade Range, flows westerly about 120 
miles, and empties into Pacific Ocean 180 miles south of 
Columbia River and 465 miles north of San Francisco Bay. 
(See NOAA Charts 18580 and 18584.) 
Existing project. A jetty on north side of entrance about 
8,000 feet long, a south jetty 4,200 feet long extending to a 
point 1,800 feet south of outer end of north jetty; dredging to 
provide a usable entrance channel 26 feet deep, and a river 
channel 22 feet deep and 200 feet wide, from mouth to 
Reedsport, a distance of about 12 miles with a turning basin at 
Reedsport 1,000 feet long, 600 feet wide, and 22 feet deep; 
deepening of channel at Winchester Bay to 16 feet deep by 
100 feet wide for 3,100 feet, then adding 16 feet deep by 100 
feet wide for 500 feet, and 12 feet deep by 75 feet wide for 950 
feet beyond boat basin making up the East Boat Channel. A 
new West Boat Channel was added 16 feet deep by 100 feet 
wide for 4,300 feet and completed in 1984. Project was modified 
in 1951 to provide a channel in Scholfield River, but this 
portion of the project is currently inactive. Mean lower low 
water is plane of reference. Tidal range between mean lower 
low water and mean higher high water at river mouth is 7 feet, 
and extreme range is about 11 feet. 
North jetty was completed in 1930. Extension to original 
south jetty was completed in 1938. Dredging a 22-foot channel 
from mouth of river to Reedsport was completed in 1941. 
Gardiner Channel and turning basin was completed in 1949 
and Winchester Bay Channel and mooring basin in 1956. 
Rehabilitation of south jetty was completed August, 1963. 
Extension of training jetty was completed October 9, 1980. 
Deepening Winchester Bay East Channel and new West 
Channel completed 1984 under Section 107. (For details 
relating to previous projects, see page 2967 of Annual Report 
for 1898 and page 1732 of Annual Report for 1938.) 
Local cooperation. None required. 
Terminal facilities. At Gardiner there is about 650 feet of 
wharf frontage. Also there is an oil unloading facility owned 
by International Paper Co. for exclusive use of tanker barges. 
Port of Umpqua owns one wharf with 456 feet of water 
frontage, of which 228 feet is usable for vessels and another 
with about 75 feet of water frontage which has not been used 
generally for commercial shipping. 
On Bolon Island across the river from Reedsport a wharf 
was constructed which has about 5 acres of open storage for 
lumber and available to all on equal terms. 
At Winchester Bay, 2 miles from river entrance there is a 
major sports and commercial fishing harbor. Facilities are 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 285,043 cubic yards of material. 
The channel flusher Sandwick worked 12 days at the entrance 
channel to Winchester Bay. 
21. WILLAMETTE RIVER AT WILLAMETITE 
FALLS, OR 
Location. Locks and dam covered by this project are at 
Willamette Falls, a rocky reef in Willamette River at Oregon 
City, OR, about 26 miles above mouth of river. 
Existing project. Canal and locks were originally constructed 
by private interest in 1873 and were purchased by the 
United States in April 1915 for $375,000. Final report on 
purchase and rehabilitation of canal and locks is in the Annual 
Report for 1923, when project was reported 98 percent 
complete. The project includes four locks a canal basin and 
an extra guard lock used to prevent flooding when river levels 
are high. The system acts as a fluid staircase between the 
upper and lower reaches of the Willamette River. Total 
length of existing canals and locks is about 3,500 feet. Principal 
features of existing canal and locks at Willamette Falls are 
set forth in Table 37-K. Ordinary fluctuation of stage of 
water above locks is 12 feet and extreme, due to flood conditions, 
20 feet. Below locks, ordinary fluctuation is 15 feet and 
extreme 50 feet. 
Until the 1940's, the gates were opened manually. Now, the 
gates are operated by hydraulic pumps controlled by switches 
in two control stations with the aid of closed-circuit television 
and radio communication. All the gates have been replaced 
under minor rehabilitation funds. Existing locks and grounds 
are in good condition and in continuous operation. New service 
building was completed in 1988 costing $523,000. The 
project was placed on the National Register of Historic 
Places in 1974, and was established as an Oregon Civil Engineering 
Landmark in 1991. 
Local cooperation. Fully complied with. 
Terminal facilities. James River Paper has a timber wharf 
about 850 feet long, extending to and supported by a concrete 
division wall built in lock canal by the United States. This 
wharf is used for receiving mill supplies and shipping paper 
and paper products. 
Operations during fiscal year. Routine operation and 
maintenance performed. 
37-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
22. YAQUINA BAY AND HARBOR, OR 
Location. Yaquina Bay is on Oregon coast, 113 miles south 
of mouth of Columbia River. (See NOAA Charts 18580 and 
18581.) 
Existing project. Two high tide rubblemound jetties at entrance, 
north jetty 7,000 feet, and south jetty 8,600 feet long; 
a spur jetty on channel side of south jetty 4,700 feet from its 
sea end, 800 feet long; five groins channelward from south 
jetty; channel 40 feet deep for a general width of 400 feet 
across bar and at outer end of entrance channel; a channel 30 
feet deep and 300 feet wide to a turning basin of same depth, 
900 to 1,200 feet wide and 1,400 feet long, and a channel 18 
feet deep and 200 feet wide from 30-foot channel at about 
mile 2.4, thence upstream to abandoned railroad terminus at 
Yaquina, a distance of about 4.5 miles. Project also provides 
for two small boat mooring basins at Newport, OR. Mean 
lower low water is plane of reference. Tidal range between 
mean lower low water and mean higher high water is 8 feet 
and extreme is about 12 feet. At mile 1.2 a 1,300 foot long 
breakwater protecting the Port of Newport South Beach 
Marina together with an entrance channel 8 feet long by 100 
feet wide for a distance of 2,035 feet. 
Project as originally authorized was completed in May 
1952. Restoration of jetties was completed in 1934 and extension 
of north jetty 1,000 feet seaward was completed in 1940. 
Construction of mooring basin at Newport and dredging of 
channel and turning basin to project dimensions were completed 
during fiscal year 1949. Restoration of north jetty was 
again accomplished in 1956. Under modification of July 3, 
1958, extension of north jetty was completed in September 
1966, dredging of 40-foot bar channel and 30-foot river channel 
was completed in October 1968, and extension of south 
jetty was completed in June 1972. The north jetty was rehabilitated 
in 1978 and again in 1988. (For details relating to 
previous projects see Annual Report for 1893, part 4, page 
3314, and Annul Report for 1938, page 1736.) 
Local cooperation. None required. 
Terminal facilities. At McLean Point, on north side of bay, 
about 2 miles from entrance, Port of Newport has two berths 
capable of serving ocean-going vessels, one 435 feet long, the 
second 520 feet long. At the time the second berth was 
dredged, a retaining wall and fill of 6 acres were constructed 
adjacent to deep water. There now is 40 acres of filled land 
adjacent to deep water, and of this total, 7 acres were constructed 
in 1956-57. This facility has necessary carriers and 
lift trucks for handling lumber cargoes, warehouse for covered 
cargo storage, and is open to all on equal terms. 
Port of Newport also has a public wharf with 300 feet of 
frontage for servicing fishing boats. In addition, Port of Newport 
maintains 510 berths for mooring commercial and sport 
fishing vessels. There are several seafood companies on the 
bay which have their own facilities for handling fresh fish and 
crab. Supplies and petroleum products are readily available 
for small vessels. On south side of bay about 1.2 miles above 
entrance, Port of Newport has constructed South Beach Marina 
which can handle approximately 600 pleasure craft and 
shallow draft fishing boats. Public facilities include public 
automobile and boat trailer parking, boat launching ramp, 
fuel dock, fishing pier, and picnic area. A dry boat moorage of 
120 boats, is completed. A swing hoist with 3- ton capacity is 
currently available and one with 60-ton capacity is planned. 
About 1.5 miles above entrance, Oregon Aqua Foods, subsidiary 
of Weyerhaeuser Company, maintains a commercial 
fish farm facility. 
About 2.0 miles above entrance, Oregon State University, 
in conjunction with the Marine Science Center on 52 acres, 
maintains a 220-foot pier for docking large and small research 
vessels and a 100-foot float for docking small boats. 
Docking facilities are restricted to research vessels and State 
of Oregon small boats. 
Operations during fiscal year. Maintenance: U.S. hopper 
dredge Yaquina removed 321,652 cubic yards, and the contract 
dredge Nehalem removed 21,104 cubic yards of material. 
Monitored the north jetty for deterioration. 
23. APPLEGATE LAKE, ROGUE RIVER 
BASIN, OR 
Location. In Jackson County, OR, on Upper Applegate 
River, a tributary of Rogue River, at River Mile 46, about 23 
airline miles southwest of Medford, OR. 
Existing project. A gravel-fill embankment dam, 242 feet 
high from streambed to crest with an overall length of 1,300 
feet. A gate- controlled concrete chute-type spillway on the 
left abutment, and a regulating outlet conduit, and intake 
tower with multilevel intakes on the left side of valley floor. 
Lake, 5 miles long, provides 75,000 acre-feet of usable storage 
for flood control and water conservation utilization. Project 
controls runoff from a drainage area of 223 square miles. 
In addition to flood control, reservoir is operated to provide 
irrigation, fish and wildlife enhancement, water quality control, 
and recreation benefits. Recreation facilities were provided 
by the Corps of Engineers with operation and maintenance 
by the USFS under a memorandum of agreement. 
Project is complete and operating. 
Local cooperation. Authorizing act requires that State of 
Oregon insure maintenance of stream flow released for fishery. 
In addition, costs allocated to irrigation would have to be 
repaid in a manner and to an extent consistent with reclamation 
laws and policies. Oregon Department of Fish and Wildlife 
made filing May 31, 1962 with State Engineer for water 
rights for use of stored water and natural flows for fish habitat 
improvement in amounts and at times specified in project 
authorization. The U.S. Bureau of Reclamation has made a 
feasibility study of Applegate Irrigation Division. The results 
of the study indicate that at present there does not appear to 
be a feasible Federal irrigation project for the Applegate 
River valley. Local interests have furnished all local cooperation 
specified by the 1970 Flood Control Act. The assurances 
were approved by the Secretary of the Army on May 8, 1975. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance was performed. Freshets regulated 
by Applegate Lake on Applegate River and Rogue River are 
shown in Table 37-M. 
37-10

PORTLAND, OREGON DISTRICT 
24. BLUE RIVER LAKE, OR 
Location. On Blue River, a major tributary of McKenzie 
River, 1.8 miles above confluence of the two streams at the 
confluence of Quartz Creek and Blue River and about 42 
miles easterly of Eugene, OR. 
Existing project. A gravel-fill embankment dam 1,329 feet 
long at crest including spillway and 319 feet above the lowest 
point of the general foundation. A concrete gravity chutetype 
spillway with two gates is located on left abutment. 
Outlet works are in left abutment. On left shore of reservoir 
an earth-and-gravel fill embankment, about 1,535 feet long 
and 70 feet high, closes a low saddle between Blue River and 
McKenzie River. Project controls runoff from drainage area 
of 88 square miles. Reservoir provides 85,000 acre-feet of 
usable flood control storage and is operated as a unit of 
coordinated reservoir system to protect Willamette River 
Valley and increase low waterflows for navigation and other 
purposes. Recreation facilities are provided by the U.S. Forest 
Service under a Memorandum of Agreement. Project is 
complete. Construction of dam and appurtenant works was 
initiated in May 1963 and operation for flood control was 
effective in October 1968. Settlement of claims was completed 
in May 1974. Eugene Water and Electric Board made 
an application on April 1982 for permit to install two small 
hydropower units at Blue River Lake project. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance work performed. Freshets regulated 
by Blue River Lake project on Blue River, a major 
tributary of McKenzie River, are shown in Table 37-M. 
25. COTTAGE GROVE LAKE, OR 
Location. ON Coast Fork of Willamette River, 29 miles 
from mouth. Coast Fork rises in Douglas County, OR, on 
western slope of Cascade Range and northern slope of 
Calapooia Range, flows north for 49 miles, and unites with 
Middle Fork to form main Willamette River. 
Existing project. An earthfill dam, 1,750 feet long at crest, 
114 feet high from lowest point of the general foundation, a 
concrete gravity free overflow spillway 264 feet long near the 
right abutment, and a concrete gravity non-overflow section 
96 feet long forming the right abutment. Total length of dam 
is 2,110 feet. Outlet works, consisting of three gate- controlled 
conduits, pass through spillway section. Reservoir 
provides 30,060 acre-feet of usable flood control storage and 
controls runoff of drainage area of 104 square miles. Project 
is operated as a unit of coordinated reservoir system to protect 
Willamette River Valley and increase low waterflow for 
navigation and for other purposes. Recreational development 
consists of day use and overnight facilities at five sites 
operated by the Corps of Engineers. Construction of project 
initiated August 1940 was completed April 1952. Dam and 
reservoir have been in continuous operation since September 
1942. 
Local cooperation. Development of additional recreation 
facilities will require a local sponsor willing to cost share and 
assume all operation and maintenance of park facilities. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance work continued. Freshets regulated 
by Cottage Grove Lake on Coast Fork Willamette River are 
shown in Table 37-M. 
26. DORENA LAKE, OR 
Location. On Row River, OR, 7 miles from mouth. Row 
River rises in Lane County on western slope of Cascade 
Range, flows northwest for 19 miles, and enters Coast Fork of 
Willamette River 19.5 miles above mouth. 
Existing project. An earthfill embankment dam, 3,352 feet 
long at crest and 145 feet high from lowest point of the 
general foundation. Concrete gravity free-overflow spillway, 
200 feet long, forms right abutment. Outlet works on five 
slide-gate-controlled conduits pass through spillway section. 
Reservoir provides 70,500 acre-feet of usable flood control 
storage and controls runoff of 265 square miles. The Project 
is operated as a unit of coordinated reservoir system to protect 
Willamette River Valley and increase low waterflows for 
navigational and other purposes. Construction of project initiated 
June 1941 was completed October 1952 except for 
construction of additional recreation facilities that were 
funded under the Code 710 program. Future recreation facility 
construction will be accomplished in accordance with the 
cost-sharing contract with Lane County, OR. Dam and reservoir 
have been in continuous operation since November 
1949. 
Local cooperation. A multiple project cost sharing agreement 
has been in force with Lane County since Sept. 1976. It 
includes 4 projects and 14 parks. At Dorena Lake, 6 parks 
included in the agreement are managed by Lane County 
under a lease agreement. Future recreation development 
will require a supplement to the cost sharing agreement. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. Freshets regulated by 
Dorena Lake project on Row and Coast Fork Willamette 
Rivers are shown in Table 37-M. 
27. ELK CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Location. In Jackson County, OR at River Mile 1.7 on Elk 
Creek, a tributary of Rogue River, about 26.5 miles northerly 
from Medford, OR. 
Existing project. Construction work for the 249-foot high 
roller compacted concrete gravity dam, 2,600 feet long at the 
crest, with a gate controlled concrete chute spillway, regulating 
outlet conduits, power penstock and multiple use intake 
tower attached to the upstream face of the dam has been 
stopped due to a court injunction. The project would control 
runoff from a drainage area of 135 square miles, and provide 
future municipal and industrial water supply, irrigation, fish 
and wildlife enhancement, water quality control, and recreation 
benefits. 
Construction of the project was initiated in February 1971. 
Work completed to date includes construction of roads and 
37-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
the main dam structure and outlet works to elevation 1563 
(approximately 1/3 proposed height). All lands for the project 
have been acquired with the exception of the clearing of 
water rights for a seemingly abandoned irrigation canal which 
originates within the project boundaries. Environmental 
statements were filed with Council of Environmental Quality 
June 15, 1972 and Supplement No. 1 addressing water quality 
and social/demographic information was filed with EPA on 
December 24, 1980. Estimated federal cost of project is 
$174,000,000. 
In October 1985, the Corps was advised by Oregon Natural 
Resources Council (ONRC), an environmental group, they 
intended to file suit against the government to halt construction 
of Elk Creek, on specific environmental issues. A hearing 
on the motion for a preliminary injunction was scheduled 
before Oregon Federal District Court December 16, 1986. 
On that date, the Court refused to grant the injunction to halt 
construction and bids were opened and the contract subsequently 
awarded to Ohbayashi Corp. An appeal was filed by 
ONRC in March, 1986 and heard by the 9th Circuit Court in 
July, 1986. 
On June 23, 1987, the Circuit Court reversed the decision 
of the District Court and returned the case to the District 
Court for appropriate injunctive relief. The resulting District 
court order issued in August and September 1987 allowed 
construction of the dam to El. 1563 ft. (approximately 1/3 the 
height of the dam), backfilling of the foundation key trench, 
aggregate processing, quarry restoration, and other miscellaneous 
work. The construction of the main dam to elevation 
1563 was reached in mid-January 1988. The Department of 
Justice petitioned the 9th Circuit Court for a rehearing. On 
December 10, 1987 the 9th Circuit Court rejected the petition 
for a rehearing, requiring the termination of the existing 
main dam and reservoir clearing contracts. The Department 
of Justice petitioned with the U.S. Supreme Court for a 
review of the decisions made by the 9th Circuit Court. The 
hearing before the U.S. Supreme Court was held May 1, 
1989. The U.S. Supreme Court remanded the case back for 
injunctive relief. In September 1989, the District Court was 
requested by the Corps to remand the case back to the Corps 
for preparation of a supplemental EIS. 
To lift the injunction against the dam a Supplemental Environmental 
Impact Statement (EISS) has been prepared to 
address cumulative effects. Additional studies have been 
conducted in water temperature and turbidity, and fish and 
wildlife. The EISS identified a preferred interim operating 
alternative of operating the project without a conservation 
pool. The reservoir would only temporarily store water during 
flood control operations. 
Local cooperation. Authorizing act requires that State of 
Oregon take action prior to construction to insure maintenance 
in stream of flow to be released for fishery. In addition, 
costs allocated to irrigation would have to be repaid in a 
manner and to an extent consistent with the U.S. Bureau of 
Reclamation laws and policies. On February 24, 1966, State 
of Oregon Water Resources Board filed for withdrawal rights 
of 25 cubic feet per second to maintain a minimum flow for 
fish. Development of recreation facilities require a local 
sponsor willing to cost share in recreation development and 
assume operations and maintenance of park facilities. 
Operations during fiscal year. Operation and maintenance 
during the construction phase of the project, fishery evaluation 
studies, and water quality analysis. 
28. FALL CREEK LAKE, OR 
Location. On Fall Creek, a tributary of Middle Fork Willamette 
River, about 7 miles above confluence of the streams 
and about 19 miles southeasterly of Eugene, OR. 
Existing project. An earth-and-gravel fill embankment 
about 5,100 feet long at crest and 193 feet high from lowest 
point of the general foundation. A gated concrete gravity 
spillway is in left abutment. Outlet is in right abutment. 
Reservoir provides 115,000 acre-feet of usable flood control 
storage and is operated as a unit of coordinated reservoir 
system to protect Willamette River Valley and increase low 
waterflows for navigation and other purposes. 
Construction of project began May 1962 and was essentially 
complete November 1965. Reservoir storage for flood 
control was effective October 1965. Sky Camp Lodge was 
completed October 1978. Future recreation facilities will be 
provided in accordance with the cost-sharing contract with 
Bethel School District. Bethel School District has a subagreement 
with the Springfield Kiwanis Club for management 
of this facility. The Corps manages one park at the 
project. 
Local cooperation. Fall Creek Lake is included in the Lane 
County multiple project cost sharing agreement. Two parks 
are managed by Lane County under lease agreement. Future 
development will require a supplement to the cost sharing 
agreement. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance work performed. Freshets regulated 
by Fall Creek Lake project on Fall Creek, a tributary of 
Middle Fork, Willamette River, are shown in Table 37-M. 
29. FERN RIDGE LAKE, OR 
Location. On Long Tom River, 23.6 miles from the mouth. 
Long Tom River rises in Lane county, OR, on eastern slope 
of Coast Range, flows north for 50 miles, and enters Willamette 
River 147 miles above its mouth. 
Existing project. A main dam 6,624 feet long at crest and 49 
feet high from lowest point of the general foundation and two 
auxiliary dikes, 915 and 3,929 feet long, along northeasterly 
boundary of lake. Main dam consists of an earthfill embankment 
dam 6,330 feet long, a concrete gravity spillway near left 
abutment with a non-overflow structure 46 feet long, containing 
outlet works, and an overflow structure, 248 feet long, 
controlled by six automatic gates. Project includes rectification 
of channel of Long Tom River downstream of dam. 
Reservoir provides 110,000 acre-feet of usable flood control 
storage and controls runoff of tributary drainage area of 275 
square miles. Reservoir protects Long Tom River Valley and 
is operated as a unit of coordinated reservoir system to protect 
Willamette River Valley generally and to increase low 
water-flows for navigation and other purposes. Dam was 
37-12

PORTLAND, OREGON DISTRICT 
originally constructed in 1941 to height of 47 feet. Provision 
of additional storage for flood control was obtained in 1965 by 
raising embankments 2 feet to 49 feet above lowest point of 
the general foundation. 
Construction of project initiated April 1940 was completed 
August 1951, except for provision of additional storage for 
flood control authorized in 1962 and completed April 1965, 
and construction of additional recreation facilities funded 
through the Code 710 program. Dam and reservoir have been 
in continuous operation since December 1941. Development 
of future recreation facilities will be in accordance with the 
cost-sharing contract with Lane county, and requires a 50 
percent contribution by the county. Development is subject 
to availability of funds by the Government and the county. 
Local cooperation. Fern Ridge Lake is included in the Lane 
County multiple project cost sharing agreement. Three parks 
are managed by Lane County under lease agreements. Future 
development will require a supplement to the cost sharing 
agreement. The Oregon Department of Fish and Wildlife 
manages 5,000 acres of land and water for migratory water 
fowl under a lease agreement. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. Freshets regulated by 
Fern Ridge Lake project on Long Tom River are shown in 
Table 37-M. 
30. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205 of the 1948 
Flood Control Act, Public Law 858, 80th Congress, as 
amended (preauthorization): 
Feasibility and reconnaissance studies continued. See Table 
37-L for expenditures under Section 205 during the fiscal 
year. 
Emergency bank protection activities pursuant to Section 
14 of the 1946 Flood Control Act, Public Law 526, 79th Congress, 
as amended (preauthorization): 
Construction of a bank protection project at Mill Creek, 
OR is discussed in Section 34. 
Feasibility and reconnaissance studies continued. See Table 
37-L for expenditures under Section 14 during the fiscal 
year. 
Emergency flood control activities-repair, flood fighting, 
and rescue work pursuant to Public Law 99, 84th Congress 
and antecedent legislation: 
Federal costs for the fiscal year were: $343,828 for disaster 
preparedness; $3,513 for emergency operations; $33,626 for 
rehabilitation of non-federal flood control works and field 
investigations; and $7,906 for advance measures associated 
with the Mt. St. Helens recovery effort. National Emergency 
Preparedness Program fiscal year costs were $193,813. 
Project modification for the improvement of the environment 
pursuant to Section 1135 (b), Public Law 99-362 as 
amended: 
A feasibility study continued at Fern Ridge Lake, OR. See 
Table 37-L for expenditures under Section 1135 during the 
fiscal year. 
31. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Funds appropriated for inspection of completed local flood 
protection works are used to determine maintenance condition 
of completed works and to ascertain whether those works 
are being properly maintained by local interests. A total of 68 
leveed areas and 262 bank protection works are inspected at 
various locations along both banks of Lower Columbia River 
below Bonneville Dam, along Oregon Coast, in eastern Oregon, 
in southern Oregon and in Willamette River Basin. 
Aerial inspection of revetments in Willamette River Basin 
are supplemented by an onsite inspection at locations requiring 
maintenance. A representative of sponsoring districts 
accompanied the Portland District representatives performing 
the levee inspections. Deficiencies in maintenance and 
need for repairs were discussed with sponsoring districts' 
representatives and a report was made to each sponsor with 
recommendations for improving maintenance. The program 
to improve maintenance of completed Federal projects initiated 
by House Appropriations Committee on Civil Functions 
was continued. Of the 68 levee areas inspected during the 
fiscal year, one was reported deficient in maintenance. Fiscal 
year costs were $154,787. 
32. LOWER COLUMBIA RIVER BASIN BANK 
PROTECTION, OR AND WA 
Location. On Columbia River and tributaries between 
Sandy River, OR, and mouth of Columbia River. 
Existing project. Provides for construction of 224,000 linear 
feet of bank protection works at 96 locations along Lower 
Columbia River below River Mile 125 and along principal 
tributaries in this reach, to protect existing improvements 
such as levees and developed industrial lands from further 
erosion. Existing project is a unit of general comprehensive 
plan for flood control, navigation, and other purposes in 
Columbia River Basin. Construction of project began in July 
1961 and is 88 percent complete. A total of 191,000 linear 
feet of bank protection work at 84 locations has been completed. 
Estimated Federal cost is $25,600,000. 
Local cooperation. Flood Control Act of 1950 provides 
local interests furnish lands and rights-of-way; make necessary 
highway, highway bridge, and utility alterations; hold the 
United States free from damages; and maintain and operate 
completed works. Under Section 103 of the Water Resources 
Development Act of 1986, Local Interests will also be required 
to make a cash contribution for construction of each 
site. Estimated costs for all requirements of local cooperation 
are $1,500,000. 
Operations during fiscal year. Work consisted of coordination 
with sponsors and evaluation of local erosion problems 
continued. 
37-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
33. MILL CREEK, SALEM, OR 
Location. On the right bank of Mill Creek at the southeast 
fringe of the city of Salem, Oregon, near the junction of 
Interstate Highway 5 and State Highway 22. Mill Creek 
confluence with Willamette River is about 3.7 miles downstream 
of the project. 
Existing project. Work was authorized under the special 
continuing authority contained in Section 14 of the 1946 
Flood Control Act, as amended. This authority allows construction 
of emergency bank protection to prevent flood 
damage to public works. Project consists of construction of 
three riprap groins along the upstream and middle portion of 
the eroding bankline, excavation of a portion of land area 
downstream of the groins, and extending the existing riprap 
revetment 250 linear feet upstream to the groins. This action 
will prevent the outflanking of the right abutment of Hawthorne 
Avenue Bridge and provide acceptable flow alignment 
to the bridge. The cost for preparation of the plans and 
specifications and construction of the project was $205,471, 
of which $154,103 was Federal and $51,368 non-federal. The 
non-federal cost includes cash contributions of $31,031 and 
the value of $20,337 for lands, easements, rights-of-way, 
relocations, and disposal areas (LERRD). 
Local cooperation. The City of Salem, Oregon, the nonfederal 
sponsor, provided lands, easements and rights-ofway. 
In addition, the City of Salem participated financially in 
accordance with the cost sharing requirements of the Water 
Resource Development Act of 1986, Public Law 99-662. 
Operations during fiscal year. New Work: Final project 
costs and non-federal credit for the value of the LERRD was 
determined. 
34. MT. ST. HELENS SEDIMENT CONTROL, 
WA 
Location. On the North Fork Toutle River, 2 miles upstream 
from its confluence with the Green River, in Cowlitz 
County, southwest Washington. The river systems impacted 
by the project include Toutle, Cowlitz and Columbia Rivers. 
Most of the population affected by the problems reside in the 
communities of Longview, Kelso, Lexington, and Castle 
Rock, Washington. 
Existing project. The project was authorized by the Supplement 
Appropriations Act, 1985 (Public Law 88, 99th Congress, 
August 15, 1985). The Act includes authorization "..to. 
construct, operate and maintain a sediment retention structure 
near the confluence of the Toutle and Green River, 
Washington, with such design features and associated downstream 
actions as are necessary, in accordance with the Feasibility 
Report of the Chief of Engineers dated December 
1984." The project will provide a permanent solution to potential 
flooding on the Cowlitz River from sedimentation 
problems created by the eruption of Mt. St. Helens. The 
Decision document recommended construction of a single 
sediment retention structure (SRS) with a 125- foot high 
spillway at the Green River site on the North Fork Toutle 
River, improvements to the levee system at Kelso, Washington, 
and dredging downstream from the SRS. 
Local cooperation. Local interests were responsible for 
provision of all lands, easements, and rights-of-way for the 
sediment retention structure, dredging disposal areas, and 
levee improvements. Local interests were also responsible 
for all alterations and relocations of buildings, roads, bridges 
and other structures or utilities made necessary by implementation 
of the project. In addition, operation and maintenance 
of fish facilities, the levee system at Kelso and dredged material 
disposal sites are the responsibility of local interests. 
Cowlitz County offers visitor services in their viewpoint area. 
Non-federal cash contribution is $3,690,000 and the estimated 
non-federal land, easements, right-of-ways, and relocations 
costs are $21,000,000. 
Operations during fiscal year. New work: Work on the 
Sediment Retention Structure was substantially completed 
with some follow-on work remaining. The fish collection 
facility is completed and is operated by the State of Washington. 
Maintenance: Routine operation and maintenance performed. 
35. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Corps of Engineers monitored flood control operations at 
five Bureau of Reclamation projects (Prineville, Ochoco, 
Emigrant, Scoggins, and Galesville) and one municipal power 
project operated by Tacoma City Light (Mossyrock). The 
Bureau of Reclamation projects were partially constructed 
with flood control funds, thereby subjecting project operation 
to monitoring by the Corps of Engineers under Section 7, 
Flood Control Act of 1944. Monitoring of Mossyrock flood 
control operation is assigned to the Corps by the Federal 
Energy Regulatory Commission as the Mossyrock license 
calls for specific flood control regulation. 
The five Bureau of Reclamation projects and Mossyrock 
project were operated during the fiscal year within the flood 
control regulations specified for each project. Total cost of 
monitoring the six projects during the fiscal year was $6,770. 
36. WILLAMETTE RIVER BASIN BANK 
PROTECTION, OR 
Location. On Willamette River and tributaries, between 
Cascade Range and Coast Range, from a point south of 
Eugene to Portland, OR. 
Existing project. Provides for clearing, sloping, and reveting 
riverbanks; construction of pile and timber bulkheads and 
drift barriers; minor channel improvements; and maintenance 
of existing works for control of floods and prevention 
of erosion at various locations along Willamette River and its 
tributaries. The current scope of the project is a total of 
510,000 linear feet of bank protection at 236 locations. Estimated 
Federal cost is $30,700,000. 
Construction of project began in 1938 and is 96 percent 
complete. A total of 489,795 linear feet of bank protection 
37-14

PORTLAND, OREGON DISTRICT 
work at 230 locations consisting of revetment of riverbanks, 
pile and timber bulkheads, drift barriers, and channel improvements, 
have been completed on Willamette River and 
tributaries. 
Local cooperation. Section 3, Flood Control Act of 1936 
and Section 103, Water Resources Development Act of 1986 
applies. Estimated costs for all requirements of local cooperation 
under terms of project authorization were 
$2,300,000. 
Operations during fiscal year. Maintenance: continued coordination 
and evaluation of local erosion problems. 
37. WILLOW CREEK LAKE, HEPPNER, OR 
Location. On Willow Creek immediately upstream from 
Heppner and just downstream from junction of Balm Fork 
and Willow Creek in Section 35, Township 2 South, Range 26 
East, Willamette Meridian. 
Existing project. Project provides flood protection to the 
city of Heppner and downstream area by controlling runoff 
from a drainage area of 96 square miles. The dam is a roller 
compacted concrete structure 160 feet high at crest elevation 
2,130. Ancillary features include a center uncontrolled spillway 
with a maximum flood capacity of 93,300 cfs (cubic feet 
per second), an outlet works with a capacity of 500 cfs, a 
minor flow works and diversion works. Gross storage capacity 
of the project is 13,250 acre-feet, consisting of 7,750 acrefeet 
for exclusive flood control, 1,750 acre-feet for joint flood 
control and irrigation, 1,750 acre- feet exclusive irrigation, 
and 2,000 acre-feet dead storage for fish, wildlife, recreation, 
sediment accumulation, and aesthetics. Limited recreation 
facilities are being provided. 
Willow Creek Parks and Recreation District has leased 
recreation facilities at Willow Creek Lake. A courtesy handling 
dock was constructed by the Recreation District utilizing 
Oregon State Marine Board funds. A playfield area below 
the dam has been leased to the City of Heppner. 
The final Environmental Impact Statement was filed with 
the Environmental Protection Agency on December 20, 
1979. The provisions of the Clear Water Act were met by a 
Section 404(b)(1) Evaluation and a public notice issued January 
12, 1980, and a section 401 certification from the State of 
Oregon on February 15, 1980. Land acquisition is about 99 
percent complete. 
Local cooperation. A Local Cost Agreement (LCA) is being 
developed for construction of recreation facilities with 
the Willow Creek Parks and Recreation District. 
Operations during fiscal year. New work: LCA development 
and plans and specifications preparation by local sponsor 
for recreation facilities. 
Maintenance: Routine operation and maintenance performed. 
Multiple-Purpose Projects, Including Power 
38. BONNEVILLE LOCK AND DAM - LAKE 
BONNEVILLE, OR AND WA 
Location. Project is on Columbia River, 40 miles east of 
Portland, OR, about 146 miles above mouth of river. For 
description of Columbia River, see Section 4. 
Existing project. A dam, powerplant, and lock for power 
and navigation. Spillway dam extends across main channel 
from Cascade island shore to Bradford Island. Overflow crest 
at 24 feet above mean sea level is surmounted by 18 verticallift 
steel gates, 10 with remote control hoists placed between 
piers which extend to elevation 99 feet where a service roadway 
provides access, and two 350-ton gantry cranes for regulating 
gates. Powerhouse No. 1 extending across Bradford 
Slough to the Oregon shore has an installation of 10 units, 
consisting of one unit of 48,000 kilowatts, one unit of 59,500 
kilowatts, and eight units of 60,000 kilowatts each, totaling 
587,500 kilowatts. Ordinary and extreme fluctuations of river 
at lower lock gate are about 21 and 47 feet respectively. 
Project includes fish ladders to serve both main channel, 
Bradford Slough Channel, and Powerhouse II channel. Navigation 
lock and powerhouses are founded on andesite, and 
main dam rests on solidified sedimentary rock of volcanic 
origin. The pool created by dam provides a navigable channel 
27 feet deep between Bonneville and The Dalles Dams, a 
distance of 47 river miles. Principal data concerning navigation 
lock, spillway dam, and powerplant are set forth in Table 
37-N. 
Dam, navigation lock, 10-unit power generating installation, 
fishways, and attendant buildings and grounds cost 
$83,239,395, of which $6,072,480 is for navigation facilities, 
$39,350,824 for power facilities and $37,816,091 for joint 
facilities, consisting of dam, fishways, buildings and grounds, 
and headwall section of power units 0 to 6, cost of which 
$2,106,000 is allocated to dam and lake facilities. 
In response to flow regulations and peakings from upstream 
plants operating under conditions of Canadian storage 
and Pacific Northwest-Southwest Intertie, two modifications 
were undertaken at the Bonneville project. The 
modification for peaking project was undertaken to minimize 
adverse environmental effects under rapidly changing flow 
conditions from upstream dams. The project was completed 
in 1978 at a cost of $27,195,000. The second modification 
provided for increased power installation by building a second 
powerhouse located on the Washington shore adjacent 
to the end of the existing spillway. The new powerhouse 
contains eight units of 66,500 kilowatts each and two fish 
attraction turbine generator units of 13,100 kilowatts each for 
a combined capacity of 558,200 kilowatts, bringing the entire 
Bonneville capacity to 1,145.7 megawatts. Additional fish 
facilities consist of the powerhouse collection system, second 
fish ladder on the Washington shore, transportation channel 
connecting the Cascade Island fish ladder with new exit control 
section, and fingerling bypass facilities which include fish 
screens in both the powerhouses. To provide for the anticipated 
increased visitor use, onsite visitor facilities are included. 
Under authority of the Bonneville Project Act 
(August 20, 1937), a letter from Bonneville Power Admini- 
37-15

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
stration to North Pacific Division dated January 21, 1965, 
requested construction of a second powerhouse. 
Construction of project started October 1933, was completed 
February 1943. Modification of powerhouse control 
equipment started March 1957, was completed September 
1958. First two power units were placed in operation during 
fiscal year 1938. Powerhouse with complete installation of 10 
units, was in operation December 1943. 
Construction of modification for peaking work commenced 
in September 1970 and was completed in September 1978. 
Construction of second powerhouse is near completion. 
Final environmental impact statement was filed with Council 
on Environmental Quality in April 1972. In response to increasing 
visitation which now exceeds 800,000 a year at the 
dam site itself and 1,500,000 project wide, a visitor center 
with windows into the fish ladders, a 60-seat theatre, exhibits 
and displays was completed in 1975. Units 11 through 18 were 
on-line by October, 1982. The visitor facility for the new 
powerhouse (which does not require cost-sharing) is an integral 
part of that structure. The total cost for construction of 
the second powerhouse is $681,000,000. 
The first powerhouse, spillway, navigation lock and associated 
facilities have been designated as a National Historic 
District. 
A cost sharing agreement between The Corps and 
Skamania County has been finalized. Development of recreation 
facilities at Home Valley was completed in FY 89. 
Through September 1992, power generation totaled 220.6 
billion kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, $462,365,155 
was reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. None required, except for non-Federal 
cost-sharing for development of recreational facilities. 
Operations during fiscal year. New work: Development of 
a design continued for correction of deficiencies of juvenile 
fish guidance efficiency at the second powerhouse to reduce 
fingerling mortality incurred during annual downstream migration. 
Development of a portion of Steigerwald Lake for 
mitigation continued. Additional investigations to determine 
the scope of necessary environmental cleanup actions for 
Hamilton Island were conducted. 
Maintenance: Increased activities to protect and enhance 
the anadromous fisheries in the Northwest were performed. 
Evaluation Reports for the first powerhouse transformers, 
switchgear, and main units rehabilitation were completed. 
Routine operation and maintenance was performed with enhanced 
maintenance on the turbines. During the fiscal year 
4,147,170,000 kilowatt-hours of electrical power energy were 
generated, of which 4,116,043,000 kilowatt-hours were delivered 
to Bonneville Power Administration, the marketing 
agency. 
39. COLUMBIA AND SNAKE RIVERS 
PORTS DREDGING, OR & WA 
Location. On the Columbia River from Bonneville Dam to 
McNary Dam 
Existing project. On a one-time basis, at full Federal 
expense, and without requirement of local sponsorship, 
maintain navigation access to, and berthing areas at, all currently 
operating public and private commercial dock facilities 
associated with the Federal navigation project on the Columbia 
River from Bonneville Dam to Umatilla, Oregon, at a 
depth commensurate with the Federal navigation project, 
and the Federal Government is exempted from any liability 
due to public and private facilities including docks adjacent to 
the access channels and berthing areas resulting from this 
maintenance. 
Sites identified for dredging under this authorization included 
recreational channels at Wind River, Mayer State 
Park, and Rock Creek State Park; recreational boat basins at 
The Dalles, Cascade Locks, and Bingen; commercial docks at 
Port of Morrow, Stevenson Co-Ply, Mt. Adams, Hood River 
Inn, Rock Creek Cove, SD&S, Mountain Fir, Bernert, Cargill, 
Biggs, and Roosevelt; commercial log storage facilities at 
Wind River, SD&S, and Government Cove; commercial 
channels at Hood River, McNary, Port of Skamania, Herman 
Creek, and Little White Salmon. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Four dredging 
contracts were awarded and the U.S. channel flusher 
Sandwick utilized for 10 days to perform the required work. 
A total of 419,000 cubic yards of material was removed from 
25 sites. 
40. COLUMBIA RIVER JUVENILE FISH 
MITIGATION PROGRAM (The Dalles Project), 
OR AND WA 
Location. The Dalles Dam on the Columbia River in the 
states of Oregon and Washington. This program encompasses 
work at five other locations within Walla Walla District 
as well as The Dalles Dam within the Portland District. 
Existing Project. Congress passed and the President signed 
the FY 89 Energy and Water Development Act (P. L. 
100-371) which mandated the expenditure of approximately 
$25 million for the design, testing, and construction of fish 
bypass facilities. Funds for FY 88, 89, and 90 were expended 
on a project by project basis. However, the mitigation program 
starting in FY 91 is to be considered one project and 
funds will be appropriated and expended as such. The program 
will consist of juvenile fish mitigation facilities and a 
detailed mitigation study to be prepared in cooperation with 
regional interests, for juvenile fish. The mitigation study will 
determine the overall scope of the fish mitigation facilities for 
the Columbia and Snake River dams in the Portland and 
Walla Walla Districts. 
The plan of improvement at The Dalles Dam includes 
submerged extended fish screens and bypass system and a 
crane and maintenance facility. 
The total estimated Federal cost for work at The Dalles 
Dam is $101,500,000. 
37-16

PORTLAND, OREGON DISTRICT 
Local Cooperation. None required. 
Operations during fiscal year. Work continued on the 
General Design Memorandum for the juvenile bypass system 
and for design and procurement of prototype extended 
length fish screens and other testing equipment. 
41. COUGAR LAKE, OR 
Location. At mile 4.4 on South Fork McKenzie River which 
joins McKenzie River about 56.5 miles above its confluence 
with Willamette River. Project is about 42 miles east of 
Eugene, OR. 
Existing project. A rockfill dam with an impervious earth 
core, about 1,738 feet long at crest and 445 feet high above 
the streambed. Reservoir is 6 miles long with storage capacity 
at full pool of 219,000 acre-feet and controls runoff of tributary 
drainage area of 210 square miles. Spillway is on right 
abutment and outlet and power tunnels in left abutment. 
Outlet tunnel is provided with a chute and stilling basin. 
Powerplant consists of two 12,500 kilowatt units with minimum 
provisions for installing a third unit of 35,000 kilowatts 
for future peaking capacity. Improvement functions as a unit 
in coordinated system of reservoirs for multiple-purpose development 
of water resources in Willamette River Basin. 
Recreation facilities are provided by the U.S. Forest Service. 
Also authorized (but unconstructed) is a reregulating dam, 
Strube Lake, below Cougar Lake, which would permit Cougar 
to operate as a peaking powerplant. The Strube dam 
would contain two units totalling 4,600 kilowatts. 
Construction of project initiated June 1956 is complete, 
excluding Strube Lake and Cougar Additional Unit for which 
planning is essentially complete. Also, plans and specifications 
for the first construction contract (relocations) have 
been completed. Generating units 1 and 2 were placed in 
commercial operation March 23 and February 4, 1964, respectively. 
Physical in-service date for flood control was November 
29, 1963. Through September 1992 power generation 
totaled 3.7 billion kilowatt-hours. Of the gross income from 
sale of this power by Bonneville power Administration, 
$20,731,873 was reimbursed to the U.S. Treasury to recover 
Corps of Engineers project investment and operating costs. 
Estimated Federal cost of Strube lake and Cougar Additional 
Unit is $114,000,000. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. During fiscal year, 
118,830,000 kilowatt-hours of electrical energy were generated 
at project, of which 118,057,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Cougar Lake on South 
Fork McKenzie River are shown on Table 37-M. 
42. DETROIT LAKE - BIG CLIFF, OR 
Location. On North Santiam River with dam 50 miles from 
mouth 40 miles southeast of Salem, OR. North Santiam 
River flows north and west for 85 miles, and unites with South 
Santiam River to form Santiam River, which 10 miles downstream 
enters Willamette River 108 miles above its mouth. 
Existing project. Main dam and a reregulating dam, both 
with power-generating facilities. Detroit Dam is a concrete 
gravity structure about 1,522 feet long and 454 feet high from 
lowest point of the general foundation to roadway deck. Spillway 
is a gate-controlled overflow section, and outlet works 
are gate- controlled conduits through dam. Powerhouse with 
two units having a capacity of 50,000 kilowatts each is in right 
abutment immediately below dam. Reservoir has a storage 
capacity at full pool of 454,900 acre-feet and controls runoff 
of tributary drainage area of 438 square miles. It is being 
operated as a unit in coordinated reservoir system to protect 
Willamette Valley from floods, to increase low water flows in 
interest of navigation and irrigation, to generate power, and 
for other purposes. Reregulating dam 3 miles downstream at 
Big Cliff site is concrete gravity type, about 191 feet high from 
lowest point of the general foundation to roadway deck. 
Power installation consists of one unit with a capacity of 
18,000 kilowatts. Reservoir has a storage capacity of 5,930 
acre-feet at full pool. Project is a unit of comprehensive plan 
for flood control and other purposes in Willamette Basin. 
Recreation facilities are provided by the U.S. Forest Service, 
Oregon State Park System and the town of Detroit. 
Construction of project begun in May 1947 was completed 
December 1960. The two powerhouse generating units were 
placed in commercial operation June and October 1953. At 
Big Cliff powerhouse, single generating unit was placed online 
June 1954. Use of Big Cliff Dam for reregulating fluctuating 
flow from Detroit units was effected October 1953. 
Through September 1992 power generation totaled 19.0 billion 
kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, $66,011,950 was 
reimbursed to the U.S. Treasury to recover Corps of Engineers 
project investment and operating costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. During fiscal year 
362,501,000 kilowatt-hours of electrical energy were generated 
at project of which 359,484,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by the Detroit Lake project on 
North Santiam River are shown in Table 37-M. 
43. GREEN PETER-FOSTER LAKES, OR 
Location. At approximate mile 5.5 on Middle Santiam 
River which joins South Santiam River about 56.8 miles 
above its confluence with Willamette River. Dam is about 30 
miles southeast of Albany in Linn County, OR. 
Existing project. Main dam and a reregulating dam, both 
with power-generating facilities. Green Peter Dam is a concrete 
gravity structure, 1,400 feet long and 385 feet high 
above the lowest point of the general foundation with a gatecontrolled 
spillway. Outlet works consist of two conduits 
through spillway, discharging into a stilling basin. 
Powerplant, on right bank adjacent to spillway stilling basin, 
consists of two units with an installed capacity of 80,000 
kilowatts. Reservoir provides storage capacity at full pool of 
430,000 acre-feet, extending 6.5 miles up Quartzville Creek 
and some 7.5 miles up Middle Santiam River above creek 
junction, forming a Y- shaped pool. Reservoir controls 
runoff of tributary drainage area of 277 square miles. 
37-17

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Foster Dam, 7 miles downstream from Green Peter Dam is 
located on South Santiam River about 38 miles above its 
confluence with Santiam River and 1.5 miles below its confluence 
with Middle Santiam River. Foster Dam consists of an 
earth, gravel, and rock-filled embankment, 146 feet high 
from lowest point of the general foundation and a concrete 
gravity gate controlled spillway and stilling basin for a total 
length of 4,800 feet. Power installation consists of two units 
with capacity of 20,000 kilowatts. Foster Lake has a storage 
capacity, at full pool, of 61,000 acre-feet. Project functions as 
a unit in coordinated system of reservoirs for multiple-purpose 
development of water resources in Willamette River 
Basin. 
All construction on Green Peter-Foster Lakes project initiated 
June 1961 is completed. Green Peter Lake was placed 
in operation for useful flood control June 1967 as a unit of 
coordinated reservoir system for protection of the Willamette 
River Basin. First power- generation unit was placed 
on the line June 9, 1967 and second, June 28, 1967. Use of 
Foster Lake for reregulating fluctuating flows from Green 
Peter units was effective December 1967. First power generation 
unit was placed on-line August 22, 1968 and second, 
September 6, 1968. Through September 1992 power generation 
totaled 8.6 billion kilowatt-hours. Of the gross income 
from sale of this power by Bonneville Power Administration, 
$51,133,988 was reimbursed to the U.S. Treasury to recover 
Corps of Engineers project investment and operating costs. 
Local cooperation. Future recreation development at Foster 
or Green Peter will require cost sharing. Recreation facilities 
at Foster Lake includes 4 parks and 2 parks at Green 
Peter Lake. Five of these parks were developed by the Corps 
and are operated by Linn county under lease agreement. One 
park is operated by the Corps. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. During the fiscal year 
271,991,000 kilowatt-hours of electrical energy were generated 
at project of which 269,581,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Green Peter Lake project 
on Middle Santiam River are shown in Table 37-M. 
44. HILLS CREEK LAKE, OR 
Location. On the Middle Fork, Willamette River, 47.8 
miles from mouth and 26.5 miles upstream from Lookout 
Point Dam. Middle Fork, Willamette River rises on west 
slope of Cascade Range and flows northwesterly to its junction 
with Coast Fork, Willamette River. Dam is about 45 
miles southeast from Eugene, OR. 
Existing project. An earth-and-gravel-fill dam about 
2,150 feet long at the crest and 338 feet above lowest point of 
the general foundation. A gate-controlled concrete gravity 
chute-type spillway is in right abutment. Diversion tunnel, 
outlet tunnel and power tunnel are in same abutment. Powerhouse 
with two 15,000 kilowatt units is located next to 
spillway. Hills Creek Lake is about 8.5 miles long and provides 
storage capacity at full pool of 356,000 acre-feet. Project 
controls runoff of drainage area of 389 square miles and 
is an integral unit of comprehensive plan for development of 
water resources of Willamette River Basin. Hills Creek Lake 
and Lookout Point Lake are operated as a unit for control of 
floods and generation of power on Middle Fork Willamette 
River. These projects, in conjunction with Dexter reregulating 
dam and Fall Creek Lake flood control system, will effectively 
control floods on Middle Fork and provide maximum 
efficient generation of hydroelectric power. Recreation facilities 
are provided by the U.S. Forest Service. Hills Creek 
power units are remote controlled from Lookout Point. 
Construction of project, initiated May 1956, was completed 
June 1963. The project was placed in service for useful flood 
control in November 1961. On May 2, 1962, the two power 
units were placed on-line. Through September 1992, power 
generation totaled 4.7 billion kilowatt-hours. Of the gross 
income from sale of this power by Bonneville Power Administration, 
$20,409,081 was reimbursed to the U.S. Treasury to 
recover Corps of Engineers project investment and operating 
costs. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. During fiscal year, 
119,529,000 kilowatt-hours of electrical energy were generated 
at project, of which 118,944,000 kilowatt-hours were 
delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Hills Creek Lake on Middle 
Fork Willamette River are shown in Table 37-M. 
45. JOHN DAY LOCK AND DAM - LAKE 
UMATILLA, OR AND WA 
Location. On Columbia River about 3 miles downstream 
from mouth of John Day River and about 215 miles above 
mouth of Columbia River. 
Existing project. A dam, powerplant, navigation lock, fish 
ladders, and appurtenant facilities with a slack-water lake 
about 75 miles long extending to McNary Lock and Dam. 
Included is relocation of railroads, highways, utilities, and 
communities affected by the impoundment. The project as 
originally authorized would have provided 2,000,000 acrefeet 
of flood control storage. As modified, the project provides 
500,000 acre-feet of flood control storage between 
elevations 257 and 268. The structure is 5,900 feet in length 
and stands about 161 feet above streambed. Powerhouse has 
space for 20 generating units of 135,000 kilowatts each; 16 
units have been installed for a present capacity of 2,160,000 
kilowatts. Principal project data are set forth in Table 37-N. 
A detailed description of project as authorized and modified 
is on pages 1992 and 1993 of Annual Report for 1962 
under the Walla Walla District. 
Construction began July 1958 and the project was opened 
to navigation April 1968. The main dam contract is complete. 
Lock rehabilitation work begun in FY 1980 was completed in 
FY 1986. Entire project is estimated to be 99 percent complete. 
Through September 1992 power generation totaled 
249.0 billion kilowatt-hour. Of the gross income from sale of 
this power by Bonneville Power Administration, 
$337,591,745 was reimbursed to the U.S. Treasury to recover 
Corps of Engineers project investment and operating costs. 
37-18

PORTLAND, OREGON DISTRICT 
Estimated Federal cost of new work is $513,168,000, consisting 
of $512,835,000 Corps of Engineers and $333,000 for 
Coast Guard navigation aids. 
Local cooperation. Recreation facilities at 5 parks are operated 
and maintained by local agencies under lease agreement 
with the Corps. Six developed recreation areas are operated 
and maintained by the Corps of Engineers. Any future recreation 
development will require cost sharing. 
Operations during fiscal year. New work: Work continued 
on modifications to the fish bypass system. 
Maintenance: Increased activities to protect and enhance 
the anadromous fisheries in the Northwest were performed. 
Routine operation and maintenance continued. During fiscal 
year 8,792,280,000 kilowatt-hours of electrical power were 
generated by the 16 generating units of which 8,774,750,000 
kilowatt-hours were delivered to Bonneville Power Administration, 
the marketing agency. 
Rehabilitation: Work continued on refurbishment of one 
generator winding and rebuilding (to strengthen) one turbine, 
installation of the new control system to increase reliability 
and ease of operation of the powerhouse, and on the 
station service improvement contract which will allow black 
start up of the powerhouse. Final major contract for rewinding 
of 5 generators was awarded. 
46. LOOKOUT POINT - DEXTER LAKES, OR 
Location. On Middle Fork, Willamette River at Meridian 
site, 21.3 miles from mouth. Middle Fork, Willamette River, 
rises in Lane County on western slope of Cascade Range and 
flows northwesterly to its junction with Coast Fork, which is 
head of mainstem Willamette River. Dam is about 22 miles 
southeast from Eugene, OR. 
Existing project. A main dam at Meridian site and a 
reregulating dam 3 miles downstream at Dexter site. Both 
dams are earth-and-gravel- fills with concrete spillways and 
have power generating facilities. Main dam is 258 feet high 
from lowest point of the general foundation to deck and is 
3,381 feet long at crest forming a reservoir 14.2 miles long 
providing storage of 456,000 acre-feet at full-pool level. 
Reservoir controls runoff of tributary drainage area of 991 
square miles. Spillway, 274 feet long, is a gate-controlled 
overflow type, forming right abutment. Outlet works consisting 
of slide- gate-controlled conduits pass through spillway 
section. Powerhouse has three main generating units with a 
capacity of 120,000 kilowatts. Dexter reregulating dam has a 
maximum height of 107 feet above lowest point of the general 
foundation and is 2,765 feet long at crest, forming a full pool 
of 27,500 acre-feet extending upstream to main dam and 
providing pondage to regulate Lookout Point powerhouse 
water releases to a uniform discharge. Spillway consists of a 
gate-controlled overflow section 509 feet long forming right 
abutment. 
Flow regulation is accomplished by use of spillway gates 
and releases through powerhouse, which contains one 
15,000-kilowatt unit. Lookout Point and Dexter Lakes are 
operated as a single unit of a coordinated system of reservoirs 
to protect Willamette River Valley against floods, to provide 
needed hydroelectric power, and to increase low water flows 
for navigation, irrigation, and other purposes. Existing project 
authorized as a unit of comprehensive plan for flood 
control and other purposes in Willamette River Basin. 
Construction of project initiated May 1947 was completed 
June 1961, except for construction of additional recreation 
facilities funded through the Code 710 program. Future recreation 
facilities will be provided in accordance with the costsharing 
contract with Lane County and will require a 50 
percent contribution by Lane County and is subject to funding 
availability by the Government and the County. At Lookout 
Point powerhouse, generating units 1,2, and 3 were 
placed in commercial operation December 1954, February 
1955, and April 1955, respectively. At Dexter powerhouse 
the single unit was placed on- line May 1955. Dexter was 
placed in operation for reregulation in December 1954. 
Through September 1992 power generation totaled 15.1 billion 
kilowatt-hours. Of the gross income from sale of this 
power by Bonneville Power Administration, $70,881,547 was 
reimbursed to the U.S. Treasury to recover Corps of Engineers 
project investment and operating costs. 
Local cooperation. A multiple project cost sharing agreement 
has been in force with Lane County since September 
1976. It includes 4 projects and 13 parks. All these parks are 
managed by Lane County under lease agreement. Recreation 
opportunities are provided at 2 parks on Dexter Lake which 
are operated by Lane County via the multi-project cost-sharing 
agreement and lease instruments. The north shore of 
Lookout Point Lake is also:leased to Lane County for recreation 
purposes; there is essentially no development. Future 
development will require a supplement to the cost sharing 
agreement. 
Operations during fiscal year. Maintenance: Studies to 
rewind/uprate the generators continued. Routine operation 
and maintenance continued. During fiscal year, 285,046,000 
kilowatt-hours of electrical power energy were generated at 
project of which 283,217,000 kilowatt-hours were delivered 
to Bonneville Power Administration, the marketing agency. 
Freshets regulated by Lookout Point Lake project on Middle 
Fork Willamette River are shown in Table 37-M. 
47. LOST CREEK LAKE, ROGUE RIVER 
BASIN, OR 
Location. On Upper Rogue River at mile 153.6 about 30 
miles northeasterly from Medford, OR. 
Existing project. A rock and gravel-fill embankment dam 
about 327 feet high from streambed to crest, with an overall 
length of 3,750 feet with an impervious earth core and a 
gate-controlled concrete spillway. Powerhouse is on right 
abutment and houses two Francis-type turbines with installed 
capacity of 24,500 kilowatts each. Regulating outlet 
facility was provisions for temperature regulation for releases 
in interest of fishery enhancement is also on right bank. 
Reservoir 10 miles long provides 315,000 acre-feet of usable 
storage. Project provides control of runoff of drainage area of 
674 square miles. In addition to hydroelectric power generation, 
project provides flood control, irrigation, future municipal 
and industrial (M&I) water supply, fish and wildlife enhancement, 
water quality control and recreation benefits. 
37-19

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Construction of project initiated July 1967 is complete. 
Generating units 1 and 2 were placed in commercial operation 
July 6 and July 13, 1977, respectively. Physical in-service 
date for flood control was February 18, 1977. Final environmental 
statement was filed with Council on Environmental 
Quality in June 1972. Recreation opportunities are provided 
by 4 parks at the project. The State of Oregon operates 2 
parks, including a 200 unit campground, part of Stewart State 
Park. Through September 1992, power generation totaled 
4.2 billion kilowatt-hours. Of the gross income from sale of 
this power by Bonneville Power Administration, $25,165,074 
was reimbursed to the U.S. Treasury to recover Corps of 
Engineers project investment and operating costs. 
Local cooperation. Authorizing act required that local 
agencies furnish assurances prior to construction that demands 
will be made for future use of water supply storage 
within a period that will permit repayment of costs, including 
interest, allocated to water supply within life of the project; 
that State of Oregon take action, prior to construction to 
insure maintenance in stream of flows to be released for 
fishery; in addition, costs allocated to irrigation would have to 
be repaid in manner and to an extent consistent with reclamation 
laws and policies; and costs allocated to power will be 
repaid on a system basis by revenue from sales of power in 
Pacific Northwest Federal system by Bonneville Power Administration. 
A survey in September, 1980 of M&I water 
supply needs showed nine communities with water supply 
needs. A contract for M&I supply has been completed with 
one of the communities. Assurances for municipal and industrial 
water supply were obtained from six communities in 
Rogue River Valley. On February 26, 1966 Oregon State 
Department of Fish and Wildlife agreed to operate Cole M. 
Rivers Fish Hatchery for mitigation and enhancement of fish. 
The Corps provides full funding for the operation and maintenance 
of the hatchery. The hatchery became operational in 
1972. 
Operations during fiscal year. Maintenance: Routine operation 
and maintenance continued. During fiscal year 
193,193,000 kilowatt-hours of electrical power energy were 
generated by the project of which 190,414,000 kilowatt-hours 
were delivered to Bonneville Power Administration, the marketing 
agency. Freshets regulated by Lost Creek Lake on 
Rogue River are shown in Table 37-M. 
48. THE DALLES LOCK AND DAM - LAKE 
CELILO, WA AND OR 
Location. On Columbia River at head of pool behind Bonneville 
Dam, about 192 miles above mouth of river and 88 
miles east of Portland, OR. 
Existing project. A dam, powerplant, navigation lock, and 
appurtenant facilities. Improvement provides for navigation 
and hydroelectric power generation. Dam is designed for a 
normal pool at elevation 160 feet at mean sea level. Normal 
pool forms a reservoir extending upstream about 23 miles 
providing slackwater to John Day Dam site. The Dalles Dam 
is 8,700 feet long and consists of a rock, gravel, and sand river 
closure section from Oregon shore connecting to a nonoverflow 
section which in turn joins powerhouse, then concrete 
nonoverflow sections connecting spillway with powerhouse 
and spillway with navigation lock at right abutment on Washington 
shore. Fish-passing facilities including two ladders 
and a fish lock are provided. Powerhouse was constructed for 
14 units initially with substructure for eight additional units, 
an ultimate total of 22 units. Initial installation, excluding two 
13,500 kilowatt fish-water units, is 1,092,000 kilowatts. With 
eight units installed for a capacity of 687,800 kilowatts. The 
total generating capacity is 1,806,800 kilowatts. Structures 
are founded on Columbia River basalt. Principal data concerning 
lock, spillway, and powerhouse are set forth in Table 
37-N. 
Major construction of project initiated February 1952, was 
completed October 1960 when unit No. 14 was placed in 
commercial operation. Initial contract for additional units 
15-22 was awarded in September 1967. Additional 8-unit 
phase was completed when unit 22 was placed in commercial 
operation in November 1973. Basic recreation facilities were 
developed with construction funds at 4 parks on Lake Celilo. 
These parks were further expanded with code 710 funds in 
the late 60's and early 70's. Two parks are operated by Washington 
State Park Commission under a lease agreement. 
Studies for adding power generation facilities to the North 
Shore Fish Ladder Auxiliary Water supply System were initiated 
in October 1979 and completed in December 1980. 
These facilities would provide baseload generation (3.5 
megawatts) and would not impact the present operation of 
the North Fish Ladder. However, it was determined that it 
was not within the Chief of Engineer's authority to add these 
power facilities. A local interest, North Wasco County Public 
Utility District pursued the construction of these power facilities 
through the FERC license processes and awarded a 
construction contract in September 1989. Seufert Visitor 
Center was completed in September 1980. Through September 
1992, power generation totaled 250.0 billion kilowatthours. 
Of the gross income from sale of this power by Bonneville 
Power Administration, $329,601,002 was reimbursed 
to the U.S. Treasury to recover Corps of Engineers project 
investment and operating costs. 
Local cooperation. Further recreation development will 
require cost sharing and assumption of operation and maintenance 
by local, non-federal sponsor. 
Operations during fiscal year. New Work: Engineering 
and design activities associated with preparation of a general 
design memorandum for juvenile fish bypass facilities continued. 
Maintenance: Increased activities to protect and enhance 
the anadromous fisheries in the Northwest were performed. 
Studies to rehabilitate the fishwater generators and generating 
units 1-22 are continuing. Routine operation and maintenance 
continued. During fiscal year 6,901,235,000 kilowatthours 
of electrical power energy were generated at project of 
which 6,883,894,000 kilowatt-hours were delivered to Bonneville 
Power Administration, the marketing agency. 
37-20

PORTLAND, OREGON DISTRICT 
General Investigations 
49. SURVEYS 
Fiscal year costs were $919,005 of which $180,526 was for 
navigation studies, $578,460 for flood damage prevention 
studies, $0 for comprehensive studies, $131,639 for miscellaneous 
activities, and $28,380 for coordination with other 
agencies. Contributed funds in the amount of $28,485 were 
expended of which $27,419 was contributed by the International 
Port of Coos Bay for the Coos Bay navigation study and 
$1,066 was contributed by the State of Oregon for a dredged 
material disposal study. 
50. COLLECTION AND STUDY OF BASIC 
DATA 
Flood plain management services. Flood Plain Management 
Services Program comes under Section 206 of the 1960 
Flood Control Act, PL 86-645, as amended. Through technical 
services and planning guidance, the program encourages 
comprehensive flood plain management planning at all levels 
to reduce the potential for losses to life and property from 
floods. Federal and non- Federal agencies and the private 
sector are assisted with planning and development information 
for flood hazard areas. This assistance is in the form of 
local flood plain regulations, Federal Insurance Program requirements, 
and Executive Order 11988 guidelines. Such 
assistance may include factual flood information (available or 
determined) and interpretation on flood frequencies, extent 
of flooding, flood-water velocity, duration of flooding and 
floodway limits. 
Technical services and planning guidance responses furnished 
totaled 724. 
Fiscal year costs totaling $110,443 were associated with the 
following tasks under the Flood Plain Management Services 
Program: FPMS Unit $20,425; Technical Services $75,248; 
Quick Responses $4,834; and a special study for Portland 
Metro $9,936. Contributed funds in the amount of $4,198 
were expended for technical services. 
51. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
Columbia River Treaty Fishing Access Sites, OR and WA 
The authorized plan includes land management, acquisition, 
and river access facility development for Indian tribes 
who exercise treaty fishing rights on the Columbia River, 
Oregon and Washington. Public Law 100-581 Title IV designates 
21 sites on Bonneville, The Dalles, and John Day pools 
for treaty fishing use and authorizes the acquisition of 6 
additional sites on Bonneville pool from willing sellers. The 
law specifies the construction of access roads, boat ramps, 
dock sanitation, fish cleaning facilities, and others at these 
locations and provides additional authority for facility improvements 
at five sites currently administered for treaty 
fishing access resulting from construction of Bonneville 
Dam. 
Fiscal year work consisted of completion of the Phase I 
Evaluation Report. Fiscal year expenditures were $505,981. 
37-21

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-A COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY89 FY90 FY91 FY92 to 
In Text Sep.30, 1992 
1. Bonneville Navigation 
Lock, Bonneville Dam, 
OR and WA 
(Federal Funds) 
(Inland Waterway 
Trust Fund) 
2. Chetco River, OR 
3. Columbia and Lower 
Willamette Rivers 
Below Vancouver, 
WA and Portland, OR 
(Federal Funds) 
(Contributed Funds) 
4. Columbia River at 
Baker Bay, WA 
5. Columbia River 
Between Chinook, 
WA, and Head of 
Sand Island 
6. Columbia River at 
The Mouth, OR and 
WA 
7. Columbia River 
Between Vancouver, 
WA and The Dalles 
OR 
8. Columbia River, 
Seafarers Memorial, 
Hammond, OR 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
24,150,000 19,298,000 38,949,000 32,440,000 
14,050,665 29,331,438 38,867,937 32,423,462 
24,150,000 19,298,000 38,949,000 32,440,000 
12,732,518 30,987,600 38,864,327 32,417,676 
132,000 382,047 489,000 342,000 
129,856 373,100 500,675 341,065 
12,630,000 8,928,540 10,496,000 10,887,000 
13,065,333 8,844,097 10,588,846 10,888,793 
515,000 60,902 
516,034 54,872 
34,000 
38,263 
16,000 
16,528 
554,000 53,064 250,000 256,000 
631,348 51,247 249,278 258,564 
8,201,000 6,386,150 6,410,000 7,774,000 
8,207,278 6,183,847 6,571,092 7,761,894 
201,000 281,411 315,000 208,000 
201,199 256,750 335,274 206,931 
50,000 
36,226 
16,000 
15,798 
37-22 
149,389,30761 
149,036,053'1 
149,389,000 
149,133,327 
2,043,713' 
2,043,713' 
7,095,673 
7,094,652 
28,349,3042 
28,349,3042 
303,222,2963 
303,204,4643 
665,9544 
665,9544 
941,252 
941,252 
3,991,087 
3,989,607 
220,2836 
220,2836 
5,916,877 
5,916,861 
24,913,661 
24,913,6616 
127,317,6497 
127,252,3387 
7,322,878 
7,322,878 
5,989,509* 
5,989,509* 
12,952,3599 
12,941,253* 
66,000 
52,024

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY89 FY90 FY91 FY92 to 
In Text Sep.30, 1992 
9. Coos Bay, OR New Work 
(Federal Funds) 
(Contributed Funds) 
10. Coquille River, OR 
11. Depoe Bay, OR 
13. Port Orford, OR 
15. Rogue River Harbor 
At Gold Beach, OR 
16. Siuslaw River, OR 
(Federal Funds) 
(Contributed Funds) 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work 
Contrib 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
10,584,000 2,990,266 4,776,500 3,595,000 
10,573,892 2,934,530 4,777,143 3,630,859 
114,000 204,043 
129,841 188,056 
140,000 7,841 
134,729 11,114 
189,000 227,888 
188,579 227,326 
511,000 638,000 
525,445 636,419 
7,000 
7,743 
7,000 
5,418 
237,000 290,000 
235,425 281,764 
705,000 592,874 1,025,000 944,000 
708,632 565,743 1,050,034 929,545 
353,000 473,285 884,000 781,000 
374,215 452,345 896,203 789,737 
29,750,0920 
29,750,09210 
88,843,718" 
88,791,12211 
2,335,966 
2,335,966 
486,680 
486,680 
693,366'13 
693,366'13 
7,047,98714 
7,043,97014 
367,364 
367,364 
954,717 
949,582 
758,692' 
758,6921' 
3,890,217 
3,878,690 
4,156,252'* 
4,156,252' 
13,127,39417 
13,110,3447 
635,783 
635,783 
29,502,21218 
29,502,21218 
14,137,3841* 
14,135,433' 
879,285 
879,285 
493,611 
493,611 
37-23

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY89 FY90 FY91 FY92 to 
In Text Sep.30, 1992 
17. Skipanon Channel, New Work 
18. Tillamook Bay and 
Bar, OR 
19. Tongue Point, OR 
(Federal Funds) 
(Contributed Funds) 
20. Umpqua River, OR 
21. Willamette River at 
Willamette Falls, OR 
22. Yaquina Bay and 
Harbor, OR 
23. Applegate Lake, 
Rogue River Basin 
OR 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
224,000 120,050 
224,676 119,727 
9,000 
3,149 
57.500 143,792 3,596,000 
59,942 132,773 3,535,492 
2,030,000 
2,123,166 
1,779,100 
261,787 
500,000 
463,585 
1,578,138 
19,000 
21,311 
-45,000 
15,405 
- 26,376 
8,902 64,363 
- -92,592 
392 -64,309 
661,000 677,204 1,291,000 869,000 
662,499 642,729 1,317,613 874,091 
610,000 571,995 620,000 664,000 
619,085 539,137 624,494 684,759 
686,000 692,556 1,601,500 1,603,000 
713,859 644,105 1,648,282 1,602,679 
11,238 
437,000 
460,289 
441,415 425,000 519,000 
435,982 425,054 511,520 
OR 
37-24 
280,854 
280,854 
3,505,064 
3,501,056 
22,434,82720 
22,434,82720 
6,718,08221 
6,706,50621 
2,839,799 
2,839,799 
2,807,876 
2,807,876 
1,776,008 '2 
1,776,00812 
17,718,87722 
17,718,877 
27,771,093 
27,767,423 
2,500,677 
2,500,677 
520,00523 
520,00523 
18,332,81824 
18,323,30524 
234,794 
234,794 
19,242,04620 
19,242,04620 
32,491,7582 
32,489,509 
12,005 
12,005 
91,642,489 
91,642,489 
5,603,1154* 
5,588,7904*

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY89 FY90 FY91 FY92 to 
In Text Sep.30, 1992 
24. Blue River Lake, OR 
25. Cottage Grove Lake, 
OR 
26. Dorena Lake, OR 
27. Elk Creek Lake, 
Rogue River Basin, 
OR 
28. Fall Creek Lake, OR 
29. Fern Ridge Lake, OR 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
32. Lower Columbia River New Work 
Basin Bank Protection Approp. 
OR & WA Cost 
33. Mill Creek, Salem, OR New Work 
(Federal Funds) Approp. 
Cost 
New Work 
(Contributed Funds) Contrib. 
Cost 
34. Mt. St. Helens New Work 
Sediment Control, WA Approp 
(Federal Funds) Cost 
(Contributed Funds) New Work 
Contrib. 
Cost 
Maint. 
Approp. 
Cost 
135,000 145,308 147,000 182,000 
135,957 139,048 144,629 178,433 
663,000 731,610 622,000 434,000 
690,448 723,552 575,680 487,367 
705,115 512,171 418,000 
711,406 513,852 380,554 
5,911,000 1,190,000 2,054,000 
6,361,434 1,445,595 1,732,568 
361,000 434,256 510,000 
359,851 419,192 470,766 
61,000 
60,840 
747,000 719,564 744,000 
755,964 701,482 750,600 
76,000 86,000 
74,921 24,832 
27,000 137,000 
14,238 140,393 
18,900 
16,000 
25,000 
38,684 
1,531 
411,000 
418,433 
1,110,000 
1,226,541 
616,000 
663,086 
6,000 
4,823 
912,000 
919,406 
23,000 
45,084 
-9,600 
1,203 
-100 
12,195,000 11,567,000 1,824,000 
27,743,424 12,507,990 1,695,82 536,658 
149,240 
3,500,000 149,240 
389,000 396,000 
383,937 389,294 
37-25 
32,038,22527 
32,038,22527 
2,970,299 
2,957,338 
4,013,1232 
4,013,1232 
11,960,2882 
11,935,694@ 
14,568,26230 
14,568,26230 
7,557,460 
7,506,733 
103,894,579 
103,645,480 
22,118,2643' 
22,118,2643' 
6,706,671 
6,683,141 
8,593,9353 
8,592,5983 
16.379,1983 
16,355,7853 
21,005,745 
20,978,465 
190,900 
190,892 
18,900 
15,900 
111,719,000 
111,548,694 
3,649,240 
3,649,240 
785,000 
773,231

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY89 FY90 FY91 FY92 to 
In Text Sep.30, 1992 
36. Willamette River New Work 
Basin Bank Protection, 
OR 
37. Willow Creek Lake, OR 
38. Bonneville Lock and 
Dam - Lake Bonneville 
OR and WA 
39. Columbia and Snake 
Rivers, Ports Dredging, 
OR and WA 
40. Columbia River 
Juvenile Fish 
Mitigation Program 
(The Dalles Project), 
OR and WA 
41. Cougar Lake, OR 
42. Detroit Lake - Big Cliff, 
OR 
Approp. 
Cost 
Maint 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab 
Approp 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
43. Green Peter-Foster 
Lakes, OR 
44. Hills Creek Lake, OR 
30,000 
25,308 
65,000 
62,717 
86,000 
34,897 
27,965 
35,039 
-25,000 
30,800 
82,000 
67,732 
30,000 
14,332 
687,000 490,051 432,000 
685,094 470,052 457,792 
1,152,000 
2,405,289 
10,727,000 
10,813,072 
4,115,000 
3,851,145 
12,090,262 
11,967,851 
3,911,000 
3,888,349 
12,153,300 
12,417,302 
56,000 
61,566 
25,000 
40,420 
420,000 
412,532 
2,716,000 
2,888,142 
13,393,000 
13,161,143 
5,630,000 
5,587,370 
1,343,000 3,804,000 
1,114,175 3,434,045 
786,000 795,480 913,000 920,000 
818,440 743,983 860,144 989,556 
1,539,000 1,569,935 1,720,000 1,699,000 
1,530,767 1,575,262 1,597,219 1,811,308 
1,773,000 1,932,671 2,118,000 1,981,000 
1,822,417 1,926,322 2,072,319 2,038,785 
595,000 524,108 627,000 601,000 
592,142 529,110 612,945 606,010 
37-26 
TABLE 37-A 
(Continued) 
24,843,816M 
24,843,816# 
3,922,709 
3,913,109 
37,223,114 
37,222,866 
3,899,051 
3,878,067 
776,138,6043@ 
775,817,4783 
200,899,66336 
200,423,88438 
5,630,000 
5,587,370 
5,147,000 
4,548,220 
58,636,393** 
58,636,39337 
14,901,29660 
14,866,1386 
62,729,698 
62,729,698 
33,239,707* 
33,209,547 
363,086 
363,086 
84,005,7883 
84,005,7883 
31,606,8033 
31,595,9853 
45,700,619 
45,700,619 
10,542,37540 
10,532,09640

PORTLAND, OREGON DISTRICT 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See Total Cost 
Section Project Funding FY89 FY90 FY91 FY92 to 
In Text Sep.30, 1992 
45. John Day Lock and New Work 
Dam - Lake Umatilla, Approp. 39,000 145,000 - 512,400,24641 
OR and WA Cost 55,598 100,501 123,266 51,754 512,388,44341 
Maint. 
Approp. 8,019,500 10,113,768 11,045,300 10,719,000 145,622,72742 
Cost 7,983,895 10,019,973 10,985,601 10,906,494 145,390,49442 
Major Rehab. 
Approp. 2,725,000 3,328,128 735,000 2,134,000 28,405,128 
Cost 2,702,857 3,455,386 761,975 2,073,299 28,332,732 
46. Lookout Point - Dexter New Work 
Lakes, OR Approp. 88,238,39543 
Cost 88,238,39543 
Maint. 
Approp. 3,085,000 2,991,027 3,468,000 3,265,000 51,564,632" 
Cost 3,144,995 2,976,150 3,333,658 3,399,006 51,493,938" 
47. Lost Creek Lake, New Work 
Rogue River Approp. 136,408,150 
Basin, OR Cost 7,688 136,408,150 
Maint 
Approp. 2,657,000 2,888,918 2,996,000 3,149,000 33,776,718 4 
Cost 2,646,763 2,957,551 3,039,651 3,114,685 33,732,0584" 
48. The Dalles Lock and New Work 
Dam - Lake Celilo, Approp. 1,210,000 986,000 - 303,260,28848 
WA and OR Cost 488,415 1,477,796 229,789 303,260,28848 
Maint. 
Approp. 7,695,000 8,114,362 8,214,300 9,700,000 131,519,67047 
Cost 7,721,519 8,154,857 7,921,077 10,024,491 131,311,66347 
1. Excludes $17,742 contributed funds for new work. 
2. Includes $1,529,413 for previous project. 
3. Includes $150,955 allotted from deferred maintenance funds, 
Code 700, $62,296 for public works accelerated program repair, 
and $1,214,865 for previous project. Excludes $24,320 expended 
from contributed funds prior to 1964. 
4. Excludes $31,636 contributed by city of Astoria and Bumble Bee 
Sea Foods, Astoria, OR (not part of regular project). Includes 
$223,026 expended from contributed funds prior to 1964 and 
$428,136 contributed by Port of Portland and $14,792 by Port of 
Vancouver. 
5. Includes $84,930 rehabilitation funds. 
6. Includes $1,986,253 for previous project and $608,111 allotted 
and expended under Code 710, recreation facilities at completed 
project. Excludes $500,000 contributed funds. 
7. Includes $2,186,000 for previous project and $1,188,625 under 
deferred maintenance, Code 700. 
8. Includes funds under Code 721 (small authorized projects) 
$30,393. Entrance to Oregon slough; $161,897, Camas-Washougal 
Turning Basin; $227,908, Hood River Small Boat Basin; $157,470, 
Bingen, WA, Barge Channel; and $140,619, The Dalles Small 
Boat Basin. 
9. Includes $2,033,408 under code 700 (Deferred Maintenance). 
10. Includes $802,096 for previous project, Excludes contributed 
funds. 
11.Includes $178,801 for previous project and $1,444,640 under 
Code 700, Deferred Maintenance. Excludes $8,387 contributed 
funds. 
12. Excludes $97,339 in-kind services. 
13. Includes $340,726 for previous project. Excludes $72,891 
contributed funds. includes $36,000 under Code 711. 
14. Includes $41,467 for previous project and $78,500 under Code 
700, Deferred Maintenance. 
15. Excludes $9,900 contributed funds. 
16. Excludes $13,779 (other funds) contributed for additional 
landfill and extension of drainage lines. 
17. Includes $21,000, Wedderburn Study Funds. 
18. Includes $1,159,357 for previous project. 
19. Includes $10,611 for previous project and $188,000 under code 
700, Deferred Maintenance. 
20. Includes $77,209 for previous project and $57,767 under Code 
720 (Small Authorized Projects) Garibaldi Boat Basin. Excludes 
$592,622 contributed funds and $300,000 channel dredging by local 
interest. 
21. Includes $71,498 for previous project. Excludes $6,450 
expended from contributed funds. 
22. Includes $39,242 for previous project. Excludes $6,450 
expended from contributed funds. 
23. Excludes $300,000 contributed funds. 
24. Includes $452,110 on operation and care from permanent 
indefinite appropriation and $150,000 under maintenance and 
operation of dams and other improvements of navigable waters. 
25. Includes $707,313 for previous project and $170,000 
appropriated from public works acceleration program for north 
jetty rehabilitation. 
26. Includes $6,026 for previous project. 
27. Includes $96,000 pro rata share of site selection costs in lieu of 
Quartz Creek Lake. 
28. Includes $1,639,828 allotted and expended under Code 710, 
recreation facilities at completed project. 
29. Includes $167,878 special recreation use fees. Includes $66,678 
under maintenance and operation of dams and other 
improvements to navigable waters. 
37-27

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
30. Includes $1,038,790 allotted and expended under Code 710, 
recreation facilities at completed project. 
31. Includes $1,026,264 allotted and expended under Code 710, 
recreation facilities at completed project. 
32. Includes $3,894,673 allotted and expended under Code 710, 
recreation facilities at completed project and $136,482 allotted 
under 721 (small authorized project) reservoir modification. 
Excludes $2,100 other funds contributed). 
33. Includes $9,750 allotted under Code 00, deferred 
maintenance. Includes $66,678 under maintenance and operation 
of dams and other improvements to navigable waters. 
34. Excludes $93,733 contributed funds. 
35. Includes $12,200,000 Public Works Administration funds, 
$20,240,700 National Recover Act Funds, $27,195,400 modification 
for peaking funds, $136,457 Code 710, recreation facilities at 
completed project funds and $627,593,352 allotted and 
$642,322,501 expended second powerhouse funds, $6,000 allotted, 
$6,000 expended power units funds. 
36. Includes $540,000 deferred maintenance funds, Code 700 and 
$1,692,148 maintenance and operation of dams and other 
improvements of navigable waters. 
37. Includes $96,000 pro rata share of site selection costs.in lieu of 
Quartz Creek Lake. Includes $1,789,988 allotted and $1,789,954 
expended for Strube Lake and Cougar Additional Unit. 
38. Includes $113,000 pro rata share of site selection costs in lieu 
of Quartz Creek Lake. 
39. Includes $587,078 under maintenance and operation of dams 
and other improvements of navigable waters. 
40. Includes $75,400 under maintenance and operation of dams 
and other improvements of navigable waters. 
41. Includes $25,984 allotted and expended under 710, recreation 
facilities at completed projects. 
42. Includes $1,361,900 for O&M and fish evaluation of Spring 
Creek Hatchery (funds revoked and paid to USFWS at OCE level, 
but a cost to project); includes $423,800 special recreation use fees. 
Includes $933,438 under maintenance and operation of dams and 
other improvements of navigable waters. 
43. Includes $457,611 allotted and expended under 710, recreation 
facilities at completed projects. 
44. Includes $592,078 under maintenance and operation of dams 
and other improvements of navigable waters. 
45. Includes $586,878 under maintenance and operation of dams 
and other improvements of navigable waters. 
46. Includes $1,140,747 allotted and expended under 710, 
recreation facilities at completed projects, and $52,997,220 allotted 
and expended additional units 15 - 22 funds. 
47. Includes $721,490 under maintenance and operation of dams 
and other improvements of navigable waters. 
48. Includes $535,578 under maintenance and operation of dams 
and other improvements of navigable waters. 
49. Includes $66,678 under maintenance and operation of dams 
and other improvements of navigable waters. 
50. Includes $460,178 under maintenance and operation of dams 
and other improvements of navigable waters. 
51. Includes $24,307 under code 422 General Investigation. 
37-28

PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. BONNEVILLE NAVIGATION LOCK, BONNEVILLE DAM, OR AND WA 
Construction of a new navigation lock just south P. L 99-88 
of existing lock. 
Construction to be funded 50% from fuel taxes paid P.L 99-662 
into Inland Waterways Trust Fund. 
CHETCO RIVER, OR 
To provide for the stabilization of the channel, 
by constructing jetties and dredging. 
Modification of channel entrance and channel 
improvements. 
Deepen channel 2 feet to 16 feet, extend the existing 
jetty system 750 feet for the North, and 1,250 feet 
for the South jetty. 
H. Doc. 817, 77th Cong., 2d Sess 
S. Doc. 21, 89th Cong., 1st Sess. 
S. Doc. 10, 96th Cong., 1st Sess. 
3. 
Feb 27, 1911 
Jul 25, 1912 
Jul 27, 1916 
Aug 08, 1917 
Sep 22, 1922 
Mar 04, 1923 2 
Mar 03, 1925 
Mar 03, 1927 
Jul 03, 1930 
Sep 06, 19333 
Aug 30, 1935 
Aug 30, 1935 
Aug 30, 1935 
Aug 26, 1937 
Aug 26, 1937 
Mar 02, 1945 
Mar 02, 1945 
Jul 24, 1946 
COLUMBIA AND LOWER WILLAMETTE RIVERS BELOW 
VANCOUVER, WA AND PORTLAND, OR 
2 pipeline dredges and accessories. H. Doc. 1278, 61st Cong., 3d Sess.1 
Increasing main channel to 30 feet. H. Doc. 1278, 61st Cong., 3d Sess.1 
Consolidating improvement below Portland, OR and No Prior Report 
between Vancouver, WA and mouth of Willamette. 
For the Cathlamet channel. H. Doc. 120, 63d Cong., 1st Sess.1 
Construct an additional dredge (dredge was not built) H. Doc. 1009, 66th Cong., 3d Sess. 
and accessories for better maintenance, and 
construct contraction works. 
Channel from deep water in Willamette Slough to H. Doc. 156, 67th Cong., 2d Sess. 
deep water in Columbia River. 
Depth of 25 feet and width of 300 feet from mouth of H. Doc 126, 68th Cong., 1st Sess. 
Willamette River to Vancouver, WA 
Closing east channel at Swan Island in Willamette River Rivers and Harbors 
on condition that main channel to be opened to project Committee Doc. 10 
dimensions on west side of island by Port of Portland 69th Cong., 2d Sess. 
For a 35-foot channel 500 feet wide from Portland to H. Doc. 195, 70th Cong., 
the sea. 1st Sess. and Rivers and Harbors 
Committee Doc. 8, 71st Cong., 
1st Sess. 1 
A channel 28 feet deep and 300 feet wide from mouth of H. Doc. 249, 72d Cong., 2d Sess. ' 
Willamette River to Vancouver, with 2 turning 
basins, each generally 28 feet deep by 800 feet wide by 
2,000 feet long. 
A channel in Columbia River from mouth of Willamette Rivers and Harbors 
to interstate highway bridge at Vancouver, WA, Committee Doc. 1, 
30 feet deep and 300 feet wide, with 2 turning 74th Cong., 1st Sess. 
basins at Vancouver. 
Maintenance of not to exceed 35 foot depth at low water Rivers and Harbors 
in Portland Harthr and Willamette River between its Committee Doc. 6, 
mouth and Broadway Bridge at Portland. 73d Cong., 1st Sess. ' 
Auxiliary channels, 30 feet deep, 300 feet and 500 H. Doc. 235, 72d Cong., 1st Sess. ' 
feet at St. Helens. 
Extension of lower turning basin at Vancouver, WA, Rivers and Harbors 
1,000 feet downstream. Committee Doc. 81, 
74th Cong., 2d Sess. 1 
An auxiliary channel 24 feet deep and 200 feet wide H. Doc. 203, 75th Cong., 1st Sess.1 
along waterfront at Rainier, OR. 
Improvement of old mouth of Cowlitz River. H. Doc. 341, 77th Cong., 1st. Sess.1 
An auxiliary channel in vicinity of Longview, WA. H. Doc. 630. 77th Cong., 2d Sess. 1 
A small-boat mooring basin at Astoria, OR. H. Doc. 692, 79th Cong.,2d Sess. 1 
37-29 
TABLE 37-B 
Aug 15, 1985 
Nov 17, 1986 
Mar 02 , 1945 
Oct 27, 1965 
Dec 04, 1981

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
A channel 35 feet deep and 500 feet wide from mouth 
of Willamette River to interstate highway bridge at 
Vancouver, WA, with 2 turning basins of same depth. 
A channel 40 feet deep and 600 feet wide from Vancouver, 
WA, to mouth of Columbia River; a turning basin at 
Vancouver, WA, a turning basin at Longview, WA, and a 
channel 40 feet deep in Willamette River from mouth to 
Broadway Bridge which encompasses Portland Harbor area. 
COLUMBIA RIVER AT BAKER BAY, WA 
East Channel 
Main channel 
West channel 8 feet deep. 
West channel 10 feet deep and mooring basin with 
protecting breakwaters. 
H. Doc. 203, 87th Cong., 1st Sess. 
H. Doc. 452, 87th Cong., 2d Sess. 1 
Public Works Administration 
H. Doc. 44, 73d Cong., 1st Sess. 
H. Doc. 443, 76th Cong., 1st Sess. 
S. Doc. 95, 81st Cong., 1st Sess. 
COLUMBIA RIVER BETWEEN CHINOOK, WA AND HEAD OF SAND ISLAND 
Channel 8 feet deep. Rivers and Harbors Committee 
Doc. 50,75th Cong., 2d Sess. 
Channel 10 feet deep and mooring basin. S. Doc. 8, 83d Cong., 1st Sess.1 
COLUMBIA RIVER AT THE MOUTH, OR AND WA 
Extend South Jetty and construct North Jetty and dredging. 
Construction, operation, and maintenance of recreation 
facilities 
Bar channel of 48-foot depth and spur jetty on north 
shore.9 
Deepening the northernmost 2,000 feet of the channel 
cross section to 55 feet. 
H. Doc. 94, 56th Cong., 1st Sess. 
Sec. 4, Flood Control 
Act of 1944 as amended 
H. Doc. 249, 83d Cong., 2d Sess. 1 
P.L 98-63 
Dec 11, 1933 
Aug 30, 1935 
Mar 02, 1945 
May 17, 1950 
Jun 20, 1938 
Sep 03, 1954 
Mar 03, 1905 
Dec 22, 1944 
Sep 03, 1954 
Jul 30, 1983 
Aug 26, 1937 
Mar 02, 1945 
Jul 24, 1946 
Jul 24, 1946 
Jul 24, 1946 
Jul 24, 1946 
Nov 5. 1990 
COOS BAY, OR 
Dredging the Ocean Bar Channel. 
A channel 22 feet deep to Smith's Mill. 
Restore North Jetty 9,600 feet long, construct a South Jetty 
about 3,900 feet long, extend 22-foot bay channel from 
Smith's Mill to Millington. 
H. Doc. 958, 60th Cong.,lst Sess. 
H. Doc. 325, 65th Cong., 1st Sess. 
H. Doc. 150, 67th Cong., 2d Sess. 
37-30 
Oct 23, 1962 
Oct 23, 1962 
6. 
COLUMBIA RIVER BETWEEN VANCOUVER, WA, AND THE DALLES, OR 
Construct a channel 27 feet deep by 300 feet from H. Committee Doc. 94, 
Vancouver, WA, to Bonneville, OR. 74th Cong., 2d Sess.1 
Construct Camas-Washougal turning basin. H. Doc. 218, 76th Cong., 1st Sess. 
Construct a channel 27 feet deep by 300 feet wide H. Doc. 704, 79th Cong., 2d Sess. 
from Bonneville, OR, to The Dalles, OR. 
Construct a boat basin at Hood River, OR, 10 feet deep, H. Doc. 704, 79th Cong., 2d Sess. 
500 feet wide, by 1,300 feet long. 
Construct a barge channel at Bingen, WA, 10 feet deep, H. Doc. 704, 79th Cong., 2d Sess. 
200 feet wide, by 1 mile long, and an access channel 
7 feet deep, 100 feet wide, by 1,000 feet long to natural 
mooring basin. 
Construct The Dalles Harbor 8 feet deep, 400 feet wide S. Doc. 89, 79th Cong., 1st Sess. 1 
by 800 feet long. 
COLUMBIA RIVER, SEAFARERS MEMORIAL, HAMMOND, OR 
Engineering, design, acquisition and construction of a P. L 101-514; H. R. 101-889, 101st 
support structure to serve as the foundation for the Cong, 2d Sess. 
Seafarer's Memorial in the Columbia River, in cooperation 
with the City of Hammond, Oregon. 
8. 
Jun 25, 1910 
Mar 02, 1919 
Sep 22, 1922

TABLE 37-B 
(Continued) 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Jan 21, 1927 
Jul 03, 1930 
Aug 30, 1935 
Jul 24, 1946 
Jun 30, 1948 
Dec 31, 1970 
Jun 25, 1910 
Mar 02, 1919 
Jul 03, 1930 
Aug 30, 1935 
Dec 22, 1944 
Mar 02, 1945 
Aug 26, 1937 
Mar 2, 1945 
Oct 27, 1965 
Dec 31, 1970 
Sep 03, 1954 
Sep 19, 1890 
Jun 25, 1910 
Mar 03, 1925 
Jul 03, 1958 
Oct 22, 1976 
Oct 01, 1980 
Extend jetties to such lengths as may be practicable H. 
within estimate of total cost of jetties, $3,250,000 
given in H. Doc. 150, 67th Cong. 
A channel 24 feet deep and 300 feet wide, through H. 
Pigeon Point Reef, following a location along westerly side of bay. 
For 24-foot channel from Pigeon Point Reef to S. 
Smith's Mill and a turning basin above Marshfield. 73 
Increased dimensions of channel across bar and to S. 
Isthmus Slough and turning basin opposite Coalbank 
Slough and at city of North Bend; anchorage basins at 
mile 3.5 and near mile 7. 
A mooring basin and connecting channel at Charleston. H. 
Increase dimensions to provide for bar channel 45 feet deep, H. 
inner channel 35 feet deep to mile 15, and deepening 
and widening existing turning basins and anchorage area. 
COQUILLE RIVER, OR 
Dredging shoals between mouth and Riverton, and H. 
removing obstruction between mouth of North Fork 
and Bandon. 
For a 13-foot channel from ocean to Bandon. H. 
Deepen channel to 16 feet between sea and eastern end H. 
of North Jetty. 
Present project depth between sea and eastern end of S. 
North Jetty. 741 
Construction, operation, and maintenance of Sec 
recreation facilities. Ac 
For 13-foot depth from sea to a point 1 mile above Coquille H. 
River Lighthouse and snagging to State Highway Bridge. 
DEPOE BAY, OR 
Construction of an inner basin 375 feet long, 125 feet wide H. 
and 5 feet deep, with an entrance channel of same depth and 1st 
50 feet wide. 
Construction of an inner basin 750 feet long, 390 feet wide H. 
and 8 feet deep, with entrance channel at same depth and 30 1st 
feet wide. 
S. Doc. 62, 88th Cong., 2d Sess 
H. Doc 151, 91st Cong., 2d Sess. 
S. Doc. 83, 83d Cong. 2d Sess. 
H. Doc. 71, 51st Cong., 1st Sess. 
H. Doc. 648, 61st Cong., 2d Sess. 
S. Committee Print, 
Serial, 68th Cong., 1st Sess. 
H. Doc. 204, 85th Cong.,lst Sess. 
Final Report of Chief 
of Engineers 
P.L 96-367 
37-31 
Doc. 320, 69th Cong., 1st Sess. 
Doc. 110, 70th Cong., 1st Sess. 1 
Committee Print, 
d Cong., 2d Sess.1 
Doc. 253, 79th Cong., 2d Sess. 
Doc 646, 80th Cong., 2nd Sess. 
Doc. 151, 91st Cong., 2d Sess. 
Doc. 673, 61st Cong., 2d Sess. 
doc. 207, 65th Cong., 1st Sess. 1 
Doc. 186, 70th Cong., 1st Sess. 
Committee Print, 
th Cong., 1st Sess. 
c. 4, Food Control 
:t of 1944 as amended 
Doc. 672, 76th Cong., 2d Sess. 1 
Doc. 202, 75th Cong. 
Sess. 
Doc. 350, 77th Cong. 
Sess. 
10. 
11. 
PORT ORFORD, OR 
Extension of existing breakwater by 550 feet. 
Dredging of turning basin 340 feet long, 100 feet wide, 
16 feet deep. 
ROGUE RIVER HARBOR AT GOLD BEACH, OR 
Two jetties at entrance and improvement of channel. 
SIUSLAW RIVER, OR 
Build two high-tide stone jetties. 
Extends North Jetty 3,700 feet from old work constructed 
under previous project and provides for 4,200 foot south jetty. 
12-foot deep channel. 
18-foot bar channel and 16-foot river channel and a 600-foot 
extension of north Jetty. (600-foot extension classified 
deferred.) 
Phase I advance engineering and design for north 
and south jetty extensions. 
Extending north and south jetties about 2,000 and 
2,500 feet, respectively. 
13. 
15. 
16.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
17. 
Jul 03, 1930 
18. 
Aug 26, 1937 
Jun 30, 1948 
Jul 26, 1912 
Mar 04, 1913 
Mar 02, 1919 
Mar 03, 1925 
Mar 02, 1945 
Jun 30, 1948 
Sep 03, 1954 
Oct 27, 1965 
Jul 18, 1989 
19. 
SKIPANON CHANNEL, OR 
Channel from deep water in Columbia River to railroad 
bridge, 30 feet deep. 
Channel extending upstream from railroad bridge a 
distance of 4,500 feet. 
Mooring basin 12 feet deep at Warrenton. 
TILLAMOOK BAY AND BAR, OR 
Construct North Jetty 5,700 feet long and dredging 
channel 16 feet deep, 200 feet wide, to Bay City. 
Abandon that portion of project above Bay city. 
Abandon Bay City Channel and present project dimension 
of channels and turning basins with regulating works as needed. 
Repair damage and check erosion on Bayocean Peninsula 
caused by storm Jan. 1939. 
Dredging small-boat basin and approach at Garibaldi, OR, 
to depth of 12 feet. 
Closure of breach in Bayocean Peninsula 
Construct South Jetty, 80,000 feet long. 
TONGUE POINT, OR 
Channel 34 feet deep and 350 feet wide from Columbia River 
channel to Tongue Point docks, and a turning basin located 
near the piers. 
H. Doc. 278, 70th Cong., 1st Sess. ' 
H. Doc. 201, 75th Cong., 1st Sess. 
S. Doc. 93, 80th Cong., 1st Sess. ' 
H. Doc. 349, 62d Cong., 2d Sess. 
H. Doc. 760, 65th Cong., 2d Sess 
H. Doc. 562, 68th Cong., 2d Sess. 
S. Doc. 35, 79th Cong., 1st Sess.4 
H. Doc. 650, 80th Cong., 1st Sess. 
S. Doc. 128, 83d Cong., 2d Sess.' 
S. Doc. 43, 89th Cong., 1st Sess.' 
Section 107 of the 1960 River and 
Harbor Act, as amended. 
UMPQUA RIVER, OR 
North Jetty, 7,500 feet long H. Doc. 913, 65th Cong., 2d Sess. 
Present project dimensions of North Jetty and dredging H. Doc. 320, 69th Cong., 1st Sess. 
ocean bar. 
A short south jetty H. Doc. 317, 70th Cong., 1st Sess.' 
A full length south jetty and maintenance dredging Rivers and Harbors Committee 
to a 26-foot depth. Doc. 9, 72d Cong., 1st Sess. 
Channel 22 feet deep and 200 feet wide from mouth S. Doc. 158, 75th Cong., 3d Sess. 
to Reedsport. 
Channel 22 feet deep and 200 feet wide from river channel S. Doc. 86, 76th Cong., 1st Sess.' 
to Gardiner, and turning basin 22 feet deep, 500 feet wide and 
800 feet long. 
Channel 10 feet deep and 100 feet wide from river channel to S. Doc. 191, 77th Cong., 2d Sess.' 
dock in Winchester Bay with mooring and turning basin 10 feet 
deep, 175 feet wide , and 300 feet long at inner end. 
Channel 12 feet deep and 100 feet wide from river channel to S. Doc. 154, 80th Cong., 2d Sess.' 
dock in Winchester Bay with mooring and turning basin 
12 feet deep, 175 feet wide, and 300 feet long at inner end. 
Channel 12 feet deep, Scholfield River. a S. Doc. 133, 81st Cong., 2d Sess.' 
WILIAMETTE RIVER AT WILLAMETTE FALLS, OR 
For purchase and rehabilitation of system and H. Doc. 202, 56th Cong., 1st Sess. 
construction of concrete division wall. and Annual Report, 1900, P. 4374 
Deepening of locks. H. Doc. 1060, 62d Cong., 3d Sess.' 
Operation and care of canal and locks provided for with funds 
from War Department appropriations for Rivers and Harbors. 
Construction of New Willamette Falls Locks. H. Doc. 544, 75th Cong., 3d Sess. 
YAQUINA BAY AND HARBOR, OR 
Restoration and extension of jetties constructed under H. Doc. 109, 65th Cong., 
previous projects, rock removal at entrance, and 1st Sess. 
dredging in bay up to railroad terminus at Yaquina. 
Extension of north jetty seaward 1,000 feet. S. Committee Print, 75th Cong., 
1st Sess. 
37-32 
20. 
Sep 22, 1922 
Jan 21, 1927 
Jul 03, 1930 
Aug 30, 1935 
Jun 20, 1938 
Mar 02, 1945 
Mar 02, 1945 
Jun 30, 1948 
Sep 03, 1954 
Jun 25, 1910 
Aug 08, 1917 
Jun 26, 19348 
Mar 02, 19458 
Mar 02, 1919 
Aug 26, 1937 
21. 
22.

TABLE 37-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
Mar 02, 1945 
Jul 24, 1946 
Jul 03, 1958 
Jul 14, 1960 
Oct 23, 1962 
Mar 07, 1974 
May 17, 1950 
Nov 17, 1986 
Jun 28, 1938 
Dec 22, 1944 
Jun 28, 1938 
Dec 22, 1944 
Oct 23, 1962 
Oct 07, 1970 
May 17, 1950 
Dec 22, 1944 
Jun 28, 1938 
Dec 22, 1944 
Oct 23, 1962 
May 17, 1950 
Jul 9, 1990 
Aug 15, 1985 
Jun 22, 1936 
Jun 28, 1938 
May 17, 1950 
Oct 27, 1965 
26-foot channel of suitable width across entrance bar, 
as far as rock bottom will allow, a 20-foot channel 300 feet 
wide along south side of bay to and including a turning basin 
22 feet deep, 1,000 feet wide and 1,200 feet long. 
Construct a small-boat mooring basin at Newport, OR. 
40-foot bar channel and 30-foot river channel 
extension of jetties at entrance. 
A small boat basin, south shore. 
APPLEGATE LAKE, ROGUE RIVER BASIN, OR 
Authorizes a rockfill embankment dam. 
Authorizes construction of project but no operation for 
irrigation until local interests agree to repay cost allocated. 
BLUE RIVER LAKE, OR 
Authorizes gravel-filled embankment dam. 
Authorizes Construction of hydroelectric power facilities 
COTTAGE GROVE LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
DORENA LAKE, OR 
Earthfill dam. 
Construction, operation, and maintenance of recreation 
facilities. 
ELK CREEK LAKE, ROGUE RIVER BASIN, OR 
Roller compacted concrete dam. 
Authorized construction but not operation for irrigation 
until local interests agree to repay cost allocated. 
FALL CREEK LAKE, OR 
Earth and gravel fill embankment dam. 
Construction, operation, and maintenance of recreation 
facilities. 
FERN RIDGE LAKE, OR 
Earthfill embankment dam 
Construction, operation, and maintenance of recreation 
facilities. 
Raise height of dam to obtain additional storage. 
LOWER COLUMBIA RIVER BASIN BANK PROTECTION, OR AND WA 
Provides bank protection on Columbia River below H. Doc. 531, 81st Cong., 2d Sess. 
river mile 125 and along principal tributaries. 
MILL CREEK, SALEM, OR 
Construction of three riprap groins and 250 feet of riprap 
bank protection. 
Sec 14, Flood Control Act of 1946, 
as amended 
MT. ST. HELENS SEDIMENT CONTROL, WA 
Authorized construction of sediment and retention structures. P.L. 99-88 
WILLAMETTE RIVER BASIN BANK PROTECTION, OR 
Bank protection works, with channel clearing. 
Provide additional protection against flooding. 
Addition of 77 locations to scope of projects. 
WILLOW CREEK LAKE, HEPPNER, OR 
Storage project for flood control, recreation, and fish 
and wildlife. 
F.C. Act 1936 
H. Doec. 544, 75th Cong., 3d Sess. 
H. Doc. 531, 81st Cong., 2d Sess. 
H. Doec. 233, 89th Cong., 1st Sess. 
37-33 
Documents 
23. 
24. 
25. 
26. 
27. 
S. Doc. 119, 77th Cong., 1st Sess.' 
S. Doc. 246, 79th Cong., 2d Sess. 
S. Doc. 8, 85th Cong., 1st Sess.' 
Section 107, P.L 86-645 
Authorized by Chief of Engineers, 
Mar. 4, 1977 
H. Doc. 566, 87th Cong., 2d Sess. 
P.L 93-251 
H. Doc. 531, 81st Cong., 2d Sess. 
P.L 99-662 
H. Doc. 544, 75th Cong., 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc. 544, 75th Cong., 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc. 566, 87th Cong., 2d Sess. 
P.L 91-439 
H. Doc. 531, 81st Cong., 2d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc. 544, 75th Cong. 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc 403, 87th Cong. 2d Sess. 
28. 
29. 
32. 
33. 
34. 
36. 
37.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
38. BONNEVILLE LOCK AND DAM - LAKE BONNEVILLE. OR AND WA 
Aug 30, 1935 
Aug 20, 1937 
Dec 22, 1944 
Mar 07, 1974 
Aug 22, 1984 
Aug. 17,1991 
39. 
40. 
41. 
42. 
43. 
44. 
45. 
Jun, 1988 
May 17, 1950 
Sep 03, 1954 
Oct 23, 1962 
June 28, 1938 
Jun 30, 1948 
May 17, 1950 
Sep 03, 1954 
Jul 14, 1960 
May 17, 1950 
May 17, 1950 
Dec 22, 1944 
Mar 24, 1965 
Jun 28, 1938 
Dec 22, 1944 
May 17, 1950 
Sep 21, 1962 
Oct 15, 1966 
46. 
47. 
Existing project was originally authorized Sep. 30, 1933, by 
Federal Emergengy Administration of Public Works. 
Existing project authorized by congress S. Committeee Print, 73d Cong., 
2d Sess., (Report of Chief of 
Engineers dated Aug 21, 1933) 
Completion, maintenance, and operation of Bonneville project 
under direction of Secretary of War and supervision of 
Chief of Engineers, subject to certain provisions herein relating 
to powers and duties of Bonneville Power Administrator. 
Construction, operation, and maintenance of recreation Sec 4, Flood Control Act of 1944, 
facilities as amended 
Authorizes relocation of town of North Bonneville P.L 93-251 
to new town site. 
Acquisition of Steigerwald Lake wetland area P.L 98-396 
COLUMBIA AND SNAKE RIVERS PORTS DREDGING, OR AND WA 
Maintain navigation access to commercial dock facilities P.L 102-104, 102d Cong., 1st Sess. 
from Bonneville Dam to McNary Dam 
COLUMBIA RIVER JUVENILE FISH MITIGATION PROGRAM (The Dalles), OR and WA 
Design, test, and construct fish bypass facilities P. L 100-371 
COUGAR LAKE, OR 
Rockfill dam. H. Doc. 531, 81st Cong., 2d Sess. 
Addition of power P.L 83-780 
Strube Lake reregulating dam. P.L. 87-874 
DETROIT LAKE - BIG CLIFF, OR 
Authorizes concrete gravity structure. H. Doc. 544, 75th Cong.,3d Sess. 
Addition of power and regulating Big Cliff Dam with power. P.L 858, 80th Cong. 2d Sess. 
GREEN PETER-FOSTER LAKES, OR 
Authorized Green Peter Dam in lieu of originally H. Doc. 531, 81st Cong., 2d Sess. 
authorized Sweet Home Lake (1938) 
Addition of power at Green Peter and White Bridge P.L 83-780 F. C. Act 1954 
Reregulating Dam. 
Changes location of reregulating dam from White S. Doc. 104, 86th Cong., 2d Sess. 
Bridge location to Foster. 
HILLS CREEK LAKE, OR 
Earth and gravel fill dam. H. Doc. 531, 81st Cong., 2d Sess. 
JOHN DAY LOCK AND DAM - LAKE UMATILLA, OR AND WA 
Multiple-purpose dam, flood control, navigation and power. H. Doc. 531, 81st Cong., 2d Sess. 
Construction, operation, and maintenance of recreation Sec 4, Flood Control Act of 1944, 
facilities. as amended 
John Day waterfowl management area. S. Doc. 28, 89th Cong., 1st Sess. 
LOOKOUT POINT - DEXTER LAKES, OR 
Earth-and-gravel filled dam. 
Construction, operation, and maintenance of recreation 
facilities. 
Addition of power and authorization of Dexter Lake 
as reregulating dam. 
LOST CREEK LAKE, ROGUE RIVER BASIN, OR 
Rock and gravel fill embankment dam, including power. 
Authorizes construction of project but not operation for 
irrigation until local interests agree to repay cost allocated. 
H. Doc. 544, 75th Cong., 3d Sess. 
Sec 4, Flood Control Act of 1944, 
as amended 
H. Doc. 531, 81st Cong., 2d Sess. 
H. Doc. 566, 87th Cong., 2d Sess. 
P.L 89-689, Public Works 
Approp. Act, 1967 
37-34 
TABLE 37-B 
(Continued)

PORTLAND, OREGON DISTRICT 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
48. THE DALLES LOCK AND DAM - LAKE CELILO, WA AND OR 
May 17, 1950 Multiple-purpose dam, flood control, navigation and power. H. Doc. 531, 81st Cong., 2d Sess. 
Dec 22, 1944 Construction, operation, and maintenance of recreation Sec 4, Flood Control Act of 1944, 
facilities, as amended 
1. Contains latest published maps. 
2. Public Resolution 105, 67th Cong. 
3. Public Works Administration 
4. Includes following work, classified inactive. A channel to 
Hobsonville 200 feet wide and 16 feet deep, with a turning basin 
500 feet wide at Hobsonville, and regulating works as needed. 
5. Inactive. 
6. Permanent appropriations Repeal Act. 
7. Flood Control Act 
8. Classified Deferred 
9. Spur Jetty "B" classified inactive. 
37-35 
TABLE 37-B 
(Continued)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Alsea River, OR 
AstoriaTurning Basin, OR 1 
Bandon Small Boat Basin, Coquille, OR 1 
Bridges, Columbia River, Cascade Locks 
and Hood River, OR (Alteration) 
Cathlamet, WA 1 
Charleston Channel, Coos Bay, OR 1 
Clatskanie River, OR 2 
Columbia River, Illwaco, WA 1 
Coos & Millicoma Rivers, OR 
Cowlitz River, WA 
Cushman-Mapleton Channels 
(Siuslaw River), OR 1 
Deep River, WA 2 
Depoe Bay, OR 1 
Elochoman Slough, WA 2 
Grays River, WA 2 
Hammond Small Boat Basin, OR 1 
Interstate Bridge, Columbia River, 
Portland, OR to Vancouver WA (Alteration) 
Interstate Highway Bridge(Barge Channel), OR 1 
Kalama Turning Basin, Kalama, WA 1 
Lake River, WA 
Lewis River, WA 
Long Tom River, OR 
Mooring for Battleship Oregon, OR 
Multnomah Channel, OR 2 
Nehalem Bay, OR 
Nestucca River, OR 
Oregon Slough, (North Portland Harbor), OR 2 
Salmon River, OR 2 
Smith River, OR 2 
Skamokawa Creek, WA 
South Channel, Government Island, OR 1 
South Slough (Charleston), OR 1 
The Cascades Canal, Columbia River, Or 12 
The Dalles-Celilo Canal, Or and WA13 
Umatilla Harbor, OR14 
Westport Slough, OR 2 
Willamette River above Portland and 
Yamhill River, OR 
Winchester Bay, Umpqua River, OR 
Yaquina Bay and Harbor Small Boat Basin, Or 1 
Yaquina River, OR 1 
Yaquina River, OR 
Youngs and Claskanie River, Or 
Youngs Bay and Youngs River, OR 2 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Abandoned 
Abandoned 
Abandoned 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1977 
1985 
1944 
1971 
1985 
1969 
1986 
1991 
1985 
1975 
1963 
1971 
1990 
1941 
1977 
1961 
1963 
1986 
1983 
1985 
1982 
1987 
1963 
1949 
1974 
1991 
1985 
1970 
1939 
1957 
1952 
1966 
1985 
1985 
1979 
1971 
1984 
1979 
2,000 
870,139 
1,173,524 
1,081,806 
171,467 
1,197,300 
19,2403 
1,589,231 
350,23819 
277,436 6 
329,423 
15,384 
145,588 6 
18,6411' 
2,500 
519,0907 
1,154,1628 
15,281 
302,000 
2,700 
58,132 
437,669 * 
302,00610 
16,881 
2,145 
143,120 
2,400 
119,80011 
26,821 
3,903,780 
4,716,205 
16,276 
862,918 
1,616,369 
891,695'1 
195,31316 
28,800 
2,000 
9,348 
26,237 
16,648 
194,896^ 
2,152,914 
1,474,036 
32,768 
196,864 
35,670 
58,127 
685,677 
4,000 
25,000 
55,195 
6,000 
90,514 
205,130 
436,185 
559,858 
2,833,888 
171,909 
17,900,293 
749,694 '1 
34,449 
1. Authorized by Chief of Engineers (sec. 107). 
2. Channel adequate for present commerce. 
3. Includes $15,537 for previous project 
4. Includes $23,489 for previous project. 
5. Excludes $42,000 contributed funds. 
6. Includes $239,529 for Sec. 107 project. 
7. Excludes $75,000 contributed funds. 
8. Non-Federal funds, $1,204,100. 
9. Includes $419,557 for Sec. 107 project. 
10. Excludes $304,826 contributed funds. 
11. Excludes $102,000 contributed funds. 
12. Project abondoned due to flooding by Bonneville Dam pool. 
13. Project abandoned due to flooding by The Dalles Dam pool 
14. Project transferred to Portland Distrct from Walla Walla 
District FY 1974 and abandoned due to flooding by the John Day 
Dam pool. 
15. Excludes $969,342 contributed funds. 
16. Excludes $50,565 contributed funds 
17. Excludes $3,000 contributed funds. 
18. Excludes $86,586 contributed funds. 
19. Excludes $80,000 contributed funds; includes $8,000 for 
previous project. 
37-36

PORTLAND, OREGON DISTRICT 
TABLE 37-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
COLUMBIA RIVER BASIN 
Blind Slough Diking District, Clatsop County, OR Completed 1939 163,397 
Consolidated Diking and Improvement District 1, 
Cowlitz County, WA Completed 1941 163,291 
Deep River Area, Wahkiakum County, WA Completed 1942 69,724 
Deer Island Area, Columbia County, OR Completed 1943 574,123 
Diking District 2, Clatsop County, OR Completed 1940 25,609 
Diking District 5, Clatsop County, OR Completed 1940 25,609 
Diking and Improvement District 5, 
Cowlitz County, WA Completed 1940 161,381 
Diking District 1 and 3 (Puget Island) and 
Little Island, Wahkiakum County, WA Completed 1941 258,795 
Diking Improvement District 1, Pacific County WA Completed 1941 26,810 
Diking and Improvement District 4, 
Wahkiakum County, OR Completed 1951 169,542 
Drainage District 1, Clatsop County, OR Completed 1939 240,939 
John Day River Area, Clatsop County, OR Completed 1942 33,080 
Karlson Island, Clatsop County, OR Completed 1941 25,773 
Knappa Area, Clatsop County, OR Completed 1942 18,789 
Lewis and Clark River Area, Clatsop County, OR Completed 1942 158,419 
Lower Cowlitz River Area, Clatsop County, OR Completed 1961 91,652 
Magruder Drainage District, Columbia County, OR Completed 1940 61,186 
Marshland Drainage District, 
Columbia County, OR Completed 1940 39,475 
Midland Drainage District Columbia County, OR Completed 1939 77,7743 
Multnomah Drainage District 1, OR Completed 1951 593,0344 
Peninsula Drainage District 1, Multnomah County, OR Completed 1942 241,148 
Port of Kalama, WA1 Completed 99,844 
Rainier Drainage District, Columbia County, OR Completed 1942 47,662 
Sauvie Island Areas A and B, Multnomah County, OR Completed 1951 1,623,505 
Scappoose Drainage District, OR Completed 1984 3,991,558 
Skamokawa Creek Area, Wahkiakum County, WA Completed 1946 178,885 
Wahkiakum County Consolidated 
Diking District No. 1, WA Completed 1985 5,289,833 
Tenasillahe Island, Clatsop County, OR Completed 1939 133,778 
Upper Grays River Area, WA Completed 1947 61,263 
State Hwy 101 & 401, Columbia River, WA' Completed 1985 504,642's 
Walluski River, Clatsop County, OR Completed 1942 66,932 
Warrenton Diking District, 1, Clatsop County, OR Completed 1940 69,503 
Warrenton Diking District 2, Clatsop County, OR Completed 1940 74,596 
Webb District Improvement Co.,Columbia County, OR Completed 1940 84,592 
Westland District Improvement Co., 
Columbia County, OR Completed 1940 205,531 
Westport District Columbia and Clatsop Counties, OR Completed 1943 40,658 
Woodson Drainage District, Columbia County, OR Completed 1940 22,797 
Youngs River Dikes, Clatsop County, OR Completed 1942 248,802 
Total Columbia River Basin 16,399,775 
LEWIS RIVER BASIN 
Diking and Improvement District 11, 
Cowlitz County, WA Completed 1943 172,521 
COWLITZ RIVER BASIN 
Cowlitz County Drainage Improvement District 1, WA Completed 1939 42,978 
Diking Improvement District 13, Cowlitz County, WA Completed 1939 28,592 
Huntington Avenue, Castle Rock, WA' Completed 1985 250,000 
Total Cowlitz River Basin 442,735 
37-37

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to Sep, 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
LOWER COLUMBIA RIVER BASIN 
Beaver Drainage District, OR Completed 1984 3,131,944 
Cowlitz County Consolidated Diking Improvement 
District No. 2, WA Completed 1977 1,661,367 
Cowlitz County Diking Improvement District 2, WA Completed 1967 363,000 
Cowlitz County Diking Improvement District 13, WA Completed 1967 65,345 
Cowlitz County Diking Improvement District 15, WA Completed 1967 304,794 
Cowlitz River, Hopkins Creek, WA1 Completed 236,860 
Hayden Island, OR Inactive 
Midland Drainage District, OR Completed 1971 304,511 
Multnomah County Drainage District 1, OR Completed 1964 1,499,186 
Peninsula Drainage District 2, OR Active 1961 35,265 
Rainier Drainage District, OR Completed 1967 593,945 
Sandy Drainage District, OR Completed 1954 154,0126 
Sauvie Island Drainage District, OR Completed 1966 674,137 
Vancouver Lake Area, WA Deferred 1981 889,391 
Wahkiakum Co. Diking District 4, WA Inactive 1971 48,619 
Washougal Area Levees, Clark County, OR Completed 1973 1,803,488 
Woodson Drainage District, OR Completed 1964 162,500 
Total Lower Columbia River Basin 11,928,364 
WILLAMETTE RIVER BASIN 
Amazon Creek, OR Completed 1960 1,214,3006 
Cascadia Lake, OR Deferred 1976 i,U66,l1iA1 7 
Gate Creek Lake, OR Deferred 1972 840,0006 
Holley Lake, OR Deferred 1963 241,992 
Sandy River and Sleepy Hollow, OR1 Completed 276,700 
Whelton Ditch, OR Inactive 1967 39,624 
Willamette River Basin Channel Clearing 
and Snagging Inactive 
Total Willamette River Basin 3,678,731 
ALL OTHER FLOOD CONTROL 
Arlington, Alkali Canyon, OR9 Abandoned 1950 23,439 
Bear Creek, Medford, OR1 Completed 23,050 
Beaver Creek Near Tillamook, OR2 Completed 1967 106,198 
Castle Rock, Cowlitz River, WA Completed 1957 104,921 
Catching Inlet Drainage District Coos River, OR2 Completed 1959 182,655 
Chewaucan River, Paisley, OR1 Completed 42,761 
Clackamas River at Dixon Farm Location, OR Completed 1952 70,84510 
Days Creek Lake, OR (Phase I) Deferred 1982 1,307,216 
Depoe Bay, Lincoln County, OR1 Completed 22,963 
Deschutes River, Bend, OR2 Completed 1988 106,25015 
John Day River (West), OR1 Completed 1986 127,800 
Johnson Creek, OR Active 1981 170,245 
McDonald Dike Road, Nehalem River, OR' Completed 1985 29,500 
McKenzie River Near Walterville, OR2 Completed 1966 148,358 
Miami River, OR1 Completed 15,321 
Mill Four Drainage District, Yaquina River, OR Completed 1948 118,433 
Molalla River at Milk Creek Location, OR2 Completed 1955 55,007 
Molalla River at Ressel Location, OR2 Completed 1952 55,189 
Mount St. Helens and Vicinity, WA Completed 1989 42,158,000 
Nestucca River, Condor Road, OR1 Completed 11,690 
Nestucca River, Vicinity Pacific City, OR' Completed 16,000 
37-38

PORTLAND, OREGON DISTRICT 
TABLE 37-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Pendleton Levees, Umatilla River, OR 11 
(a) Riverside Area Units Deferred 1960 9,100 
(b) State Hospital and City Areas (Zone 1) Completed 1959 267,748 
(c) State Hospital and City Areas (Zone 2)2 Completed 1960 161,540 
Pendleton, Umatilla River, OR 10 Completed 1939 143,263 
Reedsport Levees, Umpqua River, OR2 Completed 1971 968,71612 
Rogue River, OR1 Completed 86,230 
Salmon Creek at Oakridge, OR2 Completed 1960 288,447 
Salmon Creek Near Vancouver, WA1 Completed 1985 435,000'14 
Siuslaw River, Lane County, OR 1 Completed 215,939 
Stillwell Drainage District, Tillamook Bay, OR2 Completed 1961 176,351 
Sumner Parker Airport, OR1 Completed 92,500 
Trask River, Tillamook County, OR1 Completed 1984 121,273 
Tualatin, OR Completed 1985 1,803,094 
Umatilla River, Stanfield, OR1 Completed 33,835 
Umatilla River, Thorn Hollow, OR' Completed 1985 154,600 
Umpqua River and Tributaries, OR Completed 1952 428,881 
Vicinity of Nehalem, Nehalem River, OR Completed 1952 45,677 
West Makinster Rd., Wilson River, OR 1 Completed 1986 176,000 
Wilson River, Vicinity Highway 101, OR1 Completed 30,000 
Total All Other Flood Control 7,965,985 
1. Authorized by Chief of Engineers (Sec. 14). 9. Project transferred from Walla Walla District FY 1974 and 
2. Authorized by Chief of Engineers (Sec. 205). abandoned due to flooding by the John Day Dam pool. Includes 
3. Includes $26,241, Emergency Relief Act Funds $3,328 FY 1960 preauthonzation costs, Sec. 205, P.L 80-85. See 
4. Excludes $25,000 contributed funds FY 1960 Annual Report, page 1887 
5. Previous completed project, $138,956; $15,056 engineering costs 10. Excludes $2,520 contributed funds 
project constructed by local interests. 11. Reported by Walla Walla District prior to 1974 
6. Excludes $154,751 contributed funds. 12. Excludes $230,070 contributed funds for new work and $31,284 
7. Includes $112,000 pro rata share of site selection in lieu of Government furnished sheet steel pile. 
Sweet Home. 13. Includes $254,642 contributed funds. 
8. Includes $95,000 pro rata share of site selection in lieu of 14. Includes $185,000 contributed funds. 
Quartz Creek Lake. 15. Excludes $5,822 contributed funds. 
TABLE 37-F OTHER AUTHORIZED MULTIPLE PURPOSE PROJECTS, 
INCLUDING POWER
For Last Cost to Sep,. 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Restoration of Indian Fishing Grounds, Bonneville, OR Completed 1969 185,000 
37-39

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Area East of Albany, OR 1977 
Bachelor Island, WA 1977 
Bear Creek, Long Tom River, OR 1966 1971 4,559 
Calapooya River, OR 1959 1965 11,595 
Cascadia Lake, OR 1987 954,114' 
Clatskanie River Area, Columbia County, OR 1960 1965 268 
Clatskanie Drainage Dist. 1, OR 1964 1978 18,543 
Clatsop County Drainage District 1, OR 1960 1974 4,472 
Clatsop County Diking District 3, OR 1938 1961 258 
Clatsop County Diking District 4, OR 1978 
Clatsop County Diking District 6, OR 1961 1978 8,824 
Columbia Drainage District No. 1, OR 1987 
Columbia Slough, OR 1953 1978 21,352 
Coquille River, OR 1948 1953 908 
Cowlitz County Consolidate Diking Improvement District 1, OR 1977 
Cowlitz River at Randle, WA 1962 1977 11,095 
Coyote and Spencer Creek, Long Tom River, Or 1960 1970 6,819 
Deer Island Drainage District, OR 1987 
East Muddy and Lake Creek, OR 1959 1970 6,465 
Ferguson Creek Long Tom River, Or 1978 
Flat Creek, Long Tom River, OR 1977 
Floodwall and Levees at Portland, OR 1977 
Gate Creek Lake, OR 1987 745,0012 
Holley Lake, OR 1963 1987 241,9923 
John Drainage District, OR 1961 1979 23,754 
John Day River, OR 1974 1974 210,220 
Kalama River (South Area) Levee, Cowlitz County, WA 1969 1978 55,594 
Lake River Delta Area, WA 1977 
Lewis River Area, WA 1978 
Magruder Drainage District, OR 1940 1974 774 
Mud and Basket Slough Rickreall Creek, OR 1977 
Pendleton Levees, Riverside Area, OR 1987 9,000 
Peninsula Drainage District 1, OR 1942 1977 43,292 
Pilot Rock, Birch Creek, OR 1963 1968 4,558 
Prescott Area, Columbia County, OR 1941 1978 125 
Prineville Area, Crooked River and Ochoco Creek, OR 1962 1977 11,318 
Pudding River, OR 1950 1979 5,000 
Shelton Ditch, Marion County, Or 1967 1987 39,624 
Skamokawa (Steamboat Slough), WA 1939 1979 
Soap Creek, WA 1977 
Turner Prairie, Mill Creek, OR 1978 
Umatilla River (Echo), OR 1960 1964 24,145 
Umpqua River-Scholfield River, OR 1987 4,000 
Waldo Lake Tunnel, OR 1958 
West Muddy Creek and Mary's River, OR 1962 1970 4,056 
Westport Slough, OR (Modification for 32-foot channel) 1966 1977 
Wiley Creek Lake, OR 1960 112,000 
Willamette River above Portland and 
Yamhill River, OR (uncompleted portions) 1987 
Willamette Falls Fishladder, OR 1961 
Willamette River at Willamette Falls, OR 1948 1987 142,883 
1. Excludes Pro-rata share of $112,000 for Sweet Home Reservoir. 
2. Excludes Pro-rata share of $95,000 for Quartz Creek Reservoir 
3. Excludes $100,000 preauthorization study costs. 
37-40

PORTLAND, OREGON DISTRICT 
TABLE 37-H COLUMBIA AND LOWER WILLAMETTE RIVER 
BELOW VANCOUVER, WA, AND PORTLAND, OR 
TOTAL COST OF EXISTING PROJECT TO SEP. 30, 1992 
(SEE SECTION 3 OF TEXT) 
Funds New Work Maintenance Total 
Regular 28,349,304 303,204,464 331,553,768 
Public Works 446,296 14,414 460,710 
Emergency Relief Administration 138,449 98,668 237,117 
Total U.S. 28,934,049 303,317,546 332,251,595 
Contributed Prior to 1964 223,026 24,320 247,346 
Contributed (1975) 35 to 40-foot Channel 442,928 442,928 
Total Contributed 665,954 24,320 690,274 
Total All Funds 29,600,003 303,341,866 332,941,869 
TABLE 37-I NAVIGATION WORK UNDER SPECIAL AUTHORIZATION 
(SEE SECTION 12 OF TEXT)
Fiscal Year Costs 
Federal Non-Federal Total 
Channels and Harbors (Section 107) 
Charleston Harbor, Coos Bay, OR ' 6,366 6,366 
Coquille River, Bandon, OR 3 7,286 7,286 
Columbia River, Vancouver, WA 3 72,848 72,848 
Newport, OR 1 18,184 18,184 
Port of Gold Beach, OR 1 13,075 13,075 
Port of Morrow, Morrow, OR ' 620 620 
Tongue Point, OR 8 64,363 (64,309) 54 
Westport, OR - Puget Island, WA 2 4,382 4,382 
Yaquina River, Port of Toledo, OR ' 6.078 6,078 
TOTAL Channels and Harbors 193,202 (64,309) 128,893 
Mitigation of Shore Damages (Section 111) 
Siuslaw River Near Florence, OR 1 2.687 2.687 
TOTAL Mitigation of Shore Damages 2,687 2,687 
1. Reconnaissance Study 4. Construction Funds 
2. Feasibility Report 5. Construction Completed 
3. Plans and Specifications 
TABLE 37-J PROJECT CONDITION SURVEYS 
(SEE SECTION 14 OF TEXT) 
Project Date Survey Conducted 
Columbia River between The Dalles and Umatilla, OR JuV/Aug/Sep 1992 
Elochoman Slough, WA Sep 1992 
Nehalem Bay. OR May/Sep 1992 
Skamokawa Creek, WA Sep 1992 
Tillamook Bay and Bar, OR Oct 1991/May 1992 
37-41

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-K WILLAMETTE RIVER AT WILLAMETTE FALLS, OR 
PRINCIPAL FEATURES OF EXISTING CANAL AND LOCKS 
(See Section 21 of Text) 
Usable Lock Dimensions Series of 4 locks, each 175 feet by 37 feet 1 
Lift of each lock Lock 1 (Lower), 22,5 feet; Lock 2, 8.7 feet; Lock 3, 10.9 feet and 
Lock 4 (Upper), 8.1 feet2 
Depth of Miter Sills at Lower Water Lower Lock, 8.4 feet; Upper Lock, 6 feet 
Character of foundation Rock 
Kind of Dam Fixed3 
Type of Construction Concrete 
Year of Completion 1873; Purchased by United States Apr. 26, 1915 
Cost Unknown; purchase price $375,000 
1. A guard lock 210 by 40 feet, which is used only at higher states powerplants operated by Crown Zellerbach Corp., and Portland 
of water, is at upper end of canal basin. Ry., Light & Power Co., which is now being operated by Portland 
2. A concrete division wall, 1,227 feet long, extending from Lock 4 General Electric Co. 
to Guard Lock, separates upper basin of canal from head race, 3. The dam is owned by private parties. 
which formerly led directly from basin and supplied water for 
TABLE 37-L FLOOD CONTROL WORK UNDER SPECIAL AUTHORIZATION 
(SEE SECTION 30 OF TEXT)
Fiscal Year Costs 
Federal Non-Federal Total 
Flood Control (Section 205) 
Bear Creek, Vernonia, OR 1 10,000 10,000 
Lakeside, OR 1 11,685 11,685 
Nehalem River, Sunset Drainage District, OR 1 3,401 3,401 
Pringle Creek, Salem, OR ' 407 407 
Peninsula Drainage District 11, OR ' 13,483 13,483 
Scappoose, OR 1 3,076 3,076 
Seaside, OR ' 14,000 14,000 
Sheridan, OR ' 20,307 20,307 
Springfield Millrace, OR 1 6,074 6,074 
Tillamook River, OR ' 8,476 8,476 
Umatilla River Water District, OR ' 7,740 7,740 
Warrenton Diking District, OR 2 19,093 19,093 
Willamette River, OR ' 7 134 7.134 
TOTAL Flood Control 124,876 124,876 
Emergency Bank Protection (Section 14) 
Antelope - Little Bear Creek, Eagle Pt., OR 2 6,310 6,310 
Beaver Creek, Troutdale, OR 2 4,958 4,958 
Mill Creek, Salem, OR 6 1,204 1,204 
Sporthaven Beach, Brookings, OR 2 5,309 5,309 
Sandy River, City of Troutdale, OR 2 32,311 32,311 
Umatilla River, Stanfield, OR 2 10.458 10,458 
TOTAL Emergency Bank Protection 60,550 60,550 
Project Modification for Improvement of Environment (Section 1135) 
Fern Ridge Lake, Long Tom River, OR 2 4.823 4.823 
TOTAL Project Modification for Improvement of Environment 4,823 4,823 
1. Reconnaissance Study 
2. Feasibility Report 
3. Plans and Specifications 
4. Construction Funds 
5. Construction Completed 
37-42

PORTLAND, OREGON DISTRICT 
TABLE 37-M FLOOD CONTROL RESERVOIR OPERATIONS 
See Section Date of Peak Inflow Storage Used 
in Text Project Peak Inflow Cu. Ft./Sec. Acre/feet 
23. Applegate Lake, OR January 21, 1992 2,000 7,110 
24. Blue River Lake, OR December 6, 1991 6,200 11,470 
25. Cottage Grove Lake, OR December 7, 1991 2,300 280 
41. Cougar Lake, OR December 6, 1991 7,500 15,230 
42. Detroit Lake, OR December 6, 1991 13,780 39,040 
26. Dorena Lake, OR December 7, 1991 4,020 1,230 
28. Fall Creek Lake, OR December 7, 1991 7,550 10,600 
29. Fern Ridge Lake, OR December 7, 1991 2,600 3,130 
43. Foster Lake, OR December 6, 1991 13,130 3,220 
43. Green Peter Lake, OR December 6, 1991 12,370 36,930 
44. Hills Creek Lake, Or December 6, 1991 7,750 19,520 
46. Lookout Point Lake, OR December 6, 1991 13,890 21,300 
47. Lost Creek Lake, Or April 10, 1992 4,100 6,270 
TABLE 37-N PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
Bonneville Lock and Dam 
OR and WA - 
Lake Bonneville 
(See Section 38 of Text) 
NAVIGATION LOCK 
Dimensions: 
Clear Width of Chamber 
Greatest Length Available for Full Width 
Lift (Vertical): 
At Extreme Low Water and Normal Pool Level 
At Normal River Stage 
At Extreme High Water 
Depth Over Miter Sills at Adopted Low Water 
Character of Foundation 
Open to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Capacity 
Elevation of Gate Sills on Crest of Spillway 
Height above Lowest Foundation 
Length of Dam Proper 
Length of Dam Overall 
Width at Base 
Gate Openings 
Crest Overflow (Above Mean Sea Level) 
Elevation(NormalXAbove Mean Sea Level) 
POWERPLANT 
Length (First Powerhouse) 
Length (Second Powerhouse) 
Width (First Powerhouse) 
Width (Second Powerhouse) 
Height (Roof to Bedrock) (First Powerhouse) 
Height (Roof to BedrockXSecond Powerhouse) 
Generator (Station Unit) 
Generators (First Powerhouse) 
76 Feet 
500 Feet 
66 Feet 
59 Feet 
About 30 Feet 
24.2 Feet 
Andesite 
January 1938 
Concrete Gravity 
1938 
1,600,000 CFS 
23.3 Feet 
About 170 Feet 
1,090 Feet 
1,230 Feet 
200 Feet 
18 
24 Feet Pool 
72 Feet 
1,027 Feet 
953 Feet 
190 Feet 
235 Feet 
190 Feet 
200 Feet 
1 @ 5,000 kw 
1 @ 48,000 kw 
1 @ 59,500 kw 
8 @ 60,000 kw each 
37-43

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 37-N PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
John Day Lock and Dam, 
OR and WA - 
Lake Umatilla 
(See Section 45 of Text) 
The Dalles Lock and 
Dam, OR and WA - 
Lake Celilo 
(See Section 48 of Text) 
Generators (Second Powerhouse) 
Fishwater Supply Units (Second Powerhouse) 
Total Rated Capacity 
Speed 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Space for Additional 
Rating, Each 
Total Installed Capacity 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area At Elevation 268 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Type 
Lift Normal 
Net Clear Length 
Net clear Width 
Normal Depth Over Upper Sill 
Minimum Depth Over Lower Sill 
Opened To Navigation 
8 @ 66,500 kw each 
2 @ 13,100 kw each 
1,145,700 kw 
75 Revolutions per Minute 
86 Feet 
669 feet 
97 Feet 
105 Feet 
113 Feet 
15 Feet 
April 1968 
Concrete Gravity 
March 1968 
2,250,000 cfs 
210 Feet 
Tainter 
50 ft. by 58.5 Ft. 
20 
1,975 Feet 
243 Feet 
16 
4
135,000 kw 
2,160,000 kw 
2,700,000 kw 
235 Feet 
July 1968 
268-257 Feet 
276 Feet 
500,000 Ac.-ft. 
76.4 Miles 
55,000 Acres 
15 Ft. by 250 Ft. 
200 miles 
Single Lift 
87.5 Feet 
675 Feet 
86 Feet 
20 Feet 
15 Feet 
March 17, 1957 
37-44

PORTLAND, OREGON DISTRICT 
TABLE 37-N 
(Continued) 
PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, AND POWERPLANT 
Project 
SPILLWAY DAM 
Type 
Elevation of Crest 
Top of Crest Gates 
Number of Gates 
Size of Gates 
Height (Foundation to Crest) 
Design Flood 
POWERPLANT 
Powerhouse Dimensions 
Generators Main Units 
Controlled 
121 Ft. msl 
162 Ft. msl 
23 
50 by 43 Feet 
120 Feet 
2,290,000 cfs 
240 by 2,150 feet 
14 @ 78,000 kw each 
8 @ 86,000 kw each 
2 @ 13,500 kw each 
1,807,000 kw 
2 @ 3,000 kw each 
Fishwater Supply Units 
Total Rated Capacity 
Station Service Units 
37-45 
Project

SEATILE, WA, DISTRICT* 
This District comprises Washington State except southern 
and southeastern portions, northern Idaho, and northwestern 
Montana, embraced in drainage basins tributary to Pacific 
Ocean south of international boundary to Cape Disappointment, 
and to the Columbia River above Yakima River, inclusively. 
IMPROVEMENTS 
Navigation 
1. Anacortes Harbor, WA ................... 38-1 
2. Bellingham Harbor, WA ............... . 38-2 
3. Ediz Hook, WA .......................... 38-2 
4. Everett Harbor and Snohomish River, WA .... 38-3 
5. Friday Harbor, WA ........................ 38-3 
6. Grays Harbor and Chehalis River, WA ........ 38-3 
7. Kenmore Navigation Channel, WA ........... 38-4 
8. Lake Crockett, WA ....................... 38-4 
9. Lake Washington Ship Canal, WA ........... 38-5 
10. Navigation Work under Special Authorization.. 38-5 
11. Olympia Harbor, WA ..................... 38-5 
12. Project Condition Surveys ................. 38-5 
13. Puget Sound and its Tributary Waters, WA .... 38-6 
14. Quillayute River, WA ..................... 38-6 
15. Seattle Harbor, WA ...................... 38-6 
16. Swinomish Channel, WA ........................ 38-7 
17. Tacoma Harbor, WA .................. ... 38-7 
18. Willapa River and Harbor and Naselle River, WA38-7 
Beach Erosion Control 
19. Lincoln Park Beach, Seattle, WA ........... 38-8 
Flood Control 
20. Flood Control Work under Special Authorization 38-8 
21. Howard A. Hanson Dam, WA ............ 38-9 
22. Inspection of Completed Flood Control Projects 38-9 
23. Lower Green River, King County, WA ........ 38-9 
24. Mud Mountain Dam, WA ...... ............. 38-9 
25. Scheduling Flood Control Reservoir Operations 38-10 
26. Stillaguamish, River, WA ............. .. 38-10 
27. Tacoma, Puyallup River, WA ............... 38-10 
28. Wynoochee Lake, WA .................... 38-10 
Multiple Purpose Power 
29. Albeni Falls Dam, ID ..................... 
30. Chief Joseph Dam - Rufus Woods Lake, WA. 
31. Libby Dam - Lake Koocanusa, MT .......... 
38-11 
38-11 
38-11 
Miscellaneous 
32. Miscellaneous Work under Special Authorization 
General Investigations 
33. Surveys ................................. 
34. Collection and Study of Basic Data .......... 
35. Preconstruction Engineering and Design ..... 
Tables 
38-12 
38-12 
38-12 
Table 38-A Cost & Financial Statement ....... 38-14 
Table 38-B Authorizing Legislation ........... 38-20 
Table 38-C Other Authorized Navigation Projects38-25 
Table 38-D Not Applicable 
Table 38-E Other Authorized 
Flood Control Projects ........... 38-26 
Table 38-F Other Authorized Multiple Purpose 
Projects, Power .................. 38-29 
Table 38-G Deauthorized Projects .......... 38-29 
Table 38-H Lake Washington Ship Canal, WA 
Principal Features of Double Lock 
and Dam ..................... 38-30 
Table 38-I Project Conditions Surveys ........ 38-30 
Table 38-J Flood Control Activities Pursuant to 
Section 205, Public Law 80-858 .... 38-30 
Table 38-K Emergency Flood Control Activities - 
Public Law 99, 84th Congress ...... 38-31 
Navigation 
1. ANACORTES HARBOR, WA 
Location. On northern point of Fidalgo Island in Puget 
Sound, 17 miles south of Bellingham, WA, and 64 miles north 
of Seattle. The main harbor is on Guemes Channel. (See 
NOAA Survey Chart 18427.) 
Existing project. Channel in Capsante Waterway, 12 feet 
deep and 150 to 250 feet wide, between east side of Q Avenue 
and deep water in Fidalgo Bay, a distance of 2,850 feet; a 
mooring basin 12 feet deep, 570 feet wide, and 960 feet long 
- 38-1 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
adjacent to north side of Capsante Waterway, protected by 
two pile breakwaters, each 470 feet long, east and southeast 
of basin; and a navigation channel 18 feet deep, 150 feet wide, 
extending 5,180 feet from deep water in Guemes Channel to 
the west shore of Fidalgo Bay (construction under authority 
of Section 107, P.L. 86-645. Construction cost for this feature 
is recorded in Table 38-C). Plane of reference is mean 
lower low water. Range between mean lower low water and 
mean higher high water is 8.2 feet. Extreme range is about 
15.5 feet. Project was completed in January 1977. Extensions 
completed in December 1964 increased lengths of both 
breakwaters to 470'. (For further details, see Annual Report 
for 1977.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 piers and wharves in the 
Port of Anacortes; 15 on Guemes Channel, 3 on Capsante 
Waterway, and 7 on Fidalgo Bay. Three wharves on Guemes 
Channel are open for public use; of these, one is publicly 
owned and operated and used for handling general cargo in 
foreign and domestic trade. In addition, two wharves are used 
for ferries plying to the San Juan Islands and to Vancouver 
Island, British Columbia. Both are publicly owned and operated. 
Two of the wharves on Capsante Waterway and basin 
are publicly owned and operated and used for receiving petroleum 
products, and as a moorage for fishing and pleasure 
craft. All other wharves are used for general industrial purposes. 
In addition, there are two oil-refinery wharves located 
to the south of Capsante Waterway that are privately owned 
and operated and used for handling petroleum products in 
foreign and domestic trade. These facilities are considered 
adequate for existing commerce. (See Port Series No. 37 - 
Ports of Port Angeles, Port Townsend, Everett, Anacortes, 
and Bellingham, WA, revised 1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Routine coordination with Port of Anacortes and navigation 
users. Dredged material management program costs resulted 
in an expenditure of $6,000. 
2. BELLINGHAM HARBOR, WA 
Location. Part of Bellingham Bay, an arm of Puget Sound, 
at Bellingham, in northwestern Washington. (See NOAA 
Survey Chart 18424.) 
Existing project. Channel 30 feet deep in Whatcom Creek 
Waterway from deep water to head of harbor, 363.2 feet wide 
to 750 feet from inner end, thence 18 feet deep for inner 750 
feet; I & J Street Waterway, a channel 100 feet wide and 18 
feet deep at mean lower low water for a distance of 3,200 feet; 
Squalicum Creek Waterway, including dredging an entrance 
channel 200 feet wide and 26 feet deep from deep water in 
the bay to main pierhead line, and maintenance of southerly 
half and westerly end of Squalicum Creek basin to 26 feet 
deep, provided that no dredging can be done within 75 feet of 
wharves, piers, or similar structures; and small-boat basin 
adjacent to Squalicum Creek Waterway by construction and 
maintenance of two sections of rubblemound breakwater 
with combined length of 5,400 feet, including maintenance of 
minimum depths of 12 feet in entrance to basin. Plane of 
reference is mean lower low water. Range between mean 
lower low water and mean higher high water is 8.6 feet. 
Extreme range is about 16 feet.The small-boat basin expansion 
from 3,900 feet to 5,400 feet at Squalicum Creek Waterway 
and channel at I & J Street Waterway were constructed 
under authority of Section 107, P.L. 86-645. Construction 
costs for these features are recorded in Table 38-C. Project 
was completed in October 1980. (For further details see 
Annual Report for 1981. For details relating to previous project 
see page 797 of Annual Report for 1907.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-2 of FY 1980 Annual Report. 
Terminal facilities. Of the forty wharves and piers in Bellingham 
Harbor, 9 are on Whatcom Creek Waterway; 3 on 
Squalicum Creek Waterway; 3 on I&J Street Waterway; and 9 
on Bellingham Bay. Two wharves on Whatcom Creek Waterway 
serve general cargo terminals. One is publicly owned and 
operated and is suitable for use by ocean-going vessels; the 
other one is privately owned and operated. There is one 
publicly owned terminal and small-boat harbor with 11 
wharves handling private craft and fishing boats. (See Port 
Series No. 37 - Ports of Port Angeles, Port Townsend, 
Everett, Anacortes, and Bellingham, WA, revised 1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Channel condition surveys were conducted throughout the 
year. Dredged material management program costs resulted 
in an expenditure of $20,000. 
Maintenance, contract: A maintenance dredging contract 
for Squalicum Creek Waterway resulted in clamshell dredging 
of 109,800 cy of shoal material with open-water disposal 
at a cost of $296,400. Maintenance dredging of berthing areas 
on Squalicum Creek Waterway was performed by others in 
conjunction with Federal maintenance. Litigation with the 
Lummi Indian Tribe resulted in a delay in the completion of 
maintenance. A second maintenance dredging contract was 
awarded in September 1992 to complete Squalicum Creek 
Waterway maintenance and perform I & J Street Waterway 
dredging. Estimated cost is $95,100. 
3. EDIZ HOOK, WA 
Location. Ediz Hook and the city of Port Angeles are on the 
Strait of Juan de Fuca in Clallam County, WA, about 100 
miles northwest of Seattle. (See NOAA Survey Chart 18468.) 
Existing project. Provides for about 16,400 linear feet of 
rock revetment, together with initial beach replenishment 
and periodic nourishment. Project was completed in October 
1978. (For further details, see Annual Report for 1979.) 
Local cooperation. Fully complied with. 
Terminal facilities. Of the 27 waterfront facilities at Port 
Angeles Harbor, 3 are located along the inner side ofEdiz 
Hook. Functional uses of the piers include placing logs into 
water from trucks for shipment by rafting; mooring harbor 
pilot boats; mooring U. S. Coast Guard vessels, Naval Reserve 
vessels, and occasionally, oceanographic research vessels; 
and fueling government vessels. (See Port Series No. 37 
- Ports of Port Angeles, Port Townsend, Everett, Anacortes, 
and Bellingham, WA, revised 1987.) 
- 38-2 -

SEATTLE, WASHINGTON DISTRICT * 
Operations during fiscal year. Maintenance, hired labor: 
Inspection and coordination with local sponsor. 
4. EVERETT HARBOR AND SNOHOMISH 
RIVER, WA 
Location. On Port Gardner Bay, at northern end of Possession 
Sound, an arm of Puget Sound at Everett, in northwestern 
Washington; and Snohomish River for 6.3 miles above 
mouth. (See NOAA Survey Chart 18443.) 
Existing project. Training dike extending from a point opposite 
23d Street northward 12,550 feet to outlet of 
Snohomish River, with spur dike extending 400 feet to pierhead 
line from north end of main dike; spur dike extending 
1,410 feet westward from Preston Point; removal of a section 
of training dike north of Snohomish River outlet; channel 150 
to 425 feet wide and 15 feet deep from deep water in Port 
Gardner Bay to 14th Street dock; thence a settling basin 700 
feet wide, 1,200 feet long, and 20 feet deep, thence a channel 
150 feet wide and 8 feet deep upriver to head of Steamboat 
Slough, a total distance of about 6.3 miles; settling basin 
within upper channel reach about 1 mile long with a capacity 
of 1 million cubic yards and maintaining East Waterway to 30 
feet deep. Plane of reference is mean lower low water. Range 
between mean lower low water and mean higher high water is 
11.1 feet. Extreme tidal range is about 19 feet. Project was 
completed in April 1963. (For further details, see page 1683 
of Annual Report for 1963. For details relating to previous 
projects, see page 704 of Annual Report for 1905, page 2005 
of Annual Report for 1915, and page 1883 of Annual Report 
for 1938.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-3 of FY 1981 Annual Report. 
Terminal facilities. There are 42 piers and wharves in the 
Port of Everett, 17 in Port Gardner and 25 on the Snohomish 
River. These include: 19 publicly owned terminals with four 
berths handling ocean-going vessels and 1 publicly owned 
terminal and small-boat basin handling fishing and pleasure 
craft. A portion of the East Waterway has been deepened and 
modified by the U.S. Navy for a Homeport. (See Port Series 
No. 37 - Ports of Port Angeles, Port Townsend, Everett, 
Anacortes, and Bellingham, WA, revised 1987.) 
Operations during fiscal year. Maintenance, hired labor: 
Channel condition surveys were conducted throughout the 
year. Dredged material management program costs resulted 
in an expenditure of $139,000. 
Maintenance, contract: A FY 1991 maintenance dredging 
contract for the Upper Snohomish River channel and upstream 
settling basin was completed in March 1992. 275,200 
cy of shoal material were removed by pipeline dredge with 
upland disposal at a cost of $614,275. A FY 1992 maintenance 
dredging contract for the upstream settling basin was 
awarded in September 1992. Estimated cost is $442,000. 
5. FRIDAY HARBOR, WA 
Location. Friday Harbor is located on the eastern shore of 
San Juan Island on the inland waters of northwestern Washington, 
about 28 nautical miles east of Victoria, British Columbia, 
and 60 nautical miles north of Seattle, WA. San Juan 
Island is one of over 170 islands in the San Juan Archipelago. 
Friday Harbor is the San Juan Island County seat and a 
United States Customs Port of Entry. (See NOAA Survey 
Chart 18425.) 
Existing project. 1,600-foot concrete breakwater to protect 
the existing port facilities and to allow the Port of Friday 
Harbor to provide 294 additional permanent moorage spaces 
and 44 additional transient spaces. Construction was completed 
in March 1984. 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-4 of FY 1981 Annual Report. 
Operations during the fiscal year. Maintenance, hired 
labor: Repairs to the concrete floating breakwater anchor 
system were completed in September 1992. The Corps crane 
barge PUGET was used to replace worn anchor chain and 
hardware. An underwater dive team rigged the worn portions 
of breakwater anchorage system for replacement. Repairs 
cost about $30,000. 
6. GRAYS HARBOR AND CHEHALIS RIVER, 
WA 
Location. Harbor lies at mouth of Chehalis River, in southwestern 
part of Washington, 45 miles north of entrance to 
Columbia River. Inner portion comprises two main channels, 
the south and the north, connecting harbor proper with 
Chehalis River at Aberdeen. Chehalis River rises in southwestern 
part of Washington about 40 miles east of Pacific 
Ocean, flows generally northwesterly and empties into eastern 
part of Grays Harbor. (See NOAA Survey Chart 18502.) 
Existing project (including navigation improvenemnts to 
date). Provides for an entrance channel across the bar and 
through entrance 600 to 1000 feet wide and 38 to 46 feet 
deep, to be secured by a south jetty 13,734 feet long and a 
north jetty 17,200 feet long, both at an elevation of 16 feet, 
and by dredging; maintenance of channel 36 feet deep and 
350 feet wide from deep water in Grays Harbor 14 miles to 
Cow Point; thence 30 feet deep and 200 feet wide, suitably 
widened at bends, to a point 13,700 feet upstream from Union 
Pacific Railroad bridge at Aberdeen, a distance of 4.125 
miles; a turning basin 30 feet deep, 550 feet wide, and 1,000 
feet long at upstream end of 30-foot channel near Cosmopolis; 
three breakwaters at, and maintenance of entrance 
channel to Westhaven Cove; protection of Point Chehalis for 
an exposed length of about 7,500 feet; and removal of 
350-foot southwestern extension of the breakwater, replacing 
it with an 865-foot northeastern extension, and adding a 
200-foot spur breakwater along the southerly entrance, constructed 
under authority of Section 107, P.L. 86-645. Construction 
cost for this feature is recorded in Table 38-C. 
Plane of reference is mean lower low water. Tidal range 
between mean lower low water and mean higher high water is 
8.9 feet at Point Chehalis, 10.1 feet at Aberdeen, and 8.1 feet 
at Montesano. Extreme range is 17.5 feet at Point Chehalis, 
17.8 feet at Aberdeen, and 23.8 feet at Montesano (river 
flood of 1935). Project was completed in 1981. Rehabilitation 
of 4,000 feet of the south jetty was completed in October 
1966. (For further details, see Annual Report for 1981. For 
details relating to previous projects, see pages 2002-03 of 
- 38-3 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
Annual Report for 1915 and page 1863 of Annual Report for 
1938.) 
Improved project. Authorized by Section 202 of the Water 
Resources Development Act of 1986. Project construction 
was started in April 1990. Completed project features are: 
deepen and widen 20 miles of existing 30-foot channel across 
ocean bar (46 feet deep and 1,000 feet wide), through the 
harbor entrance (46-38 feet deep and 1,000-600 feet wide), 
through South to Cow Point Reaches (36 feet deep and 350 
feet wide); expand and deepen Cow Point turning basin; 
deepen two downstream local berths; and construct fish and 
crab mitigation. Remaining project features are: deepen and 
widen 3.5 miles of existing 30-foot river channel (36 feet deep 
and 300-250 feet wide); expand Elliott Slough turning basin; 
deepen two upstream local berths; improve navigation aids; 
modify Union Pacific Railroad bridge; modify highway bridge 
fendering; remove two old highway bridge piers; and relocate 
utility lines. Construction is scheduled for completion in 
1994. Estimated project cost is $64,000,000 ($41,900,000 
Federal; $22,100,000 non-Federal). 
Local cooperation. Fully complied with. Local Cooperation 
Agreement with Port of Grays Harbor, local sponsor for 
improvement project, was executed on February 16, 1990. 
The Port is contributing 25-35 percent of project cost. In 
complying with terms of local cooperation, the Port is required 
to furnish lands and diked disposal areas and assure 
relocation of utility lines. 
Terminal facilities. There are 23 waterfront facilities 
(piers, wharves, and docks), exclusive of those available to 
recreational craft, at Grays Harbor, of which five are publicly 
owned. In foreign and domestic trade they serve various purposes 
which include the receipt and/or shipment of: logs and 
lumber, woodchips, conventional and containerized general 
cargo, seafood and fishing supplies, sand and gravel, and 
construction materials. Other uses include: mooring and 
icing fishing boats, mooring small vessels for outfitting and 
repair, and mooring company-owned tugs. Those piers operated 
by the U.S. Coast Guard moor government-owned vessels. 
(See Port Series No. 35 - Ports of Tacoma, Grays Harbor 
and Olympia, WA, revised 1983.) 
Operations during fiscal year. New work, hired labor: 
Supervised crab mitigation construction and monitoring. 
Continued preparation of plans and specifications for railroad 
bridge modification. Coordinated with local sponsor, 
resource agencies, and Union Pacific Railroad Company. 
New work, contract: Purchased and placed oyster shell on 
two crab mitigation construction sites. A-E contracts covered 
crab utilization of mitigation sites and review of railroad 
bridge plans and specifications. 
Maintenance, hired labor: Channel condition surveys were 
conducted throughout the year. The Corps hopper dredge 
Yaquina dredged in the entrance and South Reach channels 
in August/September 1992, removing 65,884 and 40,558 cy of 
material, respectively, at a cost of $376,250. The Corps hopper 
dredge Essayons dredged in Crossover and Cow Point 
Reaches in March 1992, removing 16,188 and 228,197 cy, 
respectively, at a cost of $948,260. The Essayons also dredged 
in the South Reach, entrance and bar channels in September 
1992, removing 55,562, 273,075 and 372,121 cy, respectively, 
at a cost of $1,270,500. 
Maintenance, contract: Maintenance dredging of the inner 
harbor was completed in July 1992, at a cost of $4,011,382 
with 2,350,442 cy of material being removed. An offshore 
erosion control berm using 200,000 cy of maintenancedredged 
sand was constructed in the vicinity of Westport to 
break larger waves eroding the shoreline and to nourish the 
beach at no increase in cost. 
7. KENMORE NAVIGATION CHANNEL, WA 
Location. The Kenmore Navigation Channel lies at the 
northern end of Lake Washington adjacent to the Sammamish 
River. Kenmore, an unincorporated industrial and 
business center in King County just north of Seattle, WA, 
encompasses the lands to the north of the channel. (See 
NOAA Survey Chart 18447.) 
Existing project. The construction of a navigation channel 
to serve the Kenmore industrial area, King County, WA, 
involves a 15-foot deep channel which consists of a 100-foot 
wide inner channel 900 feet long, an 800-foot-long transition 
channel with a 24 o 30-foot bend and a maximum width of 190 
feet, and a 120-foot-wide outer channel, 1,200 feet long. 
The project also consists of the installation of a goose nesting 
area on property adjacent to the new channel as mitigation 
for the removal of goose nests during construction. Project 
was completed in March 1981. 
Local Cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired labor: 
Routine coordination with navigation users. Dredged material 
management program costs resulted in an expenditure of 
$6,000. 
8. LAKE CROCKETT, WA 
Location. The harbor is on the west side of Whidbey Island, 
about 35 nautical miles north of Seattle, WA. The lake lies 
parallel to Admiralty Bay and is separated from it by a narrow 
strip of gravel beach. (See NOAA Survey Chart 18441.) 
Existing project. Provides for a basin in Lake Crockett with 
an area of about 6 acres and 18 feet deep at mean lower low 
water, connected with Admiralty Bay by a channel of the 
same depth and 150 feet wide, protected by a breakwater. 
The diurnal tidal range in Admiralty Bay is 8.4 feet and the 
extreme range is about 16.5 feet. Project was completed in 
January 1948. (For further details, see Annual Report for 
1948.) Recreational facilities at project under cost-sharing 
agreement with Washington State Parks and Recreation 
Commission include the following construction and improvements: 
construct a 35-unit camping loop and restroom, new 
boat ramp handling facility, breakwater, a restroom in the 
day-use area and porto-potti dumps for boats; and expand 
day-use facility and add riprap at the construction site. 
Local cooperation. None required. 
Terminal facilities. One publicly owned and privately 
owned passenger and automobile ferry landing within the 
dredged basin is open for public use, and is adequate for 
- 38-4 -

SEATTLE, WASHINGTON DISTRICT 
existing commercial traffic. The basin contains two publicly 
owned boat ramps open for public use. The ramps are adequate 
for recreational craft. 
Operations during fiscal year. Maintenance, hired labor: 
Channel condition surveys were conducted during the year. 
Performed environmental coordination and prepared plans 
and specifications for 1992/1993 maintenance dredging. 
9. LAKE WASHINGTON SHIP CANAL, WA 
Location. Entirely within city of Seattle and extends from 
Puget Sound through Shilshole Bay, Salmon Bay, Lake Union, 
Portage Bay, and Union Bay to deep water in Lake 
Washington. (See NOAA Survey Chart 18447.) 
Existing project. Provides for a double lock and fixed dam 
from gated spillway and necessary accessory works, including 
fishladder, at the Narrows at entrance to Salmon Bay, about 
1.25 miles from deep water in Puget Sound; for a channel 34 
feet deep and 300 feet wide from Puget Sound to Burlington 
Northern Railway bridge, about 5,500 feet, with a passing 
basin 34 feet deep and log basin 8 feet deep at turn below 
railway bridge; then 34 feet deep and 150 feet to 200 feet wide 
to locks, about 900 feet; and a guide pier 600 feet long; for 
revetment of canal banks between locks and Lake Union and 
between Lakes Union and Washington; and for a channel 30 
feet deep with a width of 100 feet from locks to Lake Union, 
200 feet thence to Portage Cut, 100 feet through Portage 
Cut, and thence 200 feet wide through Union Bay to Lake 
Washington. Section included in project is about 10 miles 
long. Plane of reference is mean lower low water. Extreme 
tidal range is 19.3 feet. Range between mean lower low water 
and mean higher high water is 11.3 feet, and between mean 
lower low water and extreme low water is 4.6 feet. Ordinary 
fluctuation in upper pool is 24 inches; extreme fluctuation 
has been 3.6 feet. Principal features of double lock and dam 
(structures are at Seattle, WA) are set forth in Table 38-H. 
Project was completed in 1934. (For further details, see Annual 
Report for 1935. For details relating to previous projects, 
see page 2003 of Annual Report for 1915, and page 
1880 of Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. The eight waterfront facilities at Lake 
Washington Ship Canal are used for fuel oil, seafood, marine 
repair, drydocking, outfitting, mooring fishing vessels and 
repairs to the locks' equipment. Project is a part of Seattle 
Harbor's inner harbor. (See Port Series No. 36, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Locks were operated and maintained all year, passing 15,109 
commercial and 52,340 pleasure vessels, and 2,945,253 tons 
of commerce. Fishladder passed more than 500,000 fish and 
there were more than 996,000 project visitors. 
Maintenance, contract: Contract for repair of the large 
lock upstream service and guard gates continued. Contracts 
were awarded in August and September 1992 to reroof the 
Cavanaugh House and three project buildings in the total 
amount of $100,450. 
10. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
Navigation activities pursuant to Section 107, Public Law 
86-645 (preauthorization). 
Fiscal year costs for preauthorization studies were: 
Anacortes Harbor, WA, $20,269; Friday Harbor, WA, $8,932 
(terminated); Keystone Harbor, Admiralty Inlet, WA, 
$45,333; Neah Bay, WA, $82,255; Port Townsend, WA, $252 
(terminated); Seabeck Marina, Hood Canal, WA, $9,809; 
Whatcom Creek Waterway, WA, $2,089 (terminated), a total 
of $168,939. In addition, $6,465 contributed funds were expended 
for Keystone Harbor, Admiralty Inlet, WA. 
Navigation activities prusuant to Section III, Public Law 
90-483 (preauthorization). 
Fiscal year costs were $16,204 at Grays Harbor, Point 
Chehalis, WA. 
11. OLYMPIA HARBOR, WA 
Location. Near southern end of Puget Sound at head of 
Budd Inlet, about 45 miles southwest of Tacoma. (See Coast 
and Geodetic Survey Chart 6462.) 
Existing project. Provides for a channel between deep 
water in Budd Inlet and port terminal, 30 feet deep at mean 
lower low water and 500 feet wide, with suitable additional 
width at bend; a turning basin adjacent to port terminal 30 
feet deep, 3,350 feet long, and 500 to 960 feet wide; and 
construction of a 656-foot concrete floating breakwater and 
dredging of the entrance and access channels and turning 
basin, constructed under authority of Section 107, P.L. 
86-645. Construction cost for this feature is recorded in 
Table 38-C (East Bay Small Boat Basin). Extreme tidal range 
is 22.5 feet. Range between mean lower low water and mean 
higher high water is 14.4 feet. Existing project was completed 
in 1985. (For details relating to previous projects, see page 
1369 of Annual Report for 1934 and page 1873 of Annual 
Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. Five port facilities are located in Olympia 
at Budd Inlet, exclusive of the numerous waterfront facilities 
in the ports used by recreational craft. The industrial 
docks are used for conventional general cargo, logs, timber 
products and miscellaneous mooring. (See Port Series No. 35 
- Ports of Tacoma, Grays Harbor and Olympia, WA, revised 
1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Maintained project coordination. Performed continuous 
water quality monitoring at East Bay Marina during the seasonal 
periods of poor water quality. An underwater dive 
inspection of the floating concrete breakwater confirmed the 
breakwater and anchor pile system to be in good condition. 
12. PROJECT CONDITION SURVEYS 
Hydrographic surveys and inspections to determine navigation 
conditions at boat basins, small navigation projects, and 
- 38-5 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
channels, not funded on a project basis for the current fiscal 
year. Soundings and visual inspections in subject areas are 
conducted in order to evaluate shoaling conditions. Hydrographic 
charts are prepared and distributed. Costs for the 
fiscal year were $66,457. Total costs to date are $3,121,473. 
(See Table 38-I.) 
13. PUGET SOUND AND ITS TRIBUTARY 
WATERS, WA 
Location. Puget Sound is in the western part of Washington. 
Cities of Seattle, Tacoma, Olympia, Everett, Bellingham, 
and many small towns are on its bays and inlets. (See 
NOAA Survey Charts 18400, 18441, and 18448.) 
Existing project. Maintenance of Puget Sound and its 
tributary waters by snagging and dredging; and removal, in 
cooperation with the U.S. Coast Guard and city of Seattle, of 
floating debris from the Seattle Harbor area. Work consists 
of collecting large pieces of drift, waterlogged pilings, logs 
and other debris considered hazardous to navigation from 
Puget Sound and Federally authorized channels. (For details 
relating to previous projects, see page 2003 of Annual Report 
for 1915 and page 1869 of Annual Report for 1938.) 
Local cooperation. None required. Cities of Seattle, 
Tacoma, Olympia, Everett and Bellingham are cooperating 
in a program for control of floating debris in their harbors and 
setting up collection sites for our debris vessel. 
Terminal facilities. Terminal facilities at numerous localities 
on Puget Sound and its tributary waters are, in general, 
considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired labor: 
The debris vessel Puget operated continuously throughout 
Puget Sound and its tributary waters and removed approximately 
1900 tons of floating debris and hazards to navigation. 
(Debris tonnage was down due to shipyard maintenance.) 
Debris was disposed of locally or loaded aboard barges and 
disposed of by contract. Snagging operations were accomplished 
at Blaine Harbor, Bellingham Harbor, Swinomish 
Channel, Skagit River, Everett Harbor, Snohomish River 
(upstream to town of Snohomish), Lake Washington Ship 
Canal, Lake Washington, Tacoma Harbor, Olympia Harbor, 
Duwamish River, and Elliott Bay. 
Maintenance, contract: 500 tons of harbor debris were 
disposed of at a cost of $58,000. Contractor continues to 
recycle much of the debris, reducing the cost of disposal by 
contract. Remainder of debris is placed in a demolition 
landfill. 
14. QUILLAYUTE RIVER, WA 
Location. River is formed by junction of Soleduck and 
Bogachiel Rivers, in northwestern Washington, and flows 
westerly 5 miles to Pacific Ocean at La Push, about 30 miles 
south of Cape Flattery. (See NOAA Survey Chart 18480.) 
Existing project. Provides for: (a) jetty 15 feet high on 
easterly side of river mouth, and a dike on westerly side, with 
a view of stabilizing entrance; (b) channel 10 feet deep and 
100 feet wide extending 2,000 feet upstream from deep 
water; (c) basin 10 feet deep, 300 to 425 feet wide, and 2,400 
feet long upstream of channel; and (d) maintenance of an 
ocean spit. Plane of reference is mean lower low water. 
Range between mean lower low water and mean higher high 
water at La Push is 8.3 feet. Extreme range is about 15 feet. 
The spit is nourished with dredged material in conjunction 
with channel dredging. The spit was rehabilitated with quarry 
rock in 1974, in 1979-80, and in 1982. In addition, a 500-foot 
breakwater section paralleling the channel and extending the 
spit was constructed. Project was completed in February 
1960. (For further details, see Annual Report for 1963.) 
Local cooperation. Fully complied with. Project sponsorship 
was transferred from the Port of Port Angeles to the 
Quileute Tribe Port Authority in 1983. 
Terminal facilities. There are 3 privately-owned docks at 
La Push, near the mouth of the Quillayute River. In addition, 
there is a protected boat basin owned by the Quileute Tribe 
Port Authority which is used by fishing boats, pleasure craft, 
and the Coast Guard, which has a separate pier. 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys were made of the river channel. 
15. SEATTLE HARBOR, WA 
Location. Harbor at Seattle, WA, includes all waterways 
within city limits. Chief anchorage basin is Elliott Bay, an arm 
of Puget Sound. (See NOAA Survey Chart 18450.) 
Existing project. Maintenance of East and West Waterways, 
34 feet deep and 750 feet wide for 6,500 and 5,200 feet, 
respectively, from pierhead line in Elliott Bay, the 30-foot by 
200-foot wide channel from West Waterway to 1st Avenue 
South Bridge, and the 20-foot by 150-foot-wide channel 
from 1st Avenue South Bridge to 8th Avenue; dredging 
Duwamish Waterway 150 feet by 15 feet from 8th Avenue to 
a point about 1.4 miles above 14th Avenue South Bridge, and 
turning basin 500 by 250 feet and 15 feet deep at the upper 
end of the waterway; maintenance of East Waterway between 
upper end of 750-foot section and Spokane Street, 34 feet 
deep, 700 feet long and 400 feet wide, and a turning basin, 
including head of East Waterway at junction of waterways 
south of Chicago, Milwaukee, St. Paul & Pacific Railroad 
bridge, to 30 feet deep, after these sections of waterway are 
dredged by local interests to full project dimensions. Total 
length of all waterways included in project is about 7.5 miles. 
Plane of reference is mean lower low water. Range between 
mean lower low water and mean higher high water is 11.3 
feet. Extreme tidal range is 19.3 feet. Project was completed 
in 1931, excluding maintenance of East Waterway above the 
750-foot section. Turning basin, constructed under authority 
of R&H Act of Mar. 3, 1925, in 20-foot deep waterway was 
deauthorized by P.L. 99-662 dated Nov. 17, 1986 (see Report 
of the Chief of Engineers, dated May 31, 1985). (For further 
details, see Annual Report for 1932.) 
Local cooperation. Fully complied with. Local sponsor has 
no maintenance responsibility. 
Terminal facilities. There are 196 piers, wharves, and docks 
located on the inner and outer harbors at Seattle, WA. 
Salmon Bay, Lake Union, Portage Bay and Lake Washington 
form the inner harbor; Elliott Bay and East, West and 
- 38-6 -

SEATTLE, WASHINGTON DISTRICT 
Duwamish Waterways form the outer harbor. (Lake Washington 
Ship Canal, a part of the inner harbor, is a separate 
project in this report.) These terminals serve a variety of 
purposes which include cargo handling, bunkering vessels, 
ferry service (vehicular, passenger and rail car), marine repair/
outfitting/drydocking/conversion, shipbuilding, handling 
supplies and equipment, and mooring company-owned 
equipment, excursion vessels, fire boats, fishing vessels, government 
equipment, harbor craft/tugs, and oceanographic 
research vessels. The numerous waterfront facilities in the 
port used exclusively by recreational craft are not included. 
(See Port Series No. 36, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys made of channels. Sediment sampling and 
testing was performed to characterize sediments proposed 
for open water disposal. Dredged material management 
program costs resulted in an expenditure of $86,000. 
Maintenance, contract: Maintenance dredging of the upstream 
turning basin and channel was completed in February/
March 1992 at a cost of $410,000 with 221,646 cy of 
material being removed. In a cooperative beneficial use project 
with the city of Seattle, 4.5 acres of contaminated Elliott 
Bay sediment was capped with 22,285 cy of clean sand from 
the maintenance. Seattle District has been a leader in development 
and use of economic capping technology since 1984. 
16. SWINOMISH CHANNEL, WA 
Location. An inland passage, 11 miles long, between 
Saratoga Passage and Padilla Bay, in northwestern part of 
Washington, about 60 miles north of Seattle. (See NOAA 
Survey Charts 18400, 18427 and 18421.) 
Existing project. A channel 100 feet wide and 12 feet deep 
for 11 miles from deep water in Saratoga Passage to deep 
water in Padilla Bay, by dredging and dike construction where 
necessary; and removal of protecting rocky points of McGlinn 
and Fidalgo Islands obstructing navigation at "Hole-in-the- 
Wall". Plane of reference is mean lower low water. Range 
between mean lower low water and mean higher high water is 
11.5 feet at south end of channel, 8.4 feet at north end, and 10 
feet at La Conner. Extreme tidal range is about 19.5 feet at 
south end of channel and about 16 feet at north end. Project 
was completed in March 1965. (For further details, see Annual 
Report for 1965.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 18 wharves, docks, and piers 
on Swinomish Channel, all but 3 of which are privately 
owned. Of these, 1 is used for handling general cargo, 5 are 
used exclusively for moorage, unloading and servicing of fishing 
vessels; 2 are used for handling petroleum products; 3 
facilities are used for log dumps; and 2 for handling non-metallic 
minerals. Three publicly owned facilities for launching, 
mooring, and servicing small craft are within the city limits of 
La Conner. 
Operations during fiscal year. Maintenance, hired labor: 
Maintained project coordination. Dredged material management 
program costs resulted in an expenditure of $31,000. 
17. TACOMA HARBOR, WA 
Location. Harbor includes Commencement Bay and tributary 
waterways at Tacoma, in northwestern Washington. 
(See NOAA Survey Chart 18453.) 
Existing project. Provides for: (a) channel in City Waterway 
500 feet wide and 29 feet deep from deep water in 
Commencement Bay to 11th Street Bridge, 500 feet wide and 
22 feet deep to 14th Street Bridge, and varying from 500 to 
250 feet wide and 19 feet deep from 14th Street Bridge to end 
of this waterway, a total length of 8,500 feet; (b) channel in 
Hylebos Waterway 30 feet deep, 3.1 miles long, and 200 feet 
wide except where width is increased to 250 feet at the bend 
below East 11th Street, to 300 feet at Lincoln Avenue bend, 
and to 510 feet and 770 feet, respectively, at the channel 
widening above Lincoln Avenue and the turning basin at the 
head of the waterway; (c) construction of two training walls, 
each about 700 feet long at mouth of Puyallup River; and (d) 
channel in Blair Waterway 2.6 miles long, including a portion 
seaward of East 11th Street, 650 feet wide and 30 feet deep 
over southerly 350 feet, and 35 feet deep over northerly 300 
feet; and remaining portion, 35 feet deep and 150 feet wide at 
East 11th Street, 600 feet wide between East 11th Street and 
Lincoln Avenue, and 300 feet wide between Lincoln Avenue 
and a 1,200-foot wide turning basin at head of waterway. 
Plane of reference is mean lower low water. Range between 
mean lower low water and mean higher high water is 11.8 
feet. Extreme tidal range is about 20 feet. Project was completed 
in December 1966. (For further details, see Annual 
Report for 1967. For details relating to previous projects, see 
pages 1372 to 1376 of Annual Report for 1934 and page 1875 
of Annual Report for 1938 for Puyallup Waterway, and page 
1702 of Annual Report for 1944 and page 1502 of Annual 
Report for 1954 for Blair (formerly Wapato and Port Industrial) 
Waterway.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 81 terminal facilities, exclusive 
of those available to recreational craft, located in 
Tacoma Harbor which is comprised of Commencement Bay 
and its many waterways. These facilities serve a variety of 
purposes which include cargo handling, fueling small vessels, 
ferry traffic, marine repair, conversion/outfitting, dry-docking, 
mooring, bunkering, ship-building and shipbreaking. 
(See Port Series No. 35 - Ports of Tacoma, Grays Harbor, and 
Olympia, WA, revised 1983.) 
Operations during fiscal year. Maintenance, hired labor: 
Dredged material management program costs resulted in an 
expenditure of $6,000. 
18. WILLAPA RIVER AND HARBOR AND 
NASELLE RIVER, WA 
Location. Willapa Harbor consists of lower reaches of Willapa 
River and Bay, an inlet of Pacific Ocean about 30 miles 
north of mouth of Columbia River in Washington. Willapa 
River rises about 30 miles east of harbor, flows generally 
westerly, and empties into the bay. Naselle River enters the 
bay near its southerly end. (See NOAA Survey Chart 18504.) 
Existing project. Provides for: (a) channel over bar at 
mouth of Willapa Bay, 26 feet deep and at least 500 feet wide; 
- 38-7 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
(b) channel 24 feet deep and 200 feet wide from deep water in 
Willapa Bay to foot of Ferry Street at South Bend, thence 300 
feet wide to westerly end of narrows, thence 250 feet wide to 
forks of river at Raymond, including a cutoff channel 3,100 
feet long at narrows and a closing dike at Mailboat Slough; (c) 
channel 24 feet deep and 150 feet wide up south fork to deep 
basin above Cram Lumber Mill, and up north fork to 12th 
Street, with a turning basin 250 feet wide, 350 feet long, and 
24 feet deep at latter point; (d) channel 10 feet deep and 40 
feet wide from deep water in Palix River to Bay Center dock, 
with widening at shoreward end to provide a small mooring 
basin; (e) mooring basin 15 feet deep, 340 feet wide, and 540 
feet long adjacent to port wharf at Tokeland; (f) entrance 
channel at Nahcotta 10 feet deep and 200 feet wide, and 
mooring basin 10 feet deep, 500 feet wide, and 1,150 feet 
long, protected by a rubblemound breakwater about 1,500 
feet long; and (g) removal of snags, piles, and other obstructions 
in navigable channel of Naselle River between Naselle 
and mouth. Project includes about 26 miles of channel from 
entrance through Willapa River forks, 2,800 feet of Palix 
River-Bay Center channel, and 9 miles of Naselle River 
upstream of U.S. Highway 101 Bridge. Plane of reference is 
mean lower low water. Tidal range between mean lower low 
water and mean higher high water is 8.9 feet at Toke Point, 
9.9 feet at Raymond, 8.9 feet at Bay Center, and 10.8 feet 
near Naselle. Extreme range is 18 feet at Toke Point, 19.3 
feet at Raymond, 16 feet at Bay Center, and 18 feet near 
Naselle. Project was completed in November 1958. (For further 
details, see Annual Report for 1959. For details relating 
to previous projects, see page 968 of Annual Report for 1910, 
page 2001 of Annual Report for 1915, and page 1861 of 
Annual Report for 1938.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are 24 wharves on Willapa River 
and Harbor, including5 in Willapa Bay, 4 in Bay Center, 12 in 
Raymond and South Bend, and 1 in Tokeland. Two of the 
wharves at Raymond and South Bend are suitable for use by 
ocean-going vessels. One of these is publicly owned and 
operated as a general cargo terminal, and one is located at a 
sawmill. The other wharves, including 3 that are publicly 
owned and operated, are used by shallow-draft vessels. 
These facilities are considered adequate for existing commerce. 
Operations during fiscal year. Maintenance, hired labor: 
Condition surveys were made of various segments of the 
project. 
Maintenance, contract: The Port of Willapa Harbor performed 
Toke Point Marina berthing area clamshell maintenance 
dredging. 
Beach Erosion 
Beach Erosion Control 
19. LINCOLN PARK BEACH, SEATTLE, WA 
Location. Project is located within the city of Seattle, at 
Williams Point, and adjacent to the East Passage of Puget 
Sound. 
Existing project. Initial beach nourishment consisted of the 
placement of 34,000 tons of sand, gravel, and cobble fill 
seaward of the existing seawall, a distance of 2,300' along the 
southwest beach. The fill extended horizontally 10' seaward 
of the wall, then sloped downward on a 1V to 5H gradient to 
intersect the existing groundline 65' seaward of the wall. 250' 
of rock revetment, at Williams Point, consisting of 2 layers of 
1,500- to 4,000-pound armor rock were placed on a 2'-thick 
filter bed of quarry spalls, constructed with a 1V to 1.5H 
slope, a 10'-top width, and a top elevation approximately 1' 
above the existing seawall. The revetment is fronted by 2,000 
tons of gravel and cobble fill, with the same top elevation, 
slope and seaward extent as the beach nourishment on the 
southwest beach. Periodic beach nourishment, consisting of 
placement of beach material to replenish the erosion loss, is 
required approximately every 5 years. Monitoring of beach 
nourishment consists of initial and periodic profile surveys, 
estimate alongshore/offshore volumes of material, periodic 
beach sediment sampling, and evnironment re-establishment. 
Initial construction was completed in December 1988. 
Re-nourishment is being studied for placement in fall of 
1993. Studies will include rate of material loss, re-nourishment 
required, and environmental considerations. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (city of Seattle) provided 35% of 
total project cost. Local Cooperation Agreement was executed 
on June 15, 1988. 
Operations during fiscal year. New work, hired labor: Continued 
post-construction monitoring and initiated re-nourishment 
study. 
Flood Control 
20. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 14, Public Law 
526, 79th Congress as amended (preauthorization). 
Fiscal year costs were: Clark Fork River, MT, $13,591 and 
Half Moon Bay, WA, $3,553 (terminated), a total of $17,144. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended (preauthorization). 
See Table 38-J. 
- 38-8 -

SEATTLE, WASHINGTON DISTRICT 
Emergency flood-control activities - repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and antecedent 
legislation.) 
See Table 38-K. 
21. HOWARD A. HANSON DAM, WA 
Location. Green River, in northwestern Washington, flows 
westerly for 40 miles to Auburn, thence northerly 32 miles to 
its mouth in Elliott Bay at Seattle. Dam is at river mile 64, 6 
miles southeast of Kanaskat, and 1 mile downstream from 
mouth of North Fork. (See Geological Survey topographic 
sheet, "Cedar Lake Quadrangle, WA.") 
Existing project. Rockfill dam about 235 feet high, with 
gated spillway having a concrete weir at elevation 1176 feet 
above mean sea level and top of gates at elevation 1206, 
creating a reservoir with capacity of 106,000 acre-feet. Dam 
along crest is about 675 feet long. Improvement is designed to 
control flooding in Green River Valley to alleviate agricultural 
and urban flood damage, and make possible further 
expansion of Seattle industrial area. It also supplements 
Tacoma water supply which was included as a betterment. 
Project was completed in June 1963. (For further details, see 
Annual Report for 1963.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired labor: 
Operation continued all year. Routine maintenance was accomplished 
on roads, gages, debris booms, ditches, powerline, 
and other project features. Additional anchorage was 
provided for the 36" by-pass pipeline. Work continued on 
water quality surveys. 
Maintenance, contract: Contract was awarded for installation 
of additional right abutment piezometers. 
22. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections are made of Federally constructed local flood 
protection projects which are maintained by local interests, 
and agencies responsible for their operation and maintenance 
are advised of any needed repairs. During the fiscal 
year, inspections were made on American Lake at Tacoma, 
Dungeness River at Sequim, Okanogan River at Omak and 
Oroville and Sammamish River in Washington state; Lightning 
Creek, Coeur d'Alene, St. Maries and Placer Creek 
projects in Idaho; and, Clark Fork River at Missoula in Montana. 
Fiscal year costs were $74,928. Costs to date have been 
$1,057,711. 
23. LOWER GREEN RIVER, KING COUNTY, 
WA
Location. The project lies wholly within the city limits of 
Tukwila in King County, WA. 
Existing Project. The project involves a Standard Project 
Flood (SPF) levee approximately 3.5 miles long. The downstream 
one third of the levee was constructed in an existing 
strip park along the levee alignment and the upstream two 
thirds is a conventional levee. Close coordination with the 
city of Tukwila was necessary during construction to insure 
that the use of the strip park for recreation would not be 
affected by the levee construction. Construction was completed 
in May 1992. Completion of an operation and maintenance 
manual and final fiscal requirements remain. 
Local cooperation. Under current cost sharing requirements, 
the local sponsor (The City of Tukwila) will pay a 
minimum of 25% of project costs. A Local Cooperation 
Agreement was executed. The local sponsor will provide 
operation and maintenance of the project. 
Operations during the fiscal year. New work, hired labor: 
Initiated preparation of operation and maintenance manual. 
New work, contract: Completed construction contract. 
24. MUD MOUNTAIN DAM, WA 
Location. On White River, principal tributary of Puyallup 
River, near Mud Mountain, 28 miles above its confluence 
with Puyallup River, and 38 miles above mouth of Puyallup 
River. Dam is 6 miles southeast of Enumclaw, in northwestern 
Washington, and 38 miles east of Tacoma. (See Geological 
Survey topographic sheet "Cedar Lake Quadrangle, 
Washington.") 
Existing project. Rockfill dam, 700 feet long at crest elevation, 
rises 432 feet above bedrock. Reservoir has storage 
capacity of about 106,000 acre-feet. Outlet works are in right 
abutment and permit controlled discharge of 17,700 cubic 
feet per second through two concrete-lined tunnels with 
uncontrolled discharge over spillway having maximum capacity 
of 139,000 cubic feet per second. Improvement affords 
flood protection to White and Puyallup River Valleys and 
protects Tacoma industrial district in conjunction with Puyallup 
River project at Tacoma against floods about 50 percent 
greater than maximum discharge of record. Project was completed 
in June 1953, except for recreational facilities. (For 
further details, see Annual Report for 1953.) To date the 
Corps has constructed two vistas, a picnic area, and playground 
adjacent to the project office, a reservoir access point 
for hunters and fishermen, and a 1,760-foot trail leading to 
the lower vista area. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired labor: 
Project features were operated all year. Maintenance was 
accomplished on dam facilities, intake structure, gages, debris 
booms, power lines, roads, ditches, vista observation 
deck, recreation area, and fish facilities. Approximately 2,054 
fish were transported from the fish collection facility. 
Dam Safety Assurance. New work, hired labor: Supervision 
and inspection of construction contracts. Initiated engineering 
during construction support for the new reservoir 
outlet tower. 
New work, contract: Contract for construction of a new 
reservoir outlet tower was awarded. 
Major Rehabilitation. Major rehabilitation work which 
commenced in FY 1987 was completed in FY 1992. New 
work, hired labor: Supervision and inspection of installation 
contract. 
- 38-9 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
New work, contract: Contract for installation of dam instrumentation, 
piezometers, and inclinometers was completed. 
25. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Flood control storage space was available in Hungry Horse 
Reservoir, MT, Flathead Lake, MT (controlled by Kerr 
Dam), Grand Coulee project, WA, Upper Baker and Ross 
Reservoirs, WA. Guidance forecasts were made during the 
flood control season, as required. No Lost Valley storage 
replacement was requested at Rocky Reach, Priest Rapids, 
and Wells Dams. Daily and/or hourly data were collected and 
tabulated as required to check compliance with operating 
criteria. Coordination necessary in preparation or revision of 
reservoir regulation manuals was carried on during the year 
with agencies responsible for the operation of these projects. 
Fiscal year costs were $206,399. Total costs to date have been 
$2,738,107. 
26. STILLAGUAMISH RIVER, WA 
Location. Formed by confluence of its north and south 
forks at Arlington, in northwestern Washington, Stillaguamish 
River flows westerly 22 miles to Puget Sound, 
entering Port Susan through Hat Slough and South Pass, and 
Skagit Bay through West Pass. (See NOAA Survey Chart 
18441, and Geological Survey Quadrangles Stanwood, 
Marysville, and Stillaguamish, WA.) 
Existing project. Works to reduce bank erosion and channel 
changes on Stillaguamish River 15 miles between Arlington 
and head of Hat Slough, and on Cook Slough, 3 miles 
long, as follows: Revetment at 26 places on river and Cook 
Slough; concrete weir (including a fishway) 275 feet long 
between steel-sheet-pile piers at head of Cook Slough to 
limit flow through slough; and two cutoff channels, each 
about 900 feet long, to eliminate sharp bends in Cook Slough. 
Tidal influence extends about 3 miles into improved section. 
Flood stages of 16 feet above low water at Cook Slough weir 
have been observed. Project was completed in July 1939. (For 
further details, see Annual Report for 1940.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired labor: 
Utilized in-house labor and equipment to replace rock riprap 
bank protection along segments 10, 23, and 24. 
27. TACOMA, PUYALLUP RIVER, WA. 
Location. Puyallup River has its source in glaciers on western 
slopes of Mount Rainier, WA, flows northwesterly 50 
miles, and empties into Commencement Bay, an arm of 
Puget Sound, at Tacoma. Work covered by this project is on 
Puyallup River, within city limits of Tacoma. (See NOAA 
Survey Chart 18453.) 
Existing project. A channel with a capacity of 50,000 cubic 
feet per second between East 11th Street Bridge and lower 
end of inter-county improvement, a distance of about 2.2 
miles, by straightening channel, building levees, revetting 
channel and levees, and making necessary bridge changes. 
The 11th Street Bridge at lower end of project is 0.75 mile 
above mouth of Puyallup River. Diurnal tidal range at mouth 
of river is 11.8 feet and extreme range is 20 feet. Improvement 
was planned in conjunction with Mud Mountain Dam 
and affords protection against floods about 50 percent 
greater than maximum discharge of record. A real estate 
design memorandum, approved by Office of the Chief of 
Engineers on October 2, 1985, changed the project boundary 
to allow the Port of Tacoma to create a wetland adjacent to 
the project. This action resulted in the Corps acquiring approximately 
2,450 linear feet of setback levee in fee simple. 
Maintenance funds to cover the increased length of the project 
have been provided by the Port of Tacoma for the project 
life. Project was completed in May 1950. (For further details, 
see Annual Report for 1950.) 
Local cooperation. Fully complied with. 
Operations during fiscal year. Maintenance, hired labor: 
Removed brush and noxious weeds from the entire project 
along slopes of levee. 
28. WYNOOCHEE LAKE, WA 
Location. On Wynoochee River, a tributary of Chehalis 
River, about 28 miles north of Montesano, Grays Harbor 
County, WA. (See Geological Survey Quadrangles, Grisdale, 
Wynoochee Valley, and Montesano.) 
Existing project. Provides for a concrete and earthfill dam, 
177 feet high, and reservoir of 70,000 acre-feet of total storage 
for water supply, flood control, irrigation, and fish and 
wildlife. Upstream fish facilities were operational in the fall 
of 1970. The project was completed and became operational 
in December 1972. Installation of power-generating facilities 
was not authorized, pending a reexamination report by the 
Chief of Engineers. In February 1966, the Federal Power 
Commission asserted that power production as part of the 
Wynoochee project was not feasible at that time. (For further 
details, see Annual Report for 1972.) 
Local cooperation. Fully complied with. Requirements are 
described in full on page 38-12 of FY 1981 Annual Report. 
The Water Resources Development Act of 1988 authorized 
the Secretary of the Army to transfer the Operations, Maintenance, 
Repair and Rehabilitation (OMR&R) of the 
Wynoochee project to the city of Aberdeen. The dam was 
built on a cost-share basis with the city which paid approximately 
46% of the investment and the O&M costs. The 
legislation relieved the city of the O&M payment when it 
assumed the OMR&R, to the extent the city personnel does 
the work. The OMR&R was assumed by city of Aberdeen on 
July 1, 1990. 
Operations during fiscal year. Maintenance, hired labor: 
Beginning July 1, 1990 the Corps' effort has been limited to 
quality assurance monitoring and water control assistance in 
flood control operations. Legislation has been enacted which 
allows fee title transfer of the Wynoochee Lake project to the 
city of Aberdeen. 
- 38-10 -

SEATTLE, WASHINGTON DISTRICT 
Multiple-Purpose Power 
29. ALBENI FALLS DAM, ID 
Location. Dam is on Pend Oreille River about 25 miles 
west of Sandpoint, in northern Idaho, and 50 miles northeast 
of Spokane, WA. Dam is 838 and 90 miles upstream from 
mouths of Columbia and Pend Oreille Rivers, respectively. 
(See Geological Survey topographic sheets, Sandpoint, ID, 
and Newport, WA.) 
Existing project. Provides flood control, hydroelectric 
power, and related water uses on Pend Oreille River as a part 
of the multiple-purpose plan for development of Columbia 
River Basin, including recreation development. At the dam, 
the river channel was formerly divided by an island and a low 
waterfall of about 7 feet. Dam is a gated, gravity-structure 
spillway in left channel and a powerhouse having an installation 
of 42,600 kilowatts in right channel, creating a reservoir 
with a usable storage capacity of 1,153,000 acre-feet. Project 
was completed in June 1957. (For further details, see Annual 
Report for 1957.) Recreational facilities for public use have 
been provided at Albeni Cove, Priest River, Riley Creek, 
Johnson Creek, Trestle Creek, Strongs Island, and Springy 
Point. (Strongs Island was closed in FY 1982 to reduce O&M 
costs.) (Refer to Albeni Falls Master Plan dated June 1981 
for further planned development.) 
Local cooperation. None required. 
Operations during fiscal year. Maintenance, hired labor: 
Reservoir was operated through its annual cycle of storage 
and release. Routine structural, mechanical, and electrical 
maintenance was performed on spillways, dam, powerhouse, 
and equipment. 
Maintenance, contract: Contracts were awarded for 4 gate 
houses ($42,300), debris removal ($140,200), annunciator 
system ($42,600), station service transformers ($27,500), and 
restroom rehabilitation ($96,000). 
30. CHIEF JOSEPH DAM - RUFUS WOODS 
LAKE, WA 
Location. On Columbia River in north central Washington, 
at River Mile 545, just upstream from mouth of Foster Creek, 
1.5 miles upstream from Town of Bridgeport. (Geological 
Survey topographic sheet, Okanogan, WA, shows general 
locality.) 
Existing project. A concrete gravity structure which consists 
of a 19-gate spillway and a 27-unit powerhouse. The 
powerhouse has sixteen 88,274 kilowatt and eleven 95,000 
kilowatt generators with nameplate capacity of 2,457,384 
kilowatts. Work continued to bring turbine efficiency for 
units 17-27 up to design standards. Estimated cost of current 
construction project is $397,000,000. 
Local cooperation. None required. 
Operations during fiscal year. New work, hired labor: Continued 
real estate acquisition. 
New work, contract: Contracts continuing through the 
fiscal year included project security, data acquisition and control 
system, project final completion, station service governors, 
repaint powerhouse interior, and turbine deficiency 
correction (units 17-27). Contracts completed during the 
fiscal year included circuit breaker sound suppressors (units 
1-16) and replacement of generator brakes (units 17-27). 
Maintenance, hired labor: Project was operated all year, 
and routine maintenance work was performed. 
Maintenance, contract: Major contracts awarded during 
the fiscal year included seal spillway pier cracks, and Brown 
Boveri replacement parts. Contracts continuing through the 
fiscal year included wildlife mitigation and security implementation. 
31. LIBBY DAM - LAKE KOOCANUSA, MT 
Location. On Kootenai River in Lincoln County, MT, 
about 17 miles upstream from Libby, and 219 miles upstream 
from confluence of Kootenai and Columbia Rivers. (See 
Geological Survey topographic sheet, Thompson Lakes, 
MT.) 
Existing project. Provides storage for local flood control 
protection in Montana and Idaho, and main stem flood control 
in Lower Columbia River, hydroelectric power generation 
at-site and at downstream plants through storage release. 
Project is operated as a unit of comprehensive system 
for improvement of Columbia River basin for flood control, 
navigation, hydroelectric power, and other purposes. 
Local cooperation. Fully complied with. 
Libby Dam - Lake Koocanusa Project. Dam is a straight 
concrete gravity overflow type, 420 feet high, 3,055 feet long, 
with normal full pool at elevation 2459 feet above mean sea 
level. Powerhouse has an initial installed capacity of 420,000 
kilowatts from four hydroelectric generating units.A fifth 
unit was completed in 1984 with capacity of 105,000 kilowatts, 
and there is a provision for three additional units. Lake 
Koocanusa is 90 miles long, backing water 42 miles into 
Canada and has a usable storage capacity of 4,965,000 acrefeet 
at 50 percent drawdown. Construction of dam was in 
accordance with treaty between United States and Canada 
relating to international cooperation in water-resource development 
of the Columbia River basin. Construction is complete. 
Operations during fiscal year. Maintenance, hired labor: 
Reservoir was operated through its annual cycle of storage 
and release. Routine structural, mechanical, and electrical 
maintenance was performed on spillway, dam powerhouse, 
and equipment. 
Maintenance, contract: Contracts were awarded for power 
house HVAC renovation ($179,000), removal of underground 
storage tanks ($61,400), and purchase of aboveground 
storage tanks ($23,200). 
Libby Additional Units Project. Provides for installation of 
4 additional units at the Libby Dam powerhouse. Fabrication 
of generators for units 5 through 8 is complete; however, only 
the unit 5 generator was installed. Installation of the electrical 
equipment was limited to unit 5. Parts for units 6 through 
8 have been stored at the site. Project is complete with units 1 
through 5 operational. Units 6 through 8 have been reclassified 
inactive. 
- 38-11 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
Operations during fiscal year. None. 
Libby Reregulating Dam Project. Provides for construction 
of a reregulating dam about 10 miles downstream of Libby 
Dam and associated relocation of about 9 miles of Burlington 
Northern Railroad, 7.5 miles of St. Regis log haul road, 0.5 
mile of Forest Development Road, and 7.5 miles of Montana 
State Highway. Funds were provided for a construction start 
in 1977; however, courts have found that Congress did not 
authorize construction of the reregulating dam. 
Operations during fiscal year. In FY 1982, all work was 
terminated due to court direction. 
Libby Reregulating Dam - Power Units Project. Provides 
for installation of three hydroelectric generating units at the 
reregulating dam with 78,900 kilowatt installed capacity. A 
General Design Memorandum 1, Phase II, Preliminary Design 
Report was approved by the Office, Chief of Engineers 
on March 3, 1981. 
Miscellaneous 
32. MISCELLANEOUS WORK UNDER 
SPECIAL AUTHORIZATION 
Project Modifications for Improvement of Environment 
(Section 1135, Public Law 99-662). 
Fiscal year costs were: Sammamaish River Restoration, 
WA, $29,822. 
Aquatic plant control (Section 302, Public Law 89-298). 
The program consists of control measures for selected 
water bodies currently infested with Eurasian watermilfoil 
and measures to prevent its spread into uninfested waters. 
Major operations under the cost-share program included 
mechanical harvesting of 27 acres, maintaining 6 acres of 
fiberglass bottom screens at Lake Washington, Lake Union 
and Lake Sammamish, WA; follow up to the chemical treatment 
of 82 acres with the aquatic herbicide fluridon in Long 
Lake, WA (inspection, diver-operated dredge, bottom barriers); 
rotovating 100 acres at Pend Oreille River, WA; lake 
drawdown and inspection in Lake Chelan, WA; and, chemically 
treating 40 acres with the aquatic herbicide fluridon at 
Columbia River, WA. The FY 1992 work also included treatment 
effectiveness and carryover studies, final write-up by 
the University of Washington on a grass carp study, aquatic 
plant surveys, and public information efforts. Total costs for 
the fiscal year were $305,179. 
General Investigations 
33. SURVEYS 
Fiscal year costs were -$18,630 for navigation studies, 
$207,874 for flood damage prevention studies, $259,607 for 
special studies, $373,316 for review of authorized projects, 
$166,536 for miscellaneous activities, and $129,323 for coordination 
with other agencies and non-Federal interests, a 
total of $1,118,026. In addition, $19,028 contributed funds 
were expended for the navigation study, Olympia Harbor, 
WA, and $209,796 contributed funds were expended for review 
of authorized projects, Howard Hanson Dam Water 
Storage, WA, and $20,556 contributed funds were expended 
for coordination with other agencies and non-Federal interests, 
a total of $249,380. 
34. COLLECTION AND STUDY OF BASIC 
DATA 
The work programmed for collection and study of basic 
data covers international water studies, flood plain management 
services, and hydrologic studies. Work on international 
water studies included checking Kootenay Lake storage computations 
to determine compliance of West Kootenay Power 
& Light Co. with orders of International Joint Commission, 
and coordination with International Kootenay Lake and 
Osoyoos Lake Boards of Control in enforcement of International 
Joint Commission orders. Technical assistance was 
provided other Federal and non-Federal agencies in flood 
hazard evaluation and related services as requested. Fiscal 
year costs were $2,571 for international water studies, 
$116,327 for flood plain management services, and $4,241 for 
hydrologic studies, a total of $123,139. In addition, $9,741 
contributed funds were expended for flood plain management 
services. 
35. PRECONSTRUCTION ENGINEERING 
AND DESIGN 
Centralia, WA 
The city of Centralia lies in west central Washington at the 
confluence of the Chehalis and Skookumchuck Rivers, about 
midway along the Chehalis River from its source in the Willapa 
Hills to its mouth at Aberdeen at Grays Harbor. Floods 
of record on Skookumchuck and Chehalis Rivers occurred in 
January 1990. 
The plan of improvement authorized in P.L. 99-662 would 
reduce flooding in the Skookumchuck River valley for the 22 
miles between Skookumchuck Dam and the river mouth and 
along the Chehalis River downstream from Centralia for 
about 20 miles to Oakville. The improvement, as recommended 
in the feasibility report, consists of structural modifications 
(flood control outlet tunnel and spillway gate) which 
would enable the existing, private water supply dam to provide 
flood control storage during winter months. The 
200-year flood on the Skookumchuck River at Centralia 
would be reduced from 13,300 cubic feet per second to 6,700 
cubic feet per second (about a current 4-year flow). The 
200-year flood plain would be reduced by 1,500 acres with 
water surface reductions of between 2 and 5 feet. 
Preconstruction Engineering and Design (PED) was 
started in FY1988 to refine the project design recommended 
in the feasibility report. In FY 1990, refinement of project 
design to less costly gated spillway sluice and reevaluation of 
hydrology, existing local levees and embankments, estimated 
flood damages, and potential flood reduction benefits were 
completed. Studies determined that the Skookumchuck 
Dam modification was no longer economically justifiable and 
thus lacked Federal interest. However, structural and non- 
- 38-12 -

SEATTLE, WASHINGTON DISTRICT 
structural alternatives appeared to be economically justified. 
Since these potential projects were small enough, it was determined 
that further work should be pursued under the 
small flood control project program and that deauthorization 
of the Skookumchuck Dam modification should be recommended. 
Accomplishments during the fiscal year included completion 
of a letter report which recommended deauthorization, 
and completion of a wrap-up report which presented results 
of the technical analyses that had been completed at the time 
work was terminated. The report was provided to the local 
sponsor. Fiscal year costs were $16,692. Total costs to date 
have been $1,538,347. 
Chehalis River at South Aberdeen and Cosmopolis, WA 
The cities of Aberdeen and Cosmopolis are located at the 
mouth of the Chehalis River in Grays Harbor County. The 
Chehalis River, about 125 miles in length, rises in the Willapa 
Hills in west central Washington. 
Preconstruction Engineering and Design (PED) was 
started in FY 1984. General Design Memorandum studies 
resulted in design changes providing a significant reduction in 
project costs while retaining essentially the same flood damage 
reduction benefits. The plan of improvement, authorized 
in P.L. 99-662, as refined by the General Design Memorandum, 
would protect most of the left bank flood plain at the 
mouth of the Chehalis River in the cities of Aberdeen and 
Cosmopolis. The improvement would include segments of 
earthen embankment levee (2.2 miles) and steel sheetpile 
floodwall (0.9 mile), joining areas of high ground (1.1 miles). 
The project roughly follows the left bank of the Chehalis 
River from Devonshire Slough to Cosmopolis. The levee 
would protect 1,176 acres of the cities from inundation by the 
standard project flood. 
Accomplishments during the fiscal year included initiation 
of work on plans and specifications following completion of 
higher authority review of the General Design Memorandum 
and EISS and passage of a bond issue to fund the local share 
of project costs by the local sponsor. Estimated PED cost is 
$2,555,000. Fiscal year costs were $392,502. Total costs to 
date have been $1,869,535. 
La Conner, WA 
The town of La Conner is located on the eastern bank of 
Swinomish Slough, about 64 miles north of Seattle, WA. The 
La Conner Historical District is suffering from bank erosion 
and deterioration of wood pilings supporting overwater 
buildings. Erosion control and repair or replacement of the 
damaged pilings are required to maintain the structural integrity 
of the overwater buildings and prevent loss of the 
historic area. 
Construction of streambank erosion control measures necessary 
to prevent damages to structures in the La Conner 
Historical District was authorized by Section 603f, P.L. 
99-662 of the 1986 Water Resources Development Act, subject 
to the Secretary of the Army determining such work to be 
economically justified and environmentally acceptable. The 
improvement, as recommended in the Design Memorandum, 
involves placement of rock riprap along 1,660 feet of the 
Swinomish Channel bank at the La Conner Historical District, 
plus repair of about 200 piles using concrete jackets. 
Preconstruction Engineering and Design (PED) was 
started in FY 1991 to resolve environmental concerns raised 
during review of the 1989 Decision Document, primarily 
regarding project impacts on juvenile salmonids. The Draft 
Design Memorandum and Environmental Assessment for 
the project was submitted in 1991. The project design was 
modified to include benches in the rock slope to assist fish 
passage as well as creation of a strip marsh along a portion of 
the project. 
Accomplishments during the fiscal year included continuation 
of work on the final Design Memorandum and Environmental 
Assessment, and continuing coordination with the 
local sponsor on his financial plan and obligations. Estimated 
PED cost is $183,000. Fiscal year costs were $47,209. Total 
costs to date have been $135,308. 
Other Preconstruction Engineering and Design 
Projects 
Blair and Sitcum Waterways, Tacoma Harbor, WA 
Total costs to date have been $1,310,000, including 
$300,000 appropriated and expended under Section 101(c). 
For last full report see Annual Report for FY 1989. 
East, West and Duwamish Waterways, Seattle Harbor, WA 
Total costs to date have been $663,000. Project has been 
deferred. For last full report see Annual Report for FY 1988. 
Grays Harbor, Chehalis and Hoquiam Rivers, WA 
Total costs to date have been $5,670,000, $3,530,000 of 
which is now included in Cost and Financial Statement of this 
report. Project improvement by construction commenced in 
FY 1990. For last full report see Annual Report for FY 1989. 
Yakima River at Union Gap, WA 
Total costs to date have been $502,000. Project has been 
deferred. For last full report see Annual Report for FY 1988. 
- 38-13 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY91 FY 92 Sep.30, 1992 
1. Anacortes Harbor, New Work 
WA (Federal Funds) 
(Contrib. Funds) 
2. Bellingham Harbor, 
WA (Federal Funds) 
(Contrib. Funds) 
3. Ediz Hook, WA 
(Federal Funds) 
(Contrib. Funds) 
4. Everett Harbor and 
Snohomish River, 
WA (Federal Funds) 
(Contrib. Funds) 
5. Friday Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work. 
Contrib. 
Cost 
Maint 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
-5000 
7,472 
- 260 
- 286 
7,000 
6,482 
222,345 
222,3451 
1,156,499 
1,155,980 
59,524 
59,524 
5,000 
5,000 
- 1,566,839 
- 1,566,8392 
13,000 129,887 193,300 
12,859 35,927 282,485 
7,000 
16,773 
- 334,000 
2,873 330,850 
- 1,362 -1,362 
617,000 
432,040 
35,1 
5, 
31,800 
29,272 -1, 
970,600 480,129 708,500 816, 
1,083,617 486,811 606,592 669, 
13,800 15,152 
13,649 14,749 
- 45,1 
- 32,E 
2,273,256 
2,083,3703 
29,421 
29,421 
9,103 
9,103 
- 5,878,740 
- 5,878,740 
000 1,531,860 
182 1,498,404 
- 385,850 
- 385,850 
- 163,765 
831 159,388 
- 1,723,745 
- 1,723,7454 
000 11,439,807 
147 11,190,9676 
- 116,618 
- 116,618 
- 584,090 
584,090 
- 1,575,500 
- 1,575,5006 
000 73,952 
643 61,041 
- 1,267,881 
- 1,267,881 
- 38-14 -

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY91 FY 92 Sep.30, 1992 
6. Grays Harbor and 
Chehalis River, WA 
(Federal Funds) 
(Contrib. Funds) 
7. Kenmore Navigation 
Channel, WA 
8. Lake Crockett, WA 
9. Lake Washington 
Ship Canal, WA 
(Federal Funds) 
(Contrib. Funds) 
11. Olympia Harbor, WA 
13. Puget Sound and its 
Tributary Waters, WA 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
- 14,030,000 
- 10,551,615 
2,941,480 3,041,014 
2,889,250 3,045,373 
3,198,291 
5,156,476 
5,092,707 
2,318,000 21,467,962 
1,622,158 20,492,0248 
7,754,000 103,249,341 
7,802,000 103,180,7939 
-- 9,592 
- 9,59210 
- 4,606,145 
- 4,606,145 
-- 4,561,000 396,000 571,000 
- 3,753,379 1,202,468 502,831 
- 
344 
344 
-6,800 
134 
- 7,500 
- 7,371 
7,000 
6,000 
69,614 
15,674 
5,528,000 
5,458,67911 
55,889 
55,889 
946,000 
946,000 
444,344 
443,344 
377,990 
377,99012 
774,754 
720,684 
- - - - 4,611,436 
- - - - 4,611,43613 
4,715,000 4,353,835 7,239,400 6,393,000 93,652,095 
4,627,269 4,398,158 7,220,250 6,135,650 93,119,566'4 
-- -- - - 7,465,230 
- -- - - 7,465,230 
-- -- - - 250,000 
- - - - 250,000 
2,133 
- 9,400 
-- 9,397 
10,400 
6,633 
560,000 590,928 695,520 890,000 
548,423 580,994 697,751 857,511 
337,709 
337,709 '5 
759,177 
755,37118 
43,337 
43,337 
20,310,750 
20,247,527' 7 
- 38-15 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY91 FY 92 Sep.30, 1992 
14. Quillayute River, WA New Work 
(Federal Funds) 
(Contrib. Funds) 
15. Seattle Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
16. Swinomish Channel, WA 
(Federal Funds) 
(Contrib. Funds) 
17. Tacoma Harbor, WA 
(Federal Funds) 
(Contrib. Funds) 
18. Willapa River and Harbor 
and Naselle River, WA 
(Federal Funds) 
(Contrib. Funds) 
19. Lincoln Park Beach, 
Seattle, WA 
(Federal Funds) 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
902,000 
901,651 
- 525,236 
402 524,627 -325 
144,900 647,227 237,000 681,000 
108,357 685,066 231,022 684,210 
- - - 41,595 
- - - 41,595 
83,100 206,820 331,700 
91,253 81,218 459,582 
- 88,071 
- 88,015 
- - 
- - 
361,100 2,300 
354,726 5,863 
177,000 
358,921 57,411 
52,400 
51,522 
160,600 
163,948 
-18,891 
34,412 
34,450 
521,850 
521,850'* 
11,019,308 
11,018,351 
20,000 
20,000 
170,335 
170,335 
9,356,873 
9,350,330 
69,333 
69,333 
61,595 
61,595 
808,332 
808,332' 
7,422,972 
7,422,926 
32,000 
32,000 
- 2,383,891 
- 2,383,89120 
5,934 1,537,150 
6,868 1,537,14921 
- 1,147,208 
- 1,147,208 
- 222,500 
- 222,500 
- 1,386,955 
- 1,386,95522 
52,640 13,854,736 
48,240 13,850,21823 
- 78,372 
- 78,372 
17,724 
722,500 
720,754 
- 38-16 -

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY91 FY 92 Sep.30, 1992 
(Contrib. Funds) 
21. Howard A. Hanson 
Dam, WA 
(Federal Funds) 
(Contrib. Funds) 
23. Lower Green River, 
King County, WA 
(Federal Funds) 
(Contrib. Funds) 
24. Mud Mountain 
Dam, WA 
(Federal Funds) 
(Contrib. Funds) 
26. Stillaguamish River, WA 
(Federal Funds) 
(Contrib. Funds) 
27. Tacoma, Puyallup River, 
WA 
(Federal Funds) 
(Contrib. Funds) 
28. Wynoochee Lake,WA 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Minor Rehab. 
Approp. 
Cost 
Major Rehab. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
New Work 
Approp. 
Cost 
Maint 
Approp. 
Cost 
199,303 42,036 
-26 
15,170 
269,474 
269,474 
- - - - 37,048,061 
- - - - 37,048,061 
713,000 685,628 720,900 842,000 14,026,329 
597,463 788,180 645,685 717,555 13,806,81424 
- - - - 2,000,000 
- -- - - 2,000,000 
-- 204,000 430,000 
15,462 176,250 61,009 
- - 84,250 
1,420,000 
1,429,669 
965,000 
990,238 
4,223,000 
3,343,165 
1,066,322 
1,141,473 
10,800,000 
11,550,063 
1,247,200 
1,175,095 
240,000 
634,574 
43,750 
107,067 
6,913,000 
6,841,950 
1,384,000 
1,390,453 
13,400,000 13,743,500 1,000,000 274,000 
13,366,684 13,311,323 1,343,118 409,294 
97,600 86,177 283,900 317,000 
38,459 149,583 276,385 325,245 
30,000 35,986 
29,686 33,919 
- 843 
1,646,000 1,378,902 
1,615,314 1,264,215 
21,600 
22,000 
921,500 
919,328 
128,000 
107,067 
41,439,84825 
41,214,47526 
25,124,997 
25,026,82027 
285,908 
285,908 
30,437,500 
30,425,032 
3,928 
3,928 
134,595 
134,595" 
2,559,524 
2,559,165 
21,000 
21,000 
- 3,947,853 
- 3,947,853" 
33,000 702,367 
35,646 702,107 
- 54,405 
- 7,007 
- - 23,494,445 
-- - 23,494,44530 
72,000 369,000 17,052,348 
253,823 275,940 16,957,81431 
- 38-17 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-A COST AND FINANCIAL STATEMENT 
(Continued) 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY91 FY 92 Sep.30, 1992 
29. Albeni Falls Dam, ID New Work 
Approp. - - - - 31,741,561 
Cost - - - - 31,741,5612 
Maint. 
Approp. 3,524,200 3,921,663 3,319,700 3,728,000 49,188,769 
Cost 3,448,526 3,970,757 3,294,401 3,642,283 48,995,404M 
30. Chief Joseph Dam- New Work 
Rufus Woods Lake, WA Approp. 4,370,000 9,701,000 3,400,000 1,570,000 536,419,235" 
Cost 4,344,812 8,576,556 3,857,685 2,031,600 536,176,357" 
Maint. 
Approp. 9,134,400 9,479,470 9,947,156 10,009,000 126,508,538 
Cost 8,840,800 9,670,106 9,872,186 10,010,518 126,184,872* 
Major Rehab. 
Approp. - - - - 297,630 
Cost - - - - 297,630 
31. Libby Dam - Lake New Work 
Koocanusa,MT Approp. - -- - - 543,858,440 
(Federal Funds) Cost 791 312 1,089 60 543,858,440 
Maint. 
Approp. 4,084,000 4,081,223 3,851,200 4,405,000 49,327,002 
Cost 4,100,378 3,999,702 3,851,003 4,318,921 49,029,3553 
(Contrib. Funds) New Work 
Contrib. - - - - 1,458,252 
Cost - - - - 1,458,252" 
1. Excludes $2,000 Coast Guard funds expended. 
2. Includes $56,582 appropriated and expended for previous 
project. Excludes $13,000 Coast Guard funds expended. 
3. Includes $1,092 appropriated and expended for previous project. 
4. Includes $418,209 appropriated and expended for previous 
project. Excludes $43,000 Coast Guard funds expended. 
5. Includes $5,869 appropriated and expended for previous project. 
6. Includes $1,180,500 expended under Productive Employment 
Appropriation Act of 1983 (P.L98-8). 
7. Includes $3,530,000 appropriated for Preconstruction 
Engineering and Design, $124,945 for recreation facilities at 
completed project (Code 710) and $113,134 for previous project. 
Excludes $161,909 Navy funds and $6,000 Coast Guard funds. 
8. Includes $3,529,998 expended for Preconstruction Engineering 
and Design, $124,945 for recreation facilities at completed project 
(Code 710) and $113,134 for previous project. Excludes $161,909 
Navy funds and $6,000 Coast Guard funds expended. 
9. Includes $37,415 appropriated and expended for previous 
projects. Excludes $409,660 Emergency Relief funds and $57,000 
Public Works Administration funds expended. 
10. Excludes $111,000 Public Works Acceleration Act funds 
expended. 
11. Excludes $3,418,000 contributed by Port of Grays Harbor in 
fulfilling requirements of local cooperation. 
12. Includes $117,750 appropriated and expended for recreation 
facilities at completed project (Code 710). 
13. Includes $779,655 for recreation facilities at completed project 
(Code 710), and $485,002 for previous project, appropriated and 
expended. Excludes $246,567 expended by State of Washington 
and $742,071 expended by King County. Excludes $192,516 Public 
Works Administration funds expended. 
14. Includes $1,631,195 (1916 to 1936) and $338,163 subsequently 
appropriated and expended under Maintenance and Operation of 
Dams and Other Improvements of Navigable Waters and $32,000 
expended under Productive Employment Appropriation Act of 
1983 (P.L 98-8). 
15. Includes $183,257 appropriated and expended for previous 
projects. Excludes $105,467 Public Works Administration funds 
expended. 
16. Includes $14,418 appropriated and expended for previous 
projects. 
17. Includes $64,996 appropriated and expended for previous 
project. 
18. Excludes Navy funds expended on dredging river channel in 
1944 and Coast Guard funds expended for channel dredging in 
1948 and 1949. 
19. Excludes $1,000 Coast Guard funds expended. 
20. Includes $159,585 appropriated and expended for previous 
project. Excludes $51,609 Public Works Administration funds 
expended. 
21. Includes $5,347 appropriated and expended for previous 
projects. 
22. Includes $228,084 appropriated and expended for previous 
projects. Excludes $40,000 Coast Guard funds and $192,314 
Emergency Relief funds expended. 
23. Includes $309,177 appropriated and expended for previous 
projects. Excludes $78,532 Public Works Administration funds 
expended. 
24. Includes $66,678 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters and $8,000 expended under Productive 
Employment Appropriation Act of 1983 (P.L 98-8). 
25. Includes $13,182,063 appropriated for original project, $87,785 
appropriated for recreation facilities at completed project (Code 
710) and $28,170,000 for Dam Safety Assurance. Excludes $26,000 
Emergency Relief funds. 
26. Includes $13,182,063 expended for original project,$87,785 
expended for recreation facilities at completed project (Code 710) 
and $27,944,627 for Dam Safety Assurance. Excludes $26,000 
Emergency Relief funds expended. 
27. Includes $198,578 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters and $378,162 expended under Productive 
Employment Appropriation Act of 1983 (P.L 98-8). 
- 38-18 -

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-A 
(Continued) 
COST AND FINANCIAL STATEMENT 
28. Excludes $281,000 Works Progress Administration funds and 
$85,999 Emergency Relief funds expended. 
29. Includes $5,035 appropriated and expended for recreation 
facilities at completed project (Code 710). 
30. Includes $102,200 appropriated and expended for recreation 
facilities at completed project (Code 710). 
31. Includes $66,678 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters and $27,000 expended under Productive 
Employment Appropriation Act of 1983 (P.L 98-8). 
32 Includes $971,947 appropriated and expended or recreation 
facilities at completed project (Code 710). Excludes $136,736 
Public Works Acceleration Act funds expended for recreation 
facilities at completed project (Code 710). 
33. Includes $174,776 Special Recreation Use Fees, appropriated 
and expended. Includes $739,920 appropriated and expended 
under Maintenance and Operation of Dams and Other 
Improvements of Navigable Waters and $188,475 expended under 
Productive Employment Appropriation Act of 1983 (P.L 98-8). 
34. Includes $144,338,252 appropriated for original project, 
$391,933,000 for additional units, and $147,983 for recreation 
facilities at completed project (Code 710). Excludes $58,000 Public 
Works Acceleration Act funds for recreation facilities at 
completed project (Code 710). 
35. Includes $144,338,252 expended for original project, 
$391,690,122 for additional units, and $147,983 for recreation 
facilities at completed project (Code 710). Excludes $58,000 Public 
Works Acceleration Act funds for recreation facilities at 
completed project (Code 710). 
36. Includes $774,561 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters and $530,000 expended under Productive 
Employment Appropriation Act of 1983 (P.L 98-8). 
37. Includes $484,753,143 appropriated and expended for original 
project, $42,221,634 for additional units, $16,276,363 for 
reregulating dam, $475,000 for power planning, and $132,300 for 
Kelley Flats Airport. 
38. Includes $987,224 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters and $219,900 expended under Productive 
Employment Appropriation Act of 1983 (P.L 98-8). 
39. Excludes $161,849 expended by Federal Aviation Agency, 
$32,000 expended by Lincoln County- City of Libby Joint Airport 
Board, $8,000 expended by Bonneville Power Administration, and 
$379,555 expended by U.S. Forest Service. 
- 38-19 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. ANACORTES HARBOR. WA 
3. 
5. 
Mar. 2, 1919 
Sep. 3, 1954 
July 14, 1960 
as amended 
June 25, 1910 
July 3, 1930 
Aug. 26, 1937 
Sep. 3, 1954 
July 14, 1960 
as amended 
July 3, 1958 
July 14, 1960 
as amended 
Mar. 7, 1974 
June 25, 1910 
July 3, 1930 
June 20, 1938 
Sep. 3, 1954 
July 14, 1960 
July 14, 1960 
as amended 
June 3, 1896 
Mar. 2, 1907 
Mar. 2, 1907 
June 25, 1910 
June 25, 1910 
Aug. 8, 1917 
Jan. 21, 1927 
Aug. 30, 1935 
Aug. 30, 1935 
Channel in Capsante Waterway. 
Mooring basin. 
Navigation Channel. 
BELLINGHAM HARBOR, WA 
Whatcom Creek Waterway 26- and 18-foot channels. 
Entrance channel in Squalicum Creek Waterway. 
Maintenance of southerly half and westerly end of 
Squalicum Creek Basin. 
Small-boat basin adjacent to Squalicum Creek Waterway. 
Whatcom Creek Waterway, 30-foot channel. 
Channel 3,200 feet long, 100 feet wide, and 18 feet deep 
in I&J Street Waterway. 
EDIZ HOOK, WA 
Construction of 10,000 linear feet of rock revetment, 
together with initial beach replenishment and annual 
nourishment.Emergency interim measures necessary to 
prevent breaching of Ediz Hook prior to construction of 
authorized project. 
EVERETT HARBOR AND SNOHOMISH RIVER, WA 
Training dike 10,500 feet long extending across bar 
at outlet of old river channel. 
Raise 6,000 feet of training dike, extend spur dike, 
widen gap in dike as required, maintain East Waterway and 
channel to gap. 
Abandon project for Snohomish River and provide 
settling basin near 14th Street. 
Spur dike at Preston Point, remove training dike 
north of river outlet, enlarge channel to 14th Street, and 
deepen settling basin. 
Widen channel from settling basin to gap; extend 
channel to head of Steamboat Slough; and a settling basin 
within upper channel reach. 
FRIDAY HARBOR, WA 
Construction of 1,600 feet of concrete floating breakwater. 
GRAYS HARBOR AND CHEHALIS RIVER, WA 
South jetty. 
A north jetty 9,000 feet long. 
The 18-foot channel. 
Extend north jetty 7,000 feet; length of south jetty 
fixed at 13,734 feet. 
A 6-foot channel above Cosmopolis. 
Dredging in bar channel. 
Dredging in bar channel. 
Reconstruct north and south jetties to an elevation of 
16 feet above mean lower low water. 
Maintain 26-foot channel below Aberdeen (as authorized 
by Public Works Administration Dec. 11, 1933) 
and combining projects for Grays Harbor and bar entrance 
and Grays Harbor, inner portion, and Chehalis River under 
a modified project for Grays Harbor and Chehalis River. 
H. Doc. 1117, 64th Cong., 1st Sess. 
S. Doc. 102, 83rd Cong., 2d Sess. 
Sec. 107, P.L86-645. 
Authorized by Chief of Engineers 
Dec. 31, 1974. 
H. Doc. 1161, 60th Cong., 2d Sess. 
H. Doc. 187, 70th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 70, 74th Cong., 1st Sess. 
H. Doc. 558, 82d Cong., 2d Sess. 
Sec. 107, P.L 86-645. 
Authorized by Chief of Engineers 
Feb. 10, 1976. 
S. Doc. 46, 85th Cong., 1st Sess. 
Sec. 107, P.L 86-645. 
Authorized by Chief of Engineers 
May 5, 1965. 
H. Doc. 101, 93d Cong., 1st Sess., 
P.L 93-251 
H. Doc. 1108, 60th Cong., 2d Sess. 
H. Doc. 377, 71st Cong., 2d Sess. 
H. Doc. 546, 75th Cong., 3d Sess. 
H. Doc. 569, 81st Cong., 2d Sess. 
H. Doc. 348, 86th Cong., 2d Sess. 
Sec. 107, P.L 86-645. 
Authorized by Chief of Engineers 
July 9, 1981. 
Annual Report, 1895, pp. 3517-3533. 
Rivers and Harbors Committee 
Doc. 2, 59th Cong., 2d Sess. 
H. Doc. 507, 59th Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 29, 61st Cong., 2d Sess. 
H. Doc. 1125, 60th Cong., 2d Sess. 
H. Doc. 1729, 64th Cong., 2d Sess. 
H. Doc. 582, 69th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc.2, 74th Cong., 1st Sess. 
H. Doc. 53, 73rd Cong., 1st Sess.; 
Rivers and Harbors Committee 
Doc. 2, 74th Cong., 1st Sess. 
- 38-20 - 
TABLE 38-B

TABLE 38-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
Dec. 22, 1944 
as amended 
Mar. 2, 1945 
June 30, 1948 
Sep. 3, 1954 
Sep. 3, 1954 
July 14, 1960 
as amended 
Nov. 17, 1986 
July 14, 1960 
as amended 
Mar. 2, 1945 
Dec. 22, 1944 
as amended 
June 25, 1910 
Mar. 4, 1913 
Aug. 8, 1917 
Sep. 22, 1922 
June 26, 19341 
Aug. 30, 1935 2 
Dec. 22, 1944 
as amended 
July 24, 1956 
Jan. 21, 1927 
July 3, 1930 
Aug. 30, 1935 
Aug. 26, 1937 
July 14, 1960 
as amended 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized Documents 
Construction, operation, and maintenance of recreation Sec. 4, Flood Control Act of 1944 
facilities. 
Maintain 30-foot depth in channel from deep water in Report in Office, Chief of Engineers 
Grays Harbor to Port of Grays Harbor Commission terminal 
which was deepened from 26 to 30 feet with Navy funds. 
Breakwater at Westhaven; H. Doc. 635, 80th Cong., 2d Sess. 
protection of Point Chehalis; and maintenance of 
Westhaven entrance channel. 
Dredging and maintenance of a 30-foot channel and H. Doc. 412, 83d Cong., 2d Sess. 
turning basin from Aberdeen to Cosmopolis. 
Additional breakwater, 1,400 feet long, at Westhaven Cove. H. Doc. 30, 84th Cong., 1st Sess. 
Westhaven Cove small boat basin. Sec. 107, P.L86-645. 
Authorized by Chief of Engineers, 
Feb. 7, 1979. 
Improve project features with accompanying fish mitigation. P.L. 99-662 
Modify existing railroad bridge. 
KENMORE NAVIGATION CHANNEL, WA 
Construction of navigtion channel 15 feet deep consisting Sec. 107, P.L86-645. 
of a 100-foot-wide inner channel 900 feet long, an 800- Authorized by Chief of Engineers 
foot-long transition channel with 240 30-foot bend and Oct. 7, 1980. 
maximum width of 190 feet, and a 120-foot-wide outer 
channel 1,200 feet long. 
LAKE CROCKETT, WA 
Small-boat basin. H. Doc. 303, 77th Cong., 1st Sess. 
Construction, operation, and maintenance of Sec. 4, Flood Control Act of 1944 
recreation facilities. 
LAKE WASHINGTON SHIP CANAL, WA 
Provides for a double lock and fixed dam with gated H. Doc. 953, 60th Cong., 1st Sess. 
spillway and necessary accessory works at entrance to 
Salmon Bay; dredging a channel from locks to deep water 
in Puget Sound, and excavation by local interests of a channel 
from locks into Lake Washington. 
Dredging below locks and revetting canal banks. H. Doc. 800, 64th Cong., 1st Sess. 
Increased dimensions of channel between Puget Sound H. Doc. 324, 67th Cong., 2d Sess. 
and locks and a 600-foot extension of lower guide pier. 
Operating and care of locks and dam provided for with 
funds from War Department appropriations for Rivers and 
Harbors. 
Enlarge channel between locks and Lake Washington. H. Doc. 140, 72d Cong., 1st Sess. 
Construction, operation, and maintenance of Sec. 4, Flood Control Act of 1944 
recreation facilities. 
Government Locks to be known as P.L 84-779 
Hiram M. Chittenden Locks. 
OLYMPIA HARBOR, WA 
Channel 22-feet deep and 150-feet wide. H. Doc. 244, 69th Cong. 1st Sess. 
Increase channel to 26-foot depth on east side of harbor. Rivers and Harbors Committee 
Doc. 5, 71st Cong., 1st Sess. 
Elimination from project of 12-foot channel on east Rivers and Harbors Committee 
and west sides of harbor, and for a channel 30 feet deep Doc. 21, 73rd Cong., 2d Sess. 
and 300 feet wide between Budd Inlet and port terminal, 
with turning basin of same depth. 
Widen outer portion of channel to 500 feet, and Rivers and Harbors Committee 
widen entrance to turning basin. Doc. 75, 74th Cong., 2d Sess. 
656-foot concrete floating floating breakwater and dredging Sec. 107, P.L86-645. 
of entrance and access channels and turning basin. Authorized byChief of Engineers 
May 13, 1981. 
- 38-21 - 
8. 
11.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
PUGET SOUND AND ITS TRIBUTARY WATERS, WA 
Maintenance of the rivers tributary to Puget Sound by 
snagging and dredging; and removal of floating debris from 
Seattle Harbor. 
Annual Report for 1893, page 3425 
QUILLAYUTE RIVER, WA 
Jetty (5 feet high) on easterly side of mouth, and a H. Doc. 125, 71st Cong., 1st Sess. 
dike on westerly side, to stabilize entrance. 
Maintenance dredging to provide a channel 6 feet H. Doc. 218, 78th Cong., 1st Sess 
deep and of suitable width from ocean to within river mouth. 
Raising jetty to 15 feet; channel 10 by 100 feet, 2,000 feet H. Doc. 579, 81st Cong., 2d Sess 
long; moorage basin.3 
SEATTLE HARBOR, WA 
Maintenance of East and West Waterways 750 feet wide S. Doc. 313, 65th Cong., 3d Sess. 
and 34 feet deep, and of Duwamish Waterway 20 feet deep 
and 150 feet wide as far south as Eighth Avenue South Bridge. 
Enlargement of Duwamish Waterway. H. Doc. 108, 68th Cong., 1st Sess. 
H. Doc. 126, 71st Cong., 2d Sess. 
Maintenance of East Waterway between 750-foot section H. Doc. 211, 72d Cong., 1st Sess. 
and Spokane Street, and turning basin at junction of East 
and Duwamish Waterways. 
July 13, 1892 
Aug. 30, 1935 
Oct. 23, 1962 
June 13, 1902 
July 3, 1930 
Aug. 26, 1937 
Aug. 30, 1935 
Sep. 3, 1954 
Oct 23, 1962 
July 27, 1916 
Aug. 30, 19352 
Aug. 30, 19354 
Mar. 2, 1945 
Sep. 3, 1954 
Oct. 23, 1962 
as amended 
May 17, 1950 
Aug. 6, 1958 
SWINOMISH CHANNEL, WA 
Channel 4 feet deep and 100 feet wide, and dike 
construction. 
Enlargement of channel to present project dimensions. 
Removal of navigation hazards at "Hole-in-the-Wall". 
TACOMA HARBOR, WA 
City Waterway 
Hylebos Waterway 
Training walls at mouth of Puyallup River (previously 
authorized by Public Works Administration Sep. 6, 1933) 
Blair Waterway extension. 
Blair and Hylebos Waterways extension. 
WILLAPA RIVER AND HARBOR AND NASELLE RIVER, 
Channel 24 feet deep, 200 feet wide, in Willapa River, 
and 150 feet wide in the forks. 
Maintenance of channel over bar to a depth of 26 feet 
and minimum width of 500 feet. 
For cutoff channel at Narrows. 
Channel from deep water in Palix River to BayCenter dock. 
Widen Willapa River channel to 360 and 250 feet between 
South Bend and the forks; Tokeland and Nahcotta basins; 
and Naselle River clearance. 
LINCOLN PARK BEACH, SEATTLE, WA 
250-foot rock revetment and 2,550 feet of sand and 
gravel nourishment. Periodic monitoring and replenishing 
beach nourishment. 
HOWARD A. HANSON DAM, WA 
Eagle Gorge flood control dam on Green River. 
Redesignation of project as Howard A. Hanson Dam. 
H. Doc. 31, 52d Cong., 1st Sess. and 
Annual Report for 1892, p. 2752 
S. Committee Print, 73rd Cong., 
1st Sess. 
H. Doc. 499, 87th Cong., 2d Sess. 
H. Doc. 76, 56th Cong., 2d Sess. 
Rivers and Harbors Committee 
Does. 25, 71st Cong., 2d Sess., 
and 91, 74th Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 55, 72nd Cong.,2d Sess. 
H. Doc. 271, 84th Cong., 2d Sess. 
S. Doc. 101, 87th Cong., 2d Sess. 
WA 
H. Doc. 706, 63d Cong., 2d Sess. 
Rivers and Harbors Committee 
Doc. 41, 72d Cong., 1st Sess. 
Rivers and Harbors Committee 
Doc. 37, 73rd Cong., 2d Sess. 
H. Doc. 481, 76th Cong., 2d Sess. 
H. Doc. 425, 83d Cong., 2d Sess. 
Sec. 103, P.L 87-874. 
Authorized by Chief of Engineers 
Oct. 18, 1983 
H. Doc. 271, 81st Cong., 1st Sess. 
P.L 85-592 
- 38-22 - 
TABLE 38-B 
(Continued) 
13. 
July 13, 1892 
14. 
15. 
July 3, 1930 
Mar. 2, 1945 
Sep. 3, 1954 
Mar. 2, 1919 
Mar. 3, 1925 
July 3, 1930 
Aug. 30, 1935 
16. 
17. 
18. 
19. 
21. 
.

TABLE 38-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
24. 
SEATTLE, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
LOWER GREEN RIVER, KING COUNTY, WA 
Construct 3.5 miles of levees. 
MUD MOUNTAIN DAM, WA 
Flood control dam on White River. 
Construction, operation, and maintenance of 
recreation facilities. 
Documents 
Sec. 205, P.L80-858. 
Authorized by Chief of Engineers 
Sep. 12, 1991. 
S. Committee Print, 
Puyallup River, WA, 
74th Cong., 2d Sess. 
Sec. 4, Flood Control Act of 1944 
June 30, 1948 
as amended 
June 22, 1936 
Dec. 22, 1944 
as amended 
June 22, 1936 
June 28, 1938 
June 22, 1936 
Dec. 22, 1944 
as amended 
Oct. 23, 1962 
Dec. 22, 1944 
as amended 
Mar. 7, 1974 
Mar. 7, 1974 
Nov. 17, 1988 
May 17, 1950 
Dec 22, 1944 
as amended 
July 24, 1946 
June 30, 1948 
July 9, 1952 
Dec. 22, 1944 
as amended 
Oct. 22, 1976 
as amended on 
May 4, 1977 
WYNOOCHEE LAKE, WA 
Dam and reservoir for water supply, flood control, 
irrigation, fish and wildlife, and recreation. 
Construction, operation, and maintenance of 
recreation facilities. 
Transfer to State of Washington as a part of project costs, 
$696,000 for construction of fish hatchery facilities. 
Amend contract between city of Aberdeen and United 
States for use of storage space, permitting deferral of the 
major portion of the first 10-year payments. 
Transfer operation, maintenance, repair, and 
rehabilitation (OMR&R) to the city of Aberdeen, WA. 
ALBENI FALLS DAM, ID 
Multi-purpose dam with powerhouse. 
Construction, operation, and maintenance of 
recreation facilities. 
CHIEF JOSEPH DAM - RUFUS WOODS LAKE, WA 
Multi-purpose dam and powerhouse on Columbia 
River at Foster Creek. 
Redesignation of the project as Chief Joseph Dam. 
Designation of reservoir as Rufus Woods Lake. 
Construction, operation, and maintenance of 
recreation facilities. 
School facilities for education of dependents of 
construction personnel. 
H. Doc. 601, 87th Cong., 2d Sess. 
Sec. 4, Flood Control Act of 1944 
P.L 93-251 
P.L 93-251 
H. Doc. 1098, 100th Cong., 2d Sess. 
P.L 100-676 
S. Doc. 9, 81st Cong., 1st Sess. 
Sec. 4, Flood Control Act of 1944 
H. Doc. 693, 79th Cong., 2d Sess. 
P.L 858, 80th Cong., 2d Sess. 
P.L 469, 82d Cong., 2d sess. 
Sec. 4, Flood Control Act of 1944 
P.L 94-587 
P.L 95-26 
- 38-23 - 
23. 
STILLAGUAMISH RIVER, WA 
Improvement of flood channel by clearing and bank H. Doc. 657, 71st Cong., 3d Sess. 
revetment at 26 places; concrete weir at head of Cook Slough; 
and 2 cutoff channels in Cook Slough. 
Maintenance of improvements. P.L 75-761 
TACOMA, PUYALLUP RIVER, WA 
Channel improvement to protect people and industrial S. Committee Print, Puyallup River, 
section of city of Tacoma. WA, 74th Cong., 2d Sess. 
Construction, operation, and maintenance of Sec 4, Flood Control Act of 1944 
recreation facilities. 
26. 
27. 
28. 
29. 
30.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
31. 
May 17, 1950 
Nov. 7, 1966 
Jan. 2, 1968 
Aug. 13, 1968 
June 19, 1970 
Dec. 31, 1970 
Dec. 31, 1970 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Mar. 7, 1974 
Oct. 22, 1976 
Nov. 17, 1988 
LIBBY DAM - LAKE KOOCANUSA, MT 
Multi-purpose dam and powerhouse, and reregulating H. Doc. 531, 81 
facilities. 
School facilities for education of dependents of construction P.L 89-789 
personnel, Libby project. 
Airport facility at Kelley Flats, MT. P.L 90-2395 
Design standards for relocation of Montana State P.L 90-4836 
Highway 37 to be those adopted by State of Montana 
pursuant to provisions of Highway Safety Act of 1966. 
Participation with State of Montana in construction, P.L 91-2827 
operation and maintenance of fish hatchery facilities. 
Designation of lake formed by the waters impounded P.L. 91-625 
by Libby Dam as Lake Koocanusa. 
Design and construction of sewage collection and P.L 91-611 
sewage treatment facility as part of relocation of municipal 
facilities of Rexford, MT; and compensation for railroad 
employees suffering long-term economic injury through 
reduction of income as result of the relocation of rail 
transportation facilities due to the construction of Libby Dam. 
Phase I design memorandum stage for installation S. Doc. 29, 93d 
of power generating facilities at Libby Reregulating Dam. P.L 93-251 
Construction of fish production measures to P.L 93-251 
compensate for fish losses attributed to the project, and for 
acquisition of necessary real estate, construction of access 
roads and utilities (amends P.L 91-282 by increasing 
limitation from $750,000 to $4,000,000). 
Acquisition of land (not to exceed $2,000,000) for P.L 93-251 
prevention of wildlife grazing losses caused by the project. 
Reimbursement (not to exceed $350,000) to Boundary P.L 93-251 
County, ID, for reconstruction of Deep Creek Bridge made 
necessary by duration of high flows during drawdown 
operations at Libby Dam. 
Compensation (not to exceed $1,500,000) to Drainage P.L 93-251 
Districts and owners of leveed and unleveed lands in 
Kootenai Flats, Boundary County, ID, for damages caused 
by duration of higher flows during drawdown operations at 
Libby Dam. 
Amends P.L 93-251 by increasing limitation from $350,000 P.L 94-587 
to $380,000 for reimbursement to Boundary County, ID, for 
reconstruction of Deep Creek Bridge. 
Alleviate low water impact on existing facilities and protect H. Doc. 1098, 11 
Indian archeological sites exposed during course of P.L 100-676 
operations, at an estimated cost of $750,000. 
1. Permanent Appropriations Repeal Act. 
2. Included in Public Works Administration program. 
3. Maintenance of these items, as well as sandspit north of James 
Island, is included in this modification. 
4. Included in Emergency Relief program, May 28, 1935. 
5. Supplemental Appropriations Act of 1968, Section 502. 
6. Flood Control Act of 1968, Section 212. 
7. River Basin Monetary Authorization and Miscellaneous Civil 
Works Amendments Act of 1970, Section 7. 
- 38-24 - 
st Cong., 2d Sess. 
Cong., 1st Sess., 
00th Cong., 2d Sess.

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report Operation 
See Annual and 
PROJECT Status Report for Construction Maintenance 
Anacortes Navigation Channel, WA 1 Completed 1977 825,2635 - 
Bellingham Harbor, WA (I&J Street Waterway) 1 Completed 1966 125,6348 - 
Blaine Harbor, WA Completed 1958 346,650 - 
Columbia River, Wenatchee to Kettle Falls, WA Completed 1923 274,397 7,693 
East Bay Small Boat Basin, Olympia, WA1 Completed 1985 1,619,956- 
Edmonds Harbor, WA2 Completed 1987 - 224,756 
Flathead River, MT Completed 1901 9,811 - 
Hammersley Inlet, WA Completed 1950 9,000 10,683 
Hoquiam River, WA Completed 1950 18,921* 5,316 
Kingston Harbor, WA Completed 1967 262,5701� 5,0001' 
Kootenai River, ID and MT Completed 1933 9,255 5,643 
Mats Mats Bay, WA 1 Completed 1970 137,67912- 
Neah Bay, WA Completed 1982 2,057,266 1,854,058 
Okanogan and Pend Oreille Rivers, WA Abandoned 1913 63,879 7,634 
Poison Bay, Flathead Lake, MT Completed 1918 4,491 259 
Port Angeles Harbor, WA3 Completed 1960 470,873 - 
Port Gamble Harbor, WA Completed 1953 11,91113 13,337 
Port Orchard Bay, WA4 Completed 1928 42,804 - 
Port Townsend, WA Completed 1987 480,89914 78,787 
Prototype Breakwater Test Program, WA1 Completed 1985 1,461,590 - 
Shilshole Bay, Seattle, WA Completed 1962 2,575,09115- 
Skagit River, WA Completed 1950 102,3301' 36,258 
Squalicum Small Boat Harbor, Bellingham, WA ' Completed 1981 1,744,02517 - 
Waterway Connecting Port Townsend 
and Oak Bay, WA Completed 1987 73,322 378,378 
Westhaven Cove Small Boat Basin, WA1 Completed 1981 2,000,00018 - 
1. Authorized by Chief of Engineers under authority of Section 
107, Public Law 86-645. 
2. Constructed by local interests at a cost of $415,000. Excludes 
$1,000 Coast Guard funds expended for new work. Corps of 
Engineers is responsible for maintenance. 
3. Maintenance by Port of Port Angeles. 
4. No maintenance required. 
5. Excludes $457,200 contributed funds expended. 
6. Excludes $2,500 Coast Guard funds expended. 
7. Includes $8,005 appropriated and expended for previous project. 
8. Excludes $2,184,766 contributed funds expended. 
9. Excludes $32,373 Emergency Relief funds expended. 
10. Excludes $390,753 contributed funds and $3,000 Coast Guard 
funds expended. 
11. Mitigation of shore damages study. 
12. Excludes $28,288 contributed funds and $9,000 Coast Guard 
funds expended. 
13. Excludes $21,260 contributed funds expended. 
14. Excludes $92,423 contributed funds expended. 
15. Excludes $15,000 Coast Guard funds expended. 
16. Includes $2,500 appropriated and expended for previous 
project. 
17. Excludes $1,570,886 contributed funds expended. 
18. Excludes $1,230,035 contributed funds expended. 
- 38-25 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual Contributed 
Project Status Report for Construction Funds 
American Lake, Vicinity of Fort Lewis, WA1 Completed 1957 59,582 10,000 
Bear Creek, Flathead CountyBridge, near Essex, MT2 Completed 1971 1,424 - 
Bitterroot River, Florence, MT2 Completed 1990 180,950 49,759 
Blackfoot River, Matt Little Road, MT2 Completed 1964 17,836 - 
Bogachiel River, Highway 101, near Forks, WA2 Completed 1981 156,000 - 
Bogachiel River, Undie Road, Forks, WA2 Completed 1981 57,000 - 
Cedar River, King County, WA3 Completed 1953 3,229 
Cedar River, Renton, WA2 Completed 1949 32,264 
Chehalis River, City of ChehalisRaw Water 
Pumphouse, WA2 Completed 1966 35,454 
Chehalis River, Independence Road, 
Thurston County, WA2 Completed 1965 47,916 
Chehalis River, Montesano, WA2 Completed 1977 140,080 
Clallam Bay, Sekiu, WA2 Completed 1977 48,698 
Clallam County, WA (Various Locations)" Completed 1936 67,835 17,700 
Clallam River, Highway 112, WA2 Completed 1981 43,500 - 
Clark Fork River, Drummond, MT2 Completed 1978 18,660 
Clark Fork River, Missoula, MT2 Completed 1978 31,548 
Clark Fork River, Superior, MT2 Completed 1971 28,357 
Clark Fork River, Vicinity of Plains, MT2 Completed 1950 27,947 
Clearwater River, Jefferson County Road, WA2 Completed 1968 50,000 24,728 
Clearwater River, Queets River Bridge, WA2 Completed 1950 49,165 
Coeur d'Alene, Spokane River, ID Completed 1941 152,872 
Coeur d'Alene River, Springston, ID2 Completed 1950 25,452 - 
Coffee Creek, WA3 Completed 1966 15,000 
Columbia River Basin, Local Protection Projects, 
ID, MT, and WA: 
Clark Fork River, Missoula, MT Completed 1983 384,8628 13,500 
Lightning Creek, Clark Fork, ID Completed 1959 42,726 
Deschutes River, Gleason Road Bridge 
near Tumwater, WA2 Completed 1965 26,292 
Deschutes River, Rich Road Bridge, 
near East Olympia, WA2 Completed 1967 22,956 - 
Dungeness River, Area #5, WA2 Completed 1950 2,155 2,155 
Dungeness River, Area #8, WA2 Completed 1950 2,895 2,895 
Dungeness River, Clallam County, WA1 Completed 1964 52,040- 
Dungeness River, Sequim, WA2 Completed 1981 99,000 
Dungeness River, Clallam County, WA2 Completed 1986 47,500 
Dungeness River, Taylor Cut-off Road, WA2 Completed 1961 14,093 3,314 
Elwha Klallam Reservation, Elwha River, WA1 Completed 1991 1,455,023 119,449 
Elwha River, Clallam County, WA2 Completed 1951 17,303 
Entiat River, WA3 Completed 1971 49,300 
Entiat River, Chelan County, WA2 Completed 1978 38,000 
Flathead River, MT2 Completed 1972 20,940 
Flathead River, Bradley Channel Area, MT2 Completed 1955 26,265 
Flathead River, near Kalispell, MT2 Completed 1948 33,347 
Flathead River, near Kalispell, MT Deferred 1981 300,000. 
Flathead River, Old Steel Bridge, near Kalispell, MT2 Completed 1964 13,438 
Flower and Parmenter Creeks, MT 3 Completed 1950 2,320 
Foster Creek, West Fork, WA 2 Completed 1958 19,513 
Foster Creek Road, Douglas County, WA2 Completed 1962 50,000 
Grays Harbor County, WA (Various Locations) 4 Completed 1936 297,020 24,059 
Green River between Kent and Auburn, WA 
and Allentown, WA2 Completed 1972 24,605 
Green River, State Highway 181, WA2 Completed 1976 27,001 
Henderson Bay, Purdy, WA2 Completed 1977 37,359 
Hoh River, County Road 216, WA2 Completed 1980 143,000 
- 38-26 -

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to Sep. 30. 1992 
Full Report 
See Annual Contributed 
Project Status Report for Construction Funds 
Hoh River, U.S. Highway 101, WA2 Completed 1980 194,000 - 
Hoh River Road, Jefferson County, WA (HO 1360)2 Completed 1956 22,082 21,807 
Hoh River Road, Jefferson County, WA (HO 1361)2 Completed 1961 11,916 - 
Hoh River Road, Jefferson County, WA (HO 1362)2 Completed 1964 41,622 - 
Hoh River, near Forks, WA2 Completed 1983 173,000� - 
Hoko River, Sekiu, WA2 Completed 1977 21,083 - 
Hood Canal, Hoodsport, WA2 Completed 1977 59,812 - 
Hoquiam River, WA2 Completed 1977 52,600 - 
Jackman Creek, Skagit River, WA 3 Completed 1962 24,000 - 
Jefferson County, WA (Various Locations) 4 Completed 1936 58,996 8,411 
King County, WA (Various Locations) 4 Completed 1936 335,947 173,073 
Kootenai River, Bonners Ferry, ID2 Completed 1950 42,325 - 
Kootenai River, Kootenai Flats Area, District #1, ID2 Completed 1965 14,885 - 
La Conner, Swinomish Channel, WA2 Completed 1979 40,525 - 
Mason County, WA (Various Locations) 4 Completed 1936 36,642 1,407 
Methow River, WA (MET 1-74)2 Completed 1974 15,700 - 
Methow River, WA (MET 2-74)2 Completed 1974 11,200 - 
Methow River, WA (MET 3-74)2 Completed 1974 13,450 - 
Methow River, Barclay Canal, WA2 Completed 1976 19,810 - 
Methow River, State Highway No. 16 Bridge, 
Twisp, WA2 Completed 1949 31,783 
Methow River, Twisp-Carlton Highway, 
Vicinity of Twisp, WA2 Completed 1951 33,300 6,786 
Methow River, Vicinity of Pateros, WA2 Completed 1951 11,726 11,726 
Mineral Creek, Lewis County, WA2 Completed 1972 11,836 - 
Missoula, MT (Sewage Treatment Plant) 2 Completed 1965 50,000 5,339 
Moclips River, Moclips, WA2 Completed 1977 17,608 - 
Naches River, Naches, WA2 Completed 1982 59,000 - 
Neah Bay, Clallam County, WA2 Completed 1991 253,995 78,433 
Newaukum River, Lewis County, Hamilton, WA2 Completed 1972 24,792 - 
Nisqually River, near Elbe, WA2 Completed 1948 37,636 - 
Nisqually River, Thurston County, WA2 Completed 1960 26,790 - 
Nisqually River, Vicinity of Elbe, WA2 Completed 1952 19,345 - 
Nooksack River, WA3 Completed 1948 24,006 - 
Nooksack River, Acme, WA2 Completed 1985 77,300 - 
Nooksack River, Guide Bridge Location, WA2 Completed 1950 6,075 6,075 
Nooksack River, Middle Fork,Deming, WA2 Completed 1986 79,000 - 
Nooksack River, above Highway 1Z Bridge, WA2 Completed 1960 10,807 - 
Okanogan River, WA2 Completed 1974 10,100 - 
Okanogan River at Outlet of Osoyoos Lake, WA3 Completed 1949 52,100 - 
Okanogan River, Tonasket Creek and 
Osoyoos Lake, WA3 Completed 1953 7.987 - 
Okanogan River, Omak, WA1 Completed 1981 2,231,030 - 
Okanogan River, Oroville, WA1 Completed 1982 1,787,630 - 
Pierce County, WA (Various Locations) 4 Completed 1936 153,417 21,943 
Pilchuck River, WA3 Completed 1948 25,401 
Pilchuck River, WA2 Completed 1985 81,000 - 
Pilchuck River, WA2 Completed 1971 10,713 - 
Pilchuck River, Everett, WA2 Completed 1980 54,000 - 
Pilchuck River, State Highway 92, Granite Falls, WA2 Completed 1971 30,973 - 
Placer Creek, ID Completed 1986 5,865,000 - 
Powell County High School, Deer Lodge, MT2 Completed 1964 11,291 - 
Puyallup River, WA Completed 1937 50,00010 
Pysht River, Sekiu, WA2 Completed 1977 86,160 - 
Queets River, Jefferson County Sewage Lagoon, WA2 Completed 1981 125,000 - 
- 38-27 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-E OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
(Continued) 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual Contributed 
Project Status Report for Construction Funds 
Quillayute River, Quileute Tribal Float 
and Bridge, WA2 Completed 1972 39,300 - 
Quinalt River, Grays Harbor, WA2 Completed 1981 208,000 - 
Quinalt River Road, Jefferson County, WA2 Completed 1961 15,928 4,843 
Rock Creek, Granite County, MT2 Completed 1974 49,657 - 
Rock Creek, Missoula County, MT2 Completed 1973 31,565 - 
Rock Creek Road, MT2 Completed 1980 50,000 
Rye Creek, MT2 Completed 1973 22,819 - 
St. Maries, St. Joe River, ID Completed 1942 357,698 
St. Regis River, MT 3 Completed 1942 7,234 - 
St. Regis River at St. Regis, MT 3 Completed 1951 2,983 - 
Sammamish River, WA Completed 1967 2,582,53612 696,923 
Sauk River, WA2 Completed 1974 20,860 - 
Sauk River, Skagit County, WA2 Completed 1989 119,60024 32,778 
Shelton Creek, WA1 Completed 1979 872,021 - 
Skagit County, WA (Various Locations) 4 Completed 1936 390,150 44,966 
Skagit River, WA (Levee and Channel Improvements) Inactive 1982 1,934,792 
Skagit River at Burlington Bend, WA2 Completed 1949 50,000 - 
Skagit River, Cape Horn Road, WA2 Completed 1966 46,489 - 
Skagit River, Deadman's Slough, WA2 Completed 1980 93,000 - 
Skagit River, Pressentin Creek, WA2 Completed 1980 137,000 - 
Skagit River, South Skagit Highway, WA2 Completed 1963 40,753 - 
Skagit River, South Skagit Highway, WA (Job 66-1)2 Completed 1966 17,719 - 
Skagit River, South Skagit Highway, WA (Job 67-1)2 Completed 1967 50,000 24,488 
Skykomish River, North Fork, Index, WA2 Completed 1981 222,500 - 
Snohomish County, WA (Various Locations)' Completed 1936 1,160,311 191,262 
Snohomish River, Lowell-Snohomish River 
Road, WA2 Completed 1969 44,227 - 
Snohomish River, Snohomish, WA2 Completed 1970 60,900 14,307 
Snoqualmie River, West Snoqualmie, WA2 Completed 1977 15,565 - 
Soleduck River Bridge, WA2 Completed 1961 16,437 1,960 
Soleduck River, near Mora Road Bridge, WA2 Completed 1963 11,433 
Spokane River, Spokane, WA 2 Completed 1989 122,138 79,311 
Startup, Skykomish and Wallace Rivers, WA1 Completed 1970 271,713 - 
Stillaguamish River, South Fork, Mountain 
Loop Highway, near Robe, WA2 Completed 1964 50,000 46,182 
Stillwater River, MT2 Completed 1973 17,457 
Stillwater and Whitefish Rivers, MT2 Completed 1977 34,513 
Strong Creek, Hope, ID2 Completed 1970 8,442 
Tahola, WA2 Completed 1979 223,893 
Thurston County, WA (Various Locations) 4 Completed 1936 62,943 425 
Upper Puyallup River, WA5 Completed 1938 71,495'3 13,704 
Whatcom County, WA (Nooksack River) 4 Completed 1936 298,942 72,124 
Willapa River at Raymond, WA Inactive 1982 508,130' - 
Wynoochee River, County Road 141, WA2 Completed 1976 111,072 
Wynoochee River, near Montesano, WA2 Completed 1969 50,000 21,311 
Wynoochee River, near Montesano, WA (WR-1-722 Completed 1972 50,000'5 - 
Yakima County, WA (Yakima River) 4 Completed 1936 84,303 13,132 
Yakima, Yakima River, WA Completed 1948 381,961 - 
Yakima River, Cle Elum, WA2 Completed 1949 8,047 - 
Yakima River, below mouth of Teanaway River, 
near Cle Elum, WA2 Completed 1947 48,272 - 
Yakima River, West Richland, WA2 Completed 1977 36,768 - 
Yakima River, Yakima WA2 Completed 1983 125,500'8 
- 38-28 -

SEATTLE, WASHINGTON DISTRICT 
TABLE 38-E 
(Continued) 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report 
See Annual 
Project Status Report for Construction Maintenance 
1. Authorized by Chief of Engineers under authority of Section 
205, Public Law 858, 80th Congress, as amended. 
2. Authorized by Chief of Engineers under authority of Section 
14, Public Law 526, 79th Congress, as amended. 
3. Authorized by Chief of Engineers under authority of Section 2, 
Public Law 406, 75th Congress, as amended 
4. Authorized under the provisions of the Emergency Relief 
Appropriation Act of 1935 (Works Progress Administration). 
5. Authorized by Works Progress Administration Project No. OP 
65-93-917. 
6. Includes $7,850 appropriated and expended for recreation 
facilities at completed project (Code 710). 
7. Excludes $340,066 Public Works Acceleration Act funds 
expended. 
TABLE 38-F 
For Last 
Full Report 
See Annual 
Project Report for 
8. Preconstruction planning only. 
9. Productive Employment Appropriation Act of 1983 (P.L 98-8). 
Excludes $189,000 Federal Highway Administration funds 
expended. 
10. Emergency Relief funds, Works Progress Administration. 
11. Excludes amount expended by Works Progress Administration 
which is not available. 
12. Excludes $1,000 Coast Guard funds expended. 
13. Emergency Relief funds, Works Progress Administration. 
14. Includes $8,888 expended for restudy, FY 1967- 1972. 
15. Excludes $17,988 Office of Emergency Preparedness funds 
expended. 
16. Includes $118,000 expended under Productive Employment 
Appropriation Act of 1983 (P.L 98-8). 
Cost to Sep. 30. 19912 
Construction 
Operation 
and 
Maintenance 
Priest Rapids Dam, Columbia River, WA 1954 350,0001 
1. For partnership planning. Excludes funds expended for acquisition 
of lands under partnership arrangement for Priest Rapids and 
Wanapum Dams, in accordance with Public Law 544, 83d Congress. 
Project constructed by Grant County Public Utility District. 
- 38-29 - 
OTHER AUTHORIZED MULTIPLE PURPOSE PROJECTS, 
INCLUDING POWER

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
TABLE 38-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Calispell Creek, WA ' 1968 1968 $25,000 -- 
Columbia River Basin, Local Protection Projects, 
ID, MT, and WA: 
Crab and Wilson Creeks, WA 2 1958 1964 9,0007 - 
Entiat River, WA 3 1958 1986 -- 
Methow River, WA 3 1958 1986 - - 
Okanogan River, WA 3 1958 1986 1,100' - 
St. Regis River, MT 4 1958 1978 1,400- 
Wenatchee River, WA 4 1958 1978 -- -- 
Yakima River at Ellensburg, WA 3 1980 1986 44,30078 - 
Everett Harbor and Snohomish River, WA (RH 68)3 1973 1989 52,000' - 
Grays Harbor and Chehalis River, WA (RH 48) 
(Uncompleted Portion) 3 1962 1989 -- -- 
Grays Harbor and Chehalis River, WA (RH 30) 1933 1989 35,834 $35,834 
Hammersley Inlet, WA (Uncompleted Portion) 4 1950 1978 -- -- 
Hoquiam,Aberdeen, and Cosmopolis, Chehalis River, WA 5 1948 1952 83,6317- 
Olympia Harbor, WA (RH 45)3 1973 1989 21,6067 10 
Port Angeles Harbor, WA (Uncompleted Portion) 4 1960 1977 - - 
Port Gamble Harbor, WA (Uncompleted Portion) 4 1953 1977 -- -- 
Quillayute River, WA (Uncompleted Portion) 3 1986 1986 -- -- 
Seattle Harbor, WA (RH 25) (A Completed Portion)6 1986 1986 -- -- 
Seattle Harbor, WA (RH 30) (Uncompleted Portion) a 1986 1986 -- -- 
Skagit River, WA (Uncompleted Portion)" 1950 1978 -- -- 
Skagit River, WA (Avon Pass) 3 1968 1989 54,4687 - 
Spokane River, Spokane, WA 3 1939 1986 2,9447 
Stillaguamish River, WA 3 1946 1986 4,234- 
Wenatchee, Canyons 1 and 2, WA 3 1978 1989 544,331? - 
1. Authority for project expired October 27, 1968. 6. Turning basin constructed under authority of R&H Act of March 
2. Authority for project expired July 1964. 3,1925, was deauthorized under authority of Section 202, P.L 99-662 
3. Deauthorized under authority of Section 1002, P.L 99-662 dated dated November 17, 1986. Cost of turning basin is not available. 
November 17, 1986. 7. Preconstruction planning only. 
4. Deauthorized under authority of Section 12, P.L. 93-251 dated 8. Includes $14,300 expended for restudy, FY 1970. 
March 7, 1974. 9. Economic study only. 
5. Authority for project expired in October 1952. 10. Includes $18,700 expended for restudy, FY 1968-1973. 
TABLE 38-H LAKE WASHINGTON SHIP CANAL, WA 
PRINCIPAL FEATURES OF DOUBLE LOCK AND DAM 
(SEE SECTION 9) 
Section Large Lock Small Lock 
Miles above mouth 11/4 11/4 
Clear width of chamber Feet 80 28 
Maximum available length Feet 760 123 
Lift Feet 26 26 
Depth on upper miter sill1 Feet 331/2 16 
Depth on intermediate miter sill2 Feet 29 - 
Depth on lower miter sill2 Feet 29 16 
Character of foundation Clay Clay 
Kind of dam Fixed dam with Fixed dam with 
gated spillway. gated spillway. 
Type of construction Concrete Concrete 
Year completed 1916 1916 
Cost 3 3 
1. Low water in upper pool. 
2. Mean lower low water in Puget Sound. 
3. Cost of double lock and dam was $2,382,200 and the emergency 
gates, completed in 1923, $262,300. 
- 38-30 -

SEATTLE, WASHINGTON DISTRICT 
PROJECT CONDITION SURVEYS 
(SEE SECTION 12) 
TABLE 38-I 
Name of Project Date Survey Conducted 
Blaine Harbor 
Everett Harbor 
Lake Crockett 
Mats Mats Bay 
Port Townsend 
Quillayute River 
Swinomish Channel 
Waterway connecting Port Townsend and Oak Bay 
May 1992 
October, November 1991 
July, September 1992 
May 1992 
May 1992 
May 1992 
June 1992 
August 1992 
June 1992 
TABLE 38-J FLOOD CONTROL ACTIVITIES 
PURSUANT TO SECTION 205, 
PUBLIC LAW 858, 80TH CONGRESS, AS AMENDED 
(PREAUTHORIZATION) 
Study Identification Fiscal Year Costs (1992) 
Cataldo, ID 1,927' 
Cedar River, WA 136' 2 
Centralia-Chehalis Flood Warning System, WA 2,704' 
Chehalis River, Salzer Creek, WA 193 
Coeur d'Alene River, (North Fork), ID 13,813 
Flathead River, Kalispell, MT 12,620 
Horseshoe Bend, WA 25,832 
Nooksack River, Everson, WA 36,106 
Nooksack River, Marietta, WA 1,522' 
Nooksack River, Sumas, WA 13,328 
Nooksack River, Whatcom County, WA 11,076 
Quinault River, WA 231 
Snoqualmie River, WA 73' 
Stillaguamish River, Snohomish County, WA 0' 
Trumbell Creek, MT 11,959 
Yakima River, Easton, WA 15,000' 
TOTAL $146,312 
1. Terminated. 2. Excludes -$136 contributed funds expended. 
TABLE 38-K EMERGENCY FLOOD CONTROL ACTIVITIES 
REPAIR, FLOOD FIGHTING, AND RESCUE WORK 
(PUBLIC LAW 99, 84TH CONG., AND ANTECEDENT LEGISLATION) 
Project and Location Fiscal Year Costs (1992) 
Disaster Preparedness $473,524 
Emergency Operations 10,330 
Rehabilitation 531,535 ' 
TOTAL $1,015,389 
1. Excludes $264,074 contributed funds expended. 
- 38-31 - 
Washington:

WALLA WALLA, WA, DISTRICT* 
This District consists of all Columbia River drainage and 
tributaries thereto between the head of the McNary pool 
(River Mile 345.4) and the Umatilla Bridge (River Mile 
290.5) below McNary Dam, except the Yakima River Basin 
above the Van Giesen Street Bridge (River Mile 8.4) near 
Richland, WA. The primary tributary drainage area is the 
Snake River which includes more than 107,000 square miles 
in six states: Washington, Oregon, Idaho, Wyoming, and 
small portions of Nevada and Utah. 
IMPROVEMENTS 
Navigation 
1. Navigation Work Under Special Authorization .. 39-1 
Flood Control 
2. Columbia River Basin, Local Flood Protection 
Projects .................................. 39-1 
3. Flood Control Work Under Special Authorization39-2 
4. Inspection of Completed Flood Control Projects 39-2 
5. Inspection of Completed PL-99 Works ....... 39-2 
6. Jackson Hole, WY ........................ 39-2 
7. Lucky Peak Lake, ID ....................... 39-2 
8. Mill Creek Lake, WA ...................... 39-3 
9. Scheduling Flood Control Reservoir Operations 39-3 
Multiple-Purpose Projects, Including Power 
10. Columbia River Juvenile Fish 
Mitigation Program ..................... 39-3 
11. Dworshak Dam and Reservoir, ID ............ 39-4 
12. Ice Harbor Lock and Dam -- 
Lake Sacajawea, WA ....................... 39-5 
13. Little Goose Lock and Dam -- Lake Bryan, WA 39-5 
14. Lower Granite Lock and Dam, WA .......... 39-5 
15. Lower Monumental Lock and Dam - 
Lake Herbert G. West,WA ................ 39--6 
16. Lower Snake River Fish & Wildlife Compensation 
Plan, WA,OR, ID ......................... 39-7 
17. McNary Lock and Dam - Lake Wallula, 
OR and WA .............................. 39-7 
Navigation 
1. NAVIGATION WORK UNDER SPECIAL 
AUTHORIZATION 
18. Snake River Downstream from Johnson Bar 
Landing, OR, WA and ID ................ 39-7 
General Investigations 
19. Surveys ................................. 39-8 
20. Collection and Study of Basic Data ........... 39-8 
21. Preconstruction, Engineering and Design ...... 39-8 
Tables 
Tables 39-A 
Tables 39-B 
Tables 39-C 
Tables 39-D 
Tables 39-E 
Tables 39-F 
Tables 39-G 
Tables 39-H 
Tables 39-I 
Tables 39-J 
Tables 39-K 
Cost & Financial Statement ....... 39-10 
Authorizing Legislation ........... 39-12 
Other Authorized Navigation Projects39-15 
Not Applicable 
Other Authorized Flood Control 
Projects ........................ 39-15 
Other Authorized Multiple Purpose 
Projects, Including Power ......... 39-17 
Deauthorized Projects ............ 39-17 
Columbia River Basin, Local Flood 
Control Projects ................ 39-18 
Inspection of Completed Flood 
Control Projects ............... 39-18 
Principal Data Concerning Navigation 
Lock, Spillway Dam, Powerplant and 
Impoundment ................... 39-18 
Snake River Downstream from Johnson 
Bar Landing, OR, WA, and ID .... 39-23 
new barge slip at Port of Walla Walla, Snake River, near Burbank, 
Washington. FY 92 costs were $4,620. 
Flood Control 
2. COLUMBIA RIVER BASIN, LOCAL 
FLOOD PROTECTION PROJECTS. 
Navigation activities pursuant to Section 107, Public Law Location. Improvements included in this project are along 
86-645. A reconnaissance study was initiated for adding a Columbia River and its tributaries. 
- 39-1 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Existing project. Flood Control Act of 1950 approved a 
general comprehensive plan for Columbia River Basin for 
flood control and other purposes based on plans in H. Doc. 
531, 81st Cong., 2d Sess., and authorized $75 million to be appropriated 
for partial accomplishment of certain projects. Of 
that authorization, an amount not to exceed $15 million was 
allotted for construction of local flood protection works 
throughout Columbia River Basin, subject to conditions that 
all work undertaken pursuant to authorization would be economically 
justified prior to construction, and local cooperation 
specified in 1936 Flood Control Act, as amended, should 
be required. (See Tables 39-B and 39-H for projects in Walla 
Walla District.) 
Local cooperation. Section 3, Flood Control Act of June 22, 
1936, applies. 
Operations during fiscal year. No projects were 
deauthorized during FY 92. 
3. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Congress, as amended. 
Fiscal year costs were $204,629 for continued ice jam testing 
studies on the Salmon River near Salmon, ID. 
Emergency flood control activities-repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and antece. 
dent legislation). 
Federal costs for fiscal year were $199,331 for disaster preparedness, 
and $0 for flood fight and rescue operations. 
Emergency Bank Protection (Section 14, 1946 Flood Control 
Act, Public Law 526, 79th Congress). 
Fiscal year costs were $21,055 including terminating the reconnaissance 
study on the Big Lost River at Moore, ID 
($1,089), and Pataha Creek at Pomeroy, WA ($19.966). 
Snagging and clearing of navigable streams and tributaries 
in interest of flood control (Section 208, 1954 Flood Control 
Act, Public Law 780, 83rd Congress). 
No activities were conducted this year. 
Project modification for the Improvement of the Environment 
pursuant to Section 1135 (b), Public Law 99-362 as 
amended. 
Fiscal year costs were $34,120 for Jackson Hole Project, 
WY. 
4. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Federal law requires local interests to maintain and operate 
completed local protection projects in accordance with 
regulations prescribed by Secretary of Army. Inspections 
were made to determine extent of compliance and to advise 
local interests as necessary of measures required to correct 
deficiencies. An appraisal report was completed for the existing 
Portneuf River Flood Control project at Pocatello, Idaho. 
The study evaluated the Federal interest in further studies 
regarding environmental restoration and ice jam flooding. 
See Table 39-I for inspections made during FY 92. 
Fiscal year costs were $76,661. Total costs to September 30, 
1992 were $2,682,996. 
5. INSPECTION OF COMPLETED PL-99 
WORKS 
FY 89 was the last year for expenditures on this program. 
The program is carried under the Flood Control and Coastal 
Emergencies appropriations. 
6. JACKSON HOLE, WY 
Location. On both banks of the Snake River, Teton 
County, west of Jackson, Wyoming. 
Existing project. 23.5 miles of levees consisting of: Right 
bank - a levee with full riprap protection from 10 miles upstream 
of the Jackson-Wilson Highway Bridge, to 3.5 miles 
below, a total of 13.5 miles. Left bank - a levee with full 
riprap protection extending from 10 miles upstream of Jackson-
Wilson Highway Bridge to 5 miles upstream and extending 
1.5 miles immediately upstream from the same bridge to 
3.5 miles below the bridge, for a 10-mile total length. 
Project authorized by Public Law 516, Flood Control Act of 
1950 for flood control protection by channel improvements 
consisting of channel rectification, levees, and revetment 
along Snake River in the vicinity of Wilson, Wyoming. Public 
Law 99-662 modified the original Public Law 516 to provide 
that the operation, maintenance, modifications, and additions 
to the project become Federal responsibility. 
Local cooperation. Non-Federal sponsors shall pay the initial 
$35,000 in cash or materials of any such costs expended in 
any one year, plus inflation as of the date of enactment of the 
Water Resources Development Act of 1986. 
Operations during fiscal year. A claim following last years 
riprap contract was settled. Levee maintenance was performed 
by Teton County under the Local Cooperative agreement. 
Monitoring for the Bald Eagle Management Plan was 
done by the Wyoming Dept. of Game and Fish. Preliminary 
studies for Environmental Assessments on substandard 
bridges and access ways were incorporated into a Supplemental 
Environmental impact statement for an alternate quarry 
site and improvement of local access roads were initiated this 
year. Alternate quarry investigations continued with drilling 
and rock testing of four possible sites. Efforts continued in 
mapping owner boundaries, real-estate right-of ways, and 
easements. Mosaics were made of aerial photographs over 
the Jackson Levees. Plans and specifications were begun for 
providing additional 5,000 cubic yards of riprap. A preliminary 
survey of alternate levee construction methods was begun. 
Total costs during fiscal year were $713,204. 
7. LUCKY PEAK LAKE, ID 
Location. On Boise River in southwestern Idaho about 10 
miles southeast of city of Boise, ID. 
Existing project. The project includes a rolled-earthfill 
dam about 250 feet high above streambed and 1,700 feet long 
- 39-2 -

WALLA WALLA, WASHINGTON DISTRICT 
at crest, with a lake providing a total storage at upper operating 
lake level of 306,000 acre-feet. Project provides for flood 
control, irrigation, and recreation. (For details, see page 2000 
of Annual Report for 1962.) 
Construction of existing project was initiated November 
1949 and completed June 1961. Since 1961, $138,532,000 in 
potential flood damages have been prevented by the project. 
During the detailed investigation of outlet capacity and the 
potential for adding hydropower to the existing project, a 
need for an auxiliary outlet became apparent. Construction 
of an auxiliary outlet was authorized in the Water Resource 
Development Act of 1976. In FY 78, an "Interim Feasibility 
Report on Modification of Lucky Peak Dam and Lake" 
(power facilities) was submitted to the Board of Engineers for 
Rivers and Harbors and approved. States, agencies, and the 
Chief of Engineers have commented on the report to the Secretary 
of the Army. The report was forwarded to the Office of 
Management and Budget in February 1982. 
A license to construct and operate power facilities at the 
project was issued by the Federal Energy Regulatory Commission 
(Project #2832) to the Boise Project Board of Control 
on June 10, 1980 and modified on October 9, 1980 and 1982. 
Construction of the auxiliary outlet facility began in May 1984 
and was completed in August 1986. Construction of modifications 
to the existing outlet tunnel and powerhouse excavation 
began in August 1986 and was completed January 1987. Powerhouse 
general contract construction began in April 1986. 
The project was completed and dedicated on October 7, 
1988. Power on line for all units was August 18, 1988. 
Local cooperation. None Required. 
Operations during fiscal year. Operation and Maintenance: 
Contract for office remodeling awarded. Normal operation 
and maintenance continued, which included the dam 
structures and recreation areas. Federally authorized 2nd 
outlet was deauthorized FY 90. 
8. MILL CREEK LAKE, WA 
Location. In and upstream from Walla Walla, WA, on Mill 
Creek, a tributary of Walla Walla River. 
Existing project. The project includes an off-stream 
earthfill storage dam about 125 feet high above streambed 
and 3,200 feet long at the crest, two concrete-lined outlet 
channels, an earthfill diversion dam, and division structures. 
Project provides for flood control and recreation. Authorizing 
legislation to provide a channel through the City of Walla 
Walla was added to the project in 1941. Recreation was 
added to the project purposes through the Federal Water 
Project Recreation Act of 1965. 
Construction of the dam and appurtenant works was completed 
in 1942. Paving of the channel through City of Walla 
Walla was completed in 1948. Recreation facilities were completed 
in 1966. (For details, see page 2005 of Annual Report 
of 1962.) Since 1942, $10,818,412 in potential flood damages 
have been prevented by the combined storage and channel 
operation. 
The rehabilitation of the existing project was to correct the 
seepage and internal erosion by constructing a cutoff wall. 
The construction of the cutoff wall did not alleviate the seepage 
problem, thus requiring limited flood control use of the 
project. The seepage and internal erosion create a high vulnerability 
for dam failure. 
Local cooperation. Fully complied with. (For details, see 
page 2006 of Annual Report of 1962.) 
Operations during fiscal year. Operation and Maintenance: 
Normal operation and maintenance continued, which 
included regulation of water control structures and care of 
recreation areas. 
9. SCHEDULING FLOOD CONTROL 
RESERVOIR OPERATIONS 
Functional regulation of non-Corps projects was accomplished 
under several authorities. Regulation of Palisades, 
Little Wood, and Anderson Ranch Reservoirs in Idaho, and 
Bully Creek, Warm Springs, Agency Valley, and Mason Reservoirs 
in Oregon, was accomplished as authorized under 
Section 7, Flood Control Act of 1944, and coordinated with 
the Bureau of Reclamation. 
Flood control operations at Jackson Lake, Arrowrock Reservoir, 
and Lake Lowell were in accordance with formal 
agreements with the Bureau of Reclamation. Regulation of 
American Falls, Owyhee, Magic, Mackay, Cascade, and 
Deadwood Reservoirs, Idaho, for flood control were accomplished 
under informal agreements. Brownlee, Oxbow, and 
Hells Canyon Reservoirs provided flood control regulation in 
accordance with provisions of the Federal Power Commission 
license to Idaho Power Company. 
Fiscal year costs were $263,190. 
Multiple-Purpose Projects, Including Power 
10. COLUMBIA RIVER JUVENILE FISH 
MITIGATION PROGRAM (Walla Walla 
Projects) 
Location. At Ice Harbor, Lower Monumental, Little 
Goose, and Lower Granite Dams on the Snake River in the 
state of Washington and McNary Dam on the Columbia 
River in the states of Oregon and Washington. 
Existing project. Congress passed and the President signed 
the FY 89 Energy & Water Development Act (P.L. 100-371) 
which mandated the expenditure of $8.7 million in FY 88 and 
$9.6 million in FY 89 for the design, testing, and construction 
of fish bypass facilities. Funds for FY 88, 89 and 90 were expended 
on a project by project basis. However,the mitigation 
program starting in FY 91 is considered as one project and 
funds will be appropriated and expended as such. The program 
will consist of juvenile fish mitigation facilities which includes 
construction of juvenile fish passage facilities and a detailed 
mitigation study to be prepared in cooperation with 
regional interest, for juvenile fish losses at Corps dams on the 
Columbia and Snake Rivers. Completion of the bypass and 
transportation facilities will significantly increase the survival 
- 39-3 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
of migrating downstream juvenile fish. The mitigation study 
will determine the overall scope of the fish mitigation facilities 
for these Columbia and Snake River dams. 
The plan of improvement includes the following facilities: 
(a) Ice Harbor - submerged standard traveling fish screens, 
intake gate raise, new gantry crane, collection bypass facility; 
(b) Lower Monumental - submerged standard traveling fish 
screens, gate raise modification, gantry crane, collection bypass 
facility, and holding and loading facility; (c) Little Goose 
- gantry crane modification,, gate raise modification, submerged 
extended fish screens, and holding and loading facilities 
Phase I and II; (d) Lower Granite - submerged extended 
fish screens, two fish transport barges, gate raise modification, 
fish support facility, wet separator, barge moorage facility 
expansion, and gantry crane modification; (e) McNary - 
submerged extended fish screens, gantry crane modifications, 
collection and bypass facilities; transport holding and loading 
facility, gate raise modification, and extended screen rehab 
facility; (f) A mitigation study that analyzes long-term alternatives 
to mitigation for fish losses at Corps dams on the Columbia 
and Snake Rivers. 
The total estimated Federal project cost is $217,500,000. 
Ice Harbor bypass facilities were not initially authorized for 
construction under the Columbia River Juvenile Fish Mitigation 
Program. However in FY 89, Congress authorized expenditures 
to proceed with design of a bypass system. The 
mitigation study project was added to the President's FY 91 
budget. 
Local cooperation. None required. 
Operations during fiscal year. Conservation groups, represented 
by the State of Idaho, requested that the lower Snake 
River reservoirs be drawn below minimum authorized operating 
pool in an effort to improve migration conditions for juvenile 
salmon. In 1992, a test was conducted during the 
month of March to evaluate the effect of drawdown on project 
structures and the operation of project features. It was 
ascertained that drawing Lower Granite Reservoir down 52 
feet and Little Goose Reservoir down 20 feet below normal 
minimum pool affected the operation of turbine units at 
Lower Granite Dam, eliminated commercial navigation on 
both reservoirs, affected shoreline fills, embankments, railroad 
fills, and highway fills. In addition to damage to facilities, 
loss of business occurred at marinas and port facilities. Adult 
and juvenile fish passage facilities were not operational, and 
spill caused excessive gas supersaturation below the spillway 
and downstream through several reservoirs. No biological 
data on juvenile fish migration timing was gathered because 
the test was done before the outmigration to minimize effects 
on Snake River salmon. Construction was completed on submerged 
fish screens and collection/bypass facilities at Lower 
Monumental. Construction was initiated for a holding/loading 
facility at Lower Monumental. Design was completed and 
construction was initiated on the collection/bypass/holding 
and loading facilities at McNary. Design was continued on a 
new gantry crane at Ice Harbor. FY 92 costs were 
$27,723,497. Total project costs through FY 92 are 
$75,530,038. 
11. DWORSHAK DAM AND RESERVOIR, ID 
Location. Dam is on North Fork Clearwater River 1.9 miles 
above its junction with Clearwater River, near Orofino, ID, 
and about 35 miles east of Lewiston, ID. 
Existing project. The project includes a dam, powerplant, 
and appurtenant facilities. Project provides for flood control, 
navigation, hydroelectric power generation, recreation, and 
area redevelopment. The reservoir has a normal operating 
range between Elevations 1600 and 1445 Mean Sea Level 
(MSL). The reservoir has a gross storage capacity of 
3,453,000 acre-feet, of which 2,000,000 acre-feet are effective 
for both local and regional flood control and for at-site 
and downstream power generation. In addition, the reservoir, 
extending 53 miles into rugged and relatively inaccessible 
timberland, provides important transportation savings in 
connection with movements of marketable logs. The reservoir 
is habitat for elk, deer, and other wildlife. Dam structure 
is about 3,300 feet long and about 717 feet high above 
streambed. Fish passage is not feasible due to the height of 
the dam. A hatchery has been built below the dam to assure 
continuance of anadromous fish runs. Powerhouse has two 
90,000 kilowatt and one 220,000 kilowatt generating units in 
operation for a capacity of 400,000 kilowatts. Provisions have 
been made for three additional 220,000 kilowatt generating 
units for an ultimate installed capacity of 1,060,000 kilowatts. 
A reconnaissance report justifying the feasibility and cost 
benefits for the addition of a 200,000 kilowatt fourth generating 
unit was completed in FY 78. Environmental and economic 
studies on additional generating units have been curtailed 
due to public opposition. Unit 4 is undeveloped. Units 
5 and 6 were deauthorized FY 90. Principal project data are 
set forth in Table 39-J. 
Construction of the project started in April 1963 and was 
completed in 1986. Since the project became operational in 
June 1972, it has prevented about $737,000 of potential flood 
damages. Power generation through September 1992 was 
34.17 billion kilowatt hours. 
Eighty mini-recreation sites have been established along 
the reservoir shoreline. Each site includes at least a picnic table, 
U.S. Forest Service-type fireplace, and chemical toilet. 
Some of the sites have several picnic tables. Dent Acres and 
Freeman Creek recreation sites are open to the public. Facilities 
consist of a boat launching ramp, boat docks, cartrailer 
parking, comfort stations, and fully-developed overnight 
camping. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contract 
completed for purchase of generator excitation equipment. 
Contract completed for visitor center and asbestos removal. 
Operation and Maintenance: Wildlife habitat browse continued 
on project lands to provide winter browse for elk and 
deer. During fiscal year 1.23 billion kilowatt hours of electrical 
power were generated by the three generating units. 
Dworshak National Fish hatchery 
Dworshak National Fish Hatchery (DNFH) operations 
were less affected by the IHNV disease than in past years due 
to the completion of the hatchery water supply line from 
- 39-4 -

WALLA WALLA, WASHINGTON DISTRICT 
Dworshak Reservoir. Although DNFH receives only 6,500 
gpm from the water line, this was sufficient to allow eggs and 
fry to be raised in IHNV free water. Numbers of eggs transferred 
to Kooskia (KNFH) and Hagerman (HNFH) national 
fish hatcheries were reduced, with 337,000 and 540,000 
smolts produced by early rearing at these sites, respectively. 
Another 1,433,000 smolts were produced at DNFH, so the 
mitigation goal of 2,300,000 steelhead was exceeded by some 
9,000 fish. The average size of fish was larger with 450,785 
pounds produced in 1992 compared with 396,751 in 1991. 
DNFH also released 1,670,000 spring chinook weighing 
42,958 pounds. For 1992, nearly 8 million eggs were collected 
from a return of 3700 steelhead. A total of 1.8 million eyed 
eggs were shipped to Magic Valley and Clearwater fish hatcheries. 
Spring chinook returns were low again in 1992 with 675 
adults collected at DNFH and KNFH. Some 800,000 eggs 
were taken with an estimated smolt release of 600,000. This is 
well below the 1.9 million capacity of the hatchery. The steelhead 
return to the Columbia River was the fourth highest run 
of record with over 310,000 going over Bonneville Dam, and 
over 160,000 entering the Snake River. A new record of over 
135,000 was counted over Lower Granite Dam. 
12. ICE HARBOR LOCK AND DAM - LAKE 
SACAJAWEA, WA 
Location. On Snake River, 9.7 miles above river mouth at 
head of Lake Wallula (McNary Reservoir) and 12 miles east 
of Pasco, WA. 
Existing project. The project includes a dam, powerplant, 
navigation lock, two fish ladders, and appurtenant facilities. 
Project provides for navigation, hydroelectric power generation, 
recreation, and incidental irrigation. The reservoir has a 
normal operating range between Elevations 440 and 435 
Mean Sea Level (MSL). Lake Sacajawea extends upstream 
about 31.9 miles and provides slack water to Lower Monumental 
Lock and Dam. Dam structure is about 2,790 feet long 
and about 130 feet high above streambed. Fish passage facilities 
include two fish ladders. Powerhouse has three 90,000 
kilowatt units and three 111,000 kilowatt generating units in 
operation for a capacity of 603,000 kilowatts. Spillway dam is 
610 feet long and overflow crest at Elevation 391 MSL is surmounted 
by 10 radial gates, 50 feet wide and 51 feet high, 
which provides the capacity to pass a design flood of 850,000 
cubic feet per second. Deck is at Elevation 453 MSL and provides 
a service road and track for a gantry crane. Navigation 
lock is single-lift type with clear plan dimensions of 86 by 675 
feet and 15-foot minimum depth over the sills. A navigation 
channel 250 feet wide, 14 feet deep and 41.6 miles long is provided 
from the mouth of the Snake River to the dam and from 
the dam to Lower Monumental Lock and Dam. Principal data 
are set forth in Table 39-J. 
Construction of the original project started in December 
1955 and was completed in 1971. Construction of the additional 
generating units was started in 1971 and completed in 
1981. Power generation through September 1992 was 67.51 
billion kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contract 
completed for cavitation repair on Units 4, 5, and 6. Contract 
awarded for navlock control valve replacement. Operation 
and Maintenance: During fiscal year 1.39 billion kilowatt 
hours of electrical power were generated by the 6 generating 
units. Traffic through the navigation lock, consisted of grains, 
petroleum products, fertilizer, wood products, and miscellaneous 
cargo, amounted to 3,508,987 tons during calendar 
year 1991. 
13. LITTLE GOOSE LOCK AND DAM - 
LAKE BRYAN, WA 
Location. Dam is 70.3 miles above mouth of Snake River at 
head of Lake Herbert G. West (Lower Monumental Reservoir), 
about 40 airline miles northerly of Walla Walla, WA, 
and 50 miles westerly of Lewiston, ID. 
Existing project. The project includes a dam, powerplant, 
navigation lock, fish ladder, and appurtenant facilities. Project 
provides for navigation, hydroelectric power generation, 
recreation, and incidental irrigation. The reservoir has a normal 
operating range between Elevations 638 and 633 Mean 
Sea Level (MSL). Lake Bryan extends upstream about 37.2 
miles and provides slack water to Lower Granite Lock and 
Dam. Dam structure is 2,655 feet long and about 165 feet 
high above streambed. Fish passage facilities include one ladder 
with entrances on both shores with a fish channel through 
the spillway which connects to the powerhouse fish collection 
system and south shore ladder. Powerhouse has six 135,000 
kilowatt generating units in operation for a capacity of 
810,000 kilowatts. Spillway dam is 498 feet long and overflow 
crest at Elevation 581 MSL is surmounted by 8 radial gates, 
50 feet wide and 60 feet high, which provide the capacity to 
pass a design flood of 850,000 cubic feet per second. Navigation 
lock is single-lift type with clear plan dimensions of 86 
feet by 675 feet and 15-foot minimum depth over the sills. A 
navigation channel 250 feet wide, 14 feet deep and 37.2 miles 
long is provided from the dam to Lower Granite Lock and 
Dam. Relocations along the lake included 32 miles of Camas 
Prairie Railroad, 6.8 miles of county roads, 2.2 miles of state 
highways, and Central Ferry Bridge. Principal project data 
are set forth in Table 39-J. 
Construction of the original project started in 1963 and was 
completed in 1976. Construction of the additional generating 
units started in 1974 and was completed in 1984. Power generation 
through September 1992 was 55.52 billion kilowatt 
hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contract continuing 
for turbine repair Unit 1. Contracts awarded for unit 2 
and 3 turbine repair, fish pump turbine repair and asbestos 
removal. Operation and Maintenance: During fiscal year 1.63 
billion kilowatt hours of electrical power were generated by 
the 6 generating units. Traffic through the navigation lock, 
consisted of grains, petroleum products, fertilizer, wood 
products, and miscellaneous cargo, amounted to 2,921,135 
tons during calendar year 1991. 
- 39-5 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
14. LOWER GRANITE LOCK AND DAM, WA 
Location. At River Mile 107.5 on Snake River at head of 
Lake Bryan (Little Goose Reservoir) and about 33 miles 
downstream from Lewiston, ID. 
Existing project. The project includes a dam, powerplant, 
navigation lock, fish ladder, appurtenant facilities, and required 
about 8 miles of backwater levees along the Snake and 
Clearwater Rivers at Lewiston, ID. Project provides for slackwater 
navigation, hydroelectric power generation, recreation, 
and incidental irrigation. The reservoir has a normal operating 
range between Elevations 738 and 733 Mean Sea 
Level (MSL) in Lewiston, ID-Clarkston, WA area. Lower 
Granite pool extends upstream about 38 miles and provides 
slackwater to the confluence of the Snake and Clearwater 
Rivers. Dam structure is about 3,200 feet long and about 146 
feet high above streambed. Fish passage facilities include one 
ladder with entrances on both shores with a fish channel 
through the spillway which connects to the powerhouse fish 
collection system and south shore ladder. Powerhouse has six 
135,000 kilowatt generating units in operation for a capacity 
of 810,000 kilowatts. Spillway dam is 512 feet long and overflow 
crest at Elevation 581 MSL is surmounted by 8 radial 
gates, 60 feet wide and 60.5 feet high, which provide the capacity 
to pass a design flood of 850,000 cubic feet per second. 
Navigation lock is single-lift type with clear plan dimensions 
of 86 by 675 feet and 15-foot minimum depth over the sills. A 
navigation channel 250 feet wide, 14 feet deep and 38.0 miles 
long is provided from the dam to the confluence of the Snake 
and Clearwater Rivers. Principal data are set forth in Table 
39-J. 
Construction of the original project started in July 1965 and 
was completed in 1984. Construction of the additional generating 
units was started in 1974 and completed in 1979. Power 
generation through September 1992 was 46.74 billion kilowatt 
hours. Approximately $4,119,300 in potential flood 
damages have been prevented since the levees became functional. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contracts 
completed on confluence dredging, forebay debris boom, and 
raceway shading. Operation and Maintenance: During fiscal 
year 1.65 billion kilowatt hours of electrical power were generated 
by the 6 generating units. Traffic through the navigation 
lock consisted of grains, petroleum products, fertilizer, 
wood products, and miscellaneous cargo, amounted to 
1,861,347 tons during calendar year 1991. 
As the first collection point on the Snake River, Lower 
Granite Dam is a primary component of the District's Juvenile 
Fish Transport Program. Transport began in the 1960's 
as a study of methods of bypassing juvenile steelhead and 
salmon around turbines of the Corps' Snake and Columbia 
River dams. Transport became a routine operation in 1980 
while other structural modifications, installation of screens, 
and development of bypass systems continue. 
The 1992 transport season was marked by below normal 
flows in the Snake River for the seventh consecutive year. 
The spring/summer chinook outmigration was fairly normal, 
but many steelhead smolts refused to move downstream resulting 
in below normal survival to Lower Granite Dam. Collection 
totaled 6,911,174 at Lower Granite Dam compared 
with 9,356,391 in 1990 and 8,616,516 in 1992. After four days 
of over 400,000 fish collected per day and a peak collection of 
464,253 on May 5, over 118,000 fish were bypassed on May 6 
when holding and barge capacities were exceeded. At Little 
Goose Dam, 1,795,834 juvenile salmon and steelhead were 
collected, down from previous years. Movement peaked at 
145,848 on 3 May. Because flows did not exceed 100 thousand 
cubic feet per second (cfs) until the spring/summer chinook 
outmigration was past Little Goose Dam, no fish were bypassed 
back to the river. At McNary Dam, 9,551,616 fish were 
collected. Peak collection was 140,571 on 13 May when yearling 
fish dominated collection, and 572,200 fish on 28 June 
when sub-yearling fish comprised 99.9 percent of the collection. 
With flows below 220 kcfs, fish were not bypassed at Mc- 
Nary Dam except for research. In contrast with 1991 with 
over 80 consecutive days of spill, spill occurred on three days 
in 1992. A grand total of 18,259,554 fish were collected, well 
below the record 22,261,661 fish collected in 1990. A total of 
17,561,019 fish were transported, 96.2% of those collected. 
Of those transported, 970,289 (5.5%) were by truck, and 
16,590,730 (94.5%) were by barge. Because of the listing of 
Snake River sockeye as endangered, and Snake River chinook 
as threatened, the transport season was extended from 
mid-July to the end of October at Lower Granite and Little 
Goose Dams, and from the end of September through December 
at McNary Dam. Transport ceased on schedule at 
Lower Granite and Little Goose dams, but was terminated 
early (December 7) at McNary Dam because of icy road conditions 
and dangerous conditions at the release area below 
Bonneville Dam.The first phase of construction of a new collection/
bypass system at Lower Monumental Dam was operational 
by the beginning of the outmigration providing full 
screening and bypass capability. Construction of holding, 
loaking, and fish handling facilities continued through December 
1992, with completion expected before the 1993 
outmigration. A Biological Assessment was completed recommending 
full transport from Lower Monumental, as well 
as the other three collector dams. A Biological Opinion is 
pending from the National Marine Fisheries Service. An Endangered 
Species Act Section 10 permit was received for the 
1992 fish transport program, and an application has been submitted 
for 1993 activities including research at Corps dams 
funded by the Corps. Additional facility modifications in 1992 
included installation of a roof over the west raceways and installation 
of a new trash shear boom at Lower Granite Dam, 
further modification and improvement of the Little Goose juvenile 
fish collection system, and initiation of construction of 
a new fish collection facility at McNary Dam. 
15. LOWER MONUMENTAL LOCK AND 
DAM - LAKE HERBERT G. WEST, WA. 
Location. On Snake River at head of Lake Sacajawea (Ice 
Harbor Reservoir), about 45 miles northeast of Pasco, WA, 
and 41.6 miles above river mouth. 
Existing project. The project includes a dam, powerplant, 
navigation lock, two fish ladders, and appurtenant facilities. 
Project provides for navigation, hydroelectric power genera- 
- 39-6 -

WALLA WALLA, WASHINGTON DISTRICT 
tion, recreation, and incidental irrigation. The reservoir has a 
normal operating range between Elevations 540 and 537 
Mean Sea Level (MSL). Lake Herbert G. West extends upstream 
about 28.7 miles and provides slack water to Little 
Goose Lock and Dam. Dam structure is about 3,800 feet long 
and about 135 feet high above streambed. Fish passage facilities 
include two fish ladders, one at each end of the dam. Powerhouse 
has six 135,000 kilowatt generating units in operation 
for a capacity of 810,000 kilowatts. Spillway dam is 508 feet 
long and overflow crest at Elevation 483 MSL is surmounted 
by 8 radial gates, 50 feet wide and 61 feet high, which provide 
capacity to pass a design flood of 850,000 cubic feet per second. 
Deck is at Elevation 553 MSL and provides a service 
road and track for a gantry crane. Navigation lock is single-lift 
type with clear plan dimensions of 86 by 675 and 15-foot 
minimum depth over the sills. A navigation channel 250 feet 
wide, 14 feet deep and 28.1 miles long is provided from the 
dam to Little Goose Lock and Dam. Relocations along the 
lake included railroads and highways. Principal data are set 
forth in Table 39-J. 
Construction of the original project started in June 1961 
and was completed in 1976. Construction of the additional 
generating units started in 1975 and was completed in 1981. 
Power generation through September 1992 was 68.60 billion 
kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contract 
awarded for unit 3 repair, fish pump turbine repair and naylock 
control valve replacements. Operation and Maintenance: 
During fiscal year 1.53 billion kilowatt hours of electrical 
power were generated by the 6 generating units. Traffic 
through the navigation lock, consisted of grains, petroleum 
products, fertilizer, wood products, and miscellaneous cargo, 
amounted to 2,419,668 tons during calendar year 1991. 
16. LOWER SNAKE RIVER FISH AND 
WILDLIFE COMPENSATION PLAN, WA, OR, 
ID
Location. At various locations within the Columbia Snake 
River drainage in the States of Idaho, Oregon, and Washington. 
Existing project. The project consists of a series of fish 
hatcheries, wildlife development areas and purchase of offsite 
project lands for fishing and hunting access. The project 
will compensate for loss of wildlife habitat and anadromous 
and resident fishery inundated as a result of construction of 
four multiple-purpose dams and reservoirs on the Lower 
Snake River (Ice Harbor, Lower Monumental, Little Goose, 
Lower Granite). 
The real estate design memorandum, and feature design 
memorandums on all hatcheries and satellites, the off-project 
wildlife lands, and the site selection report have all been 
approved. A final Environmental Impact Statement was filed 
with Council on Environmental Quality on November 2, 
1977. The Dworshak National Fish Hatchery Expansion, the 
Irrigon Hatchery, Hagerman Hatchery, Lyons Ferry Hatchery, 
Lookingglass Hatchery, McCall Hatchery, Sawtooth 
Hatchery and Magic Valley Hatchery are in operation. The 
compensation plan is 89 percent complete. 
Estimated Federal cost of the project is $219,000,000. 
Local cooperation. None required 
Operations during fiscal year. New work: Work was completed 
Clearwater Hatchery Water Supply and Clearwater 
Hatchery. Off-project land acquisition is being pursued. 
17. McNARY LOCK AND DAM - LAKE 
WALLULA, OR AND WA 
Location. On Columbia River 292 miles above mouth, near 
Umatilla, OR, and 3 miles above mouth of Umatilla River. 
Existing project. The project includes a dam, powerplant, 
navigation lock, two fish ladders, appurtenant facilities, and a 
system of levees and pumping plants. Project provides for 
slackwater navigation, hydroelectric power generation, recreation, 
and incidental irrigation. The reservoir has a normal 
operating range between Elevations 340 and 335 Mean Sea 
Level (MSL). Lake Wallula extends upstream about 64 miles 
and provides slack water to Ice Harbor Lock and Dam. Dam 
structure is 7,365 feet long and about 183 feet high above 
streambed. Fish passage facilities include two fish ladders. 
Powerhouse has fourteen 70,000 kilowatt generating units in 
operation for a capacity of 980,000 kilowatts. Spillway dam is 
1,310 feet long and overflow crest at Elevation 291 MSL is 
surmounted by 22 vertical lift gates, 50 feet wide and 51 feet 
high, which provide the capacity to pass a design flood of 
2,200,000 cubic feet per second. Navigation lock is single-lift 
type with clear plan dimensions of 86 by 675 feet and 15-foot 
minimum depth over the sills. A navigation channel 250-feet 
wide, 14-feet deep and 32 miles long is provided from the 
dam to the mouth of the Snake River. Relocations along the 
lake included railroad bridges over the Columbia and Snake 
Rivers in order to eliminate hazards to navigation. Principal 
project data are set forth in Table 39-J. 
Construction started May 1947 and was completed in 1982. 
Power generation through September 1992 was 235.29 billion 
kilowatt hours. 
Local cooperation. None required. 
Operations during fiscal year. Maintenance: Contract 
awarded for machine shop roof repair. Operation and Maintenance: 
During fiscal year 5.82 billion kilowatt hours of electrical 
power were generated by the 14 generating units. Traffic 
through the navigation lock consisted of grains, petroleum 
products, fertilizer, wood products, and miscellaneous cargo, 
amounted to 6,151,333 tons during calendar year 1991. 
18. SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING, OR, WA, AND ID 
Location. On Snake River downstream from Johnson Bar 
Landing, River Mile 230 Snake River, which is largest tributary 
of Columbia River, rises in Yellowstone National Park in 
western part of Wyoming, flows generally westerly for about 
1,000 miles, and empties into Columbia River near Pasco, 
WA, 324 miles from Pacific Ocean. 
Existing project. The River and Harbor Act of 1945 authorized 
construction of dams as necessary for power, incidental 
- 39-7 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
irrigation, and open channel improvements for purposes of 
providing slack-water navigation and irrigation between 
mouth of Snake River and Lewiston, ID. That authorization 
modified previous authorizations only for the portion of improvement 
below Lewiston, ID. Acts of June 13, 1902, and 
August 30, 1935, as they pertain to open river improvement 
from Lewiston, ID, to Johnson Bar Landing, remain part of 
existing project. 
Improvements included in existing project are Ice Harbor 
Lock and Dam - Lake Sacajawea; Little Goose Lock and 
Dam - Lake Bryan; Lower Granite Lock and Dam; Lower 
Monumental Lock and Dam - Lake Herbert G. West; and 
open-river improvement, Lewiston to Johnson Bar Landing. 
Each of the four locks and dams is described in an individual 
report, and cost and financial data for the entire project are 
shown on Table 39-A and 39-K. 
Ice Harbor, Lower Monumental, Little Goose, and Lower 
Granite are in full operation. (See individual reports for details.) 
(For further details see Annual Reports, page 2246 for 
1903; page 1986 for 1906; page 1991 for 1915; and page 1981 
for 1962.) 
Local cooperation. None required. 
Terminal facilities. On Snake River from the mouth to 
Johnson Bar Landing there are 18 privately-owned barge terminals 
in use for shipping grain, petroleum products, fertilizers, 
wood products, cement, and other general cargo. There 
are also 5 marinas and 28 small-boat launching ramps, all 
open to public use. The facilities serve slack-water navigation 
to Snake River Mile 140, the site of Lewiston, ID. That slackwater 
reaches the Lewiston, ID-Clarkston, WA area since 
the lake behind Lower Granite Dam was filled in February 
1975. 
Operations during fiscal year. See individual report for Ice 
Harbor, Lower Monumental, Little Goose, and Lower Granite 
Locks and Dams. On Snake River from Lewiston, ID, to 
Johnson Bar Landing, reconnaissance and condition surveys 
were conducted and survey markers were maintained. Fiscal 
year costs were $7,056. 
General Investigations 
19. SURVEYS 
The Water Resources Development Act of 1986 authorized 
the Corps to operate and maintain a system of non-federal 
levees along the Snake River in the vicinity of Jackson 
Hole, WY. A draft reconnaissance study of the potential for 
improving the system with levee raises, extensions, or relocations 
was completed in FY 90. The final reconnaissance study 
was combined with the Jackson Hole Restoration study which 
will be completed in FY93. A combined flood protection and 
restoration feasibility study is expected to start in FY93. 
A reconnaissance study of a proposal to lower the Tri-Cities 
Levees at Kennewick, Pasco and Richland, WA was completed. 
The levees were built by the Corps as part of the Mc- 
Nary Lock and Dam in the 1950's. Consequent upstream 
storage development may provide an opportunity to reduce 
levee heights for the purpose of land enhancement and recreation. 
It was determined that there was not presently a Federal 
interest in lowering levees. However, locals may do so at 
their cost. 
A reconnaissance study of the Walla Walla River Basin, 
Washington and Oregon was completed in April 1992. The 
study focused primarily on flood damage and prevention. 
However, local interests requested consideration be given to 
other water resource needs including M&I water supply, irrigation, 
water-based recreation, and restoration of spring chinook 
salmon and steelhead trout runs. Future studies of 
water respource development in the Walla Walla basin were 
not recommended at this time. 
Jackson Hole River and Wetland Restoration and Flood 
Control reconnaissance study was initiated to restore fish and 
wildlife habitat in the 500-year floodplain of the leveed reach 
of the Snake and Gros Ventre Rivers at Jackson Hole, WY. 
The study will evaluate losses resulting from levee construction 
over the past 30 years and determine restoration measures 
to compensate for these losses. 
The Energy and Water Development Act, Public Law 
102-104 authorized a study in cooperation with the Port of 
Walla Walla, Washington, for disposition of the current 
Walla Walla District Headquarters. The study was completed 
in September and forwarded to North Pacific Division 
for comments and review.We participated in the Columbia 
River and Tributary Study, a survey directed by the North Pacific 
Division. 
Total cost of surveys was $926,685 for FY 92, including: 
flood control studies ($698,676); special studies including Soil 
Conservation Service, Bureau of Reclamation, River Basin 
and Regional Planning Commissions, and Cooperation with 
States, ($24,229), Special Investigations, Inter Agency Water 
Resource Development and FERC Licensing Activities, and 
North American Waterfowl Management Plan, ($111,014) 
and District Disposition Study ($92,766).. 
20. COLLECTION AND STUDY OF BASIC 
DATA 
During the fiscal year, flood hazard data for a number of 
locations in the District were collected and analyzed. Flood 
information was provided to several Federal agencies, to the 
States of Idaho, Oregon, and Washington, to various cities 
and counties in those states, and to some private organizations. 
Total cost of collection and study of basic data during fiscal 
year was $108,477 which included: flood plain management 
services ($20,585), flood warning system ($6,403), technical 
services, ($76,874), and quick responses ($4,615). 
21. PRECONSTRUCTION, ENGINEERING 
AND DESIGN 
Little Wood River Project, Vicinity Gooding and Shoshone, 
ID. 
The Little Wood River Project was authorized by the 
Water Resource Development Act of 1986. The proposed 
project would have consisted of a diversion channel and two 
ponding facilities to divert floodflows from the Little Wood 
- 39-8 -

WALLA WALLA, WASHINGTON DISTRICT 
River into adjacent lava fields via the Dietrich and Milner- 
Gooding Canals for the purpose of reducing flood damages in 
the Gooding and Shoshone, ID vicinities. As a result of lack 
of local sponsorship, the project is being terminated. A limited 
reevaluation paper was prepared and submitted to 
higher authority.. 
Preconstruction engineering and design activities were initiated 
in FY 1990 to review and update the project formulation 
development for the 1976 feasibility report. A coordination 
meeting was held in Gooding, ID, on 29 May 1991 with 
the project sponsor. At that meeting, the sponsor indicated 
that they no longer have financial capability to act as project 
sponsor. As a result, the project is being terminated pending 
completion of a reevaluation report documenting the reformation 
studies completed to date. 
FY 92 costs were $24,994.06. 
McNary Lock and Dam (Second Powerhouse), OR and WA 
The McNary Second Powerhouse project, with the exception 
of levee beautification of the existing levees adjacent to 
Richland, Pasco, and Kennewick, WA, was automatically 
deauthorized on 16 November 1991, under Section 1001, 
PL99-362. The levee beautification portion of the project 
was reauthorized by the Water Resource Development Act 
of 1990. 
Zintel Canyon Dam, WA 
The project consists of a roller compacted concrete dam 90 
feet high with uncontrolled spillway and a fixed release outlet 
works that will create a detention reservoir of 1,260 acre-feet 
of capacity. The storage comprises 860 acre-feet for flood 
control and 400 acre-feet for sediment. In addition, the project 
also includes a conduit with a capacity of 400 cfs and a 
dike plug will be installed across the Union Pacific Railroad 
to protect downtown Kennewick, WA, when major floods occur. 
The plan of improvement will provide protection against 
heavy rainfall, snowmelt, and thunderstorm floods to the city 
of Kennewick, WA. 
Reevaluation of the project economics due to hydrology 
modifications resulted in a revised General Design Memo 
No. 2 and a Post-Authorization Change Report. The GDM 
was approved by the Washington Level Review Board on 
January 24, 1990. The Post-Authorization Change Report 
which reduced the flood control storage of the authorized 
project was approved March 5, 1990. FY 92 costs were 
$4,860,000 for construction of the dam and channel contracts.. 
The current total estimated Federal and Non-Federal project 
cost is $9,700,000. The estimated Federal cost is 
$7,275,000. 
Local cooperation. Non-Federal sponsors, city of Kennewick, 
Washington, shall pay 25 percent of the total project 
cost or an estimated $2,425,000. 
- 39-9 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 39-A COST AND FINANCIAL STATEMENT 
See 
Section 
In Total to 
Text Project Funding FY89 FY 90 FY91 FY 92 Sep. 30,1992 
6. Jackson Hole, WY New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Contrib. 
Cost 
7. Lucky Peak Lake, ID New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
8. Mill Creek Lake, WA New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab 
Approp. 
Cost 
10. Columbia River Juvenile Fish New Work 
Mitigation Program Approp. 
Cost 
11. Dworshak Dam & New Work 
Reservoir, ID Approp. 
Cost 
Maint 
Approp. 
Cost 
12. Ice Harbor Lock New Work 
& Dam,WA Approp. 
Cost 
Maint. 
Approp. 
Cost 
13. Little Goose Lock New Work 
& Dam, WA Approp. 
Cost 
Maint. 
Approp. 
Cost 
14. Lower Granite Lock New Work 
& Dam, WA Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint 
Contrib. 
Cost 
- 45,000 50,000 
- 41,075 34,120 
20,000 379,000 
50,833 139,306 
777,500 493,000 
668,270 713,204 
-- 77,205 
--- 77,205 
852,000 784,014 
1,068,450 761,029 
1,047,550 853,797 
1,046,431 799,866 
1,974 24 
42,661 
42,660 
634,800 1,221,500 
734,478 1,128,878 
511,700 531,000 
553,930 538,305 
2,483,270 
2,463,390 
1,849,500 
1,720,780 ' 
119,866 ' 
119,865 
19,652,081 2 
19,652,081 2 
16,336,865 * 
16,237,845 3 
2,258,495 4 
2,258,495 4 
10,533,940 
10,511,009 
8,500 17,714,107 
-1 8,500 17,714,102 
- 21,136,000 28,1 
- - 20,617,366 27,7 
399 - - 
6,178,520 6,408,122 
6,507,158 6,102,810 
690,000 99,000 
248,487 387,310 
7,346,305 5,358,025 
7,876,699 5,169,866 
4,963,000 4,043,000 
6,391,061 5,071,935 
3,704,800 3,711,324 
4,257,639 3,572,515 
-563,000 1,958,000 
3,781,755 1,997,535 
7,770,300 5,547,966 
8,177,073 5,310,080 
6,365,300 7,8( 
6,534,885 7,74 
153,202 
6,806,900 8,0 
6,474,349 8,33 
543,004 
4,290,400 5,65 
3,883,098 5,19 
1,257,307 
5,330,900 8,42 
5,436,731 8,46 
52,000 
23,497 
49,288,000 
48,349,863 
5,000 329,528,296 6 
5,000 329,528,296 
D2,200 80,080,8576 
48,991 87,758,198 6 
- 168,029,757w 
168,029,757w 
19,500 89,026,4048 
30,550 88,690,091 " 
- 233,361,022 ' 
- 233,361,022 
55,000 66,973,129 10 
P1,554 65,951,172 10 
- 374,836,315 11 
- 374,836,315 " 
!1,000 89,302,468 12 
14,239 89,109,068 12 
-20,000 
- 20,000 
- 39-10 -

TABLE 39-A 
(Continued) 
WALLA WALLA, WASHINGTON DISTRICT 
COST AND FINANCIAL STATEMENT 
See 
Section 
In Total to 
Text Project Funding FY89 FY 90 FY91 FY 92 Sep. 30,1992 
15. Lower Monumental New Work 
Lock & Dam, WA Approp. 2,120,00019 99,000 -- - 238,612,73213 
Cost 363,114 1,335,148 540,738 - 238,612,732 13 
Maint 
Approp. 5,837,300 3,961,605 3,930,300 6,380,000 66,965,437 14 
Cost 7,270,127 3,760,855 4,001,616 4,522,986 64,938,561 14 
16. Lower Snake Fish & Wildlife New work 
Compensation, ID, OR & WA Approp. 8,687,000 11,472,832 27,902,000 6,813,500 195,425,241 
Cost 8,567,973 9,877,498 28,988,737 7,094,430 195,029,651 
(Contributed Funds) New Work 
Contrib. - - - - 223,965 
Cost - - - - 223,965 
17. McNary Lock & Dam, - New Work 
Lake Wallula, OR & WA Approp. 1,180,000 2,578,000 - - 326,293,105 16 
Cost 1,022,277 2,231,198 505,723 - 326,293,105 '1 
Maint. 
Approp 8,865,480 9,351,148 8,781,700 9,479,000 186,648,963 16 
Cost 9,331,470 8,897,860 9,076,330 9,501,861 186,277,692 18 
(Contributed Funds) Maint. 
Contrib. - - - - 43,707 
Cost - - - - 43,707 
18. Snake RiverDownstream New Work 
from Johnson Bar Landing Approp. 7,210,000'1 6,199,000 13,333,000 16,110,000 2 1,044,717,589 17 
OR, WA & ID Cost 10,784,417 8,791,928 15,630,347 15,893,070 20 1,044,303,754 17 
Maint. 
Approp. 24,662,405 18,590,284 20,358,500 28,494,500 312,866,377 18 
Cost 27,588,435 17,815,413 19,799,683 26,516,385 309,270,43118 
1. $39,000 of cost sharing funds from county were received in FY 
90, but were not expended until FY 91. 
2. Includes $570,831 appropriated and expended for Code 710, 
Recreation Facilities at Completed Projects. 
3. Includes $66,700 allotted and expended under Maintenance and 
Operation of Dams and Other Improvements of Navigable 
Waters. 
4. Excludes $80,000 contributed funds, but includes $96,340 
appropriated and expended for Code 710, Recreation 
Facilities at Completed Projects. 
5. Includes $2,046,100 regular project construction 
funds appropriated for and expended by Department of Interior 
in Fiscal Years 1969 through 1972 for hatchery operations. 
Includes $655,000 appropriated and expended for additional unit. 
6.Includes $20,137,847 regular project operation and maintenance 
funds expended by Department of Interior starting FY 1972 for 
hatchery operations. FY 72-78 funds of $6,097,000 were charged 
to project as a cost, but not as an expenditure for accounting 
purposes. Includes allotted and expended under Special 
Recreation Use Fees. Includes funds allotted and expended under 
Maintenance and Operation of Dams and Other Improvements 
of Navigable Waters. 
7. Excludes $82,500 contributed for artificial spawning channel. 
Includes $36,748,021 appropriated and expended for additional 
Units 4 through 6. Includes $914,256 appropriated and expended 
for Code 710, Recreation Facilities at Completed Projects. 
Includes $789,000 appropriated and $788,999 expended for 
Columbia River Juvenile Fish Mitigation Program. 
8. Includes $48,919 allotted and expended under Special 
Recreation Use Fees; $641,063 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
9. Includes $60,941,807 appropriated and expended for additional 
Units 4 through 6. Includes $12,006,000 appropriated and 
$12,006,000 expended for Columbia River Juvenile Fish Mitigation 
Program. 
10. Includes $621,063 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
11. Includes $46,212,534 appropriated and expended for additional 
Units 4 through 6. Excludes $405,819 contributed funds on lock 
and dam project. Includes $63,800 appropriated and expended for 
Code 710, Recreation Facilities at completed projects. Includes 
$10,645,966 appropriated and $7,056,001 expended for Columbia 
River Juvenile Fish Mitigation Program. 
12. Includes $338,163 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
13. Includes $51,661,371 appropriated and expended for additional 
Units 4 through 6. Includes $2,239,000 appropriated and 
$2,239,000 expended for Columbia River Juvenile Fish Mitigation 
Program. 
14. Includes $372,376 appropriated and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
15. Includes $1,976,586 appropriated and expended for Code 710, 
Recreation Facilities at Completed Projects. Includes $3,778,000 
appropriated and $3,778,000 expended for Columbia River 
Juvenile Fish Mitigation Program. 
16. Includes $28,851 allotted and expended under Special 
Recreation Use Fees and $1,035,860 allotted and expended under 
Maintenance and Operation of Dams and Other Improvements of 
Navigable Waters. 
17. Includes $400,150 for new work on previous projects (Pasco to 
Lewiston), and $34,613 for new work appropriation used for 
maintenance prior to 1953. Excludes $167,500 contributed funds 
- 39-11 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
for new work consisting of $85,000 for new work on existing 
projects (Pasco to Riparia), plus $82,500 for new work on existing 
artificial spawning channel. 
18. Includes $186,570 appropriated and expended for maintenance 
of previous projects (Pasco to Lewiston) and $408,019 
appropriated and $390,619 expended open river Pasco to 
TABLE 39-B 
Lewiston and Lewiston to Johnson Bar Landing. 
19. Adjusted to correct FY89 appropriation from 2,140,000 to 
2,120,000. 
20. This does not include the appropriations and cost from the 
mitigation analysis under the Columbia River juvenile fish 
program which will be allocated at the conclusion of the analysis. 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
1. 
81st Cong., 2nd Sess. 
COLUMBIA RIVER BASIN, LOCAL FLOOD 
PROTECTION PROJECTS 
Blackfoot Area, Snake River, ID. Levee left bank. H. Doc 531, 
Blackfoot River, ID. Levees, channel improvement, and 
rectification works. 
Boise Valley, Boise River, ID. Channel improvement and 
enlargement, levees, and revetments in Ada County. Canyon 
County unit was deauthorized April 18, 1967. Ada County 
unit was deauthorized in 1986. 
Camas Creek, ID. Channel deepening and rectification of a 
20-mile reach of Camas Creek. Deauthorized in 1965. 
Gooding Area, Little Wood River, ID. Channel improvement. 
Grande Ronde Valley, OR. Levees and channel clearing, 
straightening and realignment; would complement stream 
regulation by upstream storage projects. Deauthorized in 1986. 
Heise-Roberts Extension, Snake River, ID. Channel clearing 
and rectification, levees, and bank protection. Henrys Fork 
Unit deauthorized in 1986. 
Jackson Hole, Snake River, WY. Flood protection. 
Kendrick, Potlatch River, ID. Revetted levee. 
Little Wood River, ID. Flood protection in immediate area. 
Deauthorized in 1965. 
Malheur River, OR. Channel rectification, levees, and bank 
protection at Vale. Willow Creek unit was deauthorized 
October 14, 1969. 
Mud Lake, ID, Idaho Falls Area. Flood protection. Deauthorized in 1990. 
Palouse River, WA. Flood protection for urban and rural 
areas at Garfield and near Malden. Deauthorized in 1986. 
Payette Valley, ID. Channel rectification, levees, and bank 
protection along 38 miles of Payette River below Black 
Canyon Dam. Payette Valley was deauthorized October 3, 1978. 
Portneuf River and Marsh Creek, ID. Concrete-lined channel 
through Pocatello. Inkom-Marsh Creek unit was deauthorized 
October 14, 1969. 
Shelley Area, Snake River, ID. Bank protection. 
South Fork Clearwater River, ID. Emergency construction of 
levees and revetments. Deauthorized in 1986. 
Teton River, ID. Flood protection. Deauthorized in 1986. 
Tomanovich-Salmon City, Salmon, ID. Channel improvement. 
Weiser River, Weiser Area, ID. Intermittent channel 
realignment and improvement, levees, and bank protection, 
lower river area. Project deauthorized in 1990. 
Whitebird Creek, ID. Flood protection. Deauthorized in 1986. 
CATHERINE CREEK LAKE, OR 
Flood control and multipurpose dam on Catherine Creek H. Doc. 280, 
near Union, OR. Project deauthorized 1990. Oct 27, 1965 
CATHERINE CREEK, OR 
Organic debris removal along Catherine Creek. Sec 208, P.LI 
by Chief Eng 
- 39-12 - 
May 17, 1950 
Oct 27, 1965 
Sep 24, 1954 
AUTHORIZING LEGISLATION 
89th Cong. 1st Sess. 
83-780 Authorized 
ineers Sep. 3, 1985 
2. 
3.

TABLE 39-B 
(Continued) 
See Date 
Section Authorizing 
in Text Act 
WALLA WALLA, WASHINGTON DISTRICT 
AUTHORIZING LEGISLATION 
Project and Work Authorized Documents 
CLEAR & BURNT RIVER, OR 
Construction of riprap bank protection at city of 
Huntington Waste Water Lagoon. 
COLFAX, PALOUSE RIVER, WA 
Provides for flood control works in vicinity of and through 
Colfax, WA, by channel enlargement and modification, 
levees, floodwalls, revetments, and modification of railroad 
bridges. 
LUCKY PEAK LAKE, ID 
Dam for flood control, irrigation, and recreation. 
Second outlet for streamflow maintenance. 
Deauthorized in 1990. 
Construction, operation, and maintenance of recreation 
facilities. 
MILL CREEK LAKE, WALLA WALLA, WA 
Off-stream storage project upstream fromWalla Walla. 
Channel improvement through Walla Walla; concretelined 
channel. 
Redesignation of reservoir to the Virgil B. Bennington Lake 
OWYHEE RIVER, OR 
Gravel, brush and small tree removal from 12 miles of 
Owyhee River. 
Sec. 14, P.L 79-526 
Authorized by Chief of Engineers 
Jul 10, 1985 
Flood Control Act of 1944 
H. Doc 888, 77th Cong., 2nd Sess. 
P.L 79-526, Chief of 
Engineers Report dated 
May 13, 1946 
P.L 94-587 
Sec. 4, Flood Control Act of 1944 
H. Doc. 578, 75th 
Cong., 3d Sess. 
H. Doc. 719, 76th Cong. 
Sec. 377, P.L. 77-228, Cong., 3rd Sess. 
Sec. 118. P.L. 102-580 102nd Cong. 
Sec. 208, P.L. 83-780 
Authorized by Chief of Engineers 
Feb. 11, 1985. 
Jul 24, 1946 
Oct 22, 1976 
Dec 22, 1944 
as amended 
Jun 28, 1938 
as amended 
Aug 18, 1941 
Oct 31, 1992 
Sep 24, 1954 
as amended 
Jul. 19, 1988 
Jul 3, 1958 
Oct 23, 1958 
Aug 15, 1963 
Oct 23, 1962 
Mar 2, 1945 
Dec 22, 1944 
as amended 
Oct 22, 1976 
Dec 29, 1981 
Jul 30, 1983 
Mar 2, 1945 
Dec 31, 1970 
Mar 2, 1945 
- 39-13 - 
Jul 24, 1946 
Dec 22, 1944 
10. 
11. 
12. 
14. 
15. 
COLUMBIA RIVER JUVENILE FISH 
MITIGATION PROGRAM 
Design, test and construction of fish bypass facilities at P.L. 100-371 
Lower Monumental, Little Goose, Lower Granite and 
McNary dams. 
(BRUCES EDDY) DWORSHAK DAM AND RESERVOIR, ID 
Preparation of detailed plans. S. Doc 51, 84th Cong., 1st Sess. 
Bruces Eddy dam and reservoir for flood control, H. Doc. 403, 87th. P.L 87-874 
navigation, power, recreation, and area redevelopment. Cong., 2nd Sess. 
Redesignation of project as Dworshak Dam and Reservoir. P.L. 88-96 
Dworshak Added Units 4, 5 and 6, ID. Units 5 and 6 were P.L. 87-874 
deauthorized in FY 90. 
ICE HARBOR LOCK AND DAM - LAKE SACAJAWEA, WA 
Unit 1 of 4, Lower Snake River project. Lock and dam for H. Doc. 704, 75th 
navigation, power, recreation, and incidental irrigation. Cong., 3rd Sess. 
Construction, operation, and maintenance of recreation Sec. 4, Flood Control of 1944 
facilities. 
LEWISTON-CLARKSTON BRIDGE, ID AND WA 
Four-lane highway bridge and approaches. P.L 94-587 
Increase of authorized amount to $23,200,000. P.L 97-140 
Approach roadway from bridge to Sixteenth Avenue in P.L 98-63 
Clarkston, WA. Increase of authorized amount to $24,000,000. 
LITTLE GOOSE LOCK AND DAM - LAKE BRYAN, WA 
Unit 3 of 4, Lower Snake River project. Lock and dam for H. Doc. 704, 75th Cong., 3rd Sess. 
navigation, power, recreation, and incidental irrigation. 
Designation of reservoir as Lake Bryan. P. L 91-638 
LOWER GRANITE LOCK AND DAM, WA 
Unit 4 of 4, Lower Snake River project. Lock and H. Doc. 704, 75th Cong., 3rd Sess. 
dam for navigation, power, recreation, and incidental irrigation. 
16. 
17. 
18. 
19.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 39-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
20. 
21. 
Mar 2, 1945 
May 25, 1978 
Oct 22, 1976 
as ammended 
Nov. 17, 1986 
2. 
Mar 2, 1945 
Dec 22, 1944 
as amended 
Nov 17, 1986 
23. 
Jun 13, 1902 
Jun 25, 1910 
Aug 30, 1935 
Mar 2, 1945 
Table E Aug 18, 1941 
Table E Dec 22, 1944 
Table E Jul 11, 1956 
Table E Oct 23, 1962 
Table E Nov 7, 1966 
LOWER MONUMENTAL LOCK AND DAM - 
LAKE HERBERT G. WEST, WA 
Unit 2 of 4, Lower Snake River project. Lock and dam for 
navigation, power, recreation, and incidental irrigation. 
Designation of reservoir as Lake Herbert G. West. 
LOWER SNAKE RIVER FISH & WILDLIFE 
COMPENSATION PLAN, WA, OR, AND ID 
Fish hatcheries and replacement of wildlife habitat. 
Changes to land acquisition authority. 
McNARY LOCK AND DAM - 
LAKE WALLULA, OR AND WA 
Lock and dam for navigation, power, recreation, and 
irrigation 
Construction, operation, and maintenance of 
recreation facilities. 
Construction, operation and maintenance of a second 
powerhouse. 
NcMary Second Powerhouse automatically deauthorized 
Nov. 16, 1991 
SNAKE RIVER MOUTH TO JOHNSON BAR, OR, 
WA, AND ID 
Open-river navigation Riparia to Pittsburg Landing. 
Mouth to Riparia. 
Pittsburg Landing to Johnson Bar. 
H. Doc. 704, 75th Cong., 3rd Sess. 
P. L 95-285 
P.L 94-587 
H.R. 6-P.L99-662 
H. Doc. 704., 75th Cong., 3rd Sess. 
Sec. 4, Flood Control Act of 1944 
H.R. 6- P.L 99-662 
Sec. 1001, P.L 99-362 
H. Doc. 127, 56th Cong., 2nd. Sess. 
H. Doc. 411, 55th Cong., 2nd Sess. 
Rivers and Harbors Committee 
Doc. 25, 72nd Cong., 1st Sess. 
Supercedes previous legislation mouth to Lewiston, ID only. H. Doc. 704, 75th 
See Ice Harbor, Lower Monumental, Little Goose, and Cong., 2d Sess. 
Lower Granite Locks and Dams. 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
Dayton, Touchet River, WA. Flood protection. H. Doc. 662, 76th Cong., 3rd Sess. 
Milton-Freewater, Walla Walla River, OR.Flood Protection. H. Doc. 719, 76th Cong., 3rd Sess. 
Heise-Roberts Area, Snake River, ID. H. Doc 452, 77th Cong., 1st Sess. 
Channel improvement. 
Malheur Improvement District, Snake River, OR. 
Flood protection. 
Pullman, Palouse River, WA. Flood protection. 
Deauthorized in 1986. 
Esquatzel Coulee, Connell, WA. Levees and protective work P.L. 84-685 
Lower Dry Creek, Lowden, WA. Channel improvement. 
Mission and Lapwai Creeks, ID. Construction of levee. 
Bear Creek, Kendrick, ID. Channel improvement. P.L 87-874 
Lapwai Creek Culdesac, ID. Construct left bank levee. 
Lyman Creek near Rexburg, ID. Channelization. 
Tucannon River, Camp Wooten, WA. Levee and channel work. 
Blackfoot Reservoir, Blackfoot River, ID. Modification to 
increase spillway capacity. Deauthorized in 1986. 
Ririe Lake, Willow Creek, ID. Storage for flood control. 
Grande Ronde Lake, OR. Flood control, irrigation, water P.L 89-298 
supply, anadromous fish, downstream and resident trout 
fishery, recreation and downstream power. Deauthorized 
in 1986. 
Zintel Canyon Dam, WA. Local protection reservoir to provide 
flood protection to portions of the city of Kennewick, WA. 
Cottonwood Creek Dam, ID. Protection to highly- P.L. 89-789 
developed urban and suburban areas against flash floods. 
Deauthorized in 1986. 
- 39-14 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-B AUTHORIZING LEGISLATION 
(Continued) 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
Stuart Gulch Dam, ID. Protection to highly-developed urban 
and suburban areas against flash floods. Deauthorized 
in 1979. 
9. & Table E Nov 17, 1986 Jackson Hole, WY. Flood control protection by channel P.L 99-662 
improvement consisting of channel rectification, levees, 
and revetment along Snake River in vicinity of Wilson, 
Wyoming. Also operation, maintenance, modifications, and 
additions are Federal responsibility. 
Little Wood River, ID. Flood protection 
TABLE 39-C OTHER AUTHORIZED 
NAVIGATION PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Columbia River and Tributaries Completed 1968 1,851,195 - 
above Celilo Falls to Kennewick, WA1 
1. Obviated by The Dalles, John Day, and McNary projects. 
TABLE 39-E OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30. 1992 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Asotin Creek, Asotin, ID 1 
Bear Creek, Kendrick, ID 1 
Big Wood River, IDs 
Boise River, IDs 
Catherine Creek, OR 
Catherine Creek Lake, OR 
Clear and Blurnt River, OR 
Colfax, Palouse River, WA 
Connell, WA 1 
Cottonwood Creek Community Church, Culdesac, ID2 
Dayton, Touchet River, WA 
Dry Creek, WA1 
Esquatzel Coulee, Connell, WA1 
Completed 
Completed 
Completed 
Completed 
Completed 
Deferred 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1951 
1970 
1985 
1985 
1990 
1978 
1990 
1990 
1967 
1984 
1966 
1961 
1967 
12,019 
133,518 
170,000 
236,500 
28,800 
1,552,000 
99,500 
5,810,240 
60,000 
23,400 
380,617 
384,426 
232,792 
- 39-15 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 39-E 
(Continued) 
OTHER AUTHORIZED FLOOD 
CONTROL PROJECTS 
For Last Cost to Sep. 30. 1992 
Full Report Operation 
See Annual and 
Project Status Report For Construction Maintenance 
Esquatzel Coulee, Mesa, WA1 
Gooding Area, ID 1 
Graves Creek, ID1 
Heise-Roberts Area, Snake River, ID 
Jackson Hole, Snake River, WY 
Lapwai Creek, Culdesac, ID1 
Lava Hot Springs, Portneuf River, ID' 
Little Wood River, ID 6 
Lower Dry Creek, Lowden, WA1 
Lyman Creek, ID1 
Malheur Lake Project, OR 
Malheur Improvement District, Snake River, OR 
Milton-Freewater, Walla Walla River, OR3 
Mission and Lapwai Creeks, ID1 
Orofino Creek & Clearwater River, Orofino, ID2 
Owyhee River, OR 
Rapid Creek, IDs 
Pataha Creek, Pomeroy, WA2 
Payette River, Emmett Sewage Lagoon, ID2 
Riverside Area, Pasco, WA1 
Ririe Lake, ID 
Sewage Lagoon, Vale, OR2 
Shobe Canyon, Heppner, OR1 
Snake River, Blackfoot, ID' 
Snake River, Heise Bridge Location, ID2 
Snake River, Stevens, Blackfoot, ID 1 
South Fork, Boise River, ID5 
South Fork Clearwater River, Kooskia-Stites, ID 
Tomanovich-Salmon City, ID 1 
Touchet River, Waitsburg, WA 1 
Tucannon River, Wooten, WA1 
Umatilla River, OR1 
Wallowa River, Weaver Bridge, OR2 
Weiser River, IDs 
Willow Creek, ID1 
Willow Creek Lake, OR 
Yakima River, West Richland, WA1 ,4 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Active 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1969 
1954 
1953 
1955 
1978 
1972 
1973 
1990 
1972 
1971 
1990 
1957 
1968 
1965 
1949 
1990 
1985 
1977 
1967 
1972 
1983 
1985 
1970 
1980 
1952 
1968 
1985 
1973 
1955 
1973 
1971 
1961 
1960 
1985 
1963 
1985 
1964 
2,665 
59,167 
75,469 
1,575,838 
2,388,270 
176,833 
113,296 
235,025 
17,592 
230,315 
2,561,136 
55,894 
1,786,753 
54,538 
23,050 
69,316 
19,500 
110,815 
39,172 
28,839 
39,677,448 
75,000 
5,000 
131,700 
8,501 
32,425 
44,400 
61,055 
128,635 
72,140 
73,932 
161,540 
16,118 
106,900 
976 
37,168,114 
229,890 
1. Authorized by Chief of Engineers pursuant to Section 205, PL 
80-858. 
2. Authorized by Chief of Engineers pursuant to Section 14, PL 
79-526. 
3. Exclusive of $6,300 contributed funds. 
4. Exclusive of $9,000 contributed funds. 
5. Authorized by Chief of Engineers pursuant to Section 208, PL 
83-780. 
6. Authorized by Chief of Engineers pursuant to PL99-662. No 
funds authorized until FY90. 
7. Exclusive of $853,712 contributed funds. 
-39-16 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-F OTHER AUTHORIZED MULTIPURPOSE PROJECTS, 
INCLUDING POWER 
For Last Cost to Sep,. 30, 1992 
Full report Operation 
See Annual and 
Project Report For Construction Maintenance 
Lewiston-Clarkston Bridge. ID 1990 23,085,832 
TABLE 39-G DEAUTHORIZED PROJECTS 
For Last 
Full report Federal Contributed 
See Annual Date Funds Funds 
Project Report For Deauthorized Expended Expended 
Asotin Dam, Snake River, ID & WA 1964 1975 - 
Blackfoot Reservoir, ID 1980 1986 267,626 
Boise Valley, ID 
Ada County Unit 1963 1986 46,084 - 
Canyon County Unit 1963 1967 10,600 - 
Camas Creek, ID 1960 1965 9,080 - 
Catherine Creek Lake, OR 1978 1990 1,552,000 - 
Cottonwood Creek Dam, Boise, ID 1972 1986 183,100 - 
Dworshak Units 5 and 6, ID 1990 1990 655,000 - 
Grande Ronde Lake, OR 1966 1986 - - 
Grande Ronde Valley, OR 1958 1986 102,458 - 
Heise-Roberts Extension, ID 
Henrys Fork Unit 1968 1986 27,800 - 
Little Wood River, ID 1960 1965 21,334 - 
Lower Walla Walla River, WA 1953 1986 4,000 - 
Lucky Peak 2nd Outlet, ID 1988 1990 - - 
Malheur River, OR 
Willow Creek Unit 1961 1969 13,000 - 
McNary Second Powerhouse, OR & WA 1991 1991 - - 
Mill Creek, WA 1958 1977 3,537 - 
Mud Lake Area, ID 1957 1990 5,994 - 
Palouse River, WA 1958 1986 2,000 - 
Payette Valley, ID 1960 1978 23,178 - 
Portneuf River, Inkom-Marsh Creek, ID 1969 1969 - - 
Pullman, Palouse River, WA 1964 1986 99,540 - 
S.Fork Clearwater River, ID 1973 1986 3,899 - 
Stuart Gulch Dam, Boise, ID 1974 1979 234,100 - 
Teton River, ID 1955 1986 10,387 - 
Touchet River, WA 1957 1977 11,198 - 
Weiser River, Weiser Area, ID 1960 1990 112,757 - 
Whitebird Creek, ID 1957 1986 1,896 - 
- 39-17 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 39-H COLUMBIA RIVER BASIN, LOCAL FLOOD PROTECTION 
PROJECTS (See Section 2 of Text) 
Estimated 
Federal Cost to 
Project Status Cost Sep. 30, 1992 
Blackfoot Area, Snake River, ID Completed - 42,796 
Blackfoot River, ID Completed - 391,143 
Heise-Roberts Extension, ID Snake River Unit Completed - 3,375,158 
Kendrick, Potlatch River, ID Completed - 59,942 
Malheur River, OR Vale Unit Completed - 325,581 
Mud Lake, ID Inactive 1,187,000 5,996 
Portneuf River and Marsh Creek, ID Pocatello Unit Completed - 6,456,032' 
Shelley Area, Snake River, ID Completed - 32,335 
Weiser River, ID Deferred 1,565,000 37,757 
Weiser River, ID Cambridge-Midvale Deferred - 75,000 
TOTAL 10,801,740 
1. Exclusive of $36,800 contributed funds. 
TABLE 39-I INSPECTION OF COMPLETED FLOOD CONTROL PROJECTS 
(See Section 7 of Text) 
Clearwater River, ID July 1992 
Lyman Creek, ID August 1992 
Mill Creek, WA October 1992 
Palouse River, WA June 1992 
Portneuf River, ID August 1992 
Potlatch River, ID July1992 
Snake River, ID August 1992 
Touchet River, WA August 1992 
Tucannon River, WA July 1992 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
Project 
Dworshak Dam and 
Reservoir, ID 
(See Section 15 of Text) 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Concrete Gravity 
September 1974 
150,500 cfs 
1613 feet 
Tainter 
50 ft. by 55 ft. 
2 
428 feet
3 
2 @ 90,000 kw 
1 @ 220,000 kw 
400,000 kw 
- 39-18 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
Ice Harbor Lock and Dam, WA 
(See Section 16 of Text) 
Space for additional 
Rating, Each 
Total Potential Capacity 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Flood Control Storage 
Lake Length 
Lake Water Surface Area at Elevation 1600 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 440 
Navigation Channel, Depth by Width 
Length of Shoreline 
3 
3 @ 220,000 kw 
1,060,000 kw 
150 feet 
March 1973 
1600-1445 feet 
1605 feet 
2,000,000 ac.-ft. 
53 miles 
17,090 acres 
175 miles 
86 feet 
675 feet 
97 feet 
100 feet 
103 feet 
15 feet 
May 1962 
Concrete Gravity 
January 1962 
850,000 cfs 
391 feet 
Radial 
50 ft. by 51 ft. 
10 
671 feet
6 
3 @ 90,000 kw 
3 @ 111,000 kw 
603,000 kw 
226 feet 
December 1961 
440-437 feet 
446 feet 
31.9 miles 
9,200 acres 
14 ft. by 250 ft. 
80 miles 
- 39-19 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
Little Goose Lock and Dam, WA 
(See Section 18 of Text) 
Lower Granite Lock and Dam, WA 
(See Section 19 of Text) 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
86 feet 
675 feet 
93 feet 
98 feet 
101 feet 
15 feet 
May 1970 
Concrete Gravity 
January 1970 
850,000 cfs 
581 feet 
Radial 
50 ft. by 60 ft. 
8 
656 feet 
243 feet
6 
135,000 kw 
810,000 kw 
244 feet 
March 1970 
638-633 feet 
646.5 feet 
37.2 miles 
10,025 acres 
14 ft. by 250 ft. 
92 miles 
86 feet 
675 feet 
95 feet 
100 feet 
105 feet 
15 feet 
May 1975 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
Concrete Gravity 
February 1975 
850,000 cfs 
581 feet 
Radial 
50 ft. by 60.5 ft. 
8 
- 39-20 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
Lower Monumental Lock and 
Dam, WA (See Section 20 of Text) 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 738 
Navigation Channel, Depth by Width 
Length of Shoreline 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift: 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Width 
Generating Units: 
Number Installed 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 540 
Navigation Channel, Depth by Width 
Length of Shoreline 
738-733 feet 
746.5 feet 
38 miles 
8,900 acres 
14 ft. by 250 ft. 
91 miles 
86 feet 
675 feet 
97 feet 
98 feet 
103 feet 
15 feet 
April 1969 
Concrete Gravity 
March 1969 
850,000 cfs 
483 feet 
Radial 
50 ft. by 61 ft.
8 
656 feet 
243 feet 
6 
135,000 kw 
810,000 kw 
242 feet 
May 1969 
540-537 feet 
548 feet 
28.7 miles 
6,590 acres 
14 ft. by 250 ft. 
78 miles 
- 39-21 - 
656 feet 
243 feet 
6 
135,000 kw 
810,000 kw 
246 feet 
April 1975

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 39-J PRINCIPAL DATA CONCERNING 
NAVIGATION LOCK, SPILLWAY DAM, POWERPLANT, AND IMPOUNDMENT 
(Continued) 
Project 
McNary Lock and Dam, OR 
and WA (See Section 22 of Text) 
NAVIGATION LOCK 
Clear Width 
Clear Length 
Lift 
Minimum 
Average 
Maximum 
Minimum Water Depth Over Sills 
Opened to Navigation 
SPILLWAY DAM 
Type of Construction 
Completed 
Maximum Capacity 
Crest Elevation 
Control Gates: 
Type 
Size, Width by Height 
Number 
POWERPLANT 
Length 
Generating Units: 
Number Installed. 
Rating, Each 
Total Capacity Installed 
Maximum Structural Height 
First Power-On-Line 
IMPOUNDMENT 
Elevations: 
Normal Operating Range 
Maximum 
Lake Length 
Lake Water Surface Area at Elevation 340 
Acres Navigation Channel, Depth by Width 
Length of Shoreline 
86 feet 
675 feet 
67 feet 
75 feet 
83 feet 
15 feet 
November 1953 
Concrete Gravity 
October 1953 
2,200,000 cfs 
291 feet 
Vertical Lift 
50 ft. by 51 ft. 
22 
1,348 feet 
14 
70,000 kw 
980,000 kw 
193 feet 
November 1953 
340-335 feet 
356.5 feet 
64 miles 
38,800 
14 ft. by 250 ft. 
242 miles 
- 39-22 -

WALLA WALLA, WASHINGTON DISTRICT 
TABLE 39-K SNAKE RIVER DOWNSTREAM FROM 
JOHNSON BAR LANDING OR, WA, AND ID 
(See Section 23 of Text) 
Estimated 
Cost (Corps New Work Maintenance Percent 
of Engineers to Sep. 30 1992 to Sep. 30, 1992 Com- Constr. 
Project Funds Only) Approp. Cost Approp. Cost pleted Started 
Ice Harbor Lock & Dam 
Initial Project 129,578,480 129,578,480' 129,578,4804 89,026,404 88,690,091 100 FY 57 
Code 710 Recreation Facilities 914,256 914,256 914,256 0 0 100 FY 57 
Power Units 4-6 36,748,021 36,748,021 36,748,021 0 0 100 FY 71 
Fish Bypass Program 27.800.0003 6.392.000 6.204.000 0 0 22 FY 91 
Totals 195,040,757 173,632,7574 173,444,7574 89,026,404 88,690,091 88 
Little Goose Lock & Dam 
Initial Project 160,413,215 160,413,2155 160,413,2156 66,973,129 65,951,172 100 FY 63 
Power Units 4-6 60,941,807 60,941,807 60,941,807 0 0 100 FY 74 
Fish Bypass Program 33.000.0003 14.944.000 14.937.589 0 0 45 FY 89 
Totals 254,355,022 236,299,0225 236,292,6115 66,973,129 65,951,172 92 
Lower Granite Lock & Dam 
Initial Project 321,503,981 321,503,9818 321,503,9796 89,302,468 89,109,068 100 FY 65 
Code 710 Recreation Facilities 63,800 63,800 63,800 0 0 100 FY 84 
Power Units 4-6 46,212,534 46,212,534 46,212,534 0 0 100 FY 74 
Fish Bypass Program 28.200.0003 9.370.000 9.348,085 0 0 33 FY 88 
Totals 395,980,315 377,150,3156 377,128,3986 89,302,468 89,109,068 95 
Lower Monumental Lock & Dam 
Initial Project 184,712,361 184,712,3617 184,712,3617 66,965,437 64,938,561 100 FY 61 
Power Units 4-6 51,661,371 51,661,371 51,661,371 0 0 100 FY 75 
Fish Bypass Program 34.700.0003 20.827.000' 20,629.493 0 0 59 FY 90 
Totals 271,073,732 257,200,7327 257,003,2257 66,965,437 64,938,561 94 
Open River Lewiston to Johnson Bar 
Landing 34,613 34,6131 34,613 408,0192 390,6192 
Open River Pasco to Lewiston 0 0 0 4,350 4,350 
Totals Existing Project 1,116,484,439 1,044,317,439 1,043,903,604 312,679,807 309,083,861 100 
Previous Projects Pasco to Lewiston 400,150 400,150 400,150 186,570 186,570 
Totals Authorized Project 1,116,884,589 1,044,717,5896 1,044,303,7548 312,866,377 309,270,431 
1. New work appropriations used for maintenance prior to 1953. 
2. Includes $19,000 appropriated and $7,056 expended in FY 1992 
for project condition survey cost. 
3. Does not include mitigation analysis. 
4. Includes $203,000 appropriated and $201,931 expended for 
Columbia River Juvenile Mitigation Program. 
5. Includes $370,000 appropriated and $358,589 expended for 
Columbia River Juvenile Mitigation Program. 
6. Includes $1,628,000 appropriated and $1,626,084 expended for 
Columbia River Juvenile Mitigation Program. 
7. Includes $11,132,000 appropriated and $10,949,493 expended 
for Columbia River Juvenile Mitigation Program. 
8. Includes $13,333,000 appropriated and $13,136,097 expended 
for Columbia River Juvenile Mitigation Program. 
9. Adjusted to correct FY91 appropriations from $2,259,000 to 
$2,239,000. 
- 39-23 -

ALASKA DISTRICT* 
This District consists of the State of Alaska. 
IMPROVEMENTS 
Navigation 
1. Anchorage Harbor, AK ..................... 
2. Bethel Small Boat Harbor, AK .............. 
3. Cordova Harbor, AK ...................... 
4. Craig Harbor, AK ......................... 
5. Dillingham Harbor, AK ................... 
6. Homer Harbor, AK ....................... 
7. Metlakatla Harbor, AK ................... .. 
8. Mountain Point, AK ....................... 
9. Ninilchik Harbor, AK ...................... 
10. Nome Harbor, AK ......................... 
11. Project Condition Surveys ................... 
12. St. George, AK ........................... 
13. St. Paul Island Harbor ..................... 
14. Wrangell Harbor, AK .................... 
40-1 
40-2 
40-2 
40-2 
40-2 
40-2 
40-3 
40-3 
40-3 
40-3 
40-4 
40-4 
40-4 
40-4 
Flood Control 
15. Bethel Bank Stabilization, AK ............... 40-5 
16. Chena River Lakes, AK .................... 40-5 
17. Homer Spit Erosion, AK ................... 40-5 
18. Flood Control Work Under 
Special Authorization ...................... 40-5 
19. Inspection of Completed Flood 
Control Project ........................... 40-5 
Navigation 
1. ANCHORAGE HARBOR, AK 
Location. Anchorage is in southcentral Alaska on the 
southeast shore of Knik Arm, north of Turnagain Arm near 
its junction with Cook Inlet. (See NOAA Charts 16660 and 
16664.) 
Existing project. Provides for dredging along a 3,300-foot 
baseline adjacent to the Port of Anchorage dock to a depth of 
36 feet below mean lower low water. Tidal range between 
mean lower low water and mean higher high water is 29.0 feet 
and the extreme range is 42.0 feet. 
Local cooperation. Fully complied with. 
Multiple-Purpose Projects, Including Power 
20. Snettisham, AK.......................... 40-6 
General Investigations 
21. Survey .................................. 40-6 
22. Collection and Study of Basic Data .......... 40-6 
23. Preconstruction, Engineering and Design ..... 40-6 
Tables 
Table 40-A 
Table 40-B 
Table 40-C 
Table 40-D 
Table 40-E 
Table 40-F 
Table 40-G 
Table 40-H 
Table 40-I 
Table 40-J 
Table 40-K 
Cost & Financial Statement ........ 40-7 
Authorizing Legislation ............ 40-9 
Other Authorized Navigation Projects 40-11 
Not Applicable 
Other Authorized Flood 
Control Projects ................ 40-12 
Not Applicable 
Deauthorized Projects ............. 40-12 
Navigation Work Under Special 
Authorization .................... 40-13 
Project Condition Surveys .......... 40-13 
Not Applicable 
Not Applicable 
Terminal facilities. The Port of Anchorage facility consists 
of a POL terminal at the southern end and three general 
cargo terminals northward. The northernmost terminal, 
completed during 1976 and 1977, was outside the Federal 
project limits. Extension of the limits from 2,070 feet northward 
to 3,000 feet was authorized by Public Law 94-587 and 
funded in FY 1978. 
Operations during fiscal year. Maintenance: Dredging was 
accomplished across the entire project during July and 
August 1991. The Municipality of Anchorage contributed 
funding for dredging in front of the POL terminal. Controlling 
depth at the harbor was at a project depth of -36 feet 
MLLW. Regular maintenance dredging was accomplished by 
contract with Manson Construction and Engineering of Seattle, 
WA. A total of 227,559 cubic yards was dredged in 1992. 
- 40-1 - 
I

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
Of that amount, 123,517 cubic yards were for the Municipality 
of Anchorage. 
2. Bethel Harbor, AK 
Location. The City of Bethel is located about 85 miles 
inland from the Bering Sea and adjacent to the Kuskokwimn 
River. (See NOAA Chart 16006.) 
Existing project. Bethel Small Boat Harbor was authorized 
by Section 107 of the Rivers and Harbors Act enacted 14 July 
1960 (Public Law 86-645) as amended. The project consists 
of a small boat basin of approximately 6 acres dredged to a 
depth of 4 feet below mean lower low water, a maneuvering 
and turning basin, and an access channel connecting the 
channel to the Kuskokwim River. The project originally 
included four finger-type berthing areas providing beach 
moorage for 1,200 small river boats and a future mediumdraft 
moorage basin. The fingers were removed by local 
interests in 1986 and replaced with floating docks in 1989. 
Local cooperation. Fully complied with. 
Terminal facilities. One publicly owned and operated 
wharf capable of handling deep-draft vessels serves for general 
cargo. Small boat facilities in the basin area include 
publicly owned mooring floats. 
Operations during fiscal year. Maintenance: Dredging of 
the harbor and entrance channel was accomplished by contract 
with 18,411 yards of material removed from the end of 
March to the end of April 1992. 
3. Cordova Harbor, AK 
Location. Cordova is on the Gulf of Alaska near the mouth 
of the Copper River, about 150 miles southeast of Anchorage. 
(See NOAA Chart 16710, 16709, 16700, and 16013.) 
Existing project. Adopted 30 August 1935 and 30 August 
1964, provides for construction of two breakwaters 1,100 and 
1,400 feet in length protecting a 23 acre area, with an initial 
8.27 acre basin by 10.4 acres to a depth of -14 feet MLLW; 
and construction of an entrance breakwater 183 feet in 
length. 
Local cooperation. Fully complied with. 
Terminal facilities. Existing facilities include two docks for 
deep-draft vessels, the small boat harbor, and a few piers 
associated with fish processing plants which are used by fishing 
vessels. Both municipal and city docks are owned by the 
city of Cordova, with the small boat inner harbor facilities 
being owned by the State but operated by the city. 
Operations during fiscal year. Maintenance: Dredging of 
the harbor and entrance channel was accomplished by contract 
with an estimated 8,500 cubic yards of material removed 
by the end of November 1992. 
4. CRAIG HARBOR, AK 
Location. Craig is on the west side of Prince of Wales Island 
about 200 miles south of Juneau in Southeast Alaska. (See 
NOAA Charts 17405, 17400, and 16016) 
Existing Project. Adopted 2 March 1945, the harbor project 
includes a 3.6-acre mooring basin 225 feet wide and 700 
feet long plus a 100 foot wide entrance channel in South Cove 
dredged to -11 feet MLLW. Construction of two City owned 
and maintained rubblemound breakwaters to protect the expanded 
float system was authorized in 1979. The north breakwater 
is 160 feet long and the south breakwater is 300 feet 
long. Contstruction began in 1981 and was completed in 
1983. 
Local Cooperation. Fully complied with. 
Terminal Facilities. Existing facilities include a City owned 
dock, publicly owned docks for deep draft vessels, two small 
boat harbors, and several piers which support commercial 
fishing. 
Operations during fiscal year. A contract was awarded in 
late September 1992 for maintenance dredging of approximately 
6300 cubic yards of material from the basin and entrance 
channel. Work is scheduled for completion in late 
December 1992. 
5. DILLINGHAM HARBOR, AK 
Location. At the head of Nushagak Bay, an arm of Bristol 
Bay, on the right bank of Nushagak River, just below its 
confluence of Wood River; about 470 miles northeasterly of 
Dutch Harbor and 300 miles southwest of Anchorage. (See 
NOAA/NOS Chart #16660.) 
Existing project. A small-boat basin 230,000 square feet in 
area with a depth of + 2 feet above mean lower low water 
along Scandinavian Creek; with entrance channel 1,100 feet 
long and 40 feet wide in Scandinavian Creek; and a sill across 
the basin outlet. Tidal range between mean lower low water 
and mean higher high water is 19.8 feet. Extreme range is 
30.0 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Four docks at the city of Dillingham; 
three privately owned, one owned by the city, and four publicly 
owned small boat floats are located in the project basin. 
Two docks are used by the city to unload barges which come 
into Dillingham. New floats for the harbor were installed in 
June 1982, they are removed before fall freezeup and replaced 
each spring. Cargo and passengers from ocean vessels 
are unloaded at the docks or in the small-boat basin. Facilities 
are inadequate for the number of boats using the harbor. 
Operations during fiscal year. Maintenance: Regular 
maintenance was accomplished by dredging from the middle 
of May to the middle of June 1992. A total of 89,148 cubic 
yards of material was removed. 
6. HOMER HARBOR, AK 
Location. In Kachemak Bay, on Kenai Peninsula, 152 miles 
by water southwest of Anchorage. The harbor site is land 
based near the extremity of Homer Spit, which varies to 
one-quarter mile in width and extends 4.5 miles southeasterly 
from the mainland. (See NOAA/NOS Chart #16645.) 
- 40-2 -

ALASKA DISTRICT 
Existing project. Provides for a sheltered small-boat harbor, 
relocated and based within Homer Spit about 50 acres in 
area. Project depth varies from 10 feet mean lower low water 
in the most western segment of the harbor to 20 feet below 
mean lower low water in the entrance channel and the most 
eastern segment of the harbor; a north entrance channel; 
protected by a main rock breakwater 1,018 feet long and 
secondary rock breakwater 238 feet long. Tidal range between 
mean lower low and mean higher high water is 18.1 
feet, with an extreme range of 30.4 feet. (For details relating 
to previous projects, see page 1593 of Annual Report for 
1964.) 
Local cooperation. Fully complied with. 
Terminal facilities. One publicly owned and operated 
wharf capable of handling oceangoing vessels serves for passengers 
and general cargo. Small boat facilities in basin area 
include publicly owned mooring floats, a publicly owned 
wharf, and an industrial wharf. Construction has tripled size 
of the harbor. The city of Homer has tripled the size of its fish 
dock located at the southern end of the harbor. 
Operations during fiscal year. Maintenance: Regular 
maintenance dredging was accomplished by contract during 
the middle of July to the middle of August 1992. A total of 
9,468 cubic yards was removed. 
7. METLAKATLA HARBOR, AK 
Location. Metlakatla is located in the southern portion of 
Port Chester, a small bay on the northwest coast of Annette 
Island in southeastern Alaska, 18 miles south of Ketchikan. 
(See Coast and Geodetic Charts 8074, 8075, and 8102.) 
Existing project. Consists of two small boat basins. Existing 
basin is 2.18 acres in extent with a depth of 10 feet below 
mean lower low water, protected by a rubblemound breakwater 
900 feet long. New basin consists of two rubblemound 
breakwaters, 1,255 and 1,150 feet long, and an entrance channel 
and maneuvering area, 1,100 feet long, 100 feet wide, 
dredged to a depth of 15 feet below mean lower low water and 
a basin area of 6.25 acres dredged to a depth of 15 feet below 
mean lower low water. Tidal range between mean lower low 
water and mean higher high water is 14.7 feet, with an extreme 
range of 24 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Publicly owned facilities are one general 
cargo dock, one barge ramp, and a small boat float 
system in existing basin. Privately owned facilities are one oil 
pier and one industrial wharf. Facilities are not adequate for 
mooring the commercial fishing vessels operating from Metlakatla. 
Existing protected harbor area is fully utilized. 
Operations during fiscal year. Project physically complete, 
contractor claims pending. 
8. MOUNTAIN POINT BREAKWATER, AK 
Location. The project is located within the Ketchikan Gateway 
Borough on Revillagigedo Island in Southeast Alaska. 
The city of Ketchikan is located approximately 250 air miles 
south of Juneau. Mountain Point is a residential area about 6 
miles south of Ketchikan on the Tongass Highway. 
Existing project. The authorized Section 107 project consists 
of a 424-foot L-shaped rubblemound breakwater and a 
timber float. The existing local project consists of two ramps: 
a cast-in-place concrete slab extending 190 feet seaward 
from a parking lot to the -2 feet mean lower low water level, 
and precast reinforced concrete planks extending 194 feet to 
the -5 feet mean lower low water level. 
Local coorperation. Local sponsor has provided funds for 
construction. 
Operations during fiscal year. Plans and specifications 
were completed. A Local Cooperation Agreement detailing 
cost sharing of the project was signed with the Ketchikan 
Gateway Borough. Funds were received for construction. 
9. NINILCHIK HARBOR, AK 
Location. At mouth of Ninilchik River in Cook Inlet, at the 
community of Ninilchik, AK about 40 miles upcoast from 
Homer and 112 miles southwest of Anchorage. (See NOAA/ 
NOS Chart #16640.) 
Existing project. A small boat basin 320 feet long by 150 
feet wide dredged to an elevation of 2 feet above mean lower 
low water, with an approach channel 400 feet long and 50 feet 
wide dredged to an elevation of 9 feet above mean lower low 
water; protected by a pile jetty 410 feet long. The project was 
modified in the design stage to delete the pile jetty and revise 
the harbor dimensions to 400 feet long by 125 feet wide, and 
was completed in November 1961. Modification, including 
river channel diversion, two armor rock jetties, and beach 
protection, were accomplished in 1967 and 1969. Range between 
mean lower low water and mean higher high water is 
19.1 feet, with an extreme range of 29.3 feet. 
Local cooperation. Fully complied with. 
Terminal facilities. Facilities, which are limited to shallowdraft 
vessels and accessible from Cook Inlet only at half-tide 
or higher, are a cannery dock along Ninilchik River available 
for offloading fish, and small boat floats in the project basin, 
provided by State of Alaska. Other supplies are landed on 
beach or brought by road from deep draft ports in the vicinity. 
Facilities are extremely inadequate for the number of boats 
presently using the harbor. Expansion of facilities would require 
construction of additional protected harbor area. 
Operations during fiscal year. Maintenance: Dredging of 
the harbor and entrance channel was accomplished by contract 
with 9,319 cubicyards of material removed from the end 
of April to the middle of May 1992. 
10. NOME HARBOR, AK 
Location. At mouth of Snake River at the city of Nome, 
AK, on northerly shore of Norton Sound, an arm of the 
Bering Sea. It is a shallow open roadstead, 581 nautical miles 
north of Dutch Harbor and 545 air miles northwest of Anchorage. 
(See NOAA/NOS Chart #16206.) 
Existing project. Provides for two jetties, the easterly 951 
and the westerly not exceeding 676 feet long, at the mouth of 
- 40-3 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
Snake River; a channel 8 feet at mean lower low water, 75 
feet wide, from Norton Sound through Snake River to 
mouths of Bourbon and Dry Creeks, in city of Nome, ending 
in a turning basin of the same depth, 250 feet wide and 600 
feet long; revetting banks of rivers; and protecting all existing 
waterfront improvements on easterly beach by means of rock 
mount seawall 3,350 feet long extending easterly from east 
jetty. The project has been completed except extension of 
jetties beyond present 400 and 240 feet, which is classified 
inactive. Range between mean lower low water and mean 
higher high water is 1.6 feet and extreme tidal range is 7.5 
feet, but water levels are influenced more by wind than tide. 
Levels of 5 feet below mean lower low water have been 
observed during offshore winds, and a level of 14 feet above 
mean lower low water has been observed during a southerly 
storm. 
Local cooperation. Fully complied with. 
Terminal facilities. Cargoes and passengers from ocean 
vessels are lightered to and from shore, a distance of about 2 
miles. Traffic enters the dredged channel and is handled over 
revetment, where a lighterage company has transfer facilities 
which are open to the public. Facilities considered inadequate 
for existing commerce. In July 1984, the city of Nome 
received Department of Army authorization (permit) to construct 
a 3,600 foot gravel filled causeway. Construction of the 
causeway began in July 1985. Due to lack of complete funding, 
the length of the causeway was shortened to 2,700 feet. 
Construction was completed in May 1987. Use of this causeway 
for offloading petroleum products was delayed until the 
September 1987 arrival of a required berthing barge. 
Operations during fiscal year. Maintenance: Dredging of 
the harbor and entrance channel was accomplished by contract 
with 9,524 cubic yards of material removed from the end 
of June to the end of August 1992. 
11. PROJECT CONDITION SURVEYS 
Preliminary and detailed surveys were completed to determine 
navigation conditions at boat basins, small navigation 
projects, channels and tributaries of major rivers not within 
major project boundaries. Total costs for fiscal year were 
$493,957. (See Table 40-I) 
12. ST. GEORGE, AK 
Location. The city of St. George is located on St. George 
Island, the southernmost island of the Pribilof Islands, near 
the edge of the southwest Bering Sea shelf. 
Existing project. The project was authorized in Section 107 
of the Rivers and Harbors Act of 1960, PL 86-845, as 
amended. The work consists of dredging approximately 
176,000 cubic yards of material in the maneuvering area from 
an average depth of + 3 feet mean lower low water to -18 feet 
mean lower low water and the entrance channel from an 
average depth of -14 feet mean lower low water to -20 feet 
below mean lower low water. 
Local cooperation. Fully complied with. 
Operations during the fiscal year. Local sponsor's funds 
were used to pay the contractor's last pay estimate for the 
prior year. The project is physically complete, contractor 
claims pending. 
13. ST. PAUL ISLAND, AK 
Location. St. Paul Island Harbor is located on the shore of 
Village Cove on the southern side of St. Paul Island, the 
largest and most populated island of the Pribilof group in the 
central southeast Bering Sea. 
Existing Project. A St. Paul Harbor project was authorized 
by Congress in Section 202 of Public Law 99-662, based on a 
1982 Corps of Engineers feasibility report. Since that report 
was published, new wave and climatic information was gained 
through field measurement and through a November 1984 
storm that severely damaged a city built breakwater at St. 
Paul. American vessels have also assumed control of the 
groundfish harvest in the area more rapidly than expected, 
while crab stocks and catches have declined markedly. St. 
Paul also constructed 750 feet of breakwater and a 200-foot 
dock at the harbor site. On 31 March 1989, Assistant Secretary 
of the Army signed an Agreement under Section 204(e) 
of PL 99-662 which states that the government would pay 80 
percent of the costs of general navigation features of the 
Authorized Project. The agreement was unique in that the 
city had to successfully build the harbor with their own funds 
and the government would reimburse them upon acceptance 
by the Corps of Engineers. The general navigation features 
consist of: (1) 1,050 feet of rubblemound breakwater with a 
finished elevation of + 37 feet MLLW; (2) 1,000 feet of 
rubblemound detached breakwater with a crest elevation of 
+ 18 feet MLLW; and (3) a 200 foot wide maneuvering area 
at a depth of -18 feet MLLW. Construction commenced in 
May 1989 and was completed in December 1989. The city 
was reimbursed in March 1990 in the amount of $18,150,000. 
Local Cooperation. A 204(e) agreement was signed by the 
Assistant Secretary of the Army (Civil Works) on 30 March 
1989. One minor item remains incomplete. The agreement 
was amended on 30 April 1992 to allow the local sponsor an 
additional 5 years to complete the inner harbor facility. 
Operations during fiscal year. The general navigation 
features were completed in 1989 and accepted by the government. 
Coordination was performed with the city for compliance 
with the LCA. A condition survey was completed in 
fiscal year 1992. 
14. WRANGELL HARBOR, AK 
Location. Wrangell Harbor is located on the west side of 
the northern end of Wrangell Island, 824 miles from Seattle 
and 160 miles from Juneau. (See U.S. Coast and Geodetic 
Survey Charts Nos. 8164, 8161, and 8201.) 
Existing project. Consists of a rubblemound breakwater 
300 feet long to protect the southern portion of the outer 
harbor; a mooring basin 600 feet long, 400 feet wide, and 10 
feet deep below mean lower low water within the protected 
area; an inner basin in the tide flat area east of Shakes Island, 
325 feet wide and 550 feet long; a connecting channel 120 feet 
wide and approximately 530 feet long; a connecting channel 
- 40-4 -

ALASKA DISTRICT 
120 feet wide and approximately 530 feet long from the outer 
mooring basin all at a depth of 10 feet at mean lower low 
water; and construction of a rock mound breakwater 320 feet 
long on the reef north of Shakes Island. The range between 
mean lower low water and mean higher high water is 15.7 
feet. The extreme tidal range is 26 feet. Heavy swells, dangerous 
to small fishing boats, are caused by the wind, which 
causes an additional rise of about 1 foot. 
Construction of the breakwater north of Shakes Island was 
placed on inactive status as material to be used from the inner 
basin was unsuitable and the breakwater considered unnecessary 
for safe moorage of vessels. The cost of this portion was 
last revised in 1956 and estimated to be $6,500. (See table 
40-B for authorizing legislation.) 
Local cooperation. Fully complied with. 
Terminal facilities. There are eight wharves and floats in 
Wrangell Harbor. Two privately owned wharves serving general 
cargo and passenger terminals, one of which includes a 
cold storage facility, are open for public use. The remaining 
wharves serve various industrial purposes. One of the floats is 
publicly owned and is open for public use for mooring and 
servicing small craft, and two privately owned floats serve oil 
handling facilities. 
Operations during fiscal year. Maintenance: A revised 
letter report on the repair of the concrete parapet wall on the 
breakwater was prepared during the spring and summer of 
FY 90. Repair was accomplished in September 1992. The 
recommended method of repair used was shotcrete, a high 
quality wet-mix concrete containing steel fibers and silica 
powder. Shotcrete was applied to both the harbor and seaward 
sides at the rubblemound's intersection with the walls' 
foundation, included rebuilding of all the construction joints 
and major fractures along the parapet structure. 
Flood Control 
15. Bethel Bank Stabilization, AK 
Location. In southwestern Alaska on the north bank of the 
Kuskokwim River 400 miles west of Anchorage. 
Existing project. The project consists of rock riprap toe 
protection to be installed on the unprotected river bank and 
at locations where existing city construction bulkheads are 
threatened by erosion. This includes 3,500 feet of unprotected 
riverbank and 3000 feet of previously installed bulkheads. 
Local cooperation. A Local Cooperation Agreement detailing 
the cost sharing requirements will be required. 
Terminal facilities. The POL tank farm is situated at the 
downstream end of the project and the city's general cargo 
dock is at the upstream end of the project. 
Operations during fiscal year. Plans and specifications 
were initiated with surveys and design review by the Corps of 
Engineers Channel Stabilization Committee. 
16. CHENA RIVER LAKES, AK 
Location. In the vicinity of Fairbanks, AK, and encompassing 
the Tanana River, Chena River, Little Chena River, and 
their tributaries. (See USGS map Fairbanks, C1, D1, D2, and 
Big Delta D6.) 
Local cooperation. Fully complied with. 
Existing project. Moose Creek Dam has been constructed 
17 miles east of Fairbanks with control works on the Chena 
River. The dam itself extends from a bluff one mile north of 
the Chena River and south past the control works for approximately 
six miles to the Tanana River. The dam connects 
with a completed 22 mile levee system along the north 
boundary of the Tanana river to a point south and west of 
Fairbanks. Estimated Federal cost is $210,000,000, Little 
Chena Dam was submitted for deauthorization in September 
1990. 
Operations during fiscal year. Maintenance: Modification 
of gates and installation of a curbwall were completed by 
contract at a total cost, during 1992, of $264,262. Major surface 
flooding at Fairbanks was avoided due to flood control 
operations at the Moose Creek Dam, during May and June 
1992. 
17. HOMER SPIT, AK 
Location. Located near the town of Homer, Alaska, 120 
miles southwest of Anchorage. It is a 4.5 mile long finger of 
land that varies in width from 30 to 500 yards wide extending 
into Kachemak Bay. 
Existing project. The authorized project, which is being 
designed, consists of rock revetment along 1,100 feet of 
sheetpile beachfront for the initial phase and periodic beach 
nourishment as needed. 
Local cooperation. A Local Cooperation Agreement was 
signed detailing cost sharing of the project. The local share of 
project cost was received. 
Operations during fiscal year. Plans and specifications for 
construction of the project were completed and the contract 
has been awarded. No placement has been made. 
18. FLOOD CONTROL WORK UNDER 
SPECIAL AUTHORIZATION 
Emergency flood control activities - repair, flood fighting, 
and rescue work (Public Law 99, 84th Congress, and antecedent 
legislation). 
Federal costs for the fiscal year were $561,330 for disaster 
preparedness, emergency operations, and rehabilitation. 
Flood control activities pursuant to Section 205, Public 
Law 858, 80th Cong., as amended (preauthorization). 
19. INSPECTION OF COMPLETED FLOOD 
CONTROL PROJECTS 
Inspections were made of flood control works at Fairbanks, 
Bethel, Galena, Gold Creek, Lowell Creek, Salmon River, 
Skagway River, and Talkeetna River, Alaska. 
- 40-5 -

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
Multiple-Purpose Projects, Including Power 
20. SNETTISHAM, AK 
Location. At the mouth of the Speel River, between Crater 
Lake to the west and Long Lake to the north, 29 nautical 
miles southeast of Juneau. (See Coast Geodetic Survey chart 
8227.) 
Existing project. Snettisham is a multi-stage power project. 
The initial stage, which was completed in 1977, tapped 
Long Lake and included an underground powerhouse with 
two 23.4 megawatt units and a transmission line to Juneau, 
AK. The project was turned over to the Alaska Power Administration 
for operation and maintenance. The second 
stage, which is nearly completed, provided a tunnel to Crater 
Lake and added a third unit. The final phase will provide a 
dam on Long Lake to increase storage and the energy capability 
of Long Lake. The Long Lake Dam is currently unscheduled. 
The existing Long Lake (elevation 815 feet) water 
is transported through an approximately horizontal 13 foot 
diameter tunnel 8,400 feet long and a 1,400 foot penstock 
dropping at a 46 degree angle to the underground powerhouse 
at tidewater to drive two turbines with a combined 
generating capacity of 47,600 kilowatts. Power from two generators 
is supplied to Juneau by a 13.8 kilovolt overhead 
transmission line and a submarine cable traversing Taku Inlet. 
The Crater Lake stage of construction tapped Crater 
Lake (elevation 1,002 feet) to drive a third turbine installed in 
the existing underground powerhouse. An additional 
nameplated-rated generating capacity of 34,500 kilowatts 
was added. Estimated cost of Stage 1 and Stage 2 construction 
is $148,284,000. 
Local cooperation. None required. 
Operations during fiscal year. The Remote Supervisory 
Control and Data Acquisition (SCADA) Contract was 
awarded in September 1990. The contract is substantially 
behind schedule. A July 1993 completion is anticipated. A 
successful lake tap occurred on 21 October 1988. Power-online 
initially occurred in May 1989, but was shut down for 
repairs to the turbine and generator. It has since been 
brought back on line. 
General Investigations 
21. SURVEYS 
Fiscal year costs for surveys include $325,480 for flood 
control studies, $256,714 for coordination studies and 
$107,974 for miscellaneous activities. 
22. COLLECTION AND STUDY OF BASIC 
DATA 
Technical assistance, information, flood plain management 
guidance, and other flood plain management services have 
been provided to military and nonmilitary Federal agencies, 
local communities, State agencies, Architectural/Engineering 
firms, lending institutions, and private individuals at a 
fiscal year cost of $124,124. 
Fiscal year costs for Hydrologic Studies were $17,901. 
23. PRECONSTRUCTION, ENGINEERING 
AND DESIGN 
KODIAK HARBOR, AK 
Location. The port of Kodiak is located 242 and 175 nautical 
miles south of Anchorage and Seward, respectively, and 
approximately 1,258 nautical miles northwest of Seattle. St. 
Herman Harbor is located at Near Island across Near Island 
Channel from Kodiak. 
Existing project. The recommended plan has a 1,865 foot 
rubblemound split breakwater with a crest elevation of + 22 
feet MLLW. The main entrance channel is located in the split 
breakwater and has a design width of 200 feet and design 
depth of -20 MLLW. Since the natural water depth at the 
main entrance channel is -55 feet MLLW, no dredging is 
required in this channel. A 100 foot rubblemound stub 
breakwater is recommended next to a secondary entrance 
channel at the north end of the harbor. This secondary 
entrance channel is to be 100 feet wide with a design depth of 
-12 feet MLLW, and will require 4,400 square yards of rock 
excavation. 
The current estimated cost of $26,243,000, of which 
$23,478,000 would be the Federal first cost and $2,687,000 is 
the non-Federal first cost (cash and land easement rights of 
way). Local interests will pay 10 percent initially plus 10 
percent during a period of up to 30 years, resulting in an 
ultimate non-Federal cost of $5,218,000. 
Local cooperation. A Local Cooperation Agreement will 
be required with the city of Kodiak. 
Terminal facilities. Thirty-one piers, wharves, and docks 
are located in the port of Kodiak. Four are located in 
Womens Bay and two in Gibson Cove, west of the main part 
of the city. Twenty-four facilities are along the main waterfront 
of Kodiak, with thirteen on St. Paul Harbor and eleven 
on Kodiak Harbor, west and east of the Kodiak Small Boat 
Harbor, respectively. The remaining facility is the St. Herman 
Small Boat Harbor between Uski and Near Islands, 
directly south of the Kodiak Small Boat Harbor. 
Operations during fiscal year. All efforts were toward 
completing the GDM and advancing plans and specifications 
and all other activities leading to construction. 
- 40-6 -

ALASKA DISTRICT 
TABLE 40-A COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep.30, 1992 
1. Anchorage Harbor, AK New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contrib. Funds) Maint. 
Contrib. 
Cost 
2. Bethel Small Boat 
Harbor, AK 
3. Cordova Harbor, AK 
4. Craig Harbor, AK 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
5. Dillingham Harbor, AK New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contrib. Funds) Maint. 
Contrib. 
Cost 
1,433,100 1,636,355 994,680 
1,479,384 1,636,750 1,069,549 
- - 585,647 
- - 560,618 
-447,000 
-- 83,664 
- - 471,000 
- - 79,798 
1,107,100 
1,127,641 
52,433 
77,462 
329,161 
75,500 
314,748 
- 356,000 
-- 76,303 
95,934 31,419 - - 
720,600 550,061 480,500 396,200 
714,936 535,593 516,326 388,230 
6. Homer Harbor, AK New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
Rehab. 
Approp. 
Cost 
7. Metlakatla Harbor, AK New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
(Contrib. Funds) New Work 
Contrib. 
Cost 
8. Mountain Point Boat 
Launch, AK 
323,000 345,002 221,000 239,700 
333,942 338,376 221,148 239,829 
20,000 
50,258 
- 5,077,470 
Maint. 
Approp. 
Cost 
9. Ninilchik Harbor, AK New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
229,200 161,063 
198,740 159,540 
69,000 
54,883 
72,900 207,300 
100,642 159,601 
- 40-7 - 
533,235 
533,235 
25,390,707 
25,247,409 
638,080 
638,080 
447,000 
412,825 
395,500 
394,546 
356,000 
76,303 
548,790 
580,209 
8,124,282 
8,126,784 
1,700 
1,700 
3,512,350 
3,512,350 
4,768,113 
4,462,051 
67,974 
67,974 
5,077,470 
5,074,730 
148,520 
148,520 
830,644 
722,096 
69,000 
54,883 
428,720 
428,720 
4,347,039 
4,293,844

TABLE 40-A 
(Continued) 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
COST AND FINANCIAL STATEMENT 
See 
Section Total to 
In Text Project Funding FY 89 FY 90 FY 91 FY 92 Sep.30, 1992 
10. Nome Harbor, AK New Work 
(Contrib. Funds) 
12. St. George, AK 
(Contrib. Funds) 
13. St. Paul Harbor, AK 
14. Wrangell Harbor, AK 
15. Bethel Bank Stabilization, 
AK 
16. Chena River Lakes, AK 
(Contrib. Funds) 
17. Homer Spit Erosion, 
AK 
20. Snettisham, AK 
23. Kodiak Harbor, AK 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
Maint. 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
New Work 
Approp. 
Cost 
- - 
236,700 330,628 
443,745 158,884 
2,500 5,000 
2,500 5,000 
3,710,000 
3,204,451 531,360 
633,828 2,366,172 
-- 2,823,937 
450,000 18,141,200 
248,714 18,304,806 
52,500 44,888 
21,787 61,039 
1,157,000 
1,160,900 76 
1,268,000 114,000 
3,477,192 474,789 
962,300 994,754 
962,828 947,827 
48,000 110,000 
54,529 74,267 
4,715,113 2,986,000 
6,782,000 2,457,450 
560,000 509,000 
528,250 495,000 
-- 
99,100 
275,678 
--- 
271,300 
241,890 
2,500 
2,500 
130 
30,683 
125 
8,163 
358,671 
1,312,200 
1,182,576 
46,000 
90,000 
-800,000 
2,063,559 
375,000 
403,840 
340,000 
334,021 
424,854 
312,456 
-100,000 
-129,571 
1,657,800 
1,582,178 
110,000 
110,423 
4,787,000 
5,571,354 
250,000 
223,394 
1,348,240 
1,348,240 
9,920,080 
9,884,069 
175,000 
175,000 
4,000,000 
3,923,400 
3,004,000 
2,823,937 
19,635,200 
19,593,562 
537,020 
537,020 
882,240 
6,273,224 
1,581,854 
1,473,557 
214,013,928 
213,974,046 
2,970,000 
2,764,754 
2,182,300 
2,145,929 
1,070,000 
1,078,583 
143,209,550 
142,515,669 
1,769,000 
1,724,669 
- 40-8 -

ALASKA DISTRICT 
Table 40-B 
See Date 
Section Authorizing 
in Text Act 
AUTHORIZING LEGISLATION 
Project and Work Authorized 
ANCHORAGE HARBOR, AK 
Deep winter harbor, adjacent to docks, dredge to 35 feet 
below mean lower low water, protected by two jetties. 1 
Extension of project limits. 
H. Doc. 34, 85th Cong., 1st Sess.2 
P.L 94- 587 
BETHEL HARBOR, AK 
Basin of 6 acres dredged to -4 feet mean lower low water, Section 107, 1960 Rivers and 
manuvering and turning basin, and access channel. Floating Harbors Act, P.L 86- 645 
docks constructed by locals in 1989. H.R. 7634, 86th Cong. 
CORDOVA HARBOR, AK 
Two breakwaters, 1,000 and 1,400 feet in length protecting 
an 18.67 acre area dredged to a depth of -14 feet mean 
lower low water. 
Harbor expansion from 8.26 acres to 20 acres by removal of 
1400 foot breakwater and construction of a new 2000 foot 
long breakwater. The entrance channel dredged to -16 
feet mean lower low water and turning basin dredged from 
-10 to -12 feet mean lower low water. 
DILLINGHAM HARBOR, AK 
Basin 230,000 square feet in area with depth of 2 feet 
above mean lower low water along Scandinavian Creek, 
with entrance channel 1,100 feet long and 40 feet wide. 
HOMER HARBOR, AK 
Basin 2.7 acres in area with depth of 12 feet below mean 
lower low water, and rock breakwater 1,260 feet long. 
Relocation and rehabilitation of project destroyed by 
March 27, 1964 earthquake, by construction of basin 10 
acres in area with 12-foot depth over 2.75 acres and 15-foot 
depth over 7.25 acres protected by rock breakwaters, 1,018 
feet and 238 feet long. 
Increased width and depth of entrance channel and an 
enlarged staging area. Basin enlarged from 16.5 to 50 acres. 
Doc. 33, Committee on Rivers and 
Harbors, House of Representatives 
73rd Cong. 
Sec. 55, P.L 88-451, 
Senate Doc. 2881, 88th Cong. 
Sec. 107, 1960 Rivers and Harbors 
Act, P.L 86-645 
H.R. 7634, 86th Cong. 
H. Doc. 390, 84th Cong., 2d Sess.2 
H. Doc. 34, 85th Cong., 1st, Sess. 2 
P.L 88- 451 
Section 107, P.L 86-645 
Authorized by Chief of Engineers, 
Nov. 13, 1981 
METLAKATLA HARBOR, AK 
Dredging small boat basin 2.18 acre in extent to a depth H. Doc. 138, 76th Cong., 91st Sess. 
of 10 feet below plane of mean lower low water; construction 
of rubblemound breakwater 900 feet long. 
Entrance channel and two rubblemound breakwaters Section 201, P.L 89- 298 
inclosing a 7.0 acre basin. S. Doc. 92- 64, 92d Cong., 2d Sess.2 
Authorized Oct. 12, 1972 
NINILCHIK HARBOR, AK 
Basin 320 feet long by 150 feet wide with depth of 2 feet H. Doc. 34, 85th Cong., 1st Sess.2 
above mean lower low water, approach channel 400 feet 
long and 50 feet wide with depth of 9 feet above mean lower 
low water, protected by 410 foot jetty. 
NOME HARBOR, AK 
Two jetties, easterly 335 feet and westerly 460 feet long H. Doc. 1932, 64th Cong., 2d Sess.2 
revetment, channel and basin 200 feet wide and 250 feet long. 
Extension of the jetties and enlarging basin to 250 feet H. Doc. 404, 71st Cong., 2d Sess., 
wide and 600 feet long. 3 and Rivers and Harbors Committee 
Doc. 38, 73d Cong., 2d Sess. 
Seawall Reports of Chief of Engineers 
dated March 8, 1948 
- 40-9 - 
July 3, 1958 
Oct. 22, 1976 
July 14, 1960 
Documents 
Apr. 20, 1933 
Aug. 19, 1964 
Ju.ly 14, 1964 
July 3, 1958 
5. 
July 2, 1958 
Aug. 19, 1964 
July 14, 1960 
7. 
Mar. 2, 1945 
Oct. 27, 1965 
9. 
July 3, 1958 
10. 
Aug. 8, 1917 
Aug. 30, 1935 
June 16, 1948

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
Table 40-B 
(Continued) 
AUTHORIZING LEGISLATION 
See Date 
Section Authorizing 
in Text Act Project and Work Authorized Documents 
12. 
Nov. 17, 1986 
13. 
14. 
15. 
16. 
17. 
20. 
23. 
Nov. 17, 1986 
Sept. 22, 1922 
Aug. 30, 1935 
Mar. 2, 1945 
Nov. 17, 1986 
Aug. 13, 1968 
Nov. 28, 1990 
Oct. 23, 1962 
Nov. 17, 1986 
Nov. 28, 1990 
ST. GEORGE, AK 
Dredging the maneuvering area from an average depth of 
+ 3 feet MLLW to 18 feet below MLLW and dredging the 
entrance channel from an average depth of 14 feet MLLW 
to 20 feet below MLLW. 
ST. PAUL ISLAND, AK 
Add 1,050 feet of breakwater at existing crest height, 
37 feet mean lower low water and 1,000 feet long with a 
crest height of + 18 mean low low water. 
WRANGELL HARBOR, AK 
Breakwater 300 feet long to protect southern portion 
of harbor. 
Mooring basin 600 feet long, 400 feet wide, and 10 feet deep. 
Inner basin and connecting channel from the existing 
mooring basin, both 10 feet deep at mean lower low water, 
and breakwater 320 feet long on the reef north 
of Snakes Island. 
BETHEL BANK STABILIZATION, AK 
Streambank protection by placing riprap along 8,500 feet 
of riverbank. 
CHENA RIVER LAKES, AK 
Dam and reservoir on the main Chena River, a dam and 
detention reservoir on the Little Chena River, and a levee 
along the north side of the Tanana River.4 
Section 107 of The Rivers and 
Harbors Act of 1960, Public Law 
86-645, as amended. 
Section 202, PL 99-662 
H. Doc. 161, 67th Cong., 2d Sess. 
H. Doc. 202, 72nd Cong., 1st Sess. 
H. Doc. 284, 76th Cong., 1st Sess. 
Section 202, PL 99-662 
S. Doc. 89, 90th Cong., 2d Sess.2 
HOMER SPIT, AK 
Extension of an existing rubblemound revetment along an Sec. 101, Water Resource 
existing sheetpile wall to provide protection and nourishment Development Act of 1990, 
along a 1000 foot portion of State highway. P.L. 101-640, 101st Cong. 
SNETTISHAM, AK 
Multi-purpose dam, with powerhouse and transmission H. Doc. 40, 87th Cong., 1st Sess.2 
facilities. 
KODIAK HARBOR, AK 
Breakwater 1,900 feet long with an entrance channel 
930 feet long and 20 feet deep to serve 45 acres of 
moorage in St. Herman's Bay. 
Section 202, PL 99-662 
S. Doc. 6, 96th Cong., 1st Sess. 
Section 102, Water Resource 
Development Act of 1990, 
P.L101-640, 101st Cong. 
1. Purchase of dredge and deepwater jetties deauthorized 
November 6, 1977 under section 12, Public Law 93-251. 
2. Contains latest published map. 
3. Extension of jetties classified "inactive". 
4. Little Chena Dam deauthorized in 1991. 
- 40-10 -

ALASKA DISTRICT 
TABLE 40-C OTHER AUTHORIZED NAVIGATION PROJECTS 
For Last Cost to Sep. 30. 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Apoon Mouth of Yukon River, AK1 
Bar Point Harbor, AK2 
Bethel Small Boat Harbor, AK 
Cook Inlet Shoals, AK 
Cordova Harbor, AK2 
Cordova, AK 
Craig Harbor, AK 
Douglas Harbor, AK 
Dry Pass, AK 
Egegik River, AK 
Elfin Cove, AK 
Gastineau Channel, AK 
Haines Harbor, AK2 
Homer Harbor, AK2 
Hoonah Harbor, AK 
Humboldt Harbor, AK 
Iliuliuk Harbor, AK 
Juneau Harbor, AK 
Kake Harbor, AK 
Kasilof Harbor, AK2 
Ketchikan Harbor, AK 
Kodiak Harbor, AK 
Mekorykuk, AK 
Myers Chuck Harbor, AK 
Naknek River, AK 
Neva and Olga Straits, AK 
Old Harbor, Kodiak Island, AK2 
Pelican Harbor, AK 
Petersburg Harbor, AK 
Port Alexander, AK 
Port Lions, AK2 
Rocky Pass, AK 
St. Michael Canal, AK 
Seldovia Harbor, AK 
Sergius Whitestone, AK 
Seward Harbor, AK 
Sitka Harbor, AK 
Skagway Harbor, AK 
Stikine River, AK 
Valdez Harbor, AK 
Wrangell Narrows, AK 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Inactive 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
Completed 
1920 
1983 
1985 
1977 
1978 
1986 
1983 
1963 
1983 
1972 
1959 
1964 
1977 
1987 
1983 
1977 
1941 
1974 
1991 
1975 
1979 
1973 
1986 
1970 
1961 
1960 
1972 
1964 
1972 
1949 
1986 
1960 
1916 
1974 
1973 
1973 
1973 
1972 
1987 
1968 
1979 
128,896 
2,000,0003 
1,520,272 
1,220,000 
843,534 
9,642,000 
1,033,5004 
282,019 
943,351 
4,441 
154,191 
789,461 
1,000,000 5 
2,000,000 
4,255,0008 
3,679,6837 
66,037 
1,381,150 
870,700 
109,848 
1,602,417 
1,891,212 e 
1,372,139 
9,700 
20,789 
155,009 
370,415 
369,683 
252,932 
17,000 
1,825,311 
337,668 
377,062 
1,051,883s 
1,798,010 
712,369 o0 
1,611,009 
133,180 
649,740"1 
3,562,343 
2,154 
5,000 
488,156 
72,500 
23,466 
3,107 
102,701 
260,991 
331,256 
37,946 
132,946 
18,973 
26,800 
560 
5,518 
1,934 
219,789 
15,400 
32,665 
8,804 
221,498 
309,260 
1. Abandonment recommended in H. Doc. 467, 69th Cong., 1st 
Sess. 
2. Authorized by Chief of Engineers (Sec. 107). 
3. In addition, $272,779 of State funds. 
4. Includes $656,240 for Sec. 107 project. 
5. In addition, $925,500 of State funds. 
6. In addition, $973,875 of State funds. 
7. In addition, $857,000 of State funds. 
8. Includes $594,163 for rehabilitation. 
9. Includes $400,000 for rehabilitation. 
10. Includes $90,026 for rehabilitation and $2,528 Code 710. 
Recreation facilities at Completed projects. 
11. Includes $73,000 for rehabilitation and $2,713 Code 710, 
Recreation facilities at Completed projects. 
- 40-11 -

TABLE 40-E 
REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR 1992 
OTHER AUTHORIZED FLOOD CONTROL PROJECTS 
For Last Cost to Sep. 30, 1992 
Full Report Operation 
See Annual and 
Project Status Report for Construction Maintenance 
Bethel Bank, Kuskokwim River' Completed 1985 553,970 
Fairbanks, Tanana River & Chena Slough, AK Completed 1943 557,000 
Gold Creek, AK Completed 1975 876,0062 4,301 
Klutina River, Cooper Center, AK 3 Completed 1973 260,681 
Lowell Creek, AK^ Completed 1945 416,382s 30,771 
Salmon River, AK Completed 1963 37,7706 7 162,925 8 
Talkeetna River, AK Completed 1981 516,694 
1. Section 14. 5. In addition $25,000 expended from contributed funds. 
2. In addition, $25,000 expended from contributed funds. 6. Includes $34,197 of PWA funds. 
3. Authorized by Chief of Engineers (Sec. 205). 7. In addition, $7,000 expended from contributed funds. 
4. During FY 88, $551,690 was expended from FC and CE. 8. In addition, $27,400 expended from contributed funds. 
TABLE 40-G DEAUTHORIZED PROJECTS 
For Last 
Full Report Federal Contributed 
See Annual Date Funds Funds 
Project Report for Deauthorized Expended Expended 
Allison Lake, AK (Valdez Hydropower) 1992 
Anchorage Harbor, AK (Uncompleted Portion) 1967 1977 
Bradley Lake, AK 1983 1983 1982 46,701,000 
Ketchikan Harbor, AK (West Breakwater) 1979 1979 
Port Alexander, AK (Inner Harbor) 1949 1977 
Tolovana River, AK (Snagging) 1931 1977 
Little Chena River Dam 1983 1990 
Long Lake Dam 1975 1990 
Myers Chuck Harbor, AK 1970 1991 9,700 
Scammon Bay, AK 1992 
Skagway River, AK 1966 1991 26,385 
- 40-12 -

ALASKA DISTRICT 
TABLE 40-H NAVIGATION WORK UNDER 
SPECIAL AUTHORIZATION 
NAVIGATION ACTIVITIES PURSUANT TO SECTION 107, PUBLIC LAW 86- 645 
(PREAUTHORIZATION) 
Study Identification 
Anchor Point, AK 
Atka, AK 
Akutan, AK 
Barrow, AK 
Chignik, AK 
Cordova, AK 
Craig, AK 
Ketchikan, AK 
Klawock, AK 
Koyuk, AK 
Larsen Bay, AK 
Little Diomede, AK 
Mountain Point, AK 
Port Lions, AK 
St. Mary's, AK 
Seward Expansion, AK 
Wainwright, AK 
Whittier, AK 
Williamsport, AK 
Wrangell Narrows, AK 
Fiscal Year Costs 
$ 44,971 
13,125 
7,891 
6,735 
2,000 
8,500 
34,983 
15,555 
6,755 
4,806 
32,997 
27,815 
54,883 
174,689 
9,751 
6,758 
4,860 
25,307 
10,000 
219 
TOTAL 492,600 
TABLE 40-I PROJECT CONDITION SURVEYS 
Name of Project Date Survey Conducted 
King Cove Harbor August 1992 
Kodiak Harbor (Near Island Channel ) June 1992 
Port Lions Harbor June 1992 
St. Paul Harbor June 1992 
Dry Pass Channel June 1992 
Elfin Cove Channel July 1992 
New Metlakatla Harbor February 1992 
Old Metlakatla Harbor February 1992 
Port Alexander Channel July 1992 
Sitka (Crescent Bay) Harbor July 1992 
Wrangell Narrows Channel (Mile 20) February 1992 
- 40-13 -

BOARD OF ENGINEERS FOR RIVERS AND HARBORS 
The Board of Engineers for Rivers and Harbors is a 
continuing body created by Section 3 of the 1902 River 
and Harbor Act. The board is selected by the Chief of 
Engineers and consists of seven senior engineer officers. 
The Deputy Chief of Engineers normally serves as chairman. 
The seven members are division engineers with 
membership rotated among divisions having civil works 
missions. The civilian staff members of the board consists 
of four senior advisors, one of which serves as Acting 
Resident Member. The board meets quarterly or on call 
of the chairman. 
The board under the direction of the Chief of Engineers: 
a. Conducts independent review of reports covering a 
wide range of project purposes as requested by Acts of 
Congress or resolutions of Congressional Committees, or 
as directed by the Chief of Engineers, concerning proposed 
works for development of the water resources of 
the United States; prepares reports and recommendations 
theron in compliance with study directives, with 
regard to formulation of project scope, suitability of 
engineering plans, adequacy of costs, economic justification, 
and requirements of local cooperation including cost 
sharing and propriety of proposed construction by the 
Federal government. 
b. Reviews reports and makes recommendations for 
major modification or reconstruction of existing navigation 
improvements to ensure conformity with existing 
authorized improvements and essentially for efficient 
and economical maintenance and operation. 
c. Provides independent evaluation and counsel with 
respect to the environmental quality aspects of water 
resources development. 
d. Provides assistance, as required, to HQUSACE in the 
development of policy and related procedures for the 
uniform application of standards in the project formulation 
process. 
e. Provides advice on potential issues related to ongoing 
planning studies, as discussed during Feasibility Review 
Conferences. 
Total membership of the board is fixed by law at seven. 
In December 1982, the Chief of Engineers instituted a 
mechanism for predesignating future members, based on 
their time of service as division engineers, geographical 
factors, and other criteria. This procedure achieves a 
wider involvement of division engineers and their staffs 
with the proceedings of the board. Members Designate 
attend and participate in the meetings of the board, but 
are not permitted to vote on board actions. 
The membership of the board as of September 30, 1992 
was: 
Members 
Major General Peter J. Offringa, Deputy Chief of 
Engineers, Washington, DC 
Brigadier General Roger F. Yankoupe, Division Engineer, 
South Atlantic, Atlanta, GA 
Brigadier General Albert J. Genetti, Jr., Division 
Engineer, Ohio River, Cincinnati, OH 
Brigadier General Robert L. Herndon, Division Engineer, 
Southwestern, Dallas, TX 
Member Designate: 
Major General Ernest J. Harrell, Division Engineer, 
North Pacific, Portland, OR 
Official Board Actions. In compliance with resolutions 
of Congress and instructions from the Chief of 
Engineers, the board approved 24 official report reviews 
during Fiscal Year (FY) 1992. 
The favorable reports category includes favorable recommended 
projects for Federal construction as well as 
projects for solving water resources problems for major 
metropolitan areas, even though they may not include 
recommendations for construction by any agency of the 
Federal government. 
Reports Recommending Favorable for Federal 
Construction. The board approved 16 projects at an 
estimated total first cost of $3,462,777,000, of which 
$1,779,988,000 is the first cost to the United States. A 
listing of the projects follows: 
American River Watershed Investigation, CA 
Delaware River Comprehensive Navigation Study, 
Main Channel Deepening, NJ, PA, and DE 
Gulf Intracoastal Waterway, Sargent beach, TX 
Kissimmee River Restoration, FL 
Lackawanna River Near Scranton, PA 
Lackawanna River at Olyphant, PA 
Las Vegas Wash and Tributaries (Tropicana), NV 
Los Angeles County Drainage Area, CA 
Lower-Cumberland-Tennessee Rivers, KY 
Monongahela-Youghiogheny River Basin, MD, PA and 
WV 
Morro Bay Harbor, CA 
Rio Grande De Loiza, PR 
Sacramento Metropolitan Area, CA 
Savannah Harbor, GA 
Shoal Creek, TX 
Southeast Alaska Harbors, AK 
Recommending Unfavorable for Federal Construction: 
During FY 1992, the board concurred in the 
unfavorable recommendations of the reporting officers 
for Federal construction in eight projects: 
Black Hawk County, IA (Cedar Run and Tributaries) 
Connecticut River, Turns Falls to State Line, MA 
Eastern North Carolina Above Cape Lookout, NC 
Frog Pond, FL 
Lower Hillsborough River and Curiosity Creek, 
Mississippi Gulf Coastal Areas, MS 
Savannah River Basin, GA, SC, and NC 
Wrightsville Beach-North Portion, NC 
During FY 1992, the board held meetings on 2 December 
1991, 10 March 1992, 5 May 1992, 27 May 1992, and 
23-24 June 1992. 
Since 1902, the board has acted on 8,900 reports, 
recommending favorably on 3,966 and unfavorably on 
4,934. 
41-1

MISSISSIPPI RIVER COMMISSION* 
The Mississippi River Commission (MRC) was created 
by an act of Congress on Jun. 28, 1879. The Flood 
Control Act of May 15, 1928, authorized the Flood 
Control, Mississippi River and Tributaries (MR&T) 
Project. The Commission consists of three officers of 
the Corps of Engineers, one from the former Coast and 
Geodetic Survey (presently the National Oceanic and 
Atmospheric Administration), and three civilians, two 
of whom must be civil engineers. All members are 
appointed by the President with the advice and consent 
of the Senate. 
During the fiscal year the Commissioners were: BG 
Pat M. Stevens IV, President Designee, Mr. Sam E. 
Angel, appointed Sep. 25, 1979; Mr. R. D. James, civil 
engineer, appointed Dec. 1, 1981; Mr. Frank H. Walk, 
appointed Oct. 22, 1987; BG Albert J. Genetti, Jr., 
Member Designee, Commander, Ohio River Division; 
RADM J. Austin Yeager, Member Designee, NOAA: 
COL Gerald E. Galloway, U.S. Army, appointed Oct. 
28, 1989; COL Jack B. Avant, appointed Jun. 20, 1991 
served as Secretary of the Commission. 
The MRC is charged, under direction of the Secretary 
of the Army and supervision of the Chief of 
Engineers, with prosecution of improvements for flood 
control of the Mississippi River and of its tributaries 
and outlets in its alluvial valley, so far as they are 
affected by Mississippi River backwater, between 
Head of Passes, LA (mile 0), and Cape Girardeau, MO 
(1,006 miles AHP-Lower Mississippi mileage terminates 
at mile 954 AHP), and with prosecution of improvements 
in the interest of navigation between 
Cairo, IL (954 miles AHP), and Baton Rouge, LA (234 
miles AHP); and for stabilization of the lower 7 miles 
of the right bank of the Ohio River, to former mouth 
of Cache River. It also is charged with prosecution of 
certain flood control works on the Mississippi River 
and tributaries, as far as they are affected by backwater, 
between Cape Girardeau, MO, and Rock Island, 
IL (1,437 miles AHP), and with prosecution of improvements 
on designated tributaries and outlets 
below Cape Girardeau for flood control, navigation, 
major drainage, and related water uses. Authorized 
operations of the Commission below Cape Girardeau 
are conducted by District Engineers of New Orleans, 
Vicksburg, and Memphis Districts within the areas 
described below, in accordance with approved directives 
and programs and congressional appropriations 
therefor. 
New Orleans District: Mississippi River project 
levees and river channel stabilization as required 
from Head of Passes, mile 0 to 320 AHP, construction 
of five salinity-control structures for fish and wildlife 
enhancement, four in lower Mississippi River Delta 
region, and one in the Mississippi - Louisiana Estuarine 
Area; Bonnet Carre' and Morganza Floodways; 
maintenance and improvements of Mississippi River 
navigation channel from Baton Rouge, LA (mile 234 
AHP), to mile 320; Baton Rouge Harbor (Devils 
Swamp); navigation improvement of Atchafalaya and 
Old Rivers from Mississippi River to Morgan City; 
control of Old and Atchafalaya Rivers; Atchafalaya 
Basin Floodways; flood control and drainage improvements 
in Bayou Cocodrie and tributaries, in 
Bayou des Glaises, and in Upper Pointe Coupee Loop 
area; flood protection in eastern Rapides and southcentral 
Avoyelles Parishes, LA; and freshwater distribution 
from Atchafalaya River to Teche-Vermilion 
Basins. 
Vicksburg District: Mississippi River project levees 
and river channel stabilization as required from upper 
limits of New Orleans District (mile 320 AHP) in 
vicinity of Black Hawk, LA, to Coahoma-Bolivar 
County line, MS (mile 620 AHP) on left bank, and to 
vicinity of mouth of White River, AR (mile 599 AHP), 
on right bank including south bank Arkansas River 
levee to vicinity of Pine Bluff, AR, and north bank 
levee to vicinity of Tucker on left bank of Plum Bayou, 
AR; bank stabilization in lower 36.1 miles of Arkansas 
River; maintenance and improvement of Mississippi 
River navigation channel between miles 320 and 599 
AHP; Vicksburg and Greenville Harbors; specific fish 
and wildlife facilities in Tensas, Yazoo, and Big Sunflower 
Basins; a demonstration erosion control project 
in the Yazoo Basin; flood control and drainage improvements 
in Red River backwater area including 
leveed portions east and west of Black River and south 
* Authorizing legislation (Tables 42-D and 42-E) is listed at the end of this chapter. All other tables are referenced in text and also appear at 
the end of this chapter. 
42-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
of Red River; Jonesville, LA, Boeuf and Tensas Rivers, 
Bayou Macon Basins and tributaries, AR and LA, and 
Bayou Lafourche, LA; Yazoo River Basin, MS, including 
backwater area; Big and Little Sunflower Rivers, 
Deer Creek, and Steele Bayou, MS; and Grand Prairie 
Region and Bayou Meto Basin, AR, including provision 
for agricultural water supply. 
Memphis District: Mississippi River project levees 
and river channel stabilization as required, from 
upper limits of Vicksburg District to north bank of 
Little River diversion channel, MO (1,003 miles AHP), 
a few miles below Cape Girardeau, MO, on right bank, 
and to Cache River diversion channel (967 miles AHP) 
above Cairo, IL, on left bank, including levees and 
revetment on right bank of Ohio River, in Mounds- 
Mound City area, IL; except operations above Cairo, 
IL, do not include channel stabilization on the Mississippi 
River. Maintenance and improvement of Mississippi 
River navigation channel between mile 599 and 
954 AHP and of Memphis Harbor, TN; specific fish 
and wildlife facilities in St. Francis Basin; levees in 
White River backwater area up to vicinity of Augusta, 
AR, and a pumping plant near mouth of White River; 
levees and pumping plants at De Valls Bluff and Des 
Arc, AR; channel improvements in Cache River Basin, 
AR; channel improvements in Big Creek and tributaries, 
AR; improvement works in St. Francis River 
Basin, MO and AR, including backwater area improvements 
in Belle Fountain Ditch and Drainage 
District No. 17, AR; Little River diversion channel, 
MO, and L'Anguille River, AR; Wolf River Basin, TN; 
Obion and Forked Deer River Basins, TN; Reelfoot 
Lake area, including channel improvement for Bayou 
du Chien and Lake No. 9, TN and KY; West Kentucky 
tributaries, KY; Mud Lake pumping station, TN; and 
pumping plants and outlet structures in the Cairo- 
Mounds-Mounds City area, IL. Channel improvements 
to Eight Mile Creek, Arkansas; Ten Mile 
and Fifteen Mile Bayous in West Memphis, and vicinity 
Arkansas; Horn Lake Creek and Tributaries, Mississippi; 
and Nonconnah Creek, Tennessee and Mississippi. 
Navigation channel and harbor improvements 
to Helena Harbor and vicinity, Arkansas 
at Mississippi River, mile 652 AHP. Channel improvements 
and pumping station for Helena, Phillips 
County,and vicinity, Arkansas and St. Johns Bayou 
and New Madrid Floodway, Missouri. 
Field operations of the commission restricted to 
levee construction under Sec. 6, 1928 Flood Control 
Act (local interests contributing one-third of costs and 
furnishing rights-of-way) are conducted within the 
following limits by two districts reporting directly to 
the Commission on matters within their jurisdiction-
St. Louis District: Mississippi River (Sec. 6) 
levees from upper limits of Memphis District to Clemens 
Station, MO (1,254 miles AHP), on right bank, and 
Hamburg Bay, IL (1,215 miles AHP), on left bank, and 
Illinois River from its mouth to mile 120 at Havana, 
IL. Rock Island District: Mississippi River (Sec. 6) 
levees from upper limits of St. Louis District to Rock 
Island, IL (1,437 miles AHP). For work accomplished 
see Table 42-N. page 42-50, Annual Report for 1975. 
MISSISSIPPI RIVER AND 
ALLUVIAL VALLEY BELOW 
CAPE GIRARDEAU, MO 
Location and description. The Mississippi 
River rises in Lake Itasca, MN, and flows generally 
southerly for 2,340 miles through the central portion 
of United States to empty into the Gulf of Mexico 115 
miles below New Orleans. It is improved for barge 
navigation for 1,832 miles to Minneapolis, MN. The 
Mississippi River and its major tributaries, the Missouri, 
Ohio, St. Francis, White, Arkansas, Yazoo, and 
Red-Old Rivers, drain 1,245,000 square miles in all or 
part of 31 states between the Rocky and Appalachian 
Mountains and part of two Canadian provinces. 
Below Cape Girardeau, MO, 53 miles above Ohio 
River, river bottomlands widen abruptly into an alluvial 
valley of 35,460 square miles which was originally 
subjected to flood overflow. A major part of the alluvial 
valley has been protected from floods by levees 
which confine floodflows within a floodplain having an 
average width of 5 miles. (See map of alluvial valley 
of Mississippi River, scale 1:500,000.) Observations 
made by Mississippi River Commission to Sep. 30, 
1982, show approximate all-time maximum and minimum 
discharges between levees as follows: Cairo to 
White River, 2,000,000 and 70,000 cubic feet per second; 
thence to Red River, 2,150,000 and 90,000 cubic 
feet per second; thence to the Gulf of Mexico, 1,500,000 
and 50,000 cubic feet per second in Mississippi River 
and 660,000 and 11,000 cubic feet per second in 
Atchafalaya River. As the 1927 floodflow was not 
confined between levees, maximum discharges recorded 
do not include entire flow of the 1927 flood, 
maximum of record below White River. High water 
and flood stages usually occur in late winter or early 
spring, but great floods such as that of 1937 occurred 
as early as January. Low water stages generally 
prevail from August to December. Extreme all-time 
high in stages recorded at representative gages 
(rounded to nearest foot) are 60 feet at Cairo, 49 feet 
at Memphis, 61 feet at Red River Landing, and 21 feet 
at New Orleans (Carrollton). The river is nontidal 
above Red River Landing where tidal amplitude 
rarely exceeds 0.1 foot during extreme low water. 
Previous projects. For details see page 1944, 
Annual Report for 1932. 
Existingproject. The Mississippi River and Tributaries 
Project in the alluvial valley between Head of 
Passes, LA, and Cape Girardeau, MO, provides 
42-2

MISSISSIPPI RIVER COMMISSION 
protection from floods by means of levees, 
floodwalls, floodways, reservoirs (in Yazoo and St. 
Francis Basins), bank stabilization, and channel 
improvements in and along the river and its tributaries 
and outlets insofar as affected by backwater 
of Mississippi River, including levee work on the 
main stem between Cape Girardeau and Rock Island. 
When completed, 23,621 square miles will be 
protected from the Mississippi River project flood. 
The project also provides for a 12- by 300-foot navigation 
channel between Baton Rouge, LA, and 
Cairo, IL; for salinity-control structures; and for 
channel realinement and improvement including 
bank stabilization and dikes to reduce flood heights, 
control natural tendency of river to lengthen by 
meandering, and protect levees from being destroyed 
by caving banks. Locations of major main 
stem Mississippi River improvements are shown in 
Table 42-A and those for off-main stem tributaries 
are shown in Table 42-B. Pertinent data on dams 
and lakes are shown in Table 42-C. Authorizing and 
incorporating legislation are shown in Tables 42-D 
and 42-E. Summary of presently estimated Federal 
cost of authorized improvements is shown in Table 
42-F. Construction of the existing project began in 
1928 and has continued throughout ensuing years. 
Based on the estimated cost of $11,403,428,000 (cost 
projected through the construction period), and actual 
expenditures through Sep. 30, 1992, of 
$5,373,205,868, the entire project is about 82.6 percent 
complete. 
Recommended modifications. None. 
Local cooperation. The Flood Control Act of 
1928, as amended, applies. Such requirements have, 
in general, been complied with by local interests. 
Terminal facilities. See Port Series No. 21, 1990, 
for Ports of Baton Rouge and Lake Charles, LA; Port 
Series No. 20, 1990, for Port of New Orleans, LA; also 
folio of Flood Control and Navigation Maps of Mississippi 
River from Cairo, IL, to the Gulf of Mexico (59th 
edition), 1992. 
Project cost. Total allotted for flood control, excluding 
maintenance charges through Aug. 18, 1941, 
chargeable under authorizations to Sep. 30, 1992, was 
$5,408,357,337. (See Table 42-V.) (See also Tables 
42-U, 42-W, and 42-X for additional financial 
statements. 
Operations and results duringfiscalyear. The 
339th Session was held Apr. 6-10, 1992, on board the 
Motor Vessel MISSISSIPPI enroute on the Mississippi 
River from Cairo, IL, to Baton Rouge, LA. Bank 
protection works, levees, and channel conditions were 
observed enroute. On Apr. 4-5, 1992, the Commission 
traveled from Paducah, KY, on the Ohio River, up the 
Cumberland River, through the Barkley and Kentucy 
Locks, and Tennessee River and Ohio River before 
arriving at Cairo. Public meetings were held at Cairo, 
IL; Helena, AR; Greenville, MS; and New Orleans, LA, 
with approximately 240 people in attendance. This 
session adjourned at New Orleans, LA, at 9:50 a.m. on 
Apr. 10, 1992. 
The 340th Session was held on Jun. 16, 1992, at its 
headquarters in Vicksburg, MS, for the purpose of 
considering the Memphis District project report entitled 
"Whitman's Creek, Arkansas, Final Feasibility 
Report." After a briefing and discussions, the members 
approved and signed the document, authorizing 
its transmittal to the Chiefs office. This meeting adjourned 
at 10:10 a.m. on Jun. 16, 1992. 
The 341st Session was held Aug. 31 - Sep. 4, 1992, 
on board the Motor Vessel MISSISSIPPI. The Commission 
inspected the Mississippi River from Cairo, 
IL, to Morgan City, LA. Bank protection works, levees, 
and channel conditions were observed enroute. Public 
meetings were held at Cairo, IL; Memphis, TN; Vicksburg, 
MS; and Morgan City, LA; with approximately 
160 people in attendance. This 341st Session of the 
Commission adjourned at Morgan City, LA, at 10:30 
a.m., on Sep. 4, 1992. 
Records of Proceedings of all sessions of the Mississippi 
River Commission are on file in the office of the 
President. 
Alluvial Valley Mapping 
General. Contoured quadrangles and general 
maps of the alluvial valley are available for departmental 
use and public distribution under prescribed 
regulations. Preparation, revision, and publication of 
quadrangle maps (scale 1:62,500) continued. 
Roadmap-type information brochures of principal portions 
of the overall project were published along with 
pamphlets on the subject of flood control and navigation. 
Maps and supplemental data sheets for active 
works were updated and published as required. 
The 1992 (59th) edition of the folio of flood control 
and navigation maps (scale 1:62,500) covering the 
Mississippi River from Cairo, IL, to the Gulf of Mexico 
was revised and printed. 
Approximately 4,097 flight-line miles of black-andwhite 
aerial photography (various scales); 1292 flightline 
miles of color photography; and about 54.3 hours 
of oblique photography were flown along the Mississippi 
River and tributaries in the New Orleans, Vicksburg, 
and Memphis Districts. 
Work accomplished in the Districts: New Orleans 
District: The revision of 1:62,500 scale quadrangle 
maps Artonish, LA; Batchelor, LA; Grosse Tette, 
LA; and Hahnville, LA, were completed and printed 
in 1992. 
Memphis District--Series conversion of U.S. Geological 
Survey 1:24,000-scale to 1:62,500-scale quads 
of Jackson, TN; Como, MS; Luray, TN; Mayfield, KY; 
42-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Water Valley, KY; Corinth, MS; Zelma, MO; Lonoke, 
AR; Guys, TN; and Mt. Peter, TN are complete. 
Vicksburg District--Series Conversion of U.S. Geological 
Survey 1:24,000 - scale quadrangles to 1:62,500 
- scale quadrangles of Crosby, MS; Gloster, MS; Union 
Church, MS; Bude, MS; Canton, MS; Sharon, MS; 
Carthage, MS; Thomastown, MS; Edinburg, MS; Liberty, 
MS; Hodge, LA; Jonesboro, LA; Goldonna, LA; 
and Franklinton, LA are in progress. Woodville, MS; 
Morton, MS; Forest, MS; Pelahatchie, MS; Fayette, 
MS; Yazoo City, MS; Flora, MS; Poplarville, MS; Bernice, 
LA; Ruston, LA; Sarepta, LA; and England, AR, 
were published. 
Floods 
Streamflow observations during the fiscal year 
follow: 
Memphis District--Mississippi River crest stage of 
41.7 feet at Cairo gage on Dec. 9, 1991, and maximum 
discharge of 898,000 cubic feet per second occurred at 
Hickman, KY and crest stage of 25.7 feet at Memphis 
on Dec. 13, 1991, with maximum discharge of 936,000 
cubic feet per second on Dec. 13, 1991. 
Vicksburg District--No significant flooding in the 
Vicksburg District during FY 92. Peak stages and discharges 
on the Vicksburg Districts reach of the Mississippi 
River were as follows: Arkansas City, 25.8 feet on 
Mar. 29, 1992, and maximum discharge of 940,000 cubic 
feet per second; Vicksburg, 32.1 feet on Mar. 30, 1992, 
and maximum discharge of 956,000 cubic feet per 
second. 
New Orleans District--On the Mississippi River, 
the Red River Landing gage recorded a maximum 
stage of 47.0 feet NGVD on Dec. 19, 1991, and the New 
Orleans gage recorded a maximum stage of 12.3 feet 
NGVD on Dec. 20, 1991. On the Atchafalaya River, 
the Simmesport gage recorded a maximum stage of 
28.75 feet NGVD on Dec. 20, 1991. Hurricane Andrew, 
which hit south central Louisiana on Aug. 26, 1992, 
set several new highwater records in that area including 
7.60 feet NGVD at the Atchafalaya Bay near 
Eugene Island gage and 7.65 feet NGVD at the Round 
Bayou at Deer Island gage. 
Studies and Investigations 
General investigations. Surveys and reports, authorized 
by laws and by Senate and House Public 
Works Committee resolutions, were made as required. 
Collection and study of basic data continued. The 
Energy and Water Development Appropriation Bill of 
1990 directed the Corps to develop the most cost-effective 
flood control plan for the City of West Memphis 
without regard to frequency offlooding, drainage area, 
and the amount of runoff. It also directed the Secretary 
of the Army to incorporate existing flood control 
features of the Bayou Rapides Drainage Structure and 
Pumping Plant into the Lower Red River, South Bank 
Levees portion of the MR&T Project. 
Engineering studies. A research program was 
continued for development of materials and more effective 
and economical design of regulation features 
for placing and stabilizing the Mississippi River in a 
suitable alinement. 
Potamology investigations of river behavior continue to 
be made. Investigations into the major cause-and-effect 
relationships attributable to major changes in stage-discharge 
relationships on the Mississippi River as a result of 
both natural and man-made modifications are continuing. 
Mississippi River and Tributaries--Levees 
Operations and results during fiscal year. 
This feature consists of construction of new, and enlargement 
of existing, levees to approved grade and 
section; construction and restoration of levee berms; 
and construction, repair, and maintenance of roads on 
levees. Work accomplished is summarized in Table 
42-N and further broken down as follows: 
New Orleans District-Enlarged 22.7 miles of levees 
and surfaced 4.0 miles of roads on levees in the 
Main Stem System. See Table 42-K. 
Vicksburg District-Surfaced 5.8 miles of roads on 
levees in the Main Stem System. See Table 42-L. 
Memphis District--Completed 1.4 miles of berms 
in the Main Stem System. See Table 42-M. 
Condition as of Sep. 30. (See Tables 42-K, 42-L, 
42-M, and 42- N.) There are 1,608.7 miles of levees 
authorized for the Mississippi River below Cape Girardeau, 
of which 1,601.9 are in place with 1,245.6 built to 
approved grade and section. The Main Stem Levee 
System consists of 2,202.5 miles, of which 2,195.7 are in 
place with 1,731.9 miles completed to approved grade 
and section. Included in this system are additional 
levees and structures along the south bank of Arkansas 
River (85.4 miles); along the south bank of Red River 
(59.2 miles, with 59.2 completed); and 449.2 miles in the 
Atchafalaya River Basin, with 449.2 in place and 341.7 
completed to grade and section (see Table 42-N). Of the 
authorized 681.5 miles of berms, 525.5 are complete. 
Graveled or hard-surfaced roads have been constructed 
on 2,087.0 miles of these levees. 
There are an additional 1,511.0 miles of authorized 
tributary levees in the MR&T Project, of which 
1,125.3, are in place with 974.8 to approved grade and 
section. Berms have been completed on 15.3 miles and 
858.4 miles of graveled or hard-surfaced roads have 
been constructed on the levees. 
For summary of levee work Table 42-N. 
42-4

MISSISSIPPI RIVER COMMISSION 
Mississippi River and Tributaries-- 
Channel Improvements 
Operations and results during fiscal year. 
Dredging: Mississippi River Main Stem--(See Table 
42-G.) Work included dredging 34,390,600 cubic 
yards for maintenance of channel and harbor improvements. 
Minimum channel depth of 9 feet was 
maintained. Dredging was done with the following 
plant: New Orleans District, channel maintenance 
was performed by Government-owned dustpan dredge 
Jadwin at Wilkerson Point Crossing. Vicksburg District, 
channel maintenance was performed by government-
owned dredge Jadwin. The MR&T harbors, in 
the Vicksburg District, maintained were Greenville 
and Vicksburg. Memphis District channel maintenance 
dredging was performed by Government-owned 
dustpan dredge Burgess, and leased dustpan dredge 
Lenel Bean. 
The MR&T Harbor maintained in Memphis District 
was Memphis Harbor (McKellar Lake), by leased 
cutterhead dredges Natchez. 
Bank revetment and dikes: (See Table 42-H, 42-I, 
and 42-J.) Construction of 19.45 miles of new bank 
revetment and 141,132 squares of concrete mattress, 
for maintenance, along the Mississippi River was completed 
by Government plant and hired labor. Also, 
14.98 miles of new dikes were constructed and required 
maintenance was performed. 
Approximately 0.3 mile of new bank revetment was 
constructed on the Atchafalaya River. 
Other work performed in the interest of navigation, 
supplementing maintenance dredging on Mississippi 
River between Cairo, IL, and Baton Rouge, LA, included 
removal of snags, wrecks, and obstructions; 
issuance of bulletins by the Vicksburg District providing 
information on available high-water velocities at 
selected locations; maintenance of bulletin boards 
showing daily gage readings at regular MRC gages; 
and contact pilot service furnishing navigation interests 
with latest information and advice on channel 
conditions and navigation interests. Cost of this work 
is given in Table 42-R. 
Condition as of Sep. 30. In carrying out authorized 
channel improvement program between Baton 
Rouge and Cairo, 16 cutoffs were developed between 
1933 and 1942. These, combined with chute channel 
development and alignment improvements, decreased 
channel length between these cities by about 170 miles. 
However, current velocities increased the attack on the 
banks and the river began to regain its length. As a 
result, the net shortening between 1933 and 1962 was 
114 miles of the theoretical 170-mile cutoff. 
There are now in place 973.11 miles of operative 
bank revetment and 256.1 miles of dikes on the lower 
Mississippi River. This amount of channel stabilization 
should prevent the river from regaining much 
more of its length due to meandering. A navigation 
channel 9 by 300 feet is being accomplished by revetment 
and dikes and maintained by dredging as required 
during the low- water season. Due to growing 
effectiveness of channel improvement program, average 
maintenance dredging requirements are steadily 
being reduced, and an increase in navigable depth is 
being obtained. Approximately 128.5 miles of foreshore 
protection have been constructed along the 
lower Mississippi River. 
There are 70.2 miles of revetment and 5.2 miles of 
dikes on tributary channels as listed in Tables 42-H, 
42-I, and 42-J. 
New Orleans District 
ATCHAFALAYA BASIN, LA 
Operations and results during fiscal year. 
New work by hired labor: Real estate activities and 
planning for construction were continued. 
Construction of levee enlargements and floodwalls 
continued on the east and west protection levees. 
There were three levee enlargement and floodwall 
contracts completed along the east protection levee 
over a distance of 3.3 miles with a placement of 35,000 
cubic yards during the period. Another contract was 
completed in the area west of Berwick, LA, to enlarge 
4.1 miles of levee with a placement of 37,300 cubic 
yards during the period. Another contract completed 
for the placement of 1.3 miles of foreshore protection 
along the east protection levee. A contract for the 
repair of slides at two locations along the east protection 
levee was completed with the placement of 35,000 
cubic yards. 
There are 4.0 miles of levee enlargement under construction 
on the east protection levee with 94,300 cubic 
yards of placement during the period. Two other other 
ongoing contracts during this period provided 9.1 miles 
of levee enlargement and floodwall work on the west 
protection levee with the placement of 238,200 cubic 
yards. Another contract for 3.4 miles of levee enlargement 
west of Berwick, LA, is ongoing with the placement 
of 45,400 cubic yards during the period. 
Two channel training contracts were completed in 
FY 92. Another contract continued from FY 1990. The 
contract initiated in FY 1990 for training works, consisted 
of 22 miles of channel embankment amounting 
to 335,000 cubic yards of material along the banks of 
the Atchafalaya River above Morgan City, Louisiana 
was completed. Construction of the Interior Circulation 
Channel and Closure/Weir was completed. The 
contract consisted of the removal of 477,300 cubic 
yards of material to construct a circulation channel in 
the basin near Grand Lake and a closure and weir 
42-5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
near Lake Chicot. The closure consisted of 9,100 cubic 
yards of fill and the weir was constructed with 3,800 
tons of rock. Another contract for closure Phase 1 was 
initiated and completed during the period. It consisted 
of 50,600 cubic yards for eight earthen closures where 
small pipeline canals or bayous intersected the 
Atchafalaya main channel. 
One channel realignment contract was completed 
during the period. The East Freshwater Distribution 
Channel and Little Tensas Bayou Closure provides a 
channel between the Atachafalaya River and Upper 
Grand River and an earthen closure at Little Tensas 
Bayou. Channel construction removed 2,000,000 cubic 
yards and the closure was constructed of 90,000 cubic 
yards of fill material. 
Maintenance by hired labor: Operation and maintenance 
of Bayou Boeuf, Berwick, and Bayou Sorrel 
Locks, Morganza Control Structure, Dewatering and 
major repairs were accomplished on two gates at both 
Bayou Boeuf and at Bayou Sorrel Locks, along with 
numerous drainage structures as required, condition 
and operation studies, and water control management. 
One levee enlargement was completed during 
the period. Two of three gap closures were ongoing at 
one location and three of seven were completed at 
another location. 
Maintenance dredging was performed, resulting in 
the removal of 2,500,000 cubic yards by two leased 
cutterhead dredges from Berwick Bay harbor in February 
and June 1992. 
Condition as of Sep. 30. Construction was initiated 
Aug. 7, 1929, with commencement of the west 
protection levee from Bordelonville to Hamburg, LA. 
The project is 86 percent complete. The current estimated 
Federal cost is $1,540,000,000 and non-Federal 
cost is $8,000,000. Of the 449.2 miles of levees and 
floodwalls authorized for the Atchafalaya system, 
341.7 miles are built to grade. See Table 42-K for 
status of levees. 
Major items remaining to be completed include 
completion of levees to grade and section, channel 
training works in the lower basin, realignment of the 
two principal distributaries of the Atchafalaya River, 
and construction of two freshwater distribution structures. 
Approximately 38.4 miles of bank stabilization 
have been placed as shown in Table 42-H. 
BATON ROUGE HARBOR 
(DEVILS SWAMP), LA 
Condition as of Sep. 30. Construction of the first 
2.5 miles of the proposed 5.0 miles of channel was 
initiated in January 1958 and completed in July 1959, 
with 7,458,086 cubic yards excavated. 
Maintenance dredging was not performed in FY 
1992. 
The remaining 2.5 miles were to be constructed 
when development of the initially constructed portion 
warrants expansion. Project expansion has not been 
necessary. Therefore this feature was deauthorized 
on Nov. 2, 1979, under the provisions of Section 12, 
Public Law 93-251 (WRDA 74), as amended. 
BAYOU COCODRIE AND 
TRIBUTARIES, LA 
Operations and results during fiscal year. 
Maintenance by hired labor consisted of water control 
management. 
Condition as of Sep. 30. Construction was initiated 
in June 1946 and is 57 percent complete, based 
on the current estimated Federal cost of $20,400,000 
and non-Federal cost of $323,000. See page 2031, 
Annual Report for 1961, for description of completed 
work. 
Work required to complete the project consists of 
enlargement of 13.5 miles of upper Bayou Boeuf, channel 
improvement of 25.3 miles of Bayou Cocodrie, 
enlargement of Bayou Courtableau from Washington, 
LA, to the west protection levee, and additional culverts 
through the west protection levee at 100 percent 
Federal cost in lieu of the previously authorized diversion 
channel from Washington to the Bayou 
Courtableau drainage structure. 
With the termination of the Eastern Rapides and 
South Central Avoyelles project, it has become necessary 
to provide an adequate outlet structure solely for 
the Bayou Cocodrie and Tributaries project. The economic 
effects of this change along with current benefits 
estimates have caused the benefit-cost ratio for 
the project to be less than unity. As a result, the 
project has now been classified as "inactive." If economic 
conditions change, the project could be 
reactivated. 
BONNET CARRE SPILLWAY, LA 
Operations and results during fiscal year. 
Maintenance by hired labor: Condition and operation 
studies, water control management, and ordinary 
maintenance of the control structure and spillway 
continued. 
Condition as of Sep. 30. Construction of the 
spillway was initiated in FY 1929. The control structure 
was completed in 1931, levees were completed in 
1932, and utility crossings were completed in 1936. 
The cost of the completed work is $14,212,200. 
It was necessary to operate the structure to reduce 
flood stages in 1937, 1945, 1950, 1973, 1975, 1979, and 
1983. 
42-6

MISSISSIPPI RIVER COMMISSION 
A new office building was completed in FY 1990 at 
a cost of $245,500. 
OLD RIVER, LA 
Operations and results during fiscal year. 
Maintenance by hired labor consisted of operation 
and maintenance of the lock and control structures as 
required, condition and operation studies, water control 
management, maintenance of cleared areas, levee 
shaping, and engineering studies. A picket boat was 
previously used at the inflow channels to the low sill 
and auxiliary control structures. It was removed from 
operation in FY 1988. 
Maintenance by contract: Maintenance dredging 
was not performed in FY 1992. 
Condition as of Sep. 30. Construction began September 
1955 and is complete at a Federal cost of 
$292,273,000. Principal items completed are as follows: 
Low-sill structure, June 1959; overbank structure, 
October 1959; auxiliary structure, September 
1986; levees and levee enlargements, October 1963; 
inflow and outflow channels for the low-sill structure, 
February 1961; inflow and outflow channels for the 
auxiliary structure, August 1987; navigation lock 
completed December 1962 and opened to navigation 
March 1963, at which time Old River was closed to 
navigation with a rock and earthfill dam; highway 
approaches and bridge over the lock completed March 
1965. Approximately 9.4 miles of bank protection 
have been constructed at the inflow and outflow channels. 
(See Table 42-H for details of bank protection.) 
Vicksburg District 
TENSAS BASIN, AR AND LA 
Operations and results during fiscal year. 
(a) Boeuf and Tensas Rivers, and Bayou 
Macon, AR and LA. Planning and design on project 
features are complete. The Lake Chicot Pumping 
Plant and related features are complete and in operation. 
The riverside gate repair contract awarded Aug. 
26, 1988, and the contract for the bulkhead gate repairs 
awarded Aug. 18, 1989, and the contract for 
pump repairs awarded Jan. 24, 1990. No further work 
on the Tensas River Project (Separable Element) will 
be initiated due to lack of commitment from a local 
sponsor to cost share remaining E&D and construction. 
This project has been placed in the "inactive" 
category. 
(b) Red River backwater area. Planning and 
design continued on project features. All channel work 
required to get flows to the Tensas Cocodrie Pumping 
Plant and gravity structure is complete. The gravity 
structure and the pumping plant are complete and are 
being operated and maintained by contract. One mitigation 
item, the construction of two water control 
weirs, was completed in May 1988. Contracts for three 
additional mitigation features were awarded in December 
1988 and February 1989. Planning and design 
has been deferred on the two remaining mitigation 
features. Tensas-Cocodrie, Item 4-A, levee enlargement, 
6.3 miles in length, was completed in September 
1988, and Item 4-B, 2.4 miles of levee enlargement, 
was completed in October 1990. A contract for 
Item 2 was awarded in January 1991 and is substantially 
complete. These contracts will complete the 
levee enlargement for all of the levee system, except 
0.8 miles. 
Work on the Below Red River Phase II GDM has been 
deferred pending economic justification. A contract for 
Sicily Island Item 5-B, is substanially complete and the 
contract for Sicily Island Item 5A-R was awarded Jun. 
16, 1992. 
Condition as of Sep. 30. 
(c) Boeuf and Tensas Rivers, and Bayou 
Macon, AR and LA. Channel improvement has been 
accomplished on 741.7 miles of project streams, providing 
major drainage outlets for the tributary areas. 
Additionally, 61.0 miles of the Tensas River has been 
cleared and snagged. The GDM for the Tensas River 
Project, above mile 61, including Mill Bayou-Bayou 
Vidal is complete. However, no further work will be 
initiated due to lack of a local sponsor. 
(d) Red River backwater area. Levees in Tensas-
Cocodrie area are complete except for levee raising 
of 0.8 miles. The work comprised 93.1 miles of new 
levee, excluding 2.1 miles of high ground where no 
levees are required, and 86.9 miles of gravel road on 
levees. Construction of 63.4 miles of levee, Larto Lake 
to Jonesville levee system, has been completed. A 
levee grade reevaluation study for all levee systems in 
the Red River Backwater area was completed in Mar. 
1985. Based on results of that study, work is underway 
to complete enlargement of the Tensas-Cocodrie levee 
system. Levee Item 4-A and levee Item 4-B have been 
completed. Levee work on Sicily Island area consists 
of 56 miles of new levee, 8.7 miles of which have been 
completed. 
LOWER ARKANSAS BASIN, AR 
Condition as of Sep. 30. Arkansas River levees. 
A total of 56.2 miles of the 61.5 miles of north bank 
levees and all of the 85.4 miles of south bank levees 
have been completed to approved grade and section. 
These levees above mile 36.1 are protected by bankprotection 
works constructed as a feature of project for 
Arkansas River and tributaries, AR and OK. For 
present status of this work, see report of Little Rock 
District. Below mile 36.1, needed bank protection is 
constructed with project maintenance funds. Little 
Bayou Meto gates and lifting mechanism were replaced 
during FY 88. 
42-7

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
YAZOO BASIN, MS 
Operations and results during fiscal year. 
(a) Yazoo City and Belzoni protection works. 
Contract forces continued operation and maintenance 
of levees, drainage facilities, and pumping plant. 
(b) Greenwood protection works. Contract 
forces continued operation and maintenance of pumping 
plant, levees, and drainage facilities. 
(c) Main stem. Remaining unconstructed features 
are subject to Yazoo Basin Reformulation Study. 
Contract forces continued operation and maintenance 
of channels, levees, and drainage facilities. 
(d) Big Sunflower River, etc. Weir A on the 
National Wildlife Refuge and the instream weir at 
Mile 56.0 in Steele Bayou have been completed. 
Work continued throughout FY 92 on Steele Bayou, 
Item 66-B, and it is now 87 percent complete. The 
contract for selective clearing and snagging on Black 
Bayou, Item 1-A, was awarded on Sep. 22, 1992. The 
Draft Reformulation Report for the Upper Steele 
Bayou Project was published during the past FY, 
and the final report is scheduled for completion in 
early FY 93. 
(e) Tributaries. Construction: (1) Levees. 
Levee work associated with the last item of work on 
Ascalmore-Tippo Project is complete. Levee work associated 
with Item 1 and Item 1-A Pelucia Creek is 
complete. Construction contracts are underway and 
scheduled for FY 93 completion on Pelucia Creek, Item 
2, Item 3, Rising Sun Pumps 1 and 2 and Pelucia Creek 
Pump. Pelucia Creek Levee Item 4 construction contract 
is scheduled for award in FY 93. 
(2) Channels. Construction of the Alligator-Catfish, 
Round Lake Water Control Structure was completed 
Nov. 28, 1989. Construction on the remaining 
channel work on the Ascalmore-Tippo Project is 
complete. Contract forces continued operation and 
maintenance of channels, levees, and drainage 
facilities. 
(f) Enid Lake. (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Rehabilitation of boat channels and snagging 
and clearing of tributary streams in the lake area 
continued. Maximum pool elevation in the lake was 
257.0 feet NGVD on Dec 16, 1991, when storage in the 
flood control pool was 397,200 acre-feet. Peak 24- 
hour inflow was 29,600 cubic feet per second on Dec. 
21, 1991. On Sep. 30, 1992, pool elevation was 245.9 
feet NGVD and storage in the flood control pool was 
209,200 acre-feet. 
(g) Grenada Lake. (See Table 42-C.) Construction 
of remaining public-use facilities has been deferred 
pending development of cost-sharing agreements 
with local interests for construction and non- 
Federal operation and maintenance, consistent with 
projects for which recreation facilities are being constructed 
under the provisions of the Federal Water 
Project Recreational Act of 1965 (Public Law 89-72), 
as amended. Maximum pool elevation in the lake was 
213.1 feet NGVD on Dec. 16, 1991, when storage in 
the flood control pool was 484,000 acre-feet. Peak 
24-hour inflow was 63,000 cubic feet per second on 
Dec. 31, 1991. On Sep. 30, 1992, the pool elevation 
was 207.8 feet NGVD and storage in the flood control 
pool was 330,100 acre-feet. 
(h) Sardis Lake (See Table 42-C.) The dam and 
appurtenant structures were maintained and operated. 
Clearing of tributary streams in the lake area 
continued. Maximum pool elevation in the lake was 
270.2 feet NGVD on Dec. 16, 1991, when storage in 
the flood control pool was 996,900 acre-feet. Peak 
24-hour inflow was 76,300 cubic feet per second on 
Dec. 3, 1991. On Sep. 30, 1991, the pool elevation was 
255.6 feet NGVD and storage in the flood control pool 
was 478,900 acre-feet. 
(i) Arkabutla Lake. (See Table 42-C.) The dam 
and appurtenant structures were maintained and 
operated. Clearing of tributary streams in the lake 
area was continued. Maximum pool elevation in the 
lake was 229.3 feet NGVD on Dec. 15, 1991, and 
storage in flood control pool was 279,500 acre-feet. 
Peak 24-hour inflow was 26,300 cubic feet per second 
on Dec. 3, 1991. On Sep. 30, 1992, the pool elevation 
was 217.3 feet NGVD, and storage in the flood control 
pool was 91,500 acre-feet. 
(j) Yazoo Basin backwater. The Yazoo area 
backwater levees are complete, including the backwater 
levee from the Mississippi River levee to the west 
levee of the lower Auxiliary Channel, the Little Sunflower 
River drainage structure, and the connecting 
channel from the Steele Bayou drainage structure to 
the Big Sunflower River. A Phase I GDM was completed 
in FY 82 which addresses rural flooding from 
ponded runoff inside the backwater levee. A GDM for 
a pumping station of 17,500 cfs to reduce this ponding 
was approved Jul. 12, 1985. Later budgetary guidance 
reduced the pumping plant capacity to 10,000 
cubic feet per second. A contract for portions of the 
inlet and outlet channel excavation for the pumping 
plant has been completed. A construction schedule for 
the remaining project features is dependent upon the 
local sponsor meeting the cost sharing requirements 
specified in the Water Resources Development Act of 
1986. 
The Satartia area backwater levee is complete. 
Rocky Bayou area levee Items lA and lB have been 
completed. Completed backwater levees will require 
raising to provide the degree of protection intended 
based on the project design flow line developed for the 
Mississippi River following the 1973 flood. 
42-8

MISSISSIPPI RIVER COMMISSION 
Four Greentree Reservoirs and pumping stations 
are now complete. A decision on construction of the 
three remaining reservoirs will be made in the future. 
Mitigation of the Yazoo Backwater is now underway. 
Approximately 8,800 acres of cleared, frequently 
flooded, agricultural lands have been obtained 
in the Yazoo Backwater area of Mississippi 
to mitigate the wildlife losses resulting from construction 
and operation of the Yazoo Area and 
Satartia Area levees projects. This land is now 
being reforested and will be managed for terrestrial 
wildlife. The reformulation of the backwater project 
is scheduled to begin in FY 93. 
(k) Upper Yazoo Projects. The first eight items 
of channel improvement, approximately 56 miles, and 
four drainage structures have been completed. This 
work extends from Yazoo City, Mississippi, to about 
15 miles upstream of Belzoni, Mississippi. 
The Fort Pemberton Flood Control Structure was 
completed on Apr. 29, 1991. 
Contracts scheduled for award after FY 90 are subject 
to Yazoo Basin Reformulation Study. 
(1) A contract for bank stabilization on Upper Yazoo 
Projects, Item 2-B-R, was completed. 
(2) Construction contracts for Levee Item 3A-2 and 
Roebuck Lake Water Control Structure were awarded 
Jul. 29, 1992, and Sep. 25, 1992, respectively. Construction 
is scheduled for completion in FY 93. 
(3) Contracts for Fort Loring Water Control Structure 
and Tchula Lake Weirs are scheduled for award 
in FY 93 pending completion of right-of-way 
acquisition. 
(1) Streambank erosion control. Construction 
of the following projects has been completed: 
Tillatoba and Hunter Creeks, Items 1 and 2; Hunter 
Creek, Item IA; South Fork Tillatoba Creek, Items 5A 
and 5B; North Fork Tillatoba Creek, Items A and 3A; 
Batupan Bogue, Items 4A, 4A-1, and 4A-2; Perry 
Creek, Items 6A and 6B; Johnson Creek, Items 9A, 
9B, and vegetative treatment, Item 12; Goodwin 
Creek, Items 8A, 8B, and 8C; and Hotopha Creek, 
Item 7. 
All construction under this feature is complete, 
and a final report was submitted to the Secretary of 
the Army Jan. 5, 1982. All work constructed has 
been turned over to the local sponsors for operation 
and maintenance except for the instrumented system 
on Goodwin Creek where the structures were 
retained for possible future studies. The Demonstration 
Erosion Control Project (DEC), a joint project 
with the USDA Soil Conservation Service was 
initiated by FY 85 appropriations as a continuation 
on streambank erosion control efforts. The purpose of 
the project is to demonstrate the applicability of a 
systems approach to the design of erosion, sedimentation, 
and flood control works by applying this approach 
to 15 demonstration watersheds in the Yazoo 
Basin hill area. During FY 92, work continued in the 
DEC toward development of the systems plans and 
implementation of a monitoring program. The District 
completed the construction of 17 grade control 
structures; 32,720 linear feet of bank stabilization; 
and 58 riser pipe grade control structures. 
Condition as of Sep. 30. The first feature of Yazoo 
Basin project was started in 1936, and the total project 
is about 65 percent complete. A total of 50.9 miles of 
backwater levee has been completed to the interim 
grade. 
(m) Reformulation Study. Investigations of 
engineering, economic, and environmental aspects 
of the uncompleted segments of the upper Steele 
Bayou and Upper Yazoo Projects continued. The 
reformulation study evaluates reasonable arrays of 
alternatives to the project features remaining after 
construction of items budgeted and scheduled for 
award in FY 90. This effort is being conducted in 
phases, with the final upper Steele Bayou report 
scheduled for completion in December 1992 and the 
final Upper Yazoo Projects report scheduled for completion 
in December 1993. Studies of the uncompleted 
portions of the projects include acquisition of 
new land use, survey, mapping, real estate, and 
environmental data. Among the findings of the completed 
Yazoo River Basin Study were preliminary 
indications that a conceptual multipurpose flood 
control/water supply plan for the Yazoo Delta Area 
was potentially feasible. However, further studies 
of the primarily agricultural water supply plan are 
not in consonance with policy. 
LOWER RED RIVER-SOUTH BANK 
RED RIVER LEVEES, LA 
Operations and results during fiscal year. 
New work by hired labor consisted of engineering 
studies. The engineering studies included preparation 
of a report on incorporation of the Bayou Rapides 
outlet into the project. This report was submitted to 
higher authority. 
Maintenance by hired labor consisted of water control 
management and economic studies. 
Condition as of Sep. 30. Construction was initiated 
in FY 29 and is complete. All of the 59.2 miles of 
levees authorized are completed to approved grade 
and section. 
42-9

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Memphis District 
ST. FRANCIS BASIN, AR AND MO 
Operations and results during fiscal year. 
(a) Little River Drainage. Alteration of New 
Madrid County Route 282 for Ditch 281-9, awarded 
Apr. 18, 1988, Oct. 1, 1991, completed. 
(b) Upper St. Francis River. Alteration of seven 
powerlines Ditches 10 and 12 awarded Feb. 24, 1987, 
Oct. 1, 1991, completed. 
Belle Fountain, Channel Enlargement, awarded 
Jul. 28, 1989, Oct. 1, 1991 completed. Main Ditch 9 
Bridge, Miles 1.85 and 3.92, awarded Mar. 30, 1990, 
Apr. 25, 1991 completed. Main/New Franklin 
Bridge, Miles .54 and 3.03, awarded Sep. 28, 1990, 
Oct. 12, 1991 completed. Below Locust Creek, 
awarded Jun. 26, 1990, Oct. 3, 1991 completed. 
Alteration Highway E Bridge, awarded Sep. 28, 
1989, 20 percent complete. Main/N. Franklin Br. 
2.35 awarded, Sep. 30, 1992. Lake County Levee 
Surfacing awarded Sep. 26, 1992. Ditch I-1 Excan., 
awarded Jul. 31, 1992. Mud Lake Floodgate 
awarded, Jun. 30, 1992, 10 percent completed. 
Main/N. Franklin Ditch, awarded Jul. 2, 1992, 20 
percent completed. Castor/River I-2 awarded, Jun. 
25, 1992, 90 percent completed. Riprap Protection 
Hwy 'U' Missouri, awarded, Jun. 30, 1992, completed 
Aug. 20, 1992. DD17 Trash Barrier awarded, 
Jun. 30, 1992, 50 percent completed, Bypass Steel 
Bridge, mile 1.00, awarrded, Jan. 9, 1992, completed 
Aug. 8, 1992. Big Slough Ditch I-2M-3M, awarded 
Dec. 12, 1992, completed May 15, 1992. Mat Casting 
at Richardson awarded, Oct. 8, 1991, 85 percent 
completed. Culvert Replacement Blue Bayou, 
awarded, Sep. 30, 1991, 35 percent completed. Elk 
Chute W. Ditch Resurfacing, awarded Aug. 26, 
1991, completed Apr. 11, 1992. Item 2A Halls Br., 
awarded Mar. 22, 1991, completed May 13, 1992. 
Main Ditch Channel Enlargement, awarded Jan. 31, 
1991,completedMay 21, 1992. Canoe Lake Floodgate, 
awarded Jul. 31, completed Sep. 24, 1991. 
St. Francis River and Tributaries 
Cleaning and Painting DD17 Pumping Station 
awarded Apr. 30. 1991, Sep. 23, 1991 completed. 
Ditch 9 Channel Enlargement awarded Jun. 28, 
1991, 85 percent complete. Ditch 10 Channel Excavation 
awarded May 30, 1991, Dec. 11, 1991 completed. 
10th/28th Pump Plant awarded Jul. 28, 
1990, Oct. 3, 1991 completed. 10th/28th pump repairs 
awarded Jul. 20, 1989, 90 percent completed. 
Main Ditch Channel Enlargement awarded Jan. 31, 
1991, Apr. 11, 1992 completed. Lower Buffalo Creek 
Channel Clearing, awarded Sep. 28, 1990, Oct. 3, 
1991 completed. 
(c) Lower St. Francis River. Channel Cleanout, 
Madison to Highway 64, awarded Sep. 30, 1988, Dec. 
4, 1991 completed. 
Slope Restoration below Marked Tree, Item 2, 
awarded Sep. 23, 1991 completed. W. G. Huxtable 
Gravel Restoration Hwy 79, awarded July 18, 1991 
completed. Madison-Hwy 64 Channel Cleanout I-3 
awarded Sep. 25, 1990, completed Dec. 10, 1991. State 
Bridge, Main-New Franklin, Mile 3.64, awarded Sep. 
29, 1989, 15 percent complete. State Bridges, I-2, 
Ditch 1, Miles 14.32 and 15.00, awarded Jun. 13, 1989, 
15 percent complete. State Bridges, I-3, Ditch 1, Miles 
22.80 and 27.63 awarded Oct. 23, 1990, 50 percent 
complete. Princedale/Birdeye Levee, awarded Sep. 11, 
1992. Scour Repair Madison - Marianna, awarded Jul. 
30, 1992. Levee Madison - Hwy 64, awarded Jul. 31, 
1992, 50 percent complete. County Bridges, Mile 
20.50, 21.60 - Ditch 1, I-3 awarded May 29, 1992, 35 
percent complete. Tyronza Slide/Culvert, awarded 
Apr. 27, 1992, completed Aug. 2, 1992. County Bridge, 
mile 19.55 awarded, Feb. 4, 1992, completed Sep. 26, 
1992. Horseshoe Lake Levee Resurfacing, awarded 
Nov. 21, 1991, completed Apr. 18, 1992. Casting at 
Helena, awarded Oct. 18, 1991, 98 percent complete. 
Channel Excav, Cockle Burr Slough, awarded Sep. 12, 
1991, completed May 30, 1992. 
Condition as of Sep. 30. 
(a) Little River Drainage. Project was initiated 
during 1938 and is 90 percent complete. 
(b) St. Francis River and Tributaries. Project 
was initiated during 1937 and is 81 percent complete. 
WHITE RIVER BACKWATER 
LEVEES 
Helena Harbor, Phillips County, AR 
Operations and results during fiscal year. 
Item 1, Harbor Construction, awarded Aug. 31, 
1989, completed Jul. 10, 1991. Item 1-2, Harbor 
Construction, awarded Dec. 31, 1990, completed 
Sep. 23, 1991. Item 2-1, Harbor Construction, 
awarded Apr. 23, 1991, completed Sep. 14, 1991. 
Item 3-1 Harbor construction, awarded May 26, 
1992 and is 90 percent complete. Item 3-2, Harbor 
Construction aawarded Sep. 10, 1992, construction 
not yet underway. 
Condition as of Sep. 30. Project construction was 
initiated during 1989 and is 38 percent complete. 
LOWER WHITE RIVER 
Operations and results during fiscal year. 
(a) Augusta to Clarendon Levee. There were no 
contracts awarded or completed during the fiscal year. 
42-10

MISSISSIPPI RIVER COMMISSION 
(b) Clarendon Levee. There were no contracts 
awarded or completed. 
Condition as of Sep. 30. 
(a) Augusta to Clarendon Levee. Project was 
initiated during 1946 and is 39 percent complete. 
(b) Clarendon Levee. Project was initiated during 
1972 and is 36 percent complete. 
CACHE BASIN, AR 
Operations and results during fiscal year. 
No contracts awarded or completed during the fiscal 
year. 
Condition as of Sep. 30. Project was initiated 
during 1971 and is 4 percent complete. 
REELFOOT LAKE-LAKE NO. 9, 
TN AND KY 
Operations and results during fiscal year. No 
contracts awarded or completed during this fiscal 
year. 
Condition as of Sep. 30. Project was initiated 
during 1974 and is 89 percent complete. 
WEST TENNESSEE TRIBUTARIES, 
TN 
Operations and results during fiscal year. 
(a) Obion River and principal tributaries, TN. 
Obion Rivers channel improvement is 66 percent 
complete. 
(b) Forked Deer River and principal tributaries, 
TN. Forked Deer River channel improvement is 
13 percent complete. 
(c) Halls, TN, I-2A County Bridge. Mile 11.85 
awarded Mar. 22, 1991, 10 percent complete. 
(d) Sharon, TN, I-1A Gas Pipeline. Mile 7.4 
awarded Aug. 18, 1992, 10 percent complete. 
Condition as of Sep. 30. West Tennessee Tributaries 
Project is 41 percent complete. 
WEST KENTUCKY TRIBUTARIES, 
KY 
Operations and results during fiscal year. No 
contract awarded or completed during fiscal year. 
Condition as of Sep. 30. Project was initiated 
during 1978 and is 4 percent complete. 
NONCONNAH CREEK, MS AND TN 
Operations and results during fiscal year. 
Item 1-A, bridge protection, awarded Oct. 26, 1990, 61 
percent complete. 
Condition as of Sep. 30. Project construction was 
initiated during 1990 and is 8 percent complete. 
MISSISSIPPI RIVER LEVEES 
Operations and results during fiscal year. 
Modifications to 10th and 28th Streets Pumping 
Stations Pumps, Cairo, IL, awarded Jul 28, 1989, 50 
percent complete. Item R-735 West Memphis, AR, 
Landside Berm and Drainage Improvements, West 
Memphis, AR, awarded May 28, 1991, 90 percent 
complete. In addition minor maintenance on levees is 
performed as required by the local interests and major 
maintenance is performed as required for slide repairs, 
road rehabilitation, and other similar work by 
the U.S. Army Corps of Engineers Levee Roadway 
Resurfacing, St. John Setback Levee, MO, awarded 
Jul. 30, 1991, completed Nov. 26, 1991. 
MEMPHIS HARBOR 
Operations and results during fiscal year. 
Item No. 6-717.5, Ensley, TN Berm, awarded Jun. 27, 
1990, 97 percent complete. 
CONSTRUCTION GENERAL 
Ensley Main Access Bridge Repairs awarded Jun. 28, 
1991, completed Nov. 25, 1991. Replacement Bldg. at 
Richardson landing awarded May 31, 1991, completed 
Dec. 3, 1991. Nonconnah Erosion Protection awarded, 
Oct. 26, 1990, 95 percent complete. Fletcher Creek-Nonconnah 
Bank Protection awarded Jul. 25, 1991, completed 
Oct. 2, 1991. Nonconnah Erosion Protection I-B, 
awarded, Jun. 25, 1992, 80 percent completed. 
42-11

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-A MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
0-9571 
10-81 
11-25 
38 
45 
118 
81 
44-91 
81-96 
91-104 
96-279 
104-234 
127-129 
129 
129-234 
235 
279-287 
287-303 
Head of Passes, LA-Cairo, IL 
The Jump-New Orleans, LA 
Baptiste Collette-Bayou 
Ostrica, LA 
Homeplace, LA 
Bohemia, LA 
Davis Pond, LA (formerly 
Myrtle Grove, LA) 
Caernarvon, LA 
Bohemia, LA-New Orleans, 
LA 
New Orleans, LA 
New Orleans, LA 
New Orleans-Morganza, LA 
New Orleans-Baton Rouge, 
LA 
Bonnet Carre' Floodway, LA 
Mississippi-Louisiana 
Estuarine Areas, LA/MS 
(Bonnet Carre') 
Bonnet Carre'-Baton Rouge, 
LA 
Baton Rouge Harbor 
Morganza Floodway, LA 
Morganza-Old River, LA 
Dredging, revetment, and contract 
work 
Main line levee, right bank 
Local levees, left bank 
Salinity control structure, right 
bank 
Salinity control structure, left 
bank 
Salinity control structure, right 
bank 
Salinity control structure, left 
bank 
Main line levee and floodwall, 
left bank 
Main line levee, right bank 
Main line levee and floodwall, 
left bank 
Main line levee, right bank 
Main line levee, left bank 
Regulating spillway, left bank 
Salinity control structure, 
left bank 
Main line levee, left bank 
Devils Swamp barge channel 
Regulating spillway, right bank 
Main line levee, right bank 
42-12 
Authorized by Public 
Law 89-298 
(HD 308/74/1). 
Included in MS 
Delta Region, LA 
feature. 
Authorized by Public 
Law 89-298 
(HD 308/74/1). 
Included in MS 
Delta Region, LA 
feature. 
Authorized by Public 
Law 89-298 
(HD 308/74/1). 
Included in MS 
Delta Region, LA 
feature. Postauthorization 
change 
report, approved 
June 1987. 
Authorized by Public 
Law 89-298 
(HD 308/74/1). 
Included in MS 
Delta Region, LA 
feature. 
Authorized by Public 
Law 81-516. 
Authorized by Public 
Law 81-516. 
Authorized by Public 
Public Law 100-676 
Modified by Public 
Law 87-874. 
-- 
Extends up south 
bank of Old River 
to Barbre Landing.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-A 
(Continued) 
MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
303-314 Old River, LA control 
314-572 Old River-Cypress Creek, AR 
437 Vicksburg Harbor, MS 
437-721 Vicksburg-Lake View, MS 
490 Wilson Point, LA 
537 Greenville Harbor, MS 
646 Long Lake, Helena, AR 
605-666 Henrico-Helena, AR 
672-993 St. Francis River-Commerce, 
MO3 
722-725 Industrial levee (Ensley 
Bottoms) 
721-734 Memphis Harbor, TN 
803-873 Tiptonville-Obion River 
857 Near Mud Lake, TN 
890 St. Johns Bayou, MO 
890 New Madrid Floodway, MO 
890-954 New Madrid-Birds Point, 
MO 
902-922 Slough Bend, Hickman, KY 
922 Hickman, KY 
946 Peafield, MO 
9571 Cairo, Cairo drainage 
district 
Levee closure and enlargement, 
low and high water spillway 
structures, navigation lock, and 
approach channels, right bank 
Main line levee, right bank 
Harbor extension and industrial 
fill 
Main line levee, left bank 
Pumping Plant and drainage 
structure, right bank 
Harbor improvements and port 
area 
Culvert and floodgate, right 
bank 
Main line levee and floodwall, 
right bank 
Main line levee, right bank 
Levee and pumping station 
Closure of Tennessee Chute, 
industrial fill, levee, harbor 
channels, etc. 
Main line levee, left bank, levee 
extension, and diversion Obion 
River 
Pumping station and adjacent 
channel improvements 
Drainage floodgate and levee 
closure 
Drainage floodgate and levee 
closure 
Floodway, right bank 
Main line levee, left bank 
Floodwall, left bank 
Drainage floodgate 
Floodwalls and levees 
Authorized by Public 
Law 83-780. 
Joins Arkansas 
River, south bank 
levee. 
Authorized by Public 
Law 70-391. Modified 
by Public 
Laws 79-526 and 
83-780. 
-- 
Unpublished 
Vicksburg District's 
MRC report approved 
Apr. 14, 
1966.2 
Authorized by Public 
Law 85-500. 
Authorized by Public 
Law 79-526.2 
Authorized by Public 
Law 79-526. 
Modified by Acts of 
Jul. 24, 1946 and 
Dec. 23, 1971. 
Authorized Dec. 15 
and 17, 1970 under 
Sec. 201 of Oct. 27, 
1965 FC Act. 
Modified by Jul. 24, 
1946 Act. 
Modified by Sep. 3, 
1954 Act.
-- 
-- 
Authorized by 
Sep. 3, 1954 Act. 
42-13

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-A 
(Continued) 
MISSISSIPPI RIVER IMPROVEMENTS 
Mileage 
Above Head 
of Passes Locality Improvement Remarks 
9571 Cairo, Cairo drainage Floodwalls, levees, and pumping -- 
district, Mounds, Mound plant 
City, and vicinity 
Thebes-Rock Island, IL Levees, both banks Intermittent (Sec. 6). 
Cape Girardeau, MO, to Rock Levees Intermittent (Sec. 6). 
Island, IL 
1. Cairo, IL, is on Ohio River about 3 miles above its mouth (Mississippi River mile 954 AHP). 
2. Also see Table 42-D, "Authorizing Legislation." 
3. Commerce, MO, is on Upper Mississippi River, 39 miles above mouth of Ohio River. 
42-14

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
0-54 
27-54 
54-117 
20-27 
25-117 
27 
0-27 
31-57 
80 
53-117 
117 
117-129 
117-129 
105 
105-120 
115 
116 
5 
5-105 
29 
Floodway 
Floodway 
Floodway 
ATCHAFALAYA BASIN, LA1 
Atchafalaya Basin, Morganza 
and West Atchafalaya 
Floodways 
West Atchafalaya Floodway 
between Red River and 
Alabama Bayou 
Morganza Floodway between 
Mississippi River and 
Alabama Bayou 
Atchafalaya Basin Floodway 
between Alabama Bayou and 
Morgan City 
East protection levee 
(Morganza and Atchafalaya 
Floodways) 
Lacour-Red Cross 
Morganza-Morgan City 
Bayou Latenache 
Upper Pointe Coupee Loop 
area 
Bayou Fordoche-Ramah 
Bayou Sorrel1 
Bayou Sorrel Lock-Morgan 
City 
Morgan City 
Below Morgan City 
Below Morgan City 
Atchafalaya Basin Floodway 
lower protection levee 
Calumet 
Below Morgan City 
Berwick1 
Patterson 
West protection levee 
(Atchafalaya Basin and West 
Atchafalaya Floodways) 
Simmesport-Hamburg 
Mansura to Wax Lake Outlet 
Coulee des Grues 
West Atchafalaya Floodway 
Including lower Morganza Floodway 
guide levee. 
Through upper Morganza guide 
levee and enlargement of outlet 
channel. 
Enlargement of Bayou Latenache. 
Approved Jun. 4, 1970. See 
Table 42-D. 
Levee landside borrow pit. 
Alternate route, Gulf Intracoastal 
Waterway, Port Allen to Morgan 
City. 
Gulf Intracoastal Waterway utilizes 
levee west side borrow pit 
channel. 
Gulf Intracoastal Waterway. 
Bypass route for Gulf Intracoastal 
Waterway. 
East of lower river. 
Bayou Teche-Wax Lake Outlet. 
Inclosed area between Wax Lake 
Lake Outlet and Berwick. 
Lower Atchafalaya River. 
Adjustment to provide fresh water. 
West Atchafalaya Floodway. 
42-15 
Levee, upper Morganza guide 
Levee and Morgan City floodwall 
Drainage structure, Pointe 
Coupee, and channel 
enlargement 
Additional drainage facilities 
Drainage channel 
Lock 
Alternate navigation channel. 
Gulf Intracoastal Waterway 
Lock in Bayou Boeufl 
Channel relocation 
Levee, floodwall 
Floodgate, east 
Levees, floodwall, drainage 
structures, and pumping plants 
Lock 
Water system 
Levee fuse plug 
Protection levee 
Levee enlargement and floodgate 
extension 
Railway

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
29 
40 
40 
40 
41 
41 
41 
94 
94 
105 
105 
0-54 
5-6 
5-66 
28-30 
40-41 
54-117 
94-106 
Mileage 
Above 
Mouth 
0-8 
50-133 
96 
133 
Morganza Floodway 
Bayou Darbonne 
West Atchafalaya Floodway 
Morganza Floodway 
Bayou Courtableau 
West Atchafalaya Floodway 
Morganza Floodway 
Charenton 
Jaws-Lake Fausse Pointe 
Calumet 
Wax Lake Outlet 
Atchafalaya River 
Barbre Landing-Alabama 
Bayou 
Simmesport 
Simmesport-Bayou Garofier 
Melville 
Krotz Springs 
Below Alabama Bayou 
Mississippi River-Morgan City 
TECHE-VERMILION 
BASINS, LA 
Atchafalaya River to Teche- 
Vermilion Basins 
Courtableau Basin, LA, and 
outlets 
Charenton Canal 
West Atchafalaya protection 
levee borrow pit channel 
Bayou Courtableau spillway 
Bayou des Glaises 
BAYOU COCODRIE AND 
TRIBUTARIES 
Bayou Courtableau 
Bayou Cocodrie 
Through West Atchafalaya 
protection levee. 
-- 
-- 
Borrow pit channel to Grand Lake 
through West Atchafalaya 
protection levee. 
Restoration of drainage west of 
West Atchafalaya Basin protection 
levee. 
Bayou Teche and Wax Lake Outlet. 
To lower flood heights. 
Railway 
Gated drainage structures 
Highway 
Highway 
Gated drainage control 
structures and channels 
Railway 
Railway 
Floodgate and approach 
channels 
Outlet, Charenton drainage 
canal and protection levee 
Floodgate, west 
Drainage canal-railway and 
highway bridges 
East bank, levee 
Levee, ring, and drainage 
structure 
West bank, levee 
Levee, ring 
Levee, ring 
Channel enlargement 
12- by 125-foot navigation 
channel 
Pumping station above Krotz 
Springs, conveyance channels, 
and appurtenant works 
Drainage channel 
Drainage channel 
Drainage control structure 
Diversion channel 
Enlargement and additional 
culverts 
Enlargement and realinement 
Washington to west protection 
levee. 
42-16 
Increase channel capacities to 
decrease flood heights. 
Through Grand and Six Mile Lakes. 
Freshwater distribution from 
Atchafalaya River to Teche- 
Vermilion Basins. 
Outlet to gulf 
Intercepting drainage channel. 
0-17

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
17-40 
40-51 
51-60 
17-42 
87-107 
40 
60 
87 
New channel 
New channel 
New channel 
Enlargement, clearing, and 
snagging 
Enlargement, realinement, 
clearing, and snagging 
Fixed elevation weir 
Gated drainage structure 
Gated drainage structure 
Railway, highway, and local road 
bridges, and pipeline crossing 
Flood protection 
Bayous Cocodrie-Boeuf 
diversion 
Bayou Boeuf 
Bayous Boeuf-Rapides 
diversion 
Upper Cocodrie 
Bayou Boeuf 
Bayou Lamourie to Kincaid 
Structures 
Lecompte Control Structure 
Bayou Rapides Control 
Structure 
Bayou Lamourie Control 
Structure 
Various 
LAKE PONTCHARTRAIN, LA 
Lake Pontchartrain, Jefferson 
Parish, LA 
AMITE RIVER, LA 
Amite River, LA 
LOWER RED RIVER, SOUTH 
BANK, RED RIVER 
LEVEES, LA 
Moncla-Hotwells 
Bayou Rapides Pumping 
plant and gravity 
structure 
Red River-Moncla to Lake 
Long 
EASTERN RAPIDES AND 
SOUTH-CENTRAL 
AVOYELLES PARISHES, LA 
Eastern Rapides and southcentral 
Avoyelles Parishes, 
LA 
TENSAS BASIN, AR AND LA 
Red River backwater area 
Tensas-Cocodrie area 
Larto Lake-Jonesville 
Flood protection and drainage 
improvement 
Levees, drainage channels, 
structures, and pumping plant 
Levees, drainage channels, and 
structures 
(2,3) 
Authorized by Public Law 81-516. 
Eliminated by Public Law 89-298. 
-- 
Senate Doc. (Public Law 84-99) 
Intermittent (Sec. 6). 
Authorized by Public Law 91-611. 
(4) 
(4) 
42-17 
Bank protection 
Levee, south bank 
Levee, south bank 
Levees 
82-145 
3-56

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
Sicily Island area 
3-56 
5 
56 
0-32 
0-56 
151-235 
210-286 
286-296 
0-75 
0-8 
0-7 
0-33 
0-10 
0-9 
0-14 
0-170 
0-34 
0-35 
Lake Chicot 
0-6 
0-165 
0-22 
0-0.2 
Below Red River area 
Black River, LA 
Six Mile Bayou area 
Jonesville, LA 
Ouachita River 
Boeuf and Tensas Rivers and 
Bayou Macon, AR and LA 
Boeuf River, AR and LA 
Below Bayou La Fourche 
Bayou La Fourche 
Boeuf River, AR and LA 
above Bayou La Fourche 
Canal 19 
Canal 19 extension 
Big and Colewa Creeks 
Tributaries of Boeuf River-- 
Canal 19 
Fleschmans Bayou 
Caney Bayou 
Big Bayou 
Canal 18 
Kirsch Lake Canal 
Black Pond Slough 
Bayou Macon, AR and LA 
Bayou Macon 
Canal 43 
Canal 81 
Pumping plant and drainage 
structure 
Tributary of Bayou Macon 
Rush Bayou 
Tensas River, AR and LA 
Tensas River 
Tributary of Tensas River 
Mill and Vidal Bayous 
Grant's Canal, LA 
Grant's Canal at Lake 
Providence 
LOWER ARKANSAS RIVER, 
AR 
Yancopin-Pine Bluff 
Levees, drainage channels, 
structures, and pumping plants 
Levees, drainage channels, 
structures, and pumping plants 
Drainage structure and 
appurtenant channel works 
Levees, floodwall, pumping 
plant, and interior drainage 
Levees, drainage channels, and 
structures 
Clearing 
Channel improvement and 
realinement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
To divert flows from Lake Chicot 
Clearing 
Channel improvement 
Channel improvement 
Filling canal 
Levee, south bank 
42-18 
(4) 
(4) 
Unpublished VXD-MRC Letter 
Report dated May 31, 1977, 
MR&T authority. 2 
Portion of levee built under Sec. 6. 
Incorporated in MR&T by Public 
Law 81-516.2 
Monroe to Sandy Bayou and 
Bawcomville (Sec. 6). 
(5) 
(5) 
Authorized by Public Laws 78-534 
and 79-526.2,3 
(5) 
(6) 
Authorized by Public Law 78-534.3 
(6) 
(6) 
(5) 
(6) 
(6) 
(6) 
See Table 42-E 
(5) 
(5) 
Authorized by Public Law 90-483. 
(6) 
Authorized by Public Law 78-534. 3 
Authorized by Public Law 89-298. 
Authorized by Public Law 81-516. 
23-98

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
35-98 
48-102 
0-75 
0-381 
75-366 
75-345 
45-109 
75 
127 
185 
381 
0-64 
64 
0-24 
0-26 
26 
0-13 
13 
0-88 
137-260 
75-381 
0-8.3 
0-23 
0-42 
Revetment 
Levee, north bank 
Water supply and drainage 
improvements 
Levees and pumping plants 
Channel improvement 
Levees, right bank 
Levees, left bank 
(5) 
Authorized by Public Law 81-516. 
Including Tallahatchie and 
Coldwater Rivers. 
Intermittent. 
Intermittent. 
Fletcher Bend, AR, to 
Pine Bluff 
North Little Rock to Gillett 
(below Plum Bayou) 
GRAND PRAIRIE-BAYOU 
METO, AR 
Grand Prairie Region and 
Bayou Meto Basin, AR 
YAZOO BASIN, MS 
Yazoo Backwater area 
Yazoo River System below 
Arkabutla Lake 
Yazoo River between Yazoo 
City and Prichard 
Yazoo River between Yazoo 
City and Askew 
Will M. Whittington Auxiliary 
Channel 
Yazoo City protection 
Rocky Bayou area 
Belzoni protection 
Greenwood protection 
Arkabutla Lake 
Yalobusha River below 
Grenada Lake 
Grenada Lake 
Tallahatchie River-Little 
Tallahatchie River 
Little Tallahatchie River 
below Sardis Lake 
Sardis Lake 
Yocono River below Enid Lake 
Enid Lake 
Cassidy Bayou below Old 
Coldwater River 
Upper Yazoo Projects 
Area between main stem and 
hills including Bobo Bayou 
McKinney Bayou 
Alligator-Catfish Bayous 
Bear Creek 
Whiteoak Bayou 
Levee, drainage structure, and 
pumping plant 
Channel clearing and 
enlargement 
Levee and floodwall 
Levees, channel improvement, 
drainage structures, and 
pumping plants 
Flood detention and conservation 
Channel improvement 
Flood detention and conservation 
Levees, Panola-Quitman Floodway 
Improvement of 7.8 miles was 
approved Apr. 29, 1970. 
See Table 42-C. 
See Table 42-C. 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Flood detention and conservation 
Channel improvement 
Floodway channel 
Levees and channel improvement 
Channel improvement and 
enlargement of pumping plant. 
Channel improvement 
Channel improvement 
Channel improvement 
See Table 42-C. 
See Table 42-C. 
Including Moores Bayou, Cutoff 
Bayou, Whiting Lake and outlet. 
Authorized by Public Law 79-526. 
Authorized by Public Law 79-526. 
Authorized by Public Law 89-298. 
As modified in GDM in 1967. 
Authorized by Public Law 89-298. 
Authorized by Public Law 89-298. 
42-19 
Floodway channel

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
275-290 
0-204 
0-8 
0-28 
0-81 
0-43 
0-4 
0-27 
153-160 
0-68 
13-55 
0-68 
99 
108-192 
122 
143 
0-196 
0-90 
260 
0-225 
225 
0-105 
86 
0-36 
0-29 
Tallahatchie River, MS 
Big Sunflower River, etc. 
Big Sunflower River 
Hull Brake-Mill Creek Canal 
Hushpuckena River 
Quiver River 
Gin and Muddy Bayous, MS 
Bogue Phalia 
Ditchlow Bayou 
Little Sunflower River 
Deer Creek 
Steele Bayou 
Muddy Bayou 
LOWER WHITE RIVER AND 
BASIN, AR 
Laconia Circle-Old Town Lake 
Big Creek and tributaries 
Clarendon levee 
Augusta to Clarendon 
De Valls Bluff 
Des Arc, AR 
CACHE BASIN, AR 
Cache River, AR 
Bayou DeView, AR 
ST. FRANCIS RIVER AND 
BASIN, AR AND MO 
Inter-River Drainage District 
in Missouri 
Mouth of St. Francis River- 
Wappapello Dam 
Wappapello Lake 
Little River Basin 
Marked Tree, AR 
Tyronza River 
Big Slough Ditch 
Two road crossings of Panola- 
Quitman Floodway, MS, and for 
protection of Sheley Bridge 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Water-control structure 
Levee, backwater including 
outlet 
Pumping plant 
Channel improvement and 
structures 
Levee and outlet structures 
Levees, outlet structures 
Levee, outlet structure, and 
pumping station 
Levee, outlet structure, and 
pumping station 
Channel improvement and 
structures 
Channel improvement and 
structures 
Channel improvement and two 
outlet structures 
Floodway, levees, drainage 
channels, and structures 
Flood detention and conservation 
Floodway, levees, drainage 
channels, and structures 
Marked Tree Siphon 
Channel improvement 
Channel improvement 
42-20 
Authorized by Public Law 90-147. 
Authorized by Public Law 78-534.3 
-- 
Authorized by Public Law 87-874. 
Authorized by Public Law 78-534. 3 
Authorized by Public Law 78-534. 3 
Authorized by Public Law 78-534.3 
Authorized by Public Law 78-534. 3 
Authorized by Public Law 78-534. 3 
Modified in December 1970. See 
Table 42-D. 
Approved Mar. 3, 1970. See 
Table 42-D. 
Mile 605-645 Mississippi River. 
(6) 
Authorized by Public Law 89-298. 
Authorized by Public Law 89-298. 
(5) 
(5) 
Authorized by Public Law 81-516. 
Authorized by Public Law 81-516. 
Authorized by Public Law 81-516. 
Authorized Dec. 16, 1975. See 
Table 42-D. 
See Table 42-C.

MISSISSIPPI RIVER COMMISSION 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
0-17 
0-12 
0-108 
0-25 
0-20 
0-15 
0-47 
Mayo Ditch 
Cross County Ditch 
Belle Fountain Ditch 
Drainage District No. 17 
L'ANGUILLE RIVER, AR 
L'Anguille River and 
tributaries, Brushy and First 
Creeks 
WEST TENNESSEE 
TRIBUTARIES 
Wolf River and tributaries, TN 
Obion River and tributaries, 
North, South, Middle, and 
Rutherford Forks 
Forked Deer River and 
tributaries, North, Middle, 
and South Forks 
Mud Lake Pumping Station, 
TN 
Harris Fork Creek, TN 
and KY 
Porter Gap, TN 
REELFOOT LAKE-LAKE 
NO. 9, TN AND KY 
Running Reelfoot Bayou, TN 
Bayou du Chien and Lake 
No. 9, KY and TN 
WEST KENTUCKY 
TRIBUTARIES, KY 
Obion Creek, KY 
LITTLE RIVER DIVERSION 
CHANNEL, MO 
Delta to Ancell, MO 
MISSOURI RIVER, MO 
Mouth to St. Charles, MO 
ILLINOIS RIVER, IL 
Mouth to Havana, IL 
Levees 
Levees 
Levees 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement and 
pumping station 
Channel improvement 
Channel improvement 
Channel improvement 
Channel improvement 
Pumping plant 
Flood control improvements 
Construction to main-stem 
standards, levee and 
appurtenant structures for 
flood control 
Channel improvement 
Channel improvements and 
pumping station 
Channel improvement 
Mile 49 above Cairo. 
Intermittent (Sec. 6). 
Intermittent (Sec. 6). 
42-21 
Authorized by Public Law 90-483. 
Authorized by Public Law 90-483. 
Authorized by Public Law 80-858. 
(6) 
Authorized by 1948 Flood Control 
Act. 
Authorized by 1948 Flood Control 
Act. 
Authorized by Resolutions Dec. 15 
and 17, 1970.2 
Authorized by Water Resources Act 
of Oct. 22, 1976.2 Section 102, 
1976.2 
Section 183, 1976.2 
Authorized by Public Law 83-780. 
Authorized in December 1970. See 
Table 42-D. 
Authorized by Public Law 89-298. 
0-28 
0-120

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-B 
(Continued) 
MISSISSIPPI RIVER TRIBUTARY AND 
OUTLET IMPROVEMENTS 
Mileage 
Below Head of 
Atchafalaya 
River Locality Improvement Remarks 
OHIO RIVER, IL AND KY 
Cairo to Mound City and Floodwall, levee, revetment, and 
Mounds, IL pumping plant 
1. General data concerning Bayou Boeuf, Bayou Sorrel, and Berwick locks where Atchafalaya Basin protection levees cross 
Gulf Intracoastal Waterway, alternate route to Plaquemine, LA, and lower Atchafalaya River (extension of Bayou Tech 
Waterway), respectively, are in report of New Orleans District. 
2. Also see Table 42-D, "Authorizing Legislation." 
3. Public Law 81-516 modified requirements of local cooperation. 
4. Authorized by Public Law 77-228. Modified by Public Law 89-298. 
5. Authorized or incorporated in MR&T by Public Law 79-526.3 See Table 42-D. 
6. Authorized by Public Law 85-500. 
42-22

TABLE 42-C 
MISSISSIPPI RIVER COMMISSION 
MISSISSIPPI RIVER TRIBUTARY 
DAMS AND LAKES 
Grenada Enid Sardis Arkabutla Wappapello 
Namel Lake Lake Lake Lake Lake 
River 
Nearest town to damsite 
Drainage area, square miles 
Conservation pool: 
Area, thousand acres 
Volume, thousand acre-feet 
Elevation, feet, NGVD 
Flood control pool: 
Area, thousand acres 
Volume, thousand acre-feet 
Runoff, inches 
Outlet gates: 
Number 
Size, feet 
Capacity, thousand cubic 
feet per second 
Spillway: 
Type, uncontrolled 
Length, feet 
Elevation, crest, feet, NGVD 
Discharge capacity, thousand 
cubic feet per second 
Surcharge pool: 
Area, thousand acres 
Volume, thousand acre-feet 
Runoff, inches 
Elevation, feet, NGVD 
Dam: 
Type, earthfill 
Length, thousand feet 
Elevation, crest, feet, NGVD 
Yalobusha 
Grenada 
1,320 
10 
86 
193.0 
65 
1.252 
17.8 
3
7.5 by 14 
10.7 
Chute 
200 
231.0 
52 
106 
1,385 
19.7 
247.5 
Rolled 
13.9 
256.0 
Yocona 
Enid 
560 
6
58 
230.0 
28 
602 
20.2 
Little Tallahatchie 
Sardis 
1,545 
11 
108 
236.0 
58.5 
1,462 
17.7 
2 4 
8 by 16 6 by 12 
9.4 
Chute 
200 
268.0 
50 
41 
554 
18.5 
284.0 
Rolled 
8.4 
293.0 
10.0 
Chute 
400 
281.4 
132 
90 
1,447 
17.6 
301.0 
Hydraulic 
15.3 
311.4 
42-23 
Coldwater 
Arkabutla 
1,000 
5
31 
209.3 
33 
494 
9.3 
3
8.5 by 19 
10.0 
Chute 
300 
238.3 
89 
63 
858 
16.1 
256.3 
Rolled 
11.5 
264.3 
St. Francis 
Wappapello 
1,310 
4
31 
354.7 
23 
582 
8.4 
3
10 by 20 
18.0 
Gravity 
740 
394.7 
229 
32 
521 
7.5 
413.7 
Rolled 
2.7 
419.7 
1. Grenada, Enid, Sardis, and Arkabutla Lakes are in Yazoo River Basin, MS; Wappapello Lake is in St. Francis River Basin, 
MO.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-D AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
May 15, 1928 
Jun. 19, 1930 
Feb. 15, 1933 
Apr. 23, 1934 
Aug. 30, 1935 
Jun. 15, 1936 
Flood protection in alluvial valley of Mississippi River, revetment 
and contraction works and dredging to provide least channel 
depth of 9 feet and width of 300 feet below Cairo. 
Provided for allotment of the balance of emergency rescue funds 
to reimburse levee districts and others for expenditures in floodcontrol 
works during the 1927 and subsequent floods. 
Provided for ownership of lands in Bonnet Carre' Spillway and 
Floodway with proviso for granting rights-of-way, easements, 
and permits, in said lands. 
Authorized payment for purchase of, or to reimburse states and 
local levee districts for the cost of, levee rights-of-way for floodcontrol 
work in the Mississippi Valley, and for other purposes. 
Improvement of Wolf and Nonconnah Rivers, TN (Nonconnah 
Creek is correct title). 
Improvement of Wolf River (Memphis Harbor), TN. 
Modification of the 1928 Act to provide for: 
Construction of a backwater levee at mouth of White River, AR. 
Construction of Eudora floodway in lieu of Boeuf floodway; flood 
control, Yazoo River: construction of Morganza floodway; and an 
outlet to the Gulf of Mexico west of Berwick, LA, including a 
6-year program for the improvement and regularization of the 
Mississippi River between Arkansas and Red Rivers, and 
Atchafalaya River; and construction of roads on levees and 
drainage adjustments incident to floodway levees. 
Provided for construction of floodwalls, levees, and revetments 
along Wolf River and Nonconnah Creek for protection of 
Memphis, TN. 
Modify the Yazoo River project to substitute a combined 
reservoir floodway and levee plan. 
Construction of Mounds to Mound City levee and control works 
along Cache River, IL. 
Modification of previous act pertaining to floodways and outlets 
and lands therein; including program for the improvement and 
regularization of the Mississippi River, between Cairo and 
Arkansas River, extension of levee road system; strengthening 
of levees. 
Enlarge main line levees to offset abandonment of floodways 
between Arkansas and Red Rivers, flood-control works in 
backwater areas of Yazoo and Red Rivers, and in Bayous 
Rapides, Beouf, and Cocodrie, LA. 
Navigation channel 12 feet deep and 300 feet wide between 
Baton Rouge and Cairo; flood protection of Yazoo River 
Backwater Area in vicinity of Satartia, MS. 
Unpublished report on 
record in OCE. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 
1st sess. 
H. Comm. on Flood Control, 
Doc. 1, 75th Cong., 
1st sess. 
H. Doc. 359, 77th Cong., 
1st sess. 
H. Doc. 509, 78th Cong., 
2d sess. 
42-24 
H. Doc. 90, 70th Cong., 
1st sess. 
Public Law 395, 71st Cong., 
2d sess. 
Public Law 351, 72d Cong. 
Public Law 171, 73d Cong. 
R&H Comm. Doc. 26, 
72d Cong., 1st sess. 
R&H Comm. Doc. 45, 
74th Cong., 1st sess. 
Unpublished report dated 
Apr. 2, 1925. 
H. Comm. on Flood Control, 
Doc. 1, 74th Cong., 
1st sess. 
Aug. 28, 1937 
Jun. 28, 1938 
Aug. 18, 1941 
Dec. 22, 1944

MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Jul. 24, 1946 
Jun. 30, 1948 
May 17, 1950 
Continue prosecution of channel improvement and stabilization 
program, $200 million. 
Flood control on the Big Sunflower, Little Sunflower, 
Hushpuckena, and Quiver Rivers and their tributaries, and on 
Hull Brake-Mill Creek Canal, Bogue Phalia, Ditchlow Bayou, 
Deer Creek, and Steele Bayou, MS. 1 
Improve Boeuf and Tensas Rivers and Bayou Macon, AR.1 
Improve Bayou Lafourche, LA. 
Improve Yazoo River tributaries. 
North bank, Arkansas River levees(below Plum Bayou).1 
Levees on White River (Augusta to Clarendon).1 
Bayou des Glaises diversion channel, LA. 1 
Modify local cooperation requirements in St. Francis and Yazoo 
Basins. 
Tiptonville-Obion levee and drainage improvements.1 
Improvement of St. Johns Bayou, MO. 
Big Sunflower River, etc.1 
Tennessee Chute (Memphis Harbor), TN. 
Continue prosecution of project for flood control and channel 
improvement, $100 million. 
Improve Mississippi River below Cape Girardeau, MO, with 
respect to West Tennessee tributaries. 
Improve L'Anguille River, AR. 
Baton Rouge Harbor (Devils Swamp), LA.1 
Flood protection at Des Arc, AR. 
Improve St. Francis River and Basin, AR and MO. 
Improve Cache River and Bayou DeView, AR and MO. 
Improve Grand Prairie Region and Bayou Mete Basin, AR. 
Flood protection, Lake Pontchartrain, Jefferson Parish, LA. 1 
Filling Grant's Canal, Lake Providence, LA. 
42-25 
TABLE 42-D 
(Continued) 
Public Law 534, 
78th Cong., 2d sess. 
H. Doc. 516, 78th Cong., 
2d sess. 
S. Doc. 151, 78th Cong., 
2d sess. 
S. Doc. 191, 79th Cong., 
2d sess. 
H. Doc. 516, 78th Cong., 
2d sess. 
H. Doc. 308, 74th Cong., 
1st sess. 
H. Doc. 98, 76th Cong., 
1st sess. 
H. Doc. 602, 79th Cong., 
2d sess. 
Public Law 526, 
79th Cong., 2d sess. 
H. Doc. 757, 79th Cong., 
2d sess. 
H. Doc. 138, 80th Cong., 
1st sess. 
H. Doc. 516,78th Cong., 
2d sess. 
S. Doc. 51, 80th Cong., 
1st sess. 
Public Law 526, 
79th Cong., 2d sess. 
H. Doc. 627, 
80th Cong., 2d sess. 
H. Doc. 651, 
80th Cong., 2d seas. 
H. Doc. 321, 80th Cong., 
1st sess. 
H. Doc. 485, 81st Cong., 
2d sess. 
H. Doc., 132, 81st Cong., 
1st sess. 
S. Doc. 88, 81st Cong., 
1st sess. 
H. Doc. 255, 81st Cong., 
1st sess. 
S. Doc. 139, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Additional protection to Red River Backwater Area. 
Extend Federal jurisdiction to cover levees in Orleans Parish, LA. 
Bank protection, Amite River, LA. 
Continue prosecution of project for flood control and channel 
improvement, $200 million. 
Jonesville, LA, levee, retaining wall, and drainage structure.1 
Modify requirements for local cooperation in White River 
Backwater Area, AR. 
Navigation improvement of Atchafalaya from Mississippi River 
to Morgan City, LA. 
Modify project for Vicksburg-Yazoo Area (Harbor), MS. 
Improve New Madrid Floodway, MO, including Peafield drainage 
floodgate. 
Control of Old and Atchafalaya Rivers and a lock for navigation. 
Improve Reelfoot Lake area, KY and TN. 
Improve Greenville Harbor, MS. 
Extensions to project for Boeuf and Tensas Rivers and Bayou 
Macon in Arkansas. 
White River backwater area pumping plant. 
Wolf River and tributaries for flood protection in Tennessee. 
Continue prosecution of project for channel improvement-- 
$50 million. 
Modification--Baton Rouge Harbor (Devils Swamp), LA. 
Construct improvements in Gin and Muddy Bayous, Yazoo River 
Basin, MS. 
Replace 2 bridges with adequate floodway over Boeuf River and 
Big Bayou in Boeuf Basin, AR. 
Continue prosecution of project for flood control and channel 
improvement, $53 million. 
Modify and expand levees and channel improvement features of 
main stem project. 
Modify flood control improvements in following tributary areas 
and basins: Cairo-Mounds-Mounds City, St. Francis, Lower 
White, Boeuf-Tensas-Macon, Red River backwater, Yazoo 
headwater, Grand Prairie, and Bayou Meto. 
Acquire any modified easements required in New Madrid 
Floodway as provided by Sec. 4 of May 15, 1928 act. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
Public Law 516, 81st Cong., 
2d sess. 
S. Doc. 117, 81st Cong., 
1st sess. 
Public Law 237, 82d Cong., 
1st sess. 
S. Doc. 53, 82d Cong., 
1st sess. 
H. Doc. 85, 83d Cong., 
1st sess. 
H. Doc. 183, 83d Cong., 
1st sess. 
H. Doc. 478, 83d Cong., 
2d sess. 
S. Doc. 160, 83d Cong., 
2d sess. 
S. Doc. 15, 86th Cong., 
1st sess. 
H. Doc. 108, 85th Cong., 
1st sess. 
S. Doc. 26, 85th Cong., 
1st sess. 
H. Doc. 76, 85th Cong., 
1st sess. 
Public Law 86-645. 
Public Law 87-874. 
Public Law 87-874 
Public Law 87-874. 
Public Law 89-42. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
42-26 
Oct. 30, 1951 
Sep. 3, 1954 
Jul. 3, 1958 
Jul. 14, 1960 
Oct. 23, 1962 
Jun. 18, 1965 
Oct. 27, 1965

MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Operate and maintain pumping plant in Red River backwater 
area (Tensas-Cocodrie Pumping Plant). 
Provide improvements in West Kentucky tributaries. 
Provide fish and wildlife facilities in St. Francis and Big 
Sunflower Basins; Yazoo Headwater and Backwater Areas; and 
Mississippi Delta region. 
Deauthorize Amite River, LA, project. 
Modify St. Francis River, MO and AR, project within District 
No. 7, Poinsett County, AR. 
Provide pumping plant and drainage structure at Wilson 
Point, LA. 
Construction of improvements to supplement freshwater supply 
in Teche-Vermilion Basins in Louisiana. 
Bank revetment for protection of existing industrial facilities 
along Mississippi River below Baton Rouge, LA. 
Modification of West Tennessee tributaries feature to provide 
relocation of gas transmission lines at Federal expense. 
Continue emergency work, $87,135,000, which includes $100,000 
for road crossing of Panola-Quitman Floodway, MS, and $80,000 
for protection of Sheley Bridge, Tallahatchie River, MS. 
Improvements in Boeuf and Tensas Rivers and Bayou Macon 
Basin to divert flows that would otherwise enter Lake Chicot, 
AR. 
Improvements in the Belle Fountain ditch and tributaries, MO, 
and Drainage District No. 17, AR. 
Provide pumping plants and other drainage facilities in Cairo, 
IL, and vicinity. 
Modification of Yazoo Headwater Project to include cleanout 
along David Bayou, MS. 
Modify Yazoo Backwater feature to include a control structure in 
Muddy Bayou, MS. 
Modification of Yazoo Headwater Project to include drainage 
structure and channel improvement on Rocky Bayou, MS. 
Provide for enlargement of Bayou Latenache from Pointe Coupee 
drainage structure to Alabama Bayou, LA. 
Modify and expand project to include flood protection within the 
area of eastern Rapides and south-central Avoyelles Parishes, 
LA, that are drained by Bayou des Glaises diversion channel 
and Lake Long, and their tributaries. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc., 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
H. Doc. 308, 88th Cong., 
2d sess. 
S. Doc. 57, 89th Cong., 
1st sess. 
Unpublished Vicksburg 
District's MRC report. 
Approved Apr. 14, 1966. 
H. Doc. 524, 89th Cong., 
2d sess. 
Public Law 89-789. 
Public Law 89-789. 
Public Law 90-147. 
H. Doc. 168, 90th Cong., 
1st sess. 
H. Doc. 339, 90th Cong., 
2d sess. 
Public Law 90-483. 
Unpublished MRC report 
dated May 8, 1968. 
Unpublished MRC report 
dated Feb. 2, 1970. 
Unpublished MRC report 
dated Mar. 6, 1970. 
Unpublished MRC report 
dated Sep. 22, 1969. 
S. Doc. 91-113, 2d sess. 
42-27 
TABLE 42-D 
(Continued) 
Apr. 14, 19662 
Nov. 7, 1966 
Nov. 20, 1967 
Aug. 13, 1968 
Sep. 10, 19683 
Mar. 3, 19703 
Apr. 29, 19703 
Jun. 4, 19703 
Dec. 31, 1970

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Senate and 
House Public 
Works 
Resolutions 
adopted Dec. 17 
and 15, 1970 
respectively. 
River Basin 
Monetary Act 
of Dec. 23, 1971 
Jan. 19, 19732 
TITLE I Water 
Resources 
Development 
Act of 1974. 
Modify the project for West Kentucky tributaries (Obion Creek), 
KY, to provide for all relocations, at Federal expense, of all 
transmission lines required by the project. 
Report on Western Tennessee Tributaries, TN and KY, 
authorized: 
a. Modification of Reelfoot Lake feature to provide channel 
improvements on Bayou du Chien and Lake No. 9 in KY and 
TN. 
b. Modification of Mississippi levee feature to include a 
pumping station near Mud Lake floodgate and adjacent 
channel improvements. 
Modification of Big Sunflower Basin feature to provide 
additional improvements in Steele Bayou Basin, MS. 
Continue prosecution of project for the comprehensive 
development of the basin, $97 million. 
Modification of Tiptonville-Obion River levee feature to relieve 
local interests of all responsibility except that of providing 
maintenance. 
Modification of the Mississippi levee feature to provide additional 
drainage facilities in Long Lake area, vicinity of Helena, AR. 
Projects recommended by four completed reports were 
authorized for accomplishment of Phase I design memorandum 
of advance engineering and design on: 
a. Greenville Harbor, Greenville, MS. 
b. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Natchez area). 
c. East bank of Mississippi River, Warren to Wilkinson 
Counties, MS (Vicksburg-Yazoo area). 
d. Bushley Bayou Area of Red River Backwater Area, LA. 
Modification of West Tennessee tributaries feature (Obion and 
Forked Deer Rivers), TN, to acquire lands for fish and wildlife, 
recreation, and environmental purposes. 
Modification of the Yazoo Basin, MS, feature to provide for a 
streambank erosion control demonstration project for the delta 
and hill areas of basin. 
Modification of project to provide that the Secretary of the Army, 
acting through the Chief of Engineers, can substitute authorized 
mitigation lands, not yet acquired and no longer suitable, for 
like acreage in the same or adjacent subbasins of the project 
area. This section provides the authority to substitute authorized 
mitigation lands in: 
a. Tensas Basin, LA and AR, feature (Red River backwater). 
b. St. Francis Basin, AR and MO, feature. 
Public Law 91-611. 
H. Doc. 91-414, 2d sess. 
S. Doc. 91-74, 2d sess. 
Sec. 1, Public Law 92-222. 
Sec. 7, Public Law 92-222. 
Unpublished Memphis 
District's MRC report 
dated Oct. 4, 1972. 
Sec. 1, Public Law 93-251, 
Mar. 7, 1974. 
S. Doc. 93-38, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-148, 1st sess. 
H. Doc. 93-157, 1st sess. 
Sec. 3, Public Law 93-251. 
Sec. 32, Public Law 93-251. 
Sec. 42, Public Law 93-251. 
42-28

MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
TITLE II River 
Basin 
Monetary 
Authorization 
Act of 1974 
River Basin 
Monetary Act 
of Oct. 2, 1975 
Dec. 16, 19752 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1976. 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1977. 
Water Resources 
Development 
Act of 1976. 
Modification of Bayou Cocodrie and tributaries, LA, feature, to 
provide for: enlargement of Bayou Courtableau from 
Washington to west protection levee; right-of-way and spoil 
disposal areas at Federal expense; and necessary additional 
culverts through west protection levee. 
Modification of Cache River Basin, AR, feature to provide for: 
acquisition by fee easements of lands for fish and wildlife 
management, recreation, and environmental purposes. 
Continue prosecution of project for the comprehensive 
development of the basin, $211 million. 
Continue prosecution of project for the comprehensive 
development of the basin, $158,000,000. 
Modification of St. Francis Basin, AR and MO, feature to provide 
relief from ponding of interior runoff in the Inter-River 
Drainage District of Missouri. 
Continue prosecution of project for comprehensive development 
during period Jul. 1-Sep. 30, 1976, $60,300,000. 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $231,497,000. 
Sec. 101(a) authorized accomplishment of Phase I - Advanced 
Engineering and Design Memoranda-On: 
a. St. Johns Bayou and New Madrid Floodway, MO, project: 
Report of OCE - Sep. 26,1975. 
b. Nonconnah Creek, TN and MS, project: Report of OCE - 
Jun. 23, 1976, and as an independent part of the project: 
Improvements for flood control and allied purposes on Horn 
Lake Creek and tributaries, including Cowpen Creek, TN 
and MS. 
Sec. 87, Public Law 93-251. 
Sec. 99, Public Law 93-251. 
Sec. 201, Public 
Law 93-251. 
Mar. 7, 1974. 
Sec. 1, Public Law 94-101. 
Unpublished Memphis 
District's MRC report 
dated Nov. 11, 1975. 
Public Law 94-180, 
Dec. 26, 1975. 
Public Law 94-355, 
Jul. 12, 1976. 
Public Law 94-587, 
Oct. 22, 1976. 
42-29 
TABLE 42-D 
(Continued)

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-D 
(Continued) 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
TITLE II Public 
Works for 
Water and 
Power 
Development 
and Energy 
Research 
Appropriation 
Act, 1978. 
Dec. 9, 1977, 5th 
Ind. on VXD 
May 31, 1977, 
Letter Report.2 
Jun. 28, 1980 
Energy and 
Water 
Development 
Appropriation 
Act. 1981 
Supplemental 
Appropriations 
Bill for FY 
Ending 
Sep. 30, 1985 
(PL 99-88), and 
the Water 
Resources 
Development 
Act of 1986 
(PL 99-662) 
Modification of West Tennessee Tributaries feature (Obion and 
Forked Deer Rivers), TN, to: 
a. (Sec. 102) - Provide project for flood control for Harris Fork 
Creek, TN and KY: (H.D. 94-221) except that highway bridge 
relocations and alterations shall be at Federal expense. 
b. (Sec. 183) - Provide for construction of a levee and 
appurtenant works from mouth of Obion diversion channel to 
vicinity Highway 88 and thence to vicinity of Porter Gap, TN. 
Continue prosecution of project for flood control, rescue work, 
repair, restoration, and control of bank erosion, $253,081,000. 
Modification of the Tensas Basin Project, Red River Backwater 
Area, to include a drainage structure and appurtenant channel 
works in the Six Mile Bayou area of Concordia Parish, LA. 
The establishment of the Tensas River National Wildlife Refuge 
for the preservation and development of environmental 
resources and in lieu of mitigation acquisitions which 
otherwise would be required for certain water resources 
projects, within designated limits, in the basins of the Tensas, 
Boeuf, and Red Rivers in the State of Louisiana. 
For expenses necessary for prosecuting work of flood control 
projects, rescue work, repair, restoration or maintenance of 
flood control projects threatened or destroyed by flood, 
$232,519,000: Provided, That not less than $250,000 be 
available for control of bank erosion of streams in the Yazoo 
Basin, including the foothill area. Provided further, That funds 
for the Tensas Basin Red River Backwater Area, be used for 
flood control, etc., for Sicily Island and Below Red River 
including pumping stations. 
Authorizes and directs the Secretary of the Army acting 
through the Chief of Engineers to proceed with planning, 
design, engineering, and construction of 41 water resources 
projects, including Atchafalaya Basin Floodway System. For 
the Atchafalaya Basin Floodway Systems project, cost-sharing 
is only required for the recreation feature of the project. The 
flood control and environmental features are Federal costs. 
Public Law 95-96 
Aug. 7, 1977. 
Unpublished Vicksburg 
District report dated 
May 31, 1977, on Cynthia 
and Six Mile Bayous, LA. 
Public Law 96-285, 
Jun. 28, 1980. 
Public Law 96-367, 
Oct. 1, 1980. 
FY 1985 Supplemental 
Appropriations Bill 
(PL 99-88), and Water 
Resources Development 
Act of 1986 (PL 99-662). 
42-30

MISSISSIPPI RIVER COMMISSION 
AUTHORIZING LEGISLATION 
Act or 
Authorization Work Authorized Document 
Water 
Resources 
Development 
Act, 1986 
Public Law 99-662, 
Nov. 17, 1986. 
42-31 
TABLE 42-D 
(Continued) 
Sec. 104(a), Authorization of Projects - Authorization of 
Construction: 
Incorporation of the project for flood control, Louisiana State 
Penitentiary levee, Mississippi River, LA: Report of the Chief 
of Engineers, dated Dec. 10, 1982, at a total cost of $23,400,000, 
with an estimated first Federal cost of $17,600,000 and an 
estimated first non-Federal cost of $5,800,000. No acquisition 
of land for or actual construction of the project may commence 
until appropriate non-Federal interests shall agree to 
undertake measures to minimize the loss of fish and wildlife 
habitat lands in the project area. 
a. Bushley Bayou, LA. Water Resources Development Act of 
1986 authorized the project for flood control, Bushley 
Bayou, LA. 
b. Eight Mile Creek, Paragould, AR. Project entails channel 
improvement along the creek with miniparks and hiking/ 
biking trails. 
c. Helena and Vicinity, AR. The Helena Basin is an urban 
basin containing approximately 3,500 acres which 
frequently and severely floods the city of Helena. A 
pumping station and sump with channel enlargement and a 
gated culvert was recommended. 
d. West Memphis and Vicinity, AR. Channel improvements 
along Ten Mile Bayou and Fifteen Mile Bayou for a total of 
23.86 miles, with limited revegetation of right-of-way to 
maintain environmental stability. 
e. St. Johns Bayou and New Madrid Floodway, MO. Flood 
control for urban and rural land. 
f. Nonconnah Creek and Johns Creek, TN and MS. Channel 
enlargement, recreation features with channel construction 
and environmental enhancement. 
g. Horn Lake Creek and Tributaries, TN and MS. This is an 
urban flood control project located in extreme northwest 
Mississippi and southwest Tennessee. The plan of 
improvement consists of 3.5 miles of selective drift removal 
on lower Horn Lake Creek and 2.6 miles of vegetative 
clearing on Horn Lake Creek, 2.1 miles on Rocky Creek and 
0.6 miles of vegetative clearing and 1.8 miles of channel 
enlargement on Cow Pen Creek. Hike/bike trails are 
included along Rocky Creek and Cow Pen Creek. 
Sec. 601(a) Authorization of Projects. Authorization of 
Construction: 
a. Yazoo Backwater Area, MS. Authorized the project for 
mitigation of fish and wildlife losses at the Yazoo 
Backwater Project, MS. The project shall include 
acquisition of 40,000 acres for mitigation of project-induced 
fish and wildlife losses. 
b. Greenville Harbor, MS. Authorized the project for 
navigation, Greenville Harbor, MS, as contained in the 
reports of Chief of Engineers, Nov. 15, 1977 and 
Feb. 2, 1982, at a total cost of $43,700,000 with an estimated 
first Federal tost of $28,000,000 and an estimated non- 
Federal first cost of $15,700,000.

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-D AUTHORIZING LEGISLATION 
(Continued) 
Act or 
Authorization Work Authorized Document 
c. Vicksburg Harbor, MS. Authorized the project for 
navigation, Vicksburg Harbor, as contained in the report of 
the Chief of Engineers, Aug. 13, 1979, at a total estimated 
first Federal cost of $55,900,000 and an estimated non- 
Federal first cost of $23,300,000. 
d. Helena Harbor, Phillips County, AR. The recommended 
plan consists of dredging a navigation channel to provide 
access to 685 acres of landfill; construction of an overlook 
park; implementing landscaping and erosion control 
measures; and mitigation fish and wildlife losses. The 
project is scheduled to be constructed in two phases. 
e. White River Navigation to Batesville, AR. The plan of 
improvement recommended in the Feasibility Report 
provides for construction and maintenance to provide a 
200-foot wide, 9-foot deep channel available 95 percent of the 
time from mile 10 (Arkansas Post Canal) to mile 254, two 
scenic overlooks, a primitive camping area, and acquisition 
of about 1,865 acres of woodlands for mitigation. However, 
section 52 of the Water Resources Development Act of 
1988 deauthorized this project. 
f. Obion Creek, KY. To prevent headwater flooding along 
tributary streams and backwater flooding of alluvial lands. 
g. Memphis Harbor, Memphis, TN. This is a navigation 
project in the vicinity of Memphis, TN, which would consist 
of dredging and maintaining a 4.9 mile long, 500-foot 
minimum width, 9-foot deep general navigation channel 
with additional dredging as required and strategic 
placement of dredged material to create and provide 
navigation access to 1,000 acres to be developed as a 
waterfront industrial complex. 
Sec. 806. Reelfoot Lake, KY. This project is modified to 
provide that the Federal share of the cost of operating the 
pumping plant feature of such project shall be 50 percent. 
Sec. 836. Mud Lake, Western Tennessee Tributaries. This 
project is modified to provide that the requirements of local 
cooperation shall be (1) 50 percent of the value of the lands, 
easements, and rights-of-way, (2) to hold and save the United 
States free from damages due to the construction works, and 
(3) to maintain and operate all the works after completion. 
Jun. 4, 1987 Modification of Mississippi Delta Region project to construct Unpublished New Orleans 
salinity control structure at Davis Pond (mile 118) rather than District report, 
at Myrtle Grove (mile 59). Nov. 1, 1984. 
Water Sec. 3(a), Project Authorizations - Authorization of Public Law 100-676 
Resources Construction: Nov. 17, 1988 
Development a. Mississippi-Louisiana Estuarine Area, MS and LA. 
Act, 1988 Authorized the project for environmental enhancement, 
as contained in the report of Chief of Engineers, dated 
May 19, 1986, at a total cost of $59,300,000. 
42-32

MISSISSIPPI RIVER COMMISSION 
TABLE 42-D AUTHORIZING LEGISLATION 
(Continued) 
Act or 
Authorization Work Authorized Document 
Water Section 4(b) Public Law 100-676, 
Resources West Memphis and Vicinity, AR. Modified the project Nov. 17, 1988 
Development by allowing that non-Federal cooperation may be 
Act, 1988 provided by levee districts, drainage districts, or 
any unit of a state, county, or local government. 
Energy and West Memphis and Vicinity, AR. Public Law 101-83, 
Water Directed the Corps to develop the most cost-effective Jul. 25, 1989 
Development flood control plan for the City of West Memphis without 
Appropriation regard to frequency of flooding, drainage area, and the 
Bill, 1990 amount of runoff. 
Energy and Bayou Rapides Drainage Structure and Pumping Plant Public Law 101-514, 
Water Directed the Secretary of the Army to incorporate Nov. 5, 1990 
Development existing flood control features for the Bayou Rapides 
Appropriation Drainage Structure and Pumping Plant into the Lower Red 
Bill, 1990 River, South Bank Levees portion of the MR&T Project. 
Water Resource Whiteman's Creek, Arkansas. Public Law 102-580 
Development Directed the Secretary of the Army to implement flood control Oct. 31, 1992 
Act, 1992 improvement, which essentially consist of 6.1 miles of channel 
enlargement along streams within the city limits of Jonesboro, 
Arkansas. 
1. Incorporated into Mississippi River and tributaries project as shown in Table 42-E. 
2. Date minor modification for blocked drainage was approved under delegated authority of the President, Mississippi River 
Commission, and in accordance with Sec. 10(p) of the 1946 Flood Control Act (Public Law 79-526). 
3. Date minor modification was approved under discretionary authority of Chief of Engineers contained in May 15, 1928, Flood 
Control Act, as amended. 
4. Projects approved under the provisions of Sec. 201 of Flood Control Act of Oct. 27, 1965. 
42-33

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-E INCORPORATING AND AUTHORIZING 
LEGISLATION 
For Last 
Public Full Report 
Act of Law Authorizing See Annual 
Incorporation No. Act Description Report for 
Jul. 24, 1946 79-526 Jun. 22, 1936 Tiptonville-Obion levee and drainage 1941, p. 943 
improvements, TN 
Jul. 24, 1946 79-526 Jun. 22, 1936 Bayou des Glaises diversion ditch, LA 1946, p. 1029 
Jul. 24, 1946 79-526 Jun. 22, 1936 From North Little Rock, AR, to Gillett, 1946, p. 1053 
AR, on north bank of Arkansas River 
(portion below Plum Bayou) 
Jul. 24, 1946 79-526 Aug. 18, 1941 White River levees, Augusta to 1946, p. 1083 
Clarendon and De Valls Bluff, AR 
Jul. 24, 1946 79-526 Dec. 22, 1944 Boeuf and Tensas Rivers and Bayou 1945, p. 982 
Macon, LA 
Jul. 24, 1946 79-526 Dec. 22, 1944 Big Sunflower River, etc. 1946, p. 1061 
Jun. 30, 1948 80-858 Jul. 24, 1946 Devils Swamp barge channel at Baton 1948, p. 1059 
Rouge, LA (Baton Rouge Harbor) 
May 17, 1950 81-516 Jun. 22, 1936 Jonesville, LA 1953, p. 773 
May 17, 1950 81-516 Jul. 24, 1946 Lake Pontchartrain-Jefferson Parish, LA 1953, p. 737 
42-34

MISSISSIPPI RIVER COMMISSION 
TABLE 42-F SUMMARY OF PRESENTLY ESTIMATED 
FEDERAL FIRST COST OF AUTHORIZED IMPROVEMENTS 
Estimated Cost 1 
Project Title Fiscal Year 1992 
Completed features 2 
Mississippi River levees 
Mud Lake Pumping Station, TN 
Sec. 6 levees, 1928 Flood Control Act 
Channel improvement 
Atchafalaya Basin, LA 
Atchafalaya Basin Floodway System, LA 
Bayou Cocodrie and tributaries, LA 
Old River, LA 
Lower Red River--South Bank Red River levees, LA 
Eastern Rapides and South-Central Avoyelles Parishes, LA 
Mississippi Delta Region, LA 
Tensas Basin, AR and LA 
Lower Arkansas River, AR 
Grand Prairie-Bayou Meto, AR (Flood Control & Water Supply) 
Yazoo Basin, MS 
Lower White River, AR (All except Big Creek & Tribs.) 
Lower White River (Big Creek & Tribs.) 
Cache Basin, AR 
St. Francis Basin, AR and MO 
Eight Mile Creek, AR 
L'Anguille Basin, AR 
West Tennessee Tributaries, TN 
Harris Fork Creek, TN and KY 
Reelfoot Lake-Lake No. 9, TN and KY 
Reelfoot Lake, TN and KY (Completed) 
Reelfoot Lake-Lake No. 9, TN and KY 
West Kentucky Tributaries, KY 
Tensas River National Wildlife Refuge 
Sardis Dam (Dam Safety Assurance) 
St. Johns Bayou and New Madrid Floodway 
Nonconnah Creek 
Horn Lake Creek and Tributaries 
Greenville Harbor 
Memphis Harbor (Ensley Berm) 
Helena Harbor 
Helena, AR, and Vicinity 
West Memphis, AR, and Vicinity 
Vicksburg Harbor, MS 
Louisiana State Penitentiary Levee 
$ 199,238,000 
1,370,000,000 
5,270,0003 
4,000,0003 
3,570,000,000 
1,550,000,000 
142,700,000 
20,400,0003 
292,273,000 
23,200,0003 
50,000,000 3 
84,300,000 
522,000,000 
29,680,0003 
130,900,0003 
1,997,000,000 
16,802,0003 
49,800,0003 
141,000,000 
381,000,000 
9,100,0003 
14,000,0003 
124,000,000 
14,300,0003 
(10,700,000) 3 
440,000 
10,266,000 
24,800,0003 
40,000,0003 
29,400,000 
46,600,0004 
18,400,0004 
2,290,0004 
32,400,0003,4 
23,100,0004 
32,156,0004 
7,365,0003,4 
11,600,0004,6 
63,500,0004 
18,800,0004 
42-35

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-F 
(Continued) 
SUMMARY OF PRESENTLY ESTIMATED 
FEDERAL FIRST COST OF 
AUTHORIZED IMPROVEMENTS 
Estimated Cost1 
Project Title Fiscal Year 1992 
Teche Vermilion Basin 35,700,0004 
Mississippi and Louisiana Estuarine Areas 3,340,0005 
Whiteman's Creek, AR 3,340,000 
Eastern Arkansas 114,0003 
Jackson and Trenton, AR 8,800,0003 
Mississippi Delta, MS 157,300,0003 
Bushley Bayou 37,000,000 
TOTAL $11,403,428,000 
1. Inflation projected through the construction period. Harbors; Lake Pontchartrain; Wolf River; completed 
roads. 
2. Includes Bonnet Carre', Morganza, and New Madrid Floodways; Memphis, Greenville, and Vicksburg on 
main stem levees; channel construction works; Atchafalaya River and Basin; Wax Lake Outlet; Charenton 
Canal; Bayou des Glaises diversion channel, Boeuf Basin levees; Grant's Canal; De Valls Bluff, Jonesville, 
and Des Arc protection works; Baton Rouge Harbor; and miscellaneous features; Teche-Vermilion Basins, 
LA. 
3. Incremental (not projected through the construction period). 
4. Authorized by Water Resources Development Act of 1986, Public Law 99-662, Nov. 17, 1986. 
5. Authorized by Water Resources Development Act of 1988, Public Law 100-676, Nov. 18, 1988. 
6. Locals are building their own project. 
42-36

TABLE 42-G 
MISSISSIPPI RIVER COMMISSION 
MISSISSIPPI RIVER MAIN STEM 
CHANNEL IMPROVEMENTS 
Location Operations in 1,000 Cubic Yards 
Mileage Fiscal Year 1992 
Above Head Channel 
District of Passes Construction Maintenance Total 
New Orleans 
Baton Rouge Harbor 
(Devils Swamp) 235 -- -- -- 
Main stem channel 234-320 -- 721.3 721.3 
Vicksburg 
Main stem channel 322-600 -- 2,476.1 2,476.1 
Vicksburg Harbor 437 -- 86.7 86.7 
Greenville Harbor 537 -- 70.2 70.2 
Memphis 
Main stem channel 600-954 -- 29,982.6 29,982.6 
Memphis Harbor, 
McKellar Lake 725 -- 1,053.7 1,053.7 
TOTAL -- 34,390.6 34,390.6 
42-37

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)1 Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Venice, LA .............. 
Olga, LA ................ 
Lower Childress- 
Fort Jackson, LA ........ 
Buras, LA .............. 
Tropical Bend, LA ........ 
Bayou Lamoque, LA ...... 
Port Sulphur, LA ......... 
Point Michel, LA ......... 
Bohemia, LA ............ 
Diamond, LA ............ 
Gravolet, LA ............ 
Junior, LA .............. 
Harlem, LA ............. 
Myrtle Grove, LA ........ 
Monsecour, LA .......... 
Alliance, LA ............ 
Belair, LA .............. 
Jesuit Bend, LA .......... 
Linwood, LA ............ 
Oak Point, LA ........... 
Scarsdale, LA ........... 
English Turn, LA ........ 
Poydras, LA ............. 
Twelve Mile Point, LA ..... 
Cutoff, LA .............. 
Third district reach, LA .... 
Algiers Point, LA ......... 
Gouldsboro Bend, LA ...... 
Gretna Bend, LA ......... 
Greenville Bend, LA ...... 
Carrollton Bend, LA ...... 
Avondale Bend, LA ....... 
Kenner, LA ............. 
12 
19 
22 
25 
30 
33 
39 
44 
46 
49 
51 
54 
56 
59 
61 
62 
65 
68 
71 
72 
75 
78 
82 
84 
88 
93 
95 
96 
97 
100 
104 
109 
R
L
R
R
R
L
R
R
L
R
L
R
L
R
L
R
L
R
L
R
L
R
L
R
R
L
R
R
R
R
L
R 
13,885 
2,718 
4-,-510 
-- 
- 
114 L -- 
-- 40,126 
-- 94,951 -- 13,885 
57 
--. 
-- 
10,430 
15,162 
-- 
-- 
--. 
3,152 
569 
995 
3,295 
-- 
-- 
-- 
-- 
-- 
19,442 
2,105 
6,022 
20,360 
-- 
-- 
-- 
--.. 
-- 
7,930
-- 
10,587 
12,901 
--
-- 
-- 
--. 
2,826 -- 41,595 
0O
H
0
O
0
C, 
O O 
x
ca 
m
D 
t 
15,430 
17,283 
25,012 
19,537 
36,995 
22,932 
15,441 
11,600 
23,874 
23,599 
15,148 
17,435 
11,571 
17,265 
26,111 
24,978 
12,005 
12,377 
16,570 
19,718 
45,864 
9,979 
21,256 
27,167 
12,238 
4,960 
9,662 
22,045 
15,015 
28,409 
,, 
,, 
,, 
,, 
,, 
,, 
,, 
,, 
,, 
,, 
,I

TABLE 42-H BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(Continued) (FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
Luling, LA .............. 119 R 5,660 173 26,945 -- -- -- -- 41,948 
Destrehan, LA ........... 102 L -- -- -- -- -- -- -- 5,409 
Good Hope, LA .......... 126 L -- -- -- -- -- -- -- 24,531 
Waterford, LA............ 128 R -- -- -- -- -- -- -- 20,386 
Montz, LA .............. 132 L -- -- -- -- -- -- -- 17,502 
Lucy, LA ............... 136 R -- -- -- -- -- - - -- 17,826 
Reserve, LA ............. 138 L -- -- -- -- -- -- -- 20,947 
Willow Bend, LA ......... 141 R -- -- -- -- -- -- -- 13,227 
Angelina, LA ............ 145 L -- -- -- -- -- -- -- 31,727 
Vacherie, LA ............ 148 R -- -- -- -- -- -- -- 26,025 
Belmont, LA ............ 152 L -- -- -- 741 7,122 -- -- 25,575 
Rich Bend, LA ........... 157 R -- -- -- -- -- -- -- 38,498 
Romeville, LA ........... 161 L -- -- -- -- -- -- -- 25,966 
St. Alice, LA ............ 165 R -- -- -- -- -- 8,877 -- 27,052 
Burnside, LA ............ 170 L -- -- -- -- -- -- -- 29,304 
Aben, LA ............... 172 R -- -- -- -- -- 3,690 -- 11,700 
St. Elmo, LA ............ 174 L -- -- -- -- -- -- -- 10,240 
Smoke Bend, LA ......... 177 R 1,147 65 4,656 -- -- -- -- 18,180 
Marchand, LA ........... 180 L -- -- -- -- -- -- -- 17,583 
Philadelphia Point, LA .... 183 R -- -- -- -- -- -- -- 5,379 
New River Bend, LA ...... 185 L 2,007 56 10,091 -- -- -- -- 45,672 
White Castle, LA ......... 193 R -- -- -- -- -- -- -- 42,658 
St. Gabriel, LA .......... 201 L -- -- -- -- -- -- -- 33,292 
Plaquemine Bend, LA ..... 209 R -- -- -- -- -- -- -- 42,952 
Manchac, LA ............ 215 L -- -- -- -- -- -- -- 38,976 
Missouri Bend, LA ........ 222 R -- -- -- -- -- -- -- 27,498 
Arlington, LA ........... .227 L -- -- -- -- -- -- -- 16,615 
Port Allen, LA ........... 231 R -- -- -- -- -- -- -- 17,627 
Scotlandville, LA ......... 234 L 1,623 -- 9,119 -- -- -- -- 1,623 
Allendale, LA ........... 238 R -- -- -- -- -- -- -- 25,502 
Springfield Bend, LA ...... 244 L -- -- -- -- -- -- -- 25,690 
Arboth, LA ............. 250 R -- -- -- -- -- -- -- 13,190 
Faulkner Lake, LA ....... 253 L -- -- -- -- -- 10,540 -- 17,382 
Grand Bay, LA .......... 258 R 7,122 110 31,752 -- -- 20,559 -- 12,302 
Bayou Sara, LA .......... 265 L -- -- -- 4,720 19,608 -- -- 27,698 
MCI 
CI) 
CI) 
C) 
0
z

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
Red Store, LA ........... 
Arrow Bend, LA ......... 
Boies Point, LA .......... 
Morganza, LA ........... 
Iowa Point, LA .......... 
Brunette Point, LA ....... 
Greenwood Bend, LA ...... 
Hog Point, LA ........... 
Carr Point, LA .......... 
Above Old River, LA ...... 
Fort Adams, MS ......... 
Point Breeze, LA ......... 
Coochie, LA............. 
0 Palmetto, MS ........... 
269 
272 
275 
279 
282 
285 
289 
296 
304 
305 
308 
313 
317 
322 
R
L
R
R
L
R
L
R
R
R
L
R
R
L 
7,149 
10,828 
5,923 
325 
245 
910 
-- 
-- 
-- 
-- 
--. 
30,083 
51,033 
32,699 
-- 
-- 2,320 
-- 
-- 
-- 
-- 
-- 
-- 
-- 
6,-0-78 
Subtotal 
New Orleans District, 
Mississippi River ..... 
Dikes: 
Profit Island Chute 
Closure, LA ............. 
Hog Point, LA ............ 
OLD RIVER CONTROL 
Standard revetment: 
Inflow channel ........... 
Inflow channel ........... 
Outflow channel ......... 
252 L 
299 L 
C00 
5a 
13 
H
O
ra 
A
O
Ci 
H
0
0I
0
0
O 
d 
r
e0 Cm 
62,572 1,941 316,921 15,792 80,737 77,910 -- 1,741,162 
(11.85 Miles) (2.99 Miles) (329.76 Miles) 
-- -- -- -- -- -- -- 4,315 
6,850 -- -- -- -- -- -- 6,850 
6,850 
(1.30 Miles) 
315 L 
315 R 
315 L&R 
11,165 
(2.12 Miles) 
-- 2,415 
-- 4,365 
-- 19,891 
18,464 
13,600 
16,094 
20,513 
11,375 
8,038 
25,815 
21,424 
17,120 
8,170 
24,206 
13,565 
17,150 
30,864

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares) Feet) Feet) 
Auxiliary inflow channel ... 312 L&R -- -- -- -- -- -- 17,200 
Auxiliary outflow channel .. 312 L&R -- -- -- --- -- -- 5,790 
Total standard revetment, 
Old River ............ -- 49,661 
(9.41 Miles) 
ATCHAFALAYA RIVER 
Standard revetment: 
Mile One, LA ............ 
Coville Bayou, LA ........ 
Legonier, LA ............ 
Simmesport, LA ......... 
Kuhlman Bayou, LA ...... 
Odenburg, LA ........... 
Cason, LA .............. 
McCrea, LA ............. 
Woodside, LA ........... 
Provosty, LA ............ 
Crooked Bayou, LA ....... 
Mercier, LA............. 
Barberton, LA ........... 
Evans Point, LA ......... 
Goudeau, LA ............ 
Morris Bayou, LA ........ 
Goodwood, LA ........... 
Red Cross, LA ........... 
Melville LA ............. 
Cross Bayou, LA ......... 
Melville South, LA ....... 
Toles, LA ............... 
Petite Prairie, LA ........ 
Below Confluence 
of Red and 
Atchafalaya 
Rivers 
1
3
4
6
7
9 
12 
13 
14 
17 
18 
22 
23 
24 
26 
27 
28 
29 
30 
31 
33 
35 
36 
L
R
L
R
L
R
R
L
R
L
R
L
R
L
R
L
R
L
R
L
R
L
R 
1,545 
.. 
.- 
--
.. 
-- 
--
.. 
-- 
--
.- 
-- 
4O 
--. - 
-- 
-- 
-- 
-- 
--8,456 
-- 
-- 
8,456 
--
.-- 
.-- 
--
--. 
-- 
-- 
U, 
U, 
=. 0 
9,628 
.. 
.. 
.. 
.. 
.. 
..
.. 
.. 
-- 
-- 
1,705 
1,188 
-- 
--
-- 
5,915 
4,254 
-- 
-- 
-- 
-- 
-- 
4,150 
6,550 
8,940 
10,636 
5,565 
5,375 
10,798 
6,572 
13,002 
7,768 
9,600 
10,478 
3,592 
4,898 
3,938 
3,800 
8,505 
8,065 
4,870 
3,815 
4,070 
6,355 
8,381 
F 
F

TABLE 42-H 
(Continued) 
BANK REVETMENTS AND DIKES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)l Feet) Feet) 
Holloway Lake, LA ....... 37 L -- -- -- -- -- -- -- 7,085 
Bayou Sherman, LA ...... 38 L -- -- -- -- -- -- -- 5,200 
Krotz Springs, LA ........ 40 R -- -- -- -- -- -- -- 7,925 
Sherburne, LA ........... 43 R -- -- -- -- -- -- -- 7,035 
Bayou Big Graw, LA ...... 46 R -- -- -- -- -- -- -- 8,394 
Otis Landing, LA ......... 54 R -- -- -- -- -- -- -- 5,251 
Morgan City ............ 115 L -- -- -- -- -- -- -- 3,410 
Total standard revetment 1,545 40 8,456 2,893 10,169 9,628 -- 204,023 
(.29 miles) (.55 miles) (38.64 Miles) 
Dikes: 
None 
Below Confluence 
of Old River 
LOWER RED RIVER Outflow Channel 
and Red River 
Standard revetment: 
Long Lake, LA ........... 10 R -- -- -- -- -- -- -- 6,652 
Naples, LA ............. 7 R -- -- -- -- -- -- -- 6,190 
Turnbull Island, LA ....... 9 L -- -- -- -- -- -- -- 11,038 
Total standard revetment -- -- -- -- -- -- 23,880 
(4.52 Miles) 
Dikes: 
None 
1. Gross squares articulated concrete mattress (100 square feet). 
t3 
ro 
0
0
O
I
O
0
0I
0
A
H
UO 
0
O- 
56 
b

TABLE 42-I BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares) 1 Feet) (Squares)1 (Squares)1 Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Bougere Bend, LA ........ 
Dead Mans Bend, MS ..... 
Glasscock Cutoff, MS-LA ... 
Railroad Landing, MS ..... 
St. Catherine Bend, LA .... 
Morville, LA ............ 
Natchez Island, MS ....... 
Carthage, MS ........... 
Vidalia Casting Field ...... 
Natchez Front, MS ....... 
Giles Cutoff, LA-MS ...... 
Gibson, LA ............. 
Ashland, LA-MS ......... 
Kempe Bend, LA ......... 
Browns Field, LA ........ 
Goldbottom, MS .......... 
Hardscrabble, LA ........ 
Grand Gulf, MS .......... 
Point Pleasant, MS-LA .... 
Togo Island, LA .......... 
Lake Karnac, LA-MS ...... 
Diamond Point, LA-MS .... 
Reid-Bedford, LA ......... 
Racetrack, MS ........... 
Barge Line Terminal, MS .. 
Vicksburg Harbor, MS ..... 
Delta Point, LA .......... 
King's Point--Opposite 
Delta Point, LA-MS ...... 
False Point, LA .......... 
Marshall-Brown's Point, 
LA-MS ............... 
Milliken Bend, LA ....... 
Belle Island, LA-MS ..... 
329 
335 
342 
346 
350 
356 
357 
361 
363 
364 
366 
371 
374 
383 
389 
392 
398 
403 
413 
415 
419 
423 
429 
433 
437 
437 
437 
R
L
R
L
R
R
R
L
L
L
R
R
L
R
R
L
R
L
R
R
L
R
R
L
L
L
R 
439 L 
443 R 
446 L 
453 R 
460 L 
4,585 
-- 
.- 
2,080 
2,540 
-- 
-- 
-- 
195 
-- 
-- 
--. 
--. 
904 
.. 
.. 
..
.. 
-- 
5,945 
--
-- 
5,967 
6,855 
--
-- 
-- 
--. 
10,766 -- 
-- 
-- 
-- 
26,055 
33,220 
20,540 
12,235 
29,108 
14,855 
2,180 
14,700 
2,670 
6,510 
5,270 
26,000 
29,407 
28,285 
9,280 
30,250 
22,530 
53,948 
32,345 
7,080 
19,260 
14,665 
18,392 
13,935 
3,040 
7,350 
7,650 
-- 19,330 
-- 12,860 
1,490 
-- 
165 
.-- 
3,664 423 -- 
19,580 
46,140 
24,160 
U
0
H
H 
M
OU, 
U, 
0x

TABLE 42-I BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(Continued) (FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)1 Feet) Feet) 
Goodrich, LA ............ 467 R -- -- -- -- -- -- -- 39,205 
Cottonwood Bar, MS ...... 470 R -- -- -- -- -- -- -- 18,580 
Filter-Cottonwood, MS ..... 474 L -- -- -- -- -- -- -- 28,427 
Hagaman, LA ........... 481 R -- -- -- -- -- -- -- 37,756 
Ben Lomond, MS ......... 486 L -- -- -- -- -- -- -- 10,235 
Baleshed Towhead-Stack 
Island, LA-MS .......... 488 R -- -- -- -- -- -- -- 52,1242 
Lake Providence, LA ...... 489 R -- -- -- -- -- -- -- 11,600 
Mayersville, MS ......... 497 L -- -- -- -- -- -- -- 34,992 
Sarah Island-Opossum 
Point, LA-MS .......... 503 R -- -- -- -- -- -- 26,815 
Carolina, MS ............ 507 L -- -- -- -- -- -- -- 11,080 
Cracraft, AR ............ 511 R -- -- -- -- -- -- -- 22,210 
Worthington, MS-AR ...... 514 R -- -- -- -- -- -- -- 8,350 
Walnut Point Kentucky 
Bend, MS ............. 519 L -- -- -- -- -- -- -- 45,653 
American Cutoff, MS-AR ... 526 L -- -- -- -- -- -- -- 2,980 
Sunnyside-Lakeport, AR ... 530 R -- -- -- 5,775 13,553 13,762 -- 33,685 
Vancluse, AR ............ 534 R -- -- -- -- -- -- 4,300 
Island 84, AR-MS ........ 535 L -- -- -- -- -- -- -- 13,475 
Warfield Point, MS ....... 537 L -- -- -- -- -- -- -- 4,320 
Leland-LaGrange, AR-MS .. 538 L -- -- -- -- -- -- -- 14,150 
Spanish Moss, AR ........ 539 R -- -- -- -- -- -- -- 4,580 
Tarpley Island, MS ....... 542 R -- -- -- -- -- -- -- 2,000 
Miller Bend, MS ......... 544 L -- -- -- -- -- -- -- 29,360 
Island 82, AR ........... 546 R -- -- -- -- -- -- -- 3,080 
Ashbrook Island, MS ...... 549 R -- -- -- -- -- -- -- 3,455 
Arkansas City-Yellow 
Bend, AR .............. 553 R -- -- -- -- -- -- -- 43,015 
Huntington Point, MS ..... 556 L 2,455 1,172 10,728 -- -- 7,168 -- 21,205 
Pair O'Dice, AR .......... 561 R -- -- -- -- -- -- -- 9,095 
Eutaw-Mounds, MS ....... 563 L -- -- -- -- -- -- -- 40,188 
Cypress Bend, AR ........ 568 R -- -- -- -- -- -- -- 31,575 
Catfish Point, MS ........ .573 L -- -- -- -- -- -- -- 20,075 
Ozark, AR-MS ........... 578 R -- -- -- -- -- -- -- 22,015 
Prentiss, AR-MS .......... 582 L -- -- -- -- -- -- 20,315 
00 
HU, 
0
0I
0
U, 
0
y
O
z
A
O
r

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
Rosedale Bend, AR ....... 
Riverton, MS ............ 
Klondike, AR ............ 
Victoria Bend-Terrene, MS 
Lake Concordia, MS ...... 
Big Island, AR ........... 
Smith Point, MS ......... 
Dennis, MS ............. 
Cessions, MS ........... 
Total revetment, 
Vicksburg District, 
Mississippi River ....... 13,150 
(2.49 Miles) 
Dikes: 
Jackson Point, MS ........ 
Esperance Point, LA ...... 
Opposite Warnicott Ldg., 
MS .................. 
Natchez Island, LA-MS .... 
Waterproof Bar, LA ....... 
Spithead Towhead, MS .... 
Browns Field, LA ........ 
Cottage Bend, LA-MS ..... 
Bondurant Towhead, LA ... 
Coffee Point, LA ......... 
Yucatan, MS ........... 
Togo Island, LA .......... 
Below Racetrack, MS ...... 
Racetrack Towhead, MS ... 
False Point, LA .......... 
Marshall Cutoff, LA ...... 
Below Grand Gulf, MS .... 
Fritz Island, LA .......... 
330 L 
347 R 
352 
358 
379 
386 
388 
389 
394 
405 
410 
416 
430 
431 
441 
448 
399 
338 
L
R
R
L
R
L
R
R
R
L
L
R
R
R
L
R 
1,532 33,159 5,775 13,553 38,500 
(3) 
640 
-- 
750 -- 
-- .- 
-- 
--
850 
9,128 
-- 
-- 
-- 1,430,475 
(270.92 Miles) 
-- 4,306 
-- 640 
-- 5,351 
-- 12,225 
-- 14,330 
-- 3,661 
-- 10,917 
-- 14,049 
-- 6,029 
-- 8,640 
-- 9,010 
-- 8,256 
-- 12,619 
-- 10,880 
-- 5,675 
-- 5,166 
-- 3,575 
-- 4,160 
585 
586 
588 
593 
596 
598 
601 
611 
615 
L
L
R
L
L
R
L
L
L 
0i 
5,477 
-- 
--. 
4,820 
12,500 
23,400 
29,245 
6,980 
16,515 
18,185 
25,195 
10,910 
MI, 
M 1 CI, 
C
C) 
C,, 
0:

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares) 1 Feet) (Squaruesa)r1 es Sares) Feet) Feet) 
Forest Home Towhead, LA 
Willow Cutoff, LA ........ 
Arcadia Point, MS ........ 
Cottonwood Bar, MS ...... 
Point Lookout, LA ........ 
Ajax Bar, MS ............ 
Ben Lomond, MS ......... 
Baleshed Ldg., MS ....... 
Wilson Point, LA ......... 
Corregidor, MS .......... 
Carolina, AR ............ 
Cracraft Lower, AR ....... 
Cracraft, AR ............ 
Leota, MS .............. 
Island 86, AR ........... 
Seven Oaks, AR .......... 
Walnut Point, MS ........ 
Anconia Chute, AR ....... 
Refuge, MS ............. 
Island 84, AR ........... 
Leland Bar, AR-MS ....... 
Leland Neck, AR-MS ...... 
Tarpley Cutoff, MS-AR .... 
Island 82-Miller Bend, 
AR-MS ............... 
Ashbrook-Miller Bend, 
AR-MS ............... 
Ashbrook Cutoff, MS ...... 
Chicot Ldg., AR .......... 
Catfish Point, MS ........ 
Below Prentiss, MS ....... 
Malone Field, AR ......... 
Terrene, MS ............ 
White River Landing, AR .. 
Montgomery Towhead, AR.. 
Victoria Bend, AR ........ 
449 
462 
470 
471 
478 
482 
488 
493 
500 
505 
509 
510 
513 
514 
520 
523 
525 
527 
528 
532 
538 
540 
540 
L
R
L
R
R
L
L
L
R
L
L
R
R
L
R
R
L
R
L
L
R
L
R 
6,402 
4,673 
2,500 
4,502 
1,905 
(-780) 
--
--. 
--. 
--. 
--. 
-- 
10,976 
4,275 
9,463 
2,406 
2,751 
28,152 
24,667 
15,101 
6,092 
6,730 
2,897 
9,614 
3,809 
7,571 
17,067 
5,754 
4,725 
4,604 
15,125 
6,485 
16,118 
4,315 
10,478 
544 R&L -- 13,646 
547 
549 
564 
571 
580 
585 
590 
591 
592 
596 
L&R 
L
R
L
R
R
L
R
R
R 
13,015 
8,728 
17,451 
5,290 
7,813 
7,549 
7,921 
2,201 
6,071 
5,033 
0
O
O
O
O
0

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maint'nance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares) Feet) Feet) 
Smith Point, MS ......... 
Island 70, MS ........... 
Total dikes, 
Vicksburg District, 
Mississippi River ....... 
600 L 
608 L
R
R
R
R
R 
-- -- -- -- -- -- -- 7,617 
-- -- -- -- -- -- -- 21,435 
30,570 
(5.79 Miles) 
-- 482,434 
(91.37 Miles) 
Miles 
Above 
Mouth 
ARKANSAS RIVER4 
Standard revetment: 
Menard Bend, AR ........ 
Como, AR .............. 
Morgan Bend, AR ........ 
Yancopin, AR ........... 
Total standard revetment, 
Arkansas River ........ 
Dikes: 
Hopedale Cutoff, AR ...... 
Morgan Bend, AR ........ 
Fletcher Bend, AR ........ 
Total dikes, Arkansas 
River ................ 
RED RIVER5 
Standard revetment: 
Dupre, LA .............. 
Bringol, LA ............. 
Egg Bend, LA ........... 
Cologne Bend, LA ........ 
Roxana, LA............ 
31 
34 
36 
24 
30 
36 
39 
L
R
L
R
R
L
R 
-- -- -- -- -- -- -- 11,770 
-- -- -- -- -- -- -- 11,720 
-- -- -- -- -- -- -- 5,250 
-- -- -- -- -- -- -- 2,800 
-- -- -- -- -- -- -- 31,540 
(5.97 Miles) 
-- -- -- -- -- -- -- 1,848 
-- -- -- -- -- -- -- 3,658 
-- -- -- -- -- -- -- 2,187 
H 
Cl) 
C) 
0
H
l1 
H 
-- 7,693 
(1.46 Miles) 
69 
73 
75 
77 
83 
2,690 
4,000 
2,400 
650 
3,325

TABLE 42-I 
(Continued) 
BANK REVETMENTS AND DIKES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)1 Feet) Feet) 
Ryland, LA ............. 88 R -- -- -- -- -- -- -- 3,925 
Whittington, LA ......... 89 R -- -- -- -- -- -- -- 2,900 
Smith, LA .............. 91 R -- -- -- -- -- -- -- 2,700 
Latanier, LA ............ 93 R -- -- -- -- -- -- -- 2,460 
Hudson, LA ............. 99 R -- -- -- -- -- -- -- 1,458 
Robert, LA ............... 102 R -- -- -- -- -- -- -- 5,500 
Alexandria Front, LA ..... 105 R -- -- -- -- -- -- -- 5,280 
Callahan, LA ............ 110 R -- -- -- -- -- -- -- 4,000 
Cotton, LA .............. 116 R -- -- -- -- -- -- -- 14,700 
Rapides, LA ............. 119 R -- -- -- -- -- -- -- 1,030 
Boyce, LA .............. 125 R -- -- -- -- -- -- -- 4,548 
Total standard revetment, 
Red River ............-- -- -- -- -- -- -- 61,566 
(11.66 Miles) 
Dikes 6: 
Choctaw Bayou Bend, LA .. 71 R -- -- -- -- -- -- -- 2,000 
Bringol (Egg Bend), LA .... 73 R -- -- -- -- -- -- -- 2,477 
Egg Bend, LA ........... 75 R -- -- -- -- -- -- -- 900 
Cologne Bend, LA ........ 77 R -- -- -- -- -- -- -- 1,850 
Echo, LA ............... 78 R -- -- -- -- -- -- -- 1,900 
Richardson, LA .......... 79 R -- -- -- -- -- -- -- 2,700 
Alexandria, LA .......... 105 R -- -- -- -- -- -- (Rock groin) 270 
Bertrand, LA ............ 122 R -- -- -- -- -- -- -- 7,630 
Total dikes, Red River .... -- -- -- -- -- -- -- 19,727 
(3.74 Miles) 
1. Gross squares articulated concrete mattress (100 square feet). 
2. Contains 7,814 linear feet of trenchfill revetment (stone). 
3. Linear feet of dike on which repairs were made. 
4. See report on Arkansas River and tributaries, AR and OK, under Little Rock District. 
5. Mileages based on 1967 hydrographic survey. 
. Includes all types of dikes and retards. 
i o 
EP 
h7 0
0
U) 
O
O
O
L1: 
O0
0

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
MISSISSIPPI RIVER 
Standard revetment: 
Big Island, AR ........... 
Scrubgrass Bend, AR ...... 
Henrico, AR ............. 
Cessions Towhead, AR ..... 
Island 67, MS ........... 
Island 68 Bar-- 
Knowlton, AR .......... 
Ludlow, AR ............. 
Rescue Land, AR-MS ...... 
Fair Landing, AR ........ 
Burke Landing, MS ....... 
Island 62, AR ........... 
Island 63, MS ........... 
Island 63 Bar, MS ........ 
Oldtown Bend, AR ........ 
Horseshoe, MS .......... 
Westover, AR ........... 
Delta-Friars Point, MS .... 
Helena, AR ............. 
Trotters Landing, MS ..... 
Flower Lake, MS ......... 
St. Francis, AR .......... 
Harbert Point, MS ........ 
Walnut Bend, AR ........ 
Mhoon Bend, MS ......... 
Peters, AR .............. 
Commerce, MS .......... 
Porter Lake, AR ......... 
Pickett, MS-AR ......... 
Seyppel, AR............. 
Norfolk-Star, MS ......... 
Cow Island Bend, AR ..... 
598 
600 
606 
615 
621 
622 
626 
629 
632 
637 
638 
639 
639 
644 
647 
650 
665 
660 
665 
667 
672 
675 
680 
685 
692 
695 
700 
703 
709 
711 
714 
R
R
R
L
L
R
R
L
R
L
R
L
L
R
L
R
L
R
L
L
R
L
R
L
R
L
R
R
R
L
R 
850 
2,910 
4,630 
4-- 
0
0
-- 
-- 
06 
-- 
06 
7,806 
06 
.. 
3,03 
.. 
-- 
-- 
-- 3 
-- 3,905 
-- 7,315 
-- 33,310 
-- 11,465 
-- 9,630 
-- 26,710 
-- 10,390 
-- 27,020 
-- 25,690 
-- 19,070 
-- 9,030 
-- 11,514 
-- 3,795 
-- 26,860 
-- 16,385 
-- 15,640 
-- 30,090 
-- 36,460 
-- 48,970 
-- 16,385 
-- 24,663 
-- 9,065 
-- 31,070 
-- 35,828 
-- 33,760 
-- 29,085 
-- 34,155 
-- 12,575 
-- 4,630 
-- 35,582 
-- 22,274 
H
r 
CI) 
C
M 1 
0z

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
Cow Island Bend 
(Upper), TN............. 
Coahoma, TN ........... 
Ensley, TN ............. 
Dismal Point, AR ......... 
Bauxippi-Wyanoke, AR .... 
Presidents Island, TN ..... 
Hopefield Point, AR-TN .... 
Loosahatchie-Memphis, 
TN .................. 
Loosahatchie Bar, TN ..... 
St. Clair, AR ............ 
Island 40, TN-AR ........ 
Brandywine, AR-TN ...... 
Shelby Forest, TN ........ 
Dean Island, AR ......... 
Cedar Point-Densford, 
TN .................. 
Chute of Island 35, TN .... 
Lookout Bar, TN ......... 
Lookout, TN ............ 
Sunrise Towhead, TN ..... 
Lower Bullerton, AR ...... 
Kate Aubrey Towhead- 
Island 30, TN .......... 
Osceola, AR ............. 
Osceola, AR ............. 
Ashport-Keyes Point, TN ... 
Kate Aubrey, TN ......... 
Island 26, TN ........... 
Bend of Island 25, TN ..... 
Barfield, AR ............ 
Obion-Tamm, TN ......... 
Huffman-Hickman, 
AR-TN ................ 
Heloise, TN ............. 
716 
717 
723 
724 
730 
733 
736 
737 
740 
742 
744 
750 
753 
756 
759 
764 
772 
774 
776 
782 
786 
786 
786 
791 
793 
798 
803 
808 
819 
R
L
L
R
R
L
R
L
R
R
R
R
L
R
L
R
R
R
R
R
R
R
R
L
R
R
L
R
L 
6,853 
9,270 
44,026 
7,200 
24,530 
12,755 
10,360 
31,293 
2,070 
2,9302 
30,750 
18,010 
9,550 
7,555 
5,405 
--. 
93--5 
935 
--. 
110 
-- 
--. 
2,599 
826 R 
831 L 
14,769 
--. 
-- 20,190 
-- 30,400 
-- 2,9902 
-- 5,005 
-- 16,995 
-- 28,350 
-- 30,808 
-- 1,3503 
-- 5,823 
-- 44,232 
-- 2,500 
-- 15,690 
-- 31,565 
-- 52,335 
-- 51,321 
-- 26,984 
-- 12,935 
o 
ro O
O0
O
O
y
O
pA 
t! 
O
0
0
O
0d 
m
m6

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)' Feet) Feet) 
Island 18, MO ........... 
Linwood Bend, TN ........ 
Blaker Towhead, TN ...... 
Bells Point, MO .......... 
Gayoso-Caruthersville, 
MO .................. 
Island 15, TN ........... 
Hathaway Landing, TN .... 
Robinson Bayou, MO ...... 
Fritz Landing, TN ........ 
Lee Towhead, MO ........ 
Bend of Island 14, TN ..... 
Above Lee Towhead, TN ... 
Little Cypress, MO ....... 
Merriwether-Cherokee, 
TN .................. 
Linda, MO............... 
Below Toney's Towhead, 
TN .................. 
Toney's Towhead, 
KY-TN ............... 
Kentucky Point, KY ....... 
New Madrid Bar, KY ...... 
New Madrid Bend, MO .... 
La Forge, MO ........... 
Slough Landing Neck, 
TN-KY ............... 
Winchester Towhead, 
M O .................. 
Island 9, KY-TN ......... 
Milton Bell, MO ......... 
Chute of Island 8, KY ..... 
Bend of Island 8, MO ..... 
Island 8, KY ............ 
Hickman-Reelfoot, KY ..... 
Beckwith Bend, MO ...... 
836 
841 
845 
845 
848 
851 
852 
852 
857 
859 
859 
861 
864 
R
L
L
R
R
L
L
R
L
L
L
L
R 
2,070 
2,540 
--
.- 
--. 
90 
5-- 
06
-- 
6,549 
--. 
-- 
-- 
25 
7,237 
869 L 
876 R 
879 L 
882 
887 
888 
889 
892 
L
L
R
R
R 
4,548 
2,550 10 06 
899 L 
900 
905 
908 
913 
914 
914 
919 
924 
R
L
R
L
R
R
L
R 
6,910 
--. 
10 
-- 
-- 
24,240 
14,850 
18,562 
5,420 
25,600 
3,630 
1,000 
22,630 
15,670 
9,640 
12,050 
4,943 
40,140 
-- 41,058 
-- 11,950 
-- 20,895 
-- 13,640 
-- 7,960 
-- 16,825 
-- 43,262 
-- 24,930 
-- 37,520 
5,540 
33,585 
16,600 
12,620 
18,375 
18,515 
43,359 
14,588 
06
-- 
C,' 
H Cl) 
u, 
CI 
UI 
U, IU,

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares) 1 (Squares)' Feet) Feet) 
Williams, KY............ 
Wolf Island, KY .......... 
Columbus, KY........... 
Belmont, MO ............ 
Island 3 and 4, KY ...... . 
Campbell, KY ........... 
Pritchard, MO ........... 
Mayfield Creek, KY ....... 
Wickliffe, KY ............ 
Cache-Cairo, IL 
(Ohio River) ........... 
Total revetment, 
Memphis District, 
Mississippi River ....... 
Dikes: 
Henrico, AR ............. 
Below Knowlton, AR ...... 
Island 67, MS ........... 
Below Ludlow, AR ........ 
Sunflower, AR ........... 
Island 64, AR ........... 
Island 62, AR ........... 
Island 63 Bar, MS ........ 
Island 63, MS ........... 
Kangaroo Point, AR ....... 
Friars Point, MS ........ . 
Montezuma Bar, MS ...... 
Montezuma Towhead, AR .. 
Prairie Point, AR ......... 
Flower Lake, MS ......... 
St. Francis Towhead, MS... 
Below Walnut Bend, AR ... 
Bordeaux Point, MS ...... 
927 
934 
937 
938 
940 
943 
948 
949 
953 
L
R
L
R
R
L
R
L
L 
958 R 
3,570 
-- 
0-- 16,679 
-- 
1,903 
--
-- 
10,015 
19,205 
7,395 
5,785 
19,970 
6,865 
15,045 
8,935 
8,455 
-- -- -- -- -- -- -- 26,152 
26,965 
(5.11 Miles) 
603 
616 
621 
624 
627 
630 
638 
639 
640 
649 
652 
657 
656 
668 
668 
671 
676 
681 
R
R
L
R
L
R
R
L
L
R
L
L
R
R
L
L
R
L 
2,770 
..-- 
-- 
-- 
-- 
-- 
-- 
310 34,321 
470 
-- 
--. 
--. 
-- 
24,722 
(5) 
1,625 
300 
-- 
(4) 
-- 1,966,365 
(372.42 Miles) 
-- 9,080 
20,670 
4,320 
5,040 
5,520 
7,330 
23,180 
2,600 
5,640 
5,730 
6,870 
15,240 
3,450 
10,391 
11,060 
3,380 
6,420 
5,780 
03 0n 
O0
O
O
IU) 
OO 
H
Lr 
0: 
0
0
U) 
0
O
O 
d

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Continued) (FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)l Feet) Feet) 
Peters, AR .............. 693 R -- -- -- 970 -- - -- 7,830 
Commerce, MS .......... 694 L -- -- -- -- -- -- -- 10,745 
Basket Bar, AR .......... 696 R -- -- -- -- -- -- 5,560 
Buck Island, MS ......... 700 L -- -- -- -- -- -- -- 4,705 
Porter Lake, AR ......... 701 R -- -- -- 4,100 - -- - 22,315 
Pickett, MS ............. 704 L -- -- -- 1,145 -- -- - 7,180 
Seyppel, AR ............. 706 R -- -- -- -- -- - - 12,250 
Cat Island, AR .......... 710 R -- - -- -- -- - - 15,590 
Coahoma, TN ........... 718 L -- -- -- 1,465 -- - - 4,640 
Armstrong, AR-TN ....... 720 R -- -- -- 1,450 -- -- - 18,690 
Dismal Point, AR. ........ 724 R -- -- -- 1,500 -- -- - 25,510 
Hopefield Point, AR ....... 736 R 4,020 -- -- -- -- -- -- 5,350 
Memphis Front, TN ....... 736 L -- -- -- -- -- -- -- 6,300 
cO Robinson Crusoe, TN ...... 738 R -- -- -- 1,200 - -- -- 21,939 
Loosahatchie Bar, TN ..... 739 R -- -- -- -- - -- -- 3,950 
Above Loosahatchie, TN ... 742 L -- -- -- 300 -- -- -- 8,990 
Redman Point, AR ........ 743 R -- -- -- -- - -- -- 7,750 
Randolph Point, TN ....... 747 L -- -- -- -- - - -- 16,740 
Poker Point, AR .......... 748 R -- -- -- 1,600 -- -- -- 8,050 
Corona Bar, TN-AR ....... 755 R -- -- -- 400 -- -- -- 8,430 
Densford, TN ............ 757 L -- -- -- 400 -- -- -- 7,780 
Cedar Point, TN ......... 759 L -- -- -- -- -- -- -- 2,890 
Below Richardson 
Landing, TN........... 767 L -- -- -- -- 5,950 
Lookout, TN-AR ......... 771 R 7,327 -- -- -- -- -- - 12,865 
Plum Point, TN .......... 784 L -- -- -- 2,000 -- -- -- 9,695 
Lake Neark, AR ......... 786 R -- -- -- -- -- -- -- 2,545 
Island 30 ............... 787 R -- -- -- -- -- -- - 3,010 
Kate Aubrey, TN ......... 791 R -- -- -- 600 -- -- -- 11,270 
Keyes Point, TN ......... 791 L -- -- -- 1,500 -- -- -- 24,690 
Ashport-Goldust, TN-AR ... 795 R -- -- -- -- -- -- -- 17,330 
Forked Deer, TN ......... 798 L -- -- -- 300 -- -- -- 8,550 
Island 25, AR ........... 804 R -- - -- -- -- -- -- 5,450 
Nebraska Point, TN ....... 808 L -- -- -- -- - -- -- 12,149 
Below Tamm Bend, TN .... 813 L -- -- -- -- -- -- -- 8,300 
Wrights Point, AR ........ 820 R -- -- -- 600 -- -- -- 34,775 
r 
I 
I r 
i C 
t 
) C 
)) 
m 
1
1 Z 
) 
$ 
)

TABLE 42-J BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(Continued) (FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares)1 Feet) Feet) 
Island 21, Chute, TN ...... 824 L -- -- -- -- -- -- -- 3,170 
Head of Island 21, TN ..... 828 L -- -- -- -- -- -- -- 5,460 
Island 20, MO-TN ......... 831 R -- -- -- -- -- -- -- 18,139 
Island 18, TN ........... 837 L -- -- -- -- -- -- -- 8,670 
Tennemo, TN ........... 842 L -- -- -- -- -- -- -- 8,240 
Blaker Towhead, TN ...... 843 L -- -- -- 4,000 -- -- -- 4,070 
Caruthersville-Linwood 
Bend, MO ............. 844 R -- -- -- 2,000 -- -- -- 28,630 
Opposite Carthersville, TN . 846 L 3,300 -- -- -- -- -- -- 3,300 
Sandy Hook, TN ......... 850 R -- -- -- -- -- -- -- 2,350 
Island 15, TN ........... 851 L -- -- -- 500 -- -- -- 8,830 
Robinson Bayou, MO ...... 853 R -- -- -- 800 -- -- -- 10,768 
Hathaway, TN ........... 854 L -- -- -- 850 -- -- -- 27,355 
Island 15 Neck, TN ....... 854 L -- -- -- -- -- -- -- 21,100 
Above Lee Towhead, TN ... 859 L -- -- -- -- -- -- 1,300 
Below Cherokee, TN ...... 866 L -- -- -- -- -- -- -- 6,230 
Stewart Towhead, MO ..... 871 R -- -- -- -- -- -- -- 18,290 
Ruddles Point, MO ....... 874 R -- -- -- -- -- -- -- 8,130 
Island 11, MO............ 882 R -- -- -- 1,150 -- -- -- 14,330 
New Madrid Bend, MO .... 887 R -- -- -- -- -- -- -- 1,715 
Kentucky Point, KY ....... 887 L -- -- -- -- -- -- -- 11,550 
Morrison Towhead, MO .... 890 R -- -- -- -- -- -- -- 1,070 
Hotchkiss Bend, MO ...... 895 R -- -- -- -- -- -- -- 6,583 
Below Island 9, TN ....... 901 L -- -- -- 1,180 - -- -- 18,859 
Donaldson Point, MO ..... 905 R 5,300 -- -- 200 -- -- -- 16,435 
Island 9, KY ............ 906 L -- -- -- -- -- -- -- 7,0105 
Island 7 - Island 8, MO-KY . 917 R 14,795 -- -- -- -- -- -- 14,795 
Below Williams, KY ....... 925 L 2,160 -- -- -- -- -- -- 2,160 
Moore Island, KY-MO ..... 929 R 3,240 4,225 -- -- -- -- -- 7,925 
Above Williams, KY ....... 930 L -- -- -- -- -- -- -- 1,150 
Campbell, KY ........... 942 L -- -- -- -- -- -- -- 2,610 
i 
ro 
0IO
0
0
I0
0
0
O
m
m

TABLE 42-J 
(Continued) 
BANK REVETMENTS AND DIKES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Operations This FY Nonop- Opera- 
Construction erative tive 
Above New Work Since Thru 
Head Bank Exten- Prior This 
of R sion Lap Reinforcement FY FY 
Passes or (Linear (Linear (Linear Maintenance (Linear (Linear 
Location (Miles) L Feet) Feet) (Squares)1 Feet) (Squares)1 (Squares) Feet) Feet) 
Pritchard, MO ........... 944 R -- -- -- 1,800 -- -- -- 9,390 
Island 1, KY ............ 948 L 2,085 2,110 -- -- -- -- -- 17,345 
Total dikes 
Memphis District, 
Mississippi River ....... 41,697 6,805 -- 37,535 -- -- -- 858,423 
(7.90 Miles) (162.58 Miles) 
Gross squares articulated concrete mattress (100 square feet). 
Changed to correct previous errors. 
Lumber mattress revetment. 
Rock Groins. 
Linear feet of triangular frame retards and pile dikes. 
Linear feet of dike on which repairs were made. 
Riprap paving only. 
O1 
C,' 
C71 
1. 
2. 
3. 
4. 
5. 
6. 
7. 
CI) 
rI) 
H
CI 
Cl) 
M 1 
0

TABLE 42-K PROJECT LEVEES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Total rently System Com- rently System plete ren 
Authorized Place Thru Under When Built plete Under When Built Thru Un 
for This This This Con- Com- This This Con- Com- This This Co 
Location System FY FY FY struction pleted FY FY struc 
Main Stem Levees 
Mississippi River Levees 
Fifth Louisiana Levee District .. 
Levees .............. 
Old River structures and 
levees ................... 
Atchafalaya Basin Levee 
District .................. 
Levees ................... 
Morganza structure and 
levee ................... 
,p Morganza forebay levee ...... 
Port Allen lock ............ 
Lafourche Basin Levee District 
Levees ................... 
Plaquemines West Levee 
District Levees ............ 
Buras Levee District ......... 
Levees ................... 
Empire lock .............. 
Baton Rouge front levees ...... 
Pontchartrain Levee 
(16.8) (16.8) (-) (10.7) 
15.5 15.5 -- 9.4 
1.3 1.3 - 1.3 
(126.3) (126.3) (1.8) (102.2) 
118.7 118.7 1.8 94.6 
0.8 
6.7 
0.1 
0.8 -- 
6.7 -- 
0.1 -- 
31.7 61.7 6.1 30.2 
37.9 37.9 -- 28.7 
34.1) (34.1) (5.5) (30.2) 
34.0 34.0 5.5 30.1 
0.1 0.1 -- 0.1 
2.1 2.1 -- 0.9 
District .................. (124.9) (124.9) (-) (91.1) 
Levees ................... 110.8 110.8 -- 77.0 
Bonnet Carre' guide levees ... 11.3 11.3 -- 11.3 
Bonnet Carre' forebay levee .. 1.3 1.3 -- 1.3 
Bonnet Carre' structure ..... 1.5 1.5 -- 1.5 
East Jefferson Levee District 
Levees ................... 
West Jefferson Levee District .. 
Levees .................. 
Floodwalls ................ 
Harvey Canal Lock ......... 
11.6 
(20.0) 
19.8 
0.1 
0.1 
11.6 -- 10.8 
(20.0) (1.0) (16.9) 
19.8 1.0 16.7 
0.1 -- 0.1 
0.1 -- 0.1 
(--) (--) (-) (-) 
(--) (5.3) (--) (1.0) 
-- 5.3 -- 1.0 
(-) (15.5) 
-- 15.5 
-- 18 
(--) (118.7) 
-- 118.7 
0.8 -- 
6.7 -- 
0.1 -- 
18.0 
2.0 
(3.9) 
3.9 
(3.8) 
3.8 
(--) 
--. 
-- 
0.1 
-- ) 
-- 
-- 0.1 
(-) (-) 
-- 61.7 
-- 37.9 
(-) (34.0) 
-- 34.0 
rtly 
der 
tion 
tion 
LA 
(--) (15.5) (-) 
-- 15.5 - 
-- - -- 0 
(-) (118.7) (-) 
-- 118.7 -- 
- -- I 
61.7 
(--) 
-- 
37.9 
(34.0) 
34.0 
- 
-- -- -- -- -- -- -- -- 
-- -- -- -- 2.1 -- 2.1 -- 
(4.'1 (-) (-) (-) (110.8) (--) (110.8) (-) 
4.7 -- -- -- 110.8 -- 110.8 -- 
-- -- -- -. 11.6 -- 11.6 -- 
(--) (--) (-) (-) (19.9) (--) (19.9) (-) 
-- -- - -. 19.8 -- 19.8 -- 4 
-- -- -- -- 0.1 -- 0.1 -- O
- - 
0
0
BJ 
6
3 
(3 
3

TABLE 42-K 
(Continued) 
PROJECT LEVEES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Corn- Cu 
in Total rently System Corn- rently System plete rent 
Authorized Place Thru Under When Built plete Under When Built Thru Und 
for This This This Con- Com- This This Con- Com- This This Coi 
Location System FY FY FY struction pletedl FY FY struction pleted FY FY struct 
Orleans Levee District........ 
Left descending, east bank ..... 
Levees ................... 
Floodwalls ................ 
IHNC lock ................ 
Right descending, west bank . . 
Levees ................... 
Algiers Canal lock .......... 
Lake Borgne Basin Levee 
District Levees ............ 
Grand Prairie Levee District 
P. Levees .................. 
Total Mississippi River ..... 
Other Levees Included in 
Mainstem Atchafalaya Basin 
Atchafalaya River and 
Bayou des Glaises .......... 
East Bank Atchafalaya River.. 
Bayou des Glaises .......... 
West bank Atchafalaya River.. 
Simmesport Ring ........... 
Melville Ring............. 
Krotz Springs Ring ......... 
Mansura Hills to Hamburg ... 
West protection levee, Hamburg 
to Berwick drainage canal via 
Calumet ................. 
Levees west of Berwick, Berwick 
drainage canal to Charenton 
drainage canal ............ 
Morganza upper guide levee ... 
(27.2) 
(13.3) 
4.6 
8.6 
0.1 
(13.9) 
13.8 
0.1 
11.6 
(27.2) (0.2) (21.6) 
(13.3) (0.2) (9.4) 
4.6 0.1 0.7 
8.6 0.1 8.6 
0.1 - 0.1 
(13.9) (-) (12.2) 
13.8 -- 12.1 
0.1 - 0.1 
11.6 - 
(-) 
(-) 
((-)-) 
-- 
(--) 
(--) 
(-) 
(--) (--) 
(--) (--) 
(-) (--) 
--.-- 
--.-- 
11.6 
37.4 37.4 - 28.4 
511.6 511.6 14.6 383.3 
(148.4) (148.4) (-) (143.9) 
52.5 52.5 - 52.5 
7.9 7.9 - 7.9 
60.1 60.1 - 55.6 
1.6 1.6 - 1.6 
4.1 - 
1.7 - 
20.5 - 
36.7 
(-) 
- 
1.0 -- - 
1.0 -- 1.1- 
(-) 
(-) 
-- 
-- 
-- 
-- 
(18.4) 
(4.6) 
4.6 
(13.8) 
13.8 
-- 
-- 11.6 
-- 37.4 
-- 479.6 
(-)
-- 
-- 
-- -- 
(-) (-) (-) (148.4) 
-- -- -- 52.5 
-- -- -- 7.9 
-- -- -- 60.1 
-- -- -- 1.6 
-- -- -- 4.1 
-- -- -- 1.7 
-- -- - 20.5 
4.1 
1.7 
20.5 
128.7 0.7 90.9 
56.5 4.1 13.7 
8.9 - 8.9 
9.2 
3.4 
-- 128.7 
-- -- -- -- 56.5 
-- -- -- -- 8.9 
r- 
;ly 
er 
1- 
tion 
(--) (18.4) (--) 
(--) (4.6) (-) 
-- 4.6 -- 
(--) (13.8) (--) 
-- 13.8 -- 
-- ----.. 
-- 11.6 -- 
-- 37.4 -- 
-- 479.6 -- 
(-) (148.4) (-) 
-- 52.5 -- - 
-- 7.9 -- 
-- 60.1 -- 
-- 1.6 -- 
-- 4.1 -- 
-- 1.7 -- 
-- 20.5 -- 
0.7 128.4 -- 
-- 56.5 -- 
-- 8.9 -- 
In error last year

PROJECT LEVEES: NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Location 
East Protection levee, Morganza 
to Cutoff Bayou, including 
19.5 miles of Morganza lower 
guide levee ................. 
Total Atchafalaya Basin..... 
Total-Main Stem Leaves....... 
Levees and Floodwalls Berm Surfaced Roads on Levees 
(Miles) (Miles) (Miles) O 
Built to 
Approved Total 
Total G etiod Cur- In Cur- In Com- Curin 
Total rently System Com- rently System plete rently 
Authorized Place Thru Under When Built plete Under When Built Thru Under 
for This This This Con- Corn- This This Con- Corn- This This Con- 
System FY FY FY struction pleted1 FY FY struction pleted FY FY struction 
106.7 106.7 3.3 84.3 4.0 .- -- -- -- 105.0 3.3 82.0 - 
449.2 449.2 8.1 341.7 16.6 -- -- - -- 447.5 4.0 _30 . 
960.8 960.8 22.7 725.0 53.3 10.1 - 1.1 -- 927.1 4.0 930.82 O 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
Lake Pontchartrain, LA ........ (17.4) (17.4) (-) (17.4) (-) 
Item A levees .............. 5.0 5.0 - 5.0 -- 
, Item B levees .............. 10.1 10.1 - 10.1 -- 
Item C levees .............. 2.3 2.3 - 2.3 -- 
TPot al Tributary Levees in MR&T 
Project .................... 17.4 17.4 - 17.4 -- 
(-) (-) (-) (-) (17.4) 
-- -- -- -- 5.0 
-- -- -- -- 10.1 
-- -- - -- 2.3 
-- - -. - 17.4 
(-) (17.4) (-) 
-- 5.0 - 
-- 10.1 - 
-- 2.3 - 
- 17.4 - 
GRAND TOTAL ............. 978.2 978.2 22.7 742.4 53.3 10.1 - 1.1 -- 944.5 
1. Figures indicate landside seepage berms only. 
2 In error last year 
TABLE 42-K 
(Continued) 
4.0 921.2-' 
0
O
0
m

TABLE 42-L PROJECT LEVEES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm1 Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Total rently System Com- rently System plete ren 
Authorized Place Thru Under When Built plete Under When Built Thru Und 
for This This This Con- Com- This This Con- Com- This This Co 
Location System FY FY FY2 struction pleted3 FY4 FY struction pleted FY FY struc
lrtly 
ler 
ntion 
MAIN STEM LEVEES 
Mississippi River Levees 
East bank in Mississippi ...... 
Greenville Harbor dikes ...... 
West bank in Arkansas ....... 
West bank in Louisiana 
(above Red River) .......... 
Total Mississippi River 
Levees ................ 
178.34 178.3 -- 109.1 
7.8 7.8 -- 7.8 
75.6 75.6 -- 52.4 
-- 156.9 
2.6 61.3 
198.7 198.7 -- 67.1 4.6 
460.4 460.4 -- 236.4 
Other Levees Included in Main 
p Stem 
Lower Red River-South Bank 
C Red River levees ........... (59.2) (59.2) (--) (59.2) 
Hotwells to Moncla, LA, 
levees .................. 59.2 59.2 -- 59.2 
Arkansas River, South Bank .. 85.4 85.4 -- 85.4 
Total Other Levees Included in 
Main Stem ................. 144.6 144.6 -- 144.6 
Total--Main Stem Levees .... 605.0 605.0 -- 381.0 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
Arkansas River, North bank .. 61.55 
Red River Backwater Levees .. 263.6 
56.2 -- 56.2 
165.1 4.6 161.86 
-- 119.3 
-- 53.1 
-- 174.2 
1.2 75.4 
93.3 -- 69.6 2.3 197.8 
7.2 311.5 0 242.0 
(-) (-) (-) (-) 
-- 24.7 -- 24.7 
-- 24.7 -- 24.7 
7.2 336.2 0 266.7 
-- 8.3 
7.1 -- 
-- 8.3 -- -- 
3.5 447.4 
(-) (59.2) 
- 59.2 
-- 84.1 
-- 143.3 
3.5 590.7 
-- 47.4 
- 249.0 
5.8 174.2 - 
-- 75.4 - 
-- 197.8 - 
5.8 447.4 - - 
(--) (59.2) (-) E 
-- 59.2 - 
-- 81.1 - 
5. 140.3 8 587.7 
U, 
0 
-- 47.4 - 
4.6 146.5 7.1

TABLE 42-L 
(Continued) 
PROJECT LEVEES: VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berml Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Total rently System Comrn- rently System plete ren 
Authorized Place Thru Under When Built plete Under When Built Thru Und 
for This This This Con- Comrn- This This Con- Com- This This Co 
Location System FY FY FY2 struction pleted3 FY4 FY struction pleted FY FY struc 
Yazoo River Basin ........... . (624.1) (357.2) (-) (211.8) (18.7) (--) (--) (--) (--) (624.1) (--) (333.6) (4. 
Headwater................ 527.5 305.6 - 160.2 18.7 -- -- -- -- 527.5 -- 294.6 4. 
Backwater ................ 96.6 51.6 - 51.6 -- -- -- -- -- 96.6 -- 39.0 - 
Total Tributary Levees in 
MR&T Project ........... . 949.2 578.5 4.6 429.8 25.8 8.3 -- 8.3 -- 920.5 4.6 527.5 11 
GRAND TOTAL ............. ... 1,554.2 1,183.5 4.6 810.8 33.0 344.5 0 275 3.5 1,511.2 10.4 1,115.2 11 
1. This tabulation does not include riverside berms which are considered an integral part of the levee section. Riverside berms will be constructed along with levee enlargements or seepage berm 
contracts. 
2. Levee that has adequate freeboard based on the refined 1973 MR&T project flood flow line for the Mississippi River. Levees with more than 2 feet of freeboard are considered adequate. 
S b ntt Ihna a l nin Drnt iir nl l dn itinb wn hih d t donrehr. 
3 . nu ject to cnange as pianning progresses. oees not inciuue exsung prsw nne etu 04. Includes 1.4 miles of concrete floodwall and 0.3 mile of levee on Vicksburg city front. 
5. Includes 5.3 miles for Gillett new levee. 
6. Reflects results of 1985 flowline reanalysis. 
Is 
r- 0 
r- PTJ 
tly 
der 
ntion 
3) 
.3 y 
.4 '
. 
.4 
I0 
0
0

TABLE 42-M PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm1 Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Total rently System Comrn- rently System plete ren 
Authorized Place Thru Under When Built plete Under When Built Thru Und 
for This This This Con- Comrn- This This Con- Com- This This Co 
Location System FY FY FY struction pleted FY FY struction pleted FT FY struc
lrtly 
ler 
ntion 
MAIN STEM LEVEES 
Mississippi River 
Mounds, IL ................ 
Mound City, IL ............. 
Cairo Drainage District ....... 
City of Cairo ............... 
Little River Drainage District .. 
Levee District No. 2, Scott 
County, MO .............. 
Levee District No. 3, Mississippi 
County, MO .............. 
St. Johns Levee and Drainage 
District .................. 
SSt. Francis Levee District 
of MO ................... 
City of Hickman, KY ......... 
Board of Levee Commissioners 
Fulton, County, KY ......... 
Reelfoot Levee District of Lake 
and Obion Counties, TN ..... 
Madrid Bend Levee District, 
Lake Co., TN .............. 
Lake County Levee and Drainage 
District .................. 
Dyer County Levee and Drainage 
District No. 1 ............. 
Tipton-Obion levee extension... 
St. Francis Levee District 
of AR .................... 
Helena Improvement District 
No. 1 .................... 
Cotton Belt Levee District 
No. 1 .................... 
3.9 3.9 -- 3.9 - 0.5 -- 0.5 -- 3.6 -- 3.6 -- 
2.7 2.7 -- 2.7 -- 2.5 -- 2.5 -- 1.1 -- 1.1 -- 
13.82 13.8 -- 13.8 -- 1.6 -- -- -- 8.5 -- 8.5 -- 
6.2 6.2 -- 6.2 -- 4.4 -- 2.0 -- 4.0 -- 3.5 -- 
19.3 19.3 -- 19.3 -- 9.7 -- 4.9 -- 19.3 -- 19.3 -- 
13.8 13.8 -- 13.8 -- 4.2 -- -- -- 13.8 -- 13.8 -- 
26.0 26.0 -- 26.0 -- 12.9 -- 4.9 -- 26.0 -- 26.0 -- 
59.03 58.7 -- 58.7 -- 9.2 -- - - 46.9 -- 46.1 -- 
55.7 55.7 -- 55.7 -- 23.0 -- 12.0 -- 55.1 -- 55.1 -- 
1.4 1.4 -- 1.4 -- -- -- -- -- 0.5 -- -- -- 
16.7 16.7 -- 16.7 -- 15.1 -- 11.4 -- 16.3 -- 16.3 -- 
4.5 4.5 -- 4.5 -- 0.6 -- 0.3 -- 4.5 -- 4.3 -- 
5.2 5.2 -- 5.2 -- -- -- -- -- 5.2 -- 5.2 -- 
15.9 
21.3 
6.5 
15.9 -- 15.9 
21.3 -- 21.3 
156.7 156.7 -- 153.2 
-- 9.1 -- 6.4 -- 15.9 -- 15.9 
1.3 -- 0.4 -- 21.3 -- 21.3 
-- -- -- -- 6.5 -- -- 
-- 84.7 1.4 83.2 -- 156.7 -- 156.7 
5.3 5.3 -- 5.3 -- 2.4 -- 2.4 -- 4.7 -- 4.2 -- 
23.9 23.9 -- 23.9 18.8 -- 18.8 -- 23.9 -- 23.9

TABLE 42-M 
(Continued) 
PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Laconia Drainage and Levee 
District Phillips County, AR .. 
Laconia Levee District No. 1 of 
Deshna County, AR ......... 
Laconia Circle Special Drainage 
District of Deshna 
County, AR ............... 
Yazoo-Mississippi Delta Levee 
District .................. 
Madrid Bend L.D., Fulton Co., 
KY ..................... 
F Birds Point-New Madrid setback 
ts levee .................... 
S Total Mississippi River ..... 
TOTAL MAIN STEM LEVEES .. 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
St. Francis River ............. 
East bank ................. 
West bank ................ 
Little River ................. 
East bank (left) ............. 
West bank ................. 
Elk Chute ................. 
West Basin and middle valley .. 
Lower White River ............ 
White River backwater levee ... 
Augusta to Clarendon ........ 
Clarendon levee ............. 
20.5 
18.1 
20.5 -- 
18.1 -- 
6.6 6.6 -- 
93.6 93.6 -- 
4.8 4.8 
35.3 
636.7 
636.7 
(308.2) 
159.5 
148.7 
(130.1) 
40.7 
35.1 
39.9 
14.4 
(95.6) 
40.2 
49.2 
6.2 
20.5 -- 11.5 
18.1 -- 12.6 
-- 11.5 -- 20.5 
-- 9.2 - 16.5 
-- 20.5 
-- 16.5 
6.6 
93.6 -- 87.3 -- 87.3 
4.8 
35.3 -- 35.3 
629.9 -- 625.9 
629.9 -- 625.9 
(302.9) -- (302.9) 
156.2 -- 156.2 
146.7 -- 146.7 
(130.1) -- (130.1) 
40.7 -- 40.7 
35.1 -- 35.1 
39.9 -- 39.9 
14.4 -- 14.4 
(85.9) -- (84.1) 
40.2 -- 40.2 
39.5 -- 39.5 
6.2 -- 4.4 
23.8 -- -- 
335.2 1.4 257.7 
335.2 1.4 257.7 
-- 93.6 
-- 4.8 
-- 35.3 
-- 604.5 
-- 604.5 
-- (301.0) 
- 156.7 
- 144.3 
- (128.9) 
- 40.7 
-- 35.1 
-- 39.7 
-- 13.4 
-- (88.0) 
-- 38.8 
- 49.2 
ritly 
der 
nation 
ro 
0
0
A -- 
0
-- 
-- 
-- 93.6 
- 4.8 
- 5 35.3 -- 
- 595.5 -" 0 
- 595.5 -- z 
(133.5) 
94.7 
38.8 
(94.5) 
40.1 
23.7 
17.3 
13.4 
(75.0) 
38.8 
36.2 
-. 
-a 
- U
-- 
-- 
Levees and Floodwalls Berm1 Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Total rently System Com- rently System plete ren 
Authorized Place Thru Under When Built plete Under When Built Thru Uni 
for This This This Con- Com- This This Con- Com- This This Co 
Location System FY FY FY struction pleted FY FY struction pleted FY FY stru

TABLE 42-M 
(Continued) 
PROJECT LEVEES: MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm1 Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and 
Section Total 
Total Cur- In Cur- In Comin 
Total rently System Com- rently System plete r 
Authorized Place Thru Under When Built plete Under When Built Thru U 
for This This This Con- Com- This This Con- Corn- This This 
Location System FY FY FY struction pleted FY FY struction pleted FY FY str 
Memphis Harbor ............. 10.5 10.5 -- 10.5 -- 7.0 4.4 7.0 -- 10.5 -- 10.5 
Total Tributary Levees in 
MR&T Project ............. 544.4 529.4 - 527.6 -- 7.0 4.4 7.0 528.4 -- 313.5 
GRAND TOTAL............... 1,181.1 1,159.3 - 1,153.5 -- 342.2 5.8 264.7 -- 1,132.9 -- 909.0 
1. Subject to change as planning progresses. 
2. Includes 5.1 miles of Cache River levee. This levee was enlarged to 1928 grades with Federal funds, but since that time has been classified as a secondary levee. 
3. Includes 12.1 miles of Farrenburg levee. This levee was enlarged to 1928 grades with Federal funds, but since that time has been classified as a secondary levee. 
2bv 
W) 
Curently 
nder 
Conuction 
-- 
-- U) 
UI) 
U) 
Cl) 
n
0
0

TABLE 42-N RECAPITULATION 
PROJECT LEVEE TABLES 42-K, -L, AND -M 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Total rently System Com- rently System plete ren 
Authorized Place Thru Under When Built plete Under When Built Thru Un 
for This This This Con- Com- This This Con- Com- This This Co 
Location System FY FY FY struction pleted FY FY struction pleted FY FY struc 
MAIN STEM LEVEES 
Mississippi River 
New Orleans District, 
Table 42-K. ............... 511.6 511.6 14.6 383.3. 
Vicksburg District, Table 42-L .. 460.4 460.4 -- 236.4 
Memphis District, Table 42-M .. 636.7 629.9 -- 625.9 
Total Mississippi River ...... 1,608.7 1,601.9 14.6 1,245.6 
Other Levees Included in Main 
Stem 
Atchafalaya Basin Floodway-- 
p NOD .................... 
Lower Red River-South Bank-- 
VXD .................... 
Arkansas River-South Bank-- 
VXD .................... 
Total Other Levees Included 
in Main Stem........... 
449.2 449.2 8.1 341.7 
59.2 59.2 -- 
36.7 
7.2 
43.9 
10.1 -- 1.1 
311.5 -- 242.0 
335.2 1.4 257.7 
658.8 1.4 500.8 
16.6 
59.2 
85.4 85.4 -- 85.4 
593.8 593.8 8.1 486.3 
Total Main Stem Levees .... 2,202.5 2,195.7 22.7 1,731.9 
-- 24.7 -- 24.7 
16.6 
60.5 
24.7 -- 24.7 
681.5 1.4 525.5 
-- 479.6 
3.5 447.4 
-- 604.5 
3.5 1,531.5 
-- 447.5 
-- 59.2 
-- 84.1 
-- 590.8 
3.5 2,122.3 
-- 479.6 -- 
5.8 447.4 -- 
-- 595.5 -- 
5.8 1,522.5 -- 
4.0 424.2 -- 
-- 59.2 -- 0 
-- 81.1 - 
4.0 564.5-- - 
9.8 2,087.0- -- 
TRIBUTARY LEVEES IN 
MR&T PROJECT 
Lake Pontchartrain, LA,--NOD .. 
Yazoo River Basin--VXD ....... 
Arkansas River-North Bank-- 
VXD ..................... 
Red River Backwater--VXD ..... 
St. Francis River--MD ......... 
Little River--MD ............. 
Lower White River--MD ....... 
17.4 
624.1 
61.5 
263.6 
308.2 
130.1 
95.6 
17.4 -- 17.4 
357.2 -- 211.8 
56.2 -- 56.2 
165.1 4.6 161.8 
302.9 -- 302.9 
130.1 -- 130.1 
85.9 -- 84.1 
-- -- -- -- -- 17.4 
18.7 -- -- -- -- 624.1 
7.1 
8.3 8.3 47.4 
249.0 
301.0 
128.9 
88.0 
-- 17.4 
-- 333.6 
-- 47.4 
4.6 146.5 
-- 133.5 
-- 94.5 
-- 75.0 
v In error last year 
ro 0
0I
M 
Lrtly 
der 
n- 
;tion 
-- y 
4.3 
-- n 
7.1 
-- 0 
-- --

TABLE 42-N 
(Continued) 
RECAPITULATION 
PROJECT LEVEE TABLES 42-K, -L, AND -M 
(FISCAL YEAR 1992) 
Levees and Floodwalls Berm Surfaced Roads on Levees 
(Miles) (Miles) (Miles) 
Built to 
Approved 
Grade and Total 
Total Section Cur- In Cur- In Com- Cu 
in Totl rently System Com- rently System plete rent 
Authorized Place Thru Under When Built plete Under When Built Thru Und 
for This This This Con- Com- This This Con- Com- This This Col 
Location System FY FY FY structioni pleted FY FY struction pleted FY FY struc 
Memphis Harbor--MD ......... 10.5 10.5 - 10.5 -- 7.0 4.4 7.0 -- 10.5 -- 10.5 
Total Tributary Levees in 
MR&T Project ............ 1511.0 1125.3 4.6 974.8 25.8 15.3 4.4 15.3 -- 1,463 4.6 858.4 11. 
Grand Total in Project ....... 3,713.5 3,321.0 27.3 2,706.7 86.3 696.8 5.8 540.8 3.5 3,588.6 14.4 2,945.4! 11.
rtly 
ler 
ntion 
4
4 
1 In error last year 
t3 
0i 
vs. 
0
I
o
^ 
1 
O1 
Nf 
iii 
H 
rr 
M 1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-0 CHANNEL IMPROVEMENTS: 
NEW ORLEANS DISTRICT 
(FISCAL YEAR 1992) 
Total 
In Complete 
System Built Thru Currently 
Year When This This Percent Under 
Location Initiated Completed FY FY Complete Construction 
(Miles) 
Bayou des Glaises diversion channel .............. 1938 6.0 -- 6.0 100 -- 
Bayous Rapides, Boeuf, and Cocodrie .............. 1946 92.6 -- 63.4 75 -- 
Charenton drainage and navigation canal .......... 1939 6.3 -- 6.3 100 -- 
Wax Lake Outlet ............................. 1938 15.7 -- 15.7 100 -- 
Atchafalaya Basin Floodway ................... 1933 244.2 -- 186.4 76 -- 
Morganza Floodway ........................... 1941 3.3 -- 3.3 100 -- 
Old River outflow channel ...................... 1956 8.3 -- 8.3 100 -- 
Old River inflow channel ....................... 1960 2.3 -- 2.3 100 -- 
Old River lock approach channels ................ 1961 2.2 -- 2.2 100 -- 
Baton Rouge Harbor (Devils Swamp) .............. 1958 2.5 -- 2.5 100 -- 
Teche-Vermilion Water Supply .................. 1977 6.3 -- 6.3 100 -- 
Old River Auxiliary Control Structure inflow channel . 1986 1.9 -- 1.9 100 -- 
Old River Auxiliary Control Structure outflow channel 1988 0.9 -- 0.9 100 -- 
Caernarvon Freshwater Diversion channel .......... 1988 1.7 -- 1.7 100 -- 
42-66

TABLE 42-P 
Total 
In Complete 
System Built Thru Currently 
Year When This This Percent Under 
Location Initiated Completed FY FY Complete Construction 
(Miles) 
BIG SUNFLOWER RIVER, 
ETC., MS 
Big Sunflower River .......................... 
Quiver River ................................ 
Deer Creek ................................ 
Steele Bayou ............................... 
Steele Bayou 1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 
M ain Canal ...................... .......... 
Main Canal 2 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 
BlackBayou .......................................... 
Big Sunflower River tributaries .................. 
Quiver River tributaries ....................... 
YAZOO BACKWATER 
Yazoo Backwater ............................. 
YAZOO BASIN HEADWATER, MS 
Upper Yazoo Project ......................... 
Coldwater River ............................ 
Arkabutla Canal ............................ 
Tallahatchie Canal .......................... 
Little Tallahatchie River and 
Panola-Quitman Floodway ................... .. 
Greenwood protection works .................. .. 
Yacona River ................................ 
BoboBayou............................................ 
Cassidy Bayou................................ 
Cassidy Bayou ............................... 
Bear Creek Diversion ........................ 
Lake Cormorant ............................ 
Hurricane Bayou ............................. 
Opossum Bayou............................. 
Abaica Creek ................................ 
Chicopa Creek ............... .... ....... .. 
Bear Creek ................................. 
Rocky Bayou ............ ................. 
Whiteoak Bayou ............................. 
Miscellaneous ditches ......................... 
Yalobusha River ............................ 
Yazoo River ................................ 
Whittington Auxiliary Channel .................. 
Tchula Lake ................................ 
David-Burrell Bayou .......................... 
McKinney Bayou ............................. 
Hillside Floodway ............................ 
Yazoo City protection works .................... 
Ascalmore-Tippo Bayous ....................... 
MISSISSIPPI RIVER COMMISSION 
CHANNEL IMPROVEMENTS: 
VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
2.7 
-- 
-- 
-- 
-- 
199.1 
69.6 
7.0 
54.9 
71.2 
21.1 
22.2 
36.5 
227.2 
35.4 
39.9 
179.0 
54.6 
0.4 
74.8 
48.0 
2.9 
1.8 
16.1 
69.0 
26.0 
4.8 
20.9 
2.5 
20.8 
7.7 
7.0 
23.3 
7.8 
55.9 
12.3 
46.0 
160.2 
30.8 
26.4 
40.4 
3.5 
11.0 
1.6 
30.2 
1947 
1947 
1947 
1947 
1965 
1959 
1957 
1960 
1960 
1976 
1941 
1948 
1940 
1939 
1971 
1952 
1944 
1934 
1939 
1940 
1956 
1964 
1957 
1960 
1964 
1953 
1975 
42-67 
-- 
--. 
-- 
42-67 
199.1 
69.6 
7.0 
54.9 
68.5 
21.1 
227.2 
35.4 
-- 39.9 
-- 58.1 
-- 54.6 
-- 0.4 
-- 73.5 
-- 48.0 
-- 2.9 
-- 1.8 
-- 16.1 
-- 69.0 
-- 46.0 
-- 160.2 
-- 30.8 
-- 26.4 
-- 40.4 
-- 3.5 
-- 11.0 
-- 1.6 
-- 15.1 
100 
100 
100 
100 
96 
100 
100 
100 
100 
32 
100 
100 
85 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
50 
-- 
-- 
-- 
-- 
--
-- 
-- 
.-- 
-
--

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-P 
(Continued) 
CHANNEL IMPROVEMENTS: 
VICKSBURG DISTRICT 
(FISCAL YEAR 1992) 
Total 
In Complete 
System Built Thru Currently 
Year When This This Percent Under 
Location Initiated Completed FY FY Complete Construction 
(Miles) 
YAZOO BASIN HEADWATER, MS 
(Continued) 
Alligator-Catfish Bayou ................... :.... 1973 8.3 -- 8.2 99 -- 
Pelucia Creek .............................. 1975 13.7 -- 5.6 40 6.3 
BOEUF & TENSAS RIVERS, 
ETC., LA AND AR 
Bayou Lafourche ............................. 1949 45.3 -- 45.3 100 -- 
Bayou Lafourche 4 ,7 . . . . . . . . . . . . . . . . . . . . . . . . . . . 1972 43.0 -- 4.4 10 -- 
Big & Colewa Creeks .......................... 1947 81.4 -- 81.4 100 -- 
Big & Colewa Creeks 5' 7 . . . . . . . . . . . . . . . . . . . . . . . . 1965 86.8 -- 51.5 60 -- 
Tensas River ................................ 1947 96.5 -- 96.5 100 -- 
Tensas River6 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1968 165.0 -- 61.0 37 -- 
Boeuf River, AR and LA ....................... 1953 103.9 -- 103.9 100 -- 
Fleschmans Bayou, AR ........................ 1963 6.6 -- 6.6 100 -- 
Caney Bayou, AR ............................ 1964 7.4 -- 7.4 100 -- 
Canal 18, AR ................................ 1963 10.3 -- 10.3 100 -- 
Big Bayou, AR ............................... 1952 33.3 -- 33.3 100 -- 
Black Pond Slough, AR ........................ 1962 14.3 -- 14.3 100 -- 
Bayou Macon, AR and LA ...................... 1959 150.8 -- 150.8 100 -- 
Rush Bayou, AR ............................... 1964 6.7 -- 6.7 100 -- 
Canal 19, AR ................................ 1957 50.2 -- 50.2 100 -- 
Canal 43, AR ................................ 1956 34.5 -- 34.5 100 -- 
Canal 81, AR ................................ 1957 32.7 -- 32.7 100 -- 
Mill Bayou-Bayou Vidal-Bayou 
Vidal Cutoff ................................ -- 17.1 -- -- -- -- 
Kirsch Lake Canal ............ ................. -- 9.3 -- -- -- 
Canal 19 Extension ............................ 1964 9.4 -- 9.4 100 -- 
Lake Chicot Pumping Plant .............. ....... -- 2.5 -- 2.5 100 -- 
Mill Bayou .................................. 1955 4.8 -- 4.8 100 -- 
RED RIVER BACKWATER, LA 
Tensas-Cocodrie Pumping Plant ................. . 1976 6.9 -- 6.9 100 -- 
Six Mile Bayou, LA . . . . . . . . . . . . . . . . . . . . . . . . . . -- 1.5 -- 1.5 100 -- 
GRAND PRAIRIE, AR8 . . . . . . . . . . . . . . . . . . . . . . . . -- 338.1 -- -- -- -- 
BAYOU METO, AR8 . . . . . . . . . . . . . . . . . . . . . . . . . . -- 164.9 -- -- -- -- 
1. 
2. 
3. 
4. 
Includes further work on 54.9 miles and adds 16.3 miles of channel to the project. 
Includes further work on 21.1 miles and adds 1.1 miles of channel to the project. 
Includes further work on 26.0 miles. 
Includes further work on 38.6 miles and adds 4.4 miles of channel to the project. 
5. Includes further work on 75.3 miles and adds 11.5 miles of channel to the project. 
6. Includes further work on 96.5 miles and adds 68.5 additional miles of channel to the project. 
7. Further work on these items has been deferred due to local oppositions and withdrawal of sponsorship by 
the levee district. 
8. Deauthorized Dec. 31, 1989. 
42-68

TABLE 42-Q 
MISSISSIPPI RIVER COMMISSION 
CHANNEL IMPROVEMENTS: 
MEMPHIS DISTRICT 
(FISCAL YEAR 1992) 
Total 
In Complete 
System Built Thru Currently 
Year When This This Percent Under 
Location Initiated Completed FY FY Complete Construction 
(Miles) 
BIRDS POINT-NEW MADRID 
FLOODWAY 
Birds Point-New Madrid Intercepting 
Ditch Enlargement, Samos and 
Vicinity, MO ............................... 
ST. FRANCIS BASIN 
Little River Drainage, MO ...................... 
St. Francis River, MO and AR ................... 
West Memphis Drainage, AR .................... 
Big Slough and Mayo Ditch, AR ................. 
Tyronza River, AR ............................ 
L'Anguille River, AR .......................... 
LOWER WHITE RIVER 
BASIN, AR 
Cache River Basin, AR ........................ 
Big Creek and tributaries, AR ................... 
WEST KENTUCKY TRIBUTARIES 
Obion Creek, KY .............................. 
WEST TENNESSEE TRIBUTARIES 
MS River, Western TN tributaries 
(Backwater Areas) (1946 Act) .................. 
Obion River Diversion Channel, 
TN (1946 Act) .............................. 
Reelfoot Lake-Lake No. 9, KY and TN ............. 
Running Reelfoot Bayou, TN ................... . 
MS River Below Cape Girardeau: West 
TN tributaries (1948 Act) ..................... 
Wolf River and tributaries, TN .................. 
NONCONNAH CREEK, MS AND TN 
Nonconnah Creek, MS and TN .................. 
HELENA HARBOR, PHILLIPS 
COUNTY, AR 
Helena Harbor, AR (2 ) . . . . . . . . . . . . . . . . . . . . . . . . . 
1952 
1963 
1953 
1951 
1960 
1939 
(1) 
1972 
(1) 
(1) 
1952 
(1) 
1974 
1955 
1961 
1960 
1990 
1989 
9.6 
298.9 
638.5 
19.8 
28.0 
12.7 
95.0 
231.5 
103.8 
-- 9.5 100 
0
9.2 
-- 
-- 
283.7 
481.2 
19.8 
28.0 
12.7 
-- 7.2 -- -- 
95 
75 
100 
100 
100
3 -- 
41.71 
34.3 
9.3 
15.8 
19.7 
225.0 
25.5 
18.2 
2.25 
-- 34.3 
-- 3.0 
-- 19.7 
-- 89.8 
-- 25.5 
100 
19 
100 
41 
100 
-- 0.5 38 
1. Not started. 
2. Data for Stage 1 only. 
42-69 
19.9 
-- 
--
-- 
0.5

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-R PUMPING STATIONS: 
NEW ORLEANS DISTRICT 
Rehabilitation Status 
(If Applicable) 
Percent Percent 
Complete Year Complete Year 
Authorized Thru Complete Thru Complete 
Size This (Schedule/ Year This (Schedule/ 
Name (CFS) FY Actual) Initiated FY Actual) 
Bayou Yokely 489 100 1955 1990 100 1991(A) 
Bayou Yokely Enlargement 568 100 1963 1990 100 1991(A) 
Centerville 332 100 1964 1991 100 1992(A) 
Ellerslie 136 100 1953 -- -- -- 
Franklin 144 100 1958 1992 42 1993(S) 
Franklin Enlargement 144 100 1978 1992 42 1993(S) 
Gordy 238 100 1964 -- -- -- 
Maryland 136 100 1957 1991 100 1992(A) 
North Bend 52 100 1962 -- -- -- 
Tiger Island 75 100 1955 -- -- -- 
Wax Lake East 1,008 100 1961 1990 100 1992(A) 
Wax Lake West 496 100 1965 1990 100 1992(A) 
Teche Vermilion 1,300 100 1982 -- -- -- 
PT Coupee 1l500 100 1983 -- -- -- 
TOTAL 6,618 
42-70

TABLE 42-S 
MISSISSIPPI RIVER COMMISSION 
PUMPING STATIONS: 
VICKSBURG DISTRICT 
Rehabilitation Status 
(If Applicable) 
Percent Percent 
Complete Year Complete Year 
Authorized Thru Complete Thru Complete 
Size This (Schedule/ Year This (Schedule/ 
Name (CFS) FY Actual) Initiated FY Actual) 
Bawcomville 270 100 1955 19921 5 1993(s ) 
Jonesville 180 100 1952 -- -- -- 
Natchez Port 100 -- -- -- -- -- 
Wilson Point 50 -- -- -- -- -- 
Greenwood - Lee Street 90 100 1953 1952 -- -- 
Greenwood - Wilson Street 67 100 1953 1952 -- -- 
Greenwood - Walker Lake 675 100 1949 1952 -- -- 
Yazoo City 540 100 1954 1957 -- -- 
West Monroe 4 488 -- -- -- -- -- 
Columbia 45 100 1939 -- -- -- 
Calion 200 100 1959 -- -- -- 
McKinney Bayou, MS 250 100 1962 1961 -- -- 
Lake Chicot 6,500 100 1987 -- -- -- 
Tensas Cocodrie 4,000 100 1986 -- -- -- 
Yazoo Backwater 10,000 -- -- -- -- -- 
Natchez Area 300 -- -- -- -- -- 
Bushley Bayou 300 -- Indef2 
- - -- 
Bushley Bayou 20 -- Indef2 
-- -- -- 
Sicily-HAHA Bayou 750 -- 1966 -- -- -- 
Sicily - Fool River 300 -- 1995 -- -- -- 
Pelucia Creek - Rising Sun #1 10 -- 1993 1991 -- -- 
Pelucia Creek - Rising Sun #2 15 -- 1993 1991 -- -- 
Pelucia Creek Pump 75 -- 1993 1992 -- -- 
Below Red River 500 -- Indef -- -- -- 
Total 25,925 
1 Repair of culverts to be accomplished in FY 92. 
2 This project has been placed in the inactive category. 
3 This project has been deferred indefinitely. 
4 Corps did not construct. 
42-71

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-T PUMPING STATIONS: 
MEMPHIS DISTRICT 
Rehabilitation Status 
(If Applicable) 
Percent Percent 
Complete Year Complete Year 
Authorized Thru Complete Thru Complete 
Size This (Schedule/ Year This (Schedule/ 
Name (CFS) FY Actual) Initiated FY Actual) 
Devall's Bluff 215 100 1949 1987 100 1989 
Des Arc, Ark. 30 100 1954 -- -- -- 
Ensley 900 100 1966 -- -- -- 
DD #17, Station #1 375 100 1 -- - 
Huxtable Pumping Plant 12,000 100 1977 -- -- -- 
Graham Burke 1,500 100 1964 -- -- -- 
Finley Street 100 100 1978 -- -- -- 
Dyersburg 26 100 1961 -- -- -- 
Cotton Slough 50 100 1964 -- -- -- 
West Hickman 190 100 1976 -- -- -- 
Cypress Creek 3,000 100 1944 -- -- -- 
Fairfax 53.5 100 1950 -- -- -- 
Goose Pond 110 100 1976 -- -- -- 
Marble Bayou 220 100 1952 -- -- -- 
Workhouse Bayou 520 100 1950 -- -- -- 
Nonconnah 1,620 100 1944 -- -- -- 
L&DD #3 Peafield 400 100 1 -- - 
Treasure Island 150 100 1976 -- -- -- 
Lake No. 9 500 100 1981 -- -- -- 
Cairo 10th Street 65 100 1981 -- -- -- 
Cairo 28th Street 65 100 1981 -- -- -- 
DD #17, Station #2 700 100 1981 -- -- -- 
Drinkwater Sewer 150 100 1979 -- -- -- 
May Street 5 100 1948 -- -- -- 
Cairo 22nd Street 37 100 1-- -- -- 
Gayoso Bayou 1,500 100 1915 -- -- -- 
Mud Lake 200 -- -- -- -- -- 
Madison 25 -- -- -- -- -- 
Cache River 200 -- -- -- -- 
New Madrid 1,500 -- -- -- -- 
St. John's Bayou 1,000-- -- -- -- 
TOTAL 27,406.5 
1 Unknown constructed by local interest. 
42-72

MISSISSIPPI RIVER COMMISSION 
TABLE 42-U COSTS DURING FISCAL YEAR 1992 
Item Construction Maintenance Other 
FEDERAL FUNDS 
Flood control, Mississippi River and tributaries: 
St. Louis District: 
St. Francis Basin-Wappapello Lake 
Subtotal 
Memphis District: 
General investigations 
Mississippi River levees 
St. Francis Basin 
White River Backwater 
Cache Basin, AR 
Channel improvement 
West Tennessee tributaries 
West Kentucky tributaries 
Inspection of completed works 
Mapping 
Reelfoot Lake No. 9, TN-K 
Mud Lake, TN 
Eight Mile Creek 
Helena Harbor 
L'Anguille River 
Memphis Harbor Ensley Berm 
Nonconnah Creek, TN & MS 
West Memphis & Vicinity 
Horn Lake Creek & Tribs 
Lake #9 Pumping Plant, KY 
Subtotal 
Vicksburg District: 
General investigations 
Mississippi River levees 
Lower Arkansas River 
Tensas Basin 
Yazoo Basin 
Channel improvement 
Mapping 
Inspection of completed works 
Lower Red River--South Bank Red River Levee 
Dam Safety Assurances 
Subtotal 
New Orleans District: 
General investigations 
Mississippi River levees 
Mississippi Delta Region 
Old River 
Bayou Cocodrie and tributaries 
Atchafalaya Basin 
2,509,800 
8,070,990 
304,437 
39,985,023 
1,222,735 
10,412 
522 
522 
1,725 
1,054,549 
8,423 
1,219,544 
2,548,215 
44,189 
306,935 
$ 4,620,973 
4,620,973 
4,713,797 
9,036,270 
680,903 
26,942,778 
791,518 
313,403 
3,017,213 
--. 
-- 
-- 4,566 -- 
57,288,022 42,483,235 3,017,213 
-- -- 211,008 
3,475,126 1,237,009 -- 
-- 1,081,140 -- 
4,212,507 4,158,763 -- 
43,799,644 26,330,825 -- 
14,395,232 13,778,438 -- 
-- 332,615 -- 
-- 178,701 -- 
-- 35,917 -- 
562,252 -- -- 
66,444,761 47,133,406 211,008 
16,736,441 
2,272,992 
711 
23,755,951 
414,511 
-- 
-- 
4,028,170 
62,757 
3,596,901 
144,434 
12,698,237 
42-73

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-U 
(Continued) 
COSTS DURING FISCAL YEAR 1992 
Item Construction Maintehance Other 
New Orleans District (Continued): 
Atchafalaya Basin Floodway System 3,659,853 -- -- 
Channel improvement 66,608,217 16,393,472 -- 
Mississippi & LA Estuarine 171,469 -- -- 
B. R. Harbor Devil Swamp -- 20,728 -- 
Inspection of completed works -- 148,231 -- 
Mapping -- 325,647 -- 
Subtotal 113,205,635 37,418,577 414,511 
Total Federal Funds 236,938,418 131,656,191 3,642,732 
CONTRIBUTED FUNDS 
New Orleans District: 
Atchafalaya Basin -- 6,723 -- 
Old River -- 164,915 
Mississippi Delta Region 2,309 -- -- 
Total Contributed Funds 2,309 171,638 -- 
Grand Total, Federal 
and Contributed Funds 236,940,728 131,827,830 3,642,732 
42-74

MISSISSIPPI RIVER COMMISSION 
TABLE 42-V STATEMENT OF ALLOTMENTS AND 
ACCRUED EXPENDITURES FOR FLOOD 
CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, 
THROUGH SEP. 30, 1992 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1992 
ALLOTMENTS AND ACCRUED EXPENDITURES 
CHARGEABLE AGAINST FLOOD CONTROL 
ACT LIMITATIONS: 
COMPLETED WORKS: 
Waterways Experiment Station 
Office, Chief of Engineers 
Rock Island District: 
S. G. & O. prior to Aug. 18, 1941 
St. Louis District: 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Memphis District: 
Des Arc, AR 
Contraction works 
DeValls Bluff, AR 
Mapping 
Memphis Harbor 
New Madrid Floodway 
Wolf River and tributaries 
Roads on levees (Mississippi River levees) 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
Vicksburg District: 
Boeuf Basin levees 
Channel realignment, Arkansas River 
Contraction works 
Eudora Floodway 
Vicksburg Harbor 
Greenville Harbor 
Grants Canal (Mississippi River levees) 
Mapping 
Jonesville, LA 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Subtotal 
$ 874,000 
19,158 
14,010 
$ 874,000 
19,158 
14,010 
169,3D 19,~5 
~ 
-- 
1,076,520 1,076,520 -- 
178,925 178,925 -- 
8,692,791 8,692,791 -- 
231,215 231,215 -- 
1,450,337 1,450,337 -- 
18,736,432 18,736,432 -- 
6,521,543 6,521,543 -- 
1,723,620 1,723,620 -- 
12,426 12,426 -- 
1,998,766 1,998,766 -- 
39,546,054 39,546,054 -- 
2,764,605 2,764,605 -- 
125,074 125,074 -- 
1,972,183 1,972,183 -- 
826,235 826,235 -- 
4,664,515 4,664,515 -- 
2,864,516 2,864,516 -- 
7,070 7,070 -- 
1,531,021 1,531,021 -- 
172,950 172,950 -- 
105,660 105,660 -- 
2,350,201 2,350,201 -- 
17.384.031 17_384_031 -- 
New Orleans District: 
Baton Rouge Harbor, LA 
Atchafalaya River and Basin, LA 
Bonnet Carre' Spillway, LA 
Contraction works 
Mapping 
699,185 
3,375,492 
14,212,198 
1,258,916 
1,112,967 
699,185 
3,375,492 
14,212,198 
1,258,916 
1,112,967 
42-75

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-V 
(Continued) 
STATEMENT OF ALLOTMENTS AND 
ACCRUED EXPENDITURES FOR FLOOD 
CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, 
THROUGH SEP. 30, 1992 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1992 
New Orleans District: (Continued) 
Roads on levees 
S. G. & O. prior to Aug. 18, 1941 
Wax Lake Outlet and Charenton Canal 
Morganza Floodway and structure 
Lake Pontchartrain 
Atchafalaya Basin, rights-of-way and flowage, 
Bayou des Glaises setback 
Subtotal 
All other completed items: 
Surveys under Sec. 10, Flood Control Act of 1928 
Impounded savings 
Plant transferred to revolving fund 
OCE (portion of allotment transferred to 
revolving fund, Washington Dist.) 
Subtotal 
TOTAL COMPLETED WORKS 
UNCOMPLETED WORKS: 
Rock Island District: 
Levees under Sec. 6, Flood Control Act of 1928 
St. Louis District: 
Levees under Sec. 6, Flood Control Act of 1928 
Subtotal 
Memphis District: 
Mississippi River levees 
Mississippi River levees 
New Madrid 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Reelfoot Lake 
Reelfoot Lake, Lake No. 9, TN-KY 
St. Francis Basin: 
Wappapello Lake 
St. Francis River and tributaries 
Big Slough and Mayo ditch 
Little River drainage 
540,838 
2,701,566 
10,098,817 
35,992,117 
5,513,110 
540,838 
2,701,566 
10,098,817 
35,992,117 
5,513,110 
387,917 387,917 -- 
75,893,123 75,893,123 -- 
4,995,215 4,995,215 -- 
1,593,097 1,593,097 -- 
24,924,578 24,924,578 -- 
18,882 19,882 -- 
31,532,772 31,532,772 -- 
165,432,500 165,432,500 -- 
579,462 579,462 -- 
1,897,980 1,897,980 -- 
2_477_442 2_447442-- 
182,640,354 
98,000 
377,899,369 
58,566,439 
178,695,900 
439,434 
7,895,000 
9,019,908 
245,633,682 
965,429 
51,766,592 
182,463,223 
98,000 
377,402,972 
58,566,439 
177,347,224 
439,434 
7,887,607 
9,019,908 
243,783,149 
965,429 
51,759,354 
177,131 
-- 
496,397 
-- 
1,348,676 
--
7,393 
-- 
1,850,532 
7,238 7,238 
42-76

MISSISSIPPI RIVER COMMISSION 
TABLE 42-V 
(Continued) 
STATEMENT OF ALLOTMENTS AND 
ACCRUED EXPENDITURES FOR FLOOD 
CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, 
THROUGH SEP. 30, 1992 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1992 
Lower White River: 
Clarendon Levee 
Augusta to Clarendon, AR 
White River backwater levee, AR 
Horn Lake Creek & Tribs 
Memphis Harbor Ensley Berm 
Nonconnah Creek, TN & MS 
West Memphis and Vicinity 
Levees under Sec. 6, Flood Control Act of 1928 
West Tennessee tributaries 
Helena Harbor 
Cache Basin, AR 
West Kentucky tributaries 
Mud Lake Pumping Station, TN 
L'Anguille River 
Eight Mile Creek 
Subtotal 
Vicksburg District: 
Mississippi River levees (excludes Grants Canal, 
$7,070, shown under completed works) 
Section 6 Levees 
Lower Arkansas River: 
North Bank 
South Bank 
Tensas Basin: 
Lake Chicot pumping plant 
Tensas River 
Red River Backwater: 
Below Red River 
Red River backwater levee, LA 
Tensas Cocodrie pumping plant 
Lower Red River South Bank Red River Levees 
Tensas National Wildlife Refuge, LA 
Channel improvement: 
Revetments 
Dredging 
Dikes 
Levees under Sec. 6, Flood Control Act of 1928 
Ouachita River Levees 
Yazoo Basin: 
Sardis Lake 
Enid Lake 
Arkabutla Lake 
Grenada Lake 
Greenwood 
Belzoni 
Yazoo City 
505,715 
1,788,846 
10,624,501 
625,000 
3,497,000 
6,328,000 
570,000 
108,651 
42,516,900 
7,671,000 
10,450,000 
1,440,000 
107,000 
196,000 
1,993,000 
1,202,041,720 
212,665,990 
9,000 
7,049,414 
15,676,286 
96,172,400 
41,507,200 
639,400 
70,915,046 
55,058,900 
756,300 
39,800,000 
440,662,065 
23,549,260 
127,934,040 
958,175 
400,000 
26,502,400 
21,292,400 
16,000,700 
45,401,494 
11,543,000 
316,656 
2,205,611 
505,703 
1,788,174 
10,624,501 
441,901 
3,439,916 
5,351,269 
537,514 
108,651 
42,015,917 
7,140,067 
10,446,038 
1,439,545 
95,128 
180,676 
1,692,305 
1,195,540,043 
211,106,412 
9,000 
7,049,414 
15,676,286 
95,637,407 
41,507,200 
639,400 
70,006,315 
55,016,257 
756,300 
39,800,000 
438,012,406 
23,549,260 
126,602,137 
958,175 
400,000 
26,502,400 
21,292,400 
16,000,700 
45,401,494 
11,543,000 
316,656 
2,205,611 
42-77 
12 
673 
-- 
183,099 
57,084 
976,731 
32,486 
500,983 
530,933 
3,962 
455 
11,872 
15,324 
300,695 
6,501,677 
1,559,579 
-- 
534,993 
-- 
908,731 
42,643 
-- 
-- 
2,649,659 
1,331,904
--

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-V STATEMENT OF ALLOTMENTS AND 
(Continued) ACCRUED EXPENDITURES FOR FLOOD 
CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, 
THROUGH SEP. 30, 1992 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1992 
Yazoo Basin: (Continued) 
Will M. Whittington auxiliary channel 10,950,966 10,950,966 -- 
Big Sunflower, etc. 54,568,000 54,056,499 511,501 
Main Stem 34,404,300 34,403,926 374 
Upper Yazoo Projects 82,655,036 81,719,034 936,002 
Yazoo Basin--Tributaries 
Tributaries (Except Ascal-Tippo-Opossum Bayous) 90,984,166 89,315,349 1,668,817 
Tributaries--Bank Stabilization 612,484 612,484 -- 
Ascalmore-Tippo-Opossum Bayous 23,978,100 23,977,200 900 
Yazoo Basin Backwater 
Yazoo Backwater 56,597,200 56,589,321 7,879 
Rocky Bayou 3,407,500 3,403,874 3,626 
Yazoo Backwater Pumping Plant 9,064,850 9,064,850 -- 
Muddy Bayou 5,145,200 5,145,200 -- 
Yazoo Backwater, F&WL Mitigation 4,832,900 4,723,421 109,479 
Yazoo Basin Reevaluation 12,533,270 12,163,726 369,544 
Streambank Erosion Control, Eval. and Demo. 14,767,000 14,767,000 -- 
Demonstration Erosion Control 91,744,900 87,476,519 4,268,381 
Dam Safety Assurances-Sardis Dam 7,287,000 7,197,533 89,467 
Subtotal 1,760,548,610 1,745,555,132 14,993,478 
New Orleans District: 
Teche-Vermilion Basin Water Supply 34,506,000 34,506,000 -- 
Bayou Cocodrie and Tributaries 5,008,008 5,008,008 -- 
Miss. & LA Estuarine 1,337,000 1,131,845 205,155 
Channel Improvement: 
Dredging 35,945,266 35,945,266 -- 
Revetments 861,799,117 860,986,871 812,245 
Lower Red River (South Bank Levees) 18,056,600 18,056,600 -- 
Levees Under Sec. 6, Flood Control Act of 1928 200,680 200,680 -- 
Mississippi River Levees 280,217,000 277,330,221 2,886,779 
Mississippi Delta Region 21,736,000 21,223,059 512,941 
Atchafalaya Basin Floodway: 
Atchafalaya Basin 684,196,537 678,686,196 5,510,341 
Atchafalaya River Navigation 303,463 303,463 -- 
Atchafalaya Basin Floodway System 27,527,000 23,798,147 3,728,853 
Old River 292,274,000 292,274,000 -- 
Subtotal 
TOTAL UNCOMPLETED WORKS 
ADVANCE ENGINEERING AND DESIGN 
(CONSTRUCTION) 
Memphis District: 
L'Anguille River Basin, AR 
Reelfoot Lake, Lake No. 9 
Cache River 
Big Creek and Tributaries, Lower White River 
2,263,106,671 2,249,450,356 13,656,315 
5,228,174,442 5,193,022,973 35,151,469 
150,000 150,000 
30,000 30,000 
420,000 420,000 
365,000 365,000 
42-78

MISSISSIPPI RIVER COMMISSION 
TABLE 42-V 
(Continued) 
STATEMENT OF ALLOTMENTS AND 
ACCRUED EXPENDITURES FOR FLOOD 
CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, 
THROUGH SEP. 30, 1992 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1992 
Memphis District: (Continued) 
Clarendon Levee, Lower White River 
West Kentucky Tributaries 
Mud Lake Pumping Station, TN 
Harris Fork Creek, KY & TN 
Subtotal 
Vicksburg District: 
Yazoo Basin, Big Sunflower River, Steele Bayou 
Tensas - National Wildlife Refuge, LA 
Subtotal 
New Orleans District: 
Mississippi Delta Region 
Teche Vermilion Basin-Water Supply 
East Rapides & S. Central Avoyelles Parishes 
Subtotal 
TOTAL ADVANCE ENGINEERING 
AND DESIGN 
TOTAL COMPLETED WORKS, UNCOMPLETED 
WORKS AND ADVANCE ENGINEERING 
AND DESIGN 
RECREATION FACILITIES--COMPLETED 
PROJECTS 
Eight-Year Project Funds 
St. Louis District: 
Wappapello Lake, MO 
Wappapello Lake, MO, Rockwood Landing 
Subtotal 
Vicksburg District: 
Sardis Lake 
Enid Lake 
Arkabutla Lake 
Grenada Lake 
Subtotal 
Total Eight-Year Program Funds 
Total chargeable against Flood Control 
Act Limitations excluding flood 
control emergencies 
Total maintenance since Aug. 18, 1941 
65,000 
175,000 
350,000 
540,000 
65,000 
175,000 
350,000 
540,000 
2,095,000 2,095,000 -- 
29,700 29,700 -- 
200,000 200,000 -- 
229,700 229,700 -- 
69,753 69,753 -- 
1,109,000 1,109,000 -- 
965,247 965,247 -- 
2,144,000 2,144,000 -- 
4,468,700 4,468,700 -- 
5,398,075,642 5,362,924,173 35,151,469 
2,405,300 2,405,300 -- 
203,286 203,286 -- 
2,608,586 2,608,586 -- 
1,584,339 1,584,339 -- 
2,268,209 2,268,209 -- 
2,189,280 2,189,280 -- 
1,631,281 1,631,281 -- 
7,673,109 
10,281,695 
5,408,357,337 
2,315,479,855 
7,673,109 
10,281,695 
5,373,205,868 
2,306,771,481 
35,151,469 
8,708,375 
42-79

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-V 
(Continued) 
STATEMENT OF ALLOTMENTS AND 
ACCRUED EXPENDITURES FOR FLOOD 
CONTROL, MISSISSIPPI RIVER AND 
TRIBUTARIES, FROM MAY 15, 1928, 
THROUGH SEP. 30, 1992 
Unexpended 
Accrued Balance 
District or Installation and Class of Work Allotments Expenditures Sep. 30, 1992 
Vicksburg District: (Continued) 
Total rehabilitation 31,113,000 31,113,000 -- 
Total flood control emergencies 14,900,300 14,900,300 -- 
Total general investigations 85,033,381 83,930,341 1,103,041 
Total flood control, MR&T appropriations 7,854,883,873 7,809,920,989 44,962,885 
Appropriations in addition to flood control, MR&T 
Other appropriations itemized in footnote (1), 
pp. 2068-69, Annual Report for 1953 32,068,909 32,068,909 -- 
Grand total appropriated to Sep. 30, 1992 7,886,952,782 7,841,989,897 44,962,885 
Note: Preauthorization study costs chargeable to the MR&T authorization have been transferred to completed 
work. Costs not chargeable have been excluded from this report. 
42-80

MISSISSIPPI RIVER COMMISSION 
TABLE 42-W STATEMENTS OF EXPENDITURES FOR 
LEVEES BY STATE AND LOCAL 
ORGANIZATIONS THROUGH DEC. 31, 1991 
Engineer District Expenditures 
St. Louis $ 80,750,859 
Memphis 301,832,123 
Vicksburg 145,341,089 
New Orleans 711,358,390 
Total $1,239,282,461 
42-81

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-X COST AND FINANCIAL STATEMENT 
Total 
Project Funding FY 89 FY 90 FY 91 FY 92 Sep. 30, 1992 
Mississippi River General investigations: 
and tributaries Allotted 5,029,000 2,628,500 2,510,000 3,774,000 85,033,381 
(Regular Funds)1 Cost 5,286,048 2,903,198 2,610,794 3,642,732 83,930,341 
Construction (includes 
advance engineering 
and design): 
Allotted 210,139,000 216,161,500 215,162,000 217,256,000 5,228,174,442 
Cost 197,370,967 209,946,171 217,709,941 236,938,418 5,193,022,973 
Maintenance 
Allotted 121,878,000 113,768,000 126,690,000 132,439,000 2,315,479,855 
Cost 119,586,856 110,049,671 129,231,497 131,656,191 2,306,771,480 
Rehabilitations 
Allotted -- -- -- -- 31,113,000 
Cost -- -- -- -- 31,113,000 
Flood control 
emergencies 
(Maintenance): 
Allotted -- -- -- -- 14,885,992 
Cost -- -- -- -- 14,885,992 
(Contributed Funds) New Work: 
Contributed 2,028,507 1,845,800 195,910 -- 15,365,680 
Cost 1,296,903 2,185,585 726,505 2,309 15,304,026 
Maintenance 
Contributed 83,164 85,742 14,423 -- 2,687,827 
Cost 64,994 65,698 7,700 171,638 2,623,991 
1. Appropriations were as follows: 
Appropriations chargeable against Flood Control Act authorizations: 
Flood Control, MR&T except for emergencies (excludes Maintenance 
allotments Aug. 18, 1941, through Sep. 30, 1992): 
Net total allotted for works under Mississippi River Commission: 
Eight-Year Program Funds, Construction General: 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 
Transferred to revolving fund: 
Impounded savings: 
Flood control emergencies: 
Net total allotted: 
Impounded savings: 
Additional funds not chargeable against Flood Control Act authorizations: 
Appropriations for Flood Control, MR&T, except for flood control emergencies: 
General investigations: 
Maintenance allotments Aug. 18, 1941, through Sep. 30, 1992 
Appropriations in addition to appropriations for Flood Control, MR&T 
(itemized in footnote (1), pp. 2068-69, Annual Report for 1953): 
Budgetary and OCE Reserves: 
Grand total: 
$5,397,655,870 
10,281,695 
4,995,215 
24,944,460 
1,593,097 
14,885,922 
14,378 
85,033,381 
2,315,479,855 
$5,439,470,337 
14,900,300 
2,400,513,236 
32,068,909 
7,886,952,782 
42-82

MISSISSIPPI RIVER COMMISSION 
TABLE 42-X 
(Continued) 
COST AND FINANCIAL STATEMENT 
Total 
Project Funding FY 92 Sep. 30, 1992 
Reconciliation of appropriations and allotments: 
Total allotted to Sep. 30, 1992 
Transferred to revolving fund: 
Surveys under Sec. 10, Flood Control Act of 1928 (not under MRC): 
Impounded savings withdrawn by Chief of Engineers: 
7,855,405,632 
24,944,460 
4,995,215 
1,607,475 
Total Appropriations to Sep. 30, 1992: 
Appropriations for past four reporting periods were as follows: 
FY 89: $337,046,000 FY 91: $344,362,000 
FY 90: $332,558,000 FY 92: $353,469,000 
2. Totals for General Investigations include four projects transferred from Construction totals per DAEN-CWB-W, Aug. 4, 
1978, teletype. 
42-83 
7,886,952,782

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
TABLE 42-Y MISSISSIPPI RIVER AND TRIBUTARIES 
ACTIVE GENERAL INVESTIGATIONS 
(96X3112) 
Federal Cost Totals by 
Item and CWIS Number FY 92 Categories 
SURVEYS (Category 100) 
Flood Damage Prevention (112) 
New Orleans District 
Alexandria, LA-12743 $ 380,740 
Atchafalaya Basin Water & Land Res-12026 $ 33,771 
Subtotal 414,511 
Vicksburg District 
Boeuf-Tensas Basin, AR & LA-81273 16,912 
Natchez, MS-12675 1,784 
Southeast Arkansas, AR-12756 132 
South Bank Levee, Bayou Rapides, LA-10220 16,116 
Subtotal 34,944 
Memphis District 
Jackson & Trenton, TN - 12874 $573,974 
Mayfield Creek-10850 757 
Newport Harbor, MS-10361 322,703 
St. Francis River Below Wappapello (Whiteman's Creek)-22000 288,590 
St. Francis River F&WL, AR & MO-79690 51,717 
Subtotal 1,237,741 
TOTAL (Category 110) $1,687,196 
COLLECTION AND STUDY OF BASIC DATA (Category 120) 
Vicksburg District 175,064 
Memphis District 88891 
TOTAL (Category 120) 263,955 
CONTINUATION OF PLANNING & ENGINEERING (Category 140) 
Flood Control Projects (141) 
Memphis District 
Eastern Arkansas Regional- 
Comprehensive Study - 81266 $815,680 
Whiteman's Creek, AR - 12738 
$930,861 
TOTAL (Category 140) 930,861 
42-84

MISSISSIPPI RIVER COMMISSION 
TABLE 42-Y 
(Continued) 
MISSISSIPPI RIVER AND TRIBUTARIES 
ACTIVE GENERAL INVESTIGATIONS 
(96X3112) 
Federal Cost Totals by 
Item and CWIS Number FY 92 Categories 
PRE-CONSTRUCTION ENGINEERING & DESIGN (Category 160) 
Flood Control Projects (162) 
Memphis District 
Helena AR & Vicinity-81280 432,743 
Horn Lake Creek & Tribs/Cowpen Creek-81282 7 
Lower White River Big Creek & Trib-12472 320,849 
St. Johns Bayou & New Madrid Fdwy-77005 205 
West Memphis & Vicinity-81281 5,915 
TOTAL (Category 160) 759,719 
GRAND TOTAL MR&T GENERAL INVESTIGATIONS 3,641,731 
42-85

US ARMY CONSTRUCTION ENGINEERING RESEARCH LABORATORIES 
The U. S. Army Construction Engineering Research 
Laboratories (USACERL)) at Champaign, Illinois conducts 
research in the planning, design, construction, 
operation and maintenance and environmental quality 
for Military and Civil Works facilities. 
During FY 92, significant accomplishments by 
USACERL applicable to Civil Works included: 
(1) Research was completed on new epoxy coating 
systems for immersion in fresh water and for atmospheric 
exposure. These coatings will provide cost effective 
protection and compliance with air pollution regulations. 
Metallized coating systems and guidance for their 
use have been developed. These materials have proven 
to be very cost effective for severely abrasive fresh water 
exposures on locks and dams. A study of anti fouling and 
non toxic foul-release coatings for the conrol of zebra 
mussels at public facilities has been initiated. 
(2) Six training courses were conducted for Corps of 
Engineers personnel on the use of Repair, Evaluation, 
Maintenance and Rehabilitation (REMR) Management 
Systems for Miter Lock Gates, Steel Sheet Pile Structures, 
and Concrete Lockwalls. Two new systems have 
also been completed. These systems include Sector Lock 
Gate and Filling and Emptying Valves. The REMR 
Management ;systems provide uniform and objective 
analysis and development condition assessment and 
tools for economic analysis and data management. Cost 
savings are realized through the development of optimal 
maintenance and repair work plans and optimal budget 
planning. 
(3) The Application Distribution System, GAPPL 
Version 1.04 is complete. It is in use by all Civil Works 
districts and divisions and is operational in the CEAP 
environment. HQUSACE electronically distributes five 
critical Civil Works applications and monitors version 
control, as required. This product is taught to all Civil 
Works districts during the annual district training. 
(4) A prototype of the District Operation and Maintenance 
Budget System was implemented at Portland 
District in the spring of 1992. 
43-1

U.S. ARMY COLD REGIONS RESEARCH 
AND ENGINEERING LABORATORY 
BACKGROUND 
The U.S. Army Cold Regions Research and Engineering 
Laboratory (CRREL), in Hanover, New 
Hampshire, maintains the finest research and engineering 
staff and facilities in the world for the 
study of cold regions science and technology. 
CRREL's experience spans 50 years, starting with 
the Boston District's Soils Laboratory work on 
frozen soils in the early 1940s. The creation of 
CRREL in 1961 with the merger of the Arctic Construction 
and Frost Effects Laboratory (ACFEL) and 
the Snow, Ice, and Permafrost Research Establishment 
(SIPRE)-both of which were outgrowths of 
the Army's World War II experience in Alaska, Iceland, 
and Greenland-put the Nation's and DoD's 
principal cold regions expertise in one place. 
CRREL's traditional program involves the study 
of the earth's cold regions, focusing on basic and applied 
scientific research and on expanding the technologies 
required for both military and civil works 
development and operations. CRREL was the first 
organization in the world to recover complete ice 
cores from the Greenland and Antarctic ice caps to 
analyze the world's climate over the past 100,000 
years. This accomplishment has served as a platform 
for the present international global change research 
effort. CRREL provided engineering support for the 
design and construction of the Alyeska Oil Pipeline 
in Alaska, early exploration and scientific work in 
Antarctica, and helped develop engineering testing 
methods and design criteria for construction in cold 
regions that are used as national and international 
standards. CRREL also has developed river ice technology 
and management systems that allow costeffective 
use of the Nation's 25,000 miles of inland 
waterways throughout the winter. 
CRREL's unique mission strongly supports a 
changing Corps, a changing Army, and a changing 
nation. CRREL recognizes its responsibility to use its 
exceptionally creative scientists and engineers to assist 
the Corps in its mission as engineer-defender 
and builder of a new nation. Worn-out and outmoded 
infrastructure; environmental degradation of 
land, water, and air; increased awareness of the need 
to understand and master the complexities of the 
global environment; the apparent end of the cold 
war; and increased international economic pressures 
making long-term investment in research and development 
difficult-all cry out for innovative and 
effective action. The Corps has responded decisively 
and effectively to the challenge of new mission responsibility, 
and CRREL has been at the leading 
edge of this effort. 
Other priority national programs to which 
CRREL has contributed significantly include work in 
pavement and transportation systems for the 
Federal Aviation and Highway Administrations, including 
participation in the Strategic Highway Research 
Program. CRREL continues to be a principal 
consultant to the National Science Foundation in its 
Arctic, Antarctic, and Greenland Ice Sheet research 
programs. CRREL works with the Department of the 
Interior to study the effects of global climate change 
on water regimes in the North, and has been a significant 
participant with the Navy to develop DoD 
initiatives to complement the U.S. Global Climate 
Change Program. CRREL also provides support to 
DoE and EPA concerning the environmental characterization 
and restoration of toxic and hazardous 
materials in the special conditions of permafrost and 
high-latitude environments. Private industry also 
comes to CRREL for assistance not available in the 
private sector. 
As the Army's center of expertise, CRREL conducts 
cold regions scientific and engineering 
research that addresses problems encountered by 
the Army and other DoD agencies wherever accomplishment 
of their mission is affected by winter/cold 
regions conditions. 
CRREL's unique and capable research staff and 
facilities are matched to its equally unique mission. 
CRREL's 333 employees include many of the 
world's experts on snow, ice, frozen ground, and 
cold regions engineering. The dominant in-house execution 
of programs, coupled with a very rigorous 
peer review, has maintained the high level of staff 
expertise and the Laboratory's reputation as the best 
44-1

Report of the Secretary of the Army on Civil Works Activities for FY92 
of its kind in the world. CRREL's national and international 
reputation has been its most effective recruiting 
tool and attracts high-quality scientists and 
engineers to perpetuate the excellence of the technical 
staff. 
FACILITIES 
The combination and variety of specialized research 
and experimental facilities at CRREL is unequaled 
in the world. The main laboratory contains 
26 coldrooms that can be operated at temperatures 
as low as -50�F, a computer center, chemistry laboratories, 
a well-equipped soil physics laboratory, a 
cleanroom complex, soil chemistry facilities, and a 
remote sensing analysis center. 
Specialized equipment includes low-temperature 
materials testing machines, gas chromatographymass 
spectrometers, atomic absorption spectrometers, 
supercritical fluid chromatography, a lowtemperature 
electron microscope, a dual gamma 
nondestructive testing device, a Hopkinson pressure-
bar impact test device, and nuclear magnetic 
resonance equipment. 
The Ice Engineering Facility (IEF) is one of the 
largest refrigerated hydraulics laboratories in the 
world. It contains a research area for large-scale refrigerated 
hydraulic models, a refrigerated flume, 
and a wind tunnel for simulating drifting snow, and 
includes the only active low-temperature ice towing 
tank in the United States. It serves the civil works 
needs of the Corps, the Navy's needs for testing the 
ice capability of its surface and submarine hulls, 
and, when necessary, provides support to private 
industry. 
The Frost Effects Research Facility (FERF) is a 
29,000-square-foot refrigerated soils laboratory consisting 
of 12 test cells that are individually temperature 
controlled. Pavements, base and subbase 
courses, and buried utilities can be tested here at full 
scale. Six to eight natural freeze-thaw cycles can be 
simulated in a single year using refrigeration panels. 
Unique in the world, the FERF is a facility that supports 
research needs of the DoD and other Federal 
agencies, such as FAA and FHWA. 
Construction has begun on a Technical Information 
Analysis Center, which will house the Information 
Management and the DoD Cold Regions 
Information Analysis Center functions at CRREL. 
CRREL is recognized as having the world's foremost 
collection of cold regions scientific and technical literature. 
More than 2,000 requests for information are 
filled each year. In addition, the Bibliography on 
Cold Regions Science and Technology is prepared at 
the Library of Congress under joint CRREL/NSF 
sponsorship. It contains more than 140,000 citations 
of world cold regions literature, including approximately 
50,000 Russian items. 
A building to house the Army Corps of Engineers' 
Remote Sensing and Geographic Information 
Systems Center will be occupied in early 1994. The 
Center provides a focus for assisting the Corps District 
offices in exploiting the rapidly expanding 
capabilities of remote sensing and geographical 
information systems technologies in the execution of 
their water resources and environmental regulatory 
missions. 
The rebuilt Cold Laboratory Complex at CRREL 
is the only major low-temperature physical sciences 
complex in the Nation. It supports work for the 
three military services as well as other Federal agencies, 
such as the Geological Survey and the National 
Science Foundation. The CRREL Sleepers River Experimental 
Watershed in Danville, Vermont, was 
named a national site for study of climate change in 
conjunction with the Department of the Interior. 
CRREL's Permafrost Research Site at Farmer's Loop, 
Alaska, and the close association of CRREL's Alaska 
Projects Office with military units in Alaska provide 
day-to-day interaction with the user. 
RESEARCH PROGRAM 
CRREL's basic and applied research cover a 
broad spectrum of cold regions studies. Basic research 
includes work in environmental quality, 
boundary layer processes, and the physical, mechanical, 
and chemical properties of snow and other 
forms of frozen precipitation, freshwater ice, sea ice, 
and frozen soils. Basic research supports applied 
research in the major cold regions mission areas of: 
* ice jam floods 
* winter navigation 
* remote sensing for civil works 
* base support 
* infrastructure design and construction 
* combat operations and materiel performance 
44-2

Major civil works cold regions research topics include 
ice engineering, river ice management, river 
confluence ice, water resources in cold regions, and 
remote sensing. 
CRREL has an international reputation and maintains 
close ties with the international research community 
and with Federal and state agencies, providing 
consulting services on a reimbursable basis. 
As the cold regions scientific and engineering expert 
for the Corps of Engineers, CRREL supports districts 
and divisions by publishing field engi-neering 
reports, conducting demonstrations, sponsoring 
technical seminars for field engineers, and making 
field visits to consult on engineering problems. 
OPERATIONS AND RESULTS DURING FY92 
CRREL provides a world-class capability not 
available in academia or industry through its highly 
focused mission, one-of-a-kind research and engineering 
facilities, and renowned technical staff, 
making it an invaluable and unique resource for the 
Army, DoD, and the Nation. The synergism of 
applying these assets to a broad range of military 
and civilian problems, and the ability to sustain a 
critical mass of resources in a highly specialized and 
sophisticated area, contribute significantly to 
CRREL's effectiveness as an organization. 
In FY92, CRREL published and distributed 368 
scientific and engineering documents (27 CRREL 
Reports; 3 Monographs; 44 Special Reports; 30 Fact 
Sheets; 30 technical videotapes; 119 journal articles; 
108 conference papers; one Technical Digest; and six 
miscellaneous CoE, DA, and other government 
publications). 
CRREL'S CIVIL WORKS R&D PROGRAM 
There are four major thrusts and one new 
initiative in CRREL's civil works R&D program: 
* The Ice Engineering Program has developed 
the Nation's principal guidance for winter navigation, 
river ice management, and ice jam 
flood control. In severe winters, ice jams are 
responsible for more than $100 million in damage 
due to ice-induced flooding. Efforts to control 
ice jams and ice-induced flooding have 
helped reduce their cost to the Nation. 
* CRREL is Program Manager of the Corps of 
Engineers Civil Works Remote Sensing Research 
and Development Program: The program 
emphasizes the exploitation of real-time 
in-situ sensors and commercially available satellite 
imagery and integration of these data into 
a spatial data management system. Development 
and utilization of remote sensing technology 
for civil works applications in water 
and natural resources are urgently needed to 
provide cost-effective information necessary 
for many of the Corps engineering, operations, 
and planning missions. 
* In the Water Resources of Cold Regions Program, 
the USGS joined CRREL in conducting 
research at the Sleepers River Research 
Watershed. This partnership has filled a significant 
gap, with the USGS undertaking biogeochemical 
research in conjunction with our 
snowmelt research. Work continues on developing 
an improved snowmelt runoff module 
for CoE hydrologic models, with additional 
studies focusing on the partly glacierized 
basins. A deliberate shift to understand the 
hydroclimatic regimes in northern wetlands 
was undertaken because of the lack of and 
need for knowledge in this technical area. 
* The Construction Productivity Advancement 
Research (CPAR) Program is a cost-shared 
partnership between the Corps of Engineers, 
the U.S. construction industry, academia institutions, 
state and local governments, and 
other groups. Its purpose is to cooperatively 
advance research innovation in the U.S. construction 
industry, thereby enhancing its productivity 
and competitiveness. This is a cooperative 
program with WES, CERL, and TEC. 
ACCOMPLISHMENTS 
Ice Engineering Program 
A new concept for installing a low-cost ice control 
structure during freezeup on small streams was developed, 
and a model was tested in the hydraulic research 
area of CRREL's Ice Engineering Facility. A 
demonstration prototype was installed on the Ompompanoosuc 
River just above the Corps of Engineers 
Dam at Union Village, Vermont, to verify the 
model's performance and to refine design and installation 
procedures. This relatively inexpensive 
removable structure, called a tension weir, is designed 
to control frazil ice production during freezeup 
in areas where regular ice booms are ineffective 
44-3

Report of the Secretary of the Army on Civil Works Activities for FY92 
and where traditional permanent structures are unacceptable 
for environmental or economic reasons. 
A patent application has been submitted for an 
economical technique to prevent clogging of water 
intakes by frazil ice by heating only the edges of 
trash-rack bars. This technique is much more efficient 
than heating the whole bar, and it eliminates 
the risk of damaging the trash racks when the ice is 
removed manually or mechanically. It has large 
potential cost savings, not only to the Corps, but also 
to those industries (such as the power industry and 
fisheries) and municipalities that may have to 
reduce or even shut down operations when their 
water intakes become clogged by frazil ice. 
In 1992 CRREL continued to provide assistance to 
Corps districts and divisions and to the Nation in 
studies on flood protection in areas prone to ice 
jams. For the Walla Walla District, CRREL concluded 
a three-year field demonstration program of 
an experimental modified freezeup control ice boom 
on the Salmon River in Idaho. The field results 
proved that this modified ice boom would indeed 
prevent major flooding of the town of Salmon. An 
assessment of the feasibility of ice jam control on the 
Missouri River in the Williston, North Dakota, area 
was conducted for the Omaha District. Also, personnel 
from the Ice Engineering Research Branch assisted 
the New York District and the State of Vermont 
during the ice jam flood of Montpelier, 
Vermont, in March 1992. Finally, CRREL conducted 
a field study for the Detroit District on the effects of 
ship-induced ice movement, bottom water currents 
and sediment transport in wetland areas of the St. 
Marys River, Michigan, as well as potential damages 
to marinas and shoreline structures, that might 
result from an early opening of the Soo Locks. 
Remote Sensing Program 
An area of emphasis has been the incorporation 
of geographic information system (GIS) technology 
coupled to forecast models, such as the Corps water 
control system. The Remote Sensing/GIS Center recently 
created at CRREL provides an integrated 
technical assistance and transfer function to complement 
the R&D program. The Center managed a 
major field demonstration with Omaha District, the 
Oahe Dam Safety Exercise, to demonstrate the utility 
of remote sensing and GIS technology for emergency 
operations, and it has coordinated research 
for detecting oil spills. 
The Center also provided assistance to the Jacksonville 
District in configuring, acquiring and staffing 
a fully operational GIS capability as part of the 
Hurricane Andrew recovery effort. The system was 
used to map the location and status of emergency 
shelters and life support centers, debris removal operations, 
temporary housing-clearing, infrastructure 
installation and mobile home placement, location of 
sunken vessels, and installation of mobile classrooms. 
The debris volume was estimated and the 
status of removal operations tracked. In one case, the 
Federal government saved $3.6 million when, by 
using the GIS to more accurately estimate the total 
acreage of Australian pine downed on the south end 
of Key Biscayne, a bid of $7.0 million for clearing the 
pine was rejected and a re-bid of $3.4 million was accepted, 
a savings of more than ten times the $350,000 
investment in GIS. 
Cold Regions Water Resources 
In the Water Resources of Cold Regions Program, 
CRREL and the USGS in their WEBB research program 
continued their cooperative research at the 
Sleepers River Research Watershed. This partnership 
has continued to fill a significant gap in our 
hydrologic research with the USGS focusing on 
geochemical interactions in the surface and groundwater 
flows that complement our snowmelt research. 
Work continues on developing an improved 
snowmelt runoff module for CoE hydrologic models, 
with additional studies focusing on the partly 
glacierized basins. A need to understand the interaction 
between the surface and groundwater regimes 
is now recognized as critical to understanding 
the hydrologic flow paths to the streams. 
Research continues on understanding the physical 
and thermal regimes of riparian areas in the 
winter, and, in particular, the northern sites with 
snow and ice covers. Two sites, one of which is being 
monitored in conjunction with the University of 
New Hampshire, continue to operate, and the information 
gained from this research will lead to defining 
the winter influence of these critical areas and 
the impact on the functions and values during the 
winter low flow and spring runoff periods. 
Construction Productivity Advancement Research 
CRREL played an active role in the continued success 
of the CPAR program, a civil works research initiative 
to improve the productivity of the U.S. con- 
44-4

struction industry. Severe winter environmental 
conditions provide significant challenges to construction. 
CPAR provides an excellent opportunity 
to our industry counterparts to address the construction 
challenges presented by winter conditions. 
During FY92, CRREL was actively involved in 
seven projects. Three were started in FY90, three in 
FY91, and one was a new start that required the negotiation 
of a cooperative research and development 
agreement with an industry partner. The seven ongoing 
projects involve cost-shared research on concrete 
aggregates, cold regions pavements, landfill 
liner design, treatment of contaminated soils, concrete 
admixtures and bioremediation technologies. 
Project partners include three state transportation 
departments, two engineering design firms, and two 
construction material suppliers. 
In addition, two FY92 projects were selected for 
funding. The National Concrete Masonry Association 
is CRREL's partner in the area of cold weather 
masonry construction productivity. Cold weather 
construction procedures and materials that eliminate 
excessive cold weather protection requirements for 
newly installed masonry and that also will improve 
long-term durability of concrete masonry subjected 
to freezing will be developed and demonstrated. 
CRREL's partner in the area of remediation of 
haztox materials is Sound Environmental Services, 
Incorporated. This project will examine the dispersion 
by chemical reaction technology for remediating 
both organics and heavy metals in soils with 
special focus on cold regions. 
Work for Private Industry 
A major initiative at CRREL for the past three 
years has been the development of collaborative research 
efforts with private industry. The thrust of 
this effort has been to take advantage of existing legislation, 
such as the Stevenson-Wydler Act of 1980, 
the Federal Technology Transfer Act of 1986, and 
Section 318 of the Water Resources Development 
Act of 1990 to provide technical support and conduct 
cooperative research with private industry 
partners. This legislation allows Federal laboratories 
to enter cooperative research and development 
agreements (CRDAs) and technical assistance agreements 
(TAAs) with private industry partners. In the 
case of the Water Resources Act, technical assistance 
can be provided to U.S. firms competing for international 
work. 
During FY92, CRREL entered into seven CRDAs 
with several industry partners. Research topics included 
a study of seasonal pavement layer response 
for the Rhode Island Department of Transportation; 
a study of the use of scrap rubber as a road construction 
material for the Town of Richmond, Maine; design 
pavements for freeze-thaw conditions for the 
University of Alaska-Fairbanks; a study of the frost 
susceptibility of recycled glass/aggregate for road 
construction for the New Hampshire Department of 
Transportation; support of an Interim Barrier Technology 
workshop for Bovay Northwest, Inc.; support 
to further the understanding of the freezing 
process in various soils for Howard University; and 
evaluation of the performance of shallow tray aeration 
systems for the removal of volatile organics 
from groundwater for North East Environmental 
Products. This research provides an excellent opportunity 
to expand our customer base and leverage 
research dollars for increased mission effectiveness, 
while making our unique facilities and technical 
expertise available to industry partners. 
44-5

U. S. ARMY ENGINEER WATERWAYS 
EXPERIMENT STATION 
Organization and fwuctions. The U.S. Army Engineer 
Waterways Experiment Station (WES) is a field operating 
agency of the Chief of Engineers operating under the staff 
supervision of the Director, Research and Development Dr. 
Robert W. Whalin, PE, is Director. COL Leonard G. 
Hassell, Corps of Engineers, is Commander and Deputy Director. 
Dr. Dennis R. Smith is Associate Technical Director. 
The U.S. Army Engineer Waterways Experiment 
Station (WES) is the largest and most diverse civil and 
environmental engineering R&D complex in the world. 
It is a unique matrix managed complex of six laboratories 
with world-renowned expertise and facilities capable 
of solving a wide range of civil engineering related 
problems. The Tri-Service Reliance Strategy clearly evidences 
the significance of WES research capabilities. 
WES is the designated lead laboratory (category 3 Reliance-
to maintain the in-house expertise and facilities for 
technology base RDTE applicable to all Tri-Service requirements) 
for Airfields and Pavements, Sustainment 
Engineering, and Survivability and Protective Structures 
(major subareas of Civil Engineering Reliance panel). 
The Survivability and Protective Structures subarea includes 
assignment to WES of the Tri-Service lead in 
Fixed (and Semi-fixed) Facility Camouflage, Concealment, 
and Deception RDTE. WES is the Army lead laboratory 
in the Environmental Restoration subarea of the 
Reliance panel on Environmental Quality. WES operates 
the Army Supercomputer and is one of two regional 
processing centers under the Corps of Engineers Automation 
Plan (CEAP). The WES Army Computer Aided 
Design and Drafting (CADD) Center was designated the 
Tri-Service CADD/GIS (Geographic Information Systems) 
Center effective 1 October 1992. The Hydraulics 
Laboratory, the largest laboratory of its kind in the 
world, uses a wide range of working models and computer-
based numerical models for research and analysis 
of dams, levees, river and harbor projects, soil and 
streambank erosion, thermal pollution, etc. The Geotechnical 
Laboratory conducts research in soil mechanics, 
structural foundation design, embankment design and 
slope stability, seepage analysis, military pavements, 
engineering geology, rock mechanics, expedient surfacing, 
earthquake engineering, and mobility and trafficability. 
The Structures Laboratory uses theoretical, 
analytical, experimental, and modeling approaches to research 
the effects of nuclear and non-nuclear explosions, 
the response of structures to natural and explosive disturbances, 
and various construction materials including 
the testing, repair, and preservation of existing concrete 
structures. The Environmental laboratory researches the 
problems caused by man's activities with respect to the 
environment. Research programs include Dredged Material, 
Aquatic Plant Control, Environmental and Water 
Quality Operational Studies, Environmental Impact, 
Wetlands, and the Natural Resources Research Program. 
These and other programs of the Environmental Laboratory 
range through waste management, environmental 
regulations, and military aspects of terrain and 
camouflage. The Coastal Engineering Research Center 
conceives, plans, and conducts research and data collection 
in coastal/ocean engineering and nearshore oceanography 
to: provide a better understanding of waves, 
winds, water levels, tides, and currents; and provide 
scientific and engineering data and design criteria for 
materials as they apply to navigation improvements, 
flood storm protection, beach erosion control, recreation, 
and protection of structures in the coastal zone. The Information 
Technology Laboratory is responsible for all 
communications, mainframe computer functions for 
both technical and administrative applications, graphic 
presentations, and printed media at the station. 
WES Laboratories are engaged in research and 
engineering investigations in support of the civil and military 
missions of the Chief of Engineers. On a reimbursable 
basis, WES performs basic and applied research, develops 
state-of-the-art methods and techniques, tests materials and 
equipment, and provides consulting services for other federal 
and non federal agencies. 
WES maintains for the Corps of Engineers not only 
a scientific and engineering reference library but also an 
engineering computer programs library. WES operates 
DoD Informational Analysis Centers in the fields of 
Pavements and Soils Trafficability, Concrete Technology, 
Hydraulic Engineering, Soil Mechanics, and 
Coastal Engineering. 
During Fiscal year 1992, WES published 538 technical 
documents in-house including 175 Technical Reports, 
17 Contract Reports, 87 Miscellaneous Papers, 18 Instruction 
Reports, 5 video reports, and 236 special purpose technical 
documents. In addition to these documents, 45 
Information Exchange Bulletins on technical subjects were 
produced. WES engineers and scientists also submitted 
288 technical articles to refereed journals, and presented 75 
papers at national and international symposia. 
Operations and results during the period. Work accomplished 
at WES is initially financed by the Corps of 
Engineers Revolving Fund with direct reimbursement 
from agencies requesting research investigations and related 
services. The Station's total program during Fiscal 
Year 1992 was $183,754,120 which included 
$66,300,270 performed by contract. Of the total program 
$104,301,370 was oriented toward the civil and 
$79,452,750 toward the military. The plant replacement 
and improvement program was $3,502,500 for this 
period. 
45-1

U.S. ARMY TOPOGRAPHIC ENGINEERING CENTER 
ORGANIZATION AND FUNCTIONS 
The U.S. Army Topographic Engineering Center 
(TEC) is a world class laboratory whose primary 
technologies relate to accurate and graphic 
description of the earth's surface for both military 
and non-military applications. With new importance 
placed on construction efficiency and the regulation, 
recovery, sustenance, and enhancement of the earth's 
life-support systems, it has become increasingly 
urgent to develop effective tools for surveying and 
mapping, and for environmental monitoring and 
control. To meet this challenge, TEC scientists and 
engineers have developed faster, and more accurate 
and cost-effective ways to use remote sensing 
technologies to describe and characterize the surface 
of the earth. The tools and technology that TEC 
provided for the rapid deployment and precise 
management of forces in Desert Shield and Desert 
Storm can now be applied to environmental 
restoration and management. The ultimate success 
of the nation and the globe to creatively meet the 
environmental challenges of tomorrow could well 
depend on the successful adaptation of technologies 
that TEC has developed, largely for military 
purposes, to existing and new civil program 
applications. 
The extensive development of remote sensing 
technologies for use in construction, environmental 
rehabilitation, and resource management will give 
the nation the research and operational tools that it 
needs to both do a better and more complete job than 
would otherwise be possible, as well as to do that job 
more rapidly, more accurately, and at the lowest 
possible cost. 
The ability of TEC to cost-effectively participate in 
the Corps Civil Works Program is enhanced by its 
extensive on going efforts in the development of 
remote sensing technologies for both military and 
non-military applications. These efforts include 
multispectral image (MSI) and hyperspectral image 
(HSI) analysis, change detection, automated image 
registration techniques, development of advanced 
image compression techniques, MSI/HSI enhanced 
software development, development of the world's 
finest and most extensive spectral signature data 
base, computer-assisted stereo editing, 
photogrammetric interfaces with computer vision, 
research in HSI data processing and classification 
using neural networks, development of lap-top 
terrain analysis systems with Global Positioning 
System (GPS) capability, terrain visualization, and 
extensive modeling and simulation. 
TEC, currently developing the world's most 
complete spectral signature data base, along with the 
techniques and tools to use it, offers remote sensing 
exploitation technologies that could form an essential 
part of a new national approach to environmental 
management and control. These technologies include 
advanced and more efficient methods of surveying 
and mapping, as well as advanced methods of 
identifying problems and trends on the earth's 
surface. These tools can already accurately 
characterize many surface conditions, including 
certain types and conditions of vegetation and soils. 
With further development, these tools could be 
greatly enhanced to provide rapid and accurate 
determination of change in the biosphere for a wide 
and yet-to-be determined range of applications, to 
indicate both the location of point and non-point 
pollution sources as well as to warn of impending 
negative or positive environmental change. 
TEC looks forward to helping the nation increase 
its survey and mapping capability, improve its 
construction efficiency, and develop efficient 
environmental and resource management tools by 
adapting remote sensing technologies for civil 
program use. 
OPERATIONS AND RESULTS DURING FY92 
During FY92, TEC concentrated on developing 
new applications of rapidly advancing technology in 
the surveying engineering and mapping sciences, as 
well as to applying digital image processing to the 
wetland monitoring needs of the Corps districts. 
Considerable effort was devoted to transferring 
technology through field demonstrations, technical 
papers and reports, criteria documentation and 
formal classroom training. Technologies especially 
relevant to the Corps of Engineers include the Global 
Positioning System (GPS), Computer Aided Design 
and Drafting (CADD), Geographic Information 
Systems (GIS), and photogrammetry. 
Global Positioning System (GPS) 
The GPS is a satellite navigation, timing and 
ranging system developed by Department of Defense 
(DOD). Highly efficient measurements of position 
can be made with GPS using several techniques, 
with accuracies ranging from meters to millimeters. 
One of TEC's major thrusts in 1992 was the ongoing 
development of an extremely accurate threedimensional 
GPS-based positioning system for use by 
the Corps' hydrographic surveyors and the U.S. 
dredging industry. Great technological advances 
46- 1

Report of the Secretary of the Army on Civil Works Activities for FY 1992 
were made during 1992 that will allow engineers to 
position marine vessels to an accuracy of 4 inches, in 
all three dimensions, in real time. Although an 
operational prototype will not be available until late 
1993, Corps districts are already posturing 
themselves in anticipation of this new technology. 
TEC has aided the Corps districts and divisions 
successfully in the implementation of Differential 
GPS (DGPS) to the extent that they have great 
confidence in and call frequently upon the expertise 
of TEC. Assistance ranges from a variety of 
technical questions and training to helping in the 
establishment of regional and national 
implementation plans. A great deal of time, effort 
and funds have been saved in this manner. 
Computer Aided Design and Drafting (CADD) 
Dredge Volumes Study 
TEC engineers, in coordination with the National 
Institute of Standards and Technology (NIST), 
performed a detailed analysis of dredge volume 
computations. The traditional average-end-area 
technique and the new triangulated irregular 
network (TIN) techniques were used to compute 
volumes for several test cases. The TIN technique, 
which uses surface terrain model comparisons, was 
found to be more accurate and flexible than the 
average-end-area technique, and potentially offers a 
superior method for dredge volume computations. 
Results from the study were documented in an 
Engineer Technical Letter, which will provide U.S. 
Army Corps of Engineers districts with technical 
information for the effective use of average-end-area 
and TIN methods in their dredging missions. 
TEC also used the TIN method in an actual 
dredge project on an inland waterway. In 
coordination with the Baltimore District, before- and 
after-dredge volumes were computed using several 
different TIN programs. The results closely agreed, 
and the dredge contractor was paid based on these 
results. This pilot project confirmed the advantages 
stated in the Engineer Technical Letter. 
CADD Conversion Software 
TEC computer scientists produced a software 
package for Corps-wide distribution that creates 
Intergraph Design files from ASCII coordinate data. 
This software, program CVT-PC, is similar to the 
previously produced CVTDATA3-D, although the new 
software is for PC applications. With this program, 
users can create CADD graphics files from a user's 
survey data with his/her own descriptors and 
symbology. This program provides an important link 
between field survey data and CADD applications. 
Surveying Engineering 
Survey System Evaluation 
TEC engineers investigated new multibeam 
technology for hydrographic surveying. The 
Hydrographic Inland Marine Acoustic Platform (HIMAP), 
a survey system developed by John E. Chance 
and Associates Inc., uses a phased-array multibeam 
sounding transducer to provide dense and accurate 
bathymetric data for inland waterways. The HIMAP 
also uses real-time differential GPS for 
horizontal positioning, and an on-board computer 
system for all post-processing and plotting. TEC 
engineers conducted a carefully controlled, highly 
accurate survey, using conventional methods, of a 
revetment area on the Mississippi. This survey was 
then compared to one performed by the HI-MAP. 
The HI-MAP was found to provide accurate results 
at a coverage far more dense than conventional 
systems currently used in the Corps. The results 
have been documented in a TEC report. This 
evaluation also gave TEC engineers valuable 
experience in performing highly accurate or "ground 
truth" surveys for comparison to other systems. 
Standardized Hydrographic Survey System 
TEC engineers developed plans and specifications 
for a standard hydrographic survey system with 
primary emphasis on new Global Positioning System 
(GPS) technology. Based on a unanimous preference 
from Corps districts, TEC specified personal 
computer platforms for hydrographic data collection. 
The system is designed to work with or without other 
input devices such as heave compensators. This is 
possible through time-tagging all input ports based 
on the GPS Universal Time Coordinate (UTC). 
Cooperative Research and Development 
Agreement (CRADA) 
Global Positioning System Controlled 
Photogrammetry (GCP) 
This cooperative effort between the Topographic 
Engineering Center (TEC) and Photo Science Inc. 
will prove the feasibility and practicability of using 
a Global Positioning System Control-based 
Photogrammetry (GCP) system for mapping of civil 
activities with greatly increased efficiency and 
reduced cost. This will be accomplished with an 
airplane-based GPS receiver using differential carrier 
phase observations to position an aerial 
photogrammetric camera. The technology transfer 
effort will produce a fully configured system 
including software and documented procedures. 
Fully developed, GCP will reduce or even eliminate 
currently requisite ground control in the aerial 
46 - 2

photogrammetric process, thereby reducing product 
cost by up to 60 percent, and reducing preparation 
time for a single operation by weeks or even months. 
Construction Productivity Advancement 
Research (CPAR) 
Autonomous Construction Vehicle Navigation and 
Automation (Robotics) 
This development effort, part of the Construction 
Productivity Advancement Research (CPAR) 
program, utilizes a technology transfer partnership 
between the Topographic Engineering Center (TEC) 
and Caterpillar Inc. to develop a system to position, 
track, and maneuver mining and other construction 
equipment during their normal construction 
activities. This effort will assist Caterpillar Inc. to 
significantly increase the operational efficiency of its 
products by providing the ability to precisely position 
and navigate construction equipment in real time 
and with a positional accuracy of approximately 4 
inches. The positioning system uses the Global 
Positioning System. Use of this system will increase 
accuracy and efficiency of construction operations by 
reducing operator workload and by permitting 
development of autonomous systems, resulting in 
greatly increased productivity and 24-hour 
operational capability. Development of this product 
to its full potential will give Caterpillar Inc. and the 
entire U.S. construction industry a considerable 
competitive and technical advantage in the U.S. and 
international construction markets. 
Future uses of this technology outside this CPAR 
effort may permit integration within a total system 
that performs autonomous steering, braking, 
guidance, and vehicle control with little or no human 
interaction, resulting in an autonomously guided 
robotic construction vehicle. Extensions of this 
technology may find application in a wide range of 
existing and advanced forms of freight and passenger 
transportation, especially those ground-based 
systems operating at high speeds, such as Maglev or 
high-speed rail; those whose safety and reliability 
might be improved by its use, such as rail, truck, and 
air systems; and those systems for which autonomous 
or semi-autonomous operation are envisioned. 
Assistance to Districts 
TEC Monitors Wetlands with Digital Image 
Processing 
During FY92, TEC continued an important 
transition of off-the-shelf digital image processing 
technology from military and commercial to 
environmental applications through involvement in 
wetlands protection. The Corps of Engineers is the 
primary regulatory agency involved in the 
enforcement of Section 404 of the Clean Water Act, 
which involves protection and permitting activities 
for wetlands. To support this mission, TEC 
scientists and engineers are providing field operating 
activities support in digital image analysis, 
geographic information systems, and field work. 
Through use of the Terrain Information Extraction 
System (TIES), a state-of-the-art soft copy 
photogrammetric work station and image scanner, 
and the Global Positioning System, TEC scientists 
have exploited digitized multi-temporal imagery to 
identify and map man-made changes to several 
wetland'sites. Image maps have been produced to 
show these changes and have been used in the 
mitigation and litigation of various wetland 
violations. These projects have clearly shown the 
value of the analysis of historical imagery for 
monitoring environmental change. Further, 
demonstrations of PC-based image processing for 
wetlands delineation and change assessment have 
been conducted for the Baltimore, Norfolk, Omaha 
and Philadelphia District offices, and for other Corps 
representatives. In one case, TEC worked on a 
reimbursable basis to provide technical support for 
the Baltimore District's Regulatory Branch to obtain 
and install two Map and Image Processing Systems 
(MIPS). These systems are now being used in 
support of their Section 404 mission. 
Criteria Documentation 
Work has continued on writing and updating 
criteria documentation for the Corps. Preparation of 
the following documents are in progress, with many 
near completion: 
* EM 1110-1-1004 ...... Control, Precise and Geodetic 
Surveying and associated Guide Specification 
* EM 1110-2-1003 ....... Hydrographic Surveying - rewrite 
and associated Guide Specification 
" EM 1110-1-1005 ....... Topographic Surveying and 
associated Guide Specification 
* ETL 1110-1-152 ....... North American Vertical Datum of 
1988
The following reports were published in FY92: 
* TEC-0008 ............ Evaluation of the Bathyscan Sweep 
Survey System 
* TEC-0012 ............ An Evaluation of the Hydrographic 
Inland Marine Acoustic Platform (HIMAP) Survey 
System 
* TEC-0024 ............ "Investigation of the Real-Time 
Accuracy of the DGPS Method" 
* DRP-92-1 ............ Feasibility of a Kinematic 
Differential Global Positioning System 
* DRP-92-2 ............ Global Positioning System 
Bibliography 
46 - 3

THE WATER RESOURCES SUPPORT CENTER 
The Water Resources Support Center (WRSC) is a 
field operating agency under the staff supervision of the 
Director of Civil Works, Headquarters, U. S. Army Corps 
of Engineers. The Center consists of the Institute for 
Water Resources, the Navigation Data Center, the Washington 
Level Review Center and support elements. It is 
located at the Humphreys Engineer Center, Fort Belvoir, 
Virginia, with satellite elements at other locations, including 
the Hydrologic Engineering Center at Davis, 
California; and the Waterborne Commerce Statistics 
Center, part of the Navigation Data Center, in New 
Orleans, Louisiana. The accomplishments of WRSC 
during FY92 are listed by division. 
HYDROLOGIC ENGINEERING CENTER 
The mission ofthe Hydrologic Engineering Center is to 
support the Corps and the Nation in its water resources 
management responsibilities. This is accomplished 
through research, training, and technical assistance programs 
in hydrologic engineering and planning analysis. 
HEC makes every effort to be aware of the present needs 
and upcoming problems of the water resources community. 
HEC maintains continuous dialogue with universities, 
private industry, other Federal agencies, and state 
and local governments to keep abreast of latest developments. 
In FY92, HEC continued its commitment to move 
forward on several fronts: develop new generation hydrologic 
engineering software; document technical methods 
and guidance for reference by field offices and Corps 
partners; and continue to work closely with headquarters 
and field offices on high-priority projects. 
HEC continues to be convinced that engineering software 
for the 1990s will use powerful desktop computers. 
These machines include high-end Intel-chip based personal 
computers and RISC-chip based engineering workstations. 
These machines have great processing power 
and high quality interactive graphics capabilities. HEC's 
new software products are being developed for these 
desktop computers running UNIX in the case of workstations 
and Microsoft Windows for personal computers. 
HEC is developing the software so that it will perform 
quite similarly in both environments. 
HEC made excellent progress on its NexGen software 
development project, initiated in October 1990. The 
project is developing successor software packages to the 
existing family of HEC batch computer programs. 
Progress was advanced in this second year by teams 
developing prototype models for catchment analysis and 
river analysis. Design concepts, program architecture, 
coding languages and approaches, and graphics and data 
persistence recommended by the first-year teams were 
tested in the prototype model efforts. The teams surfaced 
and resolved a number of critical issues, and functioning 
prototype models were completed. The prototypes are 
now providing the basis for developing the beta versions 
of the models. 
HEC made important progress on a new reservoir 
operations analysis program. The program (called HECPRM) 
is a reservoir system operation optimization model 
developed for application in studies to update operation 
plans for existing reservoir systems. The model incorporates 
engineering, economic, and environmental objectives 
in an optimization framework. It implements a 
network-flow programming algorithm for monthly period-
of-record operation for an existing reservoir system. 
The preliminary model, applied to the Missouri River 
Main Stem Master Water Control Manual Update Study, 
has been substantially improved and applied to the 
Columbia River system for the System Operation Review 
Study. Initial Corps-wide release of the program is 
targeted for early in calendar year 1993. 
HEC has made a few enhancements and continues to 
actively support the mature versions of major batch 
programs HEC-1, HEC-2, HEC-5, HEC-5Q, HEC-6, 
UNET, and HEC-FDA, and released two new programs: 
HEC-IFH for interior flooding analysis; and DSSMATH 
that replaces MATHPAK and WCCOMP. HEC also 
released a new version of HEC-FFA for flood frequency 
analysis and updated the Unsteady Flow Program and 
user's manual. 
Progress continues on products for the Corps guidance 
development project and cost-share partner communications. 
Several more ERs addressing river hydraulics, 
catchment analysis, and flood damage reduction studies 
have either been published or final drafts have been sent 
to HQUSACE for processing. The new river hydraulics 
EM is completed and in publication. The new catchment 
analysis EM is in final processing for approval and 
publication. Documents describing hydrologic performance 
of flood control projects, explaining flood risk, and 
communicating flood facts were completed and were 
published as pamphlets. Several guidance products are 
nearing draft status and several new documents were 
initiated. Next fiscal year will see completion of many 
guidance products with reduced efforts in followingyears. 
Seven PROSPECT courses were conducted for a total 
of nine weeks of training. The courses covered a variety 
of hydrologic engineering and planning analysis topics. 
Attendance averaged about 31 students per course. Presentations 
on the Corps two-phased planning process, 
partnership arrangements with local agencies, life-cycle 
project management, and risk-based analysis are now 
emphasized in courses where appropriate. Eight workshops 
were also held totaling seven weeks of training. 
Topics presented included HEC-1, HEC-2, HEC-5, HEC- 
5Q, and HEC-DSS. One seminar was held and proceedings 
will soon be published on Initial Project Management 
Plans (IPMPs). 
Reimbursable project work was undertaken for nine 
Corps offices including districts, divisions, headquar- 
47-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
ters, and R&D laboratories. A research project undertaken 
for the Federal Emergency Management Agency, 
addressing performance of flood damage reduction measures 
on alluvial fans, was continued. The total reimbursable 
program was $830,000, with individual projects 
ranging from a few thousand dollars to over $100,000. 
Projects include watershed modeling, river hydraulics, 
water quality, flood frequency analysis, reservoir analysis, 
interior flooding, water control hardware replacement 
studies and related software development, and 
minor participation in the National Drought Study. 
The planned program for FY93 continues emphasis on 
development of technical guidance products in support of 
HQUSACE initiatives and concentrated efforts to develop 
new HEC software packages for engineering desktop 
computers. Training activities will be up to nine 
courses totaling ten weeks. Technical assistance will 
continue to be substantial. R&D funding will continue 
near past levels. The new R&D program in real-time 
water control scheduled to begin in FY93 was not funded 
and will not likely be resubmitted. 
INSTITUTE FOR WATER RESOURCES 
NAVIGATION DIVISION 
The IWR Navigation Division provides support to 
Corps field divisions and districts for project-specific and 
system studies of navigation improvements. It also 
provides support for the Inland Waterways Users Board 
and performs special studies as directed by the Office of 
the Chief of Engineers. The special studies address a 
variety of subjects where expertise in economic analysis 
is required, and range from assessment of transportation 
infrastructure to identification of economic impacts. 
Continuing Support Activities. The foundation for 
evaluation of navigation projects, both inland waterway 
and deep draft harbors, is the comparison of transportation 
costs with and without proposed improvements. The 
division maintains and annually updates data on ocean 
and inland waterway vessel operating costs, the dimensions 
of those vessels, the distribution of ocean vessel 
sizes in the world fleet, and the configuration of barge 
tows on inland waterways. 
Coordination of Navigation Studies. The Inland Waterways 
Users Board, created by the Water Resources 
Development Act of 1986, is charged with advising Congress 
on priorities for improving inland waterways. To 
provide information desired by the Board and by the 
Corps, the division leads a Corps Task Force which has 
evaluated 38 high priority inland navigation projects to 
determine the sequence which would maximize net national 
transportation benefits and observe the budget 
constraints imposed by the Inland Waterways Trust 
Fund. 
POLICY AND SPECIAL STUDIES DIVISION 
The Policy and Special Studies Division undertakes 
investigations, studies and research on current or emerging 
water resources and public works management issues 
and assists in the development of the Corps national 
water resources issues policy. The Division program for 
FY92 included policy analysis, strategic planning and 
major studies of wetlands mitigation banking, water 
management during drought, development of a Federal 
infrastructure strategy, and a separate program of policy 
and strategic studies focusing on implementing and 
improving the Corps legislated responsibilities. 
The Wetlands Mitigation Banking Study is reviewing 
and analyzing technical, legal, financial and other administrative 
aspects relevant to the establishment and 
operation of wetland mitigation banks. Also included is 
an evaluation of potential application to the Corps Regulatory 
Program and the feasibility of a demonstration 
program. Work on the study is scheduled to be completed 
in FY93. 
The National Study of Water Management During 
Drought has designed an archetypal water resources 
management approach which integrates long established 
planning principles and innovations in computer modeling, 
demand management, dispute resolution and public 
involvement. This method is results oriented, rather 
than process oriented, with two subsequent advantages 
over traditional planning methods. First, the outputs of 
the planning process itself (not just the alternatives 
studied) are quantified, which allows more effective 
management, including time and cost control. Second, 
the requirements for defining objectives and study team 
composition encourage every player to invest energy in 
the planning process, rather than litigation or lobbying 
after the planning budget is exhausted. This method has 
been tested and refined in four Drought Preparedness 
case studies across the country, and will be published in 
the Fall of FY93 at the conclusion of the National Drought 
Study. 
The Federal Infrastructure Strategy is designed to 
develop innovative ways to advance technical, administrative, 
governmental, public and private financing, economic 
policies, and other opportunities for improving 
infrastructure performance and ensuring more efficient 
investments. The program is being managed by the 
Corps as a cooperative, intergovernmental effort. Study 
development has involved representatives of Federal, 
state and local governments, numerous organizations, 
the academic community, and public works associations 
in a far-reaching dialogue of the barriers and opportunities 
to the delivery and management of the Nation's 
public works infrastructure. 
47-2

The FY92 projects included in the general policy studies 
program, among others, were the Global Change 
Program (representing Army in UNCED, IPCC, CEES), 
the Study of Dredged Material Management (Deep Draft), 
preparation of An Environmental Desk Reference, the 
Great Lakes Levels Reference Study, and work with the 
National Science Foundation on the Economic Impacts of 
Climate Change. 
TECHNICAL ANALYSIS AND RESEARCH 
DIVISION 
The Technical Analysis and Research Division responds 
to the water planning research needs of the field 
offices, as well as one-of-a-kind projects assigned by the 
Office of the Chief of Engineers. At the same time, 
technical assistance is given to Corps field divisions and 
districts. Staff members of the Technical Analysis and 
Research Division apply specialized knowledge in fields 
such as economics, environmental science, sociology and 
engineering, to develop and conduct a broad range of 
research aimed at producing practical and effective planning 
and management tools. Research outputs are applied 
in Civil Works (CW) throughout the Corps. 
During FY92, the Technical Analysis and Research 
Division was responsible for two long range research 
programs: Planning Methodologies and Risk Analysis 
Planning. 
Planning Methodologies and Risk Analysis focused on 
developing economic, financial, and environmental evaluation 
techniques for planning and operating flood control, 
navigation, and other water resources projects. 
Work included developing economic evaluation manuals, 
environmental planning guidelines, navigation project 
evaluation procedures, and flood control evaluation. 
An overview manual for evaluating National Economic 
Development benefits of water projects was produced 
as part of a comprehensive manual series. 
Also, guidelines to assist the planning of environmental 
mitigation have been published which incorporate 
economic considerations into the traditional biologically 
based mitigation planning process. The technique, incremental 
cost analysis, will greatly improve our ability to 
assure that mitigation plans are cost-effective as well as 
environmentally sound. 
The Risk Analysis area was expanded to include development 
of evaluation techniques which integrated planning 
and engineering reliability to be used in major 
rehabilitation studies. 
PROGRAM ANALYSIS DIVISION 
Created in 1991, IWR's newest division provides analytic 
and process management services in support of 
improving the effectiveness of Civil Works program execution. 
During FY92, the primary clients of the division 
were Programs Division, Operations and Management 
Division, and Project Management Division. 
Representative projects include the continued development 
of an incremental analysis procedure for prioritizing 
maintenance projects; the refinement of a database 
for making improved estimates of planning study 
attrition rates for the General Investigations (GI) program, 
and for creating improved cost commitment curves 
for estimating Construction General (CG) expenditures; 
the completion of a study of "lessons learned" for the 
Corps Reorganization Program Office; and, assistance to 
the Project Management Division in the completion of 
the revised Engineering Regulation 5-7-1 on the Project 
Management System. 
In addition, in FY92 the division administered the 
HQUSACE Process Action Team (PAT) process to facilitate 
the improvement of key headquarters business processes. 
Division personnel also designed and managed 
the PAT study on improving the Civil Works project 
review process. As part of its Alternative Dispute Resolution 
(ADR) program of reimbursable support, division 
personnel assisted Mobile District in developing a conflict 
management plan for the ACT/ACF comprehensive 
study, and successfully mediated a dispute over a levee 
alignment for the Kansas City District. 
NAVIGATION DATA CENTER 
The Navigation Data Center's mission is to collect, 
process, manage, and distribute information regarding 
the characteristics of the U.S. waterway system, including 
use, operation and performance, and physical aspects. 
Included is system-wide use data such as domestic 
and foreign commodity tonnage and ton-miles, passengers, 
vessel movements and lockages; physical facilities, 
vessels and waterways; and, operation and performance 
data for dredging and locks. During FY92, the Center 
focused on the design and development of new executive 
products for the decision-making process. In addition, 
NDC implemented standardized ORACLE relational 
database design for the major systems, and the majority 
of the data systems are linked via the CEAP communication 
environment. Geographic Information System navigation 
products were deployed at Headquarters. The 
modernization and integration of each data area continues. 
The Center consists of the Waterborne Commerce 
Statistics Center, the Ports and Waterways Division, the 
Waterways Systems Division, the Lock Performance 
Monitoring Program, and the Dredging Statistics Program. 
WATERBORNE COMMERCE STATISTICS 
CENTER (WCSC) 
In FY92, the Waterborne Commerce Statistics Center 
began producing advanced copies of the 1990 Waterborne 
47-3

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Commerce of the United States publication using their 
new computer software system. The revised publication 
format uses a new commodity classification system that 
is hierarchically compatible with the Lock Performance 
Monitoring System commodity codes which facilitates 
comparing the two data sets. The new format also 
includes subtotals for major commodity groups such as 
petroleum products, fertilizers, chemicals, iron and steel 
products, grains, etc. In addition, WCSC completed the 
design of a computer representation of the waterway 
network for the 50 states, Puerto Rico, Virgin Islands, 
and Pacific Islands in U.S. trust. It includes the inland 
waterway system, coastal channels, the Great Lakes, 
and major shipping lanes. WCSC's routing algorithm 
uses this waterway network to route vessel movements 
from origin to destination which enables through traffic 
and past-a-point computations. 
PORTS AND WATERWAYS 
Automated port facility information is being integrated 
into the overall NDC database. Latitude/longitude 
coordinates are being included in each facility record, 
as well as being computed for each waterway mile point, 
thereby forming a commonality for interagency dissemination 
of port and waterway information. Descriptive 
data encompassing over 9,300 docking facilities is resident 
in the NDC database. Focus for FY92 - Linkage 
across databases including key terms, data dictionary 
standardization. 
In FY92, five reports were completed: 
Number 
20A 
60 
61 
Title 
Mississippi River Ports Below and Above 
New Orleans, LA 
Pittsburgh, PA, and Ports on the Ohio, 
Monongahela, and Allegheny Rivers, PA 
Huntington, WV, Ports on Ohio River 
Miles 40-317, and Kanawha River, WV 
63 
70 
Louisville, KY, Ports on Ohio River Miles 
560-980, and Cumberland and Green 
Rivers 
St. Louis, MO, and Ports on Upper 
Mississippi River Miles 0-300 AOR 
LOCK PERFORMANCE MONITORING 
SYSTEM (LPMS) 
FY92 was a year of enhancing the LPMS Database 
System to provide management and executive information 
in quick, easily accessible and geographical display 
formats. This included the linkage of LPMS with Geographical 
Information Systems, creation of a summary 
file for an executive information system and transfer 
method to graphic software. A relational database design 
was completed to link LPMS with WCSC and the 
newly created Lock Characteristics database. 
DREDGING STATISTICS PROGRAM 
The Dredging Statistics Program entered Phase II of 
the planned three-phase approach in the development 
and full implementation of a national Dredging Information 
System. The Interim Dredging Information System 
(IDIS), a refinement of the 1991 prototype system, has 
been distributed to all Corps districts responsible for 
dredging contract administration. The database includes 
data elements that track a dredging contract from 
initial pre-bid stages through final execution. It also 
contains a representative latitude and longitude for all 
dredging and disposal sites for use in an integrated NDC 
data management system. Data entered at the districts 
are transmitted to the central database at NDC where 
data integrity and quality control procedures are executed. 
This national database, at the NDC, addresses 
other Corps, Federal, and private sector data requests. 
Database refinement and the establishment of improved 
communication links between the field and the NDC 
central database are ongoing. 
THE WASHINGTON LEVEL REVIEW CENTER 
The mission of the Washington Level Review Center 
(WLRC) is to review feasibility reports, post authorization 
change reports, detailed project reports where approval 
authority has not been delegated, general design 
memoranda, and other decision documents recommending 
USACE implementation that the Director of Civil 
Works may request. These reports address proposed 
water resource developments involving deep-draft harbors, 
inland navigation, flood damage reduction, fish and 
wildlife restoration and mitigation, hydroelectric power, 
water supply, recreation, beach erosion, hurricane and 
storm damage protection, and other related water resource 
needs. In addition to reviewing reports, during 
FY92, WLRC: 
a. Managed the concurrent Washington level review 
process for feasibility reports in which projects have been 
recommended for Corps implementation. 
b. Coordinated feasibility report review comments 
from Washington echelons and provided information to 
assist the Board of Engineers for Rivers and Harbors 
(BERH), the Chief of Engineers, the Assistant Secretary 
of the Army for Civil Works, and the Office of Management 
and Budget. 
47-4

c. Monitored and tracked the review and processing of 
feasibility reports recommending Corps action beginning 
with issuance of the division commander's public 
notice through project authorization. 
d. Provided all administrative support to the BERH 
and its advisory staff. 
e. Conducted professional training in water resources 
planning and project management as directed by the 
Chief of Engineers. 
WLRC managed the comprehensive review of 17 feasibility 
reports recommending USACE action. In addition, 
WLRC staff reviewed and provided written documentation 
for 40 design memoranda, 10 detailed project 
reports, 3 post authorization change reports, 19 feasibility 
reports recommending no USACE action, and 39 
miscellaneous documents. Also, staff members reviewed 
draft reports in preparation for attendance at 21 conferences. 
The WLRC Education and Policy Division conducted 
the Planners and Project Managers (PPM) Program. 
This program is an 11-month internship for Corps water 
resource planners and project managers from various 
areas of expertise who exhibit exceptional promise and 
demonstrate potential for advancement to positions of 
greater responsibility. There were 20 participants who 
graduated from this program in June 1992, including 6 
women. Instruction in the form of lectures, workshops, 
short courses, case studies, and field trips was presented 
by staff members ofWLRC, BERH, and HQUSACE, and 
by representatives from other government agencies and 
private consulting firms. Also, PPMs were assigned to 
work at HQUSACE for 6 weeks, and they taught the 
Planners and Project Managers Orientation Course for 2 
weeks in several Corps offices. 
47-5

PERMANENT INTERNATIONAL ASSOCIATION OF NAVIGATION CONGRESS 
(PIANC) 
The Permanent International Association of Navigation 
Congresses (PIANC) is an international organization 
consisting of approximately 40 national members, 
with headquarters in Brussels, Belgium. It is a clearinghouse 
where technology and experiences relating to ocean 
and inland navigation improvements are exchanged 
among engineers, scientists, port operators, and marina 
and vessel owners, to name a few. Its objective, broadly 
stated, is to promote the worldwide progress of inland 
and maritime navigation through the exchange of technical 
information on port and waterway development. 
The objective of the Association is met by holding International 
Congresses and by publishing quarterly technical 
bulletins and special reports. Special reports are 
published as a result of international research teams, 
called Working Groups, made up of those national members 
interested in the particular subject under study. 
Examples include methods of disposal of dredged material, 
means of combating oil spills, an international 
survey of dry dock facilities and their characteristics, the 
beneficial use of dredged material, and other various 
topics relating to port and waterway development. The 
organization also serves as an excellent source of identifying 
individual and corporate expertise throughout the 
world on PIANC-related subjects. Personal interchange 
of ideas and information also is promulgated by members 
attending the International Congresses held once every 
four years. 
The affairs of the Association are managed by a Permanent 
International Commission (PIC), composed of 
delegates from each member government. It is in this 
way that member governments are represented in PIANC. 
The number of delegates is determined by the size of the 
national membership, but may not exceed eleven per 
country. 
The United States has been a member of PIANC since 
1902 and has since provided an annual appropriation for 
the support and maintenance of the organization. This 
includes an annual subvention to PIANC International 
and payment of the travel expenses of properly accredited 
national delegates (Commissioners) of the United 
States to meetings of the International Commission and 
Congresses. Total appropriations for the U.S. Section, 
PIANC are currently $45,000 per year, including the 
annual subvention of approximately $12,000 to PIANC 
International. 
The United States Section is administered, by law, 
under the auspices of the Department of the Army (Corps 
of Engineers). The U.S. Section is composed of both 
individual and corporate members who pay their own 
membership dues. Membership of the U.S. Section on 
December 31, 1992, totaled 433, consisting of 356 individual 
members and 77 corporate members. 
Like all other member nations, the United States 
National Commission constitutes the governing body of 
the National Section. The ex-officio offices of the U.S. 
National Commission are: Chairman (Assistant Secretary 
of the Army (CW)); President (Director of Civil 
Works); and Secretary (Mr. DuWayne A. Koch). 
During calendar year 1992, U.S. National Commissioners 
were: Mr. J. Ron Brinson, President and Chief 
Executive Officer, Port of New Orleans; Mr. Charles F. 
Connors, Director of Maritime Services, Moffatt & Nichol, 
Engineers; Dr. Tudor T. Davies, U.S. Environmental 
Protection Agency; Dr. G. Edward Dickey, Office of the 
Assistant Secretary of the Army (Civil Works); Mr. John 
M. Pisani, Maritime Administration, U.S. Department of 
Transportation; Mr. Charles R. Roberts, Executive Director, 
Port of Oakland; Mr. R. Erik Stromberg, President, 
American Association of Port Authorities; and Dr. 
Alan R. Thomas, National Oceanic and Atmospheric 
Administration. 
The U.S. Section representatives to the two Permanent 
Technical Committees (PTCs) and Working Groups 
of PTCs were as follows: 
International Commission on the Environment - Dr. 
Robert M. Engler, USACE WES 
Permanent Committee for Developing Countries - 
Dr. Anatoly B. Hochstein, LSU/GW Ports and Waterways 
Institute 
Permanent Technical Committee I (Inland Waterways 
and Ports) - Major General Robert F. Seedlock, 
USA (Ret.) 
Working Group 1, Economic Implications of Inland 
Waterway Development - George Antle, USACE IWR 
Working Group 2, Disposal of Dredged Materials - 
Charles C. Calhoun, USACE WES 
Working Group 3, Consideration of Risk in Determining 
Bank Protection - Alan D. Crowhurst, River & Sea 
Gabions (Birmingham, U.K.) 
Working Group 4, Guidelines for the Design and 
Construction of Flexible Revetments Incorporating 
Geotextiles for Inland Waterways- Max Lamb, USACE 
LMVD 
Working Group 5, Container Transport with Inland 
Vessels - John M. Pisani, USDOT/MarAd 
Working Group 6, Brackish Water Penetration in 
Inland Canals and Rivers: Consequences, Control and 
Adaptation Measures - Christina E. Correale, USACE 
SAW
Working Group 7, Management of Dredged Material 
from Inland Waterways - Charles C. Calhoun, USACE 
WES 
Working Group 8, Automatic Management of Canalized 
Waterways and Its Hydraulic Problems - Jack R. 
Niemi, USACE LMS 
Working Group 9, Standardization of Inland Waterways' 
Dimensions, Dr. Anatoly B. Hochstein, LSU/GW 
Ports and Waterways Institute 
Working Group 10, Supervision and Control of Long 
Lateral Embankments - No U.S. Representative 
Working Group 11, Analysis of Cost of Operating 
Vessels on Inland Waterways - George Antle, USACE 
IWR 
Working Group 12, Design, Installation and Maintenance 
of Natural Vegetation Bank Protections Utilizing 
Geotextile Reinforcement for Inland Waterways - Max 
Lamb, USACE LMVD 
Working Group 13, Special Inland Waterway Craft - 
Charles F. Lehman, American Commercial Barge Line 
48-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
Co.
Working Group 14, Inland Waterway Craft and Pollution 
- Darrell D. Brown, International Maritime Organization 
(London, England) 
Working Group 15, Barge Fleeting--Jerry F. Lavelle, 
P.E., Tri-City Regional Port District 
Working Group 16, Coasters-No. U.S. Representative 
Working Group 17, Treatment and/or Disposal of 
Contaminated Dredged Material - U.S. Representative 
not appointed 
Working Group 18, Advanced Control of Locks and 
Bridges - U.S. Representative not appointed 
Permanent Technical Committee II (Maritime Ports 
and Seaways) - Mr. Thorndike Saville, Jr. (Retired) 
Working Group 1, Navigation in Muddy Areas - No 
U.S. Representative 
Working Group 2, Stability of Rubble Mound Breakwaters 
in Deeper Water- Eugene H. Harlow, Eugene H. 
Harlow, Inc. 
Working Group 3, Ice Navigation - C. Allen Wortley, 
University of Wisconsin 
Working Group 4, Dangerous Goods in Ports - No. 
U.S. Representative 
Working Group 5, Underkeel Clearance for Large 
Ships in Maritime Fairways with Hard Bottoms - Ronald 
C. Uhlin, Exxon International 
Working Group 6, Classification of Soils and Rocks to 
be Dredged - James W. Bean, C.F. Bean, Inc., New 
Orleans 
Working Group 7, Dimensions and Layout of One and 
Two-Way Channels and Fairways- Dr. Ernst G. Frankel, 
Massachusetts Institute of Technology 
Working Group 8, The Damage Inflicted by Ships with 
Bulbous Bows on Underwater Structures - Wesley 
Allen, Jr., Georgia Ports Authority 
Working Group 9, Development of Modern Marine 
Terminals - Charles R. Roberts, Port of Oakland 
Working Group 10, Disposal of Dredged Material at 
Sea - Robert Engler, USACE WES 
Working Group 11, Consequences of New Developments 
of Car/Passenger Ferries - No U.S. Representative
Working Group 12, Performance and Design Parameters 
of Rubble Mound Breakwaters - Robert Whalin, 
USACE WES 
Working Group 13, Floating Breakwaters - John 
Oliver, USACE NPD 
Working Group 14, Economic Methods of Channel 
Maintenance - DeWitt D. Barlow, Great Lakes Dredge 
and Dock Co. 
Working Group 15, Dry Docks - Michael Yachnis, 
Naval Facilities Engineering Command 
Working Group 16, Specification of Quantities and 
Related Risks on Maritime Transportation of Hazardous 
Chemicals and Wastes - Patrick Tobin, USEPA 
Working Group 17, Inspection, Maintenance and Repair 
of Maritime Structures Exposed to Material Degradation 
Caused by a Salt Water Environment - Charles 
F. Connors, Moffatt & Nichol, Engineers 
Working Group 18, Planning of (Commercial) Fishing 
Ports - No U.S. Representative 
Working Group 19, Beneficial Uses of Dredged Material 
- Jesse Pfeiffer, USACE CERD-C 
Working Group 20, Capacity of Ship Manoeuvring 
Models forApproach Channels and Fairways in Harbours 
- Haruzo Eda, Stevens Institute of Technology 
Working Group 21, Flexible Revetments in the Marine 
Environment - Gene Chatham, USACE WES 
Working Group 22, Armored Slopes Under Piled Piers 
- Dennis V. Padron, Han-Padron Associates 
Working Group 23, Site Investigation Requirements 
for Dredging - Richard M. Lowry, Great Lakes Dredge 
and Dock Co. 
Working Group 24, Movement of Moored Ships - 
Gary K. Greene, LPA Group, Inc. 
Working Group 25, Coastal Instrumentation - U.S. 
Representative resigned 
Working Group 26, Means of Combating Oil Spills - 
U.S. Representative resigned 
Working Group 27, Artificial Islands - Dr. Ernst G. 
Frankel, Massachusetts Institute of Technology 
Working Group 28, Breakwaters with Vertical and 
Inclined Concrete Walls - U.S. Representative not appointed 
Working Group 29, Recommendations for By-Pass 
Systems for Harbours on Sandy Coasts - J. Richard 
Weggel, Drexel University 
Working Group 30, Dimensions of Channels and Fairways-
A Practical Guide - U.S. Representative not 
appointed 
Special Commission on Sport and Pleasure Navigation 
- John M. Nichol, Moffatt & Nichol, Engineers 
(Retired) 
Working Group 1, Ecological Conservation in Relation 
to Sport and Pleasure Navigation - Neil W. Ross, International 
Marina Institute 
Working Group 2, Wave Climate Criteria for the 
Design of Yacht Harbors and Marinas - Orson Smith, 
Anchorage, AK 
Working Group 3, Provision of Navigation Aids for 
Pleasure Craft - Austin E. Brant, Jr., TAMS 
Working Group 4, Chartering Services-Their Growth 
and Impact on Sport and Pleasure Navigation - Eugene 
H. Harlow, Eugene H. Harlow, Inc. 
Working Group 5, Guidance on Facility and Management 
Specifications for Marine Yacht Harbours and 
Inland Waterway Marinas with Respect to User Requirements- 
William A. Jansen, McClure Engineers Associates 
Working Group 6, Use ofJetskis and Similar Personal 
Powered Craft on Controlled Waters - Roger F. Hagie, 
Kawasaki Motors Corp. 
Working Group 7, Marine Sanitation Pumpouts - 
U.S. Representative not appointed. 
48-2

INTERNATIONAL BOUNDARY WATERS BOARDS 
In order to carry out United States obligations under 
international agreements, the Office of the Chief of 
Engineers and several Corps Divisions and districts with 
jurisdiction over areas bordering Canada have representation 
numerous international boards, committees, 
and other groups. The majority of these boards were 
established by the International Joint Commission (IJC) 
as empowered in accordance with the provisions of the 
Boundary Waters Treaty of 1909 between the United 
States and Great Britain (for Canada). IJC boards fall 
into two broad categories: boards of control, which are 
more or less permanent and supervise compliance over 
an IJC order; and engineering, technical, or study 
boards, which are usually dissolved after completing and 
reporting on an investigation assignment. In addition to 
boards created by the Commission, other international 
boards and committees are created by treaties or other 
arrangement in matters concerned with the water resources 
ofjoint interest, and the members report directly 
to the Governments or establishing agency. International 
boundary waters boards and committees having 
Corps of Engineer memberships during the fiscal year 
are listed in Table 49-1. For an explanation of the 
constitution of the various boards and committees, see 
the FY 77 and FY 80 annual reports. An innovative study 
organization, neither a board nor a committee, was 
established to initiate a study of impact from fluctuating 
Great Lakes levels pursuant to a Reference to the IJC 
from the Governments of Canada and the United States, 
dated August 1, 1986. A discussion of that study organization, 
which has since appointed a formal study board, 
follows Table 49-1. 
TABLE 49-1 
IJC BOARDS HAVING CE MEMBERS 
BOARD NAME 
1. Int. Lake Superior 
2. Int. St. Croix River 
3. Int. Lake of the Woods 
4. Int. Lake Champlain 
5. Int. Kootenay Lake 
6. Int. Rainy Lake 
7. Int. Osoyoos Lake 
8. Int. Niagara 
9. Int. St. Lawrence River 
10. Int. Skagit River 
11. Int. Souris River 
12. Int. Souris-Red Rivers 
Engineer 
13. Int. Champlain-Richelieu 
14. Int. Great Lake Diversios 
and Consumptive 
Uses Study 
15. Int. Great Lakes Technical 
Information Network 
Board 
YEAR 
ESTABLISHED 
1914 
1915 
1925 
1937 
1938 
1941 
1943 
1953 
1953 
1967 
1959 
1948 
1975 
1977 
1979 
*Signifies U.S. Section Chairman. 
UNITED STATES REPRESENTATION 
*Div. Engr., NCD 
*Div. Engr., NED 
*Dist. Engr., St. Paul 
*Dist. Engr., New York 
*1. Dist. Engr., Seattle 
2. Dept. of Interior, USGS, Boise, ID 
*Dist. Engr., St. Paul 
1. Dist. Engr., Seattle 
*2. Dept. of Interior, USGS, Tacoma, WA 
3. Washington State Parks & Recreation Commission, 
Olympia, WA 
* 1. Div. Engr., NCD 
2. Dept. of Energy, FERC, Washington, D.C. 
*1. Div. Engr., NCD 
2. St. Lawrence-Eastern Ontario Commission, 
Waterton, NY 
3. NY Power Authority, Massena, NY 
*Dist. Engr., Seattle 
1. Dist. Engr., St. Paul 
*2. ND State Engr., Bismark, ND 
3. Dept. of Interior, USGS, Bismark, ND 
1. Dist. Engr., St. Paul 
*2. Dept. of Interior, BOR, Washington, D.C. 
3. Dept. of Interior, USGS, Reston, VA 
*1. New York Dept. Environ. Conser. 
2. Dist. Engr., New York 
3. Vermont Agency Environ. Conser. 
4. New England River Basins Commision, Staff Associate 
5. Dept. of Interior F&WS Boston, MA 
*1. Div. Engr., NCD 
2. Michigan Dept. Nat. Res. 
3. Illinois Dept. of Trans. 
4. Pennsylvania Dept. of Envir. Res. 
5. Dept. of Energy, FERC, New York, NY 
* 1. CENCE-ED, Detroit, MI 
2. Great Lakes Environmental Research Lab., NOAA, 
Ann Arbor, MI 
3. USGS, Reston, VA 
49-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
OTHER INTERNATIONAL BOARDS OR GROUPS HAVING CE MEMBERS 
BOARD NAME 
16. Int. Lake Memphremagog 
17. Coordinating Committee 
on Great Lakes Basic 
Hydraulic and Hydrologic 
Data 
18. Int. Niagara Committee 
19. Columbia River Treaty 
Entities 
20. Columbia River Treaty 
Permanent Engineering 
YEAR 
ESTABLISHED 
1920 
1953 
1955 
1964 
1964 
*Signifies U.S. Section Chairman. 
Study of Fluctuating Great Lakes Levels Under the 
August 1, 1986, Reference. 
In 1986, the Governments of Canada and the United 
States issued a reference to the IJC to study methods to 
alleviate the adverse consequences of fluctuating water 
levels in the Great Lakes-St. Lawrence River basin. The 
IJC was requested to address the immediate high lake 
level crisis and identify and evaluate intermediate and 
long-term potential measures, while considering such 
vital matters as domestic waste supply and sanitation, 
navigation, agriculture, shore property, flood control, 
wildlife and others. The IJC is to determine the full costs 
and benefits of any works or measures and indicate how 
the various interests on either side of the boundary would 
be affected. Compensatory works or measure to offset 
costs to the interests which may be adversely affected by 
any proposed regulatory measures also must be determined. 
The IJC proceeded with its reference responsibilities 
on three tracks. First, it submitted an initial report to the 
federal governments on November 14, 1986, listing immediate 
actions that could be taken to lessen damages 
from the then current high water levels. Second, the IJC 
formed a taskforce to evaluate measures which could be 
implemented within approximately one year to reduce 
high lake levels. The third track is the comprehensive 
study of long-term measures. 
UNITED STATES REPRESENTATION 
*Dist. Engr., New York 
*1. Eng. Div., North Central Div. 
2. Dept. of Commerce, NOAA, Rockville, MD 
* Div. Engr., NCD 
1. Div. Engr., NPD 
*2. Bonneville Power Admin., Portland, OR 
*1. HQUSACE, CECW-ZB, Washington, D.C. 
2. Dept. of Energy, Tulsa, AR 
The IJC, through the U.S. Department of State, requested 
by letter dated November 24, 1986 that the 
Corps of Engineers provide lead agency support on what 
became known as the Levels Reference Study. The 
Division Commander, NCD assumed the role of U.S. 
Chair of a multi-discipline study group which functioned 
as a Project Management Team. The team consisted of 
five functional groups co-chaired by U.S. and Canadian 
representatives. The Canadian counterpart to the Corps 
of Engineers was Environment Canada. A Plan of Study 
was completed in April 1987. The plan called for a twophase 
study with the initial phase emphasizing problem 
identification and a program of measures for detailed 
study and evaluation in Phase II. The Phase I progress 
report was submitted to the IJC in July 1989. 
After a period of public review in February 1990, the 
IJC issued a directive for the Phase II study, which 
included the appointment of a ten-member Levels Reference 
Study Board. The Board appointed a full-time study 
director and a 18-member Citizens Advisory Committee. 
Upon completion of the Phase II Plan of Study in May 
1990, the Board also appointed four Working Committees 
to carry out the detailed study plan. The working 
committees are: (1) Public Participation and Information; 
(2) Land use and Management; (3) Existing Regulation, 
System-wide Regulation, and Crisis Conditions; 
and (4) Principles, Measures Evaluation, Integration 
and Implementation. 
49-2

INVESTIGATION OF PROJECTS UNDER FEDERAL POWER ACT 
Federal Water Power Act of June 10, 1920 created the 
Federal Power Commission (in 1377 named the Federal 
Energy Regulatory Commission, FERC) composed of the 
Secretaries of War, Interior, and Agriculture, with authority 
to grant permits and licenses for hydroelectric 
development in all water over which Congress has jurisdiction. 
The act further required that work of the Commission 
be preformed by and through the Department of 
War, Interior and Agriculture and their engineering, 
technical, and other personnel except as may be otherwise 
provided by law. By an act of June 23, 1930, entitled 
"An Act to reorganize the Federal Power Commission" 
Sections 1 and 2 of the Federal Water Power Act of 1920 
were amended. A commission was provided for, to be 
composed of five commissioners to be appointed by the 
president, by and with the advice and consent of the 
Senate. The necessity of performing work through the 
departments of War, Interior and Agriculture was removed 
and the Commission was authorized to appoint 
such officers and employees as necessary in executing its 
function. By Title II, Public Utility Act of 1935, the 
original Federal Water Power Act was made Part I of the 
Federal Power Act, and Part II and III were added to the 
act. On October 1,1977, pursuant to the provisions of the 
Department of the Energy Organization Act (DOE Act), 
Public Law 991 Stat. (August 4, 1977) and Executive 
Order No. 12009, Federal Regulation 46267 (September 
1, 1977), the Federal Power Commission ceased to exist 
and its functions and regulatory responsibilities were 
transferred to the Secretary of the Energy and the Federal 
Energy Regulatory Commission (FERC) which, as 
an independent commission within the Department of 
energy was activated on October 1, 1977. 
Section 4(e) of the Federal Power Act provides that no 
water power license affecting navigable capacity of any 
navigable waters of the United States shall be issued 
until plans of the dam or other structures affecting 
navigation have been approved by the Chief of Engineers 
and the Secretary of the Army. By an action, notice of 
which was published in the Federal Register Volume 40, 
Number 74, dated April 16, 1973, the Secretary of the 
Army delegated to the Chief of Engineers his authority 
under Section 4(e) of the Federal power Act. The Chief of 
Engineers on 5 September 180 delegated to the Corps 
division engineers the authority for Section 4(e) approval 
of the plans for non-Federal hydropower development 
affecting navigation. 
The following work of an engineering nature was 
accomplished by the Corps division and district offices 
under the direction of the Chief of Engineers during the 
fiscal year: (1) 308 applications from non-Federal entities 
for planning, design, construction and operation of hydropower 
projects were reviewed and appropriate recommendations 
in the interest of flood control, navigation, 
structural safety, and environmental impacts, relative to 
Corps projects, were furnished to the FERC; (2) 24 
licensed power plants were in various stages of design 
review and approval for addition of power at Corps dams; 
and (3) 6 COPE approved non-Federal power plants were 
in active construction stages by the end of the fiscal year. 
The Corps bills FERC licensees for the cost incurred 
by the Corps for reviewing and approving final design, 
plans and specifications for construction of power plants 
at Corps projects. In FY 92 the total cost reimbursement 
to the Corps for this service was $ 197,294. Review and 
approval of license applications for hydro development at 
non-Corps dams are funded by the Corps as a line item in 
the General Investigation Account. In FY 1992, the cost 
of this activity was $ 00,000. This cost was reported to 
FERC for the Commission's assessment of annual charges 
to licensees. 
50-1

REGULATORY, SUNKEN VESSEL REMOVAL & 
NATIONAL EMERGENCY PREPAREDNESS ACTIVITIES 
1. Regulatory Activities 
Authorities. The following authorities charge the 
Corps of Engineers with the regulation of various waterrelated 
construction activities: Sections 9 and 10 of the 
River and Harbor Act of 1899 (structures in an alteration 
of waterways, e.g., boat docks); Section 103 of the Marine 
Protection Sanctuaries Act of 1972 (ocean dumping); and 
Section 404 of the Clean Water Act (discharge of dredged 
and fill material). 
Work Completed. During FY 1992, the Corps received 
approximately 15,100 applications for permits 
and issued about 5,400 permits and 3,300 letters of 
permission. In addition about 16,000 activities were 
authorized by regional or statewide permits which did 
not require individual applications from the public. More 
than 50,000 other minor activities were authorized by 
the Corps' nationwide permits. 
Significant improvements were made in several areas 
of the regulatory program during Fiscal Year 1992. 
Pursuant to Section 404(q) of the Clean Water Act, 
regulatory agreements with the Departments of Commerce 
and Interior and the Environmental Protection 
Agency were revised. The agreements streamline the 
regulatory process by reducing unnecessary delays caused 
by the "threat" of elevation, i.e., the agencies' power to 
refer final decision on permits to Washington. This 
threat was not only unfair to applicants but also caused 
substantial additional work effort for the Corps - for no 
reason. 
In May of 1992, the Corps issued formal guidance 
clarifying its role as the decision maker in the permit 
process. Comments from the agencies continue to be 
actively used in the process. The agencies concurred in 
their recognition of the Corps as solely responsible for 
making final permit decisions. As a result, permit 
decisions can be made on a more timely basis with full 
opportunity for agencies to provide substantive in put. 
During FY 92 the wetlands delineation problem was 
diffused thru adoption of the Corps 1987 wetlands manual 
for identifying and delineating wetlands. Difficulties 
with an interagency manual published in 1989 had 
become a national environmental issue. In August 1991, 
as an interim solution to the problem, the Corps began 
using its 1987 manual to delineate wetlands. The manual 
proved to be a successful tool through FY 92 and the 
Corps worked with the administration and EPA to formally 
adopt the Corps 87 manual. 
In August 1992, the Corps and EPA jointly proposed 
regulation changes in the Federal Register to close a 
loophole in the 404 regulations that has allowed discharges 
of excavated material in conjunction with wetlands 
drainage activities to go unregulated. The changes 
also clarify the definition of discharge of dredged material, 
define when pilings are regulated under Section 404, 
and codify the Corps 1990 regulatory guidance that 
exempts prior converted croplands from 404 regulation. 
Over 6,000 comments were received on this proposal - 
mostly favorable. 
During FY 92 the Corps began an initiative to promote 
the use of state programmatic general permits. These 
permits reduce duplication of effort between the Corps 
and states by reducing Corps review of minor activities 
that are already covered by state programs. 
TABLE 51-A 
GENERAL REGULATORY FUNCTIONS 
Obligations 
Unobligated Balance - 30 Sep 91 ......... $ 2,328,907 
Allotments ..................... ................ 86,000,000 
Total Funds Available ........................ 88,328,907 
Obligations.................... ................... 86,216,895 
Unobligated Balance - 30 Sep 92 ........... $ 2,112,021 
Expenditures 
Unexpended Balance - 30 Sep 91 ........... $ 4,330,329 
Allotment ...................... ............... 86,000,000 
Total Funds Available ....................... 90,330,329 
Expenditures ...... ................ 85,170,678 
Unexpended Balance - 30 Sep 92 ........... $ 5,097,813 
2. Investigation and Removal of Sunken Vessels 
Under the authority of Sections 19 and 20 of the 
River and Harbor Act of 1899, the Corps of Engineers 
investigated sunken vessels in navigable waters and 
removed those obstructing navigation. For obligation 
expenditures, see Table 51-B. 
TABLE 51-B 
REMOVAL OF SUNKEN VESSELS 
Obligations 
Unobligated Balance - 30 Sep 90 ........... $ 
A llotm ents ............................................. 
Total Funds Available .................... 
O bligations................ ..... .............. 
Unobligated Balance - 30 Sep 91 ........... $ 
Expenditures 
Unexpended Balance - 30 Sep 90 ......... $ 
Allotments ....................... 
Total Funds Available ..................... 
Expenditures ..... ......... ............ 
Unexpended Balance - 30 Sep 91 ........... $ 
282,191 
592,456 
874,647 
853,272 
21,375 
314,392 
592,456 
906,848 
878,318 
28,530 
51-1

REPORT OF THE SECRETARY OF THE ARMY ON CIVIL WORKS ACTIVITIES FOR FY 1992 
3. National Emergency Prepardness Activities 
Authorities. Executive Order 12656, as 
amended, assigns responsibilities to executive departments 
and agencies in order to undertake the national 
emergency planning and preparedness necessary to develop 
an effective national capability to meet essential 
civilian and defense needs during major domestic emergencies 
and national securities emergencies. 
Status. During FY 92, the Corps of Engineers 
continued its effort to improve the command readiness 
posture and its ability to respond to various national 
emergencies. Emphasis was placed on the initiation of 
activities which would contribute to the successful transition 
in program emphasis that is required as a result of 
the end of the "cold war" era, and the attendant new 
military strategy, as well as the evolving philosophy 
associated with natural disaster preparedness and response. 
This included the continuation of Engineer Command 
Readiness Program (ECRP) activities. During FY 
92, ECRP activities were designed to address Corps 
readiness roles and responsibilities for the 1990's (and 
into the 21st century) as well as the resources and 
organization required to accommodate them. Consideration 
of Corps roles associated with Military Support to 
Civil Authorities, as outlined in the new Department of 
Defense Directive 3025.1, were included in this effort. 
Other activities included a continuation of the planning 
for and maintenance of emergency facilities needed to 
support continuity of operations and increased emphasis 
on the planning required to meet the Nation's water 
needs during a national emergency. In the latter case, 
Executive Order 12656 has tasked the Corps of Engineers 
to be the Executive Agency responsible for emergency 
water planning. For fiscal year obligations and 
expenditures, see Table 51-C. 
TABLE 51-C 
NATIONAL EMERGENCY PREPAREDNESS 
Obligations 
Unobligated Balance - 30 Sep 91............ $ 693,406 
Appropriations FY 92 ........................... 7,692,800 
Total Funds Available .......................... 8,386,206 
Obligations......................... 7,181,103 
Unobligated Balance - 30 Sep 92............ $ 1,205,103 
Expenditures 
Unexpended Balance - 30 Sep 91 ....... $ 
Appropriations FY 92 .............................. 
1,380,183 
7,692,800 
Total Funds Available .......................... 9,072,983 
Expenditures ..................... 7,192,738 
Unexpended Balance - 30 Sep 92 ........ $ 1,880,245 
51-2

NATURAL DISASTER PREPAREDNESS RESPONSE AND RECOVERY ACTIVITIES 
Activities. Disaster preparedness activities included 
the review and update of existing emergency response 
plans, creation of generic division and district plans, 
training response personnel, procurement and maintenance 
of critical supplies and equipment used during 
emergency response activities, upgrading emergency 
operation centers, coordination with Federal, State and 
local response agencies, and development of training 
courses to support USACE missions under the Federal 
Response Plan. 
Through the winter several series of storms caused 
flooding in Arizona, Southern California, Southeast and 
Southcentral Texas, Iowa, Ohio and Western New York. 
Response efforts included emergency contracting, reservoir 
control, sandbags,, and technical assistance. With 
the spring came the Great Chicago Tunnel Flood. Water 
from the Chicago River entered a breached freight tunnel 
system located under the City of Chicago. The resultant 
flooding filled subbasements of multi-story buildings, 
disrupted power, closed the subway system, and required 
the evacuation of the Flood Area for several days. FEMA 
tasked the Corps of Engineers to stop the flow of water 
into the tunnel and dewater the tunnel system. The 
Corps successfully plugged the breach and drained the 
system. At the peak of operations 150 personnel were 
involved in the mission and contracts totalling more 
than $57 million were awarded. Late August saw the 
arrival of Hurricane Andrew in Florida and Louisiana, 
and Typhoon Omar in Guam. Hurricane Andrew was the 
costliest disaster in U.S. history estimated at $20 billion. 
There was widespread devastation, more than 50 people 
had died, and over 200,000 people were left homeless. 
FEMA authorized the Cops of Engineers to expend $382 
million in response and recovery missions that included 
debris clearance, removal and disposal; garbage removal; 
school repair; potable water and ice; technical assistance; 
temporary shower and laundry facilities; temporary 
roofing generators to support public utilities; and preparation 
of damage survey reports. The U.S. Air Force 
authorized the Corps $15 million for missions on Homestead 
AFB. For Typhoon Omar in Guam, FEMA tasked 
USACE to restore power, place plastic sheeting as temporary 
roofing, provide potable water, and complete 
Damage Survey Reports. September brought with it 
Hurricane Iniki to the island of Kauai, Hawaii. This tie 
FEMA authorized USACE $40.5 million for response and 
recovery missions. Again, the Corps provided temporary 
roofing, potable water, ice, debris clearance, and technical 
assistance. Hurricane Andrew and Iniki brought 
several hundreds of Corps employees together to accomplish 
these missions. Never before had so many Federal, 
state, and local agencies worked together to achieve a 
common goal. 
52-1

APPENDIX A 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
ALASKA 
Chena River Lakes 
ARIZONA 
Adobe 
Alamo 
Cave Buttes 
Dreamy Draw 
New River 
Painted Rock 
Tat Momolikot 
Whitlow Ranch 
ARKANSAS 
Blakely Mountain 
Dam 
Blue Mountain 
DeGray 
DeQueen 
Dierks 
Gillham 
Millwood 
Narrows Dam 
Nimrod 
CALIFORNIA 
Black Butte 
Brea 
Buchanan Dam- 
H.V. Eastman Lake 
Carbon Canyon 
Coyote Valley 
Dry Creek 
(Warm Springs) 
Lake and Channel 
Farmington 
Fullerton 
Hansen 
Harry L. Englebright 
Hidden Dam- 
Hensley Lake 
Isabella 
Lopez 
Martis Creek 
Merced County 
Stream Group: 
Bear 
Bums 
Mariposa 
Owens 
Mojave River 
New Hogan 
North Fork 
Pine Flat 
Prado 
San Antonio 
Santa Fe 
Sepulveda 
Yukon 
-Kuskokwim 
Gila 
Colorado 
Gila 
Gila 
Gila 
Gila 
Gila 
Gila 
Chena River 
Skunk Creek 
Bill Williams River 
Cave Creek 
Dreamy Draw 
New River 
Gila River 
Santa Rosa Wash 
Queen Creek 
Ouachita Ouachita 
Arkansas 
Ouachita 
Red 
Red 
Red 
Red 
Ouachita 
Arkansas 
Petit Jean River 
Caddo 
Rolling Fork River 
Saline River 
Cossatot River 
Little River 
Little Missouri 
Fourche La Fave River 
Sacramento Stony Creek 
Santa Ana Brea Creek 
San Joaquin Chowchilla River 
Santa Ana Carbon Canyon River 
Russian East Fork 
Russian River 
Russian 
San Joaquin 
Santa Ana 
Los Angeles 
Sacramento 
San Joaquin 
San Joaquin 
Los Angeles 
Sacramento 
San Joaquin 
San Joaquin 
San Joaquin 
San Joaquin 
Mojave 
San Joaquin 
Sacramento 
San Joaquin 
Santa Ana 
Santa Ana 
San Gabriel 
Los Angeles 
Dry Creek 
Littlejohn Creek 
East Fullerton Creek 
Big Tujunga Wash 
Yuba River 
Fresno River 
Kern River 
Pacoima Wash 
MartiCsr eek 
Bear Creek 
Bums Creek 
Mariposa Creek 
Owens Creek 
Mojave River 
Calaveras River 
American River 
Kings River 
Santa Ana River 
San Antonio Creek 
San Gabriel River 
Los Angeles River 
Fairbanks 
Phoenix 
Wenden 
Phoenix 
Phoenix 
Phoenix 
Gila Bend 
Casa Grande 
Superior 
Hot Springs 
Paris 
Arkadelphia 
DeQueen 
Dierks 
Gillham 
Ashdown 
Murfreesboro 
Plainview 
Orland 
Fullerton 
Chowchilla 
Brea 
Ukiah 
Healdsburg 
Farmington 
Fullerton 
Los Angeles 
Marysville 
Madera 
Bakersfield 
San
Fernanado 
Reno 
Merced 
Merced 
Merced 
Merced 
Victorville 
Valley 
Springs 
Auburn 
Piedra 
Corona 
Upland 
Duarte 
Van Nuys 
1979 2,000 NPP FR 
1982 18,350 
1968 1,046,310 
1979 46,600 
1973 320 
1985 43,520 
1959 2,476,340 
1974 198,550 
'960 34,500 
NPP FR 
560 FRWX 
NPP FRX 
NPP FRX 
NPP F 
NPP FRWX 
NPP GWX 
NPP FX 
1955 2,768,500 20,900 FP 
1947 257,900 
1971 881,900 
1977 136,100 
1975 96,800 
1975 221,800 
1966 1,854,930 
1949 407,900 
1942 336,010 
2,910 FRWX 
6,400 FRZRS 
1,680 FSQRW 
1,360 FSRAW 
1,370 FSQW 
29,200 FSW 
2,500 FP 
3,550 FSWX 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
50 40,200 
109 2,275 
283 975 
109 2,275 
50 448 
104 2,320 
1281 4,780 
75.5 12,500 
149 637 
235 1,100 
Earth 115 2,800 
Earth 243 3,400 
Earth 160 2,360 
Earth & Rock 153 2,500 
Earth & Rock 160 1,750 
Earth 88 17,554 
Concrete 175 941 
Concrete 97 1,012 
1963 160,000 770 FIRX Earth 156 2,970 
1942 4,010 NPP FRX Earth 87 1,765 
1975 150,000 470 FIRW Earth & Rock 205.5 1,800 
1961 6,610 NPP FERX 
1959 122,500 1,700 FRX 
1983 381,000 
1952 52,000 
1941 760 
1940 25,450 
1941 69,000 
1975 90,000 
1953 570,000 
1954 440 
1971 20,400 
1954 7,700 
1950 7,000 
1948 15,000 
1949 3,600 
1971 89,670 
1963 325,000 
1939 14,700 
1954 1,000,000 
1941 196,240 
1956 7,700 
1948 22,110 
1941 17,430 
500 FRSW 
NPP F 
NPP FRX 
120 FRWX 
400 DR 
5,000 FIRW 
1,850 FIRW 
NPP FX 
71 FSR 
NPP F 
NP F 
NPP F 
NPP F 
NPP FRWX 
715 FIRX 
280 DR 
NPP FIRX 
NPP FRX 
NPP FX 
NPP FRX 
NPP FRX 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth & Rock 
Concrete 
Concrete 
Earth 
Earth 
Earth 
Earth 
99 2,610 
160 3,500 
319 3,000 
60 7,800 
45 575 
97 10,475 
280 1,142 
163 5,730 
185 4,952 
50 1,300 
113 2,670 
92 1,830 
55 4,075 
88 1,330 
75 790 
200 2,200 
210 1,960 
155 620 
429 1,820 
106 2,280 
160 3,850 
92 23,800 
57 15,444 
A-1

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
CALIFORNIA (Continued) 
Success 
Terminus 
Whittier Narrows 
COLORADO 
Bear Creek 
Chatfield 
Cherry Creek 
John Martin 
Trinidad 
CONNECTICUT 
Black Rock 
Colebrook River 
Hancock Brook 
Hop Brook 
Mansfield Hollow 
Northfield Brook 
Thomaston 
West Thompson 
IDAHO 
Lucky Peak 
ILLINOIS 
Carlyle 
Farmdale 
Fondulac 
Shelbyville 
Rend Lake 
INDIANA 
Brookville 
Cagles Mill 
Cecil M. Harden 
Huntington 
Mississinewa 
Monroe 
Patoka 
Salamonie 
San Joaquin Tule River 
San Joaquin Kaweah River 
San Gabriel San Gabriel River 
;and Rio Hondo 
Missouri 
Missouri 
Missouri 
Arkansas 
Arkansas 
Housatonic 
Connecticut 
Housatonic 
Housatonic 
Thames 
Thames 
Housatonic 
Thames 
Bear Creek 
South Platte River 
Cherry Creek 
Arkansas River 
Purgatoire River 
Branch Brook 
West Branch, 
Farmington River 
Hancock Brook 
Hop Brook 
Natchaug River 
Northfield Brook 
Naugatuck River 
Quinebaug River 
Columbia Boise River 
Upper Kaskaskia River 
Mississippi 
Upper Farm Creek 
Mississippi 
Upper Fondulac Creek 
Mississippi 
Upper Kaskaskia River 
Mississippi 
Upper Big Muddy River 
Mississippi 
Ohio East Fork of 
Whitewater River 
Ohio Mill Creek 
Ohio Raccoon Creek 
Ohio Wabash River 
Ohio Mississinewa 
Ohio Salt Creek 
Ohio Patoka River 
Ohio Salamonie 
IOWA 
Coralville 
Red Rock 
Rathbum 
Saylorville 
Upper 
Mississippi 
Upper 
Mississippi 
Missouri 
Upper 
Mississippi 
Iowa River 
Des Moines River 
Chariton River 
Des Moines River 
Porterville 
Visalia 
El Monte 
Denver 
Denver 
Denver 
Lamar 
Trinidad 
Thomaston 
Riverton 
Plymouth 
Middlebury 
Willimantic 
Thomaston 
Thomaston 
Thompson 
Boise 
Carlyle 
East Peoria 
East Peoria 
Shelbyville 
Benton 
Brookville 
Tere Haute 
Rockville 
Huntington 
Peru 
Harrodsburg 
Ellsworth 
Wabash 
Iowa City 
Des Moines 
Centerville 
Des Moines 
1960 85,000 400 FIRX Earth 
'1961 150,000 345 FIRX Earth 
1967 35,150 NPP FRWX Earth 
1978 30,810 
1974 231,429 
1950 93,920 
1943 608,250 
1977 123,523 
1970 8,700 
1969 97,700 
1960 4,030 
1968 6,970 
1952 52,000 
1965 2,430 
1960 42,000 
1965 26,800 
109 
1,412 
852 
1,844 
280 
20 
760 
40 
21 
450
8 
NPP 
200 
FRX 
FRX 
FRX 
FIR 
FIRX 
FR 
FRSX 
FRW 
FR 
FRW 
FRW 
F
FRW 
Earth 
Earth 
Earth 
Concrete 
& Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
1945 307,000 2,820 FIR Earth 
1967 983,000 
1951 15,500 
1951 3,780 
1970 684,000 
1970 294,000 
1974 359,600 
1952 228,120 
1960 132,800 
1969 153,100 
1967 368,400 
1964 441,000 
1978 301,600 
1966 263,600 
1958 492,000 
1969 1,830,000 
1969 552,000 
1975 602,000 
26,000 
NPP 
NPP 
11,100 
18,900 
2,250 
1,400 
1,100 
500 
1,100 
3,280 
2,010 
976 
1,820 
8,950 
11,000 
74,000 
FSNRWA Earth 
F Earth 
F Earth 
FSNRW Earth 
FQRSW Earth 
FRSW 
FRX 
FRX 
FRW 
FRW 
Earth& Rock 
Earth 
Earth 
Earth 
Earth 
FARS Earth 
FRSQW Earth & Rock 
FRW Earth 
FARW Earth 
FARWQ Earth 
FNRWXQ Earth 
FARWQ Earth 
142 3,490 
250 2,375 
56 19,960 
180 5,300 
148 12,400 
141 14,300 
106 13,962 
200 6,610 
154 933 
223 1,300 
57 630 
97 520 
68 12,420 
118 810 
142 2,000 
70 2,550 
340 1,700 
67 6,570 
80 1,275 
67 1,000 
108 3,000 
54 10,600 
182 3,000 
150 950 
117 1,790 
91 5,332 
137 8,100 
93 1,400 
84 1,550 
133 6,100 
100 1,400 
110 5,676 
86 10,600 
125 6,750 
A-2

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
KANSAS 
Clinton 
Council Grove 
El Dorado 
Elk City 
Fall River 
Hillsdale 
John Redmond 
Kanopolis 
Marion 
Melvern 
Milford 
Pearson Skubitz 
Big Hill 
Perry 
Pomona 
Toronto 
Tuttle Creek 
Wilson 
KENTUCKY 
Barren River 
Buckhorn 
Carr Fork 
Cave Run 
Dewey 
Fishtrap 
Grayson 
Green River 
Martins Fork 
Paintsville 
Nolin 
Rough River 
Taylorsville 
Yatesville 
LOUISIANA 
Bayou Bodcau 
Caddo Lake 
Wallace Lake 
MARYLAND 
Jennings Randolph 
Lake 
MASSACHUSETTS 
Barre Falls 
Birch Hill 
Buffumville 
Charles River Natural 
Valley Storage 
Conant Brook 
East Brimfield 
Hodges Village 
Knightville 
Littleville 
Missouri 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Missouri 
Arkansas 
Missouri 
Arkansas 
Missouri 
Missouri 
Arkansas 
Missouri 
Missouri 
Arkansas 
Missouri 
Missouri 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Cumberland 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Red 
Red 
Red 
Wakamusa River 
Grand (Neosho) 
Walnut River 
Elk River 
Fall River 
Big Bull Creek 
Grand (Neosho) 
Smoky Hill River 
Cottonwood River 
Marais des Cygnes 
Republican River 
Big Hill Creek 
Deleware River 
110 Mile Creek 
Verdigris River 
Big Blue River 
Saline River 
Barren River 
Middle Fork of 
Kentucky River 
Carr Fork 
Licking River 
Johns Creek 
Levisa Fork, 
Big Sandy River 
Little Sandy 
Green River 
Martins Fork 
Paint Creek 
Nolin River 
Rough River 
Salt River 
Blain Creek 
Bayou Bodcau 
Cypress Bayou 
Cypress Bayou 
Potomac North Branch 
Potomac River 
Connecticut 
Connecticut 
Thames 
Charles 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Ware River 
Millers River 
Little River 
Charles River 
Conant Brook 
Quinebaug River 
French River 
Westfield River 
Middle Branch, 
Westfield River 
Lawrence 
Council Grove 
El Dorado 
Independence 
Fall River 
Hillsdale 
Burlington 
Marquette 
Marion 
Melvem 
Junction City 
Cherryvale 
Perry 
Pomona 
Toronto 
Manhattan 
Wilson 
Glasgow 
Buckhorn 
Hazard 
Farmers 
Paintsville 
Pikeville 
Grayson 
Campbells 
-vile 
Harlan 
Paintsville 
Kyrock 
Leitchfield 
Taylorsville 
Yatesville 
Shreveport 
Shreveport 
Shreveport 
Barnum 
Barre 
So. Roylaston 
Charlton 
Millis 
Monson 
Fiskdale 
Oxford 
Huntington 
Chester 
1977 397,200 
1964 112,882 
1981 236,200 
1966 287,300 
1949 256,400 
1981 160,000 
1964 628,540 
1948 450,000 
1968 141,770 
1972 363,000 
1965 1,160,000 
1981 39,740 
1969 770,000 
1963 230,000 
1960 200,800 
1962 2,346,000 
1964 776,000 
1964 815,200 
1960 168,000 
1976 47,700 
1974 614,100 
1949 93,000 
1968 164,360 
1967 118,990 
1969 723,200 
1978 21,00 
1983 73,500 
1963 609,400 
1958 334,400 
1983 291,670 
1988 86,951 
1949 357,300 
1971 175,000 
1946 96,100 
7,000 FSWAXR Earth 
3,310 FSQR Earth 
8,000 FSQR Earth 
4,122 FSQ Earth 
2,350 FSX Earth 
4,580 FSQR Earth 
9,710 FSQR Earth 
3,815 FRWX Earth 
6,210 FRQS Earth 
6,930 FRQWX Earth 
15,600 FRSXWQ Earth&Rock 
1,190 FSR Earth 
12,500 FRSXW Earth&Rock 
4,000 FRSWXQ Earth&Rock 
2,660 FX Earth 
15,800 FRWXQAN Earth&Rock 
9,000 FIRWXNA Earth 
4,340 FARS 
550 FQRW 
530 FQRW 
6,790 FQRW 
1,100 FARW 
569 FARW 
1,050 FQRW 
5,070 FRSQW 
578 FQ 
261 FQRW 
2,890 FAR 
2,180 FRX 
1,625 FQRW 
3,921 FQRW 
NPP FRW 
32,700 NFRS 
2,300 FQRS 
Earth 
Earth 
Earth & Rock 
Earth & Rock 
Earth 
Rock 
Earth & Rock 
Earth & Rock 
Concrete 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth 
Concrete 
& Earth 
Earth 
1981 130,900 952 FQRS Earth & Rock 296 2,130 
1958 24,000 
1941 49,900 
1958 12,700 
1983 35,000 
1966 3,740 
1960 30,000 
1959 12,800 
1941 49,000 
1965 32,400 
NPP FRW 
NPP FRW 
200 FRW 
NPP F 
NPP F 
360 FRW 
NPP FRW 
NPP FRW 
275 FRWS 
Earth & Rock 62 885 
Earth & Rock 56 1,400 
Earth & Rock 66 3,255 
Nonstructural -- -- 
Earth & Rock 85 1,050 
Earth & Rock 55 520 
Earth & Rock 55 2,140 
Earth & Rock 160 1,200 
Earth & Rock 1,164 1,360 
A-3 
114 9,250 
96 6,500 
99 20,930 
107 4,840 
94 6,015 
75 11,600 
86.5 21,790 
131 15,360 
67 8,375 
98 9.700 
126 6,300 
83 3,902 
96 7,750 
85 7,750 
90 4,712 
157 7,500 
160 5,600 
146 3,970 
162 1,020 
130 720 
148 2,740 
118 913 
195 1,100 
120 1,460 
142 2,350 
97 574 
160 1,600 
174 990 
124 1,530 
164 1,280 
105 760 
70 12,850 
3,700 
30 4,994

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
MASSACHUSETTS (Continued) 
Tully 
West Hill 
Westville 
MINNESOTA 
Big Stone Lake- 
Whetstone River 
Lac Qui Parle 
Chippewa River 
LacQui Parle 
Marsh Lake 
Orwell 
Red Lake 
MISSISSIPPI 
Ariabutla Lake 
Enid Lake 
Grenada Lake 
Okatibbee 
Sardis Lake 
MISSOURI 
Clearwater 
Long Branch 
Little Blue River Lakes 
Blue Springs Lake 
Longview 
Pomme de Terre 
Smithville 
Wappapello 
NEBRASKA 
Harlan County 
Paipillion Creek 
and Tributaries 
Glenn Cunningham 
(Site 11) 
Standing Bear Lake 
(Site 16) 
Ed Zorinsky (Site 18) 
Wehrspann (Site 20) 
Salt Creek & Tributaries 
Olive Creek (Site 2) 
Blue Stem (Site 4) 
Wagon Train (Site 8) 
Stagecoach Site (9) 
Connnecticut Tully River 
Blackstone West River 
Thames Quinebaug River 
Upper Minnesota River 
Mississippi 
Upper Chippewa River 
Mississippi 
Upper Minnesota River 
Mississippi 
Upper Minnesota River 
Mississippi 
Red River Otter Tail River 
of the North 
Red River Red Lake River 
of the North 
Lower Coldwater River 
Mississippi 
Lower Yocona River 
Mississippi 
Lower Yalobusha River 
Mississippi 
Pascagoula Okatibbee Creek 
Lower Little Tallahatchie 
Mississippi River 
White 
Grande 
Chariton 
Missouri 
Missouri 
Missouri 
Missouri 
Lower 
Mississippi 
Black River 
Little Charlton 
Little Blue River 
Little Blue River 
Pomme de Terre River 
Little Platte River 
St. Francis River 
Missouri Republican River 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
M:i;ssouri 
Misouri 
Knight Creek 
Trib of Big Papillion 
Creek 
Boxelder Creek 
S. Pipillion Creek 
S. Trib. Olive Br. Creek 
N. Trib Olive Br. Creek 
N. Trib. Hickman Creek 
S. Trib. Hickman Creek 
Fryville 
Uxbridge 
Sturbridge 
Ortonville 
Montevideo 
Montevideo 
Montevideo 
Fergus Falls 
Red River 
Arkabutla 
Enid 
Grenada 
Meridian 
Sardis 
Piedmont 
Macon 
Kansas City 
Kansas City 
Hermitage 
Smithville 
Wappapello 
1949 22,000 300 FRW Earth & Rock 62 1,570 
1960 12,350 NPP FRW Earth & Rock 51 2,400 
1961 11,100 23 FRW Earth & Rock 78 560 
1973 45,000 12,700 
1950 (2) 
1950 122,800 
1953 14,100 
1953 14,100 
1951 3,270,000 
1943 525,300 
1951 660,000 
1954 1,337,400 
1969 142,400 
1940 1,570,000 
NPP 
6,500 
210 
210 
279;000 
5,100 
6,100 
9,800 
1,280 
10,700 
FRW 
FRWX 
FRWX 
FARS 
FARS 
FARSX 
F
F
F
FQSR 
F 
Earth 25 13,700 
Earth & Rock 21 17,97 
Earth & Rock 21 4,100 
Earth & Rock 19.5 11,800 
Eaarth & Rock 47 1,355 
Earth & Rock 15.5 36,500 
Earth & Rock 
Earth & Rock 
Earth & Rock 
Earth 
Earth & Rock 
81 11,500 
99 8,400 
102 13,900 
67 6,543 
117 15,300 
1948 413,700 1,630 FRWX Earth & Rock 154 4,225 
1980 65,000 2,430 FRSQW Earth 71 3,800 
1988 26,600 
1986 46,900 
1961 650,000 
1982 246,500 
1941 613,200 
560 
930 
7,820 
7,190 
4,100 
FRWQ 
FRWQ 
FRWX 
FSQRW 
FR 
Earth&Rock 
Earth&Rock 
Earth&Rock 
Earth 
Earth & Rock 
78 2,500 
120 1,900 
155 4,630 
95 4,200 
109 2,700 
Republican City 1952 850,000 13,600 FIRWX Earth & Rock 107 11,827 
Omaha 
Omaha 
Omaha 
Omaha 
Kramer 
Sprague 
Holland 
Hickman 
1975 17910 
1973 5,220 
1991 6,910 
1991 1,990 
1964 5,470 
1963 10,260 
1963 9,280 
1964 6,640 
391 
137 
418 
203 
174 
316 
303 
196 
FQEX 
FRX 
FR 
FR 
FR 
FR 
FR 
FB 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
67 1,940 
70 1,460 
64 11,400 
59 11,810 
45 3,020 
57 2,760 
52 1,650 
48 2,250 
A-4

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
NEBRASKA (Continued) 
Yankee Hill (Site 10) 
Conestoga (Site 12) 
Town Lake (Site 13) 
Holmes ark Lake 
(Site 17) 
Branched Oak (Site 18) 
NEW HAMPSHIRE 
Blackwater 
Edward MacDowell 
Franklin Falls 
Hopkinton-Everett 
Otter Brook 
Surry Mountain 
NEVADA 
Mathews Canyon 
Pine Canyon 
NEW MEXICO 
Abiquiu 
Cochiti 
Conchas 
Galisteo 
Jemez Canyon 
Two Rivers: 
Diamond "A" Dam 
Rocky Dam 
Santa Rosa Dam & 
Reservoir 
NEW YORK 
Almond 
Axkport 
East Sidney 
Mount Morris 
Whitney Point 
NORTH CAROLINA 
B. Everett Jordan 
Falls 
W. Kerr Scott 
NORTH DAKOTA 
Baldhill 
Borman-Haley 
Homme 
Pipestem 
Missouri 
Missouri 
Missouri 
Missouri 
Missouri 
Merrimack 
Merrimack 
Merrimack 
Merrimack 
Merrimack 
Connecticut 
Connecticut 
Cardwell Creek 
Holmes Creek 
Middle Creek 
Antelope Creek 
Oak Creek 
Blackwater River 
Nubanusit Brook 
Pemigewasset River 
Contoocook River 
Piscataquog River 
Otter Brook 
Ashuelot River 
Colorado Mathews Canyon 
Colorado Pine Canyon 
Rio Grande 
Rio Grande 
Arkansas 
Rio Grrande 
Rio Grande 
Rio Grande 
Rio Grande 
Pecos 
Susquehanna 
Susquehanna 
Susquehanna 
Genesee 
Susquehanna 
Cape Fear 
Neuse 
Yadkin- 
Pee Dee 
Rio Charma 
Rio Grande 
Canadian River 
Galisteo Creek 
Jemez River 
Rio Hondo 
Rocky Arroyoo 
Pecos 
Canacadea Creek 
Canisteo Creek 
Ouleout Creek 
Genesee River 
Otselic River 
New Hope 
Neuse 
Yadkin 
Red River Sheyenne River 
of the North 
Denton 
Denton 
Pleasantdale 
Lincoln 
Raymond 
Webster 
West 
Peterborough 
Franklin 
West 
Hopkinton 
East Weare 
Keene 
Keene 
Caliente 
Caliente 
Abiquio 
Pena Blanca 
Tucumcari 
Santa Fe 
Bemailillo 
Roswell 
Santa Rosa 
Homell 
Arkport 
Franklin 
Mount Morris 
Whitney Point 
Durham 
Raleigh 
Wilkesboro 
Valley City 
Missouri North Fork, Grand River Haley 
Red River South Branch of Park River 
of the North Park River 
James River Pipestem Creek Jamestown 
1966 7,560 
1964 10,640 
1966 8,080 
1963 6,510 
1968 97,560 
1941 46,000 
1950 12,800 
1943 154,000 
1962 71,500 
1962 87,500 
1958 18,300 
1941 32,500 
208 FR 
230 FR 
255 FR 
100 FR 
1,780 FR 
NPP FRW 
NPP FRW 
NPP FRW 
200 FRW 
120 FRW 
85 FRW 
265 FRW 
1957 6,271 NPP FX 
1957 7,747 NPP FX 
1963 1,198,500 
1975 589,159 
1939 513,900 
1970 89,468 
1953 100,485 
1963 163,775 
1979 439,860 
1949 14,600 
1940 7,900 
1950 33,550 
1952 337,000 
1942 86,440 
1982 753,500 
1983 374450 
1963 153,000 
1950 70,000 
1967 92,980 
1951 3,660 
1974 146,880 
NPP FXS 
1,200 FRWX 
2,694 FI 
NPP FX 
NPP FX 
NPP FX 
NPP FIX 
124 FRW 
NPP F 
210 FRW 
170 FR 
1,200 FRW 
Earth 52 3,100 
Earth 63 3,000 
Earth Pawnee (Site 14) Missouri 
Earth 55 7,700 
Earth 70 5,200 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
& Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete & 
Earth 
Concrete 
Earth 
14,300 FQRSWX Earth 
11,300 FQRSWX Earth 
1,470 FARSX Earth 
325 FARS Earth 
1,750 FSRWK Earth 
51 FARS Earth 
885 FRWX Earth 
A-5 
75 1,150 
67 1,030 
140 1,740 
76 790 
115 2,000 
133 1,288 
86 1,670 
71 800 
92 884 
325 1,540 
241 28,300 
200 19,400 
156 2,820 
146.6 780 
998 4,885 
118 2,940 
212 1,950 
90 1,260 
113 1,200 
130 2,010 
210 1,028 
95 4,900 
112 1,330 
92 1,915 
148 1,740 
61 1,650 
79 5,730 
67 865 
108 4,000

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
OHIO 
Alum Creek 
Berlin 
Caesar Creek 
Clarence J. Brown 
Deer Creek 
Delaware 
Dilon 
Michael J. Kirwan 
Mosquito Creek 
Muskingum River 
Reservoirs: 
Atwood 
Beach City 
Bolivar 
Charles Mill 
Clendening 
Dover 
Leesville 
Mohawk 
Mohicanville 
Piedmont 
Pleasant Hill 
Senecaville 
Tappan 
Wills Creek 
North Branch, 
Kakosing River Lake 
Paint Creek 
Tom Jenkins 
West Fork Mill Creek 
William H. Harsha 
OKLAHOMA 
Arcadia 
Birch 
Canton 
Copan 
Fort Supply 
Great Salt Plains 
Heyburn 
Hugo 
Hulah 
Kaw 
Oologah 
Optima 
Pine Creek 
Sardis 
Skiatook 
Waurika 
Wister 
OREGON 
Applegate 
Blue River 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Ohio 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Red 
Arkansas 
Arkansas 
Arkansas 
Arkansas 
Red 
Red 
Arkansas 
Red 
Arkansas 
Rogue 
Alum Creek 
Mahoning Creek 
Caesar Creek 
Buck Creek 
Deer Creek 
Licking River 
Licking River 
West Branch, 
Mahoning River 
Mosquito Creek 
Indian Fork 
Sugar Creek 
Sandy Creek 
Black Fork 
Brushy Fork 
Tuscarawas River 
McGuire Creek 
Walhondoing River 
Lake Fork 
Stillwater Creek 
Clear Fork 
Seneca Fork 
Little Stillwater Creek 
Wills Creek 
North Branch of 
Kakosing River 
Paint Creek 
East Branch, 
Sunday Creek 
Mill Creek 
Little Miami River 
Deep Fork River 
Birch Creek 
North Canadian River 
Little Caney River 
Wolf Creek 
Salt Fork of the 
Arkansas River 
Polecat Creek 
Kiamichi River 
Caney River 
Arkansas River 
Verdigris River 
North Canadian River 
Little River 
Jackfork Creek 
Hominy Creek 
Beaver Creek 
Poteau River 
Applegate River 
Columbia Blue River 
Africa 
Deerfield 
Wilmington 
Springfield 
New Holland 
Zanesville 
Zanesville 
Newton Falls 
Cortland 
New 
Cumberland 
Beach City 
Bolivar 
Mufflin 
Tippecanoe 
Dover 
Leesville 
Nellie 
Mohicanville 
Piedmont 
Perrysville 
Senecaville 
Tappan 
Conesville 
Fredericktown 
New Petersburg 
Gloucester 
Mount Healthy 
Williamsburg 
Edmond 
Bamsdall 
Canton 
Copan 
Fort Supply 
Cherokee 
Sapulpa 
Hugo 
Bartlesville 
Ponca City 
Oologah 
Hardesty 
Wright City 
Clayton 
Skiatook 
Waurika 
Wister 
Medford 
Blue River 
1975 134,800 
1943 91,200 
1978 242,200 
1974 63,700 
1968 102,500 
1961 273,000 
1961 273,000 
1966 78,700 
1944 104,100 
1937 49,700 
1937 71,700 
1938 149,600 
1936 88,000 
1937 54,000 
1938 203,000 
1937 37,400 
1937 285,000 
1936 102,000 
1937 65,000 
1938 87,700 
1937 88,500 
1936 61,60-0 
1937 196,000 
1973 14,900 
1972 145,000 
1951 26,900 
1952 11,380 
1978 284,500 
1986 92,010 
1977 58,200 
1948 377,100 
1983 227,700 
1942 100,700 
1941 271,400 
1950 55,395 
1974 966,700 
1951 289,000 
1976 1,348,000 
1963 1,519,000 
1978 29,460 
1969 465,780 
1984 396,900 
1985 500,700 
1977 343,500 
1949 427,900 
348 
240 
13,300 
1,010, 
727 
1,325 
1,325 
580 
700 
1,540 
420 
NPP 
1,350 
1,800 
350 
1,000 
NPP 
NPP 
2,270 
850 
3,550 
2,350 
900 
98 
710 
394 
200 
18,760 
1,820 
1,137 
7,910 
4,850 
1,820 
8,690 
880 
13,250 
3,570 
17,040 
29,460 
5,340 
3,750 
13,610 
10,190 
10,100 
5,360 
FRSW Concrete & 
Earth 
FARSWQ Concrete & 
Earth 
FRSQW Earth & Rock 
FQRW Earth & Rock 
FRW Earth 
FRWX Earth 
FRWX Earth 
FAQRSW Earth 
FARSWQ Earth 
FRX 
FRX 
FR 
FRX 
FRX 
FRX 
FRX 
FR 
FR 
FRX 
FRX 
FRSX 
FRX 
FRX 
FRW 
FRSQW 
FRSWX 
FRX 
FRSQW 
FSR 
FSQRW 
FSI 
FSQRW 
FSX 
FRWX 
FRWXS 
FSQRW 
FSAX 
FSQRW 
FSN 
FSRW 
FSQWR 
FSRW 
FSQRW 
FISQWR 
FSAX 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth & Rock 
Concrete 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
93 10,000 
96 5,750 
165 2,750 
72 6,620 
93 3,880 
118 1,400 
118 1,400 
83 9,900 
47 5,650 
65 3,700 
64 5,600 
87 6,300 
48 1,390 
64 950 
83 824 
74 1,694 
111 2,330 
46 1,220 
56 1,750 
113 775 
45 2,350 
52 1,550 
87 1,950 
71 1,400 
118 700 
84 944 
100 1,100 
200 1,450 
102 5,250 
97 3,190 
68 15,140 
70 7,730 
85 11,865 
68 6,010 
89 2,920 
101 10,200 
94 5,200 
125 9,466 
137 4,000 
120 15,200 
124 7,712 
81 14,138 
143 3,590 
106 16,600 
99 5,700 
1981 82,000 988 AFIQRSW Gravel 242 1,300 
Embankment 
1968 85,000 975 FINR Earth 319 1,329 
A-6

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
OREGON (Continued) 
Cottage Grove 
Dorena 
Fall Creek 
Fern Ridge 
Willow Creek 
PENNSYLVANIA 
Alvin R. Bush 
Aylesworth Creek 
Beltzville 
Blue Marsh 
Conemaugh 
Cowanesque * 
Crooked Creek 
Curwensville 
East Branch, 
Clarion River 
Foster Joseph Sayers 
Francis E. Walter 
(Bear Creek) 
Gen. Edgar Jadwin 
Indian Rock 
Kinzua 
Loyalhanna 
Mahoning Creek 
Prompton 
Raystown 
Shenanago 
Stillwater 
Tioga-Hammond 
Lakes 
Hammond Lakes 
Tionesta 
Union City 
Woodcock Creek 
Youghiogheny River 
Columbia 
Columbia 
Columbia 
Columbia 
Columbia 
Susquehanna 
Susquehanna 
Delaware 
Delaware 
Ohio 
Susquehanna 
Ohio 
Susquehanna 
Ohio 
Susquehanna 
Delaware 
Delaware 
Susquehanna 
Ohio 
Ohio 
Ohio 
Delaware 
Susquehanna 
Ohio 
Susquehanna 
Susquehanna 
Susquehanna 
Ohio 
Ohio 
Ohio 
Ohio 
Coast Fork, 
Willamette R iver 
Row River 
Middle Fork, 
WillametteRiver 
Long Tom River 
Willow Creek 
Kettle Creek 
Aylesworth Creek 
Pohopco Creek 
Tulephoken Creek 
Conemaugh River 
Cowanesque River 
Crooked Creek 
West Branch, 
Susquehanna River 
East Branch, 
Clarion River 
Bald Eagle Creek 
Lehigh River 
Dyberry Creek 
Codorus Creek 
Allegheny River 
Loyalhanna Creek 
Mahoning Creek 
Lackawaxem River 
Raystown Branch, 
Juniata River 
Shenanago River 
Lackawanna River 
Tioga River 
Crooked Creek 
Tionesta Creek 
French Creek 
French Creek 
Youghiogheny River 
Cottage Grove 
Cottage Grove 
Eugene 
Eugene 
Heppner 
Renovo 
Archbald 
Lehighton 
Reading 
Saltsburg 
Lawrenceville 
Ford City 
Curwensville 
Wilcox 
Blanchard 
White Haven 
Honesdale 
York 
Warren 
Saltsburg 
New Bethlehem 
Honesdale 
Huntingdon 
Sharpsville 
Uniondale 
Tioga 
Tioga 
Tionesta 
Union City 
Meadville 
Confluence 
1942 30,060 
1949 70,500 
1965 115,000 
1941 110,000 
1983 13,250 
1962 75,000 
1970 1,700 
1971 68,250 
1978 50,010 
1952 274,000 
1980* 89,000 
1940 93,900 
1965 124,200 
1952 84,300 
1969 99,000 
1961 107,610 
1960 24,500 
1942 28,000 
1965 1,180,000 
1942 95,300 
1941 74,200 
1960 52,000 
1973 762,000 
1966 191,400 
1960 12,000 
1978 62,000 
1978 63,000 
1940 133,400 
1970 47,640 
1973 20,000 
1943 254,000 
1,155 
1,885 
1,865 
10,305 
96 
160 
NPP 
947 
960 
300 
1085 
350 
790 
90 
1,730 
80 
NPP 
NPP 
1,900 
210 
170 
290 
8,300 
1,910 
85 
470 
680 
480 
NPP 
118 
450 
FINR 
FINR 
FINR 
FINR 
FRN 
Concrete & 
& Earth 
Concrete 
& Earth 
Rockfill 
Rockfill 
& Concrete 
Roller 
Compacted 
Concrete 
FRW Earth & Rock 
F Earth & Rock 
FQRSWA Earth & rock 
FAQRSW Earth & Rock 
FW Concrete 
& Earth 
FRS Earth & Rock 
FRW Earth 
FR Earth 
FARQW Earth 
FRW Earth 
FRW Earth & rock 
F Earth 
FRW Earth 
PFAQRW Concrete 
& Earth 
FRW Concrete 
& Earth 
FRW Concrete 
FRW Earth 
FRW Earth & Rock 
FAQRW Concrete 
FS Earth 
FR Earth & Rock 
FR Earth & Rock 
FRW Earth 
F Earth 
FQRA Earth 
FARWQ Earth 
* Project became operable for water supply FY 1990 
SOUTH DAKOTA 
Cold Brook Missouri Cold Brook 
Cottonwood Springs Missouri Cottonwood Springs 
Creek 
Lake Traverse: 
Reservation Control Red River Bois de Sioux River 
Dam of the North 
White Rock Red River Bois de Sioux River 
of the North 
Hot Springs 
Hot Springs 
Wheaton 
Wheaton 
19534 7,200 36 FRWX Earth 
1970 8,385 41 FRWX Earth 
1941 164,500 10,925 FRX Earth 
1941 85,500 6,500 FRX Earth 
A-7 
114 
145 
193 
49 
160 
165 
90 
170 
98 
137 
151 
143 
131 
184 
100 
234 
109 
83 
1'77 
114 
162 
140 
225 
68 
77 
140 
122 
154 
88 
90 
184 
2,110 
3,352 
5,100 
6,624 
1,780 
1,350 
1,270 
4,560 
1,775 
1,265 
3,100 
1,480 
2,850 
1,725 
6,835 
3,000 
1,255 
1,000 
1,877 
960 
926 
1,200 
1,700 
720 
1,700 
2,710 
6,450 
1,050 
1,420 
4,650 
1,610 
127 925 
123 1,190 
14 9,100 
16 14,400

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
TEXAS 
Addicks 
Aquilla 
Barker 
Belton 
Benbrook 
Canyon 
Cooper Lake 
and Channel 
Ferrells Bridge Dam- 
Lake O' the Plains 
Granger Dam and Lake 
Grapevine 
Hords Creek 
Joe Pool 
Lake Kemp 
Lavon 
Lewisville 
Navarro Mills 
North San 
Gabriel Dam, 
Lake Georgetown 
O.C. Fisher 
Pat Mayse 
Proctor 
Ray Roberts 
Somerville 
Stillhouse Hollow 
Waco 
Wright Patman 
VERMONT 
Ball Mountain 
North Hartland 
North Springfield 
Townshend 
Union Village 
VIRGINIA 
John W. Flannagan 
Gathright Dam & 
Lake Moomaw 
North Fork of 
Pound River 
San Jacinto 
Brazos 
San Jacinto 
Brazos 
Trinity 
Guadalupe 
Red 
Red 
Brazos 
Trinity 
Colorado 
Trrinity 
Red 
Trinity 
Trinity 
Trinity 
Brazos 
Colorado 
Red 
Brazos 
Trinity 
Brazos 
Brazos 
Brazos 
Red 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Connecticut 
Ohio 
James 
Chehalis 
South Mayde Creek 
Aquilla Creek 
Buffalo Bayou 
Leon River 
Clear Fork, 
Trinity River 
Guadallupe River 
Sulphur River 
Cypress Creek 
San Gabriel River 
Denton Creek 
Hords Creek 
Mountain Creek 
Wichita River 
East Fork, 
Trinity River 
Elm Fork, 
Trinity River 
Richland Creek 
North Fork, 
San Gabriel River 
North Concho River 
Sanders Creek 
Leon River 
Elm Fork 
Yegua Creek 
Lampasas River 
Bosque River 
Sulphur River 
West River 
Ottauguechee River 
Black River 
West River 
Ompompanoosuc River 
Pound River 
Jackson 
Wynoochee River 
Addicks 
Hillsboro 
Barker 
Belton 
Fort Worth 
New Braunfels 
Cooper 
Jefferson 
Granger 
Grapevine 
Coleman 
Grand Prairie 
Wichita Falls 
Fort Worth 
Lewisville 
Corsicana 
Georgetown 
San Angelo 
Paris 
Comanche 
Denton 
Somerville 
Belton 
Waco 
Texarkana 
Jamaica 
North Hartland 
Springfield 
Townshend 
Union Village 
Haysi 
Alleghany 
Montesano 
1948 204,500 
1983 146,000 
1945 207,000 
1954 1,097,600 
1952 258,600 
1964 366,400 
1991 441,200 
1959 842,100 
1980 244,200 
1952 425,500 
1948 25,310 
1986 304,000 
1972 502,900 
1953 748,200 
1954 989,700 
1962 212,200 
1980 130,800 
1952 396,400 
1967 189,100 
1963 374,200 
1987 1,064,600 
1967 507,500 
1968 630,400 
1965 726,400 
1957 2,654,300 
1961 54,600 
1960 71,420 
1960 51,067 
1961 33,700 
1950 38,000 
1963 145,700 
1979 123,739 
1972 70,000 
NPP 
3,280 
NPP 
12,300 
3,770 
346,400 
19,305 
18,700 
4,400 
7,280- 
510 
7,470 
15,590 
21,400 
23,280 
5,070 
1,310 
5,440 
5,993 
4,610 
29,350 
11,460 
6,430 
7,270 
20,300 
75 
220 
290 
100 
NPP 
310 
2,532 
1,150 
FX 
FSX 
FX 
FIRSX 
FNRXA 
FRSX 
FRSWX 
FRS 
FRSWX 
FNRSXA 
FARSX 
FRSX 
FX 
FRSW 
FRSX 
FRSX 
FRSWX 
FRSX 
FRSW 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRSX 
FRW 
FRW 
FRW 
FRW 
FRW 
FAWR 
FQR 
FSARI 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Rock 
Earth 
Earth 
Earth 
Earth 
Earth 
Earth 
Concrete 
& Earth 
Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Concrete 
& Earth 
Earth & Rock 
Concrete 
& Earth 
49 
104.5 
27 
192 
130 
224 
79 
97 
115 
137 
91 
109 
115 
81 
125 
82 
164 
128 
96 
86 
109 
80 
200 
140 
100 
265 
185 
120 
133 
170 
250 
257 
177 
61,166 
11,890 
72,844 
5,524 
9,130 
4,410 
28,070 
10,600 
16,320 
12,850 
6,800 
22,360 
8,890 
19,483 
32,888 
6,700 
6,700 
40,885 
7,080 
13,460 
14,965 
26,175 
15,624 
24,618 
18,500 
915 
1,520 
2,940 
1,700 
1,100 
960 
1,172 
1m700 
A-8

APPENDIX A (Continued) 
FLOOD CONTROL RESERVOIRS OPERABLE SEPTEMBER 30, 1992 
Permanent 
Pool Characteristics of Dam 
Cal. Year Total (Acreage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
WASHINGTON 
Howard A. Hanson 
Mill Creek 
Mud Mountain 
WEST VIRGINIA 
Green 
Columbia 
Puyallup 
Green River 
Mill Creek 
White River 
Kanaskat 1961 106,000 
Walla Walla 1942 8,300 
Enumclaw 1953 106,000 
1,600 FAS Rock 
225 FR Earth 
NPP FR Rock 
Beech Fork Ohio 
Bluestone Ohio 
Bumsville Ohio 
East Lynn Ohio 
R. D. Bailey OhioG 
Stonewall Jackson L.,WV Ohio 
Summersville Lake Ohio 
Sutton Ohio 
Tygart River Ohio 
WISCONISIN 
Beech Fork 
New River 
Little Kanawha 
Twelve Pole Creek 
uynabdot River 
West Fork River 
Gauley River 
Elk River 
Tygart River 
Lavalette 
Hinton 
Burnsville 
East Lynn 
Justice 
Wested 
Summersville 
Sutton 
Grafton 
1977 37,540 
1952 631,000 
1977 65,400 
1970 82,500 
1979 203,700 
1988 74,650 
1965 413,800 
1960 265,300 
1938 287,700 
450 FRW Earth 86 1,080 
1,800 FRWX Concrete 180 2,048 
550 FQRW Earth & Rock 89 1,400 
823 FQRW Earth & Rock 122 650 
440 FQRW Earth & Rock 310 1,397 
3,470 FAQAS Concrete 45 620 
407 FANR Rock 390 2,280 
270 FNAR Concrete 220 1,921 
620 FNAR Concrete 230 1,921 
Chippewa Eau Galle Spring Valley 1969 43,600 150 FR 
A-9 
235 675 
125 3,200 
425 700 
Eau Galle Earth 122 1,800

FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS 
SEPTEMBER 30, 1992 
Permanent 
Pod Characteristics of Dam 
Cal. Year Total (Acacage) 
Community Placed in Storage or No Project Height Length 
Name River Basin Stream in Vicinity Useful Op. (Acre-Ft.) Pool (NPP) Functions Type (Feet) (Feet) 
CALIFORNIA 
Big Dry Creek 
Camanche2 
Cherry Valley 3 
Del Valle 
Eaton Wash 
New Bullards Bar2 
New Don Pedro 3 
New Exchequer2 
Oroville2 
Tahchevah Creek 
COLORADO 
Pinon Canyon 
CONNECTICUT 
East Branch 
Hall Meadow Brook 
Mad River 
Sucker Brook 
HAWAII 
Kaneohe-Kailua Area 
IDAHO 
Ririe 
MARYLAND 
Savage River 
MISSOURI 
Bear Creek 
NEW YORK 
Onandaga 
OKLAHOMA 
Altus4 
Grand Lake O' 
the Cherokees 
Lake Hudson5 
UTAH 
Big Wash 
VERMONT 
East Barre 
Waterbury 
Wrightsville 
San Joaquin Big Dry Creek 
San Joaquin Mokelumne River 
Tuolumne Cherry Creek 
Alameda Arroyo Del Valle 
Rio Hondo Eaton Wash 
Sacramento Yuba River 
San Joaquin Tuolumne River 
San Joaquin Merced River 
Sacramento Feather River 
Whitewater Tahchevah Creek 
Colorado Pinon Canyon Arroyo 
Housatonic East Branch, 
Naugatuck River 
Housatonic Hall Meadow Brook 
Connecticut Mad River 
Connecticut Sucker Brook 
Kaneohe Kaneohe Stream 
Upper Snake Willow Creek 
Potomac Savage 
Upper Bear Creek 
Mississippi 
Oswego 
Red 
Arkansas 
Arkansas 
Beaver 
Winooski 
Winooski 
Winooski 
Fresno 
Clements 
Sonora' 
Livermore 
Pasadena 
Marysville 
Modesto 
Merced 
Oroville 
Palm Springs 
Trinidad 
Torrington 
Torrington 
Winchester 
Winchester 
Kaneohe 
Idaho Falls 
Westem Port 
Hannibal 
Onondaga Creek Syracuse 
North Fork, of the Red Riv. Altus 
Grand (Neosho) River Disney 
Grand (Neosho) River Locust Grove 
Big Wash 
Jail Branch 
Waterbury 
North Branch, 
Milford 
East Barre 
Waterbury 
Wrightsville 
1948 16,250 NPP F 
1963 431,500 NPP FRS 
1956 268,000 475 FS 
1968 77,000 200 FRS 
1937 960 NPP F 
1968 960,000 1,910 FIRPW 
1970 2,030,000 3,520 FISP 
1966 1,026,000 1,900 FIR 
1964 3,539,000 5,838 FIRSW 
1965 960 NPP F 
1954 4,350 NPP FW 
1964 4,350 NPP FR 
1962 8,620 NPP F 
1963 9,700 10 FR 
1970 1,480 NPP F 
1981 3,800 26 FR 
1979 100,500 364 FIR 
1952 20,000 360 FRS 
1962 8,700 NPP F 
1949 18,200 NPP F 
1948 152,429 6,260 FISR 
1941 2,197,000 46,5006 FRP 
1964 444,500 10,9006 FRP 
1961 1,200 NPP F 
1938 12,050 NPP F 
1938 37,000 890 FRP 
1938 20,300 570 FR 
Earth 40 
Earth & Rcck 171 
Earth & Rock 315 
Earth 223 
Earth 82 
Concrete 645 
Earth & Rock 565 
Rock 480 
Earth 770 
Earth 42 
Earth 92 
Earth 92 
Earth & Rock 73 
Earth 178 
Earth 68 
Earth 92 
Earth 253 
Earth & Rock 184 
Earth 65 
Earth 
Concrete 
Concrete 
Concrete 
& Earth 
Earth 
Earth 
Earth 
Earth 
67 
98 
147 
90 
34 
65 
158 
115 
A-10 
20,038 
2,450 
2,500 
880 
1,795 
2,323 
1,920 
1,200 
6,850 
3,610 
700 
100 
1,200 
940 
1,160 
100 
1,070 
1,050 
1,450 
1,782 
1,112 
6,565 
4,494 
2,814 
1,460 
1,800 
1,525

FLOOD CONTROL RESERVOIRS CONSTRUCTED OR CONTRIBUTED TO 
BY CORPS OF ENGINEERS BUT OPERATED BY OTHERS 
SEPTEMBER 30, 1992 
Pod Chaacteristic of Dun 
Cal. Year Total (Acaeage) 
Community Placed in Storag or No Project Height Length 
Name River Balin Stream in Vicinity Useful Op. (Acse-Pt.) Pool (NPP) Functions Type (Fet) (Pot) 
WASHINGTON 
Wynoochee Chehalis Wynoochee River Montesano 1972 70,000 1,150 FSARI Concrete 177 1,700 
& Earth 
NOMENCLATURE FOR PROJECT FUNCTIONS 
A - Low Flow Augmentation 
D - Debris Control 
F - Flood Control 
I - Irrigation 
N - Navigation 
P - Power 
Q - Water Quality Control 
R - Public Recreation (Annual Attendance exceeding 5,000) 
S - Water Supply 
W - Fish and Wildlife (Federal or State) 
X - Water Conservation and Sedimentation 
1 Acres of water surface at top of permanent pool 
2 Federal Government contributed for flood storage 
3 Cherry Valley Reservoir: Planned and constructed by local interests as initial phase; provided flood control on interim basis. Second and final phase,N ew Don Pedro Reservoir: 
Federal Government contributed for flood protection. Construction and operation by City and County of San Francisco and Turlock and Modesto Irrigation Districts. 
4 Construction by Bureau of Reclamation. Participation by Department of the Army to finance flood control portion. 
5 Construction by Grand River Dam Authority. Participation by Department of the Army to finance flood control portion. 
6 Top of power pool. 
A-l11

APPENDIX B 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Alton to Gale Levee System, Mississippi 
River, IL and MO.................................... ...... 
Arcadia Lake, OK .................................... ........ 
Ardsley, NY ..................................... ............ 
Arkansas-Red River Basins Chloride Control 
(Area VIII). OK, TX, and KS (Stage II)................... 
Ascalmore-Tippo Items, MS ............................................ 
Atchafalaya Basin, LA..................................................... 
Atlantic Coast of Maryland...................................... 
B. Everett Jordan Dam and Lake, NC............................... 
Baraga County, MI (Sec 14) ............................................ 
Batesville Sewage Lagoon ...................................... 
Bassett Creek, MN ...................................... ........ 
Bayou Des Glaises, LA ..................................... .... 
Big Blue River, Blue Springs, NE 
Sewerline and Road (Sec 140)..................................... 
Black River, Butler County Road 607, MO (Sec 14) ......... 
Black River, Hwy HH, Wayne Co., MO............................ 
Blue River Basin, Overland Park 
(Indian Creek), KKS (Sec 205).................................... 
Blue River Channel, Kansas City, MO............................... 
Boggy Bayou, Valparaiso, FL............................................ 
Browns Creek, Nashville, TN............................ ............ 
Brush Creek, Kansas City, MO........................................... 
Buffalo Bayou and Tributaries, TX.................................... 
Buffalo Bayou and Tributaries, TX, Addicks and 
Barker, Dam Safety Assurance................................... 
Cache Creek Settling Basin, CA ....................................... 
Candy Lake, OK ....................................... ......... 
Cannonball River, Grant County, ND (Sec 14) .................. 
Canton Bridge, Trigg Co., KY .......................................... 
Cape Girardeau-Jackson, MO ........................................... 
Cascade, IA ........................................ ............ 
Cedar Creek, Spaulding, NE (Sec 14)................................. 
Central and Southern, FL ................................................. 
Century Park, Lorain, OH (Sec 103) ................................... 
Chagrin River, Solon Rd, Chagrin Falls, OH (Sec 14) ....... 
Chaska, MN................................... ............. 
Chatfield Lake, CO ...................................... ....... 
Chena River Lakes, AK ................................................... 
Clear Creek, TX .................................................................. 
Cooper Lake and Channels, TX .......................................... 
Corte Madera Creek, CA................................... .... 
County Line Road Bridge, Mantachie, MS (Sec 14)........... 
Cowanesque Lake, PA ..................................... ..... 
Cox Rum, Wellsburg, WV...................................... 
Cribbs Mill Creek, Tuscaloosa, AL ................................... 
Cuyahoga River, Brecksv ille, KD, UH (Sec 14) ............... 
1983 
1980 
1987 
1976 
1984 
1928 
1990 
1967 
1991 
1990 
1987 
1938 
1991 
1985 
1988 
1992 
1984 
1990 
1988 
1991 
1956 
1986 
1990 
1976 
1991 
1986 
1990 
1992 
1991 
1950 
1990 
1991 
1988 
1968 
1973 
1988 
1958 
1966 
1989 
1987 
1992 
1990 
1992 
B-1 
1992 
1986 Indefinite 4 
1990 1989 
1987 
(2) 
1982 
1991 
1990 
1939 
1991 
1985 
1989 
1991 
1988 
1992 
1992 
1992 
1991 
1991 
1980 
1979 
1991 
1990 
1990 
1991 
1993 
1988 3 
1987 
2010 
2043 
1993 
1991 
1990 
1993 
1939 
1992 8 
1991 
1986 
1989 
1993 
1998 
1992 
1991 
1995 
Indefinite 
1993 
1993 
Deferred 
1992 
1987 
1994 
1992 
1992 
1998 
1991 
1991 
1995 
1992 
1989 
1997 
1995 
Indefinite 
1992 
1990 
1993 
1992 
1993 
Local Protection 
Reservoir 
Local Protection 
Chloride Control 
Local Protection 
Floodway and Levees 
Beach Erosion Control/ Shore 
Protection 
Reservoir 
Shoreline Protection 
Streambank Protection 
Local Protection 
Interior Drainage 
Streambank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Dam Safety 
Local Protection 
Reservoir 
Streambank Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
Shoreline Protection and 
Nourishment 
Streambank Protection 
Local Protection 
Reservoir 
Reservoirs and Levee 
Local Protection 
Reservoir, channel 
improvement 
Local Protection 
Streambank Protection 
Water Supply Modification 
Streambank Protection 
Local Protection 
Streambank Protection

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Dade County, FL........................................ ......... 
Deleware Coast Protection, DE............................ ......... 
Demonstration Erosion Control, MS................................. 
Des Moines Recreational River and Greenbelt, IA............. 
Dry Creek (Warm Springs) Lake & Channel...................... 
Dunbar (Sewage Facilities), WV (Sec 14)........................ 
East Bow Creek, Wynote, NE (Sec 14) .............................. 
East Nishnabotna River, Page County Bridge, IA (Sec 14) 
East St. Louis and Vicnity, IL - Rehabilitation.................... 
El Paso, TX ..................................... ............. 
Elizabeth, NJ ..................................... ............ 
Elk Creek Lake, OR ....................................... ....... 
Elkhorn River, West Point, NE (Sec 205)............................ 
Emeryville, Alameda, CA........................................ 
Eslava Creek, Mobile, AL(Sec 205) ................................. 
Evansville, IN................................ .... .............. 
Fairfield Vicinity Streams, CA ........................................ 
Falls Lake, NC....................................... ............ 
Fire Island Inlet to Montauk Point, NY............................... 
(Remainder) ...................................... .............. 
Fisher Ferry Road, MS (Sec 14) ....................................... 
Fletcher Creek, Memphis, TN (Sec 14) ............................ 
Fort Toulouse, Wetlampka, AL........................................... 
Four Rivers Basin, FL ...................................... ...... 
Fourche Bayou, Vicinity of Little Rock, AR .................... 
Fox River, Bridge Site #4, IA (Sec 14)............................. 
Fox River, Route J40 Bridge, IA (Sec 14)........................ 
Gallatin River, (1-90), Gallatin County, MT (Sec 14)......... 
Grand Mound, State Historic Site, MN (Sec 14) .............. 
Great Bend,KS.............................. .............. 
Greenwood Bendway, Site 3, MS ..................................... 
Greenwood Bendway, Site 4, MS ..................................... 
Greenwood Bendway, Site 5, MS ..................................... 
Guadalupe River, CA ........................................ ......... 
Guntersville Lake, Guntersville, AL ................................... 
Halstead,KS............... ........................................... ...... 
Hannibal, MO................................... ............ 
Humboldt, TN (Sec 205) ..................................................... 
Hurricane Creek , Prentiss Co., MS (Sec 14)....................... 
Isle of Wight Bay, Ocean City,MD (Sec 14)......................... 
Joe Pool Lake, TX ........................... ...................... 
Kahawainui Stream, Oahu, HI (Sec 205)............................. 
Kahoma Stream, Maui, HI ........................................ 
Kaskaskia Island Drainage & Leeve Dist., IL...................... 
Kirbyville, TX (Sec 205)................................. ...... 
Lake Chicot Pumping Plant, AR ....................................... 
Lake Erie, Fredonia, NY (Sec 14)..................................... 
Lake Pontchartrain, LA ...................................... ..... 
Lake Wichita, Holliday Creek, TX ................................... 
Larose to Golden Meadow, LA......................................... 
Lead Bayou, MS (Sec 205)................................................... 
Levisa & Tug Forks of the Big Sandy River & 
1975 
1971 
1985 
1989 
1967 
1986 
1992 
1992 
1988 
1971 
1972 
1971 
1989 
1992 
1988 
1939 
1985 
1973 
1963 
1963 
1987 
1991 
1991 
1966 
1987 
1992 
1992 
1991 
1990 
1987 
1986 
1987 
1987 
1992 
1988 
1989 
1989 
1986 
1989 
1989 
1975 
1989 
1986 
1980 
1989 
1981 
1992 
1967 
1987 
1972 
1982 
2038 
1990 2021 
Indefinite 
Indefinite 
1983 1993 
1987 
1992 1992 
1992 1992 
1995 
1973 Indefinite 
1991 
Indefinite 
1991 
1993 
1993 
1995 
1992 
1983 1994 
Indefinite 
Indefinite 
1990 
1991 1991 
1993 
1986 1995 
1991 
1992 1992 
1992 1992 
1992 1992 
1991 
1993 
1988 
1988 
1988 
1997 
1989 
1994 
1992 
1988 1988 
1990 1992 
1990 1991 
1986 1993 
1990 1990 
1990 1990 
1986 
1992 
1992 
1992 1992 
2013 
1995 
2002 
1988 1988 
Shore Protection 
Local Protection 
Local Protection 
Recreation 
Reservoir 
Streambank Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Beach Erosion Control 
Local Protection 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Streambank Protection 
Streambank Protection 
Local Protection 
Riverbank Protection 
Riverbank Protection 
Riverbank Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
S treambank Protection 
Shoreline Protection 
Reservoir 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Shoreline Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
B-2

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Cumberland River, KY, WV & VA.............................. 
Liberty State Park, Levee and Seawall, NJ (Sec 205)......... 
Little Blue River Lakes, MO.............................. ........... 
Little Calumet River, IN ..................................... .... 
Little Dell Lake, UT................................. 
Little Kanawha River, Glenville, WV (Sec 14) .................. 
Little Red River, Clinton, AR (Sec 205)............................. 
Lock Haven, PA ............................................................. 
Long Branch Lake, MO ..................................... ..... 
Loves Park, IL ................................................................. 
Lower Columbia River Bank Protection, OR and WA....... 
Lower Green River, King County, WA (Sec 205).............. 
Lower San Joaquin River, CA (Snagging & Clearing)....... 
Main Street, Wellsburg, WV.................... ........... 
Martin Creek, Prentiss Co., MS ........................................ 
Masefau Bay, Tutuila Island, American Samoa (Sec 14).. 
Maumee Bay State Park, OH ........................................... 
Mauvaise Terre, IL......................................... 
Mayfield Creek, KY........................... 
McGee Creek Drainage and Levee Dist., IL..................... 
Merced County Streams, CA ........................................... 
Middle River at Argyle, ND (Sec 205) ...................... 
Middle School, Wellsburg, WV.......................................... 
Mill Creek, OH ..................................... .......... 
Mill Creek, Dalton, GA .................................................... 
Mill Creek, Salem, OR (Sec 14) ....................................... 
Millington, TN ..................................... .......... 
Mingo Creek, OK...................................... ........ 
Miss. River Channel Improvements (AR, IL, KY, LA, 
MI, MO & TN)..................................... ......... 
Miss. River Levees .............................................................. 
Missouri River Levee System, IA, NE, KS, and MO ......... 
Mound State Park, Moundville, AL.................................... 
Mt. St. Helens Sediment Control, WA................................ 
Muddy Creek Cascade, Vaughn, MT (Sec 14) ................... 
Mudline to Pineville, MS ..................................... .. 
Murder Creek, Brewton, AL (Sec 205)................................... 
Muskegon (Duck Lake), MI (Sec 14) ............................... 
Muskingham River Lakes, OH ......................................... 
Muskingum River Lakes, OH 
(Dam Safety Assurance)........................................... 
New Orleans to Venice, LA............................................. 
Newark, OH ..................................... ............ 
NonconnanhCreek, TN & MS............................................. 
North Branch Chicago River, IL....................................... 
Oates Creek, GA ........................................ ......... 
O'Hare Reservoir, IL ....................................... ...... 
One Hundred Two River, Nodaway Co., MO 
County Road and Bridge (Sec 14)............................. 
Otter Creek, Shannon Hills, AR (Sec 205) ................... 
Paintsville Lake, KY .................................................. 
1981 
1987 
1978 
1990 
1985 
1986 
1985 
1991 
1973 
1991 
1961 
1988 
1985 
1992 
1986 
1989 
1990 
1985 
1992 
1979 
1985 
1985 
1992 
1981 
1990 
1990 
1990 
1988 
1928 
1928 
1948 
1991 
1986 
1992 
1984 
1986 
1990 
1976 
1982 
1969 
1976 
1990 
1988 
1990 
1990 
1991 
1984 
1973 
Indefinite 
1988 
1988 1992 
1996 
1993 
1987 
1986 1987 
1994 
1980 Indefinite 
1997 
Indefinite 
1992 
Indefinite 
1993 
1987 
1992 1992 
1991 1991 
1987 
1994 
1985 
Indefinite 
1990 1992 
1993 
Indefinite 
1990 1992 
1990 1993 
1992 
1996 
(4) 
(2) 
1990 
1985 
1991 
1992 
1984 
1983 
2010 
2008 
Indefinite 
1993 
1993 
1994 
1985 
1991 
1992 
1988 
1995 
2013 
1992 
1994 
1993 
1992 
1995 
1992 
1986 
1991 
Local Protection 
Shore Protection 
Reservoir 
Local Protection 
Reservoirs 
Streambank Protection 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Local Protection 
Local Protection 
Snagging and Clearing 
Streambank Protection 
Streambank Protection 
Shoreline Protection 
Shoreline Protection 
Local Protection 
Local Protection 
Local Protection 
Reservoirs 
Local Protection 
Streambank Protection 
Local Protection 
Snagging and Clearing 
Streambank Protection 
Local Protection 
Local Protection 
Channel Improvement 
Main Line Levees 
Local Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
S treambank Protection 
Local Protection 
Shoreline Protection 
Major Rehabilitation 
Modernization of Dams 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Reservoir 
S treambank Protection 
Local Protection 
Reservoir 
B-3

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Pajaro River, CA ........................................ ......... 
Panola-Quitman Item C, MS ............................................ 
Papillion Creek and Tributaries Lake, NE ........................ 
Pearl River, MS ..................................... ......... 
Pelucia Creek, Item 1, MS .................................. 
Pelucia Creek, Item 1A, MS ............................................ 
Pelucia Creek, Item 2....................................................... 
Pennypack Creek, Hatboro, PA........................................... 
Perkins Street Bridge, TN (Sec 14)...................................... 
Perry County L & D Nos. 1, 2, 3, MO.............................. 
Petit Jean River, Hwy 309, AR (Sec 14)............................. 
Phoenix, AZ, and Vicinity (including New River) ............. 
Plum Creek, Norden Dam Road, NE (Sec 14).................... 
Poquessing Creek, Bucks Co., PA .................................... 
Port Arthur and Vicinity, TX ........................................... 
Porter Bayou, MS (Sec 205) ............................................ 
Portersville Bay, Mobile County, AL ............................... 
Portugues and Bucana Rivers, PR....................................... 
Presque Isle Peninsula, PA (Permanent)........................... 
Proctor Creek, Atlanta, GA (Sec 205).................................. 
Pt. Leflore, MS ..................................... .......... 
R. D. Bailey Lake, WV ...................................... .... 
Raritan Bay and Sandy Hook Bay, NJ, Matawan 
and Union Beach Sections......................................... 
Ray Roberts Lake, TX................................... ....... 
Redbank & Fancher Creeks, CA....................................... 
Red River Basin Chloride Control (Area X) 
OK and TX................. ............ ........... 
Red River Below Deanson Dam ....................................... 
Reno Beach, Howard Farms, OH........................................ 
Republican River, Clifton, KS, Sewage 
Lagoon (Sec 14)..................................... ....... 
Reserve Sewage Lagoon, NM (Sec 14) ..................... 
Richmond, VA............................... ... ... ............. 
Roanoke River, Upper Basin, VA ..................................... 
Rochester, MN ..................................... .......... 
Roseau River Duxby Levee, MN.................................. 
Running Slough Ditch...................................... ..... 
Sabana Grande, PR (Sec 205) ........................................... 
Sacramento River Bank Protection, CA ........................... 
Sacramento River, Chico Landing to Red Bluff, CA ......... 
Sacramento River Flood Control, CA............................... 
Sacramento Urban Area Levee Reconstruction, CA........... 
Saginaw River, MI ....................................... ....... 
San Antonio Channel Improvement, TX............................. 
San Luis Rey River, CA................................. ....... 
Santa Ana River Mainstem, CA.......................................... 
San Vincente Arroyo, Silver Spring, NM ........................... 
Savan Gut, VI (Sec 205) .................................... 
Saw Mill River at Ardslay ............................. 
Saylorville Lake, IA ........................................ ................ 
1987 
1984 
1972 
1984 
1985 
1987 
1990 
1988 
1987 
1977 
1991 
1980 
1991 
1987 
1966 
1982 
1992 
1975 
1990 
1989 
1985 
1967 
1965 
1975 
1987 
1991 
1971 
1990 
1992 
1986 
1989 
1990 
1987 
1991 
1990 
1987 
1963 
1963 
1918 
1990 
1965 
1957 
1988 
1990 
1988 
1987 
1987 
1965 
1989 
1974 
1989 
1989 
1985 
1991 
1992 
1988 
1984 
1986 
1987 
1992 
1989 
1993 
1995 
1985 
1987 
1987 
1993 
1989 
1990 
1985 
1991 
1994 
1992 
1988 
1995 
1988 
1992 
1993 
1993 
1992 
1986 
1988 
Indefinite 
1996 
1993 
Local Protection 
Local Protection 
Reservoirs 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Breakwaters 
Local Protection 
Streambank Protection 
Reservoir 
Local Protection 
Reservoir 
Reservoir 
Indefinite Chloride Control 
Indefinite Levee & Streambank 
Protection 
1992 Shoreline Protection 
1992 1992 
1989 1987 
1993 
1997 
1995 
1992 1992 
1990 1990 
1989 1990 
1996 
Indefinite 
Indefinite 
1993 
1979 Indefinite 
1996 
1996 
Indefinite 
1988 1988 
1989 1990 
1989 1990 
1977 1994 
Streambank Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Reservoir 
B-4

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Scotts Creek, Newberry, SC (Sec 205) ............................. 
Sewer Line Protection, Valley, AL (Sec 14)....................... 
Sewer Outfall, Glendale, WV ............................................ 
Sheyenne River, ND ..................... ...... 
Shupe Run, Mt. Pleasant, PA ............................................ 
Sicily Island, LA, Levee ......................................... 
Silver Creek, Rome, GA (Sec 205)...................................... 
Sim s Bayou, TX .................................................................. 
Sims Park, Euclid, OH (Sec 103)...................................... 
Soap Creek, Bridge Site 3, IA (Sec 14)............................... 
Socastee Creek, Harry conty, SC (Sec 205)........................ 
Solomon Creek, Ashley, PA (Sec 14) ............................... 
Solomons Island, Calvert County, MD (Sec 14)................. 
Sope Creek, Marietta, GA...................................... 
Souris River Basin, ND..................................... ... 
South Platte River, Logan County Bridge, 
Proctor, CO (Sec 14).................................. ..... 
South Shore Park, Milwaukee County, WI....................... 
Southwestern Jefferson County, KY ................................. 
Sowashee Creek, Meridian, MS....................................... 
State Highway 111 Bridge, Lake Texoma, TX (Sec 14) .... 
State Road and Ebner Coulees, WI................................... 
Steele Bayou, MS ...................................... ......... 
St. Francis Basin ........................................ ......... 
St. Paul, MN........................ .. .... ............. 
Stonewall Jackson Lake, WV ........................................... 
Swan Creek, Taney County, MO (Sec 14).......................... 
Sweetwater River, CA...................................................... 
Tallahatchie River, Site 1, MS .......................................... 
Tama, IA (Sec 205) ....................................... ....... 
Taylors Bayou, TX ........................................................... 
Taylorsville Lake, KY ...................................... ..... 
Tensas Cocodrie Pumping Plant, LA ............................... 
Tensas Cocodrie, LA, Levee (5)........................................ 
Texas City and Vicinity, TX (1958 authorization) ............. 
Threemile Creek, AL................................. ......... 
Tombigbee River Tributaries, AL and MS ....................... 
Town Brook, Quincy;, MA ....................................... 
Town River Bay, Quincy, MA (Sec 14) ........................... 
Tributary Kill Creek, DeSoto, KS, Sewage 
Treatment Plant (Sec 14) ............ ...................... 
Tulsa and Wst Tulsa, OK................................................. 
Tynes Branch, Houston School Road Bridge, Itawamba 
Co., MS ........................................................................ 
Upper Scioto River, Marion County, OH (Sec 205)........... 
Upper Yazoo Projects, MS ................................................. 
U.S. Hwy. 11 Bridge, Fosters, AL (Sec 14)........................ 
U.S. Hwy. 82 Bridge, Columbus, MS (Sec 14) .................. 
U.S. Hwy 190, Bridge, Sabine River, 
Merryville, LA (Sec 214)..................... .................. 
1986 
1985 
1992 
1990 
1992 
1983 
1989 
1990 
1992 
1992 
1992 
1992 
1992 
1986 
1985 
1992 
1992 
1974 
1988 
1992 
1988 
1966 
1938 
1991 
1977 
1984 
1972 
1988 
1991 
1982 
1974 
1983 
1974 
1962 
1988 
1965 
1992 
1992 
1992 
1943 
1986 
1986 
1976 
1985 
1985 
1991 
1986 
1991 
1992 
1992 
1988 
1989 
1992 
1999 
1992 
20005 
1992 
2002 
1992 
1992 
1993 
1993 
1993 
1990 
1994 
1992 1992 
1993 1993 
1983 1993 
1992 1993 
1994 
1993 
2010 
(4) 1999 
1994 
1988 
1986 1986 
1993 
1988 
1994 
1994 
1983 1990 
Indefinite 6 
19927 
1987 1992 
1992 1993 
1990 Indefinite 
1997 
1992 1992 
1992 
1945 
1986 
1986 
1992 
1992 
1993 9 
1987 
1987 
2013 
1986 
1986 
1993 
Local Protection 
Sewer Line Protection 
S treambank Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Local Protection 
Shoreline Protection and 
Nourishment 
Streambank Protection 
Local Protection 
S treambank Protection 
Streambank Protection 
Local Protection 
Reservoir 
Streambank Protection 
Shoreline Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Tributary levees & channels 
Local Protection 
Reservoir 
Streambank Protection 
Local Protection 
Riverbank Protection 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Bridge Protection 
Local Protection 
Local Protection 
Streambank Protection 
Streambank Protection 
Streambank Protection 
B-5

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
U.S. Interstate 59 Bridges, Fosters, AL (Sec 14)................. 
Valley Creek, AL (Sec 14)............. ................................. 
Village Creek, AL ....................................... ........ 
Vince and Little Vince Bayous, TX .................................. 
Wabasha, Mississippi River, MN (Sec 14) ....................... 
Walnut Creek, CA ............................................................ 
Warner Road, Mississippi River, St. Paul, MN (Sec 14)..... 
Westerly Creek, Colorado.............................. ....... 
West Des Moines, IA ...................................... ...... 
West Ray, Marshall, PA (Sec 14) ..................................... 
West River, New Haven, CT (Sec 205) ............................ 
West Tennessee Tributaries ............................................. 
Westwego to Harvey, LA................................ ...... 
Wheeler Creek, Gainesville, TX (Sec 205)....................... 
White River, Batesville, AR (Sec 14) ............................... 
White River, Jacksonport, AR (Sec 205).......................... 
White River, Newport, AR (Sec 14).................................... 
White River, St. Paul, AR (Sec 208).................................... 
White River, Tripp Sounty, SD (Sec 14) .......................... 
Wildcat and San Pablo Creeks, CA..................................... 
Wilamette River Basin Bank Protection, OR...................... 
Willow Creek Lake, OR.................................. ...... 
Wolf River at 2nd Street, Memphis, TN (Sec 14)................ 
Wyoming Valley, PA...................................... ...... 
Yatesville Lake, KY..................... ....... 
Zintel Canyon, Kennewick, WA....................................... 
1985 
1985 
1989 
1968 
1989 
1964 
1989 
1988 
1991 
1990 
1991 
1960 
1991 
1983 
1984 
1984 
1988 
1988 
1991 
1980 
1938 
1991 
1988 
1983 
1964 
1992 
1986 
1989 
1992 
1991 
1990 
1094 
1986 
1986 
1989 
1990 
1992 
1989 
1976 
1993 
1987 
1986 
1994 
1990 
1992 
1994 
1992 
1992 
1997 
1990 
1993 
Indefinite 1 
2002 
1984 
1986 
1986 
1989 
1990 
1992 
1995 
Indefinite 
1994 
1990 
1991 
1991 
1993 
Streambank Protection 
Sewerline Protection 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Local Protection 
Streambank Protection 
Local Protection 
Drainage and Flood Control 
Local Protection 
Local Protection 
Local Protection 
Local Protection 
Streambank Protection 
Snagging and Clearing 
Streambank Protection 
Local Protection 
Local Protection 
Reservoir 
Local Protection 
Rehabilitation of levee system 
Reservoir 
Local Protection 
1 Construction of further channel improvement was halted in 1987 due to the denial of water quality certification. 
Construction work currently underway includes the stabilization of bridge, utility and tributary crossings in the 
uncompleted portion of the project. 
2 Project was in useful operation before Corps started working on it. Work consists primarily of improvements to 
existing channels, levees, pumping stations and other flood control structures. 
3. Completion of Stage I (Truscott facilities) only. Stage II (Ross facilities) indefinite. 
4. Remaining recreation unscheduled. Lawsuit was resolved by a Consent Decree Feb 10, 1992. The Decree was for the City of 
Edmond and the Edmond Public Works Authority to reimburse the government $7,207,636 over a period of 40 years for the 
recreation contract and $16,253, 644 for the water supply contract over a period of 43 years. 
5 Project consists of levee upgrade and enlargement. 
B-6

APPENDIX B (Continued) 
FLOOD CONTROL PROJECTS UNDER CONSTRUCTION DURING FISCAL 
YEAR 1992 
6 Durham Prong Diversion local support problem. 
7 Item 2A temporarily deferred. 
8 A maintenance contract for a culvert replacement was completed Nov 1990. 
9 Present work is for repair of the levee and pipes. 
BEACH EROSION CONTROL PROJECTS UNDER CONSTRUCTION 
DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion 
Revere Beach, Revere, MA 
Southeast Lighthouse Block Island, RI 
Woodmont Beach, Milford, CT 
1991 
1993 
1992 
1992 1992 
1993 
1993 
B-7

APPENDIX C 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Type
1
l (feet) Opened (miles) (feet) (fe(t) 
Alabama-Coosa Rivers, AL 
Claiborne Lock & Dam 
Millers Ferry Lock and 
Dam 
Jones Bluff Lock and Dam 
Allegheny River, PA and NY 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
Lock and Dam No. 6 
Lock and Dam No. 7 
Lock and Dam No. 8 
Lock and Dam No. 9 
Apalachicola, Chattahoochee, 
and Flint Rivers, GA, AL 
and FL 
Jim Woodruff Lock 
and Dam 
George W. Andrews 
Lock and Dam 
Walter F. George 
Lock and Dam 
Atlantic Intracoastal 
Wasterway 
Albemarle and Chesapeake 
Canal Route: 
Great Bridge Lock 
Dismal Swamp Canal 
Route: 
Deep Creek Lock 
South Mills Lock 
Bayou Teche, LA 
Berwick Lock 
Keystone Lock 
Black Rock Channel and 
Tonawonda Harbor, NY 
Black Rock Lock 
Black Warrior, Warrior 
and Tombigbee Rivers, AL 
Coffeeville (Jackson) 
Lock and Dam 
Demopolis Lock and Dam 
Armstead I. Selden Lock 
and Dam 
Wm. Bacon Oliver 
Lock and Dam (Replacement) 
HoltL ock and Dam 
John Hollis Bankhead 
Lock and Dam (New Lock) 
Canaveral Harbor, FL 
Canaveral Lock 
Cape Fear River, NC 
Lock and Dam No. 1 
Lock and Dam No. 2 
William O. Huske 
Lock and Dam 
Central and Southern Florida 
S-61 Lock 
S-65 Lock 
S-65A Lock 
S-65B Lock 
S-65C Lock 
81.82 
142.32 
254.42 
6.7 
14.5 
24.2 
30.4 
36.3 
45.7 
52.6 
62.2 
Qaibome, AL 
Camden, AL 
Benton, AL 
Aspinwall, PA 
Cheswick, PA 
Natrona, PA 
Freeport, PA 
Qinton, PA 
Kittanning, PA 
Templeton, PA 
Rimer, PA 
84 600 30 16 13 Movable 3,1603 1973 60.5 9 200 
84 600 45 16 13 Movable 9,9003 1969 103.1 9 200 
84 600 45 16 13 Movable 14,9623 1974 88.0 9 200 
56 360 
56 360 
56 360 
56 360 
56 360 
56 360 
56 360 
56 360 
11 
13 
10 
12 
12 
13 
18 
22 
11 
12
9 
10 
11 
11 
14 
11 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
1,393 19342 
1,436 193420 
876 1927 
780 1927 
1,140 1928 
916 1930 
984 1931 
950 1938 
7.8 9 
9.7 9 
6.2 9 
5.9 9 
9.4 9 
6.9 9 
9.6 9 
9.8 9 
200 
200 
200 
200 
200 
200 
200 
200 
107.64 Chattahoochee, FL 82 450 33 14 14 Movable 5,924 1957 46.7 6 100 
182.85 Columbia, GA 
182.85 Fort Gaines, GA 
82 450 25 19 13 Movable 620 1963 28.5 6 100 
82 450 88 18 13 Movable 13,371 1963 85.0 6 100 
11.56 Great Bridge, VA 72 530 3 167 167 
10.66 
33.26 
1.53 
72.53 
Deep Creek, VA 
South Mills, NC 
Berwick, LA 
New Iberia, LA 
0.0 Buffalo, NY 
None 
52 300 12 127 127 None 
52 300 12 127 127 None 
45 307 79 97 97 
36 162 9 9 9 
None 
Fixed 
1932 12 90 
1940 6 50 
1941 6 
1950 
175 1913 
68 625 5 21.6 21.6 None 
50 
8 80 
34.5 6 50 
1914 7.1 21 200 
116.610 Coffeeville, AL 110 600 33 13 13 Movable 1,185 1965 96.6 9 200 
213.210 Demopolis, AL 110 600 40 13 13 Fixed 1,485 1962 47.9 9 200 
261.110 
32770 
347.010 
Eutaw, AL 
Tuscaloose, AL 
Holt, AL 
365.1 Adger, AL 
2.7 Cocoa, FL 
67.0 Kings Bluff, NC 40 
99.0 Browns Landing, NC 40 
123.0 Tolars Landing, NC 40 
0.0 
56.0 
46.0 
32.0 
25.0 
St. Cloud, FL 
Frostproof, FL 
Avon Park, FL 
Sebring, FL 
Sebring, FL 
110 600 22 13 13 Movable 1,832 1962 77.0 9 200 
110 600 28 18 
110 600 64 19 
18 Fixed 800 n/a 8.9 9 200 
13 Movable 1,138 1969 18.1 9 200 
110 600 68 13 13 Fixed 1,170 1975 42.7 9 200 
90 600 3 14 14 None 
200 11 9 9 Fixed 
200 9 12 12 Fixed 
300 9 9 9 Fixed 
90 
90 
90 
90 
90 
None 
None 
None 
None 
None 
1965 12 125 
275 1915 32.0 8 100 
229 1917 24.0 8 100 
220 1935 20.0 8 100 
1963 
1964 
1967 
1965 
1965 
8 
28.0 3 
10.0 3 
14.0 3 
7.0 3 
20 
30 
30 
30 
30 
C-1

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
Central and Southern Florida (continued) 
S-65D Lock 
S-65E Lock 
S-308B 
S-310 
16.0 
12.0 
38.7 
0.0 
Okeechobee, FL 
Okechobee, FL 
Port Mayaca, FL 
Clewiston, FL 
Chicago Harbor, IL 
Chicago Lock 0.0 Chicago, IL 
30 90 6 6 
30 90 5 6 
56 400 14 14 
50 60 5 13 
80 600 4 23 
None 
None 
Movable 
Movable 
23 None 
1964 
1964 
1977 
1980 
9.0 3 
4.0 3 
5.0 8 
.5 6 
30 
30 
100 
50 
1939 .15 21 470 
Columbia River, OR and WA 
Bonneville Lock and Dam 
The Dalles Lock and Dam 
John Day Lock and Dam 
McNary Lock and Dam 
Cross-Florida Barge Canal 
Inglis Lock, Dam 
and Spillway 
Eureka Lock and Dam 
Harry H. Buckman Lock 
Cumberland River, KY 
and TN 
Barkley Dam 
Cheatham Lock and Dam 
Old Hickory Lock and Dam 
Cordell Hull Dam 
and Reservoir 
Fox River, WI 
DePere Lock 
DePere Dam 
Little Kaukauna Lock 
Little Kaukauna Dam 
Rapide Croche Lock 
Rapide Croche Dam 
Kaukauna Fifth Lock 
Kaukauna Fourth Lock 
Kaukauna Third Lock 
Kaukauna Second Lock 
Kaukauna First Lock 
Kaukauna Dam 
Kaukauna Guard Lock 
Little Chute combined Lock 
Lower 
Upper 
Little Chute Second Lock 
Little Chute First 
(Guard) Lock 
Little Chute Dam 
Cedars Lock 
Cedars Dam 
Appleton Fourth Lock 
Appleton Lower Dam 
Appleton Third Lock 
Appleton Second Lock 
Appleton First Lock 
Appleton Upper Dam 
Menasha Lock 
Menasha Dam 
Freshwater Bayou, LA 
Freshwater Bayou Lock 
Green and Barren Rivers, KY 
Green River: 
Lock and Dam No. 1 
Lock and Dam No. 2 
Gulf Intracoastal Waterway 
Inner Harbor Navigation 
Channel Lock 
Harvey Lock 
146.0 Bonneville, OR 
190.0 The Dalles, OR 
215.0 Rufus, OR 
292.0 Umatilla, OR 
168.611 Inglis, FL 
20.0 Spare, FL 
90.4 Palatka, FL 
76 500 65 32 24 Movable 2,680 1938 
86 675 88 15 15 Movable 8,735 1957 
86 675 110 15 15 Movable 5,900 1968 
86 675 75 15 20 Movable 7,365 1953 
84 
84 
84 
600 28 18 
600 20 14 
600 20 14 
30.6 Kuttawa, KY 110 800 57 
148.7 Ashland City, TN 110 800 26 
216.2 Old Hickory, TN 84 400 60 
313.5 Carthage, TN 
7.1 
7.2 
13.0 
13.1 
19.2 
19.3 
22.8 
23.1 
23.3 
23.4 
23.6 
24.0 
24.0 
25.4 
25.4 
26.4 
26.5 
26.6 
27.3 
27.4 
30.7 
30.9 
31.3 
31.6 
31.9 
32.2 
37.8 
37.8 
Movable 5,100 1968 
Movable 3,830 1971 
None 1972 
Movable 9,959 1964 
Movable 801 1959 
Movable 3,605 1957 
11 
14 
14 
47.5 27 
25,0 14 
76.0 14 
64.0 14 
300 
250 
250 
250 
11.0 12 150 
12 150 
21.2 12 150 
118.1 9 150 
67.5 9 150 
97.3 9 150 
84 400 59 14 13 Movable 1,138 1973 71.9 9 150 
DePetr, WI 
DePere, WI 
DePere, WI 
DePere, WI 
Wrightstown, WI 
Wrightstown, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Kaukauna, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Little Chute, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Appleton, WI 
Menasha, WI 
Menasha, WI 
146 
146 
146 
144 
144 
144 
144 
144 
147 
144 
144 
144 
144 
144 
145 
145 
144 
9
7
8
9 
10 
10 
10 
11 
9 
11 
11 
14 
7 
10 
8
9 
10 
10 
8 
10 12 
8 10 
9 10 
7 9 
7 6 
7 6 
6 6 
7 6 
19.08 Intracoastal City, LA 84 600 16 
9.1 Spottsville, KY 84 600 12 12 
63.1 Calhoun, KY 84 600 14 15 
92.612 
98.312 
New Orleans, LA 
Harvey, LA 
1936 5.9 6 100 
Movable 986 1929 
1938 6.2 6 100 
Movable 588 1926 
1934 3.6 6 100 
Movable 461 1930 
1898 0.3 6 100 
1879 0.2 6 100 
1879 0.1 6 100 
1903 0.2 6 100 
1883 0.4 6 100 
Movable 603 1931 
1891 1.4 6 100 
1879 6 100 
1879 6 100 
1881 1.0 6 100 
1904 0.7 6 100 
Movable 562 1932 
1888 3.4 6 100 
Movable 654 1933 
1907 0.6 6 100 
Movable 549 1934 
1900 0.3 6 100 
1901 0.3 6 100 
1884 5.1 6 100 
Movable 691 1940 
1899 28.3 6 100 
Movable 401 1937 
16 None 
11 Fixed 
12 Fixed 
75 640 99 317 317 None 
75 425 109 127 127 None 
1968 12 125 
482 1956 54.0 9 200 
519 1956 45.4 9 200 
1923 
1934 
12 150 
12 125 
C-2

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
Gulf Intracoastal Waterway (continued) 
Algiers Lock 
Bayou Bouef Lock 
Bayou Sorrel Lock 
Port Allen Lock 
Calcasieu Lock 
Brazos River Floodgates 
Colorado River 
East Lock 
West Lock 
Hudson River, NY 
Troy Lock and Dam 
Illinois Waterway, IL 
LaGrange Lock and Dam 
Peoria Lock and Dam 
Starved Rock Lock 
and Dam 
Marseilles Lock 
Marseilles Dam 
Dresden Island 
Lock and Dam 
Brandon Road Lock 
and Dam 
Lockport Lock 
Thomas J. O'Brien 
Lock and Dam 
Inland Route, MI 
Crooked River 
Lock and Weir 
Kanawha River, WV 
Winfield Lock and Dam 
Marmt Lock and Dam 
London Lock and Dam 
Kaskaskia River, IL 
Kaskaskia Lock and Dam 
Kentucky River, KY 
Lock and Dam No. 1 
Lock and Dam No. 2 
Lock and Dam No. 3 
Lock and Dam No. 4 
Lock and Dam No. 5 
Lock and Dam No. 62 
Lock and Dam No. 7
2 
Lock and Dam No. 8 
Lock and Dam No.9 
24 
Lock and Dam No. 10 
Lock and Dam No. 112 
Lock and Dam No. 122 
Lock and Dam No. 13
2 
Lock and Dam No. 142 
Lake Washington Ship Canal 
Kiram M. Chittenden Lock 
Large Lock 
Small Lock 
McClellan-Kerr Arkansas 
River Navigation System, 
AR and OK 
Norell Lock and Dam 
Wilbur D. Mills, Lock No. 2 
Dam No. 2 
88.012 
93.3 
131.013 
228.512 
238.513 
404.113 
Algiers, LA 
Morgan City, LA 
Plaquemine, LA 
Port Allen, LA 
Lake Charles, LA 
Freeport, TX 
75 
75 
56 
84 
75 
75 
797 
1,158 
800 
1,198 
1,205 
109 
69 
109 
45 
69 
137 
137 
14
7 
14
7 
137 
157 
137 
13
7 
147 
147 
13
7 
15
7 
444.8 Matagorda, TX 75 1,200 59 15 157 
444.8 Matagorda, TX 75 1,200 59 15
7 15 
153.8 Troy, NY 
None 
None 
None 
None 
None 
None 
None 
None 
1956 
1954 
1952 
1961 
1950 
1943 
1954 
1954 
45 493 17 16 13 Fixed 1,495 1917 
16 
16 
12 
12 
16 
12 
150 
150 
125 
125 
200 
125 
12 125 
12 125 
22 14 200 
80.2 Beardstown, IL 110 600 10 16 13 Movable 1,066 1939 77.5 9 300 
157.7 PoriaI,L 110 600 11 16 12 Movable 536 1939 73.3 9 300 
231.0 Uitca, IL 
244.6 Marseilles, IL 
247.0 Marseilles, IL 
271.5 Morris, IL 
286.0 Joliet, IL 
291.1 Lockport, IL 
326.5 Chicago, IL 
30.0 Alanson, MI 
31.1 
67.8 
82.8 
Winfield, WV 
Marmet, WV 
London, WV 
.8 Ellis Grove, IL 
4.0 
31.0 
42.0 
65.0 
82.2 
96.2 
117.0 
139.9 
157.5 
176.4 
201.0 
220.9 
239.9 
249.0 
Carrolton, KY 
Lockport, KY 
Gest, KY 
Frankfort, KY 
Tyrone, KY 
High Bridge, KY 
High Bridge, KY 
Camp Nelson, KY 
Valley View, KY 
Ford, KY 
Irvine, KY 
Ravenna, KY 
Willow, KY 
Heidelberg, KY 
1.3 Seattle, WA 
1.3 Seattle, WA 
10.3 
13.3 
40.5 
Arkansas Post, AR 
Arkansas Post, AR 
Arkansas Post, AR 
110 600 19 17 14 Movable 1,280 1933 13.6 9 
110 600 24 19 14 1933 26.9 9 
Movable 819 1933 24.6 
300 
300 
110 600 22 17 12 Movable 1,616 1933 14.5 9 300 
110 600 34 18 14 Movable 2,373 1933 5.1 9 300 
110 600 40 12 15 None 1933 9 300 
110 1,000 2 14 14 Movable 257 1960 6.9 9 300 
17.8 66 1 6.9 7.9 SSP Weir 83 1967 4.0 5 30 
56 
56 
56 
360 
360 
360 
28 
24 
24 
12 
12 
12 
Movable 834 1937 
Movable 707 1934 
Movable 707 1934 
36.7 9 300 
15.0 9 300 
7.8 9 300 
84 600 32 18 11 Movable 130 1973 35.0 9 225 
38 
38 
38 
38 
38 
52 
52 
52 
52 
52 
52 
52 
52 
52 
145 
145 
145 
145 
145 
147 
147 
146 
148 
148 
148 
148 
148 
148 
8 
14 
13 
13 
15 
14 
15 
19 
17 
17 
18 
17 
18 
17 
88 
96 
10
9
9 
11 
11
9 
10 
10 
10
9 
80 760 26 33.5 
28 123 26 166 
110 
110 
600 30 16 
600 20 18 
15
6
766 
6
7
6
7
6
6
6
6
6 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
Fixed 
424 1839 
400 1939 
465 1844 
534 1844 
556 1844 
413 1891 
350 1897 
257 1900 
362 1907 
472 1907 
208 1906 
240 1910 
248 1915 
248 1917 
29 Movable 235 1916 
16 Movable 235 1916 
15 Fixed *4,577 1967 
14 1967 
Movable *42,073 1968 
27.0 6 
11.0 6 
23.0 6 
17.2 6 
14.0 6 
20.8 6 
22.9 6 
17.6 6 
18.9 6 
24.6 6 
19.9 6 
19.0 6 
9.1 6 
9.6 6 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
100 
17.0 34 150 
17.0 34 150 
3.0 9 250 
36.9 9 250 
C-3

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
McClellan-Kerr Arkansas 
River Navigation System, 
AR and OK (continued) 
Joe Hardin Lock and Dan (No. 3) 
Emmett O. Sanders Lock 
and Dam (No. 4) 
Lock and Dam No. 5 
David D. Terry Lock 
and Dam 
Murray Lock and Dam 
Toad Suck Ferry Lock 
and Dam 
Arthur V. Ormond Lock 
and Dam No. 9 
Dardanelle Lock and Dam 
Ozark-JetaTaylor Lock * 
James W. Trimble 
Lock and Dam N(o. 13) 
W. D. Mayo Lock and Dam 
Robert S. Kerr Lock and 
Dam and Reservoir 
Webbers Falls Lock and 
Dam 
Chouteau Lock and Dam 
Newt Graham Lock 
and Dam 
Mississippi River 
Between Ohio and Missouri 
Rivers 
Lock and Dam No. 27 
Mississippi River Between 
Missouri River and 
Minneapolis, MN 
Locak and Dam No. 26 
2 6 
Melvin Price Locks & Dam 
Lock and Dam No. 25 
Lock and Dam No. 24 
Lock and Dam No. 22 
Lock and Dam No. 21 
Lock and Dam No. 20 
Lock and Dam No. 19 
Lock and Dam No. 18 
Lock and Dam No. 17 
Lock and Dam No. 16 
Lock and Dam No. 15 
Lock and Dam No. 14 
Lock and Dam No. 13 
Lock and Dam No. 12 
Lock and Dam No. 11 
Lock and Dam No. 10 
Lock and Dam No. 9 
Lock and Dam No. 8 
Lock and Dam No. 7 
Lock and Dam No. 6 
Lock and Dam No. 5A 
Lock and Dam No. 5 
Lock and Dam No. 4 
Lock and Dam No. 3 
Lock and Dam No. 2 
Lock and Dam No. 1 
50.2 Grady, AR 
66.0 Pine Bluff, AR 
86.3 Redfield, AR 
108.1 Little Rock, AR 
125.4 Little Rock, AR 
155.9 Conway, AR 
176.9 Morrilton, AR 
205.5 Russellville, AR 
256.8 Ozark, AR 
292.8 Fort Smith, AR 
319.6 Fort Smith, AR 
336.2 SallisawOK 
366.6 Webbers Falls, OK 
401.4 Muskogee, OK 
4421.7 Inola, OK 
185.114 Granite City, IL 
202.915 Alton, IL 
200.8 Alton, IL 
241.4 
15 
Cap Au Gris, MO 
273.415 Clarksville, MO 
301.215 Saverton, MO 
324.915 Quincy, IL 
343.215 Canton, MO 
364.215 Keokuk, IA 
410.515 Burlington, IA 
437.115 New Boston, IL 
457.215 Muscatine, IA 
482.915 Rock Island, IL 
493.115 LcClair, IA 
493.315 LeClaire, IA 
522.5
1 5 
Clinton, IA 
556.715 Bellevue, IA 
583.015 Dubuque, IA 
615.115 Guttenberg, IA 
647.915 Lynxville, IA 
679.215 Genoa, WI 
702.515 Dresbach, MN 
714.315 Trempealeau, WI 
728.515 Winona, MN 
738.115 Minneiska, MN 
752.815 Alma, WI 
796.915 Red Wing, MN 
815.215 Hastings, MN 
847.615 Minneapolis,, MN 
St. Paul 
110 600 20 18 14 Movable *6,1110 1968 
110 600 14 18 
110 600 17 18 
110 600 18 18 
110 600 18 18 
110 600 16 18 
110 
110 
110 
110 
110 
600 19 18 
600 54 18 
600 34 18 
14 Movable *5,745 1968 
14 Movable *7,455 1968 
14 Movable *8,890 1968 
14 Movable (3,930 1969 
14 Movable *1,580 1969 
14 Movable *1,505 1969 
14 Movable **1,815 1969 
15 Movable *12,480 1969 
600 20 18 14 Movable *4,725 1969 
600 20 14 15 Movable 7,400 1970 
110 600 48 18 
110 600 30 19 
110 600 21 15 
14 Movable 7,230 1970 
16 Movable 4,370 
14 Movable 11,690 1970 
110 600 21 15 14 Movable 11,630 1970 
110 1,200 21 16 
110 
110 
110 
110 
110 
110 
110 
110 
110 
100 
110 
110 
110 
80 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
56 
600 24 
360 24 
1,200 24 
600 15 
600 15 
600 10 
600 10 
600 10 
1,200 38 
600 10 
600 8 
600 9 
600 16 
360 16 
320 11 
600 11 
600 11 
600 9 
600 11 
600 8 
600 9 
600 11 
600 8 
600 7 
600 6 
600 9 
600 7 
600 8 
600 12 
400 38 
400 38 
19 
16 
23 
19 
19 
18 
17 
15 
15 
17 
16 
17 
27 
27 
18 
21 
19 
17 
19 
15 
16 
22 
18 
17 
18 
18 
17 
17 
22 
13 
13 
15.8 9 250 
20.3 9 250 
21.8 9 250 
17.3 9 250 
30.5 9 250 
21.0 9 250 
28.6 9 250 
51.3 9 250 
36.0 9 250 
26.8 9 250 
16.6 9 250 
30.4 9 250 
1970 34.8 9 
20.2 9 150 
23.7 9 150 
15 Fixed 3,240 1953 17.8 9 200 
10 Movable 1,725 1938 
10 
18 Moveable 1160 1990 
12 Movable 1,296 1939 
12 Movable 4,280 1940 
14 Movable 1,024 1938 
12 Movable 1,066 1938 
12 Movable 2,144 1936 
13 Fixed 4,434 1913 
14 Movable 1,350 1937 
13 Movable 921 1939 
12 Movable 1,099 1937 
11 Movable 1,203 1934 
11 
11 1922 
14 Movable 1,343 1939 
13 Movable 1,066 1939 
13 Movable 849 1938 
13 Movable 1,278 1937 
12 Movable 763 1937 
13 Movable 811 1937 
14 Movable 935 1937 
12 Movable 940 1937 
13 Movable 893 1936 
13 Movable 682 1936 
12 Movable 1,619 1935 
13 Movable 1,367 1935 
14 Movable 365 1938 
13 Movable 822 1930 
8 Fixed 574 1932 
10 1917 
38.5 9 300 
40.6 9 300 
32.0 9 300 
27.8 9 300 
23.7 9 NS 
18.3 9 NS 
21.0 9 NS 
46.3 9 NS 
26.6 9 NS 
20.1 9 NS 
25.7 9 NS 
10.4 9 NS 
29.2 9 NS 
34.2 9 NS 
26.3 9 NS 
32.1 9 NS 
32.8 9 NS 
31.3 9 NS 
23.3 9 NS 
11.8 9 NS 
14.2 9 NS 
9.6 9 NS 
14.7 9 NS 
44.1 9 NS 
18.3 9 NS 
32.4 9 NS 
5.7 9 NS 
C-4

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
St. Anthony Falls 
Lower Lock and Dam 
Upper Lock and Dam 
Monongahela River, PA 
and WV 
Locks and Dam No. 2 
Locks and Dam No. 3 
Locks and Dam No. 4 
Maxwell Locks and Dam 
Locks and Dam No. 7 
Point Marion, Lock 8 Replacement 
Morgantown Lock and Dam 
Hildebrand Lock and Dam 
Opekiska Lock and Dam 
Ohio River 
Locks and Dam No. 53 
Locks and Dam No. 52 
Smithland Locks and Dam 
Uniontown Locks and Dam 
Newburgh Locks and Dam 
Cannelton Locks and Dam 
McAlpine Locks and Dam 
Markland Locks and Dam 
Captain Anthony Meldahl 
Locks and Dam 
Greenup Locks and Dam 
Gallipolis Locks and Dam 
Racine Locks and Dam 
Belleville Locks and Dam 
Willow Island Locks 
and Dam 
Hannibal Locks and Dam 
Pike Island Locks and Dam 
New Cumberland Locks 
and Dam 
Montgomery Island Locks 
and Dam 
Dushield Locks and Dam 
Emsworth Locks and Dam 
Okeechobee Waterway, FL 
St. Lucie Lock and Dam 
Moore Haven Lock 
Ortona Lock and Dam 
W. P. Franklin Lock and 
Control Structure 
Port Mayoca 
853.315 Minneapolis, MN 56 400 25 14 10 Movable 188 1956 0.6 9 100 
853.915 Minneapolis, MN 56 400 49 16 14 Fixed 3,584 1963 3.8 9 100 
11.2 Braddock, PA 
23.8 Elizabeth, PA 
41.5 MonessenP,A 
61.2 Maxwell, PA 
85.0 Greensboro, PA 
90.8 Point Marion, PA 
102.0 Morgantown, WV 
108.0 Morgantown, WV 
115.4 Morgantown, WV 
18.4 Mound City, IL 
42.1 Brookport, IL 
35.3 Smithland, KY 
135.0 Uniontown, KY 
204.9 Newburgh, IN 
260.3 Cannelton, IN 
374.2 Louisville, KY 
449.5 Markland, IN 
544.8 Chilo, OH 
640.0 Greenup, KY 
701.8 Hogsett, WV 
743.5 Letart Falls, OH 
777.1 Reedsville, OH 
819.3 Waverly, WV 
854.6 New Martinsville 
, WV 
896.7 Warwood, WV 
926.6 Stratton, OH 
949.3 Industry, PA 
967.7 Glenwillard, PA 
974.8 Emsworth, PA 
15.1 Stuart, FL 
78.0 Moore Haven, FL 
93.6 LaBelle, FL 
121.4 Fort Myers, FL 
38.5 Pahokee, FL 
56 
110 
56 
56 
56 
56 
84 
84 
56 
56 
84 
84 
84 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
56 
110 
56 
110 
56 
360 9 
720 9 
360 8 
720 8 
360 17 
720 17 
720 20 
720 20 
360 15 
360 19 
600 17 
600 21 
600 22 
600 12 
1,200 12 
600 12 
1,200 12 
1,200 22 
1,200 22 
1,200 22 
600 22 
1,200 16 
600 16 
1,200 25 
600 25 
1,200 37 
600 37 
360 37 
1,200 35 
600 35 
1,200 30 
600 30 
1,200 30 
600 30 
600 23 
360 23 
1,200 22 
600 22 
1,200 22 
600 22 
1,200 20 
600 20 
1,200 21 
600 21 
1,200 21 
600 21 
1,200 21 
600 21 
600 18 
360 18 
600 10 
360 10 
600 18 
360 18 
16 
16 
12 
12 
20 
20 
21 
21 
11 
15 
18 
14 
18 
15 
15 
15 
15 
34 
34 
34 
34 
32 
32 
38 
38 
49 
19 
19 
50 
50 
45 
45 
45 
45 
18 
18 
37 
37 
37 
37 
35 
35 
38 
38 
17 
17 
17 
17 
16 
16 
13 
13 
17 
16 
50 250 13 14 
50 250 2 10 
50 250 11 12 
56 400 3 14 
56 400 4 14 
16 Fixed 748 1951 
16 195321 
12 Fixed 670 1907 
12 190721 
11 Movable 535 1932 
11 193221 
15 Movable 460 1964 
15 1964 
10 Fixed 610 192521 
10 Movable 560 192521/22 
15 Movable 410 1950 
15 Movable 530 1959 
14 Movable366 1964 7.0 
10 Movable 3,978 1929 
10 Temporary Lock 1980 
11 Movable 3,073 1928 
11 Temporary Lock 1969 
12 Movable 3,560 1980 
12 
12 Movable 3,516 1975 
12 
16 Movable 2,272 1975 
16 
13 Movable 1,965 1972 
13 
12 Movable 8,627 1961 
11 1921 
11 1930 
15 Movable 1,395 1963 
15 1963 
15 Movable 1,756 1962 
15 1962 
15 Movable 1,287 1962 
15 
15 Movable 1,132 1937 
15 
15 Movable 1,202 1970 
15 
15 Movablel,206 1969 36.4 
15 
15 Movable 1,128 1973 
15 
17 Movable 1,098 1972 
17 
18 Movable 1,306 1965 
18 
15 Movable 1,315 1961 
15 
15 Movable 1,379 1936 
15 
18 Fixed 1,585 1929 
18 
13 Movable 1,717 1921 
13 
12 Movable 170 1941 
11 None 1953 
11 Movable 104 1937 
14-- Movable 1,150 1965 
14 Movable 1977 
12.6 9 300 
17.7 9 300 
19.7 9 300 
23.8 9 300 
5.8 9 300 
11.2 9 300 
6.0 9 300 
7.4 9 300 
9 300 
23.7 9 300 
35.8 9 300 
99.7 9 300 
69.9 9 300 
55.4 9 300 
116.3 9 400 
75.3 9 300 
95.3 9 300 
9 300 
95,2 9 300 
61.8 9 300 
41.7 9 300 
33.6 9 300 
9 300 
35.3 9 1,000 
36.0 9 300 
29.9 9 300 
22.7 9 300 
18.4 9 300 
7.1 9 300 
6.2 9 300 
15.1 8 80 
15.6 8 90 
15.6 8 90 
7.9 8 90 
8 100 
C-5

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Typel (feet) Opened (miles) (feet) (feet) 
Old River, LA 
Old River Lock 
Ouchita and Black Rivers, 
AR & LA 
Jonesville Lock and Dam 
(Black River) 
Columbia Lock and Dam 
(Ouachita River) 
Calion Lock 
(Ouachita River) 
Felsenthal Lock 
(Ouachita River) 
Parl River, MS and LA 
Lock 1 
Lock 2 
Lock 3 
Red River Waterway 
Lock 1 
Lock 2 
Lock 3 
Sacramento River, CA 
Barge Canal Lock 
Snake River, WA 
Ice Harbor Lock and Dam 
Little Goose Lock and Dam 
Lower Granite Lock and Dam 
Lower Monumental Lock and Dam 
St. Mary's River, MI 
South Canal: 
MacArthur Lock 
Poe Lock 
North Canal: 
Davis Lock 
Sabin Lock 
Savannah, GA 
New Savannah Bluff Lock 
and Dam 
Tennessee River, TN, AL, 
MS, and KY 
1 8 
Kentucky Lock and Dam 
Pickwick Landing Lock 
and Dam 
Auxiliary Lock 
Main Lock 
Waterway Connecting 
Tombigbee and Tennessee 
Rivers, AL and MS 
Gainesville Lock and Dam 
Aliceville Lock and Dam 
Columbus Lock and Dam 
Aberdeen Lock and Dam 
Lock A and Spillway 
Lock B and Spillway 
Lock C and Spillway 
Lock D and Spillway 
Lock E and Spillway 
Bay Springs Lock and Dam 
Wilson Lock and Dam 
Main Lock 
Auxiliary Lock 
General Joe Wheeler Lock 
and Dam 
304.0 Simmsport, LA 
25.0 Jonesville, LA 
117.2 Columbia, LA 
75 1,200 35 11 11 None 1963 
84 600 30 18 14 Movable 450 1972 
84 600 18 18 13 Fixed 
12 125 
92.2 9 100 
400 1972 106.2 9 100 
281.7 84 600 12 18 13 Movable 350 1984 
226.8 84 600 13 18 
29.417 learl River, LA 
40.717 Bush, LA 
43.917 Sun, LA 
310 26.7 10 
310 15 10 
310 11 10 
43.8 84 685 38 
86.5 84 685 24 
141.0 84 685 31 
42.8 West Sacramento, 
CA 
9.7 Pasco, WA 
70.3 Starbuck, WA 
107.5 Pomeroy, WA 
41.6 Kahlotus, WA 
47.0 Sault Ste. Marie, 
MI 
47.0 Sault Ste. Marie, 
MI 
47.0 Sault Ste. Marie, 
MI 
47.0 Sault Ste. Marie, 
MI 
187.2 Augusta, GA 
22 
23.5 
25 
13 Movable 350 1984 
10 None 
10 None 
10 None 
1951 
1951 
1951 
13 Movable 550 1984 
15 Movable 300 1987 
18 Novable 360 1991 
86 600 4 13 13 None 
86 675 100 
86 675 101 
86 675 100 
86 675 98 
80 
110 
80 
80 
800 22 31 
1,200 22 32 
1,350 22 24 
1,350 22 24 
20 Movable 
20 Movable 
20 Novable 
20 Movable 
31 None 
32 None 
23 None 
23 None 
50.3 9 100 
55.2 9 100 
11.1 7 80 
3.2 7 80 
13.2 7 80 
44.2 9 200 
74.3 9 200 
116.5 9 200 
1961 1.5 13 120 
1962 
1970 
1975 
1969 
1943 
1968 
1914 
1919 
56 360 15 14 12 Movable 360 1936 
22.4 Gilbertsville, KY 110 600 56 11 13 Tainter 7,976 1944 
206.7 Hamburg, TN 110 600 55 10 13 Bulkhead 7,385 1937 
206.7 Hamburg, TN 110 1,000 55 10 13 Bulkhead 7,385 1984 
49.1 Gainesville, AL 
89.8 Aliceville, AL 
117.6 Columbus, MS 
140.4 Aberdeen, MS 
154.1 Amory, MS 
159.3 Smithville, AL 
174.0 Fulton, MS 
181.4 Fulton, MS 
189.7 Belmont, MS 
194.9 Tupelo, MS 
259.4 Florence, AL 
259.4 Florence, AL 
110 
110 
110 
110 
110 
110 
110 
110 
110 
110 
600 36 
600 27 
600 27 
600 27 
600 30 
600 25 
600 25 
600 30 
600 30 
600 84 
110 600 94 
60 292 94 
15 
15 
15 
15 
15 
18 
18 
18 
18 
18 
15 Movable 15,460 1978 
15 Movable 14,790 1979 
15 Movable 10,040 1981 
15 Movable 10,640 1984 
15 Movable -- 1985 
18 Movable -- 1985 
18 Movable -- 1985 
18 Movable -- 1985 
18 Movable -- 1985 
18 None 10,640 1985 
13 13 Bulkhead 3,728 1959 
11 11 Bulkhead 3,728 1927 
1 14 250 
14 250 
14 250 
14 250 
27 
16.2 9 90 
184.3 9 300 
52.7 9 300 
52.7 9 300 
49.1 9 300 
40.7 9 300 
27.8 9 300 
22.8 9 300 
13.7 9 300 
14.7 9 300 
7.4 9 300 
8.3 9 300 
5.2 9 300 
64.5 9 300 
15.5 9 300 
15.5 9 300 
C-6

APPENDIX C (Continued) 
NAVIGATION LOCKS AND DAMS OPERABLE SEPTEMBER 30, 1992 
Locks Dams Authorized Channel 
Miles Width Available Lift at Depth on Sills 
Above Community of Length for Normal Length Year Length Depth Width 
Project Mouth in Vicinity Chamber Width Pool Level Upper Lower Type
1 
(feet) Opened (miles) (feet) (feet) 
Main Lock 
Auxiliary Lock 
Waterway Connecting 
Tombigbee and Tenonsssee 
Rivers, AL and MS (continued) 
Guntersville Lock and Dam 
Main Lock 
Auxiliary Lock 
Nickajack Lock and Dam 
Chickamauga Lock and Dam 
Watts Bar Lock and Dam 
Fort Loudon Lock and Dam 
Melton Hill Lock and Dam 
(Clinch River) 
WillarnmeRt iver at 
Willameti Falls, OR 
Lock No. 1 
Lock No. 2 
Lock No. 3 
Lock No. 4 
Guard Lock 
274.9 Florence, AL 
274.9 Florence, AL 
110 600 48 13 13 Bulkhead 5,738 1963 74.1 9 300 
60 400 48 15 13 Bulkhead 5,738 1962 74.1 9 300 
349.0 Guntersville, AL 110 600 39 13 13 Tainter 3,837 1965 75.7 9 300 
349.0 Guniersville, AL 60 400 39 13 12 Tainter 3,837 1939 75.7 9 300 
424.7 Ghattanooga, TN 110 600 39 13 11 Tainter 3,763 1967 46.3 9 300 
471.0 Chattanooga, TN 60 360 49 10 14 Tainter 5,654 1940 58.9 9 300 
529.9 Breendenton, TN 60 360 58 12 12 Tainter 2,646 1942 72.4 9 300 
602.3 Lenoir City, TN 60 360 72 12 12 Tainter 3,687 1943 49.8 9 300 
23.1 Kingston, TN 75 400 54 13 13 Tainter 1,072 1963 38.2 9 30019 
26.0 Oregon City, OR 40 210 20 6 
26.0 Oregon City, OR 40 210 10 6 
26.0 Oregon City, OR 40 210 10 6 
26.0 Oregon City, OR 40 210 10 6 
26.4 Oregon City, OR 40 210 10 6 
8 None 
8 None 
8 None 
8 None 
8 None 
1872 6 150 
1872 
1872 
1872 .4 
1872 23.6 6 
1 
Fixed; crest without gates or other facility to control streamflow. Movable; includes any type of crest gates, tainter gates, wickets, or others to control streamflow. 
2
Above mouth of Mobile River. 
3Includes length of earth dikes. 
4
From mouth of Apalachicola River. 
5
From mouth of Chattahoochee River. 
6
Above Norfolk, VA. 
7
With reference to mean low water, or low mean Gulf as case may be. 
8
From Gulf Intracoastal Waterway. 
9 
Average high and low water conditions, lift varying widely, depending on tides and river stages. 
From foot of Government Street, Mobile, AL. 1 1
From mouth of St. Johns River. 
12Above Head of Passes. 
1 3
1 4From New Orleans, LA. 
Salt water barrier in down position. Will clear 15-foot vessels in normal position. 
15Above the Ohio River. 
1 6 
17 Channel completed to depth of 6.5 feet. 
From mouth of West Pearl River. 
1 8
TenrnesseeR iver locks operated by the Corps, dams operated by the Tennessee Valley Authority. 
1 9 
300-foot width from lock to mouth of Clinch River and 175-foot width upstream from lock to Clinton, TN. 
20Dates shown represent replacement structures. 
2 1 
Dates shown represent reconstruction for locks and dams Nos. 2-8 inclusive. 
22Dam was rebuilt in 1959. 
23 
Ol1d1 10 X 358 lock replaced in 1957. 
24 
nop-rable, caretaker status September 7, 1982. 
2 
Inoperable, caretaker status October 1, 1981. 
26 Lock and Dam 26 has been removed and replaced by Melvin Price Locks and Dam 
* Includes length of left and right embankments 
** Includes length of left embankment 
C-7

APPENDIX D 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Agat Small Boat Harbor, Guam (Sec 107).......................... 
AIWW - Replacement of Federal Hwy Bridges in NC..... 
Baltimore Harbor (50 foot), MD & VA............................ 
Barnegat Inlet, NJ ............................................ 
Bonneville Navigation Lock, OR & WA ......................... 
Brazos Island Harbor, TX ........................................ 
Buffalo Smallboat Harbor, NY .......... ........................ 
Channel to Newport News, VA (1965 Mod.) .............. 
Channel to Newport News, VA (1986 Mod.) ................... 
Charleston Harbor, SC .................... ..... 
Cleveland Harbor, OH (NCH/Pier 34)................................ 
Columbia River, Seafarers Memorial, 
Hammond, OR .................................. ... ................. 
Corpus Christi Ship Channel, TX ..................................... 
Delaware River in the Vicinity of Camden, NJ ................ 
Falls of the Ohio National Wildlife Conservation Area, 
IN and KY ..................................... ...................... 
Finney Creek at Wachapreague, VW.................................. 
Freeport Harbor, TX ..................... ...... 
Gallipolis Locks and Dam, Ohio River............................. 
Grays Harbor, WA ..................... ....... 
Grays Landing Lock & Dam (Lock & Dam 7) 
M onongahela River, PA....................... ............... 
Gulfport Harbor, MS ..................... ...... 
Helena Harbor, AR ............................ 
Hempstead Harbor, NY.......................................... 
Kill Van Kull - Newark Bay, NJ and NY .................... 
Krebs Lake, MS (Sec 107) ....................................... 
LaGrange Lock and Dam, Illinois Waterway, IL ............... 
Laupahoehoe Harbor, Hawaii, HI ..................................... 
Lock and Dams 3, 5A, 6,7,8 and 9, MN, WI and IA .......... 
Lock and Dam 17, IL .................... ...... 
Lock and Dam 18, IA..................... ....... 
1987 
1974 
1987 
1985 
1985 
1992 
1991 
1967 
1987 
1988 
1992 
1991 
1972 
1987 
1984 
1988 
1987 
1985 
1990 
1986 
1991 
1989 
1992 
1986 
1983 
1986 
1988 
1989 
1989 
1989 
1989 
1986 1 
1990 
1992 
1968 
1989 
1990 
1988 
1988 
1983 
1992 
1988 
1989 Dredging and breakwater 
1999 Replacement of existing bridges 
1993 Deepdraft channel deepening 
1992 Jetty realignment and dredging 
1994 New larger lock 
1994 Enlarging and Deepening Deep 
Draft Channel to 42 foot 
depth 
1992 Emergency Dike Repair 
Indefinite Deferred anchorage construction 
Indefinite Dredge 50 ft. Channel. Deepen 
to 55 feet 
1994 Dredging and channel 
wideningand deepening 
1993 Recreation Navigation 
Indefinite 
1994 
1988 
Construction of support structure 
Dredging 
Dredging 
Indefinite Protection of a National Natural 
Landmark 
1988 Dredging 
1994 Dredging, jetty construction, and 
recreation 
1999 Replacement of existing locks 
and major rehabilitation of the 
dam 
1994 Navigation channel widening and 
deepening 
1995 Construct new lock & dam to 
replace existing lock & dam 7 
1994 Deepen Channel 
1994 New Slackwater Harbor 
1994 Removal of derelect barges 
1995 Deepdraft channel - widening 
and deepening 
1984 Dredging, navigation channel 
1992 Major Rehabilitation of Lock and 
Dam 
1988 Breakwater 
1999 Major rehabilitation of 
electrical/mechanical systems 
1992 Major maintenance of lock and 
dam 
1993 Major maintenance of lock and 
daml 
D-1

APPENDIX D (Continued) 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Lock and Dam 20, MO ..................................... ..... 
McClellan-Kerr Arkansas River Navigation System, AR .. 
Melvin Price Lock and Dam, MO..................................... 
Mississippi River between Ohio and Missouri Rivers 
IL and MO.................................................................... 
Mississippi River, Gulf Outlet, LA ................................... 
Mississippi River, Ship Channel, Gulf to 
Baton Rouge, LA................................................. 
Moriches Inlet, NY ........................................... 
Mouth of Colorado River, TX (Gulf Intracoastal 
Waterway) .................... ................... 
Nawiliwili Harbor, Kauai, HI .......................................... 
New York Harbor, NY and NJ............................................ 
Newburgh Locks & Dam, Ohio River, IN and KY............. 
Norfolk Harbor Channel, VA (1965 Mod.)......................... 
Norfolk Harbor Channel, VA (1986 Mod) ....................... 
1986 
1963 
1974 
1910 
1958 
1987 
1987 
1984 
1985 
1976 
1965 
1966 
1987 
Norfolk Harbor, Thimble Shoal Channel, VA.................... 1987 
Oakland Harbor, CA ........................... 1987 
Olmsted Locks and Dam, IL & KY ................................. 1992 
Ouachita and Black River, AR and LA............................... 1964 
Peoria Lock and Dam, Illinois Waterway, IL ................... 
Point Marion, Lock & Dam 8 
Monongahela River, PA...................................... 
Portsmouth Harbor & Piscataqua River, ME and NH ........ 
Red River WW, Mississippi River to Shreveport, LA........ 
Richmond Harbor, CA ........................................... 
1986 
1986 
1989 
1974 
1985 
Rudee Inlet, VA................................... 1990 
Sacramento River Deep Water Ship Channel, CA.............. 1986 
San Diego River and Mission Bay, CA............................... 
San Francisco Bay to Stockton, CA (John F. Baldwin 
and Stockton Ship Channels), CA ............................. 
1991 
1971 
Savannah Harbor Widening, GA ..................................... 1990 
Schinnecock Inlet, NY ........................................ 1990 
1970 
1990 
1992 Major Rehabilitation of Lock and 
Dam 
2000 Locks and dams 
1997 Replacement 
2000 Regulating works 
1975 Dredging and jetties 
1987 2 Indefinite 3 Dredging 55-foot channel 
1994 Dredging channels 
1994 Breakwaters, dredging, and 
recreation 
1987 1987 Breakwater repair 
Incremental Indefinite Collection and removal of drift 
1969 1974 Replacement of locks and dams 
46 and 47 
1967 Indefinite Deferred anchorage const. 
1989 Indefinite Dredge 50 ft. channel and deepen 
to 55 feet 
Indefinite Dredge outbound element and 
deepen to 55 feet 
1995 Channel deepening and widening 
turning basin 
2006 Navigation 
1984 Indefinite Replacement of six locks and 
dams, channel deepening to 9 
feet and realignment 
1992 1992 Major Rehabilitation of lock and 
dam 
1994 Replaces existing 56x360' lock 
chamber with new 84'x720' 
chamber 
1992 1992 Dredging (widening channel) 
19844 Indefinite Lock and dam construction. 
Channel improvement and 
realignment 
1995 Channel deepening and turning 
basin 
1991 1991 Dredge 7 foot channel 
Indefinite Deep draft channel, widening and 
deepening 
1994 Dredging and breakwater 
1998 Deep draft channel, widening, 
deepening and dredging 
1992 Widening channel 
1993 Dredging and repair of jetties 
D-2

APPENDIX D (Continued) 
NAVIGATION PROJECTS UNDER CONSTRUCTION DURING FISCAL YEAR 1992 
Fiscal Year 
Fiscal Placed in Completed or 
Year Useful Scheduled for 
Project Started Operation Completion Nature of Project 
Smithland Locks and Dam, IL, IN, and KY .................... 1971 
Tampa Harbor, FL (Main Channel) .................................. 
Tenn River, Decatur Morgan County Port, AL................... 
Tombigbee River, Columbus Port, MS (Sec 107) ............. 
Tongue Point, OR .................................. ...... 
Toussaaant River, Caroll Twsp. , OH (Sec 107) ................ 
W allisville Lake, TX ........................................................ 
1976 
1988 
1987 
1989 
1991 
1967 
1980 
1987 
1990 
Winfield Lock and Dams, Kanawha River, WV.................. 1990 
Wood Island harbor, Biddeford, ME................................ 1992 
1987 Replacement of existing locks 
and dams 50 and 51 
1987 Dredging 
1989 Channel excavation 
1989 Navigation channels & turning 
basin 
1992 Dredging 
1992 Dredging 
1997 Multipurpose lake (navigation, 
salinity control, water supply, 
fish & wildlife, & 
recreational) 
1997 Construction of new lock 
1993 Improvement Dredging 
1 Walter Jones and Joseph P. Knapp completed; Core Creek is under construction; Hobucken and Fairfield have been funded for 
design. 
2 Phase I, forty-five foot channel to New Orleans, LA. Forty-five foot channel to Mile 181 (Donaldsonville, LA) placed in 
useful operation in 1988. 
3 Awaiting further LCA's to extend project to Baton Rouge, LA, and to go deeper than 45 feet. 
4 Lock and Dam No. 1 placed in useful operation in 1984. Lock and Dam No. 2 in 1987. and Lock and Dam No. 3 in 1992. 
Construction was initiated on Lock and Dam Nos 4 and 5 in 1991. 
D-3

APPENDIX E 
MULTIPURPOSE PROJECTS INCLUDING POWER 
OPERABLE SEPTEMBER 30, 1992 
Flood Cmtrod 
and/oar 
Total Nay. Feature 
Storage Placd Initial Existing Scheduled Ultimase 
Community Capability in useful Power Installtion Installation Installation Project Height Length 
Project River inVicinity (acre-feet) 
1 OperationC Y In PFY (KW) (KW) (KW) Functions Type
2 (fet) (fet) 
Albeni Falls, ID Fend Oreille 
Allatoona Lake,GA Etowah 
Barkeley Dam & Cumberland 
Lake Barkeley, KY KY 
& TN 
BeaverLake, AR White 
Big Bend Dam (Lake 
Sharpel), SD Missouri 
Blakely Mountain Ouachita 
Dam Lake 
Ouachit 
BonnmvilLle& D Columbia 
Lake Bonneville, 
OR &WA 
Broken Bow Lake, Mountain Fork 
OK 
Buford Dam, Chattahoochee 
Lanier, GA 
Bull Shoals Lake White 
AR & MO 
Clazence Cannon Salt 
Dam 
CartersDam, GA Coosawate 
Center Hill Lake, Caney Fork 
TN 
Ceatham L&D, TN Cumberland 
ChiefJosephDam Columbia 
(Rufus Woods 
Lake),WA 
Cooper River, Santee 
Charleston 
Harbor, SC 
Cordell Hull L&D, Cumberland 
TN 
Cougar Lake, OR S. Fork McKenzie 
Dale Hollow Lake, Obey 
TN & KY 
Dardanelle L&D, Arkansas 
AR 
DeGray Lake, AR Caddo 
DenisonDamn(Lake Red 
Texoma), TX & 
OK 
Detroit Lake, OR, North Santiam 
including Big 
Cliff Lake, OR 
DworshakDam N. Fork, 
& Reservoir, Clearwatr 
ID 
Eufaula Lake, OK Canadian 
Fort Gibson Grand (Neosho) 
Lake 
Fort Peck Lake, Missouri 
MT 
Fort Randal Dam Missouri 
(Lake Francis 
Case), SD 
Garrison Dam Missouri 
(Lake 
Sakakawea), 
ND 
Gavins Point Dam Missouri 
(Lewis & Clark 
Lake), SD & NE 
Green Peter Middle Santiam 
Lake,OR, including 
Foster Lake, OR 
GreersF erry Little Red 
Lake, AR 
Harry S. Truman Osage 
Dam & Res. 
Hartwell Lake, Savannah 
GA & SC 
Hills Coeek Lake, Middle Fork 
OR Wilanetet 
Ice Harbor LAD Snake 
(LSacajawea), 
Sacajawea), WA 
NewportWA 1,153,000 1952 
Caroersville,GA 670,000 1950 
Frand Rivers, 2,082,000 1964 
Eureka Springs, 
ChamberlainSD 
Mt. Pine, AR 
1,952,000 
1,883,000 
2,768,000 
1963 
1964 
1953 
1955 
1950 
1966 
1965 
1965 
1956 
42,600 
74,000 
130,000 
112,000 
468,000 
75,000 
Bonneville,OR 537,000 1938 1938 1,145,700 
Broken Bow, 1,368,230 
OK 
Buford, GA 2,554,000 
MountainHome 5,408,000 
AR 
Perry, MO 1,428,000 
Carters, GA 472,756 
Lancaster,TN 2,092,000 
Ashland City, TN 104,000 
Bridgeport, WA 593,000 
St. Stephen, SC 2,560,000 
Carthage, TN 
Blue River, OR 
Clina, TN 
Dardancle, AR 
Arkadelphia, AR 
Denison, TX 
Mill City, OR 
310,900 
219,000 
1,706,000 
486,200 
831,900 
5,312,300 
1968 
1956 
1952 
1983 
1975 
1948 
1952 
1955 
1970 
1957 
1953 
1985 
1975 
1951 
1958 
1956 
100,000 
86,000 
340,000 
58,000 
500,000 
135,000 
36,000 
2,457,384 
N/A 1985 84,000 
1973 
1963 
1943 
1969 
1969 
1944 
1974 
1964 
1949 
1965 
1972 
1945 
100,000 
25,000 
54,000 
124,000 
68,000 
70,000 
461,000 1953 1954 118,000 
Orofino, ID 3,453,000 1972 1973 400,000 
Eufaula, OK 3,825,400 
Ft. Gibson, OK 1,284,400 
Glasglow, MT 18,909,000 
Lake Andes, SD 5,574,000 
Riverdale, ND 24,137,000 
Yankton, SD 
1964 
1949 
1938 
1953 
1964 
1953 
1944 
1954 
90,000 
45,000 
185,250 
320,000 
1954 1956 430,000 
504,000 1956 1957 100,000 
Sweet Hoae, OR 491,000 
Heber Spings 
Warsaw, MO 
Hartwell, GA 
OakridgOe,R 
Pasco, WA 
2,844,000 
5,202,000 
2,842,700 
356,000 
417,000 
1967 1967 100,000 
1962 
1982 
1961 
1961 
1962 
1964 
1982(4) 
1962 
1962 
1961 
96,000 
160,000 
344,000 
30,000 
603,000 
42,600 NFPR C 90 1,055 
74,000 FPRW C 190 1,250 
130,000 NPFR CE 157 9,959 
112,000 FPSR CE 228 2,575 
468,000 FPRIW E 95 10.570 
75,000 FPRW E 235 1,100 
1,145,700 NPR C 122 2,690 
100,000 FPWSR E 225 2,750 
86,000 NFPW E 192 5,400 
340,000 FPR C 258 2,256 
58,000 FNPRSW CE 138 1,700 
500,000 FPRW ER 450 1,950 
135,000 FPR CE 250 2,160 
36,000 NPR C 75 801 
2,457,384 PIR C 230 5,998 
84,000 NPW CE 86 876 
100,000 NPR CE 93 1,306 
64,600 NFPRI ER 445 1,738 
54,000 FPR C 200 1,717 
124,000 NPR C 68 2,683 
108,000 FNPRS E 243 3,400 
175,000 FPRSN E 165 17,200 
118,000 NFPRI C 382 1,528 
1,060,000 PNFR CG 717 3,300 
90,000 FNPS CE 114 3,200 
67,500 FP CE 110 2,990 
185,250 NFPRIW E 251 21,026 
320,000 NFPRIW E 165 10,700 
430,000 NFPRIW E 210 11,300 
100,000 NFPRIW E 74 8,700 
100,000 PFNIR C 340 1,380 
96,000 FPRS C 243 1,704 
160,000 FPRW CE 96 5,000 
344,000 NFPRS (E 204 17,880 
30,000 NFPRI GE 304 2,150 
603,000 NPRI CG 130 2,790 
E-1

APPENDIX E (Continued) 
MULTIPURPOSE PROJECTS INCLUDING POWER 
OPERABLE SEPTEMBER 30, 1992 
Flood Control 
Total Nay. Feature 
Storage Placed Initial Existing Scheduled Ultimate 
Community Capability in useful Power Inatallation Installation Installation Project Height Length 
Project River inVicinity (acre-feet) 
1 Operation CY In FY (KW) (KW) (KW) Functions Type
2 
(feet) (fet) 
J.l PrcyP riest Stones 
Dam & 
Reservoir, TN 
J. Strom Thurmond Savannah 
Dam & Reservoir 
GA & SC 
Jim Woodruff Dam Appalachicola 
(Lake Seminole), 
FL, GA & AL 
JohnD ay L&D Columbia 
(Lake Umatilla), 
OR &WA 
John H. Kerr Roanoke 
Dam & 
Reservoir, NC 
& VA 
KeystornLea ke, Arkansas 
OK 
LakeG reesonA,R Little Missouri 
Laurel River, KY Laurel 
Libby Dam, Lake Kootenai 
Koocanusa, MT 
Little GooseL &D Snake 
(Lake Bryan), WA 
Lookout Point Middle Fork 
Lake including Willam tte 
Dexter Lake, OR 
Lost Creek Lake, Rogue 
OR 
Lower Granite Snake 
L&D, WA 
Lower Snake 
Monumental 
L&D (Lake 
Herbert G. 
West), WA 
McNaryL&D Columbia 
OR & WA 
Millers Ferry Alaberna 
L&D, AL 
Mississippi Delta 
Region, LA 
(Caernarvon 
Freshwater 
Diversion) Mississippi 
Nanpil River Nanpil River 
Hydropower, 
Pohnpei, FSM 
New Melones Stanislaus 
Lake, CA
6 
Norfork Lake, AR North Fork 
& MO 
Oahe Dam (Lake Missouri 
Oahe)S,D & ND 
Old Hickory L&D, Cumberland 
TN 
Ozark-Jeta Arkansas 
Taylor L&D, AR 
Philpott Lake, VA Roanoke 
Richard B. Russell GA and SC 
Robert F. Henry Alaberm 
L&D, AL 
Robert S. Kerr Arkansas 
L&D and 
Reservoir, OK 
Sam Raybum Dam Angelima 
& Reservoir, TX 
St. Mary's River, Great Lakes 
MI 
Snettisham, AK
7 
Speel 
StocktonLake, MO Sac 
Table Rock White 
Lake, AR & MO 
Tenkller Lake, Illinois 
OK 
TheDba les L&D Columbia 
(Lake Celilo), 
WA & OR 
Walter F. George Chattahooche 
L&D, GA & FL 
Nashville, TN 652,000 1967 1970 28,000 
Augusta, GA 2,900,000 1952 1953 280,000 
CQattahooche, FL 367,300 
Rufus, OR 
1957 1957 30,000 
2,500,000 1968 1969 2,160,000 
Boydton, VA 2,750,300 1952 1953 204,000 
Tulsa, OK 1,737,600 
Murfreesboro,AR 407,900 
London, KY 435,600 
Libby, MT 5,809,000 
Starbuck, WA 565,000 
Lowell, OR 483,000 
Trail, OR 
Pomeroy, WA 
Kahlotus, WA 
465,000 
484,000 
376,000 
1964 1968 
1950 1950 
1973 1978 
1972 1975 
1970 1970 
1954 1955 
1977 1977 
1975 1975 
1969 1969 
70,000 
25,500 
61,000 
525,000 
810,000 
135,000 
49,000 
810,000 
810,000 
Umatilla, OR 1,550,000 1953 1954 980,000 
Camden, AL 331,8090 1969 1979 75,000 
Braithwaite, LA 
Pohnpei, FSM 
1991
1 1987 1988 2,000 
Oakdale, CA 2,400,000 1978 1979 300,000 
Norfolk, AR 
Pierre, SD 
Hendersonville, 
TN 
Ozark AR 
Bassett, VA 
Augusta, GA 
Benton, AL 
Sallisaw, OK 
Jasper, TX 
Sault Ste. Marie 
MI 
Juneau, AK 
Stockton, MO 
BransoMnO, 
Gore, OK 
The Dalles, OR 
1,983,000 
23,337,000 
545,000 
148,400 
318,500 
1,026,244 
234,200 
522,700 
1943 1944 
1959 1962 
1954 1957 
1969 1973 
1951 1954 
1984 1984 
1972 1975 
1970 1971 
3,997,600 1965 1966 
--- 1855 1952 
352,400 1973 
1,674,000 1969 1973 
3,462,000 1958 1959 
1,230,800 1952 1953 
53,000 1957 1957 
80,550 
595,000 
100,000 
100,000 
14,000 
300,000 
68,000 
110,000 
52,000 
18,400 
73,700 
45,200 
200,000 
40,000 
1,806,800 
Fort Gaines, GA 934,000 1963 1963 130,000 
28,000 FPRW CE 147 2,716 
280,000 NFPRSW (E 200 5,680 
30,000 NPRW CE 67 6,150 
2,700,000 NPRFI CE 161 5,900 
204,000 FPRW CE 144 22,285 
70,000 FNPWS E 121 4,600 
25,500 FPRW C 183.5 941 
61,000 FPRW R 282 1,420 
840,000 FPR C 420 3,055 
810,000 NPRI CG 165 2,655 
135,000 NFPRI CE 243 3,381 
49,000 DFPISWR CE 345 3,600 
810,000 NPRIF CG 146 3,200 
810,000 NPRI CG 135 3,800 
1,754,000 NPRI CG 181 7,365 
75,000 NPRW (E 90 11,380 
W CE 38.5 371 
2,000 P C 17 70 
300,000 FIPRW FR 625 1,560 
163,000 FPRS .C 216 2,624 
595,000 NFPRIW E 245 9,300 
100,000 NPR CE 98 3,605 
100,000 NPR C 58 2,480 
14,000 FPR C 220 892 
600,000 NPR (E 195 4,524 
68,000 NPRW CE 101 14,962 
110,000 NPR E 75 7,230 
52,000 FPWR CE 120 19,430 
18,400 NP Control Gate 
73,700 P C
9 
18 338 
45,200 FPRW CE 128 5,100 
200,000 FPR (E 252 6,423 
40,000 FP E 197 3,000 
1,806,800 NPR CR 300 8,875 
130,000 NPRW CE 114 13,585 
E-2

APPENDIX E (Continued) 
MULTIPURPOSE PROJECTS INCLUDING POWER 
OPERABLE SEPTEMBER 30, 1992 
Flood Control 
azxVor 
Total Nay. Feature 
Storage Placed Initial Existing Scheduled Ultimate 
Conmunity Capability inuseful Power Installatila tista llaion Installation Project Height Length 
Project River in Vicinity (acr -f�et)
1 
OperatioCnY In FY (KW) (KW) (KW) Functim Type 
2 (aet) (fet) 
Webbers Falls Arkansas Wevbbers Palls, OK 170,100 1970 1973 60,000 60,000 NP E 84 4,370 
L&D, OK 
West Point Chattahooche West Point, GA 604,500 1975 1975 73,375 108,375 FPRW CE 97 7,250 
Lake, AL & GA 
Whitney Lake, TX Brazos Whitney, TX 1,999,500 1953 1954 30,000 30,000 FPR CE 159 17,695 
WoldfCekDam Cumberland Jamestown, KY 6,089,000 1950 1952 270,000 270,000 FPR CE 258 5,736 
(Lake 
Cumberland), KY 
1
Total of all storage functions, including inactive and dead storage to normalf ull pool level 
2:. gravel; R: rock; C: concrete; E: earth 
4
Units 4 and 5 were declared commercially operable by Southwestrn Power Administration 9SWPA) on 1 May 1982. No other units have been declared commercially operable by SWPA. 
All six units have successfully generated power, but one or two units at a time will be out of service for sepairs and modifications until late 1995. 
6
Being operated for the Department of Interior by the Bureau of Reclamation 
7Being operated by the Alaska Power Administartion 
8 
Weir for Long Lake 
9 
Formerly Clarks Hill Lake 
Nomanclature for Project Functions 
D--Debris Control P--Power 
F--Flood Control R--Public Recreation Annual Attendance exceeding 5,000 
I--Irrigation S-Water Supply 
N--Navigation W--Fish and Wildlife (Federal or State) 
E-3

APPENDIX F 
MULTIPLE-PURPOSE PROJECTS INCLUDING POWER 
UNDER CONSTRUCTION, SEPTEMBER 30, 1992 
Nameplate Capacity 
Fiscal Scheduled Scheduled 
Year for for Scheduled Ultimate 
Project Started Operation Completion Functions Installation Installation 
Bonneville Second Powerhouse, OR and WA .................... 1974 1981 1996 PR 558,200 558,200 
Clarence Cannon Dam, Salt River, MO................................ 1966 1985 1990 FNPRSW 58,000 58,000 
Harry S. Truman Dam and Reservoir, 
Osage River, MO ... ................................... 1965 19821 19931 FRPW 160,000 160,000 
New Melones Lake, CA2 ...... . .... ... . . . . . . . ... . . .. . . .. ... . 1966 1979 Indefinite1 DFIPRW 300,000 300,000 
Richard B. Russell Dam and Lake, Savannah 
River, GA and SC........................................ 1975 1985 1995 FRP 600,000 600,000 
Cooper River, Charleston Hbr, SC 3 ......................................... 1977 1985 2001 NWDP 84,000 84,000 
Snettisham, AK.................................................. 1967 1989 1993 P 73,700 27,000 
KEY 
DFI 
NP 
RS 
W 
Redevelopment 
Flood Control 
Irrigation 
Navigation 
Power 
Recreation 
Water Supply 
Fish and Wildlife 
1 Units 4 and 5 were declared commercially operable by Southwestern Power Administration (SWPA) on 1 May 1982. No other units have 
been declared commercially operable by SWPA. All six units h ave successfully generated power, but one or two units at a time will be out 
of service for repairs and modifications until late 1995. 
2 New Melones Lake was turned over to the Bureau of Reclamation for operation on November 20, 1979. Corps retains responsibility for 
facilities along the lower Stanisalaus River. Remaining construction consists of unscheduled recreation facilities and minor feature 
closeouts. 
3 Remaining construction consists of a two-lane bridge and highway facility which the SC HWY Dept has an option to initiate 
construction on until May 2001. 
F-1

Flood Damages Prevented 
in the United States 
17.6 17.4 
40- 
35- 
30- 
25- 
20- 
15 
10-
LLLLLL&LLL z 
1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 
Fiscal Year 
Flood damages prevented (damages in billions of dollars) in the United States by 
the U.S. Army Corps of Engineers since Fiscal Year 1982. The ten (fical) year (1982-91) 
average is shown for comnparison. 
'"""" " 10- Year (1982- 1991) 
S8.1 Average -$13.3 8.1Billion 
27.3 
23.2 
O
o
u
c 
m 16.8 
10.8 
11n......... m I I..II.I. .III 
4.3 
5- 
O- 
1/11,1111111111111111111111111111 
8.3 
5.2

Flood damages prevented (in thousands of dollars) in the United States, by state, 
by the U.S. Army Corps of Engineers for 10 fiscal years (1983-92). 
Location FY 83 FY 84 FY 85 FY 86 FY 87 FY 88 FY 89 FY 90 FY 91 FY 2 Average 
Alabama 3,350 0 0 0 0 0 0 0 0 0 335.0 
Alaska 4,885 5,055 6,846 6,828 17,000 0 8,000 0 8,100 10,000 6,671.4 
Arizona 12,000 90,630 14,300 0 0 0 0 0 0 3,945 12,087.5 
Arkansas 1,006,930 812,472 265,510 466,429 397,754 240,694 401,796 635,569 478,008 65,947 477,110.9 
California 1,097,869 102,360 72,800 13,910,920 154,858 98 4,770 9,500 64,022 406,036 1,582,323.3 
Colorado 9,173 2,639 440 502 1,442 1,755 0 0 482 9,367 2,580.0 
Connecticut 4,123 391,130 250 25 224,314 0 1,892 53,180 100 4,228 67,924.2 
Delaware 0 0 0 0 0 0 0 0 0 0 0.0 
Florida 16,687 297 2,079 0 2,619 6,461 456 256 1,305 17,591 4,775.1 
Georgia 2,251 19,426 811 0 4,220 0 850 37,618 1,689 1,474 6,833.9 
Hawaii 869 0 0 220 220 8,540 82 1,085 5,457 194 1,666.7 
Idaho 47,140 43,271 338 20,757 623 113 14,900 5,073 23,018 253 15,548.6 
Illinois 97,712 25,570 75,446 68,235 262,386 2,105 7,925 450,687 64,996 10,369 106,543.1 
Indiana 22,370 32,725 117,822 46,287 14,257 9,032 61,145 57,583 149,239 27,288 53,774.8 
Iowa 156,763 200,359 17,060 106,878 376,965 476 76 128,746 77,099 14,662 107,908.4 
Kansas 72,487 143,594 26,722 114,694 284,377 16,712 105,716 78,201 30,816 298,933 117,225.2 
Kentucky 57,646 217,046 9,976 16,110 20,768 7,718 96,757 25,868 159,089 35,464 64,644.2 
Loulsana 17,863,178 8,474,126 8,463,296 8,478,185 113,053 1,001,845 5,007,949 9,623,200 13,670,272 1,005,357 7,370,046.1 
Maine 0 1,982 0 0 7,605 0 0 0 0 0 958.7 
Maryland and 0 1,011 1,404 109,102 7,000 364 3 9 14 93,074 21,198.1 
Dstridct o Columbia 
Maasachusett 1,348 422,587 304 437 203,457 230 237 6,975 9,472 574 64,562. 1 
Michigan 1,649 1,198 15,197 10,411 31,352 8,477 3,654 3,405 0 412 7,575.5 
Minnesota 4,016 3,790 2,861 22,083 5,888 411 21,995 1,485 5,400 2,929 7,085.8 
Missiaasppi 1,486,446 866,631 1,072,098 360,552 226,975 198,604 549,885 626,709 1,196,409 155,364 673,967.3 
Missouri 544,166 827,765 100,086 717,926 1,006,876 42,370 117,726 245,361 200,669 299,878 410,282.3 
Montana 434 985 555 19,531 277 0 27 7,394 15,408 4,483 4,909.4 
Nebraska 13,817 124,083 1,082 72,187 172,657 457 17,427 11,007 58,559 7,351 47,862.7 
O 
N>

(continued). Flood damages prevented (in thousands of dollars) in the 
United States, by state, by the U.S. Army Corps of Engineers for 10 fiscal years (1983-92). 
Lcaocon FY 83 FY 84 FY 85 FY 86 FY 87 FY 88 FY 89 FY 90 FY1 FY92 Averge 
Nevada 15,015 2,000 0 14,000 0 0 0 0 0 0 3,101.5 
New Hampshire 27 9,837 0 350 14,397 0 0 0 0 0 2,461.1 
New Jersey 0 136 135 121 94 4,907 3,336 4,991 1,247 445 1,541.2 
New Mexico 29,968 100,220 119,648 87,139 97,900 21,528 2,755 42,531 91,189 27,619 62,049.7 
New York 13,192 567,993 15,158 80,610 34,739 5,656 39,507 12,879 17,566 6,120 79,342.0 
North Carolina 24,630 7,886 14,220 4,034 94,430 65 18,362 17,063 23,231 8,474 21,239.5 
North Dakota 7,883 1,141 53 4,324 53,497 0 47,131 6,429 1,591 942 12,299. 1 
Ohio 74,027 38,520 113,279 97,966 80,260 45,183 89,977 140,824 250,242 6,601 93,687.9 
Oklahoma 32,500 45,177 56,900 61,857 758,329 109,979 123,272 220,136 19,116 52,838 148,010.4 
Oregon 499,103 826,337 28,013 1,394,551 38,568 294,945 840,765 693,409 42,633 47,243 470,556.7 
Pennsylvania 33,543 1,981,162 24,387 224,267 9,971 15,290 27,845 16,424 40,498 3,046 237,643.3 
Puerto Roo and 0 0 0 25,000 0 0 0 0 0 4,665 2,966.5 
Virgin islands 
Rhode Island 298 10,541 175 0 9,975 0 0 2,940 1,620 0 2,554.9 
South Caroini 1,300 167 796 157 694 17 1,434 59 2,849 625 609.8 
South Dakota 1,149 1,046 511 811 536 457 457 460 572 4,140 1,013.9 
Tennessee 28,187 192,529 43 10,749 5,253 4,864 9,651 7,588 310,926 496 57,028.6 
Texas 21,527 5,270 46,346 208,333 192,464 6,245 537,403 4,122,558 13,860 5,197,449 1,035,145.5 
Utah 140,000 31,000 2,200 2,300 0 0 500 500 1,500 .700 17,870.0 
Vermont 2,000 2,952 535 1,362 6,295 782 2,298 1,874 2,525 2,275 2,289.8 
Virginia 0 1,186 3,265 87,703 124,709 5,375 11,243 10,035 1,686 124,553 3,975.5 
Washington 7,720 113,407 65,444 98,808 86,774 1,039 62,403 258,333 357,877 54,343 110,614.8 
West Virginia 31,450 44,054 9,088 354,265 49,269 458 18,592 7,406 76,882 40,152 63,161.6 
Wisconsin 1,700 0 11 127 24 0 0 0 0 0 186.2 
Wyoming 545 6,492 0 10,637 91 62 779 2,603 4,424 1,373 2,700.6 
Totals 23,493,073 16,799,785 10,767,490 27,317,770 5,195,212 2,063,314 8,260,978 17,577,953 17,481,657 8,059,272 13,701,650.4 
C0
N
h> 
9>

Flood Damages Suffered 
in the United States 
7
6-6 
O
C 5 
0 
C) m 4 4 
I- 4
3 
o sses ssss I+ I() L_ 11 1111112- III(( III .16 |.IISS1 uS 
o 2 1.5 1.5 .6 
00.8 
0.5 0.5 
1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 
Fiscal Year 
10- Year (1982- 1991) 
Average - $2.2 
Billion 
Flood damages suffered (damages in billions of dollars) in the United States since 
Fiscal Year 1982. The ten (fiscal) year (1982-91) average is shown for comparison.
*I 
i

33.3 
27.2 
40 
35 
30 
25 
20 
15 
10 
20.8 
E 
C
.a 
c) 
00 
LL 
[I' 
III 4I1i 
5.8 
1982 1983 1984 1985 
Potential Flood Damages 
in the United States 
19.2 19.1 
n nI 
11s1'111 111 /lll1illll1110 lll111111s 
9.4 
m==I 6.7 
2.6 
1986 1987 1988 
Fiscal Year 
1989 
111 1IIi ig. 11 ll l 111 11g 
8.9 
10 - Year(1982- 1991) 
Average - $15.5 
Billion 
1990 1991 1992 
Flood damages suffered LI Flood damages prevented 
Potential flood damages (damages in billions of dollars) in the United States since 
Fiscal Year 1982. The potential damages for each year is the sum of the damages suffered 
and the damages prevented. The ten (fiscal) year (1982-91) average is shown for 
comparison. 
I isIIIIIsI 4 iIiI l11.31ll 
11.3 
C) 
.fr 
5- 
0- _ __ m_ I _ -L- \ YY _-- ------ U -- j---U ------- U ------- YI

Flood damages prevented (in millions of dollars) 
the U.S. Army Corps of Engineers during Fiscal Year 1992. 
in the United States, by region, by 
Damage Preverted Damages Prevered FY 1992 Damages Prwered 
Region Fiscal Year 192 FY1982 - 91 Compared to FY 1982 - 91 Average 
New England 4.5 162.7 Low 
MidAtlanlc 97.9 300.6 Low 
Gulf and South Alagic 150.7 51.4 Very High 
Ohio 102.8 318.7 Low 
Tennessee 18.9 35.9 Medium 
Great Lakes 5.7 23.9 Low 
Upper Mississippi 19.0 156.8 Low 
SourwRedRainy 0.5 15.8 Low 
MIssour 609.6 498.4 Medium 
Arkansas- ed-White 87.8 249.8 Low 
Lower Mississippi 1,213.7 8,475.9 Low 
F.o Grande 39.8 61.7 Medium 
Teous and GuM 5,184.6 555.6 Very High 
Colorado 3.9 11.8 Low 
Great Basin 0.7 6.3 Low 
Casomia 406.0 1,570.2 Low 
Coelubl-North Pacic 102.8 781.9 Low 
Alaska 10.0 6.1 Medium 
Hawai .2 3.4 Low 
Total 8,059.3 13,286.9 61 percent of 1982- 1991 average 
1 fi

Major floods in the United States during Fiscal Year 1992 and their effects 
(damages in millions of dollars). 
Month Location Lives Lost Damages Suffered 
December 1991 Texas 14 137 
January 1992 Puerto Rico 23 88 
February 1992 California 2 91 
March 1992 Texas 1 0.5 
May 1992 New Mexico 0 32 
June 1992 Florida 2 40 
June 1992 Connecticut 1 10 
June 1992 Kentucky 0 25 
July 1992 Ohio/Kentucky 6 17 
August 1992 Indiana/Kentucky 2 33 
September 1992 lowa/Wisconsin 0 75 
Subtotals 51 , 549 
Totals (All Floods in U.S.) 87 800 
Other major weather events in the 
their effects (damages in millions of dollars). 
United States during Fiscal Year 1992 and 
Events Number Total Damages 
Lives Lost Suffered 
Tropical Cyclones 8 51 up to 30.000 
Tornadoes 1148 11 404 
Drought 3 - Not Available 
Dust Storms 1 17 Not Available 
Hail Storms 1 0 60 
Totals 1158 79 up to 30.464 
G-6

Flood Damages Prevented 
Compared to Average 
D!,. 
U 
Alaska 
-o 
o" Hawaii 
Flood Damages Suffered 
Compared to Average 
D 
-J 
.* 
a Hawaii Puerto Rico 
(Top) Fiscal Year 1992 flood damages prevented by the U.S. Army Corps of 
Engineers, as compared to the nine (fiscal) year (1983-91) averages. (Bottom) Fiscal Year 
1992 flood damages sufered as compared to the nine (fiscal) year (1983-91) averages. 
G-7 
Puerto Rico 
Alaska 
l.c urn 
-erv r.ian 
I ~

Flood damages prevented (in thousands of dollars) in 
by the U.S. Army Corps of Engineers during Fiscal Year 1992. 
the United States, by state, 
Deages Damages Prevented Total Flood Average Damages FY 1992 Damages 
Location Prevented by by Corps-Supported Damage Prevented Prevented Prevented Compared 
CorpControlled Emergency by the Corps FY 1983 -91 to FY 1983 -91 
Projects Operation of Engineers Average 
Alabemn 0 0 0 372 Low 
Alaska 10,000 0 10,000 6,301 High 
Artrona 3,945 0 3,945 12,992 Low 
Arklaes 65,947 0 65,947 522,791 Low 
Caifomrnia 406,036 0 406,036 1,713,005 Low 
Colorado 9,367 0 9,367 1,826 Very High 
Connectcut 4,228 0 4,228 75,001 Low 
Delaware 0 0 0 0 Low 
Florida 17,591 0 17,591 3,351 Very High 
Georgla 1,474 0 1,474 7,428 Low 
Hawal 194 0 194 1,830 Low 
Idaho 253 0 253 17,248 Low 
IInot 10,369 0 10,369 117,228 Low 
indlan 27,288 0 27,288 56,717 Low 
lowa 14,662 0 14,662 118,268 Low 
Kawas 298,933 0 298,933 97,034 High 
Karaucky 35,464 0 35,464 67,886 Medium 
Louisiana 1,005,357 0 1,005,357 8,077,153 Low 
Maine 0 0 0 1,065 Low 
Maryland and 93,002 72 93,074 13,212 Very High 
Disbidt of Columbia 
Massachies 574 0 574 71,671 Low 
MIchigan 412 0 412 8,371 Low 
Minnesota 2,929 0 2,929 7,548 Low 
Miessppi 155,364 0 155,364 731,583 Low 
MissourI 298,778 1,100 299,878 422,545 Medium 
Montana 4,483 0 4,483 4,957 Medium 
Nebraska 7,351 0 7,351 52,363 Low

(continued). Flood damages prevented (in thousands of dollars) in the United 
States, by state, by the US. Army Corps of Engineers during Fiscal Year 1992. 
ODmages Damages Prevented Total Flood Average Damages FY 1982 Damages 
Location Prevented by by Corps-Supported Damages Prevented Prevented Prevented Compared 
Controled Emergency by the Corps FY 1983-91 to FY 1983 - 91 
Projects Operations of Engineers Average 
Nevada 0 0 0 3,446 Low 
New Hampshire 0 0 0 2,735 Low 
New Jersey 445 0 445 1,663 Low 
New Mexico 27,619 0 27,619 65,875 Low 
New York 5,770 350 6,120 87,477 Low 
North Carolina 8,474 0 8,474 22,658 Low 
North Dakota 942 0 942 13,561 Low 
Ohio 6,601 0 6,601 103,363 Low 
Oklahoma 52,838 0 52,838 158,584 Low 
Oregon 47,243 0 47,243 517,586 Low 
Penneylvania 3,046 0 3,046 263,707 Low 
Puerto Floo and 4,665 0 4,665 2,778 Medium 
Virgh ands 
Rhode and 0 0 0 2,839 Low 
Soult Caroin 625 0 625 830 Medium 
Soulh Dakota 4,140 0 4,140 667 Very High 
Tennessee 496 0 496 63,309 Low 
Texas 5,196,377 1,072 5,197,449 572,662 Very High 
Utah 700 0 700 19,778 Low 
Vermont 2,275 0 2,275 2,291 Medium 
Virginia 124,553 0 124,553 27,244 High 
Washington 54,343 0 54,343 116,866 Low 
West Virginia 40,152 0 40,152 65,718 Medium 
Wisconsin 0 0 0 207 Low 
Wyoming 1,373 0 1,373 2,848 Low 
Totals 8,056,678 2,594 8,059,272 14,328,438 
0

Flood damages suffered (in thousands of dollars) in the United States, by state, 
during Fiscal Year 1992. 
Lives Lost Average Damages FY 1992 Damages 
Location Property Agricultural Total Suffered Suffered Compare 
FY 1992 FY 1983 -92 Damages Loe Damages FY 1983 -91 to FY 1983- 91 
10 Years Average 
Alabama 2 30 320 0 320 21,316 Low 
Alaska 0 2 7,302 0 7,302 3,744 High 
Adrizon 3 38 5,187 2 5,189 49,387 Low 
Arkansas 0 31 909 0 909 79,122 Low 
California 2 54 93,152 0 93,152 130,117 Medium 
Colorado 0 0 1,602 0 1,602 13,083 Low 
Connedicut 1 1 10,216 150 10,366 9,725 Medium 
Delaware 0 3 0 2 2 739 Low 
Florida 2 5 41,776 162 41,938 32,320 Medium 
Georgia 1 20 1,156 0 1,156 16,373 Low 
Hawaii 6 10 9,180 80 9,260 8,292 Medium 
Idaho 0 5 192 32 224 899 Low 
Illinois 0 20 187 2 189 63,253 Low 
Indiana 1 8 21,278 24,146 45,424 32,495 Medium 
Iowa 0 10 31,667 19,133 50,800 135,228 Low 
Kansas 1 7 5,547 4,580 10,127 45,638 Low 
Kentucky 8 36 42,028 4,842 46,870 24,809 High 
Louisiana 1 31 4,191 0 4,191 316,719 Low 
Maine 0 7 2,179 0 2,179 10,695 Low 
Maryland and 0 8 339 0 339 1,321 Low 
Distriocft Columbia 
Massachusetts 0 11 176 0 176 14,367 Low 
Michigan 0 10 355 0 355 54,685 Low 
Minnesota 0 5 1,760 0 1,760 6,398 Low 
Mississippi 0 20 1,010 0 1,010 133,989 Low 
Missoud 3 37 2,042 2 2,044 46,876 Low 
Montana 0 11 1,027 375 1,402 6,004 Low 
Nebraska 0 5 2,857 3,826 6,683 30,601 Low 
Does no include flood damages caused by storm surges (i.e. hurricanes) or coastal flooding. 
C0

(continued). Flood damages suffered (in thousands of dollars) in the United States, 
by state, during Fiscal Year 1992. 
Lives lot Average Damages FY 192 Damages 
Location Property Agricultural Total Suffered Suffered Compre 
FY 1992 FY 1983- 92 Damages Loses Damage FY 1983- 91 to FY1983 -91 
10 Years Average 
Nevada 0 8 1,621 0 1,621 2,417 Medium 
New Hampshire 0 1 0 0 0 3,599 Low 
New Jersey 0 8 500 0 500 40,989 Low 
New Mexico 0 16 32,264 0 32,264 6,571 High 
New York 0 30 1,830 32 1,862 45,881 Low 
North Carolina 2 15 9,567 3,360 12,927 9,757 Medium 
North Dakota 0 0 0 0 0 2,366 Low 
Ohio 2 41 18,713 1,365 20,078 22,099 Medium 
Oklahoma 2 45 10,871 0 10,871 128,203 Low 
Oregon 0 3 32 0 32 11,706 Low 
Pennsylvania 0 25 1,805 0 1,805 18,163 Low 
Puerto Rico and 25 101 84,127 6,000 90,127 14,756 Very High 
Virgin Islands 
Rhode island 0 0 16 0 16 87 Low 
South Carolina 0 16 0 0 0 5,441 Low 
South Dakota 0 0 1,810 1,650 3,460 24,299 Low 
Tennessee 2 33 188 16 204 17,246 Low 
Texas 19 184 181,733 17,623 199,356 176,638 Medium 
Utah 0 7 24 0 24 116,802 Low 
Vermont 0 2 2 0 2 8,647 Low 
Virginia 1 38 6,792 579 7,371 100,078 Low 
Washington 0 15 176 0 176 39,520 Low 
West Virginia 3 44 5,791 0 5,791 93,447 Low 
Wisconsin 0 2 8,804 20,501 29,305 13,647 High. 
Wyoming 0 12 0 0 0 4,897 Low 
Totals 87 1,071 654,301 108,460 762,761 2,195,448 
Does not include flood damages caused by storm surges (i.e. hurricanes) or coastal flooding. 
CO

Deaths and Flood Losses 
for Fiscal Year 1992 
200 
180 169 
- 160 
o 140 
C
.2 120 
97 102 
; 100 88 
n 75 
30 ~ 80 
28 26 59 59 
26 326 
j 24 40 
0 22 
20,20 10 g 
20 -0.2 
18 0 
N 16 Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 
14 
12- 10 
10
8 
5 55 
6 4 3 
4 2 
2 0 "" 
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep 
Month 
Monthly flood losses (deaths (bottom), and damages (top) in millions of dollars) 
in Fiscal Year 1992.

Flood insurance claims (in actual amounts) in the United States, by state, through 
the National Flood Insurance Program during Fiscal Year 1991. 
C a i 8P To al Claims Clikn Pad Total Claims 
Number Amount Number Amount Number Amount Number Amount 
Alabama 223 1,869,833.98 283 2,903,008.00 Nevada2 14,811.9 6 25,81100 
Alaska 29 433,231.30 41 449,503.00 New HampshIre 12 38,928.78 32 53,161.00 
Arizona 5 15,241.12 11 19,104.00 New Jersey 213 1,459,761.54 388 2,363,178.00 
Arkanse. 273 1,805,890.94 332 8,217,930.00 New Medoo 6 6,833.27 11 66,532.00 
Califormi 123 1,182,003.49 228 1,724,526.00 New York 268 1,975,346.82 559 2,975,644.00 
Colorado 24 115,435.55 47 259,285.00 North Carolina 203 1,475,902.08 320 8,488,989.00 
Connectict 65 287,414.49 131 438,063.00 North DakaQ 25 109,385.48 47 128,710.00 
Delaware 2 10,800.15 4 12,308.00 Ohio 367 2,841,660.86 489 4,137,302 00 
Flord 486 2,738,078.32 788 4,073,886.00 Oklahomu~a 17 180,738.23 32 209,419.00 
Georgi 258 3,505,047.96 331 14,853,064.00 Oregon 16 158,037.31 23 178,956.00 
Hawaii 116 1,157,325.11 171 3,425,213.00 Pennsylvania 257 2,402,469.68 333 4,121,998.00 
Idaho 3 30,292.56 4 34,678.00 PuArto ioo and 44 274,939.75 50 334,673.00 
IllInos 252 1,294,728.37 428 2,535,810.00 Fhode Island 442 6,327,523.87 635 8,922,798.00 
Indiana 702 9,504,596.79 906 12,675,013.00 Sousih Carolna 154 670,990.76 258 2,463,969.00 
Iowa 8 8679,082.16 123 1,101,896.00 Soih Dakota 2 3,248.71 7 4,298.00 
Kansas 10 48,761.53 16 67,504.00 Tennmese 221 2,026,629.18 254 4,412,200.00 
Kerducky 325 2,199,534.48 371 12,387,578.00 Tern 1,600 15,951,180.71 2,112 32,635,267.00 
LouIstana 7,121 72,249,953.43 8,353 100,313,871.00 Utah 4 4,300.35 10 6,225.00 
Mane. 71 945,366.21 134 1,103,807.00 Vermont 1 5,603.79 7 6,104.00 
Maryland and 8 64,448.51 25 72,106.00 Virginia 63 419,754.85 113 626,392.00 
District of Columbia 
Massachusetts 2,493 44,269,446.53 3,014 52,723,890.00 Washington 1,123 17,446,478.76 1,351 23,578,664.00 
Michigan 40 434,088.83 75 665,681.00 West Virginia 71 589,761.07 101 1,136,207.00 
Minnesota 17 108,170.53 31 1,370,563.00 Wisconsin 6 29,220.98 18 33,506.00 
Mississipi 1,615 13,704,933.78 1,882 67,284,513.00 Wyoming 1 1,309.71 13 2,503.00 
Missour 181 2,187,171.06 225 2,866,450.00 
Montana 12 137,241.88 23 148,297.00 Totals 19,681 215,831,106.85 25,182 387,209,213.00 
Noebraska 23 440,171.29 36 569,180.00 
Administered by the Federal Emergency Management Agency, Federal Insurance Administration. Data include only flood damage 
claims ( g damage caused by hurricanes, tornadoes, winds, etc.). Dollar amounts do not include administrative costs. 
Total claims includes claims paid, claims denied, insurance deductibles, and damages in excess of insurance policies. 
C) 
-

Flood insurance claims (in actual amounts) in the United States, by state, through 
the National Flood Insurance Program during Fiscal Year 1992. * 
Location Number Amount Number Amount Location Number Amount Number Amount 
Alabama 51 389,614.33 67 749,672.00 Nebraska 16 105,503.55 35 176,557.00 
Alaska 19 396,286.01 23 305,312.00 Nevada 4 56,641.56 10 132,199.00 
Artrzona 93 546,530.65 121 616,335.00 New Hampshire 186 1,865,047.29 255 2,354,734.00 
Arkansas 15 28,826.43 20 34,870.00 New Jersey 4,094 33,777,697.83 5,049 42,484,231.00 
California 400 3,085,508.06 661 4,962,601.00 New Mexico 58 556,885.72 81 920,672.00 
Colorado 6 10,143.84 15 11,644.00 New York 2,969 35,528,641.24 3,657 52,689,070.00 
Connectictd 470 4,632,407.71 653 7,054,528.00 North Carolina 910 8,978,656.67 1,096 25,348,135.00 
Delaware 550 4,728,692.11 721 5,978,118.00 North Dakota 1 1,865.20 3 2,366.00 
Flordda 5,899 43,803,528.25 10,042 47,822,158.00 Ohio 158 1,058,801.30 226 3,147,992.00 
Georgia 101 566,746.79 133 1,047,562.00 Oklahoma 83 567,703.56 108 716,583.00 
Guam 3 48,356.77 4 57,658.00 Oregon 1 0.00 2 0.00 
Hawai 579 5,087,070.80 710 6,914,597.00 Pennsylvania 88 678,916.93 113 1,391,130.00 
Idaho 3 2,711.61 8 4,774.00 Pueto Rco and 412 3,750,112.10 448 5,309,868.00 
88nols 25 138,225.90 53 222,952.00 FRhode Wsland 53 283,164.66 100 360,272.00 
kdlana 133 1,193,440.12 186 1,630,055.00 South Carolina 64 169,608.86 97 188,754.00 
lw 11 20,141.91 15 27,196.00 South Dakota 6 9,387.43 7 13,119.00 
Kansas 65 684,414.27 74 846,069. 0 Tennessee 61 277,721.79 72 348,035.00 
Kentucky 216 985,637.10 281 3,124,256.00 Texes 4,536 75,140,530.22 5,362 112,108,780.00 
Louisiana 3,351 30,749,833.02 3,988 38,575,442.00 Utah 0 0.00 2 0.00 
Maine 384 4,522,707.99 541 5,411,948.00 Vermnnont 68 1,326,284.96 91 1,627,429.00 
Maryland and 352 4,518,148.75 468 5,277,802.00 Virginia 664 8,883,142.68 890 11,986,621.00 
District ol Columbia 
Massachusets 3,888 81,720,958.02 4,301 448,478,184.00 Washington 11 19,069.55 22 32,985.00 
Michigan 8 29,134.85 21 115,742.00 West Virginia 109 589,122.18 150 1,245,793.00 
Minnesota 13 61,228.79 20 118,680.00 Wisconsin 24 77,657.18 34 102,016.00 
Mississippi 151 624,081.87 182 4,441,315.00 Wyoming 0 0.00 1 0.00 
Missouri 97 443,185.04 127 546,264.00 
Montana3 36,544.26 4 41,291.00 Totals 31,462 362,756,267.71 41,350 847,104,36600 
Administered by the Federal Emergency Management Agency, Federal Insurance Administration. Data include only flood damage 
claims (e damage caused by hurricanes, tornadoes, winds, etc.). Dollar amounts do not Include administrative costs. 
Total claims includes claims paid, claims denied, insurance deductibles, and damages in excess of insurance policies. 
SData are preliminary for Fiscal Year 1992. Amounts are likely to increase as claims near the end of the fiscal year are compiled 
n.ttr r.,l!,, I R' mic,,, (. ....... t � - 11";, #"zd" .. :1 ... .. .. ... I� r-.~. ... . 
I

Drought Severity 
Start of Fiscal Year 1992 
" 'remr 
'.? aerate / Se sere 
%C 'rcuant 
End of Fiscal Year 1992 
E "t-me 
SNo Drougnt 
Data from NWS, Climate Analysis Center. 
Drought severity (from Palmer Long-tm Drought Inde) in the United States at 
the start of Fiscal Year 1992 (top) and at the end of Fiscal Year 1992 (bottom). 
G-12 
.

Atlantic Tropical Cyclones 
1982-1992 Fiscal Years 
12 
9 
1111..11..111..... .. 1 .III.. 
1111 
I 
1982 1983 1984 1982 1983 1984 
12 
11 
ie.e esi IsIaI..III. s s iii is s 
8 8 
7 
5 
.,,p,,..*e* 
7 
1985 1986 1987 1988 1989 
Fiscal Year 
12 
*, 10-Year(1982- 1991) 
Tropical Storm 
Average - 9.3 
I' 10- Year (1982-1991) 
Hurricane 
Average - 4.8 
1990 1991 1992 
No. of tropical cyclones 
(winds of greater than 35 mph) 
No. of hurricanes 
(tropical cydones with 
winds of greater than 74 mph) 
Data from NWS, National Ilurncanc Ccnicr. 
Tropical cyclones in the Atlantic Oceanu Basin since Fiscal Year 1982. The ten 
(fiscal) year (1982-91) average is shown for comparison. 
14- 
12- 
10
2 
(0 
c
0
o 
i-
E
Z 
c) 
D

Distribution of tornadoes and their effects (damages in thousands of dollars) in the 
United States, by state, during Fiscal Year 1992. 
Number of 
Tomadoes Lost 
Number of 
Tomernadoes 
LoUs 
Los 
7 2 2,400 Nevada 4 0 75 
1 0 0 New Hampshire 0 0 0 
10 0 1,166 New Jersey 4 0 125 
6 0 5.376 New Mexoo 24 0 536 
5 0 1,016 New York 25 0 9,091 
81 0 179 North Carolina 14 0 2,383 
4 0 1 North Dakota 15 0 930 
6 0 240 Ohio 59 0 24,025 
45 0 5,950 Oklahoma 70 0 4,603 
3 0 77 Oregon 4 0 60 
0 0 0 Pennsylvhrania 30 0 5.357 
4 0 25 Puerto Rioo and 0 0 0 
Virgin slands 
27 0 31.427 Rfhode Wland 0 0 0 
26 0 15,616 Souh Caroina 5 0 70 
30 0 4.241 South Dakota 41 0 35,228 
91 0 22,687 Tennessee 8 0 747 
7 0 2,606 .Texas 175 0 48,934 
55 2 23,040 Utah 4 0 5 
0 0 0 Vermont 0 0 0 
12 0 548 Virginia 2 0 5 
2 0 10 Washington 1 0 0 
21 0 7,270 We t Virginia 1 0 0 
39 1 69,140 Wisoonsln 22 1 36.,728 
39 3 7,638 Wyoming 10 0 0 
25 2 16,626 
9 0 140 Totals 1148 11 404,160 
75 0 17,839 
Data from NWS, National Severe Storms Forecast Center. 
1. There is no single source of tornado damage statistics. Damage estimates may be underestimated. Information on tornado events 
that occurred at the end of the fiscal year is subject to greater uncertainty because reports may be either preliminary or unavailable. 
These data reprint the best data available at the time of publication, and provide a good indication of the scope of damage in each 
state. 
SThis number represents the sum of all of the tornadoes reported by all of the states through the end of the fiscal year. Final 
confirmation and/or verification of tornadoes can take several months, therefore the number of tornadoes is subject to change. These 
data represent the best available data at the time of publication, and provide a reasonably accurate estimate of the number of 
confirmed tornadoes.

Atlantic Ocean Basiz tropical cyclones and their effects (damages in dollars) on 
the United States during Fiscal Year 1992. 
Name Month and Year Location U.S. Deaths U.S. Damage 
1. Tropical Storm Fabian Oct. 1991 Caribbean/Florida 0 - 
2. Hurricane Grace Oct. 1991 Atlantic/Bermuda 0 - 
3. Unnamed Hurricane Nov. 1991 Atlantic/Nova Scotia 0 
4. Hurricane Andrew Aug. 1992 Bahamas/Southeastern U.S. 50 $ 20 - 30 billion 
5. Hurricane Bonnie Sep./Oct. 1992 Atlantic/Azores 0 - 
6. Hurricane Charley Sep. 1992 Atlantic/Azores 0 
7. Tropical Storm Danielle Sep. 1992 Atlantic/Eastern U.S. 1 - 
8. Tropical Storm Earl Sep. 1992 Atlantic 0 - 
i. This hurricane formed near the center of a large non-tropical storm (the great "Halloween Storm). Though never named, the 
hurricane was a true tropical cyclone, and thus is being included as such in this report. The hurricane had no impact on the United 
States. Rather, it was the huge Halloween Storm which was blamed for at least four deaths and hundreds of millions of dollars of 
damage along much of the Eastern Seaboard, due to extraordinary sea conditions, high winds, beach erosion and coastal flooding. 
2. Of these 50 United States fatalities, 44 occurred in Florida (15 as a direct result of the hurricane, another 29 as an indirect result), 
while six perished in Louisiana (all directly related to the hurricane). Of the deaths directly related to the hurricane, most occurred as 
a result of the high winds. Others died as a result of high sea conditions, tornadoes or other hurricane effects. No deaths were 
reported as a result of rainfall-induced flooding. Four other deaths were reported in the Bahamas (three direct and one indirect). 
Thus, Hurricane Andrew resulted in a total of 54 fatalities: 24 as a direct result of the storm's effects, and 30 due to indirect causes. 
3. Damage estimates in Florida range from $15-30 billion. I)amages in Louisiana are estimated at close to $1 billion. Damages in 
the Bahamas are estimated at $0.25 billion. The majority of the damages produced by lurricane Andrew were caused by the strong 
winds. Other hurricane effects which caused damages included storm surges and coastal flooding, tornadoes, high seas and beach 
erosion. Only a minimal amount of damage was produced by rainfall-induced flooding. 
4. This death occurred when a sailboat east of New Jersey sank in the storm, drowning one person. 
C) 
I 
01

A 
AIWW - Mooring Basins (SAW) 6-29 
AIWW - New River Onslow County, NC (SAW) 6-29 
AIWW - Norfolk to St. Johns River, FL (SAJ) 9-51 
AIWW - Peltier Creek, 12-foot project (SAW) 6-29 
AIWW - Tidal Lock in Snows Cut (SAW) 6-29 
Aberdeen and Vicinity, SD (MRO) 26-21 
Aberdeen Creek, VA (NAO) 5-17, 5-19 
Aberdeen, MS (SAM) 10-56 
Aberdeen, OH (ORH) 17-22 
Abescon Inlet, NJ (NAP) 3-25 
Abilene, KS (MRK) 27-17, 27-20 
Abiquiu Dam, NM (SWA) 32-5, 32-14, 32-18 
Absecon Creek, NJ (NAP) 3-25 
Accotink Creek, VA (NAB) 4-32 
Acequias Irrigation System, NM (SWA) 32-1, 32-12, 
32-16 
Active Investigations 
Charleston District (SAN) 7-9 
Ada County Unit (NPW) 39-17 
Adams Creek, SC (SAN) 7-17 
Adams, Hossie River Basin, MA (NAN) 2-32 
Adams Levee, IN (Wabash River) (ORL) 16-26, 16-30 
Addicks and Barker Reservoirs, TX (SWG) 31-11 
Addison, NY (NAB) 4-12, 4-24 
Adena, OH (Short Creek) (ORP) 18-24 
Adkin Branch, NC (SAW) 6-29, 6-32 
Advance Engineering and Design 
Alaska District (NPA) 40-6 
Albuquerque District (SWA) 32-12 
Baltimore District (NAB) 4-20 
Buffalo District (NCB) 20-15 
Detroit District (NCE) 21-46 
Fort Worth District, (SWF) 30-12 
Jacksonville District (SAJ) 9-24 
Los Angeles District (SPL) 33-8 
Louisville District (ORL) 16-13 
Mobile District (SAM) 10-31 
Pittsburgh District (ORP) 18-12 
Portland District (NPP) 37-21 
Rock Island District (NCR) 23-6 
Sacramento District (SPK) 35-25 
San Francisco District (SPN) 34-6 
Seattle District (NPS) 38-12 
St. Paul District (NCS) 24-17 
Tulsa District (SWT) 29-12 
Walla Walla District (NPW) 39-8 
Wilmington District (SAW) 6-18 
Afono Area and Aoa Area, American Samoa (POD) 
36-8 
Agana Bayfront, Guam (POD) 36-12 
Agana River, Guam (POD) 36-9 
Agana Small Boat Harbor, Guam (POD) 36-7 
Agat Harbor, Guam (POD) 36-7 
Akutan, AK (NPA) 40-13 
Ala Wai Harbor, Oahu, HI (POD) 36-10 
Alabama-Coosa Rivers, AL & GA (SAM) 10-24, 
10-37, 10-52, 10-47 
Alabama River at Montgomery, AL (SAM) 10-50, 
10-51 
Alabama River, Selma AL (SAM) 10-51 
Alameda Creek, CA (SPK) 35-38 
Alamogordo Diversion Channel, Tularosa (closed) 
Basin, NM (SWA) 32-19 
Alamogordo, NM (SWA) 32-2, 32-12 
Alamosa, CO (SWA) 32-2, 32-12, 32-16 
Albemarle and Chesapeake Canal, VA (NAO) 5-16 
Albeni Falls Dam, ID (NPS) 38-11, 38-18, 38-23 
Albuquerque Diversion Channels, NM (SWA) 32-2, 
32-13 
Alenaio Stream, Hawaii, HI (POD) 36-3, 36-5, 36-6 
Alford, Green River, MA (NED) 1-46, 1-55 
Algoma Harbor, WI (NCE) 21-84 
Alhambra Creek, CA (SPK) 35-40 
Alii Drive, Hawaii, HI (POD) 36-11 
Aliso Creek Dam (SPL) 33-32 
Allatoona Dam - Coosa River Basin, GA (SAM) 
10-26, 10-37 
Allegany, NY Unit I (Allegheny River) (ORP) 18-23 
Allegany, NY Unit II (Five Mile Creek Area) (ORP) 
18-23 
Allegheny River, open channel work (ORP) 18-21 
Allegheny River, PA (ORP) 18-2, 18-13, 18-17, 18-25 
Allentown, Lehigh River, PA (NAP) 3-27 
Allenville, AZ (SPL) 33-30 
Alley Bay, Beals, ME (NED) 1-46 
Alligator Branch, Sumter County, SC (SAN) 7-18 
Allison Lake (Valdez Hydropower), AK (NPA) 40-12 
Alloway Creek, NJ (NAP) 3-25, 3-26 
Alma Harbor, WI 25-7 
Almond Lake, NY (NAB) 4-12, 4-24 
Almond Village, NY (NAB) 4-36 
Aloha-Rigolette Area, Grant and Rapides Parishes, LA 
(LMK) 12-20, 12-21 
I-1

Aloha Rigolette, LA (LMK) 12-3, 12-10, 12-12 
Alpena Harbor, MI (NCE) 21-2, 21-48, 21-69 
Alpine Dam and Page Park Dam, Rockford, IL (NCR) 
23-14 
Alpine, TX (SWA) 32-19 
Alsea River, OR (NPP) 37-36 
Altamaha, Oconee, and Ocmulgee Rivers (SAS) 8-2, 
8-11, 8-13 
Alteration of Berwick Bay Bridge (LMN) 11-15 
Alternative for Sugar Hill Reservoir (NED) 1-47, 1-49 
Alton, IN (ORL) 16-26, 16-30 
Alton to Gale Organized Levee Districts, IL & MO 
(LSM) 14-3, 14-9, 14-12 
Altoona Lake, Coosa River Basin, GA (SAM) 10-47 
Alum Creek Lake, OH (ORH) 17-2, 17-12, 17-17 
Alvin R. Bush Dam, PA (NAB) 4-18, 4-26 
Amazon Creek, OR (NPP) 37-38 
Ambrose Channel (NAN) 2-28 
American and Sacramento Rivers, CA (SPK) 35-34 
American River, CA (SPK) 35-38 
Ames Dam and Reservoir, Skunk River, IA (NCR) 
23-13 
Amesbury, Powwow River, MA (NED) 1-46, 1-56 
Amite River and Bayou Manchac, LA (LMN) 11-15 
Amite River and Tributaries, LA (LMN) 11-17 
Amory, MS (SAM) 10-56 
Amsterdam, OH (ORP) 18-22, 18-29 
Anacortes Harbor, WA (NPS) 38-1, 38-14, 38-20 
Anacortes Navigation Channel, WA (NPS) 38-25 
Anacostia River (NAB) 4-38 
Anacostia River and Flats (NAB) 4-32 
Anacostia River and Tributaries, Flood Protection and 
Navigation, Improvements, DC & MD (NAB) 
4-9, 4-23, 4-30, 4-35 
Anacostia River Basin (NAB) 4-38 
Anaheim Bay Harbor Orange County, CA (SPL) 
33-29 
Anahuac Channel, TX (SWG) 31-8 
Anchor Point, AK (NPA) 40-13 
Anchorage Harbor (Uncompleted Portion), AK (NPA) 
40-12 
Anchorage Harbor, AK (NPA) 40-1, 40-7, 40-9 
Anchorages, VA (NAO) 5-15 
Anclote River, FL (SAJ) 9-49, 9-51 
Andalusia Harbor, IL 25-7 
Anderson, IN (White River) (ORL) 16-26 
Anderson Park, Newport News, VA (NAO) 5-18 
Andover Lake, CT (NED) 1-47, 1-49 
Andrews River, MA (NED) 1-41 
Angler-use sites, Meramec Basin, MO (LSM) 14-18 
Annapolis Harbor, MD (NAB) 4-32 
Ansonia-Derby, CT (NED) 1-46, 1-55 
Antelope and Blackburn Creeks, CA (SPK) 35-44 
Antelope Creek, CA (SPK) 35-43 
Antelope Creek, Lincoln, NE (MRO) 26-21 
Antelope - Little Bear Creek, Eagle Point, OR (NPP) 
37-42 
Apalachicola Bay, FL (SAM) 10-3, 10-33, 10-39, 
10-52 
Apalachicola, Chattahoochee, and Flint Rivers, AL, 
FL & GA (SAM) 10-27, 10-37, 10-48, 10-53 
Applegate Lake, Rogue River Basin, OR (NPP) 37-10, 
37-24, 37-33, 37-43 
Appomattox River, VA (NAO) 5-2, 5-9, 5-13, 5-17 
Appon Mouth of Yukon River, AK (NPA) 40-11 
Apponaug Cove, RI (NED) 1-41 
Appoquinimink River, DE (NAP) 3-25, 3-28 
Apra Harbor, Guam (POD) 36-11 
Aquashicola Reservoir, PA (NAP) 3-28 
Aquatic Plant Control 
Charleston District (SAN) 7-1, 7-10, 7-13, 7-17 
Galveston District (SWG) 31-2, 31-19, 31-23, 
31-38 
Jacksonville District (SAJ) 9-2, 9-26, 9-34, 9-34 
Mobile District (SAM) 10-3, 10-33, 10-39 
New England Division (NED) 1-3, 1-26, 1-35 
New Orleans District (LMN) 11-15 
New York District (NAN) 2-3, 2-18, 2-22 
Philadelphia District (NAP) 3-26 
Sacramento District (SPK) 35-26, 35-38 
Savannah District (SAS) 8-2, 8-11, 8-13 
Wilmington District (SAW) 6-2, 6-19, 6-26 
Aquia Creek, VA (NAB) 4-32 
Aquilla Lake, TX (SWF) 30-3, 30-15, 30-19 
Ararat River, Mount Airy, NC (SAW) 6-28 
Arcadia Harbor, MI (NCE) 21-3, 21-48, 21-69 
Arcadia Lake, OK (SWT) 29-2, 29-13, 29-20 
Arch Creek, Dade County, FL (SAJ) 9-50 
Archers Creek, SC (SAN) 7-17 
Archusa Creek, MS (SAM) 10-56 
Ardsley, NY (NAN) 2-32 
Area East of Albany, OR (NPP) 37-40 
Area V, Estelline Springs, TX (SWT) 29-3, 29-13, 
29-21 
Area VIII, TX (SWT) 29-3, 29-13 
Arecibo Harbor, FL (SAJ) 9-2, 9-26, 9-34 
I-2

Arkansas City (SWT) 29-30 
Arkansas-Red River Basins Chloride Control Projects, 
KS, OK and TX (SWT) 29-3, 29-13, 29-21 
Arkansas River Basin, AR and OK (SWT) 29-29 
Arkansas River Basin, AR, OK and KS (SWL) 28-2, 
28-14, 28-18 
Arkansas River Basin, AR, OK and KS: Navigation 
28-24, 28-25, 28-26, 28-27 
Arkansas River Basin Multiple-Purpose Plan (SWT) 
29-26 
Arkansas River, Great Bend, KS to Tulsa, OK (SWT) 
29-29 
Arkansas River, Little Rock Slackwater Harbor, AR 
(SWL) 28-21 
Arkansas River, Moffett, OK (SWT) 29-27 
Arkport Dam, NY (NAB) 4-12, 4-24 
Arlington, Alkali Canyon, OR (NPP) 37-38 
Arlington, Grand Prairie, TX (SWF) 30-23 
Arlington Lake, MO (MRK) 27-18 
Armuchee Creek, GA (SAM) 10-50 
Arroyo Colorado, TX (SWG) 31-14, 31-38 
Arthur Kill Channel (NAN) 2-28 
Arthur V. Ormond Lock and Dam (No. 9), AR (SWL) 
28-2 
Asan Village, Guam (POD) 36-9 
Ashland Harbor, WI (NCE) 21-3, 21-48, 21-69 
Ashland, KY (ORH) 17-21, 17-24 
Ashley River, SC (SAN) 7-17 
Ashtabula Harbor, OH (NCB) 20-2, 20-16, 20-24 
Asotin Creek, Asotin, ID (NPW) 39-15 
Asotin Dam, Snake River, ID & WA (NPW) 39-17 
Asquiroga Bay, Guam (POD) 36-8 
Astoria Turning Basin, OR (NPP) 37-36 
Atchafalaya River Bayous Chene Boeuf, and Black, 
LA (LMN) 11-15 
Atchafalaya River, Morgan City to Gulf of Mexico, 
LA (LMN) 11-15 
Atchinson, KS (MRK) 27-17 
Athalia, OH (ORH) 17-22 
Athens, OH (ORH) 17-21, 17-24 
Atkinson Creek, Green County, MS (SAM) 10-51 
Atka, AK (NPA) 40-13 
Atlantic Beach Channels, NC (SAW) 6-26 
Atlantic City, NJ (NAP) 3-28 
Atlantic Coast of Maryland (NAB) 4-9, 4-23, 4-30 
Atlantic Gulf Ship Canal, FL (SAJ) 9-49 
Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL (SAS) 8-3, 8-11, 8-13 
Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL (SAJ) 9-2, 9-26, 9-34 
Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL (SAW) 6-2, 6-19, 6-23 
Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL (SAN) 7-2, 7-10, 7-13 
Atlantic Intracoastal Waterway Between Norfolk, VA 
and St. Johns River, FL (NAO) 5-2, 5-9, 5-13 
Atlantic Ocean Channel, VA (NAO) 5-17, 5-19 
Auasi Harbor American Samoa (POD) 36-7 
Auburn, NY, Owasco Outlet (NCB) 20-42 
Auburn Water Pump Facility, Auburn, NY (NCB) 
20-44 
Auglaize River, Paulding County, OH (NCB) 20-44 
Augusta, KY (ORH) 17-21 
Augusta LPP, KS (SWT) 29-24 
Aunt Lydia's Cove, Chatham, MA (NED) 1-51 
Aunuu Harbor American Samoa (POD) 36-7 
Aurora, IN (ORL) 16-26, 16-30 
Aurora, Westerly Creek-Kelley Road Dam, CO 
(MRO) 26-19 
AuSable Harbor, MI (NCE) 21-3, 21-48, 21-69 
Authorized Beach Erosion Control Projects 
Detroit District (NCE) 21-38 
Authorized Bridge Alteration 
New England Division (NED) 1-9 
Avalon (SPL) 33-28 
Avoca, NY (NAB) 4-12, 4-24 
Avon Harbor, NC (SAW) 6-26 
Avon, OH (NCB) 20-43 
Aylesworth Creek Lake, PA (NAB) 4-11, 4-24 
B 
B. Everett Jordan Dam and Lake, NC (SAW) 6-11, 
6-21 
Bachelor Island, WA (NPP) 37-40 
Back Creek, MD (NAB) 4-32 
Bad River, Bank Protection, Fort Pierre, SD (MRO) 
26-19 
Badger Creek, Glacier City, MT (MRO) 26-24 
Bagaduce River, ME (NED) 1-46, 1-41 
Bagaduce River, ME (uncompleted portion) (NED) 
1-47, 1-49 
Bailey Creek, Indianapolis, IN (ORL) 16-37 
Bainbridge, NY (NAB) 4-35, 4-38 
Baker Brook, MA (NED) 1-47, 1-49 
Bakers Haulover Inlet, FL (SAJ) 9-2, 9-26, 9-34 
I-3

Ball Mountain Lake, VT (NED) 1-12, 1-29, 1-53 
Baltimore Harbor and Channels, MD and VA (NAB) 
4-3, 4-22, 4-27, (NAO) 5-2, 5-9, 5-13, 5-19 
Baltimore Harbor and Channels, MD (Ferry Bar and 
Spring Garden Channel) (NAB) 4-36 
Baltimore Harbor, MD Collection and Removal of 
Drift (NAB) 4-4, 4-22, 4-28 
Bandon Small Boat Basin, Coquille, OR (NPP) 37-36 
Banner Special Drainage and Levee Districts, IL 
(NCR) 23-11, 23-14 
Banning Levee-San Gorgonio River, Riverside County 
(SPL) 33-31 
Bar Harbor Bar, ME (NED) 1-41 
Bar Harbor, ME (NED) 1-41 
Bar Harbor, ME (uncompleted portion) (NED) 1-49 
Bar Point Harbor, AK (NPA) 40-11 
Barataria Bay Waterway, LA (LMN) 11-15 
Barbers Point Harbor, Oahu, HI (POD) 36-7 
Barbour Creek, Eufaula, AL (SAM) 10-51 
Barbourville, KY (ORN) 15-13, 15-18 
Barcelona Harbor, NY (NCB) 20-40 
Bardwell Lake, TX (SWF) 30-3, 30-15, 30-19 
Barkley Dam and Lake, Barkley, KY and TN (ORN) 
15-14 
Barnard, KS (MRK) 27-17 
Barnegat Inlet, NJ (NAP) 3-2, 3-16, 3-20 
Barnegat Light, NJ (NAP) 3-28 
Barnett Creek, KY (Rough River) (ORL) 16-29 
Barre Falls Dam, MA (NED) 1-12, 1-29, 1-53 
Barren River Lake, KY (ORL) 16-5, 16-14, 16-32 
Barrow, AK (NPA) 40-13 
Bartley, NE (MRK) 27-1727-20 
Bass Harbor Bar, ME (NED) 1-41 
Bass Harbor, ME (NED) 1-41, 1-51 
Bassett Creek, MN (NCS) 24-4, 24-18 
Bastrop Bayou, TX (SWG) 31-38 
Batavia and Vicinity, Tonawanda Creek, NY (NCB) 
20-42 
Bath, NY (NAB) 4-35, 4-38 
Baton Rouge Harbor Segment between Mi 2.5 and 5.0 
(LMN) 11-18 
Battle Creek, Bank Protection, Battle Creek, NE 
(MRO) 26-20 
Baudette Harbor, MN (NCS) 24-23 
Bay City Harbor, WI 25-7 
Bay Ridge, Red Hook Channels, NY (NAN) 2-3, 
2-18, 2-22, 2-28 
Bay River, NC (SAW) 6-26 
Bayard, WV (NAB) 4-35, 4-39 
Bayfield Harbor, WI (NCE) 21-84, 21-90 
Bayou Bartholomew, LA and MO (LMK) 12-16, 
12-23 
Bayou Bodcau and Tributaries, AR and LA (LMK) 
12-4, 12-10, 12-12, 12-19 
Bayou Bodcau, Red Chute, and Loggy Bayou, LA 
(LMK) 12-20, 12-21 
Bayou Bodcau Reservoir, LA (LMK) 12-20, 12-21 
Bayou Bonfouca, LA (LMN) 11-15 
Bayou Choupique, LA (LMN) 11-17 
Bayou Coden, AL (SAM) 10-3, 10-33, 10-39, 10-52 
Bayou Dorcheat, Loggy Bayou and Lake Bisteneau, 
LA (LMN) 11-15 
Bayou Dupre, LA (LMN) 11-15 
Bayou Grosse Tete, LA (LMN) 11-18 
Bayou La Batre, AL (SAM) 10-4, 10-33, 10-39, 10-52 
Bayou La Lautre, St. Malo, and Yscolskey, LA 
(LMN) 11-15 
Bayou Lacombe, LA (LMN) 11-15 
Bayou Lafourche and Lafourche Jump Waterway, LA 
(LMN) 11-15 
Bayou Nicholas-Coushatta, LA (LMK) 12-19 
Bayou Pierre in Vicinity of Shreveport, LA (LMK) 
12-19, 12-20, 12-21 
Bayou Plaquemine Brule, LA (LMN) 11-15 
Bayou Queue de Tortue, LA (LMN) 11-15 
Bayou Rapides, LA (LMN) 11-17 
Bayou Rigolette, LA (LMN) 11-13 
Bayou Segnette Waterway, LA (LMN) 11-15 
Bayou Teche & Vermillion River, LA (LMN) 11-15 
Bayou Teche, LA (LMN) 11-15 
Bayou Terrebonne, LA (LMN) 11-15 
Bayou Vermillion, LA (LMN) 11-15 
Bayous D'Arbonne and Corney, LA (LMK) 12-16 
Bayport, FL (SAJ) 9-49 
Bayport Harbor, MI (NCE) 21-4, 21-48, 21-69 
Baytown, TX (SWG) 31-38 
Beach Erosion Control Activities Pursuant to Section 
103, Public Law 87-874 (Preauthorization) 
New England Division (NED) 1-10 
Beach Erosion Control Projects Under Construction 
C-1 
Beach Erosion Control Work Under Special 
Authorization 
Baltimore District (NAB) 4-8 
Buffalo District (NCB) 20-12 
Charleston District (SAN) 7-8 
I-4

Chicago District (NCC) 22-7 
Detroit District (NCE) 21-39 
Jacksonville District (SAJ) 9-20 
Mobile District (SAM) 10-15 
Norfolk District (NAO) 5-7, 5-11 
Pacific Ocean Division (POD) 36-3 
San Francisco District (SPN) 34-5 
Savannah District (SAS) 8-6 
Beal Slough, NE (MRO) 26-23 
Beals Harbor, ME (NED) 1-41 
Bear Creek, County Route 276, Marion County, MO 
(NCR) 23-16 
Bear Creek Dam (City of Hannibal, MO) (NCR) 
23-11, 23-14 
Bear Creek Lake, CO (MRO) 26-226-9, 26-12 
Bear Creek, Flathead County Bridge, near Essex, MT 
(NPS) 38-26 
Bear Creek, Kendrick, ID (NPW) 39-15 
Bear Creek, Long Tom River, OR (NPP) 37-40 
Bear Creek, Medford, OR (NPP) 37-38 
Bear Creek, NC (SAW) 6-32 
Bear Creek, Vernonia, OR (NPP) 37-42 
Bear River, CA (SPK) 35-40 
Bear Stream, CA (SPK) 35-42 
Beards Brook Reservoir, NH (NED) 1-49 
Beatrice, Big Blue River, NE (MRK) 27-18 
Beaufort Harbor, NC (SAW) 6-4, 6-19, 6-24 
Beaver Bay, MN (NCE) 21-84 
Beaver Brook, Keene, NH (NED) 1-46, 1-54 
Beaver Brook Lake, NH (NED) 1-49 
Beaver Creek, Montezuma, GA (SAM) 10-50 
Beaver Creek Near Tillamook, OR (NPP) 37-38 
Beaver Creek, Platte County, NE (MRO) 26-24 
Beaver Creek, Troutdale, OR (NPP) 37-42 
Beaver Drainage District, OR (NPP) 37-38 
Beaver Lake, AR (SWL) 28-10, 28-16, 28-30 
Beaver Run/Walnut Creek, Millcreek, PA (NCB) 
20-43 
Bedford, East Fork, 102 River, IA (MRK) 27-17 
Beebe Lake, Frankfort, MN (NCS) 24-30 
Beech Fork Lake, WV (ORH) 17-3, 17-12, 17-17 
Beechwood Girl Scout Camp, Sodus, NY (NCB) 
20-44 
Belfast Harbor, ME (NED) 1-41, 1-58 
Belford, NJ (NAN) 2-35 
Belhaven Harbor, NC (SAW) 6-26 
Belington, PA (reconnaissance) (ORP) 18-30 
Bell Foley Lake, White River, AR (SWL) 28-22, 
28-30 
Bellaire, PA (ORP) 18-24 
Bellamy River, NH (NED) 1-41 
Belle Fourche, Belle Fourche River, SD (MRO) 26-19 
Belle Fourche, Cheyenne River, SD (MRO) 26-15 
Belle River, MI (NCE) 21-84 
Bellevue, KY (ORL) 16-26, 16-30 
Bellingham Harbor (I&J Street Waterway), WA (NPS) 
38-25 
Bellingham Harbor, WA (NPS) 38-2, 38-14, 38-20 
Bellville Point, GA (SAS) 8-18 
Belpre, OH (ORH) 17-22 
Beltline Road, Cameron, TX (SWF) 30-23 
Belton Lake Modification, TX (SWF) 30-22 
Belton Lake, TX (SWF) 30-3, 30-15, 30-19 
Beltzville Lake, PA (NAP) 3-11, 3-18, 3-23 
Benbrook Lake, TX (SWF) 30-4, 30-15, 30-19 
Bennett Creek, VA (NAO) 5-3, 5-9, 5-13, 5-17 
Bennett-McDonald-Smithland D.D., Little Sioux 
River, IA (MRO) 26-21 
Bennington Reservoir, NH (NED) 1-49 
Bennington, VT (NAN) 2-34 
Benwood, WV (ORP) 18-22 
Berkeley Harbor, CA (SPN) 34-13 
Berkeley Marina, CA (SPN) 34-13 
Berlin Lake, Ohio River Basin, OH (ORP) 18-6, 
18-13, 18-18 
Berrien County, MI (St. Joseph Shore) beach erosion 
control (1958 Flood Control Act) (NCE) 21-86 
Bethel Bank, Kuskokwim River, AK (NPA) 40-12 
Bethel Bank Stabilization, AK (NPA) 40-5, 40-8, 
40-10 
Bethel Small Boat Harbor, AK (NPA) 40-2, 40-7, 
40-9, 40-11 
Bethlehem, Lehigh River, PA (NAP) 3-27 
Bettendorf, IA (NCR) 23-11, 23-14 
Betterton Harbor, MD (NAB) 4-36 
Beverly Harbor, MA (NED) 1-41 
Beverly Hills, McLennan County, TX (SWF) 30-23 
Big (Cunningham) Creek, OH (NCB) 20-40 
Big and Little Sallisaw Creeks (SWT) 29-30 
Big and Little Sallisaw Navigation Project (SWT) 
29-23 
Big Bay Harbor, MI (NCE) 21-4, 21-49, 21-69 
Big Bend Dam-Lake Sharpe, Missouri River Basin, 
SD (MRO) 26-6, 26-11, 26-14, 26-18 
Big Bend Wildlife Restoration (MRO) 26-22 
I-5

Big Bend, WV (ORH) 17-23 
Big Black River, MS (LMK) 12-16, 12-21 
Big Blue Lake, IN (ORL) 16-27, 16-31, 16-33 
Big Blue River, Seward, NE (MRK) 27-17 
Big Brown Creek, Prentiss County, MS (SAM) 10-50 
Big Choctaw Bayou, LA (LMK) 12-21 
Big Coulee to Devils Lake, ND (NCS) 24-31 
Big Creek and L'Anguille River, White River Basin, 
AR (LMM) 13-7 
Big Creek Canal, Millington, TN (LMM) 13-6 
Big Darby, OH (ORH) 17-23 
Big Dry Creek Dam and Diversion, CA (SPK) 35-38 
Big Fork River, MN (NCS) 24-30 
Big Fossil Creek, TX (SWF) 30-22 
Big Fossil Creek, TX (SWF) 30-22 
Big Hole River, Pennington Bridge, Near Twin 
Bridges, MT (MRO) 26-19 
Big Horn River, Two Leggin Bridge, Near Hardin, 
MT (MRO) 26-19 
Big Lake Drainage and Levee District, IL (NCR) 
23-11, 23-14 
Big Pigeon and Little Pigeon Bayous, LA (LMN) 
11-15 
Big Pine Lake, IN (Wabash River) (ORL) 16-24 
Big Pine Lake, TX (SWT) 29-24 
Big River Reservoir, RI (NED) 1-49 
Big Run, PA (ORP) 18-22, 18-29 
Big Sandy Lake, TX (SWF) 30-22 
Big Sioux River at Sioux City, IA (MRO) 26-15 
Big Sioux River/Dakota Dunes, SD (MRO) 26-23 
Big Sioux River, Fink Bridge, Near Flandreau, SD 
(MRO) 26-19 
Big Sioux River, Harrisburgh, SD (MRO) 26-19 
Big Sioux River, Jefferson, SD (MRO) 26-19 
Big Sioux River, North Sioux City, SD (MRO) 26-19 
Big Sioux River, Plymouth County, IA (MRO) 26-21 
Big Sioux River, Schofield Bridge, Near Flandreau, 
SD (MRO) 26-19 
Big Sioux River, Sioux City, IA (MRO) 26-21 
Big Sioux River, Union County, SD (MRO) 26-19 
Big South Fork National River and Recreation Area, 
KY and TN (ORN), 15-4, 15-9 
Big Spring, TX (SWF) 30-22 
Big Stone Lake and Whetstone River, MN and SD 
(NCS) 24-4, 24-18, 24-29 
Big Stranger Creek, KS (MRK) 27-17 
Big Suamico Harbor, WI (NCE) 21-84, 21-90 
Big Sunflower River, MS (LMK) 12-16 
Big Swan D&L District, Illinois River, IL (LSM) 
14-18 
Big Thompson River, Johnstown, CO (MRO) 26-19 
Big Timber Creek, NJ (NAP) 3-25 
Big Walnut Creek, 500 W. Putnam Co., IN (ORL) 
16-37 
Big Walnut Lake, IN (Wabash River) (ORL) 16-24, 
16-33 
Big Wash, Milford, Beaver County, UT (SPK) 35-38 
Big Wood River, ID (NPW) 39-15 
Billings, MT (MRO) 26-17 
Biloxi Harbor, MS (SAM) 10-4, 10-33, 10-40, 10-52 
Biloxi River at Lorraine Road, Harrison County, MS 
(SAM) 10-50 
Binghamton, NY (NAB) 4-13, 4-24 
Birch Hill Dam, MA (NED) 1-13, 1-29, 1-53 
Birch Lake, OK (SWT) 29-4, 29-13, 29-21 
Birch, WV (ORH) 17-23 
Bird Rock Area, La Jolla, San Diego County, CA 
(SPL) 33-29 
Biscayne Bay, FL Hurricane Protection (SAJ) 9-50 
Bitter Creek and Rock Springs, WY (SPK) 35-44 
Bitterroot River, Florence, MT (NPS) 38-26 
Black Bayou Lake, LA (LMK) 12-20 
Black Bayou Reservoir, LA (LMK) 12-21 
Black Bear & Miller Lakes, Crow Wing City, MN 
(NCS) 24-24, 24-29 
Black Creek, Gadsden, AL (SAM) 10-50 
Black Creek, Town of Chili, NY (NCB) 20-43 
Black Fork at Hendricks, WV (ORP) 18-23 
Black River (Alcona County), MI (NCE) 21-84 
Black River (Port Huron), MI (NCE) 21-4, 21-49, 
21-69 
Black River, AR and MO (SWL) 28-21 
Black River, Butler County Road 607, MO (SWL) 
28-22 
Black River Falls, WI (NCS) 24-29 
Black River Harbor (U.P.), MI (NCE) 21-5, 21-49, 
21-70 
Black River Harbor, Alcona County, MI Authorized 
Dec. 17, 1979 under Section 201 of the 1965 
Flood Control Act (NCE) 21-86 
Black River Harbor, MI (1936 R&H Act) (NCE) 
21-86 
Black River Harbor, NY (NCB) 20-40 
Black River Lake, WI (NCS) 24-26 
Black River, NC (SAW) 6-26, 6-28 
I-6

Black River Obstruction Removal, Butler County, AR 
(SWL) 28-5, 28-14 
Black River, WI (NCS) 24-23, 24-26, 24-29, 24-30 
Black Rock Channel and Tonawanda Harbor, NY 
(NCB) 20-2, 20-16, 20-24 
Black Rock Channel and Tonawanda Harbor, NY, 
1954 R&H Act (NCB) 20-45 
Black Rock Channel and Tonawanda Harbor, NY, 
1935 R&H Act (NCB) 20-45 
Black Rock Harbor, CT (NED) 1-41 
Black Rock Harbor, CT (uncompleted portion) (NED) 
1-49 
Black Rock Lake, CT (NED) 1-17, 1-31, 1-55 
Black Walnut Harbor, MD (NAB) 4-32 
Black Walnut Point, MD (NAB) 4-35 
Black Warrior and Tombigbee Rivers, AL (SAM) 
10-5, 10-33, 10-40, 10-54 
Black Warrior River, North Port, AL (SAM) 10-51 
Black Warrior River, U.S. Hwy 11 Bridge, Fosters, 
AL (SAM) 10-50 
Blackberry Creek, Henry County, VA (SAW) 6-32 
Blackbird Creek Near Macy, NE (MRO) 26-15, 26-20 
Blackboy Creek, Tulsa County, OK (SWT) 29-27 
Blackfoot Reservoir, ID (NPW) 39-17 
Blackfoot River, ID (NPW) 39-18 
Blackfoot River, Matt Little Road, MT (NPS) 38-26 
Blackhawk Creek, Davenport, IA (NCR) 23-15 
Blackstone River Basin, MA and RI (NED) 1-11 
Blackstone River, Millbury, MA (NED) 1-46, 1-53 
Blackwater Dam, NH (NED) 1-19, 1-31, 1-56 
Blackwater River, Milton, FL (SAM) 10-49, 10-51, 
10-52 
Blackwater River, VA (Active portion) (NAO) 5-17 
Blaine Harbor, WA (NPS) 38-25, 38-31 
Blakely Mt. Dam-Lake Ouachita, AR (LMK) 12-18, 
12-21 
Bldwn, Sqw Creek Lndr Swg Lgn, WY (MRO) 26-23 
Blind Slough Diking District, Clatsop County, OR 
(NPP) 37-37 
Blue Bluff Road, Morgan County, IN (ORL) 16-37 
Blue Marsh Lake, PA (NAP) 3-11, 3-18, 3-23 
Blue Mountain Lake, AR (SWL) 28-5, 28-14, 28-28 
Blue River Channel, Kansas City, MO (MRK) 27-2, 
27-10, 27-13 
Blue River Lake, OR (NPP) 37-11, 37-25, 37-33, 
37-43 
Blue River, Salem, IN (ORL) 16-24 
Bluegrass Creek, Audubon, IA (MRO) 26-23 
Bluestone Lake, Ohio River Basin, WV (ORH) 17-3, 
17-12, 17-1,7 
Bluff Creek, MS (SAM) 10-49 
Board of Engineers for Rivers and Harbors 41-1 
Bodega Bay, CA (SPN) 34-7 
Bodie Island, NC (SAW) 6-29 
Boeuf River, LA (LMK) 12-16 
Bogachiel River, Highway 101, near Forks, WA 
(NPS) 38-26 
Bogachiel River, Undie Road, near Forks, WA (NPS) 
38-26 
Boggy Bayou, Valparaiso, FL (SAM) 10-15, 10-35, 
10-46 
Boggy Creek, Bryan County, OK (SWT) 29-28 
Boggy Creek, TX (SWF) 30-4, 30-15, 30-19 
Boise River, ID (NPW) 39-15 
Boise Valley, ID (NPW) 39-17 
Boligee Canal, Boligee, AL (SAM) 10-50 
Bolivar, NY (ORP) 18-29 
Bolles Harbor, MI (NCE) 21-5, 21-49, 21-70 
Bon Secour River, AL (SAM) 10-7, 10-33, 10-41, 
10-52 
Bonnes Coulee, Velva, ND (NCS) 24-24 
Bonneville Lake, KY (Kentucky River) (ORL) 16-24, 
16-32 
Bonneville Lock and Dam - Lake Bonneville, OR and 
WA (NPP) 37-15, 37-26, 37-34, 37-43 
Bonneville Navigation Lock, Bonneville Dam, OR and 
WA (NPP) 37-2, 37-22, 37-29 
Bonpas Creek, IL (Wabash River) (ORL) 16-26, 16-30 
Bonum Creek, VA (NAB) 4-4, 4-22, 4-28 
Boone County, KY (Ohio River, Rabbit Hash) (ORL) 
16-23 
Boothbay Harbor, ME (NED) 1-41, 1-58 
Boston Harbor, MA (1945 Act) (NED) 1-49 
Boston Harbor, MA (NED) 1-3, 1-26, 1-35 
Boswell Lake, OK (SWT) 29-24 
Boulder, CO (MRO) 26-17 
Bound Brook, Scituate, MA (NED) 1-46 
Bowman-Haley Lake, ND (MRO) 26-2, 26-9, 26-12 
Brackenridge, Tarentum and Natrona, PA (ORP) 
18-24 
Bradenton Beach, FL (SAJ) 9-61 
Bradford, PA (ORP) 18-22, 18-29 
Bradford, TN (LMM) 13-6 
Bradley Lake, AK (NPA) 40-12 
Brake Branch, Montgomery County, VA (SAW) 6-32 
Bramwell, WV (ORH) 17-24 
I-7

Branford Harbor, CT (NED) 1-41 
Branson Cove, Lower Machodoc River, VA (NAB) 
4-32 
Brant Rock Beach, Marshfield, MA (NED) 1-49 
Braymer Lake, Shoal Creek, MO (MRK) 27-17 
Brays Bayou, TX (SWG) 31-11 
Brazos Island Harbor, (SWG) 31-2, 31-19, 31-23, 
31-39, 31-40, 31-45 
Brazos River, Velasco to Old Washington, TX (SWG) 
31-38 
Breton Bay, MD (1902 River & Harbor Act) (NAB) 
4-36 
Breton Bay, MD (NAB) 4-32 
Brevard County, FL (SAJ) 9-16, 9-31, 9-45 
Brevoort Levee, IN (Wabash River) (ORL) 16-23, 
16-34 
Bridge, Mary Creek, TX (SWF) 30-23 
Bridgeport Harbor, CT (NED) 1-41, 1-58 
Bridgeport Harbor, CT (uncompleted portion) (NED) 
1-49 
Bridges, Columbia River, Cascade Locks and Hood 
River, OR (Alteration) (NPP) 37-36 
Bridgewater, VA (NAB) 4-35, 4-39 
Brigantine Island (NAP) 3-27 
Brilliant, OH (ORP) 18-24 
Bristol Harbor, Bristol, RI (NED) 1-41 
Broad Creek, Beaufort, NC (SAW) 6-28 
Broad Creek, MD (NAB) 4-32 
Broad Creek River, DE (NAB) 4-32 
Broad Creek, VA (NAO) 5-17, 5-19 
Broadkill River, DE (NAP) 3-25 
Broadwater Creek, MD (NAB) 4-36 
Broadway Street, Pecan Creek, Gainsville, TX (SWF) 
30-23 
Brockway Lake, VT (NED) 1-49 
Brockway, PA (Allegheny River Basin) (ORP) 18-24 
Broken Bow Lake, OK (SWT) 29-10, 29-19, 29-22 
Broken Bow, Mud Creek, NE (MRO) 26-20 
Bromley, KY (ORL) 16-26, 16-30 
Bronx River, NY (NAN) 2-29, 2-34 
Brookfield Lake, Yellow Creek, MO (MRK) 27-17 
Brookfield, PA (ORP) 18-22, 18-29 
Brookgreen Gardens, SC (SAN) 7-2, 7-10, 7-13 
Brooklyn, WV (ORH) 17-22 
Brookport, IL (ORL) 16-23, 16-29, 16-34 
Brookville Lake, KY (ORL) 16-5, 16-15 
Broward County, FL Beach Erosion Control and 
Hillsboro Inlet, FL Navigation Project (SAJ) 9-16, 
9-31, 9-45 
Browder Creek, Springton, TX (SWF) 30-23 
Browns Creek (NAN) 2-28, 2-29, 2-34 
Browns Creek, Nashville, TN (ORN) 15-18 
Brownwood Channel Improvement, TX (SWF) 30-22 
Brunswick County Beaches (Cape Fear to North 
Carolina - South Carolina State Line), NC (SAW) 
6-28 
Brunswick County Beaches - Long Beach Portion - 
Berm, NC (SAW) 6-29 
Brunswick Harbor, GA (SAS) 8-3, 8-11, 8-13 
Brush Creek, Jeanette, PA (plans and specifications) 
(ORP) 18-30 
Brush Creek, Kansas City, MO (MRK) 27-3, 27-10, 
27-13 
Buck Creek, NC & SC (SAN) 7-18 
Buchanan Dam-H.V. Eastman Lake, Chowchilla 
River, CA (SPK) 35-5, 35-27 
Buckhannon River, WV (ORP) 18-21 
Buckhannon, WV (ORP) 18-22, 18-29 
Buckhorn Lake, KY (ORL) 16-6, 16-15, 16-32 
Bucks Harbor, Machiasport, ME (NED) 1-41 
Bucksport Harbor, ME (NED) 1-41 
Buena Vista, OH (ORH) 17-22 
Buffalo Bayou and Tributaries, TX (SWG) 31-10, 
31-20, 31-35 
Buffalo Creek, Meadow Grove, Scranton, ND (MRO) 
26-15 
Buffalo Harbor Drift Removal, NY (NCB) 20-45 
Buffalo Harbor, NY (NCB) 20-2, 20-16, 20-25 
Buffalo, Johnson County, Diversion Channel, WY 
(MRO) 26-17 
Buffalo River, MS (LMK) 12-23 
Buffalo Ship Channel, Buffalo, NY (NCB) 20-45 
Buffalo Small Boar Harbor, NY (NCB) 20-3, 20-16, 
20-26 
Buffumville Lake, MA (NED) 1-21, 1-32, 1-57 
Buford Dam, Lake Sidney Lanier, GA (SAM) 10-28, 
10-37, 10-48 
Bull Run, PA (NAB) 4-35 
Bull Shoals Lake, AR (SWL) 28-10, 28-17, 28-30 
Bullocks Point Cove, RI (NED) 1-41 
Bunker Harbor, ME (NED) 1-41 
Burch and Jewett Creeks near Corning, CA (SPK) 
35-44 
Burch Creek, Weber County, UT (SPK) 35-38 
I-8

Burgettstown, PA (ORP) 18-22, 18-29 
Burial Hill Beach, Westport, CT (NED) 1-45 
Burketts Creek, Amory, MS (SAM) 10-50, 10-51 
Burlington Dam, Souris River, ND (NCS) 24-24 
Burlington Harbor, VT (NAN) 2-29 
Burlington, IA (NCR) 23-14 
Burns Stream, CA (SPK) 35-42 
Burns Waterway Harbor, IN (NCC) 22-2, 22-12, 
22-15, 22-19 
Burns Waterway SBH, IN (NCC) 22-2, 22-12, 22-15, 
22-19 
Burnsville Lake, Ohio River Basin, WV (ORH) 17-3, 
17-12, 17-17 
Burt-Washington Counties, NE (MRO) 26-21 
Butler County Drainage District 3, MO (SWL) 28-22 
Butler, PA (ORP) 18-22, 18-29 
Buttahatchee Creek, MS (SAM) 10-50 
Buttermilk Bay Channel, MA (NED) 1-41 
Buttermilk Channel, NY (NAN) 2-29 
Butternut Creek, East Syracuse, NY (NCB) 20-44 
Bypass Levees, CA (SPK) 35-43 
Byram River at Pemberwick, CN (NAN) 2-32 
C 
Cabrillo Beach (SPL) 33-29 
Cache Creek Basin, (Cache Creek Settling Basin), CA 
(SPK) 35-6, 35-25, 35-27, 35-34 
Cache La Poudre River, Ft. Collins (Water Treatment 
Plant), CO (MRO) 26-19 
Cache La Poudre River, Greely, CO (MRO) 26-23 
Cache La Poudre River, Windsor, CO (MRO) 26-19 
Cache River Diversion, IL (LSM) 14-16 
Cache River Levee, IL (ORL) 16-34 
Cache River, Upper Basin, IL (ORL) 16-24 
Caddo Lake Dam, LA (LMK) 12-21 
Caddo Lake, LA (LMK) 12-19 
Cadet Bayou, MS (SAM) 10-52, 10-49 
Cadle Creek, MD (NAB) 4-36 
Caesar Creek Lake, OH (ORL) 16-6, 16-15, 16-32 
Cagles Mill Lake, IN (ORL) 16-6, 16-15, 16-32 
Cairo, WV (ORH) 17-24 
Cal.-Sag Channel, Part II, Illinois Waterway, IL and 
IN (NCR) 23-13 
Calabash Creek, Brunswick County, NC (SAN) 7-17 
Calapooya River, OR (NPP) 37-40 
Calaveras River and Littlejohn Creek and Tributaries, 
including New Hogan Lake and Farmington Dam, 
CA (SPK) 35-6, 35-27 
Calcasieu Pass Channel in Old River Bend at 
Cameron, LA (LMN) 11-16 
Calcasieu River and Pass, LA (LMN) 11-15 
Calcasieu River at Coon Island, LA (LMN) 11-15 
Calcasieu River at Devil's Elbow, LA (LMN) 11-15 
Calcasieu River Salt Water Barrier, LA (LMN) 11-15 
Caledonia, Genesee River, NY 1950 FC Act (NCB) 
20-45 
Calf Pasture Beach Park, Norwalk, CT (NED) 1-45 
Calhoun County (SAM) 10-56 
Caliente Creek, CA (SPK) 35-34 
California (Cincinnati), OH (ORL) 16-26, 16-30 
Calion, AR (H.K. Thatcher) (LMK) 12-15, 12-18 
Calispell Creek, WA (NPS) 38-30 
Calloway Branch, Hurst, TX (SWF) 30-22 
Calloway Branch, Richland Hills, TX (SWF) 30-23 
Calumet Harbor and River, IL and IN (NCC) 22-2, 
22-12, 22-15, 22-19, 22-21 
Calumet River Bridges (NCC) 22-20 
Camas Creek, ID (NPW) 39-17 
Cambridge Harbor, MD (1948 River & Harbor Act) 
(NAB) 4-36 
Cambridge Harbor, MD (NAB) 4-32 
Cambridgeport Lake, VT (NED) 1-49 
Camden Harbor, ME (NED) 1-41, 1-58 
Camelsback Dam (Gila River) (SPL) 33-30 
Camp Facility, Red River, Telephone TX (SWT) 
29-28 
Camp Ground Lake, KY (Salt River) (ORL) 16-24 
Camp Perry, OH (NCB) 20-42 
Campbells Island, Mississippi River, IL (NCR) 23-13 
Campti-Clarence Area in Natchitoches Parish, LA 
(LMK) 12-19, 12-21 
Canadaway Creek, Fredonia, NY (NCB) 20-43, 20-44 
Canadian River, OK, TX, NM (SWT) 29-29 
Canal 43, AR (LMK) 12-4, 12-10, 12-12 
Canapitsit Channel, MA (NED) 1-41 
Canaseraga Creek, Dansville, NY (NCB) 20-44 
Canaveral Harbor, FL (SAJ) 9-3, 9-26, 9-34, 9-52 
Candy Lake, OK (SWT) 29-4, 29-14, 29-21 
Cane River, LA (LMN) 11-15 
Caney Creek, MS (LMK) 12-12 
Caney Fork River, Carthage, TN (ORN) 15-18 
Caney Fork River, TN (ORN) 15-13 
Canisteo, NY (NAB) 4-13, 4-24 
I-9

Cannelton, IN (ORL) 16-23, 16-29, 16-34 
Canneries to Breakers Point, American Samoa (POD) 
36-12 
Cannon River at Faribault, MN (NCS) 24-24, 24-29 
Cannonball River, Sheilds, ND (MRO) 26-23 
Cano Cacul, Aguidilla, PR (SAJ) 9-61 
Canoe Creek, Henderson, KY (ORL) 16-23, 16-34 
Canton (Nimishillen), OH (ORH) 17-24 
Canton Creek, GA (SAM) 10-56 
Canton Lake, OK (SWL) 28-28 
Canton Lake, OK (SWT) 29-4, 29-14, 29-21, 29-26 
Canton, MA (NED) 1-46 
Canton, MO (NCR) 23-11, 23-14 
Canyon County Unit (NPW) 39-17 
Canyon Lake, TX (SWF) 30-4, 30-15, 30-19 
Cap Vincent Harbor, NY (NCB) 20-40 
Cape Charles, VA (NAO) 5-7, 5-11, 5-15, 5-17, 5-19 
Cape Cod Canal, MA (NED) 1-3, 1-26, 1-36 
Cape Fear River, Above Wilmington, NC (SAW) 6-4, 
6-19 
Cape Fear River Basin, NC (SAW) 6-10, 6-31 
Cape Florida State park, FL (SAJ) 9-50 
Cape Girardeau-Jackson, MO (LSM) 14-4, 14-9, 
14-12 
Cape Girardeau, MO No. 2, MO (LSM) 14-16 
Cape Girardeau, MO Reaches Nos. 1, 3 and 4 (LSM) 
14-18 
Cape Henry Channel, VA (NAO) 5-13 
Cape Lookout, NC (SAW) 6-29 
Cape May City, NJ (NAP) 3-28 
Cape May Inlet to Lower Twp., NJ (NAP) 3-10, 3-18, 
3-23 
Cape Porpoise Harbor, ME (NED) 1-41 
Cape Vincent Harbor, NY 1945 R&H Act (NCB) 
20-45 
Carden's Bottom Drainage District No. 2, Arkansas 
River, AR (SWL) 28-22 
Carl L. Estes Dam and Lake, TX (SWF) 30-22 
Carlyle Lake, IL (LSM) 14-16 
Carneros Creek, CA (SPL) 33-8, 33-14 
Carolina Beach and Vicinity, NC (SAW) 6-11, 6-21 
Carpenters Bayou, TX (SWG) 31-12 
Carr Fork Lake, KY (ORL) 16-7, 16-15, 16-32 
Carrabelle Harbor, FL (SAM) 10-52, 10-49 
Carroll County Levee and Drainage District, IL 
(NCR) 23-13 
Carrollton, KY (ORL) 16-26, 16-30 
Carson River below Lahontan Dam, Fallon, NV (SPK) 
35-44 
Carters Creek, VA (Active portion) (NAO) 5-17 
Carters Dam and Reservoir, GA (SAM) 10-24, 10-37 
Caruthersville Harbor, MO (LMM) 13-5 
Carvers Harbor, Vinalhaven, ME (NED) 1-41 
Carysville, FL (SAM) 10-51 
Cascadia Lake, OR (NPP) 37-38 
Cascadia Lake, OR (NPP) 37-40 
Caseville Harbor, MI (NCE) 21-6, 21-50, 21-70 
Caseyville, KY (ORL) 16-26, 16-30 
Cashie River, NC (SAW) 6-26 
Casino Beach, IL (NCC) 22-6, 22-13, 22-17 
Castle Rock, Cowlitz River, WA (NPP) 37-38 
Castlewood Lake, Douglas County, CO (MRO) 26-17 
Cat Claw Creek, Abilene, TX (SWF) 30-22, 30-23 
Cataldo, ID (NPS) 38-31 
Catching Inlet Drainage District, Coos River, OR 
(NPP) 37-38 
Catfish Branch, Kingston, NC (SAW) 6-32 
Cathance River, ME (NED) 1-41 
Catherine Creek Lake, OR (NPW) 39-12, 39-15, 
39-17 
Catherine Creek, OR (NPW) 39-12, 39-15 
Cathlamet, WA (NPP) 37-36 
Cattaraugus Creek, NY (NCB) 20-40 
Cattaraugus Creek, Village of Arcade, NY (NCB) 
20-44 
Cattaraugus Harbor, NY (NCB) 20-3, 20-16, 20-26 
Cattlesburg, KY (ORH) 17-21, 17-24 
Cave-in-Rock, IL (ORL) 16-26, 16-30 
Cave Run Lake, KY (ORL) 16-7, 16-15, 16-32 
Cave Springs, GA (SAM) 10-56 
Cayuga Creek, Cheektowaga, NY (NCB) 20-42 
Cazenovia Creek, NY (NCB) 20-43 
Cecil M. Harden Lake, IN (ORL) 16-7, 16-15, 16-32 
Cedar Bayou, TX (SWG) 31-38 
Cedar Beach, Milford, CT (NED) 1-52 
Cedar Canyon Dam, Rapid City, SD (MRO) 26-15 
Cedar Creek at Cedar Lodge, NE (MRO) 26-23 
Cedar Creek, Jacksonville, FL (SAJ) 9-61 
Cedar Creek, NJ (NAP) 3-2, 3-16, 3-20 
Cedar Creek, Spaulding, NE (MRO) 26-23 
Cedar Falls, Cedar River, IA (NCR) 23-15 
Cedar Hammock, Bradenton, FL (SAJ) 9-61 
Cedar Key Harbor, FL (SAJ) 9-49, 9-51 
Cedar Point, GA (SAS) 8-18 
Cedar Point Lake, KS (SWT) 29-25, 29-29 
I-10

Cedar River Harbor, MI (NCE) 21-84 
Cedar River, Kenton, WA (NPS) 38-26, 38-31 
Cedar River, King County, WA (NPS) 38-26 
Celina Dam, KY (ORN) 15-14 
Center Hill Lake, Ohio River Basin, TN (ORN) 15-6, 
15-9, 15-17 
Central and Southern Florida (SAJ) 9-20, 9-32, 9-47, 
9-55, 9-57, 9-58, 9-59 
Central City Lake, Wapsipinicon River, IA (NCR) 
23-13 
Centralia-Chehalis Flood Warning System, WA (NPS) 
38-31 
Century Park, Lorain, OH (NCB) 20-21, 20-38 
Ceredo-Kenova, WV (ORH) 17-21, 17-24 
Chacon Creek, Laredo, TX (SWF) 30-23 
Chadakoin River, Jamestown, NY (plans and 
specifications) (ORP) 18-30 
Chagrin River, East Branch, Route 84, OH (NCB) 
20-44 
Chagrin River, Solon Road, OH (NCB) 20-44 
Chambersburg, OH (ORH) 17-22 
Channel between North & South Hero Islands, VT 
(NAN) 2-29 
Channel Connecting Plain Dealing Creek and Oak 
Creek, MD (NAB) 4-36 
Channel Connecting Thoroughfare Bay with Cedar 
Bay, NC (SAW) 6-26 
Channel Connecting York River, VA Back Creek to 
Slaights Wharf (NAO) 5-17, 5-19 
Channel from Back Sound to Lookout Bight, NC 
(SAW) 6-5, 6-19 
Channel from Naples to Big Marco Pass, FL (SAJ) 
9-3, 9-26, 9-34 
Channel from Pamlico Sound to Rodanthe, NC (SAW) 
6-26 
Channel from Phoebus, VA to deepwater in Hampton 
Roads (NAO) 5-17 
Channel Islands Harbor, CA (SPL) 33-2, 33-12, 33-16 
Channel, Naples to Big Marco Pass, FL (SAJ) 9-51 
Channel to Liberty, TX (SWG) 31-9 
Channel to Newport News, VA (NAO) 5-3, 5-9, 5-13, 
5-17 
Channel to Port Bolivar, TX(SWG) 31-2, 31-19, 
31-24, 31-39 
Channels in Straits of Mackinac, MI (NCE) 21-84 
Chaplin River, Perryville, KY (ORL) 16-23 
Chariton-Little Chariton Basin, MO (1965 Act) 
Inactive Units Little 
Chariton-Little Chariton Basin, MO (1965 Act) (MRK) 
27-17 
Chariton River (East and Middle Fork) and Mussell 
Fork Units only (MRK) 27-1 
Chariton River, MO (1944 Act) (MRK) 27-17 
Charleroi, PA (complete) (ORP) 18-30 
Charles River (Natural Valley Storage Areas), MA 
(NED) 1-11, 1-29, 1-39 
Charles River Dam, MA (NED) 1-46 
Charleston Channel, Coos Bay, OR (NPP) 37-36 
Charleston Harbor, Coos Bay, OR (NPP) 37-41 
Charleston Harbor Rediversion (Fish Lift), SC (SAN) 
7-3, 7-10, 7-14 
Charleston Harbor, SC (SAN) 7-2, 7-10, 7-13 
Charlestown, NH (NED) 1-46, 1-54 
Charlevoix Harbor, MI (NCE) 21-6, 21-50, 21-70 
Charlotte County, FL (SAJ) 9-45 
Charlotte Harbor, FL (SAJ) 9-4, 9-26, 9-34 
Chartiers Creek, PA (ORP) 18-4, 18-13, 18-29 
Chaska, MN (NCS) 24-5, 24-18 
Chatfield Lake, CO (MRO) 26-2, 26-9, 26-12 
Chatham (Stage) Harbor, MA (NED) 1-4, 1-26, 1-36 
Chattahoochee River, Eufaula, AL (SAM) 10-50 
Chattahoochee River, Franklin, GA (SAM) 10-51 
Chattooga River, Trion, GA (SAM) 10-51 
Chauvin Bayou, LA (LMK) 12-5, 12-11, 12-13 
Cheat River, WV (ORP) 18-21 
Cheatham Lock and Dam, TN (ORN) 15-14 
Cheboygan Harbor, Isle Royale, MI (NCE) 21-84, 
21-90 
Cheesequake Creek (NAN) 2-28, 2-29, 2-34 
Chefuncte River and Bogue Falia, LA (LMN) 11-15 
Chehalis River, City of Chehalis, Raw Water 
Pumphouse, WA (NPS) 38-26 
Chehalis River, Independence Road, Thurston County, 
WA (NPS) 38-26 
Chehalis River, Montesano, WA (NPS) 38-26 
Chehalis River, Salzer Creek, WA (NPS) 38-31 
Chena River Stabilization, AK (NPA) 40-5, 40-8, 
40-10 
Cherokee County, GA (SAM) 10-56 
Cherry and Red Fork Creeks LPP, OK (SWT) 29-24, 
29-27 
Cherry Creek Lake, CO (MRO) 26-3, 26-9, 26-12, 
26-18 
Cherryfield, ME (NED) 1-46 
Chesapeake and Delaware Canal, St. Georges Bridge 
Replacement, DE, 3-20 (NAP) 3-2, 3-16 
I-11

Chesapeake, OH (ORH) 17-22 
Chesconessex Creek, VA (NAO) 5-17, 5-19 
Chesire, OH (ORH) 17-22 
Chester, CA (SPK) 35-38 
Chester River, Delaware County, PA (NAP) 3-28 
Chester River, MD (1873 River & Harbor Act) (NAB) 
4-36 
Chester River, MD (NAB) 4-4, 4-22, 4-28 
Chetco River, OR (NPP) 37-2, 37-22, 37-29 
Chewaucan River, Paisley, OR (NPP) 37-38 
Chicago Harbor, (NCC) 22-3, 22-12, 22-15, 22-19 
Chicago River, IL (NCC) 22-4, 22-12, 22-16, 22-19 
Chicago River, IL (North Branch) (NCC) 22-7, 22-13 
Chickasah, OK (SWT) 29-27 
Chickasaw Bouge Creek, U.S. Highway 43 Bridge, 
Linden, AL (SAM) 10-50 
Chickasawhay River, MS (SAM) 10-56 
Chickasha, OK (SWT) 29-27, 29-29 
Chico Landing, CA (SPK) 35-40 
Chicopee Falls, MA (NED) 1-46 
Chicopee, MA (NED) 1-46, 1-54 
Chicopee, MA (uncompleted portion) (NED) 1-49 
Chief Joseph Dam - Rufus Woods Lake, WA (NPS) 
38-11, 38-18, 38-23 
Chignik, AK (NPA) 40-13 
Chikaskia River, Blackwell, OK (SWT) 29-27 
Chikaskia River, Blackwell, OK (SWT) 29-28 
Chikaskia River, Ft. Oakland, OK (SWT) 29-28 
Chillicothe, OH (ORH) 17-21, 17-24 
Chilo, OH (ORH) 17-22 
Chincoteague Bay, VA (NAO) 5-17 
Chincoteague Harbor of Refuge, VA (NAO) 5-17 
Chincoteague Inlet, VA (NAO) 5-3, 5-9, 5-13, 5-17 
Chino Canyon Improvements, Palm Springs (SPL) 
33-31 
Chippewa River, Montevideo, MN (NCS) 24-30 
Chittenango Creek and Tributaries, NY 1944 R&H 
Act (NCB) 20-45 
Choctawhatchee River, FL and AL (SAM) 10-49 
Choptank River, MD (NAB) 4-32 
Chouteau Lock and Dam (17), OK (SWT) 29-26 
Chouteau, Nameoki, and Venic Drainage and Levee 
District, IL (LSM) 14-16 
Chowan River, NC (NAO) 5-17 
Chowan River, NC (SAW) 6-26 
Christiansted Harbor, St. Croix, VI (SAJ) 9-49 
Chubb Run, Franklin, PA (detalied project report 
underway) (ORP) 18-30 
Cibolo Creek, TX (SWA) 32-19 
Cilley Creek, Cincinnati, OH (ORL) 16-37 
Cincinnati, OH (ORL) 16-23, 16-29, 16-34 
Cincinnati, OH (Unit 2) (ORL) 16-26, 16-30 
Cincinnati, OH (Unit 4) (ORL) 16-26, 16-30 
Cincinnatus, NY (NAB) 4-38 
City Creek Levee, San Bernardino County, CA (SPL) 
33-30 
City Dam, Little Caney River, KS (SWT) 29-28 
City of Aurora, Westerly Creek, CO (MRO) 26-15 
City of Isleton, CA (SPK) 35-44 
Clackamas River at Dixon Farm Location, OR (NPP) 
37-38 
Claiborne Lock and Dam, AL (SAM) 10-25, 10-37 
Clairborne County Port, MS (LMK) 12-16 
Clairborne Harbor, MD (NAB) 4-32 
Clallam Bay, Sekiu, WA (NPS) 38-26 
Clallam County (Various Locations), WA (NPS) 38-26 
Clallam River, Highway 112, WA (NPS) 38-26 
Clanton, AL (SAM) 10-50 
Claremont Lake, NH (NED) 1-49 
Claremore, OK (SWT) 29-29 
Clarence Cannon Dam and Mark Twain Salt River, 
MO (LSM) 14-7, 14-10, 14-14 
Clarence J. Brown Dam and Reservoir, OH (ORL) 
16-8, 16-16 
Clarendon to Laconia Circle White River Basin, AR 
(LMM) 13-7 
Clarington, OH (ORP) 18-24 
Clarion River, PA (reconnaissance) (ORP) 18-30 
Clark Fork River, Missoula, MT (NPS) 38-26 
Clark Fort River, Drummond, MT (NPS) 38-26 
Clark Fort River, Superior, MT (NPS) 38-26 
Clark Fort River, Vicinity of Plains, MT (NPS) 38-26 
Clark Maritime Center, Jeffersonville, IN (ORL) 
16-37 
Clark Point Beach, New Bedford, MA (NED) 1-45 
Clarkson, Middle Fork, Maple Creek, NE (MRO) 
26-20 
Clarkson, NE, Maple Creek (MRO) 26-15 
Clarksville, AR (SWL) 28-22 
Clatskanie Drainage District 1, OR (NPP) 37-40 
Clatskanie River Area, Columbia County, OR (NPP) 
37-40 
Clatskanie River, OR (NPP) 37-36 
Clatsop County Diking District 3, OR (NPP) 37-40 
Clatsop County Diking District 4, OR (NPP) 37-40 
Clatsop County Diking District 6, OR (NPP) 37-40 
1-12

Clatsop County Drainage District 1, OR (NPP) 37-40 
Clayton County, AL (SAM) 10-56 
Clayton County Bridge, Osterdock, IA (NCR) 23-16 
Clayton County, Elport, Osterdock, IA (NCR) 23-16 
Clayton County Road Creek C1X, Site 1, IA (NCR) 
23-16 
Clayton County Road Creek, Site 2, IA (NCR) 23-16 
Clayton County Road, NW, Osterdock, IA (NCR) 
23-16 
Clear & Burnt River, OR (NPW) 39-13, 39-15 
Clear Creek and Clear Lake, TX (SWG) 31-38 
Clear Creek Drainage and Levee District, IL (LSM) 
14-18 
Clear Creek, TX (SWG) 31-12, 31-20, 31-35 
Clear River, Burrilville, RI (NED) 1-46, 1-53 
Clearwater Lake, MO (SWL) 28-5, 28-15, 28-30 
Clearwater Pass, FL (SAJ) 9-49, 9-51 
Clearwater River, ID (NPW) 39-18 
Clearwater River, Jefferson County Road, WA (NPS) 
38-26 
Clearwater River, Queets River Bridge, WA (NPS) 
38-26 
Cleveland Harbor, OH (NCB) 20-3, 20-17, 20-26 
Cleves, OH (ORL) 16-26, 16-30 
Cliff Walk, Newport, RI (NED) 1-45 
Clifton, AZ (SPL) 33-9, 33-15 
Clifton, San Francisco River, AZ (SPL) 33-30 
Clifton, WV (ORH) 17-22 
Clifty Creek Lake, IN (ORL) 16-27 
Clinch River, TN and VA (ORN) 15-13 
Clinton Harbor, CT (NED) 1-41, 1-58 
Clinton Harbor, IA 25-7 
Clinton, IA (NCR) 23-11, 23-14 
Clinton, IN (ORL) 16-26, 16-30 
Clinton Lake, Wakarusa River, KS (MRK) 27-3, 
27-10, 27-13 
Clinton River, MI (NCE) 21-7, 21-50, 21-70 
Cloucester Harbor, Gloucester, MA (NED) 1-51 
Cloverport, KY (ORL) 16-26, 16-30 
Clyde, RI (NED) 1-49 
Coal Creek and Tributaries (Lake City), TN (ORN) 
15-13 
Coal Creek Drainage and Levee District, IL (NCR) 
23-11, 23-14 
Coal Creek, Henryetta, OK (SWT) 29-27 
Coal Grove, OH (ORH) 17-22 
Coal River, WV (ORH) 17-21 
Coan River, VA (NAB) 4-36 
Coast of California, Point Mugu, to San Pedro 
Breakwater, CA (SPL) 33-29 
Coasters Island Harbor, RI (NED) 1-41 
Cobscook Bay, ME (NED) 1-41 
Cocheco River, NH (NED) 1-41, 1-46 
Cochiti Lake, NM (SWA) 32-6, 32-14, 32-18 
Cochiti Wetfields, NM (SWA) 32-2, 32-12 
Cochrane, Mississippi River, WI (NCS) 24-29 
Cockrells Creek, VA (NAO) 5-17 
Coeur d'Alene River (North Fork), ID (NPS) 38-31 
Coeur d'Alene, Spokane River, ID (NPS) 38-26 
Coeur d'Alene, Springston, ID (NPS) 38-26 
Coffee County, AL (SAM) 10-56 
Coffee Creek, WA (NPS) 38-26 
Cohasset Harbor, MA (NED) 1-41 
Cold Regions Research & Engineering Laboratory 
44-1 
Cold Spring Inlet, NJ (NAP) 3-3, 3-16, 3-20 
Coldwater Creek, MO (LSM) 14-4, 14-12 
Colebrook River Lake, CT (NED) 1-13, 1-29, 1-53 
Colfax, Grant Parish, LA (LMK) 12-20, 12-21 
Colfax, Palouse River, WA (NPW) 39-13, 39-15 
Collection and Study of Basic Data 
Alaska District (NPA) 40-6 
Albuquerque District (SWA) 32-12 
Baltimore District (NAB) 4-20 
Buffalo District (NCB) 20-14 
Chicago District (NCC) 22-11 
Detroit District (NCE) 21-47 
Fort Worth District, (SWF) 30-13 
Galveston District (SWG) 31-18 
Huntington District (ORH) 17-11 
Jacksonville District (SAJ) 9-24 
Little Rock District (SWL) 28-13 
Los Angeles District (SPL) 33-8 
Louisville District (ORL) 16-13 
Mobile, District (SAM) 10-31 
Nashville District (ORN) 15-8 
New England Division (NED) 1-25 
New York District (NAN) 2-17 
Norfolk District (NAO) 5-8, 5-11 
Pacific Ocean Division (POD) 36-4 
Philadelphia District (NAP) 3-15 
Pittsburgh District (ORP) 18-12 
Portland District (NPP) 37-21 
Rock Island District (NCR) 23-6 
Sacramento District (SPK) 35-25 
San Francisco District (SPN) 34-6 
1-13

Savannah District (SAS) 8-10 
St. Paul District (NCS) 24-16 
Tulsa District (SWT) 29-12 
Walla Walla District (NPW) 39-8 
Wilmington District (SAW) 6-18 
Colliers, WV (ORP) 18-29 
Collinsville, AL (SAM) 10-50 
Collinsville, CA (SPK) 35-40 
Colonial Beach, MD (NAB) 4-9, 4-23, 4-30 
Colorado River at Grand Junction, CO (SPK) 35-44 
Colorado River at Riverside, CO (SPK) 35-44 
Colorado River, Matagorda, TX (SWG) 31-38 
Colorado Springs, Fountain que Bouille River, CO 
(Templeton Gap Floodway) (SWA) 32-19 
Colquitt County, GA (SAM) 10-56 
Columbia and Lower Willamette Rivers below 
Vancouver, WA and Portland, OR (NPP) 37-2, 
37-22, 37-29, 37-41 
Columbia and Snake Rivers Ports Dredging, OR and 
WA (NPP) 37-16, 37-26, 37-34 
Columbia Drainage and Levee District No. 3, IL 
(LSM) 14-16 
Columbia Drainage District No. 1, OR (NPP) 37-40 
Columbia, LA (LMK) 12-15, 12-18 
Columbia River and Tributaries above Celilo Falls to 
Kennewick, WA (NPW) 39-15 
Columbia River at Baker Bay, WA (NPP) 37-3, 
37-22, 37-30 
Columbia River at the Mouth, OR and WA (NPP) 
37-4, 37-22, 37-30 
Columbia River Basin, Local Flood Protection Projects 
(NPW) 39-1, 39-12 
Columbia River Basin, Local Protection Projects, ID, 
MT, and WA (NPS) 38-26, 38-30 
Columbia River between Chinook, WA and Head of 
Sand Island (NPP) 37-4, 37-22, 37-30 
Columbia River between The Dalles and Umatilla, OR 
(NPP) 37-41 
Columbia River between Vancouver, WA and The 
Dalles, OR (NPP) 37-4, 37-22, 37-30 
Columbia River, Illwaco, WA (NPP) 37-36 
Columbia River Juvenile Fish Mitigation Program 
(The Dalles, 37-26 Project), OR and WA (NPP) 
37-16, 37-34 
Columbia River Juvenile Fish Mitigation Program 
(Walla Walla District) (NPW) 39-3, 39-10, 39-13 
Columbia River, Seafarers Memorial, Hammond, OR 
(NPP) 37-5, 37-22, 37-30 
Columbia River, Vancouver, WA (NPP) 37-41 
Columbia River, Wenatchee to Kettle Falls, WA 
(NPS) 38-25 
Columbia Slough, OR (NPP) 37-40 
Columbus Flood Control Project, Lost Creek, 
Columbus, NE (MRO) 26-20 
Columbus, IN (ORL) 16-24 
Columbus, Loup River, NE (MRO) 26-20 
Columbus, MS (SAM) 10-56 
Columbus, OH (ORH) 17-22 
Colusa, CA (SPK) 35-40 
Commercial Port Road, Guam (POD) 36-12 
Compo Beach, Westport, CT (NED) 1-45 
Conant Brook Dam, MA (NED) 1-13, 1-29, 1-53 
Conchas Lake, NM (SWA) 32-3, 32-13 
Concordia, KY (ORL) 16-26, 16-30 
Conemaugh River Lake, Ohio River Basin, PA (ORP) 
18-6, 18-14, 18-19, 18-28 
Conesus Lake, Livonia, NY (NCB) 20-22, 20-38 
Conetoe Creek, NC (SAW) 6-28 
Coney Island Channel (NAN) 2-28, 2-29 
Coney Island Creek (NAN) 2-28, 2-29, 2-34 
Conklin-Kirkwood, NY (NAB) 4-35, 4-38 
Conneaut Harbor, OH (NCB) 20-4, 20-17, 20-29 
Conneaut Lake, PA (detalied project report underway) 
(ORP) 18-30 
Connecticut River (above Hartford), CT (NED) 1-49 
Connecticut River Basin Fish Passage Facilities for 
Townshend and Ball Mountain Lakes, West River, 
VT (NED) 1-14, 1-29, 1-39 
Connecticut River Basin, VT, NH, MA and CT 
(NED) 1-11 
Connecticut River below Hartford, CT (uncompleted 
portion) (NED) 1-49 
Connecticut River below Hartford, CT (NED) 1-4, 
1-26, 1-36, 1-58 
Connecticut River, Middletown, CT (NED) 1-13, 
1-29, 1-39 
Connecticut River, North Stratford, NH (NED) 1-46 
Connecticut River, W. Stewartstown, NH (NED) 1-46 
Connell, WA (NPW) 39-15 
Connellsville, PA (reconnaissance) (ORP) 18-30 
Connoquenessing Creek, Marion Township, PA 
(reconnaissance) (ORP) 18-30 
Connoquenessing Creek, Sewickley Township, PA 
(reconnaissance) (ORP) 18-30 
Conoho Creek, NC (SAW) 6-29 
1-14

Consolidated Diking and Improvement District 1, 
Cowlitz County, WA (NPP) 37-37 
Construction Engineering Research Laboratory 43-1 
Construction of Locks and Dams on Ohio River 
(ORD) 19-1, 19-5, 19-6, 18-2 
Construction of Locks and Dams on Ohio River 
(ORH) 17-2 
Construction of Locks and Dams, Ohio River (ORL) 
16-2, 16-28 
Contentnea Creek, NC (SAW) 6-26, 6-28, 6-29 
Continuation of Planning and Engineering 
Albuquerque District (SWA) 32-12 
Jacksonville District (SAJ) 9-24 
Mobile District (SAM) 10-32 
Savannah District (SAS) 8-10 
Conway County Drainage and Levee District No. 1, 
Arkansas River, AR (SWL) 28-22 
Conway County Levee District No. 6, Arkansas 
River, AR (SWL) 28-22 
Conway County Levee District Nos. 1, 2 and 8, 
Arkansas River, AR (SWL) 28-22 
Cook Inlet Shoals, AK (NPA) 40-11 
Cooper Lake and Channels, TX (SWF) 30-4, 30-15, 
30-19 
Cooper River, Charleston Harbor, SC (SAN) 7-4, 
7-10, 7-14 
Cooper River, NJ (NAP) 3-25 
Cooper River, Pompion Hill Chapel, SC (SAN) 7-19 
Cooper River Seismic Modification, SC (SAN) 7-4, 
7-10, 7-14 
Coos & Millicoma Rivers, OR (NPP) 37-36 
Coos Bay, OR (NPP) 37-5, 37-23, 37-30 
Coosa River, GA (SAM) 10-56 
Coosa River, Montgomery to Gadsden, AL (SAM) 
10-25, 10-37 
Coosawattee, Ellijay and Cartecay Rivers, Vicinity of 
Ellijay, GA (SAM) 10-56 
Copan Lake, OK (SWT) 29-4, 29-14, 29-21 
Copes Corner Lakes, NY (NAB) 4-36 
Coquille River, OR (NPP) 37-6, 37-23, 37-31, 37-40, 
37-41 
Coralville Lake, IA (NCR) 23-4, 23-10 
Coraopolis, PA (ORP) 18-24 
Corbin (Lynn Camp Creek), KY (ORN) 15-13, 15-18 
Cordele Creek & Malcolm Branch, GA (SAM) 10-56 
Cordell Hull Lock and Dam, TN (ORN) 15-14 
Cordova, AK (NPA) 40-13 
Cordova Harbor, AK (NPA) 40-2, 40-7, 40-9, 40-11 
Core Creek, NC (SAW) 6-28 
Corea Harbor, Gouldsboro, ME (NED) 1-41 
Corning-Monkey Run, NY (NAB) 4-38 
Corning, NY (NAB) 4-13, 4-25 
Cornucopia Harbor, WI (NCE) 21-8, 21-50, 21-70 
Corporation Gulch, Norfolk, NE (MRO) 26-23 
Corpus Christi Beach (Restoration Project), TX 
(SWG) 31-10, 31-20, 31-35 
Corpus Christi, Channel to Navy Seaplane Base 
Encinal, TX (SWG) 31-38 
Corpus Christi Channel, TX (SWG) 31-3, 31-19, 
31-24, 31-39, 31-40, 31-45 
Corsica River, MD (NAB) 4-32 
Corson Inlet and Ludlam Beach, NJ (NAP) 3-27 
Corte Madera Creek, CA (SPN) 34-14 
Corte Madre Creek, CA (SPK) 35-7, 35-28, 35-35 
Cortland, NY (NAB) 4-35, 4-38 
Cottage Grove Lake, OR (NPP) 37-11, 37-25, 37-33, 
37-43 
Cottonwood Creek, CA (SPK) 35-38 
Cottonwood Creek Dam, Boise, ID (NPW) 39-17 
Cottonwood Creek near Walker Lake Community, NV 
(SPK) 35-44, 39-15 
Cottonwood Slough pumping plant, IL (LMM) 13-6 
Cotuit Harbor, MA (NED) 1-49 
Cougar Lake, OR (NPP) 37-17, 37-26, 37-34, 37-43 
Council Bluffs, IA (Act of 1944) (MRO) 26-15 
Council Bluffs, IA (Act of 1936) (MRO) 26-15 
Council Bluffs, IA (MRO) 26-18, 26-20 
Council Grove Lake, KS (SWT) 29-5, 29-14, 29-21 
County Bridge, Elk River, Elk City, KS (SWT) 29-28 
County Bridge, Walnut River, Arkansas City, KS 
(SWT) 29-28 
County Line Road Bridge, Itawamba County, MS 
(SAM) 10-16, 10-35, 10-46 
County Road, (Sec. 2), Deer Creek, KS (SWT) 29-28 
County Road, (Sec. 6), Deer Creek, KS (SWT) 29-28 
County Road 55, Etowah County, AL (SAM) 10-51 
County Road, North Canadian River, OK (SWT) 
29-28 
County Road, Tyner Creek, Adair (SWT) 29-28 
County Road, Washita River, Caddo, OK 
County Road, Washita River, Caddo City, OK (SWT) 
29-28 
County Road, Washita River, Carter County, OK 
(SWT) 29-28 
Courtnay Channel, FL (SAJ) 9-49 
Cove Island, Stamford, CT (NED) 1-45 
I-15

Covered Bridge, Sheffield, MA (NED) 1-46 
Covington County, MS (SAM) 10-56 
Covington, KY (ORL) 16-23, 16-29, 16-34 
Cow Castle Creek, SC (SAN) 7-18 
Cow Castle, Orangeburg County, SC (SAN) 7-18 
Cow Creek, Comache, OK (SWT) 29-28 
Cow Creek, Hutchinson, KS (SWT) 29-25 
Cowanesque Lake, PA (NAB) 4-17, 4-26 
Cowlitz County Consolidate Diking Improvement 
District 1, OR (NPP) 37-40 
Cowlitz County Consolidated Diking Improvement 
District No. 2, WA (NPP) 37-38 
Cowlitz County Diking Improvement District 15, WA 
(NPP) 37-38 
Cowlitz County Diking Improvement District 13, WA 
(NPP) 37-38 
Cowlitz County Diking Improvement District 2, WA 
(NPP) 37-38 
Cowlitz County Drainage Improvement District 1, WA 
(NPP) 37-37 
Cowlitz River at Randle, WA (NPP) 37-40 
Cowlitz River, Hopkins Creek, WA (NPP) 37-38 
Cowlitz River, WA (NPP) 37-36 
Cowpens Swamp, SC (SAN) 7-18 
Cox Run, Wellsburg, WV (construction) (ORP) 18-30 
Cowskin Creek, Haysville, KS (SWT) 29-27 
Coyote and Berryessa Creeks, CA (SPL) 33-30 
Coyote and Spencer Creek, Long Tom River, OR 
(NPP) 37-40 
Coyote Creek (Known as Coyote and Berryessa 
Creeks), CA (SPK) 35-25, 35-34, 35-38 
Coyote Creek, CA (SPN) 34-14 
Coyote Valley Dam (Lake Mendocino) Channel 
Improvement below Dam on Lower 98 miles of 
Russian River, CA (SPK) 35-42, 35-43 
Crab and Wilson Creeks, WA (NPS) 38-30 
Crabtree Swamp, SC (SAN) 7-18 
Craig, AK (NPA) 40-13 
Craig Harbor, AK (NPA) 40-2, 40-7, 40-11 
Crane Creek Drainage and Levee District, IL (NCR) 
23-11, 23-14 
Crane Creek State Park, OH 1962 R&H Act (NCB) 
20-45 
Cranes Creek, VA (NAO) 5-3, 5-9, 5-13 
Crawford County Levee District, AR (SWL) 28-22 
Creede, Willow Creek, CO (Floodway) (SWA) 32-19 
Crescent City Harbor, CA (SPN) 34-7 
Cribbs Mill Creek, Tuscaloosa, AL (SAM) 10-16, 
10-35, 10-46 
Criehaven Harbor, ME (NED) 1-41 
Crisfield Harbor, MD (NAB) 4-32 
Crooked Creek, City Garage, Madison, IN (ORL) 
16-37 
Crooked Creek, J. Paul Park, Madison, IN (ORL) 
16-37 
Crooked Creek Lake and Levee, AR (SWL) 28-23 
Crooked Creek Lake, Ohio River Basin, PA (ORP) 
18-6, 18-14, 18-19, 18-28 
Crooked Creek, Union County, NC (SAW) 6-32 
Cross Creek, Fayetteville, NC (SAW) 6-32 
Cross Florida Barge Canal, (SAJ) 9-4, 9-27, 9-35, 
9-52, 9-53 
Cross Lake, NY (NCB) 20-43 
Cross Rip Shoals, Nantucket Sound, MA (NED) 1-41 
Cross Village, MI (NCE) 21-84 
Crow River, Rockford, MN (NCS) 24-30 
Crutcho Creek LPP, KS (SWT) 29-24, 29-29 
Crystal River, FL (SAJ) 9-49 
Cucamonga Creek, Santa Ana River Basin, CA (SPL) 
33-5, 33-13, 33-23 
Cuckold Creek, MD (NAB) 4-36 
Cuivre River, MO (LSM) 14-15 
Cumberland County Streams, NC (SAW) 6-32 
Cumberland, KY (ORN) 15-9 
Cumberland, MD and Ridgeley, WV (NAB) 4-10, 
4-23, 4-30, 4-38 
Cumberland River above Nashville, TN (ORN) 15-14 
Cumberland River, TN and KY (ORN) 15-2, 15-9, 
15-11, 15-15 
Cummings Park, Stamford, CT (NED) 1-45 
Cunninghill Cove, MD (NAB) 4-36 
Curiosity Creek, Tampa, FL (SAJ) 9-61 
Curia Creek Drainage District, Independence County, 
AR (SWL) 28-22 
Current River, AR and MO (SWL) 28-21 
Curry Creek Dam and Lake, GA (SAS) 8-19 
Curwensville Lake, PA (NAB) 4-18, 4-26 
Cushman-Mapleton Channels (Siuslaw River), OR 
(NPP) 37-36 
Cuttyhunk Harbor, MA (NED) 1-5, 1-26, 1-37 
Cuyahoga River, Akron Peninsula Road, OH (NCB) 
20-44 
Cuyahoga River at County Highway 10, OH (NCB) 
20-44 
Cuyahoga River Basin, OH (NCB) 20-42 
I-16

Cuyahoga River, Brecksville Road, OH (NCB) 20-44 
Cuyahoga River, Tinkers Creek, OH (NCB) 20-43 
Cuyahoga River, Valley View, OH (NCB) 20-43 
Cuyahoga River, West Creek, Independence, OH 
(NCB) 20-43 
Cypress Bayou and Waterway Between Jefferson, TX 
and Shreveport, LA (LMK) 12-16 
Cypress Bayou and Waterway between Jefferson, TX, 
and Shreveport, LA (LMN) 11-15 
Cypress Creek, McLean County, KY (ORL) 16-34 
Cypress Creek, MD (NAB) 4-32 
Cypress Creek, TX (SWG) 31-13, 31-21, 31-35 
Cyril E. King Road, St. Thomas, VI (SAJ) 9-61 
D 
Dade County, FL (SAJ) 9-21, 9-32, 9-45 
Dade County, North of Haulover Beach, FL (SAJ) 
9-22, 9-32, 9-45 
Dale County, AL (SAM) 10-56 
Dale Hollow Lake, Ohio River Basin, TN and KY 
(ORN) 15-6, 15-9, 15-17 
Dallas Floodway, TX (SWF) 30-22 
Dam "A" Lake, TX (SWF) 30-22 
Dam and Bridge, Neosho River, KS (SWT) 29-28 
Dam Safety Program (ORN) 15-7 
Damariscotta River, ME (NED) 1-41 
Dan River, Madison Wastewater Treatment Plan, NC 
(SAW) 6-28 
Dana Point, Harbor, CA (SPL) 33-28 
Danbury, CT (NED) 1-46, 1-55 
Dansville and Vicinity, Canaseraga Creek, NY (NCB) 
20-42 
Danvers River, Danvers, MA (NED) 1-51 
Danville, VA (SAW) 6-32 
Dardanelle Lock and Dam (No. 10), AR (SWL) 
28-11, 28-17 
Darien Harbor, GA (SAS) 8-18 
Dauphin Island, AL (SAM) 10-7, 10-33, 10-41, 10-52 
Davenport Center Lake, NY (NAB) 4-36 
Davenport, IA (NCR) 23-13 
David D. Terry Lock and Dam (No. 6), AR (SWL) 
28-3 
Davids Creek Lake, IA (MRO) 26-17 
Davis Creek, VA (NAO) 5-17, 5-19 
Davis, NC (SAW) 6-29 
Days Creek Lake, OR (Phase I) (NPP) 37-38 
Dayton, KY (ORL) 16-23, 16-29, 16-34 
Dayton, Touchet River, WA (NPW) 39-15 
Dayton, WY (MRO) 26-17 
Deadman's Gulch, Sturgis, SD (MRO) 26-15, 26-19 
Deadman's Run, NE (MRO) 26-23 
Dearborn River, Lewis-Clark County, MT (MRO) 
26-24 
Dearmenville and Golden Springs, AL (SAM) 10-56 
Decorah, (Dry Run), IA (NCS) 24-29 
Deefield River, Wilmington, VT (NED) 1-52 
Deep Creek, Accomack County, VA (NAO) 5-17, 
5-19 
Deep Creek, Edgecombe County, NC (SAW) 6-28 
Deep Creek, Newport News, VA (NAO) 5-17 
Deep River Area, Wahkiakum County, WA (NPP) 
37-37 
Deep River, WA (NPP) 37-36 
Deer Creek Lake, Ohio River Basin, OH (ORH) 17-3, 
17-12, 17-17 
Deer Creek, Prairie Levee, IN (ORL) 16-26, 16-30 
Deer Island Area, Columbia County, OR (NPP) 37-37 
Deer Island Drainage District, OR (NPP) 37-40 
Deer Island Thoroughfare, ME (NED) 1-41, 1-58 
Degognia and Fountain Bluff Levee and Drainage 
District, IL (LSM) 14-16 
DeGray Lake, AR (LMK) 12-18, 12-21 
DeKalb, IL (NCR) 23-14 
Delaware Bay to Lebanon Jetties and entrance at 
mouth (NAP) 3-25 
Delaware Coast Protection, DE (NAP) 3-12, 3-18, 
3-24 
Delaware Creek, Dallas, TX (SWF) 30-23 
Delaware Lake, Ohio River Basin, OH (ORH) 17-4, 
17-12, 17-17 
Delaware River between Philadelphia, PA and 
Trenton, NJ (NAP) 3-3, 3-16, 3-20 
Delaware River, PA, NJ and DE Philadelphia to the 
sea (NAP) 3-4, 3-16, 3-20 
Delaware River, Pennsville, NJ (NAP) 3-25 
Delaware River Vicinity of Camden, NJ (NAP) 3-5, 
3-16, 3-21 
Delphi, IN (Wabash River) (ORL) 16-23, 16-29, 
16-34 
Delware Bay to Millville, Millville fixed bridge to 
upper end of project (NAP) 3-25 
Delware River, Mouth of Neversink (NAP) 3-28 
Delware River to Wharf at Smyrna Landing (NAP) 
3-25 
Dennis Creek, NJ (NAP) 3-26 
1-17

Depoe Bay, Lincoln County, OR (NPP) 37-38 
Depoe Bay, OR (NPP) 37-6, 37-23, 37-31, 37-36 
DeQueen Lake, AR (SWL) 28-6, 28-15, 28-29 
Derby, CT (NED) 1-46, 1-55 
Derby, IN (ORL) 16-26, 16-30 
Des Lacs River, Burlington, ND (NCS) 24-30 
Des Moines and Mississippi Levee District No. 1, MO 
(NCR) 23-11 
Des Moines and Mississippi Levee District No. 1, MO 
(NCR) 23-14 
Des Moines, IA (NCR) 23-11, 23-14 
Des Moines Recreational River and Greenbelt, IA 
(NCR) 23-4, 23-7, 23-10 
Deschutes River, Bend, OR (NPP) 37-38 
Deschutes River, Rich Road Bridge, near East 
Olympia, WA (NPS) 38-26 
Detour Harbor, MI (NCE) 21-84 
Detroit Lake - Big Cliff, OR (NPP) 37-17, 37-26, 
37-34; 37-43 
Detroit River, MI (NCE) 21-8, 21-51, 21-71, 21-88 
Detroit River, Trenton Channel, MI (1950 R&H Act) 
(NCE) 21-86 
Detroit River, Trenton Channel, MI (1968 R&H Act) 
(NCE) 21-86 
Devil, East Twin and Warm Creeks Channel 
Improvements and Lytle Creek Levee (SPL) 
33-30 
Devils Lake, ND (NCS) 24-5, 24-18, 24-29, 24-30 
Dewey Lake, Ohio River Basin, KY (ORH) 17-4, 
17-13, 17-17 
Dice Grove, Lampasas River, Bell County, TX (SWF) 
30-23 
Dickey-Lincoln School Lakes, ME (NED) 1-49 
Dickinson Bayou, TX (SWG) 31-38 
Dierks Lake, AR (SWL) 28-6, 28-15, 28-29 
Diking and Improvement District 11, Cowlitz County, 
WA (NPP) 37-37 
Diking and Improvement District 4, Wahkiakum 
County, OR (NPP) 37-37 
Diking and Improvement District 5, Cowlitz County, 
WA (NPP) 37-37 
Diking District 1 and 3 (Puget Island) and Little 
Island, Wahkiakum County, WA (NPP) 37-37 
Diking District 2, Clatsop County, OR (NPP) 37-37 
Diking District 5, Catsop County, (NPP) 37-37 
Diking Improvement District 1, Pacific County, WA 
(NPP) 37-37 
Diking Improvement District 13, Cowlitz County, WA 
(NPP) 37-37 
Dillingham Harbor, AK (NPA) 40-2, 40-7, 40-9 
Dillon Lake, Ohio River Basin, OH (ORH) 17-4, 
17-13, 17-17 
Dillonvale, OH (Short Creek) (ORP) 18-24 
Dismal Swamp Canal (Canal Creek), VA (NAO) 5-16 
Dismal Swamp Canal (South Mills), NC (NAO) 5-16 
District of Columbia & MD Projects (NAB) 4-39 
Dively Drainage and Levee District, IL (LSM) 14-16 
Dixie Creek, GA (SAM) 10-56 
Dodge City, KS (SWT) 29-27 
Doe & Watanga River, Elizabethtown, TN (ORN) 
15-18 
Dog and Fowl Rivers, AL (SAM) 10-8, 10-34, 10-42 
Doheny Beach State Park, CA (SPL) 33-29 
Domonakas Library, Sheffield, OH (NCB) 20-44 
Dorchester Bay and Neponset River, MA 
(uncompleted portion) (NED) 1-49 
Dorchester Bay and Neponset River, MA (NED) 1-41 
Dorena Lake, OR (NPP) 37-11, 37-25, 37-33, 37-43 
Double Bayou, TX (SWG) 31-38 
Double Creek, NJ (NAP) 3-25 
Douglas Harbor, AK (NPA) 40-11 
Dover, KY (ORH) 17-22 
Downers Run, Fayette City, PA (terminated) (ORP) 
18-30 
Downyville Lake, IN (Wabash River) (ORL) 16-24, 
16-33 
Drainage District 1, Clatsop County, OR (NPP) 37-37 
Drainage District No. 13, IA (NCR) 23-12, 23-15 
Drakes Island Beach, Wells, ME (NED) 1-51 
Drinkwater Sewer, MO (LMM) 13-6 
Drum Inlet, NC (SAW) 6-5, 6-19 
Drury Drainage District, IL (NCR) 23-11, 23-14 
Dry Branch Creek, Grand Prairie, TX (SWF) 30-23 
Dry Creek (Warm Springs) Lake and Channel 
Improvements, CA (SPK) 35-30, 35-42, 35-43 
Dry Creek, Goodlettsbille, TN (ORN) 15-18 
Dry Creek, Hawarden, IA (MRO) 26-15, 26-20 
Dry Creek, WA (NPW) 39-15 
Dry Fork and East Fork Lakes, Fishing River, MO 
(MRK) 27-18 
Dry Pass, AK (NPA) 40-11 
Dry Pass Channel, AK (NPA) 40-13 
Dry Run, IA (NCS) 24-24 
DuBois, PA (ORP) 18-22, 18-29 
Dubuque Harbor, IA 25-7 
1-18

Dubuuqe, IA (NCR) 23-11, 23-14 
Duck Creek Channel Improvement, TX (SWF) 30-22 
Duck Creek, Elwood, IN (ORL) 16-37 
Duck Creek, Garland, TX (SWF) 30-23 
Duck Creek, San Joaquin County, CA (SPK) 35-38 
Duck Creek, Scott County, Davenport, and 
Bettendorf, IA (NCR) 23-15 
Duck Island Harbor, CT (NED) 1-41 
Duck Island Water Refuge, Lake Barkley, KY (ORN) 
15-18 
Duck Point Cove, MD (NAB) 4-32 
Duck River, TN (ORN) 15-13, 15-18 
Duluth-Superior Harbor, MN and WI (NCE) 21-9, 
21-51, 21-71 
Duluth-Superior Inner Harbor, MN (1960 R&H Act) 
(NCE) 21-86 
Duncan Creek, Bloomer, WI (NCS) 24-30 
Dungeness River, Area #5, WA (NPS) 38-26 
Dungeness River, Area #8, WA (NPS) 38-26 
Dungeness River, Clallam County, WA (NPS) 38-26 
Dungeness River, Taylor Cut-off Road, WA (NPS) 
38-26 
Dunkirk Harbor, NY (NCB) 20-5, 20-17, 20-29 
Dunkirk Harbor, NY WRDA 1986 (NCB) 20-45 
Dunn Branch, Woodbine, Camden (SAS) 8-19 
Duval County, FL (SAJ) 9-17, 9-31, 9-46 
Duxbury Harbor, MA (NED) 1-41 
Dworshak Dam and Reservoir, ID (NPW) 39-4, 
39-10, 39-13, 39-18 
Dworshak Units 5 and 6, ID (NPW) 39-17 
Dyersburg, TN (LMM) 13-6 
Dymers Creek, VA (NAO) 5-17 
E 
Eagle Creek Lake, KY (ORL) 16-24 
Eagle Creek Reservoir, OH (ORP) 18-24 
Eagle Creek, SC (SAN) 7-18, 7-18 
Eagle Harbor, MI (NCE) 21-84 
East Agana, Guam (POD) 36-12 
East Barre Dam, Winooski River, VT (NAN) 2-32 
East Bay (Hanna Reef), TX (SWG) 31-38 
East Bay Small Boat Basin, Olympia, WA (NPS) 
38-25 
East Boothbay Harbor, ME (NED) 1-41 
East Bow Creek, Cedar County Bridge, WY (MRO) 
26-24 
East Branch, Clarion River Lake, Ohio River Basin, 
(ORP) 18-6, 18-14, 18-19, 18-28 
East Branch Dam, CT (NED) 1-46 
East Brimfield Lake, MA (NED) 1-21, 1-32, 1-57 
East Cap Girardeau and Clear Creek Drainage and 
Levee District, IL (LSM) 14-18 
East Chester Creek, NY (NAN) 2-3, 2-18, 2-22, 2-28, 
2-34 
East Fork, Deer Creek, Slaughters, KY (ORL) 16-37 
East Fork of Boyer River, Near Vail, IA (MRO) 
26-21 
East Fork of Clarks River, KY (ORN) 15-18 
East Fork, TX (SWF) 30-22 
East Fork White River, Brownstown (Jackson 
County), IN (ORL) 16-35 
East Harbor State Park, OH (NCB) 20-43 
East Hartford, CT (NED) 1-46, 1-54 
East Liverpool Drainage and Levee District, IL (NCR) 
23-11, 23-14 
East Lynn Lake, Ohio River Basin, WV (ORH) 17-5, 
17-13, 17-18 
East Moline, IL (NCR) 23-12, 23-14 
East Muddy and Lake Creek, OR (NPP) 37-40 
East Muddy Creek, MO (MRK) 27-17 
East Nishnabotna River at Red Oak, IA (MRO) 26-15 
East Nishnabotna River, Near Griswold, IA (MRO) 
26-21 
East Nishnabotna River, Page Bny Brdg., IA (MRO) 
26-23 
East Nishnabotna River, Page County Bridge, Near 
Essex, IA (MRO) 26-21 
East Nishnabotna River, Red Oak, IA (MRO) 26-21 
East Pass Channel from Gulf of Mexico into 
Choctawhatchee Bay, FL (SAM) 10-8, 10-34, 
10-42 
East Peoria Drainage and Levee District, (NCR) 
23-12, 23-14 
East Peoria, IL (NCR) 23-15 
East Peoria Sanitary District, IL (NCR) 23-14 
East Point, LA (LMK) 12-21 
East Poplar Bluff and Poplar Bluff, MO (SWL) 28-22 
East Rainelle, WV (ORH) 17-21, 17-24 
East River (NAN) 2-28, 2-29, 
East River, Wareham, MA (NED) 1-51 
East Rockaway Inlet, NY (NAN) 2-4, 2-18, 2-22, 
2-28, 2-34 
East Rockaway Inlet to Rockaway Inlet and Jamaica 
Bay, NY 2-31, 2-34 
I-19

East Sidney Lake, NY (NAB) 4-14, 4-25 
East St. Louis and Vicinity, IL (LSM) 14-4, 14-9, 
14-12 
East Weaver Creek, CA (SPK) 35-38 
East Weaver Creek, CA (SPN) 34-14 
Eastlake, Chagrin River, OH 1965 FC Act (NCB) 
20-45 
Eastpoint Channel, FL (SAM) 10-51 
Eastport Harbor, ME (NED) 1-49 
Eau Galle River, WI (NCS) 24-5, 24-18 
Eau Gallie Harbor, FL (SAJ) 9-4, 9-27, 9-35, 9-51 
Echo Bay Harbor, NY (NAN) 2-29 
Edenton Harbor, NC (SAW) 6-26 
Edgartown Harbor, MA (NED) 1-41 
Edgartown Harbor, MA (uncompleted portion) (NED) 
1-49 
Edgewater Park, OH 1954 R&H Act (NCB) 20-45 
Edisto River, North Fork, SC (SAN) 7-18 
Edisto River, SC (SAN) 7-17, 7-18 
Edisto River, Vicinity Canadays Landing, SC (SAN) 
7-18 
Ediz Hook, WA (NPS) 38-2, 38-14, 38-20 
Edmonds Harbor, WA (NPS) 38-25 
Edward MacDowell Lake, NH (NED) 1-19, 1-31, 
1-56 
Eel River at Sandy Prairie, CA (SPN) 34-14 
Eel River, Brazil Waterworks, IN (ORL) 16-34 
Eel River, CA (SPK) 35-40 
Egegik River, AK (NPA) 40-11 
Eight Mile Creek, Richland County, SC (SAN) 7-18 
Eighteen Mile Island, Oldham County, KY (ORL) 
16-35 
Eire Harbor, PA 1899 R&H Act (NCB) 20-45 
El Dorado Lake, KS (SWT) 29-5, 29-14, 29-21 
El Dorado, West Branch, Walnut River, KS (SWT) 
29-25 
El Paso, TX (SWA) 32-3, 32-13, 32-16 
El Turque Beach, Ponce, PR (SAJ) 9-50 
Elder and Unionhouse Creeks, CA (SPK) 35-44 
Eldred and Spankey Drainage and Levee District, IL 
(LSM) 14-12 
Eldred, IL (LSM) 14-18 
Eldred, PA (ORP) 18-29 
Elfin Cove, AK (NPA) 40-11, 40-13 
Elizabeth, NJ (NAN) 2-32, 2-34, 2-35 
Elizabethtown, IL (ORL) 16-26, 16-30 
Elk and Little Elk Rivers, MD (NAB) 4-32 
Elk City Lake (Table Mound), KS (SWL) 28-28 
Elk City Lake, KS (SWT) 29-5, 29-14, 29-21, 29-26 
Elk Creek, Clyde, KS (MRK) 27-17 
Elk Creek Harbor, PA 1966 R&H Act (NCB) 20-45 
Elk Creek, Jackson, NE (MRO) 26-20 
Elk Creek Lake, Rogue River Basin, OR (NPP) 37-11, 
37-25, 37-33 
Elk Creek, Willis, NE (MRO) 26-20 
Elk River, AL and TN (ORN) 15-1318 
Elk River, MN (NCS) 24-24, 24-29, 24-30 
Elk River, WV (ORH) 17-20 
Elkhorn River, Beemer, NE Bridge (MRO) 26-24 
Elkhorn River Bridge, Norfolk, NE (MRO) 26-20 
Elkhorn River, Ewing, Holt County, NE (MRO) 
26-20 
Elkhorn River, Near Beemer, NE (MRO) 26-20 
Elkhorn River, Q Street Bridge, Near Gretna, NE 
(MRO) 26-20 
Elkhorn River, Ray Bridge, Near Norfolk, NE (MRO) 
26-20 
Elkins, WV (ORP) 18-4, 18-13, 18-18, 18-22 
Elkland, PA (NAB) 4-35, 4-38 
Elkport, IA (NCR) 23-12, 23-14 
Ellerbe Creek, Durham County, NC (SAW) 6-28 
Ellicott Creek, NY (NCB) 20-12, 20-22, 20-38 
Ellis Swamp, Gates County, NC (SAW) 6-28 
Elm Creek, Burt County, NE (MRO) 26-20 
Elm Creek, Decatur, NE (MRO) 26-20 
Elm Fork Floodway, TX (SWF) 30-22 
Elmira, NY (NAB) 4-14, 4-25 
Elochoman Slough, WA (NPP) 37-41 
Elochoman Slough, WA (NPP) 37-36 
Elvis Stahr Harbor, KY (LMM) 13-5 
Elwha Klallam Reservation, Elwha River, WA (NPS) 
38-26 
Elwha River, Clallam County, WA (NPS) 38-26 
Emergency Bank Protection 
Philadelphia District (NAP) 3-12 
Emergency Bank Protection for Certain Highway and 
Railroad Facilities at Price Landing, MO (LSM) 
14-16 
Emergency Flood Control Activities 
Norfolk District (NAO) 5-8, 5-11 
Tulsa District (SWT) 29-10 
Emergency Protection for Certain Highway and 
Railroad Facilities at Chester, IL (LSM) 14-16 
Emergency Protection for Illinois Approach, Chain of 
Rocks Bridge, IL (LSM) 14-16 
I-20

Emergency Repairs to Levees on Mississippi, Illinois, 
and Kaskaskia Rivers and Flood Fighting and 
Rescue Work (LSM) 14-16 
Emergency Shore Protection 
Detroit District (NCE) 21-38 
Emergency Streambank and Shoreline Protection 
Under Special Authorization 
Charleston District (SAN) 7-9 
Galveston District (SWG) 31-16 
New York District (NAN) 2-17 
Savannah District (SAS) 8-7 
Emerson, Manitoba-Noyes, MN (NCS) 24-6, 24-18, 
24-29, 24-30 
Emmett Sanders Lock and Dam (No. 4) (SWL) 28-3 
Emory River, Harriman, TN (ORN) 15-18 
Empire-Stratton, OH (ORP) 18-24 
Enderline, Maple River, ND (NCS) 24-24 
Endicott Johnson City and Vestal, NY (NAB) 4-35, 
4-38 
Engineer Topographic Laboratories 46-1 
England Pond Levee, IL (Wabash River) (ORL) 
16-23, 16-29, 16-34 
English, IN (Little Blue River) (ORL) 16-23, 16-34 
Enid Diversion Channel, OK (SWT) 29-27 
Enid LPP, OK (SWT) 29-24 
Entiat River, Chelan County, WA (NPS) 38-26 
Entiat River, WA (NPS) 38-30 
Entiat River, WA (NPS) 38-26 
Erie Harbor, PA (NCB) 20-5, 20-17, 20-30 
Erie Harbor, PA 1945 R&H Act (NCB) 20-45 
Erie Harbor, PA 1960 R&H Act (NCB) 20-45 
Escambia Bay, FL (SAM) 10-52 
Escambia-Conecuh Rivers, AL and FL (SAM) 10-49 
Eslava Creek, Mobile, AL (SAM) 10-16, 10-35, 10-46 
Esquatzel Coulee, Connell, WA (NPW) 39-15, 39-16 
Essex River, MA (NED) 1-41 
Estate Mon Bijou, St. Croix, VI (SAJ) 9-61 
Etna, PA (ORP) 18-29 
Euclid Creek, OH (NCB) 20-22, 20-38 
Eufaula Lake, OK, (SWL) 28-28 
Eufaula Lake, OK (SWT) 29-11, 29-19, 29-22, 29-26 
Evansdale, IA (NCR) 23-14 
Evanston, IL (NCC) 22-20 
Evansville, IN (ORL) 16-3, 16-14, 16-29, 16-34 
Everett Harbor and Snohomish River, WA (NPS) 
38-3, 38-14, 38-20, 38-30 
Everett Harbor, WA (NPS) 38-31 
Everglades Harbor, FL (SAJ) 9-49 
Exeter River, NH (NED) 1-41 
Existing leveees and extensions thereto from Bastrop, 
LA to mouth of Boeuf River and at West Monroe. 
LA (LMK) 12-18 
F 
Fabius River Drainage District, MO (NCR) 23-12, 
23-14 
Fair Grounds Park, Clarksville, TN (ORN) 15-18 
Fairbanks, Tanana River & Chena Slough, AK (NPA) 
40-12 
Fairbury, Little Blue River, NE (MRK) 27-17 
Fairfield Vicinity Streams, CA (SPK) 35-8, 35-28 
Fairhaven Beach State Park, NY 1958 R&H Act 
(NCB) 20-45 
Fairport Harbor, OH (NCB) 20-5, 20-17, 20-30 
Fajardo Harbor, PR (SAJ) 9-49 
Falcon/Little Eagle Creeks, IN (ORL) 16-37 
Falfurrias, TX (SWG) 31-13, 31-21, 31-36 
Fall Brook Lake, PA (NAB) 4-36 
Fall Creek Lake, OR (NPP) 37-12, 37-25, 37-33, 
37-43 
Fall River Basin, SD (MRO) 26-3, 26-9, 26-12 
Fall River Harbor, MA (NED) 1-41 
Fall River Harbor, MA (uncompleted portion) (NED) 
1-49 
Fall River Lake, KS, (SWL) 28-28 
Fall River Lake, KS (SWT) 29-5, 29-15, 29-21, 29-26 
Falls Lake, NC (SAW) 6-12, 6-21 
Falmouth Harbor, MA (NED) 1-41 
Falmouth Lake, KY (Licking River) (ORL) 16-24, 
16-32 
Far Creek, NC (SAW) 6-5, 6-19 
Fargo, ND (NCS) 24-29 
Farm Creek, IL (NCR) 23-4, 23-7, 23-10 
Farmers Branch, White Settlement, TX (SWF) 30-23 
Farmers Drainage and Levee District (Sangamon 
River), IL (NCR) 23-13 
Farmers Levee and Drainage District, IL (NCR) 
23-12, 23-14 
Farmington, Des Moines River, IA (NCR) 23-16 
Farmington River, Simsbury, CT (NED) 1-14, 1-29, 
1-39 
Faulkner County Levee District No. 1, Arkansas 
River, AR (SWL) 28-22 
Felsenthal, AR (LMK) 12-15, 12-16 
Ferguson Creek, Long Tom River, OR (NPP) 37-40 
1-21

Fern Ridge Lake, Long Tom River, OR (NPP) 37-42 
Fern Ridge Lake, OR (NPP) 37-13, 37-25, 37-33, 
37-43 
Fernandina Harbor, FL (SAJ) 9-5, 9-27, 9-35 
Ferrells Bridge Dam-Lake O' The Pines, TX (SWF) 
30-6, 30-15, 30-19 
Filberts Creek, NC (SAW) 6-28 
Finney Creek at Wachapreague, VA (NAO) 5-17 
Fire Island Inlet (NAN) 2-28, 2-29 
Fire Island to Jones Inlet, NY (NAN) 2-4, 2-18, 2-22, 
2-31 
Fire Island to Montauk Point, NY (NAN) 2-32 
Fisher Creek, Tulsa County, OK (SWT) 29-28 
Fisherman's Wharf Areas, San Francisco Harbor, CA 
(SPN) 34-7 
Fishing Bay, MD (NAB) 4-32 
Fishing Creek, MD (NAB) 4-32 
Fishing Creek, NC (SAW) 6-26 
Fishing Creek, Pine Grove, WV (ORH) 17-24 
Fishpond Drain and Tributaries, GA (SAM) 10-56 
Fishtrap Lake, Ohio River Basin, KY (ORH) 17-5, 
17-13, 17-18 
Fitchburg, MA (See No. Nashua River) (NED) 1-46 
Fivemile River Harbor, CT (NED) 1-41 
Fivemile River Harbor, CT (uncompleted portion) 
(NED) 1-49 
Flat Branch, Gulfport, MS (SAM) 10-51 
Flat Rock and Valley View Creeks LPP, Tulsa, OK 
(SWT) 29-24, 29-27 
Flathead River, Bradley Channel Area, MT (NPS) 
38-26 
Flathead River, MT (NPS) 38-25, 38-26 
Flathead River, near Kalispell, MT (NPS) 38-26, 
38-31 
Flathead River, Old Steel Bridge, near Kalispell, MT 
(NPS) 38-26 
Fletcher & Sunshine Gardens Levee, IN (ORL) 16-26, 
16-30 
Fletcher Creek at Memphis, TN (LMM) 13-1, 13-4 
Flood Control and Coastal Emergencies 
Mobile District (SAM) 10-31 
Flood Control Projects Under Construction B-1 
Flood Control Reservoir Operations 
New England Division (NED) 1-23 
Flood Control Reservoirs Operable A-1 
Flood Control Work Under Special Authorization 
Alaska District (NPA) 40-5 
Albuquerque District (SWA) 32-11 
Baltimore District (NAB) 4-19 
Buffalo District (NCB) 20-13 
Charleston District (SAN) 7-9 
Chicago District (NCC) 22-11 
Detroit District (NCE) 21-41 
Galveston District (SWG) 31-16 
Huntington District (ORH) 17-11 
Jacksonville District (SAJ) 9-24 
Kansas City District) (MRK) 27-7 
Little Rock District (SWL) 28-6 
Los Angeles District (SPL) 33-8 
Louisville District (ORL) 16-13 
Memphis District (LMM) 13-2 
Mobile District (SAM) 10-23 
Nashville District (ORN) 15-6 
New England Division (NED) 1-24 
New Orleans District (LMN) 11-9 
New York District (NAN) 2-17 
Omaha District (MRO) 26-6 
Pacific Ocean Division (POD) 36-3 
Philadelphia District (NAP) 3-12 
Pittsburgh District (ORP) 18-11 
Portland District (NPP) 37-13 
Rock Island District (NCR) 23-6 
Sacramento District (SPK) 35-23 
San Francisco District (SPN) 34-5 
Savannah District (SAS) 8-7 
Seattle District (NPS) 38-8 
St. Louis District (LSM) 14-7 
Tulsa District (SWT) 29-10 
Vicksburg District (LMK) 12-9 
Walla Walla District (NPW) 39-2 
Wilmington District (SAW) 6-15 
Flood Damages Sustained and Prevented G-1 
Floodwall and Levees at Portland, OR (NPP) 37-40 
Florence LPP, KS (SWT) 29-24, 29-27 
Flower and Parmenter Creeks, MT (NPS) 38-26 
Floyd County, GA (SAM) 10-56 
Floyd River, Sioux City, IA (MRO) 26-15, 26-20 
Flushing Bay and Creek, NY (NAN) 2-5, 2-18, 2-22, 
2-28 
Fly Creek, Fairhope, AL (SAM) 10-9, 10-34, 10-42, 
10-52 
Follansbee, WV (ORP) 18-24 
Folly Beach, SC (SAN) 7-8, 7-12, 7-16 
Folly Brook, Wethersfield, CT (NED) 1-46, 1-54 
Folly River, SC (SAN) 7-4, 7-11, 7-14 
Folsom Lake, American River, CA (SPK) 35-38 
I-22

Forest Heights, MD (NAB) 4-35, 4-38 
Forestville Harbor, MI (1968 R&H Act) (NCE) 21-86 
Forked Deer River, TN, including South Fork (LMM) 
13-5 
Forsyth, MT (MRO) 26-15 
Fort Chartres and Ivy Landing Drainage District No. 
5, IL (LSM) 14-16 
Fort Chartres and Ivy Landing Drainage District No. 
5, and Stringtown Drainage and Levee District 
No. 4, IL (LSM) 14-18 
Fort Fisher and Vicinity, NC (SAW) 6-27 
Fort Gaines, Dauphin Island, AL (SAM) 10-51 
Fort Gibson Lake, OK (SWL) 28-28 
Fort Gibson Lake, OK (SWT) 29-11, 29-19, 29-23, 
29-26 
Fort Kent, ME (NED) 1-46 
Fort Leavenworth Bridge Removal (MRK) 27-16 
Fort Lupton, CO (Lagoon) (MRO) 26-23 
Fort Macon Park, NC (SAW) 6-27 
Fort Macon State Park, NC Remaining Work (SAW) 
6-29 
Fort Madison Harbor, IA 25-7 
Fort Myers Beach, FL (SAJ) 9-5, 9-27, 9-35, 9-51 
Fort Niagara State Park, NY Sec. 201 1965 FC Act 
(NCB) 20-45 
Fort Peck Lake, MT (MRO) 26-6, 26-11, 26-14, 
26-18 
Fort Pierce Harbor, FL (SAJ) 9-5, 9-27, 9-36 
Fort Randall Dam-Lake Francis Case, Missouri River 
Basin, SD (MRO) 26-6, 26-11, 26-14, 26-18 
Fort Scott Lake Marmaton River, KS (MRK) 27-17, 
27-20 
Fort Smith, Arkansas River, AR (SWL) 28-22 
Fort Supply Lake, OK (SWT) 29-5, 29-15, 29-21 
Fort Toulouse, Wetumpka, AL (SAM) 10-17, 10-35, 
10-46 
Fort Worth Floodway (Clear Fork), TX (SWF) 30-22 
Fort Worth Floodway (West Fork), TX (SWF) 30-22 
Fortuna Bay, St. Thomas, VI (SAJ) 9-61 
Foster Creek Road, Douglas County, WA (NPS) 
38-26 
Foster Creek, West Fork, WA (NPS) 38-26 
Foster Joseph Sayers Dam, PA (NAB) 4-19, 4-26 
Fosters Loop Road, Tuscaloosa County, AL (SAM) 
10-51 
Fountain Creek, Pueblo, CO (SWA) 32-4, 32-13, 
32-16 
Four Holes Swamp, Orangeburg County, SC (SAN) 
7-18 
Four River Basins, FL (SAJ) 9-22, 9-32, 9-48, 9-60, 
9-61 
Fource Bayou Basin, Little Rock, AR (SWL) 28-6, 
28-15 
Fourche Creek, Little Rock, AR (SWL) 28-22 
Fourmile Creek, Des Moines, IA (NCR) 23-15 
Fourmile Run, VA (NAB) 4-35, 4-39 
Fourpole Creek, WV (ORH) 17-24 
Fowl River, AL (SAM) 10-52 
Fox Point Barrier, RI (NED) 1-46 
Fox River, Bridge Site #4, Davis County, IA (NCR) 
23-16 
Fox River, Bridge Site #7, Davis County, IA (NCR) 
23-16 
Fox River Locks and Dams (NCE) 21-89 
Fox River, Route J40 Bridge, Davis County, IA 
(NCR) 23-16 
Fox River, WI (NCE) 21-10, 21-51, 21-72 
Foxholm, ND (NCS) 24-30 
Francis E. Walter Dam, PA (NAP) 3-12, 3-18, 3-24 
Frankfort, Black Vermillion River, KS (MRK) 27-17 
Frankfort Harbor, MI (NCE) 21-11, 21-51, 21-72 
Frankfort, KY (Benson Creek)(Kentucky River) (ORL) 
16-24, 16-29 
Frankfort, KY (North Frankfort)(Kentucky River) 
(ORL) 16-23, 16-29, 16-34 
Frankfort, KY (South Frankfort)(Kentucky River) 
(ORL) 16-24, 16-29 
Franklin Falls Dam, NH (NED) 1-19, 1-32, 1-56 
Frazer-Wolf Point, MT (MRO) 26-15 
Frazeysburg, OH (ORH) 17-23 
Freeport and Vicinity, Hurricane Flood Protection, TX 
(SWG) 31-38 
Freeport Harbor, TX (SWG) 31-3, 31-19, 31-26, 
31-39, 31-40, 31-45 
Freeport, IL (NCR) 23-13 
Freeport, PA (Allegheny River) (ORP) 18-24 
Fremont, OH, Sandusky River (NCB) 20-42 
French Broad and Little Pigeon Rivers, TN (ORN) 
15-13 
French Creek, Wattsburg, PA (detalied project report 
underway) (ORP) 18-30 
Frenchboro Harbor, ME (NED) 1-41 
Freshwater Bayou, LA (LMN) 11-15 
Friday Harbor, WA (NPS) 38-3, 38-14, 38-20 
Friendly, WV (ORH) 17-22 
I-23

Friendsville, MD (ORP) 18-22, 18-29 
From North Little Rock to Gillett (Above Plum 
Bayou), AR (SWL) 28-22 
Fry Creeks, Bixby, OK (SWT) 29-30 
Ft. Clinch State Park, Nassau County, FL (SAJ) 9-61 
Ft. Collins, CO (MRO) 26-21 
Fullerton, KY (ORH) 17-22 
Fulton County, GA (SAM) 10-56 
Fulton, IL (NCR) 23-12, 23-14 
G 
Galax, VA (ORH) 17-21, 17-24 
Galena, IL (NCR) 23-12, 23-14 
Galisteo Dam, NM (SWA) 32-6, 32-14, 32-18 
Gallatin River, Gallatin County, MT (MRO) 26-23 
Gallipolis, OH (ORH) 17-22 
Galveston Harbor and Channel, TX (SWG) 31-4, 
31-19, 31-27, 31-39, 31-41 
Ganargua Creek, Plasermill Road, NY (NCB) 20-44 
Gapway Swamp, NC and SC (SAW) 6-28 
Gapway Swamp, SC (SAN) 7-18 
Gardner, MA (NED) 1-46, 1-54 
Gardners Creek, NC (SAW) 6-28 
Garland City, AR (LMK) 12-19, 12-21 
Garnett Lake, Pottawatomie Creek, KS (MRK) 27-18, 
27-20 
Garrison Dam-Lake Sakakawea, Missouri River Basin, 
ND (MRO) 26-7, 26-11, 26-14, 26-18 
Garvin Brook, Stockton, MN (NCS) 24-30 
Gasconade River, MO (MRK) 27-16 
Gastineau Channel, AK (NPA) 40-11 
Gate Creek Lake, OR (NPP) 37-38, 37-40 
Gathright Dam and Lake Moomaw, VA (NAO) 5-8, 
5-11, 5-15 
Gauley River, WV (ORH) 17-20 
Gavins Point Dam-Lewis and Clark Lake, Missouri 
River Basin, NE and SD (MRO) 26-7, 26-11, 
26-14, 26-17, 26-18 
Gaysville Lake, VT (NED) 1-49 
Genegantslet Lake, NY (NAB) 4-36 
General Edgar Jadwin Dam and Reservoir, PA (NAP) 
3-13, 3-18, 3-24 
Genesee River, Back River Road, Amity, NY (NCB) 
20-44 
Geneva-on-the-Lake, OH (NCB) 20-40 
Genoa Sewer Facility, Wayne County, NC (SAW) 
6-28 
George W. Andrews Lock and Dam, AL & GA 
(SAM) 10-28, 10-37, 10-48 
Georges River, ME (NED) 1-41 
Georgetown Harbor, SC (SAN) 7-5, 7-11, 7-15 
Gering Valley, Gering Drain and Tributaries, NE 
(MRO) 26-20 
Gering Valley, NE (MRO) 26-15 
Gibson Creek, TN (ORN) 15-18 
Gila and Salt Rivers Levee and Channel Improvements 
(SPL) 33-30 
Gila River Basin, AZ (SPL) 33-5, 33-30 
Giles Creek, Elkhorn, NE (MRO) 26-17 
Gill Township Levee, IN (Wabash River) (ORL) 
16-23, 16-34 
Gillham Lake, AR (SWL) 28-7, 28-15, 28-29 
Gills Creek Above Lake Catherine, Richland County, 
SC, 7-18 
Gills Creek Below Lake Catherine, Richland County, 
SC, 7-18 
Gilmore Creek, Winona, MN (NCS) 24-30 
Girty's Run, Millvale, PA (ORP) 18-22 
Glade Creek, Roanoke County and Vinton, VA (SAW) 
6-32 
Glasgow, MT (MRO) 26-15, 26-18 
Gleason Creek, NV (SPK) 35-40 
Glen Cove Creek, NY (NAN) 2-29 
Glen Cove Harbor, NY (NAN) 2-34 
Gloucester Harbor and Annisquam River, MA (NED) 
1-41 
Golconda, IL (ORL) 16-23, 16-29, 16-34 
Gold Creek, AK (NPA) 40-12 
Goldsboro, Neuse River, NC (SAW) 6-28 
Goleta, CA and Vicinity (SPL) 33-30 
Goodfood Creek, Chickasaw County, MS (SAM) 
10-50 
Gooding Area, ID(NPW) 39-16 
Goose Creek, Boulder, CO (MRO) 26-21 
Goose Creek, MD (NAB) 4-32 
Gordon Creek, Iowa Park, TX (SWT) 29-27 
Gordon's Landing, VT (NAN) 2-29 
Gordons Creek, Hattiesburg, MS (SAM) 10-50, 10-51 
Goshen Creek, NJ (NAP) 3-26 
Governors Run, MD (NAB) 4-36 
Gowanas Creek Channel, NY (NAN) 2-29 
Grafton, ND (NCS) 24-26, 24-29 
Grafton Pumping Station, ND (NCS) 24-24 
Grafton Small Boat Harbor, IL (LSM) 14-18 
Grahn, KY (ORH) 17-24 
I-24

Grand Bayou Pass, LA (LMN) 11-15 
Grand Haven Harbor and Grand River, MI (NCE) 
21-11, 21-52, 21-72 
Grand Haven Harbor, MI (1945 R&H Act) (NCE) 
21-86 
Grand Isle and Vicinity, LA (LMN) 11-4, 11-10, 
11-13 
Grand Lake O' the Cherokees (SWT) 29-26 
Grand Marais Harbor, MI (NCE) 21-13, 21-52, 21-73 
Grand Marais Harbor, MN (NCE) 21-13, 21-52, 
21-73 
Grand Mound-State Historical Site, MN (NCS) 24-6, 
24-18, 24-29, 24-30 
Grand Neosho River Basin, KS and OK (SWT) 29-29 
Grand Prairie (Landfill), TX (SWF) 30-22 
Grand Prairie (Meyers Road), TX (SWF) 30-22 
Grand River at Grandville, MI (1965 Flood Control 
Act) (NCE) 21-86 
Grand Ronde Valley, OR (NPW) 39-17 
Grand Tower Drainage and Levee District, IL (LSM) 
14-16 
Grand Traverse Bay Harbor, MI (NCE) 21-13, 21-53, 
21-73 
Grande Ronde Lake, OR (NPW) 39-17 
Grandview Bay Harbor, NY 1945 R&H Act (NCB) 
20-45 
Grandview, IN (ORL) 16-26, 16-30 
Grant Parish, Below Colfax, LA (LMK) 12-20, 12-21 
Granville, PA (ORP) 18-22, 18-29 
Grapevine Lake, TX (SWF) 30-6, 30-15, 30-19 
Grasse River (Massena), NY (NCB) 20-40 
Grassy Creek, Jackson County, IL (Muscatatuck 
River) (ORL) 16-23, 16-34 
Graves Creek, ID (NPW) 39-16 
Grays Creek Canal, Shelby County, TN (LMM) 13-6 
Grays Harbor and Chehalis River (1948 R&H Act), 
WA (NPS) 38-30 
Grays Harbor and Chehalis River, WA (NPS) 38-3, 
38-15, 38-20 
Grays Harbor and Chehalis River (Uncompleted 
portion), WA (1968 R&H ACT) (NPS) 38-30 
Grays Harbor County (Various Locations), WA (NPS) 
38-26 
Grays Reef Passage, MI (NCE) 21-84, 21-90 
Grays River, WA (NPP) 37-36 
Grayson Lake, KY (ORH) 17-5, 17-13, 17-18 
Grayville, IL (ORL) 16-24 
Great Bend, KS (SWT) 29-5, 29-15, 29-21 
Great Chazy River, NY (NAN) 2-29 
Great Coharie Creek, NC (SAW) 6-32 
Great Egg Harbor Inlet and Peck Beach, NJ (NAP) 
3-13, 3-19, 3-24 
Great Falls, MT (MRO) 26-15 
Great Kills Harbor, NY (NAN) 2-29 
Great Lakes Connecting Channels, MI (R&H Acts of 
1946 and 1956) (NCE) 21-86 
Great Lakes to Hudson River W/W, NY (NAN) 2-29 
Great Miami River, Brookville Lake, IN (ORL) 16-32 
Great Miami River, Port Jefferson, OH (ORL) 16-37 
Great Miami River, Sidney, OH (ORL) 16-35 
Great Pee Dee River, SC (SAN) 7-17 
Great Salt Plains Lake, OK (SWT) 29-6, 29-15, 29-21 
Great Salt Pond, Block Island, RI (uncompleted 
portion) (NED) 1-49 
Great Salt Pond, Block Island, RI (NED) 1-41 
Great Sodus Bay Harbor, NY (NCB) 20-6, 20-18, 
20-31 
Great Sodus Bay Harbor, NY 1941 R&H Act (NCB) 
20-45 
Great South Bay, NY (NAN) 2-5, 2-22, 2-28 
Green and Barren Rivers, KY (ORL) 16-2, 16-14, 
16-19, 16-28 
Green Bay Harbor, MI (NCE) 21-13, 21-53, 21-73 
Green Bay Levee and Drainage District No. 2, IA 
(NCR) 23-12, 23-14 
Green Brook (Regional Center), NJ (NAN) 2-34 
Green Harbor, MA (NED) 1-5, 1,27, 1-37 
Green Island Levee and Drainage District, IA (NCR) 
23-13 
Green Peter-Foster Lakes, OR (NPP) 37-17, 37-26, 
37-43 
Green River between Kent and Auburn, WA and 
Allentown, WA (NPS) 38-26 
Green River, Calhoun, KY (ORL) 16-35 
Green River Lake, KY (ORL) 16-8, 16-16, 16-32 
Green River, State Highway 181, WA (NPS) 38-26 
Green Swamp, Sumter County, SC (SAN) 7-18 
Green Valley Creek, Solano County, CA (SPK) 35-38 
Greene County, AL (SAM) 10-56 
Greene, NY (NAB) 4-35, 4-38 
Greenfield Bayou, IN (Wabash River) (ORL) 16-24 
Greenfield Bayou Levee, IN (Wabash River) (ORL) 
16-29 
Greenport Harbor (NAN) 2-28, 2-29 
Greens Bayou, TX (SWG) 31-11 
Greens Creek, Petal, MS (SAM) 10-51 
I-25

Greenup, KY (ORH) 17-22 
GreenvaleCreek, VA (NAO) 5-17 
Greenville, TX (SWF) 30-22 
Greenwich Bay, RI (NED) 1-41 
Greenwich Harbor, CT (NED) 1-41 
Greenwich Point Beach, CT (NED) 1-49 
Greers Ferry Lake, AR (SWL) 28-11, 28-17, 28-30 
Gregory Drainage District, MO (NCR) 23-12, 23-14 
Greilickville Harbor (Formerly Traverse City Harbor, 
)MI (NCE) 21-84, 21-90 
Greybull, WY (MRO) 26-15, 26-19 
Griffithville-Yawkey, WV (ORH) 17-24 
Grove Lake, Soldier Creek, KS (MRK) 27-18 
Guadalupe River (Remove Log Jams), TX (SWG) 
31-38 
Guadalupe River, CA (SPK) 35-9, 35-28 
Guayanes Harbor, PR (SAJ) 9-49 
Guilford Harbor, CT (NED) 1-5, 1,27, 1-37, 1-58 
Guilford Point Beach (Jacobs Beach), Guilford, CT 
(NED) 1-45 
Gulf Beach, Milford, CT (NED) 1-45f 
Gulf Breeze, Santa Rosa County, FL (SAM) 10-50 
Gulf Intracoastal Waterway between Apalachee Bay, 
FL & Mexican Border TX (SWG) 31-5, 31-19, 
31-28, 31-39, 31-43, 31-44, 31-45, 31-46 
Gulf Intracoastal Waterway between Apalachee Bay, 
FL, & Mexican Border (LMN) 11-15 
Gulf Intracoastal Waterway between Apalachee Bay, 
FL & Mexican Border (SAM) 10-9, 10-34, 10-42 
Gulf Intracoastal Waterway, St. Marks to Tampa Bay, 
FL (SAJ) 9-49 
Gulf Street, Milford, CT (NED) 1-46, 1-54 
Gulfport Harbor, MS (SAM) 10-10, 10-34, 10-42 
Guttenberg, IA (NCS) 24-24, 24-29 
Gypsum, Gypsum Creek, KS (MRK) 27-17 
H 
Haaula Highway, Oahu, HI (POD) 36-11 
Hackensack River (NAN) 2-28 
Hackleman Corners Lake, Cedar Creek, MO (MRK) 
27-18 
Haikey Creek, OK (SWT) 29-27 
Haines Harbor, AK (NPA) 40-11 
Haleiwa Beach, Oahu, HI (POD) 36-8 
Haleiwa Small Boat Harbor, Oahu, HI (POD) 36-7 
Halfway Branch, Spartenburg, SC (SAN) 7-18 
Hall Meadow Brook Dam, CT (NED) 1-46, 1-55 
Halls Bayou, TX (SWG) 31-12 
Halstad, MN (NCS) 24-29 
Halstead, KS (SWT) 29-6, 29-15, 29-21 
Hamlet City Lake, NC (SAW) 6-13, 6-21 
Hamlin Beach Harbor, NY 1968 R&H Act (NCB) 
20-45 
Hamlin Beach State Park, NY (NCB) 20-41 
Hammersley Inlet (Uncompleted Portion), WA (NPS) 
38-30 
Hammersley Inlet, WA (NPS) 38-25 
Hammonasset Beach, Madison, CT (NED) 1-45 
Hammond Bay Harbor, MI (NCE) 21-14, 21-53, 
21-73 
Hammond Small Boat Basin, OR (NPP) 37-36 
Hammondsport, Oswego River Basin, NY 1941 FC 
Act (NCB) 20-45 
Hampton Beach, Hampton, NH (NED) 1-45 
Hampton Creek, VA (NAO) 5-17 
Hampton Harbor, NH (NED) 1-41 
Hampton Institute, VA (NAO) 5-18 
Hampton Roads, VA (Collection and Removal of 
Drift) (NAO) 5-4, 5-10, 5-14 
Hana Small Boat Harbor, Maui, HI (POD) 36-10 
Hanalei Small Boat Harbor, Kauai, HI (POD) 36-10 
Hanapepe Bay, Kauai, HI (POD) 36-10 
Hanapepe River, Kauai, HI (POD) 36-9 
Hancock Brook Lake, CT (NED) 1-17, 1-31, 1-55 
Hancock County, Seawall, MS (SAM) 10-51 
Hanging Rock, OH (ORH) 17-22 
Hannibal Harbor, MO 25-8 
Hannibal, MO (NCR) 23-4, 23-7, 23-10 
Hannibal SBH, MO (NCR) 23-11 
Hanover, Hennepin County, MN (NCS) 24-24, 24-29 
Hansen Dam, CA (SPL) 33-9, 33-15, 33-30 
Harbor Beach Harbor, MI (NCE) 21-15, 21-54, 21-73 
Harbor of Refuge (NAP) 3-25 
Harbor of Refuge, Block Island, RI (NED) 1-41 
Harbor of Refuge, Block Island, RI (uncompleted 
portion) (NED) 1-49 
Harbor of Refuge, NC (SAW) 6-29 
Harbor Office at Morro Bay, CA (SPL) 33-28 
Harbors of Washington Island, WI (R&H Act of 1937) 
(NCE) 21-86 
Harlan County Lake, Republican River, NE (MRK) 
27-3, 27-10, 27-13, 27-20 
Harlem River, NY (NAN) 2-29 
Harpers Ferry, WV (NAB) 4-36 
Harpeth River, Williamson County, TN (ORN) 15-18 
1-26

Harraseeket River, ME (NED) 1-41 
Harrisburg, IL (ORL) 16-23, 16-29, 16-34 
Harrisonville Levee and Drainage District, IL (LSM) 
14-16 
Harrisville Harbor, MI (NCE) 21-84, 21-90 
Harry S. Truman Dam and Reservoir, MO 
(Downstream Fish and Wildlife Mitigation) 
(MRK) 27-17 
Harry S. Truman Dam and Reservoir, Osage River, 
MO (MRK) 27-8, 27-12, 27-16 
Hartford, CT (NED) 1-46, 1-54 
Hartford, White River, CT (NED) 1-46, 1-54 
Hartford, WV (ORH) 17-22 
Hartwell Drainage and Levee District, IL (LSM) 
14-12 
Hartwell Lake, GA and SC (SAS) 8-8, 8-12, 8-17 
Harvey Canal, Bayou Barataria Levee, LA (LMN) 
11-17 
Hastings Harbor, MN 25-7 
Hatchie River, Alcorn County, MS (LMM) 13-6 
Haverhill, MA (NED) 1-46, 1-56 
Havre, MT (MRO) 26-15, 26-18 
Havre, Scott Coulee-Bull Hook Dam (MRO) 26-18 
Hawesville, KY (ORL) 16-23, 16-29, 16-34 
Hay (West Harbor), Fisher's Island, NY (NED) 1-42 
Hay Creek, Belle Fource, SD (MRO) 26-23 
Hay Creek, Birdsboro, PA (NAP) 3-27 
Hayden Island, OR (NPP) 37-38 
Hays, Big Creek, KS (MRK) 27-18 
Haysi, VA (ORH) 17-21 
Hayward Creek, Braintree-Quincy, MA (NED) 1-46 
Hazard, KY (ORL) 16-20 
Hazard, KY (ORL) 16-24 
Heeia-Kea Small Boat Harbor, Oahu, HI (POD) 36-10 
Heise-Roberts Area, Snake River, ID (NPW) 39-16 
Heise-Roberts Extension, ID (NPW) 39-17, 39-18 
Helena Harbor, AR (LMM) 13-5 
Hellens Creek, MD (NAB) 4-37 
Helm Lake, IL (ORL) 16-27, 16-33 
Hempstead County Levee District No. 1, AR (LMK) 
12-20, 12-21 
Hempstead Harbor, NY (NAN) 2-6, 2-18, 2-23, 2-34 
Henderson Bay, Purdy, WA (NPS) 38-26 
Henderson County Drainage District No. 3, IL (NCR) 
23-12 
Henderson County Drainage District No. 2, IL (NCR) 
23-12, 23-14 
Henderson County Drainage District No. 1, IL (NCR) 
23-12, 23-14 
Henderson Creek, Warren County, IL (NCR) 23-16 
Henderson Harbor Cut, NY (NCB) 20-43 
Henderson River, IL (NCR) 23-13 
Henderson, WV (ORH) 17-22 
Hendrick's Harbor, ME (NED) 1-42 
Hennepin Drainage and Levee District, IL (NCR) 
23-12, 23-14 
Henrys Fork Unit (NPW) 39-17 
Henson Creek, Lake City, CO (SPK) 35-44 
Hereford Inlet (NAP) 3-27 
Hergot Drainage and Levee District, IL (NCR) 23-14 
Herkimer, NY (NAN) 2-32 
Herreid, Spring Creek, SD (MRO) 26-15, 26-19 
Herring Bay and Rockhold Creek, MD (NAB) 4-32, 
4-38 
Herring Creek, MD (NAB) 4-32 
Heyburn Lake and Polecat Creek, OK (SWT) 29-6, 
29-15, 29-21 
Hickman Run, Little Tyron Township, PA 
(reconnaissance) (ORP) 18-30 
Hidden Dam-Hensley Lake, Fresno River, CA (SPK) 
35-10, 35-28 
Higginsport, OH (ORH) 17-22 
Highland Bayou, TX (SWG) 31-38 
Highway 12, CO (SWA) 32-19 
Highway 39 Bridge, Gainesville, FL (SAM) 10-50 
Hills Creek Lake, OR (NPP) 37-18, 37-26, 37-34, 
37-43 
Hills Point Road, Dorchester County, MD (NAB) 4-35 
Hillsborough Bay, FL (SAJ) 9-50 
Hillsborough River, FL (SAJ) 9-43 
Hillsdale Lake, Big Bull Creek, KS (MRK) 27-3, 
27-10, 27-14, 27-20 
Hillview Drainage and Levee District, IL (LSM) 
14-12 
Hilo Harbor, Hawaii, HI (POD) 36-7 
Hilslboro Inlet, FL (SAJ) 9-49 
Hingham Harbor, MA (NED) 1-42 
Hintonville Road Bridge, Perry County, MS (SAM) 
10-50 
Hiwassee River, Polk and Bradley Counties, TN 
(ORN) 15-14 
Hockingport, OH (ORH) 17-22 
Hodges Dam, San Dieguito River Basin, CA (SPL) 
33-32 
Hodges Village Dam, MA (NED) 1-21, 1-33, 1-57 
I-27

Hoh River, County Road 216, WA (NPS) 38-26 
Hoh River, near Forks, WA (NPS) 38-27 
Hoh River Road, Jefferson County, WA (NPS) 38-27 
Hoh River, U.S. Highway 101, WA (NPS) 38-27 
Hokah, MN (NCS) 24-29 
Hoko River, Sekiu, WA (NPS) 38-27 
Holbrook, AZ (SPL) 33-9, 33-15 
Holbrook Levee, Little Colorado River, Colorado 
River Basin, AZ (SPL) 33-30 
Holes Creek, West Carrollton, Ohio (Great Miami 
River) (ORL) 16-24 
Holland Harbor Entrance Channel, MI (1954 R&H 
Act) (NCE) 21-86 
Holland Harbor, MI (NCE) 21-15, 21-54, 21-74 
Holley Lake, OR (NPP) 37-38, 37-40 
Holly, CO (SWA) 32-19 
Hollywood-Ardmore Beach, Chicago, IL (NCC) 22-20 
Holmes Bay, Whiting, ME (NED) 1-46 
Holmes Creek, FL (SAM) 10-49 
Holston River, TN (ORN) 15-13 
Holyoke, MA (NED) 1-46, 1-54 
Homasassa River, FL (SAJ) 9-49 
Homer Harbor, AK (NPA) 40-2, 40-7, 40-9, 40-11 
Homer Spit Erosion, AK (NPA) 40-5, 40-8, 40-10 
Hominy Swamp, NC (SAW) 6-29, 6-32 
Homme Lake and Dam, ND (NCS) 24-6, 24-19, 
24-31 
Homochitto River, MS (LMK) 12-16, 12-21 
Honey Creek Levee, IN (ORL) 16-26, 16-30 
Honey Hill Lake, NH (NED) 1-49 
Honga River and Tar Bay, MD (NAB) 4-32 
Honga River and Tar Bay (NAB) 4-38 
Honokohau Small Boat Harbor, Hawaii, HI (POD) 
36-7 
Honolulu Harbor, Oahu, HI (POD) 36-7 
Hood Canal, Hoodsport, WA (NPS) 38-27 
Hoonah Harbor, AK (NPA) 40-11 
Hooper, Elkhorn River, NE (MRO) 26-20 
Hoosic Falls, Hoosic River Basin, NY (NAN) 2-32 
Hop Brook Lake, CT (NED) 1-17, 1-31, 1-55 
Hoper, NE (MRO) 26-16 
Hopkinton-Everett Lakes, NH (NED) 1-19, 1-32, 1-56 
Hoquiam, Aberdeen, and Cosmopolis, Chehalis River, 
WA (NPS) 38-30 
Hoquiam River, WA (NPS) 38-25, 38-27 
Hords Creek Lake, TX (SWF) 30-6, 30-16, 30-19 
Horn Harbor, VA (NAO) 5-17 
Hornell, NY (NAB) 4-14, 4-25 
Horsepen Branch, Sumter County, SC (SAN) 7-18 
Horseshoe Bend, WA (NPS) 38-31 
Horseshoe Cove, FL (SAJ) 9-49 
Hoskins Creek, VA (NAO) 5-17, 5-19 
Hot Springs, Fall River Channel, SD (MRO) 26-19 
Houlka Creek, Chickasaw & Clay Counties, MS 
(SAM) 10-50 
Housatonic River Basin, CT and MA (NED) 1-17 
Housatonic River, CT (NED) 1-42, 1-58 
Housatonic River, CT (uncompleted portion) (NED) 
1-49 
Housatonic River, Pittsfield, MA (NED) 1-46, 1-55 
Housatonic River, Salisbury, CT (NED) 1-46, 1-55 
Housatonic River, Sheffield, MA (NED) 1-46, 1-55 
Houston County, AL (SAM) 10-56 
Houston, MN (NCS) 24-7, 24 19 
Houston School Road Bridge, Itawamba County, MS 
(SAM) 10-50 
Houston Ship Channel, TX (SWG) 31-6, 31-20, 
31-30, 31-39, 31-41, 31-46 
Howard A. Hanson Dam, WA (NPS) 38-9, 38-17, 
38-22 
Howards Mill Lake, NC (SAW) 6-28 
Hudson Harbor, WI (NCS) 24-26 
Hudson River Channel, NY & N.J. (NAN) 2-7, 2-19, 
2-23, 2-28 
Hudson River, FL (SAJ) 9-49 
Hudson River, NY (NAN) 2-6, 2-19, 2-23, 2-27 
Hudson River, NYC to Albany (NAN) 2-34 
Hugo Lake, OK (SWT) 29-6, 29-15, 29-21 
Hulah Lake, OK (SWT) 29-6, 29-16, 29-21 
Hull Branch, MS (SAM) 10-56 
Humboldt Bay (Buhne Point), CA (SPN) 34-13 
Humboldt Harbor, AK (NPA) 40-11 
Humboldt Harbor and Bay, CA (SPN) 34-7 
Humboldt River and Tributaries, NV (SPK) 35-40 
Humboldt, TN (LMM) 13-6 
Hunt Drainage District and Lima Lake Drainage 
District, IL (NCR) 23-12, 23-14 
Hunting Bayou, TX (SWG) 31-12 
Hunting Island Beach, SC (SAN) 7-17 
Huntingdon, TN (LMM) 13-7 
Huntington Avenue, Castle Rock, WA (NPP) 37-37 
Huntington Harbor, NY (NAN) 2-29, 2-34 
Huntington Lake, IN (ORL) 16-8, 16-16 
Huntington, MA (NED) 1-46, 1-54 
Huntington, WV (ORH) 17-21, 17-24 
Huot, MN (NCS) 24-29 
I-28

Huron Harbor, OH (NCB) 20-6, 20-18, 20-32 
Huron Harbor, OH 1962 R&H Act (NCB) 20-45 
Hurricane Barrier Operations 
New England Division (NED) 1-24 
Hurricane Creek, Prentiss County, MS (SAM) 10-17, 
10-35, 10-46 
Hutchins, KY (ORH) 17-24 
Hutchinson LPP, KS (SWT) 29-24, 29-27 
Hutto Creek, Austin, IN (ORL) 16-37 
Hyannis Harbor, MA (NED) 1-6, 1,27, 1-37 
Hyde County Dike, NC (SAW) 6-29 
I 
I-38 Lake, MO (LSM) 14-18 
Iao Stream, Maui, HI (POD) 36-9 
Ice Harbor at Marcus Hook, PA (NAP) 3-26 
Ice Harbor at New Castle, DE (NAP) 3-26 
Ice Harbor Lock and Dam - Lake Sacajawea, WA 
(NPW) 39-5, 39-10, 39-13, 39-19, 39-23 
Ida Grove, IA (MRO) 26-16 
Ida Grove, Maple River-Odebolt Creek, IA (MRO) 
26-20 
Iliuliuk Harbor, AK (NPA) 40-11 
Illinois and Mississippi Canal, (NCR) IL 23-2, 23-7 
Illinois Beach State Park, IL (NCC) 22-6, 22-13, 
22-17 
Illinois River, Liverpool, IL (NCR) 23-15 
Illinois Shore of Lake Michigan, Winnetka, IL (NCC) 
22-21 
Illinois Shore of Lake Michigan, Chicago, IL (NCC) 
22-21 
Illinois Shore of Lake Michigan, Kenilworth, IL 
(NCC) 22-20 
Illinois Waterway, (NCR) IL and IN 23-22, 23-7, 23-8 
Illinois Waterway Existing Locks and Dams (NCR) 
23-17 
Illinois Waterway, IL (LSM) 14-2 
Illinois Waterway, IL and IN (NCR) 23-19, 23-20 
Illinois Waterway, IL and IN Additional Features 
(NCR) 23-18, 23-19 
Illinois Waterway, IL and IN Lock and Dam 
Construction (NCR) 23-17, 23-18 
Illinois Waterway, IL and IN Duplicate Locks (NCR) 
23-13 
Illinois Waterway, Marseilles Canal, IL (NCR) 23-14 
Illinois Waterway, Navigation Project (Pekin, IL) 
(NCR) 23-13 
Imperial Beach, CA (SPL) 33-29 
Inarajan Shoreline, Guam (POD) 36-11 
Indian Bend Wash (SPL) 33-30 
Indian Creek at Emerson, IA (MRO) 26-16, 26-21 
Indian Creek, Burton Road, Morgan County, IN 
(ORL) 16-37 
Indian Creek, Corydon, IN (ORL) 16-23, 16-34 
Indian Creek, Hastings, IA (MRO) 26-23 
Indian Creek Lake, IA (MRO) 26-17 
Indian Grave Drainage District, IL (NCR) 23-12, 
23-14 
Indian Lake, Blue River, KS (MRK) 27-18 
Indian River County, FL (SAJ) 9-17, 9-31, 9-46 
Indian River Inlet and Bay, DE (NAP) 3-5, 
3-17(NAP) 3-21 
Indiana Dunes National Lakeshore, Bank Protection, 
Beverly Shores, IN (NCC) 22-7, 22-13, 22-17 
Indiana Harbor, IN (NCC) 22-4, 22-12, 22-16, 22-19 
Indiana Shoreline Erosion, IN (NCC) 22-7, 22-13, 
22-18 
Indianapolis, IN (Fall Creek Section)(White River) 
(ORL) 16-23, 16-34 
Indianapolis, IN (Warfleigh Section)(White River) 
(ORL) 16-24 
Indianola, NE (MRK) 27-17, 27-20 
Industry, PA (ORP) 18-24 
Inex, KY (ORH) 17-24 
Inland Waterway from Chincoteague Bay to Delaware 
Bay (NAP) 3-25 
Inland Waterway from Delaware River to Chesapeake 
Bay, DE, MD, 3-17 (NAP) 3-5, 3-21 
Inland Waterway from Franklin to Mermentau River, 
LA (LMN) 11-15 
Inland Waterway Rehoboth to Delaware Bay, DE 
(NAP) 3-6, 3-17, 3-22 
Inspection of Completed Beach Erosion Control 
Projects 
New England Division (NED) 1-10 
Inspection of Completed Flood Control Projects 
Alaska District (NPA) 40-5 
Albuquerque District (SWA) 32-10 
Baltimore District (NAB) 4-19 
Buffalo District (NCB) 20-13 
Charleston District (SAN) 7-9 
Detroit District (NCE) 21-41 
Fort Worth District, (SWF) 30-11 
Galveston District (SWG) 31-16 
Huntington District (ORH) 17-10, 17-19 
I-29

Jacksonville District (SAJ) 9-24 
Kansas City District) (MRK) 27-7, 27-12 
Little Rock District (SWL) 28-7 
Los Angeles District (SPL) 33-8 
Louisville District (ORL) 16-13 
Memphis District (LMM) 13-2 
Mobile District (SAM) 10-23 
Nashville District (ORN) 15-5 
New England Division (NED) 1-23 
New Orleans District (LMN) 11-9 
New York District (NAN) 2-17 
Omaha District (MRO) 26-5, 26-10 
Philadelphia District (NAP) 3-14 
Pittsburgh District (ORP) 18-11 
Portland District (NPP) 37-13 
Rock Island District (NCR) 23-6 
Sacramento District (SPK) 35-22 
San Francisco District (SPN) 34-5 
Savannah District (SAS) 8-7, 8-11 
Seattle District (NPS) 38-9 
St. Louis District (LSM) 14-6 
St. Paul District (NCS) 24-16 
Tulsa District (SWT) 29-10 
Vicksburg District (LMK) 12-8 
Walla Walla District (NPW) 39-2 
Wilmington District (SAW) 6-15 
Inspection of Completed PL-99 Works (NPW) 39-2 
Inspection of Non-Federal Levees 
Philadelphia District (NAP) 3-14 
Intercounty D.D., Little Sioux River, IA (MRO) 26-20 
International Boundary Waters Board 49-1 
Interstate 59 Bridges, Foster, AL (SAM) 10-50 
Intracoastal Waterway, Caloosahatchee River to 
Anclote River, FL (SAJ) 9-6, 9-27, 9-36 
Interstate Bridge, Colubmia River, Portland, OR to 
Vancouver, WA (Alteration) (NPP) 37-36 
Interstate Highway Bridge (Barge Channel), OR (NPP) 
37-36 
Intracoastal Waterway from the Mississippi River to 
Bayou Teche, LA (LMN) 11-15 
Intracoastal Waterway, Jacksonville to Miami, FL 
(SAJ) 9-6, 9-27, 9-36 
Intracoastal Waterway, Miami to Key West, FL (SAJ) 
9-49 
Investigation of Projects Under Federal Power Act 
50-1 
Iola LPP, KS (SWT) 29-24, 29-27 
Iowa River, Chelsea, IA (NCR) 23-16 
Iowa River-Flint Creek Levee District No. 16, IA 
(NCR) 23-12, 23-15 
Ipswich River, MA (NED) 1-42 
Ipswich River, MA (uncompleted portion) (NED) 1-49 
Irondequoit Bay, NY (NCB) 20-6, 20-18, 20-32 
Ironton, OH (ORH) 17-21, 17-24 
Irving Township at Nichols Road, Jackson County, WI 
(NCS) 24-24 
Irving Township, Jackson County, WI (NCS) 24-24 
Irvington Harbor, NY (NAN) 2-34 
Isabella Lake, Kern River, CA (SPK) 35-10, 35-28 
Island Avenue, Quincy, MA (NED) 1-46 
Island Creek, MD (NAB) 4-32 
Island Creek, St. Georges Island, MD (NAB) 4-32 
Island End River, Chelsea, MA (NED) 1-42 
Island Levee, IN (Wabash River) (ORL) 16-24, 16-30 
Isle Au Haut Thoroughfare, ME (NED) 1-42 
Isle of Shoals Harbor, ME and NH (NED) 1-42, 1-58 
Isle of Wight Bay, Ocean City, MD (NAB) 4-10, 
4-23, 4-30 
Islesboro (The Narrows), ME (NED) 1-46 
Isreal River, NH (NED) 1-52 
Ithaca, Cayuga Inlet, NY (NCB) 20-42 
Ithaca, NY - Cascadilla Creek 1941 FC Act (NCB) 
20-45 
Ithaca, NY - Fall Creek 1941 FC Act (NCB) 20-45 
J 
J. Percy Priest Dam and Reservoir, Ohio River Basin, 
TN (ORN) 15-6, 15-9, 15-17 
J. Strom Thurmond Dam and Reservoir, GA and SC 
(Formerly Clarks Hill Lake, GA and SC) (SAS) 
8-8, 8-11, 8-17 
Jackman Creek, Skagit River, WA (NPS) 38-27 
Jackson Brand, Dallas, TX (SWF) 30-23 
Jackson County Levee District No. 2, White River, 
AR (SWL) 28-22 
Jackson Creek, Richland County, SC (SAN) 7-18 
Jackson Creek, VA (NAO) 5-17 
Jackson Hole, Snake River, WY (NPW) 39-16 
Jackson Hole, WY (NPW) 39-2, 39-10 
Jackson, KY (Kentucky River) (ORL) 16-23, 16-29, 
16-34 
Jackson Port, Vicinity of Jackson, AL (SAM) 10-6, 
10-33, 10-41 
Jackson Township, Bulter County, PA 
(reconnaissance) (ORP) 18-30 
I-30

Jacksonburg, Fishing Creek, WV (ORH) 17-24 
Jacksonville Harbor (Mill Cove), FL (SAJ) 9-7, 9-28, 
9-37 
Jacksonville Harbor, FL (SAJ) 9-7, 9-28, 9-37 
Jamaica Bay, NY (NAN) 2-8, 2-19, 2-24, 2-28 
James R. Olin Flood Control Project (NAO) 5-7, 
5-11, 5-15 
James River Environmental, SD (MRO) 26-22 
James River, VA (NAO) 5-19 
James River, VA (NAO) 5-4, 5-10, 5-14 
James W. Trimble Lock and Dam (No. 13) (SWL) 
28-3 
Jamestown Reservoir, ND (MRO) 26-16 
Janesville and Indian Ford Dams, WI (NCR) 23-13 
Jarvis Creek, VA (NAO) 5-17 
Jefferson County (Various Locations), WA (NPS) 
38-27 
Jefferson County, AL (SAM) 10-56 
Jefferson River, Bank Protection, Near Waterloo, MT 
(MRO) 26-19 
Jefferson River, Willow Creek Bridge, Near Three 
Forks, MT (MRO) 26-19 
Jeffersonville-Clarksville, IN (ORL) 16-23, 16-29, 
16-34 
Jeffries Creek, Darlington County, SC (SAN) 7-18 
Jemez Canyon Dam, NM (SWA) 32-7, 32-14, 32-18 
Jenks LPP, OK (SWT) 29-24, 29-27 
Jennings Beach, Fairfield, CT (NED) 1-45 
Jennings Randolph Lake, MD and WV (NAB) 4-10, 
4-24, 4-30 
Jeremy Creek, SC (SAN) 7-5, 7-11, 7-15 
Jim Woodruff Lock and Dam, FL & GA (SAM) 
10-29, 10-37, 10-48 
Joe Creek LPP, OK (SWT) 29-24, 29-27 
Joe Ilardin Lock and Dam (No. 3), AR (SWL) 28-4 
Joe Pool Lake, TX (SWF) 30-6, 30-16, 30-19 
John Day Lock and Dam - Lake Umatilla, OR and 
WA (NPP) 37-18, 37-27, 37-34, 37-44 
John Day River (West), OR (NPP) 37-38 
John Day River Area, Clatsop County, OR (NPP) 
37-37 
John Day River, OR (NPP) 37-40 
John Drainage District, OR (NPP) 37-40 
John H. Kerr Dam and Reservoir, VA and NC (SAW) 
6-15, 6-22 
John Marvin Reservoir, CO (SWA) 32-4, 32-13 
John Redmond Dam and Reservoir, KS (SWT) 29-7, 
29-16, 29-21 
John W. Flannagan Dam and Reservoir, Ohio River 
Basin, VA (ORH) 17-6, 17-13, 17-18 
John's Pass, FL (SAJ) 9-8, 9-28, 9-37 
Johnson Bay, Lubec, ME (NED) 1-46 
Johnson Bayou, TX (SWG) 31-38 
Johnson Creek, Grand Prairie, TX (SWF) 30-23 
Johnson Creek, OR (NPP) 37-38 
Johnsonburg, PA (ORP) 18-22, 18-29 
Johnstown, PA (ORP) 18-22 
Johnstown, PA (ORP) 18-4, 18-13, 18-18 
Jones Inlet (NAN) 2-28, 2-29 
Jonesport Harbor, ME (NED) 1-6, 1,27, 1-37 
Jonesville, LA (LMK) 12-15 
Josias River, ME (NED) 1-42, 1-58 
Joyce Creek, Camden County, NC (SAW) 6-28 
Juan Mendez Channel, PR (SAJ) 9-61 
Julian, Rock Creek, NE (MRO) 26-20 
Juneau Harbor, AK (NPA) 40-11 
K 
Kaaawa Beach, Oahu, HI (POD) 36-8 
Kaaawa Highway, Oahu, HI (POD) 36-11 
Kaelepulu Stream, Oahu, HI (POD) 36-12 
Kahawainui Stream, Oahu, HI (POD) 36-9 
Kahoma Stream, Oahu, HI (POD) 36-9 
Kahului Beach Road, Maui, HI (POD) 36-7 
Kahului Harbor, Maui, HI (POD) 36-7 
Kahului Small Boat Harbor, Maui, HI (POD) 36-11 
Kailua Small Boat Harbor, Oahu, HI (POD) 36-10 
Kaimu Black Sand Beach, Hawaii, HI (POD) 36-10 
Kake Harbor, AK (NPA) 40-11 
Kalama River (South Area) Levee, Cowlitz County, 
WA (NPP) 37-40 
L 
Lake River Delta Area, WA (NPP) 37-40 
Kalama Turning Basin, Kalama, WA (NPP) 37-36 
Kalamazoo River (Battle Creek), MI (NCE) 21-85 
Kalamazoo River, Battle Creek, MI (1954 Flood 
Control Act) (NCE) 21-86 
Kalamazoo River, Kalamazoo, MI (1958 Flood 
Control Act) (NCE) 21-86 
Kalaupapa Harbor, Molokai, HI (POD) 36-7 
Kanawha River, WV (ORH) 17-2, 17-12, 17-17 
Kaneohe-Kailua Area, Oahu, HI (POD) 36-9 
1-31

Kankakee River, IL and IN Levee Between Shelby 
Bridge and Baum's Bridge, IN (NCC) 22-21 
Kanopolis Lake, Smoky Hill River, KS (MRK) 27-4, 
27-11, 27-14, 27-20 
Kansas City, Kansas River, KS (62 Mod.) (MRK) 
27-17 
Kansas Citys on MO and KS Rivers, MO and KS 
(MRK) 27-17 
Kansas River and Minor Tributaries (MRK) 27-20 
Kansas River Navigation (MRK) 27-18 
Kapaa Town, Kauai, HI (POD) 36-8 
Kapaakea Homestead Flood Control, Molokai, HI 
(POD) 36-10 
Karlson Island, Clatsop County, OR (NPP) 37-37 
Kasilof Harbor, AK (NPA) 40-11 
Kaskaskia Island Drainage and Levee District, IL 
(LSM) 14-5, 14-9, 14-12, 14-16 
Kaskaskia River, IL (LSM) 14-11, 14-16 
Kaulana Bay Boat Harbor, Hawaii, HI (POD) 36-7 
Kaumalapau Harbor, Lanai, HI (POD) 36-11 
Kaunakakai Deep Draft Harbor, Molokai, HI (POD) 
36-10 
Kaunakakai Small Draft Harbor, Molokai, HI (POD) 
36-10 
Kaunakakai Stream, Molokai, HI (POD) 36-9 
Kaw Dam to Keystone Lake (SWT) 29-29 
Kaw Lake, OK (SWT) 29-7, 29-16, 29-21 
Kawaihae Harbor, Hawaii, HI (POD) 36-7 
Kawaihae Small Boat Harbor, Hawaii, HI (POD) 36-2, 
36-5, 36-6 
Kawainui Marsh, Oahu, HI (POD) 36-12 
Kawainui Swamp, Oahu, HI (POD) 36-9 
Kaweah and Tule Rivers, including Terminus Dam 
and Success Lake, CA (SPK) 35-11, 35-28 
Kawishiwi River, MN (NCS) 24-30 
Kawkawlin River, MI (NCE) 21-85 
Kays Creek, UT (SPK) 35-38 
Keach Drainage and Levee District, IL (LSM) 14-18 
Keehi Lagoon, Oahu, HI (POD) 36-7 
Keene, NH (NED) 1-46, 1-54 
Keg Creek, Minden, IA (MRO) 26-21 
Kehoe Lake, KY (ORH) 17-21 
Keithsburg Drainage District, IL (NCR) 23-14 
Kekaha Beach, Kauai, HI (POD) 36-8 
Kelleys Island, OH (NCB) 20-40 
Kendrick, Potlatch River, ID (NPW) 39-18, 39-18 
Kenmore Navigation Channel, WA (NPS) 38-4, 
38-15, 38-21 
Kennebec River, ME (NED) 1-6, 1,27, 1-37, 1-52, 
1-58 
Kennebec River, ME (uncompleted portion) (NED) 
1-49 
Kennebunk River, ME (NED) 1-42 
Kenosha Harbor, WI (1962 R&H Act) (NCE) 21-86 
Kenosha Harbor, WI (NCE) 21-16, 21-55, 21-74 
Kentucky River, Frankfort, KY (ORL) 16-37 
Kentucky River, KY (ORL) 16-2, 16-14, 16-28 
Kentucky River, National Recreation Area (ORL) 
16-24 
Kern River-California Aqueduct Intertie, CA (SPK) 
35-38 
Kerton Valley Drainage and Levee District, IL (NCR) 
23-15 
Ketchikan, AK (NPA) 40-13 
Ketchikan Harbor (West Breakwater), AK (NPA) 
40-12 
Ketchikan Harbor, AK (NPA) 40-11 
Keuka Lake, NY (NCB) 20-22, 20-39 
Kewalo Harbor, Oahu, HI (POD) 36-10 
Kewaunee River, WI (1960 R&H Act) (NCE) 21-86 
Kewaunee, WI, WI (NCE) 21-17, 21-55, 21-74 
Keweenaw Waterway, MI (NCE) 21-17, 21-55, 21-74 
Key West Harbor, FL (SAJ) 9-49, 9-51 
Keyport Harbor (NAN) 2-28, 2-29 
Keystone Lake, OK (SWL) 28-28 
Keystone Lake, OK (SWT) 29-11, 29-19, 29-23, 
29-26 
Kickapoo River, Gays Mills, WI (NCS) 24-24, 24-29 
Kihei Beach, Maui, HI (POD) 36-8 
Kikiaola Small Boat Harbor, Kauai, HI (POD) 36-7 
Kill Van Kull Channel (NAN) 2-28 
Kill Van Kull-Newark Bay, N.J. & NY (NAN) 2-8, 
2-19, 2-24 
Kindred Lake, ND (NCS) 24-26 
King County (Various Locations), WA (NPS) 38-27 
King Cove Harbor, AK (NPA) 40-13 
Kings Creek, VA (NAO) 5-17 
Kingston-Edwardsville, PA (NAB) 4-35, 4-38 
Kingston Harbor (North Plymouth), MA (NED) 1-42 
Kingston Harbor, WA (NPS) 38-25 
Kingstree Branch, Williamsburg County, SC (SAN) 
7-18 
Kinley Creek, Lexington County, SC (SAN) 7-18 
Kinzua Dam and Allegheny Reservoir, Ohio River 
Basin, PA and NY, (ORP) 18-7, 18-14, 18-19, 
18-28 
I-32

Kiowa Tribe Housing Development, Andarko, OK 
(SWT) 29-28 
Kirbyville, TX (SWG) 31-13, 31-21 
Kishwaukee River at DeKalb, IL (NCR) 23-12 
Kissemmee River Restoration, FL (SAJ) 9-25, 9-32, 
9-48, 9-49 
Kittanning, PA Part I (ORP) 18-22, 18-29 
Kittanning, PA part II (Allegheny River) (ORP) 18-24 
Kitzmiller, MD (NAB) 4-35, 4-38 
Klamath River, CA (SPK) 35-38 
Klawock, AK (NPA) 40-13 
Klutina River, Cooper Center, AK (NPA) 40-12 
Knappa Area, Clatsop County, OR (NPP) 37-37 
Knapps Narrows, MD (NAB) 4-5, 4-22, 4-28 
Knife River Harbor, MN (NCE) 21-84 
Knights Valley Lake, R.R. Basin, CA (SPN) 34-13 
Knightville Dam, MA (NED) 1-14, 1-30, 1-53 
Knobb's Creek, NC (SAW) 6-26 
Kodiak Harbor (Near Island Channel), AK (NPA) 
40-13 
Kodiak Harbor, AK (NPA) 40-6, 40-8, 40-10, 40-11 
Kootenai River, Bonners Ferry, ID (NPS) 38-27 
Kootenai River, ID and MT (NPS) 38-25 
Kootenai River, Kootenai Flats Area, District #1, ID 
(NPS) 38-27 
Koyuk, AK (NPA) 40-13 
Kualoa Regional Park, Oahu, HI (POD) 36-8 
Kuliouou Stream, Oahu, HI (POD) 36-9 
L 
La Conner, Swinomish Channel, WA (NPS) 38-27 
La Crosse, WI (NCS) 24-26 
La Farge Lake and Channel Improvemnet, WI (NCS) 
24-8, 24-19 
La Trappe, MD (NAB) 4-33 
Lac La Belle Harbor, MI (NCE) 21-84, 21-90 
Lac qui Parle Lakes, Minnesota River, MN (NCS) 
24-7, 24-19, 24-31 
Lac qui Parle, MN (NCS) 24-30 
Lacakawanna, NY, Smokes Creek (NCB) 20-42 
Lacey Drainage and Levee District, IL (NCR) 23-15 
Lacey Langellier, West Mantanzas and Kerton Valley 
Drainage and Levee District, IL (NCR) 23-12 
Lackawanna River Basin, PA (NAB) 4-11, 4-30 
Lafayette Lake, IN (Wabash River) (ORL) 16-24 
Lafayette River, VA (NAO) 5-17 
Lago de Cerillos, PR (SAJ) 9-48 
Lago de Portuges, PR (SAJ) 9-48 
Lagoon Pond, Martha's Vineyard, MA (NED) 1-42 
LaGragne Bayou, FL (SAM) 10-52 
LaGrange Bayou, FL (SAM) 10-49 
LaGrange Gut, Frederiksted, St. Croix, VI (SAJ) 9-61 
Lahaina Small Boat Harbor, Maui, HI (POD) 36-10 
Lake Andrusia, Mississippi River, MN (NCS) 24-29 
Lake Andursia, Mississippi River, MN (NCS) 24-24 
Lake Ashtabula and Baldhill Dam, Sheyenne River, 
ND (NCS) 24-8, 24-19 
Lake Borgne and Chef Menteur Bulkheads and Jetties 
(LMN) 11-18 
Lake Brownwood Modification, TX (SWF) 30-22 
Lake Camanchie, CA (SPK) 35-38 
Lake Charles Deep Water Channel, LA (LMN) 11-15 
Lake Charles, LA (LMN) 11-12 
Lake Chautauqua and Chadakoin River, NY (ORP) 
18-24 
Lake City Harbor, MN 25-7 
Lake Creek, Round Rock, TX (SWF) 30-23 
Lake Crescent and Dunns Creek, FL (SAJ) 9-49 
Lake Crockett, WA (NPS) 38-4, 38-15, 38-21, 38-31 
Lake Darling Dam, ND (NCS) 24-24 
Lake Douglas, Decatur, GA (SAM) 10-50 
Lake Elsinore, CA (SPL) 33-9, 33-15 
Lake Erie, Cooley Canal, Lucas, OH (NCB) 20-43 
Lake Erie, Eastlake, OH (NCB) 20-44 
Lake Erie, Fredonia, NY (NCB) 20-44 
Lake Erie, Middle Bass Island, Deist Road, OH 
(NCB) 20-44 
Lake Erie-Ohio Canal, OH and PA - 1935 Act (ORP) 
18-24 
Lake Erie, SR 531, Ashtabula, OH (NCB) 20-44 
Lake Erie Sturgeon Point, NY (NCB) 20-21 
Lake Fork Lake, Sabine River, TX (SWF) 30-22 
Lake George, Hobart, IN (NCC) 22-8, 22-14, 22-18 
Lake Herman (Dredging), SD (MRO) 26-17 
Lake Hudson (Markham Ferry) (SWT) 29-26 
Lake Kemp, TX (SWT) 29-7, 29-16, 29-21 
Lake Michigan Diversion (NCC) 22-6, 22-13, 22-16 
Lake Michigan, Edgewater/Rogers Park Communities, 
Chicago, IL (NCC) 22-20 
Lake Michigan-Lake Bluff, IL (NCC) 22-20 
Lake Michigan-Lake Forest, IL (NCC) 22-20 
Lake Montauk Harbor (NAN) 2-28, 2-29 
Lake Ogleton, MD (NAB) 4-37 
Lake Oroville, CA (SPK) 35-38 
I-33

Lake Pontchartrain and Vicinity, LA (Hurricane 
protection) (LMN) 11-4, 11-10, 11-13 
Lake Pontchartrain, North Shore, LA (LMN) 11-13 
Lake Providence Harbor, LA (LMK) 12-16 
Lake Pulaski, Wright County, MN (NCS) 24-24 
Lake River, WA (NPP) 37-36 
Lake Sawyer, Camp Miakonda, Toledo, OH (NCB) 
20-44 
Lake Shelbyville, IL (LSM) 14-16 
Lake Shirley, Lunenburg, MA (NED) 1-52 
Lake St. Clair, MI, Channels in (NCE) 21-18, 21-56, 
21-75 
Lake Texoma (Denison Dam) OK and TX (SWT) 
29-11, 29-19, 29-23, 29-29 
Lake Traverse and Bois de Sioux River, SD and MN 
(NCS) 24-9, 24-19 
Lake Traverse, MN and SD (NCS) 24-23 
Lake Washington Ship Channel, WA (NPS) 38-5, 
38-15, 38-21, 38-30 
Lake Wichita, Holliday Creek, TX (SWT) 29-7, 
29-16, 29-22 
Lakeport Lake, CA (SPK) 35-38 
Lakeshore Park, Ashtabula, OH (NCB) 20-21, 20-38 
Lakeside,OR (NPP) 37-42 
Lakeview Park, Lorain, OH (NCB) 20-41 
Lamoille River, VT (NAN) 2-34 
Lamoille River, VT: Hardwich Dams (NAN) 2-32 
Lamprey River, NH (NED) 1-42 
Lancassange Creek, Clark County, IN (ORL) 16-37 
Lancaster, Cayuga Creek, NY (NCB) 20-42 
Lancaster, Israel River, NH (NED) 1-46, 1-54 
Langellier Drainage and Levee District, IL (NCR) 
23-15 
Lansing (Grand River), MI (1958 Flood Control Act) 
(NCE) 21-86 
Lansing Harbor, IA 25-7 
LaPoint Harbor, WI (NCE) 21-18, 21-56, 21-75 
Lapwai Creek, Culdesac, ID (NPW) 39-16 
Larchmont Harbor, NY (NAN) 2-29 
Largo Sound Channel, FL (SAJ) 9-49 
Lamed LPP, KS (SWT) 29-24, 29-27 
Larose to Golden Meadow, LA (Hurrican protection) 
(LMN) 11-5,, 11-14 11-10 
Larsen Bay, AK (NPA) 40-13 
Las Animas, CO (SWA) 32-19 
Las Cruces, NM (SWA) 32-19 
Las Tunas Beach, San Diego County, CA (SPL) 33-29 
Las Vegas Wash Tributaries, Colorado River Basin, 
NV (SPL) 33-32 
LaSueur, MN (NCS) 24-29 
Latrobe, PA (ORP) 18-22, 18-29 
Latta Brook Road, NY (NAB) 4-35 
Lauderdale County, MS (SAM) 10-56 
Lauliifou Shoreline Protection, American Samoa 
(POD) 36-11 
Lauliituai-Aumi, American Samoa (POD) 36-12 
Launiupoko, Maui, HI (POD) 36-11 
Laupahoehoe Harbor, Hawaii, HI (POD) 36-7 
Laurel River Lake, Ohio River Basin, KY (ORN) 
15-7, 15-9, 15-17 
Lava Hot Springs, Portneuf River, ID (NPW) 39-16 
Lavaca-Navidad River, TX (SWG) 31-38 
Lavon Lake Modification and East Fork Channel 
Improvement, TX (SWF) 30-7, 30-16, 30-20 
Lavon Lake, TX (SWF) 30-7, 30-16, 30-20 
Lawrence, Kansas River, KS (MRK) 27-17, 27-20 
Lawrenceburg, IN (ORL) 16-23, 16-29, 16-34 
Lead Bayou, MS (LMK) 12-13, 12-21 
Leading Creek, WV (ORH) 17-23 
Leaf and Bowie Rivers, Hattiesburg, MS (SAM) 10-50 
Leaf River, County Road Bridge, Mahned, MS (SAM) 
10-50, 10-51 
Leaf River, MS (SAM) 10-56 
Leavenworth, IN (ORL) 16-26, 16-30 
Lebanon Junction, KY (Salt River) (ORL) 16-23, 
16-34 
Lee County, FL (SAJ) 9-50 
Lee, Housatonic River, MA (NED) 1-46 
Leesville, VA (SAW) 6-28 
Leetonia, OH (ORP) 18-22, 18-29 
Leetsdale, PA (ORP) 18-24 
Leipsic River, DE (NAP) 3-26 
Leith's Creek, SC (SAN) 7-18 
Leith's Creek, Scotland County, NC (SAW) 6-28 
Leland Bowman Lock, LA (LMN) 11-15 
Leland Harbor, MI (NCE) 21-19, 21-56, 21-75 
Lemon Creek, NY (NAN) 2-34 
Lepua Area, American Samoa (POD) 36-8 
Les Cheneaux Island Channels, MI (NCE) 21-84 
Letart Falls, OH (ORH) 17-22 
Letart, WV (ORH) 17-22 
Levee, Arkansas River, Tulsa, OK (SWT) 29-28 
Levee Districts Between Carlyle and New Athens, IL 
Nos. 2, 5, 6, and 7 (LSM) 14-18 
I-34

Levee Districts Between Carlyle and New Athens, IL 
Nos. 3, 4, 8, 10 and 13 (LSM) 14-18 
Levee Unit 1, Eel River, IN (ORL) 16-26, 16-30 
Levee Unit 1, IL (Wabash River) (ORL) 16-26 
Levee Unit 1, Little Wabash River, IL (ORL) 16-26, 
16-30 
Levee Unit 1, White River, IN (ORL) 16-26, 16-30 
Levee Unit 10, White River, IN (ORL) 16-26 
Levee Unit 17, Wabash River Basin, IN (ORL) 16-26, 
16-30 
Levee Unit 2, East Fork White River, IN (ORL) 
16-26 
Levee Unit 2, Eel River, IN (ORL) 16-26, 16-30 
Levee Unit 2, Little Wabash River, IL (ORL) 16-26, 
16-30 
Levee Unit 2, Wabash River, IL (ORL) 16-26, 16-30 
Levee Unit 2, White River, IN (ORL) 16-30 
Levee Unit 3, East Fork White River, IN (ORL) 
16-26 
Levee Unit 6, Wabash River, IL (ORL) 16-26 
Levee Unit 7, White River, IN (ORL) 16-26, 16-30 
Levee Unit 9, White River, IN (ORL) 16-26 
Levee Unit No. 5, Wabash River, IN (ORL) 16-23, 
16-34 
Levee Unit No. 8, White River, IN (ORL) 16-23, 
16-34 
Levee Units 3 and 4, Wabash River, IL (ORL) 16-26 
Levisa and Tug Forks of the Big Sandy and 
Cumberland Rivers, KY, WV and VA (ORH) 
17-6, 17-13, 17-18, 17-20 
Lewis and Clark River Area, Clatsop County, OR 
(NPP) 37-37 
Lewis River Area, WA (NPP) 37-40 
Lewis River, WA (NPP) 37-36 
Lewisport, KY (ORL) 16-26, 16-30 
Lewiston-Clarkston Bridge, ID and WA (NPW) 39-13, 
39-17 
Lewisville Dam, TX (SWF) 30-7, 30-16, 30-20 
Lexington Harbor, MI (NCE) 21-19, 21-56, 21-75 
Libby Dam - Lake Koocanusa, MT (NPS) 38-11, 
38-18, 38-24 
Liberty Island Anchorage (NAN) 2-28 
Liberty Local Protection Project, TX (SWG) 31-38 
Liberty State Park Levee and Seawall, NJ (NAN) 2-32 
Lick Creek, Hartford City (Blackford County) (ORL) 
16-35 
Lick Run, Roanoke, VA (SAW) 6-28 
Licking River, KY (ORL) 16-24, 16-35 
Lighthouse Beach, Chatham, MA (NED) 1-51 
Lighthouse Point Park (Area 9), CT (NED) 1-45 
Lightning Creek, Clark Fork, ID (NPS) 38-26 
Deschutes River, Gleason Road Bridge, near 
Tumwater, WA (NPS) 38-26 
Limestone Creek, Fayetteville, NY (NCB) 20-43 
Lincoln Lake, IL (ORL) 16-27 
Lincoln Park Beach, Seattle, WA (NPS) 38-8, 38-16, 
38-22 
Lincoln, Salt Creek and Tributaries, NE (MRO) 26-20 
Linderberg Bay Area, St. Thomas, VI (SAJ) 9-61 
Linton, ND (MRO) 26-16 
Linville River, Avery County, NC (SAW) 6-32 
Lisle, NY (NAB) 4-15, 4-25 
Little Arkansas River, Sedgwick, KS (SWT) 29-27 
Little Bay De Noc, Gladstone Harbor, MI (NCE) 
21-84 
Little Bay, TX (SWG) 31-38 
Little Blue River Channel Improvement, Little Blue 
River, MO (MRK) 27-17 
Little Blue River Lakes, MO (MRK) 27-4, 27-11, 
27-14 
Little Browns Creek, AL (SAM) 10-50 
Little Caillou Bayou, LA (LMN) 11-15 
Little Calumet River Basin, Cady Marsh Ditch, IN 
(NCC) 22-8, 22-14, 22-18 
Little Calumet River, IL and IN Little Calumet River 
and Tributaries, IL and IN (NCC) 22-21 
Little Calumet River, IN (NCC) 22-8, 22-14, 22-18, 
22-20 
Little Chena River Dam, AK (NPA) 40-12 
Little Colorado River at Holbrook, AZ (SPL) 33-30 
Little Cove Creek, Glencoe, AL (SAM) 10-50 
Little Creek, Kent Island, MD (NAB) 4-33, 4-38 
Little Cross Creek, Fayetteville, NC (SAW) 6-32 
Little Deep Fork Creek, OK (SWT) 29-28 
Little Dell Lake, UT, CA (SPK) 35-13, 35-28 
Little Diomede, AK (NPA) 40-13 
Little Egg Harbor, NJ (NAP) 3-26 
Little Fork River, Hwy 75, MN (NCS) 24-30 
Little Goose Lock and Dam - Lake Bryan, WA 
(NPW) 39-5, 39-10, 39-13, 39-20, 39-23 
Little Harbor, NH (NED) 1-42 
Little Harbor, Woods Hole, MA (NED) 1-42 
Little Harpeth River, Brentwood, TN (ORN) 15-18 
Little Kanawha River, WV (ORH) 17-20 
Little Lake Harbor, MI (NCE) 21-20, 21-57, 21-75 
Little Machipongo River, VA (NAO) 5-17 
I-35

Little Manatee River, FL (SAJ) 9-49 
Little Massard Creek, Fort Smith, AR (SWL) 28-22 
Little Miami River, Indian Hill, OH (ORL) 16-35 
Little Miami River, Milford, OH (ORL) 16-35 
Little Miami River, South Lebanon, OH (ORL) 16-37 
Little Missouri River, AR (LMK) 12-16 
Little Missouri River below Murfreesboro, AR (LMK) 
12-18 
Little Neck Bay, NY (NAN) 2-29 
Little Nemaha River, Nemaha County, NE (MRO) 
26-17 
Little Nemaha River, Tangeman, NE (MRO) 26-20 
Little Papillion Creek, NE (MRO) 26-16 
Little Papillion, Little Papillion Creek, NE (MRO) 
26-20 
Little Popo Agie River, Lander, WY (MRO) 26-24 
Little Red River and Tributaries, Clinton, AR (SWL) 
28-7, 28-15, 28-19 
Little Red River, District 1, AR (SWL) 28-22 
Little Red River, White County Road Bridge, 
Judsonia, AR (SWL) 28-22 
Little River (Creek), VA (NAO) 5-17 
Little River, AR (LMK) 12-16 
Little River at Cayuga Island, NY (NCB) 20-40 
Little River Basin, AR (SWL) 28-7, 28-15 
Little River, Belfast, ME (NED) 1-46 
Little River, Cameron, TX (SWF) 30-23 
Little River, DE (NAP) 3-25 
Little River Inlet, NC and SC (SAN) 7-6, 7-11, 7-15 
Little Rock Levee, AR, East End Fourche Bayou, AR 
(SWL) 28-22 
Little Rockfish Creek, Hope Mills, NC (SAW) 6-28 
Little Scooba Creek, MS (SAM) 10-56 
Little Sioux River, Anthon, IA (MRO) 26-21 
Little Sioux River, IA (MRO) 26-3, 26-9, 26-12 
Little Sodus Bay Harbor, NY (NCB) 20-6, 20-18, 
20-32 
Little Sugar Creek, Charlotte, NC (SAW) 6-28 
Little Tallahatchie River, MS (LMK) 12-16 
Little Tennessee River, TN (ORN) 15-13 
Little Valley Wash, Magna, UT (SPK) 35-40 
Little Wabash River, Carmi, IL (ORL) 16-37 
Little Walnut Creek, Austin, TX (SWF) 30-23 
Little Walnut Creek, Mansfield, TX (SWF) 30-23 
Little Walnut Creek, Seguin, TX (SWF) 30-23 
Little Walnut Creek, Springtown, TX (SWF) 30-23 
Little White Oak Bayou, TX (SWG) 31-12 
Little Wicomoco River (NAB) 4-33, 4-38 
Little Wills Creek, AL (SAM) 10-51 
Little Wood River, ID (NPW) 39-16, 39-17 
Little Yankee Creek, Hubbard, OH (reconnaissance) 
(ORP) 18-30 
Littleville Lake, MA (NED) 1-14, 1-30, 1-53 
Liverpool Drainage and Levee District, IL (NCR) 
23-12, 23-15 
Lock and Dam 13, AR (SWT) 29-26 
Lock and Dam No. 1 25-9 
Lock and Dam No. 2 25-9 
Lock and Dam No. 5, AR (SWL) 28-4 
Lock Haven, PA (NAB) 4-11, 4-24, 4-31 
Lock No. 2 and Wilber D. Mills Dam (No. 2), AR 
(SWL) 28-3 
Lockwoods Folly River, NC (SAW) 6-5, 6-19 
Lodgepole Creek, Arvada, CO (MRO) 26-23 
Logan Creek, Bank Protection, Near Bancroft, NE 
(MRO) 26-20 
Logan Creek, Pender, NE (MRO) 26-23 
Logan, OH (ORH) 17-23 
Lone Rock, Buffalo River, AR (SWL) 28-23 
Long Beach Island (NAP) 3-27, 3-28 
Long Branch, Jacksonville, FL (SAJ) 9-61 
Long Branch Lake, Little Chariton River, MO (MRK) 
27-4, 27-11, 27-14 
Long Island Intracoastal W/W, NY (NAN) 2-9, 2-19, 
2-24, 2-28 
Long Lake Area, Helena, AR (LMM) 13-7 
Long Lake Dam, AK (NPA) 40-12 
Long Tom River, OR (NPP) 37-36 
Longboat Pass, FL (SAJ) 9-8, 9-28, 9-37 
Lookout Point-Dexter Lakes, OR (NPP) 37-19, 37-27, 
37-34, 37-43 
Lorain Harbor, OH (NCB) 20-7, 20-18, 20-32 
Lorain Harbor, OH 1960 R&H Act modified by 1930 
R&H Act (NCB) 20-45 
Lorean Branch, Hurst, TX (SWF) 30-23 
Los Angeles and Long Beach Harbors, CA (SPL) 
33-2, 33-12, 33-16 
Los Angeles County Drainage Area, CA (SPL) 33-6, 
33-14, 33-23 
Los Coches Creek, CA (SPL) 33-6, 33-14, 33-25 
Lost Creek at Columbus, NE (MRO) 26-3, 26-9, 
26-12 
Lost Creek, Carbon Hill, AL (SAM) 10-51 
Lost Creek Drainage and Levee District, IL (NCR) 
23-12, 23-15 
I-36

Lost Creek Lake, Rogue River, OR (NPP) 37-19, 
37-27, 37-34, 37-43 
Lost River, MN (NCS) 24-24 
Lost River, Orleans & Orange Counties, IN (ORL) 
16-37 
Louisville, KY (ORL) 16-23, 16-24, 16-29, 16-34 
Louisville, KY (Partial) (ORL) 16-26 
Louisville Lake, IL (Wabash River) (ORL) 16-24, 
16-33 
Loup River, Columbus, NE (MRO) 26-16 
Loves Park, IL (NCR) 23-5, 23-7, 23-10 
Lowell Creek, AK (NPA) 40-12 
Lowell, MA (NED) 1-46, 1-56 
Lower Big Sioux River, IA and SD (MRO) 26-16 
Lower Branch Rush River, ND (NCS) 24-24 
Lower Butte Basin, CA (SPK) 35-43 
Lower Columbia River Basin Bank Protection, OR and 
WA (NPP) 37-13, 37-25, 37-33 
Lower Cowlitz River Area, Clatsop County, OR 
(NPP) 37-37 
Lower Creek, Lenoir, NC (SAW) 6-13, 6-21 
Lower Dry Creek, Lowden, WA (NPW) 39-16 
Lower Fox River, WI (1925 R&H Act) (NCE) 21-87 
Lower Gila River Levee and Channel Improvements 
(Gila River and Tributaries downstream from 
Painted Rock Dam) (SPL) 33-30 
Lower Grand River, MO (MRK) 27-17 
Lower Granite Lock and Dam, WA (NPW) 39-6, 
39-10, 39-13, 39-20, 39-23 
Lower Green River, King County, WA (NPS) 38-9, 
38-17, 38-23 
Lower Guyandotte River Basin, WV (ORH) 17-22 
Lower Heart River, Mandan, ND (MRO) 26-16 
Lower Heart River, ND (MRO) 26-16 
Lower Machodoc Creek, VA (NAB) 4-33 
Lower Mauvais Coulee/Devils Lake, ND (NCS) 24-31 
Lower Mission Creek, CA (SPL) 33-9, 33-15 
Lower Monumental Lock and Dam - Lake Herbert G. 
West, WA (NPW) 39-6, 39-11, 39-14, 39-21, 
39-23 
Lower Rio Grande Basin, TX (SWG) 31-13, 31-21, 
31-36 
Lower San Francisco Bay, CA (SPN) 34-13 
Lower San Joaquin River and Tributaries, including 
Tuolumne and Stanislaus Rivers, CA (SPK) 35-38 
Lower San Joaquin River and Tributaries, CA (SPK) 
35-30 
Lower San Joaquin River, CA (SPK) 35-13, 35-29 
Lower Santa Cruz, AZ (SPL) 33-10, 33-15 
Lower Savannah River (SAS) 8-7 
Lower Snake River Fish and Wildlife Compensation 
Plan, WA, OR and ID (NPW) 39-7, 39-11, 39-14 
Lower Thorofare, Deal Island, MD (NAB) 4-33, 4-38 
Lower Walla Walla River, WA (NPW) 39-17 
Lower Woonsocket, RI (NED) 1-46, 1-53 
Lowes Wharf, MD (NAB) 4-33 
Lowndes County, MS (SAM) 10-56 
Loyalhanna Lake, Ohio River Basin, PA (ORP) 18-7, 
18-14, 18-19, 18-28 
Lubec Channel, ME (NED) 1-42 
Lucky Peak 2nd Outlet, ID (NPW) 39-17 
Lucky Peak Lake, ID (NPW) 39-2, 39-10, 39-13 
Ludington Harbor, MI (NCE) 21-20, 21-57, 21-75 
Ludlow, KY (ORL) 16-26, 16-30 
Ludlow Lake, VT (NED) 1-49 
Lukfata Lake, OK (SWT) 29-24, 29-29 
Lusk Creek, Golconda, IL (ORL) 16-35 
Lutsen Harbor, MN (NCE) 21-84 
Lyford Levee Unit, IN (Wabash River) (ORL) 16-23, 
16-34 
Lyman Creek, ID (NPW) 39-16, 39-18 
Lynches River and Clark Creek, SC (SAN) 7-17 
Lynn Harbor, MA (NED) 1-42 
Lynn Harbor, MA (uncompleted portion) (NED) 1-49 
Lynn-Nahant Beach, MA (NED) 1-45 
Lynnhaven Inlet, VA (NAO) 5-17, 5-19 
Lytle and Warm Creeks, Santa Ana Basin, CA (SPL) 
33-6, 33-14, 33-25 
Lytle Creek, Murfreesboro, TN (ORN) 15-18 
M 
Maalaea Harbor, Maui, HI (POD) 36-2, 36-5, 36-6 
Machias River, Machias, ME (NED) 1-46 
Machias River, ME (NED) 1-42 
Mackay Creek, NC (SAW) 6-26, 6-29 
Mackinac City Harbor, MI (NCE) 21-84, 21-90 
Mackinac Island Harbor, MI (NCE) 21-84 
Macon County, GA (SAS) 8-19 
Macy, Blackbird Creek, NE (MRO) 26-20 
Mad River at Blue Lake, CA (SPN) 34-14 
Mad River Basin, CA (SPK) 35-40 
Mad River, CA (SPN) 34-14 
Mad River Lake, CT (NED) 1-46, 1-53 
Mad River, Waterbury, CT (NED) 1-52 
Mad River, Wolcott, CT (NED) 1-52 
I-37

Madison Bay, MD (NAB) 4-33, 4-38 
Madison, IN (ORL) 16-26, 16-30 
Madison, NE, Union and Taylor Creeks (MRO) 
26-16, 26-20 
Madison River, Quake Lake, MT (MRO) 26-19 
Madisons Parish Port, LA (LMK) 12-16 
Magby Creek, Columbus, MS (SAM) 10-50 
Magpie and Don Julio Creeks, CA (SPK) 35-44 
Magruder Drainage District, Columbia County, OR 
(NPP) 37-37 
Magruder Drainage District, OR (NPP) 37-40 
Mahnomen, MN (NCS) 24-29 
Mahoning Creek Lake, Ohio River Basin, PA (ORP) 
18-7, 18-14, 18-19, 18-28 
Mahoning River, Hwy. 139a, Trumbull County, OH 
(construction completed) (ORP) 18-30 
Mahukona (North Kohala), Hawaii, HI (POD) 36-11 
Maiden Creek Reservoir, PA (NAP) 3-28 
Main Street, Wellsburg, WV (construction) (ORP) 
18-30 
Maintenance and Repair Fleet and Marine Terminals, 
AR (SWL) 28-4 
Malden River, MA (NED) 1-42 
Malheur Improvement District, Snake River, OR 
(NPW) 39-16 
Malheur Lake Project, OR (NPW) 39-16 
Malheur River, OR (NPW) 39-17 
Malheur River, OR Vale Unit (NPW) 39-18 
Maline Creek, MO (LSM) 14-5, 14-12 
Mamaroneck Harbor (NAN) 2-28, 2-29 
Manasquan River, NJ (NAP) 3-25 
Manatee County, FL (SAJ) 9-50 
Manatee County, FL (SAJ) 9-17, 9-31, 9-46 
Manatee Harbor, FL (SAJ) 9-8, 9-28, 9-37 
Manatee River, FL (SAJ) 9-49 
Manchester Harbor, MA (NED) 1-49 
Manchester, OH (ORH) 17-22 
Mandan, Heart River, ND (MRO) 26-16, 26-19 
Manele Bay Small Boat Harbor, Lanai, HI (POD) 36-7 
Manhasset Creek, NJ (NAN) 2-34 
Manhattan, Kansas River, KS (MRK) 27-17, 27-20 
Maniece Bayou, AR (LMK) 12-19, 12-21 
Manistee Harbor, MI (NCE) 21-20, 21-57, 21-75 
Manistique Harbor, MI (NCE) 21-21, 21-58, 21-76 
Manitowoc Harbor, WI (1962 R&H Act) (NCE) 21-87 
Manitowoc Harbor, WI (NCE) 21-21, 21-58, 21-76 
Mankato and North Mankato, MN (NCS) 24-9, 24-19, 
24-29 
Mann's Harbor, NC (SAW) 6-29 
Manokin River, MD (NAB) 4-33 
Mansfield Hollow Lake, CT (NED) 1-21, 1-33, 1-57 
Manteo (Shallowbag) Bay, NC (SAW) 6-6, 6-20 
Mantua Creek, NJ (NAP) 3-25 
Maple Creek, East Fork, Howells, NE (MRO) 26-23 
Maple Creek, Nickerson, NE (MRO) 26-23 
Maple River, ND (NCS) 24-26, 24-29 
Mapleshade, OH (ORH) 17-22 
Maquoketa River County Road 47 Bridge, IA (NCR) 
23-16 
Marblehead Harbor, MA (NED) 1-49 
Marengo County, AL (SAM) 10-56 
Marengo, IA (NCR) 23-12, 23-15 
Marginal Way, Ogunquit, ME (NED) 1-46 
Marietta, OH (ORH) 17-22 
Marina Del Rey, CA (SPL) 33-2, 33-12, 33-19 
Marion County Drainage District, MO (NCR) 23-12, 
23-15 
Marion, IN (Wabash River) (ORL) 16-26, 16-33 
Marion, KS (SWT) 29-24, 29-27 
Marion Reservoir, KS (SWT) 29-7, 29-16, 29-22 
Mariposa, CA (SPK) 35-42 
Markham Ferry Lake, OK (SWL) 28-28 
Marmarth, ND (MRO) 26-16, 26-19 
Marne Creek, Yankton, SD (MRO) 26-19 
Marquette Harbor, MI (NCE) 21-22, 21-58, 21-76 
Marsh Creek, Geneva, NY (NCB) 20-42 
Marshall, MN (NCS) 24-9, 24-19, 24-29 
Marshalltown, IA (NCR) 23-12, 23-15 
Marshland Drainage District, Columbia County, OR 
(NPP) 37-37 
Martin County, FL (SAJ) 9-46 
Martin Creek, Prentiss County, MS (SAM) 10-50 
Martin, KY (ORH) 17-21 
Martins Creek, Unicoi County, TN (ORN) 15-18 
Martins Ferry, OH (ORP) 18-24 
Martins Fork Lake, KY (ORN) 15-4, 15-9, 15-17 
Martis Creek Lake, Martis Creek, NV and CA (SPK) 
35-14, 35-29 
Mary's Creek, Fort Worth and Benbrook, TX (SWF) 
30-23 
Marysville, KS (MRK) 27-18 
Marysville Lake, CA (SPK) 35-38 
Masefau Bay, American Samoa (POD) 36-8 
Mason and Menard Drainage District, IL (NCR) 
23-12, 23-15 
Mason County (Various Locations), WA (NPS) 38-27 
I-38

Mason Creek, NC (SAW) 6-32 
Mason J. Niblack Levee, (Wabash River) (ORL) 
16-23, 16-29, 16-34 
Mason, WV (ORH) 17-22 
Massillon, OH, (ORH) 17-6, 17-13, 17-18 
Matafao Shoreline, American Samoa (POD) 36-8 
Matagorda Ship Channel, TX (SWG) 31-7, 31-20, 
31-31, 31-41, 31-46 
Matawan Creek (NAN) 2-28, 2-29, 2-34 
Matinicus Harbor, ME (NED) 1-42 
Mats Mats Bay, WA (NPS) 38-25, 38-31 
Mattapoiset Harbor, MA (NED) 1-49 
Mattaponi River, VA (NAO) 5-17 
Mattituck Harbor, NY (NAN) 2-29 
Mauckport, IN (ORL) 16-26, 16-30 
Maumee Bay State Park, OH (NCB) 20-11, 20-21, 
20-37 
Maumee River, above Toledo, OH 1872 Act (NCB) 
20-45 
Maumee River, Providence Metropark, OH (NCB) 
20-44 
Maumee River, Wallbridge Park, OH (NCB) 20-44 
Maunalua Bay Small Boat Harbor, Oahu, HI (POD) 
36-10 
Maurice River, NJ (NAP) 3-25 
Maurice River, NJ-Channel 8 feet deep, Delaware Bay 
to mouth 3-26 
Maurice River, NJ, Millville fixed bridge to upper end 
of project (NAP) 3-28 
Mauvaise Terre Drainage and Levee District, IL 
(LSM) 14-13, 14-16 
Maxwell Creek, Parker County, TX (SWF) 30-23 
Mayaguez Harbor, PR (SAJ) 9-9, 9-28, 9-37, 9-51 
Maynard Bayou, Muskogee County, OK (SWT) 29-27 
Maynor Creek State park, Wayne, MS (SAM) 10-51 
Maysville, KY (ORH) 17-21, 17-24 
Mazon River, Goose Lake, Grundy County, IL 
McClellan-Kerr Arkansas River Bank Stabilization and 
Channel Recertification, AR (SWL) 28-3, 28-14, 
29-26 
McClellan-Kerr Arkansas River Navigation System, 
OK (SWT) 29-2, 29-13, 29-20, 29-26 
McCook and Thorton Reservoirs, IL (NCC) 22-9, 
22-14, 22-18 
McCook Lake, SD (MRO) 26-16 
McDonald Dike Road, Nehalem River, OR (NPP) 
37-38 
McGary Hollow Run, Weston, WV (reconnaissance) 
(ORP) 18-30 
McGee Creek Drainage and Levee District, IL (LSM) 
14-13, 14-16 
McGinnis Levee, IN (ORL) 16-26, 16-30 
McGrath Creek, Wichita Falls, TX (SWT) 29-24, 
29-30 
McGregor Park, Montgomery County, TN (ORN) 
15-18 
McKees Rocks, PA (ORP) 18-24 
McKenzie River Near Walterville, OR (NPP) 37-38 
McKinney Bayou, AR (LMK) 12-19 
McKinney Bayou, Finn Bayou Segment, AR (LMK) 
12-23 
McLean Bottom Levee District No. 3, Arkansas 
River, AR (SWL) 28-22 
McNary Lock and Dam - Lake Wallula, OR and WA 
(NPW) 39-7, 39-11, 39-14, 39-22 
McNary Second Powerhouse, OR & WA (NPW) 
39-17 
Meadow Grove, Buffalo Creek, NE (MRO) 26-20 
Medicine Knoll, Blunt, SD (MRO) 26-23 
Medomak River, ME (NED) 1-42 
Meherrin River, VA (NAO) 5-17 
Mekorykuk, AK (NPA) 40-11 
Melbourne Harbor, FL (SAJ) 9-9, 9-28, 9-37, 9-51 
Melvern Lake and Pamona Lake (Road 
Improvements), KS (1974 Act) (MRK) 27-18, 
27-20 
Melvern Lake, Marais des Cygnes (Osage) River, KS 
(MRK) 27-5,, 27-14 27-11, 27-20 
Melvin Price Locks & Dam (Formerly Lock and Dam 
No. 26 (Replacement)) (LSM) 14-11 
Memphis, Wolf River, and Nonconnah Creek, TN 
(LMM) 13-6 
Menemsha Creek, MA (NED) 1-42 
Menominee Harbor and River, MI and WI (NCE) 
21-23, 21-58, 21-76 
Meramec Park Lake, MO (LSM) 14-18 
Meramec River Basin Valley Park, MO (LSM) 14-5, 
14-9, 14-13 
Merced County Stream Group, CA (SPK) 35-15, 
35-29, 35-42 
Merced County Streams, CA (SPK) 35-14, 35-29 
Merced River, CA (SPK) 35-38 
Mercer Lake, Weldon River, MO (MRK) 27-17 
Meredosia Lake and Willow Creek Drainage and 
Levee District, IL (LSM) 14-16 
I-39

Meredosia Levee and Drainage District, IL (NCR) 
23-12, 23-15 
Merkle Creek, Norman, OK (SWT) 29-27 
Mermentau River, Bayou Nezpique, and Bay Des 
Cannes, LA (LMN) 11-15 
Mermentau River, LA (LMN) 11-15 
Merriam, Turkey Creek, KS (MRK) 27-18 
Merriconeag Sound, Harpswell, ME (NED) 1-46 
Merrimack River Basin, NH and MA (NED) 1-18 
Merrimack River, MA (NED) 1-42 
Metamora Lake, IN (ORL) 16-27, 16-32 
Methow River, Barclay Canal, WA (NPS) 38-27 
Methow River, State Highway No. 16 Bridge, Twisp, 
WA (NPS) 38-27 
Methow River, Twisp-Carlton Highway, Vicinity of 
Twisp, WA (NPS) 38-27 
Methow River, Vicinity of Pateros, WA (NPS) 38-27 
Methow River, WA (NPS) 38-27, 38-30 
Metlakatla Harbor, AK (NPA) 40-3, 40-7, 40-9 
Metropolis, IL (ORL) 16-26, 16-30 
MFS, Howard Complex, Cranston, RI (NED) 1-59 
Miami and Vicinity, OK (SWT) 29-29 
Miami Harbor, FL (SAJ) 9-9, 9-29, 9-38, 9-51 
Miami River Basin, Pleasant Run, Vicinity Fairfield, 
OH (ORL) 16-20, 16-24 
Miami River, OR (NPP) 37-38 
Mianus River, CT (NED) 1-42 
Michael J. Kirwan Dam and Reservoir, Ohio River 
Basin, OH (ORP), 18-8, 18-14, 18-19, 18-28 
Michigan City Harbor, IN (NCC) 22-5, 22-13, 22-17, 
22-19 
Middle Beach, CT (NED) 1-45 
Middle Creek, CA (SPK) 35-38 
Middle Gila River Channel Improvements, upper end 
of Safford Valley to Buttes damsite (Camelsback 
damsite to Salt River) (SPL) 33-30 
Middle Pebble Creek, Snyder, NE (MRO) 26-20 
Middle Penn, Orangeburg County, SC (SAN) 7-18 
Middle Rio Grande Flood Protection, Bernalillo to 
Belen, NM (SWA) 32-7, 32-14, 32-17 
Middle River and Dark Head Creek, MD (NAB) 4-33 
Middle River at Argyle, MN (NCS) 24-10, 24-19, 
24-30 
Middle School, Wellsburg, WV (construction) (ORP) 
18-30 
Middleport, OH (ORH) 17-22 
Middlesboro (Diversion Canal) KY (ORN) 15-18 
Middlesboro (Yellow Creek), KY (ORN) 15-13, 
15-14, 15-18 
Middlesboro, Cumberland River Basin, KY (ORN) 
15-5, 15-9 
Midland Drainage District, Columbia County, OR 
(NPP) 37-37 
Midland Drainage District, OR (NPP) 37-38 
Milan, IL (NCR) 23-12, 23-15 
Miles City, MT (MRO) 26-16 
Milford Harbor, CT (NED) 1-42, 1-58 
Milford Harbor, CT (uncompleted portion) (NED) 
1-49 
Milford Lake, Republican River, KS (MRK) 27-5, 
27-11, 27-14, 27-20 
Milk River, Havre, MT (MRO) 26-17 
Milk River, Malta, MT (MRO) 26-19, 26-23 
Mill Brook, Brownsville, VT (NED) 1-46, 1-54 
Mill Brook-Highland Park, NJ (NAN) 2-35 
Mill Creek, City of Moab, UT (SPK) 35-44 
Mill Creek, Dalton, GA (SAM) 10-17, 10-35, 10-46 
Mill Creek, Fort Smith, AR (SWL) 28-7, 28-15 
Mill Creek, Jefferson County, KY (ORL) 16-23, 
16-35 
Mill Creek Lake, WA (NPW) 39-3, 39-10, 39-13 
Mill Creek Levees (SPL) 33-31 
Mill Creek, Mcgee, MS (SAM) 10-51 
Mill Creek, MD (NAB) 4-37 
Mill Creek, NC (SAW) 6-29, 6-32 
Mill Creek, OH (ORH) 17-23 
Mill Creek, OH (ORL) 16-4, 16-14 
Mill Creek, Salem, OR (NPP) 37-14, 37-25, 37-33, 
37-42 
Mill Creek, Sumrall, MS (SAM) 10-17, 10-35, 10-46 
Mill Creek, TX (SWG) 31-38 
Mill Creek, VA (NAO) 5-17 
Mill Creek, WA (NPW) 39-17, 39-18 
Mill Creek, Yarmouth, MA (NED) 1-51 
Mill Four Drainage District, Yaquina River, OR 
(NPP) 37-38 
Mill Lake, Blue River, MO (MRK) 27-18 
Mill Run, Sinclairville, NY (plans and specifications) 
(ORP) 18-30 
Miller, OH (ORH) 17-22 
Miller Pond Drainage District, IL (LSM) 14-16 
Miller Run, Cecil Township, PA (detalied project 
report underway) (ORP) 18-30 
Millers Ferry Lock and Dam, AL (SAM) 10-25, 10-37 
Millersburg, OH (ORH) 17-23 
I-40

Millford Haven, VA (NAO) 5-17 
Millican, TX (SWF) 30-22 
Millington, TN (LMM) 13-2, 13-4 
Millwood Lake, AR (SWL) 28-8, 28-16, 28-29 
Millwood, WV (ORH) 17-22 
Milton Harbor (NAN) 2-28, 2-30 
Milton, KY (ORL) 16-26, 16-30 
Milton, PA (NAB) 4-38 
Milwaukee Harbor, WI (NCE) 21-23, 21-59, 21-77 
Milwaukee Outer Harbor, WI (1935 R&H Act) (NCE) 
21-87 
Mineral Creek, Lewis County, WA (NPS) 38-27 
Mines Creek, Spring Valley, WI (NCS) 24-29 
Mingo Creek, OK (SWT) 29-7, 29-17, 29-22 
Mingo Creek, SC (SAN) 7-17 
Mingo Junction, OH (ORP) 18-24 
Mining City Lake, KY (Green River) (ORL) 16-24, 
16-32 
Minneota, MN (NCS) 24-24, 24-29 
Minnesota River at Henderson, MN (NCS) 24-10, 
24-19, 24-30 
Minnesota River at LeSueur, MN (NCS) 24-24 
Minnesota River, MN (NCS) 24-2, 24-18, 24-22, 
24-30 
Minot, ND (NCS) 24-24 
Mispillion River, DE (NAP) 3-7, 3-17, 3-22 
Misquamicut Beach, Westerly, RI (NED) 1-45 
Mission and Lapwai Creeks, ID (NPW) 39-16 
Mission Beach, CA (SPL) 33-29 
Missisquoi River at Richford, VT (NAN) 2-32 
Mississinewa Lake, IN (ORL) 16-9, 16-16 
Mississippi and Leech Rivers, MN (NCS) 24-23 
Mississippi River Agricultural Area 8, MO (LSM) 
14-16 
Mississippi River Agricultural Area No. 10, MO 
(LSM) 14-18 
Mississippi River Agricultural Area No. 12, MO 
(LSM) 14-16 
Mississippi River at Alton, IL Small Boat Harbor 
(LSM) 14-18 
Mississippi River at St. Louis, MO (LSM) 14-16 
Mississippi River Baton Rouge to Gulf of Mexico, LA 
(LMN) 11-12, 11-16 
Mississippi River Between Brainerd and Grand Rapids, 
MN (NCS) 24-23 
Mississippi River Between the Missouri River and 
Minneapolis, MN (NCS) 24-2 
Mississippi River Between the Missouri River and 
Minneapolis, MN (Includes Melvin Price Locks & 
DAM) (LSM) 14-2 
Mississippi River Between the Missouri River and 
Minneapolis, MN 25-1, 25-10 
Mississippi River Between the Missouri River and 
Minneapolis, MN (NCR) 23-3 
Mississippi River betwen Ohio and Missouri Rivers, 
MO and IL (LSM) 14-2, 14-9, 14-11 
Mississippi River Commission 42-1 
Mississippi River, First Avenue, Hampton IL (NCR) 
23-16 
Mississippi River, Fridley, MN (NCS) 24-30 
Mississippi River-Gulf Outlet, LA (LMN) 11-2, 
11-10, 11-12 
Mississippi River-Gulf Outlet, Michoud Canal, LA 
(LMN) 11-16 
Mississippi River near Aitkin, MN (NCS) 24-24, 
24-29 
Mississippi River Outlets, Venice, LA (LMN) 11-16 
Mississippi River Ship Channel, Gulf to Baton Rouge, 
LA (LMN) 11-2, 11-10, 11-12 
Missoula (Sewage Treatment Plant), MT (NPS) 38-27 
Missouri National Recreational River, NE and SD 
(MRO) 26-3, 26-9, 26-12 
Missouri River at New Haven, MO (Sec 212, 1950 
Act) (MRK) 27-17 
Missouri River, Aten, NE (MRO) 26-16 
Missouri River, Bank Protection, Greenwood, SD 
(MRO) 26-19 
Missouri River, Bank Stabilization, Fort Benton, MT 
(MRO) 26-19 
Missouri River Fish and Wildlife Mitigation, IA, NE, 
KS and MO (MRK) 27-2, 27-10, 27-13 
Missouri River, Garrison Dam to Lake Oahe, ND 
(MRO) 26-18 
Missouri River, Kenslers Bend, NE to Sioux City, IA 
(MRO) 26-4, 26-10, 26-12 
Missouri River Levee System, IA, NE, KS and MO 
(Kansas City District) (MRK) 27-5, 27-11, 27-14, 
27-18, 27-19, 27-20 
Missouri River Levee System, Sioux City, IA to Rulo, 
NE (MRO) 26-4, 26-18 
Missouri River Levees, IA, NE, KS and MO (MRO) 
26-10, 26-12, 26-18, 26-21 
Missouri River Main Stem (MRK) 27-20 
Missouri River, Marina, Sioux City, IA (MRO) 26-21 
1-41

Missouri River Master Water Control Review and 
Update (MRO) 26-7, 26-11, 26-14 
Missouri River, Niobrara, NE (MRO) 26-16 
Missouri River, Sioux City, IA to Mouth (MRK) 27-2, 
27-10, 27-13 
Missouri River, Sioux City, IA (MRO) 26-2, 26-9, 
26-12 
Missouri River, Sioux City, IA to Fort Benton, MT 
(MRO) 26-15 
Mitigation of Shore Damages 
Detroit District (NCE) 21-39 
Mobile Harbor, AL (SAM) 10-10, 10-34, 10-43 
Mocassin Swamp, NC (SAW) 6-29 
Moccasin Springs, MO (LSM) 14-15 
Moclips River, Moclips, WA (NPS) 38-27 
Mojave River Dam, Mojave River Basin, CA (SPL) 
33-6, 33-14, 33-25 
Molalla River at Milk Creek Location, OR (NPP) 
37-38 
Molalla River at Ressel Location, OR (NPP) 37-38 
Moline Harbor, IL 25-7 
Moline, IL (NCR) 23-13 
Mon River, Sewage Treatment Plant, Pt. Marion, PA 
(detalied project report underway) (ORP) 18-30 
Mon River, Water St., Pt. Marion, PA (detalied 
project report underway) (ORP) 18-30 
Moncreif Creek, Jacksonville, FL (SAJ) 9-61 
Monona-Harrison Ditch Control, Monona County, IA 
(MRO) 26-21 
Monongahela River, PA and WV (ORP) 18-2, 18-13, 
18-17, 18-26, 18-27, 18-28 
Monoosnoc Brook, MA (NED) 1-49 
Monoosnoc Lake, MA (NED) 1-49 
Monroe and West Monroe Parish, LA and Ouachita 
Parish, LA (LMK) 12-13 
Monroe Bay and Creek, VA (NAB) 4-33, 4-38 
Monroe County, AL (SAM) 10-56 
Monroe County, FL (SAJ) 9-46 
Monroe County, IA (NCR) 23-16 
Monroe County, MS (SAM) 10-56 
Monroe Harbor, MI (NCE) 21-24, 21-59, 21-77 
Monroe, LA, floodwall extension (Plan B) (LMK) 
12-18, 12-21 
Monroe Lake, IN (ORL) 16-9, 16-16, 16-32 
Montcalm, WV (ORH) 17-24 
Monterey Harbor, CA (SPN) 34-13 
Montgomery County, AL (SAM) 10-56 
Montour Falls, Oswega River Basin, NY (NCB) 20-42 
Moore, OK (SWT) 29-29 
Moorefield, WV (NAB) 4-37 
Moores Ferry, VA (ORH) 17-23 
Moorhead, MN (NCS) 24-26 
Mooring for Battleship Oregon, OR (NPP) 37-36 
Moosabec Bar, ME (NED) 1-42 
Morais River, ND (NCS) 24-30 
Moravian Creek, Wilksboro, NC (SAW) 6-32 
Morehead City Harbor, NC (SAW) 6-7, 6-20 
Morehead City Harbor, NC Jetties at Beaufort Inlet 
(SAW) 6-29 
Morgan City and Vicinity, LA (Hurrican protection) 
(LMN) 11-6, 11-11, 11-14 
Moriches Inlet, NY (NAN) 2-30 
Mormon Slough, CA (SPK) 35-38 
Morris Cove, New Haven, CT (NED) 1-51 
Morrison, Bear Creek, CO (MRO) 26-17 
Morristown Harbor, NY (NCB) 20-40 
Morro Bay Harbor, CA (SPL) 33-3, 33-12, 33-20 
Moscow, OH (ORL) 16-27, 16-30 
Mosquito Creek Lake, Ohio River Basin, OH (ORP) 
18-8, 18-14, 18-20, 18-28 
Mott, ND (MRO) 26-16 
Moss Street, Pecan Creek, Gainsville, TX (SWF) 
30-23 
Mound State Park, Moundville, AL (SAM) 10-18, 
10-35, 10-41 
Mounds and Mound City, Ohio River Basin, IL 
(LMM) 13-6 
Moundsville, WV (ORP) 18-24 
Mount Carmel, IL (Wabash River) (ORL) 16-23, 
16-34 
Mount Clemens, Clinton River, MI (NCE) 21-85 
Mount Morris Lake, NY Genesee River (NCB) 20-13, 
20-22, 20-38 
Mount St. Helens and Vicinity, WA (NPP) 37-38 
Mount Vernon, IN (ORL) 16-24 
Mountain Brook Dam, NH (NED) 1-49 
Mountain Point, AK (NPA) 40-3, 40-7, 40-13 
Mouth of Yazoo River, MS (LMK) 12-16 
Moycock Creek, NC (SAW) 6-29 
Mt. Baldy, Indiana Dunes National Lakeshore, IN 
(NCC) 22-20 
Mt. Holly, NJ (NAP) 3-27 
Mt. St. Helens Sediment Control, WA (NPP) 37-14, 
37-25, 37-33 
Mucky creek, Mapleton, IA (MRO) 26-21 
I-42

Mud and Basket Slough Rickreall Creek, OR (NPP) 
37-40 
Mud Creek, Broken Bow, NE (MRO) 26-16 
Mud Lake Area, ID (NPW) 39-17, 39-18 
Mud Mountain Dam, WA (NPS) 38-9, 38-17, 38-23 
Mud River, WV (ORH) 17-23 
Muddy Creek, Cascade, Vaughn, MT (MRO) 26-24 
Muddy Creek Dam, PA (ORP) 18-24 
Muddy Creek Near Syracuse, NE (MRO) 26-20 
Muddy Hook and Tyler Coves, MD (NAB) 4-33 
Mulberry Creek, VA (NAO) 5-17 
Multiple-Purpose Projects Including Power in 
Operation F-i 
Multiple Purpose Projects, Including St. Marys River, 
MI (NCE) 21-85 
Multnomah Channel, OR (NPP) 37-36 
Multnomah County Drainage District 1, OR (NPP) 
37-38 
Multnomah Drainage District 1, OR (NPP) 37-37 
Muncie, IN (White River) (ORL) 16-23, 16-34 
Munday, TX (SWF) 30-22 
Murder and Burnt Corn Creeks, Brewton, AL (SAM) 
10-50, 10-51 
Murder Creek, Brewton, AL (SAM) 10-18, 10-35, 
10-46 
Murder Creek, East Brewton, AL (SAM) 10-50 
Murder-Goose Neck Creek, Corfu, NY (NCB) 20-43 
Murder-Goose Neck Creek, Pembroke, NY (NCB) 
20-43 
Murderkill River, DE (NAP) 3-7, 3-17, 3-22 
Murfreesboro Dam and Lake (LMK) 12-21 
Murray County, GA (SAM) 10-56 
Murray Lock and Dam (No. 7), AR (SWL) 28-4 
Murrells Inlet, SC (SAN) 7-6, 7-11, 7-15 
Muscatatuck River, Crothersville, IN (ORL) 16-35 
Muscatine Harbor, IA (NCR) 23-11 
Muscatine Harbor, IA 25-7 
Muscatine Island, IA (NCR) 23-8, 23-10 
Muscatine Island Levee District and Muscatine-Louisa 
County, 
Muscatine, Mad Creek, IA (NCR) 23-12, 23-14 
Muscooten Bay, Illinois River, IL (NCR) 23-11 
Muskegon Harbor, MI (NCE) 21-25, 21-60, 21-77 
Muskingum River Lakes, OH (ORH) 17-7, 17-14, 
17-18 
Muskingum River, OH (OIRH) 17-20 
Muskogee, OK (SWT) 29-27 
Mustinka River, MN (NCS) 24-28 
Myers Chuck Harbor, AK (NPA) 40-11, 40-12 
Mystic, CT (NED) 1-49 
Mystic River, CT (NED) 1-42 
Mystic River, CT (uncompleted portion) (NED) 1-49 
Mystic River, MA (NED) 1-42 
N 
N. Fork, Maquoketa River, Cascade, IA (NCR) 23-16 
Naches River, Naches, WA (NPS) 38-27 
Nagel D.D., Little Sioux River, IA (MRO) 26-20 
Naguabo River, PR (SAJ) 9-61 
Nahunta Swamp, NC (SAW) 6-29 
Naknek River, AK (NPA) 40-11 
Nameless Creek, County Road 850 N, IN (ORL) 
16-37 
Namo River, Guam (POD) 36-9 
Nan Cove, MD (NAB) 4-33, 4-38 
Nandua Creek, VA (NAO) 5-17 
Nanpil River Hydropower, Pohnpei, Federated States 
of Micronesia (POD) 36-3, 36-5, 36-6 
Nansemond River, VA (NAO) 5-17, 5-19 
Nantasket Beach, Hull, MA (NED) 1-52 
Nantasket Beach, MA (NED) 1-49 
Nanticoke River (Including Northwest Fork), DE and 
MD (NAB) 4-33 
Nanticoke River at Bivalve, MD (NAB) 4-33, 4-38 
Nanticoke River, MD (NAB) 4-5, 4-22, 4-28 
Nantucket (Harbor of Refuge), MA (NED) 1-42 
Nantucket, Harbor of Refuge, MA (uncompleted 
portion) (NED) 1-49 
Nantucket, Harbor of Refuge, MA (inactive portion) 
(NED) 1-49 
Napa River Basin, CA (SPK) 35-38 
Napa River, CA (SPK) 35-26, 35-34 
Napa River, CA (SPN) 34-7 
Napatree Beach, RI (NED) 1-49 
Narragansett Pier, RI (NED) 1-50 
Narraguagus River, ME (NED) 1-42, 1-58 
Narrows Dam-Lake Greeson, AR (LMK) 12-18, 12-21 
Narrows of Lake Champlain, NY & VT (NAN) 2-9, 
2-19, 2-24 
Nashua, NH (NED) 1-46, 1-56 
Nassau County, FL (SAJ) 9-18, 9-31, 9-46 
Natches Port Area, MS (LMK) 12-21 
Natchitoches Parish, LA (LMK) 12-20 
National Emergency Preparedness 
Buffalo District (NCB) 20-13 
I-43

Chicago District (NCC) 22-6 
Kansas City District) (MRK) 27-7, 27-12 
Mobile District (SAM) 10-31 
Omaha District (MRO) 26-8 
Philadelphia District (NAP) 3-14 
Natural Disaster Preparedness, Response & Recovery 
Activities 52-1 
Navarro Mills Lake, TX (SWF) 30-8, 30-16, 30-20 
Navasota Lake Navasota River, TX (SWF) 30-22 
Navigation Activities Pursuant to Section 107, Public 
Law 86-645 (Preauthorization) 
New England Division (NED) 1- 
Navigation Locks and Dams Operable D-1 
Navigation Projects Under Construction E-1 
Navigation Work Under Special Authorization 
Baltimore District (NAB) 4-8 
Buffalo District (NCB) 20-11 
Charleston District (SAN) 7-8 
Detroit District (NCE) 21-38 
Galveston District (SWG) 31-10 
Jacksonville District (SAJ) 9-16 
Louisville District (ORL) 16-3 
Little Rock District (SWL) 28-4 
Memphis District (LMM) 13-1 
Mobile District (SAM) 10-15 
Nashville District (ORN) 15-4 
New Orleans District (LMN) 11-3 
New York District (NAN) 2-14 
Norfolk District (NAO) 5-7, 5-11 
Omaha District (MRO) 26-2 
Pacific Ocean Division (POD) 36-2 
Portland District (NPP) 37-6 
San Francisco District (SPN) 34-5 
Savannah District (SAS) 8-5 
Seattle District (NPS) 38-5 
St. Louis District (LSM) 14-3 
Vicksburg District (LMK) 12-3 
Walla Walla District (NPW) 39-1 
Nawiliwili Deep Draft Harbor, Kauai., HI (POD) 
36-10 
Nawiliwili Harbor, Kauai, HI (POD) 36-7 
Nawiliwili Small Boat Harbor, Kauai, HI (POD) 36-7 
Neabsco Creek, MD (NAB) 4-33 
Neabsco Creek, VA (1811 River & Harbor Act) 
(NAB) 4-37 
Neah Bay, Clallam County, WA (NPS) 38-27 
Neah Bay, WA (NPS) 38-25 
Neale Sound, MD (NAB) 4-33 
Near Dardanelle, Arkansas River, AR (SWL) 28-22 
Near Springfield on Sangamon River, IL (NCR) 23-12 
Neavitt Harbor, MD (NAB) 4-33 
Neches River and Tributaries, Salt Water Barrier to 
Beaumont, TX (SWG) 31-38 
Needles, San Bernardino, CA (SPL) 33-30 
Nehalem Bay, OR (NPP) 37-41 
Nehalem Bay, OR (NPP) 37-36 
Nehalem River, Sunset Drainage District, OR (NPP) 
37-42 
Nelson Run, Ross Township, PA (detalied project 
report underway) (ORP) 18-30 
Neodesha Lake, KS (SWL) 28-28 
Neodesha Lake, KS (SWT) 29-25, 29-26 
Neon-Fleming, KY (Kentucky River) (ORL) 16-23, 
16-35 
Neshaminy State Park Harbor, PA (NAP) 3-25 
Neshannock Creek, New Castle, PA (terminated) 
(ORP) 18-30 
Nestucca River, Condor Road, OR (NPP) 37-38 
Nestucca River, OR (NPP) 37-36 
Nestucca River, Vicinity Pacific City, OR (NPP) 
37-38 
Neuse River, 300-foot wide channel in front of New 
Bern, NC (SAW) 6-29 
Neuse River Barrier, NC (SAW) 6-29 
Neuse River Basin, NC (SAW) 6-12, 6-31 
Neuse River, NC (SAW) 6-29 
Neuse River, Oriental, NC (SAW) 6-14, 6-21, 6-26 
Neva and Olga Straits, AK (NPA) 40-11 
Neville Island, PA (ORP) 18-24 
New Albany, IN (ORL) 16-23, 16-29, 16-34 
New Amsterdam, IN (ORL) 16-27, 16-30 
New Bedford and Fairhaven Harbors, MA (NED) 
1-42 
New Bedford and Fairhaven Harbors, MA 
(uncompleted portion) (NED) 1-50 
New Bedford, Fairhaven, and Acushnet, MA (NED) 
1-19, 1-32, 1-39 
New Buffalo Harbor, MI (NCE) 21-25, 21-60, 21-77 
New Bullards Bar, CA (SPK) 35-38 
New Cumberland, WV (ORP) 18-24 
New Harbor, ME (NED) 1-42 
New Harmony Bridge, IL & IN (Wabash River) 
(ORL) 16-23, 16-24, 16-29 
New Harmony, IN (ORL) 16-27, 16-30 
New Haven Breakwater, CT (NED) 1-42 
New Haven Harbor, CT (NED) 1-42, 1-58 
I-44

New Haven Harbor, CT (uncompleted portion) (NED) 
1-50 
New Jersey Intercoastal Waterway (NAP) 3-8, 3-17, 
3-22 
New Kensington and Parnassus, PA (ORP) 18-24 
New London, CT (NED) 1-20, 1-32, 1-39 
New London Harbor, CT (NED) 1-42 
New Madrid Harbor, MO (LMM) 13-5 
New Martinsville, WV (ORH) 17-22 
New Matamoras, OH (ORH) 17-22 
New Melones Lake, CA (SPK) 35-23 
New Metlakatla Harbor, AK (NPA) 40-13 
New Orleans to Venice, LA (Hurrican protection) 
(LMN) 11-7, 11-11, 11-14 
New Pass, Sarasota, FL (SAJ) 9-10, 9-29, 9-39 
New Richmond, OH (ORL) 16-27, 16-30 
New River, FL (SAJ) 9-49 
New River, NC (SAW) 6-28 
New River, Onslow County, NC (SAW) 6-28 
New River, WV and VA (ORH) 17-20 
New Rochelle Harbor, NY (NAN) 2-30 
New York and New Jersey Channels (NAN) 2-9, 
2-19, 2-24, 2-34 
New York Harbor-Collection and Removal of Drift 
(NAN) 2-10, 2-20, 2-24 
New York Harbor-Entrance Channels and Anchorage 
Areas (NAN) 2-11, 2-20, 2-25 
New York Harbor-Main Ship Channel (NAN) 2-28 
Newark Bay (NAN) 2-28 
Newark Bay, Hackensack & Passaic Rivers, NJ 
(NAN) 2-30, 2-34 
Newark, OH (Interior Drainage) (ORH) 17-21 
Newark, OH (ORH) 17-7, 17-14, 17-18, 17-24 
Newaukum River, Lewis County, Hamilton, WA 
(NPS) 38-27 
Newbegun Creek, NC (SAW) 6-26 
Newburgh, IN (Ohio River) (ORL) 16-23 
Newburyport Harbor, MA (NED) 1-7, 1,27, 1-37 
Newburyport Harbor, MA (uncompleted portion) 
(NED) 1-50 
Newmarket Creek, VA (NAO) 5-18 
Newport Bay Harbor, CA (SPL) 33-28 
Newport Harbor, RI (NED) 1-42 
Newport, KY (ORL) 16-23, 16-29, 16-34 
Newport News Creek, VA (NAO) 5-4, 5-10, 5-14, 
5-17 
Newport, OH (ORH) 17-22 
Newport, OR (NPP) 37-41 
Newport, White River, AR (SWL) 28-22 
Newport-Wilder, KY (ORL) 16-27 
Newt Graham Lock and Dam (18), OK (SWT) 29-26 
Newtown Creek (NAN) 2-28, 2-30 
Niagara Remedial Works, NY (NCB) 20-40 
Niagara River, Compensating Works, 1930 R&H Act 
(NCB) 20-45 
Niagara River, NY (NCB) 20-40 
Niantic Bay and Harbor, CT (NED) 1-42 
Nicholasville (Town Fork) Vicinity, KY (ORL) 16-35 
Nichols, NY (NAB) 4-35, 4-38 
Nimrod Lake, AR (SWL) 28-8, 28-16, 28-28 
Nine Mile Drain, Scottsbluff, NE (MRO) 26-23 
Ninilchik Harbor, AK (NPA) 40-3, 40-7, 40-9 
Niobrara River (Carns Bridge), NE (MRO) 26-24 
Niobrara River, Bassett, NE (MRO) 26-20 
Niobrara River-Carns Bridge, Bassett, NE (MRO) 
26-20 
Nishnabotna River at Hamburg, IA (MRO) 26-16, 
26-20 
Nishnabotna River, Hamburg, IA (MRO) 26-23 
Nisqually River, near Elbe, WA (NPS) 38-27 
Nisqually River, Thurston County, WA (NPS) 38-27 
Nisqually River, Vicinity of Elbe, WA (NPS) 38-27 
Nixon Creek, TN (LMM) 13-6 
NJ Pierhead Channel (NAN) 2-28 
Nogales Wash, AZ (SPL) 33-10, 33-15, 33-30 
Nolin Lake, KY (ORL) 16-9, 16-16, 16-32 
Nome Harbor, AK (NPA) 40-3, 40-8, 40-9 
Nomini Bay and Creek, VA (NAB) 4-33, 4-38 
Nonconnah Blvd., Nonconnah Creek, TN (LMM) 
13-6 
Nonconnah Creek at Perkins, Memphis, TN (LMM) 
13-2, 13-4 
Nonconnah Creek, Interceptor Sewer, Memphis, TN 
(LMM) 13-6 
Nonewaug River, Woodbury, CT (NED) 1-46 
Nookagee Lake, MA (NED) 1-50 
Noosack River, Acme, WA (NPS) 38-27 
Noosack River, Everson, WA (NPS) 38-31 
Noosack River, Guide Bridge Location, WA (NPS) 
38-27 
Noosack River, Marietta, WA (NPS) 38-31 
Noosack River, Middle Fork, Deming, WA (NPS) 
38-27 
Noosack River, above Highway 1Z Bridge, WA (NPS) 
38-27 
Noosack River, Sumas, WA (NPS) 38-31 
I-45

Noosack River, WA (NPS) 38-27 
Noosack River, Whatcom County, WA (NPS) 38-31 
Norfolk Floodwall, VA (NAO) 5-18 
Norfolk Harbor, Eastern Branch, VA (NAO) 5-14 
Norfolk Harbor, Southern Branch, VA (NAO) 5-14, 
5-19 
Norfolk Harbor, VA (NAO) 5-5, 5-10, 5-14 
Norfolk Harbor, Western Branch, VA (NAO) 5-15, 
5-19 
Norfolk Lake, AR (SWL) 28-12, 28-17, 28-30 
Norfolk, NE (MRO) 26-16 
Norfolk, North Fork, Elkhorn River, NE (MRO) 
26-20 
Normal, KY (ORH) 17-22 
Norrel Lock and Dam (No. 1) and Entrance Channel, 
AR (SWL) 28-4 
North Adams, Hoosic River Basin, MA (NAN) 2-32 
North Alexander Drainage and Levee District, IL 
(LSM) 14-16 
North Andover and Lawrence, MA (NED) 1-50 
North Branch, Chicago River, IL (NCC) 22-10, 
22-14, 22-18 
North Branch of Kokosing River Lake, OH (ORH) 
17-8, 17-14, 17-18 
North Canaan, Blackberry River, CT (NED) 1-47, 
1-55 
North Canadian above Lake Overholser (SWT) 29-29 
North Canadian River, Okfuskee County, OK (SWT) 
29-28, 29-29 
North Canadian River Wastewater Plant, Oklahoma 
City, OK (SWT) 29-27 
North Ellenville, NY (NAN) 2-15, 2-21, 2-26 
North Fork of Pound River Lake, VA (ORH) 17-8, 
17-14, 17-19 
North Fork, Pit River at Alturas, CA (SPK) 35-38 
North Hampton Beach, North Hampton, NH (NED) 
1-50 
North Hartland Lake, VT (NED) 1-15, 1-30, 1-53 
North Little Rock, Arkansas River, AR (SWL) 28-22 
North Nantasket Beach, Hull, MA (NED) 1-51 
North Nashua River, Fitchburg, MA (NED) 1-47, 
1-56 
North Nashua River, Lancaster, MA (NED) 1-47 
North Platte River, Bank Stabilization, Minatare, NE 
(MRO) 26-20 
North Ridgeville, OH (NCB) 20-43 
North River Dike, NC (SAW) 6-29 
North Sandy Pond, Oswego County, NY (NCB) 20-43 
North Scituate Beach, Scituate, MA (NED) 1-45 
North Second Street at Wolf River, Memphis, TN 
(LMM) 13-4, 13-6 
North Shore of Long Island, Suffolk County, NY 
(NAN) 2-34 
North Shore, Santa Rosa Island, FL (SAM) 10-51 
North Springfield Lake, VT (NED) 1-15, 1-30, 1-53 
North Stratford, NH (NED) 1-54 
Northeast Cape Fear River, NC (SAW) 6-28 
Northeast Cape Fear River, NC (SAW) 6-26 
Northeast Harbor, ME (NED) 1-42 
Northeast River, MD (NAB) 4-33 
Northfield Brook Lake, CT (NED) 1-18, 1-31, 1-55 
Northhampton, MA (NED) 1-47, 1-54 
Northport Harbor, NY (NAN) 2-30 
Northport Harbor, WI (1975 Flood Control Act) 
(NCE) 21-87 
Northport Harbor, WI (NCE) 21-84 
Norwalk, Ct (NED) 1-47 
Norwalk Harbor, CT (NED) 1-42 
Norwalk-Wilton, CT (NED) 1-50 
Norwich, CT (NED) 1-47, 1-57 
Norwich, NY (NAB) 4-35, 4-38 
Nottoway River, VA (NAO) 5-17 
Nouma Navigation Canal, LA (LMN) 11-15 
Noxubee River, MS (SAM) 10-49 
Noxubee River Relief Bridge, Shuqualak, MS (SAM) 
10-50 
Noyo River and Harbor, CA (SPN) 34-6, 34-7 
Nua-Amaluia, American Samoa (POD) 36-12 
Nutwood Drainage and Levee District, IL (LSM) 
14-13, 14-17 
O 
O.C. Fisher Dam and Lake, TX (SWF) 30-8, 30-16, 
30-20 
O'Hare Reservoir, IL (NCC) 22-10, 22-14, 22-18 
Oahe Dam-Lake Oahe, Missouri River Basin, SD and 
ND (MRO) 26-7, 26-11, 26-14, 26-18 
Oahe Wildlife Restoration (MRO) 26-22 
Oak Bluffs Harbor, Oak Bluffs, MA (NED) 1-51 
Oak Bluffs Town Beach, Martha's Vineyard, MA 
(NED) 1-45 
Oak Orchard Harbor, NY (NCB) 20-7, 20-19, 20-33 
Oakdale, PA (ORP) 18-23 
Oakford Special Drainage District, IL (NCR) 23-12, 
23-15 
I-46

Oakland Beach, Warwick, RI (NED) 1-45 
Oakland Harbor (Deepen Tidal Canal), CA (SPN) 
34-13 
Oakland Harbor (Fruitvale Avenue Bridge), CA (SPN) 
34-13 
Oakland Harbor, CA (SPN) 34-1, 34-7, 34-11 
Oates Creek, Richmond County, GA (SAS) 8-6, 8-11, 
8-17, 8-19 
Obey River, TN (ORN) 15-13 
Obion River, TN (LMM) 13-5 
Occohannock Creek, VA (Active portion) (NAO) 5-17 
Occoquan Creek, VA (NAB) 4-33 
Ocean Beach, San Diego County, CA (SPL) 33-29 
Ocean City Harbor and Inlet and Sinepuxent Bay, MD 
(NAB) 4-5, 4-22, 4-29 
Ocean City Harbor and Inlet and Sinepuxent Bay, MD 
(1954 River & Harbor Act) (NAB) 4-37 
Ocean City, NJ (NAP) 3-28 
Ocean Springs Harbor, MS (SAM) 10-51 
Oceana, WV (ORH) 17-21 
Oceanside Harbor, CA (SPL) 33-3, 33-12, 33-20, 
33-30 
Oceanside Harbor Sand Bypass, CA (SPL) 33-3, 
33-12, 33-20 
Oceanside, San Diego County, CA (SPL) 33-29 
Oceanside, Sand By-pass, CA (SPL) 33-29 
Oconto Harbor, WI (NCE) 21-26, 21-60, 21-78 
Ocracoke Inlet Jetty, NC (SAW) 6-29 
Ocracoke Island, NC (SAW) 6-29 
Oelwein, Fayette County, IA (NCR) 23-16 
Ofu Airstrip (West End), American Samoa (POD) 
36-11 
Ofu Airstrip, American Samoa (POD) 36-8 
Ofu Small Boat Harbor, American Samoa (POD) 36-7 
Ogdensburg Harbor, NY (NCB) 20-40 
Ogdensburg Harbor, NY 1935 R&H Act (NCB) 20-45 
Ohio River Basin (Huntington District) (ORH) 17-8, 
17-14 
Ohio River Basin (Louisville District) (ORL) 16-10, 
16-16, 16-19 
Ohio River Basin (Nashville District) (ORN) 15-5, 
15-12, 15-17 
Ohio River Basin (Pittsburgh District) (ORP) 18-9, 
18-14, 18-20, 18-28 
Ohio River, Brandenburg, KY (ORL) 16-35, 16-37 
Ohio River, Chester, WV (detalied project report 
underway) (ORP) 18-30 
Ohio River, City Park, West Point, KY (ORL) 16-37 
Ohio River, Cloverport, KY (ORL) 16-35 
Ohio River, Daviess County, KY (ORL) 16-35, 16-37 
Ohio River, Fort Massac State Park, IL (ORL) 16-35 
Ohio River, Hawesville, KY (ORL) 16-35 
Ohio River, Lewisport, KY (ORL) 16-35 
Ohio River, Madison, IN (ORL) 16-35 
Ohio River, Moscow, OH (ORL) 16-35 
Ohio River, Moundsville, WV (detalied project report 
underway) (ORP) 18-30 
Ohio River, Mount Vernon, IN (ORL) 16-35 
Ohio River, Newburgh, IN (ORL) 16-35 
Ohio River, Ohio County, IN (ORL) 16-37 
Ohio River, Ohio Street, Evansville, IN (ORL) 16-35 
Ohio River, Otter Creek Park, KY (ORL) 16-35 
Ohio River, Owensboro, KY (ORL) 16-35 
Ohio River, Owensboro Riverport Authority, KY 
(ORL) 16-35 
Ohio River, Rabbit Hash, Boone County, KY (ORL) 
16-35 
Ohio River, Rockport/Rockport Landing, IN (ORL) 
16-35 
Ohio River, Sellersburg, IN (ORL) 16-35 
Ohio River, SR 66, Cannelton, IN (ORL) 16-35 
Ohio River, Switzerland County, IN (ORL) 16-37 
Ohio River, Troy, IN (ORL) 16-35 
Ohio River, Upper River Road, Jefferson County, KY 
(ORL) 16-35 
Ohio River, Vanderburg County, IN (ORL) 16-35 
Oil City Ice Control Structures, PA (ORP) 18-22 
Oil City, PA (ORP) 18-22, 18-30 
Oil Creek, Oil City, Verango County, PA 
(reconnaissance) (ORP) 18-30 
Okabena Creek at Worthington, MN (NCR) 23-12 
Okanogan and Pend Oreille Rivers, WA (NPS) 38-25 
Okanogan River at Outlet of Osoyoos Lake, WA 
(NPS) 38-27 
Okanogan River, Omak, WA (NPS) 38-27 
Okanogan River, Oroville, WA (NPS) 38-27 
Okanogan River, Tonasket Creek and Osoyoos Lake, 
WA (NPS) 38-27 
Okanogan River, WA (NPS) 38-27, 38-30 
Okatibbee Lake, MS (SAM) 10-18, 10-36, 10-46 
Okeechobee Waterway, FL (SAJ) 9-10, 9-29, 9-39, 
9-54 
Oklahoma City, Floodway, OK (SWT) 29-27 
Oklahoma City LPP, OK (SWT) 29-24 
Oklawaha River, FL (SAJ) 9-10, 9-29, 9-39, 9-51 
Oktassi Creek, AL (SAM) 10-56 
I-47

Olcott Harbor, NY (NCB) 20-7, 20-19, 20-34 
Old Field Swamp, NC (SAW) 6-28 
Old Harbor, Kodiak Island, AK (NPA) 40-11 
Old Hickory Lock and Dam, TN (ORN) 15-14 
Old Hwy. 82 Bridge, Columbus, MS (SAM) 10-50 
Old Kingstree Canal, Williamsburg County, SC (SAN) 
7-18 
Old Metlakatla Harbor, AK (NPA) 40-13 
Oldmans Creek, NJ (NAP) 3-25, 3-28 
Olean, NY (ORP) 18-22 
Oliver Lock and Dam (Replacement), AL (SAM) 
10-6, 10-33, 10-41 
Olympia Harbor (1945 R&H Act), WA (NPS) 38-30 
Olympia Harbor, WA (NPS) 38-5, 38-15, 38-21 
Omaha, NE (MRO) 26-16, 26-18, 26-20 
Onaga Lake, Vermillion Creek, KS (MRK) 27-18 
Onancock River, VA (NAO) 5-17, 5-19 
Oneida Creek, NY (NCB) 20-43 
Oneonta, NY (NAB) 4-38 
Onondaga Creek, Nedrow, NY (NCB) 20-42 
Ontonagon Harbor, MI (1962 R&H Act) (NCE) 21-87 
Ontonagon Harbor, MI (NCE) 21-26, 21-61, 21-78 
Oologah Lake, OK (SWL) 28-28 
Oologah Lake, OK (SWT) 29-8, 29-17, 29-22, 29-26 
Oostanaula River, GA (SAM) 10-56 
Open Channel Work, Licking River, KY (ORL) 16-2, 
16-14, 16-22 
Open Channel Work, Ohio River (ORD) 19-3, 19-5, 
19-6, 18-3 
Open Channel Work, Ohio River (ORH) 17-2 
Open Channel Work, Ohio River (ORL) 16-3 
Open River Lewiston to Johnson Bar Landing (NPW) 
39-23 
Open River Pasco to Lewiston (NPW) 39-23 
Optima Lake, OK (SWT) 29-8, 29-17, 29-22 
Oracoke Inlet, NC (SAW) 6-26 
Orange River, FL (SAJ) 9-49 
Orange Road, Mercer County, PA (terminated) (ORP) 
18-30 
Oregon Slough (North Portland Harbor), OR (NPP) 
37-36 
Orleans, IN (ORL) 16-27 
Oro Grande Wash Channel Improvements, Mojave 
River Basin, CA (SPL) 33-30 
Orofino Creek & Clearwater River, Orofino, ID 
(NPW) 39-16 
Orowoc Creek, NY (NAN) 2-34 
Orwell Lake, MN (NCS) 24-31 
Orwell River (Otter Tail River), MN 24-28 
Osage River, KS and MO (MRK) 27-20 
Osage River, MO lock and dam (MRK) 27-16 
Osawatomie, Pottawatomie Creek, KS (MRK) 27-17, 
27-20 
Osborne Creek, Highway 362 Bridge, Prentiss 
County, MS (SAM) 10-50 
Osceola Harbor, AR (LMM) 13-5 
Oslo, MN (NCS) 24-29 
Oswego Harbor, NY (NCB) 20-8, 20-19, 20-34 
Oswego Harbor, NY 1930 R&H Act (NCB) 20-45 
Oswego Harbor, NY 1940 R&H Act (NCB) 20-45 
Otranto Watershed, Charleston County, SC (SAN) 
7-18 
Ottawa, IL (NCR) 23-16 
Ottawa,- OH (NCB) 20-42 
Ottawa, Osage (Marais des Cygnes) River, KS (MRK) 
27-17, 27-20 
Ottawa River Harbor, MI and OH (NCB) 20-8, 20-19, 
20-34 
Otter Brook Lake, NH (NED) 1-15, 1-30, 1-53 
Otter Creek and Tributaries, Shannon Hills, AR 
(SWL) 28-22 
Otter Creek, VT (NAN) 2-34 
Otter Tail River, MN (NCS) 24-28 
Otto Creek, Leshara, NE (MRO) 26-23 
Ottumwa, IA (NCR) 23-12 
Ouachita and Black Rivers below Camden, AR (LMK) 
12-2, 12-10, 12-12 
Ouachita River and Tributaries, AR and LA (LMK) 
12-5, 12-13 
Ouachita River Levees (additional work) (LMK) 12-18 
Ouachita River Levees, LA (LMK) 12-5, 12-11 
Overton-Red River Waterway, LA (LMK) 12-16 
Owasco Inlet and Outlet, Montville and Dry Creek, 
State Ditch and Crane Brook, NY (NCB) 20-42 
Owego, NY (NAB) 4-38 
Owens, CA (SPK) 35-42 
Owensboro, KY (ORL) 16-27, 16-30 
Owl Creek, West Carrolton, OH (ORL) 16-37 
Owl's Head Harbor, ME (NED) 1-42 
Owyhee River, OR (NPW) 39-13, 39-16 
Oxford, MD (NAB) 4-34 
Oxford, NY (NAB) 4-15, 4-25 
Oyster Channel, VA (NAO) 5-17 
Oyster Creek, TX (SWG) 31-38 
Ozan Creek, AR (LMK) 12-18 
I-48

Ozark-Jeta Taylor Lock and Dam (No. 13), AR 
(SWL) 28-12, 28-17 
Ozona, FL channel and turning basin (SAJ) 9-49 
P 
Paauau Stream, Hawaii, HI (POD) 36-9 
Paducah, KY (ORL) 16-23, 16-29, 16-34 
Pagan River, VA (NAO) 5-17 
Pago Pago Airport, American Samoa (POD) 36-8 
Pago Pago to Nuuuli, American Samoa (POD) 36-8 
Paint Creek at Chillicothe, OH (ORH) 17-24 
Paint Creek at Washington Court House, OH (ORH) 
17-24 
Paint Creek Lake, Ohio River Basin, OH (ORH) 17-8, 
17-14, 17-19 
Paint Rock River, AL (ORN) 15-13, 15-18 
Painted Post, NY (NAB) 4-35, 4-38 
Painted Rock Dam (Gila River), AZ (SPL) 33-5, 
33-13, 33-23 
Paintsville Lake, KY (ORH) 17-8, 17-15, 17-19 
Pajaro River, CA (SPK) 35-15, 35-29 
Pajaro River, CA (SPN) 34-14 
Palm Beach County, FL (SAJ) 9-18, 9-31, 9-46 
Palm Beach County, FL, from Lake Worth Inlet to 
South Lake Worth Inlet (SAJ) 9-50 
Palm Beach, FL side channel and basin (SAJ) 9-49 
Palm Beach Harbor, FL (SAJ) 9-11, 9-29, 9-39, 9-51 
Palouse River, WA (NPW) 39-17, 39-18 
Pamlico and Tar Rivers, NC (SAW) 6-7, 6-20 
Pamona Lake, Osage River Basin, KS 
Pamunkey River, VA (Active portion) (NAO) 5-17 
Panacea Harbor, FL (SAM) 10-49, 10-52 
Panama City Beaches, FL (SAM) 10-44 
Panama City Harbor, FL (SAM) 10-11, 10-34, 10-44 
Pantego Creek and Cucklers Creek, NC (SAW) 6-28 
Panther Creek, KY (Green River) (ORL) 16-23, 16-35 
Panther Creek, Sangamon River, Chandlerville, IL 
(NCR) 23-16 
Panther Creek, WV (ORH) 17-23 
Papillion Creek and Tributaries Lakes, NE (MRO) 
26-4, 26-10, 26-13 
Parish Creek, MD (NAB) 4-33 
Park City, KS (SWT) 29-27 
Park River, Hartford, CT (NED) 1-47, 1-54 
Park Row, Arlington, TX (SWF) 30-23 
Parker Creek, VA (NAO) 5-17 
Parker Lake, OK (SWT) 29-8, 29-17, 29-22 
Parkersburg, WV (ORH) 17-21, 17-24 
Parrots Creek, VA (NAO) 5-17 
Parsons, Hambleton, Hendricks, WV (complete) 
(ORP) 18-30 
Pascagoula Harbor, MS (SAM) 10-12, 10-34, 10-44 
Pascagoula River, MS (SAM) 10-49 
Pasquotank River, NC (SAW) 6-28 
Pass-A-Grille Pass, FL (SAJ) 9-49 
Pass Christian Harbor, MS (SAM) 10-49 
Pass Manchac, LA (LMN) 11-16 
Passaic River (NAN) 2-28 
Passaic River Basin, N.J. & NY (NAN) 2-16, 2-21, 
2-26 
Passamaquoddy Tidal Power Project, ME (NED) 1-48 
Pat Mayse Lake, TX (SWT) 29-8, 29-17, 29-22 
Patchogue River, CT (NED) 1-42 
Patoka Lake, IN (ORL) 16-10, 16-17, 16-32 
Patoka River, Jasper, IN (ORL) 16-35 
Patoka River, Winslow, IN (ORL) 16-35 
Patriot, IN (ORL) 16-27, 16-30 
Pattonsburg Lake, Grand River, MO (MRK) 27-17 
Pattonsburgh Lake, Grand River, MO I-35 Highway 
Relocation Town Relocation (MRK) 27-18 
Patuxent River, MD (NAB) 4-33 
Paw Paw Lake, MI (NCE) 21-85 
Pawcatuck, CT (NED) 1-47 
Pawcatuck River, Little Narragansett Bay, RI & CT 
(NED) 1-50 
Pawcatuck River, Little Narragansett Bay and Watch 
Hill Cove, RI & CT (NED) 1-42 
Pawcatuck River, RI & CT (uncompleted portion) 
(NED) 1-50 
Pawtucket, RI (NED) 1-50 
Pawtuxet Cove, RI (NED) 1-42 
Pawtuxet River, Warwick, RI (NED) 1-47, 1-53 
Pax, WV (ORH) 17-24 
Payette River, Emmett Sewage Lagoon, ID (NPW) 
39-16 
Payette Valley, ID (NPW) 39-17 
Pea & Choctawhatchee Rivers, Geneva, AL (SAM) 
10-51 
Pea River, Elba, AL (SAM) 10-51 
Peachtree Creek, Basin, Atlanta, GA (SAM) 10-51 
Peacock Creek, Liberty County, GA (SAS) 8-19 
Pearl River Basin, MS and LA (LMK) 12-6, 12-11, 
12-13 
Pearl River, Jackson-East Jackson, MS (LMK) 12-21 
Pearl River, MS (LMK) 12-16 
I-49

Pearl River, Slidell, St. Tammany Parish, LA (LMK) 
12-7, 12-11, 12-14 
Pearson-Skubitz Bill Hill Lake, KS (SWT) 29-9, 
29-17, 29-22 
Pebble Creek, Scribner, NE (MRO) 26-4, 26-10, 
26-13, 26-20, 26-23 
Pecan Bayou, TX (SWT) 29-29 
Pecatonica River at Darlington, WI (NCR) 23-14 
Peconic River (NAN) 2-28, 2-30 
Pecos, TX (SWA) 32-19 
Peekskill Harbor, NY (NAN) 2-30 
Pekin and La Marsh Drainage and Levee District, IL 
(NCR) 23-12, 23-15 
Pelican Harbor, AK (NPA) 40-11 
Pelican Lake, Frankfort, MN (NCS) 24-30 
Pembina, ND (NCS) 24-29 
Pembina River Lake, ND (NCS) 24-26 
Pembina River, ND (NCS) 24-24 
Pembroke Creek, NC (SAW) 6-26 
Pendleton Levees, Riverside Area, OR (NPP) 37-40 
Pendleton Levees, Umatilla River, OR (NPP) 37-39 
Pendleton, Umatilla River, OR (NPP) 37-39 
Peninsula Drainage District 1, Multnomah County, OR 
(NPP) 37-37, 37-40, 37-42 
Peninsula Drainage District 2, OR (NPP) 37-38 
Peninsula, TX (SWG) 31-38 
Penitentiary Jones Run, KY (ORL) 16-37 
Penn Township, Butler County, PA (complete) (ORP) 
18-30 
Penny Slough, Rock River, IL (NCR) 23-12, 23-15 
Penobscot River, ME (NED) 1-42, 1-47 
Pensacola Beach, FL (SAM) 10-51 
Pensacola Harbor, FL (SAM) 10-12, 10-34, 10-45, 
10-52 
Pensacola Lake, OK (SWL) 28-28 
Pensaukee Harbor, WI (NCE) 21-27, 21-61, 21-78 
Pentwater Harbor, MI (1892 R&H Act) (NCE) 21-87 
Racine Harbor, WI (1945 R&H Act and Section 107 
of the 1960 R&H Act) (NCE) 21-87 
Pentwater Harbor, MI (NCE) 21-27, 21-61, 21-78 
Peoria, IL (NCR) 23-13 
Peoria Levees, IL (NCR) 23-14 
Pepin Harbor, WI 25-7 
Pepper Creek, DE (NAP) 3-25 
Pepperell Cove, ME (NED) 1-42 
Pepperell Cove, ME (uncompleted portion) (NED) 
1-50 
Percosin Creek and Tributaries, GA (SAM) 10-56 
Perdido Pass Channel, AL (SAM) 10-13, 10-35, 
10-45, 10-52 
Perkins Cove, Ogunquit, ME (NED) 1-51 
Perley Brook, Fort Kent, ME (NED) 1-47 
Permenant International Association of Navigation 
Congresses 48-1 
Perquimans River, NC (SAW) 6-26, 6-28 
Perry County Drainage and Levee District Nos. 1, 2 
and 3, MO (LSM) 14-17 
Perry Lake Area (Road Improvements), KS (MRK) 
27-17, 27-20 
Perry Lake, Delaware River, KS (MRK) 27-11 
Perryville, KY (ORL) 16-34 
Perth Amboy Channel (NAN) 2-28 
Perth Amboy, NJ (NAN) 2-34 
Petaha Creek, Pomeroy, WA (NPW) 39-16 
Petaluma River, CA (SPN) 34-8 
Petersburg Harbor, AK (NPA) 40-11 
Petit Jean River, AR (SWL) 28-22 
Petit Jean River, Highway 309, AR (SWL) 28-8, 
28-16 
Petite Anse, Tigre, and Carlin Bayous, LA (LMN) 
11-16 
Petoskey Harbor, MI (NCE) 21-84 
Pettibone Park, La Crosse, WI (NCS) 24-24, 24-29 
Peyton Creek, TX (SWG) 31-38 
Phillipi, WV (terminated) (ORP) 18-30 
Phillippi Creek Basin, FL (SAJ) 9-50 
Phillips Lake, MA (NED) 1-47, 1-56 
Philpott Lake, VA (SAW) 6-16, 6-22 
Phoenix, AZ and Vicinity (Including New 
River)(Stage 2 and Remaining Work) (SPL) 33-6, 
33-13, 33-23 
Pick-Sloan Missouri Basin Program (Kansas City 
District) (MRK) 27-6, 27-14 
Pick-Sloan Missouri River Basin Program (Omaha 
District) (MRO), 26-5, 26-13 
Pickens County, AL (SAM) 10-56 
Pierce County (Various Locations), WA (NPS) 38-27 
Pierce, NE (MRO) 26-16, 26-20 
Pig Island Gut, ME (NED) 1-42 
Pilchuck River, Everett, WA (NPS) 38-27 
Pilchuck River, State Highway 92, Granite Falls, WA 
(NPS) 38-27 
Pilchuck River, WA (NPS) 38-27 
Pillar Point Harbor, CA (SPN) 34-8 
Pilot Rock, Birch Creek, OR (NPP) 37-40 
I-50

Pinal Creek Channel Improvements (Globe) (SPL) 
33-30 
Pine and Mathews Canyons Dams, Colorado River 
Basin, NV (SPL) 33-7, 33-14, 33-25 
Pine Bluff, AR, local protection (LMK) 12-18 
Pine Creek, Angle Inlet, MN (NCS) 24-23 
Pine Creek Lake, TX (SWT) 29-9, 29-17, 29-22 
Pine Flat Lake and Kings River, CA (SPK) 35-16, 
35-29 
Pine Ford Lake, MO (LSM) 14-6, 14-9 
Pine Mountain Lake, AR (SWL) 28-22 
Pine River, MI (NCE) 21-84 
Pinellas County, FL (SAJ) 9-19, 9-31, 9-46 
Pineville, KY (ORN) 15-13, 15-18 
Pineville, Red River, LA (LMK) 12-20, 12-21 
Piney Creek, Spring City, TN (ORN) 15-18 
Pinole Creek, CA (SPK) 35-38 
Pinole Creek, CA (SPN) 34-14 
Pinon Canyon Dam, Trinidad, CO (Sec. 212) (SWA) 
32-19 
Pioneer Lake, KS (MRK) 27-18 
Pipe Creek, Alexandria, IN (ORL) 16-37 
Pipestem Lake, ND (MRO) 26-5, 26-10, 26-14 
Pithlachascotee River, FL (SAJ) 9-49 
Pittsburgh Harbor, PA (ORP) 18-21 
Pittsburgh, PA (Golden Triangle) (ORP) 18-24 
Pittsburgh, PA (North Side) (ORP) 18-24 
Pittsburgh, PA (The Strip) (ORP) 18-24 
Placer Creek, ID (NPS) 38-27 
Plainview Road Bridge, Chester County, TN (LMM) 
13-4, 13-6 
Planning and Engineering (SWG) 31-17 
Planning Engineering and Design (NED) 1-25 
Planting Island Causeway, Marion, MA (NED) 1-51 
Plants Creek, Seymour, TX (SWF) 30-23 
Platte River and Lost Creek, Schuyler, NE (MRO) 
26-16 
Platte River and Tributaries, NE (MRO) 26-16 
Platte River, Ashland, NE (MRO) 26-20 
Platte River, Bank Protection, Louisville, NE (MRO) 
26-20 
Platte River, Brady, NE (MRO) 26-20 
Platte River, Cedar Creen, NE (MRO) 26-23 
Platte River, Ginger Cove Near Valley, NE (MRO) 
26-20 
Platte River, Hansen-Chris Lakes, Bellevue, NE 
(MRO) 26-20 
Platte River, M.U.D. Protection, Cedar Island, NE 
(MRO) 26-20 
Platte River, MO, Channel Improvement (MRK) 27-17 
Platte River, Near North Bend, NE (MRO) 26-20 
Platte River near Schuyler, NE (MRO) 26-16 
Plattsburgh Harbor, NY (NAN) 2-30 
Pleasant Bay, MA (NED) 1-50 
Pleasant Meadow Swamp, Lori, SC (SAN) 7-18 
Pleasant Point, Perry, ME (NED) 1-47 
Pleasant River, ME (NED) 1-42 
Pleasanton, TX (SWF) 30-22 
Plum Creek at New Haven Township, MN (NCS) 
24-29, 16-35 
Plum Creek, Bank Stabilization, Aurora, CO (MRO) 
26-19 
Plum Creek, Norden Dam Access Road, NE (MRO) 
26-23 
Plum Creek, Oakmont, PA (plans and specifications) 
(ORP) 18-30 
Plum Island, MA (NED) 1-45 
Plymouth Harbor, MA (NED) 1-42 
Plymouth, PA (NAB) 4-35, 4-38 
Poca, WV (ORH) 17-23 
Pocomoke River, MD (1945 River & Harbor Act) 
(NAB) 4-37 
Pocomoke River, MD (NAB) 4-33, 4-38 
Pocotaligo River, Manning, SC (SAN) 7-18 
Pogues Run, Indianapolis, IN (ORL) 16-37 
Pohoiki Bay, Hawaii, HI (POD) 36-7 
Point Beach, Milford, CT (NED) 1-52 
Point Judith Pond and Harbor of Refuge, RI (NED) 
1-42 
Point Judith, RI (NED) 1-50 
Point Lookout Harbor, MI (NCE) 21-84, 21-90 
Point Place, Toledo, OH (NCB) 20-42 
Point Remove Levee and Drainage District, Conway 
County, AR (SWL) 28-22 
Point Shirley, Winthrop, MA (NED) 1-51 
Poison Bay, Flathead Lake, MT (NPS) 38-25 
Pollock Rip Shoals, Nantucket Sound, MA (NED) 
1-42 
Poloa Area, American Samoa (POD) 36-8 
Pomeroy, OH (ORH) 17-22 
Pomme de Terre Lake (Power Addition), MO (MRK) 
27-19 
Pomme de Terre Lake, Pomme de Terre River, MO 
(MRK) 27-6, 27-11, 27-15, 27-20 
1-51

Pomona Lake, One Hundred Ten Mile Creek, KS 
(MRK) 27-6, 27-11, 27-15 
Pompton Lake, PA (NAP) 3-14, 3-19, 3-24 
Ponca City, OK, Flood Forecast Map (SWT) 29-29 
Ponce de Leon Inlet, FL (SAJ) 9-11, 9-29, 9-40, 9-51 
Ponce Harbor, PR (SAJ) 9-11, 9-29, 9-40,'9-51 
Ponce, PR (SAJ) 9-48 
Ponce Regional, PR (SAJ) 9-61 
Pond Creek, Cheatham County, TN (ORN) 15-18 
Pontiac Diversion, RI (NED) 1-50 
Poppenessett Spit, Mashpee, MA (NED) 1-51 
Popperdam Creek, North Charleston, SC (SAN) 7-18 
Port 5 Facility, Bridgeport, CT (NED) 1-47 
Port Alexander (Inner Harbor), AK (NPA) 40-12 
Port Alexander, AK (NPA) 40-11 
Port Alexander Channel, AK (NPA) 40-13 
Port Allen Harbor, Kauai, HI (POD) 36-7 
Port Angeles Harbor (Uncompleted portion), WA 
(NPS) 38-30 
Port Angeles Harbor, WA (NPS) 38-25 
Port Arthur and Vicinity (Hurricane Flood Protection), 
TX (SWG) 31-14, 31-21, 31-36 
Port Austin Harbor, MI (NCE) 21-28, 21-61, 21-78, 
21-90 
Port Bay, NY 1950 R&H Act (NCB) 20-45 
Port Chester Harbor (NAN) 2-28, 2-30, 2-34 
Port Clinton Harbor, NY (NCB) 20-40 
Port Dickerson, NY (NAB) 4-38 
Port Everglades Harbor, FL (SAJ) 9-12, 9-30, 9-40, 
9-51 
Port Gamble Harbor (Uncompleted portion), WA 
(NPS) 38-30 
Port Gamble Harbor, WA (NPS) 38-25 
Port Henry Harbor, NY (NAN) 2-30 
Port Hueneme, CA (SPL) 33-3, 33-12, 33-20 
Port Jefferson Harbor, NY (NAN) 2-30, 2-34 
Port Lions, AK (NPA) 40-11, 40-13 
Port Lions Harbor, AK (NPA) 40-13 
Port of Gold Beach, OR (NPP) 37-41 
Port of Kalama, WA (NPP) 37-37 
Port of Morrow, Morrow, OR (NPP) 37-41 
Port Ontario Harbor, NY (NCB) 20-8, 20-19, 20-35 
Port Orchard Bay, WA (NPS) 38-25 
Port Orford, OR (NPP) 37-6, 37-23, 37-31 
Port Royal Harbor, SC (SAN) 7-7, 7-11, 7-16 
Port San Luis, CA (SPL) 33-28 
Port San Luis Shore and Bluff Erosion (SPL) 33-29 
Port Sanilac Harbor, MI (NCE) 21-28, 21-62, 21-8 
Port St. Joe, FL (SAM) 10-49, 10-52 
Port Townsend, WA (NPS) 38-25, 38-31 
Port Washington Harbor, WI (NCE) 21-28, 21-62, 
21-78 
Port Wing Harbor, WI (NCE) 21-29, 21-62, 21-79 
Portage Lake Harbor, MI (NCE) 21-84, 21-90 
Portage, PA (ORP) 18-22 
Portage, WI (NCS) 24-10, 24-19 
Porter Bayou, MS (LMK) 12-7, 12-11, 12-14 
Portersville Bay-East, Mobile County, AL (SAM) 
10-19, 10-36, 10-46 
Portersville Bay-West, Mobile County, AL (SAM) 
10-19, 10-36, 10-46 
Portland Harbor, ME (NED) 1-42 
Portland, IN (Salamonie River) (ORL) 16-23, 16-35 
Portland, OH (ORH) 17-22 
Portneuf River and Marsh Creek, ID Pocatello Unit 
(NPW) 39-18 
Portneuf River, Inkom-Marsh Creek, ID (NPW) 
39-17, 39-18 
Portsmouth Harbor and Piscataqua River, ME and NH 
(NED) 1-7, 1-28, 1-37 
Portsmouth Harbor, VA Channel to Nansemond 
Ordinance Depot, (NAO) 5-17 
Portsmouth-New Boston, OH (ORH) 17-21, 17-24 
Portugues and Bucana Rivers, PR (SAJ) 9-23, 9-32, 
9-48 
Portville, NY (ORP) 18-22 
Post Oak Creek, Corsicana, TX (SWF) 30-23 
Posten Bayou, AR and LA (LMK) 12-19, 12-21 
Poteau River, LeFlore County, OK (SWT) 29-28 
Poteau River Navigation Project, OK and AR (SWT) 
29-23 
Poteet, TX (SWF) 30-22 
Potomac and Anacostia Rivers, DC, Collection and 
Removal of Drift (NAB) 4-6, 4-22, 4-29 
Potomac River and Tributaries at and below 
Washington, DC, Elimination of Waterchestnut 
(NAB) 4-33 
Potomac River - Aquatic Plant Control, MD, VA, DC 
(NAB) 4-6, 4-22, 4-29 
Potomac River at Alexandria, VA (NAB) 4-6, 4-22, 
4-29 
Potomac River at Lower Cedar Point, MD (NAB) 
4-33 
Potomac River at Mt. Vernon, VA (NAB) 4-33 
Potomac River at North Side of Washington Channel, 
DC (NAB) 4-33 
I-52

Potomac River Below Washington, DC (NAB) 4-7, 
4-23, 4-29 
Potowomut River, RI (NED) 1-43 
Pottstown, PA (NAP) 3-27 
Poverty Point, LA (LMK) 12-22 
Powder Horn Branch, Sumter County, SC (SAN) 7-18 
Powder River, Arvada, WY (MRO) 26-23 
Powder River, Broadus, MT (MRO) 26-23 
Powell County High School, Deer Lodge, MT (NPS) 
38-27 
Powhaten Point, OH (ORP) 18-24 
Praire du Chien, WI (NCS) 24-24, 24-29 
Prairie du Chien Harbor, WI 25-7 
Prairie du Pont Levee and Sanitary District, IL (LSM) 
14-17 
Prairie du Rocher and Vicinity, IL (LSM) 14-17 
Prattville, Autauga Creek, AL (SAM) 10-50 
Preconstruction Engineering and Design - See 
Advance Engineering and Design 
Prescott Area, Columbia County, OR (NPP) 37-40 
Presque Isle Harbor, MI (NCE) 21-29, 21-63, 21-79 
Presque Isle Peninsula, Erie, PA (NCB) 20-11, 20-21, 
20-37 
Prestile Stream, Blaine, ME (NED) 1-47 
Preston Drainage and Levee District, IL (LSM) 14-18 
Preston Drainage and Levee District, IL (LSM) 14-17 
Prestonsburg, KY (ORH) 17-24 
Prestonville, KY (ORL) 16-27, 16-31 
Prevention of Obstructions and Injurious Deposits, 
Baltimore Harbor, MD (NAB) 4-7, 4-23, 4-29 
Priest Rapids Dam, Columbia River, WA (NPS) 38-29 
Princeton, WV (ORH) 17-21, 17-24 
Prineville Area, Crooked River and Ochoco Creek, 
OR (NPP) 37-40 
Pringle Creek, Salem, OR (NPP) 37-42 
Proctor Creek, Atlanta, GA (SAM) 10-19, 10-36, 
10-46 
Proctor Lake, TX (SWF) 30-8, 30-16, 30-20 
Proctor, WV (ORP) 18-24 
Proctorville, OH (ORH) 17-22 
Project Condition Surveys 
Alaska District (NPA) 40-4 
Portland District (NPP) 37-7 
Seattle District (NPS) 38-5 
Project Modifications for Improvement of 
Environment (SWG) 31-17 
Project Modifications for Improvement of 
Environment Under Special Authorization 
Savannah District (SAS) 8-7 
Prospect Beach, West Haven CT (NED) 1-45, 1-51 
Prosperity Lake, MO (SWL) 28-23 
Prototype Breakwater Test Program, WA (NPS) 38-25 
Providence River and Harbor, RI (NED) 1-43 
Providence River and Harbor, RI (uncompleted 
portion) (NED) 1-50 
Provincetown Beach (Herring Cove), MA (NED) 1-50 
Provincetown Harbor, MA (NED) 1-43, 1-51 
Provincetown Harbor, MA (uncompleted portion) 
(NED) 1-50 
Pt. Pleasant, WV (ORH) 17-21, 17-24 
Pudding River, OR (NPP) 37-40 
Pueblo, Arkansas River, CO (Floodway levee 
extension) (SWA) 32-19 
Puerco River, Gallup, NM (SWA) 32-5, 32-13, 32-16 
Puget Sound and its Tributary Waters, WA (NPS) 
38-6, 38-15, 38-22 
Pullman, Palouse River, WA (NPW) 39-17 
Pultneyville Harbor, NY (NCB) 20-40 
Pumpkinville Creek, Emerson, GA (SAM) 10-50 
Punaluu Highway, Oahu, HI (POD) 36-11 
Pungo River, NC (SAW) 6-28 
Punta Salinas, PR (SAJ) 9-50 
Punxsatawney, Ohio River Basin, PA (ORP) 18-5, 
18-13, 18-18 
Punxsutawney, PA (ORP) 18-22 
Put in Bay, OH (NCB) 20-40 
Puyallup River, WA (NPS) 38-27 
Pysht River, Sekiu, WA (NPS) 38-27 
Q 
Quail Wash Levee, Joshua Tree, San Bernardino, CA 
(SPL) 33-30 
Queens Creek, VA (NAO) 5-17 
Queenstown Harbor, MD (NAB) 4-33, 4-38 
Queets River, Jefferson County Sewage Lagoon, WA 
(NPS) 38-27 
Quillayute River (Uncompleted portion), WA (NPS) 
38-30 
Quillayute River, Quileute Tribal Float and Bridge, 
WA (NPS) 38-28 
Quillayute River, WA (NPS) 38-6, 38-16, 38-22, 
38-31 
Quinalt River, Grays Harbor, WA (NPS) 38-28 
Quinalt River Road, Jefferson County, WA (NPS) 
38-28 
I-53

Quinault River, WA (NPS) 38-31 
Quinby Creek, VA (NAO) 5-17 
Quince Road Bridge, Memphis, TN (LMM) 13-2, 
13-4 
Quincy Harbor, IL 25-8 
Quincy, IL, Harbor Access Channel (NCR) 23-11 
Quincy Shore Beach, Quincy MA (NED) 1-45 
R 
R.B. West Nishnabotna River, Mills County Bridge, 
Near Malvern, IA (MRO) 26-21 
R.D. Bailey Lake, WV (ORH) 17-9, 17-15, 17-19 
Raccoon Creek, Baconton, GA (SAM) 10-20, 10-36, 
10-46 
Raccoon Creek Levee, IN (ORL) 16-27, 16-31 
Raccoon Creek, NJ (NAP) 3-25 
Raccoon River, Des Moines, IA (NCR) 23-16 
Racine, OH (ORH) 17-22 
Rahway, NJ (NAN) 2-32 
Rahway River, NJ (NAN) 2-34 
Rainmaker Hotel, American Samoa (POD) 36-10 
Ralston & Leydon Creeks, CO (MRO) 26-21 
Ramapo River, Monroe, NJ (NAN) 2-35 
Rancocas River, NJ (NAP) 3-28 
Randleman Lake, NC (SAW) 6-11, 6-21 
Ranier Drainage District, Columbia County, OR 
(NPP) 37-37 
Ranier Drainage District, OR (NPP) 37-38 
Rapid City, Cedar Canyon Dam, SD (MRO) 26-19 
Rapid Creek, ID (NPW) 39-16 
Rapid Creek, Rapid City, SD (MRO) 26-16, 26-19 
Rapidan River, Orange, VA (NAO) 5-18 
Rappahannock River at Bowlers Wharf, VA (NAO) 
5-17 
Rappahannock River, VA (NAO) 5-17 
Rappahannock Shoal Channel, VA (NAO) 5-13 
Raritan Bay and Sandy Hook, NJ (NAN) 2-32 
Raritan River (NAN) 2-28, 2-30, 2-34 
Raritan River Cut-off (NAN) 2-28, 2-30 
Rat Root River, MN (NCS) 24-30 
Rathburn Lake, Chariton River, IA (MRK) 27-6, 
27-12, 27-15 
Rathburn Lake Fish Hatchery (MRK) 27-17 
Rawls Creek, Irmo, SC (SAN) 7-18 
Ray Roberts Lake, TX (SWF) 30-8, 30-16, 30-20 
Raymondville, TX (SWG) 31-14 
Raystown Lake, Raystown Branch, Juniata River, PA 
(NAB) 4-11, 4-24, 4-31 
Reconnaissance and Condition Surveys 
Albuquerque District (SWA) 32-12 
Baltimore District (NAB) 4-8 
Buffalo District (NCB) 20-10 
Charleston District (SAN) 7-8 
Chicago District (NCC) 22-6 
Detroit District (NCE) 21-38 
Galveston District (SWG) 31-10 
Jacksonville District (SAJ) 9-15 
Los Angeles District (SPL) 33-5 
Mobile District (SAM) 10-15 
New England Division (NED) 1-9 
New York District (NAN) 2-14, 2-28 
Pacific Ocean Division (POD) 36-2 
Philadelphia District (NAP) 3-14 
San Francisco District (SPN) 34-5 
Savannah District (SAS) 8-5 
Red Arroyo, San Angelo, TX (SWF) 30-23 
Red Bluff, CA (SPK) 35-40 
Red Brook Harbor, Bourne, MA (NED) 1-43 
Red Creek, NY 1966 FC Act (NCB) 20-45 
Red Hook Flats Anchorage (NAN) 2-28 
Red Lake and Red Lake River, MN (NCS) 24-23 
Red Lake River at Gentilly, MN (NCS) 24-24, 24-29 
Red Lake River at Huot, MN (NCS) 24-24 
Red Lake River at Red Lake Falls, MN (NCS) 24-24, 
24-29 
Red Lake River, East Grand Forks, MN (NCS) 24-31 
Red Lake River, MN including Clearwater River, MN 
(NCS) 24-11, 24-20 
Red Lake River, Red Lake County, Hwy 3, MN 
(NCS) 24-30 
Red River at East Grand Forks, MN (NCS) 24-28 
Red River at Fargo, MN (NCS) 24-28 
Red River at Grand Forks, MN (NCS) 24-28, 24-30 
Red River Bank Stabilization below Denison, OK and 
TX (SWT) 29-24 
Red River Basin Chloride Control, TX and OK (SWT) 
29-4, 29-13 
Red River below Denison Dam, levees and bank 
stabiliation (Vicksburg District) (LMK) 12-7, 
12-11, 12-14, 12-19 
Red River below Denison Dam (Vicksburg District) 
(LMK) 12-7, 12-14 
Red River below Fulton, AR (LMK) 12-16 
I-54

Red River Emergency Bank Protection (LMK) 
12-2(LMK) 12-10 
(LMK) 12-10, 12-12 
Red River from Fulton, AR to Mouth of Washita 
River (SWT) 29-23 
Red River, Hwy 71, Little River County, AR (SWL) 
28-9, 28-16 
Red River, Hwy. 31, Little River County, AR (SWL) 
28-22 
Red River, 1-30, Little River County, AR (SWL) 
28-9, 28-16, 28-22 
Red River in Vicinity of Shreveport, LA (LMK) 12-22 
Red River Lake, KY (Kentucky River) (ORL) 16-24 
Red River of the North at Argusville, ND (NCS) 
24-24, 24-29 
Red River of the North at East Grand Forks, MN 
(NCS) 24-30 
Red River of the North at Oslo, MN (NCS) 24-24 
Red River of the North at Halstad, MN (NCS) 24-24 
Red River of the North, County Road 2, ND (NCS) 
24-30 
Red River of the North at Breckenridge, MN (NCS) 
24-24, 24-29 
Red River of the North at Fargo, ND - Moorehead, 
MN (NCS) 24-11, 24-20, 24-31 
Red River of the North, Grand Forks, ND (NCS) 
24-31 
Red River of the North at Pembina, ND (NCS) 24-24 
Red River of the North, MN and ND (NCS) 24-23 
Red River of the North Drainage Basin, MN, SD and 
ND (NCS) 24-11, 24-20 
Red River of the North, Walsh County (NCS) 24-30, 
24-31 
Red River Parish, LA (LMK) 12-20, 12-22 
Red River, TN (ORN) 15-13 
Red River Waterway, LA, AR, OK and TX (LMK) 
12-16 
Red River-Waterway-Mississippi River to Shreveport, 
LA (LMK) 12-3, 12-10, 12-12 
Red River-Waterway-Shreveport, LA to Index, AR 
(LMK) 12-8, 12-11, 12-124 
Red River Waterway, Shreveport, LA to Daingerfield, 
TX (LMK) 12-16 
Red Rock Dam and Lake Red Rock, IA (NCR) 23-5, 
23-7, 23-10 
Red Run Drain, Lower Clinton River, MI (1970 Flood 
Control Act) (NCE) 21-87 
Red Wing Harbor, MN 25-7 
Redbank and Fancher Creeks, CA (SPK) 35-17, 35-29 
Redbank Creek Lake, PA (ORP) 18-24 
Redbird Creek, O'Neill, NE (MRO) 26-20 
Reddies River Lake, NC (SAN) 7-18, 6-28 
Redondo Beach Harbor (King Harbor), CA (SPL) 
33-4, 33-13, 33-20, 33-28 
Redwater River and Hay Creek, Belle Fourche, SD 
(MRO) 26-17 
Redwood City Harbor, CA (SPN) 34-8 
Redwood Creek, CA (SPN) 34-14 
Redwood River below Marshall, MN (NCS) 24-24 
Redwook Creek, Humboldt County, CA (SPK) 35-38 
Reeds Bay Small Boat Harbor, Hawaii, HI (POD) 
36-10 
Reedsport Levees, Umpqua River, OR (NPP) 37-39 
Reedy Creek, Sullivan County, TN (ORN) 15-18 
Reedy River, SC (SAN) 7-18 
Reese River, Battle Mountain, NV (SPK) 35-38 
Reevesville, IL (Cache River) (ORL) 16-23, 16-29, 
16-34 
Regulation of Hydraulic Mining and Preparation of 
Plans (CDC) 35-1A, 35-5A, 35-7A 
Regulatory Functions Program 
Mobile District (SAM) 10-31 
Regulatory Sunken Vessel Removal & National 
Emergency Preparedness 51-1 
Rehoboth Beach to Indian River Inlet, DE (NAP) 3-28 
Removal of Aquatic Growth from Navigable Waters in 
the State of Florida, (SAJ) 9-12, 9-30, 9-41, 9-56 
Removal of Aquatic Growth, LA (LMN) 11-16 
Removing of snags and wrecks from Mississippi River 
below mouth of Missouri River and from Old and 
Atchafalaya Rivers (LMM) 13-5 
Removing of snags and wrecks from Mississippi River 
below mouth of Missouri River and from Old and 
Atchafalaya Rivers (LMK) 12-16 
Removing Water Hyacinths (SAM) 10-49 
Rend Lake, Big Muddy River, IL (LSM) 14-13, 14-17 
Reno Beach-Howard Farms Area, OH (NCB) 20-13, 
20-22, 20-38 
Republican River, NE and KS (MRK) 27-20 
Research and Development 
Los Angeles District (SPL) 33-8 
Pittsburgh District (ORP) 18-12 
Sacramento District (SPK) 35-25 
Savannah District (SAS) 8-10 
Reservoirs at Headwaters of Mississippi River, MN 
(NCS) 24-2, 24-18, 24-22, 24-27, 24-31 
I-55

Restoration of Indian Fishing Grounds, Bonneville, 
OR (NPP) 37-39 
Revere Beach, MA (NED) 1-9, 1-28, 1-38 
Reynoldsville, PA (ORP) 18-22 
Rheem Creek, CA (SPK) 35-38 
Rheem Creek, CA (SPN) 34-14 
Rhodes Point to Tylerton, MD (NAB) 4-33 
Rice Creek, FL (SAJ) 9-49 
Richard B. Russell Dam and Lake, GA and SC 
(Formerly Trotters Shoals Lake, GA and SC) 
(SAS) 8-9, 8-12, 8-17 
Richland Creek, IL (LSM) 14-18 
Richland Lake, MO (MRK) 27-19 
Richmond Filtration Plant, VA (NAO) 5-18 
Richmond Harbor (Deepening), CA (SPN) 34-2, 34-8, 
34-11 
Richmond Harbor, ME (NED) 1-43 
Richmond, VA (NAO) 5-8, 5-11, 5-15 
Richmond's Island Harbor, ME (NED) 1-43 
Richwood and Fenwick, WV (ORH) 17-24 
Ridgeley, WV (NAB) 4-39 
Ridgeway & Vicinity (on Clarion River) (ORP) 18-23 
Ridgeway, PA (Elk Creek) (ORP) 18-22 
Right and Left Forks of Beaver Creek, KY (ORH) 
17-24 
Rillito River, AZ (SPL) 33-10, 33-15 
Rio Anton Ruiz-Runta, Santiago, PR (SAJ) 9-61 
Rio Cibuco, Vega Baja, PR (SAJ) 9-61 
Rio Culebrinas, Aguada, PR (SAJ) 9-61 
Rio De La Plata, PR (SAJ) 9-48 
Rio Descalabrada, Santa Isabel, PR (SAJ) 9-61 
Rio El Ojo De Aqua, PR (SAJ) 9-61 
Rio Fajardo, PR (SAJ) 9-61 
Rio Grande Basin, NM (SWA) 32-5, 32-14, 32-17 
Rio Grande Floodway, NM (SWA) 32-7, 32-14, 
32-17, 32-18 
Rio Grande Floodway, San Acacia to Bosque del 
Apache Unit, NM (SWA) 32-8, 32-14, 32-17 
Rio Guadiana, Naranjito, PR (SAJ) 9-61 
Rio Guamani, Guayama, PR (SAJ) 9-61 
Rio La Plata, Comerio, PR (SAJ) 9-61 
Rio Loco, Guanica, PR (SAJ) 9-61 
Rio Manati, Bareceloneta, PR (SAJ) 9-61 
Rio Niqua, Arroyo, PR (SAJ) 9-61 
Rio Puerto Nuevo, PR (SAJ) 9-48 
Riol Manati, PR (SAJ) 9-61 
Ripley, OH (ORH) 17-22, 17-24 
Ririe Lake, ID (NPW) 39-16 
Rising Sun, IN (ORL) 16-27, 16-31 
River des Peres, MO (LSM) 14-6, 14-13 
River Rouge, MI (NCE) 21-85 
Riverdale, West Springfield, MA (NED) 1-15, 1-30, 
1-39, 1-54 
Riverland Levee District, MO (LSM) 14-18 
Rivers and Harbors, Contributed Funds 
Mobile District (SAM) 10-32 
Riverside Area, Pasco, WA (NPW) 39-16 
Riverside Levees (SPL) 33-31 
Riverview, WV (ORH) 17-22 
Road Knife River, Staton, ND (MRO) 26-24 
Roanake River Upper Basin, VA Headwaters Area 
(SAW) 6-14, 6-21 
Roanoak Lake, TX (SWF) 30-22 
Roanoke River, 50-mile long Channel from Palmyra 
Landing to Weldon (SAW) 6-29 
Roanoke River Basin, VA and NC (SAW) 6-15, 6-31 
Roanoke River, NC (SAW) 6-26 
Roaring River Lake, NC (SAW) 6-28 
Roaring River, Wilkes County, NC (SAN) 7-18 
Roaring Springs Road, Bridge, TX (SWF) 30-23 
Robert Douglas Willis Hydropower, TX (SWF) 30-11, 
30-16, 30-21 
Robert F. Henry Lock and Dam, AL (SAM) 10-26, 
10-37 
Robert S. Kerr Lock and Dam (15), OK (SWT) 29-26 
Robert S. Kerr Lock and Dam and Reservoir, OK 
(SWT) 29-11, 29-19, 29-23 
Robert S. Kerr Marine Terminal, OK (SWT) 29-26 
Rochester & McCleary's Bluff Levee, IL (Wabash 
River) (ORL) 16-23, 16-29, 16-34 
Rochester Harbor, NY (NCB) 20-9, 20-19, 20-35 
Rochester Lake, Cedar River, IA (NCR) 23-14 
Rochester, MN (NCS) 24-12, 24-20 
Rochester, PA (ORP) 18-24 
Rock Creek, Granite County, MT (NPS) 38-28 
Rock Creek, Maxwell, IA (NCR) 23-16 
Rock Creek, Missoula County, MT (NPS) 38-28 
Rock Creek Road, MT (NPS) 38-28 
Rock Creek, Unicoi County, TN (ORN) 15-18 
Rock Hall Harbor, MD (NAB) 4-33 
Rock Island Harbor, IL 25-7 
Rock Island, IL (NCR) 23-12, 23-15 
Rock Island Slough, Wellington, KS (SWT) 29-27 
Rock River Agricultural Levees, IL (NCR) 23-13 
Rockaway Inlet to Norton Point (Coney Island) NY 
(NAN) 2-14, 2-21, 2-25 
I-56

Rockfish Creek, NC (SAW) 6-29 
Rockford, IL (NCR) 23-12 
Rockland Harbor, ME (NED) 1-43, 1-58 
Rockland Harbor, ME (uncompleted portion) (NED) 
1-50 
Rockland Lake, TX (SWF) 30-22 
Rockport and Old Harbors, Rockport, MA (NED) 
1-43 
Rockport Harbor and Pigeon Cove, Rockport, MA 
(NED) 1-43 
Rockport Harbor, ME (NED) 1-43 
Rockport, IN (ORL) 16-27, 16-31 
Rocky Creek and Basie Branch, MS (SAM) 10-56 
Rocky Ford Drainage and Levee District, IL (NCR) 
23-12 
Rocky Pass, AK (NPA) 40-11 
Rocky River, OH (NCB) 20-9, 20-20, 20-35 
Rocy Fork, OH (ORH) 17-23 
Rodeo Creek, CA (SPK) 35-38 
Rodeo Creek, CA (SPN) 34-14 
Rogers City Harbor, MI (1910 R&H Act) (NCE) 
21-87 
Rogue River Harbor at Gold Beach, OR (NPP) 37-7, 
37-23, 37-31 
Rogue River, OR (NPP) 37-39 
Roland Drainage District, Arkansas River, AR (SWL) 
28-22 
Rolling Fork, Lebanon Junction, KY (ORL) 16-37 
Rolling Fork River, Sevier County, AR (SWL) 28-22 
Rollison Channel, NC (SAW) 6-8, 6-20 
Rome, Coosa River, GA (SAM) 10-50, 10-51 
Rome, IN (ORL) 16-27, 16-31 
Rome Mohawk River, NY (NAN) 2-34 
Rondout Harbor (NAN) 2-30 
Roosevelt Campobello International Park, Lubec, ME 
(NED) 1-9, 1-28, 1-38 
Root Creek, Bolivar, NY (ORP) 18-22 
Root River at Hokah, MN (NCS) 24-12, 24-20 
Rose Creek Channel Improvements, San Diego, CA 
(SPL) 33-30 
Roseau River, MN (NCS) 24-13, 24-20 
Rosendale Harbor, MS (LMK) 12-16 
Rosendale, NY (NAN) 2-32 
Roseville, OH (ORH) 17-9, 17-15, 17-19, 17-24 
Rosiclaire, IL (ORL) 16-23, 16-34 
Rossview Lake, TN and KY (ORN) 15-14 
Rota Harbor, CNMI (POD) 36-7 
Rouge River, MI (1935 R&H Act) (NCE) 21-87 
Rouge River, MI (1958 R&H Act) (NCE) 21-87 
Rouge River, MI (1962 R&H Act) (NCE) 21-87 
Rouge River, MI (NCE) 21-29, 21-63, 21-79 
Rough River, KY (ORL) 16-29, 16-35 
Rough River Lake and Channel Improvement, KY 
(ORL) 16-10, 16-17, 16-22 
Rough River Lake, KY (ORL) 16-32 
Roughans Point, Revere, MA (NED) 1-20, 1-32, 1-40 
Rouses Point, Lake Champlain, NY (NAN) 2-30 
Rouseville, PA (ORP) 18-23 
Rowlesburg Lake, WV (ORP) 18-23 
Royal River, ME (NED) 1-43 
Ruby River, Wheatly Bridge, Near Twin Bridges, MT 
(MRO) 26-19 
Rudee Inlet, VA (NAO) 5-6, 5-10, 5-15 
Ruffy Brook, MN (NCS) 24-26 
Rumphs Hill Creek, Dorchester County, SC (SAN) 
7-18 
Rush Creek, Arlington, TX (SWF) 30-23 
Rush River, MN (NCS) 24-28 
Rushford, MN (NCS) 24-24, 24-29 
Russell & Allison Levee, IL (Wabash River) (ORL) 
16-24, 16-29 
Russell, KY (ORH) 17-21 
Russian River Basin, CA (SPK) 35-18, 35-30, 35-35, 
35-42, 35-43 
Russian River, CA (SPN) 34-14 
Rutland Otter Creek, VT (NAN) 2-34 
Rutledge Hollow Creek Channel Improvement, Poteet, 
TX (SWF) 30-22 
Rye Creek, MT (NPS) 38-28 
Rye Harbor, NH (NED) 1-43 
S 
S. River Drainage District, Marion County, MO 
(NCR) 23-16 
Sabana Grande, PR (SAJ) 9-61 
Sabine-Neches Waterway, TX (SWG) 31-7, 31-20, 
31-32, 31-39, 31-41, 31-46 
Sabine River and Tributaries (Echo to Morgan Bluff), 
TX (SWG) 31-38 
Sabula, IA (NCR) 23-12 
Sackets Harbor, NY 1945 R&H Act (NCB) 20-45 
Sackets Harbor, OH (NCB) 20-40 
Saco, MT (MRO) 26-16, 26-18 
Saco River ME (NED) 1-8, 1-28, 1-38 
Saco River ME (uncompleted portion) (NED) 1-50 
I-57

Sacramento, CA (SPK) 35-40 
Sacramento River and Tributaries, CA (Debris 
Control) (CDC) 35-2A, 35-5A 
Sacramento River and Tributaries from Collinsville to 
Shasta Dam, CA (SPK) 35-19, 35-30, 35-36, 
35-43 
Sacramento River, CA (CDC) 35-3A, 35-5A, 35-7A 
Sacramento River, CA (SPK) 35-2, 35-27, 35-35 
Sacramento River Deep Water Ship Channel, CA 
(SPK) 35-3, 35-27 
Sacramento River, Tehama, CA (SPK) 35-44 
Sacred Heart Hospital, Yankton, SD (MRO) 26-16 
Sag Harbor, NY (NAN) 2-30, 2-34 
Saginaw River, MI (NCE) 21-30, 21-39, 21-63, 
21-67, 21-79, 21-82 
Saipan Beach Road, CNMI (POD) 36-2 
Saipan Harbor, Northern Marianas (POD) 36-10 
Saipan Small Boat Harbor, CNMI (POD) 36-7 
Sakonnet Harbor, RI (NED) 1-43 
Sakonnet Harbor, RI (uncompleted portion) (NED) 
1-50 
Sakonnet River, RI (NED) 1-43 
Salado Creek near Patterson, CA (SPK) 35-44 
Salamanca, NY (ORP) 18-22 
Salamonie Lake, IN (ORL) 16-11, 16-17 
Salamonie River, Hartford, Ohio County, KY (ORL) 
16-35 
Salamonie River, Montpelier, IN (ORL) 16-37 
Salem Harbor, MA (NED) 1-43 
Salem Harbor, MA (uncompleted portion) (NED) 1-50 
Salem River, NJ (NAP) 3-8, 3-17, 3-22 
Salina, Smoky Hill River, KS (MRK) 27-17 
Salinas River, CA (SPK) 35-38 
Saline Point, LA (LMK) 12-20, 12-22 
Saline River & Tributaries, IL (ORL) 16-23, 16-35 
Salkahatchie River, SC (SAN) 7-17 
Salmon Creek at Oakridge, OR (NPP) 37-39 
Salmon Creek Near Vancouver, WA (NPP) 37-39 
Salmon River, AK (NPA) 40-12 
Salmon River, Colchester, CT (NED) 1-47, 1-54 
Salmon River, OR (NPP) 37-36 
Salt Creek and Tributaries, NE (MRO) 26-5, 26-10, 
26-14 
Salt Creek Levees, Lincoln, NE (MRO) 26-23 
Salt Creek, OH (ORH) 17-23 
Salt Creek Sewage Treatment Plant, Lincoln, NE 
(MRO) 26-20 
Salt Lake City, Jordan River, UT (SPK) 35-38 
Saluda River, SC (SAN) 7-18 
Salyersville, KY (ORL) 16-4, 16-14, 16-21 
Sam Rayburn Dam and Reservoir, TX (SWF) 30-11, 
30-16, 30-20 
Sam Rayburn Spillway (Dam Safety Assurance), TX 
(SWF) 30-12, 30-20 
Sammamish River, WA (NPS) 38-28 
San Antonio Channel Improvements, TX (SWF) 30-9, 
30-17, 30-20 
San Antonio Floodway, TX (SWF) 30-22 
San Diego (Sunset Cliffs), CA (SPL) 33-29 
San Diego Creek, Alice, TX (SWG) 31-38 
San Diego Harbor, CA (SPL) 33-4, 33-13, 33-20 
San Diego River (Mission Valley), San Diego River 
Basin, CA (SPL) 33-30 
San Diego River & Mission Bay, CA (SPL) 33-4, 
33-13, 33-22 
San Francisco Bay-Delta Model Structure, CA (SPN) 
34-3, 34-8 
San Francisco Bay Long Term Management Strategy 
(LTMS), CA (SPN) 34-4, 34-8 
San Francisco Bay to Stockton, CA (John F. Baldwin 
and Stockton Ship Channels) (SPN) 34-3, 34-8 
San Francisco Bay to Stockton, CA (John F. Baldwin 
and Stockton Ship Channels), CA (SPK) 35-3, 
35-27 
San Francisco Harbor (Islais Creek), CA (SPN) 34-13 
San Francisco Marina (Gas House Cove), CA (SPN) 
34-13 
San Gabriel River to Newport Bay (Surfside-Sunset 
and Newport Beach), Orange County, CA (SPL) 
33-29 
San Gabriel River, TX (SWF) 30-9, 30-17, 30-20 
San Jacinto River Levee & Bautista Creek Channel 
(SPL) 33-31 
San Joaquin River, CA (SPK) 35-4, 35-27, 35-41 
San Juan Dam (SPL) 33-32 
San Juan Harbor, PR (SAJ) 9-14, 9-30, 9-42 
San Juan, PR (SAJ) 9-50 
San Leandro Creek, CA (SPK) 35-38 
San Leandro Marina (Breakwater), CA (SPN) 34-13 
San Leandro Marina, CA (SPN) 34-8 
San Lorenzo Creek (Upper Portion), CA (SPN) 34-13 
San Lorenzo Creek, CA (SPK) 35-38 
San Lorenzo River, CA (SPK) 35-38 
San Luis Rey River, CA (SPL) 33-5, 33-13, 33-22 
San Pablo Bay and Mare Island Strait, CA (SPN) 34-9 
I-58

San Pablo Bay and Mare Island Strait (Approaches to 
Vallejo and South Vallejo), CA (SPN) 34-13 
San Rafael, CA (SPN) 34-9 
Sand Cove, Gouldsboro, ME (NED) 1-47 
Sand Creek LPP, KS (SWT) 29-24, 29-27 
Sand Hill Cove Beach, RI (NED) 1-45 
Sand Hill River, MN (NCS) 24-28 
Sand Island, Oahu, HI (POD) 36-8 
Sand Island Shore Protection, Oahu, HI (POD) 36-2, 
36-5 
Sand Lake, OK (SWT) 29-24 
Sandburg Creek, Spring Glen, NY (NAN) 2-32 
Sanders Creek, Boscobel, WI (NCS) 24-30 
Sandusky Harbor, OH (NCB) 20-9, 20-20, 20-35 
Sandusky River, OH (NCB) 20-40 
Sandy Bay (Harbor of Refuge), Cape Ann, MA (NED) 
1-43 
Sandy Bay, Cape Ann, MA (uncompleted portion) 
(NED) 1-50 
Sandy Creek, Jackson, TN (LMM) 13-6 
Sandy Drainage District, OR (NPP) 37-38 
Sandy Hook Bay at Atlantic Highlands (NAN) 2-28 
Sandy Hook Bay at Leonardo (NAN) 2-28, 2-30 
Sandy Hook Bay, NJ (NAN) 2-30 
Sandy Hook Channel (NAN) 2-28 
Sandy Hook to Barnegat Inlet, N.J. (NAN) 2-14, 
2-21, 2-26, 2-31 
Sandy Point, West Haven, CT (NED) 1-51 
Sandy River and Sleepy Hollow, OR (NPP) 37-38 
Sandy River, City of Troutdale, OR (NPP) 37-42 
Sangamon River (Mouth), IL (NCR) 23-12 
Sanitary District of Beardstown, IL (NCR) 23-15 
Sans Bois Navigation Channel, OK (SWT) 29-26 
Santa Ana Mainsteam, CA (SPL) 33-7, 33-14, 33-26 
Santa Ana River Basin and Orange County, CA (SPL) 
33-7, 33-14 
Santa Ana River Basin, CA (SPL) 33-30 
Santa Ana River Mainstem, CA (SPL) 33-10, 33-27 
Santa Barbara Harbor, CA (SPL) 33-4, 33-13, 33-22 
Santa Clara River, Fillmore, CA (SPL) 33-31 
Santa Clara River Levee Improvement, Santa Clara 
River Basin, CA (SPL) 33-31 
Santa Cruz County, CA (SPN) 34-13 
Santa Cruz Harbor, CA (SPN) 34-9 
Santa Fe River and Arroyo Mascaras, NM (SWA) 
32-19 
Santa Paula Creek, CA (SPL) 33-11, 33-14 
Santa Paula Creek Channel and Debris Basins 
(including Mud Creek), Santa Clara River Basin, 
CA (SPL) 33-31 
Santa Rosa Dam and Lake, NM (SWA) 32-8, 32-15 
Santa Rosa Wash (Tat Momolikot Dam and Lake St. 
Clair) (SPL) 33-30 
Santee River, NC & SC (SAN) 7-17 
Sapelo Harbor, GA (SAS) 8-18 
Sarasota County, FL (SAJ) 9-20, 9-32, 9-47 
Sardis Lake, OK (SWT) 29-9, 29-18, 29-22 
Sardis, OH (ORH) 17-22 
Sasanoa River, ME (NED) 1-43 
Sasco Hill Beach, Fairfield, CT (NED) 1-45 
Satilla River, GA (SAS) 8-18 
Saucelito Canal, Richardson Bay, CA (SPN) 34-13 
Saugatuck Harbor and Kalamazoo River, MI (NCE) 
21-34, 21-65, 21-81 
Saugerties Harbor, NY (NAN) 2-30 
Saugus and Pine Rivers, MA (NED) 1-51 
Sauk River, Skagit County, WA (NPS) 38-28 
Sauvie Island Areas A and B, Multnomah County, OR 
(NPP) 37-37 
Sauvie Island Drainage District, OR (NPP) 37-38 
Savage River Dam, MD (NAB) 4-35, 4-38 
Savan Gut, St. Thomas, VI (SAJ) 9-48, 9-61 
Savanna Harbor, IL 25-7 
Savannah City Park, TN (ORN) 15-18 
Savannah Harbor, GA (SAS) 8-4, 8-11, 8-14 
Savannah River above Augusta, GA (SAS) 8-18 
Savannah River at Augusta, GA (SAS) 8-18, 8-19 
Savannah River Basin, GA and SC (SAS) 8-8 
Savannah River Below Augusta, GA (SAS) 8-5, 8-11, 
8-16 
Saw Mill Run, PA (ORP) 18-22 
Saw Mill Run Road, Salamanca, NY (plans and 
specifications) (ORP) 18-30 
Sawmill Branch, SC (SAN) 7-18 
Sawmill R. Elmsford & Greenburgh, NY (NAN) 2-32 
Saxis Island, VA (NAO) 5-18 
Saxon Harbor, WI (NCE) 21-84, 21-90 
Saxonville, MA (NED) 1-47, 1-56 
Saylorville Lake, IA (NCR) 23-5, 23-7, 23-10 
Scajaquada Creek, NY (NCB) 20-42 
Scammon Bay, AK (NPA) 40-12 
Scappoose Drainage District, OR (NPP) 37-37 
Scappoose, OR (NPP) 37-42 
Scarboro River, ME (NED) 1-43 
I-59

Scheduling Flood Control Reservoir Operations 
Albuquerque District (SWA) 32-10 
Baltimore District (NAB) 4-19 
Fort Worth District, (SWF) 30-11 
Kansas City District) (MRK) 27-7, 27-12 
Los Angeles District (SPL) 33-8 
Mobile District (SAM) 10-30 
Omaha District (MRO) 26-6, 26-10 
Portland District (NPP) 37-14 
Sacramento District (SPK) 35-23 
Seattle District (NPS) 38-10 
Tulsa District (SWT) 29-10 
Walla Walla District (NPW) 39-3 
Wilmington District (SAW) 6-16 
Schuyler, Lost Creek and Platte River, NE (MRO) 
26-20 
Schuylkill River above Fairmount Dam, PA (NAP) 
3-25 
Schuylkill River, PA (NAP) 3-9, 3-18, 3-22 
Scioto River at Portsmith, OH (ORH) 17-20 
Sciotovile, OH (ORH) 17-22 
Scituate Harbor, MA (NED) 1-43 
Scott County D&L District, Illinois River, IL (LSM) 
14-18 
Scotts Creek, SC (SAN) 7-18 
Scotts Creek, VA (NAO) 5-15 
Scottsville, VA (NAO) 5-18 
Scranton, Buffalo, ND (MRO) 26-19 
Scranton, PA (NAB) 4-35, 4-38 
Scuppernong River, NC (SAW) 6-26, 6-29 
Sea Bluff Beach, West Haven, CT (NED) 1-45 
Seahorn Drainage and Levee District, IL (NCR) 
23-12, 23-15 
Searsport Harbor, ME (NED) 1-43, 1-58 
Seaside, OR (NPP) 37-42 
Seaside Park, CT (NED) 1-45 
Seattle Harbor (A Completed portion) (1925 R&H 
Act), WA (NPS) 38-30 
Seattle Harbor (Uncompleted portion), WA (NPS) 
38-30 
Skagit River (Uncompleted portion), WA (NPS) 38-30 
Seattle Harbor, WA (NPS) 38-6, 38-16, 38-22 
Sebasticook River, Hartland, ME (NED) 1-47 
Sebasticook River, Pittsfield, ME (NED) 1-52 
Sebewaing Harbor, MI (NCE) 21-35, 21-65, 21-81 
Sebewaing, Sebewaing River, MI (NCE) 21-41, 
21-67, 21-82 
Section 20 Aqueduct, Washita River, Caddo County, 
OK (SWT) 29-28 
Section 24 Aqueduct, Washita River, Caddo County, 
OK (SWT) 29-28 
Section 24 Road North Canadian River, Pottawatomie 
County, OK (SWT) 29-28 
Section 27 Road North Canadian River, Pottawatomie 
County, OK (SWT) 29-28 
Seekonk River, RI (NED) 1-43 
Seldovia Harbor, AK (NPA) 40-11 
Selkirk Shore State Park, Lake Ontario, NY (NCB) 
20-41 
Selkirk Shores State Park, OH 1954 R&H Act (NCB) 
20-45 
Seneca Falls, NY (NCB) 20-44 
Sequoyah Hills Park, Knoxville, TN (ORN) 15-18 
Sesuit Harbor, MA (NED) 1-8, 1-28, 1-38 
Sergius Whitestone, AK (NPA) 40-11 
Sespe Creek at Fillmore, Ventura County, CA (SPL) 
33-31 
Seveir River near Redmond, UT (SPK) 35-38 
Sewage Lagoon, Vale, OR (NPW) 39-16 
Sewage Lagoons, North Canadian River, New Castle 
(SWT) 29-28 
Sewage Lagoons, South Canadian River (SWT) 29-28 
Seward Expansion, AK (NPA) 40-13 
Seward Harbor, AK (NPA) 40-11 
Seward, NE (MRK) 27-17 
Sewer Outfall, Glendale, WV (construction completed) 
(ORP) 18-30 
Sewerline Protection Valley, AL (SAM) 10-50 
Seymour Creek, Seymour, TX (SWF) 30-23 
Shad Landing State Park, MD (NAB) 4-33 
Shades Creek, AL (SAM) 10-56 
Shallotte Inlet, NC (SAW) 6-30 
Shallotte River, NC (SAW) 6-8, 6-20 
Shallow Creek, MD (NAB) 4-33 
Shark River, NJ (NAN) 2-30 
Shawnee, OK (SWT) 29-29 
Shawneetown, IL (ORL) 16-23, 16-27, 16-31, 16-34 
Sheboygan Harbor, WI (NCE) 21-25, 21-65, 21-81 
Sheburne, NY (NAB) 4-38 
Sheepshead Bay (NAN) 2-28, 2-30 
Sheffield Lake Community Park, OH 1962 R&H Act 
(NCB) 20-45 
Sheffield Water Intake, AL (ORN) 15-18 
Shelburne, Androscoggin River, NH (NED) 1-47 
I-60

Shell Creek, County Road Near Columbus, NE 
(MRO) 26-20 
Shell Creek, NE (MRO) 26-17 
Shelley Area, Snake River, ID (NPW) 39-18 
Shelton Creek, WA (NPS) 38-28 
Shelton Ditch, Marion County, OR (NPP) 37-40 
Shenango River Lake, Ohio River Basin, PA and OH 
(ORP) 18-9, 18-14, 18-20, 18-28 
Shepard Road, Mississippi River, St. Paul, MN (NCS) 
24-24, 24-29 
Sheridan, Big and Little Goose Creeks, WY (MRO) 
26-19 
Sheridan, OR (NPP) 37-42 
Sheridan, WY (MRO) 26-16 
Sherwood Island State Park, Westport, CT (NED) 
1-45 
Sheyenne River, ND (NCS) 24-13, 24-20, 24-26, 
24-29 
Sheyenne River, Valley City, ND (NCS) 24-24 
Shidler Lake, OK (SWT) 29-24 
Shields River, near Clyde Park, MT (MRO) 26-16, 
26-18 
Shields River, Park County, MT (US 89) (MRO) 
26-23 
Shilshole Bay, Seattle, WA (NPS) 38-25 
Shinnecock Inlet, NY (NAN) 2-11, 2-20, 2-25, 2-29 
Shipyard River, SC (SAN) 7-7, 7-12, 7-16, 7-17 
Shoal Harbor & Compton Creek, NJ (NAN) 2-30 
Shoals, IN (East Fork White River) (ORL) 16-27 
Shooters Island, NJ & NY (NAN) 2-34 
Short Beach, CT (NED) 1-45 
Short Creek, Connerville, OH (complete) (ORP) 18-30 
Shoshone River, Bank Protection, Lovell, WY (MRO) 
26-19 
Shoshone River, Byron, MW (MRO) 26-19 
Shot Pouch Creek, Sumter County, SC (SAN) 7-18 
Shrewsbury River, N.J. (NAN) 2-12, 2-20, 2-25, 
2-28, 2-34 
Shufflebarger Levee, IN (ORL) 16-27, 16-31 
Shupe Run. Mt. Pleasant, PA (detalied project report 
underway) (ORP) 18-30 
Sid Simpson Project, IL (NCR) 23-12 
Sierra Madre Wash Channel, Los Angeles County 
Drainage Area, CA (SPL) 33-32 
Silver Beach, Milford, CT (NED) 1-52 
Silver Beach to Cedar Beach, CT (NED) 1-45, 1-50 
Silver Creek, Rome, GA (SAM) 10-20, 10-36, 10-46 
Silver Lake Harbor, NC (SAW) 6-8, 6-20, 6-24 
Simmons Bay, NC (SAW) 6-28 
Simms Bayou, TX (SWG) 31-14, 31-21, 31-36 
Simpson Creek, SC (SAN) 7-18 
Sims Park, Euclid, OH (NCB) 20-22, 20-38 
Singing Hills Creek, Watauga, TX (SWF) 30-23 
Sioux Falls, Big Sioux River, SD (MRO) 26-19, 26-21 
Sioux Falls, SD (MRO) 26-16 
Sisterville, OH (ORH) 17-22 
Sitka Harbor, AK (NPA) 40-11, 40-13 
Siuslaw River, Lane County, OR (NPP) 37-39 
Siuslaw River Near Florence, OR (NPP) 37-41 
Siuslaw River, OR (NPP) 37-7, 37-23, 37-31 
Six Bridge Lake, MD & PA (NAB) 4-37 
Six Runs Creek, NC (SAW) 6-29 
Slaughter Creek, MD (NAB) 4-33 
Skaggs Ferry, Black River, AR (SWL) 28-23 
Skagit County (Various Locations), WA (NPS) 38-28 
Skagit River (Avon Pass), WA (NPS) 38-30 
Skagit River (Levee and Channel Improvements), WA 
(NPS) 38-28 
Skagit River at Burlington Bend, WA (NPS) 38-28 
Skagit River, Cape Horn Road, WA (NPS) 38-28 
Skagit River, Deadman's Slough, WA (NPS) 38-28 
Skagit River, Pressentin Creek, WA (NPS) 38-28 
Skagit River, South Skagit Highway, WA (NPS) 38-28 
Skagit River, WA (NPS) 38-25 
Skagway Harbor, AK (NPA) 40-11 
Skagway River, AK (NPA) 40-12 
Skamokawa (Steamboat Slough), WA (NPP) 37-40 
Skamokawa Creek Area, Wahkiakum County, WA 
(NPP) 37-37 
Skamokawa Creek, WA (NPP) 37-36, 37-41 
Skiatook Lake, OK (SWT) 29-9, 29-18, 29-22 
Skiatook, OK (SWT) 29-29 
Skipanon Channel, OR (NPP) 37-8, 37-24, 37-32 
Skykomish River, North Fork, Index, WA (NPS) 
38-28 
Slovan, PA (ORP) 18-22 
Small Boat Harbor opposite Chester, IL (LSM) 14-18 
Small Navigation Project at Sioux City, IA (MRO) 
26-15 
Smelt Brook, Weymouth-Braintree, MA (NED) 1-47 
Smith Creek, CO (SWA) 32-19 
Smith Creek, MD (NAB) 4-33 
Smith Ferry, PA (ORP) 18-24 
Smith River, OR (NPP) 37-36 
Smith's Creek (Pamlico County), NC (SAW) 6-26 
Smithfield, WV (ORH) 17-24 
1-61

Smithville Channel, Little Platte River, MO (MRK) 
27-17 
Smithville Lake, Little Platte River, MO (MRK) 27-6, 
27-12, 27-15 
Smoky Hill, Saline, and Soloman Rivers (MRK) 27-20 
Smyrna River, DE (NAP) 3-25 
Snake River, Alvarado, MN (NCS) 24-30, 24-31 
Snake River, Blackfoot, ID (NPW) 39-16, 39-18 
Snake River Downstream from Johnson Bar Landing, 
OR, WA and ID (NPW) 39-7, 39-11, 39-14 
Snake River, Heise Bridge Location, ID (NPW) 39-16 
Snake River, Stevens, Blackfoot, ID (NPW) 39-16, 
39-18 
Snettisham, AK (NPA) 40-6, 40-8, 40-10 
Snohomish County (Various Locations), WA (NPS) 
38-28 
Snohomish River, Lowell-Snohomish River Road, WA 
(NPS) 38-28 
Snohomish River, Snohomish, WA (NPS) 38-28 
Snoqualmie River, West Snoqualmie, WA (NPS) 
38-28, 38-31 
Sny Basin, IL (NCR) 23-12, 23-15 
Sny Island Levee Drainage District, IL (NCR) 23-12, 
23-15, 23-16 
Soap Creek, Bridge Site #3, Davenport, IA (NCR) 
23-16 
Soap Creek, WA (NPP) 37-40 
Socastee Creek, SC (SAN) 7-8, 7-12, 7-16 
Socorro Diversion Channel, Tributaries or Rio 
Grande, NM (SWA) 32-19 
Soldier River, Near Ute, IA (MRO) 26-21 
Soleduck River Bridge, WA (NPS) 38-28 
Soleduck River, near Mora Road Bridge, WA (NPS) 
38-28 
Solomon Creek, Ashley Borough, Luzerne County, 
PA (NAB) 4-16, 4-25, 4-31 
Solomons Island, Calvert County, MD (NAB) 4-16, 
4-25, 4-31 
Somerville Lake, TX (SWF) 30-10, 30-17, 30-20 
Sonomo Creek, CA (SPK) 35-38 
Sope Creek, Marietta, GA (SAM) 10-50 
Souris River Basin, ND (NCS) 24-13, 24-20 
Souris River, Velva, ND (NCS) 24-24, 24-29 
South Agat (Route 2), Guam (POD) 36-11 
South Amsterdam, Mohawk River, NY (NAN) 2-32 
South Bank, Arkansas River, Little Rock to Pine 
Bluff, AR Tucker Lakes (SWL) 28-23 
South Beardstown and Valley Drainage and Levee 
District, IL, (NCR) 23-13 
South Beardstown Drainage and Levee District, IL 
(NCR) 23-13, 23-15 
South Beloit, IL (NCR) 23-14 
South Bristol Harbor, ME (NED) 1-43, 1-58 
South Channel, Government Island, OR (NPP) 37-36 
South Coventry Lake, CT (NED) 1-50 
South Creek, Martinburg, NE (MRO) 26-20 
South Creek, NC (SAW) 6-28 
South Deer Creek, OK (SWT) 29-27 
South Ellenville, NY (NAN) 2-32 
South Fork, Arkansas River (Head Fourche Island to 
Pennington Bayou), AR (SWL) 28-23 
South Fork, Boise River, ID (NPW) 39-16 
South Fork, Bon Secour River, AL (SAM) 10-51 
South Fork, Clearwater River, ID (NPW) 39-17 
South Fork, Clearwater River, Kooskia-Stites, ID 
(NPW) 39-16 
South Fork, Elkhorn River, Ewing, NE (MRO) 26-23 
South Fork of Cumberland River, KY (ORN) 15-13 
South Fork of the Santa Clara River, Santa Clarita 
Valley, CA (SPL) 33-31 
South Fork of Wildcat Creek, County Road 7 East, 
Tippecanoe County, IN (ORL) 16-35 
South Frankfort, KY (ORL) 16-21 
South Haven Harbor, MI (NCE) 21-36, 21-65, 21-81 
South Holston River, Kingsport, TN (ORN) 15-18 
South Main Channel, TX (SWG) 31-14 
South Milwaukee Harbor, WI (1836 Flood Control 
Act) (NCE) 21-87 
South Orange, NJ (NAN) 2-32 
South Platte River, Adams County, No. Washington 
Street, Water and Sanitary District, CO (MRO) 
26-19 
South Platte River Basin, CO (MRO) 26-5, 26-14 
South Platte River, Iliff, CO (MRO) 26-19 
South Platte River, Kersey, CO (MRO) 26-19 
South Platte River Levees and Channel Improvements, 
Chatfield Lake to Ft. Morgan, CO (MRO) 26-16 
South Platte River, Logan County Bridge, NE (MRO) 
26-23 
South Platte River, Merino, CO (MRO) 26-19 
South Platte River/Merino, Logan City, CO (MRO) 
26-23 
South Platte River, Platteville, CO (MRO) 26-19 
South Platte River, Weld County Bridge 87, CO 
(MRO) 26-23 
I-62

South Platte River, Weld County Bridge 28, CO 
(MRO) 26-23 
South Platte River, Weld County Bridge 61, CO 
(MRO) 26-23 
South Plymouth Lake, NY (NAB) 4-37 
South Point, OH (ORH) 17-22 
South Portsmouth, KY (ORH) 17-22 
South Quincy Drainage and Levee District, IL (NCR) 
23-13, 23-15 
South River, Conway, MA (NED) 1-47, 1-54 
South River Drainage District, MO (NCR) 23-13, 
23-15 
South River, NC (SAW) 6-26 
South Skunk River Logjam, Keokuk, IA (NCR) 23-16 
South Slough (Charleston), OR (NPP) 37-36 
South Table Creek, Nebraska City, NE (MRO) 26-23 
South Turnbridge Lake, VT (NED) 1-50 
South Williamson, KY (ORH) 17-24 
Southeast Lighthouse, Block Island, RI (NED) 1-10, 
1-38 
Southeast Missouri Port, MO (LSM) 14-11 
Southeast Missouri Port, MO (LSM) 14-2, 14-9 
Southern New York Flood Control Projects (NAB) 
4-12, 4-31 
Southport Beach, CT (NED) 1-45 
Southport Harbor, CT (NED) 1-43 
Southwest Harbor, ME (NED) 1-43 
Southwest Ohio Urban Waterfront Development 
(ORL) 16-24 
Southwestern Jefferson County, KY (ORL) 16-4, 
16-14, 16-34 
Southwind Maritime Center, Mt. Vernon, IN (ORL) 
16-37 
Sowashee Creek, Meridian, MS (SAM) 10-20, 10-36, 
i0-46, 10-47 
Spanish Fork River, UT (SPK) 35-40 
Spokane River, Spokane, WA (NPS) 38-28, 38-30 
Spring Brook Creek, Pittston Township, PA (NAB) 
4-16, 4-26, 4-31 
Spring City, KY (ORN) 15-18 
Spring Lake Drainage and Levee District, IL (NCR) 
23-13, 23-15 
Springdale, MA (NED) 1-47, 1-54 
Springers Branch, MS (SAM) 10-56 
Springfield, MA (NED) 1-47, 1-54 
Springfield Millrace, OR (NPP) 37-42 
Springfield, SD Water Intake (MRO) 26-17 
Squalicum Small Boat Harbor, Bellingham, WA (NPS) 
38-25 
Squantz Pond, New Fairfield, CT (NED) 1-47 
Squaw Chute at Quincy, IL (NCR) 23-11 
St Catherines Sound, MD (NAB) 4-33 
St. Albans Harbor, Lake Champlain, NY (NAN) 2-30 
St. Anthony Falls Lower Lock and Dam 25-9 
St. Augustine Harbor, FL (SAJ) 9-13, 9-30, 9-41 
St. Clair County, AL (SAM) 10-56 
St. Clair River Compensating Works, MI (1930 R&H 
Act) (NCE) 21-87 
St. Clair River, MI (NCE) 21-31, 21-64, 21-79, 21-88 
St. Croix River, ME (NED) 1-43 
St. Croix River, MN and WI (NCS) 24-23, 24-30 
St. Francis and L'Anguille Rivers and Blackfish 
Bayou, AR (LMM) 13-5 
St. Francis River Highway No. 90, AR (LMM) 13-6 
St. George, AK (NPA) 40-4, 40-8, 40-10 
St. Georges Creek, MD (NAB) 4-33, 4-37, 4-38 
St. Hilaire, MN (NCS) 24-30 
St. James, Beaver Island, MI (NCE) 21-84 
St. James Harbor, MI (NCE) 21-90 
St. Jeromes Creek, MD (NAB) 4-33, 4-38 
St. John River Basin, ME (NED) 1-47 
St. Johns County, FL (SAJ) 9-47 
St. Johns River, Jacksonville to Lake Harney, FL 
(SAJ) 9-13, 9-30, 9-41, 9-51 
St. Jones River, DE (NAP) 3-25 
St. Jones River, DE, Delaware Bay to Lebanon Jetties 
and new entrance at mouth (NAP) 3-26 
St. Joseph Harbor, MI (NCE) 21-31, 21-64, 21-80 
St. Joseph River, MI (NCE) 21-84 
St. Louis County Drainage and Levee District No. 1, 
MO (LSM) 14-18 
St. Louis Harbor, MO and IL (LSM) 14-3, 14-11 
St. Lucie Inlet, FL (SAJ) 9-13, 9-30, 9-41, 9-51 
St. Maries, St. Joe River, ID (NPS) 38-28 
St. Marks River, FL (SAM) 10-52, 10-49 
St. Mary's, AK (NPA) 40-13 
St. Mary's River, GA and FL, and North River, GA 
(SAS) 8-18 
St. Mary's, WV (ORH) 17-22 
St. Marys, PA (Allegheny River Basin) (ORP) 18-24 
St. Marys River (MacArthur Lock Guard Gates), MI 
(1942 R&H Act) (NCE) 21-87 
St. Marys River, MI (NCE) 21-32, 21-64, 21-80 
St. Michael Canal, AK (NPA) 40-11 
St. Michaels Harbor, MD (NAB) 4-33 
I-63

St. Patricks Creek, MD (NAB) 4-33 
St. Paul and South St. Paul, MN (NCS) 24-24 
St. Paul Harbor, MN 25-7 
St. Paul Island Harbor, AK (NPA) 40-4, 40-8, 40-10, 
40-13 
St. Paul, MN (NCS) 24-15, 24-20 
St. Peters Creek, MD (NAB) 4-33, 4-38 
St. Petersburg Harbor, FL (SAJ) 9-49 
St. Regis River at St. Regis, MT (NPS) 38-28 
St. Regis River, MT (NPS) 38-28, 38-30 
St. Thomas Harbor, VI (SAJ) 9-49 
Stamford, CT (NED) 1-20, 1-32, 1-40 
Stamford Harbor, CT (2 projects uncompleted 
portions), (NED) 1-50 
Stamford Harbor, CT (inactive portion) (NED) 1-50 
Stamford Harbor, CT (NED) 1-43, 1-58 
Starlings Creek, VA (NAO) 5-17, 5-19 
Startup, Skykomish and Wallace Rivers, WA (NPS) 
38-28 
State Highway 111 Bridge, Lake Texana, TX (SWG) 
31-15, 31-21 
State Highway 156, Kay County, OK (SWT) 29-28 
State Hwy 101 & 401, Columbia River, WA (NPP) 
37-37 
State Road & Ebner Coulees, WI (NCS) 24-24 
State Road and Ebner Coulees, WI (NCS) 24-14, 
24-20 
Staten Island, NY (NAN) 2-32 
Staten Island Rapid Transit Railway Bridge, Arthur 
Kill, NY (NAN) 2-30 
Ste. Genevieve Drainage and Levee District No. 1, 
MO (LSM) 14-18 
Ste. Genevieve, MO (LSM) 14-13 
Steinhatchee River, FL (SAJ) 9-49 
Sterling, KS (SWT) 29-29 
Stevens Creek, Decatur, IL (NCR) 23-16 
Stevens Creek, Village of Forsyth, IL (NCR) 23-16 
Stewart Canyon Debris Basin and Channel (SPL) 
33-31 
Stikine River, AK (NPA) 40-11 
Stillaguamish River, South Fork, Mountain Loop 
Highway, near Robe, WA (NPS) 38-28 
Stillaguamish River, WA (NPS) 38-10, 38-17, 38-23, 
38-30, 38-31 
Stillhouse Hollow Dam, TX (SWF) 30-10, 30-17, 
30-20 
Stillwater and Whitefish Rivers, MT (NPS) 38-28 
Stillwater Lake, Lackawanna River, PA (NAB) 4-17, 
4-26, 4-31 
Stillwater River, MT (NPS) 38-28 
Stillwell Drainage District, Tillamook Bay, OR (NPP) 
37-39 
Stockton Harbor, ME (NED) 1-43 
Stockton Lake, Sac River, MO (MRK) 27-9, 27-12, 
27-16, 27-20 
Stonehouse Creek, Jefferson County, KS (MRK) 27-17 
Stoner Creek, North Middleton, KY (ORL) 16-35 
Stonewall Jackson Lake, Ohio River Basin, WV 
(ORP) 18-9, 18-14, 18-20, 18-28 
Stoney Creek, Branford, CT (NED) 1-43 
Stoneycreek River, Johnstown, PA (complete) (ORP) 
18-30 
Stonington Harbor, CT (NED) 1-43 
Stonington Harbor, CT (uncompleted portion) (NED) 
1-50 
Stonington Harbor, ME (NED) 1-43, 1-50, 1-58 
Stony Brook, Wilton, NH (NED) 1-47 
Stratford, CT (NED) 1-50 
Stream 5B13, Dallas, TX (SWF) 30-23 
Strington, Ft. Chartres, and Ivy Landing, IL (LSM) 
14-17 
Strong Creek, Hope, ID (NPS) 38-28 
Stuart Gulch Dam, Boise, ID (NPW) 39-17 
Stuart, VA (SAW) 6-28 
Stumpy Point Bay, NC (SAW) 6-9, 6-20 
Sturgeon Bay and Lake Michigan Ship Canal, WI 
(NCE) 21-36, 21-66, 21-81 
Sturgeon Point, Evans, NY (NCB) 20-11, 20-37 
Sturgis, KY (ORL) 16-23, 16-29, 16-34 
Subdistrict No. 1 of Drainage Union No. 1 and Bay 
Island Drainage and Levee District No. 1, IL 
(NCR) 23-13, 23-15 
Sucker Brook Dam, CT (NED) 1-47, 1-53 
Sugar Creek, Bellbrook, OH (ORL) 16-37 
Sugar Creek Levee, IN (ORL) 16-27, 16-31 
Sugar Creek, Watermelon Hollow Road, Montgomery 
County, IN (ORL) 16-37 
Sugar Hill Reservoir, NH (NED) 1-50 
Suisun Bay Channel, CA (SPN) 34-9 
Suisun Channel, CA (SPN) 34-9 
Sullivan Falls Harbor, ME (NED) 1-43 
Sulphur Branch, Euless, TX (SWF) 30-23 
Sulphur River, AR and TX (LMN) 11-16 
Sulphur RW Red River, Franklin City, TX (SWF) 
30-23 
I-64

Summersville Lake, Ohio River Basin, WV (ORH) 
17-9, 17-15, 17-19 
Summerville Creek, Dorchester County, SC (SAN) 
7-18 
Sumner Parker Airport, OR (NPP) 37-39 
Sumpawanus (Babylon Creek) Inlet, NY (NAN) 2-30 
Sun Creek, Okibbeha County, MS (SAM) 10-50 
Sunbright, TN (Whiteoak Creek) (ORN) 15-18 
Sunbury, PA (NAB) 4-35, 4-39 
Sunset Harbor (Bolsa Chica Bay), CA (SPL) 33-28 
Supervisor of New York Harbor (NAN) 2-1, 2-2, 
2-13, 2-20, 2-27 
Supervisor of the Harbor of Hampton Roads 
(Prevention of Obstructive and Injurious Deposits) 
(NAO) 5-6, 5-11 
Surry Mountain Lake, NH (NED) 1-16, 1-30, 1-53 
Surveillance of Northern Waters and International 
Water Studies 
Detroit District (NCE) 21-42, 21-68 
Surveys 
Alaska District (NPA) 40-6 
Baltimore District (NAB) 4-20 
Buffalo District (NCB) 20-14 
Chicago District (NCC) 22-11 
Detroit District (NCE) 21-46 
Fort Worth District, (SWF) 30-12 
Galveston District (SWG) 31-17 
Huntington District (ORH) 17-11 
Jacksonville District (SAJ) 9-23 
Little Rock District (SWL) 28-13 
Los Angeles District (SPL) 33-8 
Louisville District (ORL) 16-13 
Mobile District (SAM) 10-31 
Nashville District (ORN) 15-7 
New England Division (NED) 1-24 
New York District (NAN) 2-17 
Norfolk District (NAO) 5-8, 5-11 
Pacific Ocean Division (POD) 36-4 
Philadelphia District (NAP) 3-14 
Pittsburgh District (ORP) 18-12 
Portland District (NPP) 37-21 
Rock Island District (NCR) 23-6 
Sacramento District (SPK) 35-25 
San Francisco District (SPN) 34-5 
Savannah District (SAS) 8-10 
Seattle District (NPS) 38-12 
St. Paul District (NCS) 24-16 
Tulsa District (SWT) 29-12 
Walla Walla District (NPW) 39-8 
Wilmington District (SAW) 6-17 
Susquehanna River above and below Havre De Grace, 
MD (NAB) 4-33 
Susquehanna River at Williamsport, PA (NAB) 4-33 
Susquehanna River Flood Control Projects, NY and 
PA (NAB) 4-17, 4-31 
Sutton Lake, Ohio River Basin, WV (ORH) 17-10, 
17-15, 17-19 
Suwannee River, FL (SAJ) 9-49 
Swan Creek Bank Stabilization, Taney County, AR 
(SWL) 28-23 
Swan Creek, Toledo, OH (NCB) 20-22, 20-39 
Swanton Harbor, VT (NAN) 2-34 
Swash Channel (NAN) 2-29 
Sweetwater Creek, Austell, GA (SAM) 10-51 
Sweetwater Creek, NC (SAW) 6-29 
Sweetwater River, CA (SPL) 33-11, 33-14 
Swift Creek, NC (SAW) 6-26 
Swift Creek, Pitt and Craven Counties, NC (SAW) 
6-28 
Swinomish Channel, WA (NPS) 38-7, 38-16, 38-22, 
38-31 
Swoyersville-Forty Fort, PA (NAB) 4-35, 4-39 
Sycamore Creek, Coffeyville, KS (SWT) 29-27 
Sykesville, PA (ORP) 18-22 
Sylvia State Beach, Oak Bluffs, MA (NED) 1-51 
Syracuse, OH (ORH) 17-22 
Syracuse, Oswego River Basin, NY (NCB) 20-42 
T 
Table Rock Lake, MO (SWL) 28-12, 28-17, 28-30 
Tacoma Harbor, WA (NPS) 38-7, 38-16, 38-22 
Tacoma, Puyallup River, WA (NPS) 38-10, 38-17, 
38-23 
Tahchevah Creek Detention Basin and Channel 
Improvements (SPL) 33-31 
Tahola, WA (NPS) 38-28 
Tahquitz Creek (SPL) 33-31 
Talkeetna River, AK (NPA) 40-12 
Tallabinella Creek, Chickasaw County, MS (SAM) 
10-50 
Tallahalla Creek, Laurel, MS (SAM) 10-21, 10-36 
Tallahalla Creek, Pascagoula River, MS (SAM) 10-47, 
10-47 
Tallahatchie and Coldwater Rivers, MS (LMK) 12-16 
Talofofo Bay Shore Protection, Guam (POD) 36-11 
I-65

Tama, IA (NCR) 23-16 
Tamaqua, PA (NAP) 3-27 
Tampa and Hillsborough Bays, FL (SAJ) 9-43 
Tampa Harbor Branch Channels, FL (SAJ) 9-30, 9-45 
Tampa Harbor East Bay Channel, FL (SAJ) 9-30, 
9-45 
Tampa Harbor, FL (SAJ) 9-15, 9-30, 9-31, 9-43 
Tangier Channels, VA (NAO) 5-5, 5-10, 5-15, 5-17, 
5-19 
Tangier Island Shore Protection, VA (NAO) 5-18 
Tangipahoa River, LA (LMN) 11-16 
Tar River and Tributaries, NC (SAW) 6-28 
Tar River, NC (SAW) 6-28 
Tarentum, PA (ORP) 18-22 
Tarrytown Harbor, NY (NAN) 2-13, 2-20, 2-25, 2-29 
Taskinas Creek, VA (NAO) 5-17 
Tau Small Boat Harbor, American Samoa (POD) 36-7 
Taunton River, MA (inactive portion) (NED) 1-50 
Taunton River, MA (NED) 1-43 
Tawas Bay Harbor, MI (NCE) 21-84 
Taylors Bayou, TX (SWG) 31-15, 31-21, 31-36, 
31-46 
Taylorsville, KY (Salt River) (ORL) 16-23, 16-29, 
16-34 
Taylorsville Lake, KY (ORL) 16-11, 16-17 
Telegraph Canyon Creek, Chula Vista, CA (SPL) 
33-31 
Tell City, IN (ORL) 16-23, 16-24, 16-29, 16-34 
Ten Mile Creek, De Soto, TX (SWF) 30-23 
Ten Mile Creek, Lancaster, TX (SWF) 30-23 
Ten Mile River, Chesire, CT (NED) 1-52 
Tenants Harbor, ME (NED) 1-43, 1-58 
Tenasillahe Island, Clatsop County, OR (NPP) 37-37 
Tenkiller Ferry Lake, OK (SWL) 28-28 
Tenkiller Ferry Lake, OK (SWT) 29-12, 29-20, 29-23, 
29-26 
Tenmile Creek at Marianna, PA (ORP) 18-22 
Tennessee River, Chattanooga, TN (ORN) 15-18 
Tennessee River, TN, AL and KY (ORN) 15-3, 15-9, 
15-11, 15-16, 15-17 
Tennessee-Tombigbee Waterway, AL and MS (ORN) 
15-3, 15-9, 15-12 
Tennessee-Tombigbee Waterway, AL and MS (SAM) 
10-13, 10-35, 10-45, 10-55 
Tennessee-Tombigbee Wildlife Mitigation, AL and MS 
(SAM) 10-14, 10-35, 10-46 
Tensas River and Bayou Macon, LA (LMK) 12-16 
Terre Haute (Conover Levee), IN (Wabash River) 
(ORL) 16-23, 16-34, 16-37 
Terre Haute, IN (ORL) 16-27 
Terre Noire Creek, AR (LMK) 12-18 
Teton River, Chateau/Teton County, CO (MRO) 
26-24 
Teton River, ID (NPW) 39-17 
Teton River, Teton County, MT (MRO) 26-24 
Teton RV/Chateau/Teton County, MT (MRO) 26-23 
Texas City and Vicinity (Hurricane Flood Protection), 
TX (SWG) 31-15, 31-21, 31-36 
Texas City Channel, TX (SWG) 31-8, 31-20, 31-33, 
31-39 
Thames River Basin, CT, RI and MA (NED) 1-20 
Thames River, CT (NED) 1-43 
Thames River, CT (uncompleted portion) (NED) 1-50 
Thatcher Brook, Gowanda, NY (NCB) 20-44 
The Cascades Canal, Columbia River, OR (NPP) 
37-36 
The Dalles-Celilo Canal, OR and WA (NPP) 37-36 
The Dalles Lock and Dam - Lacke Celilo, WA and 
OR (NPP) 37-20, 37-27, 37-34, 37-43 
The Inland Route, MI (NCE) 21-16, 21-54, 21-74 
The Island Lake, VT (NED) 1-50 
Thimble Shoals Channel, VA (NAO) 5-17 
Thomas Creek, CA (SPK) 35-43 
Thomas Creek, Reno, NV (SPK) 35-44 
Thomaston Dam, CT (NED) 1-18, 1-31, 1-55 
Thoroughfare Swamp, NC (SAW) 6-29 
Three Forks, Lower Madison River (MRO) 26-18 
Three Islands Reservoir, Ohio River Basin, TN (ORN) 
15-14 
Three Rivers, MA (NED) 1-47, 1-54 
Three Rivers, TX (SWG) 31-38 
Threemile Creek, Mobile, LA (SAM) 10-21, 10-36, 
10-47 
Thumperton Beach, Eastham, MA (NED) 1-50 
Thurman to Hamburg, IA (MRO) 26-21 
Thurston County (Various Locations), WA (NPS) 
38-28 
Tickfaw, Natalbany, Ponchatoula, and Blood Rivers, 
LA (LMN) 11-16 
Ticonderoga River, NY (NAN) 2-34 
Tiger Creek, Columbus, GA (SAM) 10-51 
Tijuana River Basin, CA (SPL) 33-31 
Tilghman Island Harbor, MD (NAB) 4-33 
Tillamook Bay and Bar, OR (NPP) 37-8, 37-24, 
37-32, 37-41 
I-66

Tillamook River, OR (NPP) 37-42 
Tioga-Hammond Lakes, PA (NAB) 4-18, 4-26 
Tionesta Lake, Ohio River Basin, PA (ORP) 18-10, 
18-15, 18-21, 18-28 
Toad Suck Ferry Lock and Dam (No. 8), AR (SWL) 
28-4 
Tocks Island (Relocation of U.S. Route 209 only), PA 
(NAP) 3-28 
Tocks Island, PA, NJ and NY (NAP) 3-28 
Todd Swamp, SC (SAN) 7-18 
Toledo Harbor, OH (NCB) 20-9, 20-20, 20-36 
Tolovana River (Snagging), AK (NPA) 40-12 
Tolu, KY (ORL) 16-27, 16-31 
Tom Jenkins Dam, Ohio River Basin, OH (ORH) 
17-10, 17-15, 17-19 
Tomahawk Lake, Blue River, KS (MRK) 27-19 
Tomanovich-Salmon City, ID (NPW) 39-16 
Tombigbee River (East Fork), MS & AL (SAM) 
10-21, 10-36, 10-47 
Tombigbee River & Tributaries, MS & AL (SAM) 
10-22, 10-36, 10-47 
Tombigbee River at Columbus Port, MS (SAM) 10-49 
Tombigbee River Bridge #6, Monroe County, MS 
(SAM) 10-51 
Tombigbee River, Demopolis, AL (SAM) 10-51 
Toms River, NJ, Channel 12 feet deep (NAP) 3-28 
Toms River, NJ, Channel 5 feet deep (NAP) 3-25 
Tongue Point, OR (NPP) 37-8, 37-24, 37-32 
Tongue Point, OR (NPP) 37-41 
Tongue River Lake, ND (NCS) 24-26 
Topeka, Kansas River, KS (MRK) 27-17, 27-20 
Topsail Bay and Surf City, NC (SAW) 6-29 
Toronto Lake, KS (SWL) 28-28 
Toronto Lake, KS (SWT) 29-9, 29-18, 29-22 
Torrington, East Branch, CT (NED) 1-47, 1-55, 1-55 
Torrington, West Branch, CT (NED) 1-47, 1-55 
Totuskey Creek, VA (NAO) 5-17 
Touchet River, Waitsburg, WA (NPW) 39-16, 39-17, 
39-18 
Toussaint River, Carroll Township, OH (NCB) 20-21, 
20-37 
Towanda Lake, KS (SWT) 29-25 
Town Beach, Madison, CT (NED) 1-51 
Town Beach, Narragansett, RI (NED) 1-51 
Town Beach, Plymouth, MA (inactive portion) (NED) 
1-50 
Town Beach, Plymouth, MA (NED) 1-45 
Town Bluff Dam- B.A. Steinhagen Lake, TX (SWF) 
30-12, 30-17, 30-21 
Town Branch Creek, Lockhart, TX (SWF) 30-23 
Town Brook, Quincy and Braintree, MA (NED) 1-22, 
1-33, 1-40 
Town Creek, Americus, GA (SAM) 10-50 
Town Creek, Harrodsburg, KY (ORL) 16-23, 16-34 
Town Creek, MD (NAB) 4-33 
Town Creek, SC (SAN) 7-7, 7-12, 7-16 
Town Neck Beach, Sandwich, MA (NED) 1-50 
Town River Bay, Quincy, MA (NED) 1-22, 1-33, 
1-40 
Townsends Inlet and Seven Mile Beach, NJ (NAP) 
3-27 
Townshend Lake, VT (NED) 1-16, 1-30, 1-53 
Trabuco Dam (SPL) 33-32 
Tradewater River, KY (ORL) 16-22 
Tranquitas Creek, Kingsville, TX (SWG) 31-38 
Tranters Creek, NC (SAW) 6-29 
Trask River, Tillamook County, OR (NPP) 37-39 
Treasure Island, MO (LMM) 13-6 
Treatment of Yuba River debris situation-restraining 
barriers, CA (CDC) 35-2A, 35-5A 
Tred Avon River, MD (NAB) 4-33 
Tremplealeau River, Arcadia, WI (NCS) 24-29 
Trent River, Basins and Access Channels at New 
Bern, NC (SAW) 6-29 
Trent River, NC (SAW) 6-26, 6-28 
Trenton Lake, Thompson River, MO (MRK) 27-17 
Trexler Lake, PA (NAP) 3-28 
Tri Pond Levee, IL (ORL) 16-27, 16-31 
Trim Cane Creek, Okitbbeha County, MS (SAM) 
10-50 
Trimble Wildlife Area, Smithville Lake, MO (MRK) 
27-17 
Trinidad Lake, CO (SWA) 32-9, 32-15 
Trinity River and Tributaries, TX (SWG) 31-8, 31-20, 
31-34, 31-39, 31-46 
Trinity River Project, TX (SWF) 30-2, 30-15, 30-21 
Triplett Creek, Morehead, KY (Licking River) (ORL) 
16-24, 16-35 
Tropicana and Flamingo Washes, NV (SPL) 33-11, 
33-14 
Troublesome Creek, Hindman, KY (ORL) 16-35 
Troy, IN (ORL) 16-27, 16-31 
Truckee Meadows, NV (SPK) 35-25, 35-34 
Truckee River and Tributaries, CA and NV (SPK) 
35-38 
I-67

Trumbell Creek, MT (NPS) 38-31 
Trumbull Lake, CT (NED) 1-47 
Trussville, AL (SAM) 10-50 
Truth or Consequences Unit, NM (SWA) 32-8, 32-14, 
32-18 
Tualatin, OR (NPP) 37-39 
Tucannon River, Wooten, WA (NPW) 39-16, 39-18 
Tuckahoe River, MD (NAB) 4-33 
Tuckerton Creek, NJ (NAP) 3-25 
Tug and Levisa Forks of the Big Sandy River and 
Cumberland River, WV, VA and KY (ORN) 
15-5, 15-9 
Tully Lake, MA (NED) 1-16, 1-30, 1-53 
Tulsa and West Tulsa, OK (SWT) 29-9, 29-18, 29-22, 
29-24 
Tulsa/West Tulsa Levees, OK (SWT) 29-27 
Tunkhannock Creek, Tunkhannock, PA (NAB) 4-35 
Turkey Creek, Sumter County, SC (SAN) 7-18 
Turkey Creek, Sumter County, SC (SAN) 7-18 
Turkey River, Elkader, IA (NCR) 23-16 
Turner Creek, Corinth, MS (LMM) 13-6 
Turner Prairie, Mill Creek, OR (NPP) 37-40 
Turpentine Run, St. Thomas, VI (SAJ) 9-61 
Turtle Cree, PA (ORP) 18-22 
Turtle Creek LPP, Yukon, OK (SWT) 29-24 
Turtle Creek, PA (ORP) 18-5, 18-13 
Tuscon Diversion Channel (SPL) 33-30 
Tuskahoma Lake, OK (SWT) 29-24 
Tuttle Creek Lake, Big Blue River, KS (MRK) 27-7, 
27-12, 27-16, 27-20 
Tuttle Creek Lake, KS (Road Improvement - 1974 
Mod.) (MRK) 27-19 
Tuttle Creek Lake, KS Road and Bridge (1976 Act) 
(MRK) 27-19, 27-20 
Twelvemile Bayou, LA (LMK) 12-22 
Twenty Mile Creek, Airport Road Bridge, 
Frankstown, MS (SAM) 10-50 
Twin Valley Lake, MN (NCS) 24-24 
Twitch Cove and Big Thorofare, MD (NAB) 4-7, 
4-23, 4-29, 4-33 
Two Harbors, MN (NCE) 21-37, 21-66, 21-82 
Two Rivers Dam, NM (SWA) 32-10, 32-15 
Two Rivers Harbor, WI (1935 R&H Act) (NCE) 
21-87 
Two Rivers Harbor, WI (NCE) 21-37, 21-66, 21-82 
Tyaskin Creek, MD (NAB) 4-33, 4-38 
Tybee Island, GA (SAS) 8-6, 8-11, 8-16 
Tygart Lake, WV (ORP) 18-3, 18-13, 18-18 
Tylers Beach Channel, VA (NAO) 5-6, 5-10, 5-15, 
5-17 
Tyrone, PA (NAB) 4-35, 4-39 
U 
U.S. 190 Bridge, Sabine River, Merryville, TX 
(SWG) 31-16, 31-21 
Umatac Shoreline, Guam (POD) 36-11 
Umatilla Harbor, OR (NPP) 37-36 
Umatilla River (Echo), OR (NPP) 37-40 
Umatilla River, OR (NPW) 39-16 
Umatilla River, Stanfield, OR (NPP) 37-39, 37-42 
Umatilla River, Thorn Hollow, OR (NPP) 37-39 
Umatilla River Water District, OR (NPP) 37-42 
Umpqua River and Tributaries, OR (NPP) 37-39 
Umpqua River, OR (NPP) 37-9, 37-24, 37-32 
Umpqua River-Scholfield River, OR (NPP) 37-40 
Unadilla, NY (NAB) 4-35, 4-38 
Union City Dam, Ohio River Basin, PA (ORP) 18-10, 
18-15, 18-21, 18-28 
Union Creek/Stanton Bridge, NE (MRO) 26-23 
Union Lake, MO (LSM) 14-18 
Union River, ME (NED) 1-43 
Union Township Drainage District, MO (NCR) 23-13 
Union Village Dam, VT (NED) 1-16, 1-31, 1-53 
Uniontown, KY (ORL) 16-24, 16-29, 16-34 
Uniontown, PA (ORP) 18-24 
University Wash and Spring Brook, Riverside, CA 
(SPL) 33-32 
Unnamed Creek, Tioga, ND (MRO) 26-23 
Upper Butte Basin, CA (SPK) 35-43 
Upper Gordon Creek, Hattiesburg, MS (SAM) 10-22, 
10-36, 10-47 
Upper Grand River, MO (MRK) 27-17 
Upper Grays River Area, WA (NPP) 37-37 
Upper Iowa River, IA (NCS) 24-24, 24-29 
Upper Jordan River, CA (SPK) 35-34 
Upper Little Arkansas River Watershed, KS (SWT) 
29-30 
Upper Machodoc Creek, VA (NAB) 4-33, 4-38 
Upper Marlboro, MD (NAB) 4-35, 4-38 
Upper Mississippi River Environmental Management 
Program (LSM) 14-7 
Upper Mississippi River - Illinois Navigation Study 
(NCR) 23-3, 23-7 
Upper Mississippi River System Environmental 
Management Program (UMRS-EMP)(NCS) 24-3 
I-68

Upper Mississippi River System Environmental 
Management Program (UMRS-EMP), IL, IA, 
MN, MO, WI (NCR) 23-3, 23-7, 23-9 
Upper Missouri River, SD Streambank Erosion 
Control Project (MRO) 26-17 
Upper Puyallup River, WA (NPS) 38-28 
Upper River Rouge, MI (NCE) 21-85 
Upper White Oak Bayou, TX (SWG) 31-38 
Upper White River, AR (SWL) 28-21 
Upper Zacate Creek, Laredo, TX (SWF) 30-23 
Urban Areas of Alton, IL (LSM) 14-17 
Urbanna Creek, VA (NAO) 5-18 
US Highway 51, Nonconnah Creek, TN (LMM) 13-6 
Utica, IN (ORL) 16-27, 16-31 
Utica, OH (ORH) 17-23, 17-24 
V 
Valdez Harbor, AK (NPA) 40-11 
Valley City Drainage and Levee District, IL (LSM) 
14-17 
Valley Drainage and Levee District, IL (NCR) 23-15 
Van Buren, Arkansas River, AR (SWL) 28-23 
Van Meter, IA (NCR) 23-13, 23-15 
Vanceburg, KY (ORH) 17-21 
Vancouver Lake Area, WA (NPP) 37-38 
Vatia Area, American Samoa (POD) 36-8 
Vaughn, MT, Sun River, Great Falls (MRO) 26-16, 
26-18 
Velva (Bonnes Coulee), ND (NCS) 24-29 
Velva, ND (NCS) 24-24, 24-29 
Ventura Harbor, CA (SPL) 33-5, 33-13, 33-23, 33-31 
Ventura-Pierpoint Area, CA (SPL) 33-29 
Ventura River Basin, CA (SPL) 33-31 
Ventura River Levee (SPL) 33-31 
Verdigris River City Dam, Independence, KS (SWT) 
29-28 
Vermilion Harbor, OH (NCB) 20-10, 20-20, 20-36 
Vermillion River and Tributaries, SD (MRO) 26-17 
Vermillion River Basin, SD (MRO) 26-21 
Vermillion River, Hastings, MN (NCS) 24-24, 24-29 
Vermillion River, Vermillion, SD (MRO) 26-19 
Vernon Branch, Columbus, MS (SAM) 10-51 
Verona (Mouth of Feather River), CA (SPK) 35-40 
Verona Lake, VA (NAB) 4-35 
Veteran's Memorial Levee, Mississippi River, 
Hastings, MN (NCS) 24-24, 24-29 
Vevay, IN (ORL) 16-27, 16-31 
Vicinity of Nehalem, Nehalem River, OR (NPP) 37-39 
Victory Lake, VT (NED) 1-50 
Villa Park Dam (SPL) 33-32 
Village Creek, Birmingham, AL (SAM) 10-22, 10-36, 
10-47 
Village Creek, Jackson and Lawerence Counties, AR 
(SWL) 28-23 
Village Creek, SC (SAN) 7-17 
Village Creek, White River, and Mayberry Levee 
Districts, AR (SWL) 28-23 
Village of New Athens, IL (LSM) 14-17 
Village of Saxtons, VT (NED) 1-47 
Vince and Little Vince Bayous, TX (SWG) 31-16, 
31-21, 31-36 
Vincennes, IN (Partial) (ORL) 16-27 
Vincennes, IN (Uncompleted Portion) (ORL) 16-31 
Vincennes, IN (Wabash River) (ORL) 16-24, 16-29, 
16-34 
Vineyard Haven, MA (NED) 1-43 
Vinton Waterway, LA (LMN) 11-18 
Virginia Beach Canal No. 2, VA (NAO) 5-18 
Virginia Beach, VA (NAO) 5-7, 5-11, 5-15 
Volga, IA (NCR) 23-14 
W 
W. Hickman, Area, Hickman, KY (LMM) 13-6 
W. Kerr Scott Dam and Reservoir, NC (SAW) 6-15, 
6-21 
W.D. Mayo Lock and Dam (14), OK (SWT) 29-26 
Wabash Railroad Bridges, Illinois River, Meredosia, 
and Valley City, IL (LSM) 14-15 
Wabash River, Adams County, IN (ORL) 16-35 
Wabash River Basin (ORL) 16-12, 16-2- 
Wabash River, near Merom, IN (ORL) 16-35 
Wabash River, New Harmony, IN (ORL) 16-36, 
16-37 
Wabash River, Vigo County, County Road 83 West 
(ORL) 16-36 
Wabash River, Vigo County, Little Road (ORL) 16-36 
Wabash River, York Township, Clark County, IL 
(ORL) 16-24 
Wabasha County, Hyw 11, MN (NCS) 24-30 
Wabasha Harbor, MN 25-7 
Wabasha, Mississippi River, MN (NCS) 24-15, 24-20, 
24-30 
Waccamaw River & Seven Creeks, NC & SC (SAW) 
6-28 
I-69

Waccamaw River, NC & SC (SAN) 7-17 
Waco Lake, TX (SWF) 30-10, 30-17, 30-21, 30-23 
Wagoner County, CO (SWT) 29-29 
Wahkiakum County Consolidated Diking District 
No.1, WA (NPP) 37-37 
Wahkiakum County Diking District 4, WA (NPP) 
37-38 
Wahway, South Branch, NJ (NAN) 2-32 
Waianae Small Boat Harbor, Oahu, HI (POD) 36-7 
Waihanau Stream, Molokai, HI (POD) 36-12 
Waikiki Beach, Oahu, HI (POD) 36-8 
Wailele Stream, Oahu, HI (POD) 36-12 
Wailoa Stream and Tributaries, Hawaii, HI (POD) 
36-9 
Waimea Beach, Kauai, HI (POD) 36-11 
Wainwright, AK (NPA) 40-13 
Wake Island Harbor, Wake Island (POD) 36-11 
Waldo Lake Tunnel, OR (NPP) 37-40 
Wallabout Channel, NY (NAN) 2-30 
Wallace Channel, Pamlico Sound, NC (SAW) 6-26 
Wallace Lake, LA (LMK) 12-20, 12-22 
Wallace, WV (ORP) 18-23 
Wallawa River, Weaver Bridge, OR (NPW) 39-16 
Wallis Sands State Beach, Rye, NH (NED) 1-45 
Wallisville Lake, TX (SWG) 31-9 
Walluski River Clatsop County, OR (NPP) 37-37 
Walnut Bottom Run, Beaver Falls, PA (detalied 
project report underway) (ORP) 18-30 
Walnut Creek, CA (SPK) 35-21, 35-30 
Walnut Creek, Purcell, OK (SWT) 29-27 
Walnut River, Cowley County, KS (SWT) 29-28 
Walter F. George Lock and Dam, AL & GA (SAM) 
10-29, 10-37, 10-48 
Wappinger Creek at Pleasant Valley, NY (NAN) 2-32 
Wappinger Creek, NY (NAN) 2-30 
Ware, MA (NED) 1-47, 1-54 
Wareham Harbor, MA (inactive portion) (NED) 1-50 
Wareham Harbor, MA (NED) 1-43 
Wareham-Marion, MA (NED) 1-50 
Warner Road at Sibley Street, Mississippi River, St. 
Paul, MN (NCS), 24-15, 24-20, 24-30 
Warner Road, Mississippi River, St. Paul, MN (NCS) 
24-24, 24-29 
Warren River, RI (NED) 1-43 
Warrenton Diking District 1, Clatsop County, OR 
(NPP) 37-37 
Warrenton Diking District 2, Clatsop County, OR 
(NPP) 37-37 
Warrenton Diking District, OR (NPP) 37-42 
Warrenville Township, Mill Creek, OH (NCB) 20-44 
Warroad Harbor and River, MN (NCS) 24-23, 24-26 
Warroad River and Bulldog Creek, MN (NCS) 24-26 
Warsaw Harbor, IL 25-8 
Warsaw, NY, Oatka Creek (NCB) 20-42 
Warwick Cove, RI (NED) 1-43 
Warwick River (NAB) 4-38 
Warwood, WV (ORP) 18-24 
Washington Aqueduct (NAB) 4-20 
Washington Canal and South River, NJ (NAN) 2-30 
Washington DC and Vicinity (NAB) 4-35, 4-39 
Washington Harbor, DC (NAB) 4-7, 4-23, 4-29 
Washington Island, WI (NCE) 21-84 
Washington, PA (ORP) 18-22 
Washington Street Bridge, Laredo, TX (SWF) 30-23 
Washougal Area Levees, Clark County, OR (NPP) 
37-38 
Wastewater Treatment Pond, Great Miami River, 
Ross, OH (ORL) 16-36 
Water Resources Support Center 47-1 
Water Valley, Eleven Point River, AR & MO (SWL) 
28-23 
Water Works, Park and Pool, Wellsburg, WV 
(construction) (ORP) 18-30 
Waterbury Reservoir Winooski River Basin, VT 
(NAN) 2-32 
Waterbury, VT (NAN) 2-34 
Waterbury-Watertown, CT (NED) 1-47, 1-55 
Wateree River, SC (SAN) 7-17 
Waterford, NY (NAN) 2-34 
Waterloo, IA (Bridges) (NCR) 23-13 
Waterloo, IA (NCR) 23-13, 23-15 
Waterloo, NE (MRO) 26-16, 26-20 
Waterman Creek, Near Sutherland, IA (MRO) 26-21 
Watertown and Vicinity, SD (MRO) 26-21 
Waterway Connecting Pamlico Sound and Beaufort 
Harbor, NC (SAW) 6-9, 6-20, 6-24 
Waterway Connecting Port Townsend and Oak Bay, 
WA (NPS) 38-25, 38-31 
Waterway Connecting Swanquarter Bay with Deep 
Bay, NC (SAW) 6-26 
Waterway from Empire, LA to Gulf of Mexico 
(LMN) 11-16 
Waterway from Indian River Inlet to Rehoboth Bay, 
DE (NAP) 3-25 
Waterway from Intracoastal Waterway to Bayou 
Dulac, LA (LMN) 11-16 
I-70

Waterway From Intracoastal Waterway to Bayou 
Dulac, LA (LMN) 11-13 
Waterway from Little Choptank River to Choptank 
River, MD (NAB) 4-37 
Waterway from White Lake to Pecan Island, LA 
(LMN) 11-16 
Waterway - Norfolk, VA to Sounds of NC (SAW) 
6-26 
Waterway on the Coast of VA (NAO) 5-6, 5-11, 5-15 
Waterways Experiment Station 45-1 
Watkins Glen, NY 1941 FC Act (NCB) 20-45 
Waukegan Harbor, IL (NCC) 22-5, 22-13, 22-17, 
22-19 
Waurika Lake, OK (SWT) 29-10, 29-18, 29-22 
Waverley, WV (ORH) 17-22 
Waycake Creek, NJ (NAN) 2-34 
Webb District Improvement Co, Columbia County, 
OR (NPP) 37-37 
Webber Falls Lock and Dam (16), OK (SWT) 29-26 
Webbers Falls Lock and Dam, OK (SWT) 29-12, 
29-20, 29-23 
Weber River and Tributaries, UT (SPK) 35-40 
Weegie/Pipe Creeks, Shadyside, OH (complete) (ORP) 
18-30 
Weiser River, Cambridge-Midvale (NPW) 39-18 
Weiser River, ID (NPW) 39-16 
Weiser River, Weiser Area, ID (NPW) 39-17, 39-18 
Welles Harbor, Midway Island (POD) 36-7 
Wellfleet Harbor, MA (NED) 1-43 
Wells Harbor, ME (NED) 1-43, 1-58 
Wellsburg, WV (ORP) 18-24 
Wellsville, NY Genesee River (NCB) 20-42 
Wellsville, OH, Section I (ORP) 18-22 
Wellsville, OH, Section II (ORP) 18-22 
Wenatchee, Canyons 1 and 2, WA (NPS) 38-30 
Wenatchie River, WA (NPS) 38-30 
Wessagusset Beach, Weymouth, MA (NED) 1-45 
West Antioch Creek, CA (SPK) 35-44 
West Bank Hurricane Protection Levee, Jefferson 
Parish, LA (LMN) 11-14 
West Branch Chisholm Creek LPP, KS (SWT) 29-24, 
29-27 
West Branch, Indian Creek, Neveda, IA (NCR) 23-16 
West Branch Limestone Creek, Manlius, NY (NCB) 
20-43 
West Branch of Susquehanna River, PA (NAB) 4-18, 
4-31 
West Branch, Papillion Creek, Omaha, NE (MRO) 
26-20 
West Branch, Pebble Creek, Dodge, NE (MRO) 26-23 
West Branch, Westfield River, Huntington, MA 
(NED) 1-47 
West Bridgewater, PA (ORP) 18-24 
West Brookfield Reservoir, MA (NED) 1-50 
West Canaan Lake, NH (NED) 1-50 
West Des Moines, IA (NCR) 23-6, 23-8, 23-10 
West Fork, Blue River, Salem, IN (ORL) 16-37 
West Fork, Des Moines River, MN (NCR) 23-16 
West Fork, Drakes Creek, TN & KY (ORL) 16-24 
West Fork of Mill Creek Lake, OH (ORL) 16-12, 
16-17, 16-24, 16-32 
West Fork River, Clarksburg, PA (detalied project 
report underway) (ORP) 18-30 
West Fork, WV (ORH) 17-23 
West Harbor, OH (NCB) 20-10, 20-20, 20-37 
West Haven Beaches, CT (NED) 1-51 
West Hill Dam, MA (NED) 1-11, 1-29 
West Hill, Worcester, MA (NED) 1-52 
West Little Pine Creek, Etna, PA (ORP) 18-22 
West Makinster Road, Wilson River, OR (NPP) 37-39 
West Matanzas Drainage and Levee District, IL 
(NCR) 23-15 
West Muddy Creek and Mary's River, OR (NPP) 
37-40 
West Nishnabotna River, Mills County Bridge, Near 
Hastings, IA (MRO) 26-21 
West Nishnabotna River, Mills County Bridge, Near 
Malvern, IA (MRO) 26-21 
West Nishnabotna River, Near Hancock, IA (MRO) 
26-21 
West Nishnabotna River, Near Oakland, IA (MRO) 
26-21 
West of Morrilton, Arkansas River, AR (SWL) 28-23 
West Oneonta Lake, NY (NAB) 4-37 
West Point, Chattahoochee River, GA (SAM) 10-50 
West Point Lake, Chattahoochee River Basin, GA and 
FL (SAS) 8-10 
West Point Lake, Chattahoochee River Basin, AL & 
GA (SAM) 10-30, 10-38, 10-48 
West Point, NE (MRO) 26-16, 26-20 
West River, New Haven, CT (NED) 1-22, 1-33, 1-40, 
1-57 
West Springfield, MA (NED) 1-16, 1-31, 1-39, 1-54 
West Terre Haute, IN (Wabash River) (ORL) 16-24, 
16-29, 16-34 
1-71

West Thompson Lake, CT (NED) 1-21, 1-33 
West Union, Middle Island, WV (ORH) 17-24 
West Warren, MA (NED) 1-47, 1-54 
Westchester Creek, NY (NAN) 2-13, 2-20, 2-25, 
2-29, 2-34 
Westcott Cove, CT (NED) 1-43 
Westerly Creek, CO (MRO) 26-5, 26-10(MRO) 26-14 
Westerly, RI (NED) 1-50 
Westfield, MA (NED) 1-50 
Westfield, RI (NED) 1-50 
Westhaven Cove Small Boat Basin, WA (NPS) 38-25 
American Lake, Vicinity of Fort Lewis, WA (NPS) 
38-26 
Westland District Improvement Co., Columbia 
County, OR (NPP) 37-37 
Weston Mills, Olean, NY (ORP) 18-23 
Weston Mils, Portville, NY (ORP) 18-23 
Weston, VT (NED) 1-47, 1-54 
Westpoint, KY (ORL) 16-24, 16-31 
Westport, CT (NED) 1-50 
Westport District Columbia and Clatsop Counties, OR 
(NPP) 37-37 
Westport Harbor and Saugatuck River, CT (NED) 
1-43 
Westport Harbor and Saugatuck River, CT 
(uncompleted portion) (NED) 1-50 
Westport Harbor, Westport, MA (NED) 1-51 
Westport, KY (ORL) 16-27, 16-31 
Westport, OR - Puget Island, WA (NPP) 37-41 
Westport River, MA (NED) 1-50 
Westport Slough, OR (Modification for 32-foot 
channel) (NPP) 37-40 
Westport Slough, OR (NPP) 37-36 
Westville Lake, MA (NED) 1-22, 1-33, 1-57 
Westwego to Harvey Canal, LA (Hurrican protection) 
(LMN) 11-8, 11-11 
Wet Spottedtail Creek, Mitchell, NE (MRO) 26-23 
Weymouth Back River, CT (NED) 1-43 
Weymouth-Fore & Town Rivers, MA (NED) 1-43 
Wharf at Smyrna Landing to fixed bridge (NAP) 3-25, 
3-28 
Whatcom (Nooksack River), WA (NPS) 38-28 
Wheeler Creek, TX (SWF) 30-22 
Wheeling, WV (North Wheeling) (ORP) 18-24 
Wheeling, WV (ORP) 18-24 
Wheeling, WV (Wheeling Island) (ORP) 18-24 
Whelton Ditch, OR (NPP) 37-38 
Whiskey and Rock Creeks, Independence, KS (SWT) 
29-27 
White City Park, OH 1954 R&H Act (NCB) 20-45 
White Lake Harbor, MI (NCE) 21-38, 21-67, 21-82, 
21-90 
White Oak Creek, OH (ORH) 17-23 
White Oak Dike, Bladen and Pender Counties, NC 
(SAW) 6-28 
White River, AR (below Newport) (LMM) 13-5 
White River, at Hwy. 14, 1/4 mile east of Oil Trough, 
AR (SWL) 28-23 
White River Bank Stabilization, Batesville, AR (SWL) 
28-23 
White River Basin (Little Rock District, AR & MO) 
(SWL) 28-9, 28-16, 28-19, 28-30 
White River, Batesville, AR (SWL) 28-10, 28-16 
White River, Elnora, IN (ORL) 16-37 
White River, Franklin County, IN (ORL) 16-37 
White River, Hagerstown, IN (ORL) 16-37 
White River, Hazleton, IN (ORL) 16-37 
White River; IN (ORL) 16-22 
White River, Jacksonport, AR (SWL) 28-23 
White River Jacksonport, AR (SWL) 28-21 
White River, Newport, AR (SWL) 28-23 
White River, Petersburg (Pike County), IN (ORL) 
16-36 
White River, Petersburg, IN (ORL) 16-37 
White River, Road 400W, Pike County, IN (ORL) 
16-37 
White River, St. Paul, AR (SWL) 28-23 
White River, Tripp County Road, SD (MRO) 26-24 
White River, Winner, SD (MRO) 26-19 
Whitebird Creek, ID (NPW) 39-17 
Whitefish Point Harbor, MI (NCE) 21-84 
Whites and Ewing Creeks, TN (ORN) 15-18 
Whitesburg Bridge, Morgan County, AL (ORN) 15-18 
Whitesburg, KY (North Fork, Kentucky River) (ORL) 
16-35 
Whitewater River and Tributaries, IN & OH (ORL) 
16-24 
Whitewater River Basin Floodwarning System, CA 
(SPL) 33-7, 33-14 
Whitewater River, CA (SPL) 33-31 
Whitewater River, Levee Road, near Brookville, IN 
(ORL) 16-36 
Whitings Creek, VA (NAO) 5-18, 5-19 
Whitmanville Lake, MA (NED) 1-47, 1-56 
Whitney Lake, TX (SWF) 30-12, 30-17, 30-21 
I-72

Whitney Point Lake, NY (NAB) 4-15, 4-25 
Whitney Point Village, NY (NAB) 4-16, 4-25 
Whittier, AK (NPA) 40-13 
Whorton's Bend Road, Etowah County, AL (SAM) 
10-50 
Wichita and Valley Center LPP, KS (SWT) 29-24, 
29-27 
Wichita Falls, TX, Plum Creek (SWT) 29-27 
Wichita, KS (SWT) 29-29 
Wickford Harbor, RI (NED) 1-43 
Wicomico River, MD (NAB) 4-8, 4-23, 4-30 
Wiedmer Chemical Drainage and Levee District, MO 
(LSM) 14-18 
Wilcox, PA (ORP) 18-24 
Wild Rice and Marsh Rivers, MN (NCS) 24-28 
Wild Rice River at Mahnomen County, MN (NCS) 
24-29 
Wild Rice River, Hendrum/Lee, MN (NCS) 24-30 
Wild Rice River, Lake Ida, MN (NCS) 24-30, 24-31 
Wild Rice River, South Branch and Felton Ditch, MN 
(NCS) 24-24 
Wildcat and San Pablo Creeks, CA, CA (SPK) 35-22, 
35-30 
Wildcat Creek, CA (SPN) 34-14 
Wiley Creek Lake, OR (NPP) 37-40 
Wilkes-Barre, Hanover Township, PA (NAB) 4-35, 
4-39 
Willamette Falls Fishladder, OR (NPP) 37-40 
Willamette River above Portland and Yamhill River, 
OR (uncompleted portion) (NPP) 37-40 
Willamette River above Portland and Yamhill River, 
OR (NPP) 37-36 
Willamette River at Willamette Falls, OR (NPP) 37-9, 
37-24, 37-32, 37-40, 37-42 
Willamette River Basin Bank Protection, OR (NPP) 
37-14, 37-26, 37-33 
Willamette River Basin Channel Clearing and 
Snagging (NPP) 37-38 
Willamette River, OR (NPP) 37-42 
Willapa River and Harbor and Naselle River, WA 
(NPS) 38-7, 38-16, 38-22 
Willapa River at Raymond, WA (NPS) 38-28 
Wynoochee River, County Road 141, WA (NPS) 
38-28 
Willard Beach, South Portland, ME (NED) 1-45 
William H. Harsha Lake, OH (ORL) 16-12, 16-17, 
16-32 
William L. Springer Lake, Decatur, IL (NCR) 23-14 
Williamson, WV (ORH) 17-21, 17-24 
Williamsport, AK (NPA) 40-13 
Williamsport, PA (NAB) 4-35, 4-38 
Williamstown, WV (ORH) 17-22 
Williamsville Reservoir, VT (NED) 1-50 
Williston, ND Water Intake (MRO) 26-17 
Willoughby Channel, VA (NAO) 5-18, 5-19 
Willow Creek, CA (SPK) 35-43 
Willow Creek, ID (NPW) 39-16 
Willow Creek Lake, Heppner, OR (NPP) 37-15, 
37-26, 37-33 
Willow Creek Lake, OR (NPW) 39-16 
Willow Creek Unit (NPW) 39-17 
Wilmington Harbor, DE (NAP) 3-10, 3-18, 3-23 
Wilmington Harbor, NC (SAW) 6-9, 6-21 
Wilmington Harbor, NC, Passing Lane (SAW) 6-30 
Wilmington Harbor, NC, Turns and Bends (SAW) 
6-30 
Wilmington Harbor Widening and Deepening, NC 
(SAW) 6-29 
Wilmington Ice Control Demonstration (NCC) 22-21 
Wilmore, PA (ORP) 18-22 
Wilson Creek, Sumter County, SC (SAN) 7-18 
Wilson Harbor, OH (NCB) 20-10, 20-20, 20-37 
Wilson Lake, Saline River, KS (MRK) 27-7, 27-12, 
27-16, 27-20 
Wilson Point Harbor, CT (NED) 1-43 
Wilson River, Vicinity Highway 101, OR (NPP) 37-39 
Winchester bay, Umpqua River, OR (NPP) 37-36 
Winfield L&D (ORH) 17-12 
Winfield LPP, KS (SWT) 29-24, 29-29, 29-30 
Winnipesaukee Lake, NH (NED) 1-43 
Winona Harbors, MN 25-7 
Winona, MN (NCS) 24-24, 24-29 
Winooski River, VT (NAN) 2-32 
Winslow (tributaries of Little Colorado River), Little 
Colorado River Basin, AZ (SPL) 33-31 
Winsted, CT (NED) 1-47, 1-54 
Winter Harbor ME (NED) 1-43, 1-58 
Winter Harbor, VA (NAO) 5-18 
Winthrop Beach, MA (NED) 1-45 
Winthrop Beach, MA (uncompleted portion) (NED) 
1-50 
Winthrop Harbor, MA (NED) 1-43, 1-51 
Wisconsin River, WI (NCS) 24-23 
Wishart Point Channel, VA (NAO) 5-18 
Wister Lake, OK (SWL) 28-28 
Wister Lake, OK (SWT) 29-10, 29-18, 29-22, 29-26 
I-73

Withlacoochee River, FL (SAJ) 9-49 
Wolf and Jordan Rivers, MS (SAM) 10-49, 10-52 
Wolf-Coffee Lake, Blue River, KS (MRK) 27-19 
Wolf Creek Dam - Lake Cumberland, Ohio River 
Basin, KY (ORN) 15-7, 15-10 
Wolf Creek, Highway 362 Bridge, Prentiss County, 
MS (SAM) 10-50 
Wolf Creek, LaPorte City, IA (NCR) 23-16 
Wolf Creek, Lawton, OK (SWT) 29-27 
Wolf Creek, U.S. Highway 45 Bridge, Prentiss 
County, MS (SAM) 10-50 
Wolf River (Memphis Harbor), TN (LMM) 13-5 
Wood Island Harbor and the Pool at Biddeford, ME 
(NED) 1-8, 1-28, 1-38, 1-58 
Wood River Drainage and Levee District, IL (LSM) 
14-13, 14-17 
Wood River, Grand Island, NE (MRO) 26-21 
Woodbridge Creek, NJ (NAN) 2-30 
Woodbury Creek, NJ (NAP) 3-25 
Woodcock Creek Lake, Ohio River Basin, PA (ORP) 
18-10, 18-15, 18-21, 18-28 
Woodlands, WV (ORP) 18-24 
Woodmont Beach, Milford, CT (NED) 1-10, 1-28, 
1-38 
Woods Hole Channel, MA (NED) 1-43 
Woodson Drainage District', Columbia County, OR 
(NPP) 37-37 
Woodson Drainage District, OR (NPP) 37-38 
Woonsocket, RI (NED) 1-47 
Woonsocket, RI (NED) 1-53 
Worcester Diversion, MA (NED) 1-47 
Worcester, MA (NED) 1-53 
Worthington, MN (NCR) 23-15 
Wrangell Harbor, AK (NPA) 40-4, 40-8, 40-10 
Wrangell Narrows, AK (NPA) 40-11, 40-13 
Wrangell Narrows Channel (Mile 20), AK (NPA) 
40-13 
Wright Patman Dam and Lake, TX (SWF) 30-10, 
30-17, 30-21 
Wrights Creek, NC (SAW) 6-26 
Wrightsville Beach, NC (SAW) 6-28 
Wrightsville Dam, Winooski River Basin, VT (NAN) 
2-32 
Wynoochee Lake, WA (NPS) 38-10, 38-17 
Wynoochee River, near Montesano, WA (NPS) 38-28 
Wyoming Valley, PA (NAB) 4-35 
Y 
Yadkin River Basin, NC and SC (SAW) 6-14, 6-31 
Yakima County (Yakima River), WA (NPS) 38-28 
Yakima River at Ellensburg, WA (NPS) 38-30 
Yakima River, below mouth of Teanaway River, near 
Cle Elum, WA (NPS) 38-28 
Yakima River, Cle Elum, WA (NPS) 38-28 
Yakima River, Easton, WA (NPS) 38-31 
Yakima River, West Richland, WA (NPS) 38-28 
Yakima River, West Richland, WA (NPW) 39-16 
Yakima River, Yakima, WA (NPS) 38-28 
Yalobusha River, MS (LMK) 12-17 
Yaquina Bay and Harbor, OR (NPP) 37-10, 37-24, 
37-32 
Yaquina Bay and Harbor Small Boat Basin, OR (NPP) 
37-36 
Yaquina River, OR (NPP) 37-36 
Yaquina River, Port of Toledo, OR (NPP) 37-41 
Yatesville Lake, KY (ORH) 17-10, 17-15, 17-19 
Yazoo River, MS (LMK) 12-17 
Yellow Bend Port, AR (LMK) 12-17 
Yellow Jacket Creek, Hogansville, GA (SAM) 10-50 
Yellowstone River, Bank Protection, Billings, MT 
(MRO) 26-19 
Yellowstone River, Glendive, MT (MRO) 26-19 
Yellowstone River, Greycliff Bridge (MRO) 26-19 
Yellowstone River, Highway 89 Bridge, MT (MRO) 
26-24 
Yellowstone River, MT (MRO) 26-24 
Yellowstone River, Near Miles City Water Intake and 
Sewage Lagoon (MRO) 26-19 
Yellowstone River, Reedpoint Bridge (MRO) 26-19 
Yellowstone River, Route 111, Livingstone, MT 
(MRO) 26-24 
Yellowstone River, Springdale Bridge (MRO) 26-19 
Yellowstone River, Voges Bridge, New Big Timber, 
MT (MRO) 26-19 
Yellowstone River, W. Glendive, MT (MRO) 26-16, 
26-18 
Yellowstone River Water Plant, Livingston (MRO) 
26-18 
Yellowstone River, Yellowstone County Bridge, Near 
Billings, MT (MRO) 26-19 
Yolo Basin Wetlands, Sacramento River, CA (SPK) 
35-26 
Yonkers, Nepera Park, NY (NAN) 2-35 
Yonkers, NY (NAN) 2-32 
I-74

York Harbor, ME (NED) 1-44, 1-58 
York, Indian Rock Dam, PA (NAB) 4-19, 4-26, 4-32 
York River, VA (Active portion) (NAO) 5-18 
Yough, Turkeyfoot Township, PA (terminated) (ORP) 
18-30 
Youghiogheny River Lake, Ohio River Basin, PA and 
MD (ORP) 18-11, 18-15, 18-21, 18-28 
Youghiogheny River, PA and MD (Canalization) 
(ORP) 18-24 
Youngs and Claskine River, OR (NPP) 37-36 
Youngs Bay and Youngs River, OR (NPP) 37-36 
Youngs River Dikes, Clatsop County, OR (NPP) 
37-37 
Youngstown, OH (ORP) 18-22 
Z 
Zacate Creek Channel, TX (SWF) 30-22 
Zacate Creek, TX (SWF) 30-22 
Zanesville, OH (ORH) 17-22 
Zippel Bay Harbor, MN (NCS) 24-23 
Zippel Bay, Lake of the Woods County, MN (NCS) 
24-3, 24-18, 24-29 
Zumbro River at Genoa, MN (NCS) 24-16, 24-20, 
24-29 
Zumbro River at Jarrett and Millville, MN (NCS) 
24-25, 24-29 
Zumbro River, MN (NCS) 24-25, 24-29, 24-30 
^ U.S GOVERNMENT PRINTING OFFICE 1993 - 3 5 6 - 5 3 4/ 9 0 0 8 5 
I-75

3 1364 0012767 1

